﻿Fiscal Year 1986
AN 
F 
'kVo 
- I 
TE S A"

FY 1986 STATISTICAL HIGHLIGHTS 
ITEM 
APPROPRIATIONS ($ Millions) 
Navigation .............................. 
Flood Control Total ........................ 
Flood Control 
Mississippi River and Tributaries' .......... 
Multipurpose, including power .............. 
Beach Erosion Control ..................... 
Total New Work
2 
.......................... 
O ther W ork' ............................. 
T O T A L .. ............ .. . ........ 
NAVIGATION (Calendar Year)* 
Ton-Miles of Commerce (Millions) 
Foreign, Coastal Ports ..................... 
Foreign, Great Lakes Ports ................. 
Domestic, Coastal Ilntraterritory not compiled) 
Domestic, Great Lakes ............. ....... . 
Dom estic, Inland ......................... 
D om estic, Local ........................... 
T O T A L ................................ 
Tons of Commerce (Millions) 
Foreign Coastal Ports ...................... 
Foreign Great Lakes Ports .................. 
Domestic, Coastal and Intraterritory ......... 
Domestic, Great Lakes ..................... 
Dom estic. Inland .......................... 
Domestic, Local ............................ 
TOTAL ................................ 
FLOOD DAMAGES PREVENTED ($ Billions) ... 
FLOOD DAMAGES SUSTAINED (S Billions) ..... 
POWER 
Installed (Cumulative in millions of kw) ......... 
Generated (Billions of kwh) .................. 
RESERVOIR STORAGE (Millions of acre-feet) 
A ll Purposes . . ................. .... .. ..... 
Flood Control (Maximum) .... . ..... 
W ater Supply ............................... 
Irrigation .............................. 
PUBLIC ATTI'ENDANCE AT RESERVOIRS 
(Millions of visitor days, calendar years) ........ 
' Included in Flood Control Total 
2 Advance engineering and design, and construction. (Including major rehabilitation projects.) 
Savings and slippage applied to projects. 
' Operation and maintenance, surveys, adminiustration and misc. programs and activities. 
' Includes New Melones and Snettisham, built by the Corps and operated by others. 
1986 1985 1984 1983 1982 1981 1980 1979 1978 1977 
299 304 257 577 552 607 485 395 357 261 
673 676 647 882 774 772 873 802 895 859 
(227) (225) (203) (291) (177) (145) (211) (158) (188) (173) 
93 112 171 221 247 275 538 358 155 464 
17 12 25 5 7 12 9 12 12 16 
1,082 1,104 1,127 1,685 1,580 1.666 1.905 1,567 1,719 1,600 
1,658 1,797 1,561 1,734 1,417 1,331 1,296 1,223 1,070 887 
2,740 2,901 2,688 3,419 2,997 2,997 3.201 2,790 2,789 2,487 
44,769.3 46,509.0 45,287.0 51,262.7 58,929.2 60,569.8 59,940.5 58,925.6 58,925.1 
27,171.9 32,249.3 24,309.4 27,165.5 35,294.0 33,679.6 43,146.4 42,108.8 37,734.3 
610,976.5 593,923.0 649,749.4 632,707.1 634,765.3 631,149.2' 532,290.2 540,373.2 343,536.8 
48,183.9 49,784.4 43,088.1 35,623.3 62,148.4 61,749.1 77,971.9 76,284.0 52,416.9 
232,707.5 242,855.4 225,628.2 217,026.7 231,184.1 227,343.0 217,090.2 209,266.2 201,784.2 
1,102.0 1,157.1 1,099.6 1,111.7 1,315.6 1,596.4 1,710.2 1,339.8 1, d62.3 
964,911.1 966,478.2 989,161.7 964,897.0 1,023,636.5 1,016,085.1 931,846.4 928,297.6 692,527.4 
723.0 744.5 702.7 769.2 823.9 860.8 919.7 875.5 866.1 
51.3 58.7 48.4 50.4 62.3 60.6 73.8 70.6 69.2 
313.2 311.1 312.8 313.9 322.0 333.2 308.7 308.6 251.7 
92.0 98.0 83.5 72.1 115.4 115.2 143.6 142.7 109.1 
534.7 542,5 487.1 495.5 520.7 535.0 535.0 534.5 528.7 
74.2 81.1 73.1 75.6 93.2 94.2 93.1 89.5 83.4 
1,788.4 1,835.9 1,707.6 1,776.7 1,938.4 1,999.0 2,073.9 2,021.4' 1,908.2 
27.3 10.8 16.8 23.2 4.3 1.2 7.3 19.4 6.3 2.6 
6.0 .5 4.0 2.1 1.0 1.8 3.6 1.1 1.5 1.8 
20.0 20.1" 20.1' 19.7' 19.7' 19.2' 19.0' 19.0' 17.9 16.4 
80.7 88.3 91.2 88.2 75.8 77.3 77.8 81.2 83.6 64.0 
273.6 273.6 272.1 270.6 269.0 268.5 263.3 263.3 262.9 252.0 
123.3 123.3 123.0 123.0 123.0 122.7 120.4 120.4 120.1 104.0 
9.5 9.5 9.2 9.2 9.2 9.1 8.9 7.8 7.7 7.6 
7.8 7.8 7.8 7.8 7.8 7.8 7.8 7.8 7.8 7.8 
506 502 482 480 480 469 457 449 439 424 
*For further information on waterborne commerce, see Waterborne Commerce of the United 
States, published annually. It may be obtained by writing the District Engineer, U.S. Army 
Engineer District, New Orleans, P.O. Box 60267, New Orleans, Louisiana 70160. (Note 1986 
navigation figures were not available as of press time, and will be included in the FY 1987 
Annual Report on Civil Works Activities.)

DEPARTMENT OF THE ARMY 
OFFICE OF THE ASSISTANT SECRETARY I WASHINGTON, DC 20310 
7 DEC 1987 
TO: THE PRESIDENT OF THE SENATE 
AND THE SPEAKER OF THE HOUSE OF REPRESENTATIVES 
SUBJECT: Annual Report of the Secretary of the Army on 
Civil Works Activities for FY 1986 
I am submitting Volume II of the Annual Report on 
Civil Works Activities for Fiscal Year 1986 in 
accordance with Section 8 of the Rivers and Harbors Act 
of 1888 and Section 925(b) of the Water Resources 
Development Act of 1986. 
This volume of field reports contains narrative 
summaries and statistics on water resources development 
projects of the Army Corps of Engineers where there has 
been activity between October 1985 and September 1986. 
John S. Doyle, Jr. 
Acting Assistant Secretary of the Army 
(Civil Works)

CONTENTS 
NEW ENGLAND DIVISION ............................................................. 
NORTH ATLANTIC DIVISION: 
N ew York, NY, D istrict...................................................................... 
Philadelphia, PA, District ................................................................... 
Baltimore, MD, District 
N orfolk, VA , D istrict ............... .... .................................................... 
SOUTH ATLANTIC DIVISION: 
W ilm ington, NC, D istrict .................................................................... 
Charleston, SC, D istrict ..................................... ................................ 
Savannah, GA, District ..................................................................... 
Jacksonville, FL, District .................................................................... 
M obile, A L, D istrict ......................................................................... 
LOWER MISSISSIPPI VALLEY DIVISION: 
New Orleans, LA, District ................................................................... 
Vicksburg, MS, District ..................................................................... 
M em phis, TN , D istrict ...................................................................... 
St. Louis, MO, District ...................................................................... 
SOUTHWESTERN DIVISION: 
G alveston, TX, D istrict ...................................................................... 
Forth W orth, TX, District ................................................................... 
Albuquerque, NM , District..................... ............................................. 
Little Rock, AR, D istrict .................................................................... 
Tulsa, O K , D istrict.......................................................................... 
MISSOURI RIVER DIVISION: 
Kansas City, MO, District ................................................................... 
Omaha, NE, District ........................................................................ 
OHIO RIVER DIVISION: 
O hio R iver ................................................................................. 
Nashville, TN, District ....................................................................... 
Louisville, KY, District ...................................................................... 
Huntington, WV, District .................................................................... 
Pittsburgh, PA, District ..................................................................... 
NORTH CENTRAL DIVISION: 
St. Paul, MN, District ....................................................................... 
Rock Island, IL, D istrict ............................................ ....................... 
Mississippi River between Missouri River and Minneapolis, MN ............................... 
Chicago, IL, District ........................................................................ 
Detroit, MI, District ........................................................................ 
Buffalo, NY, District ........................................................................ 
Page 
1-1 
2-1 
3-1 
................ ........... ............. ........ .............. 4 -1 
5-1 
6-1 
7-1 
8-1 
9-1 
10-1 
11-1 
12-1 
13-1 
14-1 
15-1 
16-1 
17-1 
18-1 
19-1 
20-1 
21-1 
22-1 
23-1 
24-1 
25-1 
26-1 
27-1 
28-1 
29-1 
30-1 
31-1 
32-1

SOUTH PACIFIC DIVISION: 
Los Angeles, CA, District .................................................................. 33-1 
San Francisco, CA, District ................................................................ 34-1 
Sacram ento, CA, District ................................................................... 35-1 
PACIFIC OCEAN DIVISION ........................................................... 36-1 
NORTH PACIFIC DIVISION: 
Portland, OR, District...................................................................... 37-1 
Seattle, W A, District ....................................................................... 38-1 
Walla Walla WA, District................................................................... 39-1 
Alaska District ............................................................................ 40-1 
Board of Engineers for Rivers and Harbors.................................................... 41-1 
Mississippi River Commission ................................................................ 42-1 
Natural Disaster Preparedness, Response & Recovery Activities ................................. 43-1 
California Debris Commission ................................................................ 44-1 
Waterways Experiment Station ............................................................... 45-1 
Permanent International Association of Navigation Congresses ................................... 46-1 
Investigations of Projects Under Federal Power Act............................................ 47-1 
Regulatory Sunken Vessel Removal and National Emergency Preparedness ...................... 48-1 
International Boundary Waters Boards ........................................................ 49-1 
Construction Enginering Research Laboratory .................................................. 50-1 
Engineer Topographic Laboratories ........................................................... 51-1 
Cold Regions Research Engineering Laboratory ................................................. 52-1 
Water Resources Support Center ............................................................. 53-1 
APPENDICES: 
Flood Control Reservoirs Operable September 30, 1986 ...................................... A-1 
Flood Control Projects Under Construction During Fiscal Year 1986 .......................... B-1 
Navigation Locks and Dams Operable September 30, 1986 .................................. C-1 
Navigation Projects Under Construction September 30, 1986 ............................... D-1 
Multipurpose Projects Including Power In Operation September 30, 1986 ................ ...... E-1 
Multipurpose Projects Including Power Under Construction September 30, 1986 ................ F-1 
Flood Damages Sustained and Prevented During Fiscal Year 1986 ............................ G-1 
INDEX ........................................................................ I-1

NEW ENGLAND DIVISION * 
The New England Division, an operating division with 
both district and division functions, comprises all of New 
England except western Vermont and small portions of 
Massachusetts and Connecticut along their western 
boundaries, and includes small portions of southeastern 
New York, all embraced in the drainage basins tributary 
to Long Island Sound and the Atlantic Ocean east of the 
New York-Connecticut State line. It also includes Fishers 
Island, NY. 
IMPROVEMENTS 
Navigation Page 
1. Aquatic Plant Control .................... 1-3 
2. Black Rock Harbor, CT .................... 1-3 
3. Bristol Harbor, Bristol, RI ................. 1-3 
4. Cape Cod Canal, MA ....................... 1-3 
5. Connecticut River Below 
Hartford, CT ........................... 1-4 
6. Green Harbor, MA .......................... 1-4 
7. Hampton Harbor, NH ...................... 1-5 
8. Hyannis Harbor, MA ........................ 1-5 
9. Jonesport Harbor, ME ..................... 1-5 
10. Kennebec River, ME ....................... 1-6 
11. Mystic River, MA .......................... 1-6 
12. New Haven Harbor, CT .................... 1-6 
13. New London Harbor, CT ................... 1-7 
14. Newburyport Harbor, MA ................. 1-7 
15. Point Judith Pond and Harbor 
of Refuge, Point Judith, RI ................. 1-7 
16. Rockport and Old Harbors, 
Rockport, M A ................ .............. 1-8 
17. Royal River, ME .......................... 1-8 
18. Saco River, M E ............... ............. 1-9 
19. Reconnaissance and condition 
surveys ..................................... 1-9 
20. Other authorized navigation 
projects .................................... 1-9 
21. Navigation activities pursuant to 
Section 107, Public Law 86-645 
(Preauthorization) .......................... 1-9 
22. Authorized bridge alteration ............... 1-9 
Beach Erosion Control 
23. Lynn-Nahant Beach, MA ................. 1-9 
24. Revere Beach, MA ................. .... 1-10 
25. Inspection of completed beach 
erosion control projects .................. 1-10 
26. Other authorized beach erosion 
control projects ..... ................... 1-10 
27. Beach erosion control activities 
pursuant to Section 103, Public 
Law 87-874 (Preauthorization) .............. 1-10 
Flood Control 
28. Blackstone River Basin, MA and RI .. 
Page 
. 1-10 
28A. Blackstone River, Millbury, MA ............ 1-10 
28B. Clear River, Burrillville, RI ............... 1-10 
28C. Pawtuxet River, Warwick, RI ............. 1-11 
28D. West Hill Dam, MA ....................... 1-11 
28E. Charles River (Natural Valley 
Storage Areas), MA ....................... 1-11 
29. Connecticut River Basin, VT, 
NH, MA and CT .......................... 1-11 
29A. Ball Mountain Lake, VT ................... 1-12 
29B. Barre Falls Dam, MA ..................... 1-12 
29C. Beaver Brook, Keene, NH ................. 1-13 
29D. Birch Hill Dam, MA ...................... 1-13 
29E. Colebrook River Lake, CT .................. 1-13 
29F. Conant Brook Dam, MA .................... 1-13 
29G. Knightville Dam, MA ..................... 1-13 
29H. Littleville Lake, MA ....................... 1-13 
291. Mill Brook, Brownsville, VT ............... 1-14 
29J. North Hartland Lake, VT ................. 1-14 
29K. North Springfield Lake, VT ............... 1-14 
29L. Otter Brook Lake, NH ..................... 1-14 
29M. Park River, Hartford, CT ................. 1-14 
29N. South River, Conway, MA ................. 1-15 
290. Surry Mountain Lake, NH ................ 1-15 
29P. Townshend Lake, VT...................... 1-15 
29Q. Tully Lake, MA ........................... 1-16 
29R. Union Village Dam, VT ................... 1-16 
29S. West Springfield, MA ..................... 1-16 
30. Housatonic River Basin, CT and MA ....... 1-16 
30A. Black Rock Lake, CT ...................... 1-16 
30B. Hancock Brook Lake, CT .................. 1-17 
30C. Hop Brook Lake, CT ....................... 1-17 
30D. Northfield Brook Lake, CT ................ 1-17 
30E. Thomaston Dam, CT ...................... 1-17 
31 Covered Bridge, Housatonic 
River, Sheffield, MA ...................... 1-17 
32. Gulf Street and Trumbull Avenue, 
M ilford, CT ............................... 1-18 
33. Port 5 Facility, Bridgeport, CT ............ 1-18 
1-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Page 
34. Merrimack River Basin, NH and MA ...... 1-18 
34A. Blackwater Dam, NH ..................... 1-18 
34B. Edward MacDowell Lake, NH ............. 1-18 
34C. Franklin Falls Dam, NH .................. 1-19 
34D. Hopkinton-Everett Lakes, NH ............. 1-19 
35. New Bedford, Fairhaven, and 
Acushnet, MA ............................. 1-19 
36. New London, CT .......................... 1-19 
37. Saint John River Basin, ME ............... 1-20 
38. Marginal Way, Ogunquit, ME ............. 1-20 
39. Penobscot River, Old Town, ME ............ 1-20 
40. Pleasant Point, Perry, ME ................. 1-20 
41. Stamford, CT ............................. 1-20 
42. Thames River Basin, CT, RI 
and M A ................................... 1-21 
42A. Buffumville Lake, MA .................... 1-21 
42B. East Brimfield Lake, MA ................. 1-21 
42C. Hodges Village Dam, MA ................. 1-21 
42D. Mansfield Hollow Lake, CT ................ 1-21 
42E. West Thompson Lake, CT ................. 1-22 
42F. Westville Lake, MA ...................... 1-22 
43. Inspection of completed flood 
control projects ............................ 1-22 
44. Flood control reservoir 
operations .................................. 1-22 
45. Hurricane barrier operations .............. 1-23 
46. Other authorized flood 
control projects ............................ 1-23 
47. Flood control work under 
special authorization ...................... 1-23 
48. Deauthorized projects ...................... 1-24 
General Investigations 
49. Surveys ................................... 1-24 
50. Collection and Study of Basic Data ......... 1-24 
Page 
51. 
52. 
Continuation of Planning 
and Engineering ........ .................. 1-24 
Advance Engineering and Design .......... 1-24 
Tables 
Table 1-A Cost & Financial 
Statement ............................ 1-25 
Table 1-B Authorizing Legislation .............. 1-33 
Table 1-C Other Authorized 
Navigation Projects ................... 1-38 
Table 1-D Other Authorized Beach 
Erosion Control Projects ............... 1-42 
Table 1-E Other Authorized 
Flood Control Projects ................ 1-43 
Table 1-F Other Authorized Multiple- 
Purpose Projects including Power ..... 1-44 
Table 1-G Deauthorized Projects ................ 1-45 
Table 1-H Navigation Activities 
Pursuant to Sec. 107 .................. 1-46 
Table 1-I Beach Erosion Activities 
Pursuant to Sec. 103 .................. 1-46 
Table 1-J Flood Control Activities 
Pursuant to Sec. 205 .................. 1-47 
Table 1-K Blackstone River Basin ................ 1-47 
Table 1-L Connecticut River Basin .............. 1-48 
Table 1-M Housatonic River Basin ................ 1-49 
Table 1-N Merrimack River Basin ............... 1-51 
Table 1-0 Thames River Basin .................. 1-52 
Table 1-P Boston Harbor, MA ................... 1-52 
Table 1-Q Reconnaissance and 
Condition Surveys .................... 1-53 
1-2

NEW ENGLAND DIVISION 
Navigation 
1. AQUATIC PLANT CONTROL 
Location. The program is conducted in all navigable 
waters, tributary streams, connecting channels and associated 
waters under the New England Division jurisdiction. 
Existing project. The purpose of the program is to provide 
technical assistance in the eradication or control of 
aquatic plants that are causing or have the potential to 
cause major economic problems in the above waterways. 
The plant control is done in the interest of navigation, 
flood control, drainage, agriculture, fish and wildlife conservation, 
public health and research. The program is 
administered by the Chief of Engineers, under the direction 
of the Secretary of the Army, and in cooperation with 
other Federal and State agencies. (See Table 1-B at end of 
chapter for Acts authorizing existing program). 
Local cooperation. Local interests must contribute 30 
percent of the cost of controlling the aquatic plants, and in 
addition must hold the United States free from damages 
that may occur from control operations. 
Operations during fiscal year. Surveys were made in 
each of the six New England States to determine: State 
level programs; the relationships of the Aquatic Plant 
Control Program and extent of specific needs. As a result 
of these surveys the program has been directed toward 
technical assistance activities upon request. We continue 
to work closely with the States. 
2. BLACK ROCK HARBOR, CT 
Location. On north shore of Long Island, about 51 miles 
east of New York City. (See National Ocean Survey Chart 
12369). 
Existing project. Black Rock Harbor and Cedar Creek 
Channel, 18 feet deep and 100 to 200 feet wide from the 18 
foot contour in Black Rock Harbor to the heads of both 
branches of Cedar Creek, about 2.4 miles. (See Table 1-B 
at end of chapter for Act authorizing existing project). 
Local cooperation. Fully complied with for completed 
portion of project; for Black Rock Harbor breakwaters 
and Burr and Cedar Creek anchorage there is no reasonable 
prospect that required cooperation will be forthcoming 
from local interests. For further details see Annual 
Report for 1968. 
Terminal facilities. There are 6 waterfront facilities 
serving Black Rock Harbor. Facilities are adequate for 
existing commerce. 
Operations during fiscal year. Maintenance: In conjunction 
with Field Verification Program, $23,000 was 
expended to extend existing lease of land. 
3. BRISTOL HARBOR, BRISTOL, RI 
Location. Bristol Harbor is on the east side of upper 
Narragansett Bay, in Bristol County, about 13 miles southeast 
of Providence, Rhode Island. (See National Ocean 
Survey Charts 13224, 13221 and 13218). 
Existing project. The project provides for an offshore 
breakwater 1,600 feet long located about 400 feet west of 
the Coast Guard pier and extending generally in a northwesterly 
direction. Construction has not begun. Revised 
plan developed during advance engineering and design 
recommends an A-frame type breakwater 1,250 feet long. 
Total estimated cost (June 1986) of the modified plan is 
$4,600,000 of which $1,996,000 is non-Federal cost. (See 
Table 1-B at end of chapter for Act authorizing existing 
project). 
Local cooperation. Local interests are required to 
provide, without cost to the United States, all lands, easements 
and rights-of-way necessary for construction; hold 
and save the United States free from damages due to 
construction and subsequent maintenance of the project 
and provide a cash contribution currently estimated at 50 
percent of project cost based on project benefits. 
Terminal facilities. The developed waterfront of Bristol 
Harbor is concentrated along a half-mile stretch of east 
shore of harbor. In this section, there are six privately 
owned landings, two owned by the town, one by the State, 
and one by the Federal government. All private landings 
are of granite construction and have truck access. Two 
have gasoline and one has diesel oil service; and are used 
primarily for landing shellfish. Town and State piers are 
open to public, and include facilities for about 50 small 
boats and finger piers for larger craft. 
Operations during fiscal year. New work: Continuing 
General Design activity focused mainly on the project's 
economic analysis and in particular a detailed review of 
project benefits. This review determined that earlier 
projected commercial benefits are no longer applicable 
and that benefits expected to be realized from the project 
are almost entirely recreational in nature. Further, the 
estimated annual benefits are now less than the estimated 
annual costs, resulting in a benefit-to-cost ratio of less 
than one. The town of Bristol was informed of this development 
and of our intention to cease further activity and to 
recommend that the project be placed in an inactive 
status. 
4. CAPE COD CANAL, MA 
Location. This waterway is a sea level canal; extending 
from head of Buzzards Bay, MA, to a point on Cape Cod 
Bay about 15 miles southeast of Plymouth Harbor, MA. In 
general direction canal trends from Buzzards Bay easterly 
to Cape Cod Bay. (See National Ocean Survey Chart 
13246). 
Existing project. For description of existing project 
see Annual Report for 1975. (See Table 1-B at end of 
chapter for Acts authorizing existing project). Navigational 
improvements were completed in April 1963, with 
completion of East Boat Basin extension. Initial recreational 
development consists of public use facilities at 
various locations, which were completed in February 
1965. Improvements to public use facilities at the East 
Boat Basin were completed in May 1974. Construction of 
public use facilities at Bourne Scenic Park were completed 
in May 1976. Canal is crossed by two high-level 
highway bridges and a vertical-lift railroad bridge. 
Initial major rehabilitation of Bourne Highway Bridge 
was completed in December 1965. Minor rehabilitation of 
stone breakwater was completed in October 1963. 
1-3

- REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Local cooperation. Fully complied with. Local interests 
must also bear 50 percent of future recreational 
development in accordance with 1965 Federal Water 
Project Recreation Act. 
Terminal facilities. There are seven terminals on the 
canal, of which three are privately owned. Four are used 
for receipt and freezing of fish and two are used for 
receipt and storage of oil. Seventh terminal is State pier, 
owned by Commonwealth of Massachusetts, and on north 
bank of canal at Bourne Neck. Terminals are adequate for 
purposes for which they are used. 
Operations during fiscal year. Maintenance: A continuing 
contract, awarded last fiscal year, for rehabilitation 
of the Sandwich Bulkhead was completed in September 
1986 with $1,521,000 expended this fiscal year. A contract 
for installation of suspension cables and other repair work 
on the Bourne and Sagamore Bridges was awarded in 
January 1986 and was 65 percent complete ending the 
fiscal year. Contract payments of $1,111,000 were made in 
fiscal year 1986. Contracts awarded and completed in 
fiscal year 1986 were: purchase of suspension cables for 
Bourne Bridge $197,000; purchase of riprap stone for 
canal banks $50,000; architectural engineering contract 
to prepare plans and specifications for rehabilitation of 
railroad bridge $218,000. Other fiscal year 1986 costs for 
work accomplished by hired labor and contract were: 
resource management facilities, including operating 
equipment $35,000; replacement parts for the computerized 
electronic traffic control system $27,000; repairs to 
project vessels $36,000; replacement of project maintenance 
equipment $31,000; engineering and design 90,000; 
supervision and administration of contracts $150,000; 
operation and maintenance of railroad bridge, tower and 
signal system $102,000; vessel traffic control activities 
$745,000; operation of recreation areas $315,000; supervision 
and administration by Division office $223,000; 
condition surveys $35,000; real estate activities $67,000 
and operational costs for roads, bridges and project 
facilities $1,043,000. 
5. CONNECTICUT RIVER BELOW 
HARTFORD, CT 
Location. Has its source in Connecticut Lake in northern 
New Hampshire, flows southerly 380 miles and 
empties into Long Island Sound at Saybrook, CT, 14 miles 
west of New London. Hartford, now head of commercial 
navigation, is 52 statute miles, by channel, from mouth. 
(See National Ocean Survey Charts 12373 and 12377). 
Previous project. For details see Annual Reports for 
1915 and 1938. 
Eightmile River, CT, elimination as separate project: 
Provides for a channel 8 feet deep and 75 feet wide from 
deep water in Connecticut River to Hamburg and for 
turning basin of same depth, 150 feet wide, approximately 
300 feet long at Hamburg. Project was adopted by River 
and Harbor Act of 1910. Costs and expenditures were 
$9,000 all for new work. In accordance with River and 
Harbor Act of 1950, project for Connecticut River below 
Hartford was modified to include project for Eightmile 
River. Aforementioned Act also provided for an anchorage 
basin 6 feet deep and about 6.5 acres in area in upper 
cove in Hamburg. A channel 15 feet deep and 150 feet 
wide for a distance of 52 miles upstream to Hartford; two 
riprap jetties at the mouth of the river; and dikes, training 
walls, revetments and other regulatory works along the 
river between Hartford and Gildersleeve Island. The 
project provides for small-boat improvements at Wethersfield 
Cove; Eightmile River; Essex; and North Cove, Old 
Saybrook. For a more detailed description of project see 
page 7 of Annual Report for 1974. (See Table 1-B at end of 
chapter for Acts authorizing existing project). Existing 
project was completed in September 1965 with the construction 
of channel and anchorage in North Cove, Old 
Saybrook, CT. For further details, see Annual Report for 
1974. 
Local cooperation. Fully complied with. 
Terminal Facilities. Along both Connecticut and Eightmile 
Rivers there are two or three wharves at each river 
town, one or more in each town being open to public use. 
At Hartford and Middletown there is about one-half of 
wharf frontage along west bank of river. Facilities are 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Scheduled 
maintenance dredging was deferred due to insignificant 
shoaling. A contract for maintenance dredging of 
the entrance to Wethersfield Cove was awarded in June 
1986. Work had not started at close of fiscal year. Hired 
labor costs of $44,881 were incurred for check surveys, 
sampling and testing, preparation of plans and specifications 
and an environmental assessment. 
6. GREEN HARBOR, MA 
Location. On west side of Massachusetts Bay within the 
town of Marshfield about 30 miles southeast of Boston and 
9 miles north of Plymouth Harbor. (See National Ocean 
Survey Chart 13253). 
Existing project. Provides for channel 6 feet deep (8 
feet at entrance), 100 feet wide extending about 4,000 feet 
from deep water to head of navigation with small turning 
basin at upstream limit; 5-acre anchorage near Town 
Pier, 6 feet deep; sealing, rebuilding in part, and a 200 
feet extension of existing west jetty at elevation +12, with 
dike to beach berm at elevation +14 feet, and raising east 
jetty to elevation +14. (See Table 1-B at end of chapter for 
Act authorizing existing project). Construction was completed 
in October, 1969. 
Local cooperation. Fully complied with. 
Terminal facilities. Major terminal facility is Town 
Pier in village of Brant Rock. Facility is a bulkheaded, 
earth-filled landing and parking area about 290 feet wide, 
extending 210 feet into harbor. A marina service is south 
of Town Pier; and a facility for recreational craft has been 
developed on south side of harbor near head of navigation. 
Operations during fiscal year. Maintenance: Work 
under a maintenance contract in progress in October 
continued through the month. A total of 30,000 cubic 
yards of material was removed from the entrance channel 
at a cost of $114,600. The contract was terminated in fiscal 
year 1986 for default when the contractor failed to return 
in the spring to complete the work. Advertisement for 
bids to remove two limited shoal areas produced no 
1-4

NEW ENGLAND DIVISION 
qualified bidders. Hired labor costs of $44,034 were incurred 
for preparation of an environmental assessment, 
plans and specifications, surveys and supervision and 
inspection associated with the dredging. Additional hired 
labor costs of $13,871 were incurred for analysis of alternatives 
and preparation of a report on entrance area modifications 
by the Waterways Experiment Station. 
7. HAMPTON HARBOR, NH 
Location. On New Hampshire seacoast 13 miles south 
of Portsmouth Harbor, 5 miles north of mouth of Merrimack 
River at Newburyport, MA. (See National Ocean 
Survey Chart 13278). 
Existing project. Extending north jetty 1,000 feet, 
raising outer 300 feet of south jetty and constructing a 
180-foot spur to high ground, and dredging to provide a 
channel 8 feet deep and 150 feet wide across entrance bar. 
(See Table 1-B at end of chapter for Act authorizing existing 
project). Project was completed in November 1965. 
Local cooperation. Fully complied with. 
Terminal facilities. There are seven piers in Hampton 
Harbor. State of New Hampshire maintains three pile 
and timber piers, two in Hampton about 1,500 feet north 
of entrance and one in Seabrook one-half mile south of 
entrance. Hampton pier has a 6-foot walkway to a float 
that has depths of 4 to 6 feet. Seabrook pier has a float and 
a water depth of about 3 feet at outer end. One landing is 
open to public. Facilities are adequate for existing commerce. 
Operations during fiscal year. Maintenance: Maintenance 
dredging planned for this fiscal year was deferred 
due to funding limitations. Hired labor costs of $3,587 
were incurred for a utilization survey and preparation of 
an environmental assessment. 
8. HYANNIS HARBOR, MA 
Location. On south shore of Cape Cod about 16 miles 
west of Chatham, Massachusetts and 20 miles northeast of 
Vineyard Haven, Massachusetts. (See National Ocean 
Survey Chart 13237). 
Existing project. A stone breakwater 1,170 feet long, 
lying about 0.7 mile off shore, dredging to 15.5 feet deep in 
protected area behind breakwater; a channel 12 feet deep 
with widths of 150 and 100 feet in outer and inner harbors 
respectively, an anchorage area 12 feet deep and and 
about 5 acres in area adjacent to inner harbor channel 
north of Harbor Bluff; and a riprap jetty 1,000 feet long 
extending south from Dunbar Point. Mean spring tidal 
ranges in outer harbor 3.1 and 3.7 feet, respectively. 
Breakwater was completed in 1882 and dredging behind 
breakwater in 1906. Rehabilitation was necessary to 
restore breakwater to its designed purpose of providing a 
harbor of refuge. Restoration was completed in November 
1961. Construction of 12-foot channel and anchorage was 
initiated in May and completed in November 1959. 
Commonwealth of Massachusetts constructed the jetty 
extending south from Dunbar Point in 1962. (See Table 
1-B at end of chapter for Acts authorizing existing 
project). 
Local cooperation. Fully complied with. 
Terminal facilities. There are two town wharves in the 
inner harbor. One has a bulkhead frontage of about 800 
feet. Other private landings are available. Facilities are 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Payment 
of an additional $6,282 was made on the maintenance 
dredging contract awarded last fiscal year. The contract 
was not closed out at the end of the fiscal year pending 
resolution of claims. Hired labor costs of $10,008 were 
incurred for supervision and inspection associated with 
the contract claim and for work on an environmental 
assessment. 
9. JONESPORT HARBOR, ME 
Location. Jonesport Harbor is situated on the north 
side of Moosabec Reach in Washington County, Maine 
about 190 miles northeast of Portland, Maine, and about 
40 miles southwest of the Canadian border at Eastport, 
Maine. 
Existing project. Provides for a combined rubble 
mound and cellular steel sheet pile breakwater, 1,200 feet 
in length; a 15-acre anchorage composed of 9 acres, 6 feet 
deep, and 6 acres, 8 feet deep; and an entrance channel 
100 feet wide and 8 feet deep. Latest approved cost 
estimate (October 1985) is $9,520,000. (See Table 1-B at 
end of chapter for Act authorizing existing project). 
Local cooperation. Consistent with the cost sharing 
and financing concepts agreed to by the Administration 
and the Senate majority leadership, local interests are 
required to provide without cost to the United States, all 
lands, easements, and rights-of-way required for construction 
and subsequent maintenance of the project and for 
aids to navigation upon the request of the Chief of 
Engineers, including suitable areas determined by the 
Chief of Engineers to be required in the general public 
interest for initial and subsequent disposal of spoil, and 
also necessary retaining dikes, bulkheads, and embankments 
therefor or the costs of such retaining works; hold 
and save the United States free from damages that may 
result from the construction and maintenance of the 
project; provide, maintain, and operate necessary mooring 
facilities and utilities including a public landing in 
Sawyer Cove with berthing depths alongside the landing 
commensurate with the depth provided in the entrance 
channel and including an adequate access road, parking 
area, and suitable related facilities open to all on equal 
terms, including transients; accomplish without cost to 
the United States such utility or other relocations or 
alterations as necessary for project purposes; reserve 
spaces within the harbor adequate for the accommodation 
of transient craft; regulate the use, growth, and free 
development of the harbor facilities with the understanding 
that said facilities will be open to all on equal terms, 
including transients; establish regulations prohibiting discharge 
of pollutants into the waters of Jonesport Harbor 
by users thereof, which regulations shall be in accordance 
with applicable laws or regulations of Federal, State, and 
local authorities responsible for pollution prevention and 
1-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
control; pay 10 percent of project cost during construction; 
and pay an additional 10 percent of project costs within a 
period of 30 years following completion. 
Terminal facilities. There are thirteen privately owned 
wharves in the harbor, twelve of which are used by local 
fishermen and one which is used for receiving about three 
million gallons of petroleum annually. 
Operations during fiscal year. New work: All preconstruction 
planning and design activity was completed, 
including the preparation of contract plans and specifications. 
A Local Cooperation Agreement (LCA) was 
signed by both the local sponsors and the department of 
the Army. At year end local interests were pursuing 
means of financing their share of project construction. 
10. KENNEBEC RIVER, ME 
Location. Drains a large number of lakes and minor 
streams, and flows from Moosehead Lake about 150 miles 
southerly and discharges into Atlantic Ocean about 25 
miles east of Portland. (See National Ocean Survey Chart 
13298). 
Previous projects. For details see Annual Reports for 
1915 and 1938. 
Existing project. A channel 27 feet deep and not less 
than 500 feet wide, extending from mouth to bridge at 
Bath; thence to Gardiner a channel not less than 150 feet 
wide, 17 feet deep at Beef Rock Shoal, at foot of Swan 
Island, 18 feet deep through rock at Lovejoy Narrows, 
near head of Swan Island, decreasing to 16 feet deep at 
Gardiner; channel west of Swan Island, 100 feet wide, 12 
feet deep, except at upper shoal, where depth was to be 15 
feet; and channel 125 feet wide and 11 feet deep from 
Gardiner upstream to Augusta at head of navigation. 
Section of river included in project is about 44 miles long. 
Work includes dredging, rock excavation, and two riprap 
training walls. Portion of project for dredging 27-foot 
channel from Bath Iron Works Corp. to 0.6 of a mile above 
bridge at Bath is considered inactive. Estimated cost 
(1954) of this portion is $129,500. (See Table 1-B at end of 
chapter for Acts authorizing existing project). 
Local cooperation. None required. 
Terminal facilities. Wharves suitable for landing or 
loading are at Bath, Woolwich, Richmond, Randolph, 
Gardiner, Hallowell, and Augusta. Of the 24 wharves at 
Bath, 5 are publicly owned and 19 privately owned; about 
one-third are in poor repair and little used. Rail connections 
are available at 19 wharves at Bath. Depths alongside 
range from 12 to 25 feet. At other points named above 
there are 16 wharves in usable condition. All but one are 
equipped with mechanism for handling passengers and 
freight. Those open to the public on equal terms are two at 
Hallowell and one each at Randolph and Augusta. None 
are publicly owned. Facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. Maintenance: Dredging 
of the Doubling Point Reach was accomplished in late 
September 1986 by the Government hopper dredge MCFARLAND 
at a rental cost of $349,999. Approximately 
57,902 cubic yards of material was removed, restoring the 
Reach to 27.0 feet below mean low water. Hired labor 
costs of $15,092 were incurred for progress surveys and 
supervision and inspection. 
11. MYSTIC RIVER, MA 
Location. Rises in Mystic Lake, MA, flows southeasterly 
7 miles and empties into Boston Harbor near Boston 
Naval Shipyard. (See National Ocean Survey Chart 
13272). 
Previous projects. For details see page 1743 of Annual 
Report 1915, and page 59 of Annual Report for 1938. 
Existing project. Channel 35 feet deep, extending from 
limit of 35-foot channel of Boston Harbor at Mystic River 
Bridge to approximately 300 feet downstream of Malden 
Bridge, having width varying from about 940 feet at its 
lower end, to about 1,060 feet at a point about 1,200 feet 
below the Malden Bridge, thence decreasing to 150 feet at 
its upper limit; channel 20 feet deep from head of existing 
35-foot channel to a point 800 feet above Malden Bridge, 
with widths decreasing from 150 feet at lower end to 75 
feet through drawspan, thence increasing to about 340 
feet to form turning basin above bridge; channel 6 feet 
deep and 100 feet wide from Boston & Maine Railroad 
(western division) Bridge to about 2,500 feet above Wellington 
Bridge, about 1 mile, and thence 4 feet deep, gradually 
narrowing from 100 to 50 feet at upper end for about 2 
miles to head of commercial navigation at Craddock 
Bridge in Medford. Project depths refer to mean low 
water. Mean range of tide is 9.6 feet at Mystic River 
Bridge, 9.6 feet at Wellington Bridge, and 9.3 feet at 
Craddock Bridge. Extreme range is 13.7 feet. Project was 
completed in June 1958. (See Table 1-B at end of chapter 
for Acts authorizing existing project). 
Local cooperation. None required. 
Terminal facilities. In section of river benefited by 35- 
foot channel project there are on the south bank four 
wharves consisting of substantial stone or wooden bulkheads 
filled solid, aggregating over 4,000 feet of berthing 
space; also a lumber terminal, the largest of its kind on the 
Atlantic Coast, equipped with most modern mechanical 
appliances, has railroad connections and occupies 4,400 
feet of waterfront. On north bank of river there is a large 
wharf used for receipt and shipment of oil on extensive 
scale; and adjacent thereto an extensive terminal used in 
connection with an iron works. There are several other 
wharves downstream of Malden Bridge and on west bank 
of Island End River used for receipt and shipment of coal, 
coke, tar, oil and in connection with a generating plant. 
None of the above is publicly owned or opened to general 
public use. In 20-foot channel section on south bank there 
are 1,850 feet and on north bank 1,235 feet of available 
dockage; none of which is publicly owned, two are open to 
public on payment of charges. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Incidental 
hired labor costs of $792 were incurred for finalizing 
and administrating the deobligation of funds from a prior 
fiscal year contract for sediment testing. 
12. NEW HAVEN HARBOR, CT 
Location. On north shore of Long Island Sound, about 
75 miles east of New York City. (See National Ocean 
Survey Chart 12371). 
Previous project. For details, see Annual Report for 
1915 and 1938. 
1-6

NEW ENGLAND DIVISION 
Existing project. For description of existing project 
see Annual Report for 1978. (See Table 1-B at end of 
chapter for Acts authorizing existing project). Project is 
complete. 
Local cooperation. Fully compiled with. 
Terminal facilities. Port of New Haven is served by 53 
waterfront facilities; 40 are within city limits of New 
Haven, and 5 in West Haven. Improved waterways within 
port area along which facilities are located include West 
River, Main Harbor, West and East Branches of Mill 
River, and Quinnipiac River channels. Facilities are all 
privately owned and operated with exception of city 
wharf and U.S. Coast Guard wharf. Depths alongside 
piers and wharves range from 35 to zero feet at mean low 
water. Nearly half of the facilities have rail connections 
and most are accessible by paved streets. Nineteen 
wharves have mechanical handling facilities, six wharves 
are open to public use upon agreement with the owners. 
Facilities are adequate for existing commerce. (For further 
details see Port and Terminal Facilities of Southern 
New England No. 4, revised 1983). 
Operations during fiscal year. Maintenance: Funds 
from a prior fiscal year contract for sediment testing were 
deobligated. 
13. NEW LONDON HARBOR, CT 
Location. On the north shore of Long Island, at its 
eastern end and about 14 miles east of the mouth of the 
Connecticut River. (See National Ocean Survey Chart 
13213). 
Previous projects. Adopted by River and Harbor Acts 
of June 14, 1880, March 3, 1881, and July 13, 1892. For 
further details see Annual Reports for 1915 and 1938, 
pages 1753 and 116, respectively. 
Existing project. For description of existing project 
and authorizing legislation see Annual Report for 1978. 
Project was completed in 1938. The Department of the 
Navy has twice deepened extensive lengths of the harbor 
in the interest of the National Defense. In May 1980 they 
completed their second effort. The Corps, at request of the 
Department of the Navy is currently maintaining these 
deeper depths within width limits of the authorized Corps' 
project. 
Local cooperation. Fully complied with for completed 
work; for new work, local interests are required to provide 
easements and rights-of-way required for construction 
and subsequent maintenance of the project; hold and save 
the United States free from damages due to construction 
of the project; make such alterations to underwater utilities 
as necessary to enable full realization of the project 
benefits; and improve berth and access channels commensurate 
with the project depth. 
Terminal facilities. There are 36 wharves and piers in 
a developed frontage of about 3 miles. Seven piers are 
owned by the Federal Government of which five are being 
used. One pier is owned by the State and one by the city. 
Eight waterfront facilities are equipped to receive petroleum 
products. Seven of the wharves have direct rail 
connections. The total available berthage space is about 
27,000 feet. (For further details, see Port and Terminal 
Facilities at the Ports of Southern New England, 1983). 
1-7 
Operations during fiscal year. Maintenance: A maintenance 
dredging contract of the 36-foot channel was 
awarded in December 1985 and work was completed in 
February 1986. A total of 331,400 cubic yards of material 
was removed. Contract costs of $443,503 were paid by the 
Corps of Engineers and Contributed Funds of $517,557 
were provided by the Navy for a total contract of $961,060. 
Hired labor costs of $111,562 were incurred for preparation 
of plans and specifications, supervision and inspection 
and surveys. 
14. NEWBURYPORT HARBOR, MA 
Location. On south bank of Merrimack River, about 2.5 
miles above mouth, and about 48 miles by water north of 
Boston. (See National Ocean Survey Chart 13282). 
Existing project. Two jetties, one projecting 4,118 feet 
from the north shore, the other projecting 2,445 feet from 
the south shore, converging until 1,000 feet apart, then 
extending seaward 1,000 feet parallel to axis of channel; 
partially closing Plum Island Basin by a timber dike; 
channel 12 feet deep and 400 feet wide through bar, 
thence 9 feet deep and 200 feet wide to and including a 
widened turning basin in front of wharves. Portion of 
project for continuous channel from sea to wharves at 
Newburyport, 15 feet deep and 200 feet wide to and 
including a widened turning basin in front of wharves is 
considered inactive. Estimated cost of this portion (June 
1955) is $106,000. (See Table 1-B at end of chapter for 
Acts authorizing existing project). Existing project except 
for inactive portion was completed in August 1958, 
with the improvement of 12-foot channel and outer 
harbor. North jetty was completed in 1914; south jetty was 
completed, except for a length of about 30 feet at its outer 
end, in 1905. Required rehabilitation in these jetties 
completed in September 1970. Plum Island Basin was 
partially closed in 1883 by construction of a timber dike. 
North Rock was removed in 1901. 
Local cooperation. Fully complied with. 
Terminal facilities. Twenty wharves extending along a 
frontage of about 3,500 feet of south bank of Merrimack 
River below highway bridge and one small pier on north 
side of river. Terminal facilities are adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Hired 
labor costs of $6,850 were incurred for work on an environmental 
assessment. 
15. POINT JUDITH POND 
AND HARBOR OF REFUGE, 
POINT JUDITH, RI 
Location. Point Judith marks southwestern entrance to 
Narragansett Bay. Harbor lies in shallow bight west of 
point, about 14 miles southwest of Newport Harbor, RI, 
and 33 miles east of New London Harbor, CT. Point 
Judith Pond is a shallow salt pond, with a length north 
and south of about 4 miles, lying in rear of sandy beach of 
Rhode Island shore, just west of Point Judith Harbor by a 
narrow opening through sand dunes. (See National Ocean 
Survey Charts 13218 and 13219). 
Previous project. For details see Annual Report for 
1948.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Existing project. For description of existing project 
see Annual Report for 1977. (See Table 1-B at end of 
chapter for Acts authorizing existing project). All work 
for project authorized prior to 1949 was completed in 
1950. Breakwaters were completed in 1914 and dredging 
of shoals in project area was done in 1921. Main and east 
shore arm breakwater had deteriorated and required 
restoration to project design. In 1962 reconstruction of 
east arm breakwater and main breakwater dock facilities 
were completed. Rehabilitation required for remainder of 
breakwater restoration was completed in October 1963. 
The extension of the 15-foot channel was completed in 
April 1977. 
Local cooperation. Fully complied with. 
Terminal facilities. Consist of one town wharf of steel 
sheetpile bulkhead construction which comprises southern 
and eastern limits of basin. Total docking space 
amounts to 500 feet. No mechanical handling facilities are 
available. Wharf is owned by the town and open to the 
public. State of Rhode Island maintains two State piers, 
one in Galilee and one in Jerusalem, each having about 
500 feet of berthing space. A facility comprising a bulkhead 
with 15 finger piers projecting channelward there 
from provides berthing space of about 4,000 linear feet. 
This facility is used for receipt of fish and fish products 
for dehydrating purposes. Mechanical handling facilities 
including fish pumps, are available for discharge of 
cargo. In addition, there are approximately 10 small 
privately owned wharves used in the fishing business and 
passenger traffic. Facilities are adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: A payment 
of $393,999 was made to the contractor relative to 
contract for breakwater repairs which was terminated 
last fiscal year. Hired labor costs of $3,540 were incurred 
for testing and $27,725 for supervision and inspection 
relating to contract claims. Further payments, if any, are 
pending results of audit. 
16. ROCKPORT AND OLD HARBORS, 
ROCKPORT, MA 
Location. The town of Rockport is located on the seaward 
end of Cape Ann on the northeast Massachusetts 
coast about 35 miles north of Boston. The town is bordered 
by the city of Gloucester to the west, Essex Bay to the 
north, Massachusetts Bay to the south, and Sandy Bay to 
the east. (See National Ocean Survey Charts 13278 and 
13279). 
Existing project. Rebuilding the two breakwaters at 
entrance of harbor with rubblestone to a height of 18.5 
feet and removing the principal rocks in the harbor. This 
work was completed in 1905. Current modification: An 
access channel -10 feet deep at mean low water (MLW) by 
80 feet wide, leading from deep water outside the existing 
Federal breakwaters 1,100 feet to the town wharf at the 
center of the harbor. At the wharf the 10-foot channel 
branches to form two 40-foot-wide channels leading to the 
north and south iner anchorage basins which are separated 
by the wharf. The North Basin would have an area 
of 1.7 acres and a depth of -8 feet MLW. The South Basin 
would have an area of 1.3 acres and a depth of -8 feet 
MLW. Two additional outer harbor anchorages, both 8 
feet deep at MLW would be located along the 80-foot-wide 
access channel between the breakwaters and the town 
wharf. 
The plan of improvement developed for Pigeon Cove 
consists of a 75-foot-wide channel -10 feet deep MLW 
extending from deep water outside the breakwater 550 
feet across the southeast end of the cove to the public pier 
and offloading facilities. An anchorage area north of the 
channel would be dredged to -8 feet deep MLW. (See 
Table 1-B at the end of chapter for Acts authorizing 
project.) 
Local cooperation. For the current modification: contribute 
in cash, prior to construction, 3.3 percent of the 
first cost of construction; provide, maintain and operate 
without cost to the United States, an adequate public 
landing with provisions for the sale of motor fuel, lubricants 
and potable water open and available to the use of 
all on equal terms; provide without cost to the United 
States all necessary lands, easements and rights-of-way; 
hold and save the United States free from damages that 
may result from construction, operation, and maintenance 
of the project, except for damages due to the fault or 
negligence of the United States or its contractors; accomplish 
without cost to the United States alterations and 
relocations as required in sewer, water supply, drainage 
and other utility facilities; provide and maintain mooring 
facilities as needed for transient and local vessels as well 
as necessary access roads, parking areas and other needed 
public-use shore facilities; assume full responsibility for 
all project costs in excess of the Federal statutory cost 
limitations; establish regulations prohibiting the discharge 
of untreated sewage, garbage, and other pollutants 
in the waters of the harbor. 
Terminal facilities. There are four commercial 
wharves, one of granite, the others of timber construction. 
There is one yacht club with a public landing. Facilities 
are adequate for present commerce. 
Operations during fiscal year. New work: The project 
was authorized for construction and contract plans and 
specifications were completed. Local assurances and contributed 
funds were received. A $811,111 contract was 
awarded on May 6, 1986 but actual work will not begin 
until October 1986 due to environmental constraints. 
Contract expenditures for the fiscal year were $16,272. 
17. ROYAL RIVER, ME 
Location. Situated 11 miles north of Portland, Maine in 
Yarmouth Village. Royal is a small coastal stream which 
empties into Casco Bay. (See National Ocean Survey 
Chart 13290). 
Existing project. Provides for enlargement of channel 
through bar at Gravel Point, 100 feet wide, 4.5 feet deep 
up to head of commercial navigation at Yarmouth, and 
removal of several ledges near village of Yarmouth; construction 
of 195-foot rubblestone jetty opposite Wolfe's 
Point, and dredging channel 4.5 feet deep through obstructed 
channels; as modified under Section 107 authority, 
the project provides for a channel 8 feet deep, 80 feet wide 
from State channel in Casco Bay to commercial wharf at 
Yarmouth and anchorage of 8 acres, 6 feet deep down- 
1-8

NEW ENGLAND DIVISION 
stream of Interstate 95 Highway Bridge. Project was 
completed in June 1969. (See Table 1-B at end of chapter 
for Acts authorizing existing project). 
Local cooperation. Fully complied with. 
Terminal facilities. Town has constructed public landing 
and launching ramp immediately below Interstate 95 
Highway Bridge on north bank. There are two boatyards 
equipped with floats, marine railways and launching 
ramps. 
Operations during fiscal year. Maintenance: Work 
under a maintenance dredging contract awarded last 
fiscal year was completed. Payments under the contract 
this fiscal year were $114,221 for a total contract cost of 
$252,121. A total of 42,626 cubic yards of material was 
removed. Hired labor costs of $17,865 were incurred for 
supervision and inspection and completion of after dredge 
surveys. 
18. SACO RIVER, ME 
Location. Rises in White Mountain region of New 
Hampshire at an elevation about 1,900 feet above sea 
level, flows about 105 miles in a general southeasterly 
direction, and discharges into Atlantic Ocean about 16 
miles southwest of Portland, Maine. (See National Ocean 
Survey Chart 13287). 
Existing project. For description of completed existing 
portion of project see Annual Report for 1978. For a 
description of completed improvement of project see 
Annual Report for 1983. (See Table 1-B at end of chapter 
for Acts authorizing existing project). 
Local cooperation. Fully complied with. 
Terminal facilities. There are five wharves of solid fill 
construction at Saco and Biddeford, none of which has 
railroad connection; and a small pier near mouth of river 
used for summer passenger business. 
Operations during fiscal year. Maintenance: Payment 
of $9,504 was processed for a contract awarded last fiscal 
year for installation of spindles and day beacons on the 
jetty and breakwater. All work is complete. Navigation 
aids are to be maintained by the Coast Guard. 
19. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 1-Q at end of chapter). 
20. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 1-C at end of chapter). 
21. NAVIGATION ACTIVITIES 
PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645 
(PREAUTHORIZATION) 
(See Table 1-H at end of chapter). 
Alterations of Bridges 
22. AUTHORIZED BRIDGE 
ALTERATION 
Location. Chelsea Street Highway Bridge, MA. Construction 
was completed in October 1961 with a Federal 
cost of $138,518. In addition non-Federal contributed 
funds amounted to $8,062. For details see page 63 of 
Annual Report for 1962. 
23. LYNN-NAHANT BEACH, MA 
Location. The beach is one continuous beach comprised 
of King's Beach Reservation in the town of Swampscott, 
Lynn Short Reservation in the city of Lynn, and Nahant 
Beach Parkway in the town of Nahant, all of which are in 
Essex County, Massachusetts. Lynn Beach is located between 
the towns of Swampscott to the north and Nahant to 
the south. A small section of the southern end of the 
proposed project is located in the town of Nahant. The 
beach is 7%2 miles northeast of the city of Boston. 
Existing project. The authorized plan consists of the 
direct placement of approximately 172,000 cubic yards of 
suitable sandfill for a distance of 2,600 feet between 
Woodbury's Point and the dune on the Nahant tombolo. 
The plan will provide a protective, recreational dry beach 
berm along the backshore to an elevation of 18.0 feet 
above mean low water (MLW). 
Local cooperation. Local interests are rquired to construct 
the project presently estimated at $1,510,000. The 
Federal share of the cost of construction is 57.7 percent or 
$871,270 and will be reimbursed to non-Federal interests 
upon the completion of construction. Provide, without cost 
to the United States, all lands, easements, and rights-ofway 
necessary for project construction and subsequent 
maintenance of the project. Maintain continued public 
ownership of the shore upon which the Federal participation 
is based and its administration for public use during 
the 50-year economic life of the project. Hold and save the 
United States free from all claims for damages that may 
arise before, during, or after prosecution of the work and 
subsequent maintenance of the project other than damages 
due to the fault or negligence of the United States or 
its contractors. Maintain the protective measures during 
the 50-year economic life of the project as may be required 
to serve their intended purpose by contributing 42.3 
percent of the cost of periodic annual sand nourishment 
for the economic life of the project. The current estimated 
cost of periodic sand nourishment is $56,000 annually. The 
Federal share is 57.7 percent or $32,000 and will be 
reimbursed to non-Federal interests upon the completion 
of each nourishment operation. Control water pollution to 
the extent necessary to safeguard the health of the 
bathers. 
Operations during fiscal year. New work: (Note: the 
following is provided for record purposes for work accomplished 
in fiscal year 1983 but inadvertantly omitted from 
the fiscal year 1983 Annual Report). The sponsoring 
Metropolitan District Commission was prepared to construct 
the project in fiscal year 1983. Federal funding of 
$875,000 was received in anticipation of reimbursing the 
MDC for the Federal share. In-house costs of $50,000 were 
incurred for project formulation reviews and environmental 
report efforts undertaken in conjunction with the 
MDC. At the last moment, however, the MDC encountered 
unexpected strong local opposition to the project 
1-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
and, as a result, terminated its plans to construct the 
project. The project was subsequently placed in the inactive 
category. 
24. REVERE BEACH, MA 
Location. In the city of Revere, Suffolk County, Massachusetts, 
approximately 7 miles north of the main entrance 
channel to Boston Harbor and 6 miles northeast of the city of 
Boston. (See National Oceanic and Atmospheric Administration 
Chart No. 13275 and U.S. Geological Survey Maps, 
Boston Bay quadrangle). 
Existing project. Placement of sandfill along 13,000 feet 
of beach. The top of the sandfill will be placed at 18 feet 
above mean low water, including a 50 foot wide berm, 
sloping one-foot vertical in 15 feet horizontal to meet the 
existing beach. The total width of the beach will extend 
approximately 300 feet, of which, about 185 feet is above the 
mean high water line. The estimated total first cost (October 
1985) of the project is $7,850,000 of which 36 percent is 
non-Federal. (See Table 1-B at end of chapter for Acts 
authorizing existing project). 
Local cooperation. Formal assurances have not been 
requested. Consistent with the cost sharing and financing 
concepts agreed to by the Administration and the Senate 
majority leadership, local interests are required to: contribute 
in cash 36 percent of the cost of construction of the 
project, presently estimated at $2,585,000; contribute in 
cash 36 percent of the periodic nourishment cost for an 
initial period of 15 years, now estimated at $22,000 annually, 
such contribution to be prior to each nourishment operation; 
assure the continued performance of the periodic nourishment 
and repair of the project after the first 15 years and 
during the economic life as may be required to serve the 
intended purpose; assure that water pollution that would 
endanger the health of bathers would not be permitted; hold 
the United States free from damages due to construction of 
the project; provide all necessary lands, easements and 
rights-of-way for the initial construction and subsequent 
nourishment of the project; assure continued public ownership 
of the shore and its administration for public use 
during the economic life of the project. 
Operations during fiscal year. New work: Advance 
engineering and design continued, primarily in area of 
coordination with local sponsors on availability of sandfill 
source and satisfying environmental and permit requirements 
in anticipation of project construction. 
25. INSPECTION OF COMPLETED 
BEACH EROSION CONTROL 
PROJECTS 
Inspections of beach erosion projects were not conducted 
in fiscal year 1986. 
26. OTHER AUTHORIZED BEACH 
EROSION CONTROL 
PROJECTS 
(See Table 1-D at end of chapter). 
27. BEACH EROSION CONTROL 
ACTIVITIES PURSUANT TO 
SECTION 103, PUBLIC LAW 
87-874 (PREAUTHORIZATION) 
(See table 1-I at end of chapter). 
Flood Control 
28. BLACKSTONE RIVER BASIN, 
MA AND RI 
Works covered by this plan include a dam and reservoir 
on West River and local protection works at three cities on 
Blackstone River. Flood Control Act of 1944 authorized plan 
for a reservoir on West River and local protection works at 
Worcester,Ma, and Woonsocket and Pawtucket, RI, substantially 
in accordance with House Document 624, 78th Congress, 
2nd session. Flood Control Act of 1960 authorized a 
local flood protection project at lower Woonsocket, RI, 
substantially in accordance with Senate Document 87, 85th 
Congress, 2nd session. Local protection nonstructural project 
authorized in 1982 for Belmont Park section of Warwick, RI 
along the Pawtuxet River. Streambank protection projects 
on the Blackstone River in Millbury, MA and on the Clear 
River in Burrillville, RI were authorized in 1985. (See Table 
1-K at end of chapter on reservoir and local protection 
projects, Blackstone River Basin, for projects comprising 
authorized plan). 
28A. BLACKSTONE RIVER, 
MILLBURY, MA 
Location. The town of Millbury is located in the southcentral 
part of Worcester County in central Massachusetts, 
and lies about 3 miles south of Worcester. 
Existing project. Remove the existing shoal and construct 
a stone slope protection along both banks of the 
Blackstone River to prevent further erosion and possible loss 
of McCracken Road Bridge. 
Local cooperation. Provide without cost to the United 
States all lands, easements, rights-of-way and utility relocations 
necessary for project construction; hold and save 
the United States free from damages due to the construction, 
operation and maintenance of the project, 
except where such damages are due to the fault or 
negligence of the United States or its contractors; maintain 
and operate the project after completion without cost 
to the United States; assume responsibility for all costs in 
excess of the Federal cost limitation of $250,000; prevent 
future encroachment which might interfere with proper 
functioning of the project. 
Operations during fiscal year. New work: A construction 
contract awarded last fiscal year was completed 
in November 1985. Contract payment this fiscal year was 
$123,243 for a total contract amount of $188,243. 
28B. CLEAR RIVER, 
BURRILLVILLE, RI 
Location. The town of Burrillville is located in the 
northwest corner of Rhode Island. The main stem of the 
Clear River originates in the northwest corner of Rhode 
1-10

NEW ENGLAND DIVISION 
Island and flows easterly for 8 miles to its confluence with 
the Branch River. 
Existing project. Remove approximately 60 linear feet 
of granite retaining wall, which has been damaged from 
erosion, and construct a new mortared stone wall. 
Local cooperation. Provide without cost to the United 
States all lands, easements, rights-of-way and utility relocations 
necessary for project construction; hold and save 
the United States free from damages due to the construction, 
operation and maintenance of the project, 
except where such damages are due to the fault or 
negligence of the United States or its contractors; maintain 
and operate the project after completion without cost 
to the United States; assume responsibility for all costs in 
excess of the Federal cost limitation of $250,000; and 
prevent future encroachment which might interfere with 
proper functioning of the project. 
Operations during fiscal year. New work: A construction 
project in the amount of $110,774 was awarded 
in June 1986 and was 5 percent complete at fiscal year 
end. 
28C. PAWTUXET RIVER, 
WARWICK RI 
Location. The Pawtuxet River flows in a northeasterly 
direction through West Warwick, Warwick and Cranston 
before it discharges into Narragansett Bay at Pawtuxet 
Cove. The watershed has a maximum length of 18 miles 
running west to east and 23 miles width from north to 
south. The drainage area at its mouth in Pawtuxet Cove is 
230 square miles. The project is located in the Norwood 
section of Warwick, locally referred to as Belmont Park. 
Existing project. Consists of acquisition, demolition 
and removal from the flood plain a total of 61 homes; 
acquisition of 19 privately owned vacant lots; construction 
of 12 above ground utility room additions to residences 
which experience basement flooding; and the installation 
of an automated flood forecasting and warning system. 
The current estimated project cost is $4,000,000 with the 
Federal government paying 80 percent of the project cost 
up to a Federal limit of $4 million. After implementation, 
the city of Warwick would be responsible for the cost of 
operating and maintaining the flood forecasting/warning 
system. (See Table 1-B at end of chapter for authorizing 
legislation). Project implementation was begun in September 
1982 with property acquisition. Acquisition is 
complete. 
Local cooperation. Local interests were required to 
implement acqusition and removal of properties and pay 
20 percent of project costs unless total project costs 
exceeded $5,000,000 in which case local interests would 
incur all costs above that figure. 
Operations during fiscal year. New work: Acquisition 
was completed. A total of 8 properties were acquired during 
the year, bringing the total to 82. The utility room additions 
were completed under two contracts for a total cost of 
$360,000. 
28D. WEST HILL DAM, MA 
Location. Dam is on West River, MA, 3 miles above its 
confluence with Blackstone River and 2.5 miles northeast of 
Uxbridge, MA. (See Geological Survey maps - 
Blackstone, MA and RI, Milford, MA, and Grafton, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Work on contract for dam 
and appurtenant structures was initiated in June 1959 
and completed in June 1961. Construction of recreational 
facilities was completed in June 1967. 
Local cooperation. Section 3, Flood Control Act of 1944 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
28E. CHARLES RIVER (NATURAL 
VALLEY STORAGE AREAS), MA 
Location. The Charles River extends inland from 
Boston Harbor southwesterly toward the Massachusetts- 
Rhode Island border and is some 80 miles long with a 
watershed covering 307 square miles. 
Existing project. The project provides for Federal 
acquisition and protection of 17 natural valley storage 
areas totalling 8,102 acres in what is known as the Middle 
and Upper watershed of the Charles River. The acquisition 
in fee or by easement of the major natural valley 
storage areas within the Charles River watershed is 
intended as a multiple-purpose project for flood control, 
recreation, and fish and wildlife management. The latest 
cost estimate for new work is $9,000,000. (See Table 1-B at 
end of chapter for Act authorizing existing project). Land 
acquisition is complete. 
A total of 3,210 acres have been acquired in fee at a cost 
of $2,121,283 and restrictive easements have been obtained 
for 4,892 acres at a cost of $584,693. 
Local cooperation. Local interests are required to 
prevent modifications or alteration of existing roadways, 
utilities, bridges, culverts, and any other improvements 
that might affect the drainage characteristics of the 
natural storage areas; adopt and enforce regulations to 
restrict development of flood plan lands; and operate and 
maintain the existing dams along the Charles River. Local 
assurances have been received. 
Operations during fiscal year. New work: Resolution 
of remaining condemnation cases continued. Of 27 tracts 
remaining to be settled at the beginning of the fiscal year, 
5 were resolved. Fiscal year costs totalled $96,871 including 
$48,750 for fee/easement acquisition, $9,200 for 
appraisal contracts, $4,021 in hired labor costs for miscellaneous 
project administration activities, and $34,900 
for condemnation trial activity. Maintenance: Contract costs 
of $59,542 for boundary marking were incurred. Hired 
labor costs for project surveillance and inspection as well as 
land use administration were $96,697. 
29. CONNECTICUT RIVER BASIN 
VT, NH, MA and CT 
Location. Works covered by this project are a series of 
dams and reservoirs on tributaries of Connecticut River in 
Vermont, New Hampshire and Massachusetts, within a 
radius of 230 miles from Hartford, CT, and local protection 
works at several cities in the basin. 
1-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Existing project. Flood Control Act of 1936, as 
amended by Act of May 25, 1937, authorized construction 
of 10 reservoirs on tributaries of Connecticut River in 
accordance with plans in House Document 412, 74th 
Congress, 2nd session, as the same may be revised upon 
further investigation of 1936 flood. Flood Control Act of 
1938 approved a general comprehensive plan for control 
of floods and other purposes in Connecticut River Valley, 
as set forth in House Document 455, 75th Congress, 2nd 
session, and authorized $11,524,000 for construction of 
local flood protection projects ih the plan. Act of October 
15, 1940, modified Act of June 18, 1938, to provide 
additional protection at East Hartford, CT, as set forth in 
House Document 653, 76th Congress, 3rd session. Act of 
August 18, 1941, modified comprehensive plan approved 
in 1938 to include improvements recommended in House 
Document 653, 76th Congress, 3rd session, and House 
Document 724, 76th Congress, 3rd session, with such 
further modifications as may be found justifiable in discretion 
of Secretary of the Army and Chief of Engineers. 
Latter Act also authorized to be appropriated additional 
$6 million for local protection works and $10 million for 
reservoirs. Act of October 26, 1942, further modified plan 
by including construction of Gully Brook conduit at Hartford, 
CT. Flood Control Act of 1944 authorized expenditure 
of $30 million in addition to previous authorization 
for comprehensive plan approved in 1938 and modified 
plan by directing specific consideration of an alternative 
plan of Vermont State Water Conservation Board instead 
of Williamsville Reservoir in West River Basin, VT; 
directing consultation with affected States during course 
of investigations and transmission of proposal and plans to 
each affected State for written views and recommendations 
for reservoir projects heretofore authorized for construction 
at Cambridgeport, Ludlow, South Tunbridge, 
and Gaysville, and resubmission of projects or modifications 
for construction of Sugar Hill site. Flood Control Act 
of 1950 modified project for flood control at Hartford, CT, 
authorized by Flood Control Act of 1938, as amended to 
include Folly Brook dike and conduit. Flood Control Act 
of 1954 modified plan for flood control in Connecticut 
River Basin to provide for construction of a reservoir on 
Otter Brook at South Keene, NH, in lieu of any reservoir 
or reservoirs heretofore authorized. This Act further 
modified plan for West River Basin of Connecticut River 
in Vermont to consist of three reservoirs at Ball Mountain, 
The Island, and Townshend sites, in lieu of plan of eight 
reservoirs authorized in Flood Control Act of 1944. Flood 
Control Act of 1958 modified plan for flood control in 
Connecticut River Basin to include construction of Littleville 
Reservoir on Middle Branch of Westfield River, MA 
and Mad River Reservoir on Mad River, above Winsted, 
CT. Flood Control Act of 1960 included authorization in 
Connecticut River Basin of plan for flood protection on 
Chicopee River, MA, substantially in accordance with 
House Document 434, 86th Congress; plan for flood protection 
on Westfield River, MA, substantially in accordance 
with Senate Document 109, 86th Congress; plan for 
flood control and related purposes on Farmington River, 
CT, substantially in accordance with House Document 
443, 86th Congress. Flood Control Act of 1968 included 
authorization in Connecticut River Basin of plan for 
construction of Beaver Brook Reservoir, on Beaver Brook 
in Keene, NH, substantially in accordance with Senate 
Document 60, 90th Congress; and plan for protection on 
Park River, CT, substantially in accordance with Senate 
Document 43, 90th Congress. Flood Control Act of 1970 
deauthorized the construction of a reservoir at Claremont, 
NH. The Water Resources Development Act of 1976 
deauthorized the construction of Gaysville Lake, Vermont 
project. Flood control projects at Cambridgeport Lake, 
Brockway Lake, Victory Lake, South Tunbridge Lake, 
Ludlow Lake and The Island Lake, Vermont; Honey Hill 
Lake, West Canaan Lake, and the Alternative to Sugar 
Hill Reservoir, New Hampshire were deauthorized in 
August 1977 in accordance with section 12 of the Water 
Resources Development Act of 1974. The authorization for 
Beaver Brook Lake, New Hampshire project expired in 
April 1978 due to lack of local cooperation. Local protection 
projects at Gardner, MA, Hartford, VT and 
Wethersfield, CT authorized and constructed in accordance 
with section 205 of 1948 Flood Control Act. Local 
protection project at Keene, NH authorized in accordance 
with Section 205 of 1948 Flood Control Act, is under 
construction. Emergency streambank erosion control 
projects at Brownsville,VT and Conway,MA authorized in 
accordance with Section 14 of the 1946 Flood Control Act 
are under construction. (See Table 1-L at end of chapter 
for reservoirs and local protection works included in 
comprehensive plan). 
29A. BALL MOUNTAIN LAKE, VT 
Location. Dam is on West River, 29 miles above its 
junction with Connecticut River at Brattleboro, VT. It is 2 
miles north of village of Jamaica, VT. (See Geological 
Survey map for Londonderry, VT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Project is complete. Construction of dam and appurtenant 
works was initiated in May 1957 and completed in 
November 1961. Construction of initial recreation facilities 
was initiated in June 1975 and completed in June 
1977. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded in May 1985 to update the control panels at two 
projects was completed in October 1985. Final contract 
amount was $15,595 of which $5,073 was the Ball Mountain 
portion. 
29B. BARRE FALLS DAM, MA 
Location. Dam is on Ware River in town of Barre,MA, 
31.9 miles above confluence of Ware and Swift Rivers. It 
is 13 miles, northwest of Worcester, MA.(See Geological 
Survey maps for Barre, MA, and Wachusett Mountain, 
MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual report for 
1975. Project is complete. Construction of dam and 
appurtenant works was initiated in May 1956 and completed 
in May 1958. 
1-12

NEW ENGLAND DIVISION 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
last fiscal year, to replace the gatehouse furnace and 
utility building boiler was completed. Final contract 
amount was $14,700. A contract to replace the sewage 
disposal system was awarded in August 1985 and completed 
in November 1985. Final contract amount was 
$23,587. A contract for repairing the gatehouse masonry 
was awarded in May 1986 and is scheduled for completion 
next fiscal year. Contract amount is $36,453. 
29C. BEAVER BROOK, KEENE, NH 
Location. Keene is located in southwestern New Hampshire 
approximately 15 miles north of the Massachusetts 
border and 12 miles east of the Vermont border. 
Existing project. Consists of structural modifications 
to the outlet of the Three Mile Swamp and widening the 
Beaver Brook channel in the reach between Water Street 
and Marlboro Street. Estimated project first costs amount 
to $2,100,000 of which the Federal first cost totals 
$1,925,000. Non-Federal first costs are estimated to total 
$175,000. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
was essentially complete as of the end of the fiscal year. 
Contract earnings to date are $1,717,592. 
29D. BIRCH HILL DAM, MA 
Location. Dam is on Millers River, 27.3 miles above its 
junction with Connecticut River. It is 1.3 miles east of 
South Royalston, MA and 7.5 miles northwest of city of 
Gardner, MA. (See Geological Survey maps for Royalston 
and Winchendon, MA-NH and Templeton, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant works was initiated in June 1940 and completed 
in February 1942. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Local interests have contributed $32,000 as their 
required 50 percent cost sharing of recreational development 
in accordance with 1965 Federal Water Project 
Recreation Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
29E. COLEBROOK RIVER LAKE, CT 
Location. Damsite is in town of Colebrook, Litchfield 
County, CT, on West Branch Farmington River about 3.9 
miles upstream from its confluence with Still River at 
Riverton, CT, and about 1.5 miles upstream from Goodwin 
(Hogback) Dam. (See Geological Survey map for 
Winsted, CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant works was initiated in May 1965 and completed 
in June 1969. Construction of recreation facilities 
was initiated in August 1969 and completed in June 1970. 
Local cooperation. Water supply contract was signed 
by Hartford Connecticut Metropolitan Water District. 
Repayment is being made in accordance with provisions 
of 1958 Water Supply Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract to replace 
the Control House roof at six damsites was awarded 
in April 1985 and completed in November 1985. Total 
contract amount was $23,985 of which $3,895 was for the 
Colebrook River Lake replacement. 
29F. CONANT BROOK DAM, MA 
Location. Site is in south central part of Massachusetts 
in town of Monson. Damsite, across Conant Brook, is about 
2 miles southeast of community of Monson. (See Geological 
Survey map for Monson, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam, highway 
relocations, and appurtenances was initiated in June 
1964 and completed in December 1966. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
29G. KNIGHTVILLE DAM, MA 
Location. Dam is on Westfield River, 27.5 miles above 
its confluence with Connecticut River. It is 4 miles north 
of town of Huntington, MA, and about 12 miles west of 
city of Northampton, MA. (See Geological Survey map for 
Westhampton, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant works was initiated in August 1939 and 
completed December 1941. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
29H. LITTLEVILLE LAKE, MA 
Location. Dam is on Middle Branch of Westfield River, 
1 mile above its confluence with main stem of Westfield 
River and 25.2 miles above confluence of Westfield River 
with Connecticut River, in town of Chester. (See Geological 
Survey map for Chester, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenances was initiated under a multicomponent 
contract in June 1962 and completed in September 1965. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938, and Title III, Water Supply Act of 1958 
applies and fully complied with. 
1-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract to replace 
the Control House roof at six damsites was awarded 
in April 1985 and completed in November 1985. Total 
contract amount was $23,985 of which $4,865 was for the 
Littleville Lake replacement. 
29I. MILL BROOK, BROWNSVILLE, VT 
Location. The project is located along Mill Brook behind 
the Gleanor Grange Hall in the village of Brownsville, 
Vermont. The village is located in the town of West 
Windsor, Vermont in Windsor County, about 12 miles 
north of Springfield, Vermont and 9.5 miles northwest of 
Claremont, New Hampshire. 
Existing project. The streambank stabilization project 
consists of concrete grid block protection placed along 120 
feet of eroded streambank. The grid block is 6 inches 
thick, placed on a 1-foot gravel layer on a slope 1 vertical 
to 1-5 horizontal. The grid block is to be anchored 5 feet 
below the streambed and will extend approximately 8 feet 
above the channel bed. 
Local cooperation. Provide without cost to the United 
States, all lands, easements, rights-of-way, and utility 
relocations necessary for project construction; hold and 
save the United States free from damages due to the 
construction, operation and maintenance of the project, 
except where such damages are due to the fault or 
negligence of the United States or its contractors; maintain 
and operate the project after completion without cost 
to the United States; assume the responsibility for all costs 
in excess of the Federal limitation of $250,000; prevent 
future encroachment which might interfere with proper 
functioning of the project. 
Operations during fiscal year. New work: A construction 
contract in the amount of $48,735 was awarded in 
September 1986. Construction is expected to begin in 
June 1987 following spring runoff. 
29J. NORTH HARTLAND LAKE, VT 
Location. Dam is on Ottauquechee River, 1.5 miles 
above its junction with Connecticut River and 1 mile 
northwest of North Hartland, VT. Reservoir extends 
upstream 5.5 miles. (See Geological Survey map for 
Hanover, NH-VT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam was 
initiated in June 1958 and completed in June 1961. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
in June 1984, to replace the emergency generator and 
feeder circuit was completed in October 1985. Final 
contract amount was $48,893. 
29K. NORTH SPRINGFIELD LAKE, VT 
Location. Dam is in town of Springfield, VT, on Black 
River, 8.7 miles above its junction with Connecticut River, 
and 3 miles northwest of Springfield, VT. (See Geological 
Survey maps for Ludlow, VT and Claremont, NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam was 
initiated in May 1958 and completed in November 1960. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. The contract for 
remedial measures for seepage control that was awarded 
in July 1985 was completed in June 1986. Final contract 
amount was $810,000. A contract for pavement repairs of 
the recreation area road and parking area was awarded in 
April 1986 and completed in July 1986. Contract amount 
was $18,835. 
29L. OTTER BROOK LAKE, NH 
Location. Dam is on Otter Brook, 2.4 miles upstream 
from its junction with The Branch, which flows 2.5 miles 
to Ashuelot River at Keene. (See National Ocean Survey 
maps for Keene, NH-VT, and Monadnock, NH). 
Existing project.For description of completed improvement 
and authorizing legislation see Annual Report for 
1975. Project is complete. Construction of dam and 
appurtenant works was initiated in September 1956 and 
completed in August 1958. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract awarded 
in June 1984 to replace the emergency generator was 
completed in November 1985. Contract amount was 
$23,229. A contract awarded in June 1985 to replace the 
two bridges in the recreation area was completed in May 
1986. Final contract amount was $112,866. A contract in 
the amount of $31,180 for surface treatment of the Access 
Road was awarded in July 1986 and was 43 percent 
complete at fiscal year end. 
29M. PARK RIVER, HARTFORD, CT 
Location. On the Park River in the city of Hartford, 
Hartford County, CT. (See Geological Survey map of 
Hartford North, CT). 
Existing project. Authorized as a modification to 
completed Hartford, CT local protection project. (For 
details on completed project see Annual Report for 1960). 
Two sections of reinforced concrete conduit totalling 2,569 
feet with width of 34 feet and height of 26.5 feet on the 
Park River; one section of reinforced concrete conduit 103 
feet long, 36 feet wide and 27.5 feet high on the South 
Branch; two sections of reinforced concrete conduit 1,364 
feet long, 22 feet wide and 25 feet high on the North 
Branch; a reinforced concrete junction structure to combine 
the flows from the North and South Branches and 
distribute them to the Park River and auxiliary conduits 
and thence to the Connecticut River, circular auxiliary 
conduit approximately 9,200 feet long to be constructed as 
a deep tunnel in rock with an inside diameter of 22 feet 
and lined with 9-inch thick precast concrete walls, an inlet 
structure and an outlet structure; a concrete headwall at 
1-14

NEW ENGLAND DIVISION 
the entrance to the North Branch conduit extension; and 
two pumping stations on the banks of the Park River. The 
latest approved cost estimate (September 1984) for new 
work is $1,300,000 for lands including relocations and 
$60,177,000 for construction, a total of $61,477,000. Total 
includes local costs of $1,200,000 for lands and $100,000 
for relocations. (See Table 1-B at end of chapter for Act 
authorizing existing project). Construction was completed 
in 1981. 
Local cooperation. Provide all lands, easements and 
rights-of-way for construction and operation of project; 
hold and save the United States free from damages due to 
construction works; maintain and operate all works after 
completion; upon completion of conduit construction 
replace pavements, sidewalks, drainage and other appurtenances, 
including those at Broad Street, Flower Street 
and Laurel Street and bear cost of removal, replacement 
and modification to sewers, drains, utilities or highways 
beyond the area required for excavation and construction 
of the project; prevent changes in headpool ponding areas 
which would decrease the effectiveness of the improvements 
and if ponding areas and capacities are impaired, 
promptly substitute equivalent storage capacity; and 
undertake all practical measures to prevent pollution 
from entering the Park River conduit system. 
Operations during fiscal year. New work: As a result 
of recent remedial work the O&M manual was revised. 
Preparation of as-built drawings is underway. 
29N. SOUTH RIVER, CONWAY, MA 
Location. The South River originates below the Lower 
Reservoir in Ashfield, Massachusetts and joins the Deerfield 
River in Conway. The river is approximately 15 
miles long and flows in a southeasterly direction through 
Conway. The town of Conway is located in Franklin 
County in western Massachusetts within the 655 square 
mile Deerfield River drainage basin. It is situated approximately 
five miles west of Interstate 91 between the communities 
of Greenfield and Shelburne Falls to its north, 
and Northampton to its south. 
Existing project. The plan at Site 2 calls for clearing 
and grubbing of the existing slope and refilling the eroded 
areas with compacted random fill. Slope protection consisting 
of a 3-foot thick uniform stone layer underlain by 
filter layers of 1-foot thick stone bedding and 1-foot thick 
gravel bedding would be placed on the random fill. The 
plan at Site 3 calls for clearing and grubbing the existing 
terraced slope and refilling the eroded areas with compacted 
random fill. Slope protection would be provided 
for the lower bank consisting of a 2-foot thick uniform 
stone layer underlain by a 1-foot thick gravel bedding 
layer and continuing to the top of the bank with loam and 
seed. 
Local cooperation. Provide without cost to the United 
States all lands, easements, rights-of-way, and utility 
relocations necessary for project construction; hold and 
save the United States free from damages due to the 
construction, operation, and maintenance of the project, 
except where such damages are due to the fault or 
negligence of the United States or its contractors; maintain 
and operate the project after completion without cost 
to the United States; assume responsibility for all costs in 
excess of the Federal cost limitation of $250,000; prevent 
future encroachment which might interfere with proper 
functioning of the project. 
Operations during fiscal year. New work: A construction 
contract in the amount of $75,443 was awarded in 
August 1986. Work is scheduled for completion next fiscal 
year. 
290. SURRY MOUNTAIN LAKE, NH 
Location. Dam is on Ashuelot River, 34.6 miles above 
its junction with Connecticut River and 5 miles north of 
Keene, NH. (See Geological Survey maps for Keene and 
Bellows Falls, NH-VT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant works was initiated in August 1939 and 
completed in June 1942. Initial phase of additional recreational 
facilities completed in September 1969, secondary 
phase in 1980. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last fiscal year, to repair the roads and parking 
area of the recreation area was completed in October 
1985. Final contract amount was $81,770. 
29P. TOWNSHEND LAKE, VT 
Location. Dam is on West River, 19.1 miles above its 
junction with Connecticut River at Brattleboro, VT, and 
about 2 miles west of Townshend, VT. Reservoir extends 
upstream about 4 miles. (See Geological Survey maps for 
Saxtons River, VT, and Londonderry, VT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant works was initiated in November 1958 and 
completed in June 1961. Initial phase of additional recreational 
facilities completed in October 1969. Secondary 
phase completed in September 1971. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded in May 1985 to update the control panels at two 
projects was completed in October 1985. Final contract 
amount was $15,595 of which $10,522 was the Townshend 
Lake portion. A contract awarded in July 1985 for 
remedial measures for seepage control of relief wells was 
completed in February 1986. Final contract amount was 
$273,955. A contract to replace the emergency generator 
was awarded in May 1986 and is scheduled for completion 
next fiscal year. Contract amount is $38,474. A contract 
for pavement repairs in the recreation area was awarded 
in June 1986 and is scheduled for completion next fiscal 
year. Contract amount of $49,290 was approximately 28 
percent complete at fiscal year end. 
1-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
29Q. TULLY LAKE, MA 
Location. Dam is on East Branch of Tully River, 3.9 
miles above its junction with Millers River. It is 1 mile 
north of Fryville, MA and 3.5 miles north of Athol, MA. 
(See Geological Survey map for Royalston, MA-NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant works was initiated in March 1947 and 
completed in September 1949. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Local interests must also bear 50 percent of future 
recreational development, in accordance with 1965 Federal 
Water Project Recreational Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
29R. UNION VILLAGE DAM, VT 
Location. Dam is on Ompompanoosuc River, 4 miles 
above its junction with Connecticut River. It is one-fourth 
mile north of Union Village, VT and 11 miles north of 
White River Junction, VT. (See Geological Survey maps 
for Strafford, VT and Mount Cube, NH-VT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam was 
initiated in March 1947 and completed in June 1950. 
Local Cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
29S. WEST SPRINGFIELD, MA 
Location. The West Springfield local protection works 
are located in the town of West Springfield, MA. The 
project is on the west bank of the Connecticut River, 76 
miles above its mouth. (See Geological Survey maps for 
Springfield South and West Springfield, MA-CT). 
Existing project. This project consists of a system of 
earth levees and concrete floodwalls approximately 24,500 
feet in length. The system starts at high ground, in the 
vicinity of Harrison Place, and extends downstream along 
the Connecticut River and up the north bank of the 
Westfield River to high ground at the Boston & Albany 
Railroad. The work involved raising 13,700 feet of existing 
levee, constructing 2,300 feet of floodwall, improving 
2,400 feet of river bank, and treating 6,100 feet of existing 
levee foundation. Three pumping stations with appurtenant 
drainage facilities were also constructed for the 
disposal of interior drainage. The project, with the 
approved plan of reservoirs, is designed to protect against 
a flood greater than any of record. The levee and floodwall 
grades are, at all points, above the maximum stage of the 
greatest flood of record, that of March 1936. 
A modification to the project was authorized in October 
1982 providing for the raising of the floodwall sections by 
one foot and the provision of a flood forecasting system. 
The project is a unit of the comprehensive plan of flood 
control and other purposes in the Connecticut River Basin 
and was authorized by the Flood Control Act approved 
June 28, 1938. The project is complete. Construction of the 
prior project work was initiated in March 1939 and 
completed in July 1942 with the exception of foundation 
treatment along the Westfield River south of Agawam 
Bridge, which was initiated in May 1947 and completed in 
November 1947, and relief well and drainage system, 
which was initiated in August 1952 and completed in July 
1953. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Local 
interests continued acquisition of easements needed for 
installation of field equipment that will become part of 
flood warning system. 
30. HOUSATONIC RIVER BASIN, 
CT AND MA 
Authorized improvements in Housatonic River Basin 
are comprised of seven flood control reservoirs on tributaries 
of the Naugatuck River, principal tributary of the 
Housatonic River, and seven local protection projects, five 
of which are along Naugatuck River, one on Housatonic 
River and one on Still River. Naugatuck and Housatonic 
Rivers converge 12 miles above mouth of Housatonic 
River. A project for emergency snagging and clearing of 
the Blackberry River, a tributary of the Housatonic River, 
was authorized under authority contained in Section 208 
of the 1954 Flood Control Act. Emergency bank protection 
projects at Alford, Green River, MA and at Sheffield, 
MA, and Salisbury, CT along the Housatonic were authorized 
under authority provided by Section 14 of the 1948 
Flood Control Act. A project for local flood protection 
along the Housatonic River in Pittsfield, MA was authorized 
under authority provided by Section 205 of the 1948 
Flood Control Act. (See Table 1-B at end of chapter for 
Acts authorizing existing project; also Table 1-M on dams 
and reservoirs and local protection projects for Housatonic 
River Basin). 
30A. BLACK ROCK LAKE, CT 
Location. Damsite is on Branch Brook about 2 miles 
upstream from its confluence with Naugatuck River in 
towns of Thomaston and Watertown, CT. (See Geological 
Survey map for Thomaston, CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Road relocation completed 
in November 1967. Contract for construction of dam and 
appurtenances was awarded in July 1967 and completed 
in July 1971. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. However, local interests must establish encroachment 
lines downstream of dam to permit efficient reservoir 
operation. State legislation requires establishment of 
such lines. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
1 14

NEW ENGLAND DIVISION 
30B. HANCOCK BROOK LAKE, CT 
Location. Dam is on Hancock Brook in town of Plymouth, 
CT, about 3.4 miles above its confluence with 
Naugatuck River. (See Geological Survey map for Waterbury, 
CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 3975. Project is complete. Construction of dam and 
ap urtenanat structures was initiated in July 1963 and 
completed in August 1966. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. However, local interests must establish encroachment 
lines downstream of dam to permit efficient reservoir 
operation. State legislation requires establishment of 
such lines. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
30C. HOP BROOK LAKE, CT 
Location. Damsite is on Hop Brook in city of Waterbury 
and towns of Middlebury and Naugatuck, CT, about 
1.4 miles upstream of confluence of Naugatuck River and 
Hop Brook. (See Geological Survey map for Waterbury, 
CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant structures was initiated in December 1965 
and completed in December 1968. Construction of a public 
use facility was completed in November 1973. Construction 
of an additional restroom was completed in 1980. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. However, local interests must establish encroachment 
lines downstream of dam to permit efficient reservoir 
operation. State legislation requires establishment of 
such lines. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract to 
replace the Control House roof at six damsites was 
awarded in April 1985 and completed in November 1985. 
Total contract amount was $23,985 of which $3,215 was 
for the Hop Brook Lake replacement. 
30D. NORTHFIELD BROOK LAKE, CT 
Location. Dam is on Northfield Brook about 1.3 miles 
upstream from its confluence with Naugatuck River, in 
town of Thomaston, CT. (See Geological Survey map for 
Thomaston, CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenances was initiated in May 1963 and completed 
in October 1965. Construction of recreation facilities was 
initiated in November 1966 and completed in August 
1967. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. However, local interests must establish encroachment 
lines downstream of dam to permit efficient reservoir 
operation. State legislation requires establishment of 
such lines. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
30E. THOMASTON DAM, CT 
Location. On Naugatuck River about 30.4 miles above 
its junction with Housatonic River and about 1.6 miles 
north of Thomaston, CT. Reservoir extends upstream 
about 6.4 miles. (See Geological Survey map for Thomaston, 
CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant works was started in May 1958 and completed 
in November 1960. 
Local cooperation. Section 3, Flood Control Act of 1944 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. The contract to 
perform remedial measures for seepage control awarded 
in September 1985 was completed in December 1985. 
Final contract amount was $198,837. A contract to replace 
the Control House roof at six damsites was awarded in 
April 1985 and completed in November 1985. Total 
contract amount was $23,985 of which $2,965 was for the 
Thomaston Dam replacement. 
31. COVERED BRIDGE, HOUSATONIC 
RIVER, SHEFFIELD, MA 
Location. The town of Sheffield is located in the southwestern 
corner of Berkshire County, Massachusetts, 
approximately 7.5 miles east of the Massachusetts - New 
York state line and about 4.2 miles north of the Massachusetts 
- Connecticut state line. 
Existing project. Construct a 70-foot long stone apron 
to protect the slopes and bottom of the bridge channel. 
Also, a total of approximately 500 linear feet of riprap to 
be located upstream and downstream from the bridge on 
both riverbanks. 
Local cooperation. Assume responsibility for all costs 
in excess of the Federal limitation of $250,000; provide, 
without cost to the United States, all lands, easements, 
rights-of-way and utility relocations necessary for project 
construction; hold and save the United States free from 
damages due to the construction, operation and maintenance 
of the project, except where such damages are due 
to the fault of the United States or its contractors; maintain 
and operate the project after completion, without cost 
to the United States; prevent future encroachment which 
might interfere with proper functioning of the project. 
Operations during fiscal year. New work: Project 
design, including preparation of contract plans and specifications, 
was completed. Formal local cooperation agreement 
was signed and Required Contributed Funds of 
$180,000 were received. A construction contract award in 
amount of $345,675 was made on 8 September 1986. Work 
had not started at fiscal year end. 
1-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
32. GULF STREET 
AND TRUMBULL AVENUE, 
MILFORD, CT 
Location. The city of Milford, is located in the southwest 
corner of New Haven County, in southwestern 
Connecticut. The erosion site at Gulf Street is located 
immediately to the southeast of Milford harbor and the 
site at Trumbull Avenue is located immediately to the 
southwest of Milford Harbor. 
Existing project. Shoreline protection measures will 
consist of construction of stone slope protection for the 140 
foot long reach of shoreline, roadway and associated 
utilities. 
Local cooperation. Provide without cost to the United 
States all lands, easements, rights-of-way and utility 
relocations necessary for project construction; hold and 
save the United States free from damages due to the 
construction, operation and maintenance of the project, 
except where such damages are due to the fault or 
negligence of the United States or its contractors; maintain 
and operate the project after completion without cost 
to the United States; assume responsibility for all costs in 
excess of the Federal cost limitation of $250,000; prevent 
future encroachment which might interfere with proper 
functioning of the project. 
Operations during fiscal year. New work: Project was 
readvertised and contract award in amount of $174,200 
was made on 21 April 1986. Notice to proceed was not 
given until 12 August. Actual work had not begun by 
fiscal year end since contractor was preparing a proposal 
for precast concrete grid block revetment in lieu of stone 
slope protection. 
33. PORT 5 FACILITY, 
BRIDGEPORT, CT 
Location. The Naval Veterans Port 5 Facility is located 
in the city of Bridgeport in coastal southwestern Connecticut, 
specifically on a peninsula extending from the right 
bank at the mouth of Cedar Creek and facing south 
toward Black Rock Harbor and Long Island Sound. 
Existing project. Provides for protection of Naval 
Veterans property against further shoreline erosion from 
wave action by placement of 250 linear feet of graded 
riprap slope protection. (See Table 1-B at end of chapter 
for Acts authorizing existing project). Project is complete. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Operation 
and maintenance manual was prepared and furnished to 
local interests for their use. Project was fiscally completed 
and closed out. 
34. MERRIMACK RIVER BASIN, 
NH AND MA 
Works covered by comprehensive plan are on Merrimack 
River and its tributaries in New Hampshire and 
Massachusetts. Flood Control Act of 1936 authorized 
construction of a system of flood control reservoirs in 
Merrimack River Basin for reduction of flood heights in 
Merrimack Valley. Flood Control Act of 1938 approved 
general comprehensive plan for flood control and other 
purposes as approved by Chief of Engineers pursuant to 
preliminary examinations and surveys authorized by Act 
of June 22, 1936, and modified project to provide in 
addition to construction of a system of flood control 
reservoirs, related flood control works which may be 
found justified by the Chief of Engineers. All operations 
pertaining to flood control in Merrimack River Basin are 
now carried on under and reported under projects for 
individual units of comprehensive plan referred to above. 
No further expenditures are contemplated under general 
project for flood control in Merrimack River Basin. For 
final cost and financial summary, see Annual Report for 
1946. 
A comprehensive plan for development of water resources 
of the North Nashua River Basin, a principal 
tributary of the Merrimack River, was authorized by 1966 
Flood Control Act substantially in accordance with Senate 
Document 113, 89th Congress. Plan provides for construction 
of coordinated system for four reservoirs and 
three local protection projects for flood protection, water 
supply, recreation and allied purposes. 
The 1966 Flood Control Act also authorized construction 
of Saxonville local protection project substantially in 
accordance with Senate Document 61, 89th Congress. An 
emergency bank protection project at Amesbury, MA was 
authorized under authority provided by Section 14 of the 
1948 Flood Control Act. (See Table 1-N at end of chapter 
for reservoirs and related flood control works included for 
construction under comprehensive plan). 
34A. BLACKWATER DAM, NH 
Location. Dam is on Blackwater River, NH, 8.2 miles 
above confluence with Contoocook River and 118.8 miles 
above mouth of Merrimack River. It is in the town of 
Webster, just above village of Swetts Mills, 12.5 miles by 
highway northwest of Concord, NH. (See Geological Survey 
maps for Penacook and Mount Kearsarge, NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete except for construction of 
public facilities. Construction of dam and appurtenant 
works was initiated in May 1940 and completed in 
November 1941. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded in November 1985 for installation of log boom 
anchors at three damsites was completed in January 1986. 
Total contract amount was $20,445 of which $6,545 was 
for the Blackwater Dam installation. A contract to replace 
the emergency generator at three damsites was 
awarded in March 1986 and was 80 percent complete at 
fiscal year end. Total contract amount is $67,000. 
34B. EDWARD MACDOWELL LAKE, NH 
Location. Dam is on Nubanusit Brook, a tributary of 
Contoocook River, one-half mile upstream from village of 
West Peterborough, NH and 14 miles east of Keene, NH. 
1-18

NEW ENGLAND DIVISION 
(See Geological Survey map for Peterboro and Manadnock, 
NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant works was initiated in March 1948 and 
completed in March 1950. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract to 
repaint the service bridge and floodgates was awarded in 
February 1986 and was 70 percent complete at fiscal year 
end. Contract amount is expected to be $30,000 pending 
modifications. 
34C. FRANKLIN FALLS DAM, NH 
Location. Dam is on Pemigewasset River, NH, main 
tributary of Merrimack River, and about 212 miles upstream 
of Franklin, NH. (See Geological Survey maps for 
Penacook and Holderness, NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant works was initiated in November 1939 and 
completed in October 1943. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last fiscal year for repainting the service bridge 
was completed in October 1985. Contract amount was 
$8,600. A contract awarded in November 1985 for installation 
of log boom anchors at three damsites was completed 
in January 1986. Total contract amount was 
$20,445 of which $10,625 was for the Franklin Falls Dam 
installation. 
34D. HOPKINTON-EVERETT LAKES, 
NH 
Location. Hopkinton Dam is on Contoocook River, NH, 
17.3 miles above its junction with Merrimack River and 
about one-half mile upstream from village of West Hopkinton. 
Everett Dam is on Piscataquog River, NH, 16 
miles above its junction with Merrimack River and about 
1.3 miles southeast of village of East Weare. Two interconnecting 
canals were provided to enable the two reservoir 
areas to function as one. (See Geological Survey map 
for Hillsboro, NH, and Concord, NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of two dams 
and appurtenant works was initiated in November 1959 
and completed in December 1962. Construction of recreation 
facilities was initiated in November 1974 and completed 
in September 1975. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Local interests must also bear 50 percent of 
future recreational development in accordance with 1965 
Federal Water Project Recreation Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded in November 1985 for installation of log boom 
anchors at three damsites was completed in January 1986. 
Total contract amount was $20,445 of which $3,275 was 
for the Hopkington Lake installation. A contract in the 
amount of $67,000 to replace the emergency generator at 
three damsites was awarded in March 1986 and was 80 
percent complete at fiscal year end. 
35. NEW BEDFORD, FAIRHAVEN, AND 
ACUSHNET, MA 
Location. Main harbor barrier is across New Bedford 
and Fairhaven Harbor in vicinity of Palmer Island. 
Supplemental dikes and walls are provided in Clark Cove 
area of New Bedford and Fairhaven. (See Geological 
survey maps for New Bedford North, New Bedford South, 
Marion, and Sconticut Neck, MA and National Ocean 
Survey Charts 13230, 13070 and 13218). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of barrier and 
appurtenances was initiated in October 1962 and completed 
in January 1966. Construction of the pumping 
station was initiated in October 1962 and completed in 
June 1964. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance: Operating 
costs included $106,226 for project operations; $4,085 
for administrative activities and $4,722 for completion of 
the five year periodic inspection. 
36. NEW LONDON, CT 
Location. In the city of New London, CT, about 45 miles 
southeast of Hartford, CT, and 50 miles southwest of 
Providence, RI. (See Geological Survey map for New 
London, CT). 
Existing project. The hurricane protection project 
consists of approximately 715 feet of rock-faced earthfill 
dike and 800 feet of I-walls around the northerly shore of 
Shaw Cove and the regrading of approximately 21 acres 
of land along the west shore of the cove to elevation 12.5 
feet mean sea level. Top of dike and floodwalls will be 14.5 
feet mean sea level. Appurtenant structures will include a 
street gate, pressure conduit and a pumping station to 
discharge interior drainage. Latest estimate (December 
1984) for the project is $10,860,000 for construction and 
$1,140,000 for lands and damages including relocations, a 
total of $12,000,000 for new work. Total includes local 
costs of $1,140,000 for lands and relocations and a 
$2,310,000 cash contribution. (See Table 1-B at end of 
chapter for Act authorizing existing project). Project is 
under construction and is approximately 99 percent 
complete. 
Local cooperation. Local interests must: (a) Provide 
lands and rights-of-way for construction; (b) make alterations 
and relocations; (c) bear 30 percent of construction 
cost with credit allowed for (a) and (b); (d) hold the United 
States free from damages; and (e) maintain and operate 
all works. Assurances have been provided. 
1-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Operations during fiscal year. New work: Administrative 
close-out of the Part V contract was made. Final 
contract earnings totaled $973,765. The Part VI contract 
was completed in May 1986. Contract earnings to date are 
$1,054,650 pending modifications. Project dedication was 
held on 1 August 1986. 
37. SAINT JOHN RIVER BASIN, ME 
Comprehensive plan for water resources development 
within the basin was comprised of the multiple-purpose 
Dickey and Lincoln School Reservoirs on the upper Saint 
John River. Projects were authorized by Flood Control 
Act of 1965 substantially in accordance with plans included 
in report of Department of Interior and Corps of 
Engineers dated August 1964 which is supplement to July 
1963 report of International Passamaquoddy Tidal Power 
Project and Upper Saint John River Hydroelectric Power 
Development. *The Dickey Dam component of the project 
was deauthorized by Public Law 97-128 on 29 December 
1981. Local protection project at Fort Kent authorized by 
Chief of Engineers on 25 September 1975 in accordance 
with Section 205 of 1948 Flood Control Act. (See Table 1-F 
at end of chapter for authorized multiple-purpose projects 
including power). 
38. MARGINAL WAY, OGUNQUIT, ME 
Location. The town of Ogunquit is located within York 
County along the coast of southern Maine about 15 miles 
north of Portsmouth, New Hampshire and 40 miles southwest 
of Portland, Maine. Marginal Way is a public footpath 
that starts near the center of town and follows the 
edge of the ocean atop rugged cliffs to Perkins Cove. The 
walkway is about a mile and a half long and was constructed 
in 1926. 
Existing project. Construction of 240 linear feet of 42- 
inch thick stone slope protection along the unprotected 
portion of the walkway which is adjacent to and just north 
of the rebuilt section. 
Local cooperation. Provide without cost to the United 
States all lands, easements, rights-of-way, and utility 
relocations necessary for project construction; hold and 
save the United States free from damages due to the 
construction and maintenance of the project, except 
where such damages are due to the fault or negligence of 
the United States or its contractors; maintain the project 
after completion without cost to the United States; assume 
responsibility for all costs in excess of the Federal cost 
limitation of $250,000; insure that erosion conditions along 
portions of Marginal Way, outside the limits of the proposed 
Corps project, are protected and properly maintained; 
maintain Marginal Way as a public walkway. 
Operations during fiscal year. New work: A construction 
contract in the amount of $182,600 was awarded in 
September 1986. Work has not yet begun. 
39. PENOBSCOT RIVER, OLD TOWN, ME 
Location. The town of Old Town, Maine is located on 
Indian Island along the Penobscot River in south-central 
Maine about 14 miles northeast of Bangor, Maine. 
Existing project. The project consists of modification 
of two existing earth dike structures. These dikes, located 
on the left and right banks of Indian Island just beyond 
the access road bridge are 560 and 700 feet long, respectively. 
The modifications include raising the existing top 
elevation from about 107 feet to 110 feet and providing 
rock slope protection at the riverside face. In addition, 
more adequate interior drainage facilities, consisting of 
two 18-inch gated drainage lines and two portable pumps 
to discharge interior runoff will be provided. Project is 
complete. (See Table 1-B at end of chapter for Acts 
authorizing existing project). 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: The contract 
awarded in September 1985 for remedial measures 
was completed in December 1985. Final contract amount 
was $19,948. 
40. PLEASANT POINT, PERRY, ME 
Location. The town of Perry is located within Washington 
County along the coast of northeastern Maine about 
126 miles east of Bangor, Maine and 20 miles south of 
Calais, Maine. 
Existing project. The project consists of 800 linear feet 
of stone slope protection. The stone is placed on a slope of 1 
vertical to 2 horizontal and extends from mean high tide 
up to the height of expected storm wave runup. A gravel 
walkway will run along the top of the stone protection. 
Local cooperation. Provide without cost to the United 
States, all lands, easements, rights-of-way, and utility 
relocations necessary for project construction; hold and 
save the United States free from damages due to the 
construction, operation and maintenance of the project, 
except where such damages are due to the fault or 
negligence of the United States or its contractors; maintain 
and operate the project after completion without cost 
to the United States; prevent future encroachment which 
might interfere with proper functioning of the project. 
Operations during fiscal year. New work: A construction 
contract in the amount of $126,765 was awarded in 
September 1986. Work has not yet begun. 
41. STAMFORD, CT 
Location. In Fairfield County on north shore of Long 
Island Sound, about 30 miles east of New York City and 
20 miles southwest of Bridgeport, CT. (See Geological 
Survey map for Stamford, CT). 
Existing project. For description of completed improvement 
see Annual Report for 1974. (See Table 1-B at 
end of chapter for Act authorizing existing project). 
Project was completed in 1969. Local interests still owe a 
substantial amount based on claims settlements, including 
interest payment under the Contract Disputes Act. 
Local cooperation. Local interests will provide lands, 
easements, and rights-of-way; make modifications to existing 
storm drainage system which may be required to 
obtain full benefits of protection plan, all necessary modifications 
to existing sanitary sewer facilities required to 
prevent entry of tidal-waters, and all changes, alterations 
1-20

NEW ENGLAND DIVISION 
and additions to or relocations of any buildings and 
utilities made necessary by construction of project; bear 
30 percent of total first cost, estimated at $4,340,000 and 
consisting of cost items listed above plus a cash contribution 
estimated at $3,150,000; contribute in cash, in lieu 
of cost of annual maintenance and operation of tidal 
portion of East Branch barrier which is to be operated 
and maintained by the United States, an amount estimated 
at $880,000; maintain and operate all works after 
completion with exception of tidal portion of East Branch 
barrier and aids to navigation; and hold the United States 
free from damages. Assurances received and cash contributions 
have been deposited except for $662,000 outstanding 
which is local share of final claims settlement including 
interest payment. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. 
42. THAMES RIVER BASIN, CT, 
RI, AND MA 
Works covered by this plan are a series of dams and 
reservoirs on tributaries of Thames River in Massachusetts 
and Connecticut, within a radius of 45 miles from 
Norwich, CT, and a channel enlargement on Shetucket 
River where it discharges into Thames River at Norwich. 
Flood Control Act of August 18, 1941, approved plan for a 
system of reservoirs and channel improvements in 
Thames River Basin in accordance with House Document 
885, 76th Congress, 3rd session, and authorized $6 million 
for initiation and partial accomplishment of project. 
Flood Control Act of December 22, 1944, authorized 
completion of approved plan. Flood Control Act of July 14, 
1960, authorized project for West Thompson Reservoir, 
substantially as recommended in Senate Document 41, 
86th Congress, 2nd session. (See Table 1-0 at end of 
chapter on reservoirs and local protection districts, 
Thames River Basin, for projects comprising approved 
plan). 
42A. BUFFUMVILLE LAKE, MA 
Location. Dam is on Little River, 1.3 miles above its 
junction with French River and 8 miles northeast of 
Southbridge, MA. Reservoir extends upstream about 1.7 
miles northerly and 1.9 miles southerly. (See Geological 
Survey maps for Webster, MA and CT, and Leicester, 
MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant works was initiated in September 1956 and 
completed 1958. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. The contract to 
replace the Utility Building heating system awarded in 
June 1985 was completed in November 1985. Contract 
amount was $14,500. A contract in the amount of $17,900 
to repaint the flood control gates was awarded in February 
1986 and completed in September 1986. 
42B. EAST BRIMFIELD LAKE, MA 
Location. Dam is on Quinebaug River, 64.5 miles above 
its confluence with Shetucket River and 1 mile southwest 
of village of Fiskdale, MA. (See Geological Survey maps 
for Whales, MA and CT, Southbridge, MA and CT, East 
Brookfield MA, and Warren, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant works was initiated in May 1958 and completed 
in June 1960. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract to 
replace the emergency generator was awarded in March 
1986 and was 80 percent complete at fiscal year end. 
Contract amount is expected to be $24,000 pending 
modifications. 
42C. HODGES VILLAGE DAM, MA 
Location. Dam is on French River, 15 miles above its 
confluence with Quinebaug River, at Hodges Village in 
town of Oxford, MA, about 5 miles north of Webster, MA. 
(See Geological Survey maps for Webster, MA, and CT, 
Leicester, MA, Worcester South, MA, and Oxford, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant works, initiated in March 1958, was completed 
in December 1959. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. The contract to 
replace the emergency generator awarded in February 
1985 was completed in December 1985. Contract amount 
was $23,820. 
42D. MANSFIELD HOLLOW LAKE, CT 
Location. Dam is at Mansfield Hollow, CT, on Natchaug 
River, 5.3 miles above its confluence with Willimantic 
River. It is 4 miles northeast of city of Willimantic, CT. 
(See Geological Survey maps for Spring Hill and Willimantic, 
CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam, initiated 
in 1949, was completed in May 1952. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. The contract to 
replace the Control House roof at six damsites awarded in 
April 1985 was completed in November 1985. Total contract 
amount was $23,985 of which $4,230 was for the 
Mansfield Hollow Lake replacement. 
1-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
42E. WEST THOMPSON LAKE, CT 
Location. Dam is on Quinebaug River in town of Thompson, 
CT. Site is in village of West Thompson, 2 miles 
upstream from city of Putnam, CT. (See Geological Survey 
map, for Putnam, CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam, road 
relocation, and appurtenances was initiated in August 
1963 and completed in October 1965. Initial phase of 
recreation facilities was completed in May 1976. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. The contract for 
miscellaneous repairs to the service bridge awarded in 
May 1985 was completed in May 1986. Final contract 
amount was $34,803. A contract for construction of a 
storage building was awarded in April 1986 and was 75 
percent complete at fiscal year end. Contract amount is 
$57,960. 
42F. WESTVILLE LAKE, MA 
Location. Dam is on Quinebaug River, 56.7 miles above 
its confluence with Shetucket River, in towns of Sturbridge 
and Southbridge, MA, and 1.3 miles west of center 
of Southbridge. (See Geological Survey maps for Southbridge, 
MA and RI, and East Brookfield, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam and 
appurtenant works was initiated in April 1960 and 
completed in August 1962. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. The contract to 
replace the emergency generator awarded in March 1985 
was completed in October 1985. Contract amount was 
$19,222. The contract to replace the Control House roof at 
six damsites awarded in April 1985 was completed in 
November 1985. Total contract amount was $23,985 of 
which $4,785 was for the Westville Lake replacement. The 
contract to replace the Gatehouse furnace and Utility 
Building boiler awarded in May 1985 was completed in 
October 1985. Contract amount was $10,900. A contract 
for restroom renovations was awarded in March 1986 and 
completed in August 1986. Contract amount was $23,984. 
43. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
In accordance with provisions of the Flood Control Act 
of 1936, as amended, local flood protection works constructed 
with Federal funds are transferred to local 
interests to operate and maintain. To insure compliance 
with regulations prescribed for their operation and maintenance, 
regular inspections of the following projects were 
made during the fiscal year: 
CONNECTICUT: October 1985 and May 1986 - Ansonia, 
Derby, East Hartford, Hartford New London, 
Pawcatuck, Stamford; April 1986 - Bridgeport, Colchester/ 
East Hampton, North Canaan, Salisbury, Torrington, 
Winsted, Woodbury; May 1986 - Danbury, East Branch, 
Hall Meadow, Mad River, New Fairfield, Norwalk, 
Sucker Brook, Waterbury, Wethersfield. 
MAINE: May 1986 - Beals, Blaine, Castine, Cherryfield, 
Fort Kent, Harpswell, Hartland, Indian Island, Islesboro, 
Lubec, Whiting. 
MASSACHUSETTS: October 1985 and April 1986 - 
Gardner, Haverhill, Lowell; October 1985 and May 1986 
-Charles River Dam, Chicopee, Fitchburg, Holyoke, Northampton, 
Springfield, West Springfield; November 1985 
and May 1986 - Saxonville; April 1986 - Alford, Canton, 
Lee, Pittsfield, Scituate, Sheffield, Three Rivers, West 
Warren, Worcester; May 1986 - Amesbury, Blackstone, 
Haywood Creek, Huntington, Lancaster, Quincy, Ware, 
Weymouth-Braintree. 
NEW HAMPSHIRE: October 1985 - Keene; October 
1985 and May 1986 - Nashua; April 1986 - Lincoln, 
Shelburne, Wilton;May 1986 - Charlestown, Farmington, 
North Stratford, West Stewartstown. 
RHODE ISLAND: October 1985 and May 1986 - 
Woonsocket. 
VERMONT: May 1986 - Rockingham, Weston. 
44. FLOOD CONTROL 
RESERVOIR OPERATIONS 
A coordinated system of reservoirs, many of which are 
multipurpose in nature and all containing significant 
amounts of storage for flood control purposes, has been 
established in five major flood producing basins in New 
England. During periods of floodflows, regulation of reservoirs 
is fully coordinated within each basin dependent 
upon its location in the watershed, its available storage 
capacity and origin of flood. In addition to flood control 
releases, water supply, flow augmentation and hydropower 
releases were made from selected reservoirs. 
On 26-27 January 1986, a complex storm system deposited 
between 2 to 4 inches of rain over central New 
England. Because many of the rivers and streams were 
frozen, the runoff from this storm caused several rivers to 
rise near flood stage. Corps reservoirs at these sites were 
throttled as a result of this condition and limited releases 
were made to empty the reservoirs without causing flows 
to exceed the reduced downstream channel capacities. 
The operation resulted in several Corps projects holding 
water longer than normal and hence significant storages 
were experienced at many of the Corps reservoirs. 
A second event, during the month of March, was caused 
by about 2 inches of rainfall during snowmelt in central 
Massachusetts, New Hampshire and Vermont. Rivers 
rose to near bankfull capacity, and several Corps reservoirs 
stored significant amounts of runoff; however, no 
serious flooding was attributed to this storm. 
During 5-8 June 1986, 3 to 6 inches of rain fell on 
southern New England, with an unusual 9.2 inches occurring 
at Colebrook Lake, CT. Corps reservoirs were throttied 
in anticipation of this storm, however, dry antecedent 
conditions prevented any significant problems and no 
flooding occurred downstream of our reservoirs. 
1-22

NEW ENGLAND DIVISION 
Connecticut River Basin 
Storages at Corps reservoirs for the March event were 
33 percent of capacity at Ball Mountain, 31, percent at 
Surry Mountain, 30 percent at Otter Brook, 28 percent at 
Townshend and 25 percent at Knightville. 
Regulation for canoe activities occurred at Ball Mountain 
and Townshend - October 1985 and May 1986, Birch 
Hill and Tully - April 1986 and Knightville and Littleville 
- April 1986. Water supply releases were made 
throughout the year at Colebrook Lake. 
Non-flood releases from North Hartland Lake have 
been controlled by the Vermont Electric Generation and 
Transmission Cooperative for hydropower during most of 
FY 1986. 
Merrimack River Basin 
Regulation of reservoirs in the Merrimack River Basin 
for the 26-27 January storm resulted in peak storages at 
MacDowell Lake - 41 percent, Franklin Falls - 28 
percent and Blackwater Dam - 17 percent. 
Runoff was stored at Blackwater Dam in April in order 
to provide sufficient flows for canoeing activities on 12-13 
April. 
Thames River Basin 
There were no important events in the Thames River 
Basin during FY 1986, however, reservoir storages 
amounting to 20 percent and 19 percent were experienced 
at Westville and Buffumville, respectively, in March 1986. 
Other regulation activities in the basin included regulation 
for canoeing at Mansfield Hollow in June and September 
and at East Brimfield and Westville in April. Also, 
the permanent pool at West Thompson was raised on 
several occasions during FY 1986 to accommodate AKC 
retreiver trials and powerboat competitions. 
Housatonic River Basin 
Regulation of the reservoirs in the Naugatuck River 
Basin in January 1986 resulted in peak storages at Black 
Rock - 22 percent and Thomaston - 16 percent. The 
peak storage at Hop Brook occurred in March 1986 and 
amounted to 18 percent. 
Blackstone River Basin 
West Hill Dam, in the Blackstone River Basin, utilized 
24 percent of storage in June of 1986. 
45. HURRICANE BARRIER OPERATIONS 
Five hurricane barriers, including the recently completed 
New London Hurricane Barrier, are situated along 
the southern coast of New England, protecting coastal 
communities from tidal flooding associated with hurricanes 
or severe coastal storms. The Corps operates the 
navigational elements of the Stamford, Connecticut and 
the New Bedford-Fairhaven, Massachusetts barriers. The 
Fox Point, Rhode Island and the Pawcatuck and New 
London, Connecticut barriers are operated by the local 
communities. A brief resume of operations for the fiscal 
year follows: 
Stamford Barrier. The barrier gates were operated on 
nine occasions for coastal storms, and prevented $25,000 
in damages during FY 1986. 
New Bedford Barrier. The New Bedford Barrier was 
operated on three occasions for coastal storms and prevented 
$25,000 in damages during FY 1986. 
Fox Point Hurricane Barrier. The Fox Point Hurricane 
Barrier was not operated during FY 1986 and did 
not experience damaging tidal flood conditions. 
Pawcatuck Hurricane Barrier. The Pawcatuck Hurricane 
Barrier was not operated during FY 1986 and did 
not experience damaging tidal flood conditions. 
New London Hurricane Barrier. The New London 
Hurricane Barrier was not operated during FY 1986 and 
did not experience damaging tidal flood conditions. 
46. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 1-E at end of chapter). 
47. FLOOD CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205. Public 
Law 858, 80th Congress, as amended (preauthorization). 
(See Table 1-J at end of chapter). 
Snagging and clearing activites pursuant to Section 208 
of the 1954 Flood Control Act. 
Konkapot River, 
North Canaan, CT $ 14,895 
Pawtuxet River, 
Cranston, RI 5,500 
Quinnipiac River, 
North Haven, CT 7,500 
Emergency Bank Protection activities pursuant to Section 
14 of the 1946 Flood Control Act. 
Fiscal year costs were as follows: 
Baker River, Warren, NH 6,000 
Blackstone River, Millbury, MA 128,528 
(See Section 28A of Text) 
Clear River, Burrillville, RI 7,180 
(See Section 28B of Text) 
Clesson Brook, Buckland, MA 5,000 
Connecticut River, Walpole, NH 7,500 
Connecticut River, North Stratford, NH 455 
Connecticut River, Cornish, NH 7,500 
Covered Bridge, Sheffield, MA 2,073 
(See Section 31 of Text) 
Factory Brook, Middlefield, MA 396 
Falulah Brook, Fitchburg, MA 7,500 
Fort Trumbull Beach, Milford, CT 10,309 
George Street, Keene, NH 7,500 
Machias River, Machias, ME 31,996 
Marginal Way, Ogunquit, ME 22,784 
(See Section 38 of Text) 
Merrimack River, Concord, NH 5,000 
Mill Brook, Brownsville, VT 23,188 
(See Section 29I of Text) 
1-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Narraguagus River, Cherryfield, ME 6,000 
Pleasant Point, Perry, ME 46,949 
(See Section 40 of Text) 
Port 5 Facility, Bridgeport, CT 7,349 
(See Section 33 of Text) 
Saxtons River, Rockingham, VT 6,700 
South River, Conway, MA 28,263 
(See Section 29N of Text) 
Ware River, MA 7,000 
Emergency flood control activities - repair, flood fighting, 
and lescue work (Public Law 99, 84th Cong., and 
antecedent legislation). 
Federal costs for fiscal year were $111,652 for disaster 
preparedness and $86,286 for rehabilitation work in 
Farmington, NH. 
Streambank Erosion Control Evaluation and Demonstration 
Act of 1974 as amended in 1976 (Section 32 of the 
Water Resources Development Act of 1974. P.L. 93-251). 
There were no fiscal year costs for demonstration project 
proposals. Total costs to 30 September 1986 were 
$1,204,996. 
48. DEAUTHORIZED PROJECTS 
(See Table 1-G at end of chapter). 
General Investigations 
49. SURVEYS 
Costs for the fiscal year for surveys from regular funds 
were $1,601,331 of which $201,287 was for four navigation 
studies; $211,371 for three flood damage prevention 
studies; $4,712 for one special study; $785,410 for three 
comprehensive studies; $84,940 for review of three completed 
or deferred projects; $313,611 for coordination 
studies. 
50. COLLECTION AND STUDY OF 
BASIC DATA 
The Division Engineer is the U.S. member on Saint 
Croix River Board of Control. Annual inspections are 
made of conditions on the Saint Croix River and a continuing 
program of compilation of basic hydrologic information 
is carried out. Division Engineer's representatives 
during the past year kept closely in touch with developments 
in the basin and cooperated with their Canadian 
counterparts assisting in development of basins' resources. 
Total costs for the fiscal year were $14,889. Total costs to 
30 September 1986 were $179,423. 
Flood plain studies comprise compilation and dissemination, 
upon responsible local request, of information on 
floods and potential flood damages, including identification 
of areas subject to inundation by floods of various 
magnitudes and frequencies, and general criteria for 
guidance in use of flood plain area; and engineering 
advice to local interests for their use in planning to 
ameliorate flood hazard. Total costs for the fiscal year 
were $192,225. Total costs to 30 September 1986 are 
$4,944,625. 
51. CONTINUATION OF PLANNING 
AND ENGINEERING 
Total costs for continuation of Planning and Engineering 
were $305,023 of which $13,349 was for channels and 
harbors and $291,674 for local protection. 
The channels and harbor study was at Portsmouth, New 
Hampshire. The continuing local protection studies were 
for Town Brook in Quincy, Massachusetts and for 
Roughans Point in Revere, Massachusetts. 
52. ADVANCE ENGINEERING 
AND DESIGN 
Advance Engineering and design costs were $34,807 for 
the beach erosion control project at Revere Beach, Massachusetts 
and $64,396 for the navigation project at Bristol 
Harbor, RI. 
1-24

NEW ENGLAND DIVISION 
TABLE 1-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
1. Aquatic Plant 
Control 
2. Black Rock 
Harbor, CT 
3. Bristol Harbor 
Bristol, RI 
4. Cape Cod Canal, 
MA 
(Contributed 
Funds) 
5. Connecticut River 
below Hartford, 
CT 
(Contributed 
Funds) 
6. Green Harbor, 
MA 
(Contributed 
Funds) 
7. Hampton Harbor, 
NH 
(Contributed 
Funds) 
8. Hyannis Harbor, 
MA 
(Contributed 
Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Minor rehab. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
10,000 
2,093 
1,426,000 
1,244,713 
8,575 
7,995 
79,359 
242,071 
40,000 
36,134 
22,900 
22,180 
30,000 
31,931 
245,496 
243,559 
23,000 1,551,259 
23,000 1,531,964 
113,000 
64,396 
351,288 
302,684 
1,654 
1,654 
-9,000 
75,308 
- 32,786,7501,2 
- 32,786,2191,2 
4,541,756 4,865,718 6,469,630 6,093,171 86,696,584 
5,043,968 5,311,711 6,765,682 6,101,729 86,426,774 
- - - - 115,432 
- - - - 115,432 
874,000 
930,549 14,269 
2,011,524 1,775,602 
695,246 3,387,864 
305,561 
272,598 
154,525 
192,598 
168 
177,567 
179,124 
254,900 
264,505 
- 390,677 
- 390,677 
- 26,609,000 
- 26,609,000 
- 1,541,1853,4 
- 1,541,1853,4 
129,792 14,744,3015 
118,673 14,733,1645 
- 60,000 
- 60,000 
- 130,410 
- 130,410 
- 254,512 
- 254,512 
58,116 1,765,299 
44,232 1,740,379 
9,658 
11,700 
13,301 
12,946 
12,946 
1-25 
317,558 
311,599 
18,398 
18,398 
-6,000 
357,454 
339,813 
168,000 
168,000 
- 200,000 
- 200,000 
4,000 1,762,216 
3,587 1,761,761 
15,184 
16,473 
193,761 
193,761 
484,499 
484,499 
641,1956 
624,8436 
103,001 
103,001

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
9. Jonesport Harbor, 
ME 
10. Kennebec River, 
ME 
11. Mystic River, 
MA 
12. New Haven 
Harbor, CT 
13. New London 
Harbor, CT 
14. Newburyport Harbor, 
MA 
15. Point Judith Pond 
and Harbor of 
Refuge, RI 
(Contributed 
Funds) 
16. Rockport and Old 
Harbors, Rockport, MA 
(Contributed 
Funds) 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
25,000 
8,160 
8,956 
9,422 
50,132 
9,148 
2,678,304 
2,437,301 
697,825 
680,448 
2,463,926 
722,522 
25,000 
13.889 
12,791 
62,474 
648,500 
971,281 
773,584 
772.839 
-19,652 
6,305 
-125,695 
612,029 
40,000 
3,725 
22,003 
22,003 
46,404 
44,013 
106,071 
103,063 
176,641 
177.322 
21,243 
24,225 
-358,831 
644,031 
205,000 510,000 
261,017 501,179 
- 1,599,940 7 
- 1,599,940 7 
422,302 2,215,058 
421,393 2,214,149 
- 3,222,777 
- 3,222,777 
-10,000 1,964,740 
- 7,106 1,964,740 
- 4,205,2468 
- 4,205,2468 
22,564 12,789,7249 
25,795 12,788,9749 
- 638,77410 
- 638,77410 
582,206 1,810,465 
582,270 1,810,465 
569,225 
569,225 
34,909 4,095,461 
36,759 4,094,948 
- 1,415,524 
- 1,415,524 
- 2,714,51011 
- 2,714,510" 
426,000 3,842,884 
425,264 3,838,388 
- 1,926,000 
- 1,926,000 
- 17,587 
- 17,587 
50,000 
47,420 
39,000 
72,000 
69,420 
194,963 
194,963 
39,000 
1-26

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
17. Royal River, 
ME 
(Contributed 
Funds-Required) 
(Contributed 
Funds-Other) 
18. Saco River, ME 
23. Lynn-Nahant 
Beach, MA 
24. Revere Beach, MA 
(Contributed 
Funds) 
28A. Blackstone River, 
Millbury, MA 
28B. Clear River, 
Burrillville, RI 
28C. Pawtuxet River, 
Warwick, RI 
28D. West Hill Dam, 
MA 
28E. Charles River 
(Natural Valley) 
Storage Areas), MA 
29A. Ball Mountain 
Lake, VT 
29B. Barre Falls Dam, 
MA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
31,116 
31,116 
223,772 
204,072 
149,965 
169,051 
336,704 
336,704 
661,22712 
660,61312 
49,562 
49,562 
18,000 
18,000 
15,000 
211,293 
316 
820,000 
49,884 
-5,000 
8,194 
9,891 
9,891 
59,880 
50,176 
- 1,064,983 
- 1,064,983 
78,829 1,644,971 
88,333 1,644,771 
-770,000 
116 
- - 230,000 
- - 195,093 
- 47,500 202,500 
- 34,149 84,277 
- - 50,000 
- - 40,704 
770,000 1,015,000 1,375,000 
635,554 1,128,982 1,151,872 
150,650 
168,669 
615,000 
567,600 
16,000 
176,430 
256,800 
255,273 
243,000 
243,211 
182,000 
171,654 
125,000 
118,167 
132,000 
120,973 
4,000 
3,872 
354,000 
341,628 
252,000 
240,017 
212,700 
196,959 
140,000 
177,899 
144,000 
149,099 
336 
698 
588,800 
456,093 
416,600 
378,002 
50,000 
50,000 
- 483,71213 
34,807 483,61213 
- 142,965 
- 142,965 
- 250,000 
128,528 246,954 
130,000 180,000 
7,180 47,884 
- 3,300,000 
133,022 3,171,022 
- 2,306,90214 
- 2,306,90214 
264,000 2,724,234 
243,999 2,678,065 
191,000 8,606,000 
96,871 8,474,187 
198,000 474,000 
156,239 426,311 
- 11,039,29815 
- 11,039,29815 
606,000 5,477,739 
660,207 5,375,592 
- 1,967,819 
- 1,967,819 
405,000 3,686,627 
334,097 3,550,419 
1-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
29C. Beaver Brook, 
Keene, NH 
29D. Birch Hill Dam, MA 
(Contributed 
Funds) 
29E. Colebrook River 
Lake, CT 
29F. Conant Brook 
Dam, MA 
29G. Knightville Dam, 
MA 
29H. Littleville Lake, 
MA 
29I. Mill Brook, 
Brownsville, VT 
29J. North Hartland 
Lake, VT 
29K. North Springfield 
Lake, VT 
29L. Otter Brook 
Lake, NH 
29M. Park River, 
Hartford, CT 
(Other Contributed 
Funds) 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
65,000 
87,689 
278,400 
328,596 
111,500 
129,544 
48,000 
54,350 
231,200 
305,915 
222,000 
216,117 
50,000 
22,795 
230,000 
204,543 
107,000 
104,747 
82,000 
76,250 
588,000 
465,260 
237,000 
251,701 
236,000 1,775,000 2,286,000 
223,473 1,731,994 2,195,868 
- - 4,815,67916 
- - 4,815,67916 
230,800 217,000 3,767,727 
261,717 215,317 3,758,725 
- - 32,00017 
- - 32,00017 
- - 14,263,971 
- - 14,263,971 
150,900 190,000 1,999,444 
159,338 185,002 1,988,190 
- - 2,950,530 
- - 2,950,530 
59,000 126,000 1,080,680 
55,768 115,990 1,061,526 
- - 3,415,64018 
- - 3,415,64018 
349,400 296,000 4,928,904 
490,983 301,828 4,919,099 
248,800 
250,330 
- 7,013,412 
- 7,013,412 
464,000 3,209,891 
290,889 3,029,404 
38,000 
23,188 
229,600 
232,025 
270,300 
280,799 
13,000 
148,619 
352,300 
341,681 
75,000 
67,401 
301,000 
281,472 
312,000 
309,613 
2,000 
2,525 
339,000 
321,897 
225,000 
233,110 
329,700 
325,812 
818,000 
715,240 
401,300 
333,319 
54,889 
13,408 
38,000 
23,188 
- 7,312,22519 
- 7,312,22519 
279,000 3,772,815 
264,351 3,725,756 
- 6,831,52620 
- 6,831,52620 
861,000 5,982,097 
972,541 5,969,220 
- 4,360,44821 
- 4,360,44821 
356,000 3,719,614 
448,103 3,699,340 
- 60,176,919 
-8,733 60,156,007 
24,415 
259,408 
259,408 
1-28

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
29N. South River New Work 
Conway, MA 
290. Surry Mountain 
Lake, NH 
29P. Townsend Lake, 
VT 
29Q. Tully Lake, MA 
(Contributed 
Funds) 
29R. Union Village 
Dam, VT 
29S. West Springfield, 
MA 
(Contributed 
Funds) 
30A. Black Rock Lake, 
CT 
30B. Hancock Brook 
Lake, CT 
30C. Hop Brook Lake, 
CT 
30D. Northfield Brook 
Lake, CT 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
364,000 
369,268 
235,000 
241,188 
244,500 
256,745 
204,700 
241,811 
215,000 
58,510 
192,200 
186,989 
61,500 
65,798 
307,550 
312,547 
12,961 
122,500 
118,349 
394,000 
403,328 
289,000 
266,179 
285,000 
279,572 
293,000 
284,628 
112,162 
13,000 
181,000 
178,239 
79,000 
77,599 
382,000 
379,251 
129,000 
117,350 
391,300 
373,176 
673,900 
569,734 
371,900 
297,333 
250,700 
243,528 
12,169 
162,000 
170,351 
94,400 
96,252 
375,400 
321,003 
156,800 
151,456 
50,000 
28,263 
50,000 
28,263 
- 2,833,61022 
- 2,833,61022 
280,000 4,493,443 
294,216 4,469,588 
- 7,398,41323 
- 7,398,41323 
472,000 5,076,471 
541,835 5,001,846 
- 1,666,75224 
- 1,666,75224 
313,000 3,599,986 
310,633 3,500,316 
- 40,000'7 
- 40,00017 
- 4,095,16025 
- 4,095,16025 
216,000 3,525,556 
243,036 3,517,290 
- 215,000 
37 182,878 
- 13,000 
- 8,182,300 
- 8,182,300 
191,000 2,170,609 
172,852 2,150,622 
- 4,178,911 
- 4,178,911 
84,000 1,075,649 
80,751 1,072,327 
- 6,151,56226 
- 6,151,56226 
531,000 3,930,885 
499,564 3,822,817 
- 2,850,51227 
- 2,850,51227 
200,000 1,647,711 
202,038 1,624,661 
1-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
30E. Thomaston Dam. New Work 
CT 
31. Covered Bridge, Housatonic 
River, Sheffield, MA 
32. Gulf Street and Trumbull 
Avenue, Milford, CT 
33. Port 5 Facility, 
Bridgeport, CT 
34A. Blackwater Dam, 
NH 
34B. Edward MacDowell 
Lake, NH 
34C. Franklin Falls 
Dam, NH 
34D. Hopkinton-Everett 
Lakes, NH 
35. New Bedford, 
Fairhaven, and 
Acushnet, MA 
(Contributed 
Funds) 
36. New London, CT 
(Contributed 
Funds-Required) 
(Other 
Contributed 
Funds) 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
237,000 
241,314 
12,000 
11,982 
32,500 
27,705 
224,000 
234,591 
254,000 
236,598 
35,000 
33,286 
207,000 
171,445 
167,000 
165,282 
171,600 205,000 
169,835 207,435 
438,000 325,000 
434,604 336,139 
533,900 429,000 
564,139 428,898 
509,000 202,000 
475,213 330,791 
1,160,000 
1,018,945 
140,000 
165,095 
36,008 
825,000 
625,839 
300,000 
93,884 
84,750 
58,208 
588,500 
405,293 
660 
48,500 
38,921 
-12,000 
21,001 
193,200 
197,527 
232,600 
229,583 
562,100 
563,698 
568,800 
489,672 
227,750 
230,766 
350,000 
540,331 
65,000 
218,246 
37,640 
- 14,282,112 
- 14,282,112 
343,000 4,292,767 
533,544 4,272,558 
50,000 
2,073 
97,000 
48,001 
X0,000 238,500 
10,309 49,230 
- 227,500 
7,349 227,500 
- 1,319,74628 
- 1,319,74628 
248,000 2,850,985 
213,093 2,815,144 
- 2,014,25329 
- 2,014,25329 
277,000 3,371,392 
254,523 3,330,649 
- 7,950,48730 
- 7,950,48730 
367,000 5,394,137 
438,508 5,378,883 
- 21,452,44031 
- 21,452,44031 
512,500 6,188,540 
502,046 6,080,454 
- 11,510,088 
- 11,510,088 
120,000 3,559,864 
115,033 3,552,533 
- 6,513,76332 
- 6,513,76332 
- 9,272,046 
124,061 9,243,190 
- 2,255,00033 
54,932 2,251,31433 
6,500 
3,500 
222,250 
219,250 
1-30 
19
1

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
38. Marginal Way, 
Ogunquit, ME 
39. Penobscot River, 
Old Town, ME 
40. Pleasant Point, 
Perry, ME 
41. Stamford, CT 
(Contributed 
Funds-Required) 
(Other 
Contributed 
Funds) 
42A. Buffumville Lake, 
MA 
42B. East Brimfield 
Lake, MA 
42C. Hodges Village 
Dam, MA 
42D. Mansfield Hollow 
Lake, CT 
42E. West Thompson 
Lake, CT 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
32,500 
13,081 
40,000 
4,923 
121,000 
120,960 
341,000 
150,264 
239,000 
253,141 
170,000 
179,248 
225,300 
203,446 
203,000 
228,848 
3,000 
19,708 
477,800 
434,456 
190,000 
364,097 
297,000 
305,796 
164,000 
137,426 
308,000 
291,612 
207,000 
204,938 
480 
320,000 
376,345 
210,000 
207,808 
312,400 
292,103 
191,100 
208,938 
195 
195 
350,800 
350,711 
239,500 
244,183 
317,300 
301,293 
30,000 
22,784 
24,940 
63,000 
46,949 
62,500 
35,865 
188,045 
177,908 
63,000 
46,949 
- 9,911,300 
- 9,900,618 
156,000 2,458,372 
185,598 2,450,647 
- 3,367,97034 
- 3,367,45334 
- 210,000 
- 209,969 
- 2,998,60335 
- 2,998,60335 
243,000 3,089,322 
256,020 3,079,022 
- 7,057,04336 
- 7,057,04336 
215,000 2,520,683 
211,889 2,506,943 
- 4,461,26837 
- 4,461,26837 
271,500 2,984,098 
295,212 2,959,888 
- 6,447,16438 
- 6,447,16438 
178,000 3,090,797 
173,872 3,085,172 
- 7,001,22039 
- 7,001,22039 
423,000 3,356,998 
423,571 3,333,795 
1-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
42F. Westville Lake, New Work 
MA Approp. - - - - 5,684,68340 
Cost - - - - 5,684,68340 
Maint. 
Approp. 213,000 243,000 373,300 382,000 3,069,096 
Cost 199,653 199,852 377,556 342,850 2,969,751 
SIncludes $6,138,157 from Public Works Funds and $4,849,740 
from Emergency Relief Funds. 
2 Includes $389,929 Code 711 funds and $511,089 Code 713 
funds. 
3 Includes $287,374 for previous projects. 
4 Excludes $9,000 for subproject "Eightmile River, CT". 
5 Includes $366,348 for previous projects. 
6 Excludes $129,757 expended for rehabilitation; breakwater 
repaired in 1961. 
7 Includes $509,411 for previous projects. 
s Includes $331,626 for previous projects. Includes $290,877 
National Industrial Recovery Funds and $59,207 Public Works 
Funds. 
9 Includes $32,570 for previous projects. 
10 Includes $40,800 for previous project. 
11 Includes $12,000 for previous project. 
12 Excludes $20,000 expended from Contributed Funds, Other. 
13 Excludes $73,800 for previous project. 
14 Includes $18,310 Code 711 funds. 
15 Includes $504,060 Code 711 funds. 
16 Includes $618,469 Code 711 funds and $32,000 Code 713 
funds. 
17 Recreational cost sharing. 
18 Includes $199,303 Code 711 funds. 
19 Includes $229,436 code 711 funds. 
20 Includes $59,536 Code 711 funds. 
21 Includes $364,688 Code 711 funds. 
22 Includes $470,077 Code 711 funds. 
2 Includes $245,168 Code 711 funds. 
24 Includes $3,695 Code 711 funds and $115,138 Code 713 
funds. 
Zs Includes $88,932 Code 711 funds. 
Z Includes $143,538 Code 711 funds. 
27 Includes $20,000 Code 711 funds. 
3 Includes $2,881 Code 711 funds. 
29 Includes $6,432 Code 711 funds. 
3 Includes $4,671 Code 711 funds. 
31 Includes $179,728 Code 711 funds. 
32 Cash for construction only. Excludes $164,020 expended to 
date for land condemnation. 
33 Excludes $22,517 expended to date for land condemnations. 
3 Cash for construction only. Excludes $199,410 expended to 
date for land condemnations. 
3 Includes $71,943 Code 711 funds. 
3 Includes $207,700 Code 711 funds. 
37 Includes $6,255 Code 711 funds and $40,353 Code 713 funds. 
3 Includes $68,717 Code 711 funds. 
3 Includes $315,420 Code 711 funds. 
40 Includes $67,667 Code 711 funds. 
1-32

NEW ENGLAND DIVISION 
TABLE 1-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 
Oct. 23, 1962 
Oct. 27, 1965 
July 3, 1930 
August 13, 1968 
Jan. 21, 1927 (Sec. 2) 
Included in Public 
Works Administration 
program, 
Sept. 6, 1933 
June 26, 1934 (Permanent 
Appropriations 
Repeal Act) 
Included in Public 
Works Administration 
program 
Apr. 29, 1935 
Included in Emergency 
Relief Program. 
May 28, 1935 
Aug. 30, 1935 
Mar. 2, 1945 
July 3, 1958 
June 10, 1872 
Mar. 3, 1881 
June 25, 1910 
Feb. 27, 1911 
Mar. 2, 1919 
Aug. 30, 1935 
May 24, 1937 
Mar. 2, 1945 
May 17, 19503 
July 14, 1960, 
as amended 
July 14, 1960, as 
amended 
July 14, 1960 as 
amended in 1965 
AQUATIC PLANT CONTROL (See Section I of Text). 
Control and progressive eradication of obnoxious Aquatic Plant 
growths from the waters and streams in the U.S. 
Research and planning costs to be borne by U.S. 
Provided for continued research. 
BLACK ROCK HARBOR, CT 
(See Section 2 of Text). 
Black Rock Harbor 18 feet deep and 100 to 200 feet wide from 
the 18-foot contour in harbor to the heads of both branches of 
Cedar Creek, about 2.4 miles. 
BRISTOL HARBOR, BRISTOL, RI 
(See Section 3 of Text). 
Construction of a rubblestone breakwater 1,600 feet long 
CAPE COD CANAL, MA. (See Section 4 of Text). 
Purchase canal from Boston, Cape Cod & New York 
Canal Co., in accordance with contract dated July 29, 
1921, executed by that company. 
Construct 3 bridges and widen canal to 250 feet 
Operation and care of works of improvement provided 
for the funds from War Department appropriations for 
rivers and harbors. 
Construct a mooring basin. 
Dredging and bank protection. 
Existing project for main canal adopted. 
15-foot channel and turning basin in Onset Bay. 
Extend East Boat Basin for an area of about 4.3 acres to 
a depth of 8 feet. 
CONNECTICUT RIVER BELOW HARTFORD, CT 
(See Section 5 of Text). 
Jetties at the mouth 
The Hartford dike. 
Channel and turning basin in Eightmile River. 
Present project dimensions of channel over Saybrook Bar. 
Dikes, training walls, and revetments 
Present project dimensions of channel and additional 
dikes, training walls, revetments, and accessory works. 
Park River declared nonnavigable. 
Channel and anchorages, North Cove, Old Saybrook 
Channel, anchorage, and turning basin, Eightmile River. 
Channel and anchorage in Essex Cove. 
Channel and anchorage in Wethersfield Cove. 
GREEN HARBOR, MA (See Section 6 of Text) 
Channel 6 feet deep, 100 feet wide from deep water to head 
of navigation; anchorage near town pier; sealing 
rebuilding in part and extension of existing west jetty. 
HAMPTON HARBOR, NH (See Section 7 of Text) 
Extending north jetty 1,000 feet, raising outer 300 feet 
south jetty and constructing 180-foot spur to high 
ground, channel 8 feet deep, 150 feet wide across 
entrance bar. 
H. Doc. 37, 85th Cong., 1st sess. 
Public Law 87-874, 87th Cong. 
H. Doc. 251, 89th Cong. 
H. Doc. 281, 71st Cong., 2nd sess. 
H. Doc. 174, 90th Cong., 1st sess. 
H. Doc. 139, 67th Cong., 2nd sess. 
H. Doc. 795, 71st. Cong., 3rd sess. 
Do. 
Do. 
Do. 
Rivers and Harbor Committee 
Doc. 15, 74th Cong., 1st sess. 
H. Doc. 431, 77th Cong., 1st 
sess. 
H. Doc. 168 85th Cong. 1st 
sess. 
Present project dimensions approved 
by Chief of Engineers, Dec. 22, 1887. 
Present project dimensions authorized 
by Chief of Engineers in 1889. 
H. Doc. 327, 60th Cong., 1st sess. 
H. Doc. 1294, 61st. Cong.,3rd sess. 
H. Doc. 132, 65th Cong., 1st sess.4 
H. Doc. 49, 73rd Cong., 1st sess. 
Ltr. Sec. War, Apr. 21, 1937. 
H. Doc. 368, 76th Cong., 1st sess.4 
H. Doc. 666, 80th Cong., 2nd sess. 4 
P.L. 86-645, Sec. 107, Authorized by 
Chief of Engineers, October 18, 1961. 
P.L. 86-645, Sec. 107, Authorized by 
Chief of Engineers, Nov. 15, 1960. 
P.L. 86-645, Section 107. Authorized 
by Chief of Engineers, Dec. 15, 1965. 
P.L. 86-645, Section 107. Authorized 
by Chief of Engineers, Feb. 18, 1964. 
1-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1827 
July 11, 1871 
Aug. 5, 1886 
Mar. 2, 1945 
Oct. 27, 1965 
June 13, 1902 
Mar. 2, 1907 
Mar. 4, 1913 
Oct. 17, 1940 
July 13, 1892 
June 25, 1910 
Aug. 30, 19355 
June 20, 1938 
May 17, 1950 
Aug. 2, 1882 
Mar. 3, 1899 
June 25, 1910 
July 25, 1912 
Do. 
July 3, 1930 
Aug. 30, 19357 
Mar. 2, 1945 
July 24, 1946 
Aug. 16, 1949 
Aug. 9, 1955 
June 13, 1902 
June 25, 1910 
July 27, 1916 
Aug. 26, 1937 
Oct. 22, 1976 
June 14, 1880 
June 25, 1910 
Mar. 2, 1945 
HYANNIS HARBOR, MA (See Section 8 of Text) 
Breakwater. 
Present dimensions of breakwater. 
Dredging behind breakwater. 
Channel, anchorage and jetty. 
JONESPORT HARBOR, ME. (See Section 9 of Text). 
A steel sheetpile breakwater 1200 feet in length. 
A 15-acre anchorage composed of 9-acres; 6 feet deep and 
6 acres 8 feet deep. 
An entrance channel 100 feet wide and 8 feet deep. 
KENNEBEC RIVER, ME (See Section 10 of Text). 
Channel between Augusta and Gardiner, ME 
Channel below Gardiner, ME 
Channel west of Swan Island. 
27-foot channel from mouth of Bath. 
MYSTIC RIVER, MA (See Section 11 of Text). 
Improve upper Mystic 
Improve channel downstream from mouth of Island End River 
to 35-foot channel of Boston Harbor. 
Improve channel upstream from mouth of Island End River 
to city playground at Charlestown. 
Improve channel upstream from city playground at 
Charlestown to a point 800 feet above Malden Bridge. 
Improve channel from upper limit of 35-foot Boston 
Harbor channel to Malden Bridge. 
NEW HAVEN HARBOR, CT (See Section 12 of Text) 
Sandy Point dike. 
The 16-foot anchorage basin. 
Brewery Street channel, removal of rocks in Morris Cove 
and present project dimensions of 15-foot basin. 
Present project dimensions of channels in Mill River. 
Present project dimensions of West River channel and 
anchorage. 
18- and 16-foot channels in Quinnipiac River. 
25-foot channel 
30-foot channel and anchorage and present location 
of 16-foot anchorage. 
35-foot main channel, elimination of 30-foot anchorage, 
present location and extent of 16-foot anchorage and 
22-foot channel and turning basin in Quinnipiac 
River. 
Brewery Street channel declared nonnavigable. 
Abandonment of upper end of West River. 
NEW LONDON HARBOR, CT (See Section 13 of Text). 
Waterfront channel and branch channels in Winthrop Cove 
and east of Central Vermont Railroad pier. 
Dredging in Shaws Cove. 
Entrance channel. 
Maneuvering area and present project extent of entrance 
channel. 
Deepening existing channel to 40 feet; providing a 40-acre 
turning basin 30 feet deep and a 4.9-acre maneuvering area 
32 feet deep. (Phase I Authorization) 
NEWBURYPORT HARBOR, MA. (See section 14 
of Text). 
Construction of rubblestone jetties. 
Dredging the bar at entrance to harbor. 
Dredging channel from sea to wharves and a widened 
turning basin. 
1-34 
S. Doc. 32, 18th Cong., 2nd sess. 
H. Doc. 63, 41st Cong., 2nd sess. 
H. Ex. Doc. 96, 48th Cong., 2nd 
sess. 
H. Doc. 98, 77th Cong., 1st 
sess. 4 
H. Doc. 481, 94th Cong., 2nd sess. 
Authorized by H. Res. 23 Sept. 76 and 
S. Res. 1 Oct. 76 pursuant to Sec. 201 
of cited Act. 
H. Doc. 262, 56th Cong., 1st sess.4 
H. Doc. 321, 59th Cong. 2nd sess.4 
H. Doc. 746, 62nd Cong., 2nd sess. 4 
S. Doc. 55, 77th Cong., 1st sess. 4 
Annual Report, 1891, p. 672. 
H. Doc. 1086, 60th Cong., 2nd sess. 
Rivers and Harbors Committee. 
Doc. 33, 74th Cong., 1st sess. 
H. Doc. 542, 75th Cong., 3rd sess. 
H. Doc. 645, 80th Cong., 2nd sess. 6 
Plans approved by a Board of 
Engineers, Oct. 2, 1882. 
H. Doc. 82, 55th Cong., 1st sess. 
H. Doc. 1159, 60th Cong., 2nd sess. 
H. Doc. 26, 62nd Cong., 1st sess. 
H. Doc. 535 62nd Cong., 2nd sess. 
H. Doc. 686, 69th Cong., 2nd sess. 
H. Doc. 479, 72nd Cong., 2nd sess. 
H. Doc. 307, 76th Cong., 1st sess. 
H. Doc. 517, 79th Cong., 2nd sess. 4 
H. Doc. 392, 56th Cong., 1st sess. 
H. Doc. 329, 60th Cong., 1st sess. 
H. Doc. 613, 63rd Cong., 2nd sess.4 
Rivers and Harbors Committee 
Doc. 82, 74th Cong., 2nd sess.4 
Chief of Engineers report 
dated February 20, 1975. 
Annual Report 1910, p. 59. 
H. Doc. 703, 76th Cong., 3rd sess.

NEW ENGLAND DIVISION 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sept. 16, 1890 
Mar. 2, 1907 
June 25, 1910 
Mar. 2, 1919 
June 30, 1948 
July 14, 1960, 
as amended 
June 13, 1902 
July 14, 1960 
as amended 
Mar. 3, 1871 
River and Harbor 
Act 1882 
July 14, 1960, as 
amended in 1965 
Mar. 2, 1827 
June 23, 1866 
Sept. 19, 1890 
June 25, 1910 
Mar. 3, 1925 
Aug. 30, 1935 
July 14, 1960, 
as amended 
May 17, 1951 
Sept. 3, 1954 
Oct. 27, 1965 
July 24, 1946, 
as amended. 
POINT JUDITH POND AND HARBOR 
OF REFUGE, POINT JUDITH, RI 
(See Section 15 of Text). 
The main breakwater. 
Present dimensions of eastern shore arm. 
Western shore arm. 
Removing 3 shoals from the harbor arm. 
Abandons project for entrance to Point Judith Ponds, and 
authorizes channels and anchorages in lower pond and 
upper pond. 
Extension of existing 15-foot channel. 
ROCKPORT HARBOR, MASS. (See Section 16 of Text). 
Rebuilding two breakwaters at entrance and removing 
principal rocks in harbor. 
An access channel - 10 feet deep by 80 feet wide. Two outer 
harbor anchorages between the breakwater and the 
town wharf. 
Pigeon Cove consists of 75-foot wide channel - 10 feet deep; 
dredge anchorage area north of channel to -8 feet. 
ROYAL RIVER, ME (See Section 17 of Text). 
Enlargement of channel through bar at Gravel Point and 
removal of several ledges near Yarmouth. 
Construction of 195-foot rubblestone jetty and dredging 
channel. 
8 foot channel, 80 feet wide and anchorage. 
SACO RIVER, ME (See Section 18 of Text). 
Extension of piers, placing of buoys, and removal of 
obstructions at entrance to harbor. 
Breakwater on north side of mouth of river. 
Jetty on north side of mouth of river. 
Channel improvements and jetty extension on south 
side of mouth of river. 
Present project channel dimensions and extensions 
of north breakwater about 1,600 feet. 
Extension of north breakwater to Sharps Ledge. 
Anchorage and maneuvering basin. 
LYNN-NAHANT BEACH, MA 
(See Section 23 of Text) 
Artificial placement of approximately 172,000 cubic 
yards of sand and construction of a stone mound 
along the tombolo for approximately 6,250 feet. 
REVERE BEACH, MA (See Section 24 of Text). 
Placement of sandfill for protection and improvement. 
Raising and widening of about 13,000 feet of beach by 
placement of sandfill 
BLACKSTONE RIVER, MILLBURY, MA 
(See Section 28A of Text). 
Remove existing shoal and construct stone slope 
protection along both banks of the Blackstone River 
to prevent further erosion and possible loss of 
the McCraken Road bridge. 
H. Doc. 66, 51st Cong., 1st sess. 
H. Doc. 60, 58th Cong., 2nd sess. 
H. Doc. 911, 60th Cong., 1st sess. 
H. Doc. 2001, 64th Cong., 2nd sess. 
S. Doc. 15, 80th Cong., 1st sess. 
P.L. 86-645, Section 107, Authorized by 
Chief of Engineers, Sept. 29, 1976. 
H. Doc. 363, 56th Cong., 1st sess. 
P.L. 86-645, Section 107. Authorized 
by Chief of Engineers, March 27, 1986. 
P.L. 86-645, Section 107. Authorized 
by Chief of Engineers, April 27, 1965. 
S. Ex. Doc. 44, 48th Cong., 
1st sess., and Annual Report 
1884, p. 482 
H. Doc. 752, 61st Cong., 2nd sess.4 
H. Doc. 477, 68th Cong., 2nd sess. 
Rivers and Harbors Committee. 
Doc. 11, 74th Cong., 1st sess.4 
P.L. 86-645. Section 107. Authorized by 
Chief of Engineers, Nov. 14, 1967. 
H. Doc. 134, 82nd Cong., 1st sess. 
River and Harbor Act of 1954 
dated September 3, 1954. 
H. Doc. 146, 82nd Cong., 1st sess. 
H. Doc. 211, 91st Cong., 2nd sess. 
Authorized by H. Res. 15 Dec. 70 and 
S. Res. 17 Dec. 70 pursuant to 
Section 201 of 1965 Flood 
Control Act. 
P.L. 79-526, Section 14. Authorized by 
Chief of Engineers, Nov. 29, 1984. 
1-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 24, 1946, 
as amended 
June 30, 1948, 
as amended 
Mar. 7, 1974 
June 30, 1948, 
as amended. 
July 24, 1946, 
as amended 
Aug. 13, 1968 
July 24, 1946, 
as amended 
June 30, 1948, 
as amended 
July 24, 1946, 
as amended 
July 24, 1946. 
as amended 
July 24, 1946, 
as amended 
July 3, 1958 
CLEAR RIVER, BURRILLVILLE, RI 
(See Section 28B of Text). 
Remove approximately 60 linear feet of granite 
retaining wall, damaged from erosion, and 
construct a new mortared stone wall. 
PAWTUXET RIVER, WARWICK, RI 
(See Section 28C of Text). 
Flood damage reduction through acquisition of land and 
improvements in the flood plain. Demolition and 
removal of acquired structures. Flood proofing certain 
dwellings and installing a flood forecasting system. 
CHARLES RIVER (NATURAL VALLEY STORAGE) 
AREAS), MA (See Section 28E of Text). 
Federal acquisition and perpetual protection of 17 
crucial natural valley storage areas totalling 8,422 acres 
in what is known as the Middle and Upper watershed of 
the Charles River. 
BEAVER BROOK, KEENE, NH (See Section 29C of Text). 
Construct improvements to reduce the damaging 
effects of floods. 
MILL BROOK, BROWNSVILLE, VT 
(See Section 291 of Text). 
Clear lower portion of bank and fill with compacted gravel. 
Protect bank with layer of "tri-lock" grid blocks extended 
approximately 9 feet above channel bed. 
PARK RIVER, HARTFORD, CT 
(See Section 29M of Text). 
Flood protection on Park River in Hartford, CT. 
SOUTH RIVER, CONWAY, MA (See Section 29N of Text) 
Site 2 protection consisting of 3-foot thick uniform stone 
layer; site 3 terraced slope refilled with compacted 
random fill. 
WEST SPRINGFIELD, MA 
(See Section 29S of Text). 
Raise the floodwall section of the West Springfield 
project by 1 foot in combination with a flood forecasting 
system. 
COVERED BRIDGE, HOUSATONIC RIVER, 
SHEFFIELD, MA (See Section 31 of Text). 
Construct 70-foot long stone apron. On both banks 
upstream and downstream of bridge, place 
riprap along 500 linear feet. 
GULF STREET AND TRUMBULL AVENUE, 
MILFORD, CT. (See Section 32 of Text). 
Construction of stone slope protection. 
PORT 5 FACILITY, BRIDGEPORT, CT 
(See Section 33 of Text). 
250 linear feet of graded riprap slope protection. 
NEW BEDFORD, FAIRHAVEN AND ACUSHNET, 
MA (See Section 35 of Text). 
Hurricane barriers in New Bedford Harbor. 
P.L. 79-526, Section 14. Authorized by 
Chief of Engineers, May 15, 1985. 
P.L. 80-858, Section 205. Authorized 
Chief of Engineers, July 12, 1982. 
Chief of Engineers report dated 
December 6, 1972. 
P.L. 80-858, Section 205. Authorized 
by Chief of Engineers, June 21, 1985. 
P.L. 79-526, Section 14. Authorized 
by Chief of Engineers, July 23, 1986. 
S. Doc. 43, 90th Cong., 1st sess. 
P.L. 79-526, Section 14. Authorized 
by Chief of Engineers, April 1, 1986. 
P.L. 80-858, Section 205. Authorized 
by Chief of Engineers, October 5, 1982. 
P.L. 79-526, Section 14. Authorized by 
by Chief of Engineers, July 24, 1984 
P.L. 79-526, Section 14. Authorized by 
Chief of Engineers. 
September 11, 1984. 
P.L. 79-526, Section 14. Authorized by 
Chief of Engineers, May 26, 1983. 
S. Doc. 59, 85th Cong., 1st sess. 
1-36

NEW ENGLAND DIVISION 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
NEW LONDON, CT (See Section 36 of Text). 
Oct. 23, 1962 Hurricane barrier protecting city of New London from H. Doc. 478, 87th Cong., 2nd sess. 
Oct. 22, 1976 tidal damage. 
MARGINAL WAY, OGUNQUIT, ME 
(See Section 38 of Text) 
July 24, 1946 Place 2-foot layer of armor stone along the 150-foot section P.L. 79-526, Section 14. Authorized 
as amended of walkway. Construct 150 linear feet of 42-inch thick stone by Chief of Engineers, May 7, 1986. 
slope along walkway. 
PENOBSCOT RIVER, OLD TOWN, ME 
(See Section 39 of Text). 
June 30, 1948, Modification of two existing earth dike structures. P.L. 80-858, Section 205. 
as amended Authorized by Chief of Engineers, 
May 20, 1974. 
June 30, 1948, Repair settling of the inlet and/or outlet structures P.L. 80-858, Section 205. 
as amended and reinforced concrete pipe of east Authorized by Chief of Engineers, 
and west dikes. May 16, 1985. 
PLEASANT POINT, PERRY, ME (See Section 40 of Text) 
July 24, 1946, Construct precast concrete modular wall stacked to 6-foot P.L. 79-526, Section 14. Authorized 
as amended height along 600 feet of shorefront. by Chief of Engineers, July 31, 1986. 
STAMFORD, CT (See Section 41 of Text). 
July 14, 1960 Hurricane barrier protecting areas of Stamford from tidal H. Doc. 210, 86th Cong., 1st sess. 
damage. 
Removal of one ledge inactive. 
2 Quinnipiac River 22-foot channel and turning basin deferred 
for restudy. 
SInactive. 
SContains latest maps. 
S Also Emergency Relief Act of 1935. 
6 Contains latest published map; a map showing entire river is 
in H. Doc. 2108, 64th Cong., 2nd session. 
7 Also Public Works Administration, September 6, 1933. 
1-37

TABLE 1-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1986 
Full Report Contributed 
See Annual Operation and Funds Expended 
Project Report for Construction Maintenance (Construction) 
Andrews River, MA,'615 
Apponaug Cove, RI',6 
Bagaduce River, ME3,4, 5 
Bar Harbor, ME6 
Bass Harbor, ME' 6 
Bass Harbor Bar, ME' 
Beals Harbor, ME' 
Belfast Harbor, ME' 
Bellamy River, NH1,3, 4 
Beverly Harbor, MA' 
Boothbay Harbor, ME' 
Boston Harbor, MA', 22 
Branford Harbor, CT' 
Bridgeport Harbor, CT5 
Bristol Harbor, RI 
Bucks Harbor, Machiasport, ME',6 
Bucksport Harbor, ME' 
Bullocks Point Cove, RI' 
Bunker Harbor, ME',6 
Buttermilk Bay Channel, MA',6 
Camden Harbor, ME 1' 
Canapitsit Channel, MA1, 4 
Cape Porpoise Harbor, ME' 
Carvers Harbor, Vinalhaven, ME' 
Cathance River, ME', 3 
Chatham (Stage) Harbor, MA' 
Clinton Harbor, CT' 
Coasters Island Harbor, RI', 4 
Cobscook Bay, ME1,3, 4 
Cocheco River, NH',a,4 
Cohasset Harbor, MA' 
Connecticut River (above Hartford), 
CT8 
Corea Harbor, Gouldsboro, ME' 6 
Criehaven Harbor, ME' 
Cross Rip Shoals Nantucket Sound, 
MA' 
Cuttyhunk Harbor, MA' 
Damariscotta River, ME', 4 
Deer Island Thoroughfare, ME' 4 
Dorchester Bay and Neponset 
River, MA" 
Duck Island Harbor, CT' 
Duxbury Harbor, MA' 
East Boothbay Harbor, ME' 
Eastport Harbor, ME' 
Edgartown Harbor, MA' 
Essex River, MA' 
Exeter River, NH', 4 
Fall River Harbor, MA' 
Falmouth Harbor, MA' 
Fivemile River Harbor, CT 5 
Frenchboro Harbor, ME' 
Georges River, ME' 
Gloucester Harbor and Annisquam 
River, MA' 
Great Salt Pond, Block Island, RI'5 
Greenwich Bay, RI' 
Greenwich Harbor, CT' 
Guilford Harbor, CT' 
Harbor of Refuge, Block Island, RI5 
Harraseeket River, ME', 4 
Hay (West Harbor), Fisher's 
Island, NY' 
Hendrick's Harbor, ME' 
Hingham Harbor, MA' 
Housatonic River, CT 5 
1981 
1964 
1912 
1932 
1965 
1920 
1959 
1971 
1897 
1951 
1953 
1984 
1978 
1983 
1983 
1976 
1907 
1979 
1969 
1985 
1960 
1899 
1977 
1964 
1884 
1984 
1985 
1911 
1866 
1913 
1979 
1932 
1984 
1939 
1954 
1978 
1906 
1916 
1968 
1953 
1978 
1953 
1984 
1978 
1948 
1913 
1984 
1978 
1969 
1978 
1978 
1983 
1983 
1893 
1969 
1983 
1983 
1896 
1931 
1957 
1954 
1983 
$ 219,042 
156,8742 
28,000 
406,591 
188,859 
4,076 
184,880 
61,56157 
34,643 
246,048 
18,000 
25,313,08353 
9,537 
4,491,11949 
238,288 
277,420 
18,421 
170,902 
95,372 
163,855 
102,400 
9,113 
175,037 
190,438 
21,000 
266,705 56 
104,957 
5,500 
4,173 
119,089 
267,76738 
116,324 
797,954 
40,776 
24,200 
27,167 
5,000 
40,000 
94,584 
482,166 
421,29729 
6,500 
638,67547 
65,61435 
21,759 
27,454 
6,164,75740 
123,763 
35,490 
657,345 
25,788 
1,296,93436 
189,037 
2,000 
198,758 
137,222 
576,856 
30,963 
8,401 
28,204 
28,316 
859,691 
$ 415,395 
21,679 
39 
2,187 
21,475 
12,175 
48,014 
252,763 
16,821 
22,983 
9,820,68254 
987,348 
1,976,01750 
1,654 
16,838 
13,593 
76,667 
28,406 
183,74946 
125,936 
12,279 
347,865 
9,021 
1,919,96056 
952,564 
13,161 
42,617 
219,713 
15,822 
73,150 
8,125 
54,328 
964,07452 
905 
301,944 
399,139 
798,722 
17,238 
192,624 
47,922 
83,93814 
3,032 
2,064,76751 
279,080 
188,802 
24,616 
228,937 
1,449,216 
550,235 
6,527 
204,872 
1,229,777 
1,341,954 
5,309 
30,702 
6,325 
154,272 
2,384,449 
$ 187,500 
100,000 
147,887 
123,757 
69,323 
20,000 
127,000 
11,643 
35,00030 
10,000 
35,000 
25,500 
100,000 
25,000 
222,010 
1-38

NEW ENGLAND DIVISION 
TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1986 
Full Report Contributed 
See Annual Operation and Funds Expended 
Project Report for Construction Maintenance (Construction) 
Ipswich Harbor, MA 
Island End River, Chelsea, MA, " 
Isle Au Haut Thoroughfare, ME' 
Isle of Shoals Harbor, ME and NH' 
Josias River, ME' 
Kennebunk River, ME' 
Kingston Harbor (North Plymouth), 
MA' 
Lagoon Pond, Martha's Vineyard, 
MA' 6 
Lamprey River, NH', 4 
Little Harbor, NH',4,2 " 
Little Harbor, Woods Hole, MA'"4 
Lubec Channel, ME' 
Lynn Harbor, MA' 9 
Machias River, ME' 
Malden River, MA',2- 
Matinicus Harbor, ME' 
Medomak River, ME' 
Menemsha Creek, MA' 
Merrimack River, MA' 
Mianus River, CT' 
Milford Harbor, CT5," 
Moosabec Bar, ME' 
Mystic River, CT' 
Nantucket (Harbor of Refuge), MA5 
Narraguagus River, ME' 
New Bedford and Fairhaven 
Harbors, MA5 
New Harbor, ME' 
New Haven Breakwater, CT' 
Newport Harbor, RI' 
Niantic Bay and Harbor, CT',6 
Northeast Harbor, ME' 
Norwalk Harbor, CT' 
Owl's Head Harbor, ME" 
Patchogue River, CT',22 
Pawcatuck River, Little Narragansett 
Bay and Watch Hill Cove, RI & CT5 
Pawtuxet Cove, RI' 
Penobscot River, ME' 
Pepperell Cove, ME 5 
Pig Island Gut, ME' 6 
Pleasant Bay, MA 
Pleasant River, ME' 
Plymouth Harbor, MA' 
Pollock Rip Shoals, Nantucket 
Sound, MA' 
Portland Harbor, ME' 
Portsmouth Harbor & Piscataqua 
River, ME & NH',22 
Potowomut River, RI' 
Providence River & Harbor, RI5 
Provincetown Harbor, MA 
Red Brook Harbor, Bourne. MA"" 
Richmond Harbor, ME'.4 
Richmond's Island Harbor, ME', 4 
Rockland Harbor, ME" 
Rockport Harbor, ME'.' 
Rye Harbor, NH' 
St. Croix River, ME' 
Sakonnet Harbor, RI' 
Sakonnet River, RI''" 
Salem Harbor, MA5 
Sandy Bay (Harbor of Refuge). 
Cape Ann. MA 
1969 
1983 
1980 
1977 
1977 
1985 
1895 
1976 
1913 
1977 
1906 
1956 
1956 
1972 
1922 
1962 
1953 
1981 
1940 
1985 
1981 
1930 
1957 
1965 
1969 
1953 
1966 
1950 
1953 
1972 
1954 
1983 
1968 
1984 
1978 
1975 
1985 
1969 
1966 
1971 
1892 
1978 
1956 
1985 
1984 
1882 
1976 
1985 
1972 
1883 
1882 
1976 
1915 
1965 
1950 
1983 
1909 
1969 
1922 
5,618 
311,850 
137,653 
80,691 
115,565 
261,417 
8,940 
99,098 
19,980 
133,227 
18,000 
380,322 
755,576 
32,000 
104,853 
14,00021 
17,000 
56,926 
369,891 
132,435 
90,50658 
11,400 
197,582 
502,66123 
821,144 
1,857,618 
118,62024 
1,242,246 
733,524 
66,464 
138,942 
531,12939 
124,158 
355,445 
318,78731' 
295,356 
501,020 
171,351 
191,753 
3,500 
2,127,21832,31 
1,083,504 
9,588,71027 
5,384,04312 
5,000 
25,417,02228 
3,548,9544' 
38,764 
20,000 
119,844 
1,948,462 
32,000 
130,342 
179,550 
764,651 
38,427 
1,693,202 
1,925,553 
1-39 
32,947 
161,586 
643,364 
122,173 
1,234,403 
8,940 
33,563 
266,119 
5,224 
23,941 
206,203 
185,217 
45,097 
8,989 
92,359 
629,181 
158,224 
659,390 
679,75959 
25,227 
104,932 
444,606 
71,087 
708,967 
26,944 
40,273 
128,223 
71,570 
51,032 
3,723,52042 
13,867 
621,988 
655,185 
152,105 
837,447 
26,553 
43,863 
217 
924,9013
4 
846,590 
7,903,331 
1,936,959 
50 
3,830,502 
1,053,966 
1,808 
452,800 
54,520 
128,453 
36,392 
180,016 
9,549 
390,326 
16,060 
314,50048 
26,813 
88,917 
80,990 
62,000 
12,500 
46,500 
11,380 
14,000 
20,385 
7,015 
67,500 
34,500 
4,383 
56,694 
20,000 
295,356 
541,611 
99,707 
760,000 
255,000 
61,338'
7 
19,892 
21,928

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1986 
Full Report Contributed 
See Annual Operation and Funds Expended 
Project Report for Construction Maintenance (Construction) 
Sasanoa River, ME' 3,4 1915 35,000 124 
Scarboro River, ME' 1976 392,635 1,239,293 10,000 
Scituate Harbor, MA' 1971 379,851 130,391 69,976 
Searsport Harbor, ME' 1966 572,56816 31,120 
Seekonk River, RI' 1954 672,214 793,234 67,792 
Sesuit Harbor, MA'",6 1983 226,306 24,704 124,588 
South Bristol Harbor, ME' 1971 89,593 11,052 2,663 
Southport Harbor, CT' 1962 96,9277 231,489 18,525 
Southwest Harbor, ME' 1962 180,042 66,540 7,501 
Stamford Harbor, CT5 1980 892,82437 1,683,02045 169,636 
Stockton Harbor, ME',:, 4 1915 33,000 23,216 
Stonington Harbor, CT' 1959 377,328 123,060 
Stonington Harbor, ME'," 1985 898,500 5,067 
Stony Creek, Branford, CT'," 1978 112,487 274,598 92,000 
Sullivan Falls Harbor, ME' 1914 19,871- 
Taunton River, MA5 1948 442,895 32,917 
Tenants Harbor, ME' 1920 18,750 13,292 
Thames River, CT" 1967 1,471,919 1,527,151 
Union River, ME,1' 1912 146,855 119,511 
Vineyard Haven, MA' 1943 27,186 8,699 
Wareham Harbor, MA 5 1896 95,997 10,296 
Warren River, RI' 1890 5,000- 
Warwick Cove, R'11,6 1975 155,430 51,196 107,220 
Wellfleet Harbor, MA' 1981 157,63425 894,584 32,000 
Wells Harbor, ME' 1979 360,973 1,554,836 212,000 
Westcott Cove, CT' 1978 55,960 217,309 21,000 
Westport Harbor and 
Saugatuck River, CT5 1972 19,308 180,824 
Westport River, MA4,9 1942 -- 
Weymouth Back River, MA' 1944 48,740 7,184 20,000 
Weymouth-Fore & Town Rivs., MA',22 1979 and 1983 30,194,61343 1,339,06844 630,133 
Wickford Harbor, RI', 22 1973 233,410 70,435 49,094 
Wilson Point Harbor, CT',4 1895 54,177- 
Winnipesaukee Lake, NH' 1952 7,500 29,870 
Winter Harbor, ME'1,6 1976 162,937- 
Winthrop Harbor, MA' 1895 8,992 38,515 
Wood Island Harbor, and 
Pool at Biddeford, ME' 1957 143,112 14,707 12,000 
Woods Hole Channel, MA' 1940 230,000 51,718 
York Harbor, ME' 1977 239,654 351,090 32,161 
' Completed. 
2 Excludes costs of $137,583 for local cooperation requirements, 
which includes $104,583 cash contribution. 
3 Abandonment recommended in H. Doc. 467, 69th Congress, 
1st session. 
4 No commerce reported. 
5 Completed except for inactive portion. 
6 Authorized by the Chief of Engineers (Public Law 86-645, 
Sec. 107). 
7 Includes $37,714 Emergency Relief Funds. Excludes $18,525 
Contributed Funds, of which $1,785 was for work outside approved 
project. 
R Inactive. 
9 Awaiting local cooperation. Improvement to be restudied. 
'o Commerce included under Tiverton Harbor, RI. 
1 Authorized work remaining on project is comprised of an 
incomplete and an inactive portion. 
12 Includes $130,393 for previous projects. 
'3 Recommendation for abandonment of existing project 
made in H. Doc. 467, 69th Congress 1st session. Portion of project 
authorized by the Chief of Engineers (P.L. 86-645, Sec. 107) is 
complete. 
14 Excludes $5,000 Contributed Funds expended. 
'5 Improvement adequate for commerce. 
16 Costs to local interests for berth improvements are estimated 
to be $60,000. 
'7 Excludes $81,548 Contributed Funds "Other" expended. 
18 Abandonment recommended in H. Doc. 411, 64th Congress, 
1st session, and in River and Harbor Committee Doc. 3, 65th 
Congress, 1st session. 
9 Improvement to be restudied. 
20 Under State maintenance. 
21 Excludes $114,327 expended for rehabilitation; breakwater 
repaired in 1962. 
22 Portion of project authorized by Chief of Engineers. 
23 Excludes $211,649 expended for rehabilitation; jetty 
repaired in 1963. 
24 All assurances of local cooperation have not been fulfilled. 
Public landing at Back Cove has not been constructed. Portion of 
project authorized by Chief of Engineers (Public Law 86-645, Sec. 
107).
25 Includes $11,350 for previous project. 
26 H. Doc. 467, 69th Cong., 1st sess. recommended eliminating 
maintenance dredging. 
1-40

NEW ENGLAND DIVISION 
TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
27 Includes $692,435 for previous projects. 
28 Final fund adjustment made FY 1978 ($52,323.28). 
29 Includes $37,000 for new work for previous project. 
3� Excludes local requirementsof$65,000consistingof$13,000 
for public wharf and $52,000 for additional construction costs. 
.' Includes $133,357 for previous project. 
32 Includes $188,647 for previous project. 
SExcludes $894,475 major rehabilitation for Long Beach 
Dike. 
:4 Includes $2,013 for previous projects. In addition $400 
was expended for maintenance from Contributed Funds. 
; Includes $15,614 for new work for previous projects. 
� Includes $21,000 for previous projects. 
SIncludes $135,143 for previous project. 
:; Includes $10,000 for previous project. 
y Includes $162,517 for previous project. 
SIncludes $330,204 for previous project. 
41 Includes $215,801 for previous project. 
42 Includes $66,120 for previous projects. 
4 Includes for previous projects $735,900 (Weymouth, Fore 
R.) and $25,000 (Town R.). 
44 Includes for previous project $5,250 (Weymouth, Fore 
River and $12,577 (Weymouth Town River). 
45 Includes $59,420 for previous project. 
46 Includes $35,214 from previous project. 
47 Excludes $141,530 expended Contributed Funds. Other. 
48 Excludes $829,000 Contributed Funds "Other" expended. 
49 Includes $378,450 for previous project. 
so Includes $11,949 for maintenance of previous project. 
s' Includes $81,410 for previous project. 
52 Excludes $50,000 Contributed Funds expended for maintenance. 
53 Includes $1,465,123 for previous projects. Includes 
$935,303 Emergency Relief Funds and $1,030,806 Public Works 
Funds. 
54 Includes $17,879 for previous projects. Excludes $17,767 
Contributed Funds. 
5 Includes $7,889 for previous project. 
5�6 Includes $83,276 for maintenance of previous project. 
57 Includes $22,000 for previous projects. 
5 Includes $42,340 for previous project. 
59 Includes $3,160 for previous project. 
1-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 1-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
For Last 
Full Report Cost to Amount 
See Annual Sept. 30, 1986 Expended by 
Project Report For Construction Local Interest 
Burial Hill Beach, Westport, CT' 1958 $ 5,810 $ 11,612 
Calf Pasture Beach Park, Norwalk, CT' 1964 56,386 120,179 
Clark Point Beach, New Bedford, MA' 1982 228,081 228,080 
Cliff Walk, Newport, RI7 1984 405,491 955,237 
Compo Beach, Westport, CT' 1962 84,544 169,089 
Cove Island, Stamford, CT' 1961 47,131 94,262 
Cummings Park, Stamford, CT' 1963 26,886 53,771 
Guilford Point Beach (Jacobs Beach), Guilford, CT' 1961 15,620 31,241 
Gulf Beach, Milford, CT' 1958 21,303 42,606 
Hammonasset Beach, Madison, CT' 1956 163,183 326,366 
Hampton Beach, Hampton, NH' 1966 260,868 385,641 
Jennings Beach, Fairfield, CT' 1956 14,401 28,802 
Lighthouse Point Park (Area 9), CT' 1961 3,930 7,859 
Lynn-Nahant Beach, MA 1986 50,000 - 
Middle Beach, CT' 1958 8,810 17,620 
Misquamicut Beach, Westerly, RI3 1963 14,512 29,024 
Nantasket Beach, MA4 1971 - - 
North Scituate Beach, Scituate, MA' 1969 106,552 106,552 
Oak Bluffs Town Beach, Martha's Vineyard, MA' 1976 273,334 198,583 
Oakland Beach, Warwick, RI' 1982 559,200 181,175 
Plum Island, MA' 1977 118,882 104,875 
Prospect Beach, West Haven, CT' 1958 104,573 240,819 
Quincy Shore Beach, Quincy, MA' 1962 621,440 1,242,880 
Sand Hill Cove Beach, RI' 1959 40,143 82,000 
Sasco Hill Beach, Fairfield, CT' 1961 23,759 47,518 
Seaside Park, CT' 1958 150,000 329,921 
Sherwood Island State Park, Westport, CT' 1983 1,186,830 889,330 
Short Beach, CT' --- - 
Silver Beach to Cedar Beach, CT 1964 62,560 270,695 
Southport Beach, CT' 1960 17,631 35,263 
Town Beach, Plymouth, MA 1964 5,490 10,981 
Town Neck Beach, Sandwich, MA8 1961 - - 
Wallis Sands State Beach, Rye, NH' 1966 65,131 435,942 
Wessagusset Beach, Weymouth, MA' 1971 180,944 200,208 
Willard Beach, South Portland, ME 1983 171,000 - 
Winthrop Beach, MA' 1960 176,5676 353,134 
Woodmont Shore, Milford, CT' 1961 53,838 111,6792 
S Completed. 
2 Excludes $118,215 expended for work beyond scope of 
project. 
3 Additional Federal participation will be required based 
on Public Law 87-874. 
4 Project inactive. 
5 Project completed at no cost to Federal Government by 
using fill from Federal navigation improvement at Housatonic Riv 
6 Project is complete. There are three additional groins, 
construction of which is deferred until it is determined that they 
are necessary. 
7 Completed except for inactive portion. 
S Project inactive; Federal costs of $1,500.00 were incurred 
for preauthorization survey. 
1-42

NEW ENGLAND DIVISION 
TABLE 1-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Contributed 
Project Report for Construction Funds 
Alley Bay, Beals, ME 3,4,1 0� 
Alford, Green River, MA 3,4 
Amesbury, Powwow River, MA 3,4 
Ansonia-Derby, CT 3 
Bagaduce River, ME3,4,'o 
Bound Brook, Scituate, MA 3,4 
Canton, MA 3,4 
Charles River Dam, MA 3 
Charlestown, NH 3,4 
Cherryfield, ME 3,4 
Chicopee, MA 3 
Chicopee Falls, MA 3 
Cocheco River, NH 3,4 
Connecticut River, North Stratford, NH 3,4 
Connecticut River, W. Stewartstown, NH 3,4 
Danbury, CT3 
Derby, CT3 
East Branch Dam, CT 3 
East Hartford, CT 3 
Fitchburg, MA (See No. Nashua River) 
Folly Brook, Wethersfield, CT3,4 
Fort Kent, ME 3,4 
Fox Point Barrier, RI3 
Gardner, MA3,4 
Hall Meadow Brook Dam, CT 3 
Hartford, CT3 
Hartford, White River, VT3,4 
Hayward Creek, Braintree-Quincy, MA3,4 
Holmes Bay, Whiting, ME 3,4, '� 
Holyoke, MA 3 
Housatonic River, Pittsfield, MA 3,4 
Housatonic River, Salisbury, CT 3,4,'0 
Housatonic River, Sheffield, MA 3,4,1� 
Huntington, MA 3,4'�, 
Island Avenue, Quincy, MA 3,4 
Islesboro (The Narrows), ME 3,4'�, 
Johnson Bay, Lubec, ME 3,4,' � 
Keene, NH3,4 
Lancaster, Israel River, NH3,4 
Lee, Housatonic River, MA:3,4', 
Lincoln School Lake, ME 
Little River Dike, Westfield, MA 3 
Lowell, MA 3 
Lower Woonsocket, RI3 
Mad River Lake, CT3 
Merriconeag Sound, Harpswell, ME 3 , ' 
Monoosnoc Brook, MA ' 3 
Monoosnoc Lake, MA '" 
Nashua, NH3 
Nonewaug River, Woodbury, CT3,4,1' 
Nookagee Lake, MA 
Northampton, MA:3 
North Canaan, Blackberry River, CT3,4 
North Nashua River, Fitchburg, MA 3 
North Nashua River, Lancaster, MA 3,4,'0 
Norwalk, CT3,4 
Norwich, CT3 
Pawcatuck, CT:3 
Phillips Lake, MA 
Prestile Stream, Blaine, ME:34.'" 
Riverdale, MA3 
Salmon River, Colchester, CT3 4 
Sand Cove, Gouldsboro, ME 
Saxonville, MA3 
Sebasticook River, Hartland, ME:I,4 
Shelburne, Androscoggin River, NH'" 
Smelt Brook, Weymouth-Braintree, MA:3,4 
Springdale. MA3 
1979 
1977 
1978 
1977 
1985 
1974 
1964 
1981 
1976 
1963 
1954 
1978 
1963 
1982 
1976 
1978 
1977 
1973 
1951 
1979 
1979 
1976 
1970 
1970 
1960 
1973 
1979 
1980 
1953 
1985 
1982 
1981 
1960 
1983 
1985 
1985 
1955 
1982 
1976 
1984 
1945 
1977 
1973 
1980 
1967 
1967 
1950 
1985 
1976 
1950 
1977 
1981 
1979 
1952 
1960 
1966 
1982 
1980 
1952 
1983 
1984 
1981 
1985 
1977 
1978 
1952 
$ 190,500 
41,419 
132,113 
18,266,040 
129,500 
47,300 
180,6705 
41,170,921 
113,330 
203,000 
1,433,6007 
2,183,912 
183,100 
180,000 
54,703 
13,143,000 
7,582,642 
1,959,836 
2,135,447 
220,284 
1,997,820 
11,112,801 
495,691 
2,572,357 
6,094,1009 
332,236 
2,235,470 
207,390 
3,418,000 
739,003 
102,800 
202,608 
3,900 
172,000 
165,500 
163,082 
44,100 
551,606 
37,852 
13,155,29826 
5,000 
490,600" 
6,600,681 
4,773,020 
107,681 
270,0008 
222,500 
563,677 
680,000' 
7 
73,865 
3,235,00023 
81,671 
52,150 
1,209,000 
644,311 
300,000 
73,674 
1,138,000 
247,100 
127,500 
4,218,700 
1,857,475 
37,657 
1,803,739 
700,000 
1-43 
$-
- 
21 
92,891 
5,554,087'1s 
385 
411,29222 
- 2
19 
7,637 
4 
3,679,500' 4 
15,500 
2,781,100 
24,447 
- 25 
1,266,63820 
327 
214,106 
25,00 
24

TABLE 1-E 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Contributed 
Project Report for Construction Funds 
Springfield, MA 3 1950 577,00018 5,350 
Squantz Pond, New Fairfield, CT34 1983 116,296 - 
Stony Brook, Wilton, NH3, 4 1973 19,500 - 
Sucker Brook Dam, CT3 1976 2,227,712 58,800 
Three Rivers, MA 3 1970 1,577,18912- 
Torrington, East Branch, CT 34 1963 389,200 - 
Torrington, West Branch, CT3,4 1963 228,300 - 
Trumbull Lake, CT' 1983 1,498,799 - 
Village of Saxtons, VT3,4,1 1985 140,500 - 
Ware, MA3 4 1963 400,000 - 
Waterbury-Watertown, CT34 1963 263,300 - 
Westerly, RI 1966 - - 
Weston, VT34 1957 13,000 1,800 
West Branch, Westfield River, Huntington, MA 3 ,4 1983 116,492 - 
West Springfield, MA3 1954 1,334,00016- 
West Warren, MA34 1964 389,200 41,000 
Whitmanville Lake, MA 1979 605,023 - 
Winsted, CT 3 1954 245,500 - 
Woonsocket, RI3 1962 4,040,000 224, 500 
Worcester Diversion, MA 3 1978 5,086,859 79,300 
I Inactive. 15 Excludes $1,674,567 Contributed Funds, Other. 
2 Excludes $1,146,828 expended from Contributed Funds, 16 Excludes $245,000 Public Works Administration funds. 
Other. 17 Excludes $280,000 Public Works Administration funds. 
3 Completed. 18 Excludes $355,000 Public Works Administration funds. 
Authorized by Chief of Engineers. 19 Excludes $406,653 Contributed Funds, Other. 
5 Reflects FY1967 settlement of outstanding claims. 20 Excludes $488,920 Contributed Funds, Other. 
6 Completed except for inactive portion. 21 Excludes $727,460 Contributed Funds, Other. 
7 Includes $295,000 Public Works Administration funds. 22 Excludes $12,000 expended for land condemnations and 
8 Excludes $147,366 Flood Control and Coastal $25,184 Contributed Funds, Other for relocations. 
Emergency funds expended. 23 Excludes $1,370,000 Public Works Administration funds 
9 Excludes $835,000 Public Works Administration funds. expended on Fitchburg, MA. 
1o Emergency Bank Protection. 24 Excludes $8,503 Contributed Funds, Other. 
" Excludes $794,374 Public Works Administration funds. 25 Excludes $3,000 Contributed Funds, Other. 
12 Excludes $565,168 Contributed Funds, Other. 26 Dickey Lake portion deauthorized; costs shown reflect 
13 To be restudied. combined Dickey-Lincoln School effort. 
'4 Cash for construction only. Excludes $245,000 expended 
for land condemnation. 
TABLE 1-F OTHER AUTHORIZED MULTI-PURPOSE PROJECTS 
INCLUDING POWER 
For Last Cost to September 30, 1986 
Full Report 
See Annual Contributed 
Project Report for Construction Funds 
Passamaquoddy Tidal Power Project, ME' 1935 6,384,394 -- 
I Work discontinued in 1937. Facilities transferred to War Assets Administration. 
1-44

NEW ENGLAND DIVISION 
TABLE 1-G DEAUTHORIZED PROJECTS 
For Last Funds Expended 
Full Report 
See Annual Date Contributed 
Project Report For Deauthorized Federal Funds 
Alternative for Sugar Hill Reservoir - Aug 1977 $ - $ - 
Andover Lake, CT - Aug 1977 -- 
Bagaduce River, ME (uncompleted portion) - Oct 1978 - - 
Baker Brook, MA 1972 Nov 1979 94,000 - 
Beards Brook Reservoir, NH 1949 Aug 1977 78,000- 
Beaver Brook Lake, NH 1973 Apr 1978 378,300 - 
Bennington Reservoir, NH 1949 Aug 1977 205,000 - 
Brant Rock Beach, Marshfield, MA 1961 Nov 1979- 
Bridgeport Harbor, CT (uncompleted portion) 1980 Nov 1979 - - 
Brockway Lake, VT 1946 Aug 1977- - 
Cambridgeport Lake, VT - Aug 1977- - 
Chicopee, MA (uncompleted portion) 1954 Aug 1977 - - 
Claremont Lake, NH 1968 Dec 1970 242,700 - 
Clyde, RI 1948 Apr 1951 8,800- 
Connecticut River below Hartford 1979 Oct 1978 - - 
CT (uncompleted portion) 
Cotuit Harbor, MA 1962 Oct 1978 8,541- 
Dickey Lake, ME 1983 Dec 1981 13,130,000' - 
Fivemile River Harbor, CT (uncompleted portion) 1969 Oct. 1978 - - 
Gaysville Lake, VT 1970 Oct 1976 206,600 - 
Greenwich Point Beach, CT 1959 Oct 1978 - - 
Housatonic River, CT (uncompleted portion) 1979 Nov 1979 - - 
Honey Hill Lake, NH 1949 Aug 1977 92,000- 
Ludlow Lake, VT - Aug 1977 - - 
Manchester Harbor, MA 1949 Nov 1979 23,986- 
Marblehead Harbor, MA 1968 Oct 1978 43,711 
Mattapoisett Harbor, MA 1950 Oct 1978 - - 
Mountain Brook Dam, NH 1949 Aug 1977 57,000 
Mystic, CT 1968 Aug 1972 67,700- 
Napatree Beach, RI - Nov 1979- - 
Narragansett Pier, RI 1966 Nov 1970 115,590 - 
North Andover and Lawrence, MA 1949 Aug 1977 20,000 - 
North Hampton Beach, North Hampton, NH 1963 Nov 1981 - - 
Norwalk-Wilton, CT 1973 Nov 1979- 
Pawcatuck River, RI & CT (uncompleted portion) 1979 Nov 1979 -- 
Pawtucket, RI 1949 Nov 1977 -- 
Pepperell Cove, ME (uncompleted portion) 1969 Nov 1981 - - 
Point Judith, RI 1968 Nov 1977 198,477 - 
Pontiac Diversion, RI 1948 Apr 1951 24,200- 
Provincetown Beach (Herring Cove), MA 1961 Oct 1978 -- 
Provincetown Harbor, MA (uncompleted portion) 1979 Oct 1978 -- 
Saco River, ME (uncompleted portion) 1979 Oct 1979 - - 
Sakonnet Harbor, RI (uncompleted portion) 1982 Jun 1982 176,000 - 
Sandy Bay, Cape Ann, MA (uncompleted portion) 1922 Oct 1978- - 
South Coventry Lake, CT 1951 Aug 1977 96,000- 
South Tunbridge Lake, VT - Aug 1977 - - 
Stamford Harbor, CT (2 projects 
uncompleted portions) 1979 Oct 1978 - - 
Stonington Harbor, ME 1961 Nov 1979 2,543 - 
Stratford, CT 1973 Mar 1977 934,500 - 
Sugar Hill Reservoir, NH 1946 Dec 1944 - - 
The Island Lake, VT - Aug 1977 - - 
Thumperton Beach, Eastham, MA 1961 Nov 1979 - - 
Wareham-Marion, MA 1965 Aug 1977 81,715 - 
Victory Lake, VT 1967 Aug 1977 168,400 - 
West Brookfield Reservoir, MA 1948 July 1960 67,000 - 
West Canaan Lake, NH 1948 Aug 1977 92,000 - 
Westfield, MA 1967 Sep 1969 507,200 - 
Westport, CT 1965 Feb 1970 29,634 - 
Westport Harbor and Saugatuck River, CT 1972 Nov 1979 
(uncompleted portion) 
Williamsville Reservoir, VT 1949 Dec 1944 146,500 
1 For Dickey-Lincoln School Lakes Project. 
1-45

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 1-H 
Study Identification 
NAVIGATION ACTIVITIES PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645 (PREAUTHORIZATION) 
Fiscal Year 
Costs 
Bass Harbor, Tremont, ME 
Bass River, MA 
Gloucester Harbor, Gloucester, MA 
Green Harbor, Marshfield, MA 
Harraseeket Inner Harbor, MA 
Nantucket Inner Harbor - Polpis, MA 
North Cove, Old Saybrook, CT 
Patten Bay, ME 
Perkins Cove, Ogunquit, ME 
Pine Point Harbor, Scarborough, ME 
Pines River, Revere, MA 
Point Judith Pond, RI 
Rockport and Old Harbors, MA 
Saugus and Pine Rivers, MA 
Scituate Harbor, MA 
Stonington Harbor, CT 
Weymouth Back River, Weymouth, MA 
Winthrop Harbor, Winthrop, MA 
Wood Island Harbor, Biddeford, ME 
TABLE 1-I 
Study Identification 
BEACH EROSION ACTIVITIES PURSUANT TO SECTION 103, 
PUBLIC LAW 78-874 (PREAUTHORIZATION) 
Fiscal Year 
Costs 
Belfast City Park, Belfast, ME 
City Point Beach, South Boston, MA 
Conimicut Beach, Warwick, RI 
Constitution Beach, East Boston, MA 
Cornhill Beach, Truro, MA 
Kennebunk Beach, Kennebunk, ME 
Pleasure Bay Beach, South Boston, MA 
Prospect Beach, West Haven, CT 
Sea Gull Beach, Yarmouth, MA 
Seaview and Parkers Rivers, MA 
South End Beach, Rockland, MA 
Tenean Beach, Dorchester, MA 
Town Beaches, CT 
Wollaston Beach, Quincy, MA 
West Haven Beaches, CT 
Woodmont Beach, CT 
$17,340 
43,870 
28,169 
26,375 
7,500 
56,976 
15,829 
7,500 
14,971 
27,478 
4,431 
52,363 
47,420 
40,734 
21,736 
16,445 
260 
29,362 
29,717 
$ 160 
6,500 
54,465 
2,600 
192 
39,357 
2,700 
55,590 
18,647 
298 
10,300 
6,500 
14,243 
2,700 
17,401 
61,088 
1-46

NEW ENGLAND DIVISION 
TABLE 1-J FLOOD CONTROL ACTIVITIES PURSUANT TO SECTION 205, 
PUBLIC LAW 80-858 (PREAUTHORIZATION) 
Study Identification 
Aroostook River, Fort Fairfield, ME 
Baker Brook, Fitchburg, MA 
Blackstone River, Cumberland, RI 
Blind Brook, Danbury, CT 
Connecticut River, Lebanon, NH 
Freshwater Brook, Enfield, CT 
Hobarts Pond, Whitman, MA 
Industrial Area, Waterbury, CT 
Mad River, Waterbury, CT 
Pawtuxet River, West Warwick, RI 
Point of Pines, Revere, MA 
Quinnipiac River, Wallingford, CT 
Rippawam River, Stamford, CT 
Riverdale, MA 
Saugus River, Reedy Meadows, Lynnfield, MA 
Souhegan River, Milford, NH 
Tankerhoosen River, Vernon, CT 
Ten Mile River, Cheshire, CT 
Wepawaug River, Milford, CT 
West River, New Haven, CT 
Winnipesaukee River, NH 
TABLE 1-K BLACKSTONE RIVER BASIN, MA AND RI 
(See Section 28 of Text) 
RESERVOIR 
Miles 
Above Estimated Federal Cost 
Mouth of 
Black- Reservoir Lands 
stone Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total 
West Hill2 Worcester, MA 25.8 51 Earthfill 12,400 $1,366,902 $940,000 $2,306,902 
I Includes highway, railroad, and utility relocations. 
2 See individual report for details. 
1-47 
Fiscal Year 
Costs 
$146,517 
24,065 
2,454 
2,000 
7,500 
3,800 
7,500 
28,441 
63,077 
49,316 
69,405 
43,424 
33,824 
7,125 
6,500 
5,000 
6,500 
18,457 
16,811 
79,088 
133,406

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 1-K (Continued) LOCAL PROTECTION PROJECTS 
Miles 
Above Estimated Cost 
Mouth of 
Black- Lands 
stone and 
Location River Type of Structure Construction Damages1 Total 
Worcester, MA 48 Diversion tunnel and channel $4,923,500 $1,179,0002 $6,102,500 
Woonsocket, RI 15 Channel improvement 3,740,100 1,069,0003 4,809,100 
Lower Woonsocket, RI 13 Flood wall, conduits and 
channel improvement 8,356,239 435,000 8,791,239 
Blackstone River, Millbury, MA 32 Slope protection 250,000 - 250,000 
Clear River, Burrillville, RI 23 Retaining wall 180,000 - 180,000 
Pawtuxet River, Warwick, RI - Land acquisition 3,300,000 - 3,300,000 
1 Includes relocations. 
2 $158,000 Federal; $1,021,000 non-Federal. 
3 $300,000 Federal; $769,000 non-Federal. 
TABLE 1-L CONNECTICUT RIVER BASIN, VT, NH, MA AND CT 
(See Section 29 of Text) 
DAMS AND RESERVOIRS 
Miles 
Above Estimated Federal Cost 
Mouth of 
Conne- Reservoir Lands 
cticut Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages1 Total 
Vermont: 
Union Village2 White River 228.4 170 Earthfill 38,000 $3,186,860 $ 908,300 $4,095,160 
Junction 
North Hartland 2 White River 211.7 185 Earthfill 71,400 6,349,225 963,000 7,312,225 
Junction 
North Springfield 2 Springfield 191.3 120 Earthfill 50,600 4,781,526 2,050,000 I 6,831,526 
Ball Mountain2 Brattleboro 178.2 265 Rockfill- 54,600 10,689,298 350,000 11,039,298 
earth 
Townsend 2 Brattleboro 168.3 133 Earthfill 33,200 5,520,413 1,878,000 7,398,413 
New Hampshire: 
Surry Mountain 2 Keene 174.4 86 Earthfill 32,500 2,448,610 385,000 2,833,610 
Otter Brook 2 Keene 171.2 133 Earthfill 18,300 2,982,048 1,378,400 4,360,448 
Massachusetts: 
Birch Hill2 Gardner 153.3 56 Earthfill 49,900 1,740,679 3,075,000 4,815,679 
Tully2 Athol 148.7 62 Earthfill 22,000 1,298,752 368,000 1,666,752 
Barre Falls2 Worcester 130.2 62 Rockfill- 24,000 1,928,819 39,000 1,967,819 
earth 
Knightville 2 Northampton 102.8 160 Earthfill 49,000 2,594,440 821,200 3,415,640 
Littleville 2 Northampton 102.0 150 Earthfill 32,400 5,863,412 1,150,000 7,013,412 
Conant Brook2 Springfield 122.0 85 Rockfill- 3,740 1,935,530 1,015,000 2,950,530 
earth 
Connecticut: 
Colebrook River 2 Winsted 116.0 223 Rockfill- 98,500 8,341,971 5,922,000 14,263,971 
earth 
Mad River Winsted 120.0 178 Earthfill 9,700 4,773,020 2,210,0004 6,983,020 
Sucker Brook Winsted 118.5 68 Earthfill 1,480 2,227,712 180,0003 2,407,712 
1 Tnl,id hiohwav railrnad and utility rplocatinns 3 Nnn-Fpdprnl en.t 
2 or d a l s, ,.se e. r, t .iv 
2 For details, see individual report. 4 Non-Federal $670,000; Federal $1,540,000. 
1 4IQ

NEW ENGLAND DIVISION 
TABLE 1-L (Continued) LOCAL PROTECTION PROJECTS 
Miles 
Above Estimated Cost 
Mouth of 
Conne- Lands 
cticut and 
Location River Type of Structure Construction Damages' Total 
Charlestown, NH 181 Riverbank protection $ 113,330 - $ 113,330 
Chicopee, MA 80 Wall and levee 1,434,000 $ 250,000 1,684,000 
Chicopee Falls, MA 83 Wall and levee 2,600,000 70,000 2,670,000 
East Hartford, CT 52 Wall and levee 2,135,447 271,000 2,406,447 
Folly Brook, Wethersfield, CT 50 Channel improvement 220,284 - 220,284 
Gardner, MA 163 Dam and levee 495,691 35,000 530,691 
Hartford, CT 52 Wall and levee 6,930,000 1,150,000 8,080,000 
Hartford, VT 216 Channel improvement 332,236 - 332,236 
Holyoke, MA 85 Wall and levee 3,418,000 150,000 3,568,000 
Huntington, MA 100 Riverbank protection 3,900 - 3,900 
Israel R., Lancaster, NH 314 Gabion overflow weir 551,606 - 551,606 
Keene, NH 167 Channel improvement 44,100 - 44,100 
Northampton, MA 94 Wall and levee 960,0005 150,000 1,110,000 
North Stratford, NH 345 Slope protection 180,000 - 180,000 
Park River, CT2 51 Conduit 60,164,740 1,300,000 61,464,740 
Riverdale, MA 80 Wall and levee 1,138,000 50,000 1,188,000 
Salmon R., Colchester, CT 38 Slope protection 247,100 - 247,100 
Springdale, MA 84 Wall and levee 700,000 57,000 757,000 
Springfield, MA 76 Wall and levee 932,0006 272,000 1,204,000 
Three Rivers, MA 98 Wall and levee 1,577,189 700,000 2,277,189 
Ware, MA 110 Channel improvement 400,000 85,000 485,000 
Weston, VT 195 Channel improvement 13,000 2,000 15,000 
West Springfield, MA 76 Wall and levee 1,579,0003 30,000 1,609,000 
West Warren, MA 111 Wall and levee 389,200 64,000 453,200 
Winsted, CT 115 Channel improvement 245,500 30,000 275,500 
1 To be borne by local interests. Also includes local interests " Includes $835,000 Public Works Administration funds. 
portion of relocation. 5 Includes $280,000 Public Works Administration funds. 
2 For details see individual report. 6 Includes $355,000 Public Works Administration funds. 
3 Includes $245,000 Public Works Administration funds. 
TABLE 1-M HOUSATONIC RIVER BASIN, CT AND MA 
(See Section 30 of Text) 
DAMS AND RESERVOIRSi 
Miles 
Above Estimated Federal Cost 
Mouth of 
Nagua- Reservoir Lands 
tuck Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages 2 Total 
Hall Meadow 4 Torrington, CT 41.0 73 Rock and 8,620 $2,572,357 $1,290,0003 $3,862,357 
earthfill 
East Branch' Torrington, CT 43.7 92 Earthfill 4,350 1,959,836 1,290,0003 3,249,836 
Thomaston Torrington, CT 30.5 142 Rock and 42,000 6,382,112 7,900,000 14,282,112 
earthfill 
Northfield Brook Torrington, CT 30.6 118 Earthfill 2,432 1,875,512 975,000 2,850,512 
Black Rock Waterbury, CT 29.0 154 Earthfill 8,700 5,223,700 2,958,600 8,182,300 
Hancock Rock Waterbury, CT 25.0 57 Earthfill 4,030 1,593,911 2,585,000 4,178,911 
Hop Brook Waterbury, CT 15.9 97 Earthfill 6,970 2,701,562 3,450,000 6,151,562 
1 For details of projects, see individual reports. 
2 Includes highway, railroad, and utility relocations. 
3 Includes cost of lands borne by local interests. 
4 For last full report, see Annual Report for 1970. 
5 For last full report, see Annual Report for 1973. 
1-49

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 1-M (Continued) LOCAL PROTECTION PROJECTS' 
Miles 
Above Estimated Cost 
Mouth of 
Housa- Lands 
tonic and 
Location River Type of Structure Construction Damages2 Total 
Alford, Green River, MA 111.0 Earth dike and stone slope $ 41,419 $ - $ 41,419 
protection 
Ansonia-Derby, CT 13.0 Wall, levee, chainnel 18,266,040 1,178,000 19,444,040 
improvement and pumping 
station 
Danbury, CT 56.0 Walls, channel improvement 13,143,000 1,862,000 15,005,000 
and bridge replacement 
Derby, CT 12.0 Walls, levees and pumping 7,582,642 647,000 8,229,642 
station 
North Canaan, Blackberry 83.0 Snagging and clearing 73,865 - 73,865 
River, CT project 
Pittsfield, MA 133.0 Stone arch culvert 739,003 85,000 824,003 
Salisbury, CT 76.0 Gabionade with slope 102,800 - 102,800 
protection 
Sheffield, MA 96.0 Stone slope protection 202,608 - 202,608 
Squantz Pond, New 43.0 Timber Bulkhead 116,296 - 116,296 
Fairfield, CT 
Torrington, East Branch, CT 51.0 Dike and channel 389,200 - 389,200 
improvement 
Torrington, West Branch, CT 52.0 Walls, dikes and channel 228,300 - 228,300 
Waterbury- Watertown, CT 32.0 Wall, dike and channel 263,300 - 263,300 
S For details of projects, see individual reports. 
2 To be borne by local interests. Includes relocations. 
1-50

NEW ENGLAND DIVISION 
TABLE 1-N MERRIMACK RIVER BASIN, NH, AND MA 
(See Section 34 of Text) 
RESERVOIRS 
Miles 
Above Estimated Federal Cost 
Mouth of 
Merri- Reservoir Lands 
mack Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total 
Franklin Falls 2 Franklin, NH 118.2 140 Earthfill 154,000 $ 6,190,487 $ 1,760,000 $ 7,950,487 
Blackwater 2 Concord, NH 118.8 75 Earthfill 46,000 766,746 553,000 1,319,746 
Hopkinton-Everett 2 ,4 Concord, NH 87.3 115 Earthfill 157,300 12,715,440 8,737,000 21,452,440 
Edward MacDowell 2 Keene, NH 161.3 67 Earthfill 12,800 1,708,253 306,000 2,014,253 
Monoosnoc3 Leominster, MA 100.6 71 Earthfill 2,000 3,430,000 370,000 3,800,0006 
Phillips2 Fitchburg, MA 105.4 48 Earthfill 1,600 13,450,000 7,350,000 20,800,0006 
Nookagee Fitchburg, MA 107.9 106 Earthfill 8,100 15,476,000 5,742,000 21,200,000 
Whitmanville Fitchburg, MA 110.6 76 Earthfill 9,350 11,590,000 6,210,000 17,800,000 
1 Includes highway, railroad, and utility relocations. 4 Substituted for Bennington and Beards Brook. Distance and 
2 For details, see individual report. height are for Everett Dam. Distance and height for Hopkinton 
3 Project deferred, cost not revised on current price basis. Dam are 118 miles and 76 feet, respectively. 
5 Includes Non-Federal reimbursement. 
6Based on "large" Phillips plan which would eliminate 
Nookagee Lake. 
LOCAL PROTECTION PROJECTS 
Miles 
Above Estimated Cost 
Mouth of 
Merri- Lands 
mack and 
Location River Type of Structure Construction Damages' Total 
Amesbury, Powwow and 3.0 Wall and reventment $ 132,113 $ - $ 132,113 
Merrimack Rivers, MA 2 
Nashua, NH 2 55.0 Wall and levee 270,000 3,000 273,0004 
Lowell, MA2 39.0 Wall and levee 490,6005 90,000 580,600 
Monoosnoc Brook, MA:; 98.4 Channel improvement 310,000 90,000 400,000 
North Nashua River, MA2,6 100.5 Channel improvement 3,235,000 - 3,235,000 
Saxonville, MA2 69.0 Wall, levee, channel 4,218,700 530,000 4,748,700 
' To be borne by local interests. 
2 Project completed. 
3 Project deferred. Cost has not been revised on current price 
basis. 
4 Excludes $15,000 expended from Contributed Funds. 
5 Excludes $794,374 Public Works Administration funds. 
6 Excludes $1,370,000 Public Works Administration 
funds expended on Fitchburg, MA. 
1-51

TABLE 1-O 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
THAMES RIVER BASIN, CT, RI AND MA 
(See Section 42 of Text) 
RESERVOIRS.. 
Miles 
Above Estimated Federal Cost 
Mouth 
of Reservoir Lands 
Thames Height Capacity and 
Name Nearest River (feet) Type (acre-feet) Construction Damages' Total 
Hodges Village2 Webster, MA 74.5 55 Earthfill 13,000 $1,317,268 $3,144,000 $4,461,268 
Buffumville2 Webster, MA 74.4 66 Earthfill 12,700 2,157,603 841,000 2,998,603 
East Brimfield 2 Southbridge, MA 82.8 55 Earthfill 30,000 1,337,043 5,720,000 7,057,043 
Westville 2 Southbridge, MA 75.2 80 Earthfill 11,000 2,284,683 3,400,000 5,684,683 
West Thompson2 Putman, CT 59.3 70 Earthfill 25,600 5,036,221 1,965,000 7,001,220 
Mansfield Hollow2 Willimantic, CT 40.0 70 Earthfill 52,000 4,107,164 2,340,000 6,447,164 
SIncludes highway, railroad, and utility relocations. 
2 For details, see individual report. 
LOCAL PROTECTION PROJECTS 
Miles Estimated Cost 
Above 
Mouth of Lands 
Thames and 
Location River Type of Structure Construction Damages' Total 
Norwich, CT 15.0 Channel improvements $1,209,000 $72,000 $1,281,000 
SBorne by local interests. 
TABLE 1-P BOSTON HARBOR, MA 
Total Federal Cost for Existing Project to September 1986 
Funds New Work Maintenance Total 
Regular $21,881,851 $9,096,164 $30,978,015 
Public Works 1,030,806 - 1,030,806 
Emergency Relief 935,303 - 935,303 
$23,847,960 $9,096,1641 $32,944,124 
1 Excludes $17,767 contributed funds. 
1-52

NEW ENGLAND DIVISION 
TABLE 1-Q RECONNAISSANCE AND CONDITION SURVEYS 
Date Survey Date Survey 
Project Conducted Project Conducted 
Massachusetts 
Bridgeport Harbor 
Clinton Harbor 
Connecticut River below Hartford 
Duck Island 
Milford Harbor 
Narraguagus River 
New London Harbor 
Jan 1986 
Jul 1986 
Jun 1986 
Feb 1986 
May 1986 
Nov 1985 
Apr 1986 
Maine 
Andrews River 
Annisquam River 
Beverly Harbor 
Boston Harbor 
Cape Cod Canal 
Chatham (Stage) Harbor 
Cuttyhunk Harbor 
Gloucester Harbor 
Green Harbor 
Newburyport Harbor 
Scituate Harbor 
Sesuit Harbor 
Wareham Harbor 
Weymouth Fore & Town River 
New Hampshire 
Belfast Harbor 
Harraseeket River 
Isle Au Haut 
Rockport Harbor 
Saco River 
Stonington Harbor 
Union River 
York Harbor 
Apr 1986 
Jul 1986 
Jun 1986 
Oct 1985 
Feb 1986 
Nov 1985 
May 1986 
May 1986 
Hampton Harbor 
Rhode Island 
Block Island, Harbor of Refuge 
Great Salt Pond 
Point Judith Harbor 
New York 
Hay (West) Harbor Jun 1986
1-53 
Connecticut 
Jul 1986 
Oct 1985 
Jun 1986 
Jun 1986 
Feb 1986 
Feb 1986 
May 1986 
May 1986 
Jul 1986 
Apr 1986 
Dec. 1985 
Feb 1986 
Jul 1986 
Jun 1986 
Nov 1985 
Nov 1985 
Nov 1985 
Feb 1986

NEW YORK, N.Y. DISTRICT * 
This district comprises western Vermont, small 
portions of western Massachusetts and Connecticut, eastern 
New York including Long Island, and northeastern New 
Jersey, embraced in the drainage basins tributary to Lake 
Champlain and St. Lawrence River system east thereof and 
to the Atlantic Ocean from New York-Connecticut State 
line to, but not including Manasquan I nlet, N.J. It 
exercises 
jurisdiction, however, over all matters pertaining to improvement 
of Great Lakes to Hudson River waterway. Under the 
direction of the Secretary of the Army, the District Engineer, 
as Supervisor of New York Harbor, also exercises jurisdiction 
under the laws enacted for the preservation of the tidal waters 
of New York Harbor, its adjacent or tributary waters, and the 
waters of Long Island Sound. 
IMPROVEMENTS 
Flood Control 
1. Aquatic Plant Control.........................................2-2 
2. Bay Ridge-Red Hook Channels. N.Y...................2-2 
3. Bronx River, N.Y...............................................2-2 
4. Browns Creek, N.Y.............................................2-3 
5. Buttermilk Channel, N.Y....................................2-3 
6. East Rockaway Inlet, N.Y...................................2-4 
7. Fire Island to Jones Inlet, N.Y.............................2-4 
8. Glen Cove Creek, N.Y.........................................2-5 
9. Hudson River, N.Y............................................2-5 
10. Jones Inlet, N.Y.................................................2-6 
11. Kill Van Kull-Newark Bay, N.J. & N.Y..............2-7 
12. Long Island Intra Coastal W/W, N.Y...................2-7 
13. Moriches Inlet, N.Y.............................................2-7 
14. Narrows of Lake Champlain, N.Y........................2-8 
15. Newark Bay, Hackensack & Passaic 
Rivers, N.J ............................................... 2-8 
16. Newtown Creek, N.Y..........................................2-9 
17. New York and New Jersey Channels....................2-10 
18. New York Harbor-Collection and 
Removal of drift........................................2-11 
19. New York Harbor-entrance channels & 
20. 
21. 
22. 
23. 
24. 
25. 
26. 
27. 
28. 
29. 
Anchorage areas.........................................2-11 
Plattsburgh Harbor, N.Y.....................................2-12 
Raritan River, N.J.............................................2-12 
Rondout Harbor, N.Y.........................................2-13 
Shinnecock Inlet, N.Y.......................................2-14 
Shrewsbury River, N.J........................................2-14 
Westchester Creek, N.Y......................................2-15 
Supervisor of New York Harbor.............................2-16 
Reconnaissance and Condition Surveys...............2-14 
Other authorized navigation projects.....................2-17 
Navigation work under special authorization.........2-17 
Beach Erosion Control 
30. East Rockaway Inlet to Rockaway Inlet and 
Jamaica Bay, N.Y. (Part I)...........................2-17 
31. Sea Bright to Ocean Township, NJ ..................... 2-17 
32. Other Authorized Beach erosion control projects......2-17 
33. Beach erosion control work under 
special authorization...................................2-18 
34. 
35. 
36. 
37. 
38. 
39. 
40. 
41. 
42. 
Ardsley, N.Y.............. ................................... 2-18 
Liberty State Park Levee and Seawall, N.J............2-18 
Passaic River Basin, N.J. & N.Y. Phase I............2-18 
Sawmill River Elmsford-Greenburgh, N.Y...........2-19 
Inspection of completed flood control projects..........2-20 
Other authorized flood control projects...................2-20 
Dam Safety Program..........................................2-20 
Flood control work under special authorization.......2-20 
Emergency streambank and shoreline 
protection under special authorization...........2-21 
General Investigations 
43. 
44. 
45. 
Surveys..............................................................2-21 
Collection and study of basic data.........................2-21 
Deauthorized projects..........................................2-21 
Tables 
Table 2-A Cost & Financial Statement.....................2-22 
Table 2-B Authorizing Legislation...........................2-27 
Table 2-C Hudson River, N.Y. Features of Lock 
and Dam Included in Existing Project.....2-32 
Table 2-D Total Costs for Existing Project ................. 2-32 
Table 2-E Supervisor of New York Harbor 
Statement of Activities...........................2-32 
Table 2-F Reconnaissance and Condition Surveys.....2-33 
Table 2-G Other Authorized Navigation Projects.........2-34 
Table 2-H Other Authorized Beach Erosion Control 
Projects...............................................2-36 
Table 2-I Other Authorized Flood Control Projects......2-37 
Table 2-J Surveys..................................................2-38 
Table 2-L Costs for Flood Plain Management Services 2-38 
Table 2-M Deauthorized Projects .............................. 2-38 
Table 2-N Section 17 Continue Detailed Project Report.2-39 
Table 2-0 Section 13 Complete Preauthorization 
Reconnaissance Report.........................2-40 
Table 2-P Section 25 Continue Preauthorization 
Reconnaissance Report.........................2-40 
Table 2-Q Section 14 Complete Reconnaissance 
Reports................................................2-41 
Navigation Page 
Page

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. AQUATIC PLANT CONTROL 
Location. Navigable waters, tributary streams, 
connecting channels, and other allied waters in 
New York District. 
Existing Project. Provides for control and progressive 
eradication of water-hyacinth, alligatorweed, 
Eurasian water milfoil, and other obnoxious 
aquatic plant growths, from the navigable waters, 
tributary streams, connecting channels, and other 
allied waters of the United States, in the combined 
interest of navigation, flood control, drainage, 
agriculture, fish and wildlife conservation, public 
health, and related purposes, including continued 
research for development of the most effective and 
economic control measures. (See Table 2-B for 
Authorizing Legislation.) 
Local cooperation. Local interests must provide 30 
percent of the cost of the program except as modified 
by 1962 River and Harbor Act and agree to hold the 
United States free from damages. 
Operations and results during period. FY1986 has 
been the fifth year of a ten year control program, 
started in FY 1982, for the removal of nuisance 
aquatic plants in Lake Champlain. This work was 
performed for the removal of water chestnut in the 
South Bay and Eurasian milfoil in St. Albans Bay at 
a cost of $277,000. 
Condition as of September 30. Reconnaissance 
report covering the aquatic plant problems of the 
North Atlantic Division area was completed in 
August 1967. Planning for the water chestnut control 
in the Hudson-Mohawk basin was completed by the 
New York District, contracts for $181,562 
accomplished during FY 1971 through FY 1976. The 
General Design Memorandum for this program was 
completed in March 1982 by the State of Vermont. 
The total Federal cost of this control program to date 
is $1,095,700. 
2. BAY RIDGE AND RED HOOK 
CHANNELS, N.Y. 
Location. These channels lie along east shore of 
Upper Bay, New York Harbor and, with Buttermilk 
Channel, form an easterly channel along Brooklyn 
waterfront from the Narrows to East River. (See 
National Ocean Survey Charts 12327 and 12334). 
Previous projects. For details see Annual Reports 
for 1915 and 1938, pages 1768 and 195, respectively. 
Existing projects. A channel 1,200 feet wide and 40 
feet deep at mean low water from the Narrows to Bay 
Ridge Avenue, Brooklyn, thence 1,750 feet wide to 
junction of Bay Ridge and Red Hook channels, 
thence 1,200 feet wide through Red Hook Channel to 
junction with Buttermilk Channel and a channel of 
same depth extending into Gowanus Bay from 
junction of Bay Ridge Channel with Red Hook 
channel, narrowing uniformly in width to about 500 
feet at 28th Street, Brooklyn. Section included in 
project is 4 miles long. Mean tidal range, 4.7 feet; 
mean range of spring tides, 5.6 feet; irregular 
fluctuations due to wind and atmospheric pressure 
vary from 3.9 feet below mean low water up to 5.2 feet 
above mean high water. New work for completed 
project cost $4,277,197, exclusive of amounts 
expended on previous projects. (See Table 2-B for 
Authorizing Legislation). 
Local cooperation. None required. 
Terminal facilities. See Port Series No. 5, revised 
1978. Vol. 2. 
Operations and results during period. A 
continuing contract in the amount of $2,746,622.00 
for the removal of approximately 823,000 cubic yards 
of material, except ledge rock, lying above the plane 
of 40 feet below mean low water in specified sections 
of Bay Ridge and Red Hook Channels, N.Y. with 
satisfactory disposal of the dredged material at the 
EPA approved Mud Dump site in the Atlantic Ocean 
was awarded on September 8, 1986. Operations and 
Maintenance funds in the amount of $48,776 was 
expended on engineering and design and surveys. 
Condition as of September 30. Work under 
existing project was commenced March 1901 and 
completed June 1940. 
3. BRONX RIVER, N.Y. 
Location. Empties into a shallow bay in north 
shore of East River, 11 miles by water northeast of the 
Battery, New York City. (See National Ocean 
Survey Chart 12339.) 
Previous projects. For details see Annual Report 
for 1915, page 1762, and Annual Report for 1938, page 
166. 
Existing project. A channel 10 feet deep at mean 
low water and 100 feet wide to extend from deep water 
in East River to the head of navigation at the dam at 
East 177th Street, involving the first dredging from 
East River at Randall Avenue to a width of 200 feet; 
thence to Spofford Avenue, 150 feet; thence to Watson 
Avenue, 125 feet; thence to railroad bridge near 
Westchester Avenue, 100 feet, except in southern 
approach to bridge, where it is to be 140 feet. Section 
included in project is about 2.4 miles long. Mean 
tidal range is 6.9 feet in the estuary; mean range of 
spring tides, 8.2 feet; irregular fluctuations due to 
wind and barometric pressure vary from 4 feet below 
mean low water up to 8.5 feet above mean high water. 
New work for completed active portion of project as 
described above cost $1,080,910, exclusive of amounts 
expended under previous projects, and exclusive of 
$10,000 contributed by local interests. Channel 
widening from Westchester Avenue to East 172d 
Street is considered inactive and excluded from 
foregoing description of existing project and cost 
estimate. For latest published map, see Annual 
2-2

NEW YORK, N.Y. DISTRICT 
Report for 1912, page 1470. (See Table 2-B for 
Authorizing Legislation.) 
Local cooperation. River and Harbor Act of 1913, 
provides that any right-of-way that may be 
necessary for the execution of the project shall be 
furnished free of cost to the United States. Right-ofway 
within bulkhead lines below Westchester 
Avenue Bridge was accepted by Chief of Engineers 
June 1920, and above the Westchester Avenue Bridge 
October 28. On September 10, 1940, the Chief of 
Engineers approved releases from damages 
furnished by adjoining property owners between 
Westchester Avenue and East 174th Street. On 
November 12, 1940, the Chief of Engineers approved 
an agreement under which City of New York would 
reimburse the United States for cost of a retaining 
wall to protect adjoining property in reach of river 
between Westchester Avenue and New York, New 
Haven and Hartford Railroad bridge in lieu of 
furnishing additional right-of-way. On October 28, 
1940, the Secretary of War authorized the acceptance 
of $10,000 from the city of New York to defray the cost 
of retaining wall. Additional right-of-way required 
in the section below East 172d Street has not been 
furnished. City of New York indicated it does not 
feel justified in acquiring any additional land 
along the river. 
Terminal facilities. See Port Series No. 5, revised 
1978, Vol. 2. 
Operations and results during period. A lump 
sum contract in the amount of $671,313.00 for the 
removal of all material except ledge rock lying 
above the plane of 10 and 12 feet below mean low 
water in specified sections of Bronx River, N.Y. 
with satisfactory disposal of the dredged material at 
the EPA approved Mud Dump site in the Atlantic 
Ocean, was awarded on 24 April 1986, to Weeks 
Dredging Company. The dredging work 
commenced on 5 August 1986 and was still in 
progress as of 30 September 1986. Operations and 
Maintenance funds in the amount of $826,094 as of 30 
September 1986 was expended for maintenance 
dredging accomplished during FY 1986. 
Condition as of September 30. Work under entire 
existing project is about 82 percent complete. Active 
portion of existing project was commenced in 1914 
and completed in 1941. Work remaining under 
existing project consists of widening reach between 
Westchester Avenue Bridge and East 172d Street. 
Channel between 172d Street and the upper limit of 
authorized project was filled in by City of New York 
under a Department of the Army permit and is no 
longer a waterway. 
4. BROWNS CREEK. N.Y. 
Location. A narrow, crooked tidal stream 
emptying into Great South Bay, near Sayville, Long 
Island, N.Y., about 15 miles by water northeast of 
Fire Island Inlet, and about 65 miles by water east of 
New York City. (See National Ocean Survey Chart 
12352.) 
Existing project. A channel 100 feet wide and 6 feet 
deep at mean low water from 6-foot contour in Great 
South Bay for 1,850 feet, and thence, with same width, 
4 feet deep for 1,350 feet; also for two stone jetties to 
protect the entrance, east jetty to be 448 feet long and 
west jetty 700 feet long. Section included in project is 
about 0.6 mile. Mean tidal range, 0.6 feet; mean 
range of spring tides 0.7 feet; irregular fluctuations 
due to wind and atmospheric pressure vary from 1.8 
feet below mean low water up to 3.2 feet above mean 
high water. Cost of new work for completed portion 
of project is $33,976. Dredging of channel to a depth 
of 4 feet for 3,300 feet northward to upper limit of 
project and extension of jetties; east jetty to 1,400 feet 
long and west jetty 1,600 feet long were deauthorized 
in 1977. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. None required. 
Terminal facilities. Numerous terminals, 
including several ferries, with a total available 
dockage of 7,980 feet, are scattered along shore of 
creek between its mouth and head of improved 
channel. Three are publicly owned; all are open to 
the public. None has rail connections. Facilities 
are considered adequate for existing commerce. 
Operations and results during the period. A 
continuing contract in the amount of $117,132.40 for 
the removal of approximately 20,392 cubic yards of 
material, lying above the planes of 6 feet and 4 feet 
below mean low water with disposal of the dredged 
material on a confined upland disposal site was 
awarded to Gibson & Cushman Dredging 
Corporation on 26 September 1986. Operations and 
maintenance funds in the amount of $18,412 was 
expended on engineering design and surveys. 
Condition as of September 30. Work under 
existing project was commenced August 1891 and 
completed July 1927. East jetty was completed to a 
length of 448 feet in 1893. West jetty was completed to 
a length of 492 feet in 1892 and extended in 1927 to a 
total length of 700 feet. Six-foot channel has been 
completed. Four-foot channel has been completed for 
1,350 feet. 
5. BUTTERMILK CHANNEL, N.Y. 
Location. Connects deep water in Upper Bay, New 
York Harbor, southwest of Governors Island, with 
deep water in East River northeast of Governors 
Island, and, with Bay Ridge and Red Hook 
Channels, forms an easterly channel along 
Brooklyn waterfront from Narrows to East River. 
Ut lies between Governors Island and Borough of 
Brooklyn, New York City. (See National Ocean 
Survey Charts 12334 and 12335.) 
Previous projects. For details see page 205, 
Annual Report for 1932. 
2-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Existing project. A channel 1,000 feet wide, 40 feet 
deep at mean low water for width of existing 500-foot 
channel and 35 feet deep for remaining 500-foot 
width of existing channel. Suitable widening at 
junctions with East River and Anchorage Channel 
to 35 feet deep and with Red Hook Channel to 40 feet 
deep and for additional widening with Anchorage 
and Red Hook Channels to provide maximum clear 
channel width of 2,100 feet to 35 feet deep. Section 
included in project is 2.25 miles long. Mean tidal 
range 4.4 feet; mean range of spring tides, 5.3 feet, 
irregular fluctuations due to wind and atmospheric 
pressure vary from 3.8 feet mean low water up to 5.2 
feet above mean high water. New work for 
completed projected cost $4,093,951, exclusive of 
amounts expended on previous projects. (See Table 
2-B for Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. See Port Series No. 5, revised 
1978. 
Operations and results during period. Operations 
and maintenance funds in the amount $30,000 was 
expended on engineering and design for future 
maintenance dredging of this project. 
Condition as of September 30. Work under 
existing project commenced October 1903 and was 
completed March 1965. Easterly 500-foot width of 
channel, from Anchorage Channel to East River, 
was completed to a 40-foot depth in May 1935. 
Westerly 500-foot channel, including widening the 
junction with East River, was completed to a 35-foot 
depth in July 1961. Widening the junctions with 
Anchorage and Red Hook Channels was completed 
in March 1965. 
6. EAST ROCKAWAY INLET, N.Y. 
Location. On south shore of Long Island between 
main body of island and western end of Long Beach. 
It is 10 miles east of Rockaway Inlet and about 27 
miles by water south and east from the Battery, New 
York City. (See National Ocean Survey Chart 
12353.) 
Existing project. A channel 12 feet deep at mean 
low water and 250 feet wide from 12-foot contour in 
Long Beach Channel protected by a jetty. Mean tidal 
range, 4.3 feet; mean range of spring tides, 5.2 feet; 
irregular fluctuations due to wind and atmospheric 
pressure vary from 3.9 feet below mean low water up 
to 5.6 feet above mean high water. New work for 
completed project cost $603,969, including $100,000 
contributed funds. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. Complied with. 
Terminal facilities. There are 39 terminals in 
Oceanside, Island Park, Long Beach, and East 
Rockaway. Nine of these are oil terminals, one of 
which has a railroad spur. Other terminals are 
repair and mooring docks with a berthage of 7,655 
feet. Of these, 21 have marine railways and 1 has 
mechanical-handling facilities. There are public 
wharves at East Rockaway and Woodmere. 
Waterfront on north side of Long Beach has been 
bulkheaded. Facilities are considered adequate for 
existing commerce. 
Operations and results during period. A 
continuing contract for the removal and disposal of 
all material except ledge rock lying above the plane 
of 14 feet below mean low water in the Inlet was 
awarded on June 28, 1985. Work commenced on 
September 19, 1985 and was continuing as of 30 
September 1985. Fiscal Year operations and 
maintenance funds in the amount of $2,042,116 was 
expended on engineering and design, supervision 
and inspection and for contract payment for this 
project. 
Condition as of September 30. Work under 
existing project began February 1933 and is 100 
percent complete. East jetty, 4,250 feet long, was 
completed in July 1834. Project channel was 
completed in May 1935. 
7. FIRE ISLAND TO JONES INLET, 
N.Y. 
Location. On south shore of Long Island, about 50 
miles by water south and east of the Battery, New 
York City. Fire Island Inlet is the main entrance 
into Great South Bay from the Atlantic Ocean. (See 
National Ocean Survey Chart 12352.) 
Existing project. A jetty extending generally 
southwest and south for 5,000 feet from high ground 
on Democrat Point at the west end of Fire Island and 
a channel generally parallel to the jetty 18 feet deep 
and 500 feet wide from a littoral reservoir (sediment 
trap) in the ocean to deep water in the inlet. Mean 
tidal ranges at the ocean and inlet ends of Democrat 
Point are 4.1 ft. and 2.4 ft. respectively. Irregular 
fluctuations due to wind and atmospheric pressure 
vary from 2.5 feet below mean low water up to 6.2 feet 
above mean high water on the ocean side. (See Table 
2-B for Authorizing Legislation.) 
Local cooperation. Requires cost sharing and 
lands, easements & rights-of-way. 
Terminal facilities. None within the area 
immediately adjacent to the Federal improvements. 
Operations and results during the period. At the 
request of local interests, maintenance dredging 
was postponed in 1979 until the completion of an Inlet 
Dynamic Study. The residents of Oak Beach 
contend that dredging the Inlet exposes Oak Beach to 
direct wave attack thereby causing an erosion 
problem. The Inlet Dynamic Study was completed 
in 1985; and other subsequent, related studies have 
not proven the contention that the erosion at Oak 
Beach is related to the construction of the project 
channel. The resumption of the project is still being 
studied. 
2-4

NEW YORK, N.Y. DISTRICT 
Condition as of September 30. Work under the 
existing project was commenced in late 1973. As a 
result of three consecutive dredging operations 
completed in 1977, the project channel was brought to 
the approximate authorized dimension at that time. 
No maintenance dredging was accomplished in the 
ensuing time period. Due to the aforementioned 
local concerns maintenance has been deferred since 
1979 which has allowed the complete shoaling of the 
authorized channel. 
8. GLEN COVE CREEK, N.Y. 
Location. A narrow tidal inlet extending 
eastwardly about 1 mile from east side of Hempstead 
Harbor on the north shore of Long Island, 26 miles 
northeast of the Battery, New York City. (See 
National Ocean Survey Chart 12366.) 
Existing project. Provides for a channel 100 feet 
wide and 8 feet deep at mean low water from deep 
water in Hempstead Harbor about 1 mile to the head 
of navigation at city of Glen Cove. Mean tidal 
range, 7.4 feet; mean range of spring tides, 8.7 feet; 
irregular fluctuations due to wind and barometric 
pressure vary from 3.6 feet below mean low water up 
to 8.4 feet above mean high water. New work for 
completed project cost $29,760, exclusive of $29,774 
expended from contributed funds. Widening to 100 
feet the upper 1,630 feet of channel were it crosses the 
beach are considered inactive and excluded from 
foregoing description and cost estimate. Existing 
project adopted by 1925 River and Harbor Act (H. 
Doc. 207, 68th Cong., 1st sess.). Latest published map 
is in project document.) 
Local cooperation. River and Harbor Act of March 
3, 1925, provides that local interests pay one-half of 
first cost of the work, provided rights-of-way, spoildisposal 
areas, and bulkheads, and give assurances 
that adequate terminals will be built. Complied with 
as to contribution of one-half of first cost of work 
done to date, ceding of rights-of-way, provision of 
disposal areas, and the construction of terminals. 
Pending construction of bulkheads by local interests 
along southerly side of channel in the upper 1,600 feet 
of the improvement, a channel of less than project 
width has been excavated. In letter dated February 4, 
1948, the Commissioner, Department of Public 
Works, City of Glen Cove, was notified of the 
conditions affecting the remaining work. There is 
no indication as to when compliance with these 
conditions may be expected. 
Terminal facilities. There are 1,875 feet of 
bulkheads along northerly side of waterway. 
Terminals are adequate for present needs and there 
is ample waterfront, both public and private, for 
additional terminals as needs arise. 
Operations and results during period. Operations 
and maintenance funds in the amount of $29,925 was 
expended on reconnaissance surveys, and 
engineering and design in conjunction with future 
maintenance dredging of this project. 
Condition as of September 30. Entire existing 
project is about 55 percent complete. Work under the 
active portion of existing project was commenced 
August 1933 and completed August 1934. The work 
done provided a channel 100 feet wide from deep 
water in Hempstead Harbor for 3,470 feet, thence 
gradually decreasing to 50 feet wide for 180 feet, and 
50 feet wide for about 1,450 feet to the head of the 
improvement. Head of navigation is at City of Glen 
Cove, about 1 mile above the mouth. Work 
remaining to complete existing project consists of 
widening to 100 feet the upper 1,630 feet of channel 
and building a sand fence along north side of 
channel where it crosses the beach. 
9. HUDSON RIVER, N.Y. 
Location. Originates in Adirondack Mountains, 
about 250 miles in a direct line and 315 miles along 
its course from the Battery, New York City, and 
flows generally southerly into New York Bay. 
Section under improvement extends from New York 
City about 156 miles to Waterford. (See National 
Ocean Survey Charts 12335,12341,12343,12347,12348, 
and 14786.) 
Previous projects. For details see Annual Reports 
for 1915 and 1938, pages 1764 and 226, respectively. 
Existing projects. A channel 600 feet wide from 
New York City to Kingston and thence 400 feet wide 
to Albany, with widening at bends, a turning basin 
700 feet wide and 1,200 feet long at Albany, and 2 
anchorages, 1 near Hudson and 1 near Stuyvesant, 
each 400 feet wide and an average length of 2,400 feet; 
all with depths of 32 feet in soft material and 34 feet 
in rock to 2,200 feet south of the Mall Bridge; thence 
27 feet deep and 400 feet wide to 900 feet south of the 
Mall Bridge, thence 14 feet deep at lower low water 
and generally 400 feet wide to Federal lock at Troy; 
and thence of same depth and 200 feet wide to 
southern limit of State barge canal at Waterford; 
and removal of State dam at Troy and construction 
of a lock and dam about 2.5 miles below Waterford. 
Channel is to be formed by dredging and rock 
excavation, and maintained by dredging and 
constructing new, and raising and repairing old, 
longitudinal dikes, built partly under previous 
projects and partly by the State of New York. Mean 
range of pool elevation above Federal dam at Troy, 
in seasons of moderate rains, is about 2.2 feet, as 
determined in 1934. Mean tidal range is about 4.8 
feet between May and October and 5.1 feet between 
July and September at Albany, extreme range due to 
freshets is 33.1 and 25.9 feet, respectively normal 
pool level above Federal dam from Troy to 
Waterford is 14.33 feet above mean sea level. In 
tidal section of river below dam, assumed lowest low 
water plane from Troy to Albany is 3 feet below mean 
sea level. (See Table 2-C for features of lock and 
2-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
dam included in existing project.) New work for 
completed project cost $39,050,019 exclusive of 
amounts of expended on previous projects. 
Widening to form harbors at Albany and Troy, 
N.Y., to 12 feet deep at a cost of $522,000 (1954) and 
completion of 27-foot channel at Albany at a cost of 
$642,000 (1957) was placed in deferred for restudy 
category. All three features of work are excluded 
from foregoing description of existing project and 
cost estimate. Construction of mooring facilities has 
been authorized. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. Complied with except that local 
interests must furnish suitable soil disposal areas 
for future maintenance as required. 
Terminal facilities. See Port Series No. 6. 
Operations and results during period. A contract 
in the amount of $96,500 was awarded on August 14, 
1985 for shoreline protection at the Albany Turning 
Basin, Hudson River, Rensselaer, New York. Of 
the contract amount, $80,000 was Federal fund, while 
the remaining $16,500 were contributed funds for the 
reconstruction of a storm sewer outfall through the 
riprap. Work was completed on the project on 
October 28, 1985. Operation and maintenance funds 
in the amount of $158,461 were expended on 
engineering and design and preparation of 
maintenance dredging specifications for the North 
Germantown, Stuyvesant and Castleton reaches of 
the Hudson River. A contract for removal of 
approximately 497,500 cubic yards of material was 
awarded on August 18, 1986 to North American 
Trailing Company. A total of $399,938 of an 
estimated contract amount of $2,538,750 was 
expended on the contract by September 30, 1986. 
Government plant and hired labor were employed 
through the fiscal year in the removal of stumps, 
snags and other obstructions which constituted a 
potential hazard to navigation at a cost of $223,594 for 
maintenance in FY 1986. Government plant and 
hired labor were employed through the fiscal year 
performing dredging and project condition surveys 
at a cost of $235,786 for maintenance in FY 1986. 
Government plant and hired labor were employed 
intermittently through the fiscal year on repairs to 
Cedar Hill Dike at a cost of $27,083 for maintenance 
in FY 1986. Government plant and hired labor were 
employed throughout the fiscal year with operation 
and maintenance of the Troy Lock and Dam 
including the associated buildings and grounds. 
Operation of the Lock was suspended for the 1985 
navigation season on December 9, 1985 and was 
resumed for the 1986 navigation season on April 26, 
1986. Total cost incurred for the operation and 
maintenance of the Troy Lock and Dam and the 
associated buildings and grounds was $697,386 for 
FY 1986. 
Condition as of September 30. Work under 
existing project began in July 1910 and was 
substantially completed in November 1965. New 
lock and dam at Troy, removal of dam at Troy and 
construction of 15,545 linear feet of dikes also are 
complete. In reconstruction of old dikes 39,676 
linear feet were raised to adopted crest height. 
Channel from New York City to Albany is complete 
to a depth of 32 feet except for the 1,500 linear-foot 
section at the northern end of the 32-foot project which 
has never been dredged to project depth. 
Additionally, the 1,300 linear feet of the 27-foot 
project remains undredged. Channel from Albany 
to Waterford is complete to a depth of 14 feet except for 
a small part of the widening to form a harbor at 
Troy. Work remaining under the project consists of 
completion of the 12-foot harbor at Troy and 
dredging the 27-foot and the remainder of the 32-foot 
channels at Albany which are not deemed necessary 
at this time; and reconstruction of dikes. 
10. JONES INLET, N.Y. 
Location. A small inlet on south shore of Long 
Island connecting Hempstead Bay with Atlantic 
Ocean, 37 miles by water southeast of the Battery, 
New York City. (See National Ocean Survey Chart 
12352.) 
Existing project. An entrance jetty and a channel 
12 feet deep and 250 feet wide, from that depth in the 
ocean through the inlet to Loop Causeway Bridge over 
Long Creek. Section included in project is about 2.1 
miles long. Mean tidal range varies from 4.2 feet at 
ocean entrance to 3.1 feet at Loop Causeway Bridge; 
mean range of spring tide varies from 5 to 3.7 feet, 
respectively; irregular fluctuations due to wind and 
atmospheric pressure vary from 3.9 feet below mean 
low water up to 8.5 feet above mean high water. (See 
Table 2-B for Authorizing Legislation.) 
Local cooperation. Complied with except that local 
interests must furnish suitable spoil-disposal areas 
for future maintenance as required, and must 
maintain a channel 12 feet deep and generally 200 
feet wide from Loop Causeway Bridge over Long 
Creek to head of navigation in Freeport Creek at 
Mill Road. 
Terminal facilities. Within area tributary to 
Jones Inlet there are a number of privately owned 
small wharves and numerous boat repair and 
storage yards. The latter are equipped for repair of 
pleasure craft and fishing vessels. In addition, 
there are nine public wharves open to the public free 
of charge, with a total dockage of 2,180 feet. 
Additional terminals would have to be constructed 
for receipt of commercial freight in any sizable 
quantity. 
Operations and results during period. Operations 
and maintenance funds in the amount of $137,883 
was expended on reconnaissance surveys of the 
navigation channel and also studies to evaluate the 
rehabilitation requirements of the federal jetty.

NEW YORK, N.Y. DISTRICT 
Condition as of September 30. Work under 
existing project was commenced August 1953 and 
completed June 1959. JONES INLET - JETTY 
REHABILITATION ($34,500). The purpose of this 
study is to develop a feasible and cost effective 
design for rehabilitation of the Jones Inlet Jetty to 
insure structural stability and maximize the sand 
trapping efficiency of the structure. Inlet 
hydrographic and existing jetty condition surveys 
have been performed. Preliminary design and cost 
estimates for alternative schemes have been 
developed and the superior scheme recommended. 
JONES INLET - MAINTENANCE 
MODIFICATIONS ($49,264). The purpose of this 
study is to develop feasible and cost efficient 
alternative which would minimize channel 
maintenance requirements. Existing tidal/inlet 
hydraulics, inlet/bay stability, jetty impoundment 
rates, etc., have been evaluated. Several methods of 
shoaling analysis were reviewed and the most 
applicable used. Preliminary design layouts and 
cost estimates for a deposition basin and navigation 
channel have been developed and the superior 
scheme recommended. 
11. KILL VAN KULL - NEWARK BAY 
CHANNEL, N.J. & N.Y. 
Location. The project includes Kill Van Kull 
connecting upper New York Bay with Newark Bay, 
and channels in lower Newark Bay serving Port 
Newark and Elizabeth Marine Terminal. These 
terminals are located on the west shore of Newark 
Bay. (See National Ocean Survey Chart 12333.) 
Existing project. Deepening the existing Kill Van 
Kull channel and channels in lower Newark Bay, 
including turning and maneuvering areas. The 
deepening to be done from the existing 35 foot depth 
incrementally to 40 feet and then 44 feet. The 
Federal cost of construction is estimated at 
$198,000,000 with an additional $142,000,000 to be 
contributed by local interests (Oct 86 P.L.). 
Local operation. The Port Authority of New York 
and New Jersey, the local cooperating agency, has 
indicated that it intends to fulfill the legal 
requirements for non-Federal interests existing at 
the time of Congressional authorization. 
Terminal facilities. See Port Series No. 5, Vol. 2. 
Operations and results during period, and 
condition as of Sept. 30. No construction work has 
been started. Preparation of a General Design 
Memo is in process on an accelerated basis. A draft 
supplement EIS including the 404 evaluation has 
been completed. 
12. LONG ISLAND INTRACOASTAL 
WATERWAY, N.Y. 
Location. Extends from East Rockaway Inlet, on 
the south side of Long Island, to Great Peconic Bay at 
eastern end of Long Island. Section included under 
this project extends from Great South Bay opposite 
Patchogue to the south end of Shinnecock Canal. 
(See National Ocean Survey Chart 12352.) 
Existing project. A channel 100 feet wide and 6 feet 
deep at mean low water from the federally improved 
channel in Great South Bay, opposite Patchogue to 
south end of Shinnecock Canal. Section included in 
project is 34 miles long. Mean tidal range varies 
from 1 foot in Shinnecock Bay to 0.7 foot in 
Patchogue Bay; mean range of spring tides varies 
from 1.2 feet to 0.8 foot; irregular fluctuations due to 
wind and atmospheric pressure vary from 1.8 feet 
below mean low water to 12 feet above mean high 
water. (See Table 2-B for Authorizing Legislation.) 
Local cooperation. Complied with except local 
interests must furnish suitable spoil-disposal areas 
for future maintenance as required. 
Terminal facilities. There are 17 boat repair and 
storage yards within the area immediately adjacent 
to the Federal improvement. There is ample room 
for expansion and development of terminals when 
future commerce warrants. 
Operations and results during period. A contract 
was awarded to Gibson & Cushman Dredging 
Corporation on 4 April 1986 for the removal of all 
material lying above the planes of 6 & 8 feet below 
mean low water in specific sections within the 
Shinnecock Bay reach and 10 feet below mean water 
in the Moriches Bay reach of Long Island 
Intracoastal waterway, New York. The material 
was disposed on nearby beaches. The work 
commenced on 13 May 1986 and was completed on 20 
June 1986. A total of 106,155 cubic yards, place 
measurement, of material was removed at a cost of 
$702,448. Operations and maintenance funds in the 
amount of $971,988 was expended on engineering 
and design, supervision and inspection and for 
contract payments for this project. 
Condition as of September 30. Original work 
under the existing project was commenced Oct 1939 
and commenced Sept 1940. 
13. MORICHES INLET, N.Y. 
Location. On the south shore of Long Island, about 
80 miles by water east of the Battery, New York City. 
It is an opening through the narrow sandy barrier 
beach on the south shore of Long Island which 
separates the Atlantic Ocean from a series of 
interconnected bays. (See National Ocean Survey 
Chart 12352.) 
Existing project. Provides for a channel, 10 feet 
deep at mean low water and 200 feet wide extending 
from that depth in the Atlantic Ocean to Moriches 
Bay, a distance of 0.7 mile; thence a channel 5 feet 
deep and 100 feet wide to the Long Island Intracoastal 
Waterway, a distance of 1.1 miles; rehabilitation of 
the existing jetties and revetments. Estimate of cost 
2-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
of work is $10,300,000 (October 1986 P.L.) including 
$50,000 from Coast Guard and $3,700,000 to be 
contributed by local interests. (See Table 2-B for 
Authorizing Legislation.) 
Local cooperation. In accordance with the project 
authorization, local interests are required to furnish 
all easements, rights-of-way including relocations 
that are necessary for improvements at an overall 
35% cost sharing basis. The annual Operations and 
Maintenance cost is estimated to be $1,860,000, of 
which the local share is 50% or $930,000 per year. An 
Agreement of Local Cooperation was executed on 30 
June 1986. The New York State Department of 
Environmental Conservation is the local sponsor. 
Terminal facilities. No terminals are within the 
area immediately adjacent to the Federal 
improvement. However, numerous public and 
private terminals facilities are available in 
Moriches Bay and in the connecting canals. 
Several yacht clubs, boatyards, and public wharfs 
and landings,, and numerous private landings are 
located in Moriches Bay. The yacht clubs and 
boatyards have equipment for servicing boats. 
There are boat basins open to the public. The 
facilities existing in the bay are considered 
adequate for present and probable future needs under 
present conditions of Moriches Inlet. There is room 
for expansion should future commerce warrant. 
Operations and results during period. Preconstruction 
planning resumed in October 1977. 
Coordination continued with Federal, State and 
local agencies on current problems and need for all 
project purposes (i.e. navigation; beach erosion 
control; water quality improvement). Formulated 
plans for single purpose navigation project. In 
January 1980, a breach occurred adjacent to the 
eastern jetty. Emergency funds ($11.3 million) 
were authorized under the authority of PL84-99 to 
close the breach. About 1,185,000 yards of sand fill 
were used to effect closure of the breach by March 
1981. 
Condition as of September 30. Construction has not 
been initiated. Preconstruction planning (advance 
engineering and design) has been completed and 
contract plans and specifications were completed in 
January 1985. 
14. NARROWS OF LAKE CHAMPLAIN, 
N.Y. & V.T. 
Location. This waterway, 37 miles long, 
comprises southern end of Lake Champlain and 
extends from Whitehall to Crown Point, N.Y. at 
southern extremity of lake, northerly to Benson 
Landing, Vt. (See National Ocean Survey Chart 
14784.) 
Previous projects. For details, see Annual Reports 
for 1931, and 1963, pages 256 and 177, respectively. 
Existing project. A channel extending from 
Whitehall, N.Y., at head of Lake Champlain, to 
Benson Landing, 12 feet deep at low lake level and 
generally 150 feet wide, and installation of fender 
booms at Putts Rock, Putts Leap, Narrows near 
Dresden, Pulpit Point and Cedar Mountain. 
Reference plane of low lake level is 93 feet above 
mean sea level. Section included in project is about 
13.5 miles. Usual annual variation of lake level is 
5.8 feet and extreme variation varies from 0.6 foot 
below up to 8.8 feet above low lake level. 
Widening channel throughout its entire length to 
project width of 20 feet is inactive and excluded from 
foregoing description of existing project and cost 
estimate. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. None required. 
Terminal facilities. In Whitehall Harbor 
consisting of three timber wharves, aggregating 
4,200 feet in length. State of New York constructed a 
barge canal terminal at Whitehall, just south of 
terminus of canal, which has been equipped with a 5- 
ton hand-operated derrick and a storehouse. 
Facilities are considered adequate for present 
commerce. 
Operations and results during period. 
Government plant and hired labor were employed 
intermittently during the fiscal year in removal of 
stumps and snags that posed a potential hazard to 
navigation at a cost of $19,418. Government plant 
and hired labor were employed in replacing 
deteriorated fender booms at a cost of $17,789. 
Operations and maintenance funds in the amount of 
$45,723 were expended on engineering and design 
for future maintenance of this project. 
Condition as of September 30. Work under the 
existing project was commenced June 1919 and is 
about 77 percent complete. A channel 12 feet deep at 
low lake level and least a width of 150 feet has been 
excavated throughout the length of the improvement, 
except at the Elbow (Putts Leap and Putts Rock). 
(Fender booms opposite the Delaware and Hudson 
Railroad trestle have been removed as they are no 
longer considered necessary for navigation.) The 
work remaining to complete the project consists of 
widening the channel throughout its entire length to 
the project width of 200 feet. 
15. NEWARK BAY, HACKENSACK 
AND PASSAIC RIVERS, N.J. 
Location. Newark Bay is an estuary about 1.25 
miles wide and 6 miles long extending southerly 
from confluence of Hackensack and Passaic Rivers 
to New York and New Jersey Channels. 
Hackensack River rises near Haverstraw, 
Rockland County, N.Y. and flows about 45 miles 
into Newark Bay. Passaic River rises in highlands 
of northeastern New Jersey and flows about 80 miles 
2-8

NEW YORK, N.Y. DISTRICT 
into Newark Bay. (See National Ocean Survey 
Charts 12333 and 12337.) 
Previous projects. For details see 1926 Annual 
Report, pages 265 and 266; and Annual Reports for 
1929,1938,1954, and 1976, pages 301,244,134, and 2-11 
respectively. 
Existing project. A main channel 700 feet wideto 
the branch channel to Port Newark, thence 500 feet 
wide to a turning basin 1,300 feet long and 900 feet 
wide at the junction of the Hackensack and Passaic 
River channels, length about 4.7 miles; a 
maneuvering area south of the former Central 
Railroad of New Jersey Bridge 2,200 feet long and 
300 feet wide with depths of 38 feet in the south half 
and 35 feet in the north half; a combined bend cutoff 
and maneuvering area at the south side of the 
junction with Elizabeth branch channel; and 
widening of bends at the Kill Van Kull and Port 
Newark Channels. (Authorized depth 35 feet except 
as noted above.) (adopted 1966.) 
At Port Newark - A branch channel 800 feet wide 
leading to an inshore channel 400 feet wide 1.6 miles 
(adopted 1945). Authorized depth 37 feet in rock and 
35 feet in soft material; a pierhead channel 200 feet 
wide along the east bulkhead between the Port 
Newark and Elizabeth branch channels, length 
4,100 feet. Authorized depth 35 feet (adopted 1962). 
At Elizabeth Marine Terminal - A branch 
channel 500 feet wide, length about 1.4 miles; a 
pierhead channel along the east bulkhead 290 feet 
wide, length about 1.1 miles; a south channel along 
the south bulkhead 290 feet wide, length about 2,600 
feet; a southern approach area just above former 
Central Railroad of New Jersey Bridge enlarged for 
turning and maneuvering, with a maximum length 
of about 2,700 feet and width (between the pierhead 
channel and Newark Bay channel) of about 800 feet. 
Authorized depth 35 feet (adopted 1962). 
Local cooperation. River and Harbor Act of 1954 
provides local interests furnish lands, rights-ofway, 
and suitable spoil-disposal areas for initial 
construction and future maintenance; provide 
depths commensurate with channel depth in 
approaches and berths at terminals of companies 
which would use improvement; and hold the United 
States free from damages. River and Harbor Act of 
1962 provides that local interests must provide lands, 
easements and rights-of-way for maintenance and 
construction, hold United States free from damages, 
provide and maintain adequate public terminal and 
transfer facilities, and accomplish without cost to the 
United States, removal or relocation of pipelines, 
cable and other utilities. Assurances were furnished 
by Port of New York Authority and accepted June 12, 
1964. Local cooperation required by previous 
modifications is fully compiled with. 
Terminal facilities. See Port Series No. 5, revised 
1978, Vol. 2. 
Operations and results during period. A lump 
sum contract was awarded to Great Lakes Dredge & 
Rock Company on 16 January 1986 for the removal of 
all material except ledge rock lying above the plane 
of 30 feet and 25 feet below mean low water from the 
specified sections of the Hackensack River with 
disposal of the dredged material at the EPA approved 
Mud Dump Site in the Atlantic Ocean. Work 
commenced on 27 February 1986 and was completed 
on March 14 1986. Contractor's total earnings was 
$838,633. Operations and maintenance funds in the 
amount of $957,000 was expended on engineering 
and design, contract supervision and inspection and 
contract payments on this project. 
Condition as of September 30. Work under the 
active portion of project began June 1976 and is 100 
percent complete. Work remaining to complete 
existing project consists of; deepening the 
Hackensack River channel to depths of 32 feet and 15 
feet. 
Work was initiated for modification of project 
consisting of additional widening at junction with 
Kill Van Kull by deepening to 37 feet a triangular 
area at the eastern end of the 30 foot channel south of 
Shooters Island. Two contacts for the removal of all 
material including ledge rock to 37 feet mean low 
water were completed at a total cost of $4,402,631. 
16. NEWTOWN CREEK, N.Y. 
Location. A tidal waterway entering East River, 
N.Y., and 4.5 miles by water northeast of the Battery, 
New York City, and forms a part of boundary 
between boroughs of Brooklyn and Queens, New 
York City. (See National Ocean Survey Chart 
12335). 
Previous projects. For details see Annual Reports 
for 1915 and 1938, pages 1769 and 207, respectively. 
Existing project. A channel 23 feet deep and 130 
feet wide from East River to a point 150 feet north of 
Maspeth Avenue; a turning basin at former location 
of Mussel Island and a triangular area lying on 
north side of entrance to creek of same depth; a 
channel 20 feet deep, 75 to 100 feet wide in Dutch 
Kills, 2,800 feet long; a channel in Maspeth Creek of 
same depth and 100 feet wide, for 2,000 feet; a 
channel in East Branch, 18 feet deep and 150 feet 
north of Maspeth Avenue to Grand Street Bridge and 
thence 125 feet wide, to Metropolitan Avenue Bridge; 
a channel in English Kills or West Branch, 16 feet 
deep and 150 feet wide to Metropolitan Avenue 
Bridge, including easing of bends. Section included 
in project is about 5.2 miles. Mean tidal range, 4.2 
feet; mean range of spring tides, 5 feet; irregular 
fluctuations due to wind and barometric pressure 
vary from 3.8 feet below mean low water up to 4.2 feet 
above mean high water. New work for active portion 
of project consisting of channels described above, 
cost $767,093, exclusive of amounts expended on 
2-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
previous projects. Deepening English Kills to 20 feet 
to Metropolitan Avenue Bridge and thence 12 feet 
deep, and 100 feet wide from Metropolitan Avenue 
Bridge to within 80 feet of Montrose Avenue Bridge, 
suitably widened by excavating upland at second 
bend above Metropolitan Avenue Bridge, and 
deepening East Branch to 20 feet are inactive and are 
excluded from foregoing description and cost 
estimate. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. See page 160, 1964 Annual 
Report for requirements under acts of March 1919 
and August 26, 1937. 
Terminal facilities. See Port Series No. 5, revised 
1965, Vol. 2, Part 2, pages 190-208. 
Operations and results during fiscal year. 
Operations and maintenance funds in the amount of 
$50,950 was expended on engineering and design 
surveys and environmental studies for future 
maintenance dredging of this project. 
Condition at end of fiscal year. Work under 
entire existing project is about 64 percent complete. 
Work under active portion of existing project was 
commenced May 1921 and completed December 1932. 
Enlarging main channel to 23-foot depth and 130- 
foot width from entrance to 150 feet north of Maspeth 
Avenue, including triangular area at entrance, and 
a turning basic at former location of Mussel Island, 
is about 90 percent complete. Dutch Kills has been 
dredged to project depth, 20 feet, for a width of 75 to 100 
feet except at a few places near head of improvement 
where unstable bulkheads restricted dredging 
operations. Maspeth Creek dredged to project 
dimensions throughout. Work remaining consists 
of completing to project dimensions 23-foot main 
channel between Greenpoint and Meeker Avenue, 
and between 800 and 150 feet north of Maspeth 
Avenue; 20 foot channel in East Branch; and 20- and 
12-foot channels in English Kills. 
17. NEW YORK AND NEW JERSEY 
CHANNELS 
Location. Extends from deep water northwest of 
Sandy Hook, through Lower New York bay and 
Raritan bay, to Perth Amboy, and thence through 
Arthur Kill, lower Newark Bay, and Kill Van Kull 
to deep water in Upper New York Bay. This route is 
approximately along boundary line between states of 
New York and New Jersey. (See National Ocean 
Survey Charts 12333, 12331, and 12327.( 
Previous projects. For details see 1963 Annual 
Report pages 184 and 185. 
Existing project. A channel through Lower New 
York Bay, Raritan Bay, Arthur Kill, lower Newark 
Bay, and Kill Van Kull to Upper New York Bay and 
Raritan Bay and in Arthur Kill to a point 1,000 feet 
north of Smith Creek, widened to 800 feet in vicinity 
of Seguine Point and Wards Point, respectively; 
thence 500 wide to a point 1,000 feet south of Piles 
Creek; thence 500 to 600 feet wide and passing north 
of Shooters Island and protected by a dike on its 
northern side to junction of channel into Newark 
Bay; thence 800 feet wide through Kill Van Kull to 
Constable Hook; thence 1,000 feet wide from a point 
opposite the east end of Constable Hook to a point near 
the intersection with the channel along New Jersey 
pierhead line; and thence 1,400 feet wide through 
Kill Van Kull to Upper New York Bay; with an 
anchorage 38 feet deep to accommodate five vessels 
south of Perth Amboy, all with suitable easing at 
bends and junctions. Section included in project is 
30.8 miles long. In addition, construction of a dike 
north of Shooters Island and two secondary channels 
30 feet deep and 400 feet wide, one south of Shooters 
Island and the other in Raritan Bay connecting with 
Raritan River, were completed under previous 
projects and maintained under existing project. A 
triangular area at the eastern end of the 30 foot 
channel south of Shooters Island was deepened to 35 
feet in order to provide additional widening in the 
vicinity of Bergen Point and is included in the 
Newark Bay project. All depths refer to plane of 
mean low water. Mean range of tides varies 
between 4.7 and 5.1 feet; mean range of spring tides, 
5.7 to 6.3 feet; irregular fluctuations due to wind and 
atmospheric pressure vary from 3.9 feet below mean 
low water up to 6.9 feet above mean high water. 
Anchorage at Sandy Hook, and cutoff at junction of 
Main Ship Channel are deferred for restudy and 
excluded from foregoing description and cost 
estimate. (See Table 20B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with except for 
the middle section of Arthur Kill where local interest 
must furnish spoil disposal areas for maintenance. 
Terminal facilities. See Port Series No. 5, revised 
1978, Vol. 2. 
Operations and results during period. The U. S. 
Army Corps of Engineers' dredge "McFarland" 
was employed from 22 May 1986 to 5 June 1986 to 
restore project dimensions in Seguine Point 
vicinity. Removed 54,460 cubic yards, place 
measurement, of material at a cost of $292,004. 
Hopper dredge was also employed from 5 June 1986 to 
7 July 1986 to restore project dimensions in Raritan 
Bay reach (east channel). Removed 226,532 cubic 
yards, place measurement, of material at a cost of 
$903,863. 
Conditions as of September 30. Work under active 
portion of existing project began in October 1933. 
Work completed consists of providing authorized 
project depth and widths throughout entire channel 
from Lower New York Bay to Upper New York Bay 
and providing depths of 37 and 25 feet in Perth 
Amboy Anchorage. In addition to above mentioned 
work, construction of dike north of Shooters Island, 
2-10

NEW YORK, N.Y. DISTRICT 
two secondary channels 30 feet deep and 400 feet 
wide, one south of Shooters Island, the other in 
Raritan Bay connecting with Raritan River were 
completed under previous projects. Work 
remaining under existing project consists of 
dredging cutoff at junction of Main Ship Channel to 
dimensions authorized by River and Harbor Acts of 
August 30, 1935, and May 17, 1950, dredging 
anchorage in vicinity of Sand Hook. (See Table 2-D 
for total cost for existing project to September 30, 
1982.) 
18. NEW YORK HARBOR - 
COLLECTION AND REMOVAL 
OF DRIFT 
Location. Applies to Lower and Upper Bays, New 
York Harbor; East River, Harlem River, Hudson 
River Channel, N.Y., New York and New Jersey 
Channels, Newark Bay, N.J. and their tributaries. 
Existing project. Provides for collection, removal 
and disposal of drift, derelict vessels, deteriorated 
shore structures and debris along shores of New 
York Harbor and tributary waters, and for the repair 
of certain other piers, wharves and shore structures. 
Work authorized before Act of 1970 was restricted 
solely to removal of drift from waterways and was 
funded as a maintenance activity. Estimate of first 
cost of improvement under Act of 1974 is $125,400,000 
(October 86 P.L.), including $23,200,000 cash 
contribution from local interests, plus $55,900,000 to 
be contributed for repair and disposal of deteriorated 
shore structures in use. (See Table 2-B for 
Authorizing Legislation.) 
Local cooperation. Local cooperation conditions of 
the plans currently under review by the Chief of 
Engineers provide that local interests must furnish 
all lands, easements and rights-of-way required for 
the improvement; hold the United States free from 
damages; enact and enforce local legislation to 
prevent creation of sources of drift, contribute in 
cash one third of the first cost of the Federal work, 
and make necessary repairs to deteriorated 
structures in use so as to eliminate them as a source 
of drift. These conditions are subject to approval by 
the Secretary of the Army and the President, as 
stipulated in Section 113 of the authorizing law, 
Public Law 91-611. 
Operations and results during period. New work: 
Liberty State Park Contract IVB was completed at a 
cost of $1,268,000. East River-Manhattan 
Waterfront contract was completed at a cost of 
$1,477,806. A contract for the removal of Piers 17 and 
18 on the East River was completed at a cost of 
$219,609. The City of Elizabeth contract was 
completed at a cost of $791,700. The Stapleton, Staten 
Island contract was completed at a cost of $2,820,000. 
A contract for the City of Bayonne was completed at a 
cost of $2,160,100. Work along the Jersey City South 
waterfront was completed at a cost of $965,300. 
Contract Number One at Weehawken to Edgewater 
was completed at a cost of $1,598,500. A continuing 
contract was awarded for Brooklyn Reach One at an 
estimated cost of $4,164,600. Engineering and 
design for the balance of the project is continuing. 
Maintenance. U.S. Debris Boats Driftmaster, 
Gelberman and Hayward and auxiliary plant were 
assigned the task of removing and disposing of 
floating debris that is a hazard to navigation. 
Removal and disposal of 645,942 cubic feet (5,046 
cords) of floating debris consisting mainly of 
driftwood, ranging in size from small blocks to 
large timbers, including pilings, pieces of 
wreckage, derelict vessels and sections of 
deteriorated pier structure was accomplished at a 
cost of $3,270,340 in FY 1986. 
Conditions as of September 30. Work authorized 
under River and Harbor Acts of 1915, 1917, and 1930 
is continuous maintenance for which no percentage 
of completion exists. For work authorized by the 1974 
Water Resources Development Act, removal of drift 
sources has been completed in New Jersey at Liberty 
State Park, the City of Elizabeth, Hoboken, and parts 
of Jersey City, Weehawken, and Edgewater. In New 
York City, work has been completed along the 
Manhattan side of the East River inclusive of Piers 
17 and 18, Stapleton, Staten Island. Removal work is 
currently underway at Brooklyn. 
19. NEW YORK HARBOR - 
ENTRANCE CHANNELS AND 
ANCHORAGE AREAS 
Location. In Upper and Lower bays, New York 
Harbor is 330 miles southwest by water of Boston 
Harbor, Mass., and 165 miles northwest of entrance 
to Delaware Bay, N.J. The Upper Bay extends about 
5.5 miles southerly from junction of Hudson and 
East Rivers opposite the Battery, New York City to the 
Narrows. Lower Bay extends about 9 miles from the 
Narrows to the sea. (See National Ocean Survey 
Charts 12327,12334,12335, and 12349). 
Existing project. Ambrose Channel 45 feet deep 
and 2,000 feet wide, extending about 10.2 miles from 
sea to deep water in the Lower bay; Anchorage 
Channel, an extension of Ambrose Channel, with 
same depth and width, in the Upper bay, opposite 
anchorage grounds, about 5.7 miles long; a 
southerly entrance channel, Sandy Hook Channel 
(East Section) 35 feet deep and generally 800 feet 
wide extending 3.4 miles from 35-foot ocean contour 
to Bayside Channel along an alignment generally 
west of the South Channel; and elimination from 
authorized project of that portion of Bayside-Gedney 
Channel east of junction with new southerly 
entrance channel; for Bayside Channel 35 feet deep 
and 800 feet wide, extending about 3.7 miles from 
junction with new southerly entrance to junction 
2-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
with Main Ship Channel; Main Ship Channel 30 feet 
deep and 1,000 feet wide, extending about 5.3 miles 
from Bayside Channel to deep water in Lower bay; a 
channel along New Jersey pierhead line connecting 
Kill Van Kull with deep water in Anchorage 
Channel, south of Liberty Island anchorage, 20 feet 
deep for 500 feet wide with widening at bends to 800 
feet and about 3 miles long; an anchorage in 
vicinity of Liberty (Bedloes) Island (about 160 acres 
in extent) 20 feet deep; and for removal of Craven 
Shoal to 30 feet deep; for a channel 16 feet deep, 200 
feet wide, and about 2.3 miles long, extending from 
bell buoy 23 to Hoffman and Swinburne Island; for 
an anchorage area in Red Hooks Flats to depths of 
45, 40 and 35 feet and an anchorage area in 
Gravesend Bay to 47 feet deep. Project depths refer to 
mean low water. Mean tidal range is 4.7 feet at Fort 
Hamilton; mean range of spring tides, 5.7 feet; 
irregular fluctuations due to wind and atmospheric 
pressure vary from 3.9 feet below mean low water up 
to 6.2 feet above mean high water. 
Local cooperation. Fully complied with. 
Terminal facilities. See Port Series No. 5, revised 
Vol. 2. 
Operations and results during period. A contract 
was awarded to Great Lakes Dredge & Dock 
Company on 21 April 1986 for the removal of all 
material except ledge rock lying above the plane of 
40 feet below mean low water from the Red Hook 
Flats Anchorage area of New York Harbor, with 
disposal of the dredged material at the EPA approved 
Mud Dump Site in the Atlantic Ocean. Work 
commenced on 22 April 1986 and was completed on 
14 May 1986. Removed 209,672 cubic yards, place 
measurement, of material at a cost of $943,524. 
Operation and maintenance funds in the amount of 
$181,244 were expended on engineering and design, 
and contract supervision and inspection, for this 
project. The U.S. Army Corps of Engineers' dredge 
"McFarland" was employed from 11 April 1986 to 20 
May 1986 to restore authorized dimensions in Main 
Ship Channel. A total of 274,026 cubic yards, place 
measurement, of material was removed at a cost of 
$937,169. 
Condition as of September 30. Work under 
existing project began in 1885 and is 100 percent 
complete. Main Ship and Bayside-Gedney 
Channels were completed to 30 feet deep in February 
1891. Deepening of Bayside-Gedney Channel to 35 
feet for a width of 800 feet was completed in June 
1939. Ambrose Channel was completed to 40 feet deep 
for a width of 2,000 feet in April 1914 and 
substantially completed to 45 feet deep for a width of 
2,000 feet in 1951. Relocation of Anchorage Channel 
was completed to 40 feet deep in October 1932. Center 
800 feet was dredged to 45 feet in June 1947 and 
westerly 600-foot strip in April 1948. Easterly 600- 
foot strip was substantially completed in June 1953. 
Channel between Staten Island and Hoffman and 
Swinburne Islands was completed in December 1920 
up to within 300 feet of southerly limits of the project. 
Dredged channel meets all needs of navigation and 
no further work of improvement is contemplated for 
the present. Channel along New Jersey pierhead 
line from Kill Van Kull to Anchorage Channel was 
completed in March 1939. Widening at bends near 
southerly and northerly ends authorized in 1948 was 
completed to depths of 45, 50, and 35 feet in October 
1976. Anchorage Channel was relocated to the 
westward in 1982. Red Hook Flats Anchorage was 
accordingly increased in area. No dredging was 
required. Liberty (Bedloes) Island anchorage was 
completed to 20 feet in October 1944. Sandy Hook 
Channel (east section) was completed to a depth of 35 
feet in June 1963. Gravesend Bay Anchorage was 
completed to a 47-foot depth in November 1977. 
20. PLATTSBURGH HARBOR, N.Y. 
Location. An area of about 25 acres along the 
westerly shore of Cumberland Bay, an arm of Lake 
Champlain. The harbor is that portion of the bay 
between the wharf front of the city of Plattsburg, 
N.Y., and the breakwater constructed by the United 
States. (See Lake Surveys Chart 172.) 
Existing projects. Provides for a breakwater 1,565 
feet long, built of timber cribs filled with rubblestone 
and capped with large stone and extending from a 
point 750 feet south of outer face of South dock 
generally northeasterly to a point about 1,400 feet 
from shore; and for dredging to a depth of 9 feet at 
low lake level between the breakwater and the 
wharves. Reference plane of low lake level is 93.0 
feet above mean sea level at Sandy Hook, N.J. 
Usual variation of lake level is 5.8 feet, and extreme 
variation from 0.6 foot below up to 8.8 feet above low 
lake level. New work for completed project cost 
$198,415. 
Terminal facilities. Four timber wharves, 
aggregating 1,780 feet in length, 400 feet of which are 
open to the public; all are privately owned. The State 
of New York has constructed a barge canal terminal 
about 1 mile north of the breakwater. These appear 
adequate for the existing commerce. 
Operations and results during period. Operations 
and maintenance funds in the amount of $58,000 was 
expended on engineering and design for repair of 
the breakwater. 
Condition at the end of fiscal year. Work under 
existing project commenced 1836 and was completed 
in 1913. Breakwater was completed in 1893 and 
dredging in 1913. 
21. RARITAN RIVER, N.J. 
Location. Rises in north-central part of New 
Jersey and flows generally southeasterly into 
Raritan Basin, between Perth Amboy and South 
2-12

NEW YORK, N.Y. DISTRICT 
Amboy, about 24 miles by water south of the Battery, 
New York City. (See National Ocean Survey Chart 
12332.) 
Previous projects. For Details see Annual Reports 
for 1915, 1918, and 1938, pages 1777, 359, and 259 
respectively. 
Existing projects. A channel 25 feet deep and 300 
feet wide extending 5.8 miles from turn in New 
York and New Jersey Channels near Great Beds 
Light to Government wharf on Main Channel, 
widened to 600 feet for 1,000 feet long opposite wharf to 
form a turning basin of same depth; thence a 
channel 15 feet deep and 200 feet wide 3 miles to 
Washington Canal; thence 10 feet deep in soft 
material, 11 feet deep in rock, and generally 100 feet 
wide with widening at bends 5 miles to Delaware 
and Raritan Canal entrance at New Brunswick, 
and a South Channel 25 feet deep and 300 feet wide 0.8 
mile from junction with Main Channel at Keasby to 
upper limit of Titanium Pigment Co. property; 
thence 15 feet deep and 150 feet wide 0.4 mile to dock 
of Middlesex County Sewerage Authority; thence 10 
feet deep and 150 feet wide 2 miles to a point 1,300 feet 
below upper junction with Main Channel at Crab 
Island. Plane of reference is mean low water. 
Mean range of tides is 5.1 feet at mouth of river and 
5.6 feet at New Brunswick; mean range of spring 
tides, 6.1 and 6.6 feet respectively. Irregular 
fluctuations due to winds and atmospheric pressure 
vary from 3.6 feet below mean low water up to 6.9 feet 
above mean high water. New work for completed 
portion of project, consisting of channels described 
above cost $1,237,000, exclusive of amounts expended 
on previous projects and including $66,000 
contributed by local interests. Dredging South 
Channel to 10 feet deep and 150 feet wide for 1,300 feet 
to upper junction with Main Channel at Crab Island 
is inactive and excluded from foregoing description 
and cost estimate. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. Complied with except local 
interests must furnish spoil-disposal areas for 
maintenance to 25-foot channel from New York & 
Long Branch Railroad bridge to junction of Main 
and South Channels, and in South Channel to 
Titanium Pigment Co. property. River and Harbor 
Act of 1962, provides local interests furnish spoildisposal 
areas and necessary retaining dikes, 
bulkheads and embankments therefore, required for 
maintenance of improvement, and hold the United 
States free from damages. 
Terminal facilities. See Port Series No.5, revised 
1965, Vol. 2, Part 2, pages 274-279 and 281. 
Operations and results during period. Operations 
and maintenance funds in the amount of $22,004 was 
expended on reconnaissance surveys and 
engineering and design for future maintenance 
dredging of this project. 
Conditions as of September 30. Entire existing 
project is about 96 percent complete. Work under 
active portion of existing project was commenced 
September 1919 and completed July 1941. A shoal 
along northerly channel line in vicinity of Victory 
Bridge was eliminated by relocation of channel in 
February 1959. Main Channel dredged 25 feet deep 
and 300 feet wide from junction with New York and 
New Jersey Channels to and including a turning 
basin of same depth opposite Government wharf, 
thence 15 feet deep and 200 feet wide to mouth of 
Washington Canal, thence 10 and 11 feet deep and 
100 feet wide to Delaware and Raritan Canal outlet 
locks at New Brunswick. South Channel dredged 25 
feet deep and 300 feet wide for 3,200 feet, thence 10 feet 
deep and 150 feet wide for 12,400 feet to within 1,300 
feet of junction with Main Channel to Crab Island. 
Model study of Raritan River was completed in 
March 1952. Work remaining under existing 
project is dredging South Channel to 10 feet deep and 
150 feet wide for 1,300 feet to upper junction with 
Main Channel at Crab Island. 
22. RONDOUT HARBOR, N.Y. 
Location. Comprises tidal mouth about 3.5 miles 
long, of Rondout Creek, whose source is about 18 
miles west of Rondout. Creek empties into Hudson 
River from the west, about 89 miles north of the 
Battery, New York City, and 55 miles south of 
Albany. 
Existing project. A channel 100 feet wide, 
widening at bends, and 14 feet deep from deep water 
in Hudson River to highway bridge, 1.3 miles above 
mouth, thence 12 feet deep to 3.5 miles above mouth, 
two parallel dikes 350 feet apart to maintain 
channel, and a branch dike to extend upstream from 
outer end of north dike to protect that dike from 
running ice in Hudson River. Mean tidal range, 
3.7 feet; mean range of spring tides, 4.2 feet; extreme 
range, 8.2 feet; irregular fluctuations due to freshets 
vary from 2 feet below mean low water up to 2.5 feet 
above mean high water. New work for completed 
project cost $131,140. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. River and Harbor Act of 1965 
provides local interests furnish lands, easements, 
and rights-of-way for construction and future 
maintenance of the Federal project as modified and 
for construction and maintenance of aids to 
navigation upon request of the Chief of Engineers, 
including suitable spoil-disposal areas and 
necessary retaining dikes, bulkheads and 
embankments therefore or the costs of such 
retaining works; hold the United States free from 
damages, and provide and maintain depths in 
berthing areas serving terminals commensurate 
with depths provided in related project areas. 
Assurances of local compliance were furnished by 
2-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
town of Ulster on June 9, by city of Kingston on June 
17, and by town of Esopus on June 20, 1966. 
Terminal facilities. Seventeen timber wharves 
with available dockage of 12,132 feet along 
waterway. Four terminals are equipped with 
transfer facilities; all are privately owned. 
Terminals adequate for present needs of commerce. 
(For latest full description see Port and Terminal 
Facilities at the Ports on Upper Hudson River, 1941, 
Corps of Engineers.) 
Operations and results during fiscal year. 
Operations and maintenance funds in the amount of 
$58,000 was expended on surveys and engineering 
and design for rehabilitation of dikes at Rondout 
Harbor, N.Y. 
Condition at end of fiscal year. Work under 
existing project was commenced April 1873 and is 
about 87 percent complete. Part of diking originally 
proposed was not built because it was deemed of 
doubtful usefulness. Two parallel dikes of an 
aggregate length of about 5,000 feet, generally 350 
feet apart, with a now obsolete spur from the old 
lighthouse south of south dike, were built across the 
bar at mouth of creek. A branch dike about 1,000 feet 
long, extending northerly from outer end of north 
dike, was also constructed. Work remaining 
consists of removal of shoals in extension of 12 foot 
channel from mile 1.8 to 3.5. 
23. SHINNECOCK INLET, N.Y. 
Location. On the south shore of Long Island, about 
95 miles east of the Battery, New York City. It is an 
opening through the sandy barrier beach, connecting 
Shinnecock Bay with the Atlantic Ocean. (See 
National Ocean Survey Chart 12352.) 
Existing project. Provides for a channel 10 feet 
deep (mlw) and 200 feet wide extending through the 
inlet to Shinnecock Bay for a distance of about 0.7 
mile; thence a channel 6 feet deep and 100 feet wide to 
the Long Island Intracoastal Waterway, a distance 
of about 1 mile; rehabilitation of the existing jetties 
and revetments. Estimate of cost for work is 
$18,700,000 (Oct 86 P.L.) including $130,000 from the 
Coast Guard and $7,060,000 to be contributed by local 
interests. (See Table 2-3 for Authorizing 
Legislation.) 
Local cooperation. The share of local cooperation 
is 38 percent of the initial cost and 47 percent of 
maintenance, operating and replacement costs 
(based on the cost sharing provisions of the Water 
Resources Development Act of 1986). The 
authorizing document also requires that local 
authorities: furnish, free of cost to the United States, 
all lands easements, rights-of-way, and suitable 
spoil-disposal areas for the initial work and for 
subsequent maintenance, when and as required; 
hold and save the United States free from damages 
due to the construction and maintenance of the 
project; provide and maintain suitable terminal 
facilities when and as required for the 
accommodation of vessels that would navigate the 
inlet and adjacent bays, open to all on equal terms; 
maintain, for the duration of the economic life of the 
project; provide and maintain suitable terminal 
facilities when and as required for the 
accommodation of vessels that would navigate the 
inlet and adjacent bays, open to all on equal terms; 
maintain, for the duration of the economic life of the 
project, continued public ownership of the publicly 
owned shores and their administration for public 
use, and continued availability for public use of the 
privately owned shores upon which a portion of the 
Federal share of the costs is based. The New York 
State Department of Environmental Conservation 
expressed their intent to provide required items of 
local cooperation by letter dated 8 September 1986. 
Terminal facilities. Shinnecock Bay, and 
adjacent ocean area, constitute an important marine 
fishery. It is part of the Long Island resort region, 
which affords recreation to thousands of people 
participating in fishing, pleasure boating, and 
bathing. Many hotels and tourists homes are located 
in the area, as well as yacht clubs, boatyards, public 
wharves and landing, and numerous private 
landings. Safe access to the ocean is necessary for 
commercial fishing and recreational craft. 
Operations and results during period. Work was 
done on preparation of the Environmental Impact 
Statement. 
Condition as of September 30. No Federal 
construction has been done. Preconstruction 
engineering and design is continuing. 
24. SHREWSBURY RIVER, N.J. 
Location. Mainly a large tidal basin in eastern 
part of New Jersey, the outlet being at the southeast 
end of Sandy Hook. (See National Ocean Survey 
Chart 12324.) 
Previous projects. For details see Annual Reports 
of 1915, 1918, and 1938, pages 1778, 373, and 267, 
respectively. 
Existing project. A channel 12 feet deep and 300 
feet wide, following the westerly shore, from deep 
water in Sandy Hook Bay 2.2 miles to a point 500 feet 
south of former location of railroad bridge at 
Highlands; then 9 feet deep and generally 150 feet 
wide, suitably widened at bends and turns, in south 
branch of river 6.8 miles to Branchport Avenue 
Bridge in city of Long Branch; and a channel in 
north branch (Navesink R.) 6 feet deep and 150 feet 
wide 6.1 miles from the junction to Red Bank. Plane 
of reference is mean low water. Mean range of tide 
at Highlands, 3.8 feet; at Seabright, 1.7 feet; at 
Branchport, 1.7 feet; and at Red Bank, 3 feet. Mean 
range of spring tides is 4.7, 2.1, 2.2, and 3.6 feet 
respectively, irregular fluctuations due to wind and 
2-14

NEW YORK, N.Y. DISTRICT 
atmospheric pressure vary from 1.9 feet below mean 
low water up to 6.5 feet above mean high water. 
Dredging turning basin and anchorage in vicinity 
of Red Bank, 6 feet deep and about 19 acres in area; a 
channel in Claypit Creek, 6 feet deep and 100 feet 
wide about 1 mile from 6-foot curve in north branch 
to head of the creek; a channel in Oceanport Creek, 6 
feet deep, 100 feet wide and 2 miles long from 
channel in south branch to New York and Long 
Branch Railroad Bridge; and a channel in Little 
Silver Creek, 6 feet deep, 100 feet wide, and 2.6 miles 
long from channel in south branch to Seven Bridge 
Road Bridge is inactive and excluded from 
foregoing description and cost estimate. Cost 
estimate for this portion (1960) is $578,000 exclusive 
of $86,000 to be contributed by local interests. (See 
Table 2-B for Authorization Legislation.) 
Local cooperation. River and Harbor Act of 1950 
provides local interests furnish lands, rights-ofway, 
and spoil-disposal areas for construction and 
future maintenance; hold the United States free from 
damages; provide and maintain a suitable public 
wharf on each of the creeks to be improved, which 
shall be open to all on equal terms; remove Locust 
Avenue bridge over Claypit Creek; and make cash 
contributions of $25,000, $33,000, and $27,500 toward 
cost of improvement of Claypit, Oceanport, and Little 
Silver Creeks, respectively. Provided further that 
construction of any unit of proposed improvement 
may be undertaken independently of the other units 
when the required local cooperation has been 
provided. These conditions have not been fulfilled. 
Requirements under prior acts have been fully 
complied with. 
Terminal facilities. There are 33 terminals with 
a total berthage of 7,986 feet on the waterway. Eight 
terminals with a total berthage of 1,000 feet are open 
to the public. In addition, many private pleasure boat 
landings have been constructed by owners of 
riverfront estates. Fifteen boatyards with storage 
space for 670 craft and equipped with 21 marine 
railways are available. None of the terminals has 
direct rail connections. Facilities considered 
adequate for existing commerce. 
Operations and results during period. Work 
commenced on 5 November 1985 and was completed 
on 16 April 1986. A total of 172,211 cubic yards of 
material, was removed at a total contract price of 
$1,235,850, of which $659,393 represented contributed 
funds from the State of New Jersey for the removal of 
98,961 cubic yards of material from the state 
channel. Operations and maintenance funds in the 
amount of $660,526 was expended for this work. 
Condition as of September 30. Work under the 
active portion of existing project began in October 
1919. Work completed consisted of providing 
authorized project dimensions in 12-foot entrance 
channel, 9-foot channel in South Branch, and a 6- 
foot channel in North Branch of the river. Work 
remaining (dredging an inlet channel across the 
base of Sandy Hook protected by jetties and 
bulkheads, a bay channel extending to the existing 
Shrewsbury River Channel and a six-lane fixed 
highway bridge to span the new inlet as authorized 
by the River and Harbor Act of 1965) was 
subsequently reclassified to inactive because of state 
and local opposition. Formal close out of this work 
remains. Under the River and Harbor Act of 1950 
work remaining consists of dredging turning basin 
and anchorage in vicinity of Red Bank and 
channels in Claypit, Oceanport, and Little Silver 
Creeks. 
25. WESTCHESTER CREEK, N.Y. 
Location. A tidal stream flowing into East River 
from north at a point 14 miles by water northeast of 
the Battery, New York City. (See National Ocean 
Survey Chart 12336.) 
Previous projects. For details see Annual Reports 
for 1921 and 1938, pages 238 and 164, respectively. 
Existing project. A 2.6 mile channel 12 feet deep at 
mean low water, 100 feet wide for 2,000 feet through 
the estuary; thence 80 feet wide for 3,000 feet; and 
thence 60 feet wide 8,800 feet to head of navigation at 
East Tremont Avenue (Fort Schuyler Road), with 
widening at bends, and two turning basins, one near 
upper end of channel, the other near Eastern 
Boulevard (Unionport) Bridge. Mean tidal range, 7 
feet; mean range of spring tides, 8.4 feet; irregular 
fluctuations due to wind and atmospheric pressure 
vary from 3.9 feet below mean low water up to 8.4 feet 
above mean high water. New work for completed 
active portion of the project cost $98,751 exclusive of 
amounts expended on pervious projects. Dredging 
turning basin to a depth of 12 feet below mean low 
water, 250 by 1250 feet in extend, 500 feet downstream 
from head of navigation, is inactive and excluded 
from foregoing description and cost estimate. (See 
Table 2-B for Authorizing Legislation.) 
Local cooperation. River and Harbor Act of 1954 
provides that local interests agree to furnish lands, 
easements, and rights-of-way for construction and 
maintenance and furnish suitable spoil-disposal 
areas for initial work and future maintenance as 
required; hold the United States free from damages; 
and provide and maintain a suitable bulkhead or 
other works approved by Chief of Engineers for 
retaining the east bank of the turning basin 
alongside Hutchinson River Parkway; and that 
local interests give assurances they will construct a 
public wharf when required. Requirements under 
prior acts have been fully complied with. 
Terminal facilities. See Port Series No. 5, revised 
1978, Vol. 2. 
Operations and results during period. A lump 
sum contract in the amount of $719,217 for the 
removal of all material, except ledge rock, lying 
2-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
above the plane of 12 feet below mean low water with 
satisfactory disposal of dredged material at the 
EPA's approved Mud Dump Site in the Atlantic 
Ocean was awarded on 24 April 1986 to Weeks 
Dredging Company. The dredging work 
commenced on 22 July 1986 and was ongoing as of 30 
September 1986. Operations and maintenance funds 
in the amount of $932,244 were expended for 
maintenance dredging accomplished during FY 
1986. 
Conditions as of September 30. Work under the 
entire existing project is about 82 percent complete. 
Work under active portion of existing project 
commenced March 1932 and was relocated by city of 
New York in 1941. Head of navigation is at East 
Tremont Avenue, Bronx, about 2.6 miles above the 
mouth. Work remaining under existing project 
consists of dredging to 12 feet below mean low water 
a turning basin 250 by 250 feet in extent to be 500 feet 
downstream from head of navigation. 
26. SUPERVISOR OF NEW YORK 
HARBOR (PREVENTION OF 
OBSTRUCTION AND 
INJURIOUS DEPOSITS) 
The District Engineer, New York District, was 
designated Supervisor of New York Harbor under 
the provisions of the River and Harbor Act of June 29, 
1888 (33 U.S.C. 441-451), as amended July 12, 1952. 
Under this Act, the Supervisor of New York Harbor 
is charged with the mission of preventing the deposit 
of obstructive and injurious materials in New York 
Harbor and its adjacent and tributary waters, 
including Long Island Sound. The River and 
Harbor Act of August 18, 1894 (33 U.S.C. 452) makes 
it unlawful for any person or persons to engage in 
fishing or dredging for shellfish in any of the 
channels leading to and from New York Harbor, or 
to interfere in any way with the safe navigation of 
those channels by ocean steamships and ships of 
deep draft; the River and Harbor Act of March 3, 1899 
(33 U.S.C. 403, 307, 409) prohibits obstructions to 
navigable waters such as unauthorized structures, 
unauthorized fill, deposit of refuse, and willful or 
negligent abandonment of vessels. Other laws 
relating to the supervision of New York Harbor and 
its tributary waters are the Clean Water Act, the 
Marine Protection, Research and Sanctuaries Act of 
1972, the Coastal Zone Management Act of 1969, the 
Fish and Wildlife Act of 1956, the Federal Power Act 
of 1920, the National Historic Preservation Act of 
1966, the Endangered Species Act of 1973, the 
Deepwater Port Act of 1972, the Wild and Scenic 
rivers Act, and the Land and Water Conservation 
Fund Act. 
Direct supervision of the waters under jurisdiction 
of the New York District was accomplished by 
means of a patrol vessel whose scope of duty includes 
surveillance of the waterfront for unauthorized 
construction or fill, surveillance of the 3-mile limit 
of tows enroute to dumping grounds in the Atlantic 
Ocean to ensure that material is not illegally 
deposited in the waters of New York Harbor, and 
investigation of wrecks and abandoned vessels. In 
addition to the patrol vessels, whose range of patrol 
was limited to New York Harbor, inspectors 
utilizing government vehicles equipped with twoway 
radios patrolled shorefront facilities and 
property. These inspectors operate out of field offices 
located at Melville, New York and one inspector 
working at the New York District Office. Their 
duties include inspection of authorized construction, 
fill or excavation in waterways, including wetland 
areas, to ensure that work is performed in 
accordance with the Corps permit. The inspectors 
also patrol all waterways in their respective areas 
and inform the public of the Corps role and 
jurisdiction as well as provide assistance in the 
preparation of permit applications. (See Table 2-E at 
end of chapter.) 
27. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 2-F at end of chapter.) 
28. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 2-G at end of chapter.) 
29. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation Activities pursuant to Section 107, 
Public Law 645, 86th Congress as amended (Preauthorization). 
(See Table 2-N at end of chapter.) 
Beach Erosion Control 
30. EAST ROCKAWAY INLET TO 
ROCKAWAY INLET & 
JAMAICA BAY, N.Y. (PT.1) 
Location. Atlantic coast of New York City, 
between East Rockaway and Rockaway Inlets, and 
the lands within and surrounding Jamaica Bay. 
The coastal area (about 10 miles long) is a peninsula 
in Queens County separating the ocean and the bay. 
(See National Ocean Survey Charts 12327, 12350, and 
12326.) 
Existing project. The project provides for 
approximately 8.7 million cubic yards of sand fill 
including the advanced placement of a two year 
G-16

NEW YORK, N.Y. DISTRICT 
supply of beach nourishment of the shore protection 
works for 10 years after completion of the initial 
beach fill. Federal participation (50 percent) 
includes first cost and periodic beach nourishment, 
the total estimated at $25,400,000 (Oct. 1986 P.L.) 
Local cooperation. Local interests must provide 
lands and rights-of-way, including borrow areas; 
bear 50 percent of total first cost presently estimated 
at $25,400,000 consisting of a cash contribution of 
$8,813,500 the final apportionment of cost to be made 
after actual costs and values have been determined 
and $16,586,500 for periodic nourishment, hold the 
United States free from damages; maintain, during 
economic life of project, continued public ownership 
and use of non-Federal publicly-owned shores upon 
which Federal participation in beach protection is 
based; maintain and operate all works after 
completion, control water pollution to the extent 
necessary to safeguard the health of bathers; local 
cooperation agreement was executed by the State May 
17, 1974 and approved for Secretary of Army May 21, 
1974. On May 22, 1974 sent to State an approved 
Escrow Agreement. 
Operations and results during period. Periodic 
Nourishment Contract No. 4 was completed in 
August 1986. 
Condition as of September 30. Advance 
engineering and design is completed. Final 
Environmental Impact Statement on file with 
Council of Environmental Quality on April 16, 1971. 
Initial beach restoration completed in FY 1977. 
Contract for first increment of periodic nourishment 
was completed in August 1982. Contract for 
construction of stone groin at Beach 149th Street was 
completed in September 1982. Contract for third 
periodic nourishment contract No. 4. is completed. 
The fifth nourishment contract is scheduled for 
summer 1988. This is the final nourishment 
contract in which Federal participation is 
authorized. 
31. SEA BRIGHT TO 
OCEAN TOWNSHIP, N.J. 
Location. That portion of the Atlantic coast of New 
Jersey in Monmouth County extending from Sea 
Bright southerly to Ocean Township - length about 
12 miles. Sea Bright is about 30 miles by water south 
of the Battery, New York City. Erosion has seriously 
reduced the width of most beaches in the study area 
with consequent exposure of the shore to storm 
damage. Because of this erosion of the shore the area 
does not provide sufficient recreational beaches for 
the proper accommodation of the present and 
prospective tributary population. 
Existing project. Provides for Federal 
participation in the restoration and protection of the 
shore from Sea Bright to Ocean Township by 
artificial placement of sand to widen the beach to a 
minimum width of 100 feet at an elevation of 10 feet 
above mean low water and by the construction of 23 
new groins and the extension of 14 existing groins 
in the Sea Bright - Ocean Township section. The 
project provides for Federal participation in periodic 
nourishment costs for a period of 10 years from the 
year that the total quantity of fill placed has equalled 
that required to restore the beach to project 
dimensions in that section. Total estimated Federal 
cost is $91,000,000. Total estimated non-Federal for 
all requirements of local cooperation is $12,000,000. 
(See Table 2-B for Authorizing Legislation.) 
Local cooperation. Reconstruction of the sea wall 
at Sea Bright and Monmouth was funded by the State. 
In addition the State provided funds in the amount of 
$100,000 for a limited analysis by the New York 
District with a view to deferring certain construction 
elements. 
Operations and results during period, and 
Condition as of September 30. Construction has not 
been initiated, but the project is in active status with 
work continuing on the preparation of General 
Design Memorandum and Environmental Impact 
Statement. 
32. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Table 2-H at end of chapter.) 
33. BEACH EROSION CONTROL 
WORK UNDER 
SPECIAL AUTHORIZATION 
Beach Erosion Control activities pursuant to 
Section 103 Public Law 826, 84th Congress as 
amended (preauthorization). 
(See Table 2-0 at the of chapter.) 
Flood Control 
34. ARDSLEY, N.Y. 
Location. The Village of Ardsley in Westchester 
County, New York is located on the Saw Mill River 
approximately 5 miles upstream from its junction 
with the Hudson River. (See U.S. Geological Survey 
Map, White Plains, N.Y.) 
Existing project. The Federal flood control project 
provides for relocation of the existing channel from 
the upstream limit of the project downstream for 
approximately 1,000 feet, and approximately 290 feet 
of concrete channel upstream of the new Ashford 
Avenue Bridge. Upstream of the concrete channel 
along the left bank of the Saw Mill River, 425 feet of 
floodwall will be constructed running north of the 
Conrail Bridge. Ponding areas, drainage ditches 
2-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
and other drainage structures will be provided. The 
total estimated Federal cost for the project is 
$3,310,000 exclusive of land, relocations and other 
work to be provided by local interests at an estimated 
cost of $1,100,000 (October 1986 P.L.). 
Local cooperation. In accordance with cost 
sharing and financing concepts reflected in S.1567, 
local interests are required to furnish all lands, 
easements and rights-of-way including relocations 
that are necessary for flood control improvements 
presently estimated at $610,000 and operate and 
maintain the project at an estimated cost of $29,000; 
interests pay 25 percent of the costs allocated to flood 
control for a total cost of $1,100,000 project cost but not 
less than that required by project authorization 
presently estimated at $1,100,000. The New York 
State Department of Environmental Conservation, 
the local sponsor, in an 11 December 1973 letter, 
indicated its intent to comply with the items of local 
cooperation and reaffirmed this on 15 August 1979 
and 23 August 1985. The State of New York, in a 18 
October 1985 letter, expressed this willingness to 
assume responsibility as local sponsor in 
accordance with the Cost Sharing and financing 
concepts agreed to by the Administration and 
Senator Majority Leadership Compromise as 
reflected in WRDA 1986. 
Operation and results during period. Preconstruction 
planning continued. 
Condition as of September 30. Plan of Study 
approved in March 1979. Construction has not been 
initiated. 
35. LIBERTY STATE PARK 
LEVEE AND SEAWALL, N.J. 
Location. At Liberty Park, in Jersey City, Hudson 
County, New Jersey, directly behind Ellis Island 
and Statue of Liberty, in Upper New York Bay. (See 
National Ocean Survey Chart 12334.) 
Existing project. Construction of a levee and sea 
wall, and pedestrian walkways; over 
environmentally sensitive areas. The construction 
of the levee project will allow the creation of a large 
Greenpark to include a wetlands preserve, an 
inland water course and boat basin, a marina, an 
amphitheater, indoor and outdoor recreation 
facilities, picnic areas, historic areas, community 
facilities, restaurants, plaza, and many other areas 
for both active and passive recreational and 
aesthetic benefit to visitors. The stone armored levee 
will also serve as a settlement-free base for 
subsequent construction of a tree-lined promenade, 
the Liberty walk, curving along the water's edge. 
The Federal cost of construction is estimated at 
$19,100,000; with an additional $19,100,000 
contribution by local interests including lands, 
certain relocations, utilities, and interior drainage. 
Local cooperation. In accordance with the project 
authorization, local interests are required to furnish 
all land, easements and rights-of-way including 
relocations, save those existing utilities passing 
through the proposed levee, necessary for the flood 
control improvements and to operate and maintain 
the project at an annual cost estimated to total 
$56,000. The State will assume all costs for 
construction of an interior drainage system to 
provide (10) year level of protection estimated to be 
$5,100,000. Local interests have agreed to 
voluntarily pay 50% of project cost. The New Jersey 
Department of Environmental Protection is the local 
sponsor. The local cooperation agreement was 
executed on 26 June 1986. 
Operation and results during period and 
Conditions as of September 30. Phase I is completed. 
The District has completed their review of final 
contract documents for seawall (Area 2) and 
walkways (Areas 3 and 4) contracts. The contract 
for the levee and seawall is intended to be advertised 
in mid-November. 
36. PASSAIC RIVER BASIN, 
N.J. & N.Y. 
Location. The Passaic River Basin, comprising 
787 square miles in northeastern New Jersey and 
148 square miles in southern New York State, is 
located in the greater New York City Metropolitan 
area. The Passaic River Basin is roughly elliptical 
in shape 26 miles long and 56 miles wide - and 
contains portions of Bergen, Essex, Morris, Passaic, 
Hudson, Somerset, Sussex and Union Counties in 
New Jersey. The Basin also includes parts of 
Orange and Rockland Counties in New York. 
Previous projects. Two Federal flood control 
projects have been completed by the Corps of 
Engineers in Passaic River Basin. A $67,400 
desnagging, debris removal, and channel 
restoration project was completed in 1951 along 
Beaver Brook and the Pequannock Township Ditch, 
tributaries of the Pompton River in Pequannock 
Township, N.J. Along the Pompton River, a 
channel clearing project including shoal removal 
and channel restoration was implemented in the 
two-mile reach from the Delaware, Lackawanna 
and Western Railroad Bridge to the Erie Railroad 
(Greenwood Lake Branch) Bridge. This work, in 
Pequannock Township, Wayne Township and 
Lincoln Park Borough, N.J., was completed in 1954 
at a cost of $50,000. 
Existing project. The project was authorized for 
Phase I advance engineering and design study in 
Section 101(a) of the Water Resources Development 
Act of 1976 in accordance with the February 18, 1976 
report of the Chief of Engineers. The estimate of 
Federal cost under the authorizing legislation is 
$1,140,000,000 (October 1986 P.L.), plus a $229,000,000 
2-18

NEW YORK, N.Y. DISTRICT 
cash contribution from local interests and 
$151,000,000 for items of work to be contributed by 
local interests. The recommended plan for flood 
protection, navigation, hurricane protection and 
recreation, included a flood detention reservoir, 
channel diversions and modifications, levees and 
floodwalls, and streambank filling and grading. 
These works would provide protection against storm 
with a recurrcnce interval of 235 years, which is 20 
percent larger than the October 1903 flood of record. 
Six independent tributary local protection plans 
were also recommended. However, because of a 
lack of public support for structural components of 
the project in the New Jersey portion of the Basin, the 
entire project was reformulated during the Phase I 
study. 
The House Public Works Committee Report (94- 
1702) on the 1976 Water Resources Development Act 
directed "...the reformulation of the plan for water 
management and flood control for the entire Passaic 
Basin." This report further stated that local 
opposition to any plan which relies upon extensive 
use of dikes, dams and levees, such as those proposed 
in previous survey reports, mandates that the 
following alternatives, or any combination thereof, 
shall be the only ones surveyed and considered: (a) 
A full range of nonstructural flood control 
alternatives to include land acquisition, flood plain 
mapping, flood-proofing, developing early warning 
systems and relocation of buildings; (b) A tunnel 
diversion plan; (c) A system of tunnels addressing 
the needs of the entire basin; (d) Plans that combine 
local protection works where locally acceptable and 
nonstructural solutions including improvements to 
stream carrying capacity in accordance with 
different needs in the Lower Basin and in the 
Central Basin; (e) Evaluation of fulfilling water 
supply objectives together with flood control; (f) 
Aquifer recharge and underground storage; and (g) 
Reservoir management in the headwaters. The 
Phase I Study considered these alternatives in the 
formulation of revised plans. 
Conditions as of September 30. The reformulation 
study was initiated in October 1977 under the 
existing authorization and Congressional Guidance 
in House Report 94-1702. The Study schedule runs 
through September 1987 at an estimated cost of 
$21,000,000. A wide range of feasible Basin-wide 
alternative plans were developed. These 
alternatives, which were presented for extensive 
public review, included tunnel diversions, channel 
modifications, levees and floodwalls, and 
nonstructural measures. In April 1984, the Passaic 
Basin experienced flooding estimated to be the worst 
in 40 years. In June 1984, the State of New Jersey 
selected a dual inlet diversion tunnel plan as the 
local option for detailed plan formulation. A draft 
Phase I General Design Memorandum and draft 
Environmental Impact Statement, recommending 
the Pompton River/Passaic River Dual Inlet Tunnel 
Diversion Plan, were completed during FY 1986. 
Local protection plans were completed for tributary 
flood damage areas along the Ramapo and Mahwah 
Rivers at Mahwah, N.J., and Suffern, N.Y., Molly 
Ann's Brook at Haledon, Prospect Park and 
Paterson, N.J., the Ramapo River at Oakland, N.J., 
and the Lower Saddle River in Bergen County, N.J. 
These projects were authorized in the Water 
Resources Development Act of 1986. 
37. SAW MILL RIVER AT ELMSFORD 
AND GREENBURGH, N.Y. 
Location. On the Saw Mill River in the town of 
Greenburgh, N.Y. One portion known as Babbitt 
Court lies along the river immediately south of the 
Village of Elmsford. The second portion of the 
project, known as the Elmsford-Greenburgh area, is 
north of the Village of Elmsford, separated from 
Babbitt Court by approximately 4,000 feet. (See U.S. 
Geological Survey Map, White Plains, N.Y.) 
Existing project. The project provides for 
approximately 2.6 miles of 20 foot wide channel 
improvement along the Saw Mill River from the 
upper reaches in the Town of Greenburgh 
downstream to approximately Exit 7A of the New 
York State Thruway, with an additional 675 feet of 
channel modification along the tributary Mine 
Brook. A diversion channel will be constructed 
south of the Saw Mill River Parkway. The total 
estimated Federal cost (October 1986 P.L.) for the 
project is $4,600,000 exclusive of land, relocations 
and other work to be provided by local interests at an 
estimated cost of $1,530,000. (See Table 2-B for 
Authorizing Legislation.) 
Local cooperation. Local interests must provide 
lands and rights-of-way for construction, including 
borrow, ponding, and waste disposal areas; hold the 
United States free from damages; maintain and 
operate completed works; provide all alterations, 
relocations, and necessary replacements of existing 
facilities, including bridges, highways, sewers, 
utilities, and railroad modifications and 
relocations other than bridges and bridge 
approaches; protect the channel and other flood 
works from future encroachment or obstruction, 
including waste disposal which would reduce or 
otherwise impair their flood-carrying capacity, or 
provide a pumping station or additional gravity 
outlets, as appropriate, to compensate for any loss in 
ponding area effectiveness due to modification of or 
encroachment upon such areas; take appropriate 
measures to control development in partially 
protected areas and fringe areas not included in the 
project with a view toward preventing an undue 
increase in the flood damage potential; and at least 
annually, notify those affected that flooding will 
still be possible from large floods. New York State is 
2-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Local Cooperating Agency. The New York State 
Department of Environmental Conservation, by 
letter dated June 12, 1974, indicated the State's 
intention to cooperate in the proposed plan, and 
agreed to the current Administration's cost sharing 
by letter dated 11 June 1986. 
Operation and results during period. During 
Phase I preconstruction planning the authorized 
project was found to be no longer economically 
justified. Phase I project reformulation to develop 
an alternative plan of improvement has been 
completed. 
Condition as of September 30. Plan of Study 
approved January 28, 1977. Preconstruction 
planning started in February 1977. The final Phase 
I General Design Memorandum was approved in 
March 1986. The final Phase II General Design 
Memorandum is scheduled for submission in June 
1987. 
38. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspections of completed flood control works and 
beach erosion and hurricane protection projects were 
performed to determine the extend of compliance by 
local interests with the requirements of operation 
and maintenance. 
39. OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
(See Table 2-I at end of chapter.) 
40. DAM SAFETY PROGRAM 
Beginning in FY 1985 the New York District 
performed a two phase modification to Waterbury 
Dam in an attempt to drastically reduce or totally 
eliminate a long existing seepage problem at the 
dam. The first phase of construction is the addition 
of 48 inch pipe to the two existing 54 inch pipes that 
comprise the existing outlet works of the dam. This 
work was completed in July 1985 at a cost of $513,400. 
The second phase of work is the partial rebuilding of 
the toe of the dam to include a seepage filter and 
monitoring system and to fill voids by means of 
sand injection and to fill voids in the river gorge by 
grouting. The seepage filter was completed on 11 
November 1986 at a cost of $933,100. The sand 
injection and gorge grouting work was completed on 
17 December 1986 at a cost of $1,604,367. The sand 
injection and gorge grouting work was done by the 
Baltimore District for the New York District. 
41. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Natural Disaster and Emergency Flood Control 
Activities. Pursuant to Public Law 84-99 and 
antecedent legislation advance preparation, 
emergency operations, rehabilitation, emergency 
drinking water, advance measures and drought 
assistance. 
Under disaster preparedness, the New York 
District completed revisions of various emergency 
manuals and pamphlets, attended meetings and 
seminars dealing with emergency response and 
preparation, provided in-house training to District 
employees in emergency operations activities, and 
purchased supplies and equipment to maintain its' 
flood fighting and response capability. 
Under emergency operations, the New York 
District provided technical assistance and sandbags 
to local, county and state governmental 
organizations which requested such aid during 
several minor storm/flood events. 
The District received mission assignments from 
the Federal Emergency Management Agency 
(FEMA) under the provisions of PL93-288 to prepare 
detailed damage survey reports in Long Island New 
York, and Monmouth County New Jersey following 
the Presidential Disaster Declaration resulting 
from Hurricane Gloria. On Long Island the New 
York District surveyed 169 applicants including 
State Agencies, county and local governments and 
Fire Districts throughout Nassau and Suffolk 
Counties. Over 900 detailed Damage Survey Report 
packages were completed recommending to FEMA 
over $56 million of eligible damages incurred by 
applicants. 
42. EMERGENCY STREAMBANK 
AND SHORELiNE PROTECTION 
Activities pursuant to Section 14, Public Law 526, 
79th Congress as amended (Preauthorization). 
(See Table 2-Q at end of chapter.) 
43. SURVEYS 
(See Table 2-J at end of chapter.) 
44. COILECTION AND STUDY 
OF BASIC DATA 
Costs for the period of $152,966 for flood plain 
management services are set forth in Table 2-L at 
the end of chapter. 
2-20

NEW YORK, N.Y. DISTRICT 
45. DEAIJTHORIZED PROJECTS 
A total of 23 projects were deauthorized by 
Congressional Action pursuant to Section 12 of 
Public Law 93-251, Water Resources Development 
Act of 1976. (See Table 2-M at end of chapter.) 
2-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 2-A COST AND FINANCIAL STATEMENT 
See 
Section Funding FY 83 FY 84 FY 85 FY 86 Total Cost to 
in Text Projects September 30,1986 
1. Aquatic Plant 
Control 
2. Bay Ridge & Red 
Hook Channels, N.Y. 
3. Bronx River, N.Y. 
4. Browns Creek, N.Y. 
5. Buttermilk Channel, 
N.Y. 
6. East Rockaway Inlet 
7. Fire Island To 
Jones Inlet, N.Y. 
8. Glen Cove Creek, N.Y. 
New Work 
Approp 
Cost 
New Work 
Aprop. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
105,000 
102,224 
100,000 
43,973 
185,000 
176,102 
336,000 1,339,000 7,059,000 
343,044 1,339,000 7,056,993 
- - 60,000 
- - 59,390 
- - 199,790 
- - 199,790 
- - 717,000 
- - 716,771 
(800) 
45,349 
100,000 
129,779 
3,937 
390,034 2,030,000 
377,768 2,042,166 
- 1,695,700 
21,005 1,681,761 
2-22 
220,000 
277,065 
164,000 
159,069 
837,000 
826,094 
18,412 
18,412 
30,000 
30,000 
1,123,8061 
1,095,6322 
5,523,297 
5,528,29727 
30,168,988 
30,162,050 
1,149,946 
1,149,946 
2,844,853 
2,833,3375 
33,97630 
33,97630 
525,529 
5233,781 
4,590,201 
4,590,2019 
4,269,773 
4,269,773 
83,969 
533,3344 
7,522,736 
7,522,586 
594,355 
594,35528 
5,125,404 
5,181,797 
29,760 
29,760 
59,7605 
56,6855 
425,000 
438,934 
30,000 
26,925

NEW YORK, N.Y. DISTRICT 
TABLE 2-A (Continued) COST AND FINANICIAL STATEMENT 
See 
Section Funding FY 83 FY 84 FY 85 FY 86 Total Cost to 
in Text Projects September 30,1986 
9. Hudson River, N.Y. 
10. Jones Inlet, N.Y. 
11. Kill Van Kull-Newark 
Bay, N.J. & N.Y 
12. Long Island 
Intracoastal 
Waterway, N.Y. 
13. Moriches Inlet, N.Y. 
(Required 
Contributed 
Funds) 
14. Narrows of Lake 
Champlain, N.Y. 
15. Newark Bay, 
Hackensack & 
Passaic Rivers, N.J. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
1,838,256 758,400 
1,314,247 1,299,002 
673,000 1,792,600 
,579,097 1,873,853 
98,000 1,709,966 128,500 
98,000 1,699,398 137,883 
- - 240,000 
- 15,000 254,025 
887,000 
816,138 70,862, 
- 100,000 
20,660 81,283 
450,000 
449,913 
15,000 
-0- 
-0- 
-0- 
-0- 
358,855 -0- 
975,000 
971,074 
95,000 
64,000 
535,000 
44,249,8036,7,8 
44,249,865 
29,375,415 
29,270,279 
1,822,53010 
1,822,530 
11,265,576 
11,264,490 
240,000 
269,025 
- 
235,964 
235,964 
4,678,8621 
4,687,8491 
1,141,000 
1,076,282 
9,422 
9,422 
3,390,000 
937,301 
681,81112 
681,811 
25,000 
26,547 
630,000 
630,000 
29,000 
28,744 
30,000 
29,326 
82,000 
82,930 
1,021,695 
1,021,674 
29,014,510 
9,014,51122,23 
Approp. 7,681,000 3,866,000 (295,000) 
Cost 2,6154,509 3,936,107 (296,200) 
955,000 
956,975 
28,206,036 
23,211,427 
2-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 2-A (Continued) COST AND FINANICIAL STATEMENT 
See 
Section Funding FY 83 FY 84 FY 85 FY 86 Total Cost to 
in Text Projects September 30,1986 
16. Newtown Creek, 
N.Y. 
17. New York and New 
Jersey Channels 
18. New York Harbor- 
Collection and 
Removal of Drift 
(Required 
Contributed 
Funds) 
19. New York Harbor- 
Entrance Channel 
and Anchorage Areas 
20. Plattsburgh 
Harbor, N.Y. 
21. Raritan River, N.J. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Aprop. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint & Oper 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New York 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New York 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
(13,568) 
53,554 
12,856 
12,856 
94,781 
94,781 
50,000 
50,950 
1,168,354 
1,168,354 
1,675,342 
1,676,292 
73,053,435 
73,052,43515,16,17 
680,000 8,704,000 1,162,000 1,332,000 
657,732 8,386,840 1,096,073 1,397,900 
2,570,000 2,700,000 1,930,000 2,105,000 
1,654,623 2,960,800 1,801,315 2,351,181 
- 2,700,000 2,820,000 3,210,000 
3,245,344 2,960,800 2,786,239 3,278,166 
470,459 1,380,950 
181,077 1,250,972 
707,096 
537,350 1,830,700 
8,047,000 8,739,000 3,4419,900 4,033,000 
7,525,976 9,132,502 3,508,699 4,130,537 
58,000 
58,000 
6,308,359 
40,657,574 
19,334,000 
18,571,923 
42,192,89619 
42,387,718 
21,279,000 
20,483,872 
6,464,328 
7,424,32229 
45,009,7102c 
45,009,710 
40,382,524 
43,202,475 
198,415 
198,415 
256,415 
256,415 
- 1,,551,47021 
- 1,551,47025 
- 180,000 1,119,000 
- 177,126 1,119,269 
20,000 
22,004 
11,432,703 
11,432,302 
2-24 
454,773 
454,773

NEW YORK, N.Y. DISTRICT 
TABLE 2-A (Continued) COST AND FINANICIAL STATEMENT 
See 
Section Funding FY 83 FY 84 FY 85 FY 86 Total Cost to 
in Text Projects September 30,1986 
22. Rondout Harbor, 
N.Y. 
23. Shinnecock Inlet, N.Y. 
24. Shrewsbury River, N.J. 
25. Westchester Creek, 
N.Y. 
26. Supervisor of New 
York Harbor 
30. East Rockaway Inlet 
to Rockaway Inlet 
and Jamaica Bay, 
N.Y. (PI) 
(Required 
Contributed 
Funds) 
31. Sea Bright to 
Ocean Tnp, N.J. 
34. Ardsley, N.Y. 
35. Liberty State Park 
and Seawall, N.J. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
58,000 
58,000 
-0- 
151 
80,000 
79,472 
832,000 
784,221 
483,006 
526,571 
660,000 
660,527 
- 950,000 
- 932,244 
560,000 577,000 
564,738 576,363 
- 2,900,000 2,250,000 3,445,000 
220,088 2,918,123 2,224,852 3,212,342 
127,660 
186,169 
- 2,316,000 
3,967 2,251,199 4,805,000 
- 1,300,000 1,435,000 
- 1,252,310 1,435,815 
846 
45,000 
32,325 
15,000 
-0- 
20,000 
-0- 
83,000 
83,000 
25,000 
20,250 
142,437 
142,437 
200,437 
200,437 
-0-
173 
1,145,457 
1,145,457 
2,472,880 
2,473,879 
175,9339 
175,933 
3,871,31111 
3,853,555 
28,140,447 
28,622,756 
21,345,356 
21,03,769 
17,120,961 
19,438,942 
2,735,000 
2,687,110 
443,000 
415,324 
225,043 
200,338 
2-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
1. Of which $12,500 is for North Atlantic Division Accounts. 
2. Of which $12,127 is for North Atlantic Division Accounts. 
3. Include $1,040,000 for new work and $1,040,000 expended 
for the portion under construction general. 
4. Excludes $1'00,000 for new work expended from 
contributed funds and includes $82,600 for new work 
expended from public work fund. 
5. Includes $68,036 for new work and $216,931 for 
maintenance for previous projects. 
6. Includes $5,112,694 for new work for previous project. 
7. Includes $238,350 for new work expended from public 
works funds and $311,461 emergency relief runds. 
Excludes $81,373 expended from contributed funds. 
8. Excludes $454,273 expended between August 18 1915 and 
June 30, 1935, for operation and care of lock and dam at 
Troy, N.Y., under permanent indefinite appropiation. 
Excludes $23,735 reimbursement for repairs to Troy 
Lock. 
9. Includes $77,182 for new work for previous projects. 
10. Excludes $1,882,530 for new work expended from 
contributed funds. 
11. Includes $66,000 for maintenance for previous projects. 
12. Includes $115,000 for new work expended from 
contributed funds. 
15. Includes $ 12,809,975 for new work for previous projects 
and $6,621 for new work for Lemon Creek, Staten Island, 
N.Y. 
16. Excludes $7,712 for new work expended from contributed 
funds. 
17. Includes $807,000 for new work expended from public 
works funds and $2,023,308 for new work expended from 
emergency relief funds. 
18. Includes $1,160,380 for maintenance for previous project, 
and $1,621 for maintenance of Lemon Creek, Staten 
Island, N.Y. 
19. Includes $2,491,206 expended to date for construction of a 
land-based overfire air pit incinerator ($1,493,393 in 
maintenance funds and $997,813 in O&M funds). 
20. Includes $116,530 applied to removing wrecks authorized 
by acts prior to adoption of existing projects. 
21. Includes $673,155 for new work for previous project. 
22. Includes $1,836,403 for new work expended from 
contributed funds. 
23. Excludes $285,600 for new work expended from 
contributed funds. 
24. Includes $1,490,715 for maintenance for previous 
projects. 
25. Excludes $292,685 for new work expended from 
Ordinance funds and $66,000 for new work expended 
from contributed funds. 
26. Includes $111,419 for maintenance for previous projects 
and $64,560 extended from public works funds. 
27. Include $1,246,100 for new work for previous projects and 
$64,560 extended from public works funds. 
28. Excludes $90,190 for new work expended from contributed 
funds. 
29. Includes $400,000 Jobs Bill funds. 
30. Includes $200,000 Jobs Bill funds. 
2-26 
TABLE 2-A (Continued) COST AND FINANICIAL STATEMENT

NEW YORK, N.Y. DISTRICT 
TABLE 2-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
River and Harbor 
Act of 1958 
AQUATIC PLANT CONTROL (See Section 1 of Text) 
Control and Progressive Eradication of obnoxious Aquatic 
Plant growths 
H. Doc. 37, 85th Cong., 
1st sess. 
Section 104 and Harbor Provided that all research and Planning cost to be borne fully 
Act of 1958 by the United States. 
Section 302 River and 
Harbor act of 1965 
Mar. 3, 1899 
Mar. 2,1907 
July 3,1930 
Mar. 4, 1913 
Sept.19,1890 
June 13,1902 
July 3,1930 
Aug. 26,1937 
May 17,1950 
1958 River and 
Harbor Act 
1962 River and 
Harbor Act 
Mar. 3, 1925 
Modified project to include control of waterchestnut. 
BAY RIDGE AND RED HOOK CHANNELS, N.Y. 
(See Section 2 of Text) 
Channel 40 feet deep and 1,200 feet wide. 
Dredging to obtain first a depth of 35 feet, subsequently 
increasing depth of 40 feet for full width. 
Widening of Bay Ridge Channel to 1,780 feet. 
BRONX RIVER, N.Y. (See Section 3 of Text) 
Channel 10 feet deep and 100 feet wide from East River 
to Dam at East 177th Street. 
BROWNS CREEK, N.Y. (See Section 4 of Text) 
6 foot channel for 1,850 feet and 4 feet 
for 1,350 feet, and 2 jetties. 
BUTTERMILK CHANNEL, N.Y. (See Section 5 of Text) 
Channel 1,200 feet wide and not less than 30 feet deep. 
EAST ROCKAWAY INLET, N.Y. (See Section 6 of Text) 
Channel 12 feet deep and 250 feet wide, and a jetty. 
FIRE ISLAND TO JONES INLET, N.Y. 
(See Section 7 of Text) 
Construction of jetty. 
Channel 10 feet deep. 
Three dredging operations with sand serving as 
nourishment to the beaches westerly of the inlet. 
Extension of existing jetty, a littoral reservoir, a navigation 
channel and dikes, sand deposit on westery beaches. 
GLEN COVE CREEK, N.Y. (See Section 8 of Text) 
Channel 8 feet deep and 100 feet wide. 
H. Doc. 337, 54th Cong. 2d 
Sess. (Annual Report 
1899, P. 1177). 
Rivers and Harbors Committee 
Doc. 44, 71st Cong. 
2d sess. 
H. Doc. 897, 62d Cong. 
2d sess. 
H. Ex Doc. 22, 51st Cong. 
1st sess. 
H. Doc. 122, 56th Cong., 
2d sess. (Annual Report 1901, 
p. 1299) 
H. Doc. 19, 71st Cong., 
1st sess. 
Rivers and Harbor Committee 
Doc. 33, 75th Cong. 1st sess. 
H. Doc. 762, 80th Cong., 
2d sess. 
H. Doc. 411, 84th Cong., 
2d sess. 1 
H. Doc. 115, 89th Cong., 
1st sess. 
H. Doc. 207, 68th Cong. 
1st sess. 
2-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 2-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3,1930 
July 1, 1935 
Aug. 30,1935 
June 20,1938 
Sep. 3,1954 
P.L. 89-72 
Mar. 2,1945 
Channel 27 feet below Hudson 
Operation and care of lock and dam at Troy were included 
in project. 
Relocation of 12-foot channel between Troy and Waterford 
H. Doc. 210, 70th Cong., 
1st sess. 
S. Doc. 155, 72nd Cong., 
2d sess. 
Deepen channel between Albany and Waterford to 14 feet H. Doc. 572, 75th Cong., 
with no change in depths for harbors in front of Albany 3d sess. 
and Troy. 
Deepen channel between New York City and Albany to 32 H. Doc. 228, 83d Cong. 
feet and construct a turning basin and 2 anchorages. 1st sess. 
Mooring facilities. 
JONES INLET, N.Y. (See Section 10 of Text) 
Construction of jetty and channel 12 feet deep and 250 feet wide. H. Doc. 409, 77th Cong. 
FY 1985 Supplemental 
Appropriations Act 
(PL99-88) 
Aug. 26,1937 
July 14,1960 
KILL VAN KULL-NEWARK BAY, N.J. & N.Y. 
(See Section 11of Text) 
Deepening existing 35 foot channels in increments 
to 40 feet and then 44 feet. 
LONG ISLAND INTRACOASTAL WATER, N.Y. 
(See Section 12 of Text) 
Channel 6 feet deep and 100 feet wide. 
MORICHES INLET, N.Y. (See Section 13 of Text) 
Channel 10 feet deep and 200 feet wide in inlet and 6 feet 
deep and 100 feet wide in the Bay, and 2 jetties. 
H. Doc 181, 75th Cong., 
1st sess. 
H. Doc. 126, 86th Cong., 
1st sess. 
Aug. 8,1917 
Mar. 2,1907 
Feb. 27,1911 
July 25,1912 
Jan. 21,1927 
July 3,1930 
Mar. 22,1945 
Mar. 2,1945 
Sept. 3,1954 
Oct. 23,1962 
NARROWS OF LAKE CHAMPLAIN, N.Y. AND 
VERMONT (See Section 14 of Text) 
Channel 12 feet deep and 150 feet wide. H. Doc. 1387, 62d Cong., 
3d sess. 
NEWARK BAY, HACKENSACK AND PASSAIC RIVERS, NJ. 
(See Section 15 of Text) 
16-foot channel in Passaic River H. Doc. 441, 59th Cong., 
2d sess. 
Widening 16-foot channel in Passaic River H. Doc. 441, 59th Cong., 
2d sess. 
20-foot channel in Passaic River. H. Doc. 707, 62d Cong., 
10-foot channel in Passaic River. H. Doc. 284, 60th Cong., 
2d sess. 
30-foot channel in Passaic River. H. Doc. 156, 71st Cong., 
2 sess. 
35 and 37 feet in main channel of Newark Bay and branch S. Doc 250, 79th Cong., 
channel to an inshore channel at Port Neward terminal and 2d sess. 
remove portion of rock area at Bergen Point to same depths. 
Modification of local cooperation for 10-foot channel in H. Doc. 430, 76th Cong., 
Passaic River 1st sess. 
34-32 foot channel in Hackensack River including approach H. Doc. 252, 82d Cong., 
channel in Newark Bay from branch channel at Port 1st sess. 
Newark Terminal and a 25-foot turning basin. 
35-foot channels at Port Elizabeth. H. Doc. 289, 88th Cong., 
2d sess. 
2-28

NEW YORK, N.Y. DISTRICT 
TABLE 2-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Nov. 7,1966 
Mar. 2, 1919 
July 3,1930 
Sept. 6,1933 
Aug. 30,1935 
May 28,1935 
May 17,1950 
Oct. 27,1965 
Mar.4, 1915 
July 3,1930 
Dec. 31,1970 
Mar. 7, 1974 
July 5, 1884 
Mar. 3, 1899 
Widening 35-foot channel in Newark Bay, provision of two H. Doc. 494, 89th Cong., 
maneuvering areas, widening entrance into Port Elizabeth 2d sess. 
and Port Newark branch channels, deepening and widening 
Newark Bay 32-foot channel, and provision of a turning basin 
at junction of Hackensack and Passaic Rivers; and deepening 
12-foot channel in Hackensack River to 15 feet. 
Additional widening at junction with Kill Van Kull Report on file in the Office of 
by deepening to 35 feet a triangular area at the eastern the Chief of Engineers. 
end of the 30-foot channel south of Shooters Island. 
NEWTOWN CREEK, N.Y. (See Section 16 of Text) 
20-foot channel H. Doc. 1936, 64th Cong., 
1st sess. 
23-foot channel Rivers and Harbors 
Committee Doc. 42, 
71st Cong., 2d sess. 
12-foot channel in English Kills Rivers and Harbors 
Committee Doc. 4, 
75th Cong., 1st sess. 
NEW YORK AND NEW JERSEY CHANNELS 
(See Section 17 of Text) 
Anchorage off Perth Amboy to 35 feet. Rivers and Harbors Committee 
Doc. 17, 71st Cong., 2d sess. 
Channels 35 feet deep from lower bay to upper bay, except H. Doc. 133, 74th Cong., 
between vicinity of Smith Creek and vicinity of Piles Creek 1st sess. 
to 30 feet with anchorage 38 feet deep at Sandy Hook and 
Perth Amboy. 
Channel 35 feet deep from vicinity of Smith Creek to H. Doc. 233, 81st Cong., 
vicinity of Piles Creek. 1st sess. 
Widen entrance to Kill Van Kull to 1,400 feet narrowing H. Doc. 108, 89th Cong., 
to a minimum width of 1,000 feet. 1st sess. 
NEW YORK HARBOR, COLLECTION AND REMOVAL 
OF DRIFI' (See Section 18 of Text) 
Allotment from appropriations made for New York Harbor and 
its immediate tributaries may be used for collection and 
removal of drift in these waterways. 
Carrying on this work as a separate and distinct project. 
Increase scope of project to include removal and disposal P.L. 91-611, 91st 
of derelict vessels, some deteriorated shore structures and Cong., H.R. 19877 
debris along shores; and the repair of other shore structures; 
all subject to approval by Secretary of the Army and the President. 
Removal and disposal of derelict vessels, some deteriorated P.L. 93-251, 93rd Cong., 
shore structures and debris along shores and the repair 
of other shore structures. 
NEW YORK HARBOR, ENTRANCE CHANNELS 
AND ANCHORAGE AREAS (See Section 19 of Text) 
Main-Ship-Bayside-Gedney to 30 feet for width of 1,000 
feet (dimensions fixed by Secretary of War, De. 27, 1886 
by authority of Act of Aug. 5, 1886). 
Ambrose Channel (East Channel) to 40 feet. 
Annual Reports 1887, p.6 2 
and 1888, p. 63 
H. Doc. 159, 55th Cong., 
3d sess. (Annual Report 
1899, p. 1279) 
2-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 2-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 25,1910 
Aug. 8,1917 
Aug. 8,1917 
July 4, 1836 
July 11,1870 
Sept. 19,1890 
June 25,1910 
Mar 2,1919 
Jul. 3,1930 
Jul. 3,1930 
Jul. 3,1930 
Aug. 26,1937 
Oct. 17, 1940 
Oct. 23,1962 
June 10,1872 
Aug. 30,1935 
Oct. 27,1965 
July 14, 1960 
Mar. 2, 1919 
Aug. 30,1975 
Maintenance of entrance channel under 1 head. 
Anchorage Channel, extension of Ambrose Channel 
into Upper Bay 
Removal of Craven Shoal 
PLATISBURGH HARBOR, N.Y. (See Section 20 of Text) 
Construction of 1,000 feet of breakwater 
Extension of 400 feet to breakwater, dredging between 
breakwater and wharves and beach revetment 
Extension of 300 feet to 1,250 feet of breakwater already 
built. 
Completion of improvement by dredging areas not heretofore 
dredged to 9 feet. 
RARITAN RIVER, NJ. (See Section 21 of Text) 
Channel 15 feet deep and 200 feet wide to Washington canal 
10 feet deep and 150 feet wide to canal locks and 
10 feet deep thru South Channel7 
Channel 25 feet deep and 300 feet wide up to New York and 
Long Branch Railroad bridge. 
Channel 10 feet deep in earth and 11 feet in rock to 
New Brunswick. Width reduced to 100 feet. 
Relocation of lower reach to South Channel. 
Channel 25 deep and 300 feet wide to junction of main and 
south channels, thence of same depth on South Channel to 
Titanium Pigment Co. 
Channel 25 feet deep and 300 feet wide from junction of main 
south channels to government wharf, including a turning 
basin. 
In South Channel, maintenance of 15-foot channel to dock of 
Middlesex County Sewerage Authority. 
RONDOUT HARBOR, N.Y. (See Section 22 of Text) 
Parallel dikes, branch dike, and entrance channel, 
14 feet deep. 
Extension of 14-foot channel and for 12-foot channel., 
Extend 12-foot channel from mile 1.8 to 3.5. 
SHINNECOCK INLET, NJ. (See Section 23 of Text) 
Channel 10 feet deep and 200 feet wide in Inlet, and 
6 feet deep and 100 feet wide in the Bay, and 
2 jetties. 
SHREWSBURY RIVER, NJ. (See Section 24 of Text) 
Channel 6 feet in North Branch 
Channel 12 feet deep. 
H. Doc. 518, 63d Cong., 
2d sess. 
H. Doc. 557, 64th Cong., 
1st sess. 
H. Doc. 131, 23d Cong., 
1st sess. 
H. Doc. 89, 39th Cong., 2d 
sess., and Annual Report, 
1870, p.55. 
Annual Report 1889, p. 2458. 
H. Doc. 759, 61st Cong., 
2d sess.11 
H. Doc. 1341, 62d Cong., 
3d. sess. 
H. Doc. 127, 70th Cong., 
1st sess. 
H. Doc. 454, 70th Cong., 
2d sess. 
Rivers and Harbors Committee 
Doc. 31, 71st Cong., 
2d sess. 
Rivers and Harbors Committee 
Doc. 74, 74th Cong., 
2d sess. 
Report on file in the Office. 
Chief of Engineers 
(report not printed) 
H. Doc. 455, 86th Cong., 
2d sess. 
S. Ex. Doc. 35, 42d 
Cong., 2d sess. Annual 
Report 1872, p. 8 10 
Rivers and Harbors Committee 
Doc. 17, 73d Cong., 2d sess. 
H. Doc. 288, 89th Cong., 
1st sess. (contains latest 
published map.) 
H. Doc. 126, 86th Cong. 
1st sess. 
FY 83 Supplemental 
Appropriations Act 
H. Doc. 1296, 62d. Cong., 
3d sess. 
H. Doc. 157, 71st Cong., 
2d sess. 
2-30

NEW YORK, N.Y. DISTRICT 
TABLE 2-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30,1935 
May 17,1950 
Sept. 22,1922 
1965 Flood Control Act 
1974 Water Resources 
Development Act 
July 3,1958 
Section 201 
Flood Control Act 
of 1965 
1976 Water Resources 
Development Act 
1976 Water Resources 
Development Act 
Section 101(a) 
1965 Flood Control Act 
Channel 9 feet deep. 
Turning basin and anchorage 6 feet at Red Bank and 
Channels 6 feet deep in Claypit, Oceanport, and Little 
Silver Creeks. 
WESTCHESTER CREEK, N.Y. (See Section 25 of Text) 
Channel 12 feet deep and two turning basins. 
EAST ROCKAWAY INLET TO ROCKAWAY INLET 
AND JAMAICA BAY, N.Y. (PART 1). 
(See Section 30 of Text) 
Hurricane barrier, dikes, levees, floodwalls, fill, placement, 
stoplog structures, stairways, ramps, road raising, fishing 
platforms, annual nourishment. 
Authorized beach erosion control aspect to be constructed 
independent of the hurricane flood protection aspect of 
the project. 
SEA BRIGHT TO OCEAN TOWNSHIP, N.J. 
(See Section 31 of Text) 
Restoration of beach to minimum width of 100 feet at 
height of 10 feet above mlw, and construction of 23 
new groins and extension of 14 existing groins. 
ARDSLEY, N.Y. (See Section 34 of Text) 
Channel improvement, concrete flume, flood walls, levees, 
various drainage structures. 
LIBERTY STATE PARK LEVEE AND SEAWALL, NJ. 
(See Section 35 of Text) 
Approximately 7,000 feet of seawall and elevated pedestrian 
walkway. 
PASSAIC RIVER BASIN, NJ. & N.Y., PHASE I 
(See Section 36 of Text) 
Advanced engineering and design study, involving 
reformulation of plans for flood control and water 
resource management. 
SAW MILL RIVER AT ELMSFORD AND 
GREENBURGH, N.Y. (See Section 37 of Text) 
Levees, floodwalls, channel improvement. 
Rivers and Harbors Committee 
Doc. 31, 74th Cong. 
H. Doc. 285, 81st Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 8, 67th Cong., 
2d sess. 
H. Doc. 215, 89th Cong., 
1st sess. 
H. Doc. 332, 85th Cong., 
2d sess., modified by Appr. 
Act for Energy and Water Dev. 
for FY 85. 
H. Doc. 215/89/1. 
H. Rpt. 94-1702 
H. Doc. 94-465, 94th Cong., 
2d sess. 
2-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 2-C HUDSON RIVER, N.Y. 
FEATURES OF LOCK AND DAM INCLUDED IN EXISTING PROJECT 
(See Section 9 of Text) 
Location: 
Below Waterford 
Above Battery, New York City 
Locks: 
Clear Width 
Greatest length available for full width 
Lift at lowest stages 
Depth on miter sills: 
Upper (at normal pool level) 
Lower (at lowest low water) 
2.2 miles 
152.6 miles 
44.4 feet 
492.5 feet 
17.3 feet 
16.3 feet 
13.0 feet 
Character of foundation: Rock 
Kind of dam: Fixed Crest 
Type of construction: Concrete 
Completed: 1917 
Cost: $1,463,014 
TABLE 2-D TOTAL COSTS FOR EXISTING PROJECT TO 
SEPTEMBER 30, 1986 
See 
Section Operation 
of Text Project Funds New York Rehabilitation Maintenance and Cost Total 
6. Hudson River, Regular $38,560,839 - $1,100,517 $697,386 $44,177,215 
N.Y. Public Works 238,350 - - - 238,350 
Emergency Relief 311,461 - - - 311,461 
TOTAL $39,110,650 - $1,100,517 $697,386 $44,727,026 
16. N.Y. and N.J. Regular $57,412,152 - $1,397,899 - $69,299,856 
Channels Public Works 807,000 - - - 870,000 
Emergency Relief 2,023,308 - - - 2,023,308 
Contributed 7,712 - - - 7,712 
TOTAL $60,250,172 - $1.397,899 - $72,137,876 
TABLE 2-E SUPERVISOR OF NEW YORK HARBOR 
(See Section 26 of Text) 
STATEMENT OF ACTIVITIES-FY 1986 
1. Number of Patrols 
a. Shore 200 
b. Vessel 250 
Air (helicopter) 3 
Total 453 
2. Number of Inspections 
a. Shore Facilities 3,750 
b. Vessels 900 
Total 4,650 
3. Disposition of Cases 
a. Voluntary Restoration 20 
b. After-the-fact Permit Applications Accepted 36 
c. Permit not required or already under permit 53 
d. Submitted for litigation to OCE or US Attorney 2 
e. Cases pending as of October 1,1982 130 
Total 241 
2-32

NEW YORK, N.Y. DISTRICT 
TABLE 2-F RECONNAISSANCE AND CONDITION SURVEYS 
FY 1986 
NAME OF PROJECT DATE SURVEY CONDUCTED 
NEW JERSEY 
Cheesequake Creek....................................................................................... Aug. 1986 
Newark Bay Hackensack & Passaic Rivers.....................................................Feb. 1986 
Raritan River...............................................................................................Jul. 1986 
Raritan River to Arthur Kill Cut-off...............................................................Jul. 1986 
Sandy Hook Bay at Leanardo .......................................................................... Aug. 1986 
Shark River.................................................................................................Feb. 1986 
Shoal Harbor & Compton Creek......................................................................Aug. 1986 
Shrewsbury River..........................................................................................Apr. 1986 
NEW YORK 
Bay Ridge & Red Hook Channels....................................................................May, Jun, Dec., 1985 
Browns Creek...............................................................................................Jun 1986 
Buttermilk Channel.......................................................................................* 
Coney Island Channel................................................................................... Jul. 1986 
Coney Island Creek.......................................................................................Sep.1986 
Eastchester Creek...........................................................................................* 
Flushing Bay & Creek....................................................................................M ar. 1986 
Hudson River................................................................................................Jan, May, 1986 
Hudson River Channel...................................................................................Jan, Apr, 1986 
Jamaica Bay................................................................................................May 1986 
Jones Inlet.................................................................................................... Jun, Jul 1986 
Lake Montauk Harbor.....................................................................................* 
Long Island Intracoastal W aterway ................................................................ * 
Mattituck Harbor........................................................................................... May 1986 
Narrows of Lake Champlain...........................................................................* 
Newark Bay Hackensack & Passaic Rivers...................................................Feb, Jun, 1986 
Newtown Creek.............................................................................................* 
New York Harbor...........................................................................................Oct, 1985-Feb, Mar, Apr, 
May, Jun 1986 
New York & New Jersey Channels.................................................................. 
*Items for which no date is furnished reflects costs for gathering data only. 
Total cost of Reconnaissance and Condition Surveys in Fiscal Year 1986 was $998,917. 
2-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 2-G OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sept, 30,1986 
For Last 
Full Report 
See Annual Operation and 
Projects ReportFor Construction Maintenance 
Burlington Harbor Vt 1 
Channel between North and South Hero Island, 
Lake Champlain, Vt.1,2 
Coney Island Inlet, N.Y. 
East Chester Creek, N.Y. 
East River, N.Y. 
Echo Bay Harbor, N.Y.1 
Flushing Bay and Creek, N.Y. 
Gordons Landing, Lake Champlain, Vt.1 ,2 
Gowanus Creek Channel, N.Y. 
Great Chazy River, N.Y. 
Great Kills Harbor, N.Y. 1,2 
Great Lakes to Hudson River Waterway, N.Y. 
Great South Bay, N.Y.' 
Greenport Harbor, N.Y.' 
Harlem River, N.Y.1 
Hempstead Harbor, N.Y. 
Hudson River Channel, N.Y. 
Jamaica Bay, N.Y. 
Keyport Harbor, N.J. 
Lake Montauk Harbor, N.Y. 
Larchmont Harbor, N.Y. 
Lemon Creek, N.Y. (Inactive)2,3 
Little Neck Bay, N.Y.1 
Mamaroneck harbor, N.Y. 
Manhasset Bay, N.Y. (Inactive)3 
Matawan Creek, N.J. 
Mattituck Harbor, N.Y. 
Milton Harbor, N.Y. 
New Rochelle Harbor, N.Y 1 ,2 
Northport Harbor, N.Y 1 
Orowoc Creek, N.Y.(Inactive) 3 
Otter Creek, Vt. 
Peconic River, N.Y.1 
Peekskill Harbor, N.Y.1 
Port Chester Harbor, N.Y. 
Port Henry Harbor, N.Yi' 
Port Jefferson Harbor 
Raritan River to Authur Kill Cutoff Channel, N.J. 
Rouses Point, Lake Champlain, N.Y.1 
Sag Harbor, N.Y.' 
St. Albans Harbor, Lake Champlain, Vt'1,2 
Sandy Hook Bay, N.J. 
Sandy Hook Bay at Leonardo, N.J.1 ,2 
Saugerties Harbor, N.Y 1 ,2 
Shark River, N.J. 
Sheepshead Bay, N.Y. 
Shoal Harbor & Compton Creek, N.J. 
Shooters Island, N.Y. & N.J. 
Staten Island Rapid Transit Railway Co. 
bridge across Arthur Kill, N.Y. 
Sumpawanus (Babylon Creek) Inlet, N.Y. 1,2 
1966 
1909 
1973 
1985 
1985 
1953 
1984 
1892 
1972 
1980 
1962 
1976 
1974 
1953 
1969 
1969 
1980 
1985 
1985 
1984 
1970 
1937 
1969 
1981 
1948 
1984 
1981 
1984 
1971 
1956 
1949 
1977 
1953 
1951 
1985 
1931 
1977 
1972 
1895 
1964 
1917 
1'985 
1967 
1968 
1984 
1948 
1984 
1983 
1973 
1895 
2-34 
706,414 9 
31,000 
111,371 
592,056 
32,723,700 12 
64,584 
2,102,905 7 
34,750 
346,831 
18,000 
137,301 15 
266,857 
74,681 
3,616,119 
39,468 
6,771,870 27 
4,545,753 
40,475 
791,68011 
76,065 
6,621 
1,741,21019 
513,764 
21,000 
177,925 32 
151,37318 
73,2148 
78,644 23 
60,254 
25,000 
19,400 
433,470 
69,406 25 
221,128 3 
810,500 
98,468 
121,805 26 
3,125 
508,936 
56,470 
81,905 
488,048 29 
33,828 
124,57220 
100,000 
7,730,476 
7,000 
283,556 
1,288 
284,109 
1,471,810 
4,448,80012 
11,571 
4,352,089 
115 
255,291 
292,919 
88,029 
457 
1,290,469 
21,720 
480,777 
76,497 16 
24,970,637 
2,604,547 
848,130 
849,709 
267,768 
1,621 
537 
551,677 
4,636 
237,097 
935,786 
986,520 
142,411 
1,487 
4,951 
27,059 
116,509 
66,037 
1,060,100 
1,299 
359,294 
2,019,141 
249 
11,710 
385 
3,902,330 
93,964 
169,18128 
1,129,100 29 
5,364 
1,104,940 21 
1133

NEW YORK, N.Y. DISTRICT 
TABLE 2-G (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sept 30,1986 
For Last 
Full Report 
See Annual Operation and 
Projects ReportFor Construction Maintenance 
Tarrytown Harbor, N.Y. 1 1974 69,836 431,199 
Wallabout Channel, N.Y. 1 1953 18,174 36,312 
Wappinger Creek, N.Y.1 ,2 1950 13,000 44,691 
Washington Canal and South River, N.J.1 1953 206,116 212,827 30 
Waycake Creek, N.J.2 ,3 1949 - 2,781 
Woodbridge Creek, N.JJ1 1953 48,823 178,398 
1. Completed. 
2. No commerce reported. 
3. Awaiting local cooperation. 
5. A portion of this project is classified "inactive." 
6. Includes $69,036 for new work and $26,921 for 
maintenance for previous project. Excludes 
$10,000 for new work expended from contributed 
funds. 
7. Excludes $419,879 for new work expended from 
contributed funds and $580,425 contributed funds 
other and $8,752 expended by the Worlds Fair 
Corp. for riprap protection of rubble dike. 
8. Includes $43,175 for new work for previous 
projects. 
9. Includes cost of maintenance prior to July 1, 1886. 
Excludes $1,425,133 for rehabilitation. 
11. Excludes $82,738 expended for new work from 
Navy Dept. funds. 
12. Includes $6,187,690 for new work and $37,664 for 
maintenance for previous projects. 
13. Includes $4,813,400 for new work expended from 
emergency relief funds. 
14. Excludes $94,366 for rehabilitation. 
15. Excludes $104,805 for new work expended from 
contributed funds. 
16. Included $64,034 for maintenance of previous 
projects. 
17. Excludes $19,546 for new work expended from 
contributed funds and $31,454 to be contributed. 
18. Excludes $119,276 required contributed funds and 
$72,619 other contributed funds. 
19. Excluded $1,741,210 for new work expended from 
contributed funds. 
20. Includes $17,000 for new work for previous 
projects. 
21. Includes $169,700 for maintenance for previous 
projects. 
23. Excludes $15,000 for new work expended from 
contributed funds. 
24. Includes $16,369 for maintenance for previous 
projects. 
25. Excludes $1,000 for new work expended from 
contributed funds. 
26. Excludes $66,758 for rehabilitation. 
27. Includes $668,820 public works funds. 
28. Includes $15,000 for maintenance for previous 
projects. 
29. Includes $338,048 contributed funds. 
30. Includes $84,934 for maintenance for previous 
projects. 
31. Includes costs for new work $171,427 and 
maintenance $10,646 for previous projects. 
32. Excludes $34,580 for new work from contributed 
funds. 
2-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 2-H OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
Cost to Sept. 30,1986 
ForLast 
Full Report 
See Annual Operation and 
Projects Report For Construction Maintenance 
Atlantic Coast of N.J., Sandy Hook to Barnegat Inlets 1959 - - 
Fire Island Inlet to Jones Inlet, N.Y. 1981 18,044,667 217,899 
North Shore of Long Island, Suffolk County, N.Y. 1979 8,880,000 - 
Perth Amboy, N.J. 1966 - - 
TABLE 2-I OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Construction to Sept. 30, 1986 
Full Report 
See Annual Operation and 
Projects ReportFor Construction Maintenance 
Adams, Hossic River Basin, Mass1 1964 6,282,3072- 
Bennington, Vt. 1974 670,000 - 
Byram River at Pemberwick, Conn.1,3 1959 363,515- 
East BarreDam, Winooski River, Vt 1 1963 2,832,084- 
East Rockaway Inlet to Rockaway Inlet 
and Jamaica Bay, N.Y. (Part II) 1976 1,185,365- 
Elizabeth, N.J. 1985 54,091,740 - 
Fire Island to Montauk Point N.Y. 1984 12,441,8646 143,753 
Herkimer, N.Y. 1973 1,201,2759 - 
Hoosic Falls, Hoosic River Basin, N.Y.1 1956 1,064,626 - 
Lamoille River, Vt.: Hardwich Dams 4,5,6 1939 - - 
Missisquoi River at Richford, Vt. 1,3 1965 221,476 - 
North Adams, Hoosic River Basin, Mass. 1968 15,409,3257 - 
North Ellenville, N.Y. 1978 3,900,650 - 
Rahway, N.J. 1971 973,1428 - 
Rahway, South Branch, N.J. 1979 15,863,723 - 
Raritan Bay and Sandy Hook Bay, N.J. 1981 11,061,256 262 
Rosendale, N.Y. 1975 3,684,966 - 
Rutland, Otter Creek, Vt.4 1963 211,015 - 
Sandburg Creek, Spring Glen, N.Y. 1976 109,702 - 
South Amsterdam, Mohawk River, N.Y.1 1967 1,564,976 - 
South Ellenville, N.Y. 1984 289,702 - 
South Orange, N.J. 1981 6,857,484 - 
Staten Island, N.Y. 1983 644,998 - 
Wappinger Creek at Pleasant Valley, N.Y.1,3 1959 142,075 
Waterbury Reservoir, Winooski River Basin, Vt. 1976 886,769 8,200 
Winooski River, Vt.1 1940 5,897,427 - 
Wrightsville Dam, Winooski River Basin, Vt. 1970 1,549,929- 
Yonkers, N.Y. 1984 13,641,77110 
2-36

NEW YORK, N.Y. DISTRICT 
1. Completed. 6. Includes $3,788,341 contributed funds. 
2. Excludes costs of $913,360 under other contributed funds. 7. Excludes cost of $21,000 under other contributed funds. 
3. Authorized by Chief of Engineers pursuant to Sec. 205, 8. Excludes cost of $51,500 under otheer contributed funds. 
Public Law 858, 80th Cong., as amended. 9. Uncompleted portion has been deauthorized on August 
4. Inactive. 5,1977. 
5. Includes $213,507 emergency relief funds. 10. Includes $622,871 contributed funds. 
TABLE 2-J SURVEYS 
(See Section 43 of Text) 
Study Class Cost 
Navigation Studies 
Flood Control Studies 
Beach Erosion Studies 
Special Studies 1 
Total Surveys 
$400,606 
1,651,988
0 
2,829,269 
4,882,269 
1Includes review of Authorized Projects, Inspection of Dams, Coordination Studies with Other Agencies, Planning 
Assistance to States, International Water Studies Investigations, Review of FERC Licenses and Preconstruction 
Engineering and Design. 
TABLE 2-L COSTS FOR FLOOD PLAIN MANAGEMENT SERVICES 
(See Section 44 of Text) 
Studies and Services Cost 
Flood Plain Technical Services $87,966 
Flood Plain Management Unit 65,000 
Total 152,966 
TABLE 2-M DEAUTHORIZED PROJECTS 
(See Section 45 of Text) 
ForLast 
Full Report Date Federal Contributed Operation 
See Annual And Funds Funds and 
Projects ReportFor Authority Expended Construction Expended Maintenance 
Bronx River, N.Y.4 ,6 1981 Aug. 1982 1,149,946 1,159,94612 10,000 1,947,8536 
Brown's Creek, N.Y. 1980 Aug. 1977 33,976 33,976 8 - 505,369 
Cheesequake Creek, N.J.4,6 1963 Aug. 1982 40,000 40,000 - 30,675 
Coney Island Creek, N.Y. 4,6 1952 Aug. 1982 69,489 69,489 - 1,622 
East Rockaway (DEBS) Inlet, N.Y. 1963 Aug. 1977 3503,96913 100,000 829,421 - 
Elizabeth, N.J. 1948 Aug. 1977 60,481 60,481 - 59,391 
Glen Cove Harbor, N.Y. 1966 Aug. 1977 165,882 165,8824,11 - 2,455 
2-37

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 2-M (Continued) DEAUTHORIZED PROJECTS 
(See Section 45 of Text) 
ForLast 
Full Report Ite Federal Contributed Operation 
See Annual And Funds Funds and 
Projects ReportFor Authority Expended Construction Expended Maintenance 
Hudson River, NY to Albany 4 1 8 1982 Aug. 1982 -... 
Huntington Harbor, N.Y. 1953 Aug. 1977 49,035 68,5814,5,14 19,546 51,566 
Irvington Harbor, N.Y. 1947 Aug. 1977. - - - 
Lamoille River, Vt. 1939 Aug. 1977 49,837 49,837 - - 
Newark Bay, Hackensack 
and Passaic Rivers, N.J.16 1982 Aug. 1982- - - - 
New York and New Jersey 1982 Aug. 1982- - - - 
Channels4,17 
Portchester Harbor, N.Y. 2 ,3 1967 Aug.1977 433,470 433,4704 - 441,656 
Proctor, Otter Creek, Basin, Vt.6,7 1937 Aug. 1977 - - - 
Rahway River, '79 1948 Aug. 1982 - 37,000' - 307 
Raritan River, N.J.4,6 1981 Aug. 1982 1,551,470 1,617,47015 66,000 10,113,903 
Rome Mohawk River, N.Y.6 ,7 1959 Aug. 1982 7,000 7,000 - - 
Swanton Harbor, Vt. (Inactive) 1888 Aug. 1977 - 70,500' - 235 
Ticonderoga River, N.Y.1,6 1895 Nov. 1983 167,760 16,500 - 1,260 
Waterbury (1941 Act), Vt.7,6 1951 Nov. 1981 9,253 9,253 -- 
Waterford, N.Y. 6 ,7 1939 Aug. 1982- - - - 
Westchester Creek, N.Y. 1981 Aug. 1982 175,933 175,933 - 2,921,311 
1. No commerce reported. 10. Under Section 12 Public Law 93-251. 
2. Completed. 11. Includes $93,882 for Rehabilitation. 
3. A portion of this project is classified "inactive." 12. Includes $10,000 expended from contributed funds. 
4. Uncomplete portion deauthorized. 13. Includes $100,000 expended from contributed funds. 
5. Excludes $19,546 for new work expended from 14. Includes $19,546 expended from contributed funds. 
contributed funds and $31,454 to be contributed. 15. Includes $66,000 expended from contributed funds. 
6. Inactive. 16. 1912 authorization. 
7. Entire project deauthorized. 17. 1935 authorization. 
8. Excludes $71,423 for rehabilitation. 18. 1910 construction dikes. 
9. Deferred. 
TABLE 2-N SECTION 107 
(See Section 29 of Text) 
Name of Project Cost to Sept.30,1986 
COMPLETE RECONNANISSANCE REPORT 
LaPlatte River, Shelburne Bay, Vt. 
COMPLETE PLANS & SPECIFICATIONS 
Sheepshead Bay, N.Y. $3
$7,500 
30,253 
2-38

NEW YORK, N.Y. DISTRICT 
TABLE 2-0 SECTION 103 
(See Section 33 of Text) 
Name of Project Cost to Sept, 30,1986 
COMPLETE DETAILED PROJECT STUDY 
Orchard Beach, Bronx, N.Y. $1,864 
TABLE 2-P SECTION 205 
(See Section 41 of Text) 
Name of Project Cost to Sept. 30,1986 
COMPLETE RECONNAISSANCE REPORT 
Bashbish Brook, Copake, N.Y. $7,500 
CONTINUE DETAILED PROJECT STUDIES 
E. Canada Creek, Dolgeville, N.Y. $40,775 
Elizabeth River, Hillside, N.J. 53,454 
Missisquoi River, Vt. 37,122 
Ramapo River,. Monroe, N.Y. 465 
Sauquoit Creek, Whitesboro, N.Y. 9,819 
Yonkers, Nepera Park, N.Y. 15,138 
COMPLETE DETAILED PROJECT STUDIES 
Esopus Creek, Ulster, N.Y. $8,639 
Lake Champlain, Plattsburgh, N.Y. 10,600 
Sawkill Creek, Kingston, N.Y. 3,652 
COMPLETE PLANS AND SPECIFICATIONS 
Passaic River (Field Emergency $6,098 
Preparedness System), N.J. 
COMPLETE CONSTRUCTION 
Wallkill River (Black Dirt Area), N.Y. 0 
2-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 2-Q SECTION 14 
(See Section 42 of Text) 
Name of Project Cost to Sept.30,1986 
COMPLETE RECONNAISSANCE REPORT 
Dune Road, Southampton, N.Y. 
COMPLETE PLANS AND SPECIFICATIONS 
Green Brook, Green Brook, N.J. $8,916 
COMPLETE CONSTRUCTION 
Sandburg Creek, Ellenville, N.Y. $2,486 
2-40

PHILADELPHIA, PA DISTRICT* 
This district comprises a portion of southeastern New 
York, eastern Pennsylvania, western and southern New 
Jersey, northern and southeastern Delaware, and a small 
Part of northeastern Maryland embraced in the drainage 
basins tributary to the Atlantic Ocean from Manasquan 
River, NJ inclusive, to south boundary of Delaware. It 
also includes Chesapeake and Delaware Canal and 
approach channel thereto in Chesapeake Bay and Elk 
River, MD. 
IMPROVEMENTS 
Navigation Page 
1. Barnegat Inlet, NJ...................... 3-2 
2. Cohansey River, NJ ..................... 3-2 
3. Cold Spring Inlet, NJ.................... 3-2 
4. Delaware River between 
Philadelphia, PA, and Trenton, NJ ......... 3-3 
5. Delaware River, PA, NJ and DE 
Philadelphia to the Sea .................. 3-4 
6. Indian River Inlet and Bay, DE............ 3-4 
7. Inland Waterway, Rehoboth Bay to 
Delaware Bay, DE ...................... 3-5 
8. Inland Waterway from Delaware River 
to Chesapeake Bay, DE, and MD........... 3-6 
9. Manasquan River, NJ ................... 3-7 
10. Mispillion River, DE..................... 3-7 
11. Murderkill River, DE .................... 3-7 
12. Navigation Work Under Special 
Authorization .......................... 3-8 
13. New Jersey Intracoastal Waterway ......... 3-8 
14. Schuylkill River, PA ..................... 3-9 
15. Tuckerton Creek, NJ .................... 3-9 
16. Wilmington Harbor, DE ................. 3-10 
Beach Erosion Control 
17. Shoreline Erosion Control ........... 
18. Beach Erosion Control Work 
Under Special Authorization ......... 
Page 
.... 3-10 
.... 3-10 
Flood Control Local Protection cont. Page 
24. Francis E. Walter Dam, PA .............. 3-12 
25. General Edgar Jadwin Dam and 
Reservoir, PA ......................... 3-13 
26. Inspection of Completed Flood 
Control Projects ....................... 3-13 
27. Inspection of Non-Federal Levees ......... .3-13 
28. Prompton Lake, PA .................... 3-13 
29. Reconnaissance and Conditions 
Surveys ............................. 3-14 
30. National Emergency Preparedness ........ 3-14 
General Investigations 
31. Surveys .......................... 
32. Collection and Study of Basic Data ...... 
Tables 
TABLE 3-A 
TABLE 3-B 
TABLE 3-C 
TABLE 3-D 
TABLE 3-E 
TABLE 3-F 
TABLE 3-G 
Cost and Financial Statement ..... 
Authorizing Legislation .......... 
Other Authorized 
Navigation Projects............ 
Other Authorized Beach 
Erosion Control Projects ......... 
Other Authorized Flood 
Control Projects ............... 
Multiple Purpose Project 
Including Power ................ 
Deauthorized Projects ........... 
Page 
.. 3-14 
.. 3-14 
Page V 
3-15 
3-18 
3-21 
3-23 
3-23 
3-24 
3-24 
Flood Control Local Protection Page 
19. Beltzville Lake, PA..................... 3-11 
20. Blue Marsh Lake, PA................... 3-11 
21. Delaware Coast Protection, DE ........... .3-11 
22. Flood Control Work Under 
Special Authorization ................... 3-12 
23. Emergency Bank Protection ............. .3-12 
*All costs and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and also appear at the 
end of this chapter. 
3-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. BARNEGAT INLET, NJ 
Location: On the east coast of New Jersey about 
50 miles south of Sandy Hook, between Island Beach 
on the north and Long Beach on the south (See U.S. 
Coast and Geodetic Chart Nos. 825 and 1216). This 
inlet is main entrance to Barnegat Bay, largest of the 
bays on New Jersey coast which are separated from the 
ocean by narrow barrier beaches. 
Existing project: Provides for a channel 8 feet 
deep through inlet and 10 feet through outer bar, 
channel to be protected by two converging stone jetties 
extending to 12-foot contour in the ocean and spaced 
1,000 feet apart at outer ends; a channel of suitable 
hydraulic characteristics extending in a northwesterly 
direction from gorge in inlet to Oyster Creek Channel 
just northwest of Sunset Shoal, thence via Oyster Creek 
Channel to deep water in the Bay; and maintenance of 
a channel 8 feet deep and 200 feet wide to connect 
Barnegat City harbor with main inlet channel. Total 
length of section included in project is about 4.5 miles. 
Plane of reference is mean low water. Extreme tidal 
range at inlet is from about 2 feet below mean low water 
to about 3 feet above mean high water. Project was 
completed in 1940. (For details, see page 203, Annual 
Report for 1964.) (See Table 3-B at end of chapter for 
Acts authorizing existing projects.) 
Recommended modifications: The existing 
Federal project at the inlet, which was completed in 
1940, has failed to maintain a suitable and safe channel 
for navigation. As a result of the finding of AE&D 
studies on this matter, the Chief of Engineers decided 
on 20 January 1983 that modification to the project 
should be implemented to correct a design deficiency. 
The recommended modification would serve to correct 
the design deficiency through the construction of a new 
south jetty aligned more nearly parallel to the existing 
north jetty, the dredging and maintenance of a new 
realigned navigation channel, and the removal of a 
shoal located between the proposed navigation channel 
and the north jetty. 
Local cooperation: Fully complied with. 
Terminal facilities: There are four docks or 
terminals in inner harbor at Barnegat Light which 
furnish adequate facilities for present commerce of 
locality. 
Operations during fiscal year: Maintenance, 
hired labor: Maintenance dredging by U.S. Government 
Side Casting Dredge FRY was performed from 05 May 
1986 to 04 July 1986. Removed an estimated 24,000 
cubic yards of material at a cost of $237,800; dredging 
by Currituck was performed from 01 July 1986 to 07 
August 1986 removing 63,964 cubic yards of material at 
a cost of $147,600. Work also included general 
maintenance, engineering surveys on dredging, and 
supervision and administration. 
2. COHANSEY RIVER, NJ 
Location: Rises in Salem County, NJ, flows 
southerly and southwesterly 27 miles through 
Cumberland County, and empties into Delaware Bay 
about 62 miles below Philadelphia, Pa. (See Coast and 
Geodetic Survey Chart 1218). 
Previous projects: For details see page 1785, 
Annual Report for 1915, and page 348, Annual Report 
for 1938. 
Existing project: A channel 12 feet deep, 100 feet 
wide from that depth in Delaware Bay through a neck 
of land at the mouth and within the river to the south 
side of Glass Street in Bridgeton, 19 miles above the 
mouth; thence a channel 8 feet deep, 100 feet wide to 
Broad Street; and thence 75 feet wide to Commerce 
Street Bridge, 19.25 miles above the mouth; and a 
turning basin 12 feet deep and 800 feet long formed by 
widening the channel on the south side to a maximum 
width of 250 feet just below Glass Street. Section 
included in project is about 19.5 miles long. All depths 
refer to the plane of mean low water. Extreme tidal 
range is from about 2 feet below mean low water to 
about 3 feet above mean high water. Completed project 
cost $110,756 for new work, exclusive of amounts 
expended on previous projects. (See Table 3-B at end of 
chapter for Acts authorizing existing project.) Existing 
project was completed in 1939. 
Local cooperation: Complied with except local 
interests must furnish suitable spoil-disposal areas for 
required maintenance. 
Terminal facilities: Twenty wharves, of which 
16 are at Bridgeton and 4 at Greenwich. Facilities 
considered adequate for existing commerce. 
Operations during fiscal year: Maintenance, 
contract: Work included Cultural Resource Investigation, 
maintenance dredging at the mouth of the 
Cohansey River from 02 June 1986 to 30 September 
1986 removing 350,000 cubic yards of material at a cost 
of $1,127,510. 
Maintenance, hired labor: Work included BCR update, 
environmental assessment and monitoring, plans and 
specifications on maintenance dredging, engineering 
surveys on dredging, and supervision and administration. 
3. COLD SPRING INLET, NJ 
Location: In Cape May County, southern New 
3-2

PHILADELPHIA, PA. DISTRICT 
Jersey, about 3 miles east of Cape May City and about 
16 miles northeast of Delaware breakwater. Inlet 
connects Cape May Harbor and New Jersey Intracoastal 
Waterway with the Atlantic Ocean and is about 
1 mile long. (See Coast and Geodetic Survey Charts 
234, 827 and 1219). 
Existing project: This provides for an entrance 
channel 25 feet deep and 400 feet wide, protected by two 
parallel jetties, and extending from the 25-foot depth 
curve in the Atlantic Ocean to a line 500 feet harborward 
of a line joining the inner ends of the jetties, thence 20 
feet deep and 300 feet wide to deep water in Cape May 
Harbor. The total length of the section included in the 
project is about 2.25 miles. Extreme tidal range, due to 
ocean storms, is about 11 feet. Project was completed in 
1942. (For details see page 238, Annual Report for 1962. 
See table at end of chapter for Acts authorizing existing 
project.) 
Local cooperation: Complied with Act of 1907, 
except work of deepening and enlarging inner harbor, 
which is 80 percent complete. 
Terminal facilities: See page 238 Annual Report 
for 1962. 
Operations during fiscal year: Maintenance, 
dredging by Currituck from 16 June 1986 to 30 June 
1986 and 08 August 1986 to 14 August 1986 removing 
3,502 cubic yards of material at a total cost of $82,000. 
Work also included general maintenance and plans 
and specifications. 
4. DELAWARE RIVER BETWEEN 
PHILADELPHIA, PA, AND 
TRENTON, NJ 
Location: Rises in southeastern New York, flows 
generally southerly 367 miles, forming boundary line 
between New York and New Jersey on the east and 
Pennsylvania and Delaware on the west, and empties 
into Delaware Bay. (See U.S. Coast and Geodetic Survey 
Charts 1218, 280, 294, 295, and 296.) 
Previous projects: For details see page 1778 of 
Annual Report for 1915, page 311 of Annual Report for 
1924, page 220 of Annual Report for 1934, and page 296, 
Annual Report for 1938. 
Existing project: A channel from Allegheny 
Avenue, Philadelphia, 23.5 miles to upstream end of 
Newbold Island 40 feet deep and 400 feet wide, with 
suitable widening of bends, including relocation of 
channel at Delair Railroad bridge, and reconstruction 
of bridge, thence 5.5 miles to upper end of Trenton 
Marine Terminal, 35 feet deep and 300 feet wide, with a 
turning basin 800 feet wide and 1,700 feet long at the 
terminal; and maintenance of a channel 12 feet deep 
and 300 feet wide from upper end of 34-foot channel to 
Penn Central Railroad Bridge at Trenton, dredged 
under a previous project. Project also provides for an 
auxiliary channel 20 feet deep and 200 feet wide east of 
Burlington Island, extending easterly from main 
channel to upper end of U.S. Pipe and Foundry Co.'s 
property at East Burlington, with a turning basin 450 
feet wide at upper end; for initial excavation, only, of a 
cross channel 8 feet deep and 200 feet wide through 
artificial island opposite Delanco, NJ, and for 
construction of such bank protection works as may be 
necessary. Section included in project is about 30.5 mile 
long, excluding auxiliary channel east of Burlington 
Island, which is 1.4 miles long, and cross channel 
opposite Delanco. Lower end is about 55 miles above 
river mouth at Liston Point and about 105 miles above 
Harbor of Refuge at mouth of Delaware Bay. Freshets, 
which occur usually during February and March, attain 
a height of 9 to 20 feet above mean low water in vicinity 
of Trenton. Navigation is occasionally suspended 
during a portion of winter months due to ice. Existing 
project is 90 percent complete. A 40-foot channel under 
the 1954 modification from Allegheny Avenue to upper 
end of Newbold Island was completed April 1964. Work 
remaining is dredging from upper end of Newbold 
Island to Trenton Marine Terminal and widening 
turning basin at terminal which is in deferred category. 
(See Table 3-B at end of chapter for Acts authorizing 
existing project. See Table 3-C at end of chapter for 
total cost for existing project to Sept. 30, 1984.) 
Local cooperation: Modification authorized by 
1954 River and Harbor Act provides local interests 
must provide suitable terminal facilities, furnish lands 
and rights-of-way for construction and future 
maintenance, and hold the United States free from 
damages. Local interest complied with requirements, 
except city of Trenton has not provided suitable terminal 
facilities. 
Terminal facilities: There are 21 piers, wharves, 
and docks from Allegheny Avenue, Philadelphia, PA 
to Trenton, NJ Facilities are considered adequate for 
existing commerce. (For details see Port Series No. 8 
(revised 1966) Corps of Engineers). 
Operations during fiscal year: Maintenance, 
contract: Work included operation of stream gages in 
USGS cooperative stream gaging program and 
maintenance dredging. 
Maintenance, hired labor: Work included maintenance 
dredging from 01 October 1985 to 18 January 
1986 removing a total of 645,322 cubic yards of material 
at a cost of $2,413,504. Other work included maintenance 
on surveys, supervision and administration on 
maintenance dredging, and general engineering and 
design. 
3-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
5. DELAWARE RIVER, PA, NJ 
AND DE, PHILADELPHIA 
TO THE SEA 
Location: See U.S. Coast and Geodetic Survey 
Charts 1218, 394, 295, and 280. 
Previous projects: For details see page 1779 of 
Annual Report for 1915, and page 299, Annual Report 
for 1938. 
Existing project: Provides for a channel from deep 
water in Delaware Bay to a point in the bay, near Ship 
John Light, 40 feet deep and 1,000 feet wide; thence to 
Philadelphia Naval Base, 40 feet deep and 800 feet 
wide, with 1,200-foot width at Bulkhead Bar and 1,000- 
foot width at other bends; thence to Allegheny Avenue, 
Philadelphia, PA, 40 feet deep and 500 feet wide through 
Horseshoe Bend and 40 feet deep and 400 feet wide 
through Philadelphia Harbor, along west side of 
channel; and for anchorages at Reedy Point, Deepwater 
Point, Marcus Hook, and Mantua Creek, each 40 feet 
deep and 2,300 feet wide with respective length of 8,000, 
5,200, 12,650, and 11,500 feet; anchorage at Gloucester 
30 feet deep and about 3,500 feet long. Project also 
provides for construction of dikes and training works 
for regulation and control of tidal flow; for maintenance 
of an area on north side of channel opposite Philadelphia 
Naval Base between Shipway 3 and Schuylkill 
River to 40 feet deep and width of 150 feet on Mifflin 
Range and 200 feet on West Horseshoe Range; and for 
maintenance of any areas dredged by local interests to 
35 feet deep between channel and a line 100 feet 
channelward of pierhead line between Point House 
wharf and Philadelphia Naval Base, when in opinion 
of Chief of Engineers such areas are so located as to be 
of benefit to generate navigation. Section included in 
project is about 96.5 miles long. All depths refer to 
plane of mean low water. Under influence of heavy and 
long-continued winds extreme tidal range is about 14 
feet. Normal maximum velocity of tidal currents in the 
dredged channel varies between 2 and 3.5 miles per 
hour. Storm tides may increase maximum to as much 
as 4.5 miles per hour. Estimated cost for new work is 
$71,630,000 (July 1972) exclusive of amounts expended 
on previous projects. Channel to 37 deep and 500 feet 
wide through Horseshoe Bend and 37 feet deep and 60 
feet wide through Philadelphia Harbor along east side 
of channel and Port Richmond anchorage to 37 feet 
deep, except for that portion of channel which forms a 
part of 40 feet deep and 400 feet wide channel portion is 
to be restudied and excluded from foregoing cost 
estimate. Estimated cost (July 1960) of this portion of 
project is $2,951,000. Existing project, excluding work 
deferred for restudy, is about 66 percent complete. The 
40-foot channel from Naval Base to the sea was 
completed in 1942. Dredging Naval Base to Allegheny 
Avenue to 40 feet deep was completed in 1962. Enlarging 
anchorage at Marcus Hook was completed in 1967. 
Work remaining is to construct new anchorages at 
Reedy Point and Deepwater Point, and enlarge Mantua 
Creek anchorage, channel dredging from 35 to 37 feet 
deep over a width of 500 feet through Horseshoe Bend 
and about 600 feet through Philadelphia Harbor, and 
deepening Port Richmond Anchorage to 37 feet, all of 
which have been deferred for restudy. (See Table 3-B at 
end of chapter for Acts authorizing existing project. 
See Table 3-C at end of chapter for total costs for existing 
project to Sept. 30, 1984.) 
Local cooperation: Requirements under 1938 
River and Harbor Act for maintaining channel and 
anchorage in Philadelphia Harbor annually by cities 
of Philadelphia and Camden were removed (see 1962 
Annual Report for details). 
Terminal facilities: There are 217 piers, wharves, 
and docks between Allegheny Avenue, Philadelphia 
and the sea, 135 on waterfront of Philadelphia, Camden, 
and Gloucester, and 82 below Philadelphia. Facilities 
are considered adequate for existing commerce. (For 
further details see Port Series Nos. 7, revised 1967, and 
8, revised 1966-Corps of Engineers.) 
Operations during fiscal year: Maintenance, 
contract: Maintenance dredging of Mifflin Range, 
Mantua Creek Anchorage, and New Castle Range 
performed by Norfolk Dredging Company during period 
1 October 1985 through 31 December 1986. Removed a 
total of 2,025,000 cubic yards of material at a total cost 
of $7,085,500. Maintenance dredging of Cherry Island, 
Marcus Hook Anchorage and New Castle Range was 
performed by Norfolk Dredging Company during period 
of 28 May 1986 through 30 September 1986. Removed a 
total of 2,700,000 cubic yards of material at a total cost 
of $3,535,730. Other work included sturgeon studies, 
lease and maintenance of equipment for disposal areas, 
construction of dikes and sluices at disposal areas, 
general maintenance, disposal area groundwater 
testing, subsurface exploration, replaced sluice pipes, 
and operation of stream gages by USGS. 
Maintenance, hired labor: Dredging performed by 
U.S. Hopper Dredge McFarland during the period 20 
August 1986 through 30 September 1986. Removed 
785,208 cubic yards of material at a cost of $1,590,000. 
Other work included engineering survey, miscellaneous 
environmental research coordination, maintenance of 
disposal area equipment, general maintenance, 
sturgeon studies, snagging and clearing, debris 
removal, ditching at disposal areas, environmental 
assessment, subsurface explorations, handling shore 
pipe, engineering and design, supervision and administration, 
and plans and specifications on surveys and 
dredging. 
6. INDIAN RIVER INLET 
AND BAY, DE 
Location: Indian River rises in Sussex County, 
DE, and flows easterly 13 miles into Indian River Bay 
3-4

PHILADELPHIA, PA. DISTRICT 
which is a shallow lagoon 6 miles long and 2 miles wide 
on the Delaware Coast about midway between Cape 
Henlopen and the Maryland State line. The inlet is an 
opening through the barrier beach separating Indian 
River Bay and the Atlantic Ocean (See U.S. Coast and 
Geodetic Survey Chart No. 1219.) 
Previous projects: Adopted by River and Harbor 
Act of August 2, 1882. For further details see page 744, 
Annual Report for 1888. 
Existing project: This provides for the fixation of 
the inlet by the construction of two parallel jetties of 
steel-sheet pile and stone design extending to approximately 
the 14-foot depth curve in the ocean, and for 
dredging an entrance channel 15 feet deep and 200 feet 
wide, for a distance of 7,000 feet inshore from the jetties; 
thence a channel 9 feet deep, 100 feet wide in the bay, 
and 80 feet wide in the river, to and including a turning 
basin 9 feet deep, 175 feet wide, and 300 feet long at Old 
Landing; thence a channel 4 feet deep and 60 feet wide 
to the highway bridge at Millsboro. The project also 
provides that the interior channel dimensions may, at 
the discretion of the Chief of Engineers, be modified as 
found desirable to increase the hydraulic efficiency of 
the channel, without increasing the cost. The total 
length of the section included in the project is about 
13.75 miles. All depths refer to the plane of mean low 
water. The extreme tidal range at the highway bridge is 
about 6 feet. Existing project was completed in 1951. 
For details see Annual Report for 1963. 
The cost for new work for the completed project was 
$511,210, exclusive of $10,000 expended on previous 
projects and exclusive of $210,000 contributed funds. 
(See Table 3-B at end of chapter for Acts authorizing 
existing project.) 
Local Cooperation: Fully complied with except 
that local interest are required to furnish suitable areas 
for disposal of dredged material during maintenance 
as and when needed, and provide terminal facilities. 
Terminal facilities: There is a privately owned 
basin with berthing facilities for small boats located 
.75 miles west of the highway bridge near the inlet and 
.25 miles north of the inlet channel, connected therewith 
by a channel 6 feet deep and 40 feet wide; a U.S. Coast 
Guard wharf on the north side of the inlet channel in 
the same locality; and two wharves at Oak Orchard in 
Indian River Bay. The facilities are considered adequate 
for existing commerce. 
Operations during fiscal year: Maintenance, 
hired labor: Work included preparing BCR update and 
project monitoring. 
7. INLAND WATERWAY, 
REHOBOTH BAY TO 
DELAWARE BAY, DE 
Location: A tidal canal in southeasterly part of 
Sussex County, DE It extends 12 miles northward from 
Rehoboth Bay through high land west of town of 
Rehoboth to Gordon Lake; thence through marshes 
back of Cape Henlopen to Lewes River; thence down 
Lewes River to its junction with Broadkill River near 
its mouth. An entrance to the waterway from Delaware 
Bay is about 4 miles above Cape Henlopen. (See U.S. 
Coast and Geodetic Survey Charts 379, 1218, and 1219.) 
Previous projects: A canal along a slightly 
different route formed a part of projected waterway 
from Chincoteague Bay, VA to Delaware Bay, begun in 
1886 and abandoned in 1905. 
Existing project: This provides for an entrance 
channel near Lewes 10 feet deep and 200 feet wide 
protected by two parallel jetties 500 feet apart; thence a 
channel 10 feet deep and 100 feet wide to South Street 
Bridge at Lewes, and a basin of the same depth 1,200 
feet long and up to 375 feet in width at the latter point; 
thence a channel 6 feet deep and 50 feet wide (40 feet 
wide through Deep Cut near Rehoboth Bay) to Rehoboth 
Bay; a channel 6 feet deep and 100 feet wide from the 
entrance to Broadkill River; two parallel rubble jetties 
725 feet long at the Rehoboth Bay entrance; and the 
construction of one highway bridge and on railroad 
Bridge at Rehoboth. The total length of the section 
included in the project is about 12 miles. 
The cost for new work for the completed portion of 
the project was $561,514 exclusive of amounts expended 
on previous projects and $60,000 contributed funds. 
The extension of the jetties at the Delaware Bay 
entrance is considered to be inactive and is excluded 
from the foregoing cost. The cost of the portion was last 
revised in 1960 and was estimated to be $816,000. 
Existing project is about 70 percent complete. For details 
on completed work see page 241 of Annual Report for 
1963. Work remaining, extension of existing jetties at 
Delaware Bay entrance, is considered inactive. (See 
Table 3-B at end of chapter for Acts authorizing existing 
project.) 
Local cooperation: Complied with except local 
interest must furnish suitable terminal facilities and 
necessary spoil-disposal areas. 
Terminal facilities: See page 228, Annual Report 
1962. 
Operations during fiscal year: Maintenance, 
hired labor: Work included engineering and design, 
and supervision and administration. 
3-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
8. INLAND WATERWAY FROM 
DELAWARE RIVER TO 
CHESAPEAKE BAY, DE 
AND MD 
Location: Begins at Reedy Point on Delaware 
River, about 41 miles below Philadelphia, PA, and 
passes through sea level Chesapeake and Delaware 
Canal, a distance of 14 miles, to Back Creek, at 
Chesapeake City, MD. It then passes for 5 miles down 
Back Creek, thence 9 miles down Elk River to Chesapeake 
Bay and thence 18 miles down Chesapeake Bay 
to a point near Pooles Island. A branch channel 
connects Delaware River at Delaware City, DE, with 
main channel at a point about 1.5 miles west of Reedy 
Point. (See U.S. Coast and Geodetic Survey Charts 294, 
1226, 570, and 572.) 
Previous projects: For details see Annual Report 
for 1934, page 242, and Annual Report for 1938, page 
312. 
Existing project: A channel 35 feet deep and 450 
feet wide from Delaware River through Elk River and 
Chesapeake Bay to water of natural 35-foot depth in 
Chesapeake Bay including a cutoff at Penn Central 
Railroad crossing, and having a maximum radius of 
curvature of 7,000 feet at bends; a high-level, fixed 
railroad bridge with vertical clearance of 135 feet and 
horizontal clearance of 600 feet at the railroad crossing 
over the cutoff (economic study of railroad crossing 
requested by Office of Management and Budget resulted 
in construction of a single track vertical lift bridge in 
lieu of a high-level fixed railroad bridge); high-level 
fixed highway bridges over canal at Reedy Point, St. 
Georges, Summit, and Chesapeake City; a bascule 
drawbridge across Delaware City Branch Channel; 
extension of entrance jetties at Reedy Point; and 
anchorage in Elk River, 35 feet deep and 1,200 feet 
wide, with an average length of 3,700 feet; enlargement 
of anchorage and mooring basin in Back Creek to afford 
an area about 400 feet wide, 1000 feet long, and 12 feet 
deep; dredging Delaware City Branch Channel to 8 feet 
deep and 50 feet wide, and deepening existing basin to 
same depth; revetment of banks of canal as required 
between Delaware and Elk Rivers, and on banks of 
Delaware City Branch Channel east of Fifth Street 
Bridge; and construction of bulkheads. Total of section 
included in project, excluding Delaware City Branch 
Channel, which is about 2 miles long, is about 46 miles. 
All depths refer to plane of low water in Delaware 
River. Extreme tidal range is from 6.3 feet above mean 
high water to 3 feet below mean low water. Existing 
project is about 89 percent completed. Channel 27 feet 
deep and 250 to 400 feet wide. Delaware River to Pooles 
Island, completed in 1938. High-level fixed highway 
bridges were completed at St. Georges (4-lane) in 1942; 
at Chesapeake City (2-lane) in 1949; and at Summit 
(4-lane) in 1960. Relocation of Penn Central Railroad 
bridge was completed December 21, 1965. Enlargement 
to 35 feet deep and 450 feet wide St. Georges and Summit 
bridges and Summit and Goose Island was completed 
on June 20, 1972 and February 18, 1972, respectively. 
Removing the old Penn Central railroad bridge was 
completed on January 21, 1972. Channel work for Part 
II is about 87 percent complete. Work remaining consists 
of completing channel enlargement to 35 feet deep and 
450 feet wide between Reedy Point Bridge and St. 
Georges Bridge; widening and deepening the channel 
between Delaware River and Reedy Point Bridge, the 
completion of recreation facilities, and miscellaneous 
completion items. Deepening Delaware City Branch 
Channel from 6 to 8 feet from a point 400 feet east of 
Fifth Street Bridge to its junction with the canal has 
been deferred for study. 
Original cost of canal including purchase was 
$10,709,755; estimated cost of new work for modifications 
of 1935 and 1954 is $139,574,000 (October 1977). 
Total estimated cost of new work including original 
purchase is $151,683,755. Portion of project comprising 
completion of Delaware City Branch Channel from a 
point 400 feet east of Fifth Street Bridge to its junction 
with canal is to be restudied and excluded from 
foregoing estimate. Estimated cost of this portion is 
$145,000 (July 1954). (See Table 3-B at end of chapter 
for Acts authorizing existing project.) 
Local cooperation: River and Harbor Act of 1954 
provided that local interests furnish lands and rightsof-
way required for bridges. Assurances accepted and 
approved February 16,1955. Requirements for Summit 
and Reedy Point Bridges have been met. 
Terminal facilities: Ample mooring facilities at 
eastern and western ends of canal and bulkheads at 
Delaware City and St. Georges were constructed by the 
United States. A small-boat harbor was provided and a 
wharf constructed at Chesapeake City. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year: Maintenance, 
contract: Maintenance dredging performed by Norfolk 
Dredging Company in the Upper Chesapeake Bay 
during the period 9 September 1986 through 30 
September 1986, removing a total of 100,000 cubic yards 
of material at a cost of $360,000. Other work included 
maintenance of Chesapeake City, Summit, St. Georges 
and Reedy Point bridges. 
Maintenance, hired labor: General maintenance of 
disposal areas; maintenance of rip-rap, roadways, night 
lighting, buildings and grounds, banks, auxiliary works 
and traffic controlled TV, environmental drainage of 
disposal areas, disposal area construction, lease 
equipment, Reedy Pt. bridge overlay, fish and wildlife 
study, bridge inspection, trash removal, subsurface 
investigation and testing of disposal areas, and 
supervision and administration. 
3-6

PHILADELPHIA, PA. DISTRICT 
9. MANASQUAN RIVER, NJ 
Location: This small stream flows in eastern part 
of New Jersey, rises near Freehold, flows easterly and 
empties into the Atlantic Ocean, about 26 miles south 
of Sandy Hook. (See U.S. Coast and Geodetic Survey 
Chart No. 795.) 
Previous projects: For details see Annual report 
for 1909, page 186, and Annual Report for 1938, page 
269. 
Existing project: A channel 14 feet deep and 250 
feet wide, protected by jetties and other works, extending 
from the Atlantic Ocean to inner end of north jetty, 
thence 12 feet deep and 300 feet wide to within 700 feet 
of New York and Long Branch Railroad bridge, thence 
of same depth and narrowing to 100 feet wide to within 
300 feet of bridge; for a widening on northerly side of 
channel of 200 feet for 3,150 feet to a depth of 8 feet; for a 
19-acre anchorage to 10 feet deep on south side of 
channel and for a 27.5-acre anchorage to 12 feet deep 
about 0.5 miles west of Route 35 highway bridge. Section 
included in project is about 1.5 miles long. Mean tidal 
range is 3.7 feet at inner end of inlet and 4 feet at ocean 
end; mean range of spring tides, 4.4 and 4.8 feet, 
respectively, irregular fluctuations due to wind and 
barometric pressure vary from 2.7 feet below to 7.5 feet 
above mean low water at inner end of inlet. Project, 
excluding 10-and 12-foot anchorages, cost $518,243. 
Estimated cost (1958) for 10 and 12-foot anchorages 
portion of project considered inactive is $504,000. 
Restoration of bulkheads completed 16 August 1965 at 
a cost of $117,807. Existing project was completed in 
June 1963. Dredging 19-acre anchorage south of channel 
and 27.5-acre anchorage west of highway bridge is in 
the inactive category. (See Table 3-B at end of chapter 
for Acts authorizing existing project.) 
Local cooperation: River and Harbor Act of 1945 
provides that local interests must furnish lands and 
rights-of-way for construction and future maintenance 
and hold the United States free from damages. 
Assurances to date have been complied with. 
Terminal facilities: Five landings with a total 
wharfage of 700 feet used by commercial fishermen, 
and 7 landings and boat basins for pleasure craft. 
Existing facilities are considered adequate for present 
requirements. 
Operations during fiscal year: Maintenance, 
contract: Work included CERC and air monitoring, 
repairs to north Bulkhead, and monitoring jetty. 
Maintenance, hired labor: Work included BCR 
update, engineering and design, and supervision and 
administration. 
10. MISPILLION RIVER, DE 
Location: Rises in Kent and Sussex Counties, DE, 
flows northeasterly 15 miles along the boundary line 
between the two counties and empties into Delaware 
Bay about 16 miles above Cape Henlopen. (See Coast 
and Geodetic Survey Chart 1218). 
Previous projects: For details see page 1786, 
Annual Report for 1915, page 448 of Annual Report for 
1918, and page 327 of Annual Report for 1938. 
Existing project: Project is about 31 percent 
complete. Four cutoffs for 6-foot channel were completed 
in 1923; 6-foot channel from Delaware Bay to Milford in 
1924; and jetties at the mouth in 1939. Work remaining 
is dredging channel to 9-foot depth, 80 feet wide in 
Delaware Bay to the mouth, thence 60 feet wide to 
Milford, with the provision of three cutoffs to eliminate 
bends, and a turning basin at Milford. Controlling 
depths at mean low water; in October 1964 from 
Delaware Bay to mouth 7.1 feet, and thence to fixed 
highway bridge at Milford, 6.1 feet. For details see page 
243 of Annual Report for 1957. 
Local cooperation: Assurances required by 1954 
River and Harbor Act have not been furnished. For 
details see page 243, Annual Report for 1957. Prior 
requirements fully complied with. 
Terminal facilities: For details see page 244, 
Annual Report for 1957. 
Operations during fiscal year: Maintenance, 
contract: Work included rip-rap bank stabilization, plan 
and specifications on maintenance dredging. 
11. MURDERKILL RIVER, DE 
Location: Rises in Kent County, DE, flows 
northeasterly 19 miles through county, and empties 
into Delaware Bay about 25 miles above Cape Henlopen. 
(See U.S. Coast and Geodetic Survey Chart no. 1218.) 
Existing project: Provides for a channel 7 feet 
deep at mean low water, 150 feet wide in Delaware Bay 
to mouth, and thence 80 feet wide to Frederica, 7.5 miles 
above mouth. Total length of section included in project 
is about 8.5 miles. Extreme tidal range is from about 1 
foot below mean low water to about 2 feet above mean 
high water. 
Estimated cost for new work revised in 1954 is $38,000. 
Portion comprising widening channel to project width 
throughout its length is to be restudied and excluded 
from foregoing cost estimate. Estimated cost of this 
portion last revised in 1954 was $86,000. Project was 
authorized by River and Harbor Act of July 13, 1892 (H. 
Ex. Doc. 21,52d Cong., 1st Sess. See page 981 Annual 
3-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Report for 1892.) Latest published map is in House 
Document 1058,62d Congress 3d Session. 
Existing project about 30 percent complete, including 
revision to be restudied. Channel 7 feet deep and 60 feet 
wide was completed in 1911. Work remaining is 
widening the channel to project width. 
Local cooperation: None required. 
Terminal facilities: There are a number of light 
timber wharves on both sides of river near mouth and 
two wharves at Frederica, all privately owned. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year: Maintenance, 
contract: Maintenance dredging was done at the 
entrance to the canal by Garden State Dredging 
Company from 20 August 1986 to 30 September 1986 
removing 9,500 cubic yards of material at a cost of 
$19,000 
Maintenance, hired labor: Maintenance dredging, 
plans and specifications and supervision and 
administration. 
12. NAVIGATION WORK 
UNDER SPECIAL 
AUTHORIZATION 
Navigation Activities Pursuant To Section 107, Public 
Law 86-645 (Preauthorization) 
Name of Project Cost to 30 Sept. 1986 
Detail Project Reports 
Schuylkill River-Fairmount Park, Pa. $17,638 
Plans and Specifications 
Wilmington Harbor, DE $19,463 
13. NEW JERSEY 
INTRACOASTAL 
WATERWAY 
Location: A sea level inland water route approximately 
parallel with New Jersey coast, extends from 
Atlantic Ocean at Manasquan Inlet, about 26 miles 
south of Sandy Hook, NJ to Delaware Bay about 3 
miles above Cape May Point. Waterway extends 
through inlet and up Manasquan River about 2 miles; 
thence by Point Pleasant Canal through high ground 
for 2 miles to head of Barnegat Bay. It then passes 
through a series of bays, lagoons, and thoroughfares 
along New Jersey coast to Cape May Harbor; thence 
across Cape May County to Delaware Bay through a 
land cut by way of New England Creek basin. (See U.S. 
Coast and Geodetic Survey Charts, 234, 795, 825, 826, 
827, 1216, 1217, 1218, and 1219.) 
Existing project: This provides for a channel 12 
feet deep at mean low water and generally 100 feet 
wide, extending from the Atlantic Ocean at Manasquan 
Inlet, NJ to Delaware Bay above Cape May, NJ, by the 
further improvement of Manasquan River and Inlet, 
NJ, and the present New Jersey Intracoastal Waterway, 
and by the construction of a canal of similar dimensions 
from Cape May Harbor to Delaware Bay via the New 
England Creek basin, with adequate jetties at the 
Delaware Bay entrance. The total length of the project 
is about 117 miles. Normal tide range in sections of the 
waterway remote from inlets is 0.5 foot. 
Estimated cost for new work is $71,549 (July 1969), 
exclusive of $1,824,940 Navy Department funds and 
$99,000 contributed by local interests. Portion of project 
extending from Manasquan River to Cape May Harbor 
is to be restudied and excluded from new work costs 
estimate. Estimated cost of this portion is $6,470,000 
(July 1954). Existing project was adopted by 1945 River 
and Harbor Act (H.Docl33,76th Cong., 1st Sess.) Latest 
published map is in project document. River and Harbor 
Act of 1946 (Public Law 525, 79th Cong., 2nd Sess., as 
extended by Public Law 240,82d Cong.), authorized use 
for a period not to exceed 6 years, of funds from 
appropriations heretofore or hereafter made for 
maintenance and improvement of rivers and harbors, 
for maintenance of canal from Cape May Harbor to 
Delaware Bay constructed as an emergency wartime 
project with Navy Department funds, including cost of 
maintaining temporary railroad and seashore highway 
bridges over canal. 
Existing project is about 25 percent complete. A canal 
12 feet deep and 100 feet wide from Cape May Harbor to 
Delaware Bay was completed in 1942 as well as two 
parallel stone jetties at Delaware Bay entrances and a 
temporary highway and a railroad bridge in 1944, all 
with Navy Department funds. Work remaining consists 
of dredging a channel 12 feet deep and 100 feet wide 
from Atlantic Ocean at Manasquan Inlet to Cape May 
Harbor, has been deferred for restudy; however, the 
project between Ottens Harbor and Richardson 
Channel and from that point to Cape May are being 
maintained to 10 feet and 12 feet, respectively, since 
they were originally dredged to these depths by the 
State. 
Local cooperation: The project is subject to the 
conditions that the State of New Jersey cede to the 
United States all right, title, and interest that it has 
acquired to lands, easements, rights-of-way, and 
structures other than bridges for the Bayhead- 
Manasquan Canal; that the State of New Jersey furnish, 
free of cost to the United States, all lands, easements, 
rights-of-way, and disposal areas required for construction 
of the Cape May Canal and for improvement of the 
proposed waterway and for their subsequent 
maintenance; that local interests provide, maintain, 
and operate suitable bridges over the waterway; that 
the State of New Jersey donate to the United States the 
3-8

PHILADELPHIA, PA. DISTRICT 
navigation aids in use on the present New Jersey 
Intracoastal Waterway; and that the State of New 
Jersey hold and save the United States and its agents 
free from any claims for damages resulting from the 
work of improvement. Compliance with these conditions 
was completed January 15, 1954, except that local 
interests are required to furnish disposal areas for the 
construction and the subsequent maintenance of the 
proposed improvement. 
Terminal facilities: See Annual Report for 1962. 
Operations during fiscal year: Maintenance, 
contract: Dredging performed by Spickard Enterprises 
on the Cape May Canal, Great Sound and Shad Islands 
from 10 April 1986 through 30 September 1986 removed 
400,000 cubic yards of material at a cost of $935,300. 
Other work included general maintenance, Pt. Pleasant 
Canal Bulkhead design, erosion report on West End 
Cape May Canal, and maintenance dredging. 
Maintenance, hired labor: Work included general 
maintenance, BCR update, plans and specifications, 
erosion construction, lease plant dredging, engineering 
and design, and supervision and administration. 
14. SCHUYLKILL RIVER, PA 
Location: Rises in Schuylkill County, PA, flows 
generally southeasterly 150 miles, and empties into 
Delaware River at Philadelphia, PA. (See U.S. Coast 
and Geodetic Survey Charts 295 and 280.) 
Previous project: For details see page 325, Annual 
Report for 1932. 
Existing project: This provides for a channel 33 
feet deep and 400 feet wide in Delaware River to the 
mouth and within the river to 29th Street, .75 mile 
above the mouth; thence the same depth and 300 feet 
wide to Passyunk Avenue Bridge, 3.5 miles above the 
mouth; thence 26 feet deep and 300 feet wide to Gibson 
Point, 4.5 miles above the mouth; and thence 22 feet 
deep and 200 feet wide to University Avenue Bridge, 6 
miles above the mouth, including widening at bends. 
The total length of the section included in the project is 
about 6.5 miles. All depths refer to the plane of mean 
low water. The extreme tidal range, due to freshets and 
prolonged heavy winds, is about 14 feet. 
The cost for new work for the completed existing 
project was $2,809,007. Existing project was completed 
in September 1962. For details see Annual Report for 
1962. (See Table 3-B at end of chapter for acts 
authorizing existing project.) 
Local cooperation: The River and Harbor Act of 
July 24, 1946, imposed the condition that the City of 
Philadelphia agree to remove 60,000 cubic yards, place 
measurement, of material annually from that portion 
of those portions of the project which the District 
Engineer may designate until such time as adequate 
municipal sewage-treatment works are constructed and 
placed in effective operation. Compliance with this 
condition has been met through the completion of 
sewage-treatment works by the City of Philadelphia. 
All other requirements have been fully complied with. 
Terminal facilities: There are 38 wharves, piers, 
and docks within limits of improvement. Facilities are 
considered adequate for existing commerce. (For further 
details see Port Series No. 7, Revised 1967, Corps of 
Engineers.) 
Operations during fiscal year: Maintenance, 
contract: Work included plans and specifications, and 
supervision and administration on maintenance 
dredging. 
Maintenance, hired labor: Work included environmental 
monitoring, plans and specifications, dredging 
surveys, supervision and administration, and general 
maintenance. 
15. TUCKERTON CREEK, NJ 
Location: This creek rises in Ocean County, NJ 
flows southerly 7 miles, and empties into Little Egg 
Harbor about 8 miles north of Little Egg Inlet. (See U.S. 
Coast and Geodetic Survey Charts Nos. 825 and 1216.) 
Existing project: This provides for a channel 6 
feet deep, 80 feet wide from the head of Marchelder 
Channel in Little Tuckerton Bay to the mouth; thence 
75 feet wide to Parkers Landing, 1 mile above the mouth; 
thence 60 feet wide to West Tuckerton Landing, 1.75 
miles above the mouth; thence a channel 5 feet deep 
and 60 feet wide to just above Scow Landing, 2 miles 
above the mouth; and thence a channel 3 feet deep and 
40 feet wide to the mill dam at Tuckerton 2.25 miles 
above the mouth. The total length of the section included 
in the project is about 3.5 miles. All depths refer to the 
plane of mean low water. The mean tidal range is 2.5 
feet. The extreme tidal range is from about 1 foot below 
mean low water to about 1 foot above mean high water. 
The cost of new work for the complete project was 
$60,242. (See table at end of chapter for Acts authorizing 
existing project.) 
Local cooperation: None required. 
Terminal facilities: There are a number of 
wharves and piers ofpile-and-timber construction along 
the creek. There are also four boatyards with marine 
railways, and repair and storage facilities located at 
Tuckerton. One wharf at Tuckerton is publicly owned. 
The facilities are considered adequate for existing 
commerce. 
3-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Operations during fiscal year: Maintenance, 
hired labor: BCR update. 
16. WILMINGTON HARBOR, DE 
Location: Formed by Christina River, which rises 
in New Castle County, DE, flows northeasterly 16 miles, 
passing through the City of Wilmington, DE, and 
empties into Delaware River about 29 miles below 
Philadelphia, PA (See U.S. Coast and Geodetic Survey 
Chart 294.) 
Previous projects: For details see page 1785 of 
Annual Report for 1915 and page 308 of Annual Report 
for 1938. 
Existing project: This provides for a channel 35 
feet deep and 400 feet wide from west edge of Delaware 
River ship channel to Lobdell Canal, a distance of 
about 1.2 miles; thence 21 feet deep and 250 feet wide for 
the distance of .8 mile to the mouth of Brandywine 
River; thence the same depth and 200 feet wide for a 
distance of about 2.2 miles to a point approximately 4.2 
miles from the Delaware River ship channel; thence 
decreasing a depth of 10 feet in a distance of 750 feet to 
Penn Central Railroad bridge No. 4; and thence 7 feet 
and 100 feet wide for a distance of about 5.6 miles to 
Newport, DE, approximately 9.9 miles above Delaware 
River ship channel, including a turning basin 35 feet 
deep opposite the Wilmington Marine terminal and 
extending upstream from the mouth to Lobdell Canal, 
200 feet wide, 2,900 feet long on the north side of the 
channel and decreasing to a length of 2,000 feet on the 
north side of the basin. It also provides for the removal 
of about 1,200 feet of the outer end of a stone-filled, 
pile-and-timber crib jetty constructed 2,150 feet long on 
the north side of the entrance; for a steel sheet-pile jetty 
2,300 feet long, with 120-foot inshore wing, on the south 
side of the entrance, and for a V-shaped stone-filled 
pile-and-timber jetty at the mouth of Brandywine River 
430 feet along the north side of Brandywine and 260 
feet long on the Christina. Depths refer to the plane of 
mean low water. The extreme tidal range, due to 
prolonged heavy winds, is about 13 feet. Existing project 
was completed in 1962. (For details see page 222, Annual 
Report 1962. See Table 3-B at end of Chapter for Acts 
authorizing existing project.) 
Local cooperation: Fully complied with. 
Terminal facilities: There are 18 piers, wharves, 
and docks within limits of the improvement. Facilities 
considered adequate for existing commerce. (For further 
details see Port Series No. 8, revised 1966-Corps of 
Engineers.) 
Operations during fiscal year: Maintenance, 
contract: Maintenance dredging in the Christina River 
was performed by the American Dredging Co. during 
the period 20 December 1985 through 23 January 1986 
removing 509,000 cubic yards of material at a cost of 
$499,017; during the period 06 June 1986 through 24 
September 1986 removing 283,832 cubic yards of 
material at a cost of $474,600. Other work included 
design of Wilmington Harbor South, Water Quality 
Study, subsurface explorations, design and field testing 
of the American Shad monitoring program, and 
preliminary development of the evaluation factors to 
be used for the procurement of the artificial reefs. 
Maintenance, hired labor: Work included general 
maintenance, plans and specifications, inspections of 
subsurface explorations, design and analysis of 
embankment construction, inpervious borrow investigations, 
monitoring of construction operations, design 
of dikes, instrumentation monitoring, and engineering 
and design. 
Beach Erosion Control: 
17. SHORELINE EROSION 
CONTROL 
DEMONSTRATION 
Location: Demonstration projects were undertaken 
at a total of 16 sites nationwide, 6 of which are located 
in the Delaware Bay and include Pickering Beach, Kitts 
Hummock, Slaughter Bowers Beach, Broadkill Beach, 
and Lewes, Delaware. The latter three sites were only 
monitored as there are presently Federal and State 
projects in progress. 
Existing project: Section 54 of Water Resources 
Development Act of 1974 authorized a nationwide, 5 
year program to test and evaluate low cost shoreline 
erosion control measure, both structural and vegetative, 
which can be implemented by individual private 
property owners. The emphasis of the program was not 
to solve individual problems, so much as to explore the 
effectiveness of various ways to control erosion at 
different types of shorelines, and provide this 
information to private and public landowners. The 
construction and evaluation at all sites are completed 
and information dissemination has been started. 
Operations during fiscal year: Maintenance, 
hired labor: Only costs incurred were in support of 
information dissemination program. Cost during this 
period was $1,101.48. 
18. BEACH EROSION CONTROL 
WORK UNDER SPECIAL 
AUTHORIZATION 
Beach erosion control activities pursuant to Section 
103, Public Law 87-874 (Preauthorization). 
Name of project Cost to 30 Sep 1986 
Detailed Project Reports 
North Shore-Indian River Inlet 
South Shore-Indian River Inlet 
$55,764.00 
50,699.00 
3-10

PHILADELPHIA, PA. DISTRICT 
Flood Control 
19. BELTZVILLE LAKE, PA 
Location: Damsite is on Pohopoco Creek about 4.5 
miles upstream from its confluence with Lehigh River 
and 4 miles east of Lehighton, PA. (See Geological 
Survey Quadrangle Map for Lehighton, PA-1960.) 
Existing project: A multiple-purpose development 
project providing water supply, flood control, and 
recreation. Plan of improvement provides for an earth 
and rock fill dam 4,200 feet long rising 170 feet above 
creekbed; a spillway around north end of dam; and gate 
control outlet works discharging through a conduit on 
rock along right abutment. The lake, a unit of comprehensive 
plan for flood control and other purposes of 
Delaware River Basin, has a reservoir capacity of 68,250 
acre-feet at spillway crest level with 1,390 acre-feet of 
inactive storage, 39,830 acre-feet for water supply and 
recreation, and 27,030 acre-feet for flood control. The 
cost of project was $22,931,400 including $6,100,000 
required non-Federal reimbursement for costs allocated 
to water supply storage during life of project. The 
construction of the dam and appurtenances was 
completed in 1971. 
Local cooperation: Project was approved subject 
to certain requirements of cooperation by local interests 
as defined in approved House Document. Resolution of 
Delaware River Basin Commission providing assurances 
of repayment of water supply and pollution 
control costs was accepted June 7, 1965. A contract for 
repayment of water supply costs was signed October 
16, 1966. 
Operations during fiscal year: Maintenance, 
contract: Work included reservoir operation and 
maintenance, operation of stream gages in cooperative 
stream gaging program, correcting electric problems, 
water quality data collection and monitoring, and 
repairing outlet Channel side slope. 
Maintenance, hired labor: Work included reservoir 
operation and minor maintenance, annual safety 
inspection, water quality monitoring, instrumentation 
survey, operation of stream gages in cooperative stream 
gaging program, sedimentation survey, inundation 
mapping, dam safety training, tower leakage 
monitoring, engineering and design, and supervision 
and administration. 
20. BLUE MARSH LAKE, PA 
Location: Dam site is on Tulpehocken Creek about 
1.5 miles upstream from its confluence with Plum Creek 
and about 6 miles northwest of Reading, PA (See 
Geological Survey Quadrangle Sheet, Bernville, PA) 
Existing project: This is a multiple-purpose development 
project providing water supply, flood control, 
and recreation. Construction started in 1974 and was 
completed in 1980. The dam is 1,775 feet long and rises 
98 feet above creekbed, with at spillway about 1,500 feet 
south of dam, and gate-controlled outlet works 
discharging through a conduit on rock along right 
abutment. The lake, a unit of comprehensive plan for 
flood control and other purposes of Delaware River 
Basin, has a capacity of 50,010 acre-feet at spillway 
crest level, with 3,000 acre-feet of inactive storage, 14,620 
acre-feet for water supply and recreation, and 32,390 
acre-feet for flood control. (For details see H.Doc 533 
87th Cong., 2nd Sess.) Cost of project (October 1984), 
$63,163,791 includes $16,132,000 required non-Federal 
reimbursement for costs allocated to water supply 
storage during life of project after use of this storage is 
initiated. Existing project was authorized by 1962 Flood 
Control Act (H. Doc. 533, 87th Cong., 2d Sess., contains 
latest published maps.) 
Local cooperation: Project was approved subject 
to certain requirements by local interests, as prescribed 
in House Document cited above. Delaware River Basin 
Commission on December 29, 1964, adopted a preliminary 
resolution providing for repayment of water 
supply costs. 
Operations during fiscal year: Maintenance, 
contract: Work included reservoir operation and 
maintenance, recreation area well drilling, recreation 
area operation and maintenance, snow survey, stream 
gage operation in cooperative stream gaging program, 
water quality testing and monitoring, recreation area 
mowing and fertilizing janitorial services, trash 
removal, dam break analysis, sewage treatment plant 
maintenance, lawn maintenance, dam survey 
recreation safety program, sewage vacuum system, and 
costs incurred for Bern and Heidelberg Township police. 
Maintenance, hired labor: Work included reservoir 
operation and maintenance, annual safety inspection, 
water quality monitoring, instrumentation survey, 
snow survey, stream gage operation in cooperative 
stream gaging program, sedimentation survey, plans 
and specifications to correct shoreline erosion, dam 
break analysis, sewage vacuum system, seasonal 
employment, dam safety training, plans and 
specifications, engineering and design, and supervision 
and administration. 
21. DELAWARE COAST 
PROTECTION, DE 
Location: The project is located in Sussex County, 
Delaware, on the Atlantic Ocean and starts immediately 
south of Delaware Bay extending in a southerly 
direction a distance of 24.5 miles to Fenwick Island on 
the Delaware-Maryland border. 
Existing project: Provides a plan of improvement 
3-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
which consists of the construction of dunes and beach 
fill; the construction of bulkheads at Rehoboth and 
Dewey beaches; periodic nourishment of the beaches; 
placement of sand fences; planting dune grass; and 
maintenance and replacement of existing structures. 
(For details, see S. Doc. 90, 90th Cong. 2d Sess.) 
Estimated cost of project (October 1985) $14,300,000 
includes $2,700,000 required non-Federal costs. The 
construction of the feeder beach north of Indian River 
Inlet was completed in 1973 and nourished in 1978, and 
1984. Other work undertaken has been engineering 
and design associated with the rest of the project. 
Local cooperation: Assurances of local cooperation 
were provided by the State of Delaware, January 
13, 1981. 
Operations during fiscal year: Maintenance, 
contract: Work included construction of Feeder Beach, 
statistical analysis, survey of bypass plant site, and 
advance engineering and design. 
Maintenance, hired labor: Work included continuation 
of engineering and design. 
22. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 205, Public 
Law 838, 80th Congress, as amended (Preauthorization). 
Name of Project Cost to 30 Sept. 1986 
Reconnaissance Reports 
Pennypack, Hatboro, PA $2,949.00 
Plans and Specifications 
Delaware River, Port Jervis, NY $42,240.00 
Poquessing Creek, Bucks Co., PA $74,052.00 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Congress, and antecedent legislation). 
Fiscal year costs were $220,715 for disaster preparedness, 
and $12,419 for emergency operations. 
23. EMERGENCY BANK 
PROTECTION 
Emergency bank protection Section 14, Public Law 
79-526. 
Darby Creek - Lansdowne Borough, PA 
Revolving Funds $ 7,500.00 
Detail Project Study 41,500.00 
Initial Contract 10,000.00 
Perkiomen Creek- Berks County, PA 
Revolving Funds $ 7,500.00 
Detail Project Study 19,000.00 
Construction 40,900.00 
24. FRANCIS E. WALTER DAM, 
PA 
Location: Reservoir is in northeastern Pennsylvania 
on Lehigh River between White Haven and 
Stoddartsville. Dam is about 0.4 mile below mouth of 
Bear Creek, about 60 miles above confluence of Lehigh 
River and Delaware River at Easton, PA. (See 
Geological Survey Quadrangle Sheet, Stoddartsville, 
PA.) 
Existing project: Plan of improvement authorized 
by 1946 Flood Control Act (H. Doc 587, 79th Cong., 2d 
Sess.) provided for a single-purpose flood control 
reservoir. Modification of project, authorized by 1962 
Flood Control Act (H. Doc. 522, 87th Cong., 2d Sess.), 
provides for a multiple-purpose development for water 
supply and recreation in addition to present singlepurpose 
flood control project. Plan of improvement 
requires altering spillway, increasing height of dam, 
extending outlet tunnel by addition of a concrete 
conduit, and constructing new dikes and raising 
existing dikes. Modified dam will rise 263 feet above 
riverbed and be 3,500 feet long. Reservoir modification, 
a unit of comprehensive plan for flood control and 
other purposes of Delaware River Basin, will have a 
reservoir capacity of 180,000 acre-feet spillway crest 
level with 2,000 acre-feet of inactive storage, 70,000 
acre-feet for water supply and recreation and 108,000 
acre-feet for flood control. Estimated Federal cost of 
new work (October 1985) is $127,000,000 including 
$110,700,000 required non-Federal reimbursement for 
costs allocated to water supply storage during life of 
project after use of this storage is initiated. Project as 
authorized under the 1946 Flood Control Act was 
completed June 1961. Settlement for lands was 
completed October 1962. The advance engineering and 
design for the modified project is now underway. 
Local cooperation: None required under 1946 
Flood Control Act. Under 1962 Flood Control Act, 
project was approved subject to certain requirements 
by local interests, as defined in House Document 522 
cited above. The Delaware River Basin Commission 
reiterated its sponsorship for the modified project in 
August 1982. 
Operations during fiscal year: Maintenance, 
contract: Work included reservoir operation and minor 
maintenance, master planning data collection, 
monumentation survey, snow survey, stream gage 
operation in cooperative stream gaging program, 
stream gage repair, water quality testing, instrumentation 
survey and general equipment maintenance, 
and master plan data collection. 
Maintenance, hired labor: Work included initial filling 
plan, emergency planning, analysis mapping, reservoir 
data collection, reservoir operation and minor 
maintenance, instrumentation surveillance, minor 
3-12

PHILADELPHIA, PA. DISTRICT 
maintenance of recreation facilities, periodic 
inspections, stream gage operation in USGS cooperative 
stream gaging program, annual safety inspection, 
general engineering and design, and supervision and 
administration. 
25. GENERAL EDGAR JADWIN 
DAM AND RESERVOIR, PA 
Location: In Dyberry Creek valley in central part 
of Wayne County, PA, between borough of Honesdale 
and village of Tanners Falls. Dam is about 3 miles 
above confluence of Dyberry Creek and Lackawaxen 
River in Honesdale and 29 miles above confluence of 
Lackawaxen and Delaware Rivers. (See Geological 
Survey Quadrangle Sheet, Honesdale, PA) 
Existing project: A single-purpose flood control 
reservoir with a capacity of 24,500 acre-feet formed by 
an earth embankment, about 1,225 feet long at crest 
and rising 109 feet above creek bed. It also has a tunnel 
with intake structure and a chute-type spillway with a 
stilling basin in left abutment. Reservoir controls runoff 
from a drainage area of 65 square miles which is 91 
percent of watershed of Dyberry Creek and 39 percent 
of Lackawaxen River watershed above Honesdale, PA 
Construction of project was authorized by 1948 Flood 
Control Act (H. Doc. 113, 80th Cong., 1st Sess.). Federal 
cost of new work was $4,064,510. Non-Federal funds 
not required. Project completed in June 1960. 
Local cooperation: Assurances of Compliance 
with requirements of local cooperation were accepted 
July 30, 1956. For details see page 251, Annual Report 
for 1962. 
Operations during fiscal year: Maintenance, 
contract: Work included reservoir operation and 
maintenance, stream gage operation in USGS 
cooperative stream gaging program, and dam survey. 
Maintenance, hired labor: Work included inundation 
mapping, reservoir operation and minor maintenance, 
safety and engineering inspections, stream gage 
operation in cooperative stream gaging program, 
instrumentation and surveillance analysis, general 
engineering and design, trash boom construction, dam 
break analysis, dam surveys, and supervision and 
administration. 
26. INSPECTION OF 
COMPLETED FLOOD 
CONTROL PROJECTS 
To ascertain whether local interests were maintaining 
and operating completed projects as required, 
inspections were made as follows: 
PROJECT 
Lehigh River at Allentown, PA 
Lehigh River at Bethlehem, PA 
Delaware River at East Branch, NY 
Rancocas Creek at Mount Holly, NJ 
Chester River at Chester, PA 
Beach Erosion & 
Hurricane Protection 
INSPECTION 
DATES 
25 October 1985 
17 April 1986 
30 October 1985 
24 April 1986 
6 November 1985 
30 April 1986 
17 October 1985 
28 April 1986 
10 October 1985 
29 April 1986 
10 & 11 October 1985 
Local interests are satisfactorily maintaining and 
operating projects in accordance with regulation. Costs 
during the period were $11,145. Total costs were 
$104,882. 
27. INSPECTION OF 
NON-FEDERAL LEVEES 
Inspection of non-Federal levees were conducted at a 
cost of $1,838 at the following sites: 
Port Jervis, NY 23 December 1985 
28. PROMPTON LAKE, PA 
Location: In Lackawaxen River Valley in central 
part of Wayne County, PA, between borough of 
Prompton and village of Aldenville. Dam is within 
corporate limits of Prompton, 4 miles upstream from 
Honesdale, Pa., and approximately 30 miles above 
confluence of Lackawaxen and Delaware River. (See 
Geological Survey Quadrangle Sheet, Honesdale, Pa.) 
Existing project: Plan of improvement authorized 
by 1948 Flood Control Act (H. Doc. 113, 80th Cong., 1st 
Sess.) provides for a single-purpose flood control 
reservoir. Modification of project authorized by 1962 
Flood Control Act (H. Doc. 522, 87th Cong., 2d Sess.) 
provides for a multiple-purpose development for water 
supply and recreation in addition to present singlepurpose 
flood control project. Plan of improvement 
requires construction of control tower with gates and 
service bridge, placing an impervious blanket on valley 
walls and floor upstream from dam, widening spillway, 
and clearing land and relocating roads in reservoir. 
Dam, completed under 1948 Flood Control act which 
will not be modified, is 1,230 feet long and rises 140 feet 
above riverbed. Existing spillway, cut into rock of right 
abutment, will be modified and present uncontrolled 
outlet works discharging into a concrete conduit along 
right bank, will be provided with gates and a control 
tower. Reservoir modification, a unit of comprehensive 
plan for flood control and other purposes of Delaware 
River basin has a capacity of 52,000 acre-feet; 3,500 
acre-feet for inactive storage, 28,200 acre-feet for water 
supply and recreation, and 20,300 acre-feet for flood 
control. Estimated Federal cost of new work (October 
3-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
1985) is $43,300,000 including $38,100,000 required 
non-Federal reimbursement for costs allocated to water 
supply storage during life of project after use of this 
storage is initiated. Project as authorized under the 
1948 Flood Control Act was completed in November 
1960. (For details, see page 358, Annual Report for 
1963.) Work accomplished under the 1962 Flood Control 
Act was advance engineering and design. 
Local cooperation: Project modification was 
approved subject to certain requirements by local 
interests, as defined in House Document 522 cited above. 
Assurances of compliance under Flood Control Act of 
1948 have been met. Delaware River Basin Commission 
on March 18, 1966, gave their view that the need for 
water supply was not urgent at that time. However 
recent studies conducted by DRBC have determined 
that there is now a need for water supply. In August 
1983, DRBC expressed their strong support for the 
project modification. Therefore resumption of planning 
will take place when funds are made available. 
Operations during fiscal year: Maintenance, 
contract: Work included operation and minor 
maintenance, water quality monitoring, USGS 
cooperative stream gaging, survey analysis, dam 
survey, supervision and administration, and 
engineering and design. 
Maintenance, hired labor: Work included inundation 
mapping, dam break analysis, annual safety inspection, 
dam safety training, water quality data collection, 
instrumentation and surveillance, dam survey, repair 
of instrumentation and engineering and design. 
29. RECONNAISSANCE AND 
CONDITION SURVEYS 
Project 
Murderkill 
Mispillion 
Salem River 
Cohansey River 
Alloway Creek 
Date Survey Conducted 
8 January 1986 
14 January 1986 
20 February 1986 
8 July 1986 
September 1986 
30. NATIONAL EMERGENCY 
PREPAREDNESS 
The total fiscal year cost for this category amounted 
to $171,055. 
GENERAL INVESTIGATIONS 
31. SURVEYS 
Cost for the period were $858,560 for navigation 
studies: $208,873 for flood control studies: $679,087 for 
special studies: a total of $1,746,520. 
32. COLLECTION AND STUDY 
OF BASIC DATA 
Cost and expenditures during the period for flood 
plain information studies were $277,304. 
3-14

PHILADELPHIA, PA. DISTRICT 
TABLE 3-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
1. Barnegat Inlet, 
N.J. 
(Regular 
Funds) 
(Contributed 
Funds) 
2. Cohansey River, 
N.J. 
(Regular 
Funds) 
3. Cold Springs Inlet, 
N.J. 
(Regular 
Funds) 
(Contributed 
Funds) 
4. Delaware River 
Between Philadelphia, 
Pa. and 
Trenton, N.J. 
(Regular 
Funds) 
(Contributed 
Funds) 
5. Delaware River 
Pa., N.J. and 
Del., Philadelphia 
to the Sea 
(Regular 
Funds)* 
6. Indian River 
Inlet and Bay, 
Del. 
(Regular 
Funds) 
(Contributed 
Funds) 
7. Inland Waterway 
Rehoboth Bay 
to Delaware 
Bay, Del. 
(Regular 
Funds) 
(Contributed 
Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
703,000 
680,607 
30,000 
11,049 
396,000 
395,501 
967,000 
968,187 
210,000 
206,975 
670,000 
694,337 
-3,000 
15,951 
112,000 
112,554 
15,000 
3,022 
289,000 
286,860 
66,000 
65,367 
-1,000 
-1,385 
110,000 
61,094 
515,000 
509,472 
1,434,000 
1,424,916 
266,000 
264,703 
298,125 3,328,000 3,005,000 
298,476 3,321,857 3,009,484 
16,782,000 21,533,300 25,051,285 14,309,000 
16,775,510 21,639,776 25,051,285 14,287,846 
-16,000 
697 
114,000 
112,228 
4,000 
4,171 
30,000 
32,572 
22,000 
20,617 
19,000 
16,346 
64,000 
65,196 
208,000 
208,523 
3-15 
783,849 
719,940 
10,525,135 
10,517,325 
300,000 
300,000 
146,75620 
146,75620 
2,272,931 
2,263,214 
879,275 
879,275 
2,656,507 
2,654.824 
1,134,346 
1,134,346 
150,0008 
150,0008 
72,147,8001 
72,147,8001 
32,841,8602 
32,840,1982 
15,000 
15,000 
57,879,872; 
57,879,872; 
323,944,1524 
323,904,8014 
508,324 
508,324 
511,2105 
511,2105 
2,827,923 
2,827,736 
1,323,775 
1,323,775 
210,000 
210,000 
561,514 
561,514 
1,531,978 
1,529,847 
60,000 
60,000

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 3-A (continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
8. Inland Waterway 
from Delaware 
River to Chesapeake 
Bay, Del. 
and Md. 
(Regular Funds) 
9. Manasquan 
River, N.J. 
(Regular 
Funds) * 
(Contributed 
Funds) 
10. Mispillion 
River, Del. 
(Regular 
Funds) 
11. Murderkill 
River, Del. 
(Regular 
Funds) 
12. New Jersey 
Intracoastal 
Waterway 
(Regular 
Funds) 
(Contributed 
Funds) 
13. Schuylkill 
River, Pa. 
(Regular 
Funds) 
14. Tuckerton Creek, 
N.J. 
15. Wilmington 
Harbor, Del. 
(Regular 
Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- - 297 
12,045,500 10,488,275 12,068,000 
12,216,932 10,666,460 11,940,091 
15,000 
94,659 
177,314 
5,235 
25,000 
40,081 
1,028 
11,000 
11,000 
273,000 
264,024 
84,705 
7,500 
7,500 
111,000 
110,600 
159,000 
160,280 
11,129,053 
11,295,557 
23,000 
34,520 
995 
211,000 
210,107 
153,000 
149,713 
818,000 1,121,000 979,000 2,563,300 
849,876 1,152,487 981,788 2,560,370 
770,100 1,241,000 1,693,000 125,000 
768,856 1,244,884 1,641,466 125,433 
- - - 15,000 
- - - 14,943 
2,011,000 2,006,000 3,226,600 4,207,700 
1,980,620 2,069,777 3,215,739 4,217,572 
3-16 
132,535,5916 
132,532,5986 
159,564,7587 
159,519,3667 
577,24915 
577,24915 
3,417,55716 
3,419,45316 
7,410,60019 
7,429,55819 
300,000 
300,000 
385,34817 
385,34817 
1,581,56618* 
1,573,33618* 
253,491 
253,491 
37,630 
37,630 
1,268,355 
1,265,067 
71,5499 
71,5499 
22,145,87110 
22,142,71210 
1,196,581 
1,196,581 
99,000 
99,000 
3,334,00711 
3,334,00711 
26,067,033 
26,066,819 
60,242 
60,242 
638,917 
638,860 
1,954,72512 
1,954,72512 
35,005,465 
34,997,130

PHILADELPHIA, PA. DISTRICT 
TABLE 3-A (continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
(Contributed New Work 
Funds) Approp. - - - - 60,000 
Cost - - - - 60,000 
16. Beltzville Lake, New Work 
Pa. Approp. - - - - 22,931,831 
(Regular Cost - - - - 22,931,130 
Funds) Maint. 
Approp. 721,000 655,800 521,000 515,000 5,318,175 
Cost 691,749 713,170 521,407 496,875 5,298,264 
17. Blue Marsh New Work 
Lake, Pa. Approp. - - - - 63,180,300 
(Regular Cost 118,186 3,212 - - 63,163,790 
Funds) Maint. 
Approp. 787,000 1,002,200 1,186,000 1,053,000 6,562,200 
Cost 742,145 1,068,725 1,167,543 1,058,095 6,522,634 
18. Delaware Coast New Work 
Protection Approp. 50,000 775,000 200,000 550,000 3,003,95321 
(Regular Funds) Cost 43,580 455,165 120,542 148,701 2,196,89221 
Maint. 
Approp. - 88,000 - - 215,350 
Cost - 88,000 - - 215,350 
(Contributed New Work 
Funds) Approp. 85,000 -921 - - 1,033,473 
Cost 69,557 11,538 614,809 1,052 1,033,473 
19. Francis E. New Work 
Walter Dam, Pa. Approp. - - - - 11,503,432' 3 
(Regular Cost - - 1,460 - 11,503,432'3 
Funds) Maint. 
Approp. 331,000 383,700 422,000 460,000 4,993,521 
Cost 330,420 388,882 421,975 449,970 4,972,623 
20. General Edgar New Work 
Jadwin Dam and Approp. - - - - 4,073,105 
Resevoir, Pa. Cost - - - - 4,073,105 
(Regular Maint. 
Funds) Approp. 104,000 74,200 243,000 222,000 1,612,564 
Cost 91,463 88,156 242,742 210,796 1,601,032 
21. Prompton Lake New Work 
Pa, Approp. - - - - 4,609,483' 4 
(Regular Cost - - - - 4,609,48314 
Funds)* Maint. 
Approp. 167,000 298,000 353,000 287,000 2,700,162 
Cost 173,611 306,608 348,359 295,841 2,697,724 
* Total Adjusted to correct discrepancies in prior years. 
1. Includes $2,489,173 for new work for previous projects, $105,000 
for preauthorization studies and minus $142,015 adjustment (new 
work) to Delaware River, Philadelphia to Sea project from this 
project under 1954 modification. 
2. Included $552,720 for maintenance for previous projects, and 
$685,000 Jobs Bill Funds. 
3. Excludes $12,976,054 for new work for previous projects and 
$142,015 adjustment from Delaware River, Philadelphia to 
Trenton, NJ under 1954 modification. 
4. Includes $1,025,409 for maintenance of previous projects, and 
$8,000 Jobs Bill funds. 
5. Excludes $10,000 for previous project. 
6. Includes $10,709,755 for new work for previous projects. 
7. Includes $6,903,748 for maintenance for previous projects, and 
$9,500 Jobs Bill funds. 
8. Includes $50,000 Navy Department Funds. 
9. Excludes $1,824,940 Navy Department Funds. 
** For Construction, General funds only on legislative Phase I 
AE&D, or support work for Phase II AE&D. 
10. Excludes $286,953 Navy Department funds expended for 
maintenance. 
11. Includes $525,000 for previous projects. 
12. Includes $402,121 for new work for previous project, and $206,177 
emergency relief funds. 
13. Includes $40,000 appropriated and expended under Code 710 
Recreation Facilities. 
14. Includes $63,000 appropriated and $61,551 expended under Code 
710 Recreation Facilities, excludes $23,600 preauthorization 
studies under 1948 modification. 
15. Includes $39,000 for new work for previous projects. 
16. Includes $2,054 for maintenance for previous projects. 
17. Includes $148,798 for new work on previous projects. 
18. Includes $61,172 for maintenance on previous projects. 
19. Includes $555,600 for previous project. 
20. Includes $36,000 for new work for previous projects. 
21. Includes $438,953 AE&D. 
3-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 3-B AUTHORIZING LEGISLATION 
Acts 
Aug. 30, 1935 
Aug. 26, 1937 
July 24, 1946 
July 2, 1985 
Mar. 2, 1907 
Aug. 26, 1937 
Mar. 2, 1907 
Mar. 2, 1945 
July 3, 1930 
Aug. 30, 19352 
Aug. 30, 19352 
Aug. 26, 1937 
July 24, 1946 
Sept. 3, 1954 
June 25, 1910 
July 3, 1930 
Aug. 30, 1935 
June 20, 19384 
Mar. 2, 19456 
Mar. 2, 19455 
Mar. 2, 19456 
Sept. 3, 1954 
Work Authorized 
BARNEGAT INLET, NJ (See Section 1 of Text) 
An 8-foot depth through inlet to Oyster Creek Channel across inner bar, 10-foot 
depth through outer bar and for jetties. 
A channel of suitable hydraulic characteristics from gorge to Oyster Creek 
Channel, and thence to deep water in bay. 
Maintenance dredging of channel to connect main inlet channel with Barnegat 
City Harbor. 
Construction of a parallel, 4,270 foot rubble mound south jetty and dredging a 
channel 10 feet deep, 300 feet wide, and 11,300 feet long. 
COHANSEY RIVER, NJ (See Section 2 of Text) 
Channel 7 feet deep over entire project. 
Channel 12 feet deep to Glass Street, thence 8 feet to Commerce Street with turning 
basin. 
COLD SPRING INLET, NJ (See Section 3 of Text) 
An inlet channel 25 feet deep and jetties. 
A 20-foot channel to deep water in harbor. 
DELAWARE RIVER BETWEEN PHILADELPHIA, PA AND 
TRENTON, NJ (See Section 4 of Text) 
A channel 28 feet deep, 300 feet wide between Alleghney Ave., Philadelphia, PA 
and Delair Bridge. 
Channel 25 feet deep from Delair Bridge to Trenton, NJ, and maintenance of 12- 
foot channel from upper end of 25-foot project to Penn Central R.R. Bridge at Ferry 
St., Trenton. 
Auxiliary channel, 20 feet deep east of Burlington Island. 
A cross channel 8 feet deep, opposite Delanco, NJ 
Anchorage at mouth of Biles Creek 
A channel 40 feet deep and 400 feet wide between Allegheny Ave., Philadelphia, 
PA, and upstream end of Newbold Island, thence 35 feet deep to Trenton Marine 
Terminal and turning basin to 800 feet wide. Relocate channel at railroad bridge 
at Delair and suitably reconstruct bridge. Construct necessary bank protection 
works; and eliminate authorized anchorage near mouth of Biles Creek, PA. 
DELAWARE RIVER, PA, NJ, AND DE, PHILADELPHIA TO THE SEA 
(See Section 5 of Text) 
Channel 35 feet deep from Allegheny Ave., Philadelphia, PA to Delaware Bay. 
Anchorages 35 feet deep at Port Richmond and Mantua Creek, a 30 foot anchorage 
at Gloucester, NJ and extend 1,000 foot channel in Philadelphia Harbor to 
Horseshoe Bend. 
An anchorage 35 feet deep at Marcus Hook, PA. 
A channel 37 feet deep from Philadelphia - Camden Bridge to Navy Yard, thence 
40 feet deep to deep water in Delaware Bay. 
A 37-foot depth channel from Allegheny Ave., Philadelphia, PA to Philadelphia- 
Camden Bridge 
A 37-foot depth in an enlargement of anchorage near Mantua Creek and Marcus 
Hook. 
Maintain enlarged channel opposite Philadelphia Navy Yard. 
A channel from Allegheny Ave., to Naval Base 40 feet deep, 400 feet wide along 
west side of channel through Philadelphia Harbor and 500 feet wide through 
Horseshoe Bend. 
Documents 
Rivers and Harbors 
Committee Doc. 19, 
73d Con., 2d sess.' 
Rivers and Harbors 
Committee Doc. 85, 
74th Cong., 2d sess.' 
H. Doc. 358, 79th Cong. 
2d sess. 
H. Doc. 236, 99th Cong. 
2nd sess. 
H. Doc. 645, 59th Cong. 
1st sess. 
Senate Committee print, 
75th Cong., 1st sess. 
H. Doc. 388, 59th Cong. 
2nd sess. 
H. Doc. 262, 77th Cong. 
1st sess. 
Rivers and Harbors 
Committee Doc. 3, 
71st Cong., 1st sess. 
Rivers and Harbors 
Committee Doc.11, 
73d Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 66, 
74th Cong., 1st sess.' 
Rivers and Harbors 
Committee Doc. 90, 
74th Cong., 2d sess. 
H. Doc. 679, 79th 
Cong., 2d sess. 
H. Doc. 358, 83rd 
Cong., 2d sess.' 
H. Doc. 733, 61st Cong. 
2d sess. 
H. Doc. 304, 71st Cong. 
2d sess.' 
Rivers and Harbors 
Committee Doc. 5, 73d 
Cong., 1st sess. 
S. Doc. 159, 75th Cong. 
3d sess.' 
H. Doc. 580, 76th Cong. 
1st sess.' 
H. Doc. 340, 77th Cong. 
1st sess.' 
Specified in Act. 
H. Doc. 358, 83rd Cong. 
2d sess. 
3-18

TABLE 3-B (Continued) 
PHILADELPHIA, PA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 
Aug. 26, 1937 
Mar. 2, 1945 
July 25, 1912 
Aug. 30, 1935 
Mar. 2, 1945 
Aug. 30, 1935 
Aug. 7, 1939 
Sept. 3, 1954 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Mar 2, 1919 
Aug. 26, 1937 
Sept. 3, 1954 
July 13, 1982 
July 1, 1954 
Anchorages at Reedy Point, Deepwater Point, Marcus Hook, and Mantua Creek 
40 feet deep and 2,300 feet wide with mean lengths of 8,000, 5,200, 13,650 and 
11,500 feet respectively. 
INDIAN RIVER INLET AND BAY, DE (See Section 6 of text) 
A 15-foot inlet channel, steel and stone jetties, 6 foot channel from end of inlet 
channel to deep water in the bay and authority to modify interior inlet channel. 
A 9-foot channel from inlet to Old Landing, including basin, and 4-foot channel to 
highway bridge at Millsboro. 
INLAND WATERWAY, REHOBOTH BAY TO DELAWARE BAY, DE 
(See Section 7 of Text) 
For a 6-foot depth canal to connect Rehoboth Bay and Delaware Bay. 
For a 6-foot depth entrance near Lewes, for jetties, for widening the canal from 
Broadkill River to Lewes and basin. 
For a 10-foot depth from Delaware Bay to Lewes and in basin, and for extending 
jetties.6. 
INLAND WATERWAY FROM DELAWARE RIVER TO CHESAPEAKE 
BAY, DE & MD. (See Section 8 of Text) 
A sea level channel 27 feet deep, 250 feet wide from Delaware River to Elk River and 
400 feet wide down Elk River and Chesapeake Bay to deep water at or near Pooles 
Island; alter existing bridges over canal; enlarge Delaware City Branch Channel 
to 8 feet deep and 50 feet wide, with a basin same depth and revetment of both 
banks east of Fifth Street; enlarge anchorage and mooring basin in Back Creek to 
400 feet wide, 1,000 feet long and 12 feet deep; extend jetties at Reedy Point; and 
construct bulkheads. 
Construct a 4-lane high-level fixed highway bridge at or near St. Georges. 
A channel 35 feet deep and 450 feet wide from Delaware River through Elk River 
and Chesapeake Bay at water of that depth in the bay, including a cutoff at Penn 
Central Railroad crossing, with a minimum radius of curvature of 7,000 feet at 
bends; a high level fixed railroad bridge over cutoff; high level fixed highway 
bridge at Reedy Point and Summit; and an anchorage in Elk River 35 feet deep 
and 1,200 feet wide, averaging 3,700 feet long. 
MANASQUAN RIVER, NJ (See Section 9 of Text) 
Channel 8 feet deep and provision of works designed to secure channel. 
Widening channel on northerly side. 
Deepening channel to 12 and 14 feet, 10 and 12 foot anchorages.7 
MISPILLION RIVER, DE (See Section 10 of Text) 
A 6-foot depth and extension of south jetty. 
Extension of north jetty. 
A channel 9 feet deep, 80 feet wide from like depth in Delaware Bay to the landward 
end of the jetties and thence 60 feet wide to Milford, including 3 cutoffs, with a 
turning basin at Milford. 
MURDERKILL RIVER, DE (See Section 11 of Text) 
A channel 7 feet deep at low water from Frederica to the 7 foot curve in Delaware 
Bay, 80 feet wide down to the mouth, and 150 feet wide at bottom and 250 feet wide 
at top from the mouth to the 7 foot curve in the bay. Embankment of dredged 
material on each side to a height of at least 2 feet above high spring tides. 
NEW JERSEY INTRACOASTAL WATERWAY (See Section 13 of Text) 
A channel 12 feet deep at mean low water and generally 100 feet wide, extending 
from the Atlantic Ocean at Manasquan Inlet, NJ, to Delaware Bay above Cape 
May, NJ. Construction of a canal of similar dimensions from Cape May Harbor to 
Delaware Bay via the New England Creek basin, with adequate jetties at the 
Delaware Bay entrance. 
H. Doc. 185, 85th Cong. 
1st sess. 
74th Cong., 1st sess.' 
Rivers and Harbors 
Committee Doc. 41, 
75th Cong. 1st sess. 
H. Doc. 330, 76th 
Cong., 1st sess.' 
H. Doc. 823, 60th Cong., 
1st sess. and Rivers 
and Harbors 
Committee Doc. 51, 
61st Cong., 3d sess. 
Rivers and Harbors 
Committee Doc. 56, 
75th Cong., 1st sess.' 
H. Doc. 344, 77th Cong., 
1st sess.' 
H. Doc. 201, 72d Cong., 
1st sess. and Rivers 
and Harbors 
Committee Docs. 18 
and 24, 73d Cong., 
2d sess.' 
Public Law 310, 76th 
Cong., 1st sess. 
S. Doc. 123, 83rd Cong. 
2d sess.' 
H. Doc. 482, 70th Cong., 
2d sess. 
Senate Committee Doc., 
74th Cong., 1st sess. 
H. Doc. 356, 77th Cong., 
1st sess. 
H. Doc. 678, 62d Cong., 
2d sess.' 
Rivers and Harbors 
Committee, Doc. 83, 
74th Cong., 2d sess.' 
S. Soc. 229, 81st Cong., 
2d sess.' 
H. Ex. Doc. 21, 52nd 
Cong. 1st sess. 
(See page 981 
Annual Report 
of 1892.) 
H. Doc. 133, 76th Cong., 
1st sess.) 
Rivers and Harbors 
Committee Doc. 525 
79th Cong., 2nd sess. 
3-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 3-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
SCHUYLKILL RIVER, PA. (See Section 14 of Text) 
Aug. 8, 1917 Depths of 35 feet from mouth to Girard Point thence 30 feet, 26, and 22 feet to H. Doc. 1270, 64th 
University Avenue Bridge, Philadelphia. Cong., 1st sess. 
July 3, 1930 A depth of 30 feet instead of 35 feet between the mouth and the conditional restora- Rivers and Harbors 
tion and maintenance of the channel below Passyunk Ave., by the United States. Committee Doc. 40, 
71st Cong., 2d sess. 1 
July 24, 1946 A depth of 33 feet from the channel in Delaware River to Passyunk Ave., restora- H. Doc. 699, 79th Cong., 
tion of the project channel dimensions between Passyunk Ave., and University 2d sess. 1 
Ave., and full maintenance of the entire project. 
TUCKERTON CREEK, NJ (See Section 15 of Text) 
June 13, 1902 For depths of 6, 5 and 3 feet. H. Doc. 274, 56th Cong. 
1st sess. 
Mar. 3, 1905 Substitution of channel as across Little Tuckerton Bay. Specified in act. 
(H. Doc. 1040, 
64th Cong., 1st sess.) 
WILMINGTON HARBOR, DE (See Section 16 of Text) 
June 3, 1896 Depths of 21, 10 and 7 feet and jetties. H. Doc. 66, 54th Cong., 
1st sess. 
Annual Report, 1897 
p. 1250' 
July 25, 1912 Purchase or construct a dredge and auxiliaries including a wharf and depot, and H. Doc. 359, 62d Cong., 
maintenance of project. 2nd sess. 
Sept. 22, 1922 Entrance channel and basin with 25-foot depth and construction by local interests H. Doc. 114, 67th Cong., 
of new south jetty. 1st sess. and S. 
Committee Print, 68th 
Cong., 1st sess. 
July 3, 1930 A 30-foot depth between Delaware River and Lobdell Canal and modification or Rivers and Harbors 
removal of a portion of north jetty. Committee Doc. 20, 
71st Cong. 2d sess. 
Aug. 30, 19358 Completion of new south jetty by the United States subject to provision that city of Rivers and Harbors 
Wilmington reimburse the United States for cost, without interest, of any part of Committee Doc. 32 
structure that may subsequently be occupied and utilized for city activities. 73d Cong., 2d sess. 
Oct. 17, 1940 Permit temporary occupancy by city of Wilmington of any part of south jetty for H. Doc. 658, 76th Cong., 
city activities under revocable license, provided occupied portion of jetty is 3rd sess. 
properly maintained without expense to the United States. 
July 14, 1960 A 35-foot depth between Delaware River ship channel and Lobdell Canal including S. Doc. 88, 86th Cong., 
turning basin of same depth, opposite Wilmington Marine Terminal, 200 feet 2d sess. 
wide, 2,900 feet long on north side of channel, and 2,000 feet long on north side of 
basin. 
1. Contains latest published maps. 
2. Also Public Works Administration, September 6, 1933, and 
Emergency Relief Administration, May 28, 1935. 
3. Also Public Works Administration. 
4. Channel 37 feet deep and 600 feet wide from Naval Base to 
Philadelphia-Camden Bridge, deferred for restudy. 
5. Channel 37 feet deep and 600 feet wide from Philadelphia-Camden 
Bridge to Allegheny Ave. deferred for restudy. 
6. Extension of jetties considered to be active. 
7. The 10 and 12 foot anchorages are considered inactive. 
8. Also May 28, 1935, under Emergency Relief Administration. 
3-20

PHILADELPHIA, PA. DISTRICT 
TABLE 3-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Completed Projects Status Report for Construction Maintenance 
Absecon Creek, NJ' COMPLETED 1969 11,935 167,682* 
Absecon Inlet, NJ COMPLETED 1984 534,209 5,939,362 
Appoquinimink River, DE COMPLETED 1931 36,973 41,270 
Big Timber Creek, NJ' COMPLETED 1962 58,6652 53,986* 
Broadkill River, DE COMPLETED 1976 68,228 243,641 
Cape May Inlet, NJ COMPLETED 1984 149,995 1,115.354 
Cedar Creek, Sussex City, DE COMPLETED - 256,100 - 
Cold Spring Inlet, NJ COMPLETED 1984 879,275 2,391,507 
Cooper River, NJ' COMPLETED 1962 33,102 379,244* 
Delaware River at Camden, NJ COMPLETED 1982 464,906 362,79912 
Delaware River, Pennsville, NJ COMPLETED - 256,624 - 
Double Creek, NJ1 COMPLETED 1912 7,800 -5 
Harbor of Refuge COMPLETED 1985 516,230 1,104,769 
Inland Waterway from Chincoteague Bay 
to Delaware Bay COMPLETED 1981 168,41218's 98,36019 
Little River, DE COMPLETED 1980 12,016 288,310 
Mantua Creek, NJ COMPLETED 1966 169,687 339,340* 
Maurice River, NJ COMPLETED 1948 - - 
Delaware Bay to Millville fixed Bridge COMPLETED - 143,98410 147,050 
Millville fixed bridge to upper end of project SEE TABLE 3-G 
**Neshaminy State Park Harbor, PA COMPLETED 1968 128,20321 54,601 
Oldmans Creek, NJ COMPLETED 1941 31,188 32,125 
**Pepper Creek, DE' COMPLETED 1965 138,09422 1,797* 
Raccoon Creek, NJ COMPLETED 1981 83,66520 341,734 
Salem River COMPLETED 1985 107,634 1,317,778 
St. Jones River, DE 1961 - - 
Delaware Bay to Lebanon""1 COMPLETED - 207,102 66,093 
Jetties and entrance at mouth - - - 
Schuylkill River above Fairmount Dam, PA' COMPLETED 1955 4,291,810 -5 
Smyrna River, DE 1949 - - 
Delaware River to Wharf at Smyrna Landing' 5 COMPLETED - 198,844 197,327 
Wharf at Smyrna Landing to fixed bridge SEE TABLE 3-G - - - 
Toms River, NJ 1950 - - 
Channel 5 feet deep' COMPLETED - 10,050 33,311 
Channel 12 feet deep9 SEE TABLE 3-G - - - 
Waterway from Indian River Inlet 
to Reboboth Bay, DE COMPLETED 1981 90,908 241,497 
Woodbury Creek, NJ' COMPLETED 1940 27,09316 56,474 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Inactive Projects Status Report for Construction Maintenance 
Alloway Creek, NJ1 INACTIVE 1931 21,398 35,761 
Aquatic Plant Control 1975 87,594 - 
Chester River, PA3 INACTIVE 1931 6,000 1,139 
Dennis Creek, NJ' INACTIVE 1897 4,701 - 
Goshen Creek, NJ' INACTIVE 1905 15,359 870 
Ice Harbor at Marcus Hook, PA'- 6 INACTIVE 1928 208,964 14,336 
Ice Harbor at New Castle, DE'-6 INACTIVE 1898 224,704 - 
Leipsic River, DE' INACTIVE 1931 36,956 32,345 
Little Egg Harbor, NJ" 4 INACTIVE -7 15,048 - 
Maurice River, NJ 1948 
Channel 8 feet deep, Delaware Bay to mouth INACTIVE - - 
3-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 3-C 
OTHER AUTHORIZED 
NAVIGATION PROJECTS (Cont'd) 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Deferred Projects Status Report for Construction Maintenance 
St. Jones River, DE 1961 - - 
Delaware Bay to Lebanon1 ,1 1 - 207,102 66,093 
Jetties and new entrance at mouth 9 DEFERRED - - - 
1. Completed. 
2. Excludes $50,000 contributed funds expended for new work. 
3. Includes $6,000 new work and $63 maintenance funds expended 
on previous projects. 
4. Abandonment recommended in House Doc. 467, 69th Congress, 
1st Sess. 
5. Maintenance assumed by local interests. 
6. Harbor not now required by commerce. 
7. Last appropriation for project was in 1852. No information is at 
hand relative to work done. 
8. Includes $3,000 for new work for previous projects. 
9. Deferred 
10. Includes $43,000 new work funds expended on previous projects. 
11. Includes $54,590 new work and $28,935 maintenance funds 
expended on previous projects. 
12. Excludes $15,000 contributed funds. 
15. Includes $55,085 new work and $22,723 maintenance funds 
expended on previous projects. 
16. Includes $2,950 new work funds expended on previous projects. 
18. Entire amount expended on previous projects repealed in 1905. 
19. Excludes $2,000 contributed funds and includes $25,330 for 
maintenance for previous projects. 
20. Includes $757 new work funds expended on previous projects. 
21. Excludes $327,957 contributed funds allotted expended for new 
work. 
22. Excludes $38,988 non-Federal Funds. 
*Operation and maintenance figure includes cost incurred for preparation of environmental impact statements. 
**Projects authorized by the Chief of Engineers. 
3-22

PHILADELPHIA, PA. DISTRICT 
TABLE 3-D 
OTHER AUTHORIZED 
BEACH EROSION CONTROL PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Corson Inlet and Ludlam Beach, NJ ACTIVE* 1978 314,400 - 
Great Egg Harbor Inlet and Peck Beach, NJ ACTIVE* 1978 387,882 
Townsend Inlet and Seven Mile Beach, NJ ACTIVE* - - - 
Atlantic City, NJ INACTIVE 1972 2,083,289 - 
Ocean City, NJ INACTIVE 1969 395,8313 -' 
Stone Harbor, NJ INACTIVE 1961 - -' 
Barnegat Light, NJ DEFERRED 1964 70,908 - 
Cape May City, NJ DEFERRED 1961 22,9572 1-' 
Long Beach Island, NJ DEFERRED 1964 40,665 -_1 
North Wildwood, NJ DEFERRED 1961 - - 
Rehoboth Beach to Indian River Inlet, DE4 1965 326,116 -' 
Ventnor, Margate and Longport, NJ DEFERRED 1961 - - 
1. Operation and maintenance required by law to be assumed by 3. Excludes cost of $1,146,325 to local interests and $272,766 Federal 
local interests. participation expended under Public Works Acceleration Program 
2. Excludes $58,585 Accelerated Public Works funds expended for for Extension of five existing groins completed 11 May 1964. 
extension to two groins. 4. This project was included in and modified by the Delaware Coast 
project. 
* NO CURRENT YEAR FUNDS. 
OTHER AUTHORIZED 
TABLE 3-E FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Allentown, Lehigh River, PA COMPLETED 1961 1,615,581 -1 
Bethlehem, Lehigh River, PA COMPLETED 1966 4,520,995 - 
Mt. Holly, NJ COMPLETED 1946 283,655 -1 
Hay Creek, Birdsboro, PA ACTIVE 1984 335,299 - 
Pottstown, PA ACTIVE 1984 487,366 - 
Tamaqua, PA ACTIVE 1984 524,373 - 
Trexler Lake, PA' INACTIVE 1981 
Aquashicola Reservoir, PA2 DEFERRED 1963 - - 
Maiden Creek Reservoir, PA2 DEFERRED 1963 - - 
1. Maintenance assumed by local interest as required by authorizing 
project. 
2. New project deferred. 
3. $1,316,464 expended for preconstruction planning only. 
4. Transferred to Baltimore Dist. in 1982. 
3-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 3-F MULTIPURPOSE PROJECT INCLUDING POWER 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Report for Construction Maintenance 
Tocks Island, PA, NJ and NY2 1979 65,106,2601 
Tocks Island (Relocation of U.S. Route 209 only) PA2 1979 195,223 - 
1. Includes $3,489,088 for AE&D. / authority to proceed with the project. Legislation would be required 
2. National Parks and Recreation Act of 1978 terminated Corps' to proceed with the project. 
TABLE 3-G DEAUTHORIZED PROJECTS 
For Last Full Date Federal Contributed 
Report See Annual And Funds Funds 
Navigation Projects Report For Authority Expended Expended 
3 Oct 78 
Appoquinimink River, DE 1 1931 HD 95-351 $ 78,243- 
5 Aug 77 
Delaware River, Mouth of Neversink 1917 HD 94-192 - - 
Maurice River, NJ 1948 Section 12 PL 93-251 
Millville fixed bridge to upper end of project 2 
2 Nov 79 
Oldmans Creek, NJ 1941 Section 12 PL 93-251 $ 63,313 - 
2 Nov 79 
Rancocas River, NJ4 1942 Section 12 PL 93-251 $ 57,590- 
2 Nov 79 
Smyrna River, DE5 1949 HD 95-157 $396,169- 
Wharf at Smyrna Landing to fixed bridge. 
2 Nov 79 
Toms River, NJ6 1950 Section 12 PL 93-251 $ 43,361- 
Channel 12 feet deep 
Flood Control Projects 
2 Nov 79 
Lehigh River at Bethlehem, PA7 1966 Section 12 PL 93-251 $4,520,995 
Includes $36,973 new work, and $41,270 for maintenance. 
There is no need now for this portion of the project. 
Includes $31,188 new work, and $32,125 for maintenance. 
Includes $44,500 new work, and $13,090 for maintenance. 
5. Includes $143,759 new work, $55,085 previous project, $174,602 for 
maintenance, and $22,723 maintenance, previous project. 
6. Includes $10,050 new work, and $33,311 for maintenance. 
7. Maintenance assumed by local interest. 
3-24 
1. 
2. 
3. 
4.

BALTIMORE, MD DISTRICT * 
This district comprises the watershed of Susquehanna 
River and its tributaries from headwaters in south 
central New York State through central Pennsylvania to 
its mouth in Chesapeake Bay; watershed of the Potomac 
River and its tributaries from headwaters in Maryland, 
eastern West Virginia, and Northern Virginia to its 
mouth in Chesapeake Bay; District of Columbia; and 
southwestern portion of Delaware. It includes that portion 
of Chesapeake Bay and its tributaries north of Smith 
Point, MD, on western shore of the bay, and includes that 
portion of Maryland between Chesapeake Bay and 
Atlantic Ocean. 
IMPROVEMENTS 
Navigation 
1. Baltimore Harbor and 
Channels, MD and VA ............... 
2. Baltimore Harbor, MD, 
Collection and Removal of Drift ....... 
3. Chester River, MD .................... 
4. Claiborne Harbor, MD . ............... 
5. Fishing Creek, MD .................... 
6. Herring Bay and Rockhold 
Creek, MD ....................... 
7. Herring Creek, MD .................... 
8. Island Creek, St. Georges 
Island, MD....................... 
9. Little Wicomico River, VA ............. 
10. Lower Thorofare, Deal 
Island, MD....................... 
11. Lowes Wharf, MD .................... 
12. Ocean City Harbor and Inlet and 
Sinepuxent Bay, MD ................ 
13. Parish Creek, MD................... 
14. Potomac and Anacostia 
Rivers, DC, Collection 
and Removal of Drift ................ 
15. Potomac River-Aquatic 
Plant Control, MD, VA, DC .......... 
16. Prevention of Obstructions 
and Injurious Deposits, 
Baltimore Harbor, MD ............... 
17. Rhodes Point to Tylerton, MD .......... 
18. St. Patricks Creek, MD ................ 
19. Slaughter Creek, MD .................. 
20. Tred Avon River, MD ................. 
21. Twitch Cove and Big 
Thorofare, MD.................... 
22. Upper Thorofare, MD ................. 
23. Washington Harbor, DC ............... 
24. Wicomico River, MD .................. 
Page Navigation (cont'd) 
25. Reconnaissance and Condition Surveys... 
4-3 26. Navigation work under special 
authorization..................... 
4-4 
4-4 
4-5 
4-5 
4-5 
4-5 
4-6 
4-6 
4-6 
4-6 
4-7 
4-7 
Beach Erosion Control 
27. Colonial Beach, VA .................. 
28. Beach Erosion Control Work 
under special authorization ........... 
Flood Control 
29. Bloomington Lake, MD and WV ....... 
30. Cumberland, MD, and Ridgeley, WV ..... 
31. Lackawanna River Basin, PA ........... 
31A. Aylesworth Creek Lake, PA ........... 
32. Raystown Lake, Raystown Branch, 
Juniata River, PA ................... 
33. Southern New York Flood 
33A. 
33B. 
4-7 33C. 
33D. 
4-8 33E. 
33F. 
33G. 
4-8 33H. 
4-8 33I. 
4-8 33J. 
4-9 33K. 
4-9 33L. 
33M. 
4-9 33N. 
4-10 34. 
4-10 35. 
4-10 
Control Projects ................... 
Addison, NY ......................... 
Almond Lake, NY ..................... 
Arkport Dam, NY ................... 
Avoca, NY .......................... 
Binghamton, NY.................... 
Canisteo, NY ......................... 
Corning, NY ......................... 
East Sidney Lake, NY ................. 
Elmira, NY .......................... 
Hornell, NY......................... 
Lisle, NY ............................ 
Oxford, NY .......................... 
Whitney Point Lake, NY ............... 
Whitney Point Village, NY ............. 
Stillwater Lake, Lackawanna River, PA .. 
Susquehanna River Flood Control 
Projects, NY and PA ................ 
Page 
4-11 
4-11 
4-11 
4-11 
4-11 
4-12 
4-12 
4-12 
4-12 
4-13 
4-13 
4-13 
4-13 
4-13 
4-14 
4-14 
4-14 
4-15 
4-15 
4-15 
4-16 
4-16 
4-16 
4-16 
4-16 
4-17 
4-1 
]

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Flood Control (cont'd) 
35A. Cowanesque Lake, PA ................. 
35B. Tioga-Hammond Lakes, PA ............ 
36. West Branch of Susquehanna River, PA . 
36A. Alvin R. Bush Dam, PA ............... 
36B. Curwensville Lake, PA................ 
36C. Foster Joseph Sayers Dam, PA ......... 
37. Wyoming Valley, PA ................. 
38. York, Indian Rock Dam, PA ............ 
39. Inspection of Completed Flood 
Control Projects .................... 
40. Scheduling Flood Control Reservoir 
Operations ........................ 
41. Flood Control Work under special 
authorization .................... 
Water Supply 
42. Washington Aqueduct ................. 
General Investigations 
43. Surveys ........................... 
Page 
4-17 44. 
4-17 45. 
4-18 
4-18 46. 
4-18 
4-18 
4-19 
A _1 
4-19 
4-19 
4-19 
4-19 
4-20 
4-20 
General Investigations (cont'd) 
Collection and Study of Basic Data ...... 
Continuation of Planning 
and Engineering .................... 
Advanced Engineering 
and Design....................... 
Tables 
Table 4-A Cost and Financial Statement ...... 
Table 4-B Authorizing Legislation ........... 
Table 4-C Other Authorized 
Navigation Projects .............. 
Table 4-D Other Authorized Beach Erosion 
Control Projects................ 
Table 4-E Other Authorized Flood 
Control Projects................ 
Table 4-F Not Applicable 
Table 4-G Deauthorized Projects ............ 
Table 4-H Reconnaissance and 
Condition Surveys .............. 
Table 4-I Inspection of 
Completed Projects .............. 
4-2 
Page 
4-20 
4-20 
4-20 
4-22 
4-27 
4-33 
4-35 
4-35 
4-37 
4-38 
4-39

BALTIMORE, MD DISTRICT 
Navigation 
1. BALTIMORE HARBOR AND 
CHANNELS, MD AND VA 
Location. Baltimore Harbor is at the head of the 
navigable portion of Patapsco River about 12 miles from 
Chesapeake Bay. The Patapsco River rises near the town 
of Westminster in Carroll County, MD, and flows generally 
southeast for about 65 miles to enter Chesapeake 
Bay. (See National Ocean Survey Chart 12278.) 
Existing Project. 
a. A uniform main channel depth of 50 feet between 
Cape Charles, VA, and Fort McHenry at Baltimore, MD, 
with dimensions as follows: (1) Cape Henry Channel: 50 
feet deep and 1,000 feet wide from the 50-foot depth curve 
in the Atlantic Ocean to that depth in Chesapeake Bay, 
a distance of 2.3 miles; (2) York Spit Channel: 50 feet deep 
and 1,000 feet wide connecting the 50-foot depth curves 
in Chesapeake Bay near York Spit, a distance of 18.2 
miles; (3) Rappahannock Shoal Channel: 50 feet deep and 
1,000 feet wide connecting the 50-foot depth curves in 
the Chesapeake Bay opposite the Rappahannock River, 
a distance of 8.9 miles; and (4) Baltimore Harbor Approach 
Channels: 50 feet deep and generally 800 feet 
wide, widened at the approach and bends, from the 
50-foot depth curve in Chesapeake Bay opposite the 
mouth of the Magothy River to Fort McHenry on the 
Patapsco River, a distance of 19.9 miles. 
b. Branch channels with dimensions as follows: (1) 
Connecting Channel to Chesapeake and Delaware Canal 
Approach Channel: 35 feet deep, 600 feet wide, and 13.0 
miles long from the Cutoff-Brewerton Angle in the main 
channel to the 35-foot depth curves in the natural channel 
on the east side of Chesapeake Bay which is part of the 
inland waterway from Delaware River to Chesapeake 
Bay, The channel includes the Brewerton Extension and 
Swan Point and Tolchester Sections; (2) Curtis Bay: 50 
feet deep, 600 feet wide, and 2.3 miles long from the main 
channel to and including a turning basin at the head of 
Curtis Bay; (3) Curtis Creek: (a) a channel, 35 feet deep 
and generally 200 feet wide, from the 50-foot channel in 
Curtis Bay to 750 feet downstream of the Pennington 
Avenue Bridge; (b) a channel, 22 feet deep and generally 
200 feet wide, from the 35-foot channel to and along the 
marginal wharf of the Curtis Bay Ordnance Depot; (c) 
an irregular shaped 3-acre basin, with a depth of 18 feet, 
adjacent to the head of the 22-foot channel; (d) a basin, 
15 feet deep and 450 feet wide, from the end of the 22-foot 
channel to the end of the marginal wharf; and (e) a channel, 
22 feet deep and 200 feet wide, from the 22-foot 
channel south of the Baltimore and Ohio Railroad Bridge 
to the vicinity of Arundel Cove, a distance of 2,800 feet, 
thence 100 feet wide in Arundel Cove for a distance of 
2,100 feet, with an anchorage basin, 700 feet square, adjacent 
to the channel and southwest of the wharf of the 
Coast Guard Depot at Curtis Bay; (4) Middle Branch: (a) 
Ferry Bar East Section: a channel, 42 feet deep and 600 
feet wide, from the main channel at Fort McHenry to 
Ferry Bar, a distance of 1.4 miles; (b) Ferry Bar West 
Section: a channel, 35 feet deep and 400 feet wide, from 
the Ferry Bar East Section to Ferry Bar, a distance of 
0.8 mile; (c) Spring Garden Section: a channel, 27 feet 
deep and 250 feet wide, from Ferry Bar to and including 
a turning and anchorage basin immediately below the 
Western Maryland Railway Bridge, a distance of 1.0 mile; 
and (5) Northwest Branch: Federal maintenance of 
39-foot or 35-foot deep channels after either depth has 
been provided by local interests: (a) East Channel: a channel, 
49 feet deep, 600 feet wide, and 1.0 mile long with 
a turning basin at the head of the channel from that 
depth existing at the time of construction; and (b) West 
Channel: a channel, 40 feet deep, 600 feet wide, and 1.2 
miles long with a turning basin at the head of the channel 
from that depth existing at the time of construction. 
c. The following anchorages: (1) Quarantine Anchorage: 
35 feet deep, 3,500 feet long, and 600 feet wide; 
(2) Riverview Anchorage No. 2: 30 feet deep, 2,400 feet 
long, and 1,300 feet wide; (3) Riverview Anchorage No. 
1: 35 feet deep, 4,500 feet long, and 1,500 feet wide; and 
(4) Fort McHenry Anchorage: 35 feet deep, 3,500 feet 
long, and 400 feet wide. 
The mean range of tide is 2.8 feet at the Cape Henry 
Channel, 2.3 feet at the York Spit Channel, 1.4 feet at 
the Rappahannock Shoal Channel, 0.8 foot at the 
Craighill Entrance, 0.9 foot in the Cutoff Section, 1.1 feet 
at Fort McHenry, and 1.2 feet at Pooles Island in the 
upper Chesapeake Bay. Depths refer to mean low water. 
Estimated cost for new work is $412,880,000 which includes: 
$8,330,000 for completed work through the River 
and Harbor Act of 1945; $47,350,000 (October 1985 
prices) for work authorized by the River and Harbor Act 
of 1958 of which $42,800,000 is Corps of Engineers, 
$60,000 is U.S. Coast Guard and $4,490,000 is non- 
Federal; and $357,200,000 (October 1985 prices) for work 
authorized by the River and Harbor Act of 1970, of which 
$400,000 is U.S. Coast Guard and $356,800,000 is Corps 
of Engineers and non-Federal. 
Widening 35-foot depth from Port Covington Channel 
from 150 to 400 feet to Ferry Bar, widening 27-foot depth 
channel from 150 to 250 feet to Hanover Street Bridge, 
and providing a channel 27 feet deep by 250 feet wide 
to Western Maryland Railway Bridge with an anchorage 
and turning basin at upper end is considered inactive and 
is excluded from the foregoing estimate. Estimated cost 
(1954) of this portion is $1,603,000. 
Local cooperation. Requirements are described in full 
on page 4-3 of Fiscal Year 1982 Annual Report. 
Terminal facilities. The Port of Baltimore has 45 miles 
of waterfront of which 25 miles are industrially developed. 
There are 94 covered and open overseas piers for 
the loading and discharging of 173 ships, providing 84 
general cargo, 65 specialized cargo, and 24 public bulk 
cargo berths. The existing ground storage is equivalent 
to 53,700 railroad cars of cargo. There are 31 public 
general merchandise warehouses, with 4.9 million square 
feet of storage space and 4.7 million cubic feet of cold 
storage space. Eight ship-building, ship repair, and ship 
dismantling yards are available for handling up to 90 vessels. 
The three grain elevators in the port have a capacity 
of about 13 million bushels. Latest description of 
terminal facilities is in "Port Series No. 10 (revised 1983)" 
on Port of Baltimore, MD, (issued by Board of Engineers 
for Rivers and Harbors). 
4-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Operations and results during fiscal year. New Work, 
Baltimore District: Remaining work under the River and 
Harbor Act of 1958, deepening and widening the Connecting 
Channel (Brewerton Channel Eastern Extension), 
was reactivated May 15, 1985 and preconstruction planning 
was essentially completed during FY 1985 at a cost 
of $198,183. The District's Supplement to the General 
Design Memorandum which recommended deepening 
and widening of the Connecting Channel from 27 feet 
deep and 400 feet wide to 35 feet deep and 450 feet wide 
was approved by the Assistant Secretary of the Army 
on May 20, 1986. New work dredging of the Connecting 
Channel was included with the District's maintenance 
dredging contract awarded on June 12, 1986. Dredging 
of 4,000,000 cubic yards from the Connecting Channel 
at a cost of $8,552,550 commenced on August 22, 1986 
and was approximately 50% complete as of September 
30, 1986. Engineering and design of work authorized by 
the River and Harbor Act of 1970 continued in FY 1986 
at a cost of $712,000. A Local Cooperation Agreement 
between the Assistant Secretary of the Army and the 
State of Maryland was executed on June 17, 1986. Initiation 
of construction is pending enactment of a nationwide 
Federal Port use charge. 
Maintenance, Baltimore District: Condition surveys of 
the project channels were made. Maintenance dredging 
of the Brewerton Channel Eastern Extension, Swan 
Point and Tolchester Channels, by contract, began on 
July 11, 1986 and was still in progress at the end of the 
fiscal year. An estimated 1,700,000 cubic yards of material 
was dredged and deposited in the Hart-Miller Island 
containment facility at a cost of $5,585,000 as of September 
1986. 
Maintenance, Norfolk District: Condition surveys of 
the York Spit and Rappahannock Shoal Channels were 
made. Maintenance dredging of the Cape Henry Channel, 
by government hopper dredge, began on March 1, 
1986 and was completed on March 26, 1986. A total of 
84,156 cubic yards of material were dredged and deposited 
in the Dam Neck ocean disposal area at a cost of 
$950,000. 
2. BALTIMORE HARBOR, MD 
COLLECTION AND REMOVAL 
OF DRIFT 
Location. Project applies to Baltimore Harbor, MD, 
and its tributaries. 
Existing project. Provides for collection and removal 
of drift from Baltimore Harbor and its tributary waters, 
and authorizes the Secretary of the Army to allot such 
amounts as may be necessary for work from appropriations 
for maintenance and improvement of existing river 
and harbor works or other available appropriations, and 
that this work shall be carried as a separate and distinct 
project. It is wholly a work of maintenance. Purpose of 
work is to afford relief from variable conditions of obstruction. 
Local cooperation. None required. 
Terminal facilities. See Section 1 of this text. 
Operations and results during fiscal year. Maintenance: 
Operations, by hired labor, consisted of collection 
and disposal of 22,680 cubic feet of driftwood, 
ranging from small blocks up to timbers of large 
dimensions. 
3. CHESTER RIVER, MD 
Location. Rises in Kent County, DE, flows 50 miles 
generally southwesterly and empties into the Chesapeake 
Bay. Kent Island Narrows is a passage connecting 
Chester River and Eastern Bay. Wells Cove is an indentation 
on the easterly side of Kent Island Narrows about 
0.4 miles south of the highway bridge crossing the Narrows. 
(See Coast and Geodetic Survey Charts 548 and 
1226.) 
Previous project. For details see page 262 of the 1960 
Annual Report. 
Existing project. Provides for a channel 6 feet deep at 
mean low water and 60 feet wide from Crumpton to Jones 
Landing, section included in project is about 5.5 miles 
long with the lower end of the section being about 37 
miles above mouth of river; for a channel 7 feet deep at 
mean low water and 75 feet wide from Chester River to 
Eastern Bay through Kent Island Narrows; and a channel 
7 feet deep at mean low water and 75 feet wide extending 
from 7-foot deep curve in Kent Island Narrows 
800 feet into Wells Cove with a basin of same depth and 
300 feet square at head of channel. Mean range of tide 
is 2.4 feet. Cost of new work for completed project was 
$32,454, exclusive of amounts expended on previous 
projects. Widening 7-foot deep channel from 75 to 100 
feet from Chester River to Eastern Bay through Kent 
Island Narrows is considered inactive and is excluded 
from the foregoing estimate. 
Local cooperation. Fully complied with except local interests 
are to furnish spoil disposal areas for future maintenance 
of Wells Cove section of the project. 
Terminal facilities. There are two bulkhead wharves 
on Chester River section. Facilities on the Kent Island 
Narrows section of the existing project consist of about 
10,000 linear feet of timber pile bulkheaded wharf. About 
1,350 linear feet of the wharf is owned and operated by 
the Queen Anne's County; the remainder is privately 
owned. The privately owned bulkheaded wharf is operated 
mostly by the 7 marinas located on the Narrows 
with the remainder being owned and operated by the 
seafood packing houses in the area. In addition to the 
slips of the marinas, there are marine railways, launching 
ramps, and travel-lifts. All of these facilities are in 
good condition and are located adjacent to the proposed 
improvements. In Wells Cove there is a small wharf, a 
small marine railway, and a public landing. All facilities 
are privately owned except the public landing on Wells 
Cove. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Engineering 
and design work was accomplished in connection with 
proposed maintenance dredging. 
4-4

BALTIMORE, MD DISTRICT 
4. CLAIBORNE HARBOR, MD 
Location. The harbor is located on the eastern side of 
Eastern Bay, an arm of Chesapeake Bay, about 42 miles 
southeast of Baltimore Harbor. (See U.S. Coast and 
Geodetic Survey Chart No. 1225.) 
Existing project. This provides for a channel 14 feet 
deep from the vicinity of the harbor wharves to deep 
water in Eastern Bay with widths of 100 feet at mean 
low water for a distance of 1,800 feet to the bend opposite 
the existing Black Beacon, thence widening in a distance 
of 260 feet to 150 feet to the 14-foot depth in 
Eastern Bay, with necessary widening at the bends. The 
total length of the channel is about 4,400 feet. The project 
also provides for a 250-foot extension of the jetty built 
by the railway company. 
Terminal facilities. There are two solid bulkhead 
wharves, with open pile piers at their outer ends, served 
by this improvement. 
Operations and results during fiscal year. Maintenance: 
A contract was awarded for rehabilitation of 500 
l.f. of revetment. 
5. FISHING CREEK, MD 
Location. A narrow winding tidal stream which enters 
Chesapeake Bay from the west 56 miles south of Baltimore 
and about 26 miles south of Annapolis, MD. (See 
U.S. Coast and Geodetic Survey Chart 1226.) 
Existing project. A channel 7 feet deep with widths 
of 100 and 60 feet from deep water in the Chesapeake 
Bay to an anchorage of same depth, 120 feet wide and 
400 feet long, located in marsh 500 feet above mouth of 
creek, and twin stone jetties at entrance; north jetty is 
about 1,050 feet long, and south jetty about 1,100 feet 
long. The mean range of tide is about 1 foot. Cost of new 
work for the completed project was $111,242. 
SLocal cooperation. Fully complied with except that 
local interests are to furnish spoil disposal areas as needed 
for future maintenance. 
Terminal facilities. Seven hundred feet of bulkhead 
wharf are available on the south side of the entrance 
channel running west from bay shore, and the U.S. Navy 
Department constructed a pile-and-timber wharf on west 
side of basin. 
Operations and results during fiscal year. Maintenance: 
A contract for rehabilitation of twin stone jetties 
was awarded on November 7, 1985. Work was 
completed on April 7, 1986. 
6. HERRING BAY AND 
ROCKHOLD CREEK, MD 
Location. Herring Bay is a wide-mouthed indentation 
on the west side of Chesapeake Bay about 20 miles below 
Annapolis, MD. It is about 3 miles long from north 
to south and penetrates the shore for a depth of about 
1 mile. Rockhold Creek, which is about 2.5 miles long, 
is an estuary which extends northward from the northerly 
end of Herring Bay. (See U.S. Coast and Geodetic 
Survey Chart 1225.) 
Existing project. Provides for channel 7 feet deep and 
60 feet wide from 7-foot contour in Herring Bay to vicinity 
of county wharf on Rockhold Creek, with turning 
basin of same depth, 100 feet wide and 150 feet long at 
head of channel, and a stone breakwater approximately 
900 feet long east of entrance channel. Mean range of tide 
is about 1.5 feet and extreme tidal range about 4 feet. 
The Federal cost of new work for completed project was 
$50,591. 
Local cooperation. Fully complied with except local interests 
are to furnish disposal areas for future maintenance 
as needed. 
Terminal facilities. Consists of a public wharf on Rockhold 
Creek about 600 feet below the county bridge, open 
to all, together with a few private landing stages. No 
freight-handling devices are installed on any of the 
wharves which are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design was accomplished in 
connection with proposed maintenance dredging. 
7. HERRING CREEK, MD 
Location. Herring Creek in St. Marys County, MD., is 
a small tidal stream 134 miles in length which flows in 
a westerly direction and enters the north bank of the 
Potomac River 16 miles upstream of its mouth at 
Chesapeake Bay and 92 miles downstream from 
Washington, DC (See U.S. Coast and Geodetic Survey 
Chart No. 557.) 
Existing project. This provides for an entrance channel 
6 feet deep, 60 feet wide, and approximately 1,630 
feet long extending from deep water in the Potomac River 
to deep water within the creek, a turning basin of irregular 
shape 6 feet deep adjacent to the proposed public 
wharf, and riprap-stone jetties on the upstream and 
downstream sides of the entrance channel 770 and 650 
feet long, respectively. The plane of reference is mean low 
water. The tidal ranges are: Mean, 1.6 feet; irregular, 1.9 
feet; and extreme, approximately 7 feet. The project was 
modified in 1985 under Section 111 of the River and Harbor 
Act of 1968. The modification consists of constructing 
250 feet of beachfill, 2,187 linear feet of stone 
revetment and upgrading 350 linear feet of existing revetment 
along the Tall Timbers waterfront south of the 
project inlet to preclude shoreline erosion induced by the 
project jetties. 
Local cooperation: The Local Cooperation Agreement 
(LCA) includes the following provisions: 
1. The Local Sponsor will assume full responsibility 
for initial project costs in excess of the $1,000,000 
Federal Cost Limitation. 
2. Compliance with the Uniform Relocation Assistance 
and Real Property Acquisitions Policies Act of 1970. 
3. Provide without cost to the United States, when 
and as required all lands, easements, rights-of-way 
4-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
and soil-disposal areas necessary for the construction 
and subsequent maintenance of the project. 
4. Hold and save the United States free from damages 
to other property resulting from the improvement. 
Terminal facilities: There are a number of small 
wharves and landings within the creek, all privately 
owned. The facilities are considered adequate for present 
commerce. 
Operations and results during fiscal year: New work: 
A contract for construction of the project modification 
was awarded on May 15, 1986 to R&G Construction in 
the amount of $929,750. Construction is scheduled to be 
completed by June 1987. 
8. ISLAND CREEK, ST. GEORGES 
ISLAND, MD 
Location. Island Creek in St. Marys County, MD., is 
a tidal estuary three-fourths of a mile long, flowing in a 
southeasterly direction and entering the right bank of 
St. Marys River at its junction with the Potomac River, 
11 miles upstream of the Chesapeake Bay and 97 miles 
downstream from Washington, DC. It lies entirely within 
the lower half of St. Georges Island. (See U.S. Coast and 
Geodetic Survey Chart 557.) 
Existing project. Provides for a channel 5 feet deep, 
50 feet wide, and 2,000 feet long from the St. Marys River 
through the entrance to Island Creek and a turning basin 
5 feet deep, 200 feet wide, and 500 feet long within 
the creek. The plane of reference is mean low water. The 
tidal ranges are: Mean, 1.5 feet; irregular, 2.5 feet; and 
extreme, approximately 7 feet. Costs of Federal new work 
for the completed project were $6,230. 
Local cooperation. Fully complied with except local interests 
are to furnish spoil disposal areas for future maintenance 
as needed. 
Terminal facilities. On Island Creek there are five 
small private landings or stagings which are considered 
adequate for present commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design was accomplished in 
connection with proposed maintenance dredging. 
9. LITTLE WICOMICO RIVER, VA 
Location. A tidal estuary 6 miles long in Northumberland 
County, VA, flowing southeasterly to Potomac 
River, which it enters on the right bank one-half mile upstream 
of its mouth and about 108 miles downstream 
from Washington, DC. (See U.S. Coast and Geodetic Survey 
Chart 1223.) 
Existing project. A channel 8 feet deep, 150 feet wide, 
and 4,800 feet long, extending from deep water in the 
Potomac River to deep water in the Little Wicomico 
River; two stone jetties, extending to the 8-foot contour 
in Potomac River; and bulkhead walls from the inner ends 
thereof extending sufficiently into Little Wicomico River 
to stabilize the dredged inner channel. Plane of reference 
is mean low water. Tidal ranges in Potomac River at the 
entrance are: Mean 1.2 feet; irregular, 2.5 feet; and extreme, 
about 7 feet. Mean tidal range within the river is 
about 1 foot. Federal cost of new work for the completed 
project was $81,885, exclusive of $5,000 contributed 
by local interests. 
Local cooperation. Fully complied with. 
Terminal facilities. Two wharves open to the public 
and numerous small wharves and stagings for private 
use, an oyster shucking, and packing plant, and a marine 
railway and boat-building yard. Facilities are considered 
adequate for present commerce. 
Operations and results during fiscal year. Maintenance: 
The contract for rehabilitation of the twin stone 
jetties was completed on February 5, 1986. 
10. LOWER THOROFARE, DEAL 
ISLAND, MD 
Location. This is a tidal waterway, about 1.5 miles long 
and from one-eighth to one-half mile wide, branching off 
from Tangier Sound between Deal Island and Little Deal 
Island, MD. It is about 12 miles north of Crisfield Harbor, 
MD. (See U.S. Coast and Geodetic Survey Chart 78.) 
Previous project. The original project was dated March 
3, 1881. For further details see page 1790 of Annual 
Report for 1915. 
Existing project. Provides for a channel 60 feet wide 
and 7 feet deep from that depth in Tangier Sound to and 
including a mooring basin of the same depth, 100 feet 
wide and 300 feet long, in the marsh at the head of the 
cove at Wenona. The cost for new work for the completed 
project was $39,658, exclusive of amounts expended 
under previous projects. 
Local cooperation. Fully complied with except local interests 
are required to furnish spoil disposal areas for future 
maintenance as needed. 
Terminal facilities. There are three packing-house 
wharves and a small marine railway above the head of 
the project channel at Wenona. The facilities are privately 
owned but are open to the public for transaction of 
business with the owners. Present facilities are adequate 
for existing commerce. Sufficient areas are available for 
the construction of additional terminals when and as required. 
Operations and results during fiscal year. New Work: 
A contract was awarded on May 14, 1986 to construct 
a stone jetty and breakwater. 
Maintenance: A maintenance dredging contract was 
awarded on July 18, 1986 to remove approximately 
42,000 cubic yards of material. 
11. LOWES WHARF, MD 
Location. Lowes Wharf is in Ferry Cove, also known 
as Haddaway Cove, a small indentation on the eastern 
shore of Chesapeake Bay about 6 miles north of the Choptank 
River and 13 miles west of Easton, MD. (See U.S. 
Coast and Geodetic Survey Chart 1225.) 
Existing project. Provides for a channel 60 feet wide 
and 7 feet deep at mean low water from the 7-foot depth 
4-6

BALTIMORE, MD DISTRICT 
curve in Ferry Cove to and including a basin of the same 
depth, 200 feet wide and 300 feet long on the south side 
of Lowes Wharf. The mean tidal range is 1.4 feet; 
however, greater fluctuations frequently result from 
prolonged or high winds. The cost of new work for the 
completed project was $21,000. 
Local cooperation. Fully complied with except that local 
interests are to furnish spoil disposal areas for future 
maintenance as needed. 
Terminal facilities. Lowes Wharf, a solid-fill pier, with 
a seafood house located on the outer end, is the only terminal 
facility in Ferry Cove. The pier is public and is open 
to watermen at all times. 
Operations and results during fiscal year. Maintenance: 
Modification was issued for maintenance dredging 
completed on March 19, 1984. 
12. OCEAN CITY HARBOR AND 
INLET AND SINEPUXENT BAY, MD 
Location. Ocean City is on a barrier island between 
Sinepuxent Bay and Atlantic Ocean about 35 miles south 
of entrance to Delaware Bay. (See U.S. Coast and Geodetic 
Survey Chart 1220.) 
Existing project. This provides for an inlet channel 300 
feet wide and 16 feet deep from the 16-foot depth curve 
in Atlantic Ocean through the inlet to the channel in the 
Isle of Wight Bay, protected on the south side by a stone 
jetty with a top elevation of 8.8 feet above mean low 
water and a top width of 18 feet, and on the north side 
by a stone jetty with a top elevation of 9 feet above mean 
low water and a top width of generally 20 feet, thence 
generally 200 feet wide and 16 feet deep to the project 
harbor; a depth of 14 feet and 150 feet wide to the head 
of the harbor, a length of approximately 3,400 feet; a 
channel 6 feet deep and 150 feet wide in Sinepuxent Bay 
from the inlet to Green Point, and thence 100 feet wide 
in Chincoteague Bay; and for a channel 6 feet deep and 
125 feet wide from the inlet channel to a point opposite 
North Eighth Street in Ocean City, thence 75 feet wide 
into the Isle of Wight Bay. Depths in the inlet channel 
and harbor refer to project datum. Depths in the bay 
channels refer to mean low water. 
The elevation of mean low water in the bays above 
mean low water in the ocean at Ocean City varies from 
about 0.8 foot in the vicinity of the inlet to 1.7 feet at 
their heads. The mean range of ocean tide is 3.4 feet. The 
extreme range is from 3 feet below mean low water to 
about 3.5 feet above mean high water, a total of 9.9 feet. 
In the bays the mean range of tide varies from approximately 
2.5 feet at the inlet to 0.3 foot at their heads. 
Greater fluctuations are caused by prolonged high winds. 
Federal cost of new work for the completed project was 
$1,190,530, exclusive of $500,000 contributed by local interests 
and exclusive of $3,700,000 for rehabilitating the 
south jetty. 
Local cooperation. Fully complied with except local interests 
must furnish spoil disposal areas for future maintenance 
as needed. 
Terminal facilities. On bay side of Ocean City: two 
storage basins, for pleasure and small commercial craft, 
and numerous privately owned pile-and-timber piers and 
bulkhead wharves. At project harbor: a public landing 
about 1,000 feet long, several privately constructed bulkhead 
wharves open to the public for transaction of business 
with the owners, and a boat repair yard with a 
marine railway capable of handling boats up to about 150 
tons. All piers and wharves are accessible by highway. 
Port facilities have been expanded to include all available 
space in the Fish Harbor. 
Operations and results during fiscal year. New Work: 
Construction for the south jetty rehabilitation was completed 
in December 1985. 
Maintenance: Maintenance dredging of the Isle of 
Wight Bay was completed in March 1986. A total of 
70,000 cubic yards of material were removed. 
13. PARISH CREEK, MD 
Location. A small branch of West River, an estuary 
of Chesapeake Bay on Maryland western shore, at Shadyside, 
MD., about 7 miles south of mouth of Severn River. 
(See U.S. Coast and Geodetic Survey Chart No. 1225.) 
Existing project. Provides for a channel 8 feet deep and 
50 feet wide, widened at ends, from deep water in West 
River to head of south fork of Parish Creek, and an anchorage 
basin at junction of north fork having a depth 
of 6 feet and an area not exceeding 1V2 acres. Mean tidal 
range is about 2 feet. 
Cost of new work for completed project was $19,170 
exclusive of $1,000 contributed by local interests. Average 
annual maintenance cost for past 5 years was $6,000. 
Existing project was adopted by River and Harbor Act 
of August 30, 1935. (See H. Doc. 185, 72d Cong., 1st 
Sess., which contains latest published map.) 
Local cooperation. Local interests must contribute 
$1,000 toward cost of improvement, furnish suitable 
spoil-disposal areas, and provide a suitable water freight 
terminal at head of Parish Creek, open to all on equal 
terms. Total funds required to complete project were 
provided by Works Progress Administration. Local interests 
furnished disposal areas. Not fully complied with 
in that a public wharf has not been provided. 
Terminal facilities. There are numerous timber piers, 
one bulkhead wharf, two marine railways, 300 feet of concrete 
bulkhead and 350 feet of timber bulkhead on Parish 
Creek. Piers and bulkheads are privately owned, but 
open to the public for transaction of business with owners. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with proposed maintenance dredging. 
14. POTOMAC AND ANACOSTIA 
RIVERS, DC COLLECTION AND 
REMOVAL OF DRIFT 
Location. Project applies to the Potomac and 
Anacostia Rivers, Washington, DC and their tributaries. 
4-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Existing project. Collection and removal of drift from 
the waters of the Potomac and Anacostia Rivers and 
their tributaries in the Washington area from the head 
of tidewater to Mount Vernon, VA. Total length of 
project, considering both sides of the waterway, is about 
50 miles. 
Local cooperation. None required. 
Terminal facilities. See Section 23 of this text. 
Operations and results during fiscal year. Maintenance: 
Operations by hired labor consisted of collection 
and disposal of 379,080 cubic feet of driftwood, ranging 
from small blocks up to timbers of large dimensions. 
15. POTOMAC RIVER AQUATIC PLANT 
CONTROL, MD, VA, DC 
Location: The project is located in the Potomac River 
and its tributaries with the northern boundary at Chain 
Bridge in Washington, DC extending southward to the 
U.S. Route 301 Bridge (See U.S. Coast and Geodetic 
Chart 12289). 
Existing project: On July 2, 1986 the Chief of Engineers 
under the authority of Section 302 of the 1965 
River and Harbor Act, as amended, authorized the control 
of hydrilla and other nuisance plants using mechanical 
harvesting to clear a 60 foot wide, 6 foot deep 
connecting channel from open waters to eligible public 
use areas. 
Local cooperation: The Local Cooperation Agreement 
(LCA) was signed on June 6, 1986 between the Corps, 
MD, VA, DC and Metropolitan Washington Council of 
Governments. The LCA which must be reexecuted annually 
expires on September 30, 1986 includes the following 
provisions: 1. Local sponsors share 50 percent of 
the program cost; 2. Local sponsors provide lands, easements, 
and rights-of-way; 3. Metropolitan Washington 
Council of Governments is responsible for coordinating 
local interests. 
Terminal facilities: There are 75 marina activities between 
DC and the U.S. Route 50 Bridge providing approximately 
3,400 commercial and recreational boat slips 
and 50 boat ramps. 
Operations and results during fiscal year: On July 9, 
1986 a harvesting contract was awarded and approximately 
36 acres of nuisance aquatic plants were mechanically 
harvested. 
16. PREVENTION OF OBSTRUCTIONS & 
INJURIOUS DEPOSITS, 
BALTIMORE, MD 
Location. Project applies to tidal waters of the harbor 
of Baltimore and its adjacent and tributary waters and 
to all tidal waters of Chesapeake Bay and in Maryland. 
Existing project. Patrol and inspection throughout the 
project location to detect violations of sections 13 and 
15 of the River and Harbor Act of March 3, 1899 and 
to investigate obstructions to navigation pursuant to 
Federal regulations (33 CFR 209.109). 
Local cooperation. None required. 
Operations and results during fiscal year. Maintanance: 
Operations, by Supervisor of Harbor of Baltimore 
included inspections of approximately 75 Federal 
navigation channels within the project location to insure 
channels are not obstructed to general navigation by 
debris, sunken vessels/wrecks and/or fishing appurtenance. 
There were 3 detailed investigations of sunken 
vessels/wrecks resulting in no declarations of "Hazards 
to Navigation" issued. 
17. RHODES POINT TO TYLERTON, MD 
Location. Rhodes Point and Tylerton are two settlements 
about 1.5 miles apart on Smith Island, between 
Chesapeake Bay and Tangier Sound, about 60 miles 
north of Virginia Capes and about 110 miles south of Baltimore. 
(See U.S. Coast and Geodetic Survey Chart 1224.) 
Existing project. Channel 6 feet deep, 50 feet wide from 
that depth in Tyler Creek to and including an anchorage 
basin of the same depth 150 feet wide and 400 feet long 
at Tylerton; channel 6 feet deep and 50 feet wide from 
that depth in Shanks Creek to and including an anchorage 
basin of the same depth 100 feet wide and 400 
feet long at Rhodes Point; channel 6 feet deep and 50 feet 
wide from that depth in Big Thorofare River to Tylerton; 
channel 6 feet deep and 50 feet wide from Rhodes 
Point to Tylerton. Mean range of tide is 1.7 feet. On January 
22, 1982, the Chief of Engineers under authority of 
Section 107 of the 1960 River and Harbor Act, as amended, 
authorized a channel 6 feet deep and 50 feet wide a 
distance of about one mile from the anchorage basin at 
Rhodes Point through Sheep Pen Gut to deep water in 
the Chesapeake Bay. 
Local cooperation. Fully complied with for work authorized 
by the Chief of Engineers January 22, 1982. See 
section 19 of 1982 Annual Report for requirement details. 
Terminal facilities. There are numerous pile-and-timber 
wharves along waterfronts at Rhodes Point and Tylerton. 
Facilities are privately owned, but open to the public 
without charge when not in use by the owners, and 
are adequate for existing commerce. Sufficient space for 
construction of additional facilities is available, if required. 
Operations and results during fiscal year. Maintenance: 
A maintenance dredging contract was completed 
in January 1986. A total of 30,000 cubic yards of 
material were removed. 
18. ST. PATRICKS CREEK, MD 
Location. St. Patricks Creek in St. Marys County, MD 
is a small tidal stream 11/2 miles long which flows in a 
southeasterly direction and enters the west side of St. 
Clement Bay at its junction with the Potomac River. The 
creek is 33 miles upstream from the Chesapeake Bay and 
83 miles downstream from Washington, DC (See U. S. 
Coast and Geodetic Survey Chart No. 558). 
Existing project. Provides for an entrance channel 7 
feet deep, 60 feet wide, and approximately 2,450 feet long 
4-8

BALTIMORE, MD DISTRICT 
from deep water in St. Clement Bay to deep water within 
the creek. The plane of reference is mean low water. The 
tidal ranges are: mean, 1.9 feet; irregular, 2.5 feet; and 
extreme, approximately 7 feet. 
The cost to the Federal Government for new work for 
the completed project was $15,752, exclusive of $1,000 
contributed by local interests. The latest (1950) approved 
estimate for the annual cost of maintenance is $4,800. 
Local cooperation. The existing project was approved 
subject to the provisions that (a) local interests contribute 
$1,000 in cash toward the cost of new work; (b) hold 
and save the United States free from any damage resulting 
from construction and maintenance of the improvement; 
(c) furnish releases from damages to oyster 
grounds; (d) furnish free of cost to the United States 
suitable spoil-disposal areas for new work and subsequent 
maintenance, when and as required; and (e) agree 
to provide a suitable public wharf with access road open 
to all on equal terms. Items (a) through (d) have been fully 
complied with. Local interests have initiated action to 
complete item (e). 
Terminal facilities. There are 41 small wharves and 
stagings located in the creek. All are privately owned, 
but one is open to the public. There is also one marine 
railway in the creek. The terminal facilities are considered 
adequate for present commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with proposed maintenance dredging. 
19. SLAUGHTER CREEK, MD 
Location. This is a waterway about 8 miles long and 
tidal throughout connecting with Little Choptank River 
5 miles from its mouth. It lies in Dorchester County, MD, 
between Taylors Island and the mainland of the eastern 
shore of Chesapeake Bay. (See U.S. Coast and Geodetic 
Survey Chart 1225.) 
Existing project. This provides for dredging a channel 
7 feet deep and 100 feet wide at mean low water through 
the bar at the mouth, a distance of about one-third of a 
mile, the lower end of the section extending about 900 
feet into Little Choptank River. The mean range of tide 
is about 1.5 feet and the extreme tidal range is 2.9 feet. 
The cost for new work, made in 1911, is $4,140. 
Local cooperation. None required. 
Terminal facilities. There is one solid bulkhead wharf 
about 300 feet long, served by this improvement. It is 
privately owned but open to general public use, and is 
considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with proposed maintenance dredging. 
20. TRED AVON RIVER, MD 
Location. This stream, formerly called Treadhaven 
Creek, rises in Talbot County, MD, flows southerly and 
empties into Choptank River 10 miles above its mouth. 
It is about 10 miles long and is a tidal estuary with very 
little natural flow. Draining area is 36 square miles. (See 
U.S. Coast and Geodetic Survey Chart 78.) 
Previous project. For details see page 397 of Annual 
Report for 1951. 
Existing project. Provides for a channel 12 feet deep 
and 150 feet wide in Tred Avon River from that depth 
in river near Peach Blossom Creek to Easton Point, 
thence a channel of same depth and width and about 
1,400 feet long in the North Fork, thence a channel of 
same width and 8 feet deep and about 700 feet long with 
a turning basin of same depth at upper end. Project also 
provides for a turning basin in South Fork 12 feet deep 
and 250 feet wide and 600 feet long on east side of main 
channel at Easton Point. Section included in project is 
about 2 miles long, and its lower end is about 7.5 miles 
above mouth. Mean range of tide is about 2 feet. 
Local cooperation. Requirements are described in full 
on page 4-11 of Fiscal Year 1979 Annual Report. 
Terminal facilities. Five large terminals for receiving 
and distributing petroleum products, and a marina with 
stalls and ships, marine railway, a launching ramp, and 
a 6-ton travel-lift at Easton Point. These facilities are in 
good condition. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was completed in 
connection with proposed maintenance dredging. Work 
was deferred because locals were unable to provide the 
required contributed funds. 
21. TWITCH COVE AND BIG 
THOROFARE, MD 
Location. A tidal waterway about 4 miles long traversing 
Smith Island, MD, southeasterly from Chesapeake 
Bay on the west to Tangier Sound on the east. (See U.S. 
Coast and Geodetic Survey Chart 1224.) 
Existing project. A channel 7 feet deep at mean low 
water and 60 feet wide from Twitch Cove on Tangier 
Sound through Big Thorofare, thence through canal at 
Ewell, MD, thence through Levering Creek and Big 
Thorofare to vicinity of Swan Point, thence of same depth 
and 100 feet wide through offshore bar to deep water in 
Chesapeake Bay, with twin stone jetties at entrance, 
north jetty is about 2,080 feet long, and south jetty about 
1,800 feet long; and anchorage basin 7 feet deep, 100 feet 
wide, and 700 feet long connecting with west side of existing 
project channel at Ewell; extension of existing 
project channel in Levering Creek, 6 feet deep, 60 feet 
wide, and 1,000 feet long; and a channel 4 feet deep and 
25 feet wide around point between Big Thorofare and 
Tylers River. Mean range of tide is 1.7 feet, and extreme 
tidal range is 3 feet. Federal cost of new work Mr completed 
project was $193,175. 
Local cooperation. Fully complied with, except that local 
interests are to furnish spoil disposal areas for future 
maintenance as needed. 
Terminal facilities. Numerous privately owned pileand-
timber wharves and bulkheads at Ewell are open to 
4-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
the public for business transactions with the owners. A 
county wharf is also at west end of town. Five crab 
houses are on Levering Creek, and one oyster house on 
project waterway west of Town of Ewell. 
Operations and results during fiscal year. Maintenance: 
A maintenance dredging contract was completed 
in January 1986. A total of 10,000 cubic yards of 
material was removed. 
22. UPPER THOROFARE, DEAL 
ISLAND, MD 
Location. Natural waterway lying between Deal Island 
and mainland of Somerset County, MD., on eastern shore 
of Chesapeake Bay. (See U.S. Coast and Geodetic Survey 
Chart 1224.) 
Previous project. For details see page 277 of Annual 
Report for 1962. 
Existing project. Entrance channel from Tangier 
Sound 9 feet deep and 100 feet wide, thence of irregular 
width to and along south shore of Thorofare, protected 
by two stone breakwaters at entrance, north breakwater 
is about 410 feet long and south breakwater about 310 
feet long, with a turning basin at inner end 9 feet deep 
on south side of channel to within 50 feet of bulkhead 
along south shore, an anchorage area 6 feet deep and 150 
feet wide extending across waterway parallel to highway 
bridge to within 50 feet of bulkhead on south shore, and 
an anchorage area 650 feet long, 300 feet wide, and 9 feet 
deep on north side of channel between breakwater and 
6-foot anchorage. Mean range of tide is about 2 feet. Cost 
of new work for completed project was $62,116. 
Local cooperation. Fully complied with. 
Terminal facilities. A small packing-house wharf on 
shore of Tangier Sound south of project channel: two 
small packing houses along approach channel at which 
seafood is landed; and a public wharf at turning basin 
with a suitable road connecting it with the road system. 
Operations and results during fiscal year. Maintenance: 
A maintenance dredging contract was awarded 
for removal of approximately 88,000 cubic yards of 
material. 
23. WASHINGTON HARBOR, DC 
Location. Within District of Columbia at junction of 
Anacostia River with Potomac River which flows southeasterly 
108 miles to Chesapeake Bay. It is southerly 202 
miles by water from Baltimore, MD, and northerly 195 
miles from Norfolk, VA. (See U.S. Coast and Geodetic 
Survey Chart 12289.) 
Existing projects. A combination and extension of 
latest projects for Potomac River at Washington, DC, 
and Anacostia River, DC. The Washington Harbor 
project provides for a channel in the Potomac River from 
Giesboro Point to Key Bridge, a second channel from 
Giesboro Point to the end of Washington Channel, and 
a third channel from the mouth of the Anacostia River 
to the foot of 15th Street, SE, with turning basins opposite 
the Naval Weapons Plant (800 feet wide and 2,400 
feet long) and at the head of the Anacostia Channel (400 
feet square). Channel dimensions are 24 feet deep and 400 
feet wide except upstream from Anacostia Bridge where 
the width is reduced to 200 feet and from Giesboro Point 
to a point 3,000 feet downstream of Arlington Memorial 
Bridge and above Easby Point where channel dimensions 
are 20 feet deep and 200 feet wide. Channel lengths including 
turning basins are: Virginia Channel, 5,000 feet; 
Washington Channel, 10,000 feet; and Anacostia River, 
15,000 feet; and operation and maintenance of the inlet 
gates and lock and the outlet gates of the Tidal Basin 
constructed under a previous project to flush Washington 
Channel. Plane of reference is low-water datum which 
is 0.35 foot below mean low tide as observed from 1932 
to 1942. Tidal ranges are: mean, 2.9 feet; irregular, 4.5 
feet; and extreme, 10.7 feet. Federal cost of new work for 
the completed project was $162,006. 
Local cooperation. None required. 
Terminal facilities. There are four wharves generally 
of bulkhead type on Virginia Channel that are privately 
owned and not open to the public except by special 
arrangement. On Washington Channel there are four 
piers under jurisdiction of District of Columbia, two of 
which are open to the public and one open to the public 
by special arrangement. In Anacostia River there are four 
privately owned piers and eight governmental piers and 
slips. None of the piers are open to the public except by 
special arrangement. Terminal facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
The tidal basin gates were inspected and maintained 
by hired labor. 
24. WICOMICO RIVER, MD 
Location. Wicomico River has its source in northern 
part of Wicomico County, MD, and flows generally southwardly 
emptying into Monie Bay, a tributary of Tangier 
Sound on the east side of Chesapeake Bay about 85 
miles southeast of Baltimore. Webster Cove is site of improved 
small-boat harbor on southeast bank of Wicomico 
River about 3 miles above the mouth. (See U.S. Coast 
and Geodetic Survey Charts 567 and 1224.) 
Existing project. Channel 14 feet deep and 150 feet 
wide from Chesapeake Bay to Salisbury, section included 
in project is 37 miles long, including about 12 miles 
from mouth of river to Chesapeake Bay; 14 feet deep in 
channels and turning basins in north and south prongs 
with channel widths of 100 feet, and a channel 6 feet deep 
and 60 feet wide extending from 6-foot contour in 
Wicomico River to and including a basin in Webster Cove 
of same depth, 100 feet wide and 400 feet long; and extension 
of basin 200 feet long and 100 feet wide on each 
side. Plane of reference is mean low water. Mean range 
of tide is about 3 feet and extreme tidal range is 4.4 feet. 
Cost of new work for completed project was $421,609, 
exclusive of amounts expended on previous project. 
Local cooperation. Fully complied with, except that local 
interests are to furnish spoil disposal areas for future 
4-10

BALTIMORE, MD DISTRICT 
maintenance as needed and hold the United States free 
from such damages as may occur to public or leased oyster 
beds. 
Terminal facilities. Present waterfront at Salisbury 
consists of pile-and-timber bulkheads with earthfills. 
Some wharves have warehouses and factories with 
mechanical freight-handling facilities and rail sidings. All 
terminals are privately owned. A shipyard, with two marine 
railways with capacities of 1,200 and 500 tons, 
respectively, is on right bank of river below prongs. Areas 
for development of new terminals on north prong are 
limited. Areas for considerable expansion of terminal facilities 
are available on main river. There is a pileand-
timber wharf about 4 miles above mouth of river at 
Mount Vernon. A wharf of similar construction is at 
White Haven. There is a county wharf at head of basin 
in Webster Cove, a pile-and-timber pier at oyster house 
on southwest side of basin, a T-shaped pile-and-timber 
pier at cafe on southwest side of basin and several small 
timber piers on walkways that local interests constructed 
around the basin. Fueling facilities are available at the 
T-shaped pier. Sufficient areas are available for construction 
of additional facilities when required. 
Operations and results during fiscal year. Maintenance: 
Engineering and design was accomplished in 
connection with proposed maintenance dredging. 
25. RECONNAISSANCE AND CONDITION 
SURVEYS 
(See Table 4-H at end of chapter.) 
26. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645 (preauthorization). 
Fiscal year costs were $1,431 for Hull Creek, VA; and 
$7,600 for Shallow Creek, MD. 
Beach Erosion Control 
27. COLONIAL BEACH, VA 
Location. Colonial Beach, Westmoreland County, VA, 
is located on the right bank of the Potomac River 40 miles 
upstream from its mouth at Chesapeake Bay and 69 
miles downstream from Washington, DC. (See U.S. Coast 
and Geodetic Survey Chart No. 558.) 
Existing project. On May 29, 1980, the Chief of Engineers 
under authority of Section 103 of the 1960 River 
and Harbor Act, as amended, authorized construction of 
the following work: Extending and widening the existing 
Central Beach area downstream from Hawthorne 
Street southward to provide an additional beach area of 
about 107,200 square feet, stablizing with vegetation 
about 200 feet of the bank behind the beachfill and constructing 
four segments of offshore breakwater with estimated 
lengths of 200 feet each, to stablize the beachfill 
area; and extending and widening the existing beach at 
Castlewood Park to provide an additional beach area of 
about 59,300 square feet; constructing three segments 
of offshore breakwater with estimated lengths of 200 feet 
each for two of the segments and 300 feet for the third 
segment; removing debris in the beachfill area; and constructing 
a 100-foot long terminal groin at the southern 
end of the Castlewood Park beachfill. The estimated cost 
of this work is $1,910,977 of which $1,000,000 is Federal 
cost and $910,977 is required local cash contribution. The 
$1,910,977 includes $992,000 for periodic beach nourishment 
as needed, after FY 1983. 
Local cooperation. Among other requirements, local interests 
must provide all lands, easements, and rights-ofway 
and relocations required for construction including 
periodic nourishment and provide a cash contribution 
equal to 50 percent of the final project construction cost 
(excluding lands and relocations). 
Operations and results during fiscal year. New Work: 
Surveys were accomplished in FY 1986 at a total cost 
of $1,530. 
28. BEACH EROSION 
CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Beach Erosion Control pursuant to Sec. 103 of Public 
Law 727, as amended (preauthorization). 
Fiscal year costs were $55,874 for town of North Beach, 
MD. 
Flood Control 
29. BLOOMINGTON LAKE, MD & WV 
Location. Project is located on the North Branch 
Potomac River on the state line between Garrett County, 
MD, and Mineral County, WV. The damsite is located 
approximately 7.9 miles upstream from the confluence 
with Savage River at Bloomington, MD. It is also about 
5 air miles southwest of the tritowns of Luke and 
Westernport, MD, and Piedmont, WV. (See Geological 
Survey quadrangle sheets, "Kitzmiller" and "Westernport," 
MD.) 
Existing project. The improvement consists of a rolled 
earth and rock fill dam with an impervious core and an 
800-foot long dike on the left bank. Top of dam is 296 
feet above streambed with a total length of 2,130 feet. 
When filled to spillway crest, the reservoir will extend 
about 6.6 miles upstream and inundate 965 acres. Flood 
control storage of 36,200 acre-feet is provided. Storage 
available for low flow augmentation for water supply and 
water quality improvement is 92,000 acre-feet. The reservoir 
controls a drainage area of 263 square miles. Recreation 
facilities are provided for picnicking, camping and 
boating. Estimated cost (October 1986) of new work is 
$176,270,300 of which $58,521,700 is required non- 
Federal reimbursement. 
4-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Local cooperation. See page 4-15 of the 1977 Annual 
Report for requirements. A water supply contract between 
the Federal Government and the Washington 
Suburban Sanitary Commission in concert with the Fairfax 
County Water Authority, VA, and the District of 
Columbia has been executed for repayment of all water 
supply costs. The first of 50 annual payments began in 
July 1981. Federally approved water quality standards 
put into effect by Maryland, Virginia, West Virginia, and 
the District of Columbia are considered satisfactory assurances 
of intent to control pollution. Satisfactory assurances 
have been received from Maryland, West 
Virginia, and Virginia that they will protect downstream 
channels from encroachment that would adversely affect 
operation of the project. 
Operations and results during fiscal year. New 
Work: The project became operational for water supply, 
flood control, and for water quality control in July 1981. 
Miscellaneous costs for the fiscal year were $26,678. 
Maintenance: Normal operation and maintenance of 
the project continued. 
30. CUMBERLAND, MD, AND 
RIDGELEY, WV 
Location. On North Branch of Potomac River, 21 miles 
upstream from its junction with the South Branch of the 
Potomac River and 197 miles upstream from Washington, 
DC. (See Geological Survey Quadrangles, Frostburg 
and Flintstone, MD, WV, and PA.) 
Existing project. Channel improvements of North 
Branch of Potomac River from the Western Maryland 
Railway bridge in South Cumberland upstream to the 
mouth of Wills Creek, with levees and fill along the left 
bank and levees along the right bank from downstream 
corporate limits of Ridgeley, WV, to a point about 150 
feet above Johnson Street Bridge; channel improvements 
along Wills Creek from its mouth upstream to a point 
in the Narrows about 500 feet upstream from the highway 
bridge on U.S. Highway 40; levee and flood wall in 
West Cumberland, MD, on the left bank of the North 
Branch of the Potomac River from the mouth of Wills 
Creek upstream to Kelly Boulevard; levee and flood wall 
in Ridgeley, WV, on the right bank of the North Branch 
of the Potomac River from Carpenter Avenue upstream 
to Patapsco Street near the upstream corporate limits 
of Ridgeley, WV; interior drainage facilities in Cumberland 
and West Cumberland, MD, and Ridgeley, WV; 
removal of the Chesapeake and Ohio Canal dam and construction 
of a new industrial dam on the North Branch 
of the Potomac River immediately above mouth of Wills 
Creek; and alteration and reconstruction of highway and 
railroad bridges. Federal costs of new work for the completed 
project were $15,633,970, which includes $49,998 
emergency relief funds and is exclusive of $197,513 public 
works acceleration funds. Estimated cost to local interests 
is $2,900,000 of which $1,402,001 is contributed 
funds and $1,497,999 is for lands and damages. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Removal of gravel deposits, grass cutting of 
areas channelward of levees, and removal of brush and 
debris from channel were accomplished as required in 
channel area. 
31. LACKAWANNA RIVER BASIN, PA 
Flood Control Act of 1962 authorized construction of 
Aylesworth Creek Lake, Fall Brook Lake, and local protection 
works on Lackawanna River at Scranton, PA, 
substantially as recommended by the Chief of Engineers 
(S. Doc. 141, 87th Cong., 2d Sess.). The Basin includes 
an area of 346 square miles in northeastern Pennsylvania. 
31A. AYLESWORTH CREEK LAKE, PA 
Location. Project is located in Lackawanna County on 
Aylesworth Creek about one mile above its confluence 
with the Lackawanna River, near the community of East 
Jermyn, PA. 
Existing project. Provides for an earthfill dam with a 
maximum height of 90 feet above streambed and a top 
length of 1,200 feet. The spillway located adjacent to the 
left abutment is an open cut channel 80 feet wide with 
a concrete sill. The outlet works consist of a 3-foot diameter 
uncontrolled conduit. Project controls a drainage 
area of 6.2 square miles and provides flood control 
storage of 1,700 acre-feet equivalent to 5.1 inches of 
runoff from the drainage areas. The lake will extend 
about 4,600 feet and inundate 87 acres when filled to spillway 
crest. Recreation facilities constructed by local interest 
include a bathing beach, bathhouse, and picnic 
area. Federal cost of new work was $2,268,200 of which 
$2,153,559 was for construction and $114,641 for lands 
and damages. In addition $52,200 Federal and $52,200 
non-Federal funds were expended for construction of 
bathhouse facilities under the recreation facilities for 
completed projects program. 
Local cooperation. None required. The Aylesworth 
Creek Reservoir Park Authority, representing the 
Boroughs of Archbald and Jermyn, operate and maintain 
limited day use facilities including a small beach. In 
September 1978 a cost-sharing agreement for construction 
of bathhouse facilities was signed. The cost for the 
facilities which were completed in July 1979 was $104,400 
of which $52,200 was Federal and $52,200 was non- 
Federal. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
32. RAYSTOWN LAKE, RAYSTOWN 
BRANCH, JUNIATA RIVER, PA 
Location. Damsite is on Raystown Branch, about 5.5 
miles upstream from its confluence with Juniata River. 
Project is about 10 miles south of Huntingdon, PA. (See 
Geological Survey Quadrangle sheets, Huntingdon, Mt. 
Union, Broad Top and Everett, PA.) 
4-12

BALTIMORE, MD DISTRICT 
Existing project. The rock and earthfill dam rises 225 
feet above streambed with a gated concrete spillway and 
auxiliary spillway in the right abutment. The reservoir 
has a storage capacity of 762,000 acre-feet, of which 
248,000 acre-feet are for flood control, 476,000 acre-feet 
for recreation and water quality control, and the balance 
for sediment reserve. At full flood control pool elevation, 
the reservoir would inundate 10,800 acres and extend 34 
miles upstream. Recreation facilities are provided for 
boating, fishing, camping, swimming, hunting, and picnicking. 
Federal cost for new work was $77,408,700 of 
which $46,120,931 was for construction and $31,287,769 
was for lands and damages including relocations. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
33. SOUTHERN NEW YORK FLOOD 
CONTROL PROJECTS 
Authorized plan provides for construction of reservoirs 
and related flood control works for protection of towns 
in New York and Pennsylvania. The improvements are 
located in the upper watershed of the Susquehanna River 
to and including the Chemung River. 
33A. ADDISON, NY 
Location. At confluence of Tuscaroroa Creek and 
Canisteo River in the City of Addison, NY. (See Geological 
Survey map for Addison, NY.) 
Existing project. Provides for construction of about 
3,100 feet of earth levee and 700 feet of concrete flood 
wall on the right bank of the Canisteo River, extending 
from high ground on Steuben Street near the Baltimore 
& Ohio Railroad to the mouth of Tuscarora Creek; 
removal of existing dam, mill, and raceway from the 
channel; construction of about 2,200 feet of earth levee 
on the left bank of Tuscarora Creek, extending from Tuscarora 
Street to Canisteo River; construction of 4,600 feet 
of earth levee on the right bank of Tuscarora Creek, extending 
from high ground at the southwest edge of the 
village to high ground at the southeast edge of the village; 
and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
33B. ALMOND LAKE, NY 
Location. Dam is located two miles upstream from Hornell, 
NY, on Canacadea Creek, a tributary of the Canisteo 
River. (See Geological Survey map for Hornell, NY.) 
Existing project. The dam is an earthfill structure, 
1,260 feet long rising 90 feet above the streambed, with 
a concrete spillway and a gated outlet conduit in the left 
abutment. The outlet works consist of three 5-foot by 
10-foot service gates and three emergency gates of the 
same size. The reservoir has a storage capacity of 14,640 
acre-feet at spillway crest. The project controls a draining 
area of 56 square miles, 36 percent of the watershed 
of the Canisteo River upstream from Hornell, NY. Recreation 
facilities include a boat-launching ramp and dock, 
bathing beach, picnic area, and tent and trailer camping 
area. 
Local cooperation. None required. Local interests have 
developed recreational facilities at the lake in conjunction 
with the Federal Government. These facilities are 
operated and maintained by the Steuben County Board 
of Supervisors. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of project 
continued. 
33C. ARKPORT DAM, NY 
Location. Dam is located five miles upstream from Hornell, 
NY, on the Canisteo River, a tributary of the 
Chemung River which flows into the Susquehanna River. 
(See Geological Survey map for Arkport, NY.) 
Existing project. The dam is an earthfill structure, 
1,200 feet long, exclusive of spillway, rises 113 feet above 
the streambed, with a concrete spillway and an ungated 
outlet in the right abutment. The outlet structure consists 
of an 8-foot diameter reinforced concrete lined conduit, 
660 feet long. A cast iron nozzle is placed in the 
lower end of the conduit, reducing the outlet size to 4 feet 
4 inches. The reservoir has a storage capacity of 7,950 
acre-feet at spillway crest. The project controls a 
drainage area of 31 square miles, 20 percent of the 
watershed of the Canisteo River upstream from Hornell. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
33D. AVOCA, NY 
Location. On the Cohocton River at the Village of Avoca, 
NY, about 30 miles upstream from the confluence of 
the Cohocton and Chemung Rivers. (See Geological Survey 
map for Avoca, NY.) 
Existing project. Provides for improvement and 
realignment of about 8,300 feet of Cohocton River channel, 
extending from above the Erie Railroad to below the 
junction of Main Street and U.S. Highway 15; construction 
of about 8,500 feet of earth levee on left bank of the 
Cohocton River, extending from high ground above Alexander 
Avenue to about 1,300 feet below the junction of 
Main Street and U.S. Highway 15; and 4,500 feet of earth 
levee on the right bank of Salmon Creek, extending from 
high ground above Alexander Avenue to the Erie Railroad; 
a new highway bridge for U.S. Highway 15 over 
Cohocton River, raising of the Erie Railroad bridge 4 feet; 
and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
4-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
33E. BINGHAMTON, NY 
Location. At the confluence of the Chenango and 
Susquehanna Rivers in the City of Binghamton, NY. (See 
Geological Survey map for Binghamton, NY.) 
Existing project. Provides for construction of earth 
levees, concrete flood walls, and appurtenant drainage 
structures, consisting of about 850 feet of channel excavation 
and about 1,375 feet of earth levee along Phelps 
Creek, Town of Port Dickinson; new concrete wall on the 
right bank of the Chenango River, extending downstream 
from high ground near the city limits to an existing flood 
wall below DeForest Street, a distance of about 520 feet; 
about 150 feet of concrete wall just below Cutler Dam; 
about 180 feet of concrete wall at the pumphouse near 
McDonald Avenue; raising existing earth levees on the 
right bank of Chenango River, extending from Cutler 
Dam downstream for about 1,220 feet; about 2,915 feet 
of earth levee on the left bank of Chenango River north 
of the city limits in the Village of Port Dickinson, extending 
from Church Street to high ground just north of the 
city line; about 3,900 feet of earth levee on the left bank 
of Chenango River, extending from DeForest Street to 
Cutler Dam; new concrete flood walls and riverbank 
revetment for about 5,570 feet extending on the left bank 
of Chenango River from Cutler Dam to the junction with 
the Susquehanna River; about 540 feet of new concrete 
flood wall and raising about 1,085 feet of concrete flood 
wall on the right bank of the Susquehanna River, extending 
from the Delaware, Lackawanna & Western Railroad 
downstream to Tompkins Street Bridge; about 1,940 feet 
of earth levee; about 1,940 feet of concrete flood wall and 
capping about 125 feet of concrete flood wall, on the right 
bank of the Susquehanna River from Stuyvesent Street 
to mouth of Chenango River; about 8,380 feet of earth 
levee, about 2,180 feet of new concrete flood wall and raising 
about 125 feet of existing flood wall on the left bank 
of the Susquehanna River extending from Pierce Creek 
to high ground at State Highway 17; a debris dam and 
flume between Corbett and Hotchkiss Streets and a concrete 
pressure conduit, 1,060 feet long to carry flow of 
Park Creek from Vestal Avenue to the Susquehanna 
River; about 665 feet of levee extending from the Erie 
Railroad to high ground along the right bank of Chamberlain 
Creek near the mouth; closure structures at Erie 
Railroad and at Court Street; a weir, a drop structure, 
and about 1,800 feet of earth levee, about 2,235 feet of 
channel excavation, about 645 feet of channel paving and 
raising, about 470 feet of existing concrete flood wall, and 
about 200 feet of new concrete flood wall for improvement 
of Pierce Creek from its mouth to about 1,000 feet 
above Conklin Avenue; and appurtenant drainage structures. 
Improvement, supplemented by authorized flood 
control dams above the area, will provide protection for 
the City of Binghamton against a flood discharge about 
20 percent greater than the maximum flood of record, 
which occurred in July 1935 on the Chenango River and 
in March 1936 on the Susquehanna River. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New Work: 
Plans and specifications for correction of the underseepage 
at the First Ward Area, Front Street Levee were 
completed and the locals are acquiring the lands, easements 
and rights-of-way. 
Maintenance: Normal operation and maintenance of 
the project continued. 
33F. CANISTEO, NY 
Location. On Purdy and Bennetts Creeks in the Town 
of Canisteo, NY, situated along the south side of the 
Canisteo River, at the confluence of Bennetts Creek and 
the Canisteo River. (See Geological Survey map for 
Canisteo, NY.) 
Existing project. Provides for construction of about 
8,000 feet of earth levees on the right bank of the 
Canisteo River, extending from high ground 1,570 feet 
west of State Highway Route 21 above the Town to a 
point at the intersection of Ordway Lane and East Main 
Street; about 7,400 feet of earth levee on the left bank 
of Purdy and Bennetts Creeks, extending from the Main 
Street Bridge to high ground above Greenwood Street; 
1,000 feet of earth levee on the right bank of Bennetts 
Creek extending upstream from the Main Street Bridge; 
a concrete check dam with wing levees from Greenwood 
Street; a new highway bridge at Greenwood Street; alterations 
to existing timber check dams in Bennetts 
Creek; channel excavation in Bennetts and Purdy Creeks; 
and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
33G. CORNING, NY 
Location. On the Chemung River in the City of Corning, 
NY, about 44 miles upstream from the confluence 
of Chemung River and North Branch of Susquehanna 
River. (See Geological Survey map for Corning, NY.) 
Existing project. Flood protection for this community 
was originally authorized by the Flood Control Act of 
1936. Plan of improvement provides for construction of 
a pumping station, earth levees, and concrete flood walls, 
consisting of: about 4,300 feet of earth levee, enlargement 
of about 8,610 feet of existing earth levee and about 3,100 
feet of concrete flood wall on the right bank of the 
Chemung River, extending from the Erie Railroad Bridge 
to high ground at Park Avenue below the City; about 200 
feet of concrete flood walls; about 2,500 feet of earth levees 
and enlargement of about 11,500 feet of existing 
earth levee on the left bank of the Chemung and Cohocton 
Rivers, extending from the Erie Railroad Bridge over 
Cohocton River to the mouth of Post Creek; about 2,500 
feet of earth levee and enlargement of about 4,700 feet 
of existing earth levee on the right bank of Post Creek 
from its mouth to Watkins Street; realignment of about 
3,000 feet of channel, about 8,800 feet of earth levee, 
about 3,000 feet of channel excavation, a pressure con- 
4-14

BALTIMORE, MD DISTRICT 
duit about 400 feet long, a drop structure and a weir for 
improvement of Cutler Creek, extending from its mouth 
to high ground at Deckertown Road and Hornby Road; 
and appurtenant drainage structures. Flood protection 
on Monkey Run was authorized by the Flood Control Act 
of 1950. Plan of improvement provides for construction 
of 2,010 feet of open flume, 2,320 feet of pressure conduit 
storm sewers, and appurtenant facilities between the 
existing improved channel above Sixth Street and the 
Chemung River at a point immediately east of Pine 
Street East. Modified improvement will provide protection 
for the City of Corning against a flood discharge in 
Chemung River approximately equal to the maximum 
flood of record, which occurred in May 1945, and on tributary 
streams against floods of greater magnitude than 
known to date. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operaton and maintenance of the project 
continued. 
33H. EAST SIDNEY LAKE, NY 
Location. Dam is located near East Sidney, NY, on the 
Ouleout Creek, about five miles above the confluence of 
the creek with the Susquehanna River. (See Geological 
Survey map for Franklin, NY.) 
Existing project. The dam is an earthfill and concrete 
structure, 2,010 feet long, including spillway, rises 130 
feet above the streambed and consists of a concrete 
gravity-type section with a compacted earth-dike section 
at the right abutment. The outlet works consist of five 
rectangular conduits each 3.5 feet by 5.85 feet and 105 
feet long. The reservoir has a storage capacity of 33,500 
acre-feet at spillway crest. The project controls a 
drainage area of 102 square miles which is 93 percent of 
the Ouleout Creek drainage area, and 5 percent of the 
watershed of the Susquehanna River upstream from 
Binghamton, NY, exclusive of the separately controlled 
Chenango River. Recreation facilities include a bathing 
beach, picnic and camping areas, and boat-launching and 
docking facilities. 
Local cooperation. None required. The Town of Sidney, 
NY, cooperated in the development of recreation facilities 
and operates and maintains all the facilities with the 
exception of the recreational pool, which is the responsibility 
of the Federal Government. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
33I. ELMIRA, NY 
Location. On the Chemung River in the City of Elmira, 
NY, about 27 miles upstream from the confluence of the 
Chemung River and North Branch of Susquehanna 
River. (See Geological Survey map for Elmira, NY.) 
Existing project. Provides for about 17,700 feet of 
earth levees, and about 4,100 feet of concrete flood wall 
on the right bank of the Chemung River, extending from 
South Hoffman Street to a point below the city near the 
upper end of Big Island; about 12,100 feet of earth levee 
and about 6,300 feet of concrete wall on the left bank of 
the Chemung River extending from Durland Avenue to 
the Delaware, Lackawanna & Western Railroad at the 
mouth of Newton Creek; about 10,000 feet of earth levee 
on right bank of Newton Creek, extending from about 
the intersection of Delaware, Lackawanna & Western 
Railroad and East Church Street to high ground near intersection 
of Sullivan and Warren Streets; about 4,300 
feet of earth levee on the right bank of Divan Creek; 
about 2,000 feet of concrete conduit enclosing Hoffman 
Brook from West Second Street to the Chemung River; 
clearing islands and riverbanks of trees and brush for 
about 3.5 miles in the Chemung River; about 14,300 feet 
of earth levee on the left bank of Seely Creek, extending 
from the Erie Railroad to high ground approximately 
1,000 feet northwest of the intersection of South Broadway 
and Pennsylvania Avenue; a pumping plant for disposal 
of interior drainage; an interceptor sewer about 
6,000 feet long varying in size from 48 to 96 inches in 
diameter; and appurtenant structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
33J. HORNELL, NY 
Location. On the Canisteo River in the City of Hornell, 
NY, about 42 miles upstream from the confluence of the 
Canisteo and Tioga Rivers. (See Geological Survey map 
for Canisteo, NY.) 
Existing project. Provides for channel realignment and 
earth levees, concrete flood walls, and check dams consisting 
of: realignment of about 4,600 feet of the 
Canisteo River channel, and about 5,800 feet of earth 
levee on its right bank, extending from Seneca Street upstream 
to the junction of the Pittsburgh, Shawmut & 
Northern Railroad and the Erie Railroad; about 4,500 feet 
of earth levee, extending on both sides of Seneca Street 
from the Canisteo River to Wrightman Avenue and the 
junction of Cleveland Avenue and Bethesda Drive; about 
7,200 feet of earth levee, about 2,500 feet of concrete flood 
wall, and raising about 1,500 feet of existing concrete 
flood wall, on the right bank of the Canisteo River, and 
about 12,000 feet of channel improvement, extending 
from Seneca Street to the Erie Railroad; about 2,500 feet 
of earth levee, about 2,100 feet of concrete flood wall on 
the left bank of the Canisteo River extending from a point 
opposite Walnut Street to the Erie Railroad; a ring-earth 
levee about 2,800 feet long around the sewage-disposal 
plant on the left bank of the Canisteo River; about 4,500 
feet of realignment and improvement of the Canisteo 
River Channel with about 4,500 feet of earth levee on its 
right bank extending from Cedar Street downstream to 
about 1,400 feet above East Avenue; about 2,400 feet of 
channel paving, 1,400 feet of earth levee, raising about 
1,900 feet of concrete flood wall, and construction of one 
check dam on Canacadea Creek; about 1,600 feet of channel 
paving and construction of three check dams on 
4-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Chauncey Run with about 300 feet of new wall and about 
300 feet of capping; a weir, a check dam, 3,030 feet of 
channel paving, 4,800 feet of flood walls and levees, and 
related work on existing walls, on Crosby Creek; removal 
of 6 bridges, erection of 4 bridges, miscellaneous bridge 
structures, and 3 drop structures; and appurtenant 
drainage structures and small stream control works. Improvement, 
supplemented by Arkport and Almond 
Reservoirs above the area, provides protection for the 
City of Hornell against a flood discharge approximately 
double the maximum flood of record, which occurred in 
July 1935. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
33K. LISLE, NY 
Location. On the Tioughnioga River in the Village of 
Lisle, NY, about 12 miles upstream from the confluence 
of the Tioughnioga and Chenango Rivers. (See Geological 
Survey map for Lisle, NY.) 
Existing project. Provides for channel realignment and 
construction of earth levees and concrete flood walls, consisting 
of: relocation of about 3,000 feet of Dudley Creek 
Channel, extending from 1,200 feet west of the intersection 
of Cortland and Main Streets to the confluence with 
Tioughnioga River, realignment of some 5,700 feet of 
Tioughnioga River Channel east of the Village; about 
4,150 feet of earth levee and 970 feet of concrete wall on 
the right bank of Dudley Creek and Tioughnioga River; 
realignment of some 5,700 feet of Tioughnioga Street to 
the railroad crossing on River Street; raising about 1,860 
feet of the Delaware, Lackawanna & Western single track 
railroad over the levee; relocation of about 1,600 feet of 
Cortland Street; a new bridge over relocated Dudley 
Creek; and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
33L. OXFORD, NY 
Location. On the Chenango River in the Village of Oxford, 
NY, about 40 miles upstream from the confluence 
of the Chenango and Susquehanna Rivers. (See Geological 
Survey map for Oxford, NY.) 
Existing project. Provides for earth levees and clearing 
of Chenango River Channel, consisting of about 2,100 
feet of earth levees on the left bank of the Chenango 
River, extending from high ground near Cemetery Drive 
and running mostly along the railroad to high ground 
near Main Street; removal of dam and island below Main 
Street; raising the Delaware, Lackawanna & Western 
Railroad over the levee; and appurtenant closure and 
drainage structures. Improvement provides protection 
for the Village of Oxford on the left bank against a flood 
discharge substantially larger than the maximum flood 
of record, which occurred in July 1935. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
33M. WHITNEY POINT LAKE, NY 
Location. Dam is located near Whitney Point, NY, on 
the Otselic River about 0.7 mile upstream from its confluence 
with Tioughnioga River. (See Geological Survey 
map for Whitney Point and Willet, NY.) 
Existing project. The dam is an earthfill structure, 
4,900 feet long, exclusive of a spillway, rises 95 feet above 
the streambed, with a concrete spillway and gated outlet 
in the left abutment. The outlet works consist of three 
5-foot by 10-foot gates and one emergency gate of the 
same size. The reservoir has a storage capacity of 86,440 
acre-feet at spillway crest. The project controls a 
drainage area of 255 square miles, the entire watershed 
of Otselic River, or 16 percent of the Chenango River 
watershed upstream from Binghamton, NY. Recreation 
facilities, constructed in cooperation with local interests, 
provide for swimming, picnicking, camping, boating, fishing, 
and hunting. 
Local cooperation. None required. Local interests operate 
and maintain all of the recreation facilities. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
33N. WHITNEY POINT VILLAGE, NY 
Location. On the Tioughnioga River at the confluence 
of the Tioughnioga and Otselic Rivers, tributaries of the 
Susquehanna River. (See Geological Survey map for 
Whitney Point, NY.) 
Existing project. Provides for channel realignment and 
earth levees, consisting of realignment of about 1,800 feet 
of Tioughnioga River Channel, above the confluence with 
Otselic River; about 7,100 feet of earth levee along the 
right bank of the Tioughnioga River, extending from high 
ground on Main Street above the village to Collins Street 
just below the Village; and appurtenant drainage 
structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
34. STILLWATER LAKE 
LACKAWANNA RIVER, PA 
Location. Dam is on the Lackawanna River, 39 miles 
from the mouth of the stream and about 4 miles upstream 
from Forest City, Susquehanna County, PA (See Geological 
Survey Quadrangle sheet, Honesdale, PA.) 
4-16

BALTIMORE, MD DISTRICT 
Existing project. Dam is earthfill type, rising 77 feet 
above the streambed, with a controlled outlet conduit and 
side channel spillway in the left abutment. Reservoir capacity 
is 12,000 acre-feet, of which 11,600 acre-feet is 
flood control storage and the remainder utilized to maintain 
the existing water supply reservoir for Forest City, 
PA, at this site. Reservoir area is 422 acres,and the pool 
extends about 2.1 miles upstream. Reservoir controls 52 
percent of the watershed above Carbondale, 26 percent 
above Olyphant, and 17 percent above Scranton. Federal 
cost of new work, completed in 1965, was $5,725,700 of 
which $4,500,500 was for construction and $1,225,200 
was for lands and damages. 
Local Cooperation. None required. Section 2, Flood 
Control Act of June 28, 1938, applies. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of project 
continued. 
35. SUSQUEHANNA RIVER FLOOD 
CONTROL PROJECTS, NY AND PA 
Plan of improvement authorized by the 1958 Flood 
Control Act provides for construction of Cowanesque 
Lake, PA, Tioga-Hammond Lakes, PA, local protection 
works at Elkland, PA, and Nichols, NY, and channel improvements 
at Cortland, NY. This project plan supplemented 
the comprehensive flood control program for 
Southern New York and Northern Pennsylvania which 
included the Southern New York flood control project 
and Stillwater, Genegantslet, and South Plymouth 
Reservoirs. 
35A. COWANESQUE LAKE, PA 
Location. Dam is on the Cowanesque River about 2.2 
miles above its confluence with Tioga River at Lawrenceville, 
PA. (See Geological Survey map for Tioga, PA.) 
Existing project. The project constructed under the 
Flood Control Act of 1958 provides for an earthfill dam 
3,100 feet long and rising 151 feet above the streambed, 
an uncontrolled spillway in the right abutment, a gated 
conduit in the Valley floor, and flood control storage is 
82,000 acre-feet. Relocation of the Town of Nelson to a 
new townsite was authorized by Section 121 of the Water 
Resources Development Act of 1976. The Federal cost 
of this new work was $106,030,700 of which $61,743,600 
was for construction and $44,287,100 was for lands and 
damages and relocations (which includes $5,755,000 for 
relocation of the Town of Nelson). Within the discretionary 
authority of the Chief of Engineers the project was 
modified in March 1983 in accordance with the Water 
Supply Act of 1958, as amended, and the Flood Control 
Act of 1944, as amended. The modification provides for 
reallocating 25,600 acre-feet of present flood control 
storage for water supply storage by raising the permanent 
pool from elevation 1,045 to 1,080 mean sea level. 
Other features include modifying the existing intake 
tower and two access ramps, stabilizing the reservoir 
slope near the relocated Town of Nelson, replacing existing 
day-use recreation facilities, and expanding both 
day-and overnight-use recreation facilities to accommodate 
an expected increase in annual visitation due to the 
larger pool. Estimated cost (October 1986) of the modification 
is $53,114,000 of which $970,000 is Federal (for 
expanded recreation facilities) and $52,144,000 is non- 
Federal (which includes $39,414,000 for reimbursement 
of the cost of existing flood control storage reallocated 
to water supply storage, $11,760,000 cash contribution 
for the water supply modification, and $970,000 cash contribution 
for expanded recreation facilities). 
Local cooperation. The Water Resources Development 
Act of 1976, which authorized relocation of the Town of 
Nelson, provides that before the Secretary of the Army 
acquires any real estate property for the new townsite, 
appropriate non-Federal interests shall furnish binding 
contractual commitments that all lots in the new townsite 
will be either occupied when available, replacements 
for open space and vacant lots in the existing town, or 
will be purchased by non-Federal interests at the fair market 
value. The required contractual agreement for local 
cooperation was executed with Nelson Township on August 
25, 1977. The March 1983 project modification (discussed 
above) requires non-Federal interests repay 100 
percent of the investment cost of project modifications 
allocated to water supply, to terrestial wildlife habitat 
mitigation, and to in-kind replacement recreation, plus 
the allocated share of the project's original cost (escalated 
to current price levels). Additionally, they are required 
to pay annual costs of operation, maintenance, and major 
replacements allocated to water supply and to provide 
50 percent of the cost of expanded recreation facilities, 
as well as, all operation, maintenance, and replacement 
costs for the expanded facilities. Water supply and recreation 
contracts were executed by the Assistant Secretary 
of the Army (Civil Works) and the Susquehanna River 
Basin Commission on June 30, 1986. 
Operation and results during fiscal year. New Work: 
Engineering and design continued on the project modification. 
Costs for the fiscal year were $418,395. 
Maintenance: Normal operation and maintenance of 
the project continued. 
35B. TIOGA-HAMMOND LAKES, PA 
Location. The dams are located in Tioga County, PA, 
upstream from the confluence of the Tioga River and 
Crooked Creek. Tioga Dam is located on the Tioga River 
and Hammond Dam on Crooked Creek, approximately 
opposite the Tioga damsite, about 3.3 miles above its 
mouth and less than one mile from the Village of Brooklyn. 
(See Geological Survey map for Tioga, PA.) 
Existing project. Tioga Dam is 2,600 feet long, rising 
140 feet above the streambed, with a controlled outlet 
conduit. Hammond Dam is 5,900 feet long, and has a 
maximum height of 121.5 feet above the streambed, with 
a concrete spillway. Both dams are of earth and rockfill 
construction. The Tioga-Hammond Lakes project controls 
a total drainage area of 402 square miles, with Tio- 
4-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
ga Dam controlling 280 square miles of the Tioga River 
Basin and Hammond Dam controlling 122 square miles 
of the Crooked Creek Basin. Recreation facilities are 
provided for swimming, camping, picnicking, boating, 
and fishing. Estimated Federal cost (October 1986) of 
new work is $193,120,000 of which $125,029,000 is for 
completed construction, $60,591,000 is for lands and 
damages and relocations and $7,500,000 is for construction 
of the Mill Creek recreation facilities. 
Local cooperation. None required on the completed portion 
of the project; however, construction of the Mill 
Creek Area recreation facilities relies on local interests 
providing specialized facilities including buildings, 
lodges, demonstration centers, and non-water oriented 
equipment and accepting full responsibility for operation 
and maintenance of the entire recreation area. 
Operations and results during fiscal year. New Work: 
Planning for the joint development of the Mill Creek 
Recreation Area continued by the Baltimore District and 
Mansfield University including initiation of plans and 
specifications for construction. 
Maintenance: Normal operation and maintenance of 
the project continued. 
36. WEST BRANCH OF 
SUSQUEHANNA RIVER, PA 
A system of three flood control reservoirs, in the headwaters 
of the West Branch Susquehanna River, PA, are 
known as Curwensville, Alvin R. Bush (formerly known 
as Kettle Creek) and Foster Joseph Sayers (formerly 
known as Blanchard) on the West Branch about 2.5 miles 
upstream from Curwensville, PA; on Kettle Creek 8.4 
miles above the mouth and 17 miles upstream from 
Renovo, PA; and on Bald Eagle Creek about one mile upstream 
from Blanchard, PA, respectively. 
In accordance with the terms of local cooperation, the 
Commonwealth of Pennsylvania furnished assurances 
that it will coordinate operation of George B. Stevenson 
Reservoir (formerly known as First Fork Reservoir) with 
operation of Curwensville, Alvin R. Bush, and Foster 
Joseph Sayers Reservoirs to secure optimum flood control 
benefits from system operation. George B. Stevenson 
Reservoir on the First Fork Sinnemahoning Creek 
in Cameron and Potter Counties, PA, was constructed 
by the Commonwealth of Pennsylvania at a first cost of 
$12,240,000 and an estimated $30,000 annually for operation 
and maintenance. 
36A. ALVIN R. BUSH DAM, PA 
Location. Alvin R. Bush Dam (formerly Kettle Creek 
Dam) is located on Kettle Creek about 8.4 miles above 
the mouth and 15 miles upstream from Renovo, PA. (See 
Geological Survey map for Keating, PA.) 
Existing project. Dam is an earthfill structure,about 
1,350 feet long, rises 165 feet above the streambed, with 
an uncontrolled spillway located in rock adjacent to the 
right abutment, and has a horseshoe-shaped outlet tunnel 
with 3 service gates. The reservoir has a storage capacity 
of 75,000 acre-feet at spillway crest. The project 
controls a drainage area of 226 square miles or about 92 
percent of the Kettle Creek watershed. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
36B. CURWENSVILLE LAKE, PA 
Location. Dam is on the West Branch of the Susquehanna 
River approximately 2.5 miles upstream from Curwensville, 
Clearfield County, PA. (See Geological Survey 
map for Curwensville, PA.) 
Existing project. Dam is an earthfill structure, about 
1,850 feet long, rises 131 feet above the streambed, and 
has an open-cut concrete sill 1,750 feet from the left abutment. 
The outlet works, located in the left abutment, consist 
of a 15-foot diameter circular outlet conduit with 3 
slide control gates 5.5 feet wide and 12 feet high. The 
reservoir has a storage capacity of 124,200 acre-feet at 
spillway crest. The project controls a drainage area of 
365 square miles, or about 98 percent of the West Branch 
Susquehanna River at Curwensville and about 75 percent 
at Clearfield. Recreation facilities include a seasonal 
recreational pool of 790 acres, access roads, parking 
areas, beach area, boat dock, and launching ramp. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of project 
continued. 
36C. FOSTER JOSEPH SAYERS DAM, PA 
Location. Dam is located on Bald Eagle Creek in Centre 
County, PA, about one mile upstream from Blanchard 
and about 14 miles above the confluence of Bald Eagle 
Creek with the West Branch Susquehanna River at Lock 
Haven, PA. (See Geological Survey map for Howard, 
PA.) 
Existing project. Dam is an earthfill structure, about 
6,835 feet long, rises 100 feet above the streambed, and 
has an open-cut concrete chute and uncontrolled concrete 
weir 600 feet wide located in rock in a saddle adjacent 
to the left abutment. The outlet works, located in the left 
abutment, consist of a 15-foot diameter circular outlet 
conduit with two hydraulically-operated wheel gates 7 
feet wide and 15 feet high. The reservoir has a storage 
capacity of 99,000 acre-feet at spillway crest. The project 
controls a drainage area of 339 square miles or 88 percent 
of the drainage area above Beech Creek and 43 percent 
of the Bald Eagle Creek drainage area. Recreation 
facilities include a summer recreation pool of 1,730 acres, 
a conservation pool of 630 acres for the preservation of 
fish life, access roads, parking areas, boat docks and 
launching ramps, and camping areas. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
4-18

BALTIMORE, MD DISTRICT 
37. WYOMING VALLEY, PA 
Location. The project is located in Luzerne County, PA, 
on the Susquehanna River. The project area is limited 
to the four existing Federal flood control projects. These 
levee improvements are in Plymouth, Kingston- 
Edwardsville, Swoyersville-Forty Fort, and Wilkes-Barre 
and Hanover Township. 
Existing project. The four projects were constructed 
during the period 1935 through 1976 and consist of levee, 
sheet piling, flood wall, and associated interior drainage 
structures along both banks of the Susquehanna River 
which provide flood control benefits estimated at $46.1 
million annually. Remedial measures to protect against 
levee failure under future high discharge conditions consist 
of: weighted filter drains on the landside of the levees 
to protect against erosion due to seepage in certain 
areas; stability berms and toe protection on the riverside 
of the levees in certain areas to stabilize the riverbank 
and protect against erosion due to river flows; stabilization 
of sheet piling in certain areas; and additional relief 
wells to control the underseepage in other areas. 
Local cooperation. Lands and relocations for construction 
of the existing projects at an estimated cost of 
$1,000,000 were provided by the Boroughs of Kingston, 
Edwardsville, Plymouth, the City of Wilkes-Barre, 
Hanover Township, and Luzerne County. These entities 
also operate and maintain the existing projects. Updated 
assurances were obtained during preparation of the 
General Design Memorandum. Additional local costs in 
connection with the proposed remedial work are expected 
to be minor. 
Operations and results during fiscal year. Construction 
continued for the filter drain work at Wilkes-Barre, 
Hanover Township, which is 99 percent complete and 
filter drain work at Kingston-Edwardsville and 
Swoyersville-Forty Fort is 75 percent complete. A contract 
for the Ross Street Sewer Modification was awarded 
on July 21, 1986 and is 5 percent complete. 
38. YORK, INDIAN ROCK DAM, PA 
Location. On Codorus Creek 10 miles above its confluence 
with the Susquehanna River. Codorus Creek has 
tributary branches in York County in the south and central 
parts of Pennsylvania. (See Geological Survey Quadrangle 
sheets, Pennsylvania-York and Hanover.) 
Existing project. Indian Rock Dam is an earth and 
rockfill dam about 1,000 feet long at the top, rising 83 
feet above the streambed, with a reservoir providing for 
control storage of 28,000 acre-feet. Dam is on the main 
branch of Codorus Creek about 3 miles above York. Outlet 
works are in the right abutment and the uncontrolled 
spillway is on the right bank. Reservoir will control entire 
drainage area of the main branch of Codorus Creek 
and 41 percent of the drainage area above York. Improvements 
in Codorus Creek in the vicinity of and through 
the City of York provide for 22,969 feet of channel extending 
from 300 feet above Richland Avenue to a point 
downstream from the Pennsylvania Railroad crossing 
known as Black Bridge. Improvements, which will increase 
channel capacity to 24,000 cubic feet per second, 
include widening and deepening the channel, bank protection, 
removal of York Roller Mill Dam, and a low water 
channel about 3,900 feet long in the vicinity of York 
Roller Mill Dam. Cost of new work for the completed 
project was $5,061,167, of which $4,566,446 (regular 
funds) and $11,588 (emergency relief funds) were for construction 
and $483,133 (regular funds) was for lands and 
damages. 
Local cooperation. Section 2, Flood Control Act of June 
28, 1938, applies. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
39. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Projects in New York, Pennsylvania, Maryland, District 
of Columbia, and Virginia were inspected during the 
period by hired labor. See Table 4-I. 
40. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Operations and results during fiscal year. The operation 
of George B. Stevenson Dam, PA, was coordinated 
with the operation of Alvin R. Bush, Curwensville, and 
Foster Joseph Sayers Dams in the West Branch Susquehanna 
River Basin in order to secure optimum flood control 
benefits from the system operation. Costs during the 
period were $29,586. 
Supplemental instructions for the operation of Savage 
River Dam, MD, were provided, during periods of high 
water, to insure maximum protection for downstream localities. 
Costs during the period were $47,412. 
41. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and 
antecedent legislation). 
Cost for the period was $514,050 of which $331,088 was 
for Disaster Preparedness Program, and $182,962 was 
for Rehabilitation and Emergency operations. 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (preauthorization). 
Fiscal year costs were $94,938 for Conklin-Kirkwood 
NY. Non-structural study for Conklin-Broome (Ice Jam) 
NY; $290,289 for Hyndman, PA; $33,209 for Tunkhannock 
Creek, Tunkhannock, PA; and $13,362 for Hills 
Point Rd., MD. 
4-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Water Supply 
42. WASHINGTON AQUEDUCT 
Location. The diversion dam and raw water supply intakes 
at Great Falls, the two collecting conduits, part of 
Dalecarlia receiving reservoir, the booster pumping station 
and the Little Falls raw water pumping station are 
located in Maryland. All other structures of the water 
supply system including parts of the raw water collecting 
system, two purification plants, pumping stations, 
storage reservoirs, and transmission mains are in the District 
of Columbia. Federal owned water mains are maintained 
in Virginia and Maryland. 
Existing project. Control of the water supply system 
is vested in Chief of Engineers (See Acts of March 3, 
1859, and March 2, 1867, November 22, 1973 and Sec. 
1800 of Revised Statutes). The project includes: administration; 
operation and maintenance of the collection, 
purification, pumping, and transmission facilities; protection 
of the water supply system; engineering; and construction 
of major water system additions and 
improvements. 
Authority to supply water to Arlington County, the 
City of Falls Church, and other jurisdictions in Virginia 
is contained in Public Law 119, 69th Congress, approved 
April 14, 1926; and Public Law 118, 80th Congress, June 
26, 1947. 
Local cooperation. Requirements are described in full 
on page 4-19 of the Fiscal Year 1981 Annual Report. 
Operations and results during fiscal year. New Work: 
The McMillan Water Treatment Plant Replacement work 
authorized with "no year" funds is 99 percent complete. 
A contract for the new Chlorine Bldg. at Dalecarlia was 
awarded July 31, 1984 and construction is complete and 
operational. 
Maintenance (operation): An uninterrupted and adequate 
supply of purified water was furnished to the District 
of Columbia; Arlington County, and Falls Church, 
VA; and to Federal establishments in the District of 
Columbia, Arlington County, VA and Montgomery and 
Prince Georges Counties in Maryland. Total consumption 
for Fiscal Year 1986 was 74,122 million gallons; the 
maximum daily consumption was 253 million gallons and 
average daily consumption was 203 million gallons. The 
amount furnished Arlington County and Falls Church, 
VA was 40.6 million gallons per day. The Corps of Engineers 
was reimbursed in the amount of $4,765,183 for 
water furnished to the Virginia communities by the 
Washington Aqueduct. 
The treated water delivered to the 1.1 million consumers 
served by the Washington Aqueduct met or surpassed 
all Water Quality standards promulgated by the 
U.S. Environmental Protection Agency under the Safe 
Drinking Water Act (P.I. 93-523.) 
General Investigations 
43. SURVEYS 
Costs for the fiscal year were $530,840 of which 
$150,026 was for flood damage prevention studies, 
$109,231 for shoreline protection studies, $1,509 for special 
studies, $72,000 for special investigations, and 
$198,074 for coordination with other agencies and non- 
Federal interests. 
44. COLLECTION AND STUDY OF 
BASIC DATA 
Costs for flood plain management activities and general 
planning guidance during the period was $304,209. 
Providing assistance and guidance to local interests on 
methods and procedures for preventing and reducing 
flood damages was in progress at end of fiscal year. 
45. CONTINUATION OF PLANNING 
AND ENGINEERING 
Susquehanna Basin at Harrisburg, PA-The plan of 
improvement for the South Harrisburg area recommended 
in an interim report on the Susquehanna River 
Basin study includes a floodwall 3,800 feet long, a pump 
station and floodgates for interior drainage, a dry detention 
dam along Asylum Run (a small tributary of Paxton 
Creek), an enlarged earth and concrete channel for 
Paxton Creek about 4 miles long, and minor recreation 
and fish and wildlife facilities. Preparation of a General 
Design Memorandum continued during the fiscal year. 
Estimated planning and engineering cost is $2,900,000. 
Total costs during the fiscal year were $363,317. 
Lock Haven, PA-The plan of improvement recommended 
in the Phase I General Design Memorandum includes 
24,500 feet of levee, 6,500 feet of flood wall, eight 
closure structures, four pumping stations, diversion of 
Lusk Run, and minor recreation facilities. Preparation 
of a Phase II General Design Memorandum continued 
during the fiscal year. Estimated planning and engineering 
cost is $2,025,000. Total costs during the fiscal year 
were $842,935. 
Wyoming Valley, PA (Levee Raising)-The plan of improvement 
in the Phase I General Design Memorandum 
includes raising the existing levees and flood walls between 
5 and 7 feet, modifying closure structures, relocating 
utilities, and providing some new flood walls and 
levees to maintain the system's integrity. The plan also 
includes raising five other local protection projects, 
removing an abandoned railroad bridge, and providing 
non-structural measures to mitigate any significant induced 
damages and the potential of a catastrophic failure 
of an existing project. The estimated planning and engineering 
cost is $5,700,000 and costs during the fiscal 
year were $732,177. 
Atlantic Coast of Maryland & Assateague Island, 
VA-The plan of improvement recommended in the survey 
report included widening and raising the existing 
beach about 7.6 miles, constructing a steel sheet pile 
bulkhead about 1.8 miles, and constructing a sand dune 
about 6.3 miles. The State of Maryland will now provide 
the expanded beach for recreation and the Corps will provide 
the bulkhead and dune for hurricane protection. 
Preparation of a combined General Design Memorandum 
4-20

BALTIMORE, MD DISTRICT 
was initiated during the fiscal year. The estimated planning 
and engineering cost is $1,800,000 and costs during 
the fiscal year were $144,704. 
46. ADVANCED ENGINEERING 
AND DESIGN 
Francis E. Walter Dam, PA-(Modification)-The 
authorized project would provide for modifying the existing 
single purpose flood control project by raising the 
existing dam 30 feet thereby adding water supply and 
recreation purposes. Work continued on design memoranda 
for project features and plans and specifications were 
prepared for the operations building and dam grouting. 
The preconstruction planning cost is $5,688,000. Total 
costs during the fiscal year were $1,354,692. 
Tamaqua, PA-The authorized project would provide 
for a 9-foot diameter diversion tunnel 2,930 feet long, that 
starts at Wabash Creek at the west boundary of Tamaqua 
and terminates at the Little Schuylkill River. The 
project also includes an intake structure, a stilling basin, 
a highway bridge, and a small dry detention reservoir 
on a tributary of Wabash Creek. Coordination with 
the local sponsor continued during the fiscal year. The 
preconstruction planning cost is $1,850,000 and total 
costs during the fiscal year were $6,733. 
Washington, DC & Vicinity-The authorized project 
would provide for raising the grade of a portion of P 
Street, filling an area near the Lincoln Memorial (along 
23rd Street) regrading the area adjacent to 17th Street 
and constructing a removable closure structure across 
17th Street. These measures were authorized to restore 
the design level of protection of the existing project and 
to reduce the need for emergency closure in the event of 
a flood. Preparation of a combined General Design 
Memorandum was initiated furing the fiscal year and total 
costs were $137,489. Estimated preconstruction planning 
cost is $2,000,000. 
4-21

TABLE 4-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
1. Baltimore Harbor 
and Channels, 
MD and VA 
2. Baltimore Harbor 
MD Collection 
& Removal of 
Drift 
3. Chester 
River, MD 
4. Claiborne 
Harbor, MD 
5. Fishing Creek, 
MD 
6. Herring Bay & 
Rockhold Creek, 
MD 
7. Herring 
Creek, MD 
8. Island 
Creek, St. Georges 
Island, MD 
9. Little Wicomico 
River, VA 
10. Lower Thorofare, 
Deal Island, 
MD 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,300,000 770,000 455,000 5,904,000 52,755,7121 
851,317 1,055,174 555,821 5,585,736 52,365,1501 
5,769,0002 12,865,0004 15,637,0006 7,440,7918 73,417,65110 
6,568,7553 13,035,8145 15,637,012' 7,440,790' 73,417,64610 
177,000 
186,916 
5,000 
5,000 
202,000 
202,323 
205,000 
201,424 
228,000 
227,999 
95,129 
95,127 
318,636 
333,032 
80,450 
80,450 
19,310 
19,310 
236,000 
239,574 
25,000 
25,000 
68,000 
68,000 
432,750 
432,748 
20,000 
20,000 
503,200 
478,502 
3,287,210 
3,287,207 
70,495"1 
70,495" 
1,364,473 
1,364,473 
42,97412 
42,97412 
258,733 
258,731 
111,242 
111,242 
1,372,400 
1,372,398 
50,591 
50,591 
474,248 
474,248 
788,000 
763,302 
66,229 
66,229 
10,306 
10,306 
14,000 
14,000 
7,078 
7,079 
416,600 
416,600 
20,000 
20,000 
138,600 
134,210 
1,369,000 
117,978 
164,500 
164,499 
23,836 
23,836 
342,110 
342,110 
81,88513 
81,885'13 
1,387,653 
1,383,261 
1,413,65814 
162,636' 4 
505,442 
505,441 
4-22

BALTIMORE, MD DISTRICT 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
11. Lowes 
Wharf, MD 
12. Ocean City Harbor 
and Inlet and Sinepuxent 
Bay, MD 
13. Parish Creek, 
MD 
14. Potomac and 
Anacostia Rivers, 
DC, Collection & 
Removal of Drift 
15. Potomac River- 
Aquatic Plant 
Control, MD, 
VA, DC 
16. Prevention of 
Obstructions & 
Injurious Deposits, 
Baltimore Harbor, 
MD 
17. Rhodes Point 
to Tylerton, MD 
18. St. Patricks 
Creek, MD 
19. Slaughter 
Creek, MD 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
182,000 
48,900 
30,000 
151,790 
1,343,000 935,000 
251,452 2,106,987 
781,000 
709,961 
1,000,000 1,750,000 1,050,000 
- 2,734,267 1,056,190 
- - 31,578 
- - 31,578 
486,000 
493,074 
40,929 
-51,000 
213,698 
352,000 
353,227 
162,000 
162,000 
410,000 
394,333 
51,000 
50,949 
41,488 
41,487 
2,934 
2,934 
8,354 
8,354 
4-23 
31,000 
42,310 
422,600 
493,639 
38,000 
47,143 
19,400 
19,400 
417,000 
432,664 
378,000 
323,826 
54,363 
35,825 
84,000 
84,040 
398,200 
398,201 
21,000 
21,000 
317,829 
317,829 
350,193's 
350,1931 
9,651,508 
9,651,506 
3,838,000 
3,837,600 
19,17016 
19,17016 
113,834 
113,834 
6,220,175 
6,220,171 
378,000 
323,826 
54,363 
35,825 
.4,456,040 
4,456,029 
304,000 
304,000 
711,194 
711,194 
5,000 
5,000 
15,752 
15,752 
46,602 
46,602 
4,140 
4,140 
448,030 
448,030 
5,000 
5,000 
15,000 
15,000 
40,000 
40,000

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
20. Tred Avon, New Work 
MD Approp. 
Cost 
Maint. 
Approp. 
Cost 
21. Twitch Cove & New Work 
Big Thorofare, Approp. 
MD Cost 
Maint. 
Approp. 
Cost 
22. Upper Thorofare, New Work 
MD Approp. 
Cost 
Maint. 
Approp. 
Cost 
23. Washington Harbor, New Work 
DC Approp. 
Cost 
Maint. 
Approp. 
Cost 
24. Wicomico River, New Work 
MD Approp. 
Cost 
Maint. 
Approp. 
Cost 
27. Colonial Beach, New Work 
VA Approp. 
Cost 
Contrib. 
Approp. 
Cost 
29. Bloomington Lake, New Work 
MD & WV Approp. 
Cost 
Maint. 
Approp. 
Cost 
30. Cumberland, MD New Work 
and Ridgeley, Approp. 
WV Cost 
Maint. 
Approp. 
Cost 
31A. Aylesworth Creek New Work 
Lake, PA Approp. 
Cost 
Maint. 
Approp. 
Cost 
32. Raystown Lake, New Work 
Raystown Branch, Approp. 
Juniata River, PA Cost 
Maint. 
Approp. 
Cost 
17,000 
17,000 
36,000 
36,000 
27,569 
27,569 
10,000 
10,000 
- 19,000 
440,826 
824,730 
547,075 
-64,000 
-7,138 
-65,023 
44,678 
1,688,000 
1,856,543 
893,200 
885,166 
64,600 
66,856 
67,000 
71,631 
63,000 
77,569 
134,000 
915,074 
206,782 
206,782 
681,000 
681,000 
15,000 
12,500 
43,000 
43,000 
55,000 
55,000 
358,500 
358,498 
523,310 
523,310 
109,843 
109,843 
193,175 
193,175 
1,937,811 
1,937,811 
62,446 
62,446 
705,941 
705,939 
3,191,07717 
3,191,07717 
44,000 4,794,4961819 
44,000 4,794,49618,19 
49,000 
49,001 
1,530 
471,60920 
471,60920 
5,962,737 
5,962,736 
519,00021 
518,03021 
414,977 
414,977 
-110,000 1,900,000 
582,603 1,974,750 
- 176,270,300 
26,678 176,266,783 
988,978 1,160,200 1,759,000 
1,005,530 1,163,471 1,759,018 
45,000 
45,000 
72,925 
75,636 
55,930 
55,930 
113,500 
113,424 
61,000 
61,000 
101,000 
101,071 
2,423,056 1,741,000 2,125,500 2,108,000 
2,447,276 1,778,456 2,077,231 2,138,283 
5,733,978 
5,733,938 
15,633,97022 
15,633,97022 
639,229 
639,229 
2,320,400 
2,320,400 
963,602 
963,595 
77,408,770 
77,408,770 
17,767,295 
17,749,242 
4-24

BALTIMORE, MD DISTRICT 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
33A. Addison, NY 
33B. Almond Lake, 
NY 
33C. Arkport Dam, 
NY 
33D. Avoca, NY 
33E. Binghamton, NY 
33F. Canisteo, NY 
33G. Corning, NY 
33H. East Sidney Lake, 
NY 
331. Elmira, NY 
33J. Hornell, NY 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
827,050 
827,050 
12,900 
12,879 
221,000 
230,101 
180,800 
178,847 
15,900 
16,788 
34,300 
34,283 
38,100 
40,321 
24,800 
27,126 
347,500 
359,826 
22,800 
26,264 
348,200 
257,415 
16,049 
16,124 
160,772 
164,920 
78,363 
87,246 
18,300 
18,300 
28,300 
28,398 
25,800 
25,802 
25,600 
25,600 
300,118 
302,918 
20,400 
20,400 
85,051 
176,056 
17,200 
17,200 
379,500 
379,362 
130,700 
130,621 
23,526 
23,525 
18,000 
18,000 
53,474 
53,472 
53,900 
53,900 
262,100 
262,095 
25,900 
25,900 
106,170 
106,168 
14,100 
14,091 
234,000 
234,127 
148,000 
148,073 
24,300 
24,300 
383,000 
40,480 
35,200 
35,200 
25,900 
25,874 
38,500 
38,500 
330,000 
329,995 
28,300 
28,297 
135,900 
135,901 
178,155 
178,146 
5,760,211 
5,760,211 
3,022,840 
3,022,826 
1,910,00023 
1,910,00023 
1,591,174 
1,591,165 
436,37424 
436,37424 
380,661 
380,660 
3,335,00025 
2,992,48025 
413,781 
413,781 
1,183,11126 
1,183,11126 
618,135 
618,107 
3,322,00027 
3,322,00027 
641,558 
641,558 
6,049,504 
6,049,504 
3,447,319 
3,447,303 
6,883,305 
6,883,305 
264,549 
264,546 
4,558,69828 
4,558,69828 
2,990,133 
2,990,130 
4-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
Total 
to 
Sept. 30, 1986 
33K. Lisle, NY 
33L. Oxford, NY 
33M. Whitney Point 
Lake, NY 
33N. Whitney Point 
Village, NY 
34. Stillwater Lake, 
Lackawanna 
River, PA 
35A. Cowanesque Lake, 
PA 
35B. Tioga-Hammond 
Lakes, PA 
36A. Alvin R. Bush 
Dam, PA 
36B. Curwensville Lake, 
PA 
36C. Foster Joseph 
Sayers Dam, PA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
22,500 
26,382 
11,200 
13,737 
259,500 
300,269 
26,300 
29,273 
158,600 
161,139 
168,891 
851,200 
833,587 
-220,000 
79,419 
1,269,200 
1,331,830 
488,800 
413,472 
360,500 
361,923 
412,000 
412,339 
25,400 
25,453 
15,900 
15,900 
265,843 
266,070 
33,200 
33,253 
201,340 
201,680 
670,000 
722,340 
743,904 
754,305 
-60,000 
23,487 
1,144,289 
1,166,973 
403,810 
572,896 
405,491 
405,237 
446,722 
449,450 
19,800 
19,800 
17,600 
17,600 
304,800 
304,721 
20,500 
20,500 
211,700 
211,631 
1,065,000 
853,691 
932,800 
938,312 
35,000 
30,000 
1,540,700 
1,540,278 
427,300 
427,275 
491,100 
492,316 
472,300 
472,515 
26,100 
26,098 
11,300 
11,290 
644,000 
643,908 
18,400 
18,380 
218,000 
218,056 
195,000 
418,395 
894,200 
897,042 
90,000 
65,546 
1,329,800 
1,330,248 
463,000 
452,583 
628,000 
628,049 
424,000 
423,980 
661,19929 
661,19929 
642,122 
642,120 
131,000 s0 
131,0003o 
200,732 
200,722 
5,421,539 
5,421,539 
4,095,140 
4,094,961 
424,096 
424,096 
323,661 
323,641 
5,725,700 
5,725,700 
2,060,209 
2,060,190 
107,960,700 
107,957,868 
4,669,354 
4,668,706 
18,744,800 
18,715,346 
8,454,654 
8,454,585 
7,103,001 
7,103,001 
4,130,622 
4,120,171 
20,396,060 
20,396,060 
5,989,389 
5,989,360 
30,887,06331 
30,887,06331 
4,906,084 
4,906,055 
4-26 
See 
Section 
in Text Project Funding FY83 FY84 FY85 FY86 aaa a vwv a s v vva a r aaaaa ab a a vva a vz a s vy a a v

BALTIMORE, MD DISTRICT 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
37. Wyoming Valley, New Work 
PA Approp. 2,390,000 2,190,000 6,800,000 740,000 26,145,000 
Cost 1,388,786 3,205,348 2,686,198 3,531,080 24,734,047 
38. York, Indian New Work 
Rock Dam, PA Approp. - - - - 5,061,16732 
Cost - - - - 5,061,16732 
Maint. 
Approp. 294,800 373,344 534,000 548,000 4,867,21733 
Cost 312,558 379,530 523,994 557,982 4,867,18533 
Contributed 
Approp. - - 85,000 - 85,000 
Cost - - - 81,849 81,849 
1. Includes $8,764,003 for previous projects. 16. Includes $19,170 Works Progress Administration 
2. Includes $1,085,000 for sections of project in Norfolk funds. 
District. 17. Includes $3,029,001 for previous project. 
3. Includes $1,891,518 for sections of project in Norfolk 18. Includes $1,831,609 for previous project. 
District. 19. Excludes $4,000 for emergency dredging under provi- 
4. Includes $40,000 for sections of project in Norfolk sions of Section 3, 1945 River and Harbor Act. 
District. 20. Includes $50,000 for previous project and excludes 
5. Includes $200,691 for sections of project in Norfolk $14,000 contributed funds. 
District. 21. Excludes $414,977 contributed funds. 
6. Includes $88,000 for sections of project in Norfolk 22. Includes $49,998 emergency relief funds. 
District. 23. Includes $62,577 emergency relief funds. 
7. Includes $88,001 for sections of project in Norfolk 24. Includes $109,944 emergency relief funds. 
District. 25. Excludes $163,096 contributed funds. 
8. Includes $967,791 for sections of project in Norfolk 26. Includes $207,520 rehabilitation funds. 
District. 27. Excludes $34,729 contributed funds. 
9. Includes $967,791 for sections of project in Norfolk 28. Includes $250,899 emergency relief funds and excludes 
District. $15,000 contributed funds. 
10. Includes $399,802 for previous projects. 29. Includes $71,557 emergency relief funds. 
11. Includes $38,041 for previous project. 30. Includes $73,465 emergency relief funds. 
12. Project deferred for restudy. 31. Excludes $263,900 contributed funds in accordance 
13. Excludes $5,000 contributed funds. with the Tri-party Agreement for construction of sanitary sys- 
14. Includes $5,000 for previous project. temrn for public use. 
15. Includes $283,008 public works funds and $67,185 32. Includes $11,588 emergency relief funds. 
emergency relief funds; excludes $500,000 contributed funds. 33. Includes $15,000 for deferred maintenance. 
TABLE 4-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
BALTIMORE HARBOR AND CHANNELS, MD and VA 
Aug. 8, Branch channel 35 feet deep to head of Curtis Bay, and one 35 feet deep and 
1917 400 feet wide Fort McHenry to Port Covington entrance channel, thence 
150 feet wide to Ferry Bar, and thence 27 feet deep and 150 feet wide to 
Hanover Street Bridge, widen approaches and bends, and enlarge anchorage 
basin near entrance. Inclusion of Patapsco River and tributaries into one 
project for Baltimore Harbor. 2 
Jan. 21, Change in location of anchorage near upper end of Fort McHenry Channel. 
1927 
Jul. 3, 
1930 
Increased anchorage facilities. 
H. Doc. 799, 
64th Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 11, 
70th Cong., 1st Sess. 
4-27 
1.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul. 3, For 37-foot depth in that portion of channel to Baltimore lying between 37-foot 
1930 depth curve near Baltimore Light to Sparrows Point entrance channel; widen 
angle between Fort McHenry and Ferry Bar section; and for width of 400 
feet in Curtis Bay section. 
Oct. 17, For 22-, 18-, and 15-foot channels in Curtis Creek from 22-foot depth below 
1940 Pennington Avenue Bridge to upper end of marginal wharf of U.S. Ordnance 
Depot. 
Mar. 2, Uniform main channel 39 feet deep from the ocean through York Spit section 
1945 and Craighill entrance to Fort McHenry, additional anchorage area, 2,400 
feet long, 1,200 feet wide, and 30 feet deep; a connecting channel 400 feet 
wide and 27 feet deep from Cutoff Brewerton Angle in main channel to Inland 
Waterway from Delaware River to Chesapeake Bay; a channel in Curtis Creek 
200 feet wide and 35 feet deep from head of existing 35-foot project channel 
in Curtis Bay to a point in the creek about 750 feet below Pennington 
Avenue Bridge. 
Mar. 2, A channel 22 feet deep and 200 feet wide from 22-foot depth curve south of 
1945 Baltimore & Ohio R.R. bridge about 2,800 feet to vicinity of Arundel Cove, 
thence 100 feet wide in Arundel Cove for about 2,100 feet; with an anchorage 
basin about 700 feet square adjacent to channel southwesterly of Coast 
Guard wharf. 
Jul. 3, Main channel 42 feet deep and 1,000 feet wide in Cape Henry section at 
1958 entrance to Chesapeake Bay and in York Spit section; 42 feet deep and 800 
feet wide in Rappahannock Spit section and in approach channel to Baltimore 
Harbor from Craighill entrance to Fort McHenry, with widening at entrance 
and bends; channels 42 feet deep and 600 feet wide in Curtis Bay and Ferry 
Bar sections of harbor; a connecting channel 35 feet deep and 600 feet wide 
from main channel to approach channel to Chesapeake and Delaware Canal; 
and for three disjointed sections of channels of same depth and width in 
Chesapeake Bay leading to Chesapeake and Delaware Canal; and to provide 
Federal maintenance of 39-foot depth in Northwest Branch, in areas dredged 
to that depth by local interests. 
Dec. 31, Deepening of the Cape Henry Channel to 50 feet at the existing width of 
1970 1,000 feet, with widening at bends; deepening of the Spit Channel to 50 feet 
at the existing width of 1,000 feet, with widening at bends; enlargement of 
the Rappahannock Shoal Channel to a depth of 50 feet and a width of 1,000 
feet; deepening of the main ship channel from Chesapeake Bay to Fort 
McHenry to a depth of 50 feet at the existing width of 800 feet, with widening 
at bends and at the Craighill Entrance; deepening of the Curtis Bay 
Channel to a depth of 50 feet at the existing width of 600 feet, and deepening 
of the 950-foot wide and 980-foot long turning basin at the head of channel 
to the same depth; deepening of the Northwest Branch-East Channel to 
a depth of 49 feet from the depth existing at the time of construction at a 
width of 600 feet, and deepening of the 950-foot wide and 950-foot long turning 
basin at the head of the channel to the same depth; and deepening and 
extension of the Northwest Branch-West Channel to a depth of 40 feet from 
the depth existing at the time of construction, at a width of 600 feet, and 
with an irregularly shaped turning basin at the head of the channel 40 feet 
deep and about 2,000 feet long with a maximum width of 1,150 feet. 
BALTIMORE HARBOR, MD-COLLECTION AND REMOVAL OF 
DRIFT 
Jun. 30, Collection and removal of drift from Baltimore Harbor and its tributary 
1948 waters. 
CHESTER RIVER, MD. 
Mar. 3, A channel 7 feet deep at mean low water and 100 feet wide from Chester 
1873 River to Eastern Bay through Kent Island Narrows. 
Sep. 19, A channel 6 feet deep at mean low water and 60 feet wide from Crumpton 
1980 to Jones Landing. 
H. Doc. 86, 85th 
Cong., 1st Sess. 
Adopted as a national 
defense project. (No 
printed report.) 
H. Doc. 741, 
79th Cong., 2nd Sess. 
In accordance with 
plans on file in the 
Office, Chief of 
Engineers 
H. Doc. 86, 
85th Cong., 1st Sess. 
H. Doc. 181, 
94th Cong., 1st Sess. 
River and Harbor Act 
of 1948 
E. Doc. 25, 
42d. Cong., 3d Sess. 
H. Ex. Doc. 65, 
51st. Cong., 1st Sess. 
4-28

BALTIMORE, MD DISTRICT 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jun. 30, A channel 7 feet deep at mean low water and 75 feet wide extending from 
1948 the 7-foot depth in Kent Island Narrows 800 feet into Wells Cove with a 
basin of the same depth and 300 feet square at the head of the channel. 
CLAIBORNE HARBOR, MD 
Jun. 13, A channel 12 feet deep and 300 feet wide from deep water to the railroad 
1902 pier in the harbor, and thence shoreward along the south side of the pier 
with a width of 195 feet and a length of 500 feet. An extension of the present 
jetty. 
FISHING CREEK, MD 
Aug. 26, A channel 7 feet deep with widths of 100 feet and 60 feet from deep water in 
1937 Chesapeake Bay to an anchorage of the same depth, 120 feet wide and 
400 feet long, located in the marsh 500 feet above the mouth of the creek 
and twin stone jetties at the entrance. 
HERRING BAY & ROCKHOLD CREEK, MD 
Jul. 3, A channel 60 feet wide, 5 feet deep, from the 6-foot contour in Herring Bay 
1930 to the 3-foot contour in Rockhold Creek. 
Jun. 20, For the present project channel dimensions, 7 feet deep and 60 feet wide, 
1938 the turning basin 7 feet deep, and a stone breakwater 900 feet long. 
HERRING CREEK, MD 
Jul. 3, Provides for an entrance channel 6 feet deep and 60 feet wide with a 
1950 turning basin of irregular shape and 6 feet deep, and riprap stone jetties 
on the upstream and downstream sides of the entrance channel 770 and 650 
feet long, respectively. The project length is 1,630 feet. 
Mar. 7, 
1986 
Sec 111 
Constructing 250 feet of beachfill, 2,187 linear feet of stone revetment, 
and upgrading 350 feet of existing revetment along the Tall Timbers 
waterfront. 
ISLAND CREEK, ST. GEORGES ISLAND, MD (See Section 9 of Text) 
Mar. 2, A channel 5 feet deep and 50 feet wide through the entrance to Island 
1945 Creek with an anchorage basin of same depth, 200 feet wide, and 500 feet 
long in the creek. 
LITTLE WICOMICO RIVER, VA 
Aug. 30, A channel 8 feet deep and 150 feet wide from Potomac River to deep water 
1935 in Little Wicomico River; two stone jetties 1,000 feet and 1,300 feet long 
at the entrance; and 1,004 linear feet of timber bulkhead to stabilize the 
dredged inner channel. 
10. 
Jun. 25, 
1910 
Mar. 2, 
1945 
Mar. 7, 
1986 
Sec 107 
11. 
LOWER THOROFARE, DEAL ISLAND, MD 
A channel 6 feet deep, 80 feet wide, from Tangier Sound to the wharves 
at Wenona; widening the angles and the end to furnish anchorage basins. 
Modified to provide a channel 60 feet wide, 7 feet deep from Tangier Sound 
to and including a mooring basin 7 feet deep, 100 feet wide, 300 feet long, 
in the marsh at the head of the cove at Wenona. 
Constructing a stone breakwater within Lower Thorofare, and a stone jetty 
on Deal Island to reduce channel maintenance. 
LOWES WHARF, MD 
Sep. 3, A channel 60 feet wide and 7 feet deep at mean low water from the 7-foot 
1954 depth curve in Ferry Cove to and including a basin of the same depth, 200 
feet wide and 300 feet long on the south side of Lowes Wharf. 
OCEAN CITY HARBOR & INLET & SINEPUXENT BAY, MD 
Aug. 30, Construction of an inlet between the Atlantic Ocean and Sinepuxent Bay, 
19358 10 feet deep and 200 feet wide, protected by jetties; a channel 8 feet deep 
and 100 feet wide from the inlet to Ocean City, 6 feet deep and 150 feet 
wide to Green Point, and 100 feet wide into Chincoteague Bay. 
4. 
5. 
6. 
4-29 
H. Doc. 380, 
80th Cong., 1st Sess.1 
H. Doc. 81, 
56th Cong., 1st Sess. 
H. Doc. 241, 
75th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 34, 
71st Cong., 2nd Sess. 
H. Doc. 595, 
75th Cong., 3rd 
Sess.' 
H. Doc. 159 
84th Cong., 1st Sess.' 
Detailed Project 
Report 
July 18, 1985 
H. Doc. 99, 
76th Cong., 1st Sess.' 
Rivers and Harbors 
Committee Doc. 24, 
72nd Cong., 1st Sess. 
H. Doc. 76, 
60th Cong., 1st Sess. 
H. Doc. 238, 
76th Cong., 1st Sess.' 
Detailed 
Project Report. 
Mar. 8, 1984 
H. Doc. 90, 
82d Cong., 1st Sess.' 
Rivers and Harbors 
Committee Doc. 38, 
72nd Cong., 1st Sess. 
8. 
9. 
12.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug. 30, Modification providing a 10-foot by 100-foot channel from the inlet to the 
1935' west side of the bay with two turning basins; a channel 6 feet deep and 125 
feet wide from the inlet channel to opposite North 8th Street, Ocean City, 
and 75 feet wide into Isle of Wight Bay. 
Sep. 3, Modification providing for raising the north jetty to an elevation 9 feet 
19455 above mean low water, and a channel 300 feet wide and 16 feet deep from 
the ocean through the inlet to the Isle of Wight Bay Channel, thence 200 
feet to the project harbor, and a depth of 14 feet in the project harbor. Channel 
depths refer to project datum. 
PARISH CREEK, MD 
Aug. 30, Provide a channel 8 feet deep and 50 feet wide, widened at its ends, from 
1935 deep water in West River to the head of the south fork of Parish Creek, 
and an anchorage basin at the junction with the north fork of Parish Creek, 
having a depth of 6 feet and an area not exceeding 1.5 acres. 
POTOMAC & ANACOSTIA RIVERS, DC-COLLECTION & 
REMOVAL OF DRIFT 
Oct. 27, Collection and removal of drift from waters of the Potomac and Anacostia 
1965 Rivers and their tributaries in the Washington, DC area from the head of 
the tidewater to Mount Vernon, VA. 
POTOMAC RIVER AQUATIC PLANT 
CONTROL, MD, VA, DC 
Jul. 2, Control of Hydrilla and other nuisance plants using mechanical harvesting 
1986 to clear a 60 foot wide, 6 foot deep connecting channel from open waters to 
eligible public use areas. 
PREVENTION OF OBSTRUCTIONS & INJURIOUS DEPOSITS, 
BALTIMORE HARBOR, MD 
Aug. 28, Continuous patrol and inspection of Baltimore Harbor, Chesapeake Bay, 
1958 and its tributaries to prevent and detect violations, and issue permits as 
required for transporting and depositing waste materials in navigable 
waters. (The project is limited to the tidal waters of Chesapeake Bay and 
its tributaries that lie within the State of Maryland.) 
17. 
Jan. 22, 
1982 
Sec. 107 
Jul. 14, 
1960 
Sep. 3, 
1954 
Aug. 1, 
1968 
Sec. 107 
Jul. 14, 
1960 
RHODES POINT TO TYLERTON, MD 
A channel 6 feet deep and 50 feet wide at mean low water from the northern 
limit of existing Rhodes Point to Tylerton Federal navigation channel, a 
distance of about one mile, through Sheep Pen Gut to deep water in the 
Chesapeake Bay. 
A channel 4 feet deep at mean low water and 50 feet wide from Tylerton to 
Rhodes Point via Rhodes Point Gut. 
Modification providing for a channel 6 feet deep and 50 feet wide from that 
depth in Tyler Creek to and including an anchorage basin of the same depth 
150 feet wide and 400 feet long at Tylerton; channel 6 feet deep and 50 feet 
wide from that depth in Shanks Creek to and including an anchorage basin 
of the same depth 100 feet wide and 400 feet long at Rhodes Point; channel 
6 feet deep and 50 feet wide from that depth in Big Thorofare River to 
Tylerton; channel 6 feet deep and 50 feet wide from Rhodes Point to Tylerton. 
ST. PATRICKS CREEK, MD 
May 17, Entrance channel 7 feet deep, 60 feet wide and approximately 2,450 feet 
1950 long from deep water in St. Clement Bay to deep water within the creek. 
SLAUGHTER CREEK, MD 
Jul 25, A channel 7 feet deep and 100 feet wide at mean low water through the 
1912 bar at the mouth, a distance of about one-third of a mile, the lower end 
of the section extending about 900 feet into Little Choptank River. 
Rivers and Harbors 
Committee Doc. 60, 
74th Cong., 1st Sess. 
H. Doc. 444, 
82nd Cong., 2nd 
Sess. 
H. Doc. 185, 
72nd Cong., 1st Sess. 
H. Doc. 286, 
89th Cong., 1st Sess. 
State Design 
memorandum 
July 2, 1986 
River and Harbor Act, 
June 29, 1888 as 
amended by Public 
Law 85-802, dated 
August 28, 1958 
Detailed Project 
Report, 
June 1981 
H. Doc. 51, 
82nd Cong., 1st Sess.1 
Detailed Project 
Report, 
February 1968 
H. Doc. 671, 
80th Cong., 2nd 
Sess. 
H. Doc. 87, 
62nd Cong., 1st Sess. 
4-30 
14. 
15. 
16. 
18. 
19.

BALTIMORE, MD DISTRICT 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
20. 
24. 
Sep. 19, 
1890 
Jun. 25, 
1910 
Mar. 2, 
1919 
Jul. 3, 
1930 
WICOMICO RIVER, MD 
Channel 9 feet deep from Main Street Bridge to about 2 miles below. 
Extend 9-foot depth into north prong from Main Street Bridge to the 
Salisbury Dam and turning basin. 
Extend 9-foot depth into south prong to head of navigation at Cathell Street, 
including a turning basin, and extend project down to mouth of river in 
Monie Bay. 
A 12-foot channel below the Main Street Bridge. 
TRED AVON RIVER, MD 
Jul. 25, Restore the channel, formerly dredged from Peach Blossom Creek to Easton 
1912 Point, to 8 feet deep at mean low water, and 150 feet wide, widening out 
at the upper end. 
Mar. 2, A channel 8 feet deep and 150 feet wide up the North Fork, with a turning 
1919 basin at the upper end. 
Oct. 27, A 12-foot channel from a point near Peach Blossom Creek to Easton Point, 
1965 thence 1,400 feet in North Fork and a turning basin 12 feet deep and 250 
feet wide and 600 feet long in the South Fork. 
TWITCH COVE AND BIG THOROFARE, MD 
Jul. 25, A channel 4 feet deep and 25 feet wide from Tangier Sound into Big 
1912 Thorofare River, and one of same dimensions around point between said 
river and Tyler River. 
Jul. 3, A channel 5 feet deep at mean low water and 25 feet wide from Twitch 
1930 Cove on Tangier Sound through Big Thorofare River to a point on Levering 
Creek about 800 feet north of canal at Ewell, MD. 
Aug. 30, A channel 7 feet deep and 60 feet wide from Twitch Cove through Big 
1935 Thorofare River to a point on Levering Creek about 800 feet north of 
canal at Ewell, MD. 
Jun. 20, Present project dimensions of main channel with twin jetties at entrance. 
1938 
May 17, Anchorage basin 7 feet deep, 100 feet wide and 700 feet long on west side 
1950 of project channel at Ewell, MD, and an extension of existing project 
channel in Levering Creek, 6 feet deep, 60 feet wide, and 1,000 feet long. 
UPPER THOROFARE, DEAL ISLAND, MD 
Aug. 30, A 9-foot channel 75 feet wide protected by breakwater at entrance, with 
1935 turning basin at inner end and anchorage area 6 feet deep and 150 feet 
wide. 
Aug. 26, Widen entrance channel to 100 feet, extend 9-foot turning basin and 6-foot 
1937 anchorage, and dredging an additional anchorage area on north side of 
channel. 
WASHINGTON HARBOR, DC 
Aug. 30, Provides for: (a) Virginia Channel, from Giesboro Point to area for 25,000 
1935 square feet; (b) Washington Channel, from Haines Point to head of Washington 
Channel, 24 feet deep and 400 feet wide; (c) Anacostia River from 
Giesboro Point to Anacostia Bridge, 24 feet deep and 400 feet wide, with 
turning basin 800 feet wide and about 2,400 feet long of same depth opposite 
Naval Weapons Plant; (d) Anacostia River from Anacostia Bridge 24 feet 
deep and 200 feet wide to turning basin 400 feet square of same depth at 
foot of 15th Street SE Channel lengths including turning basins are: Virginia 
Channel, 25,000 feet; Washington Channel, 10,000 feet; and Anacostia River, 
15,000 feet; and (e) operation and maintenance of inlet gates and lock and 
outlet gates of Tidal Basin constructed under a previous project to flush 
Washington Channel. 
4-31 
21. 
H. Doc. 399, 
62nd Cong., 2nd Sess.' 
H. Doc. 26, 
63rd Cong., 1st Sess.' 
H. Doc. 225, 
89th Cong., 1st Sess.' 
H. Doc. 285, 
62nd Cong., 2nd Sess. 
H. Doc. 313, 
71st Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 67, 
74th Cong., 1st Sess. 
Rivers & Harbors 
Committee Doc. 49, 
75th Cong., 2nd Sess.' 
H. Doc. 340, 
81st Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 37, 
72nd Cong., 1st Sess. 
H. Doc. 76, 
75th Cong., 1st Sess.' 
Rivers and Harbors 
Committee Doc. 22, 
74th Cong., 1st Sess.' 
H. Doc. 20, 
51st Cong., 1st Sess., 
and Annual Report 
1890, p. 947, 
H. Doc. 569, 
61st Cong., 2nd Sess. 
H. Doc. 1509, 
63rd Cong., 3rd Sess. 
22. 
23.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug. 26, A 14-foot channel, 150 feet wide; depths of 14 feet in the north and south 
1937 prongs and a basin 6 feet deep at Webster Cove and approach channel 
thereto of the same depth. 
Sep. 3, Enlarge existing basin at Webster Cove, by dredging an extension 6 feet 
1954 deep, 100 feet wide, and 200 feet long on each side of existing basin to 
form a T-shaped harbor. 
COLONIAL BEACH, VA 
Sep. 15, Extending and widening the existing Central Beach area, stabilizing the 
1980 bank behind the beachfill with vegetation, and constructing four segments 
of offshore breakwater; and extending and widening of the existing Castle 
Beach area, constructing three segments of offshore breakwater, removing 
debris in the beachfill area, and constructing a 100-foot long terminal groin 
at the southern end of Castlewood Park beachfill. 
Oct. 23, 
1962 
Jun. 22, 
1936 
Jul. 24, 
1946 
BLOOMINGTON LAKE, MD & WV 
Construction of Bloomington Lake project. 
Senate Committee 
Print, 75th Cong., 
3rd Sess.1 
H. Doc. 619, 
81st Cong., 2nd Sess. 
Detailed Project 
Report, May 1980 
H. Doc. 469, 
87th Cong., 2nd 
Sess. 
CUMBERLAND, MD AND RIDGELEY, WV 
Levees, retaining walls, movable dam, and channel clearing for Cumberland, 
West Cumberland and South Cumberland, MD and Ridgeley, WV. 
Levees, wall, channel improvement, remove Chesapeake and Ohio Canal 
Dam and construct new industrial dam. 
LACKAWANNA RIVER BASIN, PA 
Oct. 23, Construction of Aylesworth Creek Lake, Fall Brook Lake, and local pro- 
1962 tection works on Lackawanna River at Scranton, Pennsylvania. 
Oct.23, 
1962 
Jun. 22, 
1936 
modified 
by Acts 
of Jun. 
28, 1938; 
Aug. 18, 
1941; 
Dec. 22, 
1944; 
May 17, 
1950; and 
Jul. 3, 
1958 
Aug. 18, 
1941 
RAYSTOWN LAKE, RAYSTOWN BRANCH, JUNIATA RIVER, PA 
Construction of dam and appurtenant facilities. 
SOUTHERN NEW YORK FLOOD CONTROL PROJECTS 
Construction of detention reservoirs and related flood control works for 
protection of Binghamton, Hornell, Corning and other towns in New York 
and Pennsylvania. 
STILLWATER LAKE, LACKAWANNA RIVER, PA 
Construction of a flood control reservoir. 
SUSQUEHANNA RIVER FLOOD CONTROL PROJECTS, NY AND PA 
Jul. 3, Construction of Cowanesque and Tioga-Hammond reservoirs, local flood 
1958 protection works at Elkland, PA, and Nichols, NY and channel improvement 
at Cortland, NY. 
Oct. 22, Modification in connection with the construction of Cowanesque Lake to 
1976 relocate the Town of Nelson, PA, to a new townsite. 
Mar. 1, Modification of Cowanesque Lake to include water supply as provided by 
1983 Section 4 of the Flood Control Act of 1944 (PL 78-534) and Section 301 of 
Water Supply Act of 1958 (PL 85-500). 
H. Doc. 101, 
73rd Cong., 1st Sess. 
Report on file in 
Office, Chief of 
Engineers. 
S. Doc. 141, 
87th Cong., 2nd Sess. 
H. Doc. 565, 
87th Cong., 2nd Sess. 
H. Doc. 702, 
77th Cong., 2nd Sess. 
H. Doc. 702, 
77th Cong., 2nd Sess. 
H. Doc. 394, 
84th Cong., 2nd Sess. 
4-32 
27. 
29. 
30. 
31. 
32. 
33. 
34. 
35.

BALTIMORE, MD DISTRICT 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
36. WEST BRANCH OF SUSQUEHANNA RIVER, PA 
Sep. 3, Construction of three flood control reservoirs. H. Doc. 29, 
1954 84th Cong., 1st Sess. 
37. WYOMING VALLEY, PA 
Jun. 22, Construction of a levee and flood wall protection system with associated H. Doc. 308, 
1936 interior drainage facilities at Plymouth, Kingston-Edwardsville, Swoyersville- 69th Cong. 1st Sess. 
Forty Fort, and Wilkes-Barre and Hanover Township. 
38. YORK, INDIAN ROCK DAM, PA 
Jun. 22, Construction of Indian Rock Dam and channel improvements on Codorus H. Doc. 702, 
1936 Creek. 77th Cong., 2nd Sess. 
1. Contains latest published maps. September 16, 1933. The site chosen for the inlet under this 
2. Exclusive of portion considered inactive. Inactive por- authorization was that opened just south of Ocean City by 
tion is widening 35-foot depth channel from 150 to 400 feet from natural forces during a severe storm in August 1933. This 
Port Covington to Ferry Bar, widening 27-foot depth channel eliminated the necessity for an 8-foot channel from the inlet to 
from 150 to 250 feet to Hanover Street Bridge, and providing Ocean City. 
a channel 27 feet deep by 250 feet wide to Western Maryland 4. Included in Emergency Relief program 1935. 
Railway Bridge with an anchorage and turning basin at the 5. Raising of the north jetty to an elevation of 9 feet above 
upper end. mean low water was accomplished with maintenance funds in 
3. Included in Public Works Administration program 1956. 
OTHER AUTHORIZED NAVIGATION PROJECTS 
TABLE 4-C 
Cost to September 30, 1986 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Accotink Creek, VA' 
Anacostia River and Flats 2 
Annapolis Harbor, MD 
Aquia Creek, VA 
Back Creek, MD 
Betterton Harbor, MD 
Black Walnut Harbor, MD 
Bonum Creek, VA' 
Branson Cove, 
Lower Machodoc River, VA 
Breton Bay, MD7 
Broad Creek River, DE 
Broad Creek, MD 
Cambridge Harbor, MD7 
Choptank River, MD" 
Corsica River, MD 
Crisfield Harbor, MD 
Cypress Creek, MD 
Completed 
Deferred 
Completed 
Inactive 
Completed 
Inactive 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
1878 
1953 
1946 
1928 
1946 
1960 
1982 
1982 
1950 
1950 
1964 
1962 
1984 
1979 
1948 
1980 
1947 
$ 5,000 
3,910,582 
34,2503 
52,4654 
23,061 
3,482 
32,631 
202,0006 
15,755 
47,9248 
64,5109 
28,227 
195,97410 
96,796 
39,07112 
349,15413 
3,057 
15,623 
11,770 
23,072 
412,349 
144,576 
17,675 
12,621 
114,373 
81,219 
678,258 
94,095 
80,285 
551,62314 
10,528 
4-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED NAVIGATION PROJECTS 
TABLE 4-C (Continued) 
Cost to September 30, 1986 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Duck Point Cove, MD Completed 1982 25,289 293,964 
Elk and Little Elk Rivers, MD'5 Completed 1932 90,12116 53,80817 
Fishing Bay, MD Completed 1985 33,874 705,652 
Goose Creek, MD5 Completed 1973 75,900 8,312 
Honga River and Tar Bay 
(Barren Island Gaps), MD Completed 1985 66,11918 2,998,926 
Island Creek, MD Completed 1948 6,230 54,828 
Knapps Narrows, MD Completed 1985 46,12119 553,075 
La Trappe, MD Completed 1980 8,064 40,475 
Little Creek, Kent Island, MD Completed 1958 23,00020 7,327 
Lower Machodoc Creek, VA Completed 1904 9,916 16,485 
Madison Bay, MD5 Completed 1977 125,550 20,854 
Manokin River, MD2
1 Completed 1919 34,78822 43,534 
Middle River and Dark Head Creek, MD Completed 1947 38,71523 23,173 
Monroe Bay and Creek, VA Completed 1982 12,460 207,685 
Muddy Hook and Tyler Coves, MD5 Completed 1984 64,001 388,928 
Nan Cove, MD5 Completed 1965 34,86124 22,498 
Nanticoke River at Bivalve, MD'5 Completed 1983 240,817 131,878 
Nanticoke River (Including 
Northwest Fork), DE & MD Completed 1984 143,13425 584,777 
Nanticoke River, MD Completed 1971 73,243 76,89526 
Neabsco Creek, MD Inactive 1978 14,600 - 
Neale Sound, MD Completed 1982 12,60027 289,770 
Neavitt Harbor, MD5 Completed 1968 36,500 28,084 
Nomini Bay and Creek, VA28 Completed 1946 78,446 42,063 
Northeast River, MD Completed 1984 28,48929 905,044 
Occoquan Creek, VA15 Completed 1971 66,25330 176,920 
Patuxent River, MD 15 Completed 1905 14,000' - 
Pocomoke River, MD Inactive 1985 191,72632 1,537,535 
Potomac River and Tributaries at and 
below Washington, DC, Elimination 
of Waterchestnut Completed 1977 - 184,394 
Potomac River at Alexandria, VA Completed 1965 95,214 506,394 
Potomac River at Lower Cedar Point, MD Completed 1920 10,234 6,216 
Potomac River at Mt. Vernon, VA'5 Completed 1984 $ 17,000 306,574 
Potomac River below Washington, DC Completed 1984 153,836 1,876,673 
Potomac River North Side 
of Washington Channel, DC' Completed 1956 1,744,69293 27,46126 
Queenstown Harbor, MD Completed 1985 72,85894 321,803 
Rock Hall Harbor, MD Completed 1982 1,072,50096 77,113 
Shad Landing State Park, MD Completed 1966 33,53136 6,719 
St. Catherines Sound, MD Completed 1981 29,94797 271,618 
St. Georges Creek, MD Completed 1985 132,850 - 
St. Jeromes Creek, MD Completed 1982 44,35738 400,243 
St. Michaels Harbor, MD 5 Completed 1964 16,723"7 7,742 
St. Peters Creek, MD5 Completed 1963 46,740"9 17,084 
Smith Creek, MD Completed 1936 5,252 8,551 
Susquehanna River 
above and below Havre De Grace, MD Completed 1985 293,57040 929,018 
Susquehanna River at Williamsport, PA5 Completed 1974 57,0314' 41,437 
Tilghman Island Harbor, MD Completed 1983 424,80042 378,783 
Town Creek, MD Completed 1950 43,220 29,368 
Tuckahoe River, MD Completed 1980 9,727 23,489 
Tyaskin Creek, MD Completed 1923 16,297** 45,295 
Upper Machodoc Creek, VA Completed 1971 20,281 34,777 
Warwick River, MD Completed 1984 22,041" 145,911 
4-34

BALTIMORE, MD DISTRICT 
1. Unconstructed portion of the project was deauthorized 
August 5, 1977. 
2. Project deferred for restudy. 
3. Includes $8,476 for previous project. 
4. Includes $31,065 for previous project. 
5. Authorized by Chief of Engineers. 
6. Unconstructed portion of the project is inactive. 
7. Excludes $3,998 contributed funds. 
8. Includes $37,500 for previous project. 
9. Includes $50,000 for previous project. 
10. Includes $61,321 for previous project. 
11. Authorization for the unconstructed portion of the 
project was withdrawn by the Chief of Engineers January 
22, 1979. 
12. Includes $30,000 for previous project. 
13. Includes $87,740 for previous project. 
14. Includes $2,839 for previous project. 
15. Unconstructed portion of the project was deauthorized 
November 2, 1979. 
16. Includes $79,626 for previous project and excludes 
$8,414 contributed funds. 
17. Includes $24,321 for previous project. 
18. Excludes $2,200 contributed includes $27,668 emergency 
relief funds. 
19. Includes $46,121 public works funds. 
20. Excludes $1,100 contributed funds. 
21. Abandonment recommended in 1926 (H. Doc. 467, 69th 
Cong., 1st sess.) 
22. Includes $2,000 expended outside project limits. 
23. Excludes $111,581 expended by Navy Department and 
$54,000 from contributed funds. 
24. Excludes $565 contributed funds. 
25. Includes $5,000 for previous project. 
26. Excludes $101,162 Public Health Service funds expended 
for waterchestnut removal. 
27. Excludes $1,000 contributed funds. 
28. Unconstructed portion of the project was deauthorized 
November 6, 1977. 
29. Includes $20,640 for previous project. 
30. Includes $25,000 for previous project. 
31. Includes $10,617 for previous project. 
32. Unconstructed portion of the project is inactive. Includes 
$20,500 for previous project. 
33. Excludes $389,000 contributed funds. 
34. Includes $19,000 for previous project. 
35. Excludes $672,880 contributed funds. 
36. Excludes $24,125 contributed funds. 
37. Excludes $600 contributed funds. 
38. Includes $26,500 for previous project. 
39. Excludes $6,984 contributed funds. 
40. Unconstructed portion of the project was deauthorized 
November 6, 1977. Includes $22,905 Works Progress funds and 
$97,390 for previos project. 
41. Excludes $40,000 contributed funds. 
42. Excludes $16,409 contributed funds. 
43. Includes $10,158 for previous project. 
44. Includes $6,000 for previous project. 
OTHER AUTHORIZED BEACH 
TABLE 4-D EROSION CONTROL PROJECTS 
Cost to September 30, 1986 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Oxford, MD' Completed 1978 $ 97,7502 
1. Authorized by Chief of Engineers. 
2. Excludes $80,648 contributed funds. 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
TABLE 4-E 
Cost to September 30, 1986 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Anacostia River and Tributaries, Flood Protection 
and Navigation Improvements, DC and MD 
Anacostia River and Tributaries, 
Prince Georges Co., MD 2 
Bainbridge, NY' 4 
Completed 
Completed 
Completed 
1980 
1977 
1959 
$ 6,042,325 
1,000,0003 
382,000 
$1,417,655 
4-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
TABLE 4-E (Continued) 
Cost to September 30, 1986 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Bath, NY5 Completed 1970 638,332 - 
Bayard, WV4 Completed 1965 55,2186 - 
Black Walnut Point, MD Completed 1985 200,500 - 
Bridgewater, VA4 Completed 1953 136,500 - 
Bull Run, PA Completed 1984 2,742,000 - 
Conklin-Kirkwood, NY4 Completed 1955 71,000 - 
Cortland, NY' Completed 1970 324,486 - 
Elkland, PA Completed 1971 1,297,850 - 
Endicott Johnson City and Vestal, NY Completed 1979 7,034,5348 - 
Forest Heights, MD4 Completed 1964 430,0009 - 
Fourmile Run, VA Completed 1984 51,780,000 - 
Greene, NY4 Completed 1951 37,000 - 
Kingston-Edwardsville, PA Completed 1979 4,731,3941� - 
Kitzmiller, MD4 Completed 1965 501,50011 - 
Latta Brook Rd., NY Completed 1984 115,500 - 
Lock Haven, PA' 2 Active 1980 450,000" - 
Nichols, NY Completed 1974 1,487,800 - 
Norwich, NY4 Completed 1950 94,500 - 
Painted Post, NY5 Completed 1970 414,181 - 
Plymouth, PA Completed 1958 1,911,689" - 
Savage River Dam, MD Completed 1954 2,271,939" 33,999 
Scranton, PA'6 Completed 1971 2,006,800 - 
Sunbury, PA Completed 1953 6,063,000 7 - 
Swoyersville-Forty Fort, PA Completed 1968 2,728,113 - 
Tyrone, PA' 8 Deferred 1980 6,401,016 - 
Unadilla, NY Completed 1970 1,000,00019 - 
Upper Marlboro, MD4 Completed 1965 590,013 - 
Verona Lake, VA20 Deferred 1978 992,000 - 
Washington, DC and Vicinity Completed 1953 331,92721 - 
Wilkes-Barre, Hanover Township, PA Completed 1958 3,853,45722 - 
Williamsport, PA Completed 1979 12,964,8932s - 
1. Local interests will not accept operation and maintenance 
responsibility of the project until the severe erosion 
and sedimentation of the project caused by tropical storm Eloise 
is corrected and the project is restored to design condition. 
2. Excludes $357,022 contributed funds. 
3. Authorized by Chief of Engineers. 
4. Unit of Southern New York Flood Control Projects. 
5. Excludes $182,672 Public Works Acceleration funds 
and $4,290 contributed funds. 
6. Unit of Susquehanna River Flood Control Projects. 
7. Excludes $154,694 contributed funds. 
8. Excludes $87,720 contributed funds. 
9. Includes $1,162,548 emergency relief funds and excludes 
$225,877 emergency relief funds expended prior to adoption 
of project. 
10. Excludes $6,616 contributed funds. 
11. Authorized for Phase I design memorandum stage of 
advanced engineering and design. 
12. Excludes $481,000 for Phase I funded under General 
Investigations beginning October 1, 1978. 
13. Includes $4,357 emergency relief funds. 
14. Includes $200,000 expended from contributed funds. 
15. Unit of Lackawanna River Basin Projects. 
16. Excludes $140,504 contributed funds. 
17. The unconstructed portion of the project was reclassified 
to the deferred category January 8, 1981. 
18. Excludes $132,578 contributed funds. 
19. Authorized for the design memorandum stage of advanced 
engineering and design. 
20. Cost of previous project. Includes $106,500 emergency 
relief funds. 
21. Includes $872,715 emergency relief funds. Excludes 
$36,375 emergency relief funds expended for new work before 
adoption of project. 
22. Includes $1,887 emergency relief funds and excludes 
$110,835 contributed funds. 
4-36

BALTIMORE, MD DISTRICT 
DEAUTHORIZED PROJECTS 
TABLE 4-G 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Almond Village, NY1' 2 
Broadwater Creek, MD 
Cadle Creek, MD2 
Channel Connecting Plain 
Dealing Creek and Oak 
Creek, MD 
Coan River, VA 
Copes Corner Lakes, NY2 
Cuckold Creek, MD4 
Cunninghill Cove, MD' 
Davenport Center Lake, NY 2 
Fall Brook Lake, PA5 
Genegantslet Lake, NY 
1970 
1949 
1949 
1940 
1937 
1970 
1978 
1977 
1970 
1970 
1954 
1950 
1937 
1950 
1950 
1949 
1941 
1971 
Governors Run, MD 
Harpers Ferry, WV 
Hellens Creek, MD 
Lake Ogleton, MD 
Mill Creek, MD 
Moorefield, WV 
Saint Georges Creek, MD 
May 26, 1953 
1941 Flood 
Control Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1914 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
Jan. 22, 1979 
1960 River 
and Harbor Act 
Jan. 22, 1979 
1960 River 
and Harbor Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Oct. 3, 1978 
1974 Water 
Res. Dev. Act 
Sep. 23, 1986 
1974 Water 
Res. Dev. Act 
4-37 
$ 24,622$ 
212 
112 
106,7003 
5,720 
11,200 
286,4003 
46,100 
214,5783 
7,9283

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
DEAUTHORIZED PROJECTS 
TABLE 4-G (Continued) 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Sixes Bridge Lake, MD & PA6 1974 Dec. 29, 1981 $ -- 
1974 Water 
Res. Dev. Act 
South Plymouth Lake, NY 1953 May 6, 1981 100,0363 
1974 Water 
Res. Dev. Act 
Waterway from Little Choptank River to 1939 Aug. 5, 1977 305- 
Choptank River, MD 1974 Water 
Res. Dev. Act 
West Oneonta Lake, NY 2 1970 May 6, 1981 189,100- 
1974 Water 
Res. Dev. Act 
1. Local cooperation withdrawn, project authorization 5. Unit of Lackawanna River Basin Projects. 
expired May 26, 1953. 6. Authorized for the design memorandum stage of ad- 
2. Unit of Southern New York Flood Control Projects. vanced engineering and design. 
3. Cost for preliminary work only. 
4. Project authorization was withdrawn by the Chief of 
Engineers. 
RECONNAISSANCE AND CONDITION SURVEYS 
TABLE 4-H 
Date Survey 
Project Completed 
MARYLAND 
Crisfield Harbor April 1986 
Island Creek May 1986 
Muddy Hook & Tyler Cove August 1986 
Smith Creek October 1985 
St. Catherines Sound May 1986 
St. Jerome Creek November 1985 
Town Creek October 1985 
4-38

BALTIMORE, MD DISTRICT 
INSPECTION OF COMPLETED PROJECTS 
TABLE 4-I 
Date Inspected 
DISTRICT OF COLUMBIA 
Anacostia River 
Washington, DC & Vicinity 
MARYLAND 
Anacostia River Basin 
Cumberland 
Forest Heights 
Kitzmiller 
Savage 
Upper Marlboro 
NEW YORK 
Bainbridge 
Bath 
Cincinnatus 
Conklin-Kirkwood 
Corning-Monkey Run 
Cortland 
Endicott-Johnson City & Vestal 
Greene 
Nichols 
Norwich 
Oneonta 
Owego 
Painted Post 
Port Dickinson 
Sherburne 
Unadilla 
PENNSYLVANIA 
Elkland 
Kingston-Edwardsville 
Loyalsock 
Milton 
Plymouth 
Scranton 
Sunbury 
Swoyersville-Forty Fort 
Tyrone 
Wilkes-Barre-Hanover Twp. 
Williamsport 
S. Williamsport 
VIRGINIA 
Bridgewater 
Fourmile Run 
WEST VIRGINIA 
Bayard 
Ridgeley 
September 1986 
September 1986 
November 1985 
September 1986 
November 1985 
September 1986 
September 1986 
November 1985 
October 
October 
October 
October 
October 
October 
October 
October 
October 
October 
October 
October 
October 
October 
October 
October 
1985 
1985 
1985 
1985 
1985 
1985 
1985 
1985 
1985 
1985 
1985 
1985 
1985 
1985 
1985 
1985 
October 1985 
September 1986 
October 1985 
September 1986 
September 1986 
October 1985 
September 1986 
September 1986 
October 1985 
September 1986 
October 1985 
October 1985 
September 1986 
September 1986 
September 1986 
September 1986 
4-39 
Project 
a

NORFOLK, VA DISTRICT * 
Thfs district comprises the State of Virginia, except the 
Potomac, Roanoke and Ohio River Basins; the entire area 
on the eastern shore of Virginia except for the project for 
Pocomoke River, Maryland and Virginia. On the west shore 
of Chesapeake Bay, all waterways south of Smith Point, 
Virginia, at the mouth of the Potomac River except the 
project for Little Wicomico River, Virginia. North Carolina, 
only the Chowan River Basin downstream to and including 
the mouth of the Meherrin River, and the Dismal Swamp 
Canal Route of the Atlantic Intracoastal Waterway to the 
Albemarle Sound. West Virginia, only the James River 
Basin. 
IMPROVEMENTS 
NAVIGATION PAGE 
1. Atlantic Intracoastal 
Waterway between Norfolk, VA 
and St. Johns River, FL........................................5-2 
2. Baltimore Harbor and 
Channels (Norfolk District) .................................. 5-2 
3. Broad Creek, VA ..................................................... 5-3 
4. Cape Charles City Harbor, VA ............................ 5-3 
5. Chincoteague Inlet, VA.........................................5-4 
6. Cranes Creek, VA ................................................... 5-4 
7. Greenvale Creek, VA ........................................... 5-4 
8. Hampton Roads and Harbors 
of Norfolk and Newport News, VA 
Collection and Removal 
of D rift ...................................................................... 5-4 
9. Jam es River, VA ..................................................... 5-5 
10. Little Machipongo River, VA...............................5-5 
11. Norfolk Harbor, VA .............................................. 5-6 
12. Nottaway River, VA..............................................5-7 
13. Parker Creek, VA ................................................... 5-7 
14. Quinby Creek, VA ................................................. 5-7 
15. Supervision of Harbor of 
Hampton Roads 
(Prevention of Obstructive & 
Injurios D eposits) .................................................... 5-8 
16. Tangier Channel, VA............................................5-8 
17. Waterway on the Coast of VA.............................5-8 
18. York River, VA...................................................5-9 
19. Navigation Work Under 
Special Authorization.................................... ..... 5-9 
BEACH EROSION CONTROL 
20. Virginia Beach, VA...............................................5-9 
21. Beach Erosion Control Work 
Under Special Authorization................................5-9 
FLOOD CONTROL PAGE 
22. Gathright Dam and 
Lake M oom aw, VA ............................................... 5-10 
23. Richm ond, VA ...................................................... 5-10 
24. Saxis Island, V A ................................................... 5-11 
25. Scottsville, V A ...................................................... 5-12 
26. Virginia Beach Canal 
N um ber 2, V A ....................................................... 5-12 
27. Flood Control Work 
Under Special Authorization...............................5-12 
28. Emergency Flood Control 
A ctivities ................................................................ 5-12 
GENERAL INVESTIGATIONS 
29. Surveys .................................................................. 5-12 
30. Collection and Study of 
B asic D ata ............................................................. 5-13 
31. Continuation of Planning 
and Engineering ................................................... 5-13 
TABLES 
Table 5-A Cost and Financial Statement ..... 5-14 
Table 5-B Authorizing Legislation .......... 5-18 
Table 5-C Data Relative to the 
Completed Locks ................. 5-21 
Table 5-D Other Authorized Navigation 
Projects..........................5-22 
Table 5-E Other Authorized Beach Erosion 
Control Projects .................. 5-23 
Table 5-F Other Authorized Flood 
Control Projects .................. 5-23 
Table 5-G Reconnaissance and Condition 
Surveys ........................... 5-24 
5-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 19886 
Navigation 
1. ATLANTIC INTRACOASTAL 
WATERWAY BETWEEN 
NORFOLK, VA AND ST. 
JOHNS RIVER, FL 
(NORFOLK DISTRICT) 
Location. Two inland water routes approximately paralleling 
Atlantic coast south of Norfolk, VA between a point in 
Southern Branch of Elizabeth River, VA, 2,500 feet upstream 
of Norfolk & Western Railway bridge and Virginia-North 
Carolina state line in North Landing River, a distance of 
27.2 miles; and 64.6 miles between mouth of Deep Creek, 
VA and mouth of Pasquotank River, NC. These routes are 
shown on National Ocean Survey. Chart 12206. 
Existing project. A channel 12 feet deep at mean low 
water and 90 to 250 feet wide following Southern Branch of 
Elizabeth River, 5.2 miles, Virginia Land Cut, 8.3 miles, and 
North Landing River, 13.7 miles; and construction of tidal 
guard lock at Great Bridge, VA. It also provides channels 10 
feet deep at mean low water and 90 to 100 feet wide in Deep 
Creek, 3.1 miles, Turners Cut, 4.3 miles and Pasquotank 
River, 35.1 miles; maintaining Dismal Swamp Canal, 22.1 
miles, to about 9 feet deep mean canal level over a width of 
50 feet; protection of banks in Turners Cut with sheet piling, 
and cutting certain sharp points in Pasquotank River to 
shorten its course. (See Table 5-C at end of chapter on Data 
Relative to Completed Locks included in Project.) 
Project includes operating and care of completed locks, 
dams and bridges, under maintenance. Southern Branch of 
Elizabeth River and Deep Creek sections of the two routes 
are tidal, mean range being about 3 feet with extremes of 
minus 3.5 and plus 9.6 feet. Remaining sections are nontidal 
with fluctuations of 1 to 2 feet in level due to winds. Cost for 
new work for completed project was $3,396,276. Protection 
to canal property at Great Bridge portion is considered 
inactive and excluded from foregoing cost. Estimated cost 
of this portion (1954) is $265,000. For details of previous 
projects, see page 476 of Annual Report for 1938. (See 
Table 5-B for Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. Existing facilities are considered 
adequate. See Annual Report for 1970. 
Operations during fiscal year. Maintenance: 
Work on a 5-year maintenance and repair contract is 
progressing satisfactorly. Work is continuing on the 
spare lock gates located at Great Bridge, VA. 
Contract was awarded Feb. '83 at $4,117,981. Maintenance 
dredging the lower North Landing River 
was accomplished Jan. 9-24, 1986. There were 58,420 
cubic yards of material removed at a direct cost of 
$298,490. Other work performed included ordinary 
operation and maintenance of locks, dams and 
service facilities, engineering and design and 
supervision and administration. 
2. BALTIMORE HARBOR 
AND CHANNELS 
(NORFOLK DISTRICT) 
Existing project. Provides for deep water approach 
channels in Baltimore Harbor. Northern portion including 
Baltimore Harbor is under jurisdiction of Baltimore District. 
Portion under jurisdiction of Norfolk District is more fully 
described below. 
2A. CAPE HENRY CHANNEL, VA 
Location. A t mouth of Chesapeake Bay opposite Cape 
Henry. (See National Ocean Survey Chart No. 12222.) 
Existing project. A channel about 2.3 miles long, 1,000 
feet wide, and 50 feet deep at mean low water through shoal 
at mouth of Chesapeake Bay opposite Cape Henry. Under 
ordinary conditions mean range of tide 2.5 feet and extreme 
3 feet. Extremes of irregular fluctuation due to combined 
effect of wind and tides, referred to mean low water, are 
minus 2 feet and plus 9.5 feet. (See Table 5-B for Authorizing 
Legislation.) 
2B. RAPPAHANNOCK SHOAL 
CHANNEL, VA 
Location. In lower Chesapeake Bay opposite mouth of 
Rappahannock River and about 50 miles northerly from 
Atlantic Ocean at entrance of Chesapeake Bay. (See 
National Ocean Survey Chart No. 12225.) 
Existing project. A channel about 9.9 miles long, 1,000 
feet wide, and 50 feet deep at mean low water between 
contours of that depth in Chesapeake Bay, opposite 
Rappahannock River. Under ordinary conditions mean tidal 
range is 2.5 feet and extreme 3 feet. Extremes of irregular 
fluctuation due to combined effect of wind and tides, 
referred to mean low water, are minus 2 feet and plus 9.5 
feet. (See Table 5-B for Authorizing Legislation.) 
2C. YORK SPIT CHANNEL, VA 
Location. In lower Chesapeake Bay opposite mouth of 
York River and about 20 miles northerly from Atlantic 
Ocean at entrance of Chesapeake Bay. (See National Ocean 
Survey Chart No. 12221). 
5-2

NORFOLK, VA DISTRICT 
Existing project. A channel about 18.2 miles long, 1,000 
feet wide, and 50 feet deep at mean low water between 
contours of that depth in Chesapeake Bay opposite York 
Spit. Under ordinary conditions mean tidal range is 2.5 feet 
and extreme 3 feet. Extremes of irregular fluctuation, due to 
combined effect of wind and tides, referred to mean low 
water, are minus 2 feet and plus 9.5 feet. For details of 
previous projects see Annual Report for 1932. (See Table 5- 
B for Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. These three channels form the 
access between lower and upper Chesapeake Bay. 
Operations during fiscal year. Maintenance: 
Dredging was performed by Hopper Dredge 
McFarland during Mar. 1-26, 1986. There were 75,036 
cubic yards of credited material removed at a total 
direct cost of $900,550. Other operations performed 
included condition studies, engineering and design 
and supervision and inspections. 
3. BROAD CREEK, VA 
Location. Broad Creek is a small tidal estuary in Middlesex 
County, VA, 1 mile long, flowing in a northerly direction into 
the Rappahannock River, which it enters on the right bank 
about 1 mile upstream of its mouth at Chesapeake Bay. The 
creek is 61 miles northerly of Norfolk, VA. (See National 
Ocean Survey Chart No. 12235). 
Existing project. This provides for a channel 7 feet 
deep, 100 feet wide and 4,100 feet long from deep water in 
the Rappahannock River to deep water in Broad Creek. The 
plane of reference is mean low water. The tidal ranges are: 
Mean, 1.2 feet; irregular, 2 feet; and extreme, approximately 
7.5 feet. 
The cost to the Federal Government for new work for the 
completed project was $27,888. 
The existing project was adopted by the River and 
Harbor Act of March 2, 1945 (H. Doc. 381, 76th Cong., 1st 
sess.). The latest published map is in the project document. 
Local cooperation. Fully complied with except that 
local interests shall furnish, free of cost to the United States, 
suitable spoil-disposal areas when and as required for 
subsequent maintenance, and hold and save the United 
States free from claims for damages that may result from 
dredging. 
Terminal facilities. There are privately owned wharves 
and landings on the creek, many of which are open to the 
public by special arrangements. There is one marine railway 
on the creek. The terminal facilities are considered adequate 
for present commerce. 
Operations during fiscal year. Maintenance: 
Dredging was performed to remove material that 
had flowed out of the disposal area into Big Lake. 
Work was accomplished by contract at a total cost of 
$36,500. 
4. CAPE CHARLES CITY HARBOR, VA 
Location. Town of Cape Charles, VA is on 
Chesapeake Bay on west side of peninsula 
separating the bay from Atlantic Ocean. It is about 
11 miles north of southern extremity of peninsula 
and 45 miles south of Maryland-Virginia State line. 
Cape Charles City Harbor is an artificial landlocked 
harbor on south side of the town. (See 
National Ocean Survey Chart 12222). 
Existing project. A channel 18 feet deep and 500 
feet wide from that depth in Chesapeake Bay 
through Cherrystone Bar and inlet to the entrance to 
Cape Charles City Harbor, a distance of2.71 miles; a 
basin in the harbor of the same depth 400 to 800 feet 
wide and 3,000 feet long; a channel 10 feet deep, 100 
to 180 feet wide and 260 feet long connecting a basin 
of same depth 180 feet wide and 420 feet long at head 
of Mud Creek and a harbor of refuge on the north side 
of Mud Creek, 7 feet deep, 200 to 250 feet wide, and 
375 feet long connected to Mud Creek with an 
entrance channel 7 feet deep and 60 feet wide. Project 
also provides for protective works in form of a stone 
jetty on north side of harbor entrance and sand mole 
1,350 feet long south of harbor entrance. All depths 
are referred to mean low water. Mean tidal range is 
2.3 feet with extremes of 2.5 feet below and 8 feet 
above mean low water. Cost for new work for 
completed project was $628,644, including $6,000 
from contributed funds. Widening the basin an 
additional 200 feet is considered inactive and 
excluded from foregoing cost. Estimated cost of this 
portion (1954) is $207,000. 
Local Cooperation. Conditions imposed by 
River and Harbor Act of 1938 were fully complied 
with and approved by Chief of Engineers on March 
30,1940. The River and Harbor Act of 1945, in 
adopting existing project dimensions, imposed 
conditions that local interests provide all lands for 
initial construction and future maintenance; provide 
and maintain substantial bulkheads and other 
terminal facilities adequate to permit full utilization 
of improvement; and reserve at least 1,000 linear feet 
of berthinig space along such bulkheads for general 
public use on equal and reasonable terms; and agree 
to hold the United States free from damages. Local 
interests furnished all lands necessary for dredging 
harbor to 800-foot width. Items of local cooperation 
in connection with Harbor of refuge have been 
complied with. 
Terminal facilities. The Pennsylvania Railroad 
owns a wooden zkr 200 feet long and two transfer 
ships in the outer harbor. On the south side of the 
harbor, Bay Shore Concrete owns an 800-foot 
bulkhead. A bulkhead providing 200 feet of berthing 
space is on the south side of the main harbor and is 
owned by a fish plant. There are about 1400 feet of 
5-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
city-owned bulkhead open to the public. The Coast 
Guard owns a 100-foot pier on Mud Creek. The 
harbor of refuge should accomodate about 50 boats 
when berthing facilities are completed. 
Operations during fiscal year. Maintenance: 
Work performed consisted of condition surveys, 
engineering and design, supervision and 
inspections, budgeting and scheduling and work on 
a long term disposal study. 
5. CHINCOTEAGUE INLET, VA 
Location. Chincoteague Inlet at the southern end of 
Assateague Island provides access to the Atlantic Ocean 
from the inland waterway near the town of Chincoteague, 
VA. (See National Ocean Survey Chart No. 12211). 
Existing project. Provides for a channel 12 feet deep 
and 150 feet wide across the ocean bar in the Atlantic Ocean 
and to the mouth of the inlet, a channel 9 feet deep and 100 
feet wide from the inlet through the canal and then along 
Chincoteague Channel to a point approximately 2,000 feet 
north of the state highway bridge to Chincoteague, a 
distance of about 6.6 miles. Mean range of tide is about 3 
feet. All depths are referred to mean low water. (See Table 
5-B for Authorizing Legislation.) 
Local cooperation. For details see Annual Report for 
1974. 
Terminal facilities. Existing facilities at Chincoteague 
are considered adequate for current and prospective traffic. 
Operations during fiscal year. Maintenance: 
Work performed consisted of condition surveys, 
budgeting and scheduling, and engineering and 
design. 
6. CRANES CREEK, VA 
Location. Cranes Creek in Northumberland County, 
Virginia is a small tidal estuary approximately 2 miles long 
and entering the right bank of the Great Wicomico River 
2-1/2 miles upstream to the Chesapeake Bay. The creek is 
about 76 miles northerly from Norfolk, Virginia. (See Coast 
and Geodetic Chart No. 12235) 
Existing project. This provides for a channel 6 feet 
deep, 80 feet wide, and 1,500 feet long from deepwater in the 
Great Wicomico River to deepwater within Cranes Creek. 
The plane of reference is mean low water. The tidal ranges 
are mean 1.1 feet, irregular 2.0 feet, and extremes approximately 
7.2 feet. (See Table 5-B for Authorizing Legislation) 
Local cooperation. The existing project was approved 
subject to the conditions that local interest construct and 
maintain a public wharf with improved approach road, 
furnish spoil disposal areas for initial dredging, and subsequent 
maintenance when and as required and hold and 
save United States free from claims for damages resulting 
from the improvement. All conditions have been fully 
complied with. 
Terminal facilities: There are several small 
privately owned wharfs and landing on the creek 
which are considered adequate for present 
commerce. 
Operations during fiscal year. Maintenance: 
Dredging was performed between Oct. 6 - Nov. 12, 
1985, removing 17,000 cubic yards of material. In 
addition, dredging was performed between Mar. 10- 
Apr. 26, 1986 with 23,775 cubic yards of material 
being removed. Total direct cost amounted to 
$119,747. Other operations performed included 
quantity surveys, engineering and design, and 
supervision and inspections. 
7. GREENVALE CREEK, VA 
Location. A tidal estuary that enters the north 
side of Rappahannock River about 20 miles above its 
mouth. It is wholly in Lancaster County, Virginia 
about 60 miles north of Norfolk, Virginia. (See 
National Ocean Survey Chart No. 12237). 
Existing project. A channel 6 feet deep at mean 
low water and 60 feet wide from that depth in 
Rappahannock River about 950 feet to the mouth of 
Greenvale Creek, then 6 feet deep and 60 feet wide 
from the mouth into the creek for about 2,400 feet. 
(See Table 5-B for Authorizing Legislation). 
Local cooperation. Fully complied with. For 
details see Annual Report for 1965. 
Terminal facilities. Existing facilities are 
considered adequate. For details see page 215 of 
Annual Report, 1969. 
Operations during fiscal year. Maintenance: 
Dredging the mouth of the Creek was performed, by 
contract, at a cost of $29,216. There were 3,000 cubic 
yards of material removed. 
8. HAMPTON ROADS AND 
HARBOR OF NORFOLK AND 
NEWPORT NEWS, VIRGINIA 
COLLECTION AND REMOVAL 
OF DRIFT 
Location. Hampton Roads is a natural harbor 300 miles 
south of New York and 180 miles south of Washington, D.C. 
Its principal tributaries are James River, affording a 
natural deep harbor at Newport News, VA; Elizabeth River, 
with it Southern, Eastern, and Western Branches providing 
harbors for Norfolk and Portsmouth, VA; and Hampton 
Creek, serving the harbor at Hampton, VA. (See National 
Ocean Survey Charts No. 12248, 12245 and 12253) 
Existing project. Collection and removal of drift in 
Hampton Roads and its tributary waters authorizes the 
Secretary of the Army to allot necessary amounts of work 
from appropriations for maintenance and improvement of 
existing river and harbor works or from other available 
5-4

NORFOLK, VA DISTRICT 
appropriations and that this work shall be carried on as a 
separate and distinct project. It is wholly a work of maintenance. 
The purpose of work is to afford relief from variable 
conditions of obstruction. No advance estimate of the 
amount of work is required. (See Table 5-B for Authorizing 
legislation.) 
Local cooperation. None required. 
Terminal facilities. See Norfolk Harbor, VA and 
Channel to Newport News, VA. 
Operations during fiscal year. Maintenance: 
Operation of the project resulted in collection and 
disposal of 65,450 cubic feet of a variety of floating 
refuse. Operations were performed using 
government plant and hired labor. 
9. JAMES RIVER, VA 
Location. The river is formed by junction of the Cowpasture 
and Jackson Rivers in Botetourt County, VA, flows 
easterly 340 miles and empties into Hampton Roads at 
Newport News, VA. (See National Ocean Survey Charts No. 
12248 and 12251.) 
Existing project. A channel 35 feet deep and 300 feet 
wide from the mouth to Richmond Deepwater Terminal, 
and a channel 18 feet deep and 200 feet wide from the 
deepwater terminal to Richmond Lock; a mooring basin 35 
feet deep, 180 to 220 feet wide and 2,100 feet long along 
side the channel opposite waterfront at Hopewell; enlargement 
of the turning basin at Richmond Deepwater Terminal 
to 825 feet wide, 2,770 feet long and 35 feet deep; a turning 
basin in Richmond Harbor 200 feet wide, 600 feet long and 
18 feet deep; and construction of spur and training dikes. 
Depth of channels are referred to mean low water. Total 
length of channel included in the project is 87 miles, which is 
the navigable section, Mean tidal ranges under ordinary 
conditions for different parts of the river are: mouth, 2.6 
feet; Jamestown, 2 feet; City Point, 2.6 feet; and Richmond, 
3.2 feet. Spring tide ranges under ordinary conditions at the 
same localities are mouth, 3.1 feet; Jamestown, 2.4 feet; 
City Point, 3 feet; Richmond, 3.2 feet. Ordinary fluctuations 
of stage at Richmond, due to floods are 6 to 12 feet above 
mean low water. Extreme fluctuations are 16 to 32 feet. 
Flood heights below Richmond diminish rapidly. The extreme 
according to available information is about 11 feet 
lower at Dutch gap, 14 miles below and 17 to 18 feet lower, 
20 miles below. The estimated (1971) total cost for new work 
is $71,145,940 including required non-Federal cost for conditions 
of local cooperation imposed by the River and 
Harbor Act of 1930, 1945, and 1950, estimated (1939) to be 
$1,949,700; and by the River and Harbor Act of 1962, 
estimated (1971) to be $2,950,000. For previous projects, 
see Annual Report for 1938. (See Table 5-B for Authorizing 
Legislation). 
Local cooperation. Fully complied with for conditions 
imposed by River and Harbor Act of 1930, 1945, and 1950. 
The conditions imposed by the River and Harbor Act of 
1962 have not been complied with. 
Terminal facilities. River commerce at Richmond is 
handled by city-owned terminals, city wharves, Richmond 
dock, and 16 privately-owned wharves within or in the 
immediate vicinity of Richmond Harbor. The city's Upper 
Terminal, located on the north bank within the manufacturing 
section of Richmond, provides for 750 feet of concrete wharf 
and 80,000 square feet of warehouse and transit shed. The 
other terminal is located approximately 4 miles downstream 
from the Upper Terminal which provides about 1,250 feet of 
wharf and 2 concrete warehouses with about 190,000 
square feet of floor space. This deepwater terminal at the 
head of the 25-foot deep improved channel serves oceangoing 
vessels and larger ships engaged in coastwide trading. 
Below the deepwater terminals the improvement is served 
by 42 wharves. Richmond terminals and wharves together 
with wharves between Richmond and the river's mouth are 
adequate for river's commerce. 
Operations during fiscal year. Maintenance: 
Dredging was performed on the Shoals of Hopewell, 
Richmond Harbor and the Richmond I)eepwater 
Terminal. Dredging, by contract, was accomplished 
Jun. 20 - Sept. 3, 1986. A total of 276,612 cubic yards 
of material were removed for a total direct cost of 
$1,859,345. Other work performed included condition 
surveys, budgeting and scheduling, engineering and 
design and supervision and inspection. 
10. LITTLE MACHIPONGO RIVER, VA 
Location. This river, locally known as Parting Creek, 
has its source in the marsh of Bell Neck, Northampton 
County Va., flows in a southerly and easterly direction 
about 5 miles, and empties into Great Machipongo River, 
about 12 miles by water from Great Machipongo inlet, and 
about 28 miles by water from Cape Charles, Va. The drainage 
area is about 11 square miles. No information is 
available as to the discharge of this stream. The length of 
the tidal reach is about 2 miles. The Great Machipongo Inlet 
and the Great Machipongo River are the waterways connecting 
with the Atlantic Ocean, and have a controlling 
depth of 16 feet. Willis Wharf, a town with a population of 
about 500, is located on the west bank about 1 mile above its 
junction with the Great Machipongo River. The high-water 
width varies from about 450 feet at the mouth to 350 feet at 
Willis Wharf. (See U.S. Coast and Geodetic Survey Chart 
No. 1221.) 
Existing project. This project provides for a channel 
8 feet deep at mean low water and 80 feet wide from the town 
of Willis Wharf to deep water in the river below. The mean 
xange of tide is about 0.7 foot below mean low water to about 
2 feet above mean high water. (See Table 5-B for Authorizing 
Legislation) 
Local cooperation: None required. 
Terminal facilities. At the town of Willis Wharf, there 
are three wharves with a total wharfage space of about 300 
feet, five bulkheads with a total wharfage space of about 
1,140 feet, and two marine railways which will accommo- 
5-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
date vessels up to 50 feet in length. All facilities are privately 
owned, being used for packing seafoods and servicing 
fishing vessels. The wharves have no railroad connections, 
but are served by local roads connecting with the country 
and State highway system. The facilities are considered' 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Dredging, scheduled to be performed this fiscal year, 
was rescheduled for Fiscal Year 1987 due to 
prolonged disposal area issues. $45,920 was paid to 
landowners to acquire property for the disposal area. 
Engineering and design is still in progress. 
11. NORFOLK HARBOR, VA 
Location. Norfolk, Virginia is 187 miles south of Baltimore, 
Maryland and 30m iles from entrance to Chesapeake Bay at 
Cape Charles and Cape Henry. Harbor extends 18.3 miles 
from 45-foot contour at Hampton Roads to a point 2,500 
feet above Norfolk and Western Railway Bridge over 
Southern Branch of the Elizabeth River. (See National 
Ocean Survey Charts Nos. 12245 and 12253.) 
Existing projects. A main channel 45 feet deep, 1,500 
feet wide from that depth in Hampton Roads near Fort Wool 
to a point just south of Norfolk International Terminal 
Piers; at the same depth 800 feet wide to mouth of Southern 
Branch of Elizabeth River; and 450 fet wide up this branch 
to the Belt Line Railroad bridge, including an approach in 
turning area to same depth and a maximum width of 830 
feet opposite Norfolk Naval Shipyard, extending downstream 
3,250 feet from Belt Line Railroad bridge 40 feet deep, 
375 feet wide and 1 mile long to Norfolk and Western 
(formerly Virginia Railway bridge); 35 feet deep, 250 feet 
wide and 3.1 miles long to a point 1,900 feet above Norfolk 
and Western Railway (Gilmerton's Bridge); 35 feet deep, 250 
-feet to 500 feet wide to a point 1.6 miles above Interstate 
64 high level bridge. 
A turning basin at the mouth of St. Julian's Creek, 35 feet 
deep and 400-600 feet square, and a turning basin at the 
mouth of Main's Creek 35 feet deep and 600 feet square, the 
upstream end of the project. A channel in Eastern'Branch, 
25 feet deep, 500f eet wide and 1.09 miles long from 40-foot 
channel to Norfolk and Western Railway bridge; 25 feet 
deep, 300 feet wide, 0.55 mile long to Campostella Bridge; 
25 feet deep, 200 feet wide and 1.2 mile to Norfolk and 
Western Railway bridge (formerly Virginia Railway bridge); 
and for maintenance at a depth of 25 feet of existing turning 
basin and 5.5 acres in extent at head of existing project just 
below the Norfolk and Western (formerly Virginian) Railway 
bridge; a channel in Western Branch, 40 foot channel in 
Elizabeth River, 24 feet deep, 300 feet wide and 0.78 mile 
long; 24 feet deep and 200 feet wide for 0.37 mile to West 
Norfolk Highway bridge; 18 feet deep, 150 feet wide, 0.57 
mile long. A channel in Scotts Creek between 40-foot 
channel at mouth and a point 100 feet above former location 
of Atlantic Coast Line Railroad bridge (about 0.73 miles 
upstream), 12 feet deep and 100 feet wide. Anchorage areas 
on west side of 40-foot channel opposite Lamberts Point 
and south of Craney Island aggregating 173 acres, consisting 
of 1 anchorage space 1,500 feet square and 38 feet deep; 1 
anchorage space 1,500 feet square and 35 feet deep; and 1 
anchorage 1,000 feet wide, 3,000 feet long and 20 feet deep. 
Another anchorage of 45 acres and 12 feet deep near Pinner 
Point. Two anchorages opposite Sewells Point 45 feet deep 
over a swinging radius of 1,200 feet and a trapezoidal 
shaped disposal area of about 2,500 acres of flats adjacent 
to the north of Craney Island,enclosed by stonefaced levees, 
3 sluiceways in west levee, and an access road. 
Facilities for unloading of hopper dredged material 
consisting of mooring dolphins; a mooring barge anchorage 
100 by 600 feet, 21 feet deep, with approach channel 300 to 
3,600 feet; 30-feet deep connecting anchorage with Norfolk 
Harbor 45-foot channel; and a 28-inch discharge pipe line to 
the leveed area. Facilities for contract rehandling of bucket 
dredged material consisting of a rehandling basin 1,000 by 
1,200 feet, 40 feet deep, protected by a spur levee extending 
2,350 feet from main levee and provided with approach exit 
channels, 200 feet wide by 18 feet deep to Norfolk Harbor 
45 foot channel and a pipe line trestle from rehandling basin 
to leveed area. All depths are referred to mean low water. 
Mean tidal range is 2.7 feet, and extreme is 3.4 feet. 
Extremes of irregular fluctuations, due to combined effect 
of tides and winds referred to mean low water on -3.5 feet 
and +9.6 feet. Eastern Branch, 30-foot channel portion is 
considered inactive. For details of previous projects see 
Annual Report for 1938. (See Table 5-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Latest published description of 
terminal facilities is in Port Series No. 11 (revised 1971, part 
II) on Ports of Hampton Roads, prepared by Board of 
Engineers for River and Harbors. 
Operations during fiscal year. New Work: 
Planning and engineering for the deepening of 
Norfolk Harbor and Channels, initiated in prior 
years with General Investigations Appropriations, 
continued with Construction General 
Appropriations with a total project cost of $273,772. 
Completion of the 55-foot Channel and Anchorage 
General Design Memorandum amounted to $28,287, 
Long-Term Disposal Investigations amounted to 
$122,770, preliminary work on the 40-45 foot 
improvements amounted to $26,069, and $96,646 was 
expended for tcontract plans and specifications for 
the 50 foot Outbound Channels, the first 
construction element. Work was accomplished by 
contract and government plant and hired labor. 
Maintenance: Dredging 6 separate reaches was 
performed Jul. 22 - Aug. 30, 1986. A total of 280,202 
cubic yards of material were removed at a total direct 
cost of $2,119,860. 
Operation and maintenance of the Craney Island 
project consisted of operation and maintenance of 
roads, service facilities, rental equipment, and 
5-6

NORFOLK, VA DISTRICT 
government plant. In addition, condition surveys, 
engineering and design and supervision and 
inspection was performed at a total cost of 
$1,567,110. 
Operation and maintenance of the Norfolk Harbor 
portion continued this fiscal year at a cost of 
$2,300,806. Condition and quantity surveys, 
budgeting and scheduling, engineering and design 
and supervision and inspection was performed using 
government plant and hired labor. 
Work progressed on the Craney Island 
Management Plant at a total cost of $692,802. 
12. NOTTOWAY RIVER, VA 
Location. The study section of the Nottoway 
River, a major tributary of the Chowan River, is 
located in Southampton County in southeastern 
Virginia. (See Courtland and Sebrell, Virginia 
quadrangles of geological survey). 
Previous projects. None. 
Existing project. Channel width of 15 feet from 
the public boat ramp located 700 feet above Route 653 
(Carey's Bridge) downstream to open water just 
below the seaboard Coast Line Railway Bridge. 
Under normal river conditions, the water depths are 
adequate for the recreational craft using the river. 
Therefore, dredging is not a part of this project. (See 
Table 5-B for Authorizing Legislation). 
Local cooperation. Fully complied with. For 
details, see Annual Report for fiscal year 1979. 
Operations during fiscal year. Maintenance: 
Snagging and clearing was performed using 
government plant and hired labor. 
13. PARKER CREEK, VA 
Location. Parker Creek empties into the western 
side of Metomkin Bay in Accomack County, 
Virginia. It is on the ocean side of Virginia's Eastern 
shore, about 20 miles south of Maryland-Virginia 
State line. 
Existing project. The existing project, 
authorized under Section 107 of the 1960 River and 
Harbor Act, provides for establishment and 
maintenance of a channel 40 feet wide and 5 feet deep 
at mean low water from the same depth in Metomkin 
Bay into the mouth of the creek, a distance of about 
2,200 feet or .5 mile. The existing project was 
completed in 1964 at a cost of $15,530 to the Federal 
Government and $1,350 to local interests. 
Local cooperation. Fully complied with. Non- 
Federal contributions amounted to $1,350. 
Terminal facilities. There are 9 small privately 
owned boat landings and two small public landings 
on the creek. Local interests have also constructed a 
50-foot public dock with adequate shore facilities. 
These facilities are deemed adequate for existing and 
prospective commerce. 
Operations during fiscal year. Maintenance: 
Dredging was performed between Sept. 30 - Oct. 5, 
1986. There were 37,185 cubic yards of material 
removed at a total direct cost of $9,482. Other 
operations performed included quantity surveys, 
engineering and design and supervision and 
inspection. 
14. QUINBY CREEK, VA 
Location. A natural channel on the Atlantic 
Ocean side of Delmarva Peninsula about 32 miles 
north of Cape Charles; and about 33 miles south of 
Chincoteague, VA. Creek extends in a generally 
southeasterly direction between Quinby Landing at 
Quinby, VA and head of Tony Rock Drain, in Upshur 
Bay, a distance of 6,900 feet (See National Ocean 
Survey Chart No. 12210). 
Existing project. Provides for a channel 8 feet 
deep in Upshur Bay to a point 600 feet bayward from 
Quinby Landing, thence 60 feet wide to Quinby 
Landing, a total distance of about 6,900 feet and a 
turning and mooring basin of the same depth, 200 
feet wide and 400 feet long opposite public terminal 
and landing. Mean range of tide is 4.4 feet. Existing 
project was adopted by River and Harbor Act of 1950. 
(H. Doc. 241, 81st. cong., 1st sess. which contains 
latest published map). Project is complete, for details 
see Annual Report for 1964. 
Local cooperation. Fully complied with for 
initial construction. Local interests must provide 
spoil disposal areas for maintenance. 
Terminal facilities. There are two open-pile 
wooden wharves and about 125 feet of wooden 
bulkhead at Quinby, Va., which are privately owned. 
In addition, a number of berthing spaces, a wooden 
dock and launching ramp were constructed which 
are open to all on equal terms. These facilities are 
connected to the State Highway system by a suitable 
access road and are considered adequate. 
Operations during fiscal year. Maintenance: 
Engineering and design was accomplished. 
5-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
15. SUPERVISION OF HARBOR 
OF HAMPTON ROADS (PREVENTION 
OF OBSTRUCTIVE AND 
INJURIOUS DEPOSITS) 
The District Engineer, Norfolk District, was 
designated Supervisor of the harbor of Hampton 
Roads under the provisions of the River and Harbor 
Act of June 29, 1888 (33 U.S.C. 441-451) as amended 
July 12, 1952. Under this Act, the Supervisor of the 
harbor of Hampton Roads is charged with the 
mission of preventing the deposit of obstructive and 
injurious materials in the tidal waters of the harbors 
of Norfolk, Portsmouth, Newport News, Hampton 
Roads, and their adjacent and trubitary waters, so 
much of the Chesapeake Bay and its tributaries as 
lies within the state of Virginia and so much of the 
Atlantic Ocean and its tributaries as lies within the 
jurisdiction of the United States within or to the east 
of the State of Virginia. The Riverand Harbor Act of 
March 3, 1899 (33 U.S.C. 403,407,409) as amended 
prohibits obstructions to navigable waters such as 
unauthorized structures, unauthorized fill, deposit 
of refuse, and sinking of vessels. Other laws relating 
to the supervision of Norfolk Harbor and its 
tributary waters are the Clean Water Act, the Marine 
Protection, Research and Sanctuaries Act of 1969, 
the Fish and Wildlife Act of 1956, the Federal Power 
Act of 1920, the National Historic Prevention Act of 
1966, the Endangered Species Act of 1973, the 
I)eepwater Port Act of 1972, the Wild and Scenic 
Rivers Act, and the Land and Water Conservation 
Fund Act. 
DI)irect supervision of the waters under the 
jurisdiction of the Norfolk District was accomplished 
by means of two patrol vessels performing 
inspections, debris removal, investigation and removal 
of sunken or abandoned vessels and navigational 
hazards, and support for Federal dredging 
projects. In addition, surveillance of the harbor was 
performed regarding the Corp's regulatory program, 
using also three small outboard craft, motor vehicles 
from land, and occasional chartered aerial recon 
naissance. This regulatory surveillance involved 
compliance surveys of permitted dredging, and 
evaluation of navigational impacts of proposed piers 
and other structures. 
16. TANGIER CHANNEL, VA 
Location. A tidal channel about 2 miles long extending 
from Tangier Island, Virginia, northeasterly to deepwater 
in Tangier Sound, Chesapeake Bay and northwesterly to 
deepwater on Chesapeake Bay. (See Coast and Geodetic 
Chart No. 12228.) 
Existing project. A channel 8 feet deep at mean low 
water and 100 feet wide from 8-foot contour to Tangier 
Sound to day marker No. 4, and thence 8 feet deep and 60 feet 
wide to the town of Tangier, with an anchorage basin 
adjacent of town 400 feet square and 7 feet deep. A channel 7 
feet deep and 60 feet wide for about 4,000 feet from the 
anchorage basin northwesterly across Tangier Island to 
Chesapeake Bay. Mean range of tide is 1.7 feet and extreme 
tidal range 4.7 feet. (See Table 5-B for Authorizing 
Legislation.) 
Local cooperation. Complied with except that interests 
must furnish spoil disposal area as needed for future 
maintenance. 
Terminal facilities. Accomack County constructed a 
public dock in 1961. There are four privately owned docks 
adjacent to existing project and two marine railways. 
Operations during fiscal year. Maintenance: 
Routine operation, condition surveys and scheduling 
were performed. 
17. WATERWAY ON THE COAST OF VA 
Location. Between barrier beach along the 
Atlantic Ocean on the east and Virginia portion of 
mainland peninsula on the west. It extends for 83.7 
miles from south end of Chincoteague Bay through a 
number of creeks, throughfares, and bays to enter 
Chesapeake Bay in the vicinity of Fisherman Island, 
just south of Cape Charles on the southern tip of the 
peninsula. (See National Ocean Survey Chart No.'s 
12211, 12210, 12221). 
Existing project. An inland waterway 6 feet deep 
at mean low water and 60 feet wide from Chesapeake 
Bay to Chincoteague Bay, VA. mean range of tide is 
about 3 feet. Greater fluctuations in water level are 
caused by high winds and storms. A modification of 
the project approved during 1970 under Section 201 
of the Flood Control Act of 1965 authorizes relocation 
of portions of the waterway and widening of 100 feet. 
(See Table 5-B for Authorizing Legislation). 
Local cooperation. Complied with except that 
local interests are to furnish spoil disposal areas for 
future maintenance. 
Terminal facilities. Existing facilities are 
considered adequate. For details see Annual Report 
for 1969. 
5-8

NORFOLK, VA DISTRICT 
Operations during fiscal year. Maintenance: 
Dredging was accomplished at Gull marsh, Sloop 
Channel, and the North Channel between Dec. 31, 
1985 - Mar. 2, 1986. A total of 282,531 cubic yards of 
material were removed at total direct cost of 
$593,709. In addition, 306,285 cubic yards of dredged 
material were removed from Metompkin Bay at a 
total direct cost of $85,709. Other operations 
performed included condition studies and surveys, 
engineering and design and supervision and 
inspection. 
18. YORK RIVER, VA 
Location. This river is formed at West Point, VA, by the 
confluence of the Mattaponi and Pamunkey Rivers, and 
flows southeasterly about 41 miles into Chesapeake Bay, 
which it enters about 20 miles in a northerly direction from 
Norfolk, VA, and 20 miles in a northwesterly direction from 
the Atlantic Ocean at Cape Henry. (See National Ocean 
Survey Chart Nos. 494 and 495.) 
Existing project. This provides for dredging a channel 
22 feet deep at mean low water and 400 feet wide through the 
bars, and a basin of the same depth at the wharves at West 
Point, and the construction of a dike on the right bank at 
West Point to assist in maintaining the channel. The plane 
of reference is mean low water. Tidal ranges are: Mean 2.2 
feet at mouth and 2.9 feet at West Point; and the extreme 3.9 
feet at mouth and at West Point; irregular 6 feet at West 
Point. 
The existing project was adopted by the River and Harbor 
Act of June 14, 1880 (Annual Report for 1880, p. 897). It was 
modified in 1884 and 1887. The latest published map is in the 
Annual Report for 1894, p. 964. 
Terminal facilities. There are 18 wharves on the York 
River of open-pile construction. The facilities are considered 
adequate for the existing commerce. 
Operations during fiscal year. Maintenance: 
Ordinary operations, to include condition surveys 
and budgeting and scheduling, were accomplished. 
19. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
STUDY/ 
PROJECT 
FY 1986 
EXPENDITURES STATUS 
Study/ 
Pr*-4 -+ 
r AV PCJ; u. I a _ .7 iili 
FY 1986 
Frnynditum.. aia 
Hunting/Guilford Creeks, 28,471 RECON in 
Accomack County, VA progress. 
Scotts Creek, VA 18,536 RECON in 
progress. 
Jordan Bridge Park Channel, 10,434 DPS determined 
Chesapeake, VA negative. 
Kings Creek, Northampton 7,912 DPS determined 
County, VA negative. 
Nansemond River, Constance 7,500 DPS determined 
Wharf, VA negative. 
Little Machipongo River, 2,424 DPS completed. 
Northampton County, VA 
Rudee Inlet, VA 29,482 P&S in progress. 
Finney Creek, 20,861 P&S in progress. 
Wachapreague, VA 
AR Appraisal Report 
RECON Reconnaissance Study 
DPS Detailed Project Study 
P&S Plans and Specifications 
Beach Erosion Control 
20. VIRGINIA BEACH, VA 
Location. On the Atlantic Seaboard, 22 miles north of 
Virginia-North Carolina State line, 3.5 miles south of Cape 
Henry, and 19 miles east of Norfolk, VA. (See National 
Ocean Survey Chart 12207.) 
Existing project. Federal participation in restoration 
and protection of shore of Virginia Beach between Rudee 
Inlet and 49th Street by artificial placement of sand to 
provide a minimum beach width of 100 feet at elevation 7 
feet above mean low water, and maintenance of such beach 
by periodic replenishment of losses to insure continuous 
protection; including construction of a groin system to be 
undertaken at such times as estimated annual charges 
therewith would be less than the annual cost of beach 
replenishment alone. The United States shall participate in 
the first cost of the project to the full extent of its 
proportionate share of cost as a landowner, plus one third 
total first cost of restoring and protecting all publicly-owned 
5-9 
.I. I 
Meachim's Creek, Middlesex 4,600 AR in progress. 
County, VA

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
sections of the shore. The 1962 modification provided that 
the United States shall further participate in periodic beach 
nourishment of the beach in the amount of one third the cost 
for 25 years from date of commencement of operations in 
placing an initial quantity of nourishment material equal to 
deficiency in the design beach at that time. Section 103 of 
the 1962 River and Harbor Act increased Federal participation 
to one-half of the cost incurred after October 23, 
1962. Estimated Federal cost (1986) is $5,500,000. Estimated 
cost to local interests is $5,500,000. Construction of 
the groin system is not included in the above estimate. The 
1962 estimate for this work was $549,000 Federal cost and 
$531,000 cost to local interests. The 1974 modification 
provides for structural and nonstructural improvements. 
Structural measures would be provided for the 6 mile reach 
of shoreline between Rudee Inlet and 89th street. This 
would include raising the beach to elevation 10 feet and a 
width of 100 feet, driving a sheet pile wall just seaward of the 
existing bulkhead from Rudee Inlet to 57th Street; and 
raising and strengthening sand dunes from 57th to 89th 
Streets. The estimated cost (1986)of the structural improvements 
are Federal $28,900,000 and non-Federal $12,800,000. 
(See Table 5-B for Authorizing Legislation.) 
Local cooperation. Requirements are described in full 
on page 5-11 of FY 81 Annual Report. Necessary changes in 
requirements will be made if the 1974 modification is 
constructed. 
Operations during fiscal year. There were 
150,000 cubic yards of material deposited on the 
project beach. Local interests were reimbursed 
$333,094 for the Federal share of costs incurred in 
Fiscal Year 1985. 
21. BEACH EROSION CONTROL 
WORK UNDER SPECIAL 
AUTHORIZATION 
None this fiscal year. 
Flood Control 
22. GATHRIGHT DAM AND LAKE 
MOOMAW, VA 
Location. Site of proposed Gathright Dam is on 
Jackson River, a tributary of James River at mile 
43.3 and Alleghany County. Gathright Dam site is in 
reach of Jackson River known as the Gorge. About 19 
miles upstream from Covington, VA at the elevation 
at the top of the conservation pool. Gathright 
Reservoir will ectend upstream about 9 miles (see 
Falling Spring and Mountain Grove, Virginia-West 
Virginia quadrangles of geological survey.) 
Existing project. Gathright Dam consists of a 
1,172-foot long rolled rock fill dam with an 
impervious core, with a top at elevation 1,684.5; 
outlet works consisting of a concrete intake structure 
located in the right bank 500 feet upstream from the 
axis of the dam; a 1,075-foot long outlet tunnel crest 
emergency spillway excavated in a low saddle in the 
divide at fortney Branch, about 2.5 miles south ofthe 
dam. Discharges through the macimum 
conservation pool elavation 1,582 will be provided 
for water quality control. The reservoir area at 
elevation 1,582 will be provided for water quality 
control. The reservoir area at elevation 1,582 will be 
2,530 acres. A total of 302,000 acre-feet of storage 
between elevation 1,582 spillway crest (elevation 
1,663.5) will be reserved for flood control. At the 
spillway crest the reservoir will have an area of 4,540 
acres. Last approved estimated Federal cost (1979) is 
$83,000,000. (See table 5-B for Authorizing 
Legislation.) 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: 
Operations performed this fiscal year consisted of 
care of service and receational facilities, water 
control management, testing and monitoring, 
supervision and administration and engineering 
and design. Work was performed using government 
plant and hired labor. Additionaly, the following 
work was performed by contract: Installation of 
intake tower elevator, steam gage activities, and 
painting of the Intake Tower Bridge. 
23. RICHMOND, VA 
Location. The city of Richmond, the capital of 
Virginia, is located in the Piedmont Plateau and is 
bordered on the north by Henrico County and on the 
south by Chesterfield County. The James River 
flows directly through Richmond separating its 
business district into two areas, the Shockoe Creek 
area on the north bank and the industrialcommercial 
complex on the south bank. 
Previous project. None. 
Existing project. The project will provide a 
system of floodwalls and levees on both sides of the 
river in the downtown area, which would protect 
against a flood higher than that which occurred in 
June 1972 which is the maximum flood of recent 
record. The project to be constructed is that generally 
described in House Document 98-178, 98th Congress, 
2nd Session with modifications recommended by the 
Assistant Secretary of the Army on February 21, 
1984. The present construction cost of the project is 
now estimated at $77,500,000 based on October 1985 
price levels which does not include inflation during 
term of construction. 
Local cooperation. The City of Richmond would 
provide the following: 
5-10

NORFOLK, VA DISTRICT 
a. Provide without cost to the United States all 
lands, easements and rights-of-way, including 
suitable borrow and disposal areas for excavated 
materiats as determined by the Chief of Engineers, 
necessary for the construction of the project. 
b. Accomplish without cost to the United States all 
alterations and relocations of buildings, 
transportation facilities, storm drains, utilities, 
cemeteries, and other structures and improvements 
made necessary by the construction, excluding 
railroad bridges and approaches and facilities 
necessary for the normal interception and disposal 
of local interior drainage at the line of protection. 
c. Share in paying the total project construction 
costs on the following bases: 
(1) If the value of lands, easements, rights-of-way, 
and relocations required for project construction and 
maintenance as specified in subparagraphs a and b 
above is equal to or greater than 20 percent of total 
project construction costs contribute the value of 
these items plus a cash payment equal to 5 percent of 
the total project construction costs during the period 
of construction; 
(2) If the value of the lands, easements, rights-ofway, 
and relocations required for project 
construction and maintenance as specified in 
subparagraphs a through c above is less than 20 
percent of total project constructions costs, 
contribute 25 percent of said costs including not less 
than 5 percent in cash during the period of 
construction. 
d. Hold and save. the United States free from 
damages due to the construction, operation and 
maintenance of the project, except where such 
damages are due to the fault or negligence of the 
United States or its contractors; 
e. Maintain and operate all works after completion 
in accordance with regulations prescribed by the 
Secretary of the Army; 
f. Prescribe and enforce regulations to prevent 
encroachment of ponding areas and rights-of-way 
necessary for the proper functioning and 
maintaining of the project; and 
g. Publicize floodplain information in the areas 
concerned and provide this information to zoning 
and other regulatory agencies for their guidance and 
leadership in preventing unwise future development 
in the floodplain and in adopting such regulations as 
may be necessary to insure compatibility between 
future development and protection levels, including 
ponding areas, provided by the project. 
Operations during fiscal year. New Work: 
Preconstruction engineering and design initiated in 
prior years with General Investigations 
Appropriations, continued with Construction 
General Appropriations with a total project cost of 
$591,086. At yearend a draft General Design 
Memorandum was under preparation. 
24. SAXIS ISLAND, VA 
Location. Located adjacent to the town of Saxis, 
VA, in Accomack County. This Eastern Shore island 
is apporoximately 80 miles north of Norfolk, VA, and 
100 miles southeast of Washington, D.C. 
Previous project. None. 
Existing project. Shoreline erosion threatens a 
public landing owned by Accomack County and 
located at the southern end of Saxis Island. The 
threatened public landing is currently protected by a 
timber bulkhead which is in danger of immediate 
failure due to erosion. Consideration was given to a 
catilever steel sheet pile wall and an anchored timber 
system. However, the recommended plan provides 
for construction of an anchored timber bulkhead 
along the northern and western portions of the 
landing. 
Local cooperation. The County ofAccomack, Va 
shall, in consideration of the Government 
commencing construction of such project, fulfill the 
requirements of non-Federal cooperation specified in 
such legislation, to wit: 
(a) Provide without cost to the United States all 
lands, easements, and rights-of-way necessary for 
construction, operation and maintenance of the 
project, including all necessary relocations and 
alterations to utilities and other structures or 
improvements that may be required; 
(b) Hold and save the United States free from 
damages due to the construction, operation and 
maintenance of the project except where such 
damages are due to the fault or negligence of the 
united States or its contractors; 
(c) Maintain and operate all works after 
completion in accordance with regulations 
prescribed by the Secretary of the Army; 
(d) Assume full responsibility for all project costs 
in excess of the Federal cost limitation of $250,000. 
5-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
(e) The County in acquiring lands, easements 
and rights-of-way for project construction, operation 
and maintenance will comply with the provisions of 
the Uniform Relocation Assistance and Real 
Property Acquisition Policy Act of 1970 (Public Law 
91-646, approved 2 January 1971); and 
(f) The County will comply with Section 601 of 
Title VI of the Civil Rights Act of 1964 (Public Law 
88-352) to wit: That no person shall be excluded from 
participation in, denied the benefits of, or subjected 
to discrimination in connection with project on the 
grounds of race, color or national origin. 
Operations during fiscal year. Design and cost 
estimates and real estate studies were conducted 
during the year. $20,000 was allotted at the end of the 
Fiscal Year to initiate construction. 
25. SCOTTSVILLE, VA 
Location. The town of Scottsville, VA is located in 
Albemarle and Fluvanna Counties, on the north 
bank of the James River, 185 miles above its mouth. 
Previous project. None. 
Existing project. The town encompasses 130 
acres and the 1980 population was 250. It includes 
small commercial establishments and dwellings 
including many of historical value. A relatively large 
tire manufacturing plant is located adjacent to the 
town in Albemarle County and is the largest 
employer in the area with about 270 employees. 
Local cooperation. Requirements are described 
in full on page 5-11 of FY 85 Annual Report. 
Operations during fiscal year. New Work: 
Construction, initiated in FY 1985, is continuing 
with repair work to the existing project. Other vwork 
performed this FY consisted of engineering and 
design and supervision and inspection. Total 
contractor's earnings this year amounted to 
$631,285. 
26. VIRGINIA BEACH STREAMS 
CANAL NUMBER 2, VA 
Location. The canal number 2 watershed with a 
drainage area of about 37 square miles lies within the city of 
Virginia Beach. The city consists of 255 square miles of 
primarily low, flat terrain with about 75 percent of the area 
below elevation 15 feet, mean sea level. The existing canal, 
from the Eastern Branch of the Lynnhaven River to the 
North Landing River is about 12 miles long and follows a 
north-south alignment. (See National Ocean Survey Chart 
No. 12205.) 
Existing project. The project will provide for 
construction of a new canal for a length of 2.6 miles and 
channelization of an existing canal fro a lenght of 1.1 miles. 
The canal botom width will range from 45 feet to 80 feet and 
a depth from -4feet mean sea level to -8 feet mean sea level 
with a flow capacity great enough to carry a 100 year flood. 
Its construction will require dredging 741,000 cubic yards of 
material. 
Local cooperation. Requirements are described in full on 
page 5-14 of FY 81 Annual Report. Requirements may 
change if legislation is enacted regarding new cost-sharing 
proposals. 
Operations during fiscal year. Funds, in the 
amount of $400,000, were received this FY to initiate 
construction. Award of the contract was delayed at 
yearend while local cooperation items were provided. 
27. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
The District was reimbursed for an unfavorable 
Initial Appraisal Report prepared on South River, 
Vesuvius, VA. Total cost amounted to $7,500. 
28. EMERGENCY FLOOD 
CONTROL ACTIVITIES 
During FY 86, $112,610 was spent on the National 
Emergency Preparedness Program. In addition, 
$5,104 was spent for rehabilitation work at 
Scottsville, VA. 
General Investigations 
29. SURVEYS 
Total cost of surveys during the fiscal year 
amounted to $705,175. Work performed consisted of: 
Item FY86 Expenditure 
Navigation Studies ........................................ $138,988 
Flood Control Studies........................................ 30,462 
Shoreline Protection Studies ............................ 37,375 
Review of Authorized Projects...................... 349,263 
Special Investigations...................................... 29,512 
FERC Licensing.................................................. 5,219 
Coordination Studies with Other Agencies... 40,210 
Supplmntl Preauth Studies (Flood Control).. 74,146 
5-12

NORFOLK, VA DISTRICT 
30. COLLECTION AND STUDY OF 
BASIC DATA 
Dtring the fiscal year, cost of collection and 
study of Basic Data was $181,707, consisting of 
$59,758 for Management Services Unit, $70,432 
for Technical Service, and $51,517 on a 
Hurricane Evacuation Study. 
31. CONTINUATION OF PLANNING 
AND ENGINEERING 
Work was initiated on the 1974 modification of the 
Virginia Beach (Hurricane Protection) Erosion 
Control project. Total project costs amounted to 
$797,954 for this fiscal year. Work performed 
included preparing a work plan, topographic 
surveys, exploration, beach sampling, 
environmental analysis and hydraulic model study. 
Work was completed on the Norfolk Harbor 
Deepening project. Total project costs amounted to 
$1,770,444 and included work on the 55-foot channel 
and anchorage plan. Other work performed included 
environmental and economic studies, preparation of 
reports and surveys. 
Work was also completed on the Richmond (Local 
Protection) Flood Control project. Total project costs 
this fiscal year amounted to $1,011,379. Work 
performed included design of interior drainage 
system, civil and structural engineering, bridge 
studies, archeological studies and geotechnical 
investigations. 
All work was performed by government plant and 
hired labor. 
5-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 5-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Sect. Project Funding FY 83 FY 84 FY 85 FY 86 To 30 Sep 1986 
In Tect
1. Atlantic Intracoastal 
Waterway, between 
Norfolk, VA and the 
St. John's River, FL 
(Norfolk Dist) 
(Regular Funds) 
2. Baltimore Harbor and 
Channels 
(Norfolk Dist) 
(Regular Funds) 
3. Broad Creek, VA 
(Regular Funds) 
(Contributed Funds) 
4. Cape Charles City 
Harbor, VA 
(Regular Funds) 
5. Chincoteague Inlet, 
VA (Regular Funds) 
(Contributed Funds) 
Cranes Creek, VA 
(Regular Funds) 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
Major Rehab 
Approp 
Cost 
Recreation 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
2,077,000 1,213,817 2,570,649 1,964,374 
1,415,832 2,343,728 2,521,787 1,931,265 
3,688,3721 
3,688,372' 
45,169,3352 
45,083,287 
479,947 
479,947 
59,871 
59,871 
1,079,000 
1,885,518 
40,000 
200,690 
46,945 353,314 
24,945 375,313 
88,000 968,902 
88,001 967,792 
12,250 
12,251 
74,139 
74,139 
8,015,0733 
8,015,0733 
9,633,388 
9,645,278 
27,888 
27,888 
568,418 
568,418 
500 
500 
9,798 
8,545 
32,724 
33,977 
708,366 1,381,182 918,0.15 
625,959 1,484,896 917,618
- 113,223 
- 113,222 
65,107 
65,508 
622,644 
622,644 
606,931 
606,930 
227,000 
227,000 
5,444,514 
5,444,514 
3,850 
3,850 
6,274 
6,274 
- 187,000 
- 175,130 
200,231 
212,101 
394,556 
394,556 
5-14

NORFOLK, VA DISTRICT 
TABLE 5-A (Cont.) COST AND FINANCIAL STATEMENT 
See Total Cost to 
Sect. Project Funding FY 83 FY 84 FY 85 FY 86 30 Sep 1986 
in Text 
7 Greenvale Creek,VA 
(Regular Funds) 
8. Hampton Roads and 
Harbors of Norfolk 
and Newport News, 
VA Collection and 
Removal of Drift 
(Regular Funds) 
9. James River, VA 
(Regular Funds) 
(Contributed Funds) 
10. Little Machipongo 
River, VA 
(Regular Funds) 
11. Norfolk Harbor, VA 
(Regular Funds) 
(Contributed Funds) 
12. Nottoway River, VA 
(Regular Funds) 
(Contributed Funds) 
13. Parker Creek, VA 
(Regular Funds) 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
155,000 169,526 178,241 
120,910 221,568 178,209 
37,196 
37,196 
185,105 
185,163 
1,440,000 814,658 1,538,877 2,311,895 
1,689,700 1,076,147 1,430,155 2,312,981 
50,000
- 67,500 
- 39,163 
26,719 
26,719 
(-)2,548 
56,000 
19,755 
5,590 
5,590 
6,013 
31,512 
11,000 
28,579 
64,811 
64,809 
63,000 
15,127 
2,424 
84,934 
84,735 
15,000 297,000 
.. 271,772 
7,305,699 4,627,375 3,816,880 5,369,398 
4,648,737 9,369,636 3,739,813 4,840,919 
10,000 
8,734 
- 21,000 
- 20,999 
29,329 
29,328 
5-15 
20,003 
20,003 
223,125 
223,125 
2,940,984 
2,940,984 
7,639,904 
7,639,904 
28,523,481 
28,415,589 
413,456 
360,850 
93,500 
85,166 
230,328 
230,127 
36,711,1156 
36,670,887 
74,897,654 
74,289,106 
179,480 
179,480 
44,295 
44,295 
10,000 
8,734 
34,000 
15,530 
147,973 
147,971

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 5-A (Cont.) COST AND FINANCIAL STATEMENT 
See Total Cost to 
Sect. Project Funding FY 83 FY 84 FY 85 FY 86 30 Sep 1986 
in Text 
14. Quinby Creek, VA 
15. Supervision of 
Harbor of Hampton 
Roads, VA 
(Regular Funds) 
16. Tangier Channel, VA 
(Regular Funds) 
17. Waterway on the 
Coast of VA 
(Regular Funds) 
18. York River, VA 
(Regular Funds) 
20. Virginia Beach, VA 
(Regular Funds) 
(Contributed Funds) 
22. Gathright Dam and 
Lake Moomaw, VA 
(Regular Funds) 
23. Richmond, VA 
(Regular Funds) 
New Work 
Approp 
Cost 
Maint. 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost' 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Cost 
New Work 
Approp 
Cost 
(-)13,418 
128,504 
- 40,766 
- 30,766 
212,000 230,912 247,759 
176,835 274,501 247,229 
(-)7,881 
66,945 
536,348 
536,346 
260,225 
261,036 
76,399 
76,401 
1,354,300 175,000 212,000 1,048,097 
1,001,236 547,251 211,272 900,425 
380,000 430,000 
363,513 384,330 
16,500 
16,350 
9,747 
10,183 
10,333 
330,000 
361,017 
104,176 
104,176 
771,973 
761,973 
5,103,824 
5,103,824 
116,550 
116,550 
2,414,829 
2,414,829 
850,498 
850,498 
10,910,729 
10,762,248 
180,904 
180,904 
204,854 
204,854 
4,270,195 
4,237,030 
204,683 
204,683 
193,721 
833,000 
838,172 
820,000 
914,128 
870,000 
852,484 
- 15.000 
- 80,670,527 
80,670,527 
880,842 7,257,842 
851,948 7,203,492 
584,000 
591,086 
599,000 
591,086 
5-16

NORFOLK, VA DISTRICT 
TABLE 5-A (Cont.) COST AND FINANCIAL STATEMENT 
See Total Cost to 
Sect. Project Funding FY 83 FY 84 FY 85 FY 86 30 Sep 1986 
In Text 
24. Saxis Island, VA New Work 
(Regular Funds) Approp - - 37,700 20,000 57,700 
Cost - - 21,670 14,693 36,363 
25. Scottsville, VA New Work 
(Regular Funds) Approp - 213,500 3,090,000 - 3,303,500 
Cost - 47,345 151,884 722,029 921,258 
26. Virginia Beach New Work 
Streams, Canal Approp 33,000 - 15,000 408,000 843,000 
Number 2, VA Cost 57,446 10,864 7,088 43.661 462,661 
Includes $292,096 for previous projects. 
2 Includes $52,804 for previous projects. 
s Costs prior to 1942 are included in the project "Baltimore Harbor and Channels, MD (Baltimore District). Costs listed are for York 
Spit Channel, VA and Cape Henry Channel, VA. 
4 Includes $445,291 military funds expended from new work dredging on existing project and $83,041 expended from military funds 
for construction-of a wharf. 
5 Includes $763,000 for previous projects. 
6 Includes $2,561,704 for previous projects and new work. 
' Includes $72,039 for previous projects. 
5-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 5-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1899 
July 25, 1912 
July 25, 1912 
Mar. 3, 1925 
July 3, 1930 
June 26, 1934 
Mar. 2, 1945 
July 3, 1958 
Dec. 31, 1970 
July 3, 1958 
Dec. 31, 1970 
Mar. 3, 1905 
Mar. 4, 1913 
July 3, 1930 
Mar. 2, 1945 
July 3, 1958 
Dec. 31, 1970 
Mar. 2, 1945 
Sept. 19, 1890 
July 14, 1960 
(Sec. 107) 
Mar. 2, 1945 
July 14, 1960 
(Sec. 107) 
May 17, 1950 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA. AND ST. JOHNS RIVER, FLA. 
(NORFOLK DISTRICT) (See Section 1 of Text) 
Existing project dimensions and original route, waterway 
from Norfolk, Va. to sounds of North Carolina 
Original route to Norfolk-Beaufort Inlet section 
Purchase of Albemarle & Chesapeake Co. Canal 
Purchase of Lake Drummond Canal (Dismal Swamp Canal) 
Construct a tidal lock at Great Bridge at a cost not to exceed 
$500,000 
Operating and care of works of improvement provided for with 
funds from War Department appropriations for rivers and 
harbors 
Construct dikes for protection of canal property against 
floodtides 
BALTIMORE HARBOR AND CHANNELS (NORFOLK 
DISTRICT) (See Section 2 of Text) 
CAPE HENRY CHANNEL, VA. (See Section 2 of Text) 
A channel 42 feet deep, 1,000 feet wide 
Channel depth increased to 50 feet 
RAPPAHANNOCK SHOAL CHANNEL, VA. 
(See Section 2 of Text) 
Channel 42 feet deep and 800 feet wide 
Channel width increased to 1,000 feet and depth increased 
to 50 feet. 
YORK SPIT CHANNEL, VA. (See Section 2 of Text) 
Channel 35 feet deep, 600 feet wide 
Channel width increased to 1,000 feet 
Channel depth increased to 37 feet 
Channel depth increased to 39 feet 
Channel depth increased to 42 feet 
Channel depth increased to 50 feet 
BROAD CREEK, VA. (See Section 3 of Text) 
Channel 7 feet deep, 100 feet wide 
CAPE CHARLES CITY HARBOR, VA (See Section 4 of Text) 
Dredging a channel through Cherrystone Inlet and bar 
CHINCOTEAGUE INLET, VA (See Section 5 of Text) 
Existing Project 
CRANES CREEK, VA (See Section 6 of Text) 
Entrance Channel 6 fet dep, 80 feet wide 
GREENVALE CREEK (See Section 7 of Text) 
Existing Project 
HAMPTON ROADS AND HARBORS OF NORFOLK AND 
NEWPORT NEWS, VA. COLLECTION AND REMOVAL 
OF DRIFT (See Section 8 of Text) 
Collection and removal of floating debris in Hampton roads and 
its tributary waters 5-18 
H. Doc. 317, 54th Cong., 1st sess. 
AR 1896 
H. Doc. 131, 55th Congs., 3d sess. 
AR 1899 
H. Doc. 391, 62d Congs., 2d sess. 
H. Doc. 589, 62d Cong., 2d sess. 
Rivers & Harbors Comm. Doc. 
67th Cong., 2d sess. 
S. Doc. 23. 71st Cong., 1st sess.' 
Not available 
H. Doc. 117, 76th Cong., 1st sess. 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers Report Sept. 21, 1970 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers Report, Sept. 21, 1970 
H. Doc. 186, 57th Cong., 2d sess. 
H. Doc. 190, 62d Cong., 3d sess. 
H. Doc. 29, 71st Cong., 1st sess. 
H. Doc. 741, 79th Cong., 2d sess. 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers Report Sept. 21, 1970 
H. Doc. 381, 76th Cong., 1st sess. 
unknown 
Approved in 1972 
H. Doc. 687, 76th Cong., 3d sess. 
Approved in 1965 
Specified in Act

NORFOLK, VA DISTRICT 
TABLE 5-B (Cont.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
JAMES RIVER, VA. (See Section 9 of Text) 
July 5, 1884 Channel 22 feet deep from mouth ot Richmond and construct spur 
and training dikes 
June 13, 1902 Extension of improvement to Richmond lock gate 
Mar. 3, 1905 Form a turning basin by widening channel at Richmond 
July 3, 1930 Channel 25 feet deep mouth to Richmond Deepwater Terminal 
Aug. 26, 1937 Removal of Trigg cofferdam 
Mar. 2, 1945 
May 17, 1950 
Oct. 23, 1962 
Turning basin at Richmond Harbor 
Maintaining turning basin at Rich mond Deepwater Terminal 
Channel depth increased to 35 feet to Richmond Deepwater 
Terminal 
LITTLE MACHIPONGO RIVER, VA (See Section 10 of Text) 
Jul. 3, 1930 Existing Project. 
S. Ex. Doc. 714, 47th Cong., 1st sess. 
H. Doc. 234, 56th Cong., 1st sess. 
H. Doc. 234, 56th Cong., 1st sess. 
H. Doc. 314, 71st Cong., 2d sess. 
Rivers & Harbors Comm. Doc. 68 
74th Cong., 1st sess. 2 
H. Doc. 738, 77th Cong., 2d sess. 
H. Doc. 191, 81st Cong., 1st sess. 
H. Doc. 586, 87th Cong.,2d sess. 
H. Doc. 260, 71st Cong., 2d sess. 
Mar. 2, 1907 
June 25, 1910 
Aug. 8, 1917 
Sept. 3, 1954 
Oct. 27, 1965 
June 25, 1910 
Aug. 8, 1917 
Mar. 30, 1925 
Aug. 30, 1935 
June 30, 1948 
Oct. 27, 1965 
Oct. 22, 1976 
NORFOLK HARBOR, VA. (See Section 11 of Text) 
Hampton Roads and Elizabeth River 
Channel 30 feet deep to Navy Yard 
Depth of 35 feet to Navy Yard. 
Depth of 40 feet and width of 750 feet to mouth of Southern 
Branch. 
Widen 40-foot channel to 1,500 feet from 40-foot contour in 
Hampton Roads to a point just south of Norfolk 
International Terminal. 
45 feet deep Ft. Wool to Lambert Point, 800 feet wide Norfolk 
International Terminal to Lambert Point. 
SOUTHERN BRANCH 
Channel with a depth of 22 and 25 feet. 
Depth of 40 feet and width of 450 feet from mouth to Belt Line 
.RR Bridge. 
Channel 30 feet deep and 375 feet wide to Virginia Ry. bridge: 
thence 25 feet deep and generally 200 feet wide to Norfolk & 
Western RR Bridge. 
Depth of 25 feet and width of 200 feet from Norfolk & Western 
RR bridge to a point 2,500 feet above with a turning basin 500 
feet square. 
Approach and turning area 40 feet deep and a maximum width 
of 830 feet opposite Norfolk Naval Shipyard: thence a channel 
35 feet deep and 375 and 250 feet wide to a point 1900.feet 
above Norfolk & Western RR bridge and a turning basin 35 
feet deep and 600 feet at upstream end. 
45 feet deep Belt Line bridge to Old Virginia bridge, 35-foot 
deep turning basirn opposite St. Julians Creek. 
Extend existing 35-foot project to a channel 35 feet deep arid 
250 feet wide upstream 1.5 miles to the Norfolk and 
Portsmouth Belt Line RR bridge and a turning basin at the 
mouth of Mains Creek 35 feet deep and 800 feet square. 
H. Doc. 381, 59th Cong., 1st sess. 
H. Doc. 551, 61st Cong., 2d sess. 
H. Doc. 140, 65th Cong., 1st sess. 
S. Doc. 122, 83rd Cong., 2d sess. 
H. Doc. 187, 89th Cong., 1st sess. 
H. Doc. 551, 61st Cong., 2d sess. 
H. Doc. 140, 65th Cong., 1st sess. 
H. Doc. 226, 68th Cong., 1st sess. 
H. Doc. 182, 73d Cong., 2d sess.2 
H. Doc. 545, 80th Cong., 2d sess. 
H. Doc. 187, 89th Cong., 1st sess. 
H. Doc. 355, 94th Cong., 2d sess. 
5-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 5-B (Cont.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
EASTERN BRANCH 
Mar. 2, 1907 Width of 500 feet and depth of 25 and 22 feet. 
Removel of shoals at mouth. 
Mar. 3, 1925 Depth of 25 feet and width of 200 feet from Norfolk & Western 
RR bridge to Virginia RR bridge. 
July 3, 1930 30-foot channel to a point opposite terminal of Imperial 
Tobacco Co. in Berkley. 
Mar. 2, 1945 Depth of 25 feet and width of 300 feet from Norfolk & Western 
RR bridge to Campostella bridge. 
WESTERN BRANCH 
Mar. 4, 1913 Channel 24 feet deep and 300 & 400 feet wide to West 
Norfolk highway bridge. 
July 3, 1930 For 18-foot channel to a point about 3,000 feet above West 
Norfolk highway bridge. 
SCOTTS CREEK 
July 3, 1930 Channel 12 feet deep and 100 feet wide to a point 100 feet above 
the Atlantic Coast Line RR bridge. 
ANCHORAGES 
June 25, 1910 30-foot anchorage'at Lambert Point 
Aug. 8, 1917 12-foot anchorage at Pinner Point 
Sept 3, 1954 An anchorage 38 feet deep and 1,500 feet square: anchorage 
35 feet deep and 1,500 feet square and an anchorage 20 
feet deep, 1,000 feet wide and 3,000 feet long. 
Oct. 27, 1965 Two anchorages opposite Sewells Point 45 feet deep with 
1,200-foot swinging radius. 
NOTTAWAY RIVER, VA (See Section 12 of Text) 
July 14, 1960 Existing Project 
PARKER CREEK, VA (See Section 13 of Text) 
Jul. 14, 1960 Existing Project 
(Sec. 107) 
QUINBY CREEK, VA (See Section 14 of Text) 
May 17, 1950 Existing project. 
TANGIER CHANNEL, VA (See Section 16 of Text) 
Mar. 2, 1919 Channel from Tangier Sound and anchorage 
Jan. 3, 1934 
(P.W.A. Act) 
& Aug. 30, 1935 
Mar 2, 1945 Modified project dimensions 
Jul. 14, 1960 Channel across Tangier Island 
(Sec. 107) 
H. Doc. 373, 59th Cong., 1st sess. 
Specified in act 
H. Doc. 226, 68th Cong., 1st sess. 
H. Doc. 37, 71st Cong., 1st sess.3 
H. Doc. 224, 76th Cong., 1st sess. 
H. Doc. 556, 62nd Cong., 2d sess. 
H. Doc. 265, 70th Cong., 1st sess. 
H. Doc. 189, 70th Cong., 1st sess. 
H. Doc. 551, 61st Cong., 2d ses,. 
H. Doc. 605, 63rd Cong., 2d sess.' 
S. Doc. 122, 83rd Cong., 2d sess. 
H. Docs. 187 & 143, 89th Cong., 1st sess. 
Approved in 1965 
Approved in 1964. 
H. Doc. 241, 81st Cong., 1st Session 
H. Doc. 107, 63rd Cong., 1st Sess. 
Rivers and Harbors Comm. 
Doc. 51, 72nd Cong., 2d sess. 
H. Doc. 141, 77th Cong., 1st sess. 
Approved in 1964 
5-20

NORFOLK, VA DISTRICT 
TABLE 5-B (Cont.) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 25, 1910 
Mar. 2, 1945 
Oct. 27, 1965 
(Sec. 107) 
June 14, 1880 
1884 
1887 
Sept. 3, 1954 
Oct. 23, 1962 
Mar. 7, 1974 
July 24, 1946 
Aug. 15, 1985 
July 24, 1946 
1948 
(Sec. 205) 
Oct. 27, 1965 
(Sec. 201) 
WATERWAY ON THE COAST OF VIRGINIA 
(See Section 17 of the Text) 
Existing project adopted. 
Project modified. 
Project widened to 100 feet, partially relocated, and 
incorporated in Delaware Bay-Chesapeake Bay Waterway in 
Delaware-Maryland-Virginia. 
YORK RIVER, VA (See Section 18 of Text) 
Project Authorized 
Project Modified 
Project Modified 
VIRGINIA BEACH, VA (See Section 20 of Text) 
Project authorized. 
Project modified. 
Project modification authorized for Phase I Advanced 
Engineering and Design. 
GATHRIGHT DAM AND LAKE MOOMAW, VA 
(See Section 22 of Text) 
Project authorized. 
RICHMOND, VA (See Section 23 of Text) 
Existing project. 
SAXIS ISLAND, VA (See Section 24 of Text) 
Existing project. 
SCOTTSVILLE, VA (See Section 25 of Text) 
Project Approved 
VA. BEACH STREAMS, CANAL NO. 2, VA. BEACH, VA. 
(See Section 26 of Text) 
Project authorized. 
H. Doc. 957, 60th Cong., 1st sess. 
H. Doc. 268, 76th Cong., 1st sess. 
Approved in 1970. 
H. Doc. 186, 83rd Cong., 1st sess. 
H. Doc. 382, 87th Cong., 2d sess. 
H. Doc. 365, 92nd Cong., 2d sess. 
H. Doc. 325, 61st Cong., 2d sess 
H. Doc. 178,98th Cong., 2nd Session 
Approved in 1986 
H. Doc. 551, 84th Cong., 1st sess. 
H. Doc. 640, 94th Cong., 2d sess. 
5-21 
' Contains latest published map.s For latest published map. See H. Doc. 1246. 62d Cong., 3d Sess. 
2 Included in Emergency Relief Administration Program May 23, 1935.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 5-C 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK VA. AND ST. JOHNS RIVER, FLORIDA: 
DATA RELATIVE TO THE COMPLETED LOCKS 
(See Section 1 of Text) 
Dimensions 
Greatest 
Length Depth on 
Width Avail- Year 
of able Miter Sills Opened 
Miles Cham- for Full Character to 
from Location ber Width Lift Upper Lower of Navi- Cost 
Norfolk, Va. feet (feet) (feet) (feet) (feet) Foundation gation 
12.4 Albemarle and Chesa- 75 600 2.7 Piles in sand 1932 $499,913 
peake Canal (Great and shells 
Bridge, Va.) 
10.7 Dismal Swamp Canal 52 300 12 12 12 Natural earth 1940 $348,879 
(Deep Creek) with cutoff 
walls 
33.1 Dismal Swamp Canal 52 300 12 12 13 Natural earth 1941 $372,556 
(South Mills, N.C.) with cutoff walls 
'16 feet at mean low water 
5-22

NORFOLK, VA DISTRICT 
TABLE 5-D OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Full Cost to Sept. 30, 1986 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintenance Contributed Funds 
Appomattox River, Va. 1 
Aberdeen Creek, Va.2 
Blackwater River, Va. 
Active portion2 1 
Carters Creek, Va. 
Active portion2 3 
Channel to Newport News, VA 
Channel from Phoebus, Va. 
to deepwater in Hampton Roads 2 
Channel connecting York River, Va. 
Back Creek to Slaights Wharf2 
Chesconessex Creek, Va.2 
Chincoteague Bay, VA 
Chincoteague Harbor of Refuge, VA 
Chowan River, N.C.2 
Cockrells Creek, Va.4 
Davis Creek, Va.2 
Deep Creek, Accomack Co., Va. 
Deep Creek, Newport News, Va.2 
Dymers Creek, Va.2 
Hampton Creek, Va. 
Horn Harbor, Va. 2 
Hoskins Creek, Va.2 
Jackson Creek, Va.2 
Jarvis Creek, Va.4 
Kings Creek, Va.4 
Lafayette River, Va. 2 
Little River (Creek), Va.2 
13 
Locklies Creek, Va.2 
Lynnhaven inlet, VA 
Meherrin River, N.C. 2 
Milford Haven, Va.2 
Mill Creek, Va.2 
Mulberry Creek, Va.2 
Nandua Creek, Va.2 
Nansemond River, Va.8 
Newport News Creek, Va.2 
Occohannock Creek, Va. 
Active portion2 
Onancock River, Va.2 5 
Oyster Channel, VA 2 
Pagan River, Va.26 
Pamunkey River, Va. 
Active portion2 
Parrotts Creek, Va.2 
Portsmouth Harbor, Va. Channel to 
Nansemond Ordnance Depot 2 
1980 
1975 
1975 
1951 
1985 
1944 
1950 
1968 
1984 
1985 
1975 
1949 
1971 
1974 
1980 
1953 
1981 
1964 
1977 
1971 
1979 
1957 
1982 
1966 
1928 
1985 
1950 
1950 
1937 
1950 
1950 
1978 
1962 
1951 
1963 
1984 
1950 
1964 
1957 
1947 
$870,341 $863,140 
109,643 200,893 
342,118 151,735 
28,398 3,277 
8,955.974 5,720,969 
11,500 
14,855 
25,516 
25,126 
49,396 
107,220 
97,612 
83,000 
288,278 
5,582 
186,237 
13,987 
44,100 
8,500 
39,259 
5,593 
242,047 
168,623 
11,581 
445,354 
47,734 
24,568 
5,445 
2,393 
6,988 
167,477 
135,600 
13,859 
187,914 
119,117 
51,425 
31,376 
37,045 
165,566 
32,442 
36,874 
31,889 
371,984 
132,327 
158,323 
39,675 
2,054,201 
4,610 
1,116,952 
88,488 
622,801 
34,437 
153,598 
442,033 
9,560 
2,098,035 
49,591 
32,322 
4,346 
2,458 
39,804 
426,777 
147,570 
78,283 
427,233 
630,353 
284,381 
161,183 
37,771 
66,162 
5-23 
19,300 
1,200 
2,500 
5,700 
4,000 
62,969 
500 
188,962 
16,955 
98,580

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Queens Creek 2 
Rappahannock River, Va.9 10 12 
Rappahannock River at 
Bowlers Wharf, Va.4 
Starlings Creek, Va. 2 
Taskinas Creek, Va. 
Thimble Shoal. Channel, VA 2 
Totuskey Creek, Va. 
Tylers Beach, Va.2 
Urbanna Creek, Va.2 7 
Whitings Creek, Va. 
Winter Harbor, Va. 2 
Willoughby Channel, Va. 2 
Wishart Point Channel, Va. 2 
1979 
1983 
1950 
1981 
1975 
1985 
1970 
1982 
1963 
1971 
1981 
1953 
1975 
Ilncludes $22,500 for previous projects. 
2Completed. 
31n addition, $700 for maintenance was expended from 
contributed funds. 
4lnactive. 
5lncludes $33,549 for new work and $24,754 for maintenance 
for previous projects. 
6lncludes $20,671 for new work for previous projects. 
TABLE 5-E 
26,949 101,803- 
414,633 1,958,360- 
66,242 603,632- 
7,479 135 - 
13,534,967 11,025,732- 
167,869 450,693 2,000 
261,201 404,943- 
55,724 106,868- 
21,630 112,333 500 
171,334 291,048 2,973 
8,500 42,485- 
118,762 102,244 30,625 
71n addition, $61,087 was expended for rehabilitation. 
8lncludes $30,000 for new work and $7,000 for maintenance 
for previous projects. 
9 In addition, $168,091 was expended for rehabilitation. 
10 lncludes $197,146 for previous new work projects. 
1 1Includes $15,000 for new work for previous projects. 
12lncludes $113,500 for previous maintenance projects. 
13Federal funds expended by the U.S. Navy for new work. 
For Last Full Cost to Sept. 30, 1986 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintenance Contributed Funds 
Anderson Park. 1979 $471,474 - $176,671 
Newport News, Va 
Hampton Institute 1976 S$156.906 - $175,845 
TABLE 5-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Full Cost to Sept. 30, 1986 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintenance Contributed Funds 
Buena Vista, Va. 1977 $ 417,900' - 
Newmarket Creek, Va. 1970 1,000,000 12,283 $550,097 
Norfolk Floodwall, Va. 1973 1,851,933 32,877 516,256 
Richmond Filtration Plant, VA 1985 478,224- 
Salem Church Lake, Va. 1976 1,896,716' 2 - - 
'Preconstruction planning terminated. 2lncludes $144,785 for previous projects. 
5-24 
OTHER AUTHORIZED BEACH EROSION

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 5-G 
Name of Project 
RECONNAISSANCE AND CONDITION SURVEYS 
Date Survey 
Conducted 
CONDITION SURVEYS 
Baltimore Harbor 
Cape Henry Channel 
Rappahannock Shoal Channel 
Jul 1986 
Oct - Nov 1985 
Dam Neck Disposal Area Jul 1986 
Guilford Creek Jul 1986 
James River 
Richmond Deepwater Terminal 
Turkey Island 
Nov 1985 
Nov 1985 
Norfolk Harbor 
45' Channel 
Craney Island Pipeline 
Rehandling Basin 
Southern Branch 
Dec 1985 
Feb 1986 
Jan 1986 
Mar 1986 
Mar 1986 
Mar 1986 
Rudee Inlet 
Scotts Creek 
RECONNAISSANCE SURVEYS 
None this fiscal year. 
5-25

WILMINGTON, N. C., DISTRICT * 
This district comprises central and eastern North 
Carolina and a portion of south-central Virginia, embraced 
in drainage basins tributary to the Atlantic Ocean from 
the southern boundary of Virginia to the Shallotte River, 
inclusive, with exception of the Meherrin River Basin 
above Murfreesboro, N. C., the Chowan River Basin above 
the confluence of the Nottaway and Blackwater Rivers, 
and the Pasquotank River and its tributaries for navigation 
only. Also included are those portions of the Yadkin- 
Pee-Dee and Catawba River basins within the state of 
N. C. as well as a portion of the Atlantic Intracoastal 
Waterway from the northern boundary of North Carolina 
to Little River, S. C., and a portion of the waterway from 
Norfolk, Va., to the Sounds of North Carolina, south of the 
north shore of Albemarle Sound. 
IMPROVEMENTS 
Navigation Page 
1. Aquatic Plant Control 
(R & H Actof 1965)................ .......... 6-2 
2. Atlantic Intracoastal Waterway 
Between Norfolk, Va. and St. Johns 
River, Fla. (Wilmington District)..............6-2 
3. Avon Harbor,N.C........... .......... 6-4 
4. Beaufort Harbor, N. C........................6-4 
5. Belhaven Harbor, N. C.......................6-4 
6. Cape Fear River, N. C. Above Wilmington....... 6-5 
7. Channel from Back Sound to 
Lookout Bight, N. C......................6-5 
8. Lockwoods Folly River, N. C.. .......... 6-5 
9. Manteo (Shallowbag) Bay, N. C................. 6-6 
10. Morehead City Harbor, N. C...................6-7 
11. Ocracoke Inlet, N. C...................... 6-7 
12. Pamlico and Tar Rivers, N. C................ 6-7 
13. Rollinson Channel, N. C............ .......... 6-8 
14. Silver Lake Harbor, N. C.....................6-8 
15. Waterway Connecting Pamlico Sound 
and Beaufort Harbor, N. C....................6-8 
16. Wilmington Harbor, N. C....................6-9 
Flood Control 
17. 
18. 
18A. 
18B. 
19. 
20. 
21. 
21A. 
22. 
23. 
Ararat River, Mount Airy, N. C...............6-9 
Cape Fear River Basin, N. C..................6-10 
B. Everett Jordan Dam and Lake, N. C........ 6-10 
Randleman Lake, N. C.................. 6-11 
Carolina Beach and Vicinity, N. C.............. 6-11 
Leesville, Va., Roanoke River, 
Sec. 32, Demo. Project......................6-12 
Neuse River Basin, N. C................ 6-12 
Falls Lake, N. C.......................6-12 
Scuppernong River, N. C................ 6-13 
Stuart, Va....................... .......... 6-13 
Page 
24. Yadkin River Basin, N. C. and S. C............ 6-13 
24A. W. Kerr Scott Dam and 
Reservoir, N. C...... ..... ................ 6-13 
25. Inspection of Completed 
Flood Control Projects...................6-14 
26. Flood Control Work Under 
Special Authorization...................6-14 
Multiple-Purpose Projects, 
Including Power 
27. Roanoke River Basin, Va. and N. C.......... 
27A. John H. Kerr Dam and Reservior, 
Va. and N. C....................... 
27B. Philpott Lake, Va................ ....... 
28. Scheduling Flood Control 
Reservoir Operations.................... 
... 6-14 
... 6-14 
... 6-15 
... 6-15 
General Investigations 
29. Surveys........................ ......... 6-16 
30. Collection and Study of Basic Data...........6-16 
31. Continuation of Planning 
and Engineering.......................6-17 
32. Advance Engineering and Design............. 6-17 
Tables Page 
Table 6-A Cost and Financial Statement......... 6-18 
Table 6-B Authorizing Legislation.............. 6-22 
Table 6-C Other Authorized 
Navigation Projects.................6-25 
Table 6-D Other Authorized Beach Erosion 
Control Projects....................6-26 
Table 6-E Other Authorized Flood Control 
Projects........................6-27 
6-1

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
Page 
Not Applicable 
Deauthorized Projects................ 6-28 
Reconnaissance and 
Condition Surveys...................6-29 
Table 6-I Navigation Work Under 
Special Authorization................. 6-29 
Table 6-J Dams and Reservoirs................. 6-30 
Table 6-K Flood Control Work Under 
Special Authorization................6-31 
Navigation 
1. AQUATIC PLANT CONTROL (RIVER AND HARBOR 
ACT OF 1965) 
Location. Navigable waters, tributary streams, connecting 
channels, and other allied waters in Wilmington 
District. 
Existing project. The existing project provides for control 
and progressive eradication of water-hyacinth, 
alligatorweed, Eurasian watermilfoil, and other obnoxious 
aquatic plant growths from navigable waters, tributary 
streams, connecting channels, and other allied waters of 
the United States, in the combined interest of navigation, 
flood control, drainage, agriculture, fish and wildlife conservation, 
public health, and related purposes, including 
continued research for development of the most effective 
and economic control measures in cooperation with other 
Federal and State agencies in accordance with the report 
of the Chief of Engineers, House Document 251, 89th Congress, 
1st session. The project was authorized by Section 
302, 1965 River and Harbor Act (H.D. 25, 89th Cong., 1st 
sess.). The Act provides that research and planning costs 
shall be borne fully by the United States. 
Local cooperation. Local interests must agree to hold 
the United States free from damages that may occur from 
operations performed in connection with this project, and 
participate to the extent of 30 percent of the cost of the 
program. Requirements are being met. 
Operations and results during fiscal year. New work: 
Operations for FY86 included chemical and biological control 
efforts on 132 acres of hydrilla and chemical control on 
46 acres of alligatorweed. Sonar treatment was applied to 
32 acres of hydrilla at three lakes in William B. Umstead 
State Park. Triploid grasscarp were placed in Lake 
Wheeler to control 100 acres of hydrilla. 
Successful FY85 alligatorweed control efforts reduced 
the area which required treatment on the Scuppernong 
and navigable tributaries to 3 acres. Herbicide application 
was expanded in the Scuppernong Basin this year to include 
major drainage canals with an additional 11 acres 
treated in those areas. Alligatorweed in the Little River 
Basin required limited spot applications that totaled about 
0.5 acres. The Pasquotank River Basin was added as a 
treatment area this year with 27 acres treated. Four and 
one half acres required retreatment. 
Planning efforts included investigations for and the 
preparation of supplemental information reports for the 
inclusion of major drainage canals in the Scuppernong 
Basin and sites in the Pasquotank River Basin in the program. 
Studies for the inclusion of Egeria sp. as a new problem 
plant species are ongoing. Investigations of the 
Lumber River as alligatorweed treatment area and two 
new hydrilla sites were initiated and several reconnaisance 
investigations of aquatic weed problems in 
response to requests by others were made. Control work 
was accomplished for $55,701. Planning was accomplished 
at a Federal Cost of $28,216. 
Condition at end of fiscal year. No hydrilla is known to 
be growing in any of the Umstead State Park Lakes at this 
time; however, tubers are present and regrowth is expected. 
It appears that all three lakes in Umstead State 
Park will require herbicide treatment in FY87. The sterile 
triploid grasscarp stocked in Lake Wheeler provided control 
early in the recreation season but by mid-summer 
hydrilla reached the problem level. It is expected that the 
grasscarp will be large enough during the 1987 growing 
season to provide good control throughout the year. 
Alligatorweed is under maintenance control in the Scuppernong 
River, Little River and their major tributaries. 
These sites should require only spot treatments in FY87; 
however, the Pasquotank River and tributaries will require 
extensive weed control operations. 
Alligatorweed and hydrilla treatment sites presently 
under investigation will likely be added to the program 
this fiscal year. Investigations of aquatic weed problems, 
in response to requests by county governments and 
municipalities, may result in the addition of new treatment 
sites and species in future years. 
2. ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA., AND ST. JOHNS 
RIVER, FLA. (WILMINGTON DISTRICT) 
Location. The project is located on the east coast of the 
United States, between Norfolk, Va., and St. Johns River, 
Florida. The section within Wilmington District begins at 
the Virginia-North Carolina State line and extends 
generally southerly and southwestwardly to Little River, 
S. C., a total of 308 statute miles. (See Coast and Geodetic 
Survey Charts 830 to 842, inclusive.) 
Previous projects. For details see Annual Reports for 
1915, 1926, 1932, and 1938. 
Existing project. The authorized project provides for a 
waterway, 12 feet deep, with widths varying from 90 feet 
in land cuts to 300 feet in open waters; the construction, 
operation and maintenance of suitable bridges; saltwaterintrusion 
preventive measures in the vicinity of Fairfield, 
N. C.; a channel in Peltier Creek, 6 feet deep and 50 feet 
6-2 
Tables 
Table 6-F 
Table 6-G 
Table 6-H

WILMINGTON, N. C., DISTRICT 
wide from the Intracoastal Waterway in Bogue Sound to 
and including a basin in Peltier Creek, 6 feet deep, 200 feet 
wide, and 600 feet long; a channel, 6 feet deep and 90 feet 
wide between the Intracoastal Waterway and the gorge in 
Bogue Inlet, then 8 feet deep and 150 feet wide across the 
ocean bar; a channel, 12 feet deep and 90 feet wide to a 
turning basin, 200 feet wide and 350 feet long, at 
Swansboro; a channel, 6 feet deep and 90 feet wide in New 
River Inlet, and a connecting channel of the same dimensions 
to the Intracoastal Waterway near the mouth of New 
River; a channel, 10 feet deep, and 90 feet wide in New 
River, between the Intracoastal Waterway and the 
Seaboard Coastline Railroad bridge at Jacksonville, N. C.; 
a channel through New Topsail Inlet, 8 feet deep and 150 
feet wide and a channel from New Topsail Inlet to the Intracoastal 
Waterway by way of Old Topsail Creek, 7 feet 
deep and 80 feet wide; a channel, 7 feet deep and 80 feet 
wide, in Banks Channel, from New Topsail Inlet, paralleling 
the barrier beach, to the Atlantic Intracoastal Waterway; 
a channel, 14 feet deep and 400 feet wide, across the 
ocean bar at Masonboro Inlet, with suitable jetties at the 
entrance, thence 12 feet deep and 90 feet wide to the channel 
of the Intracoastal Waterway at Wrightsville by way 
of Banks and Motte Channels; a turning basin, 15 feet 
deep, 300 feet wide, and 700 feet long, on the east side of 
Banks Channel near Masonboro Inlet, with three 15-pile 
dolphins therein; a channel, 8 feet deep and 150 feet wide 
across the ocean bar at Carolina Beach Inlet to the Atlantic 
Intracoastal Waterway; a channel, 6 feet deep, 80 feet 
wide, and 8,000 feet long, to and including a turning basin 
of the same depth, 130 feet wide and 180 feet long, at 
Carolina Beach; a yacht basin, 230 feet wide, 450 feet long, 
and 12 feet deep, at the town of Southport, connected to 
the waterway by a suitable channel of the same depth; and 
maintenance of the general navigation features of the 
North Carolina State Ports Authority Small-Boat Harbor 
at Southport, consisting of an entrance channel, 150 feet 
wide and 400 feet long, an eastern harbor-access channel, 
70 feet wide and 430 feet long, a western harbor-access 
channel, 60 feet wide and 185 feet long, to a turning basin, 
180 feet wide and 550 feet long, all to a depth of 6 feet. A 
modification providing for the replacement of five Federally 
owned and operated highway bridges was authorized in 
December 1970. A modification providing for 100 percent 
Federal funding for Walter B. Jones (formerly Wilkerson 
Creek) and Coinjock bridges was authorized in October 
1976. Estimated Federal Cost is $46,100,000 (1986). The 
tidal lock at Snow's Cut was deauthorized September 23, 
1986, under authority of Sec. 12, PL 93-251.The south jetty 
at Masonboro Inlet has an estimated Federal cost of 
$9,110,000 (1986) and is complete except for the training 
wall. A Section 111 project to mitigate damages caused by 
the north jetty was authorized in October 1980 and was 
completed in April 1981. Length of channels and basins 
total 347.7 miles. Plane of reference is mean low water. 
In the waterway north of Neuse River, variations in 
water surface due to winds seldom exceed 2 feet above or 
below mean stage. Between Beaufort and the Cape Fear 
River, normal tidal range varies from 3.5 feet at the inlets 
to 1 foot at points between. Average range of tide is 4 feet 
on the ocean side of Bogue Inlet and 2.5 feet just inside the 
inlet. At New River, tidal range varies from 3.5 feet at the 
inlet to 1 foot at the head of the marshes and zero at Tar 
Landing, 31 miles above. From Cape Fear River, N. C., to 
Little River, S. C., mean tidal range varies between 4.7 
feet in Cape Fear River and 4 feet at the intermediate inlets, 
and 2 feet at points midway between the inlets. On October 
15, 1954 (Hurricane Hazel), the tide at Holden Beach 
reached an elevation of 17.6 feet. (See Table 6-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date except 
for the uncompleted modifications. The State of North 
Carolina has agreed to keep the bridges toll free and upon 
completion of each bridge, accept maintenance, replacement, 
and ownership responsibilities thereof. They have 
withdrawn their offer to contribute 25 percent of the first 
cost. The Water Resources Act of 1976 modified the terms 
of local cooperation to delete the non-Federal cost-sharing 
requirement for the Walter B. Jones (formerly Wilkerson 
Creek) and Coinjock bridges. The three remaining bridges 
were not included in this modification and are awaiting additional 
authorization to reflect 100 percent Federal 
funding. 
Operations and results during fiscal year. New work: 
Settlement of a claim on Wilkerson Creek Bridge cost 
$5,070,724. Replacement of Coinjock Bridge was continued 
at a cost of $2,253,524. Maintenance: During intermittent 
periods the U. S. sidecasting dredge Merritt removed 
72,284 cubic yards from shoals in New River Inlet at a cost 
of $222,851; 56,067 cubic yards from shoals in Bogue Inlet 
at a cost of $190,335; and 2,898 cubic yards from shoals in 
Carolina Beach Inlet at a cost of $32,441. The Merritt incurred 
cost of $559 at New Topsail Inlet. During intermittent 
periods the U. S. hopper dredge Currituck removed 
126,015 cubic yards from shoals in Carolina Beach Inlet at a 
cost of $320,777; and 87,875 cubic yards from shoals in New 
River Inlet at a cost of $168,977. The Currituck had a 
negative cost of -$1,024 at Bogue Inlet. During intermittent 
periods the U. S. sidecasting dredge Fry removed 
80,900 cubic yards from shoals in Bogue Inlet at a cost of 
$292,857; 129,344 cubic yards from shoals in New Topsail 
Inlet at a cost of $312,012; 51,194 cubic yards from shoals in 
New River Inlet at a cost of $125,228; and 29,733 cubic 
yards from shoals in Carolina Beach Inlet at a cost of 
$70,613. During intermittent periods the U. S. debris boat 
Snell conducted clearing and snagging operations and 
maintained dredging ranges and mooring facilities at a 
cost of $282,560. Between November 8, 1985 and July 17, 
1986, the contract dredge XL removed 921,871 cubic yards 
from shoals in the through channel at a cost of $3,013,169. 
Between April 10 and August 3, 1986, the contract dredge 
American removed 1,997,521 cubic yards from shoals in 
Masonboro Inlet for sand bypassing at a Federal cost of 
$2,305,757 and non-Federal cost of $655,300. The non- 
Federal share was for pumping additional material to 
Wrightsville Beach. Design costs for dredging in fiscal 
year 1987 was $43,310. Marking of easements along the 
AIWW cost $23,083. Easement and boundary surveys in 
Onslow, Pender and New Hanover Counties cost $148,283. 
6-3

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
Mosquito control in disposal areas cost $31,102. Disposal 
area stabilization at Swansboro and Sneads Ferry cost 
$4,306. Monitoring at Carolina Beach Inlet and Masonboro 
Inlet cost $12,864. Archeological investigations of sounds 
and inlets cost $6,602. Trash removal at Snow's Cut cost 
$1,200. Structural repairs to three remaining highway 
bridges cost $946,804. Reimbursement for damage to 
bridges was -$58,349. Condition and operation studies cost 
$440,015. Four highway bridges and utilities were 
operated and maintained at a cost of $626,854. 
Condition at end of fiscal year. The project was completed 
in September 1983 except for the training wall and three 
tie-up dolphins at Masonboro Inlet and the bridge replacement 
program. Coinjock Bridge was completed on 
November 13, 1986. Total cost for existing project to 
September 30, 1986 was $115,825,289, of which $41,624,019 
was for new work including $86,851 in contributed funds 
and $74,201,270 was for maintenance, including $667,300 in 
contributed funds. 
3. AVON HARBOR, N. C. 
Location. The project is located on the east coast of 
North Carolina, 9 miles north of Cape Hatteras. (See Coast 
and Geodetic Survey Chart 1232.) 
Existing project. The authorized project provides for a 
direct channel 6 feet deep, 100 feet wide, and 3.5 miles long 
from the depth in Pamlico Sound southeast to a basin of 
the same depth, 100 feet wide and 300 feet long at Avon. 
Plane of reference is mean low water. Variations in the 
water surface of Pamlico Sound due to winds, seldom 
range as much as 2 feet above or below mean stage; 
however, severe windstorms will double or triple that 
variation. The original project was authorized by the 1945 
River and Harbor Act (H.D. 316, 76th Cong., 1st sess.) and 
modification for direct channel authorized May 5, 1965, 
under Section 107, River and Harbor Act of 1960. 
Local cooperation. Fully complied with. 
Terminal facilities. There are five wharves in the basin 
at Avon, with a total frontage of about 300 feet. These 
facilities are considered adequate for present commerce. 
Operations and results during fiscal year. Maintenance: 
Between March 7 and May 25, 1986, the contract dredges 
Blue Ridge and Richmond removed 12,541 cubic yards 
from shoals at Avon at a cost of $264,426. Contributed 
funds of $74,986 were expended on dikes for pipeline 
dredging. 
Condition at end of fiscal year. The project was completed 
July 1965. (For further details, see Annual Report 
for 1962.) 
4. BEAUFORT HARBOR, N. C. 
Location. The project is just inside Beaufort Inlet, adjacent 
to Morehead City Harbor. (See Coast and Geodetic 
Survey Chart 420.) 
Previous projects. For details see Annual Reports for 
1915 and 1938. 
Existing project. The authorized project provides for 
stopping erosion at Beaufort Inlet by jetties and sand 
fences at Fort Macon and Shackleford points and other 
shore protection; channels 15 feet deep at mean low water 
and 100 feet wide in Bulkhead and Gallants Channels, except 
for a depth of 12 feet in the upper 5,000 feet of 
Gallants Channel; a harbor of refuge in Town Creek 12 feet 
deep, 400 feet wide, and 900 feet long connected to 
Gallants Channel by a channel 12 feet deep, 150 feet wide, 
and 1,400 feet long; a basin 12 feet deep, 600 feet wide in 
front of the town of Beaufort except for a channel 15 feet 
deep, 100 feet wide through the basin; a stone bulkhead 
from Town Marsh across Bird Shoal to the west end of 
Carrot Island; a channel 14 feet deep, 70 feet wide, and 
1,900 feet long from Bulkhead Channel to a turning basin 
14 feet deep, 150 feet wide and 300 feet long near the upper 
end of Morgan Creek; and a channel in Taylors Creek 
15 feet deep, 100 feet wide, extending about 2.6 miles 
easterly from about opposite Marsh Street in Beaufort to 
Lennoxville Point at North River, except for an 800-footlong 
section at the east end which is 12 feet deep. Total 
length of channels is 7.3 miles. Average tidal range is 2.5 
feet at Beaufort and 3.5 feet at the inlet. (See Table 6-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. There are fifty waterfront facilities 
with a total frontage of 2,000 feet. These facilities are adequate 
for present commerce. 
Operations and results during fiscal year. Maintenance: 
Cost in connection with prior year dredging was $7,840. 
Design for pipeline dredging in fiscal year 1987 was 
$17,692. Condition and operation studies cost $25,689. 
Condition at end of fiscal year. The project was completed 
in October 1965 except for the Morgan Creek 
modification which was completed November 12, 1983. 
(For further details see Annual Report for 1962.) Costs 
under existing project to September 30, 1986, were 
$827,040 for new work,including $34,000 contributed funds 
and $3,054,893 for maintenance, including $168,833 contributed 
funds, a total of $3,881,933. 
5. BELHAVEN HARBOR, N. C. 
Location. The town of Belhaven is at the junction of 
Pantego Creek and Pungo River, about 11 miles above the 
mouth of the latter. The harbor consists of the lower 
reaches of Pantego Creek and is about 6,000 feet long. 
Pungo River forms part of the Intracoastal Waterway between 
Norfolk and the St. Johns River. Norfolk is 130 miles 
north of Belhaven and Beaufort 66 miles south. (See U. S. 
Coast and Geodetic Survey Chart No. 123.) 
Existing project. This provides for a channel 12 feet 
deep at mean low water and 100 feet wide, extending from 
deep water in Pungo River to a point about 800 feet east of 
the highway bridge, with a turning basin 800 feet long and 
300 feet wide at the upper end; and for the construction of 
6-4

WILMINGTON, N. C., DISTRICT 
timber breakwaters at the mouth of Pantego Creek. Pungo 
River is a nontidal stream with little slope. Variations in 
the water surface, due to winds, seldom exceed 2 feet 
above or below mean stage. The project was authorized by 
River and Harbor Acts of July 3, 1930 and June 20, 1938. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 12 wharves along the 
town waterfront, all of timber construction; one is owned 
by the town and is open to all without charge; four have 
rail connections. The facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. Maintenance: 
Inspection of timber breakwaters cost $13,800. 
Condition at end of fiscal year. The project was completed 
in September 1940. 
6. CAPE FEAR RIVER, N. C. 
ABOVE WILMINGTON 
Location. The river is formed by confluence of the Deep 
and Haw Rivers at Moncure, Chatham County, N. C., and 
empties into the Atlantic Ocean at Cape Fear, near the 
southern extremity of the State. (See Coast and Geodetic 
Survey Chart 426.) 
Previous projects. For details see Annual Reports for 
1915 and 1938. 
Existing projects. The authorized project provides for a 
channel 25 feet deep and 200 feet wide from Wilmington to 
a turning basin 400 feet wide and 550 feet long at Navassa 
(2.9 miles); a channel 12 feet deep and 140 feet wide from 
Navassa to mileboard 30 at Acme, with five channel 
cutoffs, 12 feet deep and 150 feet wide to eliminate sharp 
bends; a channel 8 feet deep from mileboard 30 to 
Fayetteville by constructing three locks and dams and by 
dredging river shoals; and recreational facilities at the 
locks and dams. Total length of the project channels is 
113.9 miles. The project was authorized by River and 
Harbor Acts of June 25, 1910; June 26, 1934; August 30, 
1935; August 26, 1937; October 27, 1965; and Section 4, 
Flood Control Act of 1944. For further details see Annual 
Reports for 1962 and 1970. 
Local cooperation. Fully complied with. 
Terminal facilities. There are twelve waterfront 
facilities on the river, with a total frontage of 1,190 feet. 
Operations and results during fiscal year. Maintenance: 
During intermittent periods the U. S. debris boat Snell 
snagged and cleared and maintained the buoy systems at 
the locks at a cost of $101,516. Design of portages at the 
locks cost $657. Design for pipeline dredging in fiscal year 
1986 cost $26,779. A feasibility study on spillway repairs 
cost $9,736. Periodic inspections and evaluation of the 
three locks and dams cost $39,841. Repairs and installation 
of dikes at lock and dam no. 1 cost $25,542. Condition and 
operation studies cost $51,926. Operation and maintenance 
of three locks and dams cost $212,699. 
Condition at end of fiscal year. The project was 
completed in June 1970. Total costs of existing project to 
September 30, 1986, were $16,205,198 of which $3,610,454 
(including $1,226,385 public works) was for new work and 
$12,594,744 for maintenance. 
7. CHANNEL FROM BACK SOUND TO LOOKOUT 
BIGHT, N. C. 
Location. The project is located on the coast of North 
Carolina, 8 miles east of Beaufort Inlet. (See Coast and 
Geodetic Survey Chart 420.) 
Existing project. The authorized project provides for a 
channel 100 feet wide and 7 feet deep from Back Sound, 
through Shackleford Banks to Lookout Bight. The project 
was authorized by River and Harbor Acts of August 26, 
1937, and March 2, 1945. For details see Annual Report for 
1959. 
Local cooperation. Fully complied with. 
Terminal facilities. Not required. 
Operations and results during fiscal year. Maintenance: 
The dredge Currituck incurred cost of $739. Archeological 
investigations cost $3,068. Disposal area stabilization at 
Bardens Inlet cost $566. Condition and operation studies 
cost $8,381. 
Condition at end of fiscal year. The project was completed 
in May 1965. 
8. LOCKWOODS FOLLY RIVER, N. C. 
Location. The project is located on the south coast of 
North Carolina about 12 miles west of Cape Fear River. 
(See Coast and Geodetic Survey Chart 1236 and Geological 
Survey Map of North Carolina.) 
Existing project. The authorized project provides for a 
channel 100 feet wide and 6 feet deep at low water from 
the ocean to the bridge at Supply 12.5 miles above, to be 
obtained by dredging through oyster rocks and mudflats. 
The completed river portion of the project above the 
waterway was reclassified to the active category in 1971. 
Lunar tidal ranges in Lockwoods Folly River are 4.5 feet 
at the inlet and 2 feet at the head of navigation at Supply. 
The existing project was authorized by the 1890 River and 
Harbor Act. (See Annual Report for 1887, page 1099.) A 
modification to enlarge the channel from 6 to 12 feet deep 
and from 100 to 150 feet wide across the ocean bar for 
distance of 4,700 feet was approved by the Chief of 
Engineers on June 3, 1980, under Section 107 of the 1960 
River and Harbor Act. During dredging operations it 
became apparent that establishment of the 12-foot project 
would not be possible with currently available equipment. 
Therefore, the Chief of Engineers, on December 20, 1983, 
approved the District's recommendation that further construction 
activity for the Lockwoods Folly Inlet project be 
suspended until suitable equipment becomes available and 
that the project be maintained at an 8-foot project depth in 
the interim. 
Local cooperation. For the new modification local 
interest must: (a) pay, contribute in kind, or repay with 
interest, one-half of the first costs of construction allocated 
6-5

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
to recreational boating; (b) hold and save the United 
States free from damages resulting from changes in 
groundwater Jevels, saltwater intrusion, or wave action 
due to the construction works, except damages due to the 
fault or negligence of the United States or its contractor; 
(c) provide without cost to the United States all lands, 
easements, and rights-of-way necessary for the 
construction and subsequent maintenance of the project 
and for aids to navigation upon the request of the Chief of 
Engineers and, (d) provide depths in berthing areas 
commensurate with the project depths, and provide 
service facilities. 
Terminal facilities. Thirty-one piers and wharves on the 
Atlantic Intracoastal Waterway at Holden Beach, about 
1.25 miles west of Lockwoods Folly Inlet, with a total 
frontage of about 1,980 feet available. At Dixons Landing, 
about 2 miles upstream of the inlet, there are five wharves 
with a total frontage of 240 feet. Numerous natural 
landings are used for loading and unloading small boats. 
Berthing space in the vicinity of Lockwoods Folly Inlet 
totals about 2,220 feet. Facilities are considered adequate 
for present commerce. 
Operations and results during fiscal year. Maintenance: 
During intermittent periods the U. S. hopper dredge 
Currituck removed 54,830 cubic yards from shoals in 
Lockwoods Folly Inlet at a cost of $101,193. During 
intermittent periods the U. S. sidecasting dredge Merritt 
removed 96,264 cubic yards from shoals in Lockwoods 
Folly Inlet at a cost of $465,971. The Snell incurred cost of 
$119. Archeological investigations of the blockade runner 
Bendigo and the river cost $238. Between November 8, 
1985 and July 17, 1986 the contract dredge XL removed 
34,898 cubic yards from shoals in Lockwoods Folly River at 
a cost of $165,977. Condition and operation studies cost 
$12,667. 
Condition at end of fiscal year. The active portion of the 
project was completed in June 1965 except for the latest 
modification. Work was initiated on the latest modification 
on September 23, 1982, with a depth of 8 feet being 
reached in October 1982. The project will be maintained at 
the 8-foot depth until suitable equipment for deepening to 
12 feet becomes available. 
9. MANTEO (SHALLOWBAG) BAY, N. C. 
Location. The project is located on the northeastern side 
of Roanoke Island, North Carolina. (See Coast and 
Geodetic Survey Chart 1229.) 
Existing project. The authorized project provides for a 
channel 14 feet deep and 400 feet wide from the Atlantic 
Ocean through Oregon Inlet with connecting 12-foot channels, 
100 feet wide, to Pamlico Sound, Manteo, and Wanchese; 
and a channel 6 feet deep and 100 feet wide connecting 
the Manteo-Oregon Inlet Channel with Albemarle 
Sound. Length of channels is 25.4 miles. A newly authorized 
modification provides for stabilization of Oregon Inlet 
with a dual rubble-mound jetty system, including means 
for sand transfer to the downdrift beach; a channel, 20 feet 
deep and 400 feet wide, through the ocean bar at Oregon 
Inlet; a channel, 14 feet deep and 120 feet wide, from the 
gorge in Oregon Inlet to and through Roanoke Sound to 
and including a 15-acre basin of the same depth at Wanchese; 
and a channel 10 feet deep and 100 feet wide from 
the 12 foot deep channel in Manteo (Shallowbag) Bay 
through Roanoke and Albemarle Sounds to deepwater 
near the northern end of Croatan Sound. The 12 foot 
Croatan Sound channel has been deferred due to lack of 
economic justification. The estimated Federal cost for the 
modification is $97,000,000 (1986). The project was 
authorized by River and Harbor Acts of June 25, 1910; October 
17, 1940; May 17, 1950; and December 31, 1970; and 
under Section 107 of the 1960 River and Harbor Act. 
Local cooperation. For the new modification, local interests 
must: (a) provide all lands, easements, and rightsof-
way for construction and subsequent maintenance of the 
project, including suitable areas required for initial and 
subsequent disposal of spoil and also necessary retaining 
dikes, bulkheads, and embankments therefor, or the cost 
of such retaining works; (b) hold and save the United 
States free from damages due to the construction works 
and subsequent maintenance; (c) continue to provide and 
maintain adequate terminal and transfer facilities, open to 
all on equal terms, in accordance with plans approved by 
the Chief of Engineers; (d) provide and maintain necessary 
mooring and berthing facilities in any enlarged basin, open 
to all on equal terms, in accordance with plans approved by 
the Chief of Engineers; (e) provide and maintain depths in 
berthing areas and local access channels serving the terminals 
commensurate with depths provided in the related 
project areas; (f) accomplish such alterations as required in 
sewer, water supply, drainage, electrical powerlines, 
telephone lines, or other utility facilities as well as their 
maintenance; (g) establish a competent and properly constituted 
public body empowered to regulate the use, 
growth, and free development of the harbor facilities, with 
the understanding that said facilities will be open to all on 
equal terms; (h) and establish regulations prohibiting the 
discharge of untreated sewage, garbage, and other 
pollutants in the water of the harbor by the users thereof, 
which regulations shall be in accordance with applicable 
laws or regulations of Federal, State, and local authorities 
responsible for pollution prevention and control. 
Reasonable assurances have been received. The State of 
N. C. has constructed the Wanchese Harbor portion and 
was reimbursed under Sec. 215, PL 90-483. 
Terminal facilities. The project is served by 33 waterfront 
facilities with a total frontage of 3,320 feet. Additional 
wharves and facilities will be provided with the 
enlarged basin at Wanchese. 
Operations and results during fiscal year. New work: 
Engineering and design for the modification cost $109,007. 
Maintenance During intermittent periods the U.S. 
sidecasting dredge Schweizer removed 248,320 cubic 
yards from shoals in Oregon Inlet at a cost of $1,324,134. 
During intermittent periods the U.S. sidecasting dredge 
Merritt removed 123,123 cubic yards from shoals in 
Oregon Inlet at a cost of $450,395. During intermittent 
periods the U.S. debris boat Snell repaired dredging 
6-6

WILMINGTON, N. C., DISTRICT 
ranges and moorings at a cost of $37,298. During intermittent 
periods the U. S. hopper dredge Currituck removed 
22,740 cubic yards from shoals in Oregon Inlet at a cost of 
$76,965. Between June 28 and August 3, 1986, the contract 
dredge Northerly Island removed 219,332 cubic yards 
from shoals in Oregon Inlet at a cost of $561,617. Between 
February 2 and March 16, 1986, the contract dredge Northerly 
Island removed 258,750 cubic yards from shoals in 
Oregon Inlet at a cost of $510,953. Between October 8 and 
November 19, 1985, the contract dredge Northerly Island 
removed 266,450 cubic yards from shoals in Oregon Inlet 
at a cost of $887,252. Between May 14 and June 1,1986, the 
contract dredge Clinton removed 130,408 cubic yards from 
shoals in Old House Channel at a cost of $290,813. Cost in 
connection with prior years dredging was $39,141. Expansion 
of disposal islands cost $6,317. Project monitoring cost 
$9,736. Litigation cost on the lawsuit brought by the 
owners of the fishing vessels Brothers Pride and Lois 
Joyce was $14,868. Condition and operation studies cost 
$106,473. 
Condition at end of fiscal year. The project is complete 
except for the latest modification. (For further details, see 
Annual Report of 1962.) 
10. MOREHEAD CITY HARBOR, N. C. 
Location. The project is located on the northern shore of 
Bogue Sound, adjacent to Beaufort Inlet. (See Coast and 
Geodetic Survey Chart 420.) 
Previous project. For details see page 470 of Annual 
Report for 1935. 
Existing project. The authorized project provides for 
deepening of the channel, from the 42-foot-depth contour in 
the Atlantic Ocean through the ocean bar to the gorge in 
Beaufort Inlet, to 42 feet over a bottom width of 450 feet, 
thence to a depth of 40 feet in the east leg of the turning 
basin including the 1,200-foot diameter turning area, with 
widths of 600 feet in the cutoff channel, and 400 feet wide 
to the turning basin and connecting shallow-draft channels. 
Project deepening was completed on August 2, 1978. Jetties 
at Beaufort Inlet were reclassified to the "active" 
category on March 8, 1972. The estimated Federal cost is 
$55,600,000 (1986) for the jetties. In general the project as 
it now exists was authorized by the 1958 River and Harbor 
Act (S.D. 54, 84th Cong., 1st sess.) and the River and Harbor 
Act of December 31, 1970. For further details see Annual 
Report for 1962. 
Local cooperation. Fully complied with except for construction 
of the jetties which requires that all lands needed 
for construction be provided without cost to the United 
States. 
Terminal facilities. Twenty-six waterfront facilities 
serve the port, with a total frontage of 1,250 feet. Marine 
terminals provide 5,300 feet of berthing space, with a 
depth alongside of 35 feet, and facilities for transfer of 
cargoes between rail and water carriers. Improvements to 
facilities were completed in 1969. For further details see 
Port Series No. 12, revised 1980, Corps of Engineers. 
Operations and results during fiscal year. Maintenance: 
Between May 16 and July 17, 1986, the contract dredge 
Mermentau removed 367,681 cubic yards from shoals in 
the ocean bar at a cost of $617,540. Between November 8 
and December 8, 1985, the contract dredge Clinton removed 
255,743 cubic yards from shoals in the ocean bar at a 
cost of $362,586. Between February 11 and May 3, 1986, 
the contract dredge Jim Bean removed 3,912,894 cubic 
yards from the Brandt Island disposal area and deposited 
it on the beach at a cost of $5,150,418. Cost incurred for 
prior dredging was $1,171. Design for fiscal year 1987 
dredging cost $1,535. Ocean dumping monitoring cost 
$6,765. Monitoring at Morehead City Harbor cost $12,504. 
Condition and operation studies cost $157,840. Contributed 
funds of $122,543 were expended for State Ports dredging. 
Condition at end of fiscal year. The existing project is 
complete except for the jetties. (For further details, see 
Annual Report for 1962.) Total cost of the existing project 
to September 30, 1986, was $47,394,517 of which $6,501,569 
was for new work (including $553,477 public works funds) 
and $40,892,948 for maintenance, including $874,254 contributed 
funds. 
11. OCRACOKE INLET, N. C. 
Location. The inlet connects Pamlico Sound with the 
Atlantic Ocean, about 30 miles southwest of Cape Hatteras 
and 43 miles northeast of Cape Lookout. (See U.S. Coast 
and Geodetic Survey Chart No. 1232.) 
Existing project. The authorized project provides for a 
channel across the ocean bar 18 feet deep and 400 feet 
wide, and construction of a jetty extending from Ocracoke 
Island to the Atlantic Ocean. Construction of the jetty has 
been deferred for restudy. The project was authorized by 
the River and Harbor Act of July 14, 1960. For further 
details, see Annual Report for 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. None required. 
Operations and results during fiscal year. Maintenance: 
Archeological investigations cost $2,144. Condition and 
operation studies cost $10,294. 
Condition at end of fiscal year. Construction was completed 
in August 1971. 
12. PAMLICO AND TAR RIVERS, N. C. 
Location. The two names apply to the same river, 
known as the Tar above and as the Pamlico below 
Washington, N. C. This stream rises in Person County, 
flows southeasterly 180 miles to Washington, thence 38 
miles to Pamlico Sound. (See Coast and Geodetic Survey 
Chart 537.) 
Previous project. For details see page 502 of Annual 
Report for 1938. 
Existing project. A channel 12 feet deep at mean low 
water and 200 feet wide from 12-foot contour in the river 
below Washington to Atlantic Coastline Railroad bridge at 
Washington; thence 12 feet deep and 100 feet wide to a tur- 
6-7

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
nfling basin of same depth, 200 feet wide, 300 feet long, in 
Hardee Creek, 1,500 feet above its mouth; thence 6 feet 
deep, 75 feet wide to Greenville; thence 20 inches deep, 60 
feet wide to Tarboro; and thence to clear the natural channel 
to Little Falls. Project was authorized by River and 
Harbor Acts of August 14, 1876; March 3, 1879; August 11, 
1888; March 2, 1907; July 25,1912; July 3,1930; and August 
26, 1937. For further details see Annual Report for 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 54 wharves on the portion 
of this river under improvement, of which 34 are along the 
waterfront at Washington, 19 between Washington and 
the mouth, and only 1 in usable condition above 
Washington. They have a frontage of 3,570 feet. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
An environmental assessment and a report to determine 
the economic justification of the project cost $432. 
Condition at end of fiscal year. Project is complete. (For 
details see Annual Report for 1962.) 
13. ROLLINSON CHANNEL, N. C. 
Location. The project is located about 3.5 miles northeast 
of Hatteras Inlet. (See Coast and Geodetic Survey 
Chart 1232.) 
Existing project. The authorized project provides for a 
channel 12 feet deep, 100 feet wide, and about 5.1 miles 
long from deep water in Pamlico Sound to and including a 
basin of the same depth, 80 to 150 feet wide, and 1,450 feet 
long at Hatteras; a rubble-mound breakwater on each side 
of the channel at the entrance to the basin; and a channel 
10 feet deep and 100 feet wide from that depth in Hatteras 
Inlet gorge to Rollinson Channel, in the vicinity of the 
basin at Hatteras. The project was authorized by the 
River and Harbor Acts of August 30, 1935; March 2, 1945; 
September 3, 1954; and October 23, 1962. (For further 
details see Annual Report for 1961.) 
Local cooperation. Complied with to date. 
Terminal facilities. Six waterfront facilities serve the 
channel, with a total frontage of 926 feet. Existing facilities 
are adequate for present commerce. 
Operations and results during fiscal year. Maintenance: 
Between March 7 and May 25, 1986, the contract dredge 
Richmond removed 105,966 cubic yards from shoals in 
Rollinson Channel at a cost of $387,700. Project condition 
surveys cost $1,374. Contributed funds of $41,142 were expended 
for diking in connection with pipeline dredging. 
Condition at end of fiscal year. The project was completed 
August 22, 1966. (For further details see Annual 
Report for 1961.) 
14. SILVER LAKE HARBOR, N. C. 
Location. The project is located at the southwest end of 
Ocracoke Island, a portion of the Outer Banks on the 
southeast coast of North Carolina, separating Pamlico 
Sound from the Atlantic Ocean. (See Coast and Geodetic 
Survey Chart No. 1232.) 
Existing project. The authorized project provides for 
basin depths of 12 feet in Silver Lake Harbor; an entrance 
channel 12 feet deep and 60 feet wide, from the basin to 
Teaches Hole Channel; a channel, 12 feet deep and 150 feet 
wide, from the entrance channel through Big Foot Slough 
Bar to the 12-foot contour in Pamlico Sound; a channel, 12 
feet deep and 150 feet wide, from the entrance channel 
through Teaches Hole Channel to the gorge in Ocracoke 
Inlet; a channel, 12 feet deep and 150 feet wide, across 
Bluff Shoal; and for rubble-mound training walls on the 
north and south sides of the entrance channel, 300 feet and 
400 feet long, respectively. Mean tidal ranges are 1.9 feet 
in the throat of Ocracoke Inlet and 1 foot at Ocracoke. 
Variations in the water surface of Pamlico Sound are 
generally due to winds and seldom exceed 1 or 2 feet above 
or below mean stage. Severe storms have raised the water 
surface as much as 7 feet above normal water level at 
Ocracoke. (See Table 6-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Twelve waterfront facilities serve 
the harbor. These facilities are adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Between December 5 and 8, 1985 the contract dredge Richmond 
removed 11,092 cubic yards from shoals in Teaches 
Hole Channel at a cost $91,055. Cost in connection with 
prior year pipeline dredging was $58,446. Design for fiscal 
year 1987 dredging was $17,835. The U. S. sidecasting 
dredge Fry incurred cost of $101. Condition and operation 
studies cost $9,708. 
Condition at end of fiscal year. The project was completed 
July 28, 1970. (For further details see Annual 
Report for 1961.) 
15. WATERWAY CONNECTING PAMLICO SOUND 
AND BEAUFORT HARBOR, N. C. 
Location. The project is located in Core Sound, west of 
the outer banks of eastern North Carolina. (See Coast and 
Geodetic Survey Charts Nos. 420 and 1233.) 
Existing project. The authorized project provides for a 
through channel to Core Sound 7 feet deep and 75 feet 
wide from Pamlico Sound to Beaufort Harbor; an alternative 
route of the same dimensions through Back Sound 
by way of channels at the east and west ends of Harkers 
Island; a channel 7 feet deep and 70 feet wide from the 
through channel to the local harbor at Cedar Island, including 
the authorized passage and future maintenance of 
a channel through the existing private basin, and an access 
channel 6 feet deep, 50 feet wide and about 400 feet long to 
a basin the same depth, 60 feet by 100 feet; a channel 7 feet 
deep and 75 feet wide from the through channel to Atlantic; 
a channel 7 feet deep and 75 feet wide, with a basin 200 
feet by 500 feet, the same depth, at Sealevel; a channel 5 
feet deep and 75 feet wide, with basin 150 feet by 130 feet, 
the same depth, at Davis; a channel 6 feet deep and 60 feet 
wide with a basin 100 feet by 600 feet, the same depth, at 
6-8

WILMINGTON, N. C., DISTRICT 
Marshallberg; an entrance channel 6 feet deep and 60 feet 
wide, from Back Sound to harbor of refuge 120 feet by 250 
feet, the same depth in Brooks Creek at the west end of 
Harkers Island; and a channel 7 feet deep and 70 feet wide, 
from the existing side channel at Atlantic, N.C., to the 
mouth of Little Port Brook; thence 7 feet deep and 50 feet 
wide, along the Brook to a basin 600 feet long, 180 feet 
wide, and 7 feet deep, with a breakwater, beginning at a 
point between the mouth of Little Port Brook and White 
Point, running along the channel approximately 2,000 feet. 
Plane of reference is mean low water. The length of the 
authorized channels is about 50.6 miles. (See Table 6-B for 
authorizing legislation.) 
Local cooperation. Fully complied with to date for completed 
portion. 
Terminal facilities. Sixteen small wharves serve the 
waterway. Additional facilities are needed along Core 
Sound. 
Operations and results during fiscal year. Maintenance: 
Between November 8 and 25, 1985, the contract dredge 
Richmond removed 50,247 cubic yards from shoals in 
Atlantic Harbor and Wainwright Slough at a cost of 
$230,600. Project condition surveys cost $2,132. 
Condition at end of fiscal year. The project was completed 
in September 1972. (For further details, see Annual 
Report for 1961.) 
16. WILMINGTON HARBOR, N. C. 
Location. The project is located on the Cape Fear River, 
on southeast coast of North Carolina, between the Atlantic 
Ocean and Wilmington, North Carolina. (See Coast and 
Geodetic Survey Chart No. 426.) 
Previous projects. For details, see page 1804 of Annual 
Report for 1915 and page 533 of Annual Report for 1938. 
Existing project. The authorized project provides for a 
channel 40 feet deep and 500 feet wide from the Atlantic 
Ocean through the ocean bar and entrance channels to 
Southport, thence 38 feet deep and 400 feet wide to the 
upper end of the anchorage basin (foot of Castle Street) at 
Wilmington, thence 32 feet deep and 400 feet wide, to 
Hilton Bridge over Northeast (Cape Fear) River; a 38-footdeep 
anchorage basin at Wilmington; a 32-foot-deep 
turning basin opposite the principal terminals; a channel 
12 feet deep and 100 feet wide, about 3 miles long, in Cape 
Fear River; and a channel 25 feet deep and 200 feet wide 
from Hilton Bridge over Northeast (Cape Fear) River to a 
point 1.66 miles above, including a turning basin of the 
same depth, 700 feet wide and 500 feet long, at a point 1.25 
miles above the bridge. The project was authorized by 
River and Harbor Acts of July 3, 1930; March 2, 1945; May 
17, 1950; October 23, 1962; and March 10, 1964; under 
Section 107 of the 1960 River and Harbor Act. A modification 
to widen the existing anchorage basin by 100 feet 
was authorized on July 13, 1982, under Sec. 5 of the Cong. 
Appro. Act of March 4, 1915. (For further details of 
authorization, see 1962 Annual Report.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. Forty-three principal wharves, piers, 
and docks at port of Wilmington, with a berthing space of 
about 20,000 linear feet serve the harbor. These facilities 
handle general cargo and petroleum products. For further 
details, see Port Series No. 12, revised 1980, Corps of 
Engineers. 
Operations and results during fiscal year. Maintenance: 
During intermittent periods the U.S. debris boat Snell 
repaired survey and dredging ranges at a cost of $18,181. 
Between December 4, 1985, and February 14, 1986, the 
contract dredge Mermentau removed 804,086 cubic yards 
from shoals in the ocean bar at a cost of $997,230. Between 
December 17 and 22, 1985, the contract dredge Clinton 
removed 18,749 cubic yards from shoals in the 32-foot 
channel at a cost of $93,535. Between October 3 and 
December 15, 1985, the contract dredge Hampton Roads 
removed 405,997 cubic yards from shoals in the river 
channel at a cost of $606,628. Between March 17 and May 
1, 1986, the contract dredge Clinton removed 692,160 cubic 
yards from shoals in the anchorage basin at a cost of 
$454,123. Design for fiscal year 1987 dredging cost $9,317. 
Environmental analysis of proposed dredge material 
disposal sites cost $161,520. Ocean dumping monitoring 
cost $4,716. Condition and operation studies cost $208,239. 
Contributed funds of $258,112 were expended for diking on 
pipeline dredging. Contributed funds of $140,539 were 
expended for dredging of the state ports. 
Condition at end of fiscal year. The active portion of the 
project was completed July 1973 except for latest 
modification which was completed on October 26, 
1982,with maintenance funds. (For further details, see 
Annual Report for 1962.) Total cost of the existing project 
to September 30, 1986, was $68,392,702 of which 
$14,089,612 was for new work and $54,303,090 was for 
maintenance, including $3,697,856 contributed funds. 
Flood Control 
17. ARARAT RIVER, MOUNT AIRY, N. C. 
Location. Ararat River is a tributary of the Yadkin 
River and is located in Surry County, N. C. The river flows 
through Mount Airy, N. C., to its confluence with the 
Yadkin River. The entire project borders Mt. Airy. (See 
USGS quadrangle sheets, Mount Airy, North, Va. and 
N. C. and Mount Airy, South, N. C.) 
Existing project. The project consists of approximately 
5,100 feet of industrial area dike construction, approximately 
6,700 feet of channel improvement, approximately 
1,800 feet of floodwall/dike at the Pine Street commercial 
area, and a flood warning system. The project was approved 
by the Chief of Engineers on August 10, 1983, under 
Section 205, 1948 Flood Control Act, as amended. The 
estimated Federal construction cost is $4,000,000 (1986). 
Local cooperation. Local interest must: (a) provide 
without cost to the United States all lands, easements, and 
rights-of-way, including suitable borrow and spoil disposal 
areas and suitable conservation lands to partially compen- 
6-9

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
sate for loss of fish and wildlife resources as determined by 
the Chief of Engineers, necessary for the construction of 
the project; (b) accomplish without cost to the United 
States all alterations and relocations of buildings, 
transportation facilities, storm drains, utilities, and other 
structures and improvements made necessary by the construction; 
(c) hold and save the United States free from 
damages due to the construction works, except damage 
due to the fault or negligence of the United States or its 
contractors; (d) maintain and operate the project after 
completion in accordance with regulations prescribed by 
the Secretary of the Army; (e) prescribe and enforce 
regulations to prevent obstruction or encroachment on 
channels and interior ponding areas which would reduce 
their flood-carrying capacity or hinder maintenance and 
operation, and control development in the project area to 
prevent an undue increase in the flood damage potential; 
and (f) assume full responsibility for all project costs in excess 
of the Federal cost limitation of $4 million. Formal 
assurances have been received. 
Operations and results during fiscal year. New work: 
Project construction cost $2,765,469. Contributed funds of 
$1,103 were expended for construction. 
Condition at end of fiscal year. A construction contract 
was awarded on May 29, 1985, with completion scheduled 
for February 1987. 
18. CAPE FEAR RIVER BASIN, N. C. 
Location. Work covered by this project consists of a 
series of dams and reservoirs on tributaries of the Cape 
Fear River in North Carolina within a radius of 100 miles 
from Raleigh, North Carolina. (See Geological Survey Map 
of North Carolina.) 
Existing project. Public Law 88-253, approved 
December 30, 1963, authorized three principal dams and 
reservoirs and a series of smaller reservoirs on tributaries 
of the Cape Fear River in accordance with the comprehensive 
plans in House Document 508, 87th Congress, 2d 
session. The act also provides that the appropriate 
agencies of the Departments of the Army and Agriculture 
shall conduct joint investigations and surveys and prepare 
a report on the upper tributaries of the Cape Fear River in 
the interest of watershed protection and flood prevention, 
and the conservation, development, utilization, and 
disposal of water. The report was prepared in compliance 
with provisions of Public Law 87-639. The study was 
unfavorable and has been submitted to Congress. No 
further action will be taken. A list of the dams and 
reservoirs included in the comprehensive plan follows. 
(See Table 6-J on Dams and Reservoirs). Estimates of cost 
as given are based on 1960 price levels, except the ones for 
B. Everett Jordan Dam and Lake, and Randleman Lake, 
which were revised in 1986, and Howards Mill Lake in 
1980. These three projects have been authorized for 
construction in accordance with the above authorization. 
Howards Mill Lake was reclassified to the "deferred" 
category in October 1980 due to the current lack of 
economic justification. 
Local cooperation. Requirements are given in the 
individual project reports. 
18A. B. EVERETT JORDAN DAM AND LAKE, N. C. 
Location. The project is located on the Haw River, N. C., 
4.3 miles above its mouth, and 2.5 miles north of Moncure, 
N.C. 
Existing project. The project provides for an earth dam 
1,330 feet long with a maximum height of 112 feet above 
the streambed, an uncontrolled, unpaved chute spillway, 
and a controlled 19-foot diameter outlet structure. Some 
saddle dikes are required beyond the spillway. The 
reservoir has a gross storage capacity of 753,500 acre-feet, 
of which 538,400 acre-feet is for flood control and a 
conservation pool of 215,100 acre-feet for water-quality 
control, water supply, and sedimentation. The reservoir 
will be operated as a unit of a coordinated system for 
control of floods in the Cape Fear River Basin and for 
water supply, water-quality control, and other purposes. 
Estimated cost for new work is $136,000,000 (1986), 
consisting of $77,790,500 for construction, and $58,209,500 
for lands and damages, including highway, railroad, and 
utility relocations. The existing project was authorized by 
Public Law 88-253 approved December 30, 1963 (H.D. 508, 
87th Cong., 2d sess.) 
Local cooperation. Local interests must protect 
downstream channels from encroachments and obstructions 
which would adversely affect operation of the 
project; reimburse the Federal Government for all costs 
allocated to municipal and industrial water supply, 
presently estimated at $3,900,000 and bear all annual costs 
for operation, maintenance, and major replacements 
allocated to municipal and industrial water supply, an 
amount presently estimated at $38,000 annually; and 
contribute toward the cost of the ranger security 
buildings, an amount presently estimated at $180,000. 
Assurances that these obligations for water storage would 
be assumed have been received from the Department of 
Natural and Economic Resources, State of North Carolina. 
In addition, the State of N. C. has leased the project for 
public park, recreational, fish, wildlife, and other natural 
resource management purposes and the estimated cost to 
the State for O&M under this lease is $772,000 annually. 
Operations and results during fiscal year. New work: 
Construction of wildlife subimpoundments was continued 
at a cost of $3,320,816. Parkers Creek recreation area was 
completed at a cost of $354,220. Poplar Point recreation 
area was initiated at a cost of $3,450,521. The management 
center was initiated at a cost of $178,534. The Tailrace 
access area was initiated at a cost of $55,623. Total Federal 
expenditures were $8,595,667, including the above items. 
Status of plans and specs: Seaforth recreation area and 
Parkers Creek security building, 100 percent; Crosswinds 
campground, 90 percent; Ebenezer Church recreation 
area, 100 percent; N. C. Park maintenance headquarters, 
100 percent; rehabilitate Mason House, 100 percent; and 
Crosswinds and Poplar Point security buildings, 80 
percent. Maintenance: Water quality studies were 
6-10

WILMINGTON, N. C., DISTRICT 
conducted at a cost of $143,468. Periodic inspections cost 
$17,539. Repairs to access road cost $307. Automatic gate 
control system cost $5,409. Normal operation and 
maintenance cost $712,981. 
Condition at end of fiscal year. Relocations complete 
except for Public Service Gas Co. Recreation facilities and 
wildlife subimpoundments are underway. Impoundment 
was completed in February 1982 with dedication on May 1, 
1982. Project completion is scheduled for March 1989. 
18B. RANDLEMAN LAKE, N. C. 
Location. The project is located on Deep River, N. C., 
about 15 miles south of Greensboro and about 2 miles 
upstream from the town of Randleman. The damsite and 
about two-thirds of the reservoir would lie in Randolph 
County. The upper one-third of the reservoir would lie in 
Guilford County. 
Existing project. The authorized project provides for 
construction of an earth dam 2,300 feet long with a maximum 
height of 110 feet above the streambed to create a 
reservoir with gross storage of 108,000 acre-feet, consisting 
of 46,000 acre-feet for flood control and a conservation 
pool of 62,000 acre-feet for water supply, water-quality 
control and sedimentation. Randleman Lake is the second 
project of the comprehensive plan of development for the 
Cape Fear River Basin, providing reservoir storage for 
flood control, water supply, and recreation. Estimated 
cost of new work is $115,000,000 (1986), consisting of 
$53,659,600 for construction and $61,340,400 for lands and 
damages, including relocations. The existing project was 
authorized by the 1968 Flood Control Act (H.D. 343, 90th 
Cong., 2d sess.). 
Local cooperation. Local interests must: (1) In accordance 
with the Federal Water Project Recreation Act (P.L. 
89-72): (a) Administer project land and water areas for 
recreation and fish and wildlife and to assure access to 
such development to all on equal terms; (b) pay, contribute 
in kind, or repay (which may be through user fees) with interest, 
one-half of the cost allocated to recreation presently 
estimated at $25,752,000; and (c) bear all the costs of operation, 
maintenance, and replacement of recreation facilities, 
presently estimated at $407,000 annually; (2) In accordance 
with the Water Supply Act of 1958, as amended, assure 
payment to the United States of all costs allocated to 
water supply, presently estimated at $61,171,000 for construction 
and $445,000 annually for operation, 
maintenance, and major replacement; (3) Hold and save the 
United States free from damages due to water-rights 
claims resulting from construction and operation of the 
project; (4) Prevent encroachment on downstream channels 
to the extent needed to provide effective reservoir 
operation; (5) Exercise to the full extent of their legal 
capability control against removal of stream-flow made 
available for preservation of downstream fishery habitat; 
and (6) Pay 35 percent of the cost allocated to flood control 
presently estimated at $5,077,000 for construction and 
$32,000 annually for operation, maintenance and major 
replacement. These assurances are subject to the provision 
that Federal participation in measures required to 
safeguard the quality of water in Randleman Reservoir 
shall not be provided as a substitute for the responsiblity 
of local interests to provide adequate treatment in accordance 
with water quality standards established pursuant to 
the Water Quality Amendments of 1972 (P.L. 92-500). 
Reasonable assurances that the requirements will be 
fulfilled have been received. 
Operations and results during fiscal year. New work: 
Advance engineering and design cost $27,356. 
Condition at end of fiscal year. Preconstruction planning 
was completed in FY 1982. A new construction start was 
granted for FY 1987. 
19. CAROLINA BEACH AND VICINITY, N. C. 
Location. The project is in New Hanover County, about 
15 miles southeast of Wilmington, N. C., on the peninsula 
which separates lower Cape Fear River from the Atlantic 
Ocean. (See Coast and Geodetic Survey Map 834.) 
Existing project. The authorized project provides for 
construction of a dune with a base generally bordering at 
or near the building line, with a crown width of 25 feet at 
an elevation of 15 feet above mean low water, together 
with integral construction of a beach berm with a crown 
width of 50 feet at elevation 12, extending about 31,800 
feet from the northern limits of Carolina Beach to the 
southern limits of Kure Beach; initial deposition of sufficient 
material north of Carolina Beach to serve as a feeder 
beach; and Federal participation in the cost of beach 
nourishment for a period not to exceed 10 years from the 
year of completion of initial placement. Along the northern 
2,050 feet, the project includes a rock revetment at elevation 
12 fronted by a 130-foot-wide berm at elevation 8. The 
area south of Carolina Beach was reclassified to the active 
category, June 1985. Approved estimated Federal cost for 
new work is $15,062,000 (1986). The project was authorized 
by the 1962 Flood Control Act (H.D. 418, 87th Cong. 2d 
sess.). 
Local cooperation. Local interests must: (a) Provide 
lands, easements, and rights-of-way for construction; 
(b) make required relocations and alterations of streets, 
utilities, or structures; (c) contribute 37.9 percent of the 
total first cost, with credit allowed for (a) and (b); 
(d) hold the United States free from damages; (e) maintain 
all works after completion; (f) maintain continued public 
ownership of the shore; (g) adopt and enforce appropriate 
ordinances to provide for preservation of improvement 
and its protective vegetation; (h) control water pollution to 
extent necessary to safeguard health of bathers; and 
(i) at least annually inform interests affected that project 
will not provide any substantial protection from ocean 
surges higher in elevation than that of Hurricane Hazel, 
October 15, 1954. Requirements have been fulfilled to date 
for the town of Carolina Beach portion of the project only. 
Operations and results during fiscal year. New work: 
Cost in connection with prior year nourishment was $50. A 
cost adjustment caused a decrease in Federal expenses of 
-$40,789 and an increase in non-Federal expenses of 
6-11

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
$40,789. 
Condition at end of fiscal year. Project construction was 
completed August 12, 1982, except for grassing which was 
completed in September 1983. A contract for the first increment 
of renourishment was awarded on March 8, 1985 
and was completed on June 10, 1985. 
20. LEESVILLE, VA., ROANOKE RIVER, SEC. 32, 
DEMO. PROJECT 
Location. The project is located on the Roanoke (Staunton) 
River in southwest Virginia near the Town of 
Leesville in Campbell and Pittsylvania counties. (See 
USGS quadrangle sheet, Leesville, Va.) 
Existing project. The project provides for a total of 
about 2,200 linear feet of streambank protection on two 
separate sites along a 3-mile segment of the river between 
Leesville Dam and the town of Leesville. Three methods of 
erosion control were used, they were: stone rubble with 
vegetation, rubber tire mattress and rock windrow. The 
project was funded for construction by the Chief of 
Engineers in February 1978, under Section 32, P.L. 93-251. 
Local cooperation. Fully complied with to date. 
Operations and results during fiscal year. New work: 
Monitoring of Leesville and Little Rockfish Creek cost $23. 
Condition at end of fiscal year. Construction was completed 
in March 1981. The project is functioning as 
designed. 
21. NEUSE RIVER BASIN, N. C. 
Location. Works covered by this project consist of a 
series of dams and reservoirs in the Neuse River Basin in 
North Carolina within a radius of 50 miles from Raleigh, 
North Carolina. (See Geological Survey Map of North 
Carolina.) 
Existing project. The Flood Control Act of 1965 
authorized construction of the Falls project as the key project 
in the recommended general plan of development of 
the Neuse River Basin. The plan will serve as a guide for 
immediate and future development of the basin's water 
resources as set forth in House Document 175, 89th Congress, 
1st Session. A list of projects included in the general 
plan of development follows. (See Table 6-J on Dams and 
Reservoirs.) Estimated costs as given are based on 1963 
price levels, except for Falls Lake which was revised in 
1986. 
21A. FALLS LAKE, N. C. 
Location. The project is on the Neuse River about 10 
miles north of the city of Raleigh, North Carolina. 
Existing project. The authorized project provides for an 
earth dam 1,915 feet long with a maximum height of 92 
feet above streambed. The dam has a 30-foot top width. An 
uncontrolled chute spillway, 100-feet wide, is located in the 
east abutment. The reservoir has a gross storage capacity 
of 335,620 acre-feet, of which 220,880 acre-feet is for flood 
control, 34,970 acre-feet for water supply for the city of 
Raleigh, 54,700 acre-feet for water-quality control, and 
25,070 acre-feet for sediment storage. The reservoir will be 
operated as the initial unit of a coordinated system for control 
of floods in the Neuse River Basin for water supply, 
water quality control, recreation, and other purposes. 
Estimated cost of new work is $163,000,000, (1986) consisting 
of $72,767,800 for construction and $90,232,200 for 
lands and damages, including highway, railroad, and utility 
relocations. The project was authorized by the 1965 Flood 
Control Act (H.D. 175, 89th Cong., 1st sess.) 
Local cooperation. Local interests must prevent encroachment 
on downstream channels that would interfere 
with the operation of the reservoir; pay the United States 
in accordance with the Water Supply Act of 1958, as 
amended, the entire amount of construction cost allocated 
to water supply, presently estimated at $12,400,000 and 
entire amount of operation, maintenance, and replacement 
costs allocated to water supply, presently estimated at 
$89,000 annually, the final amounts to be determined after 
actual costs are known; administer project land and water 
areas for recreation and fish and wildlife enhancement; 
pay, contribute in kind, or repay (which may be through 
user fees), with interest, one-half of the separable cost of 
the project allocated to recreation and one-fourth of the 
separable cost allocated to fish and wildlife enhancement, 
the amount involved currently being estimated at 
$18,600,000, and, bear all costs of operation, maintenance, 
and replacement of recreation and fish and wildlife lands 
and facilities, the amount involved currently being 
estimated at $1,224,000 on an average annual basis. Formal 
assurances have been received. The N. C. Department 
of Natural and Economic Resources has been authorized 
by an act of legislation to assure payment of all non- 
Federal costs allocable to water supply in all Federal projects 
as required by law. The State will require repayment 
of water supply costs, by the users. A contract between 
the city of Raleigh and the United States for water-supply 
storage space was approved by the Secretary of the Army 
on September 11, 1972. A contract agreement for cost 
sharing of recreational lands and facilities in accordance 
with P.L. 89-72 was approved by the Secretary of the Army 
on September 11, 1972. A contract agreement in accordance 
with Section 221 of P.L. 91-611 was executed on October 
10, 1972. 
Operations and results during fiscal year. New work: 
The Corps management center was completed at a cost of 
$155,258. Sandling Beach recreation area was completed at 
a cost of $699,129. Rolling View campground and recreation 
facilities were initiated at a cost of $665,526. Wildlife 
recreation areas were completed at a cost of $784,746. 
Total Federal expenditures were $3,876,795, including the 
above items. Status of plans and specs: Fish and wildlife 
subimpoundments, 15 percent; and Mangum House rehabilitation, 
100 percent. Maintenance: Water quality studies 
were conducted at a cost of $91,493. Repairs to the dam 
cost $6,016. Borrow area repairs cost $522,702. Emergency 
lighting cost $837. Periodic inspections cost $21,146. Normal 
operation and maintenance cost $819,332, for a total of 
$1,461,526. 
6-12

WILMINGTON, N. C., DISTRICT 
Condition at end of fiscal year. Reservoir filling was 
completed on December 7, 1983. Dedication ceremonies 
were held on April 30, 1983. Dam, access road, clearing, 
main operations area, all relocations and 33 percent of the 
recreation facilities are completed. Recreation facilities, 
fish and wildlife facilities and State management and O&M 
facilities are the major items remaining. 
22. SCUPPERNONG RIVER, N.C. 
Location. The stream rises in the east-central portion of 
Washington County, N. C., flows east into Tyrrell County, 
and thence north into Albemarle Sound, a total distance of 
about 22 miles. (See Geological Survey quadrangle sheet, 
Creswell, N. C.) 
Existing project. The project provides for excavating a 
70-foot-bottom-width channel, with depths ranging from 9 
feet to 12 feet, along Scuppernong River from Spruills 
Bridge to the confluence with Mauls Creek, a distance of 
2.0 miles, and excavating a 45-foot-bottom-width channel, 
with depths ranging from 6 feet to 8 feet, along Mauls 
Creek from Scuppernong River to County Road 1163, a 
distance of 1.8 miles. Total project length is 3.8 miles. 
Estimated Federal cost of construction is $509,000 (1984). 
Project was approved by the Chief of Engineers, October 
31, 1966 (with modification adding Mauls Creek approved 
June 16, 1967), under Section 205, 1948 Flood Control Act, 
as amended. 
Local cooperation. Local interests must provide lands, 
easements, rights-of-way, utility relocations and alterations, 
and highway or highway-bridge construction and 
alterations necessary for construction; hold the United 
States free from damages; maintain and operate project 
after completion; contribute, in cash, 31.4 percent of construction 
costs, currently estimated at $141,000; and prevent 
future encroachment. Formal request has not been 
made. 
Operations and results during fiscal year. New work: 
Project reanalysis cost $14,830. 
Condition at end of fiscal year. Project reanalysis and 
environmental studies have been completed. The project is 
being terminated due to the State of N. C. not issuing a 
water quality certification. 
23. STUART, VA. 
Location. The project is located on the South Mayo 
River at Stuart, Va., above and below Route 8 highway. 
(See USGS quadrangle sheet, Stuart, Va.) 
Existing project. The recommended plan consists of a 
100-foot-bottom-width high flow diversion channel combined 
with downstream river widening. A wier will be placed 
across the entrance to the diversion channel and a bench 
channel design will be used for the downstream river 
widening. The South Mayo River above Route 8 highway 
will be widened to a 50-foot bottom width, using a 
trapezoidal channel design and the commercial site northwest 
of Route 8 will be filled to the elevation of approximately 
the 200-year frequency flood. All river widening, 
except for a short distance above Route 8, will be done on 
the north bank. Estimated Federal cost of construction is 
$2,320,000. The project was approved by the Chief of 
Engineers on February 1, 1985, under Section 205, 1948 
Flood Control Act, as amended. 
Local cooperation. Local interests must provide all 
lands, easements, rights-of-way, including suitable borrow 
and spoil disposal areas, and all alterations and relocations 
of buildings, transportation facilities, storm drains, 
utilities, and other structures and improvements 
necessary for construction; hold and save the United 
States free from damages; maintain and operate the project 
after completion; assume full responsibility for all project 
costs in excess of the Federal cost limitation of $4 
million; presribe and enforce regulations to prevent 
obstruction or encroachments; continue to enforce flood 
plan regulations that comply with FEMA guidelines; and 
at least annually, inform affected interests regarding the 
limitations of the protection afforded by the project. Formal 
assurances have been received. 
Operations and results during fiscal year. New work: 
Construction was initiated at a cost of $202,768. 
Condition at end of fiscal year. A construction contract 
was awarded May 16, 1986, and is scheduled for completion 
in December 1987. 
24. YADKIN RIVER BASIN, N. C. AND S. C. 
Location. The river rises on the eastern slope of the 
Blue Ridge Mountains in western North Carolina, flows 
generally easterly about 100 miles to the vicinity of Donnaha, 
North Carolina, thence southeasterly 104 miles to its 
confluence with Uwharrie River near Badin, North 
Carolina, where its name changes to Great Pee Dee River. 
(See U.S. Geological Survey map of North Carolina.) 
Existing project. The Flood Control Act of July 24, 1946, 
authorized construction of four flood control dams in the 
Upper Yadkin River Basin, two on the Yadkin River above 
Wilkesboro, North Carolina, and two on Reddies River, a 
tributary stream. Studies made subsequent to authorization 
established the economic advantage of providing 
needed flood-control storage in only two reservoirs, one on 
the Reddies and one on the Yadkin. Present planning considers 
only the two-reservoir plan, W. Kerr Scott Dam and 
Reservoir constructed 1962 and Reddies River Lake. W. 
Kerr Scott was transferred to the Wilmington District 
from Charleston in fiscal year 1980. Any future work on 
Reddies River will also be done by the Wilmington 
District. (See Table 6-J on Dams and Reservoirs.) 
24A. W. KERR SCOTT DAM AND RESERVOIR, N. C. 
Location. W. Kerr Scott Dam and Reservoir is on 
Yadkin River, North Carolina, about 6 miles upstream 
from Wilkesboro. At full flood-control pool elevation (1,075 
feet mean sea level), the reservoir extends 15.7 miles 
upstream to the Wilkes-Caldwell County line. 
Existing project. The project consists of a rolled earthfill 
dam 1,740 feet long, with top of dam at elevation 1,107.5 
6-13

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
feet mean sea level or about 148 feet above streambed 
elevation; a spillway near the north abutment of the dam 
in a rock cut with crest elevation 1,075; and outlet works 
consisting of An intake structure, control tower, and a circular 
concrete conduit 12.25 feet in diameter through the 
base of the dam near the south abutment. The reservoir 
has a gross capacity of 153,000 acre-feet of which 112,000 
acre-feet are reserved for flood control, 33,000 acre-feet 
will be used as required for water supply, and 8,000 acrefeet 
being contained in the minimum pool. Estimated cost 
is $9,110,000 (1983) for new work. The existing project was 
authorized by the 1946 Flood Control Act. 
Local cooperation. Requirements fully satisfied. For 
details, see page 413 of Annual Report for 1963. 
Operations and results during fiscal year. Maintenance: 
Siesmic studies of the dam cost $10,006.Rip-rap protection 
cost $7,950. Rehabilitation of campsites was accomplished 
at a cost of $11,194. Normal operation and maintenance 
cost $1,130,205 for a total of $1,159,355. 
Condition at end of fiscal year. The project was commenced 
in August 1960 and placed in operation for flood 
control and water storage purposes in August 1962. 
25. INSPECTION OF COMPLETED FLOOD CONTROL 
PROJECTS 
To determine the extent of compliance with approved 
regulations for maintenance and operation, inspections 
were made for the following projects during fiscal year 
1985: Ellis Swamp, Gates County, N. C.; Gapway Swamp, 
Columbus County, N. C.; Old Field Swamp, Robeson County, 
N. C.; Gardners Creek, Martin County, N. C.; New 
River, Onslow County, N. C.; Pungo Creek, Beaufort County, 
N. C.; South Creek, Beaufort County, N. C.; Pungo 
River, Beaufort County, N. C.; and Filberts Creek, Edenton, 
N. C.; Pantego and Cucklers Creek, Beaufort County, 
N. C.; White Oak Dike, Bladen and Pender Counties, N. C.; 
Ellerbe Creek, Durham County, N. C.; Pasquotank Dike, 
Pasquotank County, N. C.; Perquimans River, Perquimans 
County, N. C.; Core Creek, Craven County, N. C.; 
Princeville Dike, Edgecombe County, N. C.; Swift Creek, 
Pitt County, N. C.; Carolina Beach, New Hanover County, 
N. C.; Wrightsville Beach, New Hanover County, N. C.; 
Goldsboro, Neuse River, Wayne County, N. C.; Broad 
Creek, Beaufort County, N. C.; Little Rockfish Creek, 
Hope Mills, N. C.; Black River, Harnett County, N. C.; Lick 
Run, Roanoke, Va.; and Leith Creek, Scotland County, 
N. C. Responsible local officials were advised of inadequacies 
in maintenance and operation on local flood protection 
works where appropriate. Cost for the period was 
$34,000. Total cost to September 30, 1986, was $339,559, 
charged to operations. 
26. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (preauthorization/. 
(See Table 6-K.) 
Emergency flood control activities and hurricane flood 
and shore-protection activities at Federally authorized 
projects (Public Law 99, 84th Congress, and antecedent 
legislation). 
National Emergency Preparedness Program cost 
$262,418. Disaster Preparedness Program cost $125,097. 
Field surveys for the November 1985 flooding on the 
Roanoke River cost $4,608. 
Multiple-Purpose Projects, Including Power 
27. ROANOKE RIVER BASIN, VA. AND N. C. 
Location. The project is on the Roanoke River and its 
tributaries in Virginia and North Carolina within a radius 
of 100 miles from Danville, Virginia. 
Existing project. The Flood Control Act of 1944 approved 
a general plan for the comprehensive development of 
the Roanoke River Basin for flood control and other purposes, 
and authorized construction of John H. Kerr and 
Philpott Reservoirs. (See Table 6-J for a list of dams and 
reservoirs included in the comprehensive plan.) 
Local cooperation. None required. John H. Kerr and 
Philpott Reservoirs are the only projects in the comprehensive 
plan that have been authorized for construction. 
(See Table 6-J on Dams and Reservoirs.) 
27A. JOHN H. KERR DAM AND RESERVOIR, VA. 
AND N. C. 
Location. The project is on Roanoke River, about 178.7 
river miles above its mouth, in Mecklenburg County, 
Virginia, and 20.3 miles downstream from Clarksville, 
Virginia. The reservoir extends upstream on Roanoke 
River 56 miles and on Dan River 34 miles. 
Existing project. The authorized project provides for a 
concrete gravity dam with wing and saddle dikes on the 
right and left banks, with a total length of about 22,285 
feet. The reservoir is operated as a unit of a coordinated 
system of reservoirs in the Roanoke River Basin for 
control of floods, generation of hydroelectric power, 
regulation of low-water flow, and for other purposes. The 
power installation is 204,000 kilowatts. (For further details 
see Annual Report for 1962.) Estimated cost is $67,529,000 
(1983) for construction and $24,521,000 for lands and 
damages, including relocation of highways, railroads, and 
utilities, a total of $92,050,000 for new work. The existing 
project was authorized by the 1944 Flood Control Act. 
Local cooperation. None required. 
Operations and results during fiscal year. New work: 
Construction of a washhouse at Longwood and a dump 
station and washhouse at Northbend Park was completed 
at a cost of $188,245 in addition to cost incurred under 
maintenance. Cost-sharing with the State of N. C. at 
various sites cost $11,122. Maintenance: Modification of 
the highway intersection at the powerhouse cost $1,883. 
Preservation of archeological sites at Satterwhite Point 
cost $32,486. Stability analysis of the dam cost $54,548. 
6-14

WILMINGTON, N. C., DISTRICT 
Construction of the management center was initiated at a 
cost of $412,285. Investigation of shoreline erosion cost 
$604. Repairs on the right wing dike cost $1,609,659. 
Rehabilitation of campsites at North Bend Park cost 
$8,341. Design for highway bridge repairs cost $59,113. 
Study on impact of water withdrawals cost $3,596. Work 
on the South Boston litigation cost $7,845. Work on the fire 
protection system for the powerhouse cost $17,218. Dam 
break model analysis cost $48,441. Work on the fire 
extinguishing and suppression system cost $16,399. Paving 
of recreation access roads cost $356,831. Engineering and 
design for replacement of the powerhouse computer cost 
$12,519. Real estate work in the South Boston area cost 
$34,218. Periodic inspection of the dam bridge cost $5,826. 
Final guide taking line study cost $35,489. Flood damage 
and benefit updating system cost $15,164. Construction of 
a washhouse at Longwood and a dump station and washhouse 
at Northbend Park cost $212,994 in addition to cost 
incurred under construction. Investigation and stability 
analysis of earth dikes cost $40,293. Investigation and 
stability analysis of Island Creek dam cost $31,143. Design 
of courtesy docks cost $8,010. Replacement of guard rail at 
Island Creek dam cost $841. Normal operation and 
maintenance cost $3,550,979, for a total of $6,576,725. 
Condition at end of fiscal year. Project is complete 
except for additional recreational facilities. Production of 
power and protection from floods are provided by project. 
27B. PHILPOTT LAKE, VA. 
Location. On Smith River, Virginia, 44.3 miles above its 
junction with Dan River, and 35 miles upstream ,from 
Virginia-North Carolina State line in Franklin and Henry 
Counties. 
Existing project. The authorized project provides for a 
concrete gravity dam 892 feet long and with a maximum 
height of 220 feet. Reservoir is operated as a unit of a coordinated 
reservoir system for flood control in the Roanoke 
River Basin, generation of hydroelectric power, regulation 
of low-water flow, and for other purposes. The powerhouse 
has a total installation of 14,000 kilowatts. (For further 
details see Annual Report for 1962.) Federal cost estimate 
is $13,933,000 (1983) for construction and $1,157,000 for 
lands and damages, a total of $15,090,000. Existing project 
was authorized by 1944 Flood Control Act. 
Local cooperation. None required. 
Operations and results during fiscal year. New work: 
Water system modifications in the Tailrace area cost 
$22,770. Maintenance: Design of a powerhouse fire protection 
system cost $7,360. Construction of management and 
visitors center cost $528,048. Sluice bulkhead cost $34,928. 
Normal operation and maintenance cost $1,512,335, for a 
total of $2,082,671. 
Condition at end of fiscal year. The project is complete 
except for additional recreational facilities, and is providing 
power and flood protection. 
28. SCHEDULING FLOOD CONTROL RESERVOIR 
OPERATIONS 
B. Everett Jordan Dam and Lake, located in the Cape 
Fear River Basin, North Carolina, began fiscal year 1986 at 
elevation 214.85 feet, MSL or 1.15 feet below normal pool. 
Declining streamflows and below normal rainfall gradually 
lowered the lake level to 213.35 feet MSL, at the end of October. 
In November, very heavy rain brought the lake 
elevation to 224.60 feet MSL, on the 24th which was the 
maximum elevation for the fiscal year. The 9.40 inches of 
rainfall observed in November set a new record high for 
the month. The lake level fluctuated close to normal pool 
from December to April. Only twice did this pattern alter 
when heavy rains brought the lake level to elevation 
218.90 and 219.15 feet MSL, on December 2 and March 16, 
respectively. In early May, the effects of below normal 
rainfall for several months began to show as Jordan Lake 
level started a downward trend. From December to July, 
observed rainfall was 53% below normal. These conditions 
proved to be the worst drought situation the Cape Fear 
River Basin has experienced over the period of record. On 
August 11, Jordan Lake reached the minimum elevation 
for the fiscal year at 209.10 feet MSL, or 6.90 feet below 
normal pool. At this point, only 42% of the conservation 
pool was remaining. Heavy rain in late August temporarily 
reduced the severity of the drought and pushed the lake 
level to elevation 213.75 feet MSL on September 2. Jordan 
Lake once again began a downward trend to end the fiscal 
year at elevation 211.60 feet MSL or 4.4 feet below normal 
pool. Flood damages prevented during fiscal year 1986 
were $297,000 which makes the cumulative total since impoundment 
of the project equal to $3,702,000. Total cost of 
functional operation for the period was $127,741. 
Falls Lake, located in the Neuse River Basin, North 
Carolina, began fiscal year 1986 at elevation 248.87 feet 
MSL or 1.2 feet below normal pool. Below normal rainfall 
produced a gradual drawdown of the lake to elevation 
247.50 feet MSL on November 3. A new high period of 
record average rainfall amount of 9.97 inches above Falls 
Dam for the month of November produced the maximum 
elevation for the year of 256.35 feet MSL on November 23. 
Falls Lake then remained near elevation 250 feet MSL 
through mid-March. Heavy rainfalls produced a minor rise 
to elevation 252.47 feet MSL on March 16. Falls Lake fell 
below rule curve in early April and did not recover to this 
level through the remainder of fiscal year 1986. A lack of 
rainfall and increased evaporation coupled with water supply 
and water quality demands from Falls Lake caused a 
gradual drawdown to elevation 245.40 feet MSL on August 
11 which was the minimum elevation for the fiscal year. At 
this time only 38% of the water quality storage and 76% 
of the water supply storage remained in the lake. Heavy 
rainfall during late August caused the lake to recover to 
elevation 249.44 feet MSL on August 31. Again, the lake 
level began a gradual drawdown to end the fiscal year at 
elevation 248.26 feet MSL. The summer of 1986 will go 
down as one of the driest on record for the piedmont area 
of North Carolina. A new record low rainfall amount of 
0.84 inches for the month of June was recorded for the 
area above Falls Dam and overall observed rainfall and inflow 
for the period December through June was 52% and 
6-15

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
61% below normal, respectively. The temporary operation 
plan for Falls Lake which was in effect at the beginning of 
fiscal year 1986 has been agreed to by officials from the 
Wilmington District, State of North Carolina and City of 
Raleigh. This revised operation plan provides for Falls 
Lake to be operated at a normal pool elevation of 251.0 feet 
MSL during the months of May through September and at 
a normal pool level of 250.1 feet MSL during the months of 
November through March. Also, this plan specifies a 
minimum target flow in the Neuse River at the Smithfield 
river gage of 184 c.f.s. during the months of November 
through March and 254 c.f.s. during the months of April 
through October for water quality purposes. The minimum 
instantaneous discharge from Falls Dam under this revised 
plan will be about 60 c.f.s. during the months of 
November through March and 100 c.f.s. during April 
through October. These discharges may be altered at the 
discretion of the District Engineer in emergency situations. 
Flood damages prevented during fiscal year 1986 
were $2,367,000 which makes the cumulative total since inception 
of the project equal to $8,719,000. Total cost of 
functional operation for the period was $110,535. 
John H. Kerr Dam and Reservior, located in the 
Roanoke River Basin, Virginia and North Carolina, began 
fiscal year 1986 at elevation 298.09 feet MSL or 1.41 feet 
below rule curve. Excessive rainfall in early November 
caused a rapid rise in the reservoir level to elevation 
308.90 feet MSL or 12.2 feet above rule curve which was 
the maximum elevation of the fiscal year. Two additional 
reservoir level rises of 306.65 and 305.36 feet MSL occurred 
on November 25 and December 3, respectively. Minor 
rises in February and March allowed the reservoir level to 
remain near rule curve. The effects of well below normal 
rainfall for several months began to show in April producing 
declining inflows and a falling reservoir level. Observed 
rainfall and inflow for the period December through 
June were 54% and 50% below normal, respectively. The 
Kerr reservoir level began to fall in April and continued 
through early August. The minimum elevation of the fiscal 
year was 295.06 feet MSL or 4.4 feet below rule curve on 
August 6. Rainfall in August and September coupled with 
reducing power generation to a minimum helped to raise 
the reservoir level to near elevation 298 feet MSL on 
September 8 and then end the fiscal year at elevation 
295.38 feet MSL or 4.1 feet below rule curve. Due to the 
drought, the 13 foot minimum stage required in the Lower 
Roanoke River at Weldon for striped bass fish spawning 
was only met April 28 to May 26. All inflows to Kerr 
Reservoir were controlled without having to spill water 
over the spillway or through the sluices. Gross generation 
for the fiscal year amounted to 329,994,600 kilowatts and 
power revenue was $4,456,320 making a cumulative total 
since inception of $120,214,028. Flood damages prevented 
during the fiscal year were $4,100,000 which makes the 
cumulative total since the project began equal to 
$76,207,000. The total cost of functional operation for the 
fiscal year was $179,368. 
Philpott Lake, located on the Smith River in the Dan 
River Basin, Virginia, began fiscal year 1986 at elevation 
971.22 feet MSL or 0.28 feet below rule curve and remained 
near rule curve through October. Flood producing rainfall 
during the first week of November raised the lake 
level on November 5 to 982.01 feet MSL the maximum 
elevation for the fiscal year. Below normal rainfall in 
December and January produced a drawdown of the lake 
to rule curve in December where it remained through 
January. February through May the lake was at an elevation 
approximately one foot below rule curve due to normal 
rainfall and drying conditions except in mid-March 
when the lake rose briefly above rule curve following 
heavy rains. In June and July as below normal rainfall and 
declining inflows continued, a gradual drawdown of 
Philpott Lake began which lasted through mid-August. 
Observed rainfall and inflows for the period of December 
through June were 59 and 40 percent below normal, 
respectively. Intense rainfall and a reduction in generation 
requirements during late August provided temporary 
relief as the lake level continued to rise through early 
September. Below normal rainfall again produced a 
drawdown of Philpott Lake through September. The lake 
reached the minimum elevation for the fiscal year of 963.81 
feet MSL or 7.69 feet below the rule curve on September 
30. All inflows to Philpott Lake during fiscal year 1986 
were controlled without having to spill water over the 
spillway. However, the early November flood required 
water to be released throught the sluice gates to maintain 
the lake level below the spillway crest. Flood damages 
prevented during the fiscal year were $1,200,000 which 
makes the cumulative total since inception of the project 
equal to $22,670,000. Gross generation amounted to 
24,285,470 kilowatt-hours and power revenue was $887,209 
for a total of $14,635,222 since inception. Total cost of functional 
operation for the period was $93,822. 
W. Kerr Scott Dam and Reservoir, located in the 
Yadkin-Pee Dee River Basin, North Carolina, began fiscal 
year 1986 at elevation 1,024.30 feet MSL or 5.70 feet below 
normal pool. As the area received near normal amounts of 
rain, the reservoir level remained five to six feet below 
normal pool through early November. The lake level rose 
to its maximum elevation for the fiscal year of 1,038.35 feet 
MSL on November 5 as the area received 8.57 inches of 
rainfall. Scott Reservoir returned to a level slightly above 
normal pool and remained there until late December. 
Below normal rainfall and declining inflows caused the 
reservoir level to drop to elevation 1,027.80 feet MSL on 
January 16. The reservoir level remained at or slightly 
below normal pool through February. Heavy rainfall 
during mid-March caused a minor reservoir rise to 
elevation 1,032.25 feet MSL on March 20. Scott Reservoir 
level once again returned to and remained at or slightly 
below normal pool through the end of May. Below normal 
rainfall and declining inflows caused the reservoir level to 
drop through mid-August. Observed rainfall and inflows 
for the period of December through August were 47% and 
43% below normal, respectively. The lake level reached a 
minimum elevation for the fiscal year on August 17 of 
6-16

WILMINGTON, N. C., DISTRICT 
1,022.98 feet MSL or 7.02 feet below normal pool. Heavy 
rainfall during mid-August caused the lake level to rise 
slightly. Another storm in early September produced a 
rapid rise to normal pool. However, by mid-September the 
reservoir level was again below normal pool. W. Kerr 
Scott Reservoir ended the fiscal year at elevation 1,025.62 
feet MSL or 4.38 feet below normal pool. Flood damages 
prevented during the fiscal year were $133,000 which 
makes the cumulative total since inception of the project 
equal to $60,084,000. The total cost of functional operation 
for the period was $76,889. 
General Investigations 
29. SURVEYS 
Cost for the period was $1,565,210, of which $139,649 
was for navigation studies, $1,139,913 was for flood control 
studies, $149,441 was for beach erosion studies, $5,120 for 
review of authorized projects, $77,000 for Special Investigations, 
$10,361 for FERC licenses review, $3,000 for 
soil conservation service, $16,156 for hydrologic studies, 
and $24,570 for cooperation with states. 
30. COLLECTION AND STUDY OF BASIC DATA 
Flood plain information studies, as authorized by Section 
206, 1960 Flood Control Act, as amended, comprise 
compilation and dissemination, upon the request of a State 
or a political subdivision thereof, of information on floods 
and flood damages, including identification of areas subject 
to inundation by floods of various magnitudes and frequencies, 
and general criteria for guidance of Federal and non- 
Federal interests and agencies in the use of flood plain 
areas; and provide advice to other Federal agencies and 
local interests for their use in planning to ameliorate the 
flood hazard. Total costs for the period were $196,142. 
Total costs to September 30, 1986 were $3,809,033. 
31. CONTINUATION OF PLANNING 
AND ENGINEERING 
Continuation of Planning and Engineering for the 
Roanoke River Upper Basin, Virginia, Headwaters Area 
cost $132,260. This is the first report since CP&E was 
initiated. 
32. ADVANCE ENGINEERING AND DESIGN 
Advance engineering and design for Fort Fisher and 
Vicinity, N.C., cost $360. 
6-17

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
TABLE 6-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
1. Aquatic Plant Control 
(R&H Act of 1965) 
(Regular Funds) 
(Contributed Funds) 
2. Atlantic Intracoastal 
Waterway between 
Norfolk, Va. & St. 
Johns River, Fla. 
(Regular Funds) 
(Contributed Funds) 
3. Avon Harbor, N.C. 
(Regular Funds) 
(Contributed Funds) 
4. Beaufort Harbor, N.C. 
(Regular Funds) 
(Contributed Funds) 
5. Belhaven Harbor, N.C. 
6. Cape Fear River, 
N. C. above 
Wilmington 
7. Channel from Back 
Sound to Lookout 
Bight, N. C. 
8. Lockwoods Folly 
River, N. C. 
(Regular Funds) 
(Contributed Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
18,000 
13,184 
3,644,4772 
703,9513 
3,783,937 
3,914,751 
73,740 
57,800 
14,000 
44 
44 
243,500 
50,8808 
32,000 
73,559 
34,000 
70,000 
43,591 
876,080 
3,934,987 
3,760,711 
4,011,260 
1,551 
29,0516 
46,000 
50,440 
4,800,000 
4,057,998 
5,205,000 
5,345,207 
14,000 
- 
8,870 
8,844 
-23,849 
186,771 
43,500 
44,344 
34,000 
76,400 
76,379 
1,106 
1,106 
414,000 
434,800 
7,000 
11,069 
-93,477 
125,319 
363,000 
360,874 
92,650 
424,400 
423,514 
136,200 
138,455 
-156,545 
-78,833 
361,000 
356,941 
92,65015 
517,800 
519,195 
146,400 
146,585 
235,600 
232,291 
100,000 
83,917 
6,469,000 
7,324,248 
9,777,600 
9,563,186 
718,630 
653,300 
264,400 
264,426 
74,986 
74,986 
51,200 
51,221 
353,400 
309,487 
31,809 
31,809' 
41,851,973^ 
41,735,875^ 
74,084,6605 
73,641,6045 
86,851 
86,851 
732,630 
667,300 
74,096 
74,096 
363,049 
363,049 
74,986 
74,986 
818,040* 
818,040 
2,898,91410' o 
2,898,914 o 10 
34,000 
34,000 
168,833 
168,833 
- 126,687 
- 126,687 
13,800 54,406 
13,800 54,406 
- 3,759,57311 
- 3,759,57311 
618,000 12,753,61412 
468,696 12,602,92212 
- 88,328 
- 88,328 
13,000 2,269,171 
12,754 2,267,730 
- 241,272 13 
- 241,27214 
746,200 3,385,846 
746,165 3,370,357 
- 92,650 
- 92,650 
6-18

WILMINGTON, N. C., DISTRICT 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
9. Manteo (Shallowbag) 
Bay, N. C. 
(Regular Funds) 
(Contributed Funds) 
10. Morehead City 
Harbor, N. C. 
(Regular Funds) 
(Contributed Funds) 
11. Ocracoke Inlet, N. C. 
12. Pamlico and Tar 
Rivers, N. C. 
13. Rollinson Channel, N.C. 
(Regular Funds) 
(Contributed Funds) 
14. Silver Lake 
Harbor, N. C. 
(Regular Funds) 
(Contributed Funds) 
15. Waterway Connecting 
Pamlico Sound and 
Beaufort Harbor, N.C. 
(Regular Funds) 
(Contributed Funds) 
16. Wilmington Harbor, N. C. 
(Regular Funds) 
(Contributed Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib: 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
1,000,000 
1,037,405 
4,941,000 
4,270,169 
2,200 
3,418,000 
3,347,194 
40,080 
40,080 
18,000 
20,420 
1,429 
7,036 
309,000 
407,288 
52,608 
265,750 
5,354,000 
5,847,149 
354,367 
280,371 
500,000 
407,323 
3,004,500 
3,981,556 
10,000 
1,906 
3,459,011 
3,554,083 
5,000 
5,435 
7,700 
7,700 
180,206 
180,986 
40,000 
154,087 
6,259 
8,224 
2,521,850 
2,513,647 
255,004 
59,000 
169,188 
5,145,900 
5,166,545 
963,940 
965,826 
1,794,000 
1,745,676 
270,954 
55,000 
14,100 
14,741 
44,200 
44,168 
1,500 
1,500 
391,400 
338,255 
198,833 
198,837 
3,902,000 
3,997,363 
580,284 
553,500 
109,007 
4,126,500 
4,315,962 
6,262,000 
6,310,359 
261,550 
122,543 
11,000 
12,438 
400 
432 
389,074 
389,074 
41,142 
41,142 
7,484,94516 
7,474,07916 
34,068,407 
34,047,622 
1,071,940 
1,065,732 
6,546,05317 
6,546,05317 
40,303,27318 
40,303,25118 
1,229,215 
874,254 
346,240 
346,240 
908,144 
906,943 
674,651 
674,651 
822,978 
822,978 
589,105 
589,105 
1,333,676 
1,333,676 
41,142 
41,142 
- 184,284 
- 184,284 
168,000 3,650,618 
177,145 3,606,618 
- 75,000 
- 75,000 
- 502,567 
- 502,567 
232,732 2,389,321 
232,732 2,389,321 
- 2,452 
- 2,452 
- 18,715,22619 
- 18,715,22619 
2,590,000 51,247,320 � 
2,553,489 51,207,848 " 
452,560 3,782,54521 
398,651 3,697,85621 
6-19

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
17. Ararat River, N.C. 
(Regular Funds) 
(Contributed Funds) 
18A. B. Everett Jordan 
Dam and Lake, N. C. 
(Regular Funds) 
(Contributed Funds) 
18B. Randleman Lake, N. C. 
19. Carolina Beach and 
Vicinity, N. C. 
(Regular Funds) 
(Contributed Funds) 
20. Leesville, Va. - 
Roanoke River, 
Sec. 32, Demo Project 
21A. Falls Lake, N. C. 
22. Scuppernong River, N.C. 
23. Stuart, Va. 
24A. W. Kerr Scott Dam 
and Reservoir, N. C. 
27A. John H. Kerr Dam 
and Reservoir, VA & N.C. 
27B. Philpott Lake, Va. 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
450,000 22 260,00024 
418,48423 226,74624 
- 12,300 
2,500,000 
2,407,679 
589,000 
571,995 
455,000 
276,193 
5,800,000 
5,304,189 
632,900 
601,634 
250,000 
298,513 
- -295,000 
49,483 -120,714 
571,408 25 267,79626 
1,279 
7,700,000 
6,189,542 
605,000 
576,848 
1,654 
1,450,000 
4,688,430 
601,000 
584,999 
- 33,776 
20,00729 30,812 29 
45,000 
42,496 
1,167,000 
989,327 
9,000 
127,362 
3,747,759 
3,542,191 
184,000 
224,709 
1,116,000 
1,025,106 
60,000 
35,771 
1,172,716 
1,268,670 
225,000 
76,081 
4,001,091 
4,128,796 
80,000 
118,049 
1,158,300 
1,223,739 
2,000,000 
280,590 
1,000,000 
22,366 
6,041,000 
6,145,290 
822,400 
789,652 
86,195 
803,000 
835,817 
992,200 
898,78727 
322 
5,200,000 
4,388,394 
917,200 
901,339 
43,000 
39,767 29 
115,000 
127,330 
1,103,200 
1,130,085 
4,550,000 
4,579,003 
4,047,200 
4,168,199 
-50,000 
30,222 
1,368,100 
1,315,095 
- 8,841,326 
- 8,841,326 
1,216,100 12,566,54832 
1,159,355 12,405,50533 
6-20 
997,540 
2,765,469 
1,103 
8,109,000 
8,595,667 
814,400 
879,704 
27,356 
-40,739 
-52,624 
40,789 
23 
2,694,000 
3,876,795 
1,748,000 
1,461,526 
14,830 
570,000 
202,768 
3,707,540 
3,691,289 
1,012,300 
23,469 
114;157,641 
111,726,877 
4,326,356 
4,264,794 
1,721,389 
1,721,389 
4,170,588 
4,144,186 
7,898,533 
7,849,092 
5,694,965 
5,694,965 
367,75528 
364,42528 
135,014,996 
134,299,507 
4,275,200 
3,910,242 
234,682 
233,111 
790,000 3o 
408,36531 
5,400 
199,367 
6,857,000 
6,576,725 
-5,400 
22,770 
2,089,000 
2,082,671 
94,402,927 
94,397,943 
59,852,042 , 
59,160,997 3 
14,796,384 
14,796,384 
18,945,306 36 
18,732,628 3

WILMINGTON, N. C., DISTRICT 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 1986 
1. Includes $2,369 refund to local interests in FY 82. 
2. Includes preauthorization study funds for Bogue Inlet: 
FY 82, $14,000; FY 83, $38,490; and preconstruction and construction 
funds: FY 83, $38,510. 
3. Includes preauthorization study costs for Bogue Inlet: 
FY 82, $7,174; FY 83, $45,316; and preconstruction and construction 
costs: FY 83, $21,368. 
4. Includes $198,707 for previous projects. 
5. Includes $107,634 for previous projects. 
6. Includes $13,934 refund to local interests. 
7. Includes preauthorization study funds for Morgan 
Creek: FY 82, $15,000; FY 83, $18,822; and preconstruction and 
construction funds: FY 83, $209,678. 
8. Includes preauthorization study costs for Morgan 
Creek: FY 82, $8,790; FY 83, $25,032; and preconstruction and 
construction costs: FY 83, $17,058. 
9. Includes $25,000 for previous projects. 
10. Includes $12,854 for previous projects. 
11. Includes $149,119 for previous projects. 
12. Includes $8,178 for previous projects. 
13. Includes preauthorization study funds: FY 64, $3,000; 
FY 65, -$2,755; FY 71, $8,000; FY 72, $2,000; FY 74, $9,000; FY 
75, $25,000; FY 76 & 76T, $20,000; FY 77, $2,500; FY 78, $8,800; 
FY 79, $3,000; FY 81, $1,680; and preconstruction planning 
funds: FY 80, $15,000 and FY 81, $19,320. 
14. Includes preauthorization study costs: FY 64, $219; FY 
65, $26; FY 71, $8,000; FY 72, $1,448; FY 73, $552; FY 74, $9,000; 
FY 75, $11,925; FY 76 & 76T, $27,977; FY 77, $7,598; FY 78, 
$7,449; FY 79, $4,351; FY 81, $1,680; and preconstruction planning 
costs: FY 80, $5,686 and FY 81, $1,471. 
15. Includes $69,145 refund to local interests. 
16. Adjusted by $6,361 to reflect actual cost. 
17. Includes $44,484 for previous projects. 
18. Includes $284,557 for previous projects. 
19. Includes $4,625,614 for new work on previous projects. 
20. Includes $602,614 for previous projects. 
21. Includes refunds to local interests: FY 78, $92,374; FY 
79, $8,000; FY 80, $14,007; FY 81, $1,847; FY 82, $2,823; FY 85, 
$60,000. 
22. Includes preauthorization study funds: FY 81, 
$153,000; FY 82, $128,000; FY 83, $62,487; and preconstruction 
funds: FY 83, $106,513. 
23. Includes preauthorization study costs: FY 81, 
$116,322; FY 82, $162,793; FY 83, $64,372; and preconstruction 
costs: FY 83, $74,997. 
24. Includes $6,924 preauthorization costs. 
25. Includes $400,000 refund to local interests. 
26. Includes $128,345 refund to local interests. 
27. Includes $82,600 refund to local interests. 
28. Includes monitoring costs: FY 80, $7,414; FY 81, 
$10,842; FY 82, $1,382. 
29. Preauthorization cost. 
30. Includes preauthorization study funds: FY 83, $45,000; 
FY 84, $9,986; and preconstruction funds: FY 84, $50,014; FY 
85, $115,000. 
31. Includes preauthorization study costs: FY 83, $42,496; 
FY 84, $12,490; and preconstruction costs: FY 84, $23,281; FY 
85, $127,330. 
32. Includes Special Recreation Use Fees funds: FY 74, 
$4,000; FY 75, $5,500; FY 76 & 76T, $3,600; FY 77, $5,800; FY 
78, $7,200; FY 79, $8,000; FY 80, $10,000; FY 81, $10,000; FY 82, 
$11,040; FY 83, $7,000; FY 84, $9,000. 
33. Includes Special Recreation Use Fees costs: FY 74, 
$4,000; FY 75, $4,400; FY 76 & 76T, $4,666; FY 77, $5,193; FY 
78, $6,824; FY 79, $7,506; FY 80, $11,312; FY 81, $9,688; FY 82, 
$9,727; FY 83, $7,000; FY 84, $8,444; FY 85, $2,379. 
34. Includes Special Recreation Use Fees funds: FY 74, 
$35,000; FY 76 & 76T, $48,000; FY 77, $51,400; FY 78, $115,100; 
FY 79, $63,000; FY 80, $60,000; FY 81, $80,000; FY 82, $67,160; 
FY 83, $77,759; FY 84, $73,000; and maintenance and operation 
of Dams funds: FY 79, $167,646. 
35. Includes Special Recreation Use Fees costs: FY 75, 
$35,000; FY 76 & 76T, $13,606; FY 77, $85,692; FY 78, $114,604; 
FY 79, $1,120; FY 80, $118,718; FY 81, $83,760; FY 82, $67,160; 
FY 83,$77,759; FY 84, $67,850; FY 85, $5,149; and maintenance 
and operation of Dams costs: FY 79, $167,350; FY 80, $296. 
36. Includes Special Recreation Use Fees funds: FY 75, 
$47,000; FY 78, $40,400; FY 79, $22,000; FY 80, $25,000; FY 81, 
$20,000; FY 82, $20,240; FY 83, $21,000; FY 84, $19,000. 
37. Includes Special Recreation Use Fees costs: FY 75, 
$13,741; FY 76 & 76T, $31,666; FY 77, $1,593; FY 78, $39,771; 
FY 79, $22,629; FY 80, $24,619; FY 81, $20,381; FY 82, $20,240; 
FY 83, $21,000; FY 84, $19,000. 
6-21

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
TABLE 6-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 25, 1912 
July 25, 1912 
August 8, 1917 
July 18, 1918 
Jan. 21, 1927 
July 3, 1930 
March 4, 19332 
June 26, 19343 
August 26, 1937 
August 26, 1937 
June 20, 1938 
June 20, 1938 
March 2, 1945 
June 30, 1948 
May 17, 1950 
May 17, 1950 
September 3, 1954 
Nov. 29, 1963, 
sec. 107 
July 14, 1960 
April 7, 1966, 
sec. 107 
July 14, 1960 
Nov. 7, 1966 
Nov. 7, 1966 
Dec. 31, 1970 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA., and ST. JOHNS RIVER, 
FLA. (See Section 2 of text) 
Original route of the Norfolk-Beaufort Inlet section. 
Purchase of canal. 
Change in route; following changes approved by 
Secretary of War, April 14, 1919: 
Albemarle Sound-Pamlico Sound section: Changed from 
"Alligator River-Rose Bay route" to "Alligator River- 
Pungo River route." 
Pamlico Sound-Neuse River Section: Changed from 
"Pamlico Sound-Brant Shoal Neuse River route" to 
"Goose Creek-Bay River route." 
Alligator River-Pungo route (proposed land cut connecting 
the rivers): Changed from a straight line to a bent 
line approaching nearer town of Fairfield, N. C. 
A 12-foot channel 90 feet wide from Beaufort to Cape 
Fear River, N. C., including highway bridge and tidal 
lock.4 
An 8-foot channel 75 feet wide from Cape Fear River to 
Winyah Bay, S. C. 
Construct a suitable bridge near Fairfield, N. C. 
Operating and care of works of improvements provided 
for with funds from War Department appropriations for 
rivers and harbors. 
Increasing dimensions of waterway to 12 feet deep and 
90 feet wide. 
A 12-foot side channel 90 feet wide to Swansboro. 
A yacht basin near Southport, 12 feet deep, 230 feet 
wide, and 450 feet long, with connecting channel. 
A 6-foot channel 90 feet wide from New River Inlet to 
Inland Waterway. 
Six mooring basins.5 
A 12-foot channel in New River.6 
Vicinity of Fairfield - drainage. 
Masonboro Inlet and connecting channels, including jetties 
at the inlet. 
A 12-foot channel and basin in Peltier Creek.8 
A 6-foot channel 90 feet wide from Intracoastal Waterway 
to Bogue Inlet gorge. 
An 8-foot channel 150 feet wide through New Topsail Inlet, 
thence a 7-foot channel 80 ft. wide to Intracoastal 
Waterway by way of Old Topsail Creek; and a 7-foot 
channel 80 feet wide in Banks Channel from New Topsail 
Inlet, paralleling barrier beach, to Intracoastal 
Waterway. 
Maintenance of a channel, 6 feet deep, 80 feet wide, and 
8,000 feet long, from the through channel of the waterway 
to and including a basin of the same depth, 130 feet 
wide and 180 feet long at Carolina Beach. 
Maintenance of general navigation features of N. C. 
State Ports Authority Small Boat Harbor at Southport. 
Replacement of Federally-owned and operated highway 
bridges at Coinjock, Fairfield, Wilkerson Creek, 
Hobucken, and Core Creek. 
H. D. 391, 62d Cong., 2d sess. 
H. D. 589, 62d Cong., 2d sess. 
H. D. 1478, 63d Cong., 3d sess. 
and H. D. 1136, 64th Cong., 1st 
sess.' 
Approved by Secretary of War, 
May 15, 1919. 
H. D. 450, 69th Cong., 1st sess. 
H. D. 41, 71st Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 5, 72d Cong., 1st sess. 
Rivers and Harbors Committee, 
Doc. 6, 75th Cong., 1st sess.' 
Rivers and Harbors Committee 
Doc. 16, 75th Cong., 1st sess.' 
H. D. 549, 75th Cong., 3d sess.' 
H. D. 691, 75th Cong., 3d sess.' 
H. D. 660, 76th Cong., 3d sess.' 
H. D. 421, 80th Cong., 1st sess.' 
H. D. 723, 80th Cong., 2d sess.' 
H. D. 341, 81st Cong., 1st sess.' 
H. D. 379, 81st Cong., 1st sess.' 
Detailed Project Report 
April 1963. 
Detailed Project Report 
July 1965 
H. D. 515, 89th Cong., 2d sess.' 
H.D. 514, 89th Cong., 2d sess.' 
H. D. 142, 92nd Cong., 1st sess. 
6-22

WILMINGTON, N. C., DISTRICT 
TABLE 6-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
October 22, 1976 
August 13, 1968 
February 18, 1982, 
sec. 107 
July 14, 1960 
September 7, 1983, 
sec. 107 
July 14, 1960 
March 3, 1881 
March 2, 1907 
March 3, 1925 
July 3, 1930 
March 2, 1945 
May 17, 1950 
May 21, 1965, 
sec. 107 
July 14, 1960 
August 12, 1983, 
sec. 107 
July 14, 1960 
July 3, 1930 
Oct. 17, 1940 
Feb. 7, 1967 
sec. 107 
July 14, 1960 
August 30, 19359 
August 26, 1937 
March 2, 1945 
March 2, 1945 
Modification of terms of local cooperation to allow for 
full Federal funding of Wilkerson Creek and Coinjock 
Bridges. 
Mitigation of damages caused by north jetty at Masonboro 
Inlet. 
An 8-foot channel 150 feet wide through Carolina Beach 
Inlet to the Intracoastal Waterway. 
An 8-foot channel 150 feet wide from the gorge in 
Bogue Inlet through the ocean bar. 
BEAUFORT HARBOR, N. C. (See Section 4 of text) 
A 9-foot channel 200 feet wide through Bulkhead Channel 
to Beaufort; a 6-foot channel 100 feet wide to North 
River and Core Sound; and construct jetties on 
Shackleford Point. 
Repairs to Fort Macon jetties and additional jetties and 
shore protection. 
Bulkhead across Bird Shoal. 
Increase in depth to 12 feet in Bulkhead Channel, 
Gallants Channel, and in front of Beaufort. 
Increase in width and length of basin in front of 
Beaufort, all to 12 feet deep. 
Increase in depth to 12 feet and in width to 100 feet in 
Taylors Creek; transfer to Beaufort Harbor project. 
Channels 15 feet deep, 100 feet wide in Bulkhead, 
Gallants and Taylors Creek channels, and through turning 
basin in front of Beaufort; and harbor of refuge in 
Town Creek, 12 feet deep, 400 feet wide, and 900 feet 
long connected to Gallants Channel by channel 12 feet 
deep, 150 feet wide, and 1,400 feet long. 
A channel 14 feet deep, 70 feet wide, and 1,900 feet long, 
from Bulkhead Channel to a turning basin 14 feet deep 
150 feet wide, and 300 feet long near the upper end of 
Morgan Creek. 
SILVER LAKE HARBOR, N. C. (See Section 14 of 
text) 
Entrance channel, 5 feet deep and 50 feet wide, from 
Pamlico Sound to the 3-foot contour in the lake, and 
training wall at entrance. 
Channel, 10 feet deep, and anchorage basin of same 
depth, 100 feet wide across Big Foot Slough and 60 feet 
wide in entrance. 
Basin depth of 12 feet in Silver Lake Harbor; channels 
12 feet deep, 150 feet wide, in Teaches Hole and Big 
cFhoaont nSell,o usgamh eC hannels and across Bluff Shoal; entrance depth, 60 feet wide; and training wall on 
south side of entrance channel. 
WATERWAY CONNECTING PAMLICO SOUND AND 
BEAUFORT HARBOR, N. C. (See Section 15 of text) 
A 7-foot channel 75 feet wide from Pamlico Sound to 
Beaufort Harbor via Wainright Channel. 
A 7-foot channel 74 feet wide to Atlantic. 
Channels 7 feet deep, 75 feet wide, at east and west 
ends of Harkers Island and side channel 5 feet deep, 75 
feet wide, with basin 150 by 130 feet, same depth, at Davis. 
A 7-foot side channel 75 feet wide, with basin 200 feet by 
500 feet, same depth, at Sealevel. 
H. D. 597, 94th Cong., 2d sess. 
Approved by OCE Oct. 2, 1980 
Detailed Project Report 
June 1980 
Detailed Project Report 
May 1983 
Annual Report, 1881, p. 1013 
Specified in act. 
Rivers and Harbors Committee 
Doc. 8, 68th Cong., 2d sess. 1 
H. D. 776, 69th Cong., 2d sess.' 
H. D. 334, 76th Cong., 1st sess.' 
H. D. 111, 81st Cong., 1st sess.' 
Detailed Project Report 
April 1965 
Detailed Project Report 
June 1983 
Rivers and Harbors Committee 
Doc. No. 3, 70th Cong., 1st sess. 
H. D. 325, 76th Cong., 1st sess. ' 
Detailed Project Report 
July 9, 1965 
H. D. 485, 72d Cong., 2d sess. ' 
Rivers and Harbors Committee 
Doc. 92, 74th Cong., 2d sess.' 
H. D. 99, 77th Cong., 1st sess.' 
S. D. 247, 77th Cong., 2d sess.' 
6-23

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
TABLE 6-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 17, 1950 A 6-foot side channel 60 feet wide, with basin 100 feet by H. D. 68, 81st Cong., 1st sess.' 
about 600 feet, same depth, at Marshallberg. 
July 11, 1963, A side channel 7 feet deep, 70 feet wide to local harbor at Detailed Project Report 
sec. 107 Cedar Island and an access channel 6 feet deep, 60 feet Dec. 12, 1968 
July 14, 1960 wide and about 400 feet long to a basin same depth, 60 by 
100 feet. 
Sept. 22, 1967, An entrance channel 6 feet deep, 60 feet wide, from Back Detailed Project Report 
sec. 107 Sound to harbor of refuge 120 by 250 feet, same depth, at March 13, 1967 
July 14, 1960 west end of Harkers Island in Brook Creek. 
Feb. 24, 1969, A channel 7 feet deep, 70 feet wide, from existing side Detailed Project Report 
sec. 107 channel at Atlantic to a basin 600 by 180 feet, same depth, Dec. 21, 1967 
July 14, 1960 with a breakwater, between mouth of Little Port Brook 
and White Point. 
April 3, 1975, Deepening the existing 5-foot channel and basin at Davis Detailed Project Report 
sec. 107 to 7 feet. Feb. 8, 1974 
July 14, 1960'� 
1. Contains latest published maps. 
2. Public Law No. 443, 72d Cong. 
3. Permanent Appropriations Repeal Act. 
4. Tidal lock in land cut between Myrtle Sound and Cape 
Fear River, deauthorized September 23, 1986, under authority 
of Sec. 12, PL 93-251. 
5. Deauthorized August 5, 1977 under authority of Sec. 
12, PL 93-251. 
6. A 12-foot by 90-foot channel in New River from Intracoastal 
Waterway to and including a basin at Jacksonville, 
N. C. 
7. Jetties on each side of Masonboro Inlet. 
8. A 6-foot by 50-foot channel provided under Section 3, 
River and Harbor Act of March 2, 1945; 12-foot by 90-foot project 
classified as inactive. 
9. Included in the Public Works Administration Program, 
Jan. 3, 1934. 
10. Deauthorized by the Chief of Engineers March 31, 
1982. 
6-24

WILMINGTON, N. C., DISTRICT 
TABLE 6-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
Project See Annual Operation and Report for Construction Maintenance 
Aquatic Plant Control1 
(R & H Act of 1958 and 1962) 1969 70,664 - 
Atlantic Beach Channels, N. C. 1976 29,1014 66,630 
Bay River, N. C.' 1950 44,382 49,627 
Black River, N. C. 1969 12,358 124,846 
Cashie River, N. C. 1950 40,403 15,905 
Channel Connecting Thoroughfare Bay 
with Cedar Bay, N. C.1 1975 69,610 25,615 
Channel from Pamlico Sound to Rodanthe, N. C.1 1975 42,029 5,685 
Chowan River, N. C. 1950 - - 
Contentnea Creek, N. C.' 1941 64,395 32,247 
Drum Inlet, N. C.' 1979 166,119 1,050,579 
Edenton Harbor, N. C.1 1960 73,750 47,642 
Far Creek, N. C.1 1985 164,642 1,181,904 
Fishing Creek, N. C.' 1922 22,715 8,633 
Knobb's Creek, N. C.', 2 19613 80,500 48,969 
Mackay Creek, N. C.' 19383 13,375 6,273 
Neuse River, N. C.' 1982 477,2236 328,607 
Newbegun Creek, N. C. 19283 4,802 247 
Northeast (Cape Fear) River, N. C.' 1950 10,688 61,139 
Pembroke Creek, N. C. 1976 60,000 - 
Perquimans River, N. C.' 1910 13,750 414 
Roanoke River, N. C.' 1983' 404,584 550,364 
Scuppernong River, N. C.' 1950 81,164 80,682 
Shallotte River, N. C.' 1984 18,181 170,956 
Smith Creek, Pamlico County, N. C.' 1984 113,273 36,387 
Smiths Creek (Wilmington), N. C.' 1950 8,507 18 
South River, N. C.' 1936 12,452 23,686 
Stumpy Point Bay, N. C.' 1984 268,381 736,815 
Swift Creek, N. C.' 1940 1,600 5,422 
Trent River, N. C.', S 1968 115,199 143,579 
Wallace Channel, Pamlico Sound, N. C. 1965 132,834 85,221 
Waterway - Norfolk, Va. to Sounds of N. C. 1976 751,196 2,893,812 
Waterway Connecting Swanquarter 
Bay with Deep Bay, N. C. 1984 911,099 182,725 
Wrights Creek, N. C.' 1984 68,325 166,602 
1. Completed. 
2. Transferred from Norfolk District (FY 1970); Meherrin 
River, N. C., Transferred to Norfolk District. 
3. Report of Norfolk District. 
4. Includes $2,055 refund to local interests. 
5. 8-foot modification deauthorized August 5, 1977, under 
authority of Sec. 12, PL 93-251. 
6. Includes $1,959 refund to local interests on Dawson 
Creek, N.C. 
6-25

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
TABLE 6-D 
For Last Cost to September 30, 1986 
Full Report 
Project See Annual Operation and 
Report For Construction Maintenance 
Fort Fisher and Vicinity, N. C. 1984 490,000 - 
Fort Macon Park, N. C. 1973 620,000 - 
6-26

WILMINGTON, N. C., DISTRICT 
TABLE 6-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Black River, Harnett County, N. C.1 
Broad Creek, Beaufort County, N. C.1 
Brunswick County Beaches, N. C. 
(Cape Fear to North Carolina - 
South Carolina State Line)"1 
Conetoe Creek, N. C.' 
Contentnea Creek, N. C.' 
Core Creek, N. C.' 
Deep Creek, Edgecombe County, N. C.' 
Ellerbe Creek, Durham County, N. C.'1 
Ellis Swamp, Gates County, N. C.'1 
Filberts Creek, N. C.' 
Gapway Swamp, N. C. & S. C.','0 
Gardners Creek, N. C.'1 
Genoa Sewer Facility, Wayne County, N. C.' 
Goldsboro, Neuse River, N. C. 
Howards Mill Lake, N. C.12 
Joyce Creek, Camden County, N. C.' 
Leith's Creek, Scotland County, N. C.', 's 
Lick Run, Roanoke, Va.' 
Little Rockfish Creek, Hope Mills, N. C.' 
Little Sugar Creek, Charlotte, N. C.',' � 
New River, N. C.'1 
New River, Onslow County, N. C.'1 
Northeast (Cape Fear) River, N. C.'1 
Ocracoke Island, N. C.' 3 
Old Field Swamp, N. C.','10 
Pantego Creek and Cucklers Creek, N. C. 
Pasquotank River, N. C. 
Perquimans River, N. C.' 
Pungo Creek, N. C.' 
Pungo River, N. C.' 
Reddies River Lake, N. C.' s 5 
Roaring River Lake, N. C.' 5 
Simmons Bay, N. C.'� 
South Creek, N. C.' 
Swift Creek, Pitt and Craven Counties, N. C.' 
Tar River, N. C 
Tar River, N. C.' 
Tar River and tributaries, N. C.' 
Tar River, Princeville, N. C. 
Trent River, N. C.' 
Waccamaw River & Seven Creeks, N.C. & S.C.',' � 
White Oak Dike, Bladen and Pender 
Counties, N. C.'1 
Wrightsville Beach, N.C. 
1984 
1972 
1976 
1960 
1939-1943 & 1958 
1965 
1984 
1963 
1971 
1970 
1969 
1972 
1985 
1984 
1980 
1984 
1982 
1974 
1978 
1979 
1950 & 1956 
1972 
1961 
1975 
1969 
1963 
1960 
1961 
1972 
1971 
1980 
1978 
1963 
1971 
1966 
1964 
1947 
1943 
1967 
1953 
1961 
1963 
1983 
1. Project authorized by Chief of Engineers under special 
continuing authority. 
2. Includes $17,356 refund to local interests. 
3. Adjusted to reflect actual cost. 
4. Includes $3,081 refund to local interests. 
5. Includes $116,508 refund to local interests. 
6. Includes $1,519 refund to local interests. 
7. Includes $387 refund to local interests. 
8. Includes $338 refund to local interests. 
9. Adjusted $3,000 to include preauthorization cost prior to 
FY 1960. 
10. Transferred from Charleston District, FY 1980. 
11. Reclassified to inactive category February 3, 1976. 
12. Reclassified to deferred category October 2, 1980. 
13. Reclassified to inactive category November 25, 1974. 
14. Includes $61,585 refund to local interests. 
15. Transferred from Charleston District, FY 1984. 
16. Includes $1,057 refund to local interests. 
6-27 
475,574 
283,846 
572,1146 
29,867 
50,889 
236,2239 
394,055 
223,413 
138,1176 
37,7773 
374,005 
54,5978 
167,800 
50,430 
698,400 
606,18916 
430,151 
1,280,317 
113,657 
763,022 
51,896 
580,977 
95,873 
129,592 
86,600 
517,948 
80,931 
6,366 
582,270 
296,6022,3 
985,800 
370,000 
186,435 
194,367 
611,096 
81,266 
18,624 
22,660 
390,249 
64,769 
67,821 
214,286 
3,013,18814 
-
-
-
-
- 
623,687 
61,473

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
TABLE 6-G DEAUTHORIZED PROJECTS 
For Last Full Report Federal Contributed 
See Annual Report Date Funds Funds 
Project For Deauthorized Expended Expended 
Adkin Branch, N. C. 1982 8 Sep. 812 219,477 - 
AIWW - Mooring Basins None 5 Aug. 77' - - 
AIWW - Tidal Lock in Snows Cut None 23 Sept. 86' - - 
Bodie Island, N. C. None 5 Aug. 77' - - 
Cape Lookout, N. C. None 5 Aug. 77' - - 
Conoho Creek, N. C. 1974 31 Mar. 782 79,782 - 
Contentnea Creek, N. C. 1972 31 Mar. 783 4,250 - 
Davis, N. C. 1982 31 Mar. 824 25,419 - 
Harbor of Refuge, N. C. 1934 1 Nov. 81' 1,396,653 - 
Hominy Swamp, N. C. 1973 31 Mar. 782 107,472 - 
Hyde County Dike, N. C. None 5 Aug. 77' - - 
MacKay Creek, N. C. 1976 31 Mar. 782 130,900 - 
Mann's Harbor, N. C. 1973 31 Mar. 78' 7,265 - 
Mill Creek, N. C. 1973 31 Mar. 782 116,395 - 
Mocassin Swamp, N. C. 1973 31 Mar. 782 36,680 - 
Moyock Creek, N. C. 1973 31 Mar. 782 64,416 - 
Nahunta Swamp, N. C. 1973 31 Mar. 782 65,673 - 
Neuse River, N. C. None 31 Mar. 784 30,911 - 
Neuse River Barrier, N. C. None 5 Aug. 77' - - 
Neuse River, 300 ft.-wide None 5 Aug. 77' - - 
channel in front of 
New Bern 
North River Dike, N. C. None 5 Aug. 771 - - 
Rockfish Creek, N. C. 1976 31 Mar. 782 157,721 - 
Six Runs Creek, N. C. 1971 31 Mar. 782 64,977 - 
Sweetwater Creek, N. C. 1973 31 Mar. 782 64,584 - 
Thoroughfare Swamp, N. C. 1976 31 Mar. 782 132,767 - 
Topsail Beach and None 5 Aug. 771 - - 
Surf City, N. C. 
Tranters Creek, N. C. 1974 11 Jan. 852 139,339 - 
Trent River, Basins and None 5 Aug. 771 - - 
Access Channels at 
New Bern, N. C. 
1. Deauthorized under authority of Sec. 12, PL 93-251. 
2. Deauthorized pursuant to the continuing authority provided 
the Chief of Engineers under Sec. 205 of the 1948 FC Act, as 
amended. 
3. Deauthorized pursuant to the continuing authority provided 
the Chief of Engineers under Sec. 208 of the 1954 Flood Control 
Act. 
4. Deauthorized pursuant to the continuing authority provided 
the Chief of Engineers under Sec. 107 of the R&H Act of 1960 
as amended. 
6-28

WILMINGTON, N. C., DISTRICT 
TABLE 6-H RECONNAISSANCE AND CONDITION SURVEYS 
Project Date Survey Conducted 
Rollinson Channel, N. C. June 1986 
Shallotte River, N. C. September 1986 
Waterway Connecting Pamlico Sound and Beaufort Harbor, N. C. September 1986 
NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
Navigation Activities Pursuant to Section 107, Public Law 86-645 (preauthorization) 
TABLE 6-I 
Study Identification Fiscal Period Cost 
Harkers Island Harbor,N. C. 19,524 
Walters Slough, N. C. 11,241 
White Oak River, N. C. 15,138 
Wilmington Harbor, N. C. 7,500 
6-29

TABLE 6-J DAMS AND RESERVOIRS 
See Miles Height Reservoir Power Estimated 
Section Project Name Nearest City River Above of Type Capacity Development Construe- Cost Lands Total 
in Text Mouth Dam (ft) (acre-feet) (kilowatts) tion and Damages 
18. Cape Fear B. Everett Jordan
2 
River Basin, Howards Mill
2 , 14 
N.C. Randleman
2 
Small reservoirs 
21. Neuse River Falls
2 
Basin, N.C. Wilson Mills 
Beulahtown 
Bakers Mills 
Little Buffalo 
Buckhorn 
Wiggins Mill 
Stantonsburg 
Great Swamp 
Black Creek 
Aycock Swamp 
Hillsboro 
Orange 
24. Yadkin River W. Kerr Scott, N.C. 
Basin, N.C.&S.C. 
27. Roanoke River John H. Kerr, Va., and 
Basin, Va. and N.C.
2 
N.C. Philpott, Va.
2 
Gaston, Va. and N.C. 
6 
Roanoke Rapids, N.C.
7 
Smith Mountain, Va.
8 
Leesville, Va. 
9 
Taber, Va. 
Melrose, Va. 
Randolph, Va. 
Stuart, Va. and N.C. 
Schoolfield, Va. and N.C. 
Moncure, N.C. 
Carthage, N.C. 
Randleman, N.C. 
Falls, N.C. 
Wilson Mills, N.C. 
Kenly, N.C. 
Princeton, N.C. 
Kenly, N.C. 
Wilson, N.C. 
Wilson, N.C. 
Stantonsburg, N.C. 
Fremont, N.C. 
Wilson, N.C. 
Fremont, N.C. 
Durham, N.C. 
Durham, N.C. 
Wilkesboro, N.C. 
Boydton, Va. 
Bassett, Va. 
Roanoke Rapids, N.C. 
Roanoke Rapids, N.C. 
Altavista, Va. 
Altavista, Va. 
Altavista, Va. 
Brookneal, Va. 
Chase City, Va. 
Spray, N.C. 
Danville, Va. 
Haw 
Deep 
Deep 
Various 
Neuse 
Neuse 
Little 
Little 
Little Buffalo Creek 
Contentnea Creek 
Contentnea Creek 
Tisnot Swamp 
Great Swamp 
Black Creek 
Aycock Swamp 
Eno 
Little 
Yadkin-Pee Dee 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
4.3 
55.0 
85.0 
404.0 
178.7 
336.2 
144.9 
137.0 
314.2 
293.7 
275.0 
262.9 
227.8 
297.2 
265.9 
112 E 753,500 - 77,790,500 58,209,500 
106 E 233,000 - 18,874,000 14,726,000 
110 E 108,000 - 53,659,600 61,340,400 
20 to 70 + E 923,000 - - - 
92 E 335,620 - 72,767,800 90,232,200 
81 CG,E 201,000 - - - 
50 E 81,000 - - - 
53 E 36,000 - - - 
51 E 13,000 - - - 
63 E 119,000 - - - 
42 E 35,000 - - - 
36 E 48,000 - - - 
39 E 18,000 - - - 
33 E 17,000 - - - 
37 E 7,000 - - - 
136 E 123,000 - - - 
107 E 57,000 - - - 
148 E 153,000 - 5,749,343 3,360,657 
144 CG,E 2,808,000 204,000 67,529,000 24,521,000 
220 CG
1 1 
249,800 14,000 13,933,000 1,157,000 
108 CG,E 432,000 54,000 27,000,000 3,500,000 
75 CG 59,300 83,000 31,300,000 800,000 
244 CG 825,000 41,000 28,000,000 3,800,000 
95 CG,E 76,900 20,000 9,100,000 1,000,000 
54 CG 34,000 12,000 8,000,000 1,700,000 
110 CG,E 120,000 43,000 17,700,000 6,000,000 
147 CG,E 350,000 48,000 22,100,000 4,700,000 
138 E, 163,000 15,000 9,000,000 1,100,000 
126 CG,E 248,000 80,000 27,800,000 6,400,000 
1. Includes highway, railroad, and utility relocations. 
2. For details, see individual report. 
3. Includes $3,900,000 presently allocated to water supply to be reimbursed in the future by 
local interests and $180,000 cash contribution for construction of ranger security buildings. 
4. Includes $12,400,000 presently allocated to water supply and $18,600,000 recreation and fish 
and wildlife to be reimbursed in the future by local interests. 
5. Exclusive of transmission lines. 
6. Construction completed in 1963 by Virginia Electric and Power Co. 
7. Based on modified plan developed in fiscal year 1949. Construction completed June 1955 by 
Virginia Electric and Power Co. 
8. Construction completed in February 1966 by Appalachian Power Co. 
9. Construction completed in June 1963 by Appalachian Power Co. 
10. Includes cost of earth dam on Whipping Creek. 
11. Authorizing legislation provided for earth dam; concrete gravity dam constructed. 
12. Includes $1,600,000 presently allocated to recreation and fish and wildlife. 
13. Includes $61,171,000 presently allocated to water supply, $25,752,000 allocated to recreation 
and $5,077,000 to flood control. 
14. Reclassified to the deferred category October 2, 1980.
Key 
E - Earth 
CG - Concrete Gravity 
136,000,000' 
33,600,00012 
115,000,00013 
38,454,000 
163,000,000' 
13,000,000 
9,300,000 
6,600,000 
1,100,000 
17,300,000 
6,700,000 
5,100000 
1,800,000 
1,500,000 
550:000 
8,100,000 
3,500,000 
9,110,000 
92,050,0005 
15,090,000 
30,500,000 
32,100,000 
31,800,000 
10,100,000 
9,700,000 
23,700,000a 
26,800,000 
10,100,000 
36,000,000 
0
0
tD 
O0

WILMINGTON, N. C., DISTRICT 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, 
Public Law 858, 80th Congress, as amended 
TABLE 6-K (Preauthorization 
Study Identification Fiscal Period Cost 
Blackberry Creek, Henry County, VA 45 
Buffalo Creek, Lee County, N. C. 1,913 
Carolina Beach, N. C. 7,500 
Carvins Creek, Roanoke, VA.' 30,920 
Chapel Hill, N. C. 58,052 
Crabtree Creek & Trib., Wake County, N. C. 134,267 
Danville, Va. 11,083 
Falling Creek, Rockingham, N. C.2 7,500 
Great Coharie Creek, N. C. 36,550 
Grifton, N. C. 7,500 
Jordan Creek, Henry County, VA. 329 
Lower Creek, Lenoir, N. C. 31,355 
Peters Creek, Roanoke, VA. 35,465 
Siler City Streams, N. C. 1,301 
Soules Swamp, Whiteville, N. C. 1,506 
1. Includes $7,500 reimbursement to the revolving fund. 
2. Reimbursement to revolving fund. 
6-31

CHARLESTON, S.C., DISTRICT* 
This district comprises all of South Carolina (except local 
watersheds draining into the Savannah River). It embraces the 
drainage basins tributary to the Atlantic Ocean between Little 
River and Port Royal Sound, except watersheds of Mackay and 
Skull Creeks, and excluding Hilton Head Island. 
IMPROVEMENTS 
Navigation Page 
1 Aquatic Plant Control, SC ...................................... 7-2 
2 Atlantic Intracoastal Waterway Between 
Norfolk, VA and St. Johns River, FL ................ 7-2 
3 Charleston Harbor, SC ............................................ 7-2 
4 Cooper River, Charleston Harbor, SC .................... 7-3 
5 Cooper River Seismic Modification 
Charleston Harbor, SC ....................................... 7-4 
6 Folly River, SC ....................................................... 7-4 
7 Georgetown Harbor, SC...........................................7-4 
8 Little River Inlet, NC & SC .................................... 7-5 
9 Murrells Inlet, SC....................................................7-5 
10 Port Royal Harbor, SC ............................................ 7-6 
11 Shipyard River, SC ................................................. 7-6 
12 Town Creek, SC ...................................................... 7-7 
13 Reconnaissance and Condition Surveys ................. 7-7 
14 Other Authorized Navigation Projects .................... 7-7 
15 Navigation Work Under Special Authorization.......7-7 
Beach Erosion 
16 Other Authorized Beach Erosion 
Control Projects ................................................. 7-7 
17 Eagle Creek, SC ...................................................... 7-7 
Flood Control Page 
18 Scotts Creek, SC ..................................................... 7-7 
19 Cooper River, Pompion Hill Chapel, SC ................ 7-8 
20 Inspection of Completed Flood Control Projects.....7-8 
21 Other Authorized Flood Control Projects ............... 7-8 
22 Flood Control Work Under 
Special Authorization .......................................... 7-8 
General Investigations 
23 Active Investigations .............................................. 7-8 
Tables 
Table 7-A Cost and Financial Statement ........................ 7-93 
Table 7-B Authorizing Legislation ................................. 7-11 
Table 7-C Other Authorized Navigation Projects............7-15 
Table 7-D Navigation Work Under 
Special Authorization ............................... 7-15 
Table 7-E Other Authorized Beach 
Erosion Projects ........................................ 7-15 
Table 7-F Other Authorized Flood Control Projects ....... 7-16 
Table 7-G Flood Control Work Under 
Special Authorization ............................... 7-16 
Table 7-H Active General Investigations.........................7-17 
* All costs and financial statements for projects listed at the end of this chapter. All other tables are referenced in text and also 
appear at the end of this chapter. 
7-1

REPORT OF THE CHIEF OF ENGINEERS, US. ARMY 1986 
Navigation 
1. AQUATIC PLANT CONTROL, S.C. 
Location. The project includes all public waters in the 
State of South Carolina. 
Existing Project. The project provides for the control 
and progressive eradication of noxious aquatic plant growths 
from public waters in the combined interest of navigation, 
flood control, drainage, agriculture, fish and wildlife 
conservation, and public health. 
Local Cooperation. Local interests must agree to hold 
the United States free from damages that may occur from 
operations performed in connection with this project and 
contribute 30 percent of the cost of field operations. The 
South Carolina Water Resources Commission is designated as 
the State's lead agency for aquatic plant management and meets 
local interest requirements. 
Operations and results during fiscal year. Aquatic 
plants now infest approximately 40,000 acres, with the worst 
problems being in Lake Marion. During FY 864,441 acres of 
aquatic plants in 33 water bodies were treated with herbicides. 
Grass carp was purchased and stocked in 6 lakes having a total 
surface area of 622 acres. 
The cost of field operations in FY 86 was $527,734 and 
included $450,569 for the application of herbicides, $21,078 
for the purchase and stocking of grass carp, $21,000 for aquatic 
plant surveys, and $35,087 for program management by the 
contractor. The cost of planning and contract administration 
was $57,891. 
Condition at end of fiscal year. The project is 
ongoing. Federal costs for the project to date have been 
$2,112,450 for new work. 
2. ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA. AND ST. 
JOHNS RIVER, FL. (CHARLESTON 
DISTRICT) 
Location. The project starts at Little River at the North 
Carolina-South Carolina state line and extends generally south 
along the coast of South Carolina 62 miles to Winyah Bay; 
thence 63.5 miles to Charleston; thence 84.5 miles to and 
including Port Royal Sound; a total of 210 miles. (See 
National Ocean Survey Charts Nos. 11513, 11521, 11531, 
11534, and 11535.) 
Previous projects. For further details see page 613 of 
Annual Report for 1932. 
Existing project. The project provides for a waterway 
twelve feet deep and not less than 90 feet wide with a branch 
channel of the same dimensions to McClellanville and 
construction of three bridges crossing the waterway in Horry 
County, South Carolina. (See table at end of chapter for acts 
authorizing existing project.) 
Local cooperation. Requirements fully satisfied. 
Terminal facilities. There are rail-water terminals at 
Georgetown, Charleston, Johns Island, and Port Royal and 
numerous open-pile wharves mostly for shipping agricultural 
products, fish, oysters, pulpwood, wood products, and 
petroleum products. Marinas are located at convenient 
intervals along the waterway where limited supplies and repair 
facilities are available for both commercial vessels and pleasure 
craft. Facilities are considered adequate for existing commerce 
and recreation requirements. 
Operations and results during fiscal year. 
Maintenance: Contract maintenance dredging was performed 
by pipeline dredge between Winyah Bay and Charleston, S.C. 
during October 1985 - February 1986, removing 1,045,520 
cubic yards at a total cost of $548,639. Bank stabilization 
costs for the Myrtle Beach, S.C. area were $971,990 and the 
mosquito abatement control contract costs were $46,292. The 
cost of operating the Snagboat Snell in the Winyah Bay to 
Little River area was $132,000. Costs of $823,295 were also 
incurred for contract dike management. Condition and 
operation studies, natural resource management, water control 
management, engineering and design, and supervision and 
administration costs were $558,313. 
Condition at end of fiscal year. Existing project was 
completed in 1940; three bridges were completed in 1936. 
Federal costs of existing project to date have been $7,345,888 
for new work and $44,985,220 for maintenance, for a total of 
$52,331,108. 
3. CHARLESTON HARBOR, S.C. 
Location. The harbor is located on the coast of South 
Carolina about 15 miles south of the midpoint of the 
coastline, 50 miles southwest of Winyah Bay, S.C., and 80 
miles northeast of the mouth of Savannah River. (See 
National Ocean Survey Charts Nos. 11521 and 11524.) 
Previous projects. For further details see page 1808 of 
Annual Report for 1915; page 579 of Annual Report for 1926; 
and page 562 of Annual Report for 1938. 
Existing project. The authorized project provides for a 
channel 35 feet deep with varying widths from the Atlantic 
Ocean to the mouth of Goose Creek, a total of 26.3 miles, 
together with a 35-foot depth by 500-foot width channel via 
7-2

CHARLESTON, S.C., DISTRICT 
Town Creek. Also, a ten foot depth by 110-foot width 
channel on the Mount Pleasant side of the harbor into Shem 
Creek to U.S. Highway 17 Bridge, and a 30-foot anchorage 
basin in the lower harbor between Castle Pinckney and Fort 
Moultrie. A 40-foot channel estimated to cost $6,060,000 
(1960) was authorized to be executed when found necessary in 
the interest of national defense from the 40-foot contour in 
Atlantic Ocean to U.S. Naval Base. For further details see 
page 425 of Annual Report for 1962. The Phase I Design 
Memorandum stage of Advance Engineering and Design has 
been authorized for deepening of the 35-foot channel to 40 feet 
(42 feet in the ocean bar and entrance channel) from the 42-foot 
ocean contour to Goose Creek, a total distance of 26.9 miles, 
construction of one turning basin, modification of existing 
turning basins, deepening and modification of the anchorage 
basin, and deepening Shipyard River to 38 feet. (See table at 
end of chapter for acts authorizing existing project.) 
Local cooperation. Local interests have fully complied 
with their responsibility to date but are experiencing difficulty 
in securing disposal areas for dredged material for continued 
future maintenance. 
Terminal facilities. Piers and slips extend for about 
one mile along the eastern waterfront of the City of Charleston 
with an additional mile of marginal wharves. The South 
Carolina State Ports Authority operates eight piers for fruit, 
wood, cold storage facilities and general cargo, a grain elevator 
and a beltline railway which serves the entire Cooper River 
waterfront. Modern facilities are also at wharves of seven 
major petroleum companies including storage tank farms. 
Modern facilities for marine repairs and servicing are available 
at Detyens Shipyard, located approximately ten miles northeast 
of Charleston on the Wando River. The U.S. Navy 
Department has modern facilities for maintenance of naval 
vessels including nuclear-powered submarines. Loading docks 
and storage areas for missile-carrying type vessels have also 
been constructed and are being operated by the U.S. Navy. For 
further details see Port Series No. 13, 1980, Corps of 
Engineers. 
Operations and results during fiscal year. 
Maintenance: Contract maintenance dredging was performed in 
(a) the Lower Harbor by pipeline dredges during October 1985 
- December 1985 removing 723,000 cubic yards of material, 
and (b) in the Anchorage Basin during October 1985 removing 
460,000 cubic yards of material. Total FY86 costs paid for 
dredging was $2,986,518. Dike management costs were 
$838,031 including costs of Riverine Utility Craft operation 
of $24,071. Condition and operation studies, water control 
management, engineering and design, and supervision and 
administration costs were $750,471. 
Condition at end of fiscal year. Jetties protecting 
the entrance channel across the bar were completed in 1895. 
The existing project was completed in October 1962 except for 
the national defense portion. Federal costs under the existing 
project to date have been $3,328,349 for new work and 
$90,878,598 for maintenance, a total cost of $94,206,947. 
4. COOPER RIVER, CHARLESTON HARBOR, 
S.C. 
Location. Cooper River is located in Charleston and 
Berkeley Counties, S.C., and empties into the Atlantic Ocean 
at Charleston (See National Ocean Survey Charts Nos. 11521 
and 11524.) 
Existing project. The major cause of the shoaling 
problem in Charleston Harbor was the diversion of fresh water 
from the Santee River through Pinopolis Dam into the salt 
water of Charleston Harbor, which caused density currents 
which traps sediments resulting in a phenomenal rate of 
deposition. The most practical solution of the shoaling 
problem was to re-divert most of the Santee River waters 
above Pinopolis Dam back into the lower Santee River 
through a canal beginning at Lake Moultrie and extending to 
the Santee River in the vicinity of St. Stephen, South 
Carolina. The project for Cooper River as authorized by the 
1968 River and Harbor Act provided that the discharge through 
the existing Pinopolis Hydroplant be reduced to a flow which 
would not establish a density current in the harbor. This flow 
was estimated at 3,000 cubic feet per second (cfs) during the 
design phase of the project, but after operational tests this flow 
is estimated at 4,500 cfs. The excess water impounded in Lake 
Moultrie is being directed through a new canal above St. 
Stephen, South Carolina, to enter the Santee River at a point 
well below the Lake Marion Spillway (Wilson Dam). A new 
hydroelectric facility was constructed on the new canal at the 
edge of the swamp adjacent to the Santee River. This plant 
replaces those features made less effective at Pinopolis through 
curtailment of flows. The average flow of 11,100 cfs at the 
new powerplant, plus the 4,500 cfs average release planned for 
Pinopolis, approximates the historical average flow at 
Pinopolis. The three generators at the new plant are rated at 
28,000 kilowatts each, for a total of 84,000 kilowatts. In the 
interest of fish and wildlife resources of the area, the plan 
includes a herring lift at the new powerhouse site and a 
relocated fish hatchery. 
Estimated cost of the project (1985) is $191,500,000, all 
Federal. (See table at end of chapter for acts authorizing 
existing project.) 
Local cooperation. None required. 
Operations and results during fiscal year. New 
Work: Funds were received for initiation of construction 
during FY 75. Costs during FY 86 were $10,695 for lands 
and damages, $24,258 for relocations, $5,050,454 for power 
plant, $3,358 for fish and wildlife facilities contract, $83,282 
7-3 
C

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
for generators, $8,055 for governors, $30,869 for cooling 
water facilities - general construction, $9,172 for buildings, 
grounds and utilities, and $7,048 for cultural resources 
preservation. Engineering and design and supervision and 
administration costs were $577,573. Maintenance: Funds of 
$3,349,732 were spent for maintenance of completed work and 
included $1,443,185 paid to the South Carolina Public Service 
Authority for power losses incurred as a result of this project. 
Condition at end of fiscal year. Preconstruction 
planning was completed at the end of FY 74. The General 
Design Memorandum was completed in January 1972 and 
work is proceeding on schedule on other phases of the project. 
Construction was initiated March 1977. The project is 99% 
complete. The power-on-line date was March 1985. Federal 
costs for the existing project to date have been $189,334,474 
for new work and $5,786,740 for maintenance, a total of 
$195,121,214. 
5. COOPER RIVER SEISMIC MODIFICATION 
Location. The Cooper River Seismic Project is located in 
Berkeley County, South Carolina, about 50 miles north of 
Charleston, South Carolina. 
Existing project. The Santee-Cooper Project was, 
constructed in the early 1940's using the latest state-of-the-art 
design for that time. The project is currently licensed by the 
Federal Energy Regulatory Commission (FERC) as project 
No. 199. The FERC requires that the project receive 
independent inspections at least once every five years. It was 
during the 1977 inspection that the seismic deficiency of both 
the West and North Dams was noted. This was confirmed 
again in the 1982 inspection. As a result of studying the 
possible consequences of the loss of both dams, the S.C. 
Congressional Delegation introduced legislation which was 
approved in the 1983 Supplemental Appropriations Act to 
provide $2 million for design and $20 million for construction 
of remedial measures. The design and construction 
responsibility was assigned to the U.S. Army Corps of 
Engineers. The Corps began to study various alternatives to 
provide remedial measures for the liquifiable foundation of the 
West Dam in August 1983. 
Current estimated cost of the project is $22,000,000, all 
Federal. 
Local cooperation. None required. 
Condition at end of fiscal year. In June 1986, a 
conceptual design was submitted to FERC for approval and 
was subsequently rejected by FERC. By the end of FY 86, 
another conceptual design was submitted to FERC, and this 
time was approved. Currently, a preliminary design is 
underway with borrow area exploration and dewatering design 
the major work items. This project could be ready for contract 
award at the end of Fiscal Year 1987. 
6. FOLLY RIVER, S.C. 
Location. The project begins in Folly River and Folly 
Creek north of the Town of Folly Beach and follows a 
southwesterly course into the Atlantic Ocean. (See National 
Ocean Survey Chart No. 11521.) 
Existing project. The project provides: an entrance 
channel, eleven feet deep by 100 feet wide extending from the 
Stono River one mile through the ocean bar; a channel within 
Folly River nine feet deep and 80 feet wide, extending three 
miles downstream from U.S. Highway 171 to the confluence 
of Folly and Stono Rivers; and a channel within Folly Creek 
nine feet deep by 80 feet wide extending three miles 
downstream from Highway 171 to the confluence with Folly 
River. 
Local cooperation. Requirements fully satisfied. 
Operations and results during fiscal year. 
Maintenance: Maintenance dredging was performed (a) in the 
entrance bar by the sidecaster dredge, Merritt, removing 34,867 
cubic yards at a cost of $145,625, (b) costs on Folly River for 
FY 1985 of $153,189. Condition and operations studies, 
water control management, engineering and design, and 
supervision nd administration costs were $26,977. 
Condition at end of fiscal year. The existing project 
was completed in FY 1979. Federal costs for the existing 
project to date have been $337,736 for new work and 
$1,170,479 for maintenance, a total of $1,508,215. 
7. GEORGETOWN HARBOR, S.C. 
Location. The harbor is located on the coast of South 
Carolina 50 miles northeast of Charleston Harbor and 90 miles 
southwest of the entrance to Cape Fear River, North Carolina. 
(See National Ocean Survey Chart No. 11532.) 
Previous projects. For further details see page 1806 of 
Annual Report for 1915; page 549 of Annual Report for 1938; 
and page 442 of Annual Report for 1944. 
Existing project. The authorizations provide for a 
channel 27 feet deep with varying widths of 600 feet to 400 
feet from the Atlantic Ocean to and including a turning basin 
at the U.S. Highway 17 bridge over Sampit River, with a side 
channel 2,400 feet long and not less than 200 feet wide leading 
to a turning basin at the upper end of the built-up portion of 
the city waterfront, a total of 17.9 miles. The project also 
provides for the continued maintenance to a depth of 18 feet 
7-4

CHARLESTON, S.C., DISTRICT 
and a width of 400 feet for the bypassed portion of Sampit 
River opposite the City of Georgetown. (See table at end of 
chapter for acts authorizing existing project.) 
Local cooperation. Fully satisfied. 
Terminal facilities. Terminal facilities at the Port of 
Georgetown, suitable for oceangoing vessels, consist of one 
marginal concrete pier and one of creosoted-timber 
construction. For intracoastal waterway traffic there are a 
number of smaller wharves and landings along the Georgetown 
waterfront on the old channel. For further details, see Port 
Series No. 13, 1980, Corps of Engineers. 
Operations and results during fiscal year. 
Maintenance: Maintenance dredging was performed in the 
Sampit River from October 1985 - January 1986 and June - 
September 1986 removing a total of 1,761,000 cubic yards of 
material at a cost of $2,292,745. Contract dike management 
costs were $637,314. Water control management, engineering 
and design and supervision and administration costs were 
$333,907. 
Condition at end of fiscal year. The existing project 
was completed in 1951. The jetties were completed in 1903 - 
04. Federal costs for the existing project to date have been 
$4,615,903 for new work and $42,831,267 for maintenance, a 
total of $47,447,170. 
8. LITTLE RIVER INLET, N.C. AND S.C. 
Location. The project is located near the North Carolina - 
South Carolina state line. Little River enters the Atlantic 
Ocean at Little River Inlet at the state line and affords the only 
connection between the Atlantic Intracoastal Waterway and the 
ocean along 68 miles of coastline from Shallotte, N.C. to 
Georgetown, S.C. (See National Ocean Survey Chart No. 
11535.) 
Existing project. The project provides for an entrance 
channel twelve by 300 feet across the ocean bar; thence a ten 
by 90-foot inner channel to the Atlantic Intracoastal Waterway. 
The entrance channel is stabilized by jetties extending seaward 
3,200 feet and 3,000 feet long on the north and south sides of 
the inlet, respectively. 
Emergency dredging on an annual basis was authorized by 
the Water Resources Act of 1974. Previous work was done 
under the authority of the River and Harbor Act of 1945, 
Section 3, P.L. 79-14. 
Local cooperation. Requirements fully satisfied. 
Terminal facilities. There are eight marinas, numerous 
private docks, and several public boat ramps located in or near 
Little River. It is expected that existing facilities will expand 
and new ones will be added as demands for services exceed 
current capacity. 
Operations and results during fiscal year. New 
work: Costs of $437 were incurred. Maintenance: A 5-year 
monitoring program was initiated in 1981 to provide 
information for management of the project and to determine 
the effect of the project on nearby coastal areas. Charleston 
District collects the data and Coastal Engineering Research 
Center (CERC) performs data analysis and interpretation. 
Following conclusion of the initial 5-year monitoring plan 
(February 1986), CERC presented results of their preliminary 
analysis to SAC and SAD at a meeting in Charleston on 8 
April 1986. The data indicated that coastal processes in the 
vicinity of the inlet have not reached an equilibrium condition 
and recommended continued monitoring at a reduced level. 
Condition and operation studies, water control management, 
and supervision and administration costs were $94,771. 
Condition at end of fiscal year. The initial 
construction contract was awarded 14 January 1981. The 
project was completed in FY 1984. Federal costs for the 
existing project were $17,037,428 for new work and 
$2,221,216 for maintenance, a total of $19,258,644. 
9. MURRELLS INLET, S.C. 
Location. The project is located on the coast of South 
Carolina, in Georgetown County, about 13 miles southwest of 
the City of Myrtle Beach. The inlet is the ocean entrance 
through a barrier beach to several tidal streams in the Murrells 
Inlet-Garden City estuarine area. (See National Ocean Survey 
Chart No. 11535.) 
Existing project. The project provides for an entrance 
channel twelve by 300 feet across the seaward bar; thence a ten 
by 90-foot inner channel to a turning basin at the old Army 
crashboat dock. The entrance channel will be stabilized by 
ocean jetties extending seaward 3,445 feet and 3,319 feet on 
the north and south sides of the inlet, respectively. The 
recreational project includes a walkway on the south jetty 
with access road and parking area. Emergency dredging on an 
annual basis was authorized by the Water Resources Act of 
1974. Previous work was done under the authority of the 
River and Harbor Act of 1945, Section 3, P.L. 79-14. 
Local cooperation. A letter of intent to provide local 
cooperation dated 4 November 1975 has been received from the 
Georgetown County Board of Commissioners. Local interests 
have met their responsibilities to date. 
7-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Terminal facilities. There are five marinas and 
numerous private docks located about the Murrells Inlet 
Harbor. There are several public boat ramps in the area. 
Facilities are expected to be expanded and new ones added as 
demands for services outstrip capacity. 
Operations and results during fiscal year. New 
Work: Costs of $-24 were incurred. Maintenance: No 
maintenance dredging performed. A monitoring program was 
initiated in April 1978 to provide site specific information for 
proper management of the project and to provide data on 
coastal response to the project. Charleston District collects 
most of the data and Coastal Engineering Research Center 
(CERC) performs data analysis and interpretation. The 
monitoring program has been adjusted several times based on 
CERC recommendations. Currently the program includes 
daily littoral environmental observations (LEO), annual aerial 
photography, jetty surveys and site inspections, semi-annual 
surveys of beaches and the deposition basis. Channel surveys 
are not scheduled but are conducted on an "as needed" basis. 
Results of the monitoring program have led to 
recommendations for dredging the deposition basin, 
nourishment of a reach of eroded beach at North Litchfield 
Beach and erosion protection of a section of the south jetty 
sand dike. This maintenance work is scheduled for completion 
during FY 1987. Condition and operation studies, water 
control management costs and supervision and administration 
costs were $103,438. 
Condition at end of fiscal year. The existing project 
was completed in 1981. Federal costs for the existing project 
to date have been $13,407,123 for new work and $1,088,770 
for maintenance, a total of $14,495,893. 
10. PORT ROYAL HARBOR, S.C. 
Location. The harbor is located on the coast of South 
Carolina 47 miles southwest of Charleston Harbor and 23 
miles northeast of Savannah River, Georgia. (See National 
Ocean Survey Chart No. 11516.) 
Existing project. The authorized project provides for a 
channel from the ocean through Port Royal Sound to Port 
Royal, South Carolina, 27 feet deep and 500 feet wide across 
the ocean bar and in Port Royal Sound for approximately 12.7 
miles, thence 24 feet deep and 300 feet wide in Beaufort River 
and Battery Creek for approximately 8.3 miles to and including 
a turning basin 27 feet deep and 600 feet wide opposite the 
wharf of the South Carolina State Ports Authority. (See the 
table at the end of the chapter for acts authorizing the existing 
project.) 
Local cooperation. Requirements fully satisfied. 
Terminal facilities. The South Carolina State Ports 
Authority constructed a marginal concrete wharf and operates 
modemrn terminal facilities which are considered adequate for 
present commerce of the port. 
Operations and results during fiscal year. 
Maintenance: Maintenance dredging of the entrance channel 
was performed in August and September 1986 removing 
872,895 cubic yards of material at a cost of $768,800. 
Condition and operations studies, water quality management, 
engineering and design and supervision and administration 
costs were $127,386. 
Condition at end of fiscal year. The existing project 
was completed in 1959. Federal costs for the existing project 
to date have been $1,786,100 for new work and $6,806,408 for 
maintenance, a total of $8,592,508. 
11. SHIPYARD RIVER, S.C. 
Location. This waterway is a tidal tributary of Charleston 
Harbor, South Carolina. It has its source about one-half mile 
below the U.S. Naval Base, whence it flows southerly about 
three miles and empties into the Cooper River about threefourths 
mile above Drum Island. (See National Ocean Survey 
Chart No. 11524.) 
Previous projects. For details, see page 610 of Annual 
Report for 1932 and page 463 of Annual Report for 1944. 
Existing project. The authorized project provides for a 
channel 30 feet deep from Cooper River to Macalloy 
Corporation's plant, including two turning basins, one 
opposite Gulf Oil Corporation Terminal and another at the 
upper end of project. (See table at end of chapter for acts 
authorizing existing project.) 
Local cooperation. Requirements fully satisfied. 
Terminal facilities. In the lower three-quarters of a 
mile of the channel are large marginal wharves of the Gulf Oil 
Corporation and Shipyard River Terminal Company. These 
wharves accommodate deep-draft, oceangoing vessels for 
handling petroleum products, coal and fertilizer materials. In 
the upper channel is Macalloy Corporation's wharf for 
handling ores. For further details see Port Series No. 13, 
1980, Corps of Engineers. 
Operations and results during fiscal year. 
Maintenance: Maintenance diking costs of $86,018 were 
incurred for material removed during FY 1986. Condition and 
operations studies, water control management, supervision and 
administration, and engineering and design costs were $21,682. 
7-6

CHARLESTON, S.C., DISTRICT 
Condition at end of fiscal year. The existing project 
was completed in 1951. Federal costs under the existing 
project to date have been $487,824 for new work and 
$8,887,384 for maintenance for a total of $9,375,208. 
12. TOWN CREEK, S.C. 
Location. Town Creek Channel begins at the AIWW 
directly south of the town of McClellanville in Charleston 
County, S.C. The channel follows Five Fathom Creek in a 
southerly direction to the Atlantic Ocean. (See National Ocean 
Survey Chart No. 11531.) 
Existing project. The project provides a channel ten feet 
deep by 80 feet wide from the AIWW to the mouth of Five 
Fathom Creek, a distance of 6.2 miles. The project includes 
an entrance channel twelve feet deep by 100 feet wide across 
the ocean bar, a distance of 4.0 miles. (See table at end of 
chapter for acts authorizing existing projects.) 
Local cooperation. Requirements fully satisfied. 
Operations and results during fiscal year. 
Maintenance: Maintenance dredging performed by the 
Schweizer resulted in costs of $493,155. Condition and 
operations studies, water control management, engineering and 
design, supervision and administration costs were $32,087. 
Condition at end of fiscal year. The existing project 
was completed in 1975. Federal costs under the existing 
project to date have been $219,521 for new work and 
$2,214,394 for maintenance, a total of $2,433,915. 
13. RECONNAISSANCE AND CONDITION 
SURVEYS 
Costs of $1,712 were incurred for condition surveys, all on 
Waccamaw River, S.C. 
14. OTHER AUTHORIZED NAVIGATION 
REPORTS 
(See Table 7-C.) 
15. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation Work Under Special Authorization Pursuant to 
Section 107, Public Law 86-645, as amended 
(Preauthorization) and Section 111, Public Law 90-433, as 
amended. (See Table 7-D.) 
Snagging and clearing for navigation (Sec. 3 of 1934 River 
and Harbor Act, Public Law 14, 79th Congress.) None 
BEACH EROSION 
16. OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
(See Table 7-E.) 
FLOOD CONTROL 
17. EAGLE CREEK, S.C. 
Location. The Eagle Creek Project is located entirely 
within the limits of Dorchester County, South Carolina. The 
creek flows from its headwaters in the subdivisions near 
Summerville to the Ashley River. 
Existing project. The authorized project consists of 
clearing and channel excavation of approximately four miles of 
Chandler Bridge Creek and Eagle Creek. The project was 
authorized under general authority contained in Section 205 of 
the 1948 Flood Control Act, as amended. 
Local cooperation. Local interests must provide lands, 
easements, rights-of-way, utility relocations and alterations and 
highway bridge alterations necessary for construction; hold and 
save the United States free from damages; maintain and operate 
the project after completion; prevent future encroachments; 
notify affected interests annually that improvement will not 
provide complete flood protection; and prevent unwise future 
flood plain development. 
Operations and results during fiscal year. 
Contract was awarded on 28 September 1983 in the amount of 
$1,245,063. Construction period was 646 calendar days. 
Work on the Eagle Creek Project was completed in December 
1985. Upon completion and acceptance of the work, 
responsibility for operating and maintaining the project was 
turned over to the local sponsor. 
Condition at end of fiscal year. Project included in 
Completed Flood Control Projects Inventory for Inspection. 
18. SCOTTS CREEK, S.C. 
Location. Scotts Creek is located entirely within the 
limits of Newberry County, South Carolina. The authorized 
project is located within the corporate limits of the City of 
Newberry, South Carolina. 
7-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Existing Project. The authorized project consists of 
channel excavation and bank stabilization of 1.05 miles of the 
creek. The project extends from approximately 500 feet 
downstream of the crossing of O'Neal Street to the crossing of 
Nance Street. The project was authorized on 14 November 
1975 under general authorities contained in Section 205 of the 
1948 Flood Control Act, as amended. 
Local cooperation. Local interests must provide lands, 
easements, rights-of-way, utility relocations, highway bridge 
alterations necessary for construction; hold and save the United 
States free from damages; maintain and operate the project after 
completion; prevent future encroachments; notify affected 
interests annually that improvements will not provide 
complete flood protection; and prevent unwise future flood 
plain development 
Operations and results during fiscal year. A 
contract was awarded on 14 May 1986 in the amount of 
$334,584.40. The construction period for this contract is 270 
calendar days. At the close of the fiscal year, the contractor 
had earned $57,000. 
Condition at the end of fiscal year. The project was 
approximately 20% complete when a severe storm event 
occurred. This event caused substantial amounts of damage to 
all works installed at the time and generated shoaling in the 
channel. Work was stopped after the event, while Engineering 
Division could evaluate the impact of the storm and revise the 
plans and specifications in view of the new configuration the 
stream assumed as a result of the storm. 
19. COOPER RIVER, POMPION HILL 
CHAPEL, S.C. 
Location. This project is located entirely within Berkeley 
County, South Carolina, near the city of Charleston. 
Existing project. The authorized project consists of 
bank stabilization of approximately 200 feet of bank on the 
East Branch of the Cooper River. The project is adjacent to 
the Pompion Hill Chapel. The project was authorized on 23 
July 1986 under general authorities contained in Section 14 of 
the 1946 Flood Control Act, as amended. 
Local cooperation. Local interests must provide lands, 
easements, rights-of-way as necessary for construction; hold 
and save the United States free from damages; maintain and 
operate the project after completion; and prevent future 
encroachments. 
Operations and results during fiscal year. A 
contract was awarded on 24 September 1986 in the amount of 
$169,950.00. The construction period for this contract is 75 
calendar days. The contractor has not started work prior to the 
close of the fiscal year. 
Condition at the end of the fiscal year. No work 
has begun prior to the end of the fiscal year. 
20. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
To determine the extent of compliance with approved 
regulations for maintenance and operation, inspections were 
made of the following projects during the period: Eagle Creek, 
S.C., Sawmill Branch, S.C. and Cow Castle Creek, S.C. The 
following projects will be inspected during FY 87: Cowpens 
Swamp, S.C., Crabtree Swamp, S.C., Gapway Swamp, S.C., 
Simpson Creek, S.C., Todd Swamp, S.C., Buck Creek, S.C. 
and N.C., Edisto River, S.C., Shot Pouch Creek, S.C., 
Turkey Creek, S.C., Kingstree Branch, S.C., and Wilson 
Branch, S.C. Responsible local officials were advised of 
inadequacies in maintenance and operation on local flood 
protection works when appropriate. Cost for the period was 
$8,238. 
21. OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
(See Table 7-F.) 
22. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (Preauthorization). 
(See Table 7-G.) 
Emergency Flood Control Activities - Repair, Flood 
Fighting and Rescue Work (Public Law 99, 84th Congress, 
and Antecedent Legislation). 
(See Table 7-G.) 
Federal costs for FY 1985 were $169,405 for Flood Control 
and Coastal Emergencies and $184,717 for the National 
Emergency Preparedness Program. 
GENERAL INVESTIGATIONS 
23. ACTIVE INVESTIGATIONS 
See Table 7-H which covers: Surveys, Collections, and 
Study of Basic Data, and Research and Development 
Activities. 
7-8

CHARLESTON, S.C, DISTRICT 
TABLE 7-A COST AND FINANCIAL STATEMENT 
See 
Sect. Total Cost to 
in Text Project 
1 Aquatic Plant 
Control, SC 
(Regular Funds) 
(Contributed Funds) 
2 Atlantic Intracoastal 
Waterway 
Between Norfolk, 
Va. and the St. 
Johns River, FL 
3 Charleston Harbor, 
SC 
4 Cooper River, 
Charleston Harbor, 
SC 
5 Cooper River Seismic 
Modification, Chas Hbr, 
SC 
6 Folly River, SC 
7 Georgetown Harbor, 
SC 
8 Little River Inlet, 
NC and SC 
(RegularFunds) 
(Contributed Funds) 
Funding FY 83 FY 84 FY 85 FY 86 
New Work: 
Approp. 186,000 196,000 658,000 638,000 
Cost 190,974 193,631 657,623 585,625 
Approp. -- -- -- -- 
Cost -- -- -- -- 
New Work: 
Approp. -- -- -- -- 
Cost -- -- -- -- 
Maint: 
Approp. 1,742,000 2,055,000 3,224,700 3,024,000 
Cost 2,109,254 2,099,453 3,251,183 3,080,530 
New Work: 
Approp. -- -- -- -- 
Cost -- -- -- -- 
Maint: 
Approp. 3,921,200 4,796,500 5,366,000 4,476,000 
Cost 2,710,142 6,994,476 5,201,014 4,575,020 
New Work: 
Approp. 26,563,000 11,270,000 12,910,000 4,700,000 
Cost 29,835,958 11,657,195 11,336,085 5,804,764 
Maint: 
Approp. 295,000 480,000 2,556,000 2,948,000 
Cost 85,345 511,898 1,839,765 3,349,732 
New Work: 
Approp. 100,000 1,300,000 900,000 198,000 
Cost 39,925 1,174,744 894,513 233,086 
Maint: 
Approp. -- -- -- -- 
Cost -- -- -- -- 
New Work: 
Approp. -- -- -- -- 
Cost -- -- -- -- 
Maint: 
Approp. 152,000 110,000 259,000 334,000 
Cost 20,776 250,173 257,359 325,791 
New Work: 
Approp. -- -- -- -- 
Cost -- -- -- -- 
Maint: 
Approp. 1,315,400 1,945,000 1,796,500 3,242,000 
Cost 1,490,161 2,495,612 1,814,224 3,263,966 
New Work: 
Approp. 5,800,000 331,000 -- -33,000 
Cost 5,300,996 863,027 -29,255 437 
Maint: 
Approp. 585,000 -180,000 78,552 87,000 
Cost 24,988 344,186 124,428 94,771 
New Work: 
Approp. 640,000 -- 31,920 0 
Cost 499,994 140,000 31,927 0 
Sept. 30,1986 
2,167,605 
2,112,450 
52,028 
52,028 
7,455,378 1 
7,455,378 1 
45,092,004 2 
45,054,642 2 
10,165,564 3 
10,165,564 3 
91,280,587 4 
91,115,055 4 
191,482,583 
189,334,474 
6,279,000 
5,786,740 
2,498,000 
2,341,918 
-- 
337,736 
337,736 
1,188,000 
1,170,479 
7,061,755 5 
7,061,755 6 
42,993,780 6 
42,945,823 6 
17,037,428 
17,037,428 
2,225,676 
2,221,216 
1,521,920 
1,521,920 
7-8

TABLE 7-A (Cont'd) 
REPORT OF THE CHIEF OF ENGINEERS, US. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Sect. Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30,1986 
9 Murrells Inlet, SC 
(Regular Funds) 
(Contributed Funds) 
10 Port Royal Harbor, 
SC 
11 Shipyard River, 
SC 
12 Town Creek, SC 
(Regular Funds) 
(Contributed Funds) 
17 Eagle Creek, SC 
18 Scott's Creek, SC 
19 Cooper River, Pompion 
Hill Chapel, SC 
New Work: 
Approp. 
Cost 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
32,452 
99,637 
12,758 
104,225 
38,647 
4,127 -24 
78,000 107,600 
83,886 103,438 
13,419,240 
13,407,123 
1,380,000 
1,379,148 
1,166,169 7 
1,155,770 7 
-- 1,786,100 
-- 1,786,100 
-- 8,000 892,000 
-- 3,814 896,186 
316,000 15,000 691,000 106,000 
65,943 420,227 707,639 107,700 
280,000 
243,580 
1,258,000 
12,222 
-- 
345,000 
420,739 
-- 
178,000 
-2,201 
--.-- 
325,000 
525,242 
114,000 166,000 -193,540 
726,549 624,586 -11,817 
-- 326,000 
-- 114,511 
-- 46,100 
-- 14,594 
6,806,408 
6,806,408 
491,974 8 
491,974 8 
8,892,192 
8,887,384 
219,521 
219,521 
8,600 
8,600 
2,229,000 
2,214,394 
1,561,832 9 
1,561,832 9 
326,000 
114,511 
46,100 
14,594 
1 Includes $109,490 for new work for previous project. 
2 Includes $69,422 for maintenance of previous projects. 
3 Includes $6,586,455 for previous projects. $3,328,349 for the 
existing project, and $250,760 forPhase Ito deepen harbor. 
4 Includes $401,989 for maintenance ofprevious projects. In 
addition, $600 for maintenance expended from contributed funds. 
5 Includes $2,445,852 for new work for previous projects. 
6 Includes $114,556 for maintenance of previous projects. 
7 Includes $67,000 accomplished under 
authority of Section 3, P.L 79-11 incurred through 
FY73. 
8 Includes $4,150 for new work on previous 
projects. 
9 Includes $1,192,914 jobs bill money. 
7-10

CHARLESTON, S.C., DISTRICT 
TABLE 7-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
R&H Act of Oct. 27, 1965 
R&H Act of Sep. 19, 1890 
R&H Act of June 13, 1902 
R&H Act of Mar. 2, 1907 
R&H Act of Mar. 2, 1907 
R&H Act of Mar. 3, 1925 
R&H Act of Mar. 3, 1925 
R&H Act of July 3, 1930 
R&H Act of Aug. 30, 1935 1 
R&H Act of Aug. 30, 1935 2 
R&H Act of Aug. 30, 1935 2 
R&H Act of Aug. 26, 1937 
R&H Act of Mar. 2, 1945 
R&H Act of June 18, 1878 
R&H Act of Aug. 8, 1917 
R&H Act of July 18, 1918 
R&H Act of Jan. 21, 1927 
AQUATIC PLANT CONTROL, SC (See Section 1 of 
text.) Provides for control and progressive eradication 
of water hyacinth, alligatorweed, Eurasian watermilfoil 
and other obnoxious aquatic plant growths 
from navigable waters, tributary streams, connecting 
channels, and other allied waters of the U.S., in combined 
interest of navigation, flood control, drainage, agriculture, 
fish and wildlife conservation, public health and related 
purposes, including continued research for development 
of most effective and economic control measures in 
cooperation with other Federal and state agencies. 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA., AND ST. JOHNS RIVER, FL. 
(See Section 2 of text.) 
Channel from Minim Creek to Winyah Bah. 
Channel from Charleston to a point opposite 
McClellanville. 
Branch channel to McClellanville. 
Extending the channel to Minim Creek, thence 
through the Esterville-Minim Canal to Winyah Bay. 
Cut across the Santee Delta at Four Mile Creek. 
Widening and deepening the waterway from 
Charleston to Beaufort. 
A waterway eight feet deep and 75 feet wide from 
Cape Fear River to Winyah Bay. 
Construction of bridges across the waterway in 
Horry County, S.C. 
Cutoff between Ashepoo and Coosaw Rivers. 
Enlarging the channel from Winyah Bay to 
Charleston including the branch channel to 
McClellanville, to depth of ten feet and 
bottom width of 90 feet. 
Increasing dimensions of waterway to twelve 
feet deep and 90 feet wide. 
Anchorage Basin 125 feet wide, 335 feet long, 
twelve feet deep, near Myrtle Beach, S.C. 4 
CHARLESTON HARBOR, S.C. 
(See Section 3 of text.) 
2 jetties. s 
Increase in depth to 30 feet with width of 500 feet 
between the jetties and 1,000 feet seaward thereof. 
The 40-foot channel to the Naval Base. 
Act provided that the 40-foot channel should not be 
undertaken "until the proposed new drydocks at 
this navy yard, carrying a depth of 40 feet of water 
over the blocks, has been authorized." This dock 
was authorized in the Naval Appropriations Act 
approved July 1, 1918. (40 Stat. L 723). 
A 30-foot channel from the sea to Goose Creek 
via Cooper River, together with a 30-foot channel 
through Town Creek for commercial purposes. 
The act also provided that the 40-foot channel 
be prosecuted only as found necessary for 
national defense. 
Sec. 302, 1965 Rivers and Harbors Act 
(H.D. 251, 89th Cong., 1st sess.) 
Annual Report, 18 8 9 , p. 1184. 
H.D. 84, 56th Cong., 1st sess. 
and Annual Report 1900, p. 1908 
Annual Report 1903, p. 1133 
H.D. 178, 63rd Cong., 1st sess. 
H.D. 237, 68th Cong., 1st sess. 
S.D. 178, 68th Cong., 2nd sess. 
H.D. 41, 71st Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 14, 72nd Cong., 1st sess. 
H.D. 129, 72nd Cong., 1st sess. 
Rivers and Harbors Committee, 
Doc. 11, 72nd Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 6, 75th Cong., 1st seas. 3 
H.D. 327, 76th Cong., 1st sess. 
Annual Report 1878, pp. 553-572 
H.D. 288, 62nd Cong., 2nd sess. 
H.D. 1946, 64th Cong., 2nd sess. 
pt. 1, pp. 21-29, 57, 58, and 
61-63. 
H.D. 249, 69th Cong., 1st sess. 
7-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 7-B (Cont'd) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
R&H Act of Oct. 17, 1940 
R&H Act of Mar. 2, 1945 
R&H Act of Sep. 3, 1954 
R&H Act of July 14, 1960 
Water Resources Development 
Act of Oct. 22, 1976 
R&H Act of Aug. 13, 1968 
Authorized by Chief of Engrs. 
on Dec. 23, 1977 under 
authority of Section 107 
R&H Act of 1960, as amended. 
R&H Act of Aug. 5, 1886 
R&H Act of June 25, 1910 
R&H Act of Mar. 2, 1945 
R&H Act of June 30, 1948 
The 35-foot channel depth from the sea to the head 
of the project via Cooper River and Town Creek, also 
a channel in Shem Creek to Mount Pleasant, 110 feet 
wide and ten feet deep, including a turning basin at 
the upper end. 
An anchorage area 30 feet deep in the water area 
between Castle Pinckney and Fort Moultrie. 6 
Deepen the 30-foot channel north and east of 
Drum Island to 35 feet. 
Shem Creek Channel modified by extending 
1,150 feet upstream and downstream from mouth 
to Atlantic Intracoastal Waterway. 
Project is authorized for the Phase I design 
memorandum stage of Advanced Engineering 
and Design. 
COOPER RIVER, CHARLESTON, S.C. 
(ST. STEPHEN PROJECT) 
(See Section 4 of text.) 
Redivert most of the Santee River waters above 
Pinopolis Dam into the lower Santee River through 
a canal beginning at Lake Moultrie and extending 
to the Santee River in the vicinity of.SLt. Stephens, S.C. 
COOPER RIVER SEISMIC MODIFICATON, 
CHARLESTON HARBOR, S.C. 
(See Section 5 of text.) 
Install a closure structure in the diversion canal 
between Lake Marion and Lake Moultrie and 
construct such measures as necessary to improve 
the seismic stability of the Pinopolis West Dam 
on the Cooper River. 
FOLLY RIVER, S.C. 
(See Section 6 of text.) 
Consists of stable all-tide channel nine feet deep 
and 80 feet wide in Folly River and an entrance 
channel at Stono Inlet 100 feet wide and 
eleven feet deep. 
GEORGEIOWN HARBOR, S.C. 
(See Section 7 of text.) 
Jetties and earthen dike to protect south jetty. 
Previous project channel dimensions and 
training wall. 
27-foot channel from ocean, including a tuming 
basin in Sampit River. 
Cutoff and side channel in Sampit River. 
H.D. 259, 76th Cong., 1st sess. 
H.D. 156, 77th Cong., 1st sess. 
S.D. 136, 83rd Cong., 2nd sess. 
H.D. 35, 86th Cong., 1st sess. 
H.D. 436, 94th Cong., 2nd sess. 
River and Harbor Act of 1968, 
S.D. 88, 90th Cong. 
H.D. 3069, 98th Cong., 1st sess. 
Detailed Project Report 
H. Ex. Doc. 258 48th Cong., 2nd sess., 
and Annual Report 1885, pp. 1154-1170, 
and H. Ex. Doc. 117, 50th Cong., 2nd 
sess., and Annual Report 1889, 
pp. 1110-1111. 
H.D. 395, 58th Cong., 2nd sess. 
and Annual Report 1904, 
pp. 1591-1605. 
H.D. 211, 76th Cong., 1st sess. 
H.D. 21, 81st Cong., 1st sess. 
7-12

CHARLESTON, S.C., DISTRICT 
TABLE 7-B (Cont'd) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
R&H Act of 1945, Sec. 3 
Auth. by Senate Public Works 
Comm. and the House Public 
Works Comm. on Oct. 12, 1972, 
under auth. of Sec. 201, PL 
89-298, 1965 FC Act. 
Water Resources Development 
Act of 1974 
R&H Act of 1945, Sec. 3 
Auth. by the House Committee 
on Public Works on Nov. 10, 
1971, and the Senate Comm. on 
Public Works on Nov. 18, 
PL 89-298, 1965 FC Act. 
Water Resources Development 
Act of 1974 
R&H Act of Sept. 3, 1954 
R&H Act of July 25, 1912 
R&H Act of Mar. 3, 1925 
R&H Act of July 3, 1930 
R&H Act of Aug. 30, 1935 
R&H Act of Aug. 26, 1937 2 
R&H Act of Mar. 2, 1945 
LITTLE RIVER INLET, N.C. AND S.C. 
(See Section 8 of text.) 
Provides for an entrance channel twelve feet 
by 300 feet across the ocean bar; thence ten feet 
by 90-foot inner channel to the Atlantic 
Intracoastal Waterway. 
Authorized emergency dredging operations as the 
Chief of Engineers determines necessary to maintain 
channel depths sufficient to permnit free and safe 
movement of vessels until such time as the 
authorized project is constructed. 
MURRELLS INLET, S.C. 
(See Section 9 of text.) 
Provides for an entrance channel twelve feet by 
300 feet across the seaward bar, thence ten by 
90-foot inner channel to a turning basin at 
the old Army crash boat dock. 
Authorized emergency dredging operations as of 
Chief of Engineers determines necessary to maintain 
channel depths sufficient to permit free and safe 
movement of vessels until such time as the authorized 
project is constructed. 
PORT ROYAL HARBOR, S.C. 
(See Section 10 of text.) 
A channel from the ocean through Port Royal Sound 
to Port Royal, S.C.; 27 feet deep and 500 feet wide 
across the ocean bar and in Port Royal Sound for 
approximately 12.7 miles thence 24 feet deep and 
300 feet wide in Beaufort River and Battery Creek for 
approximately 8.3 miles to and including a turning 
basin 27 feet deep and 600 feet wide opposite wharf of the 
S.C. State Ports Authority. 
SHIPYARD RIVER, S.C. 
(See Section 11 of text.) 
Channel depth of 15 feet and width of 100 feet. 
Deepening of channel to 18 feet from deep water 
in Cooper River upstream 1-1/16 miles. 
Channel depths of twelve to twenty feet. 
28-feet from Cooper River to Gulf Oil Corp's 
terminal, and the deepening of the channel above 
that point to twenty feet from the depth of twelve feet 
previously authorized without local cooperation. 
Enlargement of the channel to a depth of 30 feet and 
a width of 200 feet up to the Gulf Oil Corp's terminal, 
with a turning basin 30 feet deep at the latter point. 
Extension of the existing 30-foot channel to vicinity 
of the Pittsburg Metallurgical Co. Plant, with a 
tuming basin at the upper end. 
P.L 79-14 
H.D. 362, 92nd Cong. 
H.D. 10203, 93rd Cong., 2nd sess. 
P.L 79-14 
H.D. 137, 92nd Cong. 
H.D. 10203, 93rd Cong., 2nd sess. 
River and Harbor Act, H.D. 469, 
81st Cong., 2nd sess. 
S.D. 350, 62nd Cong., 2nd sess. 
H.D. 288, 68th Cong., 1st sess. 
Rivers & Harbors Committee Doc. 
Rivers & Harbors Committee 
Doc. 43, 73rd Cong., 2nd sess. 
Rivers & Harbors Committee 
Doc. 38, 75th Cong., 1st sess. 
H.D. 93, 79th Cong., 1st sess. 
7-13

REPORT OF THE CHIEF OF ENGINEERS, US. ARMY 1986 
TABLE 7-B (Cont'd) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
TOWN CREEK, S.C. 
(See Section 12 of text.) 
Auth. by Chief of Engrs. An entrance chanel twelve feet deep by 100 feet wide Detailed Project Repoit 
on Feb. 12, 1974 under across the ocean bar a distance of 4.0 miles and a 
Auth. of Sec. 107 of channel ten feet deep by 80 feet wide from the mouth of 
R&H Act of 1960, as Five Fathom Creek to the AIWW, a distance of 6.2 miles. 
amended. 
EAGLE CREEK, S.C. 
(See Section 17 of text.) 
Auth. under Sec. 205, of the Provides for clearing and channel excavation of Detailed Project Report. 
1948 Flood Control Act, four miles of Chandler Bridge Creek and 
as amended. Eagle Creek. 
SCOTTS CREEK, SC. 
(See Section 18 of text.) 
Auth. under Sec. 205 of the Provides for clearing and channel excavation of Detailed Project Report. 
1948 Flood Control Act, 1.05 miles of channel. 
as amended. 
COOPER RIVER, POMPION HILL CHAPEL, S.C. 
(See Section 19 of text.) 
Auth. under Sec. 14 of the Provides for bank protection of the Pompion Hill Chapel. Letter Report 
1946 Flood Control Act, 
as amended. 
1 Included in Public Works Administration Program 
September 6, 1933. 
2 Included in Emergency Relief Administration 
Program May 28, 1935. 
3 Contains latest published maps. 
4 Inactive. 
5 Completed under previous projects. 
6 For national defense. 
7-14

CHARLESTON, S.C., DISTRICT 
TABLE 7-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report 
See Annual Operation & 
Project Report For Construction Maintenance 
Adams Creek, S.C. 1 1978 $125,697 $ 18,280 
Aquatic Plant Control, N.C. and S.C. 1 5 1968 '379,680 - - 
Archers Creek, S.C. 1914 20,646 - - 
Ashley River, S.C. 1 1955 260,996 530,852 
Edisto River, S.C. 1 2 1938 33,103 900 
Great Pee Dee River, S.C. 1 3 1950 183,712 269,673 
Jeremy Creek, S.C. 1 1985 49,987 3,000 
Mingo Creek, S.C. 1 2 1950 29,050 7,150 
Lynches River and Clark Creek, S.C. 1 1982 9,500 84,170 
Salkahatchie River, S.C. 1 2 4 1896 15,841 - - 
Santee River, N.C. and S.C. 1 1950 99,750 180,633 
Village Creek, S.C. 1985 26,500 105,116 
Waccamaw River, N.C. & S.C. 1 1978 262,814 278,170 
Wateree River, S.C. 1940 60,000 151,784 
1 Completed 4 Abandonment recommended in 1926 
2 No commerce reported (H.D. , 69th Cong., 1st session) 
3 Curtailment recommended in 1926 5 Pilot Program 
(H.D. 467, 69th Cong., 1st session) 
TABLE 7-D NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
(See Section 15 of Text) 
Study Identifications Section Fiscal Year Costs 
Calabash Creek, N.C. 107 $ 39,660 
Charleston Harbor, S.C. 111 106,268 
TABLE 7-E OTHER AUTHORIZED BEACH EROSION PROJECTS 
(See Section 16 of Text) 
For Last 
Full Report 
See Annual Operation & 
Project Report for Construction Maintenance 
Hunting Island Beach, S.C. 1984 $2,872,717 1- 
1 Excludes $1,249,336 contributed funds 
7-15

REPORT OF THE CHIEF OF ENGINEERS, US. ARMY 1986 
TABLE 7-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report 
See Annual Operation & 
Project Report For Construction Maintenance 
Buck Creek, N.C. & S.C. 1 2 1970 $298,167 -- 
Cow Castle Creek, S.C. 1 2 1985 250,000 - - 
Cowpens Swamp, S.C. 1 2 1960 18,679 -- 
Crabtree Swamp, S.C. 1 2 1969 97,000 - - 
Edisto River, S.C. 1 3 1947 6,379 -- 
Edisto River, North Fork, S.C. 1 2 1969 127,660 -- 
Edisto River, Vicinity Canadays Landing, S.C. 1 2 1958 3,160 -- 
Gapway Swamp, S.C. 1969 339,197 -- 
Kingstree Branch, Williamsburg County, S.C. 1 1978 247,242 - - 
Leith's Creek, S.C. 1 2 1982 430,951 - - 
Reddies River Lake, N.C. 1980 985,800 -- 
Reedy River, S.C. 1 3 1974 4,500 -- 
Roaring River, Wilkes County, N.C. 1 4 1978 370,000 - - 
Saluda River, S.C. 1 2 1963 99,000 -- 
Sawmill Branch, S.C. 1 2 1971 248,605 -- 
Shot Pouch Creek, Sumter Co., S.C. 1 2 1971 77,400 - - 
Simpson Creek, S.C. 1 2 1957 81,000 -- 
Todd Swamp, S.C. 1 2 1964 29,000 -- 
Turkey Creek, Sumter County, S.C. 1 2 1974 319,669 -- 
Wilson Creek, Sumter County, S.C. 1 2 1985 277,111 -- 
1 Authorized by Chief of Engineers 3 Discontinued due to lack of interest 
2 Completed 4 Phase I only 
TABLE 7-G FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Preauthorization studies (See Section 22 of Text) 
Study Identification Section Fiscal Year Costs 
Brushy Creek, Greenville, S.C. 205 33,226 
Camp Branch/Lynches Lake, Lake City, S.C. 205 63,240 
Crooked Creek, Bennettsville, S.C. 205 24,392 
Devils Ditch, Richland County, S.C. 205 25,527 
Kinley Creek, Lexington County, S.C. 205 22,583 
Lawsons Fork, Spartanburg, S.C. 205 31,704 
Sawmill Branch, S.C. 205 7,457 
Socastee Creek, Horry County, S.C. 205 73,341 
Stoop Creek, S.C. 205 17,490 
7-16

CHARLESTON, S.C., DISTRICT 
TABLE 7-H ACTIVE GENERAL INVESTIGATIONS 
ITEM FISCAL YEAR COSTS 
FLOOD DAMAGE PREVENTION STUDIES (CATEGORY 120) 
Gills Creek, S.C. $ 199,097 
Little Pee Dee & Pee Dee Rivers, N.C. & S.C. 16,797 
Sugar Creek Basin, N.C. & S.C. 38,932 
SHORELINE PROTECTION STUDIES (CATEGORY 130) 
Myrtle Beach, S.C. $ 53,912 
REVIEW OF AUTHORIZED PROJECTS (CATEGORY 160) $ 12,319 
MISCELLANEOUS ACTIVITIES (CATEGORY 170) 
Special Investigations $ 48,423 
FERC Licensing Activities 9,886 
COORDINATION STUDIES WITH OTHER AGENCIES (CATEGORY 180) 
Department of Agriculture, SCS $ 3,503 
Planning Assistance to States 77,210 
SUPPLEMENTAL PRE-AUTHORIZATION STUDIES (CATEGORY 190) 
TOTAL (CATEGORY 100) $ 460,079 
FLOOD PLAIN MGMT SERVICES (CATEGORY 250) $ 255,144 
HYDROLOGIC STUDIES (CATEGORY 260) 
Hydrologic Studies 3,083 
TOTAL (CATEGORY 200) $ 258,227 
CONTINUATION OF PLANNING AND ENGINEERING (CATEGORY 400) 
Charleston Harbor Deepening, S.C. $ 477,414 
TOTAL (CATEGORY 400) $ 477,414 
TOTAL GENERAL INVESTIGATIONS $ 1,195,720 
7-17

SAVANNAH, GA, DISTRICT * 
The District comprises drainage basins that flow into the 
Atlantic Ocean between Port Royal Sound, SC, and dumberland 
Sound, GA and FL, and includes the AtlantLc 
Intracoastal Waterway between these points. This area 
covers the headwaters of the Savannah River in southwestern 
North Carolina, a considerable portion of 
western South Cacolina, eastern Georgia, and a small portion 
of northeastern Florida. 
IMPROVEMENTS 
Navigation 
1. Altamaha, Oconee, and Ocmulgee 
Rivers, ....................... 
2. Aquatic Plant Control .......... 
3. Atlantic Intracostal Waterway 
Between Norfolk, VA, and St. Johns 
River, FL (Savannah District) .... 
4. Brunswick Harbor, GA .......... 
5. Savannah Harbor, GA .......... 
6. Savannah River Below 
Augusta, GA .................. 
7. Reconnaissance and Condition 
Surveys ...................... 
8. Other Authorized Navigation 
Projects ...................... 
9. Navigation Work Under Special 
Authorization ................. 
Beach Erosion Control 
10. Beach Erosion Control Work 
Under Special Authorization 
11. Tybee Island, GA .............. 
Flood Control 
12. Broadway Lake, Anderson County, 
SC ........................... 
13. Inspection of Completed Flood 
Control Projects ............... 
14. Other Authorized Flood Control 
Projects ...................... 
15. Flood Control Work Under Special 
Authorization ................. 
Page 
8-1 
8-2 
8-2 
8-3 
8-4 
8-5 
8-6 
8-6 
8-6 
Multiple-Purpose Projects 
Including Power 
16. Savannah River Basin, GA 
and SC ....................... 
16A. Clarks Hill Lake, GA and SC ..... 
16B. Hartwell Lake, GA and SC ....... 
16C. Richard B. Russell Dam and Lake, 
GA and SC (Formerly Trotters 
Shoals Lake, GA and SC) ....... 
17. West Point Lake, Chattahoochee 
River Basin, GA and AL ......... 
General Investigations 
18. Surveys ........................ 
19. Collection and Study of 
Basic Data .................... 
20. Research and Development ..... 
21. Continuation of Planning 
and Engineering ............... 
Tables 
8-6 Table 8-A Cost and Financial Statement ... 
Table 8-B Authorizing Legislation .... 
Table 8-C Other Authorized Navigation 
Projects ................. 
8-7 Table 8-D Other Authorized Flood Control 
Projects ................. 
8-7 Table 8-E Savannah River Basin, GA and 
SC Dams and Lakes ...... 
8-7 
Page 
8-8 
8-8 
8-8 
8-9 
8-9 
8-9 
8-10 
8-10 
8-10 
8-11 
8-12 
8-16 
8-16 
8-17 
8-7 
Navigation 
1. ALTAMAHA, OCONEE, AND 
OCMULGEE RIVERS, GA 
Location. These Rivers are entirely within the State of 
Georgia. (See National Oceanic and Atmospheric Administration 
Survey Map of Georgia, formerly U.S. 
Geological Survey map of Georgia.) For full description of 
these rivers, see page 636, Annual Report for 1932. 
Previous projects. Prior projects for the Altamaha River 
have been adopted, and expenditures made under 
them, by River and Harbor Acts of March 3, 1881, and September 
19, 1890; for the Oconee River by River and Harbor 
Acts of June 18, 1878, September 19, 1890, and March 3, 
1905; for the Ocmulgee River, by River and Harbor Acts of 
August 14, 1876, and September 19, 1890. 
For further details, see page 1815, Annual Report for 1915, 
and page 589, Annual Report for 1938. 
Existing project. The authorized project provides for an 
appropriation of $40,000 annually for the Altamaha, Oconee, 
and Ocmulgee Rivers, to maintain a 3-foot depth 
8-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
during ordinary summer low water and to gradually increase 
channel depth, so far as practicable without sacrificing the 
maintenance work. This project covers the entire Altamaha 
River (including a channel between the river and Darien, 
GA), a length of 137 miles, the lower 139 miles of the Oconee 
River, and the lower 199 miles of the Ocmulgee River. The 
Altamaha River has a mean tidal range of 6.4 feet at its mouth 
which gradually decreases to mile 33, where there is no 
perceptible tidal effect. At Doctortown, mile 59, ordinary 
floods attain a height of about 10 feet above low water, and at 
extreme floods, a height of about 15 feet above low water. 
On the Oconee River at Dublin the ordinary fluctuations 
attain a height of 22 feet, and the extreme fluctuations a 
height of 32 feet, above low water. On the Ocmulgee River at 
Macon the ordinary fluctuations attain a height of 15 feet, and 
the extreme fluctuations a height of 25 feet, above low water. 
There is no approved estimated cost for improvement or for 
maintenance. 
Published maps of these rivers are in the following documents: 
Altamaha River, House Executive Document 283, 
Fifty-first Congress, second session; Oconee River, House 
Executive Document 211, Fifty-first Congress, first session; 
Ocmulgee River, House Executive Document 215, Fifty-first 
Congress, first session; and Lower Altamaha River and 
Darien Harbor, GA, House Document 610, Seventy-seventh 
Congress, second session. (See Table 8-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Along these rivers there are 
numerous natural shore landings which are considered 
ample for existing commerce. Facilities for recreational 
boats have been constructed at several points. 
Operations and results during fiscal year. Maintenance: 
No maintenance was performed during the fiscal 
year. (See Table 8-A for Cost and Financial Statement.) 
Condition at end of fiscal year. The existing project is such 
that the percentage of completion cannot be stated. Channel 
depths have been increased by excavating rock shoals and 
sandbars, by constructing contraction and bank-protection 
works, and by closing cutoffs. Navigation has been rendered 
safer by removing obstructions. Many of the closing dams 
and contractions and bank-protection works need repairs. 
The notice of availability on the Final Environmental Statement 
appeared in the Federal Register October 21, 1977. 
To September 30, 1986, costs under the existing project 
were $60,847 for new work and 1,871,703 for maintenance, of 
which $69,356 were contributed funds, a total of $1,932,550. 
(See Table 8-A for Cost and Financial Statement.) 
2. AQUATIC PLANT CONTROL 
Location. Navigable waters, tributary streams, 
connecting channels, and other allied waters in Savannah 
District. 
Existing project. The project provides for control and progressive 
eradication of water-hyacinth, alligatorweed, Eurasian 
water milfoil, and other noxious aquatic plants from 
navigable waters, tributary streams, connecting channels, 
and other allied waters of the United States, in the combined 
interests of navigation, flood control, drainage, agriculture, 
fish and wildlife conservation, public health, and related purposes. 
The project provides for continued research for 
developing the most effective and economic control measures 
in cooperation with other Federal and State agencies in 
accordance with report of Chief of Engineers, House Document 
251,89th Congress, 1st session. The authorizing act 
provides that research and planning costs shall be borne 
fully by the United States. (See Table 8-C for Authorizing 
Legislation.) 
Local cooperation. Local interests must agree to hold the 
United States free from damages that may occur from operations 
performed in connection with this project and participate 
to the extent of 30 percent of the cost of the program. 
Requirements are being met. 
Operations and results during fiscal year. Georgia Game 
and Fish Division, Department of Natural Resources, who 
maintain surveillance of potential aquatic plant problem 
areas, reported nuisance aquatic plant infestations in Lakes 
Jackson, Blackshear, and Worth 
Actual control work under the Aquatic Plant Control Cost 
Sharing Program with the Georgia Game and Fish Division 
was initiated in FY 86 and over 800 acres were treated. Cost 
during the fiscal year was $58,950. The Final Environmental 
Statement was filed with EPA on August 6, 1979, and its 
notice of availability appeared in the Federal Register August 
17, 1979. (See Table 8-A for Cost and Financial Statement.) 
3. ATLANTIC INTRACOASTAL 
WATERWAY BETWEEN NORFOLK, 
VA, AND THE ST. JOHNS 
RIVER, FL (SAVANNAH DISTRICT) 
Location. This 161-mile section of waterway connects 
Port Royal Sound, SC, with Cumberland Sound, GA and FL 
(See NOAA charts 11489 - 11507, formerly Coast and Geodetic 
Survey Charts 838 - 841, inclusive.) 
Previous project. (Between Savannah, GA, and 
Fernandina, FL.) For details see pages 1814, 1821-1823 of 
Annual Report for 1915 and page 585 of Annual Report for 
1938. 
Existing project. The project provides for a waterway 12 
feet deep at mean low water and not less than 90 feet wide 
between Port Royal Sound, SC, and Savannah, GA; 12 feet 
deep at mean low water, with widths of 90 feet in land cuts 
and narrow streams and 150 feet in open waters between 
Savannah, GA and Cumberland Sound, GA and FL; and a 
suitable anchorage basin at Isle of Hope GA. Mean tidal 
8-2

SAVANNAH, GA, DISTRICT 
range between Port Royal, SC, and Cumberland Sound, 
GA and FL; is from 6to8 feet with fluctuations from 1.5 to 2.5 
feet, due to winds and lunar phases. (See Table 8-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Exclusive of adequate terminal facilities 
at ports of entry, this improvement serves 
numerous wharves, some of which are open to the public on 
equal terms. Facilities are considered ample for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
A contract for maintenance dredging was awarded on July 3, 
1985. As reported in the FY 85 Annual Report, some dredging 
occurred in FY 85. In FY 86 the dredge Clarendon continued 
in the South River from Oct 1 to Oct 3,1985 where it removed 
25,001 cubic yards of material. From Oct 4 to Oct 14, 1985, it 
continued dredging in Little Mud River, removing 226,000 
cubic yards. The next area was Altamaha Sound where 
70,490 cubic yards were removed from Oct 13 to Oct 23, 
1985. Also work was done in Buttermilk Sound where from 
Oct 24 thru Nov 10, 1985 the dredge pumped 182,538 cubic 
yards of disposal material. The final area under this contract 
was Jekyll Creek which was completed on Dec 2, 1985 after 
removing 420,141 cubic yards of disposal material. The 
expenditures for the dredging and pile dike removal were 
$355,595. Total cost including inspection, administration, 
and other government cost was $282,977. The government 
cost for surveys and inspection reports, and condition and 
operation studies amounted to $113,605. Total cost for the 
fiscal year amounted to $752,177. (See Table 8-A for Cost 
and Financial Statement.) 
Condition at end of fiscal year. The main channel of the 
existing project, completed in 1941, is maintained at 12 feet. 
The former main channel, now an alternate route through the 
westerly end of the south channel and northerly end of 
Wilmington River, will be maintained to a depth of 7 feet 
mean low water for traffic points north and south of Savannah 
Harbor. Relocation of the main channel from the Frederica 
to Mackay River near St. Simons Island, GA, was accomplished 
after construction of the new bridges for the Torras 
Causeway. The notice on the Final Environmental Impact 
Statement appeared in the Federal Register October 29, 1976 
Costs of the existing completed project to September 30, 
1986, were $763,599 for new work and $16,397,230 for maintenance, 
a total of $17,160,829. (See Table 8-A for Cost and 
Financial Statement.) 
4. BRUNSWICK HARBOR, GA 
Location. The harbor entrance is 70 statute miles south of 
the entrance to Savannah Harbor, GA, and 25 statute miles 
north of the entrance to Fernandina Harbor, FL. (See NOAA 
Chart 11215, formerly Coast and Geodetic Survey Chart 
447.) 
Previous projects. For details see page 1818 of Annual 
Report for 1915 and page 591 of Annual Report for 1938. 
Existing project. The project provides for a stone jetty 
4,350 feet long at the entrance to East River and the following 
channels: 32 feet deep and 500 feet wide across the bar; 30 
feet deep and 400 feet wide through St. Simons Sound, 
Brunswick River, and East River to the foot of Second 
Avenue; 30 feet deep and 300 feet wide in Turtle River to the 
Allied Chemical Co. wharf, formerly the Atlantic Refining 
Co.; 27 feet deep and 350 feet wide in East River from Second 
Avenue to its confluence with Academy Creek; 24 feet deep 
and 150 feet wide in Academy Creek; a channel in Back River 
20 feet deep and 150 feet wide from St. Simons Sound to the 
mouth of Mill Creek; and a channel in Terry Creek 10 feet 
deep and 80 feet wide from its mouth to a point immediately 
above the wharf of the former Glynn Canning Company. All 
depths refer to mean low water. Mean tidal range on the bar is 
6.5 feet, at the city of Brunswick 7.3, and 7.6 feet at the upper 
end of the harbor. For further details see Annual Report for 
1962. 
Local cooperation. Complied with to date. 
Terminal facilities. Eighteen wharves and piers, almost all 
privately owned, have a berthing space of 7,530 linear feet. 
The Port of Brunswick and the State of Georgia have a transit 
shed and modern docks with 1,640 feet of berthing space 
(three general cargo berths) on East River. For furtherdetails 
see Port Series No. 14, Corps of Engineers (revised 1982). 
Operations and results during fiscal year. Maintenance: 
A total of 2,553,009 cubic yards of disposal material was 
removed by dredges in FY 86. From 1 Dec 85 thru 2 Jan 86 the 
government dredge McFarland removed 534,253 cubic yards 
from the entrance channel. The dredge Stuyvesant also 
worked in the entrance channel from 15 Feb 86 to 28 Mar 86 
removing a total of 1,426,591 cubic yards of material. From 1 
May 86 thru 22 May 86 the dredge Cherokee dredged 
1,426,591 cubic yards from the East River and the dredge Jim 
Bean removed 282,047 cubic yards between 22 May 86 and 
23 Jun 86 in the Turtle River. 
Expenditures for surveys totaled $184,784, for dikes and 
dredging, and $7,148,896for S&I. Other expenditures included 
$33,115 for depot operations and project management totaling 
$62,185; $390,003 for E&D; and $108,207 for mosquito 
control. 
8-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Total operation and maintenance cost amounted 
to $8,110,481. (See Table 8-A for Cost and Financial Statement.) 
Condition at end of fiscal year. The existing project was 
completed in December 1960. General condition of the harbor 
works is satisfactory, providing maintenance dredging 
continues. The notice on the Final Environmental Impact 
Statement appeared in the Federal Register October 3,1975. 
Authorized depths were maintained throughout the fiscal 
year. 
Costs for existing completed project to September 30, 
1986, were $58,809,666, of which $3,929,968 was for new 
work and $54,879,698 for maintenance. (See Table 8-A for 
Cost and Financial Statement.) 
5. SAVANNAH HARBOR, GA 
Location. Harbor entrance is 75 statute miles south of 
Charleston Harbor, SC, and 70 statute miles north of Brunswick 
Harbor, GA (See NOAA Chart 11512, formerly Coast 
and Geodetic Survey Chart 440.) 
Previous projects. For details see page 1810 of Annual 
Report for 1915 and page 578 of Annual Report for 1938. 
Existing project. The project provides for a channel 40 feet 
deep and 600 feet wide across the ocean bar about 7.0 miles; 
38 feet deep and 500 feet wide to the Seaboard Coast Line 
terminal; 38 feet deep and 400 feet wide to the vicinity of 
Garden City (Georgia Ports Authority terminal); and 36 feet 
deep and 400 feet wide to the vicinity of Savannah Sugar 
Refinery of Savannah Foods and Industries, Inc. about 22.6 
miles; and 30 feet deep and 200 feet wide to a point 1,500 feet 
below the Atlantic Coastal Highway bridge, about 1.5 miles, a 
total length of 31.1 miles; Fig Island and Marsh Island Turning 
Basins 34 feet deep by 900 feet wide by 1,000 feet long in 
the vicinity of the Seaboard Coast Line terminal, and American 
Oil Company terminal; Kings Island Turning basin 38 
feet deep by 1,500 feet wide by 1,600 feet long in the vicinity 
of Garden City terminal of the Georgia Ports Authority; 
Argyle Island and Port Wentworth Turning Basins 30 feet 
deep by 600 feet wide by 600 feet long near Savannah Sugar 
Refinery terminal and at the extreme upper limit of the 
project near Continental Can Company terminal; and a 1,200 
foot long by 1,050 foot wide by 40 foot deep Oyster Bed 
Island Turning Basin in the vicinity of Georgia Ports Authority 
LASH facility. The project also provides for sediment control 
works consisting of a tide gate structure across Back River; a 
sediment basin 40 feet deep, 600 feet wide, about 2 miles 
long, with an entrance channel 38 to 40 feet deep and 300 feet 
wide; adrainage canal across Argyle Island 15 feet deep and 
300 feet wide; control works and canals for supplying fresh 
water to the Savannah National Wildlife Refuge; and facilities 
to mitigate damages to presently improved areas other than 
refuge lands. Mean range of tide is 7.9 feet at the upper end of 
the harbor and 6.9 feet at the lower end. Extreme ranges are 
about 11.1 and 10.7 feet, respectively. 
Local cooperation. Local interests must provide suitable 
disposal areas and retaining dikes for construction and 
future maintenance of the project. The Chatham County 
Board of Commissioners, as local assurers, have met all 
requirements to date. 
Terminal facilities. Sixty-one piers and wharves 
adequately serve existing waterborne commerce of the port. 
These facilities, with use of dolphins, have a com-bined berthing 
space of 46,930 linear feet with water depths alongside 
ranging up to 38 feet at mean low water. Included in the 
berthing space are six container berths with 271 acres of 
handling area. All have railway and highway connections. 
LASH facilities are located at the entrance to the harbor and 
have depths ranging up to 38 feet mean low water. The 
berthing space of LASH facilities is included in the above 
combined berthing space. For further details, see Port Series 
No. 14, Corps of Engineers (revised 1982) and Annual Report 
for 1962. 
Maintenance: Three dredges operated in the harbor in FY 
86. From 6 Mar 86 thru 8 Jun 86 the Cherokee removed 
516,621 cubic yards between stations 100+730 and 82+750. 
The Hendry #5 worked between stations 24+160 and 40+000 
as well as the sediment basin to remove the bulk of the 
material in the harbor which totaled 3,984,560 cubic yards. 
The third dredge, Atkinson, from 10 Aug 86 thru 31 Sep 86 
removed 361,000 cubic yards between stations 79+000 and 
40+000. We received credits of 366,689 on one 1984 contract 
and one 1985 contract. Also payment of work completed in 
FY 85, was not actually paid until 1986. Total cubic yardage in 
FY 86 was 4,862,181. 
8-4

SAVANNAH, GA, DISTRICT 
Mosquito control in disposal areas cost $241,518. (Credits 
received from agitation dredging of private shipping interest 
slips amounted to $126,225.) Distribution of 
Engineer Yard cost amounted to $116,268. Condition surveys, 
water quality monitoring, water and air pollution studies, 
environmental studies, testing, inspection and reports, 
tidegate operation, and government supervision and administration 
costs were $1,191,097. Credits of $166,690 and 
$199,999 were received for dredging contracts on the upper 
channel bend wideners and lower channel respectively. Net 
dredging expenditures were 2,222,023. Total operation and 
maintenance costs for the fiscal year amounted to $3,528,413. 
(See Table 8-A for Cost and Financial Statement.) 
Condition at end of fiscal year. Training walls, jetties, and 
other structures are in fair condition. Authorized channels 
are maintained by a planned dredging program with work at 
critical areas when necessary. The notice on the Final Environmental 
Impact Statement appeared in the Federal Register 
June 25, 1976. Notices of availability on two Final Supplements 
to the Environmental Impact Statement appeared in 
the Federal Register September 25, 1978, and January 8, 
1980. 
Costs of existing project to September 30, 1986, were 
$181,362,982, of which $38,925,359 was for new work and 
$142,437,623 for maintenance. (See Table 8-A for Cost and 
Financial Statement.) 
6. SAVANNAH RIVER BELOW 
AUGUSTA, GA 
Location. Savannah River is formed by the confluence of 
the Tugaloo and Seneca Rivers on the boundary line 
between South Carolina and Georgia. It flows southeast 314 
miles, forming the boundary line between the two states, and 
empties into the Atlantic Ocean 16.6 miles below Savannah, 
GA (See NOAA Charts 11514 and 11515, formerly Geological 
Survey maps of South Carolina and Georgia.) 
Previous project. For details see page 1813 of Annual 
Report for 1915 and page 581 of Annual Report for 1938. 
Existing project. The authorized project provides for a 
channel 9 feet deep and 90 feet wide (at ordinary summer 
flow of 5,800 second-feet at Augusta, GA) from the upper 
end of Savannah Harbor to the head of navigation at 
Augusta, 3 miles above Fifth Street Bridge, a total distance of 
about 181 miles. A lock and dam is located approximately 
15 miles below the upper limit of the project at New 
Savannah Bluff. Improvement is to be obtained by 
construction of contraction works, closure of cutoffs, bank 
protection, dredging, removal of snags, overhanging 
trees and wrecks, and open-river regulation. Mean tidal variation 
at the mouth of the river is 7 feet. Freshet variation above 
the normal pool level (elevation 114.5 mean sea level) of New 
Savannah Bluff Lock and Dam at miles 187 is ordinarily about 
13 feet with an extreme of 34 feet. Latest approved project 
cost estimate for providing a 9-foot channel (September 
1963) is $6,576,000 exclusive of amounts expended on previous 
projects. For further details see Annual Report for 1962. 
Local cooperation. Complied with to date. 
Terminal facilities. The only water terminals served by this 
improvement are at Augusta, Sylvania, and at or near Savannah. 
Augusta provided a municipal dock valued at $50,000 
and Georgia Ports Authority constructed a State port at 
Augusta, GA, costing about $418,000. These facilities were 
expanded in 1965 at an additional cost of about $250,000. 
These are supplemented by natural landings along the river 
and extensive facilities at Savannah. 
Operations and results during fiscal year. Maintenance: 
Routine maintenance and operation of the New Savannah 
Bluff Lock and Dam and its recreational area, which accommodated 
504,972 visitors, amounted to $550,825. Activity 
during the year included lock and dam operations totaling 
$117,275. Costs to repair the South Carolina pier was $58,385 
and remoting and rehabilitation of the lock totaled $48,765. 
Hydrology surveys cost $16,782 and district office support 
$1,769. Operation of the recreation area and facilities including 
the cleanup contract totaled $146,002 with additional 
maintenance costs of $161,525. (See Table 8-A for Cost and 
Financial Statement.) 
Condition at end of fiscal year. In general, open-channel 
works are in good condition. The notice on the Final Environmental 
Impact Statement appeared in the Federal Register 
February 18, 1977. 
Costs of the existing project to September 30, 1986, were 
$22,676,139 of which $6,646,551 was for new work and 
$16,029,588 for maintenance. (See Table 8-A for Cost and 
Financial Statement.) No dredging, snagging, or repair of 
pile dikes and revetment was performed in FY 86. 
8-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
7. RECONNAISSANCE AND 
CONDITION SURVEYS 
Survey Section performed project condition surveys on 
the following active O&M navigation projects: 
Savannah Harbor - - monthly 
Brunswick Harbor - - monthly 
AIWW -- 14-20 Aug. 86, 29 Apr -8 May 86, 20-25 Feb. 86, 
18-20 Nov 85 
Savannah River Below Augusta - - 11-13 Feb 86 and 25-28 
Aug 86 
8. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 8-C.) 
9. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Costs for preauthorization studies and project construction 
totaled $226,251. Plans and specifications on Bellville 
Point, GA, were prepared in January 1986 and the project 
was constructed in April 1986 at a cost of $182,302. Costs 
for BelIville totaled $217,132. The Valona, GA, detailed project 
study was inactive in FY 86 except for some coordination 
work. TheAlWWat Brunswick required $7,3700of coordination 
activity. 
Beach Erosion Control 
10. BEACH EROSION CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
A reconnaissance investigation was initiated on the 
shoreline erosion problems at Crooked River State Park, 
GA, at an FY 85 cost of $27,404. 
11. TYBEE ISLAND, GA 
Location. Tybee Island is located directly south of 
Savannah River entrance, about 17 miles east of the City of 
Savannah, GA (See NOAA Charts 11512,11513 and 11509, 
formerly U.S. Coast and Geodetic Survey Charts Nos. 440, 
1240, and 1241, and on maps included in H.D. 92-105, 92d 
Cong.) The only portion of the island that has been developed 
in bounded on the north by th south channel 
of the Savannah River, on the east by the Atlantic 
Ocean, and on the south and west by Tybee Creek and 
other small tidal streams. This area, hereinafter referred to 
as "Tybee Island," is occupied by the City of Tybee Island. 
The ocean face of this area has had a wide sandy beach. 
Tybee Island is about 3.5 miles long from its northerly tip to 
the mouth of Tybee Creek with an average width of 
about 0.5 mile. Behind the beach lies a line of sand dunes, a 
number of which have been removed during the years to 
make room for improvements and for various other reasons. 
Those that remain are from 10 to 20 feet high. The ground 
elevation west of the dunes is from 10 to 18 feet and slopes 
westward to the salt marsh. 
Existing project. The approved project plan of improvement 
provides for an 800-foot rock groin at the north end of 
the island, with a 225-foot tie-in to high ground. An additional 
1,200-foot extension of this groin is deferred, as are 
two additional, intermediate groins (480 feet long); these 
will be added at a later date, if needed. The plan also 
provides for the initial restoration of approximately 13,300 
feet of beach, from the vicinity of 18th Street to the terminal 
groin located at the northern end of the island. Periodic 
nourishment will be provided as needed to maintain suitable 
beach dimensions. In 1981, the plan was modified and 
now calls for the addition of a groin at the south end and 
modification and rehabilitation of the north rock groin and 
renourishment. 
Local cooperation. Local interests must: (a) contribute 
cash the required percentage of the first cost, including 
costsforconstruction, engineering, and design, and administration; 
and excluding the cost of lands, ease-ments, rights-of way; 
and relocations; of all items of work to be provided by the 
Corps of Engineers, presently estimated at 51.0 percent to 
be paid in a lump sum prior to start of construction or in 
installments prior to the start of pertinent work items in 
accordance with construction schedules as required by the 
Chief of Engineers, the final apportionment of cost to be 
made after the actual costs have been determined; (b) 
provide maintenance and repair of the groins, and provide, 
after the first 10 years of project life, periodic nourishment 
of the restored beach as may be required to serve the 
intended purpose during the life of the project; (c) provide 
without cost to the United States all lands, easements, 
rights-of-way, and relocations required for construction 
and subsequent nourishment of the project; (d) hold and 
save the United States free from claims for damages that 
may result from construction, maintenance, and nourishment 
of the project; (e) control water pollution to the extent 
necessary to safeguard the health of bathers; and (f) provide 
without cost to the United States access and facilities 
necessary for realization of the public benefits upon which 
Federal participation is based, and maintain continued public 
use of the beach and administer it for public use 
8-6

SAVANNAH, GA, DISTRICT 
administer it for public use during the life of the project; and 
provided further, that construction on the project shall not be 
started until local interests furnish lands for beach access 
and parking, satisfactory to the Chief of Engineers, for the 
reach from 1st Street to the terminal groin. To date, local 
cooperation is being provided as required. 
Condition at end of fiscal year. The Final Environmental 
Impact Statement was filed with CEQ on November 13,1973. 
The initial construction contract for the terminal groin was 
awarded September 13, 1974 in the amount of $980,642. 
The groin was completed and formally accepted 
on June 17, 1975. The second contract, for initial beach fill 
and advance nourishment, was awarded June 18,1975 in the 
amount of $2,175,000. This resulted in the placement of 2.3 
million cubic yards of sandfill along most of the entire length 
(13,300 feet) of ocean beach front. The sand was removed by 
hydraulic pipeline dredge from a massive sandbar borrow 
area off the south end of Tybee Island. Completed in March 
1976, the project provides approximately 124 feet of beach 
seaward of the seawall (accessible at average high tide), 
doubling the public beach area. Erosion has occurred along 
the beach front. Results of prior years beach monitoring 
indicate a decreasing or stabilizing erosion rate. The southernmost 
section south of 13th Street has experienced the 
most critical erosion. Total project cost is estimated to be 
$8,700,000, which includes $4,449,800 in non-Federal, contributed 
funds. Costs to date of existing project were 
$3,126,541 (Federal funds) and $2,128,850 (contributed funds). 
(See Table 8-A Cost and Financial Statement.) 
Flood Control 
12. BROADWAY LAKE, ANDERSON 
COUNTY, SC 
Location. The Broadway Lake is located about 4 miles of 
Anderson, South Carolina. It is formed at the junction of 
Broadway Creek and Neals Creek in the headwaters of 
Rocky River, a tributary of the Savannah River. 
Existing project. The authorization provides for the of 
Engineers to undertake a demonstration project for the removal 
of silt and aquatic growth from an existing lake known as 
Broadway Lake, owned by Anderson County, South Carolina. 
This lake has a surface area of about 1 square mile and a 
tributary area of about 44 square miles with an existing dam 
and concrete spillway. The spillway is 50 feet wide, about 19 
feet high, and flanked by an earth on the west side. The total 
length of the dam is about 610 The National Dam Safety 
Inspection Program determined that the dam did not meet 
the safety criteria. Since the repairs of the dam, spillway, and 
low-level outlet are not the authority of the demonstration 
project, the U.S. Army Corps of Engineers will withhold 
implementation of the project pending repairs to the dam by 
State or local authorities. 
Local cooperation. The local interests are now making 
the necessary repairs to the dam. Local interests have 
expressed a willingness to provide necessary easements, 
and rights-of-way for removal of silt and aquatic weeds, as 
well as provide lands for disposal areas. They will be required 
to hold and save the United States free from damages due to 
the construction works other than damages due to the fault 
or negligence of the United States or its contractors. The 
United States should be relieved of any liability due to dam 
failure from construction activity in the lake. The local 
assurer is Anderson County 
Operations and results during fiscal year. The project is 
inactive, pending completion of repairs to the dam by local 
interest. The Detailed Project Report was returned for the 
District to notify appropriate interests that the Corps can no 
longer participate in primarily recreation projects. (See 
Table 8-A for Cost and Financial Statement.) 
13. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Physical inspections of Dunn Branch, Augusta and Macon 
levees, and Peacock Creek were completed during the fiscal 
year. The total cost of the fiscal year amounted to $21,646. 
14. OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
(See Table 8-D) 
15. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, Public Law 
858, 80th Congress, as amended (preauthorization studies). 
Preauthorization studies continued through FY 86 on Federal 
Prison Creek, GA; Placentia Canal, GA; and Springfield 
Canal, GA. The DPR on Federal Prison Creek continued at a 
FY cost of $20,104. Placentia Canal DPR continued at a FY 
cost of $124,778. Detailed project studies continued in FY 86 
on Springfield Canal at a cost of $87,078. The total cost for 
preauthorization studies in FY 86 was $231,960. 
Emergency flood control activities - repair, flood fighting, 
and rescue work, (Public Law 99, 84th Congress and antecedent 
legislation). Revisions to emergency manuals, emergency 
planning, inspection, supplies, emergency 
operations, and exercises costs were $620,901. 
8-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Multiple-Purpose Projects Including Power 
16. SAVANNAH RIVER BASIN, GA 
AND SC 
Location. Works covered by this project consist of a series 
of 11 dams and lakes on Savannah River and its tributaries in 
Georgia and South Carolina. (See Geological Survey maps 
of GA and SC.) 
Existing project. The Flood Control Act of 1944 approved 
the general plan for comprehensive development of the 
Savannah River Basin for flood control and other purposes 
(H.D. 657, 78th Cong., 2d sess.) and authorized construction 
of the Clarks Hill Project on the Savannah River in Georgia 
and South Carolina as the initial step of this development. 
The Flood Control Act of 1950 authorized construction of 
Hartwell Lake under the general plan. Trotters Shoals which 
will replace Goat Island and Middleton Shoals was authorized 
for construction by the Flood Control Act of 1966 at an 
estimated cost of $84,900,000. Clarks Hill and Hartwell Lakes 
are the only projects in the comprehensive plan that have 
been constructed. (See Table 8-E on Dams and Lakes at end 
of chapter.) 
Duke Power Company has completed construction on the 
Keowee-Toxaway power complex on the Keowee River in 
the headwaters of Hartwell Lake and construction of the 
Jocassee pump-storage power project in the headwaters of 
the Keowee-Toxaway project. The Keowee-Toxaway power 
complex is located on the Newry - Old Pickens site identified 
in the approved comprehensive plan. Individual reports 
on Clarks Hill, Hartwell, and Richard B. Russell (formerly 
Trotters Shoals) Lake follow. 
Local cooperation. None required. 
16A. CLARKS HILL LAKE, GA AND SC 
Location. Clarks Hill Lake is located at mile 237.7 on 
Savannah River about 22 miles upstream from Augusta, GA 
(See Geological Survey maps of Georgia and South Carolina.) 
Existing project. The authorized project provides for construction 
of Clarks Hill Dam and Lake, the final cost of which 
was $79,156,300. The dam has a concrete section 2,282 feet 
long with a maximum height of 200 feet, and a controlled 
spillway 1,096 feet long. The concrete section is flanked on 
the west side by a rolled-earth embankment of 2,069 feet, and 
on the east side by a similar embank-ment of 1,329 feet. Total 
length of the dam is 5,680 feet. At maximum power pool 
elevation 330, the lake covers 70,000 acres. It provides a total 
storage capacity of 2,900,000 acre-feet allocated as follows: 
flood control 390,000 acre-feet; hydroelectric power 1,045,000 
acre-feet; and dead storage 1,465,000 acre-feet. Seven 
40,000-kilowatt generators have a combined generating 
capacity of 280,000 kilowatts, with an average annual output 
of 700 million kilowatt-hours of electrical energy. 
Local cooperation. None required. 
Operations and results during fiscal year. New work: Cost 
of recreational activities during the period from Construction 
General funds (Code 710) amounted to $1,655. Gross generations 
of electric energy for the period was 442,395,200 
kilowatt-hours, most of which was delivered to the Southeastern 
Power Administration. Flood damages prevented 
were zero due to the drought. 
Maintenance: Operation and maintenance costs during 
the fiscal year amounted to $6,288,836..The notice of availability 
on the Final Environmental Impact Statement on 
Clarks Hill Lake Operation and Maintenance appeared in the 
December 18,1981 Federal Register. Visitation to the project 
in FY 86 was 7,645,698 persons. 
Condition at end of fiscal year. Construction is complete 
except for providing additional recreational development. 
(See Table 8-A for Cost and Financial Statement.) 
16B. HARTWELL LAKE, GA AND SC 
Location. Hartwell Lake is on the Savannah River 305 
miles above its mouth and 89 miles upstream from Augusta, 
Georgia. (See Geological Survey maps of GA and SC.) 
Existing project. The dam is a concrete gravity-type structure, 
1,900 feet long with a maximum height of 204 feet and a 
controlled spillway 568 feet in length. The concrete section is 
flanked on the east and west abutments by earth embankments 
totaling 13,390 feet in length and by a saddle dike 
2,590 feet long also on the west side. Total length of the dam 
is 17,880 feet. At maximum power pool elevation of 660 feet 
the lake covers 55,950 acres. Total capacity of the lake is 
2,843,000 acre-feet of storage allocated as follows: flood 
control 293,000 acre-feet; hydroelectric power 1,416,000 
acre-feet; and dead storage 1,134,000 acre-feet. Four 66,000- 
kilowatt generators having generating capacity of 264,000 
kilo-watts were installed initially with provisions for a future 
unit. A fifth 80,000-kilowatt generating unit has been installed 
which increased the rated capactiy to 344,000 kilowatts. 
Local Cooperation. None required. 
Operations and results during fiscal year. Cost of activities 
during the fiscal year amounted to $6,208,293. An additional 
$281,828 was expended from (Code 713) for cost sharing at 
the 1-85 Destination Park. 
8-8

SAVANNAH, GA, DISTRICT 
The fiscal year upper diversion dam rehabilitation cost 
amounted to $138,899. Gross generation of electrical energy 
for the period amounted to 306,208,100 kilowatt-hours, most 
of which was delivered to the Southeastern Power Administration. 
Flood damages prevented were zero due to the 
drought. 
Maintenance: Operation and maintenance costs during 
the fiscal year amounted to $6,208,293. The notice on the 
Final Environmental Impact Statement on the operation and 
maintenance of Hartwell Dam and Lake appeared in the 
Federal Register August 21, 1978. Approximately 
13,127,667 persons visited the lake in FY 86 
Condition at end of fiscal year. Construction is complete 
except for providing additional recreational development. 
(See Table 8-A for Cost and Financial Statement.) 
16C. RICHARD B. RUSSELL DAM AND 
LAKE, GA AND SC, (FORMERLY 
TROTTERS SHOALS LAKE, 
GA AND SC) 
Location. Richard B. Russell Dam is on the Savannah 
River 275.1 miles above its mouth, 29.9 miles below Hartwell 
Dam and about 37.4 miles above Clarks Hill Dam. (See 
NOAA Survey maps of GA and SC.) 
Existing project. The authorized project provides for construction 
of Richard B. Russell Dam and Lake substantially in 
accordance with the recommendations of the Chief of Engineers 
at an estimated cost of $84,900,000. The latest approved 
(FY 86) cost estimate for the project is $545,000,000, of which 
$435,856,000 is for construction, $28,465,000 for lands and 
damages, $4,683,000 is for cultural resources, and $75,996,000 
for engineering and design and supervision and administration. 
Approval was received January 1977 to include minimum 
provisions for pumped storage. A notice of availability 
of a Final Environmental Impact Statement covering pumped 
storage was published in the Federal Register February 18, 
1977, and October 26, 1979. A notice of availability on the 
Final Supplement to the Environmental Impact Statement on 
Fish and Wildlife Mitigation for the Russell project appeared 
in the Federal Register on December 11, 1981. 
Operations and results during fiscal year. Contracts were 
awarded during FY 86 as follows: (1) Miscellaneous crane 
and debris removal work $182,237; (2) Modify tainter Gates 
opening time $281,697; (3) Complete visitor display areas for 
the powerhouse and natural resources management center 
$317,000; (4) Supply liquid oxygen and cryogenic equipment 
O&M $668,900 (5) Repair earth embankment $128,110; (6) 
Supply generators and motors for pump storage $13,860,700; 
(7) Structural modifications to under-water oxygen distribution 
system $1,075,000. Other FY 87 projects to be 
awarded include: (1) Downstream tailrace rock removal 
excavation contract; (2) Complete miscellaneous projects 
finish non-critical powerhouse modifications; (3) Supply liquid 
oxygen for calendar years 1987,1988,1989; (4) Install an 
alarm system for the oxygenation facility; (5) Landscape 
project for exterior area of the powerhouse; (6) complete 
relocation of SCL railroad site R-3; (7) Phase II Georgia 
recreation areas; (8) Construct operational and administrative 
roads. Remaining pump storage contract awards are 
scheduled for FY 87 awards are as follows; (1) Switchgear 
Nov. 1986; (2) Transformer Dec 86; (3) Main control board 
Feb 87; (4) Governor Mar 87. The general construction contract 
for pump storage is approximately 50% complete and is 
scheduled for a 2nd quarter FY 88. Continued water quality 
monitoring by Waterways Experiment Station is approved to 
extend their contract thru FY 92. Fish entrainment studies 
relating to future pumpback were initiated in FY 84, with 
basic Phase I study and conceptual protection system 
design completed in early FY 85. An intensive fishery data 
collection effort is ongoing. In FY 86, 293,857,000 kilowatts of 
power were generated. 
Maintenance: The operation and maintenance cost for the 
fiscal year amounted to $3,233,598. 
Condition at end of fiscal year. The project is 79 percent 
complete. 
Costs of project to September 30, 1986, were 
$434,764,323 of which $426,800,000 is for new work and 
$7,964,323 for maintenance. (See Table 8-A for Cost and 
Financial Statement.) 
17. WEST POINT LAKE 
CHATTAHOOCHEE RIVER 
The West Point Lake located on the Chattahoochee River, 
2.8 miles upstream from West Point, GA, was authorized by 
the Flood Control Act of 1962 (H. D. 570, 87th Cong., 2d 
sess.). The project was designed and constructed 
for flood control, power, recreation, fish and wildlife development 
and streamflow regulation for downstream navigation. 
Design and construction was accomplished by 
Savannah District for Mobile District. For complete information 
see Mobile District. 
General Investigation 
18. SURVEYS 
Fiscal year cost was $1,678,239, of which $444,647 was for 
navigation studies; $724,103forflood control studies; $71,844 
for special investigations; and $64,044 for coor-dination with 
other agencies, and $2,912 for coordinating FERC Licenses. 
8-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
19. COLLECTION AND STUDY 
OF BASIC DATA 
Work continued underthe Flood Plain management Services 
on the compilation of flood information, potential flood 
damages, and identification of those areas subject to inundation. 
Fiscal year expenditures for these activities were as 
follows: flood plain management services, $81,049; and 
technical services, $97,034. Flood plain management services 
included responses to other Federal agencies to aide 
them in fulfilling the requirements of Executive Order 11988 
(Management of Base Flood Area). Through the Technical 
Services Program, flood problems in several areas were analyzed 
and possible improvements were identified. Early in FY 
86 the Flood Plain Management Services Branch began the 
Coastal Georgia Hurricane Evacuation Study. This study is a 
three year joint effort of the State of Georgia, local officials, 
Federal Emergency Management Agency, and the Corps of 
Engineers. Funds available for the study in FY 86 was 
$285,000 of which $100,000 came from Corps of Engineers 
Flood Plain Management Program funds. In FY 86 $29,434 
was expended. The cost for hydrologic studies was $13,666. 
The total fiscal year cost for collection and study of basic 
data was $178,083. 
20. RESEARCH AND DEVELOPMENT 
No funds were expended for research and development 
during the fiscal year. 
21. CONTINUATION OF PLANNING 
AND ENGINEERING 
Continuation of Planning and Engineering (CP&E) for the 
Savannah Harbor Widening Project was completed in FY 85 
with the expenditure of $73,887 to complete the ship simulator 
study. The CP&E expenditures were $887,742. Plans and 
specifications were begun with FY 86 expenditures of 
$259,883. The recommended plan provides for modification 
of the harbor by widening the navigation channel between 
the present upstream limit of the 500-foot channel (Fig Island 
Turning Basin) and the Kings Island Turning Basin from 400 
to 500 feet. This will decrease the hazard of handling large 
vessels and reduce shipping transit time. 
In FY 86, the Lake Lanier Reregulation Dam Study continued 
under Continuation of Planning and Engineering. 
The cost amounted to $877,791. The recommended project 
is the construction of a reregulation dam on the Chattahoochee 
River, 6.3 miles downriver of Buford Dam. Project 
benefits are hydropower and water supply. 
Oates Creek is a major drainage outlet for flood waters 
from an urban area of Augusta, Georgia. A flood control 
study of Oates Creek was authorized and completed as part 
of the Savannah River Basin study. The Oates Creek study 
area is located just south of Augusta in Richmond County. 
The recommended plan is a channel and bridge modification 
flood control plan and has received support from 
Federal, State and local governmental agencies with no 
environmental opposition. The local sponsor, Richmond 
County, expressed support for the project and intent to participate 
financially. The plant consists of improvements to 
approximately 12,300 feet of channel and consists of 
concrete-lined channels, grass-lined channels, a low levee, 
modifications of bridges and culverts, and relocation of utilities. 
The CP&E effort began in October 1983 and consists of 
preparation of a General Design Memorandum estimated to 
cost about $780,000 and was completed in September 1986. 
FY 86 expenditures were $195,046. 
8-10

SAVANNAH, GA, DISTRICT 
TABLE 8-A 
See 
Section 
in Text Project 
COST AND FINANCIAL STATEMENT 
Funding 
Total Cost to 
FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
1. Altamaha, Oconee 
and Ocmulgee Rivers, 
GA 
2. Aquatic Plant 
Control (1965 
R&H ACT) 
3. Atlantic Intracoastal 
Waterway between 
Norfolk, VA, and the 
St. Johns River, FL 
4. Brunswick Harbor, 
GA 
5. Savannah Harbor, 
GA 
6. Savannah River 
below Augusta, 
GA 
11. Tybee Island, GA 
12. Broadway Lake, 
SC 
13. Inspection of 
Completed Flood 
Control Works 
16.A Clarks Hill Lake, 
GA and SC 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
191 - 
4,000 
269 46 
40,000 9,000 30,000 50,000 
36,731 11,488 11,433 58,950 
75,000 934,000 1,088,000 
481,164 914,900 950,290 
608,000 
752,177 
3,491,000 8,636,350 1,800,000 8,101,443 
5,221,253 9,605,206 1,896,159 8,110,481 
-319,000 
-112,480 
9,418,000 
6,986,914 
4,207,000 10,238,200 3,635,000 
8,049,868 10,084,654 3,528,413 
348,000 672,000 804,000 543,000 
171,452 884,597 759,000 550,830 
4,542 
- 386,949 1,053,000 
- 307,887 209,486 
85,000 13,000 -15,000 18,500 
4,731 59,775 15,387 29,646 
1,050,000 
593,200 
6,397,700 
5,629,293 
932,843 5,612 - 5,612 - 
6,673,800 7,554,000 6,386,000 
7,040,063 7,746,130 6,288,836 
821,4571 
821,4571 
1,917,98223 
1,914,2972,3 
341,159 
327,507 
958,0964 
958,0964 
16,556,9215 
16,532,0285 
4,573,6086 
4,573,4336 
55,036,894' 
54,934,112 
46,187,7218 
46,185,7438 
143,091,1409 
142,736,5179 
6,740,03110 
6,740,03110 
16,120,492 
16,029,588 
3,970,24913 
3,126,54113 
99,000 
99,000 
184,018 
183,731 
84,841,2901 
84,840,26311 
69,095,35415 
68,318,86615 
8-11 
- " w

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 8-A COST AND FINANCIAL STATEMENT 
FY 83 FY 84 FY 85 FY 86 
Total Cost to 
Sept. 30, 1986 
16B. Hartwell Lake, GA 
and SC 
16C. Richard B. Russell 
Dam and Lake, GA 
and SC (Formerly 
Trotters Shoals) 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
5,334,000 -450,000 
4,489,519 1,282,815 
270,000 -35,000 
213,815 355,807 
4,411,359 4,803,000 6,986,600 
4,938,210 5,031,036 6,863,402 
1,700,000 1,450,000 
1,893,576 2,463,415 
-100,000 
138,899 
6,404,500 
6,208,294 
69,000 
82,425 
78,469,000 36,300,000 21,400,000 9,310,000 
77,939,501 35,491,655 22,368,222 7,217,141 
396,000 1,231,300 2,870,000 3,734,000 
371,132 1,005,621 3,055,270 3,233,598 
115,871,3071214 
115,745,7351214 
62,297,72616 
61,566,05216 
6,619,000 
6,552,924 
426,799,509 
423,876,970 
8,559,300 
7,964,325 
1. Includes $760,610 for previous projects. 
2. Includes $111,950 for previous projects. 
3. Does not include $69,356 contributed funds. 
4. Includes $194,497 for previous projects. 
5. Includes $134,798 for previous projects. Does not 
include 35,000 appropriated but unexpended of contributed 
funds in FY 86. 
6. Includes $643,465 for previous projects and includes 
$97,521 expended from Public Works Funds for existing 
project. Does not include $10,000 contributed funds. 
7. Includes $54,414 for previous projects. Includes 
$4,995 expended from Public Works Funds for existing project. 
Excludes funds contributed by Brunswick and Ga. Port 
Authorities. Also includes $2,150,000 under '83 Job Bill Act. 
8. Includes $7,260,384 for previous projects. Does not 
include $46,847 for removal of sunken vessels or contributed 
funds. 
9. Includes $298,894 for previous projects. Does 
include $855,941 contributed funds. 
10. Includes $93,480 for previous projects. Includes 
$1,634,562 from Public Works Fund. 
TABLE 8-B AUTHORIZI 
11. Does not include $395,634 accelerated Public Works 
Funds. Includes $4,558,613 appropriated under Code 710 of 
which $4,556,958 has been expended. Also includes 
$1,000,000 expended under the '83 Job Bill Act. 
12. Does not include $276,200 accelerated Public Works 
Funds. Includes $4,861,000 appropriated under Code 710 of 
which $4,835,286 has been expended. Also includes $545,000 
expended under the '83 Job Bill Act. 
13. Does not include $2,128,850 contributed funds. 
14. Includes $17,515,000 appropriated for construction 
of 5th Unit of which $17,481,215 has been expended. 
15. Includes $316,760 under special recreation use fees. 
Also includes $736,000 under the '83 Job Bill Act. 
16. Includes $576,019 expended special recreation use 
fees. 
ING LEGISLATION 
See Date of 
Section Authorized 
in Text Act Project and Work Authorized Documents 
1. July 25, 1912 
and March 2, 1945 
Oct. 27, 1965 
Section 302 
ALTAMAHA, OCONEE AND OCMULGEE RIVERS, GA. 
Channel 3 feet deep and 60 to 100 feet wide. 
Provides for control and progressive eradication of 
noxious aquatic plant growths. 
HD 443, 62d Cong., 2d sess. 
HD 610, 77th Cong., 2d sess. 
HD 251, 89th Cong., 1st sess. 
8-12 
See 
Section 
in Text Project Funding 
" v

SAVANNAH, GA, DISTRICT 
TABLE 8-B (continued) 
See 
Section 
in Text 
AUTHORIZING LEGISLATION 
Date of 
Authorized 
Act Project and Work Authorized 
ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA., AND ST. JOHNS 
RIVER, FLA., (SAVANNAH DISTRICT) 
3. June 3, 1896 Section from Beaufort, S.C. to Savannah, Ga. Route No. 2 
adopted. 
Mar. 3, 1899 Route No. 1 adopted. 
July 13, 1892 Section from Savannah, Ga. to Fernandina, Fla. Original 
7-foot channel. 
Mar. 3, 1905 Provided for Skidaway Narrows. 
July 25, 1912 Incorporated alternative routes previously improved as 
separate projects and the auxiliary channels. 
Aug. 8, 1917 Section fromm Cumberland Sound, Ga. and Fla. to St. Johns 
River, Fla. Consolidation of the 3 sections shown above, 
into "Waterway between Beaufort, S.C. and St. Johns River, 
Fla." 
Mar. 2, 1919 Section from Beaufort, S.C. to Cumberland Sound, Ga. 
and Fla. Removing logs and snags from Generals Cut. 
Mar. 2, 1919 Improving Back River to provide a channel 7 feet deep and 
150 feet wide. 
Mar. 3, 1925 Channel 75 feet wide between Beaufort, S.C., and 
Savannah, Ga. 
July 3, 1930 Channel from Baileys Cut to Dover Creek. 
Aug. 26, 1937 A 7-foot protected channel around St. Andrews Sound. 
Aug. 26, 1937 A 12-foot channel between Beaufort, S.C., and Savannah, 
Ga. via Beaufort River and Port Royal Sound. 
June 20, 1938 A 12-foot channel between Savannah, Ga., and Fernandina, 
Fla., various cutoffs; and anchorage basin at Thunderbolt, 
Ga. 
Mar. 2, 1945 An alternate route 9 feet deep and 150 feet wide in that 
part of Frederica River, Ga., not now traversed by the main 
route, at no additional cost to the United States. 
Oct. 15, 1981 Main channel relocated from Frederica River to 
Mackay River in the vicinity of Torras Causeway. 
BRUNSWICK HARBOR, GA 
4. Mar. 3, 1879 Construction of East River jetty. 
Mar. 2, 1907 Channels in the inner and outer harbors of 30-foot depth 
at mean high water, with widths varying from 150 
feet in Academy Creek to 400 feet across 
the outer bar, extension of training wall in East River 
and construction of two spurdikes. 
Mar. 2, 1919 Channels 27 feet deep at mean low water over the 
bar and at Brunswick point; and 24 feet deet at 
mean low water in the inner harbor and provides 
for a cut from Academy Creek to Turtle River, if 
deemed advisable. 
July 3, 1930 A channel in Back River 230 feet deep and 150 feet wide. 
July 3, 1930 Increased Channel dimensions of the bar, Brunswick Point, 
East River, and Turtle River, as given in the then 
existing project. 
June 20, 1938 A 10-foot channel in Terry Creek. 
May 17, 1950 Increased channel dimensions of the bar, St. Simons 
Sound, Brunswick River, East River, and Turtle River, 
as given in the existing project. 
Oct. 22, 1976 Provides for Phase I AE&D studies for deepening portions 
of existing harbor (East River and Entrance Channel) and 
for provision of a navigation channel to Colonels Island. 
Oct. 17, 1986 Incorporated Georgia Port Authority's 30 foot by 8000 foot 
channel in South Brunswick River serving Colonel's 
Island into Brunswick Harbor Navigation Project 
HD 295, 53d Cong., 3d sess. 
HD 295, 53d Cong., 3d sess. 
HD 41, 52d Cong., 1st sess. 
HD 450, 58th Cong., 2d sess. 
HD 1236, 60th Cong., 2d sess. 
HD 581, 63d Cong., 2d sess. 
HD 1391, 62d Cong., 3d sess.' 
SD 178, 68th Cong., 2d sess. 
SD 43, 71st Cong., 2d sess.' 
Senate committee print, 74th 
Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 6, 75th Cong., 1st sess. 
HD 618, 75th Cong., 3d sess. 
HD 114, 77th Cong., 1st sess. 
Project authorized by 
Chief of Engineers under the 
Small Navigation Project 
Authority, Sec. 107, PL 
86-645 as amended. 
Annual Report, 1880, p. 959 
HD 407, 59th Cong., 1st sess. 
HD 393,64th Cong., 1st sess. 
SD 57, 71st Cong., 2d sess.' 
SD 132, 71st Cong., 2d sess.' 
HD 690, 75th Cong., 3d sess.1 
HD 110, 81st Cong., 1st sess. 
Report of Chief of Engineers 
dated Aug. 18, 1976. 
HR 6, 99th Cong. 2d sess. 
Section 846 
8-13 
Documents

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 8-B (continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorized 
in Text Act Project and Work Authorized Documents 
5. Mar. 2, 1907 
June 25, 1910 
July 25, 1912 
Aug. 8, 1917 
Jan. 21, 1927 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Nov. 7, 1945 
July 24, 1946 
Sep. 3, 1954 
Oct. 23, 1962 
Oct 27, 1965 
SAVANNAH HARBOR, GA. 
Tentative provisions for a 26-foot channel from the 
Quarantine Station to the Seaboard Air Line Ry. Bridge 
Definite provision for the 26-foot channel. 
A 21-foot channel from the Seaboard Air Line Ry. Bridge 
to the foot of Kings Island. 
A 30-foot depth from the sea to the Quarantine Station. 
A 21-foot channel above Kings Island. 
Channel 30 feet deep, with general width 50 feet, from the 
ocean to the Quarantine Station, thence 26 feet deep, 
general width 400 feet, to the Seaboard Air Line Ry. Bridge, 
thence 21 feet deep and 300 feet wide to Kings Island. 
Widening at West Broad and Barnard Streets; anchorage 
basin; mooring dolphins; regulating dam across South 
Channel; relocation of the Inland Waterway; dredging 
Drakies Cut to 13 feet; widening to 525 ft. at Kings Island; 
extension of training walls, revetments, and jetties. 
Consolidation of projects relating to Savannah Harbor. 
Channel 26 feet deep and 300 feet wide from the Seaboard 
Air Line Ry. Bridge to the foot of Kings Island. 
Authorized the 30-foot project and eliminated from the project 
(a) the relating dam across South Channel; (b) the 
relocation of the Inland Waterway; and (c) the further 
extension of training walls, revetments, and jetties. 
Deepening the channel and turning basin above the Seaboard 
Air Line Ry. Bridge from 26 to 30 feet and widening 
the channel opposite the Atlantic Coast Line Terminals to a 
maximum of 550 feet for a length of 5,000 feet. 
Deepening the channels to 36 feet deep and 500 feet wide 
across the ocean bar; 34 feet deep and generally 400 feet 
wide, increased to 550 feet opposite the Atlantic Coast 
Line Terminals, with a turning basin 34 feet deep at the 
Mexican Petroleum Corp. Refinery; and with such modifications 
thereof as the Secretary of War and the Chief of 
Engineers may consider desirable. 
Extending channel 30 feet deep, 200 feet wide, upstream 
from Atlantic Creosoting Terminal to a point 1,500 feet 
below the Atlantic Coastal Highway Bridge, with turning 
basin 30 feet deep at upper end. 
Deepening the channel to 34 feet and widening to 400 feet 
from the upper end of the presently authorized 34-foot 
channel in the vicinity of the American Oil Company 
Refinery wharf, to the Savannah Sugar Refining Corp. 
with a turning basin at the upper end of the proposed 
improvement, made by widening the channel to 600 feet 
for a length of 700 feet and providing approaches. 
Enlargement of turning basin near Kings Island to a width 
of 900 feet and a length of 1,000 feet, with suitable 
approaches, at a depth of 34 feet. 
Deepening the bar channel from 36 feet to 40 feet, the 
channel between the bar channel and Garden City Terminal 
from 34 feet to 38 feet, and the channel from the Garden 
City Terminal to the vicinity of the Savannah Sugar Refining 
Corp., from 30 feet to 36 feet; widening the bar channel 
from 500 feet to 600 feet, the channel between Fort Pulaski 
and Atlantic Coast Line Terminal from 400 feet to 500 feet, 
and the channel between Garden City Terminal and the 
Savannah Sugar Refining Corp. from 200 feet to 400 feet; 
providing necessary wideners of the bends; constructing a 
new turning basin 900 feet wide by 1,000 feet long by 34 
feet deep opposite the Atlantic Coast Line Terminals; and 
enlargement of existing turning basin at the American Oil 
Company Terminal from 600 feet wide by 600 feet long to 
900 feet wide by 1,000 feet long. 
HD 181, 59th cong., 1st sess. 
HD 563, 62d Cong., 2d sess. 
HD 1471, 64th Cong., 2d sess. 
HD 261, 69th Cong., 1st sess. 
HD 262, 69th Cong., 1st sess. 
SD 39, 71st Cong., 1st sess. 
HD 276, 73d Cong., 2d sess. 
HD 283, 76th Cong., 1st sess. 
HD 227, 79th Cong., 1st sess. 
HD 678, 79th Cong., 2d sess.1 
HD 110, 83d Cong., 1st sess. 
SD 115, 87th Cong., 2d sess. 
HD 226, 89th Cong., 1st sess. 
8-14

SAVANNAH, GA, DISTRICT 
TABLE 8-B (continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorized 
in Text Act Project and Work Authorized Documents 
Oct. 27, 1965 
SPWC Resolution 
June 15, 1976 
and HPWTC of 
June 9, 1976 
under authority 
of Sec. 201 of 
Flood Control 
Act of 1965 
Oct. 17 1986 
Sep. 19 1980 
June 25, 1910 
July 3, 1930 
Aug. 30, 1935 
Aug. 26, 1937 
May 17, 1950 
11. SPWC Resolution 
June 22, 1971 and 
HPWC of June 23, 
1972 under authority 
of Sec. 201 
of FC Act of 1965 
Oct. 17, 1986 
12. Water Resources 
Development Act 
of March 7, 1974. 
16A. Flood Control Act 
of Dec. 22, 1944 
Oct. 17, 1986 
16B. Flood Control Act 
of May 17, 1950. 
Flood Control Act 
of July 3, 1958. 
Water Resources 
Development Act 
of 1976. 
16C. Flood Control Act 
of Nov. 7, 1966. 
Water Resources 
Development Act 
of 1986 
Providing sediment control works consiting of tide 
gate structure across Back River; sediment basin 40 
feet deep, 600 feet wide about 2 miles long, with entrance 
channel 38 to 40 feet deep and 300 feet wide; drainage canal 
across Argyle Island 15 feet deep and 300 feet wide; control 
works and canals for supplying fresh water to Savannah 
National Wildlife Refuge; and facilities to mitigate damages 
to presently improved areas other than refuge lands. 
Provided for modification of the existing project to include 
(1) incorporation of the LASH Turning Basin as an 
element of the existing Federal navigation project for 
maintenance purposes, (2) enlargement of Kings Island 
Turning Basin to 1,500 feet by 1,600 feet by 38 feet. 
Savannah Harbor widening as described in Report of Chief of 
Engineers date Dec. 19,1978. Widen channel from 
400 feet to 500 feet between Kings Island Turning 
Basin and Fig Island Turning Basin 
Allows planning, engineering and design to remove 
drift and debris as part of operations and maintenance 
SAVANNAH RIVER BELOW AUGUSTA, GA. 
For a 5-foot channel. 
Special improvement by bank protection work of 20 or 25 
miles of the river immediately below Augusta. 
The present 6-foot channel project and Lock and Dam. GA. 
Provision made for locating the lock and dam at New 
Savannah Bluff. 
Conditions of local cooperation modified. 
Provides for a 9-foot channel. 
TYBEE ISLAND, GA. 
Project will provide for beach erosion control, consisting 
of beach restoration, groin 
nourishment. 
Extends authority for renourishment with 
Federal participation from 15 to 50 years. 
BROADWAY LAKE, S.C. 
Provided for undertaking a demonstration project for the 
removal of silt and aquatic growth from Broadway Lake. 
CLARKS HILL LAKE, GA. AND S.C. 
Approved the general plan for the comprehensive development 
of the Savannah River Basin and provided for construction 
of the Clarks Hill Project. 
Recreation and fish and wildlife added as project purposes. 
HARTWELL LAKE, GA. AND S.C. 
Provided for construction of Hartwell Project. 
Provided for the completion of the Hartwell Project. 
Provides for installation of 5th unit. 
RICHARD B. RUSSELL DAM AND LAKE, GA. 
Provided for construction of the Trotters Shoals Project. 
Authorized mitigation plan 
HD 223, 89th Cong., 1st sess. 
HD 94-520, 94th Cong. 
dated June 8, 1976. 
HD 6 99th Cong., 2d sess. 
Dated Oct 17, 1986 
Section 201 
Section 867 
HD 255 51st Cong., 2d sess. 
& Annual Report. 1890 p.1328 
HD 962, 60th Cong., 1st sess. 
HD 101, 70th Cong., 1st sess. 
Senate Committee Print, 
73d Cong., 2d sess. 
Rivers and Harbors Com., 
Doc. 39, 75th Cong., 1st sess. 
SD 6, 81st Cong., 1st sess. 
HD 105, 92d Cong. 
HR 6 99th Cong., 2d sess. 
Dated Oct 17, 1986 
Section 867 
PL 93-251, 93d Cong. 
HD 657, 78th Cong., 2d sess. 
PL 534, 78th Cong., 2d sess. 
HR 6 99th Cong., 2d sess. 
Section 864 
HD 657, 78th Cong., 2d sess. 
PL 516, 81st Cong., 2d sess. 
PL 85-500, 85th Cong., 
2d sess. 
PL 94-587, Sec. 182b. 
85th Cong. 
SD 52, 89th Cong., 1st sess. 
HR 6 99th Cong., 2d sess. 
dated Oct. 17, 1986 
Section 601 
1. Contains latest published maps. 8-15 
1.Cotisltspulse mas 8-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 8 in text) 
TABLE 8-C 
For Last Cost to Sep. 30, 1986 
Full Report 
Project See Annual Operation and Status Report for Construction Maintenance 
Aquatic Plant Control (R&H Act 1962) Completed 1968 25,700- 
Bellville Point, GA Completed 1986 -- 
Cedar Point, GA Completed 1982 656,233- 
Darien Harbor, GA Completed 1975 199,723 185,433 
Fancy Bluff Creek, GA 1 Completed 1935 8,000 7,200 
St. Marys River, GA and FL, and Completed 1951 15,688 69,936 
North River, GA 
Sapelo Harbor, GA 2'3 Completed 1929 17,906 19,594 
Satilla River, GA'5 Completed 1951 9,452 57,172 
Savannah River above Augusta, GA 2'
3'4 See Notes 1929 69,600 5,870 
Savannah River at Augusta, GA 2'3'5 See Notes 1929 200,556 17,444 
1. Channel adequate for commerce. 5. Excludes $185,000 contributed funds ($172,151 
2. Project recommended for abandonment in for construction and $12,849 for operation and 
H.D. 467, 69th Cong., 1st sess. maintenance). 
3. No commerce reported. 6. Water Resources Development Act of 1986 
4. About84percentcompleted.Owingtoconstruction Authorized demonstration project on the Umbrella 
of two power dams which submerged much of the Creek - Dover Creek for the purpose of reducing 
work under the present and former projects, this shoaling. Monitor for 10 years, develop a hydrodyimprovement 
cannot be completed as originally namic model. 
planned. 
TABLE 8-D OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 14 in text) 
For Last Cost to Sep. 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report for Construction Maintenance 
Augusta, Savannah River, GA Completed 1941 643,016 38,242 
Curry Creek Dam and Lake, GA 1 See Note 1974 - - 
Dunn Branch, Woodbine, Camden Completed 1977 132,640 5,219 
County, GA 
Macon, GA Completed 1955 380,043 38,243 
Oates Creek, GA Authorized N/A -2 
Peacock Creek, Liberty County, GA Completed 1976 582,163 5,219 
1. Feasibility report completed. Project not authorized 
for construction. 
2. Authorized by HR 6, Water Resource Development 
Act of 1986 dated Oct. 17, 1986. First Federal cost of 
$9,600,000 and non-federal cost of $4,100,000. 
8-16

SAVANNAH, GA, DISTRICT 
SAVANNAH RIVER BASIN, GA AND SC 
DAMS AND LAKES 
(See Section 16 in text) 
Estimated Cost 
Name River Federal Non-Federal Total 
Clarks Hill, GA and SC Savannah $79,156,0004 $79,156,00014 
Hartwell, GA and SC Savannah 89,240,000 89,240,0002 
Goat Island, GA and SC5 Savannah 36,400,000 36,400,000' 
Middleton Shoals, GA and SC 5 Savannah 16,500,000 16,500,0003 
Chattooga Units (4), GA and SC Chattoga 41,700,000 41,700,0003 
Tallow Hill, GA Broad 39,000,000 39,000,0003 
Anthony Shoals, GA Broad 18,100,000 18,100,0003 
Newry-Old Pickens, SC 6 Keowee 29,500,000 29,500,0003 
1. Final cost. (Excludes $127,000 for preauthorization 
study.) 
2. Approved Aug. 1963. (Excludes $73,000 for preauthorization 
study.) 
3. Approved July 1954. 
4. Excludes Code 710 funds. 
5. Replaced by Richard B. Russell Dam and Lake 
(formerly Trotters Shoals Lake). 
6. Site of Duke Power Co. Keowee-Toxaway Project. 
8-17 
TABLE 8-E

JACKSONVILLE, FLA. DISTRICT * 
JACKSONVILLE, FLA. DISTRICT
With the exception of a small area in the northeastern 
section of Florida, this district comprises a 
portion of south-central Georgia and all of peninsular 
Florida, embracing the watersheds tributary to the 
Atlantic Ocean and the Gulf of Mexico from, and including 
the harbor at Fernandina, Florida, to and including 
the Aucilla River. It also includes Puerto Rico 
and the Virgin Islands. 
IMPROVEMENTS 
Navigation Page 
1. Aquatic Plant Control (R&H Act 
of 1965) ......................... .............. 2 
2. Arecibo Harbor, P.R ........................ 2 
3. Atlantic Intracoastal Waterway 
between Norfolk, Va. and St. 
Johns River, Fla................ .............. 2 
4. Bakers Haulover Inlet, Fla .................. 3 
5. Canaveral Harbor, Fla ....................... 3 
6. Channel from Naples to 
Big M arco Pass ................... ............. 4 
7. Charlotte Harbor, Fla ........................ 4 
8. Cross Florida Barge Canal ................... 4 
9. Eau Gallie Harbor, Fla ....................... 5 
10. Fernandina Harbor, Fla ...................... 5 
11. Fort Myers Beach, Fla ....................... 5 
12. Fort Pierce Harbor, Fla ...................... 6 
13. Intracoastal Waterway, Caloosahatchee 
River to Anclote River, Fla .................. 6 
14. Intracoastal Waterway, Jacksonville 
to M iam i, Fla ...................... ............. 7 
15. Jacksonville Harbor, Fla .................... 7 
16. John's Pass, Fla .................. ............. 8 
17. Longboat Pass, Fla ........................... 8 
18. Mayaguez Harbor, P.R ...................... 9 
19. Melbourne Harbor, Fla ...................... 9 
20. Miami Harbor, Fla ........................... 9 
21. New Pass, Sarasota, Fla ..................... 10 
22. Okeechobee Waterway, Fla ................. 10 
23. Oklawaha River, Fla ......................... 11 
24. Palm Beach Harbor, Fla ..................... 11 
25. Ponce de Leon Inlet, Fla ..................... 12 
26. Ponce Harbor, P.R ............................ 12 
27. Port Everglades Harbor, Fla ................. 13 
28. Removal of Aquatic Growth From 
Navigable Waters in the State of Florida ..... 13 
29. St. Augustine Harbor, Fla..................... 14 
30. St. Johns River, Jacksonville to 
Lake Harney, Fla........................... 14 
31. St. Lucie Inlet, Fla ............................. 15 
32. San Juan Harbor, P.R ........................ 15 
33. Tampa Harbor, Fla.............. ............. 16 
34. Navigation Projects on which 
Reconnaissance and Condition Surveys 
only were Conducted during Period ......... 17 
Navigation (cont.) 
35. Other Authorized Navigation 
Projects ................................. 
36. Navigation Work under Special 
Authorization ......................... 
Page 
17 
17 
Beach Erosion Control 
37. Brevard County, Fla .................. 17 
38. Broward County, Fla. Beach Erosion 
Control and Hillsboro Inlet, Fla., 
Navigation Project ..................... 18 
39. Dade County, Fla ...................... 18 
40. Dade County, N. of 
Haulover Beach, Fla .................. 19 
41. Duval County, Fla ..................... 19 
42. Fort Pierce, Fla ........................ 20 
43. Palm Beach County, Fla. from Martin 
County line to Lake Worth Inlet and 
from South Lake Worth Inlet to 
Broward County line ................... 20 
44. Pinellas County, Fla ................... 21 
45. Other Authorized Beach Erosion 
Control Projects ........................ 21 
46. Beach Erosion Control Activities 
under Special Authorization ........... 21 
Flood Control 
47. Central and Southern Florida .......... 21 
48. Four River Basins, Fla ................ 23 
49. Portugues and Bucana Rivers, P.R .... 23 
50. Inspection of Completed Flood 
Control Projects ........................ 24 
51. Other Authorized Flood Control 
Projects .................................. 24 
52. Flood Control Work under Special 
Authorization ........................... 24 
General Investigations 
53. Surveys .................................. 24 
54. Collection and Study of Basic Data .... 24 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and also appear 
at the end of this chapter. 
9-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. AQUATIC PLANT CONTROL 
(R&H ACT OF 1965) 
Location. Navigable waters, tributary streams, 
connecting channels, and other allied waters in 
Florida. 
Existing project. The authorized project provides 
for control and progressive eradication of water 
hyacinth, alligatorweed, Eurasian water-milfoil, and 
other noxious aquatic plant growths from navigable 
waters, tributary streams, connecting channels, and 
other allied waters of the United States, in combined 
interest of navigation, flood control, drainage, agriculture, 
fish and wildlife conservation, public health, 
and related purposes, including continued research for 
development of most effective and economical control 
measures in cooperation with other Federal and 
State agencies in accordance with report of Chief of 
Engineers, House Document 251, 89th Congress, 1st 
session. The authorizing act provides that research 
and planning costs shall be borne fully by the United 
States. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must hold the 
United States free from damages that may occur from 
operations performed in connection with this project 
and contribute 30 percent of cost of operations. Compliance 
with requirements of local cooperation is on 
schedule. 
Operations and results during fiscal year. New 
work: There were 12,411 acres of hyacinth and/or 
water lettuce, 6,305 acres of hydrilla and 1,201 acres 
of minor plants controlled during the period. Costs incurred 
for engineering and design and supervision and 
administration were $183,960 and $32,989, respectively, 
and $1,973,341 for operations. 
Condition at end of fiscal year. Operations by the 
Corps and the State of Florida are in progress, water 
hyacinths within Florida are under maintenance control. 
Hydrilla is continuing to spread throughout the 
state and is causing major problems in some areas. 
2. ARECIBO HARBOR, P.R. 
Location. The harbor is located on the north shore 
of Puerto Rico about 40 miles west of San Juan Harbor. 
(See Coast and Geodetic Survey Chart No. 903.) 
Previous project. For details see page 504 of 1956 
Annual Report. 
Existing project. The project provides for a channel 
25 feet deep and 400 feet wide, with flare at entrance 
and widening at inner end to form a maneuvering 
area, and a stone breakwater 1,200 feet long. Place of 
reference is mean low water. Mean tidal range is 1.1 
feet. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non Federal contribution for new work was $288,000. 
Terminal facilities. A bulkhead wharf 688 by 220 
feet providing a deep water berthing space of approximately 
500 feet, and a 300 by 100 foot transit shed. 
Facilities are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition and operation studies for the year 
cost $10,979. Dredging by contract amounted to 
$326,870. Engineering and design and supervision 
and administration costs were $144 and $27,289, respectively. 
Condition at end of fiscal year. Project was completed 
in 1944. Breakwater was repaired in 1952. 
Wave action has since caused damage. Total Federal 
costs under existing project through September 30, 
1986 were $1,128,075 for new work and $4,286,232 
for maintenance, a total of $5,414,307. 
3. ATLANTIC INTRACOASTAL 
WATERWAY BETWEEN NORFOLK, 
VA. AND ST. JOHNS RIVER, FLA. 
(JACKSONVILLE DISTRICT) 
Location. That part of Intracoastal Waterway 
between southerly limit of Fernandina Harbor, 
Florida, at junction of Lanceford Creek and Amelia 
River, and St. Johns River, Fla. (See Coast and 
Geodetic Survey Chart No. 841-SC.) 
Previous project. For Details see page 605 of 1938 
Annual Report. 
Existing project. Channel 12, 90 to 150 feet wide 
from Fernandina Harbor to St. Johns River about 22 
miles long. Plane of reference is mean low water. 
Mean tidal range is 6 feet at Fernandina and 3.8 feet at 
St. Johns River. (See Table 9-B for Authorizing Legislation.) 
Existing project was authorized by River and Harbor 
Acts of 1913 (HD 898/62/2) and 1938 (HD 618/ 
75/3). 
Local cooperation. Fully complied with to date. 
Terminal facilities. There is a commercial marina 
located at Sisters Creek. No other facilities exist along 
this section of the waterway and none are currently 
required. 
Operations and results during fiscal year. Maintenance: 
Condition and operation studies for the year 
cost $153. Supervision and administrative costs were 
$19. 
Condition at end of fiscal year. Project was completed 
in 1941. Total costs under the existing project 
to September 30, 1986, have been $263,659 for new 
work and $5,300,742 for maintenance, a total of 
$5,564,401. 
9-2

JACKSONVILLE, FLA. DISTRICT 
4. BAKERS HAULOVER INLET, FLA. 
Location. The Harbor connects the Intracoastal 
Waterway and the Atlantic Ocean and is located 2 
miles north of Miami Beach in Dade County, 
Florida. 
Existing Project. The authorized project provides 
for an entrance channel 11x200 feet, thence 8x100 
feet to the Intracoastal Waterway, and a marina 
basin 8x200 feet. The length of the project is 1.02 
miles. Plane of reference is mean low water. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. The project was 
completed in December 1964. Project depths have 
been restored. 
5. CANAVERAL HARBOR, FLA. 
Location. The harbor is located on the east coast 
of Florida in Canaveral Bight, about 146 miles 
south of the entrance to Jacksonville Harbor and 69 
miles north of the entrance to Fort Pierce Harbor. 
(See Coast and Geodetic Survey Charts Nos. 456 
and 1245.) 
Existing project. The authorized project provides 
for maintenance of the 44-foot-deep entrance 
channel and 35-foot-depth turning basin; construction 
and operation of a sand transfer plant; relocation 
of the perimeter dike about 4,000 feet westward 
and extension of the harbor westward; two 
entrance jetties 100 feet long (constructed of native 
stone core and granite sides and cap); a lock; a 
channel and turning basin 31 feet deep near the 
relocated dike; and a barge canal 12 by 125 feet 
from the turning basin to the Atlantic Intracoastal 
Waterway. Plane of reference is mean low water 
(ocean) for harbor dike and lock, and mean low 
water (Banana River) for barge canal. The project is 
about 11.5 miles long. 
Mean tidal range is 3.5 feet at the entrance and 
practically non-tidal in Banana and Indian Rivers. 
(See Table 9-C for Data Relative to Lock.) 
Estimated cost (Oct. 1985) price levels) of the 
1962 modification to the project is $26,300,000 
Federal cost and $4,354,000 non-Federal cost 
($215,000 contributed funds and $4,139,000 other 
costs); $700,000 costs to NASA and $85,000 costs 
to U.S. Coast Guard. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must: provide 
all lands, rights-of-way, spoil-disposal areas, retaining 
dikes, and embankments; hold United States 
free from damages; provide and maintain four-lane 
bridge and roadway subject to Federal contribution 
of 65.3 percent of cost of constructing bridge and 
51.2 percent of constructing roadway; provide 
public terminal and transfer facilities; and make 
alterations as required in berthing facilities. For 
further details see Senate Document 140, 87th Congress, 
2nd session. Non-Federal contribution for 
new work is $1,106,000. 
Terminal facilities. Canaveral Harbor has 27 
commercial waterfront facilities. The General Cargo 
Facilities consist of 1,900 feet of usable berthing 
space and 5 transit sheds with a total shed storage 
space capacity of 168,000 square feet. The Oil Handling 
Facilities operate with 3,760 feet of usable 
berthing space and 22 storage tanks providing a 
total of 1,195,620 barrels of tank storage. Available 
warehouse storage includes 28,000 square feet of 
dry storage and 2,500,000 cubic feet of cold storage. 
Two hundred sixty-six acres of open storage is 
also available. 
Two cruise ship berths totaling 1200 feet long by 
41-foot depth and two 8800 square foot cruise 
terminals are also located on the south side. The 
western cruise ship berth is equipped with a roll on/ 
off ramp and is adjacent to 20 acres of trailer storage 
area. 
Hoisting facilities consist of one 45-ton floating 
crane and crawler and mobile cranes, with capacities 
from 70 to 200 tons, available from local crane 
rental services. There are two water-front marine 
repair facilities with the nearest drydock facilities 
located at Port Everglades and Jacksonville. Two 
tugs with ratings of 1,600 and 2,250 horsepower are 
also available. There is no rail service available at 
the port. The nearest rail service is the Florida East 
Coast Railway located 9 miles away. 
Facilities are considered adequate for existing 
commerce. (See Port Series #16, Rev. 1982.) 
Operations and results during fiscal year. New 
Work: Harbor extension contract underway at a cost 
of $2,620,923. Engineering and design and supervision 
and administration costs were $183,020 and 
$116,574, respectively. 
Maintenance: Maintenance and operation of locks 
amounted to $1,590,320 for the fiscal year. District 
communications network cost $24,000. Condition 
and operation studies for the year cost $73,531. 
Dredging of the Canaveral Harbor Entrance Channel 
by hopper dredge amounted to $1,798,418. 
Costs for the Natural Resource study were $30,584. 
Cost for operation of service facilities amounted to 
$7,143. Real estate management costs were $3,152. 
Costs for permanent operating equipment were $69. 
Acquisition costs were $4,968. Engineering and 
design and supervision and administration costs 
were $157,751 and $324,641, respectively. 
Condition at end of fiscal year. The existing 
project is about 82 percent coripleted. The perimeter 
dike and jetties are in good condition. 
Work remaining to complete the project is 
completion of the harbor extension and construction 
of the sand transfer plant. 
9-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
6. CHANNEL FROM NAPLES TO 
BIG MARCO PASS, FLA. 
Location. Naples Bay is on the southwestern side of. 
the Florida peninsula about 35 miles south of the 
mouth of the Caloosahatchee River and approximately 
1 mile inland and parallel to the Gulf of 
Mexico coastline. (See Coast and Geodetic Survey 
Chart No. 1254.) 
Existing project. The authorized project provides 
for an interior channel 6 by 70 feet from Naples to Big 
Marco Pass; a channel 12 by 150 feet from the Gulf of 
Mexico to Gordon Pass, thence 10 by 100-70 feet to a 
10-foot-depth turning basin in the upper Naples Bay; 
and an 8-foot-depth turning basin at the municipal 
yacht basin. Plane of reference is mean low water. 
Mean tidal range is 2.1 feet. (See Table 9-B for Authorizing 
Legislation.) 
For further details see Annual Report of 1962. 
Local cooperation. Fully complied with to date. 
Contributed funds for new work were $159,975. 
Terminal facilities. Four seafood packing houses, 4 
marine repair yards; a municipal pier and basin for use 
by recreational boats; and numerous private piers and 
slips for both commercial and recreational craft are 
available. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Condition and operation studies cost $24,740. 
Dredging cost was $537,704. Engineering and design 
and supervision and administration costs were $1,839 
and $62,387, respectively. 
Condition at end of fiscal year. The project is 
complete. 
7. CHARLOTTE HARBOR, FLA. 
Location. The Harbor is located on the west coast 
of Florida about 68 miles south of the entrance to 
Tampa Bay and 150 miles north of Key West. (See 
Coast and Geodetic Survey Chart No. 1255.) 
Previous projects. For details, see page 457 of 1959 
Annual Report. 
Existing project. The authorized project provides 
for a channel 32 by 300 feet, increased to 700 feet at 
the bend, from the Gulf of Mexico to Port Boca 
Grande, thence 10 by 100 feet from deep water at Port 
Boca Grande to and including a turning basin 200 feet 
square at the municipal terminal at Punta Gorda. Plane 
of reference is mean low water. The project is about 
29.5 miles long. 
Mean tidal range is one foot at Port Boca Grande 
and 1.4 feet at Punta Gorda. Extreme range is about 3 
feet at Port Boca Grande and 3.8 feet at Punta Gorda. 
Strong southwesterly winds raise water level about 
1.5 feet; strong northerly and easterly winds lower it 
about one foot. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local cooperation is fully 
complied with to date. Non-Federal contribution for 
new work was $15,563. 
Terminal facilities. Existing facilities consist of a 
phosphate wharf at Port Boca Grande and a municipal 
earthfill pier about 850 feet long at Punta Gorda, both 
open to the public. Railway connections are available 
at Port Boca Grande and highway and railway connections 
are available at Punta Gorda. There is a tank 
farm at Port Boca Grande for storage and rehandling 
of bunker fuel oil and numerous facilities are available 
in the area for docking and servicing small craft. Facilities 
are considered adequate for existing commerce. 
SOperations and results during fiscal year. Maintenance: 
Dredging cost was -$274,477. Condition and 
operation studies cost $93,517. District communications 
network costs were $10,000. Engineering and 
design and supervision and administration costs were 
$2,096 and $51,821, respectively. 
Condition at end of fiscal year. The project was 
completed in 1959. 
Total costs under existing project through 
September 30, 1986 have been $533,169 for new 
work and $11,487,983 for maintenance, a total of 
$12,071,152. In addition, $15,563 was expended 
from contributed funds for new work in Boca Grande 
entrance channel. 
8. CROSS FLORIDA BARGE CANAL 
Location. The proposed canal extends up the St. 
Johns River, past Palatka, thence up the valley of the 
Oklawaha River across the divide south of Ocala, and 
down the valley of the Withlacoochee River to the 
Gulf of Mexico, about 95 miles north of Tampa, Florida. 
Existing project. The authorized project provides 
for a lock canal with project depth of 12 feet and a 
minimum bottom width of 150 feet, with five locks 
and two earth dams. Project including the section in 
the St. Johns River is 184 miles long. (See Table 9-D 
for Locks and Dams.) 
Operation and maintenance of the locks and dams is 
a Federal responsibility. Estimated cost of new work 
(1970) is $179,000,000 Federal, and $19,500,000 
non-Federal for lands, rights-of-way, and other costs. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must furnish 
lands and rights-of-way for construction of canal; hold 
the United States free from damages; and operate and 
maintain all highway bridges and roadways built in 
connection with project. 
Terminal facilities: None. 
Operations and results during fiscal year. (See 
Table 9-E for work accomplished.) 
9-4

JACKSONVILLE, FLA. DISTRICT 
Regulation. 
a. Lake Ocklawaha. During the period the lake 
continued to be regulated at 18.0 feet, NGVD by discharging 
through the Rodman spillway. 
b. Lake Rousseau. During the period, the lake continued 
to be regulated at 27.5 ft., NGVD by discharging 
through the Inglis Main and Bypass Spillways. 
Condition at end of fiscal year. Construction of 
project commenced February 25, 1964, and is 36 percent 
completed. Inglis Lock, Dam, and Spillway; 
Rodman Dam and Spillway, Eureka Lock, Dam, and 
Spillway; Henry H. Buckman Lock; and canal from 
Palatka to Lake Ocklawaha and from Withlacoochee 
River to Gulf of Mexico, including Inglis Bypass 
Channel, are completed. Construction work on the 
project was terminated in FY 1971 by order of the 
President. A restudy report and environmental impact 
statement were completed in February 1977. 
9. EAU GALLIE HARBOR, FLA. 
Location. The Harbor is located on Indian River 
about midway of the State of Florida, 176 miles south 
of Jacksonville Harbor and 174 miles north of Miami 
Harbor. 
Existing project. The authorized project provides 
for a channel 8 x 100 feet from Indian River to and 
including a 300 x 600-foot turning basin in Eau Gallie. 
The project is about 2,000 feet long. Plane of reference 
is mean low water. The harbor is almost nontidal. 
Local cooperation. Fully complied with to date. 
Terminal facilities. A privately owned boatyard in 
Eau Gallie Harbor provides more than 600 feet of 
docking space used chiefly by pleasure boats. There 
are also two marine railways and repair and storage 
facilities available. The facilities are considered 
adequate for the present needs of navigation. 
Operations and results during fiscal year. Maintenance: 
Dredging by contract cost $133,833. Engineering 
and design and supervision and administration 
costs were $1,098 and $67,693, respectively. 
Condition at end of fiscal year. The project was 
completed in 1939. In December 1982, the controlling 
depth of the channel was 5 feet. 
10. FERNANDINA HARBOR, FLA. 
Location. Entrance to the harbor is located on the 
northeast coast of Florida about 95 miles south of the 
entrance to Savannah Harbor, Georgia, and 22 miles 
north of the entrance to Jacksonville Harbor, Florida. 
(See Coast and Geodetic Survey Chart No. 453.) 
Existing project. The authorized project provides 
for a 32-foot-depth channel (maximum channel in active 
status; 28 feet) generally 300-400 feet wide from 
deep water in the ocean to the junction of Lanceford 
Creek with Amelia River; an 800-foot-wide turning 
basin at the first bend below Lanceford Creek; and two 
jetties, 19,150 and 11,200 feet long. Plane of reference 
is mean low water. The project is 7 miles long. 
Mean tidal range is 5.8 feet on the bar and 6 feet in the 
inner harbor. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-federal contribution for new work was 
$812,000. 
Terminal facilities. There are two large wharves 
operated by industrial plants; twelve wharves serving 
fishing boats, recreational craft, and other vessels; 
three oil handling wharves with pipelines; and a Municipal 
Marine and Sportsman's Wharf with public 
facilities for small craft. Total berthing space is approximately 
4,065 feet. Most terminals are served by 
rail, and all have highway access. Facilities are considered 
adequate for existing commerce. (See Port 
Series No. 16 (Part 2), 1964.) 
Operations and results during fiscal year. New 
work: Engineering and design costs $17,575. 
Maintenance: Dredging cost $436,036. Condition 
and operation studies cost $72,157. District communications 
network costs were $12,000. Real estate 
management costs $1,682. Engineering and design 
and supervision and administration costs were 
$21,355 and $51,159, respectively. 
Condition at end of fiscal year. The active portion 
of the existing project is complete. Jetties are in poor 
condition and are badly in need of repair. Remaining 
work is to deepen the inner harbor channel and turning 
basin to 32 feet when and if the presently inactive 
1950 authorization is reactivated. The entrance 
channel has been deepened to 40 feet for the Kings 
Bay project. 
11. FORT MYERS BEACH, FLA. 
Location. Fort Myers Beach is on Estero Island 
near the mouth of the Caloosahatchee River, about 20 
miles below Fort Myers and 110 miles south of Tampa, 
Florida. (See Coast and Geodetic Survey Charts 
Nos. 855-SC and 1255.) 
Existing project. The authorized project provides 
for a channel 12 by 150 feet from that depth in San 
Carlos Bay into Matanzas Pass, thence 11 by 125 feet 
in Matanzas Pass to and including a turning basin 
2,000 feet upstream from the upper shrimp terminals. 
Plane of reference is mean low water. Project is 2.5 
miles long. 
Mean tidal range is 1.7 feet. Spring range is about 
2.3 feet. Strong northerly winds lower the water surface 
1 to 2 feet; strong southerly winds have an opposite 
effect. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was $1,095. 
Terminal facilities. There are three shrimp- 
9-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
packing houses and several fish-packing houses, two 
marine railways, a fuel terminal and an ice manufacturing 
plant in the area. There are several commercial 
facilities for servicing shrimp boats. Recreation-craft 
facilities include nine marinas, a boat motor testing 
laboratory which is closed, and numerous privately 
owned piers and wharves. All terminals have highway 
access. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition and operation studies cost $34,904. 
Dredging cost $278,725. Engineering and design and 
supervision and administration costs were $2,303 
and $61,457, respectively. 
Condition at end of fiscal year. The project is 
complete. 
12. FORT PIERCE HARBOR, FLA. 
Location. On east coast of Florida, about 218 
miles south of entrance to St. Johns River and about 
124 miles north of entrance to Miami Harbor. (See 
Coast and Geodetic Survey Chart No. 582.) 
Existing project. A channel 350 feet wide at the 27- 
foot contour in the ocean, tapering to a width of 200 
feet at Sta. 100+00, thence 200 feet wide to Sta. 
30 + 00, and thence flaring to a turning basin 900 feet 
wide. Entrance channel is 27 feet deep to Sta. 130 + 
00 and thence 25 feet deep to and including the tumrning 
basin. Project includes the maintenance of two jetties 
and shore revetments at the inlet. Length of project is 
about 3.5 miles. 
Mean tidal range is 2.6 feet at the entrance and 0.7 
foot at terminals. (See Table 9-B for Authorizing 
Legislation.) 
For further details see 1961 Annual Report. 
Local Cooperation. Fully complied with to date. 
Non-Federal contribution for new work was 
$18,574. 
Terminal facilities. Two earth-filled piers forming 
a slip 200 feet by 300 feet, with bulkhead wharf at 
inner end, affording berthing space of about 1,653 
feet. The south pier and bulkhead wharf are municipally 
owned. Facilities also include a cooling plant, a 
warehouse and a fruit packing house. The north pier 
is served by railway and both piers by highway connections. 
North of the turning basin local interests 
have provided deep-draft berthing and pier facilities. 
Also available is a bulkhead wharf with a depth of 25 
feet with ample room for open storage and with tank 
storage for petroleum in the rear. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition and operation studies cost $66,981. 
Engineering and design and supervision and administration 
costs were $12,622 and $23,526, respectively. 
Condition at end of fiscal year. The project was 
completed in 1938 except for the fishing walkway 
atop the south jetty which was completed by local interests 
in 1968. Local interests installed lighting atop 
the jetty in 1969. 
The south jetty and revetments are in good condition. 
The north jetty is scheduled for repair in FY 87. 
13. INTRACOASTAL WATERWAY, CALOOSAHATCHEE 
RIVER TO ANCLOTE 
RIVER, FLA. 
Location. The Waterway extends from the mouth 
of the Caloosahatchee River at Punta Rassa, Florida, 
to the mouth of the Anclote River, Florida, following 
in general an almost continuous series of protected 
inside waterways along the gulf coast of Florida. 
(See Coast and Geodetic Survey Charts Nos. 856- 
SC, 857-SC, and 858.) 
Previous projects. For details see page 767 of 
1945 Annual Report. 
Existing project. The authorized project provides 
for a channel 9 by 100 feet from Caloosahatchee 
River to Anclote River; deepening the existing 
channel at Caseys Pass to 9 feet; a channel 6 by 80 
feet (Cats Point Channel) along the southeastern side 
of Boca Ciega Bay past Frenchman Creek and Gulfport; 
maintenance of bulkheads, revetments, and two 
jetties built at Caseys Pass under previous project; 
and improvement and maintenance of Sunshine Skyway 
Channel. Plane of reference is mean low water. 
The project includes about 160 miles of channels. 
Mean ranges of tide are 1.7 feet at Punta Rassa, 1 
foot at Port Boca Grande, 1.4 feet in Tampa Bay at 
Anna Maria, and 2 feet at entrance to Anclote River. 
Extreme ranges are about 4.5 feet at Punta Rassa, 
about 3 to 4 feet between Port Boca Grande and 
Corey Causeway over Boca Ciega Bay, and about 
5.5 feet at entrance to Anclote River. Southerly 
winds over the area generally raise water level by I 
to 1.5 feet; northerly winds lower water level by 1 to 
2 feet. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was 
$14,473. 
Terminal facilities. Existing facilities include one 
municipal concrete pier, one railway pier, one freight 
wharf, one marginal wharf 500 feet long on terminal 
island, and eleven privately owned landings, all at 
Sarasota. Municipal pier and freight wharf are open 
to the public. All piers have highway connections. 
There are six wharves along Boca Ciega Bay and a 
number of small privately owned piers and wharves 
at various points along waterway for use of commercial 
fishing boats and recreational craft. Facilities are 
considered adequate for existing commerce. 
9-6

JACKSONVILLE, FLA. DISTRICT 
Operations and results during fiscal year. Maintenance: 
Maintenance of channel slopes and berms cost 
$12,254. Removal of sunken vessels by hired labor 
cost -$800. Real estate audits and administration costs 
were $7,350. Acquisition costs were $8,456. Permanent 
equipment costs were $3,642. Bridge maintenance 
costs were $1,415. District communications 
network cost $18,000. Condition and operation 
studies cost $41,744. Supervision and administration 
costs were $6,606. 
Condition at end of fiscal year. Existing project is 
complete. A contract to maintain the jetties at Casey's 
Pass was completed in 1983. 
Total Federal costs under existing project through 
September 30, 1986 were $7,597,078 for new work 
and $5,426,807 for maintenance, a total of $13,023,- 
885. In addition, $14,473 contributed funds were expended 
for Sunshine Skyway and Boca Ciega Bay 
channels. 
14. INTRACOASTAL WATERWAY, JACKSONVILLE 
TO MIAMI, FLA. 
Location. The waterway extends from Jacksonville 
to Miami, Florida, following the St. Johns River to the 
mouth of Pablo Creek and thence following in general 
an almost continuous series of protected inside waterways 
along the Atlantic coast of Florida to Miami. 
(See Coast and Geodetic Survey Charts Nos. 841-SC, 
843-SC, 845-SC, and 847-SC.) 
Previous projects. For details, see pages 618-619 
of 1938 Annual Report. 
Existing project. The authorized project provides 
for a channel 12 by 125 feet from Jacksonville to 
Miami, modified to 10-foot-depth from Fort Pierce to 
Miami by Chief of Engineer's report of July 22, 1960; 
side channels at Sebastian and Daytona Beach and 
turning basins at Sebastian and Vero Beach, all to an 
8-foot-depth; and operation and maintenance of the 
Palm Valley highway bridge. Project is 370 miles 
long, including 21 miles in Jacksonville Harbor. 
Mean range of the tide is 3.8 feet at St. Johns River, 
0.7 foot in the Indian River at Fort Pierce, 1.8 feet in 
Lake Worth at Port of Palm Beach terminals, 2.3 feet 
at the Port Everglades terminals, and 2 feet in Biscayne 
Bay. The extreme range is about 7 feet at St. 
Johns River, 1.5 feet at Fort Pierce, and 3 feet in 
Biscayne Bay. Plane of reference is mean low water. 
Tidal effect is imperceptible at points along waterway 
distant from inlets. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. There are a number of privately 
owned piers, wharves, and landings at various points 
along waterway. Terminals with railway connections 
are available at Jacksonville, Fort Pierce, West Palm 
Beach, Port Everglades, and Miami. Municipal piers 
or wharves have been constructed at Titusville, Cocoa, 
Melbourne and Vero Beach for handling general 
freight and at St. Augustine, Daytona Beach, New 
Smyrna Beach, Eau Gallie, West Palm Beach, Delray 
Beach, Fort Lauderdale, and Miami for use of recreational 
craft. Yacht basins, open to the public, have 
been provided at Jacksonville Beach, Daytona Beach, 
Titusville, Eau Gallie, Vero Beach, Fort Pierce, West 
Palm Beach, Fort Lauderdale, Hollywood, and Miami. 
Facilities are considered adequate for existing 
commerce. (For further details on facilities at Jacksonville, 
see Port Series No. 15, 1969, and at Palm 
Beach, Port Everglades, and Miami, see Port Series 
No. 16, Revised 1972.) 
Operations and results during fiscal year. Maintenance: 
The cost of dredging was $20,867. District 
communications network cost $18,000. Permanent 
operating equipment cost $11,919. Condition and 
operation studies cost $73,597. Real estate management 
cost $14,785. Acquisition costs were $9,488. 
Engineering and design and supervision and administration 
costs were $236,788 and $25,766, respectively. 
Operation and care: The highway bridge near Palm 
Valley was operated and maintained at a cost of 
$64,489. 
Condition at end offiscal year. The existing project 
as modified by the Chief of Engineers is complete except 
for construction of the channel and turning basin 
at Sebastian, Florida, which is in an inactive status. 
Total Federal costs under existing project through 
September 30, 1986, were $19,156,822 for new 
work: $26,194,217 for maintenance, a total of 
$45,351,039 regular funds. In addition, $2,199,842 
has been expended from public works funds for new 
work. 
15. JACKSONVILLE HARBOR, FLA. 
Location. The authorized project comprises the 
lower 24.9 miles of St. Johns River which empties 
into the Atlantic Ocean near the northeasterly corner 
of the Florida peninsula. (See Coast and Geodetic 
Survey Chart No. 636-SC.) 
Previous projects. For details, see page 607 of 
Annual Report, 1938. 
Existing project. The authorized project provides 
for a channel 38 by 400--1,200 feet from the ocean to 
mile 20 via Dame Point-Fulton Cutoff, thence 34 
feet to Commodore Point, and thence 30 feet deep to 
the F.E.C. Railway bridge at Jacksonville, including 
a 30-foot channel in Arlington Cut and in the Old 
Dame Point-Fulton Channel; maintenance of the existing 
42 and 400-foot-depth entrance channel; maintenance 
of jetties at channel entrance; and construction 
of training walls and revetments. Plane of reference is 
mean low water. The project is about 26.8 miles long. 
9-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Mean tidal range is 5.3 feet on the bar, 4.9 feet at 
Mayport, 2.6 feet at Dame Point, and I .1 feet at Jacksonville. 
The extreme range varies from about 9 feet 
on the bar to about 1.5 feet at Jacksonville. Strong 
northeasterly winds raise the water level about 2 feet 
at Mayport and Jacksonville. Strong southwesterly 
winds lower the water about 1.5 feet at Mayport and 1 
foot at Jacksonville. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests have fully 
complied with requirements of local cooperation for 
work performed to date. For work authorized by the 
1965 River and Harbor Act, local interests were required 
to contribute 2.6 percent of the contract price 
plus supervision and administration for work provided, 
by the Corps; provide all lands and rights-of-way; 
save the United States free from damages; and provide 
and maintain public terminal and transfer facilities. 
Assurances of local cooperation for this work were accepted 
February 11, 1966. 
Terminal facilities. Jacksonville Harbor has 84 
waterfront facilities. Available at the General Cargo 
Facilities are 11,140 feet of usable berthing space and 
12 transit sheds with a total storage space of 1,009,- 
800 square feet. The Oil Handling Facilities consist of 
7,843 feet of usable berthing space and 179 storage 
tanks providing a total of 8,478,900 barrels of tank 
storage. Warehouse storage at the port includes 3,- 
266,900 square feet of dry storage and 4,071,100 
cubic feet of cold storage. Available open storage is 
223 acres. 
Four fixed cranes with capacities from 40 to 100 
tons are located at the port. Available locally are 
crawler and truck cranes with capacities up to 100 
tons. Various phases of marine repair work are accomplished 
by 7 waterfront repair facilities and 
numerous other companies located offwater. Drydock 
facilities consist of 6 floating drydocks with capacities 
from 800 to 33,000 tons. Floating equipment includes 
25 tugs with up to 3,300 horsepower and 16 tank 
barges with capacities up to 20,700 barrels. Three 
major railroads furnish rail service from port docks to 
all points outside of Jacksonville. 
Facilities are considered adequate for existing 
commerce. (See Port Series #15, Rev. 1978.) 
Operations and results during fiscal year. Maintenance: 
Operation and maintenance of district communications 
network cost $12,000. Condition and operation 
studies cost $102,593. Real estate audits cost 
$6,003. Acquisition costs were $8,057. Maintenance 
dredging costs were $10,000. Jetty maintenance costs 
were $339,521. Engineering and design and supervision 
and administration costs were $225,813 and 
$77,033, respectively. 
Condition at end of fiscal year. Construction of the 
modification to the project, authorized by 1965 River 
and Harbor Act, is completed. The north jetty is in fair 
condition and partially submerged at high tide. The 
south jetty was repaired in FY 1985 to prevent further 
damage to the Mayport Naval Station. Revetments 
and retaining walls were in poor condition. 
Total Federal costs under existing project through 
September 30, 1986 were $43,786,128 for new work, 
$54,956,799 for maintenance, a total of $98,742,927 
regular funds. In addition $290,013 has been expended 
from public works funds for new work. 
16. JOHNS PASS, FLA. 
Location. A natural inlet on the west coast of 
Florida connecting Boca Ciega Bay with Gulf of Mexico. 
The pass is located about 8 miles northwest of 
lower Tampa Bay directly across Boca Ciega Bay 
from St. Petersburg, Fla. (See Coast and Geodetic 
Survey Chart No. 1257.) 
Existing project. Channel 10 by 150 feet in the gulf, 
thence 8 by 100 feet inside pass, and 6 by 100 feet to 
the Intracoastal Waterway, and suitable protective 
measures over a frontage of approximately one 
thousand linear feet of shore along the north end of 
Treasure Island. Plane of reference is mean low 
water. Mean range of tide is 1.5 feet. Project is about 
2.6 miles long. 
Project was authorized December 2, 1964 by Chief 
of Engineers under Section 107 of the 1960 River and 
Harbor Act and by Section 110 of the 1966 River and 
Harbor Act. 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was $53,732. 
Terminal facilities. Only small marinas and repair 
yards for recreational craft in the general vicinity. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Dredging costs were $252,516. Condition and 
operation studies cost $640. Engineering and design 
and supervision and administration costs were $200 
and $15,879, respectively. 
Condition at end of fiscal year. Project was completed 
in 1968. 
17. LONGBOAT PASS, FLA. 
Location. Longboat Pass is located on the west 
coast of Florida about 11 miles northwest of Sarasota 
and 23 miles south of St. Petersburg. Located in Manatee 
County, it is one of several natural inlets connecting 
Sarasota Bay, a tidal estuary, with the Gulf of 
Mexico. (See Coast and Geodetic Survey Chart No. 
1256). 
Existing project. The authorized project provides 
for an entrance channel 12 by 150 feet from the Gulf to 
Longboat Pass Bridge, thence a channel 10 by 100 
feet from Longboat Pass Bridge along a north to 
northeasterly alinement to the Intracoastal Waterway 
and extending along Intracoastal Waterway to Cortez 
Bridge. The mean tidal range is 2.2 feet and the maxi- 
9-8

JACKSONVILLE, FLA. DISTRICT 
mum tidal range is about 5 feet. Currents are predominantly 
tidal. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. See 1978 
Annual Report for detailed local cooperation requirements. 
Contributed funds for new work were 
$173,324. 
Terminal facialities. From Sarasota north to Tampa 
Bay there are about 28 small craft facilities including 
marinas, boat repair yards, and boat basins along the 
Intracoastal Waterway. Nine of them are located 
within 2 miles of Longboat Pass. Numerous private 
mooring piers and wharves also exist in the area. The 
marina and repair facilities appear adequate for the 
general boating needs of the area. 
Operations and results during fiscal year. Maintenance: 
Dredging costs were $211,493. Condition and 
operation studies cost $12,322. Supervision and 
administration costs were $21,586. 
Condition at end of fiscal year. Construction of the 
project is complete. 
18. MAYAGUEZ HARBOR, P.R. 
Location. The project is on the west coast of Puerto 
Rico, about 110 miles by water from San Juan Harbor. 
(See Coast and Geodetic Survey Chart No. 931.) 
Existing project. The authorized project provides 
for a 30 by 1,000 foot approach channel to the deep 
water terminal, decreasing to a 500 foot width opposite 
westerly end of terminal, thence the same width to 
easterly end of terminal. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. A modern deep water terminal 
is located in the northeast section of the harbor consisting 
of a bulkhead wharf about 1,270 feet long with a 
storage transit shed 800 by 60 feet immediately shoreware. 
The Puerto Rico Industrial Development Company, 
an agency of the Commonwealth of Puerto 
Rico, owns a bulkhead wharf of about 200 feet in line 
with the existing deep water terminal plant located 
within the industrial harbor area. In addition, Bumble 
Bee Packing Company, Inc., owns and operates a 
dock of about 200 feet for docking tuna fish boats. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Condition and operation studies cost $366. 
Engineering and design costs were $45. 
Condition at end of fiscal year. Project was completed 
in 1934. 
19. MELBOURNE HARBOR, FLA. 
Location. The project is on Indian River about midway 
of the State of Florida, 179 miles south of Jacksonville 
Harbor and 171 miles north of Miami Harbor. 
Existing project. The authorized project provides 
for a channel 8 x 100 feet from Indian River to a 400 x 
800-foot turning basin in Crane Creek. Project is 
about 3,150 feet long. Plane of reference is mean low 
water. The harbor is almost non-tidal. 
Terminal facilities. The Municipal Marina on the 
north end of the turning basin has a 350-foot steel 
bulkhead with eleven finger piers about 40 feet long 
each. There are also two privately owned storage and 
repair facilities and several privately owned boathouses 
and docks. The facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Dredging costs $196,104. Engineering and 
design and supervision and administration costs were 
$1,272 and $54,812, respectively. 
Condition at end of fiscal year. The project was 
completed in 1938. As of September 1984 channel 
depths as authorized were available throughout the 
project. 
20. MIAMI HARBOR, FLA. 
Location. Miami is near the northern end of 
Biscayne Bay, about 71 miles south of the entrance to 
Palm Beach Harbor. Miami River has its source in the 
Everglades and flows southeasterly to enter Biscayne 
Bay at Miami. (See Coast and Geodetic Survey Charts 
Nos. 547 and 1248.) 
Existing project. The authorized project provides 
for a 38 by 500-foot channel from the ocean to the 
outer end of the north jetty, thence 36 by 400 feet 
through the entrance and across Biscayne Bay to and 
including a turning basin at the municipal terminals; a 
36-foot depth turning basin at Fisher Island; two 
rubblestone jetties at the entrance; a channel 15 by 200 
feet from the mouth of Miami River to the turning 
basin at the municipal terminals; a channel 8 by 200 
feet from the mouth of the Miami River to the Intracoastal 
Waterway and thence 100 feet wide to Government 
Cut; a channel 15 feet deep in Miami River 
varying in width from 250 feet at mouth to 90 feet inland; 
and a channel 12 by 100 feet from Miami to a 
harbor of refuge in Palmer Lake. Plane of reference is 
mean low water, except for 15-foot channel in Miami 
River where depths are based on flood conditions. Total 
length of the project is about 15.3 miles. 
Mean tidal variation is 2.5 feet at entrance and 2 
feet in the bay. Extreme variation is about 4.5 feet at 
entrance and 3 feet in Biscayne Bay. Strong easterly 
winds raise the water level about 1.5 feet at entrance 
and 1 foot in the bay. Strong westerly winds lower 
water level about 1 foot at entrance and about 0.5 foot 
in the bay. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. See 1978 
Annual Report for detailed local cooperation requirements. 
9-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Assurances of local cooperation for the 1968 modification 
to the project were accepted December 18, 
1968. 
Terminal facilities. There are 91 commercial 
waterfront facilities serving the port. The General 
Cargo Facilities include 21,373 feet of usable berthing 
space, 13 transit sheds with a total capacity of 474,300 
square feet, and 9 freight stations with a total storage 
capacity of 270,400 square feet. Oil Handling Facilities 
consist of 2,714 feet of usable berthing space and 
36 storage tanks with a total storage capacity of 
744,475 barrels. Available warehouse storage includes 
dry storage at 1,450,500 square feet and cold 
storage at 11,204,000 cubic feet. There are 117.1 
acres of open storage at the port. 
Hoisting Facilities located at the port include two 
40-ton cranes and cranes with capacities up to 200 
tons available thru local rental. Twelve waterfront 
repair yards and two offwater yards serve the port. 
Drydock facilities available include 7 marine railways 
and 4 boat lifts with haulout capacities raning from 40 
to 1,000 tons and lifting capacities ranging from 70 to 
500 tons. Nine tugs, with ratings up to 3,000 horsepower, 
and thirteen tank barges, with capacities up to 
35,000 barrels, are also available. Rail Facilities at the 
port are served by the Seaboard Coast Line and the 
Florida East Coast Railway. 
Facilities are considered adequate for existing 
commerce. (See Port Series #16, Rev. 1982.) 
Operations and results during fiscal year. New 
work: Contract for recreation facilities at Bay Front 
Park underway cost $3,643,320. Engineering and design 
and supervision and administration costs were 
$81,417 and $146,549, respectively. 
Maintenance: Condition and operations studies cost 
$104,108. Contract dredging cost $57,625. Real estate 
management cost $3,265. Acquisition costs were 
$3,882. Engineering and design and supervision and 
administration costs were $2,732 and $536 respectively. 
Condition at end of fiscal year. Construction of the 
modification to the project, authorized by River and 
Harbor Act of 1968, is complete. South and north jetties 
are in good condition. 
21. NEW PASS, SARASOTA, FLA. 
Location. Sarasota Bay is a tidal lagoon along the 
west coast of Florida immediately south of Tampa 
Bay. New Pass is a gulf inlet across the bay from 
Sarasota, Fla. (See Coast and Geodetic Survey Chart 
No. 857-SC.) 
Existing project. The authorized project provides 
for an entrance channel 10 feet deep and 150 feet wide 
in the Gulf of Mexico diminishing to 8 by 100 feet 
through New Pass and extending across Sarasota Bay 
to the Intracoastal Waterway with side channels to, 
and turning basins at, Payne Terminal and city pier. 
Place of reference is mean low water. Mean range of 
tide is 1.3 feet in Sarasota Bay; mean spring range is 
1.7 feet. Project is about 4 miles long. (See Table 9-B 
for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work amounted to 
$45,811. 
Terminal facilities. Consists of Payne Terminal, a 
slip 200 by 650 feet, and a city pier, 400 feet long with 
two finger piers equipped with adequate facilities at 
each location. 
Operations and results during fiscal year. Maintenance: 
Condition and operations studies cost $1,702. 
Dredging costs were $58,287. Engineering and design 
and supervision and administration costs were 
$1,721 and $8,955, respectively. 
Condition at end of fiscal year. Project was completed 
in 1964. 
22. OKEECHOBEE WATERWAY, FLA. 
Location. The waterway traverses the southern part 
of the Florida peninsula via the Caloosahatchee River, 
Lake Okeechobee, and St. Lucie Canal, connecting 
coastal waterways along the Gulf and Atlantic Shores. 
(See Coast and Geodetic Survey Charts Nos. 11428 
and 11427.) 
Previous projects. For details, see page 785 of 1949 
Annual Report. 
Existing project. The authorized project provides 
for replacing the old locks on the St. Lucie Canal by a 
single new lock; a channel 10 by 100 feet from Ft. 
Myers for about 5 miles upstream, thence 8 by 80 to 
100 feet to the Intracoastal Waterway, Jacksonville to 
Miami; near Stuart; an 8-foot depth basin at Stuart; a 
side channel at Ft. Myers; operation and care of St. 
Lucie Lock; and maintenance of features completed 
under previous projects as follows: a 12 by 200-foot 
channel from the Gulf to Punta Rassa, thence 10 by 
100 feet to Fort Myers with a 10-foot depth basin at 
Fort Myers; a 6 by 80-foot channel along the south 
shore of Lake Okeechobee from Clewiston to St. 
Lucie Canal; a 6 by 60-foot channel in Taylor Creek 
from the town of Okeechobee to the Lake; and operation 
and care of Moore Haven and Ortona Locks. 
(See Table 9-B for Authorizing Legislation.) 
For further details see 1962 Annual Report. 
Local cooperation. Fully complied with for 
completed portion of project. Non-Federal contribution 
amounted to $503,700. 
Terminal facilities. There are 3 freight piers, I 
municipal recreation pier, 4 privately owned piers, 
and a municipal yacht basin on the Caloosahatchee 
River near Fort Myers. The Corps has provided a boat 
basin, launching ramp, and a 120-foot wharf on the 
Caloosahatchee River about one-quarter mile 
9-10

JACKSONVILLE, FLA. DISTRICT 
below Ortona Lock. There are tie-up dolphins above 
and below all 5 locks. Commercial yacht basins are 
provided on the south side of the Caloosahatchee 
River about halfway between Ortona and Moore 
Haven Locks and about 3 miles east of LaBelle. A 
commercial/municipal yacht basin is provided on the 
north side of the St. Lucie Canal at Indiantown. 
There are numerous small wooden-pile landings 
along the Caloosahatchee River on St. Lucie Canal, 
and on the St. Lucie River, including one railroad 
terminal pier, a municipal pier, and a pier for handling 
petroleum products at Stuart. Also, 550 feet of 
wharves have been provided on the west side of Taylor 
Creek immediately landward of Hurricane Gate 
No. 6 and 150 feet on the east side of the creek. A 
yacht basin has been provided on the west side of the 
creek immediately landward of the hurricane gate. 
The installations of Taylor Creek are privately owned, 
but are open to the public. A breakwater protected 
harbor is available at Pahokee. There is a 440-foot 
marginal wharf on the Industrial Canal at Clewiston; a 
125-foot wharf at LaBelle; a 150-foot wharf at Belle 
Glade; a 125-foot wharf at Moore Haven; a 50-foot 
wharf at Alva; and a 30-foot wharf on Taylor Creek at 
the town of Okeechobee. A docking facility for loading 
raw sugar was constructed in 1967 on Herbert 
Hoover Dike near Belle Glade. All have highway and/ 
or railway connections. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. (See 
Table 9-F for work accomplished.) 
Condition at end of fiscal year. The project is 
complete except for providing the 8-foot depth basin 
at Stuart, which is inactive. 
Total Federal costs under the existing project 
through September 30, 1986 were $5,178,315 for 
new work, $23,879,736 for maintenance ($67,558 
excluded which represents services rendered without 
reimbursement) a total of $29,058,051. 
23. OKLAWAHA RIVER, FLA. 
Location. The river has its source in a system of 
large lakes in the central part of the Florida peninsula 
and flows generally northerly, then easterly, emptying 
into the St. Johns River 22 miles above Palatka. The 
extreme head of the system is considered to be Lake 
Apopka, 120 miles above the river's mouth. 
Previous projects. For details, see page 613 of 1938 
Annual Report. 
Existing project. The authorized project provides 
for a channel 6 feet deep from the river mouth to the 
head of Silver Springs Run; clearing a channel to Lake 
Griffin; maintaining dikes to obtain a navigable depth 
of about 4 feet to Leesburg and construction of a lock 
and dam at Moss Bluff. The project length is about 
85.7 miles in the river and 5.4 miles in Silver Springs 
Run. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. Several private and public landings 
and boat-launching ramps are located along the 
river. Public recreation-craft basins and boat launching 
ramps are near Silver Springs and State Road 40 
and 316 bridges. There is a municipal wharf on Lake 
Griffin at Leesburg. A dam has created Lake Ocklawaha 
(13,000 acres) with egress to the St. Johns River 
through Buckman Lock. Along the lake are 4 launching 
ramps; Payne's Landing, Orange Springs, Kenwood 
Landing,and Rodman Recreation Area. Access 
below the dam is at the Oklawaha Boat launch ramp 
and at State Road 19. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Channel maintenance costs were $33,333. 
Real estate management costs were $8,888. Supervision 
and administration costs were $5,360. 
Condition at end of fiscal year. The project is 
complete except for providing a 6-foot depth channel 
from the mouth of the river to the head of Silver 
Springs run, which is in an inactive status. The Moss 
Bluff lock and dam structure was replaced under the 
Four River Basins, Fla., flood control project. 
Total Federal costs under the existing project 
through September 30, 1986 have been $311,352 for 
new work and $2,044,552 for maintenance, a total of 
$2,355,904. 
24. PALM BEACH HARBOR, FLA. 
Location. The authorized project is located on the 
east coast of Florida about 71 miles north of the entrance 
to Miami Harbor and about 264 miles southeasterly 
from the entrance to Jacksonville Harbor. 
(See Coast and Geodetic Survey Charts Nos. 291 and 
1248.) 
Existing project. The authorized project provides 
for an entrance channel 35 by 400 feet merging with 
an inner channel 33 by 300 feet to and including a 
turning basin; tank revetment; and restoring jetties. 
Plane of reference is mean low water. The project is 
about 1.6 miles long. 
Mean range of tide in the ocean at the entrance is 
2.8 feet and at the turning basin, 2.2 feet. Extreme 
range of tide is about 4.5 feet at the inlet and 3 feet at 
the terminals. Seven-foot tidal ranges have occurred 
during storms. For details, see 1962 Annual Report. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
For requirements, see 1961 Annual Report. Non- 
Federal contribution for new work was $509,506. 
Terminal facilities. The port has 13 commercial 
9-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
waterfront facilities. The General Cargo Facilities include 
5,156 feet of usable berthing space and 6 
transit sheds with a total of 118,030 square feet storage 
capacity. The Oil Handling Facilities consist of 
10 storage tanks with a total capacity of 2,029,600 
barrels. Usable berthing space in not available at the 
Oil Handling Facilities. Dry storage is available at 
150,500 square feet, cold storage at 19,200 cubic 
feet and open storage at 27.1 acres. 
Seven cranes with capacities from 15 to 230 tons 
are located at the port. There are no floating cranes, 
repair facilities or drydock facilities located at the 
port. A 100 ton vertical boat lift is located on the Intracoastal 
Waterway south of the port for heavy lifts. 
Two tugs with ratings of 900 and 1000 horsepower 
are available. The Palm Beach Belt Line which connects 
with the Florida East Coast Railway serves the 
port. 
Facilities are considered adequate for existing 
commerce. (See Port Series #16, Rev. 1982.) 
Operations and results during fiscal year. Maintenance: 
Management of natural resources cost 
$3,750. Condition and operation studies for the 
project totaled $44,734. Contract for jetty maintenance 
cost $545,196. Real estate management costs 
were $4,735. Engineering and design and supervision 
and administration costs were $78,126 and 
$34,843, respectively. 
Condition at end of fiscal year. The Project was 
completed in 1967. Jetties and revetments are in need 
of repair. The south jetty was completed in FY 86. 
25. PONCE DE LEON INLET, FLA. 
Location. Ponce de Leon Inlet is on the Atlantic 
coast of Florida about 65 miles south of St. Augustine 
Harbor and 57 miles north of Canaveral Harbor. 
(See Coast and Geodetic Survey Chart No. 1245.) 
Existing project. The authorized project provides 
for an entrance channel 15 by 200 feet across the 
ocean bar, thence 12 by 200 feet and 12 by 100 feet 
through the inlet; thence southward in Indian River 
North, 12 by 100 feet, and northward in Halifax 
River, 7 by 100 feet, each leg continuing to the Intracoastal 
Waterway; ocean jetties on the north and south 
of the inlet 4,200 and 2,700 feet long, respectively; 
and a weir in the north jetty with an impoundment 
basin inside the jetty. Plane of reference is mean low 
water. Mean range of tide is 4.1 feet in the ocean and 
2.3 feet inside the inlet. The project is about 5 miles 
long. 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was $2,415,- 
600. 
Terminal facilities. None in the immediate area. 
Operations and results during fiscal year. Maintenance: 
Repair of jetty cost $33,719. Real estate management 
costs were $10,319. Condition and operation 
studies cost $56,628. Engineering and design 
and supervision and administration costs were $336 
and $5,091, respectively. 
Condition at end of fiscal year. Construction of the 
project is complete. Repair of the north jetty was 
completed in FY 86. 
26. PONCE HARBOR, P.R. 
Location. Ponce Harbor is an open bay about midway 
on the south coast of Puerto Rico. From the center 
of the city of Ponce, the harbor is about 3 miles 
south. (See Coast and Geodetic Survey Chart Nos. 
927 and 902.) 
Previous project. For details, see page 12 of Annual 
Report for 1975. 
Existing project. The authorized project provides 
for a seawall 362 feet long extending northwesterly 
across the rock reef from near the landward end of the 
municipal pier; dredging an area off the municipal 
pier, 30 feet deep and containing about 18 acres; a 
breakwater 2400 feet long extending southwesterly 
from Punta Carenero; a channel 36 feet deep by 600 
feet wide extending from the Caribbean Sea approximately 
2.8 miles up to the port, thence a channel 400 
feet wide by 36 feet deep into the harbor, and a 36- 
foot-deep, irregularly shaped turning basin with a 
diameter of 950 feet. Plane of reference is mean low 
water. Mean tidal range is 0.6 foot, extreme varies 
between about 1 foot below and 2 feet above mean 
low water. Estimated cost of new work (Oct. 1985 
price levels) is $9,770,000 Federal ($7,328,000 
Corps and $10,000 U.S. Coast Guard) and $3,989,- 
000 non-Federal (other costs). (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Should provide all lands, 
easements and rights-of-way; provide and maintain at 
local expense depths in berthing areas and local access 
channels; hold United States free from any damages 
resulting from construction and maintenance of the 
project; relocate without cost to the United States all 
cables, sewer mains, water supply, drainage and other 
utility installations as required; provide adequate 
public terminal and transfer facilities open to all on 
equal terms. A letter has been received from mayor of 
Ponce, assuring compliance with local requirements 
and to cost share the project. A 25% contribution is 
required and an additional 10% reimbursement over 
30 years from locals. 
Terminal facilities. The municipality of Ponce 
owns and operates the only deep-draft terminal facilities 
in Ponce Harbor, which consist of a municipal 
pier 515 feet long and 108 feet wide, and a bulkhead 
wharf 3,811 feet long. Both are equipped for transfer 
and storage of freight. A 40 ton container lift shore 
crane is available for the handling of loaded containers. 
The municipal pier has a steel transit shed 386 
by 85 feet. The bulkhead wharf has four steel transit 
9-12

JACKSONVILLE, FLA. DISTRICT 
sheds totaling over 103,000 square feet. Three concrete 
and steel warehouses are availabe providing 
800,000 square feet for general storage. Open storage 
areas for structural steel, lumber, and other bulk 
and package commodities are also provided. Bulk 
cement is handled and loaded into cement cargo 
ships by the use of a private pipeline loading facility. 
A tuna fish processing and canning factory is located 
on the premises, with direct access to the bulkhead 
wharf. Existing facilities are open to the public. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. New 
Work: Engineering and design and supervision and 
administration costs were $23,884 and $1,91 1, 
respectively. 
Maintenance: Condition and operation studies cost 
$518. Supervision and administration cost was $65. 
Condition at end of fiscal year. Construction of the 
1976 modification of the project has not commenced. 
South and north jetties are in fair condition. 
27. PORT EVERGLADES HARBOR, FLA. 
Location. The harbor is on the east coast of Florida 
about 23 miles north of Miami and about 48 miles 
south of Palm Beach Harbor, Florida. (See Coast and 
Geodetic Survey Chart No. 546.) 
Existing project. The authorized project provides 
for an ocean entrance channel 45 by 500 feet through 
an ocean bar tapering to 42 by 450 feet between 
rubblestone entrance jetties, and continuing at that 
depth to an irregularly flared entrance and turning 
basin of same depth; enlarging Pier 7 channel to 36 
by 400 feet for a distance of about 1,600 feet; maintenance 
of the locally dredged channel opposite Berth 
18 to 36 feet deep over a length of 700 feet with 
varying widths of 200 to 150 feet; construction of a 
south jetty fishing walkway; and, maintenance of the 
jetties. Plane of reference is mean low water. The 
project is about 1.9 miles long. Mean range of tide is 
2.5 feet at the entrance and 2.3 feet at the terminals; 
extreme range is about 4.5 feet with storm tides of 
about 6.5 feet. 
Estimated cost of new work (Oct. 1980 price 
levels) of the 1974 authorization is $33,800,000 Federal 
(Corps of Engineers) cost and $7,062,000 non- 
Federal cost, ($160,000 contributed funds and 
$6,902,000 other costs.) (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local cooperation has been 
fully complied with for work completed to date. For 
work under House Document 144/93/1, local interests 
must: provide all lands, easements, and rightsof-
way; save United States free from damages; accomplish 
utility and other relocations or alterations; 
provide depths in berthing areas and local access 
channels serving the terminals commensurate with 
depths provided in the related project areas; establish 
regulations prohibiting discharge of pollutants into 
waters of the channel by users thereof; prohibit erection 
of any structure within 100 feet of project 
channel as authorized at time of construction; provide 
and maintain public terminal and transfer facilities; 
contribute 50 percent of total first costs of recreational 
jetty fishing facility; and operate and maintain jetty 
fishing facility. Assurances of local cooperation for 
the 1974 authorization have been furnished by the 
local sponsor. 
Terminal facilities. There are 22 commercial 
waterfront facilities serving the port. The General 
Cargo Facilities include 13,807 feet of usable berthing 
space, 7 transit sheds with a total capacity of 
393,870 square feet, and 6 container yards with 
space for 3,965 containers. Oil Handling Facilities 
consist of 232 storage tanks with a total storage 
capacity of 9,564,800 barrels. There is no usable 
berthing space located at the Oil Handling Facilities. 
Dry storage is available at 225,000 square feet, cold 
storage at 2,098,000 cubic feet and open storage at 
100.3 acres. 
Hoisting facilities available from a local firm include 
5 cranes with capacities from 20 to 155 tons. 
No floating cranes or derricks for heavy lifts are 
available at the port. There are 2 marine repair yards. 
Drydock facilities include 2 drydocks with capacities 
of 2,200 and 3,200 tons and a 4,270-ton vertical boat 
lift. Three tugs with ratings up to 4,290 horsepower 
serve the port. The Port Everglades Belt Line connects 
with the Seaboard Coast Line railroad to serve 
the port. 
Facilities are considered adequate for existing 
commerce. (See Port Series #16, Rev. 1982.) 
Operations and results during fiscal year. New 
work: Contract underway for recreation facilities cost 
$209,252. Engineering and design and supervision 
and administration costs were $1,379 and $177,417, 
respectively. 
Maintenance: Real estate inspection costs were 
$1,618. Acquisition costs were $5,221. Condition 
and operation studies cost $386. Supervision and 
administration costs were $1,033. 
Condition at end of fiscal year. Work required to 
complete the project is construction authorized in 
House Document 144/93/1. 
28. REMOVAL OF AQUATIC GROWTH 
FROM NAVIGABLE WATERS IN THE 
STATE OF FLORIDA. 
Location. Water hyacinth, hydrilla and water 
lettuce are found in freshwater streams and lakes in 
various parts of the district. 
9-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Existing project. The authorized project provides 
for destruction or removal of aquatic growth in navigable 
waters of the State so far as they constitute an 
obstruction to navigation and commerce, using any 
mechanical, chemical or other means not injurious to 
cattle, and use of log booms to close sloughs and backwaters 
as an auxiliary means. No estimate of the final 
cost of work has been made. (See Table 9-B for Authorizing 
Legislation.) 
For further details, see 1962 Annual Report. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Operations continued during the year. (See 
Table 9-B for Authorizing Legislation.) (See Table 9- 
G for spraying operations.) 
Condition at end of fiscal year. The project is for 
maintenance of navigable waterways. During the year 
16,950 acres of floating vegetation (water hyacinths 
and/or water lettuce), 3,142 acres of hydrilla and 
1,024 acres of minor plants were controlled in approximately 
2,200 miles of waterways. Hyacinths in Lake 
Okeechobee and in St. Johns River Watershed are 
under maintenance control. 
29. ST. AUGUSTINE HARBOR, FLA. 
Location. The harbor is on the east coast of Florida, 
about 35 miles south of the entrance to St. Johns River 
and about 180 miles north of Fort Pierce Harbor. (See 
Coast and Geodetic Survey Charts Nos. 1243 and 
1244.) 
Previous project. For details see page 412 of 
Annual Report for 1958. 
Existing project. The authorized project provides 
for a channel 16 feet by 200 feet along the best natural 
alinement as may exist from time to time across the 
new inlet bar, thence 12 feet deep to the Intracoastal 
Waterway; a sandtrap groin on the north side of the 
inlet extending seaward from the shore of Vilano 
Beach, and a sand-tight jetty on the south side of the 
channel extending seaward from the shore of Conch 
Island parallel to and coextensive with the groin, future 
landward extension of the groin and jetty; and a 
channel 10 by 100 feet in San Sebastian River from 
the Intracoastal Waterway to King Street Bridge, with 
a turning basin near the upper end. Length of the inlet 
channel is about 1.5 miles, and length of the San 
Sebastian River channel is about 2.6 miles. Plane of 
reference is mean low water. The mean tidal range is 
4.5 feet in the ocean at St. Augustine Inlet and 4.2 feet 
at the city waterfront. Strong northerly winds, mostly 
in the winter, lower the water surface about 1 foot. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work amounted to 
$137,500. 
Terminal facilities. There are several timber docks 
on the Matanzas waterfront of St. Augustine. In this 
area of the harbor is a concrete dock which serves as a 
municipal yacht pier. It has fuel facilities, 19 slips and 
accommodates boats up to 60 ft. in length. A large 
public boat ramp is also available. The principal 
terminals are the numerous shrimp docks in the San 
Sebastian River which flows southward through the 
city into the Matanzas River south of the bridge; these 
consist of timber wharves, with frame and corrugated 
iron warehouses thereon, and 9 marine railways for 
small boats. There is also a marine supply facility and 
several boat yards. The present terminals have highway 
connections and several of the shrimp docks have 
rail connections. They are considered adequate for existing 
commerce and recreational craft. 
Operations and results during fiscal year. Maintenance: 
Contract dredging costs were $334,147. Condition 
and operation studies cost $14,818. Engineering 
and design and supervision and administration 
costs were $870 and $37,584 respectively. 
Condition at end offiscal year. Project is completed 
expect for the North Jetty which is in a deferred status. 
The groin is in good condition except for the 300 feet 
which has subsided to about elevation 3.0 feet, mean 
low water. The jetty is in good condition, but is submerged 
at high tide. Total Federal costs under the existing 
project through September 30,1986 were 
$1,405,131 for new work and $4,714,107 for maintenance, 
a total of $6,119,238. 
30. ST. JOHN'S RIVER, FLA., JACKSONVILLE 
TO LAKE HARNEY 
Location. Rises in marshes of Brevard County, 
Fla., near east coast, and flows northwesterly to Jacksonville, 
thence easterly into the Atlantic Ocean, 122 
miles south of Savannah River. River is about 285 
miles long, of which 161.5 miles are included in 
project. (See U.S. Coast and Geodetic Survey Charts 
Nos. 685---688.) 
Previous projects. Adopted by River and Harbor 
Acts of June 14, 1880 and July 5, 1884. For further 
details see Annual Reports for 1915 and 1938. 
Existing project. Channel 13 feet deep and 200 feet 
wide from Florida East Coast Railway bridge at Jacksonville 
to Palatka, thence 12 by 100 feet to Sanford, 
and thence 5 by 100 feet to Lake Hamey, with side 
channel to Enterprise and maintenance of two jetties. 
Existing project was authorized by River and 
Harbor Acts of March 2, 1945 (H.Doc. 445, 78th 
Cong., 2d sess.) and July 24, 1946 (S. Doc. 208, 79th 
Cong., 2d sess.). For further details see Annual Report 
for 1962. 
Terminal facilities. There are 36 piers and wharves 
along project, including municipal piers and wharves 
9-14

JACKSONVILLE, FLA. DISTRICT 
at Green Cove Springs and Palatka, 12 Navy piers at 
Green Cove Springs, a municipal recreational pier at 
Sanford, and 19 privately owned piers, 5 of which 
have nearby tank storage facilities for petroleum 
products. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Supervision and administration costs were 
$834. 
Condition at end of fiscal year. Active portion is 
complete. Condition of project as a whole is 
adequate for present needs of navigation. (For more 
detailed information refer to Annual Report for FY 
1963). 
31. ST. LUCIE INLET, FLA. 
Location. The inlet is on the east coast of Florida 
about 19 miles south of the entrance to Fort Pierce 
Harbor, Florida, and 100 miles north of the entrance 
to Miami Harbor, Florida. (See Coast and Geodetic 
Survey Chart No. 1247.) 
Previous project. For details see page 764 of 
Annual Report for 1949. 
Existing project. The authorized project provides 
for extending the north jetty about 500 feet and modifying 
existing jetty to provide a sand bypass weir section 
about 500 feet long; excavation of a sand impoundment 
basin adjacent to the bypass weir in the 
north jetty; construction of a south jetty consisting of 
a rubblemound structure about 2,400 feet long with a 
walkway for recreational fishing; channel between 
existing bar cut and the Intracoastal Waterway 10 by 
500 feet through the bar cut, tapering to 150 feet 
through the inlet, and 100 feet wide and 7 feet deep 
to the Intracoastal Waterway; and transfer of 380,000 
cubic yards of material to the south beach during 
each two year maintenance period. Plane of reference 
is mean low water. Total project length is about 
1.9 miles. Mean tidal range is 2.6 feet on the ocean 
side and about 1 foot on the land side of the inlet. 
The estimated cost of the 1974 modification (Oct. 
1979 price levels) to the project is $6,290,000 Federal 
cost and $2,525,000 non-Federal cost 
($2,260,000 contributed funds and $265,000 other 
costs). (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must: contribute 
19.9 percent of construction cost allocated to 
navigation in the combined project, 23.2 percent 
allocated to beach erosion, and 50 percent of construction 
cost of jetty fishing walkway; provide 39.8 
percent of the annual maintenance cost allocated to 
navigation and 23.2 percent of the annual costs for 
maintenance dredging allocated to beach erosion 
control for periodic beach nourishment and 100 percent 
of the annual jetty maintenance costs allocated 
to beach erosion control; maintain jetty fishing walkway; 
agree that each five years the amount of local 
cost sharing for maintenance is to be adjusted; 
provide all lands, easements, and rights-of-way; hold 
United States free from damages; provide marina 
with mooring facilities and utilities; provide and 
maintain depths in berthing area and local access and 
feeder channels commensurate with the depths provided 
in the project; accomplish such alterations as 
required in sewer, water supply, drainage, and other 
utility facilities, and take action to place in effect 
statutes and/or regulations which will protect the 
water quality for the authorized uses of the project. 
Assurances of local cooperation for the 1974 modification 
were signed by the local sponsor on August 
24, 1978. 
Terminal facilities. A municipal pier provides 
facilities for docking and servicing charter fishing 
and small recreational craft. At Stuart there is a dock 
for handling bulk petroleum products and several 
marinas which provide facilities for mooring, servicing 
and minor repair of small craft. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. New 
work: Hired labor at recreational facility cost $1,539. 
Engineering and design and supervision and administration 
costs were $5,925 and $23,522, respectively. 
Maintenance: Maintenance dredging costs $556. 
Recreation costs -$1,539. Condition and operation 
studies cost $76,686. Engineering and design and 
supervision and administration costs were -$5,711 
and -$23,521, respectively. 
Condition at end of fiscal year. Work required to 
complete the project is construction authorized in 
House Document 294/93/1. Total Federal costs 
under existing project through September 30, 1986 
were $10,945,344 for new work (including 
$3,086,026 contributed funds) and $4,703,934 for 
maintenance, a total of $15,649,278. 
32. SAN JUAN HARBOR, P.R. 
Location. San Juan Harbor is on the north coast of 
Puerto Rico about 35 miles from the island's east end 
and 1,100 miles southeast of Miami, Florida. (See 
Coast and Geodetic Survey Chart No. 908.) 
Previous projects. For details see Annual Reports 
for 1915, 1916, 1938. 
Existing project. Provides for a bar channel 48 by 
800 feet, shifting the centerline 350 feet west; 
deepening Anegado Channel in steps from 46 to 40 
feet while reducing its width to 800 feet; deepening 
Army Terminal Channel and turning basin to 40 feet 
while widening the channel to 450 feet; deepening 
Puerto Nuevo Channel to 40 feet and widening it to 
400 feet; deepending Graving Dock Channel to 40 
feet at existing 400 foot width; an advance maintenance 
area 500 feet wide, 1,200 feet long and 44 
9-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
feet deep at the mouth of Cano de Martin Pena; 
deepening San Antonio Channel to 38 feet at varying 
widths, minimum of 500 feet; deepending cruise ship 
basin to 36 feet at an irregular width; maintaining 
Sabana Approach Channel at 30 by 250 feet; provide 
a 38-foot depth in Anchorage Area "E" with irregular 
width and six mooring dolphins for vessels using the 
area. Mean tidal range is 1.1 feet. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Should provide all lands, 
easements and rights-of-way; hold the United States 
free from any damages; provide and maintain depths 
in berthing areas and local access and feeder channels; 
provide alterations as required in sewer water 
supply, and other utility facilities. It is further recommended 
that local interests be reimbursed for work 
performed by them on the project subsequent to project 
authorization. Local interests have complied with 
authorization requirements to date. There was no 
non-Federal contribution required. 
Terminal facilities. There are 28 piers and bulkhead 
wharves in the harbor capable of docking deepdraft 
vessels, which have an aggregate berthing 
length of about 23,700 feet. Eleven piers and bulkhead 
wharves are on the north shore, two piers and a 
three-level ramp facility for roll-on/roll-off operations 
at Front Graving Dock turning basin and 
channel, nine at the eastern side and three at the 
western side of the Army Terminal basin and channel, 
and three on the south shore of San Antonio 
Channel. One pier and bulkhead wharf are privately 
owned, seven are U.S. Government property, and 24 
owned by the Commonwealth of Puerto Rico. Twenty 
piers and wharves are equipped with mechanical 
crane transfer facilities. Five wharves are equipped 
with a special crane for the handling of loaded containers. 
Twenty-four are open to general public. Pier 
No. 6 has been repaired and improved in 1985. 
There is an aggregate length of about 1,339 feet of 
berthing space at Catano Point used principally by 
small vessels within the 18-foot draft range. This 
space is also open to the public. In addition, there are 
10 piers and bulkhead wharves with approximately 
6,910 feet of berthing space owned and operated by 
different agencies of the Federal Government. This 
space is not open to the public. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Condition and operation studies cost $3,352. 
Contract dredging cost $2,245,499. Engineering and 
design and supervision and administration costs were 
$364 and $69,285, respectively. 
Condition at end of fiscal year. Remaining work to 
complete project is modification authorized in 1976. 
Total Federal costs under the existing project 
through September 30, 1986 were $13,027,284 for 
new work and $14,296,248 for maintenance, a total 
of $27,323,532 regular funds. In addition, $747,684 
was expended for new work and $44,730 for maintenance 
from public works funds and $100,000 for 
new work from contributed funds. Existing project 
includes the entrance channel and turning basin to 
Army Terminal which cost $1,543,712; this expenditure 
was made from military appropriations and is 
not included in above costs. 
33. TAMPA HARBOR, FLA. 
Location. Tampa Harbor is a large natural indentation 
of the Gulf of Mexico about midway of the west 
coast' of Florida. The entrance is about 220 miles 
north of Key West and about 330 miles southeast of 
Pensacola. (See Coast and Geodetic Survey Charts 
Nos. 586, 587, and 1257.) 
Previous projects. For details see page 665 of 
1938 Annual Report. 
Existing project. The authorized project provides 
for a channel from the Gulf of Mexico to Port Sutton 
and Tampa; 46 by 700 feet from the Gulf of Mexico 
to Mullet Key; 44 by 600 feet in Mullet Key Cut 
Channel; 44 by 500 feet in Tampa Bay from Mullet 
Key Cut to Hillsborough Bay and Port Tampa Channels; 
44 by 500 feet in Hillsborough Bay from junction 
with Tampa Bay and Port Tampa Channels to 
the junction with Port Sutton entrance channel, 
thence 42 by 400 feet to the junction with Seddon 
and Garrison Channels; 44 by 400 feet in Port Sutton 
entrance channel; 42 by 400 feet in Sparkman Channel; 
40 by 300 feet in Ybor Channel; 42 by 400 feet 
in Port Tampa Channel; 44 by 400-500 feet in East 
Bay entrance channel; 44 by 300 feet in East Bay 
approach channel; 30 by 300 feet in Seddon and Garrison 
Channels; 30 by 200 feet in Alafia River; 9 by 
100 feet in Hillsborough River to a point 2,000 feet 
above Columbus River bridge; a breakwater; turning 
basins at Port Sutton, Ybor Channel, Port Tampa, 
East Bay, mouth of Hillsborough River, and in 
Alafia River; and maintenance of a channel 12 by 
200 feet in Hillsborough River, 44 by 200 feet in Port 
Sutton terminal channel, and 34 x 300 in East Bay 
Channel. (The 46-foot and 44-foot depth portions of 
the project include a 5-foot underkeel clearance. 
Special studies on the project concluded that a 4-foot 
underkeel is sufficient. Therefore, a 1-foot overdepth 
has been placed in an inactive status, resulting in active 
project depths of 45 and 43 feet, respectively.) 
Plane of reference is mean low water. The project is 
about 67 miles long, including 10 miles in Hillsborough 
River and 3.6 miles in Alafia River. 
Mean range of tide is 1.3 feet at the lower end of 
the bay, 1.6 feet at Port Tampa, and 1.8 feet at 
Tampa. Extreme range is about 3.8 feet at the lower 
end of the bay and 4.8 feet at Tampa. Strong southwesterly 
winds raise the water level about 1.5 feet. 
9-16

JACKSONVILLE, FLA. DISTRICT 
Strong northerly winds, which usually occur in the 
winter, lower the water level about 2 feet. Estimated 
cost of new work (Oct. 1985 price levels) of the 1970 
modification to the project is $233,638,000 Federal 
($225,500,000 Corps and $2,218,000 U.S. Coast 
Guard) cost and $5,920,000 non-Federal cost 
($1,400,000 contributed funds and $4,520,000 other 
costs). (See Table 9-B for Authorizing Legislation.) 
For further details, see 1962 Annual Report. 
Local cooperation. Local cooperation has been 
fully complied with for work completed to date. See 
1978 Annual Report for requirements for work authorized 
by the River and Harbor Act of 1970, HD 
401/91/2 and HD 150/91 / 1. Assurances of local cooperation 
for the 1970 authorization were approved 
by the Secretary of the Army on January 10, 1973. 
Terminal facilities. There are 102 commercial 
waterfront facilities serving Tampa Harbor. The 
General Cargo Facilities consist of 7,226 feet of 
usable berthing space and 15 transit sheds with a total 
of 585,200 square feet of shed storage space. The Oil 
Handling Facilities include 16,440 feet of usable 
berthing space and 316 storage tanks for a total 
capacity of 11,610,350 barrels. Dry storage is available 
at 1,904,750 square feet, cold storage at 
14,309,000 cubic feet, and open storage at 59.4 
acres. There are 2 wharves available for coal storage 
at 750,000 tons total storage and grain elevators with 
a 3,400,000 bushel total capacity. One elevator on 
Ybor Channel is a 1,000,000 bushel capacity. 
Hoisting Facilities include 13 cranes, fixed and 
mobile, with capacities from 45 to 150 tons and other 
crawler and mobile cranes available locally. Marine 
repair yards include 9 waterfront repair facilities and 
numerous other offwater companies engaged in 
various phases or marine repair. There are 4 floating 
and 4 graving docks available at the port with capacities 
ranging from 548 to 5,400 long tons. Floating 
equipment includes 24 tugs with up to 3,350 horsepower 
and 4 companies with tank barges of capacities 
up to 14,000 barrels. The Seaboard System Railroad 
serves the port. 
Facilities are considered adequate for existing 
commerce. (See Port Series #17 revised 1979.) 
Operations and results during fiscal year. New 
work: Charge off cost on purchased transponder for 
offshore disposal positioning -$8,567. Construction 
of the 43-foot project from Mangrove Point to Alafia 
River completed at a cost of $742,407. Engineering 
and design and supervision and administration costs 
were $726,882 and $220,225, respectively. 
Maintenance: Real estate audits cost $815. Condition 
and operation studies cost $168,629. Engineering 
and design and supervision and administration 
costs were $81,347 and $11,570, respectively. 
Condition at end of fiscal year. Work authorized 
by the River and Harbor Act of 1970 (HD 401/91/2 is 
65 percent complete.) 
Total Federal costs under the existing project 
through September 30, 1986 were: Main project: 
$194,934,023 for new work and $19,201,025 for 
maintenance, a total of $214,135,048 regular funds. 
In addition, $853,050 was expended for new work 
from public works funds, $1,463,000 from emergency 
relief funds, and $1,029,180 from contributed 
funds. On Hillsborough River $270,466 was expended 
for new work. 
34. NAVIGATION PROJECTS ON WHICH 
RECONNAISSANCE AND CONDITION 
SURVEYS ONLY WERE CONDUCTED 
DURING PERIOD. 
(See Table 9-H.) 
35. OTHER AUTHORIZED NAVIGATION 
PROJECTS. 
(See Table 9-I.) 
36. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation Activities Pursuant to Section 107, 
Public Law 86-645 (Preauthorization) 
Fiscal year costs for Aguadilla Harbor, PR, 
$7,198; Benner Bay - Mangrove Lagoon, V.I., 
$800; Blount Island, Florida, $23,492; Cedar Island- 
Keaton Beach Channel, Florida, $18,595; Dunedin 
Pass, Florida, $629; North Lake Channel, Hollywood, 
Florida, $22,741; Pasco County, Small Boat 
Channel, Florida, $319; Rockhous Creek, Florida, 
$24,988; and Willoughby Creek, Florida, $973. 
Snagging and clearing for navigation (Sec. 3 of 
1945 River and Harbor Act, Public Law 14, 79th 
Congress.) 
No costs incurred. 
Beach Erosion Control 
37. BREVARD COUNTY, FLA. 
Location. The project is on the east coast of 
Florida at approximately the midpoint of the peninsula. 
(See Coast and Geodetic Survey Charts Nos. 
1245 and 1246.) 
Existing project. The authorization provides for a 
protective and recreational beach with a berm 50 feet 
wide at elevation 10 feet above mean low water and a 
natural seaward slope as would be shaped by wave 
action, along 14,600 feet of beach at the city of Cape 
Canaveral and 10,600 feet of beach at Indialantic and 
Melbourne beach, and for periodic nourishment of 
the restored beach at Indialantic and Melbourne 
Beach limited initially to a period of 10 years. 
9-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Nourishment of the restored beach at the city of Cape 
Canaveral would be provided by the sand-transfer 
plant authorized for construction at Canaveral 
Harbor. The project also provides for improvement 
of the Federally owned shores for beach erosion control 
or hurricane protection to be accomplished by the 
Federal agencies involved, subject to their own determination 
of economic justification. The areas involved 
include 4.9 miles of shore at Kennedy Space 
Center, 4.0 miles at Cape Kennedy Air Force Station, 
and 2.3 miles at Patrick Air Force Base. 
Mean tidal range in the area is 3.5 feet. Estimated 
cost of the project (Oct. 1985 price levels) is 
$8,450,000 Federal costs and $8,550,000 non-Federal 
cost ($8,450,000 cash contribution and $100,000 
for lands). (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must contribute 
50 percent of all first costs of the work and 50 percent 
of the nourishment cost at Indialantic and Melbourne 
Beach for the first 10 years of the project life; 
provide lands and rights-of-way; provide, after the 
first 10 years of project life, periodic nourishment of 
the restored beach at Indialantic and Melbourne 
Beach during project life; maintain continued public 
ownership of the shore upon which the amount of 
Federal participation is based; control water pollution; 
and hold the United States free from damages. 
Assurances of local cooperation were approved by 
the Secretary of the Army on July 9, 1973. 
Operations and results during fiscal year. New 
work: Engineering and design cost $3,598. 
Condition at end of fiscal year. Initial beach fill 
has been provided at Indialantic and Melbourne 
beaches. 
38. BROWARD COUNTY, FLA. BEACH 
EROSION CONTROL AND HILLSBORO 
INLET, FLA., NAVIGATION PROJECT 
Location. Broward County is on lower east coast 
of Florida, 300 miles south of Jacksonville and about 
30 miles north of Miami. Hillsboro Inlet is in northern 
part of Broward County. (See Coast and Geodetic 
Survey Chart No. 1248.) 
Existing project. The authorization provides for 
Federal participation toward cost of a shore restoration 
and protection project and a project to provide 
and maintain a channel adequate for small craft navigation. 
Plan provides for restoration of a protective 
and recreational beach at four locations generally 100 
feet wide with berm elevation of 10 feet above mean 
low water, a navigation channel 8 by 100 feet from 
the Intracoastal Waterway to a point 1,500 feet 
oceanward in Hillsboro Inlet, thence 10 by 150 feet 
in the ocean; jetties on north and south sides of ocean 
entrance; a permanently based floating dredge; and 
on a deferred basis, a trestle-mounted sand-transfer 
plant, if needed. Navigation portion of the project is 
in an inactive status. Mean range of tide in areas is 
2.5 feet. Plane of reference is mean low water. Cost 
estimate for new work (Oct. 1985 price levels) is 
$18,300,000 Federal and $22,400,000 non-Federal 
contribution. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must contribute 
90.5 percent of the first cost of beach restoration in 
the reach between north county line and Hillsboro Inlet, 
90 percent of first cost allocated to beach restoration, 
and 50 percent of first cost allocated to navigation 
for reach between Hillsboro Inlet and Port Everglades 
and 72.4 percent of beach restoration in reach 
between Port Everglades and south county line; provide 
all lands and rights-of-way; obtain approval of 
Chief of Engineers of plans and specifications if local 
interests construct beach erosion features; and furnish 
assurances that they will hold the United States free 
from damages, provide and maintain adequate public 
landing or wharf at Hillsboro Inlet, establish a public 
body to cooperate financially and to provide and operate 
local facilities for navigation, control water 
pollution, maintain ownership of publicly owned 
shores, and maintain all project works except the jetties 
(maintenance of the channel to revert to the 
United States if sand-transfer plant is constructed). 
Assurances of local cooperation were accepted November 
22, 1968. 
Operations and results during fiscal year. New 
work: Engineering and design and supervision and 
administration costs were $17,452 and $163, respectively. 
Condition at end of fiscal year. Project was constructed 
by local interests and is complete. 
39. DADE COUNTY, FLA. 
Location. Dade County is on the southeast coast of 
Florida. Project area consists of that part of the Atlantic 
shoreline of the county from Government Cut 
north to Bakers Haulover Inlet and at Haulover Beach 
Park. (See Coast and Geodetic Survey chart No. 1248.) 
Existing project. Project provides for a protective 
and recreational beach having a dune at elevation 
11.5 feet and a level berm 50 feet wide at elevation 9 
feet, mean low water, for beach erosion control and 
hurricane protection between Government Cut and 
Bakers Haulover Inlet; a protective and recreational 
beach with a berm elevation of 9 feet for beach erosion 
control at Haulover Beach Park; and Federal 
participation in the initial construction and in periodic 
nourishment of both the above reaches for the first 10 
years of project life. Plane of reference is mean low 
water. Mean range of tide in the area is 2.5 feet. 
Estimated cost of the project (Oct. 1985 price 
levels) is $47,100,000 Federal cost and $40,039,000 
non-Federal cost ($38,200,000 cash contribution and 
$1,839,000 other costs). 
9-18

JACKSONVILLE, FLA. DISTRICT 
Project was authorized by Flood Control Act of 
1968 (HD 335/90/2). 
Local cooperation. Local interests must (a) contribute 
for the first cost of the work: between Government 
Cut and Bakers Haulover Inlet amounts ranging from 
60.2 percent of the cost of the fill within the project 
limit with existing shorefront ownership, and 100 percent 
of the cost of fill required landward of the project 
limit; and for the work at Haulover Beach Park, contribute 
21.3 percent of the entire first cost excluding 
costs for lands, easements, rights-of-way, relocations, 
and preproject work, but including credit for 
preproject work; (b) contribute in cost for the first 10 
years of project life, amounts ranging from 88.9 percent 
of the nourishment cost for the beach, with existing 
ownership, to 60.7 percent with public ownership, 
and the entire maintenance cost for the dune, all between 
Government Cut and Bakers Haulover Inlet; (c) 
provide all lands and rights-of-way; (d) hold United 
States free from damages; (e) assure continued public 
ownership and use of the shore upon which the 
amount of Federal participation is based; (f) assure 
maintenance of the groin, and after the first 10 years of 
project life, periodic nourishment of the protective 
beach and maintenance of the dune during the economic 
life of the project; (g) assure that water pollution 
will not be permitted; (h) prevent removal or 
relocation by man of fill from the beach berm and 
dune; (i) prevent the erection of barriers to the littoral 
movement of material that would interfere with the 
nourishment of the beach; (j) maintain at the parks 
qualifying for 70 percent Federal participation a zone 
that excludes permanent human habitation; (k) at least 
annually inform interests affected that the project will 
not provide complete protection from a hurricane tide 
level equal to or higher in elevation than that of the 
hurricane of September 1926; and (1) establish in public 
ownership for public use the beaches within project 
limits as a requirement for Federal participation in the 
allocated beach erosion control costs of improvement 
of shores presently in private ownership. Assurances 
of local cooperation were accepted January 16, 1973. 
A supplemental agreement for Bal Harbour portion 
was approved 30 June 1976. 
Operations and results during fiscal year. New 
work: A contract for Jetty Rehabilitation and Extension 
continued at a cost of $2,234,743. Engineering 
and design and supervision and administration costs 
were $157,224 and $50,278, respectively. 
40. DADE COUNTY, NORTH OF 
HAULOVER BEACH, FLA. 
Location. On the southeast coast of Florida. Project 
area consists of that part of the Atlantic shoreline extending 
2.5 miles north of Haulover Beach Park. (See 
Coast and Geodetic Survey Chart No. 1248.) 
Existing project. The existing shore protection 
project for Dade County provides for Federal participation 
in the cost of construction of a beach fill for the 
purpose of erosion control and hurricane protection 
along 9.3 miles of shore between Government Cut 
and Bakers Haulover Inlet and for the construction of 
a beach fill for the purpose of erosion control along the 
1.2 miles of shore fronting Haulover Beach Park and 
provides for protection and nourishment of 2.5 miles 
of beach shore north of Haulover Beach Park and for 
extension of the period of Federal participation in the 
nourishment of the existing project from 10 years to 
the life of the project. Cost estimate for new work 
(Oct. 1985 price levels) was $12,300,000 Federal and 
$12,000,000 non-Federal cash contribution and 
$100,000 other costs. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Consistent with the costsharing 
and financing concepts agreed to by the 
administration and the Senate Majority Leadership, 
local interests will be required to provide lands, 
easements and rights-of-way and relocations, pay 
50% of the separable and joint costs allocated to recreation, 
pay 35% of the cost allocated to storm damage 
prevention, hold the United States free from damages, 
control water pollution and furnish assurances that 
they will maintain continued public ownership of the 
shore upon which the amount of Federal participation 
is based during economic life of project. Assurances 
of local cooperation have been requested from local 
sponsors. 
Operations and results during fiscal year. New 
work: Engineering and design and supervision and 
administration costs were $11,352 and $1,587, 
respectively. 
Condition at end of fiscal year. Continuation of 
planning and engineering. 
41. DUVAL COUNTY, FLA. 
Location. On upper east coast of Florida, within 20 
miles of Florida-Georgia line. Ocean shoreline is 
about 16 miles long. (See Coast and Geodetic Survey 
Chart No. 1243.) 
Existing project. Provides for Federal participation 
toward cost of construction with artificial fill, a beach 
60 feet wide at elevation 11 feet above mean low 
water with a natural slope seaward, and for periodic 
nourishment for 10 years. Federal participation to be 
100 percent of the first cost of construction applicable 
to the Federal shore and 50 percent applicable to the 
other publicly owned shore and 55.5 percent of 
periodic nourishment cost for first 10 years of project 
life. Mean tidal range at south jetty in St. Johns River 
is 4.9 feet. 
Estimated cost of new work (Oct. 1985 price 
levels) $15,500,000 Federal and $13,334,000 non- 
Federal ($11,000,000 contributed funds and $2,334,- 
000 for other costs. 
9-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Project was authorized by River and Harbor Act of 
1965 (HD 273/89/1). 
Local cooperation. Local interests must contribute 
50 percent of first cost of constructing non-Federal 
publicly owned shores; contribute 44.5 percent of periodic 
nourishment costs for first 10 years of project 
life; provide all lands, rights-of-way, and relocations; 
hold the United States free from damages; control 
water pollution; and furnish assurances that they will 
maintain continued public ownership of the shore upon 
which the amount of Federal participation is based 
during economic life of project. Assurances of local 
cooperation were accepted on November 29, 1973. 
Operations and results during fiscal year. New 
work: A contract for beach nourishment continued at 
a cost of $1,385,023. Engineering and design and supervision 
and administration costs were $61,133 and 
$47,395, respectively. 
Condition at end of fiscal year. Initial beach fill 
and four year advance nourishment has been completed. 
42. FORT PIERCE, FLA. 
Location. Fort Pierce Beach erosion project fronts 
the Atlantic Ocean and is on coastal barrier island in 
St. Lucie County which separates Indian River from 
the ocean. Area is 120 miles north of Miami and 
about 225 miles south of Jacksonville. (See Coast 
and Geodetic Survey Chart 582.) 
Existing project. Provides for Federal participation 
in the cost of a shore restoration and protection 
project which involves construction and periodic 
nourishment for 10 years. Federal participation 
amounts to one-half such costs for that part of the 
ocean shoreline extending 1.2 miles southward of 
Fort Pierce navigation inlet, and 70 percent of such 
costs for the adjacent 0.1 miles shoreline known as 
Lions Club Beach Park. Mean range of tide in area is 
2.6 feet. Cost estimate (Oct. 1985 price levels) is 
$3,460,000 Federal and $3,230,000 non-Federal. 
Project was authorized by 1965 River and Harbor 
Act (HD 84/89/1) as modified by section 102 of 1968 
River and Harbor Act. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must contribute 
one-half the costs of protecting and periodically nourishing 
for 10 years the reach of shoreline starting at 
and extending 1.2 miles south of Fort Pierce Inlet and 
30 percent of cost of protecting and periodically nourishing 
0.1 mile of shoreline known as Lions Club 
Beach Park; obtain approval by Chief of Engineers of 
detailed plans and specifications for the project; establish 
in public ownership for public use the beaches 
within project limits prior to reimbursement; furnish 
all lands and rights-of-way; furnish assurances that 
they will maintain continued public ownership of the 
publicly owned shores; exclude permanent human 
habitation and provide full park facilities at the Lions 
Club Beach Park; provide periodic nourishment of the 
beach; control water pollution; hold United States free 
from damages; and execute such further assurances 
and agreements as may be necessary to carry out the 
intent of Congress expressed in the acts authorizing or 
modifying the project. River and Harbor Act of 1965 
authorized construction of the project by local interests. 
Section 102 of 1968 River and Harbor Act 
modified the project to provide for construction by 
Secretary of Army and Section 215 of the same act 
permitted construction by local interests. Local interests 
have elected to construct the project. 
Assurances of local cooperation were accepted January 
2, 1969. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. Initial beach nourishment 
has been completed. 
43. PALM BEACH COUNTY, FLA., FROM 
MARTIN COUNTY LINE OF LAKE 
WORTH INLET AND FROM SOUTH 
LAKE WORTH INLET TO BROWARD 
COUNTY LINE 
Location. Palm Beach County is on east coast of 
Florida about 300 miles south of Jacksonville and 70 
miles north of Miami. Northerly reach of the project 
is separated from the southerly reach by Palm Beach 
Island. Project consists of about 12.2 miles of ocean 
coastline. (See Coast and Geodetic Survey Charts 
1247 and 1248.) 
Existing project. Provides for Federal participation 
toward the cost of local shore project for restoration 
of beaches to a general width of 100 feet with a berm 
elevation of 10 feet above mean low water, and periodic 
nourishment for 10 years from the year of initial 
nourishment, as follows: 4.8 percent of the cost for 
the Martin County line-Jupiter Inlet segment; 11.6 
percent of cost for Jupiter Inlet-Lake Worth Inlet 
segment; and 5.1 percent for South Lake Worth Inlet 
-Boca Raton Inlet segment. Mean range of tide is 2.8 
feet in the Atlantic Ocean at Palm Beach and 2.3 feet 
at Boca Raton Inlet. Estimated cost (Oct. 1985 price 
levels) is $10,800,000 Federal and $18,400,000 cash 
contribution. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must obtain 
approval by Chief of Engineers of plans and specifications 
prior to commencement of work and furnish 
assurances that they will maintain public ownership 
of publicly owned shores, maintain protective measures 
and provide periodic nourishment of protective 
beaches, and control water pollution. 
Operations and results during fiscal year. New 
work: Engineering and design and supervision and 
administration costs were $32,407 and $3,192, respectively. 
9-20

JACKSONVILLE, FLA. DISTRICT 
Condition at end of fiscal year. Local interests 
provided initial beach fill at Delray Beach which was 
completed in August 1973. A periodic nourishment 
contract at Delray Beach was awarded in FY 1978 by 
local interests and the contract has been completed. 
44. PINELLAS COUNTY, FLA. 
Location. Pinellas County is on the Gulf coast of 
Florida, about midway of the peninsula. It extends 
northerly about 39 miles from the main entrance to 
Tampa Bay to the vicinity of the mouth of Anclote 
River. (See Coast and Geodetic Charts Nos. 858 and 
1257.) 
Previous project. For details see page 429 of 
Annual Report for 1965. 
Existing project. The authorized project provides 
for Federal participation in preserving and protecting 
the shores of Pinellas County, Florida, by: restoration 
of 5,000 feet of beach at Clearwater Beach Island; 
restoration of 49,000 feet of beach at Sand Key; 
restoration of 9,200 feet of beach at Treasure Island; 
construction of 600 feet of revetment at Long Key; 
and advance nourishment of Long Key and periodic 
nourishment of each island. Estimated cost (Oct. 1985 
price levels) is $18,700,000 Federal funds and 
$20,062,000 non-Federal funds ($20,000,000 contributed 
funds and $62,000 for other costs). (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must: (a) contribute 
in cash the required percentages of the first 
costs of work provided by the Corps of Engineers, 
the percentages varying with the type of beach ownership; 
94.1 to 50 percent of the beach restoration at 
Clearwater Beach; 98.1 to 50 percent of the improvement 
at Sand Key; 94.3 to 50 percent of the improvement 
at Treasure Island; and 50 percent of the first 
cost of the revetment at Long Key; (b) contribute in 
cash an amount computed in accordance with the 
cost sharing provision contained in P.L. 826, 84th 
Congress as amended by P.L. 87-874, for beach 
nourishment cost for the first 10 years of the project 
life; (c) provide lands, easements, and rights-of-way; 
(d) assure maintenance and repair of the stone revetment 
of Long Key; (e) assure periodic nourishment 
of the restored beaches; (f) assure public ownership 
of beaches; (g) assure against water pollution; (h) 
hold the United States free from damages; and (i) 
provide beach for public use. Assurances of local 
cooperation were accepted March 22, 1967. 
Operations and results during fiscal year. New 
work: Contract for Redington shore breakwater and 
groin cost $469,060. Contract for Long Key breakwater 
and beach nourishment costs were $572,035. 
Engineering and design and supervision and administration 
costs for the fiscal year were $299,863 and 
$41,985, respectively. 
Condition at end of fiscal year. Construction of the 
project commenced in 1969 and is 25 percent completed. 
Total costs under existing project through 
September 30, 1986 were $3,614,327 Federal funds 
and $2,637,896 contributed funds for new work and 
$5,625 for maintenance. 
45. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Table 9-J.) 
46. BEACH EROSION CONTROL 
ACTIVITIES UNDER SPECIAL 
AUTHORIZATION 
Beach erosion control activities pursuant to section 
103, Public Law 87-874 (preauthorization) 
Reports incurring costs during the fiscal year were 
Boca de Congrejos, P.R., $13,186; Dorado Public 
Beach, P.R., $3,223; Dunedin Shores, Florida, 
$4,175; Fort Clinch State Park, Florida, $10,062; 
Guanica Public Beach, P.R., $14,765; Gulfport, 
Florida, $20,507; Isla de Cabras, P.R., $11,503; Key 
Biscayne, Fla., $43,884; Playa de Santa Isabel, P.R., 
$2,919; and Puerto Nuevo Beach, P.R., $3,297. 
Beach erosion control activities pursuant to section 
III, Public Law 90-483, Mitigation of Shore Damages 
Attributable to Navigation Projects 
No costs were incurred under the above authorization. 
Beach erosion control activities pursuant to Shoreline 
Erosion Control Act of 1974, Public Law 93- 
251. 
No costs were incurred under the above authorization. 
Flood Control 
47. CENTRAL AND SOUTHERN FLORIDA 
Location. The project is located generally within 
the southeastern eighteen counties of Florida covering 
an area of about 15,200 square miles. It is comprised 
of the Upper St. Johns River basin in the 
northeastern section of project, Kissimmee River 
basin in central section above the Lake Okeechobee- 
Everglades area in the central and southwestern section, 
and the east coast Everglades area in southeastern 
section. 
Previous projects. Completed works for control of 
Lake Okeechobee were included in and constructed 
under the navigation project for Okeechobee Waterway, 
Fla. (formerly Caloosahatchee River and Lake 
Okeechobee drainage area, Fla.) and under provisions 
of River and Harbor Acts of July 3, 1930, and 
August 30, 1935. For further information, see Annual 
Reports, 1948 and 1949. 
9-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Existing project. The authorized project is for flood 
relief and water conservation and provides principally 
for: an east coast protective levee extending from the 
Homestead area north to the eastern shore of Lake 
Okeechobee near the St. Lucie Canal; three conservation 
areas for water impoundment in the Everglades 
area west of the east coast protective levee with control 
structures to effect transfer of water as necessary; 
local protective works along the lower east coast; encirclement 
of the Lake Okeechobee agricultural area 
by levees and canals; enlargement of portions of 
Miami, North New River, Hillsboro, and West Palm 
Beach Canals; enlargement of the existing Lake 
Okeechobee levees and construction of new levees on 
the northeast and and northwest shore of the lake; increased 
outlet capacity for improved control of Lake 
Okeechobee; floodway channels in the Kissimmee 
River basin, with suitable control structures to prevent 
over-drainage; an interrelated system of canals, 
levees, pumping stations, and structures in southwest 
Dade County to control water levels; and facilities for 
regulating floods in the Upper St. Johns River basin; a 
system of canals and control structures for gravity 
drainage of Martin County and distribution of available 
water supplies to portions of Martin and St. Lucie 
Counties; and works to improve the supply, distribution, 
and conservation of water resources in central 
and southern Florida, including the Lake Okeechobee 
agricultural area, Everglades National Park, and other 
related areas. The project will provide water control 
and protection from recurrence of the devastasting 
floodwaters from the Everglades and local sources, 
for the highly developed urban area along the lower 
east coast of Florida and for the productive agricultural 
areas around Lake Okeechobee (including 
towns around lake), in the Upper St. Johns and Kissimmee 
River basins, and in South Dade County. 
Project also provides for navigation improvements 
suitable for recreational craft, consisting of locks and 
channel dredging in the upper Kissimmee and St. 
Johns basins. 
The project includes a total of 990 miles of levees, 
978 miles of canals, 30 pumping plants, 212 floodway 
control and diversion structures, 56 railroad bridge 
relocations, and 2 highway bridge relocations. 
The project also provides that upon completion, 
local interests assume operation and maintenance of 
all completed works except levees, channels, locks, 
and control works for regulation of Lake Okeechobee 
and the main control structures of conservation areas, 
which will be operated and maintained by the United 
States. 
The principal features of the hurricane gates, constructed 
under previous projects for Okeechobee Waterway 
and maintained under existing project since 
July 1, 1950, are set forth in Table 9-K. See also Table 
9-L for principal features of locks and dams. 
Estimated cost for new work (Oct. 1985 price 
levels) is $753,310,000 Federal funds ($751,000,000 
Corps and $2,310,000 U.S. Coast Guard) and $200,- 
000,000 contributed funds, exclusive of river and 
harbor funds expended on previous projects. Local interests 
costs in reviewing plans. and specifications are 
expected to be $700,000. In addition, estimated cost 
to local interests of lands, rights-of-way, and relocations 
is $211,960,000. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. (See Table 9-M for local cash 
contribution.) Local interests must also: provide 
lands, rights-of-way, and spoil disposal areas; hold 
the United States free from damages; bear the cost of 
maintenance and operation of all works except those 
having to do with regulation of Lake Okeechobee and 
the main control structures of conservation areas; construct 
and maintain lateral drainage facilities; prohibit 
encroachment on flood-carrying capacity of the improved 
channels; and assume cost of all new highway 
bridges, relocations of existing bridges and alterations 
to utilities incident to construction of the project. In 
addition, for small boat navigation channels, local interests 
must provide, maintain, and operate adequate 
public landings, sanitary and access facilities, and establish 
regulations prohibiting discharge of pollutants 
into the waters of the locks and channels by users 
thereof. 
Assurances of local cooperation have been accepted 
by the District Engineer for all items of work 
authorized to date except those for the Small Boat 
navigation feature added in 1970 under Section 201 of 
the Flood Control Act of 1965. 
Operations and results during fiscal year. (See 
Table 9-N for work accomplished.) 
Operations and care. a. Features completed under 
previous navigation project for Okeechobee Waterway 
and being maintained under this project are: a 
levee about 70 miles long following in general the 
south shore of Lake Okeechobee and a north shore 
levee 15.8 miles long; spillways at Ortona and St. 
Lucie locks; 5 hurricane gates; 20 gated drainage 
culverts through the levee; and 16 spillways along St. 
Lucie Canal. 
b. Features completed under existing project that 
are to be maintained with operation and maintenance 
funds are: (I) Levees 47, 58, 49 and 50-total length 
63 miles and enlargement of existing levees L-D 1, LD2, 
L-D3, L-D4, and L-D9, (2) spillway structures 
S-10, S-l l, S-12, S-18C, S-77, and S-78 (3) C-43, 
Sec. 4 (Caloosahatchee River), and (4) W.P. Franklin 
Lock and Dam. 
In addition to the actual facilities listed above it is 
necessary under operation and maintenance to continue 
meteorological studies, water level records, 
stream gaging stations, etc., for proper regulation of 
the level of Lake Okeechobee and storage of water in 
Conservation Areas 1, 2 and 3. 
9-22

JACKSONVILLE, FLA. DISTRICT 
Corps of Engineers - The Corps of Engineers 
operates and maintains the major outlets to Lake 
Okeechobee and Water Conservation Area Nos. 1, 
2A and 3A in central and southern Florida. 
South Florida Water Management District - 
SFWMD is responsible for operation and maintenance 
of the remainder of the project facilities, including 
major pumping stations, spillways, locks (except 
on Okeechobee Waterway), levees and culverts. 
Condition at end offiscal year. The scheduled work 
of project is 79 percent complete. Planning for the entire 
project began in November 1948 and has been 
continued. For construction completed prior to Fiscal 
Year 1980 see Annual Reports for 1960-1979. Construction 
completed under existing project during the 
fiscal year is set forth in Table 9-0. All Federally 
maintained features of the project were generally in 
good condition at the end of the fiscal year. (For status 
of work under contract at end of fiscal year see Table 
9-P.) 
Total Federal costs under the existing project 
through September 30, 1986 were $291,129,760 for 
new work, $51,180,261 for maintenance, a total of 
$342,310,021. In addition, $52,561,791 has been expended 
from contributed funds for new work. 
48. FOUR RIVER BASINS, FLA. 
Location. The Four River Basins area covers about 
6,000 square miles within 14 counties in central and 
southwest peninsular Florida. Project includes all or 
part of the four main stream basins-the Hillsborough, 
Oklawaha, Withlacoochee, and Peace Rivers 
-and all of three smaller coastal basins north of 
Tampa, Florida, drained by the Pithlachascotee and 
Anclote Rivers and Lake Tarpon. 
Existing project. The authorized project provided 
for improvements for control of floods and drainage, 
and for water conservation through construction of 
necessary canals, levees, reservoirs, and control 
structures. More specifically, the project provided for: 
Green Swamp Area -a conservation area and three 
storage reservoirs with necessary canals and control 
structures; Hillsborough River-four flood-storage 
reservoirs, with necessary channels, control structures, 
and levees; Oklawaha River-a levee on the 
north shore of Lake Apopka, improvement of part of 
the river channel and a west bank levee below Moss 
Bluff lock and dam, and replacement of the lock and 
dam; Withlacoochee River---one flood-storage reservoir 
with outlet canals and control structures; Peace 
River-Peace Creek canal and control structures and 
improvements to the existing water control and drainage 
features; Gulf Coastal Areas-Lake Tarpon: outlet 
anal and control structure; Anclote River: control 
structure and channel improvement; Pithlachascotee 
River: reservoir with outlet canals and control structures. 
(See Table 9-Q on Moss Bluff Lock.) 
Estimated cost for new work (Oct. 1985 price level) 
is $187,000,000 Federal funds and $131,820,000 
non-Federal cost. ($38,700,000 contributed funds; 
$55,270,000 for lands and damages; and $37,850,000 
for relocations.) (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must furnish all 
lands, and rights-of-way; provide all alterations or 
replacements of public and private utilities, roads, 
bridges (except railroad bridges), etc.; hold the United 
States free from damages; operate and maintain all 
project works after completion; construct and maintain 
such associated works as are necessary to realize 
benefits made available by the project works; and contribute 
in cash 17 percent of the first cost of construction 
and 50 percent of recreation costs. 
Operations and results during fiscal year. New 
work: Completed contract for Tampa Bypass Shoal 
removal and cleanup cost was $1,160,254. Contract 
for Dead River recreation sites was completed at a 
cost of $187,267. Engineering and design and supervision 
and administration costs were $244,340 and 
$122,265, respectively. 
Condition at end of fiscal year. Construction of the 
project commenced April 18, 1966 and the scheduled 
work is 98 percent complete. See Table 9-R for construction 
of major features of the project completed to 
date. 
49. PORTUGUES AND BUCANA 
RIVERS, P.R. 
(This project authorized as Lago de Cerrillos, Lago 
de Portugues, and Channel Improvement at Ponce.) 
Location. Portugues and Bucana Rivers originate 
on the southern slopes of Cordillera Central divide of 
Puerto Rico and flow from this central ridge of the island 
to the Carribean Sea. Their drainage areas are 
22.6 and 31.4 square miles, respectively. Ponce, the 
second largest city in Puerto Rico, is located in the 
lower coastal area along Portugues River and is the 
only urban community in the two basins. 
Existing project. The authorized project provides 
for two multiple-purpose reservoirs for flood control, 
water supply, general recreation, and fish and wildlife 
enhancement-one on Portugues River and the 
other on Cerrillos River, a tributary to the Bucana 
River; enlargement of about 5.7 miles of the Bucana 
River; with an additional 0.2-mile tieback levee at 
the upstream terminus of the improvement; enlargement 
of 2.1 miles of the Portugues River, with 
an additional 0.5 mile of tieback levee at the upstream 
terminus of the improvement; and a 1.3 mile 
diversion channel connecting Portugues River to 
lower Bucana River. Estimated cost of the project 
(Oct. 1985 price level) is $301,000,000 Federal cost 
and $80,077,000 non-Federal cost ($60,177,000 for 
lands and damages; $12,414,000 for relocation; and 
9-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
$7,486,000 for highway bridges and approaches). 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must provide all 
lands, easements and rights-of-way; hold the United 
States free from damages; operate and maintain all 
project works after completion; repay construction 
cost allocated to water supply in accordance with 
Water Supply Act of 1958; pay one-half of the 
separable cost allocated to recreation and fish and 
wildlife enhancement; prohibit discharge of inadequately 
treated sewage and other pollutants into the 
reservoir; and prevent encroachment on downstream 
channels. Assurances of local cooperation have not 
been completed, except for Cerrillos Reservoir which 
was signed March 15, 1982. 
Operations and results during fiscal year. New 
work: Contract for Cerrillos Dam & Spillway continued 
at a cost of $10,966,326. Hired labor costs 
were $62,749. Contract for Cerrillos Dam diversion 
tunnel and foundation preparation continued at a cost 
of $319,141. Contract for Upper Portugues Channel 
Sections 6E and 6F cost $870,066. Contract for Section 
7 continued at a cost of $447,898. Contracts for 
Bucana Debris Basin excavation and Portugues Channel 
improvement and debris control basin has respective 
costs of $1,540,164 and $1,330,114. Contract for 
Section 6D cost $946,086. Cultural resource investigations 
cost $335,541. Area office equipment cost 
$18,912. Engineering and design and supervision and 
administration costs were $2,604,782 and $1,765,- 
038, respectively. 
Condition at end of fiscal year. Construction of the 
project commenced in September 1975 and is 47 percent 
complete. 
50. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Features transferred to the Central and Southern 
Florida Flood Control District and Southwest Florida 
Water Management District were inspected quarterly 
during the fiscal year at a total cost of $27,180. 
52. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 685, 84th Congress, as amended (preauthorization). 
(See Table 9-T.) 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th Congress 
and antecedent legislation). 
Federal costs for the fiscal year were $154,262 for 
the Disaster Preparedness Program, and $179,229 for 
national emergency and mobilization readiness plans. 
Emergency streambank and shoreline protection 
activities pursuant to Section 14, Public Law 526, 
79th Congress as amended (preauthorization.) 
Federal costs for the fiscal year were $68,088 for 
Barrio Barrero, Rincon, Puerto Rico; and $8,816 for 
Highway 187, El Terraplan, Puerto Rico. 
General Investigations 
53. SURVEYS 
Hired labor costs during the fiscal year (all Federal 
funds) were: navigation studies, $251,981; flood 
damage prevention studies, $825,046; shoreline protection 
studies, $42,729; and special studies $289 for 
a total of $1,120,045. 
54. COLLECTION AND STUDY OF 
BASIC DATA 
The requirement for preparation of regular flood 
plain information studies has been rescinded. FPI 
studies that deal with land use changes will continue to 
be prepared. FPMS Unit Jacksonville, Fla., $64,867; 
Gold Coast hurricane evacuation study, $900; and 
Technical services, $93,048. 
51. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 9-S.) 
9-24

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
Aquatic Plant 
Control (R&H 
Act of 1965) 
(Federal Funds) 
Arecibo Harbor, 
P.R. 
(Federal Funds) 
Atlantic 
Intracoastal 
Waterway 
between 
Norfolk, Va., and 
St. John's River, 
Fla. 
(Federal Funds) 
Bakers Haulover 
Inlet, Fla. 
(Federal Funds) 
Canaveral 
Harbor, Fla. 
(Federal Funds) 
(Contrib. Funds) 
Channel from 
Naples to Big 
Marco Pass, Fla. 
(Federal Funds) 
(Contrib. Funds) 
Charlotte 
Harbor, Fla. 
(Federal Funds) 
Cross-Florida 
Barge Canal 
(Federal Funds) 
Eau Gallic 
Harbor. Fla. 
(Federal Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost. 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint:
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp: 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint:
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
1,991,000 2,106,000 
2,074,745 2,134,771 
451,914 1,564,000 
42,308 1,960,302 
1,073,000 
3,121,103 
200,000 
132,655 
4,924,000 
5,014,000 
9,063 
9,324 
82,438 
6,884 
20.685 
2,240,347 
S1,995,672 
-70,000 
458,802 
149,329 
122,033 
500,000 
246,727 
1, 120,000 
1,114,598 
972,087 
i ,048,073 
858 
1,531,0(X) 
1,949,141 
76.37() 
73,073 
2,626,000 2,300,000 
2,622,586 2, 190,290 
200,253 
190,474 
6,656 
-8,290 
16,241 
3,300,000 
241,023 
5,790,500 
5,628,309 
103,000 
83,296 
62,526 
2,024,000 
2,005,725 
310,(XX) 
242, 145 
1,593,(XX) 
1,578,798 
341,000 
365,282 
8,429 
8,630 
7,525 
10,290 
148,000 
2,886,993 
3,853,000 
4,014,577 
33,523 
623,853 
642,523 
- 116,918 
-99,761 
25,000(XX) 
82,642 
1,563,(XX) 
1,603,791 
375,(XX) 172,(XX) 
345,057 202,624 
9-25 
21,794,670 
21,614,149 
1, 128,075' 
1, 128,075' 
4,286,699 
4,286,232 
361,225' 
361,225' 
5,300,742 
5,300,742 
243,235 
243,235' 
185,688 
185,688 
1 1,569,9 I04 
10,929,264 
36,641,321 
36,606,531 
1, 106,000 
1 ,036,523 
305,290 
305,290 
1 ,628,847 
1,626,747 
159,975 
1 59,975 
533,169 
533,1595 
11,489,133 
11,487,983 
63,197,473 
63,186,455 
19,444,463 
19,381,933' 
9,627 
9,627 
708,284 
705,668

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
I10. Femrnandina 
Harbor, Fla. 
(Federal Funds) 
(Contrib. Funds) 
II. Fort Myers Beach 
Channel, Fla. 
(Federal Funds) 
12. Fort Pierce 
Harbor, Fla. 
(Federal Funds) 
(Contrib. Funds) 
13. Gulf Intracoastal 
Waterway., 
Caloosahatchee 
River to Anclote 
River, Fla. 
(Federal Funds) 
14. Intracoastal 
Waterway., 
Jacksonville to 
Miami, Fla. 
(Federal Funds) 
(Contrib. Funds) 
Jacksonville 
Harbor. Fla. 
(Federal Funds) 
(Contrib. Funds) 
16. Johns Pass. Fla. 
(Federal Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint:
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint:
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint:
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint:
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint:
Approp. 
Cost 
7,141 
716,(XX) 
965,781 
7,(XX) 
7,141 
13,521 
13,654 
1,215,646 
985,514 
773 ,(XX) 
115,111 
1.207.620 
1.284.573 
-2,(XX) 
-116 
3,768,928 
4,368,503 
-35 
2,261 ,(XX) 
2,244,910 
116 
17,575 
577,652 
594,389 
35 
56,464 
46,375 
-134,834 
125.783 
170,3(X) 
810,601 
709 
939.046 
936. 138 
77.2 14 
63,391 
1 25,(XX) 
139,039 
929,962 
852,580 
3.(07,099 5.365.7(X) 7.355.(XX) 
339,545 8.048.812 7.362.380 
6.657 
8.136 
342 
37.419 
37.419 
I 
342.839 
341.589 
367,561 
377,389 
136.675 
153.614 
88.2(X) 
98,667 
391 .036 
486,735 
61,0(X) 
4,147,816 
4.112,506 
22,734,019 
22,732,344 
812,(X)0 
811,054 
158,140 
158,140 
1.086,446 
I ,086,185 
356,056 
356,056 
3.790,835 
3,787,097 
18,574 
18,574 
8. 112.557 
8.122,557 
5.879.738' 
5,877.556' 
19,251,598" 
19.251.598" 
26,425,4672 
26,407,439' 
61,(XX) 
- 47.596,278 
- 47.596.278' 
771.854 55.502.239" 
781 .020 55.5(X). 198 ' 
- 102.813 
- 102.813 
- 927.654" 
- 927,654' 
25.(XX) 25,(XX) 
268.()15 
269.265 
82.098" 
82.098" 
1 .407.830() 
1.407.830 
9-26 
15.

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
I 7. Longboat 
Pass. Fla. 
(Federal Funds) 
(Contrib. Funds) 
18. Mayaguez 
Harbor. P.R. 
(Federal Funds) 
19. Melbourne 
Harbor. Fla. 
(Federal Funds) 
20. Miami Harbor., 
Fla. 
(Federal Funds) 
(Contrib. Funds) 
21. New Pass 
Sarasota, Fla. 
(Federal Funds) 
22. Okeechobee 
Waterway, Fla. 
(Federal Funds) 
(Contrib. Funds) 
23. Oklawaha 
River, Fla. 
(Federal Funds) 
24. Palm Beach 
Harbor, Fla. 
(Federal Funds) 
New Work: 
Approp. 
Cost 
Maint:
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
-414 
3.229 
340.(XX) 
327. 124 
-708 41.025 
71 1 33.523 
I 30.(XX) 
271,4 16 
29.868 
29.868 
76.(XX) 
69.582 
1(X).(XX) 
93,539 
57,259 
57.259 
8,239 
9,119 
80,(XX) 
77,577 
1,387,0(X00 
1,690,333 
40),(XX) 
31.430 
875,000 
702,717 
2,439 
1.746,3(X) 
1,720,4(X) 
S10,0(X) 
18, I07 
-3.984 
3,039 
228.(X)0 
233.567 
I .(X)).(XX) 
269,054 
116,512 
60,856 
894,(X)0 
892,444 
262 
2.084,(X(X) 
2,022,254 
4,062 
7,594 
232.525 
245,401 
11,154 
11.632 
251.338 
252.188 
5,190,(XX) 
3,871,286 
129.211 
183.359 
75,893 
77,449 
I.020,233 
I ,020,233 
1.400.487 
I .4(X)00.487 
172.324 
172.324 
168.187 
168.187 
1.032,674 
1,032.674 
17.696 
17.696 
634.864 
634.863 
30.986.066 
28.919.556 
2.51 1.825 
2.510.317 
2.262.710" 
2.262,7 10 
45,81 I" 
45,811" 
3.108.304 
3,108,304 
- 21,4(X),590'" 
- 21,4(X),590'" 
1,683,(XX) 3 1 .544.966 
1,779,336 31.460,886' 
- 503.7(X) 
- 503.7(X) 
45,572 
48,143 
45,697 3,725,(XX) 685,212 
208,803 3,721,562 711,384 
315,264 
315,264, 
2,048,320" 
2,044,552 
6,904,021 
6,90)4,021 ' 
9.210,1 18 
9,207.7142 
9-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
25. Ponce de Leon 
InleFtl,a. 
(Federal Funds) 
(Contrib. Funds) 
26. Ponce Harbor, 
P.R. 
(Federal Funds) 
27. Port Everglades 
Harbor, Fla. 
(Federal Funds) 
28. Removal of 
Aquatic Growth 
(Federal Funds) 
29. St. Augustine 
Harbor, Fla. 
(Federal Funds) 
30. St. Johns 
River, Fla. 
Jacksonville 
to Lake Harney 
(Federal Funds) 
31. St. Lucie 
Inlet, Fla. 
(Federal Funds) 
(Contrib. Funds) 
32. San Juan 
Harbor, P.R. 
(Federal Funds) 
33. Tampa Harbor, 
Fla. (Main 
Project) 
(Federal Funds) 
(Contrib. Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint:
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work & Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
- - 
323,000 2,600,000 
161,230 2,742,016 
50,000 
5,977 
-21,388 
622 
3,641,995 
212 
212 
25,025 
32,771 
38,000 
35,020 
1,533,415 
350,000 
304,179 
2,092,000 2,622,000 
2,192,273 2,803,286 
8,112 
8,128 
9,968 
9,977 
900,000 
758,819 
32,094 
71,798 
136,000 
250,909 
-60,159 
23,539 
21,502,000 
19,855,010 
1,290,000 
1,036,867 
135,000 
116,418 
80,000 
74,285 
33,615 
33,589 
514,688 
286,610 
273,332 
394,043 
176,942 
168,086 
150,725 
9,870,000 
9,352,559 
210,700 
463,233 
60,000 
63,490 
- - 1,953,277 
- - 1,953,277 
6,465,846 106,192 15,234,586 
6,477,022 108,285 15,217,466 
- - 2,415,600 
- - 2,415,600 
- - 1,379,000 
- - 612,663 
25,000 
6,187 
131 
2,500 
3,500,000 
4,165,925 
170,889 
2 16,660 
25,795 
23,506 
24,117 
53,000 
283,422 
36,810 
36,790 
482,9076 
452,698' 
S1,327,870 
1,327,870 
44,308,773" 
44,246,954' 
1,598,480 
1,598,410 
2,465,000 2,474,000 28,011,370 
2,450,831 2,477,801 27,977,510 
90,000 367,049 
74,992 387,772 
324,99 1 
320,979 
585 
2,075,000 
2,079,004 
233,983 
382,492 
16,039 
20,077 
30,986 
60,091 
57,293 
74,172 
170,229 2,339,241 
150,401 2,376,226 
17,015,000 
1 8,838,450 
170,000 
165,443 
100,000 
111,481 
1,354,000 
1,669,404 
255,000 
262,361 
11,543 
1,476,434x 
1,476,434 - 
4,714,107 
4,714,107 
1,171,243' 
I,17 1,214'9 
1,300,299 
1,300,299 ' 
7,863,602 
7,859,3181 
4,716,006 
4,703,934 
3,086,026 
3,086,026 
13,774,968' 
13,774,968' 
14,341,181 
14,340,9786 
195,858,643 
195,787,073 
19,222,522 
19,218,1326 
1,029,962 
1,029,180 
9-28

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
37. Brevard County, 
Fla. 
(Federal Funds) 
(Contrib. Funds) 
38. Broward County, 
Fla. Beach Erosion 
Control and Hillsboro 
Inlet, Fla. 
Navigation Project 
(Federal Funds) 
(Contrib. Funds) 
39. Dade County, 
Fla. 
(Federal Funds) 
(Contrib. Funds) 
40. Dade County, 
N.of Haulover 
Beach, Fla. 
(Federal Funds) 
(Contrib. Funds) 
41. Duval County, 
Fla. 
(Federal Funds) 
(Contrib. Funds) 
42. Ft. Pierce, Fla. 
(Federal Funds) 
(Contrib. Funds) 
43. Palm Beach 
County, Fla. from 
Martin County line 
to Lake Worth 
Inlet and from 
South Lake Worth 
Inlet to Broward 
County line 
(Federal Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
- 
1,321 
576 
4,334 
614 
614 
510,000 
-487,351 
230,000 
1,221,775 
-3,315 
3,637 
4,730,000 
4,773,650 
246,200 
50,000 
59,751 
100,000 1,000,000 
55,449 258,970 
- 200,000 
29,159 23,089 
69 4,969 
7,107 
40,(XX) 
44,904 
17,945 
-1,797 
50,000 
-300,000 
279,393 
360,000 
33,204 
15,000 
2,350,000 
1,096,216 
2,370,000 
926,428 
-415 
415 
3,598 
2,346,492 
2,274,749 
29,001 
29,001 
2,262,000 
2,257,081 
- 11,033,100 
17,615 11,000,483 
- 26,884 
- 26,884 
- 1,758,841- 
- 1,758,841' 
940,000 
1,759,116 
741,000 
683,129 
135,000 
12,939 
-506,000 
1,221,457 
272,094 
3(X),(XX) 2,050,(XX) -300,000 
48,942 1,884,034 35,599 
33,283,956 
33,165,993 
23,575,085 
23,186, 133" 
150,000 
12,939 
8,912,900 
8,381,739 
6,712,400 
5,336,041 
1, 175,448w 
1,151,021 ' 
31,734 
31,734 
773,0(X) 
769,412 
3,920,834 
3,839,409 
13,621 
13,621 
9-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 8.6 Sept. 30, 1986 
44. Pinellas County, New Work: 
Fla. Approp. - 700,000 -1 30,000 803,000 3,9 1 2,693 
(Federal Funds) Cost 542,817 290,475 316,002 943,102 3,614,327 
Maint: 
Approp. - - - - 5,625 
Cost - - - - 5,625 
(Contrib. Funds) New Work: 
Approp. - -140,706 368,342 549,250 3,102,64 I 
Cost 505,218 217,566 50,710 439,840 2,637,896 
47. Central and New Work: 
Southern Florida Approp. 9,000,000 8,600,000 8,400,000 6,065,000 292,121,397 
(Federal Funds) Cost 6,865,717 11,422,711 7,439,279 7,814,088 29 I,129,760 
Maint: 
Approp. 3,980,000 4,292,000 4,073,000 4,733,500 51,234,46 I 
Cost 3,953,714 4,550,595 4,254,980 4,916,056 51, 180,26 I 
(Contrib. Funds) New Work: 
Approp. 1,271,700 2,179,837 1,770,263 1,322,261 55,373,636 
Cost 756,016 1,652,885 1,030,971 813,118 52,561,791 
48. Four River New Work: 
Basins, Fla. Approp. 3,595,000 -1,600,000 1,050,000 903,000 72,380,095' 
(Federal Funds) Cost 1,076,456 764,489 564,734 1,714,126 72,241,196' 
(Contrib. Funds) New Work: 
Approp. 352,148 335,412 647,000 360,000 12,746,860 
Cost 389,206 335,379 359,508 347,003 12,370,477 
49. Portugues and New Work: 
Bucana Rivers, Approp. 18,990,000 18,700,000 22,600,000 20,949,000 141,374,568 
P.R. Cost 19,476,203 16,702,794 24,210,107 21,238,471 139,702,052 
(Federal Funds) 
9-30

JACKSONVILLE, FLA. DISTRICT 
1. Excludes $288,000 contributed funds for new work. 
2. Includes $97,566 for previous project. 
3. Excludes $243,235 contributed funds for new work. 
4. Excludes $700,000 contributed by NASA in connection with construction 
of lock. 
5. Includes $113,000 for new work on previous project; excludes 
$15.563 expended for new work on existing project from contributed 
funds. 
6. Excludes $1 13,744 for maintenance and operation of dams. 
7. Includes $160,367 expended for recreation facilities. 
8. Includes $10,128 cost for reconnaissance and detailed project report 
prepared under Sec. 107 modification to the project. Excludes $1,095 
contributed funds for new work. 
9. Includes $515,479 for new work for previous projects: $8,472 for 
new work on Sunshine Skyway Channel; and $9,707 for new work for 
Cats Point Channel. Excludes $14,473 contributed funds for new work. 
10. Includes $450,749 for maintenance for previous project. 
11. Includes $94,776 for work for previous projects. Excludes 
$2,199,842 expended from public works funds for new work. 
12. Includes $213,222 for maintenance on previous projects and 
$3,179 operating and care under provisions of permanent indefinite 
appropriation. 
13. Includes $3,520,137 new work on previous project and $290,013 
for new work expended from public works funds. 
14. Includes $543,399 maintenance on previous projects. 
15. Includes unused contributed funds of $64,136 returned to local 
interests. 
16. Project authorized December 2, 1964, by Chief of Engineers 
under Section 1 07 of 1960 R&H Act and by Section 110 of the 1 966 R&H 
Act. Cost of new work excludes $53,732 contributed funds. 
17. Includes $2,202,126 expended from public work funds for new 
work. Includes costs of $4,957,795 for recreation facilities. 
18. Includes $343,479 work-in-kind and $160,429 in costs for north 
jetty recreation facility. 
19. Excludes $45,811 contributed funds for new work. 
20. Includes $16,222,275 for new work under previous project, 
$626,925 for recreation facilities (Code 710), and $27,574 for reconnaissance 
and detailed project report prepared under Section 107 modification 
to the project. 
21. Includes $7,581,150 for maintenance for previous projects. Excludes 
$1,000 for maintenance from contributed funds on previous 
projects, $67,558 which represents services rendered without reimbursement,
and $113,744 for maintenance and operations of dams. 
22. Includes $3,912 for new work for previous projects. 
23. Includes $1 ,414 for operating and care under provisions for the 
permanent indefinite appropriation. 
24. Includes $80,000 new work from public works funds. Excludes 
$509,506 contributed funds. 
25. Includes $30,000 for maintenance from public works funds. 
26. Includes $11,588 expended for restudy, but excludes $21,960 
expended for new work from contributed funds. 
27. Excludes $1,033,069 contributed funds. 
28. Includes $71,303 for new work on previous project. Excludes 
$137,500 contributed funds. 
29. Baresford cutoff and completion of cutoffs and easing of bends in 
Putnam Lake and Volusia Counties in inactive status were deauthorized by 
Public Law 93-251 section 12. Includes $29,566 for new work under 
previous project. 
30. Includes $25,838 under previous project. 
31. Includes $26,689 for new work under previous project. 
32. Includes $747,684 for new work under previous project. Excludes 
$100,000 expended for new work from contributed funds. 
33. Includes $44,730 in maintenance under previous project. 
34. Includes $853,050 for new work under previous project. Excludes 
$270,466 for new work for Hillsborough River and $13,939 for new work 
from contributed funds. Includes $15,000 Appropriation for new work 
East Bay Channel. 
35. Includes $17,107 for maintenance under previous project. 
36. Excludes work-in-kind. 
37. Includes $2,294,134 for reimbursement costs to Bal Harbour. 
38. Excludes unused contributed funds of $17,969 returned to local 
interests. 
39. Excludes $300,083 in property for services furnished by local 
interests in lieu of cash contribution. 
40. Excludes $15,543 for property received without reimbursement 
and R&H Funds, expended on previous projects (see cost and financial 
statement for Okeechobee Waterway, Fla., project for these costs). Excludes 
$100,000 advanced by local interests toward federal costs. 
41. Includes costs of $89,691 for recreation facilities at Moss Bluff 
and $2,638,272 at Lake Tarpon. 
9-31

TABLE 9-B 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
October 27, 1965 
August 26, 1937 
March 4, 1913 
June 20, 1939 
July 14, 1960 
March 2, 1945 
October 23, 1962 
June 20, 1938 
July 14, 1960 
July 25, 1912 
March 3, 1925 
July 3, 1930 
August 26, 1937 
May 17, 1950 
P.L. 675/77 
July 23, 1942 
June 20, 1938 
June 14, 1880 
July 13, 1892 
March 2, 1907 
AQUATIC PLANT CONTROL (See Section 1 of Text) 
Control and progressive eradication of obnoxious aquatic plants, and 
continued research to develop best method of control 
ARECIBO HARBOR, P.R. (See Section 2 of Text) 
Construction of breakwater 1,200 feet long and dredging channel 
25 feet deep and 400 feet wide with flare at entrance and widening 
at inner end to form a maneuvering area. 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA. AND THE ST. JOHNS RIVER, FLA. 
(See Section 3 of Text) 
Channel 7 x 100 feet 
Channel 12 feet deep and 90-150 feet wide with cut-offs 
BAKERS HAULOVER (See Section 4 of Text) 
Channel II x 200 feet in ocean entrance, thence 8 x 100 feet to 
Intracoastal Waterway; Marina basin 8 x 200 feet; reconstruction of 
jetties and protection of inlet shores. 
CANAVERAL HARBOR, FLA. (See Section 5 of Text) 
Entrance channel jetties, a turning basin enclosed by a dike, and a 
barge canal with a lock 
Maintain improved channel, turning basin, enlarge barge channel and 
lock, relocate dike, provide channel and turning basin west of 
35-foot turning basin, construct and operate sand-transfer plant 
CHANNEL FROM NAPLES TO BIG MARCO PASS, FLA. 
(See Section 6 of Text) 
Interior channel 6 x 70 feet 
Channel 12 x 150 feet from the Gulf to Gordon Pass, thence 
10 x 100 feet to a point 400 feet south of U.S. Highway 41 Bridge, 
thence 10 x 70 feet to bridge and two turning basins 
CHARLOTTE HARBOR, FLA. (See Section 7 of Text) 
Channel 24 x 300 feet through Gulf through Boca Grande entrance 
Depth of 27 feet at entrance and width of 500 feet at the bend 
Channel 10 x 100 feet to Punta Gorda and a turning basin 
Depth of 30 feet at entrance and width of 700 feet at bend 
Depth of 32 feet in entrance channel 
CROSS-FLORIDA BARGE CANAL (See Section 8 of Text) 
Barge Canal 12 x 150 feet 
EAU GALLIE HARBOR, FLA. (See Section 9 of Text) 
Channel 8 x 100 feet and a turning basin 
FERNANDINA HARBOR, FLA. (See Section 10 of Text) 
Entrance jetties 
Raising and extending jetties to provide 19-foot depth 
Improvement of inner harbor to obtain 20- to 24-foot depth and 400- to 
600-foot channel width 
H. Doc. 251, 89th Cong., 
1stse ss. 
Rivers & Harbors Committee 
Doc. 43, 75th Cong., 1st sess. 
H.Doc. 898, 62nd Cong., 
2d sess. 
H.Doc. 618, 75th Cong., 
3d sess. 
H.Doc. 189, 86th Cong., 
1stse ss. 
H.Doc. 367, 77th Cong., 
1st sess. 
S.Doc. 140, 87th Cong., 
2d sess. 
H.Doc. 596, 75th Cong., 
3d sess. 
H.Doc. 183, 86th Cong., 
Ist sess. 
H.Doc. 699, 62nd Cong., 
2d sess. 
H.Doc. 113, 66th Cong. 
1st sess. 
Rivers and Harbors Committee 
Doc. 1, 70th Cong., I1st sess. 
Rivers and Harbors Committee 
Doc. 95, 74th Cong., 2d sess. 
H.Doc. 186, 81st Cong., 
Ist sess. 
H.Doc. 109, 79th Cong., 
1st sess. 
H.Doc. 497, 75th Cong., 
3rd sess. 
Annual Report 1879 
Annual Report 1891 & 1896 
H.Doc. 388, 59th Cong., 
Ist sess. 
9-32

TABLE 9-B (Continued) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 25, 1910 
March 3, 1925 
June 20, 1938 
March 2, 1945 
May 17, 1950 
July 14, 1960 
Auth. by Chief of 
Engineers 
December 6, 1968, 
under Sec. 107 of 
1960 R&H Act. 
Def. Act. of 
March 4, 1931 
War Dept. Approp. 
Act, March 4, 1933 
August 30, 1935 
March 2, 1945 
June 30, 1948 
May 17, 1950 
September 3, 1954 
May 10-16, 1957 
Auth. March I, 1962 
By Senate 
and House 
Public Works 
Committee 
Auth. by Chief of 
Engineers 
March 1, 1963, 
under Sec. 107 of 
1960 R&H Act 
January 21, 1927 
July 3, 1930 
PARA June 26, 1934 
Combining improvement of Fernandina Harbor and Cumberland Sound 
under the general heading of Fernandina Harbor 
Provided for a 26-foot channel 
Provided for the 28-foot channel and turning basin 
Provided for reducing the maximum width of turning basin from 
1,000 to 800 feet, for shifting channel line in this vicinity 50 feet 
northwesterly and for including in authorized project small area 
dredged by Rayonier, Inc. 
Provided for 32-foot channel and turning basin 
FORT MYERS BEACH, FLA. (See Section 11 of Text) 
12- x 150 foot channel in San Carlos Bay, thence 11 x 125 feet 
in Matanzas Pass to upper shrimp terminals 
Extension of 11- x 125-foot channel easterly about 2,000 feet to and 
including a turning basin adjacent to natural deep water in 
Matanzas Pass 
FORT PIERCE HARBOR, FLA. (See Section 12 of Text) 
Expenditure of $20,000 for dredging channel, maintenance by 
local interests 
Expenditure of up to $30,000 for dredging channel 
Maintaining channels, jetties, and revetments, and enlarging channels 
and turning basin to existing project dimensions 
INTRACOASTAL WATERWAY, CALOOSAHATCHEE RIVER 
TO ANCLOTE RIVER, FLA. (See Section 13 of Text) 
9- x 100-foot channel; deepening channel at Caseys Pass to 9 feet and 
construction of highway bridge at Venice 
Original route may be modified at no excess cost to U.S. 
Any route in Venice-Lemon Bay area may be used 
Use of alternate Route C-1 in Venice-Lemon Bay area 
Local interests to bear costs of Venice Avenue highway bridge and 
any other necessary crossing over Route C-1 
Sunshine Skyway Channel to be improved and maintained to 
9 x 100 feet 
H.Doc. 227, 68th Cong., 
Ists ess. 
H.Doc. 284, 77th Cong., 
1sts ess. 
H.Doc. 284, 87th Cong., 
Ists ess. 
H.Doc. 662, 80th Cong., 2d sess. 
H.Doc. 183, 86th Cong., 
Ist sess. 
Specified in Act 
Specified in Act 
H.Doc. 252, 72nd Cong., 
1st sess. and Rivers and 
Harbors Committee Doc. 21 
74th Cong., I1st sess. 
H.Doc. 371, 76th Cong., 
Ist sess. 
Specified in Act 
Specified in Act 
Specified in Act 
H.Doc. 109, 85th Cong., 
1st sess. 
6- x 80-fioot channel in Boca Ciega Bay 
INTRACOASTAL WATERWAY, JACKSONVILLE TO 
MIAMI, FLA. (See Section 14 of Text) 
Channel 8 x 75 feet from Jacksonville to Miami 
Channel width of 1(X) feet 
Operation and care of Palm Valley Bridge 
H.Doc. 586, 69th Cong., 2d sess. 
S.Doc. 71, 71st Cong., 2d sess. 
Specified in Act 
9-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
August 26, 1937 
March 2, 1945 
Do. 
Do. 
July 3, 1958 
Chief of Engineers 
Report of July 22, 
1960, Mod. 12-foot 
channel 
March 2, 1907 
Auth. by Chief of 
Engineers 
December 2, 1964 
Under Sec. 107 of 
1960 R&H Act and 
Sec. 10 of 1966 
R&H Act. 
Auth. by Chief of 
Engineers 
April 20, 1976 
under Sec. 107 of 
1960 R&H Act, as 
amended 
August 30, 1935 
August 20, 1937 
July 3, 1930 
PWA Program 
September 6, 1933 
June 13, 1902 
March 2, 1907 
March 4, 1913 
March 3, 1925 
Turning basin at Jacksonville Beach 
Channel 12 x 125 feet 
Side channel and turning basin at Sebastian 
Turning basin at Vero Beach 
Maintenance of side channel at Daytona Beach 
Channel 10 x 125 feet from Ft. Pierce to Miami 
JACKSONVILLE HARBOR, FLA. (See Section 15 of Text) 
ST. JOHNS RIVER, FLA. OPPOSITE THE CITY OF 
JACKSONVILLE 
The 24-foot area from Hogan Creek to Florida East Coast 
Railroad bridge 
JOHN'S PASS, FLA. (See Section 16 of Text) 
Channel 10 x 150 feet in the gulf, 8 x 100 feet inside pass, 
6 x 100 feet to IWW-2.6 miles long 
LONGBOAT PASS, FLA. (See Section 17 of Text) 
12- x 150-foot entrance channel from Gulf of Mexico to Longboat 
Bridge; 10- x 100-foot channel from Longboat Bridge northeasterly 
to IWW; channel from north channel to Cortez Bridge 
MAYAGUEZ HARBOR, P.R. (See Section 18 of Text) 
Approach channel 30 feet deep to and along deep water terminal 
MELBOURNE HARBOR, FLA. (See Section 19 of Text) 
Channel 8 x 100 feet and a turning basin 
MIAMI HARBOR, FLA. (See Section 20 of Text) 
MIAMI RIVER 
The 15-foot channel in Miami River, 150 feet wide at the mouth 
The channel at the Dinner Key Airport 
An 18-foot channel in a landcut across the peninsula and construction 
of the north jetty 
Construction of the south jetty and increase of channel width 
to 100 feet 
Modification of local cooperation requirements imposed by the Act of 
July 25, 1912 
A channel 25 feet deep with present widths from the ocean to 
Biscayne Bay, thence 200 feet wide across the bay to but not 
including the municipal turning basin, and extension of both jetties 
H.Doc. 180, 75th Cong., 
1st sess. 
H.Doc. 740, 79th Cong., 
2d sess. 
H.Doc. 336, 76th Cong., 
Ist sess. 
H.Doc. 261, 76th Cong., 
Ist sess. 
H.Doc. 222, 85th Cong., 
Ist sess. 
H.Doc. 663, 59th Cong., 
Ist sess. 
H.Doc. 215, 72nd Cong., Ist sess. 
& River and Harbor Committee 
Doc. 1, 73rd Cong., 1st sess. 
H.Doc. 390, 74th Cong., 
2d sess. 
Specified in Act 
S.Doc. 95, 72d Cong., I1sts ess. 
and specified in Act 
H.Doc. 622, 56th Cong., 
Ist sess. (Annual Report 
1900, p. 1987) 
Specified in Act 
Specified in Act 
H.Doc. 516, 67th Cong., 
4th sess. 
9-34

TABLE 9-B (Continued) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1930 
August 30, 1935 
August 26, 1937 
March 2, 1945 
March 2, 1945 
July 14, 1960 
August 13, 1968 
Auth. by Chief of 
Engineers 
April 20, 1964 
under Sec. 107 of 
1960 R&H Act 
PARA June 26, 1934 
August 26, 1937 
March 2, 1945 
Do. 
Auth. by Chief of 
Engineers 
November 5, 1968, 
under Sec. 107 of 
1960 R&H Act 
September 19, 1890 
March 2, 1907 
June 25, 1910 
July 25, 1912 
July 27, 1916 
PARA June 26, 1934 
A channel width of 300 feet across the bay and enlarging the 
municipal turning basin, with expenditures thereon limited to 
$200,000 
A depth of 30 feet from the ocean to and in the turning basin, with 
the existing authorized project widths, including the 300-foot width 
in the channel across the bay 
Extending the turning basin 200 feet to the southward 
The Virginia Key improvement 
For incorporation of the project for Miami River in that for Miami 
Harbor, the widening at the mouth of Miami River to existing project 
widths; the channels from the mouth of Miami River to the turninrg 
basin and to Government Cut; and the channel from Miami 
River to the harbor of refuge, provided that local interest contribute 
one-third of the cost. 
Deletion of Virginia Key development and the Dinner Key approach 
channel, widening the existing ship channel by easing the ocean 
bend and increasing the width of the 300-foot-wide section to 400 
feet, enlarging the existing turning basin 300 feet along both the 
south and northeasterly sides, and dredging a turning basin along 
the north side of Fisher Island about 39 acres in extent and 30 feet 
in depth 
Enlarging existing entrance channel to 38 x 500 feet, deepening 
existing 400-foot-wide channel across Biscayne Bay to 36 feet; 
deepening existing turning basins at Biscayne Blvd. terminal and 
Fisher Island to 36 feet. 
NEW PASS, SARASOTA, FLA. (See Section 21 of Text) 
10- x 150-foot entrance channel; 8- x 100-foot inner channels; and 
8-foot-deep turning basins at Payne Terminal and City Pier 
OKEECHOBEE WATERWAY, FLA. (See Section 22 of Text) 
Operation and care of locks and dams provided for with funds 
from R&H appropriations 
New lock and weir structure in St. Lucie Canal 
Deepening to 8 feet from Ft. Myers to Jacksonville-Miami waterway 
near Stuart via channel across lake from Clewiston 
Channel to yacht basin at Ft. Myers and a basin at Stuart 
Enlarge existing 8- x 90-foot section of Okeechobee Waterway for 
about 5 miles upstream from Ft. Myers to 10 x 100 feet 
OKLAWAHA RIVER, FLA. (See Section 23 of Text) 
Clearing obstructions for channel 4 feet deep from mouth to Leesburg 
Channel 6 feet deep from mouth to head of Silver Springs Run 
Maintenance of levels in the lakes at head of river 
Acceptance of certain artificial waterways in lieu of portions 
of natural river bed 
Operation and care of lock and dam provided for with funds from 
appropriations for rivers and harbors 
Rivers and Harbors Committee 
Doc. 15, 71st Cong., 2d sess. 
Sen. Comm. Print. 
73d Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 86, 74th Cong., 2d sess. 
S.Doc. 251, 79th Cong., 2d sess. 
H.Doc. 91, 79th Cong., 
1st sess. 
S.Doc. 71, 85th Cong., 
2d sess. 
S.Doc. 93, 90th Cong., 
2d sess. 
Specified in Act 
Rivers and Harbors Committee 
Doc. 28, 75th Cong., I1sts ess. 
H.Doc. 696, 76th Cong., 
3d sess. 
H.Doc. 736, 79th Cong., 
2d sess. 
Annual Report 1889, p. 1360 
H.Doc. 782, 59th Cong., 
Ist sess. 
Specified in Acts 
Specified in Act 
Specified in Act 
9-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 13, 1934 
December 10, 1934 
August 30, 1935 
March 2, 1945 
May 17, 1950 
July 14, 1960 
October 27, 1965 
March 3, 1925 
August 30, 1935 
March 2, 1945 
H.R. September 
23, 1976 
SR. October 1, 
1976 
July 3, 1930 
August 30, 1935 
June 20, 1938 
July 24, 1946 
July 3, 1958 
H.R. May 9, 1974 
S.R. May 31, 1974 
PALM BEACH HARBOR, FLA. (See Section 24 of Text) 
Maintenance of improvement previously constructed by local interests 
Deepening the channels and turning basin, as constructed by local 
interests to 20 feet 
Authorized the work previously approved by Public Works 
Administration, and widening the channels to existing project 
dimensions, enlarging the 700-foot-square turning basin eastward 
removing the obstructive point on south side of the inlet, revetting 
the banks of the inlet, and restoring existing jetties 
Deepening the channels and turning basin to 25 feet 
Extending the turning basin 550 feet southward over a 900-foot width, 
with a flare to the east; provided that local interests may be reimbursed 
not to exceed $305,000 for work done by them on this 
modification subsequent to July 1, 1949 
An entrance channel 35 feet deep, 400 feet wide, and 0.8 mile long, 
merging with an inner channel 33 feet deep, 300 feet wide and 0.3 
mile long, thence flaring into a turning basin, 1,400 feet north-south 
by a minimum of 1,200 feet east-west 
PONCE DE LEON INLET, FLA. (See Section 25 of Text) 
Widening and deepening channels; jetties on north and south side 
of inlet; a weir in the north jetty and an impoundment basin inside 
the weir 
PONCE HARBOR, P.R. (See Section 26 of Text) 
Dredging 3 continuous areas, aggregating 153 acres, to depths of 30, 
18, and 9 feet, and construction of a seawall, costs to be shared by 
U.S. and local interests 
Modified conditions of local cooperation to provide that U.S. undertake 
all dredging at Federal expense and return local funds previously 
contributed for dredging, all other portions of the improvement 
hereafter to be at the expense of local interests 
Eliminate previously authorized 9-foot dredging area, and provided for 
dredging 30-foot-depth area and 18 acres off the municipal pier and 
for construction of the breakwater off Punta Carenero 
Eliminate previously authorized 18-foot and a portion of the 30-foot 
project outside the proposed 36-foot and a portion of the adjacent 
to the municipal bulkhead. Channel 36 x 600 feet from Caribbean 
Sea to harbor; channel 36 x 400 feet into harbor; and a 36-foot 
turning basin 
PORT EVERGLADES HARBOR, FLA. (See Section 27 of Text) 
Maintenance of harbor constructed by local interests 
Enlarge entrance channel and complete turning basin to 
1,200 feet square 
Widen turning basin 350 feet on north side 
Widen turning basin 200 feet on north side, 500 feet on south side and 
enlarge flare at entrance channel 
Deepen and widen entrance channel on a new alinement and increase 
turning basin in size and depth 
Deepen and widen entrance channel, enlarge turning basin, widen 
Pier 7 channel, maintenance of Berth 18 channel, and planning for 
a south jetty fishing walkway with construction contingent upon 
need as developed by detailed postauthorization studies 
H.Doc. 185, 73d Cong., 
2d sess. 
Recommended by Chief of 
Engineers to Public 
Works Administration 
October 17, 1934 
H.Doc. 185, 73d Cong., 
2d sess. and Rivers and 
Harbors Committee Doc. 42, 
74th Cong., I1st sess. 
H.Doc. 530, 78th Cong., 2d sess. 
H.Doc. 704, 80th Cong., 
2d sess. 
H.Doc. 283, 86th Cong., 
1st sess. (contains latest 
published map) 
H.Doc. 74, 89th Cong., 
1st sess. 
H.Doc. 532, 67th Cong., 
4th sess. 
Rivers and Harbors Committee 
Doc. 18, 72d Cong., I1st sess. 
H.Doc. 745, 79th Cong., 
2d sess. 
H.Doc. 532, 94th Cong., 
2d sess. 
H.Doc. 357, 71st Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 25, 74th Cong., I1sts ess. 
H.Doc. 545, 75th Cong., 3d sess. 
H.Doc. 768, 78th Cong., 
2d sess. 
H.Doc. 346, 85th Cong., 
2d sess. 
H.Doc. 144, 93d. Cong., 
Ist sess. 
9-36

TABLE 9-B (Continued) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 3, 1899 
June 13, 1902 
March 3, 1905 
June 20, 1938 
May 17, 1950 
March 3, 1899 
March 2, 1919 
June 14, 1880 
June 25, 1910 
July 3, 1930 
March 2, 1945 
March 2, 1945 
July 24, 1946 
March 2, 1945 
November 7, 1966 
H.R. May 9, 1974 
SR. May 31, 1974 
August 8, 1917 
September 22, 1922 
July 3, 1930 
REMOVAL OF AQUATIC GROWTH FROM NAVIGABLE 
WATERS IN THE STATE OF FLORIDA (See Section 28 of Text) 
Construction and operation of a suitable vessel and use of log booms 
for removal of water hyacinths in the navigable waters of the State 
Extermination and removal o 1 water hyacinths by any mechanical, 
chemical, or other means 
Prohibits use of any chemical process injurious to cattle 
ST. AUGUSTINE HARBOR, FLA. (See Section 29 of Text) 
Channel 27 x 200 feet protected by a groin 
Channel 16 x 200 feet across bar, and thence 12 feet deep to 
Intracoastal Waterway; jetty on south side of inlet; future landward 
extension of groin and jetty; and channel 10 x 100 feet in San 
Sebastian River 
ST. JOHNS RIVER, FLA., JACKSONVILLE TO 
LAKE HARNEY (See Section 30 of Text) 
A channel 13 feet deep and 200 feet wide from Jacksonville 
to Palatka 
The improvement of Deep Creek 
Two jetties at Volusia Bar (Maintenance only; new work completed 
under previous project.) 
A channel 100 feet wide, 8 feet deep from Palatka to Sanford with a 
side channel to Enterprise, and thence 5 feet deep to Lake Harney 
Cutoffs at Butcher Bend, Shake Creek, and Starks Landing, and 
easing bends at other points 
A channel 10 feet deep and 100 feet wide from Palatka to Sanford, 
with a side channel to Enterprise and with cutoffs and easing of 
bends 
Combining the two projects above into a single project for St. Johns 
River, Fla., Jacksonville to Lake Harney, and for a cutoff 5 feet 
deep and 75 feet wide between Lake Monroe and the vicinity of 
Osteen Bridge (Woodruff Creek Cutoff) 
A channel 12 feet deep and 100 feet wide from Palatka to Sanford, 
and in the branch to Enterprise 
ST. LUCIE INLET, FLA. (See Section 31 of Text) 
Channel 10 x 200 feet 
Modification to maintain existing channel 6 x 100 feet 
Extending north jetty and modifying existing jetty to provide a sand 
bypass weir section; excavation of sand impoundment basin; 
construction of south jetty with walkway for recreational fishing; 
channel 10 x 500 feet thru bar cut, tapering to 150 feet thru the 
inlet, and 100 feet and 7 feet deep to the Intracoastal Waterway; and 
transfer of 380,000 cubic yards of material to the south beach during 
each two-year maintenance period 
SAN JUAN HARBOR, P.R. (See Section 32 of Text) 
Anchorage (inner harbor) area of 206 acres and San Antonio Channel 
to 30-foot depth 
Substitution of a 68-acre area 30 feet deep along southeasterly side of 
anchorage area, for one 25 acres in extent and of same depth extending 
easterly from eastern end of the San Antonio project channel 
Modified condition of local cooperation 
Annual Report 1899 
Specified in Act 
Specified in Act 
H.Doc. 555, 75th Cong., 3d sess. 
H.Doc. 133, 81st Cong., 
1stse ss. 
H.Doc. 523, 55th Cong., 2d sess. 
and Annual Report for 
1899, p. 1343 
H.Doc. 699, 63rd Cong., 2d sess. 
Annual Report for 1879, 
pp. 795-798 
H.Doc. 1111, 60th Cong., 
2d sess. 
H.Doc. 691, 69th Cong., 
2d sess. 
H. Doc. 603, 76th Cong., 
3d sess. 
H.Doc. 445, 78th Cong., 
2d sess. 
S. Doc. 208, 79th Cong., 
2d sess. 
H.Doc. 391, 77th Cong., I1st sess. 
H.Doc. 508, 89th Cong., 2d sess. 
H.Doc. 294, 93rd Cong., 
Ist sess. 
H.Doc. 865, 63d Cong., 
2d sess. 
Specified in Act 
H.Doc. 45, 71st Cong., 2d sess. 
9-37

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
August 30, 1935 
August 26, 1937 
October 17, 1940 
March 2, 1945 
July 3, 1958 
August 4, 1976 
March 3, 1899 
March 3, 1905 
June 25, 1910 
August 8, 1917 
March 3, 1899 
September 22, 1922 
July 3, 1930 
August 30, 1935 
Entrance channel across outer bar 38 feet deep and 800 feet wide, and 
thence across bay to anchorage area (Anegado Reach Channel) 30 
feet deep and 700 feet wide and increasing anchorage area to 239 
acres to 30-foot depth 
Widening Anegado Reach Channel and increasing anchorage area to 
329 acres 
Removal to 8-foot depth of Anegado, Largo, and Capitanejo Shoals, 
and dredging to 30-foot depth the entrance channel and turning 
basin to the Graving Dock 
Maintenance of the 30-foot depth entrance channel and turning basin 
to the Army Terminal 
Deepening portions of entrance and approach channels and basins to 
Army Terminal and San Antonio Pier areas to 35-45 feet; new 
32-foot depth Puerto Nuevo Channel; new 36-foot depth anchorage 
A bar channel 48 by 800 feet, shifting the centerline 350 feet west; 
deepening Anegado Channel in steps from 46 to 40 feet while 
reducing width to 800 feet; deepening Army Terminal Channel and 
turning basin to 40 feet while widening the channel to 450 feet; 
deepening Puerto Nuevo Channel to 40 feet and widening it to 400 
feet; deepening Graving Dock Channel to 40 feet at existing 
400-foot width; deepening San Antonio Channel to 38 feet at varying 
widths, minimum of 500 feet; deepening cruise ship basin to 36 
feet at an irregular width; maintaining Sabana Approach Channel at 
30 by 250 feet; provide a 38-foot depth in Anchorage Area "E" with 
irregular width; six mooring dolphins for vessels using the area. 
TAMPA HARBOR, FLA. (See Section 33 of Text) 
TAMPA BAY 
For a channel 27 feet deep from the Gulf of Mexico to Port Tampa, 500 
feet wide across the bar and 300 feet wide in the bay 
For a channel depth of 26 feet with sufficient width from the'Gulf of 
Mexico to Port Tampa 
TAMPA AND HILLSBOROUGH BAYS 
For a depth of 24 feet in Hillsborough Bay 
For a 27-foot depth from Gulf of Mexico up to and in the several 
channels of Hillsborough Bay, the widths to be 500 feet on the bar, 
300 feet in Tampa Bay, Ybor, and Garrison Channels, and 200 feet 
in Hillsborough Bay, Sparkman, and Seddon Channels, with turning 
basins at the mouth of Hillsborough and at Ybor Estuary 
HILLSBOROUGH RIVER 
For a 12-foot channel to within 100 feet of the Lafayette St. highway 
bridge (maintenance only; new work completed under a previous 
project under the title Improving Hillsborough Bay, Fla.) 
TAMPA HARBOR 
Consolidation of the above projects to form a single project for 
Tampa Harbor 
Increasing the depth of Egmont Channel to 29 feet and the width of 
Sparkman Channel to 300 feet 
For a depth of 32 feet and a width of 600 feet on Egmont Bar, a depth 
of 30 feet and a width of 400 feet in Mullet Key Cut, and a depth of 
30 feet and a width of 300 feet in all other project channels in Tampa 
Harbor (except in Hillsborough River and in the channel leading 
to Alafia River); and for a turning basin 2,000 feet long and 500 
feet in maximum width at the entrance to the Port Tampa terminals 
R&H Comm. Doc. 38, 
74th Cong., I1st sess. 
R&H Comm. Doc. 42, 
75th Cong., 1st sess. 
H.Doc. 364, 76th Cong., 
1st sess. 
Specified in Act 
H.Doc. 38, 85th Cong., 
Ist sess. 
H.Doc. 574, 94th Cong., 
2d sess. 
H.Doc. 52, 55th Cong., 
3d sess. (Also printed in 
Annual Report 1899, p. 1640) 
Channel dimensions specified 
in Act 
Specified in Act 
H.Doc. 634, 61st Cong., 2d sess. 
H.Doc. 634, 61st Cong., 
1st sess. 
H.Doc. 545, 55th Cong., 
2d sess. and Annual Report 
1898, pp. 1357-1360 
Specified in Act 
H.Doc. 100, 70th Cong., 
1st sess. 
S.Doc. 22, 72d Cong., 
Ist sess. 
9-38

TABLE 9-B (Continued) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 20, 1938 
Do. 
March 2, 1945 
Do. 
Do. 
May 17, 1950 
September 3, 1954 
October 23, 1962 
December 31, 1970 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
For widening the bend between Sparkman Channel and Cut D of 
Hillsborough Bay Channel by 250 feet; widening Ybor Channel to 
400 feet and extending the turning basin at the west end of Garrison 
Channel (mouth of Hillsborough River) easterly for 300 feet 
For construction of a breakwater at Peter O. Knight Field, Davis 
Islands, its maintenance to be assumed by local interest 
For widening Sparkman Channel to 400 feet and Ybor Channel to 
500 feet; widening the bend between Sparkman and Garrison 
Channels an additional 250 feet to extend the turning basin westerly; 
and widening the bend between Seddon and Garrison Channels by 
150 feet (in lieu of 300 feet previously authorized) to extend the 
turning basin easterly 
For a channel 9 feet deep and 100 feet wide in the Hillsborough River 
for about 2.4 miles above the upper end of the existing 12-foot 
channel, and for the removal of obstructions thence to the Florida 
Avenue Bridge 
For a channel 25 feet deep and 150 feet wide from the Hillsborough 
Bay channel to and including a turning basin in the Alafia River 
(Revoked by Act of May 17, 1950) 
For deepening Egmont Channel to 36 feet; enlarging Mullet Key Cut, 
Tampa Bay Channel, Hillsborough Bay Channel, Port Tampa Channel 
and Port Tampa turning basin to present project dimensions; 
deepening Sparkman Channel and Ybor turning basin to 34 feet; a 
channel 30 feet deep and 200 feet wide from Hillsborough Bay 
Channel to and including a turning basin in Alafia River, 700 feet 
wide and I,200 feet long (in lieu of improvement previously 
authorized); and substantial widening at entrance, bends, and turns 
Extended removal of obstructions in Hillsborough River to City Water 
Works Dam. Maintenance of cleared channel to be assumed by local 
interests 
Channel and turning basin at Port Sutton 30 feet deep, Ybor Channel 
34 x 400 feet 
For federal maintenance of Port Sutton Channel, 280 feet wide and an 
irregularly shaped turning basin both to a depth of 34 feet 
Enlarge entrance channel across Egmont Bar to 46 x 700 feet from 
the Gulf to Mullet Key 
Enlarge Mullet Key Cut Channel to 44 x 600 feet 
Enlarge Tampa Bay Channel to 44 x 500 feet from Mullet Key Cut 
through Tampa Bay to the junction of Hillsborough Bay and Port 
Tampa Channels 
Enlarge Hillsborough Bay Channel to 44 x 500 feet from the junction 
with Tampa Bay and Port Tampa Channels to the junction with Port 
Sutton entrance channel, and thence deepening to a depth of 42 
feet at the existing width of 400 feet to the junction with Seddon 
and Sparkman Channels 
Enlarge Port Sutton entrance channel to 44 x 400 feet 
Enlarge Port Sutton turning basin to a depth of 44 feet and a turning 
diameter of 1,200 feet 
Deepening Sparkman Channel to 42 x 400 feet 
Deepening Ybor Channel to 40 x 300 feet 
Enlarge turning basin at the entrance to Ybor Channel to a depth of 
42 feet and an additional width of 200 feet on the southwest edge 
of the present basin 
Deepening Port Tampa Channel to 42 feet at its existing width from 
the junction with Hillsborough and Tampa Bay Channels to the 
turning basin 
S.Doc. 164, 75th Cong., 
3d sess. 
Sen. Comm. Print. 
76th Cong., 1st sess. 
S.Doc. 183, 78th Cong., 
2d sess. 
H.Doc. 119, 77th Cong., 
Ist sess. 
S.Doc. 16, 77th Cong., 
1st sess. 
H.Doc. 258, 81st Cong., 
Ist sess. 
H.Doc. 567, 81st Cong., 
2d sess. 
H.Doc. 529, 87th Cong., 
2d sess. 
H.Doc. 150, 91st Cong., 
Ist sess. 
H.Doc. 401, 91st Cong., 
2d sess. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
9-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Do. 
Do. 
Do. 
Do. 
Do. 
August 15, 1985 
BEACH EROSION 
CONTROL PROJECTS 
August 13, 1968 
October 27, 1965 
August 13, 1968 
August 15, 1985 
October 27, 1965 
October 27, 1965 
October 23, 1962 
November 7, 1966 
FLOOD CONTROL 
PROJECTS 
June 30, 1948 
September 3, 1954 
July 14, 1960 
October 23, 1962 
Deepening the Port Tampa turning basin to 42 feet over its existing 
length of 2,000 feet and width of 900 feet 
An entrance channel in East Bay 44 x 400 feet and 500 feet north 
from the Port Sutton turning basin for a distance of about 2,000 feet 
A turning basin in East Bay at a depth of 44 feet and with a turning 
diameter of 1,200 feet 
An approach channel in East Bay 44 x 300 feet north from the East 
Bay turning basin for a distance of about 2,500 feet 
Maintenance of Port Sutton Terminal channel to 44 x 200 feet for a 
distance of 4,000 feet 
Maintenance of East Bay Channel to 34 x 300 feet for a 
distance of 5,500 feet 
BREVARD COUNTY, FLA. (See Section 37 of Text) 
Federal participation in cost of shore protection project 
BROWARD COUNTY, FLA., BEACH EROSION CONTROL AND 
HILLSBORO INLET, FLA., NAVIGATION PROJECT 
(See Section 38 of Text) 
Improvement for beach erosion control in Broward County, Fla. and a 
combined beach erosion and navigation improvement to Hillsboro 
Inlet and the shore north thereof to Port Everglades 
DADE COUNTY, FLA. (See Section 39 of Text) 
Federal participation in cost of shore protection and hurricane-flood 
control project 
DADE COUNTY-NORTH OF HAULOVER BEACH, FLA. 
(See Section 40 of Text) 
Federal participation in cost of shore protection and hurricane-flood 
control project 
DUVAL COUNTY, FLA. (See Section 41 of Text) 
Federal participation in cost of shore protection project 
FORT PIERCE, FLA. (See Section 42 of Text) 
Federal participation in cost of local shore protection projects 
PALM BEACH COUNTY, FLA., FROM MARTIN COUNTY LINE 
TO LAKE WORTH INLET AND FROM SOUTH LAKE WORTH 
INLET TO BROWARD COUNTY LINE (See Section 43 of Text) 
Federal participation in cost of local shore protection project and 
sand-transfer plant 
PINELLAS COUNTY, FLA. (See Section 44 of Text) 
Federal participation in cost of shore protection project 
CENTRAL AND SOUTHERN FLORIDA (See Section 47 of Text) 
First phase of comprehensive plan for flood control and other purposes 
Modification and expansion of authorization to include entire 
comprehensive plan of improvement 
Canals, levees, and water-control and drainage structures in the 
Nicodemus Slough area, Glades County 
Flood protection on Boggy Creek, near Orlando 
Do. 
Do. 
Do. 
Do. 
Do. 
H.Doc. 236, 99th Cong., 
Ist sess. 
H.Doc. 352, 90th Cong., 2d sess. 
H.Doc. 91, 89th Cong., 
Ist sess. 
H.Doc. 335, 90th Cong., 
2d sess. 
H.Doc. 236, 99th Cong., 
Ist sess. 
H.Doc. 273, 89th Cong., 1st sess. 
H.Doc. 84, 89th Cong., 1st sess. 
H.Doc. 164, 87th Cong., 
1st sess. 
H.Doc. 519, 89th Cong., 2d sess. 
H.Doc. 643, 80th Cong., 
2d sess. (Contains latest 
published map) 
H.Doc. 643, 80th Cong., 
2d sess. 
S.Doc. 53, 86th Cong., 
Ist sess. 
S.Doc. 125, 87th Cong., 2d sess. 
9-40

TABLE 9-B (Continued) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Do. 
Do. 
Do. 
Do. 
October 27, 1965 
Do. 
August 13, 1968 
Do. 
Approved 
December 17, 1970 
under the provisions 
of Section 
201 of the Flood 
Control Act of 
1965 
October 23, 1962 
December 31, 1970 
Flood protection in the Cutler Drain area, near Miami 
Flood control and drainage works for South Dade County 
Project for Shingle Creek between Clear Lake and Lake Tohopekaliga 
for flood control and major drainage, including development of 
Reedy Creek Swamp 
Improvement of easterly section of West Palm Beach Canal for flood 
control and major drainage 
Primary works for flood control and major drainage in southwest 
Dade County 
Primary works for flood control and major drainage in Hendry County 
Gravity drainage in Martin County and distribution of available water 
supplies to portions of Martin and St. Lucie Counties 
Improvement of supply, distribution, and conservation of water 
resources in Central and Southern Florida, including Lake 
Okeechobee agricultural area, Everglades National Park and other 
related areas 
Navigation improvements suitable for recreational craft 
FOUR RIVER BASINS, FLA. (See Section 48 of Text) 
Control of floods and improvement of drainage, and for water 
conservation through construction of necessary canals, levees, 
reservoirs, and control structures 
PORTUGUES AND BUCANA RIVERS, P.R. 
(See Section 49 of Text) 
LAGO de CERRILLOS, P.R. 
Multiple purpose dam and lake for flood control, water supply, 
and recreation 
LAGO de PORTUGUES, P.R. 
Multiple purpose dam and lake for flood control, water supply 
and recreation 
PONCE, P.R. 
Diversion and enlargement of existing channels through Ponce for 
flood control 
S.Doc. 123, 87th Cong., 
2d sess. 
S.Doc. 138, 87th Cong., 
2d sess. 
S.Doc. 139, 87th Cong., 
2d sess. 
S.Doc. 146, 87th Cong., 
2d sess. 
S.Doc. 20, 89th Cong., 
Ist sess. 
H.Doc. 102, 88th Cong., 
Ist sess. 
S.Doc. 101, 90th Cong., 
2d sess. 
H.Doc. 369, 90th Cong., 
2d sess. 
H.Doc. 394, 91st Cong., 
2d sess. 
H.Doc. 585, 87th Cong., 
2d sess. 
H.Doc. 422, 91st Cong., 
2d sess. 
9-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 9-C CANAVERAL HARBOR, FLA. PROJECT 
DATA RELATIVE TO LOCK 
(See Section 5 of Text) 
Distance to nearest town 9.9 miles via 12-foot barge canal and 
Intracoastal Waterway 
Name of nearest town Cocoa, Fla. 
Distance from Intracoastal Waterway 6.5 miles 
Lock Dimensions 90' wide; 600' long' 
Lift Varies with tide 
Depth of sills (mlw, ocean) 14 feet 
Character of foundation Piles in sand 
Year completed and opened to navigation 1965 
Contract Cost $2,966,539 
'56 x 400 feet authorized. At request of NASA lock was constructed increased to 600 feet to be compatible with increased width. Opera- 
90 feet wide with NASA bearing additional cost ($700,000). Length tion and maintenance of lock is a Federal responsibility. 
CROSS-FLORIDA BARGE CANAL PROJECT 
LOCKS AND DAMS 
(See Section 8 of Text) 
Henry H. Buckman 
Lock 
Nearest town 
(miles) 
Miles from Atlantic 
Intracoastal 
Waterway 
Lock dimensions (ft.)' 
Normal lift (ft.) 
Depth over sills 
at normal pool levels: 
Upper (ft.) 
Lower (ft.) 
Character of 
foundation 
Kind of dam 
Type const. 
Percent complete 
Estimated contract 
cost 
Palatka, 
1 1.2 
90.4 
84 x 600 
20 
14 
15 
Piles in 
sand 
Movable 
Earth' 
100 
$6,094,000 
R.N. 
Eureka Lock Bert Dosh 
and Dam Lock 
Sparr, 
15.8 
111.4 
84 x 600 
20 
17 
14 
Piles in 
sand 
Movable 
Earth 
100 
Ocala, 
8.9 
127.7 
84 x 600 
0- 15' 
16-31 
16 
Piles in 
sand 
None 
0 
$7,975,000 $7,430,000 $9,500,000 
'Clear width and greatest available length. 
Pool level varies with natural ground water profile from minimum 
elevation of 40 feet to maximum elevation of 55 feet. 
With concrete spillway and movable gates. 
9-42 
TABLE 9-D 
Dunnellon 
Lock 
Dunnellon, 
2.5 
156.5 
84 x 600 
12-272 
16-31' 
18 
Rock 
None 
0 
Inglis Lock 
and Dam 
Inglis, 
3.2 
168.6 
84 x 600 
28 
18 
15 
Rock 
Movable 
Earth 
100 
$7,800,000

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-E CROSS-FLORIDA BARGE CANAL 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 8 of Text) 
Work Performed Cost 
New Work: 
Engineering and Design $ 75,484 
Supervision and Administration 7,185 
Total 82,642 
Operation and Maintenance: 
Operations: 
Operations of locks, operations and maintenance of 
dams, spillways, reservoirs and bypasses, debris 
removal, performance monitoring system $ 472,620 
Contract maintenance of locks, grounds maintenance, 
trash removal, potable water testing 60,461 
Visitor Assistance 1,884 
Operation and maintenance of recreation facilities, 
sanitary facilities, service and maintenance of 
traffic counters and contract maintenance of grounds 362,249 
Condition and operations studies and periodic inspections 84,288 
Water quality studies, data collection and processing, 
reimbursement to USGS, water control analysis, 
Lake Oklawaha and Inglis Bypass, and water management control 71,027 
Real Estate audits, inspections and outgrants 12,377 
OSHA medical exams 3,519 
Supervision and Administration 15,711 
Sub-Total 1,084,181 
Maintenance: 
Maintenance of dams and spillways $ 19,733 
Maintenance of locks and lock repair contract 54,479 
Maintenance of roads, bridges 3,754 
Maintenance of permanent operating equipment (Recreation) 33,656 
Maintenance and purchase of non-recreational permanent operating equipment 147,814 
Bank stabilization-maintenance of slopes and berms, 
Rodman and Inglis dams, and bank 
stabilization contract. 114,924 
Maintenance of canals, clearing and snagging 82,973 
Engineering and Design 55,427 
Supervision and Inspection 5,950 
Real Estate encroachments 8,844 
Sub-Total 527,554 
Income credits - 7,944 
Total 1,603,791 
Income from Recreation Fees 23,406 
9-43

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 9-F OKEECHOBEE WATERWAY 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 22 of Text) 
Work Performed Cost 
Operations and Maintenance: 
Operations: 
Operations of Locks, and Performance 
Monitoring System 418,102 
Contract maintenance buildings grounds, potable 
water testing, repair and replacement of project 
signs, operation and maintenance of District 
communications network 335,461 
Natural resource management 80,231 
Management of recreation areas and facilities 297,232 
Real estate management and energy conservation reports 29,801 
OSHA medical exams 2,400 
Condition and operation studies, periodic inspections 102,219 
Supervision and Administration 36,515 
Sub-Total 1,301,961 
Maintenance: 
Maintenance of locks, and contract 
maintenance of locks 192,462 
Real estate acquisitions, surveys and encroachments 32,726 
Maintenance of recreational facilities 15,333 
Maintenance of permanent operating equipment, non-recreational 88,456 
Bank Stabilization 1,690 
Contract operation of reservoir and dam maintenance 89,526 
Channel and canal maintenance 42,296 
Engineering and Design 12,418 
Supervision and Inspection 39,215 
Sub-Total 514, 122 
Income Credits - 36,747 
Total 1,779,336 
Income from Recreation Fees 17,940 
9-44

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-G REMOVAL OF AQUATIC GROWTH FROM NAVIGABLE WATERS 
IN THE STATE OF FLORIDA 
CONTROL OPERATIONS 
(See Section 28 of Text) 
Locality Acres Controlled Cost 
St. John's River and tributaries and 
Withlacoochee, Kissimmee and Crystal Rivers 16,608 $1,618,615 
Okeechobee Waterway and tributaries 4,508 439,314 
Acquisition and maintenance of airboats, 
engines, and work tools 141,454 
Income credits - 402 
Operation of communications network 18,000 
OSHA medical exams 1i15 
Engineering design 54,670 
Supervision and Administration 206,035 
Total 21, I 16 2,477,801 
TABLE 9-H NAVIGATION PROJECTS ON WHICH RECONNAISSANCE AND 
CONDITION SURVEYS ONLY WERE CONDUCTED DURING FISCAL YEAR 
(See Section 34 of Text) 
Date Cost Incurred 
Survey During 
Project Conducted Period' 
Anclote River, Fla. FY 1986 $20,677 
Cedar Keys Harbor, Fla. FY 1986 9,608 
Christiansted Harbor, P.R. 1985 723 
Clearwater Pass, Fla. FY 1986 10,766 
Courtney Channel, Fla. FY 1986 7,971 
Crystal River, Fla. FY 1986 14,920 
Daytona Beach Side Channel, Fla. FY 1986 7,277 
Key West Harbor, Fla. 1985 849 
Kissimmee River, Fla. FY 1986 23,841 
Largo Sound Channel, Fla. FY 1986 9,809 
Manatee River, Fla. FY 1986 10,295 
Miami River, Fla. 1985 2,187 
New River, Fla. FY 1986 7,714 
Orange River, Fla. 1985 390 
Pass-a-Grille, Fla. FY 1986 6,583 
Pithlachascotee River, Fla. FY 1986 7,885 
St. Petersburg Harbor, Fla. FY 1986 15,015 
Suwannee River, Fla. FY 1986 23,289 
'Includes Supervision and Administration 
9-45

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 35 of Text)
For Last Cost to Sept. 30, 1986 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Anclote River, Fla. 1974 $ 267,427 $ 628,142 
Aquatic Plant Control, Fla. 
(R&H Acts of 1958 & 1962) 1968 2,619,700' - 
Atlantic Gulf Ship Canal, Fla. 1939 5,099,153 - 
Bayport, Fla.' 1972 58,495� - 
Cedar Keys Harbor, Fla. 1977 168,569 - 70,240 
Christiansted Harbor, St. Croix, V.I.6 1964 303,317 57,800 
Clearwater Pass, Fla."' 1980 46,3497 1,220,271 
Courtenay Channel, Fla.' 1940 22,846 26,779 
Crystal River, Fla.' 1941 25,000 128,000 
Everglades Harbor, Fla.' 1964 221,509 51,034 
Fajardo Harbor, P.R.' 1945 - - 
Guayanes Harbor, P.R.' 1945 - - 
Gulf Intracoastal Waterway 
St. Marks to Tampa Bay, Fla.' 1974 38,850 - 
Homosassa River, Fla.' 1937 3,9994 23,334 
Horseshoe Cove, Fla. 1977 347,521 137,493 
Hudson River, Fla.' 1974 9,889 - 
Intracoastal Waterway, Miami to Key West, Fla. 1963 243,079 28,046 
Key West Harbor, Fla.' 1972 1,548,892' 534,623 
Kissimmee River, Fla.' 1931 23,479 112,954 
Lake Crescent and Dunns Creek, Fla." 1931 10,276 9,035 
Largo Sound Channel, Fla.' '
2 1966 117,443' 51,149 
Little Manatee River, Fla. " 1949 11,903' - 
Manatee River, Fla." 1970 123,350 194,516 
New River, Fla.' 1956 36,518 31,296 
Orange River, Fla.' 1962 2,000 24,918 
Ozona, Fla., channel and turning basin' 1963 105,527 15,089 
Palm Beach, Fla., side channel and basin' 1946 - - 
Pass-A-Grille Pass, Fla. ' '" 1966 41,297' 60,268 
Pithlachascotee River, Fla. 1973 400,000 '" 261,401 
Rice Creek, Fla.' 1957 85,2086 18,814 
St. Petersburg Harbor, Fla. 1983 255,6082 " 1,570,459"' 
St. Thomas Harbor, V.I.' 1949 1,989 - 
Steinhatchee River, Fla.' 1940 135,053 43,329 
Suwannee River, Fla." 1977 76,41822 219,261 
Withlacoochee River, Fla. ' 1969 614,912 370,305 
1. Complete. 
2. Excludes $918,205 contributed funds. 
3. Inactive. 
4. Includes $41,222 for reconnaissance and detailed project reports 
under Section 107 of the R&H Act of 1960. 
5. Includes $82,500 expended under previous project. Excludes 
$1,473 contributed funds. 
6. Project as modified by Chief of Engineers in report of June 30, 1961, 
is complete. Previously authorized depth of 25 feet in inactive status. 
7. Excludes $42,783 contributed funds. 
8. Excludes $36,000 contributed funds. 
9. In addition, $1,000 expended from contributed funds. 
10. Includes $27,500 for new work under previous project. Excludes 
$35,371 contributed funds. 
11. Deauthorized by Public Law 93-251, Section 12. 
12. Authorized April 20, 1964 by Chief of Engineers under Section 107 
of 1960 R&H Act. 
13. Includes $25,008 for detailed project report but excludes $86,716 
expended from contributed funds. 
14. Expended on restudy. 
15. Inactive portion of project deauthorized by Public Law 93-251, 
Section 12. 
16. Authorized November 19, 1964 by Chief of Engineers under Sections 107 
of R&H Act of 1960. 
17. Excludes $41,297 contributed funds. 
18. Excludes $215,728 contributed funds. 
19. Excludes $93,000 contributed funds. 
20. Includes $32,689 under previous project. 
21. Includes $20,532 under previous project. 
22. Includes $10,154 expended under previous project. 
23. Includes $30,000 expended under previous project. 
9-46 
TABLE 9-I

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-J OTHER AUTHORIZED BEACH EROSION PROJECTS 
(See Section 45 of Text)
For Last Cost to Sept. 30, 1986 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Cape Florida State Park 1969 34,862' - 
El Tuque Beach, Ponce, P.R. 1985 1,396,730 - 
Key West, Fla. 1963 96,3402 3,794 
Lee County, Fla. 197 - - 
Lido Key, Fla. 1971 - - 
Mullet Key, Fla. 1973 436,201 1,656 
Manatee County, Fla. 1983 217,600 - 
Punta Salinas, P.R. 1984 855,511 - 
Palm Beach County, Fla.f,r om Lake Worth Inletto 
South Lake Worth Inlet 1970 195,140 6,257 
San Juan, Puerto Rico 1965-- 
Virginia Key and Key Biscayne, Fla. 1978 1,667,2206 1,022 
1. Includes $2,462 cost of reconnaissance and detailed project reports 4. Excludes $360,000 contributed funds. 
but excludes $13,818 contributed funds. 5. Excludes $781,188 in property or services furnished by local inter- 
2. Excludes $192,168 contributed funds. ests in lieu of cash contribution. 
3. Excludes $187,133 contributed funds. 6. Excludes $714,522 contributed funds. 
TABLE 9-K CENTRAL AND SOUTHERN FLORIDA PROJECT 
PRINCIPAL FEATURES OF HURRICANE GATES 
(See Section 47 of Text) 
Depth Character 
Over of Year 
Gate' Nearest Town Distance Sills Founda- Comrn- Actual 
No. Name (miles) (ft.) tion pleted Cost 
2. Clewiston, Fla. 0.5 10 Pile 1935 $309,748 
3. Lake Harbor, Fla. 0.5 10 Rock 1935 316,938 
4. Belle Glade, Fla. 4.0 10 Rock 1935 350,025 
5. Canal Point, Fla. 0.0 10 Rock 1935 262,465 
6. Okeechobee, Fla. 0.5 7 Pile 1936 373,273 
'All are 50 feet wide with available length unlimited. They are constructed 
of concrete with steel sector gates and have no lift. 
Gate No. 6 has an auxiliary culvert spillway with automatic control. 
Moore Haven Lock serves as Hurricane Gate Structure 1. 
9-47

TABLE 9-L CENTRAL AND SOUTHERN FLORIDA PROJECT 
PRINCIPAL FEATURES OF LOCKS AND DAMS 
(See Section 47 of Text) 
Miles Elevation 
From Lock Normal of Normal Character Kind Kind 
Nearest Nearest Dimensions lift Pool Depth of of of of Percent 
Town Town (ft.) (ft.) surface (ft.) sills (ft.) foundation Dam Construction Complete 
W.P.Franklin 
Lock and Dam' 
S-65 Lock 
S-65A Lock 
S-65B Lock 
S-65C Lock 
S-65D Lock 
S-65E Lock 
Moore Haven 
Lock (HGS-1 
Mod.) 
S-310 
(HGS-2 Mod.) 
S-193 
(HGS-6 Mod.) 
S-308B 
(Port Mayaca) 
S-57 
S-58 
S-59 
S-60 
S-61 
S-62 
S-63 
S-63A 
S-96 
S-96A 
S-53 
S-55 
S-157 
S-158 
At Olga 
Frostproof 
Avon Park 
Sebring 
Sebring 
Okeechobee 
Okeechobee 
Moore Haven 
Clewiston 
Okeechobee 
Pahokee 
Ashton 
Ashton 
Kissimmee 
Ashton 
St. Cloud 
Ashton 
Ashton 
Ashton 
Sebastian 
Sebastian 
Eau Gallie 
Christmas 
Sebastian 
Titusville 
23 
26 
20 
25 
14 
10
0.5 
0.5 
0.5 
11 
9
5
666 
10 
12 
14 
14 
16 
8 
12 
4 
15 
56 x 400 
30 x 90 
30 x 90 
30 x 90 
30x 90 
30 x 90 
30 x 90 
50 x 250 
50 x 60 
50x 60 
56 x 400 
20 x 90 
20 x 90 
20 x 90 
20 x 90 
30 x 90 
20 x 90 
20 x 90 
20 x 90 
20 x 60 
20 x 60 
20 x 60 
20x 60 
20 x 60 
20 x 60 
2.5 
4.2 
6.3 
6.0 
7.2 
5.8 
4.6 
9.4 
5.0 
7.5 
4.0 
1.0 
2.0 
3.0 
2.0 
2.0 
3.0 
5.0 
4.5 
4.0 
7.5 
3.5 
10.0 
20.0 
4.5 
3.0 
48.5-52.3 
46.3 
40.0 
34.0 
26.8 
21.0 
15.5-17.5' 
15.5-17.5' 
15.5-17.5' 
15.5-17.5' 
62.0 
64.0 
58.0 
64.0 
55.0 
61.0 
62.0 
57.0 
24.0 
25.0 
17.5 
14.0 
20.0 
4.0 
14
6
6
6
6
6
6 
11 
12.9 
7.5 
18 
6
6666666666666 
Piles in 
clay 
Earth 
foundation, 
sand 
Earth 
foundation, 
sand 
Earth 
foundation, 
sand 
Earth 
foundation, 
sand 
Earth 
foundation, 
sand 
Earth 
foundation, 
sand 
Piles in 
sand 
Slab on 
sand 
Piles in 
sand and 
slab on sand 
Slab on 
sand 
Earth foundation, 
sand
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Movable 
None 
None 
None 
None 
None 
None 
None 
None 
None 
Fixed 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
Reinforced 
concrete 
Reinforced 
concrete 
rigid frame 
Reinforced 
concrete 
rigid frame 
Reinforced 
concrete 
rigid frame 
Reinforced 
concrete 
rigid frame 
Reinforced 
concrete 
rigid frame 
Reinforced 
concrete 
Steel sheet pile 
lockwalls 
Reinforced 
concrete 
Reinforced 
concrete 
Reinforced 
concrete 
Concrete and 
concrete 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
'Operation and care of W.P. Franklin Lock and Dam (S-79) isa Federal responsibility. 
Estimated (Oct. 1985). 
3The normal pool level varies seasonally between the two elevations. 
Contract 
Cost 
100 
100 
100 
100 
100 
100 
100
0 
100
0 
100
0
000 
100
000000000 
lO 
IO 
IO
O0 
!o 
$3,803,655.00 
$1,191,574.70 
$1,513,693.91 
$1,050,600.69 
$1,326,073.12 
$1,213,248.51 
$1,320,039.84 
$369,0002 
$3,448,406 
$523,000? 
$8,308,700.00 
$2,004,000? 
$2,004,000? 
$2,000,0002 
$2,004,000? 
$689,217.00 
$2,004,0002 
$2,004,0002 
$1,962,0002 
$1,757,0002 
$1,672,0002 
$1,623,0002 
$1,664,000? 
$2,116,0002 
$1,913,0002

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-M CENTRAL AND SOUTHERN FLORIDA PROJECT 
LOCAL COOPERATION 
(See Section 47 of Text) 
Flood Control Act Work Authorized Cash Contributions' 
June 30, 1948 First phase of comprehensive plan 15.0 
Sept. 3, 1954 Second phase of comprehensive plan 20.0 
July 14, 1960 Nicodemus Slough area 31.5 
Oct. 23, 1962 West Palm Beach Canal 12.8 
Boggy Creek Basin 29.7 
Shingle Creek Basin 25.9 
South Dade County area 19.2 
Reedy Creek Swamp 50.0 
Oct. 27, 1965 Southwest Dade County 46.0 
Hendry County area 19.5 
Aug. 13, 1968 Martin County 
Flood Control Features 34.0 
Irrigation Features 49.0 
Backflow Features 20.0 
PL 89-72 Recreation Features 50.0 
Water Resources - St. Lucie 20.0 
Recreation Features 50.0 
Approved Dec. 17, 1970 Navigation improvements suitable for 50.0 
under Provisions of recreational craft 
Section 201 of 1965 
Fklood Control Act 
'Computed on total contract cost and supervision and administration 
except for Reedy Creek Swamp and Recreation Features which are 
computed on all costs, including engineering and design and land. 
9-49

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 9-N CENTRAL AND SOUTHERN FLORIDA PROJECT 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 47 of Text) 
Work Performed Cost 
New Work: 
Construction of: 
Railroad bridges $ 554,103 
Channels and canals 598,068 
Levees 2,763,597 
Floodway control and diversion structures 885,123 
Pumping plants 586,081 
Buildings, grounds and utilities 5,011 
Cultural Resource Preservation 8,045 
Equipment operation 300 
Depreciation -308 
Engineering and design 2,499,329 
Supervision and administration 727,857 
Total cost 8,627,206 
Operations: 
Operation of locks, real estate outgrants, performance monitoring system 453,921 
Maintenance of buildings and grounds, operation and maintenance of District communications 
network, repair and replacement of project signs 225,576 
Patrol, inspection and maintenance of Herbert Hoover Dike, HGS 3, 4 and 5, operation and 
maintenance of drainage ditches, culverts and 16 spillways, mowing of levees 497,786 
Reimbursement to SFWMD for pumping plant operations 202,438 
Natural resource management 62,951 
Operation and Maintenance of recreation facilities, service and maintenance of traffic counters, 
master planning 292,104 
Condition and operation studies, periodic inspections, NOAA, dam safety 250,633 
Regulation of Lake Okeeshobee and three conversation areas, water control analysis, water 
quality studies, and data collection 765,083 
Energy conservation reports and OSHA medical exams 2,642 
Supervision and Administration 62,462 
Sub-Total 2,815,596 
Maintenance: 
Contract maintenance of locks 614,390 
Maintenance of recreational roads and bridges and permanent operating equipment 8,889 
Repair and stabilization of Crown Road, Herbert Hoover Dike, removal of weeds, rebuilding 
and regrading of levee slopes, modification and maintenance of safety barriers, HGS 3, 4 
and 5, cleaning landslide toe ditches, repair of culverts, replacement of fences, removal of 
trees, topping of trees, control of Melaleuca, rip rapping of slopes and berms 905,369 
Maintenance of hydrometrological network, maintenance of non recreational permanent 
operating equipment 428,006 
Maintenance of berms, fences and shrubs 12,260 
Clear landslide entrance channel to culverts, approach channels, hurricane gate structures and 
floodway channels 576 
Engineering and Design 2,404 
Supervision and Inspection 134,610 
Sub-Total 2, 106,504 
Income Credits - 6,044 
Total 4,916,056 
Income from recreation fees 23,074 
9-50

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-0 CENTRAL AND SOUTHERN FLORIDA PROJECT 
CONSTRUCTION COMPLETED UNDER EXISTING PROJECT DURING FISCAL YEAR 
(See Section 47 of Text) 
Date transferred to 
Flood Control District 
Construction for Operation and 
Feature Period Maintenance 
Bridges: 
B-127 (C-51) April 1983-December 1985- 
Channels and Canals: 
C-51 Summit to Forest Hill Blvds October 1985-September 1986- 
Levees: 
Herbert Hoover Dike Revetment- 
2nd Contract September 1983-January 1986- 
Structures: 
S-343A, 343B, 344, 346, 347 
and Modifications to L-28 
Borrow Canal and Tieback June 1983-May 1986 June 1984 
S-65 A, B, C & D Baffle Blocks 
and Riprap Repair September 1984-December 1985- 
TABLE 9-P CENTRAL AND SOUTHERN FLORIDA PROJECT 
STATUS OF WORK UNDER CONTRACT AT END OF FISCAL YEAR 
(See Section 47 of Text) 
Construction Approx. % 
Feature Started Complete 
Channels and Canals: 
C-51 East End May 1982 100 
Levees: 
Herbert Hoover Dike Revetment 
Ist Contract (4 miles) March 1983 99 
3rd Contract February 1985 35 
4th Contract July 1985 85 
5th Contract August 1986 1 
Structures: 
S-155 May 1982 100 
HGS-4 Replacement (S-351) January 1986 15 
9-51

Nearest town 
Name of nearest town 
Distance above mouth of River 
Lock dimensions 
Normal lift 
Elevation of normal pool surface 
Depth of sills 
Character of foundation 
Kind of dam 
Type of construction 
Percent complete 
Estimated Cost (including dam and spillway) 
20 miles 
Ocala, Fla. 
65.5 miles 
30 x 125 feet 
18.0 feet 
58 feet 
12 feet 
Piles in sand 
None 
Reinforced concrete 
100 
$1,990,138 
TABLE 9-R FOUR RIVER BASINS, FLORIDA PROJECT 
CONDITION AT END OF FISCAL YEAR 
(See Section 48 of Text) 
Date transferred to 
Construction Southwest Florida 
Feature Period for Operation and Maintenance 
Bridges: 
B-194 
Alteration of Facilities B-195 
B-594 
Alteration of Facilities B-196 
SCL RR Br., B-196 
Channels and Canals: 
C-135 
C-135, Sec. IA 
C-135, Sec. IB 
C-135, Sec. IC & 2 
C-135, Sec. 3A 
C-135, Sec. 3B 
C-135, Sec. 4A 
C-136 
C-231, Phase I 
C-231, Phase II 
C-331 
C-531 
C-534 
C-135 
Structures: 
S-160 
S-161 
S-162 
S-353 
Moss Bluff Lock and Spillway 
S-55 
Levees: 
L-212, Sec. I 
L-212, Sec. 2 
L-112 
L-112 & Floodway 
S-155 
S-163 
S-159 Middle & Lower 
S-159 Upper 
Recreation: 
Morris Bridge & 
Flint Creek Sites 
Dead River Sites 
July 1968 - Mar. 1970 
May 1971 - Jan. 1973 
Jan. 1973 - Jan. 1974 
Oct. 1972 - Jan. 1975 
Dec. 1972-July 1975 
May 1967 - Dec. 1968 
July 1966-Aug. 1967 
May 1968 - Sep. 1972 
Jan. 1971 - Dec. 1973 
Dec. 1972 - Apr. 1975 
Feb. 1975 - Aug. 1977 
Apr. 1976-Jan. 1979 
Aug. 1975 - May 1977 
July 1973 - Apr. 1975 
July 1973-Jan. 1974 
July 1967 - Sep. 1968 
Apr. 1966-Jan. 1969 
June 1970-July 1971 
March 1977 - Oct. 1980 
May 1967 - Dec. 1968 
Aug. 1975 - May 1977 
Apr. 1975 - June 1977 
July 1967-Sep. 1968 
Apr. 1967 - Mar. 1969 
July 1970-Feb. 1972 
June 1968 - July 1970 
July 1970-Sep. 1971 
March 1977-Oct. 1980 
May 1978-July 1981 
May 1978-July 1981 
May 1978-July 1981 
April 1979- Aug. 1981 
June 1979- Sep. 1981 
December 1982 - August 1984 
March 1985-July 1986 
9-52 
TABLE 9-Q 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
FOUR RIVER BASINS, FLORIDA PROJECT 
MOSS BLUFF LOCK 
(See Section 48 of Text) 
Not transferred 
Do. 
Do. 
Do. 
July 1975 
Dec. 1968 
Oct. 1967 
Not transferred 
Not transferred 
Oct. 1977 
Not transferred 
Not transferred 
Nov. 1977 
Dec. 1975 
Dec. 1975 
Sep. 1968 
Apr. 1969 
Nov. 1971 
Dec. 1968 
Nov. 1977 
Apr. 1977 
Nov. 1968 
Dec. 1975 
Not transferred 
Dec. 1975 
Dec. 1975 
Oct. 1980 
Jan. 1983 
Jan. 1983 
Jan. 1983 
Oct. 1981 
Jan. 1985 
Dec. 1986

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-S OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 51 of Text) 
For Last Cost to Sept. 30, 1986 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Arch Creek, Dade County, Fla. 1960 $66,485' 
Biscayne Bay, Fla., Hurricane Protection' 1966 
Hillsborough Bay, Fla.' 1969 
Phillippi Creek Basin, Fla.' 1966 
I. Excludes $11,734 cost of preauthorization studies. Project was 2. Deauthorized by Public Law 93-251, Section 12. 
authorized February 20, 1959, by Chief of Engineers under Section 
205 of the 1948 Flood Control Act as Modified by P.L. 685, 84th 
Congress. 
TABLE 9-T FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
PURSUANT TO SECTION 205, PUBLIC LAW 685, 
(PREAUTHORIZATION) 
(See Section 52 of Text) 
Study Identification Period Costs 
Detailed Project Report: 
Alligator Creek Basin, CL Fla. $ 28,382 
Bear Creek, Pinellas County, Fla. 2,026 
Crane Creek, Melbourne, Fla. 7,138 
Naquabo River, P.R. 66,557 
RioCibuco, Vega Baja, P.R. 70,301 
Rio Niqua, Arroyo, P.R. 25,016 
Sabana Grande, P.R. 33,593 
Savan Gut-St. Thomas, V.1. 170,473 
Seminole Basin-Largo, Fla. 45,265 
Turpentine Run, St. Thomas, V.I. 968 
Wares Creek, Bradenton, Fla. 5,308 
Whitaker Bayou, Sarasota, Fla. 3,582 
9-53

MOBILE, AL., DISTRICT * 
This district comprises a small portion of southeastern 
Tennessee, western Georgia, western Florida, 
all of Alabama south of Tennessee River Basin, eastern 
Mississippi, and a small portion of southeastern Louisiana 
embraced in drainage basins tributary to the Gulf of 
Mexico, west of Aucilla River Basin, to and including 
the Pascagoula River Basin. The Pearl River Basin, 
Mississippi was included as part of the Mobile District 
until 1 October 1981, when responsibilities were transferred 
to Vicksburg District, Lower Mississippi Valley 
Division. A section of the Gulf Intracoastal Waterway 
from St. Marks, Florida, to Lake Borgne Light No. 29, 
Louisiana is also within Mobile District. 
IMPROVEMENTS 
Navigation 
1. Apalachicola Bay, FL ................. . 
2. Aquatic Plant Control (R&H Act 
of 1965) ............................. 
3. Bayou Coden, AL ...................... 
4. Bayou La Batre, AL .................. 
5. Biloxi Harbor, MS ................... 
6. Biloxi Harbor, East Harrison 
County Canal, MS .................... 
7. Black Warrior and Tombigbee 
Rivers, AL .......................... 
8. Bon Secour River, AL ................. 
9. Dauphin Island Bay, AL ............... 
10. Dog and Fowl Rivers, AL .............. 
11. East Pass Channel from Gulf of Mexico 
into Choctawhatchee Bay, FL ........... 
12. Fly Creek, Fairhope, AL . ............. . 
13. Gulf Intracoastal Waterway 
between Apalachee Bay, FL 
and Mexican Border (Mobile 
District) ............................ 
14. Mobile Harbor, AL ................... 
15. Panama City Harbor, FL .............. 
16. Pascagoula Harbor, MS ............. 
17. Pensacola Harbor, FL ............... 
18. Perdido Pass Channel, AL ............ 
19. Waterway Connecting Tombigbee and 
Tennessee Rivers, AL and MS ........ 
20. Other Authorized Navigation 
Projects ............................. 
21. Navigation Work Under Special 
Authorization ....................... 
22. Reconnaissance and Condition 
Surveys ............................. 
Deauthorized Projects 
23. Deauthorized Projects ................ 
Page Beach Erosion Control 
10-3 24. Other Authorized Beach Erosion 
Control Project ..................... 
10-3 
10-3 
1 A- 
25. Beach Erosion Control Projects 
Under Special Authorization ........... 
10-4 Flood Control 
26. Okatibbee Lake, MS ................. 
10-5 27. Tallahala Creek Lake, Pascagoula 
River, MS ......................... 
10-5 28. Airport Road Bridge, 
10-6 Frankstown, MS ..................... 
10-6 29. Big Brown Creek and 
10-7 Tributary, Prentiss Co., MS ........... 
30. Boligee Canal Boligee, AL ............. 
10-7 31. Chattahoochee River, Eufaula, AL ..... 
10-7 32. County Road Bridge over 
Leaf River, Mahned, MS.............. 
33. Goodfood Creek, Chickasaw Co., MS ... 
34. Highway 39 Bridge, Gainesville, AL .... 
10-8 35. Houston School Rd. Bridge, 
10-9 Itawamba Co., MS.................. 
10-9 36. Leaf and Bowie Rivers, 
10-10 Hattiesburg, MS................... 
10-10 37. Martin Creek, Prentiss Co., MS ....... 
10-11 38. Murder Creek, 
East Brewton, AL .................... 
10-11 39. Murder and Burnt Corn Creeks, 
Brewton, AL ....................... 
10-1240. Noxubee River Relief Bridge, 
10-12 Shuqualak, MS ...................... 
41. Sewerline Protection, 
10-12 Valley, AL .......................... 
10-1242. Sope Creek, 
1012 Marietta, GA ........................ 
43. Tallabinella Creek, 
10-12 Chickasaw Co., MS ................. 
10-1 
10-12 
10-12 
10-12 
10-13 
10-13 
10-13 
10-13 
10-14 
10-14 
10-14 
10-14 
10-14 
10-14 
10-15 
10-15 
10-15 
10-15 
10-16 
10-16 
10-16

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
44. Tombigbee River (East Fork), 
MS and AL ......................... 
45. Tombigbee River Tributaries, 
MS and AL ......................... 
46. US Highway 11 Bridge, 
Fosters, AL ......................... 
47. Wolf Creek, US Highway 45 Bridge, 
Prentiss County, MS ................. 
48. Old Highway 82 Bridge, 
Columbus, MS ..................... 
49. Interstate 59 Bridges, 
Fosters, AL ........................ 
50. Inspection of Completed Flood 
Control Projects.................... 
51. Other Authorized Flood 
Control Projects ..................... 
52. Flood Control Work Under 
Special Authorization ................. 
Multiple Purpose Projects 
Including Power 
53. Alabama-Coosa Rivers, 
AL and GA ........................ 
53A. Carters Lake, GA ................... 
53B. Claiborne Lock and Dam, AL ......... 
53C. Robert F. Henry Lock and Dam, AL ... 
Page 
53D. Millers Ferry Lock and Dam, 
10-16 AL ................................ 
53E. Coosa River Navigation ............... 
10-17 54. Allatoona Lake, Coosa River 
Basin, GA .......................... 
10-17 55. Apalachicola, Chattahoochee, 
and Flint Rivers, 
10-17 AL, GA, and FL ..................... 
55A. Buford Dam, GA .................... 
10-17 55B. George W. Andrews Lock and 
10-17 Dam, AL and GA .................... 
10-1575 C. Jim Woodruff Lock and Dam, GA 
10-18 and FL ............................. 
10-185 5D. Spewrell Bluff Lake, GA ............. 
10-18 55E. Walter F. George Lock and Dam, 
AL and GA ........................ 
10-18 55F. West Point Lake, Chattahoochee 
River Basin, GA and AL ............. 
56. Scheduling Flood Control 
Reservoir Operations ................. 
10-18 
10-19 
10-19 
10-20 
General Investigations 
57. Surveys ............................ 
58. Collection and Study of Basic 
Data .............................. 
Tables 
Table 10-A 
Table 10-B 
Table 10-C 
Table l10-D 
Table 10-E 
Table 10-G 
Table 10-H 
Table 10-1I 
Table 10-J 
Cost & Financial 
Statement .................. 
Authorizing Legislation ....... 
Other Authorized 
Navigation Projects ........... 
Other Authorized Beach 
Erosion Control Projects ...... 
Other Authorized Flood 
Control Projects .............. 
Deauthorized Projects ......... 
Navigation Work Under 
Special Authorization ........ 
Beach Erosion Control 
Projects Under Special 
Authorization ................ 
Flood Control Work Under 
Special Authorization ........ 
10-26 
10-32 
10-42 
10-42 
10-43 
10-43 
10-44 
Table 10-K 
Table 10-L 
Table 10-M 
Table 10-N 
Table 10-0 
10-44 Table 10-P 
10-44 
Reconnaissance and 
Condition Surveys ........... 
Alabama-Coosa Rivers, AL 
and GA Development Proposed 
Under Existing Project ........ 
Apalachicola, Chattahoochee, 
and Flint Rivers, AL, GA and FL, 
Locks and Dams and Multiple- 
Purpose Development Included 
in Existing Project ............ 
Black Warrior and 
Tombigbee Rivers, AL ........ 
Tennessee-Tombigbee 
Waterway, MS and AL ........ 
Completed Flood Insurance 
Studies and Flood Hazard 
Information Reports ......... 
10-2 
Page 
10-20 
10-20 
10-21 
10-21 
10-22 
.10-22 
10-23 
10-23 
10-24 
10-24 
10-24 
10-25 
10-25 
10-45 
10-45 
10-46 
10-47 
10-48 
10-49

MOBILE, ALABAMA DISTRICT 
Navigation 
1. APALACHICOLA BAY, FL. 
Location. The project is on the coast of northwest 
Florida 160 miles east of Pensacola Harbor. (See Coast 
and Geodetic Survey Chart 11401.) 
Previous project. For details, see page 1833, Annual 
Report for 1915, and page 689, Annual Report for 1938. 
Existing project. The authorized project provides for: 
(a) A channel 10 feet deep and 100 feet wide from the 
10-foot depth in Apalachicola Bay, across St. George 
Island, to within 300 feet of the gulf shore, thence 
increasing uniformly in width to 200 feet at the shore 
and continuing with that width to the 10-foot depth in 
the Gulf of Mexico, with twin jetties extending from the 
dune line to the outer end of the channel; (b) an inner 
bar channel, 10 feet deep and 100 feet wide, in Apalachicola 
Bay; (c) a boat basin 200 feet by 880 feet and 
nine feet deep at Apalachicola, Florida, with a connecting 
channel 9 feet deep and 80 feet wide through 
Scipio Creek to Apalachicola River; (d) a channel 
known as Link Channel, 10 feet deep and 150 feet wide, 
in Apalachicola Bay; (e) a channel generally parallel to 
the shore at Eastpoint, Florida, 6 feet deep, 100 feet 
wide, and about 6,000 feet long, and a connecting 
channel 6 feet deep and 100 feet wide to water at the 
same depth in St. George Sound, with twin breakwaters 
on either side parallel to the shore and having a total 
length of 5,300 feet; (f) a channel 10 feet deep and 100 
feet wide through Bulkhead Shoals, connecting 
Apalachicola Bay with St. George Sound; and (g) a 
6-foot by 100-foot channel about one mile long, generally 
parallel to the shore at Two Mile, Florida, with a 
6-foot by 100-foot connecting channel to water of the 
same depth in Apalachicola Bay. Mean range of tide 
throughout this harbor is 1.6 feet. Extreme range, 
except during storms, is about three feet. Plane of 
reference is mean low water. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Requirements have been fully 
complied with. 
Terminal facilities. Facilities consist of pile-andtimber 
wharves which are considered adequate for 
existing commerce. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Contract dredging removed 138,800 
cubic yards of material at a cost of $368,646. Other work 
on channels and canals cost $209,861. Condition surveys 
and other miscellaneous costs amounted to $110,663. 
Condition at end of fiscal year. The existing project, 
authorized by the 1954 River and Harbor Act, was 
completed in 1959, including reimbursement to local 
interests for approved work, as authorized by the 1958 
River and Harbor Act. Improvements at Two Mile 
except for modifications authorized in 1975 were completed 
in September 1964. Construction of the breakwater 
and channel improvements authorized in 1975 at 
Two Mile was completed in September 1977. Construction 
of breakwaters at Eastpoint authorized in 1983 was 
completed in March 1984. Total Federal costs under 
existing project as of September 30, 1986 were 
$1,898,848 for new work and $3,416,612 for maintenance, 
a total of $5,315,460. 
2. AQUATIC PLANT CONTROL (RIVER 
AND HARBOR ACT OF 1965) 
Location. Navigable water, tributary streams, connecting 
channels and other allied waters in Mobile 
District. 
Existing project. The authorized project provides for 
management and control of water hyacinth, alligatorweed, 
Eurasian watermilfoil, hydrilla, and other obnoxious 
aquatic plant growths from navigable water, 
tributary streams, connecting channels, and other allied 
waters of the United States, in the combined interest of 
navigation, flood control, drainage, agriculture, fish 
and wildlife conservation, public health, and related 
purposes, including continued research for development 
of the most effective and economical control 
measures to be administered by the Chief of Engineers, 
under the direction of the Secretary of the Army, in 
cooperation with other Federal and State agencies. 
Research and planning cost prior to construction shall 
be borne fully by the United States. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Local interests shall agree to hold 
and save the United States free from claims that may 
occur from control operations and to participate to the 
extent of 30 percent of such operations. Requirements 
are being met in the state of Alabama. 
Operations and results during fiscal year. Engineering 
and design costs and work on channels and 
canals amounted to $36,475. 
Condition at end of fiscal year. Total Federal costs 
under the existing project as of September 30, 1986 were 
$528,163. Contributed funds for maintenance amount 
to $21,225. 
3. BAYOU CODEN, AL 
Location. The project is located in a small tidal 
stream on the southern coast of Mobile County, Alabama, 
emptying into Mississippi Sound about 7.6 miles 
northwest of Cedar Point, the southern tip of western 
mainland shore of Mobile Bay. (See Coast and Geodetic 
Survey Chart 11376.) 
Previous project. For details see Annual Report for 
1945, page 843. 
Existing project. The project provides for a channel 
eight feet deep by 60 feet wide extending from La Belle 
Avenue bridge south for about 3,000 feet through the 
bayou to Portersville Bay, thence eight feet deep by 100 
10-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
feet wide extending about 2.3 miles westward across 
Portersville Bay to connect with the Bayou La Batre 
channel, and a turning basin eight feet deep by 60 feet 
wide by 100 feet long on the west side of the bayou 
channel about 500 feet south of the La Belle Avenue 
bridge. Mean tidal range is 1.75 feet, and extreme, 
except during storms, is 3.5 feet. Plane of reference is 
mean low water. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Small privately-owned pile-andtimber 
piers used in connection with fishing industry in 
this locality are adequate for existing commerce. A 
marina which will accommodate about 12 small recreational 
craft, and a slip with facilities for loading oyster 
shells are located near the mouth of the bayou, and are 
maintained by the Alabama Department of Conservation. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Contract dredging removed 154,800 
cubic yards of material at a cost of $208,629. Other work 
on channels and canals cost $97,703. Surveys and 
miscellaneous costs amounted to $19,650. 
Condition at end of fiscal year. That portion of the 
project authorized prior to the 1969 modification was 
completed in 1956. Construction authorized in 1969 was 
initiated 31 March 1975 and completed 26 March 1976. 
Total Federal costs under existing project as of September 
30, 1986 were $325,051 for new work and 
$730,391 for maintenance, a total of $1,055,442. Contributed 
funds expended for new work amount to $100,000 
and $50,000 for maintenance. 
4. BAYOU LA BATRE, AL 
Location. Bayou La Batre is a tidal stream about 10 
miles long, emptying into Mississippi Sound on the 
southern coast of Mobile County, Al., about 10 miles 
northwest of Cedar Point, the southern tip of the 
western mainland shore of Mobile Bay. (See Coast and 
Geodetic Survey Chart 11373.) 
Previous project. For details see Annual Report for 
1945, page 844. 
Existing project. The authorized project provides for 
a 12-foot by 100-foot channel from the 12-foot depth in 
Mississippi Sound to a point about 2,800 feet south of 
the highway bridge, thence a channel 12 feet deep by 75 
feet wide to the bridge, an overall distance of about 
33,500 feet, with the channel widened at a point 0.6 mile 
below the bridge to provide a turning basin 12 feet deep 
and about 2.6 acres in area. Mean tidal range is 1.75 feet, 
and extreme, except during storms, is 3.75 feet. Plane of 
reference is mean low water. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Wooden wharves have been provided 
at seafood processing plants and public launching 
ramps are available. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. Contract 
dredging removed 613,000 cubic yards of material at a 
cost of $224,817. Other work on channels and canals 
cost $46,148. Surveys and miscellaneous costs amounted 
to $55,283. 
Condition at end of fiscal year. The existing project 
was modified December 30, 1966 under the discretionary 
authority of the Chief of Engineers to include a 
turning basin. The project was completed in March 
1967. Total Federal costs under existing project as of 
September 30, 1986 were $311,095 for new work and 
$3,015,322 for maintenance, a total of $3,326,417. 
Contributed funds from local interests for new work 
amount to $10,500. 
5. BILOXI HARBOR, MS 
Location. The project is located on Mississippi 
Sound in southeastern Mississippi, 32 miles by water 
west of Pascagoula Harbor, Mississippi, and 14 miles 
east of Gulfport Harbor, Mississippi (See Coast and 
Geodetic Survey Chart 11373.) 
Previous project. For details see page 584, Annual 
Report for 1962. 
Existing project. The authorized project provides for 
a continuous channel 12 feet deep, 150 feet wide and 23 
miles long from the Gulf Intracoastal Waterway through 
Mississippi Sound east of Deer Island, Biloxi Bay, Back 
Bay, Cranes Neck, and a land cut to Gulfport Lake, 
including a 500-foot by 2,600-foot basin in the lake, 
thence a 12-foot deep by 100-foot wide channel for 
about two miles westward from the west end of the lake, 
terminating in a 300-foot by 500-foot basin; a 12-foot by 
100-foot channel from the main channel in Big Lake to 
and up Bayou Bernard to the Air Force oil terminal at 
about mile 2.6; a 12-foot by 150-foot spur channel from 
the main channel in Biloxi Bay for about one mile, 
terminating in a 400-foot by 600-foot turning basin 
opposite Ott Bayou; continuation of maintenance of the 
12- by 150-foot lateral channel westward about 2.2 miles 
to Biloxi's south waterfront; a 10-foot by 150-foot 
channel from Mississippi Sound, passing west of Deer 
Island to a point where it connects to the 12-foot by 
150-foot lateral channel at Biloxi's south waterfront. 
Construction for the modifications lateral channel 
authorized by River and Harbor Act of Nov. 7, 1966 
was commenced in FY 1974 and completed in Feb. 
1975. Further modifications to the project were authorized 
by the Chief of Engineers on 28 March 1979, which 
provided for a channel 10 feet deep, 100 feet wide and 
300 feet long extending northward from the Biloxi 
Lateral Channel, and into a rectangular basin, approximately 
300 by 370 feet. This work was completed 
in April 1980. 
Cost of modification as authorized by the 1966 River 
and Harbor Act was $664,390. That portion of the 
10-4

MOBILE, ALABAMA DISTRICT 
project providing for an entrance channel 6 feet deep, 50 
feet wide, and about 1,800 feet long into Old Fort 
Bayou, as authorized by the 1945 River and Harbor 
mated Act, is inactive. Estimated cost (1954) of this 
portion was $6,000. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A number of wooden piling-andtimber 
piers for small craft and fishing boats, a bulk 
gasoline terminal, several boat ways, and concrete 
products plant are available. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Contract dredging removed 236,900 
cubic yards of material at a cost of $1,634,196. Other 
work on channels and canals cost $97,724. Condition 
surveys and other miscellaneous costs amounted to 
$282,210. 
Condition at end of fiscal year. The existing project, 
prior to the modification authorized in 1966, was commenced 
in 1931 and completed in 1962. The 1966 
modification was completed in FY 1975. The 1979 
modification was completed in FY 1980. Total Federal 
costs under existing project as of 30 September 1986 
were $1,171,054 for new work and $7,592,668 for 
maintenance, a total of $8,763,722. Contributed funds 
for new work amount to $102,600. Contributed funds 
for maintenance amount to $166,535. 
6. BILOXI HARBOR, 
EAST HARRISON COUNTY 
CANAL, MS 
Location. Biloxi Harbor is located on Mississippi 
Sound in southeastern Mississippi, approximately 75 
miles east of New Orleans, Louisiana, and 45 miles west 
of Mobile Bay, Alabama. The City of Biloxi is situated 
on a peninsula bounded by Mississippi Sound on the 
south, Biloxi Bay on the east, and Back Bay of Biloxi on 
the north. 
Existing project. The project provides for the improvement 
and maintenance of the East Harrison County 
Canal to a 12-foot project depth, 130 feet wide, and 
about 2,100 feet long, and a 300- by 300-foot turning 
basin also to a 12-foot project depth. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. New work: 
Project construction was initiated and essentially completed 
during FY 1986 at a cost of $145,490. 
Condition at end of fiscal year. Total cost of construction 
as of September 30, 1986 amounts to $180,715. 
7. BLACK WARRIOR AND 
TOMBIGBEE RIVERS, AL 
Location. Black Warrior River rises in northern Alabama 
above Birmingham and flows generally southwesterly 
to unite with the Tombigbee River at Demopolis, 
Alabama. Thence the Tombigbee flows south, uniting 
with the Alabama River to form the Mobile River 45 
miles above the head of Mobile Bay. Distance by water 
from Mobile to the vicinity of Birmingham is about 415 
miles. 
Previous project. For details see page 732, Annuat 
Report for 1938. 
Existing project. The authorized project provides essentially 
for a channel 9 feet deep and 200 feet wide from the 
mouth of the Tombigbee River, 45 miles above Mobile, 
to the vicinity of Birmingham, via the Tombigbee and 
Black Warrior Rivers, to mile 430.4 on Sipsey Fork, 
mile 429.6 on Mulberry Fork and mile 407.8 on Locust 
Fork, and for maintenance by snagging of Mobile River 
above the mouth of Chickasaw Creek, a total waterway 
distance of about 408 miles. The total lift of 255 feet is 
accomplished by six locks and dams. The original 
construction program, consisting of 17 dams with 18 
lifts, was completed in 1915. Replacement of the 
original structures with new locks and dams, under the 
modernization program is as follows: William Bacon 
Oliver replaced locks 10, 11, and 12; Demopolis replaced 
locks 4, 5, 6, and 7; Armistead I. Selden replaced locks 8 
and 9; Coffeeville (Jackson) replaced locks 1, 2, and 3; 
and Holt replaced locks 13, 14, 15, and 16. Thus, 16 of 
the original locks have been replaced by five new locks. 
Bankhead Lock and Dam (Lock 17) rehabilitation to 
replace the original double lift lock with a single lift lock 
was completed in 1980. The Coffeeville Lock and Dam 
wildlife refuge, authorized in 1960, includes 4,250 acres 
within the reservoir area and along its boundaries. It is 
proposed to replace Oliver Lock with a lock located 
2,300 feet downstream. The replacement lock would 
have dimensions of 110 feet by 600 feet. A fixed crest 
spillway would extend 815 feet across the river. 
Minimum provision will be provided to allow construction 
of a hydropower plant. (See Table 10-B for 
authorizing legislation.) 
Tidal influence extends upstream from Mobile 101.6 
miles to the old lock 1, where tidal effect is apparent 
only at low stages of the river. At Mobile the mean and 
extreme tidal ranges are 1.5 and 3.6 feet, respectively. 
These are at times slightly increased by the effect of 
winds. The greatest fluctuation of river stages is at 
Demopolis, Ala., the maximum being 59.7 feet. Maximum 
fluctuations at other points are 40 feet at lock 
1,100.6 miles from Mobile; 57.8 feet at Tuscaloosa, 
346.1 miles from Mobile; 13 feet at Birmingport, 404.9 
miles from Mobile; and 27 feet at Cordova, 424.3 miles 
from Mobile. Ordinary fluctuations at these points are 
at old lock 1, 20 feet; at Demopolis, 35 feet; at 
Tuscaloosa, 40 feet; at Birmingport, four feet; and at 
Cordova, seven feet. Works of improvement reduced 
the amount of fluctuations at different points by three to 
10 feet. 
Local cooperation. Requirements of local cooperation 
have been fully complied with to date. 
Terminal facilities. Docks, storage facilities, and 
handling equipment have been provided as required at 
most loading and unloading points along the waterway. 
10-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
These include facilities for handling petroleum and 
petroleum products, coal, ores, sand and gravel, pulpwood, 
manufactures, and various other commodities. 
While most terminal facilities are privately owned, many 
are available for use by the general public. Facilities are 
considered adequate for existing commerce. (See Table 
10-N for existing locks and dams.) 
Operations and results during fiscal year. 
New work: Cost of relocations and other miscellaneous 
costs in connection with the modification of 
Franklin Ferry Bridge across the navigation channel in 
Jefferson and Walker Counties was $1,046,731. Engineering 
and design and land acquisition for Oliver Lock 
and Dam cost $1,055,336. Recreation facilities at Bankhead 
cost $468. Recreation attendance during CY 1985 totaled 
6,672,400. 
Maintenance: Contractors' dredges removed 1,107,268 
cubic yards of material from the river system at a cost of 
$243,093. Other work on channels and canals cost 
$1,589,858. Engineering and design of maintenance features 
cost $612,296. Condition surveys and other general 
charges for the overall river project totaled $1,505,577. 
Other maintenance costs for the system include: Coffeeville 
Lock and Dam, $454,872; Demopolis Lock and Dam, 
$453,204; Warrior Lock and Dam, $384,547; Oliver Lock 
and Dam, $521,338; Bankhead Lock and Dam, $497,420; 
Holt Lock and Dam, $682,929; and reservoir operation, 
$2,372,793. 
Condition at end of fiscal year. Work on the project, 
commenced in 1887, was essentially completed in 1915. 
Since then three of the original locks and dams (10, 11 and 
12) were replaced by William Bacon Oliver (Tuscaloosa) 
Lock and Dam which was opened to navigation in August 
1939; four original locks and dams (4, 5, 6 and 7) were 
replaced by Demopolis Lock and Dam which was opened 
to navigation in August 1954; two original locks and dams 
(8 and 9) were replaced by Warrior Lock and Dam which 
was opened to navigation in October 1957; three original 
locks and dams (1, 2 and 3) were replaced by Coffeeville 
Lock and Dam which was opened to navigation in August 
1960; and four original locks and dams (13, 14, 15, and 16) 
were replaced by Holt Lock and Dam which was opened to 
navigation in June 1966. Rehabilitation of the spillway at 
John Hollis Bankhead Lock and Dam commenced in 
1966, and physically completed 6 February 1970. Replacement 
of the double lift lock with a single lift lock at John 
Hollis Bankhead Lock and Dam commenced in April 1970 
and was completed in 1980. The cost to September 30, 1986 
for replacement of the lock was $47,258,651. The power 
plant at John Hollis Bankhead Lock and Dam was built 
and is operated by the Alabama Power Co. Total Federal 
costs under existing project as of September 30, 1986 were 
$109,919,824 for new work and $177,956,606 for maintenance, 
and $47,258,651 for major rehabilitation, a total of 
$335,135,081. 
8. BON SECOUR RIVER, AL 
Location. Rises 2 miles south of Foley, Ala., and flows 
southerly about 8 miles, emptying into Bon Secour Bay, an 
arm of Mobile Bay in southwest Alabama. 
Existing project. A 10- by 80-foot channel from Gulf 
Intracoastal Waterway through Bon Secour Bay to mouth 
of Bon Secour River and extending up river to vicinity of 
Swifts Landing, thence 6 by 80 feet up river to a point 
about 600 feet above Oak Landing with two turning and 
maneuvering areas 150 feet wide and 1,100 to 1,200 feet 
long opposite Swifts Landing and ice loading dock. Plane 
of reference is mean low water. Overall length of improvement 
is about 4.7 miles. Mean tidal range is about 1.5 feet 
and extreme, except during storms, is 3.5 feet. Existing 
project was authorized by Chief of Engineers, May 16, 
1963, under authority in Section 107, River and Harbor 
Act of 1960. 
Local cooperation. Fully complied with. 
Terminal facilities. A number of pile-and-timber marginal 
wharves used by the seafood industry and a marine 
ways are located along the existing project. These, together 
with numerous privately owned piers, are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition surveys and supervision and administration 
cost $26,531. 
Condition at end of fiscal year. Project was commenced 
in July and completed in October 1964. Total Federal costs 
under existing project as of September 30, 1986 were 
$118,615 for new work and $197,569 for maintenance, a 
total of $316,184. Contributed funds for new work amounted 
to $9,700. 
9. DAUPHIN ISLAND BAY, AL 
Location. The project is located between Dauphin and 
Little Dauphin Island on the west side of the entrance to 
Mobile Bay, about 30 miles south of Mobile, Alabama and 
55 miles west of Pensacola, Florida. (See Coast and 
Geodetic Survey Chart 11376.) 
Existing project. The authorized project provides for: 
(a) A channel seven feet deep and 150 feet wide from 
Mobile Bay to an anchorage basin of the same depth, and 
about seven acres in area, in the marsh just north of Fort 
Gaines on Dauphin Island; a channel four feet deep and 40 
feet wide from the anchorage basin to Dauphin Island Bay; 
and a jetty and revetment to protect the entrance channel; 
and (b) an anchorage basin seven feet deep and 500 feet 
square at Dauphin Island Village, with an entrance 
channel of like depth, 100 feet wide and about 8,300 feet 
long, extending to the 7-foot hydrographic contour in 
Mississippi Sound. Mean tidal range is 1.1 feet, and 
extreme, except during storms is about four feet. Plane of 
reference is mean low water. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Requirements of local cooperation 
have been fully complied with to date. 
Terminal facilities. Several privately-owned wharves for 
handling seafood, a public dock and mooring slip, and a 
pier for recreational craft are located on the village basin. 
A marina, public launching ramp, and a number of private 
piers are located on the bay. Facilities are considered 
adequate for existing commerce. 
10-6

MOBILE, ALABAMA DISTRICT 
Operations and results during fiscal year. New Work: 
None. 
Maintenance: Contract dredging removed 18,640 
cubic yards of material at a cost of $76,554. Other work 
on channels and canals cost $46,149. Condition surveys 
and miscellaneous costs amounted to $42,606. 
Condition at end of fiscal year. The project was completed 
in July 1959. Total Federal costs under existing 
project as of September 30, 1986 were $292,864 for new 
work and $1,313,941 for maintenance, a total of 
$1 ,606,805. 
10. DOG AND FOWL RIVERS, AL 
Location. Dog and Fowl Rivers are primarily tidal 
streams emptying into the west side of Mobile Bay, 8.5 and 
17 miles, respectively, south of central Mobile. (See Coast 
and Geodetic Survey Chart I11376). 
Existing project. The Dog River project provides for a 7 
by 100-foot channel from the Highway 163 bridge eastward 
approximately 10,000 feet then southeasterly to the 
Mobile Ship Channel following natural depths. 
The Fowl River project provides for a channel eight feet 
deep and 100 feet wide from Mobile Bay into and up Fowl 
River to deep water about 6.700 feet above its mouth. 
Total length of the channel is about 2.6 miles. Plane of 
reference is mean low water. Mean range of tide is about 
1.5 feet in Dog River. Extreme range during storms is 
about 3.6 feet. This segment of the project was completed 
in November, 1973. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Existing facilities consist of a 
boatyard for fabricating steel vessel hulls, nine marinas, 
four marine ways, a yacht basin on Dog River; two 
marinas on Fowl River, and numerous timber piers and 
docks on both rivers. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. New work: 
Dredging of the Dog River Channel to specifications was 
completed in September 1986. The city of Mobile constructed 
the disposal dikes and contributed $81,150 for the 
recreation use of the project. Federal costs during FY 1986 
amounted to $124,622. 
Maintenance: Contract dredging removed 280,500 cubic 
yards of material from Fowl River at a cost of $431,553. 
Other work on channels and canals cost $318,464. Water 
control management, condition surveys and other miscellaneous 
costs amounted to $175,416. 
Condition at end of fiscal year. The existing Fowl River 
portion of the project was commenced in August 1973 and 
completed in November 1973. Work on the Dog River 
channel was initiated during this fiscal year and essentially 
completed in September 1986. Total Federal costs on the 
existing project as of September 30, 1986 were $2,120,055; 
$315.317 for new work and $1,804,738 for maintenance. 
Contributed funds for new work amounted to $169,993. 
11. EAST PASS CHANNEL FROM 
GULF OF MEXICO INTO 
CHOCTAWHATCHEE BAY, FL 
Location. East Pass Channel is located in the entrance 
from the Gulf into Choctawhatchee Bay at eastern end 
of Santa Rosa Island, 48 miles east of the entrance into 
Pensacola Bay and 49 miles west of the new entrance to 
St. Andrews Bay. (See Coast and Geodetic Survey 
Chart 11388.) 
Previous project. For details see page 672 of Annual 
Report for 1937. 
Existing project. The authorized project provides for 
a 12-foot by 180-foot channel from the Gulf of Mexico 
into Choctawhatchee Bay, and a 6-foot by 100-foot 
channel from East Pass Channel into Old Pass Lagoon. 
The project consists also of two converging jetties 
spaced 1,000 feet apart at the seaward end. The west 
jetty is provided with a low weir section 1,000 feet long 
to permit passage of littoral drift into a dredged 
deposition basin 500 feet by 1,500 feet located between 
the west jetty and the navigation channel. Mean range 
of tide is 1.3 feet; extreme range, except during storms, 
is 2.5 feet. Plane of reference is mean low water. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Responsibilities of local cooperation 
have been complied with to date. 
Terminal facilities. Small privately-owned pile-andtimber 
piers used in connection with the fishing industry 
in this locality are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Contractor's dredges operating in the entrance 
channel to Old Pass Lagoon and East Pass removed 
300,800 cubic yards of material at a cost of $300,814. 
Other work on channels and canals cost $329,252. 
Condition surveys cost $72,971. Other miscellaneous 
costs totaled $65,093. 
Condition at end of fiscal year. Construction of the 
1965 modification was commenced October 1967 and 
completed January 1969. Total Federal costs under 
existing project as of September 30, 1986 were $916,715 
for new work and $6,968,955 for maintenance, a total of 
$7,885,670. Contributed funds for new work from local 
interests amount to $398,000. 
12. FLY CREEK, AL 
Location. Fly Creek (Volanta Bayou) is a small 
stream about 4.5 miles long rising in Baldwin County, 
Ala., 3 miles east of town of Fairhope, from whence it 
flows northerly, thence westerly and southerly, to form 
an estuary on eastern shore of Mobile Bay just north of 
Fairhope and about 13 miles southeast of Mobile, Ala. 
(See U.S. Coast and Geodetic Survey Chart No. 11376.) 
Existing project. Provides for a channel 6 feet deep, 
80 feet wide, and about 1,650 feet long from 6-foot 
depth in Mobile Bay to a turning basin of same depth, 
10-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
100 feet wide and 350 feet long, in Fly Creek. Mean tidal 
range in vicinity of project is about 1.3 feet, and 
extreme, except during storms, is 3.5 feet. 
Existing project was authorized by the River and 
Harbor Act of May 17, 1950, (H. Doc 194, 81st Cong., 
1st Sess.). The project document contains the latest 
published map. 
Local cooperation. Fully complied with. 
Terminal facilities. Fairhope Yacht Club has facilities 
for small recreational craft on both banks near mouth of 
creek, consisting of a small pile-and timber service 
wharf, several sheet metal boat sheds, boat slips, and 
other mooring facilities. There is also a marginal timber 
wharf and shed for commercial fishing boats on right 
bank of creek immediately above first bend. 
Operations and results during fiscal year. Maintenance: 
Project condition surveys, supervision and administration, 
and other miscellaneous costs amounted 
to $15,356. 
Condition at end of fiscal year. Project was commenced 
in August and completed in October, 1957. 
Total project costs as of September 30, 1986 amounted 
to $352,362 of which $29,000 was for new work and 
$323,362 for maintenance. 
13. GULF INTRACOASTAL 
WATERWAY BETWEEN 
APALACHEE BAY, FL 
AND MEXICAN BORDER 
(MOBILE DISTRICT) 
Location. The project extends westward from Apalachee 
Bay, Florida, along the Gulf coast to the Rigolets, 
Louisiana, via a series of coastal lakes, bays, sounds, 
and land cuts. (For further details see Annual Report 
for 1962.) 
Previous project. For details see page 906, Annual 
Report for 1930. 
Existing project. The authorized project provides for 
a waterway 12 feet deep and 125 feet wide at mean low 
water from Apalachee Bay, Florida, to Mobile Bay, 
Alabama, and 12 feet deep and 150 feet wide from 
Mobile Bay, Alabama to Rigolets, Louisiana (Lake 
Borgne Light No. 29), and for a tributary channel (Gulf 
County Canal), 12 feet deep, 125 feet wide and about six 
miles long connecting Intracoastal Waterway at White 
City, Florida, with St. Joseph Bay. The waterway 
between the 12-foot depth contours in Apalachee Bay 
and Lake Borgne Light No. 29 at the Rigolets is 379 
miles long. (See Table 10-B for authorizing legislation.) 
Local cooperation. Responsibilities of local cooperation 
have been fully complied with for the work 
authorized prior to 1966. For modification of the Gulf 
County Canal which was authorized by the 1966 River 
and Harbor Act, local interests must provide without 
cost to the United States all lands, easements, and 
rights-of-way required in connection with disposal of 
spoil, or the costs of such retaining works; hold and save 
the United States free from all damages due to construction 
and maintenance of the project including 
damages to wharves, piers, bridges, and other structures; 
provide and maintain at local expense adequate 
terminal and transfer facilities open to all on equal 
terms; provide and maintain without cost to the United 
States depths in berthing areas commensurate with 
depths provided in related project area; and accomplish 
without cost to the United States such alterations as 
required in sewer, water supply, drainage, and other 
facilities as well as their maintenance. 
Terminal facilities. Facilities are available for public 
use at Carrabelle, Apalachicola, Panama City, and 
Pensacola, Florida; Mobile and Bayou LaBatre, Alabama; 
and Pascagoula, Biloxi, Gulfport, Pass 
Christian, and Bay St. Louis, Mississippi. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: 
Carrabelle-Apalachicola Bay section: Maintenance 
dredging removed 447,700 cubic yards of material at a 
cost of $277,572. Other work on channels and canals 
cost $240,687. Condition surveys cost $209,452. Supervision 
and administration and miscellaneous costs 
totaled $93,617. 
Apalachicola Bay - St. Andrew Bay section: Maintenance 
dredging removed 621,600 cubic yards of material 
at a cost of $770,732. Other work on channels and 
canals cost $492,455. Condition surveys, $42,050; supervision 
and administration, $205,482; and miscellaneous, 
$48,167. 
St. Andrew Bay - Choctawhatchee Bay section: Hired 
labor costs for bank stabilization and diking of disposal 
areas were $268,479. Condition surveys cost $93,494. 
Engineering and design, supervision and administration 
and miscellaneous costs totaled $76,573. 
Choctawhatchee Bay - Pensacola Bay section: Costs 
for the year include engineering and design, condition 
surveys and miscellaneous work, $20,370. 
Pensacola Bay - Mobile Bay section: Costs for the 
year included condition surveys, engineering and design, 
supervision and administration and miscellaneous, 
$176,592. 
Mobile Bay - Rigolets section: Condition surveys, 
water control management and supervision and ad ministration 
cost $120,947. In addition, compliance inspections 
cost $222,712; direct charges to Mobile Area 
Office cost $150,559; and direct charges to 
Panama City Area Office were $6,052. 
Condition at end of fiscal year. The existing project is 
complete except for the portion between Apalachicola 
Bay and St. Marks, Florida, which is deferred for restudy. 
Modification of the Gulf County Canal to 
provide a 12-foot by 125-foot channel was commenced 
July 1968 and completed June 1969. Total costs of the 
10-8

MOBILE, ALABAMA DISTRICT 
existing project to September 30, 1986 were $51,589,385, 
of which $6,434,694 was for new work and $45,154,691 
for maintenance. 
14. MOBILE HARBOR, AL 
Location. The project is located along the lower five 
miles of Mobile River, in southwestern Alabama, 91 
miles by water west of Pensacola Harbor, Florida, 90 
miles east of Gulfport Harbor, Mississippi, and 144 
miles by water northeast of mouth of Mississippi River. 
(See Coast and Geodetic Survey Chart 11376.) 
Previous project. For details see page 503, Annual 
Report for 1963. 
Existing project. The authorized project provides for: 
(a) A 42-foot by 600-foot channel about 1.5 miles long 
across Mobile Bar; (b) a 40-foot by 400-foot channel in 
Mobile Bay to mouth of Mobile River: (c) a 40-foot 
channel in Mobile River to highway bridge, varying 
from 500 to 775 feet wide; (d) a 25-foot channel from 
highway bridge to and up Chickasaw Creek to a point 
400 feet south of mouth of Shell Bayou, widths being 
500 feet in Mobile River and 250 feet in Chickasaw 
Creek: (e) a turning basin 40 feet deep, 2,500 feet long, 
and 800 to 1,000 feet wide, opposite Alabama State 
Docks; (f) a turning basin 40 feet deep, 1000 feet wide, 
and 1,600 feet long opposite Magazine Point; (g) a 
27-foot by 150-foot channel from Mobile Bay Channel 
along Arlington pier to a turning basin 800 feet long and 
600 feet wide opposite Brookley Complex ocean terminal, 
and continuing thence to a turning basin 250 feet 
wide and 800 feet long in Garrows Bend, thence a 22- 
foot by 150-foot channel to the causeway linking 
McDuffie Island to the mainland; (h) a channel 40 feet 
deep and 400 feet wide from the main ship channel in 
Mobile Bay and extending northwesterly for about 5.3 
miles to the shore of Mobile Bay, including an anchorage 
basin near the shoreline, thence a land cut 40 feet 
deep. 300 feet wide and 1.9 miles long to and including a 
42 acre trapezoid turning basin 40 feet deep, and a barge 
channel 12-by 100-feet, extending 6500 feet and terminating 
in a 300-by 300-foot turning basin: and (i) 
maintenance of Three Mile Creek by snagging, from its 
intersection with Industrial Canal to Mobile River. The 
project provides also for an anchorage area 32 feet deep, 
100 feet wide, and 2.000 feet long opposite site formerly 
occupied by the U. S. Quarantine Station at McDuffie 
(Sand) Island. Prior to widening the Mobile Bay 
Channel as authorized in 1954, the Quarantine Station 
anchorage area was maintained to a project width of 200 
feet. Construction by local interests of a solid-fill 
causeway across Garrows Bend Channel between 
McDuffie Island and the mainland is also provided for 
under existing project. Total length of the bay and river 
channels is about 41.7 miles. Plane o1 reference is mean 
low water. Under ordinary conditions mean tidal range 
at the lower end of the improvement is 1.2 feet and at the 
upper end 1.5 feet. Extreme tidal range is 3.4 feet at the 
lower end and 3.6 feet at the upper end. Further 
authorization provides for future development to deepen 
and widen entrance channel over the bar to 57 feet by 
700 feet about 7.4 miles long, deepen and widen bay 
channel to 55 feet by 550 feet about 27.0 miles long, 
deepen and widen an additional 4.2 miles of bay channel 
to 55 feet by 650 feet and provide 55 foot deep 
anchorage area and turning basin in vicinity of Little 
Sand Island. All dredged material will be placed in an 
approved disposal area in the Gulf of Mexico. (See 
Table 10-B for authorizing legislation.) A General 
Design Memorandum has been approved at the Division 
level modifying the project dimensions which would 
provide an entrance channel of 57 feet by 600 feet about 
7.8 miles long and a bay channel of 55 feet by 400 feet 
about 29 miles long. 
Local cooperation. A local cooperation agreement 
has been signed by the local sponsor to construct the 
project in increments. The first increment will either be, 
1) a 45-foot by 400-foot channel from the McDuffie 
Coal Terminal south to the mouth of the bay and then a 
47-foot by 600-foot channel across Mobile Bar or, 2) a 
57-foot by 600-foot channel across Mobile Bar and 
north to a transshipment facility located just inside the 
mouth of the bay. 
Terminal facilities. Modern rail-connected terminal 
facilities at this port are considered adequate for 
existing commerce. (See Port Series No. 18, revised in 
1979.) 
Operations and results during fiscal year. New work: 
Engineering and design for Mobile Harbor and monitoring 
Theodore Channel cost $89,275. 
Maintenance: Contract dredging removed 6,361,501 
cubic yards of material from Mobile River Channel, 
Garrows Bend, and from Mobile Bay, all at a cost of 
$7,120,050. Other work on channels and canals.,cost 
$140,949. Condition surveys cost $941,742. Water 
control management, engineering and design and supervision 
and administration cost $593,931. 
Condition at end of fiscal year. The existing project 
was commenced in 1931 and completed in July 1965 
except for the Theodore Channel portion, which was 
essentially completed in August 1981. For details see 
Annual Report for 1965. Total Federal costs under 
existing project as of September 30, 1986 were 
$61,507,655 for new work and $78,372,052 for maintenance, 
a total of $139,879,707. Contributed funds 
expended amounted to $6,133,008 for new work and 
$846,706 for maintenance. 
15. PANAMA CITY HARBOR, FL 
Location. The project is located on the northwest 
coast of Florida, 102 miles east of entrance to Pensacola 
Harbor. (See Coast and Geodetic Survey Chart I1389.) 
Previous project. For details see page 710, Annual 
Report for 1938. 
Existing project. The authorized project (as modified) 
provides for a channel about 3.7 miles long 
extending from deep water in St. Andrew Bay to the 
Gulf of Mexico, 300 feet wide and 40 feet deep in the bay 
10-9

REPORT TO THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
and 450 feet wide, 42 feet deep and about 1.1 miles long 
in the approach channel in the Gulf, protected by two 
jetties, each about 700 feet long; branch channels 38 feet 
deep and 300 feet wide, leading from the inner end of the 
main entrance channel westward to the Port Authority 
terminal at Dyers Point and eastward to the Bay Harbor 
terminal, about 3.4 and 3.6 miles in length, respectively; 
turning and maneuvering areas comprising about 55 
acres opposite Dyers Point, and 42 acres opposite Bay 
Harbor, both at a depth of 38 feet; and an anchoring and 
loading basin for LASH type intermodal carriers, 40 
feet deep and containing about 177 acres in St. Andrew 
Bay near the inner end of the main entrance channel; a 
channel in Watson Bayou, 100 feet wide and 10 feet deep 
from that depth in St. Andrew Bay to the highway 
bridge, about 1.75 miles; channel 100 feet wide and 8 
feet deep in Grand Lagoon to a point about 2,400 feet 
east of State Highway 392 Bridge, with branches to 
serve terminal facilities. The east and west jetties have 
been reworked and are presently about 2,075 and 2,896 
feet long, respectively. Mean tidal range is about 
normally 1.3 feet and 3.0 feet extreme. (See Table 10-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Available terminal facilities are 
considered adequate for existing commerce. (See Port 
Series No. 19.) 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Contract dredging removed 270,800 
cubic yards of material at a cost of $379,067. Other work 
on channels and canals cost $101,680. Condition 
surveys and other miscellaneous costs amounted to 
$140,140. 
Condition at end of fiscal year. The existing project 
(prior to modifications) was completed in November 
1949. Repairs to jetties were commenced in June 1961 
and completed October 1968. Modifications to the 
project at Grand Lagoon were completed in January 
1972. Total Federal costs under existing project as of 
September 30, 1986 were $1,434,485 for new work and 
$6,573,278 for maintenance, a total of $8,007,763. 
Contributed funds expended for new work amount to 
$80,000. 
16. PASCAGOULA HARBOR, MS 
Location. The project is located along lower 6.8 miles 
of Pascagoula River, the lower six miles of Dog River, 
and in Bayou Casotte (about four miles east of the 
mouth of Pascagoula River), in southeastern Mississippi, 
about 38 miles west of Mobile, Alabama, and 
about 100 miles east of New Orleans, Louisiana. (See 
Coast and Geodetic Survey Chart 11373.) 
Previous project. For details see page 741, Annual 
Report for 1938. 
Existing project. The authorized project provides for 
(a) An entrance channel 40 feet deep and 350 feet wide 
from the Gulf of Mexico through Horn Island Pass, 
including an impounding area for littoral drift, 40 feet 
deep, 200 feet wide, and about 1,500 feet long adjacent 
to the channel at the west end of Petit Bois Island; (b) a 
channel 38 feet deep and 350 feet wide in Mississippi 
Sound and Pascagoula River to the railroad bridge at 
Pascagoula, including a turning basin 2,000 feet long 
and 950 feet wide (including channel area) on the west 
side of the river below the railroad bridge; (c) a channel 
38 feet deep and 225 feet wide from the ship channel in 
Mississippi Sound to the mouth of Bayou Casotte, 
thence 38 feet deep and 300 feet wide for about one mile 
to a turning basin 38 feet deep, 1,000 feet wide, and 
1,750 feet long; (d) a 22-foot deep by 150-foot wide 
channel up Pascagoula River from the railroad bridge 
to the mouth of Escatawpa (or Dog) River, then up 
Escatawpa River to Highway 613 (formerly 63) bridge; 
(e) a 12-foot by 125-foot channel from the highway 
bridge, via Robertson and Bounds Lakes, to mile 6 on 
Escatawpa River; and (f) a 12-foot by 80-foot channel 
extending from deep water in the Pascagoula River 
(about one-half mile north of the railroad bridge) to a 
turning basin in Krebs Lake a distance of about 1,500 
feet, then along the south bank of the lake a channel 
10-foot by 60-foot and terminating at a second turning 
basin, a distance of 2,700 feet from the first. Under 
ordinary conditions mean tidal range is 1.75 feet, and 
extreme range is 3.75 feet. Plane of reference is mean 
low water. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Modern rail-connected terminal 
facilities at this port are considered adequate for 
existing commerce. (See Port Series No. 19.) 
Operations and results during fiscal year. Maintenance: 
Contract dredging removed 4,237,000 cubic 
yards of material from the Channel, River and Sound at 
a total Federal cost of $2,773,234. Condition surveys 
cost $250,000. Supervision and administration and 
miscellaneous costs totaled $139,504. 
Condition at end of fiscal year. The existing project 
was completed in August 1965 and the Krebs Lake 
project was completed in November 1983. Total Federal 
costs of existing project to September 30, 1986 were 
$5,668,543 for new work and $35,920,750 for maintenance, 
a total of $41,589,293. Contributed funds expended 
for maintenance amounted to $1,756,426. 
17. PENSACOLA HARBOR, FL 
Location. The project is located in a landlocked bay 
on the coast of northwest Florida about 50 miles east of 
the entrance to Mobile bay. (See Coast and Geodetic 
Survey Charts 490 and 11382.) 
Previous project. For details see Annual Report for 
1938. 
Existing project. The authorized project provides for: 
(a) A 35-foot by 500-foot entrance channel about five 
miles long, from the Gulf of Mexico to lower Pensacola 
Bay; (b) a 33-foot by 300-foot bay channel; (c) two 
33-foot by 300-foot parallel approach channels to 
10-10

MOBILE, ALABAMA DISTRICT 
opposite ends of the inner-harbor channel: (d) an innerharbor 
channel 500 feet wide, 33 feet deep, and 3,950 
feet long: (e) a 30-foot by 250-foot approach channel to 
the pierhead line south of Muscogee wharf: and (f) a 
15-foot by 100-foot entrance channel into Bayou Chico, 
thence a channel 14 feet deep, 75 feet wide, and about 
4.400 feet long to a turning basin 14 feet deep and 500 
feet square. Mean range of tide throughout the harbor is 
about 1.1 feet near the entrance and about 1.6 feet at the 
head of bay. Extreme tidal range, except during storms, 
is about three feet. Plane of reference is mean low water. 
Modification of the Bayou Chico project to provide for 
enlarging the entrance channel to 21 by 100 feet, the 
bayou channel to 20 feet by 100 feet, and deepening the 
turning basin to 20 feet has been deferred for restudy. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Modern rail-connected terminal 
facilities at this port are considered adequate for existing 
commerce. (See Port Series No. 19, revised in 1979.) 
Operations and results during fiscal year. Maintenance: 
Condition surveys, water control management 
and miscellaneous costs amounted to $20,328. 
Condition at end of fiscal year. New work is completed 
except those features which are deferred for restudy. 
The modification authorized in 1962 was commenced 
in March and completed in May 1965. Total 
Federal costs of the existing project to September 30, 
1986 were $875,005 for new work and $6,049,622 for 
maintenance, a total of $6,924,627. 
18. PERDIDO PASS CHANNEL, AL 
Location. The project is located about midway 
between Pensacola, Florida and Mobile, Alabama. (See 
Coast and Geodetic Chart 11378.) 
Existing project. The existing project provides for a 
channel 12 feet deep and 150 feet wide for about 1,300 
feet from the Gulf of Mexico into the inlet, thence nine 
feet deep and 100 feet wide for about 2,200 feet to the 
highway bridge, where the channel branches into two 
arms, each having dimensions of 9 by 100 feet, one of 
which extends about 3,400 feet into Terry Cove and the 
other about 3,200 feet into the southern arm of Perdido 
Bay. The project also provides for two jetties spaced 600 
feet apart at the seaward end. The east jetty has a low 
weir section, 1,000 feet long to permit passage of littoral 
drift into a dredged deposition basin 800 feet by 1,200 
feet located between the east jetty and the navigation 
channel. Mean tidal range is 1. I feet and extreme is 2.8 
feet. (See Table 10-B for authorizing legislation.) 
Local cooperation. Requirements of local cooperation 
have been fully complied with to date. 
Terminal facilities. Six marinas, numerous timber 
piers, docks, and several launching ramps are available. 
These facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Contract dredging removed 266.600 cubic yards 
of material at a cost of $575,954. Other work on 
channels and canals cost $296,006. Condition surveys 
and miscellaneous costs amounted to $72,735. 
Condition at end of fiscal year. The existing project 
was commenced in May 1968 and completed in March 
1969. Total Federal costs of the existing project to 
September 30, 1986 were $629,860 for new work and 
$5,947,424 for maintenance, a total of $6,577,284. Contributions 
from local interest amount to $510,000 for 
new work and $10,325 for maintenance. 
19. WATERWAY CONNECTING 
TOMBIGBEE AND TENNESSEE 
RIVERS, AL AND MS 
Location. The waterway extends from mile 215 in 
Pickwick pool on the Tennessee River, southerly through 
northeastern Mississippi and western Alabama, a total 
of 234 miles, to the confluence of the Black Warrior and 
Tombigbee Rivers at Demopolis, Alabama. 
Location. For details see Annual Report for 1953. 
Existing project. The authorized project provides for 
a waterway 234 miles long, connecting the Tennessee 
and Tombigbee Rivers via the East Fork of Tombigbee 
River and Mackeys and Yellow Creeks. The plan of 
improvement consists of three sections. (1) the river 
section, a 9-foot by 300-foot channel for 149 miles 
between Demopolis and Amory, Mississippi; (2) the 
lateral canal section, 12 feet by 300 feet for 46 miles from 
Amory to Bay Springs; and (3) the divide section, a 
12-foot by 300-foot channel (except in the 27 mile-long 
divide cut in which the bottom width would be 280 feet) 
for 39 miles from Bay Springs through the dividing 
ridge to the Tennessee River; the total lift Of 341 feet to 
be accomplished by 10 locks. Estimated (1986) Federal 
cost for new work is $1,798,000,000, including $8,600,000 
for work by the U.S. Coast Guard, and $9,400,000 for 
National Park Service; plus, $153,000,000 non-Federal 
cost for relocations. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Local interests must make and 
maintain alterations in highways and highway bridges 
and in sewer, water-supply, and drainage facilities and 
provide and maintain suitable and adequate river and 
canal terminals. Officials of the State of Mississippi 
were notified of these requirements on December 13, 
1949, and officials of the State of Alabama were notified 
on December 20, 1949. Legislation enabling boards of 
supervisors of the various counties concerned to enter 
into agreements with the United States relative to 
navigation projects was adopted by the State of Mississippi 
in 1950. A compact between the States of Alabama, 
Mississippi, Tennessee, Kentucky and Florida has been 
formed for the purpose of promoting the project. The 
name of this organization is the Tennessee-Tombigbee 
Waterway Development Authority. 
During its 1962 session the Mississippi Legislature 
authorized the formation of the Tombigbee River 
Valley Water Management District. The District was 
10-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
organized in accordance with the enabling legislation 
and is empowered to fulfill the requirements of local 
coooperation for the portion of the project in Mississippi. 
A satisfactory resolution has been furnished. During its 
1967 session the Alabama Legislature authorized 
formation of a public corporation to be named the 
Tombigbee Valley Development Authority for the 
purpose of further development of the Tombigbee River 
and tributary streams. The organization was formed in 
accordance with the enabling legislation and in a 
referendum held 5 December 1967 the voters of Alabama 
authorized a bond issue not to exceed $10,000,000 to 
finance participation in this project and the Tombigbee 
River and Tributaries project. A satisfactory resolution 
has been furnished. 
Terminal facilities. Docks, storage facilities and handling 
equipment are still being developed along this new 
waterway. As of September 30, 1986, only eleven such 
facilities were operational, while four were under 
construction, and six more are planned. The operational 
facilities are handling grain, wood chips, and logs. 
When all facilities are complete, about half will be 
publicly owned and operated. Additional ports and 
terminals must be completed before the waterway can 
achieve its full potential. (See Table 10-N for existing 
locks and dams.) 
Operations and results during fiscal year. New work: 
Total cost of new work during the fiscal year was 
$24,174,109 of which $8,560 was for work on Demopolis 
Lake; $70,306 for Gainesville Lock and Dam; 
$5,030,584 for Aliceville Lock and Dam; $4,829,981 for 
Columbus Lock and Dam; $1,658,287 for Aberdeen 
Lock and Dam. Canal section cost included: Lock A, 
$2,243,524; Lock B, $556,740; Lock C, $3,567,615; 
Lock D, $1,300,734; Lock E, $349,211. Other costs 
associated with the overall project amounted to 
$4,558,567. Contributed funds amounted to $4,415. 
Maintenance: Contract dredging removed 303,600 
cubic yards of material from the river system at a cost of 
$1,576,744. Cost for operation of the completed portion 
of the project during the year amounted to $13,171,967, 
which included general charges of $6,583,057; Gainesville 
Lock and Dam, $301,147; Aliceville Lock and 
Dam, $334,753; Columbus Lock and Dam, $341,174; 
Aberdeen Lock and Dam, $493,843; Lock A, $317,192; 
Lock B, $353,881; Lock C, $301,047; Lock D, $385,485; 
Lock E, $310,705; Bay Springs, $378,082; lake charges 
of $3,071,601. Recreation attendance for CY 1985 
totaled 3,273,857 user days. 
Condition at end of fiscal year. Total Federal costs 
under the existing project as of September 30, 1986 were 
$973,129,909 for new work, and $47,064,302 for maintenance 
for a total of $1,020,194,211. Construction formally 
began December 12, 1972 and overall project is 
about 95 percent complete. The waterway was opened 
for navigation in January 1985. 
20. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 10-C.) 
21. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645, as amended (Preauthorization). Studies 
conducted under this authority amounted to $318,164. 
(See Table 10-H.) 
22. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 10-K.) 
23. DEAUTHORIZED PROJECTS 
Projects deauthorized under Section 12, Public Law 
251, 93rd Congress, as amended. (See Table 10-G.) 
Beach Erosion Control 
24. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECT 
(See Table 10-D.) 
25. BEACH EROSION CONTROL 
PROJECTS UNDER 
SPECIAL AUTHORIZATION 
Studies conducted under Section 103,1962 River and 
Harbor Act, as amended, amounted to $1,140. (See 
Table 10-I.) 
Flood Control 
26. OKATIBBEE LAKE, MS 
Location. The project is located on Okatibbee Creek 
37.7 miles above its mouth, in Lauderdale County, 
Mississippi, seven miles northwest of Meridian. 
Existing project. The project provides for a dam and 
reservoir for flood control, water supply, water quality 
control, fish and wildlife, and recreation. The dam 
consists of a compacted earth fill 6,540 feet long with the 
top elevation 369.8 feet above national geodetic datum, 
with top width of 18 feet. The spillway, which is located 
1,500 feet east of the east end of the dam, is an unpaved 
free overflow type, 1,500 feet long with a fixed crest at 
elevation 359. A sluice intake structure near the center 
of the dam serves a 9.0-foot diameter concrete conduit. 
Storage allocated for water supply and water quality 
control varies seasonally from 21,400 acre-feet to 34,300 
acre-feet between a minimum elevation of 328 and topof-
conservation-pool elevation varying from 339 to 343. 
Storage varying from 46,500 to 59,500 acre-feet between 
the top of the conservation pool and elevation 352 has 
been reserved exclusively for storage of flood waters. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Complied with to date. 
Operations and results during fiscal year. New Work: 
Engineering and design of public use facilities cost 
10-12

MOBILE, ALABAMA DISTRICT 
$119,906. Maintenance: Costs for the year for ordinary 
maintenance and recreational management amount to 
$877,052. No flood control benefits were attributed to 
the project during FY 1986. Recreation attendance at 
the reservoir during CY 1985 totaled 1,082,237 recreational 
user days. 
Condition at end of fiscal year. Construction began in 
June 1965, and was completed in November 1968. Total 
Federal costs of the existing project as of September 30, 
1986 were $9,739,172 for new work and $8,272,618 for 
maintenance, a total of $18,01 1,790. 
27. TALLAHALA CREEK LAKE, 
PASCAGOULA RIVER, MS 
Location. The project is on Tallahala Creek, 81.1 
miles above its mouth, in Jasper County, Mississippi, 13 
miles north of Laurel. 
Existing project. The project provides for a dam and 
reservoir for flood control, water supply, water quality 
control, recreation, and fish and wildlife enhancement. 
The dam will consist of a compacted earth fill 8,000 feet 
long, with top elevation 343.5 feet above national 
geodetic datum, or a maximum 71.5 feet above streambed 
elevation, with a top width of 18 feet, and a 300-foot 
long saddle dike with maximum height of 15 feet in the 
left abutment. The spillway which is 6,000 feet northeast 
of the left abutment, will consist of an unpaved, freeoverflow 
type, 500 feet long, with fixed crest at elevation 
335.0. A sluice intake structure near the center of the 
dam will serve an 8-foot diameter, horseshoe-shaped 
concrete conduit. The reservoir at maximum pool 
elevation 306.5 will have an area of 4,000 acres and a 
total capacity of 63,000 acre-feet of which 35,900 acrefeet 
between elevations 288.5 and 302.0 will be used for 
water supply, 20,000 acre-feet between elevations 302.0 
and 306.5 will be used for water quality improvement, 
and 7,100 acre-feet below elevation 288.5 will consist of 
dead storage. A volume varying seasonally from 50,000 
to 70,000 acre-feet between elevations 306.5 and 315.0 
will be reserved for flood storage. Estimated Federal 
cost (1986) is $120,000,000. (See Table-B for authorizing 
legislation.) 
Local cooperation. Local interests will be required to 
reimburse the United States for all costs allocated to 
water supply in accordance with the Water Supply Act 
of 1958, as amended; and one-half of the separable first 
cost of the project allocated to general recreation and 
fish and wildlife enhancement. In addition, local interests 
are required to reimburse the United States for the 
annual operation, maintenance and replacement cost 
allocated to water supply, and bear all cost of operation, 
maintenance and replacement of recreation and fish and 
wildlife areas and facilities for initial development. 
Operations and results during fiscal year. New work: 
Land and damages and engineering and design cost 
$3,931. 
Condition at end of fiscal year. Construction has not 
been initiated. 
28. AIRPORT ROAD BRIDGE, 
FRANKSTOWN, MS 
Location. The project is in northeastern Mississippi. 
The Airport Road Bridge crosses Twenty Mile Creek 
and is located about 0.5 mile north of Frankstown, in 
Prentiss County, Mississippi. 
Existing Project. The project provides for streambank 
protection along a 300-foot reach of the stream. 
The creek's banks and bottom were graded and protected 
with 24 inches of riprap on 6 inches of bedding 
material and filter fabric. A 3-foot-high weir was placed 
just downstream from the bridge. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. Project has 
been turned over to local sponsor to maintain. 
Operations and results during fiscal year. New Work: 
Miscellaneous work cost $504. 
Condition at end of fiscal year. Project was essentially 
completed in December 1984 at a total cost of $215,860. 
29. BIG BROWN CREEK 
AND TRIBUTARY, 
PRENTISS COUNTY, MS 
Location. The project is located at the Marietta- 
Hazeldell Road bridges crossing Big Brown Creek and 
Big Brown Creek tributary located about 2.0 and 2.2 
miles, respectively, east-north-east of Marietta in 
Prentiss County, MS. 
Existing Project. The authorized project provides for 
emergency streambank protection to the banks and the 
bottoms of the channels to retard erosion at the 
described project site. The banks and bottoms' will be 
graded and protected with 24 inches of riprap on six 
inches of bedding material and filter fabric. The placement 
of the riprap at the bridge crossing Big Brown 
Creek would begin 50 feet downstream from the centerline 
of the bridge and will extend upstream for 100 feet. 
The placement of the riprap at the bridge crossing Big 
Brown Creek tributary will begin 60 feet downstream 
from the centerline of the bridge and will extend 
upstream for 100 feet. 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. New Work: 
Preliminary work in the channels and miscellaneous 
costs amounted to $26,461. 
Condition at end of fiscal year. Project construction 
was initiated in FY 1986 and is scheduled for completion 
in FY 1987. 
30. BOLIGEE CANAL, BOLIGEE, AL 
Location. Boligee, Alabama is located in southern 
Greene County about 40 miles west of Tuscaloosa, 
Alabama. Boligee Canal originates about five miles 
northeast of Boligee and flows southwesterly to a point 
north of Boligee where it turns west and flows for about 
1.5 miles before it enters a natural channel, approxi- 
10-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
mately two miles upstream from its mouth on the 
Tombigbee River. 
Existing project. The authorized project provides for 
clearing and snagging Boligee Canal from its confluence 
with the Tombigbee River upstream to mile 5.84. Work 
will be done from within the channel and extend from 
top bank to top bank, an approximate width of 20 feet. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New work: 
Clearing and snagging within the channel and other 
miscellaneous costs amounted to $162,554. 
Condition at end of fiscal year. Project construction 
was initiated and essentially completed during FY 1986. 
31. CHATTAHOOCHEE RIVER, 
EUFAULA, AL 
Location. The project is located at the Alabama State 
Docks Barge Port on the Chattahoochee River in 
Eufaula, AL. 
Existing project. The authorized project provides for 
shoreline protection consisting of riprap placed on the 
slopes for 300 feet along the State Docks and a 60 linear 
foot sheet pile cutoff wall driven behind the docks 
wharf. Work will prevent further erosion and loss of fill 
material under the wharf. 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. New work: 
Preliminary work on channel and miscellaneous costs 
amounted to $14,165. 
Condition at end of fiscal year. Project construction 
was initiated in FY 1986 and is scheduled for completion 
in FY 1987. 
32. COUNTY ROAD BRIDGE OVER 
LEAF RIVER, MAHNED, MS 
Location. The project is located at the bridge that 
crosses the Leaf River 0.45 miles upstream of its 
confluence with Tallahala Creek and about one mile 
north of Mahned, MS. 
Existing project. The streambank erosion project 
provides for the protection of bridge piers undermined 
by the river at a county road bridge near Mahned, MS. 
Protection was achieved by construction of a bank 
revetment extending 400 feet upstream and 200 feet 
downstream from the bridge. A blanket of riprap was 
used under the bridge to prevent further erosion around 
the undermined piers. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. Project has 
been turned over to local sponsor to maintain. 
Operations and results during fiscal year. New work: 
None. 
Condition at end of fiscal year. Project was initiated 
in July 1979 and completed in November 1979. 
33. GOODFOOD CREEK, 
CHICKASAW COUNTY, MS 
Location. The project is located at Goodfood Creek 
Road about 1.5 miles east of U.S. Forest Service's Davis 
Lake recreation area in the northern portion of Chickasaw 
County, MS. 
Existing project. The authorised project provides for 
bridge protection using riprap extending 30 feet up and 
downstream of the bridge. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New work: 
Preliminary work on the project cost $22,699. 
Condition at end of fiscal year. Project construction 
was initiated in FY 1986 and is scheduled for completion 
in FY 1987. 
34. HIGHWAY 39 BRIDGE, 
GAINESVILLE, AL 
Location. The project is located on the Tombigbee 
River, upstream of the Highway 39 bridge in Gainesville, 
AL. 
Existing project. The authorized project provides for 
slope protection for a 2000-foot reach of the east bank 
of the Tombigbee River, immediately upstream of the 
existing Highway 39 bridge. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New work: 
Condition surveys and soil investigations were completed 
at a cost of $1,254. 
Condition at end of fiscal year. Work on the project 
will continue during FY 1987 and is scheduled for 
completion in FY 1988. 
35. HOUSTON SCHOOL ROAD BRIDGE, 
ITAWAMBA COUNTY, MS 
Location. Houston School Road Bridge crosses 
Tynes Branch, a Twenty Mile Creek tributary, and is 
located about two miles west of Houston in northwest 
Itawamba County, MS. 
Existing project. The project provides for bridge 
protection using riprap extending 62 feet downstream 
of centerline of bridge and extending upstream for 99 
feet. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. New work: 
Installation of riprap and other miscellaneous costs 
amounted to $20,738. 
Condition at end of fiscal year. Project was initiated 
in FY 1986 and is scheduled for completion in FY 1987. 
36. LEAF AND BOWIE RIVERS, 
HATTIESBURG, MS 
Location. The Leaf River forms the east boundary of 
10-14

MOBILE, ALABAMA DISTRICT 
the city of Hattiesburg, the county seat of Forrest 
County, located in south-central Mississippi. The river 
separates Hattiesburg from the smaller city of Petal. 
Bowie River flows southeasterly along the northern 
boundary of Hattiesburg and joins the Leaf River at the 
northeast corner of the city. 
Existing project. The project provides for channel 
snagging, overbank clearing within the flood plains, 
riprap protection of the Southern Railroad and River 
Avenue Bridge piers and removal of the Petal sewage 
lagoon. Work will also include installation of a flood 
warning system. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New work: 
Installation of riprap protection, overbank clearing and 
miscellaneous costs amounted to $1,067,472. 
Condition at end of fiscal year. Remaining work on 
the project is scheduled for completion in FY 1987. 
Construction costs as of September 30, 1986 amounted 
to $1,067,472. 
37. MARTIN CREEK, 
PRENTISS COUNTY, MS 
Location. The project is located at the Altitude Road 
bridge crossing Martin Creek about 6.7 miles eastsoutheast 
of Booneville in Prentiss County, MS. 
Existing project. The project provides for emergency 
streambank protection to the banks and the bottom of 
the channel to retard erosion at the Altitude Road 
bridge crossing Martin Creek. The banks and bottom 
will be graded and protected with 24 inches of riprap on 
6 inches of bedding material and filter fabric. Two 
hundred linear feet of barbed wire fence will have to be 
moved. Two acres of land will be required for construction 
of the project. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. New work: 
Preliminary work on the project during FY 1986 cost 
$14,644. 
Condition at end of fiscal year. Project construction 
was initiated in FY 1986 and is scheduled for completion 
in FY 1987. 
38. MURDER CREEK, 
EAST BREWTON, AL 
Location. The project is located in the city of East 
Brewton along the left bank of Murder Creek in the 
vicinity of Forrest and Snowden Avenues. 
Existing project. The project consists of non-structural 
measures of flood plain evacuation and flood proofing 
of selected buildings for the reduction of flood damages. 
Local cooperation. Fully complied with. Project 
turned over to local sponsor to maintain. 
Operations and results during fiscal year. New work: 
Miscellaneous costs amounted to $530. 
Condition at end of fiscal year. This non-structural 
plan was completed June 1984 and entire project 
completed September 1985. Total costs to date have 
amounted to $903,474. 
39. MURDER AND BURNT CORN 
CREEKS, BREWTON, AL 
Location. The project is located in the city of 
Brewton, AL near the confluence of Murder and Burnt 
Corn Creeks in the commercial district of downtown 
Brewton. 
Previous project. A limited stream clearing and 
snagging project was completed in 1980 on portions of 
both creeks to remove obstructions to flows. This 
interim measure was undertaken to reduce flooding in 
Brewton and East Brewton. Further, an evacuation 
plan for East Brewton was implemented under the 
Section 205 authority. The project involved removal of 
damageable structures from the low-lying flood plain of 
Murder Creek. 
Existing project. the authorized non-structural 
project provides for the alleviation of flood problems at 
Brewton by the removal of 31 damageable structures 
from the 10-year flood plains of Murder and Burnt 
Corn Creeks. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New work: 
Real estate acquisitions during FY 1986 cost $234,624. 
Condition at end of fiscal year. Real estate purchases 
are currently being conducted and will continue 
through FY 1987. 
40. NOXUBEE RIVER RELIEF BRIDGE, 
SHUQUALAK, MS 
Location. The Noxubee River relief bridge is located 
on the Shuqualak-Mahorner Road near Shuqualak, 
Mississippi. The Noxubee River at this location flows 
through Noxubee County, which is located in east 
central Mississippi. The project is about 48 miles south 
of Columbus, Mississippi. 
Existing project. The project provides for streambank 
protection at Noxubee River relief bridge consisting 
of grading and protecting of banks with 24 inches of 
riprap on 6 inches of bedding material and filter fabric. 
This would preclude any erosion from high velocities or 
from sudden drawdown associated with receding floodwaters. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. New work: 
Miscellaneous costs amounted to $6,429. 
10-15

REPORT OF THE CHIEF OF ENGINEERS, U.SI ARMY 1986 
Condition at end of fiscal year. A construction 
contract was awarded in July 1986 and project is 
scheduled for completion in November 1986. 
41. SEWERLINE PROTECTION, 
VALLEY, AL 
Location. Valley, Alabama is located on the west 
bank of the Chattahoochee River in the southeast 
corner of Chambers County. The West Point Lake and 
Dam is located approximately 11 miles up river from 
Valley and controls a drainage area of approximately 
3600 square miles. A sanitary sewage line and pumping 
station were built in 1972 to provide service from 
approximately 200 homes and several businesses 
located near Valley. This line serves as the only sewage 
transport for this area. 
Existing project. The project provides for the restoration 
of approximately 1600 linear feet of streambank. 
This will consist of placing approximately 1550 
cubic yards of No. 5 riprap on 4445 square yards of filter 
fabric. Any reshaping of the bank will be done by 
placing backfill material as opposed to cutting the 
existing streambank. The reshaped bank will then be 
grassed. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. New work: 
Project construction costs amounted to $150,482. 
Condition at end of fiscal year. Construction contract 
was awarded on 17 September 1985. The project was 
essentially completed in FY 1986. 
42. SOPE CREEK, 
MARIETTA, GA 
Location. The project is located in Marietta, Georgia 
in Cobb County which is in the north-central section of 
Georgia, just north-northwest of Atlanta. Sope Creek is 
a small tributary of the Chattahoochee River and flows 
generally from northwest to southeast from its beginning 
in the city of Marietta. 
Existing project. The project provides for flood 
control measures along Sope Creek in Cobb County, 
Georgia. The project provides for both a structural and 
nonstructural component. The structural component 
provides for clearing and snagging of the creek. This 
would involve the clearing of all material, trees, shrubs 
and any underbrush less than 12 inches in diameter from 
a strip 30 feet wide on each side of the creek and 
removing all trees, shrubs and underbrush within the 
creek banks. Snagging would involve the removal of all 
fallen trees and debris which are in the creek. The 
nonstructural component provides for the evacuation 
of 13 structures located on the west side of the creek 
within the Fox Hill subdivision. The project provides 
for purchase and removal of the structures. (See Table 
10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. New Work: 
Land and damages and engineering and design costs 
amounted to $314,854. 
Condition at end of fiscal year. The nonstructural 
component as of 30 September 1986; 10 structures were 
acquired and removed. The structural portion, clearing 
and snagging, will be readvertised in March 1987. 
43. TALLABINELLA CREEK, 
CHICKASAW COUNTY, MS 
Location. The project is located along Tallabinella 
Creek at Pleasant Valley Road about 3.5 miles northwest 
of the city of Okolona in northeast Chickasaw 
County. 
Existing project. The project provides for bridge 
protection using riprap extending 30 feet up and 
downstream of the bridge. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. New work: 
Preliminary work on the project during FY 1986 cost 
$22,900. 
Condition at end of fiscal year. Project construction 
was initiated in FY 1986 and is scheduled for completion 
in FY 1987. 
44. TOMBIGBEE RIVER (EAST FORK), 
MISS. AND ALA. 
Location. The project is located on the Tombigbee 
River and its tributaries between the junction of Browns 
and Mackeys Creek in Itawamba County, Mississippi, 
for a distance of 53 miles along the East Fork of the 
Tombigbee River, from Walkers Bridge at the junction 
of Browns and Mackeys Creeks to the Monroe County 
line, by clearing the banks of trees and underbrush to 
flood stage, the removal of drift jams and the excavation 
of 13 cutoff channels; and for additional channel 
improvements and related works for flood control of 
the Tombigbee River and tributaries above the mouth 
of and including the Noxubee River in accordance with 
plans approved by the Chief of Engineers, to protect 
people and valuable agricultural property from overflow 
waters of the Tombigbee River. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Fully complied with on work 
done under the 1936 Flood Control Act. Work to be 
done under authority of the 1941 Flood Control Act 
requires local interest to provide all lands, easements, 
and rights-of-way for project construction; hold and 
save the United States free from damages due to construction 
of the project; and maintain and operate all 
the works after completion in accordance with regulations 
prescribed by the Secretary of the Army. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $132,513. Routine maintenance 
of channels and canals cost $29,358. Engineering 
and design and supervision and administration cost 
$2,227. 
Condition at end of fiscal year. The project for 
10-16

MOBILE, ALABAMA DISTRICT 
Itawamba County, as authorized in the 1936 Flood 
Control Act, was completed during fiscal year 1940. No 
work has been done on the extension of the project 
authorized in the 1941 Flood Control Act. The over-all 
project, as modified, is about 55 percent completed. 
Total Federal costs of the existing project as of September 
30, 1986 were $134,801 for new work and $2,378,094 
for maintenance, a total of $2,512,895. 
45. TOMBIGBEE RIVER 
TRIBUTARIES, MS AND AL 
Location. The Tombigbee River rises in extreme 
northeast Mississippi and flows southerly through 
eastern Mississippi and western Alabama, emptying 
into the Mobile River about 45 miles above its mouth at 
Mobile, Alabama. Tributaries to be improved for flood 
control are all in northeast Mississippi and northwest 
Alabama. 
Existing project. The authorized project provides for 
improvement of 22 tributaries of the Tombigbee River 
by means of channel clearing and snagging. Approved 
estimate of cost (1986) for new work is $51,446,900; 
consisting of $49,000,000 Federal funds, and $2,446,900 
non-Federal funds. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Local interests must furnish lands 
and rights-of-way for construction; make all roads, 
highway bridge, and utility changes, alterations, additions, 
and relocations necessary for the project; hold the 
United States free from damages; prevent future encroachments 
along the improved channels; maintain all 
works after completion; and contribute $12,146,600 in 
cash or equivalent work. 
Operations and results during fiscal year. New work: 
Provided riprap armor for bank stabilization and 
erosion control at Twenty Mile Creek at a total cost of 
$3,126,782. Engineering and design costs for Luxapalila 
Creek and Tibbee River Basin were $170,432. 
Condition at end of fiscal year. Construction commenced 
in July 1965, and is proceeding stream by 
stream as funds are made available. Federal cost of 
existing project as of September 30, 1986 was 
$18,222,988 for new work. Contributed funds for new 
work amounted to $63,281. 
46. U.S. HIGHWAY 11 BRIDGE, 
FOSTERS, AL 
Location. The U.S. Highway 11 Bridge is located 
near the community of Fosters, in Tuscaloosa County, 
Alabama and crosses over the Black Warrior River at 
navigation mile 321.0 The bridge is about 10 miles 
southwest of Tuscaloosa, Alabama. 
Existing project. The project provides for slope 
protection by placing riprap along a 240-foot reach of 
the left descending bank at the bridge. (See Table 10-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New Work: 
Project construction costs amounted to $170,245. 
Condition at end of fiscal year. Construction contract 
was awarded on 13 September 1985. Project was 
essentially completed in FY 1986. 
47. WOLF CREEK, 
U.S. HIGHWAY 45 BRIDGE, 
PRENTISS COUNTY, MS 
Location. The U.S. Highway 45 bridge is located in 
Prentiss County, Mississippi in the northeastern part of 
the state. The project is located approximately 75 miles 
north of Columbus, Mississippi. The U.S. Highway 45 
bridge crosses Wolf Creek at mile 0.9 above the mouth 
of the creek. 
Existing project. The project provides for slope 
protection under the U.S. 45 bridge. The banks would 
be graded and protected with 24 inches of riprap on 
6 inches of bedding material and filter fabric. Threefoot 
high weirs would be placed just downstream from 
the bridge to provide a backwater effect and.a section of 
riprap at the weir would be grouted. (See Table l10-B for 
authorizing legislation.) 
Local cooperation. Fully complied with and turned 
over to local sponsor to maintain. 
Operations and results during fiscal year. New Work: 
Miscellaneous costs amounted to $505. 
Condition at end of fiscal year. Project was essentially 
completed in December 1984 at a total cost of $154,641. 
48. OLD HIGHWAY 82 BRIDGE, 
COLUMBUS, MS 
Location. The Old Highway 82 bridge is located at 
Columbus, Mississippi in east-central Mississippi and 
crosses the Tombigbee River at river mile 364.96. It is 
about 131 miles northeast of Jackson, Mississippi. 
Existing project. The project provides protection 
along the right descending bank. The slope protection 
would consist of 24 inches of riprap on 6 inches of 
bedding material and a filter fabric. The riprap placement 
would begin approximately 140 feet downstream 
of the centerline of the bridge and extend upstream 
along the right descending bank for 330 feet. (See Table 
10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New Work: 
Project construction costs totaled $84,286. 
Condition at end of fiscal year. Construction contract 
was awarded on 25 July 1985. Project was essentially 
completed in FY 1986. 
49. INTERSTATE 59 BRIDGES, 
FOSTERS, AL 
Location. The Interstate 59 bridges are located near 
the community of Fosters in Tuscaloosa County, Alabama 
and crosses over the Black Warrior River at 
10-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
navigation mile 320.5 The bridges are about 10 miles 
southwest of Tuscaloosa, Alabama. 
Existing project. The project provides streambank 
protective measures at the bridges. Bank stabilization 
would consist of placing riprap along a 195-foot reach 
of the left descending bank at the bridge. (See Table 
10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. New Work: 
Project construction cost $1 19,039. 
Condition at end of fiscal year. Construction contract 
was awarded on 13 September 1985. Project was 
essentially completed in FY 1986. 
50. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Local flood protection works for which inspection is 
performed under this heading consist of levee projects at 
West Point, Georgia, on the Chattahoochee River; 
Beaver Creek at Montezuma, Georgia, in the Flint 
River Basin; Elba and Geneva, Alabama in the Choctawhatchee 
River Basin; Rome, Georgia, and Little Wills 
Creek at Collinsville, Alabama, in the Alabama-Coosa 
River Basin. Channel rectification projects include 
Little Cove Creek, Glencoe, Alabama and Black Creek, 
Gadsden, Alabama in the Alabama-Coosa River Basin; 
Big Brown Creek, Donivan Creek, Twenty Mile Creek 
and Mantachie Creek, near Fulton, Mississippi, Stanifer 
Creek near Amory, Mississippi, Houlka Creek and 
Sakatonchee Creek in Chickasaw and Clay Counties, 
Mississippi, James Creek in Monroe County, Mississippi, 
Sun and Trim Cane Creeks, Oktibbeha County, 
Mississippi, and Luxapalila Creek, Lowndes County, 
Mississippi, all in the Tombigbee River Basin; Gordon's 
Creek, Hattiesburg, Mississippi and Sowashee Creek, 
Meridian, Mississippi in the Pascagoula River Basin; 
Burnt Corn and Murder Creeks, Brewton, Alabama in 
the Conecuh River Basin; Autauga Creek, Prattville, 
Alabama; Poley Bridge, Goose Pond and Walnut 
Creeks, Clanton, Alabama; Pinchgut Creek, and Cahaba 
River, Trussville, Alabama; Yellow Jacket Creek, 
Hogansville, Georgia; Town Creek, Americus, Georgia; 
and Lake Douglas in Bainbridge, Georgia. Shore 
protection and erosion control projects include 
Valparaiso, Florida; Harrison County, Mississippi; 
Lorraine Road, Biloxi, Mississippi; Leaf River, Mahned, 
Mississippi; Pumpkinvine Creek, Emerson, Georgia; 
and Chickasawbogue Creek, US Highway 43 Bridge, 
Linden, Alabama. The project at Rome and Montezuma, 
Georgia and Collinsville, Alabama include 
pumping stations. Inspections were made during FY 86 
to determine the extent of compliance with approved 
regulations for maintenance and operation of the 
project. Responsible local officials were advised of 
inadequacies in the maintenance and operation of the 
local flood protection works under their jurisdiction 
where appropriate. Followup for compliance of the 
deficient projects continued during the year. Fiscal year 
costs were $27,699. Total cost to September 30, 1986. 
was $379,300 charged to maintenance. 
51. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 10-E) 
52. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended (Pre-authorization). 
Snagging and Clearing for flood control pursuant to 
Section 208 of Flood Control Act of 1954, as amended. 
Emergency streambank and shoreline protection pursuant 
to Section 14 of the Flood Control Act of 1946, as 
amended. 
(See Table 10-J) 
Emergency flood control activities-repair, flood 
fighting, and rescue work under Public Law 99, 84th 
Congress, and antecedent legislation, and disaster relief 
and assistance under Public Law 288, 93d Congress. 
(See Table 10-J) 
Multiple-Purpose Projects Including Power 
53. ALABAMA-COOSA RIVERS, 
AL AND GA 
Location. Alabama River is formed 18 miles above 
Montgomery, Alabama, by the junction of the Coosa 
and Tallapoosa Rivers. It then flows southwesterly 
through Alabama 318 miles and unites with the Tombigbee 
River about 45 miles north of Mobile, in southwestern 
Alabama, to form the Mobile River. (See 
Geological Survey maps for central and southwest 
Alabama.) The Coosa River is formed at Rome, 
Georgia, in northwest Georgia, by the junction of the 
Oostanaula and Etowah Rivers, which have their 
sources in southeastern Tennessee and northern Georgia. 
From Rome the Coosa River flows southwesterly 
through Georgia and Alabama 286 miles and unites 
with the Tallapoosa River near Montgomery, Alabama, 
at about the center of the State, to form the Alabama 
River. (See Geological Survey maps for northeast Alabama, 
southeast Tennessee, and northwest Georgia.) 
Previous project. Projects for Alabama River: for 
details see page 1837, Annual Report for 1915; page 725, 
Annual Report for 1938; and page 592, Annual Report 
for 1944. Projects for Coosa River: for details see page 
1837, Annual Report for 1915; page 728, Annual 
Report for 1938; and page 594, Annual Report for 1944. 
Existing project. The authorized project provides for 
full development of the Alabama-Coosa Rivers and 
tributaries for navigation, flood control, power, recreation, 
and other purposes, in accordance with plans 
under preparation by Chief of Engineers, subject to 
modifications thereof which may be advisable for 
increasing development of hydroelectric power. (See 
Table 10-B for authorizing legislation.) Public Law 436, 
10-18

MOBILE, ALABAMA DISTRICT 
83rd Congress, suspended authorization of the comprehensive 
plan, insofar as it provides for development of 
hydroelectric power for Coosa River, to permit non- 
Federal interests to develop the Coosa River by construction 
of a series of dams in accordance with 
conditions of a license issued pursuant to Federal Power 
Act and in accordance with certain other provisions and 
requirements of the aforementioned public law. The 
present phase of improvement provides for construction 
of Robert F. Henry and Millers Ferry multiplepurpose 
improvements, Claiborne Lock and Dam, and 
supplemental channel work providing for a nine-foot 
deep navigation channel from the mouth of the Alabama 
River to Montgomery, Alabama, and for construction 
of Carters Dam, a multiple-purpose improvement 
on Coosawattee River, Georgia. 
Local cooperation. Requirements of local cooperation 
will be determined as formulation of plans for 
development of projects progress. No action in the 
matter of local cooperation has been initiated. 
Terminal facilities. On the east bank of the river a 
natural landing connects with city streets at Montgomery. 
Wofford Oil Company has a small wharf about 10 
miles below Montgomery equipped for handling petroleum 
products. There are also various natural landings 
along the river. Facilities and natural landings on 
Alabama River are considered adequate for existing commerce. 
Operations and results during fiscal year. New work: 
Engineering and design of recreation facilities at Robert 
F. Henry Lock and Dam cost $793. Public use areas at 
Millers Ferry Lock and Dam cost $38,776. Engineering 
and design for Coosa River navigation segment amounted 
to $5,745. Miscellaneous administrative costs at 
Carters amounted to $866. Total cost of new work 
amounted to $46,180. 
Maintenance: Contract dredging removed 120,100 
cubic yards of material from the river system at a cost of 
$397,135. General charges for recreation, supervision 
and administration and miscellaneous costs amounted 
to $1,399,302. Coosa River Reservoir operations cost 
$1,055,220 and lock operations $407,877. In addition, 
operation of Robert F. Henry Lock and Dam cost 
$1,858,604, Millers Ferry Lock and Dam, $2,392,094; 
Carters Lake, $2,507,840; all for a total maintenance 
cost of $10,018,072. 
Condition at end of fiscal year. Construction was 
initiated on Carters Dam in April 1962,on Millers Ferry 
Lock and Dam in April 1963, Claiborne Lock and Dam 
in May 1965, and Robert F. Henry Lock and Dam in 
March 1966. Carters Dam was essentially completed in 
FY 1980. The authorized nine-foot navigation channel 
to Montgomery, Alabama was opened to traffic in 
January 1972. Overall construction is essentially complete 
at Millers Ferry Lock and Dam. Construction of 
Robert F. Henry Lock and Dam is essentially complete. 
Total Federal costs of the existing project as of September 
30, 1986 are $413,226,247, including 
$305,733,354 for new work and $107,492,893 for maintenance. 
(See Table 10-L.) 
53A. CARTERS LAKE, GA 
Location. The damsite is in Murray County, Georgia, 
on the Coosawattee River 26.8 miles above its junction 
with Conasauga River, one of the headwater tributaries 
of the Alabama-Coosa system. It is 60 miles north of 
Atlanta near the town of Carters, Georgia. The reservoir 
is in both Murray and Gilmer Counties. 
Existing project. The authorized project consists of a 
1,950-foot long rockfill dam across the river, three 
saddle dikes on the left bank, a 258-foot long high-level, 
gated spillway on the left bank, a power house on the 
right bank having two conventional units with a generating 
capacity of 125,000 kilowatts each and two pumpgenerating 
units of the same size, and a regulating dam 
2,855 feet long with a gated spillway 208 feet long 1.5 
miles downstream from the main dam. The lake has an 
area of 3,220 acres, at maximum power pool elevation 
1,072, total capacity of 472,800 acre-feet, of which 
134,900 acre-feet is usable for power and 95,700 acrefeet 
reserved for flood control and 242,200 acre-feet 
dead storage. For other information see description of 
Alabama-Coosa project. 
Operations and results during fiscal year. New Work: 
Miscellaneous administrative costs totaled $866. 
Maintenance: Operation and ordinary maintenance 
of the dam, reservoir, powerhouse, service and recreational 
activities and administration incidental thereto 
cost $2,507,840. Gross power generation amounted to 
460,156,000 kilowatt hours during FY 1986, of which 
432,642,000 were delivered to Southeastern Power 
Administration. Recreation attendance during CY 1985 
totaled 893,000 recreational user days. 
Condition at end of fiscal year. Construction which 
commenced in April 1962 was essentially completed in 
September 1980. Total Federal costs of the existing 
project as of September 30, 1986 are $132,491,479, 
including $111,140,340 for new work and $21,351,139 
for maintenance. 
53B. CLAIBORNE LOCK AND DAM, AL 
Location.The site is in Monroe County at mile 81.8 
on the Alabama River, 15 miles northwest of Monroeville 
and 5.7 miles upstream from the U.S. Highway 84 
bridge. 
Existing project. The authorized project consists of a 
short earth dike on the right bank, a combination of a 
fixed-crest and gated spillway extending across the river 
channel and into the left bank, a navigation lock and 
mound on the left bank, and an earth dike extending 
across the left overbank to high ground. Normal upper 
pool is at elevation 35 and the minimum pool will be 
elevation 32 to provide storage for reregulation of 
Millers Ferry powerplant releases. The 60-mile long 
reservoir has an area of 5,850 acres and a volume of 
96,360 acre-feet. For other information see description 
10-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
of Alabama-Coosa projects. 
Operations and results during fiscal year. New work: 
none. Maintenance: none. Recreation attendance during 
CY 1985 totaled 666,000 user days. 
Condition at end of fiscal year. Construction began in 
May 1965 and was completed in FY 1976 at a total cost 
of $27,997,450. 
53C. ROBERT F. HENRY LOCK AND 
DAM, AL 
Location. The site is in Lowndes and Autauga 
Counties at mile 245.4 on the Alabama River, 26 miles 
west of Montgomery. 
Existing project. The authorized project provides for 
a navigation lock, a gated spillway, and a power plant 
located at mile 245.4. The normal upper pool is at 
elevation 125.0 and the minimum lower pool due to the 
Millers Ferry Lock and Dam is at elevation 80.0. The 
structures consist of earth dikes and a power plant on 
the right bank, a gated spillway in the river channel, a 
lock and mound on the left bank, and an earth dike 
extending upstream parallel to the Western Railway of 
Alabama. The total length of the structures is about 
14,962 feet with maximum height above the foundation 
at the power plant intake about 101 feet. The power 
plant contains four 17,000-kw. units. The 88-mile long 
reservoir has an area of 12,300 acres at normal pool level 
and a total capacity of 234,200 acre-feet. The lock has a 
chamber 84 feet wide and 600 feet long and provides a 
12-foot depth over the lower miter sill. For other 
information see description of Alabama-Coosa project. 
Operations and results during fiscal year. New work: 
Miscellaneous administrative costs totaled $793. 
Maintenance: Operation and maintenance costs 
amounted to $1,858,604. Gross power generation 
amounted to 211,722,000 kilowatt-hours during FY 
1986, of which 205,526,000 were delivered to Southeastern 
Power Administration. Recreation attendance 
at R.E. "Bob" Woodruff Lake during CY 1985 totaled 
2,469,000 user days. 
Condition at end of fiscal year. Construction began in 
March 1966 and is essentially complete. The first 
powerhouse unit was placed in operation in June 1975, 
with the last unit on line in November 1975. Total 
Federal costs of the project as of September 30, 1986 
were $100,191,192, including $83,360,800 for new work 
and $16,830,392 for maintenance. 
53D. MILLERS FERRY LOCK AND 
DAM, AL 
Location. The site is in Wilcox County at mile 142.2 
on the Alabama River, 10 miles northwest of Camden, 
Alabama, and 30 miles southwest of Selma. 
Existing project. The project consists of an earth dike 
on the right bank, a concrete, gravity-gated spillway in 
the river channel, a lock and mound on the left bank, an 
earth dike extending downstream paralleling the lock, 
to the powerhouse intake structure; a powerhouse, and 
an earth dike extending to high ground on the left bank. 
Normal upper pool is at elevation 80. The powerplant 
contains three 25,000 kilowatt units. The 103-mile long 
reservoir has an area of 17,200 acres at normal pool level 
and a total capacity of 331,800 acre-feet. The lock 
chamber is 84 by 600 feet with a 13-foot depth over the 
miter sills. For other information see description of 
Alabama-Coosa project. 
Operations and results during fiscal year. Total cost 
of new work amounted to $38,776 for public use 
facilities. 
Maintenance: Operation and maintenance of lock, 
dam, powerhouse, reservoir, and administration incidental 
thereto cost $2,392,094. Gross power generation 
amounted to 274,532,000 kilowatt-hours during FY 
1986, of which 270,200,000 kilowatt-hours were delivered 
to Southeastern Power Administration. Recreation 
attendance at William "Bill" Dannelly Reservoir 
during CY 1985 totaled 2,355,968 user days. 
Condition at end of fiscal year. Construction began in 
April 1963. The lock was placed in temporary operation 
in June 1968 and opened to full use in November 1969. 
The powerhouse units were placed on line during April 
and May 1970. The project was essentially completed in 
1980. Total Federal costs of the project as of September 
30, 1986 were $63,122,507 for new work and $28,826,801 
for maintenance, a total of $91,949,308. 
53E. COOSA RIVER NAVIGATION 
Location. The Coosa River is one of the two major 
tributaries forming the Alabama River approximately 
18 miles northeast of Montgomery, Alabama. From its 
source at the juncture of the Etowah and Oostanaula 
Rivers in northwest Georgia, it flows southwesterly 
about 286 miles to join with the Tallapoosa River in 
forming the Alabama River. 
Existing project. The improvement of the Alabama- 
Coosa River for navigation to Rome, Georgia was 
authorized by Congress in the River and Harbor Act of 
1945. A report in House Document 320, transmitted to 
Congress on 27 January 1960, recommended that the 
navigation project for the Coosa River from Montgomery 
to Gadsden be accomplished after the waterway to 
Montgomery was assured. The plan of improvement 
identified in House Document 320 provided for a 
waterway 9 feet deep with widths of 200 feet to 
Montgomery, Alabama, and 150 feet to Rome, Georgia. 
The water-way to Montgomery has essentially been 
completed. The estimated 1986 cost for the waterway 
from Montgomery to Gadsden is $1,359,000,000 of 
which $1,304,000,000 is Federal and $55,000,000 non- 
Federal. 
Operations and results during fiscal year. Funding 
was initiated in FY 1978 for preconstruction planning. 
FY 1986 costs were $5,745 for engineering, design, 
supervision and administration. In addition, general 
investigations funds expended amounted to $11,543 for 
10-20

MOBILE, ALABAMA DISTRICT 
advanced engineering and design. 
54. ALLATOONA LAKE, COOSA 
RIVER BASIN, GA 
Location. The project is on Etowah River in Bartow 
County, Georgia, about 48 miles upstream from Rome, 
Georgia, about five miles due east of Cartersville, 
Georgia, and about 2,000 feet downstream from mouth 
of Allatoona Creek. The reservoir extends about 28 
miles up the Etowah River at maximum power-pool 
elevation of 840 feet above mean sea level. 
Existing project. The authorized project provides for 
a dam and reservoir for flood control, regulation of 
streamflow for navigation, and development of hydroelectric 
power. Height above the river bottom of the 
concrete, gravity-type dam is about 190 feet, from 
elevation 690 feet to 880 feet national geodetic datum. 
The spillway, with crest at elevation 835, is controlled by 
nine tainter gates, 40 feet wide by twenty-six feet high, 
and two tainter gates, 20 feet wide by twenty-six feet 
high; having a combined discharge capacity of 321,000 
cubic feet per second with the water surface at elevation 
870.3. One 48-inch diameter sluicing conduit with a free 
discharge valve and four sluices, 5 feet-8 inches wide by 
10 feet high, are included in dam. Installed generating 
capacity consists of two 36,000 kilowatt units and one 
2,000 kilowatt unit, or a total of 74,000 kilowatts. 
Ultimate installed capacity will be 110,000 kilowatts. 
The reservoir, covering 19,200 acres at elevation 860, 
has a storage capacity of 670,000 acre-feet. The initial 
construction cost was $31,424,738, excluding the addition 
of recreation facilities at the completed project. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. None required (Sec. 2, Flood 
Control Act of June 28, 1938, applies). 
Operations and results during fiscal year. New work: 
Engineering and design of public use facilities cost 
$7,671. 
Maintenance: Operation and ordinary maintenance 
of the dam, reservoir, powerhouse, service and recreational 
activities, and administration incidental thereto 
cost $5,746,764. Gross power generation at Allatoona 
Reservoir amounted to 68,852,700 kilowatt-hours during 
FY 1986 of which 66,260,000 kilowatt-hours were 
delivered to Southeastern Power Administration. Recreational 
attendance at Allatoona Lake during CY 1985 
totaled 9,952,100 recreational user days. 
Condition at end of fiscal year. Construction of the 
existing project began in March 1944 and was completed 
in October 1955. Total Federal costs under existing 
project as of September 30, 1986 were $35,709,084 for 
new work and $52,834,1 17 for maintenance, a total of 
$88,543.201. 
55. APALACHICOLA, 
CHATTAHOOCHEE, AND FLINT 
RIVERS, AL, GA, AND FL 
Location. The Apalachicola River is formed at the 
southwest corner of the State of Georgia by the junction 
of the Chattahoochee and Flint Rivers and flows south 
108 miles emptying into Apalachicola Bay. Florida 
River enters the Apalachicola River from the east at 
mile 45.4 and the River Styx also enters from the east at 
mile 36.7 and Chipola River enters from the west at mile 
28.2. (See Coast and Geodetic Survey Chart 11401.) The 
Chattahoochee River, 418 miles long, rises in northeast 
Georgia and flows southwesterly to West Point, and 
thence southerly to join the Flint River at the southwest 
corner of Georgia, forming the Apalachicola River. 
(See Geological Survey maps for northwest Georgia.) 
The Flint River, 330 miles long, rises in west central 
Georgia, flows generally southeasterly to Albany, and 
thence southwest to the southwest corner of the State, 
where it joins the Chattahoochee River to form the 
Apalachicola River. (See Geological Survey maps for 
southwest Georgia.) 
Previous project. For details see page 484 of Annual 
Report for 1963. 
Existing project. The authorized project provides for 
development of the Apalachicola, Chattahoochee, and 
Flint Rivers for navigation, flood control, hydropower, 
and recreation. Navigation features of the existing 
project consist of a continuous 9-foot by 100-foot 
channel in the Apalachicola River from the intersection 
of the Gulf Intracoastal Waterway to the confluence of the 
Chattahoochee and Flint Rivers, 104 miles, thence to 
Columbus, Georgia, on the Chattahoochee River, 164 
miles, and to Bainbridge, Georgia, on the Flint River, 29 
miles, and a 3-foot by 100-foot channel on the Flint 
River from Bainbridge to Albany, Georgia, 74 miles, 
thence a channel suitable for light draft vessels at 
moderate stage to Montezuma, Georgia, 79 miles, to be 
accomplished by dredging, contraction works, and 
construction of three locks and dams (Jim Woodruff, 
George W. Andrews, and Walter F. George) along the 
9-foot depth channel, two multipurpose dams (West 
Point and Buford) on the Chattahoochee River, three 
multipurpose dams (Lower Auchumpkee Creek, Lazer 
Creek, and Spewrell Bluff) on the Flint River, and 
minor improvements of certain streams tributary to the 
Apalachicola River, including a 9-foot by 100-foot side 
channel, approximately 2,000 feet long, from Apalachicola 
River to Apalachicola River Industrial Park at 
Blountstown, Fla. Plane of reference is mean low water. 
Hydropower and flood control storage is provided at 
Sidney Lanier, Walter F. George, and West Point, and 
hydropower is provided at Jim Woodruff. The authorized 
but unconstructed projects of Lazer Creek, Lower 
Auchumpkee Creek and Spewrell Bluff would have 
storage for hydropower and flood control. For further 
details see Annual Report for 1962. (See Table 10-B for 
authorizing legislation.) 
Mean range of tide at the mouth of Apalachicola 
River is 1.6 feet. At the point where the river is formed 
the variation between low and high water is about 37 
feet. On the Chattahoochee River, variation between 
average low and high water is about 20 feet, and extreme 
10-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
fluctuation is 65.3 feet at Eufaula. On the Flint River the 
extreme fluctuation of stage due to flood is 40 feet, while 
average variation between low and high water is about 
21.5 feet. 
Local cooperation. Fully complied with to date. 
Terminal facilities. About 200 feet of public docks, in 
addition to private wharves, are available at Apalachicola, 
Florida. There are numerous constructed and 
natural landings along the entire system for launching 
small craft. For details of other terminal facilities, which 
are considered adequate for existing commerce, see 
individual project descriptions. See also Table 10-M on 
locks and dams and multiple-purpose development 
included in existing project. 
Operations and results during fiscal year. New work: 
Construction of cut off wall under Walter F. George 
Dam to correct seepage cost $468,153. Recreation 
facilities for various reservoirs cost $196. 
Maintenance: The contractor's dredge removed 
827,600 cubic yards (net) of material from the river 
system at a cost of $427,512. Other costs incidental to 
the overall project amounted to $3,098,355. Operation 
of George W. Andrews Lock and Dam cost $383,842. 
Operations and maintenance locks and dams: Buford 
Dam cost $7,328,659; Jim Woodruff Lock and Dam, 
$4,910,998; Walter F. George Lock and Dam, 
$7,347,633; and West Point Lake, $5,288,528. Total FY 
1986 cost for entire project was $28,785,723, of which 
$196 was for new work, and $28,785,527 was for 
operation and maintenance. Detailed information on 
operations and costs applicable to the individual dam 
projects is presented under their respective project titles 
elsewhere in this report. 
Condition at end of fiscal year. Improvement of 
Apalachicola River channel by dredging to provide 
project dimensions throughout is complete. All major 
construction on Lake Sidney Lanier Dam, George W. 
Andrews Lock and Dam, Jim Woodruff Lock and 
Dam, and Walter F. George Lock and Dam, is complete. 
West Point is essentially complete with the 
exception of adding recreation facilities. Channel rectification 
in Apalachicola River was completed December 
1970. More detailed information concerning condition 
at the end of fiscal year for individual locks and 
dams and multiple-purpose developments comprising 
the system is presented under their respective project 
titles elsewhere in this report. Work remaining to 
complete the project consists of completion of recreational 
facilities at Lake Sidney Lanier, George W. 
Andrews Lock and Dam, Jim Woodruff Lock and 
Dam, Walter F. George Lock and Dam and West Point 
Dam; design and construction of Lazer Creek, Spewrell 
Bluff and Lower Auchumpkee Creek Dam. (See Tables 
10-A and 10-M for fiscal year costs and summaries of 
overall project. 
55A. BUFORD DAM, GA 
Location. Buford Dam is on the Chattahoochee 
River about 348.9 miles above its mouth, 50 miles above 
Atlanta and five miles northwest of Buford, Georgia. 
The reservoir, Lake Sidney Lanier, extends about 47 
miles upstream along the Chattahoochee River, and 
about 21 miles up the Chestatee River, which enters the 
Chattahoochee River 14.5 miles above the dam. 
Existing project. The authorized project provides for 
a rolled-earth dam 1,630 feet long with crest at elevation 
1,106 feet national geodetic datum, or about 192 feet 
above streambed elevation; three earth saddle dikes 
with a total length of 5,406 feet; a chute spillway with 
crest at elevation 1,085; a powerhouse in a deep cut with 
steel penstocks in tunnels, and concrete intake structure 
at the upstream end of the tunnels; and a flood control 
sluice tunnel paralleling the power tunnels. The Lake 
Sidney Lanier reservoir has a gross capacity of 
2,554,000 acre-feet of which 637,000 acre-feet of storage 
is reserved for flood control storage. The power installations 
consist of one generating unit of 6,000 
kilowatts and two units of 40,000 kilowatts each, or a 
total of 86,000 kilowatts. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Operation and maintenance cost 
$7,328,659. Gross power generation amounted to 
111,078,000 kilowatt-hours during FY 1986, of which 
109,169,000 were delivered to Southeastern Power 
Administration. Recreational attendance at Lake Sidney 
Lanier during CY 1985 totaled 16,263,700 recreational 
user days. 
Condition at end of fiscal year. Construction commenced 
in March 1950 and was completed in June 1960. 
The reservoir was in useful operation for flood control 
in February 1956. The first power generating unit was 
placed on the line June 19, 1957; the second on July 26, 
1957; and the third on October 10, 1957. 
55B. GEORGE W. ANDREWS LOCK AND 
DAM, AL AND GA 
Location. The project is on the Chattahoochee River 
about 46.5 miles above its mouth and about one mile 
below the town of Columbia, Alabama, near the head of 
Jim Woodruff Reservoir. (See Geological Survey maps 
for southeast Alabama). The pool extends up the 
navigation channel about 28 miles upstream to Walter 
F. George Lock and Dam. 
Existing project. This single-purpose project provides 
for a concrete fixed-crest spillway 340 feet long extending 
into the right bank with a crest at elevation 102 feet 
national geodetic datum, a concrete gate spillway 
adjacent to the lock 280 feet long with crest at elevation 
82 feet national geodetic datum, a single-lift lock with 
usable chamber dimensions of 82 feet by 450 feet, and a 
maximum lift of 25 feet. Depths are 13 feet over the 
lower sill and 19 feet over the upper sill at normal pool 
elevation. The underlying foundation is limestone. The 
10-22

MOBILE, ALABAMA DISTRICT 
project provides for maintenance and care. The House 
Committee on Public Works, by resolution adopted 
May 19, 1953, approved the plan as proposed by the 
Chief of Engineers for a high dam at Walter F. George 
site and a low dam at the Fort Benning site and a high 
dam at the upper Columbia site, construction of which 
was authorized by the 1946 River and Harbor Act as the 
initiation and partial accomplishment of the plan for 
full development of the Apalachicola, Chattahoochee, 
and Flint River system. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Local interests must operate all 
movable span bridges, provide suitable public terminals, 
and hold the United States free from damages. 
These conditions are being complied with. 
Terminal facilities. At Columbia, Alabama, there is a 
public wharf with concrete deck for handling general 
cargo and a bulk petroleum terminal with an unloading 
dock. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Recreational 
attendance at George W. Andrews Lock and 
Dam during CY 1985 totaled 399,064 recreational user 
days. Maintenance: Operation and maintenance cost 
included under overall Apalachicola, Chattahoochee 
and Flint project. 
Condition at end of fiscal year. Construction of the 
lock and dam began in March 1959 and was completed 
in November 1963. 
55C. JIM WOODRUFF LOCK AND DAM, 
GA AND FL 
Location. The project is located on the Apalachicola 
River 107.6 miles above its mouth, about 1,000 feet 
below confluence of the Chattahoochee and Flint 
Rivers, and 1.5 miles northwest of Chattahoochee, Florida. 
Reservoir extends about 46.5 miles upstream along the 
Chattahoochee River to the vicinity of Columbia, 
Alabama, and about 47 miles upstream along Flint 
River, or 17 miles above Bainbridge, Georgia. (See 
Geological Survey maps for southwest Georgia.) 
Existing project. The authorized project provides for 
a concrete open-crest spillway 1,634 feet long on the 
right bank, with a crest at elevation 79 feet national 
geodetic datum; a single-lift lock with usable chamber 
dimensions of 82 by 450 feet, a maximum lift of 33 feet, 
and depth over the sills of 14 feet; a gated spillway 766 
feet long with the bridge at elevation 107 feet national 
geodetic datum, or about 67 feet above the streambed 
elevation; a powerhouse with an intake section constituting 
a portion of the dam; an earth section 506 feet 
long to accommodate the switchyard and substation: 
and an overflow dike section 2,130 feet long on the left 
bank, with a crest at elevation 85. The underlying 
foundation is limestone. At the normal pool elevation of 
77, the reservoir has a total capacity of 406,160 acrefeet. 
The power installation consists of three units of 
10,000 kilowatts each, or a total of 30,000 kilowatts. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Required cooperation is being 
fulfilled. Easements for rights-of-way and spoildisposal 
areas were provided as required along the 
Apalachicola River. Adequate public terminals were 
constructed by local interests at Bainbridge, Georgia, 
on the Flint River; and at Columbia, Alabama, on the 
Chattahoochee River. Facilities are being planned for 
other localities on the project. 
Terminal facilities. A public wharf with concrete deck 
for handling general cargo, a bulk storage terminal for 
petroleum, a grain elevator, and private riverside facilities 
at Bainbridge, Georgia, on the Flint River, are 
considered adequate for existing commerce. 
Operations and results during fiscal year. New work: 
Miscellaneous costs at completed project amounted to 
$796. Maintenance: Operation and maintenance cost 
$4,910,998. Gross power generation amounted to 
207,707,000 kilowatt-hours during FY 1986, of which 
204,238,000 were delivered to Southeastern 
Power Administration. Recreational attendance at 
Lake Seminole during CY 1985 totaled 4,203,000 
recreational user days. 
Condition at end of fiscal year. Construction of the 
lock was commenced in 1947, and completed in 1957. 
The lock was opened to navigation in May 1954, and the 
pool was raised to project level in January 1957. The 
first power-generating unit was placed on-the-line on 
February 1, the second on March 1, and the third on 
April 26, 1957. 
55D. SPEWRELL BLUFF LAKE, GA 
Location. The dam site is on the Flint River in Talbot 
and Upson Counties, Georgia, about nine miles west of 
Thomaston. The lake will extend into Meriwether, 
Pike, and Spalding Counties. 
Existing project. The authorized project provides for: 
a dam 2,475 feet long with maximum height of 211.0 
feet, a 326-foot long gated spillway with six tainter gates 
38 feet high and 45 feet wide, concrete non-overflow 
abutments 1,149 feet across the main channel including 
268 feet for the power intake, with an earth-rock fill dike 
580 feet long to high ground on the left bank, a 420-foot 
saddle dike on the left bank, and a power plant with 
three 50,000-kw units located in the left bank. The 
reservoir would have an area of 13,330 acres at maximum 
power pool elevation of 695 national geodedic 
datum. Usable storage of 241,510 acre-feet would be 
provided for power generation between elevations 665 
and 695 and 195,010 acre-feet would be reserved 
between elevations 695 and 706.5 for flood storage. 
Approved estimated (1986) cost is $426,000,000, of 
which $302,920,000 is for construction and design, and 
$123,080,000 for lands, damages, and relocations. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Local interest must maintain and 
operate all utility and highway facilities which may be 
relocated or otherwise altered as part of the improve- 
10-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
ment, provide suitable public terminal facilities, and 
hold the United States free from damages. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. Construction has not 
been initiated. 
55E. WALTER F. GEORGE LOCK AND 
DAM, AL AND GA 
Location. The project is on the Chattahoochee River 
about 75.2 miles above its mouth and about 1.5 miles 
above Fort Gaines, Georgia. (See Geological Survey 
maps for southwest Georgia.) 
Existing project. The authorized project provides for 
a concrete dam, gated spillway, and single-lift lock, with 
earth embankments at either side. The non-overflow 
section of the dam includes a powerhouse and an intake 
structure. The gated spillway is 708 feet long with a fixed 
crest at elevation 163 feet national geodetic datum. The 
two earth embankments, of almost equal lengths, have a 
total length of 12,128 feet, with a crest elevation at 215, 
and a maximum height of about 68 feet. The nonoverflow 
section of the concrete dam is 200 feet long, 
with the deck of the powerhouse section at elevation 
208. The lock, with usable chamber dimensions of 82 
feet by 450 feet, has a lift of 88 feet with the normal 
upper pool elevation at 190. Depths are 13 feet over the 
lower sill and 18 feet over the upper sill at normal pool 
elevation. The underlying foundation is limestone. 
Total reservoir capacity is 934,400 acre-feet, with 244,400 
acre-feet reserved for power. The power installation 
consists of four units of 32,500 kilowatts each, or a total 
of 130,000 kilowatts. The project provides for maintenance, 
including operation and care. The approved 
(1986) estimate for rehabilitation work to control 
seepage is $14,500,000. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Local interests must maintain and 
operate all utility and highway facilities which may be 
relocated or otherwise altered as part of the improvement, 
provide suitable public terminal facilities, and 
hold the United States free from damages. Local 
agencies and other organizations have indicated their 
willingness and ability to comply. 
Terminal facilities. Public wharves at Eufaula and 
Phenix City, Alabama, and Columbus, Georgia, are 
considered adequate for existing commerce. 
Operations and results during fiscal year. New work: 
Continuing work on construction of cutoff wall under 
dam to correct seepage cost $468,153. Minor administrative 
costs totaled $7. Maintenance of the project for 
operation and care was $7,347,633. Gross power generation 
amounted to 249,542,000 kilowatt-hours during 
FY 1986, of which 243,272,000 were delivered to Southeastern 
Power Administration. Recreational attendance 
during CY 1985 totaled 7,327,247 recreational user 
days. 
Condition at end of fiscal year. Construction was 
completed in 1963. The lock was opened to navigation 
in June 1963. The first power generating unit was placed 
on-the-line in March, the second in May, the third in 
September, and the fourth in November 1963. 
55F. WEST POINT LAKE, 
CHATTAHOOCHEE RIVER BASIN, 
GA AND AL 
Location. The damsite is on the Chattahoochee River 
2.8 miles upstream from West Point, Georgia, 201.4 
miles above the mouth of the Chattahoochee River, and 
309.2 miles above the mouth of the Apalachicola River. 
At the full power pool elevation of 635 feet above 
national geodetic datum, the reservoir would lie in 
Troup and Heard Counties, Georgia, and in Chambers 
and Randolph Counties, Alabama (See Geological 
Survey maps of Georgia and Alabama.) 
Existing project. The authorized project provides for 
flood control, power, recreation, fish and wildlife 
development, and streamflow regulation for downstream 
navigation. The project provides for a gravitytype 
concrete dam 896 feet long with earth embankments 
at either end 1,111 feet long on the east end and 
5,243 feet long on the west end. The total length of the 
dam and spillway is 7,250 feet. The main dam consists of 
a concrete non-overflow section, 185 feet long on the 
west side and an earth embankment retaining wall on 
the east side; a gravity concrete spillway 390 feet long, 
including piers and abutments, with six tainter gates, 
each 50 feet by 41 feet. A monolith intake-powerhouse 
section and erection bay 321 feet long is constructed 
directly west and adjacent to the spillway. At the full 
power-pool elevation of 635 the reservoir provides a 
total storage of 605,000 acre-feet of which 307,000 acrefeet 
is usable. During the critical flood season the 
reservoir is operated with maximum power pool elevation 
at 625 feet to provide flood storage between 
elevations 625 and 635. The initial power installation of 
73,375 kilowatts consisting of units 1, 2 and 3 were 
placed on operation in March and April, 1975. The 
ultimate installation is 108,375 kilowatts. (See Table 
10-B for authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. New work: 
Miscellaneous costs totaled $1,432. 
Maintenance: Operation and care of the project cost 
$5,288,528. Gross power generation amounted to 
104,630,000 kilowatt-hours during FY 1986 of which 
100,449,200 were delivered to Southeastern Power 
Administration. Recreational attendance during CY 
1985 totaled 6,399,300 recreational user days. 
Condition at end of fiscal year. Construction of the 
project, which was initiated in June 1966, was essentially 
complete at the end of FY 1984. 
56. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Mobile District monitors flood control operations of 
10-24

MOBILE, ALABAMA DISTRICT 
Alabama Power Company's Weiss, H. Neely Henry, 
and Logan Martin Dams on Coosa River, Alabama, 
and their Lewis Smith Dam on Sipsey Fork (headwaters 
of Black Warrior River, Alabama), for compliance with 
regulation plans prepared in accordance with Public 
Law 436, 83rd Congress, and Federal Power Commission 
licenses. Fiscal year cost for these activities on the 
Weiss, H. Neely Henry, and Logan Martin Dams are 
included under operation and maintenance costs for the 
Alabama-Coosa Rivers. Fiscal year cost for the Lewis 
Smith Dam is included under the overall operation and 
maintenance costs for the Black Warrior-Tombigbee 
Rivers System.
General Investigations 
57. SURVEYS 
Fiscal year cost was $1,263,602 of which $573,209 was 
for navigation studies; $298,263 for flood damage 
prevention studies; $130,897 for special studies; $15 for 
review of authorized projects; $28,297 for special investigations; 
$25,447 for coordination with the Federal Energy 
Regulatory Commission; $1,140 for coordination with 
other agencies and non-Federal interests; $206,334 for 
supplemental pre-authorization studies: Dalton, GA 
and Edinburg Lake, MS. 
Continuation of planning and engineering included 
$487,983 for Mobile Harbor; $1,153,859 for Oliver 
Lock and Dam; $29,906 for Panama City Beaches; 
$256,143 for Sowashee Creek; $36,500 for Three Mile 
Creek; and $5,575 for Village Creek; for a total of 
$1,969,966. Advance engineering and design includes 
$6,521 for Gulfport Harbor and $11,543 for the 
Montgomery to Gadsden Coosa River navigation 
channel for a total of $18,064. Contributed funds 
required for an authorized Federal project in Bayou La 
Batre, AL totaled $30,860. 
58. COLLECTION AND STUDY OF 
BASIC DATA 
Collection and study of basic data continued during 
the fiscal year with the initiation of Flood Insurance 
studies, the cost of which was reimbursable by FEMA. 
In addition, Flood Plain Management services were 
performed at a cost of $230,988. (See Table 10-P for 
listings of studies completed during FY 1986.) For 
listing of previous reports see page 10-50 Annual Report 
for 1974, page 10-44 of FY 1975 Annual Report, page 
10-46 of FY 1977 Annual Report, and page 10-48 of FY 
1978 Annual Report, and page 10-43 of 1983 Annual 
Report. 
The National Program for inspection of non-Federal 
dams cost $1,102. 
10-25

TABLE 10-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
1. ADalachicola Bay New Work: 
FL 
2. Aquatic Plant 
Control 
(Regular Funds) 
(Contributed Funds) 
3. Bayou Coden, AL 
(Contributed Funds) 
(Contributed Funds) 
4. Bayou La Batre, AL 
(Regular Funds) 
(Contributed Funds) 
5. Biloxi Harbor, MS 
(Contributed Funds) 
(Contributed Funds) 
6. Biloxi Harbor, 
East Harrison 
County Canal, MS 
7. Black Warrior & 
Tombigbee Rivers, 
AL 
8. Bon Secour River, 
AL 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
32,000 
55,370 
44,000 
-3,884 
25,000 
15,357 
4,000 
753,896 
52,000 
50,089 
704,505 
195,823 
455,000 
455,263 
5,000 
41,048 
75,000 
96,785 
220,000 
224,570 
501,000 
514,885 
3,605,000 
153,586 
85,000 
77,296 
60,000 
41,082 
25,000 
22,778 
24,000 
22,460 
165,000 
151,489 
61,300 
35,225 
35,000 
1,797,450 
14,137,473 15,962,000 14,087,000 
13,862,619 16,904,377 13,553,608 
19 
17,891 
10,000 
16,632 
895 
20,000 
22,452 
683,000 
689,170 
27,000 
36,475
- 2,033,461' 
- 2,033,461' 
3,587,8072 
3,585,3792 
549,687 
528,163 
21,225 
21,225 
330,7013 
330,7013 
322,000 731,533 
325,982 730,391 
- 100,000 
- 100,000 
- 50,000 
- 50,000 
- 311,095 
- 311,095 
326,000 
326,248 
2,001,0( 
2,014,13 
166,53 
166,53 
140,00 
145,49 
3,016,852 
3,015,322 
10,5004 
10,5004 
- 1,215,4365 
- 1,215,4365 
)0 7,690,1066 
30 7,689,1776 
- 102,600 
- 102,600 
36 166,536 
5 166,535 
)0 201,300 
)0 180,715 
2,850,000 11l2,878,9427 
2,102,535 110,526,7557 
8,424,000 178,200,6768 
9,317,927 178,006,6068 
-62,000 48,065,300 
482 47,258,651 
- 118,615 
- 118,615 
23,000 198,478 
26,531 197,569 
10-26

MOBILE, ALABAMA DISTRICT 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
(Contributed Funds) New Work: 
Approp: 
Cost 
9. Dauphin Island, New Work: 
Bay, AL Approp. 
Cost 
Maint: 
Approp. 
Cost 
10. Dog and Fowl New Work: 
Rivers, AL Approp. 
(Regular Funds) Cost 
Maint: 
Approp. 
Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
II. East Pass Channel New Work: 
From Gulf of Approp. 
Mexico into Chocta- Cost 
whatchee Bay, FL 
(Regular Funds) Maint: 
Approp. 
Cost 
(Contributed Funds) New Work: 
Approp. 
Cost 
12. Fly Creek, AL New Work: 
Approp. 
Cost 
13. Gulf Intracoastal 
Waterway between 
Apalachee Bay, FL 
and Mexican Border 
- 9,700 
- 9,700 
- 292,864 
- 292,864 
38,000 
66,153 
-32,000 
16,930 
96,000 
93.672 
2,037 
36,000 
39.417 
191,000 
187,526 
2,200 
163,000 
165.309 
- 217,000 
- 124,622 
922,000 
925,433 
81,150 
55,893 
1,315,026 
1,313,941 
407,695 
315,317 
1,805,593 
1,804,738 
197,450 
169,993 
- 916,715 
- 916,715 
625,000 
606,764 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
14. Mobile Harbor, AL New Work: 
Approp. 
Cost 
(Contributed Funds) New Work: 
Approp. 
Cost 
(Regular Funds) 
(Contributed Funds) 
15. Panama City 
Harbor, FL 
(Contributed Funds) 
Maint: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
626,000 
610,614 
- 109,000 
- 106,550 
2,914,000 
1,400,841 
84,000 
723,834 
280,000 
553,146 
4,793,000 
2,941,782 
-8,000 
343,829 
3,009,000 
4,536,371 
31,404 
485,000 
717,401 
2,908,700 
5,172,873 
761,000 
761,668 
695,000 
627,559 
15,000 
2,835 
5,141,000 
5,175,525 
15,000 
19,448 
4,805,000 
4,819,696 
805,000 
834,706 
435,000 
431,355 
588,000 6,969,160 
768,130 6,968,955 
- 398,000 
- 398,000 
- 29,000 
- 29,000 
1,000 323,621 
15,356 323,362 
- 6,480,2999 
- 6,480,2999 
3,502,000 45,228,722' � 
3.515.992 45.219.82810 
130,00 
89,27 
2,685,00 
1,968,03 
8,646,00 
8,796,67 
617,00 
620,88
)0 68,247,937's 
5 68,190,759" 
)0 7,017,500 
9 6,133,008 
0 82,526,183'14 
2 82,468,723'14 
- 817,000 
- 846,706 
- 1,638,045's 
- 1,638,045's 
)0 7,087,33416 
7 7,086,88216 
- 80,000 
- 80,000 
10-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
16. Pascagoula Harbor, 
MS 
(Regular Funds) 
(Contributed Funds) 
17. Pensacola Harbor, 
FL 
18. Perdido Pass 
Channel, AL 
(Regular Funds) 
(Contributed Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint: 
Contrib. 
Cost 
19. Waterway Con- New Work: 
necting Tombigbee Approp. 
and Tennessee Rivers Cost 
AL, and MS Maint: 
Approp. 
Cost 
26. Okatibbee Lake, New Work: 
MS Approp. 
Cost 
27. Tallahala Creek 
Lake, Pascagoula 
River, MS 
28. Airport Road 
Bridge, 
Frankstown, MS 
29. Big Brown Creek, 
Prentiss County, 
MS 
30. Boligee Canal, 
Boligee, AL 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
4,143,000 
1,986,816 
196,590 
565 
2,066,000 
4,587,968 
300,000 
496,024 
3,127,000 
3,150,431 
770,028 
735,831 
- 6,572,985' 
- 6,572,985' 
3,154,000 36,141,420' s 
3,162,738 36,133,37418 
75,456 
75,456 
1,811,424 
1,756;426 
- 1,469,693'9 
- 1,469,69319 
42,145 
2,032,000 
1,967,593 
68,000 
145,898 
19,000 
20,328 
6,177,23820 
6,176,2712o 
- 629,860 
- 629,860 
1,271,000 
484,340 
-62,000 
743,601 
60,000 
51,595 
936,000 
944,695 
5,948,217 
5,947,424 
- 510,000 
- 510,000 
- 10,325 
- 10,325 
120,684,000 
103,645,625 
5,474,000 
5,430,959 
20,000 
22,505 
874,000 
825,795 
60,967 
155,107,000 
88,011,301 
7,456,000 
7,447,345 
620,000 
86,839 
1,008,000 
1,184,145 
1,809 
- 221,300 
- 19,691 
-19,750,000 
43,785,515 
10,291,000 
11,170,456 
-100 
421,348 
859,000 
813,827 
593 
-5,440 
195,665 
26,496,000 
24,174,109 
13,159,425 
13,171,967 
119,906 
793,000 
877,052 
3,931 
1,000,278,20021 
973,242,11521 
47,682,75622 
47,298,633 22 
9,739,528 
9,739,172 
8,287,892 
8,272,618 
3,945,757 
3,926,626 
- 215,860 
504 215,860 
- 52,500 
- 26,46 I1 
- 163,600 
- 162,554 
31. Chattahoochee New Work: 
River, Eufaula, AL Approp. 
Cost 
32. County Road Bridge,New Work: 
Mahned, MS Approp. 
Cost 
33. Goodfood Creek, New Work: 
Chickasaw Co., MS Approp. 
Cost 
52,500 
14,165 
52,500 
26,461 
163,600 
162,554 
52,500 
14,165 
- 231,618 
- 231,618 
37,500 
22,699 
37,500 
22,699 
10-28

MOBILE, ALABAMA DISTRICT 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
34. Hwy. 39 Bridge, 
Gainesville, AL 
35. Houston School Rd. 
Bridge, Itawamba 
Co., MS 
36. Leaf and Bowie 
Rivers, Hattiesburg, 
MS 
37. Martin Creek, 
Prentiss County, 
MS 
38. Murder Creek, 
East Brewton, AL 
39. Murder and Burnt 
Corn Creeks, 
Brewton, AL 
40. Noxubee River 
Relief Bridge, 
Shuqualak, MS 
41. Sewerline Protection 
Valley, AL 
42. Sope Creek, 
Marietta, GA 
43. Tallabinella Creek 
Chickasaw County, 
MS 
44. Tombigbee River 
(East Fork)., 
MS & AL 
45. Tombigbee River 
Tributaries, 
MS and AL 
(Regular Funds) 
(Contributed Funds) 
46. U.S. Hwy 11 
Bridge, Fosters, 
AL 
47. Wolf Creek, U.S. 
Hwy 45 Bridge, 
Prentiss Co., MS 
48. Old Hwy 82 
Bridge, Columbus, 
MS 
49. Interstate 59 
Bridges, Fosters, 
AL 
53. Alabama-Coosa 
Rivers. AL and GA 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
- 50,000 
- 1,254 
- 42,300 
- 20,738 
- 1,340,000 
- 1,067,472 
- 32,500 
- 14,644 
542,500 
404,471 
-35,000 
108,490 
-5,000 
-3,91 1 
50,000 
1,254 
42,300 
20,738 
1,340,000 
1,067,472 
32,500 
14,644 
- 903,474 
530 903,474 
- 550,000 
- 234,624 
27,500 
10,341 
- 310,00 
- 9,92 
227,000 
71,996 
1,495,000 
1,289,170 
312,00 
463,70 
1,400,0(0 
2,494,13 
14,00 
13,16 
14,543 
- 185,000 
- 17,387 
)0 1.110,000 
1 833,383 
)0 449,000 
1 452,213 
)0 2,000,000 
36 985,330 
0
5 
25,00 
6,42 
150,48 
-20,00 
314,85 
35,00 
22,90 
153,00 
164,09 
2,297,00 
3,297,21 
364 
- 210,000 
- 18,829 
215,000 
15,430 
27,500 
18,564 
-15,00 
170,24 
-60,359 
138,706 
135,000 
35,117 
- 160,000 
- 15,179 
514,522 
474,340 
100,000 
608,670 84,476 
550,000 
234,624 
52,500 
31,313 
)0 
'9 
- 185,000 
2 167,869 
)0 1,400,000 
4 1,158,158 
)0 35,000 
10 22,900 
- 134,801 
- 134,801 
)0 2,380,100 
8 2,378,094 
)0 18,606,225 
4 18,222,988 
- 94,700 
- 63,281 
)0 195,000 
5 189,074 
- 154,641 
505 154,641 
84,286 
-17,500 
I19,039 
162,500 
137,967 
142,500 
134,218 
-293,000 309,497,63023 
46,180 309,445,8372; 
9,775,000 1 1,74 1,500 11,224,006 9,346,000 110,643,96024 
9,034,561 13,176,904 10,795,482 10,018,072 110,267,2232' 4 
10-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
53A. Carters Dam and 
Reservoir, GA 
53B. Claiborne Lock and 
Dam, AL 
53C. Robert F. Henry 
Lock and Dam, AL 
53D. Millers Ferry Lock 
and Dam, AL 
53E. Coosa River, 
Montgomery to 
Gadsden, AL 
54. Allatoona Lake, 
Coosa River Basin, 
GA 
55. Apalachicola, 
Chattahoochee, 
and Flint Rivers, 
AL and GA 
55A. Lake Sidney 
Lanier, GA 
55B. George W. Andrews 
Lock and Dam, 
AL and GA 
55C. Jim Woodruff Lock 
and Dam, GA and 
FL 
55D. Spewrell Bluff Lake 
GA 
-84,000 
43,083 312 
2,235,000 2,522,500 
1,952,950 2,806,966 
- -106,000 111,140,340 
- 866 111,140,340 
2,321,000 
2,361,379 
2,361,600 21,390,900 
2,507,840 21,351,139 
- 27,997,450 
- 27,997,450 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
-300,000 
239,173 
1,755,000 
1,994,862 
400,000 
306,625 
3,450,000 
3,774,011 
62,560 
70,000 
169,716 
4,776,000 
5,666,044 
1,702,000 
1,959,105 
12,150 
1,759,000 
1,776,575 
51,806 
2,499,000 
2,544,735 
20,520 
-7,000 
65,389 
5,149,000 
4,816,217 
-1,500 
28,177 
-187,000 83,360,800 
793 83,360,800 
1,858,000 16,937,778 
1,858,604 16,830,392 
- 63,125,300 
38,776 63,122,507 
2,360,000 28,960,965 
2,392,094 28,826,801 
- 15,035,400 
5,745 14,986,400 
- 35,709,08525 
7,671 35,709,08425 
5,278,000 53,089,523 
5,746,764 52,834,117 
- 339,094,09326 
196 338,993,34226 
600,000 
164,544 
1,891,000 
1,843,208 
-1,478 
22,500 
2,302,000 
2,364,854 
244,213 
201,000 
668,140 
4,298,000 
3,996,293 
208,973 
923,386 
19,006,000 
18,162,136 
4,800,000 
1,234,848 
155,782 
471,532 
5,078,500 
4,553,188 
6,400,000 
4,439,449 
3,000 
166,190 
5,342,000 
6,298,978 
4,105,313 
-1,500 
10,398 
6,948,000 
6,879,884
30 
30 
30 
30 
-1,500 
40,247 
3,062,000 
3,205,787 
-1,000 
292 3,505 
3,810,000 4,119,000 
4,057,310 4,154,005 
- -10,948 
-700,000 10,500,000 
468,153 10,247,763 
- 53,030,03828 
-2,038 53,035,37828 
7,152,000 62,843,907 
7,328,659 62,612,828 
- 13,038,42729 
- 13,038,42729 
30 
30 
- 48,017,85831 
796 47,978,749~3' 
4,768,000 50,252,081 
4,910,998 50,119,171 
- 2,158,652 
- 2,158,652 
10-30
22,362,000 26,743,000 27,337,000 275,132,36427 
24,142,063 26,228,528 28,785,527 274,205,51827

MOBILE, ALABAMA DISTRICT 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
iSne cTteioxnt Project Total Cost to Funding FY83 FY84 FY85 FY86 Sept. 30, 1986 
55E. Walter F. George New Work: 
Lock and Dam, Approp. 54,691 - - - 88,295,77932 
AL and GA Cost 402,094 8,483 14,274 7 88,295,78032 
Maint: 
Approp. 3,583,000 4,620,000 5,779,000 7,063,000 62,169,564 
Cost 3,561,801 4,544,659 5,947,570 7,347,633 61,968,123 
Major Rehab: 
Approp. 4,800,000 6,400,000 - -700,000 10,500,000 
Cost 1,234,848 4,439,449 4,105,313 468,153 10,247,763 
55F. West Point Lake, New Work: 
Chattahoochee River Approp. - 1,700,000 10,948 - 131,557,359 
Basin, GA and AL Cost 9,513 1,784,140 - 1,432 131,501,360 
Maint: 
Approp. 3,040,500 3,103,000 3,934,000 5,266,000 29,631,300 
Cost 2,952,188 3,130,304 3,958,108 5,288,528 29,366,463 
1. Includes $134,613 for previous projects and $28,500 for DPR 
on Two-Mile. 
2. Includes $168,766 for previous projects. 
3. Includes $5,650 for previous projects. 
4. Cost for providing spoil dikes for work authorized by 1965 
River and Harbor Act. 
5. Includes $44,382 for previous projects of which $5,000 was 
contributed funds. 
6. Includes $96,509 for previous projects of which $10,200 was 
contributed funds. 
7. Includes $606,931 for previous projects and $1,046,679 for 
recreational facilities on completed projects. 
8. Includes $50,000 for previous projects. 
9. Includes $45,605 for previous projects. 
10. Includes $65,137 for previous projects. 
I11. Includes $269,017 for previous projects. 
12. Includes 2,312,297 for previous projects and $442,836 Special 
O and M funds. 
13. Includes $6,683,104 for previous projects, $14,000 Public 
Work funds, and $41,242 Emergency Relief funds. 
14. Includes $4,096,681 for previous projects and $494,136 Special 
O and M funds. 
15. Includes $203,560 for previous projects, $581,959 Public 
Works funds, $457,467 rehabilitation of jetties under existing 
project and $48,001 for Grand Lagoon modification. 
16. Includes $513,604 for previous projects. 
17. Includes $904,442 for previous projects. 
18. Includes $412,624 for previous projects, $124,565 Special O 
and M funds, and $829,472 Emergency Work Funds. 
19. Includes $594,688 for previous projects. 
20. Includes $126,649 for previous projects. 
21. Includes $1,993,000 transferred to National Park Service; 
$210,249 GI funds expended during FY 1957 thru FY 1961. Previous 
project cost amounted to $197,651. 
22. Includes $234,331 for previous projects. 
23. Includes $3,692,483 for previous projects. 
24. Includes $2,978,050 for previous projects. 
25. Includes $3,347,489 for recreational facilities. 
26. Includes $1,883,193 Federal funds, $1,924 contributed funds 
for previous projects; and $809,553 for Lazer Creek design and 
$301,310 for Rysco Channel. 
27. Includes $2,246,233 for previous projects. 
28. Includes $8,231,284 for recreational facilities. 
29. Includes $84,014 for recreational facilities. 
30. Included under maintenance for overall Apalachicola, Chattahoochee 
and Flint Rivers project. 
31. Includes $1,515,822 for recreational facilities. 
32. Includes $2,441,029 for recreational facilities. 
10-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 10-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1907 
Jan. 21, 1927 
Sept. 3, 1954 
Sept. 3, 1954 
July 3, 1958 
Nov. 21, 1963' 
Feb. 5, 1975' 
Aug. I111,9 83' 
July 3, 1958 
Oct. 23, 1962 
Oct. 27, 1965 
Mar. 2, 1945 
June 2, 1969' 
Oct. 27. 1965 
APALACHICOLA BAY, FL. (See Section I of Text) 
Channel 18 feet deep through West Pass and Link Channels, 
10 feet deep across the inner bar, and 9 feet deep 
through Bulkhead Shoals. 
Modify project to provide for channel 10 feet deep from 
mouth of inner bar channel to Gulf via Link and West 
Pass Channels, and 10-foot depth in Bulkhead Shoals 
Channel. 
At Eastpoint, Fl., a channel 6 feet deep, 100 feet wide, 
and about 6,000 feet long, parallel to shore, with 
connecting channel 6 feet deep and 100 feet wide to St. 
George Sound, and at Apalachicola, Fl., a small-boat 
basin 200 feet and 9 feet deep, with a connecting 
channel 9 feet deep and 80 feet wide through Scipio 
Creek to the Apalachicola River. 
Modify project to provide for a channel 10 feet deep and 
100 feet wide from the 10-foot depth in Apalachicola 
Bay across St. George Island to within 300 feet of the 
Gulf shore, thence increasing uniformly in width to 200 
feet at shore and continuing at this width to the 10-foot 
depth in the Gulf, with two jetties extending from the 
dune line on St. George Island to the outer end of 
channel, and for abandonment of West Pass Channel upon 
completion of channel through St. George Island. 
Modify improvement of Apalachicola Bay, Fl., authorized 
by River and Harbor Act of Sept. 3, 1954 to provide 
that the Secretary of the Army shall reimburse local 
interests for such approved work as they may have done 
based upon the reduction in the amount of material 
which will have to be removed to provide project 
dimensions at such time as Federal dredging of the 
channels is undertaken. 
A channel 6 feet deep, 100 feet wide and about I mile long, 
parallel to shore at Two Mile, Fl., with a 6-by 100-foot 
connecting channel to water of the same depth in 
Apalachicola Bay. 
A channel 6 feet deep and 100 feet wide extending from the 
eastern end of the existing Two Mile channel and 
generally paralleling the shoreline for a distance of 
about 9,000 feet to intersect with the Gulf Intracoastal 
Waterway about 1,650 feet south of Gorrie Bridge at 
Apalachicola, and a breakwater built to elevation 4.0 
feet above mean low water along the seaward side of the 
existing channel parallel to the shore at Two Mile. The 
total length of the breakwater of about 6,150 feet, 
includes two 860-foot legs paralleling the existing 
entrance channel. 
Modify Eastpoint project to include breakwaters with a 
total length of 5,300 feet. 
AQUATIC PLANT CONTROL (See Section 2 of Text) 
Aquatic plant control for N.C., S.C., Ga., Fl., Al., Ms., 
and La. 
Research and planning costs to be borne by U.S. 
Provided for continued research. 
BAYOU CODEN, AL. (See Section 3 of Text) 
Channel 4 by 40 feet. 
Channel 8 by 60 feet to connect with Bayou La Batre 
channel. 
BAYOU LA BATRE, AL. (See Section 4 of Text) 
A 12- by 100-foot channel from that depth in Mississippi 
Sound to a point about 2,800 feet south of the highway 
H. Doc. 422, 59th Cong., 
1st Sess. 
H. Doc. 106, 69th Cong., 
Ist Sess. 
H. Doc. 156, 82d Cong., 
Ist Sess. 
H. Doc. 557, 82d Cong., 
2d Sess. 
DPR(Sec. 107) 
DPR(Sec. 107) 
DPR(Sec. 107) 
H. Doc. 37, 85th Cong., 
1st Sess. 
Public Law 87-874 
87th Cong. 
H. Doc. 251, 89th Cong., 
Ist Sess. 
H. Doc. 824, 77th Cong., 
2d Sess. 
DPR (Sec. 107) 
H. Doc. 327, 88th Cong., 
2d Sess. 
10-32

MOBILE, ALABAMA DISTRICT 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1930 
June 20, 1938 
Mar. 2, 1945 
Mar. 2, 1945 
May 17, 1950 
July 14, 1960 
Nov. 7, 1966 
Mar. 28, 1979' 
August 8, 1985' 
July 5, 1884 
Mar. 3, 1899 
Sept. 19, 1890 
Sept. 19, 1890 
Mar. 2, 1907 
Mar. 3, 1909 
bridge, thence a channel 12 by 75 feet to the bridge, an 
overall distance of about 33,500 feet. 
BILOXI HARBOR, MS. (See Section 5 of Text) 
Channel 10 feet deep and 150 feet wide from Mississippi 
Sound west and north of Deer Island to deep water in 
Back Bay of Biloxi. 
Relocation of channel. 
Entrance channel 6 feet deep and 50 feet wide into Old 
Fort Bayou. 
Entrance channel 8 feet deep and 100 feet wide through 
Cranes Neck into Bayou Bernard. 
Maintain channel 6 feet deep and 40 feet wide from Biloxi 
Harbor to Ott Bayou. 
Continuous channel 12 feet deep from Mississippi Sound 
the Air Force terminal on Bayou Bernard via Back Bay 
and Cranes Neck. 
A 23-mile-long through channel 12 feet deep and 150 feet 
wide from the Gulf Intracoastal Waterway through: 
Mississippi Sound, Biloxi Bay (east of Deer Island), Back 
Bay, Big Lake, and via land cut to Gulfport Lake, 
including a 500- by 2,600-foot turning basin in the lake, 
thence, a channel 12 by 100 feet from the western end of 
Gulfport Lake for about 2 miles to a 300- by 500-foot 
turning basin; adoption for maintenance of a 12- by 150- 
foot spur channel from the main channel in Biloxi Bay, 
westward about I mile to a 400- by 600-foot turning basin 
opposite Ott Bayou, and abandonment of the existing 6- by 
40-foot channel into Ott Bayou; continuation of maintenance 
of the 12- by 150-foot lateral channel westward about 2.2 
miles from the main channel in Biloxi Bay to a point 
opposite Oak Street; continuation of maintenance of the 
channel west of Deer Island. 
A channel 10 feet deep; 100 feet wide and 300 feet 
long extending northward from the Biloxi Lateral Channel, 
and, into a rectangular basin approximately 300 feet 
by 370 feet. 
BILOXI HARBOR, EAST HARRISON COUNTY CANAL, MS 
(See Section 6 of Text) 
The project provides for the improvement and 
maintenance of the East Harrison County Canal. 
BLACK WARRIOR AND TOMBIGBEE RIVERS, AL. 
(See Section 7 of Text) 
Original appropriation for improving Black Warrior River. 
Original project for slack-water improvement authorized by 
Secretary of War, Apr. 19, 1887. 
Construction of the first locks between Tuscaloosa and 
Demopolis. 
(Maintenance of the section of Tombigbee River below 
lock 1 to its mouth (66 miles) included in the existing 
project.) 
Construction of locks and dams 1, 2, and 3. Merging of 
the individual project for the Black Warrior and Warrior 
Rivers and the Tombigbee River below Demopolis. 
Construction of locks and dams 14, 15, 16, and 17. 
Provides for reconstruction of obsolete structures, modified 
in plan and location, to provide efficient and economical 
maintenance and operation. 
H. Doc. 754, 69th Cong., 
2d Sess. 
H. Doc. 639, 75th Cong., 
3d Sess. 
H. Doc. 258, 76th Cong., 
Ist Sess. 
H. Doc. 326, 76th Cong., 
1st Sess. 
H. Doc. 256, 81st Cong., 
1st Sess. 
H. Doc. 271, 86th Cong., 
2d Sess. 
H. Doc. 513, 89th Cong., 
2d Sess. 
DPR (Sec. 107) 
DPR (Sec. 107) 
Annual Report, 1887, 
pt. 2, p 1302. 
H. Doc. 178, 56th Cong., 
2d Sess., and Annual 
Report, 1901, pt. 3, 
p. 1858 
H. Doc. 165, 57th Cong., 
Ist Sess., and Annual 
Report, 1902, p. 1293 
Public Law 317 
10-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 22, 1911 
Mar. 2, 1919 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
June 26, 1934 
Dec. 22, 1944 
Mar. 2, 1945 
Mar. 2, 1945 
July 14, 1960 
Dec. 21, 1982 
July 30, 1983 
Aug. 15, 1985 
May 16, 1963' 
Mar. 2, 1945 
Sept. 3, 1954 
May 19, 1969' 
July 3, 1930 
Lift of lock 17 changed to 63 feet, and construction of locks 
and dams 18 and 19 eliminated from the project. 
Extension of slack-water improvement to Sanders Ferry 
on Mulberry Fork and Nichols Shoal on Locust Fork. 
Raising of various dams 2 feet and raising the lock walls 2 
feet at lock 1 to provide a minimum depth of 8 feet at 
low water, widening the channel to 150 feet where 
practicable. 
For snagging Mobile River from the mouth of Chickasaw 
Creek to the junction of the Alabama and Tombigbee 
Rivers. 
Increase channel dimensions to 9 by 200 feet; construct 
crest gates at lock and dam 17; add flashboards at all 
dams; Sunflower Bend Cutoff. 
Construction of a lock and dam below Tuscaloosa to replace 
original locks and dams 10, 11, and 12 
Operation and care of locks and dams provided for with 
funds from War Department appropriations for rivers 
and harbors. 
Recreation facilities. 
Construction of a lock and dam near Demopolis to replace 
existing dams 4, 5, 6, and 7. 
Provide increased spillway capacity at dam 1. 
Coffeeville Lock and Dam Wildlife Refuge. 
Provides for a wider navigation opening at the Franklin 
Ferry Bridge, Jefferson County, Al. 
Authorized to widen, as necessary for safe passage, 
the navigation opening of Franklin Ferry Bridge, Jefferson County, Al. 
Construction and land acquisition for Oliver Lock 
Replacement. 
BON SECOUR RIVER, AL. (See Section 8 of Text) 
A 10- by 100-foot channel from Gulf Intracoastal 
Waterway through Bon Secour Bay to mouth of Bon Secour 
River and extending up river to vicinity of Swift's 
Landing, thence 6 by 80 feet up river to a point 
600 feet above Oak Landing, with two turning and 
maneuvering areas 150 feet wide and 1,100 to 1,200 
feet long opposite Swift'Landing and ice loading 
dock. Overall length of improvement is about 4.7 
miles. 
DAUPHIN ISLAND BAY, AL. (See Section 9 of Text) 
A channel 7 feet deep and 150 feet wide from Mobile Bay to 
an anchorage basin of same depth, about 7 acres in area, in 
marsh just north.of Fort Gaines on Dauphin Island; a 
channel 4 feet deep and 40 feet wide from anchorage basin 
to Dauphin Islanid Bay; and a jetty and revetment to protect 
entrance channel; and (b) an anchorage basin 7 feet deep 
and 500 feet square at Dauphin Island Village, with 
an entrance channel of like depth, 100 feet wide and 
about 8,300 feet long, extending to 7-foot hydrographic 
contour in Mississippi Sound. 
DOG AND FOWL RIVERS, AL. (See Section 10 of Text) 
To provide small craft navigation on west side of Mobile Bay. 
EAST PASS CHANNEL FROM GULF OF MEXICO INTO 
CHOCTAWHATCHEE BAY, FL. (See Section 11 of Text) 
Maintenance of 6-foot channel by 100-foot channel from 
Choctawhatchee Bay into Gulf. 
H. Doc. 72, 62d Cong., 
1st Sess. 
Annual Report, 1918, 
p. 876 
H. Doc. 728, 71st Cong., 
3d Sess. 
H. Doc. 56, 73d Cong., 
1st Sess., and Rivers 
and Harbors Committee 
Doc.45, 73d Cong. 
Rivers and Harbors 
Committee Doc. 26, 
74th Cong., Ist Sess. 
H. Doc. 276, 76th Cong., 
Ist Sess. 
H. Doc. 382, 76th Cong., 
Ist Sess. 
S. Doc. 50, 86th Cong., 
Ist Sess. 
Public Law 97-377 
Public Law 98-63 
The Energy and Water 
Development Appropriation 
Act 1985 (P.L. 99-88) 
DPR (Sec. 107) 
H. Doc. 333, 76th Cong., 
Ist Sess. 
H. Doc. 394, 82d Cong., 
2d Sess. 
DPR (Sec. 107) 
H. Doc. 209, 70th Congress 
1st Sess. 
10-34

MOBILE, ALABAMA DISTRICT 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 24, 1951 
Oct. 27, 1965 
Oct. 1, 1980 
May 17, 1950 
Aug. 26, 1937 
June 25, 1910 
Aug. 30, 1935 
June 25, 1910 
Aug. 30, 1935 
July 3, 1930 
July 3, 1930 
July 3, 1930 
July 23, 1942 
June 17, 1943 
Mar. 2, 1945 
May 17, 1950 
Nov. 7, 1966 
Maintenance of 12-foot channel from Choctawhatchee Bay 
into Gulf, and maintenance of 6-foot channel into Old 
Pass Lagoon. 
Construction of twin jetties. 
(Present project dimensions.) 
Modifications to provide a channel length of 
approximately 3,800 feet in lieu of 2,000 feet from 
the East Pass Channel into Old Pass Lagoon, with 
no changes in width and depth. 
FLY CREEK, FAIRHOPE, AL (See Section 12 of Text) 
A channel 6 feet deep, 80 feet wide, and about 1,650 
feet long from 6-foot depth in Mobile Bay to a turning 
basin of same depth, 100 feet wide and 350 feet long, in Fly Creek. 
GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FL., AND MEXICAN BORDER 
(Mobile District) (See Section 13 of Text) 
APALACHICOLA BAY TO ST. MARKS RIVER, FL. 
A channel 9 feet deep and 100 feet wide at mean low water 
from Apalachicola Bay, Fl., via St. George Sound, 
Carrabelle, Crooked, and Ochlockonee Rivers and 
Ochlockonee and Apalachee Bays to St. Marks River, Fl. 
APALACHICOLA RIVER TO ST. ANDREW BAY, FL. 
A channel 5 feet deep at mean low water and 65 feet 
wide at the bottom. 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
CHOCTAWHATCHEE BAY TO WEST BAY, FL. 
A channel 9 feet deep at mean low water and 100 feet wide 
at the bottom. 
A channel 6 feet deep at mean low water, with no 
reference to width. 
CHOCTAWHATCHEE BAY TO PENSACOLA BAY, FL. 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
PENSACOLA BAY, FL., TO MOBILE BAY, AL. 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
MOBILE BAY, AL., TO NEW ORLEANS, LA. 
A channel 300 feet wide and 10 feet from the 10 
foot contour in Mobile Bay to the 10-foot contour 
in Mississippi Sound. 
A channel 100 feet wide and 9 feet deep from Lake 
Pontchartrain to Mississippi Sound. 
APALACHEE BAY, FL., TO NEW ORLEANS, LA. 
A channel 12 feet deep and 125 feet wide at mean low 
water, except in the section between Mobile, Al., 
and New Orleans, La., where the width is to be 
150 feet. 
Conditional acquisition of Gulf County Canal, Fl. 
and enlargement of the canal to 9 feet deep and 100 
feet wide. 
Construction of a movable span in the Georgia, Florida 
& Alabama R.R. bridge crossing the Ochlockonee River. 
Abandonment and closure of original channel between 
Big Lagoon and Pensacola Bay and construction of a 
new channel to enter the bay north of original 
entrance. 
Authorized enlargement of Gulf County Canal to 12 by 
125 feet. 
H. Doc. 470, 81st Cong., 
2d Sess. 
H. Doc. 194, 88th Cong., 
2d Sess. 
Energy and Water Development 
Appropriation 
Act, 1981 (P.L. 96-367) 
H. Doc. 194, 81st Cong., 
Ist Sess. 
H. Doc. 291, 75th Cong., 
Ist Sess. 
H. Doc. 670, 61st Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 52, 
72d Cong., 2d Sess. 
H. Doc. 259, 72d Cong., 
1st Sess. 
H. Doc. 565, 61st Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 42, 
73d Cong., 2d Sess. 
H. Doc. 42, 71st Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 4, 
71st Cong., I1st Sess. 
H. Doc. 341, 71st Cong., 
2d Sess. 
Public Law 675, 77th 
Cong., 2d Sess., and 
H. Doc. 96, 79th 
Cong., 1st Sess. 
H. Doc. 257, 76th Cong., 
1st Sess., and Public 
Law 75, 78th Cong. 
1st Sess. 
H. Doc. 442, 76th Cong., 
1st Sess. 
H. Doc. 325, 81st Cong., 
1st Sess. 
Public Law 89-789, 89th 
Cong. 2d Sess. 
10-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 26, 1937 
Mar. 2, 1945 
Sept. 3, 1954 
Sept. 3, 1954 
July 26, 1970 (SR) 
Dec. 15, 1970 (HR) 
Aug. 15, 1985 
Aug. 30, 1935 
Mar. 2, 1945 
June 30, 1948 
Mar. 23, 1967' 
June 14, 1972 
Mar. 4, 1913 
MOBILE HARBOR, AL. (See Section 14 of Text) 
For improvement of Threemile Creek by snagging from 
Mobile River to the Industrial Canal. 
Adoption of existing channel through Garrows Bend from 
Choctaw Point to Arlington pier, 27 feet deep and 150 
feet wide, with 2 turning basins. Adoption of the 
existing channel alongside Arlington pier from the 
Mobile Bay Channel to turning basin at the inner end 
of Garrows Bend Channel, 27 feet deep and 150 feet wide. 
A channel 25 feet deep and generally 500 feet wide in 
Mobile River from the highway bridge to the mouth of 
Chickasaw Creek, then 25 feet deep and 250 feet wide in 
Chickasaw Creek to a point about 400 feet below Shell 
Bayou. 
Enlarging Mobile Bay Channel to 42 by 600 feet, 
Enlarging Mobile Bay Channel to 40 by 400 feet. 
Deepening Mobile River Channel below highway bridge to 
40 feet over present widths, including existing 
turning basins and anchorage areas. Widening river 
channel opposite Magazine Point to provide a 40- by 800- 
by 1,400-foot turning basin. The turning basin was 
further modified for maintenance by SAD letter of 
27 November 1973 under authority contained in 
ER-1130-2-307 to increase the turning basin's 
dimensions to 1000' x 1600'. 
Closure of Garrows Bend Channel by construction and 
operation of an earth-filled causeway across said channel 
(work to be done by local interests). 
To provide a channel 40 feet deep and 400 feet wide from 
the main ship channel in Mobile Bay and extending 
northwesterly for about 5.3 miles to the shore of Mobile 
Bay including an anchorage and turning basin 
near the shoreline, thence a land-cut 40 feet deep, 300 feet 
wide and about 1.9 miles long to and including a 
trapezoidal turning basin 40 feet deep and 
approximately 42 acres, 40 feet deep; a barge channel 
12- by 100-feet extending 6500-feet and terminating in a 
300-foot by 300-foot terminal basin. 
Deepen and widen entrance channel over the bar to 57 by 
700 feet, a distance of about 7.4 miles, deepen 
and widen Mobile Bay Channel from mouth of 
bay to south of Mobile River, 55 by 550 feet a distance 
of about 27.0 miles, deepen and widen an additional 
4.2 miles of Mobile Bay Channel to 55 by 650 feet, 
provide 55 foot deep anchorage area and turning 
basin in vicinity of Little Sand Island, and construct 
a 1710 acre disposal area adjacent to the Brookley 
Industrial Complex. 
PANAMA CITY HARBOR, FL. (See Section 15 of Text) 
Channels 27 and 29 feet deep. Abandonment of project 
adopted by act of June 25, 1910. 
Maintenance of a channel in Watson Bayou 100 feet wide 
and 10 feet deep from that depth in St. Andrew Bay to 
the highway bridge. 
Channels 32 and 34 feet deep. 
A channel 8 by 100 feet in Grand Lagoon from St. Andrew 
Bay to a point about 2,400 feet east of State Highway 
392. Bridge with branches to serve shore facilities 
which terminate at the bridge. 
Channels 38, 40, 42 feet deep. 
PASCAGOULA HARBOR, MS. (See Section 16 of Text) 
Provides for through channel from the Gulf to mile 4 on 
10-36 
Rivers and Harbors 
Committee Doc. 69, 
74th Cong., I1st Sess. 
H. Doc. 739, 79th Cong., 
2d Sess. 
H. Doc. 74, 83d Cong., 
1st Sess. 
H. Doc. 74, 83d Cong., 
2d Sess. 
(Under provision of 
Section 201 of the 
1965 Flood Control 
Act) 
The Energy and Water 
Development Approp. Act 
1985 (P.L. 99-88) 
H. Doc. 33, 73d Cong., 
1st Sess. 
H. Doc. 555, 76th Cong., 
3d Sess. 
H. Doc. 559, 80th Cong., 
2d Sess. 
DPR (Sec. 107) 
H. Doc. 196, 92d-Cong., 
2d Sess. 
H. Doc. 682, 62d Cong.,

MOBILE, ALABAMA DISTRICT 
TABLE 10-B (Continued) 
Acts 
AUTHORIZING LEGISLATION 
Work Authorized 
Mar. 4, 1915 
May 17, 1950 
Sept. 3, 1954 
July 3, 1958 
July 14, 1960 
July 14, 1967 
Oct. 23, 1962 
July 11, 1983' 
June 13, 1902 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Aug. 27, 1962 
Dog River, 25 by 300 feet through Horn Island Pass, 
thence 22 by 225 feet across Mississippi Sound and up 
Pascagoula River to the railroad bridge, thence 22 by 
150 feet in Pascagoula River above bridge, and up Dog 
River to mile 4, all subject to financial participation 
by local interests. 
Waived requirement for financial participation by local 
interests. 
Cutoff channel, 12 by 125 feet, from State Highway 63 
bridge to mile 4 on Dog River, via Robertson and 
Bounds Lakes. 
Modification to provide for channel dimensions of 35 by 
325 feet through Horn Island Pass, thence 30 by 275 feet 
across Mississippi Sound and up Pascagoula River to the 
railroad bridge, and a turning basin just below the 
bridge. 
Reimbursement of local interests for work done on Dog 
River cutoff ($44,000). 
Modification to provide for maintenance of 12- by 125-foot 
channel to mile 6 on Dog River, and maintenance of 30- by 
225-foot side channel from main ship channel in 
Mississippi Sound to the mouth of Bayou Casotte, thence 
30 by 300 feet in Bayou Casotte to a turning basin of the 
same depth I mile above the mouth. 
Deepening the Horn Island Pass channel to 38 feet and 
deepening the main ship channel in Mississippi Sound, 
the river channel to the railroad bridge, and the 
turning basin all to 33 feet. 
Enlarging Horn Island Pass Channel to 40 by 350 feet 
provision of an impounding area adjacent to and east of 
channel 40 feet deep, 200 feet wide, and about 1,500 feet 
long, enlarging main channel in Mississippi Sound and 
river channel to railroad bridge to 38 by 350 feet, and 
deepening turning basin in river and Bayou Casotte 
channels and basin to 38 feet. 
Modification to provide for channel dimensions 12 x 80 feet 
extending about 2,750 feet from deep waters in the 
Pascagoula River into Krebs Lake to a turning basin, 
thence, along the south bank of the lake a channel with 
dimensions of 10 x 60 feet terminating at a second 
turning basin, a distance of about 2,750 feet. The 
project was constructed by hydraulic dredging with 
the disposal placed in an upland diked area. 
PENSACOLA HARBOR, FL. (See Section 17 of Text) 
A channel 30 feet deep at mean low water and 500 feet 
wide from the Gulf of Mexico to the dock line at the 
east end of the city of Pensacola, and also provided 
that $150,000 may be used in constructing or purchasing 
a seagoing suction dredge. 
Modified the existing project for the present inner 
channels and the deepening of the entrance channel 
to 32 feet. 
Improvement of Bayou Chico. 
Modified improvement of Bayou Chico, FL. 
Maintenance of the entrance channel from the Gulf of 
Mexico to lower Pensacola Bay, a distance of about 5 
miles to dimensions of 35 feet deep and 500 feet wide; 
maintenance of a channel along the south side of the 
aircraft carrier mooring basin, a distance of about 2.5 
2d Sess. 
River and Harbor 
Committee Doc. 12, 
63d Cong., 2d Sess. 
H. Doc. 188, 81st Cong., 
Ist Sess. 
H. Doc. 98, 86th Cong., 
Ist Sess. 
H. Doc. 98, 86th Cong., 
Ist Sess. 
Chief of Engineers Report 
dated Nov. 3, 1960. 
H. Doc. 560, 87th Cong., 
2d Sess. 
DPR (Sec. 107) 
H. Doc. 253, 72d Cong., 
Ist Sess. 
Rivers and Harbors 
Committee Doc. 96, 
74th Cong., 2d Sess. 
H. Doc. 743, 79th Cong., 
2d Sess. 
H. Doc. 528, 87th Cong., 
2d Sess. 
10-37 
Documents

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 27, 1965 
July 24, 1946 
Oct. 23, 1962 
June 7, 1968 
April 9, 19844 
April 30, 19864 
March 24, 19863 
July 25, 19864 
January 26, 19774 
miles, to dimensions of 33 feet deep and 300 feet wide; 
a bay channel 33 feet deep, 300 feet wide, and about 2.1 
miles long; parallel approach channels to opposite ends 
of the inner-harbor channel, about 1.3 and 1.4 miles in 
length, each 33 feet deep, 300 feet wide, and flared at 
the junctions with the inner-harbor channel; and 
deepening the existing 500-foot wide inner-harbor channel 
to a depth of 33 feet and lengthening it to 3,950 feet. 
PERDIDO PASS CHANNEL, AL. (See Section 18 of Text) 
A 12- by 150-foot channel stabilized by twin rubblemound 
jetties, from the Gulf of Mexico into Perdido Pass, 
thence 9 by 100 feet into Perdido Bay with a spur channel 
of the same dimensions into Terry Cove. 
WATERWAY CONNECTING TOMBIGBEE AND 
TENNESSEE RIVERS, AL. AND MS. 
(See Section 19 of Text) 
A waterway connecting Tennessee and Tombigbee Rivers via 
East Fork of Tombigbee River, Mackeys and Yellow Creeks. 
Plan of improvement consists of three sections: river 
section, 9- by 300-foot channel for 149 miles between 
Demopolis and Amory, Ms.; canal section, 12 by 300 
feet for 46 miles from Amory to Bay Springs; divide section 
12 by 300 feet (except in the 27 mile-long divide cut in 
which bottom width would be 280 feet) for 39 miles from 
Bay Springs through dividing ridge to Tennessee. Total 
lift of 341 feet to be accomplished by 10 locks. Total 
length of project is 234 miles. 
OKATIBBEE LAKE, MS. (See Section 26 of Text) 
Provides for a dam and reservoir for flood control. 
water supply, water quality control, and recreation. 
TALLAHALA CREEK LAKE, PASCAGOULA RIVER, 
MS. (See Section 27 of Text) 
Provides for a dam and reservoir for flood control, water 
supply, water quality control, recreation, and fish and 
wildlife enhancement. 
AIRPORT ROAD BRIDGE, FRANKSTOWN, MS. 
(See Section 28 of Text) 
The project provides for placing riprap protection on the sides 
and bottom of the channel at the bridge and constructing a 
grouted riprap weir section just downstream of the bridge. 
BIG BROWN CREEK AND TRIBUTARY, PRENTISS 
COUNTY, MS (See Section 29 of Text) 
Emergency streambank protection to the banks and bottoms 
of the channels to retard erosion at the Marietta-Hazeldell 
Road Bridges crossing Big Brown Creek and Big Brown 
Creek tributary. 
BOLIGEE CANAL, BOLIGEE, AL 
(See Section 30 of Text) 
Clearing and snagging Boligee Canal from its confluence 
with the Tombigbee River upstream to mile 5.84. 
Work to be done from within channel and extend from 
top bank to top bank, an approximate width of 20 feet. 
CHATTAHOOCHEE RIVER, EUFAULA, AL 
(See Section 31 of Text) 
Shoreline protection consisting of riprap placed on the 
slopes for 300 feet along the State Docks and a 60 
linear foot sheet pile cutoff wall driven behind the 
docks wharf. Work will prevent further erosion and loss 
of fill material under the wharf. 
COUNTY ROAD BRIDGE OVER LEAF RIVER, 
MAHNED, MS (See Section 32 of Text) 
Streambank erosion protection of bridge piers undermined 
by the Leaf River at a county road bridge near Mahned, MS. 
10-38 
S. Doc. 94, 88th Cong., 
2d Sess. 
H. Doc. 486, 79th Cong., 
2d Sess. 
H. Doc. 549, 87th Cong., 
2d Sess. 
H. Doc. 143, 90th Cong., 
1st Sess. 
DPR (Sec. 14) 
DPR (Sec. 14) 
DPR (Sec. 208) 
DPR (Sec. 14) 
DPR (Sec. 14)

MOBILE, ALABAMA DISTRICTTABLE 
10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 6. 19864 
July 2, 1986 
July 25, 1986 4 
October, 3 19852 
May 6, 1986~ 
February 17, 1982 - 
April 18, 19862 
May 7, 19854 
April 18, 1985 
August 23, 19842 
May 7, 19864 
Aug. 18, 1941 
GOODFOOD CREEK, CHICKASAW COUNTY, MS 
(See Section 33 of Text) 
Bridge protection using riprap extending 30 feet up and 
downstream of the bridge. 
HIGHWAY 39 BRIDGE, GAINESVILLE, AL 
(See Section 34 of Text) 
Slope protection for a 2000-foot reach of the east bank of 
the Tombigbee River, immediately upstream of the 
existing Highway 39 Bridge. 
HOUSTON SCHOOL ROAD BRIDGE, ITAWAMBA 
COUNTY, MS (See Section 35 of Text) 
Bridge protection using riprap extending 62 feet downstream 
of centerline of bridge and extending upstream for 
99 feet. 
LEAF AND BOWIE RIVERS, HATTIESBURG, MS 
(See Section 36 of Text) 
Channel snagging, overbank clearing within the flood plains; 
riprap protection of the Southern Railroad and River 
Avenue Bridge piers, and removal of the Petal sewage 
lagoon. Work also includes installation of a flood 
warning system. 
MARTIN CREEK, PRENTISS COUNTY, MS 
(See Section 37 of Text) 
Emergency streambank protection to the banks and bottom of 
the channel to retard erosion at the Altitude Road Bridge 
crossing Martin Creek. 
MURDER CREEK, EAST BREWTON, AL 
(See Section 38 of Text) 
Provides for nonstructural measures for the reduction of flood 
damages by flood plain evacuation and flood proofing of selected 
buildings along the left bank of Murder Creek. 
MURDER AND BURNT CORN CREEKS, 
BREWTON, AL (See Section 39 of Text) 
Non-structural project providing for the alleviation of 
flood problems at Brewton by the removal of 31 damageable 
structures from the 10-year flood plains of Murder 
and Burnt Corn Creeks. 
NOXUBEE RIVER RELIEF BRIDGE, SHUQUALAK, MS 
(See Section 40 of Text) 
The proposed project for streambank protection at Noxubee River relief 
bridge would consist of grading and protecting of banks with 24 
inches of riprap on 6 inches of bedding material and filter fabric. 
SEWERLINE PROTECTION, VALLEY, AL 
(See Section 41 of Text) 
The project provides for the restoration of approximately 
1600 linear feet of streambank. This will consist of 
placing 1550 cubic yards of riprap on 4445 square yards 
of filter fabric. 
SOPE CREEK, MARIETTA, GA 
(See Section 42 of Text) 
The project provides for flood control measures along Sope 
Creek in Cobb County, Georgia, by clearing and snagging 
and evacuation of 13 structures. 
TALLABINELLA CREEK, CHICKASAW COUNTY, MS 
(See Section 43 of Text) 
Bridge protection using riprap extending 30 feet up and 
downstream of the bridge. 
TOMBIGBEE RIVER (EAST FORK), MS AND AL 
(See Section 44 of Text) 
Provides for alleviation of floods from the Tombigbee River 
by clearing, snagging, and excavation of 13 cut-off 
channels, and other related channel improvements. 
DPR (Sec. 14) 
Urgent Supplemental 
Appropriations Act, 1986 
Public Law 99-349. 
DPR (Sec. 14) 
DPR (Sec. 205) 
DPR (Sec. 14) 
DPR (Sec. 205) 
DPR (Sec. 205) 
DPR (Sec. 14) 
DPR (Sec. 14) 
DPR (Sec. 205) 
DPR (Sec. 14) 
Special Report on Record 
in OCE. (Public Law 222,) 
77th Cong., 1st Sess. 
10-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 23, 1958 
July 8, 1980 
August 9, 1985 4 
December 6, 19834 
July 19, 19844 
August 9, 19854 
Mar. 2, 1945 
June 28, 1954 
May 25, 1982 
Aug. 18, 1941 
Dec. 22, 1944 
Mar. 2, 1945 
July 24, 1946 
TOMBIGBEE RIVER TRIBUTARIES, MS AND AL 
(See Section 45 of Text) 
Provides for improvement of 22 tributaries of Tombigbee 
River. 
Extends project limits on Twenty Mile Creek and 
eliminates local cooperation for this remedial work. 
U.S. HIGHWAY 11 BRIDGE, FOSTERS, AL 
(See Section 46 of Text) 
The project provides for stabilization of the banks 
by placing riprap along a 240-foot reach of the left 
descending bank at the bridge. 
WOLF CREEK, U.S. HIGHWAY 45 BRIDGE, 
PRENTISS COUNTY, MS (See Section 47 of Text) 
The project provides for stabilization of the banks under 
each of the bridges. The banks would be graded and 
protected with 24-inches of riprap on 6 inches of 
bedding material and filter fabric. 
OLD HIGHWAY 82 BRIDGES, COLUMBUS, MS 
(See Section 48 of Text) 
The project provides restoration and stabilization along the 
right descending bank of the bridge. The stabilization 
would consist of 24 inches of riprap on 6 inches of 
bedding material and a filter fabric. The riprap 
placement would begin approximately 140 feet 
downstream of the centerline of the bridge and 
extend upstream along the right descending bank 
for 330 feet. 
INTERSTATE 59 BRIDGES, FOSTERS, AL 
(See Section 49 of Text) 
The project provides streambank protective measures at the 
bridges. Bank stabilization would consist of placing riprap 
along a 195-foot reach of the left descending bank 
at the bridge. 
MULTIPLE PURPOSE PROJECTS INCLUDING POWER 
ALABAMA-COOSA RIVERS, AL. AND GA. (See Section 
53 of Text) 
Provides for full development of Alabama-Coosa Rivers 
and tributaries for navigation, flood control, 
power, recreation, and other purposes. 
Authorized construction of Carters Lake, GA 
Claiborne Lock and Dam, AL, Jones Bluff Lock and 
Dam, AL, and Millers Ferry Lock and Dam, AL. 
Suspended comprehensive plan to permit non-Federal 
interests to develop Coosa River by constructing 
series of dams. 
Designated change of name from Jones Bluff to 
Robert F. Henry Lock and Dam. 
ALLATOONA LAKE, COOSA RIVER BASIN, GA 
(See Section 54 of Text) 
Provides for dam and reservoir for flood control, regulation 
of stream flow for navigation, development of hydroelectric 
power and recreation. 
APALACHICOLA, CHATTAHOOCHEE, AND FLINT 
RIVERS, AL., GA. AND FL. (See Section 55 of Text) 
Development of Apalachicola, Chattahoochee, and Flint 
Rivers for navigation, flood control, hydropower, and 
recreation. 
Modified general plan for full development of 
Apalachicola, Chattahoochee, and Flint River System 
and authorized construction of Lake Sidney Lanier 
multipurpose reservoir. 
H. Doc. 167, 84th Cong., 
1st Sess. 
PL (96-304) 
DPR (Sec. 14) 
DPR (Sec. 14) 
DPR (Sec. 14) 
DPR (Sec. 14) 
H. Doc. 414, 77th Cong., 
1st Sess. 
Public Law 436, 83rd 
Cong. 
S.2034 97th 
Cong., 2d Sess. 
Public Law 228, 77th 
Cong., 1st Sess. 
H. Doc. 674, 76 Cong., 
3d Sess. 
H. Doc. 342, 76th Cong., 
Ist Sess. 
H. Doc. 300, 80th Cong., 
Ist Sess. 
10-40

MOBILE, ALABAMA DISTRICT 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Dec. 22, 1944 Authorized recreation facilities. 
Jan. 27, 1981' Modified the existing project to provide for DPR (Sec. 107) 
nine foot deep by 100-foot wide side channel 
into the Apalachicola River Industrial Park, 
Blountstown, Fl. 
LAKE SIDNEY LANIER, GA. (See Section 55A of Text) 
July 24, 1944 Provision of recreation facilities. 
GEORGE W. ANDREWS LOCK AND DAM, AL. AND GA. 
(See Section 55B of Text) 
July 24, 1946 Construction of high dam at Walter F. George site H. Doc. 300, 80th Cong., 
and low dam at George W. Andrews site. 1st Sess. 
Dec. 22, 1944 Provided recreation facilities. 
JIM WOODRUFF LOCK AND DAM, GA. AND FL. 
(See Section 55C of Text) 
Dec. 22, 1944 Provided recreation facilities. 
SPEWRELL BLUFF LAKE, GA. (See Section 55D of Text) 
Dec. 30, 1965 Authorized construction. H. Doc. 567, 87th Cong., 
2d Sess. 
WALTER F. GEORGE LOCK AND DAM, AL., AND GA. 
(See Section 55E of Text) 
May 19, 1953 Authorized construction of high dam at Walter F. George H. Comm. on 
site and low dam at Columbia site. Public Works 
WEST POINT LAKE, CHATTAHOOCHEE RIVER 
BASIN, GA. AND AL. (See Section 55F of Text) 
October 23, 1963 Authorized construction for flood control, power H. Doc. 570, 87th Cong., 
recreation, fish and wildlife development, and 2d Sess. 
streamflow regulation for downstream navigation. 
1. Authorized by Chief of Engineers under Section 107 of 1960 
River and Harbor Act. 
2. Authorized by Chief of Engineers under Section 205 of Flood 
Control Act of 1948. 
3. Authorized by Chief of Engineers under Section 208 of Flood 
Control Act of 1954. 
4. Authorized by Chief of Engineers under Section 14 of Flood 
Control Act of 1946. 
10-41

TABLE 10-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 20 of Text) 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Report For Construction Maintenance 
Blackwater River, FL 1981 $41,650 $266,368 
Bluff Creek, MS I 1963 1,000 6,883 
Bon Secour River, AL2 1979 118,615 197,569 
Cahaba River, AL2 1894 45,000- 
Cadet Bayou, MS 1984 87,921 705,118 
Carrabelle Bar and Harbor, FL 1979 481,627 379,413 
Choctawhatchee River, FL and AL 1973 171,885 291,694 
Escambia-Conecuh Rivers, AL and FL 1981 208,499 1,102,094 
Gulfport Harbor, MS 1985 635,758 29,189,492 
Holmes Creek, FL 1931 8,562 36,800 
LaGrange Bayou, FL 1972 289,496 82,693 
Leaf and Chickasawhay River, MS2 1919 23,090 42,676 
Noxubee River, MS' 1902 47,528 14,472 
Ochlockonee (Ochlockney) River, GA and FL' 2 1900 5,000- 
Old Town Creek, MS I 2 1887 3,000 
Oostanaula and Coosawattee River, GA' 2 1907 32,656- 
Panacea Harbor, FL 1979 122,383 92,352 
Pascagoula River, MS 1956 15,000 179,535 
Pass Christian Harbor, MS 1976 59,313 139,653 
Port St. Joe Harbor, FL 1984 1,960,862 2,865,5753 
Removing Water Hyacinths 1984 - 1,100,471 
St. Marks River, FL 1965 1,710,809 84,115 
Tallapoosa River, AL2 1893 43,972 
Upper Chipola River, FL, from Marianna to 
its mouth' 2 1941 36,781 63,193 
Wolf and Jordan Rivers, MS 1979 29,195 481,515 
1. Abandonment recommended in H. Doc. 467, 69th Cong. 96-157, 1st Session. 
2. Uncompleted portion of project deauthorized by H. Doc. 3. Includes $80,000 contributed funds. 
TABLE 10-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECT 
(See Section 24 of Text) 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Report For Construction Maintenance2 
Harrison County, MS, shore protection' 1953 $1,133,000- 
1. Completed. 
2. Operation and maintenance is the responsibility of local 
interests. 
10-42

MOBILE, ALABAMA DISTRICT 
TABLE 10-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 51 of Text) 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Report For Construction Maintenance2 
Alabama River at Montgomery, AL' 1965 $144,194- 
Armuchee Creek, GA 1966 115,547- 
Beaver Creek, Montezuma, GA 1958 149,815- 
Biloxi River at Lorraine Road, Harrison County, MS 1985 132,174- 
Black Creek, Gadsden, AL 1953 125,389- 
Burketts Creek, Amory, MS 1984 1,366,454- 
Chickasaw Bogue Creek, U.S. Highway 43 Bridge, Linden, AL 1985 121,718- 
Clanton, AL 1964 274,024- 
Collinsville, AL 1940 71,119- 
Gordons Creek, Hattiesburg, MS 1985 802,026- 
Houlka Creek, Chickasaw & Clay Counties, MS 1982 238,219- 
Jackson and East Jackson, MS 1979 7,190,200- 
Lake Douglas, Decatur County, GA 1970 164,998- 
Little Cove Creek, Glencoe, AL 1965 113,849- 
Murder and Burnt Corn Creeks, Brewton, AL 1980 190,974- 
Osborne Creek, Highway 362 Bridge, Prentiss County, MS 1985 250,000- 
Pearl River, Interstate 20 Bridges, Jackson, MS 1985 250,000- 
Prattville, Autauga Creek, AL 1946 649,280- 
Pumpkinvine Creek, Emerson, GA 1985 85,029- 
Rome, Coosa River, GA 1955 384,550- 
Sowashee Creek, Meridian, MS 1956 142,637- 
Sun Creek, Oktibbeha County, MS 1984 55,569- 
Town Creek, Americus, GA 1965 340,409- 
Trim Cane Creek, Oktibbeha County, MS 1984 145,519- 
Trussville, AL 1965 141,334- 
West Point, Chattahoochee River, GA 1955 599,637- 
Wolf Creek, Highway 362 Bridge, Prentiss County, MS 1985 114,753- 
Yellow Jacket Creek, Hogansville, GA 1966 330,734- 
I. Engineering, design, supervision, and administration (no con- 2. Operation and maintenance is the responsibility of local 
struction work has been done. Includes $17,000 for pre- interests. 
authorization studies. 
TABLE 10-G DEAUTHORIZED PROJECTS 
(See Section 23 of Text) 
Year of Last Deauthorization Date 
Project Type Full Report Document' Deauthorized 
Bayou Galere, MS Navigation 1946 H. Doc. 192, 94th Cong., 5 Aug. 1977 
1st Sess., as amended. 
I. H. Doc. 96-157 deauthorized uncompleted portions of 
certain projects as shown in Table 10-E. 
10-43

REPORT TO THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 10-H NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
(See Section 21 of Text) 
Fiscal Year 
Study Authority 1986 Costs 
Bayou Cumbest, Jackson County, MS 107 $2,203 
Carrabelle Harbor, FL 107 10 
East Point, FL 107 458 
Ocean Springs Harbor, MS 107 21,018 
Shell Point, Wakulla County, FL 107 946 
Tombigbee River, Columbus, MS 107 23,417 
Total $48,052' 
1. Excludes construction costs of $145,490 for Biloxi Harbor, 
Harrison County Canal, MS and $124,622 for Dog River Channel, 
AL. 
TABLE 10-I BEACH EROSION CONTROL PROJECT UNDER 
SPECIAL AUTHORIZATION (See Section 25 of Text) 
Fiscal Year 
Study Authority 1986 Costs 
Liza Jackson Park, Ft. Walton, FL 103 $ 518 
Santa Rosa Island, FL 103 622 
Total $1,140 
TABLE 10-J FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 52 of Text) 
Fiscal Year 
Study Authority 1986 Costs 
Big Escambia Creek, Flomaton, AL 205 $ 45,939 
Brickyard Bayou, Gulfport, MS 205 7,210 
Chattahoochee River, Vinings, GA 205 15,068 
Cribbs Mill Creek, Tuscaloosa, AL 205 71,963 
Eslava Creek, Mobile, AL 205 66,674 
Five Mile Creek, Brookside, AL 205 27,888 
Glencoe, AL 205 7,414 
Greens Creek, Petal, MS 205 16,832 
Magby Creek, Columbus, MS 205 27,370 
Mill Creek, Dalton, GA 205 9,342 
Mixons Creek, Lamar County, MS 205 40,354 
Orange Grove Community, MS 205 5,489 
Raccoon Creek, Baconton, GA 205 44,491 
Silver Creek, Rome, GA 205 15,414 
Sougahatchee Creek, Auburn, AL 205 64 
Three Mile Creek Tributary, Mobile, AL 205 6,900 
Tibbee Creek, Reform, AL 205 33,700 
Toulmins Spring Branch, Prichard, AL 205 9,701 
Trim Cane Creek, MS 205 35,701 
Upper Gordons Creek, Hattiesburg, MS 205 45,287 
Alligator Point, Franklin County, FL 14 210 
Cooks Bayou, Bay County, FL 14 3,700 
Little Wolf Creek, Booneville Airport, MS 14 5,330 
Pascagoula River, Griffin Point, MS 14 7,500 
Sucarnoochee River, De Kalb-Wahalak, Kemper County, MS 14 2,990 
Sucarnoochee River, Townsend-Porterville, Kemper County, MS 14 1,840 
Vernon Branch Bridge, Columbus, MS 14 5,162 
Wolf Creek, Booneville Airport Road, MS 14 4,890 
Elliotts Creek, Moundville, AL 208 7,320 
Haven Creek, Lee County, MS 208 6,100 
Total $577,843 
10-44

MOBILE, ALABAMA DISTRICT 
RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 22 of Text) 
Project 
Apalachicola Bay, FL 
Bayou La Batre, MS 
Biloxi Harbor, MS 
Blackwater River, FL 
Bon Secour, AL 
Cadet Bayou, MS 
Carrabelle Harbor, FL 
Dauphin Island Bay, AL 
Escambia Bay, FL 
Fly Creek, AL 
Fowl River, AL 
La Grange Bayou, FL 
Panacea, FL 
Panama City, FL 
Pascagoula River, MS 
Pass Christian, MS 
Pensacola Harbor, FL 
Port St. Joe Harbor, FL 
St. Marks River, FL 
Wolf and Jordan Rivers, MS 
Date of Survey 
July, 1986 
July, 1986 
September, 1986 
November, 1985 
September, 1986 
January, 1986 
July, 1986 
August, 1986 
November, 1985 
September, 1986 
September, 1986 
August, 1986 
July, 1986 
August, 1986 
September, 1986 
February, 1986 
July, 1986 
August, 1986 
July, 1986 
February, 1986 
Total 
TABLE 10-L ALABAMA-COOSA RIVERS, ALA. AND GA. 
DEVELOPMENT PROPOSED UNDER EXISTING PROJECT 
(See Sections 53 and 54 of Text) 
Claiborne Millers Ferry Robert F. Henry Carters Allatoona 
Proposed Structures Lock and Dam Lock and Dam Lock and Dam Lake Dam3 Dam 
Miles above mouth of river 81.1' 42.2' 245.41 26.82 47.84 
Nearest town Claiborne, Ala. Camden, Ala. Benton, Ala. Carters, Ga. Cartersville, Ga 
Distance (miles) 7 10 3 2 4 
Greatest lock length available 
for full width (feet) 600 600 600 - - 
Width of lock chamber (feet) 84 84 84 - - 
Maximum lift (feet) 30 48 47 - - 
Elevation of normal pool surface 
(mean sea level) 35 80 125 1072 Varies seasonally 
Depth over sills at low water 13 Upper 15 Upper 15 -- 
(feet) Lower 13 Lower 12 
Character of foundation Rock Rock Rock Rock Rock 
Kind of spillway Gated and Gated Gated Gated Gated 
Fixed Crest 
Height of dam (feet) 95.5 99.5 94 451 190 
Type of construction Concrete Concrete Concrete Rock-fill Concrete 
Earth Core 
Total reservoir capacity 
(acre-feet) 96,360 331,800 234,200 472,800 670,050 
Power development (kw) - 75,000 68,000 500,000 74,000 
Percent complete 100 100 100 100 100 
Cost to date:5 $27,997,450 $63,122,507 $83,360,800 $111,140,340 $35,709,084 
1. Above mouth of Alabama River (river miles). 
2. Above mouth of Coosawattee River (river miles). 
3. Reregulation dam (Carters) 25.3 (river miles). 
4. Above mouth of Etowah River (river miles). 
5. Includes cost of added recreation facilities as shown in Table 
10-A. 
10-45 
TABLE 10-K 
Cost During 
Fiscal Year 
8,466 
18,210 
1,204 
9,030 
17,055 
6,870 
12,911 
9,772 
3,119 
3,954 
859 
9,961 
13,906 
3,249 
1,258 
15,317 
151 
1,901 
4,328 
5,160 
$146,681

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 10-M 
APALACHICOLA, CHATTAHOOCHEE, AND FLINT RIVERS, ALA., GA., 
AND FLA., LOCKS AND DAMS AND MULTIPLE-PURPOSE 
DEVELOPMENT INCLUDED IN EXISTING PROJECT 
(See Section 55 of Text) 
Existing Projects Authorized Projects 
Jim George W. Walter F. Buford Dam Lower 
Woodruff Andrews George Lake Auchumpkee Lazer Spewrell 
Lock Lock Lock West Point Sidney Creek Creek Bluff 
and Dam and Dam and Dam Lake Lanier Lake Lake Lake 
Miles above mouth 107.6' 46.52 75.02 201.42 348.32 233.43 255.83 263.83 
Nearest town Chattahoochee, Columbia, Al. Ft. Gaines, West Point, Buford, Ga. Roberta, Ga. Thomaston, Manchester, 
Fl. Ga. Ga. Ga. Ga. Ga. 
Distance (miles) 1 1 2 2.8 5 7 8 8 
Greatest lock length 450 450 450 - -- - 
available for full width 
(feet) 
Width of chamber (feet) 82 82 82 - -- - 
Maximum lift (feet) 33 25 88 - -. 
Elevation of normal pool 77 102 190(Summer) 635(Summer) 1070 417 543 700 
surface (msl) 185(Winter) 625(Winter) 
Depth over sills at low 14 13 13 - - 
water (feet) 
Character of foundation Limestone Limestone Limestone Rock Rock Rock Rock Rock 
Kind of spillway Fixed-gated Fixed-gated Gated Gated Fixed Gated Gated Gated 
Height of dam (feet) 67 62 114 95 192 130 142 180 
Type of construction Concrete Concrete Concrete Concrete Earth Concrete Concrete Concrete 
and Earth and Earth and Earth and Earth and Earth and Earth 
Total reservoir capacity 367,300 18, 180 934,400 604,500 2,554,000 548,000 342,000 486,200 
(acre-feet) 
Power development 30,000 -1 30,000 73,875 86,000 81,000 87,000 150,000 
(kilowatts) 
Percent complete 100 100 100 100 100-- 
Year opened to navigation 1954 1962 1963 - - 
Estimated cost: - - - - - $222,000,000 $258,000,000 $360,000,000 
Cost to date: 4 $47,978,749 $13,038,427 $98,543,5435 $131,501,360 $53,035,378 - - $2,158,652 
1. Above the mouth of Apalachicola River (river miles). 
2. Above mouth of Chattahoochee River (river miles). 
3. Above mouth of Flint River (river miles). 
4. Includes cost of added recreational facilities as shown in Table 10-A. 
5. Includes $333,198 cost of land for wildlife refuge. 
10-46

MOBILE, ALABAMA DISTRICT 
TABLE 10-N BLACK WARRIOR AND TOMBIGBEE RIVERS, ALA. 
(See Section 7 of Text) 
Armistead I. William John Hollis 
Coffeeville Demopolis Selden Bacon Oliver Holt Bankhead 
Lock Lock Lock Lock Lock Lock 
and Dam and Dam and Dam and Dam and Dam and Dam' 
Miles above Mobile2 116.7 213.2 261.1 338.2 347.0 365.5 
Nearest town (Alabama) Coffeeville Demopolis Eutaw Tuscaloosa Tuscaloosa Oak Grove 
Distance (miles) 3)within city) 6 15 
Lock: 
Greatest length available 
for full width (feet) 600.0 600.0 600.0 450.0 600.0 600.0 
Width of chamber (feet) 110 110 110 95 110 110 
Maximum lift (feet) 34 40 22 28 64 68 
Depth over sills at low 
water (feet) 13.0 13.0 13.2 12.0 13.0 14.0 
Character of foundation Rock Rock Sand, clay Hard shale Shale, Sandstone 
sandstone 
Kind of spillway Fixed-Gated Fixed Gated Fixed Gated Gated 
Type construction 
Lock Concrete Concrete Concrete Concrete Concrete Concrete 
Dam Concrete Concrete Earth- Concrete Concrete Concrete 
Concrete 
Year completed 1965 1962 1962 1940 1969 1985 
Year opened to navigation 1960 1954 1957 1939 1966 1975 
Actual cost of lock and dam $21,597,2643 $19,774,5833 $13,295,5533 $4,450,874 $28,100,0003 $47,258,6514 
1. Single lift lock. 
2. Navigation mileage from foot of Government Street, Mobile, 
Al.
3. Excludes cost of adding recreation facilities. 
4. Cost to date (FY 86) for replacement of single lift lock which 
was essentially completed in FY 80. Excludes $1,435,636 cost of land 
submerged, damage to structures, and cost of spillway. Also 
excludes $3,824,859 cost of original double lift lock. 
10-47

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 10-0 
TENNESSEE-TOMBIGBEE WATERWAY, ALABAMA AND MISSISSIPPI 
(See Section 19 of Text) 
Existing Projects 
Gainesville Aliceville Columbus Aberdeen Lock A Lock B Lock C Lock D Lock E Bay Springs 
Lock Lock Lock Lock and and and and and Lock and 
and Dam and Dam and Dam and Dam Spillway Spillway Spillway Spillway Spillway and Dam 
Miles above mouth' 266 307 335 358 371 376 39 398 407 412 
Nearest town Gainesville, AL Aliceville, AL Columbus, MS Aberdeen, MS Amory, MS Smithville, AL Fulton, MS Fulton, MS Belmont, MS Tupelo, MS 
Greatest lock length 600 600 600 600 600 600 600 600 600 600 
available for full 
width (feet) 
Width of Chamber (feet) 1 10 110 110 110 110 110 110 110 I10 110 
Maximum lift (feet) 36 27 27 27 30 25 25 30 30 84 
Elevation of normal 109 136 163 190 220 245 270 300 330 (Summer)414 
pool surface (msl) (Winter)409 
Depth over sills at 15 15 15 15 15 18 18 18 18 18 
low water (feet) 
Character of foundation Mooreville Eutaw Form. Eutaw Form. Eutaw Form. Eutaw Form. Eutaw Form. Gordo Form. Eutaw Form. Gordo Form. Sandstone 
Chalk Sand & Clay Sand & Clay Sand Lam. Sand Sand & Clay Clay Sand Clay and Shale. 
Kind of spillway Fixed & Fixed & Gated Gated Gated Gated Gated Gated Gated N/ A 
Gated Gated 
Height of dam (feet) 56 57 57 57 46 48 53 52 44.5 103 
Type of construction Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete 
& Earth & Earth & Earth & Earth & Earth & Earth & Earth & Earth & Earth 
Total reservoir capacity 45,290 655 59,483 31,564 4,400 19,000 13,300 24,900 6,900 (Summer)180,000 
(acre-feet)(Winter)143,000 
Percent complete 100 100 100 100 100 100 100 100 100 100 
Year opened to 1978 1979 1981 1984 1985 1985 1985 1985 1985 1985 
navigation 
Estimated Cost $103,214,000 151,255,000 182,650,000 128,262,000 102,685,000 96,905,000 71,375,000 98,205,000 88,173,000 147,000,000 
Cost to date $99,961,000 137,802,000 172,715,000 I 10,437,000 91,199,000 89,790,000 62,026,000 89,468,000 75,813,000 130,398,000 
1. Miles above Mobile, Alabama (Mile 0.00 is at Bankhead Tunnel on U.S. Highway 90) 
0
00h

MOBILE, ALABAMA DISTRICT 
TABLE 10-P COMPLETED FLOOD INSURANCE STUDIES AND FLOOD 
HAZARD INFORMATION REPORTS FOR FY 1980 THRU FY 1986' 
(See Section 58 of Text) 
Date Federal 
Study Requesting Agency Completed Cost 
Flood Insurance Studies 
Montgomery Co., Alabama 
Roanoke, Alabama 
Wedowee, Alabama 
Heflin, Alabama 
Randolph County, Alabama 
Hobson City, Alabama 
Oxford, Alabama 
Weaver, Alabama 
Flood Insurance Studies 
Anniston, Alabama 
Calhoun County, Alabama 
Cave Springs, Georgia 
Columbus, Mississippi 
Lowndes County, Mississippi 
Aberdeen, Mississippi 
Amory, Mississippi 
Cherokee County, Georgia 
Monroe County, Mississippi 
Floyd County, Georgia 
Special Flood Hazard Information 
Dowling Branch, Ala. 
Choctawhatchee River, 
Vicinity of Daleville, AL 
Gum Creek, Ga. 
Choctawhatchee River, Fla. 
Chattahoochee River, Supplefor 
Buford to Whitesburg Report 
Oothcalooga Creek 
Canton Creek, Ga. 
Oktasasi Creek, Ala. 
Cordele Creek & 
Malcolm Branch, Ga. 
Hull Branch, MS 
Percosin Creek & Tribs., GA 
Coosawattee, Ellijay and Cartecay 
Rivers, Vicinity of Ellijay, GA 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
(Prepared for Federal Insurance 
Administration, HUD) 
FEMA 
FEMA 
FEMA 
FEMA 
FEMA 
FEMA 
FEMA 
FEMA 
FEMA 
FEMA 
City of Hartford, Ala. 
City of Daleville, AL 
Housing Authority, Cordele, Ga. 
Board of County Commissioners 
Holmes County, Fla. 
Atlanta Reg. Planning 
Commission 
Gordon Co., GA Board of 
Commissioners 
City of Canton, Ga. 
Alexander City, Ala. 
City of Cordele, Ga. 
East Central Planning and 
Development District 
City of Albany, GA 
City of Ellijay, GA 
I. For list of reports completed by Mobile District for FY 1965 
thru FY 1974, see FY 1974 Annual Report, page 10-50; reports 
completed in FY 1975 see FY 1975 Annual Report, page 10-44; and 
for reports completed in FY 1976 and FY 1977, see FY 1977 Annual 
Report, page 10-46. See page 10-48 FY 1978 Annual Report for FY 
1978 reports, and see page 10-43 FY 1984 Annual Report for FY 
1979 reports. 
10-49 
Apr 80 
Feb 81 
Feb 81 
Mar 81 
Mar 81 
Sep 81 
Sep 81 
Sep 81 
Apr 82 
Apr 82 
Jan 84 
Feb 85 
Feb 85 
May 85 
May 85 
July 85 
Oct 85 
Dec 85 
Jan 80 
Apr 80 
Sep 80 
Jan 81 
Mar 82 
Jun 82 
Dec 82 
Jan 83 
May 83 
Jun 84 
Nov 84 
Jul 86 
104,600 
19,400 
21,900 
20,700 
34,400 
14,200 
30,000 
6,400 
80,900 
61,200 
22,500 
36,000 
229,000 
35,000 
50,000 
168,000 
140,000 
330,000 
10,000 
15,00 
10,000 
10,000 
5,000 
10,000 
3,000 
3,000 
4,000 
7,000 
14,000 
22,000

NEW ORLEANS, LA, DISTRICT * 
District comprises a portion of Louisiana, including 
drainage area of Red River south of Fulton, AR, 
embraced in drainage basins tributary to Mississippi 
River and Gulf of Mexico, except Mississippi River 
above mile 325.5 above Head of Passes, drainage area 
of Ouchita-Black River Basin, and small eastern and 
western portions of Louisiana tributary to Pearl River 
and Sabine River and Lake. 
It includes sections of the Gulf Intracoastal Waterway 
from Lake Borgne Light 29 at the mouth of Pearl River 
to Sabine River, and the Passes of the Mississippi 
River. It exercises jurisdiction over flood control work 
on Mississippi River from mile 325.5 AHP to Gulf of 
Mexico; Atchafalaya River; and in Atchafalaya Basin; 
and maintenance of project navigation channel of 
Mississippi River below mile 325.5 AHP, under supervision 
of President, Mississippi River Commission 
(MRC), and Division Engineer, Lower Mississippi 
Valley Division. 
IMPROVEMENTS 
Navigation 
1. Leland Bowman Lock, LA 
(Replacement of Lock) 
(Formerly Vermilion Lock, LA ......... 
2. Mississippi River, Baton Rouge 
to Gulf of Mexico, LA .................. 
3. Mississippi River-Gulf Outlet, LA ...... 
4. Mississippi River Outlets, 
Venice, LA ........................... 
5. Waterway from Intracoastal Waterway 
to Bayou Dulac, LA (Bayous Grand 
Caillou and LeCarpe, LA ............. 
6. Navigation work under 
special authorization ................. 
Flood Control 
7. Grand Isle & vicinity, LA ............. 
8. Lake Pontchartrain and vicinity, 
LA, (hurricane protection) ............. 
9. Larose to Golden Meadow, LA 
(hurricane protection) ................. 
Page Flood Control (cont.) 
10. Morgan City and vicinity, LA 
(hurricane protection) ............... 
11-2 11. New Orleans to Venice, LA, 
(hurricane protection) ................ 
11-2 12. Inspection of completed flood 
11-3 control projects ...................... 
13. Flood control work under special 
11-4 authorization ....................... 
11-5 
11-5 
11-5 
11-6 
General Investigations 
14. Active Investigations ................. 
Tables 
Table 11-A 
Table 11-B 
Table 11-C 
Table 11-D 
11-7 Table 11-E 
Cost and Financial Statement.. 
Authorizing Legislation ....... 
Other Authorized Navigation 
Projects ..................... 
Other Authorized Flood 
Control Projects .............. 
Active General Investigations.. 
Page 
11-7 
11-8 
11-9 
11-9 
11-9 
11-10 
11-12 
11-14 
11-16 
11-18 
11-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. LELAND BOWMAN LOCK, LA 
(REPLACEMENT OF LOCK) 
(FORMERLY VERMILION 
LOCK, LA) 
Location. In the Louisiana section of the Gulf Intracoastal 
Waterway near Abbeville, Vermilion Parish, 
LA, about 163 miles west of Harvey Lock. 
Existing project. The present Leland Bowman 
Lock, located in the most heavily utilized section of the 
Gulf Intracoastal Waterway, is the controlling 
structure in both width and depth. The lock is used for 
navigation and flood control (prevention of salt water 
intrusion). The tumbler-type gates are unsatisfactory 
for the dual purpose. (Flood Control-Navigation) 
operation required, since once the gates are lowered to 
pass flood flows, they cannot be safely raised until the 
differential stage across the lock is reduced to about 
0.5 foot. The replacement lock also will provide a 
larger and more efficient outlet for floodwaters. 
Estimated cost for new work (October 1982) is 
$32,200,000 Federal and $240,000 non-Federal. The 
project was renamed "Leland Bowman Lock 
(Replacement)" by House Resolution 4284 dated Sep. 
21, 1981 (House Report 97-234.) 
Local cooperation. Provide all lands, easements 
and rights-of-way for construction of the project and 
hold and save the United States free from damages 
due to construction and maintenance works. The 
Vermilion Parish Police Jury furnished assurances 
covering all requirements of local cooperation, 
including PL 91-611 and PL 91-646, on Mar. 19, 1975. 
These assurances were in the process of being accepted 
by the United States, when the Water Resources 
Development Act of 1976 was enacted authorizing the 
110-foot-wide lock. Amended assurances of local 
cooperation were accepted on behalf of the United 
States by the Secretary of the Army on Jul. 5, 1977. 
The Vermilion Parish Police Jury on May 26, 1981 
granted right of entry for construction of project. 
Terminal facilities. None. 
Operations and results during fiscal year. Construction 
was initiated Oct. 15, 1981, and completed 
Mar. 9, 1985 at a cost of $26,781,241. 
Condition as of Sep. 30. The project is 100 percent 
complete. 
2. MISSISSIPPI RIVER, 
BATON ROUGE TO 
GULF OF MEXICO, LA 
Location. This reach of the river flows southeasterly 
through southeastern portion of Louisiana. At Head of 
Passes, approximately 233.1 miles below Louisiana 
Highway Commission bridge at Baton Rouge, river 
branches into three main passes: Southwest Pass, 
South Pass, and Pass a Loutre, two of which, 
Southwest Pass and South Pass, are improved under 
existing project. Head of Passes to mouths of 
Southwest and South Passes are 20.1 and 13.5 miles, 
respectively. Mouth of Southwest Pass is 141 miles 
west of Mobile, AL, and 349 miles east of Galveston, 
TX. Mouth of South Pass is 18.5 miles northeast of 
mouth of Southwest Pass. (Refer to NOAA Coast 
Charts Nos. 11361, 11364, and 11369; MRC alluvial 
valley map, and Zachary, Baton Rouge, White Castle, 
Donaldsonville, Thibodaux, Mount Airy, Bonnet 
Carre, Hahnville, New Orleans, St. Bernard, 
Barataria, Pointe a la Hache, Black Bay, Empire, 
Forts, West Delta, East Delta, and Southwest Pass 
quadrangles and 1980 (48th edition) folio of flood 
control and navigation maps, Mississippi River, Cairo, 
IL, to Gulf of Mexico, LA, published by the MRC.) 
Previous projects. For details see page 552 of 
Annual Report for 1963. 
Existing project. Provides for channel dimensions 
as follows: Between a line one-tenth mile below Louisiana 
Highway Commission bridge at Baton Rouge 
129.3 miles to upper port limits of New Orleans, 40 by 
500 feet mean low water; within limits of port of New 
Orleans, where that authority has jurisdiction over 
both banks of river, a distance of 17.8 miles, 35 by 
1,500 feet, measured from a line generally 100 feet 
from face of left bank wharves, but not closer than 100 
feet to wharves on right bank; within 35- by 1,500-foot 
channel in port limits of New Orleans, 40 by 500 feet; 
from lower limits of port of New Orleans 86.7 miles to 
Head of Passes, 40 by 1,000 feet; Southwest Pass, 17.5 
miles from Head of Passes to jetty channel, 40 by 800 
feet; 4.1 miles in the Southwest Pass bar and jetty 
channel, 40 by 600 feet; South Pass from Head of 
Passes to outer ends of jetties, 13.5 miles, 30 by 450 
feet; and 1.2 miles in the South Pass bar channel, 30 by 
600 feet. Plane of reference below New Orleans is 
mean low gulf. Plane of reference above and through 
New Orleans is low water reference plane. General 
plan of improvement of Southwest Pass provides for 
constructing pass to uniform cross section with about 
1,420-foot surface width by means of jetties, spur 
dikes, and bulkheads; for channel maintenance by 
dredging from Cubits Gap, mile 3.5 AHP through the 
gulf entrance channel, mile 21.5 BHP; for construction 
of small revetted openings through narrow portions of 
banks of pass for purpose of strengthening and 
nourishment of banks; for closure of minor outlets not 
required for maintenance of banks; for construction of 
sills to prevent enlargement of the Venice Jump and 
Cubits Gap; for repairs to sill across Pass a Loutre and 
bank revetment at Head of Passes; for construction of 
dikes with a view to reducing width of river above 
Head of Passes; for construction of a submerged 
deflecting dike above Head of Passes; and for other 
minor work. East jetty is about 24,950 feet long and 
west jetty 19,699 feet. Jetties are composed of a 
substructure of brush mattresses, orginally built to 
about elevation of mean low gulf, surmounted with a 
superstructure of concrete blocks and large riprap 
and/or stone rubble mound of core and cover stone. 
11-2

NEW ORLEANS, LA, DISTRICT 
Spur dikes are constructed of round timber piles and/ 
or triangular prestressed concrete piles, with riprap at 
the landward ends to connect the dikes to the bank 
line. General plan of improvement of South Pass 
provides for construction and maintenance of jetties 
and spur dikes; for channel maintenance by dredging 
from Head of Passes through the Gulf Entrance 
Channel beyond mile 13.5 BHP; maintenance of a sill 
across Pass a Loutre, and for seaward extension of east 
jetty at mouth of pass; removal of west dike and 
construction of spur dikes and bank revetment at Head 
of Passes; removal of false point at head of South Pass 
to bottom elevation of minus 45 feet and revetment of 
new bank line and construction and maintenance of 
east and west headland structure at Head of Passes. 
East jetty foundation is 12, 070 feet long; inner east 
jetty is 11,170 feet long; west jetty is 7,820 feet long; 
and inner west jetty is 4,710 feet long. Jetties are 
composed of a substructure of brush mattresses 
surmounted by a superstructure of stone and/or 
concrete blocks and large riprap. Plane of reference is 
mean low gulf. Variation of water surface is 16 inches 
at mouths and 10 inches at head of the passes, due to 
tides. Extreme range of tides at mouths of passes due 
to hurricanes in about 10 feet. At New Orleans 
extreme range of water surface is about 20 feet due to 
floods. At Baton Rouge extreme range is about 45 feet 
due to floods. 
Estimated cost of existing project (October 1986) is 
$386,900,000 Federal. In addition, Coast Guard is to 
provide navigation aids at an estimated cost of 
$1,222,800. 
Local cooperation. None required, except for modification 
of project in connection with Mississippi 
River-Gulf Outlet, which is reported separately. 
Terminal facilities. Piers, wharves, or docks serve 
the Port of New Orleans. Most wharves on east or left 
bank parallel riverbank forming nearly a continuous 
covered quay about 10 miles long. Public wharves 
controlled by Board of Commissioners, Port of New 
Orleans (the Dock Board), cover 62 percent of 
improved waterfront. These facilities include a 
shipside grain elevator, general cargo and cotton 
wharves, fruit landings, bunkering facilities, terminal 
warehouses, railroad terminals, marine railways, and 
drydocks. (For further details see Port Series No. 20, 
"The Port of New Orleans, LA" revised 1977.) A 
foreign trade zone is located in Port of New Orleans. 
City of Baton Rouge has a reinforced concrete dock for 
deep-sea vessels with mechanical-handling facility. 
Attached to downstream end of wharf is a floating 
wharf boat 231 by 40.5 feet, of 2,000-ton capacity. 
Facilities are served by a transfer boat and municipal 
terminal having a capacity of 40 cars per day. Private 
terminals for handling oil, grain, bauxite ore, and 
other products are at points on both sides of river 
between New Orleans and Baton Rouge. Facilities are 
considered adequate for existing commerce. (For 
further details, see "Port Facilities" included in "Flood 
Control and Navigation Maps of the Mississippi River, 
Cairo, IL, to the Gulf of Mexico, LA," published 
annually by the MRC, and Port Series No. 19, vol. 1, 
"Port St. Joe, FL, Pensacola, FL, Baton Rouge, LA, 
and Lake Charles, LA," revised 1979.) 
Operations and results during fiscal year. The 
Supplement II to the GDM was completed in March 
1986 and the environmental impact statement (EIS) 
for this supplement was completed in May 1986. 
Maintenance: (a) Baton Rouge to New Orleans: Two 
dustpan dredges removed 10,754,000 cubic yards of 
shoal material at a cost of $3,332,700. 
(b) New Orleans Harbor: One leased dredge 
contract removed 2,393,100 cubic yards of material at 
a cost of $1,519,000. 
(c) Cubit's Gap (mile 3 AHP) through Southwest 
Pass: Two hopper dredges and two cutterhead dredges 
removed 17,930,000 cubic yards of shoal material at a 
cost of $12,890,000. 
(d) Southwest Pass: Work was completed on two pile 
dike repair contracts at a total cost of $3,232,000. 
Hired labor repairs to pile dikes at a total cost of 
$508,300. In addition, a contract for repairs to the east 
and west jetties was completed at a total cost of 
$1,886,300. 
(e) Wheeler Wharf at Venice: Modification and repairs 
to the wharf were performed by hired labor units 
at a cost of $254,700. 
Condition as of Sep. 30. The existing project is 50 
percent complete. Deepening Southwest Pass to 40 feet 
mean low gulf, as authorized by the modification of 
Mar. 2, 1945, was completed in September 1963. 
Deepening the channel to 40 feet mean low water from 
Baton Rouge to New Orleans and to 40 feet mean low 
gulf in New Orleans Harbor, as authorized by the 
modifications of Oct. 23, 1962, was completed in 
August 1963. The foreshore dike Mile 0.5 to Mile 3.0 
AHP on the right descending bank is complete. The 
foreshore dike Mile 0.6 to Mile 4.6 BHP on the left 
descending bank is complete. The foreshore dike Mile 
2.3 to Mile 4.7 BHP right descending bank is 85 
percent complete. The foreshore dike Mile 4.0 to Mile 
3.0 AHP right descending bank is 75 percent 
complete. 
3. MISSISSIPPI RIVER-GULF 
OUTLET, LA 
Location. In State of Louisiana and extends from 
existing Inner Harbor Navigation Canal at a point 
7,500 feet north of existing lock and about 11,000 feet 
from Mississippi River, to a turning basin south of 
Michoud, LA, and then as a land and water cut from 
turning basin south of Michoud, LA, southeasterly to 
and along south shore of Lake Borgne and through 
marshes to and through Chandeleur Sound to 38-foot 
contour in Gulf of Mexico. (Refer to NOAA Coast 
Charts Nos. 11340, 11360, 11363, 11369, 11371, and 
11373. Also see MRC 1980 (48th edition) folio of maps, 
Mississippi River-Cairo, IL, to Gulf of Mexico, LA.) 
11-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Existing project. Provides for a seaway canal, 36 by 
500 feet, extending 76 miles as a land and water cut 
from Michoud southeasterly to and along south shore 
of Lake Borgne, and across Chandeleur Sound to 
Chandeleur Island and increasing gradually to 38 by 
600 feet in Gulf of Mexico, with protective jetties at entrance, 
a permanent retention dike through Chandeleur 
Sound, and a wing dike along islands as 
required. It also provides for an inner tidewater 
harbor consisting of 1,000- by 2,000-foot turning basin 
36 feet deep at landward end of seaway canal, and a 
connecting channel 36 by 500 feet wide extending 
westerly along Gulf Intracoastal Waterway from 
turning basin to Inner Harbor Navigation Canal, 
including construction of a suitable highway bridge 
with approaches to carry Louisiana State Highway 47 
(formerly 61) over channel. Plan further provides for 
future construction of a channel and lock in the 
vicinity of Meraux to furnish an additional connection 
between tidewater harbor and Mississippi River. 
Estimated cost for new work (October 1985) is 
$489,000,000 Federal and $225,300,000 non-Federal. 
This does not include modification for Mississippi 
River-Gulf Outlet, Michoud Canal, which is reported 
separately. The Federal cost excludes $45,000 for aids 
to navigation by U.S. Coast Guard. 
Local cooperation. Original assurances furnished 
and accepted. Local agency has furnished Supplemental 
Assurance covering Public Law 91-646. Rights-ofentry 
for entire project were furnished by local agency 
which is in process of conveying to the United States 
title to remaining tracts. Supplemental assurances 
reflecting the changes made necessary by enactment 
of the Water Resources Development Act of 1976 were 
requested on Jan. 12, 1977. The Board of Commissioners 
of the Port of New Orleans, by letter dated Sep. 18, 
1978, stated that they are unable to provide the 
required supplemental assurances at this time. They 
are concerned about the possible effects of the 
proposed new Inner Harbor Navigation Canal Lock on 
this project and pending legislation concerning local 
assurances for the Inner Harbor Navigation Canal 
project. Local interests have provided right of entry 
for construction for the Baptiste Collette Bayou 
portion of this project. 
Terminal facilities. The only facility on the waterway 
is the Public Bulk Terminal of New Orleans 
constructed by Board of Commissioners, Port of New 
Orleans, on left descending bank at mile 63. Two newcontainer 
ship berths have begun operation at the 
Industrial Canal end of the seaway. 
Operations and results during fiscal year. New 
work by hired labor: Engineering environmental and 
economic studies were completed for the new lock and 
connecting channels feature. One contract for 
foreshore protection, south bank, Chalmette Area, 
station 367 to 1007 was completed October 1986. 
Maintenance dredging under four contracts in the 
Gulf Entrance Channel, Breton Sound and Michoud 
Canal include the removal of 8,013,786 cubic yards of 
material at a cost of $3,860,009. 
Condition as of Sep. 30. Construction was initiated 
March 1958 and entire project is 75 percent complete. 
The channel was opened to navigation Jul. 25, 1963, 
and completed Jan. 20, 1968. Paris Road Bridge was 
opened to traffic Jul. 21, and completed Nov. 14, 1967. 
Approximately 3 miles of first- and second-lift stone 
dikes have been constructed on north side of channel 
and approximately 8.27 miles of first-lift and 7.34 
miles of second-lift stone dikes have been constructed 
on south side of channel in Breton Sound. Principal 
work required to complete project, construction of new 
ship lock, raising and extending dikes, is in a deferred 
status and construction of foreshore protection is 
scheduled to be initiated in June 1985. The site for the 
lock remained the major problem. President Carter, as 
a result of his review of water resource projects in 
April 1977, changed the site for the proposed shiplock 
to the Industrial Canal in Orleans Parish and recommended 
that, if justified, the existing lock should be 
replaced and expanded in place and that care should 
be taken to minimize dislocation of residents living 
adjacent to the site. These recommendations are being 
addressed in an Evaluation Report scheduled for completion 
in FY 1990. The foreshore protection is 98 
percent complete. 
4. MISSISSIPPI RIVER OUTLETS, 
VENICE, LA 
Location. In the coastal marsh area and in the 
vicinity of the Mississippi River at about miles 10 to 11 
above the Head of Passes. (Refer to NOAA Coast Chart 
No. 1361.) 
Existing project. Provides for additional navigation 
outlets in the vicinity of Venice, LA, by enlargement of 
the existing channels of Baptiste Collette Bayou and 
Grand-Tiger Passes to 14 by 150 feet with entrance 
channels in open water 16 by 250 feet and jetties to the 
6-foot-depth contour, if and when justified, to reduce 
cost of maintenance dredging. Existing project was 
completed at a cost of $10,008,400. 
Local cooperation. For details see page 11-17, 
Annual Report, FY 1980. 
Assuring Agency: Plaquemines Parish Commission 
Council. Basic assurances for the project have been 
furnished. Amended assurances covering Public Laws 
91-646 and 91-611 were received on Aug. 5, 1977. 
Terminal facilities. In the Venice area, each 
operator of a construction, repair, or supply facility 
provides dock and transfer facilities to meet his own 
needs or arranges to use those of another. These 
facilities are considered adequate for the anticipated 
traffic. If new industry or supply facilities are 
established, they would provide any needed terminal 
facilities for their use. Ample areas for future 
expansion are available. 
Operations and results during fiscal year. Hired 
labor work consisted of reconnaisance surveys, 
condition and operation, stream gaging and engineering 
11-4

NEW ORLEANS, LA, DISTRICT 
studies. One contract for maintenance dredging at 
Baptiste Collette Bar Channel, was completed August 
1986, included the removal of 1,377,189 cubic yards at 
a cost of $576,000. 
Condition as of Sep. 30. The project is 100 percent 
complete. 
5. WATERWAY FROM 
INTRACOASTAL WATERWAY 
TO BAYOU DULAC, LA (Bayous 
Grand Caillou and LeCarpe, LA) 
Location. Bayou LeCarpe is a tidal stream which 
rises about 1.5 miles southeast of Houma in 
Terrebonne Parish and flows southerly into Bayou 
Pelton, thence into Bayou Grand Caillou,,which flows 
southwesterly into Caillou Bay, a total distance of 
about 40 miles. (Refer to Coast and Geodetic Survey 
Chart, No. 1116 and Geological Survey maps of 
Houma, Dulac, Bayou DuLarge, and Dog Lake 
quadrangles.) 
Existing project. As modified, provides for a 10- by 
45-foot channel in Bayou LeCarpe from Gulf Intracoastal 
Waterway 2.6 miles to Houma navigation 
canal; a 5- by 40-foot channel through Bayou Pelton 
and Bayou Grand Caillou to Bayou Dulac, a distance of 
about 13.7 miles. Between miles 2.6 and 5, this project 
coincides with or is adjacent to 15- by 150-foot Houma 
navigation canal. Normal range of tide is 3 to 10 
inches; from winds, 1 to 3 feet. Cost of new work, 
completed in August 1964, was $129,662. 
Local cooperation. Local interests must furnish 
lands, easements, and rights-of-way necessary for 
enlargement and subsequent maintenance of Bayou 
LeCarpe and of aids to navigation, and provide alterations 
to facilities, and hold the United States free from 
-damage. Assurances were furnished and accepted. 
Local agency made available spoil areas for maintenance 
dredging of Bayou LeCarpe. None of these areas 
will be transferred to the United States. Meeting are 
continuing with local interests to resolve problems 
with their required cash contribution on total project 
cost. 
Terminal facilities. Many terminal and transfer 
facilities are in Houma and along waterways which 
flow through area between Houma and Gulf of Mexico. 
All facilities are privately owned and operated. Facilities 
are adequate for existing commerce and for 
reasonably prospective commerce. Ample space exists 
for expansion of existing facilities or for construction 
of new wharves and appurtenances. 
Operations and results during fiscal year. Hired 
labor consisted of real estate activities, reconnaissance 
surveys, and water quality studies. 
Condition as of Sep. 30. The 5- by 40-foot channel 
was constructed from January 1938 to August 1938, 
and modification of October 23, 1962, for enlargement 
of 2.54 miles of Bayou LeCarpe to 10 feet by 45 feet was 
initiated in May and completed August 1964. 
6. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization.) 
Preauthorization studies costs as of Sep. 30, 1986, 
were $512,467 for Bayou Grand Caillou. 
Flood Control 
7. GRAND ISLE AND VICINITY, LA 
Location. In south Jefferson Parish, LA, along the 
Gulf of Mexico, about 50 miles south of New Orleans 
and 45 miles northwest of southwest pass (Mississippi 
River). 
Existing project. The project provides protection 
from waves driven by hurricanes that have a 
frequency of recurrence of up to once in every 50 years. 
The plan consists of a berm and vegetated dune 
extending the length of Grand Isle's gulf shore and a 
jetty to stabilize the western end of the island at 
Caminada Pass. The dune would have a 10-foot-wide 
crown at an elevation of 11.5 feet mean sea level, 1 on 5 
side slopes, and protective vegetation. The sandfill 
berm would slope from an elevation of 8.5 feet mean 
sea level at the toe of the dune 180 feet gulfward to an 
elevation of 3 feet mean sea level and, from this point, 
would assume its natural slope to the offshore bottom. 
The jetty provided by the plan has a top width of 6 feet 
at an elevation of 4 feet mean sea level, 1 on 2 side 
slopes, and extends approximately 2,600 feet along the 
western end of the island at Caminada Pass. 
Estimated cost of project (October 1986) is $13,445,000 
Federal and $7,848,000 non-Federal, including 
$3,438,000 contributed funds. 
Local cooperation. Local interests have the responsibility 
of providing rights-of-way, 30 percent of hurricane 
protection costs, 75 percent of beach erosion costs, 
and operation and maintenance of the completed work. 
The Louisiana Legislature, by Act 833 of 1982, authorized 
the Office of Public Works of the Louisiana 
Department of Transportation and Development to 
provide the non-Federal assurances for the Grand Isle 
Hurricane Protection and Beach erosion project. On 
Jan. 11, 1983, the Louisiana State Government authorized 
the Office of Public Works to execute the required 
assurances as a co-sponsor with the Town of Grand 
Isle. The required assurances were executed on Mar. 
16, 1983, the construction rights-of-way were provided 
on May 4, 1983, and local interest provided a cash 
contribution of $2,100,000 on Jun. 1, 1983. Maintenance 
of the project is the responsibility of the local assurer. 
The local assurer will receive Federal aid for 
repairing erosion and other damage to the project for a 
period of 15 years. The average annual Federal 
maintenance cost identified in the Act of Assurances is 
$44,000; however, this is not a fixed amount. Periodic 
nourishment to repair erosion will not necessarily be 
conducted every year, but as needed, with an 
11-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
estimated frequency of one in eight years on the 
average. It is estimated that the Federal share of the 
maintenance cost will be 25 percent for the 15-year 
period. 
Operations and results during the fiscal year. 
Plans and specifications were initiated to repair 
damages caused by winter storms and three 
hurricanes. The contract is scheduled for award in FY 
87.
Condition as of Sep. 30. The project is 80 percent 
complete. 
8. LAKE PONTCHARTRAIN 
AND VICINITY, LA 
(HURRICANE PROTECTION) 
Location. In southeastern Louisiana, vicinity of 
New Orleans, in St. Charles, Jefferson, Orleans, St. 
Bernard, and St. Tammany Parishes, comprising 
lower land and water area between Mississippi River 
alluvial ridge and the Pleistocene escarpment to north 
and west. The dominant topographic feature is Lake 
Pontchartrain, a shallow landlocked tidal basin, about 
640 square miles in area and averaging 12 feet deep, 
connecting with lesser Lake Maurepas to the west and 
through Lake Borgne and Mississippi Sound to the 
gulf to the east. The lake drains about 4,700 square 
miles of tributary area. (Refer to Geological Survey 
quadrangles Yscloskey and Malheureaux Point, Drum 
Bay, Door Point, Lake Eugenie, Oak Mound Bayou, 
Mitchell Keys, Lake Eloi, and Morgan Harbor; 
Engineer quadrangles Slidell, Covington, Ponchatoula, 
Springfield, Denham Springs, Donaldsonville, 
Mt. Airy, Bonnet Carre', Spanish Fort, Chef Menteur, 
Rigolets, St. Bernard, New Orleans, and Hahnville; 
and Coast and Geodetic Survey Charts No. 1115 and 
1116. 
Existing project. Provides protection to the greater 
New Orleans area and other communities bordering 
Lake Pontchartrain from the effects of hurricanegenerated 
floods. The project is comprised of two 
major features: The Chalmette Area Plan and the 
High Level Plan. The Chalmette Area Plan consists of 
a levee and floodwall system around the Chalmette 
area and along the Mississippi River Gulf Outlet, with 
connections to the Mississippi River levees. The High 
Level Plan will provide for heightening and 
strengthening the existing hurricane protection levee 
systems in Orleans Parish and the east bank of 
Jefferson Parish, repairing and rehabilitating the 
Mandeville Seawall in St. Tammany Parish; building 
a new mainline hurricane levee on the east bank of the 
St. Charles Parish just north of US Highway 61 
(Airline Highway); raising and strengthening the 
existing levee which extends along the Jefferson-St. 
Charles Parish boundary between Lake Pontchartrain 
and Airline Highway; and deferring construction of 
the proposed Seabrook lock until its feasibility as a 
feature of the Mississippi River Gulf Outlet navigation 
project can be determined. Areas which will be 
enclosed by the levee and floodwall construction will 
be provided protection against tidal surge resulting 
from the Standard Project Hurricane (SPH). The 
estimated project cost for work (October 1986) is 
$477,000,000 Federal and $205,000,000 non-Federal. 
Local cooperation. Provide all rights-of-way; bear 
30 percent of the first cost, consisting of fair market 
value of providing all lands, easements, and rights-ofway, 
including borrow and spoil disposal areas for 
construction, accomplish alteration and relocation of 
roads, railroads, pipelines, cables, wharves, drainage 
structures, and other facilities; maintain and operate 
all works after completion; and hold and save the 
United States free from damages. See H. Doc. No. 231, 
89th Cong., 1st sess. for more detailed requirements of 
local cooperation. 
Assuring Agency: The Orleans Levee District, Lake 
Borgne Basin Levee District, St. Bernard Parish 
Police Jury, Louisiana Office of Public Works, and 
Pontchartrain Levee District. The State of Louisiana 
formed the Jefferson Levee District and assigned to it 
the Jefferson Parish levees, previously the responsibility 
of the Pontchartrain Levee District. Basic assurances 
were received from the following: Orleans Levee 
District for the entire barrier plan and that portion of 
the Chalmette area plan in Orleans Parish; 
Pontchartrain Levee District for the barrier plan; 
Lake Borgne Levee District and St. Bernard Parish 
Police Jury for the Chalmette area plan in St. Bernard 
Parish. Supplemental assurances covering Public Law 
91-646 have been received from the Orleans Levee 
District and the Pontchartrain Levee District. Lake 
Borgne Basin Levee District and St. Bernard Parish 
Police Jury have executed the supplemental assurance. 
The St. Tammany Parish portion of the project has 
been placed in an inactive status since the local 
sponsors have not provided acceptable assurances. 
Supplemental Assurances in connection with the High 
Level Plan were executed by the Orleans Levee 
District on May 29, 1985, and approved by the United 
States June 21, 1985. Supplemental Assurances have 
been forwarded to the Pontchartrain and Jefferson 
Levee Districts for execution for St. Charles and 
Jefferson Parishes respectively. The Louisiana Office 
of Public Works will coordinate the execution of these 
Supplemental Assurances with Pontchartrain and 
Jefferson Levee Districts. Supplemental Assurances 
for the High Level Plan are not required from St. 
Bernard Parish Police Jury and the Lake Borgne 
Basin Levee District for St. Bernard Parish. 
Operations and results during fiscal year. Preparation 
of design memorandums and plans and specifications 
continued by hired labor. Preparation of 
seven design memorandums are underway. Four are 
scheduled for completion in FY 87 and three in FY 88. 
A Draft Reevaluation Report (including Draft Environmental 
Impact Statement) recommending the 
tentatively selected high level plan (lieu of Barrier 
Plan) was submitted by New Orleans District to the 
Lower Mississippi Valley Division in December 1983. 
The final Reevaluation Report was submitted to 
11-6

NEW ORLEANS, LA, DISTRICT 
LMVD on Aug. 8, 1984. A Record of Decision was 
signed in February 1985 by the Office, Chief of 
Engineers. 
Condition as of Sep. 30. Construction started May 
1967 and is 68 percent complete. 
Contract work continued on nine contracts. Construction 
was initiated on three more contracts: Inner 
Harbor Navigation Canal to London Ave., Paris Road 
to South Point Levee; and Station 278 and 355. 
9. LAROSE TO GOLDEN MEADOW, 
LA (HURRICANE PROTECTION) 
Location. In coastal section of Louisiana, along 
Bayou Lafourche, and includes lands on both banks of 
the bayou from Larose to 2 miles south of Golden 
Meadow. (Refer to Geological survey quadrangles Cutoff, 
Lke Felicity, Bay Dosgris, Golden Meadow Farms, 
Bay Tambour, Mink Bayou, Caminada Pass, Leeville, 
Belle Pass, Pelican Pass, and Calumet Island; 
Engineer quadrangles New Orleans, Hahnville, Pointa-
la-Hache, Barataria, and Fort Livingston; and Coast 
and Geodetic Survey Charts Nos. 1115 and 1116 
Existing project. Provides a loop levee about 40 
miles long along both banks of Bayou Lafourche from 
Larose to South Golden Meadow; enlargement of 3 miles 
of existing levee at Golden Meadow; floodgates for 
navigation and hurricane protection in Bayou 
Lafourche at upper and lower bayou crossings; about 8 
miles of low interior levees to regulate intercepted 
drainage and seven multibarreled culverts controlled 
by flapgates. Estimated cost for new work (October 
1986) is $64,000,000 Federal and $27,400,000 non- 
Federal. 
Local cooperation. Provide without cost to the 
United States all lands, easements, and rights-of-way, 
including borrow areas and spoil disposal areas, and 
accomplish alterations to roads, pipelines, cables, 
wharves, oil wells, and any other facilities necessary 
for the construction of the project; all at an estimated 
cost of $13,822,000; bear 30 percent of the total project 
cost, a sum presently estimated at $27,400,000 consisting 
of the items listed above, and a cash 
contribution presently estimated at $13,578,000 or 
equivalent work specifically undertaken as an integral 
part of the project after authorization and in 
accordance with construction schedules as required by 
the Chief of Engineers; hold and save the United 
States free from damages due to the construction 
works; maintain and operate all the works after 
completion in accordance with regulations prescribed 
by the Secretary of the Army; and prevent any 
encroachment on ponding areas unless substitute 
storage capacity or equivalent pumping capacity is 
provided promptly without cost to the United States; 
comply with the provisions of the Uniform Relocations 
Assistance and Real Property Acquisition Policies Act 
of 1970 (Public Law 91-646) and with the provisions of 
Section 221 of the Flood Control Act of 1970 (Public 
Law 91-611) in acquiring real property. 
The Board of Commissioners of the South Louisiana 
Tidal Water Control Levee District executed the 
required Agreement of Local Cooperation on Nov. 13, 
1972, which was executed by the United States on Jul. 
10, 1973 and approved on behalf of the Secretary of the 
Army on Aug. 29, 1973. Section 38, Paragraph 1051 et 
seq., Louisiana Revised Statutes created the South 
Lafourche Levee District. The South Lafourche Levee 
District assumed the rights and obligations of the 
South Louisiana Tidal Water Control Levee District 
with respect to this project. Local interests have requested 
and received funds from the State of Louisiana 
for right-of-way acquisition and relocations required 
to support construction work. 
Operations and results during fiscal year. Work 
continued on design memorandums and plans and 
specifications by hired labor forces. Two contracts 
were awarded; Secton E-South (first lift) was 
completed April 1986, and the Larose Floodwall is 82 
percent complete. 
Condition as of Sep. 30. Construction commenced 
in February 1975 and is 52 percent complete. 
10. MORGAN CITY AND 
VICINITY, LA 
(HURRICANE PROTECTION) 
Location. In south-central Louisiana, Morgan City 
proper, and the adjacent areas. It includes the land 
south of Grand Lake, Six Mile Lake, and Lake 
Palourde extending from Morgan City westward to 
Charenton drainage and navigation canal. Lower 
Atchafalaya River and Wax Lake Outlet, the principal 
outlets for Atchafalaya Basin Floodway, traverse the 
area. Gulf Intracoastal Waterway crosses the area in 
an east-west direction. Numerous bayous and artificial 
canals excavated for drainage purposes or for access to 
oil developments exist throughout the area. (See 
Engineer quadrangles Bayou Sale, Jeanerette, Foster, 
Belle Isle, Point Au Fer, Morgan City, and Lake 
Decade; and Coast and Geodetic Survey Chart 1116.) 
Existing project. Morgan City: Construction of 
about 5.6 miles of new levees along shore of Lake 
Palourde and west bank of Bayou Ramos and about 0.5 
mile of new levee from Southern Pacific railroad 
embankment near Wyandotte to tie in with Bayou 
Boeuf lock levee, and construction of three gravity 
drainage structures. 
Franklin and vicinity: Enlargement of about 21.6 
miles of back levee and construction of about 3.5 miles 
of new levees to effect a complete closure of area to be 
protected, construction of one floodgate and eight 
gravity drainage structures, and alteration of existing 
drainage facilities where necessary. Normal range of 
tide is 1.6 feet. Storm and hurricane tide have produced 
elevations up to 10 feet while northerly storms 
during winter depress the gulf level as much as 3 feet 
below mean sea level. During low water periods on 
Atchafalaya River, generally September through 
November, the effect of tide extends about 35 miles 
11-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
above Morgan City. Estimated cost for total project 
(October 1986) is $27,700,000 Federal and $14,950,000 
non-Federal. 
Local cooperation. Local interest must furnish 
lands, easements, and rights-of-way for construction 
and future maintenance, provide relocations and alterations 
required for project; provide all interior 
drainage and pumping plants required for reclamation 
and development of protected areas; maintain and 
operate all project works after completion including 
levees, drainage structures, floodgates and drainage 
ditches or canals, in accordance with regulations 
prescribed by the Secretary of the Army; provide 
assurances that encroachment on existing ponding 
areas will be prevented unless substitute storage 
capacity or equivalent pumping capacity is provided 
promptly, without cost to the United States; contribute 
in cash or equivalent work not less than 30 percent of 
project cost, the final determination to be made after 
construction is complete; and hold and save the United 
States free from damages due to construction works. 
Assuring Agency: The act of assurance and supporting 
resolution from the St. Mary Parish Police 
Jury were accepted for and on behalf of the United 
States on Jul. 18, 1968. Supplemental assurances were 
furnished by the St. Mary Parish Police Jury for the 
Morgan City Area separable feature of the project. 
These supplemental assurances include the additional 
items of local cooperation required by PL 91-611 and 
PL 91-646 and were accepted on behalf of the United 
States on Jul. 23, 1980. The Franklin Area feature was 
specifically excluded in the supplemental assurances. 
Operations and results during period. The GDM 
for the Morgan City area was completed in FY 1985. 
Condition as of Sep. 30. Construction has not 
commenced. 
11. NEW ORLEANS TO VENICE, LA, 
HURRICANE PROTECTION 
Location. Includes land subject to inundation by 
hurricane tides extending along both banks of the 
Mississippi River below New Orleans from vicinity of 
Phoenix to Venice, LA. 
Existing project. Provides for improvements along 
Misisissippi River below New Orleans, LA, for prevention 
of hurricane tidal flood damages by increasing 
heights of existing back levees and modifying existing 
drainage facilities where necessary in three separate 
reaches: Reach A, on the west bank from City Price to 
Empire, 15 miles, 4,340 acres protected; Reach B, on 
the west bank from Empire to Venice, 21 miles, 4,900 
acres protected; and Reach C, on the east bank from 
Phoenix to Bohemia (construction recently completed 
by local agency with credit given as equivalent work), 
16 miles, 5,470 acres protected, and construction of a 
barrier levee on the east bank of the Mississippi River 
from Bohemia to mile 10 AHP with enlargement of the 
west bank Mississippi River levee from Fort Jackson 
to Venice, generally called the East Bank Barrier 
Levee plan. Reach B was later divided into two units, 
Reach B-1 from Empire to Fort Jackson and Reach B- 
2 from Fort Jackson to Venice, LA, as a result of a 
request made by the local agency. 
Estimated cost of new work (October 1988) is 
$167,000,000 Federal and $72,000,000 non-Federal, 
including $59,175,000 cash contributions or equivalent 
work. 
Local cooperation. Provide all lands, easements 
and rights-of-way including borrow areas and spoil 
disposal areas necessary for the construction of the 
project, at costs presently estimated at $4,888,000; 
accomplish all necessary alterations and relocations to 
roads, pipelines, cables, wharves and other facilities 
required by the construction of the project at costs 
presently estimated at $7,437,000; bear 30 percent of 
the first cost, a sum presently estimated at $70,000,000, 
and cash contribution presently estimated at 
$57,550,000 to be paid either in a lump sum prior to 
initiation of construction or in installments prior to 
start of pertinent work items, in accordance with 
construction schedules as required by the Chief of 
Engineers, or as a substitute for any part of the cash 
contribution, accomplish in accordance with approved 
construction schedules items of work of equivalent 
value as determined by the Chief of Engineers, the 
final apportionment of costs to be made after actual 
costs and values have been determined; hold and save 
the United States free from damages due to the 
construction works; maintain and operate all works 
after completion in accordance with regulations 
prescribed by the Secretary of the Army; prevent any 
encroachment on ponding areas unless substitute 
storage capacity or equivalent pumping is provided 
promptly; and at least annually, notify those affected 
that the project will not provide complete protection 
from tidal floodingand that further local actions must 
be taken during hurricane emergencies. 
Local interests are also required to comply with the 
provisions of the Uniform Relocation Assistance and 
Real Property Acquisition Policies Act of 1970 (PL 91- 
646), in acquiring real property. 
PL 91-611. Not applicable. Construction started 
prior to Jan. 1, 1972. 
PL 91-646. A constitutional amendment was 
provided by the Louisiana legislature on Feb. 1, 1972 
allowing local interests to comply. The estimated cost 
to local interests is $48,000. 
Assurances of local cooperation for Reaches A, B-i, 
B-2 and C, requested on Jan. 7, 1963, were furnished 
by the Plaquemines Parish Commission Council on 
Mar. 6, 1964. Required supporting papers were furnished 
on Mar. 16, 1965 and accepted. Supplemental 
assurances covering the requirements of PL 91-646 
were received from Plaquemines Parish Commission 
Council on May 23, 1973 and accepted on Jun. 20, 1973. 
Assurances for the entire project have been 
furnished and accepted, although they do not 
specifically mention the East Bank Barrier Levee 
11-8

NEW ORLEANS, LA, DISTRICT 
Plan. The scope of the project has not changed; 
however, local interests were requested to furnish 
separate assurances for the East Bank Barrier Levee. 
By letter dated Feb. 5, 1985, the local sponsor 
requested the Corps of Engineers to defer work on the 
design of Reach A and direct efforts toward earliest 
possible construction of a barrier levee or a suitable 
alternative thereto. The local sponsor expressed a 
willingness to provide supplemental assurances for the 
Barrier Levee. 
There was a delay of approximately 26 months in the 
furnishing of assurances by local interests primarily 
because they desired that agreement on levee 
alignment be consummated as fully as possible before 
giving their assurance. Problems of assurance of local 
cooperation have been resolved and rights-of-way were 
furnished for the first two Reach B-1 items of work on 
Aug. 23, 1968 and May 20, 1970, respectively. 
All negotiations for relocations are the responsibility 
of local interests. These mainly consist of raising 
several petroleum and natural gas pipelines to the 
levee configuration and relocation of privately owned 
frame structures used as fishing and boating camps. 
To assure that there will be no delay in construction of 
levees, local interests are notified well in advance so 
that the owners of the pipelines can be advised. 
Assuring Agency: Plaquemines Parish Commission 
Council. Assurances for all reaches of the project, 
except the East Bank Barrier levee, have been 
furnished. 
Operations and results during fiscal year. Work 
continued on the GDM for the East Bank Barrier 
Levee and is approximately 75 percent complete. 
Plans and specifications for segments of Reaches B-1, 
B-2 and C were initiated and are continuing. 
Construction during FY 86 included Reach B-1 
Levee, Sta. 373+00 to Sta. 635+00, completed in April 
1986; Reach B-2, Sta. 1+00 to 279+00 and Sta. 287+00 
to Sta. 481+51, awarded Sep. 24, 1986; and Reach C, 
Sta. 552+00 to Sta. 834+39, third lift, initiated Aug. 
1986. 
Condition as of Sep. 30. Construction began on the 
project in September 1968 and the total project is 
approximately 32 percent complete. 
12. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Various hurricane protection projects, as well as 
small flood control projects, were inspected during FY 
1986. Also, periodic inspection and continuing evaluation 
of completed civil works structures was 
conducted in accordance with ER 1110-2-100, at 
various times during the year on an as-needed basis. 
Fiscal year costs for the period were $247,200. Total 
costs to Sep. 30, 1986, were $1,959,827. 
13. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Disaster preparedness, FY costs for the period were 
$140,520. Emergency Operations: Total costs to Sep. 
30, 1986 were $737,379. 
General Investigations 
14. ACTIVE INVESTIGATIONS 
See Table 11-J which covers: Surveys, Collections 
and study of basic data, and Research and Development 
activities. 
11-9

TABLE 11-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
1. Leland Bowman 
Lock, LA 
(Replacement 
of lock) 
2. Mississippi 
River, Baton 
Rouge to the 
Gulf of 
Mexico, LA 
3. Mississippi 
River-Gulf 
Outlet, LA 
(Regular Funds) 
(Contrib. Funds) 
4. Mississippi 
River Outlets, 
Venice, LA 
5. Waterway from 
Intracoastal 
Waterways to 
Bayou Dulac, 
LA (Bayou 
Grand Caillou & 
LeCarpe, LA) 
7. Grand Isle 
and Vicinity, 
LA 
(Contrib. Funds) 
8. Lake Pontchartrain 
and vicinity, 
LA (Hurricane 
Protection) (Regular 
Funds) 
(Contrib. Funds) 
9. Larose to Golden 
Meadow, LA 
(Hurricane 
Protection) 
(Contrib. Funds) 
10. Morgan City and 
vicinity, LA 
(Hurricane 
Protection) 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
$ 14,000,000 
12,697,628 
900,000 
1,545,117 
10,325,000 
8,341,621 2,578,556 447,155 
800,000 4,000,000 13,251,000 
878,037 1,192,445 16,022,664 
45,611,260 48,510,600 39,039,920 24,957,067 
43,786,783 47,713,135 41,229,463 25,630,318 
2,005,000 
1,027,035 
11,048,000 
14,717,186 
500,000 
1,664,718 
9,705,000 
10,169,620 
2,200,000 
1,286,205 
4,429,000 
4,515,392 
121,500 
77,500 
6,933,000 
7,684,892 
6,663,500 
6,808,104 
-2,900 - - - 
340 - - 0 
2,196,000 1,423,000 2,832,000 1,240,276 
2,227,642 1,394,421 2,881,422 1,239,090 
75,000 
111,102 
40,000 
43,223 
3,000,000 4,161,000 
226,231 6,714,791 
- 2,110,000 
- 2,000,000 
228,000 
177,151 
-21,000 
-21,000 
432,000 
653,469 
100,000 
100,000 
56,395 
31,470 
30,669 
1,000,000 
735,330 
70,000 
70,000 
13,716,000 8,800,000 11,158,000 20,358,000 
13,510,392 7,937,422 10,382,763 21,676,920 
313,124 
356,602 
325,000 
260,000 
195,000 
260,000 
510,988 
1,102,053 
9,870,000 5,700,000 5,865,000 4,221,000 
7,734,710 6,901,800 7,441,971 4,073,880 
6,139 
384,000 
541,000 
387,000 
367,606 
182,000 
182,000 
280,000 
221,260 
-79,000 
21,762 
$ 32,200,0101 
31,896,976' 
58,162,7972 
58,624,5522 
468,003,9113,5 
467,632,3824,5 
88,273,200 
88,066,982 
102,314,080 
102,238,928 
1,240,4776 
1,196,4776 
10,008,093 
10,008,100 
9,891,076 
9,871,063 
637,622 
641,076 
899,232 
898,431 
9,342,500 
9,005,680 
2,280,000 
2,170,000 
181,596,000 
180,077,548 
4,321,172 
4,953,729 
42,188,000 
40,754,605 
2,271,721 
2,243,268 
1,953,000 
1,975,628 
11-10

NEW ORLEANS, LA, DISTRICT 
TABLE 11-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1985 
11. Mississippi New Work 
River Delta at Approp. 3,450,000 2,830,000 1,920,000 971,000 54,360,000 
and below New Cost 2,515,286 3,581,564 1,630,947 1,449,660 54,320,117 
Orleans, LA (New 
Orleans to Venice, 
LA, Hurricane 
Protection) (Regular 
Funds) 
(Contrib. Funds) New Work 
Contrib. 3,050,000 - - 1,368,989 4,785,419 
Cost 2,600,000 450,000 - 984,106 4,400,536 
1. Includes AE&D funds for replacement of Vermilion 
Lock. 
2. Includes $1,729,989 for previous project. 
3. Does not include allotment of $40,000 (9613123). 
4. Does not include expenditures of $63,370 (9613123). 
5. Includes $169,055 for previous projects and $3,379,676 
from permanent indefinite appropriation. 
6. Contributed by Board of Commissioners, Port of New 
Orleans, for providing fill for future industrial sites adjacent 
to turning basin and for dredging cable and pipeline 
crossings. 
11-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 11-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
WRD Act of 
1976, dated 
Oct. 22, 1976 
(PL 94-587) 
Mar. 2, 1945 
Oct. 23, 1962 
Mar. 29, 1956 
Oct. 22, 1976 
Aug. 13, 1968 
Aug. 30, 1935 
Oct. 23, 1962 
Adopted by 
Committee 
Resolutions 
Sep. 23, 1976, 
and Oct. 1, 
19762 
Oct. 27, 1965 
LELAND BOWMAN LOCK, LA (REPLACEMENT OF 
LOCK) (FORMERLY VERMILION LOCK) (See Sec. 1 of 
Text) 
A replacement lock, 110 feet wide and 1,200 feet long, to 
accommodate present and projected marine traffic. 
MISSISSIPPI RIVER, BATON ROUGE TO GULF OF 
MEXICO, LA (See Sec. 2 of Text) 
Combines projects of Mississippi River, Baton Rouge to New 
Orleans, Mississippi River, South Pass, and Southwest Pass, 
adding thereto project for Mississippi River from New Orleans 
to Head of Passes, to provide a single project, "Mississippi 
River, Baton Rouge to the Gulf of Mexico," with channel 
dimensions as follows: Baton Rouge to New Orleans, 35 by 500 
feet; port limits of New Orleans, 35 by 1,500 feet; New Orleans 
to Head of Passes, 40 by 1,000 feet, Southwest Pass, 40 by 800 
feet; Southwest Pass Bar Channel, 40 by 600 feet; South Pass, 30 
by 450 feet; South Pass Bar Channel 30 by 600 feet. 
Deepen existing channel from 35 to 40 feet by 500 feet wide from 
one-tenth mile below Louisiana Highway Commission bridge at 
Baton Rouge to upper limits of Port of New Orleans, and also 40 
by 500 feet within presently authorized 35- by 1,500-foot 
channel in port limits of New Orleans. 
MISSISSIPPI RIVER-GULF OUTLET, LA (See Sec. 3 of 
Text) 
Construct a seaway canal 36 feet deep and 500 feet wide from 
Michoud to 38-foot contour in gulf and an inner tidewater 
harbor consisting of a 1,000- by 2,000-foot turning basin 36 feet 
deep and a connecting channel 36 feet deep and 500 feet wide to 
Inner Harbor Navigation Canal and provides, when 
economically justified, for construction of a lock to Mississippi 
River in the vicinity of Meraux, LA. 
Amends above Act making the construction of bridge relocations 
a Federal responsibility when required by the construction of 
the Mississippi River-Gulf Outlet channel. 
MISSISSIPPI RIVER OUTLETS, VENICE, LA (See Sec. 4 
of Text) 
Enlargement of existing channels of Baptiste Collette Bayou and 
Grand-Tiger Passes to 14 by 150 feet with 16 by 250-foot 
entrance channels in open water and jetties, if justified. 
WATERWAY FROM INTRACOASTAL WATERWAY TO 
BAYOU DULAC, LA (Bayous Grand Caillou and LeCarpe, 
LA) (See Sec. 5 of Text) 
Channel 5 by 40 feet from Intracoastal Waterway at Houma 
through Bayou LeCarpe, Bayou Pelton, and Bayou Grand 
Caillou to Bayou Dulac, about 16,3 miles. 
Channel 10 by 45 feet in Bayou LeCarpe from Gulf Intracoastal 
Waterway to Houma navigation canal. 
GRAND ISLE AND VICINITY, LA (See Sec. 7 of Text) 
To provide hurricane protection by placement of a berm and 
vegetated dune extending the length of Grand Isle's gulf shore 
and a jetty to stabilize the western end of the island at 
Caminada Pass. 
LAKE PONTCHARTRAIN AND VICINITY, LA 
(HURRICANE PROTECTION) (See. Sec. 8 of Text) 
Control of hurricane tides by construction of two independent 
units, the Lake Pontchartrain Barrier plan and the Chalmette 
Area plan. 
Approved by Secretary of 
the Army, May 1967, 
under authority of the 
R&H Act of 1909. 
H. Doc. 215, 76th Cong., 1st 
sess.1 
S. Doc. 36, 87th Cong., 1st 
sess. 
H. Doc. 245, 82d Cong., 1st 
sess. 
Sec. 186, Water Resources 
Development Act of 1976 
(PL 94-587) 2d sess. 
H. Doc. 304, 90th Cong., 2d 
sess. 
H. Doc. 206, 72d Cong., 1st 
sess. 
H. Doc. 639, 94th Cong., 2d 
sess. 
H. Doc. 231, 89th Cong., 1st 
sess. 
11-12

NEW ORLEANS, LA, DISTRICT 
TABLE 11-B 
(CONTINUED) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
LAROSE TO GOLDEN MEADOW, LA (HURRICANE 
PROTECTION) (See Sec. 9 of Text) 
Oct. 27, 1965 A loop levee about 36 miles long along both banks of Bayou H. Doc. 184, 89th Cong., 1st 
Lafourche from Golden Meadow to Larose; enlargement of 3 sess. 1 
miles of existing levee at Golden Meadow; floodgates for 
navigation and hurricane protection in Bayou Lafourche at 
upper and lower bayou crossings; about 8 miles of low interior 
levees to regulate intercepted drainage; and seven 
multibarreled culverts controlled by flapgates. 
MORGAN CITY AND VICINITY, LA, HURRICANE 
PROTECTION (See Sec. 10 of Text) 
Oct. 27, 1965 Construction of new levees along Lake Palourde and Bayou H. Doc. 167, 89th Cong., 1st 
Ramos, levee to tie-in with Bayou Boeuf lock levee and three sess. 
gravity drainage structures in Morgan City unit and 
enlargement of bank levee, construction of new levee, and 
construction of one floodgate and five gravity drainage 
structures in Franklin and vicinity unit. 
NEW ORLEANS TO VENICE, LA, HURRICANE 
PROTECTION (See Sec. 11 of Text) 
Oct. 23, 1962 Improvements along Mississippi River below New Orleans, LA, H. Doc. 550, 87th Cong., 2d 
for prevention of hurricane tidal flood damages by increasing sess. 
heights of existing back levees and modifying existing drainage 
facilities where necessary in five separate reaches. 
1. Contains latest published map. 
2. Permanent Appropriation Repeal Act. 
11-13

TABLE 11-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sep. 1986 
For Last Mo. and Yr. 
Full Report Operation Completed 
See Annual and Deauthorized 
Project Status Report For: Construction Maintenance or Reclassified 
Alteration of Berwick Bay Bridge1 
Amite River and Bayou Manchac, LA 
Aquatic Plant Control Program, LA 
Atchafalaya River Bayous Chene Boeuf, 
and Black, LA 
Atchafalaya River, Morgan City to Gulf 
of Mexico, LA 
Baton Rouge Harbor, 
Segment between Mi. 2.5 and 5.02 
Barataria Bay Water, LA 
Bayou Bonfouca, LA 
Bayou Dorcheat, Loggy Bayou and 
Lake Bisteneau, LA 3,4,5,6 
Bayou Dupre, LA7 
Bayou Grosse Tete, LA8 
Bayou Lacombe, LA 
Bayou Lafourche and Lafourche Jump 
Waterway, LA 
Bayou La Lautre, St. Malo, and 
Yscolskey, LA 
Bayou Plaquemine Brule, LA 
Bayou Queue de Tortue, LA 
Bayou Segnette Waterway, LA 
Bayou Teche, LA 
Bayou Teche & Vermilion River, LA 
Bayou Terrebonne, LA4 9 
Bayou Vermilion, LA 4 
Big Pigeon and Little Pigeon 
Bayous, LA 3 
Calcasieu River and Pass, LA 
Calcasieu River at Coon Island, LA 1o 
Calcasieu River at 
Devil's Elbow, LA 
Cascasieu River Salt Water 
Barrier, LA 11 
Cane River, LA'3,6 
Chefuncte River and Bogue Falia, LA 
Cypress Bayou and Waterway between 
Jefferson, TX, and Shreveport, LA 12 
Freshwater Bayou, LA 
Grand Bayou Pass, LA 
Gulf Intracoastal Waterway 
between Apalachee Bay, FL & 
Mexican Border 
Houma Navigation Canal, LA 
Inland Waterway from Franklin 
to Mermentau River, LA1" 3 
Intracoastal Waterway from the 
Mississippi River to 
Bayou Teche, LA 14 
Lake Borgne and Chef Menteur- 
Bulkheads and Jetties 
Lake Charles Deep Water Channel, LA'5 
Little Caillou Bayou, LA 
Mermentau River, Bayou Nezpique, and 
Bay Des Cannes, LA 
Mermentau River, LA 
Complete 
Complete 
Complete 
Complete 
Deauthorized 
Complete 
Complete 
Complete 
Deauthorized 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Deauthorized 
Complete 
Complete 
Complete 
1967 
1978 
1984 
1984 
1981 
19462 
1984 
1974 
1887 
1968 
1967 
1984 
1970 
1950 
1970 
1958 
1984 
1983 
1961 
1947 
1936 
1984 
1976 
1981 
1973 
1910 
1967 
1971 
1984 
1950 
1985 
1984 
1960 
1956 
19422 
1950 
1973 
1977 
1985 
28,234 
11,768,376 
30,353,236 
501,963 
1,572,685 
30,997 
5,000 
38,915 
1969 
4,716 
1,624,424 
96,916 
33,410 
33,355 
238,828 
754,330 
2,891,822 
120,089 
34,900 
27,807,310 
1,015,81410 
5,856,200 
4,197,262 
2,500 
58,342 
202,817 
7,116,224 
7,676 
69,087 
39,822,427 
17,946,706 
320,758 
104,1877 
123,454 
119,191 
829,756 
223,616 
36,780 
28,315 
213,455 
4,440,688 
1,668,036 
251,691 
200,169 
37,169 
98,196,595 
2,000 
463,401 
452,611 
15,491,840 
14,48012 
63,284,470 179,937,233 
- 18,827,749 
249,052 
77,761 
5,197,97516 
4,672,579 
552,780 
11,699 
241,896 
751,485 
114,519 
17,436,233 
11-14 
1928 
1914 
Nov. 1979 
Nov. 1963 
1931 
1939 
May 1981 
1938 
May 1956 
1915 
March 1923 
March 1957 
1916 
1896 
3 
Oct. 1968 
April 1974 
Sep. 1978 
Jan. 1968 
1959 
Dec. 1914 
Aug. 1968 
1939 
Nov. 1979 
1929 
Jul. 1952

NEW ORLEANS, LA, DISTRICT 
TABLE 11-C 
(CONTINUED) 
OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sep. 1986 
For Last Mo. and Yr. 
Full Report Operation Completed 
See Annual and Deauthorized 
Project Status Report For: Construction Maintenance or Reclassified 
Mississippi River-Gulf Outlet, 
Michoud Canal, LA Complete 1976 2,499,555 - Nov. 1974 
Navigation work under special 
authorization (Calcasieu Pass 
channel in Old River Bend 
at Cameron, LA)17 - 1957 - 139,755- 
Pass Manchac, LA Complete 1950 79,845 13,545 1912 
Petite Anse, Tigre, and 
Carlin Bayous, LA Inactive 1981 - 1,450,172 Nov. 1980 
Removal of Aquatic Growth, LA 1984 - 22,870,845 
Sulphur River, AR and TX 3,6 - 1919 45,989 -- 
Tangipahoa River, LA - 1985 - 618,501- 
Tickfaw, Natalbany, Ponchatoula, 
and Blood Rivers, LA4 Complete 1973 8,115 92,163 1921 
Vinton Waterway, LA21 Deauthorized 1950 - - Nov. 1979 
Waterway from White Lake to 
Pecan Island, LA 13 - 1948 10,904 0,742 
Waterway from Empire, 
LA, to Gulf of Mexico Complete 1981 1,068,142 849,238 Jun. 1950 
1. Transferred to Department of Transportation. 
Authorized under Truman-Hobbs Act. 
2. Date authorized. 
3. Completed. Date will be furnished when available. 
4. Includes previous project costs. 
5. No commerce reported. 
6. Abandonment recommended in H. Doc. 467, 69th 
Cong., 1st sess. 
7. Includes $56 cost incurred in 1969. 
8. Completed except that portion above mile 10.3 
providing for widening from 40 feet to 60 feet, which is 
inactive. 
9. By Public Law 88-404, that portion of Bayou Terrebonne 
between point where Barrow Street crosses said 
stream and a line determined by prolonging and extending 
eastern right-of-way line of New Orleans Boulevard 
southerly to south bank of said stream was declared 
nonnavigable. 
10. Includes $66,000 contributed funds. 
11. Operation and maintenance of the structure 
reported under project "Calcasieu River and Pass, LA." 
12. Excludes $50,000 contributed funds. 
13. Not completed; incorporated in navigation project 
"Mermentau River, LA." 
14. Not completed; superseded for most of its length by 
present 12- by 125-foot Gulf Intracoastal Waterway, which 
coincides with or parallels it. 
15. Maintenance project; no future work schedules. 
16. Includes $57,555 ($29,974 of which was from Public 
Works funds) for new work on previous project. Includes 
$114,519 for maintenance of previous project. 
17. Work is under continuing authority. 
11-15

TABLE 11-D 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
For Last Cost to Sep. 1986 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Aloha-Rigolette Area, Grant and 
Rapides Parishes, LA 1 
Amite River and Tributaries, LA 
Bayou Bodcau, Red Chute, and Loggy 
Bayou, LA 1,12 
Bayou Choupique, LA3 
Bayou Nicholas, Coushatta, LA3 
Bayou Pierre in vicinity of 
Shreveport, LA",2,12 
Bayou Rapides, LA3 
Black Bayou Reservoir, LA 1,4 ,5 ,12 
Black Bayou-Pine Island Area, LA 3 
Campti-Clarence Area in Natchitoches 
Parish, LA 
Choctaw Bayou and Tributaries, LA 1,7 ,12 
Colfax, Grant Parishes, LA1,7 
Cooper Lake and Channels, TX8 
East Point, LA 
Ferrells Bridge Dam-Lake 0' the Pines, 
TX8.9 
Garland City, AR' 2 
Grant Parish below Colfax, LA1, 9 
Harvey Canal, Bayou Barataria Levee, LA 
Hempstead County Levee District No. 1, 
AR.1.9,12 
Maniece Bayou, AR.",2 ,u 
McKinney Bayou, Finn Bayou 
Segment, AR."' 2 
Natchitoches Parish, LA' ,2 
Pineville, Red River, LA" 3" 2 
Posten Bayou, AR."' 2 
Red River Parish, LA",9,12 
Red River in vicinity of Shreveport, LA',12 
Saline Point, LA",9 
Aug. 1977 
1956 
1964 
1948 
1954 
1964 
1951 
1952 
1945 
1963 
1978 
1977 
1938 
1979 
1969 
1979 
1976 
1941 
1979 
1941 
1970 
196310 
1956 
1953 
1973 
1939 
1953 
1945 
$ 1,653,189 
3,034,2552 
319,200 
129,930 
70,717 
243,3362 
95,179 
336,063 
1,655,700 
741,892 
70,348 
20,839,300 
486,069 
14,175,197 
1,335,842 
38,809 
1,018,005 
88,006 
970,9322 
1,529,478 
232,426 
149,435 
3,908,000 
124,111 
11-16 
Apr. 1955 
Feb. 1964 
Jan. 1948 
Mar. 1954 
Jun. 1964 
Jun. 1939 
Dec. 1951 
May 1963 
Jul. 1978 
Apr. 1976 
8,301,021 
Aug. 1968 
Jul. 1974 
9
9 
Aug. 1969 
Aug. 1955 
Dec. 1951 
Mar. 1953

NEW ORLEANS, LA, DISTRICT 
TABLE 11-D 
(CONTINUED) 
OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
For Last Cost to Sep. 1986 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Twelvemile Bayou, LA3 
Wright Patman Dam and Lake, TX8 
1966 
1979 
1. Authorized under project "Red River Below Denison 
Dam."
2. In addition, the following was expended from contributed 
funds: 
Amite River and tributaries .............. $ 430 
Bayou Pierre in vicinity of 
Shreveport, LA ....................... 89,047 
Choctaw Bayou and Tributaries, LA ...... 170,799 
Harvey Canal, Bayou Barataria 
Levee, LA .......................... 425,209 
Maniece Bayou, AR ..................... 39,293 
Natchitoches Parish, LA ................. 250,000 
3. Authorized by Chief of Engineers. (Sec. 205, 1948 
Flood Control Act, as amended.) 
4. Construction not initiated. 
5. Inactive. 
335,433 
35,659,176 11,195,021 
May 1965 
6. Includes $92,000 for preauthorization studies. 
7. Completed under provisions of Sec. 7, Flood Control 
Act 1928, as amended by Sec. 9, Flood Control Act 1936, and 
included in 1939 Annual Report of President, Mississippi 
River Commission, p. 2214. 
8. These projects transferred to the Fort Worth District, 
Southwestern Division, during FY 1979. 
9. Completed. Date will be furnished when available. 
10. Date authorized. 
11. Posten Bayou Project, authorized by Senate and 
House Resolutions, Dec. 17 and 15, 1970, deleted the plan 
authorized by the Flood Control Act dated Aug. 3, 1955. 
12. These projects transferred to the Vicksburg District 
during FY 1983. 
11-17

TABLE 11-E 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
ACTIVE GENERAL INVESTIGATIONS 
(96x3121) 
Federal Cost Totals by 
Item and CWIS Number FY 86 Categories 
SURVEYS (Category 100) 
Navigation (110) 
Bayou Lafourche & Lafourche-Jump Waterway, LA -1009 
GIWW LA & TX Section -10032 
Flood Control Studies (120) 
Aloha-Rigolette Area, LA -12123 
Amite River & Tributaries, LA -50100 
Lake Pontchartrain-West Shore, LA -79700 
Louisiana Coastal Area, LA, Land Loss & Marsh Creation -12348 
Louisiana Coastal Area, LA, Shore & Barrier Island Erosion -12354 
Louisiana Coastal Area, LA, Water Supply -12355 
Mermentau, Vermilion & Calcasieu Rivers & Bayou Teche, LA -34014 
West Bank of Mississippi River-Vicinity of New Orleans, LA -59360 
Review of Authorized Projects (160) 
Deauthorization Review -77000 
Miscellaneous Activities (170) 
Special Investigations -17250 
Coordination Studies with Other Agencies (180) 
Planning Assistance to States (186) -51850 
Planning Assistance to States (186) -14822 
TOTAL (Category 100) 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) 
Flood Plain Management Services 
TOTAL (Category 200) 
CONTINUATION OF PLANNING AND ENGINEERING (Category 400) 
Lake Pontchartrain-North Shore, LA -12349 
Mississippi River-Ship Channel, Gulf to Baton Rouge, LA (55270) 
TOTAL (Category 400) 
GRAND TOTAL GENERAL INVESTIGATIONS 
11-18 
$ 51,997 
$ 423,903 
475,900 
6,105 
294,730 
1,230 
161,614 
239,516 
179,986 
133,271 
241,513 
1,257,965 
13,081 
22,910 
232 
28,226 
28,457 
$1,798,313 
186,664 
9 
763,622 
763,631 
$2,748,608

VICKSBURG, MS, DISTRICT * 
This district comprises western and central Mississippi, 
southern Arkansas, northern Louisiana, and a 
very small portion of southwestern Tennessee, embraced 
in drainage basins of eastern tributaries of 
Mississippi River south of Horn Lake Creek to and 
including Buffalo River; Pearl River Basin in Mississippi; 
independent tributaries of the Gulf of Mexico 
south of the Buffalo River Basin to the Mississippi- 
Louisiana state line; western tributaries of Mississippi 
River between White and Atchafalaya Rivers 
including Arkansas River Basin below a point 3 miles 
upstream from Pine Bluff and Arkansas River below 
mile 36.1 near Pendleton, Arkansas; Ouachita and 
Black Rivers in Arkansas and Louisiana; and Red 
River in Louisiana and Arkansas to the Texas- 
Arkansas state line. 
IMPROVEMENTS 
Navigation 
1. Ouachita and Black Rivers below 
Camden, AR ......................... 
2. Red River emergency bank 
protection ........................... 
3. Red River Waterway-Mississippi 
River to Shreveport, LA .............. 
4. Yazoo River, MS ...................... 
5. Navigation work under special 
authorization ......................... 
Flood Control 
6. Bayou Bartholomew and 
Tributaries, AR and LA .............. 
7. Bayou Bodcau and tributaries, 
AR and LA .......................... 
8. Caddo Lake, LA ...................... 
9. Lead Bayou, MS ...................... 
10. Ouachita River Levees, LA ............ 
11. Ouachita River and tributaries 
AR and LA .......................... 
12. Pearl River Basin, MS and LA ......... 
13. Porter Bayou, MS .................... 
14. Poverty Point State Commemorative 
A rea, LA ............................ 
15. Red River Below Denison Dam 
(Vicksburg Dist.) ..................... 
16. Red River below Denison Dam, levees 
and bank stabilization 
(Vicksburg District) .................. 
Page Flood Control (cont) 
17. Red River Waterway-Shreveport, 
12-2 LA, to Index, AR .................... 
18. Inspection of completed Flood 
12-2 Control Projects ..................... 
19. Flood control work under 
12-2 special authorization ................ 
12-3 
12-3 Tables 
Table 12-A 
Table 12-B 
Table 12-C 
12-4 
12-4 
12-5 
12-5 
12-5 
12-5 
12-6 
12-6 
12-6 
Table 12-D 
Table 12-E 
Table 12-F 
Table 12-G 
Table 12-H 
12-7 Table 12-I 
12-7 
Table 12-J 
Cost and Financial Statement.. 
Authorizing Legislation ....... 
Ouachita and Black Rivers, 
AR and LA (9-Foot Project), 
Locks and Dams .............. 
Other Authorized Navigation 
Project ...................... 
Ouachita River and Tributaries 
Existing Project .............. 
Reservoir Operations 
Fiscal Year 1984 .............. 
Red River Below Denison Dam 
(Vicksburg District) 
New Projects ................ 
Red River Below Denison Dam 
(Vicksburg District) 
Incorporated Projects ......... 
Other Authorized Flood 
Control Projects .............. 
Active General Investigations .. 
Page 
12-7 
12-7 
12-8 
12-9 
12-11 
12-13 
12-14 
12-16 
12-16 
12-17 
12-18 
12-19 
12-21 
12-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. OUACHITA AND BLACK RIVERS 
BELOW CAMDEN, AR 
Location. Ouachita River rises in Polk County, AR, 
and flows southeasterly and southerly about 600 miles. 
Below its confluence with the Tensas and Little Rivers 
at Jonesville, LA, it is called Black River, which enters 
Red River 35.5 miles from the Mississippi River. 
Previous projects. See page 683 of Annual Report 
for 1962 for details. 
Existing project. See page 684 of Annual Report for 
1962 for details of the old 6.5-foot navigation project. 
New work for completed project costs $7,064,031.68, 
exclusive of amounts expended under previous 
projects. Modified project and project for Red River 
below Fulton, AR, provide for a channel 9 feet deep 
and 100 feet wide in Red River between Old River and 
mouth of Black River, and in Black and Ouachita 
Rivers from mouth of Black River to Camden, AR. 
This is being accomplished by construction of four new 
locks, 84 feet by 600 feet; new dams; channel 
realinement to accommodate the 9-foot draft tow; and 
measures to preserve Catahoula Lake for migratory 
waterfowl. The River and Harbor Act of 1970 
authorized establishment of wildlife refuges along 
Bayou D'Arbonne (14,700 acres) in connection with 
Columbia Lock and Dam and at Felsenthal Lock and 
Dam (65,000 acres). The Bayou D'Arbonne refuge was 
increased to 18,000 acres at the request of the Bureau 
of Sport Fisheries and Wildlife. Estimated cost for 
new work for 9-foot navigation project is $279,153,000 
including $269,000,000 Federal and $10,153,000 non- 
Federal for lands, damages, and relocations. 
Local cooperation. Local cooperation for all completed 
work in Louisiana has been furnished in a 
timely manner. It is anticipated that local interests in 
Louisiana will be able to supply the necessary rightsof-
way for construction of the cutoffs and bend 
widenings. Local interests in Arkansas have furnished 
the rights-of-way for the Felsenthal and Calion Locks 
and Dams and it is anticipated that the remaining 
rights-of-way will be furnished when needed. The city 
of Camden, AR, has furnished land for the Sandy 
Beach recreation area. All assurances from local 
interests including supplemental assurances (Public 
Law 91-646) have been accepted. 
Terminal facilities. Public loading docks are at 
Columbia, LA, and Camden and Crossett, AR. 
Privately owned docks and loading and unloading 
facilities are at Columbia, Monroe, and Sterlington, 
LA, and El Dorado, Calion, and Camden, AR. Two 
grain-handling facilities and a petroleum-loading 
facility are in the vicinity of Jonesville, LA, and a 
grain-handling facility is in the vicinity of Acme, LA. 
Operations and results during fiscal year. Construction 
of all the locks and dams in the project are 
now complete. Calion Access Channel Part II 
Construction Contract was initiated in FY 86. This 
contract was required due to changed site conditions 
discovered under the original contract which was 
discontinued in FY 85. The demolition contracts for 
the removal of Lock #6 and Lock #8 were completed in 
FY 86. Initiated construction of six recreation 
facilities in the Felsenthal National Wildlife Refuge 
(Felsenthal L & D access point, Calion L & D, No. 8, 
Eagle Lake Access Point, Grand Marias Phase I, 
Pereogethee Access Road, and Crossett Harbor Phase 
I). Initiated construction of the beautification and 
land-scaping at Felsenthal Lock and Dam. Initiated 
construction of the wastewater disposal system at 
Calion Lock & Dam. Maintenance dredging removed 
764,449 cubic yards of material from the Ouachita- 
Black Waterway during FY 86. 
Condition as of Sep. 30. All four locks and dams 
associated with the project are complete and in 
operation. Columbia and Jonesville Pools were opened 
to nine foot navigation in June 1972. The Felsenthal 
Lock and Dam is open to navigation. The Calion lock is 
scheduled to be open for nine foot navigation in late FY 
87. 
2. RED RIVER EMERGENCY 
BANK PROTECTION 
Location. In northwest Louisiana, southwest Arkansas, 
and northeast Texas, along the Red and Old Rivers 
between the Mississippi River and the head of the levee 
system above Index, TX. 
Existing project. Provides for realigning the banks 
by means of cutoffs and training works and for 
stabilizing banks by means of revetments, dikes, and 
other methods as emergency conditions may require in 
advance of developing the design for the entire Red 
River Waterway project. Estimated cost for new work 
(October 1986) is $65,300 Federal and $2,182,000 non- 
Federal, including a cash contribution of $7,000. 
Local cooperation. Fully complied with. For details 
see pages 11-19 to 11-20, Annual Report FY 80. 
Operations and results during fiscal year. Work 
by hired labor consisted of preparing plans and 
specifications, surveys, and general engineering. 
Construction of the Goose Lake realignment, river 
mile 407-L, was completed. Construction contracts for 
Little River Phase III revetment, river mile 405-L, and 
Oak Revetment Extension, river mile 347-R, are 
continuing. 
Condition as of Sep. 30. Construction was initiated 
in October 1972 and is 95% complete. 
3. RED RIVER WATERWAYMISSISSIPPI 
RIVER TO 
SHREVEPORT, LA 
Location. From east central to northwest Louisiana 
along the Red and Old Rivers between the Mississippi 
River and Shreveport, LA. 
Existing project. Provide a navigation route from 
the Mississippi River at the junction with Old River 
12-2

VICKSBURG, MS, DISTRICT 
via Old and Red River to Shreveport, LA, developing a 
channel approximately 236 miles long, 9 feet deep, and 
200 feet wide. The development will include five locks 
and dams, realignment and contraction of the river as 
necessary to develop an efficient channel, and bank 
stabilization as necessary to hold the newly developed 
channel in position. Facilities to provide opportunities 
for recreation and for fish and wildlife development 
are an integral part of the project. Estimated cost for 
new work is $1,564,000,000 Federal and $88,219,000 
non-federal, including $43,071,000 contributed funds. 
The Federal cost excludes $294,000 for aids to 
navigation by U.S. Coast Guard. 
Local cooperation. For details see page 11-21, 
Annual Report FY 80. 
The Red River Waterway Commission, governing 
body of the Red River Waterway District, executed an 
act of assurance for all project features in Louisiana on 
Feb. 26, 1969, supported by resolution dated Jan. 30, 
1969. The assurances were accepted for and on behalf 
of the United States on Apr. 15, 1969. The Commission 
furnished amended assurances covering the provisions 
of Public Law 91-646 on May 23, 1973, for the portion 
of the project within Louisiana which were accepted 
for and on behalf of the United States on Nov. 14, 1973. 
Terminal facilities. Local interests are to provide 
adequate terminal facilities along the waterway. The 
Corps entered into an agreement with the City of 
Alexandria, LA, whereby material excavated from the 
proposed Philip Bayou Realignment could be used as 
fill for port construction at mile 109. Construction of 
the realignment and port fill are essentially complete. 
Operations and results during fiscal year. Hired 
labor continued work on Design Memoranda, preparation 
of Plans and Specifications, Surveys, General 
Engineering, and Model Studies. Construction of the 
John H. Overton Lock and Dam reached 80 percent 
completion in November 1987. A construction contract 
for preparatory sitework at Lock and Dam #3 was 
completed, and a second contract consisting of bank 
stabilization and a portion of the cofferdam was 
awarded and is continuing. One bank stabilization 
item was awarded in Pool 3. Construction of channel 
realignment and bank stabilization works in Pools 1 & 
2 consisted of the following: Six items were completed 
- Once More realignment, Pointfield realignment, 
Raven Camp realignment, Moncla/Dupre revetment, 
Lock & Dam #1 dikes, and Lock & Dam #1 Dike 5. 
Items initiated were: Joffrion revetment, England 
realignment, Boyce revetment, Bayou Cocodrie dikes, 
Delhoste dikes, Hadden-Ft. Derussy Capout, and Larto 
ACS. Items continuing include: Meade realignment, 
Lorran Lake realignment, Philip Bayou realignment, 
and Grand Bend realignment. During FY 86, the 
contract dredge Butcher removed 897,000 cubic yards 
of material on the waterway. 
Condition as of Sep. 30. Construction was initiated 
in July 1973, and project is 40 percent complete. 
4. YAZOO RIVER, MS 
Location. Formed by junction of Tallahatchie and 
Yalobusha Rivers in Leflore County, MS, flows about 
169 miles southerly and southwesterly, and enters 
Mississippi River at Vicksburg, MS. (See Mississippi 
River alluvial valley quadrangle maps.) 
Previous projects. See page 681 of Annual Report 
for 1961 for details. 
Authorized project. The Yazoo River Navigation 
project consists of a 9-foot channel from its mouth to 
Greenwood, MS, mile 164.9 (present mileage), with a 
minimum width of 150 feet. The project includes a 
single lock (84 feet by 600 feet) and a dam located near 
Vicksburg, dredging and channel realinement; 
600,000 acre-feet of additional storage in Sardis Lake 
to augment low flows in the Yazoo River, and 
recreation features. 
Local cooperation. Requirements of local cooperation 
are fully described on page 12-3 of FY 80 Annual 
Report. 
Terminal facilities. At Greenwood there is a 
privately owned dock and a grain-loading facility. 
There are privately owned facilities for loading grain 
at Belzoni and Satartia. At Yazoo City there is a 
privately owned grain-loading facility, a private logloading 
facility, a private dock to handle dry and 
liquid fertilizer, and a public terminal. 
Operations and results during fiscal year. 
Clearing and snagging was completed. 
Condition as of Sep. 30. A portion of the river is 
navigable; however, in order for the entire system to be 
that way, alteration of the Sheppardtown Bridge will 
be necessary. No funds have been provided for this 
alteration. No work done on new authorization. Phase I 
studies are being deferred on the nine foot project due 
to lack of economic justification. 
5. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 87-645, as amended (preauthorization). 
During FY 86 detailed project studies continued on 
Union County Port, AR, at a cost of $11,820; and on 
Greenwood Port, MS, at a cost of $79,423. Plans and 
specifications were continued at Bastrop Port at a cost 
of $31,784. All three study efforts were terminated 
near the end of the FY as a result of new policy 
guidance on small ports. Funds in the amounts of $59 
and $604 were expended on two other studies at 
Yellow Bend and Two Bayou, respectively. Both 
studies were also terminated as a result of the same 
policy guidance. 
12-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Flood Control 
6. BAYOU BARTHOLOMEW AND 
TRIBUTARIES, AR AND LA 
Location. Bayou Bartholomew rises in Jefferson 
County, AR, about 10 miles northwest of Pine Bluff 
and flows southerly about 370 miles to join the 
Ouachita River upstream from Sterlington, LA. 
Authorized project. Project includes ten waterretention 
lakes in the western tributaries of Bayou 
Bartholomew in Arkansas and six local levee units 
along the main stem of Bayou Bartholomew in Louisiana. 
However, because of public opposition to construction 
of the loop levees, preconstruction planning 
of the six loop levees has been deferred until such time 
as there is sufficient support for such levees by local 
interests. Channel improvements previously 
authorized are deferred until it is determined that the 
quality and quantity of water downstream will not be 
adversely affected. Latest approved (1979) estimated 
cost of new work is $46,913,000 including $44,800,000 
Federal and $2,113,000 non-Federal. 
Local cooperation. Requirements of local cooperation 
are fully described on page 12-5 of Fiscal Year 80 
Annual Report. 
Operations and results during fiscal year. Preconstruction 
planning and design have been deferred 
pending favorable benefit-cost ratios. 
Condition as of Sep. 30. Preparation of general 
design memorandum has been deferred due to lack of 
economic justification. 
Status of studies: A re-evaluation study is underway 
to determine if there are any feasible alternatives. 
7. BAYOU BODCAU AND 
TRIBUTARIES, AR AND LA 
Location. In east bank flood plain of Red River. 
Bayou Bodcau rises in vicinity of Hope, AR, and flows 
southerly through Bayou Bodcau Reservoir and 
Bodcau Lake to join Cypress Bayou and form Red 
Chute Bayou, continues through Red Chute Bayou, 
Flat River, and Loggy Bayou to Red River, about 40 
miles below Shreveport, LA. 
Authorized project. Cypress Bayou-Red Chute 
Bayou levee: Extend existing levee from about 8 miles 
southeast of Benton, LA, proceeding southerly to 
junction of Cross and Red Chute Bayous, and then 
parallel to Red Chute Bayou on the right descending 
bank to its junction with Cutoff Bayou for a total 
distance of approximately 25 miles; construct landside 
drainage channel and several culverts with flap gates 
to Red Chute Bayou; construct approximately 5 miles 
of levee on left descending bank of Red Chute Bayou 
extending south from Louisiana Highway 612, and 
relocate utility lines as needed. 
Flat River-Loggy Bayou levee: Extend from lower 
end of existing Red River levee in vicinity of Ninock, 
LA, along high (left descending) bank of Red River to a 
point on right descending bank of Loggy Bayou, about 
1 mile above its mouth, thence generally along right 
descending bank of Loggy Bayou, Red Chute, Cutoff 
Bayou, and Flat River to Taylortown to tie into 
existing Red River levee; close Flat River near its 
junction with Cutoff Bayou and install one 36-inch 
round corrugated metal pipe with automatic flap gate 
to drain isolated pockets and provide uninterrupted 
drainage; construct drainage structures on Flat River 
near its junction with Red Chute Bayou and along 
alignment of the Loggy Bayou in the vicinity of Grassy 
Lake; and make necessary utility relocations. 
Flat River channel improvement: Enlarge to 
average bottom width of 50 feet with flat side slopes 
and deepen by 2 to 6 feet from the confluence with 
Cutoff Bayou to junction with Cooper Bayou, 11.6 
miles, including required relocations and modifications 
of utilities. Estimated cost for new work (October 
1986) is $25,600,000 Federal and $5,460,000 non- 
Federal; however, this is subject to change pending 
outcome of the reevaluation study currently under 
way. 
The subject project was one of the Water Resources 
projects reviewed in March 1977 in accordance with 
the President's request. As a result of this review, the 
President Recommended to deauthorize this project. 
Congress subsequently directed the Corps to take the 
following two actions: Construct levees on Red Chute 
Bayou below Cutoff Bayou that are required to prevent 
induced flood damage that would otherwise result 
from the abandonment of partly completed project. 
Initiate studies to determine if modifications to the 
authorized project would permit its completion in a 
form consistent with the current executive policy. 
Engineering and design work for the induced flood 
prevention plan below Cutoff Bayou and project 
modification studies were being conducted when 
President Reagan signed, on Dec. 4, 1981, the Energy 
and Water Development Appropriations Bill of 1982, 
which contained language that "reconfirmed without 
further study and analysis" the plan for flood control 
for the project as approved by the Flood Control Act of 
1965. 
Additional documents concerning environmental 
and socioeconomic impacts are currently being 
prepared and will be available to the public prior to 
further construction. There is clear evidence of a 
marked shift in land use within the project area over 
the past several years, from rural to urban-suburban. 
Because of this shift, we now find it necessary to 
expand our studies beyond those initially envisioned. 
The expanded studies will cover the areas of 
alternatives and economics, in addition to the natural 
environment. A scheduled date for resuming 
construction on the project has not been set. 
Local cooperation. For details see pages 11-24 and 
25, Annual Report for FY 80. 
Operations and results during fiscal year. New 
work by hired labor forces consisted of the 
unconstructed portion of the authorized project and 
additional engineering studies. 
12-4

VICKSBURG, MS, DISTRICT 
Condition as of Sep. 30. Construction was initiated 
in October 1974 and is 17 percent complete. 
Alternatives to provide flood protection are being 
considered and these efforts will continue. 
8. CADDO LAKE DAM, LA 
Location. In Caddo Parish, about 19 miles 
northwest of Shreveport, LA, at the eastern end of 
Caddo Lake and at head of Twelve Mile Bayou. 
Existing project. Replacement of the original dam 
was completed in June 1971, having same flow 
characteristics and located as near as practicable 
downstream of the old dam, built under navigation 
project "Cypress Bayou and Waterway between 
Jefferson, TX, and Shreveport, LA." New dam is 
capable of being raised in the future if desirable and 
justified. The Federal cost of the project through June 
1976, was $3,586,000. The non-federal cost was 
$228,000. The Water Resources Development Act of 
1976 transferred the operation and maintenance of the 
dam from local to federal responsibility. 
Local cooperation. Fully complied with. Public law 
94-587, Section 174, amended the Flood Control Act of 
1965 (Public Law 89-298) to provide that operation and 
maintenance of Caddo Lake Dam be the responsibility 
of the Secretary of the Army, acting through the Chief 
of Engineers. Conveyance of title to the United States 
from the Caddo Levee District is being reviewed. 
Operations and results during fiscal year. Maintenance 
by hired labor consisted of condition and 
operation studies, stream gaging, and water quality 
studies. Maximum pool elevation was 171.9 feet 
NGVD on June 30, 1986, when storage in the flood 
control pool was 0 acre-foot. On Sep. 30, 1986, the pool 
elevation was 168.1 feet NGVD and storage in flood 
control pool was 0 acre-foot. 
A feasibility study investigating enlarging the lake 
for M&I water supply is complete. The report was 
submitted in Nov 1985 and recommended no federal 
action. LMVD approved the report and the notice of 
issuance of summary report was disseminated in 
January 1986. 
9. LEAD BAYOU, MS 
Location. Lead Bayou is a tributary of the 
Sunflower River in Bolivar and Sunflower Counties, 
MS, approximately 30 miles from the Mississippi 
River near Cleveland, MS. 
Existing project. The plan of improvement was for 
enlargement of the existing Lead Bayou channel to 
provide a 1.5-year degree of protection to agricultural 
areas and a 10-year degree of protection to the small 
developed area near Cleveland, MS. Total estimated 
Federal cost is $1,526,000. 
Local cooperation. Fully complied with. 
Condition as of Sep. 30. The construction contract 
was completed Sep. 14, 1983. The stabilization of (1) 
bridge remains and will be accomplished by the 
Vicksburg District. 
10. OUACHITA RIVER LEVEES, LA 
Location. East bank of Ouachita River between 
Bastrop, LA, and Sandy Bayou. Loop levees on the 
west bank at West Monroe, Columbia, and 
Bawcomville. 
Existing project. There are 105.8 miles of levee on 
the east bank and 11.6 miles of levee in the three loops 
on the west bank. A letter report, approved by the 
Chief of Engineers, authorized gravel surfacing 40.3 
miles of levee, enlargement of 40.4 miles of levee, and a 
5.7-mile southward extension of the east bank levee. 
Approved (1979) estimated Federal cost is $9,400,000. 
Estimated non-Federal cost is $25,000. 
Local cooperation. Requirements and assurances of 
local cooperation are fully described on page 12-6 of 
FY 80 Annual Report. 
Condition as of Sep. 30. Item I of the Monroe to 
Sandy Bayou Levee enlargement project was 
completed July 7, 1978. Additional work was deferred 
pending results of a comprehensive study of the entire 
Ouachita River Levee System. The summary report 
which documents these study results was submitted to 
LMVD in August 1986 and indicate that it is 
economically feasible to raise portions of the existing 
levee to authorized grade and that complete 
rehabilitation of the levee system is necessary. These 
study results will be disseminated to the project 
sponsor and interested parties in October 1986. 
11. OUACHITA RIVER AND 
TRIBUTARIES, AR AND LA 
Location. Improvements comprising comprehensive 
projects are on main stem Ouachita River, AR and LA, 
on its tributaries, Caddo and Little Missouri Rivers, 
and in Pine Bluff, AR. Description of Ouachita River 
Basin is presented in greater detail on page 690 of 
Annual Report for 1962. 
Existing project. The authorized general plan for 
flood control and other purposes in the Ouachita River 
Basin includes the projects listed in Table 12-F. The 
1966 Flood Control Act modified the Bayou Bartholomew 
and Tributaries, AR and LA, project to 
include ten water-retention lakes in the western 
tributaries of Bayou Bartholomew in Arkansas and six 
local levee units along the main stem of the bayou in 
Louisiana. 
Local cooperation. Fully complied with for completed 
features of comprehensive project. (See individual 
statements for further details.) 
Operations and results during fiscal year. Operations 
for Blakely Mt. Dam-Lake Ouachita, DeGray 
Lake, Narrows Dam-Lake Greeson, Bayou Bartholomew 
and Tributaries, Monroe Floodwall, and 
Ouachita River Levees are shown in individual reports 
12-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
in 1985 report and Monroe 84 report. 
Condition as of Sep. 30. Pertinent data on those 
features which are complete or not started are in Table 
12-F. Conditions of Blakely Mt. Dam-Lake Ouachita, 
DeGray Lake, and Narrows Dam-Lake Greeson are 
given in the individual reports in 1985 report. 
An overall basin study including interim studies of 
the Monroe-West Monroe area, the Ouachita River 
Levees, the Arkansas Lakes is ongoing. 
12. PEARL RIVER BASIN, MS AND LA 
Location. The basin comprises most of the Southcentral 
portion of Mississippi and a small part of 
southeast Louisiana. The Pearl River begins in 
Neshoba county, MS and flows southwesterly 113 
miles to the vicinity of Jackson, MS, then southeasterly 
233 miles to the vicinity of Bogulasa, LA. At that point, 
the Pearl River splits into the East and West Pearl 
Rivers, and flows southerly 44 and 48 miles, 
respectively, before entering the Rogolets and Lake 
Borgne. 
Existing projects. The Jackson-East Jackson Flood 
Control Project provides for improvements of the 
Pearl River at Jackson, MS. This project includes two 
levee systems totaling 13.1 miles in length, with two 
pumping stations, four gated outlets, and 5.34 miles of 
channel rectification including three cutoffs with a 
total length of 2.2 miles in the Pearl River. This project 
was authorized by the Flood Control Act of July 14, 
1960. Construction began in July 1964 and work was 
completed in FY 68. Total Federal cost of the project 
was $7,190,200. The FY 83 Jobs Bill authorized 
extension of the Jackson-East Jackson West Bank 
Levee system along the Fortification Street 1-55 exit. 
This extension was initiated and completed in FY 84. 
Public Law #98-63, dated July 29, 1983, authorized the 
vicinity of Jackson project. This authority provided for 
additional measures to prevent recurring flood 
damages along the Pearl River at Jackson and 
included 3.3 miles of floodway clearing and enlarging 
the opening at the Highway 25 Bridge. This work has 
been completed with the exception of bank 
stabilization at one railroad bridge located in the 
clearing reach. Stabilization of this bridge is 
scheduled for construction in FY 87. Mitigation lands 
for the clearing were purchased by the local spoonsor 
in May 85 and the Corps has reimbursed the local 
sponsor to cover the cost of these lands. Total Federal 
Cost of this project including the remaining bank 
stabilization at the railroad bridge is $1,800,000. 
Authorized projects. Public Law 89-88, dated 
August 15, 1985, authorized planning, design, 
engineering, and construction of a levee system in 
Slidell, LA, to protect 3,265 residential and 
commercial structures from floods in the West Pearl. 
Local cooperation. For the Jackson-East Jackson 
and vicinity of Jackson Projects, the requirements are 
as prescribed in Section 3 of the Flood Control Act of 
1936, as amended. This Act requires that a local 
sponsor provide the easements, and rights-of-way 
necessary for construction of the project; hold and save 
the United States free from damages due to 
construction of the project; and maintain and operate 
all works after completion in accordance with 
regulations prescribed by the Secretary of the Army. 
The Slidell Levee Project authorization required costsharing 
and new guidelines for local cooperation. A 
Local Cooperation Agreement consistent with Public 
Law 99-88 was signed by the Slidell Local Sponsor and 
the Assistant Secretary of the Army for Civil Works on 
June 30, 1986. The local sponsors are as follows: 
Jackson-East Jackson, Rankin-Hinds Pearl River 
Flood Control Drainage District; Vicinity of Jackson 
Project, Pearl River Basin Development District; 
Slidell Levee Project, St. Tamany Levee District. 
Condition as of Sep. 30. Plans and specifications 
are being prepared for bank stabilization of a railroad 
bridge in the vicinity of Jackson Project. An overall 
basin study is underway. Flood control feasibility 
studies for Jackson, MS recommending the Shoccoe 
Dry Dam, and for Slidell, LA; recommending a 15 
mile levee system, have been completed. Detailed 
engineering and design studies are underway for 
Shoccoe Dam and the Slidell levee system. Flood 
control feasibility studies for the remainder of the 
basin include major emphasis on Carthage, Columbia, 
Picayune, and Monticello, Missisippi; Bogulusa, 
Louisiana, and the Bogue Chitto Subbasin. Navigation 
Studies are being conducted on the East and West 
Pearl Rivers and Port Bienville, MS. 
13. PORTER BAYOU, MS 
Location. Porter Bayou is located in Bolivar and 
Sunflower Counties, MS. It lies approximately 25 
miles east of the Mississippi River, is approximately 5 
miles south of Cleveland, MS, and travels through the 
town of Shaw, MS. 
Existing project. The plan of improvement calls for 
selective snagging and clearing of Porter Bayou from 
mile 12.5 to mile 32.3. This plan provides a 0.5-year 
frequency protection for the Porter Bayou area. All 
construction is being performed from one side of the 
stream, leaving the other side undisturbed. The total 
estimated Federal cost of the project is $1,214,000. 
Local cooperation. Fully complied with. 
Condition as of Sep. 30. The construction contract 
was completed November 16, 1983. A separate 
contract was let to biologically remove alligatorweed 
at Shaw, Mississippi, and follow-up with herbacide has 
been added. 
14. POVERTY POINT, LA 
Location. The project area is located on the west 
bank of Bayou Macon approximately 4.5 miles 
northeast of Epps, in LA, West Carroll Parish and is 
referred to as Poverty Point on Bayou Macon. 
Existing project. The project provides for erosion 
12-6

VICKSBURG, MS, DISTRICT 
protection to prevent bank failure along a 340 foot 
length of the west bank of Bayou Macon adjacent to 
Poverty Point Museum. The project involved bank 
grading, construction of a stone toe and stone tiebacks, 
sand fill covered by engineer fabric and stone paving 
over the length of the project. Top of the stone paving is 
approximately the 100-year flood elevation on Bayou 
Macon. 
Local cooperation. Requirements of Local 
Cooperation are fully described on page 12-10 of FY 85 
Annual Report. 
Condition of project. Work on this project was 
initiated Aug. 5, 1985, and was completed Oct. 4, 1985. 
15. RED RIVER BELOW DENISON 
DAM (VICKSBURG DISTRICT) 
Location. On Red River and its tributaries below 
Denison Dam, in Oklahoma, Arkansas, Texas, and 
Louisiana. (Refer to Geological Survey State maps and 
folio "Maps of Red River"-1958 edition.) 
Existing project. Flood Control Act of 1946 
approved general plan for flood control on Red River 
below Denison Dam, TX and OK, which provides for 
construction of six flood control reservoirs in 
combination with existing or authorized Federal and 
non-Federal levee improvements, modified as 
required, and channel stabilization at locations where 
levee setbacks are impossible or uneconomical. This 
act further authorized incorporation of several 
separate existing projects for flood damage prevention 
along Red River below Denison, above jurisdiction of 
the MRC, into this project. By Public Law 780, 83d 
Cong., 2d sess., as amended by Public Law 218, 84th 
Cong., 1st sess., and Public Law 645, 86th Cong., 1st 
sess., plan of improvement was amended to include 
additional projects as indicated in following lists of 
reservoirs and local protection works considered in 
general flood control plan for the Red River below 
Denison Dam, and existing flood control projects 
incorporated into project in Vicksburg District. (See 
Table 12-H for new projects and Table 12-I for 
incorporated projects.) 
Local cooperation. See individual reports herein. 
16. RED RIVER BELOW DENISON 
DAM, LEVEES AND BANK 
STABILIZATION 
(VICKSBURG DISTRICT) 
Location. Along the main stem of the Red River 
from the head of the levee system immediately above 
Index, Ar, through the southwest corner of Arkansas 
to the vicinity of Boyce, LA, on the right bank, and 
Pineville, LA, on the left bank. 
Existing project. Raising and strengthening 
existing and authorized Red River levees to provide 
protection against flooding and bank protection works 
at locations where levee setbacks are impossible or 
uneconomical. The plan consists of raising and 
strengthening existing and authorized Red River 
levees to provide against a flood approximately 20 
percent greater than the flood of 1945, the flood of 
record, as modified by authorized reservoirs. Bank 
protection works are to be constructed at locations 
where levee setbacks are impossible or uneconomical. 
Estimated cost for new work (October 1984) is 
$59,650,000 Federal and $1,560,000 non-Federal. 
Local cooperation. Requirements of local cooperation 
are fully described on page 12-10 of FY 1984 
Annual Report. 
Operations and results during fiscal year. Hired 
labor forces continued investigations, surveys, and 
preparation of plans and specifications. The Belcher 
realignment, river miles 299-306, and the Gahagan 
revetment, mile 225-L continued. 
Condition as of Sep. 30. Construction was initiated 
in February 1948 and the levees are complete and 
bank stabilization is 98 percent complete. 
17. RED RIVER WATERWAY 
SHREVEPORT, LA, TO 
INDEX, LA 
Location. In northwest Louisiana, southwest Arkansas, 
and northeast Texas, along the Red River between 
Shreveport, LA, and Index, AR. 
Existing project. To provide for realigning the 
channels of Red River from Shreveport, LA, to the 
levee system near Index, AR, by means of dredging, 
cutoffs, and training works and for stabilizing its 
banks by means of revetments, dikes, and other 
methods. Facilities to provide opportunities for 
recreation and for fish and wildlife development are an 
integral part of the project. Estimated cost for new 
work (October 1985) is $217,000,000 Federal and 
$27,500,000 non-Federal. 
Local cooperation. Requirements and assurances of 
local cooperation are fully described on pages 12-10 
and 12-11 of Fiscal Year 1984 Annual Report. 
Operations and results during fiscal year. None. 
Condition as of Sep. 30. Construction has not been 
initiated. Completion of a General Re-evaluation Study 
will be required prior to construction of the project. 
The engineering and economic feasibility of constructing 
the authorized project must be reviewed in 
light of changed conditions within the project area. The 
Re-evaluation studies are inactive at this time, as a 
result of a lack of FY 86 funding. 
18. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed work was accomplished at a 
cost of 30, 1986$,1 07,967 for the fiscal year. Total cost as of Sep. is $1,750,528. 
12-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
19. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, flood 
fighting, and rescue work. (Public Law 99, 84th 
Cong., and antecedent legislation.) 
Disaster preparedness, FY costs for the period were 
$199,596. 
Rehabilitation, total expenditures during FY 86 
amounted to $23,445 which included work on the Red 
River below Denison Dam. 
Total Public Law 99 costs through Sep. 30, 1986, 
were $223,041. 
Snagging and clearing of navigable streams and 
tributaries in the interest of flood control (Sec. 208 
of 1954 Flood Control Act, Public Law 780, 83d 
Cong.). 
No activity during the period. 
Emergency bank protection (Sec. 14 of 1956 
Flood Control Act, Public Law 780, 83d Cong.). 
Total FY 86 costs for emergency bank protection 
work was $185. 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended (preauthorization). 
During FY 1986, an initial appraisal study was 
completed on Sugar Ditch at Tunica, MS at a cost of 
$7,500. 
Detailed studies continued on Canal 43, Desha and 
Lincoln Counties, AR, at a cost of $27,680; and Bayou 
Natchitoches, LA, at a cost of $183,336; and Pearl- 
Flowood, MS, at a cost of $51,484. Funds were also 
expended on studies at By-Way Ditch in the amount of 
$4,384 and at Lead Bayou in the amount of $2,428. Both 
studies were completed. 
12-8

VICKSBURG, MS, DISTRICT 
TABLE 12-A COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
1. Ouachita and Black 
Rivers below Camden, 
AR (6.5-foot 
navigation project) 
Ouachita and Black 
Rivers below Camden, 
AR (9-foot 
navigation project) 
2. Red River 
Emergency Bank 
Protection 
(Contrib. Funds) 
3. Red River 
Waterway 
Mississippi 
River to Shreveport, 
LA 
(Contrib. Funds) 
4. Yazoo River, MS 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
20,406,000 
13,638,600 
Maint. 
4,232,756 
4,035,654 
12,700,000 
14,599,659 
4,486,300 
4,962,300 
4,000,000 
8,662,235 
4,962,000 
4,855,884 
3,362,000 5,630,000 7,000,000 
2,942,895 3,779,352 5,878,490 
6,098,000 
7,064,032 
3,375,000 
3,495,000 
1,270,000 
3,073,870 
5,248,6191 
5,248,6191 
216,622,000 
212,240,000 
69,138,467 
69,064,564 
17,262,0002 
15,674,607 
6,825 
6,825 
60,736,000 91,313,000 87,090,000 
58,456,160 91,266,477 81,574,966 
545,000 
510,042 
164,273 
103,139 
916,000 
465,295 
48,000 
7,700 
-122,000 
169,900 
142,171 
186,237 
80,000 
80,927 
-66,000 
1,892,000 
1,537,703 
1,602,515 
861,437 
10,000 
64,744 
91,585,000 330,724,0003 
65,955,521 297,253,124 
1,580,000 
1,864,677 
154,936 
153,230 
-147,000 
74,782 
66,200 
66,200 
6. Bayou Bartholomew New Work 
and Tributaries Approp. 
AK and LA Cost 
7. Bayou Bodcau 
and Tributaries, 
AR and LA 
8. Caddo Lake 
LA 
9. Lead Bayou, 
MS 
10. Ouachita River 
Levees, LA 
12. Pearl River 
Vicinity of 
Jackson 
Jackson-East 
Jackson 
13. Porter Bayou, 
MS 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
489,000 
982 
400,000 
331,125 
132,200 -144,400 
231,437 48,200 
358,000 
685,325 
-6,000 
48,000 
15,000 
162,003 
265,000 
445,448 
177,000 
187,221 
200,000 
234,820 
710,000 1,195,000 
43,737 1,820,453 
500,000 
506,187 
350,000 
290,515 
-15,000 
270,363 
265,000 
187,980 
142,000 
155,000 
200,000 
234,820 
21,217 
-60,000 
-515 
5,391 
3,875,0003 
4,082,3223 
2,547,3563 
1,787,5043 
9,679,661 
9,341,826 
1,194,515 
1,194,302 
974,000 
974,000 
1,154,000 
965,535 
628,600 
621,858 
1,945,685 
1,750,436 
2,682,000 
2,682,000 
1,905,000 
1,885,407 
290,000 
290,000 
1,035,278 
1,029,257 
12-9

TABLE 12-A 
(CONTINUED) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
14. Poverty Point New Work 
State Commemora- Approp. - 47,500 202,500 - 250,000 
tive Area, LA Cost - 47,500 207,500 - 250,000 
16. Red River below New Work 
Denison Dam, Approp. 550,000 1,600,000 1,000,000 957,000 9,217,7003 
Levees and Bank Cost 1,505,639 1,356,651 1,871,520 2,286,507 7,020,3173 
28. Red River Water- New Work 
way, Shreveport, Approp. - 90,000 50,000 - 140,0003 
LA, to Index, AR Cost 4,335 88,730 48,736 13,684 155,4853 
1. Includes $674,068 for new work on previous projects. 
2. Includes $3,312,000 PL 98-8 Jobs Bill. Excludes 
$47,828,000 previously allocated to New Orleans District. 
3. Excludes New Orleans District allocation and cost. 
12-10

VICKSBURG, MS, DISTRICT 
TABLE 12-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 17, 1950 
Jul. 14, 1960 
Dec. 31, 1970 
Aug. 13, 1968 
Aug. 13, 1968 
Mar. 3, 1875 
Aug. 13, 1968 
May 17, 1950 
Nov. 7, 1966 
Oct. 27, 1965 
Oct. 27, 1965 
Jun. 30, 1948, as 
amended 
OUACHITA AND BLACK RIVERS BELOW CAMDEN, 
AR (See Section 1 of Text) 
Modification of existing project to provide for 9-foot channel and 
deepening canal to Felsenthall, AR. 
Modification of 9-foot project to provide four new locks and dams 
and channel improvements. 
Migratory waterfowl refuges on Bayou D'Arbonne in connection 
with the pool of the Columbia Lock and Dam and in the pool of 
the Felsenthal Lock and Dam. 
RED RIVER EMERGENCY BANK PROTECTION (See 
Section 2 of Text) 
Realining the banks by dredging cut-offs and training works and 
stabilizing banks by means of revetments and dikes. 
RED RIVER WATERWAY-MISSISSIPPI RIVER TO 
SHREVEPORT, LA (See Section 3 of Text) 
Develop a 9 by 200 feet, approximately 236 miles long from 
Mississippi River at junction of Old River via Old River and Red 
River to Shreveport, LA, consisting of realinement, bank 
stabilization, and construction five locks and dams. 
YAZOO RIVER, MS (See Section 4 of Text) 
Removal of obstructions to navigation from mouth to Greenwood, 
MS, 189 miles. 
Nine-foot channel from mouth to Greenwood, mile 154.9 (persent 
mileage), with a lock and dam near Vicksburg, channel 
improvements, alteration of bridges, additional storage space in 
Sardis Lake to augment low river flows, and recreation 
features. 
BAYOU BARTHOLOMEW, AR AND LA (See Section 6 of 
Text) 
Authorized channel improvements on Bayou and Tributaries (see 
above). 
Modified 1950 authorization to include 10 lakes in the west 
escarpment in Arkansas and 6 local levees in Louisiana, and 
acquisition of lands for mitigation of fish and wildlife losses. 
The previously authorized channel improvement was deferred 
until it is determined that the quality and quantity of water 
downstream will not be adversely affected. 
BAYOU BODCAU AND TRIBUTARIES, AR AND LA (See 
Section 7 of Text) 
Extend Cypress Bayou-Red Chute Bayou levee, construct stream 
closure landside drainage channel and three culverts on Red 
Chute Bayou, and clearing and snagging channel; extend Flat 
River-Loggy Bayou levee, close Flat River near junction with 
Cutoff Bayou, and construct control structures on Flat River 
near junction with Red Chute Bayou; and enlarge Flat River 
channel to 20 to 35 feet, a distance of 11.6 miles. 
CADDO LAKE, LA (See Section 8 of Text) 
Maintenance Work. 
LEAD BAYOU, MS (See Section 9 of Text) 
Channel enlargement. 
S. Doc. 117, 81st Cong., 1st 
sess. 
S. Doc. 112, 86th Cong., 2d 
sess. 
Report of the Chief of 
Engineers dated Nov. 25, 
1970, and H. Doc. 92-109, 
92d Cong., 1st sess. 
H. Doc. 304, 90th Cong., 2d 
sess. 
H. Doc. 304, 90th Cong., 2d 
sess. 
H. Doc. 342, 90tn Cong., 2d 
sess. 
S. Doc. 117, 81st Cong., 1st 
sess. 
H. Doc. 506, 98th Cong., 2d 
sess. 
H. Doc. 203, 89th Cong., 1st 
sess. 
S. Doc. 39, 89th Cong., 1st 
sess. 
Sec. 205 of the Flood 
Control Act of 1948, as 
amended. Authorized by 
Chief of Engineers Jun. 10, 
1980. 
12-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 12-B 
(CONTINUED) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 17, 1950 
Jul. 14, 1960 
Jun. 13, 1983 
Jul. 29, 1983 
Aug. 15, 1985 
Jun. 30, 1948, as 
amended 
Jul. 24, 1946, as 
amended 
Jul. 24, 1946 
Aug. 13, 1968 
Aug. 13, 1968 
OUACHITA RIVER AND TRIBUTARIES, AR AND LA 
(See Section 11 of Text) 
Authorized DeGray Lake; Murfreesboro Lake; extension of 
floodwall at Monroe to partially close the existing gap; local 
protection at Bawcomville, LA (subsequently constructed under 
Sec. 6, Act of May 15, 1928, with local interests contributing one 
third of cost); Bayou Bartholomew channel improvement, 
including Deep Bayou and Overflow Creek; Pine Bluff local 
protection; local protection at Calion, AR; and incorporation, 
into the Ouachita River and Tributaries project, of all existing 
projects and portions thereof in the basin above the lower end of 
the levees on the east bank of the Ouachita River. In addition, 
the Chief of Engineers authorized on Nov. 14, 1966, additional 
work on the levees. 
PEARL RIVER MS, AND LA (See Section 12 of Text) 
Construction of levee system and channel rectification, Pearl 
River, vicinity of Jackson, MS 
Accomplish the clearing and channel improvements at Hwy 35 
bridge on the Pearl River in the vicinity of Jackson, MS. 
Design and construct protection to prevent flooding along the 
Pearl River in the vicinity of Jackson, MS 
Planning, design, engineering and construction of a levee system 
for Slidell LA, pending binding cost-sharing arrangements 
acceptable to the Secretary of the Army or under terms and 
conditions provided in subsequent legislation when enacted into 
law. 
PORTER BAYOU, MS (See Section 13 of Text) 
Selective snagging and clearing of Porter Bayou, MS from mile 
12.5 to mile 32.3 
POVERTY POINT STATE COMMEMORATIVE AREA, 
LA (See Section 14 of Text) 
Provides for erosion protection against bank failure along a 340 
foot length of the west bank of Bayou Macon by means of 
grading, constructing tie backs, and stone paving. 
RED RIVER BELOW DENISON DAM LEVEES AND 
BANK STABILIZATION (VICKSBURG DIST.) (See 
Section 16 of Text) 
Levee and bank stabilization. 
Deauthorization of Morringsport Dam and Reservoir on Cypress 
Creek; realining and stabilizing the banks of the Red River; and 
recreational facilities from the Mississippi River to Denison 
Dam, OK and TX. 
RED RIVER WATERWAY-SHREVEPORT, LA, TO 
INDEX, AR (See Section 17 of Text) 
Provides for realinement of the channels of the Red River from 
Shreveport, LA, to Index, AR. 
S. Doc. 117, 81st Cong., 1st 
sess. 
H. Doc. 441, 86th Cong., 1st 
sess. 
S. Doc. 153, 98th Cong., 1st 
sess. 
Public Law 98-63, 98th 
Cong., 1st sess. 
Public Law 99-88, 99th 
Cong., 2nd sess. 
Sec. 205 of the Flood 
Control Act of 1948, as 
amended. Authorized by 
Chief of Engineers, Feb. 
18, 1982. 
Public law 526, 79th Cong., 
2d sess. 
H. Doc. 602, 79th Cong., 2d 
sess. 
H. Doc. 304, 90th Cong., 2d 
sess. 
H. Doc. 304, 90th Cong., 2d 
sess. 
12-12

TABLE 12-C OUACHITA AND BLACK RIVERS, AR AND LA 
(9-FOOT PROJECT), LOCKS AND DAMS 
(See Section 1 of Text) 
Min. 
Depth 
Greatest on 
Available Lower 
Miles Length Max. Elev. Miter 
Above Width for Full Lift Normal Sill at 
Miles Mouth of Width at Pool Normal Pre- Total 
from of Lock of Lock Low Surface Pool Character cent Estimated 
Nearest Black Chamber Chamber Water (feet Level or Kind of Type of Com- Project 
Location Town River (feet) (feet) (feet) msl) (feet) Foundation Dam Construction plete Cost 
Jonesville, LA 10 25 84 600 30 34 14 Piling Moving Tainter gated dam; 992 $ 51,700,000 
bascule gated 
nagivation pass; 
steel mitering lock 
gates 
Columbia, LA 5 117 84 600 18 52 13 do do Tainter gated dam; 952 45,600,000 
fixed crest 
navigation pass; 
steel mitering lock 
gates 
Felsenthal, AR 1 227 84 600 18 701 13 Earth do Tainter gated dam; 852 95,800,000 
navigation pass 
with inflatable dam 
on crest; steel 
mitering lock gates. 
Calion, AR 7 283 84 600 12 77 13 do do Tainter gated dam; 852 75,900,000 
hinged crest gated 
navigation pass; 
steel mitering lock 
gates. 
Estimated Federal Cost $269,000,000 
Estimated Non-Federal Cost 10,150,000 
Total Estimated Cost $279,150,000 
1. Fish and wildlife impoundment level. Navigation pool 
elevation .65. 
2. The percent complete reflects all work within the 
pool.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 12-D OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sep. 1986 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Status Report For: Construction Maintenance Completed 
Bayou Bartholomew, LA and AR1, 2 , 3, 4 - 1931 $ 45,874 $ 42,857 
Bayous D'Arbonne and Corney, LA1, 2 , 4 - 1941 19,000 37,804 1 
Big Black River, MS 1, 4, 5 
- 1895 15,000 - 1 
Big Sunflower River, MS 1, 4, 6, 7 - 1942 560,027 459,328 1 
Boeuf River, LA 1, 3, 4, 7, 8, 9 - 1949 30,000 103,737 1 
Claiborne County Port, MS - 1985 2,000,000 2,000,000 1 
Cypress Bayou and Waterway between 
Jefferson, TX, and Shreveport, LA15 Complete 1971 202,817 452,611 Dec. 1914 
Homochitto River, MS 4 - 1910 15,482 8,518 1 
Lake Providence Harbor, LA - 1985 208,537 2,235,504 15 
Little Missouri River, AR 1, 4, 5 - 1873 19,992 - 1 
Little River, LA 1, 4, 5, 10 - 1890 1,500 - 1 
Little Tallahatchie River, MS 1 7 - 1913 19,000 - 1 
Madison Parish Port, LA - 1985 655,999 529,031 1 
Mouth of Yazoo River, MS 1 7 11 - 1953 1,179,211 217,266 1 
Ouachita and Black Rivers, AR and LA,1132 
Felsenthal Canal 193712 
Overton-Red River Waterway, LA - 1985 - -350,500 1 
Pearl River, MS - 1985 1,354,400 1,306,423 1 
Red River below Fulton, AR1 16, 17,18 - 1978 1,963,806 2,147,890 1 
Red River Waterway 
LA, AR, OK, and TX" 17,18 - 1969 - 1 
Red River Waterway, Shreveport, LA 
to Daingerfield, TX1 1976 70,000 - 
Removing snags and wrecks from -1948 - 272,5001 
Mississippi River below mouth of 
Missouri River and from 
Old and Atchafalaya Rivers11 
Rosedale Harbor, MS - 1985 2,000,000 1,517,584 1 
Saline River, AR1, 3, 4, 5 - 1931 26,900 12,792 1 
Tallahatchie and Coldwater 
Rivers, MS 1, 4, 5 - 1939 43,481 173,066 
12-14

VICKSBURG, MS, DISTRICT 
TABLE 12-D 
(CONTINUED) 
OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sep. 1986 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Status Report For: Construction Maintenance Completed 
Tensas River and Bayou 
Macon, LA, 1 8 12 1949 38,367 85,352 1 
Yalobusha River, MS 1, 4' 5, 14 - 1937 7,000 15,936 1 
1. Status and Date unavailable. 
2. Abandonment recommended in H. Doc. 1962, 64th 
Cong., 2d sess., and H. Doc. 467, 69th Cong., 1st sess. 
3. Channels adequate for existing commerce. 
4. Inactive project. No commerce. 
5. Abandonment recommended in H. Doc. 467, 69th 
Cong., 1st sess. 
6. Project curtailment recommended by elimination of 
work between Pentecost and mouth of Hushpuckena River. 
(Abandonment of entire project erroneously recommended 
in H. Doc. 467, 69th cong., 1st sess.) 
7. See report of Mississippi River Commission for operations 
in connection with Yazoo Basin. 
8. Report of New Orleans District, pp. 919-920 for 
Fiscal Year 1949. 
9. Project curtailment recommended by elimination of 
work above Girard, LA (Abandonment of entire project 
recommended erroneously in H. Doc. 467, 69th Cong., 1st 
sess.)
10. Due to decline of traffic, local interests not 
sufficiently interested to provide rights-of-way and dumping 
privileges. 
11. No additional funds available under this project. 
Work is being carried on under appropriation flood control, 
Mississippi River and tributaries. 
12. Year authorized. 
13. Inactive. Channel adequate for commerce. 
14. See report of Mississippi River Commission for 
operations in connection with Yazoo Basin flood control 
project including channel clearing and rectification and 
Grenada Lake on Yalobusha River. 
15. Excludes $50,000 contributed funds. 
16. Includes $1,553,878 for previous projects. 
17. Incorporated in the project "Red River Waterway- 
Mississippi River Shreveport, LA" Sept. 30, 1976. 
18. Emergency bank protection on this project is 
reported separately as "Red River Emergency Bank 
Protection." Two reaches, "Red River Waterway-Mississippi 
River to Shreveport, LA" and "Red River Waterway- 
Shreveport, LA, Daingerfield, TX," are also reported 
separately. 
12-15

TABLE 12-E 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OUACHITA RIVER AND TRIBUTARIES: 
EXISTING PROJECT 
(See Section 11 of Text) 
For Last Estimated 
Full Report Federal 
See Annual New Work 
Project Report for: Cost 
Blakely Mt. Dam-Lake Ouachita, AR 1985 $ 44,100,000 
DeGray Lake, AR 1985 72,034,0002 
Narrows Dam-Lake Greeson, AR 1985 20,900,000 
Calion, AR 1960 970,9963 
Columbia, LA 1941 204,7403 
Existing levees and extensions thereto from Bastrop, LA, to mouth of 
BoeufRiver and at West Monroe, LA 1961 3,025,1813 
Little Missouri River below Murfreesboro, AR 1957 354,8023 
Ozan Creek, AR 1957 57,7423 
Terre Noire Creek, AR 1948 123,7008 
Pine Bluff, AR, local protection 1954 172,5823 
Monroe, LA, floodwall extension (Plan B) 1984 2,561,0008 
Bayou Bartholomew and Tributaries, AR and LA (i) 44,800,000 
Ouachita River Levees (additional work) (1) 9,400,000 
Total $198,704,7434 
21.. ISnece liunddeivs idu$a5l, 8re0p0o,0r0ts0 herein. 4. Excludes the authorized Murfreesboro Lake, AR, for water supply, to be project, which is inactive. The latest estimated cost (1954) 
reimbursed by local interests. was $4,190,000. 
3. Actual cost of completed project. 
TABLE 12-F RESERVOIR OPERATIONS 
FISCAL YEAR 1984 
See 
Section Storage 
in Text Project (acre feet) Inflows Outflow 
24. Bayou Bodcau 2 Oct. 1, 1981 249 - - 
Reservoir, LA Sep. 30, 982 310 - - 
Jul. 2, 1982 (Max) 11,340 - - 
Jun. 29, 1982 (Max) - 1,664 - 
Jul.2,1982 (Max)- - 1,125 
36. Wallace lake, LA Oct. 1, 1981 7,655 - - 
Sep. 30, 1982 7,319 
Apr. 24, 1982 (Max 11,739 - - 
Apr. 23, 1982 (Max - 1,013 - 
Apr. 24, 1982 (Max - 634 
1. Cubic feet per second. 
12-16

VICKSBURG, MS, DISTRICT 
TABLE 12-G RED RIVER BELOW DENISON DAM 
(VICKSBURG DISTRICT): NEW PROJECTS 
(See Sec. 15 of Text) 
Drainage Conserva- Flood 
Area tion Control Estimated 
(square Storage (acre- Federal 
Project Stream miles) (acre-feet) feet) Cost 
Bayou Bodcau and tributaries, AR 2 and LA - 1,158 - - $25,100,0003 
Bayou Nicholas-Coushatta, LA - - - 70,7174 
Bayou Pierre in vicinity of Shreveport, LA5 - - - - 243,336' 
Caddo Lake, LA' Caddo Lake - - - 3,586,000 
Campti-Clarence Area in 
Natchitoches Parish, LA Red River - - - 1,950,000 
Garland City, AR , - - - 1,450,000' 
Maniece Bayou, AR - - - 970,032' 
McKinney Bayou, AR7 - - - - 5,610,000' 
Posten Bayou, AR and LA2 6, 9 - - - 560,000 
Red River below Denison Dam levees 
and bank stabilization, TX, AR and LA", 3 - - - - 59,650,000 
Total 99,191,885 
1. Details presented in individual report herein. 
2. Construction on this project not started. 
3. In addition non-Federal funds are: 
Bayou Bodcau and tributaries, AR and LA ........................................................ $5,300,000 
Bayou Pierre in vicinity of Shreveport, LA (cash contribution) .. .................................... 89,047 
Caddo Lake, LA ..... ........................................................................ 28,000 
Campti-Clarence Area in Natchitoches Parish, LA .. ............................................ 480,000 
East Point ........................................................................... 67,000 
Garland City, AR ......................................................................... 6,000 
Maniece Bayou, AR (cash contribution) ....................................................... 18,000 
McKinney Bayou, AR (cash contribution) ................................................... 508,000 
Red River below Denison Dam, levees and bank stabilization, TX, AR, and LA ......................... 1,560,000 
4. For last full report, see Annual Report for 1964. 
5. For last full report, see Annual Report for 1951. 
6. Inactive. 
7. Includes $4,330,200, Code 711, and $399,739 accelerated Public Work funds. 
8. Joint-use pool (sediment). 
9. Deauthorized by resolution Dec. 17, 1970, which also authorized new project "Posten Bayou, AR," under provision of 
Sec. 201 of Flood Control Act of 1965. 
12-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 12-H RED RIVER BELOW DENISON DAM 
(VICKSBURG DISTRICT): INCORPORATED PROJECTS 
(See Sec. 15 of Text) 
Flood For Last Estimated Full Report 
Control Federal See Annual 
Project Type of Work Act Cost Report For 
Aloha-Rigolette Area, Grant and Rapides 
Parishes, LA Levee and appurtenances 1941 $ 1,653,2371 1956 
Bayou Bodcau Reservoir, LA2 Flood-control reservoir 1938 5,120,740" 3 4 
Bayou Bodcau, Red Chute, and 
Loggy Bayou, LA Channel improvement 1941 319,200' 1948 
Bayou Pierre, LA Channel enlargement 1936 299,529' 4 
Black Bayou Lake, LA5' 6 Flood-control reservoir 1936 714,000 1945 
Colfax, Grant Parish, LA Cutoff 1938 70,3481 7 1938 
Grant Parish, below Colfax, LA Levees 1938 38,809' 1941 
Hempstead County levee district 
No. 1, AR Levee enlargement 1938 88,0061 1941 
Natchitoches Parish, LA Levee and appurtenances 1936 1,529,927" 1956 
Pineville, Red River, LA Levee and appurtenances 1941 232,426' 1953 
Red River in vicinity of 
Shreveport, LA Bank protection 1944 3,908,0001 1953 
Red River Parish, LA Levee enlargement 1936 149,435' 1939 
Saline Point, LA Cutoff 1936 124,111 1945 
Wallace Lake, LA Flood-control reservoir 1936 1,219,3711 3 4 
Total $15,467,134 
1. Actual cost. 
2. Project transferred to Vicksburg District August, 
1982.
3. Includes amounts indicated for recreational facilities 
under Code 711, Bayou Bodcau Reservoir, LA, $1,027,000; 
Wallace Lake, LA, $17,164. 
4. Included in this report. 
5. Work not started. 
6. Inactive. 
7. Completed under provisions of Sec. 7 of Flood Control 
Act of 1928, as amended by Sec. 9 of Flood Control Act of 
1936, and included in 1939 Annual Report of President, 
Mississippi River Commission, p. 2214. 
8. In addition, $25,000 was expended from contributed 
funds. 
12-18

VICKSBURG, MS, DISTRICT 
TABLE 12-I OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 1986 
Mo. and Yr. Full Report Operation Mo. and Yr. 
If See Annual and If 
Project Deauthorized Report For: Construction Maintenance Completed 
Aloha-Rigolette Area, Grant and 
Rapides Parishes, LA1 
Bayou Bodcau, Red Chute, and 
Loggy Bayou, LA1 
Bayou Bodcau Reservoir, LA 
Bayou Pierre, LA 
Bayou Pierre in vicinity of 
Shreveport, LA1, 2 
Big Black River, MS 3 
Big Choctaw Bayou, LA 3, 4 
Black Bayou Reservoir, LA 1, 5, 6 
Blakely Mt. Dam - Lake 
Ouachita, Ouachita River, AK 
Buffalo River, MS7 
Campti-Clarence Area in 
Natchitoches Parish, LA 
Colfax, Grant Parishes, LA 1 8 
DeGray Lake 
Caddo River, AR 
East Point, LA 
Garland City, AR 
Grant Parish below Colfax, LA 1, 3 
Hempstead County Levee District 
No. 1, AR1, 3 
Homochitto River, MS3 
Maniece Bayou, AR1, 2 
McKinney Bayou Finn Bayou 
Segment, AR 
Monroe Floodwall, LA 
Murfreesboro Dam and Lake4 
Narrows Dam-Lake Greeson, 
Little Missouri River, AK 
Natchez Port Area, MS 3', 4 
Natchitoches Parish, LA1, 2 
Pineville, Red River, LA3, 4 
Posten Bayou, AR 1� 
Red River Parish, LA 1, 3 
Red River in vicinity of 
Shreveport, LA' 
Saline Point, LA 1, 3 
Aug. 1977 
1956 
1948 
1985 
1985 
1951 
1956 
1966 
1945 
1985 
1940 
1978 
1938 
1985 
1969 
1976 
1941 
1941 
1956 
1970 
19639 
1984 
1951 
1985 
1969 
1956 
1953 
1973 
1939 
1953 
1945 
$ 1,653,189 
319,200 
243,3362 
910,185 
248,823 
34,023,108 
1,655,700 
70,348 
72,033,992 
286,069 
1,335,841 
38,809 
88,006 
205,000 
970,9322 
2,560,000 
16,516,689 
538,000 
1,529,478 
232,426 
149,435 
3,908,000 
124,111 
$ - 
1,833,125 
70,241 
Apr. 1955 
Jan. 1948 
Apr. 1961 
FY 1939 
- Jun. 1939 
670,750 3 
- 3 
43,475,820 Oct. 1955 
- Jul. 1978 
28,039,599 Dec. 1971 
- Aug. 1968 
- Jul. 1974 
144,650 
31,169,578 
3
3 
Aug. 1969 
May 1950 
5 
- Aug. 1955 
- Dec. 1951 
3 
Mar. 1953 
12-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 12-I 
(CONTINUED) 
OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 1986 
Mo. and Yr. Full Report Operation Mo. and Yr. 
If See Annual and If 
Project Deauthorized Report For: Construction Maintenance Completed 
Twelvemile Bayou, LA4 - 1966 335,433 - May 1965 
Wallace Lake, LA - 1985 - 258,183 Dec. 1946 
1. Authorized under project "Red River Below 
Denison Dam." 
2. In addition, the following was expended from contributed 
funds: 
Amite River and tributaries ............ $ 430 
Bayou Pierre in vicinity of 
Shreveport, LA .................... 89,047 
Choctaw Bayou and Tributaries, LA ..... 170,799 
Harvey Canal, Bayou Barataria Levee, 
LA ............................... 425,209 
Maniece Bayou, AR ................... 39,293 
Natchitoches Parish, LA ............... 250,000 
3. Completion Date Unavailable. 
4. Authorized by Chief of Engineers under authority 
of Sec. 205 Flood Control Act of 1948, as amended. 
5. Construction not initiated. 
6. Inactive. 
7. Deferred indefinitely because of insufficient 
justifi 
cation under present conditions. 
8. Completed under provisions of Sec. 7 Flood Control 
Act of 1928, as amended by Sec. 9, Flood Control Act 1936, 
and included in 1939 Annual Report of President, 
Mississippi River Commission, p. 2214. 
9. Date authorized. 
10. Posten Bayou Project, authorized by Senate and 
House Resolutions, Dec. 17 and 15, 1970, deleted the plan 
authorized by the Flood control Act dated Aug. 3, 1955. 
12-20

VICKSBURG, MS, DISTRICT 
TABLE 12-J ACTIVE GENERAL INVESTIGATIONS 
(96x3121) 
Federal Cost Totals by 
Item and CWIS Number FY 86 Categories 
SURVEYS (Category 100) ($) ($) 
Flood Control Studies (120) 
Ouachita River Basin, AR & LA -12046 $ 642,681 
Pearl River Basin, MS and LA -12234 1,087,156 
Pine Bluff Metro, AR -12015 9,166 
Subtotal 1,739,003 
Comprehensive Studies (150) 
Red River Below Denison Dan (153) -81129 236,910 
Miscellaneous Activities (170) 
Special Investigations (171) -17250 18,937 
Review of FERC Licenses (172) -53857 5,947 
Subtotal 24,884 
Coordination Studies with Other Agencies (180) 
Department of Agriculture, Soil Conservation Service (181) -51840 1,982 
Planning Assistance to States (186) -51850 0 
Technical and Engineering Assistance on Shoreline 
and Streambank (188) -51731 0 
Subtotal 1,982 
TOTAL (Category 100) 2,002,779 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Inspection of Dams (230) 
Inventory of Dams 0 
Flood Plain Management Services (250) 
Flood Plain Management Services 170,885 
Hydrologic Studies (260) 
Hydrologic Studies (260) -53820 15,482 
Subtotal 186,367 
TOTAL (Category 200) 186,367 
CONTINUATION OF PLANNING & ENGINEERING (Category 400) 
Flood Control Projects (450) 
Pearl River, Slidell, LA (451)-12442 211,990 
Pearl River, Shoccoe Dam, MS (452)-12444 244,054 
Subtotal 456,044 
TOTAL (Category 400) 456,044 
ADVANCE E&D (Category 600) 
Navigation Projects (620) 
Locks and Dams, Yazoo River, MS (622) 
00083 0 
Flood Control Projects (650) 
Local Protection, Red River Waterway, 
Shreveport to Index (651) -75023 13,684 
Local Protection, Pearl River Vicinity 
of Jackson, MS (651) -75426 3,581 
Subtotal 17,265 
TOTAL (Category 600) 17,265 
GRAND TOTAL GENERAL INVESTIGATIONS $2,662,455 
12-21

MEMPHIS, TN, DISTRICT * 
This district comprises a portion of southeastern 
Missouri and southern Illinois, western portions of 
Kentucky and Tennessee, a small portion of northern 
Mississippi, and the northeastern portion of Arkansas; 
includes area embraced in drainage basins of eastern 
tributaries of the Mississippi River south of Ohio River 
Basin to Nonconnah and Horn Lake Creeks, inclusive, 
and those of western tributaries south of Little River 
diversion channel and Commerce, MO, including St. 
Francis River Basin and White River and tributaries 
below Peach Orchard Bluff, AR, on the right bank and 
below Augusta, AR, on the left bank; also includes left 
bank Mississippi River levee from vicinity of Memphis 
south to about mile 620, and right bank levees from 
Cape Girardeau, MO, to about mile 605. 
IMPROVEMENTS 
Navigation Page Tables 
1. Navigation work under special 
authorization ........................ 
Flood Control 
2. Hatchie River, Alcorn Co, MS ......... 
3. Humboldt, TN ...................... 
4. Nonconnah Creek Interceptor Sewer, 
M em phis, TN ....................... 
5. Inspection of completed flood control 
projects .... ......................... 
6. Flood control work under special 
authorization ........................ 
Table 13-A 
13-1 Table 13-B 
Table 13-C 
13-1 
13-2 
13-2 
13-2 
13-2 
Table 13-D 
Table 13-E 
Cost & Financial Statement .... 
Authorizing Legislation ....... 
Other Authorized Navigation 
Projects ...................... 
Other Authorized Flood Control 
Projects ..................... 
Active General 
Investigations ................ 
Navigation 
1. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
No work was done this period under this authority. 
Flood Control 
2. HATCHIE RIVER, ALCORN 
COUNTY, MISSISSIPPI 
Location. The project is located in Alcorn County in 
northeast Mississippi, along the Hatchie River 5 miles 
upstream of U.S. Highway 72. 
Existing project. Authorized under the authority of 
Section 208 of the 1954 Flood Control Act. The project 
consists of removal of a 1,000-foot-long massive logjam 
where the Hatchie River channel was completely 
blocked and stream flows were diverted into the 
adjacent bottomland hardwood forests. Timber will be 
restored or preserved on over 1,100 acres of valuable 
forests. 
Local cooperation. Provide without cost to the 
United States all lands, easements, and rights-of-way 
necessary for the construction, operation and maintenance 
of the project and all necessary modifications 
or relocations of roads, bridges, and utilities other than 
railroad bridges and bridge approaches; to the extent 
of the legal authority of the Hatchie Drainage District 
of Alcorn County, hold and save the United States free 
from all damages arising from the construction and 
operation of the completed works, except those 
damages due to the sole fault or negligence of the 
United States or its contractors; to the extent of the 
legal authority of the Hatchie Drainage District of 
Alcorn County, maintain and operate the completed 
works without cost to the United States in accordance 
with regulations prescribed by the Secretary of the 
13-1 
Page 
13-4 
13-4 
13-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Army; prevent future encroachment which might 
interfere with proper functioning of the project for 
flood control after project construction; pay all costs 
associated with project features designated to be local 
interest responsibilities; assume full responsibility for 
all project costs in excess of the Federal cost limitation 
of $250,000; comply with the provisions of the Uniform 
Relocation Assistance and Real Property Acquisition 
Policies Act of 1970, Public Law 91-646; comply with 
the provisions of Section 221 of the Flood Control Act 
of 1970, Public Law 91-611; comply with the provisions 
of Section 601 of Title VI of the Civil Rights Act of 
1964 (Public Law 88-352) that no person shall be 
excluded from participation in, denied the benefits of 
or subjected to discrimination in connection with the 
project on the grounds of race, creed, or national 
origin. 
Local interests have furnished the required assurances. 
Condition as of Sep. 30. The channel blockage was 
removed in August 1985 and the remaining cleanup 
was completed in Feb. 1986. 
3. HUMBOLDT, TN 
Location. Humboldt is located in Gibson County, TN. 
Existing project. Authorized July 23, 1984, under 
the authority of Section 205 of the 1948 Flood Control 
Act, as amended. The project consists of clearing and 
snagging approximately 2,200 feet of existing channel 
and the construction of 2,600 feet of enlarged channel. 
The project will provide a 10-year level of protection 
for area residents and is expected to reduce average 
annual flood damages by 64 percent. The current 
estimated construction cost for the project is 
$1,110,000. The project assurances of local cooperation 
have been furnished. The construction contract for 
required channel improvement was awarded in July 
1986. It has been determined that no adverse 
environmental impacts will result from construction of 
the project. 
Local cooperation. Requirements of local cooperation 
are fully described on page 13-4 of FY 1984 
Annual Report. 
Condition as of Sep. 30. Channel work is expected 
to be completed in October 1986. Remaining work 
consists of construction of a railroad drainage 
structure. 
4. NONCONNAH CREEK 
INTERCEPTOR SEWER, MEMPHIS, 
TENNESSEE 
Location. The project is located in southeastern 
Memphis, Tennessee, along the right (north) bank of 
Nonconnah Creek through a reach extending from 
about 600 feet upstream to 100 feet downstream of the 
Highway 78 (Lamar Ave.) bridge. 
Existing project. Authorized under the authority of 
Section 14 of the Flood Control Act of 1946. The project 
consists of providing bank protection along a 700 foot 
reach of eroding creek bank to protect a major 
interceptor sewer line and the U.S. Highway 78 
bridge. Protection is to be provided via grading and 
shaping the bank and armoring it with riprap stone. 
Local cooperation. Provide without cost to the 
United States all lands, easements, and rights-of-way 
necessary for construction of the project; provide 
without cost to the United States all necessary 
relocations and alterations of buildings and utilities, 
sewers, related and special facilities; to the extent of 
the legal authority of the City of Memphis, Tennessee; 
hold and save the United States free from all damages 
due to the construction, operation, and maintenance of 
the project, except damages due to the fault or 
negligence of the United States or its contractors; to 
the extent of the legal authority of the City of 
Memphis, Tennessee, maintain and operate the project 
works after completion without cost to the United 
States in accordance with regulations prescribed by 
the Secretary of the Army; comply with provisions of 
the Uniform Relocation Assistance and Real Property 
Acquisition Policies Act of 1970, Public Law 91-646; 
comply with the provisions of Section 221 of the Flood 
Control Act of 1970, Public Law 91-611; assume any 
construction costs in excess of $250,000, the monetary 
limit established in Section 27, Public Law 93-251; 
prevent future encroachment which might interfere 
with proper functioning of the project; if applicable, 
adjust all claims covering water rights; comply with 
the provisions of Section 601 of Title VI of the Civil 
Rights Act of 1964, Public Law 88-352. 
The city of Memphis, Tennessee has provided the 
required local cooperation assurances and rights-ofway. 
Condition as of Sep. 30. A contract for construction 
of the project was awarded on September 30, 1986. The 
work is expected to be completed in December 1986. 
5. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspected completed projects at a cost of $118,480 in 
the period. Total cost as of Sep. 30, 1986, was 
$1,168,738. This included in-depth inspection of 
projects. 
6. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Sec. 205, Public 
Law 858, 80th Cong., as amended (preauthorization). 
12.-2

MEMPHIS, TN, DISTRICT 
During this period $32,594 was expended on 
Tuscumbia River, MS & TN, and $31,861 on Cane 
Creek, Martin, TN. 
During FY 1986 $6,551 was expended for detail 
studies on Nonconnah Interceptor Sewer, Memphis, 
TN, and $19,358 on Turner Creek, Corinth, MS. 
Emergency flood control activities - rehabilitation 
of private levee (Public Law 99, 84th Cong., and 
antecedent legislation). Federal cost was $88,056.19 
for rehabilitation of Dyer County Private Levee, and 
$248,878 for disaster preparedness. 
Flood control activities pursuant to Sec. 208, 
Public Law 780, 83d Cong., as amended. During 
this period $10,802 was expended on Hatchie River, 
MS. 
13-3

TABLE 13-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
2. Hatchie River, New Work 
Alcorn Co., MS Approp. $ - $ - $ 62,676 $ 10,802 $ 73,478 
Cost - - 62,673 10,802 73,475 
3. Humboldt, TN New Work 
Approp. - 155,000 - 333,333 488,333 
Cost - 124,150 11,539 349,736 485,425 
4. Nonconnah Creek New Work 
Interceptor Approp. - - - 30,000 30,000 
Sewer, Memphis, Cost - - - 29,435 29,435 
TN 
TABLE 13-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
HATCHIE RIVER (See Sec. 3 of Text) 
Sep. 24, 1954, Clearing and snagging within channel. Approved Jul 24, 19853 
as amended 
HUMBOLDT, TN (See Sec. 4 of Text) 
June 30, 1948, Channel improvement within the city of Humboldt. Approved Jul. 23, 19841 
as amended 
NONCONNAH INTERCEPTOR SEWER AND 
U.S. HIGHWAY 78 (See Sec. 5 of Text) 
Jul. 24, 1946, Stabilization - stream bank caving. Approved Oct. 18, 19852 
as amended 
1. Authorized under authority of Sec. 205 of the 1948 
Flood Control Act, as amended. 
2. Authorized under authority of Sec. 14 of the 1946 
Flood Control Act. 
3. Authorized under authority of Sec. 208 of the 1954 
Flood control Act, as amended. 
13-4

MEMPHIS, TN, DISTRICT 
TABLE 13-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 1986 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Caruthersville Harbor, MO - 1984 $768,992 $ 1,566,991 Dec 80 
Forked Deer River, TN, including South 
Fork" 2- 1912 25,000 12,818 - 
Helena Harbor, AR - 1984 90,847 3,439,163 Sep 63 
Hickman Harbor, KY - 1984 149,827 3,739,720 Jan 63 
New Madrid Harbor, MO - 1984 196,373 385,509 Oct 70 
Obion River, TN" - 1911 28,716 - - 
Osceola Harbor, AR - 1984 269,115 4,949,913 Nov 74 
Removing snags and wrecks from 
Mississippi River below mouth of Missouri 
River and from Old and Atchafalaya 
Rivers4 5 -1948 - 318,833 
St. Francis and L'Anguille Rivers and 
Blackfish Bayou, AR" 2 - 1942 92,000 300,449- 
White River, AR (below Newport) - 1984 169,994 16,379,742- 
Wolf River (Memphis Harbor), TN - 1984 586,500 8,151,431 1959 
1. No commerce. * 
2. Existing project is for maintenance only. 
3. Recommended for abandonment in H. Doc. 467, 69th 
Cong., 1st sess. 
4. Completion date not available. 
5. No funds available under this project. Work being 
carried on under "Appropriation, Flood Control, Mississippi 
River and tributaries." 
13-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 13-D OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
Project 
Big Creek Canal, Millington, TN 
Big Creek and L'Anguille River, White 
River Basin, AR 1 
Bradford, TN 
Clarendon to Laconia Circle, 
White River Basin, AR 1 
Cottonwood Slough pumping plant, IL2 
Drinkwater Sewer, MO 
Dyersburg, TN2 
Dyersburg, TN (SW) 
Grays Creek Canal 
Shelby Co., TN 
Huntingdon, TN 
Long Lake Area 
Helena, AR 
Memphis, Wolf River, and 
Nonconnah Creek, TN 
Mounds and Mound City, 
Ohio River Basin, IL 4 
Nixon Creek, TN 2 
Nonconnah Blvd., 
Nonconnah Creek, TN 
N. Second St., Memphis, TN 
(Wolf River Bridge) 
Sandy Creek 
Jackson, TN 
St. Francis River 
Highway No.90 AR 
Treasure Island, MO 
US Hwy 51, Nonconnah Creek, TN 
W. Hickman, Area, Hickman, KY 
Mo. and Yr. 
Deauthorized 
6 May 81 
6 May 81 
Sep 1980 
Jul 1983 
For Last 
Full Report 
See Annual 
Report For: 
1977 
1937 
1984 
1964 
1984 
1962 
1981 
1985 
1983 
1983 
1960 
1955 
1952 
1983 
1983 
1985 
1985 
1981 
1984 
1983 
Cost to Sep. 1986 
Operation 
and 
Construction Maintenance 
$ 70,363 $ - 
95,061 
147,000 
1,494,828 
229,6493 
1,820,869 
155,280 
2,900,281 
61,281 
11,141,199 
1,132,704 
62,821 
249,999 
249,999 
238,000 
161,000 
861,528 
369,200 
1,674,180 
1. Inactive, awaiting local cooperation. 
2. Authorized by Chief of Engineers under small project 
authority, Sec. 205, Flood Control Act of 1948, as amended. 
3. Includes $21,863 contributed funds. 
4. Work being completed under Mississippi River and 
Tributaries project. 
5. Exclusive of Cache River Pumping Station. 
13-6 
Mo. and Yr. 
Completed 
Dec 1983 
Feb 1964 
Jun 1980 
Jun 1962 
Oct 1976 
Aug 1985 
May 1959 
Oct 19596 
Dec 1951 
Nov 1981 
Sep 1980 
Dec 1984 
Sep 1985 
Mar 1978 
Mar 1983 
Oct 1976

MEMPHIS, TN, DISTRICT 
TABLE 13-E ACTIVE GENERAL INVESTIGATIONS 
(96x3121) 
Federal Cost Totals by 
Item and CWIS Number FY 86 Categories 
SURVEYS (Category 100) 
Miscellaneous Activities (170) 
Special Investigations (171) -17250 $ 24,026 
COLLECTIONS AND STUDY OF BASIC DATA (Category 200) $ 24,026 
Flood Plain Management Services (250) 
Flood Plain Management Services 242,017 
TOTAL (Category 200) $242,017 
GRAND TOTAL GENERAL INVESTIGATIONS $266,043 
13-7

ST. LOUIS, MO, DISTRICT * 
This district comprises those portions of southwestern 
Illinois and eastern Missouri embraced in 
drainage basin of Mississippi River and its western 
tributaries, exclusive of the Missouri River, from the 
mouth of the Ohio River to mile 300, and of its eastern 
tributaries to Hamburg Bay at mile 261 on left bank, 
exclusive of tributary basin of Illinois Waterway upstream 
of new La Grange Lock and Dam at mile 80.15 
above confluence of the Illinois and Mississippi Rivers. 
District also includes drainage basin in Missouri 
tributary to the Little River diversion channel. Report 
on the Mississippi River between the Missouri River 
and mile 300 is included in separate report on the 
Mississippi River between the Missouri River and 
Minneapolis, MN. Report on the portion of the Illinois 
River downstream of new La Grange Lock and Dam is 
included in report of the Chicago District on the Illinois 
Waterway, Illinois and Indiana. 
IMPROVEMENTS 
Navigation 
1. Illinois Waterway, IL 
(St. Louis Dist.) ................. 
2. Kaskaskia River, IL .............. 
3. Mississippi River between Missouri 
and Minneapolis, MN (St. Louis Dist.) 
(Includes L&D 26 Replacement) ..... 
4. Mississippi River between Ohio 
and Missouri Rivers, MO, and IL .... 
Flood Control 
5. East St. Louis and vicinity, IL ....... 
6. Eldred and Spankey Drainage and 
Levee District, IL ................ 
7. Hartwell Drainage and Levee 
D istrict, IL ..................... 
8. Hillview Drainage and Levee 
D istrict, IL ..................... 
9. Kaskaskia Island Drainage and 
Levee District, IL ............... 
10. Mauvaise Terre Drainage 
and Levee District, IL ............. 
11. Meramec River Basin, MO ......... 
11A. Meramec Park Lake, MO .......... 
11B. Pine Ford Lake, MO .............. 
12. McGee Creek Drainage and Levee 
D istrict, IL ..................... 
13. Meredosia, IL, and Meredosia, 
Willow Creek, and Coon Run 
Drainage and Levee District, IL ..... 
14. Meredosia Lake and Willow Creek 
Drainage and Levee District, IL ..... 
15. Mississippi River Agricultural 
Area 8, M O .................... 
Page Flood Control (cont.) 
16. Nutwood Drainage and Levee 
14-2 District, IL .................... 
14-2 17. Perry County Drainage and Levee 
Districts Nos. 1, 2, and 3, MO ....... 
18. Rend Lake, Big Muddy River, IL .... 
14-2 19. Wood River Drainage and 
Levee District, IL ................ 
14-2 20. Inspection of completed flood 
control projects ................. 
21. Navigation work under 
14-3 special authorization .............. 
22. Flood control work under 
14-3 special authorization .............. 
14-3 Multiple-Purpose Project 
Including Power 
14-4 23. Clarence Cannon Dam and Mark Twain 
Salt River, MO .................. 
14-4 
14-4 
14-4 
14-5 
General Investigations 
24. Active investigations ................ 
Tables 
14-5 Table 14-A 
Table 14-B 
14-5 Table 14-C 
14-5 
14-6 
14-6 
Table 14-D 
Table 14-E 
Table 14-F 
Cost and Financial Statement . 
Authorizing Legislation ...... 
Other Authorized 
Navigation Projects ......... 
Lakes, Levees, and 
Recreational Facilities ....... 
Other Authorized Flood 
Control Projects ............ 
Active General 
Investigations (96X3121) ..... 
Page 
14-6 
14-6 
14-7 
14-7 
14-7 
14-7 
14-8 
14-8 
14-8 
14-9 
14-11 
14-13 
14-13 
14-14 
14-16 
14-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. ILLINOIS WATERWAY, IL 
(ST. LOUIS DIST.) 
See report on Illinois Waterway, IL and IN, under 
Rock Island District. 
2. KASKASKIA RIVER, IL 
Location. The river rises in Champaign County, IL, 
about 5 miles northwest of Urbana, in east-central part 
of State. It flows southwesterly about 325 miles and 
empties into Mississippi River about 8 miles above 
Chester, Il, or about 118 miles above mouth of Ohio 
River. (See Cincinnati sheet of maps of United States 
published by Army Map Service, scale 1:500,000.) 
Previous project. For details see Annual Report for 
1896, page 171. 
Existing project. Improvement for navigation 
provides a channel 9 feet deep and 225 feet wide from 
mouth to Fayetteville, IL. Improvement consists of 
enlarging present channel where required, making 
overbank cutoffs to eliminate sharp bends, and construction 
of a dam at mile 0.8 with a single lock 84 feet wide 
and 600 feet long, at an estimated total Federal project 
cost (1984) of $145,060,000. Non-Federal project cost is 
$7,665,000, of which $1,500,000 is local contribution. 
Local cooperation. State of Illinois passed legislation 
authorizing Illinois Department of Public Works and 
Buildings to enter into assurances of local cooperation 
with the United States. These assurances have been 
furnished and were accepted on behalf of the United 
States on Sept. 10, 1965; these assurances were 
supplemented on Aug. 7, 1972, to incorporate the 
provisions of PL 91-646. 
Operations and results during fiscal year. Work is 
complete on the lock and dam, railroad relocations, 
and the grade control structure. Engineering and 
design continued on remaining construction items. 
Project is essentially complete. 
Maintenance. Hired labor performed operation and 
maintenance of the project. 
3. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND MINNEAPOLIS, 
MN. (ST. LOUIS DIST.) 
(INCLUDES L&D 26 REPLACEMENT) 
See separate section entitled "Mississippi River between 
Missouri River and Minneapolis, MN," printed 
in the Annual Report of the Chief of Engineers. 
4. MISSISSIPPI RIVER BETWEEN 
OHIO AND MISSOURI RIVERS, 
MO AND IL 
Location. Mississippi River rises in Lake Itasca, 
MN, and from that lake flows southerly about 2,340 
miles and empties into the Gulf of Mexico. Portion 
included in this report embraces the 195-mile section 
known as middle Mississippi, between tributary Ohio 
and Missouri Rivers about 974 to 1,169 miles from the 
gulf. See folder by Corps of Engineers of Navigation 
Charts, Middle and Upper Mississippi River, Cairo, IL, 
to Minneapolis, MN. 
Previous projects. For details see page 1879 of 
Annual Report for 1915, and page 1014 of Annual 
Report for 1938. 
Existing project. The existing project provides for 
obtaining and maintaining a minimum channel depth 
of not less than 9 feet, a minimum width of not less than 
300 feet at low water, with additional widths in bends 
from mouth of Ohio River (about 974 miles from gulf) 
to northern boundary of city of St. Louis, mile 191, 
thence 200 feet wide, with additional width in bends to 
mouth of Missouri River, mile 195; to be obtained: (1) 
by regulating works, for closing secondary channels, 
contracting river by building new banks where river 
width is excessive and protecting new and old banks 
from erosion where necessary to secure permanency at 
an estimated total Federal cost (1986) of $181,000,000; 
(2) by dredging to maintain project channels; (3) by 
construction of works authorized for Chain of Rocks 
reach in 1945 River and Harbor Act, which approved a 
comprehensive plan for development of the river at 
Chain of Rocks to provide for construction of a lateral 
canal at a cost of $59,720,600; and (4) by construction of 
a fixed-crest rock-fill dam about 900 feet below Chain 
of Rocks Bridge, authorized by 1958 River and Harbor 
Act, at cost of $4,353,000, excluding $7,000 costs to 
Coast Guard for aids to navigation. Estimated total 
Federal project cost (1986) is $245,073,600. A small 
boat harbor opposite Chester, IL, was deauthorized 
and excluded from foregoing cost estimate. See H. Doc. 
669 (76th Cong., 3d sess.) for report of Chief of 
Engineers dated Feb. 27, 1940, containing a general 
plan for improvement of Mississippi River between 
Coon Rapids Dam and mouth of Ohio River for 
purposes of navigation, power development, flood 
control, and needs of irrigation. 
Local cooperation. None required. 
Terminal facilities. Existing facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Regulating 
Works: Contract was continued on stone dike 
and revetment construction as was engineering and 
design and supervision and administration. Construction 
on existing project began in 1881 and project has 
been in beneficial use practically from its inception. 
Projects on Dam 27 and Chain of Rocks are complete. 
Work on the project is about 71 percent complete. 
Channel as a whole has been greatly improved by the 
work completed to date. Dredging is required at low 
stages to remove temporary shoals and maintain required 
channel depths. River is generally above 10-foot 
stage, St. Louis gage, from latter part of February to 
the latter part of August, during which time project 
channel depths generally prevail without dredging. 
Maintenance. Work consisted of 2,230 feet of dike 
and 18,755 feet of revetment repair. U.S. plant and 
14-2

ST. LOUIS, MO, DISTRICT 
hired labor performed channel dredging removing 
2,925,100 cubic yards of material from main channel. 
Condition and operation studies, recreation planning, 
engineering and design, and operation and maintenance 
of Lock and Dam 27 continued. 
Flood Control 
5. EAST ST. LOUIS AND VICINITY, IL 
Location. Project is in St. Clair and Madison 
Counties, IL, on the left bank of the Mississippi River 
between river miles 175 and 195 above the Ohio River. 
Project includes all bottomlands between bluffs on the 
east and Mississippi River and Chain of Rocks Canal 
on the west, and extends from Cahokia diversion 
channel on the north to Prairie du Pont Creek on the 
south. (See Corps of Engineers Navigation Charts, 
Middle and Upper Mississippi River, Cairo, IL, to 
Minneapolis, MN.) 
Existing project. The 1936 Flood Control Act 
authorized raising and enlarging existing levee 
systems by construction or reconstruction of 19.8 miles 
of levee, including 3.1 miles of floodwall, together with 
necessary appurtenant works consisting of gravity 
drainage structures, highway and railroad closure 
structures, alterations and reconstruction of existing 
pumping plants, alterations to railroad bridges and 
approaches at levee crossings, service roads on levee 
crown, and seepage control measures. Work under this 
authorization provides the area protection against a 
flood of about 200-year frequency. The completed 10 
miles of levee along Chain of Rocks Canal and Lock 27 
provide flood protection on the landward side integral 
with and to the same degree as the East St. Louis levee. 
Final cost of work under this authorization is 
$22,550,100. The Flood Control Act of 1965 modified 
existing project to provide for channel improvements, 
diversion ditches, flood plain detention areas, a 
reservoir on Little Canteen Creek, and a pumping 
plant to considerably reduce damages resulting from 
interior flooding. This act also authorized reconstruction 
of a channel stabilization dam in Cahokia Creek 
diversion channel to provide protection to adjacent 
levees and bridges from scour and eventual loss. Post 
authorization studies have indicated that flood plain 
detention areas, the reservoir on Little Canteen Creek 
and other related flood control measures in the 
Cahokia-Harding Ditch Area are not economically 
feasible. Also, further studies of the channel 
stabilization dam in Cahokia Creek diversion channel 
have been deferred due to lack of support from the 
local sponsor of the project. Estimated total Federal 
project cost of work under this authorization is 
$33,600,000 (1985), $22,020,000 for Cahokia-Harding 
Ditch Area, and $11,580,000 for Blue Waters Ditch. 
Non-Federal cost is $20,770,000. 
Local cooperation. Local interests have fully complied 
with the requirements of local cooperation for 
work under the 1936 authorization. For work authorized 
by Flood Control Act of 1965 requirements of 
local cooperation are fully described on page 14-4 of 
Fiscal Year 1980 Annual Report. Formal assurances 
were accepted on the Blue Waters Ditch area on Jun. 
25, 1981. 
Operations and results during fiscal year. 
Construction of project modifications authorized by 
Flood Control Act of 1965 was continued. This work 
included ditching contracts and the Blue Waters Ditch 
pumping station. Work authorized by Flood Control 
Act of 1936 is complete. 
6. ELDRED AND SPANKEY DRAINAGE 
AND LEVEE DISTRICT, IL 
Location. The levee district is in Greene County, Ii, 
on the left bank of the Illinois River between miles 23.8 
and 32.3 above the Mississippi River. (See Quincy, ILMO, 
sheet of maps of the United States, published by 
Army Map Service, scale 1:250,000.) 
Existing project. Project provides for raising and 
enlarging 15.9 miles of levees, altering discharge line 
of pumping station, and construction of two highway 
closure structures and seepage control measures. 
Project will provide protection to 10,470 acres of land, 
9,735 of which are highly productive agricultural 
lands, against a flood of 50-year frequency. Estimated 
total Federal project cost (1985) is $6,380,000. Non- 
Federal cost is $953,000. Project was authorized by the 
1962 Flood Control Act (H. Doc. 472, 87th Cong., 2nd 
sess.). 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-4 of Fiscal Year 
1980 Annual Report. Local interests have indicated a 
willingness to meet the terms of local cooperation. 
Operations and results during fiscal year. Preconstruction 
planning was continued under the 
general investigation appropriation. Construction has 
not begun. 
7. HARTWELL DRAINAGE AND 
LEVEE DISTRICT, IL 
Location. The levee district is in Greene County on 
the left bank of the Illinois River between miles 38.2 
and 43.1 above the Mississippi River. (See Quincy, ILMO, 
sheet of maps of the United States, published by 
Army Map Service, scale 1:250,000.) 
Existing project. Project provides for construction 
of 12.3 miles of new or enlarged levees, altering discharge 
line of pumping station and construction of 
seepage control measures. Project will provide protection 
to 9,630 acres of land, 8,955 of which are highly 
productive agricultural lands against a flood of 50- 
year frequency. Estimated total Federal project cost 
(1985) is $12,400,000. Non-Federal cost is $1,120,000. 
Project was authorized by the 1962 Flood Control Act 
(H. Doc. 472, 87th Cong., 2d sess.) 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-5 of Fiscal Year 
14-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
1980 Annual Report. Local interests have indicated a 
willingness to meet the terms of local cooperation. 
Operations and results during fiscal year. Preconstruction 
planning was deferred due to the 
inability of the project to qualify for continuation of 
funding. 
8. HILLVIEW DRAINAGE AND 
LEVEE DISTRICT, IL 
Location. The levee district is in Greene and Scott 
Counties, IL, on the left bank of the Illinois River 
between miles 43.2 and 50.0 above the Mississippi 
River. (See Qunicy, IL-MO, sheet of maps of the United 
States, published by Army Map Service, scale 
1:250,000.) 
Existing project. Project provides for construction 
of 14.3 miles of levee, alteration of discharge lines for 
three existing pumping stations, construction of a 
railroad closure structure, and seepage control measures. 
Project will provide protection to the Village of 
Hillview and to 13,070 acres of agricultural land 
against a flood of 50-year frequency. Estimated total 
Federal project cost (1985) is $12,300,000. Non- 
Federal cost is $1,220,000. Project was authorized by 
the 1962 Flood Control Act (H. Doc. 472, 87th Cong., 2d 
sess.) 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-6 of Fiscal Year 
1980 Annual Report. Local interests have indicated a 
willingness to meet the terms of local cooperation. 
Operations and results during fiscal year. Preconstruction 
planning was deferred due to the 
inability of the project to qualify for continuation of 
funding. 
9. KASKASKIA ISLAND DRAINAGE 
AND LEVEE DISTRICT, IL 
Location. In Randolph County, IL, on the right bank 
of the Mississippi River between miles 111 and 116 
above the mouth of the Ohio River. (See Paducah, KY, 
IL, MO, IN, map published by Army Map Service, 
scale 1:250,000.) 
Previous project. For details, see page 1375 of 
Annual Report for 1950. 
Existing project. Project area contains about 9,460 
acres only partially protected against flood stage of 
38.5 feet on the Chester, IL, gage. Flooding occurs 
about once in every 7.3 years with an average duration 
of 26 days, causing substantial damage. The 1962 
Flood Control Act (H. Doc. 519, 87th Cong., 2d sess.) 
provides for enlarging and raising the existing levee 
about 8 feet to provide protection against a flood 
having a frequency of once in 50 years. Estimated total 
Federal project cost (1986) is $14,100,000. Non- 
Federal cost is $2,100,000. 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-6 of Fiscal Year 
1980 Annual Report. Formal assurances from the 
Kaskaskia Island Drainage and Levee District were 
accepted on behalf of the United States on Jan. 23 1980. 
Operations and results during fiscal year. Preconstruction 
planning is complete. Construction is 
complete on the gravity drains. Plans and specifications 
for raising and enlarging the levee are complete and 
construction was continued on this item. 
10. MAUVAISE TERRE DRAINAGE 
AND LEVEE DISTRICT, IL 
Location. The levee district is in Scott County, IL on 
the left bank of the Illinois River between miles 63.5 
and 67.0 above the Mississippi River. (See Quincy, ILMO, 
sheet of maps of the United States, published by 
Army Map Service, scale 1:250,000). 
Existing project. Project provides for raising a 
portion of the existing levee and construction of two 
railroad closure structures. Project will provide 
protection to 5,700 acres of land against a flood of 100- 
year frequency. Estimated total Federal project cost 
(1986) is $1,100,000. Non-Federal cost is $230,000. 
Project was authorized by the Energy and Water 
Development Appropriation Act of 1985, Public Law 
98-360, 98th Cong., 2nd Session. 
Local cooperation. The village of Naples, IL, signed 
a letter of intent, dated March 13, 1985, indicating a 
willingness to comply with the terms of local cooperation 
including provisions of the Uniform Relocations 
and Real Property Acquisition Policy Act of 1970 (PL 
91-646) and Section 221 of the Flood Control Act of 
1970 (PL 91-611). Local Cooperation requirements are: 
furnish without cost to the United States all lands, 
easements, and rights-of-way necessary and accomplish 
all relocations necessary for the construction of the 
project; hold and save the United States free from 
damages due to the construction works, save and 
except damages due to the fault or negligence of the 
United States or its contractor; and maintain and 
operate all the works after completion in accordance 
with regulations prescribed by the Secretary of the 
Army. 
Operations and results during fiscal year. Planning 
was completed on all items. 
11. MERAMEC RIVER BASIN, MO 
Location. The basin lies within the State of Missouri 
and comprises 3,980 square miles. The river is a west 
bank tributary of the Mississippi River at mile 161 
above mouth of Ohio River. Major streams in the basin 
include the Meramec, Big, and Bourbeuse Rivers. The 
basin extends about 100 miles southwesterly from St. 
Louis into the Ozark Highlands. (See St. Louis, MO, 
and Rolla sheets of maps of the United States, 
published by Army Map Service, scale 1:250,000.) 
Existing project. The project provides for the construction 
of Meramec Park and Union Lakes, authorized 
by the 1938 Flood Control Act; and Pine Ford, 
14-4

ST. LOUIS, MO, DISTRICT 
Irondale, and 1-38 Lake projects, and 19 angler-use 
sites, authorized by the 1966 Flood Control Act. Under 
the plan, Irondale and 1-38 Lakes will reduce flood 
damages in the upper Big and Bourbeuse Rivers. 
Meramec Park, Union, and Pine Ford Lakes will 
substantially reduce flooding in the lower basin area 
and will lower flood crests on the Mississippi River. 
Project will also provide water supply, water quality 
control, recreation, and fish and wildlife conservation. 
(See Table 14-D for additional data on this comprehensive 
project.) 
11A. MERAMEC PARK LAKE, MO 
Location. Dam will be at mile 108.7 on Meramec 
River in Franklin County near Sullivan, MO. 
Reservoir will be mainly in Crawford, Franklin, and 
Washington counties, MO. (See St. Louis, MO, sheet of 
maps of the United States, published by Army Map 
Service, scale 1:250,000.) 
Existing project. Project as authorized by 1938 
Flood Control Act provides for construction of an earth 
dam about 167 feet high with a crest length of 3,000 
feet. Reservoir will provide 1 million acre-feet of 
storage and provide flood protection for 11,862 acres of 
flood plain in the Meramec River valley above the 
mouth of Bourbeuse River, and partial protection for 
20,209 acres of land below the Bourbeuse. Project will 
also provide water supply, water quality control, 
storage, and recreation, and fish and wildlife benefits. 
Estimated total project cost (1981) is $220,000,000, 
including $22,506,000 local reimbursement for water 
supply. 
Local cooperation. Local interest must contribute 
toward cost of project for storage allocated to water 
supply in accordance with the Water Supply Act of 
1958. State of Missouri, acting through its State Water 
Resources Board and under authority of the General 
Assembly of State of Missouri, executed assurances for 
water supply on Aug 23, 1967. The assurances were 
reviewed by the Office of the Attorney General, State 
of Missouri, and it is his opinion that the State of 
Missouri has the legal authority and financial 
capability to execute said assurances. These assurances 
have been approved by the Chief of Engineers. A 
water-supply contract will be entered into with the 
sponsor before any use of the water-supply storage 
provided under this contract. 
Operations and results during fiscal year. Project 
was deauthorized by Public Law 97-128. Land is being 
disposed of in accordance with deauthorizing act. 
Maintenance. Hired labor forces performed operations 
and maintenance of existing facilities. 
liB. PINE FORD LAKE, MO 
Location. Dam is on Big River at mile 43.8, about 45 
miles southwest of St. Louis. The Big River is a tributary 
of the Meramec. Lake will extend about 34 miles 
up Big River. (See St. Louis, MO, sheet of maps of the 
United States, published by Army Map Service, scale 
1:250,000.) 
Existing project. Project provides for construction 
of a compacted earth-fill dam with a concrete chute 
spillway. Dam will be 141 feet high and 2,070 feet long. 
Construction of new roads, improvements of existing 
roads, alterations to pipeline, power and telephone 
lines, and construction of recreational facilities are 
included. Maximum storage capacity will be 285,000 
acre-feet. Estimated total project cost (1984) is 
$147,000,000, of which $8,173,200 and $22,900,000 are 
local reimbursements for water supply and recreation 
and fish and wildlife respectively. 
Local cooperation. Local interests must contribute 
toward cost of project for storage allocation to water 
supply in accordance with the Water Supply Act of 
1958. 
Operations and results during fiscal year. Preconstruction 
planning previously funded but not 
completed. 
12. McGEE CREEK DRAINAGE 
AND LEVEE DISTRICT, IL 
Location. The levee district is in Brown and Pike 
Counties, IL, on the right bank of Illinois River 
between miles 67.2 and 75.1 above the Mississippi 
River. (See Kansas City sheet of maps of United States, 
published by Army Map Service, scale 1:500,000.) 
Existing project. Project provides for reconstruction 
of 14.7 miles of levee, construction of a new pumping 
plant, closure structure, and seepage control measures. 
Project will provide protection to about 12,080 acres of 
agricultural land against a flood of about 50-year 
frequency. Estimated total Federal project cost (1983) 
is $25,500,000. Non-Federal cost is $930,000. Project 
was authorized by 1962 Flood Control Act (H. Doc. 
472, 87th Cong., 2d sess.). 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-9 of Fiscal Year 
1980 Annual Report. Local interests have executed 
assurances in compliance with Public Law 91-611 and 
Public Law 91-646. 
Operations and results during fiscal year. The 
project is essentially complete. 
13. MEREDOSIA, IL, AND MEREDOSIA, 
WILLOW CREEK, AND 
COON RUN DRAINAGE AND 
LEVEE DISTRICTS, IL 
Location. The levee district is in Morgan and Scott 
Counties, IL, on the left bank of the Illinois River 
between miles 67.0 and 72.2 above the Mississippi 
River. (See Quincy, IL-MO sheet of maps of the United 
States, published by Army Map Service, scale 
1:250,000.) 
Existing project. Project provides for construction 
of 11.0 miles of new or enlarged levee, a pumping 
14-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
plant, closure structure, and seepage control measures. 
Project will provide protection to 8,215 acres of land, 
7,640 of which are highly productive agricultural 
lands, and 575 acres of noncrop and farmsteads 
against a flood of 50-year frequency. Estimated total 
Federal project cost (1986) is $12,100,000. Non- 
Federal cost is $1,030,000. Project was authorized by 
the 1962 Flood Control Act (H. Doc. 472, 87th Cong., 2d 
sess.). 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-9 of Fiscal Year 
1980 Annual Report. Local interests have indicated a 
willingness to meet the terms of local cooperation. 
Operations and results during fiscal year. 
Preconstruction planning was continued under the 
general investigation appropriation. Construction has 
not begun. 
14. MEREDOSIA LAKE AND WILLOW 
CREEK DRAINAGE AND LEVEE 
DISTRICT, IL 
Location. The project is in Cass and Morgan Counties, 
IL, on the left bank of the Illinois River between 
miles 72.2 and 79.0 above the Mississippi River. (See 
Qunicy, IL-MO sheet of maps of the United States, 
published by Army Maps Service, scale 1:250,000.) 
Existing project. Project provides for construction of 
15.9 miles of new or enlarged levee, closure structure, 
drainage facilities, and seepage control measures. 
Project will provide protection to 7,510 acres of land, 
6,980 of which are highly productive agricultural 
lands, and 530 acres of non crop and farmsteads 
against a flood of 50-year frequency. Estimated total 
Federal project cost (1985) is $10,000,000. Non- 
Federal cost is $560,000. Project was authorized by the 
1962 Flood Control Act (H. Doc. 472, 87th Cong., 2d 
sess.). 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-10 of Fiscal Year 
1980 Annual Report. Local interests have indicated a 
willingness to meet the terms of local cooperation. 
Operations and results during fiscal year. Preconstruction 
planning was continued under the 
general investigation appropriation. Construction has 
not begun. 
15. MISSISSIPPI RIVER 
AGRICULTURAL AREA 8, MO 
Location. Area 8 is in Lincoln and Pike Counties, 
MO, on west bank of Mssissippi River between river 
miles 249 and 261 above the Ohio River. Small community 
of Elsberry lies within the area. (See Quincy 
sheet of maps of the United States, published by Army 
Map Service, scale 1:250,000.) 
Existing project. The 1966 Flood Control Act (H. 
Doc. 510, 89th Cong., 2d sess.) authorized the raising 
and enlarging of existing levees to provide 24.4 miles 
of riverfront, flank, and back levees and construction 
of appurtenant works consisting of drainage structure, 
highway and railroad closure structures, and alterations 
to existing pumping plants. The project has been 
reduced in scope to consist of replacing one existing 
drainage structure, replacing an obsolete stream 
driven pump unit with a new one of 150 cubic feet per 
second capacity, and rehabilitation of the pump 
station. Project will afford protection to the area 
against a flood of 50-year frequency. Estimated total 
Federal project cost (1980) is $2,400,000. Non-Federal 
cost is $20,000. 
Local cooperation. Fully complied with. See page 
14-10 of FY 1980 Annual Report. 
Operations and results during fiscal year. Project 
is complete. Operation and maintenance manual was 
completed. 
16. NUTWOOD DRAINAGE AND 
LEVEE DISTRICT, IL 
Location. The levee district is in Greene and Jersey 
Counties, IL, on the left bank of the Illinois River 
between miles 15.2 and 23.7 above the Mississippi 
River. (See Quincy, IL-MO, sheet of maps of the United 
States, published by Army Map Service, scale 
1:250,000.) 
Existing project. Project provides for raising and 
enlarging 11.4 miles of levee, construction of 1.0 mile 
of new levee, altering discharge line of pumping 
station, and construction of seepage control measures. 
Project will provide protection to 10,360 acres of land, 
9,635 of which are highly productive agricultural 
lands against a flood of 50-year frequency. Estimated 
total Federal project cost (1986) is $6,510,000. Non- 
Federal cost is $450,000. Project was authorized by the 
1962 Flood Control Act (H. Doc. 472, 87th Cong., 2d 
sess.). 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-11 of Fiscal Year 
1980 Annual Report. Local interests have indicated a 
willingness to meet the terms of local cooperation. 
Operations and results during fiscal year. Preconstruction 
planning was continued under the 
general investigation appropriation. Construction has 
not begun. 
17. PERRY COUNTY DRAINAGE 
AND LEVEE DISTRICTS 
NOS. 1, 2, & 3, MO 
Location. Districts are in Perry County, MO, and 
Randolph County, IL, on the right bank of the Mississippi 
River between river miles 95 and 111 above the 
mouth of the Ohio River. (See Paducah, KY, IL, MO, 
IN, map published by Army Map Service, scale 
1:250,000.) 
Previous project. For details, see 475 of Annual 
Report for 1968. 
14-6

ST. LOUIS, MO, DISTRICT 
Existing project. Project area contains about 
26,881 acres protected from floods of the Mississippi 
River by levees. However, when Mississippi River 
stage exceeds 13 feet on the Chester, IL, gage, 
substantial damage results from impoundment of 
precipitation or seepage, or a combination thereof. 
Authorized project provides for construction of four 
pumping stations to reduce interior flooding. 
Estimated total Federal project cost (1982) is 
$8,812,000. 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-11 of Fiscal Year 
1980 Annual Report. Assurances were furnished by 
local interests (presently, Boil Brule Levee District, 
MO). on Nov. 16, 1978, and were accepted Nov. 27, 
1978, by the District Engineer under delegated 
authority. 
Operations and results during fiscal year. Construction 
is essentially complete on all four pumping 
stations. 
18. REND LAKE, BIG MUDDY 
RIVER, IL 
Location. The lake is in Franklin and Jefferson 
Counties in southern Illinois. The dam is on Big Muddy 
River, 103.7 miles upstream from its confluence with 
the Mississippi River, and about 3 miles northwest of 
Benton, IL. (See Belleville sheet of maps of United 
States, published by Army Map Service, scale 
1:250,000, and Geological Survey quadrangle maps, 
1:62,500.) 
Existing project. The project provides for construction 
of an earth dam, ungated concrete spillway, 
relocation of roads and utilities, recreational facilities, 
access roads, and service facilities. In addition, two 
subimpoundment dams were constructed on upper 
arms of reservoir to enhance fish and wildlife value of 
project. Reservoir has an area of 24,800 acres, and a 
storage capacity of 294,000 acre-feet. Project provides 
flood control, water supply, low-flow regulations, conservation 
of fish and wildlife, recreation, and area 
development. Estimated total Federal project cost 
(1983) is $43,100,900, of which $12,197,700 is for lands 
and damages. Non-Federal local contribution for 
water supply is $9,941,300. Federal cost for code 711 
recreation facilities is $1,060,900. 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-12 of Fiscal Year 
1980 Annual Report. Assurance of local cooperation 
and water supply contract have been executed and 
approved by the Secretary of the Army. 
Operations and results during fiscal year. Real 
estate activities in connection with project completion 
were performed. Lands acquired to date are 39,819 
acres in fee and 906 acres in easements. Project is 
essentially complete. 
Maintenance. Hired labor forces performed operation 
and maintenance of Rend Lake Reservoir. 
19. WOOD RIVER DRAINAGE AND 
LEVEE DISTRICT, IL 
Location. In Madison County, IL, on left bank of 
Mississippi River between river miles 195 and 203 
above Ohio River. District includes bottom lands between 
river and bluffs and extends from Cahokia 
diversion channel on the south to opposite lock and 
dam No. 26 at Alton, IL, on the north. Small industrial 
cities of Hartford, Wood River, Roxana, and East 
Alton and part of Alton riverfront, lie within the 
district. (See Corps of Engineers Navigation Charts, 
Middle and Upper Mississippi River, Cairo, IL, to 
Minneapolis, MN.) 
Existing project. The 1938 Flood Control Act 
authorized raising, enlarging, and extending existing 
levee system to provide 20.8 miles of levees and 
construction of appurtenant works consisting of 
gravity drainage structures, highway and railroad 
closure structures, alterations to existing or construction 
of new pumping plants; surfacing service road on levee 
crown, making necessary alterations to railroad tracks 
and bridges at levee crossings, seepage corrective 
measures and construction of a low-water dam at 
mouth of Wood River. Project will afford protection to 
this district against a flood of about 200-year 
frequency. Estimated total construction cost (1982) is 
$18,600,000 (excluding $23,000 contributed funds). 
Flood Control Act of 1965 modified 1938 Flood Control 
Act to provide for construction of a pumping station 
with collector ditches and necessary appurtenant 
facilities for removal of water impounded by existing 
levee. This portion of the project has been declared 
inactive. 
Local cooperation. Fully complied with for work 
authorized by 1938 Flood Control Act. 
Operation and results during fiscal year. Work 
authorized by the 1938 Flood Control Act is complete 
except for a closure structure. Construction was 
initiated on this item. 
20. INSPECTION OF COMPLETED 
FLOOD PROJECTS CONTROL 
Inspection of completed work was accomplished at a 
cost of $388,483 for the fiscal year. Total cost as of end 
of fiscal period is $5,459,419. 
21. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
Preauthorization studies cost for fiscal year were 
$24,849 for Southeast Missouri Port study. 
14-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
22. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended (preauthorization). 
Preauthorization study costs for fiscal year were 
$47,271 for Columbia Levee and Drainage District, 
Monroe County, IL; $67,766 for Crooked Creek, 
Bollinger County, MO; $34,325 for E. Cape Girardeau 
Main Ditch, IL; $218,432 for St. Peters, MO; and 
$33,036 for Modoc Levee and Drainage District, IL. 
Emergency Bank Protection.. 
Costs for fiscal year were $22,753 for Illinois River, 
Hardin, IL. 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Cong., and antecedent legislation). 
Federal costs for the fiscal year were $160,578 for 
disaster preparedness, and $39,987 for disaster 
preparedness. 
Multiple-Purpose Project 
Including Power 
23. CLARENCE CANNON DAM AND 
RESERVOIR SALT RIVER, MO 
Location. Salt River rises in Schuyler County, about 
12 miles south of Missouri-Iowa State line. It flows 
southeasterly about 192 miles and empties into Mississippi 
River about 2 miles above Louisiana, MO, or 
about 284 miles above mouth of Ohio River. (See 
Kansas City and Quincy sheets of maps of United 
States published by Army Map Service, scale 
1:500,000, and Geological Survey quadrangle maps, 
1:250,000.) 
Previous project. For details, see page 645 of 
Annual Report for 1968. 
Existing project. Project provides for construction 
of a multiple-purpose reservoir, including power, flood 
control, water supply, navigation storage, pollution 
abatement, fish and wildlife conservation, and recreation. 
Dam consists of a compacted earth embankment 
with a concrete spillway controlled by tainter gates. 
Dam and spillway are about 1,700 feet long. Spillway 
structure consists of an ogee overflow section surmounted 
by four 50- by 30-foot tainter gates. Reservoir 
will have a storage capacity of 1,428,000 acre-feet for 
use of flood control, future domestic and industrial 
water supply, sediment storage, and power generation. 
Project plan provides for installation of one 27,000 KW 
conventional unit and one 31,000 KW reversible unit 
for pumped storage operations. Total Federal project 
cost estimate (1984) is $330,000,000 of which $22,420,000 
is for lands and damages; $14,300,000 for water 
supply; $76,000,000 for hydropower. 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-13 of Fiscal Year 
1980 Annual Report. Assurances have been received 
from the State of Missouri and approved by the Chief 
of Engineers. 
Operations and results during fiscal year. Work 
is complete on all major items. Work remaining 
consists of minor items on recreation facilities. Lands 
acquired to date are 55,277 acres in fee and 10,068 
acres in easements. Project is essentially complete. 
General Investigations 
24. ACTIVE INVESTIGATIONS 
See Table 14-F which covers: Surveys, Collection 
and study of basic data, and Research and development 
activities. 
14-8

ST. LOUIS, MO, DISTRICT 
TABLE 14-A COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
2. Kaskaskia River 
IL (Regular 
Funds) 
(Contrib. Funds) 
4. Mississippi River 
Between Ohio and 
Missouri Rivers 
(Includes Chain 
of Rocks) 
5. East St. Louis and 
Vicinity, IL 
(Contrib. Funds) 
6. Eldred & Spankey 
Drainage and Levee 
District, IL 
7. Hartwell Drainage 
& Levee District, 
IL 
8. Hillview Drainage 
& Levee District 
IL 
9. Kaskaskia Island 
Drainage & Levee 
District, IL 
10. Mouvaise Terre 
Drainage & Levee 
District, IL 
11A. Meramec Park 
Lake, MO 
11B. Pine Ford 
Lake, MO 
12. McGee Creek 
Drainage & 
Levee District, 
IL 
13. Meredosia, IL, 
and Meredosia, 
Willow Creek and 
Coon Run Drainage 
& Levee Districts, 
IL 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
$400,000 $5,209,000 $5,300,000 $14,300,000 
388,140 3,885,032 6,419,905 14,204,126 
1,131,856 
1,036,248 
587,000 1,370,000 1,372,000 
911,518 1,345,081 1,177,658 
0 104,348 
0 0 
18,626
0 
2,437,000 2,610,000 4,197,000 3,541,000 
1,574,639 3,440,369 4,571,548 3,415,685 
8,010,656 7,490,000 12,264,000 9,545,000 
10,191,370 7,157,647 12,217,020 9,771,652 
950,000 2,597,000 3,450,000 1,890,000 
1,011,724 2,167,981 2,858,126 2,446,626 
180,000 
161,250
00 
0 
10,021
0 
572 
500,000 
375,659 
0 
158,733
00 
00 
00 
512,750 
16,250
00 
00 
00 
1,057,000 2,750,000 
451,595 2,807,469 
O 0 
0 149,447 
0 
-42,325 
595,000 
670,277
0 
-5,815 
0 
16,897 
326,000 
412,597
0 
366 
0 
36,346 
379,000 
362,268
0 
721 
8,012,900 5,420,000 1,780,000 
8,793,102 5,366,819 2,674,729 
119,000 
516,340
00 
00 
00 
957,000 
1,626,323
0 
337,089
0 
26,870 
426,000 
454,511 
-36,000 
341
0 
136,924 
0 
1,408 
$147,400,0001 
146,989,162' 
11,731,256 
11,485,246 
1,158,356 
1,118,160 
174,504,6002 
174,267,1452 
214,956,1333 
214,460,9423 
16,959,3264 
16,406,3945 
961,750 
862,574 
875,000 
875,000 
622,000 
622,000 
433,000 
433,000 
8,707,000 
8,447,668 
600,000 
486,536 
30,568,0006 
30,542,7776 
3,515,600 
3,501,531 
3,644,001 
3,644,001 
24,920,300 
24,807,032 
370,000 
370,000 
14-9

TABLE 14-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
14. Meredosia Lake New Work 
and Willow Creek Approp. 0 0 0 0 345,000 
Drainage & Levee Cost 845 0 0 0 345,000 
District, IL 
15. Mississippi River New Work 
Agricultural Area Approp. 0 0 0 0 2,137,000 
No. 8, IL Cost 6,190 5,634 4,063 169 2,137,000 
16. Nutwood Drain- New Work 
age & Levee Approp. 0 0 0 0 670,000 
District, IL Cost 8,993 120 0 0 670,000 
17. Perry County New Work 
Drainage & Levee Approp. 1,503,000 270,300 16,000 0 7,968,700 7 
District Nos. 1, Cost 1,807,562 266,200 47,146 859 7,968,7007 
2, & 3, MO 
18. Rend Lake, Big New Work 
Muddy, IL Approp. 0 0 - 0 43,700,900 
(Regular Funds) Cost 81,753 35,976 24,820 17,224 43,671,786 
Maint. 
Approp. 2,537,900 1,958,000 3,302,500 2,759,600 26,016,8008 
Cost 2,533,327 2,072,978 3,103,736 2,812,138 25,758,0268 
Code 711 Funds New Work 
Approp. 0 0 0 0 1,060,900 
Cost 0 0 0 0 1,060,900 
(Contrib. Funds) New Work 
Contrib. 0 0 0 0 9,941,2789 
Cost 0 0 0 0 9,941,2789 
Maint. 
Contrib. 0 304,348 300,000 300,000 3,486,303 
Cost 0 293,485 305,279 247,328 3,428,047 
19. Wood River New Work 
Drainage & Levee Approp. 450,000 1,000,000 0 118,000 16,707,82110 
District, IL Cost 386,143 424,513 362,773 416,517 16,667,26210 
23. Clarence Cannon New Work 33,849,700 10,240,300 3,622,000 820,000 312,019,02811 
Dam and Reservoir, Approp. 34,463,424 8,922,842 2,948,571 1,795,702 309,663,90411 
Salt River, MO Cost 
Maint. 
Approp. 1,891,100 2,074,000 3,260,500 3,929,600 16,080,660 
Cost 1,937,491 2,127,691 3,190,444 3,633,059 15,588,093 
1. Excludes $10,461 expended on previous project. 
2. Excludes previous project cost of $1,416,620. 
3. In addition $3,109 was expended for rehabilitation. 
4. Includes $8,072,326 for work authorized by Flood 
Control Act of 1965. 
5. Includes $7,921,939 for work authorized by Flood 
Control Act of 1965. 
6. Includes $200,000 for definite project under 1938 
Flood Control Act. 
7. Excludes $6,800,700 for previous project. 
8. Excludes $550,000 Area Development Administration 
Funds allotted to the State of Illinois for increased 
construction costs of Interstate Highway 57 to meet project 
requirements, and excludes $449,093 Area Redevelopment 
Administration Funds allotted to the Corps. 
9. Includes $6,103,711 credit to State of Illinois for 
work in kind. 
10. Funds are for work authorized by Flood Control Act 
of 1938. 
11. Includes $216,628 for definite project study under 
1938 Flood Control Act. 
14-10

ST. LOUIS, MO, DISTRICT 
TABLE 14-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Jun. 3, 1896 
Jun. 13, 1902 
Mar. 2, 19071 
Mar. 3, 19051 
Jun. 25, 1910 
Jan. 21, 1927 
Jul. 3, 1930 
Mar. 2, 1945 
Sep. 3, 19543 
Jul. 3, 19584 
Jun. 22, 1936 
Oct. 27, 1965 
Oct. 22, 1976 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Jul. 14, 1984 
KASKASKIA RIVER, IL (See Section 2 of Text) 
Construct canal, lock, and dam to provide a 9-foot navigation 
channel from mouth to Fayetteville, IL. 
MISSISSIPPI RIVER BETWEEN OHIO AND MISSOURI 
RIVERS (See Section 4 of Text) 
Project for regulating works in 1881. (To obtain a minimum 
depth of 8 feet.) 
Dredging introduced as part of the project. 
These acts practically abrogated that part of project for middle 
Mississippi which proposed regulating works. 
Regulating works restored to project and appropriations begun 
with a view to completion of improvement between Ohio and 
Missouri Rivers within 12 years at an estimated cost of $21 
million, exclusive of amounts previously expended. 
For 9 feet deep and 300 feet wide from Ohio River to northern 
Rivers and Harbors boundary of city of St. Louis. 
Project between northern boundary of St. Louis and Grafton 
(mouth of Illinois River) modified to provide a channel 9 feet 
deep and generally 200 feet wide with additional width around 
bends. 
Modified to provide construction of a lateral canal with lock at 
Chain of Rocks. 
Modified to provide construction of a small-boat harbor opposite 
Chester, IL. 
Modified to provide construction of a fixed crest rockfill dam 900 
feet below Chain of Rocks Bridge. 
EAST ST. LOUIS AND VICINITY, IL (See Section 5 of Text) 
Raise and enlarge existing levee. 
Construct pumping plant and other modifications to reduce 
interior flooding. 
Construct Blue Waters Ditch as independent section. 
ELDRED AND SPANKEY DRAINAGE AND LEVEE 
DISTRICT, IL (See Section 6 of Text) 
Raise and enlarge existing levee and other modifications. 
HARTWELL DRAINAGE AND LEVEE DISTRICT, IL 
(See Section 7 of Text) 
Raise and enlarge existing levee and other modifications. 
HILLVIEW DRAINAGE AND LEVEE DISTRICT, IL (See 
Section 8 of Text) 
Raise and enlarge existing levee and other modifications. 
KASKASKIA ISLAND DRAINAGE AND LEVEE 
DISTRICT, IL (See Section 9 of Text) 
Raise and enlarge existing levee. 
MAUVAISE TERRE DRAINAGE AND LEVEE 
DISTRICT, IL (See Section 10 of Text) 
Raise and enlarge existing levee and other modifications. 
S. Doc. 44, 87th Cong., 1st 
sess. 
Annual Report, 1881, p. 
1536. 
Committee Doc. 9, 69th 
Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 12, 70th 
Cong., 1st sess. 
H. Doc. 231, 76th Cong., 1st 
sess. 
H. Doc. 230, 83d Cong., 1st 
sess. 
Special report on record in 
OCE. 
H. Doc. 329, 88th Cong., 2d 
sess. 
Public Law 94-587, 94th 
Cong. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 519, 87th Cong., 2d 
sess. 
Energy and Water 
Development Approp. 
Act of 1985, 98th Cong., 2nd 
sess. 
14-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 14-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jun. 28, 1938 
Nov. 7, 1966 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Nov. 7, 1966 
Oct. 23, 1962 
Adopted by 
Senate and 
House 
Committee 
resolutions, 
Oct. 12, 19725 
Oct. 23, 1962 
Jun. 28, 1938 
Oct. 23, 1962 
Oct. 27, 1965 
MERAMEC RIVER BASIN, MO (See Section 11 of Text) 
Construct reservoirs and local protection project. 
Construct Pine Ford, Irondale, and 1-38 dams and 19 Angler-use 
sites. 
MCGEE CREEK DRAINAGE AND LEVEE DISTRICT, IL 
(See Section 12 of Text) 
Reconstruct existing levee and construct pumping plant to 
reduce flooding. 
MEREDOSIA, IL, AND MEREDOSIA, WILLOW CREEK 
AND COON RUN DRAINAGE AND LEVEE DISTRICTS, 
IL (See Section 13 of Text) 
Raise and enlarge existing levee and other modifications. 
MEREDOSIA LAKE AND WILLOW CREEK DRAINAGE 
AND LEVEE DISTRICT, IL (See Section 14 of Text) 
Raise and enlarge existing levee and other modifications. 
MISSISSIPPI RIVER AGRICULTURAL AREA 8, MO (See 
Section 15 of Text) 
Raise and enlarge existing levee and alter pumping plant to 
reduce flooding. 
NUTWOOD DRAINAGE AND LEVEE DISTRICT, IL (See 
Section 16 of Text) 
Raise and enlarge existing levee and other modifications. 
PERRY COUNTY DRAINAGE AND LEVEE DISTRICTS 
NOS. 1, 2, & 3, MO (See Section 17 of Text) 
Construct pumping plants and other modifications to reduce 
interior flooding. 
REND LAKE, BIG MUDDY RIVER, IL (See Section 18 of 
Text) 
Construct dam at Benton, Ill., and subimpoundment dams on 
upper arms of reservoir. 
WOOD RIVER DRAINAGE AND LEVEE DISTRICT, IL 
(See Section 19 of Text) 
Construct reservoirs and local protection projects. 
CLARENCE CANNON DAM AND RESERVOIR, SALT 
RIVER, MO (See Section 23 of Text) 
Modified act of 28 Jun. 1938 by deleting the reservoir therefrom 
and reauthorizing it as a separate multiple-purpose project. 
Changes name of project from Joanna Dam to present 
designation. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st sess. 
H. Doc. 525, 89th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 360, 92nd Cong., 2d 
sess. 
H. Doc. 541, 87th Cong., 2d 
sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st sess. 
H. Doc. 507, 87th Cong., 2d 
sess. 
Public Law 89-298, 89th 
Cong. 
1. Also joint resolution, Jun. 29, 1906. 
2. Contains latest published map. 
3. Inactive. 
4. All work completed. 
5. Authorized under provision of Sec. 201 of the Flood 
Control Act of 1965. 
14-12

ST. LOUIS, MO, DISTRICT 
TABLE 14-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 1986 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Cuivre River, MO 1 - 1883 $ 12,000 $ - 
Grafton Small Boat Harbor, IL Nov. 1977 19622 - 
Mississippi River at Alton, IL 
Small Boat Harbor Nov. 1977 19582 - - 
Moccasin Springs, MO - 1969 76,4363- 
Small Boat Harbor opposite Chester, IL Nov. 1977 19542 - - 
Small Boat Harbor opposite Hamburg, IL Nov. 1977 19502 
Wabash Railroad Bridges, Illinois River, 
Meredosia, and Valley City, IL -1961 2,653,194 1961 
1. Inactive. River declared nonnavigable by act of Mar. 2. Year authorized. 
23, 1900. 3. Excludes $56,605 contributed funds. 
TABLE 14-D LAKES, LEVEES, AND 
RECREATIONAL FACILITIES 
Estimated 
See Required Total Estimated 
Section Estimated Non-Federal Cost (Date to 
in Text Project Name Federal Cost Cost Revision) 
11. Meramec River Basin, MO Lakes: 
Meramec Park1 197,494,000 22,506,000 220,000,000 (1981) 
Union2 101,305,000 11,695,000 113,000,000 (1982) 
Pine Ford' 115,926,800 31,073,200 147,000,000 (1984) 
Irondale 8,744,370 66,700,000 (1982) 
1-;382 27,294,000 2,306,000 29,600,000 (1982) 
Recreation facilities: 
Angler-use sites2 2,140,000 2,140,000 4,280,000 (1982) 
1. Separate reports are included herein. 
2. See 1979 Annual Report for details. 
3. See 1967 Annual Report for details. 
14-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 14-E OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
Cost to Sep. 1986 
For Last 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Angler-use sites, Meramec Basin, MO - 1967 $ - $ - 
Big Swan Drainage and Levee District, 
Illinois River, IL. 
Cache River Diversion, IL - 1953 2,837,114 - 1953 
Cape Girardeau, MO, 
reaches Nos. 1, 3, and 4 Oct. 1978 1959 22,000 -- 
Cape Girardeau, MO, No. 2 - 1965 5,157,805 - 1964 
Carlyle Lake, IL - 1981 42,819,400 39,692,401 Oct. 1976 
Chouteau, Nameoki, and Venice Drainage 
and Levee District, IL -1955 185,700 - 1955 
Clear Creek Drainage and 
Levee District, IL 2 -1964 4,984,500 - 1963 
Columbia Drainage and Levee 
District No. 3, IL -1981 2,818,000 - Aug. 1981 
Degognia and Fountain Bluff Levee and 
Drainage District, IL - 1959 5,889,500 - 1959 
Dively Drainage & Levee District, IL - 1976 1,720,000 - 1976 
East Cape Girardeau and Clear Creek 
Drainage District, IL - 1963 1,920,600 - 1963 
Eldrid, IL Nov. 1979 19623 - - - 
Emergency bank protection for certain 
highway and railroad facilities at Price 
Landing, MO (see Flood Control 
Act of 1944)4 -1950 55,415 - Oct. 1949 
Emergency repairs to levees on Mississippi, 
Illinois, and Kaskaskia Rivers and flood 
fighting and rescue work (Sec. 5, Flood 
Control Act of 1941, as amended) 4 - 1953 - 1,033,279 1951 
Emergency protection for certain highway 
and railroad facilities at Chester, IL, bridge 
(Sec. 12, Flood Control Act of 1944) - 1952 50,000 - Jan. 1952 
Emergency protection for Illinois approach, 
Chain of Rocks Bridge (Sec. 12, Flood 
Control Act of 1944) -1946 25,000 - Aug. 1945 
Fort Chartres and Ivy Landing Drainage 
District No. 5, IL -1970 1,154,800 - 1958 
Fort Chartres and Ivy Landing Drainage 
District No. 5 and Stringtown Drainage 
and Levee District No. 4, IL -1971- 
Grand Tower Drainage and 
Levee District, IL -1959 4,677,900 - 1959 
Harrisonville Levee and 
Drainage District IL - 1981 5,829,000 - Mar. 1981 
Indian Creek Area, Illinois River, IL' - - - 
Kaskaskia Island Drainage and 
Levee District, IL - 1959 297,460 - 1949 
Keach Drainage and Levee District, IL' .. 
Lake Shelbyville, IL - 1981 44,000,000 36,936,298 Sep. 1978 
Levee Districts between Carlyle and 
New Athens, IL, Nos. 2, 5, 6, and 7 Nov. 1979 1979 
Levee Districts between Carlyle and 
New Athens, IL, Nos. 3, 4, 8, 10, and 13 Nov. 1979 1979 
Levee Districts between Cowden 
and Vandalia, IL Oct. 1978 1978 496,000 
Meredosia Lake and Willow Creek Drainage 
and Levee District, IL - 1944 249,738 - 1944 
Miller Pond Drainage District, IL - 1955 164,183 - 1955 
14-14

ST. LOUIS, MO, DISTRICT 
TABLE 14-E 
(Continued) 
OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
Cost to Sep. 1986 
For Last 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Mississippi River at St. Louis, MO - 1980 79,265,166 - Jan. 1980 
Mississippi River Agricultural Area 
No. 10, MO Nov. 1979 1967 - - 
Mississippi River Agricultural Area 
No. 12, MO - 1967 - - 
Mississippi River, Alton to Gale, IL, 
underseepage measures - - 85,422 - Oct. 1962 
North Alexander Drainage and 
Levee District, IL - 1957 939,569 - 1957 
Prairie du Pont Levee and 
Sanitary District, IL 5 - 1970 6,005,127 - 1970 
Prairie du Rocher and vicinity, IL - 1959 3,882,600 - 1959 
Preston Drainage and Levee District, IL - 1959 1,866,910 - 1959 
Richland Creek, IL - 1969 401,000 -- 
Riverland Levee District, MO Aug. 1977 1936- - - 
Scott County Drainage and Levee District, 
Illinois River, IL 1 
- - - - 
Ste. Genevieve County Drainage and 
Levee District No. 1, MO Nov. 1977 1936 - - 
St. Louis County Drainage and 
Levee District No. 1, MO Nov. 1977 1936- - - 
Strington, Ft. Chartres and Ivy Landing, IL - 1957 2,123,700 - Aug. 1956 
Union Lake, MO6 - 1979 4,917,359 -- 
Urban areas at Alton, IL - 1960 192,000 -- 
Village of New Athens, IL - 1981 1,983,000 - Sep. 1981 
Valley City Drainage & Levee District, IL 7 - 1967 91,952 - 1967 
Wiedmer Chemical Drainage and Levee 
District, MO Nov. 1977 1936 - 
1. Projects authorized or modified by Flood Control Act 
of Oct. 23, 1962 (see H. Doc. 472, 87th Cong., 2d sess., for 
details). 
2. Completed except for seepage control measures, which 
are inactive. 
3. Year authorized. 
4. Work complete, now performed under Public Law 99. 
5. Includes $5,235,927 for previous project. 
6. Includes $183,638 for definite project study under 
1938 Flood Control Act. Includes Highway 185 funds. 
7. Authorized by Chief of Engineers (Sec. 205, 1948 
Flood Control Act, as amended). 
14-15

TABLE 14-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
ACTIVE GENERAL INVESTIGATIONS 
(96x3121) 
Federal Cost Totals by 
Item and CWIS Number FY 86 Categories 
SURVEYS (Category 100) 
Flood Control Studies (120) 
St. Louis Metropolitan Area, MO & IL -55040 
Ste. Genevieve, MO -80061 
Creve Coueur Crk, MO -12440 
Sub-total 
Special Studies (140) 
Meramac R. Basin Water Supply, Mo. -14056 
Miscellaneous Activities (170) 
Special Investigations -17250 
Review of FERC Licenses -53857 
Sub-total 
Coordination Studies with Other Agencies (180) 
Dept. of Agric. - Soil Cons. Service -51840 
Plan Assist to State of Ill. -14817 
Plan Assist to State of Mo. -14829 
Sub-total
TOTAL (Category 100) 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) -82030, and 82040 
Hydrology Studies (260) -53820 
TOTAL (Category 200) 
CONTINUATION OF PLANNING & ENGINEERING (Category 400) 
St. Louis Harbor, Mo. & Ii. -10184 
Maline Creek, Mo. -12297 
TOTAL (Category 400) 
ADVANCE ENGINEERING AND DESIGN (Category 600) 
Eldred & Spankey D&LD, IL -00071 
Hartwell D&LD, IL -00073 
Hillview D&LD, IL - 00075 
Meredosia Lake & Willow Creek D&LD, IL -00079 
Meredosia, IL, and Meredosia, 
Willow Creek & Coon Run D&LD, IL -00069 
Meremac River Basin, MO -75412 
Nutwood D&LD, IL -00623 
TOTAL (Category 600) 
GRAND TOTAL GENERAL INVESTIGATIONS 
14-16 
$ 957,599 
1,589 
180,343 
1,139,531 
33,844 
18,984 
1,310 
20,294 
2,943 
7,081 
12,692 
22,716 
$1,216,385 
$ 217,745 
$ 652,369 
204,500 
13,245 
319,980 
332,389 
1,916 
4,830 
7,518 
1,284 
189,264 
29,508 
23,764 
$ 258,084 
$2,344,584

GALVESTON, TX DISTRICT * 
Galveston District comprises drainage basins of all short 
streams arising in coastal plain of Texas and flowing into 
the Gulf of Mexico, including the entire basin of Buffalo 
Bayou, San Jacinto, San Bernard, Lavaca, Navidad, 
Mission, and Aransas Rivers. It embraces Agua Dulce, 
San Fernando, and Olmos Creek Basins draining into Baffin 
Bay, and coastal area south thereof to the Rio Grande 
and east of western Boundary of Starr County, Texas. It 
includes lower basins of major streams flowing into the 
Gulf of Mexico: Sabine River, Texas and Louisiana, 
downstream from U.S. Highway 190 crossing at Bon Wier, 
Texas; Neches River downstream from Town Bluff gaging 
station; Trinity River downstream from Texas State 
Highway 19 crossing at Riverside, Texas; Brazos River 
downstream from confluence with Navasota River; Colorado 
River downstream from northern boundary of 
Fayette County; Guadalupe River downstream from confluence 
with San Marcos River; San Antonio River 
downstream from confluence with Escondido Creek; 
Nueces River downstream from confluence with Frio and 
Atascosa River. 
IMPROVEMENTS 
Navigation Page 
1. Aquatic Plant Control 
(Southwestern Division) ................... 2 
2. Brazos Island Harbor, TX .................. 2 
3. Channel to Port Bolivar, TX................ 2 
4. Corpus Christi Ship Channel, TX ........... 3 
5. Freeport Harbor, TX ...................... 3 
6. Galveston Harbor and Channel, TX ......... 4 
7. Gulf Intracoastal Waterway between Apalachee 
Bay, FL, and the Mexican Border ........... 5 
8. Houston Ship Channel, TX ................ 6 
9. Matagorda Ship Channel, TX .............. 6 
10. Sabine-Neches Waterway, TX ............... 7 
11. Texas City Channel, TX ................... 7 
12. Trinity River and Tributaries, TX ........... 7 
12A. Anahuac Channel, TX .................... 8 
12B. Channel to Liberty, TX .................... 8 
12C. Wallisville Lake, TX ...................... 8 
13. Reconnaissance and Condition Surveys ...... 9 
14. Navigation Work Under Special 
Authorization ............................ 9 
Beach Erosion Control 
15. Corpus Christi Beach, TX ................. 9 
Flood Control 
16. Arroyo Colorado, Rio Hondo, TX ............ 
17. Buffalo Bayou and Tributaries, TX .......... 
18. Clear Creek, TX ........................ 
9
9 
10 
Flood Control (cont.) Pa 
19. Port Arthur and Vicinity, TX 
Hurricane-Flood Protection ............... 
20. Taylors Bayou, TX ....................... 
21. Texas City and Vicinity, TX 
Hurricane-Flood Protection ............... 
22. Vince and Little Vince Bayous, TX ......... 
23. Inspection of Completed Flood 
Control Works .......................... 
24. Flood Control Work Under Special 
Authorization ........................... 
General Investigations 
25. Surveys ................................ 
26. Planning and Engineering ................ 
27. Collection and Study of Basic Data ........ 
Tables 
Table 15-A Cost and Financial Statement ...... 
Table 15-B Authorizing Legislation ............ 
Table 15-C Other Authorized Navigation 
Projects ........................ 
Table 15-D Other Authorized Flood Control 
Projects ........................ 
Table 15-E Total Cost of Existing Projects ...... 
Table 15-F Channel Dimensions .............. 
Table 15-G Channel Dimensions, GIWW 
Tributary Channels ............... 
Table 15-H Dredging Operations .............. 
15-1 
ige 
12 
12 
12 
13 
16 
27 
27 
28 
29 
32 
34

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. AQUATIC PLANT CONTROL 
(SOUTHWESTERN DIVISION) 
1965 ACT 
Location. Navigable waters, tributary streams, connecting 
channels, and other allied waters in Texas and the 
Sabine River Watershed of Louisiana. 
Previous project. For details see page 699 of Annual 
Report for 1963. 
Existing project. A comprehensive project to provide 
for control and progressive eradication of water-hyacinth, 
alligatorweed, Eurasian watermilfoil, and other obnoxious 
aquatic plant growths, from navigable waters, tributary 
streams, connecting channels, and other allied waters in 
Texas in the combined interest of navigation, flood control, 
drainage, agriculture, fish and wildwife conservation, 
public health, and related purposes, including continued 
research for development of the most effective and 
economic control measures. Eradication work of hydrilla, 
water hyacinth and alligator weed continues in the 
Nueces River Basin, North Coastal Area, Guadalupe 
River Basin, Sabine River Basin, Trinity River Basin, 
Cypress Creek Basin, Neches River Basin, South Coastal 
Area, San Jacinto River Basin, Rio Grande Basin, Colorado 
River Basin and Brazos River Basin. Estimated cost 
for new work is $2,019,000 Federal (Corps) and $693,000 
non-Federal. 
Local cooperation. Sec. 302, 1965 River and Harbor 
Act, applies. 
Operations during fiscal year. Eradication work by 
the State of Texas continued. The control of submerged 
species, hydrilla and Eurasian watermilfoil was initiated. 
Monitoring of the biological control nursery areas was continued 
during the year. 
2. BRAZOS ISLAND HARBOR, TX 
Location. At extreme south end of coast of Texas, about 
7 miles north of mouth of Rio Grande and about 5 miles 
east of Brownsville, Texas. (See National Ocean Survey 
Chart 11301.) 
Previous project. For details see page 1017 of Annual 
Report for 1932. 
Existing project. Provides for channel dimensions in 
various sections of the waterway as shown in Table 15F. 
Project also provides for dual jetties at the gulf entrance, 
a north jetty 6,330 feet long, a south jetty 5,092 feet long, 
and 1,000-foot extension to existing north jetty and for 
maintenance of 3rd fishing harbor constructed by local 
interests. Under ordinary conditions, mean tidal range is 
about 1.5 feet, and extreme range is about 2 feet. All 
depths refer to mean low tide. To some extent, height of 
tides is dependent on the wind, and during strong "northers" 
in winter season, water surface in southern end 
of Laguna Madre may be raised 4 feet or more above mean 
low tide in the gulf. 
Widening Brownsville Channel from Goose Island to 
Brownsville turning basin and deepening southeast corner 
of Brownsville turning basin to 36 feet was completed 
in April 1980. The 1,000-foot extension to existing north 
jetty was placed in the inactive category in 1980. (See 
Table 15-E for total cost of existing project to September 
30, 1986.) 
Local cooperation. Complied with. 
Terminal facilities. Numerous terminal facilities for 
bulk and liquid cargo are available. (See Port Series No. 
26, revised 1980.) Facilities are adequate for existing 
commerce. 
Operations during fiscal year. Routine maintenance. 
A contract for construction of retaining levees for an 
aquaculture project in the amount of $203,149 was completed 
in FY 86. This project was initiated under a joint 
program with Waterways Experiment Station to assess 
the feasibility of utilizing disposal areas for productive 
purposes in idle periods or between dredging cycles. (See 
Table 15-H for dredging operations.) 
3. CHANNEL TO PORT BOLIVAR, TX 
Location. Port Bolivar is at end of Bolivar Peninsula 
and 4 miles north of city of Galveston. Channel connects 
the port with channel in Galveston Harbor. (See National 
Ocean Survey Chart 11324.) 
Previous Project. For details see page 1856 of Appendix 
to Annual Report for 1915. 
Existing Project. Existing project dimensions for channel 
are shown in Table 15-F. (Also see Table 15-B for 
authorizing legislation.) 
Under ordinary conditions mean tidal range is about 
1.3 feet and extreme range about 2 feet. Height of tides 
is dependent largely on the wind, and during strong "northers" 
in the winter season water surface may be depressed 
as much as 2 feet below mean low tide. Enlargement 
of turning basin from 1,000 to 1,600 feet is inactive. A 
channel 14 feet deep, 200 feet wide, and approximately 
950 feet long is maintained across the east end of the turning 
basin to accommodate the Galveston-Port Bolivar 
ferry. Project is complete except for inactive portion. Project 
dimensions have not been maintained in the completed 
part since lesser dimensions are adequate for existing 
commerce. (See Table 15-E for total cost of existing 
project to September 30, 1986.) 
Local Cooperation. None required. 
Terminal facilities. Terminals are privately owned and 
consist of 2 slips and 2 piers. The piers, 400 feet wide by 
1,200 feet long and 210 feet wide by 1,200 feet long, are 
badly deteriorated and not in use. The slips are used as 
anchorage by shallow-draft vessels. A highway ferry landing 
owned by the State of Texas is located at south end 
of turning basin. Facilities are considered adequate for 
existing commerece. 
Operations during fiscal year. Routine maintenance. 
(See Table 15-H for dredging operations.) 
15-2

GALVESTON, TEXAS DISTRICT 
4. CORPUS CHRISTI SHIP CHANNEL, TX 
Location. This project, formerly known as the Port 
Aransas-Corpus Christi Waterway, Texas, was changed to 
Corpus Christi Ship Channel, Texas, by 1968 River and 
Harbor Act. This is a consolidation of old improvements 
of Port Aransas, Texas, and channel from Aransas Pass 
to Corpus Christi, Texas. Aransas Pass is on southern portion 
of Texas Coast, 180 miles southwest of Galveston and 
132 miles north of mouth of Rio Grande. Aransas Pass connects 
Corpus Christi Bay with the gulf. Waterway extends 
from deep water in the gulf through Aransas Pass jettied 
entrance, thence westerly 20.75 miles to and including 
a turning basin at Corpus Christi, thence westerly 1.75 
miles through Industrial Canal to and including turning 
basin at Avery Point, thence westerly 4.25 miles to and 
including a turning basin near Tule Lake, thence northwesterly 
1.8 miles to and including a turning basin at 
Viola, Texas. (See National Ocean Survey Charts 11308, 
11309, 11311, and 11314.) 
Previous project. For details see page 1861 of Annual 
Report for 1915. 
Existing project. (See Table 15-F for existing project 
dimensions provided for in various channels and basins 
comprising this waterway.) 
Project also provides for two rubblestone jetties at Aransas 
Pass entrance, extending into the gulf from St. Joseph 
and Mustang Islands, project lengths of which are 11,190 
and 8,610 feet, respectively. Project further provides for 
a stone dike on St. Joseph Island about 20,991 feet long, 
connecting with north jetty and extending up this island 
to prevent a channel being cut around jetty. Project also 
provides for a breakwater at the entrance to the harbor 
area at Port Aransas, and for the realignment of the existing 
12-foot by 100-foot project channel to Port Aransas. 
The breakwater consists of two overlapping sections. The 
one on the east side of the realigned entrance channel has 
a length of 830 feet and the second, located on the west 
side of the entrance channel, has a length of 1,290 feet. 
The channel to Port Aransas was relocated in the 300-foot 
clear distance between the overlapping sections. The portion 
of the channel remaining inside the breakwaters was 
widened to 150 feet. Under ordinary conditions, mean 
tidal range at Aransas Pass is about 1.1 feet and extreme 
range about 2 feet, and at Corpus Christi mean range 
about 1 foot and extreme about 1.5 feet. Heights of tides 
are dependent largely on strength and directions of winds, 
and during strong "northers" in the winter season water 
surface may be depressed as much as 3 feet below mean 
low tide. Estimated cost for new work is: Federal (Corps) 
$70,724,515, including $456,515 for Port Aransas 
Breakwaters and exclusive of amount expended on 
previous projects; and non-Federal $17,981,068 (includes 
$768 for Port Aransas Breakwaters) including $6,648,840 
contributed funds and value of useful work performed, 
$3,320,228 lands, $6,027,000 relocations and $1,985,000 
other cost. (October 1, 1986 base price.) 
The Port Aransas-Corpus Christi 40-foot project was 
completed in 1966. The Jewel Fulton Canal was completed 
in 1963. The Port Aransas Breakwaters were completed 
in July 1973. Work remaining consists of deepening deepdraft 
channels to 45 feet from Beacon 82 through Viola 
Turning Basin; widening of channels and basins; and constructing 
a mooring area at Port Ingleside with dolphins. 
Entrance and jetty channels have been dredged to project 
depth and width, and dredging of channel from Harbor 
Island to Beacon 82 at 45-foot depth has been completed. 
Initial mooring dolphins were completed in May 1979. 
Disposal area levees, Area 1 and Rincon were completed 
in August 1984. Disposal area levees, South Shore, were 
completed in September 1984. (See Table 15-E for total 
cost of existing project to September 30, 1986.) 
Local cooperation. Fully complied with except for provisions 
of Sec. 101 of 1968 River and Harbor Act and Sec. 
124 of Water Resources Development Act of 1976. 
Terminal facilities. Terminal facilities on Harbor 
Island at head of Aransas Pass, Ingleside, Corpus Christi, 
La Quinta, Avery Point, and Viola, are considered adequate 
for existing commerce. (See Port Series, No. 25, 
revised 1979, Corps of Engineers.) 
Operations during fiscal year. New Work: Fiscal year 
cost for contract for berm stabilization of Rincon Levees 
was $75,000. (See Table 15-H for dredging operations.) 
Maintenance: Routine maintenance. (See Table 15-H for 
dredging operations.) 
5. FREEPORT HARBOR, TX 
Location. Formed by improvement of Brazos River, 
Texas, from mouth to about 6 miles upstream to Freeport, 
Texas. (See National Ocean Survey Charts 11321 and 
11322.) 
Previous projects. For details see page 1860 of Annual 
Report for 1915, and page 872 of Annual Report for 1938. 
Existing project. Existing project dimensions for 
various channels and basins are shown in Table 15-F on 
channel dimensions at end of chapter. 
Existing project also provides for: Dual jetties and a 
diversion canal for the Brazos River, including a dam, a 
lock in the dam and necessary auxiliary equipment. Also 
provides for rehabilitation of southwest jetty and the 
relocation of the northeast jetty (about 640 feet to the northeast); 
realignment of the channel between the Jetty 
Channel and Brazosport Turning Basin; realignment of 
the channel between Brazosport Turning Basin and Upper 
Turning Basin; relocation of Upper Turning Basin; 
and public use facilities adjacent to the Freeport Jetties. 
The 30-foot channel from Upper Turning Basin to Stauffer 
Chemical Plant, including the turning basin, was 
deauthorized by Sec. 12 of PL 93-251. Construction of lock 
in diversion dam at local expense is considered inactive. 
The 38-36 foot project was completed in 1962. Work remaining 
consists of realigning, deepening and widening 
the Outer Bar and Jetty Channels; relocating the northeast 
jetty; rehabilitating the southwest jetty; realigning 
and deepening the harbor channel between the jetty 
channel and the Upper Turning Basin; relocating and 
15-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
enlarging the Upper Turning Basin; constructing a turning 
point near the northwesterly end of the jetty channel; 
enlarging Brazosport Turning Basin; deepening 
Brazos Harbor Channel; and enlarging and deepening 
Brazos Harbor Turning Basin, as authorized by the R&H 
Act of 1970. (See Table 15-E for total cost of existing project 
to September 30, 1986.) 
Under ordinary conditions mean tidal range is about 
1.5 feet and extreme range is about 2.5 feet. Except 
under extreme conditions, rises on river and in diversion 
channel do not cause greater variations in water surface 
than those caused by tidal action. Estimated cost of new 
work is: $58,827,000 Federal (Corps); and $29,536,000 
non-Federal, including $19,758,303 contributed funds, 
$360,249 contributed work, $6,217,448 lands, $2,668,000 
levees and spillways, and $532,000 relocations. (October 
1, 1986 base price.). 
Local cooperation. Fully complied with except for 
Section 101 of River and Harbor Act of 1970. For work 
authorized by this Act, the Local Cooperation Agreement, 
executed 26 June 1986, requires that local interest 
provide lands, easements, rights-of-way, including land 
for recreation, and dredged material disposal areas, 
presently estimated at $8,568,000, modify or relocate 
utilities, roads, and other facilities, except railroad 
bridges, where necessary for construction of the project, 
presently estimated at $532,000, contribute in cash onehalf 
of the separable and joint costs allocated to recreation, 
presently estimated at $360,000; and, during construction, 
pay 25 percent of the construction costs 
allocated to deep-draft navigation, presently estimated 
at $18,640,000. 
Terminal facilities. Small privately owned wharves, 
two oil docks, one acid dock, two shell unloading docks 
and one caustic dock. Brazos River Navigation District 
has one large dock with four transit sheds over rail 
facilities permitting all-weather work. Facilities considered 
adequate for existing commerce. (See Port Series 
No. 26, revised 1980, for additional facilities.) 
Operations during fiscal year. New Work: Engineering 
and design work continued on the 45-foot project. 
Maintenance: Routine maintenance. (See Table 15-H 
for dredging operations.) 
6. GALVESTON HARBOR AND 
CHANNEL, TX 
Location. A consolidation of authorized improvements 
at Galveston, Texas, which includes projects formerly 
identified as Galveston Harbor, Texas; Galveston Channel, 
Texas; and Galveston seawall extension. Entrance 
to Galveston Harbor is on Gulf of Mexico on the northern 
portion of the Texas Coast. Galveston Channel extends 
from a point in Galveston Harbor between Bolivar Peninsula 
and Fort Point to and along wharf front Galveston, 
Texas, and is about 5 miles long and 1,200 
feet wide. (See National Ocean Survey Chart 11324/5.) 
Previous projects. For details see page 1854 of Annual 
Report for 1915. 
Existing project. Provides for channel dimensions in 
sections of the waterway shown in Table 15-F. 
Also provided are: two rubble-mound jetties, the south 
one extending from Galveston Island and the north one 
extending from Bolivar Peninsula, for distances of 35,900 
feet and 25,907 feet, respectively, into the Gulf of Mexico; 
a concrete seawall from the angle at Sixth Street 
and Broadway, in the city of Galveston, to the south jetty, 
and a 16,300-foot extension of the concrete seawall 
in a southwesterly direction from 61st Street; for 11 
groins along the gulf shore between 12th Street and 61st 
Street; and for maintenance of seawall from the angle 
at 6th Street and Broadway to the south jetty. Under ordinary 
conditions, mean tidal range in Galveston Harbor 
is 1.6 feet on outer bar and 1.4 feet on inner bar 
with extreme ranges of 2.3 and 2.1 feet, respectively. 
Mean range in Galveston channel is about 1.3 feet and 
extreme range about 2 feet under ordinary conditions. 
Height of tides in both Galveston harbor and channel 
is dependent largely on the wind, and during strong 
"northers" water surface may be depressed 2 feet below 
mean low tide. 
Existing project is complete. Dredging of Galveston 
channel to 36 foot depth was completed in November 
1966. Dredging of the realigned entrance and Outer Bar 
Channel was completed in October 1967. Rehabilitation 
of the Beach Front Groins was completed June 1970. 
Dredging of Galveston channel to 40 feet was completed 
in March 1976. (See Table 15-E for total cost of existing 
project to September 30, 1986.) 
Local cooperation. Complied with. 
Terminal facilities. None on Galveston Harbor, which 
is entrance channel leading to terminal facilities on 
Galveston, Texas City, and Houston Ship Channels. 
Galveston Channel terminal facilities are mostly on 
south side of channel. Principal wharves, owned by the 
city of Galveston, extend from 10th to 41st Street (see 
Port Series No. 23, revised 1979). A containership terminal 
equipped with a crane capable of stacking containers 
three units high on the deck of any normal containership 
has been completed and placed into operation 
by the city of Galveston at Piers 10 and 11, on the south 
side of Galveston Channel. The city of Galveston has also 
placed into operation a barge terminal equipped with 
two 35-ton and one 5-ton cranes for loading and 
unloading barges on Lash and Seabee ships at Pier 35 
and a docking and holding area for Lash and Seabee 
barges on Pelican Island, directly across the channel 
from Piers 35 and 36. Present facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Routine maintenance. 
Repairs to Galveston groins cost $72,626. (See Table 15-H 
for dredging operations.) 
15-4

GALVESTON, TEXAS DISTRICT 
7. GULF INTRACOASTAL WATERWAY 
BETWEEN APALACHEE BAY, FL, 
AND MEXICAN BORDER 
(GALVESTON DIST.) 
Location. Extends from a point on Sabine River about 
3 miles below Orange, Texas, to Brownsville, Texas, about 
421 miles; a navigation channel, about 7 miles long, in 
Colorado River, extending from Matagorda, Texas, to Gulf 
of Mexico; a tributary channel in San Bernard River, extending 
from Intracoastal Waterway crossing to State 
highway bridge some 30 miles above crossing; a tributary 
channel in Colorado River extending from Intracoastal 
Waterway upstream 15.5 miles; a tributary channel extending 
about 14 miles from Intracoastal Waterway to 
Palacios, Texas; a tributary channel extending about 2 
miles from Intracoastal Waterway to Rockport, Texas; a 
tributary channel extending about 6 miles from Intracoastal 
Waterway near Port Aransas, Texas, to town 
of Aransas Pass, Texas; a tributary channel about onefourth 
mile long extending from Intracoastal Waterway 
near Port O'Connor, Texas, into Barroom Bay; a tributary 
channel extending about 38.8 miles from Intracoastal 
Waterway via Seadrift to a point in Guadalupe River 5.5 
miles below Victoria, Texas; a harbor of refuge for small 
craft at Seadrift; a channel extending from gulf to Port 
Mansfield, Texas, about 11 miles; and a tributary channel 
in Arroyo, Colorado extending from Intracoastal 
Waterway to a point near Harlingen, Texas, about 31 
miles; side channels in vicinity of Port Isabel, Texas, and 
a small boat basin at Port Isabel, Texas, and a tributary 
channel extending from Intracoastal Waterway main 
channel at a point in West Galveston Bay into Offatts 
Bayou about 2.2 miles with a west turnout (wye connection) 
12 feet deep and 125 feet wide between Offatts Bayou 
Channel and the Gulf Intracoastal Waterway. (See National 
Ocean Survey Charts 11302, 11303, 11305, 11306, 
11308, 11309, 11314, 11315, 11317, 11319, 11322, 11326, 
and 11331.) 
Previous project. For details see page 1859 of Annual 
Report for 1915. (West Galveston Bay and Brazos River 
Canal, Texas.) 
Existing project. Existing project dimensions provided 
for in main channel of waterway: A channel 12 feet 
deep (below mean low tide) and 125 feet wide from the 
Sabine River to Brownsville, Texas. Relocation of channel 
12 feet deep by 125 feet wide in Matagorda Bay, miles 
454.3 to 471.3, relocation of channel 12 feet deep by 125 
feet wide in Corpus Christi Bay, miles 539.4 to 549.7 
(mileage is west of Harvey Lock, Louisiana); and alternate 
channel, 12 feet deep (below mean low tide) and 125 
feet wide via Galveston Channel and Galveston Bay to 
the Galveston causeway; maintenance of existing channel 
12 feet deep by 125 feet wide through Lydia Ann Channel, 
between Aransas Bay and Aransas Pass; provisions 
of such passing places, widening of bends, locks and guard 
locks, railway bridges over artificial cuts as are necessary, 
and the tributary channels shown in tabulation. The 
authorized channel 16 feet deep and 125 feet wide from 
Sabine River to Houston Ship Channel and the 9 feet deep 
and 100 feet wide channel from mile 8.2 to mile 13.2 in 
Chocolate Bayou are inactive. (See Table 15-G on existing 
project dimensions provided for in tributary channels.) 
Removal of the railroad bridge across the canal at Mud 
Bayou was completed and operation and care of the facility 
was discontinued on April 14, 1969. Deepening the existing 
6 foot by 60 foot side channels at Port Isabel to 12 
feet was completed February 22, 1972, Offatts Bayou 
channel was completed January 1974. Relocation of main 
channel across Corpus Christi Bay was completed in 
September 1976. The 14 foot by 175 foot Channel to Aransas 
Pass was completed in April 1979. Dredging Chocolate 
Bayou Channel was completed in January 1981. Construction 
of a saltwater barrier in Chocolate Bayou was completed 
in February 1981. The 12 foot by 125 foot channel 
relocation route in Matagorda Bay has been deauthorized. 
The Harbor of Refuge at Seadrift, Texas, has been placed 
in the inactive category. Active authorized work remaining 
consists of the following: construction of jetties 
at mouth of Colorado River; dredging a navigation channel 
from gulf to the GIWW; constructing a turning basin 
at Matagorda, Texas; construction of a diversion dam and 
channel; construction of an oyster cultch; and recreation 
facilities. (See Table 15-E for total cost of existing project 
to September 30, 1986.) 
Mean tidal variation is 0.5 foot at Orange, 1 foot at Port 
Arthur, 1.3 feet in Galveston Bay, 1.5 feet at Freeport, 1 
foot in Matagorda Bay, 1 foot in San Antonio Bay, 1 foot 
at Corpus Christi, 1.5 feet at Port Isabel, and 1.5 feet at 
Brownsville. Extreme ranges of tide under ordinary conditions 
are 1 foot at Orange, 1.5 feet at Port Arthur, 2 feet 
in Galveston Bay, 2 feet at Freeport, 1.5 feet in Matagorda 
and San Antonio Bays, 1.5 feet at Corpus Christi, 2 
Feet at Port Isabel, and 1.5 feet at Brownsville. Height 
of tides is dependent largely on wind. Strong north winds 
have depressed water surface as much as 2 feet below 
mean low tide. Estimated cost for new work is: 
$76,664,000, Federal (Corps), including $8,414 for Port 
Isabel Side Channel, $46,559 for Port Isabel Small Boat 
Basin, $356,466 for Offatts Bayou, and $658,573 for Channel 
to Aransas Pass and excluding expenditures on 
previous projects; non-Federal $16,105,174 ($395,000 
voluntarily expended on Gulf Intracoastal Waterway, 
$46,559 contributed funds for Port Isabel, $49,665 contributed 
funds for Offatts Bayou, $347,950 contributed 
funds for channel to Aransas Pass, $3,400,000 contributed 
funds for Mouth of Colorado River, $4,683,000 lands for 
Gulf Intracoastal Waterway, $11,000 lands for Port Isabel, 
$4,242,000 relocations for Gulf Intracoastal Waterway and 
$2,930,000 other costs Gulf Intracoastal Waterway). (October 
1, 1986 base price.) 
Local cooperation. Fully complied with except for inactive 
portions, and provisions of Section 101, 1968 River 
and Harbor Act. Non-Federal contributions are $395,000 
for Gulf Intracoastal Waterway, $46,559 for Port Isabel, 
Texas, $49,665 for Offatts Bayou, Texas, $347,950 for 
15-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Channel to Aransas Pass, Texas, and $3,400,000 for Mouth 
of Colorado River, Texas. 
Terminal facilities. There are terminal facilities at 
Aransas Pass, Port Arthur, Galveston, Port Isabel, and 
Brownsville. See Port Series No. 22 (revised 1981), Port 
Series No. 23 (revised 1979), Port Series No. 25 (revised 
1979) and Port Series No. 26 (revised 1980), Corps of 
Engineers. Local interests constructed terminal facilities 
at Port Mansfield and Port Harlingen. There are 
numerous privately owned piers and wharves along the 
waterway. A 330-foot navigation district owned general 
cargo dock, a 770-foot private dock and a 760-foot private 
timber trestle have recently been completed at the upper 
end of the Channel to Victoria. Facilities are adequate 
for existing commerce. 
Operations during fiscal year. New work: Contract 
for construction of jetties at the Mouth of the Colorado 
River completed at a fiscal year cost of $1,013,064. 
Maintenance: The Brazos River Floodgates were 
operated and maintained at a cost of $672,914, including 
engineering and design, supervision and administration, 
and real estate activities. The Colorado River Locks were 
operated and maintained at a cost of $635,676, including 
engineering and design and supervision and administration. 
Repairs to Port O'Connor Dike cost $709,977. Cost 
for construction of levees and spillways on contract for 
dredging Cow Bayou to Bastrop Bay was $350,000. (See 
Table 15-H for dredging operations.) 
8. HOUSTON SHIP CHANNEL, TX 
Location. Connects Galveston Harbor, at a point opposite 
Port Bolivar, with city of Houston, Texas, extending 
50 miles northwesterly across Galveston Bay through San 
Jacinto River and Buffalo Bayou to a turning basin at 
head of Long Reach with light-draft channel 7 miles long 
from turning basin to Main Street, Houston. (See National 
Ocean Survey Charts 11324/5, 11327, 11328, and 11329.) 
Previous project. For details see page 1856 of Annual 
Report for 1915. 
Existing project. Provides for channel dimensions in 
sections of the waterway shown in Table 15-F. 
Also provides for certain cut-offs, for easing sharp bends, 
an earthen dam across the upper end of Turkey Bend, and 
for off-channel silting basins as deemed necessary by the 
Chief of Engineers. Construction of 26,000 linear feet of 
pile dike to protect the channel in upper Galveston Bay 
was deauthorized by Sec. 12 of PL 93-251. The 40-foot project 
was completed in March 1966. Dredging a channel 
in Greens Bayou to Mile 1.57 was completed in 1970. 
Dredging Greens Bayou, Mile 1.57 to Mile 2.73, has been 
deauthorized. (See Table 15-E for total cost of existing project 
to September 30, 1986.) 
Mean tidal range under ordinary conditions is 0.6 foot 
to 1.3 feet in lower part of Galveston Bay; 0.6 foot to 1.3 
feet in upper bay; and 0.5 to 1 foot in San Jacinto River 
and Buffalo Bayou. Extreme ranges under ordinary conditions 
are about 2 feet, 1.2 feet and 1 foot, respectively. 
Freshets caused rises of over 12 feet in Buffalo Bayou; 
however, this condition has not occurred since completion 
of Addicks and Barker Dams for flood control on upper 
watershed of Buffalo Bayou. Height of tides is dependent 
largely on the wind, and during strong "northers" in 
winter season the water surface may be depressed 2 feet 
below mean low tide. 
Local cooperation. Fully complied with. 
Terminal facilities. City of Houston and Port of 
Houston Authority operate modern terminals which supplement 
privately owned wharves, piers, and docks, as 
described in Port Series No. 24 (revised 1980), Corps of 
Engineers. Facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. Routine maintenance. 
(See Table 15-H for dredging operations.) 
9. MATAGORDA SHIP CHANNEL, TX 
Location. This is a consolidation of shallow draft channel 
improvements of "Channel from Pass Cavallo to Port 
Lavaca, Texas," and deep draft channel improvements 
authorized under "Matagorda Ship Channel, Texas." Bar 
at Pass Cavallo is 125 miles southwest of Galveston entrance 
and 54 miles north of Aransas Pass. It connects 
Matagorda Bay with the gulf. Project extends across 
Matagorda Bay and Lavaca Bay to towns of Port Lavaca 
and Point Comfort. These two towns are on opposite sides 
of Lavaca Bay and both are about 26 miles northwest from 
Pass Cavallo. (See National Ocean Survey Chart 11316.) 
Existing project. Existing project dimensions provided 
for in various channels and basins are listed in Table 
15-F on channel dimensions. 
Project also provides for dual jetties at entrance, south 
jetty extending 6,000 feet to 24-foot depth in the gulf and 
north jetty extending 5,900 feet to 24-foot depth. Under 
ordinary conditions mean tidal range is about 1 foot and 
extreme range about 2 feet. Height of tide is dependent 
largely on the wind, and during strong "northers" in 
winter season the water surface may be depressed 2 feet 
below mean low tide. Estimated cost for new work is: 
$18,058,777 Federal (Corps), and $12,859,000 non-Federal, 
including $12,259,619 contributed funds, $182,000 for 
lands, $220,000 for relocations, and $196,581 other costs. 
The project was completed in March 1967 
Local cooperation. Fully complied with. 
Terminal facilities. Privately owned facilities at Port 
Lavaca, municipally owned facilities at mouth of Lynn 
bayou, privately owned and publicly owned facilities at 
Point Comfort, Texas. These facilities are considered adequate 
for present commerce. Facilities at Point Comfort 
consist of a channel, turning basin with wharfs, oil dock 
and loading equipment, all owned by Aluminum Company 
of America; and a wharf built by local interest at Point 
Comfort turning basin. 
Operations during fiscal year. Routine maintenance. 
(See Table 15-H for dredging operations.) 
15-6

GALVESTON, TEXAS DISTRICT 
10. SABINE-NECHES WATERWAY, TX 
Location. This is a consolidation of old improvements 
of "Harbor at Sabine Pass and Port Arthur Canal" and 
"Sabine-Neches Canal, including Sabine River to Orange 
and Neches River to Beaumont, Texas" Sabine Pass is on 
Gulf of Mexico about 58 miles east of Galveston and 280 
miles west of Southwest Pass, Mississippi River. It connects 
Sabine Lake with gulf. Port Arthur canal extends 
7 miles from near upper end of Sabine Pass to Port Arthur 
docks at mouth of Taylors Bayou. Near its upper end, 
Sabine-Neches canal joins and extends to mouths of 
Neches and Sabine Rivers. Waterway next extends up 
Neches River to Beaumont and up Sabine River to 
Orange. (See National Ocean Survey Charts 11341,11342, 
and 11343.) 
Previous projects. For details see page 1863 of Annual 
Report for 1915, page 985 of Annual Report for 1916, and 
page 873 of Annual Report for 1926. 
Existing project. Existing project dimensions provided 
for in various channels and basins are set forth in Table 
15-F on channel dimensions. Project also provides for two 
stone jetties at Sabine Pass entrance from the gulf, 
western jetty to be 21,905 feet long and eastern jetty 
25,310 feet long. Project further provides for removal of 
guard lock in Sabine-Neches Canal, construction of 
suitable permanent protective works along Sabine Lake 
frontage owned by city of Port Arthur to prevent dredged 
material from entering Sabine Lake and to prevent erosion 
of material deposited, reconstruction of Port Arthur 
Bridge, and relocation of Port Arthur field office. Mean 
tidal variation at entrance is about 1.5 feet, at Port Arthur 
about 1 foot, and at Orange and Beaumont about 0.5 
foot. Prolonged north winds during winter season have 
depressed water surface as much as 3.4 feet below mean 
low tide while tropical disturbances have caused heights 
as much as 8 feet above mean low tide. 
Existing project is complete except for inactive portions. 
Removal of obstructive bridge at Port Arthur was completed 
May 1969. The high level fixed bridge across 
Sabine-Neches Canal was completed October 1970. 
Deepening project to 40 feet was completed April 1972. 
(See Table 15-E for total cost of existing project to 
September 30, 1986.) 
Local cooperation. Complied with except for inactive 
portions. 
Terminal facilities. See volume 2, Port Series No. 22 
(revised 1981), Corps of Engineers. Facilities are considered 
adequate for present commerce. 
Operations during fiscal year. Routine maintenance. 
(See Table 15-H for dredging operations.) 
11. TEXAS CITY CHANNEL, TX. 
Location. Texas City is on the mainland of Texas on west 
side of Galveston Bay, about 10 miles northwest of city of 
Galveston. (See National Ocean Survey Charts 11324/5.) 
Previous projects. For details see page 1856 of Annual 
Report for 1915. 
Existing project. Provides for channel 40 feet deep, 400 
feet wide and about 6.75 miles long, from Bolivar Roads 
to a turning basin at Texas City, 40 feet deep, 1,000 feet 
to 1,200 feet wide and 4,253 feet long; and an Industrial 
Canal, 40 feet deep and 300-400 feet wide extending a 
distance of 1.7 miles southwestward from the south end 
of Texas City Turning Basin, and a turning basin, 40 feet 
deep, 1,000 feet wide and 1,150 feet long. 
Project also provides for easing the approach to the turning 
basin; a pile dike 28,200 feet long, parallel to and 
north of the channel; and a rubble-mound dike, 27,600 feet 
long, along the southerly side of the pile dike. 
The 40-foot channel was completed in June 1967. Widening 
the Texas City Turning Basin; realigning the Texas 
City Turning Basin to a location 85 feet easterly from its 
present position; and enlargement through widening and 
deepening of the Industrial Canal and basins was initiated 
in July 1980 and completed in June 1982. The only 
work remaining is deferred construction consisting of 
widening the Industrial Canal from 250 feet to 300 feet 
at 40 foot depth. (See Table 15-E for total cost of existing 
project to September 30, 1986.) 
Under ordinary conditions mean tidal range is about 
1.3 feet and extreme range is about 2 feet. Height of tide 
is dependent largely on the wind and during strong "northers" 
water surface may be depressed 2 feet below mean 
low tide. Estimated cost for new work is $14,300,000 
Federal (Corps), excluding expenditures on previous projects, 
and $1,793,700 non-Federal, including $127,741 contributed 
funds, $248,000 work contribution, $427,959 
lands, $984,000 levees and spillways and $6,000 for 
removal of barge mooring facilities from Snake Island. 
Local cooperation. Fully complied with. 
Terminal facilities. Privately owned terminal facilities 
are on the mainland at inner end of this channel and are 
considered adequate for existing commerce. A deep-draft 
channel and turning basin extend about 1.9 miles 
southwestward from south end of Texas City Turning 
Basin have been constructed by local interests. See Port 
Series No. 23 (revised 1979), Corps of Engineers. 
Operations during fiscal year. Routine maintenance: 
Levee rehabilitation cost $1,888,791. 
12. TRINITY RIVER AND 
TRIBUTARIES, TX 
Location. The main stem of the Trinity River is formed 
at Dallas by the confluence of the West Fork and the 
Elm Fork at river mile 505.5. The mouth of the Trinity 
is about one-half mile west of Anahuac, Texas. (See 
Geological Survey base map, Texas, scale 1:500,000.) 
Previous project. For details of abandoned locks and 
dam construction see page 986 of Annual Report for 1932. 
Existing project. See individual detailed reports on 
Anahuac Channel, Channel to Liberty and Wallisville 
Lake. Project includes the existing Federal project 
designated as "Mouth of Trinity River, Texas," which was 
completed in 1907 at a cost of $80,000 (no cost to local 
interest). Project is not being maintained. (See Table 15-E 
15-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
for total cost of existing project to September 30, 1986.) 
Local cooperation. See individual detailed reports on 
Channel to Liberty and Wallisville Lake. There is no local 
cooperation required for Anahuac Channel. 
Terminal facilities. Privately owned wharves and piers 
at Anahuac, Moss Bluff, Wallisville, and Liberty, Texas, 
are adequate for existing commerce. 
12A. ANAHUAC CHANNEL, TX 
Location. Extends from 6-foot depth in Galveston Bay 
to Anahuac, Texas, opposite mouth of Trinity River 38 
miles north of Galveston, Texas. (See National Ocean 
Survey Chart 11323.) 
Existing project. No project dimensions authorized by 
1905 River and Harbor Act. A 6- by 80-foot channel, 16,000 
feet long was dredged in 1905. At present a 6- by 100-foot 
channel is maintained. Under ordinary conditions tidal 
range is 0.6 to 1.2 feet. Height of tide is dependent largely 
on wind. Strong north winds depress water surface 1.5 
feet below mean sea level. Latest published map is in 
House Document 440, 56th Congress, 1st Session. Project 
was completed in 1911. 
Local cooperation. None required. 
Terminal facilities. Privately owned wharves and piers 
are the only terminal facilities at Anahuac. 
Operations during fiscal year. Routine maintenance. 
(See Table 15-H for dredging operations.) 
12B. CHANNEL TO LIBERTY, TX 
Location. Improvement is located in Galveston Bay and 
tidal reach of lower Trinity River. (See Geological Survey 
Maps for Anahuac, Cove, Moss Bluff, and Liberty, Texas.) 
Previous projects. For details see page 986 of Annual 
Report for 1932. 
Existing project. Provides for a 6-foot channel from 
-Anahuac to Liberty which was completed in 1925. A 
navigable channel from the Houston Ship Channel near 
Red Fish Bar in Galveston Bay to Liberty, Texas, with 
depth of 9 feet and width of 150 feet, extending along the 
east shore of Trinity Bay to the mouth of the Trinity River 
at Anahuac, thence in the river channel to a turning basin 
at Liberty, Texas, and a protective embankment along the 
west side of the channel in Trinity Bay. 
The 6-foot Channel to Liberty was completed in 1925. 
The 9-foot Channel to Liberty has been dredged from junction 
with Houston Ship Channel to a point one mile below 
Anahuac, Texas. Work remaining consists of dredging a 
9- by 150-foot channel from one mile below Anahuac, Texas 
to Liberty, Texas. 
Local cooperation. Fully complied with for portion of 
"Channel to Liberty" between Houston Ship Channel and 
1 mile below Anahuac, Texas, as required by 1946 River 
and Harbor Act (H. Doc. 634, 79th Cong., 2nd Sess.), but 
not complied with for remaining portion of "Channel to 
Liberty" as required by River and Harbor Act of 1945 (H. 
Doc. 403, 77th Cong., 1st Sess.) at an estimated total cost 
of $550,000, of which $460,000 is for lands and rights-ofway 
and $90,000 for pipeline relocations for 9- by 150-foot 
channel. 
Terminal facilities. Privately owned wharves and docks 
at Anahuac, Wallisville, Texas Gulf Sulphur Co&s slip, 
Moss Bluff and Liberty, Texas, are adequate for existing 
commerce. 
Operations during fiscal year. Routine maintenance. 
(See Table 15-H for dredging operations.) 
11C. WALLISVILLE LAKE, TX 
Location. Dam is at river mile 3.9, about 4 miles northwest 
of Anahuac, Texas. (See National Ocean Survey 
Chart 11323.) 
Existing project. Provides for construction of a dam 
and overflow spillway approximately 8 miles long to prevent 
salinity intrusion and create a 5,600-acre reservoir. 
The maximum pool elevation will be 4 feet above National 
Geodetic Vertical Datum. Project provides for an 84 foot 
by 600-foot navigation lock to facilitate navigation on 
Channel to Liberty. The sill has a depth of minus 16 feet 
below National Geodetic Vertical Datum. Project also provides 
for two recreational areas. Dam controls a drainage 
area of 1,262 square miles below Livingston Dam (non- 
Federal project at channel mile 99.2) and has a storage 
capacity of 58,000 acre-feet. Under ordinary conditions 
mean tidal range in bay is from 0.6 foot to 1.2 feet. Height 
of tide is dependent largely on wind. Strong northerly 
winds depress water surface 1.5 feet below mean sea level. 
Total estimated cost of authorized project is $67,700,000 
Federal (Corps). (October 1, 1986 base price.) 
A contract for construction of access road, Big Hog intake 
structure, intake canal and access bridge was completed 
in October 1968. Work started in July 1970 on construction 
of the lock and dam, roads, diversion channel, 
and navigation channel. Work was suspended in February 
1973 because of an injunction halting construction. Protective 
work on the lock and dam was permitted and was 
completed in April 1973. An exception to the injunction 
was granted for plugging oil wells which was completed 
in August 1973. Notice of appeal to the Court of Appeals 
for the Fifth Circuit was filed in April 1973. In August 
1974, the Court of Appeals reversed the judgment and 
remanded the case with directions that a revised or supplemental 
statement be prepared and judged anew. Final 
supplement to the Environmental Impact Statement for 
the modified project authorized in the Supplemental Appropriations 
Act, 1983 (PL 98-63) was submitted to the 
Environmental Protection Agency on September 21, 1983. 
The schedule for the completion of construction for the 
modified project is dependent on the time required to coordinate 
with the courts to lift the injunction, and the 
availability of construction funds. 
Local cooperation. Local interest must contribute an 
amount equal to cost allocated to water supply, one-half 
of cost allocated to salinity control and cost allocated to 
recreation less cost of basic facilities and less 15 percent 
of total project cost. Local interest contribution is 
estimated at $9,270,000. 
15-8

GALVESTON, TEXAS DISTRICT 
Operations during fiscal year. New Work: Planning 
for the non-overflow dam, Interstate 10 to the Lock site, 
is underway. 
Maintenance: Ranger surveillance, administration of 
project, and administration of duck blind permit program 
was conducted. 
13. RECONNAISSANCE AND 
CONDITION SURVEYS 
Reconnaissance and Condition Surveys were conducted 
on the following projects: 
Project 
Double .Bayou 
Date of Survey 
Jun-Jul 1986 
14. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645 (preauthorization). 
Reconnaissance study to investigate dredging the mouth 
of the Brazos River Diversion Channel for use by commercial 
navigation was completed at a fiscal year cost of 
$11,641. Study has been terminated. 
Reconnaissance study to investigate shorter alignments 
and bend easing on Lydia Ann Channel to Cover Harbor 
was completed at a fiscal year cost of $18,309. Study has 
been terminated. 
Initial appraisal reports on the feasibility of developing 
small craft harbors at Port Arthur, Texas, and at Corpus 
Christi, Texas, were completed at a fiscal year cost of 
$7,500 each. 
Beach Erosion 
15. CORPUS CHRISTI BEACH, TX 
(RESTORATION PROJECT) 
Location. Corpus Christi Beach, a shore area having 
a length of about 2 miles, is located on the west side of 
Corpus Christi Bay in Nueces County at Corpus Christi, 
Texas. (See National Ocean Survey Charts 11309 and 
11311.) 
Existing project. The plan of improvement provided for 
initial restoration of eroded areas of Corpus Christi Beach, 
over a shore length of 1.4 miles, located on the easterly 
side of Rincon Peninsula, with periodic nourishment as 
required. Construction was completed in March 1978. 
Periodic nourishment and construction of sand retention 
groin was completed in November 1985. Estimated cost 
of new work is $2,150,000 Federal (Corps) and $2,265,000 
non-Federal consisting of $2,150,000 contributed funds, 
$43,000 relocations, and $72,000 lands. (October 1,1986 
base price.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. A contract for periodic 
nourishment and construction of sand retention groin was 
completed in November 1985. Fiscal year cost for the contract 
was $524,204. 
r
f
1
I 
imately 10,534 acres of land and water areas was approved 
in February 1983. 
15-9
Flood Control 
16. ARROYO COLORADO, 
RIO HONDO, TX 
Location. The project is located on Arroyo Colorado at 
Rio Hondo, Texas which is approximately ten miles northeast 
of Harlingen, Texas and 30 miles north northwest 
of Brownsville, Texas. 
Existing project. The project provides for bank protection 
to 400 feet of the east bank of Arroyo Colorado 
downstream of Farm-to-Market Road 106. Estimated cost 
for new work is $201,300 Federal (Corps) and $7,000 non- 
Federal. Project was completed in 1984. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Project was fiscally 
completed. 
17. BUFFALO BAYOU AND 
TRIBUTARIES, TX 
Location. Improvements are on Buffalo Bayou watershed, 
a part of San Jacinto River watershed, in Harris 
County, west and northwest of city of Houston, Texas. (See 
Geological Survey quadrangle sheets for Harris County.) 
Existing project. Provides for improvement of Buffalo 
Bayou and its tributaries above turning basin of Houston 
Ship Channel to control floods for protection of city of 
Houston, and prevent deposition of silt in turning basin 
of ship channel by construction of detention reservoirs, 
enlargement and rectification of channels and construction 
of control works. Estimated cost of new work is 
$148,200,000 Federal (Corps) including $11,900,000 for 
recreational facilities at completed projects (Code 713 
funds) and $9,300,00 for Dam Safety Assurance, and 
$98,791,000 non-Federal, consisting of $86,891,000 for 
lands and relocations, and $11,900,000 contributions for 
recreational facilities. (October 1, 1986 base price.) 
Construction of Barker Dam was completed in February 
1945. Construction of Addicks Dam and 7.4 miles of channel 
rectification downstream from Addicks and Barker 
Dams was completed in October 1948. Modification of 
Barker and Addicks Dams consisting of gating of two uncontrolled 
conduits in each dam, was completed in 1969. 
Channel rectification on White Oak Bayou was completed 
in 1976. Major rehabilitation of Addicks and Barker Dams 
to prevent seepage through the embankment was completed 
in 1982. Work remaining consists of rectification 
of approximately 22 miles of main stem of Buffalo Bayou. 
Work under the Dam Safety Assurance program was initiated 
in Fiscal Year 1986. Work to be accomplished includes 
raising approximately 32,400 feet of Addicks Dam 
1 to 3 feet and raising approximately 57,600 feet of Barker 
Dam 3 to 5 feet and armor-plating low ends of both dams. 
A contract with the city of Houston for cost-sharing in the 
construction of recreation facilities at Cullen Park was 
entered into in November 1981. The lease for approx

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Local cooperation. Section 203, 1954 Flood Control 
Act applies. Local interests have accomplished all required 
local cooperation on Brays Bayou and White Oak Bayou. 
On Buffalo Bayou, local interests purchased interests that 
the United States had in 7 miles of rectified channel below 
Barker and Addicks Dams for $256,651. Of the remaining 
required rights-of-way on Buffalo Bayou, local interests 
have acquired about 40 percent. About 53 percent 
of required bridge relocations and 3 percent of the required 
utility relocations have been accomplished. Advance of 
$4,400,000 by the Harris County Flood Control District 
was refunded in September 1956. Public Law 86-53 
authorized reimbursement of $38,726 to Galveston, 
Houston and Henderson Railroad Company for bridge 
alterations at Brays Bayou. Non-Federal contributions 
totaled $63,661 for project betterments. Recreation 
development is subject to conditions of non-Federal costsharing 
under Federal Water Project Recreation Act of 
1965. 
Operations during fiscal year. Recreation: Construction 
of picnic areas, access roads, parking areas, and rough 
grading of ball fields for the Community Park West (Phase 
1A) were completed in July 1986. Construction of additional 
access, parking, restrooms, group shelters, and completion 
of ball fields for the Community Park West (Phase 
1B) and construction of a velodrome were substantially 
completed in July 1986. The fiscal year Federal cost of 
cost-shareable items was $96,000. 
Dam Safety Assurance: Raising Main Dam, Barker 
Dam, was awarded in June 1986. Fiscal year costs were 
$137,730. Raising Main Dam, Addicks Dam, was awarded 
in July 1986. Fiscal Year costs were $50,000. 
Maintenance: Routine operations and maintenance at 
Addicks and Barker Dams. 
18. CLEAR CREEK, TX 
Location. The project is located about midway between 
the two metropolitan centers of Houston, Texas, on the 
north and Galveston-Texas City on the south in Harris and 
Galveston Counties above and below existing Clear Lake. 
Existing Project. The authorized plan of improvement 
consists of an improved channel from Mile 3.8 to Mile 34.8 
to contain within its banks all flood flows up to and including 
that of a 100-year flood. The selected plan provides 
channel enlargement and easing of bends within the existing 
stream from Mile 3.8 to Mile 26.05 to contain at 
least the 10-year frequency storm, and additional outlet 
with gated structure from Clear Lake to Galveston Bay, 
restriction of development in the residual 100-year flood 
plain and measures to mitigate environmental effects. In 
1986, at the request of Brazoria County Drainage District 
No. 4, that portion of the project upstream of the 
Brazoria/Galveston County line, approximate improved 
Mile 18.5, was placed in the "inactive" category. 
Estimated cost for new work, excluding "inactive" portion, 
is $41,100,000 Federal (Corps) and $33,000,000 non- 
Federal consisting of $4,500,000 cash contributions, 
$15,700,000 for lands, and $12,800,000 for relocations 
(October 1, 1986 base price). 
Local Cooperation. Local sponsors for the project are 
Galveston and Harris counties. The Local Cooperation 
Agreement, executed 30 June 1986, required local interests 
to provide lands, easements, rights-of-way, and 
material disposal areas; modify or relocate building, 
pipelines, utilities, roads and other facilities, except 
railroad bridges, where necessary in the construction of 
the project; make a cash contribution for mitigation 
measures consistent with the non-Federal share of total 
project costs without mitigation measures; pay five percent 
of the total costs allocated to flood control; and bear 
all costs of operation and maintenance of flood control 
facilities. 
Operations during fiscal year. Engineering and 
Design is underway. 
19. PORT ARTHUR AND VICINITY, 
TX, (HURRICANE-FLOOD 
PROTECTION) 
Location. Port Arthur is on west shore of Sabine Lake 
in extreme southeast part of Texas, about 14 miles from 
the gulf. Area under consideration is comprised of about 
38,500 acres, and includes cities of Port Arthur and 
Groves, towns of Griffing Park, Pearl Ridge, and Lakeview, 
and adjacent industrial areas. 
Existing project. Authorized plan provides for raising 
and reconstructing 6.3 miles of existing concrete and steel 
sheet-pile seawall; constructing 0.3 mile of new concrete 
and sheet-pile seawall; raising and improving 3.0 miles 
of existing earth levees; constructing 20.3 miles of new 
earth levees and constructing five interior drainage pumping 
plants. Raising and strengthening of levees surrounding 
Gulf Oil Company's fresh water reservoir was placed 
in the "inactive" category in December 1980. The project 
was initiated in March 1966 and the active portion 
of the project was completed in 1984. Estimated cost for 
new work, excluding "inactive" portion, is $59,703,000 
Federal (Corps) and $26,036,000 non-Federal consisting 
of $16,016,000 cash contributions, $3,403,000 for lands, 
$6,168,000 for relocations, and $449,000 for pumping station 
betterments and levee realignment betterments. 
Local cooperation. Fully complied with. 
Operation during fiscal year. Investigation of levee 
settlement was performed. 
20. TAYLORS BAYOU, TX 
Location. Watershed of Taylors Bayou is in extreme 
southeast corner of Texas adjoining basins of Neches River 
and Sabine Lake on the east. City of Port Arthur is about 
8 miles from the main stream of Taylors Bayou. 
Existing project. Improvement consists of enlarging 
and rectifying approximately 53 miles of natural and artificial 
channels on Taylors Bayou and tributary water 
courses. Phase I consists of constructing a gated structure 
to prevent saltwater intrusion and 2.9 miles of new diversion 
channel and enlarging 1.8 miles of Gulf Intracoastal 
15-10

GALVESTON, TEXAS DISTRICT 
Waterway and a 1.9 mile section of the Outfall Canal. 
Phase II consists of enlarging 6.0 miles of Taylors Bayou, 
14.3 miles of Hillebrandt Bayou, 1.5 miles of Pivotot 
Bayou, 2.3 miles of Bayou Din, and 3.5 miles of Willow 
Marsh Bayou. Phase III consists of enlarging 7.0 miles 
of North Fork Taylors Bayou, 7.8 miles of South Fork 
Thylors Bayou and 4.4 miles of Mayhaw Bayou. The Phase 
III portion of the project was placed in the "inactive" 
category in November 1980. Initial contract on the "active" 
portion of the project was awarded in August 1982. 
Estimated cost for new work, excluding inactive portion, 
is $39,600,000 Federal (Corps) and $21,560,000 non- 
Federal, including $13,500,000 cash contribution, 
$4,331,000 lands, and $3,729,000 for relocations. (October 
1, 1986 base price.) 
Local cooperation. Section 204, 1965 Flood Control 
Act, applies. 
Operation during fiscal year. A contract for construction 
of the Salt Water Gate was completed at a fiscal year 
cost of $1,013,211. Enlargement of discharge channel in 
Gulf Intracoastal Waterway cost $2,587,999. 
21. TEXAS CITY AND VICINITY, TX 
(HURRICANE-FLOOD 
PROTECTION) 
Location. On the west and southwest shore of Galveston 
Bay, about 9 miles northwest of Galveston, Texas. Project 
fronts on the west side of Galveston Bay and protects a 
land area of about 36 square miles. 
Existing project. Plan provides for construction of improvements 
for control of storm tides. Improvements consist 
of 15.9 miles of new levees, 1.3 miles of concrete floodwall, 
related drainage and stoplog structures, one tide control 
structure, and two pumping plants. The project was 
initiated in 1962. All work is complete except for the La 
Marque Pumping Plant and drainage structures. Construction 
of the La Marque Pumping Plant was initiated 
in September 1982. Estimated cost for new work is 
$37,982,000 Federal (Corps) and $16,627,000 non-Federal, 
including $13,937,000 cash contribution, $1,071,000 work 
contribution, and $1,363,000 for lands, and $256,000 for 
ramps in lieu of closure structures and increased low flow 
pumping capacity for La Marque Pumping Plant. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Contract for construction 
of La Marque Pumping Plant was continued at a 
fiscal year cost of $239,920. Contract for interior drainage 
structures was completed at a fiscal year cost of $537,906. 
22. VINCE AND LITTLE VINCE 
BAYOUS, TX 
Location. Watershed of Vince Bayou and tributary, Little 
Vince Bayou, has an area of about 17 square miles and 
lies entirely within Harris County. Vince Bayou is a minor 
tributary of Buffalo Bayou in San Jacinto River Basin on 
upper gulf coast of Texas. 
Existing project. Project provides for enlarging and rectifying 
channel of Vince Bayou from mouth to a point 
about 7.3 miles upstream and Little Vince Bayou from 
mouth to a point about 4.2 miles upstream, a total 
distance in both streams of about 11.5 miles. The project 
was initiated in 1968. All work on Vince Bayou is complete. 
Planning is in progress on Little Vince Bayou. 
Estimated cost for new work is $20,100,000 Federal 
(Corps) and $17,300,000 non-Federal, consisting of 
$5,100,000 for lands and $12,200,000 for relocations. (October 
1, 1986 base price.) 
Local cooperation. Sec. 203, 1962 Flood Control Act, 
applies. Local interests have acquired all real estate and 
accomplished all required relocations on Vince Bayou. On 
Little Vince Bayou, local interests have acquired all real 
estate and accomplished 90 percent of the required 
relocations. 
Operations during fiscal year. Fiscal year cost for 
channel rectification on Little Vince Bayou, mile 0.7 to 
2.7, was $1,918,956. Fiscal year cost for channel rectification 
on Little Vince Bayou, mile 2.7 to 3.1 was $135,340. 
Fiscal year cost for channel rectification on Little Vince, 
mile 0 to mile 0.7, was $559,380. 
23. INSPECTION OF COMPLETED 
FLOOD CONTROL WORKS 
Inspections of completed projects operated and maintained 
by local interests were made on the following projects. 
Fiscal year cost was $116,725. 
Date of 
Project Inspection 
Gulf Intracoastal Waterway, Chocolate Bayou, Salt 
Water Barrier, TX 
Vince and Little Vince Bayou, TX 
San Diego Creek, Alice, TX 
Tranquitas Creek, Kingsville, TX 
Arroyo Colorado, Emergency Streambank Protection, 
Rio Hondo, TX 
Port Arthur & Vicinity, TX, Hurrican Flood 
Protection 
Guadalupe River Flood Protection, Victoria, TX 
Little Cypress Bayou Flood Protection, Orange, TX 
Brays Bayou, Channel Rectification, Houston, TX 
Texas City & Vicinity, TX, Hurricane-Flood Protection 
Colorado River, Flood Protection, Matagorda, TX 
Galveston Seawall, Galveston, TX 
Three Rivers, TX, Flood Protection 
Lavaca-Navidad River Flood Protection, Halletsville, TX 
White Oak Bayou, Channel Rectification, Houston, TX 
Freeport & Vicinity, TX, Hurricane-Flood Protection 
October 1985 
October 1985 
November 1985 
November 1985 
November1985 
February 1986 
February 1986 
February 1986 
April 1986 
April 1986 
June 1986 
June 1986 
July 1986 
July 1986 
August 1986 
September 1986 
15-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
24. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205 of 1970 
Flood Control Act, Public Law 858, 80th Congress, as 
amended: 
Plans and specifications for a flood control project 
at Kirbyville, Texas, were completed at a fiscal year 
cost of $61,095. 
An initial appraisal report on the feasibility of 
flood control work at Liggett Light Channel, 
Rockport, Texas, was initiated and completed at a 
fiscal year cost of $7,420. Study has been terminated. 
An initial appraisal report was completed and 
reconnaissance studies were initiated on the 
feasibility of providing flood damage reduction 
measures at Taylor Lake Village, Texas. Fiscal year 
cost was $14,156. 
Emergency bank protection activities pursuant to Section 
14 of 1946 Flood Control Act, Public Law 526, 79th 
Congress: 
Appraisal reports on the feasibility of bank 
stabilization measures at Palacios, Texas, and at Collegeport, 
Texas, were completed at fiscal year cost 
of $7,450 and $7,400, respectively. Both studies have 
been terminated. 
Emergency flood control activities-repair, flood fighting 
and rescue work (Public Law 99, 84th Congress and 
antecedent legislation): 
Costs were $150,313 for disaster preparedness and 
$7,286 for emergency operations. 
Rehabilitation work for Brays and White Oak 
Bayous Floodways cost $49,336. 
General Investigations 
25. SURVEYS 
Fiscal year costs were $2,306,875 of which $267,928 was 
for navigation studies, $1,948,740 was for flood damage 
prevention studies, $12,719 was for shoreline protection 
studies, $6,012 was for coordination with other agencies, 
$26,235 was for Special Investigations, $167 was for 
Deauthorization review, and $45,074 was for Planning 
Assistance to States. 
26. PLANNING AND ENGINEERING 
Sims Bayou at Houston, Texas-The project will provide 
for enlargement and rectification, with appropriate erosion 
control measures, of 19.31 miles of Sims Bayou to provide 
flood protection, environmental measures and 
riparian habitat improvement along the entire alignment; 
and recreational development consisting of hike-and-bike 
trails connecting public parks, as well as picnic and other 
day-use facilities. Estimated planning and engineering 
estimate is $1,970,000. Planning and engineering studies 
were initiated in Fiscal Year 1986. Fiscal year costs were 
feet deep and 600 feet wide over its 6.7 mile length and 
enlargement of Galveston Harbor Channel to 50-52 feet 
deep and 800 feet wide over the 10.5 mile length. The 
Galveston Entrance Channel would be extended 12.5 
miles to the 52-foot bottom in the Gulf of Mexico. A 50-year 
dredged material disposal plan will be provided by a combination 
of containment of dredged material on Snake 
Island, establishment of 600 acres of wetland, enlargment 
of Texas City Dike, and deposition of dredged material in 
the Gulf. Ninety acres of water-oriented recreational 
facilities on the Texas City Dike are included as a part 
of the proposed project. Estimated planning and engineering 
estimate is $1,570,000. Planning and engineering 
studies were intitiated in Fiscal Year 1986. Fiscal year 
costs were $266,519. 
Upper White Oak Bayou and Tributaries, vicinity of 
Houston, Texas - The project will provide for channel improvements 
on White Oak Bayou from Mile 10.7 to Mile 
19.9; on Cole Creek from Mile 0 to Mile 4.9; and on Vogel 
Creek from Mile 0 to Mile 4.5, for a total of 18.6 miles. 
Project also provides for flood plain zoning and regulation 
on the residual 100-year flood plains on White Oak Bayou 
from Mile 19.9 to near Mile 25.5; on Cole Creek form Mile 
4.9 to near Mile 6.9; and on Vogel Creek from Mile 4.5 
to near Mile 6.5; and includes recreational development 
along White Oak Bayou from near Mile 14.6 to near Mile 
18.3. Estimated planning and engineering estimate is 
$3,700,000. Planning and engineering studies were initiated 
in 1982. Fiscal year costs were $317,258. 
27. COLLECTION AND STUDY OF BASIC 
DATA 
Flood plain management and technical services were 
performed at a cost of $35,394 and $121,533, respectively. 
Hydrologic studies cost $8,380. 
$300,776. 
Texas City Channel, Texas (50-foot Project)-The project 
will provide for enlargement of Texas City Channel to 50
15-12

TABLE 15-A 
GALVESTON, TEXAS DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 19861 
1. Aquatic Plant 
Control (Southwestern 
Division) 1965 Act 
2. Brazos Island 
Harbor, TX 
3. Channel to Port 
Bolivar, TX 
4. Corpus Christi 
Ship Channel, TX 
(Regular Funds) 
(Contributed Funds) 
5. Freeport Harbor, TX 
6. Galveston Harbor 
and Channel, TX 
7. Gulf Intracoastal 
Waterway between 
Apalachee Bay, FL 
and the Mexican 
Border 
(Galveston Dist.) 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major rehab: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Minor rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major rehab: 
Approp. 
Cost 
Minor rehab: 
Approp. 
Cost 
140,000 180,000 261,000 350,000 
95,390 130,816 209,089 423,289 
1,948,1001 
1,872,7181 
- 11,857,5022 
- 11,857,5022 
4,593,000 448,100 
2,961,443 2,091,003 
90,000 862,876 35,714,3613 
85,612 807,209 35,653,8533 
- 2,170,080 
- 2,170,080 
- 133,9254 
- 133,9254 
45,000 (-)3,700 
40,531 535 
40,000 
260 
8,879 
48,946 
1,120,901 s 
1,120,900 s 
3,500,000 3,100,000 2,980,000 5,186,000 58,638,3596 
2,081,707 4,943,296 3,024,206 4,433,754 57,586,6046 
3,306,300 5,514,200 3,242,650 3,958,900 83,234,7787 
1,972,610 6,826,376 3,087,727 4,158,250 83,232,330' 
- 3,576,684 
- 3,576,684 
400,000 1,300,000 250,000 
682 1,397,580 395,274 
100,000 (-)25,000 
8,628 29,224 
115,000 
63,743 
200,000 
63,401 
55,000 
143,688 
3,642,088 
3,330,847 
3,012,1528 
3,003,0588 
4,243,200 1,891,650 5,752,000 790,100 42,239,2159 
3,742,067 2,061,605 6,079,286 801,255 42,236,4589 
- - - - 8,935 
- - - - 8,935 
- - - - 29,096,39210 
- - - - 29,096,39210 
381,000 12,061,900 2,149,920 2,151,100 75,811,92311 
105,968 12,337,285 2,129,284 2,168,744 75,802,84411 
- - - - 7,969,329 
- - - - 7,969,329 
600,000 
114,177 
17,523,000 
16,141,134 
2,300,000 
2,218,220 
9,878,800 
13,015,122 
6,920,000 
7,515,223 
9,888,525 
10,452,810 
1,445,000 
1,407,010 
14,157,400 
13,885,258 
61,253,30312 
61,140,51612 
195,404,15513 
194,804,33813 
- 434,638 
- 434,638 
- 835,873 
- 835,873 
15-13

TABLE 15-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project 
8. Houston Ship 
Channel, TX 
(Regular Funds) 
9. Matagorda, Ship 
Channel, TX 
(Regular Funds) 
10. Sabine-Neches 
Waterway, TX 
(Regular Funds) 
11. Texas City Channel, TX 
12. Trinity River and 
Tributaries, TX 
(Includes Wallisville) 
15. Corpus Christi Beach, 
TX (Restoration Project) 
(Contributed Funds) 
16. Arroyo Colorado, 
Rio Hondo, TX 
17. Buffalo Bayou and 
Tributaries, TX 
18. Clear Creek, TX 
Funding 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Recreation: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major rehab: 
Approp. 
Cost 
Dam Safety: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
FY 83 FY 84 FY 85 FY 86 Sep. 30, 19861 
6,640,880 
8,161,017 
2,745,800 
3,055,463 
13,419,700 
14,438,456 
6,945,000 
5,090,215 
1,677,000 
1,360,493 
4,560,200 
3,267,663 
3,912,500 
4,302,086 
434,000 
438,273 
6,028,900 
6,216,929 
1,353,000 
1,554,590 
70,000 
312,119 
444,000 
358,725
0 
123,491 
475,000 
111,499 
7,398 
167,072 
1,038,000 
1,358,579 
98,4 
1,452,7 
1,442,5 
1,471,0 
623,5 
350,0 
331,1 
3,303,1 
3,269,1 
3,110,5 
3,056,5 
4,859,5 
4,930,7 
1,955,9 
1,963,4 
196,C 
182,7 
1,930,8 
2,001,2 
(-)120,C 
264,5 
(-)60,0 
280,0 
- 35,760,38214 
- 35,760,38214 
100 98,175,62315 
155 98,110,09815 
- 18,058,77716 
- 18,058,77716 
45 36,469,588 
503 36,408,034 
- 56,136,81517 
- 56,136,81517 
500 129,900,52018 
766 129,869,74618 
- 13,325,47219 
- 13,325,47219 
)00 21,208,26120 
X70 21,208,19220 
- 726,158 
- 726,158 
)00 29,105,67621 
708 29,041,28021 
300 9,776,60322 
X02 9,756,67622 
)00 2,030,641 
506 1,996,409 
)00 2,038,345 
)45 1,999,957 
- 201,300 
58 201,300 
- 57,206,32423 
- 57,206,32423 
- 377,804 
00 283,833 
T00 17,238,813 
566 17,172,920 
- 12,475,000 
- 12,475,000 
}00 1,471,000 
44 623,544 
)00 3,201,361 
.39 3,158,801 
7,733- 
- 583,700 
25,864 393,238 
300,0 
156,2 
165,0 
138,4 
5 
201,300 
24,712 
250,204 
4,160 
1,702,000 
1,566,899 
(-)91 
260,000 
177,349
- - 
- - 
)00 640,000 
32 564,548 
00 399,500 
96 430,108 
- 595,000 
5 53,377 
5n nnn 
u,VVV 
53,377 
169,132 
2,953 
1,924,600 
1,966,162 
127 
152,000 
226,687 
21,157 
58,330 
15-14

TABLE 15-A 
GALVESTON, TEXAS DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 198617 
19. Port Arthur and New Work: 
Vicinity, TX Hurricane Approp. - (-)276,000 - - 59,702,509 
Flood Protection Cost (-)8,648 151,068 10,902 (-)2,599 59,682,040 
(Regular Funds) 
(Contributed Funds) New Work: 
Contrib. 230,000 - - - 16,291,97524 
Cost 130,069 64,957 2,293 1,517 16,237,64424 
20. Taylors Bayou, TX New Work: 
(Regular Funds) Approp. 1,900,000 2,650,000 3,550,000 3,594,000 14,537,198 
Cost 2,574,097 1,943,612 3,933,121 3,749,224 14,260,180 
(Contributed Funds) New Work: 
Contrib. 600,000 500,000 1,099,000 1,200,000 3,799,000 
Cost 614,494 425,850 1,284,523 1,138,507 3,519,246 
21. Texas City and New Work: 
Vicinity, TX Hurricane- Approp. 2,870,000 - 122,000 300,000 37,982,400 
Flood Protection Cost 1,419,324 1,558,750 941,301 639,007 37,810,304 
(Regular Funds) 
(Contributed Funds) New Work: 
Contrib. 700,000 900,000 200,000 175,000 14,210,10025 
Cost 608,280 669,567 446,234 354,683 14,081,81925 
22. Vince and Little Vince New Work: 
Bayous, TX Approp. 1,500,000 1,300,000 2,340,000 3,145,000 15,153,100 
Cost 420,002 2,499,132 1,953,848 3,203,495 14,764,653 
1 Excludes $376,841 credit for contributed work. 
2 Includes $675,855 for previous projects. In addition, 
$1,806,619 expended from contributed funds, of which $123,361 
was for previous projects. 
3 In addition, $14,692 expended from contributed funds. 
4 Includes $48,711 for previous projects. 
s Includes $46,101 for previous projects. 
6 Includes $1,372,534 for previous projects. Includes $456,515 
for Sec. 107 project for Port Aransas Breakwaters. In addition 
$768 expended from contributed funds for Port Aransas 
Breakwaters. 
? Includes $62,452 for previous projects. In addition, $445,269 
expended from contributed funds. 
8 Includes $147,098 for previous projects. In addition, $758,303 
expended from contributed funds. 
9 In addition, $229,311 expended from contributed funds. 
o1I0n cludes $8,421,996 for previous projects. In addition, 
$3,648,932 expended from contributed funds. 
11 Includes $86,126 for previous projects. In addition, 
$2,098,600 expended from contributed funds. 
12 Includes $706,709 for previous projects. Includes Sec. 107 
projects for Port Isabel Small Boat Basin ($46,559); Port Isabel 
Side Channel ($8,414); Offatts Bayou ($356,466); and Channel 
to Aransas Pass ($658,573). In addition contributed funds expended 
for Port Isabel Small Boat Basin ($46,559); Offatts Bayou 
($49,665); Channel to Aransas Pass ($347,950); Chocolate Bayou 
($658,310); and Mouth of Colorado River ($2,375,041). 
13 Includes $1,526,564 for previous projects. In addition, 
$22,672 expended from contributed funds. 
14 Includes $4,105,157 for previous projects. In addition, 
$2,591,939 expended from contributed funds, of which 
$1,209,179 was for previous projects. 
15 Includes $1,213,142 for previous projects. In addition, 
$363,360 expended from contributed funds, of which $200,000 
was for previous projects. 
16 In addition, $12,259,619 expended from contributed funds 
and $182,800 for contributed lands. 
17 Includes $5,180,832 for previous projects. In addition, 
$2,680,942 expended from contributed funds, of which $577,507 
was for previous projects. 
18 Includes $2,379,677 for previous projects. In addition, 
$2,636,582 expended from contributed funds. 
19 Includes $366,823 for previous projects. In addition, 
$1,023,819 expended from contributed funds, of which $99,000 
was for mitigation measures. 
20 Includes $195,083 for previous projects. 
21 Includes $1,966,306 for previous projects. in addition, 
$66,000 expended from contributed funds. 
22 Includes $543,662 for previous projects. 
23 Includes $4,400,000 of advanced funds repaid to Harris 
County Flood Control District. In addition, $63,661 contributed 
funds expended for Brays Bayou and $12,900 Federal funds and 
$19,104 contributed funds expended for enlargement of Clodine 
Ditch. 
24 Excludes $3,402,588 estimated value of contributed lands, 
$6,168,360 for relocations, and $217,000 credit given local sponsor 
for work-in-kind. 
25 Excludes $1,349,069 estimated value of contributed lands 
and $1,070,959 credit given local sponsor for work-in-kind. 
26 Includes funds ($12,544,400) provided by the Jobs Act (P.L. 
98-8, dated March 24, 1983) for projects listed in Table 15-I of 
Annual Report for 1985. 
15-15

TABLE 15-B 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. 
2. 
Oct. 27,1965 
Ju. 3, 1930 
May 24, 1934 
(PWA) 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 24, 1946 
May 17, 1950 
Jul. 14, 1960 
Jun. 25, 1910 
Mar. 4, 1919 
Mar. 3, 1899 
Jun. 13, 1902 
Mar. 3, 1905 
Mar. 2, 1907 
Feb. 27, 1911 
Mar. 4,19132 
Sep. 23, 1922 
Jul. 3, 19303 
AQUATIC PLANT CONTROL 
Provides for control of progressive eradication of aquatic 
plant growth from the navigable waters and streams in 
the U.S. 
BRAZOS ISLAND HARBOR, TX 
Jetties and jetty channel, inside channels and basins. 
Local cooperation requirement modified to provide 
contribution of funds to cover cost of original dredging of 
all inside channels and basins. 
Deepen jetty channel to 31 feet and inner channels and 
Brownsville and Port Isabel turning basins to 28 feet. 
Enlarge Port Isabel turning basin. 
Deepen entrance channel to 35 feet; deepen to 33 feet 
channel across Laguna Madre; deepen to 32 feet 
channels from Laguna Madre to turning basins at 
Brownsville and Port Isabel; widen turning basins; and 
dredging present shallow-draft channel south of Port 
Isabel from railroad bridge to Laguna Madre and 
connecting channel to Port Isabel turning basin. 
Additional connecting channel between Port Isabel and 
Brownsville channels; and transfer shallow-draft 
channels at Port Isabel to GIWW. 
Deepen to 38 feet in outer bar channels and 36 feet in all 
other authorized channels and basins; extend existing 
turning basins at Brownsville and Port Isabel; and construct 
small-boat basin with a connecting channel next to Brownsville 
ship channel. 
Widen Brownsville Channel to 300 feet at a depth of 36 
feet from former Goose Island passing basin to turning 
basin extension, thence at a width of 500 feet and same 
depth to turning basin proper, deepen to 36 feet in area 
in southeast corner of turning basin, maintain two 
existing basins of fishing harbor, and a connecting 
channel, and construct a third basin, with necessary 
connecting channel and extend Brazos Island Harbor 
north jetty seaward 1,000 feet.27 
CHANNEL TO PORT BOLIVAR, TX 
A channel 30 feet deep and 200 feet wide from deep water in 
Galveston Harbor extending to a turning basin 1,000 feet 
square and 30 feet deep. 
Enlargement, extension and protection of turning basin. 
CORPUS CHRISTI SHIP CHANNEL, TX 
Acquisition of old curvey portion of north jetty 
previously constructed by private parties. 
Complete north jetty in accordance with builder's plans. 
Complete north jetty in accordance with builder's plans. 
Connect old curve to St. Joseph Island, and construct 
south jetty. 
Dredge roadstead in Harbor Island Basin to 20 feet deep 
and construct 10,000 linear feet of stone dike on St. 
Joseph Island. 
Channel between jetties and Harbor Island Basin to 25 
feet deep, extend jetties seaward, extend dike on St. 
Joseph Island 9,100 feet, and dredge approach channel 
12 feet deep to town of Port Aransas. 
Dredging channel from Aransas Pass to Corpus Christi, 
25 feet deep, 200 feet bottom wideth. 
Deepen entrance channel from gulf to Harbor Island and 
provide an inner basin at Harbor Island of reduced area 
but greater depth. 
15-16 
H.Doc. 251,89th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 16, 
71st Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 10, 
71st Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 32 
75th Cong., 1st Sess. 
H.Doc. 335, 76th Cong., 
1st Sess. 
H.Doc. 347, 77th Cong., 
1st Sess. 
H.Doc. 627, 79th Cong., 
2nd Sess. 
H.Doc. 192, 81st Cong., 
1st Sess. 
H.Doc. 428, 86th Cong., 
2nd Sess.' 
H. Doc. 328, 61st Cong., 
2nd Sess. 
H. Doc. 1122, 65th Cong., 
2nd Sess.1 
Specified in Act. 
Specified in Acts. 
Specified in Act. 
Rivers and Harbors 
Committee Doc. 5, 
59th Cong., 2nd Sess. 
H. Doc. 1094, 61st Cong., 
3rd Sess. 
H. Doc. 1125, 62nd 
Cong., 3rd Sess. 
H. Doc. 321, 67th Cong., 
2nd Sess. 
H. Doc. 214, 70th Cong., 
1st Sess. 
3. 
4.

GALVESTON, TEXAS DISTRICT 
TABLE 15-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul. 3, 1930 
Aug. 30, 19354 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
Jun. 20, 1938 
Mar. 2, 1945 
Jun. 30, 1948 
Sep. 3, 1954 
Sep. 3, 19545 
Sep. 3, 1954 
Jul. 3, 1958 
Jul. 3, 1958 
Jul. 3, 1958 
Jul. 3, 1958 
Channel from Aransas Pass to Corpus Christi Channel 
with depth 30 feet. 
Enlarge all channels from gult to western end of basin 
dredged by Humble Oil and Refining Co., at its docks on 
Harbor Island 
Maintain channel and maneuvering basin between 
breakwater and western shoreline of Corpus Christi Bay. 
Maintain 30-foot depth of approach channel, turning 
basin at Corpus Christi, Industrial Canal and turning 
basin at Avery Point. 
Maintain and deepen to 32 feet channel from deep water 
at Port Aransas to and including turning basin at 
Corpus Christi. 
Extend main turning basin at Corpus Christi westward 
2,500 feet at its present width and depth, deepen existing 
Industrial Canal and turning basin to 32 feet and extend 
this canal at a depth of 32 feet and general width of 150 
feet, westward along Nueces Bay shore to a turning 
basin 32 feet by 900 feet, and 1,000 feet long near Tule 
Lake. 
Provide depth of 34 feet in all project channels and 
basins from Port Aransas to and including Tule Lake 
turning basin, for a width of 250 feet from Port Aransas 
to breakwater at Corpus Christi, for a width of 200 feet in 
Industrial Canal and in channel between Avery Point 
and Tule Lake turning basins, and widen Avery Point 
turning basin to 1,000 feet. 
Deepen entrance channel to 38 feet from gulf to outer end 
of jetty; 38 feet decreasing to 36 feet thence to station 90 
north jetty; and 36 feet in all other deep water channels 
and basins except 2,000-foot undredged part of inner 
basin at Harbor Island, and a width of 400 feet in 
channel from Port Aransas to Maneuvering basin at 
Corpus Christi. 
An anchorage basin 12 feet deep, from 300 to 400 feet 
wide, and 900 feet long in Turtle Cove at Port Aransas, 
Texas. 
Branch channel 32 feet by 150 feet, extending northerly 
from main channel in vicinity of Port Ingleside, along 
north shore of Corpus Christi Bay to Reynolds Metals 
Co. plant and turning basin 32 feet deep and 800 feet 
square near plant in general vicinity of LaQuinta, Texas. 
An entrance channel 36 by 400 feet on a tangent 
alignment from 400-foot channel in Corpus Christi Bay, 
near Corpus Christi breakwater to flared approach 
channel to Corpus Christi turning basin. 
Deepen and widen LaQuinta Channel to 36 by 200 feet; 
enlarge LaQuinta turning basin to 36 by 800 by 1,000 
feet; a flared entrance to channel; and widening at curves. 
Deepen entrance channel to 42 feet from gult to outer end 
of jetty; 40 feet in all other deep-water channels and 
basins except undredged northward extension to inner 
basin at Harbor Island and branch channel to LaQuinta; 
and widen Industrial Canal to 400 feet with flared 
entrances to Corpus Christi and Avery Point turning 
basins. 
Channel 40 by 200 feet extending 2.2 miles from Tule 
Lake turning basin to a turning basin 40 feet deep, 700 to 
900 feet wide, 1,000 feet long at Viola, Texas. 
Depth of 12 feet and a width of 100 feet in locally 
dredged Jewel Fulton Canal from LaQuinta Channel to 
a turning basin 12 by 200 by 400 feet, and assumption of 
maintenance by United States. 
Rivers and Harbors 
Committee Doc. 9, 
71st Cong., 1st Sess. 
Rivers and Harbors 
Committee Docs. 35, 
72nd Cong., 1st Sess., 
and 40, 73rd Cong., 
2nd Sess. 
H. Doc. 130, 72nd Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 13, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 63, 
74th Cong., 1st Sess. 
H. Doc. 574, 75th Congr., 
3rd Sess. 
H. Doc. 544, 78th Cong., 
2nd Sess. 
H. Doc. 560, 80th Cong., 
2nd Sess. 
H. Doc. 654, 81st Cong., 
1st Sess. 
H. Doc. 89, 83rd Cong., 
1st Sess. 
H. Doc. 487, 83rd Cong., 
2nd Sess. 
S. Doc. 33, 85th Cong., 
1st Sess. 
H. Doc. 361, 85th Cong., 
2nd Sess. 
H. Doc. 361, 85th Cong., 
2nd Sess. 
H. Doc. 361, 85th Cong., 
2nd Sess. 
15-17

TABLE 15-B 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul. 14, 1960 
(As amended by 
Dec. 31, 1970) 
Aug. 13, 1968 
Oct. 22, 1976 
Mar. 3, 1899 
Mar. 2, 1907 
Feb. 27, 1911 
Mar. 4, 1913 
Aug. 8, 1917 
Mar. 3, 19256 
Jul. 3, 1930 
Aug. 30, 19357 
Aug. 30, 1935 
May 17, 1950 
Jul. 3, 1958 
Oct. 5, 1961 
Dec. 31, 1970 
Construction of a breakwater at entrance to harbor area 
at Port Aransas, and realignment of existing 12-foot by 
100-foot project channel. 
Provides for a project depth of 45 feet in the existing 
deep-draft channels and basins, for construction of a 
new deep-draft turning point, for construction of a deepdraft 
mooring area and mooring facilities and for 
widening of the channels and basins at certain locations. 
The Act also deauthorized the undredged northward 
extension of Inner Basin at Harbor Island and the 
undredged west turnout (Wye connection) between the 
LaQuinta Channel and the main channel of the waterway. 
Modified local cooperation requirements for 1968 Act. 
Shifted responsibility for cost of disposal areas and 
confinement works from sponsor to joint 75 percent 
Federal and 25 percent non-Federal responsibility 
FREEPORT HARBOR, TX 
Dredging and other work necessary in judgment of 
Secretary of War for improving harbor; for taking over 
jetties and privately built works at mouth of river. 
Examination authorized. Work later confied to maintenance 
of jetties. 
Repairs to jetties and dredging. 
Construct seagoing hopper dredge. 
Purchase of one 15-inch pipeline dredge and equipment, 
its operation of 3 years, operation of seagoing dredge 
one-half time for 3 years, and repairs to jetties. 
Diversion dam, diversion channel, and necessary auxiliary 
works. 
Maintenance of diversion channel at expense of local 
interest. 
Deepening channels and basins. 
Maintenance of present project dimensions of channels 
and basins at Federal expense. 
Deepen outer bar channel to 38 feet from gulf to a 
point within jetties, thence 36 feet in authorized channels 
to and including upper turning basin. 
Relocate outer bar channel on straight alignment with 
jetty channel and maintain Brazos Harbor entrance 
channel and turning basin (constructed by local 
interests). 
Modification of HD 1469. Revoking certain provisions of 
local cooperation. 
Relocation of entrance channel and deepen to 47 feet; 
enlargement to a depth of 45 feet and relocation of jetty 
channel and inside main channel; deepening to 45 feet of 
channel to Brazosport; enlargement of the widened area 
of Quintana Point to provide a depth of 45 feet with a 
750-foot diameter turning area; Brazosport turning basin 
to 45 feet deep with a 1,000 foot turning area; a new 
turning basin with a 1,200 foot diameter turning area 
and 45 feet deep; deepening Brazosport channel to 36 by 
750 feet diameter; flared approaches from Brazos Harbor 
Channel; relocation of north jetty and rehabilitation of 
south jetty. 
Sec. 107, PL 86-645 
S. Doc. 99, 90th Cong., 
2nd Sess.' 
Sec. 124, PL 94-587 
Specified in Act. 
H. Doc. 1087, 60th Cong., 
2nd Sess. 
Specified in Act. 
Specified in Act. 
Specified in Act. 
Rivers and Harbors 
Committee Doc. 10, 
68th Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 18, 
70th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 15, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Docs. 15, 
72nd Cong., 1st Sess., 
and 29, 73rd Cong., 
2nd Sess. 
H. Doc. 195, 81st Cong., 
1st Sess. 
H. Doc. 433, 84th Cong., 
2nd Sess. 
PL 394, 87th Cong. 
H. Doc. 289, 93rd Cong., 
2nd Sess.2 
15-18 
5.

GALVESTON, TEXAS DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
6. Aug. 5, 1886 
Jun. 13, 1902 
Mar. 3, 1905 
Mar. 2, 1907 
Mar. 2, 1907 
Jun. 25, 19109 
Jul. 27, 1916 
Jul. 18, 1918 
Sep. 22, 1922 
Jan. 21, 1927 
Aug. 30, 193511 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
Apr. 4, 1938 
Jun. 30, 1948 
May 17, 1950 
Jul. 3, 1958 
Jun. 23, 1971 
(House Res.) 
(Nov. 18, 1971 
(Sen. Res.) 
Mar. 2, 1907 
Mar. 3, 1925 
Jan. 21, 1927 
GALVESTON HARBOR AND CHANNEL, TX 
Construct 2 rubblestone jetties at entrance to Galveston 
Harbor. 
A channel 1,200 by 30 feet from Bolivar Roads (outer 
end of old inner bar near Fort Point) at 51st Street. 8 
Purchase or construct hydraulic pipeline dredge. 
Extension of jetties to present project length and 
construction and operation of a dredge. 
Extension of Galveston Channel from 51st to 57th Sts., 
with depth of 30 feet and width of 700 feet. 
Conditional extension of Galveston Channel between 51st 
and 57th Sts., 30 feet deep and 1,000 feet wide. 
Extend seawall at Galveston from angle at 6th St. and 
Broadway to vicinity of Fort San Jacinto. 
Deepen harbor channel to 35 feet and widen to 800 feet. 
Further extension of seawall at Galveston to a junction 
with south jetty; and repairing seawall in front of Fort 
Crockett reservation. 
Deepen Galveston Channel to 32 feet; and maintain 
Galveston Harbor channels to dimensions of 800 feet 
wide, 35 feet deep on outer bar and 34 feet deep in inner 
bar.10 
Maintain State Highway Ferry Landing Channels to 
dimensions of 12 by 100 feet. 
Construct 13 groins along gulf shore from 12th to 61st Sts. 
in city of Galveston at a limited cost of $234,000 (10 
groins constructed). 
Deepen Galveston Channel to 34 feet (Bolivar Roads to 
43rd St.). 
Deepen Galveston entrance channel to 36 feet. 
Completion of project for construction of 13 groins. 
Deepen Glaveston Harbor to 38 feet from gulf to a point 
2 miles west of seaward end of north jetty; thence 36 feet 
to Bolivar Roads; revoking authority for maintenance of 
ferry channels; and Galveston channel to 36 feet deep 
from Bolivar Roads to 43rd Street. 
Construct extension of Galveston Seawall from 61st 
Street, southwesterly 16,300 feet along gulf shore. 
Deepen Galveston Harbor to 42 feet from gulf to point 2 
miles west of seaward end of north jetty and 40 feet 
thence to Bolivar Roads. 
Deepen Galveston Channel to 40 feet from Bolivar Roads 
to 43rd Street. 
GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FL AND MEXICAN BORDER12 
Channel 4 by 100 feet from West Galveston Bay across 
Chocolate Bay to 4 feet of water in Chocolate Bay. 
Channel 9 by 100 feet, Sabine River to Galveston Bay, 
and a 20-inch pipeline dredge. Such passing places, 
widening at bends, locks or guard locks and railway 
bridges over artificial cuts as are necessary. 
Channel 9 by 100 feet, Galveston Bay to Corpus Christi. 
15-19 
TABLE 15-B 
H. Doc. 85, 49th Cong., 
1st Sess., and Annual 
Report, 1886, p. 1311. 
H. Doc. 264, 56th Cong., 
2nd Sess. 
Specified in Act. 
H. Doc. 340, 59th Cong., 
2nd Sess., and 
Rivers and Harbors 
Committee Doc. 11, 
59th Cong., 2nd Sess. 
H. Doc. 768, 59th Cong., 
2nd Sess. 
H. Doc. 328, 61st Cong., 
2nd Sess. 
H. Doc. 1390, 62nd 
Cong., 3rd Sess. 
H. Doc. 758, 65th Cong., 
2nd Sess. 
H. Doc. 693, 66th Cong., 
2nd Sess. 
H. Doc. 307, 69th Cong., 
1st Sess. 
River and Harbors 
Committee Doc. 31, 
72nd Cong., 1st Sess. 
H. Doc. 400, 73rd Cong., 
2nd Sess. 
Rivers and Harbors 
Committee Doc. 61, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 57, 
74th Cong., 1st Sess. 
PL 463, 75th Cong. 
H. Doc. 561, 80th Cong., 
2nd Sess. 
H. Doc. 173, 81st Cong., 
1st Sess. 
H. Doc. 350, 85th Cong., 
2nd Sess. 
H. Doc. 121, 92nd Cong., 
1st Sess. 
(Sec. 201, PL 89-298) 
H. Doc. 445, 56th Cong., 
1st Sess. 
H. Doc. 238, 68th Cong., 
1st Sess. 
H. Doc. 238, 68th Cong., 
1st Sess. 
7.

TABLE 15-B 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug. 26, 1937 
Jun. 20, 193813 
Jun. 20, 1938 
Jun. 20, 1938 
Jun. 20, 1938 
Jun. 20, 1938 
Mar. 23, 1939 
Jul. 23, 1942 
Mar. 2, 1945 
Mar. 2, 19459 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 194514 
Jul. 24, 1946 
Jul. 24, 1946 
May 17, 1950 
May 17, 1950 
May 17, 1950 
Jul. 12, 1952 
Sep. 3, 195415 
Sep. 3, 1954 
Sep. 9, 1959 
Maintenance of a flood-discharge channel in Colorado 
River. 
Channel 9 by 100 feet in San Bernard River, Texas. 
Channel in Colorado River, 9 by 100 feet, with basin. 
Channel 9 by 100 feet from Palacios through Trepalacios 
and Matagorda Bays. 
Channel 9 by 200 feet from main channel to harbor at 
Rockport and improve harbor to 9-foot depth. 
Channel 6 by 100 feet from main channel to Aransas 
Pass, Texas. 
Enlarge waterway to depth of 12 feet and a width of 125 
feet from Sabine River to Corpus Christi. 
Enlarge waterway from Corpus Christi to vicinity of 
Mexican border to provide a depth of 12 feet and width of 
125 feet throughout. 
Channel 6 by 60 feet from GIWW to a point in Chocolate 
Bayou near Liverpool. 
Channel 6 feet deep and 60 feet wide from main channel 
near Port O'Connor, Texas, into Barroom Bay. 
Enlarge channel from main channel to Aransas Pass, 
Texas, providing a depth of 9 feet and width of 100 feet. 
Channel 12 by 125 feet from main channel to Red Fish 
Landing, Texas, with basin. 
Channel 12 feet deep and 125 feet wide from main channel 
to vicinity of Harlingen, Texas, via Arroyo Colorado 
with basin. 
Fill a portion of shallow-draft channel adjacent to Port 
Isabel Turning Basin, construct a channel to connect 
shallow-draft channel with main channel near shoreline 
of Laguna Madre, and enlarge shallow-draft channel 
west of this connection, all to 12-foot depth and 
bottom width of 125 feet. 
Reroute main channel to north shore of Red Fish Bay 
between Aransas Bay and Corpus Christi Bay; deepen 
tributary channel from Port Aransas to Aransas Pass, 
Texas, 12 feet and extended basin at same depth. 
Deauthorized 6 by 60 foot channel in Chocolate Bayou 
and reauthorized the 4 by 100-foot channel. 
Alternate channel across South Galveston Bay between 
Port Bolivar and Galveston causeway. 
"Red Fish Landing" changed to "Port Mansfield, 
Texas." 
Incorporate as part of Intracoastal Waterway a channel 9 
by 100 feet from main channel via Seadrift to point on 
Guadalupe River 3 miles above Victoria, Texas, 
authorized by River and Harbor Act of 1945. 
Small craft harbor 9 by 200 by 1,000 feet at Seadrift with 
an entrance channel 9 by 100 feet. 
Widen tributary channel between Port Aransas and 
Aransas Pass, Texas, to 125 feet; straighten and widen 
to 125 feet connecting channel to Conn Brown Harbor, 
and maintain Conn Brown Harbor at Federal expense, 
all to 12 feet deep. 
Improve channels and basins comprising channel to Port 
Mansfield constructed in part by Federal Government 
and in part by local interest; constructing turnout curves 
at Gulf Intracoastal Waterway intersection and bend 
easing at entrance to turning basin; construct parallel 
jetties at gulf entrance; maintenance of locally dredged 
jetty channel 16 by 250 feet; and maintenance of small 
craft basin. 
S. Committee print, 
75th Cong., 1st Sess. 
H. Doc. 640, 75th Cong., 
3rd Sess. 
H. Doc. 642, 75th Cong., 
3rd Sess. 
H. Doc. 564, 75th Cong., 
3rd Sess. 
H. Doc. 641, 75th Cong., 
3rd Sess. 
H. Doc. 643, 75th Cong., 
3rd Sess. 
H. Doc. 230, 76th Cong., 
1st Sess. 
PL 675, 77th Cong. 
H. Doc. 337, 76th Cong., 
1st Sess. 
H. Doc. 428, 76th Cong., 
1st Sess. 
H. Doc. 383, 77th Cong., 
1st Sess. 
S. Doc. 248, 78th Cong., 
2nd Sess. 
H. Doc. 402, 77th Cong., 
1st Sess. (See Public 
Law 14, 79th Cong.) 
H. Doc. 627, 79th Cong., 
2nd Sess. 
H. Doc. 700, 79th Cong., 
2nd Sess. 
H. Doc. 768, 80th Cong., 
2nd Sess. 
H. Doc. 196, 81st Cong., 
1st Sess. 
PL516, 81st Cong. 
PL 527, 82nd Cong., 
2nd Sess. 
H. Doc. 478, 81st Cong., 
2nd Sess. 
H. Doc. 376, 83rd Cong., 
2nd Sess. 
S. Doc. 11, 86th Cong., 
1st Sess. 
15-20

GALVESTON, TEXAS DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul. 14, 1960 
Jul. 14, 1960 
(As amended 
Dec. 31, 1970) 
Jul. 14, 1960 
(As amended 
Dec. 31, 1970) 
Jul. 14, 1960 
(As amended 
Dec. 31, 1970) 
Oct. 23, 196216 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 27, 196517 
Aug. 13, 1968 
Mar. 5, 1905 
Mar. 2, 1919 
Mar. 3, 1925 
Jul. 3, 1930 
Entrance channel 7 feet deep by 75 feet wide from main 
channel to Gulf of Mexico to inside shoreline at Port 
Isabel, Texas, an inner channel 6 feet deep by 50 feet 
wide from entrance channel to East Harbor Basin, and 
an irregular-shaped harbor basin 6 feet deep having a 
surface area of about 7 acres. 
Deepen the existing 6-foot channel at Port Isabel to 12 feet 
and removing the submerged bars at each end of the 
island to a depth of -12 feet MLT. 
Deepening the existing channel to 12 by 125 feet, and 
extend southeasterly from the Gulf Intracoastal Waterway 
main channel in West Galveston Bay, into Offatts 
Bayou, a distance of 2.2 miles, and a west turnout 12 
by 125 feet between the proposed Offatts Bayou Channel 
and the Gulf Intracoastal Waterway. 
Deepening Aransas Pass tributary channel to 14 feet from 
mile 0 at Harbor Island to mile 6.1 at the city of Aransas 
Pass; widening to 175 feet between miles 3.5 and 4.6; 
and deepening Conn Brown Harbor, turning basin and 
connecting channel between Conn Brown Harbor and 
turning basin. 
Improve main channel 16 feet deep and 150 feet wide 
from Sabine River to Houston Ship Channel; with two 
relocations; relocate main channel in Matagorda Bay 
and Corpus Christi Bay; and maintaining existing 
Lydia Ann Channel. 
Deepen and widen channel to Palacios; construct two 
protective breakwaters; maintain and deepen existing 
basins; and deepen, enlarge and maintain existing 
approach channel to basin No. 2. 
Eliminates requirement of local interest to construct bridge 
at mile 29.2 turning basin at Victoria, and maintain 
turning basins at Victoria and Seadrift; provide: Federal 
construction of vertical-lift railroad bridge at Missouri- 
Pacific Railroad mainline crossing, mile 29.2; construction 
and future maintenance of basin near Victoria, 
Texas, and maintenance of basin constructed by local 
interests at Seadrift, Texas. 
Modify existing Federal navigation project to provide a 
channel extending from Gulf Intracoastal Waterway 
through Chocolate Bay and Chocolate Bayou to project 
channel mile 8.2, thence to a turning basin near channel 
mile 13.2 and for salt water barrier in Chocolate Bayou 
about 3.7 miles upstream from basin (channel mile 16.9). 
Entrance channel 15 feet deep and 200 feet wide at the 
mouth of Colorado River Channel protected by an east 
jetty 3,500 feet long extending to 12-foot depth and 
a west jetty 2,900 feet long extending to 5-foot contour; 
make channel 12 feet by 100 feet from gulf shore to 
Matagorda, including recreation facility, a turning basin 
12 feet by 300 feet wide and 1,450 feet long, and a new 
diversion channel 250 feet wide and varying in depth 
from 20 to 23 feet including a closure dam across the 
present river channel. 
HOUSTON SHIP CHANNEL, TX 
Easing or cutting off sharp bends and construction of a 
pile dike.18 
A channel 30 feet deep, widen bend at Manchester and 
enlarge turning basin. 
A light-draft extension of channel to mouth of White Oak 
Bayou.1 9 
Widen channel through Morgan Point and to a point 
4,000 feet above Baytown and widen certain bends. 
Sec. 107, PL 645, 
86th Cong. 
Sec. 107, PL 86-645 
Sec. 107, PL 86-645 
Sec. 107, PL 86-645 
H. Doc. 556, 87th Cong., 
2nd Sess. 
H. Doc. 504, 87th Cong., 
2nd Sess. 
H. Doc. 288, 87th Cong., 
2nd Sess. 
H. Doc. 217, 89th Cong., 
1st Sess. 
S. Doc. 102, 90th Cong., 
2nd Sess. 
Rivers and Harbors 
Committee Doc. 35, 
61st Cong., 2nd Sess. 
H. Doc. 1632, 65th Cong., 
3rd Sess. 
H. Doc. 93, 67th Cong., 
1st Sess. 
H. Doc. 13, 71st Cong., 
1st Sess. 
15-21 
TABLE 15-B

TABLE 15-B 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug. 30, 193511 
Aug. 30, 1935 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
Jun. 30, 1948 
Jul. 3, 195820 
Jul. 14, 1960 
Oct. 27, 1965 
Jun. 25, 1910 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 3, 1958 
Jul. 3, 1958 
Jul 25, 1912 
Sep. 22, 1922 
Sep. 22, 1922 
Deepen to 32 feet in main channel and turning basin, and 
a 400-foot width through Galveston Bay. 
Deepen to 34 feet in main channel and widen from Morgan 
Point to turning basin. 
Branch channel 10 by 60 feet behind Brady Island. 
Widen channel from Morgan Point to lower end of 
Fidelity Island with turning points at mouth of Hunting 
Bayou and lower end of Brady Island. 
Widen channel from lower end of Fidelity Island to 
Houston turning basin and dredge off-channel silting 
basins. 
Deepen to 36 feet from Bolivar Roads to and including 
main turning basin at Houston, Texas, including turning 
points at Hunting Bayou and Brady Island. 
Deepen to 40 feet from Bolivar Roads to Brady Island, 
construct Clinton Island turning basin, a channel 8 by 
125 feet at Five Mile Cut, and improve shallow-draft 
channel at Turkey Bend. 
Barbour Terminal at Morgan Point. 
Restoring existing locally dredged channel from mile 0 to 
0.34 to 36 feet deep and dredging a 15-12 ft. channel from 
mile 0.34 to 2.81, in Greens Bayou.21 
MATAGORDA SHIP CHANNEL, TX 
Channel to Port Lavaca, Texas 7 feet deep and 89 feet 
bottom width. 
Extend 7-foot channel to shoreline of Lavaca Bay at 
mouth of Lynns Bayou. 
Deepen and widen channel to present project dimensions. 
Extend channel 6 by 100 feet from Port Lavaca via 
Lavaca Bay, Lavaca and Navidad Rivers to Red Bluff, a 
distance of 20 miles. 
A harbor of refuge 9 feet deep near Port Lavaca and an 
approach channel 100 feet wide and equal depth. 
Deepen to 12 feet and widen to 125 feet Port Lavaca 
Channel and approach channel to harbor of refuge; 
deepen to 12 feet Port Lavaca turning basin and basins 
at harbor of refuge. 
An entrance channel 38 by 300 feet, a channel 36 by 200 
feet, 22 miles long across Matagorda and Lavaca Bays 
to Point Comfort, Texas, a turning basin 36 feet deep and 
1,000 feet square at Point Comfort, and dual jetties at 
entrance from gulf. 
SABINE-NECHES WATERWAY, TX 
Existing project dimensions of jetties, a 26-foot channel 
through Sabine Pass, Port Arthur Canal and Port 
Arthur turning basin; and a 26-foot turning basin at Port 
Arthur. A depth of 25-feet in Sabine-Neches Canal, 
Neches River to Beaumont and Sabine River to Orange, 
including cutoffs and widening channels. 
Deepen channels to 30 feet from gulf to Beaumont, with 
increased widths and an anchorage basin in Sabine 
Pass. 
Deepen Port Arthur east and west turning basins and 
approach channel to 30 feet. Take over and deepen 
to 30 feet channel connecting west turning basin with 
Taylors Bayou turning basin. For a 30-foot depth in 
channel from mouth of Neches River to cutoff in Sabine 
River near Orange. 
Rivers and Harbors 
Committee Doc. 28, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 58, 
74th Cong., 1st Sess. 
H. Doc. 226, 76th Cong., 
1st Sess. 
H. Doc. 256, 76th Cong., 
1st Sess. 
H. Doc. 737, 79th Cong., 
2nd Sess. 
H. Doc. 561, 80th Cong., 
2nd Sess. 
H. Doc. 350, 85th Cong., 
2nd Sess.1 
Sec. 107, PL 86-645 
R. Doc. 257, 89th Cong., 
1st Sess. 
H. Doc. 1082, 60th Cong., 
2nd Sess. 
Rivers and Harbors 
Committee Doc. 28, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 37, 
75th Cong., 1st Sess. 
H. Doc. 314, 76th Cong., 
1st Sess. 
H. Doc. 731, 79th Cong., 
2nd Sess. 
H. Doc. 131, 84th Cong., 
1st Sess. 
H. Doc. 388, 84th Cong., 
2nd Sess.' 
H. Doc. 773, 61st Cong., 
2nd Sess. 
H. Doc. 975, 66th Cong., 
3rd Sess. 
S. Doc. 152, 67th Cong., 
2nd Sess. 
15-22 
10.

GALVESTON, TEXAS DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Mar. 3, 1925 
Jan. 21, 1927 
Aug. 30, 193511 
Aug. 30, 193511 
Aug. 30, 1935 
Aug. 26, 1937 
Aug. 26, 1937 
Jun. 20, 193822 
Oct. 17, 1940 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 24, 194623 
Jul. 24, 194624 
Jul. 24, 1946 
May 17, 1950 
Removal of guard lock in Sabine-Neches Canal. 
Widen Sabine Pass and jetty channel, Port Arthur 
Canal, and Sabine-Neches Canal. For dredging 2 
passing places in Sabine-Neches Canal, easing of 
bends, removal and reconstructing Port Arthur field 
office, extending Beaumont turning basin upstream 
200 feet above new city wharves, and an anchorage 
basin in Sabine Pass. 
A depth of 32 feet in channels from gulf to Beaumont 
turning basin, including all turning basins at Port 
Arthur. 
Deepen channels to 34 feet with increased widths from 
gulf to Beaumont turning basin. 
Construct suitable permanent protective works along 
Sabine Lake. Maintain Taylors Bayou turning basin. 
Maintain channel from Sabine River to Orange 
Municipal wharf. 
Dredging 500 feet from eastern end of Harbor Island 
and abandonment of channel south and west of Harbor 
Island. 
Increased widths of channels from gulf to Beaumont 
turning basin and channel connecting Port Arthur west 
turning basin and Taylors Bayou turning basin, deepen 
Beaumont turning basin and Beaumont turning extension 
to 34 feet; and dredge a new cutoff from Smith's 
Bluff cutoff to McFadden Bend. 
Abandon Orange turning basin; dredge a channel 25 by 
150 feet, suitably widened on bends to highway bridge, 
and dredge a cutoff channel opposite Orange. 
Extend Beaumont turning basin upstream 300 feet. 
Widen Port Arthur west turning basin to 600 feet. 
Dredge a channel from Beaumont turning basin to 
vicinity of Pennsylvania Shipyard. 
Deepen Sabine Pass outer bar channel to 37 feet, Sabine 
Pass jetty channel to 36 feet at inner end, deepen to 
36 feet Sabine Pass Channel, Port Arthur Canal, Port 
Arthur east and west turning basins, Taylors Bayou 
turning basin and channel from Port Arthur west 
turning basin to Taylors Bayou turning basin, deepen 
to 36 feet and widen to 400 feet Sabine-Neches Canal 
from Port Arthur Canal to mouth of Neches River 
except through Port Arthur Bridge; deepen Neches 
River channel from mouth to Beaumont turning basin 
to 36 feet widening to 350 feet from Smith's Bluff 
to Beaumont turning basin; deepen junction area on 
Neches River at Beaumont turning basin to 36 feet; 
and widen Sabine-Neches Canal between Neches and 
Sabine Rivers to 150 feet. 
Improve Cow Bayou, Texas, by construction of a channel 
100 feet wide and 13 feet deep extending from navigation 
Channel in Sabine River to a point 0.5 mile above county 
bridge at Orangefield, Texas, with a turning basin. 
Improve Adams Bayou, Texas, to provide a channel 12 
feet deep and 100 feet wide extending from 12-foot depth 
in Sabine River to first county highway bridge across 
bayou. 
Deepen to 36 feet and widen to 400 feet the Sabine- 
Neches Canal near Port Arthur bridge; reconstruct Port 
Arthur Bridge and relocate Port Arthur field office. 
H. Doc. 234, 68th Cong., 
1st Sess. 
H. Doc. 287, 69th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 27, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 12, 
74th Cong., 1st Sess. 
Specified in Act. 
Rivers and Harbors 
Committee Doc. 3, 
75th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 20, 
75th Cong., 1st Sess. 
H. Doc. 581, 75th Cong., 
3rd Sess. 
S. Doc. 14, 77th Cong., 
1st Sess. 
H. Doc. 685, 76th Cong., 
3rd Sess. 
S. Doc. 60, 77th Cong., 
1st Sess. 
S. Doc. 158, 77th Cong., 
2nd Sess. 
H. Doc. 571, 79th Cong., 
2nd Sess. 
H. Doc. 702, 79th Cong., 
2nd Sess. 
H. Doc. 626, 79th Cong., 
2nd Sess. 
H. Doc. 174, 81st Cong., 
1st Sess. 
15-23 
TABLE 15-B

TABLE 15-B 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Sep. 3, 195425 
Oct. 23, 196226 
Mar. 4, 1913 
Jul. 3, 1930 
Aug. 30, 193511 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 26, 1937 
Jun. 30, 1948 
Jul. 14, 1960 
Oct. 12, 1972 
(Sen. Res.) 
Oct. 12, 1972 
(House Res.) 
Mar. 3, 1905 
Jul. 25, 1912 
Sep. 22, 1922 
Mar. 2, 1945 
Rectification of certain reaches of existing Sabine Pass 
Channel, Sabine-Neches Canal, and Neches River and 
Sabine River Channel; widen to 350 feet entrance 
channel to Port Arthur turning basins; widen curve at 
junction of Port Arthur and Sabine-Neches Canals; 
relocate and enlarge Sabine Pass anchorage basin to 34 
by 1,500 by 3,000 feet; widen to 200 feet Sabine-Neches 
Canal from mouth of Neches River to mouth of Sabine 
River and Sabine River Channel to upper end of existing 
project at Orange, except for channel around Harbor 
Island at Orange; deepen to 30 feet Sabine River 
Channel from cutoff near Orange municipal slip to upper 
end of project, except around Harbor Island; and enlarge 
area at entrance to Orange municipal slip to provide a 
maneuvering basin. 
Improve outer bar channel to 42 and 40 feet for all inland 
channels to Port Arthur and Beaumont; width of 500 feet 
in Port Arthur Canal and 400 feet in Neches River 
Channel to Beaumont with three turning points in 
Neches River; a channel, 12 by 125 feet, extending in 
Sabine River to Echo; and replace an obstructive bridge 
at Port Arthur, Texas. Deauthorization of uncompleted 
portion of channel between Port Arthur west turning 
basin and Taylors Bayou turning basin and enlargement 
of entrance channel to Port Arthur turning basins. 
TEXAS CITY CHANNEL, TX 
A channel 300 by 30 feet and construct a pile dike 28,200 
feet long north to channel. 
A harbor 800 by 30 feet at Texas City, and construct a 
rubblemound dike. 
Extension of rubblemound dike to shoreline. 
Deepen channel and harbor to 32 feet. 
Deepen channel and harbor to 34 feet. 
Extend harbor 1,000 feet southward, 800 by 34 feet. 
Deepen channel and harbor to 36 feet, widen channel to 
400 feet and harbor to 1,000 feet and changing name of 
project to "TEXAS CITY CHANNEL, TEXAS?' 
Deepen channel and turning basin to 40 feet and 
construct 16-foot Industrial Barge Canal. 
Widen the existing main turning basin to 1,200 feet 
including relocation of the basin 85 feet to the east; 
providing a 40-foot deep channel in the Industrial Canal 
at widths of 300-400 feet, with a turning basin at the 
head of the canal 40 feet deep, 1,150 feet long, and 1,000 
feet wide, and easing of the bend at the entrance to the 
canal, and deauthorization of shallow-draft Industrial 
Barge Canal not incorporated in the plan of 
improvement above. 
TRINITY RIVER AND TRIBUTARIES, TX 
Anahuac Channel. 
Six-foot channel to Liberty. 
Abandon improvements above Liberty and terminate all 
improvements by lock and dam, leaving a 6-foot channel 
from Liberty to mouth. 
Provides for a navigable channel from the Houston Ship 
Channel near Red Fish Bar in Galveston and Trinity 
Bays to the mouth of Trinity River and 9 feet deep and 150 
feet wide in the river section, with a turning basin at Liberty. 
S. Doc. 80, 83rd Cong., 
2nd Sess. 
H. Doc. 553, 87th Cong., 
2nd Sess.1 
H. Doc. 1390, 62nd Cong., 
3rd Sess. 
H. Doc. 107, 71st Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 4, 
73rd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 46, 
73rd Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 62, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 47, 
75th Cong., 1st Sess. 
H. Doc. 561, 80th Cong., 
2nd Sess.1 
H. Doc. 427, 86th Cong., 
2nd Sess. 
H. Doc. 199, 92nd Cong., 
2nd Sess. 
(Sec. 201, PL 89-298) 
H. Doc. 989, 66th Cong., 
3rd. Sess. 
H. Doc. 403, 77th Cong., 
1st Sess. 
15-24 
11. 
12.

GALVESTON, TEXAS DISTRICT 
TABLE 15-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul. 24, 1946 
Oct. 23, 1962 
Oct. 27, 1965 
Jul. 30, 1983 
Dec. 15, 1970 
(House Res.) 
Dec. 17, 1970 
(Sen. Res.) 
Jul. 24, 1946 
(As amended) 
Jun. 20, 1938 
Sep. 3, 1954 
Oct. 27, 1965 
Aug. 13, 1968 
Oct. 23, 1962 
Oct. 27, 1965 
Jul. 3, 1958 
Oct. 23, 1962 
Modification of the project to provide for a channel 9 feet 
deep and 150 feet wide from the Houston Ship Channel 
near Red Fish Bar in Galveston Bay extending along 
the east shore of Trinity Bay to the mouth of the Trinity 
River at Anahuac, including protective spoil 
embankment on the bay side of the channel in lieu of the 
9 by 200-foot channel in Galveston and Trinity Bays. 
Provides for the multiple-purpose Wallisville Reservoir, 
including a navigation lock in the Wallisville Dam at 
Channel Mile 28.30 and advancement of the Channel to 
Liberty from one mile below Anahuac (Mile 23.2) to the 
Texas Gulf Sulphur Company's slip at Channel Mile 
35.8, and incorporation into existing project Anahuac 
Channel and mouth of Trinity River projects. 
Reevaluation of navigation benefits. 
Modified Wallisville Reservoir by reducing the size to 
5,600 acres and confining the reservoir to east side 
of Trinity River. 
CORPUS CHRISTI BEACH, TX 
(RESTORATION PROJECT) 
Restoration and periodic nourishment of 1.4 miles of 
beach. 
ARROYO COLORADO, RIO HONDO, TX 
Bank protection of 400 feet of east bank of Arroyo 
Colorado downstream of Farm-to-Market Road 106. 
BUFFALO BAYOU AND TRIBUTARIES, TX 
Barker and Addicks Reservoirs, Texas. 
Clearing, straightening, enlarging and lining of Buffalo 
Bayou, Brays, and White Oak Bayous. 
Extend upper limits of White Oak Bayou upstream about 
2.1 miles from BRI RR bridge to mouth of Cole Creek. 
CLEAR CREEK, TX 
Channel enlargement and rectification from upper end of Clear 
Lake at Mile 3.8 to improved channel Mile 34.8.30 
PORT ARTHUR AND VICINITY, TX 
(HURRICANE-FLOOD PROTECTION) 
Raising and reconstructing 6.3 miles of existing seawall; 
constructing 0.3 mile of new seawall, 20.3 miles new 
levees and five pumping plants; and raising and 
improving 7.5 miles of existing levees. 28 
TAYLORS BAYOU, TX 
Enlarging and rectifying channels; construction of 
diversion channel; a salt water gate; enlargement 
of GIWW 1.3 miles and alteration of State Highway 
87 bridge.29 
TEXAS CITY AND VICINITY, TX 
(HURRICANE-FLOOD PROTECTION) 
Construction of improvements for control of storm tides, 
consisting of new and enlarged levees and floodwalls 
approximately 14.1 and 2.1 miles in length; related 
drainage and stoplog structures; a navigation opening 
and pumping plants. 
VINCE AND LITTLE VINCE BAYOUS, TX 
Enlarging and rectifying channel of Vince Bayou and 
Little Vince Bayou upstream for a total of 11.5 miles 
for both streams. 
H. Doc. 634, 79th Cong., 
2nd Sess. 
H. Doc. 215, 87th Cong., 
1st Sess. 
H. Doc. 276, 89th Cong., 
1st. Sess. 
PL 98-63 
H. Doc. 415, 91st Cong., 
2nd Sess. 
(Sec. 201, PL 89-298) 
Sec. 14, PL 79-526 
H. Doc. 456, 75th Cong., 
2nd Sess. 
H. Doc. 250, 83rd Cong., 
2nd Sess.1 
H. Doc. 169, 89th Cong., 
1st Sess. 
H. Doc. 351, 90th Cong., 
2nd Sess. 
H. Doc. 505, 87th Cong., 
2nd Sess.1 
H. Doc. 206, 89th Cong., 
1st Sess.' 
H. Doc. 347, 85th Cong., 
2nd Sess.' 
H. Doc. 441, 87th Cong., 
2nd Sess.1 
15-25 
15. 
16. 
17. 
18. 
19. 
20. 
21. 
22.

TABLE 15-B 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISLATION 
1 Contains latest published maps. 
2 Extension of north jetty 1,950 feet and south jetty 1,265 
feet considered inactive 
3 Dredging 2,000 by 650-foot northerly extension of inner 
basin deauthorized. 
4 Included in Public Works Administration program 
September 6, 1933 and February 16, 1935. 
6 West leg of Wye junction with main channel deauthorized. 
6 Construction of lock in diversion dam at local expense considered 
inactive. 
' Dredging upper .5 mile of channel to vicinity of Stauffer 
Chemical plant was deauthorized under Sec. 12 of PL 93-251. 
Included in Public Works Administration program September 
6, 1933. 
8 Dredging 43rd to 51st Streets was deauthorized under Sec. 
12 of PL 93-251. 
9 Deauthorized under Sec. 12 of PL 93-251. 
10 Deepening 43rd to 57th Streets was deauthorized under 
Sec. 12 of PL 93-251 
11 Previously authorized September 6, 1933 by Public Works 
Administration. 
12 H. Doc. 230, 76th Cong., 1st Sess. and project documents 
contain latest published maps. 
13 Dredging upper 3.5 miles was deauthorized under Sec. 12 
of PL 93-251. 
14 Dredging upper 5 miles is inactive. 
15 Inactive. 
16 Portion of 16-foot by 150-foot channel from Sabine River 
to Houston Ship Channel. Relocation of channel in Matagorda 
Bay deauthorized under Sec. 12 or PL93-251. 
15-26 
17 The 9 feet by 100 feet channel from Mile 8.2 to Mile 13.2 
in Chocolate Bayou is inactive. 
18 Construction of pile dike was deauthorized under Sec. 12 
of PL 93-251. 
19 Hill Street Bridge tG mouth of White Oak Bayou was 
deauthorized under Sec. 12 of PL 93-251. 
20 Deepening channel to 40 feet from Southern Pacific Slip 
to Brady Island was deauthorized under Sec 12 of PL 93-251. 
21 The 12-foot channel from mile 1.65 to mile 2.81 deauthorized 
under Sec. 12 of PL93-251. 
22 Complete widening of channel between Port Arthur west 
turning basin and Taylors Bayou turning basin authorized by 
1962 R&H Act. 
23 Complete deepening of channel between Port Arthur west 
turning basin and Taylors Bayou turning basin deauthorized by 
1962 R&H Act. 
24 Channel extension above Cow Bayou turning basin near 
Orangefield was deauthorized under Sec. 12 of PL 93-251. 
25 Widening to 350 feet entrance channel to Port Arthur turning 
basin deauthorized by 1962 R&H Act. 
26 The 12-foot channel in Sabine River from Orange to Echo, 
Texas deauthorized under Sec. 12 of PL93-251. 
27 Jetty extension inactive. 
28 Raising and strengthening of levees surrounding Gulf Oil 
Company's fresh water reservoir is inactive. 
29 Enlarging 7.0 miles of North Fork Taylors Bayou, 7.8 miles 
of South Fork Taylors Bayou and 4.4 miles of Mayhaw Bayou 
are inactive. 
30 Portion of project upstream of Brazoria/Galveston County 
line, approximately mile 18.5, in inactive category.

GALVESTON, TEXAS DISTRICT 
OTHER AUTHORIZED NAVIGATION PROJECTS 
TABLE 15-C 
For Last Cost To September 30, 1986 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Aquatic Plant Control (1958 and 1962 River and 
Harbor Acts)6 1967 38,2521 - 
Bastrop Bayou, TX2 3 1931 9,920 27,129 
Brazos River, TX, Velasco to Old Washington3 1924 216,9894 223,010 
Cedar Bayou, TX7 1984 681,2635 2,089,3166 
Double Bayou, TX 1983 226,558 1,121,9788 
Clear Creek and Clear Lake, TX 1982 66,934 537,139 
Corpus Christi, TX, Channel to Navy Seaplane Base 
Encinal Peninsula 1968 1,194,344 26,467 
Dickinson Bayou, TX 1954 33,942 57,553 
East Bay (Hanna Reef), TX9 1922 2,476 847 
Johnson Bayou, LA10 1933 2,261 54,042 
Little Bay, TX" 1979 - 252,728 
Neches River and Trib., Salt Water Barrier 
at Beaumont, TX (Advance Engineering & Design) 1984 1,503,843 - 
Oyster Creek, TX 1922 6,942 7,556 
Sabine River and Tributaries, TX (Echo to Morgan Bluff)3 1971 - - 
1 Excludes $1,672 work contribution. 7 Mile 3 to Mile 11 deauthorized under Sec. 12 of PL 93-251. 
2 Widening from 60 feet to 100 feet at 4-foot depth was 8 In addition, $5,366 expended from contributed funds. 
deauthorized under Sec. 12 of PL 93-251. 9 In inactive category for maintenance. 
3 Inactive. 10 Channel adequate for existing commerce. 
4 Includes $123,676 for previous projects. 11 Aransas County Navigation District, Rockport, TX., con- 
6 Includes $39,087 for previous projects. In addition, $25,000 structed project as authorized by 1950 River and Harbor Act 
expended from contributed funds. (H.D. 114, 81st Cong., 1st Sess.) in 1955 under Department of 
6 Includes $69,784 for previous projects. Army permit. 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
TABLE 15-D 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Baytown, Texas1 1980 245,400 - 
Colorado River, Matagorda, Texas2 1963 273,757 - 
Freeport and Vicinity, Texas, Hurricane- 
Flood Protection2 1984 29,285,0423 - 
Guadalupe River 
(Remove Log Jams), Texas2 1978 505,749 - 
Highland Bayou, Texas2 1984 12,254,390 - 
Lavaca-Navidad River, Texas: 
Hallettsville Project 1961 256,043 - 
General channel project 1952 21,086 - 
Liberty Local Protection Project, Texas1 1971 98,517 - 
Mill Creek, Texas1 1952 24,753 - 
Peyton Creek, Texas4 1975 66,377 - 
San Diego Creek, Alice, Texas2 1963 135,175 - 
Tranquitas Creek, Kingsville, Texas2 1956 130,239 - 
Three Rivers, Texas5 
6 5,835,927 - 
1 Inactive. 
2 Completed. 
In addition, $8,695,438 expended from contributed funds, $1,126,905 estimated value of contributed lands, and $2,726,446 
for relocations by local interests. 
4 Deauthorized under Sec. 12 of PL 93-251. 
5 See Annual Report for 1983, Fort Worth District, page 16-12. 
15-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TOTAL COST OF EXISTING PROJECTS TO SEPTEMBER 30, 1986 
TABLE 15-E 
See 
Section 
in Text Project Funds New Work Maintenance Rehabilitation Total 
2. Brazos Island Harbor, TX 
3. Corpus Christi Ship 
Channel, TX 
4. Freeport Harbor, TX 
5. Galveston Harbor and 
Channel, TX 
6. Gulf Intracoastal Waterway 
between Apalachee Bay, FL 
and the Mexican Border 
(Galveston District) 
7. Houston Ship Channel, TX 
9. Sabine-Neches Waterway, TX 
10. Texas City Channel, Tx 
11. Trinity River and 
Tributaries, TX 
Regular 
Public Works 
Contributed 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Total cost of project 
Regular 
Channel 
Seawall 
Public Works 
Contributed 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public Works 
Contributed 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public Works 
Contributed 
Total cost of project 
Regular 
Contributed 
Total cost of project 
$ 8,333,087 
2,848,560 
1,683,258 
12,864,905 
55,889,783 
324,287 
3,331,615 
59,545,685 
1,716,695 
276,720 
61,539,100 
2,739,385 
116,575 
758,303 
3,614,263 
360,249 
3,974,512 
11,920,187 
8,754,209 
3,648,932 
24,323,328 
59,967,330 
466,477 
3,477,525 
63,911,332 
395,000 
139,776 
64,446,108 
29,042,293 
2,612,932 
1,382,760 
33,037,985 
49,592,331 
1,363,652 
2,103,435 
53,059,418 
32,000 
116,760 
53,208,178 
12,822,353 
136,296 
1,023,819 
13,982,468 
27,074,974 
66,000 
27,140,974 
$ 35,653,853 
14,692 
35,668,545 
83,169,878 
445,269 
83,615,147 
83,615,147 
42,236,458
-_ 
229,311 
42,465,769 
42,465,769 
75,191,435 
512,163 
13,121 
2,098,600 
77,815,319 
193,277,774 
22,672 
193,300,446 
193,300,446 
96,896,956 
163,360 
97,060,316 
127,490,069 
2,636,582 
130,126,651 
130,126,651 
21,013,109 
21,013,109 
9,213,014 
9,213,014 
$ 2,17 
2,17 
3,57 
3,57 
3,57
0,080 $ 46,157,020 
- 2,848,560 
- 1,697,950 
70,080 50,703,530 
76,684 142,636,345 
- 324,287 
- 3,776,884 
76,684 146,737,516 
- 1,716,695 
- 276,720 
76,684 148,730,931 
8,935 44,984,778 
- 116,575 
- 987,614 
8,935 46,088,967 
- 360,249 
8,935 46,449,216 
7,373,356 94,484,978 
595,973 9,862,345 
- 13,121 
- 5,747,532 
7,969,329 110,107,976 
1,270,511 254,515,615 
- 466,477 
- 3,500,197 
1,270,511 258,482,289 
- 395,000 
- 139,776 
1,270,511 259,017,065 
- 125,939,249 
- 2,612,932 
- 1,546,120 
- 130,098,301 
- 177,082,400 
- 1,363,652 
- 4,740,017 
183,186,069 
726,158 
726,158 
32,000 
116,760 
183,334,829 
34,561,620 
136,296 
1,023,819 
35,721,735 
36,287,988 
66,000 
36,353,988 
15-28

GALVESTON, TEXAS DISTRICT 
CHANNEL DIMENSIONS 
Adopted Project Dimensions Improved Project Dimensions 
See Depth in Feet Bottom Depth in Feet Bottom 
Section (Below Mean Width (Below Mean Width Length 
in Text Project Section of Waterway Low Tide) (Feet) Low Tide) (Feet) Feet Miles 
2. Brazos Island 
Harbor, TX 
4. Corpus Christi 
Ship Channel, 
TX 
5. Freeport 
Harbor, Tx 
6. Galveston 
Harbor and 
Channel, TX 
Outer Bar and Jetty Channel 
Padre Island to Long Island 
Long Island to Goose Island 
Goose Island to Turning Basin 
Extension 
Turning Basin Extension 
Brownsville Turning Basin 
Port Isabel Channel via East 
Turnout 
West Wye, from Brownsville 
Channel 
Port Isabel Turning Basin 
Fishing Boat Harbor: 
West Basin 
Middle Basin 
East Basin 
Connecting Channel 
Entrance Channel 
Aransas Pass Outer Bar 
Channel 
Aransas Pass Jetty Channel 
Inner Basin at Harbor Island 
Channel to Port Aransas 
Port Aransas Turning Basin 
Anchorage Basin at Port 
Aransas 
Inner Basin to Mile 8.5 
Mile 8.5 to LaQuinta Junction 
LaQuinta Junction to Corpus 
Christi Turning Basin 
Corpus Christi Turning Basin 
Industrial Canal 
Avery Point Turning Basin 
Channel to Chemical Turning 
Basin 
Chemical Turning Basin 
Tule Lake Channel 
Tule Lake Turning Basin 
Viola Channel 
Viola Turning Basin 
Channel to LaQuinta 
LaQuinta Turning Basin 
Turning Point at LaQuinta 
Channel Junction 
Jewel Fulton Canal 
Jewel Fulton Turning Basin 
Mooring Area at Ingleside: 
Mooring Area (a) 
Mooring Area (b) 
Outer Bar Channel 
Jetty Channel 
Quintana Turning Basin 
Channel to Brazosport 
Turning Basin 
Brazosport Turning Basin 
Channel to Upper Turning 
Basin 
Upper Turning Basin 
Channel to Stauffer Chemical 
Plant 
Stauffer Turning Basin 
Brazos Harbor Channel 
Brazos Harbor Turning Basin 
Entrance Channel 
Outer Bar Channel 
Inner Bar Channel 
Anchorage Basin 
Bolivar Roads Channel 
TABLE 15-F 
38-36 
36 
36 
36 
36 
36 
36 
36 
36 
15 
15 
15 
15 
15 
47 
45 
45 
12 
12 
12 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
12 
12 
45 
45 
47 
45 
45 
45 
45 
45 
45 
30 
30 
36 
36 
42 
42 
40 
36 
40 
300 
200 
200 
300 
500 
1,000 
200 
200 
1,000 
370-305 
370-305 
370 
270 
100 
700 
600-730 
730-1,720 
100-150 
200-4002 
300-400 
600-500 
500 
400 
800 
400 
975 
400 
1,200 s 
300 
1,200 
300-350 
1,200 
300-400 
1,200 
1,2503 
100 
200 
150 
150 
400 
400 
750' 
400 
1,000' 
375 
1,200' 
200 
500 
200 
7504 
800 
800 
800 
2,8751 
800 
38-36 
36 
36 
36 
36 
36 
36 
36 
36 
15 
15 
15 
15 
15 
47 
45 
45 
12 
12 
12 
45 
45 
40-45 
40 
40 
40 
40 
40 
40 
40 
40 
40 
45 
45 
45 
12 
12 
45 
38 
36 
36 
36 
36 
36 
30 
25 
30 
30 
42 
42 
40 
36 
40 
300 
200 
200 
200 
500 
1,000 
200 
200 
1,000 
370-305 
370-305 
370 
265 
100 
700 
600 
Irregular 
100 
2002 
300-400 
600-500 
500 
400 
1,000 
400 
1,000 
350 
1,0505 
200 
900 
200-250 
700-900 
300-400 
1,200 
1,2503 
100 
200 
150 
300 
200 
200-350 
744-800 
350-375 
600 
200 
500 
200 
525-675 
800 
800 
800 
2,875 
800 
2.5 
2.1 
9.6 
3.2 
1.3 
2,670 0.5 
1.4 
0.8 
1,300 0.2 
1,470 0.3 
1,200 0.2 
1,470 .03 
1,230 0.2 
770 0.1 
1.8 
1.0 
1,550 - 
0.1 
200 - 
900 0.2 
8.5 
3.6 
8.6 
5,423 1.0 
1.1 
1,150 0.2 
0.6 
1,690 0.3 
3.1 
1,000 0.2 
1.8 
1,000 0.2 
5.6 
800 0.1 
1,250 0.2 
- 0.8 
400 0.1 
- 0.8 
- 3.0 
- 0.8 
- 1.2 
667 0.1 
- 1.4 
600 0.1 
- 1.1 
500 0.1 
- 0.5 
675 0.1 
- 4.7 
- 1.7 
- 3.2 
- 1.81 
- 1.0 
15-29

TABLE 15-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
CHANNEL DIMENSIONS 
Adopted Project Dimensions Improved Project Dimensions 
See Depth in Feet Bottom Depth in Feet Bottom 
Section (Below Mean Width (Below Mean Width Length 
in Text Project Section of Waterway Low Tide) (Feet) Low Tide) (Feet) Feet Miles 
Galveston 
Harbor and 
Channel, TX 
(cont'd) 
Bolivar Roads Channel 
to 43rd St. 
8. Houston Ship Bolivar Roads to Morgan Point 
Channel, TX Morgan Point to Boggy Bayou 
Boggy Bayou to Greens Bayou 
Greens Bayou to Sims Bayou 
Hunting Bayou Turning 
Point 
Clinton Island Turning Basin 
Sims Bayou to Southern 
Pacific Slip 
Southern Pacific Slip to 
Houston Turning Basin 
Houston Turning Basin 
Upper Turning Basin 
Brady Island Channel 
Barbour Terminal Channel 
Turning Basin 
Five-Mile Cut Channel 
Light-Draft Channel: 
Upper Turning Basin to 
Jensen Drive 
Turkey Bend Channel 
Greens Bayou Channel: 
Mile 0 to Mile 0.36 
Mile 0.36 to Mile 1.57 
9. Matagorda Ship Outer Bar and Jetty Channel 
Channel, TX Channel to Point Comfort 
Approach Channel to Turning 
Basin 
Turning Basin 
Channel to Port Lavaca 
Lynn Bayou Turning Basin 
Channel to Harbor of Refuge 
North-South Basin 
East-West Basin 
Channel to Red Bluff 
10. Sabine-Neches Sabine Bank Channel 
Waterway, TX Sabine Pass Outer Bar 
Channel 
Sabine Pass Jetty Channel 
Sabine Pass Anchorage Basin 
Sabine Pass Channel 
Port Arthur Canal 
Entrance to Port Arthur 
Turning Basins 
Port Arthur East Turning 
Basin 
Port Arthur West Turning 
Basin 
Channel connecting Port 
Arthur West Turning Basin 
and Taylors Bayou Turning 
Basin 
Taylors Bayou Turning Basin 
Sabine-Neches Canal, Port 
Arthur Canal to Neches River 
Turning Point at Mile 19.5 
Neches River, Mouth to 
Maneuvering Area at 
Beaumont Turning Basin 
Turning Point, Mile 31.1 
Turning Point, Mile 36.6 
Turning Point, Mile 40.3 
Channel Extension, 
Mile 40.3 
40 
40 
40 
40 
40 
40 
40 
40 
36 
36 
36 
10 
16 
16
8 
10 
10 
36 
15 
38 
36 
36 
36 
12 
12 
12 
12 
12
6 
42 
42 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
36 
1,125 
400 
400 
300 
300 
900-1,0009 
8009 
300 
300 
400-1,000 
150 
60 
100 
1,100 
125 
60 
60 
175 
100 
300 
300-2006 
200-300 
1,000 
125 
27-340 
125 
300 
250 
100 
800 
800 
800-500 
1,500 
500 
500 
275-678 
420 
600 
40 1,125 
40 
40 
40 
40 
40 
40 
40 
36 
36 
36 
10 
16 
16
8 
10 
10 
36 
15 
38 
36 
36 
36 
12 
12 
12 
12 
12
6 
42 
42 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
36 
200-250 
150-1,000 
400 
9004 
400 
1,0004 
1,0004 
1,0004 
350 
400 
400 
300 
300 
948-1,0009 
965-1,0709 
300 
300 
400-1,000 
150 
60 
100 
1,100 
125 
60 
60 
175 
100 
300 
300-2006 
200-300 
1,000 
125 
27-340 
125 
300 
250 
100 
800 
800 
800-500 
1,500 
500 
500 
275-678 
370-547 
350-550 
200-250 
90-1,233 
400 
9004 
400 
1,000 
1,000 
1,300 
350 
15-30 
3.9 
- 26.2 
- 12.8 
- 2.4 
- 5.3 
1,375 - 
1,592 - 
- 0.6 
- 2.9 
3,100 0.6 
1,000 0.2 
- 0.9 
- 1.5 
1,000 0.2 
- 1.9 
- 4.1 
- 0.8 
- 0.3 
- 1.3 
- 3.2 
- 20.9 
- 1.1 
1,000 0.2 
- 4.1 
532 0.1 
- 1.9 
1,682 0.3 
1,750 0.3 
- 20.2 
- 14.7 
3,000 
3.4 
4.1 
- 
5.6 
6.2 
- 0.3 
1,765 0.3 
1,610 0.3 
- 0.6 
3,470 0.7 
- 11.2 
- 8 
- 18.3 
700 8 
930 8 
1,530 8 
1,265 0.2

GALVESTON, TEXAS DISTRICT 
TABLE 15-F CHANNEL DIMENSIONS 
Adopted Project Dimensions Improved Project Dimensions 
See Depth in Feet Bottom Depth in Feet Bottom 
Section (Below Mean Width (Below Mean Width Length 
in Text Project Section of Waterway Low Tide) (Feet) Low Tide) (Feet) Feet Miles 
Sabine-Neches Maneuvering Area at 
Waterway, Beaumont Turning Basin 40 Irregular 40 Irregular 1,300 0.2 
TX (cont) Beaumont Turning Basin 34 500 34 160-535 1,500 0.3 
Beaumont Turning Basin 
Extension 34 350 34 300 - 0.4 
Beaumont Turning Basin 
Extension to End of Project 
Channel Vicinity 
Bethlehem Steel Company 30 200 30 200 - 0.7 
Sabine-Neches Canal, Neches 
River to Sabine River 30 200 30 200 - 4.4 
Sabine River Channel, Mouth 
to Foot of Green Ave. 30 200 30 200 - 9.5 
Orange Turning Basin 30 Irregular 30 Irregular 1,550 0.3 
Orange Municipal Slip 30 200 30 150-200 2,435 0.5 
Old Channel Around Harbor 
Island 25 150-200 25 150-200 - 2.4 
Channel to Echo7 12 125 - - - - 
Adams Bayou 12 100 12 100 - 1.7 
Cow Bayou 13 100 13 100 - 7.0 
Orangefield Turning Basin 13 300 13 300 500 0.1 
1 Average. 
2 Includes 100-foot channel width. 
3 Includes 450-foot channel to Corpus Christi. 
4 Diameter. 
5 Includes 350-foot channel width. 
6 300-foot width through Matagorda Peninsula. 
' Deauthorized. 
8 Included in channel length. 
9 Includes 300-foot channel width. 
15-31

TABLE 15-G 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
GULF INTRACOASTAL WATERWAY 
APALACHEE BAY, FLORIDA TO MEXICAN BORDER 
EXISTING PROJECT DIMENSIONS, PROVIDED 
FOR IN TRIBUTARY CHANNELS 
Authorized Improved 
Project Dimensions Project Dimensions 
Depth Depth 
(Feet Below Bottom (Feet Below Bottom 
Mean Width Mean Width Length 
Tributary Channel Low Tide) (Feet) Low Tide) (Feet) Miles Feet 
Offats Bayou 
Main Channel 
West Wye 
Chocolate Bayou Channel 
12-Foot Channel via East 
Turnout 
West Turnout 
9-Foot Channel 
Turning Basin 
San Bernard River Channel 
Colorado River Channel 
Turning Basin 
Silting Basin 
Mouth of Colorado River 
Navigation Channel, GIWW 
to Gulf 
Turning Basin at Matagorda 
Channel to Palacios 
Turning Basin No. 1 
Turning Basin No. 2 
Connecting Channel 
Channel to Barroom Bay 
Channel to Victoria 
Main Channel via east 
Turnout 
Turning Basin 
West Turnout Channel 
Channel to Seadrift via South 
Turnout 
Turning Basin 
North Turnout from Channel to 
Victoria 
Harbor of Refuge at Seadrift 
Channel 
Basin 
Channel to Rockport 
Turning Basin 
Channel to Aransas Pass 
Turning Basin 
Channel to Conn Brown Harbor 
Conn Brown Harbor 
Channel to Port Mansfield 
Entrance Channel 
Approach Channel to Hopper 
Dredge Turning Basin 
Hopper Dredge Turning Basin 
Channel Across Padre Island 
and Laguna Madre 
Turnout Channels, East Side of 
Main Channel, GIWW 
North Turnout 
South Turnout 
Channel West Side of Main 
Channel, GIWW, to PT. of 
Turnout Channels 
Turnout Channels, West Side of 
Main Channel, GIWW 
North Turnout 
South Turnout 
12 
12 
12 
12
99 
9
999 
15-12 
12 
8 12 
12 
12 
12 
9 6
999 
9
9
9
99
99 
14 
14 
14 
14 
10 
16 
16 
16 
14 
12 
12 
14 
12 
12 
125 
125 
125 
125 
100 
600 
100 
100 
400 
150 
200-100 
350 
125 
200 
300 
150-480 
60 
100 
600(avg) 
100 
100 
250 
100 
100 
200 
200 
475 
175 
300 
125 
300 
250 
100 
300 
100 
100 
100 
100 
200 
200 
2,200 
500 
635 
1,130 
800(avg) 
230 
12 
12 
12 
12
9
999 
12 
12 
12 
12
999 
99 
9
9 
14 
14 
14 
14 
2613 
2613 
2613 
26's 
14 
12 
12 
14 
12 
12 
125 
125 
125 
125 
100 
100 
400 
150 
125 
200 
300 
130-400 
100 
500(avg) 
100 
100 
200 
100 
200 
342(avg) 
125-175 
300 
125 
300 
250 
100 
300 
100 
100 
100 
100 
200 
200 
-
- 
1,225 
2,212 
1,800 
300 
2.3 
0.4 
8.2 
0.8 
26.0 
15.5 
0.1 
1.0 
16.1 
0.1 
0.2 
0.1 
34.8 
0.1 
0.8 
2.0 
0.5 
2.1 
0.2 
6.1 
0.4 
0.2 
0.3 
0.8 
0.4 
0.1 
7.7 
0.6 
0.6 
0.3 
0.6 
0.6 
15-32

TABLE 15-G 
GALVESTON, TEXAS DISTRICT 
GULF INTRACOASTAL WATERWAY 
APALACHEE BAY, FLORIDA TO MEXICAN BORDER 
EXISTING PROJECT DIMENSIONS, PROVIDED 
FOR IN TRIBUTARY CHANNELS 
Authorized Improved 
Project Dimensions Project Dimensions 
Depth Depth 
(Feet Below Bottom (Feet Below Bottom 
Mean Width Mean Width Length 
Tributary Channel Low Tide) (Feet) Low Tide) (Feet) Miles Feet 
Channel from PT. of Turnout 
Channels to Approach Channel 
to Main Turning Basin 
Approach Channel to Main 
Turning Basin 
Main Turning Basin 
Turning Basin Extension 
Small Craft Basin 
Shrimp Basin 
Channel to Harlingen via South 
Turnout from Main 
Channel, GIWW 
Turning Basin near Rio Hondo 
North Turnout from Main 
Channel 
Port Isabel Side Channels 
Main Channel 
Main Channel 
South Leg 
Port Isabel Small Boat Harbor 
Entrance Channel 
Harbor Channel 
Boat Basin 
14 
14 
14 
14
8 
12 
12 
12 
12 
12 
12 
12
766 
125 
200 
400 
1,000 
160 
350 
125 
400 
200 
125 
233-60 
125 
75 
50 
Variable 
14 
14 
14 
14
8 
12 
12 
12 
12 
12 
12 
12
766 
125 
200 
400 
1,000 
160 
350 
12511 
400 
200 
125-90 
233-60 
125 
75 
50 
72-501 
0.6 
0.3 
0.2 
0.1 
0.2 
0.3 
25.812 
0.1 
0.7 
0.6 
0.4 
0.2 
1.4 
0.3 
0.2 
1,250 
580 
860 
1,450 
500 
1,308 
- 
1,308 
1 Includes the construction of a salt water barrier at 
Mile 16.9. 
2 Constructed 10 feet deep by 100 feet wide by local interests. 
East turnout channel constructed 150 feet wide. 
3 Constructed by local interests. 
4 Authorized to mile 13.2. Mile 8.2 to Mile 13.2 is in inactive 
category. 
6 Authorized to Mile 31 above mouth (channel mile 
29.41). Upper 3.4 miles was deauthorized under Section 12 
of PL 93-251. 
6 Includes a discharge channel from Matagorda, Texas, 
to the gulf which was dredged by local interests in 1939. 
(Maintenance will be discontinued upon completion of improvements 
authorized by R&H Act of 1968.) 
' Authorized by R&H Act of 1968. Also provides for a 
dam across the present discharge channel, a new 250-foot 
wide by 20 to 23-feet deep discharge channel into Matagorda 
Bay, and a 15-foot by 200-foot wide entrance channel 
with parallel jetties from the gulf shoreline into the Gulf of 
Mexico. East jetty to be 3,500 feet long and west jetty 2,900 
feet long. 
8 Includes two protective breakwaters at entrance to turning 
basins. 
9 In the inactive category for maintenance. 
10 Also provides for two stone jetties at the gulf entrance 
about 1,000 feet apart. (North jetty constructed 2,300 feet 
long and south jetty constructed 2,270 feet long.) 
1 South turnout is 200 feet wide. 
12 Authorized to mile 31. Mile 25.8 to Mile 31 is in inactive 
category. 
15-33

TABLE 15-H 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
DREDGING OPERATIONS 
See 
Section 
in Text Project 
Brazos Island Harbor, TX 
(Maintenance)

Dredging jetty channel

April 4 to 
September 30 1986

333,692 

$329,869

Channel to Port Bolivar, TX 
(Maintenance)

Dredging channel to Port Bolivar 

October 1 to 
November 22, 1985

79,518 

$48,911

Corpus Christi Ship Channel, 
TX (New Work) 

Dredging Beacon 82 thru 
Chemical Turning Basin 

October 1, 1985 to 
April 22, 1986 

3,524,482 

$3,153,217

Corpus Christi Ship Channel, 
TX (Maintenance) 

Dredging Entrance Channel 
(Hopper Dredge WHEELER)

July 8 to 
August 2, 1986

1,340,540 

$2,695,000 

Dredging Channel to La Quinta 
and Basin and Jewel Fulton 
Canal and Basin 

October 1 to 
October 14, 1985 

1,357,371

$565,021


Freeport Harbor, TX 
(Maintenance)

Dredging Outer Bar and Jetty 
Channels 

July 13 to 
August 18, 1986 

925,709 

$568,425 
 
Galveston Harbor and 
Channel, TX 
(Maintenance)

Dredging Entrance Channel 

May 18 to 
July 31, 1986 

2,212,568 

$1,226,912

Dredging Bolivar Roads to Ferry 
Landing 

September 8 to 
September 30, 1986

591,105 

$479,470 
 
Gulf Intracoastal Waterway 
between Apalachee Bay, 
FL, and Mexican Border 
(Galveston District) 
(Maintenance) 

Dredging High Island to Port 
Bolivar 

October 1 to 
November 22, 1985

83,179

$188,390 

Dredging Main Channel near 
Caney Creek

December 13, 1985 to 
March 6, 1986 

117,776 

$127,298 

Dredging Port Mansfield to Mud 
Flats, Port Isabel Small Boat 
Harbor Entrance Channel 

February 5 to 
May 15, 1986

2,066,946 

$1,011,457 

Dredging Cedar Lakes to Colorado 
River 

February 26 to 
September 13, 1986 

2,162,700 

$2,488,959

Dredging Channel to Port 
Mansfield 

April 4 to 
May 14, 1986 

104,196 
$120,596

Dredging Channel to Victoria 
and Channel to Seadrift 

April 5 to 
September 39, 1986 

1,070,640 

$574,469

Dredging Matagorda Bay to San 
Antonio Bay 

May 18 to 
September 30, 1986 

458,135 

$893,995 

Dredging Texas City Junction to 
Galveston Causeway 

August 18 to 
September 30, 1986 

270,147 

$500,000

Dredging Turnstake Island to 
Live Oak Point 

May 14 to 
September 11, 1986

2,259,725 

$1,083,274 

Dredging Channel to Palacios 

June 23 to 
September 15, 1986 

2,070,128 

$675,337

Dredging Freeport Harbor to 
Cedar Lakes and San Bernard 
River Channel

July 20 to 
September 30, 1986 

212,333 

$500,000 
 
Dredging Main Channel in 
Matagorda Bay

January 6 to 
September 30, 1986

104,335 

$155,302 

Houston Ship Channel, TX 
(Maintenance)
  
Dredging Carpenters Bayou to 
Greens Bayou 

May 14 to 
September 15, 1986

607,330 

$1,617,830 

Dredging Red Fish Reef to 
Morgan Point and 5-Mile Cut 

September 3 to 
September 30, 1986

187,500 
$200,000
 

15-34 
-- 


GALVESTON, TEXAS DISTRICT 
TABLE 15-H DREDGING OPERATIONS 

Matagorda Ship Channel, 
TX (Maintenance) 

Dredging Matagorda Peninsula to 
Point Comfort 

January 6 to September 30, 1986

6,363,703 

$2,837,860 
 
Sabine-Neches Waterway, 
TX (Maintenance) 

Dredging Port Arthur Turning 
Basin and Junction Area, Port 
Arthur and Sabine Neches 
Canals 

October 1 to November 6, 1986 

1,225,178 

622,781 

Dredging channel around Harbor 
Island 

October 8 to November 21, 1985 

214,000 

$335,460 

Dredging Sabine Neches Canal 
and Lower Reach Neches River 
Channel 

January 15 to June 12, 1986 

2,884,479 

$1,447,595 

Dredging Sabine Pass Outer Bar 
and Sabine Bank Channel 

May 12 to July 13, 1986 

5,626,837 

$1,685,485 

12. Trinity River and 
Tributaries, TX 
(Maintenance) 

Dredging Anahuac Channel and 
Channel to Liberty 

October 1, 1985, to September 30, 1986 

808,500 

$1,663,220 


15-35

FORT WORTH, TX, DISTRICT * 
District includes that portion of Texas south of Red 
River drainage basin exclusive of drainage basin of Rio 
Grande and its tributaries above and including Pecos 
River; exclusive of drainage basins to all short streams 
arising in coastal plain of Texas and flowing into the Gulf 
of Mexico, including entire basins of Buffalo Bayou, San 
Jacinto, San Bernard, Lavaca, Navidad, Mission, and 
Arkansas Rivers; exclusive of lower basins of major 
streams flowing into the gulf as follows: Sabine River, 
Texas and Louisiana, downstream from U.S. Highway 190 
crossing at Bon Wier, Texas; Neches River downstream 
from Town Bluff gaging station; Trinity River 
downstream from Texas State Highway 45 crossing at 
Riverside, Texas; Brazos River downstream from confluence 
with Navasota River; Colorado River downstream 
from gaging station at Austin; Guadalupe River 
downstream from confluence with San Marcos River; San 
Antonio River downstream from confluence with Escondido 
Creek; Nueces River downstream from confluence 
with Frio and Atascosa Rivers; and exclusive of Agua 
Dulce, San Fernando, and Olmos Creek basins draining 
into Baffin Bay; coastal area south thereof to Rio Grande 
and south to the northern boundaries of Newton, Jasper, 
Tyler, Polk, Trinity, Walker, Waller, Austin, Fayette, Gonzales, 
Karnes, Live Oak, Jim Hogg, Zapata; the northern 
and western boundaries of McMullan; and the western 
boundaries of Montgomery and Duval Counties, Texas. 
District also includes those portions of the Sulphur River 
and Cypress Creek Watershed located in the State of 
Texas; that portion of western Louisiana in Sabine River 
drainage basin upstream from U.S. Highway 190 crossing 
at Bon Wier, Texas. 
IMPROVEMENTS 
Navigation 
1. Trinity River Project, TX ............... 
Flood Control 
2. Aquilla Lake, TX ...................... 
3. Bardwell Lake, TX ..................... 
4. Belton Lake, TX ....................... 
5. Benbrook Lake, TX .................... 
6. Big Sandy Lake, TX .................. 
7. Boggy Creek, TX ..................... 
8. Canyon Lake, TX ...................... 
9. Cooper Lake and Channels, TX .......... 
10. Elm Fork Floodway, TX ............... 
11. Ferrells Bridge Dam-Lake O'The Pines, TX 
12. Grand Prairie, TX (Landfill) ............. 
13. Grand Prairie, TX (Meyers Road) ......... 
14. Grapevine Lake, TX ................... 
15. Hords Creek Lake, TX .................. 
16. Joe Pool Lake, TX .................... 
17. Lavon Lake, TX ....................... 
18. Lavon Lake Modification and East Fort 
Channel Improvement, TX .............. 
19. Lewisville Dam, TX .................... 
20. Millican Lake, TX .................... 
21. Navarro Mills Lake, TX ................ 
22. O. C. Fisher Dam and Lake, TX .......... 
23. Proctor Lake, TX ...................... 
24. Ray Roberts Lake, TX ................. 
25. San Antonio Channel Improvement, TX ... 
26. San Gabriel River, TX .................. 
27. Somerville Lake, TX ................... 
28. Stillhouse Hollow Dam, TX ............. 
29. Waco Lake, TX ....................... 
Page Flood Control (cont) Page 
16-2 30. Wright Patman Dam and Lake, TX ....... .16-11 
31. Inspection of Completed Flood Control 
Projects ............................. 16-12 
16-2 32. Scheduling Flood Control Reservoir 
16-3 Operations ........................... 16-12 
16-3 33. Other Authorized Flood Control Projects ... 16-12 
16-3 34. Flood Control Work Under Special 
16-3 Authorization ........................ 16-12 
16-4 
16-4 
16-4 
16-5 
16-5 
16-6 
16-6 
16-6 
16-7 
16-7 
16-8 
16-8 
16-8 
16-9 
16-9 
16-9 
16-9 
16-9 
16-10 
16-10 
16-11 
16-11 
16-11 
Multiple-Purpose Projects Including Power 
35. Belton Lake Modification, TX ........... 
36. Dam "A" Lake, TX .................... 
37. Rockland Lake, TX .................... 
38. Sam Rayburn Dam and Reservoir, TX ..... 
39. Town Bluff Dam-B .A. Steinhagen Lake, TX 
40. Town Bluff Hydropower, TX ............ 
41. Whitney Lake, TX .................... 
16-12 
16-12 
16-13 
16-13 
16-13 
16-13 
16-13 
Tables 
Table 16-A 
Table 16-B 
Table 16-C 
Table 16-D 
Table 16-E 
Cost and Financial Statement .... 
Authorizing Legislation ......... 
Other Authorized Flood Control 
Projects ....................... 
Inspection of Completed Flood 
Control Projects ............... 
Flood Control Work Under 
Special Authorization ........... 
16-15 
16-19 
16-22 
16-22 
16-23 
16-1
General Investigations 
42. Surveys ............................. 16-14 
43. Collection and Study of Basic Data ....... .16-14

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. TRINITY RIVER PROJECT, TX 
The project authorized by the River and Harbor Act of 
1965 (H. Doc 276, 89th Cong., 1st Sess.) consists of five 
major components: Multiple-Purpose Channel, Tennessee 
Colony Lake, Dallas Floodway Extension, West Fork 
Floodway, and Water Conveyance Facilities. For the last 
full report on the project as authorized, see Annual Report 
of 1978. The project information present herein is based 
on the tentatively selected project plan presented in the 
Draft General Design Memorandum. The plan consists 
of three structural components: Dallas Floodway Extension, 
Tennessee Colony Lake, and Channel to Liberty in 
the lower basin. The estimated cost of the improvements 
is $1,219,400,000 including $98,400,000 non-Federal cost 
for land acquisition and relocation required for the local 
protection features (Oct. 1, 1986, base price). 
Operations during fiscal year. Preconstruction planning 
continued. 
CHANNEL TO LIBERTY: 
Location. The Channel to Liberty begins at the 
Houston Ship Channel, crosses the bay area in an easterly 
direction to intersect the existing Double Bayou Channel 
turns northward along the coastline to Wallisville Lake 
and then continues northward through the lake area 
along the course of the Trinity River to RM 45 above 
Liberty, Texas. 
Existing project. The navigation portion of the channel 
will have a width of 200 feet with a depth of 12 feet 
and will extend from the Houston Ship Channel in 
Galveston Bay to the port of Liberty, Texas. The flood control 
portion of the channel will have a bottom width of 
200 feet with a depth of 30 feet, and will extend from 
Wallisville Lake to RM 45 above Liberty, Texas. Estimated 
Federal cost of the improvements is $140,000,000 and 
estimated non-Federal cost is $35,400,000 for a total 
estimated cost of $175,400,000 (Oct. 1, 1986, base price). 
Local cooperation. Local interests are required to: (a) 
provide, without cost to the Federal Government, all lands, 
easements and rights-of-way required for construction, 
operation and maintenance of the project, (b) accomplish, 
without cost to the Federal Government, all relocations 
and alterations to existing improvements, other than 
highway bridges over new land cuts and railroad bridges 
required for the construction of the project, (c) maintain 
and operate the flood control portion of the channel 
upstream of Liberty, Texas, and (d) reimburse the Federal 
Government for one-half of the separable costs allocated 
to recreation and fish and wildlife enhancement. This 
reimbursement is presently estimated at $252,000, exclusive 
of interest. 
TENNESSEE COLONY LAKE: 
Location. The Tennessee Colony dam site is located at 
River Mile 341.7 on the Trinity River about 22 miles west 
of Palestine, Texas. The lake would extend into Freestone, 
Anderson, Henderson, and Navarro Counties, and would 
control a drainage area of 12,302 square miles. 
Existing project. The plan of improvement provides for 
the construction of an earthfilled dam with a maximum 
height of 123 feet above the streambed and a total embankment 
length of 42,350 feet with a gated concrete 
spillway. The lake will have a total controlled storage of 
3,455,000 acre-feet and a water surface area of 114,400 
acres at the top of the flood control pool and 68,100 acres 
at the top of the conservation pool. The total storage includes 
2,269,500 acre-feet for flood control, 1,040,000 acrefeet 
for conservation, and 145,500 acre-feet for sediment 
reserve. Estimated Federal cost of the improvement is 
$913,000,000 (Oct. 1, 1983, base price). 
Local cooperation. Local interests are required to 
reimburse the Federal Government for costs allocated to 
water supply storage and one-half of the separable cost 
allocated to recreation and fish and wildlife enhancement. 
This reimbursement is presently estimated at 
$461,754,000 for water supply and $9,533,000 for recreation 
(excluding future recreation facilities), for a total cost 
of $471,287,000, exclusive of interest. 
DALLAS FLOODWAY EXTENSION: 
Location. Dallas Floodway Extension is located on the 
Trinity River in the City of Dallas, Dallas County, Texas. 
Existing project. The plan of improvement provides for 
extending the existing Floodway downstream about 9 
miles to the confluence of the Trinity River and Five Mile 
Creek. The plan consists of a leveed floodway and flood 
conveyance improvement (channel) along the main stem, 
Five Mile Creek and White Rock Creek. Maintained free 
of encroachments, the levees and channels would provide 
Standard Project Flood protection for approximately 7,300 
acres of urban lands currently subject to flooding. The 
estimated Federal cost is $68,000,000 and estimated non- 
Federal cost is $63,000,000 for a total estimated cost of 
$131,000,000 for the improvement (Oct. 1, 1983, base 
price). 
Local cooperation. Local interests are required to: (a) 
provide, without cost to the Federal Government, all lands, 
easements and rights-of-way necessary for construction, 
maintenance and operation of the project, (b) accomplish, 
without cost to the Federal Government, all alterations 
to existing improvements, other than railroad bridges required 
for the construction of the project, (c) maintain and 
operate the project after completion, and (d) reimburse the 
Federal Government for one-half of the separable costs 
allocated to recreation and fish and wildlife enhancement. 
This reimbursement is presently estimated at $1,878,000 
(excluding future recreation) exclusive of interest. 
Flood Control 
2. AQUILLA LAKE, TX 
Location. On Aquilla Creek in Hill County, Texas, with 
the dam at River Mile 23.3, about 6.8 miles southwest of 
Hillsboro, Texas, and about 24.0 miles north of Waco, 
Texas. 
16-2

FORT WORTH, TEXAS DISTRICT 
Existing project. For description of completed improvements 
and authorizing Acts see Annual Report for 
1984. Construction was started March 1977, and project 
was ready for beneficial use April 29, 1983. Estimated cost 
is $46,100,000. 
Local cooperation. The Water Supply Act of 1958, as 
amended, and the Federal Water Project Recreation Act 
of 1965 and Section 221, Flood Control Act of 1970 apply. 
A contract with the Brazos River Authority for water 
supply storage was approved by the Secretary of the Army, 
June 29, 1976. To date, the Authority has paid $72,395 
toward principal and $8,314 to operation and 
maintenance. 
Benefits accrued to Aquilla project: Accumulated flood 
damages prevented through FY 1986 were $561,000. 
Operations during fiscal year. Routine operation and 
maintenance continue. 
3. BARDWELL LAKE, TX 
Location. Dam is on Waxahachie Creek, 5 river miles 
upstream from its confluence with Chambers Creek, a 
tributary of the Trinity River, and about 5 miles south 
of Ennis, Ellis County, Texas. 
Existing project. For a description of completed improvement 
and authorizing act see Annual Report of 1969. 
Construction of project was started August 1963 and completed 
for beneficial use in November 1965. Estimated cost 
of project is $12,941,000. 
Local cooperation. Local interests must reimburse the 
Federal Government for costs allocated to increased water 
supply storage under the terms of the Water Supply Act 
of 1958. A Contract was approved by the Secretary of the 
Army on June 24, 1963, and the Trinity River Authority, 
a State agency, agreed to fulfill all requirements of local 
cooperation. To date the authority has paid $349,490 
toward principal and $482,965 toward annual cost of 
operation and maintenance of project, including cost of 
operating 10-foot conduit. 
Operations during fiscal year. Routine operation and 
maintenance continued. Recreation facilities under Code 
710 remain. 
Benefits accrued to Bardwell project: Accumulated flood 
damages prevented through FY 1986 were $9,100,800. 
4. BELTON LAKE, TX 
Location. Dam is on Leon River about 16.7 miles above 
confluence of Leon and Lampasas Rivers and about 3 
miles north of Belton, Texas. 
Existing project. For a description of completed improvement 
and authorizing acts see Annual Report of 
1962. Construction started June 1949 and project was 
ready for beneficial use in March 1954. Raising water 
supply pool: Construction started in July 1970 and the 
pool raise is complete. Estimated cost of project is 
$18,410,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A contract with Brazos River Authority, a 
State agency, for remaining water supply storage in reservoir 
was approved by Secretary of the Army on January 
15, 1958, at an estimated cost of $1,602,822. To date 
$1,089,141 has been paid. Under the contract Brazos 
River Authority must also pay annually 11.2 percent of 
actual annual cost of operation and maintenance. To date 
$1,018,266 has been paid. An interim contract with 
Brazos River Authority for emergency use of water supply 
storage in project was approved by Secretary of the Army 
on January 2, 1957. Amount of $152,435 paid by 
authority on March 21, 1957 for use of these facilities was 
credited to interest and principal payable under formal 
water supply contract. 
Operations during fiscal year. Routine operation and 
maintenance continued. Recreation facilities under Code 
710 remain. 
Benefits accrued to Belton project: Accumulated flood 
damages prevented through FY 1986 were $114,857,800. 
5. BENBROOK LAKE, TX 
Location. Dam is in Tarrant County, Texas, on Clear 
Fork of Trinity River 15 river miles upstream from its confluence 
with West Fork of Trinity River about 10 miles 
southwest of downtown Fort Worth, Texas. 
Existing project. For description of completed improvement 
and authorizing acts see Annual Report for 1962. 
Construction of project was started May 1947 and ready 
for beneficial use in September 1952. Estimated cost of 
project is $14,544,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. No water supply storage is included in project. 
In 1956, Congress passed legislation enabling the city 
of Fort Worth to purchase conservation storage space in 
Benbrook lake. Contracts have been negotiated with the 
city of Fort Worth and the Benbrook Water and Sewer 
Authority for the use of portions of the navigation storage 
for water supply purposes until such storage is required 
for Trinity River Navigation. To date $115,585 has been 
paid by the city of Fort Worth and $101,079 by Benbrook 
Water and Sewer Authority. A cost sharing contract with 
the city of Benbrook for Recreation Development was approved 
by the Secretary of the Army May 20, 1977. To date, 
$16,640 has been paid. 
Operations during fiscal year. Routine operation and 
maintenance continued. Recreation facilities under Code 
710 remain. 
Benefits accrued to system consisting of Benbrook Lake, 
Clear Fork and West Fork Floodways: Accumulated flood 
damages prevented through FY 1986 are estimated at 
$50,510,300. 
6. BIG SANDY LAKE, TX 
Location. The project is located on Big Sandy Creek, 
a tributary of the Sabine River, and is virtually contained 
in Wood County, with a small area extending into Upshur 
County. The damsite is located at River Mile 15.3 
about 6.0 miles northwest of Big Sandy, Texas. 
Existing project. The project provides for construction 
16-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
of an earth and rock fill dam with a maximum height of 
94.5 feet above streambed and a total length of 6,200 feet, 
including the concrete spillway. Big Sandy Lake would 
have a total controlled storage of 418,200 acre-feet and a 
water surface area of 16,580 acres at elevation 382.0, top 
of flood control pool. At elevation 367.5, top of 
conservation pool, the lake would have an area of 10,810 
acres and a storage capacity of 221,200 acre-feet. Project 
was authorized by the Flood Control Act of 1970 (PL 
91-611) and is a unit in the comprehensive basin-wide plan 
of water resource development. Estimated cost of project 
is $99,100,000. 
Local cooperation. Water Supply Act of 1958, as 
amended, and the Federal Water Project Recreation Act of 
1965 apply. The Sabine River Authority of Texas and the 
Texas Water Development Board are the local project 
sponsors. 
Operations during fiscal year. March 25, 1982, Phase 
I General Design Memorandum was recommended for termination 
due to lack of present Federal interest in the project. 
Project was recommended to be reclassified to inactive 
status December 29, 1982, based on the infeasibility of the 
project. 
7. BOGGY CREEK, AUSTIN, TX 
Location. The project is located on Boggy Creek in 
southeast portion of the city of Austin, Texas. 
Existing project. The recommended plan consists of 
concrete trapezoidal channel on Boggy Creek beginning 
just above Webberville Road and extending downstream 
about 2.2 miles to just below Bolm Road. From there, a 
grass lined channel would extend further downstream and 
transition into the natural channel at Ed Bluestein 
Boulevard, a distance of about 1.7 miles. New bridges 
would be required at four street crossings and two railroad 
crossings. The plan calls for acquisition of 54 acres of land 
adjacent to the lower end of the channel to mitigate habitat 
losses and also to provide for environmental quality 
enhancement. About 2.25 miles of trails along the channel 
and 0.95 miles in the Environmental Quality/mitigation 
area will also be provided. Estimated Federal cost is 
$15,000,000 and $10,200,000 non-Federal cost (Oct. 1, 
1986, base price). 
The proposed flood control channel will provide 
capacities for the 100 year flood. Design will provide for 
containment of flows within the banks of the improved 
channels. Bottom widths for the concrete channel will vary 
from 60 feet to 90 feet, and top widths from 80 feet to 120 
feet. 
Local cooperation. In accordance with the cost sharing 
and financing concepts reflected in the Water 
Resources Development Act of 1986, the City of Austin is 
required to provide lands, easements, rights-of-way, and 
material disposal areas, presently estimated at $4,572,000; 
modify or relocate buildings, utilities, roads and other 
facilities except railroad bridges, where necessary in the 
construction of the project presently estimated at 
$3,906,000; pay one-half of the separable costs allocated 
to recreation, presently estimated at $323,000; and bear 
all costs of operation, maintenance, and replacement of 
recreation facilities, presently estimated at $37,000 annually; 
pay five percent of cost allocated to flood control, 
presently estimated at $1,206,000; and bear all cost of 
operation, maintenance, and replacement of flood control 
facilities presently estimated at $39,000 annually; pay 25 
percent of the first costs allocated to environmental quality 
enhancement, presently estimated at $56,000; pay 39 percent 
of the separable first cost allocated to fish and wildlife 
mitigation, presently estimated at $126,000; bear all costs 
of operation, maintenance, and replacement of fish and 
wildlife facilities presently estimated at $4,000; and pay 
39 percent of the cultural resource preservation, currently 
estimated at $11,000. The city will also be required to 
hold and save the United States free from damages due to 
the construction work, operate and maintain all works 
after completion, prevent any obstruction or encroachment 
that would reduce the flow capacity of the project, provide 
and maintain adequate lateral drains and channels, 
publicize flood plain information for all streams in the 
watershed and adopt and enforce regulations to minimize 
damages to future developments within the 100-year flood 
plain, and administer and assure access to the recreational 
facilities and lands to all on an equal basis. 
Operations during fiscal year. A reevaluation of the 
Interim Survey Report was submitted May 5,1982, and approved 
May 18, 1982. The Phase II General Design 
Memorandum was submitted in January 1984. Specific 
authorization for construction of Boggy Creek is found in 
FY 1985 Supplemental Act. The Phase I contract is 
scheduled to be awarded in April 1987. 
8. CANYON LAKE, TX 
Location. Dam is on Guadalupe River, 303 miles above 
its mouth, and about 12 miles northwest of New Braunfels, 
Comal County, Texas. 
Existing project. For a description of completed improvement 
and authorizing act see Annual Report of 1969. 
Construction started April 1958 and project completed for 
beneficial use June 1964. Estimated cost of project is 
$21,732,000, including $1,400,000 contributed by local 
interests. 
Local cooperation. Local interests (Guadalupe-Blanco 
River Authority) will utilize water impounded for water 
supply and streamflow regulation for development of electric 
power. In a formal contract approved by Chief of 
Engineers on October 24, 1957, Guadalupe-Blanco River 
Authority agreed to fulfill all requirements of local 
cooperation. Required contribution of $1,400,000 was made 
in full by Guadalupe-Blanco River Authority. The 
estimated cost of the Water Storage contract is about 
$9,000,000. To date $1,225,860 has been paid. In addition, 
$22,848 was contributed for installation and operation of 
reservoir leakage gages. Under the contract the authority 
must pay 34.8 percent of actual annual cost of operation 
and maintenance. To date $891,891 has been paid. 
16-4

FORT WORTH, TEXAS DISTRICT 
Operations during fiscal year. Regular funds: Routine 
operation and maintenance continued. Recreation 
facilities under Code 710 remain. 
Benefits accrued to Canyon project: Accumulated flood 
damages prevented through FY 1986 were $54,610,200. 
9. COOPER LAKE AND CHANNELS, TX 
Location. Cooper Dam is located in northeast Texas 
about 4 miles southeast of Cooper, 13.0 miles north of 
Sulphur Springs, and is at river mile 23.2 on the South 
Sulphur River. The South Sulphur River rises in Fannin 
County, Texas, and flows generally east for about 80 miles 
to its confluence with the North Sulphur River to form 
the Sulphur River. 
Existing project. The authorized plan of improvement 
consists of a multipurpose reservoir with levee and channel 
improvements on the Sulphur River. The reservoir consists 
of a rolled earthfill dam with a maximum height of 
about 45 feet, 28,070 feet long at its crest, a single conduit 
10.5 feet in diameter, 530 feet long, two 10.5 foot by 
4.75 foot sluices, and a 700 foot wide uncontrolled concrete 
spillway. The reservoir surface area will be 22,740 
acres at the top of the flood control pool, 19,305 acres at 
the top of the water supply pool, and 5,084 acres at the 
top of the sediment pool. The reservoir will contain 
131,400 acre-feet of flood control storage, 273,000 acre-feet 
of municipal and industrial water supply storage, and 
37,000 acre-feet of sediment storage. 
Construction of the project began in July 1958 and, to 
date, approximately 55 percent of the lands required for 
project construction have been acquired and 98 percent 
of the levees and 100 percent of the channel work have 
been completed. Approximately 14.8 miles of the South 
Sulphur River and 6.3 miles of the Middle Sulphur River 
channels have been excavated. Approximately 3.4 miles 
of levee embankment on the South Sulphur River and 7.3 
miles on the Middle Sulphur River have been constructed 
upstream of the Cooper Lake. About 10.5 miles of levee 
on the North Sulphur River, 8.2 miles of levee on the 
Sulphur River, 14 miles of levee on Cuthand Creek, and 
4.2 miles of levee on Brushy Creek were strengthened; 0.5 
mile of levee on Kickapoo Creek was enlarged; and 15.3 
miles of new channel in Cuthand Creek, 0.8 mile of new 
channel in Brushy Creek, and 0.2 mile of cutoff channel 
in Kickapoo Creek were excavated; all downstream from 
Cooper Lake. 
Lack of funds and spending limitations prevented construction 
of the levees and channel work between April 
1964 and February 1971. Construction was started again, 
however, in May 1971. The Texas Committee on Natural 
Resources, et. al., secured an injunction to halt construction 
on the project pending preparation of an Environmental 
Impact Statement (EIS), required by the National Environmental 
Policy Act of 1969. A statement was prepared 
and filed on June 24, 1977. The plan recommended, in 
the Final EIS, minimized further construction of the 
authorized channels and provided for construction of the 
lake and downstream levees. The sufficiency of the Final 
EIS was challenged in the court and in December 1978 
the U.S. District Court for the Eastern District of Texas 
ruled the statement inadequate, citing five deficiencies 
and halting all further construction. A Supplemental EIS 
to comply with the court's decision was prepared and filed 
with the Environmental Protection Agency in March 
1981. The recommended plan of improvement consists of 
the multipurpose lake, 0.9 mile of levee, and the acquisition 
of 25,500 acres of wildlife mitigation lands. All remaining 
channel and levee work was deleted from the 
recommended plan. The Supplemental EIS was filed with 
the court in July 1981 and numerous motions, documents, 
affidavits, and briefs were subsequently filed. Estimated 
Federal cost (Oct. 1, 1986 base price) is $134,227,000, non- 
Federal cost for land for the levees is $227,000 and in addition 
$53,357,000 is to be reimbursed by water supply 
users over a 50-year period. The project was transferred 
to the Fort Worth District at the end of FY 1979. 
Local cooperation. Except for Cooper Lake, local interest 
must furnish lands and rights-of-way and alter and 
relocate highways and related facilities and utilities, except 
railroads, for construction; hold and save the United 
States free from damages; maintain and operate all works 
after completion, and preserve channel capacities by 
preventing encroachment. Local agencies furnished 
rights-of-way for the first two phases of work on the levees 
and channel downstream from Cooper Dam. Rights-of-way 
acquisition for the second phase was also essentially complete 
when construction was halted. 
Assuring agencies are the following counties in Texas: 
Delta, Hunt, Franklin, Lamar, Morris, Hopkins, Titus, 
and Red River. Basic assurances have been received. Supplemental 
assurances covering Public Law 91-646 have 
not been received from Delta, Lamar, Morris, or Hunt 
Counties. 
Operations during fiscal year. After the Supplemental 
EIS was filed in July 1981, numerous motions, 
documents, affidavits, and briefs were filed through October 
1982. On December 30, 1982, the U.S. District Court 
issued a 95-page order continuing the permanent injunction. 
On March 22, 1983, the order was revised and Judge 
William Wayne Justice issued an Amended Memorandum 
Opinion and a Permanent Injunction against the construction 
of Cooper Lake. The Government filed a Notice of Appeal 
with the court in May 1983. Since that time, several 
briefs have been filed with the New Orleans Fifth Circuit 
Court of Appeals. Current action centers on the Appeal 
and resolution of the litigation. On July 16, 1984, litigation 
was resolved and the injunction was released. Contracts 
awarded during FY 1986 include the following: 
Relocate Tucker Cemetery, awarded September 16, 1986; 
Boundary Delineation Part I, awarded September 30, 
1986; Embankment Clearing, awarded June 10, 1986; and 
North Access Road, awarded September 26, 1986. Through 
FY 1986 the following is approximately complete: Levees 
and Channels, 98 percent; Real Estate, 55 percent; Embankments, 
Spillway and Outlets, 0 percent. 
16-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
10. ELM FORK FLOODWAY, TX 
Location. The project is located in Dallas and Denton 
Counties, Texas. A portion of the improvement will be in 
and adjacent to the Cities of Dallas, Irving and Farmers 
Branch, Texas. 
Existing project. Improvement of the Elm Fork of the 
Trinity River from the mouth to Lewisville Dam and 
along Denton Creek, a tributary of the Elm Fork to 
Grapevine Dam. The plan of improvement provides for 
enlargement and realignment of about 22 miles of the 
Elm Fork, enlargement and realignment of about 20 miles 
of tributary channels, construction of about 39 miles of 
new levee, rehabilitation of about 2 miles of existing 
levees, modification of 14 street and highway bridges, 4 
railroad bridges and alteration of utilities. Estimated 
Federal cost of these modifications is $60,700,000, and 
non-Federal estimated cost is $88,600,000, a total of 
$149,300,000 (Oct 1, 1983, base price). 
Local cooperation. Local interests are required to provide, 
without cost to the Federal Government, except for 
the main channel thereof, all lands, easements, utilities 
and bridge relocations except railroad bridges, necessary 
for construction and operation of the project. Assurances 
were signed March 20, 1969 by the Trinity River Authority, 
a State agency, that they would provide items required 
of local interests. 
Operations during fiscal year. Preconstruction planning 
was suspended in 1973. Further studies have been 
delayed until a definite plan has been accepted by local 
interests. 
11. FERRELLS BRIDGE DAMLAKE 
O' THE PINES, TX 
Location. Dam is on Cypress Creek in Marion, Harrison, 
Upshur, Morris, Camp, and Titus Counties, Texas, 
8 miles west of Jefferson, Texas. 
Existing project. An earth-fill dam 10,600 feet long 
and 77 feet high includes a 200-foot spillway with a capacity 
of 68,200 cubic feet per second. Reservoir controls runoff 
from 850 square miles of drainage area, and has a gross 
storage capacity of 842,100 acre-feet, including 587,200 
acre-feet flood control storage, 3,800 acre-feet conservation 
storage, and 251,100 acre-feet for municipal and industrial 
water supply. Reservoir extends 28 miles 
upstream. Project affords substantial flood protection of 
Cypress Creek Valley from damsite to confluence with Red 
River and, together with operation of other reservoirs proposed 
in Red River Basin, will provide flood protection 
along main stem of Red River below Denison Dam. Construction 
commenced in January 1955 and was completed 
in June 1960. Estimated Federal cost of project is 
$17,231,700 (Oct. 1, 1983, base price), including 
$4,349,200 for Code 711 and $399,739 accelerated Public 
Works fund. This project transferred to the Fort Worth 
District as of the end of FY 1979. 
Local cooperation. None required. 
Operations during fiscal yean Routine operation and 
maintenance continued. Recreation facilities under Code 
710 remain. 
Benefits accrued to Ferrells Bridge Dam-Lake O' The 
Pines project: Accumulated flood damages prevented 
through FY 1986 were $6,139,000. 
12. GRAND PRAIRIE, TX, 
SANITARY LANDFILL 
Location. The project is located at a bend of the West 
Fork of the Trinity River, Texas, approximately 19,500 feet 
upstream of the confluence of the West Fork and Elm Fork 
of the Trinity River. This bend in the river is adjacent and 
north of the city of Grand Prairie sanitary landfill which 
lies within Dallas County and is located in northeast 
Grand Prairie. 
Existing project. For description of completed improvements 
and authorizing acts see Annual Report for 
1985. Construction was started September 1983 and completed 
in 1985. The total Federal and non-Federal cost of 
the project is $595,000. 
Local cooperation. In accordance with Section 14 of 
the Flood Control Act of 1946 as amended, the city of 
Grand Prairie is required to assume full responsibility for 
all project costs in excess of the Federal cost limitation 
of $250,000. In addition, the city is required to provide 
without cost to the United States all lands, easements, 
and rights-of-way necessary for construction and 
maintenance; bear the cost of all alteration and relocations 
of utilities, storm drains, roads, highway bridges, and 
community services; hold and save the United States free 
from damages due to construction work; operate and 
maintain all works after completion and prevent any 
obstruction or encroachment that would reduce the flow 
capacity of the project; publicize and notify all interested 
parties that the project will not provide protection from 
the occurrence of storms greater than the project design 
flood; comply with Public Law 91-646, approved January 
2, 1971, and with the requirements of Section 221, Public 
Law 91-611, approved December 31, 1970, as amended. 
13. GRAND PRAIRIE, TX, STREAMBANK 
EROSION AT MEYERS ROAD 
Location. The project is located at a bend of the West 
Fork of the Trinity River approximately 6.1 miles 
upstream of the confluence of the West Fork and Elm Fork 
of the Trinity River. This bend in the river is adjacent to 
Meyers Road which lies within Dallas County and is 
located in northeast Grand Prairie. More specifically 
Meyers Road is north of Interstate Highway 30 and west 
of the city's sanitary landfill. 
Existing project. For description of completed improvements 
and authorizing acts see Annual Report for 
1985. Construction was started in January 1984 and completed 
in 1985. The total Federal and non-Federal 
estimated cost of the project is $300,000. 
Local cooperation. In accordance with Section 14 of 
the Flood Control Act of 1946 as amended, the city of 
Grand Prairie is required to assume full responsibility for 
16-6

FORT WORTH, TEXAS DISTRICT 
all project costs in excess of the Federal cost limitation 
of $250,000. In addition, the city is required to provide 
without cost to the United States all lands, easements, 
and rights-of-way necessary for construction and 
maintenance; bear the cost of all alteration and relocations 
of utilities, storm drains, roads, highway bridges, and 
community services; hold and save the United States free 
from damages due to construction work; operate and 
maintain all works after completion and prevent any 
obstruction or encroachment that would reduce the flow 
capacity of the project; publicize and notify all interested 
parties that the project will not provide protection from 
the occurrence of storms greater than the project design 
flood; comply with Public Law 91-646, approved January 
2, 1971, and with the requirements of Section 221, Public 
Law 91-611, approved December 31, 1970, as amended. 
14. GRAPEVINE LAKE, TX 
Location. Dam is in Tarrant County, Texas, on Denton 
Creek, 11.7 river miles upstream from its confluence with 
Elm Fork of Trinity River and about 20 miles northwest 
of City of Dallas, Texas. 
Existing project. For description of completed improvement 
and authorizing act, see Annual Report for 1962. 
Construction of project was started December 1947 and 
ready for beneficial use in July 1952. Estimated cost of 
project is $18,896,000, including $2,040,000 contributed 
by local interests. 
Local cooperation. A contract with Dallas County 
Park Cities Water Control and Improvement District No. 
2 for 50,000 acre-feet of water supply storage was approved 
by Secretary of the Army on March 21, 1955. Park 
Cities paid the required $607,000. A contract with City 
of Dallas for 85,000 acre-feet of water supply storage was 
approved by Secretary of the Army on March 17, 1954. 
Dallas paid the required $1,433,026. A contract with City 
of Grapevine, Texas, for 1,250 acre-feet of water supply 
storage was approved by Secretary of the Army on 
September 14, 1953, at an estimated cost of $22,654. A 
contract for Interim Use of Navigation Storage with city 
of Grapevine was approved by Secretary of the Army on 
February 27, 1981, at an estimated cost of $684,000. To 
date, $60,771 has been paid. Above contracts include payment 
of operation and maintenance costs as follows: 
Dallas County Park Cities Water Control and Improvement 
District No. 2, a pro rata part of the actual annual 
cost, which part is to be not less than $2,000 nor more 
than $3,000; Dallas, 9.2 percent of actual annual cost; and 
Grapevine, its pro rata part of actual annual cost 
(estimated at $79.55 annually and included in total annual 
payment). Following operation and maintenance 
payments have been made: Park Cities $102,939, Dallas 
$482,169, and Grapevine $95,157. 
Operations during fiscal year. A contract for modification 
of Embankment and Spillway was awarded 
September 30, 1983 and continues. The proposed plan of 
improvement provides for spillway modification by construction 
of spillway chute and stilling basin and a berm 
on the downstream side of the main embankment and 
completion in FY 1987. Recreation facilities under Code 
710 remain. 
Benefits accrued to system comprised of Lewisville Lake, 
Grapevine Lake and Dallas Floodway: Accumulated flood 
damages prevented through FY 1986 were $879,242,900. 
15. HORDS CREEK LAKE, TX 
Location. On Hords Creek, a tributary of Pecan Bayou, 
about 13.5 miles west of Coleman, Texas, and about 27.8 
miles upstream from mouth of Hords Creek. 
Existing project. For description of completed improvement 
and authorizing acts see Annual Report for 1962. 
Construction of project was started January 1947 and 
completed for beneficial use in April 1948. Estimated cost 
of project is $4,337,000 including $105,000 contributed by 
local interests. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Routine operation and 
maintenance continued. Recreation facilities under Code 
710 remain. 
Benefits accrued to Hords Creek project: Accumulated 
flood damages prevented through FY 1986 were $937,200. 
16. JOE POOL LAKE, TX 
Location. Dam site is located at River Mile 11.2 on 
Mountain Creek, a right bank tributary of the West Fork 
of the Trinity River, and is adjacent to the city limits of 
Grand Prairie, Dallas County, Texas, which is one of the 
rapid growing cities in the Dallas-Fort Worth 
Metropolitan area. 
Existing project. The project provides for construction 
of an earthfill dam with a maximum height of 108.5 feet 
above the streambed and a total length of 24,200 feet, including 
50-foot uncontrolled ogee type spillway, which will 
control 232 square miles of drainage area. The reservoir 
will have a total controlled storage of 304,000 acre-feet 
and a water surface area of 10,940 acres at the top of the 
flood control pool and 7,470 acres at the top of the conservation 
pool. The total storage includes 123,100 acre-feet 
for flood control, 142,900 acre-feet for conservation and 
38,000 acre-feet for sediment reserve. Estimated cost of 
the project is $195,900,000 (Oct. 1, 1986, base price) including 
$10,300,000 non-Federal first cost. Project is a unit 
in the general comprehensive plan for development and 
control of the water resources of the Trinity River basin. 
Local cooperation. The Water Supply Act of 1958 as 
amended, and the Federal Water Project Recreation Act 
of 1965 apply. Contracts for water supply storage and 
recreation with the Trinity River Authority were approved 
by the Acting Secretary of the Army, June 15, 1977. 
The recreation contract with Trinity Valley Authority was 
modified March 28, 1979, to allow the Corps to participate 
with the State of Texas and approved by the Assistant 
Secretary of the Army March 21, 1980. Recreation 
16-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
development contract with the State of Texas was approved 
by the Assistant Secretary of the Army March 21, 1980. 
Reimbursement is currently estimated at $46,636,000 for 
water supply and $9,512,000 for recreation (excluding 
future recreation facilities) for a total of $56,148,000 exclusive 
of interest. 
Operations during fiscal year. The project has been 
under construction since FY 1975 and through FY 1986 
is approximately 83 percent complete overall. Contracts 
awarded during FY 1986 include the following: Revegetation 
Part 2, awarded September 30, 1986; Boundary 
Delineation Part 3, awarded September 23, 1986; and 
Drainage Below Dam, awarded September 11, 1986. Land 
Acquisition and Engineering and Design continue. Public 
Law 97-400, H.R. 7377, 97th Congress, effective December 
31, 1982, changed the name of Lakeview Lake to Joe Pool 
Lake. Benefits accrued to Joe Pool Lake project: accumulated 
flood damages prevented through FY 1986 
were $642,700. 
17. LAVON LAKE, TX 
Location. Dam is in Collin County, Texas, on East Fork 
of Trinity River 55.9 miles above its confluence with Trinity 
River and about 22 miles northeast of Dallas, Texas. 
Existing project. For description of completed improvement 
and authorizing acts see Annual Report for 1962. 
Construction of project was started January 1948 and 
ready for beneficial use in September 1953. Project is complete. 
See following section for Lavon Lake Modification 
and East Fork Channel Improvement authorized by Flood 
Control Act of 1962. Estimated cost of project is 
$15,470,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A contract with North Texas Municipal 
Water District for water supply storage, including cost of 
intake structure, was approved by Secretary of the Army 
July 8, 1954, at an estimated cost of $1,405,753. Contract 
was revised in 1973 and final revised contract amount is 
$1,445,261.67. To date the district has paid $647,778. 
Under the contract North Texas Municipal Water District 
must pay annually 13.6 percent of actual annual cost of 
operation and maintenance. To date the district has paid 
$539,505. 
Operations during fiscal year. Routine operation and 
maintenance continued. 
Benefits accrued to Lavon project: Accumulated flood 
damages prevented through FY 1986 were $88,119,000. 
18. LAVON LAKE MODIFICATION 
AND EAST FORK CHANNEL 
IMPROVEMENT, TX 
Location. Existing dam is in Collin County, Texas, on 
East Fork of Trinity River, 55.9 miles above its confluence 
with Trinity River and about 22.0 miles northeast of 
Dallas, Texas. Channel improvement of East Fork extends 
from its mouth to River Mile 31.8. 
Existing project. Reservoir modification provides for 
raising top of existing dam from elevation 502.0 to 514.0 
and lengthening existing dam from about 9,499 feet to 
about 19,493 feet; modification of existing concrete 
spillway structure; enlargement of existing reservoir area, 
involving acquisition of additional rights-of-way; relocation 
and alteration of highways, county roads, railroads 
and utilities; and provision of recreational facilities. East 
Fork Channel and floodway improvements consist of 25 
miles of channel enlargement and straightening of the 
East Fork between River Mile 0.0 and 31.8; replacement 
of inadequate levee-sluice structures; rehabilitation of existing 
levees; acquisition and clearing of land areas as required 
for rights-of-way along improved channel and existing 
levees; alteration of existing railroad, highway and 
county road bridges crossing the improved channel as well 
as relocation of existing utility lines; and strengthening 
and raising about 202,400 linear feet of levees of seven 
existing levee districts. Reservoir will provide a total 
storage capacity of 748,200 acre-feet (275,600 are for flood 
control, 380,000 for water supply storage, and 92,600 for 
sedimentation reserve). Estimated Federal cost of the 
modification and improvement is $69,750,000 and 
estimated cost to local interests is $220,000 for lands and 
damages and relocations, a total of $69,970,000. Construction 
was initiated in May 1970 and ready for beneficial 
use in December 1975. 
Local cooperation. Local interests must reimburse the 
Federal Government for costs allocated to increased water 
supply storage under the terms of the Water Supply Act 
of 1958. The North Texas Municipal Water District has 
contracted for 43 percent of the water supply (approved 
September 22, 1967, by the Secretary of the Army) and 
to date $2,534,663 has been paid. North Texas Municipal 
Water Supply District has submitted assurance to contract 
for 57 percent of future water supply. Reimbursement is 
currently estimated at $37,606,249. 
Levee Districts 4 and 5, which comprise the lower 10 
miles of the East Fork Channel, entered into agreements 
as required by Section 221 of the Flood Control Act of 1970 
on January 28, 1972 and have furnished all necessary construction 
easements. 
Levee Districts 6, 8, 10, 13, and 15, which comprise the 
upper 15 miles of the East Fork Channel, have declined 
to provide the necessary assurances. On December 8, 
1972, this portion of the project was reclassified from "active" 
to "inactive" category. 
Operations during fiscal year. A construction contract 
for Levee Improvement, Increment I, East Fork was 
awarded May 1, 1981, and continues. Improvement of the 
lower ten miles of the East Fork Channel and Levees and 
total project are 99 percent complete. 
19. LEWISVILLE DAM, TX 
Location. Dam is in Denton County, Texas, on Elm 
Fork of Trinity River 30 river miles above its confluence 
with Trinity River and about 22 miles northwest of City 
of Dallas, Texas at a site downstream from old Garza Dam. 
1 F-R

FORT WORTH, TEXAS DISTRICT 
Existing project. For description of completed improvement 
and authorizing acts see Annual Report for 1962. 
Construction of project was started November 1948 and 
ready for beneficial use in November 1954. Estimated cost 
of project is $25,902,000, including $3,677,000 contributed 
by local interests. 
Local cooperation. A contract with City of Dallas for 
415,000 acre-feet of water supply storage land rights and 
interests to Garza Dam and Reservoir was approved by 
the Secretary of the Army on July 16, 1953. Local contributions 
have been made in full. A contract with city 
of Denton, Texas, for remaining 21,000 acre-feet of water 
supply storage was approved by the Secretary of the Army 
on May 20, 1954, with an estimated cost of $250,064. 
Local contributions have been paid in full. Under above 
contracts, cities of Dallas and Denton must pay annually 
21.9 and 1 percent, respectively, of actual annual cost of 
operation and maintenance. Tob date Dallas has paid 
$3,000,210 and Denton $128,132. 
Operations during fiscal year. Routine operation and 
maintenance continued. Recreation facilities under Code 
710 remain. 
Benefits accrued to system comprised of Lewisville Lake, 
Grapevine Lake, and Dallas Floodway: Accumulated flood 
damages prevented through FY 1986 were $879,242,900. 
20. MILLICAN LAKE, TX 
Location. Dam is on the Navasota River at mile 24.1, 
approximately 7.0 miles north of Navasota, Texas in 
Grimes and Brazos Counties, Texas. This project would 
be the first of a two-stage development consisting of 
Millican and Navasota Dams, both of which would be 
units in the overall plan of improvement for the Brazos 
River Basin. 
Existing Project. The project provides for construction 
of a concrete and earthfill dam 25,300 feet long including 
a 472-foot gate-controlled spillway, rising 83 feet above the 
streambed. Without Navasota Lake in operation, the top 
of flood control pool (elevation 234.0) would provide 
1,557,400 acre-feet of storage space and cover a surface 
area of 66,000 acres. There would be 784,800 acre-feet of 
flood control; 680,200 acre-feet for water supply (surface 
area 42,400 acres), and 92,400 acre-feet for sediment 
reserve. 
With Navasota Lake in operation, the top of flood control 
elevation and total storage would remain the same. 
The flood control pool would be 359,600 acre-feet, water 
supply storage would be 1,125,800 acre-feet (surface area 
55,500 acres) and sediment reserve would be 72,000 acrefeet. 
Estimated Federal cost of the project is $318,000,000 
(Oct. 1, 1982 base price). 
Local cooperation. The Water Supply Act of 1958 as 
amended and the Federal Water Project Recreation Act 
of 1965 applies. By letter dated December 9, 1974, the 
Brazos River Authority stated that they would be the state 
agency to cost share for both water supply and recreation. 
Operations during fiscal year. Preconstruction planning 
continued, and the General Reevaluation Report is 
scheduled to complete in September 1987. 
21. NAVARRO MILLS LAKE, TX 
Location. Dam is in Navarro County, Texas, at River 
Mile 63.9 on Richland Creek, a tributary of Trinity River, 
about 16.0 miles southwest of Corsicana, Texas. 
Existing project. For description of completed improvement 
and authorization acts see Annual Report for 1965. 
Construction started December 1959 and project completed 
for beneficial use March 1963. Estimated cost of 
project is $13,154,000, including $300,000 contributed by 
local interests. 
Local cooperation. The Water Supply Act of 1958, as 
amended applies. A formal contract with the Trinity River 
Authority was approved March 3, 1966, by the Secretary 
of the Army at an estimated cost of $2,260,800. To date 
the Authority has paid $677,186 for water supply and 
$741,523 for operation and maintenance. 
Operations during fiscal year. Routine operation and 
maintenance continued. Recreation facilities under Code 
710 remain. 
Benefits accrued to Navarro Mills project: Accumulated 
flood damages prevented through FY 1986 were 
$27,356,600. 
22. O. C. FISHER DAM AND LAKE, TX 
Location. Dam is on North Concho River, a tributary 
of Concho River, about 6.6 miles above mouth of North 
Concho River near city of San Angelo, Texas. 
Existing project. For description of completed improvement 
and authorizing acts see Annual Report for 1962. 
Name was changed from San Angelo Dam and Reservoir 
to O.C. Fisher Dam and Lake January 3, 1975 by Public 
Law 93-634. Construction of project was started May 1947 
and ready for beneficial use February 1952. Estimated 
cost of project is $17,111,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A water-supply contract with Upper Colorado 
River Authority for water-supply storage in reservoir 
was approved by Secretary of the Army on October 
11, 1948. The Authority has contributed $860,444 toward 
cost of project and $64,324 toward operation and 
maintenance for a 50-year period. The Authority must pay 
additional consideration of $1 a year for useful life of project, 
beginning January 1, 1965. 
Operations during fiscal year. Routine operation and 
maintenance continued. Recreation facilities under Code 
710 remain. 
Benefits accrued to O. C. Fisher Dam and Lake project: 
Accumulated flood damages prevented through FY 1986 
were $2,375,600. 
23. PROCTOR LAKE, TX 
Location. Dam is at River Mile 238.9 on Leon River, 
a tributary of Brazos River, about 8.0 miles northeast of 
Comanche in Comanche County, Texas. 
Existing project. For description of completed improve 
16-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
ment and authoriation act see Annual Report of 1969. 
Construction of project was started July 1960 and completed 
for beneficial use 1963. Estimated cost of project 
is $16,249,000. 
Local cooperation. The Water Supply Act of 1958 applies. 
A formal contract with the Brazos River Authority, 
a State agency, was approved by Secretary of the Army, 
July 1, 1960, and was modified and approved May 9, 1966, 
at an estimated cost of $1,707,900. To date the Authority 
has paid $312,467 for water supply and $296,192 for 
operation and maintenance. 
Operations during fiscal year. Routine operation and 
maintenance were continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Proctor project: Accumulated flood 
damages prevented through FY 1986 were $6,783,600. 
24. RAY ROBERTS LAKE, TX 
Location. Damsite is located at River Mile 60.0 on the 
Elm Fork of the Trinity River, Denton County, between 
Sanger and Aubrey, Texas and 30 miles upstream from 
Lewisville Dam. 
Existing project. The plan of improvement provides for 
construction of an earthfilled dam with a maximum 
height of 141 feet above the streambed, a length of 15,250 
feet including an uncontrolled broadcrested spillway 100 
feet long, controlling 682 square miles of drainage area. 
The lake will have a total controlled storage of 1,064,600 
acre-feet. with a water surface area of 36,900 acres. The 
total storage includes 260,800 acre-feet for flood control, 
749,200 acre-feet for water supply, and 54,600 acre-feet 
for sediment reserve. Estimated Federal cost of the project 
is $302,000,000 (Oct. 1, 1986, base price). Public Law 
96-384, 96th Congress, H.R. 8024, effective January 4, 
1981, changed the name of Aubrey Lake to Ray Roberts 
Lake. 
Local cooperation. The Water Supply Act of 1958 as 
amended and the Federal Water Project Recreation Act 
of 1965 and Section 221, Flood Control Act of 1970 apply. 
Contracts with the cities of Dallas and Denton, Texas, for 
water supply storage and recreation were approved by the 
Secretary of the Army September 16, 1980. 
Operations during fiscal year. The project is about 
53 percent complete overall. Acquisition of real estate continues. 
FY 1986 funds were used to award the following 
contracts: County Roads, Part III, awarded April 21, 1986; 
Mt. Spring Water Lines, awarded August 12, 1986; Valley 
View Telephone, awarded July 21, 1986; Texas-New Mexico 
Electric Lines, awarded September 25, 1986; Cooke 
County Electric Lines, awarded July 29, 1986; Green 
Springs Waterlines, awarded September 29, 1986; General 
Telephone Lines and FM 922, awarded October 7, 1985; 
Bolivar Water Supply, awarded September 25, 1986; and 
Denton County Electric-FM 423, awarded September 5, 
1986. At the request of the City of Denton and the approval 
of the Secretary of the Army, the penstock was added 
to the embankment as a minimum facility for future 
hydropower. Engineering and design continue. 
25. SAN ANTONIO CHANNEL 
IMPROVEMENT, TX 
Location. Floodway is in city of San Antonio, Bexar 
County, Texas, on San Antonio River and San Pedro, 
Apache, Alazan, Martinez Creeks, and Espada Aqueduct 
located in vicinity of Six Mile Creek. 
Existing project. Provides for clearing, widening, 
deepening, and straightening about 34.9 miles of river and 
creek channels to carry standard project flood discharges, 
construction of channel walls, paving, conduit, and construction 
and alteration of railroad bridges. Estimated 
Federal cost of these modifications is $121,000,000 (Oct. 
1, 1986, base price), and estimated cost to local interests 
is $73,600,000 which includes $3,000,000 cash contributions 
and $70,600,000 for lands, damages, and construction, 
a total of $194,600,000. Existing project was 
authorized by 1954 Flood Control Act. The Water 
Resources Act of 1976 added authorization to the existing 
project for construction of flood control measures needed 
to preserve and protect the Espada Aqueduct located in 
the vicinity of Six Mile Creek. Construction was started 
in October 1957 and the project is about 81 percent 
complete. 
Local cooperation. Local interests must furnish lands 
and rights-of-way for construction, including purchase and 
removal of buildings, relocation or reconstruction of 
bridges (exclusive of railway bridges), channel dams where 
applicable, and utility lines; hold the United States free 
from damages; maintain and operate all works after completion; 
and provide a cash contribution for enhancement 
benefits of 2.65 percent of actual Federal construction cost. 
San Antonio River Authority furnished assurances that 
it will comply with all requirements of local cooperation. 
These assurances were accepted by the District Engineer 
on April 15, 1957. To date $999,525 has been contributed 
by San Antonio River Authority. In addition, $30,000 has 
been contributed and accepted, under the authority of 
Civil Functions Appropriations Act of 1958, for vehicular 
crossings over the San Antonio channel. 
Operations during fiscal year. Engineering and 
design studies continued. 
Benefits accrued to San Antonio project: Accumulated 
damages prevented through FY 1986 were $105,305,500. 
26. SAN GABRIEL RIVER, TX 
Location. Project is a system of three reservoirs in 
Williamson County in the central portion of Brazos River 
Basin, which consists of Granger Dam at River Mile 31.9 
on San Gabriel River, about 7.0 miles east of Granger, 
Texas; North San Gabriel Dam at River Mile 4.3 on North 
Fork of San Gabriel River, about 3.5 miles northwest of 
Georgetown, Texas; and South Fork Dam at River Mile 
4.7 on South Fork of San Gabriel River, about 3.0 miles 
southwest of Georgetown, Texas. 
Existing project. Granger Lake was authorized by 
1954 Flood Control Act, and North (North San Gabriel 
16-10

FORT WORTH, TEXAS DISTRICT 
Dam and Lake Georgetown) and South Fork Lakes were 
authorized by 1962 Flood Control Act. Estimated total 
Federal cost of project is $181,400,000 (Oct. 1, 1986, base 
price),and estimated non-Federal cost of $90,600,000 for 
a project total of $272,000,000. Plan of improvement provides 
for the following: Granger: An earthfilled dam 
16,320 feet long, including spillway with maximum height 
of 115 feet above streambed, which controls 709 square 
miles of drainage area. Reservoir provides a total storage 
capacity of 244,200 acre-feet, of which 162,200 acre-feet 
are for flood control, 37,900 acre-feet for water supply 
storage, and 44,100 acre-feet for sediment reserve. 
Estimated cost of project is $62,062,000. North San 
Gabriel Dam: A rockfill dam 6,700 feet long, including 
spillway with maximum height of 164 feet above streambed, 
which controls 246 square miles of drainage area. 
Reservoir provides a total storage capacity of 130,800 acrefeet 
of which 87,600 acre-feet are for flood control, 29,200 
acre-feet for water supply storage, and 14,000 acre-feet for 
sediment reserve. Estimated cost of project is $38,765,000. 
South Fork: A rockfill dam 5,620 feet long, including 
spillway with maximum height of 152 feet above streambed, 
which controls 123 square miles of drainage area. 
Reservoir provides a total storage capacity of 82,600 acrefeet 
(45,700 for flood control, 28,900 for water supply 
storage, and 8,000 for sediment reserve). Estimated cost 
of project is $171,173,000. Public Law 96-575, 96th Congress, 
H.R. 4941 effective January 4, 1981, changed the 
name of North Fork Lake to North San Gabriel Dam and 
Lake Georgetown. 
Local cooperation. Construction is subject to condition 
that local interests reimburse the Federal Government 
for costs allocated to water supply at Granger, Lake 
Georgetown, and South Fork Lakes. Reimbursement currently 
estimated at $13,315,000 for Granger, $6,295,000 
for Lake Georgetown, and $50,563,000 for South Fork, for 
a total of $70,172,000 exclusive of interest. Brazos River 
Authority, a State agency, is the local interests' sponsor 
of project, and by letter dated April 18, 1966, indicated 
its acceptance of the proposed plan of development and 
its willingness to pay for the costs allocated to water supply 
in each reservoir in the ultimate plan. Such water supply 
assurances for Granger and Lake Georgetown Lakes 
were approved May 24, 1968 as satisfactory in accordance 
with requirements of the Water Supply Act of 1958, as 
amended. Contract negotiations for South Fork Lake will 
be deferred until the need for water supply develops and 
the reservoir is scheduled for construction. 
Operations during fiscal year. Through 1983 all work 
has been completed. Deliberate impoundment of water 
commenced at Granger and Lake Georgetown Lakes on 
January 21, 1980 and March 3, 1980, respectively. In FY 
1982, studies on South Fork Lake were resumed in 
preparation of General Design Memorandum to provide 
reaffirmation prior to construction. This reaffirmation is 
currently scheduled for submission in October 1986 and 
to be fully coordinated by February 1987. 
Benefits accrued to project consisting of Granger and 
Lake Georgetown: Accumulated flood damages prevented 
through FY 1986 were $15,535,700. 
27. SOMERVILLE LAKE, TX 
Location. Dam is on Yegua Creek 20 miles upstream 
from its confluence with Brazos River and about 2 miles 
south of Somerville, Texas. 
Existing project. For description of completed improvements 
and authorizing act see Annual Report of 
1969. Construction started in June 1962 and project was 
ready for beneficial use in January 1967. Estimated cost 
of project is $30,227,000. 
Local cooperation. The Water Supply Act of 1958, as 
amended, applies. A contract with the Brazos River 
Authority, a State agency, for water supply storage approved 
May 10, 1962, by the Secretary of the Army, to date, 
$905,754 has been paid. Also under the contract, the 
authority must pay annually 28.655 percent of the actual 
annual cost of operation and maintenance. 
Operations during fiscal year. Routine operation and 
maintenance continued. Recreation facilities under Code 
710 remain. 
Benefits accrued to Somerville project: Accumulated flood 
damages prevented through FY 1986 were $31,126,500. 
28. STILLHOUSE HOLLOW DAM, TX 
Location. Dam is on Lampasas River 16 miles 
upstream from its confluence with Little River, a tributary 
of the Brazos River, and about 5 miles southwest of Belton, 
Texas. 
Existing project. For description of completed improvements 
and authorizing act see Annual Report of 
1969. Construction was initiated in July 1962 and the project 
was ready for beneficial use in February 1968. 
Estimated cost of project is $23,670,000. 
Local cooperation. The Water Supply Act of 1958 applies. 
A contract with the Brazos River Authority, a State 
agency, for water supply storage was approved April 13, 
1962, by the Secretary of the Army, at an estimated cost 
of $6,912,430. To date the Authority has paid $1,135,440. 
Also under the contract the Authority must pay annually 
27.748 percent of the actual annual cost of operation 
and maintenance. To date the Authority has paid 
$554,928. 
Operations during fiscal year. Routine operation and 
maintenance continued. Recreation facilities under Code 
710 remain. 
Benefits accrued to Stillhouse Hollow Project: Accumulated 
estimate of flood damages prevented through 
FY 1986 is $22,809,300. 
29. WACO LAKE, TX 
Location. Dam is on Bosque River, 4.6 river miles above 
its confluence with Brazos River, at City of Waco, McLennan 
County. Texas. 
Existing project. For description of completed improvements 
and authorizing act see Annual Report of 
1969. Estimated cost of project is $50,853,000 including 
16-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
$250,000 contributed by local interests and $2,500,000 
other non-Federal cost. Construction was started in July 
1958, and project was ready for beneficial use in 
February 1965. 
Local cooperation. Section G of the Flood Control 
Act of December 1944 applies. A contract with the 
Brazos River Authority, a State agency, for water supply 
storage and the contract with the City of Waco 
transferring the existing Lake Waco to the Government 
for their water storage, was approved by the Secretary 
of the Army on April 15, 1958. To date the Authority 
for their portion of the water supply storage has paid 
$1,527,686. Also under the contract the Authority and 
the City must pay 14.706 and 2.087 percent respectively 
of the actual cost of operation and maintenance. To 
date the Authority has paid $716,619 and the City has 
paid $114,295. A contract with the Brazos River Authority, 
for additional storage for municipal and industrial 
water supply, was approved by the Acting Assistant 
Secretary of the Army, September 28, 1984. 
Operations during fiscal year. Routine operations 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Waco project: Accumulated 
flood damages prevented through FY 1986 were 
$58,731,900. 
30. WRIGHT PATMAN DAM 
AND LAKE, TX 
Location. Dam is on Sulphur River in Cass and Bowie 
Counties, Texas. Dam is 45 miles above mouth of 
Sulphur River, and about 8 miles southwest of Texarkana, 
Texas. 
Existing project. For description of completed improvements 
and authorizing act see Annual Report of 
1984. Estimated cost of project is $51,945,000 which includes 
$5,449,100 Code 711, $399,939 accelerated public 
works funds, and $13,138,004 to be reimbursed by local 
interests, over a period not to exceed 50 years, for water 
supply storage, and including $2,092,040 for pro rata 
share of original reservoir cost. Construction was initiated 
in August 1948 and completed in March 1962, 
except real estate activities, construction under Code 
711, and conversion of 120,000 acre-feet to water supply 
storage after completion of Cooper Reservoir. This project 
transferred to the Fort Worth District as of the end 
of FY 1979. 
Local cooperation. A contract with the city of Texarkana, 
Texas, for reserving water supply storage space 
was approved by the Secretary of the Army December 
17, 1968. To date the City has paid $357,087. 
Operations during fiscal year. Routine operation and 
maintenance continued. Recreation facilities under Code 
710 remain. 
Benefits accrued to Wright Patman project: Accumulated 
flood damages prevented through FY 1986 
were $13,697,000. 
31. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed local flood protection projects 
is made periodically in compliance with section 208.10, 
of title 33, Code of Federal Regulations, which contains 
regulations for operation and maintenance of local floodprotection 
works approved by Secretary of the Army in 
accordance with authority in Section 3, Flood Control Act 
of June 22, 1936. See Table 16-D for inspections made this 
fiscal year. 
Inspection costs for FY from regular funds for 
maintenance were $33,549. Total costs to September 30, 
1986 were $599,200. 
32. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
In accordance with Flood Control Act of 1944 expenditures 
were made for scheduling flood control reservoir 
operations and preparation of reservoir regulation manual 
for Marshall Ford Dam, on the Colorado River, near City 
of Austin, Texas, and for preparation of reservoir regulation 
manual for Twin Buttes Dam, on Middle and South 
Concho Rivers near City of San Angelo, Texas. Marshall 
Ford Dam was authorized by 1937 River and Harbor Act. 
Project was constructed jointly by Bureau of Reclamation 
and Lower Colorado River Authority and was completed 
during FY 1942. Twin Buttes Reservoir was authorized 
for construction by Department of Interior by Public Law 
152, 85th Congress. Construction was initiated in June 
1960; closure of dam started in June 1962; deliberate impoundment 
was started January 23, 1963. 
Accumulated damages prevented by Marshall Ford 
Reservoir through FY 1986 were $183,482,600 and by 
Twin Buttes through FY 1986 were $417,500. Twin Buttes 
Reservoir consists of two separate pools, one on South 
Concho River and the other on Middle Concho River and 
Spring Creek. Equalizing channel between these two 
pools is at elevation 1925.0. Costs for fiscal year from 
regular funds for operation of both reservoirs were 
$183,900,600. 
33. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 16-C.) 
34. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
(See Table 16-E.) 
Flood control activities pursuant to section 205, Public 
Law 858, 80th Congress, as amended (preauthorization); 
emergency streambank protection under section 14, 
Public Law 526, 79th Congress, as amended. 
Emergency flood control, hurricane-flood, and shore protection 
activities (Public Law 99, 84th Congress, and 
antecedent legislation). 
Fiscal year costs were $422,218 for disaster 
preparedness; no levee repair. 
16-12

FORT WORTH, TEXAS DISTRICT 
Multi-Purpose Projects Including Power 
35. BELTON LAKE MODIFICATION, TX 
Location. For location of completed dam see Belton Lake, 
Texas in this chapter. 
Existing project. The modification of Belton Lake to provide 
installation of hydroelectric power generating facilities 
was authorized by the Flood Control Act of 1954. The plan 
of improvement provides for reallocation of the gross 
storage capacity in Belton Lake to provide a power pool and 
the installation of hydroelectric power generating facilities. 
Operations during fiscal year. The modification is 
classified as deferred until the Chief of Engineers determines 
it is advisable. 
36. DAM A LAKE, TX 
Location. The dam would be located approximately 18 
miles west of Jasper and about 4 miles west of Horger,'IT exas. 
Existing project. The project is designed to be used as a 
run-of-river plant for the generation of power and to reregulate 
power surges from the proposed Rockland Lake. 
The last estimate of project cost was $3,220,000 in 1954. For 
last full report see Annual Report of 1952. 
Operations during fiscal year. The project is classified 
as deferred. 
37. ROCKLAND LAKE, TX 
Location. The dam would be located approximately 3 
miles west of Rockland, Texas, on the Neches River. 
Existing project. The project would control floods, 
generate hydroelectric power, and provide water supply for 
various uses. The last estimate of project cost was 
$767,000,000 (Oct. 1, 1985 base price), including 
$145,900,000 Federal cost and $621,100,000 non-Federal 
cost. For the last full report see Annual Report of 1952. 
Operations during fiscal year. The project was 
reclassified to active status December 2, 1982. 
38. SAM RAYBURN DAM AND 
RESERVOIR, TX 
Location. Dam is on Angelina River 25.2 miles upstream 
from its confluence with Neches River and about 10.0 miles 
northwest of Jasper, Texas. 
Existing project. For description of completed improvements 
and authorizing act see Annual Report 1969. 
Construction was started August 1956 and project was 
ready for beneficial use in March 1965. Estimated cost of 
project is $68,683,000 including $3,000,000 contributed by 
local interests. 
Local cooperation. A contract with the Lower Neches 
Valley Authority, a State agency, to contribute $3,000,000 
toward the first cost and an additional $200,000 annually 
for 50 years after completion of the project was approved by 
the Secretary of the Army on January 22, 1957. Contribution 
of $3,000,000 was made in full and annual payments 
to date of $3,800,000 have been made by the Authority. 
A contract with the City of Lufkin for water supply 
storage was approved May 27, 1969 by the Secretary of 
the Army at an estimated cost of $525,600. To date the 
City has paid $105,511. Also under the contract the City 
of Lufkin must pay annually 0.692 percent of the annual 
cost of operation and maintenance. To date the City has 
paid $109,061. 
Operations during fiscal year. Continued routine 
operation and maintenance. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Sam Rayburn project: Accumulated 
flood damages prevented through FY 1986 were 
$82,015,400. 
39. TOWN BLUFF DAMB.
A. STEINHAGEN LAKE, TX 
Location. Dam is on Neches River about 12.4 miles 
below mouth of Angelina River, one-half mile north of 
Town Bluff, Texas, and 93.0 river miles north of Beaumont, 
Texas. 
Existing project. For description of completed improvement 
and authorizing acts see Annual Report for 1962. 
Construction started March 1947 and project was ready 
for beneficial use in April 1951. Estimated cost of project 
is $9,888,000, including $2,000,000 contribution by local 
interests. 
Local cooperation. Completed as required. 
Operations during fiscal year. Routine operation and 
maintenance continued. Recreation facilities under Code 
710 remain. 
40. TOWN BLUFF HYDROPOWER, TX 
Location. For location of completed dam see Town Bluff 
Dam-B.A. Steinhagen Lake, Texas in this chapter. 
Existing project. Installation of hydroelectric power 
generating facilities at Town Bluff Dam was authorized 
by the River and Harbor Act of 1945 (Public Law 79-14), 
March 2, 1945, but deferred in the original construction. 
Town Bluff Dam was completed and placed in operation 
in 1951. A Feasibility Report was approved September 9, 
1983 and a Design Analysis Report completed in April 
1982 indicated that installing hydropower at this project 
is now economically feasible. The hydropower facilities 
will include a 6,000 kilowatt power plant (two units at 
3,000 kilowatts each), intake and outlet facilities, and 
necessary switchgear equipment to be located in the main 
embankment at the old diversion channel and will be 
operated remotely from the Sam Rayburn project. The installation 
and operation of hydropower facilities will not 
result in the altering of the existing operation at Town 
Bluff. The project will produce an estimated 35,900 
megawatt hours of energy per year. There is no Federal 
cost on this project. It is completely funded by Non-Federal 
funds. The estimated Non-Federal cost is $16,200,000. 
Local cooperation. A contract with the Sam Rayburn 
Municipal Power Authority was approved by Secretary of 
the Army, June 28, 1985, relative to financing, escrow 
agreement, and power sales agreement. 
16-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Operation during fiscal year. Plans and specifications 
were completed and construction on the turbinegenerator 
was initiated in FY 1986. Planning and 
Engineering studies continue. Project completion date is 
scheduled for 1989. 
41. WHITNEY LAKE, TX 
Location. Dam is on Brazos River, about 442 miles 
above mouth of river, 5.5 miles southwest of Whitney, 
Texas, and about 38 miles upstream from City of Waco, 
Texas. 
Existing project. For description of completed improvement 
and authorizing acts see Annual Report for 1962. 
Construction of project was started June 1946 and ready 
for flood control use in December 1951. First power was 
placed on-the-line in June 1953. Raise power pool is complete. 
Estimated cost of project is $46,306,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A contract with the Brazos River Authority, 
a State agency, for Water Supply Storage was approved 
by the Secretary of the Army November 3, 1982. To date 
the authority has paid $123,507. 
Operations during fiscal year. Continued routine 
operation and maintenance. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Whitney project: Accumulated flood 
damages prevented throuth FY 1986 were $131,516,200. 
General Investigations 
42. SURVEYS 
Fiscal year costs were $887,601 for flood damage prevention 
studies, $107,085 for coordination with other agencies, 
and $3,739 for preauthorization studies Phase I for 
a total of $1,086,558. 
43. COLLECTION AND STUDY OF 
BASIC DATA 
Work was continued under the Flood Plain Management 
Services on the compilation of information on floods and 
potential flood damages, including identification of those 
areas subject to inundation. Fiscal year expenditures for 
these activities totaled $300,266. Fiscal year costs were 
$5,918 for hydrologic studies. 
16-14

TABLE 16-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
1. Trinity River 
Project, TX 
Includes Channel to 
Liberty, Tennessee 
Colony Lake, and Dallas 
Floodway Extension 
2. Aquilla Lake, TX 
3. Bardwell Lake, TX 
4. Belton Lake, TX 
5. Benbrook Lake, TX 
6. Big Sandy Lake, TX 
7. Boggy Creek, TX 
8. Canyon Lake, TX 
9. Cooper Lake and 
Channels, TX 
10. Elm Fork Floodway, TX 
11. Ferrells Bridge Dam - 
Lake O' The Pines, TX 
12. Grand Prarie, TX 
Landfill 
(Contributed Funds) 
13. Grand Prairie, TX 
Myers Road 
Total Cost To 
FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 17 
248,000 212,999 (-)20,000 (-)81,000 22,299,865 
94,078 216,206 53,412 161,064 22,299,812 
Funding 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
3,049,000 
5,261,404 
136,000 
75,109 
1,064,700 
673,632 
20,904 
55,035 
1,169,000 
1,039,194 
13,647 
1,807,500 
1,489,685 
1,000 
1,792 
350,000 
373,933 
1,162,600 
713,806 
1,000,000 
95,448 
2,973,684 
1,995,078 
250,000 
25,826 
345,000 
38,400 
12,603 
- 58,974 
329,000 
327,291 
1, 
1,
790,000 
789,322 
3,162 
,278,600 
,308,974 
325,069 
249,000 
287,859 
561,200 
972,137 
57,000 
63,661 
1,236,000 
1,533,021 
(-)5,160 
2,457 
2,357,000 
2,098,363 
100,000 
79,858 
635,000 
1,065,277 
175,000 
319,458 
1,458,080 
2,502,913 
5,000 
13,559 
1,113,000 
1,122,862 
792,000 
1,901,072 
1,424,500 
1,425,959 
218,800 (-)24,666 
311,164 
211,600 
234,587 
1,247 
858 
- 45,506,300 
7,683 45,491,467 
412,000 1,126,000 
400,259 1,090,518 
- 10,934,505 
- 10,934,505 
1,124,800 11,364,88718 
1,116,537 10,153,63318 
(-)9,000 16,960,549 
(-)2,557 16,960,5491 
1,622,600 15,320,54218 
1,640,448 15,142,65018 
- 13,130,463 
- 13,069,9912 
1,112,000 16,228,41418 
1,140,186 16,169,38018 
- 675,000 
- 675,000 
295,000 1,020,000 
215,950 928,752 
- 19,088,5243 
- 19,088,524 
1,087,000 11,697,00418 
1,068,610 11,425,52118 
3,301,000 27,921,000 
3,181,603 27,541,243 
- 662,400 
- 662,400 
- 14,175,197� 
- 14,175,197 s 
6 
1,660,200 19,814,83118 
1,697,636 19,780,78218 
- 250,000 
- 219,960 
- 345,000 
32,589 345,000 
- 250,000 
- 248,048 
16-15 
1,355,200 
1,970,936

FORT WORTH, TEXAS DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project 
(Contributed Funds) 
14. Grapevine Lake, TX 
15. Hords Creek Lake, 
TX 
16. Joe Pool Lake, TX 
17. Lavon Lake, TX 
18. Lavon Lake 
Modification & East 
Fork Channel 
Improvement, TX 
19. Lewisville Dam, TX 
20. Millican Lake, TX 
21. Navarro Mills Lake, 
TX 
22. O. C. Fisher Dam 
and Lake, TX 
23. Proctor Lake, TX 
24. Ray Roberts Lake, TX 
37. Rockland Lake, TX 
FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
8,040 
4,200,000 
5,371,807 
1,758,000 
1.743,680 
Funding 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
1,552,800 
1,515,928 
105,939 
2,912 
122,469 
4,274,500 
2,043,428 
36,993 
250,0( 
462,3 
1,450,6( 
1,504,7 
- 40,000 
1,400,000 5,500,000 
333,895 5,165,510 
2,034,600 2,024,550 
1,323,728 2,730,034 
- 20,000 
- 18,076 
1,140,650 1,370,000 
601,409 1,792,382 
27,800,000 17,200,000 
29,007,040 14,842,702 
1,904,6 
1,945,3 
(-)184,0 
3,5 
2,054,6 
1,876,6 
23,0 
- 40,000 
- 8,040 
00 21,317,790 
95 21,301,3977 
00 18,372,76818 
55 18,331,65818 
- 2,731,0898 
24 2,731,089 
81 9,232,66918 
94 9,156,31818 
00 159,789,000 
30 159,277,976 
00 108,000 
89 159,789 
- 12,864,796 
- 12,864,796 
00 18,615,61818 
84 18,554,57018 
- 69,796,862 
- 69,796,678 
00 25,333,988 
29 25,333,9889 
00 25,351,50310 18 
03 22,841,19210 18 
- 3,627,000 
08 3,627,000 
- - 9,846,759 
- - 9,846,7591 
1,074,300 843,000 10,950,12618 
1,095,363 888,742 10,930,16918 
- - 16,027,467 
- - 16,027,467 
1,428,000 601,000 10,454,93118 
1,436,960 603,677 10,415,70718 
- - 14,469,585 
- 14,409 14,469,585 
1,083,900 1,081,000 10,954,73218 
1,107,198 1,085,535 10,735,20818 
41,500,000 44,118,000 197,712,700 
40,690,956 46,428,681 195,735,906 
- 269,000 269,000 
- 251,649 258,650 
951,0 
1,055,5 
15,550,0 
14,593,6 
(-)23,000 
19,791 
2,507,319 
1,618,813 
76,000 
709,286 
(-)13,663 
498,732 
2,585,547 
1,835,306 
232,000 
234,715 
767 
300 
1,036,500 
648,170 
964,776 
506,566 
23,000 
27,335 
1,445,300 
752,711 
37,700,000 
37,414,850 
(-)14,000 
812 
1,691,150 
2,742,378 
220,000 
221,839 
755,160 
1,151,615 
2,928,000 
3,839,707 
70,000 
24,566 
480 
788,400 
1,129,622 
704,900 
1,142,469 
821,000 
1,522,872 
46,000,000 
44,353,854 
16-16 
TABLE 16-A 
- 1,9' 
00 928,1 
80 980,1� 
00 1,951,0( 
36 7,404,0: 
- 108,0( 
- 159,7

TABLE 16-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 17 
38. Sam Rayburn Dam 
and Reservoir, TX 
25. San Antonio Channel 
Improvement, TX 
(Federal Funds) 
(Contributed Funds) 
26. San Gabriel River, 
TX 
Granger 
Lake Georgetown 
27. Somerville Lake, TX 
28. Stillhouse Hollow 
Dam, TX 
39. Town Bluff Dam- 
B. A. Steinhagen 
Lake, TX 
29. Waco Lake, TX 
40. Whitney Lake, TX 
30. Wright Patman Dam 
and Lake, TX 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
(-)1,300 
48,471 
- 60,670,957 
143 - 60,670,95612 
2,468,500 3,126,800 2;594,500 2,441,600 32,118,21418 
2,250,027 3,844,076 2,739,758 2,455,388 31,746,17518 
3,300,000 (-)425,000 808,000 2,114,000 40,215,048 
2,631,768 989,645 548,801 2,119,850 39,927,006 
71,550 
71,550 
2,150,000 (-)20,000 
2,216,366 72,540 
1,278,600 
661,833 
1,050,436 
772,455 
709,900 
1,357,865 
475,000 
783,364 
- 999,525 
- 999,525 
200,000 191,000 101,773,100 
338,897 181,784 101,759,507 
1,211,700 1,208,000 
1,222,310 1,202,657 
939,000 964,000 
960,670 980,679 
(-)1,337 110,000 - 
4,588 102,184 17,545 
2,060,109 2,266,800 1,816,500 
1,226,952 3,254,200 1,838,950 
(-)1,960 
5,721 
6,126,75618 
6,094,19018 
5,059,73218 
5,047,79418 
- 27,790,438 
3,568 27,790,436 
1,563,600 17,915,83618 
1,586,603 17,380,29518 
- 20,522,08413 
- 20,510,642 
881,500 745,300 844,000 841,000 10,249,22618 
794,558 1,037,452 843,990 900,650 10,206,05818 
- - - - 6,602,737 
-.- - - 6,602,73714 
1,059,315 1,011,100 762,000 859,000 11,479,56818 
583,762 1,464,428 788,253 848,855 11,364,96618 
- - - - 49,521,12115 
-- - - 49,521,121 
1,926,412 1,825,300 2,087,100 1,838,800 16,786,05818 
1,244,780 2,428,338 2,093,703 1,891,769 16,640,33218 
(-)18,411 
(-)588 
- 42,952,938 
- 42,952,93816 
2,609,300 2,078,000 2,079,900 2,484,600 29,447,88018 
1,973,166 2,807,910 2,035,349 2,471,637 29,002,37518 
- - - - 35,731,626 
- - - - 35,731,626 
1,829,000 885,600 1,736,500 1,541,600 20,704,69018 
1,479,911 1,379,767 1,744,716 1,534,545 20,641,35618 
Excludes $47,309 receipts from reconveyance of land 
deposited to miscellaneous receipts. 
2 Excludes $322,346 receipts from reconveyance of land 
deposted to miscellaneous receipts. 
a Excludes $1,422,848 expended for new work from contributed 
funds, including $22,848 "Contributed Funds Other" for installation 
and operation of gages for leakage study. 
4 Includes $1,378,486 for Code 711, $52,808 for Code 713, and 
$399,739 accelerated Public Works Act funds. Excludes 
$1,711,200 contributed funds. 
5 Includes $1,376,322 for Code 711, $52,808 for Code 713, and 
$399,739 accelerated Public Works Act funds. Excludes $4,137 
reimbursed in Fiscal Year 1973. 
16-17

TABLE 16-A 
FORT WORTH, TEXAS DISTRICT 
COST AND FINANCIAL STATEMENT 
6 Claim Northeast Texas Municipal Water District $16,546. 
Three payments of $12,410 less real estate charges of $1,325, 
making a total of $2,811 reimbursed in Fiscal Year 1972, Fiscal 
Year 1973, and Fiscal Year 1974. 
7 Excludes $146,795 receipts from reconveyance of land 
deposited to miscellaneous receipts, and $2,040,026 for new work 
expended from contributed funds. 
8 Excludes $105,079 expended from contributed funds. 
9 Excludes receipts from reconveyance of land of $426,606 
which were deposted to miscellaneous receipts, and $3,676,661 
for new work expended from contributed funds. 
10 Includes $130,000 under appropriation 96X5125. 
11 Excludes $300,000 expended from contributed funds. 
12 Excludes $3,000,000 expended from contributed funds. 
13 Includes receipts from disposals and revocation of funds 
related thereto. 
14 Excludes $2,000,000 contributed funds expended. 
15iEsx cludes $2,750,000 expended for contributed funds. 
16 Excludes $188,282 receipts from reconveyance of lands 
deposited to miscellaneous receipts. 
17Includes funds ($12,991,762) provided by the Jobs Act (PL 
98-8, dated March 24, 1983) for projects listed in Table 16-F, FY 
85 Annual Report. 
18 Beginning Fiscal Year 1985 data shown on Table A includes 
Special Recreation Use Fees. Data for previous fiscal years have 
been changed to conform to the new procedure. 
16-18

TABLE 16-B 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
2. 
3. 
4. 
Mar. 2, 1945 
Sep. 3, 1954 
Aug. 3, 1955 
Mar. 2, 1945 
Oct. 27, 1965 
Jul. 24, 1946 
Jul. 24, 1946 
Jul. 24, 1946 
Aug. 13, 1968 
Mar. 31, 1960 
Jul. 24, 1946 
Sep. 3, 1954 
Mar. 2, 1945 
Dec. 31, 1970 
Jun. 22, 1936 
AQUILLA LAKE, TX 
Construction of a dam on Aquilla Creek, about 6.8 miles 
southwest of Hillsboro, Texas and about 24 miles north 
of Waco, Texas. 
BARDWELL LAKE, TX 
Construction of a dam on Waxahachie Creek about 5 miles 
south of Ennis, Texas. 
BELTON LAKE, TX 
Construction of a dam on the Leon River about 3 miles 
north of Belton, Texas. 
Modification (see Sec. 36 of Text) of the dam to provide for 
generation of hydroelectric power. 
BENBROOK LAKE, TX 
Construction of a dam on the Clear Fork of the Trinity 
River about 10 miles southwest of Fort Worth, Texas. 
BIG SANDY LAKE, TX 
Construction of a dam on Big Sandy Creek about six miles 
northwest of Big Sandy, Texas. 
BOGGY CREEK, TX 
Construction of a concrete trapezoidal channel on Boggy 
Creek beginning just above Webberville Road and 
extending downstream about 2.2 miles to just below Bolm 
Road. From there, a grass lined channel would extend 
further downstream and transition into the natural 
channel at Ed Bluestein Boulevard, a distance of about 
1.7 miles. 
CANYON LAKE, TX 
Construction of a dam on the Guadalupe River about 12 
miles northwest of New Braunfels, Texas. 
COOPER LAKE AND CHANNELS, TX 
Construction of earth-fill dam and reservoir area; channel 
clearing, realignment, and enlargement; enlargement 
and extension of existing levees; construction of appurtenant 
drainage works along main stem of Sulphur River 
above mile 126; channel clearing, realignment, and 
enlargement and levee enlargement and modification of 
appurtenant drainage works on Cuthand Creek below 
mile 24, on Sulphur River below mile 70, except in 
proposed Cooper Reservoir, miles 29 to 42, and on Middle 
Sulphur River below mile 8; channel clearing and 
realignment of Brushy Creek below mile 5; and levee 
enlargement on North Sulphur River between miles 1 
and 5. 
DAM "A" LAKE, TX 
Construction of a dam on the Neches River about 18 miles 
west of Jasper, Texas. 
ELM FORK FLOODWAY, TX 
Realignment and enlargement of the Elm Fork of the 
Trinity River and Denton Creek, and a parallel levee 
system from the existing Dallas levee system upstream 
to near the Dallas and Denton county lines. 
FERRELLS BRIDGE DAM-LAKE O' THE 
PINES, TX 
Provides for construction of an earth-fill dam and reservoir 
area. 
GRAND PRAIRIE LANDFILL, TX 
Construction of a cutoff channel to eliminate an oxbow in 
the West Fork of the Trinity River. 
GRAND PRAIRIE, MEYERS RD, TX 
Slope Restoration with riprap side slopes along streambank 
of West Fork Trinity River, adjacent to Meyers 
Road. 
16-19 
S. Doc. 52, 90th Cong., 
1st Sess. 
H. Doc. 424, 82nd Cong., 
2nd Sess. 
H. Doc. 88, 81st Cong., 
1st Sess. 
H. Doc 535, 81st Cong., 
2nd Sess. 
H. Doc. 403, 77th Cong., 
1st Sess. 
H. Doc. 429, 91st Cong., 
2nd Sess. 
Flood Control Act 
of 1936 (PL 738) 
H. Doc. 247, 76th Cong., 
1st Sess. 
H. Doc. 488, 83rd Cong., 
2nd Sess. 
S. Doc. 98, 76th Cong., 
1st Sess. 
H. Doc. 276, 89th Cong., 
1st Sess. 
H. Doc. 602, 79th Cong., 
2nd Sess. 
Flood Control Act of 
1946 
Flood Control Act of 
1946 
5. 
6. 
7. 
8. 
9. 
36. 
10. 
11. 
12. 
13.

TABLE 16-B 
See Date 
Section Auth 
in Text Act 
FORT WORTH, TEXAS DISTRICT 
AUTHORIZING LEGISLATION 
)rizing 
Project and Work Authorized 
14. 
15. 
16. 
17. 
18. 
Mar. 2, 1945 
Aug. 18, 1941 
Oct. 27, 1965 
Mar. 2, 1945 
Oct. 23, 1962 
Mar. 7, 1974 
Mar. 2, 1945 
Aug. 13, 1968 
Sep. 3, 1954 
Dec. 31, 1970 
Aug. 18, 1941 
Sep. 3, 1954 
Oct. 27, 1965 
Mar. 2, 1945 
Mar. 2, 1945 
Sep. 3, 1954 
Sep. 3, 1954 
Jan. 3, 1975 
Sep. 3, 1954 
GRAPEVINE LAKE, TX 
Construction of a dam on Denton Creek, a tributary of the 
Trinity River, about 20 miles northwest of Dallas, Texas. 
HORDS CREEK LAKE, TX 
Construction of a dam on Hords Creek, a tributary of 
Pecan Bayou, near the city of Coleman, Texas. 
JOE POOL LAKE, TX 
Construction of a dam on Mountain Creek, adjacent to the 
city limits of Grand Prairie, Texas, about 3 miles above 
the existing Mountain Creek Dam. 
LAVON LAKE, TX 
Construction of a dam on the East Fork of the Trinity 
River about 22 miles northeast of Dallas, Texas. 
LAVON LAKE MODIFICATION AND EAST FORK 
CHANNEL IMPROVEMENT, TX 
Enlarge Lavon Dam and enlargement and realignment of 
the lower 25 miles of the East Fork of the Trinity River, 
including rehabilitation of existing levees. 
Improvement of Collin County Road 115. 
LEWISVILLE DAM, TX 
Construction of a dam on the Elm Fork of the Trinity River 
near the city of Lewisville, Texas. 
MILLICAN LAKE, TX 
Construction of a dam on the Navasota River about seven 
miles north of Navasota, Texas. 
NAVARRO MILLS LAKE, TX 
Construction of a dam on Richland Creek, a tributary of 
the Trinity River, about 16 miles southwest of Corsicana, 
Texas. 
Alteration of FM Highway 3164 in Wolf Creek Park. 
O. C. FISHER DAM AND LAKE, TX 
Construction of a dam on the North Concho River just 
above San Angelo, Texas. 
PROCTOR LAKE, TX 
Construction of a dam on the Leon River about 8 miles 
northeast of Comanche, Texas. 
RAY ROBERTS LAKE, TX 
Construction of a dam on the Elm Fork of the Trinity River 
between Sanger and Aubrey, Texas, about 30 miles 
upstream from the existing Lewisville Dam. 
ROCKLAND LAKE, TX 
Construction of a dam on the Neches River approximately 
three miles west of Rockland, Texas. 
SAM RAYBURN DAM AND RESERVOIR, TX 
Construction of a dam on the Angelina River about 10 
miles northwest of Jasper, Texas. 
SAN ANTONIO CHANNEL IMPROVEMENT, TX 
Channel improvement of the San Antonio River and 
tributaries in and near the city of San Antonio, Texas. 
SAN GABRIEL RIVER PROJECT, TX 
Construction of: (1) a dam (Granger Dam and Lake) on the 
San Gabriel River about 7 miles east of Granger, Texas, 
(2) a dam (North Fork Lake) on the north Fork of the 
San Gabriel River about 3.5 miles northwest of 
Georgetown, Texas and (3) a dam (South Fork Lake) on 
the South Fork of the San Gabriel River about 3 miles 
southwest of Georgetown, Texas. 
SOMERVILLE LAKE, TX 
Construction of a dam on Yegua Creek about 2 miles south 
of Somerville, Texas. 
16-20 
Documents 
H. Doc. 403, 77th Cong., 
1st Sess. 
H. Doc. 370, 76th Cong., 
1st Sess. 
H. Doc. 276, 89th Cong., 
1st Sess. 
H. Doc. 533, 78th Cong., 
2nd Sess. 
H. Doc. 554, 87th Cong., 
2nd Sess. 
H. Doc. 403, 77th Cong., 
1st Sess. 
H. Doc. 341, 90th Cong., 
2nd Sess. 
H. Doc. 498, 83rd Cong., 
2nd Sess. 
H. Doc. 315, 76th Cong., 
1st Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess. 
H. Doc. 276, 89th Cong., 
1st Sess. 
S. Doc. 98, 76th Cong., 
1st Sess. 
S. Doc. 98, 76th Cong., 
1st Sess. 
H. Doc. 344, 83rd Cong., 
2nd Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess., and 
H. Doc. 591, 87th Cong., 
2nd Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess. 
19. 
20. 
21. 
22. 
23. 
24. 
37. 
38. 
25. 
26. 
27.

TABLE 16-B 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Sep. 3, 1954 
Mar. 2, 1945 
Mar. 2, 1945 
Oct. 27, 1965 
Jul 18,1968 
Sep. 3, 1954 
Aug. 18, 1941 
Jul. 24, 1946 
28. 
39. 
40. 
STILLHOUSE HOLLOW DAM, TX 
Construction of a dam on the Lampasas River about 5 
miles southwest of Belton, Texas. 
TOWN BLUFF DAM-B. A. STEINHAGEN LAKE, TX 
Construction of a dam on the Neches River near Jasper, 
Texas. 
TOWN BLUFF HYDROPOWER, TX 
Construction of two units at 3,000 kilowatts each of 
hydroelectric power generating facilities connected with 
Town Bluff Dam. B.A. Steinhagen Lake, Texas. 
TRINITY RIVER PROJECT, TX 
Construction of Tennessee Colony Dam located at river 
mile 339.2 on the Trinity River about 16 miles west of 
Palestine, Texas; a multiple purpose channel from the 
Houston, Texas ship channel to Fort/ Worth, Texas; a 
distance of approximately 363 miles, an extension of the 
existing Dallas, Texas, Floodway downstream approximately 
9.0 miles; a realignment and enlargement of the 
West Fork of the Trinity River from the mouth of the 
West Fork to the existing Fort Worth, Texas, Floodway, 
a distance of approximately 31 miles; and water 
conveyance facilities involving construction of about 98 
miles of pipeline from Tennessee Colony Lake to the 
existing Benbrook Lake. 
WACO LAKE, TX 
Construction of a dam on the northwest edge of Waco, 
Texas, below the confluence of the North, South, and 
Middle Bosque Rivers. 
WHITNEY LAKE, TX 
Construction of a dam on the Brazos River, about 19 miles 
southwest of Hillsboro, Texas. 
Raise the power pool 13.0 feet. 
WRIGHT PATMAN DAM AND LAKE, TX 
Construction of an earth-fill dam and reservoir. 
16-21 
H. Doc. 535, 81st Cong., 
2nd Sess. 
S. Doc. 98, 76th Cong., 
1st Sess. 
S. Doc. 98, 76th Cong., 
1st Sess. 
H. Doc. 276, 89th Cong., 
1st Sess., and 
H. Doc. 364, 90th Cong., 
2nd Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess. 
H. Doc. 390, 76th Cong., 
1st Sess. 
H. Doc. 602, 79th Cong., 
2nd Sess. 
1. 
29. 
41. 
30.

TABLE 16-C 
FORT WORTH, TEXAS DISTRICT 
OTHER AUTHORIZED FLOOD CONTROL 
(See Section 33 of Text) 
PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Big Fossil Creek, TX3 1969 - - 
Big Spring, TX2 1979 - - 
Brownwood Channel Improvement, TX1 - - - 
Carl L. Estes Dam and Lake, TX2 1979 - - 
Duck Creek Channel Improvement, TX4 1983 - - 
Fort Worth Floodway (Clear Fork), TX3 1971 - - 
Fort Worth Floodway (West Fork), TX3 1971 - - 
Greenville, TX3 1983 - - 
Lake Brownwood Modification, TX4 1983 - - 
Lake Fork Lake, Sabine River, TX4 - - - 
Navasota Lake, Navasota River, TX4 - - - 
Pecan Bayou Lake, Pecan Bayou, TX4 - - - 
Plainview Local Flood Protection Project, TX4 1979 - - 
Roanoak Lake, TX' 1979 - - 
Rutledge Hollow Creek Channel Improvement, Poteet, TX3 1969 - - 
Zacate Creek Channel, TX3 1983 - - 
Calloway Branch, Hurst, TX3 1986 - - 
' Deauthorized 1 Nov 81. 
2 Inactive. 
3 Completed. 
4 Recommended for deauthorization, H.R. 3678, August 23, 1983, 98th Congress, 1st Session. 
INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
TABLE 16-D (See Section 31 of Text) 
Location Dates of Inspection 
Big Fossil Creek Sep. 26, 1986 
Dallas Floodway Jul. 31, 1986 
East Fork Sep. 4, 1986 
Fort Worth Floodway Sep. 11, 1986 
Greenville Jan. 23, 1986 
Irving Floodway Jul. 28, 1986 
Munday Nov. 30, 1983 
Pleasanton Mar. 18, 1986 
Poteet Aug. 14, 1985 
San Antonio Floodway Jun. 24, 1986 
Sulphur River Levees Aug. 23, 1985 
Wheeler Creek Apr. 16, 1986 
Zacate Creek Mar. 19, 1986 
16-22

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
TABLE 16-E (See Section 34 of Text) 
Project Cost 
Burton Creek, Bryan, TX 
California Creek, Hamlin, TX 
Calloway Branch, Hurst, TX 
Elm Fork, Gainsville, TX 
Hickory Creek, Balch Springs, TX 
Lorean Branch, Hurst, TX 
Pecan Creek, Gainesville, TX 
Walnut Creek, Sequin, TX 
Buttercup Creek, Cedar Park Hill, TX 
Delaware Creek, Dallas, TX 
Little Walnut Creek, Austin, TX 
Lower Walnut Creek, Austin, TX 
Singing Hills Creek, Watauga, TX 
South Mesquite, Mesquite, TX 
Walnut Creek Tribs, Austin, TX 
$ 75,025 
11,162 
1,254,064 
138,648 
4,630 
181,223 
16,699 
2,854 
7,500 
77,078 
63,491 
39,117 
29,913 
10,717 
42,640 
16-23

ALBUQUERQUE, NM, DISTRICT* 
The district comprises watershed of Canadian River and 
tributaries and the watershed of Arkansas River and tributaries 
in Colorado and New Mexico; the watershed of Rio 
Grande and tributaries including Pecos River and its tributaries 
upstream of Amistad Lake; and watershed of 
Mimbres River and its tributaries in New Mexico. 
Note: The district watershed boundaries were revised in 
July 1982 to include all of New Mexico west of the Texas 
state line and the southwest corner of Colorado west of 
the Kansas state line. 
IMPROVEMENTS 
Flood Control Page 
1. Albuquerque Diversion Channels, NM .... 17-1 
2. Conchas Lake, NM ...................... 17-2 
3. ElPaso, TX .......................... 17-2 
4. John Martin Reservoir, CO........... .... 17-3 
5. Rio Grande Basin, NM.................. 17-3 
5A. Abiquiu Dam, NM ...................... 17-4 
5B. Cochiti Lake, NM ..................... 17-4 
'5C. Galisteo Dam, NM....................... 17-4 
5D. Jemez Canyon Dam, NM ................. 17-5 
5E. Rio Grande Floodway, NM................ 17-5 
5F. Truth or Consequences 
(Hot Springs) Unit, NM................... 17-5 
6. Santa Rosa Dam and Lake, NM ........... 17-6 
Flood Control 
1. ALBUQUERQUE DIVERSION 
CHANNELS, NM 
Location. In an area which comprises watersheds of 
ephemeral streams entering a 15-mile reach of Rio Grande 
from the east at Albuquerque, NM, and vicinity. Combined 
drainage area of tributaries is about 276 square 
miles. Sandia range of the Rocky Mountains, which is 
about 12 miles east of Rio Grande, forms eastern border 
of watersheds. Crest of mountain range rises more than 
a mile over river to elevation of 10,692 feet above mean 
sea level. (See Geological Survey Map, Albuquerque, NM, 
quadrangle, scale 1:62,500.). 
Existing project. Plans for improvement consist of 
north and south diversion channels on high ground east 
7. Trinidad Lake, CO ...................... 17-6 
8. Two Rivers Dam, NM .................... 17-7 
9. Inspection of completed flood 
control projects........................ 17-7 
10. Scheduling flood control 
reservoir operations .................... 17-7 
11. Other authorized flood 
control projects........................ 17-8 
12. Flood control work under 
special authorizations.................. 17-8 
General Investigations 
13. Surveys .................... .... ........ 
14. Collection and study of basic data ......... 
17-8 
17-8 
of and parallel to valley. Channels are designed to carry 
floods equal in magnitude to standard project flood from 
all tributaries. For description of complete improvement 
and authorizing legislation see page 17-15 of Annual 
Report for FY 1973. 
Local cooperation. Section 2 Flood Control Act of 1938 
applies. For details of local cooperation requirements see 
page 17-2 of Annual Report for FY 1973. 
Operations and results during fiscal year. The North 
Diversion Channels prevented $3,769,400 in flood damages 
during FY 1986. The estimated total accumulated 
flood damages prevented were $49,997,600. Peak flood 
flows recorded during FY 1986 were North Diversion 
Channel near Alameda, 6,920 c.f.s. on October 9, 1985, 
and none were recorded for the South Diversion Channel. 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and also appear at the 
end of this chapter. 
17-1-

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Condition at end of fiscal year. Construction of the 
north and south diversion channels began in March 1965, 
and was completed in March 1972. The South Diversion 
Channel is in good condition and well maintained by the 
local interests. The North Diversion Channel has experienced 
severe arching and cracking of the concrete lined 
portion. Construction to correct this problem is scheduled 
to initiate in FY 1987 and complete in FY 1988. 
2. CONCHAS LAKE, NM 
Location. Dam is in San Miguel County, NM, on 
Canadian River, about one-fourth mile downstream from 
confluence of Canadian and Conchas Rivers. (See Geological 
Survey State map of New Mexico, scale 1:500,000, 
and Geological Survey topographic map. Tucumcari quadrangle, 
scale 1: 125,000). 
Existing project. A concrete gravity main dam section 
1,250 feet long with a maximum height of 200 feet 
above streambed located in Canadian River Canyon together 
with earth dikes on each side having an overall 
length of about 3.7 miles. Main section contains conduits 
in its base for release of water to maintain low flows and 
for drainage of reservoir, and an overflow, ungated spillway 
300 feet long. Earth dikes vary in height up to 100 
feet and north dike contains a concrete ogee-type emergency 
spillway 3,000 feet long. Reservoir has a gross storage 
capacity of 529,000 acre-feet (198,900 for flood control, 
259,600 for water conservation and irrigation, and 70,500 
dead storage). Dam controls 7,409 square miles of drainage 
area. (See page 17-16 of Annual Report of 1973 for 
authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. Operation 
of reservoir continued. Reservoir was operated for storage 
of floodwaters and releases for irrigation purposes. $162,800 
in sediment damages were prevented during FY 1986 
while no flood damages were prevented. Estimated total 
accumulated flood and sediment damages prevented by 
the project through FY 1986 were $2,614,600. Estimated 
irrigation benefits for FY 1986 were $132,300. Estimated 
total accumulated irrigation benefits through FY 1986 
were $8,937,100. Pool elevation at start of FY 1986 was 
4,194.44 feet with corresponding storage of 271,496 acrefeet. 
Total releases for reporting period were 73,885 acrefeet. 
Releases of 62,436 acre-feet were made to Arch 
Hurley Conservancy District and 2,516 acre-feet to Bell 
Ranch. Pool elevation on September 30, 1986, was 
4,196.34 feet with corresponding storage of 287,458 acrefeet. 
Sediment deposition during the fiscal year was 1,454 
acre-feet. 
Condition at end of fiscal year. Existing project was 
essentially complete in 1940. Reservoir and appurtenances 
are in good condition and in operation. Irrigation of some 
lands under project was begun in November 1945. A cost 
sharing agreement between the Government and the State 
of New Mexico for additional Recreation Development at 
Conchas Lake was approved in August 1977. Costs of the 
facilities are 50 percent State of New Mexico and 50 percent 
Federal. Construction of recreation facilities was initiated 
in FY 1978 and completed in FY 1983. 
3. EL PASO, TX 
Location. At El Paso, El Paso County, TX, which is on 
left bank of Rio Grande in the reach that forms part of 
international boundary between United States and Republic 
of Mexico. (Geological Survey map for El Paso, TX; New 
Mexico quadrangle, scale 1:250,000.) 
Existing project. Consists of a single-purpose flood control 
system of detention dams, diversion dikes, conduits 
and channels to collect, regulate and discharge arroyo runoff 
into Rio Grande. Runoff from tributary arroyos on 
eastern, southern, and western slopes of adjacent Franklin 
Mountains often inundates sections of city and its outlying 
suburban developments. Project is divided into three 
independent elements: Northwest area, Central area, and 
Southeast area. The project plan satisfies the 1933 U.S. 
and Mexico agreement on limited tributary discharge into 
the Rio Grande in El Paso, Texas. (See Table 17-B for 
authorizing legislation.) 
Local cooperation. Section 2 Flood Control Act of June 
28, 1938 applies. 
Operations and results during fiscal year. Flood control 
dams in operation during FY 1986 and dates of completion 
of construction are as follows: Northgate and Range 
Dams (February 1973); Sunrise and Mountain Park Dams 
(October 1974); and Pershing Dam (March 1977); Fort 
Bliss Diversion Channel (November 1978); Oxidation Pond 
and Buena Vista Diversion and Oxidation Pond Outlet 
Conduit (November 1980); Mulberry and Thorn Drive 
Dams (June 1982); Mesa Dam (September 1982); McKelligon 
Canyon Dam (October 1982); Keystone Dam (September 
1983); Keystone Outlet Conduit (March 1984); 
Highway Diversion Channel (May 1985); Dam Safety 
Assurance Program to the existing Range.and Northgate 
Dams (May 1986) and Borderland Diversion Channel (September 
1986). During FY 1986 flood flows and flood control 
storage were minimal; however, damages which would 
have resulted from these flows were prevented. The estimated 
total flood damages prevented since completion of 
Northgate and Range Dams in 1973 through FY 1986 
were $22,700. 
Condition at end of fiscal year. Construction has temporarily 
ended in the Central Area. Remaining projects 
include the Fillmore-Van Buren Dams System. The Central 
Area of the project is for all practical purposes 100 
percent complete. 
The Northwest Area is 100 percent complete. 
The Reconnaissance Report on the Southwest Area was 
completed in December 1982 and the preparation of the 
General Design Memorandum is approximately 75 percent 
complete. 
4. JOHN MARTIN RESERVOIR, CO 
Location. On Arkansas River 1,159 miles upstream 
from its mouth, 300 miles downstream from its source, 
in Bent County, about 18 miles upstream from city of 
Lamar, CO. (See Geological Survey maps for Lamar and 
Las Animas, CO quadrangles, scale 1:125,000.) 
Existing project. A concrete and earthfill structure 
about 2.6 miles long with a maximum height of 106 feet 
above streambed and an overflow, gated spillway 1,174 feet 
long. 'Ibtal capacity of reservoir at spillway crest is 615,500 
17-2

ALBUQUERQUE, NM, DISTRICT 
acre-feet (270,200 for flood control and 345,300 for conservation 
and recreation storage). Reservoir controls a contributing 
drainage area of 18,130 square miles and is 
operated as a unit of coordinated reservoir system for flood 
control in Arkansas River Basin. Public Law 89-298 modified 
the act of June 22, 1936 (49 Stat. 1570) to authorize 
10,000 acre-feet of reservoir flood control storage space 
for fish and wildlife and recreation purposes. For detail 
of completed improvement and authorizing legislation see 
page 17-16 of Annual Report for FY 1973. 
Local cooperation. Section 3 Flood Control Act of June 
22, 1936, applies. 
Operations and results during fiscal year. Routine 
maintenance and operation continued. Regulation of conservation 
storage continued under rules and regulations 
of Arkansas River Compact. No flood damages were prevented 
during FY 1986; however, $136,500 sediment damages 
were prevented. Estimated total flood and sediment 
damages prevented by project through FY 1986 were 
$75,435,800. Estimated irrigation benefits for FY 1986 
were $623,400. Estimated total accumulative irrigation 
benefits were $22,688,600. Maximum pool elevation of 
3,850.29 feet with corresponding storage of 337,136 acrefeet 
occurred on March 4, 1986. Total releases for FY 1986 
were 253,812 acre-feet. Releases attributed to irrigation 
benefits amounted to 158,631 acre-feet. Sediment deposition 
was 1,219 acre-feet for FY 1986. 
Condition at end of fiscal year. Storage and operation 
of reservoir for irrigation began in March 1943. Reservoir 
and appurtenances are in good condition and in operation. 
5. RIO GRANDE BASIN, NM 
Location. Improvements are on Rio Grande and tributaries 
in New Mexico. More definite locations and descriptions 
of individual projects are in following paragraphs 
and individual reports by projects. 
Existing project. Flood Control Act of 1948 authorized 
flood control phase of comprehensive plan of development 
of water resources of Rio Grande basin in New 
Mexico (H. Doc. 243, 81st Cong., 1st sess.) with exception 
of Chiflo Dam and Reservoir and spillway gate structure 
at Chamita Dam. Although recommended, Chiflo 
Dam and Reservoir was deleted from authorized plan. It 
was excluded without prejudice to future consideration 
by Congress. It was requested at that time, by States of 
Colorado and Texas, that project be deferred for restudy 
regarding required storage and methods of operation. By 
same act, Congress also authorized for construction irrigation 
phase of comprehensive plan as recommended by 
Bureau of Reclamation (H. Doc. 653, 81st Cong., 2nd sess.). 
The act also stipulated that work should be prosecuted 
in accordance with joint agreement approved by Secretary 
of the Army and Acting Secretary of the Interior on 
November 21, 1957. In addition, under that agreement 
Bureau of Reclamation was given responsibility for construction, 
operation, and maintenance of channel rectification, 
and drainage rehabilitation and extension phases 
of unified plan of improvement. Authority for Chamita 
Dam and Reservoir was abrogated when Cochiti Dam and 
Reservoir was authorized. (See Table 17-B for authorizing 
legislation and Table 17-C for existing projects.) 
All operations and costs for projects in authorized plan 
are in individual reports on the following pages. 
5A. ABIQUIU DAM, NM 
Location. Project is one unit of flood control phase of 
comprehensive plan for Rio Grande and tributaries, New 
Mexico. Abiquiu Dam is on Rio Chama near town of Abiquiu, 
NM, about 32 miles upstream from confluence of 
Rio Chama and Rio Grande. (See Geological Survey Map 
for plan and profile of Rio Chama, NM, from mouth to 
mile 103, sheet 1, and Army Map Service, Aztec, NM; Colorado 
NJ 13-10, scale 1:250,000.) 
Existing project. An earthfill dam 1,540 feet long, 325 
feet high, with a 12-foot diameter controlled outlet, and 
an uncontrolled spillway in a natural saddle about one 
mile north of left abutment. Reservoir provides 565,000 
acre-feet of flood control and sediment storage. Total capacity 
at spillway crest is 1,212,000 acre-feet. For detail 
description of completed improvements and authorizing 
legislation see Annual Report of 1973. A major rehabilitation 
project was completed in September, 1980 and the 
recreation facilities were completed in FY 1981. 
Local cooperation. None required. 
Operations and results during fiscal year. Routine 
maintenance and operation continued. Storage and flows 
were regulated in accordance with Section 203, Flood Control 
Act of 1960. On October 1, 1985, the pool elevation 
was 6,244.83 feet. The maximum pool (6,246.74 feet) and 
storage (319,161 acre-feet) occurred on June 27, 1986. On 
September 30, 1986, the pool elevation was 6,245.38 feet 
with a corresponding storage of 311,790 acre-feet. There 
was 2,161 acre-feet of sediment deposition during FY 1986. 
There were $34,023,300 in flood damages prevented during 
FY 1986. 
Sediment damages prevented were $242,000. Accumulated 
flood and sediment damages prevented by the project 
since completion were $193,293,300 through FY 1986. 
Condition at end of fiscal year. Project was placed 
in operation in February 1963. Project structures are in 
good condition and in operation. 
5B. COCHITI LAKE, NM 
Location. Dam is at river mile 340 on Rio Grande 
(river mile 0 being at intersection of New Mexico-Texas 
State line with international boundary at El Paso, TX), 
near Pueblo de Cochiti, which is about 50 miles upstream 
from Albuquerque, NM. (See Geological Survey Maps, 
Cochiti Dam, NM, quadrangle and Santo Domingo Pueblo, 
NM, quadrangle, scale 1:24,000.) 
Existing project. Consists of an earthfill dam about 
5.4 miles long with a maximum height of 251 feet above 
streambed. Project extends generally in an east-west line 
across Rio Grande to a point about 2 miles east of Rio 
Grande and then southward across Santa Fe River. An 
uncontrolled spillway with a 460-foot-long ogee-weir and 
a 160-foot notch 10.5 feet deep in the center is at the 
embankment on south side of Santa Fe River. Operational 
releases for flood control and irrigation are made through 
a 3-barrel gated conduit in left abutment on Rio Grande. 
Reservoir has a storage capacity of 492,500 acre-feet for 
flood control, 103,800 acre-feet for sediment and 45,700 
acre-feet for recreation within the sediment space, for a 
total of 596,300 acre-feet. The project controls flood waters 
from a 11,695 square mile drainage area. For more im- 
17-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
provements details see page 17-7 of Annual Report for 
1980. See page 17-14 of fiscal year 1981 Annual Report 
for Authorizing Legislation. 
Local cooperation. None required. 
Operations and results during fiscal year. The project 
was completed in June 1975. On October 1, 1985, the 
pool elevation was 5,387.36 feet with a corresponding storage 
of 178,540 acre-feet. The maximum pool elevation was 
5,417.32 feet with a storage of 300,997 acre-feet on July 
3, 1986. On September 30, 1986, the pool elevation was 
5,330.67 feet with a corresponding storage of 51,158 acrefeet. 
There was 1,756 acre-feet of sediment deposition during 
FY 1986. There were $50,994,900 in flood damages 
prevented during FY 1986. Sediment damages prevented 
were $196,700. Accumulated total damages prevented are 
$194,507,900. 
Conditions at end of fiscal year. The dam and appurtenances 
were placed in operation in 1975. The Cochiti 
Recreation area was completed in 1976, with the Visitors 
Center completion in 1977. The Tetilla Peak Recreation 
area was re-advertised and awarded in 1980 and completed 
in 1981. Project structures are in good condition and in 
operation. 
5C. GALISTEO DAM, NM 
Location. Dam is at river mile 12 on Galisteo Creek, 
a tributary of Rio Grande. Definite project site is about 8 
miles upstream of project document site. Reservoir will 
extend upstream from dam for about 4 miles to near village 
of Waldo, NM. (See Geological Survey Map, San Pedro 
1, NM quadrangle, scale 1:24,000.) 
Existing project. Consists of an earthfill dam 2,820 
feet long with a maximum height of 158 feet above streambed. 
The outlet works consist of a 10-foot diameter uncontrolled 
outlet with a discharge capacity of 4,980 cubic feet 
per second with pool at spillway crest elevation. The spillway 
is a broad crested weir 250 feet long in right abutment. 
The flood control storage is 89,000 acre-feet. For more 
details of completed improvements and authorizing legislation 
see page 17-17 of Annual Report for 1973. 
Local cooperation. None required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Operation of the 
project began on October 11, 1970. The reservoir was 
empty on October 1, 1985. No storage occurred during 
FY 1986. Peak inflow was 119 c.f.s. and maximum outflow 
was 119 c.f.s. There was 44 acre-feet of sediment deposition 
during the year and the reservoir was empty on September 
30, 1986. Sediment damages prevented during the 
FY were $4,900 totaling $110,800 through FY 1986. 
Condition at end of fiscal year. Project was placed 
in operation in October 1970. Project structures are in 
good condition and in operation. 
5D. JEMEZ CANYON DAM, NM 
Location. In Sandoval County, NM, on Jemez River 
about 2 miles upstream from confluence of Jemez River 
and Rio Grande, about 5 miles northwest of Bernalillo, 
NM (See Geological Survey map for Bernalillo quadrangle, 
scale 1:125,000.) 
Existing project. An earthfill dam 780 feet long with 
a maximum height of 135 feet above streambed, and offchannel 
uncontrolled saddle spillway 400 feet wide, and 
a 13-foot diameter gated outlet in left abutment with discharge 
capacity of 8,340 cubic feet per second with pool 
at spillway crest elevation. Reservoir has a capacity of 
106,100 acre-feet (73,000 acre-feet for flood control and 
33,100 acre-feet for sediment control). For more detailed 
description of completed improvements and authorizing 
legislation see page 17-17 of Annual Report for 1973. 
Local cooperation. None required. 
Operations and results during fiscal year. On October 
1, 1985, the pool elevation was 5,194.67 feet with a 
corresponding storage of 26,621 acre-feet. The maximum 
pool elevation was 5,203.43 feet with a storage of 39,328 
acre-feet on May 13, 1986. On September 30, 1986 the 
pool elevation was 5,197.92 feet with a corresponding storage 
of 31,089 acre-feet. The reservoir was regulated for 
sediment control during FY 1986. Sediment deposition 
during FY 1986 was 615 acre-feet. There were $1,325,400 
in flood damages prevented during FY 1986. Sediment 
benefits during FY 1986 were $68,900. Estimated total 
accumulated flood and sediment damages prevented by 
the project through FY 1986 were $9,847,300. 
Condition at end of fiscal year. Project was placed 
in operation in October 1953. Project structures are in 
good condition and in operation. 
5E. RIO GRANDE FLOODWAY, NM 
Location. Project is one unit of flood control phase of 
comprehensive plan of improvement for Rio Grande Basin 
in New Mexico. It is on the Rio Grande and covers a section 
of the river commencing near Truth or Consequences 
(formerly Hot Springs) at about river mile 123 and extends 
upstream to Espanola, NM, about river mile 394. (See 
Table 17-D on Rio Grande Floodway.) 
Existing project. Consists of flood protection and major 
drainage improvements by channel rectification, levee 
enlargement and construction, and bank stabilization 
work where needed to protect levees. Construction of project 
is a joint undertaking by Bureau of Reclamation and 
the Corps. Portions to be done by Corps will consist of levee 
enlargement, construction, and bank protection work, with 
channel-rectification and drainage-rehabilitation work the 
responsibility of Bureau of Reclamation. Levees constructed 
by local interests exist through reach of river involved, 
but are not uniform as to grade, section, or standard of 
construction, and in many places are threatened by meandering 
river. (See Table 17-D on existing project and Table 
17-B for authorizing legislation.) 
Local cooperation. In addition to usual requirements, 
local interests are responsible for all highway, bridge, and 
public utility relocations or replacements required in construction 
of project. Local interests will also be required 
to comply with requirements of Section 221. 1970 Flood 
Control Act and PL 91-646 Uniform Relocation Assistance 
Act of 1970. Total costs for all requirements for completed 
Albuquerque unit under terms of project authorization 
were $75,000. There were no non-Federal costs in connection 
with construction of Cochiti to Rio Puerco unit of 
floodway. Espanola Valley unit is in the deferred category. 
17-4

ALBUQUERQUE, NM, DISTRICT 
The city of Espanola or Santa Clara Pueblo has not given 
indication they plan positive action to solve the flooding 
problem. For more details see page 17-8 of Annual Report 
for 1980. 
Operations and results during fiscal year. There 
were $210,000 in flood damages prevented by the completed 
floodway project during FY 1986. Estimated total 
accumulated flood damages prevented by the floodway project 
through FY 1986 amounted to $42,326,800. The peak 
flow of the Rio Grande through the middle valley was 5,190 
c.f.s. at Albuquerque on August 11, 1986. The peak at 
San Acacia was 7,060 c.f.s. on May 14, 1986. 
Condition at end of fiscal year. Construction of Albuquerque 
unit and Cochiti to Rio Puerco units of Rio Grande 
Floodway project is complete. San Acacia to Bosque del 
Apache unit is deferred for restudy. The Truth or Consequences 
(Hot Springs) unit was reclassified to the active 
category on July 18, 1973, based on a letter of intent to 
cooperate from the city of Truth or Consequences dated 
May 31, 1973. The Espanola Valley unit was reclassified 
to deferred category on 17 October 1973. 
5F. TRUTH OR CONSEQUENCES 
UNIT, NM 
Location. Vicinity city of Truth or Consequences, New 
Mexico. 
Existing project. Authorized plan of improvement 
includes 4 miles of 20-foot-high levees with positive seepage 
control, an interior drainage system, and 5 miles of 
diversion channels. The diversion channels would be required 
for control of floods on tributary arroyos at and in 
the vicinity of Truth or Consequences. Estimated Federal 
cost is not available pending project reformulation. (See 
Table 17-B for authorizing legislation.) 
Location cooperation. Section 2 Flood Control Act 
of 1938 applies. 
Letters of intent have been received from the City of 
Truth or Consequences (dated June 8, 1983) and the County 
of Sierra (dated June 8, 1983). 
Operations and results during fiscal year. Preconstruction 
planning was initiated in FY 1979 and continued 
during FY 1986. 
6. SANTA ROSA DAM AND LAKE, NM 
Location. Lake is in Guadalupe County, on Pecos River, 
at river mile 766.4 approximately 7 miles north of Santa 
Rosa, NM (See U.S. Geological Survey map, Corazon, NM, 
sheet, scale 1:125,000.) 
Existing project. Project operation began in November 
1979. Authorized plan of improvement consists of an 
earth and rock fill dam 1,950 feet long and 212 feet maximum 
height abo':e the streambed. Project purposes are 
flood control, irrigation and sediment retention. An unlined, 
open rock cut about 1,000 feet back from the left 
abutment serves as an uncontrolled spillway. The outlet 
works, located in the left abutment, consists of a control 
tower, intake structure with gates, and a 10-foot diameter 
concrete lined tunnel with a terminal flip bucket 
energy dissipater. Storage capacity at the spillway crest 
is 447,100 acre-feet which includes 80,100 acre-feet sediment 
reserve, 200,000 acre-feet irrigation and 167,000 
acre-feet flood control storage. Surface area of the reservoir 
at the spillway crest is 10,685 acres. Contributing 
drainage area at the dam site is 2,434 square miles. 
For a more detailed report of the authorized project 
including the modification to existing Summer Lake see 
page 17-8 of fiscal year 1981 Annual Report. For authorizing 
legislation see page 17-14 of fiscal year 1981 Annual 
Report. 
Local cooperation. In addition to first costs, operation 
and maintenance of both reservoirs will be responsibility 
of Federal Government; however, Carlsbad Irrigation 
District will be required to contribute to operation 
and maintenance costs an annual amount equal to what 
they now pay toward Sumner Lake. Carlsbad Irrigation 
District also has agreed to use Sumner Lake for floodcontrol. 
Because they will realize equivalent benefits from 
storage capacity in Santa Rosa Dam and Lake, they will 
continue to fulfill their repayment obligation. The New 
Mexico Division of Parks will be required to manage the 
recreation facilities. Activities include camping, picnicking, 
boating and hiking. 
For more requirements and details on final approval 
in 1974 for transfer of irrigation storage from Sumner Lake 
to Santa Rosa Dam and Lake (formerly Los Esteros Lake) 
see page 17-5 of Annual Report for 1980. 
Operations and results during fiscal year. The project 
was completed in late 1979 and reservoir operation 
for irrigation was started in March 1980. Pool elevation 
at start of fiscal year was 4,743.02 feet with storage of 
94,811 acre-feet. Total releases for the fiscal year were 
45,182 acre-feet. Pool elevation on September 30, 1986 was 
4,745.90 feet with a storage of 105,371 acre-feet. The maximum 
elevation was 4,746.46 feet with a storage of 107,510 
acre-feet on June 29, 1986. There was 550 acre-feet of sediment 
deposition during the fiscal year. Sediment damages 
prevented during the fiscal year were $65,000. Releases 
attributed to irrigation benefits were 32,460 acre-feet. Irrigation 
benefits for the fiscal year were $113,600 with an 
accumulative total of $1,009,400 through FY 1986. 
Condition at end of fiscal year. Construction contract 
for the recreation area was awarded in September 1979 
and completed in October 1980. Design studies for spillway 
modification were initiated in FY 1979 and construction 
was completed in FY 1982. 
7. TRINIDAD LAKE, CO 
Location. On Purgatoire River about 161 miles above 
its junction with Arkansas River. Project is about 4 miles 
upstream from city of Trinidad, CO. (See Geological Survey 
map. Trinidad, CO, quadrangle, scale 1:24,000.) 
Existing project. Consists of an earthfill dam 6,610 
feet long, with a maximum height of 200 feet above streambed, 
an uncontrolled spillway 1,000 feet wide in left abutment, 
and a 10-foot diameter, gate-controlled conduit in 
right abutment with discharge capacity of 5,870 c.f.s. with 
water surface at top of flood control pool. In 1985, a 3-foot 
high parapet wall on top of the upstream face of the dam 
and a supplemental 700-foot wide rock cut emergency 
spillway located on the right abutment were constructed 
to provide adequate discharge capability and freeboard 
allowance to accommodate the revised probable maximum 
17-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
flood. Reservoir provides for storage of 60,000 acre-feet for 
flood control, 39,000 acre-feet for sediment, 20,000 acrefeet 
irrigation, and 4,500 acre-feet for recreation, a total 
of 123,500 acre-feet. Reservoir controls a drainage area 
of 671 square miles and will be operated for flood and sediment 
control, irrigation, and recreation purposes. For 
authorizing legislation see page 17-14 of fiscal year 1981 
Annual Report. 
Local cooperation. Assurances of local cooperation 
received from City of Trinidad and Purgatoire River Water 
Conservancy District were formally accepted May 11, 
1967, after execution of irrigation repayment contract. For 
complete details of requirements and costs pertaining to 
the execution of the irrigation repayment contract and 
the addition of permanent storage for recreation facilities 
see page 17-9 of fiscal year 1980 Annual Report. 
Operations and results during fiscal year. The reservoir 
was operated for flood control and irrigation releases 
during the fiscal year. On October 1, 1985 the pool elevation 
was 6,172.87 feet with a corresponding storage of 
16,936 acre-feet. The maximum pool elevation was 6,187.69 
feet with a corresponding storage of 26,492 acre-feet on 
July 29, 1986. On September 30, 1986, the pool elevation 
was 6,163.06 feet with a corresponding storage of 11,876 
acre-feet. Sediment deposition during FY 1986 was 450 
acre-feet. Sediment damages prevented during FY 1986 
was $168,300. Accrued sediment benefits are $1,702,100. 
Irrigation benefits for FY 1986 were $118,300. Accrued 
irrigation benefits through FY 1986 were $1,018,000. Irrigation 
releases for the year were 30,105 acre-feet. 
Conditions at end of fiscal year. The project was 
placed in operation in 1977. The recreation facilities were 
completed in 1980. The Dam Safety Assurance Contract 
was awarded in September 1982. Project features are in 
good condition and in operation. 
8. TWO RIVERS DAM, NM 
Location. About 14 miles southwest of Roswell, NM, 
on Rio Hondo and Rocky Arroyo. Rio Hondo is formed at 
confluence of Rio Ruidoso and Rio Bonito, near village of 
Hondo, NM, in foothills region of Sierra Blanca in southeastern 
part of Lincoln County, NM, and flows generally 
easterly to its confluence with Pecos River near Roswell, 
NM (See Geological Survey map, Hondo Reservoir quadrangle, 
scale 1:24,000.) 
Existing project. Diamond "A" Dam is an earthfill 
structure, 4,885 feet long and 98 feet high, with a gated 
outlet. Rocky Dam is an earthfill structure 2,940 feet long 
and 118 feet high with an uncontrolled outlet. No provision 
is made for storage except for flood control. Flood 
releases will be controlled so that flows through Roswell 
will not exceed Rio Hondo channel capacity which is about 
1,000 c.f.s. Capacity of Two Rivers Reservoir at spillway 
crest is 168,000 acre-feet, of which 18,000 acre-feet are 
provided for sediment reserve. Together these dams regulate 
runoff from 1,027 square miles of drainage area. For 
details of completed improvement and authorizing legislation 
see page 17-18 of Annual Report for 1973. 
Local cooperation. Section 2 Flood Control Act of 1938 
applies and compliance is satisfactory. 
Operations and results during fiscal year. Routine 
maintenance and operation continued. The reservoir was 
empty on October 1, 1985. The maximum pool elevation 
of 3,986.40 feet with a corresponding storage of 871 acrefeet 
occurred on 24 June 1986. There were $796,300 in 
flood damages prevented during 1986. Sediment damages 
prevented were $104,000. Estimated total accumulated 
flood and sediment damages prevented through FY 1986 
were $7,519,900. There were 929 acre-feet of sediment 
deposition during FY 1986. The accrued sediment benefits 
through FY 1986 are $658,000. 
Condition at end of fiscal year. Project is complete 
and was placed in operation July 1963. Project features 
are in good condition and in operation. 
9. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Included under this heading is inspection of completed 
flood control projects transferred to local interests for operation 
and maintenance. Projects in Texas, Colorado, and 
New Mexico were inspected. Federal costs for the fiscal 
year were $141,000. 
An appropriation of $60,000 was provided through the 
Inspection of Completed Works program in FY 1986 to 
evaluate the performance of the Albuquerque North Diversion 
Channel project. 
10. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Pursuant to Section 7, Flood Control Act of 1944, three 
projects are operated by others for flood control. These projects 
are Platoro, Pueblo, and Sumner. 
Platoro Dam on Conejos River above the town of Platoro, 
Conejos County, CO controls runoff from 40 square miles 
of high mountain area. Authorized purposes are irrigation 
storage and flood control. Total storage is 60,000 acrefeet 
with the top 6,000 acre-feet for flood control. The 
54,000 acre-feet is joint use storage with flood-control on 
a forecast basis during spring runoff. Platoro Dam was 
authorized by Interior Appropriation Act of 1941 (see H 
Doc 693, 76th Cong., 3rd Sess.) Construction of project 
was completed by Water and Power Resources Service 
(Bureau of Reclamation) in FY 1952. 
On October 1, 1985, storage in Platoro reservoir was 
53,506 acre-feet, elevation 10,027.5 feet. Maximum storage 
of 55,353 acre-feet, elevation 10,029.5 feet occurred 
on June 30, 1986. On September 30, 1986, storage was 
52,137 acre-feet, elevation 10,026.0 feet. Peak flow at 
Mogote gage was 2,650 c.f.s. on June 7, 1986. $502,000 
in flood damages were prevented by the project during 
FY 1986. Total flood damages prevented to date are at 
$3,955,700. Total cost for activity during FY 1986 was 
$12,811. 
Pueblo Dam is part of the Fryingpan-Arkansas project 
which was authorized under Public Law 87-590, 87th 
Congress, HR 2206 on August 16, 1962. The project was 
completed in August 1975. Pueblo is operated by the U.S. 
Bureau of Reclamation and is located at river mile 1,293.7 
on the Arkansas River in Pueblo County Colorado. Pueblo 
reservoir has 27,000 acre-feet exclusive flood space and 
66,000 acre-feet joint use space. 
Operation of Pueblo Reservoir began on February 10, 
1974. Storage on October 1, 1985 was 245,259 acre-feet, 
elev. 4,876.23 feet. Maximum storage during the year was 
17-b

ALBUQUERQUE, NM, DISTRICT 
279,938 acre-feet, elev. 4,883.75 feet on February 19,1986. 
Storage on September 30, 1986 was 251,995 acre-feet, elev. 
4,875.64 feet. There were no flood damages prevented in 
FY 1986. Total cost for FY 1986 activity was $11,660. Total 
flood damages prevented to date are $2,761,900. 
Sumner Dam is located on the Pecos River at river mile 
710.8 in DeBaca County, New Mexico. Sumner Dam was 
authorized as Alamogordo Dam by the Secretary of the 
Interior under a Finding of Feasibility approved by the 
President of the USA on 6 November 1935, under the Federal 
Reclamation laws. The original project was completed 
in 1937. Modification work of raising the dam 16 feet, adding 
a spillway and limiting the service spillway floor to 
56,000 c.f.s. was completed in 1957. A twenty-four inch 
bypass line was installed in 1977 to pass flows less than 
100 c.f.s. Storage on October 1, 1985 was 9,685 acre-feet, 
elevation 4,237.0 feet. Maximum storage for FY 1986 was 
51,702 acre-feet, elevation 4,261.1 feet on September 17, 
1986. Storage on September 30, 1986 was 50,571 acre-feet, 
elevation 4,260.7 feet. Total cost for FY 1986 activity was 
$8,667. 
11. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 17-E. 
12. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 858, 80th Congress, as amended (preauthorization). 
Costs during FY 1986 were: Kistenmacher Arroyo, Dona 
Ana County, NM $7,500; Fountain Creek at Shooks Run, 
Colorado Springs, CO $4,277; Fountain Creek at Southmoor 
Addition, City of Fountain, CO $5,812; Fountain 
Creek at Circle Drive, El Paso County, CO $2,727 and 
San Vicente Arroyo at Silver City, NM $2,454. 
TABLE 17-E OTHER AUTHORIZED F 
Emergency flood control activities repair, flood 
fighting, and rescue work. (Public Law 99, 84th Cong., 
and antecedent legislation.) 
Federal costs for fiscal year 1986 were $161,624 for 
advance preparation, and $9,969 for flood emergency operations, 
and $230,300 for repair and restoration. 
Emergency bank protection (Sec. 14, 1946 Flood 
Control Act, Public Law 526, 79th Cong.) 
Federal costs during FY 1986 were: Canipa Creek at 
Acoma, NM $11,707; Taos County Rd C-61, Vadito, NM 
$950; Monument Creek Forest View Rd, CO $7,400; Red 
River at Questa, NM $2,550; Rio Ruidoso in Lincoln 
County, NM $64,184; San Francisco River at Reserve, NM 
$24,995; Willow Creek at Creede, CO $7,500; Fountain 
Creek at Security, Colorado Springs, CO $24,639; Fountain 
Creek at Pefion Bridge, Pueblo, CO $2,216 and Rio 
Costilla at Amalia, Taos County, NM $32,345. 
General Investigations 
13. SURVEYS 
Costs for the fiscal year were $620,472 for flood damage 
prevention studies, $32,359 for special studies (coordination 
studies with other agencies), and $149,899 for preauthorization 
studies, Arkansas River and Tributaries 
above John Martin Dam, Colorado, Phase I. 
14. COLLECTION AND STUDY 
OF BASIC DATA 
Fiscal year costs were $166,000 for flood plain management 
and technical services. 
Hydrologic studies involving collection and study of 
basic data, such as stream flow data, collection of suspended 
sediment samples, recording rain gage data, hydrometeorological 
studies, and sedimentation studies 
continued. Costs during the fiscal year were $16,000. 
'LOOD CONTROL PROJECTS 
Project 
Alamogordo diversion channel, Tularosa (closed) Basin, New Mexico4 
Alpine, Texas3 
Cibolo Creek, Texas' 
Colorado Springs, Fountain que Bouille River, Colorado 
(Templeton Gap Floodway) 
Creede, Willow Creek, Colorado (floodway)' 
Highway 12, Colorado' 
Holly Colorado' 
Las Animas, Colorado 2 
Las Cruces, New Mexico 2 
Pecos, Texas3 
Pinon Canyon Dam, Trinidad, Colorado (Sec. 212)1' 
Pueblo Arkansas River, Colorado (floodway levee extension)' 
Santa Fe River and Arroyo Mascaras, New Mexico3 
Smith Creek, Colorado' 
Socorro diversion channel, tributaries of Rio Grande, New Mexico' 
'Completed. 2Responsibility of local interests. 3Inactive. 
17-7 
For Last 
Full Report 
See Annual 
Report For 
1966 
1977 
1983 
1959 
1952 
1985 
1985 
1980 
1980 
1977 
1954 
1983 
1985 
1965 
4Deferred. 
Cost to September 30, 1986 
Construction 
189,356 
130,488 
829,500 
Operation & 
Maintenance 
2 
881,262- 
219,789- 
120,500- 
2,021,400- 
4,956,000- 
4,752,310- 
480,273- 
130,678- 
201,958- 
1,123,900- 
219,000- 
2,259,328-

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See Total Costs 
Section to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
1. Albuquerque New Work 
Diversion Channels 
Project, NM 
(Federal Funds) 
(Contributed 
Funds) 
(Other Contributed 
Funds) 
2. Conchas Lake, NM 
3. El Paso, TX 
4. John Martin 
Reservoir, CO 
5. Rio Grande Basin, NM 
5A. Abiquiu Dam, NM 
5B. Cochiti Lake, NM 
5C. Galisteo Dam, NM 
5D. Jemez Canyon 
Dam, NM 
5E. 
5F. 
6. 
Rio Grande, 
Floodway, T. or C. 
Unit, NM 
Santa Rosa Dam 
& Lake, NM 
7. Trinidad Lake, CO 
8. Two Rivers Dam, NM 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
58,423 
2,648 
1,364,200 
710,414 
5,150,000 
6,026,141 
39,000 
3,601 
712,500 
684,579 
134,000 
33,519 
997,100 
771,334 
109,900 
415,245 
1,578,500 
1,273,598 
10,000 
20,565 
129,000 
123,904 
- 20,400 
9,731 
331,100 
320,473 
45,000 
37,505 
108,000 
320,612 
507,200 
395,478 
3,592,000 
4,122,547 
420,000 
390,795 
-2,000 
10,927 
31,900 
696,200 
366,107 
4,100,000 
4,267,354 
70,000 
95,377 
797,800 
875,971 
128,771 
1,270,600 
1,292,150 
-9,600 
53,404 
706,900 
1,148,752 
5,000 
13,177 
100,000 
106,851 
-775
36 
193,600 
342,025 
155,000 
164,711 
-60,000 
138,593 
500,000 
561,101 
60,000 
369,297 
290,000 
311,317 
-3,625 
1,014 
- 2,912 
542 
805,000 
838,774 
7,350,000 
9,062,333 
10,022 
1,000,000 
1,020,695 
-135,000 
1,771 
2,231,000 
2,368,302 
154 
1,014,000 
1,083,745 
9,287 
124,000 
142,277 
245,000 
269,016 
200,000 
162,971 
49,734 
622,000 
680,429 
384,730 
535,000 
598,337 
- 17,268,450 
- 17,268,450 
518,356 
518,356 
854,644 
854,644 
13,821,4991 
13,821,4991 
12,566,372 
12,480,156 
58,017,294 
57,789,907 
15,555,3582 
15,555,3582 
14,537,500 
14,514,679 
941,000 
905,216 
3,538,060 
3,743,565 
955,000 
976,245 
- 26,745,028 
14,318 26,745,028 
1,958,000 13,274,806 
2,032,253 13,177,916 
- 97,084,559 
- 97,084,559 
1,010,000 9,723,700 
996,402 9,684,616 
- 14,275,053 
- 14,275,053 
88,000 1,488,477 
97,215 1,485,712 
1,457,000 5,683,972 
1,455,797 5,682,769 
198,000 5,323,051 
201,545 5,317,267 
367,000 5,908,8683.4 
276,605 5,781,1903 
- 41,041,562 
20,833 41,010,819 
491,000 3,152,200 
489,720 3,111,826 
- 55,774,758 
20,746 55,751,239 
459,000 3,863,500 
425,597 3,805,899 
- 4,847,244 
- 4,847,244 
17-8 
TABLE 17-A

ALBUQUERQUE, NM, DISTRICT 
TABLE 17-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost5 
Section to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
Maint. 
Approp. 158,100 156,700 183,000 209,000 2,167,712 
Cost 137,317 198,258 188,678 214,225 2,160,943 
'Includes $3,492,696 maintenance and improvement costs Rio Puerco units and for preconstruction planning of Espanola 
and $869,978 for emergency relief, excludes $2,279,326, cost of Valley unit. Excludes $1,000,011 appropriated funds transferred 
initiating project under the authority of Emergency Relief to Bureau of Reclamation under memorandum agreement 
Appropriation Act of 1935 and $222,669, the cost for work per- between that agency and the Corps. 
formed with funds transferred to the Corps under Public Works 4 Starting in FY 1982, AE&D programs are funded through 
acceleration Act of 1962. GI appropriations. 
2 Excludes $59,977 emergency relief funds for new work. In- 5 Includes funds (3,192,000) provided by Jobs Act (PL 98-8 
cludes $30,000 for Code 710. March 24, 1983) for projects listed in Table 17-F of FY 1985 
3 Includes funds for completed Albuquerque and Cochiti to Annual Report. 
TABLE 17-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
EL PASO, TX 
3. Oct. 27, 1965 A single-purpose flood control system of detention dams, diversion H. Doc. 207, 89th Cong., 
dikes and channels to collect, regulate and discharge arroyo runoff 1st sess. 
in the Rio Grande. Consists of four independent units (NW Area, 
Central Area, and two units, Copper System and Bluff Channel 
of the SE Area.) 
RIO GRANDE BASIN, NM 
5. June 30, 1948 Authorized to be appropriated $3,500,000 to be expended by the H. Doc. 243, 81st Cong., 
Dept. of the Army for partial accomplishment of approved general 1st sess. 
comprehensive plan for the Rio Grande Basin in NM and Colorado. 
May 17, 1950 Authorized to be appropriated an additional $39,000,000 for Dept. Public Law 516, 81st 
of the Army for prosecution of comprehensive plan for the Rio Cong., 2nd sess. 
Grande Basin. 
July 14, 1960 Authorized Cochiti Dam on Rio Grande and Galisteo Dam on Galisteo S. Doc. 94, 86th Cong. 
Creek as additions to authorized comprehensive plan for Rio 
Grande Basin (Cochiti Dam was authorized in lieu of Low Chamita 
Dam of Chamita Reservoir Project on Rio Chama under "substitute 
plan"). Also authorized to be appropriated an additional $58,300,000 
for Dept. of the Army for this addition to comprehensive plan for 
the Rio Grande Basin. 
RIO GRANDE FLOODWAY, NM 
5. June 30, 1948 Channel rectification, levee enlargement and construction, and bank H. Doc. 243, 81st Cong., 
and stabilization on Rio Grande between river mile 123 and 394 1st sess.' and Public 
May 17, 1950 (See Table 17D.) Law 516, 81st Cong., 
2nd sess. 
TRUTH OR CONSEQUENCES (HOT SPRINGS), NM 
5. June 30, 1948 Approved comprehensive plan for Rio Grande Basin is set forth in H. Doc. 243, 81st Cong., 
the Report of the Chief of Engineers dated April 15, 1948, for flood 1st sess. 
control of Rio Grande Basin. 
May 17, 1950 In addition to previous authorizations, the completion of the plan H. Doc. 243, 81st Cong., 
approved in the Flood Control Act of 1948, for the Rio Grande 1st sess. 
Basin, at an estimated cost of $39,000,000. 
'Contains latest published maps. 
17-9

TABLE 17-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
RIO GRANDE BASIN, NM 
RIO GRANDE BASIN, NM: EXISTING PROJECT 
(See Section 9 of Text) 
Drainage 
Miles Area Total 
Above Nearest (square Estimated 
Project River Mouth Town mile) Description Cost 
Abiquiu Dam Rio Chama 32 Espanola, 2,147 Earthfil 325 feet high, 1,212,000 26,797,0963 
NM acre-feet capacity 
Jemez Canyon Jemez 2 Bernalillo, 1,034 Earthfill 136 feet high, 106,100 4,217,206 
Dam NM acre-feet capacity 
Rio Grande Rio Grande 123 to 394' - - Channel rectification, levee 25,744,0002 
Floodway enlargement and construction 
Cochiti Lake Rio Grande 3401 Cochiti, 11,695 Earthfill 251 feet high, 596,300 96,900,000 
NM acre-feet capacity 
Galisteo Dam Galisteo Creek 8 Waldo, 596 Earthfill 158 feet high, 89,000 14,340,280 
NM acre-feet capacity 
'River mile 0 is at intersection of New Mexico-Texas State Line with international boundary at El Paso, Texas. 
2Does not include non-Federal costs. 
3Includes $5,383,000 major rehabilitation, $138,900 for recreation facilities. 
RIO GRANDE FLOODWAY, NM: 
TABLE 17-D EXISTING PROJECT 
(See Section 9E of Text) 
Location Estimated 
Reach (river miles)1 Cost 
Truth or Consequences unit (formerly Hot Springs) 123 to 129 $9,200,000 
San Acacia to Bosque del Apache unit 155 to 226 6,200,000 
(1960)2 
Cochiti to Rio Puerco unit (not including Albuquerque unit) 236 to 340 2,658,0003 
Albuquerque unit 286 to 305 3,130,0004 
Espanola Valley unit 366 to 394 456,0002 
(1970)s 
'River mile 0 being at intersection of New Mexico-Texas State line with international boundary at El Paso, Texas. 
23DIne afedrdreitdio fno,r restudy. $1,650,000 incurred by the Bureau of Reclamation in this reach. 4In addition, $75,000 incurred by local interest in this reach. 5In addition, estimated cost to local interests is $69,000 (1970). 
TABLE 17-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation & 
Project Report For Construction Maintenance2 
Alamogordo diversion channel, Tularosa (closed) Basin, New Mexico4 1966 189,356 - 
Alpine, Texas3 1977 130,488 - 
Cibolo Creek, Texas' 1983 829,500 - 
Colorado Springs, Fountain qclue Bouille River, Colorado 
(Templeton Gap Floodway) 1959 881,262 - 
Creede, Willow Creek, Colorado (floodway)' 1952 219,789 - 
Highway 12, Colorado' 1985 120,500 - 
Holly, Colorado' 1985 2,021,400 - 
Las Animas, Colorado2 1980 4,956,000 - 
Las Cruces, New Mexico2 1980 4,752,310 - 
Pecos, Texas3 1977 480,273 - 
Pinon Canyon Dam, Trinidad, Colorado (Sec. 212)1 - 130,678 - 
Pueblo Arkansas River, Colorado (floodway levee extension)1 1954 201,958 - 
Santy Fe River and Arroyo Mascaras, New Mexico3 1983 1,123,900 - 
Smith Creek, Colorado' 1985 219,000 - 
Socorro diversion channel, tributaries of Rio Grande, New Mexico' 1965 2,259,328 - 
'Completed. 2Responsibility of local interests. 3Inactive. 4Deferred. 
17-10

LITTLE ROCK, AR, DISTRICT * 
This District comprises northern, western, and southwestern 
portions of Arkansas and a portion of southern 
Missouri embraced in drainage basins of Arkansas River 
and tributaries above and exclusive of Pine Bluff, AR, 
and below mouth of Poteau River, near Fort Smith, AR, 
drainage basins of the Arkansas portion of Little River 
and tributaries above its mouth near Fulton, AR, and 
drainage basins of White River and tributaries above 
Peach Orchard Bluff, AR. In addition, Little Rock 
District has responsibility for planning, design, construction, 
and operation and maintenance of that portion 
of McClellan-Kerr Arkansas River Navigation System 
below Pine Bluff. Memphis District is responsible for 
navigation maintenance on White River below Newport, 
AR, and mouth of Wild Goose Bayou. White River 
downstream from mouth of Wild Goose Bayou is a part of 
McClellan-Kerr Arkansas River Navigation System. 
IMPROVEMENTS 
Navigation Page 
1. Arkansas River Basin, AR, OK, and KS .... 18-2 
2. Bank Stabilization & Channel 
Rectification AR .......................... 18-2 
3. David D. Terry Lock and Dam 
(No. 6), AR ............................... 18-2 
4. Little Rock Slackwater Harbor, 
Arkansas River, AR ...................... 18-3 
5. Lock and Dam No. 2, AR .................. 18-3 
6. Lock and Dam No. 3, AR ................. 18-3 
7. Lock and Dam No. 4, AR ................. 18-3 
8. Lock and Dam No. 5, AR ................. 18-3 
9. Lock and Dam No. 9, AR ................. 18-3 
10. Lock and Dam No. 13, AR ................. 18-3 
11. Maintenance and Repair Fleet and 
Marine Terminals, AR .................... 18-3 
12. Murray Lock and Dam (No. 7), AR ........ 18-3 
13. Navigation Work Under Special 
Authorization ............................. 18-4 
14. Norrell Lock and Dam (No. 1) and 
Entrance Channel, AR .................... 18-4 
15. Other Authorized Navigation Projects ...... 18-4 
16. Toad Suck Ferry Lock and Dam 
(No. 8), A R ............................... 18-4 
Flood Control 
17. Black River, Butler County Road 607, MO...18-4 
18. Blue Mountain Lake, AR .................. 18-4 
19. Clearwater Lake, MO ..................... 18-4 
20. DeQueen Lake, AR ....................... 18-5 
21. Dierks Lake, AR ......................... 18-5 
22. Flood Control Work under Special 
Authorization ............................. 18-5 
23. Gillham Lake, AR ......................... 18-5 
24. Inspection of Completed Flood 
Control Projects .......................... 18-5 
25. Little Massard Creek, Fort Smith, AR ..... 18-6 
26. Little Red River & Tributaries, 
Clinton, AR ............................... 18-6 
27. Little River Basin (Little Rock District), 
A R ...... ................................ 18-6 
28. Mill Creek, Fort Smith, AR ............... 18-6 
29. Millwood Lake, AR ...................... 18-6 
30. Nimrod Lake, AR ......................... 18-7 
31. Other Authorized Flood Control 
Projects...................................18-7 
Flood Control (cont) 
32. Otter Creek & Tributaries, 
Shannon Hills, AR ........................ 18-7 
33. Swan Creek, Bank Stab., 
Taney County, MO ........................ 18-7 
34. White River, Bank Stab., 
Batesville, AR ............................ 18-7 
35. White River Basin (Little Rock District) 
AR & M O ................................ 18-7 
36. White River, Jacksonport, AR..............18-8 
Multiple-Purpose Projects Including Power 
37. Beaver Lake, AR .......................... 18-8 
38. Bull Shoals Lake, AR ..................... 18-8 
39. Dardanelle Lock and Dam (No. 10), AR ..... 18-8 
40. Greers Ferry Lake, AR ................... 18-9 
41. Norfork Lake, AR ........................ 18-9 
42. Ozark-Jeta Taylor Lock and Dam 
(No. 12), AR .............................. 18-9 
43. Table Rock Lake, MO ..................... 18-9 
General Investigations 
44. Surveys ................................. 18-10 
45. Collection and Study of Basic Data ........ 18-10 
46. Continuation of Planning and Engineering 18-10 
Tables 
Table 18-A 
Table 18-B 
Table 18-C 
Table 18-D 
Table 18-E 
Table 18-F 
Table 18-G 
Table 18-H 
Table 18-I 
Table 18-J 
Table 18-K 
Table 18-L 
Cost & Financial Statement ....... 18-11 
Authorizing Legislation ........... 18-14 
Other Authorized 
Navigation Projects .............. 18-16 
Not Applicable 
Other Authorized Flood 
Control Projects ................. 18-17 
Not Applicable 
Deauthorized Projects ............ 18-18 
Arkansas River Basin; AR, OK, 
and KS: Navigation .............. 18-19 
Arkansas River Basin; AR, OK, 
and KS: Lakes .................. 18-22 
Little River Basin, AR: Lakes ..... 18-23 
White River Basin, AR and MO: 
Lakes ........................... 18-24 
Flood Control Work Under 
Special Authorization ............ 18-25 
18-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. ARKANSAS RIVER BASIN, AR, 
OK, AND KS 
Location. Arkansas River rises in Rocky Mountains 
near Leadville, CO, and flows southeastward 1,396 miles 
through Colorado, Kansas, Oklahoma, and Arkansas to 
join Mississippi River 559 miles above Head of Passes, 
LA. (See Geological Survey state maps, 1:24,000, and 
flood control and navigation maps of Mississippi River, 
Cairo, IL, to Gulf of Mexico, 1970 edition scale 1:62,500.) 
Previous projects. For details see page 1066, Annual 
Report for 1932, and pages 744, 864, and 881, Annual 
Report for 1943. 
Existing project. Provides for improvement of Arkansas 
River Basin by construction of coordinated developments 
for navigation, hydroelectric power, flood control, 
water supply, sediment control, recreation, and fish 
and wildlife propagation. McClellan-Kerr Arkansas 
River Navigation System provides a channel of 9 feet 
deep and 445.3 miles long, beginning at mouth of White 
River, which enters Mississippi River 599 miles above 
Head of Passes, LA, thence 9.8 miles upstream to mouth 
of Wild Goose Bayou; thence 9.2 miles by a land cut, 
designated as Arkansas Post Canal to mile 42 (1943 
survey) on Arkansas River; thence 376.0 miles along 
channel of latter stream to mouth of Verdigris River at 
navigation mile 395.0; thence 50.3 miles up Verdigris 
River to head of navigation at Catoosa, OK Waterway is 
canalized throughout its length by 17 locks and dams 
with total lift of 420 feet. Dardanelle, Ozark-Jeta Taylor, 
Robert S. Kerr, and Webbers Falls are multiple-purpose 
projects including power. Lock chambers are 110 by 600 
feet. A minimum channel width of 150 feet is provided 
for Verdigris River, 225 feet for San Bois Creek, 250 feet 
for Arkansas River, and 300 feet for Arkansas Post Canal 
and White River. Other coordinated developments consist 
of 15 lakes, of which 13 are in Tulsa District, Kansas 
and Oklahoma, and two in Little Rock District. Pertinent 
data and estimated Federal cost are summarized in 
Tables 18-H and 18-I, and Arkansas River Basin; AR, 
OK, and KS: Navigation Lakes. For authorization see 
Table 18-B, Authorizing Legislation. 
Local cooperation. For McClellan-Kerr Arkansas 
River Navigation System, local interests must provide 
adequate terminal and transfer facilities and bear increased 
cost of maintenance and operation of all altered 
rail and highway routes, including bridges and appurtenances, 
utilities, and other existing improvements, 
other than federally owned. For lakes see requirements 
for each individual lake. 
Terminal facilities. Public port facilities were in 
operation at Pine Bluff-Jefferson County, Little Rock, 
and Fort Smith, AR, and Muskogee and Catoosa (Tulsa- 
Rogers County), OK. Port authorities have been organized 
to develop public facilities at North Little Rock, 
Dardanelle-Russellville, Morrilton, Clarksville, Ozark 
and Van Buren, AR, and Sallisaw, OK. Terminal facilities 
are in operation or being built at 30 locations in 
Arkansas and at 25 locations in Oklahoma along the 
improved waterways. 
Operations and results during fiscal year. Blue 
Mountain, Canton, Dardanelle Lock and Dam (No. 10), 
Dardanelle Marine Terminal, David D. Terry Lock and 
Dam (No. 6), Elk City, Eufaula, Fall River, Fort Gibson, 
Keystone, W. D. Mayo Lock and Dam (No. 14), Chouteau 
Lock and Dam (No. 17), Newt Graham Lock and Dam 
(No. 18), Robert S. Kerr Lock and Dam and Reservoir 
(No. 15), Webbers Falls Lock and Dam (No. 16) and 
Oologah; Locks and Dams Nos. 2, 3, 4, 5, 9, and 13. 
Markham Ferry, Murray Lock and Dam (No. 7), 
Nimrod, Norrell Lock and Dam (No. 1), Ozark-Jeta 
Taylor Lock and Dam (No. 12), Pensacola, Pine Bluff 
Marine Terminal, Robert S. Kerr Marine Terminal, 
Tenkiller Ferry, Toad Suck Ferry Lock and Dam (No. 8), 
Toronto, and Wister were in operation. Construction is 
complete on bank stabilization. For details of McClellan- 
Kerr Arkansas River Navigation System and lakes in 
Oklahoma and Kansas, see report of Tulsa District. 
Details of McClellan-Kerr Arkansas River Navigation 
System and lakes in Arkansas are shown on following 
pages. 
Condition at end of fiscal year. See Tables 18-H and 
18-I, Arkansas River Basin; AR, OK, and KS: Navigation/
Lakes for status for individual items, navigation 
project, lakes, and basin plan. The overall project is 99 
percent complete. Remaining work in this District is the 
Holla Bend closure structure, rock excavation, Pool 7, 
land acquisition, and detailed engineering studies of the 
entrance channel, meander cutoff in the entrance channel, 
Dam No. 2, and the North Little Rock floodwall and 
levee. 
2. BANK STABILIZATION & 
CHANNEL RECTIFICATION, AR 
Location. Several bank stabilization and channel 
rectification projects are laid out in various reaches 
extending from fixed point to fixed point on Arkansas 
River from 33.7 to 362 miles above mouth and across the 
Arkansas-White cutoff, a 4- to 5-mile natural channel 
joining Arkansas and White Rivers about 18 and 12 miles 
above their respective mouths. 
Existing project. Bank stabilization and channel 
rectification is a part of McClellan-Kerr Arkansas River 
Navigation System. For a complete description of reach 
and location of each bank stabilization and channel 
rectification project, see the Annual Report FY 81. Total 
Federal cost to date is $119,300,184 for existing project in 
Little Rock District. For authorization see Table 18-B, 
Authorizing Legislation. 
3. DAVID D. TERRY LOCK AND 
DAM (NO. 6), AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
18-2

LITTLE ROCK, AR, DISTRICT 
Condition at end of fiscal year. Construction began 
in January 1965 and lock and dam was placed in 
operation in August 1968. 
4. LITTLE ROCK SLACKWATER 
HARBOR, 
ARKANSAS RIVER, AR 
Location. On the right bank of the Arkansas River at 
navigation mile 111.5, Little Rock, AR, along the Arkansas 
River. 
Existing project. Slackwater harbor studies were 
completed and the Asst. Sec. of Army for Civil Works 
approved the Corps participation in the project in April 
1986. Plans and specifications have been prepared. The 
Corps will excavate an access channel 130 feet wide and 
4,800 feet long with a 500-foot diameter turning basin at 
the landward end. The sponsor will pay for the excavation 
of 50-foot berthing areas along the channel, provide 
the land and construct levees required to contain the 
excavated material. The sponsor will also extend utilities 
to the site and provide improvements necessary for use of 
the disposal area by water-oriented industry. Estimated 
construction cost is $2,900,000: $760,000, Federal; 
$2,140,000, non-Federal. 
Local cooperation. The Local Cooperation Agreement 
has been executed by the local sponsor, the Little 
Rock Port Authority, and the Government. 
5. LOCK AND DAM NO. 2, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Emergency 
repairs to the scour protection features and tainter 
gates at Dam 2 that resulted from the barge accident in 
December 1982 were completed in FY 85. Operation and 
maintenance continued. 
Condition at end of fiscal year. Construction began 
in May 1963. Lock was placed in operation in April 1967 
and dam was placed in operation in March 1968. 
6. LOCK AND DAM NO. 3, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction began 
in May 1963 and lock and dam was placed in operation in 
December 1968. 
7. LOCK AND DAM NO. 4, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction began 
in May 1964 and lock and dam was placed in operation in 
December 1968. 
8. LOCK AND DAM NO. 5, AR 
Location, existing project, local cooperation and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction began 
in November 1964 and lock and dam was placed in 
operation in December 1968. 
9. LOCK AND DAM NO. 9, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Continued 
operation and maintenance. Construction of Holla 
Bend closure structure (fish and wildlife mitigation) 
began in July 1986. Completion scheduled for FY 87. 
Condition at end of fiscal year. Construction began 
in April 1965 and lock and dam was placed in operation 
in July 1969. 
10. LOCK AND DAM NO. 13, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction began 
in October 1965 and lock and dam was placed in 
operation in April 1969. Bridge across dam was completed 
in July 1968. 
11. MAINTENANCE AND REPAIR 
FLEET AND MARINE 
TERMINALS, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction of Pine 
Bluff Marine Terminal began March 1968 and it was 
placed in operation in April 1969. Construction of Dardanelle 
Marine Terminal began June 1968 and it was 
placed in operation in November 1969. 
12. MURRAY LOCK AND DAM 
(NO. 7), AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Recreation 
facilities are complete except for cost sharing 
items under the 710 program. Operation and maintenance 
continued. 
Condition at end of fiscal year. Construction began 
in November 1964 and lock and dam was placed in 
operation in October 1969. 
18-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
13. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645, as amended (preauthorization). 
See project writeup for Little Rock Slackwater Harbor, 
Arkansas River, AR. (Total preauthorization study 
costs thru FY 85 - $175,000; FY 86 costs for plans and 
specifications - $103,970.) 
14. NORRELL LOCK AND DAM 
(NO. 1) AND ENTRANCE 
CHANNEL, AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Recommended modification. The Waterways Experiment 
Station (WES), Vicksburg, MS, is conducting a 
test model of an addition lock and dam in the White River 
Entrance Channel. This alternative is being tested to 
relieve restrictions on the navigation system during low 
flows. WES has determined that the other alternatives 
tested would not solve the low-flow problem. 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction began 
in May 1963 and lock and dam was placed in operation in 
June 1967. 
15. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 18-C, Other Authorized Navigation Projects. 
16. TOAD SUCK FERRY LOCK AND 
DAM (NO. 8), AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Continued 
operation and maintenance. 
Condition at end of fiscal year. Construction began 
in July 1965 and lock and dam was placed in operation in 
November 1969. Conway water supply project was 
completed and transferred to that city for operation and 
maintenance in July 1983. 
Flood Control 
17. BLACK RIVER, BUTLER 
COUNTY ROAD 607, MO 
Location. On the right bank of the Black River at 
approximately river mile 208.7 southeast of Poplar Bluff, 
in Butler County, MO. 
Existing project. Placement of stone along approximately 
250 feet of bank to curtail erosion which threatened 
the county road and a local levee. The construction 
work was completed in September 1985. The cost of the 
project was $39,500. 
Local cooperation. Section 3, Flood control Act of 
June 22, 1936, applies. 
Operations during the fiscal year. Butler County, 
the local sponsor, assumed operation and maintenance of 
the project in June 1986. 
18. BLUE MOUNTAIN LAKE, AR 
Location. See Table 18-I, Arkansas River Basin, AR, 
OK, and KS: Lakes. 
Existing project. Estimated cost is $5,069,974. For 
further information see pages 906 and 907 of 1962 
Annual Report. For authorization see Table 18-B. 
Local cooperation. Section 2, Flood Control act of 
1938 applies. 
Operations and results during fiscal year. Operation 
and maintenance of project continued. Estimated 
monetary benefits at end of fiscal year attributed to Blue 
Mountain Lake for prevention of flood damages were 
$619,000 for a total of $18,885,000 through September 30, 
1986. 
Condition at end of fiscal year. Project is complete 
except for additional recreation sanitary facilities. Construction 
of project began in May 1940, and was placed in 
operation in March 1947. 
19. CLEARWATER LAKE, MO 
Location. See Table 18-K. White River Basin, AR 
&MO. 
Existing project. Estimated cost is $11,395,000. For 
further information see pages 897 and 898 of 1962 
Annual Report. For authorization see Table 18-B, Authorizing 
Legislation. 
Recommended modification. Construction of a 
seepage berm, a grout curtain on the right abutment 
and a parapet wall along the dam was approved in 
September 1986. Material for the seepage berm will be 
obtained from the spillway area so that the project 
after construction will pass about 90 percent of the 
probable maximum flood. The estimated project cost is 
approximately $14,800,000. Plans and specifications for 
this work will be prepared in FY 87. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations and results during fiscal year. Operation 
and maintenance of project continued. Estimated 
monetary benefits attributed to Clearwater Lake for 
prevention of flood damages were $10,259,000, for a 
total of $74,772,000 through September 30, 1986. Releases 
made from lake during low-water periods were 
sufficient to supply municipal water for Poplar Bluff 
and other usages. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing sanitary 
recreational facilities. Construction of project began 
in June 1940 and was ready for beneficial use in 
March 1948. 
18-4

LITTLE ROCK, AR, DISTRICT 
20. DEQUEEN LAKE, AR 
Location. On Rolling Fork River, river mile 22.8, a 
tributary of Little River, in Sevier County, about 6 miles 
northwest of DeQueen, AR. (See Geological Survey map 
for Chapel Hill, AR, quadrangle, scale 1:24,000.) 
Existing project. An earthfill dam, 2,360 feet long, 
constructed to 160 feet above streambed. An uncontrolled 
spillway, 200 feet wide, is about 1,400 feet east of 
main embankment. Outlet works consist of a gated 
conduit, 12 feet in diameter. The lake controls 169 square 
miles of drainage area and provides a total storage of 
136,100 acre-feet (101,200 for flood control storage and 
34,900 for conservation and sedimentation reserve). Federal 
cost of project is $19,623,752. (See Table 18-B for 
authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 
1938, and Section 301, Water Supply Act of 1958, as 
amended, apply. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Estimated monetary 
benefits attributed to DeQueen Lake for prevention 
of flood damages were $257,000 for a total of $4,564,000 
through September 30, 1985. 
Condition at end of fiscal year. Construction began 
April 1966 and project placed in useful operation in 
August, 1977. 
21. DIERKS LAKE, AR 
Location. On Saline River, river mile 56.6, a tributary 
of Little River, about 5 miles northwest of Dierks, 
Howard County, AR. (See Geological Survey map for 
Dierks Dam, AR, quadrangle, scale 1:24,000.) 
Existing project. An earthfill dam, 2,760 feet long, 
about 153 feet above streambed. An uncontrolled spillway 
800 feet wide is in a saddle at west end of dam. Outlet 
works consisting of a gated 6- by 9-foot oblong conduit, 
one 24-inch low-flow pipe, and one 30-inch water supply 
pipe are provided. The lake controls a drainage area of 
114 square miles and provides for storage of 67,100 acrefeet 
for flood control and 29,700 acre-feet for water 
supply, conservation, and sedimentation reserve, a total 
of 96,800 acre-feet. Federal cost of project is $16,002,781. 
(See Table 18-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 
1938, and Water Supply Act of 1958, as amended, apply. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented 
during FY 86 are estimated at $44,000; total 
cumulative flood damages prevented are estimated at 
$2,714,000. During the year, 250 acre-feet of water 
supply storage were withdrawn by Tri-Lakes Water 
District. 
Condition at end of fiscal year. Construction began 
in June 1968. The embankment closure was made on May 
8, 1975 and the project placed in useful operation. 
22. FSPLEOCOIDA LC ONTROL WORK UNDER AUTHORIZATION 
Emergency streambank protection (Section 14of 1946 
Flood Control Act, Public Law 526, 79th Cong). The 
projects are: 
Study phase: 
Big Springs Development Area, Carter Co., MO $7,500 
Bryant Creek, Warren Bridge, Ozark Co., MO $6,426 
Construction phase: 
Black River, County Road 607, Popular Bluff, MO 
-$6,200 
Swan Creek Bridge, Taney Co., MO - $61,343 
White River, Batesville, AR - $91,299 
Total costs expended during FY 86 - $172,768 
Small flood control projects (Section 205, Flood Control 
Act of 1948, as amended). During FY 86, there were 
17 ongoing studies: 2 in the detailed project stage, 10 in 
the reconnaissance stage, and 5 in the appraisal stage. 
For status of studies, see Table 18-L. Funds expended on 
small flood control projects in study phase: $395,290. 
Funds were also expended on two Section 205 projects 
under construction: White River, Jacksonport, AR 
($1,579,228) and Little Red River, Clinton, AR 
($2,815,619). For details see individual projects. 
23. GILLHAM LAKE, AR 
Location. Damsite is on Cossatot River, river mile 
49.0, in Howard County, about 5 miles northeast of 
Gillham, Sevier County, AR. (See Geological Survey map 
for Gillham Dam, quandrangle, AR, quandrangle, scale 
1:24,000.) 
Existing project. For description of completed improvement 
see Page 19-12 of Annual Report for 1977 
(Tulsa District). Federal cost of project is $17,826,703. 
(See Table 18-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 
1938, and Water Supply Act of 1958, as amended, apply. 
Tri-Lakes Water District furnished a resolution of intent 
to repay costs allocated to water supply storage. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented 
during FY 86 are estimated at $135,000; total 
cumulative flood damages prevented are estimated at 
$4,745,000. During the year 738 acre-feet of water supply 
storage were withdrawn by Tri-Lakes Water District. 
Condition at end of fiscal year. Construction began 
in June 1963. The embankment closure was made on May 
8, 1975 and the project placed in useful operation. 
24. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Approved regulations for operation and maintenance 
of flood control works, Part 208 of Title 33, Code of 
Federal Regulations, provide for periodic inspection of 
completed projects transferred to local interests for 
operation and maintenance. Inspections of local flood 
protection projects were made to determine extent of 
18-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
compliance with approved regulations for maintenance 
and operation of these projects. Responsible officials of 
improvement districts concerned were advised of inadequacies 
in maintenance and operation of local flood 
protection works under their jurisdiction where appropriate. 
Cost for fiscal year was $76,048. Total cost 
through September 30, 1986, was $1,034,398. 
25. LITTLE MASSARD CREEK, 
FORT SMITH, AR 
Location. In southeast Fort Smith, near Highway 22 
and East of 1-540, Sebastian County, AR. 
Existing project. The flood damage reduction project 
consists of a 30-foot width earthen channel between river 
mile 1.104 and 1.49 and alteration of the 91st Street 
bridge over Little Massard Creek. A construction contract 
was awarded in September 1983. Construction 
costs of the project are $187,887: $109,578, Federal; 
$78,309, non-Federal. 
Local cooperation. The city of Fort Smith, the project 
sponsor, provided the required local assurances contained 
in the June 7, 1983, local cooperation agreement. 
Operation during the fiscal year. Local interests 
assumed operation and maintenance of the project on 
July 19, 1984. An O&M manual is being prepared. 
26. LITTLE RED RIVER AND 
TRIBUTARIES, CLINTON, AR 
Location. In Clinton, Van Buren County, AR, along 
the tributaries of the Little Red River. The city lies 
between the tributaries of Archey Fork and South Fork 
and is bisected by Town Branch. 
Existing project. The flood damage reduction project 
consists of 100-foot bottom-width channel for 1.35 miles 
on Archey Fork Creek and a 300-foot bottom-width 
channel for 1.99 miles on South Fork, Little Red River. 
Local cooperation. The city of Clinton, the project 
sponsor, provided the required local assurances contained 
in the January 3, 1983, local cooperation agreement. 
Operations during the fiscal year. The construction 
work (contract awarded in June 1985) was completed 
and the project was officially transferred to the city of 
Clinton in August 1986 for operation and maintenance. 
Mitigation measures to compensate for damages to the 
walleye pike fishery are being coordinated with the U.S. 
Fish and Wildlife Service and the Arkansas Game and 
Fish Commission. An O&M manual is being prepared. 
27. LITTLE RIVER BASIN 
(LITTLE ROCK DISTRICT), AR 
Location. Improvements are on Little River and 
tributaries, Arkansas. More definite location of individual 
items is shown in Table 18-J, Little River Basin. 
Existing project. Part of a six-lake system for flood 
control and other purposes in the Little River Basin. The 
system consists of four lakes in Arkansas: Millwood on 
the main stem, Dierks on the Saline River, DeQueen on 
the Rolling Fork River, and Gillham on the Cossatot 
River, and two lakes in Oklahoma: Broken Bow on the 
Mountain Fork River and Pine Creek on the Little River. 
Under a District boundary change, effective in October 
1980, the four projects in this system in Arkansas were 
reassigned from the Tulsa District to the Little Rock 
District. 
Local cooperation. Section 2, Flood Control Act of 
1938, and Section 301, Water Supply Act of 1958, as 
amended, apply. Tri-Lakes (DeQueen, Gillham, and 
Dierks) Water District furnished a resolution of intent to 
repay costs allocated to water supply storage. The Southwest 
Arkansas Water District is currently repaying costs 
allocated to water supply storage at Millwood Lake. 
Operations and results during fiscal year. Operation 
and maintenance of projects continued. See individual 
projects for details. 
Condition at end of fiscal year. Millwood, DeQueen, 
Gillham, and Dierks Lakes are complete and in operation. 
28. MILL CREEK, FORT SMITH, AR 
Location. In southwest Fort Smith, Sebastian 
County, AR. 
Existing project. The detailed project report was 
approved December 5, 1985. The plan of improvement 
consists of improving 3.9 miles of the Mill Creek channel 
and modifying six bridges. The estimated project cost is 
$4,780,000: $2,390,000, Federal; $2,390,000, non-Federal. 
The study, which began under the General Investigations 
Program, has been shifted to the Continuing 
Authority Program due to the size of the project. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. 
Operations during the fiscal year. Funds have been 
provided ($162,000) to initiate plans and specifications. 
Total cost of the plans and specifications is estimated at 
$332,700. 
29. MILLWOOD LAKE, AR 
Location. On Little River, river mile 16.0, approximately 
7 miles east of Ashdown, Little River County, 
AR, and about 2 miles northeast of Millwood, Little River 
County, AR. (See Geological Survey map for Red Bluff, 
AR, quadrangle, scale 1:24,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1969 (Tulsa District). Federal cost of project is 
$46,100,082. (See Table 18-B for authorizing legislation.) 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. A total of 49,045 
acre-feet of water was released from the lake for water 
supply to Southwest Arkansas Water District. Estimated 
monetary benefits attributed to Millwood Lake 
18-6

LITTLE ROCK, AR, DISTRICT 
for prevention of flood damages for the fiscal year were 
$290,000, for a total of $6,156,000 to September 30, 1986. 
Condition at end of fiscal year. Construction began 
in September 1961 and the project was placed in full 
flood control operation in August 1966. Work required to 
complete project consists of additional recreational facilities 
under the cost sharing program. 
30. NIMROD LAKE, AR 
Location. See Table 18-I, Arkansas River Basin, AR, 
OK, and KS: Lakes. 
Existing project. Estimated cost is $4,005,627. For 
further information see pages 908 and 909 of 1962 
Annual Report. For authorization see Table 18-B. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations and results during fiscal year. Operation 
and maintenance of project continued. Addition and 
improvement to existing recreation sanitary facilities 
continued. Flooding was prevented on an average of 
1,978 acres of improved land during fiscal year. 
Estimated monetary benefits at end of fiscal year 
attributed to Nimrod Lake for prevention of flood damages 
were $1,278,000, for a total of $11,562,000 through 
September 1986. Eighty-four acre-feet of water were 
withdrawn by the city of Plainview, AR, from Nimrod 
Lake. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing sanitary 
recreation facilities. Construction of project began in 
January 1940 and was ready for beneficial use in 
January 1942. 
31. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 18-E, Other Authorized Flood Control 
Projects. 
32. OTTER CREEK AND 
TRIBUTARIES, 
SHANNON HILLS, AR 
Location. In Shannon Hills, Saline County, about 10 
miles southwest of Little Rock, AR. 
Existing project. The flood damage reduction project 
consisted of construction of a 50-foot channel upstream of 
Beechwood Street to about 2,000 feet downstream of the 
corporate limits, and the replacement of the bridge at 
Shannon Hills Drive in the community of Shannon Hills. 
Final inspection of the project was performed in December 
1985. 
Local cooperation. The city of Shannon Hills, the 
project sponsor, provided the required local assurances 
(easements and rights-of-entry) January 5, 1984. 
Operations during the fiscal year. The city has 
assumed operation and maintenance of the project. An 
O&M manual is being prepared. 
33. SWAN CREEK BANK 
STABILIZATION, 
TANEY COUNTY, MO 
Location. Swan Creek, river mile 2.35, at the Swan 
Creek Bridge, County Road 160-10, near Forsyth, 
Missouri. 
Existing project. The bank stabilization project extends 
400 feet upstream and 100 feet downstream from 
the Swan Creek Bridge. A contract was approved and 
construction was completed in September 1986. The total 
cost of the project was $76,800. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. 
Operations during the fiscal year. Taney County, 
the local sponsor, will assume operation and maintenance 
of the project. 
34. WHITE RIVER BANK 
STABILIZATION, 
BATESVILLE, AR 
Location. At White River mile 299.5, Batesville, 
Arkansas. 
Existing project. The project provided 1,000 feet of 
stabilization to protect the left bank of the White River 
and a buried sewer main line. A contract was approved 
and construction was completed in March, 1986. The 
total cost of the project was $101,100. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. 
Operations during the fiscal year. The city of 
Batesville, the local sponsor, assumed operation and 
maintenance of the project in May 1986. 
35. WHITE RIVER BASIN 
(LITTLE ROCK DISTRICT), 
AR & MO 
Location. Improvements are on White River and 
tributaries, Arkansas and Missouri. More definite location 
of individual items is shown in Table 18-K, White 
River Basin. 
Existing project. A general comprehensive plan for 
flood control and other purposes in White River Basin. 
Plan now includes seven lakes, of which two are flood 
control only projects and five are multiple-purpose 
projects. Beaver, Table Rock, Bull Shoals, Norfork, 
Clearwater, Greers Ferry and Bell Foley lakes were 
selected and approved for construction by Chief of 
Engineers, and individual reports on six of these seven 
lakes are presented on subsequent pages. Bell Foley lake 
was reclassified to inactive in June 1977; reviewed for the 
purpose of deauthorization and placed in a deferred 
status in May 1985. Lakes in plan are listed in Table 
18-K, White River Basin. For authorization see Table 
18-B. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies, Water Supply Act of 1958, as amended, 
applies to Beaver, Greers Ferry, and Norfork. 
18-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Operations and results during fiscal year. Operation 
and maintenance of projects continued. Estimated 
monetary flood control benefits attributed to Beaver, 
Table Rock, Bull Shoals, Norfork, Greers Ferry, and 
Clearwater lakes for FY 86 totaled $42,331,000. A 
cumulative total of flood damages prevented by the 
lakes through September 30, 1986, is estimated at 
$269,150,000. 
Electric energy delivered to Southwestern Power 
Administration for marketing during the fiscal year 
totaled 3,387,660,600 kilowatt-hours. 
Water releases for fish hatcheries were: 28,960 acrefeet 
from Norfork Lake for Fish and Wildlife Service 
trout hatchery, 14,480 acre-feet from Table Rock Lake 
for Missouri Conservation Commission trout hatchery, 
and 14,480 acre-feet from Greers Ferry Lake for U.S. 
Fish and Wildlife Service trout hatchery. 
Withdrawals for water supply purposes were: Beaver 
Water District, 29,448 acre-feet from Beaver Lake: 
Water and Sewer Improvement District No. 3 of Mountain 
Home, AR, 2,322 acre-feet from Norfork Lake; the 
Community Water System, Cleburne County, AR, and 
the city of Clinton, AR, 1,793 acre-feet from Greers Ferry 
Lake. 
Condition at end of fiscal year. Beaver, Table Rock, 
Bull Shoals, Norfork, Clearwater, and Greers Ferry 
lakes are complete and in operation. Progress on these 
lakes is in individual reports. Bell Foley lake project has 
been placed in a deferred status. Water Valley and Lone 
Rock lakes have been deauthorized. 
36. WHITE RIVER, 
JACKSONPORT, AR 
Location. In the west-central part of Jackson County 
at Jacksonport, about 2 miles northwest of Newport at 
the confluence of the White and Black Rivers. 
Existing project. The flood damage reduction project 
consists of raising 5.1 miles of the existing levee and 
extending it about 1.4 miles to high ground to provide an 
approximate 100-year level of protection plus 3 feet of 
free board. Project was approved and funds provided for 
construction in September 1983. Construction contract 
for $1,907,000 was awarded September 28, 1984; final 
inspection of work was made April 23, 1986. 
Local cooperation. The city of Jacksonport, the project 
sponsor, acquired all the necessary land, easements, 
and rights-of-way for the project. 
Operations during the fiscal year. The city of 
Jacksonport, the local sponsor, has assumed operation 
and maintenance of the project. An O&M manual is 
being prepared. 
Multiple-Purpose Projects Including Power 
37. BEAVER LAKE, AR 
Location. See table 18-K. White River Basin. 
Existing project. Estimated cost is $50,797,000. For 
further information see pages 788 and 789 of 1966 
Annual Report. For authorization see Table 18-B. 
Local Cooperation. Section 2, Flood Control Act of 
.1938 and Water Supply Act of 1958, as amended, apply. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented 
during FY 86 are estimated at $4,276,000; total 
cumulative flood damages prevented are estimated at 
$19,036,000. During the year, 214,486,100 kilowatt-hours 
of electrical energy were delivered to the Southwestern 
Power Administration for marketing. Water supply 
storage withdrawn during the year was 29,448 acre-feet. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities. Construction of project began in 
October 1959 and was placed in operation for flood 
control in December 1963, hydroelectric power generation 
with both units in May 1965, and water supply in 
January 1966. 
38. BULL SHOALS LAKE, AR 
Location. See Table 18-K, White River Basin, AR & 
MO. 
Existing project. Estimated cost with eight generating 
units is $96,356,000. For further information see 
pages 725 and 726 of 1965 Annual Report. For authorization 
see Table 18-B. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented 
during FY 86 are estimated at $10,827,000; total 
cumulative flood damages prevented are estimated at 
$78,988,000. During the year, 875,037,000 kilowatthours 
of electrical energy were delivered to Southwestern 
Power Administration for marketing. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities. Construction of project began in 
April 1946 and was ready for beneficial use for flood 
control in June 1951 and generation of electrical energy 
in September 1952. Units 1 through 8 were placed in 
operation September 1952, September 1952, December 
1952, June 1953, January 1962, February 1962, August 
1963, and September 1963, respectively. 
39. DARDANELLE LOCK AND DAM 
(NO. 30), AR 
Location. See Table 18-H, Arkansas River Basin; AR, 
OK, and KS: Navigation. 
Existing project. Project is a unit of McClellan-Kerr 
Arkansas River Navigation System. Dam is 2,683 feet 
long and 68 feet high. It has a spillway with 20 tainter 
gates 50 feet long and 39 feet high. Navigation lock is 110 
by 600 feet with a lift of 54 feet. Powerhouse contains four 
31,000 kilowatt generators. Lake has a storage capacity 
of 486,200 acre-feet. Estimated cost is $86,507,000. (See 
Table 18-B for authorizing legislation.) 
18-8

LITTLE ROCK, AR, DISTRICT 
Local cooperation. See Section 1. 
Operations and results during fiscal year. Continued 
operation and maintenance. Pool fluctuated within 
2-foot power pondage, elevation 336.0 to 338.0. Power 
generation continued. During FY 86, 800,595,600 kilowatt-
hours of electrical energy were delivered to the 
Southwestern Power Administration for marketing. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities. Construction began June 1957. 
Power units were placed on line April, May. and September 
1965, and January 1966. Lock was placed in 
operation in December 1969. Lock was unwatered, inspected, 
and repaired September 14-23. 1981. Information 
Center and resident office were completed in FY 85. 
40. GREERS FERRY LAKE, AR 
Location. See table 18-K, White River, AR & MO. 
Existing project. Estimated cost is $55,125,000. For 
further information see page 740of 1964 Annual Report. 
(See Table 18-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 
1938 and Water Supply Act of 1958, as amended, apply. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented 
during FY 86 are estimated at $404,000; total 
cumulative flood damages prevented are estimated at 
$16,776,000. During the year. 148,946,100 kilowatthours 
of electrical energy were delivered to the Southwestern 
Power Administration for marketing. Water 
supply storage withdrawn during the year was 1,793 
acre-feet. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities. Construction of project began in 
June 1957. was ready for beneficial use for flood control 
in January 1962. and power units 1 and 2 were placed in 
operation in March and May 1964, and water supply was 
placed in operation in April 1971. The visitors center was 
completed in June 1984 at a cost of $922,340. 
41. NORFORK LAKE, AR 
Location. See Table 18-K, White River Basin, AR 
& M O. 
Existing project. Total estimated cost is $111,624,000, 
including S38.700.000 for addition of power units 3 and 4, 
and 840.000.000 for highway bridge construction. For 
further information see page 896of 1962 Annual Report. 
(See Table 18-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 
1988 and Water Supply Act of 1958, as amended, apply. 
Opei'ations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented 
during FY 86 are estimated at $5,585,000; total 
cumulative flood damages prevented are estimated at 
829.849.000. During the year, 214,673,800 kilowatthours 
of electrical energy were delivered to the Southwestern 
Power Administration for marketing. Eightyfour 
acre-feet of water supply storage were withdrawn 
by the City of Plainview, AR. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities, and addition of power units 3 and 
4. Construction of project began in October 1940, ready 
for beneficial use for flood control in June 1943, and for 
generation of electrical energy with one unit in June 
1944. Second unit was added in February 1950. Water 
supply was added as a purpose in December 1969. 
Construction of two highway bridges over Norfork Lake 
to replace ferries was completed in November 1982. The 
bridges were transferred to the Arkansas Highway and 
Transportation Department for operation and maintenance 
in July 1984. 
42. OZARK-JETA TAYLOR LOCK AND 
DAM (NO. 12), AR 
Location. See Table 18-H, Arkansas River Basin, AR, 
OK, and KS: Navigation. 
Existing project. Project is a unit of McClellan-Kerr 
Arkansas River Navigation System. Dam is 2,480 feet 
long and 58 feet above streambed. It has a spillway with 
15 tainter gates 50 feet long and 46 feet high. Navigation 
lock is 110 by 600 feet with a lift of 34 feet. Powerhouse 
contains five 20,000 kilowatt generators. Lake has a 
storage capacity of 148,400 acre-feet. In addition, I foot of 
power pondage is provided in Pool No. 13 between 
elevations 391.0 and 392.0. Estimated cost is 
$86,167,000. For authorization see Table 18-B. 
Local cooperation. See Section 1. 
Operations and results during fiscal year. Delivered 
488,006,000 kilowatt-hours of electrical energy to Southwestern 
Power Administration for marketing. Continued 
operation and maintenance. 
Condition at end of fiscal year. Construction began 
in December 1964. Project is complete except for addition 
and improvement to existing recreation sanitary 
facilities. Lock and dam was placed in operation in 
November 1969. Power units were placed on line as 
follows: Unit 1, November 1972; unit 2, August 1973; unit 
3, October 1973; unit 4, December 1973, and unit 5, May 
1974. Work remaining consists principally of modifications 
to powerplant. 
43. TABLE ROCK LAKE, MO 
Location. See Table 18-K, White River Basin, AR & 
MO. 
Existing project. Estimated cost is $71,233,000. For 
further information see page 893of 1962 Annual Report. 
For authorization see Table 18-B. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented 
during FY 86 are estimated at $10,680,000; total 
cumulative flood damages prevented are estimated at 
$49,729,000. During the year 645,916,000 kilowatt-hours 
18-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
of electrical energy were delivered to the Southwestern 
Power Administration for marketing. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities. Construction of project began in 
October 1954, was ready for beneficial use for flood 
control in November 1958, and for generation of electrical 
energy with units 1 and 2 in May 1959. Units 3 and 
4 were added in April and June 1961. 
General Investigations 
44. SURVEYS 
Fiscal year costs were $727,719: $374,438, flood damage 
prevention studies; $103,041, comprehensive studies; 
$5,138, review of completed projects; $13,467, project 
deauthorization review; $32,973, special investigations; 
$3,207, review of FERC licenses; $3,793, coordination 
studies with other agencies, and $191,662 for planning 
assistance to states. 
45. COLLECTION AND STUDY OF 
BASIC DATA 
Costs for these services for the fiscal year were 
$246,699. 
Flood plain management services (FPMS). The 
authority for the FPMS program is Section 206 of the 
1960 Flood Control Act, PL 86-645, as amended. 
Through technical services and planning guidance, the 
program encourages comprehensive flood plain managemrnent 
planning at all levels to reduce the potential for 
losses to life and property from floods. Federal and non- 
Federal agencies and the private sector are assisted with 
planning and development information for flood hazard 
areas. This assistance is in the form of local flood plain 
regulations, Federal Insurance Program requirements, 
and Executive Order 11988 guidelines. Such assistance 
may include factual flood information (available or 
determined) and interpretation on flood frequencies, 
extent of flooding, flood-water velocity, duration of flooding 
and floodway limits. Services accomplished during 
fiscal year: Technical services and planning guidance 
responses furnished during FY 86 totaled 14,700. This 
total included services to Federal and non-Federal agencies, 
individuals, realtors, corporations, lending institutions, 
engineers, architects, and others. Costs for providing 
these services during FY 1986 totaled $245,402. 
Hydrologic studies. During the fiscal year, 107 stations 
were operated, 75 cooperatively with USGS and 32 
by the Corps. The total cost for streamflow and some 
sediment data from all sources of funding for FY 1986 
was $536,330, of which $398,830 was transferred to 
USGS. The District also participated in a cooperative 
program with National Weather Service for rainfall 
and/or river reporting stations for use in forecasting 
streamflow for flood warning and operation of lake 
projects. Records were also collected at certain hydroclimate 
rainfall stations under a cooperative program 
between the two agencies. For these services, $31,303 
was transferred to the National Weather Service. 
46. CONTINUATION OF PLANNING 
AND ENGINEERING 
During this fiscal year, a total of $349,041 was expended: 
Fourche Bayou - vicinity of Little Rock, AR 
($497,043), and North Little Rock (Dark Hollow), AR 
($51,998). 
18-10

LITTLE ROCK, AR, DISTRICT 
TABLE 18-A COST AND FINANCIAL STATEMENT1 ,2, 3 
See 
Section Total to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 19862 
1. Arkansas River 
Basin, Ark., 
Okla., & Kans. 
2. Bank Stabilization 
& Channel 
Rectification, AR 
3, 5-10, 
12, 14, 
16. 
Navigation 
Locks & Dams, 
AR 
4. Little Rock Slackwater 
Harbor, AR 
17. Black River, Butler 
County Road 607, 
MO 
18. Blue Mountain 
Lake, AR 
19. Clearwater 
Lake, MO 
New Work 
Approp. 
Dams 
Navigation 
Cost 
Dams 
Navigation 
Maint. 
A prop. 
Dams 
Navigation 
Cost 
Dams 
Navigation 
Rehab. 
Approp. 
Cost. 
New Work 
Contrib. 
Cost 
Special Funds 
Cost 
Other 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost. 
Other 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
$ 2,872,052 
138,052 
2,734,000 
5,024,761 
120,404 
4,904,357 
42,620,015 
9,051,008 
33,569,007 
42,359,344 
9,316,208 
32,998,136 
$ 2,144,000 
-72,000 
2,216,000 
2,456,752 
71,746 
2,385,006 
40,244,566 
8,849,697 
31,394,869 
42,894,970 
8,881,670 
34,013,300 
3,450,000 
3,450,000 
2,464,283 
7,366 
2,456,917 
52,292,456 
10,730,500 
41,561,956 
53,144,241 
10,637,899 
42,506,342 
$ 971,000 
971,000 
1,072,738 
1,072,738 
51,802,900 
11,478,700 
40,324,200 
56,383,991 
12,196,588 
44,187,403 
$1,461,206,127 
150,318,533 
1,310,887,594 
1,459,467,728 
150,279,504 
1,309,188,224 
599,984,7793 
132,856,290 
467,128,489 
601,784,8923 
132,505,937 
469,278,955 
- 291,106 
- 291,106 
- 1,609,842 
- 1,609,842 
- 19,926,755 
- 19,926,755 
- 531,336 
- 531,336 
- 119,300,184 
- 119,300,184 
- 4,561,666 
- 4,561,666 
2,652,000 
4,868,815 
12,144,000 
13,179,192 
621,400 
642,803 
49,781 
1,520,100 
1,632,220 
2,220,000 2,600,000 493,000 422,022,473 
2,331,168 2,419,272 785,392 421,417,248 
[2,302,000 11,466,000 12,237,000 187,203,802; 
[5,282,239 16,019,197 15,261,530 189,568,177; 
- - - 973,385 
- - - 963,567 
- - - 531,336 
- - - 531,336 
- - 110,000 110,000' 
- - 103,970 103,970 
5,000 35,500 4,000 44,5005 
135 38,165 6,200 44,50(}' 
- - - 5,069,974 
- - - 5,069,974 
627,000 656,000 624,000 9,820,294:; 
675,029 652,016 636,896 9,813,177:; 
- - - 10,453,403 
- - - 10,440,204 
1,469,000 1,342,000 1,419,000 20,547,522; 
1,633,639 1,366,720 1,391,455 20,518,143 
18-11 
------- 
11 
- --- --- 
-
-

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 18-A (Continued) COST AND FINANCIAL STATEMENT1 ,2,3 
See 
Section Total to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 19862 
20. DeQueen Lake, 
Little River 
Basin, AR 
21. Dierks Lake, 
Little River 
Basin, AR 
23. Gillham Lake, 
Little River 
Basin, AR 
25. Little Massard Crk, 
Fort Smith, AR 
(Contributed Funds) 
26. Little Red River & 
Tributaries, 
27. Little River Basin, 
(Little Rock Dist.) 
28. Mill Creek, Fort 
Smith, AR 
29. Millwood Lake, 
Little River 
Basin, AR 
30. Nimrod Lake, 
AR 
32. Otter Creek & 
Tributaries, 
Shannon Hills, AR 
33. Swan Creek, Bank 
Stabilization, 
Taney County, MO 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approx. 
Cost 
New York 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
12,000 
92,539 
576,200 
623,408 
-12,000 
19,388 
613,500 
468,756 
361 
527,700 
473,013 
00 nnA 
-1,100
37 
515,000 
585,145 
14,770 
510,000 
595,000 
-1,600 
2,006 
495,000 
642,099 
y~,1 l - 
1,100 77,400 
- 95,000 
- 77,725 
1,757,500 (1,456,000) 
195,758 92,952 
- -2,700 
122,753 56,371 
3,370,900 3,513,000 
3,175,154 4,181,253 
10,465 
1,653,500 
1,609,977 
23,623 
777,000 
790,927 
322,000 
39,558 
1,993,000 
2,358,113 
671,000 
674,275 
195 
685,000 
721,135 
809,C 
805,3 
624,( 
649,E 
626,000 816,( 
574,264 841,8 
- 18,( 
1,138 3 
1,060,000 2,550,( 
777,727 2,815,(6 
3,539, 
3,577,c
335 1,1 
500 3,336,( 
)91 3,632,9 
- 162,( 
- 99,4 
7,640 
1,557,500 
1,608,317 
147 - 
589,000 919,000 
747,627 820,871 
(70,000) 0 
147,126 10,050 
- 11,500 
- 9,313 
1,1 
1,323,( 
1,335,4 
922,C 
914,3 
(24,7 
65,E 
61,E 
- 19,629,753 
- 19,623,752 
)00 5,108,03&3 
368 5,079,99&3 
- 16,002,904 
- 16,002,781 
)00 5,480,7033 
313 5,470,2423 
- 17,827,111 
- 17,826,703 
)00 4,620,4853 
372 4,568,7243 
)96 110,0964 
339 80,000 
- 95,000 
- 77,725 
300 3,911,5005 
519 3,686,2985 
- 99,959,850 
127 99,544,384 
000 34,336,2803 
464 34,172,0373 
00 162,0004 
193 99,4934 
- 46,087,3823 
127 46,091,1483 
600 18,865,6623 
111 19,053,0813 
- 4,092,826 
- 4,005,627 
300 11,468,738; 
350 11,450,7143 
796) 239,7045 
0 157,1764 
300 76,8005 
343 70,6565 
18-12

LITTLE ROCK, AR, DISTRICT 
TABLE 18-A (Continued) COST AND FINANCIAL STATEMENT1,2,3 
See 
Section Total to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 19862 
34. White River Bank 
Stabilization, 
Batesville, AR 
35. White River 
Basin (Little 
Rock District) 
36. White River, 
Jacksonport, AR 
37. Beaver Lake, 
AR 
38. Bull Shoals 
Lake, AR 
39. Dardanelle Lock 
& Dam (No. 10), 
AR 
40. Greers Ferry 
Lake, AR 
41. Norfork Lake, 
AR 
42. Ozark-Jeta Taylor 
Lock & Dam (No. 
12), AR 
43. Table Rock 
Lake, MO 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
.Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1 
1. For more details on project funds, see text for individual projects. 
2. Includes funds (total cumulative amount $3,839,700 (excluding $236,700 expended for Continuing Authority projects)) provided in the 
Jobs Act (P.L. 98-8, March 24, 1983) for projects listed in Table 18-M of FY 85 Annual Report. 
3. Beginning data shown in Table 18-A includes special recreation use fees. Data for previous fiscal years have been changed to conform to the 
new procedure. 
4. Includes funds for plans and specifications. 
5. Includes total project funds. 
18-13 
- - 19,500 91,600 111,10@ 
- - 19,500 91,600 111,100 
2,601,500 20,700 - - 335,031,873 
2,390,010 936,207 288,799 160,297 334,749,661 
[7,974,850 15,455,000 16,366,500 15,961,000 235,266,47 7 
L8,315,445 16,641,871 16,875,975 18,584,487 237,543,706:; 
2,438,500 (616,000) - 948,000 2,770,500 
234,943 82,901 864,801 1,579,228 2,761,8735 
-16,500 -4,300 - - 46,183,033 
10,675 3,933 4,039 - 46,112,072 
2,415,650 2,200,000 2,555,500 3,043,600 31,174,429 
2,295,790 2,326,174 2,563,211 3,082,886 31,134,640 
- - - - 88,858,711 
385 - - - 88,858,707 
4,656,300 3,386,000 3,889,500 4,754,600 49,909,353 
4,813,600 3,625,680 4,210,600 4,754,193 54,419,538 
- - - - 84,270,124 
- - - - 84,261,240 
3,027,056 3,198,000 3,541,000 3,751,000 43,503,869 
2,939,073 3,372,791 3,575,685 3,633,834 43,261,128; 
- - - - 48,865,512 
77,853 - - - 48,865,512 
3,554,700 3,061,000 3,197,500 3,745,600 42,658,138 
3,710,151 3,230,760 3,256,122 3,716,466 42,535,269 
2,618,000 25,000 - - 70,997,929 
2,231,986 847,235 - 159,899 70,715,709 
2,544,900 2,264,000 2,238,500 2,423,600 39,338,191 
2,572,873 2,394,031 2,310,590 2,442,185 39,190,901; 
- - - - 85,629,412 
10,532 89 - - 85,629,412 
3,823,256 2,923,000 2,608,000 2,295,000 35,591,478:3 
3,771,288 3,537,134 2,839,221 2,322,962 35,566,822' 
- - - - 67,224,000 
19,330 - - - 67,224,000 
3,283,200 3,075,000 3,134,500 3,229,600 49,813,366; 
3,294,812 3,431,587 3,168,732 3,197,302 49,732,336

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 18-B AUTHORIZING LEGISLATION 
Date of 
Authorizing Act Project and Work Authorized Documents 
June 28, 1938 
August 18, 1941 
July 24, 1946 
July 24, 1946 
June 30, 1948 
May 17, 1950 
July 14, 1960 
June 30, 1948 
July 14, 1960 
June 10, 1948 
June 30, 1948 
ARKANSAS RIVER BASIN, AR, OK, & KS 
(See Section 1 of Text) 
Approved General comprehensive plan: 
Mannford Reservoir, OK 
Oologah Lake, OK 
Canton Lake, OK 
Tenkiller Ferry Lake, OK 
Wister Lake, OK 
Blue Mountain Lake, AR 
Nimrod Lake, AR 
Modified comprehensive plan to include reservoirs in 
Grand (Neosho) River Basin, OK, and MO, and in 
Verdigris River Basin: 
Markham Ferry Reservoir, OK 
Fort Gibson Lake, OK 
Pensacola Reservoir Lake O' The Cherokees, OK 
Fall River Lake, KS 
Elk City Lake, KS 
Toronto Lake, KS 
Neodosha Lake, KS 
Authorized Chief of Engineers to provide in the Canton 
Lake 69,000 acre-feet of irrigation storage, subject to 
certain conditions. 
Approved multiple-purpose plan: 
Oologah Lake, OK 
Markham Ferry Reservoir, OK 
Fort Gibson Lake, OK 
Blackburn Reservoir, OK 
Mannford Reservoir, -OK 
Taft Reservoir, OK 
Bank stabilization 
Dardanelle Lock and Dam, AR 
Eufaula Lake, OK 
Navigation locks and dams 
Ozark Lock and Dam, AR 
Short Mountain Lock and Dam, OK 
Webbers Falls Lock and Dam, OK 
Tenkiller Ferry Lake, OK 
Modified Arkansas River navigation comprehensive plan to 
include bank protection works at Bradens Bend, OK. 
Modified comprehensive plan authorized in 1938 Flood 
CRoivnetrr ol Act and multiple-purpose plan authorized in and Harbor Act of 1946 to provide for substituting 
Keystone Lake for Mannford, Blackburn and Taft 
Reservoirs. 
Authorized incorporation of River and Harbor and Flood 
Control plans into a single plan of development and made 
all previous authorizations applicable to combined 
plan of development. 
Little Massard Creek, Fort Smith, AR 
(See Section 25 of Text.) 
Little Rock Slackwater Harbor, Arkansas River, 
Little Rock, AR (See Section 4 of Text.) 
Mill Creek Fort Smith, AR 
(See Section 28 of Text.) 
Otter Creek and Tributaries, Shannon Hills, AR. 
(See Section 32 of Text.) 
18-14 
Flood Control Cornm. 
Doc. 1, 75th Cong., 
1st sess. 
H. Doc. 107 and 440, 
76th Cong. 1st sess. 
H. Doc. 758, 79th Cong., 
2d sess. 
S. Doc. 107, 81st Cong., 
1st sess. 
Section 205, P.L. 80-858. 
Authorized by Chief of 
Engineers 
Section 107, P.L. 86-645. 
Authorized by Chief of 
Engineers 
Section 205, P.L. 80-858. 
Authorized by Chief of 
Engineers 
Section 205, P.L. 80-858. 
Authorized by Chief of 
Engineers

LITTLE ROCK, AR, DISTRICT 
TABLE 18-B (Continued) AUTHORIZING LEGISLATION 
Date of 
Authorizing Act Project and Work Authorized Documents 
RED RIVER BELOW DENISON DAM INCLUDING 
LITTLE RIVER BASIN, OK AND AR 
(See Section 27 of Text) 
July 24, 1946 
July 3. 1958 
June 28, 1938 
August 18, 1941 
September 3, 1954 
1960 
October 23, 1962 
March 1, 1974 
July 24, 1946 
June 30, 1948 
July 24, 1946 
July 24, 1946 
October 22, 1976 
June 30, 1948 
Construct Boswell, Hugo, and Millwood Lakes, and Bank 
Stabilization. 
Modified Millwood: Construct Pine Creek, Lukfata, 
Broken Bow, DeQueen, Gillham, Dierks Lakes 
WHITE RIVER BASIN (LITTLE ROCK DISTRICT) 
(See Section 35 of Text) 
Approved comprehensive plan for White River Basin: 
Lone Rock Lake, AR, Norfork Lake, AR, 
Clearwater Lake, MO, Water Valley Lake, AR, 
Bell Foley Lake, AR, Greers Ferry Lake., AR, 
and White River emergency. 
Modified comprehensive plan to include Bull Shoals 
Lake, AR, and MO, Table Rock Lake, MO, and 
AR, and Norfork Lake, AR, and MO (power). 
Authorized power in Greers Ferry Reservoir and added 
Beaver Lake to the plan. 
Jacksonport State Park in Jackson County, 
Arkansas. Improvements along the White River 
for recreation and navigation and the protection 
of the park which is historically significant. 
Authorizing clearing and straightening of channel for 
Village Creek, Jackson and Lawrence Counties. 
Authorizing highway bridge construction across 
Norfork Lake. 
Black River, Butler County Road 607, MO 
(See Section 17 of Text.) 
Little Red River and Tributaries, 
Clinton, AR (See Section 26 of Text.) 
Swan Creek Bank Stabilization, Taney County, MO. 
(See Section 33 of Text.) 
White River Bank Stabilization, Batesville, AR. 
(See Section 34 of Text.) 
White River Fish Hatchery, Arkansas provides for 
trout production facilities downstream from 
Beaver Dam. 
White River, Jacksonport, AR. 
(See Section 36 of Text.) 
H. Doc. 602, 79th Cong., 
2d sess. 
H. Doc. 170, 85th Cong., 
1st sess 
Flood Control Conm. 
Doc. 1, 75th Cong., 
1st sess. 
H. Doc. 917, 76th Cong., 
3d sess. 
H. Doc. 290. 77th Cong., 
1st sess. 
H. Doc. 499, 83d Cong. 
2d sess. 
River and Harbor Act 
of 1960 as amended 
Section 107 
H. Doc. 352, 87th Cong., 
2d sess. 
Flood Control Conm. 
Doc. 1, 75th Cong., 
1st sess. 
Section 14, P.L. 79-526. 
Authorized by Chief of 
Engineers 
Section 205, P.L. 80-858. 
Authorized by Chief of 
Engineers 
Section 14, P.L. 79-526. 
Authorized by Chief of 
Engineers 
Section 14, P.L. 79-526. 
Authorized by Chief of 
Engineers 
Water Resources 
Development Act of 
1976, P.L. 94-587, 
Sec. 105 
Section 205, P.L. 80-85&8. 
Authorized by Chief of 
Engineers 
18-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 18-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sept. 30, 1986 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Black River, AR, and MO ' 1950 $ 80,000 $ 930,324 
Current River, AR, and MO ' 1964 17,0002 132,178 
Upper White River, AR 1952 813,197 1,788,374 
White River, AR, (above Peach 
Orchard Bluff)' 1950 - 785,666 
1. Channel adequate for existing commerce. Completion 
not contemplated. 
2. Includes $7,000 for previous project. 
3. Federal operation and maintenance terminated June 
30, 1952, due to lack of commerce. Facilities at Locks and Dams 
Nos. 1, 2, and 3 disposed of in accordance with authority in 
Public Law 996, 84th Cong. 
4. Completed. 
5. Responsibility for maintenance of project downstream 
from Newport, AR, transferred to Memphis District in FY 62. 
18-16

LITTLE ROCK, AR, DISTRICT 
TABLE 18-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sept. 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Bell Foley Lake, White River, AR 1 
Black River, Poplar Bluff, MO, to 
Knobel, AR 
Carden's Bottom Drainage District No. 2, 
Arkansas River, AR 
Clarksville, AR 
Conway County Drainage and Levee District 
No. 1, Arkansas River, AR 
Conway County Levee Districts Nos. 1, 
2, and 8, Arkansas River, AR 
Conway County Levee District No. 6, 
Arkansas River, AR 
Crawford County Levee District, Arkansas 
River, AR 
Crooked Creek, Lake and Levee, AR" 
East Poplar Bluff and Poplar Bluff, MO 
Faulkner County Levee District No. 1, 
Arkansas River, AR 
Fort Smith, Arkansas River, AR 
From North Little Rock to Gillett, AR 
(above Plum Bayou) 
Fourche Creek, Little Rock, AR; 
Little Red River, White County Road Bridge, 
Judsonia, AR 
Little Rock Levee, AR, East End 
Fourche Bayou 
McLean Bottom Levee District No. 3, 
Arkansas River, AR 
Near Dardanelle, Arkansas River, AR 
Newport, White River, AR 
North Little Rock, Arkansas River, AR 
Petit Jean River, AR 
Pine Mountain Lake, AR ' 
Roland Drainage District, Arkansas River, 
AR 
Rolling Fork River, Sevier County, AR 
Skaggs Ferry, Black River, AR 
South Bank Arkansas River (Head Fourche 
Island to Pennington Bayou), AR 
South Bank, Arkansas River, Little Rock to 
Pine Bluff, AR, Tucker Lakes 
Van Buren, Arkansas River, AR 
Village Creek, White River, and Mayberry 
Levee Districts, AR6 
Village Creek, Jackson and 
Lawrence Counties, AR7 
West of Morrilton, Arkansas River, AR 
White River, at Hwy 14, 1j mile east 
of Oil Trough, AR 
Inactive 1975 $1.407.116 - 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Cancelled 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
1958 
1951 
1962 
1959 
1952 
1952 
1954 
1969 
1958 
1941 
1951 
1954 
1973 
1983 
1975 
1950 
1953 
1941 
1958 
1966 
1985 
1950 
1983 
1941 
1964 
1961 
1952 
1972 
1977 
19(i62 
1981 
584,315 
919,955 
271,717 
187,440 
1,018,840 
390,952 
2,001,820 
304,699 
99,511 
1,077,546 
845,300 
22,890 
63,355 
1,901,899 
422,549 
198,069 
314,276 
512,001 
84,350 
1,432,331 
269,907 
64,500 
81,023 
1,404,852 
409,115 
438,222 
1,567,156 
510,217 
1,269,959 
214,308 
1. Reclassified as inactive in Jun '77; reviewed & deferred 
in May '85. 
2. Recommended for deauthorization in Sep '86. 
3. Construction of project cancelled because local interests 
failed to provide right-of-way for construction and 
maintenance. 
4. Authorized by Chief of Engineers. 
5. Reclassified as inactive in Jul '85. 
6. See H Doc. 577, 87th Cong., 2d sess., for description of 
project. 
7. Reclassified in Jun '77; inability of local interests to 
meet local cooperation requirements. 
18-17

TABLE 18-G 
Project 
Lone Rock, Buffalo 
River, AR 
Water Valley, Eleven 
Point River, AR & MO 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
DEAUTHORIZED PROJECTS 
For Last F 
Full Report 
See Annual Date Feder 
Report For Authority Deauthorized Fund, 
1959 1938 FCA 1977 $130,65 
1959 1983 FCA 1977 $414,0 
unds Expended 
al Contributed 
s Funds 
3 - 
18-18

TABLE 18-H ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Miles Elevation Char- Year 
Up- Uper Depth on Miter acter Opened 
stream Lock Pool Sill of Kind to Total 
from Miles to Dimension Lift (feet, Upper Lower Founda- of Type of Navi- Estimated 
Feature Mouth 1 Nearest Town (feet) (feet) MSL) (feet) (feet) tion Dam Construction gation Cost 
LITTLE ROCK 
DISTRICT 
Norrell L&D No. 1 
Lock No. 2 
Dam No. 2 
L&D No. 3 
L&D No. 4 
L&D No. 5 
David D. Terry 
L&D No. 6 
Murray L&D No. 7 
Toad Suck Ferry 
L&D No. 8 
L&D No. 9 
10.3 
13.3 
40.5 
50.2 
66.0 
86.3 
108.1 
125.4 
155.9 
176.9 
8 east of Arkansas 
Post, AR 
6 east of Arkansas 
Post, AR 
3 southeast Arkansas 
Post, AR 
5 north of Grady, AR 
7 east of Pine Bluff, 
AR 
4 southeast of 
Redfield, AR 
12 southeast of Little 
Rock, AR 
6 northwest of Little 
Rock, AR 
6 west of Conway, AR 
3 southwest of 
Morrilton, AR 
110 by 600 
110 by 600 
110 by 600 
110 by 600 
110 by 600 
110 by 600 
110 by 600 
110 by 600 
110 by 600 
30 max. 
20 nom. 
28 max. 
20 
14 
17 
18 
18 
16 
19 
142 
162 
182 
196 
213 
231 
249 
265 
-287 
16 
18 
18 
18 
18 
18 
18 
18 
18 
15 
14 
14 
14 
14 
14 
14 
14 
14 
Piles in 
sand 
Piles in 
sand 
Piles in 
sand 
Piles in 
sand 
Piles in 
sand 
Clay 
Piles in 
sand 
Shale 
Shale 
Shale 
Fixed 
overflow 
Movable 
Movable 
Movable 
Movable 
Movable 
Movable 
Movable 
Movable 
Concrete 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
1967 
1967 
1968 
1968 
1968 
1968 
1968 
1969 
1969 
1969 
$34,265,000 
43,869,000 
33,791,000 
40,831,000 
29.568,000 
62.585,000 
37,492,000 
56,912,000 
34.357,000

TABLE 18-H 
(Continued) 
ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Miles Elevation Char- Year 
Up- Upper Depth on Miter acter Opened 
stream Lock Pool Sill of Kind to Total 
from Miles to Dimension Lift (feet, Upper Lower Founda- of Type of Navi- Estimated 
Feature Mouth' Nearest Town (feet) (feet) MSL) (feet) (feet) tion Dam Construction gation Cost 
Dardanelle 205.5 2 northwest of 110 by 600 54 338 18 14 Movable Sandstone Gated concrete 1969 $84,270,124 
L&D No. 10 
L&D No. 11 
Ozark-Jeta Taylor 
L&D (No. 12) 
L&D No. 13 
TULSA DISTRICT 
L&D No. 13 (part) 
W. D. Mayo 
L&D No. 14 
Robert S. Kerr 
L&D No. 15 
Webbers Falls 
L&D No. 16 
Chouteau L&D 
No. 17 
Newt Graham 
L&D No. 18 
256.8 
292.8 
319.6 
336.2 
366.6 
401.4 
421.6 
Dardanelle, ARI 
Deleted 
1 east of Ozark. AR 
7 east of Fort Smith, 
AR 
4 east of Redland, 
OK 
1 north of Cowlington, 
OK 
1 northwest of Gore, 
OK 
4 northwest of Okay, 
OK 
8 southwest of Inola, 
OK 
110 by 600 
110 by 600 
110 by 600 
110 by 6O) 
110 by 600 
110 by 600 
110 by 6(X00) 
34 
20 
20 
48 
30 
21 
21 
370 
392 
412 
460 
490 
511 
532 
18 
18 
14 
18 
19 
15 
15 
15 
14 
15 
14 
16 
14 
14 
Sandstone 
and shale 
Sandstone 
and shale 
Rock 
Rock 
Rock 
Rock 
Rock 
Rock 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
0 
1969 
1969 
1970 
1970 
1970 
1970 
1970 
1970 
85,629.412 
46.187.000 
6.858.000 
32.655,000 
94,578,237 
83,738,277 
31,619,000 
44,355,000 
l

TABLE I8-H 
(Continued) 
ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Additional features entering into cost of project 
Little Rock District: 
Bank stabilization and channel rectification, mile 33.7 to 362 and 
Arkansas-White Cutoff, 100 per cent complete .............. $119,300,184 
Maintenance and repair fleet and marine terminals, 
99 per cent complete .. ............................... 7,500,000 
Total, Little Rock District ................................ 716,556,720 
Navigation aids (US Coast Guard).. ...................... 2,268,000 
Tulsa District:; 
Bank stabilization and channel rectification, Short Mountain 
to Fort Smith, complete ................................... 12,700,038 
Maintenance and repair fleet and marine terminals, 
com plete .................................................. 2,750,000 
Subtotal ................................ ................ $309,253,552 
Upstream Lakes:; 
Oologah, 90.2 miles upstream from mouth, Verdigris River 
complete ........................ ......................... $ 46,722,329 
Keystone, 63&8 miles upstream from mouth, Arkansas River, 
com plete ................................................ 123,171,173 
Eufaula, 27 miles upstream from mouth, Canadian River, 
com plete ................................................ 122,680,747 
Subtotal .............................................. 292,574,249 
Total, Tulsa District.................................... 601,827,801 
Total Project Cost 99.8 percent complete................ $1,318,384,521 
1. Navigation mileage from mouth of White River except 
Dam No. 2 is 40.5 miles above mouth of Arkansas River. 
2. Includes cost of entrance channel. 
3. Details in Tulsa District report.

TABLE 18-I ARKANSAS RIVER BASIN; AR, OK, AND KS: LAKES 
(See Section 1 of Text) 
Miles Drainage Height Reservoir Power Year or Total 
Lake and State River Above Area of Dam Capacity Development Percent Estimated Mouth Nearest Town (sq mi) (feet) Type (acre-feet) (kilowatts) Complete Cost 
Blue Mountain, AR Petit Jean 74.4 Paris, AR 488 115 Earthfill 257,900 - 1947 $ 5,069,974 
Canton, OK North Canadian 384.3 Canton, OK 12,483 68 Earthfill 383,300 -1948 11,209,834 
Elk City, KS Elk 8.7 Independence, KS 634 
(Table Mound) 107 Earthfill 284,300 - 1966 19,052,990 
Eufaula, OK 1'2 Canadian 27.0 Eufaula, OK 47,522 114 Earthfill 3,798,000 90,000 1964 122,680,747 
Fall River, KS Fall 54.2 Fall River, KS 585 94 Earthfill 256,400 - 1949 10,550,873 
Fort Gibson, OK' Grand (Neosho) 7.7 Fort Gibson, OK 12,492 110 Concrete-gravity 1,284,400 45,000 1953 43,713,378 
Keystone, OK' 2 a Arkansas 538.8 Sand Springs, OK 74,506 121 Earthfill 1,836,500 70,000 1964 123,171,173 
Markham Ferry, OK' a Grand (Neosho) 47.4 Pryor, OK 11,533 90 Earthfill 444,500 100,000 1968 6,908,756 
Neodesha, KS5 Verdigris 222.8 Neodesha, KS 1,152 74 Earthfill 90,000 - 0 97,910 
Nimrod, AR Fourche La Fave 62.6 Plainview, AR 680 103 Concrete-gravity 336,010 - 1942 4,092,826 
Oologah, OK2 Verdigris 90.2 Claremore, OK 4,339 137 Earthfill 1,519,000 - 1974 46,722.329 
Pensacola, OK' 6 Grand (Neosho) 77.0 Disney, OK 10,298 147 Concrete arch 2,197,000 86,400 1940 52,126 
Tenkiller Ferry, OK' 3 Illinois 12.8 Gore, OK 1,610 197 Earthfill 1,230,800 34,000 1953 24,115,719 
Toronto, KS Verdigris 271.5 Toronto, KS 730 90 Earthfill 199,700 - 1960 13,896,324 
Wister, OK Poteau 60.9 Wister, OK 993 99 Earthfill 427,900 - 1949 10,501,226 
Subtotal, exclusive of Eufaula, Keystone, and Oologah, 93 percent complete 149,261,936 
Total, Arkansas River Basin, 98 percent complete 1,467,646,457 
1. Project includes facilities for production of hydroelectric 
power. 
2. Cost included in navigation project. 
3. Details in Tulsa District report. 
4. Constructed by State of Oklahoma under the name of 
Robert S. Kerr Dam (Lake Hudson). Estimate shown is for 
Federal participation. 
5. Inactive. Estimate is based on 1954 price levels. 
6. Constructed by State of Oklahoma under the name 
Grand River Dam (Lake O' The Cherokees). Estimate shown is 
for Federal participation.

LITTLE ROCK, AR, DISTRICT 
TABLE 18-J LITTLE RIVER BASIN, AR: LAKES 
(See Section 27 of Text) 
Project River Site' Nearest Town 
DeQueen Lake' Rolling Fork River 22.8 DeQueen, AR 
Gillham Lake' Cossatot River 49.0 Gillham, AR 
Dierks Lake' Saline River 56.6 Dierks, AR 
Millwood Lake' Little River 16.0 Millwood, AR 
1. Project is reported separately herein. 
18-23

TABLE 18-K WHITE RIVER BASIN; AR, AND MO: LAKES 
(See Section 35 of Text) 
Miles Drainage Reservoir Power Total 
Above Area Height of Dam Above Streambed Capacity Development Estimated 
Lake River Mouth Nearest Town (sq mi) and Type (acre-feet) (kilowatts) Cost 1 
Beaver2 White 609.0 Eureka Springs, AR 1,186 228 feet concrete-gravity and earthfill 1,952,000 112,000 $ 50,797,000 
Bell Foley " Strawberry 27.2 Poughkeepsie, AR 519 136 feet concrete-gravity and earthfill 51&8,000 - 93,700,000 
Bull Shoals2 White 418.6 Mountain Home. AR 6,036 258 feet concrete-gravity 5,408,000 340,000 96,356,000 
Clearwater'' Black 257.4 Piedmont, MO 898 154 feet earthfill 413,000 - 11,395,000 
Greers Ferry" Little Red 79.0 Heber Springs. AR 1,146 243 feet concrete-gravity 1,844,000 96,000 55,125,000 
Norfork2 North Fork 4.8 Norfork. AR 1,806 216 feet concrete-gravity 1,983,000 80,550 111,624,000 
Table Rock2 White 523.8 Branson, MO 4,020 252 feet concrete-gravity and earthfill 3,462,000 200,000 71,233,000 
Total 15,580,000 828,550 490,230,000 
1. Current FY price levels unless otherwise noted. 
2. For details, see individual reports. 
3. Inactive-placed in a deferred status in May 1985. Estimate 
based on 1982 price levels.

LITTLE ROCK, AR, DISTRICT 
TABLE 18-L FLOOD CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
(Section 205, PL 858, 80th Cong., as amended (Preauthorization) 
(See Section 22 of Text) 
Total Costs 
Study Identification Initiation Status Completion FY 86 through 
Date Date Costs Sept. 30, 1986 
Black River, South Poplar Bluff, MO' Aug 1983 Recon' *Oct 1985 $ 31,908 $ 67,500 
Blossom Way Creeks, Rogers. AR' Aug 1983 Recon' *Sep 1985 243 112,482 
Carter Creek & Spring River, Carthage, MO Apr 1986 Appraisal *Sep 1986 - - 
Cloverdale Drain, Little Rock, AR' Dec 1983 DPR' *Sep 1986 33,411 96,520 
Crooked & Dry Jordan Creeks, Harrison, AR' Aug 1983 Recon 2 1,377 84,954 
Current River & Tributary A, Van Buren. MO Jun 1984 Recon Oct 1987 4,486 12,766 
Holly & Dierks Creeks, Dierks, AR Aug 1983 Recon May 1987 20,048 39,522 
Howell Creek & Tributaries, West Plains, MO' Sep 1982 DPR' *Sep 1985 1,473 251,500 
Hurricane Creek, Ashdown, AR Sep 1983 Recon Jul 1987 7,478 23,998 
Jam Up & Tributary A, Mountain View, MO Jun 1984 Recon *Jul 1986 17,500 17,500 
Kelley Creek, Monett, AR Sep 1983 Recon Jun 1987 34,939 73,554 
Logan & Dickson Creeks, Ellington, MO' Feb 1983 DPR: *Apr 1985 656 145,656 
Lost & Little Lost Creeks, Seneca, MO : Aug 1983 DPR *Apr 1985 1,266 76,266 
Mayflower, AR' Apr 1985 Appraisal' *Aug 1985 5,000 5,000 
McKenzie Creek, Piedmont, MO Sep 1983 DPR Jun 1987 51,690 115,021 
Mine & Dodson Creeks, Nashville, AR' Jan 1983 Recon' *Jan 1986 3,281 87,286 
Pike Creek, Poplar Bluff, MO' Feb 1983 DPR' *Mar 1985 3,102 182,491 
Piney and Tucker Creeks, Alton, MO Jun 1984 Recon *Aug 1985 16,000 16,000 
Prairie Creek, Russellville, AR Nov 1983 Recon *May 1987 - 55,964 
Sulphur Creek, Heber Springs, AR Aug 1983 Recon Oct 1987 10,370 17,570 
Taylor Loop Creek, Hwy 10, Little Rock, AR Sep 1986 Appraisal Nov 1986 - 
Tributary 2, Bentonville, AR' Mar 1983 Recon' *Feb 1985 539 102,500 
Tucker Creek, Conway, AR' Sep 1984 Appraisal' *Aug 1985 8,843 8,843 
White River, Batesville, AR Aug 1983 DPR Apr 1987 34,688 135,128 
White River, St. Paul, AR' Aug 1985 Appraisal4 *Sep 1986 - - 
*Accomplished. 
1. No further studies recommended. 
2. Unscheduled - unfunded. 
3. City unable to provide assurances. 
4. Further study recommended. 
18-25

TULSA, OKLAHOMA, DISTRICT * 
The civil works portion of this District covers an area of 
approximately 160,000 square miles which includes 
Oklahoma and parts of Kansas and Texas within the 
Arkansas and Red River Basins. The District's 
responsibilities within the Arkansas River Basin cover 
southern Kansas, northern Oklahoma, and the Texas 
Panhandle. These areas are embraced in the drainage 
basin of the Arkansas River and its tributaries above the 
mouth of the Poteau River, extending to the Kansas- 
Colorado State line, exclusive of that portion of the South 
Canadian River Basin and its tributaries west of the 
Texas-New Mexico State line. The District's 
responsibilities within the Red River Basin cover the 
northern portion of Texas and the southern portion of 
Oklahoma. These areas are embraced in the drainage 
basin of the Red River and its tributaries above Fulton, 
AR. The District is also responsible for operation and 
maintenance of the McClellan-Kerr Arkansas River 
Navigation System in Oklahoma. 
IMPROVEMENTS 
Navigation Page 
1. McClellan-Kerr Arkansas River 
Navigation System, OK ............... 19-2 
2. Other Authorized Navigation Projects ... 19-2 
Flood Control 
3. Arcadia Lake, OK ................... 19-2 
4. Arkansas-Red River Basins Chloride 
Control Projects, KS, OK, and TX ....... 19-2 
4a. Area V, Estelline Springs ............. 19-3 
4b. Area VIII ......................... . 19-3 
5. Birch Lake, OK ...................... 19-3 
6. CandyLake,OK ..................... 19-3 
7. Canton Lake, OK .................... 19-3 
8. Copan Lake, OK ..................... 19-3 
9. Council Grove Lake, KS............... 19-3 
10. El Dorado Lake, KS .................. 19-4 
11. ElkCityLake,KS .................. 19-4 
12. Fall River Lake, KS .................. 19-4 
13. Fort Supply Lake, OK ................ 19-4 
14. Great Salt Plains Lake, OK ............ 19-4 
15. Heyburn Lake and Polecat Creek, OK ... 19-4 
16. Hugo Lake, OK ..................... 19-4 
17. Hulah Lake, OK ..................... 19-4 
18. John Redmond Dam and Reservoir, KS .. 19-5 
19. Kaw Lake, OK ...................... 19-5 
20. Lake Kemp, TX ..................... 19-5 
21. Marion, KS ........................ 19-5 
22. Marion Lake, KS ................... 19-5 
23. Oologah Lake, OK ................... 19-5 
24. Optima Lake, OK .................... 19-5 
25. Pat Mayse Lake, TX ................. 19-5 
26. Pearson-Skubitz Big Hill Lake, KS ...... 19-5 
27. Pinc Creek Lake, TX ................. 19-6 
28. Sardis Lake, OK ..................... 19-6 
29. Skiatook Lake, OK ................... 19-6 
30. Toronto Lake, KS .................... 19-6 
31. Waurika Lake, OK ................... 19-6 
32. W ister Lake, OK ..................... 
33. Other Authorized Flood Control Projects . 
34. Inspection of Completed Local Flood 
Protection Projects .................. 
35. Flood Damages Prevented by Corps and 
Non-Corps Projects ................... 
36. Flood Control Work Under Special 
Authorization ....................... 
Multiple-Purpose Projects Including Power 
37. Broken Bow Lake, OK ................ 
38. Eufaula Lake, OK .................. 
39. Fort Gibson Lake, OK ................ 
40. Grand Lake O' the Cherokees, OK ...... 
41. Keystone Lake, OK ................. 
42. Lake Texoma (Denison Dam), OK 
and TX .. ......................... 
43. Robert S. Kerr Lock and Dam and 
Reservoir, OK .................... 
44. Tenkiller Ferry Lake, OK ............. 
45. Webbers Falls Lock and Dam, OK ....... 
General Investigations 
46. Surveys ... ........................ 
47. Collection and Study of Basic Data ...... 
48. Continuation of Planning and 
Engineering ........................ 
49. Advanced Engineering and Design ...... 
Tables 
19-A Cost and Financial Statement .......... 
19-B Authorizing Legislation ............... 
19-C Other Authorized Navigation Projects .. . 
19-D Not Applicable 
19-E Other Authorized Flood Control Projects . 
19-F Not Applicable 
19-G Not Applicable 
19-1 
19-6 
19-6 
19-7 
19-7 
19-7 
19-7 
19-7 
19-7 
19-7 
19-7 
19-7 
19-8 
19-8 
19-8 
19-8 
19-8 
19-8 
19-8 
19-9 
19-13 
19-15 
19-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
19-H Arkansas River Basin Multiple- Non-Corps Projects ..................... 19-17 
Purpose Plan ......................... 19-16 19-K Flood Control Work Under Special 
19-I Inspection of Completed Local Flood Authorization ........................ 19-19 
Protection Projects .................... 19-17 19-L General Investigations ................. 19-20 
19-J Flood Damages Prevented by Corps and 
Navigation 
1. McCLELLAN-KERR ARKANSAS 
RIVER NAVIGATION SYSTEM 
(Tulsa District Portion), OK. 
Location. The Tulsa District portion of the McClellan- 
Kerr Arkansas River Navigation System provides a 
navigation route up the Arkansas River from the 
Oklahoma-Arkansas State line to the head of navigation 
at Catoosa, OK, near Tulsa, OK. The total length of the 
Tulsa District portion of the system is 137 navigation 
miles. Descriptions and costs for the entire navigation 
system can be found in the Little Rock District's entry in 
this Annual Report. 
Existing projects. The McClellan-Kerr Arkansas 
River navigation project is a component of the multiplepurpose 
plan for the Arkansas River Basin which 
provides for the improvement of the basin through the 
construction of coordinated developments for navigation, 
hydroelectric power, flood control, water supply, water 
quality control, sediment control, recreation, and fish 
and wildlife propagation. The McClellan-Kerr project 
consists of bank stabilization, channel straightening, and 
cutoffs as required. The navigation channel has a 
minimum depth of 9 feet and a minimum width of 250 
feet on the Arkansas River, and a minimum width of 150 
feet on the Verdigris River. The Tulsa District portion of 
the navigation system consists of the: Arkansas River 
Bank Stabilization and Channel Rectification, Chouteau 
Lock and Dam, Newt Graham Lock and Dam, Robert S. 
Kerr Lock and Dam, Robert S. Kerr Marine Terminal, 
Sans Bois Navigation Channel, W.D. Mayo Lock and 
Dam, Webbers Falls Lock and Dam, and the pool in 
Oklahoma which was created by Lock and Dam 13 in 
Arkansas. The other parts of the multiple-purpose plan 
for the Arkansas River Basin are listed in table 19-H. 
Terminal facilities. Public port facilities are in 
operation at Muskogee and Catoosa, OK. At Sallisaw, OK 
a port authority has been active in seeking development 
of public facilities at that location. Other private 
commercial port facilities are complete and in operation 
at eight Oklahoma locations. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Operation and 
maintenance continued. 
2. OTHER AUTHORIZED 
NAVIGATION PROJECTS. 
See table 19-C. 
Flood Control. 
3. ARCADIA LAKE, OK. 
Location. On the Deep Fork River at river mile 213.8, 
in the metropolitan area of Oklahoma City and Edmond, 
OK, about 1.5 miles west of Arcadia, in Oklahoma 
County, OK. (See Arcadia, OK, Geological Survey map, 
scale 1:24,000.) 
Existing project. The plan of improvement provides 
for flood control, water supply, and recreation by 
construction of an earthfill dam approximately 104 feet 
high and 5,200 feet long with a high-level uncontrolled 
spillway. Outlet works will consist of a gated tower and 
conduit. The lake will have a total capacity of 92,000 
acre-feet (27,380 for conservation, 64,430 for flood 
control, and 190 for sedimentation reserve) and will 
control a drainage area of 105 square miles. Construction 
began in October 1980. 
Local cooperation. Section 2, Flood Control Act of 
1938; Water Supply Act of 1958; Federal Water Project 
Recreation Act of 1965; and Section 221, Flood Control 
Act of 1970 apply. 
Operations and results during fiscal year. The 
project is 87 percent complete. Estimated cost is 
$84,200,000 (October 1986 price level). Work to complete 
the relocation of the Turner Turnpike and to complete the 
embankment, spillway, and recreation facilities, and the 
clearing of some project land was performed during the 
fiscal year. 
4. ARKANSAS-RED RIVER BASINS 
CHLORIDE CONTROL PROJECTS, 
KS, OK, AND TX. 
Location. On certain tributary streams of the 
Arkansas and Red Rivers in the western half of the Tulsa 
District. 
Existing project. Provided for studies involving the 
control of natural water pollution caused by 15 natural 
salt sources identified in 1957 by the U.S. Public Health 
Service. The Arkansas and Red Rivers represent major 
national and regional water resources which are severely 
limited due to poor water quality primarily caused by the 
natural pollutant, sodium chloride. The Arkansas River 
is polluted by five naturally occurring salt sources located 
in northwestern Oklahoma and southwestern Kansas. 
The Red River Basin is polluted by ten naturally 
occurring salt sources located in northwestern Texas and 
southwestern Oklahoma. These studies included the 
construction and subsequent maintenance of an injection 
well and a ring dike used for data collection. 
Preauthorization studies were completed in 1966 and 
1970 and recommended construction of project features 
at 13 of the 15 sites. For a detailed discussion of the 
chloride control projects, see page 19-4 of the Annual 
Report for 1983. 
19-2

TULSA, OKLAHOMA, DISTRICT 
Local cooperation. Descriptive text concerning local 
cooperation requirements is given on page 19-5 of the 
Annual Report for 1983. 
4a. AREA V, ESTELLINE SPRINGS. 
Location. Chloride Control Area V is located about 0.5 
mile east of Estelline, TX, on the Prairie Dog Town Fork 
of the Red River. 
Existing project. The plan of improvement consisted 
of an earthen dike, 9 feet high and 340 feet in diameter, 
around Estelline Springs. The springs were a salt water 
source which decreased the usability of the surface water 
in the area. Construction was started in 1963 and the 
structure was completed in 1964. 
4b. AREA VIII. 
Location. Chloride Control Area VIII is located at 
river mile 74.9 of the South Fork of the Wichita River in 
King County, TX, about 5 miles east of Guthrie, TX. 
Existing project. The plan of improvement consists of 
two low-flow collection dams with attendant pumping 
stations and pipeline facilities. These two structures (the 
Bateman Low Flow Dam and the Ross Ranch Low Flow 
Dam) will be equipped with an inflatable fabric-type weir 
located in the spillway section which would be deflated to 
pass relatively good quality high flows. The collected 
brines will be pumped to the storage reservoir behind the 
Truscott Brine Dam. This brine dam, located at river 
mile 3.6 on Bluff Creek (a tributary of the North Fork of 
the Wichita River) about 3 miles northwest of Truscott, 
TX, would contain the collected brines from this area as 
well as future collections from Area X. Preconstruction 
planning for Area X is essentially complete and 
construction is awaiting approval from the Secretary of 
the Army and funding from Congress. 
Local cooperation. See page 19-5 of the Annual 
Report for 1983. 
Operations and results during fiscal year. 
Construction was initiated at Area VIII and Truscott 
Brine Dam in 1976 and the project is 98 percent complete. 
Estimated cost of the Area VIII project and Stage I 
development of Truscott Brine Dam is $50,325,000 
(October 1985 price level). 
5. BIRCH LAKE, OK. 
Location. On Birch Creek at river mile 0.8, about 1.5 
miles south of Barnsdall in Osage County, OK. (See 
Barnsdall, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see the Annual Report for 1979. Construction 
began in November 1973 and the project was 
placed in useful operation in March 1977. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
6. CANDY LAKE, OK. 
Location. On Candy Creek, a tributary of Bird Creek 
in the Verdigris River Basin, at river mile 1.9. The 
damsite is about 1.5 miles northeast of Avant in Osage 
County, OK. (See Avant, OK, Geological Survey map, 
scale 1:24,000.) 
Existing project. The plan of improvement provides 
for an earthfill dam about 4,200 feet long, including an 
uncontrolled concrete spillway, with a maximum height 
of 103 feet above streambed. Outlet works will consist of a 
gated intake structure, a 10- by 11.25-foot conduit, and a 
stilling basin. An 18- by 24-inch low-flow pipe and an 
18-inch water supply pipe will be provided. The lake will 
have a total capacity of 75,420 acre-feet (44,160 for 
conservation and sediment reserve and 31,260 for flood 
control). The drainage area above the damsite is 43 
square miles. Candy Lake will be operated as a unit of a 
seven-lake system for flood control in the Verdigris River 
Basin in Oklahoma. Construction began in September 
1976. 
Local cooperation. Section 2, Flood Control Act of 
1938; Water Supply Act of 1958; and Section 221 of the 
Flood Control Act of 1970 apply. 
Operations and results during fiscal year. The 
project is about 13 percent complete, but construction has 
been delayed because of the U.S. Justice Department's 
decision to withdraw condemnation proceedings to 
acquire mineral rights. Estimated cost of the project is 
$38,300,000 (October 1984 price level). The project was 
deferred in January 1984. 
7. CANTON LAKE, OK. 
Location. On the North Canadian River at river mile 
394, about 2 miles north of Canton in Blaine County, OK. 
(See Canton, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 590 of the Annual Report for 1969. 
Construction began in December 1940 and the project 
was placed in useful operation in April 1948. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
8. COPAN LAKE, OK. 
Location. On the Little Caney River, a tributary of the 
Caney River in the Verdigris River Basin, at river mile 
7.4, about 2 miles west of Copan in Washington County, 
OK. (See Copan, KS, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-7 of the Annual Report for 
1983. Copan Lake is operated as a unit of a seven-lake 
system for flood control in the Verdigris River Basin in 
Oklahoma. Construction began in November 1972 and 
the project was placed in useful operation in April 1983. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Copan 
Lake became operational in 1983. There are some real 
estate deficiencies remaining to be settled, some final 
contract payments, and construction of remaining 
recreation facilities, for which funds were provided in FY 
86. 
9. COUNCIL GROVE LAKE, KS. 
Location. On the Grand (Neosho) River at river mile 
450, about 1.5 miles northwest of Council Grove in Morris 
19-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
County, KS. (See Council Grove Lake, KS, Geological Construction began in October 1938 and the project was 
Survey map, scale 1:24,000.) placed in full flood control operation in May 1942. 
Existing project. For a description of the completed 
improvement, see page 519 of the Annual Report for 1969. 
Construction began in June 1959 and the project was 
placed in useful operation in July 1964. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
10. EL DORADO LAKE, KS. 
Location. On the Walnut River, a tributary of the 
Arkansas River, at river mile 100.2, about 4 miles 
northeast of El Dorado in Butler County, KS. (See El1 
Dorado, KS, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-7 of the Annual Report for 
1983. El Dorado Lake was authorized as a unit of a threelake 
system for flood control in the Walnut River Basin. 
Construction began in October 1973 and impoundment 
began in June 1981. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. The 
project is 99 percent complete. Work to complete the real 
estate activities and recreational facilities was performed 
during the fiscal year. 
11. ELK CITY LAKE, KS. 
Location. On the Elk River at river mile 8.7, about 7 
miles northwest of Independence in Montgomery County, 
KS. (See Table Mound, KS, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 593 of the Annual Report for 1969. 
Construction began in February 1962 and the project was 
placed in useful operation in March 1966. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
12. FALL RIVER LAKE, KS. 
Location. On the Fall River at river mile 54.2, about 4 
miles northwest of Fall River in Greenwood County, KS. 
(See Severy, KS, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 953 of the Annual Report for 1969. 
Construction of the dam began in May 1946 and the 
project was placed in full operation in April 1949. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
13. FORT SUPPLY LAKE, OK. 
Location. On Wolf Creek, a tributary of the North 
Canadian River, at river mile 5.5, about 12 miles 
northwest of Woodward in Woodward County, OK. (See 
Fort Supply, OK, Geological Survey Map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 594 of the Annual Report for 1969. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
14. GREAT SALT PLAINS LAKE, OK. 
Location. On the Salt Fork of the Arkansas River at 
river mile 103.3, about 12 miles east of Cherokee in 
Alfalfa County, OK. (See Jet, OK, Geological Survey map, 
scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 594 of the Annual Report for 1969. 
Construction of the dam was initiated in September 1938 
and was completed in July 1941. The project was placed in 
full flood control operation in May 1941. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
15. HEYBURN LAKE AND 
POLECAT CREEK, OK. 
Location. On Polecat Creek, a minor tributary to the 
Arkansas River, at river mile 48.6, about 11 miles west of 
Sapulpa in Creek County, OK. (See Lake Heyburn, OK, 
Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 599 of the Annual Report for 1969. 
Construction was started in March 1948 and the project 
was placed in useful operation in October 1950. Channel 
improvements below the lake were completed in 
September 1952. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
16. HUGO LAKE, OK. 
Location. On the Kiamichi River at river mile 17.6, 
about 7 miles east of Hugo in Choctaw County, OK. (See 
Hugo Dam, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-12 of the Annual Report for 
1977. Construction began in October 1967 and the project 
was placed in useful operation in January 1974. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
17. HULAH LAKE, OK. 
Location. On the Caney River at river mile 96.2, about 
15 miles northwest of Bartlesville, near Hulah, in Osage 
County, OK. (See Bowring, OK, Geological Survey map, 
scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 595 of the Annual Report for 1969. 
Construction began in May 1946 and was completed in 
June 1950. The project was placed in full flood control 
operation in September 1951. 
Local cooperation. Fully complied with. 
19-4

TULSA, OKLAHOMA, DISTRICT 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
18. JOHN REDMOND DAM AND 
RESERVOIR, KS. 
Location. The dam is located on the Grand (Neosho) 
River at river mile 343.7, about 2 miles northwest of 
Burlington in Coffey County, KS. (See John Redmond 
Dam, KS, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 581 of the Annual Report for 1970. 
Construction was initiated in July 1959 and was 
completed in December 1965. The project was placed in 
flood control operation in July 1964. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
19. KAW LAKE, OK. 
Location. On the Arkansas River at river mile 653.7, 
about 8 miles east of Ponca City in Kay County, OK. (See 
Charley Creek West, OK, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-13 of the Annual Report for 
1977. Construction began in June 1966 and the project 
was placed in operation in May 1976. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
20. LAKE KEMP, TX. 
Location. On the Wichita River at river mile 126.7, 
about 40 miles southwest of Wichita Falls, TX. (See 
Northeast Lake Kemp, TX, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-14 of the Annual Report for 
1977. Construction began in May 1970 and the project 
was placed in useful operation in October 1972. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
21. MARION, KS. 
Location. On Mud Creek at Marion, the county seat of 
Marion County, KS. 
Existing project. For a description of the completed 
improvement, see page 19-6 of the Annual Report for 
1984. Construction began in June 1975 and was 
completed in May 1980. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. None. 
The city of Marion, KS, is responsible for project 
operation and maintenance. 
22. MARION LAKE, KS. 
Location. On the Cottonwood River at river mile 
126.7, about 3 miles northwest of Marion in Marion 
County, KS. (See Pilson, KS, Geological Survey map, 
scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 597 of the Annual Report for 1969. 
Construction began in June 1964 and the project was 
placed in flood control operation in February 1968. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
23. OOLOGAH LAKE, OK. 
Location. On the Verdigris River at river mile 90.2, 
about 2 miles southeast of Oologah in Rogers County, 
OK. (See Oologah, OK, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-15 of the Annual Report for 
1972. Construction began in July 1950 and was placed in 
standby status in October 1951. Construction was 
resumed in December 1955 and was completed in May 
1963 for initial development. Construction for ultimate 
(second stage) development was initiated in July 1967 
and was completed in 1974. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
24. OPTIMA LAKE, OK. 
Location. On the North Canadian River at river mile 
623.2, about 4.5 miles northeast of Hardesty in Texas 
County, OK. (See Optima Dam, OK, Geological Survey 
map, scale 1:24,000.) 
Existing project. For a description of the existing 
improvement, see page 19-16 of the Annual Report for 
1979. Construction began in March 1966, impoundment 
began in October 1978, and construction was completed 
in 1981. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
25. PAT MAYSE LAKE, TX. 
Location. On Sanders Creek, a tributary of the Red 
River, at river mile 4.6, about 12 miles north of Paris in 
Lamar County, TX. (See Grant, TX, Geological Survey 
map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 584 of the Annual Report for 1970. 
Construction began in March 1965 and the project was 
placed in full flood control operation in September 1967. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
26. PEARSON-SKUBITZ BIG 
HILL LAKE, KS. 
Location. On Big Hill Creek at river mile 33.3, about 
4.5 miles east of Cherryvale, KS. (See Dennis, KS, 
Geological Survey map, scale 1:24,000.) 
19-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Existing project. For a description of the completed 
improvement, see page 19-11 of the Annual Report for 
1983. Construction began in April 1974 and 
impoundment began in March 1981. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
27. PINE CREEK LAKE, OK. 
Location. On the Little River at river mile 145.3, 
about 5 miles northwest of Wright City in McCurtain 
County, OK. (See Wright City, OK, Geological Survey 
map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 584 of the Annual Report for 1970. 
Construction began in February 1963 and the project was 
placed in useful operation in June 1969. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Work to complete 
sanitary facilities at the park was conducted during the 
fiscal year. 
28. SARDIS LAKE, OK. 
Location. On Jackfork Creek, a tributary of the 
Kiamichi River, at river mile 2.8, about 2.5 miles north of 
Clayton in Pushmataha County, OK. (See Yanush, OK, 
Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-11 of the Annual Report for 
1983. Sardis Lake will be operated as a unit of a threelake 
system for flood control in the Kiamichi River Basin, 
including Hugo and Tuskahoma Lakes. Construction 
began in August 1975 and the project became operational 
in January 1983. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Estimated cost of the project is $66,772,000 (October 1986 
price level). The project is 80 percent complete. Funds 
were provided in FY 86 to complete the remaining 
recreation facilities at full Federal expense. Work was 
initiated to improve an existing road from Daisy, 
Oklahoma, to the lake area. 
29. SKIATOOK LAKE, OK. 
Location. On Hominy Creek, a tributary of Bird Creek 
in the Verdigris River Basin, at river mile 14.3, about 5 
miles west of Skiatook in Osage County, OK. (See Avant 
S.E., OK, Geological Survey map, scale 1:24,000.) 
Existing project. Provides for an earthfill dam 3,590 
feet long, 143 feet high with a crown width of 32 feet. The 
uncontrolled 100-foot spillway will be located in the right 
abutment. Outlet works will consist of a controlled intake 
structure, a 10.5-foot-diameter tunnel stilling basin, a 
2.5- by 5-foot low-flow sluice, and a 36-inch water supply 
pipe. The lake will provide a total storage of 513,500 
acre-feet (319,400 for conservation storage, 182,300 for 
flood control, and 11,800 for sedimentation), and will 
control a drainage area of 354 square miles. Skiatook 
Lake will be operated as a unit of a seven-lake system for 
flood control in the Verdigris River Basin in Oklahoma. 
Construction began in January 1974, impoundment 
began in October 1984, and the project became 
operational in November 1984. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. The 
project is 92 percent complete. Estimated cost of the 
project is $113,300,000 (October 1986 price level), 
including deferred recreational development at 
$9,000,000. Work to plug oil and gas wells, complete real 
estate activities, and construct embankment, access 
roads, and recreation facilities was performed during the 
fiscal year. 
30. TORONTO LAKE, KS. 
Location. On the Verdigris River at river mile 271.5, 
about 4 miles southeast of Toronto in Woodson County, 
KS. (See Fredonia, KS, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 600 of the Annual Report for 1969. 
Construction began in November 1954 and the project 
was placed in full operation in March 1960. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
31. WAURIKA LAKE, OK. 
Location. On Beaver Creek, a tributary of the Red 
River, at river mile 27.0, about 6 miles northwest of 
Waurika in Jefferson County, OK. (See Hastings, OK-TX, 
Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-12 of the Annual Report for 
1983. Waurika Lake is operated as a unit of a coordinated 
lake system for flood control in the Red River Basin. 
Construction began in July 1971 and impoundment 
began in August 1977. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operations and maintenance continued. 
32. WISTER LAKE, OK. 
Location. On the Poteau River at river mile 60.9, 
about 2 miles south of Wister in LeFlore County, OK. (See 
Wister, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 601 of the Annual Report for 1969. 
Construction began in April 1946 and was completed in 
May 1949. The project was placed in full flood control 
operation in October 1949. 
Local cooperation. Fully complied with. ' 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
33. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS. 
See table 19-E. 
19-6

TULSA, OKLAHOMA, DISTRICT 
34. INSPECTION OF COMPLETED 
LOCAL FLOOD PROTECTION 
PROJECTS. 
Inspections of the completed local flood protection 
projects operated and maintained by local interests are 
made to determine the extent of compliance with 
approved regulations for operations and maintenance. 
The inspections assist the Corps of Engineers to 
determine if the project provides the flood protection for 
which it was constructed. See table 19-I for a list of 
projects inspected in Fiscal Year 1986. Fiscal year cost 
was $94,155. 
35. FLOOD DAMAGES PREVENTED BY 
CORPS AND NON-CORPS 
PROJECTS. 
The Corps is authorized by the Flood Control Act of 
1944 to prescribe regulations for the use of flood control 
and navigation storages at all reservoirs constructed 
wholly or in part with Federal funds. Through this act, 
operation of Corps and non-Corps reservoirs results in 
the prevention of flood damages. Flood damages are also 
prevented by local flood protection projects constructed 
by the Corps. Table 19-J lists these reservoir and local 
protection projects and presents their fiscal year and 
cumulative flood damage prevented amounts. Fiscal year 
cost for the maintenance of flood control works at non- 
Corps projects totaled $358,928. 
36. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION. 
See table 19-K for Fiscal Year 1986 expenditures for 
Small Flood Control Projects Not Specifically Authorized 
by Congress (Section 205); Emergency Streambank and 
Shoreline Projects; Snagging and Clearing; and Flood 
Control and Coastal Emergencies - Rehabilitation 
Projects. 
Multiple-Purpose Projects 
Including Power 
37. BROKEN BOW LAKE, OK. 
Location. On the Mountain Fork River at river mile 
20.3, about 9 miles northeast of Broken Bow in 
McCurtain County, OK. (See Broken Bow, OK, Geological 
Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvements, see page 19-17 of the Annual Report for 
1971. Construction began in November 1961 and the 
project was placed in useful operation in October 1969. 
Power units 1 and 2 were placed in operation in January 
and June 1970, respectively. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
38. EUFAULA LAKE, OK. 
Location. On the Canadian River at river mile 27.0, 
about 12 miles east of Eufaula in McIntosh County, OK. 
(See Porum, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 588 of the Annual Report for 1970. 
Construction began in December 1956 and the project 
was place in full flood control operation in February 1964. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Work to plan, 
design, and construct a replacement bridge over Piney 
Creek was performed during the fiscal year. 
39. FORT GIBSON LAKE, OK. 
Location. On the Grand (Neosho) River at river mile 
7.7, about 5 miles north of Fort Gibson in Muskogee 
County, OK. (See Fort Gibson Dam, OK, Geological 
Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 604 of the Annual Report for 1969. 
Construction began in March 1942 but was held in 
abeyance during World War II. Construction of the 
concrete dam and spillway started in May 1946 and was 
completed in June 1950. The fourth generator was 
installed and the project placed in full operation in 
September 1953. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
40. GRAND LAKE O' THE 
CHEROKEES, OK. 
Location. On the Grand (Neosho) River at river mile 
77.0, near the town of Disney in Mayes County, OK. (See 
Spavinaw, OK, Geological Survey map, scale 1:24,000.) 
Existing project. Grand Lake O' the Cherokees is a 
Grand River Dam Authority project. For a description of 
the completed improvement, see page 606 of the Annual 
Report for 1969. 
Operations and results during fiscal year. Flood 
control operations at the Grand Lake O' the Cherokees 
are controlled by the Corps. See Section 35 and Table 19-J 
for additional details. 
41. KEYSTONE LAKE, OK. 
Location. On the Arkansas River at river mile 538.8, 
near Sand Springs, OK, and about 15 miles west of Tulsa, 
OK. (See Keystone Dam, OK, Geological Survey map, 
scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 589 of the Annual Report for 1970. 
Construction began in January 1957 and the project was 
placed in flood control operation in September 1964. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
42. LAKE TEXOMA (DENISON DAM), 
OK and TX. 
Location. On the Red River at river mile 725.9, about 
5 miles northwest of Denison, TX. (See Denison Dam, 
OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 603 of the Annual Report for 1969. 
19-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Lake Texoma is operated as a unit of a coordinated lake 
system for flood control in the Red River Basin. 
Construction started in August 1939 and was completed 
for the dam, spillway, and outlet works in February 1944. 
Commercial power generation was started in March 1945. 
Authorized work is complete except for installation of the 
third and fourth power units and additional perimeter 
access roads, which have been recommended for deferral. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
43. ROBERT S. KERR LOCK AND DAM 
AND RESERVOIR, OK. 
Location. On the Arkansas River at navigation mile 
336.2, about 8 miles south of Sallisaw in LeFlore County, 
OK. (See Robert S. Kerr, OK, Geological Survey map, 
scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-21 of the Annual Report for 
1972. Robert S. Kerr Lock and Dam and Reservoir is a 
unit of the McClellan-Kerr Arkansas River Navigation 
System. Construction began in April 1964 and closure 
was completed in October 1970. The lock and dam became 
operational for navigation in December 1970. Generating 
units number 1, number 2, number 3, and number 4 were 
placed in operation in October, July, September, and 
November 1971, respectively. 
Local cooperation. See section 1 of this report. 
Terminal facilities. Seven sites have been developed 
for handling coal, grain, construction aggregates, and 
miscellaneous cargo. The facilities are considered 
adequate for present traffic. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
44. TENKILLER FERRY LAKE, OK. 
Location. On the Illinois River at river mile 12.8, 7 
miles northeast of Gore in Sequoyah County, OK. (See 
Gore, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 606 of the Annual Report for 1969. 
Construction began in June 1947 and was completed in 
July 1953. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
45. WEBBERS FALLS LOCK AND 
DAM, OK. 
Location. On the Arkansas River at navigation mile 
366.6, about 5 miles northwest of Webbers Falls in 
Muskogee County, OK.(See Webbers Falls, OK, 
Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-23 of the Annual Report for 
1977. Webbers Falls Lock and Dam is a unit of the 
McClellan-Kerr Arkansas River Navigation System. 
Construction began in January 1965, and the project was 
placed in useful operation in November 1970. The lock 
and dam became operational for navigation in December 
1970. Generating units number 1, number 2, and number 
3 were placed in operation in August, September, and 
November 1973, respectively. 
Local cooperation. See section 1 of this report. 
Terminal facilities. Cargo pier, mooring dolphins, 
warehouse, terminal building, and fuel facility were built 
by the Muskogee City-County Port Authority. Liquid 
cargo loading facility and steel unloading facility were 
built by Frontier Steel Company to serve existing traffic. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
General Investigations 
46. SURVEYS. 
Fiscal year cost was $2,720,478 which included two 
navigation studies, nine flood damage prevention studies, 
three comprehensive studies, two restudies of deferred 
projects, two reviews of completed projects, two reviews 
for deauthorization studies, inventory of dams, and 
coordination with both Federal and non-Federal agencies. 
Table 19-L provides a specific list and respective fiscal 
year expenditures. 
47. COLLECTION AND STUDY OF 
BASIC DATA. 
Fiscal year cost was $305,037 which includes flood 
plain management services and hydrologic studies. Table 
19-L provides a specific list and respective fiscal year 
expenditures. 
48. CONTINUATION OF PLANNING AND 
ENGINEERING. 
Fiscal year cost was $1,333,609 which includes four 
local protection projects and one flood control reservoir. 
Table 19-L provides a specific list and respective fiscal 
year expenditures. 
49. ADVANCED ENGINEERING AND 
DESIGN. 
Fiscal year cost was $390,387 which includes one local 
protection project and one flood control reservoir. Table 
19-L provides a specific list and respective fiscal year 
expenditures. 
19-8

TULSA, OKLAHOMA, DISTRICT 
TABLE 19-A COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep 30, 1986' 
1. McClellan-Kerr Arkansas New Work 
River Navigation System, 
OK. (Tulsa District 
Portion)* 
3. Arcadia Lake, OK 
4. Arkansas-Red River Basins 
Chloride Control, OK 
and TX 
4a. Area V, Estelline Springs 
4b. Area VIII 
5. Birch Lake, OK 
6. Candy Lake, OK 
7. Canton Lake, OK 
8. Copan Lake, OK 
9. Council Grove Lake, KS 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- 296,553,114 
- 296,553,538 
7,571,632 6,540,500 7,600,266 8,635,900 110,355,111" 
8,227,217 6,403,180 7,865,411 9,120,610 105,888,6912 
20,430,000 3,800,000 9,330,000 6,646,000 73,540,289 
12,765,430 8,967,266 9,687,358 11,417,121 73,425,877 
- - - 100 100 
- - - -315 -315 
49,104 
2,000 
2,703 
3,000 
3,650 
5,215 
6,000 
5,425 
5,500 
4,791 
437 
43,000 
42,891 
4,600 
4,233 
0 25,705,208 
182 25,704,692 
3,146 3,524,393 
4,410 3,637,718 
- 300,028 
- 300,028 
6,000 137,076 
5,882 150,519 
4,923,000 1,829,000 -33,000 943,000 
5,317,748 1,527,050 562,003 601,912 
- - - 127,300 
- - - 127,232 
1,006 
583,200 
564,174 
27,026 
-1,000 
508 
933,000 
811,568 
300,000 
3,801,718 
207,000 
179,008 
120 
11,652 
672,500 
650,417 
177 
529,200 
489,132 
2,908 
120 
1,048,700 
1,072,826 
-104,440 
316,200 
305,573 
46,493,000 
45,630,415 
127,300 
127,232 
- - 13,549,170 
- - 13,549,296 
.658,700 595,000 4,883,4012 
735,047 611,520 8,182,8292 
1,663 
0 4,949,922 
8,285 4,871,852 
- - 11,209,834 
- - 10,918,727 
1,695,800 1,188,500 15,763,8722 
1,766,592 1,297,427 15,838,9822 
8,663,000 
8,531,025 
516,700 
507,386 
- -2,940 
66 -2,940 
615,866 864,200 
565,348 899,513 
3,092,000 
1,050,879 
491,000 
501,204 
88,226,999 
88,780,750 
1,530,900 
1,493,171 
- 11,810,509 
- 11,810,509 
856,000 8,739,6222 
876,525 8,681,875" 
19-9

TABLE 19-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep 30, 1986' 
10. El Dorado Lake, KS New Work 
11. Elk City Lake, KS 
12. Fall River Lake, KS 
13. Fort Supply Lake, OK 
14. Great Salt Plains Lake, OK 
15. Heyburn Lake, OK 
16. Hugo Lake, OK 
17. Hulah Lake, OK 
18. John Redmond Dam and 
Reservoir, KS 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
6,700,000 
6,806,749 
330,000 
302,618 
-5,000 
1,226 
605,708 
560,188 
5,300,000UU 2,370,000 
2,096,205 3,491,995 
319,000 355,700 
312,064 371,549 
741 
710,266 
734,948 
0 90,371,468 
1,412,317 89,429,053 
319,800 1,646,100 
338,798 1,641,025 
- - 19,052,990 
- - 19,052,990 
601,700 870,500 8,333,406" 
532,204 917,213 8,264,6232 
-520 - - - 10,550,873 
- - - - 10,550,873 
643,900 651,020 791,600 835,800 8,546,595' 
604,595 640,445 587,760 1,091,136 8,702,217' 
- - - - 7,724,134 
- - - - 7,723,127 
503,500 476,000 624,000 
475,974 487,499 634,882 
331,000 272,900 458,000 
314,860 291,510 307,513 
2,800 -1,900 
219 3,971 
449,300 461,170 
421,774 431,927 
1,848 
20,000 
3,128 
463,100 
600,987 
-279,088 
671,000 8,164,073' 
687,903 8,136,550 
- 4,626,270 
- 4,626,270 
479,200 5,165,307 
636,153 5,159,098 
- 2,560,572 
- 2,560,572 
495,200 6,667,323 
531,820 6,761,967' 
- 37,759,742 
- 37,425,243 
1,360,582 985,721 1,186,900 1,217,600 10,307,128' 
911,554 1,447,283 1,103,885 1,264,286 10,164,318' 
20,000 
27,990 
629,400 
587,292 
-2,400 
15,130 
615,970 
484,631 
2,500 
878,300 
835,107 
- 11,388,150 
- 11,182,433 
291,600 9,136,879 
497,400 9,081,069 
- 135,718 
- 135,718 
- - - - 28,151,515 
- - - - 28,151,515 
823,000 1,202,000 3,776,066 1,380,600 15,033,655 
752,018 850,643 4,123,729 1,563,663 15,108,932 
19-10

TABLE 19-A 
(Continued) 
See 
Section 
in Text Project 
19. Kaw Lake, OK 
20. Lake Kemp, TX 
21. Marion, KS 
22. Marion Lake, KS 
23. Oologah Lake, OK 
24. Optima Lake, OK 
25. Pat Mayse Lake, TX 
26. Pearson-Skubitz 
Big Hill Lake, KS 
27. Pine Creek Lake, OK 
28. Sardis Lake, OK 
TULSA, OKLAHOMA, DISTRICT 
COST AND FINANCIAL STATEMENT 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Total to 
FY 83 FY 84 FY 85 FY 86 Sep 30, 1986' 
490,000 
361,641 
1,529,400 
1,312,594 
-71,900 - 0 109,430,750 
214,312 -4,518 143,616 109,421,298 
1,145,800 1,454,800 1,714,200 13,001,6682 
1,165,463 1,407,293 2,080,047 12,927,6352 
119,000 141,000 
116,978 130,672 
-81,000 
-5,500 
3,781 
662,900 
644,828 
37,000 
2,951 
1,241,395 
1,199,023 
141 
512,000 
488,318 
762,667 
710,873 
275,827 
498,000 
519,559 
148,600 
136,531 
- 7,637,702 
- 7,637,702 
138,000 1,548,234 
172,196 1,544,283 
A 5 51a20 
- - V JJJ ,6UU 
339 7,227 29,616 5,485,050 
71,000 - - 13,420,817 
70,236 839 - 13,420,817 
797,434 986,600 719,300 9,382,4462 
730,648 1,028,180 789,868 9,351,249" 
-4,000 - - 46,722,3293 
30,049 - - 46,721,5563 
1,154,400 1,168,900 1,179,000 15,668,1042 
1,074,913 1,200,842 1,306,646 15,631,2262 
-10,000 
1,201 
420,368 
455,925 
442,400 
455,332 
- 47,173,438 
- 47,273,438 
485,500 3,203,022 
490,736 3,195,893 
848,900 1,185,400 930,000 
620,839 1,347,577 1,018,712 
- -241,000 
45,090 -147,645 
548,000 603,900 
504,413 590,428 
9,310,661 
9,310,661 
8,773,3092 
8,715,4892 
0 16,879,166 
40 16,879,165 
797,600 2,900,9002 
825,038 2,882,5202 
- 188,400 134,740 0 20,628,049 
- 100,486 154,343 45,998 20,605,736 
630,930 865,870 927,600 924,900 8,417,7582 
607,598 645,695 1,008,083 1,065,137 8,349,2282 
1,050,000 
2,159,987 
305,000 
286,000 
1,288,000 - 122,000 7,453,000 60,756,479 
-27,969 696,504 1,055,291 53,741,143 
395,000 451,100 673,700 1,824,800 
378,047 451,528 671,787 1,787,362 
19-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 19-A 
(Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Txt Project Funding FY 83 FY 84 FY 85 FY 86 Sep 30,1986' 
29. Skiatook Lake, OK New Work 
Approp. 9,355,000 10,000,000 2,375,000 0 103,518,282 
Cost 7,730,104 8,804,556 5,499,255 1,041,357 103,158,783 
Maint. 
Approp. - - 218,400 578,600 797,000 
Cost - - 202,153 524,973 727,126 
30. Toronto Lake, KS New Work 
Approp. - - - - 13,896,324 
Cost - - - - 13,896,324 
Maint. 
Approp. 256,500 264,000 188,000 301,000 4,360,503 
Cost 239,636 268,588 213,803 292,120 4,347,452 
31. Waurika Lake, OK New Work 
Approp. - - - 0 67,080,050 
Cost 122,799 1,314 - 12,313 24,340 66,927,698 
Maint. 
Approp. 759,630 776,500 727,100 938,200 5,601,3442 
Cost 751,347 730,723 770,961 958,274 4,589,2362 
32. Wister Lake, OK New Work 
Approp. - - - - 10,501,226 
Cost - - - - 10,501,226 
Maint. 
Approp. 468,000 500,614 735,900 718,400 8,434,459 
Cost 445,128 468,971 742,409 777,134 8,427,979 
37. Broken Bow Lake, OK New Work 
Approp. - - - - 41,222,692 
Cost - - - - 41,222,692 
Maint. 
Approp. 2,030,000 1,213,463 1,527,500 1,274,100 13,878,419 
Cost 1,229,088 1,809,738 1,629,880 1,393,509 13,849,473 
38. Eufaula Lake, OK New Work 
Approp. - - 850,000 478,000 123,158,7475 
Cost 11,203 200 37,645 287,346 122,144,5355 
Maint. 
Approp. 2,697,400 2,495,070 2,737,100 3,137,400 38,717,3442 
Cost 2,596,323 2,619,134 2,849,316 3,319,004 35,729,9452 
39. Fort Gibson Lake, OK New Work 
Approp. 70,000 -14,000 - - 42,591,2986 
Cost 23,146 35,489 6,625 - 43,497,7916 
Maint. 
Approp. 2,504,900 2,378,281 2,685,400 2,898,800 35,798,6662 
Cost 2,759,933 2,391,757 2,645,762 3,187,330 37,142,6962 
40. Grand Lake O' the New Work 
Cherokees, OK Approp. - - - - 52,126 
Cost - - - - 52,126 
Maint. 
Approp. 9,000 5,500 1,800 - 100 226,408 
Cost 10,933 4,222 1,877 1,590 226,064 
41. Keystone Lake, OK New Work 
Approp. 45,000 - - - 123,171,173' 
Cost 21,000 23,500 - - 123,170,675' 
Maint. 
Approp. 2,197,000 2,148,600 2,953,264 2,681,300 30,127,8302 
Cost 2,106,790 2,163,686 3,041,800 2,844,576 30,193,4832 
19-12

TABLE 19-A 
(Continued) 
TULSA, OKLAHOMA, DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep 30,1986' 
42. Lake Texoma (Denison New Work 
Dam), OK and TX Approp. 92,319 54,400 - - 68,168,9604 
Cost 10,591 128,434 15,512 - 68,019,1094 
Maint. 
Approp. 4,954,242 5,006,165 6,254,300 5,070,800 66,188,8482 
Cost 3,943,331 5,444,478 6,640,360 5,433,240 66,204,6402 
Minor Rehab. 
Approp. - - - - 46,237 
Cost - - - - 46,237 
43. Robert S. Kerr Lock New Work 
& Dam & Reservoir, OK Approp. - - - - 94,578,237 
Cost - - - - 94,578,237 
Maint. 
Approp. 2,114,832 2,234,200 2,562,400 2,452,000 31,299,8362 
Cost 2,083,891 2,014,661 2,669,319 2,510,997 30,776,2422 
44. Tenkiller Ferry New Work 
Lake, OK Approp. - -58,000 - - 24,017,7208 
Cost 40,575 35,249 - - 24,057,7188 
Maint. 
Approp. 2,508,500 2,194,416 2,392,800 2,927,600 30,055,7772 
Cost 2,660,198 2,110,520 2,674,605 3,081,392 29,971,5512 
45. Webbers Falls Lock New Work 
& Dam, OK Approp. - - - - 83,738,277 
Cost - - - - 83,738,701 
Maint. 
Approp. 2,933,256 1,869,900 2,282,026 3,561,800 32,119,064 ' 
Cost 3,530,602 2,252,816 2,445,589 3,867,890 32,194,8962 
*These figures represent the total investment for the Tulsa 3. Excludes $81,460 contributed funds and $1,348,816 
District in the McClellan-Kerr Arkansas River Navigation special funds. 
System in Oklahoma. These values include all features of the 4. Includes $433,539 Emergency Relief funds. Exchange 
navigation system as listed in Section 1 of the text. Projects $1,256,068 from special contributed funds. 
which include power are also shown in their respective section 5. Excludes $299,803 contributed funds and $13,211,728 
of this report. special funds. 
1. Includes funds ($2,077,900) expended by the Jobs Act 6. Excludes $134,919 contributed funds. Includes $49,581 
(P.L. 98-8, dated March 24, 1983) for projects listed in Table Public Works acceleration funds. 
19-M of the Fiscal Year 1985 Annual Report. 7. Excludes $5,366,231 special funds. 
2. Beginning fiscal year 1984, data shown on Table A 8. Excludes $946 contributed funds. Includes $39,999 
includes special recreation use fees. Data for previous fiscal Public Works acceleration funds. 
years have been changed to conform to the new procedure. 
TABLE 19-B AUTHORIZING LEGISLATION 
See Date of Project 
Section Authorizing and Work 
In Text Act Authorized Documents 
1. July 24, 1946 McCLELLAN-KERR ARKANSAS RIVER HD 79-758, PL 525 
NAVIGATION SYSTEM 
3. December 31, 1970 
October 22, 1976 
4. 
October 23, 1962 
November 7, 1966 
December 31, 1970 
5. October 23, 1962 
6. October 23, 1962 
ARCADIA LAKE 
Change water quality to water supply 
ARKANSAS-RED RIVER BASINS CHLORIDE 
CONTROL 
Authorized Area V (Estelline Springs) 
Authorized Areas VII, VIII and X 
Authorized Areas I, II-III, VI, IX, XIII, XIV, and XV 
BIRCH LAKE 
CANDY LAKE 
HD 91-299 
PL 94-587 
SD 87-107 
PL 89-789, SD 110 
PL 91-611 
HD 87-563 
HD 87-563 
19-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
See 
Section 
In Text 
7. 
31. December 30, 1963 
32. June 28, 1938 
July 30, 1983 
37. July 3, 1958 
October 23, 1962 
38. July 24, 1946 
39. August 18,1941 
July 24, 1946 
40. August 18, 1941 
July 24, 1946 
TABLE 19-B 
(Continued) 
8. 
9. 
10. 
11. 
12. 
13. 
14. 
15. 
16. 
17. 
18. 
19. 
20. 
21. 
22. 
23. 
24. 
25. 
26. 
27. 
28. 
29. 
30. 
HD 75-569 
Date of 
Authorizing 
Act 
June 28, 1938 
July 24, 1946 
June 30, 1948 
October 23, 1962 
May 17, 1950 
October 27, 1965 
August 18, 1941 
August 18, 1941 
June 22, 1936 
June 22, 1936 
July 24, 1946 
July 24, 1946 
June 22, 1936 
May 17, 1950 
February 15, 1958 
October 23, 1962 
October 23, 1962 
Section 201 
May 17, 1950 
June 28, 1938 
June 22, 1936 
October 23, 1962 
October 23, 1962 
November 10, 1978 
July 3, 1958 
October 23, 1962 
December 4, 1981 
October 23, 1962 
August 18, 1941 
19-14 
AUTHORIZING LEGISLATION 
Project 
and Work 
Authorized Documents 
CANTON LAKE 
Approved Irrigation Storage 
Approved Water Supply Storage 
COPAN LAKE 
COUNCIL GROVE LAKE 
EL DORADO LAKE 
ELK CITY LAKE 
FALL RIVER LAKE 
FORT SUPPLY LAKE 
GREAT SALT PLAINS LAKE 
HEYBURN LAKE AND POLECAT CREEK 
HUGO LAKE 
HULAH LAKE 
JOHN REDMOND DAM AND RESERVOIR 
Authorized name change 
KAW LAKE 
LAKE KEMP 
MARION, KS 
MARION LAKE 
OOLOGAH LAKE 
OPTIMA LAKE 
PAT MAYSE LAKE 
PEARSON-SKUBITZ BIG HILL LAKE 
Authorized name change 
PINE CREEK LAKE 
SARDIS LAKE 
Authorized name change 
SKIATOOK LAKE 
TORONTO LAKE 
WAURIKA LAKE 
WISTER LAKE 
Conservation pool elevation changed 
BROKEN BOW LAKE 
EUFAULA LAKE 
FORT GIBSON LAKE 
Incorporated into the multiple-purpose plan 
for the Arkansas River Basin 
GRAND LAKE O' THE CHEROKEES 
Incorporated into the multiple-purpose plan 
for the Arkansas River 
HD 87-563 
HD 80-442 
HD 89-232 
HD 76-440 
HD 76-440 
HD 74-308 
HD 74-308 
HD 80-290 
HD 79-602 
HD 74-308 
HD 80-442 
PL 85-327 
HD 87-143 
HD 87-144 
HD 91-256 
HD 80-442 
Committee Doc. 
No. 1, 75th 
Cong, 1st Session 
HD 74-308 
HD 88-71 
HD 87-472 
PL 95-265 
HD 85-170 
SD 87-145 
PL 97-88 
HD 87-563 
HD 76-440 
PL 77-228 
SD 88-33 
PL 88-253 
Committee Doc. 
No. 1, 75th 
Cong, 1st Session 
PL 98-63 
HD 85-170 
SD 87-137 
HD 79-758 
HD 76-107 
HD 76-107 
PL 76-228

TULSA, OKLAHOMA, DISTRICT 
AUTHORIZING LEGISLATION 
See Date of Project 
Section Authorizing and Work 
In Text Act Authorized Documents 
41. May 17, 1950 KEYSTONE LAKE SD 81-07 
'42. LAKE TEXOMA (Denison Dam) 
June 28, 1938 Flood control and power HD 75-541 
October 17, 1940 Navigation and regulating flows PL 76-868 
September 30, 1944 Authorized name PL 78-454 
August 14, 1953 Water supply PL 83-273 
43. July 24, 1946 ROBERT S. KERR LOCK AND DAM AND RESERVOIR HD 79-758 
July 8, 1963 Authorized name change PL 88-62 
44. June 28, 1938 TENKILLER FERRY LAKE Committee Doc. 
No.1, 75th 
Cong, 1st Sess. 
June 24, 1946 Power HD 79-758 
45. July 24, 1946 WEBBERS FALLS LOCK AND DAM HD 79-758 
TABLE 19-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Poteau River Navigation Project, OK and AR Complete 1983 536,952 0 
Red River from Fulton, AR, to Mouth of Washita River Complete 1924 378,574 182,157 
TABLE 19-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Augusta L.P.P., KS' 
Big Pine Lake, TX 
Boswell Lake, OK 
Cedar Point Lake, KS 
Cherry and Red Fork Creeks L.P.P., OK 
Cow Creek L.P.P., KS 
Crutcho Creek L.P.P., OK 
El Dorado L.P.P., KS 
Enid L.P.P., OK 
Flat Rock Creek, Tulsa, L.P.P., OK2 
Florence L.P.P., KS 
Hutchinson L.P.P., KS 
Iola L.P.P., KS 
Jenks L.P.P., OK 
Lukfata Lake, OK 
Neodesha I:ake, KS 
Oklahoma City L.P.P., OK 
Red River Bank Stabilization Below Denison 
Sand Creek L.P.P., KS 
Sand Lake, OK 
Shidler Lake, OK 
Towanda Lake, KS 
Tulsa/West Tulsa L.P.P., OK 
Complete 
Deferred 
Deferred 
Deferred 
Complete 
Deferred 
Deferred 
Inactive 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Inactive 
Inactive 
Complete 
Complete 
Complete 
Deferred 
Deferred 
Inactive 
Complete 
1938 
1984 
1952 
1980 
1970 
1971 
1972 
1977 
1963 
1975 
1965 
1956 
1939 
1950 
1983 
1952 
1960 
1953 
1968 
1963 
1983 
1981 
1954 
1,701,670 
261,448 
363,720 
213,016 
92,319 
743,612 
1,741,000 
369,782 
3,497,718 
22,290 
344,797 
1,424,685 
97,910 
8,047,512 
222,105 
545,996 
568,191 
392,361 
2,785,070 
84,217 
14,599 
19-15 
TABLE 19-B 
(Continued)

TABLE 19-E 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Turtle Creek L.P.P., Yukon, OK Deferred 1975 144,853 - 
Tuskahoma Lake, OK Inactive 1963 - - 
West Branch Chisholm Creek L.P.P., KS Complete 1965 364,200 - 
Wichita and Valley Center L.P.P., KS Complete 1960 12,247,379 - 
Winfield L.P.P., KS' Complete 1937 - - 
L.P.P. - Local Protection Project. 
1. Completed by Kansas Works Progress Administration. 
2. Federal cost limited to $1,000,000. 
TABLE 19-H ARKANSAS RIVER BASIN MULTIPLE-PURPOSE PLAN 
(See Section 1 of Text) 
Feature River River Mile Nearest Town 
LAKES 
Canton North Canadian 394.3 Canton, OK 
Elk City Elk River 8.7 Elk City, KS 
Eufaula Canadian 27.0 Eufaula, OK 
Fall River Fall River 54.2 Fall River, KS 
Fort Gibson Grand (Neosho) 7.7 Fort Gibson, OK 
Grand Lake O' the Cherokees Grand (Neosho) 77.0 Disney, OK 
Keystone Arkansas 538.8 Sand Springs, OK 
Lake Hudson (Markham Ferry) Grand (Neosho) 47.4 Locust Grove, OK 
Neodesha Verdigris 222.8 Neodesha, KS 
Oologah Verdigris 90.2 Oologah, OK 
Tenkiller Ferry Illinois 12.8 Gore, OK 
Toronto Verdigris 271.5 Toronto, KS 
Wister Poteau 60.9 Wister, OK 
McCLELLAN-KERR ARKANSAS RIVER NAVIGATION SYSTEM, OK' 
(Tulsa District Portion) 
Bank Stabilization and Channel Rectification Verdigris and Arkansas N/Al Fort Smith, AR, to Catoosa, OK 
Chouteau Lock and Dam (17), OK Verdigris 401.5 Okay, OK 
Lock and Dam 13, AR Arkansas 292.8 Fort Smith, AR 
Newt Graham Lock and Dam (18), OK Verdigris 421.6 Inola, OK 
Robert S. Kerr Lock and Dam (15), OK Arkansas 339.0 Sallisaw, OK 
Robert S. Kerr Marine Terminal, OK Arkansas 336.2 Cowlington, OK 
Sans Bois Navigation Channel, OK Sans Bois Creek 341.0 Keota, OK 
W. D. Mayo Lock and Dam (14), OK Arkansas 319.6 Redland, OK 
Webbers Falls Lock and Dam (16), OK Arkansas 366.6 Gore, OK 
1. Navigation miles - McClellan-Kerr Arkansas River Navigation System. 
2. As required for channel 9 feet deep. 
19-16

TULSA, OKLAHOMA, DISTRICT 
INSPECTION OF COMPLETED LOCAL FLOOD 
PROTECTION PROJECTS 
(See Section 34 of Text) 
Projects Inspected in Fiscal Year Inspection Date 
Cherry and Red Fork Creeks, OK 
Deep Fork River, OK 
Dodge City, KS 
Enid, OK 
Flat Rock Creek, OK 
Florence, KS 
Hutchinson, KS 
Iola, KS 
Jenks, OK 
Joe Creek, OK 
Larned, KS 
Marion, KS 
Oklahoma City, OK 
Park City, KS 
Sand Creek, Newton, KS 
South Deer Creek, OK 
Tulsa/West Tulsa, OK 
Wichita and Valley Center, KS 
December 1986 
November 1984 
December 1986 
November 1986 
December 1986 
December 1986 
May 1986 
October 1985 
October 1986 
October 1985 
December 1986 
December 1986 
November 1986 
June 1986 
December 1986 
October 1986 
October 1986 
June 1986 
TABLE 19-J FLOOD DAMAGES PREVENTED BY CORPS 
AND NON-CORPS PROJECTS 
(See Section 35 of Text) 
Damages Prevented Cumulative Damages 
Name/Owner Fiscal Year 1986 Prevented 
CORPS PROJECTS 
Birch Lake, OK 
Broken Bow Lake, OK 
Canton Lake, OK 
Copan Lake, OK 
Council Grove Lake, OK 
El Dorado Lake, KS 
Elk City Lake, KS 
Eufaula Lake, OK 
Fall River Lake, KS 
Fort Gibson Lake, OK 
Fort Supply Lake, OK 
Great Salt Plains Lake, OK 
Heyburn Lake, OK 
Hugo Lake, OK 
Hulah Lake, OK 
John Redmond Dam and Reservoir, KS 
Kaw Lake, OK 
Keystone Lake, OK 
Lake Kemp, TX 
Lake Texoma, OK and TX 
Marion Lake, KS 
Oologah Lake, OK 
Optima Lake, OK 
Pat Mayse Lake, TX 
Pearson-Skubitz Big Hill Lake, KS 
TABLE 19-I 
1,070,000 
177,000 
42,000 
7,281,000 
1,899,000 
929,000 
2,076,000 
141,000 
2,561,000 
308,000 
47,000 
2,155,000 
620,000 
482,000 
11,280,000 
8,867,000 
10,686,000 
28,292,000 
24,000 
4,619,000 
6,074,000 
4,000 
162,000 
4,000 
5,570,000 
15,223,000 
6,755,000 
21,255,000 
16,759,000 
1,137,000 
40,952,000 
46,102,000 
33,590,000 
34,391,000 
3,111,000 
15,401,000 
7,001,000 
7,574,000 
95,879,000 
73,235,000 
24,973,000 
127,678,000 
3,153,000 
63,276,000 
35,986,000 
57,008,000 
11,000 
4,030,000 
67,000 
19-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 19-J FLOOD DAMAGES PREVENTED BY CORPS 
(Continued) AND NON-CORPS PROJECTS 
(See Section 35 of Text) 
Damages Prevented Cumulative Damages 
Name/Owner Fiscal Year 1986 Prevented 
CORPS PROJECTS (Continued) 
Pine Creek Lake, OK 1,015,000 11,127,000 
Sardis Lake, OK 1,358,000 4,153,000 
Skiatook Lake, OK 9,279,000 20,519,000 
Tenkiller Ferry Lake, OK 140,000 12,167,000 
Toronto Lake, KS 3,053,000 31,053,000 
Waurika Lake, OK 648,000 16,265,000 
Wister Lake, OK 6,956,000 72,362,000 
NON-CORPS PROJECTS 
Altus Reservoir, OK 42,000 3,337,000 
Bureau of Reclamation 
Arbuckle Reservoir, OK -426,000 
Bureau of Reclamation 
Cheney Reservoir, KS 368,000 7,634,000 
Bureau of Reclamation 
Fort Cobb Reservoir, OK 24,000 653,000 
Bureau of Reclamation 
Foss Reservoir, OK -1,272,000 
Bureau of Reclamation 
Grand Lake O' the Cherokees, OK 177,000 39,547,000 
Grand River Dam Authority 
Lake Meredith, TX 4,000 10,000 
Bureau of Reclamation 
Lake Hudson, OK 68,000 5,819,000 
(Markham Ferry Reservoir) 
Grand River Dam Authority 
Mountain Park Reservior, OK 59,000 594,000 
Bureau of Reclamation 
Norman Reservoir, OK 1,560,000 8,713,000 
Bureau of Reclamation 
LOCAL PROTECTION PROJECTS 
Cherry and Red Fork Creeks, OK - 1,500,000 
Enid, OK - 2,532,000 
Flat Rock Creek, OK - 1,000,000 
Florence, KS - 7,397,000 
Hutchinson, KS - 9,450,000 
Iola, KS 5,160,000 11,357,000 
Jenks, OK 610,000 1,736,000 
Joe Creek, OK - 11,200,000 
Marion, KS - 
Oklahoma City, OK - 11,845,000 
Sand Creek, Newton, KS - 623,000 
Tulsa and West Tulsa, OK 34,440,000 111,862,000 
West Branch Chisholm Creek, KS - 4,000 
Wichita and Valley Center, KS - 123,557,000 
19-18

TULSA, OKLAHOMA, DISTRICT 
TABLE 19-K FLOOD CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
(See Section 36 of Text) 
Fiscal Year 
Study Identification/Name Cost 
SMALL FLOOD CONTROL PROJECTS NOT SPECIFICALLY 
AUTHORIZED BY CONGRESS (Section 205) 
Bird Creek, Skiatook, OK 7,500 
Blackboy Creek, Tulsa, OK 41,628 
Box Elder Creek, Apache, OK 32,263 
Coal Creek, Henryetta, OK 107,411 
East Cache St. Lawton, OK 5,399 
Haikey Creek, Tulsa, OK 33,842 
Kingfisher Creek, OK 27,614 
Lamed, KS 0 
Line Creek and Washita River 42,262 
Little Wichita River, Clay County, TX 61,713 
Main Branch Chisholm Creek, Park City, KS 0 
Merkle Creek, Norman, OK 53,486 
North Canadian River Wastewater Plant, Oklahoma City, OK 46,120 
Squirrel Creek, North Canadian River, Shawnee, OK 52,224 
Squirrel Hollow Creek, Sand Springs, OK 10,383 
Stink/Driftwood Creeks, Burlington, OK 16,892 
Tar Creek, Miami, OK 24,689 
Whiskey and Rock Creeks, Independence, KS 111,774 
Whitewater River, Augusta, KS 7,500 
TOTAL SMALL FLOOD CONTROL PROJECTS 682,701 
EMERGENCY STREAMBANK AND SHORELINE PROTECTION (Section 14) 
Baron Fork (Camp Egan), OK 14,114 
Beaver Creek, Waurika (Pump Plant), OK 725 
Camp Creek, Pawnee County, OK 16,568 
County Bridge, Washita County, KS 77,196 
County Bridge, Washita County, KS 75,062 
Deer Creek, Custer County, OK 12,544 
Gaines Creek, Pittsburg County, OK 1,125 
Neosho River, Lyon County, KS 113,535 
Salt Fork, Red River, Elmer, OK 502 
Sewage Lagoon, Washita River, OK 6,563 
Sugar Creek, Binger, OK 627 
Washita River, Anadarko, OK 4,178 
Washita River, Caddo County, OK 7,097 
TOTAL EMERGENCY STREAMBANK AND SHORELINE PROTECTION 329,835 
SNAGGING AND CLEARING 
Cottonwood Creek, Guthrie, OK 116 
Little Caney River, Chautauqua County, OK 1,000 
TOTAL SNAGGING AND CLEARING 1,116 
FLOOD CONTROL AND COASTAL EMERGENCIES, REHABILITATION 
Dutton Levee, Neosho County, KS 25,850 
Edith Long Private Levee 8,233 
Five Various Levees, OK and KS 4,398 
Heath Allen and Rodolph Levee, KS 3,277 
Joe Creek Channel Improvement, Tulsa County, OK 425,409 
Nation Private Levee, Neosho County, KS 6,422 
Ray L. Jones Private Levee 2,781 
Richard Jarvis Private Levee 9,498 
Six Various Levees, OK and KS 11,899 
Skinner Evers Long Private Levee 3,354 
Tom Price Private Levee 6,054 
Tulsa/West Tulsa Levee 804,890 
TOTAL FLOOD CONTROL AND COASTAL EMERGENCIES, REHABILITATION 1,312,063 
19-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 19-L GENERAL INVESTIGATIONS 
(See Sections 46, 47, 48, and 49 of Text) 
Fiscal Year 
Study Identification/Name Cost 
SURVEYS 
Navigation Studies 
Arkansas River and Tributaries Hydropower and Other, OK 7 
Central Oklahoma Project .83,613 
Flood Damage Prevention Studies 
Arkansas River, Great Bend, KS, to Tulsa, OK 422,362 
Arkansas River Basin, AR and OK 33,061 
Canadian River Basin, OK, TX, and NM 225,445 
Grand (Neosho) River Basin, KS and OK 288,844 
Lake Texoma, OK and TX 100,634 
Poteau River, OK 106 
Red River Above Denison, TX and OK - 83 
Verdigris River Basin 28,365 
Verdigris River, KS and OK 4 
Arkansas-Red River Basins Solar Energy Investigations 0 
Comprehensive Studies 
Arkansas River and Tributaries, South Central-Southeast Areas, OK 416,755 
Red River Basin, AR, TX, LA, and OK 75,226 
Red River Basin, AR, TX, LA, and OK OM 395,797 
Review of Authorized Projects 
Restudy of Deferred Projects 
Lukfata Lake, OK 21,542 
Winfield, KS 160,501 
Review of Completed Projects 
Hugo Lake, OK 113,111 
Pine Creek Lake, OK 58,047 
Review for Deauthorization 
Crutcho Creek, OK 8,868 
El Dorado, West Branch, Walnut River, KS 3 
Inventory of Dams - Special Investigations 23,896 
Coordination with Other Federal Agencies, States, and Non-Federal Interests 
Soil Conservation Service 3,732 
Bureau of Reclamation 4,974 
Planning Assistance to States - Texas 20,744 
Planning Assistance to States - Kansas 59,772 
Planning Assistance to States - Oklahoma 175,154 
TOTAL SURVEYS 2,720,478 
COLLECTION AND STUDY OF BASIC DATA 
Flood Plain Management Services 
Flood Plain Management Services 99,940 
Technical Services General 199,253 
Hydrologic Studies 
Storm Studies 5,844 
TOTAL COLLECTION AND STUDY OF BASIC DATA 305,037 
CONTINUATION OF PLANNING AND ENGINEERING 
Local Protection 
Arkansas River, Great Bend to Tulsa, Halstead 42,904 
Lake Wichita, Holliday Creek, McGrath Creek, TX 1,762 
Lake Wichita, Holliday Creek, TX 21,609 
Mingo Creek, OK 674,823 
Flood Control Reservoirs 
Parker Lake, OK 592,511 
TOTAL CONTINUATION OF PLANNING AND ENGINEERING 1,333,609 
19-20

TULSA, OKLAHOMA, DISTRICT 
TABLE 19-L 
(Continued) 
GENERAL INVESTIGATIONS 
(See Sections 46, 47, 48, and 49 of Text) 
Fiscal Year 
Study Identification/Name Cost 
ADVANCED ENGINEERING AND DESIGN 
Navigation Project 
Big and Little Sallisaw Creeks, OK 786 
Local Protection 
Great Bend, KS 159,658 
Flood Control Reservoirs 
Douglass Lake, KS 229,944 
TOTAL ADVANCED ENGINEERING AND DESIGN 390,387 
19-21

KANSAS CITY, MO., DISTRICT * 
The district comprises a portion of southwestern Iowa; 
northwestern, central, and western Missouri; northern Kansas; 
southern Nebraska; and a portion of northeastern 
Colorado embraced in drainage basin of the Missouri River 
and tributaries from Rulo, Nebraska, to the mouth. Report 
on navigation project for section of Missouri River from 
Sioux City, Iowa, to Rulo, Nebraska, is in report of Omaha 
District. 
IMPROVEMENTS 
Navigation Page 
1. Missouri River, Sioux City, IA to 
Mouth (Rulo, NE, to Mouth)................20-2 
Flood Control 
2. Blue River Channel, Kansas City, MO ........ 20-2 
3. Clinton Lake, Wakarusa River, KS .......... 20-2 
4. Harlan County Lake, Republican 
River, NE ............... ................. 20-2 
5. Hillsdale Lake, Big Bull Creek, KS..........20-3 
6. Kanopolis Lake, Smoky Hill River, KS ....... 20-3 
7. Little Blue River Channel Improvement, 
Little Blue River, MO ..................... 20-3 
8. Little Blue River Lakes, MO ............... 20-3 
9. Long Branch Lake, Little Chariton 
River, M O ............................... 20-4 
10. Melvern Lake, Marais des Cygnes 
(Osage) River, KS ...................... 20-4 
11. Milford Lake, Republican River, KS ......... 20-4 
12. Missouri River Levee System, IA, NE, 
KS, and MO (Rulo, NE to Mouth) ........... 20-5 
13. Perry Lake, Delaware River, KS ............ 20-5 
14. Pick-Sloan Missouri Basin Program 
(Kansas City Dist.) ....................... 20-5 
15. Pomme de Terre Lake, Pomme de Terre 
River, M O ................................ 20-5 
16. Pomona Lake, One Hundred Ten Mile 
Creek, KS ............................... 20-6 
17. Rathbun Lake, Chariton River, IA............ 20-6 
18. Smithville Lake, Little Platte River, MO ...... 20-6 
19. Tattle Creek Lake, Big Blue River, KS ....... 20-6 
20. Wilson Lake, Saline River, KS .............. 20-7 
21. Scheduling Flood Control 
Reservoir Operations......................20-7 
Flood Control (cont.) Page 
22. Inspection of Completed Flood 
Control Projects..........................20-7 
23. Inspection of Non-Federal Levees ........... 20-7 
24. Flood Control Work Under Special 
Authorization ............................ 20-7 
Multiple Purpose Projects Including Power 
25. Harry S. Truman Dam and Reservoir, 
Osage River, MO ......................... 20-8 
26. Stockton Lake, Sac River, MO .............. 20-9 
General Investigations 
27. General Investigations.....................20-9 
27A. Brush Creek, Kansas City, MO ............ 20-9 
Tables 
Table 20-A Cost & Financial Statement.........20-10 
Table 20-B Authorizing Legislation ............ 20-13 
Table 20-C Other Authorized Navigation 
Projects..........................20-16 
Table 20-D Not Applicable 
Table 20-E Other Authorized Flood Control 
Projects ......................... 20-17 
Table 20-F Not Applicable 
Table 20-G Deauthorized Projects..............20-18 
Table 20-H Missouri River Levee System ........ 20-18 
Table 20-I Kansas City District Projects 
Included in Pick-Sloan Missouri 
Basin Program .................... 20-19 
Table 20-J Inspection of Completed Flood 
Control Projects .................. .20-19 
Table 20-K Active General Investigations ........ 20-20 
Table 20-L Flood Control Activities Under 
Special Authorization ............... 20-21 
20-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. MISSOURI RIVER, SIOUX CITY, IA, 
TO MOUTH (RULO, NE, TO MOUTH) 
Location. Jefferson, Madison, and Gallatin Rivers conjoin 
at Three Forks, Montana, to form the Missouri River, 
which flows southeasterly 2,315 miles (1960 mileage) across 
or along seven states to the Mississippi River, 17 miles above 
St. Louis. For description see page 1149, Annual Report 
for 1932. The river is commercially navigable from Sioux 
City, Iowa, to the mouth, a distance of 732 miles. The portion 
of project in Kansas City District extends from Rulo, 
Nebraska, to the mouth, a distance of 498 miles. 
Previous Projects. For details see page 1891 of Annual 
Report for 1915, and pages 1153 and 1175 of Annual Report 
for 1938. 
Existing Project. A channel of 9-foot depth and width 
not less than 300 feet, obtained by revetment of banks, construction 
of permeable dikes to contract and stabilize the 
channel, cutoffs to eliminate long bends, closing minor channels, 
removal of snags, and dredging as required. The improved 
reach within the Kansas City District extends from 
the mouth to the upper end of Rulo Bend, a distance of 498.4 
miles. The Bank Stabilization and Navigation features of 
the project were completed in September 1980. For the 
reach from Rulo, Nebraska, to the mouth, the total construction 
cost was $237,942,190 including $8,665,594 for previous 
project. River access sites have been completed at 11 locations. 
Ordinary and extreme fluctuations of stage are 16 
and 38 feet, respectively. 
Local cooperation. Cooperation from benefited localities 
may be required where any improvement may confer special 
benefit. The receipt of contributions from private parties 
are to be expended along with Government funds upon 
authorized work where such work would be in the interest 
of navigation, as authorized by 1915 Rivers and Harbors 
Act. Secretary of the Army approved general principle of 
cooperative construction on Missouri River below Kansas 
City on basis that 25 percent of cost of any special installation 
shall be paid by the United States and 75 percent by 
local interests. Total contributed by local interests in 
cooperation with the United States from 1918 to June 30, 
1964, was $675,663, of which $8,647 was returned to contributors. 
Local interests must share in cost of recreation 
facilities in accordance with provisions of the Federal Water 
Project Recreation Act of 1965. Local interests have contributed 
$171,816 for cost sharing on construction of recreation 
in addition to constructing portions of the facilities. 
Terminal facilities. A listing of terminal facilities are included 
in Missouri River Navigation Charts and can be obtained 
from Kansas City District Engineer for a small fee. 
Operations during fiscal year. The 1974 Base Line 
Study of the reach of the Missouri River in the Kansas City 
District estimated recreation use on the river at 1,250,000 
recreation days annually. The projected tonnage on the river 
for FY 1986 is approximately 2.0 million. Maintenance: 
Repair of dikes and revetments by contract. In addition, 
following work was accomplished by hired labor: Construction 
of environmental gaps and dike and revetment repair, 
real estate management, channel reconnaissance, condition 
studies, surveys and mapping, stream gauging, environmental 
studies and special working data, engineering and 
design, surveys and layout of construction, and supervision 
and administration. There was no dredging because no 
significant bars or shoals developed. 
Flood Control 
2. BLUE RIVER CHANNEL, 
KANSAS CITY, MO 
Location. Along the Blue River and tributaries in 
Jackson County, Missouri. 
Existing project. Preliminary plans consist of 12.5 miles 
of improved channel along the Blue River within Kansas 
City, Missouri. Estimated Federal cost through construction 
of the project (1986) is $162,000,000, and estimated 
non-Federal cost of lands, damages and relocations is 
$22,200,000. 
Local cooperation. Section 2, Flood Control Act of 
June 22, 1936 applies. The city of Kansas City, Missouri, 
passed a resolution of intent on December 9, 1975 to provide 
the required assurances of local cooperation when requested. 
The Section 221 agreement was signed by the Kansas 
City District Engineer on September 8, 1983. 
Operations during fiscal year. Preconstruction planning 
is complete and final designs are underway. The first channel 
contract is complete, and the second contract is nearing 
completion. Relocation contracts had been negotiated 
with four railroad companies and construction is underway. 
3. CLINTON LAKE, WAKARUSA 
RIVER, KS 
Location. Damsite is on Wakarusa River about 4 miles 
southwest of Lawrence, Kansas, in Douglas County. Lake 
extends into Shawnee and Osage Counties, Kansas. 
Exiting project. An earthfill dam about 9,250 feet long 
constructed to a height of about 114 feet with an uncontrolled 
spillway in left abutment. Total reservoir storage 
capacity 397,200 acre-feet (258,300 for flood control, 28,500 
for sediment reserve, and 110,400 of multipurpose storage 
for municipal and industrial waste supply and recreation). 
Cost of constructing the completed project was $57,415,433. 
Construction was initiated in January 1972, and the project 
was placed in operation in November 1977. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938 applies. Reimbursement in the estimated 
amount of $6,768,000 is required for water supply storage 
in accordance with Water Supply Act of 1958. A contract 
was signed by the State on September 6, 1978 and was approved 
by the Secretary of the Army on October 30, 1978. 
Utilization of storage was initiated in December 1979. 
Repayment also began at that time. 
Operations during fiscal year. Visitation for FY 1986 
was 1,305,500 visitor days. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
4. HARLAN COUNTY LAKE, 
REPUBLICAN RIVER, NE 
20-2

KANSAS CITY, MO., DISTRICT 
Location. Dam is on main stem of Republican River 
about 235 miles above confluence of stream with Smoky 
Hill River. Site is in Harlan County, about 3 miles east of 
Republican City and 13 miles west of Franklin, Nebraska. 
Existing project. An earthfill dam about 107 feet above 
streambed with a total length of 11,827 feet, including a 
gate-controlled, concrete, gravity-type spillway section near 
center of dam. Reservoir provides storage capacity of 
850,000 acre-feet (500,000 for flood control and 350,000 for 
irrigation and sedimentation allowance). Initial cost of constructing 
the project was $45,279,532. Total Federal cost 
of project, including $1,017,623 for major rehabilitation 
work and $1,832,394 supplemental recreation development 
(Code 710), is $48,129,549. Construction of the project was 
initiated in August 1946. Project was placed in operation 
in December 1952. Major rehabilitation work was completed 
in FY 1968. 
Local cooperation. Section 2, Flood Control Act of 1938, 
applies. 
Operations during fiscal year. Visitation for FY 1986 
was 906,400 visitor days. Maintenance: Activities included 
stilling basin repair and other ordinary operation and 
maintenance activities. 
5. HILLSDALE LAKE, BIG BULL 
CREEK, KS 
Location. The project is located approximately 12 miles 
above the mouth of Big Bull Creek, a tributary of the Marais 
des Cygnes River and about 15 miles southwest of the Kansas 
City metropolitan area in Miami County, Kansas. 
Existing project. An earthfill embankment about 11,600 
feet long (including approximately 3,300 feet of dike section) 
about 75 feet above rising valley flood plain. The 
spillway is gravity type uncontrolled and the outlet works 
are controlled. The total reservoir storage capacity is 
160,000 acre-feet (81,000 for flood control, 11,000 for sediment 
reserve, and 68,000 for multipurpose storage for water 
supply, water quality control, and recreation). Construction 
was initiated in December 1974 and project was placed in 
operation in October 1981. Federal cost of construction is 
$64,161,400. 
Local cooperation. Section 2, Flood Control Act 1938, 
applies. Local interests must make reimbursement of 
$23,342,756 for water supply storage in accordance with 
Water Supply Act of 1958. The Kansas Water Resources 
Board signed a contract in January 1974, approved by the 
Secretary of the Army in April 1974, for the entire 53,000 
acre-feet of water supply storage. Local interests have 
shown no interest in sponsoring recreational development 
at this time. Therefore, only minimum recreational facilities 
have been built. 
Operations during fiscal year. Visitation for FY 1986 
was 430,400 visitor days. Settlement of a dispute on the 
Miami County Road Relocation contract for design and construction 
of road relocations resulted in financial completion 
of this contract. Maintenance: Activities consisted of 
ordinary operation and maintenance. 
6. KANOPOLIS LAKE, SMOKY 
HILL RIVER, KS 
Location. IDam is on Smoky Hill River about 19 miles 
west and 16 miles south of Salina, Kansas, and about 205 
river miles above mouth of stream. 
Existing project. An earthfill dam about 131 feet above 
streambed, having a total length of 15,360 feet, including 
4,070 feet of dike section on the left abutment and 2,550 
feet of dike section on right abutment. The reservoir provides 
storage capacity of 450,000 acre-feet, (400,000 for 
flood control and 50,000 for recreation and streamflow 
regulation). Outlet works and spillway are in right abutment. 
Initial cost of constructing the project was $12,327,735. 
TIbtal Federal cost of project, including $249,492, supplemental 
recreational development (Code 710), is $12,577,227. 
Construction was initiated in June 1940 and project was 
placed in operation in May 1948. 
Local cooperation. Section 2, Flood Control Act of 1938, 
applies. 
Operations during fiscal year. Visitation for FY 1986 
was 585,300 visitor days. Maintenance: Activities included 
drain installation, construction of administration building, 
replacement of piezometer tubes, and ordinary operation 
and maintenance. 
7. LITTLE BLUE RIVER CHANNEL 
IMPROVEMENT, LITTLE BLUE 
RIVER, MO 
Location. The project is located along the Little Blue 
River and extends from the head of Missouri River Levee 
Unit R 351, 22 miles upstream to the vicinity of Wildwood 
Creek in Jackson County, Missouri. 
Existing project. The improvements consist of 
straightening and enlarging the Little Blue River channel 
from the head of Missouri River Levee Unit R 351, near 
Blue Mills Road, upstream to the vicinity of Wildwood 
Creek, reducing the length of this section from 20.4 to about 
15 miles. Alteration of six highway bridges and construction 
of five new highway bridges and one railroad bridge 
were required. Improvements in the vicinity of Lake City 
Army Ammunition Plant consists of diversion of West Fire 
Prairie Creek into the Little Blue River and construction 
of a levee. Estimated Federal cost through construction of 
the project (1984) is $25,505,083 and estimated non-Federal 
cost is $3,390,000. Construction was initiated in December 
1974. 
Local cooperation. Section 3, Flood Control Act of June 
22, 1936, applies to the Little Blue River channel improvement 
works. Jackson County, Missouri, passed a bond issue 
for sponsorship of the project. Assurances of local cooperation 
were furnished July 31, 1973. 
Operations during fiscal year. Project is physically complete, 
but not fiscally. 
8. LITTLE BLUE RIVER LAKES, MO 
Location. This project consists of two lakes in Jackson 
County, Missouri, located in Kansas City, Missouri, and 
suburban communities. The Blue Springs Lake site is on 
20-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
the East Fork of the Little Blue River about one-half mile 
south of U.S. Highway 40 and the Longview Lake site is 
on the main stem at approximately 109th Street. 
Existing project. The Blue Springs dam will be an earthfill 
embankment about 2,500 feet long and rising about 78 
feet above the streambed, with an uncontrolled service 
spillway and uncontrolled outlet conduit. The total reservoir 
storage capacity will be 26,600 acre-feet (15,700 for 
flood control, 10,600 for multipurpose storage for water 
quality and recreation, and 300 for sedimentation). 
The Longview dam is an earthfill embankment about 
1,900 feet long and rising about 120 feet above the streambed, 
with an uncontrolled service spillway and an uncontrolled 
outlet conduit. The total reservoir storage capacity 
will be 46,900 acre-feet (24,300 for flood control and 20,600 
for multipurpose storage for water quality and recreation, 
and 2,000 for sedimentation). Estimated Federal cost (1986) 
for both lakes through construction of the project is 
$138,900,000. Construction was initiated in September 
1977. 
Local cooperation. Section 2 of the Flood Control Act 
of June 28, 1938 applies. Local interests must share in 
separable cost allocated to recreation in accordance with 
Federal Water Project Recreation Act of 1965. The Jackson 
County Legislature approved a recreation cost-sharing contract 
on July 5, 1974 which was approved by the Secretary 
of the Army on June 24, 1976. A supplemental agreement, 
signed by Jackson County officials on June 5, 1978, and approved 
by the Secretary of the Army January 10, 1979, 
revised the existing contract to include additional costs involved 
in raising the multipurpose pool elevation at the Blue 
Springs Lake. Estimated reimbursement for recreation is 
$15,050,000 of which $420,000 will be accomplished during 
construction by local interests. 
Operations during fiscal year. Longview Lake is essentially 
complete except for recreation facilities. Blue Springs 
dam, recreation facilities, and administrative facilities are 
underway. Project is 94 percent complete. Land acquisition 
is complete. 
9. LONG BRANCH LAKE, LITTLE 
CHARITON RIVER, MO 
Location. Damsite is on East Fork of Little Chariton 
River in north-central Missouri about 1 mile west of Macon 
in Macon County. 
Existing project. An earthfill dam about 3,800 feet long 
and about 71 feet high with an uncontrolled outlet conduit 
and an uncontrolled service spillway in right abutment. Total 
reservoir storage capacity will be 65,000 acre-feet (29,000 
for flood control, 4,000 for sediment reserve, and 32,000 of 
multipurpose storage for water supply, water quality control, 
fish and wildlife, and recreation). Estimated Federal 
cost (1986) is $20,503,000, and estimated non-Federal cost 
is $3,797,000. Construction was initiated in March 1973. 
Project was placed in useful operation for flood control on 
September 1, 1980. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938 applies. Local interests must make reimbursement 
of $5,588,000 for water supply storage in accordance 
with Water Supply Act of 1958 and share in separable 
cost of $3,797,000 allocated to recreation in accordance with 
Federal Water Project Recreation Act of 1965. On 
September 15, 1972 the Secretary of the Army approved 
a contract signed by the city of Macon, Missouri, for water 
supply and recreation development. Missouri State agencies 
indicated their intent to sponsor future water supply 
and signed a contract on June 17, 1977 to sponsor recreational 
development in lieu of city of Macon. After review 
by the Office of the Secretary of the Army, the state signed 
the contract in December 1979, and it was approved by the 
Secretary of the Army on April 18, 1980. 
Operations during fiscal year. Visitation for FY 1986 
was 588,400 visitor days. Design of Stage 4 recreation 
facilities was completed and contract awarded. Project is 
97 percent complete on scheduled work. The remaining 
work is construction of recreation facilities. Maintenance: 
Activities consisted of ordinary operation and maintenance. 
10. MELVERN LAKE, MARAIS DES 
CYGNES (OSAGE) RIVER, KS 
Location. Damsite is on Marais des Cygnes (Osage) River 
in Osage County, Kansas, about 2 miles west of Melvern, 
Kansas. 
Existing project. An earthfill dam about 9,700 feet long 
and about 98 feet high with an uncontrolled chute-type 
spillway in left abutment. Total reservoir storage capacity 
is 363,000 acre-feet (200,000 for flood control, 26,000 for 
sediment reserve, and 137,000 of multipurpose storage for 
water quality control, and recreation). Cost of constructing 
the completed project was $37,436,530. Construction was 
initiated in July 1967, and the project was placed in operation 
in August 1972. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Visitation for FY 1986 
was 819,400 visitor days. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
11. MILFORD LAKE, REPUBLICAN 
RIVER, KS 
Location. Damsite is on Republican River near village 
of Alida and about 8 miles downstream from Milford, Geary 
County, Kansas, and about 10 miles above confluence of 
Republican and Smoky Hill Rivers which form Kansas River 
near Junction City, Kansas. 
Existing project. An earthfill dam about 6,300 feet long 
and 126 feet high with an uncontrolled service-chute 
spillway in a saddle on right abutment. Total reservoir 
storage capacity is 1,160,000 acre-feet (700,000 for flood 
control, 160,000 for sediment reserve and 300,000 of 
multipurpose storage for water supply, water quality control, 
and recreation). Water supply storage is included in 
project at request of Governor of Kansas under provisions 
of Federal Water Supply Act of 1958. Initial cost of constructing 
the completed project was $48,268,843. Total 
20-4

KANSAS CITY, MO., DISTRICT 
Federal cost of project, including $1,297,649 supplemental 
recreational development (Code 710), is $49,566,492. Construction 
was initiated in July 1961. Project was' placed in 
operation in June 1965. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Local interests must make reimbursement of 
$13,045,576 for water supply storage in accordance with 
Water Supply Act of 1958. Utilization of storage has not 
been initiated. Reimbursement was initiated, at the option 
of the State, in September 1976. 
Operations during fiscal year. Visitation for FY 1986 
was 1,309,000 visitor days. Maintenance: Activities included 
continuation of seismic reevaluation and ordinary operation 
and maintenance. 
12. MISSOURI RIVER LEVEE 
SYSTEM, IA, NE, KS, AND MO 
(RULO, NE, TO MOUTH) 
Location. On both banks of Missouri River from Sioux 
City, Iowa, about 760 miles to mouth near St. Louis, 
Missouri. Portion of project in Kansas City District extends 
from Rulo, Nebraska, 498 miles to mouth. 
Existing project. A series of levee units and appurtenant 
works along both sides of Missouri River from Sioux 
City, Iowa, to the mouth, for protection of agricultural lands 
and small communities against floods. Estimated cost 
(1986) for the active portion of the project from Rulo, 
Nebraska, to mouth is $250,300,000, including $216,300,000 
Federal and $34,000,000 non-Federal contributions. Costs 
of $25,600,000 for lands and damages are to be borne by 
local interests. Remaining portion of project consists of units 
on which planning and construction are being delayed pending 
completion of restudy to assure that additional levee 
construction is economically justified. Cost estimate for deferred 
and inactive portion of project Rulo, Nebraska, to 
mouth is $253,558,000 (1964 price level), of which 
$233,412,000 is Federal cost for construction and 
$20,146,000 for lands and damages to be borne by local interests. 
Construction of the project was initiated in June 
1948. 
Local cooperation. Section 3, Flood Control Act of 1936 
applies. Fully complied with for all completed units and 
units under construction. Sponosor for Unit L 330-345 has 
optioned the major part of lands for rights-of-way. Because 
of anticipated changes as a result of the National Environmental 
Policy Act of 1969, the District advised the 
sponsor to-suspend condemnation proceedings for remaining 
requirements pending development of an alternate plan. 
Local sponsors provide all operation and maintenance. 
Operations during fiscal year. Status of individual units 
of active portion of project at end of fiscal year is shown 
in Table 20-H on Missouri River levee system. Reconnaissance 
report for remedial work on L 246 was approved. 
Planning on remaining active units continued. 
13. PERRY LAKE, DELAWARE 
RIVER, KS 
Location. Damsite is on Delaware River about 5 miles 
above mouth in Jefferson County, Kansas, about 3 miles 
north of Perry, Kansas 
Existing project. An earthfill dam about 7,750 feet long 
constructed to an elevation about 95 feet above valley floor 
with gated-outlet works and an uncontrolled spillway in left 
abutment. Total reservoir storage capacity is 770,000 acrefeet 
(480,000 for flood control, including 140,000 for sediment 
reserve and 150,000 of multipurpose storage for water 
supply, water quality control, and recreation). Water supply 
storage is included in project plan at request of State 
of Kansas under provisions of Federal Water Supply Act 
of 1958. Initial cost of constructing the completed project 
was $48,371,706. Total Federal cost of project, including 
$724,212 supplemental recreational development (Code 
710), is $49,095,918. Construction was initiated in March 
1964, and the project was placed in operation in January 
1969. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Local interests must make reimbursement of 
$9,208,342 for water supply storage in accordance with 
Water Supply Act of 1958. Utilization of storage has not 
been initiated. Reimbursement was initiated at the option 
of the State in September 1978. 
Operations during fiscal year. Visitation for FY 1986 
was 1,515,100 visitor days. Maintenance: Activities included 
preparation of plans and specifications and award of contract 
for replacement of relief wells, removation of Slough 
Creek PUA, and ordinary operation and maintenance. 
14. PICK-SLOAN MISSOURI BASIN 
PROGRAM (KANSAS CITY DIST.) 
Location. Flood control improvements included in this 
project are on and along the Missouri River and several of 
its principle tributaries, in states comprising the Missouri 
River Basin. 
Existing project. The Pick-Sloan Missouri Basin program 
for flood control and other purposes in Missouri River 
Basin provides for levees along Missouri River between 
Sioux City, Iowa, and the mouth, flood-protection works at 
certain municipalities, and reservoirs on main stem of 
Missouri River and on tributaries for control of flooding. 
(See Table 20-B for authorizing legislation and Table 20-I 
on Kansas City District projects included in Pick-Sloan 
Missouri Basin program.) See individual project reports. 
15. POMME DE TERRE LAKE 
POMME DE TERRE RIVER, MO 
Location. Dam is on main stem of Pomme de Trre River, 
about 44 miles above mouth of stream in Hickory County, 
Missouri. The lake extending upstream into Polk County, 
Missouri. Site is about 3 miles south of Hermitage, Missouri, 
and 20 miles north of Bolivar, Missouri. 
Existing project. An earth and rockfill dam about 4,630 
feet long constructed to about 155 feet above riverbed and 
a dike section on left abutment about 2,790 feet long, providing 
storage capacity of 650,000 acre-feet (407,000 for 
flood control and 243,000 for sedimentation and multipurpose). 
Initial cost of constructing the completed 
20-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
project was $14,946,784. Total Federal cost of project, including 
$329,140 area redevelopment and $2,089,529 supplemental 
recreational development (Code 710), is 
$17,365,453. Construction was initiated in January 1957, 
and the project was placed in useful operation in October 
1961. 
Operations during fiscal year. Visitation for FY 1986 
was 1,318,700 visitor days. Maintenance: Activities consisted 
of modification of the administration building and 
ordinary operation and maintenance. 
16. POMONA LAKE, ONE HUNDRED 
TEN MILE CREEK, KS 
Location. Dam is on One Hundred Ten Mile Creek, a 
tributary of Marais des Cygnes (Osage) River, 7 miles above 
mouth of stream in Osage County, Kansas, about 7 miles 
northwest of Pomona, Kansas, and 34 miles upstream from 
Ottawa, Kansas. 
Existing project. An earthfill dam 7,750 feet long constructed 
to an average height of about 85 feet above 
streambed, with gated-outlet workes and an ungated chutetype 
spillway near left abutment. Total reservoir storage 
capacity is 230,000 acre-feet (160,000 for flood control, 
14,000 for sediment reserve, and 56,000 of multipurpose 
storage for water quality control, and recreation). Initial 
cost of constructing the completed project was $13,272,108. 
Total Federal cost of project, including supplemental recreational 
development $731,130 (Code 710), is $14,003,238. 
Construction began in July 1959, and the project was placed 
in operation in October 1963. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Pomona has water supply reimbursement under 
Water Supply Act of 1958 totaling $71,018. 
Operations during fiscal year. Visitation for FY 1986 
was 579,500 visitor days. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
17. RATHBUN LAKE, CHARITON 
RIVER, IA 
Location. Damsite is on Chariton River about 7 miles 
north of Centerville and 1 mile north of town of Rathbun, 
Appanoose County, Iowa. 
Existing project. An earthfill dam 10,600 feet long constructed 
to an elevation about 86 feet above valley floor, with 
gated-outlet works and an uncontrolled service chute with 
paved sill spillway about a mile upstream from left abutment. 
Total reservoir storage capacity is 552,000 acre-feet 
(339,000 for flood control, 24,000 for sediment reserve and 
189,000 of multipurpose storage for navigation, water quality 
control, and recreation). Initial cost of constructing the 
project was $27,033,210. Total Federal cost of project, including 
$588,948 supplemental recreation development 
(Code 710), is $27,622,158. Construction of the project was 
initiated in September 1964 and completed in November 
1969. The operating plan for this project was revised to 
reduce flood control releases during critical times of the 
year to allow local farmers better access during planting 
and harvesting and to facilitate field drainage and drying 
out. The revised plan has resulted in more frequent high 
pool elevations than anticipated, which has inundated roads 
and recreation facilities. A shoreline erosion study was accomplished, 
and a supplement to the master plan has been 
approved recommending relocation of recreation facilities 
and bank stabilization affected by the higher lake levels. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Visitation for FY 1986 
was 941,600 visitor days. Maintenance: Activities included 
renovation of relief wells, initiation of construction of Island 
View shower building, and ordinary operation and 
maintenance activities. 
18. SMITHVILLE LAKE, LITTLE 
PLATTE RIVER, MO 
Location. Damsite is on Little Platte River about 1 mile 
northeast of Smithville and about 5 miles north of Kansas 
City, in Clay and Clinton Counties, Missouri. 
Existing project. Earthfill dam about 4,200 feet long and 
95 feet high with an uncontrolled service spillway. A dike 
about 2,400 feet long crosses a saddle in left abutment. Total 
reservoir storage capacity is 246,500 acre-feet (92,000 for 
flood control, 52,300 for sediment reserve, and 102,200 of 
multipurpose storage for water supply, water quality control, 
and recreation). Estimated Federal cost (1986) through 
construction of the project is $87,835,000. Construction was 
initiated in November 1973, and the project was placed in 
operation in March 1982. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938 applies. Reimbursement of $24,000,000 will 
be required for water supply storage in accordance with 
Water Supply Act of 1958 and reimbursement of $7,500,000 
will be required for recreation development in accordance 
with Federal Water Project Recreation Act of 1965. Additional 
non-Federal contribution for recreation amounts to 
$737,000. All contracts for local cooperation were approved 
by the Secretary of the Army on November 27, 1972. 
Operations during fiscal year. Visitation for FY 1986 
was 1,313,200 visitor days. Project is physically complete, 
but not financially complete. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
19. TUTTLE CREEK LAKE, BIG 
BLUE RIVER, KS 
Location. Dam is on main stem of Big Blue River, about 
12 miles above the mouth of stream in Riley and Pottawatomie 
Counties, Kansas. Site is about 12 miles northwest 
of Manhattan, Kansas. 
Existing project. An earth and rock dam 7,500 feet long 
and 157 feet high. Total reservoir storage capacity is 
2,346,000 acre-feet (1,933,000 for flood control, 228,000 for 
sediment reserve and 185,000 for multipurpose storage, for 
low-flow regulation, navigation, and recreation). Initial cost 
of constructing the completed project was $80,051,031. Total 
Federal cost of project, including $533,048 supplemental 
recreational development (Code 710), is $80,584,079. Construction 
began in October 1952. Project was placed in 
operation in July 1962. 
20-6

KANSAS CITY, MO., DISTRICT 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Visitation for FY 1986 
was 958,500 visitor days. Maintenance: Activities included 
boundary rectification and ordinary operation and 
maintenance. 
20. WILSON LAKE, SALINE RIVER, KS 
Location. Dam is on Saline River about 130 miles above 
its mouth, near eastern edge of Russell County, Kansas, 
about 50 miles west of Salina, 10 miles north of Wilson, and 
20 miles east of Russell, Kansas. 
Existing project. An earthfill dam about 5,600 feet long 
and 160 feet high with a gated-outlet works, chute spillway, 
storage capacity is 776,000 acre-feet (511,000 for flood control, 
40,000 for sediment reserve and 225,000 multipurpose 
storage for irrigation, navigation, and low flow regulation). 
Initial cost of constructing the project was $20,015,023. 
'btal Federal cost of project, including $448,344 supplemental 
recreational development (Code 710), is $20,463,367. 
Construction began in April 1961 and the project was placed 
in operation in December 1964. 
Local cooperation. Section 2, Flood Control Act of 1938, 
applies. 
Operations during fiscal year. Visitation for FY 1986 
was 618,500 visitor days. Maintenance: Activity consisted 
of ordinary operation and maintenance. 
21. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Under sections 7 and 9, 1944 Flood Control Act, the Corps 
is responsible for detailed scheduling of operations concerning 
storage capacity reserved for or assigned to flood control 
in reservoirs constructed by Bureau of Reclamation as 
well as those constructed by the Corps. 
22. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, P.L. 738, and subsequent 
acts require local interests to furnish assurances that 
they will maintain and operate certain local protection projects 
after 'completion in accordance with regulations 
prescribed by the Secretary of the Army. District Engineers 
are responsible for administration of these regulations 
within boundaries of their respective district. (See Table 
20-J on inspection of completed flood control projects.) 
23. INSPECTION OF NON-FEDERAL 
LEVEES 
Non-Federal flood protection works constructed or 
rehabilitated under P.L. 84-99 must be inspected by the 
Corps of Engineers to assure compliance with local cooperation 
agreements. As of July 16, 1986, new maintenance 
guidelines were established which require the Corps to perform 
more extensive, geotechnical inspections than in the 
past. 
24. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and 
Antecedent Legislation). 
Operations for period October 1, 1985 thru September 
30, 1986 were as follows: 
Disaster Preparedness Program, includes planning, 
training, inspection, supplies and equipment and personnel. 
Flood Fighting and Rescue Work, for three flood events 
on the Missouri River and tributaries. A fourth event was 
declared on September 30, 1986 and terminated in November 
1986. 
Rehabilitation of both non-Federal farm levees, and 
Federal authorized levees and control works damaged as 
a direct result of flooding. 
(See Table 20-L for costs.) 
Small Flood Control Projects Not Specifically 
Authorized by Congress (Sec. 205, 1948 Flood Control 
Act, Public Law 858, 80th Cong., June 30, 1948, as 
amended). 
Each project selected must be complete in itself, 
economically and environmentally justified, and limited to 
a Federal cost of not more than $5 million. The local sponsoring 
agency must agree to provide without cost to the 
United States, all lands, easements, and rights-of-way, including 
highway, highway bridge, and utility relocations and 
alterations; hold and save the United States free from 
damages; maintain and operate the project after completion; 
assume all project costs in excess of the Federal cost 
limit; and prevent future encroachments on improved 
channels. 
There were no Section 205 projects under construction 
in Fiscal Year 1986. 
See Table L for expenditures under Section 205 during 
Fiscal Year 1986. 
Emergency Bank Protection (Section 14, 1946 Flood 
Control Act, Public Law 526, 79th Cong., July 24, 1946) 
as amended. 
Each project selected must be complete in itself, 
economically and environmentally justified, and limited to 
a Federal cost of not more than $500,000. The local sponsoring 
agency must agree to provide without cost to the 
United States all lands, easements, and rights-of-way, including 
highway, highway bridge, and utility relocations and 
alterations; hold and save the United States free from 
damages; maintain and operate the project after completion; 
and assume all project costs in excess of the Federal 
cost limit. 
Projects that were physically complete in FY 85, but 
financially completed in FY 86 were as follows: (For detailed 
project descriptions, see FY 85 Annual Report.) 
North Fork Big Nemaha River, Elk Creek Sewage Lagoons, 
Johnson County, NE; South Fork Wolf River, County 
Bridge, Brown County, KS; Little Blue River, Gilead Bridge, 
Thayer County, NE. 
Projects that were physically complete in FY 86, but not 
financially complete in FY 86 were as follows: 
20-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Nodaway River, Road T, Andrew County, MO - Construction 
was completed in December 1985 on a project to 
protect a county road and bridge. The project consisted of 
2,450 feet of stone fill along the bank. The project was 
damaged by flooding in March 1985, and remedial measures 
to repair the structure should be completed in FY 87. 
Osage River, Road HH, Miller County, MO - Construction 
was completed in May 1986 on a project to protect a 
county road. The project consisted of a stone fill revetment 
with tieback dikes. 
Little Blue River, Overy Bridge, Clay County, NE - Construction 
was completed in September 1986 on a project 
to protect a county road and bridge. The project consisted 
of a concrete rubble revetment with tieback dikes. 
Little Blue River, Spring Ranch Bridge, Clay County, 
NE - Construction was completed in June 1986 on remedial 
repairs to the bank stabilization project. The project was 
damaged by flooding in August 1985. Repairs consisted of 
replacing stone removed by flood waters and repairing the 
damaged board fence dikes. The repaired project provides 
protection to a county road and bridge. 
Yankee Creek, West Tecumseh Bridge, Johnson County, 
NE - Construction was completed in July 1986 on a project 
to protect a county road and bridge. The project consisted 
of a concrete rubble revetment with tieback dikes. 
Yankee Creek, Vesta Bridge, Johnson County, NE - 
Construction was completed in July 1986 on a project to 
protect a county road and bridge. The project consisted of 
concrete rubble revetments with baffle dikes on both the 
left and right banks. 
Kimsey Creek, Casteel Bridge, Holt County, MO - Construction 
was completed in August 1986 on a project to protect 
a county road and bridge. The project consisted of a 
stone fill revetment with tieback dikes on the left bank. 
Nodaway River, Fillmore Bridge, Andrew and Holt 
Counties, MO - Construction was completed in September 
1986 on a project to protect a county road and bridge. The 
project consisted of bank paving with a reinforced toe section 
on both the left and right banks. 
Big Blue River, Tuxedo Park Road and Bridge, Saline 
County, NE - Construction was coompleted in August 1986 
on a project to protect a city park road and bridge. The project 
consisted of a concrete rubble revetment with tieback 
dikes on the left bank. 
Projects authorized for or under construction at the end 
of FY 86 were as follows: 
Beaver Creek, Br. 43430, Webster County, NE - Construction 
was underway on a project to protect a county 
road and bridge. The project consists of a concrete rubble 
fill and should be completed in October 1986. 
Elm Creek, Br. 33425, Webster County, NE - Construction 
was underway on a project to protect a county road 
and bridge. The project consists of a concrete rubble fill and 
should be completed in October 1986. 
Elm Creek, Br. 23015, Webster County, NE - Construction 
was underway on a project to protect a county road 
and bridge. The project consists of a concrete rubble fill and 
should be completed in October 1986. 
Beaver Creek, Br. 23025, Webster County, NE - Construction 
was underway on a project to protect a county 
road and bridge. The project consists of concrete rubble 
bank paving on the left bank and concrete rubble fill on the 
right bank to protect the bridge abutments. Construction 
should be completed in October 1986. 
Beaver Creek, Br. 14710, Webster County, NE - Construction 
was underway on a project to protect a county 
road and bridge. The project consists of concrete rubble 
bank paving and should be completed in October 1986. 
Wakarusa River, Baldwin City Waterline, Douglas 
County, KS - Construction was authorized for a project to 
protect a city waterline. The project consists of a sheet pile 
wall, stone drains, and riprap to provide erosion protection. 
Construction should be completed by March 1987. 
Turkey Creek, Br. 123, Fillmore County, NE - Construction 
was authorized for a project to protect a county road 
and bridge. The project consists of a concrete rubble revetment 
with tieback dikes. Construction should be completed 
by February 1987. 
ITurkey Creek, Br. 385, Fillmore County, NE - Construction 
was authorized for a project to protect a county road 
and bridge. The project consists of a revetment with baffle 
dikes and should be completed by February 1987. 
Little Blue River, FAS Road 1108, Marshall County, KS 
Construction was authorized for a project to protect a county 
road from flood-caused erosion. The project consists of 
a stone fill revetment with baffle dikes and should be completed 
by February 1987. 
Little Blue River, Pauline Bridge, Adams County, NE 
Construction was authorized for a project to protect a county 
road and bridge. The project consists of a concrete rubble 
fill and a windrow revetment on the right bank. Construction 
should be completed by January 1987. 
Little Blue River, Pimpel Bridge, Adams County, NE 
Construction was authorized for a project to protect a county 
road and bridge. The project consists of 450 linear feet 
of concrete rubble revetment with baffle dikes and should 
be completed by January 1987. 
See Table L for listing of Emergency Bank Protection expenditures 
during FY 1986. 
Multiple Pupose Projects 
Inclu ing Power 
25. HARRY S. TRUMAN DAM AND 
RESERVOIR, OSAGE RIVER, MO 
Location. Damsite is on main stem of Osage River about 
1.5 miles northwest of Warsaw, Benton County, Missouri. 
Reservoir extends into Bates, Henry, Hickory, St. Clair, and 
Vernon Counties, Missouri. 
20-8

KANSAS CITY, MO., DISTRICT 
Existing Project. An earthfill dam about 5,000 feet long 
constructed to an average height of about 96 feet above 
streambed, including a gate-controlled overfall spillway section 
and a power installation consisting of six inclined pumpgenerating 
units with total capacity of 160,000 kilowatts. 
Total reservoir storage capacity is 5,202,000 acre-feet 
(3,918,000 for flood control, 244,000 for sediment reserve, 
and 1,040,000 multipurpose storage for power, low-flow 
regulation, and recreation). Public Law 91-267, approved 
May 26, 1970, authorized a change in project name from 
Kaysinger Bluff Dam and Reservoir, Osage River Basin, 
Missouri, to the Harry S. Truman Dam and Reservoir. 
Estimated cost (1986) is $550 million. Construction of 
relocation of Missouri Highway M-13 was initiated 
September 1964 and completed May 1966. Construction of 
the dam and reservoir was initiated in October 1964. The 
embankment has been completed including paving the top 
of the dam roadway. The spillway was completed in October 
1979. The Southwestern Power Administration powerline 
needed for final testing and commercial operation of the 
generators was completed in December 1979. The first 
power unit was placed on line on 22 December 1979. Subsequent 
problems with the turbine bearing required remedial 
design on the bearing. Restricted commercial power production 
began in April 1982. Through September 1986, 
power generation totaled 1,769,721,800 kilowatt hours. Of 
the gross income from the sale of power by Southwestern 
Power Administration, $18,937,355 was allocated to the 
Corps of Engineers for project power operating costs, interest, 
investment recovery. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operation during fiscal year. Visitation for FY 1986 was 
2,753,700 visitor days. Work was continued on acquisition 
of land and rights-of-way; relocation of utilities and 
municipal facilities; construction of the powerplant; and construction 
of public use facilities. Construction of measures 
to protect downstream areas from power operation were 
completed. Project is 95 percent complete During FY 1986, 
337,271,000 kilowatt-hours of electrical power were 
generated. Maintenance: Activities consisted of design and 
award of contract for repair of turbine blade and ordinary 
operation and maintenance. 
26. STOCKTON LAKE, SAC RIVER, MO 
Location. Damsite is on Sac River about 49.5 miles above 
its confluence with Osage River, and about 2 miles east of 
Stockton, Cedar County, Missouri, lake extending into Dade 
and Polk Counties. 
Existing project. A rock-shell dam with impervious core 
about 5,100 feet long constructed to an average height of 
about 128 feet, with a gated overfall spillway and a 
45,200-kilowatt power installation. Total reservoir storage 
capacity is 1,674,000 acre-feet (774,000 for flood control, 
25,000 for sediment reserve and 892,000 multipurpose 
storage for power and recreation). Initial cost of constructing 
the completed project was $75,721,000. Estimated cost 
of the project, including $3,785,000 for downstream channel 
work and $502,057 for supplemental recreational 
development (Code 710), is $80,008,057 (1986). Construction 
was initiated in October 1963, and the project was 
placed in operation in December 1969. Power operation 
problems were encountered with the initial operation in 
March 1973 because the downstream channel did not have 
the capacity which earlier observations and computations 
indicated. As a result, it has been necessary to restrict the 
power operation to about the 30,000 kilowatt level. Rightof-
way for construction of a channel cutoff and bridge at 
Horseshoe Bend has been acquired, and construction has 
been completed. Remaining work consisting of completing 
acquisition of the sloughing easements downstream to Caplinger 
Mills is underway. Completion will assure 
downstream channel capacity to Caplinger Mills of 8,000 
cf.s. for powerplant operation. Discharge in this range will 
accommodate power operations at a 39,500-kilowatt level. 
Through September 1986, power generation totaled 
790,244,800 kilowatt-hours. Of the gross income from the 
sale of power by Southwestern Power Administration, 
$15,886,644 was allocated to the Corps of Engineers for 
project operating costs, interest, investment recovery. 
Local cooperation. Section 2, Flood Control Act of 1938, 
applies. 
Operations during fiscal year. Visitation for FY 1986 
was 1,871,000 visitor days. The project is complete and in 
operational status. Acquisition of sloughing easements 
downstream to Caplinger Mills was continued. The net 
amount of power marketed with Southwestern Power Administration 
was 67,817,000 kilowatt-hours. Maintenance: 
Activities consisted of ordinary operation and maintenance. 
General Investigations 
27. GENERAL INVESTIGATIONS 
Fiscal year 1986 costs totaled $1,495,950 for all General 
Investigation activities. See Table 20-K which covers 
Surveys, Collection and Study of Basic Data, Research and 
Development, Continuation of Planning and Engineering, 
Planning and Engineering under Proposed Program 
Legislation, and Advance Engineering and Design. 
27A. BRUSH CREEK, KANSAS CITY, MO 
The project is along Brush Creek, a tributary of the Blue 
River in Kansas City, Missouri, from just downstream of 
Roanoke Parkway for a distance of approximately 7,500 feet 
downstream to a point just below Troost Avenue. The plan 
of improvement consists of deepening the Brush Creek 
channel bottom in this reach by an average of 5 feet. 
Estimated Federal cost of the project (1986) is $12,600,000, 
and estimated non-Federal cost of lands, damages, and 
relocations is $4,170,000. The City of Kansas City, Missouri 
provided a letter of assurance dated June 20, 1986 stating 
its intent and ability to cost share the project. Preconstruction 
planning is underway. 
20-9

TABLE 20-A 
See 
Section 
in Text Project 
Missouri River, 
Sioux City, IA 
to Mouth (Rulo, 
Nebr., to Mouth) 
(Federal Funds) 
(Contributed 
Funds) 
(Consolidated 
Summary) 
2. Blue River Channel 
Kansas City, 
MO 
Blue River Channel 
(Contributed 
Funds) 
(Consolidated 
Funds) . 
3. Clinton Lake, 
Wakarusa 
River, KS 
(Contributed 
Funds) 
(Consolidated 
Summary) 
4. Harlan County 
Lake, Republican 
River, NE 
5. Hillsdale Lake, 
Big Bull 
Creek, KS 
6. Kanopolis Lake, 
Smoky Hill 
River, KS 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
1. 
20-10 
Funding 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
* Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Total Cost to 
FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
- - - - 237,942,190' 
- - - - 237,942,190' 
6,098,600 5,045,700 6,757,700 6,452,000 269,946,2142 
6,380,386 5,044,483 6,827,686 6,489,931 269,946,2142 
- - - - 816,190 
- - - - 816,190 
- - - - 22,642 
- - - - 22,642 
- - - - 238,758,3803 
- - - - 238,758,3803 
6,098,600 5,045,700 6,757,700 - 263,516,8564 
6,380,386 5,044,483 6,827,686 - 263,478,9254 
8,200,000 -2,225,000 2,028,000 6,052,000 17,800,171 
170,989 1,255,250 6,563,575 6,123,287 11,794,985 
- 70,000 - - 70,000 
- - 27,162 7,073 34,235 
8,200,000 -2,155,000 2,028,000 6,052,000 17,870,171 
170,989 1,255,250 6,590,737 6,130,360 17,829,220 
- -106,100 - - 57,415,433 
540,171 148,626 - - 57,415,433 
1,114,900 1,310,500 1,104,500 1,237,000 7,483,300 
1,112,529 1,315,435 1,104,848 1,237,034 7,483,300 
- - - - 118,805 
- - - - 118,805 
- - - - 57,534,238 
540,171 - - - 57,534,238 
-26,000 -8,000 - - 47,111,9265 
98,058 0 - - 47,111,926 
1,594,000 1,077,100 1,246,400 1,249,000 17,211,4617 
1,572,440 1,114,088 1,247,941 1,230,196 17,211,4617 
- - - - 1,017,623 
- - - - 1,017,623 
1,900,000 39,600 - 140,000 64,161,400 
2,115,958 203,412 14,766 140,000 64,161,400 
445,300 669,100 585,600 611,000 2,660,500 
445,047 669,879 585,618 611,096 2,660,500 
- - - - 12,577,2276 
4 - - - 12,577,2276 
1,533,400 1,069,800 1,452,400 1,696,000 13,978,010 
1,530,989 1,075,270 1,427,289 1,723,084 13,978,010

KANSAS CITY, MO., DISTRICT 
TABLE 20-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project 
7. Little Blue River 
Channel Improvement, 
Little Blue 
River, MO 
8. Little Blue River 
Lakes, Little Blue 
River, MO 
(Contributed 
Funds) 
(Consolidated 
Summary) 
9. Long Branch Lake 
Little Chariton 
River, MO 
(Contributed 
Funds) 
(Consolidated 
Summary) 
10. Melvern Lake 
Osage (Marais des 
Cygnes) River, KS 
11. Milford Lake, 
Republican River, 
KS 
12. Missouri River 
Levee System 
IA, NE, KS 
and MO 
13. Perry Lake, 
Delaware River, KS 
15. Pomme de Terre 
Lake, Pomme de 
Terre River, MO 
16. Pomona Lake, One 
Hundred Ten Mile 
Creek, KS 
FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
667,000 
562,410 
55,000 25,505,083 
128,044 25,443,249 
Funding 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
130,859,200 
130,805,693 
1,187,500 
1,017,025 
132,046,700 
131,822,718 
17,806,177 
17,804,744 
2,953,500 
2,953,500 
1,125,1348 
633,5919 
18,931,31110 
18,438,3359 
37,436,530 
37,436,530 
17,795,000 
18,471,209 
268,645 
17,500,000 
18,176,209 
275,000 
328,345 
433,100 
431,597 
-4,682 
6,056 
270,318 
334,401 
1,151,300 
1,153,735 
26,000 
10,995 
1,193,300 
1,201,212 
320,000 
569,816 
-26,000 
1,533,000 
1,576,795 
49,095,918 
49,095,918 
17,643,484 
17,643,484 
17,365,452 
17,365,452 
16,588,512 
16,588,512 
14,003,238 
14,003,238 
13,976,333 
13,976,3337 
2,300,000 3,258,000 
4,095,833 3,287,641 
1,046,000 11,356,760 
1,046,062 11,356,760 
- 49,566,492 
- 49,566,492 
1,273,000 15,541,5247 
1,273,091 15,540,5247 
583,000 56,885,851 
583,031 56,885,248 
13,085,000 12,600,000 
15,720,359 11,917,433 
264,070 96,113 
13,085,000 12,600,000 
15,984,429 12,013,546 
-29,400 150,000 
80,574 121,143 
413,000 567,800 
415,036 567,851 
108,750 
-20,074 
79,350 
60,500 
1,361,900 
1,364,012 
15,805 
1,399,800 
1,405,505 
196,000 
209,080 
1,734,000 1,874,900 
1,723,160 1,888,451 
- 15,000 
- 15,000 
1,630,600 1,578,400 
1,621,547 1,589,591 
265 
1,304,000 
1,296,852 
1,818,200 
1,830,355 
98,799 
150,000 
219,942 
1,532,000 
1,533,795 
1,396,400 
1,397,076 
512,000 
516,711 
2,419,500 
2,376,085 
1,429,500 1,453,000 
1,428,495 1,454,098 
1,038,200 
1,039,549 
1,058,000 
1,058,022 
20-11 
6,371,000 
7,060,777 
30,721 
6,371,000 
7,091,498 
48,721 
503,000 
503,029 
484,612 
59,520 
484,612 
108,241

REPORT OF THE CHIEF OF ENGINEER, U.S. ARMY 1986 
TABLE 20-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
17. Rathbun Lake, 
Chariton River, 
IA 
18. Smithville Lake, 
Little Platte 
River, MO 
19. Tuttle Creek Lake 
Blg Blue 
River, KS 
20. Wilson Lake, 
Saline River, 
KS 
21. Scheduling Flood 
Control Reservoir 
Operations 
22. Inspection of 
Completed Flood 
Control Projects 
23. Inspection of 
Non-Federal 
Levees 
25. Harry S. Truman 
Dam & Reservoir 
Osage River, MO 
26. Stockton Lake, 
Sac River, MO 
Total Cost to 
Funding FY 83 FY 84 ;FY 85 FY 86 Sept. 30, 1986 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,198,900 
1,194,485 
1,257,600 
1,246,720 
149,000 
149,401 
300,000 
299,731 
73,000 
72,999 
14,923,000 
12,929,266 
3,834,200 
3,836,394 
2,820,000 
1,276,067 
1,786,300 
1,789,410 
-15,000 
336,702 
1,898,500 
2,203,430 
1,193,000 
924,469 
1,080,500 
1,081,351 
2,541,300 1,609,500 
2,503,486 1,627,595 
- -33,000 
774,661 370,426 
879,000 987,000 
875,127 990,924 
1,539,900 1,476,700 1,375,000 
1,546,437 1,477,840 1,376,718 
995,300 
1,012,121 
161,700 
162,014 
338,100 
338,301 
95,000 
94,997 
12,425,000 
16,710,978 
4,039,900 
4,061,256 
-269,000 
855,969 
2,690,900 
2,699,062 
1,109,900 
1,110,138 
173,000 
174,032 
365,000 
364,917 
153,000 
152,458 
9,200,000 
8,860,644 
4,859,300 
4,870,785 
105,000 
132,582 
1,876,800 
1,868,147 
1,458,000 
1,239,997 
195,160 
195,160 
350,340 
350,490 
138,000 
138,546 
3,093,000 
3,563,417 
5,136,000 
5,133,990 
73,000 
451,361 
1,830,000 
1,839,804 
441,000 
101,859 
2,019,300 
1,734,316 
357,877 
1,476,459 
584,800 
589,584 
1. Includes $8,665,594 costs of new work for previous 
project. 
2. Includes $738,109 for maintenance of previous project. 
3. Includes $8,665,594 for new work for previous project 
and $816,190 from contributed funds. 
4. Includes $738,190 for maintenance of previous project, 
$22,642 from contributed funds and $200,000 Fiscal Year 1968 
Supplemental Appropriation Funds. 
5. Excludes cost of materials furnished without charge 
in the amount of $24,198. 
6. Excludes cost of materials furnished without charge 
in the amount of $7,885. 
7. Reflects $10 expenditure of undelivered order after 
close of 1978 cost records. 
8. Correct total is $1,138,370, which includes $43,771 interest 
during construction. Correction pending. 
9. Unable to verify. 
10. Correct amount is $18,944,547. 
20-12 
27,622,159 
27,622,159 
16,437,718 
16,417,936 
87,618,315 
87,612,620 
5,097,000 
5,097,000 
80,584,079 
80,584,079 
15,738,779 
15,738,779 
20,463,367 
20,463,367 
11,825,046 
11,606,996 
5,014,483 
5,014,483 
3,993,415 
3,993,415 
459,000 
459,000 
524,582,900 
524,538,202 
25,853,200 
25,850,090 
79,731,357 
79,700,239 
21,168,300 
21,165,170

TABLE 20-B AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
MISSOURI RIVER, SIOUX CITY, IA, TO 
MOUTH (RULO, NE, TO MOUTH) 
1. Jul. 25, 1912 
Aug. 8, 1917 
Mar. 3, 1925 
Jan. 12, 1927 
Jul. 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Dec. 31, 1970 
Oct. 23, 1962 
Jun. 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
Sep. 3, 1954 
Jun. 28, 1938 
Aug. 18, 1941 
Project adopted for securing a permanent navigable 
channel of 6-foot depth from Kansas City, MO to 
mouth. 
Fixed upstream limit of improvement at upper end of 
Quindaro Bend (374.8 miles from mouth) and provided 
for dredging. 
For a mimimum width of 200 feet, with a reasonable 
additional width around bends. 
Appropriation of $12 million authorized for securing a 
6-foot channel depth between Kansas City, MO, 
Quindaro bend, and Sioux City, IA. 
Appropriation of $15 million additional authorized; 
additional allotments totaling $29,153,108 were made 
by Public Works Administration under provisions of 
National Industrial Recovery Act of 1933, and 
$9,669,791 allotted under provisions of Emergency 
Relief Appropriation Act of 1935. 
Completion of improvement from mouth to Sioux City, 
IA 
Securing a navigable channel of 9-foot depth and a 
minimum width of 300 feet. 
BLUE RIVER CHANNEL, KANSAS CITY, MO 
Adopted plan for Blue River Basin and authorized 
$40,000,000 for initiation and partial accomplishment. 
CLINTON LAKE, WAKARUSA RIVER, KS 
The project for the Kansas River, KS, NE, and CO is 
authorized at an estimated cost of $88,070,000. 
HARLAN COUNTY LAKE, REPUBLICAN 
RIVER, NE 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Modified general comprehensive plan to include Harlan 
County Dam and Reservoir on Republican River, 
NE, other supplemental flood control works on 
upper Republican River, and authorized $7 million 
additional expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
HILLSDALE LAKE, BIG BULL CREEK, KS 
The comprehensive plan for the Missouri River Basin, 
approved by the Act of June 28, 1938, and as 
amended and supplemented is further modified to 
include the project for flood protection on the 
Kansas River and tributaries. It is further modified 
to include the project for flood protection on the 
Osage River and tributaries. 
KANOPOLIS LAKE, SMOKY HILL RIVER, KS 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Modified general comprehensive plan to include Harlan 
County Dam and Reservoir on Republican River, 
NE, other supplemental flood control works on 
upper Republican River, and authorized $7 million 
additional expenditure. 
20-13 
H. Doc. 1287, 61st Cong., 
(contains latest published 
map). P.L. 241-62. 
H. Doc. 463, 64th Cong., 
(contains latest published 
map). 
P.L. 585-68. 
H. Doc. 1120, 60th Cong., 
P.L. 560-70. 
P.L. 67-73 
H.R.11781 
P.L. 520-71 
H. Doc. 238, 73d Cong., 
(contains latest published 
map). P.L. 409-73 
H. Doc. 214, 76th Cong., 
(contains latest published 
map). P.L. 14-79. 
H. Doc. 91-332, 91st Cong. 
1962 Flood Control Act 
S. Doc 122, H. Doc. 578, 
87th Cong., P.L. 87-874. 
Flood Control Committee 
Doc. 1, 75th Cong., 
P.L. 761. 
H. Doc. 842, 76th Cong., 
P.L. 228. 
H. Doc. 475 and S. Docs. 
191 and 247, 78th Cong., 
P.L. 534. 
EP.L. 780, 83rd Cong., H. Doc. 
549, 81st Cong. 
Flood Control Committee 
Doc. 1, 75th Cong., 
EL. 761. 
H. Doc. 842, 76th Cong., 
EL. 228. 
2. 
3. 
5. 
6.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
Dec. 22, 1944 
Aug. 13, 1968 
Aug. 13, 1968 
Oct. 27, 1965 
Sep. 3, 1954 
Sep. 3, 1954 
Aug. 18, 1941 
Dec. 22, 1944 
Sep. 3, 1954 
Jun. 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
Jul. 24, 1946 
May 17, 1950 
Sep. 3, 1954 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
LITTLE BLUE RIVER CHANNEL 
Additional $38,000,000 for prosecution of general 
comprehensive plan for Missouri River Basin. 
LITTLE BLUE RIVER LAKES, MO 
Additional $38,000,000 for prosecution of general 
comprehensive plan for Missouri River Basin. 
LONG BRANCH LAKE, LITTLE CHARITON 
RIVER, MO 
The project for flood protection on the Chariton and 
Little Chariton Rivers and tributaries, IA and 
MO, is authorized at an estimated cost of 
$9,167,000. 
MELVERN LAKE, MARAIS DES CYGNES 
(OSAGE) RIVER, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
MILFORD LAKE, REPUBLICAN RIVER, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
MISSOURI RIVER LEVEE SYSTEM, IA, NE, KS, 
AND MO 
Levees along both sides of river from Sioux City to 
Kansas City. 
Extended project from Kansas City to the mouth 
and provided for increased protection. 
PERRY LAKE, DELAWARE RIVER, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
PICK-SLOAN MISSOURI BASIN PROGRAM 
(KANSAS CITY DIST.) 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Modified general comprehensive plan to include 
Harlan County Dam and Reservoir on Republican 
River, NE, other supplemental flood control works 
on upper Republican River, and authorized $7 
million additional expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
Additional expenditure of $150 million for prosecution 
of general comprehensive plan for Missouri 
River Basin. 
Additional expenditure of $250 million for prosecution 
of general comprehensive plan for Missouri 
River Basin. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
H. Doc. 475 and S. Does. 
191 and 247, 78th Cong., 
P.L. 534. 
P.L. 90-483 (H. Doc. 169, 
90th Cong. 
P.L. 90-483 (H. Doc. 169, 
90th Cong. 
1965 Flood Control Act, 
P.L. 89-298, (H. Doc. 238, 
89th Cong. 
H. Docs. 642, 5491, and 
561, 83rd Cong., P.L. 780 
H. Doc. 5491, 83rd Cong., 
P.L. 780 
H. Doc. 821, 76th Cong. 
H. Doc. 475 and S. Does. 
191 and 247, 78th Cong. 
H. Does. 642, 5491, and 
561, 83rd Cong., P.L. 
780. 
Flood Control Committee 
Doc. 1, 75th Cong. 
H. Doc. 842, 76th Cong. 
H. Doc. 475 and S. Docs. 
191 and 247, 78th Cong. 
H. Docs. 642 and 5491, 
83rd Cong. 
20-14 
9. 
10. 
11. 
12. 
13. 
14.

TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
May 2, 1956 
Jul. 3, 1958 
Jul. 14, 1960 
Dec. 30, 1963 
Jun. 18, 1965 
May 12, 1967 
Aug. 13, 1968 
Dec. 24, 1970 
Dec. 23, 1971 
Mar. 7, 1974 
Jun. 28, 1938 
Dec. 22, 1944 
Sep. 3, 1954 
Sep. 3, 1954 
Sep. 3, 1954 
Oct. 27, 1965 
Jun. 28, 1938 
Modified general comprehensive plan for Missouri 
River Basin by deletion of construction of Red 
Willow Dam and Reservoir, NE, and addition of 
construction of Wilson Dam and Reservoir, KS. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
Additional expenditure of $207 million for 
prosecution of general comprehensive plan for 
Missouri River Basin. 
Additional expenditure of $80 million for prosecution 
of general comprehensive plan for Missouri River 
Basin and modified plan to include bank protection 
or rectification works below Garrison Dam. 
Additional $116 million for prosecution on general 
comprehensive plan for Missouri River Basin. 
Additional $20 million for prosecution of general 
comprehensive plan for Missouri River Basin. 
Additional $38,000,000 for prosecution of general 
comprehensive plan for Missouri River Basin. 
Change comprehensive plan name to Pick-Sloan 
Missouri River Basin program. 
Additional $101,000,000 for prosecution of general 
comprehensive plan for Pick-Sloan Missouri Basin 
Program. 
Additional $72,000,000 for prosecution of general 
comprehensive plan for Pick-Sloan Missouri Basin 
Program. 
POMME DE TERRE LAKE, POMME DE TERRE 
RIVER, MO 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,000,000 additional 
expenditure. 
POMONA LAKE, ONE HUNDRED TEN MILE 
CREEK, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
RATHBUN LAKE, CHARITON RIVER, IA 
Expanded general comprehenssive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
SMITHVILLE LAKE, LITTLE PLATTE 
RIVER, MO 
The project for flood protection on the Platte River 
and tributaries, MO and IA, is authorized at an 
estimated cost of $26,889,000. 
TUTTLE CREEK LAKE, BIG BLUE RIVER, KS 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for 
initiatiion and partial accomplishment. 
H. Doc. 409, 84th Cong. 
S. Doc. 91-1100, 91st Cong. 
S. Doc. 92-222, 92nd Cong. 
Flood Control Committee 
Doc. 1, 75th Cong., 
P.L. 761. 
H. Doc. 475 and S. Docs. 
191 and 247, 78th Cong., 
P.L. 534. 
H. Docs. 642, 5491, and 
561, 83rd Cong., P.L. 
780. 
H. Doc. 5491, 561, 83rd 
Cong., P.L. 780. 
H. Doc. 561, 83rd Cong., 
P.L. 780. 
1965 Flood Control Act, 
P.L. 89-298 (H. Doc. 262, 
89th Cong.) 
Flood Control Committee 
Doc. 1, 75th Cong., 
P.L. 761. 
20-15 
15. 
16. 
17. 
18. 
19.

TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
Aug. 18, 1941 Modified general comprehensive plan to include H. Doc. 842, 76th Cong., 
Harlan County Dam and Reservoir on Republican P.L. 228. 
River, NE, other supplemental flood control works 
on upper Republican River, and authorized $7 
million additional expenditure. 
Dec. 22, 1944 Expanded general comprehensive plan for Missouri H. Doc. 475 and S. Docs. 
River Basin and authorized $200 million additional 191 & 247, 78th Cong., 
expenditure. P.L. 534. 
WILSON LAKE, SALINE RIVER, KS 
20. Dec. 22, 1944 Expanded general comprehensive plan for Missouri H. Doc. 475 and S. Docs. 
River Basin and authorized $200 million additional 191 & 247, 78th Cong., 
expenditure. P.L. 534. 
Jul. 14, 19602 Additional expenditure of $207 million for prosecu- S. Doc. 96, 86th Cong., 
tion of general comprehensive plan for Missouri P.L. 645. 
River Basin. 
HARRY S. TRUMAN DAM AND RESERVOIR, 
OSAGE RIVER, MO 
25. Sep. 3, 1954 Expanded general comprehensive plan for Missouri H. Doc. 5491, 83rd Cong., 
River Basin and authorized $217,710,000 P.L. 780. 
additional expenditure. 
Oct. 23, 1962 The Kaysinger Bluff Reservoir is hereby modified in 1962 Flood Control Act, 
accordance with recommendations of the Chief of H. Doc. 578, 87th Cong., 
Engineers in H. Doc. 578, 87th Cong., at an P.L. 87-874. 
estimated additional cost of $43,245,000; provided, 
that nothing in this Act shall be construed as 
authorizing the acquisition of additional lands for 
the establishment of a national wildlife refuge at 
the reservoir. 
STOCKTON LAKE, SAC RIVER, MO 
26. Sep. 3, 1954 Expanded general comprehensive plan for Missouri H. Doc. 5491, 83rd Cong., 
River Basin and authorized $217,710,000 P.L. 780. 
additional expenditure. 
1. Contains latest published maps of Missouri River. 2. Report of Chief of Engineers on justification of Wilson 
Dam and Reservoir, submitted in compliance with Public Law 
505, 84th Congress, published as Senate Document 96, 86th 
Congress, was approved July 14, 1960 (Public Law 645). 
TABLE 20-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Fort Leavenworth Bridge removal Complete 1965 270,393 - 
Gasconade River, MO 1, 2 Complete 1931 139,003 85,077 
Kansas River Navigation Inactive 1980 259,900 - 
Osage River, MO, lock and dam3 Complete 1952 658,076 850,495 
1. Improvement adequate for existing needs. Project for 
maintenance only. 
2. Curtailment of project in H. Doc. 467, 69th Cong. 
3. Operation of lock and dam placed in standby status. 
20-16

TABLE 20-E 
KANSAS CITY, MO., DISTRICT 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Abilene, KS 
Atchison, KS 
Barnard, KS' 
Bartley, NE 
Bedford, East Fork, 102 River, IA' 
Big Blue River, Seward, NE 1' 
Big Stranger Creek, KS' 
Blue River Basin, Vicinity of Kansas City 4 
Braymer Lake, Shoal Creek, MO 
Brookfield Lake, Yellow Creek, MO 
Chariton-Little Chariton Basin, MO (1965 Act)2 
Chariton River, MO (1944 Act) 
Dry Fork and East Fork Lakes, 
Fishing River, MO 
East Muddy Creek, MO 
Elk Creek, Clyde, KS' 
Fairbury, Little Blue River, NE 
Fort Scott Lake, Marmaton River, KS 
Frankfort, Black Vermillion River, KS 
Grove Lake, Soldier Creek, KS 
Gypsum, Gypsum Creek, KS' 
Indian Lake, Blue River, KS 
Indianola, NE 
Kansas City, Kansas River, KS (62 Mod) 
Kansas Citys on MO and KS Rivers, 
MO and KS 3 
Lawrence, Kansas River, KS5 
Lower Grand River, MO 
Manhattan, Kansas River, KS 
Mercer Lake, Weldon River, MO 
Mill Lake, Blue River, MO 
Missouri River at New Haven, MO' 
Onaga Lake, Vermillion Creek, KS 
Osawatomie, Pottawatomie Creek, KS 
Ottawa, Osage (Marais des Cygnes) River, KS 
Pattonsburg Lake, Grand River, MO 
Pattonsburg Lake, Grand River, MO 
(Advance Highway Relocation) 
Pattonsburg Lake, Grand River, MO 
(Advance Town Relocation) 
Perry Lake Area (Road Improvements), KS 
Platte River, MO, Channel Improvement 
Rathbun Lake Fish Hatchery 
Salina, Smoky Hill River, KS 
Seward, NE' 
Smithville Channel, Little Platte River, MO 
Stonehouse Creek, Jefferson Co., KS' 
Tomahawk Lake, Blue River, KS 
Topeka, Kansas River, KS 
Trenton Lake, Thompson River, MO 
Upper Grand River, MO 
Wolf-Coffee Lake, Blue River, KS 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Inactive 
Completed 
Deferred 
Inactive 
Completed 
Completed 
Active 
Completed 
Inactive 
Completed 
Inactive 
Completed 
Completed 
Completed 
Active 
Completed 
Inactive 
Deferred 
Completed 
Inactive 
Completed 
Completed 
Inactive 
Inactive 
Inactive 
Completed 
Deferred 
Completed 
Completed 
Completed 
Deferred 
Completed 
Inactive 
Completed 
Inactive 
Inactive 
Inactive 
1965 
1973 
1953 
1974 
1984 
1966 
1976 
1977 
1973 
1974 
1966 
1984 
1973 
1976 
1966 
1977 
1984 
1976 
1950 
1984 
1980 
1985 
1966 
1967 
1976 
1971 
1982 
1973 
1966 
1976 
1976 
1976 
1982 
1973 
1975 
1967 
1973 
1972 
1976 
1974 
1966 
1966 
1976 
1,099,350 
4,099,590 
127,860 
118,269 
652,414 
126,887 
337,131 
451,400 
692,706 
8,052,990 
51,989 
2.- 
989,015 
726,966 
757,500 
1,271,025 
1,754,019 
2,782,793 
127,297 
67,275 
25,010,500 
42,434,197 
8,773,488 
2,488,585 
432,245 
139,883 
2,178.261 
2,036,624 
4,462,661 
390,763 
91,929 
5,315,168 
222,193 
700,000 
3,878,668 
126,887 
6,896 
246,995 
77,189 
21,174,593 
1,095,019 
1. Authorized by the Chief of Engineers under Section 205, 
Public Law 858, 80th Congress, as amended. 
2. Little Chariton River (East and Middle Fork) and 
Mussell Fork classified inactive. Construction cost includes 
$481,106 cost of completed Shoal Creek Unit and $211,600 cost 
for inactive units, Little Chariton River and Mussell Fork. 
3. Includes $619,787 non-Federal contributions for work 
desired by local interests, but not required under the project. 
The project as a whole is complete except for Turkey Creek 
facilities in Central Industrial District Unit. 
4. Three lakes inactive and one lake deferred. 
5. Includes $153,377 non-Federal contributions. 
20-17

TABLE 20-G 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Funds Funds 
Project Report For Date and Authority Expended Expended 
Arlington Lake, MO 1948 Flood Control Act approved $8,651 - 
June 28, 1938, as modified by 
Flood Control Act approved 
August 18, 1941, and expanded 
by Flood Control Act approved 
December 22, 1944 
Beatrice, Big Blue River, NE 1965 Flood Control Act approved 16,317 - 
September 3, 1954 
Garnett Lake, Pottawatomie 1973 Flood Control Act approved 71,466 - 
Creek, KS September 3, 1954 
Hackleman Corners Lake, - Authorized by Flood Control Act - - 
Cedar Creek, MO approved September 3, 1954 
Hays, Big Creek, KS' 1974 Flood Control Act of 1965 approved 499,200 - 
October 27, 1965 
Marysville, KS - Flood Control Act of September 3, 133,682 - 
1954 
Merriam, Turkey Creek, KS 1970 Flood Control Act approved 39,708 - 
September 3, 1954 
Pioneer Lake, KS 1952 Flood Control Act approved 95,692 - 
June 28, 1938, as modified by 
Flood Control Act of August 18, 
1941, and expanded by Flood 
Control Act approved 
December 22, 1944 
Richland Lake, MO 1948 Flood Control Act approved 8,548 - 
June 28, 1938, as modified by 
Flood Control Act approved 
August 18, 1941, and expanded 
by Flood Conotrol Act approved 
December 2, 1944 
1. A study of water supply and flood problems at Hays, 
KS, is being studied under Section 205, Public Law 858, 80th 
Congress, as amended. 
TABLE 20-H MISSOURI RIVER LEVEE SYSTEM 
(See Section 12 of Text) 
Miles of 
Unit Levee Status 
R 512-513 Richardson Co. D. D. #7 
R 500 Iowa Point D. D. #4 
Kimsey Holly Creek 
L 497 Forest City L. D. 
L488 Holt Co. D. D. #7 
R 482 Burr Oak D. D. #3 
L 476 Amazonia L. D. 
R 460-471 Elwood-Gladden L. D. 
L 455 S. St. Joseph L. D. 
L 443-448 Halls L. D. 
R 440 Atchison & Doniphan Co. D. D. 
L 408 Farley-Beverly D. D. 
L 400 Waldron L. D. 
L 385 Riverside-Quindaro D. D. 
R 351 Atherton L. D. 
L 330-345 Orrick L. D. 
L 319-325 Henrietta-Crooked River D. D. 
L 246 Brunswick-Dalton D. D. 
L 15 North County L. D. 
Remaining units 
19.1 
4.1 
4.4 
16.0 
11.5 
8.2 
10.8 
13.8 
15.6 
17.3 
10.7 
12.2 
7.6 
6.5 
15.9 
43.4 
35.0 
20.0 
40.0 
Complete-1958 
Complete-1954 
Complete-1970 
Complete-1962 
Complete-1955 
Complete-1954 
Complete-1956 
Complete-1968 
Complete-1967 
Complete-1957 
Complete-1959 
Complete (Levee raise modification)-1972 
Complete-1957 
Planning underway 
Complete-1966 
Planning underway 
Planning underway 
Complete-1983 
Planning underway 
Detailed planning not initiated 
20-18

TABLE 20-I 
ALIS1\I0tto Vl 1 1 1 &AL., AJADIBAB.; 1 
KANSAS CITY DISTRICT PROJECTS INCLUDED IN 
PICK-SLOAN MISSOURI BASIN PROGRAM 
(See Section 14 of Text)
Estimated Estimated 
Project Federal Non-Federal 
Cost Cost 
Abilene, Smoky Hill River, KS $ 1,099,350 $ 287,000 
Bartley, Republican River, NE 118,269 9,500 
Fort Scott Lake, Marmaton River, KS 84,000,000 41,200,000 
Garnett Lake, Pottawatomie Creek, KS2 38,600,000 - 
Harlan County Lake, Republican River, NE 48,129,549 
Harry S. Truman Dam and Reservoir, Osage River, MO 550,000,000 133,341,000 
Hillsdale Lake, Big Bull Creek, KS 64,021,400 21,091,814 
Indianola, Republican River, NE 67,275 7,592 
Kanopolis Lake, Smoky Hill River, KS 12,577,227 - 
Lawrence, Kansas River, KS 8,620,111 2,130,000 
Manhattan, Kansas River, KS 2,488,585 265,000 
Melvern Lake, Osage (Marais des Cygnes) River, KS 37,436,530 - 
Melvern Lake and Pomona Lake (Road Improvement), 
KS (1974 Authorization) 500,000 214,300 
Milford Lake, Republican River, KS 49,566,492 - 
Missouri River Levee System, Rulo to the Mouth' 216,300,000 59,600,000 
Osawatomie, Osage (Marais des Cygnes) River, KS 2,036,624 348,300 
Ottawa, Osage (Marais des Cygnes) River, KS 4,462,661 876,000 
Perry Lake, Delaware River, KS 49,095,918 - 
Pomme de Terre Lake, Pomme de Terre River, MO 3 17,365,453 - 
Pomona Lake, Osage River Basin, KS 14,003,238 - 
Salina, Smoky Hill River, KS 3,878,668 1,960,000 
Stockton Lake, Sac River, MO 80,902,057 17,391,000 
Topeka, Kansas River, KS 21,174,593 10,383,492 
Tuttle Creek Lake, Big Blue River, KS 80,584,079 - 
Tuttle Creek Lake, KS-Road and Bridge (1976 Act) 630,000 610,000 
Tuttle Creek Lake (Road Improvement), KS 
(1974 Modification) 500,000 214,300 
Wilson Lake, Saline River, KS 20,463,367 - 
1. Active portion of project. Deferred portion of project is 2. 1969 Estimate. 
currently estimated to cost (1986) $48,443,000 Federal and 3. Active portion of project. Inactive portion of the proj- 
$4,458,000 non-Federal. Inactive portion of project is current- ect for power modification is currently estimated to cost (1954) 
ly estimated to cost (1986) $184,969,000 Federal and $7,300,000. 
$15,688,000 non-Federal. 
TABLE 20-J INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 22 of Text) 
Location Month Inspected 
Missouri River Main Stem 
Missouri River Levees: R 512-513, R 500, Kimsey Holly Creek, L 497, L 488, 
R 482, L 476, R 460-471, L 455, L 443-448, R 440, L 408, L 400 and R 351, L 246 
Kansas Citys, Missouri and Kansas: Argentine, Armourdale, 
Birmingham, CID (Mo & Kans), East Bottoms, Fairfax-Jersey 
Creek, North Kansas City Units, and GSA Federal Complex 
Osage River, Kansas and Missouri 
Ottawa, Kansas 
Osawatomie, Kansas 
Kansas River and Minor Tributaries 
Topeka, Kansas; Auburndale, North Topeka, Oakland, Soldier 
Creek, South Topeka, and Waterworks Units 
Republican River, Nebraska and Kansas 
Bartley, Nebraska 
Smoky Hill, Saline, and Solomon Rivers 
Abilene, Kansas 
Sep-Oct 86 
Sep-Oct 86 
Oct 86 
Nov 86 
Oct 86 
Apr 86 
Nov 86 
20-19

TABLE 20-K 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
ACTIVE GENERAL INVESTIGATIONS 
(See Section 27 of Text) 
Item and CWIS Number 
SURVEYS (Category 100) 
Flood Damage Prevention Studies (120) 
Blue River Basin, KS & MO - 12382 
Kansas and Osage Rivers, Kansas - 12204 
Osage River above Harry S. Truman - 14063 
Republican River, NE & KS- 12383 
Subtotal 
Review of Authorized Projects (160) 
Platte River and Little Platte River Channels, MO - 14160 
Grove Lake Deauthorization Review - 77000 
Subtotal 
Miscellaneous Activities (170) 
Special Investigations -17250 
FERC Licensing - 53857 
Subtotal 
Coordination Studies with Other Agencies (180) 
Soil Conservation Service, Dept. Agric. (181) - 51840 
Bureau of Reclamation, Dept. Interior (182) - 51820 
Missouri Basin States Association (183) - 53847 
Planning Assistance to States (186) - 51850 & 14820 
Technical Assistance for Streambank Erosion (188) - 51731 
Subtotal 
Supplemental Preauthorization Studies (190) 
Wears Creek, Jefferson City, MO- 75299 
TOTAL (Category 100) 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) - 82030/40 
Hydrologic Studies (260) - 53820 
TOTAL (Category 200) 
RESEARCH AND DEVELOPMENT (Category 300) 
None 
CONTINUATION OF PLANNING AND ENGINEERING 
(Category 400) 
Brush Creek, Kansas City, MO (451) - 12319 
TOTAL (Category 400) 
PLANNING AND ENGINEERING UNDER PROPOSED 
LEGISLATION (Category 500) 
None 
ADVANCE ENGINEERING AND DESIGN (Category 600) 
None 
GRAND TOTAL GENERAL INVESTIGATIONS
20-20 
Federal Cost 
FY 86 
Totals By 
Categories 
$194,104 
329,521 
273,531 
30,022 
$827,178 
$ 13,301 
7,177 
$ 20,478 
$ 59,353 
10,559 
$ 69,912 
$ 9,364 
17,440 
7,273 
58,032 
11,912 
$104,021 
$ 10,114 
$1,031,703 
$155,782 
6,753 
$ 162,535 
$301,712 
$301,712 
$1,495,950

KANSAS CITY, MO., DISTRICT 
TABLE 20-L FLOOD CONTROL ACTIVITIES 
UNDER SPECIAL AUTHORIZATION 
(See Section 24 of Text) 
Fiscal 
Year 
Study Stage1 Cost 
Flood Control Activities Pursuant to Section 205, Public Law 858, 
80th Congress, as Amended) 
Rossville, Cross Creek, KS D $27,307 
Hays, Lincoln Draw, KS D 134,062 
Big Creek, Pleasant Hill, MO R 15,697 
Davis Creek, Mound City, MO R 54,706 
TOTAL $231,772 
Emergency Bank Protection - Sec. 14, 1946 Flood 
Control Act, Public Law 526, 79th Cong., 
July 24, 1946, as Amended) 
North Fork Big Nemaha River, Elk Creek Sewage Lagoons, Johnson County, NE 0 $499 
Little Blue River, Spring Ranch Bridge, Clay County, NE O 14,000 
South Fork Wolf River, County Bridge, Brown County, KS O 5,752 
Little Blue River, Gilead Bridge, Thayer County, NE O 9,423 
Nodaway River, Road T, Andrew County, MO C 139,485 
Osage River, Road HH, Miller County, MO C 50,599 
Beaver Creek, Br. 43430, Webster County, NE C 8,501 
Elm Creek, Br. 33425, Webster County, NE C 5,222 
Elm Creek, Br. 23015, Webster County, NE C 15,253 
Beaver Creek, Br. 23025, Webster County, NE C 3,341 
Beaver Creek, Br. 14710, Webster County, NE C 12,442 
Yankee Creek, West Tecumseh Bridge, Johnson County, NE C 19,309 
Yankee Creek, Vesta Bridge, Johnson County, NE C 32,203 
Kimsey Creek, Casteel Bridge, Holt County, MO C 29,203 
Nodaway River, Fillmore Bridge, Andrew & Holt Counties, MO C 50,040 
Big Blue River, Tuxedo Park Road & Bridge, Saline County, NE C 40,980 
Wakarusa River, Baldwin City Waterline, Douglas County, KS C 19,290 
Turkey Creek, Br. 123, Fillmore County, NE C 18,317 
Turkey Creek, Br. 385, Fillmore County, NE C 13,843 
Little Blue River, FAS Road 1108, Marshall County, KS C 21,291 
Little Blue River, Overy Bridge, Adams County, NE C 33,871 
Little Blue River, Pauline Bridge, Adams County, NE C 19,502 
Little Blue River, Pimpel Bridge, Adams County, NE C 17,984 
West Fork Grand River, Redding Bridge, Ringgold County, IA P 7,464 
TOTAL FOR 24 ACTIVE PROJECTS: $587,814 
12 studies were terminated in FY 1986, total $37,320 
TOTAL ALL PROJECTS $625,134 
Emergency Flood Control Activities - Repair, Flood 
Flighting, and Resuce Work - Public Law 99 
84th Congress and Antecedent Legislation) 
Disaster Preparedness Program $234,251 
Flood Fighting and Rescue Work 73,627 
Rehabilitation 586,337 
TOTAL $876,215 
1. Stage: I = Initial Appraisal; R = Recon; D = DPS; P = P&S; C = Construction; O = Operational 
20-21

OMAHA, NE, DISTRICT * 
This district comprises portions of Montana, Wyoming, 
North Dakota, South Dakota, Minnesota, Colorado, 
Nebraska, Iowa, and Missouri, all embraced in 
drainage basin of Missouri River along main stem and 
tributaries to Rulo, NE. 
IMPROVEMENTS 
Navigation 
1. Missouri River, Sioux City, IA 
to Rulo, NE................. 
2. Navigation Work Under Special 
Authorization ................ 
Flood Control 
3. Bear Creek Lake, CO ................. 
4. Bowman-Haley Lake, ND ............. 
5. Chatfield Lake, CO ................... 
6. Cherry Creek Lake, CO ............... 
7. East Nishnabotna River 
at Red Oak, IA ...................... 
8. Fall River Basin, SD ............... 
9. Great Falls, MT ..................... 
10. Indian Creek at Emerson, IA .......... 
11. Little Sioux River, IA ................ 
12. Lost Creek at Columbus, NE ........... 
13. Missouri National Recreational 
River, NE and SD ................... 
14. Missouri River, Garrison Dam 
to Lake Oahe, ND................. 
15. Missouri River, Kenslers Bend, 
NE to Sioux City, IA ................. 
16. Missouri River Levee System, 
Sioux City, IA to Rulo, NE ............ 
17. Papillion Creek and Tributaries 
Lakes, N E .......................... 
18. Pick-Sloan Missouri River Basin 
Program (Omaha Dist) ................ 
19. Pipestem Lake, ND .................. 
20. Salt Creek & Tributaries, NE .......... 
21. South Platte River Basin, CO .......... 
22. Inspection of Completed Flood 
Control W orks ...................... 
23. Scheduling Flood Control 
Reservoir Operations ................. 
24. Flood Control Activities Under 
Special Authorization ................ 
Page Multiple Purpose Projects Including Power 
25. Big Bend Dam-Lake Sharpe, 
. 21-2 Missouri River Basin, SD ............ 
26. Fort Peck Lake, MT ................... 
. 21-2 27. Fort Randall Dam-Lake Francis Case, 
Missouri River Basin, SD .............. 
. 21-2 28. Garrison Dam-Lake Sakakawea, 
. 21-2 Missouri River Basin, ND .............. 
. 21-2 29. Gavins Point Dam-Lewis and Clark Lake, 
. 21-3 Missouri River Basin, NE and SD ....... 
30. Oahe Dam-Lake Oahe, Missouri 
. 21-3 River Basin, SD and ND ............... 
..... 21-3 
..... 21-4 
..... 21-4 
..... 21-4 
..... 21-4 
..... 21-4 
..... 21-5 
.21-5 
.21-5 
.21-5 
.21-5 
.21-6 
.21-6 
.21-6 
..... 21-6 
..... 21-6 
..... 21-6 
Page 
.. 21-7 
... 21-7 
.. 21-8 
.. 21-8 
.. 21-8 
.. 21-9 
Miscellaneous 
31. Streambank Erosion Control 
Evaluation and Demonstration Project ...... 21-9 
32. National Emergency Preparedness .......... 21-9 
General Investigations 
33. See Table 21-K ...................... 
Tables 
.... 21-9 
21-A Cost and Financial Statement ........... 21-10 
21-B Authorizing Legislation ................ 21-13 
21-C Other Authorized Navigation Projects .... 21-16 
21-D Not Applicable 
21-E Other Authorized Flood Control Projects.. 21-16 
21-F Other Multiple Purpose Projects 
Including Power ...................... 21-18 
21-G Deauthorized Projects ................. 21-18 
21-H Missouri River Levee System, 
Sioux City, IA to Rulo, NE ............. 21-18 
21-I Pick-Sloan Missouri Basin Program ...... 21-19 
21-J Inspection of Completed Local 
Protection Projects .................... 21-19 
21-K Active General Investigations ........... 21-21 
21-L Flood Control Activities 
Under Special Authorization ............ 21-22 
21-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. MISSOURI RIVER, SIOUX CITY, IA 
TO MOUTH (SIOUX CITY, IA 
TO RULO, NE) 
Location. Channel of the Missouri River extending 
from Sioux City, IA to Rulo, NE. 
Previous projects. For details see page 1893, Annual 
Report for 1915, and page 1175, Annual Report for 
1938. 
Existing project. Provides for a navigation channel of 
9-foot depth and width not less than 300 feet, obtained 
by revetment of banks, rock dikes to contract and stabilize 
waterway, cutoffs to eliminate long bends, closing 
minor channels, and removal of snags and dredging as 
required. Construction was initiated on this section of 
the project (Sioux City to Rulo) in fiscal year 1928, the 
bank stabilization work was completed in April 1979, 
and the navigation feature was completed in September 
1980. Work remaining to complete this section of the 
project consists of construction of fish and wildlife facilities. 
A reliable channel suitable for navigation is available 
through this section. Controlling depth at ordinary 
stages of the river is 9 feet, with additional depths available 
during high stages. Commercial navigation was inaugurated 
on this section in May 1939, and common carrier 
transportation service was inaugurated in October 
1946. Seven riverside recreation sites are complete and 
in operation. Estimated total cost of new work Sioux 
City, IA to Rulo, NE is $189,632,000 (1984), of which 
$188,045,000 is the Federal cost of construction and 
$1,587,000 is the non-Federal cost, exclusive of amounts 
expended on previous projects. 
Local cooperation. Local interests must share in cost 
of recreation facilities in accordance with provisions of 
the Federal Water Project Recreation Act of 1965. Local 
interests have contributed for cost sharing on construction 
of recreation by constructing portions of the facilities. 
Terminal facilities. Terminal facilities for loading 
and unloading grain, liquids and dry bulk products are 
maintained by private interests at various locations on 
this section of the river. A complete list of terminal facilities 
are included in the Missouri River Navigation 
Maps and can be obtained from the Omaha District for a 
small fee. 
Operations during fiscal year. Maintenance: Continued 
routine operation and maintenance activities. 
Local interests operate and maintain the recreation 
sites. 
2. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Small Navigation Projects Not Specifically Authorized 
by Congress (Sec. 107 of the River and Harbor Act 
of 1960, as amended, Public Law 645, 86th Congress). 
Federal costs for FY 1986 were $100,000 for dredging 
at the Sioux City Marina. 
Flood Control 
3. BEAR CREEK LAKE, CO 
Location. Damsite is on Bear Creek in Jefferson 
County, CO about 8 miles above the confluence of Bear 
Creek with the South Platte River at Denver. 
Existing project. Earthfill dam 180 feet high, with a 
crest length of about 5,300 feet, and a supplementary 
earthfill dike with a height of 65 feet and a crest length 
of 2,100 feet, to the south of the main dam, and an uncontrolled 
earth and rock-cut emergency spillway. The 
lake provides storage capacity of 28,831 acre-feet for 
flood control and 1,979 acre-feet for sediment and recreation. 
Construction of the project was initiated in October 
1973 and was completed in September 1982, exclusive 
of recreation facilities. The total cost of construction 
was $61,503,600. Recreation facilities were developed 
utilizing cost sharing funds at an additional 
cost of $500,000. 
Local cooperation. Requirements are described in full 
on page 21-3 of fiscal year 1981 Annual Report. 
Operations during fiscal year. Maintenance: Work by 
hired labor included miscellaneous items of ordinary repair 
and maintenance. Annual project visitation was 
estimated at 102,808. 
4. BOWMAN-HALEY LAKE, ND 
Location. Damsite is on North Fork of Grand River in 
southwestern North Dakota, about 6 miles above 
Haley, ND. 
Existing project. A dam 79 feet high, with a crest 
length of 5,730 feet, and reservoir with a storage capacity 
of about 19,780 acre-feet for sediment storage, 
fish and wildlife conservation, recreation, and future 
water supply for communities of Bowman, Reeder, 
Scranton, and Gascoyne, ND. Construction was initiated 
in July 1964, and the project was completed in 
1970. (See Table 21-A for total cost of construction.) 
Local cooperation. Local interests must prevent encroachment 
on capacity of North Fork channel below 
reservoir; obtain water rights for storage; pay the 
United States for costs allocated to water supply; and 
hold the United States free from damages. Assurances 
of local cooperation were approved June 19, 1964. With 
respect to water rights, requirements have been complied 
with. A contract with the Bowman County Water 
Management District for water storage space was' 
signed November 10, 1981. 
Operations during fiscal year. Maintenance: Continued 
routine operation and maintenance activities. 
Annual project visitation was estimated at 32,331. 
5. CHATFIELD LAKE, CO 
Location. On the South Platte River, just below the 
mouth of Plum Creek, about eight miles upstream from 
Denver, CO. 
Existing project. Consists of rolled earth-fill dam 
with a maximum height of 148 feet, a crest length of 
12,500 feet, and a reservoir with flood control capacity 
21-2

OMAHA, NE, DISTRICT 
of 204,737 acre-feet and sediment capacity of 26,692 
acre-feet, which will be used for recreation, and an enlarged 
channel from the dam downstream to Denver to 
accommodate reservoir flood releases. 
The Corps is participating with local interests in acquisition 
of lands and development of recreation facilities 
immediately downstream of the Chatfield Dam in 
lieu of a portion of the channel improvement. Construction 
of the project was initiated in August 1967 and is 
98 percent complete, with a scheduled completion date 
in FY 1989. Construction is essentially complete at the 
project with the exception of the downstream channel 
improvement, associated recreation facilities and fish 
and wildlife mitigation measures. Estimated cost 
through construction of the project is $104,970,000 
(1986) of which $95,000,000 is the Federal cost for construction, 
$7,070,000 local cost in connection with the 
downstream channel improvement, and $2,900,000 is 
the local cost for acquisition of water for the recreation 
pool. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936 applies to the downstream channel improvement. 
The Colorado Water Conservation Board 
provided assurances of local cooperation for the downstream 
improvement on December 13, 1967. Local interests 
must provide water for filling the sediment reserve 
pool for recreation use which the state agreed to on 
April 25, 1967. 
Operations during fiscal year. Continued design by 
hired labor. Completed construction on Union Avenue 
Weir of the downstream channel improvements. Continued 
construction on Stage II of the downstream 
channel improvements and initiated construction on 
Stage III. Maintenance: Continued routine operation 
and maintenance activities, including seismic evaluation 
of the dam. Annual project visitation was estimated 
at 1,083,577. 
6. CHERRY CREEK LAKE, CO 
Location. Damsite is on Cherry Creek in Arapahoe 
County, CO, approximately 6 miles southeast of Denver, 
CO just outside of city limits. Cherry Creek joins 
South Platte River within city limits of Denver. 
Existing project. A rolled-earthfill dam with maximum 
height of 141 feet above streambed and 14,300 
feet long. Project includes a reinforced concrete outlet 
works and an uncontrolled side channel spillway canal 
discharging into adjacent Toll Gate Creek. Cherry Creek 
project provides reservoir storage capacify of 93,920 
acre-feet below spillway canal invert and, in addition, a 
surcharge storage of 134,470 acre-feet. Plan of operation 
in ultimate development for multiple-purpose uses includes 
13,960 acre-feet for sediment storage and 79,960 
acre-feet for conservation purposes. Construction began 
in fiscal year 1946 and was completed in June 1961, exclusive 
of recreation facilities. Federal cost of the project 
was $15,285,000. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. New work: Recreational 
development was continued. Maintenance: Continued 
routine operation and maintenance activities. 
Annual project visitation was estimated at 1,526,653. 
7. EAST NISHNABOTNA RIVER AT 
RED OAK, IA 
Location. On the East Nishnabotna River on the 
western edge of Red Oak in Montgomery County, IA. 
Existing Project. The work on the original project 
was initiated in April 1962 and completed in October 
1962. The work consisted of 10,500 feet of levee along 
the west edge of Red Oak. The cost when completed 
(1962) was $443,000, of which $400,000 was Federal and 
$43,000 non-Federal. Flooding subsequent to completion 
of the project raised concerns about the adequacy of 
the project. A study was made and the recommendation 
to raise the existing project to standard project flood 
protection was approved February 1981. The cost of 
this work was $1,854,000, of which $1,754,000 was the 
Federal cost and $100,000 was the non-Federal cost for 
necessary rights of way and utility relocations. 
Local cooperation. A 221 contract to sponsor the 
project was furnished by the City of Red Oak and was 
approved on September 21, 1981. 
Operations during fiscal year. Project is financially 
complete. 
8. FALL RIVER BASIN, SD 
Location. In Custer and Fall River Counties, in and 
near the town of Hot Springs, SD. Hot Springs unit is in 
the town of Hot Springs, immediately south of the junction 
of Cold Brook and Hot Brook which combine to 
form the Fall River. Cold Brook Lake unit is approximately 
1.25 miles north of the town of Hot Springs on 
Cold Brook; and Cottonwood Springs Lake unit is approximately 
4.5 miles west of the town of Hot Springs 
on Cottonwood Springs Creek, one-half mile upstream 
from its confluence with Hot Brook. 
Existing project. The general plan of improvement 
provides flood protection for Hot Springs, SD. The Hot 
Springs channel improvement unit consisted of widening, 
deepening and straightening 6,000 feet of channel 
of Fall River. The Cold Brook Lake unit, an earth-fill 
dam with appurtenant structures, controls an area of 
70.5 square miles. The Cottonwood Springs Lake unit 
consists of an earth-fill dam with appurtenant structures 
and controls an area of 26 square miles. Construction 
of Hot Springs unit was completed during fiscal 
year 1951. Construction of Cold Brook unit dam and appurtenances 
was completed in fiscal year 1953 with exception 
of a road and parking area which were completed 
in fiscal year 1955. Construction of the Cottonwood 
Springs unit dam was completed in fiscal year 
1970, with the exception of the recreation facilities 
which were completed in fiscal year 1972. (See Table 
21-A for total cost of construction.) For last funding see 
FY 1981 Annual Report. 
Local cooperation. Local cooperation requirements 
have been fully complied with. 
21-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Operations during fiscal year. Maintenance: Routine 
operation and maintenance activities were continued on 
the Cottonwood Springs and Cold Brook Dams and 
structures. Annual project visitation was estimated for 
Cold Brook Lake and Cottonwood Springs Lake at 
57,507 and 15,157 respectively. 
9. GREAT FALLS, MT 
Location. In Great Falls, Cascade County, MT at confluence 
of the Sun and Missouri Rivers. 
Existing project. Provides for levees along the left 
bank of the Sun River and an interceptor ditch and 
closed conduit to collect and convey side-hill runoff to 
the Sun River. Estimated cost through construction of 
the project is $14,067,000 of which $12,017,000 is the 
Federal cost of construction and $2,050,000 is the local 
cost for lands, relocations and a cash contribution for replacement 
of a storm sewer conduit desired by local interests. 
Local cooperation. Section 3. Flood Control Act of 
June 22, 1936 applies. In addition local interests must 
zone the unleveed portion of the flood channel through 
the damage area to preserve its capacity and to prevent 
further encroachments and contribute in cash $179,000 
representing the estimated cost of replaced storm drainage 
facilities which will be incorporated into the closed 
conduit of the Watson Coulee Interceptor. West Great 
Falls Flood Control and Drainage District provided assurances 
on January 17, 1968. State Supreme Court decision 
on assessments required a change in state law, 
which was enacted in 1973. The final court ruling on 
compliance was made April 1, 1981, and the local sponsor 
was instructed to proceed toward project construction. 
Operations during fiscal year. Work continued on the 
Sun River left bank levees and channels contract and on 
O&M manuals. Initiated work on Sun River repair and 
mitigation planting. Engineering and design continued 
by hired labor. 
10. INDIAN CREEK AT EMERSON, IA 
Location. The project is located in Mills County along 
the right bank of Indian Creek just east of the city of 
Emerson, Iowa. 
Existing project. This project consists of raising old 
Highway 34 and constructing a levee 180 feet long. This 
project provides protection to commercial and residential 
areas. Federal cost of the project was $333,000 
(1986). 
Local cooperation. The local sponsor is responsible 
for all necessary rights-of-way and utility relocations. 
The city of Emerson, IA is the local sponsor. Assurances 
of local cooperation were provided by the local 
sponsor on June 24, 1983. 
Operations during fiscal year. O&M manuals were 
furnished to the local sponsor in March 1986. Project is 
financially complete. 
11. LITTLE SIOUX RIVER, IA 
Location. The project is located in the lower portion 
of the Little Sioux River Basin in Harrison and Monona 
Counties, IA, near the confluence of the Little Sioux and 
Missouri Rivers. 
Previous Project. For details see page 646, Annual 
Report for 1970. 
Existing project. Construction of the original project 
was completed in June 1966. Sill No. 4 was identified as 
a design deficiency in a June 17, 1981 report by the 
Omaha District, approved by OCE. Based on that report, 
design studies for a permanent solution to the 
problem were completed. Estimated cost of the new 
work is $5,117,000 (1986). 
Local cooperation. The Little Sioux Inter-County 
Drainage District was sponsor of that portion of the 
original project where the remedial work is being accomplished. 
Remedial work was 100 percent Federally 
funded. 
Operations during fiscal year. Ice and debris accompanying 
high flows during the spring of 1986 caused extensive 
damage to the bed grade control structure (Sill 
No. 4) that was constructed during the winter of 1985 to 
correct a design deficiency of the original project. A contract 
for repairing the damage was advertised in 
September 1986. 
12. LOST CREEK AT COLUMBUS, NE 
Location. On Lost Creek just north of the City of Columbus 
in Platte County, NE. 
Existing project. This project provides levee and 
channel improvements on the north side of Columbus 
and provides protection to commercial and residential 
areas. The estimated cost of the construction is 
$4,345,000 (1986) of which $3,485,000 is the Federal 
cost, and $860,000 is non-Federal contributed funds - 
other, that provides for all necessary right of way, utility, 
and bridge relocations. 
Local cooperation. A contract with the City of Columbus 
to sponsor the project was approved on February 
18, 1982. 
Operations during fiscal year. Work continued on 
Stage 2 and on O&M manuals. 
13. MISSOURI NATIONAL RECREATIONAL 
RIVER, NE, AND SD 
Location. NE and SD. The Missouri River between 
Gavins Point Dam and Ponca State Park, NE. This includes 
Cedar and Dixon Counties in Nebraska, and 
Yankton, Clay, and Union Counties in South Dakota. 
Existing project. The designation as a National Recreational 
River will preserve outstanding and important 
scenic values and will provide additional opportunities 
for river access and recreation use. Erosion control, consisting 
of bank stabilization and river management 
techniques designed to preserve the existing environment, 
will at the same time preserve high bank flood 
plain lands. Estimated total cost of construction is 
21-4

OMAHA, NE, DISTRICT 
$21,100,000 (1986) of which $21,000,000 is the Federal 
cost of construction and $100,000 is the non-Federal 
cost. (See Table 21-A for total costs.) 
Local cooperation. All construction on this project 
will be done in accordance with the cost sharing and 
financing concepts reflected in the Water Resources 
Development Act of 1986. Local interests will be contacted 
as specific requirements are developed. A costsharing 
contract with the State of South Dakota for the 
Myron Grove access site was signed on June 26, 1986. 
Operations during fiscal year. Coordination with the 
State of South Dakota for the Myron Grove access site, 
the City of Yankton, SD, for recreational development 
of Riverside Park, and the National Park Service continued. 
Efforts to identify additional separable elements 
which could be justified under current cost-sharing 
criteria continued. 
14. MISSOURI RIVER, GARRISON DAM 
TO LAKE OAHE, ND 
Location. Along the channel of Missouri River between 
Garrison Dam and headwaters of Oahe Reservoir 
in North Dakota. 
Existing project. Consists of bank stabilization and 
rectification works required to stabilize banks of Missouri 
River in specific areas and prevent further loss of 
agricultural lands through erosion. Construction was initiated 
January 1965 and project is complete. The cost 
of this work was $9,683,000 (1986) of which $9,413,000 
is the Federal cost of construction and $270,000 is the 
non-Federal cost for all lands, easements, and rights of 
way. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. 
Operations during fiscal year. Contractor claim 
resolved. Project is financially complete. 
15. MISSOURI RIVER, KENSLERS 
BEND, NE, TO SIOUX CITY, IA 
Location. Project is along Missouri River between 
Ponca Bend, NE, and combination bridge at Sioux City, 
IA.
Existing project. Construction of dikes, revetments 
and channel improvement along Missouri River from 
Miners Bend and vicinity, SD and NE, to Sioux City, 
IA. Project was started in June 1946 and completed in 
June 1961. (See Table 21-A for total costs.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. Routine operation and 
maintenance activities continued. 
16. MISSOURI RIVER LEVEE SYSTEM, 
IOWA, NEBRASKA, KANSAS AND 
MISSOURI (SIOUX CITY, IA 
TO RULO, NE) 
Location. On both banks of the Missouri River from 
Sioux City, IA to St. Louis, MO. Active portion of the 
project in Omaha District extends from Council Bluffs, 
IA to Rulo, NE. 
Existing project. A series of levee units and appurtenant 
works along both sides of Missouri River from 
Sioux City, IA, to mouth, for protection of agricultural 
lands and small communities against floods. Construction 
was initiated June 1948. (See Table 21-H for status 
of active units). Construction was initiated on Levee 
Unit L-611-614 in September 1980 and is 98 percent 
complete. Construction of Unit R-616 was initiated in 
May 1983 and is essentially complete. Cost estimate for 
active portion of project from Council Bluffs, IA to 
Rulo, NE is $43,000,000 (1986) of which $38,400,000 is 
Federal cost for construction and $4,600,000 local costs 
for lands and damages. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936 applies. Fully complied with for all completed 
units. Local interests have furnished assurances 
of their willingness and ability to fulfill local cooperation 
requirements for the remaining active units. 
Operations during fiscal year. Continued construction 
on Stage 1 Fish & Wildlife Facilities, drainage improvements 
and Stage 3 on Levee Unit L-611-614 and 
on Levee Unit R-616. Initiated work on Stage 2 Fish & 
Wildlife Facilities Levee Unit L-611-614. 
17. PAPILLION CREEK AND 
TRIBUTARIES LAKES, NE 
Location. The Papillion Creek basin is located in 
Washington, Douglas, and Sarpy Counties, NE. Big Papillion 
Creek rises west of Blair, flows southeasterly 
through metropolitan Omaha area where it is joined by 
the Little Papillion Creek just above Offutt AFB, forming 
Papillion Creek. The combined creek flows along the 
side of Offutt AFB to its confluence with the Missouri 
River. 
Existing project. The active project consists of a 
series of four dams and reservoirs, channel improvement 
and a flood warning system on tributaries of Papillion 
Creek. Construction was initiated in FY 1972. Completed 
projects include Standing Bear Lake (Site 16) 
December 1978 and Glenn Cunningham Lake (Site 11) 
December 1979. Construction of the dam portions of 
Sites 18 and 20 are complete. Remaining work includes 
construction of recreational facilities at both sites. 
Estimated total costs for the project are $54,400,000 
Federal funds with $3,618,000 non-Federal reimbursement. 
Local cooperation. Requirements are described in full 
on page 21-6 of fiscal year 1981 Annual Report. 
Operations during fiscal year. Design for Sites 18 and 
20 continued by hired labor. Construction continued at 
Sites 18 and 20. Maintenance: Routine operations and 
maintenance activities continued at Sites 11 and 16. Annual 
project visitation was estimated at 1,305,700. 
18. PICK-SLOAN MISSOURI BASIN 
PROGRAM (OMAHA DISTRICT) 
Location. Flood control improvements in this project 
21-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
are along Missouri River and several of its principal 
tributaries and in states comprising Missouri River 
Basin. 
Existing project. A general comprehensive plan for 
flood control and other purposes in Missouri River 
Basin provides for levees along Missouri River between 
Sioux City, IA, and mouth and reservoirs on main stem 
of Missouri River and tributaries. See individual reports 
and Table 21-I for projects in the Omaha District included 
in the program. 
19. PIPESTEM LAKE, ND 
Location. On Pipestem Creek in Stutsman County, 
ND, 3 miles upstream from where Pipestem Creek joins 
the James River at Jamestown, ND. 
Existing project. The project consists of a rolled 
earth-fill dam approximately 108 feet high with a crest 
length of 4,000 feet and outlet works of a gated reinforced 
concrete conduit. The reservoir provides 146,880 
acre-feet of storage. The multipurpose pool provides 
space for silt storage and 885 acres of water surface for 
fish, wildlife and recreation needs. Construction of the 
project was initiated in FY 1970 and completed in FY 
1977. (See Table 21-A for total construction costs.) 
Local cooperation. Local interests are required to administer 
project land and water areas for recreation and 
fish and wildlife enhancement and to bear the first cost 
of associated improvements in the wildlife management 
area; pay, contribute in kind, or repay, with interest, 
one-half of the separable cost of the project allocated to 
recreation and fish and wildlife enhancement; and bear 
all costs of operation, maintenance, and replacement of 
recreation and fish and wildlife lands and facilities. 
Operations during fiscal year. Routine operation and 
maintenance activities continued. Annual project visitation 
was estimated at 75,217. 
20. SALT CREEK AND TRIBUTARIES, NE 
Location. Salt Creek Basin comprises an area of 
about 1,627 square miles in and around Lincoln in 
southeastern Nebraska. 
Existing project. The authorized project consists of a 
system of 10 dams and reservoirs, channel clearing, enlarging 
and realignment, levees and necessary bridge alterations. 
Pursuant to Senate Resolution adopted 
August 7, 1964, which authorized a review of Salt Creek 
survey report, remaining units were placed in 
"inactive" classification. Construction of the project began 
in the spring of 1962. All work under the active portion 
of the project, consisting of the 10 dams and reservoirs 
and the channel improvements and levees through 
Lincoln, was completed in 1969. Funds were transferred 
to the project in FY 1980 with concurrence of Congressional 
Committees. These funds were used to determine 
an effective method of correction for the dispersive clay 
problem in the completed downstream levees through 
Lincoln. (See Table 21-A for total construction costs.) 
Local cooperation. Fully complied with for the completed 
levee and channel improvement part of the project. 
For the dams, local interests are required to operate 
and maintain the permanent pools for fish and wildlife 
conservation and assume all costs related to utilization 
of the permanent pools for recreational purposes and insure 
public access to the pools. 
Operations during fiscal year. Maintenance: Operation 
and maintenance activities included sedimentation 
and reservoir regulation studies, intermittent inspections 
of the dams and structures. Annual visitation to 
the system of dams was estimated at 4,268,560. 
21. SOUTH PLATTE RIVER BASIN, CO 
Location. Flood control improvements in this project 
are along the South Platte River and its tributaries in 
Colorado. 
Existing project. General plan for flood control and 
other purposes provides for construction of Chatfield 
Lake on the South Platte River, Bear Creek Lake on 
Bear Creek, and levee and channel improvements on the 
South Platte River. (See individual reports and Table 
21-B for authorizing legislation). 
22. INSPECTION OF COMPLETED 
FLOOD CONTROL WORKS 
Flood Control Act of June 22, 1936, and subsequent 
acts require local interests to furnish assurances that 
they will maintain and operate certain local protection 
projects after completion, in accordance with regulations 
prescribed by Secretary of the Army. District Engineers 
are responsible for administration of these regulations 
within the boundaries of their respective districts. 
Inspections of completed local protection projects 
which have been turned over to local interests for maintenance 
and operation during the fiscal year are set 
forth in Table 21-J, Inspections of Completed Local Protection 
Projects. Fiscal year costs were $277,285. 
Inspection of Non Federal flood protection works was 
initiated in FY 1984. The cost incurred for FY 1986 was 
$43,167. 
23. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Under sections 7 and 9, Flood Control Act of December 
22, 1944, Corps of Engineers is responsible for detailed 
scheduling of operations involving storage capacity 
reserved for or assigned to flood control in reservoirs 
constructed by Bureau of Reclamation as well as those 
constructed by Corps of Engineers. Costs for FY 1986 
were $273,069 and total costs to September 30, 1986 
were $4,809,766. 
24. FLOOD CONTROL ACTIVITIES 
UNDER SPECIAL AUTHORIZATION 
Emergency Flood Control Activities - Repair, Flood 
Fighting and Rescue Work (Public Law 99, 84th Cong., 
and antecedent legislation). 
21-6

OMAHA, NE, DISTRICT 
Federal costs for FY 1986 were $297,387 for disaster 
preparedness and emergency operations, and $266,593 
for repair and restoration. 
Small Flood Control Projects Not Specifically Authorized 
by Congress (Sec. 205, 1948 Flood Control Act 
as amended, Public Law 858, 80th Cong., June 30, 1948). 
Stage II construction continued on Lost Creek at Columbus, 
NE. Work continued in preparation for the construction 
stage for projects on Pebble Creek, Scribner, 
NE; Platte River, Cedar Creek, NE; Lodgepole Creek, 
Sidney, NE; North Platte River, Casper, WY; and 
Lower Heart River, Mandan, ND. Indian Creek at 
Emerson, IA, and East Nishnabotna River at Red Oak, 
IA, are now financially complete. Two negative Initial 
Appraisal Studies were submitted during FY 86 at a 
total cost of $14,700. 
Emergency Bank Protection (Sec. 14,1946 Flood Control 
Act, Public Law 526, 79th Cong., July 24, 1946). 
Operations under this heading were as follows: Construction 
was completed on two projects in Colorado 
along the South Platte River near Kersey and along the 
South Platte River near Merino, one project was completed 
in Iowa along the Big Sioux River in Plymouth 
County Site 2. One project was completed in South 
Dakota along the Vermillion River in Vermillion. Five 
projects were completed in Nebraska, along Redbird 
Creek in Holt County; Elk Creek near Jackson; Elm 
Creek in Decatur; Salt Creek at Lincoln; and Wigle 
Creek near Homer. Completed construction of stonefilled 
revetment along the Platte River near Hansen- 
Chris Lakes, Nebraska. O&M manuals were completed 
on Elm Creek fBroadway Bridge) Decatur, NE, Big 
Thompson River, Johnstown, CO, Cache La Poudre 
River at Windsor, CO, Elk Creek near Jackson, NE 
Platte River, Hansen-Chris, NE, Redbird Creek, Holt 
County, NE, Salt Creek, Lincoln, NE, South Platte 
River, Kersey, CO, South Platte River, Platteville, CO, 
Wigle Creek, Homer, NE and Yellowstone River, MT. 
The following O&M manuals are currently underway: 
Big Sioux River, Harrisburg, IA, Big Sioux River (Site 
2) Plymouth, IA, Blackbird Creek, Burt County, CO, 
Elk Creek, Willis, NE, Platte River, Ft. Lupton, CO, 
South Platte River, Weldona, CO, South Platte River, 
Goodrich, CO, South Platte River, Morgan, CO, Vermillion 
River Waste Water Treatment Plant, SD, Vermillion 
River, Vermillion, SD. The following projects 
were initiated: South Platte River near Goodrich, CO; 
Big Sioux River, Plymouth County, IA; South Platte 
River Wendona, CO; Medicine Bow River, Elk Mountain, 
WY; Blackbird Creek, Burt County, NE; South 
Creek, Martinsburg, NE; Elk Creek, Willis, NE; Big 
Sioux River, Harrisburg, SD; Platte River, Camp 
Ashland, NE. 
Multiple-Purpose Projects Including Power 
25. BIG BEND DAM-LAKE SHARPE, 
MISSOURI RIVER BASIN, SD 
Location. On Missouri River, 987.4 miles above 
mouth, near Fort Thompson, SD, and approximately 20 
miles upstream from Chamberlain, SD. Dam is located 
in the upstream reach of Fort Randall Reservoir. Big 
Bend Reservoir extends upstream to Pierre, SD. 
Existing project. A rolled-earthfill dam 95 feet high, 
with a crest length of 10,570 feet, a hydroelectric generating 
plant consisting of eight 58,500 kilowatt units, 
and a chute-type gated spillway. Reservoir provides 
gross storage of 1,883,000 acre-feet. Federal cost of the 
project was $107,498,000. Construction began in September 
1959 and was completed in September 1977, except 
for Code 710 recreation facilities. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with other Missouri River 
reservoirs for flood control, power production and other 
multiple uses. During the period, 897,690,000 net kilowatt-
hours of electricity were produced. Installation of a 
power plant controller system for the Missouri River 
dams continued. Initiated work on rehabilitation of rest 
rooms for the handicapped at tailrace area and replacement 
of water chillers at powerplant. Annual project 
visitation was estimated at 683,657. 
26. FORT PECK LAKE, MT 
Location. Reservoir is in Missouri River Valley in Mc- 
Cone, Valley, Garfield, Phillips, Petroleum, and Fergus 
Counties, MT. Dam is approximately 1,771.6 miles 
above mouth of Missouri River. Nearest towns are Glasgow, 
17 miles northwest, and Nashua, 9 miles north. 
Existing project. A hydraulic earthfill dam with a 
maximum height of 251 feet, with a crest length of 
21,026 feet, and a reservoir for flood control, irrigation, 
navigation, hydroelectric power, and other purposes, 
with a gross storage capacity of 18,909,000 acre-feet at 
maximum operating pool. Work started on original project 
in October 1933 and on second power plant in August 
1956. The project was completed in 1965. The power 
installations at the project were uprated in FY 1979. 
The 5 generators have a total output of 185,250 KW, 2 
generators at 40,000 KW each, 2 generators at 43,500 
KW each and 1 generator at 18,250 KW. See page 818 of 
1965 Annual Report and page 905 of 1958 Annual Report 
for project details. Federal cost of the project was 
$158,428,000. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Initiated 
work on rehabilitation of 13.8 KV switchgear, 
rehabilitation of roof and gutters shaft area buildings 
and repair of bridge joints. Ownership of the town of Ft. 
Peck, MT, was transferred from Federal to local control 
during the year. Continued work on installation of a 
powerplant controller system for the six Missouri River 
dams, work on rehabilitation of 13.8 KV bussing and 
cables, rehabilitation of townsites streets and sidewalks 
and sewage system improvements. Fort Peck Lake was 
operated in conjunction with the other Missouri River 
reservoirs for flood control, navigation, power production, 
and other multi-purpose uses. Generating facilities 
produced 982,303,000 net kilowatt hours of electricity. 
21-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Total cost of Operation and Maintenance during the 
period was $6,084,800, however, reimbursement from 
the Western Area Power Administration for the prorata 
share of Operation and Maintenance cost of the power 
plant, reimbursement for furnishing operator's village 
facilities, and property disposals reduced net cost to 
$3,310,400. Annual project visitation was estimated at 
1,061,201. 
27. FORT RANDALL DAM-LAKE FRANCIS 
CASE, MISSOURI RIVER BASIN, SD 
Location. On Missouri River in Charles Mix and 
Gregory Counties, SD, about 82 miles above Yankton, 
SD. Site is 880 miles above mouth of Missouri River and 
148 miles above Sioux City, IA. 
Existing project. A rolled-earthfill dam with a maximum 
height of 165 feet, a crest length of 10,700 feet, 
and a reservoir for flood control, irrigation, navigation, 
hydroelectric power, and other purposes, with a gross 
storage capacity of 5,574,000 acre-feet at maximum operating 
pool. The power installation consists of eight 
units rated at 40,000 kilowatts each. Construction began 
in May 1946 and was completed in 1969, except for 
Code 710 recreation facilities. Federal cost of the project 
was $199,066,000. Non-Federal contribution for constructing 
approaches to the Platte-Winner Bridge was 
$720,000. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with other Missouri River 
reservoirs for flood control, navigation, power production, 
and other multiple uses. Generating facilities produced 
1,742,596,000 net kilowatt-hours of electricity. 
Continued work on installation of a power plant controller 
system for the Missouri River dams, protective 
coating power penstock #1, West Chamberlin erosion repair 
and painting transformers C & D. Initiated work on 
erosion repair upstream face of dam, American Creek- 
Ft. Randall bank protection, paint penstock and surge 
tank interior unit #5, rehabilitation of restrooms 3 & 6 
for the handicapped, rehabilitation of HVAC, rehabilitation 
of the electrical distribution system, and rehabilitation 
of transformer bank B. Ownership of the town of 
Pickstown, SD, was transferred from Federal to local 
control during the year. Annual project visitation was 
estimated at 1,715,462. 
28. GARRISON DAM-LAKE SAKAKAWEA, 
MISSOURI RIVER BASIN, ND 
Location. On Missouri River in McLean and Mercer 
Counties, ND, about 11 miles south of Garrison, ND, 
and 9 miles west of Coleharbor, ND. 1,389.9 miles above 
mouth of river and 75 miles above Bismarck, ND. 
Existing project. A rolled-earthfill dam 11,300 feet 
long with a maximum height of 210 feet and a reservoir 
for flood control, irrigation, navigation, hydroelectric 
power, and other purposes, with a gross storage capacity 
of 24,137,000 acre-feet. It provides five power units, 
three units rated at 80,000 kilowatts each, and two units 
rated at 95,000 kilowatts each, three flood control tunnels 
and a gated spillway. Federal cost of the project 
was $299,938,000 including $4,208,000 for major rehabilitation. 
Non-Federal contribution in connection with 
widening Snake Creek Embankment was $687,000. Construction 
of the project was initiated in April 1946 and 
completed in 1966, except for recreational development 
using Code 710 funds. 
Local cooperation. None required except cost sharing 
with the State of North Dakota for widening the Snake 
Creek Embankment and recreation cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with the other Missouri 
River reservoirs for flood control, navigation, power production, 
and other multiple purpose uses. Normal operation 
and maintenance procedures were accomplished 
during the fiscal year. Generating facilities produced 
2,149,259,000 net kilowatt-hours of electricity. Continued 
work on installation of a power plant controller 
system for the Missouri River dams, rehabilitation of 
stator windings and turbine runner unit #1. Initiated 
work on voltage regulating equipment, painting surge 
tank interior unit #2, construction of maintenance facility, 
and rehabilitation of the restrooms at Camp Loop 
#1. Ownership of the town of Riverdale, ND, was transferred 
from Federal to local control during the year. Annual 
project visitation was estimated at 1,932,807. 
29. GAVINS POINT DAM-LEWIS AND 
CLARK LAKE, MISSOURI RIVER 
BASIN, NE AND SD 
Location. On Missouri River in Yankton County, SD, 
and Knox County, NE, about 4 miles upstream from 
Yankton, SD, and 811.1 miles above mouth of river. 
Existing project. A concrete and rolled-earth-fill dam 
with a maximum height of 74 feet and a reservoir for 
flood control, irrigation, navigation, hydroelectric 
power, and other purposes with a gross storage capacity 
of 504,000 acre-feet at maximum operating pool. The 
power installation consists of three units rated at 33,333 
kilowatts each. Federal cost of the project was 
$49,617,000. Construction of original project was initiated 
in March 1952 and was completed in 1964. Project 
is providing its multiple purpose benefits for flood control, 
navigation, power, and other uses. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with other Missouri River 
reservoirs for flood control, navigation, power production 
and other multiple purpose uses. Generating units 
produced 765,812,000 net kilowatt-hours of electricity 
during fiscal year. Continued work on installation of a 
power plant controller system for the Missouri River 
dams and rehabilitation of spillway gates and bulkheads. 
Initiated work on generator rewind, rehabilitation 
powerplant HVAC system, and replace restroom at 
South Cottonwood Campground. Annual project visitation 
was estimated at 3,404,543. 
21-8

OMAHA, NE, DISTRICT 
30. OAHE DAM-LAKE OAHE, MISSOURI 
RIVER BASIN, SD AND ND 
Location. Dam is on Missouri River in Hughes and 
Stanley Counties, SD, about 6 miles northwest of 
Pierre, SD, and 1,072.3 miles above mouth of river. 
Existing project. A rolled-earthfill dam with maximum 
height of 245 feet, a crest length of 9,300 feet, and 
reservoir for flood control, irrigation, navigation, hydroelectric 
power, and other purposes, with a gross storage 
capacity of 23,337,000 acre-feet at maximum operating 
pool. It contains seven power units rated at 85,000 kilowatts 
each. Federal cost of the project was $346,521,000. 
Construction was initiated August 1948 and project 
placed in operation June 1963. Land acquisition is 99 
percent complete. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with the other Missouri 
River reservoirs for flood control, navigation, power production 
and other multiple purpose uses. Generating facilities 
produced 2,472,264,000 net kilowatt-hours of 
electricity. Installation of a power plant controller system 
on the Missouri River dams continued. Annual project 
visitation was estimated at 2,547,951. 
Miscellaneous 
31. STREAMBANK EROSION CONTROL 
EVALUATION AND 
DEMONSTRATION PROJECT 
Location. Along the Missouri River between Garrison 
Dam and Lake Oahe, ND and between Fort Randall 
Dam and Sioux City, IA; along the Yellowstone River in 
Montana and North Dakota; and along undesignated 
rivers and streams in the Omaha District. 
Existing project. The project provides for development 
of new methods and techniques for bank protection. 
It consists of various experimental bank stabilization 
structures designed to stabilize the river banks and 
prevent further loss of land through erosion. Construction 
was initiated in November 1976 on the Missouri 
River between Garrison Dam and Lake Oahe and between 
Gavins Point Dam and Sioux City, IA. Construction 
was initiated in August 1978 on the Missouri River 
between Fort Randall Dam and Lewis & Clark Lake. 
Construction was initiated in October 1980 on the Yellowstone 
River between Intake, MT and the mouth. 
Construction has been completed at a total Federal cost 
of $17,485,000. 
Local cooperation. Requirements are described in full 
on page 21-9 of Fiscal Year 1983 Annual Report. 
Operations during fiscal year. Project is financially 
complete. 
32. NATIONAL EMERGENCY 
PREPAREDNESS 
The total fiscal year cost for this category amounted 
to $322,174.92. 
33. GENERAL INVESTIGATIONS 
Fiscal Year 1986 costs totaled $2,093,276 for all General 
Investigation activities. See Table 21-K which covers 
Surveys, Collection and Study of Basic Data, Research 
and Development, Continuation of Planning and 
Engineering, Planning and Engineering under Proposed 
Program Legislation, and Advance Engineering and Design. 
21-9

TABLE 21-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
1. Missouri River, 
Sioux City, IA 
to Rulo, NE 
2. Sioux City Marina 
3. Bear Creek Lake, 
CO 
4. Bowman-Haley 
Lake, ND 
5. Chatfield Lake, 
CO 
(Required 
Contributed 
Funds) 
(Consolidated 
Summary) 
6. Cherry Creek 
Lake, CO 
7. East Nishnabotna 
River at Red Oak, 
IA 
8. Fall River 
Basin, SD 
9. Great Falls, MT 
(Required 
Contributed 
Funds) 
(Consolidated 
Summary) 
10. Indian Creek, 
Emerson, IA 
i
i
1 
Total Thru 
Funding FY 83 FY 84 FY 85 FY 86 Sep 30, 19 86 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
1,660 
1,544,000 
2,018,572 
- - 
- 470,000 
48,323 501,369 
274,000 332,000 
171,428 440,291 
150,000 99,000 
139,705 112,048 
442,000 1,600,000 
509,808 889,677 
- 530,250 
442,000 
509,808 
291,000 
291,525 
744,000 
421,538 
344,000 
402,380 
316,000 
288,836 
6,950,000 
6,217,952 
6,950,000 
6,217,952 
375,000 
47,276 
2,130,250 
889,677 
456,000 
451,280 
285,000 
284,444 
831,000 
1,150,517 
14,000 
8,995 
296,000 
326,557 
200,000 
1,235,141 
200,000 
1,235,141 
-42,000 
228,337 
2,330,000 1,7 
2,306,324 1,81 
- 1( 
- 1 
1,073 
261,000 2 
258,363 2 
168,000 
168,693 
2,022,000 
2,573,718 
150,980 
492,748 
2,172,980 
3,066,466 
625,000 
623,240 
-177,023 
373,000 
374,702 
-3,000 
13,792 
253,000 
260,565 
92,375 
129,600 
221,975 
50,506 
1
1 
2,5 
1,8
5 
3,1 
2,0
74 
7
4( 
4C 
22 
8
5E 
8
5E 
30 
3,045,000 
2,569,622
21-10 
- 189,225,9911 
- 189,225,9911 
92,000 103,923,419 
14,990 103,918,761 
00,000 100,000 
00,000 100,000 
- 62,003,600 
17 62,003,600 
27,000 1,592,000 
25,407 1,583,196 
- 4,372,174 
- 4,372,174 
27,000 1,670,043 
26,115 1,668,704 
84,000 93,182,700 
92,138 92,294,429 
61,000 1,242,230 
54,129 646,877 
45,000 94,424,930 
46,267 92,941,306 
48,000 3,049,800 
52,420 3,044,829 
53,000 15,285,364 
55,464 15,216,249 
34,000 5,426,511 
32,689 5,423,046 
- 2,154,016 
861 2,154,016 
- 5,538,432 
- 5,538,432 
87,000 3,065,141 
88,506 3,064,280 
25,000 12,017,1124 
53,139 11,746,1834 
- 308,600 
- 308,600 
25,000 12,325,7124 
53,139 12,054,7834 
- 333,000 
6,881 333,000

OMAHA, NE, DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Thru 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep 30, 1986 
11. Little Sioux River New Work: 
and Tributaries, IA Approp. 
Cost 
12. Lost Creek, New Work: 
Columbus, NE Approp. 
Cost 
(Required New Work: 
Contributed Approp. 
Funds) Cost 
(Consolidated New Work: 
Summary) Approp. 
Cost 
13. Missouri National New Work: 
Recreational River Approp. 
NE & SD Cost 
Maint. 
Approp. 
Cost 
14. Missouri River, New Work: 
Garrison Dam Approp. 
to Lake Oahe, ND Cost 
15. Missouri River, New Work: 
Kenslers Bend, Approp. 
NE, to Sioux Cost 
City, IA Maint. 
Approp. 
Cost 
16. Missouri River, New Work: 
Levees, IA, Approp. 
NE, KS'& MO Cost 
(Required New Work: 
Contributed Approp. 
Funds) Cost 
(Consolidated New Work: 
Summary) Approp. 
Cost 
17. Papillion Creek New Work: 
and Tributaries Approp. 
Lakes, NE Cost 
Maint. 
Approp. 
Cost 
19. Pipestem Lake, New Work: 
ND Approp. 
Cost 
Maint. 
Approp. 
Cost 
20. Salt Creek and New Work: 
Tributaries, NE Approp. 
Cost 
Maint. 
Approp. 
Cost 
22. Inspections of Maint. 
Completed Local Approp. 
Protection Projects Cost 
22. Inspection of Maint. 
Non-Federal Levees Approp. 
Cost 
250,000 
245,482 
1,300,000 
1,165,133 
128,300 
392 
1,428,300 
1,165,525 
8,957 
35,650 
30,000 
29,873 
4,233,000 
2,581,157 
38,810 
4,271,810 
2,581,157 
7,230,000 
4,786,701 
209,000 
187,375 
1,300,000 
1,291,413 
1,367,000 
703,300 
5,000 
1 ,37'7020 A 
703 
3,467,000 
3,288,990 
610,869 
8,345 
G,UUU 
,300 619 
- 20 
3,698 
- 200 
- 32 
2,883 
40,000 
37,996 
495,000 
1,269,792 
495,000 
1,269,792 
3,655,000 
6,943,608 
198,000 
205,100 
332,000 310,000 
261,478 375,541 
13,539 
495,000 
493,631 
202,000 
203,197 
27,000 
26,099 
10,045 
457,000 
444,306 
311,000 
276,596 
46,000 
46,094 
176,247 
294,000 
547,369 
- 294,000 
),214 547,369 
),000 136,000 
215 95,984 
),000 352,000 
,073 511,978 
- -28,000 
- 35,562 
34,000 
36,231 
1,462,000 
3,076,518 
38,810 
1,462,000 
3,115,328 
2,428,000 
2,524,245 
306,000 
312,244 
345,000 
349,945 
5,302 
537,000 
549,826 
183,000 
232,834 
44,000 
44,525 
39,000 
38,585 
287,000 
218,155 
287,000 
218,155 
1,627,000 
1,610,484 
473,000 
469,039 
271,000 
269,506 
213 
390,000 
387,776 
278,000 
277,285 
43,000 
43,167 
21-11 
20,499,920 
20,485,051 
3,484,518 
3,429,857 
147,300 
22,231 
3,631,818 
3,452,088 
756,800 
696,784 
552,000 
544,051 
9,413,000 
9,413,000 
11,294,414 
11,294,414 
4,390,000 
4,388,951 
39,789,388 
39,666,716 
38,810 
38,810 
39,828,198 
39,705,526 
43,617,7625 
43,572,1355 
1,949,000 
1,936,673 
9,277,545 
9,277,545 
2,643,000 
2,640,602 
12,197,6222 
12,197,6222 
6,706,475 
6,702,268 
2,599,348 
2,598,631 
160,000 
159,884 
i
i 
- 
6

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Thru 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep 30,1986 
23. Scheduling Flood Ma 
Control Reservoir 
Operations 
25. Big Bend Dam- Nei 
Lake Sharpe, 
Missouri River 
Basin, SD Ma 
26. Fort Peck Lake, Nei 
MT 
Ma 
27. Fort Randall Nei 
Dam-Lake Francis 
Case, Missouri 
River Basin, SD Ma 
28. Garrison Dam- Ne' 
Lake Sakakawea, 
Missouri River 
Basin, ND Ma 
(Federal Funds) 
Ma 
(Contributed Ma 
Funds) 
29. Gavins Point Ne' 
Dam-Lewis & 
Clark Lake, 
Missouri River Ma 
Basin, SD 
and NE 
30. Oahe Dam-Lake Nei 
Oahe, Missouri 
River Basin, 
SD & ND Ma 
31. Streambank Nei 
Erosion Control 
Evaluation and 
Demonstration Project 
int. 
Approp. 
Cost 
w Work: 
Approp. 
Cost 
int. 
Approp. 
Cost 
w Work: 
Approp. 
Cost 
int. 
Approp. 
Cost 
w Work: 
Approp. 
Cost 
int. 
Approp. 
Cost 
w Work: 
Approp. 
Cost 
int. 
Approp. 
Cost 
jor Rehab 
Approp. 
Cost 
jor Rehab 
Contrib. 
Cost 
w Work: 
Approp. 
Cost 
int. 
Approp. 
Cost 
w Work: 
Approp. 
Cost 
int. 
Approp. 
Cost 
w Work: 
Approp. 
Cost 
222,000 209,000 
220,935 208,870 
59,000 
59,000 
3,669,400 
3,304,557 
243,000 
243,000 
268,000 
269,355 
274,000 
273,069 
4,810,976 
4,809,766 
33,000 -25,000 107,497,597 
32,979 -24,979 107,497,597 
3,066,000 3,420,000 3,667,000 
3,396,128 3,482,368 3,642,938 
- -22,000 
145 1,694 -4,091 
42,577,9743 
42,524,2243 
- 158,428,080 
4,200 158,428,080 
5,558,000 2,391,000 4,327,000 3,399,000 
4,460,663 3,470,461 4,300,604 3,461,784 
433,000 455,000 
420,623 464,367 
7,996,000 6,379,000 
7,021,679 7,162,997 
- 287,000 
29,163 296,675 
8,639,300 6,083,000 
7,157,839 7,543,117 
7,000 130,000 
7,000 130,000 
112,000 
114,700 
5,701,000 
5,896,791
6 
52,807,5543 
52,777,5953 
- 199,065,883 
311 199,065,883 
6,957,000 80,477,8523 
6,925,109 80,325,6563 
- 295,729,613 
- 295,729,613 
9,166,000 7,148,000 
9,179,213 7,144,937 
163,000 
163,000 
78,000 
78,000 
5,408,659 3,699,000 3,641,000 4,246,000 
5,291,305 3,817,338 3,602,668 4,311,714 
1,501,000 
1,496,536 
7,886,700 
6,386,350 
15,000 
577,115 
737,000 -308,000 
746,523 -307,758 
91,921,7003 
91,828,7343 
4,208,310 
4,208,310 
686,961 
686,961 
49,617,239 
49,617,239 
59,293,1503 
59,265,3253 
- 346,520,603 
-2,892 346,517,696 
7,723,000 8,119,000 7,149,000 
9,237,595 8,062,707 7,283,549 
31,073 -4,689 10,432 
83,039,1453 
82,975,1193 
17,485,000 
17,485,000 
1. Includes $18,325,581 National Industrial Recovery 
Act funds, $8,625,718 Emergency Relief Funds, and 
$1,181,125 for previous project. 
2. Includes $123,000 of government cost applicable 
to that portion of the project which is currently being 
carried in a deferred status. 
3. Includes Special Recreation Use Fees. 
4. Includes $110,000 transferred to inactive portion 
for planning cost. 
5. Does not include $1,854,338 cost of inactive sites. 
21-12

OMAHA, NE, DISTRICT 
TABLE 21-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
1. 
Jan 12, 1927 
July 3, 1930 
Aug 30, 1935 
Mar 2, 1945 
Aug 13, 1968 
Flood Control 
Act of 1962 
Flood Control 
Act of 1950 
Aug 18, 1941 
Dec 22, 1944 
Dec 22, 1944 
June 30, 1948 
Aug 18, 1941 
Flood Control 
Acts of 1955, 1965 
June 30, 1948 
Flood Control 
Act of 1954 
June 30, 1948 
National Parks 
and Recreation 
Act of 1978 
MISSOURI RIVER, SIOUX CITY, IA TO RULO, NE 
Appropriation of $12 million authorized for H 
securmng a 6 foot depth from Quindaro Bend I 
(Kansas City, MO to Sioux City, IA). 
Appropriation of $15 million additional allotments 
totaling $29,153,108 made by Public Works 
Administration under provisions of National 
Industrial Recovery Act of 1938, and $9,669,791 
allotted under provisions of Emergency Relief 
Appropriations Act of 1935. 
For completion of project from mouth to Sioux H 
City, IA. 
For a channel of 9-foot depth and 300-foot width. H
I 
BEAR CREEK LAKE, CO 
A flood control reservoir for protection of S. 
metropolitan Denver, CO. I 
BOWMAN-HALEY LAKE, ND 
Flood control reservoir and water supply. H
I 
CHATFIELD LAKE, CO 
Flood control reservoir and channel improvements H 
to provide downstream protection for Denver, CO. I 
CHERRY CREEK LAKE, CO 
Initiation and partial accomplishment of project. H
P 
Completion of plan approved in Act of H 
Aug 18, 1941. P 
General comprehensive plan, Missouri River Basin. H
1
F 
EAST NISHNABOTNA RIVER AT RED OAK, IA 
Levee and appurtenant structures on left bank of P1 
the East Nishnabotna River at Red Oak, IA. 
Section 205. 
FALL RIVER BASIN, SD 
Provide flood control to the town of Hot H 
Springs, SD. P 
GREAT FALLS, MT 
Levees and channel improvement for local H 
protection. F
F 
INDIAN CREEK AT EMERSON, IA 
Levee and channel improvement for local P1 
protection - Section 205. 
LITTLE SIOUX RIVER, IA 
Correction of design deficiency. PI
F 
LOST CREEK AT COLUMBUS, NE 
Levee and channel improvement for local PI 
protection - Section 205. 
. Doc. 1120, 60th Cong. 
PL 75-560 
. Doc. 238, 73rd Cong. 
. Doc. 214, 76th Cong. 
PL 79-14 
Doc. 87, 90th Cong. 
PL 90-483 
. Doc. 574, 87th Cong. 
PL 87-874 
. Doc. 669, 80th Cong. 
PL 81-516 
. Doc. 426, 76th Cong. 
PL 77-228 
. Doc. 426, 76th Cong. 
PL 78-534 
. Doc. 475, and S. Docs. 
91 and 247, 78th Cong. 
PL 78-534 
L 858, 80th Cong. 
. Doc. 655, 76th Cong. 
?L 77-228 
. Doc. 343, 85th Cong. 
?L 85-500 
?L 89-298 
L 858, 80th Cong. 
L 341, 80th Cong. 
?L 83-780 
L 858, 80th Cong. 
MISSOURI NATIONAL RECREATIONAL RIVER, NE AND SD 
Preservation and enhancement of the Missouri PL 95-625 
River between the reaches from Gavins Point 
Dam, NE & SD to Ponca State Park, NE. 
21-13 
4. 
5. 
6. 
7. 
10. 
11. 
12. 
13.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Date of 
Authorizing 
Act 
See 
Section 
in Text 
14. 
15. 
AUTHORIZING LEGISLATION 
Project and Work 
Authorized Documents 
MISSOURI RIVER, GARRISON DAM TO LAKE OAHE, ND 
Bank stabilization and rectification. H. Doc. 343, 85th Cong. 
PL 88-253 
PL 90-843 
MISSOURI RIVER, KENSLERS BEND, NE TO SIOUX CITY, IA 
Construction of dike, revetments. H. Doc. 821, 76th Cong. 
PL 77-228 
PL 80-858 
Aug 18, 1941 
Dec 22, 1944 
Flood Control 
Act of 1968 
June 28, 1938 
Aqg 18, 1941 
Dec 22, 1944 
July 24, 1946 
May 17, 1950 
Sep 3, 1954 
Sep 3, 1954 
May 2, 1956 
July 3, 1958 
July 14, 1960 
Dec 30, 1963 
June 18, 1965 
May 12, 1967 
MISSOURI RIVER LEVEE SYSTEM, IA, NE, KS, 
Levees along both sides of river from 
Sioux City, IA to Kansas City, MO. 
Extended project from Kansas City, MO to mouth 
and provided for increased protection. 
AND MO. 
H. Doc. 821, 76th Cong. 
PL 77-228 
H. Doc. 475, 78th Cong. 
PL 78-534 
S. Docs. 191 and 247, 78th 
Cong. 
PAPILLION CREEK AND TRIBUTARIES LAKES, NE 
Series of flood control reservoirs, providing pro- H. Doc. 349, 90th Cong. 
tection for the metropolitan areas of Omaha, NE. PL 90-485 
PICK-SLOAN MISSOURI BASIN PROGRAM (OMAHA DIST.) 
Adopted general comprehensive plan for Missouri Flood Control Committee 
River Basin and authorized $9 million for Doc. 1, 75th Cong. 
initiation and partial accomplishment. PL 75-761 
Modified general comprehensive plan to include H. Doc. 842, 76th Cong. 
Harlan County Dam and Reservoir on PL 77-228 
Republican River, NE and authorized 
additional $7 million. 
Expanded general comprehensive plan for 
Missouri River Basin and authorized additional 
$200 million. 
Authorized additional $150 million for prosecution 
of general comprehensive plan for Missouri 
River Basin. 
Authorized additional $250 million for prosecution 
of general comprehensive plan for Missouri 
River Basin. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized additional 
$217,710,000. 
Authorized $5,384,014 to compensate Sioux 
Indians for reservation lands required for Oahe, 
South Dakota project. 
Modified general comprehensive plan for Missouri 
River Basin by deletion of construction of Red 
Willow Dam and Reservoir, NE, and addition of 
construction of Wilson Dam and Reservoir, KS. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized additional $200 
million 
H. Doc. 475, and S. Docs. 191 
and 247, 78th Cong. 
PL 78-534 
PL 79-526 
PL 81-516 
H. Does. 549 and 642, 81st 
Cong. PL 83-780 
PL 83-776 
PL 84-505 
H. Doc. 409, 84th Cong. 
PL 85-500 
Authorized additional $207 million for prosecution PL 86-645 
of general comprehensive plan for Missouri River 
Basin. 
Authorized additional $80 million for prosecution of PL 88-253 
eneral comprehensive plan for Missouri River 
asin and modified the plan to include work protection 
and rectification works below Garrison Dam. 
Authorized additional $116 million for prosecution PL 89-042 
of general comprehensive plan for Missouri River 
Basin. 
Authorized additional $20 million for prosecution PL 90-17 
of general comprehensive plan for Missouri River 
Basin. 
21-14 
TABLE 21-B (Continued) 
Flood Control 
Acts of 1963, 1968 
Aug 18, 1941 
June 30, 1948 
16. 
17. 
18.

OMAHA, NE, DISTRICT 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
Aug 13, 1968 
June 19, 1970 
Dec 24, 1970 
Dec 31, 1970 
Dec 23, 1971 
Mar 7, 1974 
July 8, 1976 
Nov 16, 1977 
Flood Control 
Act of 27 Oct 1965 
July 3, 1958 
May 17, 1950 
May 12, 1967 
Aug 13, 1968 
June 19, 1970 
Dec 23, 1971 
Mar 7, 1974 
July 8, 1976 
Nov 16, 1977 
Dec 22, 1944 
June 16, 1933 
Aug 30, 1935 
May 18, 1938 
Dec 22, 1944 
June 3, 1948 
Authorized additional $38 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
Authorized additional $109 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
Changed comprehensive plan name to Pick-Sloan 
Missouri Basin Program. 
Oahe Dam and Reservoir, ND. 
Authorized additional $101 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
Authorized additional $72 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
Authorized additional $85 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
Authorized additional $59 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
PIPESTEM LAKE, ND 
Provide flood control for Jamestown, ND and 
downstream areas. 
PL 90-483 
H. Doc. 91-748 and 
S. Doe. 91-895 
PL 91-282 
S. Doc. 91-1100. 91st Cong. 
PL 91-576 
H. Doe. 91-23 and 
PL 91-611 
PL 92-222 
PL 93-251 
PL 94-347 
PL 95-189 
H. Doc. 266, 89th Cong. 
PL 89-298 
SALT CREEK AND TRIBUTARIES, NE 
Series of dams and channel improvements for flood H. Doc. 396, 84th Cong. 
control around Lincoln, NE. PL 85-500 
SOUTH PLATTE RIVER BASIN, CO 
Adopted plan of improvement for South Platte H. Doc. 669, 80th Cong. 
River Basin and authorized $26.3 million for PL 81-516 
initiation and partial accomplishment. 
Authorized additional $2 million for prosecution of plan. PL 90-17 
Authorized additional $12 million for prosecution of plan PL 90-843 
Authorized additional $21 million for prosecution of plan. PL 91-282 
Authorized additional $37 million for prosecution of plan. PI. 92-222 
Authorized additional $15 million for prosecution of plan. PL 93-251 
Authorized additional $22 million for prosecution of plan. PL 94-347 
Authorized additional $3 million for prosecution of plan. PL 95-189 
BIG BEND DAM - LAKE SHARPE, SD 
Expanded general comprehensive plan for flood H. D)oc. 475, S. I)oc. 2417, 
control and other purposes in the Missouri 78th Cong. PL 78-534 
River Basin. 
FORT PECK LAKE, MT 
Construction of earth dam, as recommended by II. I)oc. 238, 73rd Cong. 
Chief of Engineers Sep 30, 1933, was included in PL 73-409 
Public Works Administration program, Oct 14, 1933 
as authorized by the National Industrial Recovery 
Act of 1933 and adopted by the River and Harbor 
Act of 1935 (PL 74-409). 
Completion, maintenance, and operation of a PL 75-529 
hydroelectric powerplant, subject to certain provisions 
in act respecting transmission and sale of 
electric energy. Also authorizes installation of 
additional power-generating facilities by Secretary 
of War when deemed necessary in judgment of 
Bureau of Reclamation. 
Modified authorization to provide for full multiple II. Doc. 475 and S. )ocs. 191 
purpose operation. and 247, 78th Cong. 
PL 78-534 
Payments to be made to school districts serving PL 80-586 
project as reimbursement for educational facilities 
(including transportation to and from school) for 
pupils who are dependents of persons engaged in construction, 
operation, and maintenance of projects. 
21-15 
19. 
20. 
21. 
25. 
26.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
27. FORT RANDALL DAM - LAKE FRANCIS CASE, SD 
Dec 22, 1944 Expanded general comprehensive plan for flood H. Doc. 475 and S. Docs. 191 
control and other purposes in the Missouri and 247, 78th Cong. 
River Basin. PL 78-534 
28. GARRISON DAM - LAKE SAKAKAWEA, ND 
Dec 22, 1944 Expanded general comprehensive plan for flood H. Doc. 475, S. Doc. 247, 
PWA 1968 control and other purposes in the Missouri 78th Cong. PL 78-534 
River Basin. 
29. GAVINS POINT DAM - LEWIS AND CLARK LAKE, NE & SD 
Dec 22, 1944 Expanded general comprehensive plan for flood H. Doc. 475, S. Doc. 247, 
control and other purposes in the Missouri 78th Cong. PL 78-534 
River Basin. 
30. OAHE DAM - LAKE OAHE, SD & ND 
Dec 22, 1944 Expanded general comprehensive plan for flood H. Doc. 475 and S. Docs. 191 
control and other purposes in the Missouri and 247, 78th Cong. 
River Basin. PL 78-534 
31. STREAMBANK EROSION CONTROL EVALUATION AND 
DEMONSTRATION PROJECT 
Mar 7, 1974 Experimental bank stabilization methods to PL 93-251 
prevent losses due to erosion. 
TABLE 21-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report Cost to September 30, 1986 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Missouri River, Sioux City, IA to 
Fort Benton, MT Complete 1948 3,123,141 644,863 
Small Navigation Project at 
Sioux City, IA Complete 1970 43,582- 
TABLE 21-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Full Report Cost to September 30, 1986 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Belle Fourche, Cheyenne River, SD1 Complete 1940 37,410 - 
Big Sioux River at Sioux City, IA Complete 1982 7,458,934 - 
Blackbird Creek Near Macy, NE 2 Complete 1970 262,479 - 
Boulder Creek, Boulder, CO Inactive 1976 142,666 - 
Buffalo Creek, 
Meadow Grove, NE 2 Complete 1974 293,016 - 
Buffalo Creek, Scranton, ND2 Complete 1960 102,980- 
Buffalo, WY Inactive 1961 -- 
Castlewood Lake, Cherry Creek and 
Tributaries, CO Inactive 1943 - 
Cedar Canyon Dam, Rapid City, SD Complete 1960 120,482 
City of Aurora, 
Westerly Creek, CO Complete 1955 150,000 
Clarkson, NE, Maple Creek Complete 1967 191,282 
Council Bluffs, IA (Act of 1936) Complete 1939 - 
Council Bluffs, IA (Act of 1944) Complete 1954 2,557,680 
Davids Creek Lake, IA 
(Act of 1968) Inactive 1972 
21-16

OMAHA, NE, DISTRICT 
TABLE 21-E (Continued) 
Project 
Deadman's Gulch, Sturgis, SD 2 
Dry Creek, Hawarden, IA 
Eagle Bay and Fort Yates 
Highway Bridges, N.D. 
Floyd River, Sioux City, IA 
Forsyth, MT 
Frazer-Wolf Point, MT 
Gering Valley, NE 
Glasgow, MT 
Greybull, WY 
Havre, MT 
Herreid, Spring Creek, SD 
Hooper, NE2 
Ida Grove, IA2 
Jamestown Reservoir, ND 
Linton, ND 2 
Little Papillion Creek, NE 
Little Nemaha River, NE 
Loup River, Columbus, NE 2 
Lower Big Sioux River, IA and SD 
Lower Heart River, ND 
Madison, NE, Union and 
Taylor Creeks 2 
Mandan, Heart River, ND 
Marmarth, ND 
McCook Lake, SD 
Miles City, MT 
Missouri River, Aten, NE 
Missouri River, Niobrara, NE 
Mott, ND 
Mud Creek, Broken Bow, NE 2 
Nishnabotna River at 
Hamburg, IA 
Norfolk,.NE 
Omaha, NE 
Pierce, NE 
Platte River Near Schuyler, NE 2 
Platte River and Lost Creek, 
Schuyler, NE 
Platte River and Tributaries, NE 
Rapid Creek, Rapid City, SD 
Saco, MT 
Sacred Heart Hospital, 
Yankton, SD 
Sheridan, WY3 
Shields River, 
Near Clyde Park, MT2 
Sioux Falls, SD 
South Platte River Levees and 
Channel Improvements, Chatfield 
Lake to Ft. Morgan, CO 
Vaughn, MT, Sun River 2 
Waterloo, NE 
West Point, NE 
Yellowstone River, 
W. Glendive, MT 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Status 
Complete 
Complete 
Active 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Inactive 
Complete 
Inactive 
Complete 
Inactive 
Complete 
Complete 
Complete 
Complete 
Complete 
Inactive 
Complete 
Complete 
Deferred 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Inactive 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Inactive 
Complete 
Complete 
Complete 
Complete 
For Last 
Full Report 
See Annual 
Report For 
1981 
1964 
1978 
1970 
1950 
1982 
1971 
1939 
1960 
1958 
1954 
1968 
1972 
1950 
1973 
1976 
1973 
1973 
1966 
1964 
1967 
1960 
1960 
1958 
1956 
1951 
1945 
1976 
1948 
1971 
1954 
1967 
1948 
1971 
1980 
1958 
1978 
1976 
1951 
1966 
1957 
1971 
1970 
1966 
1960 
Operation and 
Maintenance 
234,839 
676,916 
169,498 
147,627 
578,791 
99,370 
1,000,000 
236,000 
3,400,504 
5,903,640 
296,597 
74,940 
257,398 
1,538,269 
1,004,000 
67,793 
184,380 
2,618,809 
25,747 
5,288,707 
457,582 
237,883 
149,596 
230,294 
5,633 
-
- 
5,633 
1. Completed as a Public Works Administration project. 
2. Authorized by Chief of Engineers. 
3. Includes inactive segment. 
21-17 
Cost to September 30, 1986 
Construction 
3,000,000 
400,000 
616,639 
11,556,667 
255,177 
435,000 
5,989,663 
16,832 
248,507 
1,825,881 
50,216 
326,667 
522,344 
3,643,111 
1,000,000 
1,961,173

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 21-F OTHER MULTIPLE PURPOSE PROJECTS INCLUDING POWER 
Full Report Cost to September 30, 1986 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Gavins Point Dam-Lewis and Clark 
Lake, Relocation of Niobrara, NE Complete 1980 13,516,459 - 
Springfield, SD Water Intake Active - - - 
Williston, ND Water Intake Complete 1981 988,583 - 
TABLE 21-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Authority Federal Contributed 
See Annual and Funds Funds 
Project Report For Date Expended Expended 
Billings, MT 1976 Sec. 201, FC Act 1950 75,000 - 
23 Mar 81 
Dayton, WY 1956 Sec. 12, PL 93-251 - - 
WRDA of 1974 
5 Aug 77 
Giles Creek, Elkhorn, NE 1952 Sec. 12, PL 93-251 - - 
WRDA of 1974 
6 Nov 77 
Indian Creek Lake, IA 1969 Sec. 12, PL 93-251 135,000 - 
WRDA of 1974 
4 Jan 74 
Morrison, Bear Creek, CO 1950 Sec. 12, PL 93-251 30,000 - 
WRDA Of 1974 
5 Aug 77 
Redwater River and 1966 Sec. 12, PL 93-251 1,000 - 
Hay Creek, Bell Fourche, SD WRDA of 1974 
4 Jan 74 
Shell Creek, NE 1962 Sec. 12, PL 93-251 71,000 - 
WRDA of 1974 
3 Oct 78 
Vermillion River and Tribs, SD 1968 Sec. 12, PL 93-251 208,000 - 
WRDA of 1974 
4 Jan 74 
TABLE 21-H MISSOURI RIVER LEVEE SYSTEM, SIOUX CITY, IA TO RULO, NE 
(See Section 16 of Text) 
Miles of 
Unit Levee Status 
L627-624 Mosquito Creek Levee 14.2 Complete 1950 
L601 Watkins-Waubonsie Ditch Levees 15.0 Complete 1966 
L594 Pleasant Valley Levee 11.4 Complete 1964 
R580 Nebraska City Levee 0.2 Complete 1950 
L575 Thurman-Hamburg Levee 45.8 Complete 1950 
R573 Otto County Drainage District No. 2 5.9 Complete 1950 
R562 Peru Dike 7.6 Complete 1950 
L561-550 Atchison County Levee District No. 1 41.3 Complete 1952 
R548 Brownville-Nemaha Levee 19.5 Complete 1952 
L536 Mill Creek Levee 13.6 Complete 1952 
R520 Richardson County Drainage Dist. No. 8 6.3 Complete 1960 
R613 Papillion Creek-Platte River Levee 14.0 Complete 1971 
R616 Bellevue-Papillion Creek Levees 4.5 Under Construction 
L611-614 Mosquito-Keg Creek Levees 22.0 Under Construction 
L627, L624, 
L561-550 Remedial Studies on Completed Units Studies Complete 
Comprehensive Restudy of Levee System Scheduled to Start 1988 
21-18

OMAHA, NE, DISTRICT 
TABLE 21-I 
PICK-SLOAN MISSOURI BASIN PROGRAM 
(See Section 18 of Text) 
Estimated Estimated 
Project Federal Cost Non-Federal Cost 
Fort Peck Lake, MT1, 2 158,428,000 1,103,000 
Garrison Dam, Lake Sakakawea, ND1, 2 299,938,000 1,516,000 
Missouri River Levee System, IA, NE, KS and MO 
(Sioux City, IA to Rulo, NE)1, 3 38,400,000 4,600,000 
Oahe Dam-Lake Oahe SD and ND1, 2 346,521,000 2,320,000 
Big Bend Dam-Lake Sharpe, SD1, 2 107,498,000 302,000 
Fort Randall Dam, Lake Francis Case, SD1 ,2 199,066,000 1,609,000 
Gavins Point Dam, Lewis & Clark Lake, SD & NE1,2 49,617,000 137,000 
Gavins Point Dam, Lewis & Clark Lake, SD 
& NE-Relocation of Niobrara, NE 2 13,516,000 - 
Omaha, NE2 5,904,000 362,000 
Council Bluffs, IA2 2,558,000 146,000 
Missouri River, Garrison Dam to Lake Oahe, ND1, 2 9,414,000 270,000 
Cherry Creek Lake, CO1,2 15,285,000 285,000 
1 Details presented on individual report. 2 Completed. 3 Active portion of project. 
INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
TABLE 21-J (See Section 22 of Text) 
Location Month Inspected 
Montana 
Glasgow, Milk River Jun 86 
Saco, Beaver Creek Jun 86 
Havre, Milk River Aug 86 
Havre, Scott Coulee-Bull Hook Dam Aug 86 
Clyde Park, Shields River Jul85 
Three Forks, Lower Madison River Jun 84 
Forsythe, Yellowstone River Jun 84 
West Glendive, Yellowstone River May 85 
Vaughn, Sun River Jun 84 
*Yellowstone River, Water Plant, Livingston Sep 85 
*Yellowstone River, Reedpoint Bridge Inactive 
*Yellowstone River, Greycliff Bridge Sep 85 
*Yellowstone River, Springdale Bridge Inactive 
*Yellowstone River, Near Miles City 
Water Intake & Sewage Lagoon Inactive 
*Yellowstone River, Bank Protection, Billings Inactive 
*Yellowstone River, Yellowstone Co. Bridge, Near Billings Jun 84 
*Yellowstone River, Voges Bridge, Near Big Timber Jun 84 
*Jefferson River, Willow Creek Bridge, Near Three Forks Sep 85 
*Jefferson River, Bank Protection, Near Waterloo Sep 85 
*Big Hole River, Pennington Bridge, Near Twin Bridges Sep 85 
*Ruby River, Wheatly Bridge, Near Twin Bridges Sep 85 
*Big Horn River, Two Leggin Bridge, Near Hardin Inactive 
*Missouri River, Bank Stabilization, Fort Benton Sep 85 
Wyoming 
Greybull, Big Horn River Jun84 
Sheridan, Big and Little Goose Creeks Jun 84 
*Shoshone River, Bank Protection, Lovell Jun 84 
North Dakota 
Mandan, Lower Heart River Aug 86 
Marmarth, Little Missouri River Aug 86 
Scranton, Buffalo Aug 86 
21-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
TABLE 21-J (Continued) (See Section 22 of Text) 
Location Month Inspected 
South Dakota 
Sioux Falls, Big Sioux River Jul86 
Belle Fourche, Belle Fourche River Aug 86 
Rapid City, Cedar Canyon Dam Sep 86 
Hot Springs, Fall River Channel Sep 86 
Herreid, Spring Creek Sep 85 
*Missouri River, Bank Protection, Greenwood Aug 84 
*Bad River, Bank Protection, Fort Pierre Jun 85 
*Big Sioux River, Schofield Bridge, Near Flandreau Sep 86 
*Big Sioux River, Fink Bridge, Near Flandreau Sep 86 
Rapid Creek, Rapid City Sep 86 
Sacred Heart Hospital, Yankton Jun 85 
Colorado 
Aurora, Westerly Creek-Kelley Road Dam Jul86 
*Plum Creek, Bank Stabilization, Aurora Jul86 
*South Platte River, Bank Protection, Denver Aug 84 
*Cache La Poudre River, Ft. Collins Jul86 
*Cache La Poudre River, Windsor Jul86 
*South Platte River, Kersey Jul86 
*South Platte River, Merino Jul86 
*South Platte River, Iliff Jul 86 
*South Platte River, Platteville Jul86 
*Big Thompson River, Johnstown Jul86 
Cache La Poudre River, Ft. Collins (Water Treatment Plant) Jul 86 
South Platte River, Adams County, No. Washington St. 
Water and Sanitary District Jul86 
Nebraska 
Omaha, Missouri River Sep 86 
Waterloo, Elkhorn River May 86 
West Point, Elkhorn River Apr 86 
Pierce, Elkhorn River May86 
Clarkson, Middle Fork, Maple Creek Jul86 
Hooper, Elkhorn River Jun 86 
Norfolk, North Fork, Elkhorn River Aug 86 
Madison, Union & Taylor Creeks Jun 86 
*Platte River, M.U.D. Protection, Cedar Island Sep 86 
*Platte River, Bank Protection, Louisville Aug 86 
*Elkhorn River, Q Street Bridge, Near Gretna Sep 86 
*Elkhorn River, Ray Bridge, Near Norfolk Aug 86 
*North Platte River, Bank Stabilization, Minatare Dec 85 
*Logan Creek, Bank Protection, Near Bancroft Feb 86 
*Battle Creek, Bank Protection, Battle Creek Mar 86 
Schuyler, Platte River May 86 
Schuyler, Lost Creek & Platte River May 86 
Little Papillion, Little Papillion Creek Jun 86 
Gering Valley, Gering Drain & Tributaries Dec 85 
Macy, Blackbird Creek May 86 
Lincoln, Salt Creek & Tributaries May 86 
Meadow Grove, Buffalo Creek Jun 86 
Columbus, Loup River Aug 86 
Broken Bow, Mud Creek Sep 86 
*Tangeman, Little Nemaha River Aug 86 
*Julian, Rock Creek Feb 86 
*Muddy Creek near Syracuse Aug 86 
21-20

OMAHA, NE, DISTRICT 
INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
TABLE 21-J (Continued) (See Section 22 of Text) 
Location Month Inspected 
Columbus Flood Control Project, Lost Creek, Columbus Aug 86 
*Shell Creek, County Road near Columbus Mar 86 
*Middle Pebble Creek, Snyder Apr 86 
*Elm Creek, Burt County Feb 86 
Iowa 
Council Bluffs, Missouri River Jul86 
Ida Grove, Maple River-Odebolt Creek Apr 86 
Sioux City, Floyd River Sep 86 
Hawarden, Dry Creek Apr 86 
Hamburg L575, Nishnabotna River Apr 86 
Intercounty D.D., Little Sioux River Jan 86 
Nagel D.D., Little Sioux River Jan 86 
Bennett-McDonald-Smithland D.D., Little Sioux River Jan 86 
*West Nishnabotna River, Mills Co. Bridge, Near Malvern Aug 86 
*West Nishnabotna River, Mills Co. Bridge, Near Hastings Aug 86 
*East Nishnabotna River, Page Co. Bridge, Near Essex Sep 86 
*Missouri River, Marina, Sioux City Jun 86 
*West Nishnabotna River, Near Hancock Sep 86 
*East Nishnabotna River, Near Griswold Sep 86 
East Nishnabotna River, Red Oak Jan 86 
Emerson, Indian Creek, Mills County Mar 86 
*East Fork tf Boyer River, Near Vail Mar 86 
Monona-Harrison Ditch Control, Monona County Jan 86 
Missouri River Levees 
L624 & L627, Mosquito Creek & Sieck Levees Jul86 
L601, Watkins Levee District Feb 86 
L601, Miller-Sturgeon Levee District Feb 86 
L601, Missouri River Levee District #1 Feb 86 
L594, Waubansie Drainage District Feb 86 
L594, Pleasant Valley Levee District Feb 86 
L575, Benton-Washington Levee District Jan 86 
L575, Northwest Atchison Levee District Jun 86 
L575, McKissock Island Levee District Jun 86 
L575, Buchannan Levee District Jun 86 
L561, L550, L536, Atchison County Levee District Apr 86 
L611-614, M & P Missouri River Levee District Mar 86 
R613, Sarpy Co. Soil & Water Cons. D. Sep 86 
R562, Peru Levee District Mar 86 
R548, Brownville-Nemaha Levee District Mar 86 
R548, Little Nemaha Levee District Feb 86 
R520, Richardson Co. Levee Dist. #8 Apr 86 
R573, Otoe County Drainage Dist. #2 Mar 86 
*Denotes Section 14 Projects 
ACTIVE GENERAL INVESTIGATIONS 
TABLE 21-K (See Section 33 of Text) 
Federal Cost Totals By 
Item FY 86 Categories 
SURVEYS (Category 100) 
Flood Damage Prevention Studies (120) 
Platte River Basin, CO 151,748 
Eastern SD and Upper Big Sioux River, SD, IA 294,389 
Missouri River, SD, NE, ND, MT 507,575 
Western Dakotas Region of SD 164,930 
Subtotal 1,118,642 
21-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 21-K (Continued) 
ACTIVE GENERAL INVESTIGATIONS 
(See Section 33 of Text) 
Federal Cost 
Item FY 86 
Review of Authorized Projects (160) 
Cannonball River at Mott, ND 
Miscellaneous Activities (170) 
Special Investigations 
FERC Licensing 
Subtotal 
Coordination Studies with Other Agencies (180) 
Soil Conservation Service, Dept. Agric. (181) 
Bureau of Reclamation, Dept. Interior (182) 
Missouri River Basin Commission (183) 
Planning Assistance to States (186) 
Technical Assistance for Streambank Erosion (188) 
Subtotal 
TOTAL (Category 100) 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) 
Hydrologic Studies (260) 
TOTAL (Category 200) 
RESEARCH AND DEVELOPMENT (Category 300) 
None 
CONTINUATION OF PLANNING AND ENGINEERING (Category 
Perry Creek, IA (450) 
Westerly Creek, CO (450) 
Gregory County Hydroelectric Pumped Storage Facility (460) 
TOTAL (Category 400) 
PLANNING AND ENGINEERING UNDER PROPOSED 
LEGISLATION (Category 500) 
None 
ADVANCE ENGINEERING AND DESIGN (Category 600) 
None 
GRAND TOTAL GENERAL INVESTIGATIONS 
20,114 
51,061 
6,435 
77,610 
5,303 
15,659 
9,065 
69,881 
258,954 
358,862 
201,819 
4,745 
Totals By 
Categories 
1,555,114 
206,564 
400) 
166,154 
148,217 
17,227 
331,598 
2,093,276 
FLOOD CONTROL ACTIVITIES UNDER SPECIAL AUTHORIZATION 
TABLE 21-L (See Section 24 of Text) 
Fiscal Year 
Project Name Stage Cost 
Section 205: 
Indian Creek, Emerson, IA - Jobs Act C 6,881 
Lower Heart River, Mandan, ND D 70,283 
Lost Creek, Columbus, NE C 547,369 
North Platte River, Casper, WY R 12,393 
Pebble Creek, Scribner, NE P 85,307 
Platte River, Cedar Creek, NE R 90,559 
East Nishnabotna River, Red Oak, IA C 861 
Lodgepole Creek, Sidney, NE D 2,610 
2 Negative Appraisals 14,700 
Total (Section 205) 830,963 
21-22 
- - - - - M - -- - - -- --

OMAHA, NE, DISTRICT 
FLOOD CONTROL ACTIVITIES UNDER SPECIAL AUTHORIZATION 
TABLE 21-L (See Section 24 of Text) 
Fiscal Year 
Project Name Stage Cost 
Section 14: 
Logan Creek, Bancroft, NE P 7,680 
County Rd. Bridge, Elm Creek, Decatur, NE C 2,857 
Blackbird Creek, Burt County, NE C 17,784 
Elm Creek, Sec. 15, Burt County, NE C 1,263 
Elm Creek, Sec. 16, Burt County, NE C 2,168 
Elm Creek, Burt County, NE C 23,675 
South Creek, Martinsburg, NE C 26,250 
Muddy Creek, Syracuse, NE - Jobs Act C 1,810 
Waste Water Treatment Plant, Snyder, NE C 1,524 
Shoshone River, Byron, WY - Jobs Act C 1,674 
Big Sioux River, Plymouth County, IA - Sec. 4 C 57,968 
Big Sioux River, Harrisburg, IA C 15,593 
Big Sioux River, Sec. 32, IA C 34,011 
Big Sioux River, Well House, SD C 7,500 
Big Thompson River, Johnstown, CO C 6,027 
Cache La Poudre River, Windsor, CO C 9,051 
Elk Creek, Jackson, NE C 30,025 
Elk Creek, Willis, NE C 18,861 
Elm Creek, Decatur, NE R 2,389 
Platte River, Brady, NE C 5,941 
Platte River, Camp Ashland, NE P 18,401 
Platte River, Hansen Lake, NE C 46,186 
Redbird Creek, Holt County, NE C 41,960 
Salt Creek, Lincoln, NE C 41,714 
Niobrara River (Carns Bridge), NE P 6,916 
Platte River, Ft. Lupton, CO C 18,907 
So. Platte River, Kersey, CO C 78,875 
So. Platte River, Platteville, CO C 1,361 
So. Platte River, Weldona, CO C 9,099 
So. Platte River, Iliff, CO C 27,790 
So. Platte River, Merino, CO C 34,350 
So. Platte River, Balzac, CO P 3,868 
So. Platte River, Goodrich, CO C 3,101 
So. Platte River, Morgan County, CO C 7,592 
Vermillion River, Waste Water Treatment Plant C 22,489 
Vermillion River, Vermillion, SD C 142,876 
Marne Creek, Yankton, SD P 32,735 
West Papillion Creek, Douglas County, NE C 89,249 
Wigle Creek, Homer, NE C 19,121 
Yellowstone River, Glendive, MT C 8,950 
Medicine Bow River, Elk Mountain, WY C 5,230 
13 Negative Appraisals 83,300 
Total (Section 14) $1,018,121 
Total Continuing Authorities $1,849,084 
R= Recon 
D=Detailed Project Study 
P= Plans & Specs 
C = Construction 
21-23

OHIO RIVER * 
For actual construction of locks and dams, and operation 
and care of completed stuctures, river is divided into 
three sections under immediate supervision and direction 
of District Engineers at Pittsburgh, Huntington and 
Louisville. Pittsburgh section extends 127 miles from 
head of river at Pittsburgh, Pa., to a point immediately 
upstream from New Martinsville, W. Va., and includes 
Emsworth, Dashields, Montgomery, New Cumberland, 
Pike Island and Hannibal locks and dam. Huntington 
section extends 311 miles from mile 127 to 438 
immediately upstream from Foster, Ky., and includes 
Willow Island, Belleville, Racine, Gallipolis, Greenup and 
Captain Anthony Meldahl locks and dams. Louisville section 
extends 543 miles from mile 438 to mouth of river, 
and includes Markland and McAlpine locks and dams 
(with Louisville and Portland Canal) Cannelton, 
Newburgh, Uniontown, and Smithland locks and dams 
and Locks and Dams 52 and 53. 
IMPROVEMENTS 
Navigation 
1. Construction of locks and dams on Ohio 
River ................................. 22-1 
2. Open channel work, Ohio River............ 22-4 
Tables 
Table 22-A Cost and Financial Statement ...... 22-5 
Table 22-B Authorizing Legislation............ 22-6 
Table 22-C Not Applicable 
Table 22-D Not Applicable 
Table 22-E Not Applicable 
Navigation 
1. CONSTRUCTION OF LOCKS AND 
DAMS ON OHIO RIVER 
Location. Ohio River is formed by junction of Allegheny 
and Monongahela rivers at Pittsburgh, Pa., and flows 
generally southwesterly for 981 miles to join Mississippi 
River near Cairo, Ill. For description of river see page 
1227, 1932 Annual Report. 
Previous projects. For details see page 1907 of Annual 
Report for 1915. 
Existing project. Provides for improvement of entire 
river by construction of locks and dams to provide a 
channel depth of 9 feet and for widening Louisville and 
Portland Canal at Louisville, Ky. Project provides for a 
lock with usable dimensions of 110 by 600 feet at each 
of the dams and, in addition, an auxiliary lock 56 by 360 
feet is available at Emsworth, Dashields, Montgomery, 
and McAlpine locks and dams with an auxiliary lock at 
Gallipolis being 110 by 360 feet. Dashields is a fixed dam, 
while Emsworth, Montgomery, and Gallipolis are fixed 
dams with movable crests. Remaining dams are movable 
Table 22-F Not Applicable 
Table 22-G Not Applicable 
Table 22-H Construction of Locks and Dams on 
Ohio River, Total Cost of Existing 
Project .......................... 22-6 
Table 22-I Federal Energy Regulatory 
Commission Licenses of Locks 
and Dams, Ohio River............. 22-6 
Table 22-J Ohio River Locks and Dams 
Statistics ....................... 22-7 
type, with navigable pass varying in width from 600 to 
1,248 feet. In addition to navigable pass, movable-type 
dams are also provided with one or more regulating weirs. 
At McAlpine Locks and Dam, a canal (Louisville and 
Portland) extends along left bank for 2 miles, with locks 
at lower end. Modifications to existing project under purview 
of Section 6, March 3, 1909 Act, provide for fixed 
dams with movable crests with two locks (110 by 1200 feet 
and 110 by 600 feet) at New Cumberland, Pike Island, 
Hannibal, Willow Island, Belleville, Racine, Greenup, 
Captain Anthony Meldahl, Markland, Cannelton, 
Newburgh, and Uniontown; two locks 110 by 1200 feet 
at Smithland; 110 by 1,200 foot temporary locks in addition 
to the existing locks at Locks and Dams 52 and 53, 
and reconstruction to provide a 110 by 1200-foot lock in 
addition to existing locks and a fixed dam with two sections 
of movable crest at McAlpine Locks and Dam; widening 
Louisville and Portland Canal to 500 feet. Auxiliary 
lock 56 by 360 feet at McAlpine Locks and Dam has been 
inoperative since failure of downstream lock gates in 
December 1972. Rehabilitation of existing Locks and 
Dams 52 and 53 was started in September 1979 under 
the purview of Section 6, March 1909 Act. Mound City 
was also considered authorized under purview of 1909 Act, 
22-1

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
and preconstruction planning was performed in the period 
1965 to 1972. The ruling of the U.S. District Court, 
District of Columbia, on September 6, 1974, with 
reference to Lock and Dam 26, Mississippi River, would 
also apply to this project. Consequently, it is no longer 
considered authorized. Operation and care of locks and 
dams were included in project July 1, 1935, under provisions 
of Permanent Appropriations Repeal Act of June 26, 
1934. Estimated Federal cost of new work (existing project, 
1983), exclusive of Gallipolis Locks and Dam reported 
under Kanawha River project is $1,778,840,999, 
estimated non-Federal cost is $14,999,000. Foregoing 
estimate does not include expenditures on previous projects. 
Various items previously included in this project are 
considered inactive or unnecessary and are excluded from 
foregoing cost estimate. See page 693, Annual Report, 
1968 for items and estimated cost. Under authority of 
1910 River and Harbor Act, Louisville and Portland 
Canal was widened to 200 feet; Locks and Dams 40 and 
42 eliminated; Locks and Dams 1 and 2 replaced by 
Emsworth Locks and Dam; Lock and Dam 3 replaced by 
Dashields Locks and Dam; and Locks and Dams 4, 5, and 
6 replaced by Montgomery Locks and Dam. Locks and 
Dams 24, 25, and 26 were replaced by Gallipolis Locks 
and Dam authorized by August 30, 1935 Act, and constructed 
under project for improving lower Kanawha 
River. Locks and Dams 7, 8, and 9 were replaced by New 
Cumberland Locks and Dam; Locks and Dams 10 and 11 
were replaced by Pike Island Locks and Dam; Locks and 
Dams 12, 13, and 14 were replaced by Hannibal Locks 
and Dam; Locks and Dams 15, 16, and 17 were replaced 
by Willow Island Locks and Dam; Locks and Dams 18, 
19, and 20 were replaced by Belleville Locks and Dam; 
Locks and Dams 21, 22, and 23 were replaced by Racine 
Locks and Dam; Locks and Dams 27, 28, 29, and 30 were 
replaced by Greenup Locks and Dam; Locks and Dams 
31, 32, 33, and 34 were replaced by Captain Anthony 
Meldahl Locks and Dam; Locks and Dams 35, 36, 37, 38, 
and 39 were replaced by Markland Locks and Dam; the 
Louisville and Portland Canal at McAlpine Locks and 
Dam was widened to 500 feet. Locks and Dams 43, 44, 
and 45 were replaced by Cannelton Locks and Dam; Locks 
and Dams 46 and 47 were replaced by Newburgh Locks 
and Dam; Locks and Dams 48 and 49 were replaced by 
Uniontown Locks and Dam, presently under construction; 
and Locks and Dams 50 and 51 were replaced by 
Smithland Locks and Dam, presently under construction, 
as modifications to existing project under purview of 
Section 6, March 3, 1909 Act, reducing total number of 
structures to 20. The Water Resources Development Act 
of 1974 combined the Newburgh Bank Protection Works 
project with the Newburgh Locks and Dam project. A 
December 1981 Act established the Falls of the Ohio 
National Wildlife Conservation Area near McAlpine 
Locks and Dam to protect and preserve existing fossilized 
coral and a diversity of wildlife. Table 22-J contains data 
relative to various features of locks and dams included 
in existing projects. For list of principal towns and cities 
along Ohio River with their mileage below Pittsburgh, 
PA, see page 1060, 1962 Annual Report. See Table 21-I 
for licenses. 
Navigation system of 21 locks and dams is in operation 
and 9-foot navigation throughout length of river is 
generally available at all times. At certain unstable bars 
project depth is maintained by dredging, supplemented 
by contraction works. (See "Open Channel Work, Ohio 
River.") Table 22-J shows cost and year completion of 
locks and dams now in operation. Existing project does 
not provide adequate facilities for present day navigation 
due to obsolescence of structures. Since repair and modernization 
of these facilities would be extremely costly, 
replacement and reconstruction is being accomplished as 
rapidly as funds are made available for the purpose. Construction 
of lock and dam replacement program was 
initiated in fiscal year 1955. New Cumberland, Pike 
Island, Hannibal, Willow Island, Belleville, Racine, 
Greenup, Captain Anthony Meldahl, Markland, 
McAlpine, Cannelton, Newburgh, Uniontown, and 
Smithland replacement locks and dams are in operation, 
replacing 39 old low-lift locks and dams. For total cost of 
existing project, see Table 22-H. 
Terminal facilities. Modern public terminals, with 
warehouses, equipped with operating machinery for 
transferring materials, have been constructed by private 
interests at some of the larger cities and towns. A list of 
terminals on Ohio River is revised annually and can be 
obtained from Division Engineer, U.S. Army Engineer 
Division, Ohio River, Cincinnati, Ohio. 
Operations during fiscal year. New work by contract 
and hired labor: 
Emsworth Locks and Dam (Rehabilitation): Upper lock 
miter gates, 110-foot chamber, were installed by hired 
labor in October 1981. Contract for Locks and Dams 
Rehabilitation, awarded October 15, 1981, was completed 
on November 9, 1984. Dam work included: placing stone 
erosion protection downstream of both back channel and 
main channel, structurally rehabilitating all 14 dam 
gates, painting of the service bridge on main channel dam 
and painting dam gates on the back channel. Lock work 
included: rehabilitation of the river chamber and land 
chamber including all lock machinery. Contract for 
modernizing electrical system of main and back channel 
dams, awarded August 6, 1984 for $1,543,000 is 99 percent 
complete. Contract for shotcrete repairs consisting 
of placing shotcrete coating, repairing damaged areas 
with reinforced shotcrete and repairing monolith joints 
on the lock walls with reinforced shotcrete, awarded on 
February 28, 1985, for $377,830 was completed on 
August 9, 1985. Contract for miscellaneous painting and 
sealing concrete surfaces, awarded April 17, 1985 for 
$289,270 is 99 percent complete. Expenditures during FY 
1986 for real estate acquisition and coordination, construction, 
and engineering and design of remaining project 
was $1,170,291. 
Montgomery Locks and Dam (Rehabilitation): Contracts 
completed include: Fabrication of lock miter gates, 
110-foot chamber for $1,049,132; upper guard wall cells 
for $856,468; emergency dam bulkheads for $329,631; 
fabrication of 56-foot lock miter gates for $344,519. Contract 
for installation of 56-foot lock miter gates and major 
rehabilitation of locks and dam, awarded on July 29, 
1985 for $22,193,960 is 42 percent complete. Installation 
of 110-foot lock miter gates completed by hired labor. 
22-2

OHIO RIVER 
Overall scheduled completion date is March 1989. Expenditures 
during FY 1986 for real estate coordination, construction, 
engineering and design of remaining project 
was $10,698,581. 
Willow Island Locks and Dam: Construction was initiated 
in January 1967. All work is complete. 
Belleville Locks and Dam: Construction was initiated 
in May 1962. All work is complete. 
Racine Locks and Dam: Construction initiated in June 
1964 is complete. 
Gallipolis Lock and Dam: The existing project, constructed 
under project for improving lower Kanawha 
River, was placed in operation in August 1937. The 
dimensions of the existing locks chambers and poor approach 
conditions, particularly to downstream traffic, 
have created a higher than normal accident rate to the 
structure with corresponding hazards and delays to traffic. 
The Water Resources Development Act of 1976 
authorized Phase I studies for a single 1200-foot lock in 
a bypass canal. These studies are complete. 
Initial construction, General funds for the continuation 
of Engineering activities were received in September 
1985. During the fiscal year real estate acquisition, planning 
and preparation of plans and specifications for the 
initial construction contract continued. The total 
estimated cost of the project is $353,000,000, which is 50 
percent federal cost and 50 percent inland waterways 
trust fund cost. 
Greenup Locks and Dam: Construction was initiated in 
October 1954. All work is complete. 
Captain Anthony Meldahl Locks and Dam: Construction 
work complete. 
Markland Locks and Dam: Project is complete including 
a public highway bridge across the navigation structure, 
as authorized by the Federal-Aid Highway Act of 1970 
(Public Law 91-606). For details of bridge see page 22-3 
of Annual Report for 1978. 
Fall of the Ohio National Wildlife Conservation Area 
was authorized by Public Law 97-137 on December 29, 
1981. The Conservation Area will protect 1,000 acres 
which consists of birdlife and other wildlife. Planning, initiated 
in September 1983, was continued. Master Plan 
and Real Estate Design Memorandum is complete. 
$10,145. 
McAlpine Locks and Dam: Project is complete except 
for alteration of lift section of railroad bridge that spans 
the upper end of the Louisville and Portland Canal which 
work is presently deferred. 
Cannelton Locks and Dam: Project is complete except 
for continuing action on Declarations of Taking on one 
tract. $13,300. 
Newburgh Locks and Dam: Project is complete except 
for the extended warranty to the centralized remote control 
and surveillance system. $29,561. 
Uniontown Locks and Dam: Project is complete except 
for continuing action on Declarations of Taking on one 
tract. $26,922. 
Smithland Locks and Dam: All major construction 
features are complete and the project was advanced to 99 
percent completion. Land acquisition is complete except 
for outstanding condemnation actions and acquisition of 
one recreation site. Final payment on the completed dam 
contract has not been made pending settlement of contractor's 
claim. One relocation contract for electric lines 
is being delayed for rights-of-way problems. 
Alteration to Rosiclare, IL drainage and water structures 
was completed. A contract for additional work on 
the Tainter Gates was completed. The construction of the 
Service Building addition was completed. Contracts for 
construction of recreation sites at Lock and Dam 50, KY 
and Dyer Creek, KY were completed. A contract for a 
recreational site at Blackburn, KY, Site 8 was advanced 
to 97 percent completion. Three contracts for recreation 
sites at Birdsville, KY, Site 2; Lusk Creek, IL, Site 4; and 
Caseyville, KY, Site 8A were awarded in October 1985, 
October 1985 and July 1986 respectively, and were advanced 
to 93 percent, 68 percent and 2 percent completion, 
respectively. Contracts for Demolition of Existing 
Buildings at Lock and Dam 50 and Paving over same 
were awarded in May 1986 and August 1986 and were 
advanced to 100 percent and 38 percent completion, 
respectively. Engineering and Design of remaining project 
features was continued: $2,308,886. 
Locks and Dam No. 52 (New Lock): Construction initiated 
in December 1967 is complete. 
Locks and Dam No. 53 (Temporary Lock): Construction 
initiated in December 1972 is complete. 
Locks and Dam No. 52 (Rehabilitation): Project is 97 
percent complete. Contract for storage building was completed. 
Contract to restore dam pier No. 1 and lock structures 
was completed. A contract to repair the beartrap 
piers and dam sill was awarded in July 1985 and advanced 
to 67 percent completion. A contract to repair miter 
gates and piston was advanced to 96 percent completion. 
Engineering and design of remaining project features was 
continued: $312,305. 
Locks and Dam No. 53 (Rehabilitation): Project is 90 
percent complete. A contract to reinforce and grout beartrap 
piers and install piston rods was awarded in August 
1985 and advanced to 91 percent completion. A contract 
to construct a stone dike was awarded in August 1986 and 
advanced to 79 percent completion: $389,988. 
Operation and maintenance, general. Locks and dams 
operated as required and necessary repairs and improvements 
made thereto and to operator's quarters, 
grounds and esplanades. Cost were $10,223,326 for Pittsburgh 
District, $11,429,459 for Huntington District and 
$11,152,024 for Louisville District. 
Dashields Locks and Dam (Rehabilitation): Feature 
Design Memorandum for Major Rehabilitation of 
Dashields Locks and Dam was completed on September 
17, 1985. Contracts awarded includes: Installation of 
mooring cells, May 29, 1986, for $474,320, and riverbed 
exploration, September 23, 1986, for $83,440. Expenditures 
during FY 1986 for construction and engineering 
and design for rehabilitation project was $1,166,000. 
22-3

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
2. OPEN CHANNEL WORK, OHIO RIVER 
Location. Under jurisdiction of district engineer in 
whose district the work is located. Portion of river included 
in project extends 974.7 miles from head of river at 
Pittsburgh, PA, to mouth of Cache River (Mound City, 
IL). Open channel improvement from mouth of Cache 
River to mouth of Ohio River is under jurisdiction of 
Mississippi River Commission. 
Existing projects. Before completion of canalization 
project, no project depth had been fixed by Congress under 
project for open channel work, but in order to properly 
aid packet and barge navigation it was necessary to 
secure a low-water channel with a minimum depth of 
4 to 6 feet, and a width, depending upon difficulty 
of running channel, of 400-600 feet; also to permit 
movemment of large coal tows, which movement occurred 
at stages of water exceeding 10 feet, it was necessary 
to remove points of projecting bars which formed at 
various locations along river. Accomplishment of this purpose 
involved concentration of current by closing back 
channels at islands with low dams, contraction and 
straightening wide open channels by low dikes, dredging 
bars and shoals, and removal of snags and wrecks. 
Incidental to direct improvement of Ohio River is construction 
and maintenance of ice piers as required for protection 
of river craft. Stage of extreme high water on Ohio 
River varies from 46 feet at Pittsburgh, Pa., to 80 feet 
at Cincinnati, Ohio, with 57.2 feet at Louisville, Ky. (head 
of falls), 53.8 feet at Evansville, Ind., and 59.5 feet at 
Cairo, Ill. (mouth of river). Estimated cost of new work 
(1960) is $16,160,000, exclusive of following items which 
are considered inactive: Ice piers authorized by 1927 River 
and Harbor Act; reforestation of sloughs on Kentucky 
Peninsula near Evansville, Ind., authorized by 1930 River 
and Harbor Act; dredging to widen channel at certain 
points; and placing revetment at various points. 
Estimated cost of these items (1954) is $6,565,000. Operation 
of snag boats on Ohio River below Pennsylvania 
State line was included in project July 1, 1935, under provisions 
of Permanent Appropriations Repeal Act of 
June 26, 1934. See Table 22-B for authorizing legislation. 
New work under this project is substantially complete, 
since it is not anticipated that work on inactive portion 
of project will be accomplished. In addition to dredging, 
local stabilization of channel has been effected at various 
points by construction of dikes and revetment. Work 
which remains consists of dredging to widen channels at 
certain points to project depth. 
Local cooperation. River and Harbor Act of 
January 21, 1927 authorizing construction of ice piers for 
general open channel work, imposes condition that before 
work is begun on any pier, local interests convey to the 
United States free of cost such riparian rights as may be 
deemed necessary in connection with the improvements 
at locality (H. Doc. 187, 67th Congr., 2nd sess.). Existing 
ice piers are adequate for present purposes and local 
cooperation is not needed since no additional construction 
is under consideration. River and Harbor Act of July 3, 
1930, provides for reforestation of sloughs of Kentucky 
Peninsula and bank protection and that no expense shall 
be incurred by the United States for acquiring lands 
required for purpose of this improvement (H. Doc. 409, 
69th Cong. 1st sess.). However, since no serious overbank 
erosion has occurred since bank revetment in 1933-34, 
reforestation is not considered justifiable at this time and 
no local cooperation is required. 
Operations during fiscal year. Operation and 
maintenance, general: Dredging was done where required 
to provide an adequate and dependable channel of project 
depth at minimum pool conditions. Dikes and 
revetments were maintained and routine work of maintaining 
navigation aids, removing snags, making channel 
studies, hydrographic surveys and mapping was performed 
as required. Channel soundings, hydrographic surveys, 
stream gaging operations, channel inspections and aids 
to navigation, and miscellaneous inspections and reports 
cost $899,331. There was no dredging by hired labor on 
the Ohio River in FY 86. Dredging by contract: Pittsburgh 
District - Contract in the amount of $483,721 was awarded 
on February 1, 1985 for approximately 171,100 cubic 
yards of dredging Dashields Pool, Neville Island Back 
Channel, PA was terminated for convenience to the 
government on March 21, 1986. Huntington District 
597,797 cubic yards at $1,583,851 and Louisville District 
1,007,084 cubic yards at $1,846,378. 
22-4

OHIO RIVER 
TABLE 22-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep 30, 1986 
1. Construction of New Work 
Locks and Dams Approp. $2,350,759 $1,801,200 $1,814,000 $7,065,000 $1,390,719,7721 3 5 o1107 
on Ohio River Cost 4,099,831 2,573,878 2,518,511 6,639,783 1,389,351,7421 3 6 11 12 15 16 18 
Maint. 
Approp. 31,744,300 30,976,373 31,056,817 32,293,874 589,642,8342 4 19 
Cost 30,311,071 30,961,371 33,742,851 32,804,809 589,086,6342 13 14 19 20 
Rehab. 
Approp. 15,897,572 10,189,000 4,605,000 10,151,000 67,515,572 
Cost 17,335,848 7,502,809 6,484,902 12,571,165 66,638,561 
Rehab.(O&M) 
Approp. - - - 1,267,100 1,267,100 
Cost - - - 1,166,100 1,166,100 
2. Open Channel New Work 
Work, Ohio River Approp. - - - - 15,962,2608 
Cost - - - - 15,962,2608 
Maint. 
Approp. 4,440,300 5,265,000 5,029,763 4,508,800 108,617,2267 9 
Cost 5,759,040 4,479,208 5,799,647 4,555,393 108,594,8327 9 
Rehab. 
Approp. - - - - 944,649 
Cost - - - - 944,649 
1 Includes $17,003,761 for previous 6-foot canalization 
project. 
2 Includes $36,943,217 expended from 1885 to 1937 on operation 
and care of work of improvement under provisions of permanent 
indefinite appropriations for such purposes. 
3 Includes $215,812 public works acceleration, executive 
1963. 
4 Includes $38,766 public works acceleration, executive 1963. 
5 Excludes $251,769 contributed funds for new work. 
6 Excludes $250,102 contributed funds for new work. 
' Excludes $1,621,349 expended in operation of snag boats 
under provisions of permanent indefinite appropriation for such 
purposes, and $267 transferred to project without 
reimbursement. 
8 Includes $1,040,236 Public Works funds. 
9 Includes $1,000 for removal of obstructions in Licking River 
under authority of Section 3, R&H Act of 1930. 
to Includes $100,000 placed in FY 1971 Budget Reserve. 
11 Excludes $3,899 transferred from project without 
reimbursement. 
12 Surplus property valued at $3,553 transferred to project 
without reimbursement. 
13 Excludes $2,140 transferred to project without 
reimbursement. 
14 Excludes surplus property valued at $73,832 transferred 
to project without reimbursement. 
15 Includes $87,724,158 prior construction cost. 
16 Excludes surplus property valued at $297,385 transferred 
to project without reimbursement. 
17 Includes $549,392 Code 710 Funds, $572,162 Code 711 
Funds, $532,677 Code 712 Funds and $1,759,812 Code 713 
Funds. 
18 Includes $549,392 Code 710 Funds, $342,162 Code 711 
Funds, $532,677 Code 712 Funds and $1,989,812 Code 713 
Funds. 
19 Includes $2,158,073 Funds provided from The Productive 
Employment Appropriations Act of 1983 (PL 98-8). 
20 Includes $920,945 cost for operations and care of previous 
projects. 
22-5

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
TABLE 22-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
2. Open Channel Work, Ohio River 
March 3, 1827 Project adopted by this act originally covered entire 
length of Ohio River from its mouth near Cairo to 
Pittsburgh, a distance of 981 miles. It provided for 
removal of all obstructions which tend to endanger 
steamboat navigation. 
January 21, 1927 Construct ice piers as a part of project, with funds H. Doc. 187, 67th Cong., 2nd sess. 
allotted from appropriations for general open 
channel work. 
July 3, 1930 Reforestation of sloughs on Kentucky Peninsula near H. Doc., 409, 69th Cong., 1st sess. 
Evansville, Ind., and a 200-foot strip along bank 
and for bank protection, at an estimated cost of 
$200,000. 
July 3, 1958 Act of March 3, 1827 modified to include maintenance H. Doc., 434, 84th Cong., 2nd sess. 
of existing Licking River Channel within lower 
3-mile limit of River slack water, at an estimated 
increase of $1,000 in cost of average annual 
maintenance. 
Locks and Dams, Ohio River 
December 29, 1981 Act of December 29, 1981 established the 1,000 H.R. 2241, PL 97-137, Title II, 
acre Falls of the Ohio National Wildlife Conser- 95 Stat. 1710 
vation Area, at a cost not to exceed $300,000. 
CONSTRUCTION OF LOCKS AND DAMS ON OHIO RIVER 
TOTAL COST OF EXISTING PROJECT TO SEPTEMBER 30, 1986 
TABLE 22-H (See Section 1 of Text) 
Operations and 
Maintenance 
Funds New Work General Rehabilitation Total 
Regular 1,296,954,567 548,124,917 67,804,661 1,912,884,145 
Public Works 3,258,368 0 0 3,258,368 
Emergency Relief 1,198,837 19,000 - 1,217,837 
Maintenance & Operation - 3,039,789 - 3,039,789 
Public Works Acceleration 215,812 38,766 - 254,578 
Executive 1963 
Total 1,301,627,5843 551,222,4721 2 67,804,661 1,920,654,717 
1 Excludes $36,943,217 expended from 1885 to 1937 under 4 Includes $1,166,100 cost for O&M Rehabilitation. 
permanent indefinite appropriation. 
2 Excludes $920,945 cost for operation and care of previous Note: All other cost variations are listed in the Footnotes 
projects. of Table 22-A. 
3 Excludes $87,724,158 prior construction cost. 
FEDERAL ENERGY REGULATORY COMMISSION LICENSES 
TABLE 22-I AT LOCKS AND DAMS, OHIO RIVER 
Markland Dam McAlpine Dam Racine Dam Greenup Dam 
F.E.R.C. License 2,211 289:1,000 2,570 2,614 
License Public Service Co. Louisville Gas and Ohio Power Co. City of Vanceburg, 
of Indiana Electric Co. Kentucky 
Annual Charge $45,950.00 $95,000.00 $50,000.00 $227,900.00 
Collections to end of 
Fiscal Year 1986 $825,211.64 . $7,400,893.16 $285,673.00 $991,369.00 
22-6

TABLE 224J OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool 
Length Elevation Depth on 
Width Available (feet, Miter Sills Actual Cost 
Lock Miles of For Full mean Year to Date of 
and Below Distance From Chamber Width Lift sea Upper Lower Character of Foundation Percent Opened to Each Lock 
Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 
1 - Replaced 
6.2 Emsworth Locks and Dam, 
Emsworth, PA 
2 - Replaced 
3 - Replaced 
13.3 Dashields Locks and Dam 
1.6 miles below 
Sewickley, PA 
4 - Replaced 
5 - Replaced 
6 - Replaced 
31.7 Montgomery Locks and Dam, 
1.4 miles above 
Industry, PA 
7 - Replaced 
8 - Replaced 
54.4 New Cumberland Locks and 
Dam, Stratton, OH 
9 - Replaced 
10 - Replaced 
11 - Replaced 
84.3 Pike Island Locks and Dam, 
2 miles upstream from 
Warwood, WV 
12 - Replaced 
13 - Replaced 
14 - Replaced 
126.4 Hannibal Locks and Dam, 
1.6 miles upstream from 
New Martinsville, WV 
15 - Replaced 
16 - Replaced 
161.7 Willow Island Locks and 
Dam, 2.7 miles above 
Waverly, WV 
110 
56 
600 18.0 710.0 17.0' 4 12.98 Rock Rock and piles 100 
360 15.5' ' 12.9' 
- $ 870,034 
1921 43,218,551 '4 
- 976,767 
- - 1,144,588 
110 600 
56 360 10.0 692.0 13.4' 17.5' Rock 
110 
56 
110 
110 
Rock 100 1929 
600 
360 17.5 682.0 16.0' 14.63 Rock and piles Rock and piles 100 
1,200 
600 20.5 664.5 7.0' 14.83 Rock Rock 100 
110 1,200 
110 600 21.0 644.0 17.0' 18.0' Rock 
110 1,200 
110 600 21.0 623.0 38.0 17.0 
Rock 
4,699,176 '4 .* 
- 1,071,472 
- 1,080,132 
- 1,123,442 
1936 21,970,96214". 
- 1,075,000 
- 1,167,456 
1959 39,099,688 
- 1,177,100 
- 1,138,000 
- 1,162,165 
100 1968 56,623,946 
- - - 1,166,104 
- - - 1,222,389 
- - - 1,133,371 
Rock Rock 
110 1,200 
110 600 20.0 602.0 35.0 15.0 Rock and piles Rock 
99 1972 87,648,953 
- - - 1,180,478 
- - - 1,275,532 
100 1972 76,520,876 
I

TABLE 224 
(Continued) 
OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool 
Length Elevation Depth on 
Width Available (feet, Miter Sills Actual Cost 
Lock Miles of For Full mean Year to Date of 
and Below Distance From Chamber Width Lift sea Upper Lower Character of Foundation Percent Opened to Each Lock 
Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 
- Replaced 
- Replaced 
- Replaced 
- Replaced 
103.9 Belleville Locks and Dam, 
0.3 mile below 
Reedsville, OH 
- Replaced 
- Replaced 
- Replaced 
237.5 Racine Locks and Dam, 
1.5 miles below 
Letart Falls, OH 
- Replaced 
- Replaced 
- Replaced 
279.2 Gallipolis Locks and Dam, 
0.7 mile below 
Hogsett, WV 
Gallipolis Modernization 
- Replaced 
- Replaced 
- Replaced 
- Replaced 
341.0 Greenup Locks and Dam, 
4.9 miles below 
Greenup, KY 
- Replaced 
- Replaced 
- Replaced 
- Replaced 
436.2 Captain Anthony Meldahl 
Locks and Dam, 2.2 miles 
above Foster, KY 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
1,200 
600 22.0 582.0 37.0 15.0' Rock and piles Rock 
1,200 
600 22.0 560.0 18.0 15.0 Rock and piles Rock 
600 
360 26.0 538.0 18.0 12.0 Rock Rock 
1,200 
600 30.0 515.0 18.0' 13.0 Rock Rock 
1,200 
600 30.0 485.0 18.0' 15.0 Rock Rock 
- - $ 1,362,591 
- - 927,091 
- - 1,213,848 
- - 936,696 
100 1968 62,591,255 
- - 1,484,562 
- - 1,218,798 
- - 1,851,488 
98 1971 64,922,680 
- - 1,187,542 
- - 1,925,205 
- - 1,307,241 
100 19376 
5,687,433 
- - 2,015,601 
- - 1,063,133 
- - 1,088,802 
- - 1,579,618 
17 
18 
19 
20 
21 
22 
b 23 
24 
25 
26 
27 
28 
29 
30 
31 
32 
33 
34 
100 1962 
57,464,191 
1,359,231 
2,951,216 
1,937,166 
3,437,057 
74,188,216 
100 1959 
0
0
y
0
LTi 
z
z

TABLE 22-J 
(Continued) 
OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool 
Length Elevation Depth on 
Width Available (feet, Miter Sills Actual Cost 
Lock Miles of For Full mean Year to Date of 
and Below Distance From Chamber Width Lift sea Upper Lower Character of Foundation Percent Opened to Each Lock 
Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Locik Dam Complete Navigation and Dam 
35 - Replaced 
36 - Replaced 
37 - Replaced 
38 - Replaced 
531.5 Markland Locks and Dam, 
1 mile above Markland, IN 
39 - Replaced 
40 - Eliminated 
41 -- 
Falls of the Ohio, 1 mile 
above McAlpine 
604.0 McAlpine Locks and Dam 
(Reconstruction of Locks 
and Dam 41) 
42 - Eliminated 
43 - Replaced 
44 - Replaced 
45 - Replaced 
720.7 Cannelton Locks and Dam 
3 miles above 
Cannelton, IN 
46 - Replaced 
776.1 Newburgh Locks and Dam, 
16 miles above 
Evansville, IN 
47 - Replaced 
48 - Replaced 
49 - Replaced 
846.0 Uniontown Locks and Dam, 
3.5 miles below 
Uniontown, KY 
50 - Replaced 
51 - Replaced 
918.5 Smithland Locks and Dam, 
2 miles above 
Smithland, KY 
110 
110 
N/A 
110 
110 
56 
110 
110 
110 
110 
1,200 
600 35.0 455.0 50.0 15.0 
N/A N/A N/A N/A N/A 
1,200 49.0 12.0 
600 37.0 420.0 19.0 11.0 
360 19.0 11.0 
1,200 25.0 383.0 38.0 13.0 
600 
1,200 
600 16.0 358.0 32.0 16.0 
110 1,200 
110 600 22.0 342.0 34.0 12.0 
110 1,200 
110 1,200 22.0 324.0 34.0 12.0 
Rock 
N/A 
Rock 
Rock 
Rock 
Piles 
N/A 
Rock 
Rock 
100 
0 
1963 
N/A 
$ 1,894,942 
3,704,535 
1,297,924 
2,857,040 
63,019,403 
2,222,448 
7,658,134' 
270,309 
1008 1961 45,726,189' 
99 1972 
2,592,242 
2,819,930 
3,202,890 
96,760,58810 
- - 3,129,028 
Pile 99 1975 104,478,082 
4,415,526 
3,062,710 
3,325,964 
Rock 
Rock 
Rock 99 1975 100,295,061 
- - - 3,751,762 
- - - 4,370,566 
Rock 95 1980 272,411,332

TABLE 22-J 
(Continued) 
OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool 
Length Elevation Depth on 
Width Available (feet, Miter Sills Actual Cost 
Lock Miles of For Full mean Year to Date of 
and Below Distance From Chamber Width Lift sea Upper Lower Character of Foundation Percent Opened to Each Lock 
Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 
52 938.9 1.4 miles below Brookport, IL 110 600 12.0 302.0 15.4 11.0 Pile Pile 100 1928 13,205,066" 
938.9 1.4 miles below Brookport, I1 110 1,200 12.0 302.0 15.4 11.0 Pile Pile 100 1969 10,197,516 
(New lock) 
53 962.6 10.8 miles above 110 600 13.4 290.0 15.4 9.6' Pile Pile 100 1929 9,715,7732 
Mound City, IL 
962.6 10.8 miles above 110 1,200 13.4 290.0 15.4 9.6 Pile - 100 1982 38,570,920 
Mound City, IL (New lock) 
974.2 Mound City Lock and Dam - - - - - - - - - -1,539,470 
1 mile below Mound City, IL 
TOTAL $1,447,942,193" 
' Depths are on emergency dam foundation and are controlling depths. 
4 Change from fixed dam to lift-gate dam completed in 1938. 
3 Depths are on poiree dam foundation and are controlling depths. 
Land chamber. 
S River chamber. 
SRoller-gate dam. Cost not included in total. Constructed under project for 
improving lower Kanawha River. 
' Lock and Dam 41 completed with 110- by 600-foot lock in 1921. Completed 
with new dam and raised canal and lock wall in 1928. Auxiliary 56- by 360-foot 
lock constructed in 1929-30. Reconstruction and modernization began 1956, 
renamed McAlpine Locks and Dam in 1960. Operation of auxiliary lock 
suspended in 1971. 
e Completed except for deferred alteration of railroad bridge. 
9 Dam below not yet constructed. Depth on lower miter sill at lower water. 
,1 Reflects reduction of $2,219,975 payment for settlement of damage to dam 
caused by barge accident in April 1978. 
" Includes $8,743,319 for major rehabilitation project initiated in FY 1979. 
12 Includes $4,305,105 for major rehabilitation project initiated in FY 1979. 
13 For preconstruction planning 1965 to 1972. No longer considered authorized. 
See Section 1 of text. 
"1 Includes $37,356,786 for major rehabilitation initiated in FY 1980. 
14* Includes $16,233,351 for major rehabilitation initiated in FY 1983. 
"**Includes $1,166,100 for major rehabilitation initiated in FY 1986 
(O&M funds). 
' Exclusive of $6,994,235 details below. 
Additional Features Entering into Cost of Project 
Louisville and Portland Canal and Indiana chute $ 5,359,203 
(under previous project) 
Examinations, survey contingencies, plants and miscellaneous 966,232 
Recreation facilities, pool area, Gallipolis Locks and Dam 668,800 
TOTAL 
GRAND TOTAL 
6,994,235 
$1,457,156,403 
C0 
tI
O
ym 
O
y
x
x

NASHVILLE, TN, DISTRICT * 
This district comprises portions of southern Kentucky, 
southwestern Virginia, western North Carolina, 
northern Georgia and Alabama, northeastern 
Mississippi and practically all of Tennessee except 
western portion, and embraces drainage basins of 
Tennessee and Cumberland Rivers and their tributaries. 
IMPROVEMENTS 
Page General Investigations 
1. Cumberland River, TN and KY ........ 23-2 
2. Tennessee River, TN, AL and KY ...... 23-3 
3. Tennessee-Tombigbee Waterway, AL 
and MS ........................... 23-4 
4. Navigation Work Under Special 
Authorization ...................... 23-4 
Alteration of Bridges 
5. Authorized Alteration of Bridges ...... 23-4 
Flood Control 
6. Big South Fork National River and 
Recreation Area, KY and TN .......... 23-4 
7. Martins Fork Lake, KY .............. 23-5 
8. Middlesboro, Cumberland River 
Basin, KY ......................... 23-5 
9. Tug and Levisa Forks of the Big Sandy 
River and Cumberland River, W VA, 
VA and KY ......................... 23-5 
10. Ohio River Basin (Nashville Dist.) .... 23-6 
11. Inspection of completed flood 
control projects .................... 23-6 
12. Flood control work under special 
authorization ....................... 23-6 
Multiple-Purpose Projects, Including Power 
13. Center Hill Lake, Ohio River 
Basin, TN .......................... 23-6 
14. Dale Hollow Lake, Ohio River Basin, 
TN and KY ........................ 23-7 
15. J. Percy Priest Dam and Reservoir, 
Ohio River Basin, TN ................ 23-7 
16. Laurel River Lake, Ohio River 
Basin, KY ......................... 23-7 
17. Wolf Creek Dam-Lake Cumberland, 
Ohio River Basin, KY ................ 23-8 
18. Surveys ............................ 23-8 
19. Collection and study of basic data ...... 23-8 
Tables 
Table 23-A Cost & Financial Statement ..... 23-9 
Table 23-B Authorizing Legislation ........ 23-11 
Table 23-C Other Authorized Navigation 
Projects ..................... 23-13 
Table 23-D Not Applicable 
Table 23-E 
Table 23-F 
Other Authorized Flood Control 
Projects ..................... 23-13 
Other Authorized Multiple- 
Purpose Projects, Including 
Power ...................... 23-14 
Table 23-G Deauthorized Projects .......... 23-14 
Table 23-H Cumberland River, TN & KY, 
Principle Features ............. 23-15 
Table 23-I Tennessee River Lock 
Dimensions ................... 23-17 
Table 23-J 
Table 23-K 
Tennessee River Total Cost of 
Existing Project ............... 23-18 
Ohio River Basin (Nashville 
District) Local Protection ...... 23-18 
Table 23-L Reservoirs .................... 23-18 
Table 23-M Inspection of Completed Flood 
Control Projects ............... 23-19 
Table 23-N Flood Control Work Under 
Special Authorization .......... 23-19 
23-1 
Navigation Page

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. CUMBERLAND RIVER, TN AND KY 
Location. Formed by junction of Poor and Clover 
Forks in Harlan County, Ky., about 694.2 miles above 
its mouth, and flows west to Burnside, Ky., from 
whence it makes a loop southwestward into Tennessee, 
passes Nashville, and returns northwestward to 
Kentucky, emptying into Ohio River near Smithland, 
Ky. (See Geological Survey base maps of Tennessee 
and Kentucky.) 
Previous projects. For details see pages 1898 and 
1901 of Annual Report for 1915, and page 1208 of 
Annual Report for 1938, and pages 1069 and 1070 of 
Annual Report for 1962. 
Existing project. Below Nashville: Improvement of 
Cumberland River between mouth and Nashville was 
authorized for 9-foot navigation; increased project 
depth to be obtained by construction of three moderate 
height dams with lockage facilities, designated as 
Kuttawa (Eureka), Dover, and Cheatham, to replace 
existing locks A to F inclusive below Nashville and 
lock 1 above Nashville. (See table 23-B for authorizing 
legislation.) Subsequent authorities provided for 
construction of hydroelectric power-generating facilities 
at Cheatham Dam, river mile 148.7, and modification 
of project for navigation on Cumberland River, 
Tenn. and Ky., to provide, in lieu of previously authorized 
works at Kuttawa, mile 32.2, and Dover, mile 
100.1, for construction of a multiple-purpose improvement 
consisting of a dam, lock, and powerplant near 
mile 30.6 on lower Cumberland River and a canal for 
navigation and other purposes connecting this reservoir 
with reservoir formed by Kentucky Dam on the 
Tennessee River. The project is known as Barkley 
Dam and Lake Barkley. Provision of interconnecting 
canal, involving excavation of a channel through narrow 
watershed divide about 2.5 miles upstream from 
damsite, permits alternative routes available for navigation 
between either Cumberland or Tennessee 
Rivers and Ohio River, and affords integrated operation 
of Barkley and Kentucky Reservoirs through 
diversion of flows in interests of flood control and 
power production. Estimated cost of modified project 
for 9-foot navigation and multiple-purpose development 
is $178,100,000 Federal funds and $102,966 non- 
Federal funds for recreation facilities under the 
completed projects program (October 1986). (See 
table 23-H for listing of principal features.) 
Under flood conditions as regulated by upstream 
reservoirs, extreme fluctuation in stage of river below 
Nashville, Tenn., varies at different localities from 
about 16 to 55 feet above minimum pool levels. Ordinary 
fluctuations vary with power flows from as 
much as the allowable 3-foot drawdown below normal 
pool elevation 385 at Cheatham Lock and Dam to a 
range of about 7 feet at Nashville. Seasonal variation 
in normal headwater levels at Lake Barkley is 5 feet, 
which in combination with power flows produces 
fluctuations up to 10 feet below Cheatham Lock and 
Dam. 
Above Nashville: See pages 1693 thru 1696 of 
Annual Report for 1950 for information including 
statistical data on locks and dams 1 to 17 and 21. 
Completion information is shown on pages 1454 of the 
report for 1951. See Table 23-B for Authorizing Legislation. 
Construction of Old Hickory, Carthage, and 
Celina Dams above Nashville was also authorized for 
navigation and power. The dam and reservoir authorized 
for construction on Cumberland River near 
Carthage, Tenn., has been redesignated as Cordell 
Hull Dam and Reservoir. Cost of Old Hickory and 
Cordell Hull projects, including locks, is $132,140,904. 
Estimated cost of Celina Dam (1985) is $213,000,000. 
(See table 23-H at end of chapter for listing of principal 
features.) 
Under flood conditions as presently regulated, including 
effect of surcharge operation of Old Hickory 
project, extreme fluctuations of stage in this section 
of river vary from a range of 35 feet at Nashville 
(mile 191) to a maximum of 46 feet immediately below 
Old Hickory Dam (mile 216.2), and from an 
8-foot variation in headwater at dam to 36 feet in 
vicinity of Carthage, Tenn., (mile 313.5), present 
head of navigation; with variations up to 35 feet at 
Celina, Tenn. (mile 380.8) and 29 feet in tailwater at 
Wolf Creek Dam (mile 460.9). Maximum fluctuations 
under ordinary conditions from power flows vary 
from about 7 feet at Nashville to 14 and 3 feet, respectively, 
in tailwater and headwater of Old Hickory 
Dam, and at other key points as follows: 13 feet at 
Carthage; 18 feet at Celina; and 19 feet at Wolf Creek 
Dam. 
Further details on project authorization for river 
sections below and above Nashville are shown on 
Table 23-B. 
Local cooperation. Under modified project for 9- 
foot navigation and multiple-purpose development, 
recreation features of reservoir components are subject 
to certain conditions of non-Federal cost-sharing 
under Federal Water Project Recreation Act of 1965. 
Terminal facilities. There are 44 terminals on the 
Cumberland River (3 municipally owned and open for 
public use; 3 government owned facilities and 35 privately 
owned facilities). A total of 23 terminals have 
23-2

NASHVILLE, TN, DISTRICT 
railroad connections. Principal commodities handled 
are petroleum products, stone, sand, gravel, coal, coke, 
iron, steel, chemicals, and grain. Facilities considered 
adequate for existing commerce. For further information 
see page 695 of Annual Report for 1969. 
Operations during fiscal year. New work: Below 
Nashville: Recreation facilities provided at Cheatham 
project under (Code 713) cost $538. 
Maintenance: Barkley, Cheatham, Cordell Hull, and 
Old Hickory locks and dams were operated as required. 
Operation and Maintenance improvements at 
Barkley included dredging at Eddy Creek Bend and 
completion of paving at Bumpus Mills, Eddyville and 
Coleman Bridge Recreation Areas, and painting at 
the Lock and Dam. A new lock lighting system was 
installed at Cheatham and dredging below Old Hickory 
continued. Painting of the spillway gates at 
Cordell Hull was completed, and a new utility system 
and paving was accomplished at the Nashville Repair 
Station, Old Hickory Lock and Dam. 
Total net energy generated at Barkley Dam 
(478,334,092 kw-hr) was made available through Department 
of the Interior to the Tennessee Valley Authority, 
Southern Illinois power Cooperative, Big 
Rivers Rural Electric Cooperative Corporation, and 
Indiana Statewide Rural Electric Cooperative, Inc., 
Hoosier Energy Division. Total net energy generated 
at Cheatham Dam (151,861,360 kw-hr), Cordell Hull 
(244,190,849 kw-hr), and Old Hickory (332,521,980 
kw-hr) was made available for distribution. Activities 
under reservoir management program comprising 
malaria control, shoreline sanitation, land management 
and disposal, and maintenance of public-use facilities 
continued. 
2. TENNESSEE RIVER, TN, AL AND KY 
Location. Formed by junction of French Broad and 
Holston Rivers in eastern Tennessee, 4.4 miles above 
Gay Street Bridge at Knoxville, flows southwest into 
northern Alabama, thence in a generally westerly 
course across north Alabama, to northeast boundary 
of Mississippi, thence nearly due north across Tennessee 
and Kentucky, entering Ohio River at Paducah, 
652.1 miles from junction of French Broad and Holston 
Rivers. (See Geological survey base map of Tennessee 
River Basin.) 
Previous projects. For details see pages 1902-1906, 
Annual Report for 1915; pages 1190-1194, 1196-1216, 
and 1220-1222, Annual Report for 1929; and page 
1216, Annual Report for 1938. 
Existing project. Originally provided for permanent 
improvement of river for a navigable depth of 9 feet 
at low water from mouth about 650 miles to Knoxville, 
Tenn. Only work performed by the Corps was construction 
of lock at General Joe Wheeler Dam and 
miscellaneous appurtenant improvements at a new 
work cost of $2,244,236. Tennessee Valley Authority 
program provided for obtaining authorized 9-foot 
project by construction of high dams and locks and 
utilization of certain locks and dams previously constructed 
under jurisdiction of the Corps. (See Table 
23-B for Authorizing Legislation.) Subsequent construction 
by that agency of Melton Hill Dam extends 
navigable channel of Tennessee River system up the 
Clinch River about 38 miles above damsite (mile 23.1) 
to vicinity of Clinton, Tenn. (See table 23-I on Tennessee 
River.) 
In accordance with general navigation laws placing 
control and supervision over navigable waters under 
direction of Secretary of the Army, the Corps of 
Engineers operates and maintains all locks, and maintains 
navigation channels and safety harbors by performing 
all necessary maintenance dredging and 
snagging operations. For information concerning 
other functions of the Corps under division of responsibilities 
for Tennessee River since adoption of Tennessee 
Valley Authority Act of 1933, see page 1084 of 
Annual Report for 1962. 
Local cooperation. Authorization requires no local 
cooperation in construction of alternate system of low 
dams. It does, however, provide that if high dams are 
built before the United States builds projected locks 
and low dams which are to be replaced, the United 
States shall contribute to cost of substituted structures 
an amount equal to estimated cost of works of 
navigation for which substitution is made. 
Terminal facilities. There are 154 terminals on the 
Tennessee River (7 municipally owned, 17 government 
owned facilities and 130 privately owned facilities). 
A total of 78 terminals have railroad connections. 
Principal commodities handled are petroleum products, 
stone, sand, gravel, coal, coke, grain, chemicals, 
iron, and steel. Facilities considered adequate for 
existing commerce. A list of terminals is revised annually 
and can be obtained from Division Engineer, 
Ohio River Division, Corps of Engineers, Cincinnati, 
Ohio. For further information see page 698 of Annual 
Report for 1969. 
Operations during fiscal year. Channel work by government 
plant and hired labor consisted of dredging 
and snagging at various locations, and maintenance 
of mooring facilities and safety harbors. Cost of channel 
maintenance was $266,435. Maintenance: All locks 
were operated and lock appurtenances and standby 
plant maintained as required. Major repairs were 
23-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
made to Kentucky Lock and Pickwick Auxiliary Lock. 
In addition other major maintenance items were completed 
including construction of new shop buildings 
at Kentucky Lock and Nickajack and painting at 
various sites. See table 23-J for total cost of existing 
project to September 30, 1986. 
3. TENNESSEE-TOMBIGBEE 
WATERWAY, AL AND MS 
Location. West Central Alabama and Northeastern 
Mississippi; in Marengo, Sumter, Greene and Pickens 
Counties, Alabama, and Noxubee, Lowndes, Clay, 
Monroe, Itawamba, Prentiss and Tishomingo Counties, 
Mississippi. 
Existing project. Provides for a waterway 234 miles 
in length, connecting the Tombigbee and Tennessee 
Rivers by way of the East Fork of Tombigbee River, 
Mackeys and Yellow Creeks, affording a channel not 
less than 9 feet deep and 280 feet in bottom width, 
with 10 locks each having clear chamber dimensions 
of 110x600 feet. Construction of the divide section, 
including Bay Springs lock and dam, is assigned to 
the Nashville District; whereas, the prosecution of 
work on the river and canal sections is under the jurisdiction 
of the Mobile District. Only activities of the 
Nashville District are reported hereon. Estimated 
Federal cost of new work under jurisdiction of the 
Nashville District is $749,000,000. (See 23-B for authorizing 
legislation.) 
Local cooperation. Authorization requires local interests 
to construct, maintain and operate all highway 
bridges, construct and maintain all highway relocations 
or alterations, make and maintain alterations as 
required to sewer, water supply and drainage facilities, 
assume cost of operation and maintenance of 
utility crossings, provide and maintain as required 
suitable and adequate river and canal terminals in 
accordance with plans approved by the Secretary of 
the Army and the Chief of Engineers. 
Operations during fiscal year. Work continued on 
the Resource Management Office, Erosion Control 
and Wildlife Planting. In addition, $5,000,000 was received 
from Corps surplus funds to initiate design 
and construction of deferred recreation. Contracts 
were awarded for Natchez Trace, Piney Grove and 
Crows Neck Sites. In addition a claim was settled on 
the BS L&D contract. The project is 99% complete. 
Navigation features are 100% complete. 
4. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
During the period $104,535 was expended for a 
study of Port of Florence, AL., $43,157 for Tennessee 
River at Calvert City, TN., and $69,908 for Tennessee 
River at Morgan City Port, AL. 
Alteration of Bridges 
5. AUTHORIZED ALTERATION OF 
BRIDGES 
Work on Woodland Street bridge, under Truman- 
Hobbs Act, was initiated in 1965 and completed in 
1966. Costs were $987,632. For details see page 922 of 
Annual Report for 1967. 
Flood Control 
6. BIG SOUTH FORK NATIONAL RIVER 
AND RECREATION AREA, KY AND TN 
Location. The proposed project is located in Northeastern 
Tennessee and Southeastern Kentucky along 
the Big South Fork River and its tributaries in Pickett, 
Scott, Fentress, and Morgan Counties, Tennessee, and 
McCreary County, Kentucky. 
Existing project. A National Recreation Area will 
be established in accordance with the concept included 
in the interagency report prepared pursuant to section 
208 of Flood Control Act of 1968. Total acreage is not 
to exceed 125,000 acres. The act specifically establishes 
the National Area for the purpose of preserving 
and interpreting the scenic, biological, archaeological 
and historical resources of the river gorge area and 
developing the natural recreational potential of the 
area. The area is divided into two categories, gorge 
and adjacent areas, with no construction permitted 
except limited clearing for establishment of day-use 
facilities, historical sites, primitive campgrounds and 
access roads. Lodges and other facilities will be provided 
in the adjacent areas. The project was authorized 
by the Water Resources Development Act of 1974 
as amended by Water Resources Development Act of 
1976. (See table 23-B for authorizing legislation.) The 
present authorized cost (ceiling) for the project is 
23-4

NASHVILLE, TN, DISTRICT 
$103,522,000. The National Park Service will operate 
and maintain the useable units of the area upon completion 
of land acquisition and construction of basic 
facilities by the Corps of Engineers. The first construction 
contract was awarded in June 1981. The 
project is 87% complete. 
Local cooperation. None required. 
Operations during fiscal year. Engineering and design 
continued. Acquired 2,757.81 acres fee. Construction 
continued on the Blue Heron Overlook, Access, 
Recreation and Campground, and the Bandy Creek 
Road and Recreation. In addition, a contract was 
awarded to provide Area Signs for the park. 
7. MARTINS FORK LAKE, KY 
Location. Dam located at mile 15.6 on Martins Fork 
of Clover Fork, Cumberland River, about 10 miles 
southeast of city of Harlan, with reservoir extending 
about 6 miles upstream within Harlan County, southeastern 
Kentucky. 
Existing project. Multiple-purpose improvement 
combining flood control with water quality control 
and recreation development adopted by 1965 Flood 
Control Act (H. Doc. 244, 89th Cong.), in general 
accordance with recommendations. Dam will be concrete 
type, about 504 feet long and rising 97 feet above 
streambed. Outlet works provide for release of water 
from reservoir at varying levels. Drainage area above 
damsite is 55.7 square miles. At full pool level, spillway 
crest at elevation 1341 above mean sea level, 
reservoir will cover 578 acres and contain 21,120 acrefeet 
of storage capacity. Provision is made for 17,450 
acre-feet of reservoir capacity between elevations 
1341 and 1300 for control of floods in winter and 
spring season, and 14,360 acre-feet (El. 1341-1310) 
during summer and fall, in conjunction with which 
storage of 3,090 acre-feet would be available on a 
seasonal basis to meet streamflow requirements for 
water quality control and fish life below the dam. A 
minimum permanent pool of 3,670 acre-feet, 274 acres 
in extent, will thus be provided during potential flood 
seasons; and during late spring and summer when 
flood storage can be reduced, the lake is to be operated 
generally at a higher level (El. 1310) to maintain a 
larger surface area of 340 acres for recreation and to 
provide the required seasonal storage for releases of 
water during critical low-flow periods. Project will 
prevent major portion of average annual flood losses 
at Harlan and result in significant stage reductions 
with related benefits along rural reaches and at other 
urban areas downstream. Actual cost of project including 
$95,000 code 710 funds is $20,479,911. First 
construction contract awarded in December 1972. 
Project completed for beneficial use in September 
1978. 
Local cooperation. Federal Water Project Recreation 
Act of 1965 (P.L. 89-72) applies in regard to 
non-Federal participation in recreation development, 
in addition to which local interests are to provide certain 
safeguards to ensure functioning of reservoir as 
intended. In May 1981 a final recreation cost-sharing 
contract with Harlan County was approved and certain 
recreation facilities have been jointly developed 
by the Corps and the County. These facilities, consisting 
of a swimming beach and a picnic area are 
now operated and maintained by Harlan County. 
Recreation investment to date (Corps and Local) is 
about $100,000. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structures operated 
as required. 
8. MIDDLESBORO, CUMBERLAND 
RIVER BASIN, KY 
Location. At Middlesboro, Ky., on Yellow Creek, a 
tributary entering Cumberland River about 660 miles 
above its mouth. 
Existing project. A system of canals and levees 
around one side of town, arranged so as to divert most 
headwaters of Yellow Creek away from present channel 
through heart of city. Protection is thus afforded 
in large measure to life and property within business 
district and a large part of residential section. For 
project details, see page 1088 of Annual Report for 
1962. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Work 
on levees, canals, and appurtenances was accomplished 
by hired labor. 
9. TUG AND LEVISA FORKS OF THE 
BIG SANDY RIVER AND UPPER 
CUMBERLAND, WV, VA AND KY 
Location. The project is located in the State of 
West Virginia and the Commonwealths of Kentucky 
and Virginia. The Cumberland portion consists of 
the Upper Cumberland River Basin, above Cumberland 
Falls, Ky. The basin is approximately 100 miles 
in length, averaging 30 miles in width at the lower 
23-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
portion and 10 miles in width upstream at Harlan, 
Ky. The Big Sandy Basin is within the Huntington 
District and the Cumberland within the Nashville 
District. 
Existing project. Provides for flood control measures 
for communities in the Tug and Levisa Forks 
and Upper Cumberland River Basins. The Cumberland 
portion has been assigned to the Nashville District. 
Only activities of the Nashville District are 
reported hereon. Estimated Federal cost of new work 
under jurisdiction of the Nashville District is currentby 
being formulated. The project was authorized by 
the Energy and Water Development Appropriation 
Act of 1981, Section 202 of PL 96-367. 
Local cooperation. Authorizing legislation requires 
that non-federal interests shall hold and save the 
United States free from damages due to construction 
works and maintain and operate all such works after 
their completion in accordance with regulations by 
the Secretary of the Army. 
Operations during fiscal year. Engineering and design 
continued. Work on the Barbourville Cutoff was 
completed. Construction on the Pineville Levee and 
Pump Station continued and a contract was awarded 
for the Pineville Floodwall and Highway. Acquired 
8.92 acres fee at Pineville. The project is 34% complete. 
10. OHIO RIVER BASIN 
(NASHVILLE DISTRICT) 
Location. A series of levees, floodwalls, channel 
improvements, and reservoirs in Ohio River Basin 
within Nashville District. 
Existing project. The general comprehensive plans 
approved for flood control and other purposes in Ohio 
River Basin is set forth in legislation listed in Table 
23-B. Individual projects, local protection projects 
and lakes, considered in comprehensive plan within 
Nashville District are listed in Table 23-K. 
11. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent 
acts, requires local interests furnish assurances they 
will maintain and operate certain local protection 
projects after completion in accordance with regulations 
prescribed by Secretary of the Army. District 
Engineers are responsible for administration of these 
regulations within their respective districts. Maintenance 
inspections were made during fiscal year of 
completed protective works in localities transferred to 
local interests for maintenance and operation. Local 
interests were advised, as necessary, of measures required 
to maintain projects in accordance with standards 
prescribed by regulations. Fiscal year cost was 
$20,224. Total cost to September 30, 1985 was 
$272,138. For project inspection data see table 23-M. 
12. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control and coastal emergencies (Public Law 
99, 84th Cong., and antecedent legislation). 
Actual Federal cost for fiscal year were $174,625 
for disaster preparedness. 
Multiple-Purpose Projects, Including Power 
13. CENTER HILL LAKE, OHIO RIVER 
BASIN, TN 
Location. Dam is on Caney Fork River, 26.6 miles 
above its confluence with Cumberland River (mile 
309.2) at Carthage, Tenn. It is in DeKalb County, 
Tenn., about 55 miles east of Nashville, and 14 miles 
southeast of Carthage, Tenn. Reservoir extends about 
64 miles up main stream and about 10 miles up Falling 
Water River and lies within DeKalb, Putnam, 
White, and Warren Counties, Tenn. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric powerplant, and reservoir 
for primary purposes of flood control and 
power production, with a permanent pool for public 
use and conservation purposes. In addition to main 
dam structure, provision was made for a rolled-earth 
dike to close a saddle in reservoir rim near damsite. 
For further details, see page 1099 of 1962 Annual Report. 
Actual cost of project including $8,940,642 code 
710 funds is $53,412,022. 
Local cooperation. None required on completed 
project. Recreation development subject to certain 
conditions of non-Federal cost-sharing under Federal 
Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structure and its 
appurtenances maintained as required. Operation of 
powerplant was continuous except for normal inter- 
23-6

NASHVILLE, TN, DISTRICT 
ruptions and necessary shutdowns for inspection and 
maintenance purposes. Major maintenance work 
items were line surveys and property line marking, 
and repairing roadway expansion joints. Total net 
energy generated (196,021,800 kw-hr) was made 
available through Department of the Interior to Tennessee 
Valley Authority for distribution. Activities 
under reservoir management involved land management, 
public relations, and maintenance of public use 
facilities. 
14. DALE HOLLOW LAKE, OHIO RIVER 
BASIN, TN AND KY 
Location. Dam is on Obey River, 7.3 miles above its 
confluence with Cumberland River (mile 380.9) at 
Celina, Tenn. It is in Clay County, Tenn., and about 
80 miles northeast of Nashville, Tenn., 28 miles north 
of Cookeville, Tenn., and 3 miles east of Celina, Tenn. 
Reservoir extends about 51 miles up main stream, 10 
miles up East Fork, and 6 miles up West Fork of Obey 
River, and lies within Cumberland and Clinton Counties, 
Ky., and Clay, Pickett, Overton, and Fentress 
Counties, Tenn. 
Existing project. A concrete gravity-type dam, hydroelectric 
powerplant, and reservoir for primary 
purposes of flood control and power production with 
a permanent pool for public use and conservation purposes. 
See page 1096 of 1962 Annual Report for 
project details. Cost of project including $2,195,600 
code 710 funds and $150,000 non-Federal funds for 
recreation facilities under the completed projects program 
is $28,317,746. 
Local cooperation. None required on completed 
project; future recreation development subject to certain 
conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structures and 
appurtenances maintained as required. Operation of 
powerplant was continuous except for normal interruptions 
and necessary shutdowns for inspection and 
maintenance purposes. Total net energy generated 
(58,921,700 kw-hr) was made available through 
Department of the Interior to Tennessee Valley Authority 
for distribution. Activities under reservoir 
management program involved public relations, land 
management, and maintenance of public-use facilities. 
Major accomplishments were replacement of oil circuit 
breakers, completion of Washhouse and Fish 
Cleaning Station and paving at Horse Creek, Lillydale 
and Wolf River. 
15. J. PERCY PRIEST DAM AND 
RESERVOIR, OHIO RIVER BASIN, TN 
Location. Damsite is on Stones River, 6.8 miles 
above its confluence with Cumberland River (mile 
205.9); in Davidson County, Tenn.; and about 7 miles 
east of Nashville, Tenn. Reservoir extends southeasterly 
from dam about 32 miles along main stream, 10 
miles up East Fork, 6.5 miles up West Fork, and for 
shorter distances up other tributaries of Stones River; 
and lies within Davidson, Rutherford, and Wilson 
Counties, Tenn. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric powerplant, and reservoir 
for primary purposes of flood control, power 
production and recreation. For further details see 
page 703 of 1969 Annual Report. Cost of project including 
$3,260,400 under code 710 funds and $46,000 
non-Federal funds for recreation facilities under the 
completed projects program is $56,914,039. 
Local cooperation. Recreation development subject 
to certain conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structures and 
appurtenances maintained as required. Total net 
energy generated (41,087,900 kw-hr) was made available 
through Department of the Interior to Tennessee 
Valley Authority for distribution. Activities under 
reservoir management program involved public relations, 
fish and wildlife management, and maintenance 
of public-use facilities. Contract for paving parking 
areas and road was completed. 
16. LAUREL RIVER LAKE, OHIO RIVER 
BASIN, KY 
Location. Damsite is at mile 2.3 on Laurel River, a 
tributary of Cumberland River, in southcentral Kentucky. 
The two streams meet about 9 miles below 
Cumberland Falls, a prominent physiographic feature 
at head of Lake Cumberland which is formed by Wolf 
Creek Dam. Reservoir extends 19.2 miles upstream to 
site of Corbin, Ky. water-supply dam and lies within 
Laurel and Whitley Counties. 
Existing project. Project approved in general accordance 
with recommendations of House Document 
413, 86th Congress, by 1960 Flood Control Act, as 
amended by Public Law 88-253, was designed for 
purposes of flood control, power, and recreation as an 
integral unit of a coordinated plan for development of 
water resources of Cumberland River Basin. With the 
view of a net gain in power potential on a system 
23-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
basis, the plan of improvement incorporated appropriate 
flood control storage in the proposed project 
and corresponding adjustment in operations of Wolf 
Creek Dam-Lake Cumberland for flood control and 
power, which in effect constituted a transfer of reservoir 
capacity without entailing a change in flood 
control benefits. Further detailed study giving full 
consideration to power capabilities and marketing arrangements 
indicated the advantage of maintaining 
present storage allocation at Wolf Creek and use of 
all available storage capacity of Laurel River Lake 
for power. The power plant is complete. Recreation 
was completed this FY. Total cost is $56,741,232. 
Local cooperation. None required. 
Operations during fiscal year. New work: Contract 
was completed for Resource Management Office. 
Forest Service completed work on recreation sites 
under agreement. The project is 100% complete. 
Maintenance: Dam was operated and structures and 
appurtenances maintained as required. Total net 
energy generated (37,827,000 kw-hr) was made available 
through Department of the Interior for distribution. 
17. WOLF CREEK DAM-LAKE 
CUMBERLAND, OHIO RIVER 
BASIN, KY 
Location. Wolf Creek Dam is on Cumberland River 
at mile 460.9 (above mouth) in Russell County, Ky., 
about 10 miles southwest of Jamestown and 12 miles 
north of Albany, Ky. Lake Cumberland extends 101 
miles up main stream, 48 miles up South Fork of 
Cumberland River, in Russell, Clinton, Wayne, 
Pulaski, McCreary, Laurel, and Whitley Counties, Ky. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric powerplant, and reservoir 
for primary purposes of flood control and 
power production, with a permanent pool for publicuse 
and conservation purposes. See page 1094 of 1962 
Annual Report for project details. Cost of project is 
$188,267,195. This cost includes $3,259,372 code 710 
funds, $880,000 non-Federal funds for recreation facilities 
under the completed program, and $104,999,237 
for major rehabilitation. 
Local cooperation. None required on completed 
project; future recreation development subject to certain 
conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: Activity 
involving the integrity of the structure began in 1968 
when a leak or seepage developed in the embankment. 
The major rehab embankment contract was physically 
completed in September 1982. Recreation Facilities 
under code 711 cost $9,190. Maintenance: Dam was 
operated and structures and appurtenances maintained 
as required. Operation of powerplant was continuous 
except for normal interruptions and necessary 
shutdowns for inspection and maintenance purposes. 
Major repairs to the generator turbines, switchyard 
oil circuit breakers and generator coolers were completed. 
Updating of the sanitary facilities at Kendall 
Recreation Site was also completed. Total net energy 
generated 492,011,000 kw-hr) was made available 
through Department of the Interior for distribution. 
Activities under reservoir management program involved 
land management activities, public relations, 
and maintenance of public-use facilities. 
General Investigations 
18. SURVEYS 
Costs for this period were $1,570,948 for which 
$883,537 was for navigation, $582,880 for flood damage 
prevention studies, $57,048 for special investigations, 
and $47,483 for coordination studies with other 
agencies. 
19. COLLECTION AND STUDY OF 
BASIC DATA 
Costs for this period were $47,788 for technical 
services to others, and $41,254 for flood plain management 
services, totalling $89,042. 
23-8

NASHVILLE, TN, DISTRICT 
TABLE 23-A COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project 
1. Cumberland River, 
TN and KY 
2. Tennessee River, 
TN, AL and KY 
3. Tenn.-Tombigbee 
Waterway, AL and MS 
5. Big South Fork National 
River and Rec. Area, 
KY and TN 
6. Martins Fork Lake, KY 
7. Middlesboro, Cumberland 
River Basin, KY 
8. Tug & Levisa Forks of the 
Big Sandy & Cumberland 
River, WV, VA and KY 
11. Cumberland, KY 
12. Center Hill Lake, 
Ohio River Basin, TN 
13. Dale Hollow Lake, 
Ohio River Basin, 
TN and KY 
14. J. Percy Priest Dam and 
Reservoir, Ohio River 
Basin, TN 
15. Laurel River Lake, 
Ohio River Basin, KY 
Funding FY 83 FY 84 FY 85 FY 86 Sep 30, 1986 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
466,319 
417,163 
14,079,949 
13,918,143 
7,153,000 
7,004,232 
.- 
65,516,000 
65,822,382 
10,975,000 
10,731,095 
100,000 
64,253 
491,000 
500,189 
39,000 
36,553 
8,270,000 
2,854,007 
146,947 
8,767 
3,605,000 
3,268,063 
365,441 
30,437 
2,988,000 
2,828,213 
- 6,907 
3,902 
1,985,000 
1,959,925 
2,170,000 
2,522,143 
773,000 
716,769 
929,000 
523,103 
14,670,200 
15,494,335 
6,848,500 
6,978,158 
25,000,000 
17,837,084 
10,300,000 
9,432,902 
- 50,000 
244 
406,000 
401,981 
22,000 
27,384 
4,000,000 
8,286,077 
9,000 
153,247 
3,790,000 
4,078,470 
30,000 
341,796 
2,554,000 
2,732,605 
3,810 
2,290,500 
2,173,573 
545,000 
379,374 
771,000 
828,369 
- 7,800 
722,194 
18,453,000 
18,461,695 
9,855,000 
9,755,161 
19,755,000 
27,688,233 
8,405,000 
9,183,262 
545,000 
523,757 
65,000 
60,309 
13,684,000 
14,504,087 
2,209 
3,198,000 
3,195,628 
- 17,700 
5,509 
3,180,000 
2,966,610 
471 
2,553,000 
2,489,352 
219,221 
864,000 
840,428 
538 
18,496,000 
18,448,409 
16,900,000 
16,908,385 
11,405,000 
6,844,558 
10,231,765 
10,105,683 
-- 6,765 
-6,765 
480,000 
507,448 
27,000 
28,020 
11,840,000 
12,317,354 
2,820,000 
2,853,975 
.-. 
3,007,000 
3,101,316 
2,353,000 
2,497,915 
58,000 
141,682 
886,000 
883,590 
23-9 
320,252,240 1,2,8 
320,176,653 1,2,4 
180,485,676 5 
179,501,301 6 
16,251,428 7 
16,251,428 7 
118,387,951 8 
118,033,208 9 
400,000 
400,000 
736,160,050 
730,302,532 
91,290,920 10 
90,346,207 11 
20,479,911 
20,479,911 
3,230,000 
3,215,079 
817,830 12 
817,830 s12 
1,722,844 
1,715,473 
42,494,000 13 
41,102,962 14 
66,642 
66,642 
53,412,022 15 
53,412,022 16 
40,017,967 17 
39,935,858 18 
28,317,746 19 
28,317,746 20 
39,031,807 21 
38,890,841 22 
56,914,039 28 
56,914,039 24 
25,115,586 25 
25,019,927 26 
56,741,232 
56,741,232 
6,043,000 
6,003,252

REPORT OF THE 'CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 23-A COST AND FINANCIAL STATEMENT 
(Continued) 
See 
Section Total to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep 30, 1986 
16. Wolf Creek Dam and New Work 
Lake Cumberland, Approp. - 28,051 - 12,300 77,800 - 83,267,958 27 
Ohio River Basin, KY Cost 13,994 2,615 79,000 9,190 83,267,958 27 
Maint. 
Approp. 3,059,000 3,894,000 5,360,000 4,847,000 55,346,441 28 
Cost 2,858,455 4,097,459 5,066,321 5,055,966 55,153,595 29 
Rehab. 
Approp. - - 35,000 - - 104,999,237 80 
Cost 22,686 7,249 - - 104,999,237 3o 
1. Includes $9,707,354 for abandoned and/or replaced works 
under the old Cumberland River system. (Amount includes 
$826,253 for new work and $3,266,706 for maintenance on previous 
projects.) 
2. Includes $61,733 public works acceleration funds, and 
$102,966 contributed by the State of Kentucky and $6,750 contributed 
by Metropolitan Nashville, TN. 
3. Includes $298,000 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
4. Includes $32,040 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
5. Includes $955,889 for special recreation use fees, and 
$1,601,079 for maintenance and operation of dams and other 
improvements of navigable waters, and $1,892,000 funds provided 
from the Productive Employment Appropriation Act (PL 
98-8) of 1983. 
6. Includes $955,889 for special recreation use fees and 
$1,601,079 for maintenance and operation of dams and other 
improvements of navigable waters, and $1,892,000 funds provided 
from the Productive Employment Appropriation Act (PL 
98-8) of 1983. 
7. Includes $14,007,193 for new work and $4,005,175 for 
maintenance on previous projects. 
8. Includes $495,763 for maintenance and operation of dams 
and other improvements of navigable waters, and $764,000 
funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
9. Includes $495,763 for maintenance and operation of dams 
and other improvements of navigable waters, and $764,000 
funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
10. Includes $300,000 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
11. Includes $300,000 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
12. Includes $33,876 Emergency Relief Funds. 
13. Includes $6,470,000 contributed by the State of Kentucky. 
14. Includes $5,336,932 contributed by the State of Kentucky. 
15. Includes $35,896 public works acceleration funds, and 
$148,000 funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
16. Includes $35.896 public works acceleration funds, and 
$148,000 funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
17. Includes $292,280 funds for special recreation use fees, 
and $131,900 for maintenance and operation of dams and other 
improvements of navigable waters, and $91,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
18. Includes $292,280 funds for special recreation use fees, 
and $131,900 for maintenance and operation of dams and other 
improvements of navigable waters, and $91,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
19. Includes $51,789 public works funds and $150,000 contributed 
by the State of Tennessee, and $341,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
20. Includes $51,789 public works funds and $150,000 contributed 
by the State of Tennessee, and $341,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
21. Includes $339,480 funds for special recreation use fees, 
and $131,900 for maintenance and operation of dams and other 
improvements of navigable waters, and $482,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
22. Includes $339,480 funds for special recreation use fees, 
and $131,900 for maintenance and operation of dams and other 
improvements of navigable waters, and $482,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
23. Includes $46,000 contributed by the Metropolitan Government, 
Nashville, TN. 
24. Includes $46,000 contributed by the Metropolitan Government, 
Nashville, TN. 
25. Includes $260,680 for special recreation use fees, and 
$75,400 for maintenance and operations of dams and other 
improvements of navigable waters, and $40,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
26. Includes $260,680 for special recreation use fees, and 
$75,400 for maintenance and operations of dams and other 
improvements of navigable waters, and $40,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
27. Includes $96,920 public works acceleration funds, and 
$880,000 contributed by the State of Kentucky. 
28. Includes $82,048 public works acceleration funds, and 
$131,900 for maintenance and operation of dams and other improvements 
of navigable waters, and $278,780 funds for special 
recreation use fees, and $293,000 funds provided from the 
Productive Employment Appropriation Act (PL 98-8) of 1983. 
29. Includes $82,048 public works acceleration funds, and 
$131,900 for maintenance and operation of dams and other improvements 
of navigable waters, and $278,780 funds for special 
recreation use fees, and $293,000 funds provided from the 
Productive Employment Appropriation Act (PL 98-8) of 1983. 
30. Includes $203,757 for claim paid on initial construction 
of switchyard. 
23-10

NASHVILLE, TN, DISTRICT 
AUTHORIZING LEGISLATION 
ee Section Date of 
1Text Authorized Act Project and Work Authorized Documents 
CUMBERLAND RIVER BELOW NASHVILLE 
Jul 13, 1892 Provision made for lock A 
Jun 25, 1910 
Aug 30, 1935 
Jul 24, 1946 
Jun 19, 1952 
Provision made for locks B to F, and for dredging below 
lock F. 
Repairing dams A to F, inclusive, and surmounting same 
with movable crests. 
Provision of 9-foot channel by the construction of 3 
moderate height dams below Nashville; via, Kuttawa 
(Eureka), Dover, and Cheatham. 
Provision for hydroelectric power production as a function 
of Cheatham Dam. 
Sep 3, 1954 Construction of Barkley (Lower Cumberland) dam and 
reservoir project for navigation, flood control, hydroelectric 
power, and related purposes in lieu of Kuttawa 
and Dover navigation--only structures. 
Jul 14, 1960 Authorized change in alignment of Illinois Central Railroad. 
CUMBERLAND RIVER ABOVE NASHVILLE 
Aug 5, 1886 Provision made for locks and dams; the Secretary of War 
to determine the final plan of improvement. 
Dimensions of the locks fixed in accordance with reports 
of Mar. 30, 1887, and Nov. 25, 1890. 
Mar 2, 1907 Adoption of the report of the Board of Engineers, dated 
Feb. 26, 1906, limiting the lock and dam construction to 
locks and dams 1 to 7, and 21. 
Mar 2, 1919 Provision made for locks and dams 8 to 17. 
Jun 5, 1920 
Jul 3, 1930 
Jun 26, 1934 2 
Authorizes work to proceed in Tennessee without waiting 
for action of local interests in Kentucky. 
Raising dam 1, 3 feet. 
Operation and care of locks and dams provided for with 
funds from War Department appropriations for rivers 
and harbors. 
Annual Report, 1890, p. 
2151 
H. Docs. 758, 60th Cong., 
1st sess.; and 1481, 60th 
Cong., 2d sess. 1 
H. Doc. 38, 73d Cong., 1st 
sess. 
H. Doc. 761, 79th Cong., 
2d sess. 
S. Doc. 81, 83d Cong., 2d 
sess. 
H. Doc. 56, 86th Cong., 2d 
sess. 
Annual Report 1884, p. 
1663. 
Annual Report 1888, p. 
1622, and Annual Report 
1892, p. 1933. 
H. Doc. 699, 59th Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 10, 63d 
Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 26, 70th 
Cong., 2d sess. 
Jul 24, 1946 Construction of Old Hickory, Cordell Hull (Carthage), and 
Celina Dams above Nashville for navigation and the 
development of power resources. 
Design and construct flood control measures for communities 
in the Upper Cumberland River basins. 
TENNESSEE RIVER 
Authorized navigable depth of 9 feet from mouth about 
650 miles to Knoxville, Tennessee to be obtained by 
construction of low dams. 
Authorized TVA to construct such dams in the Tennessee 
River as will provide a 9 foot channel. 
H. Doc. 761, 79th Cong., 
2d sess. 
Sec. 202, PL 96-367 
H. Doc. 328, 71st Cong., 
2d sess. 
23-11 
TABLE 23-B 
S. 
in 
1. 
1. 
Oct 1, 1980 
Jul 3, 1930 
May 18, 1933

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 23-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Section Date of 
in Text Authorized Act Project and Work Authorized Documents 
9. OHIO RIVER BASIN, NASHVILLE DISTRICT 
Construct levees, floodwalls, and drainage structures for 
protection of cities and towns in Ohio River Basin. 
Project to be selected by Chief of Engineers with 
approval of Secretary of War at a cost not to exceed 
$24,877,000 for construction. 
Jun 28, 1938 Approved general comprehensive plan for flood control and 
other purposes in Ohio River Basin as may be advisable 
at discretion of Secretary of War and Chief of Engineers, 
and for initiation and partial accomplishment of plan, 
authorized $75 million for reservoirs and $50,300, for 
local flood protection works. 
Aug 18, 1941 Additional $45 million for prosecution of comprehensive 
plan for Ohio River Basin. 
Dec 22, 1944 Additional $70 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Jul 24, 1946 Additional $125 million for further prosecution of 
comprehensive plan. 
May 17, 1950 
Flood Control Committee 
Doc. 1, 75th Cong., 1st 
sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st 
sess. 
H. Doc. 762, 77th Cong., 
2d sess. 
H. Doc. 506, 78th Cong., 
1st sess. 
Additional $100 million for prosecution of comprehensive 
plan for Ohio River Basin. 
Dec 30, 1963 Additional $150 million for further prosecution of 
comprehensive plan for flood control and other purposes 
in Ohio River Basin. 
Additional $89 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Additional $35 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Jun 19, 1970 Additional $69 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Mar 7, 1974 Authorized establishing Big South Fork National River and 
Recreation Area, KY and TN. Total area not to exceed 
125,000 acres. 
Mar 7, 1974 Additional $120 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
TENNESSEE-TOMBIGBEE WATERWAY 
Jul 24, 1946 Construction of waterway to connect above rivers and 
provide a 9 foot channel and minimum bottom width 
of 170 feet in river and canal sections and 150 feet in 
the divide cut, with locks 110 by 600 feet clear inside 
dimensions. 
Subsequent studies determined most practical plan consists 
of channel with bottom width of 300 feet (280 feet in 
divide cut), fewer locks with higher lifts resulted in 
reducing number of lifts from 18 to 10 and reduced 
length from 260 to 253 miles. 
H. Doc. 6755, 89th Cong., 
1st sess. 
S. 3710, 90th Cong., 2d 
sess. 
H. R. 15166 91st Cong., 
2d sess. 
H. R. 10203 93rd Cong. 
Water Resources Develop. 
Act of 1974 Amended by 
PL 94-587, 94th Cong. 
H. R. 10203 93rd Cong. 
River Basin Monetary 
Authorization Act of 
1974. 
H. Doc. 486, 79th Cong., 
2d sess. 
Page 1343, Part I, FY 
1968 House Hearings. 
1. Contains latest published maps. Included in Public 
Works Administration program Sept. 6, 1933. 
2. Permanent Appropriation Repeal Act. 
23-12 
Aug 28, 1937 
Jun 18, 1965 
Aug 13, 1968 
3.

NASHVILLE, TN, DISTRICT 
TABLE 23-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(All Projects not Specifically Identified in Text) 
Project 
Caney Fork River, TN 
Clinch River, TN and VA 
Duck River, TN 
Elk River, AL and TN 
French Broad and Little Pigeon Rivers, TN 
Hiwassee River, TN 
Holston River, TN 
Little Tennessee River, TN 
Obey River, TN 
Red River, TN 
Status 
abandoned 
abandoned 
abandoned 
abandoned 
abandoned 
abandoned 
abandoned 
abandoned 
abandoned 
abandoned 
For last Full 
Report see 
Annual Report 
1895 
1923 
1887 
1904 
1931 
1923 
1911 
1888 
1887 
1884 
Cost to Sep 30, 1986 
Operation and 
Construction 
$ 27,828 
53,949 
13,000 
4,000 
249,605 
113,311 
5,714 
5,510 
11,500 
5,000 
-. ^Am 
Maintenance 
$ 7,873 
33,554 
9,754 
Soutn For of C umberlana River, KY abandoned 189211,967 - 
TABLE 23-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(All Projects not Specifically Identified in Text) 
For last Full Cost to Sep 30, 1986 
Report see Operation and 
Project Status Annual Report Construction Maintenance 
Barbourville, KY completed 1963 $2,088,147 - 
Chattanooga, TN and Rossville, GA completed 1949 180,997 - 
Coal Creek and Tributaries (Lake City), TN completed 1962 460,134 - 
Corbin (Lynn Camp Creek), KY completed 1969 567,703 - 
Middlesboro (Yellow Creek), KY completed 1949 26,309 
Paint Rock River, AL completed 1967 544,173 
Pineville, KY completed 1963 1,679,126 - 1 
Rossview Reservoir, Ohio River Basin, TN and KY inactive - 6,779 - 
1. Includes $9,950 contributed funds. 
23-13 
i

TABLE 23-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED MULTIPLE-PURPOSE PROJECTS 
INCLUDING POWER 
For last Full Cost to Sep 30, 1986 
Report see Operation and 
Project Status Annual Report Construction Maintenance 
Barkley Dam and Lake Barkley, KY and TN beneficial use - $146,423,053 $56,759,870 1 
Celina Dam, KY active -- 222,575 -- 1 
Cheatham Lock and Dam, TN beneficial use - 31,682,762 42,580,761 1 
Cordell Hull Lock and Dam, TN beneficial use - 79,874,492 27,287,075 1 
Old Hickory Lock and Dam, TN beneficial use - 52,266,412 52,873,595 1 
1. Details given under "Cumberland River, TN and KY." See Table 23-H. 
TABLE 23-G DEAUTHORIZED PROJECTS 
For last Full Federal Contributed 
Report see Funds Funds 
Project Annual Report for Date and Authority Expended Expended 
Three Islands Reservoir, Ohio 1970 Authorized: FC Act 1938, PL 761, 75 $111,855 - 
River Basin, TN Cong., 3rd sess.; FC Act 1946, PL 525, 
79th Cong., 2d sess. 
Deauthorized: 5 Aug 1977. 
23-14

NASHVILLE, TN, DISTRICT 
TABLE 23-H CUMBERLAND RIVER, TN AND KY: PRINCIPLE FEATURES 
(See Section 1 of Text) 
Dam and Reservoir Barkley Cheatham Old Hickory Cordell Hull Celina 
Nearest town 
Miles above mouth of river 
Lock dimensions (feet)1 
Lift at normal pool levels (feet) 
Depths on guardsills at 
minimum pool levels (feet) 
Character of foundation 
Dam: 
Type 
Height 
Length, exclusive of lock section 
(feet) 
Spillway: 
Gross length (feet) 
Net length opening (feet) 
Crest gates: 
Type 
Number 
Size (feet) 
Operating levels at dam 
(feet, mean sea level) : 
Maximum regulated 
Normal operation: 
Full pool 
Minimum pool 
Minimum pool in advance of floods 
Reservoir area (acres) 
Reservoir capacity (acre-feet) : 
Flood control 
Power drawdown 
Dead storage 
Total 
Canal: 
Length (miles) 
Bottom width (feet) 
Depth at minimum pool level (feet) 
Power development: 
Number of units 
Generator rating (kilowatts) 
Total installation (kilowatts) 
Kuttawa, KY, 
11 miles. 
30.6 
110 by 800 
57 
11, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
157 
9,959 
804 
660 
Tainter 
12 
55 by 50 
Ashland City, 
TN, 9 miles. 
148.7 
110 by 800 
26 
14, upper; 
17, lower 
Rock 
Concrete 
gravity 
75 
800 
480 
420 
Tainter 
7
60 by 27 
375 
359 
354 
346 
93,430 
1,213,000 s'4 
259,000 
610,000 
2,082,000 
385 
382 
7,450 
19,800 7 
84,200 
104,000 
Old Hickory, 
TN, 3 miles. 
216.2 
84 by 400 
60 
14, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
98 
3,605 2 
325 
270 
Tainter 
6
45 by 41 
450 s 
442 
27,450 
125,000 5 
63,000 
357,000 
545,000 
Carthage, TN, 
5 miles. 
313.5 
84 by 400 
59 
14, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
93 
1,138 2 
291 
225 
Tainter 
5
45 by 41 
508 s 
508 
501 
499 
13,920 
85,600 5,6 
20,500 
204,800 
310,900 
1.75 
400 
11 
4
32,500 
130,000 
3
12,000 
36,000 
4
25,000 
100,000 
3
33,333 
100,000 
23-15 
Celina, TN, 
5 miles. 
385.4 
Rock 
Concrete 
gravity and 
earthfill 
86 
2,298 
290 
250 
Tainter 
5
50 by 37 
564 8 
560 
559 
559 
16,960 
55,950 5 
14,700 
287,300 
357,950 
3
36,000 
108,000 
l '

TABLE 23-H 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
CUMBERLAND RIVER, TN AND KY: PRINCIPLE FEATURES 
(See Section 1 of Text) 
Dam and Reservoir Barkley Celina Cheatham Cordell Hull Old Hickory 
Percent of project completion 8 - 8 8s s 
Year opened to navigation 1964 - 1952 1973 1954 
Estimated cost 9 $146,400,000 $213,000,000 $31,700,000 $79,874,500 $52,266,400 
1. Clear width and length available for full width. 
2. Exclusive of lock section. 
3. Surcharge. 
4. Normal operation (elev. 375-359) during nonflood season; 
flood control allowance to be increased to 1,472,000 acrefeet 
(elev. 375-354) during season of major floodflows. 
5. Surcharge storage. 
6. During flood season (elev. 508-501); minimum 51,800 
acre-feet (elev. 508-504) with normal operation during nonflood 
season. 
7. Daily pondage allowance; run-of-river project. 
8. Completed for full beneficial use. 
9. Includes recreation facility costs. 
23-16

TABLE 23-I TENNESSEE RIVER 
(See Section 2 of Text) 
Lock Dimensions 
Length Minimum Depth 
Width Avail- Lift on Guard Sills 
of able for Year 
Miles Cham- Full Nor- Maxi- Opened Cost of 
Above Miles from ber Width mal mum Lower Upper Character Navi- Kind Type of Each Lock 
Project 1 Mouth Nearest Town (feet) (feet) (feet) (feet) (feet) (feet) of Foundation gation of Dam Construction and Dam 
Kentucky 22.4 0.5 above Gilbertsville, 110 600 56 73.3 12.7 11.0 Limestone 1942 Fixed Concrete and 2 
KY earthfill 
Pickwick Landing: 
Auxiliary lock 206.7 4.4 above Hamburg, 110 600 55 63.0 12.8 10.0 Limestone 1937 Fixed Concrete and s 
TN earthfill 
Main lock 206.7 4.4 above Hamburg 110 1000 55 63.0 12.8 10.0 Limestone 1984 Fixed Concrete and 8 
TN earthfill 
Wilson: 
Auxiliary lock 259.4 2.9 above Florence, 60 292 94 100.0 11.0 11.2 Limestone 1927 Fixed Concrete and $46,973,540 5 
AL 300 earthfill 
Main lock 259.4 2.9 above Florence, 110 600 94 100.0 13.0 13.0 Limestone 1959 - - 7 
AL 
General Joe Wheeler: 
Auxiliary lock 274.9 18.4 above Florence 60 400 48 51.5 13.2 14.7 Limestone 1934 Fixed Concrete and 1,796,295 
AL earthfill 
Main lock 274.9 18.4 above Florence, 110 600 48 51.5 13.0 13.0 Limestone 1963 Fixed Concrete and 
AL earthfill 
Guntersville: 
Auxiliary lock 349.0 9.1 below Guntersville, 60 360 39 45.0 11.8 13.0 Limestone 1937 Fixed - S & 7 
AL 
Main lock 349.0 9.1 below Guntersville, 110 600 39 45.0 12.7 13.0 Limestone 1965 Fixed Concrete and 
AL earthfill 
Nickajack: 
Auxiliary lock 424.7 39.4 below Chatta- 110 600 39 41.0 13.0 13.0 Limestone 1967 Fixed Concrete 
nooga, TN 
Main lock 424.7 39.4 below Chatta- 110 800 39 41.0 13.0 13.0 Limestone Fixed Concrete 
nooga, TN 
Chickamauga 471.0 6.9 above Chatta- 60 360 49 53.0 13.0 10.0 Limestone 1939 Fixed 3 & T 
nooga, TN 
Watts Bar 529.9 6.8 above Breedenton, 60 360 58 70.0 11.8 12.0 Shale 1941 Fixed Concrete and s 
TN earthfill 
Fort Loudon 602.3 1.3 above Lenoir City, 60 360 72 80.0 11.8 12.0 Limestone 1943 Fixed Concrete and a 
TN earthfill 
Melton Hill 23.1 22.1 above Kingston, 75 400 54 60.0 13.0 13.0 Limestone 1963 Fixed Concrete S 
(Clinch R.) TN 
1. H. Doc. 328, 71st Cong., 2d sess., contains table, pp. 98 
and 99, giving pertinent information concerning low dams contemplated 
under 1930 project. Annual Report for 1938, pp. 1218 
and 1219, contains similar information pertaining to low dams 
in addition to existing locks and dams, including those constructed 
or under construction by Tennessee Valley Authority. 
2. Lock and dam constructed by Tennessee Valley Authority. 
3. Lock and dam constructed by Tennessee Valley Authority. 
Design for lock prepared with Corps forces and funds. 
4. Tailwater in canal; flight of 2 locks. 
5. Constructed by the Corps under authority of sec. 124, 
National Defense Act of June 3, 1916 (H. Doc. 1262, 64th 
Cong., 1st seas.). Actual cost of lock and dam. 
6. Actual cost of lock only as constructed by the Corps; 
dams constructed by Tennessee Valley Authority. 
7. Constructed by Tennessee Valley Authority. 
z
x1 
v1 
nj 
M
h1r4 
.-a

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 23-J TENNESSEE RIVER, TN, AL, AND KY 
TOTAL COST OF EXISTING PROJECTS TO SEP 
(See Section 2 of Text) 
Channel Operation & 
Funds New Work Maintenance Maintenance Total 
Regular $2,244,236 $7,235,104 $106,781,259 $116,260,599 1,2 
Maintenance - - 11,665 11,665 
Increase of compensation, - 5 - 5 
rivers and harbors, 1919 
(certified claims) 
Total $2,244,236 $7,235,109 $106,792,924 $116,272,269 1,2 
1. In addition, surplus property value at $54,336 was tion and care of works of improvement under provisions of 
transferred from the project without reimbursement. Excludes appropriation for such purposes. 
$4,005,175 expended between 1890 and June 30, 1935, on opera- 2. Excludes $14,007,192 previous construction cost. 
TABLE 23-K OHIO RIVER BASIN (NASHVILLE DISTRICT) 
LOCAL PROTECTION PROJECTS 
Estimated Cost 
Type of 
Location Protection Federal Non-Federal Total 
Middlesboro Levees $581,000 $161,000 $742,000 1 
(Yellow Creek, KY) 
Cumberland, KY Channel 520,000 240,000 760,0001 
Improvement 
1. Deferred. 
TABLE 23-L RESERVOIRS 
Total 
Estimated 
Tributary Basin and Reservoir Stream Cost 
Center Hill Lake, TN Caney Fork River $53,412,000 1 
Dale Hollow Lake, TN and KY Obey River 28,167,7001 
J. Percy Priest Dam & Reservoir, TN Stones River 59,038,200 1.2 
Laurel River Lake, KY Laurel River 56,683,200 s 
Martins Fork Lake, KY Martins Fork 20,486,700 
Rossview, TN & KY Red River 12,590,000 4.s 
1. Details of this project are in individual report. 
2. Formerly Stewarts Ferry Reservoir. 
3. See "Other authorized multiple-purpose projects." 
4. See "Other authorized flood control projects." 
5. Deferred. 
23-18 
30, 1985

NASHVILLE, TN, DISTRICT 
TABLE 23-M INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 10 of Text) 
Project Date of Inspection 
Barbourville, KY Apr. 1986 and Oct. 1986 
Corbin, KY Apr. 1986 and Oct. 1986 
Lake City, TN May 1986 and Oct. 1986 
Middlesboro, KY (Yellow Creek) May 1986 and Oct. 1986 
Middlesboro, KY (Diversion Canal) May 1986 and Oct. 1986 
Paint Rock River, AL May 1986 and Oct. 1986 
Pineville, KY Apr. 1986 and Oct. 1986 
Spring City, TN May 1986 and Oct. 1986 
TABLE 23-N FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 205 
P.L. 858, 80th Congress, as amended 
Project FY 86 Cost 
Browns Creek, Nashville, TN $23,488 
Dry Creek, Goodlettsville, TN 23,802 
Richland and Sugartree Creeks, TN 13,589 
Whiteoak Creek, Sunbright, TN 1,649 
Emergency Bank Protection (Section 14 of the 1946 
Flood Control Act, P.L. 526, 79th Congress) 
Project FY 86 Cost 
Canton Bridge, Trigg County, KY $33,261 
Concord Park, Fort Loudoun, TN 7,500 
Crab Orchard Branch, Wise County, VA 10,248 
Tenn. River, Downtown Airport, Knoxville, TN 37,996 
Lewis Branch, Houston County, TN 36,231 
Paris Landing, TN 25,907 
Piney River, Rhea County, TN 1,544 
Sheffield, AL City Dock 37,573 
Soddy Daisy, TN Repair 4,787 
1. Includes $20 contributed funds from the city of Fort Loudoun, TN. 
23-19

LOUISVILLE, KY. DISTRICT * 
This district comprises a portion of southwestern Ohio, Rivers) from mile 438 (below Pittsburgh) immediately 
west central Kentucky, a small portion of north central upstream from Foster, KY. to mouth. 
Tennessee, Indiana except northern part, and 
southeastern Illinois except Cairo-Mounds-Mound City All cost and financial statements for projects are listed 
area, all included in drainage basin of Ohio River and its at the end of this chapter. All other tables are referenced 
tributaries (exclusive of Tennessee and Cumberland in text and also appear at the end of this chapteir. 
IMPROVEMENTS 
Navigation - Locks and Dams Page 
1. Construction of Locks and Dams, 
Ohio River .............................. 24-2 
2. Green and Barren Rivers, KY.............24-2 
3. Kentucky River, KY.....................24-2 
4. Open Channel Work, Ohio River........... 24-3 
5. Other Authorized Navigation 
Projects ................................ 24-3 
6. Navigation Work Under Special 
Authorization ........................... 24-3 
Flood Control - Local Protection 
7. Dayton, KY................. ............ 24-3 
8. Evansville, IN................ ........... 24-3 
9. Levee Unit No. 5, 
Wabash River, IN .................. ...... 24-4 
10. Mason J. Niblack Levee, 
Wabash River, IN.......................24-4 
11. Mill Creek, OH............... ........... 24-4 
12. Southwestern Jefferson 
County, KY ............................. 24-5 
Flood Control - Reservoirs 
13. Barren River Lake, KY...................24-5 
14. Brookville Lake, IN ...................... 24-5 
15. Buckhorn Lake, KY .................... .24-6 
16. Caesar Creek Lake, OH...................24-6 
17. Cagles Mill Lake, IN ..................... 24-6 
18. Carr Fork Lake, KY.....................24-7 
19. Cave Run Lake, KY................ .... 24-7 
20. Cecil M. Harden Lake, IN................. 24-7 
21. Clarence J. Brown Dam 
& Reservoir, OH....................... 24-8 
22. Green River Lake, KY....................24-8 
23. Huntington Lake, IN ..................... 24-8 
24. Mississinewa Lake, IN....................24-9 
25. Monroe Lake, IN ........................ 24-9 
26. Nolin Lake, KY ......................... 24-9 
27. Ohio River Basin 
(Louisville Dist.) ....................... 24-10 
28. Patoka Lake, IN........................24-10 
29. Rough River Lake and Channel 
Improvement, KY ....................... 24-10 
30. Salamonie Lake, IN.....................24-11 
31. Taylorsville Lake, KY................... 24-11 
Page 
32. Wabash River Basin .................... 24-11 
33. West Fork of Mill Creek Lake, OH........24-12 
34. William H. Harsha Lake, OH.............24-12 
35. Inspection of Completed Flood 
Control Projects.........................24-12 
36. Other Authorized Flood Control 
Projects .............................. 24-13 
37. Flood Control Works Under 
Special Authorization.................... 24-13 
General Investigations 
38. Surveys .............................. 24-13 
39. Collection and Study of Basic Data........ 24-13 
40. Continuation of Planning and 
Engineering ............................ 24-13 
Tables 
Table 24-A Cost and Financial 
Statement ...................... 24-14 
Table 24-B Authorizing Legislation..........24-18 
Table 24-C Other Authorized Navigation 
Projects ........................ 24-19 
Table 24-D Not Applicable 
Table 24-E Other Authorized Flood 
Control Projects................. 24-20 
Table 24-F Not Applicable 
Table 24-G Deauthorized Projects ............ 24-22 
Table 24-H Principal Features of Green 
and Barren Rivers and Kentucky 
River Navigation Systems........ 24-23 
Table 24-I Ohio River Basin - Total 
Cost of Basin Plan................ 24-24 
Table 24-J Wabash River Basin - Total 
Cost of Basin Plan............... 24-28 
Table 24-K Inspection of Completed 
Flood Control Projects............24-29 
Table 24-L Flood Control Work Under 
Special Authorization.............24-31 
24-1

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
Navigation - Locks and Dams 
1. CONSTRUCTION OF LOCKS AND 
DAMS, OHIO RIVER 
For report on this improvement, see the heading under 
Ohio River. 
2. GREEN AND BARREN RIVERS, 
KY. 
Location. Green River rises in Casey County, KY, 
flows northwesterly 370 miles, and empties into Ohio 
River about 8 miles above Evansville, IN. Barren River 
rises in Monroe County, KY, flows northwesterly 130 
miles, and empties into Green River 1/2 mile above Lock 
4 and 149.5 miles above mouth of Green River. 
Existing project. Six locks and dams on Green River 
and one on Barren River to give, with channel work in 
pools of dams, a navigable depth of 9 feet and width of 
200 feet from Ohio River to mile 103 Green River, 3.2 
miles upstream from Paradise, KY; a navigable depth of 
5.5 feet from mile 103 Green River to Mammoth Cave, 
KY, mile 197.8 Green River, and from mouth of Barren 
River mile 149.5 Green River, to Bowling Green, KY, mile 
30.1, Barren River. 
Fluctuations in stage vary considerably at different 
locks. At Lock 3, Green River, ordinary high stages are 
from 12 to 15 feet above pool level, and at Lock 1, Barren 
River, from 7 to 10 feet above pool. Maximum stages of 
record are 34 feet above normal pool stage at Lock 3, 
Green River, and 29 feet at Lock 1, Barren River, obtained 
during floods of 1937 and 1913, respectively. (See Table 
24-B for authorizing legislation and Table 24-H for principal 
features of the locks and dams.) 
Local cooperation. Fully complied with. 
Terminal facilities. Coal handling facilities located 
on the Green River between miles 81.5 and 108.1 near 
South Carrollton, Rockport, Paradise and Rochester, 
Kentucky, are considered adequate for existing 
commerce. 
Operations during fiscal year. Consisted of operation 
and maintenance of Locks and Dams 1 and 2, Green 
River, and removal of shoals, snags, and slides as required 
to maintain adequate channel for existing traffic between 
mouth of Green River and Dam 3 at mile 108.5 Green 
River. Maintenance: Routine maintenance was 
performed. 
Locks and Dams 1 and 2, Green River, and Lock and 
Dam 1, Barren River, are in good condition. Lock and 
Dam 3, Green River, is in fair condition, and Lock 4, 
Green River, is in poor condition. Dam 4, Green River, 
failed May 24, 1965, when 120 feet washed out. Breach 
later widened, and repairs are deferred pending completion 
of survey report for navigation on Green River. Pool 
of Dam 1, Barren River, is maintained for local small boat 
use, but navigation through lock is suspended because of 
loss of lower pool. Operation activity was discontinued at 
Lock 4 Green River and Lock and Dam 1 Barren River 
in January 1974 and at Lock 3, Green River in September 
1981. The residences and associated buildings and 
certain real estate at Lock 4 Green River and Lock and 
Dam 1 Barren River were disposed of in January 1975. 
Operation of Locks 5 and 6, Green River, was discontinued 
August 1951, as they were no longer used by river 
traffic. Controlling project depth in lower 103 miles of 
Green River is 9 feet; controlling depth from mile 103 to 
Bowling Green; KY, is 5.5 feet. Under permit issued by 
District Engineer on August 20, 1963, private interests 
dredged channel of Green River to extend 9-foot depth to 
coal loading teminal at mile 105.7. Channel of Green 
River above Lock 3 is no longer maintained. 
3. KENTUCKY RIVER, KY 
Location. Formed by confluence of its North and Middle 
Forks about 4 miles east of Beattyville in east central 
Kentucky, (South Fork joins the main stream at that 
location), flows northwesterly and empties into Ohio River 
at Carrollton, KY, mile 545.8 below Pittsburgh, PA. 
Existing project. Provides for 14 locks and fixed dams 
to give, in connection with improvement of Ohio River, 
slack water navigation of 6 feet minimum depth from 
Ohio River to places on the three forks that are short 
distances above Beattyville, KY. Length of 6-foot-depth 
project on main stem of Kentucky River is 258.6 miles 
to confluence of Middle and North Forks. Cost of completed 
new work is $4,176,749. River frequently rises to 
35 feet or higher. Extreme height at Lock 1 due to flood 
backwater from Ohio River is 60.3 feet, while extreme 
floods reach height of 47.6 feet at Lock 4, and 35.5 feet 
at Lock 14. At some intermediate locks extreme height 
of floods exceeds 40 feet. All flood heights refer to upper 
pool gages. Existing project was adopted by 1879 River 
and Harbor Act (H. Ex. Doc. 47, 45th Cong., 3d Sess., and 
Annual Report, 1879, p. 1398). Operation and care of locks 
and dams were included in project July 1, 1935, under 
provision of Permanent Appropriations Repeal Act of 
June 26, 1934. (See Table 24-H for principal features of 
the locks and dams.) 
On December 19, 1976 the lock operation schedules for 
commercial traffic and recreational craft on the Kentucky 
River System were reduced from continuous 24-hour yearround 
operation to two shift year-round operation of Locks 
1 through 4, intermittent daily operation of Locks 5 
through 10, and intermittent operation five days weekly 
of Locks 11 through 14. Since that time the hours for 
operation of Locks 5 through 14 have been reduced in 
several increments. On 1 October 1981 Locks 5 through 
14 were closed to traffic and placed in caretaker status. 
Locks 5, 6, 8, 9, and 10 were in operation for 15 weekends 
during fiscal year 1982 and was again closed at the end 
of this period. Locks 5 through 14 were leased to the State 
of Kentucky on 21 May 1985. The State of Kentucky plans 
to operate these locks on weekends during the summer 
boating seasons. During the fiscal year Locks 1 through 
4 continued a two shift, year-round operation. 
Licenses. Federal Regulatory Commission License 
No. 539, to Kentucky Utilities Co., at Dam 7, Kentucky 
River, Annual charge, $4,400; total collections through 
September 30, 1986, $271,205. 
24-2

LOUISVILLE, KY. DISTRICT 
Terminal facilities. Facilities for bulk commodities 
and gasoline are considered adequate for existing traffic. 
Operations during fiscal year. Consisted of operation 
and maintenance of Locks and Dams 1 through 4 and 
removal of shoals, snags, and slides as required to maintain 
an adequate channel for existing traffic between 
mouth of river and Dam 5 at mile 82.2 Kentucky River. 
Maintenance: Contract for miter gate repair and guard 
chain replacement was awarded in April 1986. Routine 
maintenance was performed. 
Existing project was completed in 1917. Work 
accomplished was rehabilitation of the five old State locks 
and dams and construction of new Locks and Dams 6 to 
14 inclusive. Repairs have been made to deteriorated 
locks and dams as required to keep locks in operation and 
maintain pool levels above dams except in extreme dry 
weather, when some pools fall below normal levels, details 
in Annual Reports for 1963, 1964 and 1965. Channel work 
was performed as required to provide for existing river 
traffic. Controlling navigable depth in length of river 
covered by existing project was 6 feet at end of fiscal year. 
4. OPEN CHANNEL WORK, 
OHIO RIVER 
For report on this improvement, see this heading under 
Ohio River. 
5. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 24-C. 
6. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
None. 
Flood Control - Local Protection 
7. DAYTON, KY 
Location. In Campbell County, KY, on left bank of 
Ohio River from mile 467.0 to mile 469.2 and across the 
river from Cincinnati, Ohio. (See U. S. Geological Survey 
map of Newport, KY.) 
Existing project. Provides for construction of 8,170 
feet of levee, two pumping stations with gravity drainage 
structures, and major relocations of storm and sanitary 
sewers serving the community. Estimated cost of new 
work (1986) is $13,115,900 Federal and $2,043,000 
non-Federal. 
Local cooperation. Section 3 of the Flood Control Act 
of June 22, 1936 applies. Formal assurances of cooperation 
were executed by City of Dayton, KY, on November 
1969. Levee, floodwall, and pumping plants were transferred 
to the City of Dayton for operation and maintenance 
December 30, 1982. 
Operations during fiscal year. Operation by local interests 
for flood control prevented damages estimated at 
$287,000 during 1986 flood season. 
8. EVANSVILLE, IN 
Location. In Vanderburgh County, IN, on right bank 
of Ohio River, 792.2 miles below Pittsburgh, PA. (See U.S. 
Geological Survey map of Evansville-South, IN.) 
Existing project. Construction of a system of levees 
and concrete floodwalls, together with pumping plants for 
disposal of interior drainage, at Evansville. For further 
details, see Annual Report for 1962, page 1127. Project 
will provide protection for City of Evansville, IN, against 
Ohio River floods equal to 1937 flood (maximum of record), 
with a 3-foot freeboard. Estimated total cost of new work 
(1986) is $55,692,700 Federal, including $7,900,000 (Oct 
1977) for Howell Section, Unit 2, that is in "inactive" 
category, and $7,982,000 non-Federal, including $352,000 
(Oct 1977) for the said Howell Section, Unit 2. Existing 
project selected for construction under general authorization 
for Ohio River Basin in 1937 Flood Control Act. 
Howell Section, Unit 2, was reclassified from the "active" 
category to the "inactive" category July 7, 1977 based 
on current studies that indicated this part of the project 
is not economically justified. 
Local cooperation. Section 3 of Flood Control Act of 
June 22, 1936, as amended, applies. Fully complied with 
for Howell Unit 1 and Knight Township sections. 
Assurances for Pigeon Creek Section, Unit 1, were executed 
February 11, 1963. Authorizations-of-entry for 
Pigeon Creek Section, Unit 2, Parts 1 and 2 have been 
furnished. 
Operations during fiscal year. Engineering and 
design studies continued. Plans and specifications for U.S. 
Highway 41 and Oak Hill Road pump plants were begun 
and advanced to 35% completion. Plans and specifications 
for levee and floodwall Stringtown Road to U.S. Highway 
41 advanced to about 90% completion. Contract for design 
of North 1st Avenue, Diamond Avenue and Stringtown 
Road pumping plants advanced to about 45% completion. 
Plans and specifications for levee and floodwall U.S. 
Highway 41 to Southern Railroad and Power Service for 
1st Avenue, Diamond Avenue and Stringtown Road advanced 
to about 35% and 60% completion, respectively. 
Contract for levee and floodwall Cedar Street to 
Stringtown Road and landscaping Garvin Park were completed. 
Flood damages estimated at $123,000 were 
prevented during the 1986 flood season. 
Knight Township, Howell, Unit 1 and Pigeon Creek, 
Unit 1 Sections are complete. Howell Section, Unit 2, is 
in the "inactive" category. Construction of Pigeon Creek 
Section, Unit 2, was started in April 1974 and is about 
45 percent complete. General Design Memorandum and 
Supplement on Pigeon Creek Unit 2, and Design 
Memorandum and plans and specifications for Delaware, 
Dresden and North 6th Avenue pumping plants are 
approved. Design Memorandum for North 1st Avenue, 
Diamond Avenue, and Stringtown Road pumping plants 
is complete. Project is about 58 percent complete overall. 
24-3

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
9. LEVEE UNIT NO. 5, WABASH 
RIVER, IN 
Location. In Gibson and Posey Counties, IN, on left 
bank of Wabash River, from 58 to 94.5 miles above mouth. 
Existing project. Provides for construction of 41.9 
miles of earth levee, drainage structures, pumping plants, 
together with alterations to three railroad bridges crossing 
Wabash River. Project provides protection for 44,000 
acres of farm land and towns of Lyle, Skelton, and Griffin, 
IN, against a flood equal to that expected on an 
average of 7 times in each 100-year period. Estimated 
total cost of new work (1986) is $8,345,500 of which 
$905,500 is non-Federal cost for lands and damages and 
road utility relocations. Project was authorized by Flood 
Control Acts of 1936 and 1946. 
Local cooperation. Section 3, Flood Control Acts of 
June 22, 1936, applies. Assurances were executed by 
Superintendent of Levee District on January 8, 1962. 
Completed portions of project (levees) were transferred to 
the Levee District for operation and maintenance 
October 15, 1969. Emerson Ditch pumping plant was 
transferred to the Levee District for operation and 
maintenance November 24, 1975. 
Operations during fiscal year. Construction contract 
for Coffee Bayou pumping plant and entire project 
were completed. Flood damages estimated at $1,941,000 
were prevented during the 1986 flood season. 
10. MASON J. NIBLACK LEVEE, 
WABASH RIVER, IN 
Location. In Knox and Sullivan Counties, IN, on left 
bank of Wabash River, between miles 134.8 and 151.8 
above mouth. 
Existing project. Construction of two sections of 
earth levee totaling 18 miles in length, three pumping 
plants for disposal of interior drainage, and other 
necessary appurtenances. Length of protection, including 
high ground between the two levee sections, is 18.9 miles 
long. Project protects 15,900 acres of agricultural land 
against a flood equal to that expected to occur 7 times in 
a 100-year period. Cost of the completed pumping plants 
was $2,782,905 all Federal cost and cost of the completed 
levee was $1,663,912 of which $109,200 was non-Federal 
cost and $1,554,712 was Federal cost. The levee project 
was authorized by the 1946 Flood Control Act; pumping 
facilities were authorized by the 1968 Flood Control Act. 
Local cooperation. Section 3 of the Flood Control Act 
of June 22, 1936, as amended, applies. Fully complied 
with for levees and pumping plants. 
Operations during fiscal year. Operation by local 
interests for flood control prevented damages estimated 
at $2,026,000 during 1986 flood season. 
Construction of levees complete and transferred to 
Mason J. Niblack Levee District in January 1965 for 
operation and maintenance. Construction of the pumping 
plants and channel improvements complete and 
transferred to the local sponsor in May 1980. 
11. MILL CREEK, OH 
Location. Proposed project is located along the 
18-mile length of Mill Creek and three-fourths mile length 
of East Fork in Hamilton County, OH. Lower Mill Creek 
is in the commercial and industrial heart of the 
Cincinnati metropolitan area in the southwestern portion 
of the State. 
Existing project. Eighteen miles of channel improvement, 
2 miles of levees, two pumping plants, modification 
of 29 bridges, and the addition of two pumping units 
at the present Mill Creek Barrier Dam, located near the 
Ohio River, are included in the project. Acquisition and 
development with appropriate landscaping of 620 acres 
along the creek will be provided for high-density urban 
oriented recreational use. Estimated cost of new work 
(1986) is $188,066,000, of which $40,377,000 is 
non-Federal. 
Local cooperation. Section 3, Flood Control Act of 
1936 as amended, applies. In addition, local interests 
must provide without cost to the United States all 
modifications and relocations of buildings, utilities, street 
and foot bridges, sewers, and related and special facilities 
as necessary for construction of project; prevent encroachment 
on improved channels and on ponding areas which 
would impair capacities; at least annually inform interests 
affected as to degree of protection afforded by project, 
and provide guidance and leadership in preventing 
unwise and uneconomical development of flood plain 
areas by encouraging prudent use of floodproofing, land 
regulation planning, or other flood plain management 
techniques to reduce flood losses. Further, with respect 
to the recreational aspects of the project, local interests 
are required to furnish assurances that they will, if 
necessary, pay or contribute in kind, a portion of the cost 
of recreational facilities which, when added to the cost 
of recreation land, would amount to at least 50 percent 
of the total first cost of the recreation land and recreational 
facilities, and assure access to the recreation 
facilities to all on equal terms. An assurance agreement 
covering local cooperation requirements for the project 
consistent with Section 221 of the 1970 Flood Control Act 
and the Uniform Relocation Assistance and Real Property 
Acquisition Policies Act of 1970 was executed by the 
Millcreek Valley Conservancy District February 6, 1975, 
and for the Secretary of the Army March 28, 1975. A 
recreation cost sharing contract was executed by the 
Conservancy District February 25, 1975, and approved 
by the Secretary of the Army May 28, 1975. 
Operations during fiscal year. Engineering studies 
continued. Construction contract for channel Section 2 
was advanced to 99 percent completion. Contract for 
Railraod Relocation and Construction of Channel Section 
4A and Section 3 to Center Hill Road was awarded in 
April 1986 and advanced to 9 percent completion. Flood 
24-4

LOUISVILLE, KY. DISTRICT 
damages estimated at $2,660,000 were prevented during 
the 1986 flood season. 
Design Memoranda, Hydrology & Hydraulics, Concrete 
Aggregate and Stone Protection Sources, and Railroad 
Relocations, General Design Memoranda, Phase I and 
Phase II, Design of Channel - Sections 5 and 7 are complete. 
Construction of channel and levee - Sections 3 and 
7A, Phase I, is complete. Project is about 26 percent complete 
overall. 
12. SOUTHWESTERN JEFFERSON 
COUNTY, KY 
Location. In Jefferson County, KY, on left bank of 
Ohio River from mile 616 to 628.6. 
Existing project. Provides for the construction of 
68,500 feet of levee, 1,550 feet of concrete wall, four 
pumping plants, and other necessary appurtenances. 
Project will provide protection fo 24,100 acres against 
Ohio River floods equal to 1937 flood of record with 3-foot 
freeboard. Estimated cost of new work (1986) is 
$67,521,000, of which $57,604,000 is Federal, and 
$9,917,000 is non-Federal. Project was authorized under 
Flood Control Act of August 1968. Recreation as a project 
purpose has been deferred until such time as a water 
quality problem on Pond Creek is corrected. 
Local cooperation. Section 3 Flood Control Act of 
1936 as amended applies. In addition, local interests must 
agree to administer project land and water areas for 
recreation and fish and wildlife enhancement; and to pay, 
contribute in kind or repay (which may be through user 
fees) with interest, one-half of the separable first cost of 
the project allocated to recreation and fish and wildlife 
enhancement; and bear all costs of operation, 
maintenance and replacement of lands and facilities for 
recreation and fish and wildlife enhancement. Jefferson 
County Fiscal Court expressed intent to fulfill requirement 
by resolution dated April 4, 1967. Formal 
assurances of local cooperation for the flood protection portion 
of the project was executed by resolution of Jefferson 
County Fiscal Court, adopted September 17, 1971, and 
assurances for the recreation portion of the project were 
executed by similar resolution, adopted September 14, 
1971. Authorization-of-entry for levee and floodwall sections 
1, 2, 3, 4, 4A, 5 and Pond Creek Pump Plant have 
been furnished. 
Operations during fiscal year. Engineering studies 
continued. Two contracts for construction of railroad 
closure at levee Section 4 and for construction of levee 
and floodwall Section 4 were both advanced to completion. 
Contract for Pond Creek Pumps and Motors, awarded 
in May 1985, was advanced to two percent completion. 
Contract for Levee Section 5 and Pond Creek Pumping 
Station awarded in September 1985 was advanced to 24 
percent completion Contract for Remedial Work for 
Railroad Closure at Levee Section 5 was awarded in 
September 1986. 
Engineering studies are about 98 percent complete. 
Construction of levee and floodwall Sections 1, 2, 3 and 
4A; electric service for gatewells; Riverport and Upper 
and Lower Mill Creek pumping plants; rehabilitation of 
pump stations; and relocation of Texas Gas pipeline are 
complete. Project is 72 percent complete overall. 
Flood Control - Reservoirs 
13. BARREN RIVER LAKE, KY 
Location. Dam is on Barren River, 79.5 miles above 
its confluence with Green River and 10 miles northeast 
of Scottsville, KY. At flood control pool reservoir extends 
upstream about 40 miles in Barren and Allen Counties, 
KY. (See U.S. Geological Survey map of Lucas, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is rolled earth and rockfill, 146 feet 
high and 3,970 feet long, with gate-controlled outlet works 
and uncontrolled open-cut spillway. Total storage capacity 
is 815,200 acre-feet (768,000 for flood control and 46,600 
for water supply storage). For further details, see page 
1125 of Annual Report for 1962. Cost of the completed 
project is $27,479,717 including $2,335,055 Federal funds 
and $108,418 non-Federal funds for construction of recreation 
facilities under the completed projects program. Project 
was authorized by Flood Control Act of 1938. 
Local cooperation. None required by authorizing act. 
Under provision of Water Supply Act of 1958, contract 
with City of Glasgow for water supply storage was 
approved by Secretary of Army on October 4, 1965. Terms 
require City to pay $23,433, which is project cost allocated 
to water storage plus capitalized prepayment of proportionate 
share of operation, maintenance, and major 
replacement costs. A contract, with the Commonwealth 
of Kentucky for development of additional campsites, 
shoreline protection and breakwater extension at Barren 
River Lake State Park under the cost-sharing category 
of the completed projects program was approved by the 
Secretary of the Army November 4, 1977. 
Operations during fiscal year. New work: None. 
Maintenance: Contract for control tower maintenance and 
bulkhead modification was awarded. Routine 
maintenance was performed. Operation for flood control 
during the 1986 flood season prevented damages of 
$81,000. 
Construction started in March 1960 and all major construction 
and relocation items were completed in October 
1964. Project was placed in operation in March 1964. 
Land acquisition is complete. 
14. BROOKVILLE LAKE, IN 
Location. Damsite is on East Fork of Whitewater 
River, 2.4 miles above confluence with West Fork, and 
about 1-1/2 miles north of Brookville, Indiana. The reservoir 
lies in Franklin and Union Counties, Indiana. (See 
U.S. Geological Survey map of Brookville, IN.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is earthfill, 182 feet high and 3,004 
feet long, with gate-controlled outlet works, and uncontrolled 
open spillway. Total storage capacity is 359,600 
acre-feet (214,700 for flood control, 89,300 for water supply, 
and 35,500 for conservation). A minimum pool of 
24-5

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
20,100 acre-feet is maintained. Estimated cost of new 
work (1986) is $45,382,551 of which $37,803,813 is 
Federal cost and $7,578,738 is non-Federal contribution 
for water supply storage. Project was authorized by 1938 
Flood Control Act. 
Local cooperation. None required by authorizing act. 
Contract with State of Indiana for water supply storage 
under provisions of Water Supply Act of 1958 was 
approved by Secretary of Army, August 5, 1965. Under 
terms of contract, State paid initial costs allocated to 
water supply feature of project plus capitalized prepayment 
of proportionate share of operation and maintenance 
costs. 
Operation during fiscal year. New work: None. 
Maintenance: Installation of hydropower unit is complete 
but is not in operation pending finalization of contract 
with Southeastern Power Administration for purchase of 
surplus power. Routine maintenance was performed. 
Operation for flood control during the 1986 flood season 
prevented damages of $58,000. 
Construction was started in November 1965 and project 
was placed in operation January 1974. Construction 
and land acquisition are complete. 
15. BUCKHORN LAKE, KY 
Location. Dam is on Middle Fork of Kentucky River, 
43.4 miles above mouth, and 0.5 mile upstream from 
Buckhorn, Perry County, KY. Reservoir extends 
upstream about 34 miles and lies in Leslie and Perry 
Counties, Kentucky. (See U.S. Geological Survey map of 
Buckhorn, KY.) 
Existing project. A reservoir for flood control and 
recreation. Dam is earth and rockfill type, with gate controlled 
outlet works. Total storage capacity is 168,000 
acre-feet, of which 157,600 is for flood control. For further 
details, see page 1120 of Annual Report for 1962. 
Cost of completed new work is $11,766,206 including 
$386,707 for construction of recreation facilities under the 
completed projects program. Existing project was 
authorized by general authorization for Ohio River Basin 
in 1938 Flood Control Act. 
Local cooperation. Department of Parks of the Commonwealth 
of Kentucky has undertaken management of 
lands and recreational facilities in accordance with license 
granted by Secretary of the Army on June 29, 1962. 
Operations during fiscal year. New work: None. 
Maintenance: A contract was awarded and completed for 
emergency spillway clearing and road resurfacing. 
Routine maintenance was performed. Operation for flood 
control during the 1986 flood season prevented damages 
of $205,000. 
Construction started in September 1956 and project was 
placed in operation in August 1960. All construction and 
land acquisition is complete. 
16. CAESAR CREEK LAKE, OH 
Location. Damsite is on Caesar Creek, about 3.0 
miles above its confluence with Little Miami River, in 
Warren County, OH, about 3.5 miles southeast of 
Waynesville, OH, and 10.5 miles northeast of Lebanon, 
OH. Reservoir lies in Warren, Clinton, and Green 
Counties, OH. (See U.S. Geological Survey map of 
Oregonia, OH.) 
Existing project. Provides for construction of a reservoir 
for flood control and allied purposes. It includes an 
earth and rockfill dam, four saddle dams, outlet works 
and an uncontrolled saddle spillway. Total storage capacity 
of reservoir is 242,200 acre-feet, of which 148,500 acrefeet 
is reserved for flood control storage. Estimated cost 
of new work (1986) is $64,781,000 including $5,037,000 
non-Federal reimbursement for water supply storage. Existing 
project was authorized by general authorization for 
Ohio River Basin in 1983 Flood Control Act. 
Local cooperation. None required. However, the 
State of Ohio requested inclusion in the project of storage 
for future municipal and industrial water supply uses. 
Contract with State of Ohio for water supply storage 
under provisions of Water Supply Act of 1958, as amended, 
was approved by Secretary of the Army, May 20, 1970. 
Under terms of contract, State will reimburse the Federal 
Government for costs allocated to water supply storage 
over a period not to exceed 50 years after use of this 
storage is initiated plus estimated annual amount for cost 
of operation, maintenance and major capital replacements 
required for the water supply facilities. 
Operations during fiscal year. New work: Engineering 
and design studies continued. Contract for Tailwater 
Conversion awarded in September 1985 was advanced to 
completion. Maintenance: Routine maintenance was 
performed. Flood damages estimated at $1,481,000 were 
prevented during the 1986 flood season. 
Construction was started in January 1968 and the project 
was placed in operation January 1978. Land acquisition 
is complete. All relocation and construction features 
are complete. Project is about 99 percent complete overall. 
17. CAGLES MILL LAKE, IN 
Location. Dam is on Mill Creek, 2.8 miles above its 
confluence with Eel River, in Putnam County, IN, and 
about 25 miles east of Terre Haute, IN. Reservoir extends 
upstream about 11 miles and is in Putnam and Owen 
Counties, IN. (See U.S. Geological Survey map of Poland, 
IN.) 
Existing project. A reservoir for flood control and 
recreation. Dam is earth and rockfill embankment. Total 
storage capacity is 228,100 acre-feet, of which 201,000 
acre-feet are for flood control. For details see Annual 
Report for 1962, page 1136. Estimated cost of new work 
(1986) is $4,263,184 including $155,416 Federal funds and 
$106,813 non-Federal funds for construction of recreation 
facilities under the completed projects program. Existing 
project was selected for construction under general 
authorization for Ohio River Basin in 1938 Flood Control 
Act. 
Local cooperation. None required. State of Indiana 
has undertaken development and management of recreation 
facilities for use of the public in reservoir area in accordance 
with license granted by Secretary of the Army 
on January 17, 1952. A contract with the Indiana Depart- 
24-6

LOUISVILLE, KY. DISTRICT 
ment of Natural Resources for expanding the boat ramp 
and parking area at Site 3, Lieber State Park, under the 
cost sharing category of the completed projects program 
was signed by the State of Indiana on August 26, 1981 
and approved by the Deputy Chief of Engineers on 
March 26, 1982. 
Operations during fiscal year. New Work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1986 flood season 
prevented damages of $3,227,000. 
Construction started in July 1948 and completed in 
June 1953. 
18. CARR FORK LAKE, KY 
Location. Damsite is 8.8 miles above mouth of Carr 
Fork, a tributary of North Fork of Kentucky River, 16 
miles upstream from Hazard, KY. The reservoir lies entirely 
within Knott County. (See U.S. Geological Survey 
maps of Carrie and Vicco, KY.) 
Existing project. Provides for construction of a reservoir 
for flood control and allied purposes. Dam is rock and 
earth fill with impervious core, 720 feet long and 130 feet 
high, with uncontrolled open cut spillway through left 
abutment. Outlet works has two control gates and 8-foot 
diameter conduit to stilling basin. Total storage capacity 
is 47,700 acre-feet (31,600 for flood control and 4,300 
for water quality control). A higher level seasonal pool 
for recreation is provided. Estimated Federal cost of new 
work (1986) is $50,854,826 including $76,724 for recreation 
facilities under the completed projects program. Project 
was authorized by the 1962 Flood Control Act. 
Local cooperation. None required for reservoir 
project. Division of Flood Control and Water Usage of 
Commonwealth of Kentucky gave assurance that encroachments 
on downstream channel capacity will be 
prevented. 
Operations during fiscal year. New work: Real 
estate administrative action required for condemnation 
of remaining tracts was continued. Maintenance: Contract 
work continued on modification of hydraulic system. 
Routine maintenance was performed. Operation for flood 
control during the 1986 flood season prevented damages 
of $237,000. 
Condition at end of fiscal year. Project was placed 
in operation January 1976. Construction started in 
January 1966 is complete. All land required for the project 
has been acquired; however, a number of condemnation 
actions remain unsettled. 
19. CAVE RUN LAKE, KY 
Location. Damsite is on Licking River, about 4 miles 
upstream from U. S. Highway 60 near Farmers, KY, and 
7 miles southwest of Morehead, KY. Reservoir will be in 
Rowan, Bath, Morgan, and Menifee Counties, KY. (See 
U.S. Geological Survey maps of Salt Lick and Morehead, 
KY.) 
Existing project. Plan provides for construction of a 
reservoir for flood control and allied purposes. Dam is rolled 
earthfill, with gate controlled outlet works and uncontrolled 
open spillway. Total storage capacity is 614,700 
acre-feet (438,500 for flood control and 28,300 for water 
quality control). Estimated Federal cost of new work 
(1986) is $114,826,300 of which $35,213,000 is U. S. Forest 
Service cost. Project was authorized by Flood Control Acts 
of June 22, 1936 and June 28, 1938. 
Local cooperation. None required. 
Operations during fiscal year. New work: None. 
Real estate administrative action required for acquisition 
of remaining tracts was continued. Contract for Zilpo 
recreation buildings, part I (4 bathhouses) was advanced 
to completion. Contract for tailwater comfort station conversion 
awarded in August 1985 was advanced to completion. 
Contract for Zilpo Recreation Buildings and Paving 
was awarded in November 1986 and advanced to 74 
percent completion. Maintenance: Routine maintenance 
was performed. Operation for flood control during the 
1986 flood season prevented damages of $1,762,000. 
Project has been in operation since February 1974. 
Construction was started in June 1965 and is about 92 
percent complete overall. Land acquisition is complete 
except for outstanding condemnation actions. All 
relocation and construction features are complete 
except recreation facilities. 
20. CECIL M. HARDEN LAKE, IN 
Location. Dam is on Raccoon Creek, 32.4 miles above 
its confluence with Wabash River, and 25 miles northeast 
of Terre Haute, IN. At flood control pool, reservoir extends 
upstream about 15 miles in Parke and Putnam Counties, 
Indiana. (See U. S. Geological Survey Map of Mansfield, 
IN.) 
Existing project. A rolled earth dam and reservoir, 
for flood control and allied purposes. Total storage 
capacity is 132,800 acre-feet of which 116,600 acre-feet 
are for flood control. For details, see Annual Report for 
1962, page 1132. Cost of completed new work is 
$6,987,807 made up of $6,260,134 for the initial project 
and $373,678 Federal cost and $353,995 non-Federal 
contribution in kind for recreation facilities under the 
completed projects program. Project was selected for construction 
under general authorization for Ohio River 
Basin in 1938 Flood Control Act. Project name was changed 
from Mansfield Lake to Cecil M. Harden Lake by 
Public Law 93-521, December 14, 1974. 
Local cooperation. State of Indiana has undertaken 
management of lands and recreational facilities in 
accordance with license granted by Secretary of the Army 
on April 19, 1961. A contract with the Indiana Department 
of Natural Resources, approved by the Secretary of 
the Army in May 1974, provided for that agency to design 
and construct certain additional recreation facilities at 
Cecil M. Harden, Huntington, Mississinewa, Monroe and 
Salamonie Lakes under the cost sharing category of the 
completed projects program. 
Operations during fiscal year. New work: None. 
Maintenance: Contract work was completed for replacement 
of control tower roof. Routine maintenance was per- 
24-7

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
formed. Flood damages of $1,939,000 were prevented during 
the 1986 flood season. 
Construction started in October 1956 and all major 
items of work were completed December 1961. Land acquisition 
is complete. Project has been in operation since 
August 1960. Cost shared recreation facilities constructed 
by the State of Indiana under the completed projects program 
are completed. 
21. CLARENCE J. BROWN DAM & 
RESERVOIR, OH 
Location. Damsite is just east of Springfield, Clark 
County, OH, at mile 7.3 of Buck Creek, a tributary of Mad 
River. (See U. S. Geological Survey maps of New 
Moorefield and Springfield, OH.) 
Existing project. A reservoir for flood control and 
allied purposes. It includes an earthfill dam, 6,620 feet 
long and 72 feet high, with gated outlet works and open 
cut spillway with concrete chute through right abutment. 
Total storage capacity of reservoir is 63,700 acre-feet 
(32,900 for flood control and 20,800 for water quality control). 
Federal cost of completed project is $22,083,660. Project 
was authorized by 1962 Flood Control Act. Project 
name was changed from Buck Creek Dam and Reservoir 
to Clarence J. Brown Dam and Reservoir by Public Law 
90-46, July 4, 1967. 
Local cooperation. Assurances from City of 
Springfield, Springfield Conservancy District, and Clark 
County, Ohio, covering protection against detrimental 
channel encroachment below dam to mouth of Buck 
Creek, were accepted March 5, 1964. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Construction started in September 1966. Land acquisition 
and all major project features were completed in 
November 1973. The project was placed in operation in 
January 1974. 
22. GREEN RIVER LAKE, KY 
Location. Damsite is 305.7 miles above mouth of 
Green River in Taylor County, KY, about 8 miles south 
of Campbellsville. Reservoir lies in Taylor and Adair 
Counties. (See U. S. Geological Survey map of Cane 
Valley, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is earth and rock-fill, 141 feet high 
and 2,350 feet long. Outlet works is slide gate-controlled 
and spillway open and uncontrolled. Total storage 
capacity is 723,200 acre-feet (560,600 for flood control and 
64,500 for low-flow augmentation). Cost of completed new 
work is $33,606,061, including $317,145 Federal funds 
and $183,732 non-Federal funds for construction of recreation 
facilities under the completed projects program. 
Existing project was authorized under general authorization 
for Ohio River Basin in 1938 Flood Control Act. 
Local cooperation. None required by authorizing act. 
Taylor County, by lease approved by Secretary of Army 
February 15, 1968, undertook operation and maintenance 
of Smith Ridge public access area. In May 1980, the lease 
was amended to turn back responsibility for maintenance, 
and operation of 99 percent of the site to the Corps, with 
the County retaining responsibility for the marina area. 
Under provision of Water Supply Act of 1958, contract 
with City of Campbellsville for water supply storage was 
approved by Secretary of Army April 23, 1969. Terms require 
city to repay, with interest and annual charges for 
operation, maintenance and major replacement, the investment 
cost of $85,765 allocated to its water supply 
storage space. Total payments received through fiscal 
year 1984 was $21,504. The Department of Parks of the 
Commonwealth of Kentucky, by lease approved by 
Secretary of Army, October 4, 1971, has undertaken the 
management of the Lone Valley public access area. 
Operations during fiscal year. New work: None. 
Maintenance: Contract for construction of new office 
building advanced to completion, as well as contracts for 
installation of new boiler and roof replacement of visitor's 
center and shop. Routine maintenance was performed. 
Operation for flood control prevented damages estimated 
at $219,000 during the 1986 flood season. 
Construction began in August 1965 and all major construction 
and relocation items were completed in 1972. 
Project has been in operation since February 1969. Project 
including all land acquisition complete in 1973. 
Construction of sanitary dump station for boats at Dam 
Site in conformance with EPA and State standards and 
rehabilitation of sewage treatment facilities, washhouses 
and restrooms at Smith Ridge site js complete. 
23. HUNTINGTON LAKE, IN 
Location. Damsite is on Wabash River, about 2 miles 
from Huntington, IN, and 411.4 miles above mouth. 
Reservoir is in Huntington and Wells Counties, IN. (See 
U. S. Geological Survey maps of Majenica and Mt. Etna, 
IN.) 
Existing project. A reservoir for flood control and 
recreation. Dam consiste of a rolled earth embankment 
4,700 feet long and 89 feet high, a concrete spillway and 
outlet section 155 feet long, and a concrete gravity section 
310 feet long. Spillway is controlled by three gates, 
and outlet works by six sluices. Project also provides local 
flood protection for Markle, IN. Total storage capacity of 
reservoir is 153,100 acre-feet, of which 149,000 acre-feet 
is reserved for flood control storage. Estimated cost for 
new work (1986) is $19,777,863 made up of $19,273,252 
Federal cost for the initial project and $193,903 non- 
Federal contributed funds for low flow augmentation 
storage, and $155,354 Federal cost and $155,354 non- 
Federal contribution in kind for recreation facilities under 
the completed projects program. Project was authorized 
by Flood Control Act of 1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to one percent of project first 
cost. State of Indiana has met this obligation. Contract 
with the Indiana Department of Natural Resources, 
approved by the Secretary of the Army May 17, 1974, provided 
for that agency to design and construct certain 
additional recreational facilities at Cecil M. Harden, 
24-8

LOUISVILLE, KY. DISTRICT 
Huntington, Mississinewa, Monroe and Salamonie Lakes 
under the cost shared category of the completed projects 
program. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control prevented damages estimated 
at $1,434,000 during the 1986 flood control season. 
Land acquisition and all major construction complete. 
Project was placed in operation January 9, 1969. Cost 
shared recreation facilities constructed by the State of 
Indiana under the completed projects program are 
complete. 
24. MISSISSINEWA LAKE, IN 
Location. Damsite is 7.1 miles above mouth of 
Mississinewa River, which flows into Wabash River about 
2 miles upstream from Peru, IN. At flood control pool 
level, reservoir extends upstream about 28 miles, in 
Wabash, Grant, and Miami Counties, IN. (See U.S. 
Geological Survey map of Peoria, IN.) 
Existing project. Provides for construction of a reservoir 
for flood control and allied purposes. It includes an 
earthfill dam 137 feet high and 8,100 feet long, gatecontrolled 
outlet works, and an uncontrolled open 
spillway through right abutment. Total storage capacity 
of reservoir is 368,400 acre-feet, of which 345,100 acrefeet 
are reserved for flood control storage. Estimated project 
cost for new work (1986) is $24,596,129 made up of 
$23,578,145 Federal cost for the initial project and 
$239,200 non-Federal contributed funds for low flow 
augmentation storage and $389,392 Federal cost and 
$389,382 non-Federal contribution in kind for recreation 
facilities under the completed projects program. Project 
was authorized by the Flood Control Act of 1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to 1 percent of project first cost. 
State of Indiana assumed this obligation. A contract with 
the Indiana Department of Natural Resources, approved 
by the Secretary of the Army in May 1974, provided for 
that agency to design and construct certain additional 
recreation facilities at Cecil M. Harden, Huntington, 
Mississinewa, Monroe and Salamonie Lakes under the 
cost sharing category of the completed projects program. 
Operations during fiscal year. New work: None 
Maintenance: Routine maintenance was performed. 
Operation for flood control prevented damages of 
$6,463,000 during 1986 flood season. 
Construction and land acquisition is complete. Project 
was placed in operation in May 1968. Cost shared recreation 
facilities cconstructed by the State of Indiana under 
the completed projects program are complete. 
25. MONROE LAKE, IN 
Location. Dam is on Salt Creek, a tributary of White 
River, 25.9 miles above mouth, and 2 miles each of 
Harrodsburg, Monroe County, IN. At flood control pool 
level, reservoir will extend upstream 44 miles in Monroe, 
Brown, and Jackson Counties. (See U.S. Geological 
Survey map of Clear Creek, IN.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is earth core and rock shell, with 
gate-controlled outlet works and uncontrolled open 
spillway. Total storage capacity is 441,000 acre-feet 
(258,800 for flood control and 159,900 for low flow 
augmentation.) Cost of completed new work is 
$16,569,589 made up of $7,032,484 Federal cost for the 
initial project and $7,797,604 non-Federal contributed 
funds for low-flow regulation storage and $$70,343 
Federal cost and $869,158 non-Federal contribution in 
kind for recreation facilities under the completed projects 
program. Project was authorized by 1958 Flood Control 
Act, modifying comprehensive plan for Ohio River Basin. 
Local cooperation. Section 3, 1944 Flood Control Act 
applies. Local interests must contribute 54.1 percent of 
project cost, this being the proportion allocated to low-flow 
regulation feature, plus a capitalized amount 
representing that part of average annual maintenance 
and operation cost allocated to low-flow regulation. State 
of Indiana assumed this cost sharing obligation. A contract 
with the Indiana Department of Natural Resources, 
approved by the Secretary of the Army in May 1974, provided 
for that agency to design and construct certain 
additional recreation facilities at Cecil M. Harden, 
Huntington, Mississinewa, Monroe and Salamonie Lakes 
under the cost sharing category of the completed projects 
program. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control prevented damages of $716,000 
during 1986 flood season. 
Project is complete and was placed in operation in 
February 1965. Cost shared recreation facilities constructed 
by the State of Indiana under the completed 
projects program are complete. 
26. NOLIN LAKE, KY 
Location. Dam is on Nolin River 7.8 miles above its 
confluence with Green River, about 70 air miles 
southwest of Louisville, KY. Reservoir extends upstream 
about 57 miles and is in Edmonson, Grayson, Hart, and 
Hardin Counties, KY. (See U.S. Geological Survey maps 
of Nolin Reservoir and Dickeys Mill, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is rockfill-earth core type with gatecontrolled 
outlet works, and uncontrolled open spillway. 
Total storage capacity is 609,400 acre-feet, of which 
545,600 acre-feet is for flood control. For further details 
of project see Annual Report for 1962, page 1124. 
Estimated Federal cost of new work (1986) is $17,193,381 
including $2,596,317 for construction of recreation 
facilities. Project was selected for construction under 
general authorization for Ohio River Basin in 1938 Flood 
Control Act. 
Local cooperation. None required for authorized 
project. State of Kentucky contributed $18,195 for 
increased width of dam for public road. 
Operations during fiscal year. New work: None. 
Maintenance: Contract for control tower maintenance and 
24-9

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
bulkhead modification was awarded. Rountine 
maintenance was performed. Operation for flood control 
during the 1986 flood season prevented damages 
estimated at $47,000. 
Construction started in January 1959. Project was completed 
and placed in operation in March 1963. 
27. OHIO RIVER BASIN 
(Louisville District) 
Location. Works covered by this project are a series 
of levees, floodwalls, channel improvements, and reservoirs 
in Ohio River Basin within Louisville District. 
Existing project. Individual projects considered in 
comprehensive plan within the Louisville District. (See 
Table 24-B for authorizing leglsiation, and Table 24-I for 
cost and listing of projects in the basin plan.) 
Operations during fiscal year. No costs were 
incurred except for these projects for which individual 
reports are given. 
28. PATOKA LAKE, IN 
Location. Damsite is in Dubois County, IN, 118.3 
miles above mouth of Patoka River, and 50 miles westnorthwest 
of New Albany, IN. Reservoir extends into 
Dubois, Orange and Crawford Counties. (See Geological 
Survey map of Cuzco, IN.) 
Existing project. Reservoir for flood control and allied 
purposes. Dam is earth and rock fill, 1,550 feet long and 
85 feet high, with gate-controlled outlet works and uncontrolled 
open spillway. Total storage capacity is 301,600 
acre-feet (121,000 for flood control and 167,500 for water 
supply and water quality control). Estimated cost of new 
work (1986) is $78,417,700 of which $1,361,200 is Federal 
cost for emergency remedial measures and to clear and 
snag the Patoka River downstream of Patoka Lake, which 
work was directed by Congress in 1981; $51,507,800 is 
Federal cost for other construction, and $25,548,700 is 
non-Federal contribution for water supply storage and 
recreation facilities. Project was authorized by 1965 Flood 
Control Act, and emergency measures and snagging and 
clearing the Patoka River downstream of Patoka Lake 
to insure effective operation of the project for flood control 
was directed by 1981 Appropriation Act for Energy 
and Water Development. 
Local cooperation. Local interests are required to 
reimburse the Federal Government for costs allocated to 
water supply storage over a period not to exceed 50 years 
after use of this storage is initiated, presently estimated 
at 29.316 percent of the joint-use facilities cost, exclusive 
of interests, plus $287,000 for the cost of operating and 
maintaining water supply storage for a period of 50 years, 
plus $42,000 for the cost of major capital replacements 
required for water supply storage space for a period of 50 
years. Local interests are also required to pay, contribute 
in kind, or repay (which may be through user fees) with 
interest, one-half of the separable first cost of the project 
allocated to recreation. Present laws of the State of 
Indiana require that agency to make cash contributions 
during construction of the project. Local interests must 
also agree to prevent encroachments on channel of Patoka 
River from dam to mouth, and to pay allocated initial and 
annual maintenance and operation costs for water supply 
storage. Formal assurances of local cooperation, executed 
by the Indiana Natural Resources Commission, were 
accepted August 27, 1970. Contracts with State of Indiana 
for water supply and recreation were approved by the 
Secretary of the Army November 2, 1970. 
Operations during fiscal year. New work: Contract 
for construction of Jackson Site Access Road, awarded in 
November 1983, was advanced to completion. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1986 flood season 
prevented damage estimated at $989,000. 
Construction was started in July 1972. Engineering 
studies are complete. Land acquisition is about 99 percent 
complete. All major features are complete. Permanent 
impoundment was started in February 1978 and the 
project was placed in operation about August 1980. The 
project is about 99 percent complete overall. 
29. ROUGH RIVER LAKE AND 
CHANNEL IMPROVEMENT, KY 
Location. Dam is on Rough River, 89.3 miles above 
its confluence with Green River 160.3 miles above Ohio 
River, and about 60 miles southwest of Louisville, KY. 
Reservoir extends upstream about 30 miles and is in 
Breckinridge, Hardin, and Grayson Counties, KY. Channel 
improvement work is on Rough River, Barnett Creek, 
and West Fork of Barnett Creek. (See U.S. Geological 
Survey maps of McDaniels and Falls of Rough, KY.) 
Existing project. Reservoir is for flood control and 
allied purposes. Dam is rolled earthfill type, with gatecontrolled 
outlet works. Storage capacity is 334,380 acrefeet, 
of which 314,210 acre-feet is for flood control. Project 
also includes channel clearing of lower Rough River, and 
channel improvement on Barnett Creek, a tributary of 
Rough River. For further details see page 1126 of Annual 
Report for 1962. Cost of completed new work is 
$10,643,001 including $890,008 Federal funds and 
$22,612 non-Federal funds for construction of recreation 
facilities under the completed projects program. Existing 
project was selected for construction under general 
authorization for Ohio River Basin in 1938 Flood Control 
Act. Modification of previously approved plan to include 
channel improvement items was authorized by the 
1944 Flood Control Act. 
Local cooperation. None required for construction of 
reservoir unit. Provisions of Section 3, Flood Control Act 
of 1936, are applicable to channel improvements. 
Assurances were obtained from Ohio County for channel 
improvement. Department of Parks, Commonwealth of 
Kentucky, has undertaken management of certain lands 
and recreation facilities in accordance with license 
granted by Secretary of the Army on August 18, 1961. 
A contract with the Commonwealth of Kentucky to improve 
and pave road at the Below Dam Area - State Park 
under the cost sharing category of the completed projects 
program was approved by the Secretary of the Army 
November 4, 1977. 
24-10

LOUISVILLE, KY. DISTRICT 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1986 flood season 
prevented damages estimated at $2,564,000. 
Construction started in November 1955 and reservoir 
was placed in operation in June 1959. Land acquisition 
and all major items of construction and relocation are 
complete. 
30. SALAMONIE LAKE, IN 
Location. Damsite is 3.1 miles above mouth of 
Salamonie River which enters Wabash River about 6 
miles upstream from Wabash, IN. Reservoir extends 
upstream about 27 miles at flood control pool and lies in 
Wabash and Huntington Counties, IN. (See U. S. 
Geological Survey maps of Lagro and Majenica, IN.) 
Existing project. Provides for construction of a reservoir 
for flood control and allied purposes. It includes an 
earthfill dam with a maximum height of 133 feet and and 
length of 6,100 feet, gate-controlled outlet works with a 
16-foot diameter conduit and an uncontrolled open 
spillway through right abutment. Total storage capacity 
of reservoir is 263,600 acre-feet, of which 250,500 acrefeet 
is for flood control storage. Estimated project cost for 
new work (1986) is $17,046,151 made up of $16,244,356 
Federal cost for the initial project and $170,697 non- 
Federal contributed funds for low-flow augmentation 
storage and $315,549 Federal cost and $315,549 non- 
Federal contribution in kind for recreation facilities under 
the completed projects program. Project was authorized 
by Flood Control Act of 1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to one percent of project first 
cost. State of Indiana assumed this obligation. A contract 
with the Indiana Department of Natural Resources, 
approved by the Secretary of the Army in May 1974, provided 
for that agency to design and construct certain 
additional recreation facilities at Cecil M. Harden, 
Huntington, Mississinewa, Monroe, and Salamonie Lakes 
under the cost sharing category of the completed projects 
program. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. During 
the 1986 flood season, operation for flood control 
prevented damages of $5,167,000. 
Land acquisition and all major construction and relocation 
contracts are complete. Reservoir was placed in 
operation in spring 1967. Cost shared recreation facilities 
constructed by the State of Indiana under the completed 
projects program are complete. 
31. TAYLORSVILLE LAKE, KY 
Location. Damsite is in Spencer County, KY, 60.0 
miles above the confluence of Salt River and Ohio River, 
4 river miles above Taylorsville and 36.9 river miles 
above Shepherdsville, KY. (See U. S. Geological Survey 
map of Taylorsville, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam will be an earth and rock fill structure, 
164 feet high and 1,280 feet long. Outlet works will 
be slide gate controlled and spillway will be uncontrolled 
open cut. Total storage capacity will be 291,670 acre-feet 
(211,230 for flood control, winter months), and 52,245 for 
water quality and fish and wildlife. Estimated cost of new 
work (1986) is $119,262,000 made up of $92,225,000 
Federal cost for the initial project and $16,025,000 non- 
Federal contributed funds for initial recreation facilities 
and $5,506,000 Federal cost and $5,506,000 non-Federal 
contributed funds for recreation facilities under the completed 
projects program. Project was authorized by 1966 
Flood Control Act. 
Local cooperation. Local interests must agree to administer 
project land and water areas for recreation; pay, 
contribute in kind, or repay (which may be through user 
fees) with interest one-half of the separable first costs of 
the project allocated to recreation; bear all costs of operation, 
maintenance, and replacement of recreation lands 
and facilities. Local interests must also agree to prevent 
encroachments on flow-carrying capacities of stream 
channels below the reservoir to the extent needed to provide 
reasonably effective reservoir operation. Commonwealth 
of Kentucky has indicated intent to fulfill requirements 
for recreation cost sharing and has assumed 
responsibility for channel encroachments and pollution 
control. The Commonwealth furnished assurance 
agreements covering prevention of encroachment on 
capacity of stream channels in April and May 1973 and 
executed the recreation cost sharing contract in April 
1973. On April 2, 1980 the U. S. District Court for the 
Western District of Kentucky ruled that the 1973 recreation 
cost sharing contract between the Commonwealth 
and the United States that provded for repayment after 
completion was invalid under the Kentucky Constitution 
which prohibits one General Assembly from obligating 
future appropriations that would be binding on a subsequent 
legislature. In response to the Court's ruling, the 
Commonwealth and the United States entered into a new 
contract providing for cash contributions. Contract was 
approved by the Secretary of the Army June 11, 1980. The 
contract was found to be valid and enforceable by the 
Court July 14, 1980. 
Operations during fiscal year. New work: Engineering 
and design studies and land acquisition continued. 
Contract for Tower and Vistor's Center Repair advanced 
to completion. Contract for final paving of relocated state 
highways and Settlers Trace access road and parking lot 
repairs advanced to 99 percent completion. During the 
1986 flood season operation for flood control prevented 
damages of $470,000. 
Engineering and design studies are about 89 percent 
complete and land acquisition is about 96 percent complete. 
Construction was started in June 1974. All major 
construction items are complete except utility relocations, 
final paving of state highways and recreation facilities. 
The dam gates were closed in January 1983 for permanent 
impoundment. Dedication ceremony was May 28, 
1983. The project is about 87 percent complete overall. 
32. WABASH RIVER BASIN 
Location. Works covered by this project are located 
24-11 .

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
in the Wabash River Basin, a drainage area of 33,100 
square miles, covering parts of Indiana, Illinois and Ohio. 
Existing project. One local protection project and five 
reservoir projects were authorized for this basin plan. (See 
Table 24-B for authorizing legislation and Table 24-J for 
project list and total cost of basin plan.) 
33. WEST FORK OF MILL 
CREEK LAKE, OH 
Location. Dam is on West Fork of Mill Creek 6.5 
miles above its junction with Mill Creek and 2 miles 
northeast of Mount Health, OH, and 10 miles north of 
downtown Cincinnati. Reservoir extends upstream about 
3 miles and is in Hamilton County, OH. (See U. S. 
Geological Survey map of Glendale, OH.) 
Existing project. An earth embankment dam and a 
reservoir for flood control, recreation, and reduction of 
pumping requirements at Mill Creek barrier dam in 
Cincinnati. Total storage capacity of reservoir is 11,300 
acre-feet, of which 9,850 acre-feet is for flood control. For 
further details see page 1119 of Annual Report for 1962. 
Cost of completed new work is $4,722,463 made up of 
$3,092,941 Federal cost for the initial project, $520,800 
non-Federal cost for sewer relocation and dam, $50,000 
non-Federal contributed funds in fulfillment of project 
authorization and $529,361 Federal cost and $529,361 
non-Federal contribution in kind for recreation facilities 
under the completed projects program. Existing project 
selected for construction under additional authorization 
for Ohio River Basin in 1946 Flood Control Act. 
Local cooperation. Local interests were to release 
necessary land under their control and give assurance 
that future channel encroachment below damsite would 
be prevented. For enlargement of reservoir to include a 
conservation pool, local interests would contribute onehalf 
additional cost of such pool, including one-half cost 
of relocation of sanitary sewer, and agree to hold the 
United States free from damages resulting from its provision. 
Board of County Commissioners of Hamilton 
County, Ohio, adopted a resolution October 8, 1947, signifying 
willingness to fulfill requirements including provision 
of conservation pool. Assurances were executed on 
same date. A contract with the United States for relocation 
of sanitary sewer outside reservoir area in order to 
include conservation pool in project was accepted by 
Hamilton County, in which the United States paid onehalf 
cost of such relocation work. Hamilton County 
Commissioners furnished $50,000, required as a local contribution 
toward additional cost of providing conservation 
pool. Hamilton County Park District has undertaken 
development and management of recreation facilities in 
reservoir area for use of the public in accordance with the 
license granted by Secretary of the Army on October 31, 
1951. Contract for cost shared recreation development 
under the completed works program was executed by the 
Board of Park Commissioners, Hamilton County Park 
District, Ohio, in September 1975 and approved by the 
Chief of Engineers in December 1975. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during 1986 flood season 
prevented damages estimated at $147,000. 
Construction started in March 1949 and reservoir was 
placed in operation in December 1952. Project is complete. 
Cost shared recreation development under the completed 
projects program is complete. 
34. WILLIAM H. HARSHA LAKE, OH 
Location. Damsite is on East Fork of Little Miami 
River between Batavia and Williamsburg, OH, about 6.0 
miles above Batavia and 32.6 miles above mouth of the 
Little Miami River. Entire project lies in Clermont 
County, OH. (See U. S. Geological Survey map of Batavia, 
OH.) 
Existing project. A reservoir for flood control and 
allied purposes. It includes an earthfill dam, outlet works, 
an uncontrolled saddle spillway, and a dike to close a saddle 
north of spillway. Total storage capacity of reservoir 
is 294,800 acre-feet, of which 210,600 acre-feet is reserved 
for flood control storage. Estimated cost of new work 
(1986) is $54,932,000 including $3,484,500 non-Federal 
reimbursement for water supply storage. Existing project 
was authorized by general authorization for Ohio River 
Basin in 1938 Flood Control Act. Project name was 
changed from East Fork Lake to William H. Harsha Lake 
effective January 4, 1981 by Public Law 96-383, 
October 6, 1980. 
Local cooperation. None required. However, the 
State of Ohio requested inclusion in the project of storage 
for future municipal and industrial water supply uses. 
Contract with State of Ohio for water supply storage 
under provisions of Water Supply Act of 1958, as amended, 
was approved by Secretary of the Army, May 20, 1970. 
Under terms of contract, State will reimburse the Federal 
Government for costs allocated to water supply storage 
over a period not to exceed 50 years after use of this 
storage is initiated plus estimated annual amount for cost 
of operation, maintenance and major capital replacements 
required for the water supply facilities. 
Operations during fiscal year. New work: Engineering 
and design studies continued. Contract for comfort station 
conversion was completed. Maintenance: Routine 
maintenance was performed. Operation for flood control 
during 1986 flood season prevented damages of 
$1,145,000. 
Construction was started in May 1970. Engineering 
studies are 94 percent complete. All land required for 
project has been acquired. Major relocation and construction 
features are complete, except one recreation item. 
Project is about 95 percent complete overall and was placed 
in operation in February 1978. 
35. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent acts 
require local interests to maintain and operate local 
protection projects in accordance with regulations 
prescribed by Secretary of the Army. Inspections were 
made to determine extent of compliance and to advise in- 
24-12

LOUISVILLE, KY. DISTRICT 
terests as necessary to measures required to correct deficiencies. 
(See Table 24-K for local protection projects and 
channel improvements inspected.) 
Fiscal year costs were $103,745. Total costs to 
September 30, 1986 were $2,780,047. 
36. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 24-E. 
37. FLOOD CONTROL WORKS UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities pursuant to Public 
Law 99, 84th Congress, and antecedent legislation. Costs 
for fiscal year were $155,879 for disaster preparedness, 
$15,753 for emergency operations, and $788,281for repair 
work on eight local protection projects. 
Flood control activities pursuant to Section 205, 1948 
Flood Control Act, Public Law 858, 80th Congress, as 
amended. Costs for fiscal year were $150,439 for preparation 
of initial appraisals, summary fact sheets, and detailed 
project reports on 9 projects, and $669,335 for plans 
and specifications and construction on three projects. 
See Table 24-L. 
Snagging and clearing navigable streams and 
tributaries in interest of flood control (Section 208, 1954 
Flood Control Act, Public Law 780, 83rd Congress). Costs 
for fiscal year were $2,086 for preparation of plans and 
specifications on two projects. 
See Table 24-L. 
Emergency bank protection (Section 14, 1946 Flood Control 
Act, Public Law 526, 79th Congress). Costs for fiscal 
year were $17,000 for preparation of initial appraisals on 
eight projects, $164,196 for plans and specifications and 
construction on two projects. 
See Table 24-L. 
General Investigations 
38. SURVEYS. 
Fiscal year costs were $2,766,525 consisting of 
$1,766,583 for four flood damage prevention studies, 
$652,100 for the Wabash River Navigation Study and 
Grayville Special Report, $76,973 for Special Investigations, 
$25,262 for review of Federal Energy Regulatory 
Commission licenses, $241,017 for planning assistance to 
states, and $4,590 for Deauthorization review study. 
39. COLLECTION AND STUDY 
OF BASIC DATA 
Fiscal year costs were $171,384 for flood plain management 
services. 
40. CONTINUATION OF PLANNING 
AND ENGINEERING 
Fiscal year costs were $634,148 for plan formulation 
and continuation of detailed planning studies on Fairfield, 
Ohio, start of detailed planning and engineering studies 
for Olmsted Locks & Dam, and Holes Creek, West Carrollton, 
Ohio, Local Protection Project. 
24-13

TABLE 24-A 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding 1983 1984 1985 1986 Sep 30, 1986 
Navigation - Locks and Dams 
2 Green and Barren New Work 
Rivers, KY Approp. 
Cost 
Maint. 
Approp. 
Cost 
3 Kentucky River, KY New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
Flood Control - Local Protection 
7 Dayton, KY New Work 
Approp. 
Cost 
8 Evansville, IN New Work 
Approp. 
Cost 
9 Levee Unit No. 5, 
Wabash River, IN 
10 Mason J. Niblack 
Levee, IN 
11 Mill Creek, OH 
12 Southwestern 
Jefferson County, 
KY 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
- $ - $ - $ - $13,808,2221 
- - - - 13,808,2221 
2,069,000 1,516,927 1,987,840 1,238,500 28,102,1122 3 
1,695,152 1,926,628 2,154,447 1,267,516 28,088,0322 4 
- - - - 4,176,749 
- - - - 4,176,749 
1,049,000 1,161,700 1,411,000 2,505,800 48,955,5895 6 
881,140 1,168,626 1,609,460 2,493,699 48,931,7625 
- - - - 556,956 
- - - - 556,956 
153,953 
2,381,000 
3,691,346 
207,000 
510,989 
1,800,000 
1,664,831 
15,100 
76,533 
716,000 
757,338 
105,000 
109,246 
-89,000 
300,448 
13,117,3457 
13,115,9067 
28,376,8568 
28,240,3528 
790,000 -59,600 -89,000 0 7,530,987 
362,983 175,279 473,628 -37,029 7,433,960 
10,825 
16,453 
-1,000 
673 
- 4,337,617 
- 4,337,617 
2,683,600 7,639,900 9,586,000 9,614,000 40,371,742 
5,252,537 6,083,545 10,952,631 10,064,391 39,234,260 
7,028,710 1,420,000 2,430,000 3,484,000 42,345,183 
5,883,989 2,552,857 1,286,893 4,731,054 41,292,419 
Flood Control - Reservoirs 
13 Barren River Lake, KY New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
(Contributed Funds) New Work 
Contrib. 
Cost 
14 Brookville Lake, IN 
(Contributed Funds) 
15 Buckhorn Lake, KY 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp, 
Cost 
1,030,000 
1,054,768 
134,096 
123,811 
360,000 
373,597 
1,077,000 
1,015,488 
-23,000 
28,440 
329,000 
334,843 
1,268,000 
1,322,216 
-56 
409,000 
418,991 
1,189,000 
1,167,073 
27,371,2999 
27,371,2999 
13,416,4261 11 
13,349,89010o 11 
108,41812 
108,41812 
- 37,918,889 
95 37,904,519 
420,000 3,821,189 
410,678 3,805,783 
- 7,592,000 
12 7,578,750 
- - - - 11,766,20613 
- - - - 11,766,20613 
569,000 663,000 640,000 791,500 8,866,91014 
577,485 672,955 651,327 801,081 8,848,48314 
24-14

LOUISVILLE, KY. DISTRICT 
TABLE 24-A 
CONTINUED 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding 1983 1984 1985 1986 Sep 30, 1986 
Flood Control - Reservoirs 
16 Caesar Creek Lake, OH 
17 Cagles Mill Lake, IN 
(Contributed Funds) 
18 Carr Fork Lake, KY 
19 Cave Run Lake, KY 
20 Cecil M. Harden Lake, 
IN 
21 Clarence J. Brown 
Dam & Reservoir, 
OH 
22 Green River Lake, KY 
23 Huntington Lake, IN 
(Contributed Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Contrib 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
$ 804,600 $ -268,000 169,000 - $62,893,882 
1,421,753 1,080,039 320,283 162,680 62,844,167 
539,000 561,000 579,000 631,000 3,852,463 
557,474 515,619 618,053 601,671 3,807,695 
210,701 -100,000 - - 4,263,18415 
32,054 77,972 447 228 4,263,18415 
259,000 317,000 506,000 346,000 4,932,506 
286,789 317,164 489,109 371,968 4,928,272 
- 205,000 - - 205,000 
- 106,813 - - 106,813 
1,279,469 2,627,600 -40,000 - 50,854,82616 
1,196,546 2,697,307 4,993 1,845 50,817,13216 
676,114 781,000 803,000 747,000 6,641,90017 
752,337 776,283 768,785 784,850 6,612,10217 
1,704,800 1,332,000 724,500 - 73,862,282 
1,525,688 543,867 1,381,479 786,628 73,549,240 
420,000 588,000 562,000 485,000 4,355,546 
450,667 583,073 557,164 501,921 4,344,938 
-24,994 - 6,633,81218 
- - - 6,633,81218 
285,000 327,700 312,000 518,400 5,597,496 
294,817 330,662 313,930 500,086 5,573,845 
- - - 22,083,660 
- - - 22,083,660 
291,000 420,000 374,000 379,000 3,636,347 
318,305 373,189 419,925 372,932 3,622,875 
-87 - - 33,422,32919 
5,557 - - 33,422,32919 
955,000 915,500 1,183,000 1,124,000 11,745,74920 
967,808 908,362 1,177,646 1,143,281 11,695,02320 
-53,594 - - - 19,428,60621 
-402 -251 - - 19,427,95321 
419,000 522,000 359,000 483,000 4,695,012 
387,059 584,133 381,804 458,903 4,665,705 
- -- - 193,903 
- -- - 193,812 
24-15

TABLE 24-A 
CONTINUED 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding 1983 1984 1985 1986 Sep 30, 1986 
Flood Control - Reservoirs 
24 Mississinewa Lake, IN 
(Contributed Funds) 
25 Monroe Lake, IN 
(Contributed Funds) 
26 Nolin Lake, KY 
27 Ohio River Basin, 
Louisville District 
28 Patoka Lake, IN 
(Contributed Funds) 
29 Rough River Lake & 
Channel Improvement, 
KY 
(Contributed Funds) 
30 Salamonie Lake, IN 
(Contributed Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
$- 4,914 $ - $ - 
- - -3,003 
275,000 364,000 399,000 
322,806 345,812 331,851 
-24,373 
391,000 
349,406 
-217,719 
-5,336 
-969 
1,050,000 
1,052,033 
416,300 
449,356 
-1,503 
1,222,500 
1,196,882 
308,160 
341,747 
-2,460 
-966 
1,320,000 
1,323,666 
3,003 
411,000 
494,721 
459,600 
467,832
9 
1,337,600 
1,349,294 
$23,967,53722 
23,967,53722 
4,479,105 
4,466,079 
239,200 
237,871 
7,902,82723 
7,902,82723 
5,002,42524 
4,992,19024 
7,797,604 
7,797,604 
17,193,38125 
17,193,38125 
15,357,51526 
15,274,52526 
- 1,526,142 
- 1,526,142 
48,200 
-2,240 
257,000 
285,712 
325,639 
214,515
-8 
18 
1,213,000 
1,280,131 
-208 
1,956 
302,000 
349,336 
43,400 
399,647 
320,000 
312,123 
447,150 
339,137 
90,216 
311,000 
313,500 
76,114 
8,114 
379,000 
385,206 
-29,640 
1,618 
53,080,790 
53,058,435 
2,415,131 
2,401,726 
20,646,649 
20,293,821 
- -- 10,620,38927 
- -- 10,620,38927 
1,304,000 1,288,000 1,095,000 15,514,81028 
1,279,021 1,320,794 1,104,891 15,470,69828 
- - 22,61212 
- - 22,61212 
- - 16,559,90529 
- - - 16,559,90529 
362,000 304,000 444,000 4,587,313 
325,759 349,873 418,578 4,556,464 
- - - 170,697 
- - - 163,867 
24-16

LOUISVILLE, KY. DISTRICT 
TABLE 24-A 
CONTINUED 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding 1983 1984 1985 1986 Sep 30, 1986 
Flood Control - Reservoirs 
31 Taylorsville Lake, KY New Work 
Approp. $8,140,081 $3,200,000 $ 844,400 - $81,296,478 
Cost 7,486,233 4,433,310 1,838,703 516,124 80,527,824 
Maint. 
Approp. 290,000 379,000 468,000 528,000 1,665,000 
Cost 257,702 373,917 489,253 535,625 1,656,497 
(Contributed Funds) New Work 
Contrib. 816,838 - - 228,993 2,000,831 
Cost 370,071 448,100 118,180 249,331 1,735,635 
33 West Fork of Mill New Work 
Creek Lake, OH Approp. - -86,600 - - 3,622,30230 
Cost -55,000 78 - - 3,622,30230 
Maint. 
Approp. 280,000 294,000 264,000 285,000 3,758,889 
Cost 428,961 288,634 289,713 286,138 3,755,637 
(Contributed Funds) New Work 
Contrib. - - - 50,000 
Cost - - 50,000 
34 William H. Harsha New Work 
Lake, OH Approp. - 37,500 -15,000 - 52,023,15731 
Cost 550,103 665,689 69,624 116,209 52,008,62431 
Maint. 
Approp. 428,000 381,000 422,000 481,200 3,179,566 
Cost 440,066 378,829 425,414 482,245 3,161,116 
1 Includes $85,000 public works funds. 
2 Includes $2,000 emergency relief funds, $204,444 
"maintenance and operation of dams and other improvements 
of navigable waters" and $3,842,667 expended from 1888 to 
30 June 1936, for operation and care from permanent indefinite 
appropriation. 
3 Includes $736,767 from Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
4 Includes $731,854 from Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
5 Includes $316,871 under "maintenance and operation of 
dams and other improvements of navigable waters," and 
$6,405,372 expended between July 5, 1885 and June 30, 1937 
on operation and care from permanent indefinite appropriation. 
6 Includes $149,700 from Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
' Includes $12,426 allotted to Bellevue-Dayton and used in 
study of that project. 
8 Includes $11,812 emergency relief funds. 
9 Includes $2,224,948 Code 711 funds and $110,107 Code 713 
funds. 
10 Includes $100,000 Supplemental funds. 
1 Includes $326,900 Special Recreation Use Fees. 
12 Cost sharing for Code 713 recreation facilities. 
13 Includes $61,451 public work acceleration executive 1963 
funds, $143,088 Code 711 funds, and $243,619 Code 712 funds. 
14 Includes $52,240 Special Recreation Use Fees. 
15 Includes $35,814 Code 711 funds and $119,602 Code 713 
funds. 
16 Includes $76,724 Code 711 funds. 
17 Includes $51,854 Special Recreation Use Fees. 
18 Includes $19,683 Code 711 funds and $353,995 Code 713 
funds. 
19 Includes $133,413 Code 711 funds and $183,732 Code 713 
funds. 
20 Includes $114,280 Special Recreation Use Fees. 
21 Includes $155,354 Code 713 funds. 
22 Includes $389,392 Code 713 funds. 
23 Includes $1,185 Code 711 funds and $869,158 Code 713 
funds. 
24 Includes $54,460 from Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
25 Includes $21,897 public works acceleration executive 1963 
funds and $2,596,317 Code 711 funds. 
26 Includes $204,920 Special Recreation Use Fees and includes 
$52,000 Supplemental Funds. 
27 Includes $196,306 public works acceleration executive 1963 
funds, $867,396 Code 711 funds, and $22,612 Code 713 funds. 
28 Includes $236,640 Special Recreation Use Fees. 
29 Includes $315,549 Code 713 funds. 
30 Includes $529,361 Code 713 funds. 
31 Includes $58,571 for preconstruction planning, engineering 
and design completed before FY 1953. 
24-17

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
TABLE 24-B AUTHORIZING LEGISLATION 
Acts Work Authorized 
GREEN AND BARREN RIVERS, KY (See Section 2 of Text) 
Aug 11, 1888 Purchase of original improvement 
Mar 3, 18931 Construction of Lock 2, Green River 
Jul 13, 1892 Construction of Lock 5, Green River 
Jul 13, 1902 Construction of Lock 6, Green River 
Mar 3, 19052 Appropriated $5,000 for continuing improvements of Green 
River above mouth of Big Barren River, with provision "That the 
Secretary of War may, in his discretion, expend such portion of 
said amount as may be necessary for removal of snags in 
Nolin River" 
Mar 3, 1909 Construct new Lock 1 and new Lock and Dam 2, Green River 
Jul 3, 19302 Construct new locks at Dam 5, Green River and Dam 1, 
Barren River; modification of Dam 5, Green River, 
widens bends in Bear Creek, KY 
Jun 26, 19343 Operation and care of locks and dams with War Department 
Appropriations for rivers and harbors 
Aug 30, 19352 Improvement of Nolin River 
Sep 3, 1954 Channel enlargement of lower 103 miles of Green River 
Recovation of authorities for improvement of 
Bear Creek and Nolin River 
OHIO RIVER BASIN (Louisville Dist.) (See Section 27 of Text) 
Aug 28, 1937 Construct levee, floodwalls, and drainage structures for protection 
of cities and towns in Ohio River Basin, projects to be selected 
by Chief of Engineers with approval of Secretary of War, at a cost 
not to exceed $24,877,000 for construction 
Jun 28, 1938 Approved general comprehensive plan for flood control and other 
purposes in Ohio River Basin as may be advisable in discretion 
of Secretary of War and Chief of Engineers, and for initiation 
and partial accomplishment of plan, authorized $75 million for 
reservoirs and $50.3 million for local protection works, individual 
projects to be selected and approved by Chief of Engineers subject 
to provision that authorization shall include diversion of Cache River 
above Cairo, Illinois, and protection of area north of Cairo 
drainage district by levees at an estimated cost of $2 million 
Aug 18, 1941 Additional $45 million for further prosecution of comprehensive 
plan for Ohio River Basin 
Dec 22, 1944 Additional $70 million for further prosecution of comprehensive 
plan for Ohio River Basin, including plan of improvement for 
flood control and other purposes in Kentucky River Basin 
Flood protection works at Taylorsville, Kentucky at an 
estimated cost of $129,350 
Channel improvement of lower Rough River and Barnett Creek 
at an estimated cost of $360,000 
Jul 24, 1946 Additional $125 million for further prosecution of comprehensive 
plan, including plan of improvement for flood control in 
Wabash River Basin, Illinois and Indiana, at an estimated cost 
of $9,629,000 
Also, West Fork of Mill Creek at an estimated cost of $1,527,000. 
May 17, 1950 Additional $100 million for prosecution of comprehensive plan 
for Ohio River Basin, including necessary bank stabilization 
measures at New Harmony Bridge, Indiana, at an estimated 
cost of $500,000 
Jul 3, 1958 Flood control Act of 1958 modified comprehensive plan to provide 
for Monroe Reservoir on Salt Creek, White River Basin, Indiana, 
at an estimated cost to the United States of $4,350,000; cost to 
local interests, $5,141,000 
Oct 23, 1962 Flood Control Act of 1962 deleted Jessamine Creek Reservoir 
on Kentucky River, Kentucky, from comprehensive plan for 
Ohio River Basin 
Dec 30, 1963 Additional $150 million for further prosecution of 
comprehensive plan for Ohio River Basin 
Jun 18, 1965 Additional $89 million for further prosecution of 
comprehensive plan for Ohio River Basin 
May 12, 1967 Additional $38 million for further prosecution of 
comprehensive plan for Ohio River Basin 
Aug 13, 1968 Additional $35 million for further prosecution of 
comprehensive plan for Ohio River Basin 
24-18 
Documents 
H. Ex. Doc 111, 49th Cong., 
2d Sess., Annual Report 
1887, p. 1903 
Annual Report, 1891, p.2 4 3 9 
Annual Report, 1891, p.2 4 78 
S. Doc. 82, 83d Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 2, 71st Cong., 1st Session, 
and H. Doc. 685, 69th Cong., 
2d Session 
H.D. 480, 72d Congress, 2d Sess. 
S.D. 82, 83d Congress, 2d Sess. 
Flood Control Committee 
Document 1, 75th Congress., 
1st Session 
Flood Control Committee 
Document 1, 75th Cong., 
1st Session 
H. Doc. 504, 78th Congress, 
2d Session 
S.D. 105, 78th Congress, 
1st Session 
H. D. 535, 78th Congress, 
2d Session 
H. D. 197, 80th Congress, 
1st Session 
H.D.198, 80th Congress, 1st Sess 
H. D. 192, 85th Congress, 
1st Session 
H. D. 423, 87th Congress, 
2d Session 
Public Law 88-253, 88th Cong., 
1st Session 
Public Law 89-42, 8 ong. 
1st Session 
Public Law 90-17, 90th ong., 
1st Session 
Public Law 90-483, 90th Cong., 
2d Session

TABLE 24-B 
CONTINUED 
LOUISVILLE, KY. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
OHIO RIVER BASIN (Louisville Dist.) (Cont'd.) 
Jun 19, 1970 Additional $69 million for further prosecution of comprehen- Public Law 91-282, 91st Congress, 
sive plan for Ohio River Basin 2d Session 
Mar 7, 1974 Additional $120 million for further prosecution of comprehen- Public Law 93-251, 93rd Congress, 
sive plan for Ohio River Basin 2d Session 
Mar 7, 1974 Fifty-four local protection projects and one reservoir project in Public Law 93-251, 93rd Congress, 
comprehensive plan for Ohio River Basin were deauthorized 2d Session 
August 5, 1977, under Section 12, Water Resources 
Development Act of 1974 
Two additional local protection projects in comprehensive 
plan for Ohio River Basin were deauthorized November 6, 
1977, under Section 12, Water Resources Development 
Act of 1974 
WABASH RIVER BASIN (See Section 32 of Text) 
Aug 13, 1968 Construction of five multiple purpose reservoirs and one S.D. 96, 90th Congress, 2d Session 
local protection project in Wabash River Basin, IL & IN, with 
proviso that construction of Big Walnut Lake, IN, project 
must be approved by the President. Authorization of $50 
million for initiation and partial accomplishment of project. 
Dec 29, 1981 Two multiple purpose reservoirs in Wabash River Basin were Public Law 97-128, 97th Congress, 
deauthorized 2d Session 
1 Deficiency act. 
2 Authorization for Nolin River and Bear Creek revoked by Act 
of Sep. 3, 1954. 
s Permanent Appropriations Repeal Act. 
TABLE 24-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 5 of Text) 
For Last Cost to Sep 30, 1986 
Full Report 
See Annual Operation and 
Name of Project Status Report Construction Maintenance 
Licking River 
Rough River, KY 
Tradewater River, KY 
White River, IN 
Completed 
Completed 
Completed 
Completed 
1901 
1951 
1858 
1909 
$ 13,045 
105,500 
18,568 
119,312 
$ 
101,196 
33,331 
24-19

TABLE 24-E 
For Last 
Full Report 
See Annual 
Project and Status' Report For 
Cost to Sep 30, 1986 
Construction 
Operation and 
Maintenance 
Local Protection: 
Completed: 
Boone County, KY (Ohio River, Rabbit Hash) 
Brevoort Levee, IN (Wabash River) 
Brookport, IL 
Cannelton, IN 
Chaplin River, Perryville, KY2 
Cincinnati, OH 
Covington, KY 
Delphi, IN (Wabash River) 
England Pond Levee, IL (Wabash River) 
English, IN (Little Blue River)2 
Frankfort, KY (North Frankfort) (Kentucky River)3 8 
Gill Township Levee, IN (Wabash River) 
Golconda, IL 
Grassy Creek, Jackson County, IN 
(Muscatatuck River)2 
Harrisburg, IL 
Hawesville, KY 
Indianapolis, IN (Fall Creek Section) 
(White River) 
Indian Creek, Corydon, IN2 
Jackson, KY (Kentucky River) 
Jeffersonville-Clarksville, IN 
Lawrenceburg, IN 
Lebanon Junction, KY (Salt River)2 
Levee Unit 8, IN (White River) 
Louisville, KY4 
Lyford Levee Unit, IN (Wabash River) 
Mason J. Niblack Levee, IN (Wabash River)5 
Mill Creek, Jefferson County, KY2 
Mount Carmel, IL (Wabash River) 
Muncie, IN (White River) 
Neon-Fleming, KY (Kentucky River) 
New Albany, IN 
New Harmony Bridge, IL & IN (Wabash River)2 
7 
Newburgh, IN (Ohio River)6 
Newport, KY 
Paducah, KY 
Panther Creek, KY (Green River)2 
Portland, IN (Salamonie River)2 
Reevesville, IL (Cache River) 
Rochester & McCleary's Bluff Levee, IL 
(Wabash River) 
Rosiclare, IL 
Saline River & Tribs, IL 
Shawneetown, IL 8 
Sturgis, KY 
Taylorsville, KY (Salt River) 
Tell City, IN 
Terre Haute (Conover Levee), IN (Wabash River)7 
Town Creek, Harrodsburg, KY2 
Triplett Creek, Morehead, KY (Licking River)2 
Uniontown, KY 
Vincennes, IN (Wabash River)8 
West Terre Haute, IN (Wabash River) 
Active: 
Canoe Creek, Henderson, KY2 
Frankfort, KY (South Frankfort) (Kentucky River)8 9 
Russell & Allison Levee, IL (Wabash River) 
1977 
1954 
1958 
1959 
1957 
1965 
1953 
1972 
1965 
1979 
1948 
1960 
1953 
1952 
1955 
1953 
1964 
1957 
1959 
1953 
1967 
1952 
1975 
1944 
1965 
1973 
1972 
1956 
1963 
1957 
1959 
1974 
1959 
1959 
1970 
1962 
1954 
1972 
1954 
1981 
1972 
1952 
1956 
1965 
1967 
1972 
1956 
1964 
1977 
19-7_ 9 
$ 392,443 
1,240,299 
597,493 
2,068,391 
832,700 
10,150,935 
7,862,937 
144,563 
734,498 
372,353 
2,960,970 
561,200 
565,333 
70,304 
870,015 
969,318 
1,788,840 
300,143 
130,952 
4,226,361 
2,473,414 
130,417 
700,534 
26,721,438 
267,391 
1,554,712 
292,710 
1,980,675 
887,835 
86,532 
5,375,471 
297,624 
52,061 
7,512,987 
4,761,551 
254,031 
237,657 
600,300 
1,079,236 
622,544 
7,826,219 
91,000 
1,826,778 
378,050 
932,229 
14,913 
56,505 
893,094 
1,070,926 
3,308,941 
1,095,704 
613,927 
52,088 
24-20 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS

LOUISVILLE, KY. DISTRICT 
TABLE 24-E 
CONTINUED 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep 30, 1986 
Full Report 
See Annual Operation and 
Project and Status' Report For Construction Maintenance 
Inactive: 
Anderson, IN (White River) 
Caseyville, KY 
Cloverport, KY 
Concordia, KY 
Frankfort, KY (Benson Creek) (Kentucky River) 
Greenfield Bayou Levee, IN (Wabash River) 
Indianapolis, IN (Warfleigh Section) 
(White River) 
Island Levee, IN (Wabash River) 
Levee Unit 1, IL (Wabash River) 
Lewisport, KY 
Marion, IN (Wabash River) 
Metropolis, IL 
New Harmony Bridge, IL & IN (Wabash River)2 
Newport-Wilder, KY 
Owensboro, KY 
Salyersville, KY (Licking River) 
Shawneetown, IL 
Smithland, KY 
Tolu, KY 
Vincennes, IL (Wabash River) 
West Point, KY 
Reservoirs: 
Active - no FY 1986 expenditure 
Camp Ground Lake, KY (Salt River) 
Downeyville Lake, IN (Wabash River) 
Louisville Lake, IL (Wabash River) 
Inactive: 
Big Pine Lake, IN (Wabash River) 
Big Walnut Lake, IN (Wabash River) 
Booneville Lake, KY (Kentucky River) 
Eagle Creek Lake, KY 
Falmouth Lake, KY (Licking River) 
Lafayette Lake, IN (Wabash River) 
Mining.City Lake, KY (Green River) 
Red River Lake, KY (Kentucky River) 
1940 
1979 
1979 
1976 
1979 
1973 
1979 
1959 
1946 
1964 
1983 
1983 
1977 
1980 
1976 
1975 
1981 
1977 
1976 
$ 5,724 
157,935 
153,410 
355,963 
60,000 
209,975 
10,575 
12,000 
25,367 
4,490 
160,773 
2,335,812 
1,270,590 
1,009,188 
1,038,595 
702,471 
944,386 
1,200,920 
350,474 
1,794,308 
1 All projects are on Ohio River unless otherwise noted. 
2 Authorized by Chief of Engineers under Section 205, 1948 
Flood Control Act, as amended. 
3 Cost includes $161,098 cash contribution consisting of 
$105,118 from the City of Frankfort, KY and $55,980 from the 
Commonwealth of Kentucky. 
4 Cost includes $1,716,301 cash contribution from City of 
Louisville, KY. 
s Cost shown are for Levee only. Does not included costs for 
pump plants. 
6 The Water Resources Development Act of 1974 modified the 
Newburgh Locks & Dam project to include the bank protection 
works at Newburgh, IN. 
' Partially completed to form a useful unit. Remaining portion 
of project deauthorized. 
8 Partially completed to form a useful unit. Remaining portion 
of project deferred. 
9 Advance Engineering and Design funded with General 
Investigations Appropriation. 
24-21

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
TABLE 24-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Flood Control - Local Protection 
Adams Levee, IN (Wabash River) - 1978 $ - 
Alton, IN - 1977 
Aurora, IN - 1977 35,420 
Bellevue, KY - 1977 19,023 
Bonpas Creek, IL (Wabash River) - 1981 
Bromley, KY - 1977 
California (Cincinnati) OH - 1977 16,465 
Carrollton, KY - 1977 9,713 
Cave-in-Rock, IL - 1977 
Cincinnati, OH (Unit 2) - 1977 
Cincinnati, OH (Unit 4) - 1977 
Cleves, OH - 1977 6,343 
Clinton, IN - 1977 6,848 
Deer Creek, Prairie, Levee, IN - 1977 
Derby, IN - 1977 
Elizabethtown,, IL - 1977 
Fletcher & Sunshine Gardens Levee, IN - 1977 3,361 
Grandview, IN - 1977 8,497 
Honey Creek Levee, IN - 1977 
Leavenworth, IN - 1977 
Levee Unit 1, Eel River, IN - 1977 
Levee Unit 2, Eel River, IN - 1977 
Levee Unit 2, East Fork White River, IN - 1977 
Levee Unit 3, East Fork White River, IN 1938 1977 275 
Levee Unit 1, Little Wabash River, IL - 1977 
Levee Unit 2, Little Wabash River, IL - 1977 
Levee Unit 2, Wabash River, IL - 1977 
Levee Units 3 and 4, Wabash River, IL 1938 1977 216 
Levee Unit 6, Wabash River, IL - 1977 9,922 
Levee Unit 17, Wabash River Basin, IN - 1977 
Levee Unit 1, White River, IN - 1977 
Levee Unit 7, White River, IN - 1977 
Levee Unit 9, White River, IN - 1977 
Levee Unit 10, White River, IN - 1977 
Ludlow, KY - 1977 14,503 
Madison, IN - 1977 
Mauckport, IN - 1977 
McGinnis Levee, IN 1950 1977 71,049 
Milton, KY - 1977 
Moscow, OH - 1977 
New Amsterdam, IN - 1977 
New Harmony, IN - 1977 
New Richmond, OH - 1977 7,104 
Orleans, IN 1972 1977 13,158 
Patriot, IN - 1977 
Prestonville , KY - 1977 
Raccoon Creek Levee, IN - 1977 
Rising Sun, IN - 1977 
Rockport, IN - 1977 
Rome, IN - 1977 
Shoals, IN (East Fork White River) 1938 1977 
Shufflebarger Levee, IN 1950 1977 64,487 
Sugar Creek Levee, IN 1961 1977 28,061 
Terre Haute, IN - 1977 
Tri Pond Levee, IL 1972 1977 65,510 
Troy, IN - 1977 
Utica, IN - 1978 
Vevay, IN - 1977 
Westport, KY - 1977 
Flood Control - Reservoirs 
Big Blue Lake, IN 1980 1981 1,079,867 
Clifty Creek Lake, IN 1979 1981 1,016,358 
Helm Lake, IL 1976 1981 41,616 
Lincoln Lake, IL 1979 1981 1,331,844 
Metamora Lake, IN - 1977 
24-22

TABLE 24-H NAVIGATION LOCKS AND DAMS 
PRINCIPAL FEATURES - GREEN & BARREN RIVERS 
AND KENTUCKY RIVER NAVIGATION SYSTEMS 
Lock Dimensions 
Miles Greatest Length 
Lock above Available Upper Depth of Year 
and Mouth of Distance from Width of For Full Normal Pool Miter Sills Character of Percent Opened to Cost of 
Jam River Nearest Town Chamber Width Lift Elevation Upper Lower Foundation Complete Navigation Lock and Dam 
(feet) (feet) (feet msl) (feet) (feet) 
CONSTRUCTION OF LOCKS AND DAMS, OHIO RIVER -For report on this improvement see this heading under Ohio River. 
GREEN AND BARREN RIVERS, KY (See Section 2 of Text) 
Spottsville, KY 
0.3 miles below 
Calhoun, KY 
0.3 miles below 
Rochester, KY 
Woodbury, KY 
0.3 miles below 
Glenmore, KY 
2.8 miles above 
Brownsville, KY 
Barren 
River 
1 15.0 " 0.3 miles above 
Greencastle, KY 
KENTUCKY RIVER, KY (See Section 3 of Text) 
3.8 miles above 
Carrollton, KY 
Lockport, KY 
Gest, KY 
1.0 mile below 
Frankfort, KY 
2.8 miles below 
Tyrone, KY 
21.6 miles below 
High Bridge, KY 
0.8 mile below 
High Bridge, KY 
4.7 miles above 
Camp Nelson, KY 
Valley View, KY 
1.0 mile below 
Ford, KY 
17.2 miles below 
Irvine, KY 
Ravenna, KY 
2.2 miles below 
Willow, KY 
Heidelberg, KY 
84.0 
84.0 
35.8 
35.8 
56.0 
36.0 
56.0 
600.0 
600.0 
137.5 
138.0 
360.0 
145.0 
360.0 
11.8' 
14.3 
17.0 
16.4 
15.2 
9.2 
349.1 
363.4 
380.4 
396.8 
412.0' 
421.1 
Barren 
River 
15.2 412.0 
12.1 
15.0 
7.3 
7.1 
12.0 
8.0 
11.3 
11.7 
5.6 
6.5 
9.3 
8.8 
Shale and Coal 
Shale 
Rock 
Rock 
Piles and Rock 
Gravel 
12.0 9.3 
100 
100 
100 
100 
100 
100 
1956' 
1956' 
1836' 
1839' 
1905' 
1905' 
$5,101,978' 
4,799,2715 
121,377 
125,718 
1,020,868 ' 
168,415 
100 1934 871,565" 
Kentucky 
River 
38.0 
38.0 
38.0 
38.0 
38.0 
52.0 
52.0 
52.0 
52.0 
52.0 
52.0 
52.0 
52.0 
52.0 
145.0 
145.0 
145.0 
145.0 
145.0 
147.0 
147.0 
146.0 
148.0 
148.0 
148.0 
148.0 
148.0 
148.0 
8.2 
13.9 
13.2 
13.2 
15.0 
14.0 
15.3 
18.7 
17.3 
17.0 
18.0 
17.0 
18.0 
17.0 
430.0 
443.9 
457.1 
470.3 
485.3 
499.3 
514.6 
533.6 
550.6 
567.6 
585.6 
602.6 
620.6 
637.6 
8.21" 
7.6 
8.6 
6.4 
10.0 
9.4 
9.1 
10.6 
10.0 
9.0 
10.0 
9.6 
9.6 
8.6 
14.8 
6.1 
6.5 
7.4 
6.5 
6.4 
6.9 
6.0 
6.6 
6.0 
6.0 
6.0 
6.0 
6.0 
Rock and Clay 
Rock 
Rock 
Rock 
Rock 
Rock and Piles 
Rock 
Rock 
Rock 
Rock 
Rock 
Rock 
Rock 
Rock 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
1839" 
1839" 
1844" 
1844" 
1844" "' 
1894" 
1897" 
190018 
1907" 
19071" 
1906" 
1910 
'
" 
19151" 
19171" 
1,350,385" 
314,847 
290,788 
275,463 
237,646 
221,500 
296,593 
425,693 
461,476 
392,902 
' At normal pool Dam 48, Ohio River, Elev. 337.3, Green 
River datum (Elev. 338.0 Ohio River datum). 
= New Lock 1 placed in operation May 25, 1956; old Dam 
1, completed 1835-40, replaced with new cellular concrete 
masonry dam constructed 1970-71 with O&M General funds at 
cost of $822,000. 
' Does not include $179,110 cost of old Lock and Dam 1. 
" New Lock and Dam 2, placed in operation June 18, 1956. 
Does not include $295,696 cost of old Lock and Dam 2. 
* Operation discontinued September 30, 1981. 
Breaching of dam on May 24, 1965, stopped through traffic 
to Bowling Green, KY. 
* With movable A frame crest 3 feet high. 
* Operation discontinued Aug. 1, 1951. 
1O Does not include $179,434 cost of old Lock and Dam 5. 
" Distance from mouth of Green River is 164.5 miles. Lock 
closed to navigation as the result of loss of pool at Green River 
Lock and Dam 4 on May 24, 1965. 
" Includes $729,269 for new large lock completed in 1934. 
, At normal pool McAlpine Dam, Ohio River elev. 421.8 Kentucky 
River datum (Elev. 420 Ohio River datum). 
" Reconstruction completed by United States in 1882. 
,s Built by State of Kentucky. Cost given is for repairs by 
United States to Locks and Dams 1 through 5. Original construction 
costs to State were: L&D 1, $220,300; L&D 2, $151,983; 
L&D 3, $135,857; L&D 4, $131,607; and L&D 5, $137,436. 
Lock was closed to traffic and placed in caretaker status 
in September 1982. 
Green 
River 
New 1 
New 2
3
45 
6 
9.1 
63.1 
108.5 
149.0 
168.1 
181.7 
Kentucky 
River 
1
234 
5
6
7
8
9 
10 
11 
12 
13 
14 
4.0 
31.0 
42.0 
65.0 
82.2 
96.2 
117.0 
139.9 
157.5 
176.4 
201.0 
220.0 
239.9 
249.0 
r
0
c
rr

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(See Section 27 of Text) 
LOCAL PROTECTION 
Type of Estimated Cost2 
Project and Status' Construction Federal Non-Federal Total 
Completed: 
Barnett Creek, KY (Rough River)3 
4 
Brookport, IL5 6 
Cannelton, IN 5 7 
Cincinnati, OH5 8 
Covington, KY5 9 
Delphi, IN (Wabash River)5 
10 
England Pond Levee, IL (Wabash River)11 
Frankfort, KY (Kentucky River) 5 
North Frankfort5 
Golconda, IL5 
12 
Harrisburg, IL 5 10 
Hawesville, KY 5 13 
Jackson, KY (Kentucky River)5 8 
Jeffersonville-Clarksville, IN 7 
Lawrenceburg, IN5 
Louisville, KY5 14 
Mason J. Niblack Levee, IN 
(Wabash River)4 " 
New Albany, IN5 8 
New Harmony Bridge, IL and IN 
(Wabash River)5 7 
Newport, KY 5 7 
Paducah, K Y5 ' 
Reevesville, IL (Cache River)5 15 
Rochester and McCleary's Bluff Levee, IL 
(Wabash River)"11 
Rough River, KY3 4 
Sturgis, KY (Tradewater River)" 
Taylorsville, KY (Salt River)5 16 
Tell City, IN5 14 
Uniontown, KY 5 17 
Vincennes, IN (Wabash River)5 
(completed portion) 
West Terre Haute, IN (Wabash River) 
Active: 
Dayton, KY4 
Evansville, IN4 
Frankfort, KY (Kentucky River)5 
South Frankfort 5 
Russell & Allison Levee, IL 
(Wabash River)9 
Inactive: 
Caseyville, KY5 
Cloverport, KY 5 
Concordia, KY5 
Frankfort, KY (Kentucky River)5 
Benson Creek5 
Greenfield Bayou Levee, IN (Wabash River)5 
Island Levee, IN (Wabash River)5 
Lewisport, KY5 
Metropolis, IL' 
New Harmony Bridge, IL and IN 
(Wabash River)5 7 
Owensboro, KY 5 
Shawneetown, IL' 
Smithland, KY 5 
Tolu, KY5 
Vicennes, IN (Wabash River)5 
(Uncompleted Portion) 
West Point, KY5 
Wilders, KY 
Channel improvement 
Wall and levee 
Wall and levee 
Wall and barrier dam 
Wall and levee 
Levee 
Levee 
Wall and levee 
Wall and levee 
Wall and levee 
Levee 
Cutoff channel 
Wall and levee 
Wall and levee 
Wall and levee 
Levee and pump plants 
Wall and levee 
Bank Protection 
Wall and levee 
Wall and levee 
Levee 
Levee 
Channel improvement 
Levee 
Levee 
Wall and levee 
Levee 
Wall and levee 
Levee 
Wall and levee 
Wall and levee 
Wall 
Levee 
597,493 
2,068,391 
10,150,935 
7,862,937 
144,563 
734,498 
2,960,970 
565,333 
870,015 
969,318 
130,952 
4,226,361 
2,473,414 
25,005,137 
4,337,617 
5,375,471 
297,624 
7,512,987 
4,761,551 
600,300 
1,079,236 
1,826,778 
378,050 
932,229 
1,070,926 
3,308,941 
1,095,704 
8,500 
29,105 
1,309,146 
1,051,102 
17,164 
107,000 
272,100 
10,900 
20,000 
42,593 
3,000 
590,888 
284,725 
1,716,301 
p 
605,993 
2,097,496 
11,460,081 
8,914,039 
161,727 
841,498 
3,233,070 
576,233 
890,015 
1,011,911 
133,952 
4,817,249 
2,758,139 
26,721,438 
109,200 4,446,817 
740,000 6,115,471 
- 297,624 
298,506 7,811,493 
232,000 4,993,551 
40,000 640,300 
100,000 1,179,236 
93,000 1,919,778 
63,309 441,359 
32,707 964,936 
72,153 1,143,079 
285,000 3,593,941 
150,000 1,245,704 
13,115,900 2,043,000 15,158,90018 
55,692,700 7,982,000 63,674,70018 
7,120,000 660,000 7,780,00019 
19,400,000 2,340,000 21,740,00020 
Levee 
Wall and levee 
Levee 
Wall and levee 
Levee 
Levee 
Wall and levee 
Wall and levee 
Bank protection 
Wall and levee 
Wall and levee 
Wall and levee 
Levee 
Wall and levee 
Wall and levee 
Wall and levee 
396,000 
728,000 
590,000 
3,340,000 
4,600,000 
4,630,000 
610,000 
3,070,000 
664,376 
886,000 
1,810,000 
864,000 
303,000 
3,340,000 
35,000 
193,000 
55,000 
1,150,000 
1,087,000 
528,000 
243,000 
431,000 
99,000 
195,000 
361,000 
414,000 
35,000 
431,000 
921,000 
645,000 
4,490,00021 
5,687,00022 
5,158,00022 
853,00023 
3,501,000 
763,37624 
1,081,000 
2,171,000 
1,278,000 
338,000 
3,340,00027 
3,283,000 400,000 3,683,00023 
10,800,000 959,000 11,759,00025 
24-24 
TABLE 24-I

LOUISVILLE, KY. DISTRICT 
TABLE 24-I 
CONTINUED 
OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(FLOOD CONTROL) 
(See Section 27 of Text) 
LOCAL PROTECTION 
Type of Estimated Cost2 
Project and Status' Construction Federal Non-Federal Total 
Deauthorized August 5, 1977 under 
Section 12, Water Resources Development 
Act of 1971 (Public Law 93-251): 
Alton, IN 
Bellevue, KY 
Bromley, KY 
Carrollton, KY 
Cave-in-Rock, IL 
Cincinnati, OH (Unit 2) 
Cincinnati, OH (Unit 4) 
Cleves, OH 
Clinton, IN (Wabash River) 
Deer Creek Prairie Levee, IN 
(Wabash River) 
Derby, IN 
Elizabethtown, IL 
Fletcher and Sunshine Gardens Levee, 
IN (Wabash River) 
Grandview, IN 
Honey Creek Levee, IN 
Leavenworth, IN 
Levee Unit 1, Eel River, IN 
Levee Unit 2, Eel River, IN 
Levee Unit 1, Little Wabash River, IL 
Levee Unit 2, Little Wabash River, IL 
Levee Unit 6, Wabash River, IL 
Levee Unit 17, IN 
Levee Unit 1, White River, IN 
Levee Unit 2, White River, IN 
Levee Unit 7, White River, IN 
Ludlow, KY 
Madison, IN 
Mauckport, IN 
McGinnis Levee, IN (Wabash River) 
Milton, KY 
Moscow, OH 
New Amsterdam, IN 
New Harmony, IN (Wabash River) 
New Richmond, OH 
Patriot, IN 
Prestonville, KY 
Raccoon Levee, IN (Wabash River) 
Rising Sun, IN 
Rockport, IN 
Rome, IN 
Shufflebarger Levee, IN 
(Wabash River) 
Sugar Creek Levee, IN 
(Wabash River) 
Tri-Pond Levee, IL (Wabash River) 
Troy, IN 
Vevay, IN 
Westport, KY 
Levee 
Wall and Levee 
Wall and Levee 
Wall and Levee 
Levee 
Wall and Levee 
Wall 
Levee 
Levee 
Levee 
Wall and Levee 
Wall and Levee 
Levee 
Levee 
Levee 
Wall and Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Wall and Levee 
Levee 
Levee 
Levee 
Wall 
Levee 
Levee 
Levee 
Wall and Levee 
Levee 
Wall and Levee 
Levee 
Wall and Levee 
Wall and Levee 
Levee 
Levee 
Levee 
Levee 
Wall and Levee 
Levee- 
Wall 
$ 255,000 
1,570,000 
1,250,000 
2,220,000 
661,000 
16,800,000 
14,900,000 
1,240,000 
77,000 
213,000 
553,000 
559,000 
548,000 
580,000 
653,000 
1,470,000 
204,000 
2,090,000 
2,850,000 
3,410,000 
1,160,000 
1,580,000 
2,180,000 
724,000 
1,490,000 
2,540,000 
3,820,000 
506,000 
1,820,000 
2,480,000 
1,170,000 
476,000 
616,000 
3,200,000 
753,000 
1,710,000 
426,000 
896,000 
466,000 
359,000 
2,380,000 
418,000 
2,050,000 
502,000 
1,170,000 
1,610,000 
$ 40,000 
400,000 
925,000 
97,000 
125,000 
2,900,000 
621,000 
67,000 
9,000 
10,000 
67,000 
153,000 
26,000 
133,000 
32,000 
266,000 
40,000 
715,000 
164,000 
136,000 
56,000 
118,000 
116,000 
73,000 
88,000 
745,000 
360,000 
105,000 
104,000 
41,000 
372,000 
13,000 
25,000 
720,000 
372,000 
55,000 
37,000 
280,000 
133,000 
67,000 
90,000 
29,000 
191,000 
133,000 
146,000 
41,000 
$ 295,000 
1,970,000 
2,175,000 
2,317,000 
786,000 
19,700,000 
15,521,000 
1,307,000 
86,000 
223,00023 
620,000 
712,000 
574,00023 
713,000 
685,000 
1,736,000 
244,000 
2,805,000 
3,014,00026 
3,546,00027 
1,216,000 
1,698,00027 
2,296,00026 
797,00026 
1,578,00026 
3,285,000 
4,180,000 
611,000 
1,924,000 
2,521,000 
1,542,000 
489,000 
641,000 
3,920,000 
1,125,000 
1,765,000 
463,00023 
1,176,000 
599,000 
426,000 
2,470,000 
447,00023 
2,241,00027 
635,000 
1,316,000 
1,651,000 
24-25

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
TABLE 24-I 
CONTINUED 
OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(FLOOD CONTROL) 
(See Section 27 of Text) 
LOCAL PROTECTION 
Type of 
Project and Status' Construction Federal 
Deauthorized November 6, 1977 under 
Section 12, Water Resources Development 
Act of 1974 (Public Law 93-251) 
Aurora, IN 
California (Cincinnati), OH 
Deauthorized October 3, 1978 under 
Section 12, Water Resources Development 
Act of 1974 (Public Law 93-251) 
Adams Levee, IN (Wabash River) 
Utica, IN5 
Deauthorized May 6, 1981 under 
Section 12, Water Resources Development 
Act of 1974 (Public Law 93-251) 
Bonpas Creek, IL (Wabash River)5 
Wall and Levee 
Wall and Levee 
Levee 
Levee 
Channel 
improvement 
1 All projects are on an Ohio River unless otherwise noted. 
2 Latest cost estimate revision 1954 unless otherwise noted. 
3 Part of Rough River Reservoir and Channel Improvement 
Project, KY. 
4 Details of this project are in individual report. 
5 Also see "Other authorized flood control projects." 
6 See Annual Report for 1958 for details. 
' See Annual Report for 1959 for details. 
8 See Annual Report for 1957 for details. 
9 See Annual Report for 1965 for details. 
10 See Annual Report for 1953 for details. 
11 See Annual Report for 1972 for details. 
12 See Annual Report for 1960 for details. 
13 See Annual Report for 1955 for details. 
14 See Annual Report for 1962 for details. 
15 Substitute project for Belknap, Karnak, and Ullin, IL, complete. 
See Annual Report for 1954 for details. 
16 See Annual Report for 1952 for details. 
17 See Annual Report for 1956 for details. 
18 Latest cost estimate revision 1986. 
19 Latest cost estimate revision 1984. 
20 Latest cost estimate revision 1983. 
21 Latest cost estimate revision 1976. 
22 Latest cost estimate revision 1978. 
23 Latest cost estimate revision 1960. 
24 Latest cost estimate revision 1971. 
25 Latest cost estimate revision 1977. 
26 Latest cost estimate revision 1961. 
27 Latest cost estimate revision 1973. 
24-26 
Estimated Cost2 
Non-Federal Total 
$4,300,000 
1,750,000 
292,000 
1,570,000 
1,080,000 
'$1,190,000 
720,000 
14,000 
120,000 
630,000 
$5,490,000 
2,470,000 
306,00027 
1,690,000 
1,710,00027

LOUISVILLE, KY. DISTRICT 
TABLE 24-I 
CONTINUED 
OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(FLOOD CONTROL) 
(See Section 27 of Text) 
RESERVOIRS 
Tributary Basin 
Reservoirs 
Great Miami River: 
Brookville Lake, IN2 
Metamora Lake, IN 
Green River: 
Barren River Lake, KY2 
Green River Lake, KY 2 
Mining City Lake, KY 
Nolin Lake, KY2 
Rough River Kentucky 2 
Kentucky River 
Booneville Lake, KY 
Buckhorn Lake, KY2 
Carr Fork Lake, KY2 
Licking River 
Cave Run Lake, KY2 
Falmouth Lake, KY 
Little Miami River: 
Caesar Creek Lake, OH2 
William H. Harsha 
Lake, OH2 
Mill Creek: 
West Fork of 
Mill Creek Lake, OH 2 
Wabash River: 
Cagles Mill Lake, IN2 
Cecil M. Harden Lake, IN 2 
Monroe Lake, IN 2 
Patoka Lake, IN 2 
Status 
Active 
Deauthorized 
Complete 
Complete 
Inactive 
Complete 
Complete 
Inactive 
Complete 
Active 
Active 
Inactive 
Active 
Active 
Complete 
Active 
Complete 
Complete 
Active 
Stream 
East Fork of Whitewater 
River 
West Fork of Whitewater 
River 
Barren River 
Green River 
Green River 
Nolin River 
Rough River 
South Fork of Kentucky 
River 
Middle Fork of Kentucky 
River 
North Fork of Kentucky 
River 
Licking River 
Licking River 
Caesar Creek 
East Fork of Little Miami 
River 
West Fork of Mill Creek 
Mill Creek 
Raccoon Creek 
Salt Creek 
Patoka River 
Estimated Cost' 
Federal Non-Federal Total 
$37,904,424 $7,578,7383 $ 45,483,162 
35,300,000 
27,371,299 
33,422,329 
69,100,000 
17,193,381 
10,620,389 
60,700,000 
11,766,206 
50,854,826 
114,826,300 
125,000,000 
108,4185 
183,7325 
22,6125 
35,300,0004 
27,479,717 
33,606,061 
69,100,0004 
17,193,381 
10,643,001 
60,700,0006 
11,766,206 
50,854,826 
- 114,826,3007 
- 125,000,0008 
59,744,000 5,037,0009 64,781,000 
51,447,500 3,484,5009 54,932,000 
3,622,302 1,100,1611o 4,722,463 
4,156,368 
6,633,812 
7,902,827 
106,8165 
353,9955 
8,666,76211 
4,263,184 
6,987,807 
16,569,589 
52,869,000 25,548,70012 78,417,700 
Latest cost estimate revision 1986 unless otherwise noted. 
Details of this project given in individual report. 
Cash contributions for water supply storage. 
Latest cost estimate revision 1954. 
For Code 713 recreation development. 
Latest cost estimate revision 1975. 
Includes $35,213,000 United States Forest Service cost. 
Latest cost estimate revision 1979. 
Reimbursement for water supply storage. 
10 Includes $520,800 for non-Federal cost for sewer relocation 
and dam, $50,000 for contributed funds in fulfillment of project 
authorization, and $529,361 for Code 713 recreation 
development. 
" Includes $7,797,604 cash contribution for storage for low-flow 
regulation and $869,158 for Code 713 recreation development. 
12 Includes $14,173,500 cash contribution for water supply 
storage, and $11,375,200 for initial recreation development. 
24-27

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
TABLE 24-J WABASH RIVER BASIN 
TOTAL COST OF BASIN PLAN:. 
(FLOOD CONTROL) 
(See Section 32 of Text) 
Type of 
Construction Estimated Cost 
Project or Stream Status Federal Non-Federal Total 
LOCAL PROTECTION 
Marion, IN Wall and Levee Inactive $ 3,900,000 $ 854,000 $ 4,754,0002 
RESERVOIRS 
Big Blue Lake, IN Big Blue River Deauthorized 87,200,000 53,846,0003 141,046,0004 
Big Walnut Lake, IN Big Walnut Creek Inactive 81,800,000 45,069,0005 126,869,0004 
Downeyville Lake, IN Flatrock and Little 
Flatrock Rivers Active 74,200,000 64,448,000 138,648,0001 
Helm Lake, IN Skillet Fork Deauthorized 25,171,000 14,829,0007 40,000,0008 
Louisville, Lake, IL Little Wabash River Active 113,000,000 14,435,0009 127,435,00010 
1 Latest cost revision 1984 unless otherwise noted. 
2 Latest cost estimate revision 1977. 
3 Includes $38,190,000 reimbursable by non-Federal interests 
for water supply and $15,656,000 reimbursable for initial recreation 
facilities. 
4 Latest cost estimate revision 1979. 
5 Includes $26,663,000 reimbursable by non-Federal interests 
for water supply and $18,406,000 reimbursable for initial recreation 
facilities. 
6 Includes $53,084,000 reimbursable by non-Federal interests 
for water supply, $8,749,000 reimbursable for initial recreation 
facilities. 
' Includes $12,696,000 reimbursable by non-Federal interests 
for water supply and $2,133,000 for recreation facilities. 
8 Latest cost estimate revision 1975. 
9 Includes $8,402,000 reimbursable by non-Federal interests 
for water supply and $6,033,000 reimbursable for initial recreation 
facilities. 
10 Latest cost estimate revision 1982. 
24-28

LOUISVILLE, KY. DISTRICT 
TABLE 24-K INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 35 of Text) 
Date of 
Local Protection Projects Inspection 
Brevoort Levee, IL Jul 1986 
Brookport, IL bct 1985 
Cache River Levee, IL Oct 1985 
Cannelton, IN Nov 1985 
Cincinnati, OH Jun 1986 
Covington, KY Nov 1985 
Dayton, KY Jun 1986 
Delphi, IN Apr 1986 
England Pond Levee, IL Jun 1986 
Evansville, IN Jun 1986 
Frankfort, KY, North Frankfort Dec 1985 
Gill Township Levee, IN May 1986 
Golconda, IL Oct 1985 
Harrisburg, IL Oct 1985 
Hawesville, KY Nov 1985 
Indianapolis, IN Apr 1986 
Jeffersonville-Clarksville, IN Dec 1985 
Lawrenceburg, IN Jun 1986 
Lebanon Junction, KY Dec 1985 
Levee Unit No. 5, 
Wabash River, IN Oct 1985 
Levee Unit No. 8, IN May 1986 
Louisville, KY Aug 1986 
Lyford Levee, IN May 1986 
Mason J. Niblack Levee, IN Jul 1986 
Mt. Carmel, IL Oct 1985 
Muncie, IN Apr 1986 
New Albany, IN Dec 1985 
Newport, KY Nov 1985 
Paducah, KY Oct 1985 
Reevesville, IL Oct 1985 
Rochester-McCleary's Bluff 
Levee, IL Oct 1985 
Rosiclare, IL Oct 1985 
Shawneetown, IL Oct 1985 
Sturgis, KY Jun 1986 
Taylorsville, KY Dec 1985 
Tell City, IN Nov 1985 
Terre Haute (Conover Levee), IN May 1986 
Uniontown, KY Jun 1986 
Vincennes, IN Jul 1986 
West Terre Haute, IN May 1986 
24-29

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1986 
TABLE 24-K INSPECTION OF COMPLETED 
CONTINUED FLOOD CONTROL PROJECTS 
(See Section 35 of Text) 
Dates of 
Channel Improvements Inspection 
Chaplin River, Perryville, KY Sep 1986 
Cypress Creek, McLean County, KY Jul 1986 
Eel River, Brazil Waterworks, IN May 1986 
English, IN (Little Blue River) Aug 1986 
Grassy Creek, Jackson County, IN Sep 1985 
Harrodsburg, KY (Town Creek) Sep 1986 
Indian Creek, Corydon, IN Jul 1986 
Jackson, KY (North Fork Kentucky River) Jul 1986 
Mill Creek, Jefferson County, KY Aug 1986 
Muscatatuck River, Crothersville, IN Sep 1986 
Neon-Fleming, KY Jul 1986 
Nicholasville (Town Fork) Vicinity, KY Sep 1986 
Panther Creek, Curdsville, KY Jul 1986 
Plum Creek, Spencer County, KY Aug 1986 
Portland, IN (Salamonie River) Apr 1986 
Rough River, Hartford, Ohio County, KY Jul 1986 
Saline River and Tributaries, IL Oct 1985 
Triplett Creek, Morehead, KY Jul 1986 
Troublesome Creek, Hindman, KY Jul 1986 
Whitesburg, KY (North Fork Kentucky River) Jul 1986 
Bank Revetments 
Eighteen Mile Island, Oldham Co., KY Aug 1986 
Great Miami River, Sidney, OH Mar 1985 
Green River, Calhoun, KY Jan 1986 
Licking River, Butler, KY Nov 1985 
Lusk Creek, Golconda, IL Oct 1985 
Little Miami River, Indian Hill, OH Jun 1986 
Little Miami River, Milford, OH Jun 1986 
Ohio River, Brandenburg, KY Jul 1986 
Ohio River, Cloverport, KY Jul 1986 
Ohio River, Daviess Co., KY Jul 1986 
Ohio River, Fort Massac State Park, IL May 1986 
Ohio River, Hawesville, KY Jul 1986 
Ohio River, Lewisport, KY Jul 1986 
Ohio River, Madison, IN Sep 1986 
Ohio River, Moscow, OH Nov 1985 
Ohio River, Mount Vernon, IN Jun 1986 
Ohio River, Newburgh, IN Jun 1986 
Ohio River, Ohio Street, Evansville, IN Jun 1986 
Ohio River, Otter Creek Park, KY Jul 1986 
Ohio River, Rabbit Hash, Boone Co., KY Jun 1986 
Ohio River, Rockport Landing, IN Jun 1986 
Ohio River, Sellersburg, IN Sep 1986 
Ohio River, SR 66, Cannelton, IN Nov 1985 
Ohio River, Troy, IN Jun 1986 
Ohio River, Upper River Rd., Jefferson Co., KY Aug 1986 
Ohio River, Vanderburg Co., IN Jun 1986 
Patoka River at Jasper, IN May 1986 
Patoka River, Winslow, IN May 1986 
Stoner Creek, North Middletown, KY Jul 1986 
Wabash River near Merom, IN May 1986 
Wabash River, New Harmony, IN Jan 1985 
White River, Brownstown, IN May 1986 
White River, Pike Co., IN May 1986 
Whitewater River, Levee Rd., IN Jan 1986 
WTP, Great Miami River, Ross, OH Jun 1986 
24-30

LOUISVILLE, KY. DISTRICT 
TABLE 24-L FLOOD CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
(See Section 37 of Text) 
Fiscal Year Cost 
Jobs Bill' Total 
Flood Control: 
Canoe Creek at Henderson, KY' $12,960 $613,927 
Camp Run, Sellersburg, IN3 - 1,507 
Duck Creek, Elwood, IN4 40 
Great Miami River, Port Jefferson, OH2 3 18,188 
Lancassage Creek, Clark Co., IN- 24,885 
Little Beaver Creek, Kettering, OH4 1,769 
Lyford Levee, IN4 59,840 
Old Sulphur Cr., Orleans, IN3 14 
Pipe Creek, Alexandria, IN4 42,780 
Salyersville, KY5 36 
Sugar Creek, Bellbrook, OH4 26,265 
Whitewater River, Hagerstown, IN5 30,523 
Snagging and Clearing for Flood Control: 
Lick Creek, Hartford City, IN5 6 1,011 
Salamonie River, Montpelier, IN5 1,075 
Emergency Bank Protection: 
Ft. Massac State Park, IL 7 130,680 
Green River, Calhoun, KY7 - 33,516 
Ohio River, Riverfront Park, Evansville,IN 2 5,000 
Ohio River, Rising Sun, IN2 - 7,500 
Whitewater River, New Trenton, IN2 4,500 
Productive Employment Appropriation Act (PL 98-8) of 1983 
Initial Appraisal 
Reconnaissance Study 
Detail Project Report 
Plans and Specifications 
Construction Funds Received 
Construction Completed 
24-31

HUNTINGTON, WV, DISTRICT * 
All cost and financial statements for projects are 
listed at the end of this chapter. All other tables are 
referenced in the text and also appear at the end of this 
chapter. 
The Huntington District includes central and 
southeastern Ohio, all of West Virginia except the 
northern panhandle and northeastern portion, the 
eastern portion of Kentucky, a portion of midwestern 
Virginia, a very small portion of midwestern Virginia, a 
very small portion of northwestern North Carolina, 
embraced in the drainage basin of the Ohio River and its 
tributaries from approximate river mile 127 (below 
Pittsburgh, Pa.) to approximate river mile 438, 
immediately upstream from Foster, KY. The drainage 
area of the Huntington District is approximately 44,914 
square miles. 
IMPROVEMENTS 
Navigation Page 
1. Construction of Locks and 
Dams on Ohio River ................................... ... 25-2 
2. Kanawha River, WV ..................................... 25-2 
3. Open Channel Work, Ohio River .................... 25-2 
4. Other Authorized 
Navigation Projects ..................................... 25-2 
Flood Control 
5. Alum Creek Lake, OH ..................................... 25-2 
6. Beech Fork Lake, WV ................................... 25-2 
7. Bluestone Lake, Ohio 
River Basin, WV ..................................... 25-3 
8. Burnsville Lake, Ohio 
River Basin, WV ..................................... 25-3 
9. Chillicothe, OH ..................................... 25-3 
10. Deer Creek Lake, 
Ohio River Basin, OH ................................... 25-4 
11. Delaware Lake, Ohio 
River Basin, OH ..................................... 25-4 
12. Dewey Lake, Ohio 
River Basin, KY ........................................ 25-4 
13. Dillon Lake, Ohio 
River Basin, OH ........................................ 25-4 
14. East Lynn Lake, 
Ohio River Basin, WV ................................... 25-5 
15. Fishtrap Lake, Ohio River Basin, KY ............ 25-5 
16. Grayson Lake, KY ..................................... 25-5 
17. John W. Flannagan Dam and 
Reservoir, Ohio River Basin,VA ................... 25-6 
18. Levisa and Tug Forks of the 
Big Sandy River and Cumberland 
River, KY, WV and VA ................................. 25-6 
19. Massillon, OH ..................................... 25-6 
20. Muskingum River Lakes, OH ................ ... 25-7 
21. Newark, OH ........................................ 25-7 
22. North Branch of Kokosing 
River Lake, OH ........................................ 25-7 
23. North Fork of Pound River Lake, VA .......... 25-8 
24. Ohio River Basin (Huntington District) ......... 25-8 
25. Paint Creek Lake, Ohio 
River Basin, Ohio ..................................... 25-8 
26. Paintsville Lake, KY ..................................... 25-8 
27. R.D. Bailey Lake, WV ................................... 25-9 
28. Roseville, OH ..................................... 25-9 
29. Summersville Lake, Ohio 
River Basin, WV ..................................... 25-9 
30. Sutton Lake, Ohio River 
Basin, WV ..................................... 25-9 
31. Tom Jenkins Dam, Ohio 
River Basin, OH ..................................... 25-10 
32. Yatesville Lake, KY .................................... 25-10 
33. Inspection of Completed 
Flood Control Projects ................................. 25-10 
34. Flood Control Work Under 
Special Authorization .................................. 25-11 
General Investigations 
35. Surveys ..................................... 25-11 
36. Collection and Study of Basic Data ............... 25-11 
Tables 
Table 
Table 
Table 
25-A 
25-B 
25-C 
Table 25-D 
Table 25-E 
Table 
Table 
Table 
25-F 
25-G 
25-H 
Cost & Financial Statement ....... 25-12 
Authorization Legislation ........... 25-16 
Other Authorized 
Navigation Projects ..................... 25-19 
Not Applicable 
Other Authorized Flood 
Control Projects ........................... 25-20 
Not Applicable 
Deauthorized Projects .................. 25-21 
Inspection of Flood 
Control Projects ........................... 25-22 
25-1 
Page

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. CONSTRUCTION OF LOCKS AND 
DAMS ON THE OHIO RIVER 
See this heading under Chapter 22 - Ohio River 
2. KANAWHA RIVER, WV 
Location. The Kanawha River is approximately 97 
miles in length and is formed by the junction of the New 
and Gauley Rivers, a short distance above Kanawha 
Falls, WV, and flows generally northwesterly to the 
confluence with the Ohio River at Point Pleasant, WV. 
Previous projects. For details of previous projects 
see the Annual Reports for 1875, 1915 and 1938. 
Existing project. The existing project consists of 
three navigation structures on the Kanawha River. 
London Locks and Dam are located approximately 83 
miles above the mouth of the Kanawha River and 
approximately two miles downstream from Montgomery, 
WV. Marmet Locks and Dam are located approximately 
68 miles above the mouth of the Kanawha River at 
Marmet, WV. Winfield Locks and Dam are located 
approximately 31 miles above the mouth of the Kanawha 
River at Winfield, WV. Each structure has twin locks 
with usable dimensions of 56 feet by 360 feet. Another 
structure is located on the Ohio River at approximate 
river mile 279 and approximately nine miles below 
Gallipolis, OH. This structure has two parallel locks, the 
main lock is 110 feet by 360 feet. This system of locks and 
dams provides a navigable depth of nine feet from the 
mouth of the Kanawha River to a point approximately 91 
miles upstream. The existing project was completed at a 
cost of $23,403,201. Construction was initiated in 1931 
and completed in 1937. For further cost details see Table 
25-B, see also, Appendix C. 
Local cooperation. None required. 
Terminal facilities. There are 79 terminals along 
the Kanawha River located from the mouth of the river 
to 30 miles east of Charleston, WV. These terminals are 
constructed principally of steel and wood mooring piles 
and steel pile mooring cells. Seventeen of these terminals 
have railroad connections. One terminal, a paved wharf, 
is owned by the City of Charleston, WV. The remaining 
terminals are privately owned. The principal 
commodities handled are coal, chemicals, acids, cement, 
gasoline and oil, and sand and gravel. For further details 
see the 1962 Annual Report. 
Operations during the fiscal year. The Locks and 
Dams were operated as required and necessary repairs 
and improvements were made to the locks and dams as 
well as to the appurtenant structures and grounds. 
Channel inspections were conducted periodically. 
3. OPEN CHANNEL WORK, 
OHIO RIVER 
See this heading under Chapter 22 - Ohio River. 
4. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 25-C. 
5. ALUM CREEK LAKE, OH 
Location. The damsite is located in Delaware 
County, OH, on Alum Creek, a tributary of Big Walnut 
Creek, approximately 26 miles above the mouth of Alum 
Creek and 15 miles north of Columbus, OH, and 
approximately 157 miles above the mouth of the Scioto 
River. 
Existing project. The existing project consists of a 
rolled earthfill dam 93 feet in height and 10,000 feet in 
length with a gate controlled spillway located in the right 
abutment. The reservoir provides a total storage of 
134,800 acre-feet and controls a drainage area of 
approximately 123 square miles. See also Appendix A. 
Construction of the dam and appurtenant works was 
initiated in August 1970 and completed in July 1974. The 
405 tracts of land required for the project have been 
acquired. The Federal cost of the project was 
$56,267,427. The Sponsor will reimburse the 
Government an estimated $27,880,000, exclusive of 
interest, for cost allocated to water supply. 
Local cooperation. For details of required local 
cooperation see the 1981 Annual Report. 
Operations and Maintenance. The entire project is 
complete. The project was operated for the benefit of flood 
control as required, and necessary repairs were made to 
the structure and appurtenances. During the fiscal year 
the project prevented flood damages estimated to be 
$1,195,000. To date, the project has prevented an 
estimated $38,282,000 in flood damages. 
6. BEECH FORK LAKE, WV 
Location. The damsite is located in Wayne County, 
WV., on Beech Fork Creek, a tributary of Twelvepole 
Creek, approximately four miles above the mouth of 
Beech Fork Creek and 20 miles above the confluence of 
Twelvepole Creek and the Ohio River. 
Existing project. The existing project consists of a 
rolled earth-fill dam 86 feet in height and 1,080 feet in 
length, an uncontrolled spillway landward of the left 
abutment of the dam with a control structure at the 
upstream end. The reservoir provides a total storage of 
25-2

HUNTINGTON WEST VIRGINIA DISTRICT 
37,540 acre-feet and controls a drainage area of 
approximately 78 square miles. Construction of the dam 
was initiated in December 1972 and completed in 
February 1977. See also Appendix A. The 485 tracts of 
land required for the project have been acquired. The full 
funding estimate for new work is $42,400,000. 
Local cooperation. None required. 
Operations during the fiscal year. New Work: 
Engineering activities for remaining work items 
continued. The project is essentially complete, except for 
remaining recreation facilities, landscaping and 
cleanup. 
Operations and maintenance. The project was 
operated for flood control as required and necessary 
repairs were made to the structure and appurtenances. 
The project prevented flood damages estimated at 
$177,000 during the fiscal year. To date the project has 
prevented an estimated $2,855,000 in flood damages. 
7. BLUESTONE LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsite is located on the New River 
in Summers County, WV., approximately three miles 
above Hinton, WV and one mile from the confluence of 
the New and Greenbrier Rivers. The reservoir is located 
in Summers County, WV and Giles County, VA. 
Existing project. The existing project consists of a 
concrete gravity dam 180 feet in height and 2,048 feet in 
length. Appurtenant structures consist of a gated 
spillway 790 feet in length located in the channel section 
of the dam. The stilling pool is formed by a 23 foot 
highweir located 364 feet downstream of 16 gated sluices 
through the spillway section and discharging into the 
stilling pool. Penstocks were installed at the time of 
construction to permit the future installation of hydropower. 
The reservoir provides for a total storage of 
631,000 acre-feet. See also Appendix A. Construction of 
the dam was initiated in January 1942 and completed in 
April 1952. A total of 338 tracts of land was acquired for 
the project. The Federal cost of the project was 
$29,458,652, which includes expenditures under the 
recreation at completed projects program. For further 
details see the 1939 and 1962 Annual Reports. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. The entire project is complete. The 
reservoir was operated for flood control as required and 
necessary repairs were made to the structure and 
appurtenances. The project prevented flood damages 
estimated to be $23,090,000 during the fiscal year. To 
date, the project has prevented an estimated 
$577,441,000 in flood damages. 
8. BURNSVILLE LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsite is located in Braxton County 
WV, on the LIttle Kanawha River, approximately two 
miles above Burnsville, WV, and 124 miles above the 
confluence of the Little Kanawha River and the Ohio 
River. 
Existing project. The existing project consists of an 
earth embankment dam 80 feet in height and 1,000 feet 
in length with a gated spillway in the left abutment. The 
outlet works is an integral part of the spillway, 
consisting of five sluice gates and one low flow sluice. The 
reservoir provides for a total storage of 65,400 acre-feet 
and controls a drainage area of approximately 165 
square miles. Construction of the dam was initiated in 
June 1973 and completed in February 1976. See also 
Appendix A. The 357 tracts of land required for the 
project have been acquired. The Federal cost of the 
project was $56,195,839. 
Local cooperation. None Required. 
Operations during the fiscal year. The project is 
completed. The project was operated for flood control as 
required and necessary repairs were made to the 
structure and appurtenances. The project prevented 
flood damages estimated at $5,769,000 during the fiscal 
year. To date, the project has prevented an estimated 
$22,456,000 in flood damage. 
9. CHILLICOTHE, OH 
Location. The project is located in Ross County, OH, 
along the right bank of the Scioto River, approximately 
69 miles above the confluence with the Ohio River. 
Existing project. The existing project provides for 
the construction of 10,805 feet of earth levee, four gate 
openings and four pump stations. The Federal cost of the 
project was $20,373,314. The estimated non-Federal cost 
is $2,430,000. Construction of the project was initiated in 
June 1975 and became operational for flood control in 
May 1983. 
Local cooperation. All requirements for local 
cooperation are complete. For further details see the 
1978 Annual Report. 
Operations during the fiscal year. New Work: 
The project is complete. To date the project has prevented 
an estimated $10,000 in flood damages. 
25-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
10. DEER CREEK LAKE, 
OHIO RIVER BASIN, OH 
Location. The damsite is located in Pickaway 
County, approximately seven miles south of Mount 
Sterling, OH on Deer Creek, a tributary of the Scioto 
River, approximately 21 miles above the mouth of Deer 
Creek and approximately 106 miles above the mouth of 
the Scioto River. 
Existing project. The existing project consists of a 
rolled earth-filled dam 93 feet in height and 3,880 feet in 
length, a 741 foot concrete gravity channel section 
controlled by three tainter gates, an outlet works 
consisting of five gated sluices through a concrete 
spillway section discharging into a stilling basin and an 
earth dike 15 feet by 4,600 feet in a saddle located 
approximately four miles southwest of the damsite. The 
reservoir provides a total storage of 102,540 acre-feet and 
controls a drainage area of approximately 278 square 
miles. Construction of the dam was completed in May 
1968. The 138 tracts of land required for the project have 
been acquired. For further project details see the 1965 
Annual Report. See also Appendix A. The Federal cost of 
the project is $20,406,545, including expenditures under 
the recreation at completed projects program. 
Local cooperation. For details of required local 
cooperation see the 1981 Annual Report. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The reservoir was operated for flood control as required 
and necessary repairs were made to the structure and 
appurtenances. The project prevented an estimated 
$1,313,000 in flood damages during the fiscal year. To 
date, the project has prevented an estimated $17,521,000 
in flood damages. 
11. DELAWARE LAKE, 
OHIO RIVER BASIN, OH 
Location. The damsite is located on the Olentangy 
River, approximately six miles above and north of 
Delaware, OH, and approximately 32 miles above the 
confluence of the Olentangy and Scioto Rivers at 
Columbus, OH. The reservoir is located in Delaware, 
Marion and Morrow Counties, OH. 
Existing project. The existing project consists of a 
rolled earth-fill dam with a gate controlled ogee type 
spillway and five outlet conduits in the channel. The dam 
is 18,600 feet in length and 92 feet in height. The project 
provides for storage of 132,800 acre-feet and controls a 
drainage area of approximately 381 square miles. 
Construction of the dam was initiated in April 1946 and 
completed in July 1948. For further details see the 1962 
Annual Report. See also Appendix A. Total real estate 
requirements of 7,703 acres of fee acquisition and 2,428 
acres of flowage easements have been completed. The 
Federal cost for the project was $7,631,821. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The reservoir was operated for the benefit of flood control 
as required, and necessary repairs were made to the 
structure and appurtenances. The project prevented an 
estimated $982,000 in flood damages during the fiscal 
year. To date, the project has prevented an estimated 
$54,793,000 in flood damages. 
12. DEWEY LAKE, 
OHIO RIVER BASIN, KY 
Location. The damsite is located on Johns Creek, 
approximately seven miles southeast of Paintsville, KY 
and approximately six miles above the confluence of 
Johns Creek and the Levisa Fork of the Big Sandy River. 
Existing project. The existing project consists of 
an earthfill dam 118 feet in height and 913 feet in length, 
a controlled outlet works discharging through a channel 
excavated in the left abutment, and a rolled earth-fill 
dike blocking a low divide to Brandykeg Creek and the 
Levisa Fork. The reservoir provides a total storage of 
93,300 acre-feet and controls a drainage area of 
approximately 207 square miles. Construction of the 
dam was initiated in March 1946 and completed in July 
1949. For further project detail see the 1965 Annual 
Report. See also Appendix A. Total real estate 
requirements for the project were 12,458 acres in fee and 
1,170 acres in flowage easements. The Federal cost of the 
project was $7,845,547, including expenditures for 
recreation under the completed project program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction activities are 
complete. The reservoir was operated for the benefit of 
flood control as required and necessary repairs were 
made to the structure and appurtenances. The project 
prevented an estimated $573,000 in flood damages 
during the fiscal year. To date, the project has prevented 
an estimated $52,892,000 in flood damages. 
13. DILLON LAKE, 
OHIO RIVER BASIN, OH 
Location. The damsite is located on the Licking 
River, approximately six miles above the confluence of 
the Licking and Muskingum Rivers at Zanesville, Ohio. 
25-4

HUNTINGTON WEST VIRGINIA DISTRICT 
Existing project. The existing project consists of a 
rolled earth-fill dam 118 feet in height and 1,400 feet in 
length, a controlled outlet works discharging through a 
20-foot conduit in the right abutment, and an ungated 
280-foot spillway adjacent to the left abutment of the 
dam, and two rolled earthfill dikes. The reservoir 
provides for a total storage of 261,110 acre-feet and 
controls a drainage area of approximately 748 square 
miles. Construction of the dam was completed in July 
1959. For further project details see the 1962 Annual 
Report. See also Appendix A. Total real estate required 
for the project consists of 8,232 acre in fee and 5,380 acres 
of flowage easements. See also Appendix A. Federal cost 
of the project was $30,218,135. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The project was operated as required for flood control, 
and necessary repairs were made to the structure and 
appurtenances. The project prevented an estimated 
$4,761,000 in flood damages during the fiscal year. To 
date, the project has prevented an estimated 
$102,732,000 in flood damages. 
14. EAST LYNN LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsite is located in Wayne County, 
WV approximately six miles southeast of Wayne, WV, 10 
miles above the mouth of East Fork and 42 miles above 
the confluence of Twelvepole Creek and the Ohio River. 
Existing project. The existing project consists of 
an earth-fill dam 113 feet in height and 638 feet in 
length, an uncontrolled spillway near the left abutment 
of the dam, and a 13-foot reinforced concrete tunnel in the 
right abutment with a control structure at the upstream 
end. The reservoir provides for a total storage of 82,500 
acre-feet and controls a drainage area of approximately 
133 square miles. The required 552 tracts of land have 
been acquired. See also Appendix A. The Federal costs of 
the project was $37,025,968. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The project was operated for flood control as required and 
necessary repairs were made to the structure and 
appurtenances. The project prevented flood damages 
estimated at $504,000 during the fiscal year. To date, the 
project has prevented an estimated $34,270,000 in flood 
damages. 
15. FISHTRAP LAKE, 
OHIO RIVER BASIN, KY 
Location. The damsite is located in Pike County, 
KY, on the Levisa Fork of the Big Sandy River, 
approximately 15 miles upstream from Pikeville, KY, 
approximately three miles above the confluence of 
Levisa and Russell Forks and 103 miles above the mouth 
of the Levisa Fork. 
Existing project. The existing project consists of a 
rock-fill dam 195 feet in height and 1,100 feet in length, 
a controlled spillway containing four tainter gates 
located in the valley wall adjacent to the left abutment 
of the dam, the outlet works consists of an intake 
structure with three conduits controlled by slide gates 
and discharging into a horseshoe shaped tunnel. The 
reservoir provides for a total storage of 164,360 acre-feet 
and controls a drainage area of approximately 395 
square miles. The dam was completed in February 1969. 
The 1,301 tracts of land required for the project have been 
acquired. See also Appendix A. The Federal costs for the 
project was $54,670,126, which includes expenditures 
under the recreation at completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The project was operated for flood control as required, 
and necessary repairs wer made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $287,000. To 
date, the project has prevented an estimated 
$263,509,000 in flood damages. 
16. GRAYSON LAKE, KY 
Location. The damsite is located in Carter County, 
Kentucky on the Little Sandy River approximately 49 
miles above the confluence with the Ohio River, and 11 
miles upstream from Grayson, KY. 
Existing project. The existing project consists of a 
random earthfill dam 120 feet in height and 1,460 feet in 
length, a controlled outlet works discharging through a 
14-foot spillway beyond the left abutment. The reservoir 
provides for a total storage of 119,000 acre-feet and 
controls a drainage area of approximately 196 square 
miles. The dam was completed in January 1968. The 484 
tracts of land required for the project have been acquired. 
See also Appendix A. Federal costs for the project was 
$19,162,741, which includes expenditures for recreation 
facilities under the completed projects program. 
Local cooperation. None required. 
25-5

REPORT OF THE CHIEF ENGINEERS, U.S. ARMY 1986 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The reservoir was operated for flood control as required 
and necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $745,000. To 
date, the project has prevented an estimated $30,981,000 
in flood damages. 
17. JOHN W. FLANNAGAN 
DAM AND RESERVOIR, 
OHIO RIVER BASIN, VA 
Location. The damsite is located in Dickenson 
County, VA, approximately four miles northwest of 
Haysi, VA, on the Pound River approximately two miles 
above the confluence of the Pound River and Russell Fork 
and approximately 150 miles above the mouth of the Big 
Sandy River. 
Existing project. The existing project consists of a 
rock-fill dam 252 feet in height and 970 feet in length, an 
outlet tunnel located near the left abutment of the dam 
with a control structure at the upstream end, a spillway 
controlled by six tainter gates located in a saddle just 
upstream from the damsite. The reservoir provides for a 
total storage of 145,700 acre-feet and controls a drainage 
area of approximately 222 square miles. The project was 
modified to include water quality control by adding 
control gates to the previously uncontrolled spillway, 
which increased the total storage capacity by 39,000 
acre-feet. The dam was completed in December 1963. The 
382 tracts of land required for the project have been 
acquired. See also Appendix A. The Federal cost for the 
project was $20,444,383, which includes expenditures for 
recreation under the completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The project was operated for flood control as required and 
necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $229,000. To 
date, the project has prevented an estimated 
$137,857,000 in flood damages. 
18. LEVISA AND TUG FORKS OF THE 
BIG SANDY AND CUMBERLAND 
RIVERS, WV, VA, AND KY 
Location. The Levisa and Tug Forks form the Big 
Sandy River at Louisa, KY. The Cumberland portion is 
the Upper Cumberland River Basin above Cumberland 
Falls, KY. The basin is approximately 100 miles in 
length and averages approximately 30 miles in width in 
the lower portion and approximately 10 miles in width 
above Harlan, KY. The Big Sandy Basin is within the 
Huntington District, and the Cumberland Basin is 
within the Nashville District. This report covers that 
portion of the project located in the Huntington District. 
Existing project. The authorization language 
directs the Corps of Engineers to design and construct, at 
full Federal expense, such flood control measures as are 
determined to be necesssary and advisable for the 
communities in the Tug and Levisa Forks and Upper 
Cumberland River basins. The authorization further 
states that such flood control measures would be located 
at or in the vicinity of Pikeville, KY; and Grundy, VA on 
the Levisa Fork; Pineville, KY, on the Cumberland 
River; and Williamson and Matewan on the Tug Fork, in 
order to afford the named communities and other flood 
damaged locations and their immediate environs a level 
of protection against flooding at least sufficient to 
prevent any future losses from the likelihood of flooding 
such as occurred in April 1977. The full funding estimate 
for that portion of the authorized areas consisting of the 
Williamson, WV area, Pineville, KY, Barboursville, KY 
and other detailed studies is $314,600,000. Which 
includes $15,600,000 non-Federal contributions. 
Local cooperation. None required. 
Operations during the fiscal year. Additional 
engineering studies are now underway to determine 
what is necessary and advisable to address the flooding 
problems in both the Levisa Fork Basin and in the Tug 
Fork tributary stream areas. The contract for 
construction of the Pump Station at West Williamson, 
WV was awarded in April 1983 and is 95% complete. The 
contract for construction of the floodwall at West 
Williamson, WV, was awarded in July 1986 and is 1% 
complete. The overall project is 24% complete. 
19. MASSILLON, OH 
Location. The project is located in Stark County, on 
the Tuscarawas River, approximately 200 miles above 
the mouth of the Muskingum River. 
Existing project. The existing project consists of 
channel improvement to the Tuscarawas River, 
combined with the construction of drainage facilities, 
levees and pump stations. For further details see the 
1962 Annual Report. Construction was initiated in July 
1940 and completed in October 1951. 
Local cooperation. None required. See the 1962 
Annual Report for details of local contribution of work 
beyond the scope of the project. 
Operations during the fiscal year. Routine 
inspections were conducted to determine that the 
improved channel was maintained in satisfactory 
condition. 
25-6

HUNTINGTON WEST VIRGINIA DISTRICT 
20. MUSKINGUM RIVER LAKES, OH 
Location. The Muskingum River lies in Southeast 
Ohio and including tributaries, drains approximately 
8,000 square miles. The headwaters rise about 25 miles 
south of Lake Erie and flow into the Ohio River at 
Marietta, OH, 172 miles below Pittsburgh, PA. 
Existing project. The existing project consists of 
the construction and operations and maintenance of 14 
reservoirs and appurtenant works in the Muskingum 
River Basin. The existing project originally authorized 
by the Public Works Administration in February 1934. 
Construction of the system was initiated in January 1935 
and completed in November 1938. The system was 
initially operated and maintained by the Muskingum 
Watershed Conservancy District of Ohio, the sponsoring 
agency, from July 1938 to August 1939 when operation 
and maintenance became the responsibility of the Corps 
of Engineers in accordance with the provisions of the 
1939 Flood Control Act. For further project details, see 
the 1962 Annual Report. See also Appendix A. The cost 
of the project was $41,247,815, which includes 
expenditures for recreation facilities under the 
completed project program. A significant Major 
Rehabilitation program was approved in December 1977 
in order to assure the integrity of the existing 14 
structures under the originally designed maximum pool 
conditions. Underseepage and abutment seepage 
problems are being corrected through the installation of 
downstream blankets and/or relief wells and grouting. 
The estimated full funding cost of the rehabilitation 
program is $25,000,000. A related but separate program 
entitled Dam Safety Assurance has been initiated. 
Under current hydrologic design standards, deficiencies 
exist in the spillways at all the 14 projects in the system. 
Corrective measures include widening present 
spillways, constructing new spillways and installing 
parapet walls on top the dams. The full funding estimate 
for the Dam Safety Assurance Program is $71,340,000. 
Local cooperation. All requirements for local 
cooperation have been met. For further details see the 
1942 Annual Report. 
Operations during the fiscal year. New Work. 
The Major Rehabilitation is continuing as scheduled. 
Thus far, twenty contracts have been awarded and the 
program is 76% complete. The Dam Safety Assurance 
program was initiated during FY 1982. Thus far five 
contracts have been awarded and the Dam Safety 
Assurance program is 11% complete. 
Operations and Maintenance. The reservoirs 
were operated for flood control as required, and the 
necessary repairs were made to the structures and 
appurtenances. The system prevented an estimated 
$39,321,000 in flood damages during the fiscal year. To 
date, the system has prevented an estimated 
$1,093,374,000 in flood damages. 
21. NEWARK, OHIO 
Location. The project is located in Licking County 
at the junction of the North and South Forks of the 
Licking River, approximately 29 miles above the 
confluence with the Muskingum River at Zanesville, OH. 
Existing project. For details of the existing project 
see the 1981 Annual Report. Construction of the existing 
project was initiated in July 1940 and completed in 
November 1941. As a result of the 1968 Flood Control Act 
the existing project was modified to include improvement 
of the interior drainage facilities, construction of Log 
Pond Run diversion channel and modification of the 
North Fork Channel. Construction of the Log Pond Run 
diversion channel was awarded in September 1980 and 
completed in December 1981. The full funding estimate 
for the project is $9,800,000 Federal cost and $4,215,000 
non-Federal. 
Local cooperation. For details of required and 
completed local cooperation see the 1981 Annual Report. 
Operations during the fiscal year. New Work: 
North Fork Channel - As a result of withdrawal of State 
support for the Utica Lake project (now inactive) and the 
interdependency of the operation of Utica with the North 
Fork Channel, the North Fork Channel portion of the 
project required re-formulation. A reanalysis is 
complete. Engineering studies continued. The contract 
for construction of North Fork Channel (Phase I) was 
awarded in September 1986. 
Operations and Maintenance: Routine 
inspections were conducted to determine that the 
improved channel was maintained in satisfactory 
condition. 
22. NORTH BRANCH OF KOKOSING 
RIVER LAKE, OH 
Location. The damsite is located in Knox County, 
OH, on the North Branch of Kokosing River, 
approximately nine miles above the confluence of the 
Kokosing and North Branch Rivers, and two miles 
northwest of Fredericktown, OH. 
Existing project. The existing project consists of a 
rolled-earth dam, 70 feet in height and 1,400 feet in 
length with an uncontrolled spillway adjacent to the 
right abutment, and an uncontrolled, reinforced concrete 
outlet work located in the right abutment of the dam. The 
reservoir provides for a total storage of 14,885 acre-feet 
and controls a drainage area of approximately 45 square 
miles, the 56 tracts of land required for the project have 
been acquired. Construction of the dam was completed in 
May 1972. See also Appendix A. The Federal cost for the 
project was $6,665,985, which includes expenditures 
under the recreation at completed projects program. 
25-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
Necessary repairs were made to the structure and 
appurtenances. 
23. NORTH FORK OF POUND 
RIVER LAKE, VA 
Location. The damsite is located in Wise County, 
VA, on the North Fork of Pound River, approximately 
one mile upstream from the confluence of the North and 
South Forks which form the Pound River and 
approximately three miles upstream from Pound, VA. 
Existing project. The existing project consists of a 
rockfill dam, 130 feet in height and 600 feet in length, an 
uncontrolled spillway in a saddle upstream from the 
dam, and an outlet tunnel in the right abutment with a 
control structure at the upstream end. The reservoir 
provides a total storage of 11,300 acre-feet and controls 
a drainage area of approximately 17 square miles. The 
127 tracts of land required for the project have been 
acquired. Construction of the dam was completed in 
January 1966. See also Appendix A. The Federal costs for 
the project was $6,186,901, which includes expenditures 
for recreation under the completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction is complete. The 
project was operated as required for flood control and the 
necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $57,000. To 
date, the project has prevented an estimated $4,662,000 
in flood damages. 
24. OHIO RIVER BASIN 
(HUNTINGTON DISTRICT) 
Location. The work covered by this project consists 
of a series of levees, floodwalls, channel improvements 
and dams and lakes in the Ohio River Basin within the 
Huntington District. 
Existing project. The existing project consists of the 
individual projects considered in the Ohio River Basin 
comprehensive plan within the Huntington District. 
Operations during the fiscal year. The 
completed local protection porjects, which are operated 
and maintained by local interest, except for those local 
protection projects for which individual reports have 
been included, prevented flood damages of an estimated 
aggregate total of $28,566,000. 
25. PAINT CREEK LAKE, 
OHIO RIVER BASIN, OH 
Location. The damsite is located in Ross County, 
Ohio, on Paint Creek, a tributary of the Scioto River, 
approximately 37 miles above the mouth of Paint Creek 
and 100 miles above the mouth of the Scioto River and 
approximately four miles east of New Parkersburg, OH. 
Existing project. The existing project consists of a 
rock and random earth fill dam, 118 feet in height and 
700 feet in length, a gale controlled spillway located near 
the right abutment, an outlet tunnel located in the right 
abutment with a control structure at the upstream end, 
and a random rockfill dike located at the right abutment 
of the spillway. The reservoir provides for a total storage 
of 145,000 arcre-feet and controls a drainage area of 
approximately 576 square miles. Construction of the 
dam was completed in July 1973. The 257 tracts of land 
required for the project have been acquired. See also 
Appendix A. Federal costs for the project was 
$26,969,962, which includes expenditures under the 
recreation at completed projects program. 
Local cooperation. For details of required local 
cooperation see the 1981 Annual Report. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The reservoir was operated for flood control as required 
and the necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented an estimated $1,921,000 in flood damages. To 
date, the project has prevented flood damages estimated 
to be $37,900,000. 
26. PAINTSVILLE LAKE, KY 
Location. The damsite is located in Johnson 
County, KY, on Paint Creek, a tributary of the Levisa 
Fork of the Big Sandy River, approximately eight miles 
above the mouth of Paint Creek, and four miles west of 
Paintsville, KY. 
Existing project. The existing project consists of a 
rockfill dam 153 feet in height and 1,560 feet in length, 
an uncontrolled spillway located southwest of the right 
abutment of the dam, and an outlet tunnel in the right 
abutment with a control structure at the upstream end. 
The reservoir provides for a total storage of 76,642 acrefeet 
and controls a drainage area of approximately 93 
square miles. The 635 tracts of land required for the 
project have been acquired. Construction of the dam was 
initiated in September 1976 and was completed in 
September 1980. See also Appendix A. The full funding 
estimate for new work is $66,300,000, which is to be 
appropriated and expended by the Federal Government. 
25-8

HUNTINGTON WEST VIRGINIA DISTRICT 
The local sponsor has reimbursed the Government 
$298,222 for the cost sharing portion of recreation 
development. 
Operations during the fiscal year. New Work: 
Construction of the project is well advanced. The 
remaining work items include minor highway 
relocations, landscaping and final cleanup. 
Operations and Maintenance: The reservoir was 
operated for flood control as required and necessary 
repairs were made to the structure and appurtenances. 
During the fiscal year the project prevented flood 
damages estimated to be $57,000. To date, the project has 
prevented flood damages estimated to be $5,643,000. 
27. R. D. BAILEY LAKE, WV 
Existing project. The damsite is located in 
Wyoming County, WV, on the Guyandotte River 
approximately 108 miles above the confluence with the 
Ohio River and one mile east ofJustice, WV. 
Existing project. The existing project consists of a 
rolled rockfill dam with a concrete face, 305 feet in height 
and 1,330 feet in length, an uncontrolled spillway located 
in a saddle in the right abutment of the dam, and an 
outlet tunnel in the left abutment with a control 
structure located at the upstream end. The reservoir 
provides for a total storage of 203,700 acre-feet and 
controls a drainage area of approximately 540 square 
miles. Construction of the dam was initiated in 
November 1973 and completed in December 1979. See 
also Appendix A. The estimate for new work is 
$250,000,000. 
Local cooperation. None required. 
Condition at the end of the fiscal year. New 
Work: Construction of the project is well advanced. The 
remaining work items include remaining recreation, 
landscaping and cleanup. 
Operations and Maintenance. The reservoir was 
operated for flood control as required and necessary 
repairs were made to the structure and appurtenances. 
During the fiscal year the project prevented flood 
damages estimated to be $1,484,000. To date, the project 
has prevented flood damages estimated to be 
$57,292,000. 
28. ROSEVILLE, OH 
Location. The project is located in Muskingum and 
Perry Counties, on Moxahala Creek, approximately six 
miles the confluence with Jonathan Creek, a tributary of 
the Muskingum River. 
Existing project. The existing project consists of 
7,291 feet of channel improvement; 6,400 feet of levee 
and railroad embankment enlargements; and the 
necessary appurtenances for interior drainage. Total 
Federal cost of the project was $910,785. Construction 
was initiated in August 1959 and completed in October 
1960.
Local cooperation. All requirements for local 
cooperation have been completed. See also the 1962 
Annual Report. Total costs of local requirements were 
$62,000. 
Operations during the fiscal year. Routine 
inspections of the improved portion of the project were 
conducted to determine that the project was maintained 
in satisfactory condition. 
29. SUMMERSVILLE LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsite is located at Ruckers Bend 
in Nicholas County on the Gauley River approximately 
35 miles above the confluence of the Gauley and New 
River at Gauley Bridge, WV. 
Existing project. The existing project consists of a 
rockfill dam having a height of 357 feet and a length of 
2,280 feet, an outlet tunnel in the right abutment with 
a control structure located at the upstream end, an 
uncontrolled spillway located west of the right abutment 
and two earthfill dikes. The reservoir provides for a total 
storage of 413,800 acre-feet and controls a drainage area 
of 803 square miles. See also Appendix A. Construction 
of the dam was initiated in March 1960 and completed in 
March 1966. A total of 9,346 acres of land were acquired 
for the project. The Federal costs of the project was 
$48,375,884, which includes expenditures under the 
recreation at completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. All 
construction work is complete. The project was operated 
for flood control as required and necesssary repairs were 
made to the structures and appurtenances. The project 
prevented an estimated $26,313,000 in flood damages 
during the fiscal year. To date, the project has prevented 
an estimated $246,509,000 in flood damages. 
30. SUTTON LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsite is located on the Elk River 
in Braxton County approximately one mile above Sutton, 
WV and 101 miles above the mouth of the Elk River. 
25-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Existing project. The existing project consists of a 
concrete gravity dam having a height of 220 feet and a 
length of 1,178 feet, a gated spillway in the channel 
section of the dam, comprised of six tainter gates 
supported by piers, an outlet works comprised of five gate 
sluices through the spillway section. The reservoir 
provides for a storage of 265,300 acre-feet and controls a 
drainage area of 537 square miles. See also Appendix A. 
Construction of the dam was initiated in September 1956 
and completed in June 1960. A total of 13,154 acres of 
land were acquired for the project. The Federal costs of 
the project was $37,029,585, which includes 
expenditures under the recreation at completed projects 
program. 
Local cooperation. None required. See the 1981 
Annual Report for contributed funds. 
Operations during the fiscal year. All 
construction work is complete. The project was operated 
for flood control as required and necessary repairs were 
made to the structure and appurtenances. The project 
prevented an estimated $28,407,000 in flood damages 
during the fiscal year. To date, the project has prevented 
an estimated $171,782,000 in flood damages. 
31. TOM JENKINS RESERVOIR, 
OHIO RIVER BASIN, OH 
Location. The damsite is located in Athens County, 
on the East Branch of Sunday Creek, a tributary of the 
Hocking River, approximately three miles north of 
Glouster, Ohio and 57 miles above the mouth of the 
Hocking River. 
Existing project. The existing project consists of a 
rolled-earth dam, 84 feet in height and 944 feet in length, 
a controlled works discharging through a tunnel in the 
left abutment, and an uncontrolled spillway in the ridge 
running south from the damsite. The reservoir, known as 
Burr Oak Lake, provides for a total storage of 26,900 
acre-feet and controls a drainage area of approximately 
33 square miles. See also Appendix A. Construction of 
the project was initiated in March 1948 and completed in 
February 1950. A total of 100 acres of land were acquired 
for the project. The Federal costs of the project were 
$2,086,503, which includes expenditure for recreation at 
completed project. 
Local cooperation. All requirements of local 
cooperation have been met, see also the 1962 Annual 
Report. Contributed funds in the amount of $575,000 
have been received from the State of Ohio. 
Operations during the fiscal year. All 
construction work is complete. The project was operated 
for flood control as required and necessary repairs were 
made to the structure and appurtenances. During the 
fiscal year the project prevented flood damages estimated 
to be $171,000. To date, the project has prevented an 
estimated $9,407,000 in flood damages. 
32. YATESVILLE LAKE, KY 
Location. The damsite is located in Lawrence 
County, on Blaine Creek, a tributary of the Big Sandy 
River, approximately five miles west of Louisa, KY and 
18 miles above the mouth of Blaine Creek. 
Existing project. The existing project provides for 
the construction of an earthfill dam, 104 feet in height 
and 770 feet in length, an uncontrolled spillway located 
approximately one-half mile east of the right abutment 
of the dam, and an outlet tunnel through the left 
abutment of the dam with a control structure at the 
upstream end. The reservoir will provide a total storage 
of 86,951 acre-feet and control a drainage area of 208 
square miles. The full funding estimate for new work is 
$104,000,000, which will be allocated and expended by 
the Federal Government. The sponsor will reimburse the 
Government an estimated $6,615,000 for the cost 
sharing portion of the recreation development. To date, 
302 of the required 599 real estate tracts have been 
acquired. A contract for construction of the dam was 
awarded in January 1977 and was terminated for the 
convenience of the Government in August 1977. 
Operations during the fiscal year. New Work: 
Congress appropriated funds in fiscal year 1981 to 
resume project construction and work progressed until 
March 1981 when administration directed a deferral 
action which resulted in a substantial reduction in 
project funds and the elimination of any recommendation 
for funding in fiscal years 1982 and 1983. Congressional 
action provided fiscal year 1982, 1983, 1984, 1985 and 
1986 funding for the project. The contract for 
Construction of Dam and Appurtenant Works, Phase I, 
was awarded in March 1984 and is complete. Contracts 
with the Commonwealth and the County for relocation 
and/or abandonment of roads affected by the project are 
complete. The contract for construction of Dam and 
Appurtenances (Phase II) was awarded in April 1986 and 
is 23% complete. The contract for Relocation of SR32-2 
was awarded in February 1986 and is 85% complete. 
33. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
The flood control act of June 22, 1936 and 
subsequent acts require local interest to furnish 
assurances that they will operate and maintain certain 
local protection projects after completion in accordance 
with regulations prescribed by the Secretary of the 
Army. District Engineers are responsible for the 
administration of these regulations within their 
respective districts. Maintenance inspections were made 
during the fiscal year of those completed units 
25-10

HUNTINGTON WEST VIRGINIA DISTRICT 
transferred to local interests for operation and 
maintenance. Local interests were advised, as necessary, 
of measures required to maintain the projects in 
accordance with the standards prescribed by regulations. 
Total costs for fiscal year 1986 were $75,272. Total cost 
to September 30, 1986 were $1,276,339. The flood control 
works inspected and the dates of inspection are tabulated 
in Table H. 
34. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency bank protection activities pursuant to 
Section 14 of the 1946 Flood Control Act, Public Law 526, 
79th Congress are tabulated as follows: 
Location 
Dunbar (Sewage Facilities) WV 
Little Kanawha River, Glenville, WV 
Little Stillwater Creek, Urichsville, OH 
Ohio River, Gallipolis, Ohio 
Point Pleasant State Park, WV 
Sistersville City Park, WV 
FY 1986 Cost 
$18,303 
17,482 
15,129 
13,302 
10,849 
5,476 
Flood control activities pursuant to Section 205 of 
the 1948 Flood Control Act, Public Law 853, 80th 
Congress are tabulated as follows: 
FY 1986 Cost 
Blacklick Creek, Franklin County, OH 
Hughes Creek, Hugheston, WV 
Landis Ditch, Rittman, OH 
Marsh Fork, Fairdale, WV 
Muskingum River, Manfield, OH 
Shope Creek, Ashland, KY 
Upper Scioto River, Marion County, OH 
$152,426 
107,228 
80,111 
55,051 
34,384 
106,000 
12,042 
Snagging and clearing activities pursuant to 
Section 208 of the 1954 Flood Control Act, Public Law 
780, 83rd Congress are tabulated as follows: 
Location 
Indian Creek, Wyoming County, WV 
Wolf Creek, Proctorville, OH 
FY 1986 Cost 
$ 6,500 
37,925 
Flood control and coastal emergency activities 
pursuant to Public Law 99, 84th Congress were 
conducted as required during FY 1986 at a cost of 
$312,621. 
National emergency management activities were 
accomplished by the district as required. The costs for 
these activities during FY 1986 were $149,986. 
35. SURVEYS 
Fiscal year 1986 costs were $2,779,925 itemized as 
follows: 
Navigation Studies 
Flood Damage Prevention Studies 
Comprehensive Basin Studies 
Review for Deauthorization 
Miscellaneous Activities 
Coordination Studies 
Continuation of Planning and Engineering 
36. COLLECTION AND STUDY 
OF BASIC DATA 
Fiscal year costs were $167,221. 
$732,558 
995,694 
297,784 
4,934 
76,468 
191,268 
481,219 
25-11 
Location

TABLE 25-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
2. Kanawha River, 
WV 
5. Alum Creek Lake, 
OH 
6. Beech Fork Lake, 
WV 
7. Bluestone Lake, 
Ohio River Basin, 
WV 
8. Burnsville Lake, 
Ohio River Basin, 
WV 
9. Chillicothe, OH 
10. Deer Creek Lake, 
Ohio River Basin, 
OH 
11. Delaware Lake, 
Ohio River Basin, 
OH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
0 
430,292 
4,996,000 
5,156,126 
165,591 
1,265,550 
462,000 
466,979 
1,700,000 
1,812,526 
486,000 
502,334 
22,000 
155,886 
5,631,000 
5,522,048 
719,142 
450,000 
438,273 
1,950,000 
1,839,500 
490,000 
484,504 
- 1,049 
763,000 1,033,000 
749,878 953,694 
4,200,000 
3,394,211 
565,000 
575,697 
650,000 
1,399,214 
745,000 
726,644 
696,000 -290,000 
385,470 406,093 
621,000 
633,824 
470,000 
489,691 
884,000 975,000 
561,287 1,150,611 
- - 27,853,6991 
- - 27,853,699' 
6,271,000 6,765,000 73,056,5842 
7,008,174 6,780,172 73,021,4482 
- - 130,3943 
- - 130,3943 
-20,300 
146,538 
691,000 
698,086 
1,200,000 
1,382,433 
554,000 
545,316 
1,055,000 
1,181,993 
-110,000 
413,697 
989,000 
1,014,583 
-85,000 
11,278 
447,960 
446,813 
-45,933 
5,341 
600,200 
608,490 
186,000 
281,817 
608,000 
620,375 
56,267,422 
56,267,422 
4,439,265 
4,414,336 
42,027,500 
41,875,582 
4,532,039 
4,524,759 
- 29,458,6524 
- 29,458,6524 
730,200 11,710,278 
725,974 11,683,991 
-39,426 
12,722 
1,079,600 
1,063,503 
56,195,839 
56,195,839 
5,875,105 
5,838,573 
-1,785 20,373,314 
12,379 20,373,314 
431,200 
454,619 
334,000 1,244,500 
481,846 1,255,843 
20,406,5455 
20,406,5455 
5,686,5256 
5,679,8716 
7,631,821 
7,631,821 
7,281,2197 
7,268,964' 
25-12

TABLE 25-A (cont'd) 
HUNTINGTON WEST VIRGINIA DISTRICT 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
12. Dewey Lake, 
Ohio River Basin, 
KY 
13. Dillon Lake, 
Ohio River Basin, 
OH 
14. East Lynn Lake, 
Ohio River Basin, 
WV 
15. Fishtrap Lake, 
Ohio River Basin, 
KY 
16. Grayson Lake, 
KY 
17. John W. Flannagan 
Dam & Reservoir, 
Ohio River Basin, 
VA 
18. Levisa & Tug Forks 
of the Big Sandy & 
Cumberland Rivers, 
KY, WV, & VA 
19. Massillon, OH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
774,500 920,000 1,235,000 
794,093 848,817 1,281,093 
425,000 380,000 597,000 
373,508 376,678 631,304 
2,200,000 
2,348,307 
850,100 
855,404 
73,410 
945,000 
861,546 
83,884 
837,000 
811,006 
-1,967 
7,805 
1,175,000 
1,140,831 
- 7,845,5478 
- 7,845,5478 
935,400 11,471,3769 
935,266 11,440,8249 
- 30,218,135 
- 30,218,135 
823,300 4,928,14310 
809,990 4,908,11810 
- - 37,025,968 
27 - 37,025,968 
973,000 1,169,000 9,337,90711 
984,952 1,201,498 9,311,85811 
869,000 
992,134 
O - 
13 - - 
649,400 720,000 694,000 
682,100 606,442 785,280 
87,234 
753,010 
807,226 
-14,215 - 
759 - 
681,000 674,000 
677,713 732,210 
- 54,670,12612 
- 54,670,12612 
757,500 6,087,69813 
777,145 6,068,07613 
- 19,162,74114 
- 19,162,74114 
572,000 7,906,070 
598,334 7,895,697 
- 20,444,38315 
- 20,444,38315 
666,500 9,180,36216 
674,436 9,173,29816 
8,800,000 1,600,000 5,140,000 14,329,000 37,669,000 
3,595,244 4,744,091 8,063,946 14,833,694 36,776,609 
17,000 
16,988 
12,000 
12,013 
18,000 
17,999 
13,300 
12,942 
8,139,40617 
8,139,40617 
293,808 
293,449 
25-13

REPORT OF THE CHIEF OF ENGINEERS U.S. ARMY 1986 
TABLE 25-A (cont'd) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
20. Muskingum River New Work 
Dams & Lakes, Approp. 
OH Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Dam Safety 
Approp. 
Cost 
21. Newark, OH 
(Previous Project) 
(Existing Project) 
22. North Branch of 
Kokosing River 
Lake, OH 
23. North Fork of 
Pound River Lake, 
Ohio River Basin, 
VA 
24. Ohio River Basin 
25. Paint Creek Lake, 
Ohio River Basin, 
OH 
26. Paintsville Lake, 
KY 
27. R. D. Bailey Lake, 
WV 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
3,750,000 
3,950,351 
1,425,000 
1,144,622 
2,950,000 
2,240,704 
23,000 
23,001 
291,352 
272,524 
126,000 
109,505 
199,000 
206,535 
-15,591 
15,182 
496,700 
457,113 
6,285,000 
7,019,206 
420,500 
416,231 
5,800,000 
6,017,764 
735,000 
759,759 
4,380,000 
4,067,444 
1,550,000 
1,344,317 
1,600,000 
1,673,128 
26,000 
26,002 
300,000 
350,514 
4,118,000 
4,347,427 
1,636,000 
2,248,347 
900,000 
1,312,092 
17,377 
17,377 
134,000 
251,472 
94,000 103,000 
103,989 109,710 
313,000 255,000 
296,015 268,505 
425,000 415,000 
475,195 435,438 
3,790,000 
3,273,809 
505,000 
486,911 
15,600,000 
14,817,521 
1,575,000 
1,541,382 
1,721,000 
1,693,268 
573,000 
579,651 
9,250,000 
10,295,735 
1,034,000 
1,042,399 
4,041,000 
4,154,795 
993,000 
1,139,211 
60,000 
308,507 
13,800 
13,737 
297,785 
198,296 
58,600 
59,642 
199,000 
206,538 
464,000 
455,093 
84,359 
435,106 
844,500 
816,543 
271,600 
2,551,000 
2,571,582 
41,247,81518 
41,247,81518 
56,975,07019 
56,916,67719 
19,535,94520 
19,438,31920 
6,940,000 
6,827,774 
845,916 
845,916 
715,942 
715,879 
5,772,512 
5,671,278 
6,665,98521 
6,665,98521 
1,343,617 
1,340,933 
6,186,90122 
6,186,90122 
4,840,35923 
4,838,36923 
355,86124 
355,86124 
26,969,96225 
26,969,96225 
4,646,95626 
4,624,37726 
57,867,147 
57,546,472 
2,760,000 
2,753,141 
215,972,23327 
215,958,07227 
8,091,81428 
8,067,89328 
25-14

TABLE 25-A (cont'd) 
HUNTINGTON WEST VIRGINIA DISTRICT 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
28. Roseville, OH New Work 
Approp. - - - - 910,785 
Cost - - - - 910,785 
Maint. 
Approp. 5,000 7,000 10,000 20,000 148,968 
Cost 4,999 7,003 9,998 19,961 148,966 
29. Summersville Lake, New Work 
Ohio River Basin, Approp. - 7,183 -10,000 - 48,375,884 
WV Cost 11,682 7,598 17,895 - 48,375,88429 
Maint. 
Approp. 1,940,000 1,119,000 982,000 1,649,000 14,054,914 
Cost 2,103,955 1,087,885 1,046,276 1,656,311 14,015,783 
30. Sutton Lake, New Work 
Ohio River Basin, Approp. - 185,000 10,000 -5,376 37,029,58531 
WV Cost - 29,016 147,803 12,805 37,029,58531 
Maint. 
Approp. 1,377,700 1,228,000 1,526,000 1,480,000 17,869,48732 
Cost 1,272,293 1,360,473 1,496,687 1,567,279 17,824,55432 
31. Tom Jenkins Dam, New Work 
OH Approp. - - - - 2,086,50333 
Cost - - - - 2,086,5033" 
Maint. 
Approp. 243,000 225,000 268,000 371,000 3,637,475 
Cost 243,648 228,745 258,014 378,150 3,626,126 
32. Yatesville Lake, New Work 
KY Approp. 4,000,000 10,000,000 15,000,000 9,642,000 54,686,500 
Cost 1,401,135 3,508,186 5,921,767 10,201,760 33,298,796 
'Includes $4,294,612 for new work for previous projects, 
$4,498,636 Emergency Relief funds, $9,004,800 Public Works 
funds and $686,317 Code 713 funds. 
2Includes $3,883,513 for maintenance of previous projects 
and $546,090 Maintenance and Operation funds. 
3Public Works Acceleration funds. 
4Includes $543,960 Emergency Relief funds, $9,698 Public 
Works Acceleration funds, $211,850 Code 711 funds and 
$75,000 Code 713 funds. 
5Excludes $225,090 contributed funds. Includes $590,000 
Code 711 funds. 
6Includes $130,000 provided by the Productive 
Employment Act of 1983. 
7Includes $240,000 provided by the Productive 
Employment Act of 1983. 
8Includes $23,087 Public Works Acceleration funds, 
$1,089,94 Code 711 funds and $231,105 Code 713 funds. 
9Includes $82,900 special recreation use fee funds. 
1�Includes $100,000 provided from the Productive 
Employment Act of 1983. 
l"Includes $209,918 special recreation use fee funds. 
12Includes $362,649 Code 711 funds and $10,000 Code 712 
funds.
l3Includes $38,000 special recreation use fees. 
'4Includes $406,919 Code 711 funds and $2,317 Code 713 
funds. 
15Includes $422,983 Code 711 funds. 
16Includes $88,710 special recreation use fees. 
17Includes $477,813 contributed funds. 
l8Includes $27,190,000 National Industrial Recovery 
funds and $528,288 Code 711 funds. 
9ncludes $131,900 Maintenance and Operations funds. 
20lncludes $61,945 Public Works Acceleration funds. 
2 1Includes $45,177 Code 711 funds. 
22Includes $64,233 Code 711 funds. 
23Includes $68,200 special recreation use fees. 
24Includes $10,920 Emergency Relief funds. 
25Includes $14,153 Code 711 funds. 
26Includes $31,496 special recreation use fee funds. 
27Includes $5,534 Consolidated Army funds. 
28Includes $60,000 provided from the Productive 
Employment Act of 1983. 
29lncludes $300,062 Code 711 funds. 
30 ncludes $214,112 special recreation use fee funds and 
$300,000 provided from the Productive Employment 
Appropriations Act of 1983. 
31Includes $1,837,337 Code 711 funds and $287,843 
Accelerated Public Works funds. Excludes $62,800 contributed 
funds. 
32Includes $267,634 special recreation use fee funds, 
$215,000 provided from the Productive Employment 
Appropriations Act of 1983, and $75,400 Maintenance and 
Operations Funds. 
33Includes $8,064 Code 711 funds and $30,000 Public 
Works Acceleration funds. Excludes $575,000 contributed 
funds. 
25-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1986 
TABLE 25-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
Aug. 30,1935 
Oct. 23, 1962 
Oct. 23, 1962 
Jun. 28, 1938 
Dec. 22, 1944 
Jun. 28, 1938 
Dec. 22, 1944 
Oct. 23, 1962 
Jun. 28, 1938 
Jun. 28, 1938 
Dec. 22,1944 
Jun. 28, 1938 
Dec. 22, 1944 
Jun. 28, 1938 
Dec. 22, 1944 
KANAWHA RIVER LOCKS AND DAMS, WV 
Construction of three locks and dams on the Kanawha 
River and one on the Ohio River. 
ALUM CREEK LAKE, OH 
Construction of Flood Control Reservoir. 
BEECH FORK LAKE, WV 
Construction of Flood Control Reservoir. 
BLUESTONE LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
Deleted Power 
BURNSVILLE LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
CHILLICOTHE, OH 
Construction of Levees and Pump Stations. 
DEER CREEK LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
DELAWARE LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
DEWEY LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
DILLON LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
H. Doc. 31, 73rd Cong., 
1st Sess. 
H. Doc. 587, 87th Cong., 
2nd Sess. 
H. Doc. 520, 87th Cong., 
2nd Sess. 
H. Doc. 91, 74th Cong., 
2nd Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534 78th Cong., 
2nd. Sess. 
H. Doc. 587, 8th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
lst Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong. 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
25-16 
7. 
8. 
10. 
11. 
12. 
13.

TABLE 25-B (cont'd) 
HUNTINGTON WEST VIRGINIA DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
14. Jun. 28, 1938 
Dec. 22, 1944 
15. Jun. 28, 1938 
Dec. 22, 1944 
16. Jul. 14, 1960 
17. Jun. 28, 1938 
Dec. 22, 1944 
18. Oct. 1,1980 
19. Jun. 28, 1938 
20. Feb. 20, 1934 
Jun. 28, 1938 
Aug. 11, 1939 
21. Jun. 28, 1938 
Aug. 13,1968 
22. Oct. 23, 1962 
23. Jul. 14, 1960 
EAST LYNN LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
FISHTRAP LAKE, OHIO RIVER BASIN, KY 
Construction of Flood Control Reservoir. 
Added Recreation 
GRAYSON LAKE, KY 
Construction of Flood Control Reservoir. 
JOHN W. FLANNAGAN DAM AND RESERVOIR, 
OHIO RIVER BASIN, VA 
Construction of Flood Control Reservoir. 
Added Recreation 
LEVISA AND TUG FORKS OF THE BIG SANDY 
RIVER, AND CUMBERLAND RIVER, KY, WV 
Construction of such Flood Control Measures as deemed 
Necessary and Advisable. 
MASSILLON, OHIO 
Construction of Channel Improvement Project. 
MUSKINGUM RIVER LAKES, OH 
Construction of 14 Flood Control Reservoirs. 
Reimbursement to the Muskingum Conservancy District a 
sum not to exceed actual expenditures for project construction. 
Operations and Maintenance assigned to the Corps of Engineers. 
NEWARK, OHIO 
Construction of Channel Improvement Project. 
Modification to Existing Project and Additional Channel 
Improvement and Drainage Facilities. 
NORTH BRANCH OF KOKOSING RIVER LAKE, OH 
Construction of Flood Control Reservoir. 
NORTH FORK OF POUND RIVER LAKE, VA 
Construction of Flood Control Reservoir. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
H. Doc. 440, 86th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Sect. 202, P.L. 367, 
96th Cong., 2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
Public Works Admin. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 396, 76th Cong., 
1st Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
H. Doc. 337, 90th Cong., 
2nd Sess. 
H. Doc. 220, 87th Cong., 
2nd Sess. 
H. Doc. 645, 86th Cong., 
2nd Sess. 
25-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1986 
TABLE 25-B (cont'd) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
25. Jun. 28,1938 
Dec. 22, 1944 
Oct. 27, 1965 
Oct. 23, 1962 
Jun. 28,1938 
Jun. 28, 1938 
Dec. 22, 1944 
Jun. 28, 1938 
Dec. 22, 1944 
Dec. 22, 1944 
Oct. 27, 1965 
Jun. 22, 1936 
25-18 
PAINT CREEK LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
PAINTSVILLE LAKE, KY 
Construction of Flood Control Reservoir. 
R. D. BAILEY LAKE, WV 
Construction of Flood Control Reservoir. 
ROSEVILLE, OH 
Construction of Channel Improvement Project. 
SUMMERSVILLE LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
SUTTON LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
TOM JENKINS DAM, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
YATESVILLE LAKE, KY 
Construction of Flood Control Reservoir. 
INSPECTIONS OF COMPLETED FLOOD CONTROL 
PROJECTS 
Inspection of Local Maintenance of Federally 
Constructed Local Protection Projects. 
26. 
27. 
28. 
29. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
H. Doc. 246, 89th Cong., 
1st Sess. 
H. Doc. 569, 87th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
lst Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
H. Doc. 762, 78th Cong., 
2nd Sess. 
H. Doc. 246, 89th Cong., 
2nd Sess. 
P.L. 738, 74th Cong., 
1st Sess. 
30. 
31. 
32. 
33.

HUNTINGTON WEST VIRGINIA DISTRICT 
TABLE 25-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Big Sandy River 
WV and KY including 
Levisa and Tu Forks2 1952 1,586,236 1,569,8111 131,473 
Elk River, WV 1903 30,259 
Gauley River, WV4 1903 14,761 
Guyandotte River, WV5 1915 27,500 
Little Kanawha River, WV6 1960 470,536 1,023,854 
Muskingum River, OH7 1955 301,912 6,171,897 6,041 
New River, WA and VA5 1899 109,691 
Scioto River at Portsmouth, OH8 1953 10,951 16,593 
1In addition, $140,068 expended from funds transferred 
from Department of Commerce, under accelerated public 
works program, for repairs of eroded bank at lock 3 on Big 
Sandy River, at Louisa, KY. 
2Operation and Maintenance suspended June 30, 1952. 
3Work closed September 1902. Property transferred to 
Kanawha River improvements. 
4Work closed September 1902. Abandonment recommended 
in H. Doc. 467, 69th Congress. 
5Work suspended. 
6Operation and maintenance suspended June 30, 1951. 
7Collections from license non-Federal hydroelectric 
utilities for use of dams on Muskingum River for fiscal years 
1923-1953 were $79,154. 
"Private Law 954, August 31, 1954, authorized Secretary 
of Treasury to pay Portsmouth sand and Gravel Co. $75,000 in 
full settlement of claims against Government for damages resulting 
from change in Scioto River Channel. 
25-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1986 
TABLE 25-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Completed Local Protection Projects 
Ashland, KY 1954 3,718,839 - 
Athens, OH 1979 5,313,700 - - 
Cattletsburg, KY 1963 3,854,361 
Ceredo-Kenova, WV 1955 2,753,551 - 
East Rainelle, WV 1962 614,598 - 
Galax, VA 1953 480,536 - 
Huntington, WV 1956 7,172,840 - 
Ironton, OH 1952 2,604,646 - 
Maysville, KY 1959 6,493,747 - 
Parkersburg, WV 1955 6,652,827 - 
Pt. Pleasant, WV 1955 2,919,578 
Portsmouth-New Boston, OH 1956 9,806,424 - 
Princeton, WV 1962 808,750 - - 
Russell, KY 1953 552,493 - 
Williamson, WV 1964 1,056,166 - 
Inactive Local Protection Projects 
Augusta, KY - 11,577 - 
Burlington, OH - - - - 
Chesapeake, OH - - - - 
Coal Grove, OH - 3,389 
Coal River, WV 1979 472,229 - - 
Dover, KY - - 
Fullerton, KY - 
Greenup, KY - 4,962 - 
Lower Guyandotte River Basin, WV - 17,721 - 
Miller, OH - - - 
Normal, KY - 
Proctorville, OH - - - 
Ravenswood, WV - - 
South Point, OH - - - - 
South Portsmouth, KY - - 
Vanceburg, KY - - - 
Deferred Local Protection Projects 
Newark, OH (Interior Drainage) 1983 - - 
Oceana, WV 1981 611,000 - - 
Inactive Reservoirs and Lakes 
Haysi, VA - 2,656 - - 
Leading Creek, WV 1974 272,880 - - 
Panther Creek, WV 1976 22,879 - 
Salt Creek, OH 1975 1,089,943 - 
Utica, OH 1975 757,550 - 
West Fork, WV 1974 663,192 - 
Deferred Reservoir and Lakes 
Birch, WV . 
Kehoe Lake, KY 1981 1,272,740 - 
Logan, OH . 
Moores Ferry, WV . 
Active Authorized Projects with no current year expenditures. 
Martin, KY 1983 212,048 
25-20

HUNTINGTON WEST VIRGINIA DISTRICT 
TABLE 25-G DEAUTHORIZED PROJECTS 
All projects listed in this table have been deauthorized in accordance with Section 12 of the Water Resources Development Act 
of 1974, P.L. 251, 93rd Congress. 
For Last 
Full Report Federal Contributed 
See Annual Funds Funds 
Local Protection Projects Report For Date Expended Expended 
Aberdeen, OH - May 1981 1,334 - 
Athalia, OH - Aug 1977 - - 
Belpre, OH - Nov 1977 - - 
Brooklyn, WV - Nov 1979 - - 
Buena Vista, OH - Aug 1977 - - 
Chambersburg, OH - Aug 1977 - - 
Cheshire, OH - Nov 1977 - - 
Chilo, OH - Aug 1977 - - 
Clifton, WV - Aug 1977 11,237 - 
Columbus, OH - Aug 1977 - - 
Friendly, WV - Aug 1977 - - 
Gallipolis, OH - Aug 1977 - - 
Hanging Rock, OH - Aug 1977 - - 
Hartford, WV - Aug 1977 - - 
Henderson, WV - Aug 1977 - 
Higginsport, OH - Oct 1978 - - 
Hockingport, OH - Aug 1977 - - 
Letart, WV - Aug 1977 - - 
Letart Falls, OH - Aug 1977 - - 
Manchester, OH - May 1981 - - 
Mapleshade, OH - Oct 1978 - - 
Marietta, OH - Nov 1981 - - 
Mason, WV - Aug 1977 - - 
Middleport, OH - May 1981 9,783 
Millwood, WV - Aug 1977 - - 
New Martinsville, WV - Nov 1979 - - 
New Matamoras, OH - Aug 1977 - - 
Newport, OH - Aug 1977 - - 
Pomeroy, OH - Aug 1977 - - 
Portland, OH - Aug 1977 - - 
Racine, OH - Aug 1977 - - 
Ripley, OH - Oct 1978 7,523 - 
Riverview, WV - Aug 1977 - - 
St. Mary's, WV - Aug 1977 - - 
Sardis, OH - Aug 1977 - - 
Sciotoville, OH - Aug 1977 - - 
Sistersville, OH - Aug 1977 - - 
Syracuse, OH - Aug 1977 - - 
Waverley, WV - Aug 1977 - - 
Williamstown, WV - Nov 1979 - - 
Zanesville, OH - May 1981 - - 
Reservoirs and Lakes 
Big Bend, WV - Aug 1977 -- 
Big Darby, OH 1969 Nov 1979 3,349,568 - 
Frazeysburg, OH - May 1981 5,000 - 
Millersburg, OH - May 1981 - - 
Mill Creek, OH 1981 Nov 1981 1,602,702 
Mud River, WV - Nov 1979 - - 
Poca, WV - May 1981 - - 
Rocy Fork, OH 1950 Aug 1977 91,321 
White Oak Creek, OH - Nov 1981 - - 
25-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1986 
TABLE 25-H INSPECTION OF FLOOD CONTROL PROJECTS - See Section 33 of Text 
Flood Control Works Inspected Dates of Inspection 
Ashland, KY Nov 86 May 86 
Athens, OH Aug 86 
Bramwell, WV Aug 86 
Cairo, WV Sep 86 
Canton (Nimishillen), OH Nov 86 
Cattletsburg, KY Apr 86 Oct 86 
Ceredo-Kenova, WV Apr 86 Oct 86 
Chillicothe, OH Dec 85 Aug 86 
East Rainelle, WV Aug 86 
Fishing Creek, Pine Grove, WV Sep 86 
Fourpole Creek, WV Jul 85 
Galax, VA Aug 86 
Grahn, KY Oct 86 
Griffithsville-Yawkey, WV Dec 84 
Hutchins, KY Oct 86 
Huntington, WV Jan 86 Oct 86 
Inez, KY Oct 85 
Ironton, OH Apr 86 Oct 86 
Jacksonsburg, Fishing Creek, WV Aug 85 
Maysville, KY May 86 Nov 86 
Montcalm, WV Aug 86 
Newark, OH Aug 85 Sep 86 
Olive Hill, KY Oct 86 
Paint Creek at Chillicothe, OH Oct 84 
Paint Creek at Washington Court House, OH Oct 86 
Parkersburg, WV May 86 Nov 86 
Pax, WV Aug 86 
Point Pleasant, WV Apr 86 Oct 86 
Portsmouth-New Boston, OH Apr 85 
Prestonsburg, KY Jan 86 Jun 86 
Princeton, WV Aug 86 
Richwood and Fenwick, WV Aug 86 
Right and Left Forks of Beaver Creek, KY Jan 86 
Ripley, WV Sep 86 
Roseville, OH Jul 86 
Russel, KY Apr 86 Oct 86 
Smithfield, WV Sep 86 
South Williamson, KY May 86 Nov 86 
Utica, OH Sep 86 
West Union, Middle Island, WV Sep 86 
Williamson, WV May 86 Nov 86 
25-22

PITTSBURGH, PA DISTRICT * 
This District comprises part of eastern Ohio, western 
Pennsylvania, southwestern New York, northern West 
Virginia, and northwestern Maryland embraced in drainage 
basin of Ohio River and tributaries above mile 127 
(below Pittsburgh), immediately upstream from New 
Martinsville, W. Va. 
IMPROVEMENTS 
Navigation - Locks and Dams Page 
1. Allegheny River, PA ...................... 26-2 
2. Construction of locks and dams, 
Ohio River .............................. 26-2 
3. Monongahela River, PA and WV ............ 26-2 
4. Open-channel work, Ohio River ............. 26-3 
5. Tygart Lake, WV ....................... 26-3 
6. Other authorized navigation projects ......... 26-3 
Flood Control - Local Protection 
7. Allegheny River, Oil City, PA ............... 26-3 
8. Chartiers Creek, PA ...................... 26-3 
9. Elkins, WV ............................. 26-4 
10. Girty's Run, Millvale, PA ................. 26-4 
11. Johnstown, PA .......................... 26-4 
12. Punxsutawney, Ohio River 
Basin, PA ............................. 26-5 
13. Root Creek, Bolivar, NY ................... 26-5 
Flood Control - Reservoirs 
14. Berlin Lake, Ohio River 
Basin, OH ............................. 26-5 
15. Conemaugh River Lake, 
Ohio River Basin, PA ..................... 26-6 
16. Crooked Creek Lake, 
Ohio River Basin, PA ..................... 26-6 
17. East Branch, Clarion River Lake, 
Ohio River Basin, PA ..................... 26-6 
18. Kinzua Dam and Allegheny Reservoir, 
Ohio River Basin, PA and NY .............. 26-7 
19. Loyalhanna Lake, Ohio River 
Basin, PA ............................. 26-7 
20. Mahoning Creek Lake, 
Ohio River Basin, PA ..................... 26-7 
21. Michael J. Kirwan Dam and 
Reservoir, Ohio River Basin, OH ............. 26-8 
22. Mosquito Creek Lake, Ohio 
River Basin, OH ......................... 26-8 
23. Ohio River Basin (Pittsburgh 
District) .............................. 26-8 
24. Shenango River Lake, Ohio 
River Basin, PA and OH ................... 26-9 
Flood Control (Continued) Page 
25. Stonewall Jackson Lake, Ohio River 
Basin, W V .............................. 26-9 
26. Tionesta Lake, Ohio 
River Basin, PA ......................... 26-10 
27. Union City Dam, Ohio River 
Basin, PA ........................ 26-10 
28. Woodcock Creek Lake, Ohio River 
Basin, PA ............................. 26-11 
29. Youghiogheny River Lake, Ohio River 
Basin, PA and MD .................... 26-11 
30. Inspection of completed flood control 
projects .............................. 26-11 
31. Other authorized flood control projects ....... 26-11 
32. Flood control work under special 
authorization .......................... 26-12 
General Investigations 
33. Surveys ............................... 26-12 
34. Collection and study of basic data ........... 26-12 
35. Research and development ................ 26-12 
Tables 
Table 26-A Cost & Financial Statement .......... 26-13 
Table 26-B Authorizing Legislation ............ 26-17 
Table 26-C Other Authorized Navigation Projects . 26-21 
Table 26-D Not Applicable....................... 
Table 26-E Other Authorized Flood Control 
Projects ........................ 26-22 
Table 26-F Not Applicable....................... 
Table 26-G Deauthorized Projects .............. 26-23 
Table 26-H Allegheny River Statistics ........... 26-24 
Table 26-I Monongahela River Statistics ........ 26-25 
Table 26-J Monongahela River Total Costs ....... 26-26 
Table 26-K Ohio River Basin Local Protection 
Projects ......................... 26-26 
Table 26-L Ohio River Basin Reservoirs ......... 26-27 
Table 26-M Inspection of Completed Flood Control 
Projects ......................... 26-28 
Table 26-N Flood Control Work Under Special 
Authorization ................... . 26-29 
26-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation - Locks and Dams 
1. ALLEGHENY RIVER, PA 
Location. The Allegheny River is 325 miles long. It rises 
in northern Pennsylvania, flows northwestward into New 
York, thence generally southwestward to Pittsburgh, PA, 
where it joins with Monongahela River to form the Ohio. 
(See Geological Survey Charts for western Pennsylvania 
and southwestern New York.) 
Existing project. The project consists of eight locks and 
dams to afford slack-water navigation for a length of 72 
miles from Pittsburgh, PA to above East Brady, PA. Controlling 
depth through canalized portion is 9 feet at normal 
pool level. Channel width varies from a minimum of 200 
feet to full width of river at mouth. Existing project is 
complete, the last lock, No. 9, was placed in service in 
1938. All locks and dams are in fair condition. Navigation 
channel has been widened at certain points and, in general, 
maintained to project depth, thus affording adequate 
depth for passage of commercial tows. 
Local cooperation. Fully complied with. 
Terminal facilities. City of Pittsburgh constructed a 
modern wharf for river freight. There are numerous privately 
maintained terminals and docks, consisting of tipples, 
various types of hoists, chutes, and pipelines for use 
in loading and unloading coal, stone, sand, gravel, petroleum 
products, steel products, and other commodities. 
Transshipment of freight between river and railroads is 
handled at privately owned river-to-rail terminals. Existing 
private terminals are adequate for shipments and receipt 
in Pittsburgh District of type of commerce now in 
existence. 
Operations during fiscal year. Operation and maintenance, 
general: Locks were operated as required and 
necessary repairs were made to structures to maintain 
them in a serviceable condition. 
2. CONSTRUCTION OF LOCKS AND 
DAMS, OHIO RIVER 
See this heading under Ohio River portion. 
3. MONONGAHELA RIVER, PA AND WV 
Location. Formed by junction of Tygart and West Fork 
Rivers about 1 mile south of Fairmont, WV, and flows 
northerly for 128.7 miles to its junction with Allegheny 
River, forming Ohio River at Pittsburgh, PA (See Geological 
Survey Charts for southwestern Pennsylvania and 
northern West Virginia.) 
Previous project. For details see Annual Report for 
1963, page 1070. 
Existing project. Provides for improvement of river by 9 
locks and dams to afford slack-water navigation for its 
entire length from Pittsburgh to above Fairmont, WV. 
Original locks and dams 7, 8 and 9 were replaced by new 
locks and dams 7 and 8 in 1925. Increased traffic necessitated 
enlargement and improvement of locks and dams 1 
to 6 between Pittsburgh and Rices Landing, PA, by building 
two parallel chambers and fixed concrete dams during 
1905 and 1932. Locks and dam 1 were eliminated in 1938 by 
raising Emsworth Dam, Ohio River. Reconstruction of lock 
2 was completed in 1953 to provide two modern navigation 
chambers. The existing locks and dam 2 were originally 
completed in 1907; major modifications were made in 1923 
and 1924, and in 1926 the upper guard and guide walls were 
extended. Construction of Maxwell locks and dam and the 
reconstruction of dam 4 have allowed for removal of 
obsolete locks and dams 5 and 6. Small and antiquated 
original locks and dams 10 to 15, inclusive, have been 
replaced by three modern structures. Morgantown lock and 
dam, initial step in replacement program, was completed in 
1950 replacing locks and dams 10 and 11. Hildebrand lock 
and dam, next upstream, was completed in 1959 replacing 
locks and dams 12 and 13. Raising crest of dam 8 was also 
completed in 1959 as part of upper river improvement and 
eliminates restricted depth in upper reach of pool. Opekiska 
lock and dam was completed in 1967 replacing locks and 
dams 14 and 15. Completion of this link in upper river 
replacement program provides for entire river length of 
minimum channel depth of 9 feet, varying in width from a 
minimum of 250 feet to practically full width at mouth. 
Locks and dam 3 showed advanced stages of deterioration 
and, because of its strategic location and its importance 
to industry throughout the Greater Pittsburgh area and the 
nation, emergency remedial work had to be done in 1977. 
Major rehabilitation of locks and dam 3 was completed on 
Oct. 27, 1980. 
Local cooperation. None required. 
Terminal facilities. City of Pittsburgh constructed a 
modern wharf for freight. Boat landings are maintained by 
some municipalities along the river. A large number of tipples 
at mines and various types of hoists at manufacturing 
plants and sand and gravel supply companies are maintained 
for private use in loading and unloading coal, coke, 
billets, steel products, sand, gravel, and other commodities. 
These terminals and docks are not available for general 
commerce. A number of docks and pipelines are also 
privately maintained for petroleum and acid products. 
Marine ways are maintained by some of the larger industries. 
There are also several terminals for rail-to-river and 
river-to-rail transfer. Facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. New work: Study for 
replacement of locks and dams for middle and lower reach 
of river is being conducted as part of the continuing study 
of the entire Monongahela River Basin. The Reconnaissance 
Report on the Monongahela River Navigation 
System, Stage I Studies was submitted in Jan. 1981. A 
Feasibility Study Interim Report on the Monongahela 
River Navigation System was submitted in Jan. 1984. A 
public meeting was held in Oct. 1983. A General Design 
Memorandum for the replacement of Lock and Dam 7 on 
the Monongahela River was completed in August 1986. A 
General Design Memorandum for Point Marion Lock and 
Dam (Lock and Dam 8) is scheduled for completion in 
February 1987. Operation and maintenance, general: 
Locks were operated as required and necessary repairs 
were made to structures to maintain them in a serviceable 
condition. 
26-2

PITTSBURGH, PA., DISTRICT 
4. OPEN-CHANNEL WORK, OHIO 
RIVER 
See this heading under Ohio River portion. 
5. TYGART LAKE, WV 
Location. Tygart Lake is located on the Tygart River in 
Taylor and Barbour Counties, northcentral WV. The lake is 
approximately 26 road miles due east of Clarksburg, WV 
and 30 road miles south of Morgantown. The dam is situated 
22.7 river miles above the mouth of the Tygart River 
at Fairmont, or 2.25 miles upstream from Grafton, WV, and 
about 78 miles south of Pittsburgh, PA. (See Geological 
Survey Charts for Fairmont, Thornton, and Belington, 
WV.) 
Existing project. A reservoir for low water regulation and 
flood control. Dam is concrete gravity type with an 
uncontrolled center spillway flanked by abutment sections 
joining valley sides. Project was authorized by Public 
Works Administration January 11, 1934, and adopted by 
1935 River and Harbor Act. For further project description 
see Annual Report for 1962. Authorized project is complete. 
Reservoir is in operation for low water control in Monongahela 
River and for purpose of flood protection in Monongahela 
and Ohio Valleys. Construction of dam was started in 
1935 and placed in operation in 1938. Land acquired for 
project consists of 2,662.9 acres in fee, flowage easements 
over 1,216.9 acres and 1,731.9 acres of other easements. 
Local cooperation. The State of West Virginia has 
assumed responsibility for the development and operation 
of hunting and fishing areas as well as the Tygart Lake 
State Park. Controlled releases for downstream navigation 
and recreation are also coordinated with others to the 
extent feasible. No local cooperation is required at 
completed project; however, future recreational developments 
are subject to certain conditions of non-Federal costsharing 
under Federal Water Project Recreation Act of 
1965. A cost-sharing agreement was executed with the 
West Virginia Department of Recreation in May 1981. 
Operations during fiscal year. Operation and maintenance, 
general: Reservoir was operated for benefit of flood 
control and low water regulation, as required, and project 
structures were operated and maintained in a serviceable 
condition throughout the year. Estimated flood control 
benefits achieved by this reservoir for this period were 
8293,486,000. Total flood control benefits for this reservoir 
through September 30, 1986 are $526,816,000. Activities 
under reservoir management program comprising sanitation 
measures, conservation, land management, and operation 
and maintenance of public-use facilities continued. This 
work was limited in scope as State of West Virginia has 
jurisdiction over recreation in reservoir area. 
6. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 26-C on other authorized navigation projects. 
Flood Control - Local Protection 
7. ALLEGHENY RIVER, OIL CITY, PA 
Location. Oil City is located in Venango County, PA at 
the junction of Oil Creek and the Allegheny River (Allegheny 
river mile 132.1). (See Geological Survey Chart for Oil 
City, PA.) 
Existing project. To alleviate the long-standing ice jam 
flooding problems in Oil City, a floating ice control 
structure has been located on the Allegheny River about 
one-half mile upstream from the mouth of Oil Creek. It 
consists of a series of 23 floating steel pontoons (each 20' x 
3' x 1.25') and 24 steel cylindrical floats connected together 
by 2 1/4 inch diameter corrosion resistant steel cables. The 
cables are attached to a junction plate in the center of the 
Allegheny River and four anchors (two on each side) on the 
river banks. During non-winter months, one half of the 
structure is disengaged from its anchor to permit navigation. 
A Detailed Project Report Supplement addressing the 
ice formation problem on Oil Creek was submitted in 
September 1985. 
Estimated first cost for project is $1,143,000 of which 
$1,122.000 is Federal cost and $21,000 is non-Federal cost. 
Local cooperation. The City of Oil City is responsible for 
the acquisition of required project land interests and the 
operation and maintenance of the ice control structures. By 
early Sep. 1982, the City had acquired all the necessary 
rights-of-way for the Allegheny River structure. River 
structure was removed, repaired, repainted and reinstalled 
beginning in August, 1986 by the city. 
Operations during fiscal year. Installation of Allegheny 
River structure with all new additional components 
included was completed in Oct. 1983. Cumulative flood 
damages prevented by the project were estimated to be 
$24,000 to end of fiscal year. 
8. CHARTIERS CREEK, PA 
Location. Within Washington and Allegheny Counties, 
southwestern Pennsylvania, a tributary of Ohio River. 
(See Geological Survey Chart for Carnegie, PA) 
Existing project. Provides for channel widening, deepening 
and realignment, construction of a major channel 
cutoff, and relocations in two separate and independent 
reaches. James G. Fulton project in Allegheny County 
would be about 13.4 miles long and Canonsburg-Houston 
reach in Washington County about 4.7 miles long. Completed 
improvements would contain within banks, all 
floods up to the 1912 maximum of record, but with some 
residual damage, and would greatly reduce flood stages 
and damages resulting from higher floods. James G. 
Fulton Flood Control Project-Construction of Unit 1 was 
started in July 1968, completed in September 1970, and 
turned over to local interests for operation and maintenance 
on June 25, 1971. Construction of Unit 2 was 
started in April 1970, completed in April 1973, and turned 
over to local interests on November 22, 1974. Construction 
of Unit 3 was started in July 1971 and was completed in 
December 1974. Construction of Unit 5 was started in 
June 1972 and was Completed in December 1973. Construction 
of Unit 4 channel improvement was started in 
July 1978, completed in June 1981 and turned over to local 
interests on 18 November 1981. A contract for Environmental 
Improvement, Unit 4, James G. Fulton, was 
awarded in Sep 1981 and completed in Dec 1981. 
Canonsburg-Houston Reach-Construction of Unit I was 
26-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
started in December of 1968, completed in March 1970, 
and turned over to local interests for operation and 
maintenance on August 10, 1970. Construction of Unit 2A 
was started January 17, 1976, completed December 16, 
1976, and turned over to local interests on June 9, 1977. 
Construction plans and specifications for Unit 2B, the remaining 
unit of the reach, are 99% complete. Remaining 
work on project has been delayed due to the inability of 
local cooperating agency to provide the necessary rightsof-
way. Project was authorized by Flood Control Act of 
1965. 
Estimated cost for new work (1985) is $41,850,000 of 
which $32,750,000 is Federal cost and $9,100,000 non- 
Federal cost. 
Local cooperation. Requirements are described in full on 
page 26-3 of FY 1981 Annual Report. Local cooperating 
agency (Washington County) has been unable to provide 
the necessary rights-of-way for the remaining Unit 2B. 
Direct non-Federal contributions have been made in the 
amount of $4,225,188. 
Operations during fiscal year. Regular inspections were 
made at completed units. Estimated flood control benefits 
achieved by the Chartiers Creek project through September 
30, 1986, totaled $15,766,000. 
9. ELKINS, WV 
Location. On Tygart River in north-central Randolph 
County, WV, about 155 miles south of Pittsburgh, PA. It 
is at downstream end of a long, broad reach of upper 
Tygart Valley, about 75 miles above mouth of river. (See 
Geological Survey Chart for Elkins, WV) 
Existing project. Provides flood protection by diverting 
flood discharges from upstream arm of loop of natural 
river channel into an artificial cutoff channel, thereby 
bypassing City of Elkins. Improvement is designed to 
accommodate discharges equivalent to maximum flood of 
reasonable expectancy. Project construction was started 
May 1946 and completed May 1949. Completed works, except 
that portion of channel maintained by Federal 
Government, has been operated and maintained by City of 
Elkins since March 31, 1949. Land acquired for project 
consists of 32.04 acres in fee and 526.01 acres in 
easements. Project was authorized by 1938 Flood Control 
Act. For further project description see Annual Report for 
1962, page 1222. Federal cost of completed project was 
$1,772,627; estimated non-Federal cost for lands, easements, 
and rights-of-way was $40,000. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Operation and maintenance, 
general: Trash boom, destroyed in 1985 flood, will 
be replaced. Project was last inspected in June 1986. 
Cumulative total flood damages prevented to September 
30, 1986, totaled $14,311,000. 
10. GIRTY'S RUN, MILLVALE, PA 
Location. Girtys Run rises in the Fox Ridge area of the 
southern portion of McCandless Township, Allegheny 
County, and flows generally southeast through Ross and 
Shaler Townships and the Borough of Millvale to enter the 
Allegheny River from the right bank at River Mile 3.6 
above the "Point" at Pittsburgh. (See U.S Geological 
Survey chart for Pittsburgh, PA, East.) 
Existing project. To decrease flooding conditions in the 
Borough of Millvale area, project consists of lowering the 
existing channel bottom within the limits of the existing 
walls. The lowering was accomplished by a 16-foot average 
bottom width of cut in rock or overburden averaging 
4 feet in depth in the lower 2,750 feet of the project and 2 
1/2 feet in depth for the remaining portion. Existing 
masonry walls of the channel were replaced and/or stabilized 
where required. Construction of project complete on 
June 26, 1980. Project was authorized for construction 
by the Chief of Engineers under authority of Section 205 
of the 1948 Flood Control Act as amended. 
Federal cost is $2,000,000; estimated non-Federal cost 
of lands, easements and rights-of-way, utility adjustments, 
and amount in excess of $2 million limitation 
established by Section 205 of the 1948 Flood Control Act 
as amended, is estimated at $1,361,722. 
Local cooperation. Requirements are described in full 
on page 26-4 of FY 1981 Annual Report. The Commonwealth 
of Pennsylvania and. the County of Allegheny, 
Pennsylvania, have each agreed to provide to the 
Borough of Millvale 50% of all estimated non-Federal 
costs, currently estimated at $1,361,722. To date, nonfederal 
contributions have totaled $701,722; a formal 
request for the additional $660,000 has been presented to 
the Borough of Millvale. 
Operations during fiscal year. Work on the project 
started July 11, 1976 with a scheduled completion date of 
November 22, 1977; however, by that date the contract 
work had progressed to only about 50% of completion 
and it was found necessary to terminate that contract for 
default due to unsatisfactory and untimely performance. 
Subsequently, a new contract for completion of the remaining 
work was made on May 4, 1978 and work was 
completed July 26, 1980 at a cost of $2,091,522.95. 
Formal hearings were held on July 26, 1978 before the 
Division Engineer and July 8-15, 1980, inclusive, before 
the Engineer Board of Contract Appeals regarding the 
appeal of the defaulted contractor. In July 1982, an 
agreement was reached with the surety and default contractor 
regarding the liability resulting from the 
termination. Modification effecting settlement and release 
stipulation was finalized, resulting in payment to 
Government of $464,340.66. Cumulative flood damages 
prevented were estimated to be $140,000 to September 
30, 1986. 
11. JOHNSTOWN, PA 
Location. Project is located in southwestern Cambria 
County, PA, about 58 miles east of Pittsburgh, PA. It is in 
a deep and comparatively narrow valley at junction of 
Stoney Creek and Little Conemaugh River, which unite to 
form Conemaugh River. (See Geological Survey Chart for 
Johnstown, PA.) 
Existing project. Provides for increased channel capacity 
by enlarging and realigning channels and protecting banks 
with concrete pavement. Improvement designed to accom- 
26-4

PITTSBURGH, PA., DISTRICT 
modate discharges equivalent to those of March 1936 flood, 
maximum natural flow of record, minimum of overbank 
flow and to practically eliminate damages therefrom. 
Project construction began in August 1938 and was completed 
November 1943. Footer protection for Unit 4 was 
completed in November 1949. Land acquired for project 
consists of easements over 192 acres. Project was authorized 
by Flood Control Acts of 1936 and 1937. For further 
project description see Annual Report for 1962, page 1215. 
Local cooperation. Section 2, Flood Control Act of June 
28, 1938, applies. 
Operations during fiscal year. Operation and maintenance, 
general: Operation activities and routine investigations 
were made. Project was last inspected in April, 1986. 
Cumulative flood damages prevented by project were 
estimated to be $417,926,000 to end of September 1986. 
12. PUNXSUTAWNEY, OHIO RIVER 
BASIN, PA 
Location. Borough of Punxsutawney is on Mahoning 
Creek in Jefferson County, PA, about 85 miles northeast 
of Pittsburgh, PA. It is on a comparatively wide, alluvial 
flood plain about 52 miles above mouth of stream and 30 
miles above Mahoning Creek flood control dam. (See Geological 
Survey Charts for Punxsutawney and Smicksburg, 
PA.) 
Existing project. Provides flood protection by channel 
enlargement, dikes, and walls. Improvement is designed to 
accommodate discharges 20% greater than that of maximum 
flood of record. Construction was accomplished by 
construction of four units. Construction started May 1946 
and was completed June 1950. Land acquired for project 
consists of perpetual easements over 72.6 acres. Completed 
works, except that portion of channel maintained 
by the Federal Government, have been operated and maintained 
by Borough of Punxsutawney since July 31, 1950. 
Project was authorized by 1938 Flood Control Act. For 
further project description see Annual Report for 1962, 
page 1209. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Operation and maintenance, 
general: Operation activities and routine 
investigations and inspections were made. Cumulative 
flood damages prevented by project were estimated to be 
$28,738,000 to end of September 1986. 
13. ROOT CREEK, BOLIVAR, NY 
Location. The problem area was located in the 
southwestern portion of the State of New York in the 
Village of Bolivar, Allegany County, about 17 road miles 
east of Olean, New York. (See Geological Survey Chart of 
Olean, NY.) 
Existing project. Flooding of the Village of Bolivar from 
Root Creek causes estimated annual damages in the 
amount of about $53,000. The project consists of 3,230 
feet of Root Creek channel modification, including moderate 
widening, deepening and slope protection. The plan 
provides Bolivar with protection against a flood having a 
frequency of once in 100 years. Total first cost of the plan 
is estimated to be $1,250,000. Project was authorized for 
construction by the Chief of Engineers under authority of 
Section 205 of the 1948 Flood Control Act as amended. 
Final EIS filed with CEQ on March 11, 1976. The Detailed 
Project Report was approved April 29, 1976. 
Local cooperation. Requirements are described in full on 
page 26-5 of FY 1981 Annual Report. 
Assurances were executed by the State of New York 
Department of Environmental Conservation and accepted 
by the Department of the Army on March 23, 1977. All 
interests in real estate required for project construction 
are available. Utility adjustments were completed by 
NYDEC. Land acquired for project consists of 7.809 acres. 
Operations during fiscal year. Contract for construction 
of Bolivar Flood Protection Project was awarded Sep 17, 
1979 for $945,077.71. Construction was completed on July 
6, 1982 and turned over to local interests on 22 February 
1984. 
Flood Control - Reservoirs 
14. BERLIN LAKE, OHIO RIVER 
BASIN, OH 
Location. Dam is on Mahoning River about 73 miles 
above its confluence with Shenango River. It is about 10 
miles above existing Milton Reservoir Dam and 35 miles 
upstream from Warren, Ohio. Reservoir is in Portage, 
Mahoning and Stark Counties, OH. (See Geological Survey 
charts for Warren, Ravenna, and Alliance, OH.) 
Existing project. A reservoir for flood control and water 
supply. Dam consists of a partially controlled, concrete 
gravity, center spillway flanked by rolled-earthfill abutment 
sections joining valley sides. Authorized project is 
complete and in operation for flood control and low water 
regulation purposes in industrialized Mahoning Valley 
below. Construction of dam was started January 1942 and 
completed June 1943. Present project lands consists of 
6,885.3 acres in fee and 1,098.7 acres in easements. For 
further project description, see Annual Report for 1962, 
page 1233. 
Local cooperation. None required at completed project; 
however, future recreational developments are subject to 
certain conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. Operation and 
maintenance, general: Reservoir was operated as required 
and necessary repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by 
this reservoir for this period were $778,000; total benefits 
through September 30, 1986, $217,695,000. Activities 
under reservoir management program comprising sanitation 
measures, conservation, land management, and operation 
and maintenance of public-use facilities continued. 
26-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
15. CONEMAUGH RIVER LAKE, 
OHIO RIVER BASIN, PA 
Location. Dam is on Conemaugh River in Indiana and 
Westmoreland Counties, PA, 7.5 miles above junction of 
Conemaugh River and Loyalhanna Creek, which form the 
head of the Kiskiminetas River. It is about 2 miles 
northeast of Tunnelton, PA, and about 42 miles east of 
Pittsburgh, PA. Reservoir is in Westmoreland and Indiana 
Counties, PA. (See Geological Survey Charts for 
Latrobe, New Florence, and Elders Ridge, PA.) 
Existing Project. A flood control reservoir dam of 
concrete gravity type with a gate-controlled center spillway 
flanked by abutment sections joining valley sides and 
an earth embankment ending in right abutment. Authorized 
project is complete. Reservoir system designed for 
protection of Pittsburgh and reduction of flood heights in 
upper Ohio Valley, generally. Land acquired for dam, 
reservoir and railroad relocation consists of 7,618.1 acres 
in fee and 518.5 acres in easements. Project authorized by 
Flood Control Acts of 1936 and 1938. For further project 
description see Annual Report for 1962, page 1217. 
Local cooperation. None required by law. 
Operations during fiscal year. Operation and 
maintenance, general: Reservoir was operated for benefit 
of flood control as required, and necessary repairs were 
made to structures and appurtenances. Estimated flood 
control benefits achieved by this reservoir for this fiscal 
year were $20,134,000; total flood control benefits through 
September 30, 1986 are $560,914,000. Activities under 
reservoir management program comprising sanitation 
measures, conservation, land management and operation 
and maintenance of public-use facilities were continued. 
16. CROOKED CREEK LAKE, OHIO 
RIVER BASIN, PA 
Location. Dam is on Crooked Creek 6.7 miles above 
junction of creek with Allegheny River near Ford City, 
PA, and about 32 miles northeast of Pittsburgh, PA. (See 
Geological Survey Charts for Freeport and Elders Ridge, 
PA.) 
Existing project. A flood control reservoir dam of 
earthfill type with separate uncontrolled saddle spillway 
and tunnel outlet works. Authorized project is complete. 
Reservoir is in operation as a unit of a coordinated reservoir 
system designed for protection of Pittsburgh and 
reduction of flood heights in upper Ohio Valley, generally. 
Construction of dam was started in March 1938 and completed 
October 1940. Present project lands consist of 
2,563.6 acres in fee and 99.98 acres in easements. Project 
was authorized by Flood Control Acts of 1936 and 1938. 
For further project description see Annual Report for 
1962, page 1213. 
Local cooperation. None required by law. 
Operations during fiscal year. New work: Contract for 
construction of Water Supply and Waste Water Systems 
was awarded on 13 January 1986 for $399,700 and is 
scheduled for completion on 3 March 1987. Contract for 
construction of Maintenance Complex and Administration 
Building was awarded on 23 September 1986 for $896,149 
and is scheduled for completion on 29 January 1988. 
Contract for construction of New Restrooms was awarded 
on 18 September 1985 for $283,590 and is scheduled for 
completion on 22 December 1986. Operation and maintenance, 
general: Master Plan Design Memorandum No. 2 is 
scheduled for completion in June 1987. Reservoir was 
operated for benefit of flood control, as required, and 
necessary repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by this 
reservoir for this period were $3,726,000; total benefits 
through September 30, 1986 are $123,941,000. Activities 
under reservoir management program comprising sanitation 
measures, conservation, land management, and operation 
and maintenance of certain public-use facilities 
continued. By letter dated Aug 14, 1981, the Commonwealth 
of PA relinquished their lease having jurisdiction 
over recreation in reservoir area effective Oct 1, 1981. 
17. EAST BRANCH, CLARION RIVER 
LAKE, OHIO RIVER BASIN, PA 
Location. Dam is in Elk County, PA, on East Branch of 
Clarion River above Middle Fork, 7.3 miles above junction 
of East and West branches of Clarion River at Johnsonburg, 
PA, and about 105 miles northeast of Pittsburgh, 
PA. Reservoir is in Elk County, PA. (See Geological 
Survey Chart for Mount Jewett, PA.) 
Existing project. A reservoir for flood control and lowwater 
regulation. Dam is rolled-earthfill type with gatecontrolled 
concrete tunnel under right abutment and a 
paved uncontrolled spillway on left abutment slope. 
Authorized project is complete. Reservoir is in operation 
for low-water regulation purposes in Clarion River Valley 
below and for flood control as a unit of a coordinated 
reservoir system for protection of Pittsburgh and upper 
Ohio Valley, generally. Construction of dam was started in 
June 1947 and completed in July 1952. Present project 
lands consist of 287.2 acres in fee and 1,296.7 acres in 
easements. Project was selected for construction under 
general authorization for Ohio River Basin in Flood 
Control Acts of 1938 and 1944. For further project 
description see Annual Report for 1962, page 1206. 
Local Cooperation. None required by law. 
Operations during fiscal year. Operations and 
maintenance, general: Reservoir was operated for flood 
control and low-water regulation, as required; and 
necessary repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by 
this reservoir during this fiscal year were $615,000; total 
benefits through September 30, 1986 are $32,026,000. 
Some reservoir management activity was performed 
throughout the year comprising sanitation measures, 
conservation, land management and operation of publicuse 
facilities. Work was limited in scope as bulk of 
reservoir lands are owned by Commonwealth of Pennsylvania. 
26-6

PITTSBURGH, PA., DISTRICT 
18. KINZUA DAM AND ALLEGHENY 
RESERVOIR, OHIO RIVER BASIN, 
PA AND NY 
Location. Dam site is on Allegheny River 9 miles above 
Warren, PA, and 198 miles above mouth of river at Pittsburgh, 
PA. Reservoir is in Warren and McKean Counties, 
PA., and Cattaraugus County, NY. (See Geological Survey 
Charts for Warren and Kinzua, PA - NY, and Randolph and 
Salamanca, NY.) 
Existing project. Reservoir provides flood control, low 
water regulation, and recreation. Dam consists of a combination 
concrete gravity structure and rolled earth 
embankment with gate-controlled spillway and discharge 
conduits controlled by slide-gates in gravity section. Construction 
of project, initiated in February 1960, is complete. 
Construction of dam was started in September 1960 and 
completed in December 1965. Development of recreation 
area at Onoville under a cost-sharing agreement with 
Cattaraugus County was completed in June 1978. Land 
acquired for project consists of 2,646.6 acres in fee and 
easements over 22,420.4 acres. For further details see 
Annual Report for 1962, page 1202. Project was authorized 
by Flood Control Acts of 1936, 1938 and 1941. 
Local cooperation. None required by law. 
Licenses. The Federal Power Commission granted a 
license to Pennsylvania Electric Company and Cleveland 
Electric Illuminating Company on December 28, 1965, for 
the joint construction, operation and maintenance of a 
325-megawatt pumped-storage installation (FPC Project 
No. 2280). The project is complete. 
Operation during fiscal year. New Work: Stilling Basin 
Rehabilitation contract awarded Jul 6, 1983 for $1,278,600 
was completed on Dec 10, 1983. Operation and maintenance, 
general: Reservoir was operated for benefit of flood 
control and low water regulation, as required, and necessary 
repairs were made to structures and appurtenances. Estimated 
flood control benefits achieved by this reservoir for 
this period were $6,824,000; total to end of this fiscal year, 
$329,633,000. Of 2,212 surface tracts authorized for acquisition, 
all have been acquired but are subject to a final audit. 
Activities under reservoir management program comprising 
sanitation measures, conservation, land management, 
and operation and maintenance of public-use facilities 
continued. 
19. LOYALHANNA LAKE, OHIO 
RIVER BASIN, PA 
Location. Dam is on Loyalhanna Creek, 4.5 miles above 
junction of creek with Conemaugh River at Saltsburg, PA, 
and about 29 miles east of Pittsburgh, PA. Reservoir is in 
Westmoreland County, PA. (See Geological Survey Chart 
for Latrobe, PA). 
Existing project. A flood control reservoir dam of 
concrete gravity type with a gate-controlled center spillway 
flanked by abutment sections joining valley sides, and an 
earth embankment section ending in left abutment. Authorized 
project is complete. Reservoir is in operation as a unit 
of a coordinated reservoir system designed for protection of 
Pittsburgh and reduction of flood heights in upper Ohio 
Valley, generally. Construction of dam was started in 
October 1939 and completed in June 1942. Land acquired 
for project consists of 3,334.7 acres in fee and easements 
over 86.7 acres. Project was authorized by Flood Control 
Acts of 1936 and 1938. For further project description see 
Annual Report for 1962, page 1219. 
Local cooperation. None required by law. 
Operations during fiscal year. Operation and maintenance, 
general: Reservoir was operated for benefit of flood 
control, as required, and necessary repairs were made to 
structures and appurtenances. Estimated flood control benefits 
achieved by this reservoir for this fiscal year were 
$5,205,000; total benefits to September 30, 1986, 
$165,568,000. Activities under reservoir management program 
comprising sanitation measures, conservation, land 
management and operation and maintenance of public-use 
facilities continued. 
20. MAHONING CREEK LAKE, 
OHIO RIVER BASIN, PA 
Location. Dam is on Mahoning Creek in Armstrong 
County, Pa, 21.6 miles above junction of creek with 
Allegheny River. It is about 6.50 miles southeast of New 
Bethlehem, PA, and about 51 miles northeast of Pittsburgh, 
PA. Reservoir is in Armstrong, Indiana, and Jefferson 
Counties, PA. (See Geological Survey Charts for Rural 
Valley and Smicksburg, PA). 
Existing project. A flood control reservoir dam of 
concrete gravity type with a gate-controlled center 
spillway flanked by abutment sections joining valley 
sides. Authorized project is complete. Reservoir is in 
operation as a unit of a coordinated reservoir system 
designed for protection of Pittsburgh and reduction of 
flood heights in upper Ohio Valley, generally. Construction 
of dam was started in February 1939 and completed in 
June 1941. Land acquired for project consists of 2,519.36 
acres in fee and easements over 83.5 acres. Project was 
authorized by Flood Control Acts of 1936 and 1938. For 
further project description see Annual Report for 1962, 
page 1210. 
Local cooperation. None required at completed project. 
On November 4, 1977 a contract for wildlife development 
at Mahoning Creek Lake was executed between the U.S. 
Government and the Pennsylvania Game Commission. 
Each party will pay or contribute in kind 50% of the first 
cost of initial wildlife development. On June 7, 1979, a 
contract for fishing and boating development at Mahoning 
Creek Lake was executed between the U.S. Government 
and the Pennsylvania Fish Commission. Each party will 
pay or contribute in kind 50% of the first costs of initial 
fishing and boating development. On September 9, 1980, 
a contract for camping and day-use recreational development 
was executed between the U.S. Government and the 
County of Armstrong. Each party will pay or contribute in 
kind 50% of the first costs of initial camping and day-use 
recreational development and 50% of the costs for future 
development. Each cooperating authority is responsible 
for operation, maintenance and replacement without cost 
26-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
to the Government of all facilities developed with their 
support. 
Operations and results during fiscal year. New work: 
Cost-sharing for Construction of Fishing Access Area 
awarded in Sep 1980 was completed in Jul 1981 for 
$335,405.75. Cost-sharing contract for Construction of 
Hunting Access Areas awarded Jul 30, 1980 was completed 
on Nov 25, 1981 at a final cost of $44,540. Costsharing 
contract for Construction of Milton Loop Recreation 
Area awarded Jul 29, 1981 was completed on Sep 17, 
1982 for $467,842. $500,086 has been contributed by local 
interests towards cost-sharing developments. Operations 
and maintenance, general: Reservoir was operated for 
benefit of flood control as required, and necessary repairs 
were made to structures and appurtenances. Estimated 
flood control benefits achieved by this reservoir for this 
fiscal year were $4,541,000; total to September 30, 1986, 
$155,577,000. Activities under reservoir management and 
maintenance for public-use facilities continued. 
21. MICHAEL J. KIRWAN DAM AND 
RESERVOIR, OH 
Location: Dam site is on West Branch of Mahoning 
River which joins Mahoning River at Newton Falls, OH. 
It is 11 miles above mouth of branch and about 15 miles 
upstream from Warren, OH. Reservoir is in Portage County, 
OH. (See Geological Survey Charts for Ravenna, 
Garrettsville, Chagrin Falls, and Kent, OH.) 
Existing project. Reservoir provides flood control, lowwater 
regulation and recreation. Dam consists of a rolledearth 
embankment structure with gate-controlled outlet 
works and an uncontrolled side-hill spillway through left 
abutment. Authorized project is completed and in operation 
for flood control and low water regulation purposes. 
Construction of dam and access road was started in May 
1963 and completed in November 1966. Land acquired for 
project consists of 6,298.9 acres in fee and easements over 
27.9 areas. For further description see Annual Report for 
1962, page 1231 (West Branch Reservoir, Mahoning 
River, Ohio). Project was authorized by 1958 Flood 
Control Act (H. Doc. 191, 85th Cong. 1st sess.), with local 
contribution requirements modified by Flood Control Act 
of 1960. Federal cost of completed project was 
$17,370,000. Local interests contributed $3,230,000 during 
period of construction bringing initial project cost to 
$20,600,000. 
Local Cooperation. Local interests must contribute 
$5,200,000 for water pollution abatement and for municipal 
and industrial water supply purposes, of which 
$3,230,000 was paid in cash during construction. Unpaid 
balance at time project is placed in operation, $1,970,000, 
will be paid in cash at that time or on an annual basis. Of 
the unpaid balance of contributed funds due and payable, 
payment in full of Trumbull County's share in the amount 
of $663,040 has been received. Mahoning County elected 
to pay their share ($1,306,960) in 50 annual installments of 
$50,323.32, including interest, and has paid $500,986.19 
toward principal to date. Local interests have now 
contributed $4,394,026.19 towards total of $5,200,000 
non-Federal costs. 
Operations during fiscal year. Operation and 
maintenance, general: Contract for Master Plan Design 
Memorandum No. 8 wis completed in Dec 1982 and approved 
by division in Jan 1983. Reservoir was operated for 
benefit of flood control and low-flow augmentation, as 
required, and necessary repairs were made to structures 
and appurtenances. Estimated flood control benefits 
achieved by this dam for this fiscal year were $983,000. 
Total flood control benefits for this reservoir through 
September 30, 1986 are $76,422,000. Activities under 
reservoir management program comprising sanitation 
measures, conservation, land management, and operation 
and maintenance of public-use facilities continued. 
22. MOSQUITO CREEK LAKE, OHIO 
RIVER BASIN, OH 
Location. Dam is on Mosquito Creek, 9 miles above 
junction of creek with Mahoning River at Niles, OH, and 
about 18 miles northwest of Youngstown, OH. (See Geological 
Survey Charts for Bristolville and Kinsman, OH, 
and Pennsylvania.) 
Existing project. A reservoir for flood control, low-water 
regulation and water supply storage. Dam is rolledearthfill 
type with outlet facilities through dam, and an 
uncontrolled natural wasteway to discharge overflow from 
reservoir. Authorized project is complete and in operation 
for flood control and low-water regulation purposes in 
industrialized Mahoning and Beaver Valleys below. Construction 
of dam was started in July 1943 and was ready 
for beneficial use in January 1944. Land acquired for 
project consists of 11,180.6 acres in fee and easements 
over 276.0 acres. State of Ohio has a license from Secretary 
of the Army for development and operation of recreation 
facilities in reservoir area. Project was selected for 
construction under general authorization for Ohio River 
Basin in 1938 Flood Control Act. For further project description 
see Annual Report for 1962, page 1228. 
Local cooperation. None required at completed project; 
however, future recreational developments are subject to 
certain conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations results during fiscal year. Operation and 
maintenance, general: Reservoir was operated for benefit 
of flood control and low-flow regulation as required, and 
necessary repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by this 
dam for this fiscal year were $1,148,000. Total flood 
control benefits for this reservoir through September 30, 
1986 are $59,818,000. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management and operation and maintenance of 
certain public-use facilities continued. This work was 
limited in scope as State of Ohio has jurisdiction over 
recreation in reservoir area. 
23. OHIO RIVER BASIN 
(PITTSBURGH DISTRICT) 
Location. A series of dikes, floodwalls, channel improvements, 
and reservoirs/lakes in Ohio River Basin within 
Pittsburgh District. 
26-8

PITTSBURGH, PA., DISTRICT 
Existing project. Individual projects considered in 
comprehensive plan within Pittsburgh District. (See 
Tables 26-B, 26-K and 26-L on Acts authorizing existing 
projects, local protection projects and reservoirs.) 
Operations during fiscal year. New work: None by the 
United States except as stated in individual projects. 
Completed local protection projects operated and maintained 
by local interests, including those projects for 
which individual reports have been included, prevented 
flood damages of an estimated $30,558,000 during this 
fiscal year. Total flood damages prevented through September 
30, 1986 are $700,801,000. 
24. SHENANGO RIVER LAKE, OHIO 
RIVER BASIN, PA AND OH 
Location. Dam is on Shenango River about 0.8 mile 
above Sharpsville, PA, and about 33 miles above junction 
of river with Mahoning River, which unite near New 
Castle, PA, to form Beaver River. Reservoir is in Mercer 
County, PA, and Trumbull County, Ohio. (See Geological 
Survey Chart for Kinsman, Ohio, and Shenango, PA.) 
Existing project. A reservoir for flood control, low-flow 
augmentation and recreation. Dam consists of a concrete 
gravity structure with gate-controlled outlet works and an 
uncontrolled center spillway section. Authorized project is 
complete. Reservoir is in operation for low-water regulation 
purposes in Shenango River valley below and for 
flood control as a unit of a coordinated reservoir system 
for protection of Shenango River valley and the Beaver 
and upper Ohio River Valley, generally. Construction of 
dam was started in March 1963 and completed May 1965. 
Land acquired for project consists of 14,632.2 acres in fee 
and easements over 197.7 acres. Future work consists of 
completion of project lands of any additional recreation 
facilities as required to serve the public needs. For further 
project description, see Annual Report for 1962, page 
1230. Project was authorized by 1938 Flood Control Act. 
Local cooperation. None required by law. 
Operations during fiscal year. Operation and 
maintenance, general: Reservoir was operated for benefit 
of flood control and low-flow augmentation, as required, 
and necessary repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by 
this reservoir for this period were $2,223,000. Total flood 
control benefits for this dam through September 30, 1986 
are $18,901,000. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management and operation and maintenance of 
public-use facilities continued. 
25. STONEWALL JACKSON LAKE, 
WV 
Location. In Lewis County, North Central West 
Virginia, on the West Fork River, which joins the Tygart 
River at Fairmont, West Virginia to form the Monongahela 
River. Damsite is located at Brownsville, West 
Virginia, about 4 miles south of Weston and 72 miles 
above mouth of West Fork River at Fairmont, WV. (See 
Geological Survey Charts for Weston and Crawford, WV.) 
Existing project. Provides for construction of a reservoir 
for flood control, water supply, water quality control, area 
redevelopment and recreation. Dam would be of the concrete 
gravity type, 95 feet high and 620 feet long. Outlet 
works will consist of five multi-level sluices, spillway will 
be uncontrolled. Storage capacity will be 74,650 acre-feet 
controlling an area of 102 square miles. Project was authorized 
by 1966 Flood Control Act. Estimated initial Federal 
cost for new work (1986) is $208,000,000 (includes 
$20,070,000 reimbursement by non-Federal interests.) 
Surface land acquired for project consists of 20,839 acres. 
Local cooperation. Local interests are required to make 
arrangements for repayment, under the provisions of the 
Water Supply Act of 1958, as amended, of that part of the 
construction cost and annual operation, maintenance and 
replacement costs allocated to municipal and industrial 
water supply, an amount presently estimated at 
$4,200,000 for construction; and $15,000 annually for 
operations, maintenance and replacements. Also, in accordance 
with Federal Water Project Recreation Act, local 
interests are required to administer project land and water 
areas for recreation and fish and wildlife enhancement, 
pay, contribute in kind or repay (which may be through 
user fees) with interest, one-half of the separable first cost 
of the reservoir project allocated to recreation and fish and 
wildlife enhancement, an amount presently estimated at 
$15,870,000; bear all costs of operation, maintenance and 
replacement of recreation and fish and wildlife land and 
facilities, the amount involved being currently estimated 
on an average annual basis to be $1,117,500, exercise to 
the full extent of their legal capability, control against 
removal of streamflow made available for water quality 
control; and contribute to the control of pollution of 
streams subject to low-flow augmentation by adequate 
treatment or other methods of controlling wastes at their 
source. The requirements of Section 221 were amended in 
1971 to exempt assurances for future demands for water 
supply pursuant to the Water Supply Act of 1958 from the 
contractual requirements of the Act. Accordingly, the City 
of Weston, West Virginia, has provided assurances that it 
will enter into a water supply contract with the Department 
of the Army within a period of time which will 
permit paying out the costs allocated to the water supply 
storage within the life of the project. A recreation costsharing 
contract, in accordance with the requirements of 
the Federal Water Project Recreation Act, P.L. 89-72, was 
executed by the State of West Virginia on March 27, 1977. 
Local cooperation assurances for recreation cost-sharing 
were executed by the Governor and Attorney General of 
West Virginia on May 29, 1973. In this connection, Section 
8 of P.L. 92-222 deleted the requirement that the 
State of West Virginia "hold and save the United States 
free from damages resulting from water rights claims due 
to construction and operation of the project." Legislation 
relieving Stonewall Jackson Lake, WV, project of the requirements 
of Section 221, P.L. 96-611 vas contained in 
Water Resources Development Act of 1974 signed by the 
President on March 7, 1974. 
Operations during fiscal year. New work: Relocation of 
US Rt. 30, Section 2 contract, awarded Sep 12, 1984, 
progressed to 94% completion. Relocation of US Rt. 30, 
Section 3 contract, awarded Mar 26, 1985 for $5,926,755, 
26-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
progressed to 78% completion. Contract for Relocation of 
WV Rt. 44 and Associated Routes, awarded Feb 18, 1986 
for $4,605,724, progressed to 18% completion. 
Contract for construction of Dam, awarded Jul 29 1983 
for $15,985,064, scheduled for completion by Sep 5, 1987, 
progressed to 93% completion. 
Construction of Equitable Gas Company Access Roads, 
Phase II, awarded May 31, 1985 for $1,267,138, progressed 
to 97% completion. Construction of Equitable Gas 
Company Access Roads, Phase III, awarded Mar 25, 1986 
for $1,250,662 progressed to 22% completion. Costreimbursable 
contract with Equitable Gas Company for 
Phase II Piping Work was negotiated and awarded on 
March 8, 1985, for an estimated amount of $4,276,808, 
progressed to 56% completion. 
Contract for Relocation of Baltimore and Ohio Railroad 
Track and Appurtenances, awarded Jun 18, 1985 for 
$3,496,215, progressed to 86% completion. Costreimbursable 
contract with Baltimore and Ohio Railroad 
for Track Raise and Communication Lines was negotiated 
and awarded on January 22, 1985 for an estimated amount 
of $405,000, progressed to 64% completion. 
Cost-reimbursable contract with Consolidated Gas 
Transmission Corporation for Relocation, Removal or 
Abandonment and Subordination of Gas Pipelines, Gas 
Production Wells and Access Roads was negotiated in 
July 1984, for an estimated amount of $2,725,000, is 
scheduled to be completed by September 1987. 
Roanoke Elementary School construction contract, 
awarded Aug 1, 1984 for $3,193,000 was completed on 
July 17, 1986. 
Contract for construction of Maintenance Complex, 
Roanoke Bay Recreation Area, awarded June 10, 1986 for 
$1,989,000 progressed to 2% completion. Contract for 
Reservoir Clearing was awarded on September 26, 1986 
for $1,114,000. 
Surface land acquired for the project consists of 20,839 
acres. 
Land acquisition, detailed engineering work and construction 
continued and all items of work were progressing 
on schedule. Estimated flood control benefits through 
September 30, 1986 were $28,555,000. 
26. TIONESTA LAKE, OHIO RIVER 
BASIN, PA 
Location. Dam is on Tionesta Creek, 1.25 miles above 
junction of creek with Allegheny River at Tionesta, PA, 
and about 78 miles northeast of Pittsburgh, PA. Reservoir 
is entirely in Forest County, PA. (See Geological Survey 
Charts for Tionesta, Tidioute and Sheffield, PA.) 
Existing project. A flood control reservoir dam of 
earthfill type with separate uncontrolled saddle spillway 
and tunnel outlet works. Authorized project is complete. 
Reservoir is in operation as a unit of a coordinated 
reservoir system designed for protection of Pittsburgh and 
reduction of flood heights in upper Ohio Valley, generally. 
Construction of dam was started in May 1938 and completed 
January 1941. Land acquired for project consists of 
2,797.3 acres in fee and easements over 13.1 acres. Future 
work consists of provision on project lands of additional 
recreational facilities as required to serve public needs. 
Project was authorized by Flood Control Acts of 1936 and 
1938. For further project description see Annual Report 
for 1962, page 1203. 
Local Cooperation: None required by law. 
Operations during fiscal year. Operation and 
maintenance general: Reservoir was operated for benefit of 
flood control and low-flow augmentation, as required, and 
necessary repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by this 
reservoir for this period were $5,250,000. Total flood 
control benefits for this reservoir through September 30, 
1986 are $172,325,000. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management and operation and maintenance of 
public-use facilities continued. 
27. UNION CITY DAM, PA 
Location. In Erie County, northwestern Pennsylvania, 
on French Creek, a tributary of Allegheny River. Damsite 
is 24 miles upstream from Cambridge Springs, PA, and 41 
miles upstream from Meadville, PA. (See Geological Survey 
Chart for Union City, PA - NY.) 
Existing project. A flood control reservoir dam of earth 
embankment nongated type with uncontrolled sidechannel 
spillway. Outlet works consist of a lower outlet 
located in valley floor constructed of reinforced concrete 
conduit 8 feet by 4.5 feet and an upper outlet consisting of 
an uncontrolled slot 9.5 feet wide through the north end of 
the ogee weir in the spillway. Dam is 1,420 feet long at top 
rising 88 feet above streambed and provides gross capacity 
of 47,640 acre-feet from a drainage area of 222 square 
miles. Project authorization was modified to provide for a 
conservation pool and addition of recreation facilities. On 
November 5, 1974, a referendum proposal was defeated by 
the constituents of Erie County in regard to the costsharing 
for construction of recreation facilities. In view of 
the foregoing, all action toward implementation of the 
authorized project modification was discontinued. Reservoir 
is operated as one of a two-reservoir system for 
reduction of flood stages in French Creek Basin between 
damsite and mouth, Allegheny River from Franklin, PA, 
to Pittsburgh, PA, inclusive, and upper Ohio River Valley. 
Initial highway relocations were completed in October 
1968 and remaining highway relocations were completed 
in May 1972. Construction of the dam was started in July 
1968 and completed in September 1971. Land acquired for 
project consists of 161.4 acres in fee and easements over 
2,458.4 acres. Existing project was authorized by 1962 
Flood Control Act. 
Local cooperation. Local interests are required to inform 
affected interests in French Creek Basin at least annually, 
that the system of reservoirs of which Union City Dam is a 
part, will not provide protection against maximum floods. 
November 10, 1964 the Department of Forests and Waters 
of the Commonwealth of Pennsylvania furnished 
formal assurances of local cooperation in respect to 
notifying local interests at least annually that the system 
of reservoirs will not provide protection against maximum 
floods. A referendum on the ballot during the November 
26-10

PITTSBURGH, PA., DISTRICT 
1974 election regarding the approval to cost-share the 
maintenance of a summer pool was defeated by the local 
voters. 
Operations during fiscal year. Operation and 
maintenance, general: Maintenance of the structure and 
appurtenances was performed as required. This dam acted 
as an uncontrolled detention type dam during the fiscal 
year. Estimated flood control benefits achieved by this 
reservoir for this period were $550,000. Total flood control 
benefits for this reservoir through September 30, 1986 are 
$14,419,000. 
28. WOODCOCK CREEK LAKE, PA 
Location. In Crawford County, northwestern 
Pennsylvania, on Woodcock Creek, a tributary of French 
Creek. Damsite is about 4.1 miles above mouth of Woodcock 
Creek and about 5 miles northeast of Meadville, PA. 
(See Geological Survey Chart for Meadville, PA.) 
Existing project. A flood-control reservoir dam of rolledearth 
embankment type, gate-controlled outlet works with 
a 6 foot-wide by 7.75 foot-high conduit and uncontrolled 
saddle spillway on the left abutment. Dam is 4,650 feet 
long at top rising 90 feet above streambed and provides for 
gross capacity of 20,000 acre-feet from a drainage area of 
46 square miles. Reservoir is operated as one of a tworeservoir 
system for reduction of flood stages in French 
Creek Basin between damsite and mouth, Allegheny River 
from Franklin, PA, to Pittsburgh, PA, inclusive, and 
upper Ohio River Valley. Authorized project is complete. 
Construction of dam was started in July 1970 and completed 
in July 1973. Land acquired for project consists of 
1,731.5 acres in fee and easements over .56 acres. Project 
was authorized for flood control and recreation by 1962 
Flood Control Act. Storage for water quality control was 
added to the project during the preconstruction planning 
stage. 
Local cooperation. Local interests must inform affected 
interests in French Creek Basin at least annually, in a 
manner satisfactory to District Engineer, that a system of 
reservoirs of which Woodcock Creek Lake is a part, will 
not provide protection against maximum floods. Pennsylvania 
Department of Forests and Waters assumed responsibility 
of local cooperation for project. 
Operations during fiscal year. New work: Contract for 
Construction of Sanitary Tie-In, Saegertown Authority, 
awarded Sep 14, 1984 for $549,549, was completed on May 
22, 1986. Operation and maintenance, general: Maintenance 
of the structure and appurtenances was performed 
as required. Estimated flood control benefits achieved by 
this reservoir for this period were $185,000; total through 
September 30, 1986 is $1,607,000. 
29. YOUGHIOGHENY RIVER LAKE, 
OHIO RIVER BASIN, PA AND MD 
Location. Dam is on Youghiogheny River about 74.2 
miles above its junction with Monongahela River at 
McKeesport, PA. It is 1.2 miles upstream from Confluence, 
PA, and about 57 miles southeast of Pittsburgh, 
PA. Reservoir is in Fayette and Somerset Counties, PA, 
and Garrett County, MD. (See Geological Survey Charts 
for Confluence, PA, Accident, MD, West Virginia and 
Pennsylvania.) 
Existing project. Reservoir for flood control, low-flow 
augmentation, and pollution abatement purposes. Dam is 
rolled-earthfill type with separate uncontrolled side 
channel spillway and tunnel outlet works. Authorized project 
is complete. Reservoir is in operation for flood control, 
low-flow augmentation, and pollution abatement purposes. 
For flood control, reservoir is operated as a unit of a 
coordinated reservoir system designed for protection of 
Pittsburgh and reduction of flood heights in upper Ohio 
Valley, generally. Construction of dam was started in June 
1940 and completed May 1944. Land acquired for project 
consists of 3,914.9 acres in fee and easements over 0.62 
acre. A license was issued Commonwealth of Pennsylvania 
covering fish conservation and management in Pennsylvania 
portion of reservoir. Future work consists of provision 
on project lands of additional recreational and 
sanitary facilities as required to serve public needs. 
Project was selected for construction under general authorization 
for Ohio River Basin in 1938 Flood Control 
Act. For further project description see Annual Report for 
1962, page 1223. 
Local cooperation. None required. 
Operations during fiscal year. New work: Operation and 
maintenance, general: Design Memorandum No. 1, Master 
Plan was completed in Aug 1981 and approved by division 
on Nov 15, 1982. Reservoir was operated for benefit of 
flood control, as required, and necessary repairs were made 
to structures and appurtenances as required. Estimated 
flood control benefits achieved by this reservoir for this 
period were $19,929,000. Total flood control benefits for 
this dam through September 30, 1986 are $151,905,000. 
Activities under reservoir management' program comprising 
sanitation measures, conservation, land management, 
and operation and maintenance of public-use facilities 
were continued. 
30. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent acts 
require local interests to furnish assurances that they will 
maintain and operate certain local protection projects 
after completion in accordance with regulations prescribed 
by Secretary of the Army. District Engineers are responsible 
for administration of these regulations within boundaries 
of their respective districts. Inspections were made 
of completed units transferred to local interests for 
maintenance and operation and local interests were advised, 
as necessary, of measures required to maintain 
these projects in accordance with standards prescribed by 
regulations. (See Table 26-M for dates of inspections.) 
Costs for this fiscal year, $41,330. Total cost to September 
30, 1986 was $970,547. 
31. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 26-E on other authorized flood control 
projects. 
26-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
32. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
For flood control activities pursuant to Section 
205, Public Law 858, 80th Congress, as amended (preauthorization) 
See Table 26-N. 
For emergency bank protection (Sec. 14 of 1946 Flood 
Control Act, Public Law 526, 79th Cong.) 
See Table 26-N. 
For Streambank Erosion Control Evaluation and 
Demonstration Act of 1974 (Sec. 32, Public Law 251, 
93rd Cong.) 
See Table 26-N. 
For Shoreline Erosion Control Demonstration Act of 
1974 (Sec. 54, Public Law 251, 93rd Congress) 
See Table 26-N. 
Flood control and coastal emergencies (Public Law 99, 
84th Cong., and antecedent legislation). 
Disaster Preparedness $134,215 
Rehabilitation: 
Buckhannon, WV. 59,618 
Elkins, Randolph County, WV. 6,567 
Advance Measures: 
Parsons, WV 194,687 
Total cost for fiscal year: $395,087 
General Investigations 
33. SURVEYS 
Flood control studies 
Review of authorized projects 
Coordination with other agencies 
Special investigations 
Federal Energy Regulatory Commission 
Continuation of Planning and Engineering: 
Grays Landing Lock and Dam 
(Lock and Dam 7), Monongahela River, PA. 
Point Marion Lock and Dam 
(Lock and Dam 8), Monongahela River, PA 
and WV 
Total cost for fiscal year: 
$1,826,013 
4,956 
18,143 
105,376 
53,522 
963,898 
380,678 
$3,35 2,5 86 
34. COLLECTION AND STUDY OF 
BASIC DATA 
Costs this fiscal year were $181,682 for flood plain 
management services and $6,116 for related hydrologic 
studies. 
35. RESEARCH AND DEVELOPMENT 
None. 
26-12

PITTSBURGH, PA., DISTRICT 
TABLE 26-A COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section Sep 30, 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 1986 
Navigation - Locks and Dams 
1. Allegheny River New Work 
PA Approp. 
Cost 
Maint. 
Approp. 
Cost 
3. Monongahela New Work 
River, PA and Approp. 
WV Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
5. Tygart Lake, New Work 
WV Approp. 
Cost 
Maint. 
Approp. 
Cost 
Flood Control - Local Protection 
7. Allegheny River New Work 
Oil City, PA Approp. 
Cost 
8. Chartiers New Work 
Creek, PA Approp. 
(Federal Funds) Cost 
New Work 
(Contributed Contrib. 
Funds) Cost 
9. Elkins, WV New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
10. Girty's Run, New Work 
Millvale, PA Approp. 
(Federal Funds) Cost 
New Work 
(Contributed Contrib. 
Funds) Cost 
11. Johnstown, PA New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
12. Punxsutawney, New Work 
Ohio River Approp. 
Basin, PA Cost 
Maint. 
Approp. 
Cost 
13. Root Creek, New Work 
Bolivar, NY Approp. 
Cost 
Flood Control - Reservoirs 
14. Berlin Lake 
Ohio River 
Basin, OH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
3,270,300 
3,248,945 
3,788,000 
3,762,006 
80 - 
7,665,440 8,496,900 
7,260,530 8,375,983 
- -120,000 
66,402 44,567 
103,046 
710,000 
642,587 
-417,500 
-195,337 
689,500 
700,570 
349,000 98,000 
620,143 244,784 
-18,376 
5,221 
5,221 
26,508 
- 6,000 
5,488 4,181 
- -3,000 
19 - 
376,000 131,000 
127,912 314,450 
308,000 
28,711 
-5,000 
102,047 
-2,500 
56 
1,048,000 
1,110,833 
-6,000 
263,795 
18,426 
3,971,500 4 
4,037,823 4 
39 
8,960,000 9 
9,613,100 10 
1,698 
12 
642,000 
705,320 
69,000 1 
68,648 
41,764 
8,000 
9,619 
-56,591 
19,281 
1,988 
12,104 
2,172 
,975,000 
,986,772 
18,157,860' 
18,157,860' 
58,336,3622 
58,312,4192 
400,000 129,603,0853 
209,436 129,412,5214 
,721,852 146,156,4065 
,063,705 146,044,0506 
- 15,857,000 
7 15,856,779 
- 19,077,9327 
- 19,077,9327 
726,400 8,763,2396 
741,774 8,738,293" 
20,000 1,311,000 
95,599 1,283,967 
- 26,586,186 
5,134 26,560,187 
- 4,225,188 
- 4,204,498 
- 1,772,627 
- 1,772,627 
3,500 231,987 
2,838 230,799 
- 2,662,000 
- 2,648,849 
- 701,722 
- 701,722 
- 8,865,3889 
- 8,865,3889 
7,000 3,810,205 
7,098 3,810,005 
- 3,586,107 '" 
- 3,586,107"' 
8,000 1,022,888" 
8,346 1,022,780" 
-5,949 
787 
1,591,436 
1,591,436 
- - - 8,739,98712 
- -- - 8,739,98712 
1,259,000 1,425,500 1,366,700 14,888,983' 3 
1,025,185 1,610,473 1,397,114 14,822,58413 
26-13

TABLE 26-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section Sep 30, 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 1986 
15. Conemaugh 
River Lake, Ohio 
River Basin, PA 
16. Crooked Creek 
Lake, Ohio 
River Basin, PA 
17. East Branch, 
Clarion River 
Lake, Ohio 
River Basin, PA 
18. Kinzua Dam and 
Allegheny 
Reservoir, Ohio 
River Basin, PA 
and NY 
19. Loyalhanna 
Lake, Ohio River 
Basin, PA 
20. Mahoning Creek 
Lake, Ohio 
River Basin, PA 
21. Michael J. Kirwan 
Dam and 
Reservoir, Ohio 
River Basin, OH 
22. Mosquito Creek 
Lake, Ohio River 
Basin, OH 
23. Ohio River Basin, 
Pittsburgh, PA 
District 
Consolidated 
24. Shenango River 
Lake, Ohio River 
Basin, PA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
190,398 
476,000 
529,107 
33,500 
1,041 
1,125,000 
1,217,561 
-4,000 
7,405 
670,100 
460,055 
63,000 
68,849 
1,236,200 
1,186,299 
892,617 804,423 
703,184 915,649 
-5,162 
1,129,000 
1,120,473 
1,050,000 
948,001 
-20,000 
100,519 
1,131,100 
1,146,746 
84,066 
531,000 
540,383 
42 
765,000 
455,236 
1,214 
1,203,000 
1,163,944 
2,000,000 
1,399,020 
-5,000 
411 
826,577 
1,001,587 
-190,000 
-95,443 
584,000 
546,449 
659,100 
808,210 
742,091 717,000 
768,355 880,435 
26,610 
1,726,000 
1,713,527 
452,500 
586.993 
8,286 
1,065,500 
1,138,420 
5,000 
229,472 
940,705 
919,272 
30,160 
30,160 
780,500 
803,900 
580,807 
768,377 
46,012,411 '4 
46,012,411' 4 
7,265,904 
7,235,107 
43,001 4,474,524 '5 
- 4,431,52315 
2,619,000 12,380,92116 
2,701,478 12,330,968'6 
- 9,539,586' 7 
- 9,539,58617 
539,482 7,237,85718 
514.479 7,198,07818 
1,083,000 
1,115,419 
-100,000 
230,032 
953,700 
999,266 
650,200 
656,660 
655,500 
652,378 
536,000 523,000 514,500 683,000 
513,256 531,555 538,675 672,132 
72 
1,357,000 
1,391,237 
- -10,500 
1,239,000 2,089,000 
1,270,706 2,117,222 
2,019,000 
2,068,686 
109,309,07619 
109,298,20519 
14,495,278 
14,472,946 
3,140,000 
2,911,351 
5,727,53120 
5,727,53120 
10,272,25621 
10,241,44021 
7,144,97322 
7,138,81423 
7,378,516 
7,337,928 
47,033 
47,033 
17,376,09724 
17,376,09724 
6,985,29625 
6,964,45025 
4,253,02926 
4,253,02926 
6,444,864 
6,405,116 
985,19727 
985,19727 
40,227,20128 
40,209,89428 
16,640,6172 
16,576,72829 
26-14

PITTSBURGH, PA., DISTRICT 
TABLE 26-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section Sep 30, 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 1986 
25. Stonewall Jack- New Work 
son Lake, Ohio Approp. 21,500,000 22,300,000 25,300,000 24,106,000 159,716,200 
River Basin,WV Cost 20,229,662 21,414,527 26,553,633 25,450,413 159,155,299 
26. Tionesta Lake, New Work 
Ohio River Approp. 278,000 17,000 -17,286 -32,403 7,792,37830 
Basin, PA Cost 436,326 218,519 41,048 - 7,788,3793' 
Maint. 
Approp. 898,000 1,025,000 811,000 1,060,000 11,263,95332 
Cost 785,005 895,102 1,049,901 1,074,808 11,226,83932 
27. Union City New Work 
Dam, Ohio Approp. - - - - 14,559,800 
River Basin, PA Cost - - - - 14,559,800 
Maint. 
Approp. 246,000 345,000 417,000 512,000 3,022,668 
Cost 244,224 288,948 445,085 528,818 2,992,693 
28. Woodcock Creek New Work 
Lake, Ohio Approp. - 540,000 23,398 5,376 20,553,47433 
River Basin, PA Cost 313,216 194,349 392,820 137,846 20,538,568"4 
Maint. 
Approp. 538,500 582,900 592.000 749,000 5,178,271'" 
Cost 537,291 555,237 613,235 751,253 5,139,3173" 
29. Youghiogheny New Work 
River Lake, Approp. 277,000 5,000 -6,112 -10,959 12,521,167 6 
Ohio River Cost 27,096 279,125 7,397 2,334 12,521,167" 
Basin, PA and Maint. 
MD Approp. 1,527,500 1,229,200 1,253,000 2,602,000 16,532,389 : 
Cost 1,119,522 1,561,741 1,312,586 2,409,684 16,275,948"' 
1. Includes $2,453,737 from emergency relief funds and 
$1,250,049 from public works funds. 
2. 'Includes $64,365 public works acceleration, executive 
funds (1963) and $191,400 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
3. Includes $5,420,541 for new work for previous projects 
and $400,000 appropriated to Grays Landing, L/D 7, PA in 
FY 1986. 
4. Includes $209,436 expended for Grays Landing, L/D 7, 
PA in FY 1986. 
5. Includes $22,549 public works acceleration, executive 
funds (1963), $742 for maintenance for previous project and 
$582,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
6. Includes $22,549 public works acceleration, executive 
funds (1963), $742 for maintenance for previous project and 
$461,466 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
7. Includes $1,999,995 emergency relief funds, 
$10,000,000 public works funds, $234,000 Code 711 funds and 
$412,088 Code 713 funds; excludes $409,622 contributed by 
local interest. 
8. Includes $89,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
9. Includes $33,423 from emergency relief funds. 
10. Excludes $180,485 for new work expended from 
contributed funds. 
11. Includes $283,988 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
12. Includes $1,542,500 Code 711 funds, $809,700 Code 
712 funds and $99,111 Code 713 funds; excludes $100,000 
contributed by local interest. 
13. Includes $40,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
14. Includes $5,351 from emergency relief funds and 
$328,000 Code 711 funds. 
15. Includes $63,788 from emergency relief funds and 
$269,635 Code 711 funds. 
16. Includes $45,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
17. Includes $156,812 Code 711 funds. 
18. Includes $322,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
19. Includes $2,791 from emergency relief funds, $14,622 
Code 711 funds and $568,265 Code 713 funds; excludes 
$389,370 contributed by local interest. 
20. Includes $7,339 from emergency relief funds and 
$274,669 Code 711 funds. 
21. Includes $256,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
22. Includes $25,671 emergency relief funds, $162,381 
Code 711 funds and $561,247 Code 713 funds; excludes 
$500,086 contributed by local interests. 
23. Includes $25,671 emergency relief funds, $162,381 
Code 711 funds and $555,088 Code 713 funds; excludes 
$456,611 contributed by local interests. 
24. Includes $74,900 Code 711 funds; excludes 
$4,394,026.19 for new work contributed by local interest. 
25. Includes $315,500 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
26. Includes $122,729 Code 711 funds and $94,900 Code 
713 funds. 
27. Includes $8,914 from emergency relief funds. 
28. Includes $1,730,100 Code 711 funds and $1,618,300 
Code 713 funds. 
29. Includes $152,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
26-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
30. Includes $2,303,076 Code 711 funds ($256,760 
provided from the Productive Employment Appropriations 
Act PL 98-8, 1983 funds), $275,900 Code 712 funds, and 
$24,201 emergency relief funds. 
31. Includes $2,299,077 Code 711 funds, ($252,761 
provided from the Productive Employment Appropriations 
Act PL 98-8, 1983 funds), $275,900 Code 712 funds, and 
$24,201 emergency relief funds. 
32. Includes $203,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
33. Includes $1,679,774 Code 711 funds. 
34. Includes $1,664,869 Code 711 funds. 
35. Includes $85,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
36. Includes $2,846,263 Code 711 funds ($293,000 
provided from the Productive Employment Appropriations 
Act (PL 98-8) 1983 funds). 
37. Includes $591,000 provided from the Productive 
Employment Appropriations Act (PL 98-8) 1983 funds. 
26-16 
TABLE 26-A 
(Continued)

PITTSBURGH, PA., DISTRICT 
TABLE 26-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Replace lock and dam 1 by a dredged channel, 9 feet deep and 
200 feet wide up to lock 2, and construct new locks and 
dams 2 and 3, to replace existing locks and dams 2 and 3. 
Construct lock and dam 9, raising crest of dam 8, and 
dredging a navigable channel to head of pool 8. 
June 26, 19342 Operation and care of locks and dams provided for with funds 
from War Department appropriation for rivers and harbors. 
MONONGAHELA RIVER, PA AND WV 
Mar 3, 1899 Enlarge and improve lock and dam 6; additional works at 
lock 3; new repair steamer and new dredge boat with 
equipment; all at an estimated cost of $185,556. 
June 13, 1902 Rebuild lock and dam 2 at estimated cost of $655,961. 
(Estimate increased in 1910 to $698,961.) 
Mar 3, 1905 Acquisition of land and additional improvements at 5 and 6 
at a cost of $7,850. 
Mar 3, 1905 Rebuild lock and dam 3 at estimated cost of $589,196. 
Mar 2, 1907 Reconstruct lock and dam 5 at estimated cost of $756,042. 
Mar 4, 1913 
Sep 22, 1922 
July 3, 1930 
Jan 31, 19313 
June 26, 19342 
3. May 17, 1950 
5. 
Jan 11, 1934 
Aug 30, 1935 
Reconstruct lock and dam 6 at estimated cost of $356,400. 
(Estimate increased in 1916 to $418,860.) 
Additional improvements at estimated cost as follows: 
Guide walls and guard walls, 1 to 6, $1,255,130; 
Lengthen land chamber of lock 3 to 720 feet, $787,722; 
New chamber (360 feet long), lock 4, $699,786; 
Lock and dam 7, $1,161,241; Lock and dam 8, $1,165,758; 
Lock and dam 7 (second chamber), $419,126; 
Lock and dam 8 (second chamber), $504,465; 
Reconstruct dam 4, $397,211; Marine ways, repair plant, 
office and warehouse, $250,000, for a total of $6,640,439. 
Construct new locks and dam 2.5 miles below existing 
structure, at estimated cost of $2,175,000 in lieu of work 
authorized at old lock and dam 4. 
Chief of Engineers authorized to locate new locks and dam 4 
above existing structure and on such site as they may deem 
most desirable. 
Operation and care of locks and dams provided for with funds 
from War Department appropriations for rivers and harbors. 
Modification of existing project as follows: 
Provide 2 new locks and dams similar to Morgantown lock 
and dam to replace existing locks and dams 12 to 15, inclusive. 
Provide a movable crest on existing dam 8 to raise existing 
pool-full elevation 4 feet. 
Provide a navigation channel of 300-foot minimum bottom 
width and a 9-foot project depth above lock and dam 8. 
Provide an extension of navigable channel of upper 
Monongahela River, into lower Tygart River for 2.1 miles at a 
maximum bottom width of 200 feet and a 9-foot project depth. 
TYGART RIVER LAKE, WV 
Construction of a dam and reservior for low water regulation 
and flood control 
ALLEGHENY RIVER, PA. (See Section 1 of Text) 
Aug 5, 1886 For lock and dam 1. (Fixed dam contemplated. Sep 29, 1891 
Secretary of War authorized change to a movable dam.) 
June 3, 1896 For locks and dams 2 and 3. 
26-17 
July 25, 1912 For locks and dams 4 to 8. inclusive. 
July 3, 1930 For a depth of 9 feet in the lower 61 miles. 
Annual Report 1886, p. 1545, 
Annual Report 1891, p. 2366 
H. Doc. 204, 54th Cong., 
1st sess., and Annual Report 
1896, p. 2212 
H. Doc. 540, 62d Cong., 
2d sess. 
H. Doc. 356, 71st Cong., 
2d sess. 
Rivers and Harbors 
Committee, Doc. 16, 
72d Cong., 1st sess. 
H. Doc. 721, 71st Cong., 
3d sess., and Rivers and 
Harbors Committee, Doc. 27, 
73d Cong., 2d sess. 
Annual Report 1897, p. 2423 
Annual Report 1909, p. 1756 
Annual Report 1904, p. 460 
H. Doc. 209, 58th Cong., 
2d sess. 
H. Doc. 209, 58th Cong., 
2d sess. 
H. Doc. 1217, 62d Cong., 
3d sess. 
H. Doc. 288, 67th Cong., 
2d sess. 
Rivers and Harbors 
Committee, Doc 22, 
70th Cong., 2d sess. 
S. Doc. 100, 81st Cong., 
1st sess. 
H. Doc. 1792, 64th Cong. 
2nd Sess. 
H. Doc. 106, 76th Cong. 
1st Sess. 
Aug 30, 1935' 
Aug 30, 1935' 
3.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 26-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jun 28, 1938 
11. 
Jun 28, 1938 
12. 
Jun 28, 1938 
14. 
Jun 28, 1938 
Dec 22, 1944 
as amended 
15. 
Jun 22, 1936 
amended by 
Jun. 28, 1938 
Dec 22, 1944 
as amended 
16. 
Jun 22, 1936 
amended by 
Jun. 28, 1938 
Dec 22, 1944 
as amended 
17. 
18. 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Jun 22, 1936 
amended by 
Jun 28, 1938 
modified by 
Aug 18, 1941 
Dec 22, 1944 
as amended 
ELKINS, WV 
For construction of local flood protection projects. 
JOHNSTOWN, PA 
For construction of local flood protection projects. 
PUNXSUTAWNEY, OHIO RIVER BASIN, PA 
For construction of local flood protection projects. 
BERLIN LAKE, OHIO RIVER BASIN, OH 
Construction of a dam and reservoir for flood control and low 
water regulation. 
Construction, operation & maintenances of recreation facilities. 
CONEMAUGH RIVER LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
CROOKED CREEK LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
EAST BRANCH CLARION RIVER LAKE, 
OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control and low 
water regulation. 
Construction, operation & maintenance of recreation facilities. 
KINZUA DAM AND ALLEGHENY RESERVOIR, 
OHIO RIVER BASIN, PA AND NY 
Construction of a dam and reservoir for flood control and low 
water regulation and recreation. 
Construction of a dam and reservoir for flood control, pollution 
abatement, low water regulation and recreation. 
Construction, operation & maintenance of recreation facilities. 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Sec. 4, Flood Control Act. 
of 1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
H. Doc. 300, 76th Cong. 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
26-18

PITTSBURGH, PA., DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jun 22, 1936 
amended by 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Jun 22, 1936 
amended by 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Jul 3, 1958 
Jul 14, 1960 
Jun 28, 1938 
Dec 22, 1944 
as amended 
19. LOYALHANNA LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
MAHONING CREEK LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
MICHAEL J. KIRWAN DAM AND RESERVOIR, OH 
Construction of a dam and reservoir for flood control, water 
supply, low water, regulation and recreation. 
To define cost-sharing arrangement for municipal & industrial 
water supply & water for pollution abatement purposes. 
MOSQUITO CREEK LAKE, OHIO RIVER BASIN, OH 
Construction of a dam and reservoir for flood control, low water 
regulation and water supply storage. 
Construction, operation & maintenance of recreation facilities. 
OHIO RIVER BASIN - Pittsburgh District 
Aug 28, 1937 Construct levees, floodwalls, and drainage structures for protection Flood Control Committee, 
of cities and towns in Ohio River Basin. Projects to be selected by Doc. 1, 75th Cong., 1st sess. 
Chief of Engineers with approval of Secretary of War at a cost not 
to exceed $24,877,000 for construction. 
Jun 28, 1938 Approved general comprehensive plan for flood control and other Flood Control Committee, 
purposes in Ohio River Basin as may be advisable in discretion of Doc. 1, 75th Cong., 1st sess. 
Secretary of War and Chief of Engineers, and for initiation and 
partial accomplishment of plan, authorized $75 million for 
reservoirs and $50,300,000 for local flood protection works. 
Aug 18, 1941 Additional $45 million for prosecution of comprehensive plan for H. Doc. 300, 76th Cong. 
Ohio River Basin. 1st Sess. 
Dec 22, 1944 Additional $70 million for further prosecution of comprehensive H. Doc. 762, 77th Cong., 
plan for Ohio River Basin, including additional projects in 2d sess. 
tributary basins. 
Jul 24, 1946 Additional $125 million for further prosecution of comprehensive H. Doc. 506, 78th Cong., 
plan including additional projects in tributary basins. 1st sess. 
May 17, 1950 Additional $100 million for prosecution of comprehensive plan for S. Doc. 20, 81st Cong. 
Ohio River Basin. 1st Sess. 
Dec 30, 1963 Additional $150 million for further prosecution of comprehensive Public Law 88-253, 
plan for flood control and other purposes in Ohio River Basin. 88th Cong., 1st sess. 
Jun 18, 1965 Additional $89 million for further prosecution of comprehensive H. Doc., 6755, 89th Cong., 
plan for Ohio River Basin. 1st sess. 
May 12. 1967 Additional $38 million for further prosecution of comprehensive Public Law 90-17. 
plan for Ohio River Basin. 90th Cong., 1st sess. 
Aug 13, 1968 Additional $35 million for further prosecution of comprehensive Public Law 90-483, 
plan for Ohio River Basin. 90th Cong., 2d sess. 
Jun 19, 1970 Additional $69 million for further prosecution of comprehensive 11. Doc. 15166. 91st Cong.. 
plan for Ohio River Basin. 2d sess. 
Mar 7. 1974 Additional $120 million for further prosecution of comprehensive 11. Doc. 10203, 93rd Cong.. 
plan for Ohio River Basin. River Basin Monetary 
Oct 22. 1976 Authorized phase I design memorandum stage of advanced 
engineering and design of the project for abatement of acid mine 
drainage in the Clarion River Basin, Pla. 
26-19 
Authorization Act of 1974. 
Water Resources I)evelopment 
Act of 1976; IPublic Law 
94-587. Sec. 101(a). 
TABLE 26-B 
(Continued) 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
H. Doc. 191, 85th Cong. 
1st Sess. 
Pub. Law 86-645 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
20. 
21. 
22. 
23. 
e
i
e

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 26-B AUTHORIZING LEGISLATION 
(Continued) 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
24. SHENANGO RIVER LAKE, OHIO RIVER BASIN, PA AND OH 
Jun 28, 1938 Construction of a dam and reservoir for flood control, low water H. Doc. 306, 74th Cong. 
regulation and recreation. 1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Dec 22, 1944 Construction, operation & maintenance of recreation facilities. Sec. 4, Flood Control Act 
as amended of 1944 
25. STONEWALL JACKSON LAKE, WV 
Nov 7, 1966 Construction of a dam and reservoir for flood control, water supply, S. Doc. 109, 89th Cong. 
water quality control, area redevelopment and recreation. 2nd Sess. 
26. TIONESTA LAKE, OHIO RIVER BASIN, PA 
Jun 22, 1936 Construction of a dam and reservoir for flood control and low H. Doc. 306, 74th Cong. 
amended by water regulation. 1st Sess. 
Jun 28, 1938 FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Dec 22, 1944 Construction, operation & maintenance of recreation facilities. Sec. 4, Flood Control Act 
as amended of 1944 
27. UNION CITY DAM, PA 
Oct 23, 1962 Construction of a dam and reservoir for flood control. S. Doc. 95, 87th Cong. 
2nd Sess. 
28. WOODCOCK CREEK LAKE, PA 
Oct 23, 1962 Construction of a dam and reservoir for flood control, recreation S. Doc. 95, 87th Cong. 
and storage for water quality control. 2nd Sess. 
29. YOUGHIOGHENY RIVER LAKE, OHIO RIVER BASIN, 
PA AND MD 
Jun 28, 1938 Construction of a dam and reservoir for flood control, low-flow H. Doc. 306, 74th Cong. 
augmentation, and pollution abatement purposes. 1st Sess. 
FCC Doc. No. 1, 75th Cong. 
1st Sess. 
Dec 22, 1944 Construction, operation & maintenance of recreation facilities. Sec. 4, Flood Control Act 
as amended of 1944 
1. Included in the Emergency Relief Administration program 
April 8, 1935. 
2. Permanent Appropriations Repeal Act. 
3. Public Res. 117, 71st Cong., 3d Sess. 
26-20

PITTSBURGH, PA., DISTRICT 
TABLE 26-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 6 of Text) 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Allegheny River, PA, open-channel work Completed 1934 197,000 133,940 
Beaver and Mahoning Rivers, PA and 
OH' 6 Inactive 1938 - - 
Buckhannon River, WV 2 3 Completed 1893 5,500 - 
Cheat River, WV2 3 Completed 1895 12,997 - 
Pittsburgh Harbor, PA Completed 1922 110,663 81,613 
Youghiogheny River, PA and MD 6 Inactive 1971 47,195 ' 185,6685 
1. January 23, 1939, Chief of Engineers recommended 
constructing a waterway from Ohio River through Beaver, 
Mahoning, and Grand River Valleys to Lake Erie (H. Doc. 
178, 76th Cong., 1st Sess.) 
2. Abandonment recommended in H. Doc. 467, 69th Cong., 
1st Sess. 
3. No Commerce reported. 
4. Previous project data. 
5. Includes $1.700 expended under previous project. 
6. Eligible for deauthorization. 
26-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 26-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(All Projects Not Specifically Identified in Text) 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Allegany, NY, unit I (Allegheny River) Deferred - 4,100 - 
Allegany, NY, unit II (Five Mile Creek Area) Deferred 1975 64,851 - 
Amsterdam, OH' Completed 1964 183,072 - 
Benwood, WV2 Deferred 1954 81,028 - 
Big Run, PA' Completed 1965 364,208 - 
Black Fork at Hendricks, WV' Inactive 1972 6,800 - 
Brackenridge, Tarentum and Natrona, PA Inactive - - - 
Bradford, PA Completed 1962 7,601,763 - 
Brookville, PA Completed 1963 964,976 - 
Buckhannon, WV Completed 1972 1,568,661 - 
Burgettstown, PA' Completed - 83,129 - 
Butler, PA Completed 1970 1,556,181 - 
DuBois, PA Completed 1979 4,465,200 - 
Eagle Creek Reservoir, OH 2 Inactive - 100,000 - 
Empire-Stratton, OH 2 Inactive - 33,031 - 
Friendsville, MD' Completed - 41,529 - 
Granville, PA' Completed - 75,908 - 
Johnsonburg, PA Completed 1958 674,664 - 
Kittanning, PA, part I Completed 1949 130,317 - 
Latrobe, PA Completed 1951 207,659 - 
Latrobe, PA Completed 1970 2,556,652 - 
Leetonia, OH' Completed - 89,299 - 
Leetsdale, PA Inactive - - - 
Martins Ferry, OH 2 Inactive 1941 25,164 - 
Moundsville, WV2 Inactive - - - 
Muddy Creek Dam, PA 2 
4 Inactive 1977 402,459 - 
Neville Island, PA Inactive - - - 
New Kensington and Parnassus, PA Inactive - - - 
Oakdale, PA' Inactive - 14,127 - 
Oil City, PA' Completed - 43,595 - 
Olean, NY Completed 1954 3,217,531 - 
Portage, PA Completed 1965 150,386 - 
Portville, NY Completed 1954 2,070,484 - 
Powhatan Point, OH2 Inactive - - - 
Proctor, 1WV2 Inactive - - - 
Reynoldsville, PA Completed 1959 385,494 - 
Ridgway, PA (Elk Creek) Completed 1964 628,888 - 
Ridgway and vicinity, PA (on Clarion River)' 4 Active 1979 132,464 - 
Rochester, PA Inactive - - - 
Rouseville, PA' Inactive 1,642 - 
Rowlesburg Lake, WV3 Active 1977 2,857,575 - 
Salamanca, NY Completed 1972 2,880,535 - 
Slovan, PA' Completed - 57,811 - 
Sykesville, PA' Completed - 184,246 - 
Tarentum, PA' Completed 1964 136,591 - 
Tenmile Creek at Marianna, PA' Completed 1981 1,554,428 - 
Turtle Creek, PA Completed 1972 15,350,552 - 
Uniontown, PA2 Inactive 1956 - - 
Wallace, WV' 3 Inactive - 11,035 - 
Warwood, WV2 Inactive - - 
Washington, PA Completed 1964 789,093 - 
Wellsville, OH, Sec. I Completed 1956 483,910 - 
Wellsville, OH, Sec. II Completed 1956 157,633 - 
Weston Mills, Olean, NY' 4 Active - 50,100 - 
Weston Mills, Portville, NY' Active - 52,100 - 
Wheeling, WV (North Wheeling)2 Inactive - - - 
Wheeling, WV (Wheeling Island)2 Inactive - 21,700 - 
Wheeling, WV2 Inactive 1954 189,067 - 
Wilmore, PA' Completed - 96,853 - 
Woodlands, WV 2 Inactive - - - 
Youngstown, OH Completed 1976 3,621,134 - 
1. Authorized by Chief of Engineers. 3. Lacks local support. 
2. Eligible for deauthorization. 4. No longer economically justified. 
26-22

PITTSBURGH, PA., DISTRICT 
TABLE 26-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Adena, OH (Short Creek) - Aug 5, 1977 13,452 - 
Bellaire, OH - May 6, 1981 76,487 - 
Brilliant, OH - Aug 5, 1977 - - 
Brockway, PA (Allegheny River Basin) - Aug 5, 1977 194 - 
Clarington, OH - Aug 5, 1977 - - 
Coraopolis, PA - Aug 5, 1977 - - 
Dillonvale, OH (Short Creek) - Aug 5, 1977 16,884 - 
Follansbee, WV - Aug 5, 1977 - - 
Freeport, PA (Allegheny River) - Aug 5, 1977 - - 
Industry, PA - Aug 5, 1977 - - 
Kittanning, PA, part II (Allegheny River) - Nov 6, 1977 - - 
Lake Chautauqua and Chadokoin River, NY2 1965 Mar 2, 1970 190,722 - 
Lake Erie-Ohio Canal, OH and PA 1972 May 6, 1981 1,342,000 - 
McKees Rocks, PA - Oct 3, 1978 - - 
Mingo Junction, OH - Aug 5, 1977 - - 
New Cumberland, WV - Aug 5, 1977 - - 
Pittsburgh, PA (Golden Triangle) - Oct 3, 1978 - - 
Pittsburgh, PA (North Side) - Oct 3, 1978 - - 
Pittsburgh, PA (The Strip) - Oct 3, 1978 - - 
Redbank Creek Lake, PA - Aug 5, 1977 156,377 - 
St. Marys, PA (Allegheny River Basin) - Aug 5, 1977 13,529 - 
Smith Ferry, PA - Aug 5, 1977 - - 
Wellsburg, WV - Aug 5, 1977 6,387 - 
West Bridgewater, PA - Aug 5, 1977 - - 
Wilcox, PA' - Mar 5, 1955 16,761 - 
1. Local interests failed to meet requirements of cooperation, 
authority for project expired Feb. 20, 1951. 
2. Local interests failed to meet requirements of cooperation, 
authority for project expired Mar. 2, 1970. 
3. Local interests failed to meet requirements of cooperation, 
authority for project expired Mar. 5, 1955. 
26-23

TABLE 26-H ALLEGHENY RIVER, PA.: LOCKS AND DAMS 
(See Section 1 of Text) 
Dimensions 
Upper 
Avail- Normal Depths on Miter 
Width able Lift at Pool Sills at Normal Character of Type of Year 
of Length Normal Elevation Pool Level-- Foundation Construction Per- Opened 
Miles Cham- to Full Pool (feet, cent to 
Above ber Width Level mean sea Lower Upper Kind of Com- Navi- 
No. Mouth Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Dam Lock Dam plete gation Actual Cost 
2 6.7 Aspinwall, PA 56 360 11.0 721.0 12.0 10.9 Rock Rock Fixed Concrete Concrete 100 19342 $ 1,763,485 
3 14.5 Cheswick. PA 56 360 13.5 734.5 10.8 11.8 Rock Pile-rock Fixed Concrete Concrete 100 19342 1,875,665 
4 24.2 Natrona. PA 56 360 10.5 745.0 10.0 8.5 Rock Rock Fixed Concrete Concrete 100 1927 1,707,690 
5 30.4 Freeport. PA 56 360 11.8 756.8 10.5 10.3 Piling Crib-Pile Fixed Concrete Concrete 100 1927 1,940,537 
6 36.3 Clinton, PA 56 360 12.2 769.0 10.6 10.8 Rock Crib-Pile Fixed Concrete Concrete 100 1928 1,523,959 
7 45.7 Kittanning, PA 56 360 13.1 782.1 9.8 10.9 Piling Steel Sheet Fixed Concrete Concrete 100 1930 1,460,008 
Piling 
8 52.6 Templeton. PA 56 360 17.9 800., 10.4 13.8 Rock Rock Fixed Concrete Concrete 100 1931 2,848,920 
9 62.2 Rimer. PA 56 360 22.0 822.0 10.5 11.3 Rock Rock Fixed Concrete Concrete 100 1938 2,510,373 
Total $15,630,637 
Abandoned lock and dam I 591,187 
Abandoned lock and dam 2 544,929 
Abandoned lock and dam 3 310,103 
Demolishing old dam 1 26,001 
Dredging channel 1,055,003 
'Total $18,157,860 
1. All depths as shown are on guard sills and 
are controlling depth. 
2. Dates shown represent replacement structures. 
O
0OzE 
Cl

TABLE 26-I MONONGAHELA RIVER, PA. AND W. VA.: LOCKS AND DAMS 
(See Section 3 of Text) 
Dimensions 
Upper 
Avail- Normal Depths on Miter 
Width able Lift at Pool Sills at Normal Character of Type of Year 
of Length Normal Elevation Pool Level- Foundation Construction Per- Opened 
Miles Cham- to Full Pool (feet, cent to 
Above her Width Level mean sea Lower Upper Kind of Com- Navi- 
No. Mouth Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Dam Lock Dam plete gation Actual Cost 
2 11.2 Braddock, PA 56 360 8.7 718.7 16.0 15.95 Rock Crib pile Fixed Concrete Concrete 100 19532 $17,872,212 7 
110 720 
3 23.8 Elizabeth, PA 563 360 8.2 726.9 16.0 15.95 Rock Crib Pile Fixed Concrete Concrete 100 19533 17,538,315' 8 
720 
4 41.5 Monessen, PA 563 360 16.6 743.5 10.7 20.0 Piles Piles Movable Concrete Concrete 100 19322 17,254,071' 6 
720 
- 61.2 Maxwell locks and dam. 843 720 19.5 763.0 15.0 20.5 Rock Rock Movable Concrete Concrete 100 1964 30,110,889 
Maxwell, PA 
- 82.2 Grays Landing lock 84 720 15.0 778.0 15.0 26.0 Rock Rock Fixed Concrete Concrete - - 1,012,436 
and dam, Grays 
Landing, PA 
7 85.0 Greensboro, PA 56 360 15.0 778.0 10.0 10.5 Rock Rock Fixed Concrete Concrete 100 19252 2,639,8045 
8 90.8 Point Marion, PA 56 360 19.0 797.0 10.0 14.5 Rock Rock Movable Concrete Concrete 100 19252 6,027,253' 
102.0 Morgantown lock and 84 600 17.0 814.0 14.5 17.8 Rock Rock Movable Concrete Concrete 100 1950 8,778,000' 
dam, Morgantown, 
WV 
- 108.0 Hildebrand lock and 84 600 21.0 835.0 15.0 14.0 Rock Rock Movable Concrete Concrete 100 1959 12,506,829' 
dam, 6 miles above 
Morgantown, WV 
- 115.4 Opekiska lock and dam, 84 600 22.0 857.0 14.0 17.75 Rock Rock Movable Concrete Concrete 100 1964 25,179,622' 
13.4 miles above 
Morgantown, WV 
Marine ways, etc. 250,000' 
Abandoned lock and dam 1 1,019,907' 
Abandoned lock and dam 4 780,816' 
Abandoned lock and dam 5 1,074,812' 
Abandoned lock and dam 6 770,449' 
Abandoned lock and dam 7 213,776' 
Abandoned lock and dam 8 245,900' 
Abandoned lock and dam 9 191,000' 
Abandoned lock and dam 10 210,445' 
Abandoned lock and dam 11 227,668' 
Abandoned lock and dam 12 200,550' 
Abandoned lock and dam 13 190,6916 
Abandoned lock and dam 14 210,127' 
Abandoned lock and dam 15 175,8296 
Dredging 587,8996 
Total 145,269,3006 
01 
t 
1. All depths as shown are on guard sills and are controlling depths. 
2. Dates shown for locks and dams No. 2 to 8, inclusive, represent 
reconstruction. 
3. 2 Chambers 
4. Includes $3,322,057 for raising crest of dam, (1958-9), $2,086,438 for 
original reconstruction (1923-1926) and $618,758 AE&D costs for 
replacement of lock. 
5. Actual cost; may include estimated costs which have been 
footnoted as necessary. 
6. Includes $2,173,767 for original reconstruction (1931-2), and 
$15,080,304 for reconstruction of dam (1963-1967). 
7. Includes $16,967,114 for reconstruction of locks. 
8. Includes $15,856,779 for major rehabilitation. 
9. Includes AE&D costs for proposed lock ($803,000).

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 26-J MONONGAHELA RIVER, PA AND WV: 
TOTAL COSTS OF EXISTING PROJECT TO END OF FISCAL YEAR 
(See Section 3 of Text) 
Operation and 
Maintenance, 
Funds New Work General Total 
Regular $139,848,75913 $125,121,5492 $264,970,308' 2 3 
Maintenance and operation - 452,623 452,623 
Public Works acceleration, executive (1963) - 22,549 22,549 
Total $139,848,75913 $125,596,7212 $265,445,480' 2 3 
1. Excludes $5,420,541 for new work for previous projects. 3. Includes $15,856,779 for major rehabilitation of L/D3 
2. Excludes $20,446,587 expended between July 7, 1897 and $209,436 for replacement of L/D7. 
and June 30, 1937, on operation and care of works of 
improvement under provisions of permanent appropriation for 
such purposes and excludes $742 for maintenance of previous 
projects. 
TABLE 26-K OHIO RIVER BASIN (PITTSBURGH DISTRICT): 
LOCAL PROTECTION PROJECTS 
(See Section 23 of Text) 
Estimated Costs 
Type of 
Location' Protection Federal Non-Federal Total 
Allegany, NY, unit I (Allegheny River)2 
Allegany, NY, unit II (Five Mile Creek area)2 
Benwood, W V ' 7 14 
Brackenridge, Tarentum and Natrona, PA 
(Allegheny River)' 
Elkins, W V (Monongahela River Basin)4 5 
Empire-Stratton, OH 2 
14 
Johnsonburg, PA (Allegheny River Basin)2 5 
Johnstown, PA (Allegheny River Basin)2 5 
Kittanning, PA, part I (Allegheny River)2 5 
Latrobe, PA (Allegheny River Basin)2 
5 
Leetsdale, PA2 
Martins Ferry, OH 2 6 14 
Moundsville, WV2 14 
Neville Island, PA2 
New Kensington and Parnassus, PA 
(Allegheny River)2 
Olean, NY (Allegheny River)2 5 
Portville, NY (Allegheny River)2 5 
Powhatan Point, OH2 1' 
Proctor, WV2 
14 
Punxsutawney, PA (Allegheny River Basin)' " 
Ridgway, PA (Allegheny River Basin)2' 
Rochester, PA2 
Uniontown, PA (Monongahela River Basin)2 14 
Warwood, WV2 14 
Wellsville, OH, sec. 12 5 
Wellsville, OH, sec. II2 5 
Wheeling, WV 2 7 14 
Levee 
Channel and levee 
Wall 
Wall 
Channel diversion 
Internal drainage 
facilities 
Wall 
Channel 
Wall 
Channel 
Levee 
Wall and levee 
Wall and levee 
Wall and levee 
Wall 
Levee 
Levee 
Levee 
Levee 
Channel and levee 
Channel 
Wall 
Channel and wall 
Wall 
Wall and levee 
Wall and levee 
Wall and levee 
697,000 
980,000 
8,500,000 
11,800,000 
1,772,6273 
933,000 
674,6643 
8,865,3883 
130,3173 
207,6593 
1,270,000 
8,630,000 
3,070,000 
3,210,000 
7,900,000 
3,217,5313 
2,070,4843 
4,720,000 
334,000 
3,586,1073 
628,8883 
3,350,000 
5,820,000 
1,740,000 
483,9103 
157,6333 
19,700,000 
65,000 
133,000 
3,180,000 
3,080,000 
762,000 '0 
1,113,000" 
11,680,0009 
14,880,000 
40,000 1,812,627 
28,000 961,000 '3 
130,000 804,664 
- 8,865,3883 
2,000 132,317 
44,400 252,059 
141,000 1,411,000 
836,000 9,466,000 
605,000 3,675,000 
1,830,000 5,040,000 
148,000 8,048,000 
597,000 3,814,531 
353,000 2,423,484 
397,000 5,117,000 
121,000 455,000 
180,4853 3,766,5923 
72,000 700,888 
622,000 3,972,000 
980,000 6,800,00012 
376,000 2,116,000 
113,000 596,910 
- 157,6333 
3,460,000 23,160,0009 
26-26

PITTSBURGH, PA., DISTRICT 
TABLE 26-K 
(Continued) 
OHIO RIVER BASIN (PITTSBURGH DISTRICT): 
LOCAL PROTECTION PROJECTS 
(See Section 23 of Text) 
Estimated Cost 
Type of 
Location- Protection Federal Non-Federal Total 
Wheeling, WV (North Wheeling)2 14 Wall 11,700,000 2,700,000 14,400,000 
Wheeling, WV (Wheeling Island)2 
14 Wall and levee 13,300,000 2,470,000 15,770,000 
Woodlands, WV2 14 Levee 206,000 28,000 234,000 
1. All projects are on the Ohio River unless otherwise 8. Latest cost estimate revision 1954 unless otherwise 
noted. noted. 
2. Also see "Other authorized flood control projects." 9. Latest cost estimate revision 1960. 
3. Actual cost. 10. Latest cost estimate revision 1966. 
4. Reported in detail in an individual report. 11. Latest cost estimate revision 1974. 
5. Completed. 12. Latest cost estimate revision 1977. 
6. Reported in detail in Annual Report for 1941. 13. Latest cost estimate revision 1978. 
7. Reported in detail in Annual Report for 1954. 14. Eligible for deauthorization. 
TABLE 26-L OHIO RIVER BASIN (PITTSBURGH DISTRICT): RESERVOIRS 
(See Section 23 of Text) 
Total 
Estimated 
Tributary Basin and Reservoir Stream Cost 
Allegheny: 
Conemaugh River, PA' Conemaugh River $ 46,012,411 '3 
Crooked Creek, PA' Crooked Creek 4,431,523 ' 3 
East Branch Clarion River, PA' Clarion River 9,539,586 ' 3 
Kinzua Dam and Allegheny Reservoir, PA and NY' Allegheny River 112,209,956 36 
Loyalhanna, PA' Loyalhanna Creek 5,727,531 ' 3 
Mahoning Creek, PA' Mahoning Creek 7,138,814 ' 3 
Tionesta, PA' Tionesta Creek 7,788,379 ' 3 
Union City, PA' French Creek 14,559,800 ' 3 
Woodcock Creek, PA' Woodcock Creek 20,538,568 '3 
Beaver: 
Berlin, OH' Mahoning River 8,739,987 ' 3 
Eagle Creek, OH2 Eagle Creek 12,700,000 2 4 7 S 
Michael J. Kirwan, OH' Mahoning River 17,376,097 1 3 
Mosquito Creek, OH' Mosquito Creek 4,253,029 ' 3 
Shenango River, PA and OH' Shenango River 40,209,894 ' 3 
Monongahela: 
Stonewall Jackson Lake, WV' West Fork River 208,000,000 ' 5 
Youghiogheny River, PA and MD' Youghiogheny River 12,521,168 ' 3 
1. Reported in detail in an individual report. 
2. Also see "Other authorized flood control projects." 
3. Actual cost. 
4. Latest cost estimate revision 1954. 
5. Latest cost estimate revision in 1986. 
6. Includes $2,911,351 actual cost for Dam Rehabilitation. 
7. Inactive. 
8. Eligible for deauthorization. 
26-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 26-M INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 30 of Text) 
Project Dates of Inspection Project Dates of Inspection 
Amsterdam, OH October 1985 Leetonia, OH May 1984 
Big Run, PA October 1984 Marianna, PA June 1986 
Bolivar, NY September 1986 Millvale, PA June 1986 
Bradford, PA July 1986 Oil City, PA June 1986 
Brookville, PA October 1985 Olean, NY September 1986 
Buckhannon, WV September1986 Portage, PA August 1982 
Burgettstown-Slovan, PA September 1986 Portvile, NY September 1986 
Butler, PA September 1986 Reynoldsville, PA May 1985 
Chartiers Creek, PA Ridgway, PA May 1984 
Cannonsburg-Houston Reach September 1986 Salamanca, NY September 1986 
James G. Fulton Reach May 1985 Stonewgod-Nutter Fort, WV July 1983 
Colliers, WV October 1982 Sykesville, PA October 1985 
Dubois, PA October 1985 Tarentum, PA November 1976 
Eldred, PA June 1983 Turtle Creek, PA March 1986 
Friendsville, MD October 1985 Washington, PA September 1986 
Granville, PA September 1986 Wellsville, OH September 1986 
Johnsonburg, PA May 1984 Weston, WV July 1985 
Kittanning, PA August 1983 Wilmore, PA August 1982 
Latrobe, PA July 1984 Youngstown, PA October 1985 
26-28

PITTSBURGH, PA., DISTRICT 
TABLE 26-N FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 32 of Text) 
Flood Control Activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended (preauthorization) 
Project/Study Identification Fiscal Year Costs 
Allegheny River, Oil City, PA (construction) $ 95,599 
Robinson Run, Oakdale, PA (detailed project report) 12,499 
Root Creek, Bolivar, NY (construction) 787 
West Little Pine Creek, Etna, PA (construction) 704 124 
Total cost for current fiscal year: $813,009 
Emergency Bank Protection - Section 14 of the 
1946 Flood Control Act, Public Law 526, 79th Congress 
Project/Study Identification Fiscal Year Costs 
Beaver River, Bridgewater, PA (construction) $ 2,522 
Brook County, Hooverson Heights (construction) 29,683 
Chartiers Creek, Kennedy Township and McKees Rocks Borough, PA (construction) 8,396 
Elks Creek, Clarksburg, WV (construction) 11,029 
Greene County, Route 88, PA (initial appraisal report) 1,638 
Mahoning River, Highway 139A, Trumbull Co., OH (construction) -66 
Mahoning River, Warren Township, OH(construction) 11,881 
Monongahela River, Granville, WV (construction) 22,781 
Trout Run, Portage, PA (construction) 88 
Total cost for current fiscal year: $87,942 
Streambank Erosion Control, Evaluation and 
Demonstration - Section 32, of the 1974 Water Resources 
Development Act, Public Law 251, 93rd Congress 
Project/Study Identification Fiscal Year Costs 
Evaluate Streambank Erosion, Nationwide No 
Ohio River Main Stem Demonstration Projects Expenditures 
Ohio River Off Main Stem Demonstration Project This 
Rehabilitation of Streambank Demonstration Projects, Fiscal 
Ohio River Year 
Total cost for current fiscal year: 
Shoreline Erosion Control Demonstration 
Section 54, of the 1974 Water Resources 
Development Act, Public Law 251, 93rd Congress 
Fiscal Year Costs 
Activity 
Architect/Engineer Contract for Preparation of Three Reports for the 
Purpose of Disseminating Information on the Section 54 Program. 
Three Guides to Low Cost Shore Protection for: 
1. Engineers and Contractors 
2. Local government officials 
3. Property owners 
No 
Expenditures 
This 
Fiscal 
Year 
26-29

ST. PAUL, MN DISTRICT * 
District comprises western Wisconsin, major portion 
of Minnesota, northern and eastern North Dakota, and 
small portions of northeastern South Dakota and northern 
and northeastern Iowa embracing drainage basins 
of Mississippi River and tributaries from its source to 
mile 614 above mouth of Ohio River; Red River of the 
North and tributaries; those streams north of Missouri 
River Basin in North Dakota; and U.S. waters of Lake of 
the Woods and its tributaries. That section of Mississippi 
River above mile 614 is included in report on 
Mississippi River between Missouri River and Minneapolis, 
Minnesota. 
IMPROVEMENTS 
Navigation Page 
1. Minnesota River, MN ............................ 27-2 
2. Mississippi River between Missouri River 
and Minneapolis, MN ............................ 27-2 
3. Reservoirs at Headwaters of 
Mississippi River, MN .......................... 27-2 
4. St. Croix River, MN & WI ................... 27-2 
5. Warroad Harbor and River, MN ................ 27-3 
6. Zippel Bay, Lake of the Woods 
County, MN ...................................... 27-3 
Flood Control 
7. Bassett Creek, MN .............................. 27-4 
8. Big Stone Lake and Whetstone 
River, MN and SD ............................... 27-4 
9. Black Bear and Miller Lakes, 
Crow Wing County, MN .................... 27-5 
10. Chaska, MN ........ ..................... . 27-5 
11. Devils Lake, ND .................................. 27-5 
12. Eau Galle River, WI .............................. 27-6 
13. Enderlin, Maple River, ND .................... 27-6 
14. Hanover, Hennepin County, MN............... 27-7 
15. Homme Lake and Dam, ND ................. 27-7 
16. Irving Township at Nicols Road, 
Jackson County, WI...........................27-7 
17. Kickapoo River, Gays Mills, WI............... 27-7 
18. Lac qui Parle Lake, Minnesota River, MN .... 27-8 
19. La Farge Lake and channel 
improvement, WI ............................... 27-8 
20. Lake Ashtabula and Baldhill Dam, 
Sheyenne River, ND .............................. 27-9 
21. Lake Darling, .Souris River, ND ............. 27-9 
22. Lake Pulaski, Wright County, MN .......... 27-9 
23. Lake Traverse and Bois de Soiux 
River, SD and MN ............................. 27-10 
24. Mankato and North Mankato, MN............ 27-10 
25. Middle River at Argyle, MN ................. 27-11 
26. Minnesota River at Le Sueur, MN............ 27-11 
27. Prairie du Chien, WI ............................ 27-11 
28. Red Lake River, MN, including 
Clearwater River, MN .............. ....... 27-11 
29. Red River of the North at Argusville, ND.... 27-12 
30. Red River of the North drainage basin, 
MN, SD & ND ......... ................... 27-12 
31. Red River of the North at Halstad, MN ...... 27-13 
32. Redwood River at Marshall, MN ............ 27-13 
33. Rochester, MN .............. ............... 27-13 
34. Roseau River, MN ................................ 27-14 
35. Sheyenne River, ND ............................ 27-14 
36. Sheyenne River, Valley City, ND ............. 27-14 
37. Souris River, Velva, ND ...................... 27-15 
38. State Road and Ebner Coulees, WI.......... 27-15 
39. Twin Valley Lake, Wild Rice River, MN ..... 27-16 
40. Warner Road, Mississippi River, 
St. Paul, M N .................................... 27-16 
41. Wild Rice River, Mahnomen County, MN.... 27-17 
42. Winona, MN ................................... 27-17 
43. Inspection of completed flood 
control projects ................................. 27-18 
Miscellaneous 
44. Other work under special authority......... 27-18 
General Investigations 
45. Surveys ................ ......................... 27-18 
46. Collection and study of basic data........... 27-18 
47. Continuation of planning and engineering... 27-18 
48. Advance engineering and design ............ 27-18 
Tables 
Table 27-A Cost & Financial Statement ........ 27-19 
Table 27-B Authorizing Legislation ............. 27-22 
Table 27-C Other Authorized 
Navigation Projects ................. 27-23 
Table 27-D Not Applicable 
Table 27-E Other Authorized Flood 
Control Projects ...................... 27-24 
Table 27-F Not Applicable 
Table 27-G Deauthorized Projects ................. 27-25 
Table 27-H Reservoirs at Headwaters of 
Mississippi River.....................27-26 
Table 27-I Red River of the North Drainage Basin: 
Active Units in Comprehensive 
Basin Plan ............................ 27-27 
Table 27-J Inspection of Completed Flood 
Control Projects ...................... 27-27 
Table 27-K Flood Control Work Under 
Special Authorization................ 27-28 
27-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. MINNESOTA RIVER, MN 
Location. Rises in Big Stone Lake, MN and SD, and 
flows southeasterly about 224 miles to Mankato, MN, 
thence northeasterly about 106 miles to join the Mississippi 
River opposite St. Paul, MN. (For general location 
see Geological Survey map of Minnesota.) 
Previous projects. For details see page 1890 of 
Annual Report for 1915, and page 1105 of Annual 
Report for 1938. 
Existing project. Provides 9-foot depth below flat 
pool level of Mississippi River lock and dam 2 from 
mouth to mile 14.7, one-half mile above the railway 
bridge at Savage, MN, and 4-foot depth from mile 14.7 
to 25.6 at Shakopee, MN. For details see page 1018 of 
Annual Report for 1965. (See table 27-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. See also 
page 1074 of Annual Report for 1967. 
Terminal facilities. There are privately-owned terminals 
at miles 9, 13.1, 14.5, and two at mile 14.7. 
Operations and results during fiscal year. Maintenance: 
Snagging and clearing cost $5,337 by hired 
labor. Engineering and administrative costs amounted 
to $2,248. 
Condition at end of fiscal year: Work on project for 
4-foot depth was completed in 1931. The United States 
owns 10 acres of land in fee 2 miles east of Savage, MN, 
and easements on 123.08 acres of land. 46.20 acres have 
been transferred from the Department of the Army and 
Department of the Air Force to the project. Navigation 
from mouth to Shakopee was practicable for drafts not 
in excess of 3 feet. A contract for work under 1958 
authorization for a 9-foot channel started in May 1966 
was terminated in January 1967 when 56 percent complete. 
A channel dredging contract awarded in June 
1967 was completed in August 1968. Total costs for 
existing project to September 30, 1986, were $4,218,066, 
of which $1,940,180 was for new work and $2,277,886 
for maintenance. In addition, cost from contributed 
funds was $139,671 for dredging to 9-foot depth under 
provisions of section 4, River and Harbor Act of 1915, 
and $219,531 for work done for the State of Minnesota 
relative to modification of the project. 
2. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND 
MINNEAPOLIS, MN 
For report on this improvement see chapter on Mississippi 
River between Missouri River and Minneapolis, 
Minnesota. 
3. RESERVOIRS AT HEADWATERS 
OF MISSISSIPPI RIVER, MN 
Location. Reservoirs are on the Mississippi River 
and several of its tributaries in Itasca, Beltrami, 
Hubbard, Aitkin, Cass and Crow Wing Counties, MN. 
(See table 27-H on reservoirs.) 
Previous projects. For details see page 1888 of 
Annual Report for 1915, and page 1098 of Annual 
Report for 1938. 
Existing project. Provides for reconstruction from 
timber to concrete at Winnibigoshish, Leech Lake, 
Pokegama, Sandy Lake and Pine River Dams, and 
construction of a concrete dam at Gull Lake. Pokegama 
was built on bedrock and the others on pile foundations. 
A portion of Leech Lake Dam from piers 26 to 39 was 
replaced with an earth fill. Constructed three dikes at 
Winnibigoshish, four at Pokegama, two at Sandy Lake, 
and 16 at Pine River. Sandy Lake Dam includes a lock 
160 feet long, 30 feet wide, with a maximum lift of 9.5 
feet and a depth of 2.5 feet on lower sill at low water 
which was converted to use as a spillway. (See table 
27-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. None. 
Operations and results during fiscal year. Maintenance: 
Reservoirs were operated as required, recreation 
facilities and equipment maintained, and surveys, 
repairs, and reports were made by hired labor at a cost 
of $939,182. Reservoirs were operated by contract at a 
cost of $214,261. Physical security cost $2,816 by hired 
labor and $4,503 by contract. Periodic inspection, bridge 
and dike inspection, and dam safety costs were $113,552 
by hired labor and $84,552 by contract. Cultural resource 
investigation cost $5,693 by hired labor and 
$11,490 by other Corps of Engineers districts. Discharge 
observation, gage reading and water control analysis 
cost $90,763 by hired labor. Cooperative stream gaging 
with U.S. Geological Survey cost $28,220 and by contract, 
$1,135. Revision of water regulation manuals by 
contract cost $168,713. Commercial activities studies 
cost $46,831. Miscellaneous engineering and design cost 
$12,533. Real estate was managed by other Corps of 
Engineers districts at a cost of $48,278. Supervision and 
administration and other miscellaneous costs were 
$267,686. 
Condition at end of fiscal year: Existing project was 
completed in 1937. Flowage rights were acquired on all 
lands affected by construction, maintenance, and operation 
of reservoirs. A total of 1,672.26 acres in fee are 
owned by the United States. The United States has 
easements, flowage rights, and other rights of use on 
another 296,334.44 acres. Structures are in fair condition. 
Recreation facilities for public use are being constructed 
intermittently at all reservoir areas. (See table 
27-H for capacities and costs by reservoir.) 
4. ST. CROIX RIVER, MN & WI 
Location. From source in northwestern Wisconsin, 
flows southwesterly and then southerly about 164 miles 
to Mississippi River at Prescott, WI, about 41.7 miles 
below lower Burlington Northern railway bridge, Minneapolis, 
MN. For its greater part, forms boundary 
between Minnesota and Wisconsin. (See Geological Survey 
map of Minnesota.) 
27-2

ST. PAUL MINNESOTA DISTRICT 
Existing project. Provides for maintenance of a 
channel, 9 feet in depth and of suitable width from 
mouth to Stillwater, MN, 24.5 miles, created by improvement 
of upper Mississippi River; a channel 3 feet 
deep at mean low water between Stillwater and Taylors 
Falls (27.3 miles); improvement of harbor and waterfront 
at Stillwater; and a small-boat harbor at Hudson, 
WI, currently classified "inactive." Estimated (1981) 
Federal cost of new work is $820,400. Latest authorization 
(1954) for maintenance work on reach between 
Stillwater and Taylors Falls is limited to an expenditure 
not exceeding $5,000 per year. (See table 27-B for 
authorizing legislation. ) 
Local cooperation. Fully complied with for completed 
portion. For Hudson Harbor, see the Annual 
Report of 1970 for requirements. 
Terminal facilities. At Stillwater there is a concrete 
paved levee and a piling-and-timber trestle wharf on 
right bank. At other points along river, landing may be 
made on banks. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous engineering and design and supervision 
and administration cost $100. 
Condition at end of fiscal year: All new work was 
completed in 1930, except subsequently authorized harbor 
at Hudson which was reclassified to "inactive" on 
April 20, 1982. The United States owns 2.75 acres of 
land in fee at Taylors Falls and has easements over 7.57 
acres of land at Bayport, MN. Extension to provide a 
9-foot channel from mouth to Stillwater was completed 
August 12, 1938, when full pool at dam 3 of Mississippi 
River canalization project was reached. Minimum draft 
from Stillwater to Taylors Falls is about 1 foot at 
extreme low water, and from mouth to Stillwater, 9 feet. 
Maintenance of the 3-foot channel is limited to requests 
by the National Park Service which manages this reach 
under the Wild and Scenic Waterways classification. 
5. WARROAD HARBOR AND RIVER, 
MN 
Location. At southwestern extremity of Lake of the 
Woods, 36 miles west of mouth of Rainy River. (See 
NOAA Nautical Chart 14999). 
Existing project. Provides for a channel 8 feet deep 
from landing at Warroad to deep water in lake, channel 
being 9,200 feet long, 200 feet wide within harbor, and 
300 feet wide out in lake; for a turning basin 500 by 900 
feet to a depth of 8 feet; and for a pile-brush stone jetty 
on north side of channel extending from shore 700 feet 
into the lake. For additional details see page 1027 of 
Annual Report of 1965. Portion of dredging of entrance 
channel and turning basin to complete project width 
and depth was considered unnecessary to meet present 
navigation requirements, and classified inactive was 
deauthorized on August 5, 1977, under Section 12 of 
Public Law 93-251. Estimated cost (1954) of this portion 
was $355,200. (See table 27-B for authorization 
legislation.) 
Local cooperation. None required. 
Terminal facilities. There is one publicly owned 
wharf. There are two commercial fish wharves, one of 
which is served by a spur track, and a number of minor 
wharves, all privately owned. Facilities are adequate for 
existing commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design for repair and revetment 
wall cost $8,730. Administrative costs were $870. 
Condition at end of fiscal year: Project is complete. 
Prospective jetty completed in 1910 and reconstructed 
as a rubble mound in 1929 is in good condition. Turning 
basin at Warroad wharves was completed in 1911, and a 
channel 200 feet wide and 8 feet deep in 1915. Controlling 
depth in river channel and lake approach channel 
was 6 feet below low-water datum for a minimum width 
of 100 feet. A walkway on the jetty is provided for public 
use. A revetment wall, constructed under Section 2 of 
Public Law 269, 69th Congress, in accordance with 
Article VIII of the Lake of the Woods Treaty, has 
deteriorated and will require future maintenance. 
6. ZIPPEL BAY LAKE OF THE 
WOODS COUNTY, MN 
Location. Zippel Bay is a natural harbor located in 
northwestern Minnesota on the south shore of Lake of 
the Woods near Williams, Minnesota. The navigation 
project will be located in Zippel Bay State Park. 
Existing Project. Boats based at a state park, resort, 
marina, and a number of private residences use Zippel 
Bay to provide access to the lake. However, the natural 
channel between the bay and Lake of the Woods varies 
in depth and width and restricts navigation. The plan of 
improvement would provide a small-boat access channel 
between Zippel Bay and Lake of the Woods. Jetties 
would be constructed on both sides of the channel to 
minimize the amount of maintenance dredging. The 
total cost of the project is currently estimated at 
$751,200, of which the Federal cost is $399,600. Included 
in this latter are costs to the Corps of Engineers 
and the Coast Guard. The project was approved by the 
Chief of Engineers for construction in October 1985 
under the authority contained in Section 107 of the 
River and Harbor Act of 1960, as amended. 
Local cooperation. A local assurance agreement 
was adopted by the Minnesota Department of Natural 
Resources, the local sponsor, in December 1985. Local 
interests are required to contribute in cash 50 percent of 
that amount of the total first cost of construction of the 
general navigation facilities, except aids to navigation, 
which does not exceed $4,000,000 and all of such costs in 
excess of $4,000,000; provide without cost to the United 
States all lands, easements and rights-of-way necessary 
for construction and subsequent maintenance of the 
project and for aids to navigation, including the provision 
of sites, acceptable to the government, of sufficient 
capacity for the placement of dredged material together 
with necessary containment dikes or the cost thereof; 
accomplish all alterations and relocations of buildings, 
streets, rivers, utilities, and other structures and im- 
27-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
provements made necessary by project construction and 
maintenance; hold and save the United States free from 
damages caused by the construction, operation and 
maintenance of the project not including damages due 
to the fault or negligence of the United States or its 
contractors; provide and maintain without cost to the 
United States adequate berthing areas with depths 
commensurate with those in the Federal improvements, 
and necessary mooring facilities, utilities, and public 
landing with suitable supply and essential sanitary 
facilities, launching ramps, parking areas, and access 
roads open to all on equal terms; establish and enforce 
regulations prohibiting discharge of pollutants into the 
waters of the harbor area by users thereof, which 
regulations shall be in accordance with applicable laws 
and regulations of Federal, State, and local authorities 
responsible for pollution protection; provide facilities for 
onshore disposal of untreated sewage, garbage, debris 
and other pollutants; comply with the applicable provisions 
of the "Uniform Relocations Assistance and Real 
Property Acquisition Policies Act of 1970," Public Law 
91-646, approved January 2, 1971; comply with Section 
601 of Title VI of the Civil Rights Act of 1964 (Public 
Law 88-352) and Department of Defense Directive 
5500.11 issued pursuant thereto and published in Part 
300 of Title 32, Code of Federal Regulations, in connection 
with the construction and subsequent maintenance 
and operation of the project. 
Operations and results during fiscal year. New 
Work: A construction contract cost $70,000. Engineering 
and design and supervision and administration of 
the construction contract costs were $17,146. 
Condition at end of fiscal year: A contract for construction 
of the small boat navigation project was 
awarded May 1986. 
Flood Control 
7. BASSETT CREEK, MN 
Location. In Hennepin County and Minneapolis, 
Minnesota, on Bassett Creek, a tributary of the Mississippi 
River. (For general location, see Geological Survey 
map of Minnesota.) 
Existing project. The proposed project consists of 
nonstructural and structural flood control measures. 
Nonstructural measures include continuation of existing 
floodplain regulations, flood insurance and forecasting, 
and flood warning. Principal structural measures 
consist of six small control structures in the upper 
watershed to temporarily impound floodwaters and a 
new tunnel (part of which is being constructed on a 
cooperative basis with the Minnesota Department of 
Transportation) in a highly urbanized area of Minneapolis 
to replace the existing tunnel outletting Bassett 
Creek to the Mississippi River. Also included in the plan 
are a limited reach of channel widening, bridge removals, 
culvert replacements, a weir structure, a flood 
storage area, and a railroad bridge replacement. Estimated 
Federal cost (1986) for new work is $23,500,000 
and $3,867,000 is to be contributed by local interests. 
Project was authorized by the 1976 Water Resources 
Development Act. 
Local cooperation. See Annual Report for 1977 for 
requirements. Under current cost sharing policies, 
when the costs of lands, easements, and rights-of-way 
are less than 20 percent of total project costs, local 
interests are required to furnish the standard local 
cooperation requirements plus a cash contribution, the 
total of the two to amount to a minimum of 25 percent of 
the total project costs. On June 27, 1986, the City of 
Minneapolis entered into a local cooperation agreement 
with the Department of the Army. 
Operations and results during fiscal year. New 
Work: A tunnel FDM by contract cost $77,007, by hired 
labor, $196,769. Work by the Waterways Experiment 
Station and North Central Division real estate cost 
$19,999 and $4,805, respectively. Supervision and administration 
and other miscellaneous costs were 
$24,807. 
Condition at end of fiscal year: Preconstruction planning 
is complete. 
8. BIG STONE LAKE AND 
WHETSTONE RIVER, MN AND SD 
Location. On Minnesota River near Ortonville and 
Odessa, MN, and Big Stone City, SD, at the outlet of Big 
Stone Lake and in Big Stone and Lac qui Parle Counties, 
MN, and Grant County, SD. (For general location, 
see Geological Survey map of Minnesota.) 
Existing project. Provides for a dam and reservoir 
on Minnesota River above U.S. Highway 75, modification 
of Big Stone Lake outlet dam and silt barrier, bank 
stabilization along lower reach of Whetstone River, 
channel improvement on Minnesota River for 3 miles 
below outlet control dam at Big Stone Lake along with 
necessary relocations and acquisition of lands. These 
improvements would be made for wildlife conservation 
and development, flood control, and recreation. For 
additional details see Annual Report for 1970. Project 
was authorized by 1965 Flood Control Act (H. Doc. 579, 
87th Cong., 2d sess., contains latest map; and H. Doc. 
193, 88th Cong., 2d sess.). 
Local cooperation. See Annual Report for 1968 for 
requirements. The project requires sponsorship from 
both the States of Minnesota and South Dakota. Formal 
resolution of assurances adopted by the Upper Minnesota 
River Watershed District on June 10, 1969, and 
accepted by the District Engineer on November 3, 1969. 
Formal resolution of assurances adopted by the East 
Dakota Conservancy Sub-District for South Dakota on 
October 23, 1969, was furnished on November 18, 1969, 
and accepted by the District Engineer on November 19, 
1969. Supplemental assurances covering the requirements 
of Public Law 91-646 were provided by the Upper 
Minnesota Watershed District on August 13, 1974, and 
by the East Dakota Conservancy Sub-District on April 
15, 1976. Rights-of way for construction on the Whetstone 
River and the entire cash contribution of $153,000 
for the project were furnished by the local sponsors on 
December 21, 1981. 
27-4

ST. PAUL MINNESOTA DISTRICT 
Operations and results during fiscal year. New 
Work: Minnesota River channel construction contract 
costs were $43,097. A Big Stone Lake outlet and silt 
barrier contract cost $56,000. Engineering and design, 
supervision and administration and other miscellaneous 
costs were $122,348. Maintenance: Structure was 
operated and maintained and inspections and evaluations 
performed at a cost of $60,262 by hired labor and 
$90 by contract. Data collection, water control analysis 
and maintenance of stream gaging cost $8,797, $8,543 
and $1,833, respectively. Data collection by other government 
agencies cost $39,029. Real estate management 
by the North Central Division cost $5,852. Dam 
failure planning cost $33,030 by other districts. Engineering 
and design and supervision and administration 
cost $174 and $16,257, respectively. 
Condition at end of fiscal year: Construction of the 
new dam above Highway 75 and roads are completed. 
Surveys for land lines are complete, and the land acquisition 
program is complete. The first land payment was 
made on November 28, 1969, and 128 tracts have been 
purchased. A general plan between the Secretary of the 
Army and the Secretary of the Interior for administrating 
the use of waters, land, or interests therein has been 
consummated, and a cooperative agreement between 
the Corps of Engineers and the U.S. Fish and Wildlife 
Service was approved. On March 31, 1975, the Secretary 
of the Army transferred lands in the project not required 
for Corps of Engineers operation and maintenance 
to the Department of Interior. The transfer of 
property was accepted by the Department of the Interior 
on May 21, 1975. Construction on the Whetstone River 
portion of the upstream works is complete. The construction 
contract for the Minnesota River work is 
substantially complete. 
9. BLACK BEAR AND MILLER 
LAKES, CROW WING COUNTY, MN 
Location. Black Bear and Miller Lakes are near the 
center of the State, 20 miles north of Brainerd, Minnesota. 
The two lakes lie adjacent to the left (east) bank of 
the Mississippi River. Miller Lake is linked to Black 
Bear Lake by a very short channel. In turn, Black Bear 
Lake is joined to the Mississippi River by a one-half 
mile creek. 
Existing project. Spring high water on the Mississippi 
River backs up the creek channel, flooding shoreline 
properties and causing damages to buildings and 
related facilities. Some flooding is experienced here 
every 3 to 5 years. The project consists of an embankment 
across the creek approximately 300 feet upstream 
of its juncture with the MississippiRiver. This structure 
will have a culvert extending through it which would be 
closed off during periods of high flow on the Mississippi 
River. Residences around the two lakes would be protected 
up to the 500-year flood elevation on the Mississippi 
River with 3 feet of freeboard. Total Federal cost 
for the project is estimated at $350,000. The project was 
approved by the Chief of Engineers for construction in 
March 1985 under the authority contained in Section 
205 of the 1948 Flood Control Act, as amended. 
Local cooperation. See Annual Report for 1985 for 
requirements. A local assurance agreement was adopted 
by Crow Wing County, the local sponsor, in July 1985. 
Operations and results during fiscal year. New 
Work: A construction contract cost $204,575. Engineering 
and design cost $20,229 by hired labor and $13,120 
by contract. Supervision and administration costs were 
$7,060. 
Condition at end of fiscal year: Construction of a flood 
protection project at Black Bear and Miller Lakes is 
currently underway. 
10. CHASKA, MN 
Location. In Carver County in south-central Minnesota 
on the Minnesota River. (For general location, see 
Geological Survey map of Minnesota.) 
Existing project. The plan of improvement consists 
of a levee and interior drainage works along the Minnesota 
River, flood diversion and bypass channels on 
Chaska Creek and East Creek, and appropriate 
floodplain regulation measures. Principal project features 
include: approximately 1.1 miles of upgraded 
levee, 1.5 miles of new levee, and one pumping station 
on the Minnesota River; 1.3 miles of diversion channel 
on Chaska Creek; and 0.3 mile of flood bypass channel, 
and a 1,500-foot conduit on East Creek. Approximately 
1.6 miles of paved recreation trails on top of the levee 
and around Courthouse Lake are also included in the 
proposed plan. Estimated Federal cost (1986) for new 
work is $19,400,000 and $2,425,000 is to be contributed 
by local interests. Project was authorized by the 1976 
Water Resources Development Act. (H. Doc. 644, 94th 
Congress, 2d sess., contains latest published map.) 
Local cooperation. See Annual Report for 1977 for 
requirements. A local assurance agreement will be 
required prior to the start of construction. By letter of 
August 19, 1982, the City of Chaska indicated its 
willingness and intention to meet the requirements of 
local cooperation. By letter of October 16, 1985, the City 
of Chaska indicated its intent to participate voluntarily 
in project financing as proposed in legislation being 
considered by Congress. 
Operations and results during fiscal year. New 
Work: Preconstruction planning was continued at a cost 
of $52,066. 
Condition at end of fiscal year: Preconstruction planning 
is in progress. Plans and specifications for the first 
stage of construction are complete. 
11. DEVILS LAKE, ND 
Location. In Ramsey County in north central North 
Dakota about 80 miles west of Grand Forks, North 
Dakota. (For general location, see Geological Survey 
Map of North Dakota.) 
Existing project. Involves a system of levees and 
interior flood control facilities at the head of Creel Bay. 
The main embankment across Creel Bay is 1,810 feet 
27-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
long and varies from 0 to 27 feet high. The south Creel 
Bay tieback embankment is 1,030 feet long and varies 
from 0 to 3 feet high. The north Creel Bay tieback 
embankment is 2,400 feet long and varies from 0 to 8.5 
feet high. The south embankment is 3,100 feet long and 
varies from 0 to 9.5 feet high. 
The interior flood control system consists of temporary 
stormwater retention ponds immediately north and 
south of the city's sewage lagoons, a 16,000 gallon per 
minute pumping station and a system of ditches and 
culverts linking the ponds to the pumping station. 
Total Federal cost (1986) for the project is estimated 
at $2,570,000. The project was approved by the Chief of 
Engineers for construction August 15, 1983, under the 
authority contained in Section 205 of the 1948 Flood 
Control Act, as amended. 
Local cooperation. See Annual Report for 1983 for 
requirements. 
A local assurance agreement required by Public Law 
91-611 was adopted by the City of Devils Lake in 
August 1983. 
Operations and results during fiscal year. New 
Work: Construction contracts cost $880. Engineering 
and design cost $55,533 by hired labor. Supervision and 
administration costs were $33,711. 
Condition at end of fiscal year: Construction work on 
the project is substantially complete. 
12. EAU GALLE RIVER, WI 
Location. At and in vicinity of Spring Valley, WI, on 
Eau Galle River 30 miles above its mouth at Chippewa 
River, and its tributary, Mines Creek, which flows 
through the village. Spring Valley is about 45 miles 
east of St. Paul, MN, and 36 miles west of Eau Claire, 
WI. (See Geological Survey map for Wisconsin for general 
location.) 
Existing project. Authorized plan of improvement as 
modified by further studies includes a retarding dam 
and reservoir on Eau Galle River immediately upstream 
from Spring Valley, and remedial works on Mines 
Creek including channel enlargement, a low levee, and 
a drop structure. Project provides for earth and rock-fill 
dam, an uncontrolled outlet and an uncontrolled spillway 
emerging above Mines Creek. See page 1030 of 
Annual Report for 1965 for further details. Proposed 
improvements on Burghardt Creek were eliminated. 
Improvements provide complete protection near Spring 
Valley for standard project flood, and below that point 
in decreasing value in proportion to distance from reservoir. 
Permanent conservation pool will serve a local 
need for a recreational area. Project was authorized by 
1958 Flood Control Act (S. Doc. 52, 84th Cong., 1st sess., 
contains latest published map.) 
Local cooperation. Fully complied with. See page 
1083 of Annual Report for 1967. 
Operations and results during fiscal year. Maintenance: 
Structure and recreation facilities were operated 
and maintained, and inspections, investigations 
and evaluations were performed at a cost of $180,966 by 
hired labor and $16,023 by contract. Recreational maintenance 
contracts cost $53,626. Real estate management 
by the North Central Division cost $9,850. Data 
collection cost $3,057 by hired labor and $7,254 by other 
government agencies. Water control analysis and water 
quality by other Corps of Engineer districts cost $8,609 
and $76,682, respectively. Maintenance of stream gaging 
cost $1,565. Commercial activities studies cost 
$8,994. Administrative and other miscellaneous engineering 
costs were $105,408. 
Condition at end of fiscal year: Mines Creek improvements 
were substantially completed in 1964: minor 
work was accomplished in 1966. A contract for dam, 
spillway, and discharge channel, started July 1, 1965, 
was completed in October 1968. Recreational facilities 
have been provided. Remedial work to repair eroded 
gutters and road ditches was completed in September 
1973. Repair of failing discharge conduit by installing a 
steel liner was completed in April 1982. 
13. ENDERLIN, MAPLE RIVER, ND 
Location. In Ransom County in southeastern North 
Dakota on the Maple River about 45 miles southwest of 
Fargo, North Dakota. (For general location, see Geological 
Survey Map of North Dakota.) 
Existing project. The project at Enderlin involves a 
system of levees along the right bank of the main stem 
and the left bank of the South Branch of the Maple 
River. The total levee system would be about 1.2 miles 
long and would have an average height of about 8 feet. 
Other features of the project include channel improvements 
on the south branch, replacement of the Soo Line 
railroad bridge, and interior drainage facilities consisting 
of three ponding areas with gated outlet conduits. 
To prevent failure of the channel and levee by erosion, 
rip-rapping would be provided in selected reaches. 
The project was approved by the Chief of Engineers 
for construction August 11, 1982, under the authority 
contained in Section 205 of the 1948 Flood Control Act, 
as amended. 
Local cooperation. See page 27-5 of Annual Report 
for 1982 for requirements. 
A local assurance agreement required by Public Law 
91-611 was adopted by the City of Enderlin in July 
1982. 
Operations and results during fiscal year. New 
Work: A Phase III Highway 46 frontage road levee 
contract cost $11,498. A Phase IV contract on the south 
branch of the Maple River cost $284,476. A relocations 
contract with the Soo Line RR cost $61,446. Engineering 
and design by hired labor cost $1,649. North Central 
Division real estate costs were $816. Supervision and 
administration cost $1,784. 
Condition at end of fiscal year: Construction of the 
project is substantially complete. 
27-6

ST. PAUL MINNESOTA DISTRICT 
14. HANOVER, HENNEPIN COUNTY, 
MN 
Location. Hanover is in south-central Minnesota in 
northwest Hennepin County and eastern Wright 
County. The erosion project is located along the right 
bank of the Crow River adjacent to the Hanover Dam in 
the city of Hanover. 
Existing project. County State Aid Highway #19 is 
located on top of the bank of the Crow River and is in 
danger of being lost due to continuing erosion. The 
proposed project would consist of placement of fill to 
reconstruct the bank and riprap to protect this bank. 
The total Federal cost (1986) of the project is estimated 
at $222,100. The project was approved by the Chief of 
Engineers for construction in May 1986 under the 
authority contained in Section 14 of the 1946 Flood 
Control Act, as amended. 
Local cooperation. A local assurance agreement 
was adopted by Hennepin County, Minnesota, the local 
sponsor, in August 1986. Local interests are required to 
provide without cost to the United States all lands, 
easements and rights-of-way necessary for construction, 
operation, and maintenance of the project; accomplish 
all alterations and relocations of streets, highways, 
sewer, water supply, drainage and other utility facilities; 
hold and save the United States free from damages 
caused by the construction, operation and maintenance 
of the project except damages due to the fault or negligence 
of the United States or its contractors; provide all 
costs in excess of the $250,000 Federal cost limitation; 
maintain and operate the project after completion without 
cost to the United States in accordance with regulations 
prescribed by the Secretary of the Army; comply 
with the applicable provisions of the "Uniform Relocations 
Assistance and Real Property Acquisition Policies 
Act of 1970," Public Law 91-646, approved January 2, 
1971; comply with Section 601 of Title VI of the Civil 
Rights Act of 1964 (Public Law 88-352) and Department 
of Defense Directive 5500.11 issued pursuant thereto 
and published in Part 300 of Title 32, Code of Federal 
Regulations, in connection with the construction and 
subsequent maintenance and operation of the project. 
Operations and results during fiscal year. New 
Work: Engineering and design and administrative costs 
were $23,960. 
Condition at end of fiscal year: A contract for construction 
of the erosion protection project at Hanover 
was awarded in September 1986. 
15. HOMME LAKE AND DAM, ND 
Location. Dam is on South Branch of Park River 
about 4 miles upstream from Park River, ND, and 62.1 
miles above mouth of Park River. South, Middle, eand 
North Branches, headwater streams of Park River, rise 
in Cavalier County in northeastern North Dakota and 
flow easterly to an almost common confluence near 
Grafton, ND, forming main stream which flows easterly 
35 miles to join Red River of the North about 35 miles 
south of the international boundary. (For general location, 
see Geological Survey map of North Dakota.) 
Existing project. See page 1285 of Annual Report for 
1962. Project was authorized as Park River Reservoir by 
1944 Flood Control Act (S. Doc. 194, 78th Cong., 2d 
sess.), and redesignated Homme Reservoir and Dam by 
Public Law 435, 80th Congress, 2d session. Latest published 
map is in project document. 
Local cooperation. Fully complied with. Total costs 
for all requirements of local cooperation under terms of 
project authorization, including required non- 
Federal contributions, were $62,800. In addition, local 
interests contributed $16,220 for construction of a water 
supply outlet through dam and incurred other costs of 
$19,600. 
Operations and results during fiscal year. Maintenance: 
Structure was operated and maintained, and 
inspections and evaluations performed at a cost of 
$83,257. 
Condition at end of fiscal year: Project completed in 
June 1956 except for additional recreational facilities 
which have been done intermittently since that time. 
Construction began in April 1948 and major structures 
completed in May 1951. Structures are in good condition. 
Government has acquired 395 acres of land in fee 
and easements over 7.8 acres of land for project. An 
additional 6.3 acres of land have been donated for 
recreational development and 3.75 acres have been 
acquired due to bank erosion bordering the project. 
16. IRVING TOWNSHIP AT NICOLS 
ROAD, JACKSON COUNTY, WI 
Location. In Jackson County in west central Wisconsin 
on the Black River, approxmately 6 miles south of 
Black River Falls. The project site is near Nicols Road. 
Existing project. Erosion was threatening Nicols 
Road in Irving Township, Wisconsin. The project protects 
the road and consisted of the placement of rockfill 
at the toe of the eroding bank and revegetation of the 
upper part of the river bank. The project was approved 
for construction in May 1985, under the authority contained 
in Section 14 of the 1946 Flood Control Act, as 
amended. 
Local cooperation. See Annual Report for 1985 for 
requirements. Local cooperation agreements were 
adopted by Irving Township in July 1985. 
Operations and results during fiscal year. New 
Work: Engineering and design and supervision and 
administration costs were $27,217. A construction contract 
cost $116,993. 
Condition at end of fiscal year: Construction was 
completed in July 1986. 
17. KICKAPOO RIVER, GAYS MILLS, 
wI 
Location. Left bank of Kickapoo River, in Gays 
Mills, in southwestern Wisconsin. 
Existing project. The project to protect the streambank 
from erosion which threatens a sewage treatment 
digestion tank is authorized under Section 14 of the 
1946 Flood Control Act, as amended. The initial ap- 
27-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
praisal report, dated September 1985, recommended 
protection with 150 cubic yards of gravel bedding and 
300 yards of riprap along about 200 feet of eroding river 
bank. The project was approved for construction by the 
Office Chief of Engineers on June 18, 1986. Total 
Federal cost of the project is estimated at $33,000. 
Local cooperation. A local cooperation agreement 
was adopted by the Village of Gays Mills, Wisconsin, in 
August 1986. Local interests are required to provide 
without cost to the United States all lands, easements 
and rights-of-way necessary for construction, operation, 
and maintenance of the project; accomplish all alterations 
and relocations of streets, highways, sewer, water 
supply, drainage and other utility facilities; hold and 
save the United States free from damages caused by the 
construction, operation and maintenance of the project 
except damages due to the fault or negligence of the 
United States or its contractors; provide all costs in 
excess of the $250,000 Federal cost limitation; maintain 
and operate the project after completion without cost to 
the United States in accordance with regulations prescribed 
by the Secretary of the Army; comply with the 
applicable provisions of the "Uniform Relocations Assistance 
and Real Property Acquisition Policies Act of 
1970," Public Law 91-646, approved January 2, 1971; 
comply with Section 601 of Title VI of the Civil Rights 
Act of 1964 (Public Law 88-352) and Department of 
Defense Directive 5500.11 issued pursuant thereto and 
published in Part 300 of Title 32, Code of Federal 
Regulations, in connection with the construction and 
subsequent maintenance and operation of the project. 
Operation and results during fiscal year. New 
Work; A construction contract cost $14,100. Engineering 
and design and other study costs were $8,545. 
Condition at end of fiscal year. A contract for slope 
protection was awarded in September 1986. Project was 
50 percent complete at the end of the fiscal year. 
18. LAC QUI PARLE LAKE 
MINNESOTA RIVER, MN 
Location. Works covered by this project lie along 
Marsh Lake and Lac qui Parle and the Minnesota River 
between head of Marsh Lake and Granite Falls, MN. 
(For general location, see Geological Survey map of 
Minnesota.) 
Existing project. See page 1291 of Annual Report for 
1962. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Project was operated and maintained, and 
inspections and evaluations performed at a cost of 
$460,475. A gate operator equipment contract cost 
$60,656 and a bank stability contract for the Chippewa 
Diversion cost $410,662. 
Condition at end of fiscal year: Project has been 
operated by the Government since transfer from State of 
Minnesota to the United States in September 1950. The 
United States owns fee title to 517.62 acres of land and 
easements on 19,859.47 acres of land. In 1957, 60.1 
acres were withdrawn from public lands for use by the 
Department of the Army. Land acquisition is complete. 
Construction under present plan of improvement was 
started in September 1941 and completed in December 
1951 except for recreational facilities. All structures are 
in good condition. 
19. LA FARGE LAKE AND CHANNEL 
IMPROVEMENT, WI 
Location. On the Kickapoo River which rises in 
Monroe County in southwestern Wisconsin and flows 
south and southwest through Vernon, Richland, and 
Crawford Counties emptying into Wisconsin River 
about 16 miles above junction of latter stream with 
Mississippi River. (For general location see Geological 
Survey map of Wisconsin.) 
Existing project. Provides for a dam and impoundment 
of the Kickapoo River about 1 mile upstream from 
village of La Farge, operated for flood control, fish and 
wildlife conservation, general recreation, and a reduction 
of aggradation downstream from the dam, and 
supplemental protection at Soldiers Grove and at Gays 
Mills by means of levees, supplementary channel improvement, 
and interior drainage facilities. See Annual 
Report for 1975 for details. 
Estimated Federal cost (1976) for new work is 
$55,400,000. Project was authorized by 1962 Flood Control 
Act (H. Doc. 557, 87th Cong., 2d sess., contains 
latest published map.) 
Local cooperation. None required for construction 
of La Farge Lake. See page 1087 of Annual Report for 
1967 for requirements for local protection works. Local 
interests have not been requested to furnish assurances. 
Operations and results during fiscal year. Maintenance: 
Project was operated and maintained at a cost 
of $68,208 including a contract for the removal of five 
bridges deemed unsafe for $10,000. 
Condition at end of fiscal year: General and Real 
Estate design memorandums and detailed plans for the 
La Farge Dam and spillway and for relocations have 
been completed. Land acquisition negotiations began in 
December 1968. The first land payment was made on 
January 15, 1969, and the land acquisition program is 
80 percent complete. Contracts for excavation of the left 
abutment, for test wells, and for construction of the 
outlet works and right abutment have been completed. 
A study of alternatives has been completed. Funds to 
complete the authorized project have been withheld and 
all further construction has been indefinitely suspended. 
Work has been accomplished to provide for 
completion of relocation work left partially completed 
when construction was suspended. Soldiers Grove has 
relocated out of the floodplain area after receiving funds 
from other agencies. A study of a modified dry dam was 
completed early FY 1985. On the basis of the study 
results, it was recommended that no further work be 
done to establish the economic feasibility of a dry or wet 
dam at La Farge and that the La Farge Lake and 
channel improvement project be deauthorized. 
27-8

ST. PAUL MINNESOTA DISTRICT 
20. LAKE ASHTABULA AND 
BALDHILL DAM, SHEYENNE 
RIVER, ND 
Location. Baldhill Dam is on the Sheyenne River, 16 
miles upstream from Valley City, ND, and about 271 
miles above mouth. Sheyenne River rises in central 
North Dakota and flows 500 miles generally southeast 
to enter Red River of the North about 10 miles north of 
Fargo, ND. (For general location see Geological Survey 
map of North Dakota.) 
Existing project. See page 1287 of Annual Report for 
1962. Project was authorized by Flood Control Act of 
1944 (S. Doc. 193, 78th cong., 2d sess., contains latest 
published map). Reservoir above Baldhill Dam was 
designated as Lake Ashtabula by Public Law 772, 81st 
Congress, 2d session. 
Local cooperation. See page 1288 of Annual Report 
for 1962. Complied with except for construction of Fargo 
diversion dam and ditch for which assurances furnished 
by city of Fargo were approved by the Secretary of War 
on June 26, 1947. Necessity for this feature will be 
reviewed. 
Operations and results during fiscal year. Maintenance: 
Project was operated and maintained, and 
inspections, investigations, monitoring and evaluations 
were performed at a cost of $392,749 by hired labor and 
$-7,673 by contract. Dam instrumentation, stability and 
safety assurance cost $342,711. Real Estate Management 
by the North Central Division cost $24,432. U.S. 
Fish and Wildlife Service coordination cost $680. Data 
collection cost $10,316 by hired labor and $42,524 by 
other government agencies. Water control analysis and 
water quality by other Corps of Engineer districts and 
hired labor cost $21,749 and $6,124, respectively. Dam 
safety engineering and design cost $93,754 by contract 
and $44,181 by hired labor. Administrative and other 
miscellaneous costs were $111,170. 
Condition at end of fiscal year: Project completed in 
March 1956 except construction of recreational facilities 
which is being accomplished intermittently. United 
States owns 7,816.5 acres of land in fee and easements 
on 666.2 acres. Construction initiated in July 1947 and 
major features completed in November 1950. Dam was 
placed in permanent operation in spring of 1951. Structures 
are in good condition. 
21. LAKE DARLING, SOURIS RIVER, 
ND 
Location. On the Souris River in Ward, Renville, 
McHenry, and Bottineau Counties in northwestern 
North Dakota. The existing Lake Darling Dam, which 
is to be raised, is located about 20 miles northwest of 
Minot, North Dakota. The project also includes features 
at the communities of Sawyer and Velva and at various 
locations along the 358-mile U.S. portion of the Souris 
River. (For general location see Geological Survey Map 
of North Dakota.) 
Existing project. The Lake Darling project provides 
for raising Lake Darling design pool by approximately 4 
feet. The project also provides for other work on the 
Souris River such as levee improvements at Velva, 
Sawyer, and six subdivision areas between Burlington 
and Minot, floodproofing of rural residences, modification 
of refuge structures in the Upper Souris and J. 
Clark Salyer Refuges, and bridge stabilizations relocations 
in the reservoir. The work is a portion of the 
Burlington Dam project which required postauthorization 
approval prior to construction. However, 
Congress has directed the Corps not to take further 
actions to construct the Burlington Dam until expressly 
directed to do so. Estimated Federal cost (1986) for new 
work is $57,100,000. Project was authorized by 1982 
Energy and Water Development Appropriations Act, 
Public Law 97-88 approved December 4, 1981. 
Local cooperation. See Annual Report for 1983 for 
requirements. Representatives of the water resource 
districts from Ward, Renville, McHenry, and Bottineau 
Counties area agreed to become members of a Souris 
River Joint Board for flood control, which would serve 
as local sponsor for the project. A local cooperation 
agreement for construction at Velva was signed in 
November 1984 and another local cooperation agreement 
will be prepared for the remainder of the Lake 
Darling project after a decision has been made on cost 
sharing for the entire project. 
Operations and results during fiscal year. New 
Work: Preconstruction planning for the Lake Darling 
unit was continued at a cost of $1,228,353. Construction 
costs for improvements at Velva were $2,607,835. Engineering 
and design, and supervision and administration, 
at the Velva Unit cost $21,109, and $137,047, 
respectively. 
Condition at end of fiscal year: Preconstruction planning 
for the Lake Darling unit and construction on the 
Velva unit are in progress. 
22. LAKE PULASKI, WRIGHT COUNTY, 
MN 
Location. Lake Pulaski is approximately 45 miles 
northwest of the Twin Cities of Minneapolis and St. 
Paul, Minnesota. It lies within three local political 
jurisdictions (City of Buffalo, Wright County and Buffalo 
Township). 
Existing project. Lake Pulaski has no natural outlet. 
The lake has been rising over the past several years, 
inundating a number of houses or summer residences. 
Over 50 more structures are still vulnerable to flooding. 
A combination of a pumped pipeline and gravity-flow 
storm sewers to convey excess water through the city of 
Buffalo from Lake Pulaski to Buffalo Lake is to be 
constructed to stabilize the lake. Included in this project 
is a storm sewer upgrade which is to be constructed by 
the city of Buffalo. The lake will be maintained at 
elevation 966.0 feet mean sea level. This is the lowest 
level permitted for an artificial outlet under State of 
Minnesota rules governing landlocked lakes. The total 
cost of the project is currently estimated at $1,384,500, 
of which the Federal cost is $1,038,400. The project was 
approved by the Chief of Engineers for construction in 
27-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
March 1985 under the authority contained in Section 
205 of the 1948 Flood Control Act, as amended. 
Local cooperation. A local assurance agreement 
was adopted by the Lake Pulaski Improvement District, 
the local sponsor, in August 1986. Local interests are 
required to provide without cost to the United States all 
real estate interests necessary for construction, operation, 
and maintenance of the project; accomplish all 
alterations and relocations of buildings, utilities, highways 
and highway bridges necessary for the construction, 
operation, and maintenance of the project; hold 
and save the United States free from damages caused by 
the construction, operation and maintenance of the 
project except damages due to the fault or negligence of 
the United States or its contractors; provide all costs in 
excess of the $4 million Federal cost limitation; maintain 
and operate the project after completion without 
cost to the United States in accordance with regulations 
prescribed by the Secretary of the Army; provide during 
the period of construction an amount not less than 25 
percent of the total project costs of which in no case shall 
the cash payment be less than 5 percent of the total 
project costs; comply with the applicable provisions of 
the "Uniform Relocations Assistance and Real Property 
Acquisition Policies Act of 1970," Public Law 91-646, 
approved January 2, 1971; comply with Section 601 of 
Title VI of the Civil Rights Act of 1964 (Public Law 
88-352) and Department of Defense Directive 5500.11 
issued pursuant thereto and published in Part 300 of 
Title 32, Code of Federal Regulations, in connection 
with the construction and subsequent maintenance and 
operation of the project. 
Operations and results during fiscal year. New 
Work: Engineering and design and study costs were 
$106,728. 
Condition at end of fiscal year: A contract for flood 
protection at Lake Pulaski was awarded September 
1986. 
23. LAKE TRAVERSE AND BOIS DE 
SIOUX RIVER, SD AND MN 
Location. Works covered by this project lie along 
Lake Traverse and Bois de Sioux River between upper 
end of Lake Traverse at Browns Valley, MN, and the 
mouth of Bois de Sioux River at Breckenridge, MN. 
Lake drains through river to Red River of the North, 
and the two waters form a portion of boundary between 
State of Minnesota and States of North and South 
Dakota. (For general location, see Geological Survey 
map of Minnesota.) 
Existing project. See page 1289 of Annual Report for 
1962. Existing project was authorized by Flood Control 
Act of June 22, 1936. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Project and related facilities were operated and 
maintained, and inspections and evaluations performed 
at a cost of $277,289. 
Condition at end of fiscal year: Existing project was 
completed in June 1948, except for minor recreational 
facilities. Fee title to 1,144.13 acres and easements on 
6,172.25 acres of land have been acquired. White Rock 
Dam and Reservation control structures are in operation, 
and structures and appurtenances are in good 
condition. Remedial work for repair of apron at White 
Rock Dam was completed in November 1968. Roadways 
across structure are open to public travel. 
24. MANKATO AND NORTH 
MANKATO, MN 
Location. Along Minnesota River between miles 
103.5 and 109.5 near Mankato, North Mankato, and Le 
Hillier, in south-central Minnesota. (For general location 
see Geological Survey map of Minnesota.) 
Existing project. As modified as a result of severe 
1965 flood, provides for protection of communities of 
Mankato, North Mankato, and Le Hillier by means of 
levees and floodwalls with pumping plants and interior 
drainage facilities. See page 1090 of Annual Report for 
1967 for further details. Additional channel improvement, 
levees, pumping, and interior drainage features 
have been included in the Mankato unit of the project 
for protection from the high flows of Indian Creek. 
Expansion of Indian Creek improvements were made 
during detailed studies as a result of updated hydrologic 
data. Highway bridge relocations made necessary by the 
project have been authorized at Federal expense. Estimated 
Federal cost (1986) for new work is $94,800,000. 
Project was authorized by 1958 Flood Control Act (H. 
Doc. 437, 84th Cong., 2d sess., contains latest published 
map.) Project was modified by 1965 Flood Control Act, 
and by the Water Resources Development Acts of 1974 
and 1976. 
Local cooperation. Requirements have been fully 
complied with. See Annual Report for 1973 for requirements. 
Resolutions agreeing to provide formal assurances 
of local cooperation, when requested, were passed 
by the city council of North Mankato, Mankato, and 
South Bend Township (Le Hillier), respectively, on November 
12, 1968. 
Operations and results during fiscal year. Construction 
of the T.H. 60/Main Street bridge relocation 
continued and Stage 3C-1 construction was completed. 
Construction of the C&NW railroad bridge relocation 
and Stage 2B-HP work in Le Hillier was initiated. 
Construction costs for improvements at Mankato were 
$9,556,950, at North Mankato were $-514,390 and 
at Le Hillier were $120,684. Engineering and design by 
contract cost $287,619 and by hired labor cost $302,668. 
North Central Division Real Estate cost $228,532. Supervision 
and administration cost $261,138 by hired 
labor, $41,167 by contract, and$-2,019 by other Corps. 
Other miscellaneous costs were $-6,244. 
Condition at end of fiscal year: Construction of the 
pumping stations, interior drainage facilities and the 
diversion channel are complete. The flood barriers are 
essentially complete except for a short segment of 
27-10

ST. PAUL MINNESOTA DISTRICT 
flood'wall at the Main Street bridge (Stage 3C-2), and 
the Stage 2B-HP levee work underway. 
25. MIDDLE RIVER AT ARGYLE, MN 
Location. In Marshall County in northwestern Minnesota 
on the Middle River within the city limits of 
Argyle, Minnesota. 
Existing project. The plan of protection includes a 
system of levees, road raises along with interior drainage 
facilities to provide main developed parts of the City 
of Argyle with one percent chance flood protection. Also 
included is the evacuation of 12 residences which are 
located outside of the line of flood barrier protection. 
Total Federal cost of the project is estimated at 
$1,013,000 (March 1985 Detailed Project Report). The 
project was approved for construction on August 1, 
1985, by the Chief of Engineers. The project is being 
constructed under the authority of Section 205 of the 
1948 Flood Control Act, as amended. 
Local cooperation. See Annual Report for 1985 for 
requirements. A local assurance agreement required by 
Public Law 91-611 was adopted by the City of Argyle in 
August 1985. 
Operations and results during fiscal year. New 
Work: Construction improvements cost $807 by hired 
labor and $297,705 by contract. Engineering and design 
cost $119,352 by hired labor and $13,743 by contract. 
North Central Division real estate and Fish and Wildlife 
Service cost $1,640 and $760, respectively. Supervision 
and administration costs were $41,218. Contributions 
in lieu of cash were $-27,170. 
Condition at end of fiscal year: Construction contract 
for Stage I was about 98 percent complete. Work on 
plans and specifications was completed. 
26. MINNESOTA RIVER AT LE SUEUR, 
MN 
Location. In Le Sueur County in south central Minnesota 
on the Minnesota River about 60 miles southwest 
of Minneapolis-St. Paul. 
Existing project. Provides for erosion control along 
the right bank of the Minnesota River near downtown 
Le Sueur immediately downstream of the State Highway 
93 bridge recently replaced by the Minnesota 
Department of Transportation. Beginning at the downstream 
terminals of the zone of protection for the bridge, 
the project involves the excavation of all unstable channel 
bank material and the placement of rock-fill along 
an approximate 300 foot reach of eroding bank. The 
project was approved by the Chief of Engineers for 
construction in March 1985 under the authority contained 
in Section 14 of the 1946 Flood Control Act, as 
amended. 
Location cooperation. See Annual Report for 1985 
for requirements. Local cooperation agreements were 
adopted by Le Sueur County in July 1985. 
Operations and results during fiscal year. New 
Work: A construction contract cost $176,008. Engineering 
and design, and supervision and administration and 
other miscellaneous costs were $11,515. 
Condition at end of fiscal year. A construction contract 
for the recommended work was awarded in August 
1985. Construction was completed in June 1986. 
27. PRAIRIE DU CHIEN, WI 
Location. In Crawford County in southwestern Wisconsin 
on the left bank of the Mississippi River. (For 
general location, see Geological Survey map of Wisconsin.) 
Existing project. Combines total evacuation with 
flood proofing and land use control measures to provide 
the desired reduction of potential flood damages within 
design limits. Evacuation was accomplished by purchase 
and relocation of structures in lowest portions of 
the floodplain. Project was authorized by Water Resources 
Development Act of 1974. 
Local cooperation. See Annual Report for 1974 for 
requirements. A local assurance agreement in accordance 
with Section 221 of the Flood Control Act of 1970 
was entered into with the City of Prairie du Chien on 
May 2, 1978, and signed by the Chief of Engineers on 
September 11, 1978. 
Operations and results during fiscal year. New 
Work: Costs for property acquisition and relocation 
activities were $-90,834. A contract for site restoration 
cost $5,721. Engineering and design cost $1,791 by 
hired labor and supervision and administration cost 
$196. Contributions in lieu of cash were $ -4,661. 
Condition at end of fiscal year: Project is complete. 
28. RED LAKE RIVER MN, 
INCLUDING CLEARWATER 
RIVER, MN 
Location. Works covered by this project lie along 
upper reach of Red Lake River and also along 
Clearwater River, a tributary of Red Lake River, between 
a point near Plummer, MN, and a point just 
above the mouth of Ruffy Brook. Red Lake River, 
principal tributary of Red River of the North, has its 
source at the outlet of Lower Red Lake in northwestern 
portion of Minnesota and flows westerly about 196 miles 
to its junction with Red River of the North at East 
Grand Forks, MN. Clearwater River has a general 
westerly course from its source near Ebro, MN, about 
205 miles to its junction with Red Lake River at Red 
Lake Falls, MN. (For general location, see Geological 
Survey map of Minnesota.) 
Existing project. See page 1281 of Annual Report for 
1962. Project was authorized by 1944 Flood Control Act 
(H. Doc. 345, 78th Cong., 1st sess., contains latest 
published map.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Structures were operated and maintained and 
inspections and evaluations performed at a cost of 
$142,367. 
27-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Condition at end of fiscal year: Construction of major 
improvements on Red Lake River initiated in February 
and the Clearwater River initiated in October 1948 
were completed in June 1956. Replacement of rock and 
brush dam on Red Lake River at Indian boundary with 
a concrete structure and appurtenant work was completed 
in June 1959 to restore marshes in the area to 
better wildlife conditions. Construction of a bridge on 
Clearwater Road was completed by the Indian Service 
in July 1965. A contract for improvements on Red Lake 
River was completed in November 1966, and a contract 
for restoration of water levels in Red Lake River 
marshes was completed in November 1968. Operation of 
Red Lake Dam was assumed by the Corps on April 1, 
1951. Channels are in good condition and indicate 
effectiveness of project as a flood control measure. 
29. RED RIVER OF THE NORTH AT 
ARGUSVILLE, ND 
Location. In Cass County in eastern North Dakota 
near the confluence of the Red River of the North and 
the Sheyenne River about 15 miles northwest of Fargo, 
North Dakota. (For general location, see Geological 
Survey map of Minnesota.) 
Existing project. The project involves a levee encircling 
the City of Argusville with associated interior 
flood control facilities. The total levee system would be 
about 1.9 miles long and would have an average height 
of about 8 feet. Interior flood control facilities consist of 
interceptor ditches and pipes, two temporary ponding 
areas and a pumping station to periodically discharge 
impounded water. Total Federal cost (1986) of the 
project is estimated at $1,600,000. The project was 
approved by the Chief of Engineers for construction 
July 5, 1985, under the authority contained in Section 
205 of the 1948 Flood Control Act, as amended. 
Local cooperation. See Annual Report for 1985 for 
requirements. A local assurance agreement was adopted 
by the City of Argusville, the local sponsor, in July 
1985. 
Operations at end of fiscal year. New Work: Construction 
contracts cost $167,858. North Central Division 
real estate cost $1,081. Engineering and design cost 
$3,619 by contract and $36,410 by hired labor. Supervision 
and administration costs were $24,870. 
Condition at end of fiscal year: A construction contract 
for Stage 1 involving the west levee was completed 
in July 1986. A construction contract for Stage 2 involving 
the remainder of the project was awarded in August 
1986 and was 10 percent complete at the end of fiscal 
year 1986. 
30. RED RIVER OF THE NORTH 
DRAINAGE BASIN, MN, SD & ND 
Location. Red River of the North Basin, within the 
United States, includes northeastern corner of South 
Dakota and much of eastern North Dakota and northwestern 
Minnesota. Red River of the North, formed by 
confluence of Otter Tail and Bois de Sioux Rivers, flows 
northward through this region, forming boundary between 
North Dakota and Minnesota. (For general location 
of basin, see Geological Survey maps of Minnesota 
and South Dakota.) 
Previous project. See page 1278 of Annual Report for 
1962 for navigation and flood control projects in the 
basin, not part of this project. 
Existing project. Project includes improvements for 
local protection in interests of flood control and major 
drainage accomplished by channel improvement, levees, 
etc., in addition to construction of a multiple purpose 
reservoir on Otter Tail River to control floods and, in 
conjunction with previously authorized Federal reservoir 
project at Baldhill site of Sheyenne River and at 
Red Lake, to increase low flows for water supply and 
pollution abatement. (See table 27-I for active units in 
comprehensive basin plan.) 
Project was authorized by Flood Control Acts of 1948 
and 1950. Public Works Authorization Act, 1957, authorized 
Chief of Engineers to acquire such lands as were 
beyond legal authority of the City of Grand Forks to 
acquire. Section 205 of the Flood Control Act of 1970 
provided for extension of the expiration date for the 
East Grand Forks project. Authorization of the 
Sheyenne River (Kindred Lake) project by the 1970 
Flood Control Act provided for the deletion of channel 
improvement on the lower 48.8 miles of the Sheyenne 
River authorized under the Flood Control Acts of 1948 
and 1950. Latest published map is in House Document 
185, 81st Congress, 1st session. 
Local cooperation. See page 1039 of Annual Report 
for 1965. Following the flood of 1965, the City of East 
Grand Forks requested reactivation of the project and 
furnished a resolution adopted May 11, 1965, indicating 
its willingness to meet the requirements of local cooperation. 
Expiration date for the East Grand Forks 
project was extended to April 17, 1975, permitting local 
interests additional time to furnish assurances of local 
cooperation. A local assurance agreement was passed by 
the city on March 27, 1975, and accepted by the acting 
Director of Real Estate, OCE for the Secretary of the 
Army on April 9, 1975. 
Operations and results during fiscal year. New 
Work: Preconstruction planning was continued for the 
East Grand Forks project at a cost of $365,679. Maintenance: 
Orwell Lake and Dam were operated as required 
and miscellaneous inspections, reports, and repairs 
were made at a cost of $68,821 by hired labor, and 
$67,495 by contract. Real estate management by the 
North Central Division cost $5,544. Data collection and 
maintenance of stream gaging cost $11,116 by hired 
labor, $1,975 by contract and $13,650 by U.S. Geological 
Survey. Water quality and control cost $26,312 by hired 
labor and $26,500 by U.S. Geological Survey. Supervision 
and administration, engineering and design and 
other miscellaneous costs were $39,948, $108,751 and 
$ - 2,233, respectively. 
Condition at end of fiscal year: Major construction for 
all active units except for East Grand Forks, MN, is 
complete. Preconstruction planning is underway at East 
27-12

ST. PAUL MINNESOTA DISTRICT 
Grand Forks. A total of 1,985 acres of land for Orwell 
Lake and Dam is owned in fee by the United States. See 
page 1281 of Annual Report for 1962 for periods of 
completion at active units of project other than Fargo. 
Work at Fargo, ND, started in May 1959, was completed 
in July 1963. (See table 27-I at end of chapter for total 
costs of new work to date.) 
Costs to date for operation and maintenance of Orwell 
Lake and Dam are $3,307,769. Total costs for active 
portion of project are $11,260,190. In addition, $350,034 
was expended from contributed funds for work done for 
local interests. 
31. RED RIVER AT THE NORTH AT 
HALSTAD, MN 
Location. In Norman County in western Minnesota 
on the Red River of the North about 36 miles north of 
Moorhead, Minnesota. (For general location see Geological 
Survey Map of Minnesota.) 
Existing project. Provides for a system of levees and 
interior flood control facilities along the right bank of 
the Red River of the North. The total levee system is 
about 2.4 miles long and varies from 0 to over 20 feet 
high. Most of the levee is 5 to 12 feet high. The levee 
rings the city except for about 0.6 mile of high ground. 
Other features include 4 ponding areas and a system of 
gatewells, pipes and ditches to provide interior flood 
control. 
The project was approved by the Chief of Engineers 
for construction April 5, 1983, under the authority 
contained in Section 205 of the 1948 Flood Control Act, 
as amended. Total Federal cost of the project was 
$2,012,000. 
Local cooperation. Fully complied with. See Annual 
Report for 1983 for requirements. A local assurance 
agreement required by Public Law 91-611 was adopted 
by the city of Halstad in April 1983. 
Operations and results during fiscal year. New 
Work: Construction contracts cost $17,457. Engineering 
and design cost $39,313 by hired labor. Supervision and 
administration costs were $6,811. 
Condition at end of fiscal year: Construction of the 
flood control project at Halstad is complete. An operation 
and maintenance manual was prepared and responsibility 
for the project was officially transferred to the 
city in August 1986. 
32. REDWOOD RIVER AT 
MARSHALL, MN 
Location. In Lyon County in southwestern Minnesota 
along the Redwood River about 68 miles above its 
confluence with the Minnesota River at the City of 
Marshall, Minnesota. (For general location see Geological 
Survey map for Minnesota.) 
Existing project. See page 1059 of Annual Report for 
1964 for completed channel improvement project authorized 
by 1960 Flood Control Act. Federal costs 
amounted to $1,802,866. 
The plan contained in June 1979 feasibility report 
provides for improvements upstream and downstream of 
the existing channel project at Marshall which is affected 
by limited channel capacity in both reaches. The 
upstream measures would include 1.9 miles of levee, 0.7 
mile of channel improvement, an overflow structure, 
and 71 acres of floodway acquisition. The downstream 
improvements would consist of 1.5 miles of levee, 0.3 
mile of channel improvement, and interior drainage 
facilities. Recreation facilities would include multi-use 
trails and limited picnic facilities. The project would 
provide protection against a flood having an occurrence 
interval of about once in 114 years. Estimated Federal 
cost (1986) for new work is $3,260,000 and $870,000 is 
to be contributed by local interests. 
Local cooperation. Fully complied with for completed 
work. See page 1150 of Annual Report for 1963 
for requirements. Project was transferred to local interests 
on December 23, 1963. 
For new work, see Annual Report for 1985 for requirements. 
By resolution approved April 2, 1979, the City of 
Marshall agreed to assume non-Federal responsibilities 
for the proposed project. By letter dated July 8, 1982, 
the City of Marshall indicated its willingness to financially 
participate in construction of a project consistent 
with the current administration's proposed upfront financial 
and cost sharing policies. 
Operations and results during fiscal year. New 
Work: Preconstruction planning was continued at a cost 
of $133,624. 
Condition at end of fiscal year: Construction of completed 
work was initiated August 1962 and completed 
December 1963. Preconstruction planning for the new 
work is in progress. 
33. ROCHESTER, MN 
Location. In Olmstead County in southeastern 
Minnesota on the South Fork of the Zumbro River. 
(For general location, see Geological Survey map of 
Minnesota.) 
Existing project. Provides for stream channel modifications 
and levees functioning in combination with a 
system of seven headwaters reservoirs. Principal features, 
in addition to the reservoirs, include 0.5 mile of 
grass-sloped channels, 6.1 miles of riprapped or gabionlined 
channels, 0.9 mile of architecturally-treated concrete 
channels, 0.5 mile of dredged channel, six drop 
structures, 2.4 miles of levee, and hiking and biking 
trails. Estimated cost (1986) to the United States for 
new work is $46,600,000 and $6,458,000 is to be contributed 
by local interests. Project was authorized by the 
Water Resources Development Act of 1974 (H. Doc. 156, 
93rd Cong., 1st sess., contains latest published map.) 
Local cooperation. See Annual Report for 1974 for 
requirements. A local assurance agreement will be 
required prior to the start of construction. By letter 
dated October 18, 1985, the city of Rochester indicated 
its intent to participate voluntarily in project financing 
as proposed in legislation being considered by Congress. 
27-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Operations and results during fiscal year. New 
Work: Preconstruction planning was continued at a cost 
of $229,894. 
Condition at end of fiscal year: Preconstruction planning 
is essentially complete. 
34. ROSEAU RIVER, MN 
Location. In Roseau County and northeastern 
Kittson County, in northwestern Minnesota, and in 
south-central Manitoba, Canada. (For general location 
of the works in the United States see Geological Survey 
map of Minnesota.) 
Existing project. Provides for improvement of 
Roseau River for flood control consisting of 44.4 miles of 
channel improvement, two sections of earth levees with 
lengths of 1.9 and 5.9 miles, respectively, 76 side ditch 
inlet transitions; remedial works along 16.6 miles of 
channel in Canada or an acceptable alternative therefor; 
one new bridge; and alteration of the existing dam 
in Roseau Village. Remedial works will be constructed 
in Canada at the expense of the United States. Estimated 
cost (1986) to the United States for new work is 
$23,400,000 including $6,690,000 for cost of work in 
Canada to be accomplished with United States funds 
and $6,600,000 is to be contributed by local interests. 
Project was authorized by Flood Control Act of 1965 (H. 
Doc. 282, 89th Cong., 1st sess., contains latest published 
map.) 
Local cooperation. See Annual Report for 1968 for 
requirements. Local interests have formed a Roseau 
River Watershed District to provide local cooperation 
requirements and acquire rights-of-way. 
Operations and results during fiscal year. New 
Work: Planning activities were continued relative to 
coordination of the project plan with Canadian interests. 
Engineering and design and supervision and administration 
cost, $9,748. 
Condition at end of fiscal year: Planning is in progress 
and coordination with Canadian interests is underway. 
The general design memorandum was submitted in 
October 1971 and approved in March 1972. Design 
memorandum supplements which contain dimensions of 
environmental features added to the project were submitted 
in October 1975 and June 1980 and approved in 
November 1975 and July 1980, respectively. An EIS 
supplement was filed with the EPA in October 1981. 
35. SHEYENNE RIVER FLOOD 
CONTROL, ND (Formerly Kindred 
Lake) 
Location. The Sheyenne River Basin is included in 
16 counties in the southeastern portion of North Dakota 
and drains an area of 7,140 square miles into the Red 
River of the North near Fargo, North Dakota. The 
principal area of flood damages in the basin is located at 
the lower end within Cass County and the City of West 
Fargo. The authorized Kindred Lake project is in 
Richland County, ND, on the Sheyenne River, about 70 
miles above its mouth and 5 miles above Kindred, ND. 
(For general location, see Geological Survey map of 
North Dakota.) 
Existing project. The authorized project provides for 
a multiple-purpose impoundment for flood control, water 
quality control, recreation, and fish and wildlife 
purposes to control the runoff from 3,014 square miles. 
The improvements would be coupled with a revised 
operating plan for the existing Baldhill Dam and with 
appropriate flood plain management measures at communities 
along the river. See Annual Report for 1973 
for details. Project was authorized by 1970 Flood Control 
Act (H. Doc. 330, 91st Cong., 2d sess., contains 
latest published map.) Due to local concerns, a changed 
set of planning criteria, and potential changed conditions, 
a complete reformulation and reevaluation of 
alternatives was undertaken during preconstruction 
planning. The reevaluation studies showed that another 
alternative plan is more favorable than the authorized 
project. The General Reevaluation Report, completed in 
1982, recommends implementation of a plan other than 
the authorized plan. The plan recommended in the 
General Reevaluation Report includes levees and diversions 
at West Fargo/Riverside, a flood diversion channel 
from Horace to West Fargo, and a five foot raise of the 
flood control pool at Baldhill Dam. Other actions are 
also identified that could be taken by non-Federal interests 
to enhance the degree of flood damage reduction 
provided by the overall plan. This new plan represents a 
significant change from the authorized project and recommends 
deauthorization of the Kindred Lake project 
and reauthorization of the new plan. The estimated 
Federal cost (1986) of the plan is $22,400,000 and 
$4,105,000 is to be contributed by local interests. 
Local cooperation. See Annual Report for 1971 for 
requirements of the project as authorized. On July 7, 
1982, and May 20, 1983, the North Dakota State Water 
Commission furnished a letter of support for the recommended 
plan for flood control in the lower Sheyenne 
River Basin and also expressed its willingness to act as 
a non-Federal sponsor. On August 2, 1982, and July 30, 
1982, respectively, the City of West Fargo and the 
Southeast Cass Water Resource District furnished letters 
of support and indicated their willingness to cooperate 
with the North Dakota State Water Commission. 
The Southeast Cass Water Resource District reiterated 
its support of the project by letter dated March 30, 1984. 
Formal assurances of local cooperation will be requested 
after completion of the General Design Memorandum. 
Operations and results during fiscal year. New 
Work: Preconstruction planning was continued at a cost 
of $733,305. 
Condition at end of fiscal year: Preconstruction planning 
is in progress. 
36. SHEYENNE RIVER, VALLEY CITY, 
ND 
Location. In central Barnes County in southeastern 
North Dakota on the Sheyenne River within the city 
limits of Valley City, North Dakota. 
27-14

ST. PAUL MINNESOTA DISTRICT 
Existing project. The plan of protection includes 
placement of pervious fill, riprap, and suitable bedding 
material for emergency bank erosion protection along a 
400 foot reach of the left bank of the Sheyenne River. 
The purpose of the project is to control the erosion and 
subsequent sloughing threatening College Street and 
utilities under the roadway. The project would provide a 
stable bank and protect both the road and utilities. 
Total Federal cost of the project is estimated at 
$111,000. The project was approved for construction on 
July 25, 1986, by the Chief of Engineers. The project is 
being constructed under the authority of Section 14 of 
the 1946 Flood Control Act, as amended. 
Local cooperation. Local interests are required to 
hold and save the United States free from damages 
caused by the construction, operation and maintenance 
of the project except where such damages are due to the 
fault or negligence of the United States or its contractors; 
provide without cost to the United States all lands, 
easements and rights-of-way necessary for construction, 
operation, and maintenance of the project; accomplish 
without cost to the United States all alterations and 
relocations of buildings, utilities, highways and highway 
bridges, sewers and other facilities; assume full 
responsibility for all project costs in excess of the Federal 
cost limit of $250,000; maintain the project after 
completion in accordance with regulations prescribed by 
the Secretary of the Army; comply with provisions of the 
Uniform Relocations Assistance and Real Property Acquisition 
Policies Act of 1970, Public Law 91-646, approved 
January 2, 1971, in acquiring lands, easements 
and rights of way for construction and maintenance of 
the project, and inform affected persons of pertinent 
benefits, policies and procedures in connection with said 
Act; comply with Section 601 of Title VI of the Civil 
Rights Act of 1964 (Public Law 88-352) and Department 
of Defense Directive 5500.11 issued pursuant thereto 
and published in Part 300 of Title 32, Code of Federal 
Regulations, in connection with the construction, maintenance 
and operation of the project. A local assurance 
agreement required by Public Law 91-611 was adopted 
by the City of Valley City in August 1986. 
Operation and results during fiscal year. New 
Work: Completion of the Initial Appraisal Report and 
plans and specifications was accomplished at total cost 
for the year of $26,344 by hired labor. 
Condition at end of fiscal year. A construction contract 
was awarded in September 1986. 
37. SOURIS RIVER, VELVA, ND 
Location. In McHenry County in north central North 
Dakota on the Souris River about 24 miles Southeast of 
Minot, North Dakota. 
Existing project. Provides for erosion control along 
the north bank of the Souris River at the sewage 
lagoons serving the City of Velva. The proposed protection 
plan involves the excavation of unstable river bank 
material in two reaches totalling about 600 feet long 
and the placement of a pervious sand and gravel fill and 
rip-rap. Total Federal cost (1986) of the project is estimated 
at $125,000. The project was approved by the 
Chief of Engineers for construction in July 1986 under 
the authority contained in Section 14 of the 1946 Flood 
Control Act, as amended. 
Local cooperation. A local cooperation agreement 
was adopted by the City of Velva in July 1986. Local 
interests are required to provide without cost to the 
United States all lands, easements and rights-of-way 
necessary for construction, operation, and maintenance 
of the project; accomplish all alterations and relocations 
of streets, highways, sewer, water supply, drainage and 
other utility facilities; hold and save the United States 
free from damages caused by the construction, operation 
and maintenance of the project except damages due to 
the fault or negligence of the United States or its 
contractors; provide all costs in excess of the $250,000 
Federal cost limitation; maintain and operate the 
project after completion without cost to the United 
States in accordance with regulations prescribed by the 
Secretary of the Army; comply with the applicable 
provisions of the Uniform Relocations Assistance and 
Real Property Acquisition Policies Act of 1970, Public 
Law 91-646, approved January 2, 1971; comply with 
Section 601 of Title VI of the Civil Rights Act of 1964 
(Public Law 88-352) and Department of Defense Directive 
5500.11 issued pursuant thereto and published in 
Part 300 of Title 32, Code of Federal Regulations, in 
connection with the construction and subsequent maintenance 
and operation of the project. 
Operation and results during fiscal year. New 
Work: Engineering and design and administrative costs 
were $17,937. 
Condition at end of fiscal year. A construction contract 
for the recommended work was awarded in September 
1986. 
38. STATE ROAD AND EBNER 
COULEES, WI 
Location. In La Crosse County in west-central Wisconsin, 
on the south side of the City of La Crosse. (For 
general location, see Geological Survey map of Wisconsin.) 
Existing project. The plan of improvement for local 
protection (flood control) consists of channel deepening 
and enlarging downstream from Hagen Bridge to the 
mouth of Pammel Creek and includes 10,200 feet of 
concrete-lined rectangular channel, a drop chute inlet 
structure, a side channel inlet structure, a stilling 
basin, a terminus structure, and three new street 
bridges. The upper 4,000 feet of rectangular channel is 
designed for supercritical flow and the remaining 6,200 
feet of channel is designed for subcritical flow. When 
completed, the project will provide Standard Project 
Flood (SPF) protection. The city replaced a fourth bridge 
in 1980 that was previously included in the authorized 
plan. The city also replaced a railroad bridge in 1985 
that was also included in the authorized plan. In 1986, 
the city constructed 400 feet of rectangular channel in 
the downstream reach to SPF protection. Estimated cost 
(1986) to the United States for new work, exclusive of 
27-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
the Ebner Coulee portion of the project which was 
deleted due to lack of economic feasibility, is 
$24,800,000 and $4,162,000 is to be contributed by local 
interests. Project was authorized by 1968 Flood Control 
Act (H. Doc. 360, 90th Cong., 2d sess., contains published 
map.) 
Local cooperation. See page 826 of Annual Report 
for 1969. The local sponsor withdrew support for the 
project in 1976 citing increased non-Federal costs and 
lack of agreement on local cost sharing between three 
local units of government located within the project 
area. The project was reclassified as inactive on April 7, 
1977, but was reactivated on November 8, 1978, after 
the La Crosse County Board of Supervisors, the La 
Crosse City Council, and the Town of Shelby passed 
separate resolutions on September 17, 1978, July 13, 
1978, and July 10, 1978, respectively, which requested 
continuance of the project. All three groups reaffirmed 
their support by letter in July 1981. On October 4, 1982, 
the City of La Crosse furnished a letter in further 
support for the project and acknowledged that it would 
serve as the local sponsor. The City sent a letter of 
intent again on December 13, 1984, and furnished letter 
of assurance September 17, 1985. 
Operations and results during fiscal year. New 
Work: Preconstruction planning was continued at a cost 
of $20,953. 
Condition at end of fiscal year: Preconstruction planning 
is substantially completed. Plans and specifications 
for the first stage of construction are complete. 
Ebner Coulee has been recommended for reclassification 
to "inactive" due to lack of economic feasibility. 
39. TWIN VALLEY LAKE, WILD RICE 
RIVER, MN 
Location. In Norman County in west-central Minnesota, 
northeast of the City of Moorhead, on the Wild 
Rice River about 2 miles east of Twin Valley, MN. The 
Wild Rice River is a tributary of the Red River of the 
North. (For general location, see Geological Survey map 
of Minnesota.) 
Existing project. The project authorization provides 
for reservoir development on the Wild Rice River near 
Twin Valley, Minnesota, for flood damage reduction, 
recreation, and fish and wildlife enhancement. The 
principal features include an 84 foot high, 7,700 foot 
long, earthen dam, a gated concrete spillway with concrete 
chute and stilling basin, a 10 foot diameter gated 
circular conduit for low flow outlet works, and recreation 
development on the created 540 acre reservoir. 
Storage capacity would provide 7,500 acre-feet for recreation 
and sedimentation and 44,700 acre-feet for flood 
control. The proposed works include development of 
three recreation areas along the margin of the lake for 
public use. The Federal Government would acquire 
about 3,500 acres of land necessary for carrying out the 
purposes of the project. Approximately 2,200 additional 
acres will be acquired to offset fish and wildlife habitat 
losses associated with project construction. 
Estimated Federal cost (1986) for new work is 
$19,300,000. Project was authorized by 1970 Flood Control 
Act (H. Doc. 366, 90th Congress, 2d sess., contains 
latest published map.) 
Local cooperation. See Annual Report for 1971 for 
requirements. Local interests have not been requested 
to furnish assurances. The Norman County Board of 
Commissioners, by resolutions dated November 7, 1974, 
September 19, 1978, and August 26, 1981, has declared 
its intention to provide local cooperation for recreation 
and fish and wildlife enhancement. By letters dated 
August 17, 1982, and August 31, 1984, the Wild Rice 
Watershed Board expressed their support and intent to 
provide local cooperation requirements and participate 
in innovative financing for flood control. The Norman 
County Board of Commissioners has also indicated the 
capability to provide assurances of local cooperation 
relating to flood control improvments. 
Operations and results during fiscal year. New 
Work: Preconstruction planning was continued at a cost 
of $61,707. 
Condition at end of fiscal year: Preconstruction planning 
is in progress. Project requires further authorization 
for mitigation lands. 
40. WARNER ROAD MISSISSIPPI 
RIVER, ST. PAUL, MN 
Location. Left bank of Mississippi River, adjacent to 
Warner Road at about River mile 839, St. Paul, Minnesota. 
Existing project. The project to protect the 
streambank from erosion which threatens Warner Road 
was authorized under Section 14 of the 1946 Flood 
Control Act, as amended. The initial appraisal report, 
dated August 1984 recommended protection with 7,660 
cubic yards of graded rock fill along about 350 feet of 
eroding river bank. The project was approved for construction 
by the Office Chief of Engineers on July 2, 
1985. Total Federal cost of the project is $250,000. 
Local cooperation. A local cooperation agreement 
was adopted by the City of St. Paul, Minnesota, in 
August 1985. Local interests are required to provide 
without cost to the United States all lands, easements 
and rights-of-way necessary for construction, operation, 
and maintenance of the project; accomplish all alterations 
and relocations of streets, highways, sewer, water 
supply, drainage and other utility facilities; hold and 
save the United States free from damages caused by the 
construction, operation and maintenance of the project 
except damages due to the fault or negligence of the 
United States or its contractors; provide all costs in 
excess of the $250,000 Federal cost limitation; maintain 
and operate the project after completion without cost to 
the United States in accordance with regulations prescribed 
by the Secretary of the Army; comply with the 
applicable provisions of the Uniform Relocations Assistance 
and Real Property Acquisition Policies Act of 
1970, Public Law 91-646, approved January 2, 1971; 
comply with Section 601 of Title VI of the Civil Rights 
Act of 1964 (Public Law 88-352) and Department of 
27-16

ST. PAUL MINNESOTA DISTRICT 
Defense Directive 5500.11 issued pursuant thereto and 
published in Part 300 of Title 32, Code of Federal 
Regulations, in connection with the construction and 
subsequent maintenance and operation of the project. 
Operation and results during fiscal year. New 
Work: A bank protection contract cost $159,000. Engineering 
and design and other study costs were $23,419. 
Condition at end of fiscal year. A contract for slope 
protection was awarded in December 1985. Project was 
substantially complete at end of fiscal year. 
41. WILD RICE RIVER, MAHNOMEN 
COUNTY, MN 
Location. In Mahnomen County, in west central 
Minnesota on the Wild Rice River about 1.4 miles 
southwest of the City of Mahnomen. 
Existing project. The project to protect the 
streambank from erosion which threatens County-State 
Aid Highway (CSAH) #5 is authorized under Section 14 
of the 1946 Flood Control Act, as amended. The initial 
appraisal report, dated September 1984, recommended 
protection with 320 cubic yards of gravel bedding and 
660 cubic yards of riprap along about 450 feet of eroding 
riverbank. The project was approved for construction by 
the Office Chief of Engineers on June 18, 1985. 
Local cooperation. A local cooperation agreement 
required by Public Law 91-611 was adopted by the 
County of Mahnomen, Minnesota, in August 1985. Local 
interests are required to provide without cost to the 
United States all lands, easements, and rights-of-way 
necessary for construction, operation, and maintenance 
to the project; accomplish without cost to the United 
States all required alterations and relocations in sewer, 
water supply, drainage, and other utility facilities; hold 
and save the United States free from damages due to the 
construction, operation, and maintenance of the project 
except where such damages are due to the fault or 
negligence of the United States or its contractors; maintain 
the project after completion; assume full responsibility 
for all project costs in excess of the Federal cost 
limit of $250,000; provide a cash contribution for project 
costs in proportion to any special benefits to non-public 
property; comply with applicable provisions of the Uniform 
Relocations Assistance and Real Property Acquisition 
Policies Act of 1970, Public Law 91-646, approved 
January 2, 1971, in acquiring lands, easements, and 
rights-of- way for construction and subsequent maintenance 
of the project and inform affected persons of 
pertinent benefits, policies and procedures in connection 
with said Act; comply with the Section 601 of Title VI of 
the Civil Rights Act of 1964 (Public Law 88-352) and 
Department of Defense Directive 5500.11 issued pursuant 
thereto and published in Part 300 of Title 32, Code 
of Federal Regulations, in connection with the construction 
and subsequent maintenance and operation of the 
project. 
Operations and results during fiscal year. New 
Work: A construction contract cost $5,519.Engineering 
and design and other study costs were $9,762. 
Condition at end of fiscal year: Project was completed 
in October 1985 and is scheduled to be turned over to 
the local sponsor in November 1986. 
42. WINONA, MN 
Location. At Winona County in southeastern Minnesota 
on the right bank of the Mississippi River about 
725 miles above mouth of the Ohio River. (For general 
location see Geological Survey map of Minnesota.) 
Existing project. See page 833 of Annual Report for 
1968 for completed upstream improvements authorized 
by the Flood Control Act of 1958 providing for a continuous 
flood barrier about 6.1 miles long with related 
pumping and interior drainage facilities. Federal costs 
amounted to $2,147,131 of which $111,500 was expended 
for the portion then deferred for restudy and 
$17, 316 was contributed by local interests. 
Improvement authorized in 1971 under Section 201 of 
the Flood Control Act of 1965 (H. Doc. 152, 92d Cong., 
1st sess., contains latest published map) provides for 
levee and floodwall protection with necessary interior 
drainage works for the riverfront and the Lake Winona 
closure reaches, as well as a sound floodplain management 
program to prevent unwise development of the 
area bordered by U.S. Highway 61 and Burns Valley 
and Pleasant Valley Creeks. The plan would also provide 
the downstream flood barrier needed to prevent 
Mississippi River backup flows from entering Lake 
Winona and inundating the area now only partially 
protected by the completed segment of the project authorized 
by the 1958 Flood Control Act. The plan would 
also provide control of Burns Valley Creek by means of 
channel improvement, raising and extending the existing 
levee system, a drop structure, an erosion control 
structure, alteration of two highway bridges, and a 
sewer line modification. Earth levees averaging 10 feet 
in height total approximately 3.1 miles in length. Concrete 
floodwalls, also averaging about 10 feet in height, 
total about 2,025 feet in length. Estimated Federal cost 
(1986) for new work is $30,429,000 and $572,000 was 
contributed by local interests. Resolutions authorizing 
the project were adopted by the Public Works Committees 
of the House on July 29, 1971, and the Senate on 
November 18, 1971. 
Local cooperation. Fully complied with for completed 
work. See page 833 of Annual Report for 1968 for 
requirements. 
For improvements authorized in 1971 see Annual 
Report of 1972 for requirements. A local cooperation 
agreement required under Section 221 of the 1970 Flood 
Control Act was executed by the City of Winona on 
October 6, 1978. 
Operations and results during fiscal year. New 
Work: Construction contracts for Reaches B, C, and E 
cost $8,454, $6,939 and $14,206, respectively. Miscellaneous 
minor construction contracts cost $31,163. Engineering 
and design cost $21,209 by contract and $55,591 
by hired labor. Real estate management by NCD cost 
$5,827. Supervision and administration and other miscellaneous 
costs were $42,748. 
27-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Condition at end of fiscal year: The upstream improvement 
except for a portion of the project raising and 
extending the existing levee downstream from the Lake 
Winona outlet was completed in August 1967. Work 
authorized in 1971 is substantially complete. Project 
was formally dedicated by the city on October 13, 1985. 
43. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood control projects turned over to local interests 
were inspected to determine that project channels are 
kept clean and unobstructed, dikes and revetments are 
in good condition, and structures are in good repair and 
operable. Deficiencies, if any, were minor unless noted 
(See table 27-J on inspection of completed flood control 
projects.) 
Cost for the period was $43,419. Total cost to September 
30, 1986, is $809,429. 
Miscellaneous 
44. OTHER WORK UNDER SPECIAL 
AUTHORITY 
In the Aquatic Plant Control program (Section 302, 
Public Law 298, 89th Congress) coordination with the 
state of Minnesota cost $5,521, and the state of Wisconsin, 
$22,795. Other Corps of Engineer Wisconsin related 
costs were $5,846. Administrative and other miscellaneous 
costs were $3,719. 
General Investigations 
45. SURVEYS 
Flood control studies continued at a cost of 
$1,546,751. Coordination studies with other agencies 
and miscellaneous activities cost $358,257. Review for 
deauthorization, Tongue River cost $4,107. Total cost of 
surveys for the period was $1,909,115. 
46. COLLECTION AND STUDY OF 
BASIC DATA 
Costs during the period were $42,327 for International 
Water Studies and $179,416 for Flood Plain 
Management Services. Costs were $49,956 for stream 
flow data obtained by Corps gaging beyond cooperative 
stream-gaging program, and for hydraulic laboratory 
work in measurement and analysis of sediment load in 
streams. Costs were $96 for inspection of dams in 
conjunction with the national program of inspection of 
non-Federal dams. Total cost for collection and study of 
basic data was $271,795. 
47. CONTINUATION OF PLANNING 
AND ENGINEERING 
Cost during the period was $133,624 for Redwood 
River at Marshall, MN. For detail of the individual 
project see section 32 in text. 
48. ADVANCE ENGINEERING AND 
DESIGN 
Costs during the period were $1,463,603 for advance 
engineering and design projects. For details of individual 
projects see sections 10, 30, 33, 35, 38, and 39 in text. 
27-18

ST. PAUL MINNESOTA DISTRICT 
TABLE 27-A COST AND FINANCIAL STATEMENT 
See 
Section 
In Text Project 
1. Minnesota River, MN 
3. Reservoirs at 
Headwaters of 
Mississippi River, MN 
4. St. Croix River 
MN and WI 
5. Warroad Harbor 
and River, MN 
6. Zippel Bay, 
Lake of the 
Woods County, MN 
7. Bassett Creek, MN 
8. Big Stone Lake 
and Whetstone 
River, MN and 
SD 
9. Black Bear and 
Miller Lakes, MN 
10. Chaska, MN 
11. Devils Lake, ND 
12. Eau Galle River, WI 
13. Enderlin, Maple 
River, ND 
14. Hanover, Hennepin 
County, MN 
~ 
Total Cost to 
September 30 
Funding FY83 FY84 FY85 FY86 1986 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maj. Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
44,000 
439,098 
1,361,800 
1,485,496 
59,000 
6,605 
1,785,000 
1,673,967 
420,000 
419,039 
1,600,588 
1,544,335 
-97,000 
-7,956 
44,000 
199,906 
60,000 
79,090 
435,000 
416,333 
575,000 
473,040 
208,000 
800,572 
225,000 
242,018 
275,000 
159,656 
263,000 
261,079 
910,000 
386,927 
17,000 
30,503 
75,000 
52,669 
25,000 
41,949 
1,450,000 
904,550 
128,000 
147,247 
50,000 
32,045 
373,000 
364,914 
1,767,000 
570,621 
331,000 
275,094 
2,600,000 
861,589 
24,000 
22,720 
34,000 
25,752 
15,000 
14,668 
205,000 
800,088 
302,000 
227,418 
147,000 
59,680 
346,000 
316,949 
213,000 
1,413,067 
575,000 
502,985 
-72,000 
1,898,355 
-48,300 
7,585 
2,263,000 
2,040,208 
100 
100 
34,6004 
38,9474 
331,000 
87,146 
415,000 
323,387 
130,000 
221,445 
107,000 
173,867 
274,000 
244,984 
15,000 
52,066 
90,124 
606,000 
472,034 
361,669 
44,500 
23,960 
$ 2,057,7221 
$ 2,057,7221 
2,277,886 
2,277,886 
4,398,6282 
4,398,6282 
23,821,6463 
23,438,8953 
425,000 
425,000 
150,410 
150,410 
1,108,355 
1,108,355 
86,105 
86,105 
1,121,000 
1,119,775 
630,000 
328,237 
2,130,000 
2,020,970 
12,175,000 
12,069,9545 
2,111,200 
2,098,110 
471,000 
336,709 
1,843,000 
1,841,149 
2,470,000 
2,424,147 
9,039,250 
9,039,250 
4,902,105 
4,247,869 
4,000,0006 
3,942,2246 
44,500 
23,960 
27-19 
- 161,000 
7,385 161,546

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 27-A (CONTINUED) COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section September 30 
In Text Project 
15. Homme Lake and 
Dam, ND 
16. Irving Township 
at Nicols Road, 
Jackson County, WI 
17. Kickapoo River 
Gay Mills, WI 
18. Lac qui Parle 
Lakes, MN 
19. La Farge Lake 
and Channel 
Imp., WI 
20. Lake Ashtabula 
and Baldhill 
Dam, Sheyenne 
River, ND 
21. Lake Darling, 
Souris River, ND 
22. Lake Pulaski, 
Wright County, MN 
23. Lake Traverse 
and Bois de Sioux 
River, SD and MN 
24. Mankato and 
North Mankato, MN 
25. Middle River at 
Argyle, MN 
26. Minnesota River 
at Le Sueur, MN 
27. Prairie du Chien, WI 
28. Red Lake River, 
MN, including 
Clearwater 
River, MN 
29. Red River of the 
North at 
Argusville, ND 
Funding 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
97,000 
57,991 
184,000 
168,297 
550,000 
336,849 
22,000 
17,656 
16,268 
845,000 
788,978 
1,150,000 
1,176,694 
102,000 83,000 
108,738 99,956 
- 158,500 
- 14,290 
263,000 
312,230 
175,614 
21,000 
25,439 
180 
881,200 
898,714 
1,100,000 
1,113,594 
7,500 
7,500 
1,139,000 
517,273 
38,372 
42,000 
27,484 
1,241,000 
955,731 
3,000,000 
1,641,509 
75,000 
68,764 
190,000 179,000 203,000 
186,053 210,966 187,906 
5,950,000 7,645,000 9,176,000 
5,169,491 7,835,568 8,928,093 
60,000 40,000 215,000 
46,394 52,937 98,985 
- - 250,000 
- - 62,477 
161,000 -140,000 -125,000 
29,549 -171,891 103,876 
54,000 
34,383 
60,000 
55,178 
26,000 
52,072 
45,000 
44,994 
123,000 
72,031 
259,000 
108,758 
68,000 
83,257 
144,210 
33,000 
22,645 
384,500 
931,793 
78,000 
68,208 
934,000 
1,082,717 
3,434,000 
3,994,344 
325,000 
106,728 
265,000 
277,289 
10,875,000 
10,276,105 
345,000 
448,055 
187,523 
-70,000 
-87,787 
100,500 
142,367 
535,000 
233,838 
27-20 
FY83 FY84 FY85 FY86 1986 
1,396,0977 
1,396,0977 
2,203,421 
2,201,449 
158,500 
158,500 
33,000 
22,645 
964,873 
964,873 
4,994,663 
4,909,368 
18,642,000 
18,642,000 
181,000 
154,651 
3,325,6388 
3,325,6386 
12,908,152 
12,654,131 
9,484,000 
8,586,517 
407,500 
182,992 
1,339,727 
1,339,727 
3,112,619 
3,095,960 
76,845,500 
75,241,937 
725,000 
708,051 
250,0009 
250,0009 
3,685,000 
3,543,813 
3,120,07910 
3,120,07910 
941,302 
930,311 
1,014,000 
557,226

ST. PAUL MINNESOTA DISTRICT 
TABLE 27-A (CONTINUED) COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section September 30 
In Text Project Funding FY83 FY84 FY85 FY86 1986 
30. Red River of the 
North Drainage 
Basin, MN 
SD and ND 
31. Red River of the 
North at Halstad, MN 
32. Redwood River at 
Marshall, MN 
33. Rochester, MN 
34. Roseau River, MN 
35. Sheyenne River, 
ND (formerly 
Kindred Lake) 
36. Sheyenne River, 
Valley City, ND 
37. Souris River, 
Velva, ND 
38. State Road & 
Ebner Coulees, WI 
39. Twin Valley Lake, 
Wild Rice River, MN 
40. Warner Road, 
Mississippi River 
St. Paul, MN 
41. Wild Rice River, 
Mahnomen County, MN 
42. Winona, MN 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
175,000 255,000 
174,255 250,178 
152,000 200,000 
152,388 183,822 
296,000 1,273,000 
156,373 890,478 
- 150,000 
- 149,998 
316,000 100,000 
259,351 149,589 
- 250,000 
114,116 53,911 
- 165,000 
34,565 152,862 
275,000 
241,385 
481,000 
445,057 
200,500 
690,372 
235,000 
118,804 
400,000 
402,047 
331,000 
365,679 
385,000 
367,879 
22,500 
63,581 
75,000 
133,624 
244,000 
229,894 
19,271 9,748 
265,000 711,000 
245,105 733,305 
- 39,000 
- 26,344 
202,000 350,000 315,000 
178,742 344,756 323,466 
- 30,000 20,000 
- 1,680 45,983 
15,400 - 25,000 
8,173 7,027 23,049 
- - 58,500 
- - 43,219 
6,850,000 2,210,000 2,772,000 
6,470,128 2,354,380 2,770,665 
42,500 
17,937 
15,000 
20,953 
82,000 
61,707 
209,600 
182,419 
7,959,98411 
7,952,42111 
3,384,534 
3,307,769 
2,012,000 
2,012,000 
2,262,86612 
2,205,29212 
3,124,000 
3,082,838 
2,128,000 
1,910,338 
3,416,000 
3,404,852 
39,000 
26,344 
42,500 
17,937 
1,787,000 
1,772,866 
2,043,700 
2,021,070 
250,000 
220,668 
- 58,500 
15,281 58,500 
- 32,576,131 
186,137 32,496,98513 
'Includes $117,542 for new work for previous project. Excludes 
$359,202 contributed funds. 
2Includes $681,805 for new work for previous projects. 
3Includes $100,857 for maintenance for previous projects. 
4Includes $25,000 appropriated and $29,347 expended in FY 1986 
for condition surveys. 
5Excludes $152,223 contributed funds. In addition, $420,464 in 
other contributed funds have been expended for work under Government 
contract paid for by the Ottertail Power Company. 
6Excludes $93,099 contributed funds. 
7Excludes $56,220 contributed funds. 
sExcludes $208,000 contributed funds. 
9Excludes $130,300 contributed funds. 
10Excludes $30,020 contributed funds. 
"Includes cost of the Wahpeton-Breckenridge unit, $11,239, 
which is classed as "inactive" and the units on which authorization 
has expired: Maple River, $1,241; Moorhead, $27,700; Sheyenne, 
$37,956. In addition, $203,874 special deposit funds and $146,160 in 
other contributed funds have been expended for work under Government 
contract paid for by local interests. 
12Includes $1,802,866 for new work for previous project. 
13Excludes $589,316 contributed funds. In addition, $717,809 in 
other contributed funds have been expended for work under Government 
contract paid for by local interests. 
27-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 27-B AUTHORIZING LEGISLATION 
See 
Sec. Date of 
in Authorizing 
Text Act Project and Work Authorized Documents 
MINNESOTA RIVER, MN 
1. July 13, 1892 Open-channel improvement from mouth to Shakopee to obtain a Annual Report 1891. 
channel of 4-foot depth to accommodate vessels with 3-foot draft. p. 2209 
July 3, 1958 Dredging to provide channel of 9-foot depth from mouth to mile 14.7 S. Doc. 144. 84th Cong., 
2d sess.' 
RESERVOIRS AT HEADWATERS OF MISSISSIPPI 
RIVER, MN 
3. Mar. 3, 1899 Reconstruct 4 of the 5 original dams and surveys to determine extent 
of lands overflowed by reservoirs. 
Mar. 2, 1907 Reconstruct Sandy Lake Dam and construct Gull Lake Reservoir. 
June 25, 1910 Construct an equalizing canal between Winnibigoshish and Leech H. Doc. 363, 61st Cong., 
Lake Reservoirs (no work was done and this part of the project 2d sess. 
abandoned in Act of Mar. 4, 1915.) 
July 27, 1916 Abandonment of ditches connecting Long Lake, Round Lake, and H. Doc. 413, 64th Cong., 
Gull Lake. 1st sess. 1 
June 26, 19342 Operation and maintenance provided for with funds from War 
Department appropriations for rivers and harbors. 
ST. CROIX RIVER, MN AND WI 
4. June 18, 1878 Dredging, etc., for a 3-foot channel between mouth and H. Ex. Doc. 75, pt. 6, 43rd 
Taylors Falls. Cong., 2d Sess;4 Annual 
Report 1875, p. 372. 
June 3, 1896 Harbor and waterfront at Stillwater. 
Jan. 21, 1927 A 6-foot channel to Stillwater. H. Doc. 378, 69th Cong., 1st 
sess.4 
Aug. 30, 1935 The 9-foot channel from mouth to Stillwater. H. Doc. 184, 72nd Cong., 1st 
sess. 4 
May 17, 1950 Small-boat harbor at Hudson. H. Doc. 184, 81st Cong., 1st 
sess.4 
WARROAD HARBOR AND RIVER, MN 
5. Mar. 3, 1899 Dredging bar at mouth of Warroad River. Specified in Act. 
June 6, 1900 Entrance channel 300 feet wide and 7 feet deep. H. Doc. 92, 56th Cong., 
2d sess.5 
June 13, 19023 
Mar. 3, 1905 Enlarging turning basin H. Doc. 703, 61st Cong., 
2d sess.5 
June 25, 1910 
July 25, 1912 Deepening to 8 feet. 
'Contains latest published map. 
2Permanent Appropriations Repeal Act. 
3 Appropriation. 
4See H. Doc. 462, 71st Congress, 2d sess., for latest published 
map.
5Latest published map is opposite p. 1984 in Annual Report for 
1911. 
27-22

ST. PAUL MINNESOTA DISTRICT 
TABLE 27-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost To September 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Baudette Harbor, MN Completed 1961 $36,415 $57,768 
Black River, WI 1 1950 67,585 - 
Lake Traverse, MN and SD 3,4 1921 92 - 
Mississippi and Leech Rivers, MN Completed3 1929 277,615 40,251 
Mississippi River between Brainerd and 
Grand Rapids, MN 5 1925 47,794 3,891 
Pine Creek, Angle Inlet, MN Completed 1978 38,700 102,196 
Red Lake and Red Lake River, MN Completed3 1923 9,070 - 
Red River of the North, MN and ND 3,6 1921 293,344 76,209 
Wisconsin River, WI 2,3 1888 - 
Zippel Bay Harbor, MN Inactive5 1928 27,941 11,139 
1Existing channel adequate for commerce (see table 27-G for 
deauthorized portion of project). 
2Originally included in project 'Fox and Wisconsin Rivers, WI'. 
Abandonment of improvement of Wisconsin River by channel contraction 
works recommended in 1886 and 1887 (H. Doc. 65, 49th Cong., 2d 
sess.). Expenditures included under 'Fox and Wisconsin Rivers, WI'. 
No breakdown available. 
3No commerce reported. 
4Abandonment recommended in 1915 (H. Doc. 439, 64th Cong., 
1st sess.) and June 24, 1926 (H. Doc. 467, 69th Cong., 1st sess.). 
5Abandonment recommended June 24, 1926 (H. Doc. 467, E3th 
Cong., 1st sess.). 
6Abandonment recommended in 1915 (H. Doc. 1666, 63d Cong., 
3d sess.). 
27-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 27-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To September 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Bonnes Coulee, Velva, ND5 Completed 1985 58,500 - 
Burlington Dam, Souris River, ND Deferred 1983 5,568,5001 - 
Dry Run, IA Completed 1966 1,790,7592 - 
Elk River, MN Completed 1970 259,7003 - 
Grafton, ND Active4 1983 - - 
Guttenberg, IA Completed 1974 2,361,915 - 
Irving Township, Jackson County, WI5 Completed 1984 189,600 - 
LaCrosse, WI Active6 1983 - - 
Lost River, MN Completed 1967 517,519 - 
Lower Branch Rush River, ND8 Completed 1974 1,000,0009 - 
Minneota, MN8 Completed 1963 161,545 - 
Minot, ND Completed 1983 21,479,50010 - 
Mississippi River near Aitkin, MN Completed 1957 1,675,835 - 
Pembina River, ND Active4 1983 - - 
Pembina River Lake, ND Inactive" 1950 50,000 - 
Red Lake River at Huot, MN5 Completed 1984 64,500 - 
Red Lake River at Red Lake Falls, MN5 Completed 1984 131,000 - 
Red River of the North at Breckenridge, MN5 Completed - 27,500 - 
Red River of the North at Oslo, MN8 Completed 1984 1,960,200 - 
Red River of the North at Pembina, ND8 Completed 1979 2,000,000 - 
Redwood River below Marshall, MN8 Completed 1960 202,400 - 
Rushford, MN Completed 1980 3,192,333 - 
Shepard Road, Mississippi River, St. Paul, MN Completed 1985 250,00012 - 
St. Paul and South St. Paul, MN Completed 1974 8,476,01213 - 
Tongue River Lake, ND Inactive" 1950 23,695 - 
Upper Iowa River, IA Completed 1964 888,445 - 
Velva, ND8 Completed 1970 334,628 - 
Vermillion River, Hastings, MN8 Completed 1980 999,900 - 
Veteran's Memorial Levee, Mississippi River, Completed 1985 182,000 - 
Hastings, MN5 
Warroad River and Bull Dog Creek, MN Inactive 14 1974 182,000 - 
Wild Rice River-South Branch and Felton Completed 1985 4,534,700 - 
Ditch, MN 
Zumbro River, MN Completed 1975 1,284,100 - 
1Advance engineering and design costs only. Project deferred 
with authorization of Lake Darling project. Additional authorization 
required for implementation of recommended plan. The Senate Report 
97-256 states that the Corps is to take no further action to construct 
Burlington Dam until directed to do so by Congress. 
2Excludes $42,766 contributed funds. 
3In addition $87,878 was expended from Public Law 99 funds in 
the spring of 1969 for emergency protection and incorporation into the 
permanent project. 
4Preconstruction planning has not started. Phase I completed 
under General Investigations. 
5Project authorized by Chief of Engineers under small project 
authority, Section 14, Flood Control Act of 1946, as amended. 
6 Preconstruction planning has not started. 
7Excludes $46,034 for the Ruffy Brook unit for which authorization 
expired in April 1966 (see table 27-G). Excludes $246,911 contributed 
funds. 
sProject authorized by Chief of Engineers under small project 
authority, Section 205, 1948 Flood Control Act, as amended. 
9Excludes $35,000 contributed funds. 
1�Excludes $4,167 contributed funds. 
1'Further work deferred pending review of project document 
(inactive). 
12Excludes $62,620 contributed funds. 
13Excludes $545,637 contributed funds for new work and $38,000 
expended by South St. Paul for work in lieu of required cash contribution. 
Excludes an additional $206,629 expended for work done at 
request of local interests. 
14 Preconstruction planning suspended. Local interests requested 
the project be reclassified to inactive due to a limitation of 
their funding capability. The project was classified inactive on 
April 5, 1974. 
27-24

TABLE 27-G 
ST. PAUL MINNESOTA DISTRICT 
DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Black River, WI 1 1950 Aug. 5, 1977 - - 
Black River Lake, WI 1950 Aug. 5, 1977 - - 
Maple River, ND2 1981 Oct. 6, 1961 $1,241 - 
Moorhead, MN2 1981 Oct. 30, 1961 27,700 - 
Ruffy Brook, MN 1967 Apr. 1966 46,034 - 
Sheyenne River, ND2 1981 Dec. 31, 1970 37,956 - 
Warroad Harbor and River, MN3 1981 Aug. 5, 1977 - - 
1Portion of project for removal of obstructions at various points 
outside the dredged area to clear channel to full project width (see 
table 27-C for costs for completed portion of project). 
2Part of Red River of the North Drainage Basin (see Section 27 in 
text and table 27-J for costs for active units of the project). 
3 Portion of dredging of entrance channel and turning basin to 
complete project width and depth (see table 27-A for costs for completed 
portion of project). 
27-25

TABLE 27-H RESERVOIRS AT HEADWATERS OF 
MISSISSIPPI RIVER 
(See Section 3 of Text) 
Outlet Watershed Area (square miles) Capacity Previous Projects Existing Projects 
at 
Minimum Above Watershed Maximum 
Stages St. Paul (square Original Stage Corn- Com- Total 
Reservoir (feet)' River (miles) miles) Lake Reservoir (acre-feet) pleted Cost pleted Cost Cost 
Winnibigoshish 6 Mississippi 408 1,442 117 179.4 967,930 1884 $214,000 1900 $173,470 $387,470 
Leech Lake 0 Leech 410 1,163 173 250.9 743,320 1884 171,805 1902 84,380 256,185 
Pokegama 6 Mississippi 344 6602 24 35.0 120,750 1884 85,000 1904 126,030 211,030 
Sandy Lake 7 Sandy 267 421 8 16.6 72,500 1895 114,000 1909 117,020 231,020 
Pine River 9 Pine 199 562 18 23.7 177,520 1886 97,000 1907 133,320 230,320 
Gull Lake 5 Gull 168 287 20 20.5 70,820 - - 1913 86,826 86,826 
Surveys and flowage rights - - - - 160,939 160,939 
Recreational facilities - - - - 2,834,838 2,834,838 
Total new work - - 681,805 - 3,716,823 4,398,628 
Total operating and care - - 100,857 - 22,370,841 22,471,698 
Permanent indefinite 
appropriation for operation 
and care, Feb. 1, 1895 to end of 
fiscal year 1936 - - - - 967,197 967,197 
Rehabilitation - - - - 425,000 425,000 
Total 2,152,840 - $782,662 - $27,479,861 $28,262,523 
1Lower operating limits by regulations approved February 4, 1936, as modified December 29, 1944. 
2Exclusive of area controlled by Winnibigoshish and Leech Lake Dams. 
LTj 
C
y
O
ITj 
0c 
tTj 
0
tTj z
z
Cw I) 
x
i) 
00

ST. PAUL MINNESOTA DISTRICT 
TABLE 27-I RED RIVER OF THE NORTH DRAINAGE BASIN: 
ACTIVE UNITS IN COMPREHENSIVE BASIN PLAN 
(See Section 30 of Text) 
Total 
Cost to Estimated 
Name of Unit State Type September 30, 1986 Federal Cost 
Orwell Reservoir (Otter Tail River) Minnesota Reservoir $1,916,753 $1,916,7001 
Wild Rice and Marsh Rivers Minnesota Channel improvement 405,056 405,100 
Rush River North Dakota Channel improvement 287,686 287,000 
Sand Hill River Minnesota Channel improvement 548,778 548,800 
Mustinka River Minnesota Channel improvement 440,788 440,800 
Otter Tail River Minnesota Channel improvement 174,768 174,800 
Red River at Grand Forks North Dakota Levees and floodwall 948,895 948,900 
Red River at East Grand Forks Minnesota Levees, floodwall, 
pumping plants 1,511,637 22,000,000 
Red River at Fargo North Dakota Channel improvement, 
levees 1,639,924 1,639,9002 
Total cost to date 7,874,2853 
Total estimated cost 28,362,0004 
'Includes $181,713 for lands and $25,045 for recreation facilities, revised in 1955, was estimated to be $996,000. The Flood Control Act 
2Includes $67,900 for lands. approved December 31, 1970 (H. Doc. 330-91-2) provided for deletion 
3Costs of $11,239 for the Wahpeton-Breckenridge inactive unit of the Sheyenne River unit, and authorization of the Maple River and 
not included. Authorization of the Sheyenne River, Moorhead, and Moorhead units expired at the end of the 5-year period within which 
Maple River units has expired. Cost of these units also not included local interests were required to furnish assurances of local cooperatotal 
$66,897. tion. Authorization of these units, not included, expired on the dates 
4The Wahpeton-Breckenridge unit of the project is classed as indicated in table 27-G. 
'inactive' and is excluded from the estimate. The cost of this unit, last 
TABLE 27-J INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 43 of Text) 
Project Date Inspected 
Arcadia, WI.................................. .......................... September 1986 
Black River (North Bend), WI ............................................ September 1986 
Breckenridge, MN......................................................... September 1986 
Cochrane, WI ........................................................... September 1986 
Fargo, ND ......................... ....................... August 1986 
Grand Forks, ND ......................................................... August 1986 
Huot, MN............................. .................................. August 1986 
Irving Township, WI ...................................................... September 1986 
Mahnomen, MN .......................................................... August 1986 
Minot, ND ............................ ................................. September 1986 
Oslo, M N ................................................... ............ August 1986 
Pembina, ND......................... .......................... ....... August 1986 
Red Lake Falls, MN ....................................................... August 1986 
St. Paul, M N ............................................... ............. August 1986 
Velva, ND .................................... ......................... September 1986 
27-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 27-K FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, Public Law 858, 
80th Congress, as amended (preauthorization) 
Study Identification Fiscal Year Costs 
Afton, MN ..................... .............................................. 
Beaver Lake, Stearns County, MN ............................................... 
Emerson, Manitoba-Noyes, MN ................................................... 
English Coulee, Grand Forks, ND ............................................... 
Fridley, MN .................................................................. 
Gilmore Creek, Winona, MN ............ ........................................ 
Jordan, MN ................................................................. 
Lake Carnelian, Stearns County, MN............................................. 
Lake Charlotte, MN ............................................................. 
Minnesota River, Henderson, MN. .................................................. 
Mississippi River, Cochrane, WI ........................................ .......... 
Neche, ND .................................................................. 
Root River, Hokah, MN ................................................... 
Sanders Creek, Boscobel, WI ..................................................... 
Snake River, Alvarado, MN........ ............................................. 
Trempealeau River, Arcadia, WI .................................................. 
Trempealeau River, Blair, WI ...................................................... 
Wild Rice River, Ada, MN ...................................... ................... 
$7,500 
7,500 
6,351 
66,777 
51,778 
128,790 
40,564 
7,500 
16,488 
4,568 
7,500 
26,768 
646 
58,123 
65,941 
102,617 
7,500 
37,324 
Emergency bank protection (Section 14 of 
the 1946 Flood Control Act, Public Law 526, 79th Congress) 
Project and Location Fiscal Year Costs 
Lac qui Parle River, MN $7,500 
Snagging and clearing navigable streams 
and tributaries in the interest of flood control 
(Section 208, 1954 Flood Control Act, Public Law 780, 83rd Congress) 
Project and Location Fiscal Year Costs 
Chippewa River, Big Bend-Hagen, WI $7,500 
Emergency flood control activities - 
repair, flood fighting, and rescue work 
(Public Law 99, 84th Cong., and antecedent legislation) 
Project Fiscal Year Costs 
Disaster preparedness $251,400 
Rehabilitation 94,407 
Total emergency flood control activities 345,807 
27-28

ROCK ISLAND, IL, DISTRICT* 
This district comprises most of the northern half of 
Illinois, portions of southern Wisconsin, southern and 
southwestern Minnesota, eastern and central Iowa, and 
northeastern Missouri, embraced in drainage basin of 
Mississippi River and its eastern and western tributaries 
between mile 300 (above mouth of Ohio River) and 614, 
and of its eastern tributaries only, between Hamburg 
Bay, at mile 261 and 300. This district also includes the 
Illinois Waterway above mile 80 with its tributaries and 
drainage basins. The section of the Mississippi River between 
river miles 300 and 614 is included in the report on 
Mississippi River between Missouri River and Minneapolis, 
MN. 
IMPROVEMENTS 
Navigation Page 
1. Illinois and Mississippi Canal, IL ........... 28-2 
2. Illinois Waterway, IL and IN .............. 28-2 
3. Mill Creek and South Slough at Milan, IL .... 28-3 
4. Mississippi River between Missouri River 
and Minneapolis, MN ..................... 28-3 
5. Upper Mississippi River Environmental 
Management Program, IL, IA, MN, MO, WI . 28-3 
6. Other. Authorized Navigation Projects ....... 28-3 
Flood Control 
7. Ames Dam and Reservoir, Skunk River, IA .. 28-3 
8. Bettendorf, IA ........................... 28-4 
9. Coralville Lake, IA ....................... 28-4 
10. Davenport, IA ........................... 28-4 
10. Des Moines Recreational River and 
Greenbelt, IA ........................... 28-4 
12. Farm Creek, IL ......................... 28-5 
13. Milan, IL ............................... 28-5 
14. Red Rock Dam and Lake Red Rock, IA ...... 28-5 
15. Rockford, IL ............................ 28-5 
16. Saylorville Lake, IA ...................... 28-5 
17. W aterloo, IA ............................ 28-6 
18. Inspection of Completed Flood 
Control Projects ......................... 28-6 
19. Other Authorized Flood Control Projects ..... 28-6 
20. Flood Control Work Under Special 
Authorization ........................... 28-6 
General Investigations Page 
21. Surveys ................................. 28-6 
22. Collection and Study of Basic Data ......... 28-6 
23. Continuation of Planning and Engineering ... 28-6 
24. Advance Engineering and Design ........... 28-7 
Tables 
Table 28-A Cost and Financial Statement ....... 28-8 
Table 28-B Authorizing Legislation ........... 28-10 
Table 28-C Other Authorized Navigation 
Projects ........................ 28-13 
Table 28-D Not Applicable 
Table 28-E Other Authorized Flood 
Control Projects ................. 28-14 
Table 28-F Not Applicable 
Table 28-G Deauthorized Projects ............ 28-16 
Table 28-H Inspection of Completed Flood 
Control Projects ................. 28-16 
Table 28-I Flood Control Work Under Special 
Authorization .................. 28-18 
Table 28-J Illinois Waterway: Existing 
Locks and Dams ................. 28-20 
Table 28-K Illinois Waterway: Lock and Dam 
Construction, Foundations, Cost .... 28-20 
Table 28-L Illinois Waterway: Additional 
Features Entering into Cost ........ 28-21 
Table 28-M Illinois Waterway: Existing 
Project ........................ 28-22 
Table 28-N Illinois Waterway: Total Cost of 
Existing Project .................. 28-22 
28-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. ILLINOIS AND MISSISSIPPI 
CANAL, IL 
Location. This canal extends for 75 miles from the 
Illinois River near LaSalle, IL, to the Mississippi River at 
Rock Island, IL. A feeder canal, 29 miles in length, extends 
from the summit level of the canal to the Rock River at 
Rock Falls, IL. 
Existing project. See pages 1306-1308 of Annual Report 
for 1962 for details regarding project. The canal was constructed 
in the period 1892-1918. The canal has not been 
operated for navigation since June 1951 in accordance with 
Corps policy to discontinue operation of waterways affording 
little or no benefit to navigation. The River and Harbor 
Act of 1958 authorized the appropriation of $2,000,000 for 
the purpose of placing the canal in proper condition for 
public recreational use and to convey and transfer the canal 
to the State of Illinois as part of the State park system. The 
repair and modification program was initiated in 1961, and 
a number of canal features have been repaired or modified. 
In connection with this program, fee title to 1,062 acres 
and recreational flowage easements over 309 acres of land 
in Rock River at Rock Falls, formerly under navigation 
flowage easement, have been acquired. The State of Illinois 
accepted title to the canal as of August 1, 1970. The River 
and Harbor Act of 1970 authorized the additional appropriation 
of $6,528,000 to be expended for the repair, modification, 
and maintenance of bridges, title transfer, modification 
or rehabilitation of hydraulic structures, fencing, clearing 
auxiliary ditches, and for the repair and modification 
of other canal property appurtenances. The Water 
Resources Development Act of 1986 authorized an additional 
appropriation of $8,472,000 to accomplish the work 
described in the 1970 River and Harbor Act. 
Local cooperation. None required. 
Operations during fiscal year. During FY 1982, a 
judgment of the Court of Appeals, 7th Circuit, directed that 
a fund of $2,812,658 plus interest at 12 percent per annum 
computed from February 23, 1979, be established by the 
United States in the District Court from which payments 
are to be made to plaintiffs for required repairs to Illinois 
and Mississippi Canal bridges. Actual payment for the 
judgment award was $3,722,572, which included interest 
at 12 percent through November 4, 1981. Engineering and 
design work in connection with this matter cost $359,615 
during FY 1986. 
2. ILLINOIS WATERWAY, IL AND IN 
Location. Illinois River (entirely within State of Illinois), 
formed by confluence of Kankakee and Des Plaines River, 
flows southwesterly and enters Mississippi at Grafton, IL, 
about 38 miles above St. Louis. Illinois Waterway comprises 
Illinois River from its mouth to confluence of 
Kankakee and Des Plaines Rivers (273 miles); Des Plaines 
River to Lockport (18.1 miles) and Chicago Sanitary and 
Ship Canal and South Branch of Chicago River to Lake 
Street, Chicago (34.5 miles). Also from a point 12.4 miles 
above Lockport, IL, waterway comprises Calumet-Sag 
Channel and Little Calumet and Calumet Rivers to turning 
basin 5, near-entrance to Lake Calumet (23.8 miles); 
and Grand Calumet River from junction to 141st Street, 
deep (lake) draft navigation (9 miles) and to Clark Street, 
Gary, IN (4.2 miles). 
Previous projects. For details, see page 1945 of Annual 
Report for 1915 and page 1172 of Annual Report for 1932. 
Existing project. See table 28-K and page 1255 of Annual 
Report for 1963. Cost of new work is $124,041,436 and includes 
$445,000 for Recreation Facilities under Code 711. 
Calumet-Sag Modification, Part II, placed in the inactive 
category in June 1973, cost of $132,000,000 (July 1972) 
Federal and $16,300,000 (July 1972) non-Federal; Calumet- 
Sag Modification, Part III, placed in the deferred-for-restudy 
category in March 1972, cost of $33,000,000 (July 1971) 
Federal and $20,700,000 (July 1971) non-Federal; widen 
Pekin Bend, a portion of work authorized by River and 
Harbor Act of 1935, placed in the inactive category, cost of 
$1,360,700 (July 1972) Federal; and widen Marseilles Canal 
to 300 feet, a portion of work authorized by River and 
Harbor Act of 1935, placed in the deferred category, cost 
of $1,859,300 (July 1972) Federal, are all excluded from present 
cost estimate. See Table 28-B for authorizing legislation. 
(See also tables 28-J through 28-N on existing locks and 
dams; lock and dam construction, foundations, cost; additional 
features entering into cost of project; existing project, 
and total cost of existing project.) 
Local cooperation. Complied with for completed 
modifications and Part I of Calumet-Sag Modification. 
All pools above Alton Pool: 
Maintenance: Channel dredging by the Dredge 
DUBUQUE was performed at various locations in 
LaGrange pool at a cost of $613,700 with a total of 115,534 
cubic yards of material being removed. Dredging inspection 
and approval were completed at a cost of $42,300. 
Strike removal and snagging and clearing was accomplished 
in various locations by hired labor at a cost of $504,500. 
Maintenance of the Lucas-Berg Disposal Facility cost 
$6,300, and contractor earned $116,700 on a construction 
mitigation contract at this facility. Structural repairs to locks 
and dams were performed by hired labor at a cost of 
$1,640,300. Bank stabilization of the Chicago and ship canal 
was performed by hired labor at a cost of $38,300. Contractor 
earned $100,000 for replacing valve operating 
machinery at O'Brien Lock. Contractor earned $24,700 for 
modification of miter gate machinery at Marseilles Lock. 
Contractor earned $126,000 for construction of a combined 
maintenance building and central control station at 
Marseilles Lock and Dam. Buildings, grounds, and utility 
maintenance at the locks and dams and Illinois Waterway 
Project Office at Peoria totaled $9,600. Permanent operating 
equipment costs were $35,100. Engineering and design 
work, including preparation of design memorandums cost 
$352,900, and supervision and administration for the 
maintenance features totaled $92,500. Total maintenance 
costs were $3,702,900. Net credits to the project were 
$11,700, primarily as a result of collection of damages from 
towboat companies to lock and dam structures. 
Operation and Care: Operation of the locks and dams 
and routine maintenance and minor repairs thereto were 
made at a cost of $5,118,400. Illinois Waterway Project 
Office at Peoria was continued at a cost of $431,900. Real 
estate management services were provided at a cost of 
$62,300. Visitor's Center at Starved Rock Lock and Dam 
was operated at a cost of $200,600 with contract law en- 
28-2

ROCK ISLAND, IL, DISTRICT 
forcement provided at a cost of $3,700. Surveys, studies, 
and other inspections were performed at a cost of 
$401,100; natural resource activities cost $20,600; and 
water control management costs were $656,200; and the 
amount of $4,700 was expended on Master Plans. Supervision 
and administration for the operation features totaled 
$210,600. Total operation costs were $7,110,100. 
Total operation and maintenance costs were $10,797,875 
for all pools above Alton Pool. 
Rehabilitation: Rehabilitation work at La Grange, 
Peoria, Marseilles, Brandon Road, Starved Rock, and 
Lockport Lock Locks and Dams was in progress. Costs at 
La Grange were $782,873; at Brandon Road, $4,720,696; 
at Starved Rock, $14,559; at Lockport, $7,244,703; and at 
Marseilles, $3,203,246; and at Peoria, $562,557; for a total 
of $16,528,634. 
Alton Pool Operation: Costs by hired labor for condition 
and operation studies were $116,256; water control 
management $65,375; and supervision and administration 
$31,147. 
Alton Pool Maintenance: Costs for the year were 
$317,984 for dredging and $13,495 for supervision and 
administration. 
Total cost for work in Alton Pool was $567,785. 
Total operation and maintenance costs for all pools above 
Alton Pool were $10,797,875; Alton Pool operation and 
maintenance costs were $567,785; for a total operation and 
maintenance cost of $11,369,085. 
3. MILL CREEK AND SOUTH SLOUGH 
AT MILAN, IL 
Location. Mill Creek and South Slough are small 
streams, tributary to the Rock River, at Milan, Rock Island 
County, IL. 
Existing project. The existing project provided for flood 
protection at the village of Milan necessitated by the construction 
of the Illinois and Mississippi Canal. The project 
consisted of diversion of Mill Creek into South Slough, 
floodgates in the walls of the Illinois and Mississippi Canal 
to carry Mill Creek flood waters across the canal right-ofway 
into Rock River, levees, and other works for flood protection. 
The project was constructed in 1931-1932. In 
1962-1963, $73,366 was expended from Illinois and 
Mississippi Canal maintenance funds for restoration of the 
Mill Creek outlet into Rock River. See Table 28-B for 
authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Minor channel maintenance 
was performed at a cost of $270. 
4. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND 
MINNEAPOLIS, MN 
For report on this improvement, see chapter on 
"Mississippi River between Missouri River and Minneapolis, 
MN." 
5. UPPER MISSISSIPPI RIVER SYSTEM 
ENVIRONMENTAL MANAGEMENT 
PROGRAM, IL, IA, MN, MO, WI 
Location. The project is located in the Mississippi River 
Basin encompassing a 5-State area including IL, IA, MN, 
MO, and WI. 
Existing project. The project represents the initial implementation 
of the master plan prepared by the Upper 
Mississippi River Basin Association (report dated January 
1982). Project features include long-term resources 
monitoring, habitat rehabilitation and enhancement, 
recreation improvement and studies, traffic monitoring, 
and computerized inventory and analysis. The project will 
be initiated in FY 1986 utilizing funds provided by the 
FY 1985 Supplemental Appropriation Act. The execution 
of the project will be closely coordinated with the Upper 
Mississippi River Basin Association, other Federal agencies, 
affected States, and local communities. See Table 28-B for 
authorization legislation. 
Local cooperation. Local cooperation agreements will 
be sought as required. 
Operations during fiscal year. Costs during the year 
totaled $442,751. Funds were used to initiate engineering 
and design on ten habitat rehabilitation and enhancement 
projects and four recreation projects. Construction was 
initiated on one habitat project. Funds were also used to 
work on the long term resources monitoring program, 
recreation economics studies, traffic monitoring program, 
and the general plan. 
6. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 28-C. 
Flood Control 
7. AMES DAM AND RESERVOIR, 
SKUNK RIVER, IA 
Location. The Ames Lake project is located on the Skunk 
River in Story County, IA, about 5 miles upstream from 
the city of Ames, IA. 
Existing project. Major project features would include 
a dam constructed of compacted impervious earth with 
gated outlet works and spillway; a subimpoundment forming 
a 30-acre lake by blocking a ravine with embankment 
for access road crossing the dam; relocations consisting 
of roads, telephone and power lines; and remedial protection 
for Story City by levee and street raises. The conservation 
pool would have a surface area of 2,100 acres and 
the full flood control pool would have a surface area of 
5,000 acres. The project was authorized to store water for 
flood control, water quality control, recreation, and fish and 
wildlife benefits. Current study efforts concluded that a 
smaller scaled down project was the only feasible alternative. 
The scaled down project would have a surface area 
of 1,850 acres and the full flood control pool would have 
a surface area of 3,620 acres. See Table 28-B for authorizing 
legislation. 
Local cooperation. By letter dated October 26, 1973, 
the Governor of IA advised "There is general agreement 
28-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
that the project provides definite flood control benefits to 
the downstream landowner. However, the costs associated 
with it and the values to be foregone as a result of the 
project outweigh the benefits. Therefore, at this time, the 
State's position must be that of general opposition to the 
project." Due to the State's position in regard to the project, 
it was reclassified from the "active" to the "inactive" 
category on June 20, 1974. Recently, there has been 
renewed congressional and local interest in this project. By 
letter dated March 6, 1984, the city of Ames, IA, provided 
a copy of a resolution that the City Council adopted 
February 28, 1984, requesting reactivitation of the project. 
The project was approved for reactivation on July 2, 1984. 
By letters dated August 27, 1986 and September 9, 1986, 
the Iowa Department of Natural Resources and City of 
Ames, Iowa advised that they did not support the scaled 
down project. 
Operations during fiscal year. New work: Work was 
continued on a General Reevaluation Report (GRR). Costs 
totaled $172,865. 
8. BETTENDORF, IA 
Location. The city of Bettendorf is located on the right 
bank of the Mississippi River 485.7 miles above the mouth 
of the Ohio River, in Scott County, IA. 
Existing project. Local flood protection from the 
Mississippi River to be provided by construction of 3 miles 
of earth levee, railroad raises, closure structures, and street 
raises and ramps. Construction was started in July 1982. 
Estimated project cost is $15,906,000 including $1,510,000 
non-Federal cost for lands and relocations. See Table-28B 
for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
continued. The project is 94 percent completed. Costs 
were $3,853,355. 
9. CORALVILLE LAKE, IA 
Location. Coralville Lake is formed by the Coralville 
Dam on the Iowa River, several miles upstream from Iowa 
City, Johnson County, IA, about 83 miles above the confluence 
of the Iowa River with the Mississippi River. 
Existing project. See page 28-4, Annual Report for 1981, 
for project details. Construction began in July 1949 and the 
project has been in operation since February 1958. About 
24,406 acres of land were acquired in fee, and flowage 
easements obtained for 9,494 acres. The project was 
modified to provide for construction of a highway bridge 
crossing the lake at the Mehaffey site, which was begun 
in June 1964 and completed in October 1966. See Table 
28-B for authorizing legislation. 
Local cooperation. None required, except in connection 
with the Mehaffey Bridge, which has been fully complied 
with. 
Operations during fiscal year. New work: Additional 
land acquisition to provide for the present plan of reservoir 
operation performed at a cost of $507,889. Maintenance: 
Routine maintenance activities continued at a cost 
of $2,045,865. Expenditures from return of recreation use 
fees: $70,000. 
10. DAVENPORT, IA 
Location. The city of Davenport is located on the right 
bank of the Mississippi River, 482.4 miles above the mouth 
of the Ohio River, in Scott County, IA. 
Existing project. Local protection to the city from floods 
on the Mississippi River to be provided by construction of 
levees, floodwall, interior drainage facilities and pump 
plants, closure structures, and recreational facilities. The 
project also provides for the enhancement and preservation 
of Nahant Marsh at the downstream edge of the city 
as a wetland area with important contribution to environmental 
quality. Estimated project cost is $40,900,000 
including $11,700,000 non-federal costs. See Table 28-B for 
authorizing legislation. 
Local cooperation. The city has withdrawn support for 
the project because of high costs and public opposition. 
Operations during fiscal year. New work: None. 
11. DES MOINES RECREATIONAL 
RIVER AND GREENBELT, IA 
Location. The greenbelt area is located along both banks 
of the Des Moines River in central IA and extends from 
a point at which relocated U.S. Highway 92 crosses the 
Des Moines River near Harvey, upstream approximately 
169 river miles to U.S. Highway 20 at Fort Dodge, IA. It 
includes the Corps' operated Lake Red Rock and Saylorville 
Lake projects. 
Existing project. The project will include, but not be 
limited to: (1) the construction, operation, and maintenance 
of recreational facilities and streambank stabilization 
structures; (2) the operation and maintenance of all 
structures constructed before the date of authorization of 
this project (other than any such structure operated and 
maintained by any person under a permit or agreement 
with the Secretary); (3) such tree plantings, trails, vegetation, 
and wildlife protection and development and other 
activities as will enhance the natural environment for 
recreational purposes; and (4) the prohibition or limitation 
by the Secretary of the killing, wounding, or capturing at 
any time of any wild bird or animal in such areas as may 
be directed by the Secretary. In carrying out the project, 
the Secretary may acquire by purchase, donation, exchange, 
or otherwise, land and interests therein, as the Secretary 
determines are necessary to carry out such project. 
The authorization requires that an Advisory Committee 
will be established for consultation with the Department 
of the Army consisting of three Corps of Engineers appointees, 
one person from the city of Des Moines, and one 
from each other incorporated municipality within the 
greenbelt, two from each of eight counties in the greenbelt, 
and five from the State of Iowa. See Table 28-B for authorizing 
legislation. 
Local cooperation. There is strong local support for the 
project by recreational and environmental interests. These 
interests were instrumental in developing and supporting 
the authorization for the project. However, since cost-sharing 
requirements have not been developed for elements of 
28-4

ROCK ISLAND, IL, DISTRICT 
the project or coordinated with respective sponsors, it is 
unknown how many of the potential 20 or more sponsors 
are willing or able to participate in the project under terms 
and conditions acceptable to the Secretary of the Army. 
Operations during fiscal year. A plan for engineering 
and design was completed and General Design memorandum 
studies were initiated. Costs incurred were $163,997. 
12. FARM CREEK, IL 
Location. Farm Creek watershed in Tazewell County, 
IL, is 60 square miles in extent. Stream empties into Illinois 
Waterway at mile 162 above mouth. 
Existing project. See page 28-5, Annual Report for 1983 
for description of project. See Table 28-B for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance: Routine 
maintenance activities were continued at a cost of $79,810. 
13. MILAN, IL 
Location. The village of Milan is located on the south 
bank of the Rock River several miles upstream from the 
confluence of that stream with the Mississippi River at mile 
479.1 above the mouth of the Ohio River, in Rock Island 
County, IL. 
Existing project. Local protection against direct flooding 
from Rock River and Mill Creek and against backwater 
flooding from the Mississippi River to be provided the community 
by construction of levees, floodwalls, closure structure, 
bridges, pumping stations, drainage facilities, and 
street ramps. Construction was initiated in March 1981. 
The estimated project cost is $17,940,000, including 
$3,440,000 non-Federal cost for land and relocations. See 
Table 28-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
of the project continued at a cost of $566,240. The 
principal work items were levee construction and utilities 
relocations. The project is about 92 percent completed. 
14. RED ROCK DAM AND LAKE RED 
ROCK, IA 
Location. The site of this project is on the Des Moines 
River, chiefly in Marion County, but extending into Jasper, 
Warren, and Polk Counties. The dam is 142.9 miles above 
the mouth of the Des Moines River, which empties into 
the Mississippi River at mile 361.4 above the mouth of the 
Ohio River. The city of Des Moines lies northwesterly from 
the site, about 60 miles upstream. 
Existing project. See page 28-6, Annual Report for 1981 
for description of the project. Construction began in May 
1960, and the dam was placed in beneficial use for storage 
of flood water in January 1969. Land acquired for the 
project consisted of 47,611 acres in fee and 29,057 acres 
in flowage easement. See Table 28-B for authorizing legislation. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Routine 
maintenance activities were continued at a cost of 
$2,638,830. Expenditures from the return of recreation use 
fees were $70,000. 
15. ROCKFORD, IL 
Location. The city of Rockford is located along both 
banks of the Rock River, in Winnebago County, IL. Kent 
Creek is a small stream, tributary to the Rock River, which 
flows through the right-bank portion of the city. 
Existing project. The project provides flood protection 
for the right-bank portion of the city from floods on Kent 
Creek. It consists of a rolled earth dam with outlet works 
and spillway on North Branch Kent Creek in Page Park; 
12,000 feet of channel cleanout and straightening on North 
Branch Kent Creek; raise of Levings Lake Dam on South 
Branch Kent Creek and construction of spillway and diversion 
channel; 10,800 feet of channel cleanout and straightening 
on South Branch Kent Creek; and relocations. Construction 
was initiated in October 1978. The estimated project 
cost is $16,610,000, including $6,440,000 for land and 
relocations. See Table 28-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
of the project was continued at a cost of $564,537. The 
principal work items were channel cleanout and straightening 
on North Branch Kent Creek and construction of the 
diversion channel on South Branch Kent Creek. The project 
is about 86 percent completed. 
16. SAYLORVILLE LAKE, IA 
Location. The project site is chiefly in Polk County, IA, 
but portions extend into Dallas and Boone Counties. The 
dam is about 213.7 miles above the mouth of the 
Des Moines River and about 5 miles upstream from the 
city of Des Moines, IA. 
Existing project. The dam is an earth embankment 
6,750 feet long at crest with a height of 120 feet. Outlet 
works are a single circular concrete conduit, 22 feet in diameter, 
located at the toe of the west bluff. Control structure 
is at upstream end of conduit and houses three gates. A 
stilling basin is provided to dissipate energy of discharge 
from outlet conduit. Spillway is in west bluff, weir 430 feet 
long. Water flowing over the spillway weir discharges into 
a paved chute and thence into an escavated earth channel 
to the Des Moines River. Top of spillway is about 31 feet 
below top of earth embankment section, and flow over weir 
is uncontrolled when water in reservoir reaches its crest. 
Watershed area above dam site is 5,823 square miles. With 
pool at spillway crest elevation, lake area is 16,700 acres 
and contains about 676,000 acre-feet of water at that height 
(602,000 for flood control and 74,000 for a conservation 
pool to maintain minimum flows at downstream points). 
Lake supplements capacity of downstream Lake Red Rock 
at river mile 142.9. The two lakes provide a high degree 
of flood protection to the lower Des Moines River Valley. 
Reaches along the Mississippi River downstream from the 
mouth of the Des Moines River are also benefited. 
A project modification plan to minimize the adverse environmental 
effects at Ledges State Park, located upstream 
from the dam, was authorized in 1976. The project modi- 
28-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
fication includes relocation of affected park facilities, acquisition 
of additional park land, and the development of 
a floodway corridor, with recreational facilities, from the 
dam downstream to Sixth Avenue in Des Moines. Improvements 
to Highway 415, the main access road to existing 
facilities on the east side of the reservoir, were added to 
the project by Congress in 1984. 
Construction began in June 1965, and the dam was placed 
in operation for the storage of flood water in April 1977. 
Remedial work in Big Creek Valley, consisting of a diversion 
dam and channel and a barrier dam, for the protection 
of the town of Polk City was completed in December 1974. 
The land acquisition program involved 26,526 acres acquired 
in fee, flowage easements for 1,925 acres. The 
estimated project cost is $128,216,000, including $2,770,000 
non-Federal costs from the State of Iowa and the City of 
Des Moines, Iowa toward recreational development. See 
Table 28-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: The principal 
work item was the construction of recreational facilities 
and improvements to Highway 415, and on engineering 
and design work for the downstream floodway corridor. 
New work costs were $3,631,688. Maintenance: Routine 
maintenance activities were continued at a cost of 
$3,032,005. Expenditures from return of recreation use fees 
were $70,000. The project is about 85 percent completed. 
17. WATERLOO, IA 
Location. The city of Waterloo is located along both 
banks of the Cedar River in Black Hawk County, IA. 
Existing project. The project provides local protection 
to the city of Waterloo from floods on the Cedar River, 
Black Hawk Creek, Virden Creek, and Blowers Creek. It 
consists of 15.4 miles of earth levee, 2 miles of floodwall, 
11,330 feet of channel improvement, an impounding dam 
on Virden Creek, and interior drainage facilities including 
8 pumping plants. Extensive urban renewal, undertaken 
by the city, has been coordinated with the flood control 
project. Construction was initiated in August 1972. The 
estimated project cost is $63,760,100, including $15,000,000 
non-Federal cost for land and relocations. See Table 28-B 
for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Construction 
of the project was continued at a cost of $42,652. The 
principal work items were continuation of construction of 
levees and floodwalls along the Cedar River. The project 
is 100 percent completed. 
18. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Federal flood control regulations (part 208 of title 33, 
Code of Federal Regulations) provide that the structures 
and facilities constructed by the United States for local flood 
protection shall be continuously maintained in such a 
manner and operated at such times and for such periods 
as may be necessary to obtain the maximum benefits. Costs 
during the period for inspections of projects turned over 
to local interests to ascertain compliance with Federal requirements 
were $165,784. (See Table 28-H for list of completed 
flood control projects inspected.) 
19. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 28-E. 
20. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control Activities, Section 205, Public Law 
84-685. See Table 28-I. 
Snagging and Clearing of Navigable Streams and 
Tributaries in Interest of Flood Control, Section 208, 
Public Law 83-780. See Table 28-I. 
Emergency Bank Protection (Section 14 of the 1946 
Flood Control Act, Public Law 526.) 
Emergency Flood Control Activities, Public Law 99, 
84th Congress. See Table 28-I. 
General Investigations 
21. SURVEYS 
Flood control studies in progress included the Mississippi 
River, Coon Rapids to Ohio River; the Illinois River from 
Henry to Naples, IL; Quincy Bay, IL; and the Vermilion 
River Basin, IL. Total cost of flood control studies was 
$414,611. Special investigations, FERC review, SCS coordination, 
and planning assistance to States efforts totaled 
$40,574. Total cost of surveys was $505,185. 
22. COLLECTION AND STUDY OF 
BASIC DATA 
Flood plain management services cost $183,851. Hydrologic 
studies, including general studies, sedimentation 
studies, streamflow studies, and rainfall studies cost $2,644. 
Total cost for collection and study of basic data was 
$186,495. 
23. CONTINUATION OF PLANNING 
AND ENGINEERING 
The Loves Park, IL, project, part of an authorized study 
of the Rock River in the vicinity of Rockford, IL, lies 
in Winnebago County, IL, on the northeast boundary of 
the city of Rockford, 17 miles south of the IL-WI State 
line. The project would provide local flood protection 
(100-year level) for the city of Loves Park, IL, against 
flooding of Loves Park Creek (formerly called the Large 
Unnamed Creek). Protection measures would consist 
of 17,350 feet of channel improvements, a 75,000 GPM 
pump plant, and ponding. Congress has appropriated 
funds for preconstruction planning and engineering studies 
at Loves Park. A General Reevaluation Study was initiated 
on October 17, 1984. FY 1986 cost for continuation of 
work on the General Reevaluation Report (GRR) was 
$303,507. 
The South Quincy, IL, project is located in the South 
Quincy Drainage and Levee District in Adams County, IL. 
The existing project protects 5,800 acres of agricultural, 
28-6

ROCK ISLAND, IL, DISTRICT 
commercial, industrial, and residential lands from floods 
up to a 50-year chance of occurrence. The proposed plan 
would raise the level of protection to a 500-year chance of 
occurrence. The levee is about 8.8 miles long and starts in 
the vicinity of Curtis Creek and Highway 57 on the north, 
runs along the south bank of Curtis Creek, along the east 
bank of the Mississippi River, and along the north bank 
of Mill Creek, and ends in the area of Mill Creek and Highway 
57. Fiscal 1986 work on the project was the completion 
of a General Design Memorandum (GDM) at a cost 
of $218,160. 
Total cost for continuation of planning and engineering 
was $521,666. 
24. ADVANCE ENGINEERING AND 
DESIGN 
The Hannibal, MO, project area is on the right bank of 
the Mississippi River at the city of Hannibal, MO, 309 miles 
above the mouth of the Ohio River. The project would provide 
flood protection to the business and industrial area 
of the city of Hannibal by the construction of a system of 
levees and floodwalls. The plan also included a pumping 
plant, closure structures for railroads and streets, alteration 
of the existing sewage system, and a tainter gate closure 
at the mouth of Bear Creek. Advance planning on the 
project was begun in 1962; however, in 1965 further work 
was discontinued because of lack of local support. Local 
interest revived in 1979, and the project was reclassified 
from "inactive" to the "active" category. A study has been 
undertaken to reformulate the project to meet existing 
needs of the project area and to reflect current Federal and 
State criteria for water resources projects. No action toward 
fulfillment of local cooperation requirements has been 
taken. Detailed studies for reformulation of the project and 
evaluation of alternatives were continued at a cost of 
$117,693. 
The Moline, IL, project is located on the left bank of the 
Mississippi River, 485.7 miles above the mouth of the Ohio 
River, in Rock Island County, IL. Local protection at Moline 
from Mississippi River floods to be provided by construction 
of 4 miles of earth levee and floodwall, closure structures, 
aesthetic and recreational development, and interior 
drainage facilities consisting of gravity outlets, storm sewer 
interceptors, and pumping plants. Construction has not yet 
been initiated due to gaps in Federal funding. Local interests 
will be requested to furnish assurances after a firm 
project plan is established. Preconstruction planning continued 
at a cost of $12,715. 
Total cost for advance engineering and design was 
$130,408. 
28-7

TABLE 28-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 September 1986 
1. Illinois and 
Mississippi Canal, 
IL 
2. Illinois Waterway, 
IL and IN 
3. Mill Creek and 
South Slough at 
Milan, IL 
5. Upper Mississippi 
River Environmenta 
Management Progra 
IL, IA, MN, MO, W 
7. Ames Dam and 
Reservoir, Skunk 
River, IA 
8. Bettendorf, IA 
9. Coralville Lake, IA 
10. Davenport, IA 
11. Des Moines 
Recreational River 
and Greenbelt, IA 
12. Farm Creek, IL 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost. 
Maint: 
Approp. 
Cost 
Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
l Approp. 
im, Cost 
TI 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Contributed Funds 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
1,100,000 
2,423 
10,402,185 
11,471,710 
1,735,000 
5,681,952 
1,000 
1,500 
800,000 
57,049 
13,673,299 
13,738,078 
17,025,000 
18,248,288 
35,000 
24,184 
- - 7,605,1431 
- - 7,605,1431 
99,000 695,000 17,890,8102 
330,888 359,615 17,544,1882 
10,476,000 
10,655,009 
15,270,000 
10,389,719 
10,000 
11,895 
- 126,707,7513 
- 126,706,4193 
10,847,351 225,748,7474 
10,797,875 222,312,8814 
13,841,000 75,550,625 
16,528,634 72,855,889 
2,000 
270 
30,000 814,000 
- 442,750 
63,7196 
63,7196 
396,553 
387,144 
844,000 
442,750 
250,000 144,000 2,185,800 
194,053 172,865 2,158,718 
2,440,000 3,315,000 2,800,000 
1,859,754 3,701,200 2,952,322 
- - 289,121 
3,491,700 
199,040 
2,715,000 
2,420,201 
200,000 
100,458 
1,965,000 
2,086,884 
2,101,000 
2,329,008 
95,717 
2,037,000 
3,656,994 
2,453,500 
2,524,087 
2,240 
3,741,000 13,622,980 
3,853,355 13,587,539 
270,052 
507,889 
2,290,600 
2,045,866 
15,000 238,000 
- 163,997 
107,000 
109,008 
142,000 
70,314 
52,000 
98,920 
289,121 
270,052 
29,969,488 
29,578,309 
23,411,105 
20,997,317 
1,689,717 
1,687,833 
178,997 
- 9,859,020 
- 9,859,020 
60,000 2,685,232 
79,811 2,578,125 
28-8

ROCK ISLAND, IL, DISTRICT 
TABLE 28-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 September 1986 
13. Milan, IL 
14. Red Rock Dam and 
Lake Red Rock, IA 
15. Rockford, IL 
16. Saylorville Lake, 
IA 
22. Loves Park, IL 
South Quincy, IL 
23. Hannibal, MO 
Moline, IL 
New Work: 
Approp. 
Cost 
Contributed Funds 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Contributed Funds 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Contributed Funds 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
3,400,000 
3,522,286 
12,000 
50,000 
489,056 
2,968,500 
2,927,214 
400,000 
866,122 
-84,262 
40,448 
1,960,000 
491,088 
3,953,837 
2,703,132 
1,532,500 
395,229 
3,530,000 2,875,000 962,000 13,686,640 
3,263,505 2,464,332 566,240 12,186,235 
213,950 - 
- 201,554 
225,950 
201,554 
- - - 95,303,484 
- - - 95,302,484 
2,712,000 3,018,300 3,004,600 24,847,323 
2,518,900 3,263,730 2,638,830 22,018,810 
475,000 
1,309,129 
104,200 
117,606 
2,500,000 
1,590,361 
3,173,000 
4,451,959 
221,989 
820,558 
1,100,000 309,000 8,968,273 
883,485 564,537 8,145,286 
391 - 249,361 
981 48 244,208 
5,313,000 
6,404,697 
2,681,500 
2,724,425 
408,352 
593,869 
7,107,000 
3,631,688 
3,116,600 
3,032,005 
141,989 
141,745 
200,000 311,000 
187,644 303,507 
150,000 209,000 
138,466 218,160 
150,000 150,000 
153,304 134,787 
281,000 
172,217 106,759 
60,000 
80,692 
90,000 
48,410 
124,000 
117,693 
-25,000 
12,715 
109,826,887 
104,692,066 
22,362,043 
19,162,810 
2,304,830 
1,951,401 
511,000 
491,151 
359,000 
356,626 
644,993 
638,626 
1,415,000 
1,407,615 
1. Includes $25,000 Emergency Relief Funds. 
2. Includes $4,143,282 for Operating and Care under the 
"Permanent Indefinite Appropriation." 
3. Includes $2,569,102 for previous projects. 
4. Includes $1,028,468 for previous projects. 
5. Includes $85 for previous project. 
6. Includes cost of Mehaffey Bridge, $1,365,074 (excluding 
$100,000 contributed funds). 
7. Excludes $161,813 contributed funds. 
8. Excludes $950,000 non-Federal cost. 
28-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 28-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
2. January 21, 1927 
July 3, 1930 
June 26, 19341 
August 30, 1935 
August 30, 19353 
June 14, 1937 
June 20, 1938 
October 23, 1943 
March 2, 1945 
ILLINOIS WATERWAY, IL AND IN 
Channel 9 feet deep and 200 feet wide from mouth 
of Illinois River to Utica, 231 miles, modification 
of 2 U.S. locks and dams, removal of 2 State 
dams. (Act authorized appropriation of not to exceed 
$3,500,000 for carrying on work.) 
Channel 9 feet deep from Utica, IL, to heads of 
present Federal projects on Chicago and Calumet 
Rivers 94.6 miles to Lake Street, and 96.3 miles to 
turning basin 5, respectively, to be secured by means 
of completed dams, locks, lateral canals, and dredging 
begun by State of Illinois in general accordance with 
present plans of State for that work. Act adopting 
project authorized appropriation of not to exceed 
$7,500,000 for carrying on work. 
Operation and care of locks and dams provided for 
with funds from War Department appropriation for 
rivers and harbors. 
Construct modern locks and dams at LaGrange and 
Peoria and a channel 9 feet deep and 300 feet wide 
below Lockport, exact location and details of design 
of all structures to be left to discretion of Chief of 
Engineers, and, for time being, that no change be 
made in water authorized for navigation of Illinois 
River by act of July 3, 1930. 
Also provides for 3 passing places along Sag 
Channel and authorized channel in Calumet-Sag 
route to turning basin 5, and dredging at entrance of 
Lake Calumet. 
Realign portion of Calumet River and abandonment 
of bypassed section of Calumet River. 
Modifies local cooperation requirements in 1935 act. 
Pay damages to levee and drainage districts due to 
seepage and other factors, not to exceed $503,500. 
Enlarge Calumet-Sag Channel to 160 feet wide and 
a usable depth of 9 feet. Dredge a barge channel 160 
feet wide with a usable depth of 9 feet in Grand 
Calumet and Little Calumet River Branch of Indiana 
Harbor Canal to deep (lake) draft through 141st St., 
East Chicago, IN. Construct in Little Calumet River 
a lock of suitable dimensions for large navigation. 
Rebuild or otherwise alter at Federal expense all 
obstructive railroad bridges across Calumet-Sag 
Channel, Little Calumet River, Calumet River, Grand 
Calumet River, and Indiana Harbor Canal, so as to 
provide suitable clearance, except that no Federal 
funds shall be expended for removal or alteration 
of Illinois Central RR. bridge at mile 11.20 of Little 
Calumet River. 
Rivers and Harbors 
Committee Doc. 69th Cong., 
1st sess., and S. Doc. 130, 
69th Cong., 1st sess. 
S. Doc. 126, 71st Cong., 
2nd sess. 
H. Doc. 184, 73rd Cong., 
2nd sess. 2 
H. Doc. 180, 73rd Cong., 
2nd sess. 
Rivers and Harbors Committee 
Doc. 19, 75th Cong., 1st sess. 
H. Doc. 711, 77th Cong., 
2nd sess. 
H. Doc. 145, 76th Cong., 
1st sess. 
28-10

ROCK ISLAND, IL, DISTRICT 
TABLE 28-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
July 24, 1946 
July 24, 1946 
July 17, 1953 
July 3, 1958 
August 18, 1968 
3. July 3, 1930 
August 15, 1985 
(P.L. 99-88) 
Substitute following work for that authorized by act 
of March 2, 1945; replace emergency dam in Chicago 
Sanitary and Ship Canal; enlargement of that canal 
thence to Sag Junction and of Calumet-Sag Channel 
to afford channels 225 feet wide and usable depth of 
9 feet; construct along general route depth of 9 feet 
to 225 feet wide between Little Calumet River and 
junction with Indiana Harbor Canal and 160 feet wide 
thence to Clark St., Gary, IN, with a turning basin at 
Clark St., enlarge Indiana Harbor Canal to 225 feet 
wide and usable depth of 9 feet between Grand 
Calumet River and vicinity of 141st St., inclusive; 
remove Blue Island lock and construct a lock and control 
works in Calumet River near its head, and 
similar structures in proposed Grand Calumet 
Channel west of Indiana Harbor Canal; alter or eliminate 
railroad bridges across three channels lakeward 
of Chicago Sanitary and Ship Canal, or construct 
new railroad bridges to provide suitable 
clearance. 
A small-boat harbor in vicinity of Peoria, IL, by 
construction of a basin 510 by 250 feet, dredged to 
7 feet deep. 
$48,933 to reimburse Nutwood Drainage and Levee 
District for additional pumping operation; supplementing 
$58,750 authorized in October 1943 act. 
Federal participation in alteration of highway 
bridges, Calumet-Sag Modification, Part I, which 
constitute unreasonable obstructions to navigation, in 
accordance with Public Law 647, 76th Cong., as 
amended. 
Federal participation in alteration of highway 
bridges, Calumet-Sag Modification, Part II, which 
constitute unreasonable obstructions to navigation, 
in accordance with Public Law 647, 76th Cong., as 
amended. 
MILL CREEK AND SOUTH SLOUGH AT 
MILAN, IL 
Channel diversion, floodgates, and other work 
for flood protection. 
UPPER MISSISSIPPI RIVER SYSTEM 
ENVIRONMENTAL MANAGEMENT 
PROGRAM, IL, IA, MN, MO, WI 
Provide for a 10-year environmental program to 
include habitat rehabilitation and enhancement; longterm 
resource monitoring with computerized inventory 
and analysis; recreational development; assessment 
of economic benefits from recreational activities; 
and navigation system traffic monitoring. 
H. Doc. 677, 79th Cong., 
2nd sess. 
H. Doc. 698, 79th Cong., 
2nd sess. 
H. Doc. 144, 81st Cong., 
1st sess. 
H. Doc. 45, 85th Cong., 
1st sess.4 
Specified in Act. Also 
H. Doc. 45, 85th Cong., 
1st sess. 
Rivers and Harbors 
Committee Doc. 19, 
71st Cong., 2nd sess. 
H. Doc. 2577, 99th Cong., 
1st sess. 
28-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 28-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
October 27, 1965 
(P.L. 89-298) 
August 13, 1968 
9. June 28, 1938 
July 14, 1960 
10. December 31, 1970 
11. August 15, 1985 
(P.L. 99-88) 
12. 1944 Flood Control 
Act 
13. August 13, 1968 
14. June 28, 1938 
15. October 23, 1962 
16. July 3, 1958 
October 22, 1976 
17. October 27, 1965 
AMES DAM AND RESERVOIR, SKUNK 
RIVER, IA 
Reservoir for flood control, water quality 
control, recreation, and fish and wildlife. 
BETTENDORF, IA 
Levees, railroad raises, closure structures, and 
street raises and ramps for flood control. 
CORALVILLE LAKE, IA 
Reservoir for flood control and recreation. 
Highway bridge across Coralville Lake at or near 
the Mehaffey site. 
DAVENPORT, IA 
Levee, floodwall, and pumping plants. 
DES MOINES RECREATIONAL RIVER AND 
GREENBELT, IA 
Recreational development; environmental enhancement; 
and related streambank stabilization. 
FARM CREEK, IL 
Two flood detention dams and channel 
improvements. 
MILAN, IL 
Levee closure structures, gravity drainage outlets, 
ditches, ponding areas, and pumping plants for flood 
control. 
RED ROCK DAM AND LAKE RED ROCK, IA 
Reservoir for flood control and recreation. 
ROCKFORD, IL 
Channel enlargement and realignment, levees, and 
appurtenant works for flood control. 
SAYLORVILLE LAKE, IA 
Reservoir for flood control and recreation. 
Modification to minimize adverse project impact on 
Ledges State Park. 
WATERLOO, IA 
Levees, floodwalls, pumping plants, and closure 
structures for flood control. 
8. 
28-12 
H. Doc. 267, 89th Cong., 
1st sess. 
H. Doc. 348, 89th Cong., 
2nd sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st sess. 
None 
H. Doc. 161, 92nd Cong., 
1st sess. 
H. Doc. 2577, 99th Cong., 
1st sess. 
H. Doc. 802, 78th Cong., 
2nd sess. 
H. Doc., 348, 90th Cong., 
2nd sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st sess. 
S. Doc. 142, 87th Cong., 
2nd sess. 
S. Doc. 9, 85th Cong., 
1st sess. 
H. Doc. 487, 94th Cong., 
2nd sess. 
H. Doc. 166, 89th Cong., 
1st sess.

ROCK ISLAND, IL, DISTRICT 
TABLE 28-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
HANNIBAL, MO 
24. October 23, 1962 Levee, floodwall, closure structures, and pumping H. Doc. 564, 87th Cong., 
plant for flood control. 2nd sess. 
MOLINE, IL 
October 27, 1965 Levee, closure structures, and interior drainage H. Doc. 161, 92nd Cong., 
(Section 201) facilities for flood control, and aesthetic and 1st sess. 
Approved by recreational development. 
Committees on Public 
Works of House of 
Representatives and 
Senate, June 14, 1972, 
and June 21, 1972, 
respectively. 
1. Permanent Appropriations Repeal Act. 3. Included, in part, in Public Works Administration Program 
2. Contains latest published map of Illinois and Des Plaines October 31, 1934, and February 28, 1935. 
Rivers. 4. Contains latest published maps of Calumet-Sag portion. 
TABLE 28-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 6 of Text) 
For Last Cost To September 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Squaw Chute at Quincy, IL Completed 1967 70,9791 9,345 
Muscooten Bay, Illinois River, IL Completed 1985 265,4993 0 
Quincy, IL, Harbor Access Channel Completed 1970 35,4772 37,700 
1. Excludes $25,851 contributed funds. 2. Excludes $35,350 contributed funds. 
3. Excludes $137,869 contributed funds. 
28-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 28-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 18 of Text) 
Cost To September 30, 1986 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Completed Projects 
Banner Special Drainage and Levee Districts, IL 1943 274,822 - - 
Bear Creek Dam (City of Hannibal, MO) 1962 1,679,056 - - 
Big Lake Drainage and Levee District, IL 1943 144,910 - - 
Canton, MO' 1964 1,496,555 - - 
Clinton, IA 1981 26,001,996 - 761,050 
Coal Creek Drainage and Levee District, IL 1954 1,923,145 - - 
Crane Creek Drainage and Levee District, IL 1941 68,898 - - 
Des Moines and Mississippi Levee District 
No. 1, MO 1969 1,492,016 - - 
Des Moines, IA 1972 4,993,224 - 23,323 
Drury Drainage District, IL 1964 1,144,875 - - 
Dubuque, IA 1974 10,861,170 - 145,415 
East Liverpool Drainage and Levee District, IL 1941 207,826 - - 
East Moline, IL 1984 9,683,300 - - 
East Peoria Drainage and Levee District, IL 1946 279,963 - - 
Elkport, IA 1951 34,200 - - 
Evansdale, IA 1983 4,409,088 - - 
Fabius River Drainage District, MO 1941 60,500 - - 
Fabius River Drainage District, MO 1963 1,621,841 - - 
Farmers Levee and Drainage District, IL 1942 155,562 - - 
Fulton, IL 1984 18,017,200 - - 
Galena, IL 1952 844,100 - 118,000 
Green Bay Levee and Drainage District No. 2, IA 1949 299,000 - - 
Green Bay Levee and Drainage District No. 2, IA 1967 1,727,711 - - 
Gregory Drainage District, MO 1940 77,100 - - 
Gregory Drainage District, MO 1972 1,538,963 - 20,626 
Henderson County Drainage District No. 1, IL 1968 1,453,217 - - 
Henderson County Drainage District No. 2, IL 1968 1,043,902 - - 
Henderson County Drainage District No. 3, IL 1949 42,700 - - 
Hennepin Drainage and Levee District, IL 1940 109,593 - - 
Hunt Drainage District and Lima Lake Drainage 
District, IL 1972 4,772,498 - - 
Indian Grave Drainage District, IL 1972 3,551,961 - - 
Iowa River-Flint Creek Levee District No. 16, IA 1972 6,044,693 - - 
Kishwaukee River at DeKalb, IL1 1957 123,300 - - 
Lacey Langellier, West Mantanzas and Kerton 
Valley Drainage and Levee District, IL 1954 1,290,000 - - 
Liverpool Drainage and Levee District, IL 1943 117,731 - - 
Lost Creek Drainage and Levee District, IL 1938 152,000 - - 
Marengo, IA' 1981 2,447,001 - - 
Marion County Drainage District, MO 1967 873,748 - - 
Marshalltown, IA 1978 8,437,511 - 252,136 
Mason and Menard Drainage District, IL 1940 93,808 - - 
Meredosia Levee and Drainage District, IL1 1977 1,995,322 - 269,739 
Muscatine, Mad Creek, IA1 1983 1,129,800 - - 
Muscatine Island Levee District and Muscatine- 
Louisa County Drainage District No. 13, IA 1970 3,293,276 - 220,000 
Near Springfield on Sangamon River, IL 1941 - - - 
Oakford Special Drainage District, IL 1940 38,417 - - 
Okabena Creek at Worthington, MN 1957 72,432 - - 
28-14

ROCK ISLAND, IL, DISTRICT 
TABLE 28-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(Continued) (See Section 18 of Text) 
Cost To September 30, 1986 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Ottumwa, IA 1977 233,145 - 
Pekin and La Marsh Drainage and Levee 
District, IL 1955 158,383 - - 
Penny Slough, Rock River, IL 1940 85,800 -- 
Rock Island, IL 1979 7,582,373 - - 
Rocky Ford Drainage and Levee District, IL 1941 108,797 - - 
Sabula, IA 1958 411,915 - - 
Sangamon River (Mouth), IL 1980 1,048,990 272,848 15,122 
Seahorn Drainage and Levee District, IL 1945 32,281 - - 
Sid Simpson Project, IL 1968 5,789,800 - - 
Sny Basin, IL 1972 14,003,560 - - 
Sny Island Levee Drainage District, IL 1942 61,400 - - 
Sny Island Levee Drainage District, IL 1968 4,956,749 - - 
South Beardstown and Valley Drainage and 
Levee District, IL 1942 220,729 - - 
South Beardstown Drainage and Levee District, IL 1942 171,839 - - 
South Quincy Drainage and Levee District, IL 1940 61,200 - - 
South Quincy Drainage and Levee District, IL 1968 1,231,243 - - 
South River Drainage District, MO 1941 55,300 - - 
South River Drainage District, MO 1966 1,106,056 - - 
Spring Lake Drainage and Levee District, IL 1941 185,980 - - 
Subdistrict No. 1 of Drainage Union No. 1 and Bay 
Island Drainage and Levee District No. 1, IL 1967 3,306,695 - - 
Union Township Drainage District, MO 1947 116,576 - - 
Van Meter, IA' 1965 113,842 - - 
Authorized Projects Not Constructed 
Farmers Levee and Drainage District, IL - - - - 
Freeport, IL 1979 286,000 - - 
Peoria, IL 1973 534,580 - - 
Rock River Agricultural Levees, IL 1984 858,000 - - 
South Beloit, IL 1979 270,000 - - 
1. Authorized by Chief of Engineers (Sec. 205, 1948 Flood Control Act). 
28-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 28-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Campbells Island 
Mississippi River, IL 1969 1979 $ 76,664 - 
Carroll County Levee 
and Drainage District, IL 1938 1977 - - 
Central City Lake, 
Wapsipinicon River, IA 1970 1977 55,664 - 
Green Island Levee and 
Drainage District, IA 1938 1977 - - 
Henderson River, IL 1964 1977 102,310 - 
Illinois Waterway, IL and IN 
Duplicate Locks 1982 1981 - - 
Janesville and Indian 
Ford Dams, WI 1938 1977 - - 
Keithsburg Drainage 
District, IL 1938 1977 - - 
Pecatonica River at 
Darlington, WI - 1977 
Rochester Lake, 
Cedar River, IA - 1977 - - 
William L. Springer Lake 
Decatur, IL 1979 1986 - - 
TABLE 28-H INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 17 of Text) 
Date 
Project Inspected 
Alpine Dam and Page Park Dam, Rockford, IL 
Banner Special Drainage and Levee District, IL 
Bear Creek Reservoir, Hannibal, MO 
Big Lake Drainage and Levee District, IL 
Burlington, IA 
Canton, MO 
Clinton, IA 
Coal Creek Drainage and Levee District, IL 
Crane Creek Drainage and Levee District, IL 
DeKalb, IL 
Des Moines, IA 
Des Moines and Mississippi Levee District No. 1, MO 
Drury Drainage District, IL 
Dubuque, IA 
East Liverpool Drainage and Levee District, IL 
East Moline, IL 
East Peoria Drainage and Levee District, IL 
East Peoria Sanitary District, IL 
Elkport, IA 
Evansdale, IA 
Fabius River Drainage District, MO 
Farmers Drainage and Levee District, IL 
Fulton, IL 
October 1985 
January 1986 
January 1986 
January 1986 
January 1986 
January 1986 
October 1985 
January 1986 
January 1986 
October 1985 
February 1986 
January 1986 
October 1985 
October 1985 
November 1985 
October 1985 
November 1985 
October 1985 
September 1985 
April 1986 
January 1986 
January 1986 
September 1985 
28-16

ROCK ISLAND, IL, DISTRICT 
TABLE 28-H 
(Continued) 
Project 
INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 17 of Text) 
Date 
Inspected 
Galena, IL 
Green Bay Levee and Drainage District, No. 2, IA 
Gregory Drainage District, MO 
Henderson County Drainage District No. 1, IL 
Henderson County Drainage District No. 2, IL 
Hennepin Drainage and Levee District, IL 
Hergot Drainage and Levee District, IL 
Hunt Drainage District & Lima Lake Drainage District, IL 
Indian Grave Drainage District, IL 
Iowa River-Flint Creek Levee District No. 16, IA 
Kerton Valley Drainage and Levee District, IL 
Lacey Drainage and Levee District, IL 
Langellier Drainage and Levee District, IL 
Liverpool Drainage and Levee District, IL 
Lost Creek Drainage and Levee District, IL 
Mad Creek, Muscatine, IA 
Marengo, IA 
Mason and Menard Drainage District, IL 
Marion County Drainage District, MO 
Marshalltown, IA 
Meredosia Levee and Drainage District, IL 
Milan, ILl 
Muscatine Island, L&DD, & Louisa DD No. 13, IA 
Oakford Special Drainage and Levee District, IL 
Pekin-LaMarsh Drainage and Levee District, IL 
Penny Slough Drainage and Levee District, IL 
Rock Island, IL 
Sabula, IA 
Sanitary District of Beardstown, IL 
Seahorn Drainage and Levee District, IL 
Sny Island Levee Drainage District, IL 
South Beardstown Drainage and Levee District, IL 
South Quincy Drainage and Levee District, IL 
South River Drainage District, MO 
Spring Lake Drainage and Levee District, IL 
Subdistrict No. 1 of Drainage Union No. 1, 
and Bay Island Levee and Drainage District No. 1, IL 
The Sny Basin, IL 
Valley Drainage and Levee District, IL 
Van Meter, IA 
Volga, IA 
Waterloo, IA 
West Matanzas Drainage and Levee District, IL 
Worthington, MN 
October 1985 
November 1985 
January 1986 
October 1985 
October 1985 
November 1985 
January 1986 
January 1986 
January 1986 
October 1985 
December 1985 
December 1985 
December 1985 
November 1985 
January 1986 
October 1985 
April 1986 
January 1986 
January 1984 
April 1986 
October 1985 
November 1985 
October 1985 
January 1986 
January 1986 
October 1985 
November 1985 
September 1985 
January 1986 
January 1986 
January 1986 
January 1986 
December 1985 
January 1986 
December 1985 
October 1985 
January 1986 
January 1986 
January 1986 
September 1985 
April 1986 
December 1985 
October 1985 
1. Project partially completed. 
28-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 28-I FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, Public Law 
858, 80th Congress, as Amended (Preauthorization) 
(See Section 19 of Text) 
Study Identification Fiscal Year Costs 
Cedar River, Waverly, IA 
Couler Valley, Dubuque County, IA 
Decatur, IL 
DeKalb, IL 
Illinois River, Liverpool, IL 
Iroquois River, Sugar Creek, Watseka, IL 
Lake Creek, Rockwell City, IA 
Morton, IL 
North River, Marion County, MO 
Oelwein, Fayette County, IA 
Ottawa, IL 
Panther Creek, Sangamon River, Chandlerville, IL 
Plainfield, IA 
Raccoon River, Des Moines, IA 
Tama, IA 
Vermilion River, Pontiac, IL 
$28,310 
1,787 
19,585 
34 
27,481 
45,761 
2,500 
27,917 
18,010 
30,311 
33,682 
3,048 
34,855 
17,205 
12,778 
67,196 
TABLE 28-I Snagging and Clearing Navigable Streams and 
Tributaries in the Interest of Flood Control (Preauthorization) 
(Section 208, 1954 Flood Control Act, Public Law 780, 83rd Congress) 
Project and Location Fiscal Year Costs 
Des Moines River, East Branch, Kossuth County, IA $ 3,481 
Negro Creek, Bureau County, IL 5,858 
TABLE 28-I Emergency Bank Protection (Section 14 of 
the 1946 Flood Control Act, Public Law 526, 79th Congress) 
Project and Location Fiscal Year Costs 
320 St. N. Rock River, Rock Island, IL $ 10,961 
Des Moines River, Boone, IA 79 
Des Moines River, Eldon, IA 34 
Middle River, Adair County, IA 6,291 
Mississippi River, Cassville, WI 7,500 
North Fabius River, Lewis County, MO 144 
North River, Marion County Road 152, MO 143,771 
Turkey River, Elgin, IA 107,426 
Turkey River, Jefferson Township, IA 9,919 
Turkey River, Millville Township, IA 9,316 
28-18

ROCK ISLAND, IL, DISTRICT 
TABLE 28-I 
(Continued) 
FLOOD CONTROL WORK UNDER SPECIAL 
Emergency Flood Control Activities - Repair, 
Rescue Work (Public Law 99, 84th Congress and 
(See Section 19 of Text) 
AUTHORIZATION 
Flood Fighting, and 
Antecedent Legislation) 
Project and Location Federal Cost 
Advance Preparation 
Rehabilitation: 
Banner Levee, Fulton County, IL 
Below London Mills-Parker, IL 
Blackburn Levee, IL 
Blout-Lundry Levee, IL 
Cullinane-Zempel-Evans, IL 
Dobey Levee, IL 
Formhals Levee, IL 
Globe, IL 
Hager Slough, IL 
Hennepin Levee, Illinois River, IL 
Herman, IL 
Irvin-Blackburn Levee, IL 
LL WM & KV Drainage and Levee, IL 
Louisa County Levee District 8, Iowa River, IA 
Mississippi-Fox River Drainage District #2 Levee, MO 
Old Canal Levee-Des Moines River, Lee, IA 
St. Francisville Levee, MO 
Zempel-Mutual, IL 
28-19 
$ 224,056 
3,136 
83 
25 
83 
- 45 
124 
83 
39,354 
325,371 
183,715 
2,642 
49 
241,844 
13,797 
18,933 
40,864 
164,908 
36,694

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 28-J ILLINOIS WATERWAY: 
EXISTING LOCKS AND DAMS 
(See Section 2 of Text) 
Depth on 
Dimensions Miter Sills 
at Low Water 
Available Lift at 
Miles Width of Length for Low 
Above Chamber Full Width Water1 Lower Upper 
Lock Mouth Miles to Nearest Town (feet) (feet) (feet) (feet) (feet) 
LaGrange Lock 80.2 7.8 below Beardstown, IL 110 600 10.0 13.0 15.5 
Peoria Lock 157.7 4.1 below Peoria, IL 110 600 11.0 12.0 15.5 
Starved Rock Lock 231.0 Utica, IL 110 600 18.5 14.0 16.8 
Marseilles Lock 244.6 Marseilles, IL 110 600 24.45 14.0 18.6 
Dresden Island Lock 271.5 8 above Morris, IL 110 600 21.75 12.25 16.85 
Brandon Road Lock 286.0 Joliet, IL 110 600 34.0 13.8 17.85 
Lockport Lock 291.1 Lockport, IL 110 600 30.5-39.52 15.0 11.0-20.02 
T.J. O'Brien Lock 326.5 Chicago, IL 110 1,000 - 14.0 14.0 
1. Lifts and depth on miter sills are those obtained with flat 2. Variation in lift and depth on upper miter sill at Lockport 
pools. is due to fluctuation of water surface in the sanitary district canal. 
TABLE 28-K ILLINOIS WATERWAY, IL AND IN 
LOCK AND DAM CONSTRUCTION, FOUNDATIONS, COST 
(See Section 2 of Text) 
Lock Dam Estimated 
Federal Cost 
Under 
Type of Character of Type of Character of Year Existing 
Name Construction Foundation Kind Construction Foundation Complete Project 
Tlln1; i - - - - - - 9 7 3 AQQ1 
mouth to Utica; 
channel improvement 
by dredging 
in Illinois River 
below Starved Rock 
modification of two 
U.S. locks and 
dams, and removal 
of two State dams. 
LaGrange 
Peoria 
Starved Rock 
Marseilles 
Concrete Piles in sand 
Concrete Piles in sand 
Concrete Rock 
Concrete Rock 
Movable 
(wicket 
with Aframe-
crest) 
Movable 
(wicket 
type) 
Movable 
(tainter 
gates) 
Movable 
(tainter 
gates) 
Concrete 
and timber 
Concrete 
and timber 
Concrete 
and 
structural 
steel 
Concrete 
and 
structural 
steel 
Piles in sand 
Piles in sand 
Rock 
Rock 
1939 
1939 
1933 
1933 
2,744,5921 
3,381,0301 
885,3151 
1,853,7251 
28-20 
,! ,'JfJ ~~

ROCK ISLAND, IL, DISTRICT 
TABLE 28-K 
(Continued) 
ILLINOIS WATERWAY, IL AND IN 
LOCK AND DAM CONSTRUCTION, FOUNDATIONS, COST 
(See Section 2 of Text) 
Lock Dam Estimated 
Federal Cost 
Under 
Type of Character of Type of Character of Year Existing 
Name Construction Foundation Kind Construction Foundation Complete Project 
Dresden Island Concrete Rock Movable Concrete Rock 1933 $ 2,503,3761 
(tainter and 
gates) structural 
steel 
Brandon Road Concrete Rock Movable Concrete Rock 1933 2,031,683' 
(tainter and 
gates) structural 
steel 
Lockport Concrete Rock Movable Concrete Rock 1933 133,6081 
(Bear trap) and 
(Bear trap) structural 
steel 
T.J. O'Brien Concrete Piles in clay Fixed Concrete Piles in clay 1960 6,954,7001 
and sheet and sheet 
piling piling 
Lock and dam - - - - - - 1,250,3041 
equipment 
Total locks - - - - - - $ 24,471,832 
and dams 
1. Actual cost. 
TABLE 28-L ILLINOIS WATERWAY, IL AND IN 
ADDITIONAL FEATURES ENTERING INTO COST 
(See Section 2 of Text) 
Dredging: 
Little Calumet and Calumet Rivers $ 2,135,3581 
Calumet-Sag, 3 passing places 813,4181 
Starved Rock to Lockport 3,650,635 
Starved Rock to Grafton 2,686,307 
Calumet-Sag Channel 19,238,200 
Peoria small boat harbor 24,9371 
Protection piers at all locks 77,6131 
Calumet-Sag modification engineering and design 5,141,474 
Calumet-Sag modification, supervision and administration 5,466,804 
Rebuild highway bridges 19,327,850 
Rebuild railway bridges: 
Calumet-Sag Channel 20,828,4351 
Little Calumet and Calumet Rivers 18,362,0411 
Recreation Facilities, Code 711 445,000 
Removal of Blue Island lock 288,6001 
Grand Calumet River controlling works2 
St. Louis District 1,081,6001 
Total additional features $ 99,569,604 
Total existing project $124,041,436 
1. Actual cost. 2. Placed in inactive status November 19, 1974. 
28-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 28-M EXISTING PROJECT 
See 
Section 
in Text Project Item Length (feet) Width (feet) Depth (feet) 
1. Illinois Waterway, Nine locks and six dams - - 
IL and IN 
Grafton to Lockport, IL 291.1 miles 300 9 
Lockport to controlling works 2.0 miles 200-300 9 
Controlling works to junction with 10.0 miles 225 9 
Calumet-Sag Channel 
Calumet-Sag Channel to lock in Blue 16.0 miles 225 9 
Island 
Calumet and Little Calumet Channel, 7.7 miles 300 9 
from Blue Island to turning basin 5 
Grand Calumet River Channel from 9.0 miles 9 
junction with Little Calumet River 
to and in Indiana Harbor Canal to 
141st, East Chicago, IN 
Also, Grand Calumet River Channel 4.2 miles 160 9 
from junction of Indiana Harbor 
Canal and Grand Calumet River to 
Clark St. in Gary, IN, with a turning 
basin at Clark St. 
A channel in Chicago Sanitary and 22.1 miles 175-300 9 
Ship Canal and South Branch 
Chicago River from Sag-Junction to 
Lake St. in Chicago, IL 
TABLE 28-N ILLINOIS WATERWAY, IL AND IN 
TOTAL COST OF EXISTING PROJECT 
TO SEPTEMBER 30, 1986 
(See Section 2 of Text) 
New Work Maintenance Rehabilitation Total 
Regular Funds $118,317,646 $221,855,623 $72,855,889 $413,029,158 
Public Works Funds 3,960,735 - - 3,960,735 
Emergency Relief Funds 1,858,936 - - 1,858,936 
Total $124,137,317 $221,855,623 $72,855,889 $418,848,829 
1. Includes $1,735,890 expended between 1927 and 1936 on provisions of the permanent indefinite appropriation for such 
the operation and care of the works of improvement under the purposes. 
28-22

MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MN *
Section of river covered in this report is divided into three 
reaches, under supervision and direction of District 
Engineers at St. Louis, Rock Island, and St. Paul. Section 
in St. Louis District extends 105 miles from Mouth of 
Missouri River to Upper Mississippi River mile 300 above 
Location. Mississippi River rises in northern part of 
Minnesota, flows about 2,360 miles southerly and empties 
into Gulf of Mexico. Portion included in this report extends 
about 663 miles from mouth of Missouri River to Soo Line 
Railroad bridge, Minneapolis. Latest map and profile showing 
this section of river is in House Document 669, 76th 
Congress, 3d session. A map showing Lake Pepin is in 
House Document 511, 79th Congress, 2d session. A map 
of section Minneapolis to Dubuque is in House Document 
515, 79th Congress, 2d session. A map showing location 
of drainage districts (Bellevue, Iowa, to Missouri River) 
is in River and Harbors Committee Document 34, 75th 
Congress, 1st session. 
Previous projects. See page 1199 of Annual Report 
for 1963. 
Existing project. Provides for a channel of 9-foot depth 
and adequate width between mouth of Missouri river (1,179 
miles from the gulf) and Soo Line Railroad at Minneapolis, 
by construction of a system of locks and dams, supplemented 
by dredging. Project also provides for further 
improvements at St. Paul to provide a basin extending 
downstream from Robert Street Bridge of 2.7 miles, and 
at Minneapolis to provide adequate terminal facilities, and 
for other harbor improvements and miscellaneous work. 
Pertinent data on locks and dams, harbor improvements, 
additional features entering into cost of project, and 
authorizing legislation are given in Tables 29-C, 29-D, 29-E 
and 29-G. All dams are concrete. Three dams (Upper St. 
Anthony Falls, 1 and 19) are fixed, remainder are movable. 
Estimated cost for new work (1982) is $894,157,300 exclusive 
of amounts expended on previous projects. See 
House document 669, 76th Congress, 3d session, for a 
report of Chief of Engineers dated February 27, 1940, containing 
a general plan for improvement of Mississippi River 
between Coon Rapids Dam and mouth of Ohio River for 
purposes of navigation, power development, flood control, 
and irrigation needs. 
Local cooperation. Small-boat harbors authorized in the 
River and Harbor Act of 1962 are subject to conditions that 
local interests make a cash contribution toward cost of construction 
(except in case of Quincy Harbor which involves 
maintenance only of an existing harbor); furnish lands and 
rights-of-way for construction and future maintenance; hold 
the United States free from damages; provide and main- 
Ohio River; Rock Island District extends about 314 miles 
from mile 300 to 614; and St. Paul District extends about 
244 miles from mile 614 to Soo Line Railroad bridge, 
Minneapolis (mile 857.6). 
tain mooring facilities and utilities; reserve accommodations 
for transient small boats; accomplish all necessary 
relocations and alterations; and establish public bodies 
empowered to regulate use, growth and development of the 
harbors. 
Rectification of seepage damages to privately owned 
lands in the Sny Island Levee Drainage District, IL, is subject 
to the conditions that local interests acquire all lands, 
easements, and rights-of-way necessary for construction 
and maintenance of the project; comply with applicable 
provisions of the Uniform Relocation Assistance and Real 
Property Acquisition Policies Act of 1970; accept, operate, 
and maintain the project upon its completion; and hold and 
save the United States free from damages arising from the 
construction and operation of the completed project; provided 
further that the local public entity shall be reimbursed 
by the Government in the amounts actually expended 
by it in the acquisition of real estate and for 
payments required under Public Law 91-646 if said 
amounts have been previously submitted to and approved 
by the Government. 
Local cooperation requirements for improvement of 
commercial harbor at Dubuque, IA; for improvement of 
Beaver Slough at Clinton, IA, for navigation; and for general 
navigation facilities at small-boat harbors at Rock Island, 
IL; Hannibal, MO; Fort Madison, IA, Davenport (Lindsay 
Park); IA; Muscatine, IA (including freight terminal 
approach channel); Andalusia, IL; Warsaw, IL; Moline, IL; 
Clinton, IA; and Savanna, IL, have been complied with. 
Licenses. Federal Energy Regulatory Commission 
collects from non-Federal licensees annually to recompensate 
the United States for use of government dams for 
generation of hydroelectric power. Amounts collected are 
returned to U.S. Treasury. (See table at end of chapter for 
license fees collected through the end of the fiscal year.) 
Operations during fiscal year. St. Paul District. New 
Work: Under Section 107 authority, an initial appraisal 
was completed at Lake Pepin, Wisconsin at a cost of $7,500. 
Studies were continued under Section 107 for the establishment 
of a small-boat harbor at Guttenberg, Iowa at a cost 
of $40,066. Total new work costs were $47,566. 
Maintenance: Channel dredging to remove shoal areas 
was performed. Government pipeline dredge WILLIAM 
29-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
A. THOMPSON removed 687,980 cubic yards of material 
at 11 locations at a cost of $1,222,046. Government derrick 
barge HAUSER removed 4,200 cubic yards of material 
at 2 locations for $66,924. Government pipeline dredge 
DUBUQUE removed 15,040 cubic yards at 2 locations at 
a cost of $223,669. Mechanical dredging contract costs were 
$941,998. Contracts for dredging, dredging at Weaver 
Bottoms, and Pool 1 site preparation cost $211,896, 
$532,901, and $690,858, respectively. Dredging surveys cost 
$468,231. Other dredging and snagging cost $244,784. 
Water quality testing for dredging cost $71,691. Painting 
at lock and dams cost $741,068. Scour repair contracts at 
Locks and Dams 2, 5A, and 10 cost $666,863, $145,898 and 
-$149,000, respectively. Contracts for spillway repair at 
Lock and Dam 9, spillway resurfacing and straightening 
at Lock and Dam 10, and general dam maintenance cost 
$9,160, $4,826, and $11,208, respectively. Contracts for construction 
of handicapped facilities at Lock and Dam 9, for 
loading dock and park at Lock and Dam 7 cost $40,000, 
$313,473, and $2,153, respectively. Road repair contracts 
at Locks and Dams 1 and 5 cost $39,068 and $13,983, 
respectively. Supply and equipment contracts for 
mechanical materials at Locks and Dams 2-10, for tow 
haulage units at Locks and Dams 2 and 4-10, for air compressors, 
for equipment replacement, for generator sets, for 
electrical equipment, for computer processing equipment 
and for processing and channel sweeping system cost 
$119,459, $608,800, $37,198, $8,992, $51,026, $70,983, 
$80,000 and $477,937, respectively. Contracts for construction 
of storage building at Lock and Dam 5A, the installation 
of security fencing at Lock and Dam 3, for revising 
the radio backbone system and for purchasing a portable 
sandblasting unit cost $200,000, $16,338, $87,389, and 
$10,727, respectively. Maintenance costs for small-boat 
harbors at Lake City, Minnesota and Winona, Minnesota 
were $27,196 and $13,000, respectively. Engineering work 
and miscellaneous surveys, reports, and other work were 
carried on by hired labor for $1,329,726 and by contract 
for $334,245. 
Operating and care: Locks and dams were operated 
as required, and necessary repairs were made to those and 
appurtenant structures. Other studies, reports, and 
miscellaneous engineering work were also accomplished. 
The total cost of maintenance was $12,493,309. Total cost 
of operating and care was $11,585,502. 
Costs to St. Paul District were $47,566 for new work and 
$24,068,811 for operation and maintenance, for a total of 
$24,116,377. 
Rock Island District. New Work: A contractor earned 
$1,990,000 on Stage I, Rock Excavation contract, in Pool 
15 with 27,600 cubic yards of rock and overburden being 
removed. Costs in connection with the commercial harbor 
at Dubuque, Iowa was $35,279. Total new work costs were 
$2,025,279. 
Maintenance: Channel dredging by Government 
cutterhead pipeline Dredge WILLIAM A. THOMPSON was 
performed at various locations in Pools 11, 13, 14, 16, 17, 
18, 20, and 21 at a cost of $991,300 with 744,206 cubic yards 
of material being removed. Dredging inspection and reports 
were completed at a cost of $49,300. Snagging, clearing and 
excavation was performed by hired labor at various locations 
at a cost of $19,100. Dredged material disposal activities 
and other environmental concerns in connection with 
dredging and channel maintenance activities cost $47,700. 
Repair of channel regulating works structures was performed 
at a cost of $1,266,000. Structural repairs, including 
sandblasting and painting were performed by hired labor 
at locks and dams at a cost of $1,408,300. Contractor earned 
$17,700 for painting dam roller gates at Lock and Dam 15, 
and another contractor earned $142,100 for painting dam 
roller and tainter gates and service bridge at Lock and Dam 
17. Contractor earned $154,700 for completion of upper 
bulkhead recesses at Lock and Dam 20. Lock and Dam access 
road and parking improvements were completed by 
contract at a cost of $17,000. Contractors earned $255,300 
for road surfacing at three fee public use areas. Energy 
rehab of the central control station at Lock and Dam 21 
was completed by contract at a cost of $210,000. Contractor 
installed culvert bulkheads and hoist at Lock and Dam 
19 at a cost of $150,300. Contractor substantially completed 
installation of upper bulkhead recesses at Locks and Dams 
21 and 22 at a cost of $590,900. Maintenance of roads and 
bridges was performed at a cost of $68,400 and maintenance 
of buildings, grounds and utilities totalled $5,100. 
Maintenance of public use areas was performed at a cost 
of $605,400 and maintenance and purchase of permanent 
operating equipment cost $455,200. Maintenance of levees 
cost $471,100 and boundary monumentation was performed 
by contract at a cost of $94,900. Engineering and 
design work including preparation of design memorandums 
totalled $646,100. Supervision and administration for 
maintenance features cost $483,200. Total maintenance 
costs were $8,149,100. Net credits to the project were 
$19,200, primarily as a result of collection of damages from 
towboat companies to lock and dam structures. 
Operating and care: Operation o the locks and dams 
and routine maintenance and minor repairs thereto were 
performed at a cost of $7,339,700. Real estate management 
services were performed at a cost of $184,700. Natural 
resource activities cost $227,900. Public use areas and 
Mississippi River Visitor Center were operated at a cost of 
$916,000, with contract law enforcement provided at a cost 
of $76,800. Surveys, various condition and operation studies 
and structural inspections cost $964,500. Water control 
management costs were $817,200; amount of $54,300 was 
expended on Master Plans; and $10,400 was expended on 
various investigations and reports. Supervision and administration 
for operations features cost $247,100. Total 
operation costs we're $10,838,600. 
Total operation and maintenance costs were $18,968,600. 
Rehabilitation: Rehabilitation for Lock and Dam 20 
29-2

MISSISSIPPI RIVER BETWEEN MISSOURI AND MINNEAPOLIS, MN 
was initiated at a cost of $1,185,900. 
St. Louis District. New work: Costs incurred for new 
Lock and Dam 26 were $162,919 for real estate acquisition, 
$2,424,942 for relocations, $8,410,046 for the dam, 
$62,483,189 for the lock, $5,111 for levees and floodwalls, 
$3,285 for permanent operating equipment, $2,711,833 for 
engineering, and $4,429,136 for supervision and administration. 
Costs incurred for 2nd lock were $3,297,844 for 
engineering and $215,906 for supervision and administration. 
Total cost of new work was $84,144,211. 
Operating and care: The locks and dams were operated 
as required, and necessary repairs were made thereto and 
to appurtenant structures at a cost of $4,188,795. 
Costs to St. Louis District were $84,144,211 for new work 
and $9,371,882 for operation and maintenance for a total 
of $93,516,093. 
Condition at end of fiscal year: For information pertaining 
to locks, dams and harbors, see tables at end of chapter. 
St. Paul district. Work completed: Locks and Dams 
at St. Anthony Falls and Nos. 1 to 10, inclusive, except for 
relatively minor appurtenant work; major improvements 
of channels and harbors at St. Paul and Minneapolis; commercial 
harbors at Lake City; Red Wing, and Winona, MN; 
and Prairie du Chien, WI; small-boat harbors at St. Paul, 
Hastings, Red Wing, Wabasha, Lake City and Winona, MN; 
Lansing, IA; and Bay City, Pepin, and Prairie du Chien, WI; 
a remedial drainage ditch at Cochrane, WI; miscellaneous 
channel dredging and realignment; channel markers; pool 
clearing; and construction of various facilities for recreation 
use. Seepage damages totalling $90,027 were paid to 210 
claimants. 
Status of land and flowage acquisition: Approximately 
50,293.54 acres of land in fee, including 47,305 acres 
used by the Department of the Interior in accordance with 
a cooperative agreement and general plans, and easements 
of 15,549.63 acres of land are owned or controlled in pools 
1 to 10, inclusive, at end of fiscal year. In addition, fee title 
to 12.46 acres and perpetual easements on 2.98 acres of land 
for St. Anthony Falls and perpetual easements over 244.39 
acres of land for harbors have been obtained and Department 
of the Army holds special rights over 62,954.74 acres 
owned by Department of the Interior in pool Nos. 3 to 10, 
inclusive. Land acquisition is complete. 
Work remaining to complete portion of project in 
St. Paul District: Guidewall extension at Lock No. 3 (the 
uncompleted guidewall extensions at Lock Nos. 4, 5, 5A, 
7, 8, 9, and 10 were reclassified from the "active" to the 
"inactive" category on April 13, 1973); realignment of 
channel at Wilds Bend; construction of small-boat harbor 
at St. Paul (Harriet Island), MN; and construction of additional 
recreational facilities. 
Condition of channel at end of fiscal year was such that 
controlling depths of 9 feet at low water and minimum 
widths for long-haul common carrier service were available 
in all pools. Structures are in good condition. 
Rock Island District. Work completed: Major construction 
items, including all locks and dams, are completed 
and in operation. The following related work has also been 
completed: Construction of small-boat harbors at Rock 
Island, IL; Moline, IL; Andalusia, IL; Warsaw, IL; Fort 
Madison, IA; Davenport (Lindsay Park), IA; Muscatine, IA; 
Clinton, IA; and Hannibal, MO; improvement of Beaver 
Slough at Clinton, IA, for navigation; improvement of commercial 
harbor at Dubuque, IA; rehabilitation of old 
auxiliary lock at Lock and Dam 14; permanent closure of 
old Lock 19 and drydock; rock and conglomerate excavation 
in Pool 16; rectification of seepage damage in the Sny 
Island Levee Drainage District, IL; recreational facilities; 
and construction of visitor center at Lock 15. 
Work remaining to complete portion of project in 
Rock Island District: construction of guidewall extension 
at 16, 18, and 21: mooring facilities at 11, 12, 14, 15, 16, 
17, and 18; upper approach improvement at 19 and 20; rock 
and/or congolmerate excavation in Pools 14, 15, 18, and 21; 
and construction of small-boat harbors at Keokuk, IA, and 
New Boston, IL. Planning for the small-boat harbor at 
Savanna, IL, is currently under way. Small-boat harbors at 
Bellevue, IA, Cassville, WI, Davenport (Credit Island), IA, 
and Fort Madison, IA are inactive or have been 
deauthorized. 
Status of land and flowage acquisition: Acquisition of 
land in Pools 11 to 22, inclusive, consisting of 93,601 acres 
in fee and 10,541 acres in flowage easement, has been 
completed. 
Condition of the channel at end of fiscal year, was such 
that controlling depths of 9 feet at low water and widths 
suitable for long-haul common carrier service were being 
maintained in all pools. 
St. Louis District. Work completed: Locks and Dams 
Nos. 24, 25, and 26 (Henry T. Rainey Dam), except for 
guidewall extensions at Locks Nos. 24 and 25, have been 
completed as have recreation facilities at the three pools. 
Payments for rectification of damages have been completed. 
Other work remaining consists of construction guidewall 
extensions at Locks Nos. 24 and 25. Replacement of Lock 
and Dam 26 is under construction. 
Status of land and flowage acquisition: Acquisitions of 
lands in Pools Nos. 24, 25, and 26, involving 4,448 acres 
of land in fee and flowage easements over 6,600 acres, is 
complete. A total of 1,742 acres have been acquired for 
Lock and Dam No. 26 replacement project. 
Condition of channel at end of fiscal year was such that 
controlling depth of nine feet at low water and generally 
suitable widths for long-haul common carrier services were 
maintained in all pools and between Locks and Dam, No. 
26 and Missouri River. 
Total Federal costs of existing project to end of fiscal year 
for the three Districts was $139,808,449 of which 
$86,217,056 was for new work, $52,409,293 regular funds 
for operation and maintenance and $1,185,900 regular 
funds for rehabilitation. 
29-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 29-A COST AND FINANCIAL STATEMENT 
Total Cost to 
Project Funding FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
Mississippi River New Work 1 
between Missouri River Approp.2 70,105,398 38,441,000 85,053,000 84,345,770 651,206,903 
and Minneapolis, Cost3 67,081,730 42,157,597 84,591,964 86,217,056 651,686,562 
Minnesota (Federal Maint. 4 
Funds) Approp. 58,960,456 51,692,401 52,296,749 56,548,589 723,751,625 
Cost 50,986,450 60,514,185 53,051,295 52,409,293 710,516 701 
Rehab. 
Approp. 0 0 0 1,240,000 58,773,197 
Cost. 1,214,556 99,623 1,797 1,185,900 58,719,097 
(Contributed funds) New Work 
Approp. 400,000 512,160 -99,561 0 2,041,140 
Cost 0 774,696 37,903 0 2,041,140 
1. Includes $56,945,518 for new work on previous projects. 
2. Includes replacement Lock and Dam 26 funds $418,932,000. 
3. Includes replacement Lock and Dam 26 funds $417,248,026. 
4. Includes $8,504,026 for maintenance on previous project. 
TOTAL COSTS OF EXISTING PROJECT 
TABLE 29-B TO SEPTEMBER 30, 1986 
Regular Public Work Emergency 
District Cost Funds Funds Relief Funds Total 
St. Paul New Work1 $ 60,154,8132 $ 24,210,071 $ 9,071,214 $ 93,436,098 
Maintenance3 288,667,373 - - 288,667,373 
Rehabilitation 44,600,000 - - 44,600,000 
Total 393,422,186 24,210,071 9,071,214 426,703,471 
Rock New Work4 67,272,7455 17,403,322 11,338,865 96,014,932 
Island Maintenance 6 253,279,233 - - 253,279,233 
Rehabilitation 14,119,097 - - 14,119,097 
Total 334,671,075 17,403,322 11,338,865 363,413,262 
St. Louis New Work8 449,939,0497 10,282,566 2,440,266 462,665,681 
Maintenance 167,753,794 - - 167,753,794 
Total 617,692,843 10,282,566 2,440,266 630,415,675 
1. Excludes $2,041,140 contributed funds. Includes $7,673 expended 
in pool No. 11. 
2. Includes $159,359 transferred from Rock Island District covering pro 
rata share of cost of derrick boat Hercules. 
3. Includes $762,196 expended between 1930 and 1936 on operating 
and care of works of improvement under provisions of permanent indefinite 
appropriation for such purposes. Excludes $797,670 contributed 
funds. 
4. Excludes $58,999 contributed funds. 
5. $687,709 was transferred to St. Louis District in fiscal year 1958. Excludes 
$201.167 transferred to St. Paul and St. Louis Districts covering 
their pro rata share of cost of derrick boat Hercules. 
6. Costs subsequent to FY 1953 included with operating and care. Includes 
the sum of $395,442, expended between 1930 and 1934 on the 
operating and care of the works of improvement under the provisions 
of the permanent indefinite appropriation for such purposes. 
7. Includes $47,800 transferred from Rock Island District covering pro 
rata cost of derrick boat Hercules and $687,709 transferred from Rock 
Island District. 
8. Includes $417,248,026 for replacement of Lock and Dam 26. 
29-4

LOCKS AND DAMS 
Lock Dimensions 
Greatest Depth on Character of Foundation Percent 
Width Length Upper Miter Sill Complete 
Miles of Available Normal Locks, Year Estimated Cost of 
Above Cham- for Full Pool Dams, and Opened Each Lock and 
Ohio Miles from ber Width Lift Eleva- Upper Lower Work in to Navi- Dam Including 
Lock and Dam River Nearest Town (feet) (feet) (feet) tion1 (feet) (feet) Lock Dam Pool gation Work in Pool 
St. Anthony 853.9 In city of 56 400 49.2 799.2 15.7 13.7 Some lime- Limestone. 1002 - $ 18,203,000 
Falls, upper 
Lock 
St. Anthony 
Falls, lower 
Lock and dam 
Lock and dam 
1 
Lock and dam 
2 
Lock and dam 
3 
Lock and dam 
4 
Lock and dam 
5 
Lock and dam 
5A 
Lock and Dam 
6 
Lock and dam 
7 
Lock and dam 
8 
Lock and dam 
9 
Lock and dam 
10 
Lock and dam 
11 
Lock and dam 
12 
Lock and dam 
13 
Lock and dam 
14 
Le Claire Lock 
(Canal) 
Lock and dam 
15 
Minneapolis, 
MN 
853.3 In city of 
Minneapolis, 
MN 
847.6 Minneapolis- 
St. Paul 
815.2 1.3 above 
Hastings, MN 
796.9 6.1 above Red 
Wing, MN 
752.8 Alma, WI 
738.1 Minneiska, MN 
728.5 3 above 
Winona, MN 
714.3 Trempealeau, 
WI 
702.5 Dresbach, MN 
679.2 Genoa, WI 
647.9 3.3 below 
Lynxville, WI 
615.1 Guttenberg, IA 
583.0 3.7 above 
Dubuque, IA 
556,7 Bellevue, IA 
522.5 4.3 above 
Clinton, IA 
493.3 3.7 below 
Le Claire, IA 
493.1 3.9 below 
Le Claire, IA 
482.9 Foot of Arsenal 
Island Rock 
Island, IL 
Lock and dam 457.2 1.8 above 
16 Muscatine, IA 
stone, mainly 
sandstone. 
No piles. 
56 400 26.94 750.0 13.7 10.3 Sandstone. No Sandstone. 
piles. 
56 400 35.94 725.1 13.54 10.1 Rock and piles Piles in gravel. 
56 400 35.9 - 12.57 7.6 in gravel. 
110 500 12.2 - 16.0 15.1 Piles in sand, Piles in sand, 
1106 6008 12.2 687.2 22.2 13.0 silt and clay. silt and clay. 
110 600 8.0 675.0 17.0 14.0 Piles in sand, Piles in sand. 
silt and clay. 
110 600 7.0 667.0 17.0 13.0 Piles in sand Piles in sand 
and gravel, and gravel. 
110 600 9.0 660.0 18.0 12.0 Piles in sand Piles in sand. 
and gravel. 
110 600 5.5 651.0 18.0 12.5 Piles in sand. Piles in sand. 
110 600 6.5 645.5 17.0 12.5 Piles in sand, Piles in sand 
gravel and and clay. 
silt. 
110 600 8.0 639.0 18.0 12.0 Piles in sand Piles in sand. 
and gravel. 
110 600 11.0 631.0 22.0 14.0 Piles in sand, Piles in sand 
gravel, and and gravel. 
broken rock. 
110 600 9.0 620.0 16.0 13.0 Piles in sand. Piles in sand. 
110 600 8.0 611.0 15.0 12.0 Piles in sand. Piles in sand. 
110 600 11.0 603.0 18.5 12.5 Piles in sand, Piles in sand. 
gravel and 
silt. 
110 600 9.0 592.0 17.0 13.0 Piles in sand Piles in sand 
and gravel, and gravel. 
110 600 11.0 583.0 19.0 13.0 Piles in sand, Piles in sand 
clay and and gravel. 
gravel. 
110 600 11.0 527.0 20.5 13.5 Rock. Rock. 
80 320 11.0 - 17.6 10.9 Rock. Rock. 
110 600 16.0 561.0 24.011 11.0 Rock. Rock. 
110 360 16.0 - 17.011 11.0 
110 600 9.0 545.0 17.0 12.0 Piles in sand 
and gravel. 
Piles in sand 
and gravel. 
100 1959 
100 
100 
100 
64 
100 
100 
57 
100 
100 
100 
100 
100 
99 
99 
100 
92 
100 
95 
1917 
1930 
1948 
1938 
1935 
1935 
1936 
1936 
1937 
1937 
1938 
1936 
1937 
1938 
1938 
1939 
1922 
1934 
12,382,0005 
2,358,0006 
6,492,0009 C
t'I 
8,706,000 
4,865,000* 
5,081,000* 
8,009,000* Z 
4,874,000 
C) 
0 
5,574,000* 
6,061,000* 
z 
6,539,000* z 
4,750,000* Z 
7,428,000 0r 
5,580,000 
7,502,000 z 
6,284,000
_10 
10,525,000 
98 1937 9,788,000 
TABLE 29-C 
to
m

TABLE 29-C (Cont'd) LOCKS AND DAMS 
Lock Dimensions 
Greatest Depth on Character of Foundation Percent 
Width Length Upper Miter Sill Complete 
Miles of Available Normal Locks, Year Estimated Cost of 
Above Chain- for Full Pool Dams, and Opened Each Lock and 
Ohio Miles from ber Width Lift Eleva- Upper Lower Work in to Navi- Dam Including 
Lock and Dam River Nearest Town (feet) (feet) (feet) tion' (feet) (feet) Lock Dam Pool gation Work in Pool 
Lock and dam 437.1 4.2 above New 110 600 8.0 536.0 16.0 13.0 Piles in sand Piles in sand. 99 19.39 $ 5,843,000 
17 Boston, IL and gravel. 
Lock and dam 410.5 6.5 above 110 600 9.8 528.0 16.5 13.7 Piles in sand. Piles in sand. 90 1937 10,308,000 
18 Burlington, 
IA 
Lock and dam 364.2 Keokuk, IA 110 358 38.2 518.2 4.5 9.2 Rock. Rock. 100 1913 
19 110 1,200 5.0 13.0 99 1957 14,813,00012 
Lock and dam 343.2 0.9 above 110 600 10.0 480.0 15.0 12.0 Rock. Rock and 97 1936 6,281,000 
20 Canton, MO piles in 
sand and 
gravel. 
Lock and dam 324.9 2.1 below 110 600 10.5 470.0 16.5 12.0 Piles in sand Piles in sand 95 1938 8,065,000 
21 Quincy, IL and gravel, and gravel. 
Lock and dam 301.2 1.5 below 110 600 10.2 459.5 18.0 13.8 Rock. Rock. 99 1938 5,275,000 
22 Saverton, MO 
Lock and dam 273.4 Clarksville, MO 110 600 15.0 449.0 19.0 12.0 Rock and piles. Piles in sand. 9914 1940 10,337,000 
24 
Lock and dam 241.4 Cap Au Gris, 110 600 15.0 434.0 19.0 12.0 Piles in sand Piles in sand 9914 1939 13,694,000 
25 MO and gravel. and gravel. 
Lock and dam 202.9 Alton, IL 110 600 24.0 419.0 19.0 10.0 Piles in sand. Piles and 100 1938 12,824,000 
26 (Henry T. 110 360 24.0 - 16.0 10.0 sand. 
Rainey Dam) 
New Lock and 200.8 Alton, IL 110 1,200 24.0 419.0 23.0 18.0 Piles to Piles to 56 - 747,480,000 
dam 26 bedrock. bedrock. 
New Lock and 200.8 Alton, IL 110 600 24.0 419.0 42.0 18.0 Piles to Piles to 2 - 214,000,000 
dam 26 (2nd bedrock. bedrock. 
Lock) 
Total, Locks 
and dams $ 1,189,921,000 
1. Elevation of pools 1 to 22 and at St. Anthony Falls are mean sea level 
1912 adjustment; pools 24, 26 are mean sea level 1929 adjustment. 
2. Includes existing dam, owned by Northern States Power Co. 
3. Includes dredging above upper lock. (Federal cost only.) 
4. Based on pool elevation 723.1 in pool 1 which is crest of dam. Pool 
is normally maintained at elevation 725.1 by flashboards. 
5. Includes lower approach dredging and dredging between upper and 
lower rock. (Federal cost only.) 
6. In addition $1,948,000 expended from previous projects and 
$1,349,600 from O & C appropriation for first of twin locks. Excludes lock 
and dam rehabilitation program. 
7. Old upper guard sill. 
8. Land ward lock. 
9. In addition, $1,965,300 expended from previous projects. 
10. Existing Le Claire Canal lock is used as auxiliary to lock 14: previous 
project cost $540,000. 
11. Depth over upper poiree sill. Depth over upper miter sill is 27 feet, 
at lock 15. 
12. $640,868 for first lock was reported by Mississippi River Power 
Company, transferred to Government free in lieu of improvements destroyed. 
(Annual Report, 1928, pp. 1118-1119.) Present estimate includes 
$13,132,600 for main lock and appurtenant work. 
13. Includes cash contribution of $3,950,000. 
14. Complete except for guidewall extensions. 
* Excludes uncompleted guidewall extensions $10,339,000 (1972) 
reclassified from active to inactive on April 13, 1973. 
tT1 
~T1 
tTl 
tTl 
CO 
T1

TABLE 29-D HARBOR IMPROVEMENTS
Project Approximate size (feet) Actual or 
Name Miles above Location Type depth Percent Estimated 
Ohio River (feet) Width Length Complete Cost 
Harriet Island Harbor, 840.2 In city of St. Paul, MN Small-boat 5 70 925 0 $ 283,0001 
St. Paul, MN 
St. Paul Harbor, MN 
Hastings Harbor, MN 
Red Wing Harbor, MN 
Red Wing Harbor, MN 
Bay City Harbor, WI 
Lake City Harbor, MN 
Pepin Harbor, WI 
Wabasha Harbor, MN 
Alma Harbor, WI 
Winona Harbors, MN 
Lansing Harbor, IA 
Prairie du Chien 
Harbor, WI 
Cassville Harbor, WI 
Dubuque Harbor, IA 
Savanna Harbor, IL 
Clinton Harbor, IA 
Moline Harbor, IL 
Davenport Harbor, IA 
(Lindsay Park) 
Rock Island Harbor, IL 
Andalusia Harbor, IL 
Muscatine Harbor, IA 
New Boston Harbor, IL 
Fort Madison Harbor, 
IA 
836.5-839.2 In city of St. Paul, MN 
839.7 Channel improvement, 
Small-boat harbor and 
channel enlargement. 
813.2 Lower end of city of 
Hastings, MN 
791.4 In city of Red Wing, MN 
791.1 In city of Red Wing, MN 
785.9 Upper end of Bay City, 
WI 
773.0 In city of Lake City, MN 
767.1 In city of Pepin, WI 
760.0 Upper end of city of 
Wabasha, MN 
751.3 Upper end of Alma, WI 
726.0 In city of Winona, MN 
Latsch Island 
726.2 Crooked Slough 
663.3 Upper end of city of 
Lansing, IA 
635.5 Upper end of city of 
Prairie du Chien, WI 
635.0 In Marais de St. Friol 
East Channel below 
Hwy bridges. 
606.6 At Cassville, WI 
579.4 At Dubuque, IA 
537.3 At Savanna, IL 
519.0 At Clinton, IA 
488.0 At Moline, IL 
484.2 At Lindsay Park 
479.8 
473.0 
455.5 
455.6 
433.1 
383.7 
At Rock Island, IL 
Andalusia Slough 
At Muscatine, IA 
In Boston Bay 
At Fort Madison, IA 
Commercial 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Small-boat 
Commercial4 
Small-boat 4 
Small-boat 
Small-boat 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Small-boat 
Small-boat 
Entrance channel 
small-boat harbor 
Small-boat 
Small-boat 
Freight terminal 
approach channel 
Small-boat 
Small-boat 
9 400-1,000 2.7(mile) 100 
300 400 100 
200 
300 
450 
50-100 
400 
500 
500 
50 
175-400 
300 
200 
200 
400 
400 
5 
12
5555 
120 
340 
280 
400 
230 
200 
500 100 
1,200 
800 
5,990 
600 
1,000 
850 
600 
800 
100 
100 
100 
100 
100 
100 
100 
100 
500 100 
1,000 100 
6,000 100 
800 100 
800 100 
1,000 
frontage 
565 
1,500 
910 
1,400 
660 
1,150 
100
0 
100
0 
78 
100 
100 1,100 100 
40 
150 
200 
90-135 
250 
435 
950 
1,890 
600 
900 
100 
100 
100
0 
100 
217,100 
230,200 
74,300 
146,8002 
8,700 
39,5003 6 
93,500 
1,007,0005 
205,5006 
41,700 
56,300 
89,800 t1 
84,700 
95,300 
C 85,000 0 
93,100 
z 
178,000 
55,200 
310,000 
101,912 Z 
110,328 Z 
262,100 
31,000 0 
21,000 
353,000 
Z 
23,000 
184,200

TABLE 29-D (Cont,d) HARBOR IMPROVEMENTS 
Miles above Project Approximate size (feet) Actual or 
Name OhioRive Location Type depth Percent Estimated 
(feet) Width Length Complete Cost 
Keokuk Harbor, IA 363.5 At Keokuk, IA Small-boat 5 100-600 1,015 0 394,000 
Warsaw Harbor, IL 359.1 At Warsaw, IL Small-boat 5 100 600 100 73,000 
Quincy Harbor, IL 327.3 In Quincy Bay Small-boat 5 200-300 9,000 0 7 
Hannibal Harbor, MO 308.8 At Hannibal, MO Small-boat 5 180-260 600 100 129,000 
Total $5,077,240 
1. In addition, local interests will contribute $283,000. 
2. In addition, local interests contributed $3,455. 
3. In addition, local interests contributed $9,533. 
4. Commercial harbor converted to small-boat harbor under authority 
of Section 107 of 1960 River and Harbor Act, as amended. Primary use 
is small-boat, although some commercial activity exists. 
5. In addition, local interests contributed $812,559. 
6. In addition, local interests contributed $32,344. 
7. Maintenance only, estimated at $5,000 annually. 
0000 
t!1 
0
0
C) 
O
~T1 
0
tTI 
tTl 
O
j
tTl 
z
rr 
CD 
00

MISSISSIPPI RIVER BETWEEN MISSOURI AND MINNEAPOLIS, MN 
TABLE 29-E 
ADDITIONAL FEATURES ENTERING INTO 
COST OF PROJECT 
Facilities for public use, convenience and safety 
Rectification of damages caused by seepage and backwater 
Regulating works between lock and dam 26 (Henry T. Rainey 
Dam) and Missouri River 
Improvement of Beaver Slough at Clinton, Iowa, for navigation 
Miscellaneous 
Total additional features 
Total existing project (new work) 
$ 5,304,900 
8,152,800 
545,000 
193,600 
1,312,9002 
14,613,1003 
$468,584,858 
1. Includes a lump-sum payment of $2,146,800 (O&M appropriation) 
paid to the Sny Island Levee Drainage District, IL, for rectification of 
seepage damages. Also includes $140,000 Construction General funds for 
project studies, evaluation, and report preparation. 
2. Includes $686,500 for repairs to Stone Arch bridge, Minneapolis, MN. 
(FY 1969) 
3. Excludes $227,000 (1965) for inactive remedial measures at Sandy 
Slough, MO. 
LICENSE FEES COLLECTED 
TABLE 29-F THROUGH FISCAL YEAR 1986
Annual Collections to 
Dam Licensee Charge Sept. 30, 1986 
St. Anthony Falls Lower Northern States Power $ 3,300 $ 80,077 
Lock and Dam Co. (No. 2056) 
Lock and Dam No. 1 Ford Motor Co. 95,400 5,821,440 
Total project (No. 362) $5,901,517 
29-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 29-G AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sep. 22, 1922 
July 3, 1930 as 
amended by P.R. 
No. 10, Feb. 24, 
1932 
June 26, 1934 
Aug. 30, 1935 
Aug. 26, 1937 
Aug. 30, 1935 
Aug. 26, 1937 
Dec. 22, 1944 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
None 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 24, 1946 
June 30, 1948 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
Sep. 3, 1954 
Sep. 3, 1954 
July 3, 1958 
July 3, 1958 
MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND 
MINNEAPOLIS, MN 
Dredging channels to landing places. 
Project adopted from Illinois River to Minneapolis; Chief of 
Engineers granted discretionary authority to make such 
modification in plan as may be deemed advisable. 
Operation of snag boats and operation and care of locks and dams 
to be provided for with funds from Department of the Army 
appropriations for rivers and harbors. 
Missouri River established as lower limit of project. 
Extension of 9-foot channel above St. Anthony Falls, MN, 
including adequate terminal facilities for Minneapolis, MN 
St. Paul, MN harbor. 
Determine damages to drainage and levee districts caused by 
seepage and backwater, and cost of making rectification thereof. 
Public park and recreational facilities. 
Red Wing, MN harbor. 
Remedial works to correct damages caused by seepage and 
backwater at Cochrane, WI 
Such changes or additions to payments, remedial works, or land 
acquisitions authorized by River and Harbor Act of Aug. 26, 
1937 (River and Harbor Committee Doc. 34, 75th Cong., 1st 
sess.), as Chief of Engineers deems advisable. 
St. Paul, MN, channel enlargements, small boat harbor, and 
roadway. 
Vertical bridge clearance at Minneapolis to 26 feet above 
estimated stage for discharge of 40,000 c.f.s. 
Winona, MN basin. 
Future modification of lock and dam No. 2 for power 
development. 
Provides for cash contribution by local interests in lieu of 
alteration of privately owned bridges and utilities for St. 
Anthony Falls project. 
Lake City, MN harbor. 
Wabasha, MN harbor. 
Payment of damages caused by backwater and seepage, pools 3 
to 11. 
Hastings, MN harbor. 
Lansing, IA harbor. 
Fort Madison, IA harbor. 
Payment of damages caused by pool No. 14 at Clinton, IA. 
Davenport, IA harbor. 
Muscatine, IA harbor. 
Alma, WI harbor. 
Hannibal, MO harbor. 
Prairie du Chien, WI harbors. 
Opposite Hamburg, IL harbor.1 
Permits such change in location of Winona, MN small boat basin 
authorized by River and Harbor Act of Mar. 2, 1945 (H. Doc. 
263, 77th Cong., 1st sess.), as Chief of Engineers deems advisable. 
Construction of Crooked Slough Harbor at Winona, MN, in lieu 
of previously authorized commercial harbor. 
Payment of damages caused by pool No. 24 at Louisiana, MO. 
Permits modification of vertical bridge clearances and authorizes 
completion of St. Anthony Falls project. 
Small boat and commercial harbors at Alton, IL.2 
None 
H. Doc. 290, 71st Cong., 2d sess. 
None 
H. Co. 137, 72nd Cong., 1st sess. 
H. Doc. 137, 72nd Cong. 1st 
sess. 
Rivers and Harbors Committee 
Doc. 44, 74th Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 34, 75th Cong., 1st sess. 
None 
H. Doc. 103, 76th Cong., 1st 
sess. 
H. Doc. 137, 76th Cong., 1st 
sess. 
None 
H. Doc. 547, 76th Cong., 3rd 
sess. 
S. Doc. 54, 77th Cong., 1st sess. 
H. Doc. 263, 77th Cong., 1st 
sess. 
H. Doc. 432, 77th Cong., 1st 
sess. 
H. Doc. 449, 78th Cong., 2d sess. 
H. Doc. 511, 79th Cong., 2d sess. 
H. Doc. 514, 79th Cong., 2d sess. 
H. Doc. 515, 79th Cong., 2d sess. 
H. Doc. 559, 79th Cong., 2d sess. 
S. Doc. 192, 79th Cong., 2d sess. 
H. Doc. 661, 80th Cong. 2d sess. 
S. Doc. 197, 80th Cong., 2d sess. 
H. Doc. 642, 80th Cong., 2d sess. 
H. Doc. 733, 80th Cong., 2d sess. 
H. Doc. 66, 81st Cong., 1st sess. 
H. Doc. 67, 81st Cong., 1st sess. 
H. Doc. 71, 81st Cong., 1st sess. 
H. Doc. 254, 81st Cong., 1st sess. 
None 
H. Doc. 347, 83rd Cong., 2d 
sess. 
H. Doc. 251, 82nd Cong., 1st 
sess. 
H. Doc. 33, 85th Cong., 1st sess. 
H. Doc. 136, 84th Cong., 1st sess. 
29-10

MISSISSIPPI RIVER BETWEEN MISSOURI AND MINNEAPOLIS, MN 
TABLE 29-G (Cont'd) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 Payment of lump sum amounts for damages to drainage and levee H. Doc. 135, 84th Cong., 1st 
districts caused by operation of navigation pools. sess. 
July 3, 1958 Improvement and maintenance of Beaver Slough at Clinton, IA. H. Doc. 345, 84th Cong., 2d sess. 
Mar. 3, 1909 Reconstruction of structures as may be necessary to provide None 
adequate facilities for existing navigation. 
July 14, 1960 Construction of Industrial Harbor at Red Wing, MN. H. Doc. 32, 86th Cong., 1st sess. 
Oct. 23, 1962 Construction of small-boat harbors at Savanna,1 Moline, H. Doc. 513, 87th Cong., 2d sess. 
Andalusia, New Boston,1 Warsaw, Quincy, and Grafton, IL; 
Bellevue,' Clinton, Davenport, and Keokuk, IA; St. Paul 
(Harriet Island), MN; and Bay City, Pepin, and Cassville,' WI. 
Oct. 23, 1962 Payment of damages caused by pool 24 at Clarksville, MO. H. Doc. 552, 87th Cong., 2d sess. 
Oct. 23, 1962 Remedial works at Sandy Slough, MO. H. Doc. 419, 87th Cong., 2d sess. 
Nov. 7, 1966 Repair of Stone Arch bridge at Minneapolis, MN. None 
Nov. 7, 1966 Commercial Harbor facilities at Fort Madison, IA.3 H. Doc. 507, 89th Cong., 2d sess. 
Oct. 21, 1978 Replacement of Lock and Dam 26 Public Law 95-502 
1. Deferred. 
2. Inactive. 
3. Deauthorized FY 86. 
29-11

CHICAGO, ILLINOIS, DISTRICT *
This district comprises Cook, McHenry, Lake, Kane, Porter Counties in Indiana, including a portion of 
DuPage and Will Counties in Illinois, and Lake and LaPorte County along Lake Michigan. 
IMPROVEMENTS 
Navigation Page 
1. Burns Waterway Harbor, IN ........... 30-2 
2. Calumet Harbor and River, IL and IN ... 30-2 
3. Chicago Harbor, IL ................... 30-3 
4. Chicago River, IL ..................... 30-3 
5. Indiana Harbor, IN .................. 30-4 
6. Michigan City Harbor, IN ............... 30-5 
7. Waukegan Harbor, IL ................... 30-5 
8. Reconnaissance and Condition Surveys .. 30-6 
9. Navigation Work Under Special 
Authorization ...................... 30-6 
Alteration of Bridges 
10. Other Authorized Bridge Alteration ...... 30-6 
Beach Erosion Control 
11. Indiana Dunes National Lakeshore 
Bank Protection 
Beverly Shores, IN .................. 30-6 
TABLES 
30-A 
30-B 
30-C 
30-D 
30-E 
30-F 
30-G 
Page 
12. Other Authorized Beach Erosion Control 
Projects ............................. 30-6 
13. Beach Erosion Control Under Special 
Authorization ......................... 30-6 
Flood Control 
14. Chicago River, IL (North Branch) ....... 30-6 
15. Lake Michigan, Edgewater/Rogers Park 
Communities, Chicago, IL ........... 30-7 
16. Other Authorized Flood Control Projects . 30-7 
17. Flood Control Work Under Special 
Authorization ....................... 30-7 
General Investigations 
18. Surveys .... .......................... 
19. Collection and Study of Basic Data ...... 
20. Research and Development .............. 
21. National Emergency Preparedness ...... 
TITLE 
30-8 
30-8 
30-8 
30-8 
PAGE 
Cost and Financial Statement ....................... 30-9-10 
Authorizing Legislation ................................. 30-11-12-13 
Existing Projects ..................................... 30-14 
Other Authorized Bridge Alteration ........................ 30-15 
Other Authorized Beach Erosion Projects ................. 30-15 
Other Authorized Flood Control Projects ................. 30-15 
Reconnaissance and Condition Survey .................... 30-15 
30-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. BURNS WATERWAY HARBOR, IN 
Location. Northwestern Indiana, on the southern 
shore of Lake Michigan in Porter County, 28 miles southeast 
of Chicago harbor. (see NOAA Nautical Charts 
Numbers 14905 and 14926). 
Existing Project. Provides for (a) north breakwater 
4,646 feet long; (b) an outer west bulkhead 1,176 
feet long; (c) a west bulkhead shore connection 2,300 
feet long; (d) an approach channel 30 feet deep and 400 
feet wide; (e) an outer harbor 28 feet deep; (f) an east 
harbor arm 27 feet deep and 620 feet wide; (g) a west 
harbor arm 27 feet deep and 620 feet wide. The project 
was authorized by the River and Harbor Act of 27 
October 1965 (Public Law 89-298; House Document 
Number 160, 88th Congress, 1st Session). The authorizing 
act also provided the Secretary of the Army to 
reimburse The State of Indiana for expenditure of 
funds used to construct such portions of the project 
as approved by the Chief of Engineers and constructed 
under supervision of the Chief of Engineers. See table 
30-C. 
Local Cooperation. Fully complied with. 
Terminal Facilities. Seven berths and docks are 
available, three on the west harbor arm, one on the 
harbor basin, and three on the east harbor arm. One 
dock on the west harbor arm is used for shipment and 
receipt of steel products. One dock on the east harbor 
arm is used for receipt of iron ore pellets and limestone 
and shipment of steel products. Five facilities 
are administered by the Indiana Port Commission 
and are used for handling general cargo. 
Operations and results during period. Maintenance: 
Condition surveys performed by Detroit 
District were credited $6,393 for prior year work. A 
shore erosion study was completed by hired labor at a 
cost of $3,465. Plans and specifications were developed 
by hired labor for an emergency stone placement at 
the north breakwater at a cost of $13,361. The stone 
placement was performed by Detroit District at a cost 
of $154,007. Program management for these activities 
was performed by hired labor at a cost of $5,152. 
Condition at end of fiscal year. The existing 
project is complete. Total costs of existing project to 
September 30, 1986 were $17,554,591 of which $13,599,900 
was for new work ($13,584,000 Federal and $15,900 
non-Federal), and $3,954,691 for maintenance. 
2. CALUMET HARBOR AND RIVER, 
IL and IN 
Location. Northeastern Illinois, on the southwest 
shore of Lake Michigan in Cook County, 15 miles south 
of Chicago Harbor, within corporate limits of the city 
of Chicago, except for breakwaters, an approach 
channel and an anchorage area which are in Illinois 
and Indiana. (See NOAA Nautical Charts Numbers 
14926 and 14929). 
Previous projects. For details see page 1400 of 
Annual Report for 1962. 
Existing Project. Provides for (a) a stone filled 
timber crib breakwater 6,714 feet long; (b) a stone filled 
double row steel sheet pile detached breakwater 5,007 
feet long; (c) a north pier 2,450 feet long; (d) an approach 
channel 29 feet deep and 3,200 feet wide; (e) an outer 
harbor anchorage area 28 feet deep and 3,000 feet wide; 
(f) an entrance channel 27 feet deep and 230 to 290 feet 
wide; (g) a channel in the Calumet River 27 feet deep 
and at least 200 feet wide to the north side of 130th street; 
(h) three turning basins designated as numbers 1,3 and 
5; (i) a channel extending into Lake Calumet at a width 
of about 1,000 feet. The project was authorized by the 
River and Harbor Acts of 3 March 1899, 13 June 1902, 
30 August 1935, 14 July 1960, 23 October 1962, and 27 
October 1965. See table 30-C. 
Local Cooperation. Fully complied with. 
Terminal facilities. Thirty six docks, wharves, 
and terminals are available. The Chicago Regional 
Port District owns four wharves, two grain elevators, 
one dock, and one terminal. The United States Government 
owns one stone dock. The most important cargoes 
handled are iron ores and concentrates, coal, and lignite. 
Operations and results during period. Maintenance: 
Condition surveys were performed by Detroit 
District at a cost of $17,203. Plans and Specifications 
of the damaged southerly exterior breakwater were 
developed by hired labor at a cost of $17,795. Breakwater 
stone was purchased by contract at a cost of 
$257,080. Emergency placement by Detroit District 
(Cranebarge Manitowoc) of 5,600 tons of stone at the 
damaged breakwater was completed at a cost of 
$144,962. A major rehabilitation reconnaissance report 
was completed at a cost of $88,931. A previous 
year dredging contract was completed at a cost of $5,572. 
Water quality work was performed by hired labor at a 
cost of $3,397. A groundwater monitoring program was 
continued at the Chicago Area Confined Disposal 
Facility by hired labor at a cost of $78,008, and by contract 
at a cost of $282,194. Support by other Corps for 
groundwater monitoring amounted to $5,700. An O&M 
manual was continued for the CDF at a cost of $887. 
A boundary survey was performed by hired labor at a 
cost of $6,663. A demonstration dredging study was 
continued by St. Paul District (hydraulic Dredge 
Dubuque) at a cost of $340,178, by hired labor at a 
cost of $15,888, and by contract at a cost of $8,477. A 
CDF fence survey was performed by contract at a cost 
of $10,154 and by hired labor at a cost of $6,577. A 
previous year dredging contract was credited $6,000 
for damages. Value engineering was debited $52,250. 
Supervision and contract administration were performed 
by hired labor at a cost of $33,968 and program 
management was performed by hired labor at a cost of 
$28,046. Under the dike disposal program, an O&M 
manual was completed at a cost of $63, and value 
engineering was debited $1,463. 
30-2

CHICAGO, IL, DISTRICT 
Condition at end of fiscal year. The existing 
project is 79% complete. Work remaining to be accomplished 
consists of widening and straightening 
the Calumet River in the vicinity of 106th Street, and 
the inactive portion which consists of closing the gap 
between the breakwaters, and dredging minor shoals 
in the outer harbor. 
Total costs of existing project to September 30, 1986 
were $47,075,334, of which $21,722,594 was for new 
work ($18,685,991 regular funds and $3,036,603 public 
works funds), $23,827,072 regular runds for maintenance, 
$836,667 non-Federal funds for maintenance, 
and $689,001 regular funds for rehabilitation. 
3. CHICAGO HARBOR, IL 
Location. Northeastern Illinois on the southwest 
shore of Lake Michigan in Cook County, within the 
corporate limits of the City of Chicago, (See NOAA 
Nautical Charts Numbers 14926, 14927, and 14928). 
Previous projects. See page 1396 of Annual 
Report for 1962. 
Existing Project. Provides for (a) a stone filled 
timber crib shore arm extension breakwater 2,250 feet 
long; (b) a stone filled timber crib exterior breakwater 
5,421 feet long; (c) a rubber-mound and stone filled 
concrete caisson southerly extension to the exterior 
breakwater 4,944 feet long, exclusive of 582 foot entrance 
gap enclosing an outer basin of about 970 acres; 
(d) a stone filled timber crib north pier 960 feet long; 
(e) a stone filled timber crib north inner breakwater 
4,034 feet long with a 304 foot shore return, and a 754 
foot gap; (f) a stone filled timber crib south inner breakwater 
2,544 feet long enclosing an inner basin of approximately 
224 acres; (g) a lake approach channel 29 
feet deep and 800 feet wide; (h) a channel and maneuver 
area inside the exterior breakwater and exterior breakwater 
southerly extension 28 feet deep with a maximum 
width of 1,300 feet; (i) an inner basin 21 feet deep; (j) an 
entrance channel 21 feet deep. The project was authorized 
by the River and Harbor Acts of 11 July 1870, 14 June 
1880, 3 March 1899, 25 July 1912, 2 March 1919 and 23 
October 1962. See table 30-C. 
The Chicago Lock was constructed in 1938 by the 
Metropolitan Sanitary District of Greater Chicago. 
The deep draft lock is 600 feet long, 80 feet wide, and 
23 feet deep and uses a steel cellular design. Operation 
and maintenance responsibilities in the interests of 
navigation were transferred to the Federal Government, 
pursuant to Public Law 98-63, approved 30 July 
1983, Section 107 of the Public Law 97-88, and Memorandum 
of Agreement between the Department of the 
Army and the Metropolitan Sanitary District of Greater 
Chicago. 
Local Cooperation. Fully complied with. 
Terminal facilities. There are three docks, two 
for passenger excursion boats and one for cargo. The 
most important cargoes handled are sugar and nonmetallic 
minerals. 
Operations and results during period. Maintenance: 
Condition surveys and breakwater surveys 
were performed by other Corps at a cost of $24,646. A 
boundary survey was performed by hired labor at a 
cost of $6,080, and by contract at a cost of $54,474. 
The breakwater planning appraisal study was continued 
by hired labor at a cost of $31,922. A lock operations 
contract was continued with International Research 
and Development, Inc. for $404,590. Other 
Corps support for operations of the lock amounted to 
$31,279. A geotechnical stability study of the lock was 
performed by hired labor at a cost of $14,978. Plans 
and specifications of the lock electrical system was 
performed by hired labor at a cost of$183,030. Periodic 
Inspections of the lock continued at a cost of $76,652. 
Lock supplies were purchased at a cost of $10,931. Replacement 
of the bubbler system was performed by 
contract at a cost of $16,751. Emergency gate repairs 
were performed by contract at a cost of $17,900. Investigation 
of the North Pier and Foundation Exploration 
were performed by contract at a cost of $93,362, 
and by hired labor at a cost of $8,642. Water control 
activities were performed by hired labor at a cost of 
$12,188, and by contract at a cost of $27,353. Engineering 
and design for a dredge project was performed 
by hired labor at a cost of $17,359. Dredging to remove 
31,000 cubic yards of shoaling was performed by contract 
at a cost of $347,250. Value engineering was 
debited in the amount of $18,457. Contract administration 
and program management for these activities 
were performed by hired labor at a cost of $67,265 and 
$23,045, respectively. 
Condition at end of fiscal year. The existing 
project is complete. Total costs of existing project to 
September 30, 1986 were $15,854,649, of which $4,342,822 
was for new work, $10,185,227 for maintenance, and 
$1,326,600 for rehabilitation. 
4. CHICAGO RIVER, IL 
Location. Northeastern Illinois, in Cook County 
within the corporate limits of the city of Chicago. (See 
NOAA Nautical Charts Numbers 14926, 14927 and 
14928). 
Previous projects. See page 1394 of Annual 
Report for 1962. 
Existing Project. Provides for (a) a channel 21 
feet deep in the main river from its mouth at Rush 
Street to the junction of the North and South Branches 
(0.7 miles); (b) a channel 21 feet deep in the North 
Branch from the junction to North Avenue (2.22 miles); 
(c) a channel 21 feet deep in the North Branch Canal 
(1.04 miles); (d) a 21 foot deep North Branch Turning 
Basin just south of North Avenue; (e) a channel 9 feet 
deep in the North Branch from North Avenue to 
Addison Street. All dredging to within 20 feet of existing 
docks. The project was authorized by the River 
and Harbor Acts of 3 March 1899, 13 June 1902, 2 
March 1907, and 24 July 1946. Portion of project 
authorized by River and Harbor Act of 1946 is in deferred-
for-restudy category. See table 30-C. 
30-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Local Cooperation. Fully complied with for completed 
modifications. River and Harbor Act of 24 July 
1946 which provided improvement of channel is subject 
to condition that local interests furnish assurances they 
will hold the United States free from damages which 
may result from construction and maintenance of improvement. 
Requirement has not been complied with. 
Terminal Facilities. Six docks are available. 
The most important cargoes handled are sand, gravel 
and crushed rock. 
Operations and results during period. Maintenance: 
Condition surveys were performed by Detroit 
District at a cost of $7,548. Environmental Impact 
Statement was developed by hired labor at a cost of 
$97,918. Under the Lake Michigan Water Diversion 
monitoring program, data collection of water control 
and water quality activities were performed by hired 
labor at a cost of $260,385, by other Corps at a cost of 
$38,009, by contract at a cost of $68,561 and by other 
Government at a cost of $54,974. Engineering and 
design for a dredging project was performed by hired 
labor at a cost of $21,634. Dredging to remove 31,000 
cubic yards of shoaling was performed by contract at 
a cost of $347,250. Supply and maintenance costs 
were $6,044. Supervision and contract administration 
for these activities were performed by hired labor at a 
cost of $30,225, and project management was performed 
by hired labor at a cost of $8,968. 
Condition at end of fiscal year. The project is 
complete except for dredging the channel between 
North Avenue and Addison Street as authorized by 
1946 River and Harbor Act. Head of navigation for 
deep draft vessels are North Avenue, 5.97 miles from 
Michigan Avenue Bridge. 
Total costs of existing project to September 30, 1986 
were $8,979,519 of which $544,679 was for new work 
and $8,434,840 was for maintenance. 
5. INDIANA HARBOR, IN 
Location. Northwestern Indiana, on the southwest 
shore of Lake Michigan in Lake County, 19 miles 
southeast of Chicago Harbor. (See NOAA Nautical 
Charts Numbers 14926 and 14929). 
Previous projects. For details see page 1943 of 
Annual Report for 1915, and page 1520 of Annual 
Report for 1938. 
Existing Project. Provides for (a) northerly rubblemound 
breakwater 1,120 feet long; (b) an easterly concrete 
capped concrete caisson breakwater 201 feet long 
with a rubble mound extention 2,324 feet long; (c) a 
lake approach channel 29 feet deep and 800 feet wide; 
(d) an anchorage and maneuver basin 28 feet deep; (e) 
a canal entrance channel 27 feet deep and 280 feet wide; 
(f) a main canal 22 feet deep; (g) a turning basin 22 feet 
deep; (h) the Forks Turning Basin 22 feet deep; (i) the 
Lake George Branch 22 feet deep; (j) the Calumet River 
Branch 22 feet deep. The project was authorized by the 
River and Harbor Acts of 4 March 1913, 2 March 1919, 
20 March 1922, 3 July 1930, 30 August 1935, 26 August 
1937, and 14 July 1960. See table 30-C. 
Local Cooperation. Act of 1937 provides enlargement 
of Indiana Harbor Canal shall not be undertaken 
until local interests furnish a right-of-way 300 feet 
wide and construct substantial bulkheads along channel 
on established lines shown on map accompanying 
Rivers and Harbors Committee Document 13, 75th 
Congress, 1st session, provided that improvement on 
one side may proceed in any section on fulfillment 
of conditions for that side of section, and provided 
further, that south of turning basis at The Forks 
(beginning 450 feet south of intersection of present 
Calumet Branch and mainstem bulkhead lines), widening 
and deepening by the United States shall be 
done only as rights-of-way and bulkheads on at least 
one side of the channel are continuously provided 
southward from above limit of turning basin at The 
Forks. To provide for 300-foot channel, a parcel of land 
(of about 4.6 acres), generally 100 feet wide, lying on 
east side of Calumet River Branch, commencing at 
north side of 141st Street and extending northward 
toward The Forks for about 2,170 feet, has been conveyed 
to and accepted by the United States. Local 
interests constructed about 1,350 feet of bulkhead 
along east side of Calumet River Branch, and reconstructed 
bulkhead on west side from The Forks to 
141st Street. Defense Plant Corp. built a bulkhead 
along east side of canal between Pennsylvania Railroad 
Co.'s bridge and Dickey Place Bridge; the United 
States widened and deepened east side of this portion 
of widening. Youngstown Sheet and Tube Co. constructed 
a bulkhead along west side of canal between 
Indiana Harbor Belt Railroad Co. bridge and the 
Pennsylvania Railroad Co. bridge, and the United 
States widened and deepened west side of this portion 
of widening. All prior requirements fully complied with. 
Terminal Facilities. Fifteen docks and wharves 
are available. Six docks for handling iron ore and 
limestone. Six docks for handling petroleum products. 
Three docks for handling gypsum, scrap metal and 
steel, and bulk products. 
Operations and results during period. Maintenance: 
Engineering services for an Environmental 
Impact Statement associated with a confined disposal 
facility were completed at a cost of $142,186. Engineering 
and design for a confined disposal facility 
were continued by hired labor at a cost of $259,906 and 
by other Corps and Government Agencies at a cost of 
$3,296. Architectural and mapping of a confined disposal 
facility were performed by contract at a cost of 
$42,628. A research and development program was 
continued with the Waterway Experiment Station at a 
cost of $235,687. Monitoring of this activity was performed 
by hired labor at a cost of $18,540. 15,000 tons 
of riprap stone was purchased at a cost of $507,803. 
Program management and contract administration 
for these activities were performed by hired labor 
at a cost of $14,347. 
30-4

CHICAGO, IL, DISTRICT 
Condition at end of fiscal year. The existing 
project is complete. Total costs of existing project to 
September 30, 1986 were $13,063,082, of which $11,432,541 
was Regular Funds, $1,618,041 was Public Works 
Funds, and $12,500 was Contributed Funds. Of the 
total cost, $4,848,980 was for new work and $8,214,102 
was for maintenance. 
6. MICHIGAN CITY HARBOR, IN 
Location. Northwestern Indiana, on the southeast 
shore of Lake Michigan in LaPorte County, 38 
miles southeast of Chicago Harbor. (See NOAA Nautical 
Charts Numbers 14905 and 14926). 
Previous projects. See page 1407 of Annual 
Report for 1962. 
Existing Project. Provides for (a) a stone filled 
timber crib detached breakwater 1,304 feet long; (b) a 
pile and steel sheeting west pier 835 feet long; (c) a 
stone filled timber crib, pile and steel sheeting east 
pier 2,276 feet long; (d) a stone filled timber crib east 
breakwater 1,000 feet long; (e) an entrance channel 18 
feet deep and 425 feet wide; (f) a turning basin 18 feet 
deep; (g) a channel in Trail Creek 18 feet deep; (h) a 
turning basin 18 feet deep; (i) an outer basin 12 feet 
deep; (j) an outer basin 8 feet deep; (k) a channel in 
Trail Creek 6 feet deep and 50 feet wide. The project 
was authorized by the River and Harbor Acts of 3 
March 1889, 3 March 1905, 21 January 1927, 30 August 
1935, and Section 107 of 14 July 1960 approved on 
30 September 1966. See table 30-C. 
Local Cooperation. Fully complied with. 
Terminal Facilities. There are several marinas 
in the lower mile of Trail Creek. The commodity 
handled at this harbor is fresh fish. 
Operations and results during period. Maintenance: 
Plans and specifications for maintenance 
dredging of the entrance channel was initiated by 
hired labor at a cost of $19,746. Program management 
cost was $2,738. 
Condition at end of fiscal year. The existing 
project is complete. Total costs of existing project to 
September 30, 1986 were $7,568,723 of which $1,287,057 
was for new work ($1,256,257 Federal and $30,800 
non-Federal funds), $4,662,996 for maintenance, and 
$1,618,670 for rehabilitation. 
7. WAUKEGAN HARBOR, IL 
Location. Northeastern Illinois, on the southwest 
shore of Lake Michigan in Lake County, 38 miles 
north of Chicago Harbor. (See NOAA Nautical Charts 
Numbers 14904 and 14905). 
Previous projects. See page 1392 of Annual 
Report for 1962. 
Existing Project. Provides for (a) a northerly 
stone filled timber crib breakwater 588 feet long; (b) a 
stone filled reinforced concrete caisson shore connection 
270 feet long; (c) a stone filled double row steel 
sheeting shore connection 640 feet long; (d) a single 
row steel sheeting shore connection 398 feet long; (e) 
a stone filled timber crib north pier 998 feet long; (f) a 
single row steel sheet piling north pier 444 feet long; 
(g) a steel piling revetment 632 feet long; (h) a stone 
filled timber crib south pier 1,399 feet long; (i) a stone 
filled double row pile and sheeting south pier 1,712 
feet long; (j) an entrance channel 22 feet deep and 390 
feet wide; (k) a channel between the piers 18 feet deep 
and 200 feet wide; (1) an inner basin 13 feet deep; (m) an 
anchorage area in the southwest corner of the inner 
basin 8 feet deep. The project was authorized by the 
River and Harbor Acts of 13 June 1902, 3 July 1930, 
and 2 March 1945. See table 30-C. 
Local Cooperation. Fully complied with. 
Terminal Facilities. Four docks are available. 
The commodities handled at this harbor are gypsum 
and building cement. 
Operations and results during period. Maintenance: 
Condition surveys were performed by Detroit 
District at a cost of $10,170. Environment dredging 
studies and monitoring activities were performed by 
hired labor at a cost of $3,839 and by contract at a 
cost of $2,563. Water quality activities were performed 
by hired labor at a cost of $9,513. Inspection and 
reports were credited for $2,414. Engineering services 
for maintenance and repair of the North Pier were performed 
by hired labor at a cost of $13,446 and by contract 
at a cost of $351,952. Supervision and contract 
administration were performed by hired labor at a 
cost of $50,577. Plans and specifications for a dredging 
project were developed by hired labor at a cost of 
$25,003. FY 1985 dredging contract was completed at 
a cost of $150,248. Supervision and contract admiinistration 
for this project were $30,998. Engineering 
services for a south pier inspection report were completed 
by hired labor at a cost of $3,624. Program 
Management was performed by hired labor at a cost 
of $22,572. 
Under the dike disposal program: Engineering and 
design were developed by hired labor at a cost of 
$80,235. Program management of these activities was 
performed by hired labor at a cost of $676. 
Condition at end of fiscal year. The existing 
project is complete except for the 1970 modification 
which is inactive. Total costs of existing project to 
September 30, 1986 were $6,346,915, of which $604,793 
was for new work and $5,742,122 was for maintenance. 
30-5

-REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
8. RECONNAISSANCE AND 
CONDITION SURVEYS 
Condition surveys were performed by the Detroit 
District at a cost of $76,629 (see table 30-G for project 
cost). Project maps were printed by Government 
Printing Office at a cost of $20,623. Quarry testing 
was performed by other Corps at a cost of $4,401. Aerial 
photos were performed by contract at a cost of $32,516. 
Office supplies were purchased at a cost of $4,760. 
Engineering services for these activities were $17,034 
and real estate services were $2,864. Water quality 
studies and analyses were performed by hired labor at 
a cost of $19,224 and by contract at a cost of $13,847. 
Inspection and reports were performed by hired labor 
at a cost of $32,788. Program management for these 
activities were performed by hired labor at a cost of 
$54,079. 
9. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Small Navigation Projects Not Specifically Authorized 
by Congress (Sec. 107 of the River and Harbor 
Act of 1960, as amended, Public Law 645, 86th Congress). 
Fiscal Year Costs 
Project and Location to September 30, 1986 
SBH Burns Waterway, IN $107,727 
Lake Mich. No. Shore Channel, IL 7,500 
Lake Mich. No. Chicago, IL 7,500 
Lake Calumet SBH, IL 23,226 
Michigan City Harbor, IN 9,514 
Alteration of Bridges 
10. OTHER AUTHORIZED 
ALTERATION 
BRIDGE 
See table 30-D. 
Beach Erosion Control 
11. INDIANA DUNES NATIONAL 
LAKESHORE BANK PROTECTION, 
BEVERLY SHORES, IN 
Location. Northwestern Indiana, on the southeast 
shore of Lake Michigan in Porter County, approximately 
35 miles southeast of Chicago Harbor. 
(See NOAA Nautical Charts Numbers 14905 and 
14926). 
Existing Project. Provides for 13,000 feet of stone 
revetment and periodic repair of rip rap to maintain 
the full length of beach front at Beverly Shores, Indiana. 
The current project was authorized by Public Law 
97-88 and Public Law 98-63. 
Local Cooperation. Fully complied with. 
Operations and results during period. No work 
was performed in FY 86. 
Condition at end of fiscal year. Total costs of 
existing project to 30 September 1986 were $660,000 
for new work. 
12. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
See table 30-E. 
13. BEACH EROSION CONTROL 
UNDER SPECIAL 
AUTHORIZATION 
Beach erosion control activities pursuant to section 
103 of the River and Harbor Act of 1962, as amended. 
Project and Location 
Langdon Park, Wilmette, IL 
Lloyd Park, Winnetka, IL 
Fiscal Year Costs 
to September 30,1986 
$1,869 
6,941 
Flood Control 
14. CHICAGO RIVER, IL (NORTH 
BRANCH) 
Location Northern Illinois, in Cook and Lake Counties. 
Existing Project. Provides for clearing the channel 
of the North Branch of the Chicago River, Illinois, of 
fallen trees, roots, and other debris and objects which 
contribute to the flooding, unsightliness, and pollution 
of the river. The project extends from Wolf Point in 
Chicago, Illinois, to its source just south of Rockland 
Road east of Libertyville, Illinois. The project was 
authorized by the River and Harbor Act of 31 December 
1970 (Section 116) and amended by the River 
and Harbor Act of 7 March 1974. 
Local Cooperation. The 1970 Act provided that 
local interests furnish without cost to the United 
States all lands, easements, rights-of-way, and disposal 
areas necessary for construction of the project; 
hold and save the United States free from damages 
due to construction; maintain and operate all works 
after completion without cost to the United States; 
and agree to bear all cost in excess of $200,000 for 
completing construction. Assurance of local cooperation 
for this act was approved on 31 July 1972. The 
1974 Act provided that the United States will maintain 
the channel free of trees, roots, debris and objects 
at a cost not to exceed $150,000 per year with non- 
Federal interests paying 25 per centum of the cost of 
maintenance. 
30-6

CHICAGO, IL, DISTRICT 
Operations and results during period. Maintenance: 
Engineering and design for 1983 clean-up 
work was credited $15,451 due to final cost allocation. 
Federal funds in the amount of $15,962 were expended 
for the 1985 debris removal project for snagging and 
clearing. Supervision and contract administration 
were performed by hired labor at a cost of $2,041. 
Contributed funds from the local sponsor, Metropolitan 
Sanitary District of Greater Chicago were expended 
in the amount of $7,637 for the 1983 project and $18,821 
for the 1985 project. For the 1984 project: Engineering 
and design were performed by hired labor at a cost of 
$6,270. Supervision and Inspection were performed 
by hired labor at a cost of $6,675. For the channel 
excavation and bank stabilization project, engineering 
and design were continued by hired labor at a cost of 
$5,546. Contractual services were performed at a cost 
of $89,340, and real estate services at a cost of $1,449. 
For the 1986 project, engineering and design were 
performed by hired labor at a cost of $25,339. 
Condition at end of fiscal year. Total cost of 
existing project to September 30, 1986 were $1,927,085 
of which $231,884 was for new work ($191,884 regular 
funds and $40,000 contributed funds) and $1,695,201 
was for maintenance ($1,306,212 Federal funds and 
$388,989 contributed funds). 
15. LAKE MICHIGAN, EDGE WATER 
/ROGERS PARK COMMUNITIES, 
CHICAGO, IL 
Location. On the Illinois Shore of Lake Michigan 
in City of Chicago (Cook County) from Hollywood- 
Ardmore Beach to Chicago-Evanston border. 
Existing Project. Construction of offshore breakwaters 
at Thorndale Avenue, Hartigan Park and 
Beach, and in the Sherwin Avenue, Jarvis Avenue 
and Fargo Avenue area. Riprap revetments at Granville 
Avenue, Rosemont Avenue, and North Shore 
Avenue. Beach nourishment at Devon Avenue, Park 
and Beach. Seawall extension at Glenlake Avenue. 
Placement of Riprap revetment at Berger Park. The 
project was authorized by PL 99-190 section 123. 
Local Cooperation. The local sponsor is required 
to provide all lands, easements and rights of way, 
provide all required relocations, hold and save the 
United States from any damages due to construction 
or operation of the project, and contribute a minimum 
of twenty-five percent of the total project costs. A Local 
Cooperation Agreement will be executed prior to construction. 
Operation and results during period. New 
Work: Plans and specifications were initiated for a 
total cost of $113,972 at the following locations: 
Fiscal Year Cost 
Project and Location to September 30, 1986 
Lake Michigan-Granville Ave., Chicago, IL $ 5,400 
Lake Michigan-Glenlake Ave., Chicago, IL $ 1,000 
Lake Michigan-Thorndale Ave., Chicago, IL $ 8,200 
Lake Michigan-Rosemont Ave., Chicago, IL $ 5,400 
Lake Michigan-North Shore Ave., Chicago, IL $ 5,000 
Lake Michigan-Fargo Ave., Chicago, IL $44,590 
Lake Michigan-Jarvis Ave., Chicago, IL $44,382 
Condition at end of fiscal year: Project is under 
design. Total costs of existing project to 30 September 
1986 were $113,972. 
16. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See table 30-F. 
17. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, flood fighting 
and rescue work (Public Law 99, 84th Cong. and 
antecedent legislation). 
Project and Location 
Disaster Preparedness 
Rehabilitation 
Emergency Operations 
Advance Measures 
Fiscal Year Costs 
to September 30, 1986 
$171,205 
67,062 
54,888 
18,949 
Emergency bank protection (Sec. 14 of the 1946 
Flood Control Act Public Law 526. 79th Cong.). 
Fiscal Year Costs 
Project and Location to September 30, 1986 
Lake Michigan, Sunrise Park, Lake Bluff, IL $16,632 
Lake Michigan, Lake Forest, IL 34,091 
Lake Michigan, Devon Ave. Beach, Chicago, IL 2,329 
Lake Michigan, Berger Park, Cook County, IL 26,380 
Lake Michigan, Beverly Shores Road, IN 190,800 
Lake Mich. Long Beach, LaPorte County, IN 16,819 
Rosewood Beach Bath House, 
Highland Park, IL 5,861 
Flood control activities pursuant to section 205 of 
Flood Control Act of 1945, as amended. 
Fiscal Year Costs 
Project and Location to September 30, 1986 
Fox River, McHenry County, IL $102,991 
Salt Creek, IN 7,500 
Libertyville Estates, IL 20,509 
Valleyview, IL 23,320 
Wilmington, IL 108,589 
30-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
GENERAL INVESTIGATIONS 19. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs of $102,000 were for: 
Flood Plain Management Services $102,000 
18. SURVEYS 
Fiscal year costs were $1,731,656 itemized as follows: 
Navigation Studies 
Flood Damage Prevention Studies 
Shoreline Protection Studies 
Special Studies 
Special Investigations 
Coordination Studies 
Supplemental Pre-authorization 
Review for Deauthorization 
Continuation of Planning and Engineering 
$ 0 
156,805 
97,175
0 
26,000 
28,871 
551,323 
5,000 
866,482 
20. RESEARCH AND 
DEVELOPMENT 
Cost for hydrologic studies during the fiscal year 
was $2,069. 
21. NATIONAL EMERGENCY 
PREPAREDNESS 
Fiscal year costs of $156,990 were for: 
Training and Exercises 
Management and Mobilization Planning 
$69,451 
87,539 
30-8

CHICAGO, IL, DISTRICT 
TABLE 30-A COST AND FINANCIAL STATEMENT 
See Total to 
Section September 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 30, 1986 
1. Burns Waterway 
Harbor, IN 
(Federal Funds) 
(Contributed 
Funds) 
2. Calumet Harbor 
and River, IL 
and IN 
(Federal Funds) 
(Contributed 
Funds) 
3. Chicago Harbor, 
IL 
(Federal Funds) 
4. Chicago River, IL 
5. Indiana Harbor, 
IN 
6. Michigan City 
Harbor, IN 
(Contributed 
Funds) 
7. Waukegan 
Harbor, IL 
11. Indiana Dunes 
National Lakeshore, 
Beverly 
Shores, IN 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
-64,000 
-44,353 
4,431,000 
3,340,642 
1,499,000 
1,080,124 
0 
4,732 
639,000 2 
2,478,072 2 
842,500 
1,446,975 
1,994,000 530,000 
1,486,071 1,225,815 
510,000 
304,630 
-13,000 
-7,573 
90,000 
182,567
0 
571,486 
90,000 
70,306 
150,000 
169,592 
13,584,000 
13,584,000 
3,954,793 
3,954,691 
15,900 
15,900 
22,578,567' 
22,578,567' 
,679,000 985,000 23,865,7742 
,330,158 1,399,456 23,828,5982 
689,001': 
689,001': 
836,667 
836,667 
4,788,8274 
4,788,8274 
685,000 1,507,000 10,280,286 
653,159 1,488,154 10,185,227 
1,326,600 
1,326,600 
1,500,5655 
1,500,5655 
431,000 970,000 8,635,7376 
385,246 941,516 8,544,3036 
4,897,148 9 
4,897,148 9 
236,123 1,365,000 
434,483 1,075,541 
20,000 
18,685 
566,671 
504,344
0
0 
0 
1,315 
507,000 
309,456
00 
981,000 
1,224,393 
25,000 
22,484 
8,269,7788 
8,216,611" 
1,543,646' 
1,543,646 1' 
4,665,512 
4,662,996 
1,618,670 
1,618,670 
30,800 
30,800 
823,026" 
823,026" 
380,000 5,767,98012 
753,002 5,757,83312 
0 660,000 
0 660,000 
30-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 30-A (Cont'd) COST AND FINANCIAL STATEMENT 
See Total to 
Section September 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 30, 1986 
14. Chicago River, IL New Work: 
North Branch Approp. 191,884 
(Federal Funds) Cost 191,884 
Maint.: 
Approp. 150,000 50,000 230,000 66,000 1,343,000 
Cost 133,907 78,167 243,775 137,171 1,306,212 
(Contributed New Work: 
Funds) Approp. 40,000 
Cost 40,000 
Maint.: 
Approp. 0 60,000 60,000 111,600 531,600 
Cost 63,367 5,956 74,415 26,458 388,989 
15. Lake Michigan- New Work: 
Edgewater/ Approp. 121,000 121,000 
Rogers Park Cost 113,972 113,972 
Communities, 
Chicago, IL 
1. Includes $855,973 for previous projects. 
2. Excludes contributed funds in settlement pursuant 
to decree [No. 54-C-1608] regarding removal of flue-dust 
and includes $45,230 for previous projects. 
3. In settlement pursuant to decree [No. 54-C-1608] 
regarding removal of flue-dust. 
4. Includes $446,005 for previous projects. 
5. Includes $955,886 for previous projects. 
6. 
7. 
8. 
9. 
10. 
11. 
12. 
Includes $109,463 for previous projects. 
Includes $60,668 for previous projects. 
Includes $2,509 for previous projects. 
Excludes $12,500 contributed funds. 
Includes $287,389 for previous projects. 
Includes $218,233 on previous projects. 
Includes $15,711 on previous projects. 
30-10

CHICAGO, IL, DISTRICT 
TABLE 30-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 27, 1965 
Mar. 3, 1899 
June 13, 1902 
Mar. 3, 1905 
June 25, 1910 
Sept. 22, 1922 
Aug. 30, 1935' 2 
Aug. 30, 1935' 2 
Mar. 2, 1945: 
July 14, 1960 
Oct. 23, 1962 
Oct. 27, 1965 
July 11, 1870 
June 14, 1880 
Mar. 3, 1899 
July 25, 1912 
Mar. 2, 1919 
Mar. 3, 1931 
Mar. 2, 1945 
Oct. 23, 1962 
Dec. 4, 1981 
July 30, 1983 
Mar. 3, 1899 
June 13, 1902 
BURNS WATERWAY HARBOR, IN 
(See Section 1 of Text) 
Provides for breakwater and channel to present dimensions and 
depths: North Breakwater, West Bulkhead, Approach Channel 
and Outer Harbor, East and West Harbor Arms. 
CALUMET HARBOR AND RIVER, IL AND IN 
(See Section 2 of Text) 
Outer harbor protected by breakwaters. 
Five turning basins. 
Provided for shape and dimensions of turning basins. 
Consolidated the 2 projects for Calumet Harbor and Calumet 
River. 
Detached breakwater, dredging outer harbor to existing 
project depth and dimensions; deepen river-entrance channel 
and river to existing project depths; widen and straighten river 
channel; 5 turning basins to same depth as adjacent channel. 
Dredging area A and B in south end of Lake Calumet and an 
entrance channel 300 feet wide to 21 feet deep. 
An approach channel to harbor 3,200 feet wide and 28 feet 
deep through shoals outside breakwater and closing existing 
gap between breakwaters. 
Depth of 29 feet in lake approach to 28 feet in outer harbor; and 
27 feet in river entrance up to E.J.&-E. Ry. Bridge. 
Deepen, widen, and straighten channel in Calumet River from 
E.J.&-E. Ry. Bridge, to and including turning basin 5, to a depth 
of 27 feet in earth and 28 feet in rock; deepen turning basins 1, 
3 and 5 to 27 feet; enlarge turning basins 3 and 5; a channel 
into Lake Calumet to 27 feet deep for 3,000 feet and a width of 
1,000 feet; and eliminate turning basins 2 and 4 from project. 
Modification of Act of Oct. 23, 1962. Protection for Elgin, Joliet 
and Eastern Railway Bridge over the Calumet River, to permit 
dredging to full width of the south draw to depth of 27 feet, 
and temporary protection for center pier and south abutment 
of the New York, Chicago, and St. Louis Railroad Bridge 
[Nickel Plate] to permit dredging of full width of south bridge 
draw to depth of 27 feet prior to its replacement. 
CHICAGO HARBOR, IL 
(See Section 3 of Text) 
Inner breakwaters and inner basin. 
Exterior Breakwater. 
Present project depth in basin, and entrance to Chicago River. 
Shore-arm and southerly extension of exterior breakwater. 
Modification of area to be dredged in inner basin. 
Shore-arm extension of exterior breakwater transferred to 
Lincoln Park Commissioners. 
Resumption of jurisdiction over shore-arm extension breakwater 
and over certain navigable waters in Lake Michigan which lie 
in northwestern part of outer harbor. 
Deepen a lake approach channel to 29 by 800 feet wide for 6,600 
feet; and deepen a channel and maneuver area inside harbor 
entrance to 28 by 1,300 feet wide. 
Provides for lock operations and maintenance responsibilities 
in the interests of navigation. 
CHICAGO RIVER, IL 
(See Section 4 of Text) 
For project depth of 21 feet in lieu of that fixed by act of 
June 3, 1896 
Turning basins. 
Public Law, 89-298, H. Doc. 160, 
88th Cong., 1st sess. 
Annual Report, 1896 pp. 2584 et 
seq. and H. Doc. 277, H. 
54th Cong., 1st sess. 
H. Doc. 172, 54th Cong., 2d sess. 
H. Doc. 349, 60th Cong., 1st sess. 
H. Doc. 494, 72d Cong., 2nd sess. 
H. Doc. 180, 73rd Cong., 2d sess. 
H. Doc. 233, 76th Cong., 1st sess. 
H. Doc. 149, 86th Cong., 1st sess.4 
H. Doc. 581, 87th Cong., 2d sess.5 
H. Report No. 973, 89th Cong., 
1st sess. 
H. Ex. Doc. 114, 41st Cong., 2d 
sess., and Annual Report 1879, 
pp. 1562-1567 
Annual Report, 1870, pp. 1562- 
1567 
Annual Report 1897, pp. 2790- 
2791 
H. Doc. 710, Cong., 2d sess. 
H. Doc. 1303, 64th Cong., 1st sess. 
Public Law 797, 71st Cong. 
Public Law 14, 79th Cong. 
H. Doc. 485, 87th Cong. 2d sess. 
Section 107 of 
Public Law 97-88 
Public Law 98-63 
Specified in act. 
Specified in act. 
30-11

CHICAGO, IL, DISTRICT 
TABLE 30-B (Cont'd) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1907 
Mar. 2, 1919 
July 24, 1946 
June 25, 1910 
Mar. 4, 1913 
Mar. 2, 1919 
Mar. 20, 1922 
Mar. 3, 1925 
Mar. 2, 1929 
July 3, 19301' 
June 30, 1932 
Aug. 30, 19351 
Aug. 26, 1937 
July 14, 1960 
Oct. 27, 196512 
Mar. 3, 1889 
Mar. 3, 1905 
Jan. 21, 1927 
Interpreted by Chief of Engineers, April 11, 1908 as adopting 
new work of the then existing project for 21-foot depth. 
Eliminated all work except maintenance of main river. 
Dredging channel 9 feel deep to within 30 feet of existing 
bulkheads and river banks from North Ave. to Belmont 
Ave., thence 9 feet deep and 50 feet wide to Addison St. 
INDIANA HARBOR, IN 
(See Section 5 of Text) 
Maintenance of outer harbor. Maintenance of inner harbor 
channel when deeded free of cost to and accepted by the 
United States. 
Breakwaters. 
Lighthouse crib, present length and alignment easterly and 
northerly breakwaters. 
Reduce length of channel to be maintained in extension to 
Lake George. 
Authorized Secretary of War to modify project so far as relates to 
length and alignment of breakwaters and to sell Youngstown 
Sheet and Tube Co. about 1,180 linear feet of shoreward end of 
existing north breakwater. 
Accept 2.3 acres of land for construction of the Forks Turning 
Basin. 
Existing project channel width and depth in Lake George 
Branch and turning basin at the Forks. 
Authorized Secretary of War to sell Inland Steel Co. about 1,903 
linear feet of southerly end of existing east breakwater. 
Extended easterly breakwater, dredge entrance channel and 
outer harbor, deepen channel between bulkhead fills, widen 
main stem of canal and portion of Calumet River Branch to 
141st St. 
Modified conditions of local cooperation required before 
enlargement of Indiana Harbor Canal is undertaken by 
United States. 
Increase authorized depths to 29 feet in outer harbor entrance 
channel; 28 feet in outer harbor, and 27 feet in canal entrance 
channel to first E.J.&-E. Ry. Bridge. 
Deepen main canal from landward end of canal entrance 
channel to a point lakeward of Dickey Place Bridge over a 
modified channel width of 190 feet, except through bridge 
openings. 
MICHIGAN CITY HARBOR, IN 
(See Section 6 of Text) 
East breakwater and old east pier inclosing the outer basin. 
Extension of east pier. 
Extend east pier and construct detached breakwater. 
Lower turning basin. 
Rebuild west pier as at present located. 
Present project dimensions of entrance channel. 
Existing project depth in channel, and in lower and middle 
turning basins, eliminated improvement of Trail Creek above 
middle turning basin and uncompleted portion of detached 
breakwater, abandonment of old east breakwater and old east 
pier inclosing outer basin. 
H. Doc. 95, 56th Cong., 1st sess. 
[Annual Report, 1900, p. 3863 
and Annual Report, 1909, 
p. 709]. 
H. Doc. 1294, 64th Cong., 1st sess. 
H. Doc. 767, 78th Cong., 2d 
sess." 
H. Doc. 1113, 60th Cong., 2d 
sess. 
H. Doc. 690, 62d Cong. 2d sess. 
Rivers and Harbors Committee 
Doc. 6, 65th Cong., 2d sess. 
Public Law 176, 67th Cong. 
Rivers and Harbors Committee 
Doc. 21, 71st Cong., 2d sess. 
Public Law 219, 72d Cong. 
Rivers and Harbors Committee 
Doc. 29, 72d Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 13, 75th Cong., 1st sess. 
H. Doc. 195, 86th Cong., 1st sess. 
H. Doc. 227, 89th Cong., 1st sess.8 
Recommendations of a Board of 
Engineers, Annual Report, 
1870, p. 123. 
Reports of Boards of Engineers, 
Annual Report, 1851, pp. 
2187-2189; Annual Report 
1882, pp. 2264-2266. 
Annual Report, 1897, pp. 2903- 
2904. 
Joint resolution of Congress 
approved May 13, 1908. 
Public Law 23. 
H. Doc. 279, 69th Cong., 1st sess. 
30-12

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 30-B (Cont'd) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935 Restore and repair westerly 1,000 feet of east breakwater, Rivers and Harbors Committee 
dredging outer basin, and enlarging entrance to basin Doc. 34, 74th Cong., 1st sess. 
through east pier. 
Sept. 30, 1966 Dredge river channel 50 feet wide and 6 feet deep from upper Detailed Project Report June 
Sec. 107 turning basin to E Street bridge. 1965.8 
July 14, 1960 
WAUKEGAN HARBOR, IL 
(See Section 7 of Text) 
June 14, 1880 Parallel piers and basins. Annual Report, 1880, p. 1942 
Aug. 3, 1882 Modified location of harbor entrance. Annual Report, 1882, pp. 277, 
2162. 
June 13, 1902 Detached breakwater, extend piers, increase width of harbor at H. Doc. 343, 56th Cong., 1st sess. 
inner end of north pier, and dredge channel and basin to depth 
of 20 feet. 
July 3, 1930 Extension of breakwater to shore, dredging near outer end of Rivers and Harbors Committee 
north pier, and enlarging inner basin. Doc. 27, 71st Cong., 2d sess. 
Mar. 2, 1945 Dredge an entrance channel to existing project dimensions from H. Doc. 116, 77th Cong., 1st sess. 
outer end of north pier to project depth in lake, and dredge an 
anchorage area in southwest corner of inner basin to existing 
project depth. Abandonment of dredging triangular area in 
southwest corner of inner basin to 18 feet deep. 
Dec. 17, 1970 Provides for deepening the existing entrance channel in the H. Doc. 368, 90th Cong., 2d sess." 
Sec. 201 outer harbor to 25 feet and extending it to the depth in Lake 
Oct. 27, 1965 Michigan, at widths varying from 380 feet to 500 feet; 
deepening the channel between piers to a depth of 23 feet at a 
width of 180 feet, and deepening the inner basin to 23 feet and 
extending its limits approximately 275 feet northward. 
INDIANA DUNES NATIONAL LAKESHORE, IN, 
BEVERLY SHORES, IN 
Dec. 4, 1981 Provides for emergency shore protection repairs to stone Public Law 97-88. 
revetment initially constructed in 1973. 
July 30, 1983 Provides for operations and maintenance of the shore Public Law 98-63. 
protection measures. 
LAKE MICHIGAN-EDGEWATER/ROGERS PARK 
COMMUNITIES, CHICAGO, IL 
Dec. 15, 1985 Provides for emergency bank stabilization, shore protection Public Law 99-190 
and flood control work. 
1 Tncluded in Public Works Administration Program 7. Contains latest published map of North Branch 
Sept. 6, 1943, and Dec. 16, 1933. 
2. Uncompleted portion was deauthorized in 1977 
[dredging in front of U.S. Steel Corp.] 
3. Uncompleted portion was deauthorized in 1977 
[breakwater closure.] 
4. Contains latest map of harbor. Uncompleted portion 
is inactive. 
5. Contains latest map of river. 
6. Latest published map is in Annual Report for 1914, 
opposite p. 2928. 
above North Ave. 
8. Contains latest published map. 
9. Completed under previous project. 
10. Uncompleted portion was deauthorized in 1977 
[widen and deepen Lake George Branch] 
11. Included in Public Works Administration Program 
Sept. 6, 1933, and July 25, 1934. Uncompleted portion was 
deauthorized in 1977 [widen and deepen main canal and 
Calumet River Branch.] 
12. Project deauthorized in 1977. 
30-13

CHICAGO. IL, DISTRICT 
TABLE 30-C EXISTING PROJECTS 
See 
Section Length Width Depth 
in Text Project Item (feet) (feet) (feet) 
1. Burns Waterway North Breakwater 4.646 - - 
2. Calumet Harbor 
and River, IL 
and IN 
3. Chicago Harbor, 
IL 
4. Chicago River, 
IL 
5. Indiana Harbor, 
IN 
6. Michigan City 
Harbor, IN 
7. Waukegan Harbor, 
IL 
Harbor, IN Outer West Bulkhead 
Approach Channel 
Outer Harbor 
East Harbor Arm 
West Harbor Arm 
Northerly Crib Breakwater 
Southerly Steel Breakwater 
North Pier 
Approach channel 
Outer Harbor 
River entrance 
Elgin, Joliet & Eastern Railway Bridge 
to turning basin No. 3 
Turning basin No. 3 to turning basin No. 5 
Approach into Lake Calumet 
Extension into Lake Calumet 
Turning basins 1, 3, and 5 
Shore arm extension 
Exterior breakwater 
Exterior breakwater southerly ext. 
North inner breakwater 
South inner breakwater 
North pier 
Approach channel 
Channel and maneuver area 
Lock 
Inner basin 
Entrance channel 
Main Branch of Chicago River 
North Branch of Chicago River 
North Branch Canal 
North Branch Turning Basin 
Northerly Breakwater 
Easterly Breakwater 
Approach Channel 
Outer Harbor 
Entrance Channel 
Main Canal 
Turning Basin 
Lake George Branch 
Calumet River Branch 
Detached breakwater 
West pier 
East pier 
East breakwater 
Entrance channel 
Main channel 
Outer basin 
Trail Creek 
Trail Creek 
North breakwater and Shore Connection 
North pier and North Revetment 
South pier 
Entrance Channel 
Channel to inner basin 
Inner basin 
Anchorage Area 
3,476 
2,200 
3,700 
2,100 
3,800 
6,714 
5,007 
2,450 
9,700 
10,500 
3,000 
21,100 
8,000 
4,000 
3,000 
2,250 
5,421 
4,944 
4,034 
2,544 
960 
6,600 
2,200 
600 
1,270 
7,300 
3,800 
11,100 
5,500 
1,120 
2,525 
7,200 
4,200 
3,600 
7,400 
3,700 
2,500 
1,304 
835 
2,276 
1,000 
1,900 
2,400 
900 
3,000 
2,300 
1,896 
2,074 
3,111 
3,250 
1,700 
1,650-' 
400 
Varies 
620 
620 
3,200 
3,000 
290 
200 
and variable 
Variable 
400 
1,000 
800 
1,300 
80 
740 
190-470 
190-390 
91-390 
56-210 
800 
Varies 
65-280 
61-210 
64-160 
160-260 
150-425 
120-150 
900 
50-100 
50 
390 
200 
375-500
80 
'Area of about 6 acres. 
30-14 
30 
28 
27 
27 
29 
28 
27 
27 
earth 
28 
rock 
27 
27 
27 
27 
29 
28 
23 
21 
21 
21 
21 
21 
21 
29 
28 
27 
22 
22 
22 
22 
18 
18 
8-12
86 
22 
18 
18 
8

TABLE 30-D 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED BRIDGE ALTERATION 
(See Section 10 of Text) 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Calumet River Bridges' 1967 $1,625,068 - 
'Transferred to Department of Transportation in accordance with Section 6[g] of the Act of October 15, 1966, P.L. 89-670. 
TABLE 30-E OTHER AUTHORIZED BEACH EROSION PROJECTS 
(See Section 12 of Text) 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Mt. Baldy, Indiana Dunes National 
Lakeshore, IN 1984 $1,500,000 
Hollywood-Ardmore Beach 
Chicago, IL 1982 237,271 - 
Evanston, IL 1979 766,052 - 
Lake Michigan-Lake Bluff, IL 1976 244,889 - 
Lake Michigan-Lake Forest, IL' 1975 65,611 - 
'Authorized by River and Harbor Act of 1954. 
OTHER AUTHORIZED 
TABLE 30-F FLOOD CONTROL PROJECTS 
(See Section 16 of Text) 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
KANKAKEE RIVER, IL AND IN 
Levee between Shelby Bridge and 
Baum's Bridge in IN 1938 
LITTLE CALUMET RIVER, IL AND IN 
Little Calumet River and Tributaries, 
IL and IN' 1968 53,136 - 
Little Calumet River, IL 1984 583,000 
'Classified inactive to November 1971. 
TABLE 30-G RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 8 of Text) 
Date 
Reconnaissance 
or Condition 
Survey 
Project Conducted Cost 
Burns Waterway Harbor, IN May 1986 $ 4,748 
Calumet Harbor & River, IL and IN Apr., June, Aug. 1986 43,758 
Chicago Harbor, IL Sept., Oct. 1986 -2,000' 
Indiana Harbor, IN Oct., Dec. 1985, Mar. 1986 17,144 
Michigan City Harbor, IN Aug. 1986 166 
Waukegan Harbor, IL July, Sept., Oct. 1986 -4051 
Beveraly Shores, IN May, Sept. 1986 13,038 
Burns Small Boat Harbor, IN Sept. 1986 180 
'Cost reflects an adjustment as a result of condition surveys performed in 1985. 
30-15

DETROIT, MI DISTRICT * 
The district is composed of the upper and lower peninsulas of 
Michigan and portions of Indiana, Wisconsin and Minnesota, 
which border the lakes. It includes U.S. waters of Lakes Superior, 
Michigan, Huron, St. Clair and western Lake Erie. Unless otherwise 
indicated, all depths stated in this report are referred to 
low water datum as follows: Lake Superior, 600 feet; Lake 
Michigan-Huron, 576.8 feet; Lake Erie, 568.6 feet; and Lake 
St. Clair, 571.7 feet. Elevations in feet are above mean water 
level at Father Point, Quebec (International Great Lakes 
Datum- 1955). 
IMPROVEMENTS 
Navigation Page 
1. Arcadia Harbor, MI............ ........... 31-2 
2. Ashland Harbor WI................ ........... 31-2 
3. Big Suamico, WI ............................ 31-2 
4. Black River, (U.P.) MI........................31-3 
5. Bolles Harbor, MI............................31-3 
6. Charlevoix Harbor, MI........................31-3 
7. Cheboygan Harbor, MI......................31-4 
8. Clinton River, MI..............................31-4 
9. Cornucopia Harbor, WI........................31-4 
10. Detour Harbor, MI............................31-4 
11. Detroit River, MI.............................31-5 
12. Duluth-Superior Harbor, MN and WI............ 31-5 
13. Fox River, WI...............................31-6 
14. Frankfort Harbor, MI.........................31-6 
15. Grand Haven Harbor and Grand River, MI....... 31-7 
16. Grand Marais Harbor, MN.....................31-7 
17. Green Bay Harbor, WI.......................31-7 
18. Hammond Bay Harbor, MI....................31-8 
19. Harbor Beach Harbor, MI......................31-8 
20. Harrisville Harbor, MI.........................31-8 
21. Holland Harbor, MI...........................31-9 
22. The Inland Route, MI.........................31-9 
23. Kenosha Harbor, WI ........................ 31-10 
24. Kewaunee Harbor, WI ....................... 31-10 
25. Keweenaw Waterway, MI .................... 31-10 
26. Knife River Harbor, MN....................31-11 
27. LaPointe Harbor, WI.......................31-11 
28. Lake St. Clair, MI Channels ................... 31-11 
29. Leland Harbor, MI............ ........... 31-12 
30. Lexington Harbor, MI ....................... 31-12 
31. Little Lake Harbor, MI ....................... 31-12 
32. Ludington Harbor, MI......................31-12 
33. Mackinac Island Harbor, MI ................... 31-13 
34. Mackinaw City Harbor, MI .................... 31-13 
35. Manistee Harbor, MI ......................... 31-13 
Navigation (cont.) Page 
36. Manitowoc Harbor, WI....................... 31-14 
37. Marquette Harbor, MI ........................ 31-14 
38. Menominee Harbor and River, MI and WI....... 31-15 
39. Milwaukee Harbor, WI ....................... 31-15 
40. Monroe Harbor, MI .......................... 31-16 
41. Muskegon Harbor, MI ........................ 31-16 
42. New Buffalo Harbor, MI ..................... 31-16 
43. Ontonagon Harbor, MI ....................... 31-17 
44. Pensaukee Harbor, WI ........................ 31-17 
45. Pentwater Harbor, MI ........................ 31-17 
46. Petoskey Harbor, MI ......................... 31-18 
47. Point Lookout Harbor, (Au Gres River) MI ...... 31-18 
48. Port Austin Harbor, MI ....................... 31-18 
49. Portage Lake Harbor, MI ..................... 31-18 
50. Port Sanilac Harbor, MI ..................... 31-19 
51. Port Washington Harbor, WI..................31-19 
52. Port Wing Harbor, WI................. ..... 31-19 
53. Racine Harbor, WI ........................... 31-19 
54. Rouge River, MI ............................ 31-20 
55. Saginaw River, MI........................ 31-20 
56. St. Clair River, MI.............. ............ 31-21 
57. St. Joseph Harbor, MI.......................31-21 
58. St. Marys River, MI.........................31-22 
59. Saugatuck Harbor and Kalamazoo River, MI..... 31-23 
60. Saxon Harbor, WI ........................... 31-23 
61. Sheboygan Harbor, WI.......................31-23 
62. South Haven Harbor, MI ..................... 31-24 
63. Sturgeon Bay and 
Lake Michigan Ship Canal, WI.................31-24 
64. Tawas Bay Harbor, MI....................31-24 
65. Two Rivers Harbor, WI......................31-24 
66. White Lake Harbor, MI.......................31-25 
67. Reconnaissance and Condition Surveys .......... 31-25 
68. Other Authorized Navigation Projects...........31-25 
69. Navigation Work Under Special Authorization.... 31-25 
31-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Beach Erosion Control Page 
70. Authorized Beach Erosion Control Projects.......31-25 
71. Emergency Shore Protection.................. 31-25 
72. Beach Erosion Work Under Special 
Authorization ............................ 31-26 
73. Mitigation of Shore Damages..................31-26 
Flood Control 
74. Kawkawlin River, MI....................... 31-26 
75. Saginaw River, MI......................... 31-26 
76. Sebewaing, Sebewaing River, MI ............... 31-27 
77. Inspection of Completed Flood Control Projects...31-28 
78. Other Authorized Flood Control Projects.........31-28 
79. Flood Control Under Special Authorization ....... 31-28 
80. Surveillance of Northern Boundary Waters....... 31-29 
General Investigations Page 
81. Surveys .................................... 31-31 
82. Continuation of Planning and Engineering....... .31-31 
83. Collection and Study of Basic Data............. 31-31 
Tables 
Table 31-A Cost & Financial Statement............. 31-33 
Table 31-B Authorizing Legislation.................31-46 
Table 31-C Features of Existing Project............. 31-58 
Table 31-D St. Marys River, MI: Existing Project ... .31-59 
Table 31-E Fox River, WI: Locks & Dams.......... 31-60 
Table 31-F Reconnaissance & Condition Surveys..... 31-61 
Table 31-G Other Authorized Navigation Projects ..... 31-62 
Table 31-H Other Authorized Flood Control Projects. .31-63 
Table 31-I Deauthorized Projects.................. 31-63 
1. ARCADIA HARBOR, MI 
Location. On east shore of Lake Michigan, 193 miles northeasterly 
from Chicago, IL, and 15 miles northerly from Manistee, 
MI. (See NOAA Nautical Chart No. 14907). 
Existing project. Provided for maintenance dredging of the 
existing harbor built by private interests for a period of five years. 
The five years covered by this project were the calendar years 
1905 to 1909, inclusive. Funds were also appropriated and 
maintenance was performed in calendar years 1911, 1912, 1913 
and 1915, inclusive. There is at present no approved project for 
the improvement of this harbor. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. None required. 
Terminal facilities. Dock facilities are considered adequate 
for existing recreational traffic. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$15,086. A contract was awarded and completed for maintenance 
dredging at a cost of $27,744, removing approximately 7,102 
cubic yards of shoal material by hydraulic dredge. Repairs to 
navigation structures were performed by hired labor using the 
cranebarge MANITOWOC at a cost of $80,902. Engineering and 
design for repair to north and south piers was performed at a 
cost of $1,765. Engineering, design, surveys, supervision and 
administration cost $19,121. 
Existing project was completed in 1909. Varying depths of 5-12 
feet exist in the channel at present. Future maintenance of the 
harbor will be based on providing a 9-foot depth. Piers and 
revetments are in good condition with some sections in need of 
major repair. Total cost at the end of FY for existing project was 
$1,254,817. 
2. ASHLAND HARBOR, WI 
Location. At head of Chequamegon Bay, on south shore of 
Lake Superior, about 65 miles east of Duluth, MN. (See NOAA 
Nautical Chart 14974.) 
Existing project. A west channel 20 and 21 feet deep and an 
east basin 25 and 27 feet deep, both all protected by an 8,000-foot 
breakwater. For additional details see page 1008 of Annual Report 
for 1965. (See Table 31-B for authorizing legislation) 
Local cooperation. Fully complied with. 
Terminal facilities. City of Ashland owns 4,150 feet of waterfront 
for future public needs. Wharves for handling coal, ore, 
limestone, logs and pulpwood are served by railroads. Facilities 
are considered adequate for existing commerce. Handling of ore 
and logs has been discontinued for the present. 
Operations during fiscal year. Maintenance: Condition 
surveys and miscellaneous inspections and reports were performed 
by Government forces at a cost of $28,764. Breakwater repairs 
were performed by hired labor using the Derrickbarge COLEMAN 
at a cost of $84,305. An adjustment of -$20,000 was made 
in prior year costs for structure repairs. Supervision and administration 
was performed at a cost of $36,534. 
Work authorized prior to 1960 Act was completed in 1950. 
Work authorized by 1960 Act was completed in November 1962. 
Total cost of existing project to end of FY was $4,305,993, of 
which $1,695,645 was for new work and $2,610,348 for 
maintenance. 
3. BIG SUAMICO RIVER, WI 
Location. A small stream which flows easterly into Green Bay, 
an arm of Lake Michigan. Mouth of the river is about 8 miles 
north of Green Bay Harbor, and about 44 miles southwesterly 
from Menominee Harbor, MI and WI. (See NOAA Nautical 
Chart No. 14910.) 
Existing project. An entrance channel 8 feet deep which extends 
from that depth in Green Bay to 1,800 feet above the river 
mouth, with widths of 100 feet in bay and 60 feet in river, total 
length of channel is about 3,700 feet. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Small private wharves along lower 1.5 
miles of river, used by local fishing interests. Ample space is 
available for additional fishing wharves when required. Facilities 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys were performed by Government forces at a cost of 
$8,757. 
31-2

DETROIT, MI DISTRICT 
Existing project was completed in 1938. Dredging channel was 
started in September 1938 and completed in November 1938. 
Total costs to end of FY were $195,605. 
4. BLACK RIVER HARBOR 
(UPPER PENINSULA), MI 
Location. At mouth of Black River on south shore of Lake 
Superior 39 miles westerly from Ontonagon, MI, and 47 miles 
easterly from Ashland, WI. (See NOAA Nautical Chart 14965.) 
Existing project. Two converging breakwaters, an entrance 
channel between breakwaters, an inner channel, and an irregular 
harbor basin. For additional details see page 1092 of Annual 
Report for 1966. Project depths are 12 feet in the approach channel 
and 8 feet in the river channel and basin. (See Table 31-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. Local interests furnished 
easements on 0.85 acre of land. 
Terminal facilities. Wharves constructed on both sides of river. 
Wharf on east bank has frontage of 400 feet; on west bank, a 
frontage of 750 feet. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed 
by Government forces at a cost of $8,645. 
Project was completed in June 1958. A triangular-shaped rock 
shoal 50 feet wide at easterly end extends along southerly side 
of channel. Total cost of existing project to end of FY was 
$960,363, of which $383,350 was for new work and $577,013 
for maintenance. 
5. BOLLES HARBOR, MI 
Location. On west shore of Lake Erie at mouth of La Plaisance 
Creek, 7 miles southwest of Monroe, MI. (See NOAA Nautical 
Chart 14846.) 
Existing project. Provides for an entrance channel in Lake 
Erie, 8 feet deep and 80 feet wide from deep water to a point 
opposite the outer end of existing jetty, thence widening to 100 
feet at creek mouth; an access channel in La Plaisance Creek, 
6 feet deep and 100 feet wide at the mouth widening to 120 feet 
and extending to the first bend, thence narrowing to 50 feet wide 
and continuing at that width to the La Plaisance Road bridge; 
a steel sheet pile revetment, about 200 feet long, located along 
Michigan State Conservation Department property on west side 
of channel at creek mouth. Project also provides for inclusion 
of existing 400-foot long steel sheet pile jetty constructed by 
Michigan State Waterways Commission at the mouth of La 
Plaisance Creek. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. The Monroe Boat Club and three marinas 
provide facilities adequate for existing recreational boat traffic. 
There is also a public launching ramp and parking area at Conservation 
Department fishing site at creek mouth. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, and miscellaneous inspections 
and reports were performed by hired labor at a cost of $33,586. 
Engineering and design for repair of Diked Disposal Facility 
was ompleted at a cost of $29,879. A contract for repair of Dike 
Disposal Facility was awarded this FY in the amount of $151,032. 
Approximately 53% of the contract was completed at a cost of 
$80,000. Engineering and design for dredging cost $5,916. Supervision 
and administration cost $4,034. 
The existing project was completed in 1970 (Adequate depths 
exist over the project length except for the upstream 800 feet). 
Total costs to the end of FY were $2,665,485, of which $426,413 
was for new work ($255,000 contributed funds) and $2,239,072 
for maintenance. 
6. CHARLEVOIX HARBOR, MI 
Location. On east shore of Lake Michigan, 276 miles northeasterly 
from Chicago, IL, and 75 miles northerly from Frankfort, 
MI. (See NOAA Nautical Chart 14942.) 
Existing project. A channel 24 feet deep in Lake Michigan 
and a river channel 23 feet deep in the lower and upper channels 
connecting Lake Michigan with Lake Charlevoix via Round Lake. 
The channels are protected where needed by piers and revetments. 
For additional details see page 1476 of Annual Report for 1962. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. None required except the latest project 
modification is subject to the following: Provide without cost to 
the United States, all lands, easements, and rights-of-way required 
for construction and subsequent maintenance of the modified project 
upon the request of the Chief of Engineers, including suitable 
areas determined by the Chief of Engineers to be required in the 
general public interest for initial and subsequent disposal of excavated 
materials and any necessary retaining dikes, bulkheads, 
and embankments, therefor, or the cost of such retaining works; 
hold and save the United States free from damages due to the 
construction and maintenance of the modified project, except for 
damages due to the fault or negligence of the United States or 
its contractors; provide and maintain without cost to the United 
States depths in berthing areas and local access channels serving 
the terminals commensurate with the depths provided in the 
related project areas; accomplish, without cost to the United 
States, such alterations of submarine utility crossing as are required 
by the modified project; establish regulations prohibiting 
discharge of pollutants into the waters of the harbor by users 
thereof which regulations shall be in accordance with applicable 
laws or regulations of Federal, State and local authorities responsible 
for pollution prevention and control; if acquiring lands, 
easements and rights-of-way for construction of the project, local 
interests will comply with the applicable provisions of the 
Uniform Relocation Assistance and Real Property Acquisition 
Policies Act of 1970; Public Law 91-646, approved January 2, 
1971; contribute all costs in excess of $1,000,000 should the total 
cost of construction of the general navigation facilities exceed 
that amount, in accordance with provisions of Section 107 of the 
1960 River and Harbor Act, as amended. The total first cost of 
construction (1975) is estimated at $652,000. 
Terminal facilities. Several small landing places in Round 
Lake at Charlevoix for handling fish and miscellaneous commodities, 
a wharf for petroleum products at west end of Lake, 
Charlevoix, and coal wharves at Advance and Boyne City. 
Charlevoix, Boyne City, and East Jordan provide public docks 
31-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
for small craft. Facilities considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous inspections and 
reports were performed at a cost of $29,072. Repairs to South 
Pier and Revetment were performed by hired labor using the 
Cranebarge MANITOWOC at a cost of $74,126. Engineering 
and design for repair of South Pier Section "A" was performed 
at a cost of $47,048. Engineering, design and supervision cost 
$4,322. 
Existing project was completed in 1939 except for the latest 
modification. A controlling depth of 18 feet is available 
throughout the entire project, except for minor shoaling along 
the channel limits. Total costs to end of FY were $6,324,259, 
of which $180,623 was for new work, $5,014,240 for 
maintenance (Bank Stabilization $46,352) and $1,129,396 for 
rehabilitation. 
7. CHEBOYGAN HARBOR, MI 
Location. At mouth of Cheboygan River which empties into 
Western Lake Huron about 16 miles southeast of the Straits of 
Mackinac Bridge. (See NOAA Nautical Charts 14881 and 14886.) 
Previous project. For details see page 1956 of Annual Report 
for 1915, and page 1546 of Annual Report for 1938. 
Existing project. A channel 21 feet deep and 200 feet wide 
from 21-foot contour in Lake Huron to outer end of west pier; 
thence, between lines parallel to and 25 feet from the docks, 21 
feet deep from this point to East First Street and thence 18.5 feet 
deep and 60 feet wide from this bridge to the lock in Cheboygan 
River; a turning basin 21 feet deep, 400 feet wide, and 420 to 
770 feet long on east side of existing project channel just below 
East First Street; and rubblemound breakwater about 775 feet 
long on the site of existing west pier at mouth of river. Improvement 
is 12,000 feet long, on which about 6,000 feet are in Straits 
of Mackinac. 
Local cooperation. Fully complied with. 
Terminal facilities. Several privately owned wharves used for 
receiving coal, stone and petroleum products. Public recreational 
boating facilities constructed by the State and local agencies are 
available. These facilities satisfy existing commerce and vessel 
traffic. 
Operations during fiscal year. Maintenance: Condition 
surveys and miscellaneous inspections and reports were performed 
by hired labor at a cost of $4,663. An adjustment of -$20,000 
was made in cost for structure repair previously performed. 
Total costs to end of FY were $1,364,477 of which $504,236 
was for new work and $860,241 for maintenance. 
8. CLINTON RIVER, MI 
Location. Has its source in Oakland County, MI, flows easterly 
about 60 miles and empties into Anchor Bay in northwestern part 
of Lake St. Clair. (See NOAA Nautical Chart 14850.) 
Previous project. For details see page 1958 of Annual Report 
for 1915, and page 1556 of Annual Report for 1938. 
Existing project. An entrance channel in Anchor Bay 8 feet 
deep, 300 feet wide at 8-foot depth contour in the bay, 
gradually decreasing to 50 feet wide at about 1,000 feet upstream 
from mouth of Clinton River, a length of about 4,600 feet; a channel 
8 feet deep and 50 feet wide in the river about 38,700 feet 
long from entrance channel upstream to Mt. Clemens at Cass 
Avenue; closing old channel and making a cutoff at Shoemakers 
Bend; closing Catfish Channel; construction of revetments as 
needed in the river; and a harbor basin, 5 feet deep and 11 acres 
in area at entrance along bay channel, protected by breakwaters 
on north and south sides. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. River is used exclusively by recreational 
craft. There are numerous public and private piers and wharves 
along the river below the City. They are considered adequate. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed 
by Government forces at a cost of $8,662. Engineering and design 
for construction of confined disposal facility to be performed by 
contract next FY continued at a cost of $72,663. 
Existing project was completed in 1966. Total costs to end of 
FY were $2,027,958, of which $549,798 (including $289,752 
contributed funds) was for new work, and $1,478,160 for 
maintenance. 
9. CORNUCOPIA HARBOR, WI 
Location. At mouth of Siskiwit River on south shore of Lake 
Superior, 49 miles east from Duluth, MN. (See NOAA Nautical 
Chart 14973.) 
Existing project. Provides for an entrance channel between 
piers; an irregular-shaped turning basin; two inner channels, and 
reconstruction and Federal maintenance of deflection dike and 
entrance piers constructed by local interests. Project depths are 
10 feet between piers and 8 feet in turning basin and inner channels. 
For additional details see page 1010 of Annual Report for 
1965. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. About 1,000 linear feet of privately owned 
docking space is available. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed 
by hired labor at a cost of $10,734. 
Work authorized by earlier Act was completed in 1939. Work 
authorized in 1954 was completed in 1963. Total costs to end 
of FY were $1,293,778, of which $462,653 was for new work 
and $831,125 for maintenance. 
10. DETOUR HARBOR, MI 
Location. On the west side of DeTour Passage, about 2 miles 
upstream from Lake Huron. The passage forms the mouth of the 
St. Marys River which connects Lakes Huron and Superior. (See 
NOAA Nautical Chart 14882.) 
Existing project. Provides for small boat harbor and harbor 
of refuge by dredging a 10-foot deep entrance channel and providing 
an 8-foot deep access channel protected by a 1,305-foot 
breakwater. The total estimated (October 1981) project cost is 
$2,650,000; the Federal cost is $1,400,000 and the non-Federal 
cost is $1,250,000 which is a cash contribution. 
31-4

DETROIT, MI DISTRICT 
Local cooperation. Fully complied with. 
Terminal facilities. Public docking, landing, parking and 
sanitary facilities will be provided by the State of Michigan. 
Operations during fiscal year. New Work: Condition surveys 
were performed by Government forces at a cost of $4,118. 
Existing project is complete. Total cost to end of FY is 
$2,569,123, of which $9,776 was for maintenance and 
$2,559,347 for new work. 
11. DETROIT RIVER, MI 
Location. One of the Great Lakes connecting channels, 31 
miles long and flows south from Lake St. Clair to Lake Erie. 
(See NOAA Nautical Chart 14848.) 
Previous project. For details see page 1958 of Annual Report 
for 1915, and page 1541 of Annual Report for 1938. 
Existing project. Improving Detroit River main channels to 
provide 25.5-foot draft navigation; improving certain auxiliary 
and side channels; and construction of various water level and 
crosscurrent control structures. Details are in accompanying Table 
31-C. Project depths are referred to local low water datum planes 
which correspond to low water datums for Lakes St. Clair and 
Erie, 571.7 and 568.6 feet above mean water level at Father Point, 
Quebec (International Great Lakes Datum--1955.) (See Table 
31-B for authorizing legislation.) 
Estimated 1978 Federal cost of new work, exclusive of amounts 
expended on previous projects, is $159,300,000. 
Local cooperation. Fully complied with. No local cooperation 
is required for modifications authorized by Acts of July 1946 
and March 1956. The Trenton Channel modification approved 
August 13, 1968 is considered inactive. 
Terminal facilities. Numerous commercial installations used 
for handling coal, iron ore, limestone, steel products, petroleum 
products, and other items such as overseas general cargo. Detail 
on actual port and harbor facilities is in Port Series No. 45 (revised 
1984) prepared and published by the Water Resources Support 
Center. Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, Hi-Fix surveys, support of water control center, environmental 
studies, miscellaneous inspections and reports were 
performed by Government forces at a cost of $1,171,191. Studies 
continued under extended navigation season at a cost of $252,295. 
An adjustment of -$5,009 was made to prior year costs for 
maintenance dredging performed by U.S. Hopper Dredge 
HAINS. Maintenance of disposal areas by hired labor cost 
$179,322. Location and removal of obstructions cost $1,286,002. 
The final cost and cubic yards for the dredging contract for East 
Outer and Lower Livingston Channel completed last FY is 
$107,273 and 22,214 cubic yards of shoal material. The contract 
awarded last FY for repair of Pointe Mouillee Diked Disposal 
Facility was completed at a cost of $209,987. A contract for dredging 
Pointe Mouillee Access Channel was awarded and completed 
at a cost of $187,196, removing 18,116 cubic yards of material. A 
contract for dredging East Outer and Lower Livingston Channels 
was awarded for $1,229,824. No dredging was performed this FY, 
however, cost incurred for mobilization was $49,954. Engineering 
and design for repair to disposal area cost $11,202. 
Other engineering, design, surveys, supervision and administration 
cost $158,324. A contract was awarded for construction of 
Wetland Marsh under Section 150 of the Water Resources 
Development Act of 1967. Approximately 99% of the contract 
is complete at a cost of $680,135. Engineering during construction, 
supervision and administration cost $24,617. The State of 
Michigan contributed $203,000 of the above cost. Work under 
the dike disposal program continued at a cost of $1,383. 
Latest modification of connecting channels project in the Detroit 
River is complete except for compensating works. All work in 
Trenton Channel is complete. Pertinent data concerning channels 
covered by project at end of FY are set forth in Table 31-C. 
Costs for existing project were $188,697,179, of which 
$74,780,103 was for new work ($72,969,197 regular funds and 
$1,530,688 Public Work Funds) and $113,918,459 for 
maintenance. 
12. DULUTH-SUPERIOR HARBOR, 
MN AND WI 
Location. At extreme western end of Lake Superior. Cities 
of Duluth, MN, and Superior, WI, are on north and south sides, 
respectively. (See NOAA Nautical Chart 14975.) 
Previous projects. See page 1246 of Annual Report for 1962. 
Existing project. Provides for rebuilding canal piers at Duluth 
entry, replacement or construction of piers and breakwater at 
Superior entry and dredging approaches and channels within harbor, 
St. Louis Bay, and St. Louis River. Channels vary in depth 
from 32 to 28 feet in entrances, are 27 feet deep in iron-ore route 
channels, and are from 20 to 23 feet in inner channels, (See Table 
31-B for authorizing legislation.) 
For details of authorized channel dimensions and dimensions 
of structures, see pages 1246 and 1247 of Annual Report for 1962 
and page 1011 of Annual Report for 1965. Portion of project for 
deepening Twenty-first Avenue West channel is inactive. 
Estimated cost (1967) of this portion was $577,000. 
Local cooperation. Fully complied with for active portion of 
project. 
Terminal facilities. There are 113 docks or terminals including 
some 54 major ones; all but one are privately owned. Facilities 
for handling iron ore, coal, limestone, petroleum, steel and scrap 
iron, cement, general cargo, and grain are believed adequate for 
most existing commerce. 
Operations during fiscal year. Rehabilitation: The contract 
awarded last FY for rehabilitation of North and South Piers Sections 
O, N-1, N and M is 65% complete at a cost of $4,577,329. 
Engineering and design, supervision and inspection cost 
$196,452. Maintenance: Condition surveys, environmental 
studies, support of water control center, cooperative stream gaging, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $214,962. Studies under extended 
navigation season cost $6,221. Engineering and design for major 
rehabilitation of N. Pier Secitons O, N-l, N and M, and S. 
Pier Sections O, N-l, N and M cost $9,143. Operation and 
maintenance of the museum was performed by Government forces 
at a cost of $315,847. Operation and maintenance of service 
facilities and pier was performed at a cost of $71,843. Repairs 
to breakwater and seawalls and safety maintenance were 
31-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
performed by the COLEMAN and MARKUS at a cost of 
$554,677. An adjustment of -$20,000 was made in structure 
repair costs previously performed. Maintenance of disposal area 
was performed by hired labor at a cost of $15,842. The contract 
for maintenance dredging awarded last FY was completed with 
112,625 cubic yards removed this FY at a cost of $478,724. A 
contract for maintenance dredging of contaminated materials was 
awarded this FY in the amount of $766,215. The contract is 
aproximately 12% complete with 11,361 cubic yards of material 
removed at a cost of $100,000. Engineering, design, surveys, 
supervision and administration were performed at a cost of 
$198,043. 
Work authorized prior to 1960 Act was completed in June 1956. 
Under the 1960 Act, work on the outer harbor, included in House 
Document 150, was completed in June 1965. Work in the inner 
harbor, included in House Document 196, started in May 1963, 
was completed in November 1968 except for 21st Avenue West 
channel portion which is inactive. 
The United States owns 34.90 acres of land in fee in Minnesota 
and Wisconsin of which 2.15 acres are used for a vessel yard. 
Total cost of existing project was $59,976,604, of which 
$16,109,258 was for new work and $36,801,888 for maintenance, 
and $7,065,458 for rehabilitation. 
13. FOX RIVER, WI 
Location. Rises in Columbia County, WI, and flows about 176 
miles northerly into Green Bay. Wolf River, physically a main 
river but by designation a tributary of Fox River, rises in central 
part of Fort County, WI, and flows southerly. (See NOAA 
Nautical Chart 14916 for Lake Winnebago and lower Fox River.) 
Previous projects. See page 1368 of Annual Report for 1962. 
Existing project. Deepening and widening channel of Fox 
River from DePere 7 miles above mouth to confluence of Wolf 
River, a total length of 59 miles, to 6 feet, with 9.6 feet in rock 
cut below DePere lock and 7 feet in other rock cuts on lower 
river below Menasha lock; construction and reconstruction of 19 
locks and 9 dams; a concrete retaining wall at Kaukauna; construction 
and maintenance of harbors having depths of 6 feet on 
Lake Winnebago; widening Neenah Channel to 100 feet, with 
a 6-foot depth for about 1 mile; and dredging, snagging, and 
othewise improving Wolf River 47 miles from its mouth to New 
London, depth to be 4 feet. 
Cost of completed portion of project is $513,424 for the lower 
river exclusive of previous projects. River and Harbor Act of 
1925 portion of project is considered inactive and excluded from 
cost estimate. Estimated cost (1924) of this portion is $2,886,000. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Wharf and landing facilities are, in general, 
adequate for existing needs. (See Table 31-E on locks and dams, 
Fox River, WI.) 
Operations during fiscal year. Maintenance: Condition 
surveys, boundary monumentation, miscellaneous inspections and 
reports, safety training and plans for flood emergencies were performed 
at a cost of $36,677. Federal canal banks at various locations 
were repaired at a cost of $161,945. The operation and 
maintenance of nine (9) dams and ten (10) overflow weirs and 
caretaker status maintenance of seventeen (17) locks and two (2) 
guard locks totaled $470,918. Tainter gates and seals were reconditioned 
at Menasha Dam and Kaukauna Dam at a cost of 
$77,780. Fox River O.S.H.A. Program and major miscellaneous 
items of supply totaled $21,039. Water control studies, monitoring 
and regulation of water levels were performed at a cost of 
$155,641. Engineering and design costs were $19,141. Supervision 
and administration costs were $121,702. 
Existing project is complete except for the inactive portion. 
Nineteen original locks and nine original dams have been rebuilt. 
(See Table 31-E for year of completion of each). Structures and 
dredging in pools have increased original depths generally about 
2 feet. Work remaining to complete project consists of dredging 
in upper portion of Wolf River, and rock removal and deepening 
of Neenah Channel on lower Fox River, which are no longer 
considered necessary. Existing locks and dams are generally in 
fair to good condition. Costs for existing project to end of FY 
were $3,753,334 for new work and $36,855,061 for operation 
and maintenance; a total of $40,608,395. Funds in the amount 
of $3,706,187 were expended between July 5, 1884, and June 
30, 1935, on operation and care of works of improvement under 
provisions of permanent indefinite appropriation for such 
purposes. 
14. FRANKFORT HARBOR, MI 
Location. On east shore of Lake Michigan, 204 miles northeasterly 
from Chicago, IL, and 28 miles northerly from Manistee, 
MI. (See NOAA Nautical Chart 14907). 
Existing project. Provides for constructing an exterior basin 
in Lake Michigan formed by two breakwaters, 450 feet apart at 
the outer ends, diverging at an angle of about 90 degrees, the 
main arm and shore connection on north breakwater are 972 and 
1,000 feet long, respectively, and the main arm and shore connection 
of south breakwater 1,188 and 1,400 feet long, respectively; 
for removing 801 feet of north and 1,172 feet of south 
pier; dredging basin 20 feet deep and 800 feet wide at entrance, 
decreasing toward new pier heads to 600 feet wide, dredging approach 
and entrance channel through outer basin to a depth of 
24 feet from deep water in Lake Michigan to a point 500 feet 
landward of opening between breakwaters, over the entire width 
outside the breakwaters and to a maximum width of 500 feet inside 
the breakwaters; thence to 23 feet deep through inner portion 
of outer basin to outer end of north pier, over widths decreasing 
from 500 to 160 feet; and thence to 22 feet deep between 
the piers to the inner basin in Lake Betsie; dredging an 18-foot 
deep interior basin in Lake Betsie from within 50 feet of existing 
structures on the west and extending eastward about 1,550 feet 
to easterly boundary and from within 50 feet of existing structures 
on the north and extending southward 800 feet to the southerly 
boundary; dredging a recreational craft anchorage area 10 feet 
deep and 300 feet wide, extending 600 feet eastward of the east 
limit of the interior basin, with its north side in line with the north 
limit of the basin. Breakwaters and shore connections are built 
of concrete caissons and piling capped with concrete. Inner piers 
and revetments are built of stonefilled timber cribs and piling, 
all capped with concrete, except for 476 feet of south revetment 
which consists of steel sheet piling. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
31-6

I)ETROIT. ,I1 DISTRICT 
Terminal facilities. Two car ferry slips on south shore and 
several docks along north shore of Lake Betsie. The City and 
State provide a recreational docking facility on north side of Lake 
Betsie which is open to all on equal terms. There is also a marine 
railway capable of handling small craft. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed 
by Government forces at a cost of $49,296. 
Existing project was completed in 1939, with exception of the 
latest modification which was completed in 1969. Navigation 
structures are in good condition and programmed for major repair 
on an as needed basis. For additional details on completion of 
existing project see page 1474 of Annual Report for 1962. Total 
costs for existing project to end of FY were $9,710,451, of which 
$1,955,159 (including $31,709 contributed funds) was for new 
work, $7,480,516 for maintenance, and $274,776 for 
rehabilitation. 
15. GRAND HAVEN HARBOR AND 
GRAND RIVER, MI 
Location. Harbor is on east shore of Lake Michigan. 108 miles 
northeasterly from Chicago, IL, and 23 miles northerly from 
Holland, MI. River rises in Jackson County, MI, and flows 260 
miles westerly into Lake Michigan. (See NOAA Nautical Chart 
14933, and Geological Survey Grand Rapids quadrangle.) 
Previous project. For details see page 1949 of Annual Report 
for 1915, and page 1481 of Annual Report for 1938. 
Existing project. An entrance channel protected by parallel 
piers and revetments at mouth of Grand River, a deep draft channel 
in river extending to Spring Lake, a turning basin, and a 
shallow draft channel in river extending 14.5 miles upstream to 
Bass River. Project depths are 23 feet in entrance channel, 21 
feet in river to turning basin, 18 feet in turning basin and channel 
to Spring Lake, and 8 feet in upper Grand River channel. 
For additional details see page 1461 of Annual Report for 1962. 
Dredging on northerly side of inner channel is considered inactive. 
Estimated cost of this portion (1954) is $38,600. (See Table 
31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several wharves exist for handling coal, 
limestone, sand and gravel, petroleum products, fish and 
miscellaneous commodities. There is also a car ferry slip which 
is inactive. The State and local agencies provide recreational 
boating facilities which are open to all on equal terms. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$115,653. The U.S. Cranebarge MANITOWOC performed 
repairs to the south pier sections I, J, J-l, and K at a cost of 
$93,799. A payment of $118,522 was made this FY for a claim 
on the contract completed in FY 85 for repair of North and South 
Revetments. An adjustment of -$15,272 was made to the 
maintenance dredging contract completed last FY. A contract was 
awarded and completed this FY for maintenance dredging at a 
cost of $210,033, removing approximately 33,564 cubic yards 
of shoal material from the outer harbors. This contract was also 
for beach nourishment. Engineering, design, surveys, supervision 
and administration cost $93,209. Condition surveys, environmental 
studies, temporary permits, miscellaneous inspections 
and reports in connection with Section 111 of P.L. 90-483 
were performed at a cost of $54,951. Contract awarded last FY 
for beach nourishment was completed at a cost of $51,860. Beach 
nourishment in conjunction with above maintenance dredging contract 
cost $108,199. Another contract for mitigation of shore 
damage was awarded and completed this FY at a cost of 
$936,324. Engineering, design, supervision and administration 
cost for Section 111 was $53,253. 
Existing project was substantially completed in 1949. For additional 
details on completion of existing project see page 1463 
of Annual Report for 1982. Structures are generally in good condition; 
repairs are made on an as needed basis. Total costs of 
existing project to end of FY were $25,179,796, of which 
$1,458,469 was for new work, $22,907,714 for maintenance, 
and $813,613 for rehabilitation. 
16. GRAND MARAIS HARBOR, MN 
Location. On north shore of Lake Superior, 106 miles northeasterly 
from Duluth, MN. (See NOAA Nautical Chart 14967.) 
Existing project. Provides breakwater piers to narrow the entrance; 
concrete seawalls across ledge at southeast corner of harbor; 
an anchorage area and a small-boat basin protected by a rubblemound 
breakwater. Project depths are 16 feet in anchorage 
area increasing to 20 feet near entrance and 8 feet in small-boat 
basin. For additional details see page 1014 of Annual Report for 
1965. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two inactive pulpwood wharves and 
several fish wharves, all privately owned. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys and environmental studies were performed by Government 
forces at a cost of $20,268. Minor repairs to navigation 
structures were performed by hired labor at a cost of $667. The 
contract for repair of the East and West Breakwater awarded last 
FY was completed at a cost of $988,359. Engineering, design, 
supervision and administration cost $61,739. 
Existing project is complete. Total costs of existing project to 
end of FY were $3,647,770. 
17. GREEN BAY HARBOR, WI 
Location. At mouth of Fox River, at head of Green Bay, about 
180 miles from Milwaukee, WI, via Sturgeon Bay Canal, and 
about 49 miles southwest of Menominee Harbor, MI, and WI. 
(See NOAA Natucial Chart 14918.) 
Previous projects. See page 1366 of Annual Report for 1962. 
Existing project. See Chicago District 1979 Annual Report, 
Table 30-C, p. 30-30. 
For more detailed description of project see page 1216 of Annual 
Report for 1963. 
Cost of completed portion of project is $9,335,000, Federal, 
and non-Federal cost is $490,000 including $100,000 contributed 
31-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
funds. Local interests requested that the inactive portion of the 
1962 River and Harbor Act, consisting of dredging the reach from 
150 feet downstream of the C.&N.W. Railway Bridge to 1,700 
feet upstream of this bridge, be reactivated and the authorization 
modified to include deepening the adjacent turning basin and 
modifying the C.&N.W. Railway Bridge to provide increased 
horizontal clearance. Estimated cost of this portion (1985) is 
$5,220,000 Federal and $114,000 non-Federal. (See Table 31-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 16 wharves for handling coal, 
petroleum products, cement, limestone, general overseas cargo 
and miscellaneous commodities. Facilities are considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous inspections and 
reports were performed at a cost of $189,997. Maintenance of 
the disposal area was performed by hired labor at a cost of 
$34,791. An adjustment of -$14,891 was made on a dredging 
contract awarded and completed last FY. The contract for 
maintenance dredging awarded last FY was completed removing 
approximately 120,143 cubic yards of material at a cost of 
$1,101,792. A contract was awarded for maintenance dredging 
of the Bay Section in the amount of $832,000. The contract is 
22% complete with approximately 13,537 cubic yards being 
removed at a cost of $200,000. Engineering, design, surveys, 
supervision and administration cost $93,175. Engineering and 
design for construction of a confined disposal facility continued 
at a cost of $310,913. 
Existing project is complete. The 1962 modification was started 
in November 1966 and completed in September 1973, except for 
dredging the reach from 150 feet downstream of the C.&N.W. 
Railway Bridge to 1,700 feet upstream of this bridge. Dredging 
of the turning basin above Chicago & Northwestern Railways 
Bridge was commenced in August 1938. The turning basin was 
enlarged under authority of Section 5 of the River and Harbor 
Act of March 4, 1915, in order to provide sufficient area for the 
large ships that use it. The work was performed as part of a 
maintenance dredging contract in September and October 1973. 
East revetment at Grassy Island was entirely removed in July 
1935. Dredging Fox River and entrance channel to Tail Point 
Light was completed in September 1967. The total cost of the 
existing project was $32,299,640, of which $18,005,884 were 
regular funds and $940,800 Public Works funds; $9,946,395 for 
new work and $22,353,245 for maintenance. The new work costs 
do not include $100,000 contributed funds. 
18. HAMMOND BAY HARBOR, MI 
Location. On northwest of Lake Huron, 35 miles southeast 
of Straits of Mackinac. (See NOAA Nautical Chart 14881.) 
Existing project. Provides for a harbor of refuge, protected 
by breakwater structures, extending to 12-foot depth contour in 
the lake; for dredging a harbor basin 10 feet deep; and for dredging 
an entrance channel 12 feet deep. 
Local cooperation. Fully complied with. 
Terminal facilities. Public facilities being planned by State and 
local agencies. Plans and specifications are complete, but construction 
has not started. 
Operations during fiscal year. Maintenance: Condition 
surveys were performed by Government forces at a cost of 
$12,430. Condition surveys and environmental studies in connection 
with the Section 111 project were performed at a cost 
of $26,647. 
The existing project was completed in 1965. Total costs of existing 
project to end of FY were $1,568,900, of which $1,092,366 
was for new work and $476,534 for maintenance. 
19. HARBOR BEACH HARBOR, MI 
Location. On west shore of Lake Huron about 60 miles north 
of Port Huron, MI. (See NOAA Nautical Chart 14862.) 
Existing project. Harbor of refuge protected by three 
breakwaters; a main entrance 23 feet deep; and an anchorage area 
21 feet deep. For additional details see page 1485 of Annual 
Report for 1962. (See Table 31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Coal and limestone are received at a private 
wharf. In addition, there is a public recreational craft pier, a Coast 
Guard pier, and several small installations engaged in docking 
and servicing light-draft commercial and recreational vessels. 
These facilities satisfy current commerce and traffic requirements. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed 
by Government forces at a cost of $33,751. An adjustment of 
-$40,000 was made this FY in structure repairs performed in FY 
81. A contract to dredge the new Harbor marina was awarded 
and completed at a cost of $242,281 removing approximately 
26,231 cubic yards of material. Engineering and design for repair 
of main breakwater was performed at a cost of $49,705. Engineering, 
design, surveys, supervision and administration cost $24,957. 
Existing project was completed in 1928. For additional details 
on completion of existing project see page 1485 of Annual Report 
for 1962. Total costs to end of FY were $7,665,223, of which 
$1,200,598 was for new work, $6,270,121 for maintenance, and 
$194,504 for rehabilitation. 
20. HARRISVILLE HARBOR, MI 
Location. On the west shore of Lake Huron, 20 miles north 
of Oscoda and 30 miles south of Alpena. (See NOAA Nautical 
Chart 14864.) 
Existing project. A harbor of refuge protected by breakwater 
structures, and dredging an entrance channel 12 feet deep and 
a harbor basin 10 feet deep. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Dockage facilities built by State and local 
agencies for recreational craft; considered adequate for existing 
commerce. 
Operations during fiscal year. New Work: Financial closeout 
on the Section 107 project was accomplished at a cost of 
$12,281. Maintenance: Condition surveys, environmental studies, 
miscellaneous inspections and reports were performed by Government 
forces at a cost of $3,770. Condition surveys and en- 
31-8

DETROIT, MI DISTRICT 
vironmental studies in conjunction with the Section 111 project 
cost $24,812. Engineering, design, supervision and administration 
cost $745. 
Total costs of project to end of FY were $3,471,061, of which 
$2,679,158 was for new work (includes $287,454 contributed 
funds) and $791,903 for maintenance. 
21. HOLLAND HARBOR, MI 
Location. On east shore of Lake Michigan 95 miles northeasterly 
from Chicago, IL, and 23 miles southerly from Grand 
Haven, MI. (See NOAA Nautical Chart 14932.) 
Previous project. For details see page 1948 of annual Report 
for 1915 and page 1478 of Annual Report for 1938. 
Existing project. An outer breakwater protected approach 
channel in Lake Michigan, an entrance channel to Lake Macatawa 
protected by piers and revetments, a channel through Lake 
Macatawa into Black River, and a turning basin. Project depths 
are 23 feet in outer portion of approach channel decreasing to 
21 feet at outer end of inner piers, 21 feet to upper end of project, 
and 18 feet in turning basin. For additional details see page 
1458 of Annual Report for 1962. 
Widening bend of entrance channel into Lake Macatawa is in 
an active category as a result of a reclassification recommendation 
approved by the Office of the Chief of Engineers on August 
20, 1981. Estimated cost of this portion (1985) is $3,510,000, 
Federal and $102,000 non-Federal (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Fully complied with for completed portions 
of project. Work authorized by Act of 1954 is subject to 
condition that work on either or both proposed modifications may 
be undertaken by the United States provided local interests furnish 
all lands except 1.5 acres of Federal lands, easements, rightsof-
way, and suitable spoil disposal areas for initial work and future 
maintenance; remove buildings and other structures, except existing 
revetments, from lands to be furnished; and hold the United 
States free from damages. 
Terminal facilities. Wharves are at inner end of Lake 
Macatawa, and used for handling coal, building materials, 
petroleum products, and miscellaneous commodities. Two shipbuilding 
yards are on south shore of the lake. Holland provides 
a public wharf for small craft. Facilities are considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, temporary permits, miscellaneous 
inspections and reports were performed by Government forces 
at a cost of $106,182. Repairs to North and South breakwater 
connector were performed this FY by hired labor using the 
Cranebarge MANITOWOC at a cost of $76,987. A contract for 
maintenance dredging of the outer harbor was completed at a cost 
of $210,363, removing approximately 35,099 yards of dredge 
material. This contract was also for beach nourishment. An adjustment 
of -$30,436 was made to the contract completed last 
FY for maintenance dredging. Maintenance of the disposal area 
was performed by hired labor at a cost of $475. Engineering and 
design for repair of South Revetment, Sections I thru P, was performed 
at a cost of $66,893. Engineering, design, supervision 
and administration cost $54,412. Condition surveys, environmental 
studies and miscellaneous inspections in connection with Section 
111 of P.L. 90-483 were performed at a cost of $36,426. 
A contract for mitigation of shore damage was completed at a 
cost of $112,250. Beach nourishment in conjunction with above 
maintenance dredging contract cost $70,029. Another contract 
for mitigation of shore damage was awarded this FY and completed 
at a cost of $548,130. Engineering, design, supervision 
and administration cost $62,084. 
Existing project, with exception of widening bend in revetted 
entrance channel authorized by Act of September 3, 1954, was 
completed in 1957. For additional details on completion of existing 
project, see page 1460 of Annual Report for 1962. Costs 
of existing project to end of FY were $1,392,827 for new work 
($1,180,502 regular funds, $176,620 for previous project and 
$35,705 contributed funds), $15,498,960 regular funds for 
maintenance, and $502,452 regular funds for rehabilitation, for 
a total of $17,394,225. 
22. THE INLAND ROUTE, MI 
Location. A series of interconnected lakes and streams stretching 
across northern tip of Lower Peninsula of Michigan, and extends 
from Conway near Lake Michigan to Cheboygan on Lake 
Huron; a distance of 35 miles. Crooked and Indian Rivers are 
connecting channels in the waterway. (See NOAA Nautical Chart 
14886.) 
Existing project. Provides for a channel 30 feet wide and 5 
feet deep, with necessary widening at bends, through Crooked 
and Indian Rivers, and Crooked, Burt, and Mullett Lakes, and 
from Conway (west end of Crooked Lake) to navigation lock at 
Cheboygan; in Pickerel Channel from Pickerel Lake to Crooked 
Lake. It also provides for suitable jetties at head of Indian River. 
The addition of a lock and dam was approved by the Chief of 
Engineers on September 2, 1964, to correct a design deficiency. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. None exist for commercial cargo-handling 
along the Crooked and Indian Rivers. Numerous small privately 
owned timber piers and wharves, some equipped with covered 
boat wells for serving and storing recreational craft, have been 
constructed. Landings maintained by hotel and resort operators 
are open to the public for transfer of passengers. Public docks 
are at Conway and Oden on Crooked Lake; the Village of Indian 
River, Topinabee, and Mullett Lake Village on Mullett Lake; 
and at Cheboygan. About 30 highways dead end at the water's 
edge, permitting public access for various marine activities. Dock 
facilities are considered adequate for existing traffic. 
Operations during fiscal year. Maintenance: The navigation 
lock was operated and maintained by the Village of Alanson at 
a cost of $33,525. An adjustment of -$24 was made in the closeout 
cost for operation of the lock during previous fiscal years 
by the Village of Alanson. In 1986 the lock was operated only 
on weekends from April 21 through April 29 from 9:00 a.m. 
to 5:00 p.m.; from May 5 through September 30 it was open 
from 6:00 a.m. to 10:00 p.m. Condition surveys, cooperative 
stream gaging, miscellaneous inspections and reports were performed 
by Government forces at a cost of $27,165. 
31-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
The existing project was completed in 1958. The lock and dam 
was completed in FY 1968. For additional details see page 1382 
of Annual Report for 1960. Total costs to end of FY were 
$3,524,356, of which $770,222 was for new work and 
$2,606,134 for maintenance with $148,000 contributed by local 
interests. 
23. KENOSHA HARBOR, WI 
Location. On west shore of Lake Michigan about 35 miles 
south of Milwaukee and about 54 miles north of Chicago. (See 
NOAA Nautical Chart 14904.) 
Previous project. See page 1390 of Annual Report for 1962. 
Existing project. For detailed description see page 1237, Annual 
Report for 1963. Estimated (1985) Federal cost is $698,000 
exclusive of amounts expended on previous projects and $43,000 
non-Federal which includes $3,000 local contribution. (See Table 
31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Three wharves used for miscellaneous 
foreign overseas commodities and autos, and also several fishing 
wharves. While these facilities are considered generally adequate 
for existing commerce, more efficient use of existing terminals 
and utilization of available frontage for development of additional 
terminals should be made. 
Operations during fiscal year. New Work: $8,077 was spent 
in FY 86 on the Section 107 DPR which was terminated due to 
lack of local interest. Maintenance: Condition surveys, environmental 
studies, miscellaneous inspections and reports were 
performed by Government forces at a cost of $71,655. An adjustment 
of -$20,000 was made in structure repair costs previously 
performed. Repairs to S. Pier and breakwater were performed 
by the cranebarge MANITOWOC at a cost of $64,013. Engineering 
and design for maintenance dredging and repair of Confined 
Disposal Facility contract was completed at a cost of $42,157. 
A contract was awarded for maintenance dredging and repair of 
Confined Disposal Facility in the amount of $573,519. No work 
was performed this FY. Engineering, design, supervision and 
administration were performed at a cost of $11,091. 
Existing project is complete except for dredging 25-foot strips 
adjacent to the north and south piers which will be completed 
after rehabilitation of the piers. The north and south piers were 
completed in 1900 and the breakwater in 1909. The north pier 
is in excellent condition. The south pier and breakwater are in 
generally good condition. The total costs of the existing project 
to end of FY were $9,079,819, of which $7,907,899 were regular 
funds and $27,658 Emergency Relief funds; $529,432 being for 
new work, $7,277,112 for maintenance, and $1,270,275 for 
rehabilitation. The new work costs do not include $3,000 contributed 
funds. 
24. KEWAUNEE HARBOR, WI 
Location. On west shore of Lake Michigan, about 105 miles 
north of Milwaukee, WI, and about 78 miles from Green Bay, 
via Sturgeon Bay Canal. Harbor is at mouth of Kewaunee River. 
(See NOAA Nautical Chart 14908.) 
Previous projects. See page 1375 of Annual Report for 1962. 
Existing project. See Chicago District 1979 Annual Report, 
Table 30-C, p. 30-31. 
Costs of completed project are $603,021, Federal, and $9,000 
non-Federal, exclusive of amount expended on previous projects. 
Uncompleted portion (estimated $200,000-July 1965) of 1935 
River and Harbor Act is considered inactive, and excluded from 
present cost estimate. The portion authorized by the 1960 River 
and Harbor Act was deauthorized in 1977. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two car-ferry slips, a petroleum tank farm, 
a Corps of Engineers project office, and several fishing wharves. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed 
by Government forces at a cost of $65,196. Minor repairs to diked 
disposal area were performed by hired labor at a cost of $1,813. 
Repairs to CDF and N. Breakwaters were performed by the 
cranebarge MANITOWOC at a cost of $57,248. Engineering and 
design for repair to N. Stub Pier Section A to be performed by 
contract next FY cost $73,962. Engineering, design, surveys, 
supervision and administration cost $26,788. 
Active portion of existing project is complete. The north pier 
was completed in 1897 and the remaining portion is in generally 
good condition. Rehabilitation of the south pier was completed 
in June 1967. Construction of north breakwater and shore connection, 
except for a gap of 150 feet about 830 feet from 
shoreward end, and removal of outer 706.5 linear feet of north 
pier was commenced in September 1935 and completed in June 
1937. Removed 500 linear feet of north pier in April/May 1963 
and widened and deepened the adjacent channel in 1965. Outer 
end of the north pier was struck and severely damaged by car 
ferry vessel in October 1973 and a 24-foot section at outer end 
was subsequently removed, thus reducing the structure to a length 
of 626 feet. Dredging entrance channel in interior basin to existing 
project depth was commenced in April and completed in 
October 1938. Kewaunee River is navigable to about 6.5 miles 
above mouth for craft drawing not more than 4 feet. Total cost 
of existing project to end of FY was $7,872,406, of which 
$758,333 was for new work ($183,021 regular and $420,000 
Emergency Relief funds) $6,496,773 regular funds for 
maintenance and $617,300 regular funds for rehabilitation. 
25. KEWEENAW WATERWAY, MI 
Location. In Lake Superior across Keweenaw Peninsula in upper 
peninsula of Michigan. The west entrance is 169 miles east 
of Duluth, MN. (See NOAA Nautical Chart 14972.) 
Existing project. A navigable channel, minimum width 300 
feet, 25 miles long, partially natural and partially artificial, across 
Keweenaw Peninsula via Portage Lake. For details see page 1121 
of Annual Report for 1963. Completed cost for new work is 
$5,967,700. Portion of project providing for extension of lower 
entrance breakwater and necessary alteration or replacement of 
structures due to deepening channels is inactive and excluded from 
foregoing cost. Estimated cost (1957) of this portion was 
$3,315,000. (See Table 31-B for authorizing legislation.) 
31-10

DETROIT, MI DISTRICT 
Local cooperation. None required. 
Terminal facilities. Six coal docks, a petroleum dock, and 
several general merchandise and miscellaneous wharves, all 
privately owned. Facilities are considered adequate for existing 
commerce. Also present is a government constructed recreational 
area with facilities to include a picnic area and small boat landing 
range. 
Operations during the fiscal year. Maintenance: Condition 
surveys, safety studies, and miscellaneous inspections and reports 
were performed by Government forces at a cost of $42,880. 
Engineering and design for major repairs of the upper entry revetment 
was completed at a cost of $100,878. Safety maintenance 
was performed by hired labor at a cost of $2,444. The Derrickbarge 
COLEMAN performed breakwater repair at a cost of 
$244,321. An adjustment of -$20,000 was made in prior year 
costs for structure repairs. A contract for repair of E. and W. 
Revetments was awarded this FY in the amount of $2,348,800. 
The contract is approximately 9% complete at a cost this FY of 
$250,000. Engineering, design, supervision and administration 
cost $47,916. A contract for Construction of a Confined Disposal 
Facility was awarded for $902,706. No work was performed this 
FY. Engineering, design, supervision and administration for Dike 
Disposal cost $220,193. 
Active portion of the project is complete. Breakwaters are in 
generally good condition except for a weakness occurring in about 
300 feet of substructure of breakwater lower entrance, and major 
storm damage repairs needed for stone-covered portions of 
breakwater at upper entrance. Mooring pier at Lily Pond requires 
repairs to halt movement and permit dredging to project depth 
adjacent thereto. The flared revetment at the upper entry should 
be modified to restrict wave action from the stilling basin entrance. 
Total costs of existing project to end of FY were 
$17,962,034, of which $5,974,141 was for new work, and 
$11,987,893 for maintenance. 
26. KNIFE RIVER HARBOR, MN 
Location. Near mouth of Knife River on north shore of Lake 
Superior, 19 miles northeasterly from Duluth, MN, and 7 miles 
southwest of Two Harbors, MN. (See NOAA Nautical Chart 
14966.) 
Existing project. Provides for an entrance channel with a 
system of overlapping breakwaters, using the existing breakwater 
and a new breakwater constructed of 731 feet of rock rubblemound. 
The entrance channel is 9 feet deep and an inner straight 
channel is 8 feet deep, 50 feet wide, and 600 feet long with a 
public marina and side channel at its inner end. For additional 
details see page 1110 of Annual Report for 1963. A modification 
to correct a design deficiency was authorized in 1974. (See 
Table 31-B for authorizing legislation.) Total estimated approved 
Federal cost (1985) is $2,571,000 and $21,700 non-Federal 
cost. 
Local cooperation. Local interests are to furnish easements 
on 15.08 acres of land. 
Terminal facilities. Local interests have installed pile-andtimber 
docks on both sides of straight channel. Lake County has 
completed construction by contract of a marina along the east 
wing of the inner harbor. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed 
by Government forces at a cost of $8,973. 
Project was completed in June 1958. Breakwater and spending 
beach are in good condition. The existing breakwater does not 
effectively prevent waves caused by northeasterly winds from 
entering the entrance channel. This results in unsatisfactory and 
unsafe harbor entrance conditions during storms. Mooring conditions 
in the main channel and Y-branches of the inner harbor 
are also adversely affected. Plans and specifications for the construction 
of a breakwater to correct a design deficiency to reduce 
wave damage and improve navigation conditions were completed 
and approved by NCD in 1982. Total project costs to end of FY 
were $704,118, of which $412,944 was for new work and 
$291,174 for maintenance. 
27. LA POINTE HARBOR, WI 
Location. At westerly end of Madeline Island in the Apostle 
Island group off the south shore of Lake Superior. (See NOAA 
Nautical Chart 14973.) 
Existing project. Provides for reconstruction of 73.5 feet of 
the existing breakwater, extending the breakwater 126.24 feet 
with 5 new steel sheet pile cells, harbor dredging and related 
work. The harbor is 10 feet deep in the entrance and 8 feet deep 
in the basin. Project was authorized by Section 107 of the 1960 
River and Harbor Act (Public Law 645, 86th Cong., as amended.) 
Local cooperation. Fully complied with. 
Terminal facilities. A 400-foot L-shaped dock was constructed 
and rehabilitated by local interests, not as a part of the Federal 
project. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed 
by Government forces at a cost of $2,400. 
The existing project was completed in 1967. Total cost of existing 
project at end of FY was $219,258. 
28. LAKE ST. CLAIR, MI CHANNELS 
Location. Lake St. Clair, a section of Great Lakes connection 
channels, is an expansive shallow basin having a vessel track 
length of about 15 miles from mouth of St. Clair River to head 
of Detroit River. (See NOAA Nautical Chart 14850.) 
Previous project. For details see page 2882, Annual Report 
for 1896; pages 1957-58, Annual Report for 1915; and page 1539, 
Annual Report for 1938. 
Existing project. An improved channel through Lake St. Clair 
800 feet wide, 27.5 feet deep, and about 14.5 miles long; extending 
from mouth of Southeast Bend cutoff channel at lower end 
of St. Clair River to head of Detroit River Channel. (See Table 
31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. None 
Operations during fiscal year. Maintenance: Condition 
surveys, Hi-Fix surveys, support of Water Control Centers, environmental 
studies, inspections and reports were performed at 
a cost of $63,291. Environmental studies in connection with 
31-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
the extended navigation season cost $43,480. Maintenance of 
disposal area was performed by hired labor at a cost of $16,906. 
An adjustment of -$32,990 was made to prior year costs for 
maintenance dredging performed by the U.S. Hopper Dredge 
MARKHAM. Engineering and design for removal of the trestle 
at Dickinson Island disposal area was completed at a cost of 
$10,589. A contract for removal of the trestle at Dickinson Island 
was awarded and completed at a cost of $150,000. Surveys, 
supervision and administration cost $9,387. 
Total costs for existing project at the end of FY were 
$19,929,949, of which $7,675,357 was for new work 
($6,010,582 regular funds and $1,008,595 public work funds) 
and $12,254,592 for maintenance. 
29. LELAND HARBOR, MI 
Location. A light-draft harbor on eastern shore of Lake 
Michigan at mouth of Carp River, about 40 miles north of 
Frankfort, MI, and 40 miles southwest of Charlevoix, MI. (See 
NOAA Nautical Chart 14912.) 
Existing project. Provides for a harbor of refuge consisting 
of a breakwater about 1,200 feet long, a protected anchorage and 
maneuver area about 3 acres in extent and 10 feet deep, a 12-foot 
deep flared approach channel decreasing in width to 90 feet, an 
existing south pier 440 feet long, a 35-foot long cellular extension 
to south pier, an entrance channel 6 feet deep and 40 feet 
wide extending to mouth of Carp River, and for elimination of 
existing north pier. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Privately owned wharves on each side of 
river below the dam which is 400 feet above the river mouth. 
These wharves serve the local fishing interests and recreational 
craft. Public facilities are operated by the State and local agencies. 
All available dockage space is utilized. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$14,638. Minor repairs to navigation structures were performed 
this FY by hired labor at a cost of $143. A contract was awarded 
and completed for maintenance dredging this FY removing approximately 
24,811 cubic yards of shoal material at a cost of 
$71,399. Engineering, design, surveys, supervision and administration 
cost $18,555. 
The existing project was completed in 1932 except for the 1962 
authorization which was completed in 1967. The total costs to 
end of FY were $2,610,737, of which $1,027,089 was for new 
work, $1,512,970 for maintenance and $70,678 for rehabilitation. 
30. LEXINGTON HARBOR, MI 
Location. On southwest shore of Lake Huron, 20 miles north 
of Port Huron, MI. (See NOAA Nautical Chart 14862.) 
Existing project. Provides for two offshore breakwaters opening 
to the southeast and totaling about 2,400 feet long with provisions 
for recreational fishing on the main breakwater; an anchorage 
and maneuver area of about 5 acres, 8 feet deep; and 
a flared approach channel 10 feet deep, decreasing to 160 feet 
in width through the breakwaters. Project also provides for recreational 
fishing facilities. Estimated (1979) Federal cost for new 
work is $1,647,306 excluding $1,088,888 to be contributed by 
local interests. (See Table 31-B for authorizing legislation.) 
Local cooperation. Assurances of local cooperation were furnished 
by Michigan Department of Natural Resources to the 
Secretary of the Army. The cash contribution was $1,088,888. 
Terminal facilities. An existing public fishing pier of open 
pile construction is not adequate for existing and prospective commerce. 
Complete boating facilities are planned by State and local 
agencies in connection with the harbor construction. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, monitoring, inspections and 
reports under Section 111 were performed by Government forces 
at a cost of $39,634. A contract for beach nourishment awarded 
last FY was completed at a cost of $143,818. A contract for beach 
nourishment was awarded and completed this FY at a cost of 
$198,000. Engineering, design, supervision and administration 
were performed at a cost of $25,945. 
The existing project was completed during FY 1977. Total costs 
of existing project were $3,940,406, of which $3,107,192 (includes 
$1,088,888 contributed funds) was for new work and 
$833,214 for maintenance. 
31. LITTLE LAKE HARBOR, MI 
Location. On south shore of Lake Superior 21 miles west of 
Whitefish Point and 30 miles east of Grand Marais, MI. (See 
NOAA Nautical Chart 14962.) 
Existing project. Provides for a small-craft harbor of refuge 
by dredging an entrance channel 12 feet deep from Lake Superior 
into Little Lake, suitably protected by breakwaters and 
revetments. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Only terminal facility at project site consists 
of a public dock built by State of Michigan for light-draft 
craft. 
Operations during fiscal year. Maintenance: Condition 
surveys and environmental studies wee performed by Government 
forces at a cost of $18,122. The design deficiency study 
continued at a cost of $50,141. An adjustment of -$1,767 was 
made in cost for maintenance dredging contract completed last 
FY. A maintenance dredging contract was awarded and completed 
this FY for $196,819 with approximately 15,961 cubic yards of 
shoal material removed. Engineering, design, surveys, supervision 
and administration cost $15,814. 
This project is considered complete; however, because of shifting 
sand, the harbor entrance shoals rapidly with the result that 
full project depth is not usually available. An analysis for the 
Design Deficiency Report was submitted to North Central Division 
in March 1978 and approved. Total cost at end of FY is 
$3,360,493. 
32. LUDINGTON HARBOR, MI 
Location. On east shore of Lake Michigan, 156 miles northeasterly 
from Chicago, IL, and 67 miles northerly from Grand 
Haven, MI. (See NOAA Nautical Chart 14937.) 
31-12

DETROIT, MI DISTRICT 
Previous project. For details see page 1951 of Annual Report 
for 1915, page 1491 of Annual Report for 1938, and page 1307 
of Annual Report for 1963. 
Existing project. Provides for an exterior basin in Lake 
Michigan protected by north and south breakwater, north 
breakwater is 1,800 feet long and south breakwater 1,700 feet 
long, 550 feet apart at outer ends, diverging at an angle of 90 
degrees, with shore connections, 1,103 and 2,004 feet long, 
respectively; for dredging exterior basin to 18 feet deep with a 
maximum width of 1,500 feet; for a channel with a depth of 29 
feet from deep water in Lake Michigan decreasing to 27 feet at 
the west end of the north pier, over a maximum width of 600 
feet; thence a channel with a depth of 27 feet, over a minimum 
width of 230 feet with necessary widening at Pere Marquette 
Lake; and for inner piers and revetments, 1,649 feet long on north 
and sufficiently long on the south for turn at Pere Marquette Lake. 
The estimated (1977) Federal cost for new work is $8,250,000. 
Estimated total costs for local interests is $147,000. (See Table 
31-B for authorizing legislation.) 
Local cooperation. Has been complied with. 
Terminal facilities. In addition to main terminal of Chesapeake 
& Ohio Railway Co., consisting of three car ferry slips, a wharf, 
and warehouses, there are several wharves which handle coal, 
limestone, and miscellaneous commodities. Facilities adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$67,794. Repair to the North Breakwater was performed this FY 
using the Cranebarge MANITOWOC at a cost of $139,694. 
Engineering and design for repair to the North Revetment and 
South Breakwater was completed at a cost of $113,681. A contract 
for repairs to North Revetment and South Breakwater was 
awarded in the amount of $2,133,337. No work was performed 
this FY. Engineering, design, surveys, supervision and administration 
cost $16,529. Under the Section 111 program, an 
adjustment of -$54,105 was made to the contract for Beach 
Nourishment completed last FY. Surveys, monitoring, supervision 
and administration cost $7,174. 
Existing project was completed in 1918. For additional details 
on completion of existing project see page 1469 of Annual Report 
for 1962. Total costs for existing project to end of FY were 
$17,928,307, of which $8,532,202 was for new work, 
$9,038,192 for maintenance, and $357,913 for rehabilitation. 
33. MACKINAC ISLAND HARBOR, MI 
Location. On the southeast side of Mackinac Island which lies 
just east of the Straits of Mackinac, the connecting waterway between 
Lakes Michigan and Huron. (See NOAA Nautical Chart 
14881.) 
Existing project. Provides for the construction of two 
breakwaters 910 and 950 feet long from Mission and Biddle 
Points, respectively. The breakwaters are of rubblemound construction. 
Estimated (1969) Federal cost for new work is 
$230,000, excluding $105,000 to be contributed by local interest. 
(See Table 30-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Consists of private piers used by small 
commercial vessels and light-draft passenger ferry boats. 
Facilities for recreational craft are provided by the State dock 
which is open to all on equal terms. These facilities satisfy current 
traffic requirements, however, they are usually hard pressed 
during the annual Chicago to Mackinac-Port Huron to 
Mackinac sailboat races. 
Operations during fiscal year. Maintenance: Condition 
surveys and miscellaneous inspections and reports were performed 
by Governemnt forces at a cost o $10,816. Engineering and 
design for repair of the east and west breakwater was performed 
at a cost of $11,207. 
The existing project was completed in 1967. Total costs to end 
of FY were $427,582, of which $334,089 ($105,004 Contributed 
Funds) was for new work and $93,493 for maintenance. 
34. MACKINAW CITY HARBOR, MI 
Location. On east shore of extreme northern tip of Lower 
Peninsula of Michigan, on southerly shore of Straits of Mackinac. 
(See NOAA Nautical Chart 14881.) 
Existing project. Provides for a breakwater, about 430 feet 
long, perpendicular to existing railroad pier; wave absorbing slope 
protection for about 300 feet along harbor side of railroad pier; 
an entrance channel 10 feet deep with a minimum width of 100 
feet, and a protected anchorage and maneuver area about 3.3 acres 
in extent with depths varying from 6 to 8 feet; and maintenance 
of outer 200-foot portion of existing north breakwater. (See Table 
31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Additional public facilities are being 
planned by State and local agencies in addition to existing facilities 
owned by the Village of Mackinaw City but leased to a private 
marina operator. 
Operations during fiscal year. Maintenance: Condition 
surveys were performed by Government forces at a cost of 
$16,057. An adjustment of -$438 was made to minor structure 
repairs performed by hired labor last FY. 
Existing project is completed. Total costs of existing project 
to end of FY are $348,633, of which $272,572 (includes $136,286 
contributed funds) was for new work and $76,061 for 
maintenance. 
35. MANISTEE HARBOR, MI 
Location. On east shore of Lake Michigan, 179 miles northeasterly 
from Chicago, IL, and 26 miles northerly from 
Ludington, MI (See NOAA Nautical Chart 14938.) 
Previous project. For details see page 1952 of Annual Report 
for 1915, and page 1493 of Annual Report for 1938. 
Existing project. An entrance channel in Lake Michigan protected 
by a breakwater, piers, and revetment; a channel in 
Manistee River to Manistee Lake; and Federal participation in 
cost of replacing Maple Street Bridge. Project depths are 25 feet 
in entrance channel and 23 feet in river channel. For additional 
31-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
details see page 1470 of Annual Report for 1962. (See Table 31-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Installations are on both sides of river and 
on Manistee Lake. Commerce handled includes coal, sand, salt, 
and general cargo. In addition, there is a Government wharf and 
a State and City owned recreational craft pier which is open to 
the public. These facilities satisfy current commerce requirement. 
Operations during fiscal year. Maintenance: Condition 
surveys, inspections and miscellaneous reports were performed 
by hired labor at a cost of $47,157. Repairs to safety features 
were performed at a cost of $12,602. Engineering and design 
for repair of the North Revetment was completed at a cost of 
$65,239. A contract was awarded in the amount of $700,000 for 
repair of the North Revetment. Approximately 63% of the work 
was completed at a cost of $441,000. A contract for maintenance 
dredging was awarded and completed at a cost of $168,658 
removing approximately 32,506 cubic yards of shoal material. 
Engineering, design, supervision and administration cost $56,878. 
Existing project was completed in August 1967. For additional 
details on completion of existing project see page 1470 of Annual 
Report for 1962. Total costs for existing project from regular 
funds to end of FY were $9,197,573, of which $2,696,522 was 
for new work, $5,126,887 for maintenance, and $1,374,164 for 
rehabilitation. 
36. MANITOWOC HARBOR, WI 
Location. On west shore of Lake Michigan about 79 miles 
north of Milwaukee and about 106 miles from Green Bay via 
Sturgeon Bay Canal. (See NOAA Nautical Chart 14922.) 
Previous projects. See page 1379 of Annual Report for 1962. 
Existing project. The total estimated (Oct. 1981) project cost 
is $3,080,000; the Federal cost is $1,085,000 and the non-Federal 
cost is $1,995,000, which is a cash contribution, see Chicago 
District Annual Report for 1979, Table 30-C. 
For detailed description see page 1228 of Annual Report for 
1963. Estimated costs (1970) of new work for 1968 modification 
are $81,000 Federal and $30,000 non-Federal which includes 
a cash contribution of $18,000. Work on the 1968 modification 
was postponed until 1982. The portion authorized by the 1962 
River and Harbor Act is inactive and estimated (1970) at 
$1,150,000, Federal, and $105,000 non-Federal. (See Table 31-B 
for authorizing legislation.) 
Construction of a small boat harbor within the existing harbor 
was authorized by the Chief of Engineers, June 26, 1979, and 
720-foot channel extension reaffirmed in July 1982, under 
authority of Section 107, 1960 River and Harbor Act, as 
amended. 
Local cooperation. Fully complied with for complete modifications. 
For 1968 modification local interests must make an annual 
cash contribution equivalent to 50% of the annual costs 
associated with construction and maintenance of the channel extension 
until such time that a second user utilizes the channel extension. 
Such a contribution is presently estimated at $14,200; 
provide without cost to the United States all lands, easements, 
and rights-of-way required for construction and subsequent 
maintenance, including suitable areas determined by the Chief 
of Engineers to be required in the general public interest for initial 
and subsequent disposal of dredged materials, and the 
necessary retaining dikes, bulkheads, and embankments therefor 
or the costs of such retaining works; hold and save the United 
States free from damages due to the construction works and subsequent 
use, operation, and maintenance of the project, not including 
damages due to the fault of negligence of the United States 
or its contractors; provide and maintain without cost to the United 
States adequate berthing areas at the docks adjacent to the improvement; 
accomplish at no cost to the United States all relocations 
and alterations of utilities necessary for the project; assume 
full responsibility for all project first costs in excess of the Federal 
cost limitation of $2,000,000; and comply with the Uniform 
Relocation Assistance and Real Property Acquisition Policies Act 
of 1970. 
Terminal facilities. Three car-ferry slips, a grain elevator, one 
shipbuilding yard, and three other wharves used for handling coal, 
building materials, cement, and miscellaneous commodities. 
While these facilities are considered adequate for existing commerce, 
it is believed the City should provide a suitable wharf 
with warehouse and railway connection open to the general public. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$64,723. Repairs to N. and S. Breakwaters and N. Stub Pier were 
performed by hired labor at a cost of $13,925. Minor repairs to 
the disposal area cost $244. Engineering and design for repair 
of S. Breakwater to be performed by contract next FY was initiated 
at a cost of $3,782. Engineering and design for repairs 
to the confined disposal facility awarded last FY was completed 
at a cost of $183,780. Engineering, design, surveys, supervision 
and administration cost $33,362. 
Existing project is completed except for the 1962 and 1968 
modifications. The 1962 modification is inactive. Work on the 
1968 modification was essentially completed in FY 83. The 
Federal modification, adopted July 15, 1985, included the expansion 
of the new entrance channel to the Section 107 project 
and extension of the rubblemound breakwater. The breakwater, 
completed in 1910, is in generally fair condition. Dredging a 
channel through the outer basin to existing project depth and 
removal of a portion of old north stub pier at the river entrance 
were completed in December 1937. Dredging river channel was 
completed in July 1942. Cost of existing project to end of FY 
was $3,959,991 for new work (includes $1,911,076 contributed 
funds) and $7,983,044 for maintenance; a total of $11,943,035. 
37. MARQUETTE HARBOR, MI 
Location. In Marquette Bay on south shore of Lake Superior, 
160 miles west of Sault Ste. Marie, MI, and 265 miles east from 
Duluth, MN. (See NOAA Nautical Chart 14970.) 
Existing project. Provides for a breakwater, and a harbor basin 
26.5 feet deep, giving a protected area of 350 acres. Project was 
modified in 1960 to provide a 27-foot depth in harbor area. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. None required for earlier authorizations. 
Fully complied with for the 1960 Act. 
31-14

DETROIT, MI DISTRICT 
Terminal facilities. One ore dock, unused at present; two coal 
docks; one petroleum dock; and three other unused docks. There 
are also several small fish wharves without railroad connections. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, inspections and reports were performed by Government 
forces at a cost of $11,299. Repairs to navigation structures were 
performed by hired labor using the Derrickbarge COLEMAN 
at a cost of $193,025. 
Total costs of existing project to end of FY were $3,554,979, 
of which $1,282,893 was for new work, $1,806,329 for 
maintenance and $465,757 for rehabilitation. 
38. MENOMINEE HARBOR AND 
RIVER, MI AND WI 
Location. On west shore of Green Bay, about 49 miles northeast 
of Green Bay Harbor, and about 155 miles from Milwaukee 
via Sturgeon Bay Canal. (See NOAA Nautical Chart 14917.) 
Previous projects. See page 1361 of Annual Report for 1962. 
Existing project. See Chicago District Annual Report 1979, 
Table 30-C, page 30-26. 
For detailed description see page 1214, Annual Report for 
1963. The portion authorized by 1960 River and Harbor Act is 
inactive and estimated (1964) at $442,000 Federal, and $105,000 
non-Federal. Costs of completed new work exclusive of inactive 
work and amount expended on previous projects are $221,053 
Federal and $50,762 non-Federal, which includes a cash contribution 
of $36,762. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with for completed work. 
Terminal facilities. There are 9 wharves for handling coal, 
limestone, pulp and miscellaneous commodities. City of 
Marinette, WI, provided a public wharf. Facilities are considered 
fairly adequate for existing commerce, except that there is need 
for a public wharf owned by City of Menominee, with warehouse 
and railway connection. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed 
by Government forces at a cost of $16,747. Repairs to N. 
Breakwater were performed by hired labor at a cost of $32,318. 
An adjustment of -$523 was made to a contract for repairs to 
South Pier, Section D. Supervision and administration and liquidated 
damages to financially close-out this contract cost 
-$1,282. Engineering and design for site selection of a disposal 
facility for dredged material cost $62,142. Close-out of site selection 
under the diked disposal program cost $2,288. 
The project in effect prior to the modification of March 2, 1945, 
was completed in 1938. No additional work was necessary under 
the modification of March 2, 1945, to provide a depth of 12 feet 
in the extension of the channel to the vicinity of the Marinette 
Yacht Club, as project depth or more was available. The entrance 
piers were completed in 1884, were rehabilitated (1954-1964) 
and are in excellent condition. Dredging of the channel below 
the Marinette municipal wharf, together with enlarging the turning 
basin to existing project depth, was commenced in May 1938. 
Modification of the project authorized by the 1960 River and Harbor 
Act is inactive. Construction for the 1967 modifications was 
started August 17, 1968, and completed in October 1968. The 
costs of the existing project were $570,238 for new work (includes 
$36,762 contributed funds), $2,369,039 for maintenance 
and $1,351,852 for rehabilitation; a total of $4,291,129. 
39. MILWAUKEE HARBOR, WI 
Location. On west shore of Lake Michigan about 85 miles 
north of Chicago, IL, and about 83 miles west of Grand Haven, 
MI. (See NOAA Nautical Chart 14924.) 
Previous projects. See page 1385 of Annual Report for 1962. 
Existing project. See Chicago District Annual Report for 1979, 
Table 30-C, page 30-26. For detailed description see page 1232 
of Annual Report for 1963. 
Completed new work costs are $6,937,804 Federal and 
$478,000 non-Federal, exclusive of amount expended on previous 
projects. The uncompleted portion authorized by the 1935 River 
and Harbor Act was placed in the inactive category in June 1973. 
Estimated costs are $119,000 (July 1972) Federal and $1,170,000 
(July 1972) non-Federal for this portion. Uncompleted portion 
1945 River and Harbor Act was deauthorized in 1977. (See Table 
31-B for authorizing legislation.) 
Local cooperation. Complied with for Acts of March 2, 1945, 
October 23, 1962, and July 14, 1960, except inactive portion of 
1945 Act. Act of August 30, 1935, provided that original dredging 
of outer harbor area be done by City of Milwaukee and City 
of Milwaukee be reimbursed at actual cost but not to exceed 10 
cents per cubic yard, place measurement, for original dredging 
done subsequent to authorization of work by Congress. Agreement 
covering dredging was executed by Secretary of Way, 
February 23, 1934, after this work was originally authorized as 
part of public works program. City was reimbursed for 10 percent 
of dredging. 
Terminal facilities. Four car-ferry slips, and 57 other wharves, 
private and municipal, used for handling coal, grain, building 
materials, cement, petroleum products, and miscellaneous commodities. 
As facilities in inner harbor were inadequate for existing 
commerce, Milwaukee Harbor Commission has constructed 
nine docks in the outer harbor for handling general cargo. 
Operations during fiscal year. Rehabilitation: The contract 
for major rehabilitation of the North Pier and North Breakwater 
awarded last FY is approximately 84% complete at a cost of 
$2,859,644. Engineering and design during construction cost 
$60,793. Engineering and design for Phase II of the rehabilitation 
project cost $25,600. Supervision and administration was 
performed at a cost of $243,500. 
Maintenance: Condition surveys, environmental studies, support 
for the water control center, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$170,535. The General Design Memorandum for major 
rehabilitation of the Inner North Revetment and the detached 
North Breakwater cost $348. Hired labor maintenance of the 
diked disposal facility cost $1,958. Repair to S. Pier was performed 
by the cranebarge MANITOWOC at a cost of $138,988. 
Safety maintenance was performed by hired labor at a cost of 
$1,626. Engineering and design for breakwater and revetment 
repair cost $7,726. Engineering and design for a dredging and 
CDF repair contract was completed at a cost of $14,736. A contract 
for maintenance dredging and CDF repairs was awarded 
31-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
this FY in the amount of $1,994,470. No work was peformed 
this FY. Other engineering, design, surveys, supervision and administration 
cost $63,535. 
Existing project is complete except for inactive portions. The 
1962 modification was completed in July 1967. North breakwater 
and shore connection, 9,954 feet long, was completed in August 
1925. North pier was completed in 1905 and construction of south 
pier was completed in November 1910. Construction of south 
breakwater and shore connection was completed in October 1929. 
Before modification of August 30, 1935, City of Milwaukee also 
dredged most of the area in the outer harbor south of inner entrance 
piers and lakeward of pierhead line to more than 21 feet 
below datum without cost to the United States. City of Milwaukee 
also dredged a portion of the area of the outer harbor north of 
inner entrance piers to provide an approach channel to the 
passenger and auto pier opposite East Claybourn Street. Work 
on the 1945 modification was completed in August 1957, except 
for inactive portion which consists of dredging the Milwaukee 
River from Buffalo Street to upper limit of the project at Humbolt 
Avenue. In recent years, some repairs were completed on 
the north shore breakwater; however, additional repairs are required. 
South breakwater and shore connections are in generally 
good condition. Costs of existing project were $8,231,024 for 
new work, $30,933,450 for maintenance, and $7,022,099 for 
rehabilitation; a total of $46,186,573. 
40. MONROE HARBOR, MI 
Location. On lower reach of River Raisin, which empties into 
Lake Erie and is 36 miles south of Detroit, MI. (See NOAA 
Nautical Chart 14830.) 
Existing project. Provides for a channel in Lake Erie and River 
Raisin to City of Monroe, for a turning basin, and for riprapping 
protecting dikes at river mouth. Project depths are 21 feet 
to turning basin, 18 feet in turning basin, and 9 feet to upstream 
end of project. For additional details see page 1490 of Annual 
Report for 1962. Project feature for riprapping protecting dikes 
is considered inactive. Estimated costs of this feature (1954) is 
$90,000. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several privately owned docks and a 
municipal terminal. Port of Monroe Authority built a steel and 
concrete wharf on southeast side of turning basin for commercial 
use. Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$48,010. Maintenance of the disposal facility was performed by 
hired labor at a cost of $54,246. An adjustment of -$27,101 was 
made on prior year cost for maintenance dredging performed by 
the Hopper Dredge HAINS. The maintenance dredging contract 
awarded last FY was completed at a cost of $1,205,425 removing 
approximately 38,416 cubic yards of material this FY. A contract 
for maintenance dredging was awarded. It is approximately 
99% complete with 47,067 cubic yards removed this FY at 
a cost of $314,999. A contract for maintenance dredging was 
awarded in the amount of $995,723. No work was performed 
this FY. Engineering and design for repair of dike disposal cost 
$6,489. Engineering, design, surveys, supervision and administration 
cost $98,871. An adjustment of-$59,472 was made 
on the contract for construction of a confined disposal facility 
completed last FY. Engineering during construction, supervision 
and administration cost $35,979. 
Total costs to end of FY were $52,389,360, of which $987,340 
was for new work (including $300,000 contributed by the Port 
Commission of Monroe), and $51,402,020 for maintenance including 
$166,667 contributed funds. ($125,000 by Consolidated 
Paper Company and $41,667 by River Raisin Company.) 
41. MUSKEGON HARBOR, MI 
Location. On east shore of Lake Michigan, 114 miles northeasterly 
from Chicago, IL, and 80 miles easterly from Milwaukee, 
WI (See NOAA Nautical Chart 14934.) 
Previous project. For details see page 1950 of Annual Report 
for 1915; page 1399, Annual Report for 1924; and page 1484, 
Annual Report for 1938. 
Existing project. A breakwater protected outer basin in Lake 
Michigan and an entrance channel from Lake Michigan to 
Muskegon Lake protected by piers and revetments. Project depths 
vary from 29 feet in the lakeward portion of the outer basin to 
27 feet in the channel between the inner piers to Muskegon Lake. 
For additional details see page 1303 of Annual Report for 1963. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several privately owned wharves primarily 
for commercial use. Details on actual port and harbor facilities 
are in Port Series, No. 48 (revised 1981) prepared and published 
by the Water Resources Support Center. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Rehabilitation: The contract 
awarded in FY 84 for major rehabilitation of the North and South 
Revetment was completed at a cost of $1,307,023. Engineering 
and design during construction cost $41,100. Supervision and 
administration cost $120,481. 
Maintenance: Condition surveys, environmental studies, 
miscellaneous inspections and reports were performed by Government 
forces at a cost of $68,844. An adjustment of -$20,000 was 
made for hired labor structure repairs from previous fiscal years. 
Safety maintenance and repairs to navigation structures were performed 
at a cost of $7,610. Location of a possible hazard to 
navigation was performed by contract at a cost $18,131. 
Engineering, design, surveys, supervision and administration cost 
$15,341. Condition surveys and environmental monitoring were 
performed in conjunction with the authorized Section 111 project 
at a cost of $38,544. A contract for beach nourishment was 
awarded and completed this FY at a cost of $1,489,535. Engineering, 
design, supervision and administration cost $74,763. 
Existing project, including latest project modification, was completed 
in 1965. For additional details on completion of existing 
project see page 1465 of Annual Report for 1962. Total costs 
to end of FY were $24,081,848, of which $3,017,110 was for 
new work, $7,333,160 for maintenance, and $13,731,578 for 
rehabilitation. 
42. NEW BUFFALO HARBOR, MI 
Location. At mouth of Galien River on southeast shore of Lake 
Michigan in Berrien County, about 45 miles easterly from 
31-16

DETROIT, MI DISTRICT 
Chicago, IL. (See NOAA Nautical Chart 14905.) 
Existing project. Provides for an entrance channel 10 feet deep 
by 80 feet wide and 850 feet long, to mouth of Galien River; 
new north and south breakwaters 1,305 and 740 feet long, respectively, 
and deepening inner channel to Galien River to 8 feet wide 
and 1,250 feet long. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. One village owned boat ramp and three 
privately operated marinas, and a private boat club facility. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous inspections and 
reports were performed at a cost of $21,618. Minor repairs to 
navigation structures were performed by hired labor at a cost of 
$839. An adjustment of -$1,604 was made this FY to the 
maintenance dredging contract awarded and completed last FY. 
The contract for beach nourishment awarded last FY was completed 
at a cost of $622,186. Engineering, design, surveys, supervision 
and administration cost $21,079. 
Existing project is complete. Total costs at end of FY were 
$4,258,039, of which $1,285,716 was for new work and 
$2,972,323 for maintenance. Contributed funds were in the 
amount of $1,186,467. 
43. ONTONAGON HARBOR, MI 
Location. On south shore of Lake Superior. It consists of improvement 
of mouth of Ontonagon River. (See NOAA Nautical 
Chart 14965.) 
Previous project. For details see page 1931 of Annual Report 
for 1915, and page 1406 of Annual Report for 1938. 
Existing project. Provides for approach channel 16 feet deep, 
a channel between piers with 17 and 15-foot depths, an inner basin 
12 feet deep, and maintenance of channels, basin, and entrance 
piers. Completed project cost $19,619. See page 1100 of Annual 
Report for 1966 for details. A modification authorized by 
1962 River and Harbor Act provides for increasing depths of 
channels, construction of an inner basin and a sedimentation basin. 
This portion of project is inactive. (Estimated cost (1965) of this 
work is $6,040,000. (See Table 31 -B for authorizing legislation.) 
Local cooperation. None required for earlier authorization. 
See page 1020 of Annual Report for 1965 for requirements of 
1962 Act, 
Terminal facilities. There are no publicly owned wharves. 
There are three coal wharves, an oil receiving facility, and a few 
small fish wharves. Facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. New Work: A total of $77,669 
was spent in FY 86 on two studies: $64,377 for the Section 205 
Detailed Project Report, and $13,292 for the Section 103 study 
which was suspended because recreational benefits were excluded 
and the project then lacked economic justification. Maintenance: 
Condition surveys and environmental studies were performed by 
Government forces at a cost of $31,208. Repairs to the East Pier 
were performed by hired labor using the Derrickbarge COLEMAN 
at a cost of $196,485. Engineering and design for major 
repairs to navigation structures was performed at a cost of 
$30,696. A Reconnaissance Report on the proposed Major 
Rehabilitation was transmitted to NCD on March 19, 1986, with 
subsequent transmission to OCE on May 5, 1986. An adjustment 
of -$2,195 and -20,532 cubic yards of shoal material was made 
on a dredging contract completed last FY. A contract for 
maintenance dredging was awarded and completed this FY at a 
cost of $474,998 removing approximately 101,150 cubic yards 
of material. A contract for maintenance dredging Area 3 was 
awarded and completed this FY at a cost of $144,900, removing 
approximately 35,037 cubic yards of material. Engineering, 
design, surveys, supervision and administration cost $43,066. 
All work authorized under previous Acts was completed in 
1938. Work authorized under the 1962 Act is in an inactive status. 
Total costs of existing project to end of FY were $8,563,916, 
of which $874,468 was for new work and $7,689,448 for 
maintenance. 
44. PENSAUKEE HARBOR, WI 
Location. On west shore of Green Bay, about 22 miles northeasterly 
from Green Bay Harbor, and about 33 miles southwesterly 
from Menominee Harbor, MI and WI. (See NOAA Nautical 
Chart 14910.) 
Previous projects. For details, see Annual Report for 1899, 
page 2734, and Annual Report for 1938, page 1429. 
Existing project. An entrance channel 100 feet wide and 8 feet 
deep at low water datum from the depth in Green Bay about 4,300 
feet to mouth of Pensaukee River. Fluctuations of water level 
are seasonal changes of about one-half foot above or below the 
annual mean stage, and extreme fluctuations of a temporary 
nature, due to wind and barometric pressure, of about 2 feet above 
or below mean lake level prevailing at the time. New work for 
completed project cost $24,851, exclusive of amounts expended 
under previous projects. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. None required. 
Terminal facilities. Small private wharves along lower half 
mile of river, used by the local fishing interests. Ample space 
is available for additional fishing wharves when required. 
Facilities considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys and environmental studies were performed by Government 
forces at a cost of $12,847. Supervision and administration 
cost $346. 
The existing project was complete in 1938. Total costs at the 
end of FY were $240,542, of which $34,035 was for new work 
and $206,507 for maintenance. 
45. PENTWATER HARBOR, MI 
Location. On east shore of Lake Michigan, 146 miles northeasterly 
from Chicago, IL, and 14 miles southerly from 
Ludington, MI. (See NOAA Nautical Chart 14907.) 
Existing project. Provides for widening old entrance channel 
to 150 feet between parallel piers and revetments, channel to extend 
from Lake Michigan to Pentwater Lake, with a depth of 16 
feet. Piers and revetments are built of stonefilled timber cribs 
and piling and capped with concrete. The 200-foot extension to 
south pier portion of project is considered inactive. Estimated 
cost (1954) of this portion is $65,100. (See Table 31-B for 
authorizing legislation.) 
31-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Local cooperation. None required. 
Terminal facilities. Several small privately owned wharves 
on west end of Pentwater Lake. The City and Michigan Waterways 
Commission jointly constructed a dock on northwest side 
of Pentwater Lake for public use. Facilities are considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, inspections and reports were performed 
by Government forces at a cost of $14,815. Soil borings 
of navigation structures were performed at a cost of $9,231. A 
maintenance dredging contract was awarded and completed this 
FY removing approximately 23,098 cubic yards of shoal material 
at a cost of $78,391. Repairs to N & S Piers were performed 
by hired labor using the Cranebarge MANITOWOC at a cost 
of $70,726. Engineering, design, supervision and administration 
cost $21,304. 
Existing project was completed in 1959 except for a 200-foot 
extension to the south pier which is not considered necessary 
under present conditions. For additional details see page 1468 
of Annual Report for 1962. Total costs for existing project at 
end of FY were $3,199,228, of which $179,899 was for new 
work, and $3,019,329 for maintenance. 
46. PETOSKEY HARBOR, MI 
Location. This harbor is on the east shore of Lake Michigan 
about 50 miles south of the Straits of Mackinac. (See NOAA 
Nautical Chart 14913.) 
Previous project. For details see page 1954 of Annual Report 
for 1915, page 1547 of Annual Report for 1931, and page 2024 
of Annual Report for 1949. 
Existing project. Provides for a breakwater extending from 
shore 1,345 feet long of stone-filled timber crib, concrete capped, 
and rubblestone construction which protects the municipal 
pier. (See Table 31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. There is a municipal pier which is about 
635 feet long plus several recreational craft piers. These installations 
satisfy current commerce and traffic requirements. 
Operations durng fiscal year. New Work: Funds in the 
amount of $5,600 were expended to complete an unfavorable Initial 
Appraisal Report for a Section 107 project. Maintenance: 
Condition surveys, environmental studies, inspection and reports 
were performed by Government forces at a cost of $5,391. Minor 
repairs to navigation structures were performed by Hired Labor 
at a cost of $1,269. 
Existing project was completed in 1908. Total costs to end of 
FY were $667,650. 
47. POINTE LOOKOUT HARBOR 
(AU GRES RIVER), MI 
Location. At Au Gres River on westerly shore of Lake Huron 
at entrance to Saginaw Bay, about 17 miles northeast of mouth 
of Saginaw River. (See NOAA Nautical Chart 14863.) 
Existing project. Provides for construction of a small boat harbor 
having a 12-foot deep, 100-foot wide, 2,800-foot long outer 
entrance channel; a 5,600-foot long, 100-foot wide inner entrance 
channel having a 10-foot depth; an 8,270-foot long 6-foot deep 
river channel ending just downstream from U.S. 23 highway 
bridge and having a width of 60 feet; a 4,000-foot long north 
breakwater and a 3,800-foot long south breakwater. (See Table 
31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Small boat marina facilities are under construction 
by the State of Michigan. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$23,803. The contract awarded last FY for repair of East and 
West Breakwater is 92% complete at a cost this FY of 
$1,723,918. Engineering, design, value engineering, supervision 
and administration cost $134,575. Contributed Funds expended 
in the amount of $606 represents financial close-out for the dredging 
contract completed in FY 85. 
Existing project was completed in 1974. Total costs to end of 
FY were $5,706,961, of which $2,642,584 was for new work 
and $3,064,377 for maintenance. 
48. PORT AUSTIN HARBOR, MI 
Location. On west shore of Lake Huron at extreme 
southeastern limit of Saginaw Bay, and 29 miles south of Au Sable 
River (Oscoda). (See NOAA Nautical Chart 14863.) 
Existing project. A harbor of refuge at the mouth of Bird 
Creek, consisting of a harbor basin dredged to a depth of 10 feet 
protected by a breakwater structure, and for dredging an entrance 
channel to the harbor basin to a depth of 12 feet. (See Table 31-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A number of docks near mouth of Bird 
Creek and a State-owned dock inside breakwater. Facilities accommodate 
recreational craft and are considered adequate for existing 
traffic. 
Operations during fiscal year. New Work: A letter report 
for an additional breakwater was prepared this FY, at a cost of 
$50,753. Maintenance: Condition surveys, miscellaneous inspections 
and reports were performed by Government forces at a cost 
of $24,857. Contract awarded last FY for breakwater access was 
completed this FY at a cost of $466,864. Engineering, design, 
supervision and administration cost $52,647. 
Total costs of existing project to end of FY were $2,957,054, 
of which $1,179,087 was for new work (includes $172,100 contributed 
funds) and $1,777,967 for maintenance. 
49. PORTAGE LAKE HARBOR, MI 
Location. On east shore of Lake Michigan about 186 miles 
northeasterly from Chicago, IL, and about 37 miles northerly 
from Ludington, MI. (See NOAA Nautical Chart 14939.) 
Existing project. Provides for a harbor of refuge with an entrance 
channel from Lake Michigan to Portage Lake protected 
by piers and revetments. Project depth is 18 feet. For additional 
details see page 1297 of Annual Report for 1958. (See Table 31-B 
for authorizing legislation.) 
31-18

DETROIT, MI DISTRICT 
Local cooperation. None required. 
Terminal facilities. There are landing places and marinas at 
inner end of Portage Lake. Facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, inspections and reports were performed by Government 
forces at a cost of $20,285. Safety maintenance and repairs to 
North and South Piers and Revetments were performed by the 
U.S. Cranebarge MANITOWOC at a cost of $99,997. Supervision 
and administration cost $5,205. 
Existing project was substantially completed in 1912. For additional 
details on completion of existing project see page 1298 
of Annual Report for 1958. The structures are generally in fair 
condition. Total cost of existing project to end of FY is 
$1,806,536. 
50. PORT SANILAC HARBOR, MI 
Location. On southwest shore of Lake Huron, 30 miles north 
of Port Huron, MI. (See NOAA Nautical Chart 14862.) 
Existing project. Provides for a harbor of refuge protected 
by breakwater structures extending to 12-foot depth contour in 
lake; for dredging a harbor basin 10 feet deep; for dredging an 
entrance channel 12 feet deep; a 70-foot extension of the south 
breakwater; a 300-foot arm added to the north breakwater; and 
riprap placed at the lakeward side of the breakwater additions.' 
(See Table 31-B for authorizing legislation.) 
Local Cooperation. Fully complied with. 
Terminal facilities. There is one privately owned dock used 
principally as a fishing terminal by owner and a municipally 
owned pier for recreational craft. Facilities are considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, and environmental studies were performed by Government 
forces at a cost of $8,676. Inspection and reports under Section 
111 mitigation were performed at a cost of $6,444. A contract 
for beach nourishment awarded last FY was completed at 
a cost of $174,660. Supervision and inspection of this contract 
cost $4,748. 
The project was completed in 1951 except for latest modification 
which was completed in FY 76. The breakwaters are in good 
condition. Total costs of existing project to end of FY were 
$4,231,981 (includes $2,120,593 contributed funds). 
51. PORT WASHINGTON HARBOR, WI 
Location. On the west shore of Lake Michigan, about 53 miles 
south of Manitowoc and about 29 miles north of Milwaukee, WI. 
(See NOAA Nautical Chart 14904.) 
Previous project. For details, see page 1938 of Annual Report 
for 1915, page 1459 of Annual Report for 1938, and page 30-14 
of Chicago District Annual Report for 1975. 
Existing project. See Chicago District Annual Report for 1979, 
Table 30-C, page 30-27. 
Construction of a small boat harbor within the existing harbor 
was authorized by the Chief of Engineers, June 12, 1975, under 
authority of Section 107, 1960 River and Harbor Act, as amended. 
Local cooperation. Fully complied with. 
Terminal facilities. There is one coal wharf, a petroleum tank 
farm and several fishing wharves. City provided a wharf which 
is open to public use. Facilities considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, inspections and reports were performed by Government 
forces at a cost of $7,950. Minor repairs to navigation structures 
by hired labor were performed at a cost of $1,693. An adjustment 
of -$20,000 was made in prior year costs for structure 
repairs. Supervision and administration cost $709. 
The existing project was completed in 1936. The 1958 
modification was deauthorized in 1977. Total costs to end of FY 
were $6,426,652, of which $4,017,709 was for new work, and 
$2,408,943 for maintenance. 
52. PORT WING HARBOR, WI 
Location. On south shore of Lake Superior, 34 miles easterly 
from Duluth, MN. (See NOAA Nautical Chart 14966.) 
Existing project. Provides for two parallel piers at entrance, 
835 and 1,017 feet long, respectively, 200 feet apart; an entrance 
channel between piers 150 feet wide with 15-foot depth; an 
irregular-shaped turning basin 15 feet deep at inner end of piers 
from which two inner channels with 8-foot depth extend. One 
of these is 60 feet wide extending southerly for 340 feet and one 
70 feet wide extending easterly 1,170 feet. 
Portion of dredging of entrance channel to complete project 
width and depth is considered unnecessary to meet present navigation 
requirements. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are four privately owned fishing 
wharves which are considered adequate for existing conditions. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed 
by Government forces at a cost of $10,060. An adjustment of 
-$48,944 was made on a contract awarded and completed last 
FY. Engineering, design, supervision and administration cost 
$263. 
Existing project is complete except channel between piers and 
has been dredged to only a 100-foot width. Widening the channel 
an additional 50 feet was considered unnecessary to meet present 
navigation requirements. That work was classified inactive 
and deauthorized on August 5, 1977 under Section 12 of Public 
Law 93-251. Piers are in good condition. 
At end of FY controlling depth was 12 feet in lake approach, 
10 feet between piers in northerly portion of turning basin, and 
8 feet in easterly inner channel. Lands owned by the United States 
total 7.80 acres. Total costs to end of FY are $855,663. 
53. RACINE HARBOR, WI 
Location. On west shore of Lake Michigan about 26 miles 
south of Milwaukee, WI, and about 64 miles north of Chicago, 
IL, (See NOAA Nautical Chart 14925.) 
Previous project. See page 1389 of Annual Report for 1962. 
Existing project. See Chicago District Annual Report for 1979, 
Table 30-C, page 30-27. 
31-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
For detailed description see page 1235, Annual Report for 
1963. New work for project as completed cost $777,775, exclusive 
of amounts expended on previous projects and exclusive 
of inner 300 linear feet of pile pier and 450 linear feet of rubblemound 
originally part of south breakwater but no longer considered 
necessary. (See Table 31-B for authorizing legislation.) 
Authorization for the unconstructed Section 107 small boat harbor 
within the existing harbor was withdrawn by the Office of 
the Chief of Engineers on Aug. 25, 1986, at the request of the 
local sponsor. In addition, the entire Federal commercial navigation 
project was deauthorized by Public Law 99-315, dated May 
21, 1986, which authorized transfer of title, without consideration 
to any project facilities constructed by the United States, to 
Racine County, WI. 
Local cooperation. Fully complied with. 
Terminal facilities. Five wharves used for handling coal, 
limestone, petroleum products, and fish. City provided a public 
wharf. 
Operations during fiscal year. Maintenance: Condition 
surveys were performed by Government forces at a cost of 
$7,302. Supervision and administration cost $2,018. Engineering, 
design, supervision and administration for Section 111 were 
performed at a cost of $8,338. 
Existing project was substantially completed in 1946. Construction 
of north breakwater and shore connection was completed 
in November 1918. Removal of old north pier was completed 
in 1913. Construction of south breakwater and shore connection 
and removal of old south pier were commenced in June 1916 and 
completed in December 1924. Removal of outer shoals, widening 
and deepening channels through outer basin to existing project 
depth and width, and dredging of river channel began in July 
and was completed in November 1946. Total costs of existing 
project to end of FY were $9,583,688, of which $1,332,315 was 
for new work and $6,997,728 for maintenance, and $1,253,645 
for rehabilitation. 
54. ROUGE RIVER, MI 
Location. Rises in Oakland and Washtenaw Counties, MI, 30 
miles long, flows southeasterly through Wayne County, and joins 
Detroit River at westerly limit of City of Detroit. (See NOAA 
Nautical Chart 14854.) 
Previous project. For details see page 1530 of Annual Report 
for 1932, and page 1558 of Annual Report for 1938. 
Existing project. Provides for: (a) Main channel from Detroit 
River through Short Cut Canal extending to upstream limit of 
the project, a distance of 3.5 miles. Project depths are 25 and 
21 feet in navigation chanel, 21 feet in turning basin, and 13 feet 
in upper reach of project. (b) Old Channel from Detroit River 
extending to junction of Old Channel with Short Cut Canal. Project 
depths are 25, 18, 17, and 21 feet. For additional details see 
page 1324 of Annual Report for 1963. In 1973, work authorized 
by the 1962 River and Harbor Act was reclassified from the active 
to inactive category. Estimated cost (1972) of this work is 
$880,000. Except for dredging 25-foot channel 1,150 feet 
upstream from mouth of Old Channel, work authorized in Act 
of August 30, 1935, is considered inactive. Estimated cost (1958) 
of inactive portion is $255,000. Work authorized by Act of July 
3, 1958 is considered inactive. Estimated cost (1960) of this work 
is $210,000. (See Table 31-B for authorizing legislation.) 
Local cooperation. Act of October 23, 1962, requires local 
interests to provide lands and rights-of-way for construction upon 
request of the Chief of Engineers; hold the United States free 
from damages; provide terminal facilities to accommodate prospective 
commerce considered in report of District Engineer; 
dredge and maintain areas between the Federal improvement and 
terminal facilities to depths commensurate with improved Federal 
channel; make alterations in docks, bulkheads and other structures, 
and take such other measures as may be necessary to assure 
stability of banks adjacent to channel; and provide bridge protection. 
The assurances of local cooperation for the River and 
Harbor Act of 1962 were furnished by the Michigan State Waterways 
Commission and accepted on January 7, 1965. Fulfillment 
of all items of local cooperation has not been accomplished. 
Terminal facilities. Numerous large commercial docks for 
handling various type cargo. Details on actual port and harbor 
facilities are contained in the Port Series No. 45 (revised 1984) 
prepared and published by the Water Resources Support Center. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, inspections and reports were performed 
by Government forces at a cost of $98,835. An adjustment 
was made for the maintenance dredging contract completed 
last FY in the amount of -$158,863 and -270 cubic yards. A contract 
was awarded and completed for maintenance dredging and 
approximately 59,357 cubic yards of shoal material removed at 
a cost of $523,642. Maintenance of disposal area by hired labor 
cost $4,472. Engineering and design for repair of Grassy Island 
was completed at a cost of $33,158. Engineering, design, surveys, 
supervision and administration was performed at a cost of 
$48,512. A contract for repair to Confined Disposal Facility at 
Grassy Island was awarded late in the FY in the amount of 
$1,592,100. No work was performed this FY. A contract was 
awarded for construction of a Wetland Marsh under Section 150 
of the Water Resources Development Act of 1967. The Rouge 
River portion of this contract is complete at a cost of $100,000. 
Supervision and administration for this contract cost $44,833. Supervision 
and administration for dike disposal program cost $329. 
Work authorized before 1962 modification is complete or 
deauthorized. For additional details on completion of existing project 
see Annual Report for 1962. Total costs for existing project 
to end of FY were $30,908,173, of which $675,251 was for new 
work and $30,232,922 for maintenance. In addition, $29,563 was 
expended for new work from Emergency Relief Act Funds. 
55. SAGINAW RIVER, MI 
Location. Formed by union of Tittabawassee and Shiawassee 
Rivers, 22 miles long, and flows northerly into extreme inner 
end of Saginaw Bay, Lake Huron. Cities of Saginaw and Bay 
City are on the river. (See NOAA Nautical Chart 14867.) 
Previous project. For details, see page 1957 of Annual Report 
for 1915, and page 1550 of Annual Report for 1938. 
Existing project. Provides for an entrance channel 27 feet deep 
and 350 feet wide from 27-foot contour in Saginaw Bay to river 
mouth; thence a channel 26 feet deep and 200 feet wide to New 
York Central Railroad Bridge at Bay City; thence 22 feet deep 
and 200 feet wide to C&O Railroad Bridge in Saginaw; thence 
31-20

DETROIT, MI DISTRICT 
16.5 feet deep and 200 feet wide to upstream limit at Green Point. 
Project also provides for five turning basins; one 25 feet deep 
at Essexville, 600 feet wide with a maximum length of 1,850 feet; 
one 22 feet deep on east side of channel about 1 mile upstream 
from Cass Avenue in Bay City, 650 feet wide and 1,000 feet long; 
one 20 feet deep at Carrollton, 100 to 300 feet wide and 900 feet 
long; one 20 feet deep just downstream from C&O Bridge in 
Saginaw, 650 feet wide and 1,000 feet long; and one 15 feet deep 
between Bristol Street Bridge and New York Central Railroad 
Bridge in Saginaw. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Numerous large commercial docks for 
handling a great variety of cargo. Details on actual port and harbor 
facilities are in Port Series No. 45 (revised 1984) prepared 
and published by the Water Resources Support Center. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, Hi-Fix surveys, environmental studies, inspection and 
reports were performed by Government forces at a cost of 
$308,316. An adjustment of $942 was made to the contract for 
dredging completed last FY. A contract for maintenance dredging 
the Bay Section was awarded in the amount of $847,000. Approximately 
37% is complete at a cost of $313,389, removing 
approximately 99,000 cubic yards of material. Maintenance of 
Disposal Area was performed by hired labor at a cost of $8,939. 
Engineering, design, surveys, supervision and administration cost 
$48,784. Engineering and design for construction of a diked 
disposal area for upper Saginaw was continued at a cost of 
$207,953. 
Existing project is complete except for small part of the work 
authorized by the Act of October 23, 1962. Section D (Sixth Street 
Turning Basin) of the 1962 Act is complete except for the channel 
portion, which is pending modification. Total costs for existing 
project to end of FY were $66,829,119, of which 
$14,930,727 was for new work and $51,898,392 for maintenance. 
56. ST. CLAIR RIVER, MI 
Location. A 40 mile long section of Great Lakes connecting 
channels which flows southerly from Lake Huron and discharges 
into Lake St. Clair. (See NOAA Nautical Chart 14852.) 
Existing project. Provides for channels through St. Clair 
River, which, at low water datum, are suitable for vessels drawing 
25.5 feet. Project also provides for improvement of North 
Channel outlet, 100 feet wide and 10 feet deep, for recreational 
craft. Project depths are referred to low water datums for Lakes 
Huron and St. Clair, 576.8 and 571.7 feet above mean water level 
at Father Point, Quebec; International Great Lakes Datum 1955. 
(See Tables 31-B and 31-C for authorizing legislation and features 
of existing project.) Act of July 24, 1946 provides for widening 
and deepening of southeast bend and improvement of outlet of 
north channel. Estimated cost (1985) is $860,000. 
Local cooperation. None required. 
Terminal facilities. This improvement serves through commerce, 
between upper and lower Great Lakes, and has not 
materially influenced terminal facilities along its route. A number 
of privately owned piers and wharves are at Port Huron, 
Marysville, St. Clair, and Marine City, MI, which handle coal, 
limestone, petroleum products, woodpulp, salt and general cargo. 
These installations satisfy present commerce requirements. 
Operations during fiscal year. Maintenance: Condition 
surveys, Hi-Fix surveys, miscellaneous inspections and reports 
were performed by Government forces at a cost of $168,101. 
Environmental studies in connection with the extended navigation 
season cost $150,562. Location and removal of obstructions 
cost $524,096. Real estate activities cost $20,999. Minor 
maintenance of disposal area was performed by hired labor at 
a cost of $1,320. An adjustment of -$3,927 was made to prior 
year cost for maintenance dredging peformed by the U.S. Hopper 
Dredge MARKHAM. Engineering, design, surveys, supervision 
and administration cost $2,807. 
Existing project is complete. Total cost of existing project to 
end of FY was $34,019,134, of which $19,213,246 was for new 
work and $14,805,888 for maintenance. 
57. ST. JOSEPH HARBOR, MI 
Location. On east shore of Lake Michigan, 60 miles easterly 
from Chicago, IL, and 24 miles southerly from South Haven, 
MI (See NOAA Nautical Chart 14930.) 
Previous project. For details see page 1945 of Annual Report 
for 1915, and page 1470 of Annual Report for 1938. 
Existing project. Provides for protecting mouth of St. Joseph 
River by two piers, 250 to 325 feet apart at their inner and outer 
ends, respectively, having lengths of 2,758 feet on north side and 
2,603 feet on south side; for a channel 21 feet deep from Lake 
Michigan to mouth of Benton Harbor Canal, a length of about 
6,900 feet with widths of 265 feet at outer end of piers, 190 feet 
at inner end of piers and revetments, thence generally 215 feet 
to lower end of turning basin, increasing to 250 feet above the 
turning basin to mouth of Paw Paw River, thence generally 110 
feet in Paw Paw River to mouth of Benton Harbor canal; for 
dredging channel in Benton Harbor canal up to west line of Riverview 
Drive extended northerly, to 18 feet deep and 80 feet wide; 
and a turning basin 18 feet deep on north side of channel above 
mouth of Morrison Channel and a turning basin 18 feet deep near 
mouth of Paw Paw River. Public Law 88-88th Congress declared 
a portion of Benton Harbor Canal a non-navigable stream. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several commercial wharves for handling 
coal, building materials, petroleum products, and 
miscellaneous commodities. A package freight terminal and a 
public docking facility is also available. Facilities considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, safety and environmental studies, miscellaneous inspections 
and reports were performed by Government forces at a cost 
of $66,594. Repairs to North Revetment and N. and S. Piers were 
performed using the cranebarge MANITOWOC at a cost of 
$116,600. Hired labor cost for maintenance of disposal area was 
$3,137. An adjustment of -$4,495 was made to the contract for 
dredging completed last FY. A contract awarded last FY for 
dredging inner harbor areas was completed at a cost of $2,798. 
A contract was awarded and completed for dredging the outer 
harbor removing 17,000 cubic yards of material at a cost of 
$118,149. A second contract was awarded for dredging the inner 
31-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
harbor and maintenance and repair of the disposal facility, removing 
approximately 20,814 cubic yards of material at a cost of 
$83,259. Cost for repair and maintenance was $111,745. 
Engineering, design, surveys, supervision and administration cost 
$93,434. Engineering and design for a disposal facility for 
polluted dredged material was continued at a cost of $14,594. 
Under the Section 111 program, one contract for mitigation of 
shore damage was awarded and completed at a cost of $529,801. 
Another contract for beach nourishment was awarded in the 
amount of $298,450. No work was performed this FY. Monitoring, 
surveys, engineering, supervision and administration cost 
$103,194. 
Existing project was completed in 1956. The structures are in 
generally good condition. For additional details on completion 
of existing project see page 1454 of Annual Report for 1962. Total 
costs of existing project to end of FY were $14,234,079, of which 
$1,301,372 was for new work, $11,970,491 for maintenance and 
$962,216 for rehabilitation. 
58. ST. MARYS RIVER, MI 
Location. A Great Lakes connecting channel about 63 miles 
long, flows southeasterly between State of Michigan and Province 
of Ontario, Canada, from eastern end of Lake Superior into 
northern end of Lake Huron. (See NOAA Nautical Charts 
14882, 14883, and 14884.) At Sault Ste. Marie, MI, about 14 
miles downstream from Lake Superior, there are four parallel 
locks and a hydroelectric powerplant. 
Previous project. For details see page 1955, Annual Report 
for 1915; and page 1529, Annual Report for 1938. 
Existing project. Channels permitting 25.5-foot draft navigation 
in St. Marys River and Lake Superior and Lake Huron approaches 
thereto; constructing and operating four locks and two 
canals; constructing an electric plant of 14,000 kilowatt capacity 
(45,000 kilowatt ultimate capacity) constructing anchorage areas 
in river above and below locks; and constructing various other 
works in conjunction with project. Subsequently, in 1932, the 
Unit 10 powerhouse was installed raising the capacity to 18,400 
kilowatts (45,000 ultimate capacity). Original State locks were 
operated and maintained under permanent indefinite appropriation 
from June 9, 1881, to November 2, 1886, after which they 
were destroyed by excavation for the Poe Lock in 1896. Weitzel 
Lock, destroyed in 1942 by excavation for MacArthur Lock, was 
operated and maintained under the same appropriation from 
September 1, 1881, to June 30, 1935. Poe Lock was operated 
and maintained under the same appropriation from August 3, 
1896, Davis Lock from October 21, 1914, and Sabin Lock from 
September 18, 1919, to end of FY 1935. The 1,200 foot by 110 
foot new Poe Lock was authorized in 1962 and put into operation 
in 1968. Details of existing project are set forth in Table 
31-D. 
Project depths are referred to low water datum corresponding 
to sloping surface of river as follows: Above locks: When water 
surface of Lake Superior is at elevation 600 feet and at upstream 
side of locks is 577.8 feet above mean water level at Father Point, 
Quebec (International Great Lakes Datum 1955). Estimated 
(1973) cost for new work is $164,630. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. This improvement serves through commerce 
between Lake Superior and lower lakes and has not 
materially influenced terminal facilities at localities along its route. 
Three piers at Sault Ste. Marie receive coal and petroleum products. 
Limestone is shipped from a pier at Drummond Island. 
Vessel refueling stations are at Lime Island and Village of Detour; 
they receive coal and petroleum products. Present terminals 
satisfy current traffic requirements. 
Operations during fiscal year. Operation, maintenance and 
care of locks: Two canals and three locks were operated (the 
fourth lock, Sabin, is out of service) as required. Necessary 
repairs and improvements were made thereto and to appurtenant 
structures and equipment. Canals were open to navigation 278 
days from October 1, 1985 through September 30, 1986. During 
that period, a total of 8,051 vessels, aggregating 68,917,500 
short tons of freight and 174,823 passengers passed through the 
MacArthur, Poe, and Davis Locks. Cost for operation, 
maintenance, and care of the locks for this FY was $5,586,448 
which included $92,180 for extended season operation and 
maintenance and $842,635 for the modernization of the Gatelifter 
PAUL BUNYAN. 
Powerhouse and equipment: Two hydroelectric powerhouses 
were operated and maintained at a cost of $627,589 during the 
FY less a deduction of $32,128 for interdepartmental electricity 
sold. 
Other operation and care items: Buildings and grounds were 
maintained, condition surveyings, operation studies, 
miscellaneous inspections and reports were performed at a cost 
of $692,503 which included a custodial, snow removal, and 
grounds upkeep contract for $203,174. Environmental studies 
were made at a cost of $40,861. Security measures were performed 
at a cost of $491,865 which included a service contract 
for $467,658. Janitorial service of the facilities was done by contract 
at a cost of $41,187. A study on winter and extended navigation 
season, ice measurements, and weather monitoring was performed 
at a cost of $807,309. The Soo Harbor ice boom was 
installed and removed at a cost of $55,005. Work was done on 
the Compensating Gates at a cost of $5,407. 
Channels and canals: St. Marys River channels and canal approach 
depths were surveyed by sweeping. Removal of shoals 
in St. Marys River channels and canal approaches was accomplished 
by hired labor with U.S. Derrickboats NICOLET and 
HARVEY at a cost of $1,218,614 including engineering and 
design. A total of $72,515 has been expended this year in the 
procurement of an electronic survey sweeping system. 
Recreational facilities: Information center, comfort stations, 
park fountain, observation and overlook platforms were maintained 
at a cost of $154,053 which included a janitorial contract 
for the Information Center at a cost of $20,917, and the purchase 
of Guide uniforms at the Information Center at a cost of $707. 
Visitors entering the Soo Locks Information Center numbered 
663,000. Visitors to the observation platforms overlooking the 
31-22

DETROIT, MI DISTRICT 
locks numbered 528,820. Total visitors to the Soo Locks park 
numbered 719,200. A grand total of 894,023 people visited the 
Soo Locks. Total project costs in FY 86 amounted to $9,761,728. 
Project in effect prior to modification of March 21, 1956, is 
complete and work authorized by 1956 modification to provide 
a safe draft of 25.5 feet for both upbound and downbound traffic 
is also complete. Public Works Acceleration Funds used for 
maintenance were $118,000. Total costs to end of FY were 
$160,657,070 for new work and $176,024,657 for maintenance, 
for a grand total of $336,681,727. 
59. SAUGATUCK HARBOR AND 
KALAMAZOO RIVER, MI 
Location. Harbor is on east shore of Lake Michigan, 90 miles 
northeasterly from Chicago, IL, and 22 miles northerly from 
South Haven, MI. (See NOAA Nautical Chart 14906.) 
Previous project. For details see page 1947 of Annual Report 
for 1915, and page 1475 of Annual Report for 1938. 
Existing project. Entrance channel protected by parallel piers 
at mouth of Kalamazoo River and a river channel to Village of 
Saugatuck, MI. Project depths: 16 feet in entrance channel, 14 
feet in river channel. Additional details on page 1456, 1962 Annual 
Report. (See Table 31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. At Village of Saugatuck, MI, there are 
several landing places for recreational craft and one for small 
commercial vessels. At Village of Douglas, MI, there is a landing 
pier. Facilities are considered adequate for present traffic. 
Operations during fiscal year. Maintenance: Condition 
surveys, safety studies, inspections and reports were performed 
by Government forces at a cost of $15,170. Repairs to the North 
Pier were performed by hired labor using the Cranebarge 
MANITOWOC at a cost of $54,045. Minor safety maintenance 
performed by hired labor cost $1,283. Engineering and design 
for repair to the North and South piers and revetments was continued 
at a cost of $22,495. Supervision and administration cost 
$2,153. 
Existing project was completed in 1903. Total costs to end of 
FY were $3,366,657, of which $364,527 was for new work and 
$3,002,130 for maintenance. 
60. SAXON HARBOR, WI 
Location. On south shore of Lake Superior in Wisconsin at 
mouth of Oronto Creek, 27 miles southeast of harbor at Bayfield, 
WI, and 21 miles westerly of harbor at Black River, MI; 99 miles 
east of Duluth-Superior Harbor and 60 miles west of Ontonagon 
Harbor, MI. (See NOAA Nautical Chart 14965.) 
Previous project. For details see page 1254 of Annual Report 
for 1962. 
Existing project. Provides for east and west breakwaters, an 
outer channel 10 feet deep, an inner basin and side channel 8 
feet deep, and diversion of Oronto Creek to Parkers Creek by 
three short reaches of channel excavation and a levee. For detailed 
dimensions of features see page 1025 of Annual Report for 1965. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. One wharf 300 feet long on east side of 
present harbor basin constructed by local interests. 
Operations during fiscal year. Maintenance: Condition 
surveys, inspections and reports were performed by Government 
forces at a cost of $15,511. Minor repairs to navigation structures 
were performed by hired labor at a cost of $9,587. 
The project was fully completed in March 1968. A reconnaissance 
report was completed in August 1971 concerning erosion 
of the shoreline west of the harbor. A detailed project report 
is being prepared to develop an acceptable plan for mitigation 
measures. Total cost of existing project to end of FY is 
$1,559,657. (Includes $50,193 Contributed Funds.) 
61. SHEBOYGAN HARBOR, WI 
Location. On west shore of Lake Michigan about 26 miles 
south of Manitowoc and about 55 miles north of Milwaukee, WI. 
(See NOAA Nautical Chart 14922.) 
Previous project. See page 1381 of Annual Report for 1962. 
Existing project. See Chicago District Annual Report for 1979, 
Table 30-C, page 30-27. 
For detailed description see page 1230, Annual Report for 
1963. New Work for project as completed cost $648,271, exclusive 
of amounts expended on previous projects. (See Table 
31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Three wharves for handling coal, 
petroleum products and miscellaneous commodities. City provided 
a public wharf. Facilities considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, inspections and reports were performed 
by Government forces at a cost of $49,528. Real estate 
activities cost $19,998. Repairs to S. Pier were performed by 
the Cranebarge MANITOWOC at a cost of $114,650. The contract 
for maintenance dredging awarded last FY was completed 
at a cost of $94,060 removing 12,026 cubic yards of material. 
Engineering, design, surveys, supervision and administration cost 
$50,022. Engineering and design for revetment repair cost 
$1,343. Engineering and design for maintenance dredging clean 
material cost $5,797. Engineering and design for dike disposal 
site selection was performed at a cost of $28,104. Engineering 
and design for construction of a confined disposal facility was 
performed at a cost of $9,231. 
Existing project was completed in 1904. Construction of north 
breakwater was commenced in October 1913 and completed in 
October 1915. Dredging entrance channel to existing project depth 
was commenced in June and completed in July 1938. Work on 
1954 modification was completed in December 1956. Piers and 
breakwaters are in generally good condition. Inner 260 feet of 
south pier was replaced with a revetment by private interests under 
permit granted July 16, 1931, by the Secretary of War. Piers, 
therefore, are maintained only for a length of about 2,490 feet. 
Sheboygan River is navigable about 2.4 miles above its mouth 
for craft drawing not more than 2 feet. Costs of existing project 
are $5,717,966 for maintenance, $609,028 for rehabilitation, and 
$1,136,088 for new work; a total of $7,463,082. 
31-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
62. SOUTH HAVEN HARBOR, MI 
Location. On east shore of Lake Michigan, 77 miles northeasterly 
from Chicago, IL, and 24 miles northerly from St. 
Joseph, MI. (See NOAA Nautical Chart 14906.) 
Previous project. For details see page 1947 of Annual Report 
for 1915, and page 1473 of Annual Report for 1938. 
Existing project. An entrance channel protected by parallel 
piers and revetments at mouth of Black River, a river channel 
and a turning basin. Project depths are 21 feet in entrance channel 
and 19 feet in river channel and turning basin. For additional 
details see page 1455 of Annual Report for 1962. (See Table 31-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several wharves for handling coal, 
building materials, woodpulp, fish, and miscellaneous commodities 
will have warehouses. Facilities satisfy current commerce 
requirements. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed 
by Government forces at a cost of $17,230. Minor structure 
repairs were performed at a cost of $7,990. Engineering and 
design for repair of the North and South Piers were performed 
at a cost of $59,172. Supervision and administration cost $188. 
Condition surveys, environmental studies and monitoring in conjunction 
with Section 111 were performed at a cost of $43,838. 
The contract awarded last FY was completed at a cost of 
$600,210. Supervision and administration cost $25,268. 
Existing project was completed in 1960. Project now being 
maintained to 14-foot and 12-foot depths, respectively, in lieu 
of the 21 feet and 19 feet authorized, which is adequate for current 
usage. For additional details on completion of existing project 
see page 1456 of Annual Report for 1962. Total costs for 
existing project to the end of FY were $7,258,842, of which 
$797,193 was for new work, $4,642,340 for maintenance and 
$1,632,076 for rehabilitation. 
63. STURGEON BAY AND LAKE 
MICHIGAN SHIP CANAL, WI 
Location. On west shore of Lake Michigan about 52 miles 
northeast of Green Bay and about 128 miles north of Milwaukee, 
WI. (See NOAA Nautical Chart 14919.) 
Previous projects. See page 1373 of Annual Report for 1962. 
Existing project. See Chicago District Annual Report for 1979, 
Table 31-C, page 30-27. For detailed description, see page 1223, 
Annual Report for 1963. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. As the canal and connecting channel is 
a through waterway, only terminal facilities are in City of 
Sturgeon Bay, 4 miles from west end of revetted portion of canal. 
These facilities consist of two wharves for handling coal, 
petroleum products and miscellaneous commodities and four shipbuilding 
yards. City of Sturgeon Bay provided a public wharf 
about 5 miles northwesterly from City of Sturgeon Bay. Two major 
shipyards are located in Sturgeon Bay where repair facilities 
are available including dry docks, marine railways and hoists. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$67,046. Breakwater repairs were performed by hired labor using 
the Cranebarge MANITOWOC at a cost of $119,856. An 
adjustment of -$20,000 was made to prior year costs for structure 
repairs. A contract for maintenance dredging awarded last 
FY was completed at a cost of $129,161 removing approximately 
18,036 cubic yards of material this FY. Engineering and design 
for site selection of a disposal facility for dredged material cost 
$29,805. Engineering, design, surveys, supervision and administration 
cost $21,063. Site selection of a disposal facility cost 
$11,953. 
Total cost of existing project is $1,059,722 for new work, 
$7,405,099 for maintenance and $884,899 for rehabilitation: a 
total of $9,349,720. In addition, $235,940 was expended between 
April 25, 1893, and June 30, 1917, on operating and care 
of works of improvements under provision of permanent indefinite 
appropriations for such purposes. 
64. TAWAS BAY HARBOR, MI 
Location. On northeasterly portion of Saginaw Bay, an arm 
of Lake Huron, adjacent to Tawas, Michigan. (See NOAA 
Nautical Chart 14863.) 
Existing project. Provides for a breakwater with four interconnected 
sections with an aggregate length of 1,750 feet with 
provisions for recreational fishing. A defined entrance channel 
and anchorage area are provided for, even though no dredging 
is required. Depths to 12 feet in the entrance and 10 feet in the 
anchorage area are presently available. (See Table 31-B for 
authorizing legislation.) Federal cost was $1,120,980, excluding 
$1,120,980 contributed by local interests for a total cost of 
$2,241,960. 
Local cooperation. Assurances of local cooperation were furnished 
by Michigan Department of Natural Resources to the 
Secretary of the Army on May 18, 1976, and have been fully 
complied with. 
Operations during fiscal year. New Work: Local interest 
work activities were completed in a previous FY and financial 
close-out of the project was accomplished this FY at a cost of 
$3,611. Surplus non-Federal contributed funds were returned to 
the sponsor this FY in the amount of $10,323. Maintenance: Conditon 
surveys were performed by Government forces at a cost 
of $1,735. Construction of breakwaters was initiated on April 
21, 1977, and was completed on November 6, 1977. 
65. TWO RIVERS HARBOR, WI 
Location. On west shore of Lake Michigan about 82 miles 
north of Milwaukee and about 101 miles from Green Bay, WI, 
via Sturgeon Bay Canal. (See NOAA Nautical Chart 14903.) 
Previous projects. See page 1377, Annual Report for 1962. 
Existing project. See Chicago District Annual Report for 1979, 
Table 30-C, page 30-28. 
31-24

DETROIT, MI DISTRICT 
For detailed description see page 1226 of Annual Report for 
1963. Completed project cost $147,463, exclusive of the amount 
expended on previous projects. The 1935 River and Harbor Act 
portion of project is considered inactive. Estimated cost of this 
portion (1954) is $14,000. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A coal wharf and several fishing wharves. 
City provided a wharf for receipt of petroleum products and public 
use. Facilities considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed 
by Government forces at a cost of $17,657. Engineering and 
design for Revetment repairs, supervision and administration cost 
$3,360. 
Existing project is complete except for inactive portion of project 
which consists of dredging a 10-foot width along east side 
of lakeward portion of entrance channel between the piers. This 
dredging was omitted to avoid removal of necessary riprap along 
entrance piers. Present width of channel is considered adequate 
for present and reasonably prospective commerce. South pier was 
completed in 1883 and is in generally good condition. North pier 
was completed in 1908. North revetment, completed in 1917, 
was rebuilt in May to August 1962. Dredging entrance channel 
and inner basin to existing project depth was commenced in March 
and substantially completed in May 1937. Total costs of existing 
project were $360,320 for new work, $6,561,381 for 
maintenance, and $58,057 for minor rehabilitation, for a total 
of $6,979,758. 
66. WHITE LAKE HARBOR, MI 
Location. On east shore of Lake Michigan 120 miles northeasterly 
from Chicago, IL, and 45 miles southerly from 
Ludington, MI. (See NOAA Nautical Chart 14935.) 
Existing project. Parallel piers, revetments, and a channel 16 
feet deep, 200 feet wide, 1,950 feet long, extending from Lake 
Michigan to White Lake. For additional details see page 1465 
of Annual Report for 1962. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. None required. 
Terminal facilities. A privately owned chemical shipping dock 
on north side of lake about 3 miles from inner end of revetted 
entrance channel. Across lake, at Village of Whitehall, there are 
several installations serving light draft vessels. These terminals 
satisfy present recreational and commercial traffic requirements. 
Operations during fiscal year. Maintenance: Condition 
surveys, environmental and safety studies, miscellaneous inspections 
and reports were performed by Government forces at a cost 
of $8,918. Repairs to the East and West Piers were performed 
by hired labor using the Cranebarge MANITOWOC at a cost 
of $70,387. Minor safety maintenance performed by hired labor 
cost $684. Engineering and design for major structure repairs 
to the North and South Piers was continued at a cost of $16,368. 
Supervision and administration cost $1,891. Under the Section 
111 program, the contract awarded last FY for mitigation of shore 
damage was completed at a cost of $32,300. A contract was 
awarded and completed this FY for Beach Nourishment at a cost 
of $361,000. Surveys, engineering, supervision and administration 
cost $35,811. 
Existing project was completed in 1908. Stone was placed on 
the north and south revetments in FY 1972. The structures are 
in generally good condition. Project now being maintained to 
14-foot depth authorized, which is adequate for current usage. 
Total cost to end of FY is $3,255,542, of which $457,563 was 
for new work and $2,797,979 for maintenance. 
67. RECONNAISSANCE AND 
CONDITION SURVEYS 
See Table 31-F. 
68. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 31-G. 
69. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107. Public Law 
86-645 (pre-authorization.) Expanded reconnaissance studies 
were continued for Douglas County, WI ($8,090) and completed 
for Two Harbors, MN ($1,054). Detailed project studies were 
terminated for Bayfield, WI ($12,591) because the project had 
a B/C ratio less than unity without recreational benefits, and for 
Kenosha, WI ($8,077) due to lack of local interest. An unfavorable 
Initial Appraisal Report was completed for Petoskey, 
MI ($5,600). Financial close-out was accomplished on Harrisville 
Harbor, MI ($12,281). 
Beach Erosion Control 
70. AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
Beach erosion control projects are authorized at Berrien County 
Shore (St. Joseph) MI, and the Shore of Manitowoc County, WI. 
For last full report see Annual Report for 1963 (Berrien County). 
Both projects are in the inactive category. 
71. EMERGENCY SHORE PROTECTION 
Authority for emergency streambank and shoreline protection 
of public works and non-profit public services. (Section 
14 Flood Control Act of 1946, as amended.) 
Barkers Island, WI -A contract for erosion protection of Marina 
Drive and a high pressure gas line was completed at a cost of 
$12,512. Engineering and design, and supervision and administration 
costs were $11,504. Total FY 86 costs were $24,016. 
Bayshore Drive, N. Shoemaker Road, WI - Preparation of the 
O&M Manual was completed and financial close-out of the project 
was initiated. Costs for FY 86 were $5,537. 
Bridgeport Charter Township, MI - A contract for streambank 
31-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
erosion protection of the Fayette Street bridge was awarded in 
late September 1986. No work was performed this FY. Preparation 
of plans and specifications and advertisement and award costs 
in FY 86 were $32,639. 
Charlevoix Harbor, MI - Financial close-out of the project was 
completed at a cost of $17 Federal and $3,461 non-Federal. 
Elkhart River, Elkhart, IN - Preparation of the O&M Manual 
was completed and financial close-out of the project was initiated. 
Costs for FY 86 were -$1,101. 
Lake Michigan Shoreline, Grand Haven, MI - A contract for 
shoreline erosion protection of Harbor Drive was awarded in 
August 1986 and initiated in September 1986. Approximately 22 
percent of the work was completed at a cost of $60,000. Engineering 
and design, and supervision and administration costs were 
$38,713. Total FY 86 costs were $98,713. 
Lake Michigan Shoreline, Port Washington, WI - The contract 
for shoreline erosion protection of the Water Filtration Plant Intake 
System, which was awarded in FY 85, was initiated and completed 
at a cost of $194,000 Federal and $250,481 non-Federal. 
Engineering and design, and supervision and administration costs 
were $8,248 Federal and $29,119 non-Federal. Total FY 86 costs 
wee $202,248 Federal and $279,600 non-Federal. 
Lake Michigan Shoreline, Warren Dunes State Park, MI - 
Reimbursement of an unfavorable Initial Appraisal Report was 
completed at a cost of $7,500. 
Lake Michigan Shoreline, Cudahy, WI - A contract for erosion 
protection for the City's electric sub-station and pump house 
was awarded in late September 1986. No work was performed 
this FY. Reimbursement of the Appraisal Report, preparation of 
plans and specifications, and advertisement and award costs in 
FY 86 were $26,961. 
Lake Michigan Shoreline, Cleveland, WI -A contract for erosion 
protection for the City's waste water treatment plant was 
awarded in late September 1986. No work was performed this 
FY. Reimbursement of the Appraisal Report, preparation of plans 
and specifications, and advertisement and award costs in FY 86 
were $33,354. 
Lake Michigan Shoreline, Lake Shore Drive, Michiana, MI - 
Reimbursement of an unfavorable Initial Appraisal Report was 
completed at a cost of $6,500. 
Lake Michigan Shoreline, Manitowoc-Two Rivers, WI - Reimbursement 
of an unfavorable Initial Appraisal Report was completed 
at a cost of $7,500. 
Manistee, MI - The previously completed contract for shoreline 
erosion protection of Lakeshore Road was modified to provide 
an additional 20 feet of bank protection work to prevent possible 
undermining and failure of the completed protection work and 
all work was completed at a cost of $25,997. Engineering and 
design and supervision and administration costs were $5,250. 
Total FY 86 costs were $31,247. 
Zoological Gardens, Racine, WI - Financial close-out of the 
project was completed. Costs for FY 86 were $2,267 Federal 
and $3,885 non-Federal. 
72. BEACH EROSION WORK UNDER 
SPECIAL AUTHORIZATION 
Beach erosion activities pursuant to Section 103 of the 1962 
River and Harbor Act. All work was suspended on the Escanaba 
and Ontonagon, MI projects because the projects lacked economic 
justification when recreation benefits were excluded. FY 86 costs 
were $1,528 for Escanaba, MI and $13,292 for Ontonagon, MI. 
73. MITIGATION OF SHORE DAMAGES 
Mitigation of Shore Damages pursuant to Section 111 of the 
River and Harbor Act of 1968. Expanded Reconnaissance 
Report efforts were continued on Algoma, WI ($6,898), 
Marinette, WI ($15,489) and Sturgeon Bay, WI ($16,719). 
Detailed project study efforts were terminated at Saxon, WI when 
the project lacked economic justification when recreational 
benefits were excluded ($476). Coordination efforts continued 
on Presque Isle Harbor, MI (-$290). 
Flood Control 
74. KAWKAWLIN RIVER, MI 
Location. River drains an irregularly shaped area of about 220 
square miles in Bay, Gladwin, Midland, and Saginaw Counties 
in east-central Michigan and discharges into Saginaw Bay 2 miles 
northwest of Saginaw River. (See Geological Survey Bay City 
quadrangle and NOAA Nautical Charts 14867 and 14863.) 
Existing project. Provides for deepening about 1.8 miles of 
river channel between the river mouth and Euclid Street Bridge; 
altering Detroit and Mackinac Railway Bridge by addition of two 
45.9-foot spans; protecting by riprapping the channel bottom 
through Euclid Street Bridge, existing piers at Henry Street Bridge 
and Detroit and Mackinac Railway Bridge; and a number of utility 
relocations. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance: Condition 
surveys, supervision and administration cost $287. An adjustment 
of -$747 was made to close-out a contract. 
75. SAGINAW RIVER, MI 
Location. Saginaw River basin including its tributaries, Tittabawassee, 
Shiawassee, Flint and Cass Rivers, drains an area 
of 6,260 square miles in the east central part of Michigan and 
empties into Saginaw Bay, an arm of Lake Huron. Bay City, near 
mouth of river, and Saginaw, 22 miles upstream from mouth, 
are on Federally improved deep-draft Saginaw River navigation 
channel. (See Saginaw and Flint Geological quadrangles and 
NOAA Nautical Chart 14867) 
Existing project. Provides for improvements in Saginaw River 
Basin for flood control and other purposes: (a) at Middle Branch 
and South Branch, Cass River, to provide for major drainage improvements 
by channel improvements on Middle and South 
Branches, including a short reach of East Branch, at an estimated 
U.S. cost (July 1961) for construction of $1,448,000 for Middle 
and South Branches; provided local interests contribute in cash 
31-26

DETROIT, MI DISTRICT 
42 percent of first cost of major drainage project on Middle 
Branch, and 38 percent of first cost of major drainage project 
on South Branch, exclusive of cost of rights-of-way and other 
work required as local cooperation, and give assurances satisfactory 
to Secretary of the Army they will construct and maintain 
local drainage work required to fully and effectively utilize improvements 
to be provided under the Federal projects; (b) at 
Vassar on Cass River, to provide for flood protection of areas 
on north and south sides of river by channel improvement, levee 
construction, floodwalls, modification of Moore Drain, and 
related work at an estimatd U.S. cost (Oct. 1984) of $8,620,000 
and non-Federal cost of $579,000 for construction; (c) at Frankenmuth 
on Cass River, to provide for flood protection of areas on 
north side of river by channel improvement, levee construction, 
and related work, at an estimated U.S. cost (July 1974) of 
$410,900 for construction; (d) at Flint on Flint River, to provide 
for flood protection of areas on both sides of main stem of Flint 
River and its tributaries, Swartz and Thread Creeks by channel 
improvement, bridge alterations, floodwall and levee construction, 
and related work, at an estimated U.S. cost (Oct. 1984) of 
$18,251,600 and non-Federal cost of $2,580,000 for construction; 
provided local interests contribute in cash 1 percent of first 
cost of project, exclusive of costs of rights-of-ways (e) at Corunna 
on Shiawassee River, to provide for flood protection by 
channel improvement, levee construction, and related work at 
an estimated U.S. cost (July 1961) of $48,000 for construction; 
provided local interests modify spillway of mill dam at Corunna 
at their own expense, substantially in accordance with plan of 
District Engineer and subject to approval of Chief of Engineers, 
or in lieu thereof, contribute to the United States actual cost of 
modification to be performed by the United States; (f) at Owosso 
on Shiawassee River, to provide for flood protection by channel 
improvement at an estimated U.S. cost (July 1961) of $425,000 
for construction; (g) at Midland on Tittabawassee River, to provide 
for flood protection through non-structural (permanent 
evacuation) measures at an estimated U.S. cost (Apr. 1982) of 
$5,125,000 and non-Federal cost of $1,611,500 for implementation; 
however, project was reclassified to the "inactive" 
category on December 15, 1982; (h) at Shiawassee Flats along 
lower reaches of the four principal tributaries of Saginaw River, 
to provide for flood protection, including fish and wildlife areas; 
by channel improvement, levees, lateral reservoirs with control 
structures and related work at an estimated U.S. cost (Oct. 1984) 
of $23,417,500 Federal, and a non-Federal cost of $2,705,000 
which includes a cash contribution of $1,237,000; provided local 
interests contribute in cash 5 percent of cost of rights-of-way for 
flood control and other work required as local cooperation, and 
furnish one-half of land required for fish and wildlife areas; provided 
that the Federal allocation for conservation does not exceed 
amount obtained by taking 28 percent of project cost for 
Shiawassee Flats unit and subtracting therefrom one-half cost of 
lands for conservation; and provided further that before starting 
works for flood control to Shiawassee Flats, Chief of Engineeers 
and Director, Fish and Wildlife Service, prepare a plan mutually 
acceptable to Secretary of the Army and Secretary of the Interior 
for operation of fish and wildlife areas to required degree 
of controlled storage of flood-waters while preserving the maximum 
fish and wildlife benefits. Total estimated cost for new 
work, for active portion (1984) is $50,700,000 Federal and 
$1,421,000 to be contributed by local interests. Total estimated 
cost (1984) to local interests is $5,870,000. 
Local cooperation. Responsible local interests must make cash 
contributions as called for above; furnish lands, and rights-ofway, 
including removal of buildings, for construction; hold the 
United States free from damage; maintain and operate all works 
after completion; establish and enforce regulations designed to 
prevent encroachments in improved channels; and bear expense 
of constructing highway relocations and highway bridges, alter 
bridge approaches and existing highway bridge approaches and 
existing highway bridges (except underpinning and bridge raising), 
and alter utilities. Required assurances for Flint River at 
Flint were furnished by City of Flint and accepted by the United 
States on November 23, 1962. Estimated required cash contribution 
for Flint ($56,000) was furnished February 20, 1963. An 
additional $117,000 was furnished by the City to cover increased 
construction costs. Required assurances for Cass River at 
Frankenmuth were accepted on September 8, 1964. All necessary 
lands, easements, and rights-of-way have been provided. The 
Midland City Council adopted a resolution on June 7, 1982 declaring 
its intent not to sponsor the Flood Control project on the Tittabawassee 
River at Midland. The Vassar City Council, in a letter 
dated January 26, 1982, indicated a willingness and capability 
to provide the assurances of local cooperation for the Vassar 
Flood Control Project. Saginaw County, in a resolution dated 
August 11, 1982, indicated a willingness and capability to provide 
the assurances of local cooperation for the Shiawassee Flats 
Flood Control Project. 
Operations during fiscal year. New Work: Shiawassee: Work 
on preparing a General Design Memorandum, initiated in FY 
83, continued in FY 86. Total cost for Shiawassee this FY is 
$2,937. 
Flint: Investigation of claims for contract completed in FY 80 
was continued at a cost of $50,941. 
Vasser: Work on preparing a General Design Memorandum, 
initiated in FY 83, continued in FY 86. Total cost for Vassar 
this FY is $3,459. 
The Frankenmuth and Flint portions of the project are complete. 
Total costs for this project in FY 86 were $57,336. 
76. SEBEWAING, SEBEWAING RIVER, MI 
Location. Sebewaing River drains an area of 105 square miles 
in Huron and Tuscola Counties on the westerly side of Thumb 
area of Lower Peninsula of Michigan and discharges into Saginaw 
Bay, an arm of Lake Huron, 20 miles northeast from mouth of 
Saginaw River. Village of Sebewaing is near mouth of River. 
(See NOAA Nautical Chart 14863.) 
Existing project. Enlarging present channel of Sebewaing 
River through Village of Sebewaing, MI, to a capacity of 7,500 
cubic feet per second from junction of Columbia and State drains 
to a point 4,500 feet lakeward from railroad bridge near mouth; 
altering railroad bridge and three highway bridges to permit free 
passage of ice; and removal of present dike on south side of channel 
lakeward from railroad bridge. Project is designed to provide 
protection for Village of Sebewaing from floods with a frequency 
of once in 15 years and with a magnitude greater than 
the maximum flood of record. (See Table 31-B for authorizing 
legislation.) 
31-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Local cooperation. Complied with except for furnishing 
easements and rights-of-way for removal of remaining portion 
of dike on south side of channel lakeward from railroad bridge. 
Operations during fiscal year. Maintenance: Condition 
surveys, inspections and reports were performed by Government 
forces at a cost of $16,224. 
77. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
The listed projects were inspected during this period. Battle 
Creek, Kalamazoo River, MI; Kawkawlin, Kawkawlin River, 
MI; Sebewaing, Sebewaing River, MI; Flint, Flint River, MI; 
Frankenmuth, Cass River, MI; Mount Clemens Spillway and 
Cutoff Canal, Clinton River, MI; Red Run, Clinton River, MI; 
Estral Beach, Lake Erie, MI; Fort Wayne Mechanic St. Dike, 
St. Marys River, IN; Rouge River, MI; Burr Oak, Prairie River, 
MI. Fiscal year costs were $136,008. Total costs to end of FY 
year were $1,158,677. 
78. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 31-H. 
79. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency Flood Control Activities, Flood Fighting (Public 
Law 84-99 and P.L. 93-288 and Antecedent Legislation). 
1. In late 1985 and throughout 1986 the potential for flooding 
along the Great Lakes shorelines, particulary on Lake Superior, 
Lakes Michigan-Huron, Lake Erie and the Connecting Channels 
of the St. Clair River, Lake St. Clair, and the Detroit River continued 
and even increased as water levels set new record highs 
month after month for the past year. The conditions for sustaining 
these perilous water levels worsened in September 1986 as 
extremely heavy rainfall on the Great Lakes Basin caused extensive 
flooding on rivers tributary to these lakes. Throughout this 
period NCE staff provided technical assistance, flood fighting 
equipment, and materials (787,000 sandbags and 25 pumps) to 
state and local entities to mitigate local storm events. 
a. October 1, 1985 - September 30, 1986: Implementation of 
PL 84-99 Advance Measures flood protection program continued 
for Great Lakes shoreline communities in response to record lake 
levels. Six flood protection projects have been completed at a 
cost of $5,403,450. A seventh has been approved pending completion 
of local cooperation agreements. Eighteen other communities 
were evaluated or reevaluated during this period for 
eligibility under Advance Measures. Costs incurred for Advance 
Measures letter reports: $98,029. 
b. (1) The Rehabilitation Levee Project under PL 84-99 at Fort 
Wayne, Indiana, started in September 1985, was completed in 
April 1986 at a cost of approximately $290,000. 
(2) Damage surveys and a Rehabilitation Letter Report were 
completed for the Corps-constructed, locally operated Saginaw 
River Basin Flood Control Project at Flint, Michigan. Damages 
to this project were sustained from the flash floods of Sep. 6-9. 
1985. The Letter Report was approved by higher authority and 
the District initiated plans and specs for the rehab work. However, 
further work on the project was terminated because of a lack of 
response from the City of Flint to execute an Assurance Agreement 
with the U.S. Government. Study and design costs to date: $24,164. 
(3) A final determination was made that damaged agricultural 
levees (private) along the lower Flint River did not qualify for 
assistance through Corps authorities. These levees had been washed 
out in many places as a result of the Sep. 6-9, 85 floods. 
c. The Detroit District experienced the following significant 
flood events during the period October 1, 1985 through September 
30, 1986: 
(1) December 28, 1985 - April 18, 1986: During this period 
almost continuous record-high water levels from the St. Clair 
River, Lake St. Clair, Detroit River and Lake Erie surged onto 
shoreline community developments as a result of ice jamming 
or high winds. Major flooding occurred in St. Clair County, 
Michigan, with minor but frequent events in Monroe, Wayne, 
and Macomb Counties. Evacuations were necessary at various 
times, particularly along the lower reaches of the St. Clair River. 
U.S. Coast Guard assistance was rendered on numerous occasions 
to break-up the ice pack and relieve water retardation. 
Damages were largely confined to basement and first floor of 
residential homes, flooded roads, gas and water main ruptures, 
and interrupted telephone service. No disaster declaration was 
issued. Incurred costs for Corps flood-fight actions: $61,077. 
(2) August 6, 1986: A severe rain storm hit the Milwaukee, 
Wisonsin metropolitan area, breaking previous rainfall records 
for a 24-hour period. A maximum 6.8 inches of rain occurred 
in a period from 12 a.m. to 8:45 p.m. Flash flooding occurred 
as streets became rivers and water rapidly collected several feet 
deep in low areas causing streets and highways, including 1-94, 
to become impassable. Sanitary sewer backup caused many 
basements to flood. The City of Milwaukee reported 10,000 
basements affected, causing damages from collapsed foundation 
walls to content damage. Two deaths were reported as a result 
of flooding. The Milwaukee Airport suffered $2 million in 
damage and was forced to close because of electrical damage to 
operational equipment. Overall damage is estimated at $5.9 
million. A Presidential Disaster was declared. Local rivers and 
creeks reached flood frequencies rated as great as 500-year. Corps 
aid was not requested due to the flash-flood nature of this event 
and the District EOC was not activated. Division emergency staff 
represented the District on the Hazard Mitigation Team. An Interagency 
Hazard Mitigation Team Report was issued on August 29. 
(3) September 11-30, 1986: Flooding in Central Michigan 
and Eastern Wisconsin caused by record rainfalls of 8 to 13 inches 
in 24 hours inundated a wide area (160 miles long x 60 miles 
wide) across central Michigan from Lake Michigan to Lake 
Huron. Lesser amounts of rainfall from the same storm system 
caused flooding in several eastern counties in Wisconsin between 
Milwaukee and Green Bay. Precipitation occurred for 26 straight 
days in the Michigan flood area, reaching September totals as 
much as 19 inches. Record flood stages were experienced in the 
following Michigan rivers: Cass, Pine, Tittabawassee, Chippewa, 
Rogue, Flat, Muskegon, Pere Marquette, and Little Muskegon. 
Because of the widespread nature of the storms, numerous smaller 
ungaged streams also experienced flooding which were likely 
record stages. Some areas, i.e., the Cities of Midland and Vassar, 
Michigan, experienced flood stages which were above what had 
31-28

DETROIT, MI DISTRICT 
been considered to be the 500-year event. Eleven dams failed 
and nineteen others were threatened with failure. Overall, ten 
deaths were attributed to actual drownings or flood related conditions. 
A Presidential Disaster was declared for both Michigan 
(28 Counties) and Wisconsin (5 Counties), to provide Federal 
assistance to alleviate flood damage which approached $400 
million in Michigan and $7 million in Wisconsin. The Detroit 
District mobilized a total of 56 persons for this event. The District 
EOC was activated during this period, and although Corps contracting 
assistance for flood-fighting efforts was not required, the 
District was active furnishing flood-fight materials: 493,400 sandbags, 
199 poly rolls and 16 pumps. Corps personnel were not 
requested to assist FEMA in PL 93-288 actions except for service 
on the Hazard Mitigation Team. Incurred costs for Corps 
flood-fight support actions during this event: $320,662. 
d. Minor flood problems were experienced during the winter 
months of 1986 as a result of ice jamming on the Fox River, 
Outagamie County, and Oconto River, Oconto County, Wisconsin; 
Sturgeon River, Cheboygan County and River Raisin, 
Monroe County, Michigan. 
2. A report was prepared for Congress, in response to an 
amendment to the Supplemental Appropriations Act of 1986, 
directing the Secretary of the Army to develop emergency contingency 
plans in consultation with the states involved to prevent 
near-term flooding along the Great Lakes. The Detroit District 
was tasked as the lead in preparation of this "Contingency Plan 
Report" which was completed in August 1986. Costs incurred 
for preparation and coordination of this report: $41,040. 
Flood Control activities pursuant to Section 205 of the 1948 
Flood Control Act. The contract for flood damage reduction at 
Paw Paw Lake, MI, which was awarded in FY 85, was initiated 
in October 1985. Approximately 96 percent of the work was completed 
at a cost of $2,777,125. The Detailed Project Report was 
continued on the Ontonagon, MI project ($64,377), and a Reconnaissance 
Report was completed and the appraisal report reimbursement 
was received for Judy Creek, IN ($67,457). A negative 
appraisal report was completed and funds reimbursed for Rouge 
River, Farmington Hills, MI ($7,500). 
Flood Control activities pursuant to Section 208 of the 1954 
Flood Control Act. Reimbursement was received for the 
favorable appraisal report for LaGrange County, IN ($7,495). 
Preparation of the O&M Manual was continued and reimbursement 
was received for the appraisal report for Maple River, MI 
($10,904). 
Aquatic Plant Control activities pursuant to Section 302 of 
the River and Harbor Act of 1965 (PL 89-298). An aquatic 
plant control reconnaissance study was completed for Houghton 
Lake and Lake St. Helen within Roscommon County, MI. Funds 
in the amount of $979 were expended in FY 1986. 
80. SURVEILLANCE OF NORTHERN 
BOUNDARY WATERS 
Field Operations. The following field operations, which were 
complemented by office activities in support of basic missions, 
were conducted during the current period: In support of the 
development and calibration of Detroit District mathematical 
models of the Connecting Channels, soundings and discharge 
measurements were conducted on the St. Clair and Detroit Rivers. 
Discharge measurements were made in the Welland Canal and 
analyzed by the Water Survey of Canada supported by District 
personnel. Additional field measurements are scheduled on the 
St. Lawrence, Niagara, St. Clair, and Detroit Rivers and on the 
Ogoki Diversion during FY 87. 
During the winter months, the District monitors the presence 
of ice in the St. Marys, St. Clair, and Detroit Rivers as an ongoing 
mission. Water levels are monitored at key gages in these 
rivers for continuous updating of hydrographs for detection of 
possible ice jams and associated potential for flooding. This provides 
advance warning to area residents and other governmental 
agencies (in support of respective Flood Alert Plans). This 
monitoring activity utilizes satellite data relay technology which 
provides water level data in the District Office within minutes 
of data collection. 
International Activities. The following activities were conducted 
specifically for the International Joint Commission (IJC) 
Boards and Committees: 
Members of the Detroit District staff attended the spring and 
fall semi-annual appearances of the International Great Lakes 
Boards before the Commission in Washington, D.C. and Quebec 
City, Quebec, respectively. 
As a result of the record high lake levels, changed economic 
conditions and improved analytical techniques, the Governments 
of the United States and Canada issued the IJC a Reference, on 
August 1, 1986, requesting a new Great Lakes level regulation 
study. The IJC will investigate appropriate methods to alleviate 
problems associated with fluctuating water levels and to assess 
the viability of further lake level regulation. Once the studies are 
complete, the governments should be in a better position to make 
a determination regarding control of lake levels over the long 
term. 
a. International Lake Superior Board of Control. The 
Detroit District Engineer is the United States Regulation 
Representative of the Board of Control. In support of the U.S. 
Section of the Board, the District provided monthly Lake Superior 
outflow recommendations based upon a review of the hydrologic 
factors which influence the future regulation of Lake Superior. 
These recommendations were based on the use of probability 
forecasts of water supplies routed through the lakes, rendering 
outflows under Plan 1977, the currently approved operating rule. 
On April 25, 1985, the International Joint Commission directed 
the Board to deviate from Plan 1977 and to implement a flow 
reduction from Lake Superior beginning in May. This action was 
intended to alleviate high water conditions on Lakes Michigan, 
Huron, St. Clair and Erie, each of which experienced record high 
water levels during the spring. In response to this directive, the 
Board authorized flow reductions from May through August, 
amounting to an accumulation of 118,000 cfs-months. From 
September through November 1985, due to above normal 
precipitation causing a continuing rise in the water level of Lake 
Superior, several increases in the Lake Superior outflow were 
31-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
made, with an all-time record high outflow of 132,000 cfs being 
discharged during part of October and all of November. The 
outflow was reduced to approximately 85,000 cfs beginning in 
mid-December, the winter maximum according to Plan 1977. On 
March 19, 1986, the UIC directed the Board to reduce the outflow 
from Lake Superior to that specified by Plan 1977, 82,000 cfs. 
By letter of April 23, 1986, the IJC informed the Board that, 
until further notice, the monthly outflows from Lake Superior 
be determined by Plan 1977 and that the amount of water remaining 
in storage as a result of the Commission's emergency actions 
(30,000 cfs-months), be retained on Lake Superior. 
On several occasions between late July and late September 
1986, it was necessary to reduce the Lake Superior outflow for 
short periods to offset potential flooding in the Sault Ste. Marie 
Harbor. In order to permit a much quicker response time in effecting 
flow changes during such conditions, a portion of the 
outflow which normally would have been discharged through the 
Compensating Works was discharged through the U.S. navigation 
locks. The Board continues to closely monitor lake levels 
and will advise the Commission if and when additional flow 
changes are warranted. 
b. International Niagara Board of Control and International 
Niagara Working Committee. The Chief of the Lake Hydrology 
Section of the Great Lakes Hydraulics and Hydrology Branch 
is on the U.S. Section of the Working Committee. Under the 
auspices of the International Niagara Committee, the Detroit 
District computes, coordinates and publishes, with Canada, the 
monthly flows in the Niagara River. The District also provides 
direct technical support and consulting engineering services to 
the Board and Committee. The District is involved with the 
verification of the rating curves for the Ashland Avenue and 
American Falls gages. As part of the on-going program to 
periodically verify the stage-discharge relationship for these 
gages, discharge measurements are scheduled in the Cableway 
Section in early FY 87. In FY 88, a further series of 
measurements are scheduled at the Cableway Section for verification 
of the Ashland Avenue Rating Curve. Also during FY 88, 
measurements are planned at the American Falls Channel Section 
to check the amount of flow over the American Falls. 
c. International St. Lawrence River Board of Control. When 
requested, the Detroit District supported the Buffalo District in 
its activities. In early FY 87, the Detroit District plans to conduct 
an intensive flow measurement program in various reaches 
of the St. Lawrence River to be used as input to existing 
mathematical models of the river and also for proposed physical 
models. This effort is required to assist the Board in making 
various regulatory decisions during periods of high flow in the 
St. Lawrence River. 
d. International Great Lakes Diversions and Consumptive 
Uses Study Board. The IJC submitted its recommendations, 
based on the Board's report and subsequent public hearings, to 
the governments of the United States and Canada, in a report 
dated January 1985. A former Detroit District Engineer was 
Chairman of the U.S. Section of the Working Committee. Until 
such time as the Board is either dissolved or continued, certain 
personnel within the District continue to hold membership on the 
Diversions and Environmental Evaluation Subcommittees and on 
the Public Involvement Ad Hoc Group. 
e. International Great Lakes Technical Information Network 
Board. The former Chief of the Great Lakes Hydraulics 
and Hydrology Branch was U.S. Chairman of this Board. The 
Chief of the Lake Hydrology Section remains the Secretary to 
the U.S. Section of this Board, as well as a member on the 
Hydraulics and Hydrology Committees. The Board completed 
its study and provided a report of its findings and recommendations 
to the Commission in December 1984. In January 1985, 
the IJC informed the governments of the United States and Canada 
of the findings of the Board. Furthermore, the Commission 
recommended that a committee be established to provide an international 
mechanism for institutional coordination between the 
operational Boards of the UC and agencies making studies, gathering 
and providing data on the Great Lakes System. This Board 
would assume the functions of the "Coordinating Committee on 
Great Lakes Basic Hydraulic and Hydrologic Data." 
Coordinating Committee on Great Lakes Basic Hydraulic 
and Hydrology Data. The Chief of the Lake Hydrology Section 
of the Great Lakes Hydraulics and Hyrdology Branch is the 
U.S. Secretary to this committee, as well as a member of its subcommittees. 
Operations continued pertaining to the coordination 
of basic hydraulic and hydrologic data with Canada. Coordinating 
Committee reports being worked on in the District include one 
which documents the discharge measurements made on the Great 
Lakes Connecting Channels and St. Lawrence River during the 
period 1900-1978. Another report being worked on documents 
the flow in the St. Clair and Detroit Rivers, 1900-1985. Through 
the auspices of the Coordinating Committee, the Corps of 
Engineers by 1983, had provided funds to Canada, in the amount 
of $215,000, to aid in completion of precise leveling in the International 
Section of the St. Lawrence River. This survey, as 
well as similar surveys conducted in the U.S. by NOAA, are part 
of a program to update the International Great Lakes Datum 
(IGLD). The new IGLD will evolve around the epic year 1980 
and is expected to be published in FY 87-88. The Committee is 
scheduled to meet in Detroit in early FY 87. 
NCD Master Plan for Water Control Data System. In FY 
86, the District began implementation of the Great Lakes Water 
Control Data System, based upon a Harris-800 minicomputer and 
automated gaging stations. The Computer collects data from the 
District's data collection platforms (DCP's), from dedicated lines 
to the National Weather Service's telecommunication network, 
and from NOAA/NOS and Canadian water level computer 
systems. The District has 19 DCP's active and plans to install 
as many as 18 additional DCP's in FY 87. 
Great Lakes Information Management. The District has 
developed an automated computer mapping center based upon 
a stand-alone image processing system capable of processing 
satellite and aircraft derived data. Besides processing remotely 
sensed data, the system provides capabilities for generating multiparameter 
data bases for basin-wide hydrologic models, and for 
generating high-resolution graphics and drafting products. The 
computer mapping center is supporting the District's water control 
minicomputer in the monitoring of snowpack and ice conditions 
over the District's territory. 
31-30

DETROIT, MI DISTRICT 
Hydraulics and Hydrology of the Great Lakes. Studies to 
improve the existing Great Lakes water level forecasting system, 
including investigations into the factors affecting the Great Lakes 
water balance relationship (i.e., runoff, precipitation over water, 
evaporation, ice retardation, etc.) and use of real-time hydrologic 
data were continued by Great Lakes Hydraulics and Hydrology 
Branch staff members. Several conceptual hydrologic models 
have been studied and are being calibrated for eventual use in 
future forecasts of lake levels and outflows. District personnel 
participated, for the fourth year, in a five-year program to assess 
water supplies on the Lake Superior basin through use of 
automated hydromet stations, airborne snow and soil moisture 
surveys, and satellite imagery. 
Levels of the Great Lakes. The Branch provided technical 
information and expertise regarding lake levels and long range 
still water forecasts to many interested parties, such as Congressmen, 
State and local officials, news media, navigation and 
power interests, and concerned property owners. Explanation of 
the water levels was supplied to the public in the form of direct 
answers to numerous inquiries, addresses to various civic groups, 
and interviews with news media. The publication of an international 
(U.S. and Canada) forecast of Great Lakes water levels, 
under the auspices of the Coordinating Committee on Great Lakes 
Basic Hydraulic and Hydrologic Data, was continued during the 
period. In support of these forecasts and to assist in lake regulation, 
funds have been provided to the Department of Commerce 
for maintenance of eleven telemetric water level gages at selected 
sites throughout the Great Lakes to obtain near real-time data. 
Total costs under Surveillance and Northern Boundary Waters 
for FY 86 are $1,308,778. 
General Investigations 
81. SURVEYS 
Fiscal year costs were $55,555 for the navigation study on the 
Great Lakes Connecting Channels and Harbors, and $6,262 for 
the review of the authorized Fox River, WI project. Flood 
Damage Prevention studies cost $966,312. A feasibility study at 
Fort Wayne, IN was continued with preparation of a Draft 
Feasibility Report and DEIS, at a cost of $435,669 Federal funds 
and $60,730 non-Federal contributed funds. Funds in the amount 
of $284,125 were spent on the continuation of the Ecorse Creek 
Basin, Wayne County Flood Protection Study. In addition, 
$24,881 were expended in support of work efforts on a Summary 
Report dealing with the overall study authority for the Great 
Lakes, Particularly Lake Ontario and Lake Erie, of which Ecorse 
Creek Basin is an Interim study. Continuation of planning on the 
Saginaw River, MI Basin Study was accomplished at a cost of 
$221,637. 
82. CONTINUATION OF PLANNING 
AND ENGINEERING 
FY 86 costs for the continuation of planning and engineering 
for Monroe Harbor, MI, were $109,654. 
A Final Survey Report recommending structural modifications 
was completed in February 1980. The report recommendations 
are: to deepen the River Raisin portion of the project to 27 feet; 
to widen to 500 feet and deepen to 28 feet the entrance channel 
from Lake Erie; to provide a new turning basin able to accommodate 
1,000 foot vessels; and to construct a confined disposal 
facility that would create a 700 acre marsh and provide shoreline 
protection behind the disposal facility. 
The Monroe Harbor Study was included in the FY 1984, 1985, 
and 1986 budgets under the category "Continuation of Planning 
and Engineering" for the purpose of collecting updated and detailed 
project data, reevaluating project channel dimensions and 
dredged material disposal requirements, reaffirming project 
economic and environmental feasibility, and preparing 
preliminary project design. Although no major change in the 
scope of the recommended plan is anticipated at this time, a reduction 
in recommended channel width and alternative dredge 
material disposal options were considered. 
Work in FY 86 consisted of the reevaluation of project 
economic and environmental feasibility conducted in FY 85 using 
updated benefits and cost data. The work consisted of the 
reevaluation of several alternative channel designs, detailed 
dredge and quantity estimates, and cost estimates for dredging 
and alternative disposal options. Comprehensive benefit evaluation 
of project users was also accomplished. A preliminary 
benefit-cost analysis was completed to update the economic 
evaluation of the project. 
83. COLLECTION AND STUDY OF 
BASIC DATA 
a. Coordination Studies with Other Agencies. These studies 
include Special Investigations, $34,000 (includes $15,000 for 
engineering and technical assistance given to local citizens because 
of the high lake levels of the Great Lakes); F.E.R.C., $2,000; 
Soil Conservation Service, $2,000; Planning Assistance to States 
(Section 22), $52,003; International Water Studies, $24,000; and 
Flood Plain Management Services, $154,211. A special 
hydrologic study to develop a regional flood frequency study for 
the Saginaw River Basin was initiated in FY 80, and the preparation 
of a final report was continued in FY 86. Costs for this project 
in FY 86 were $2,000. 
b. Flood Insurance Studies. Five Michigan Flood Insurance 
Studies were completed in FY 86. They were: Blissfield Village, 
Lenawee County; Hamlin Township, Mason County; Memphis 
City, Macomb County; Sault Ste. Marie City, Chippewa County; 
and Summit Township, Mason County. The studies were completed 
at a total cost of $109,446. The FY 86 costs were $6,495, 
$6,686, $8,319, $8,205, and $2,201, respectively. Flood Insurance 
Studies for Allen County, IN, and in Michigan for Bangor 
City, Van Buren County; Allegan City, Allegan County; AuGres 
City and AuGres Township, Arenac County; Clare City, Clare 
County; Manistee Township, Manistee County; Mayfield 
Township, Lapeer County; and Scio Township, Washtenaw 
County, will be completed in FY 87. The FY 86 costs associated 
with these studies were $27,815, $25,980, $11,054, $7,472, 
$10,642, $10,253, $6,103, $8,007, and $5,785, respectively. 
Work was initiated on Flood Insurance Studies for Novi City, 
Oakland County ($7,614); Three Rivers City, St. Joseph County 
($18,276); and Lapeer Township, Lapeer County ($8,362) at 
a total FY 86 cost of $34,252. 
31-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
In addition, costs thru FY 86, in support of the Federal 
Emergency Management Agency's Community Assistance Program, 
were $18,969. 
31-32

DETROIT, MI DISTRICT 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY83 FY84 FY85 FY86 Sept.30,1986 
1. Arcadia Harbor, 
MI 
2. Ashland Harbor, 
WI 
3. Big Suamico Harbor, 
WI 
4. Black River Harbor, 
MI (U.P.) 
5. Bolles Harbor, 
MI 
6. Charlevoix Harbor, 
MI 
7. Cheboygan Harbor, 
MI 
8. Clinton River, 
MI 
9. Cornucopia Harbor, 
WI 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- - - 0 
153,800 62,514 291,000 117,000 
155,998 67,248 263,563 144,618 
88,000 238,000 27,552 115,000 
77,490 246,921 15,687 129,603 
- - - 8,757 
- - - 8,757 
11,000 11,000 81,000 
11,000 10,912 65,033 
-6,000 
8,645 
- 26,412 167,964 
- 18,642 153,415 
314,000 272,000 63,000 182,000 
310,454 288,220 52,979 154,568 
15,000 10,000 2,396 -16,528 
12,608 10,585 2,798 -15,337 
12,660 16,001 6,539 
12,660 16,001 6,539 
8,662 
8,662 
33,000 115,000 40,000 71,000 
33,412 88,419 62,567 72,663 
- - 118,086 
- - 112,517 
5,165 
10,734 
31-33 
TABLE 31-A 
00 
1,255,362 
1,254,817 
1,695,645 
1,695,645 
2,610,348 
2,610,348 
20,243 
20,243 
175,362 
175,362 
383,350 
383,350 
578,423 
577,013 
426,413' 
426,413' 
1,070,841 
1,048,522 
1,190,550 
1,190,550 
180,623 
180,623 
5,053,900 
5,014,240 
1,129,396 
1,129,396 
504,236 
504,236 
860,730 
860,241 
549,7982 
549,7982 
1,023,459 
1,023,459 
461,200 
454,701 
462,653 
462,653 
831,125 
831,125

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY83 FY84 FY85 FY86 Sept.30,19 86 
10. Detour Harbor, 
MI 
Contributed Funds 
11. Detroit River, 
MI 
Contributed Funds 
12. Duluth-Superior Harbor, 
MN and WI 
13. Fox River, 
WI 
14. Frankfort Harbor, 
MI 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
-864 
-45,564 
-30,626 
280 
280 
-34,600 
1,455 
-975 5,975 
1,478 4,266 
1,478 3,900 
8,675,000 3,894,546 9,438,900 
8,530,302 4,546,281 8,932,080 
3,752 
4,118 
3,446,800 
4,109,489 
- -14,000 25,000 0 
3,610 5,459 22,256 1,383 
- - - 242,280 
- - - 203,000 
1,354,910 
1,354,910 
1,204,436 
1,204,436 
9,776 
9,776 
76,877,3573 
76,877,3573 
72,593,824 
72,520,849 
41,400,694 
41,397,610 
242,280 
203,000 
- - - - 16,109,2584 
- - - - 16,109,2584 
2,348,000 2,431,000 3,377,400 1,973,700 35,382,270 
1,886,071 2,687,668 3,493,775 1,945,302 35,245,639 
- 2,410,000 4,830,000 
- 2,291,677 4,773,781 
1,556,249 
1,556,249 
7,240,000 
7,065,458 
- - - - 3,753,3345 
- - - - 3,753,3345 
1,780,000 1,782,000 1,018,000 1,063,000 36,895,6736 
1,752,331 1,603,620 1,247,075 1,064,843 36,855,0616 
- - - - 1,955,1597 
- - - - 1,955,1597 
-476,000 372,500 72,000 45,000 6,278,897 
994,733 367,153 75,243 49,296 6,276,016 
- - - - 274,776 
- - - - 274,776 
35,000 
82,950 
1,204,500 
23 - 1,204,500 
31-34

DETROIT, MI DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section To 
in Text Project 
15. Grand Haven Harbor, 
MI 
Section III 
Section III 
Contributed Funds 
16. Grand Marias Harbor, 
MN 
17. Green Bay Harbor, 
WI 
18. Hammond Bay Harbor, 
MI 
Section III 
Section III 
19. Harbor Beach Harbor, 
MI 
Funding 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
FY83 FY84 FY85 FY86 Sept.30,1986 
- - - - 1,283,4698 
- - - - 1,283,4698 
- - - - 175,000 
- - - - 175,000 
3,747,000 887,546 1,442,616 615,700 20,384,1559 
1,024,174 3,551,803 1,497,972 615,944 20,380,6589 
-- - - 813,613 
- - - - 813,613 
125,000 203,184 1,181,500 
70,860 236,764 1,204,587 
15,334 
50,000 
44,199 
251 
292,000 
273,423 
1,079,000 
1,071,033 
780,400 
780,400 
1,733,684 
1,731,071 
27,200 
15,585 
450,972 
450,972 
2,014,879 
1,966,798 
1,230,000 
1,230,000 
- - - 9,946,39510o,t 
- - - 9,946,39510,11 
917,350 1,035,672 1,761,000 15,963,23512 
961,792 1,069,546 1,604,864 15,774,48212 
6,583,807 
6,578,763 
1,015,366 
1,015,366 
77,000 
77,000 
428,835 
428,016 
50,000 
48,518 
1,200,598 
1,200,598 
6,039,339 
6,027,021 
194,504 
194,504 
243,100 
243,100 
145,000 
139,860 
27,200 
34,910 
19,174 
8,163 
1,605,000 
1,904,126 
104,000 230,000 395,000 290,000 
101,122 211,613 390,568 310,913 
-10,000 
10,243 
-9,180 
51,191 
3,244 
4,000 
3,683 
25,000 
19,202 
130,000 60,000 
73,791 113,766 
68,875 2,898 
58,841 12,430 
- 25,000 
2,669 26,647 
532,200 313,949 
525,580 310,694 
31-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section To 
in Text Project Funding FY83 FY84 FY85 FY86 Sept.30,19 8 6 
20. Harrisville Harbor. New Work 
MI 
Contributed Funds 
Section III 
Section III 
21. Holland Harbor, 
MI 
Section III 
Section III 
22. Inland Route, 
MI 
23. Kenosha Harbor, 
WI 
24. Kewaunee Harbor, 
WI 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
340,000 
17,633 
250,000 
3,794 
430,000 
152,128 
136,097 
131,724 
3,021,100 
2,320,232 
39,000 
36,665 
333,000 
349,018 
-44,000 
5,330 
100,000 
90,467 
100,000 
79,795 
-90,000 
232,368 
70,000 
259,445 
22,000 
320,813 
4,000 
8,239 
1,422,760 
1,758,195 
35,000 
33,713 
-15,000 
-63,981 
-32,516 
24,215 
6,401 
3,376 
13,000 
11,137 
571,720 
934,563 
558,000 
421,857 
-36,700 
12,281 
1,603 
3,770 
24,000 
25,557 
1,849,938 
1,849,938 
287,454 
287,454 
502,000 
502,000 
756,201 
755,209 
37,000 
36,694 
- 771,82713,14 
- 771,827'13,14 
- 621,000 
- 621,000 
507,000 12,406,712 
484,876 12,380,306 
694,000 1,460,200 
828,919 1,455,354 
- 502,452 
- 502,452. 
2,400 90,000 86,000 
12,934 90,723 60,666 
30,000 
38,658 
368,000 
380,004 
12,000 
3,726 
94,491 
107,405 
- - 6,000 
- - 6,000 
625,400 406,250 189,000 
607,019 400,880 218,132 
8,077 
208,000 
168,916 
1,663,300 
1,663,300 
918,222'5 
918,222's 
2,231,888 
2,201,833 
404,300 
404,300 
988,96916,17 
987,89716,17 
2,960,86818 
2,920,330'18 
1,270,275 
1,270,275 
- 4,378,600 
- 4,378,600 
- 758,33319 
- 758,33319 
243,000 3,553,59120 
225,007 3,535,31220 
- 617,300 
- 617,300 
31-36

DETROIT, MI DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section To 
in Text Project Funding FY83 FY84 FY85 FY86 Sept.30,1986 
25. Keweenaw 
Waterway, MI 
26. Knife River 
Harbor, MN 
27. La Pointe 
Harbor, WI 
28. Lake St. Clair, 
MI, Channels 
29. Leland Harbor, 
MI 
30. Lexington Harbor, 
MI 
Contributed Funds 
Section III 
Section 111 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
2,961,461 
747 2,961,461 
- - - - 5,974,141 
- - - - 5,974,141 
410,000 309,000 410,000 681,000 11,551,68421 
345,687 329,088 438,285 668,439 11,521,15921 
101,000 70,000 72,000 241,000 
78,172 90,863 70,506 220,193 
1 
24,638 
23,808 
824 37,432 
1,654 32,110 
- 9,974 
- 9,669 
13,551 
11,572 
3,651 
8,973 
296 
2,400 
491,000 
466,734 
412,945 
412,945 
291,174 
291,174 
130,874 
130,874 
88,385 
88,385 
- - - - 7,675,35722 
- - - - 7,675,35722 
346,000 745,400 297,000 262,600 7,155,08423 
323,961 767,954 299,095 260,663 7,134,79223 
- - - - 5,119,800 
- - - - 5,119,800 
189,000 236,466 66,600 100,000 
177,087 251,778 62,264 104,735 
- - 
25,000 12,000 
24,973 11,033 
- 20,000 
44,575 19,789 
3,131 
4,125 
254,000 
101,984 
260,000 
407,397 
1,027,08924 
1,027,08924 
1,513,511 
1,512,970 
70,678 
70,678 
1,646,304 
1,646,304 
1,088,888 
1,088,888 
372,000 
372,000 
124,044 
124,044 
714,000 
709,170 
31-37

REPORT OF THE CHIEF OF ENGINEERS U.S. ARMY 1986 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section To 
in Text Project Funding FY83 FY84 FY85 FY86 Sept.30,1986 
31. Little Lake Harbor, 
MI 
32. Ludington Harbor, 
MI 
Section III 
Section III 
33. Mackinac Island Harbor, 
MI 
Contributed Funds 
34. Mackinaw City Harbor, 
MI 
35. Manistee Harbor, 
MI 
36. Manitowoc Harbor, 
WI 
Contributed Funds 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
129,000 165,283 229,458 263,000 
106,875 135,253 256,986 279,129 
549,500 
726,766 
564,366 
544,182 
427,900 
420,772 
- 710,540 
- 692,796 
600,47825 
600,47825 
2,768,515 
2,760,015 
- 7,912,20226 
- 7,912,20226 
- 620,000 
- 620,000 
329,000 8,406,56627 
337,698 8,377,32727 
- 357,913 
- 357,913 
-64,000 661,540 
-46,931 660,865 
- 22,274 
- 22,023 
- 27,525 
- 16,852 
4,946 
15,619 
229,085 
229,085 
105,004 
105,004 
93,744 
93,493 
136,28628 
136,28628 
76,061 
76,061 
- - - - 2,696,52229 
- - - - 2,696,52229 
190,000 474,300 29,000 816,000 5,154,73330 
195,904 466,666 36,254 791,534 5,126,88730 
- - - - 1,374,164 
- - - - 1,374,164 
250,000 
342,112 
381,800 
799,140 
753,000 
297,937 
10,000 
22,154 
9,206 
1,883 
309,690 
763,277 
-141,950 
-137,174 
-74,718 
114,139 
124,000 
125,891 
- 2,048,91431' 
- 2,048,91431 
9,206 1,948,494 
- 1,911,076 
296,000 4,927,51532 
300,389 4,901,28832 
3,081,756 
3,081,756 
31-38

DETROIT, MI DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section To 
in Text Project Funding FY83 FY84 FY85 FY86 Sept.30,1986 
37. Marquette Harbor, New Work 
MI 
38. Menominee Harbor 
& River, MI & WI 
Contributed Funds 
39. Milwaukee Harbor, 
WI 
40. Monroe Harbor, 
MI 
Contributed Funds 
41. Muskegon Harbor, 
MI 
Section III 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
477 
987 
73,192 
73,577 
22,448 
21,556 
204,384 
204,324 
1,282,893 
1,282,893 
1,807,281 
1,806,329 
465,757 
465,757 
- - - - 533,476"3 
- - - - 533,47633 
33,000 113,000 55,000 104,000 1,784,45434 
33,898 35,520 123,282 109,403 1,778,02534 
- --- 1,351,852 
- - - - 1,351,852 
46,000 47,000 110,000 -10,000 
24,427 64,434 101,568 2,288 
410,000 1,106,700 74,000 
412,327 1,027,490 168,317 
- - 2,010,000 
- - 1,940,752 
593,660 
591,014 
36,762 
36,762 
- 8,231,02435 
- 8,231,02435 
440,000 24,596,27436 
399,452 24,552,52536 
3,205,000 7,106,810 
3,189,537 7,022,099 
6,380,925 
6,380,925 
- - - - 987,34037 
- - - - 987,34037 
398,000 777,450 1,873,000 1,640,900 12,778,12037 
380,264 656,686 1,936,061 1,700,939 12,743,69237 
22,268,000 2,850,000 995,000 -17,000 38,621,900 
19,021,218 6,152,561 1,024,457 -23,493 38,580,588 
85,000 
77,130 
85,000 
610 77,740 
- - - - 2,912,11038 
- - - - 2,912,11038 
- - - - 105,000 
- - - - 105,000 
207,000 579,000 81,000 86,000 5,444,11539 
209,364 574,185 90,592 89,926 5,442,55039 
31-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section To 
in Text Project Funding FY83 FY84 FY85 FY86 Sept.30,1986 
Section III 
42. New Buffalo Harbor, 
MI 
Contributed Funds 
43. Ontonagon Harbor, 
MI 
44. Pensaukee Harbor, 
WI 
45. Pentwater Harbor, 
MI 
46. Petoskey Harbor, 
MI 
47. Point Lookout Harbor, 
MI 
Contributed Funds 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
40,000 
33,785 
3,800,000 
74,251 
20,000 
16,028 
-350,000 
3,315,594 
48,000 
34,955 
5,100,000 
4,996,129 
1,593,000 
1,602,842 
1,337,300 
1,468,604 
204,870 112,000 311,600 526,000 
204,085 105,922 173,015 664,118 
100,000 
91,417 
215,000 
211,013 
157,000 
162,633 
359,300 
353,444 
150,000 
145,546 
544,000 
541,664 
83,000 
77,669 
916,000 
919,158 
- - 13,193 
- - 13,193 
82,000 97,533 174,004 194,666 
81,223 99,697 169,340 194,467 
- - 5,600 
- - 5,600 
- 218,074 2,391 
- 213,805 6,660 
419,721 124,734 441,522 1,701,100 
244,539 263,875 291,697 1,882,296 
12,000 
8,651 
- -2,743 
- 606 
31-40 
1,904,000 
1,890,610 
13,764,300 
13,731,578 
1,285,716 
1,285,716 
1,186,467 
1,186,467 
2,798,153 
2,790,823 
181,500 
181,500 
886,90340 
874,46840 
7,680,55341 
7,668,44841' 
21,000 
21,000 
34,035 
34,035 
206,507 
206,507 
179,899 
179,899 
3,025,255 
3,019,329 
123,839 
123,839 
543,811 
543,811 
2,642,584 
2,642,584 
2,938,190 
2,933,520 
121,600 
121,600 
9,257 
9,257

DETROIT, MI DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section To 
in Text Project Funding FY83 FY84 FY85 FY86 Sept.30,1986 
48. Port Austin Harbor, 
MI 
49. Portage Lake, 
MI 
50. Port Sanilac Harbor, 
MI 
Contributed Funds 
Section III 
Contributed Funds 
Section III 
51. Port Washington Harbor, 
WI 
Contributed Funds 
52. Port Wing Harbor, 
WI 
53. Racine Harbor, 
WI 
Section III 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
15,658 
15,658 
4,185 
5,102 
3,738 
6,476 
17,272 
9,795 
531,472 
48,528 
52,000 
50,753 
60,613 
544,368 
1,340 13,336 120,385 
1,584 8,554 125,487 
16,522 16,000 
16,065 9,552 
1,772 
8,676 
15,000 230,000 249,000 - 
41,228 222,335 71,321 185,852 
806 
10,000 
12,147 
9,000 
8,999 
157,000 24,313 
157,000 21,027 
1,180,33442 
1,179,08742 
1,625,633 
1,618,966 
159,000 
159,000 
256,129 
256,129 
1,551,217 
1,550,407 
909,963 
909,963 
487,108 
487,108 
336,000 
336,000 
1,575,184 
1,575,183 
115,000 
115,000 
9,158 
9,158 
802,000 
799,569 
- 2,582,20443 
- 2,582,20443 
-12,936 2,413,44544 
-9,650 2,413,44544 
4,000 245,717 -47,476 
4,001 236,862 -38,621 
10,621 
10,621 
1,624,000 
1,624,000 
63,393 
63,393 
792,270 
792,270 
- 1,297,31545 
- 1,297,31545 
- 35,000 
31-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section To 
in Text Project Funding FY83 FY84 FY85 FY86 Sept.30, 1 986 
t - - - 35.000 
Section III 
54. Rouge River, 
MI. 
55. Saginaw River, 
MI. 
(Federal Funds) 
(Contributed Funds) 
56. St. Clair River, 
MI. 
57. St. Joseph 
Harbor, MI. 
Section III 
Section III 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
16,636 
1166,,663366 95,011 22,083 
93,011 24,083 
35,000 20,000 51,000 
26,698 28,178 43,920 
12,362 2,944,88246 
9,320 2,941,84046 
- 1,253,645 
- 1,253,645 
2,000 
8,338 
3,948,754 
3,948,754 
108,000 
107,134 
- - - 675,25147 
- - - - 675,25147 
394,000 859,615 776,500 711,700 15,747,60348 
675,053 835,802 836,762 694,589 15,715,89248 
- - 10,000 - 14,523,823 
-1,210 24,085 4,885 329 14,517,030 
- - - - 14,917,12749 
- - - - 14,917,12749 
- - - - 13,600 
- - - - 13,600 
2,333,400 5,531,140 2,781,675 626,200 32,749,295 
2,030,316 5,729,604 2,829,598 680,370 32,738,458 
90,000 223,000 260,000 182,500 19,185,9000 
89,284 184,873 256,689 207,953 19,159,93450 
- - - - 19,213,246 
- - - - 19,213,246 
1,781,000 1,224,256 1,510,000 816,100 14,820,913 
1,792,998 1,259,444 1,462,529 863,958 14,805,888 
448,000 413,616 511,900 611,000 
434,728 423,156 506,647 591,221 
58,000 
19,428 
361,000 
323,946 
21,000 
51,533 
333,000 
258,348 
135,000 
127,783 
114,000 
152,156 
14,595 
730,000 
632,995 
976,4855' 
976,4855' 
828,000 
828,000 
8,184,465 
8,152,841 
962,216 
962,216 
643,776 
642,908 
3,345,300 
3,174,743 
31-42

DETROIT, MI DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section To 
in Text Project Funding FY83 FY84 FY85 FY86 Sept.30,1986 
58. St. Marvs River, New Work 
59. Saugatuck Harbor, 
MI 
and Kalamazoo 
River, MI 
60. Saxon Harbor, 
WI 
Section III 
61. Sheboygan Harbor, 
WI 
62. South Haven Harbor, 
MI 
Section III 
Section III 
63. Sturgeon Bay, 
WI & Lake MI 
Ship Canal, WI 
MI -m 
8,818,256 
8,329,035 
10,006,700 9,221,000 
10,323,209 8,973,402 
- 160,657,07152 
- 160,657,07052 
9,704,800 176,567,108 
9,761,729 176,011,557 
13,100 
13,100 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
- - - 364,52753 
- - - 364,52753 
-15,000 265,100 78,559 3,002,28654 
19,969 249,974 95,146 3,002,13054 
41,500 
39,200 
6,649 
6,649 
3,000 
4,685 
56,259 
36,398 
2,237 
25,098 
426,50755 
426,50755 
669,000 
667,393 
415,602 
415,602 
- - - - 1,136,08856 
- - - - 1,136,08856 
843,000 775,000 157,000 327,000 4,811,39257 
167,298 1,449,627 124,641 363,502 4,810,23857 
- - - - 609,028 
- - - - 609,028 
66,000 203,000 82,000 -15,000 907,792 
71,290 200,475 68,476 9,231 907,728 
121,881 
100,849 
- - - 452,42658 
- - - 452,42658 
- - - 532,000 
- - - 532,000 
-10,000 148,868 87,000 3,484,46659 
15,372 133,324 84,580 3,466,30259 
- - - 1,632,076 
- - - 1,632,076 
- 25,000 483,000 312,000 
- 14,741 125,600 669,316 
42,381 
42,381 
1,144,000 
1,133,657 
- 1,059,72260 
- 1,059,72260 
31-43 
182,000 
151,739 
45,000 
44,008 
7,767 
7,767

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section To 
in Text Project Funding FY83 FY84 FY85 FY86 Sept.30,19 86 
64. Tawas Bay Harbor, 
MI 
(Contributed Funds) 
65. Two Rivers Harbor, 
WI 
66. White Lake Harbor, 
MI 
Section III 
Section III 
74. Kawkawlin River, 
MI 
75. Saginaw River, 
MI 
(Federal Funds) 
(Contributed Funds) 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
93,000 72,000 406,000 176,000 7,098,61561 
105,873 68,069 234,819 346,931 7,093,98161 
28,000 
10,823 
-9,000 37,000 - 
9,057 25,485 11,953 
- - - 3,700 
831 - - 3,611 
- - - -10,323 
- - - -3,611 
- - - 1,735 
- - - 1,735 
311,119 
311,118 
884,899 
884,899 
1,154,068 
1,153,979 
989,677 
989,677 
20,925 
20,925 
- - - - 360,32062 
- - - - 360,32062 
10,987 27,000 131,000 21,978 5,386,06663 
10,987 26,890 119,914 21,017 5,373,90963 
- - - - 1,187,472 
- - - - 1,187,472 
- - - - 58,057 
- - - - 58,057 
45,000 
39,731 
96,000 
63,364 
-5,300 - 
1,678 - 
-20,000 193,000 
13,691 189,917 
- 262,000 
- 214,040 
- 250,000 
- 234,889 7,271 
1,855,000 658,400 180,000 
1,523,178 957,427 108,667 
98,000 
98,248 
389,000 
429,111 
-8,300 
-460 
207,862 
207,862 
249,700 
249,700 
2,158,463 
2,154,828 
651,000 
643,151 
241,700 
241,700 
- 24,553,359 
57,336 24,502,236 
- 173,000 
- 172,997 
31-44

DETROIT, MI DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section To 
in Text Project Funding FY83 FY84 FY85 FY86 Sept.30,1986 
76. Sebewaing River, New Work 
MI Approp. - - - - 365,64264 
Cost - - - 365,64264 
Maint. 
Approp. 32,000 -10,500 17,000 9,000 391,644 
Cost 9,533 11,411 7,332 16,224 388,644 
80. Surveillance of New Work 
North Boundary Approp. - - - - 0 
Waters Cost - - - 0 
Maint. 
Approp. 1,165,000 1,234,000 1,596,000 1,330,000 40,224,33465 
Cost 1,092,046 1,281,669 1,587,312 1,308,778 40,142,19465 
'Includes $255,000 contributed funds. 
2Includes $25,500 for previous projects and $289,752 contributed 
funds for existing projects. 
3Includes $2,097,254 for previous projects. 
4Includes $1,547,195 for new work for previous projects. 
5Includes $3,239,910 for previous projects. 
6Includes $89,309 for previous projects. 
7Includes $31,709 contributed funds. 
8Includes $311,329 for previous projects. 
9Includes $13,437 for previous projects. 
'0 Includes $396,974 for previous projects. 
"Includes $109,463 for previous projects. 
12Includes $8,918 for previous projects. 
"Includes $176,620 for new work, $127,598 for maintenance. 
14Includes $35,705 contributed funds. 
'SIncludes $148,000 contributed funds for existing project. 
'6Includes $453,839 for previous projects. 
"'Excludes $3,000 contributed funds. 
' Includes $21,818 for previous projects. 
'9Includes $149,312 for previous projects. 
20Includes $88,364 for previous projects. 
21Includes $402,242 for previous projects 
22Includes $656,000 for previous projects. 
23Includes $235,346 for previous projects. 
24Includes $354,139 contributed funds. 
25Includes $57,670 contributed funds. 
26lncludes $491,416 for previous projects. 
27Includes $126,451 for previous projects. 
28Excludes $136,286 contributed funds. 
29Includes $354,999 for previous projects. 
30lncludes $150,910 for previous projects. 
3Includes $400,126 for previous projects. 
32Includes $54,288 for previous projects. 
33Includes $312,423 for previous projects. 
"Includes $36,194 for previous projects. 
"Includes $1,293,220 for previous projects. 
3Includes $459,305 for previous projects. 
"Includes contributed funds of $300,000 for new work and $166,667 
for maintenance contributed by: Port Commission of Monroe, $300,000; 
Consolidated Paper Co., $125,000 and River Raisin Co., $41,667. 
3Includes $613,408 for previous projects. 
39Includes $446,183 for previous projects. 
40Includes $284,802 for previous projects. 
41Includes $113,326 for previous projects. 
42Includes $172,100 contributed funds. 
43Includes $188,495 for previous projects. 
44Includes $15,123 for previous projects. 
45Includes $427,240 for previous projects. 
46Includes $79,537 for previous projects. 
47Inlcudes $50,084 for previous projects. 
48Includes $56,608 for previous projects. 
49Includes $962,556 for previous projects. 
50lncludes $1,671,660 Public Works Funds and $49,419 
emergency relief funds. 
"Includes $503,113 for previous projects. 
"2Includes $2,904,807 for previous projects. 
5Includes $90,232 for previous projects. 
"Includes $117,554 for previous projects. 
"Excludes $50,193 contributed funds. 
'6Includes $487,817 for previous projects. 
"Includes $87,131 for previous projects. 
"Includes $187,233 for previous projects. 
59Includes $131,239 for previous projects. 
60Includes $323,419 for previous projects. 
6'Includes $219,730 for previous projects. 
62Includes $212,857 for previous projects. 
63Includes $33,113 for previous projects. 
64Includes $15,000 for previous projects. 
65Includes $3,973,897 for previous projects. 
31-45

TABLE 31-B 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISTLATION 
Acts Work Authorized Documents 
Mar. 3, 1905 
Aug. 5, 1886 
Aug. 11, 1888 
Mar. 3, 1899 
Jun. 6, 1900 
Aug. 8, 1917 
Jul. 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Jul. 14, 1960 
Aug. 26, 1937 
Mar. 2, 1945 
Jul. 6, 1965 
Aug. 14, 1876 
Aug. 2, 1882 
Jun. 13, 1902 
Jun. 20, 1938 
Mar. 29, 1977 
Jun. 2, 1896 
Mar. 2, 1907 
Aug. 26, 1937 
May 17, 1950 
Oct. 21, 1964 
Aug. 5, 1886 
Jul. 19, 1963 
Aug. 26, 1937 
ARCADIA HARBOR, MI (See Section 1 of Text) 
Maintenance of existing 12-foot channel. 
ASHLAND HARBOR, WI. (See Section 2 of Text) 
Breakwater 7,900 feet long and dredging to remove a shoal. 
Appropriation of $60,000 for 'Continuing improvements on enlarged project.' 
(On completion of Poe Lock in 1896, with available depth of 
20 feet, dredging at Ashland Harbor was carried to a similar depth.) 
Detached breakwater extending 4,700 feet out from shore at a point 
2,600 feet east of main breakwater (prolonged) and parallel thereto. 
Project modified by omitting detached breakwater and defining depth and 
extent of channel to be dredged. 
Widening part of present channel for entrance channel and for basin in 
eastern part of harbor. 
Deepening east basin to 25 feet and west channel, as far as 8th Ave. West 
extended to 21 feet. 
Widening west channel to 750 feet at its westerly end. 
Deepening portions of East Basin and West Channel to 27 and 21 feet, 
respectively. 
BIG SUAMICO RIVER, WI (See Section 3 of Text) 
Channel from Green Bay to 1,800 feet above the river mouth. 
BLACK RIVER HARBOR, MI (UPPER PENINSULA) 
(See Section 4 of Text) 
Two converging breakwaters, an entrance channel between breakwaters, 
an inner channel, and an irregular harbor basin. Project depths 12 feet in 
approach channel and 8 feet in the river channel and basin. 
BOLLES HARBOR, MI (See Section 5 of Text) 
Entrance channel in Lake Erie, Access channel in LaPlaisance Creek, 
Steel sheet pile revetment. 
CHARLEVOIX HARBOR, MI (See Section 6 of Text) 
Channel from Lake Michigan to Round Lake protected where needed 
by piers and revetments. 
Channel from Round Lake to Lake Charlevoix. 
Project depth increased to 15 feet. 
Project depth increased to 18 feet. 
Project depth increased to 24 and 23 feet, and construction of 
revetment upstream of Highway Bridge. 
CHEBOYGAN HARBOR, MI (See Section 7 of Text) 
181/2 foot channel. 
81/2 foot channel. 
Turning Basin. 
21-foot channel to East 1st St., Enlarge Turning Basin, 
deepen to 21 feet. 
Breakwater. 
CLINTON RIVER, MI (See Section 8 of Text) 
Channel in River and Lake St. Clair, Pile Dike, 
Closing channels and making Cutoff, and 
revetments as needed. 
Widening entrance channel and constructing protected 
harbor basin. 
CORNUCOPIA HARBOR, WI (See Section 9 of Text) 
Entrance channel 50 feet wide and 10 feet deep between existing 
piers from bay to a turning basin 200 feet long, 8 feet deep, with 
H. Doc. 194, 58th Cong., 2d Sess. 
H.Ex. Doc. 89, 48th Cong., 2d Sess. 
Annual Reports, 1886, p. 1674; and 
1887, p. 1966. 
H. Doc. 1698, 64th Cong., 2d Sess. 
S. Doc. 133, 71st Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 46, 82d Cong., 1st Sess. 
H. Doc. 337, 77th Cong., 1st Sess. 
H. Doc. 165, 86th Cong., 1st Sess.' 
H. Doc. 498, 74th, Cong., 2d Sess.' 
H. Doc. 446, 78th Cong., 2d Sess.' 
Section 107, 1960 River and 
Harbor Act. 
S. Ex. Doc. 16, 44th Cong., 1st 
Sess., and Annual 
Report 1876, p. 523 
No Prior Survey of Estimates. 
No Prior Survey of Estimates. 
S. Doc. 163, 75th Cong., 3rd Sess.' 
Section 107, 1960 River and 
Harbor Act. 
Annual Report, 1895, p. 2823 
H. Doc. 357, 59th Cong., 1st Sess. 
H. Doc. 134, 75th Cong., 1st Sess. 
H. Doc. 269, 81st Cong., 1st Sess.' 
Section 107, 1960 River and 
Harbor Act. 
S. Doc. 199, 46th Cong., 2d Sess. 
Annual Report 1880, p. 2062 and 
H. Doc. 210, 44th Cong., 2d Sess. 
and Annual Report 1886, p. 219 
Section 107, 1960 River and 
Harbor Act. 
S. Committe, 75th Cong., 1st Sess. 
31-46

TABLE 31-B (Continued) 
DETROIT, MI DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sep. 3, 1954 
Jun. 3, 1969 
Jun. 13, 1902 
Mar. 3, 1905 
Jun. 25, 1910 
Mar. 4, 1913 
Mar. 2, 1907 
Jun. 25, 1910 
Mar. 2, 1910 
Jul. 3, 1930 
Aug. 30, 19353 
Aug. 26, 1937 
Mar. 2, 1945 
Jul. 24, 1946 
May 17, 19504 
Mar. 21, 1956 
Jul. 14, 1960 
Aug. 13, 1968 
Jun. 3, 1896 
Jun. 13, 1902 
Mar. 2, 1907 
maximum width of 180 feet, with 150 and 300-foot inner channels 
each 50 feet wide and 8 feet deep. 
Reconstruction and Federal maintenance of east and west entrance 
piers, a 25-foot extension of west pier and a 300-foot extension of 
existing westerly inner channel at a depth of 8 feet and a width 
of 50 feet. 
DETOUR HARBOR, MI (See Section 10 of Text) 
Small boat harbor and harbor of refuge, 10-foot channel, 
8-foot deep access channel protected by 1,000-foot breakwater. 
DETROIT RIVER, MI (See Section 11 of Text) 
Amherstburg Channel and removal of Grosse lie 
shoal. 
Fighting Island Channel. 
Livingstone Channel. 
Channel Depths of 26 and 25 feet. 
Channel to Wyandotte 21 feet deep and 300 feet wide through 
Middle Ground opposite Head of Fighting Island. 
Trenton Channel and Turning Basin (West of 
Grosse Ile). 
American Channel North of Belle Isle between 
Windmill Point and Fairway Slip, Detroit. 
Deepen Westerly 300 feet of Amherstburg Channel 
and Ballards Reef Channel below Livingstone 
Channel to 27 feet to provide depths adequate 
for 24-foot draft navigation when governing Lakes 
are at Datum, with necessary widening at approaches 
and bends and construction of necessary compensating 
works. Detroit River. 
Extend Turning Basin in Trenton Channel 600 feet. 
Dredge through East Draw of lower Grosse Ile Bridge and 
extend 300-foot width of Channel North of lower Grosse Ile Bridge. 
Channel Depth of 28.5 feet throughout downbound and Two-Way 
Channels, except in upper (27.7-foot depth) and lower, (29-foot 
depth) Livingstone Channel, and in upbound Channel; 27-foot depth 
in Ballards Reef Channel below junction with Livingstone Channel. 
27.5-foot depth in westerly 300-foot width of Limekiln Crossing 
and Amherstburg Reaches, and 28.5-foot depth in westerly 300-foot 
width of Hackett Beach, with necessary compensation works. Also 
28.5-foot depth in Lake Erie from Detroit River to Pelee Passage Shoal. 
Inclusive. 
Trenton Channel; Deepen to 27 feet, where necessary, Wyandotte 
Reach from Detroit River to Upper Grosse Ile Bridge, about 
5.5 miles, deepen to 28 feet and widen to 300 feet below Upper 
Grosse Ile Bridge to and including a Turning Basin 28 feet deep and 15 
across in area outside project limits. 
Trenton Channel: Deepen to 28 feet and widen to 300 feet from the 
Upper Turning Basin at Trenton to Gibraltar, about 20,500 feet 
downstream: Construct a Turning Basin at Gibraltar at a depth of 
28 feet, width of 830 feet, and length of 1,500 feet: Build 
compensating works to maintain water levels. 
DULUTH-SUPERIOR HARBOR, MN AND WI 
(See Section 12 of Text) 
Dredging. 
Rebuilding piers at Superior Entry. 
Enlarge plan for Superior Entry and additional dredging near 
draw span of Burlington Northern railway bridge. 
H. Doc. 434, 83rd Cong., 2d Sess.' 
Section 107, 1960 River and 
Harbor Act. 
H. Doc. 712, 56th Cong., 1st Sess. 
and 40, 58th Cong., 3rd Sess. 
H. Doc. 17, 62d Cong., 1st Sess.. 
H. Doc. 266, 59th Cong., 2nd Sess. 
676, 61st Cong., 2d Sess, and 32, 
65th Cong., 1st Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 1, 72nd Cong., 1st Sess.' 
H. Doc. 205, 75th Cong., 1st Sess. 
H. Doc. 734, 79th Cong., 2d Sess. 
H. Doc. 335, 80th Cong., 1st Sess. 
S. Doc. 30, 81st Cong., 1st Sess.' 
S. Doc. 71, 84th Cong., 1st Sess.' 
H. Doc. 319, 86th Cong., 2d Sess.' 
H. Doc. 338, 90th Cong., 2d Sess.' 
H. Ex. Doc. 59, 53d Cong., 3d Sess. 
and Annual Report, 1895, p. 2538. 
H. Doc. 82, 59th Cong., 2d 
Sess. 
31-47

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 28, 19085 
Jul. 27, 1916 
Mar. 2, 1919 
Jan. 21, 1927 
Jul. 30, 19303 
Aug. 30, 19303 
Jul. 16, 19526 
Jul. 14, 19607 
Oct. 4, 1961 
Aug. 5, 1886 
Sep. 19, 1890 
Jun. 3, 1896 
Jun. 3, 1896 
Jun. 13, 1902 
Mar. 3, 19258 
Jun.26, 19349 
Jul. 3, 195810 
Jun. 23, 1866" 
Mar. 3, 1925 
Aug. 26, 1937 
Oct. 27, 1965 
Jun. 23, 1866 
Jun. 14, 1880 
Sep. 19, 1890 
Jul. 13, 1892 
Jul. 3, 1930 
Aug.26, 1937 
Mar. 2, 1945 
Mar. 3, 1879 
Aug. 30, 1935 
May 17, 1950 
Jun. 23, 1866 
Dredging additional area for basin inside Duluth entrance to 
22-foot depth. 
Enlarging Superior Harbor Basin. 
Removal of shoal point at southerly end of East Gate Basin. 
Howards Bay Channel, 20 feet deep. 
Deepening and widening channels and basins. 
Deepen Superior Front Channel and a portion of East Gate 
Basin to 25 feet. 
Present project dimensions of channels and basin. 
Abandons northerly portion of 21st Avenue West Channel. 
FOX RIVER, WI (See Section 13 of Text) 
Improvement of Fox River. 
Dredging Fond du Lac Harbor on Lake Winnebago. 
Improvement of Wolf River 
Improvement of Stockbridge, of Calumet 
and Miller Bay, and of Brothertown Harbor, 
on Lake Winnebago. 
Increased depth in rock cuts on lower river, widen Neenah 
Channel, and a concrete retaining wall at Kaukauna. 
Operation and care of locks and dams provided for with funds from 
War Department appropriations for rivers and harbors. 
Sec. 108, that Federal project structure, appurtenances, and 
real property of Upper Fox River, WI, be disposed of to 
State of Wisconsin. 
FRANKFORT HARBOR, MI (See Section 14 of Text) 
A New Outlet 12 feet deep protected by Piers and Revetments. 
Exterior Breakwaters, removal of portions of Piers, 
Project Dimensions of Outer Basin. 
Dredge the area in Lake Betsie. 
Deepen approach and entrance Channels. 
Extend Inner Basin and Dredge recreational anchorage area. 
GRAND HAVEN HARBOR, MI (See Section 15 of Text) 
Piers and Revetments. 
Piers and Revetments. 
Piers and Revetments. 
Piers and Revetments. 
Present Project dimensions of Harbor Channel to 
Grand Trunk Car Ferry Slip and River Channel. Eliminating all of 
that portion of Grand River above Bass River, Consolidation 
of Projects for Harbor and River. 
Channel to Spring Lake 
Present Project Dimensions of Harbor Channel from 
Car Ferry Slip to Grand Trunk Railway Bridge and Turning Basin. 
GRAND MARAIS HARBOR, MN (See Section 16 of Text) 
Breakwaters and dredging of anchorage area of 
26 acres to 16 feet. 
Seawalls across ledge in southeast corner of harbor, 
enlarging anchorage basin and deepening of entrance. 
Small-boat basin with breakwater. 
GREEN BAY HARBOR WI (See Section 17 of Text) 
Outer Channel and revetment at Grassy Islands.' 2 
H. Doc. 221, 60th Cong., 1st 
Sess. 
H. Doc. 651, 64th Cong., 1st Sess. 
H. Doc. 1018, 64th Cong., 1st Sess. 
H. Doc. 145, 69th Cong., 1st Sess. 
and Rivers and Harbors Committee, 
Doc. 32, 71st Cong., 2d Sess. 
H. Doc. 482, 72d Cong., 2d Sess. 
H. Doc. 374, 82d Cong., 2d 
Sess. 
H. Doc. 150, 86th Cong., 1st Sess. 
H. Doc. 196, 86th Cong., 1st Sess. 
Annual Report, 1885, pp. 2041-2045 
(plan of a board approach Dec. 10, 
1884, as modified by Corps of 
Engineers, May 14, 1886). 
H. Ex. Doc. 24, 51st Cong. 1st Sess. 
Annual Report, 1890, p. 2390. 
No prior survey or estimates. 
No prior survey or estimates. 
No prior survey or estimates. 
H. Doc. 294, 68th Cong., 1st Sess.' 
S. Bill 3910, 85th Cong., 2d Sess. 
H. Doc. 482, 5th Cong., 2d Sess. 
H. Doc. 208, 68th Cong.,lst Sess. 
H. Doc. 511, 74th Cong., 2d Sess. 
S. Doc. 16, 89th Cong., 1st Sess.' 
S. Ex. Doc. 42, 35th Cong.,1st Sess. 
S. Ex. Doc. 42, 35th Cong., 1st Sess. 
S. Ex. Doc. 42, 35th Cong., 1st Sess. 
S. Ex. Doc. 42, 35th Cong., 1st Sess. 
S. Doc. 88, 71st Cong., 2d Sess. 
Rivers and Harbors Committee 
Doec. 1, 75th Cong., 3d Sess.' 
H. Doc. 661, 76th Cong.,3d Sess.' 
H. Ex. Doc. 75, 43d Cong., 2d Sess. 
Annual Report, 1875, p. 184. 
Rivers and Harbors Committee 
Doc. 22, 72d Cong., 1st Sess. 
H. Doc. 187, 81st Cong., 1st Sess.' 
Annual Report, 1867, p. 70. 
31-48

TABLE 31-B (Continued) 
DETROIT, MI DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 13, 1892 Inner channel. 12 Unpublished report approved Aug. 3, 
Jun. 26, 1910 
Aug. 8, 1917 
Mar. 3, 1925 
Aug. 30, 19352 
Aug. 26, 1937 
Mar. 2, 1945 
Oct. 23, 1962 
Mar. 2, 1945 
Mar. 3, 1871 
Jan. 21,1927 
Jul. 16, 1984 
Mar. 2, 1945 
Aug. 30, 1852 
Mar. 2, 1867 
Mar. 3, 1899 
Mar. 3, 1905 
Jul. 3, 1930 
Aug. 30, 1935 
Sep. 3, 1954 
Sep. 3, 1954 
Sep. 2, 1964 
Mar. 3, 1899 
Mar. 2, 1907 
Aug. 30, 19352 
Turning basin at DePere. 
Maintenance of turning basin at DePere. 
Increasing depth of inner channel and turning basin to 18 feet. 
Deepen outer channel to 22 feet with widening and straightening 
inside of Tail Point Bend, widen channel in Fox River through 
city of Green Bay to 22 feet. 
Turning basin above Chicago & North Western Ry. Bridge. 
Turning basin at mouth of East River. 
Deepen and widen 9 miles of entrance channel to 26 by 500 feet; 
3.6 miles of entrance channel to 24 by 300 feet; and 3.2 miles 
of existing Fox River to 24 feet deep. 
HAMMOND BAY HARBOR, MI 
(See Section 18 of Text) 
Harbor of Refuge, breakwaters. 
10-foot depth in harbor basin 
12-foot depth in entrance channel. 
HARBOR BEACH, LAKE HURON, MI 
(See Section 19 of Text) 
Adopted Site and made provision for harbor. 
Closing North Entrance and dredging 
Main Entrance and Anchorage Area. 
Removal of portion of Breakwater in interest of sanitation. 
Deepen the waterway within the Marina facility. 
HARRISVILLE HARBOR, MI (See Section 20 of Text) 
Harbor of Refuge, Breakwaters. 
12-foot depth entrance channel 
10-foot depth in harbor basin. 
Extend north end of south breakwater 100 feet; extend southeast 
end of north breakwater 145 feet; install two navigation light structures. 
HOLLAND HARBOR, MI (See Section 21 of Text) 
Artificial channel between Lakes 
Macatawa and Michigan.' 2 
Piers and Revetments.' 2 
Extending Inner Piers. 
Converging Breakwater. 
Channel to Holland and Turning Basin 
at Holland. 
Present Project Dimensions of Channels 
at Turning Basin. 
Widen Bend in Reveted Entrance Channel 
into Lake Macatawa, Dredge Channel in Black River, and Widen 
and Extend Turning Basin. 
THE INLAND ROUTE, MI (See Section 22 of Text) 
Channel 30 feet wide and 5 feet deep 
through Lakes and Rivers with suitable jetties. 
Lock and Dam. 
KENOSHA HARBOR, WI (See Section 23 of Text) 
Parallel piers and 600 feet of breakwater' 2. 
Extending breakwater 200 feet. 
Present project dimensions of entrance channel and basin. 
1892. 
H. Doc. 222, 61st Cong., 2d Sess. 
H. Doc. 1017, 64th Cong., 1st Sess. 
H. Doc. 294, 68th Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 40, 72d Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 73, 74th Cong., 2d Sess. 
H. Doc. 95, 76th Cong., 1st Sess. 
H. Doc. 470, 87th Cong., 2d Sess.' 
H. Doc. 446, 78th Cong., 
2d Sess. 
Annual Report 1873, p. 292 
H. Doc. 1700, 64th Cong., 2d Sess. 
H.R. 5653, 98th Cong., 2d Sess., 
P.L. 98-360 (98 Stat. 405) Sec. 105. 
H. Doc. 446, 78th Cong., 
2d Sess. 
Sec. 107, 1960 River and 
and Harbor Act. 
S. Ex. Doc. 42, 35th Cong., 1st Sess. 
Annual Report 1866, p. 106. 
H. Doc. 272, 51st Cong., 2d Sess., 
and Annual Report 1887, p. 2950. 
Annual Report 1905, p. 2176. 
H. Doc. 588, 69th Cong., 2d Sess. 
Rivers and Harbors Committe 
Doc. 48, 74th Cong., 1st Sess. 
H. Doc. 282, 83rd Cong., 2d Sess. 
H. Doc. 142, 82nd Cong., 1st 
Sess.' 
Chief of Engineers. 
H. Doc. 328, 54th Cong., 2d Sess. 
Annual Report 1897, p. 2772, H. Doc. 
164, 55th Cong., 3d Sess. Annual 
Report, 1899, p. 1817. 
H. Doc. 62, 59th Cong., 2d Sess. and 
Rivers and Harbors Committee Doc. 3, 
59th Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
19, 74th Cong., 1st Sess. 
31-49

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 17, 1950 
Oct. 23, 1962 
Mar. 3, 1881 
Jun. 25, 1910 
Aug. 30, 19352, 14 
Jul. 14, 1960 
Sep. 19, 1890 
Jun. 25, 1910 
Mar. 2, 1919 
Aug. 30, 1936's 
Mar. 2, 1945 
Sep. 3, 1954 
Mar. 7, 1974 
Aug. 5, 1886 
Jul. 13, 1892 
Jun. 13, 1902 
Mar. 2, 1919 
Jul. 3, 1930 
Aug. 30, 19333 
Mar. 21, 1956 
Aug. 30, 1935 
Oct. 23, 1962 
Channel northwesterly from basin. 
Deepen lake approach channel to 27 feet and 800 feet wide; 
deepen approach channel to 26 feet, entrance channel and 
inner basin to 25 feet. 
KEWAUNEE HARBOR, WI (See Section 24 of Text) 
Entrance piers. 
Turning basin. 
North breakwater, remove old north pier, widen and deepen 
entrance channel and turning basin to 20 feet and remove 
outer south shoal. 
Enlarge existing turning basin, extend existing project into 
north basin, and increase depth of north basin to 20 feet 
at a maximum width of 500 feet and eliminate removal of outer shoal. 
KEWEENAW WATERWAY, MI (See Section 25 of Text) 
Acquisition of waterway; for a 16-foot channel of 70-foot 
bottom width, renew canal revetments, reconstruct and extend 
piers at upper entrance to 30-foot depth of water, and at proper 
time for increase of channel depth to 20 feet with bottom width 
of not less than 120 feet (increase in width and depth of channel 
approved Mar. 15, 1898). 
Anchorage basin just within lower entrance about one-half mile 
long, 800 feet wide; a mooring pier on its westerly side 2,000 
feet in length, and for purchase of necessary land. 
Princess Point Cutoff channel. 
General deepening, widening and straightening of channels and 
basins to provide 25-foot depth with additional overdepth at 
at entrances, extend lower entrance breakwater, and necessary 
alteration or replacement of structures due to deepening 
channels. 
KNIFE RIVER HARBOR, MN (See Section 26 of Text) 
Dredging. 
Breakwater and modified channels. 
Construction of measures to correct the design deficiencies 
which results in unsatisfactory entrance and mooring conditions. 
LA POINTE HARBOR, WI (See Section 27 of Text) 
Provides for reconstruction of 73.5 feet of the existing breakwater, 
extending the breakwater 126.24 feet with 5 new steel sheet 
pile cells, harbor dredging and related work. The harbor is 
10 feet deep in the entrance and 8 feet deep in the basin. 
LAKE ST. CLAIR, MI, CHANNELS (See Section 28 of Text) 
Two Dikes. 
Deepening Canal and dredging Channel at Grosse Point. 
Second Canal for downbound vessels. 
21-foot depth in Grosse Pointe Channel for about 5.25 miles. 
25-foot depth through Canals and Channel through Lake St. Clair. 
Removal of Center Dike and widening 
Channel to 700 feet. 
Deepening Channel to 27.5 feet and abandonment of 
Channel above mouth of Southeast bend cutoff Channel. 
LELAND HARBOR, MI (See Section 29 of Text) 
Entrance Channel protected by Piers. 
Outer Breakwater, Anchorage Area. 
Approach Channel and removal of North Pier. 
H. Doc. 750, 80th Cong., 2d Sess. 
H. Doc. 496, 87th Cong., 
2d Sess.' 
Annual Report, 1881, p. 2082 
H. Doc. 324, 60th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 43, 72d 
Cong., 1st Sess. 
S. Doc. 19, 86th Cong., 
1st Sess.' 
H. Ex. Doc. 105 49th Cong., 
2d Sess. and Annual Report 
1887, p. 1977. 
H. Doc 325, 60th Cong., 1st 
Sess. 
H. Doc. 835, 63rd Cong., 2d Sess. 
H. Doc. 55, 73rd Cong., 1st Sess.' 
H. Doc. 686, 77th Cong., 2d Sess. 
and Annual Report for 1949. 
H. Doc. 463, 83d Cong., 2d Sess.' 
Section 107 of the 1960 
River and Harbor Act. 
P.L. 645, 86th Cong., 
as amended. 
Annual Report 1885, p. 2150. 
H. Doc. 297, 51st Cong., 2d Sess. 
H. Doc. 234, 56th Cong., 2d Sess. 
H. Doc. 188, 65th Cong., 1st Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 3, 72nd Cong., 1st Sess. 
S. Doc. 71, 84th. Cong., 1st Sess.' 
Rivers and Harbors Committee 
Doec. 23, 74th Cong., 1st Sess. 
H. Doc. 413, 87th Cong., 2d Sess. 
31-50

TABLE 31-B (Continued) 
DETROIT, MI DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 27, 1965 
Mar. 2, 1945 
Mar. 2, 1867 
Mar. 3, 1899 
Mar. 2, 1907 
Dec. 31, 1970 
Jun. 25, 1910 
Aug. 17, 1966 
Jan. 15, 1965 
Mar. 2, 1867 
Sep. 19, 1890 
Jul. 25, 1912 
Jul. 3, 1920 
Mar. 2, 1945 
Jul. 14, 1960 
Mar. 2, 1907 
Aug. 30, 193517 
Aug. 26, 1937 
Oct. 23, 1962 
Dec. 31, 1968 
(Sec. 107 of 1960 
R & H) 
Jun. 26, 1979 
LEXINGTON HARBOR, MI (See Section 30 of Text) 
Approach Channel and Maneuver Area 
Protected by Breakwaters.' 
LITTLE LAKE HARBOR, MI (See Section 31 of Text) 
12-Foot Deep Channel from Lake Superior into Little Lake 
Breakwaters and Revetments. 
LUDINGTON HARBOR, MI (See Section 32 of Text) 
Entrance Piers. 
Pier Extension Reconstruction and Repairs 
to Existing Structures and Present 
Project Dimensions of Channel. 
Breakwaters, Shore Connections, and 
Removal of Outer Ends of the Two Inner Piers. 
Deepen Channels and Widen Opening between Breakwaters. 
MACKINAC ISLAND HARBOR, MI (See Section 33 of Text) 
Original Breakwater.30 
500-foot extension to East Breakwater. 
MACKINAW CITY HARBOR, MI (See Section 34 of Text) 
Breakwater 430 feet long; slope protection for about 300 feet; 
entrance channel 10 feet deep with minimum width of 100 feet; 
protected anchorage and maneuver area 3.3 acres with depth 
6 to 8 feet. 
MANISTEE HARBOR, MI (See Section 35 of Text) 
Entrance Piers. 
Extending Channel 8,000 feet to connect with Manistee Lake, 
and further Pier extension.) 
Depth of 20 feet in Outer Harbor 570 feet wide to Outer end of 
South Pier 18 feet deep in river, South Breakwater with shore 
connection, and extend North Pier if required. 
23-foot depths in entrance channel and 21-foot depths 
in River Channel. 
Remove old South Revetment, Construct new South Pier 
and Revetment, and widen river entrance Channel. 
Present Project dimensions of Channel through Outer Basin 
and River and Federal participation in cost of replacing 
Maple Street Bridge. 
MANITOWOC HARBOR, WI (See Section 36 of Text) 
Breakwaters. 
Present project dimensions of channel through outer basin, removal 
of old north stub pier, and approach channel to a proposed 
city terminal south of shore end of south breakwater. 
Channel in river. 
Deepen Lake approach to 25 feet by 800 feet wide, deepen outer 
harbor to 25 feet, river channel to 23 feet to 8th St., and 
Upper River Channel to 22 feet to Soo Line R.R. 
Dredge River Channel to 12 feet from Soo Line R.R. 
720 feet upstream 
Construct 765-Foot long stone Breakwater, and rubblemount 
bulkhead; construct 360-foot long entrance Breakwater; 
dredge 16,500 cubic yards for entrance channel. 
H. Doc. 301, 88th Cong., 2d Sess.' 
IH Doc. 446, 78th Cong., 2d Sess.' 
Annual Report 1867, p. 11416 
H. Doc. 273, 54th Cong., 2d Sess. 
and Annual Report 1897, p. 2951 
H. Doc. 62, 59th Cong., 1st Sess. 
and Rivers and Harbors 
Committee Doc. 3, 59th Cong., 
2d Sess.' 6 
H. Doc. 342, 91st Cong., 2d Sess.' 
H. Doc. 646, 56th Cong., 1st Sess. 
Section 107, 1960 River and 
Harbor Act. 
Section 107, 1960 
River and Harbor Act. 
Annual Report 1867, p. 115 
Annual Report 1891, p. 2678 
H. Doc. 599, 62d Cong., 2d Sess. 
S. Doc. 131, 71st Cong., 2d Sess. 
H. Doc. 380, 77th Cong., 1st Sess. 
H. Doc. 358, 86th Cong., 2d Sess. 
H. Doc. 62, 59th Cong., 1st Sess., 
as modified by Rivers and Harbors 
Committee Doc. 3, 59th Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 39, 73d 
Cong., 2d Sess. 
Rivers and Harbors 
Committee Doc. 80, 74th 
Cong., 2d Sess. 
H. Doc. 479, 87th Cong., 
2d Sess. 
Jun 1967 Detailed Project 
Report; Apr. 1982 
Supplement.' 
Sec. 107, 1960 
River and Harbor Act 
31-51

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1867 
Aug. 11, 1888 
Jun. 25, 1910 
Aug. 30, 1935' 
Jul. 11, 1960 
Mar. 3, 1871 
Jun. 13, 1902 
Mar. 4, 1913 
Jul. 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Jul. 14, 1960 
Jun. 27, 1967 
Sec. 107 
Aug. 30, 1852 
Mar. 3, 1883 
Mar. 2, 1907 
Sep. 22, 1922 
Aug. 30, 1935 
Mar. 2, 194518 
Jul. 14, 1960 
Oct. 23, 1962 
Feb. 24, 183519 
Jul. 3, 1920 
Jul. 14, 193221 
Jun. 13, 1902 
Mar. 3, 1925 
Aug. 30, 1935 
Oct. 23, 1962 
MARQUETTE HARBOR, MI (See Section 37 of Text) 
Breakwaters, 2,000 feet long. 
Extending the breakwater 1,000 feet. 
Additional 1,500-foot extension to breakwater and 
and removing a shoal in northerly part of harbor. 
Deepening harbor to 25 feet. 
Deepening harbor to 27 feet. 
MENOMINEE HARBOR AND RIVER, MI AND WI 
(See Section 38 of Text) 
Entrance piers. 
Consolidation of project for harbor and river, and a channel 
18 feet deep. 
Partial restoration of work above bridge which had been eliminated by 
Act of May 3, 1905. 
20-foot depth in channel and 18-foot depth in turning basin. 
21-foot depth in channel and turning basin and enlarge 
turning basin. 
Extend channel 12 feet deep to vicinity of Marinette Yacht Club. 
Deepen existing approach channel to 26 feet, entrance and river channels 
to 24 feet and enlarge turning basin. 
Deepen 1,100 feet of river channel generally north of 
Marinette Corp. facilities to 19 feet. 
MILWAUKEE HARBOR, WI (See Section 39 of Text) 
North pier.' 2 
Inner 7,600 feet of breakwater.' 2 
South pier. Extending north breakwater 1,000 feet. 
Extend north breakwater; a south breakwater; present project 
dimensions of inner entrance channel. 
Dredging a portion of outer harbor to 21-foot depth. 
Dredging river channels to 21-foot depth. 
Deepen South Menominee and Burnham Canals to 21 feet. 
Deepen an approach channel to 30 feet by 800 feet wide and 
300 feet wide through breakwater; deepen entrance channel 
28 feet through piers, outer harbor to 28 feet south of entrance 
channel, and a channel to 27 feet in Milwaukee River to Buffalo St., 
and in Kinnickinnic River to Chicago & North Western Ry. bridges. 
MONROE HARBOR, MI (See Section 40 of Text) 
9-foot channel, protecting Revetments and Piers. 
21-foot channel, dikes and Turning Basin. 20 
Modified Conditions of Local Cooperation 
imposed by Act. of Jul. 3, 1930 
MUSKEGON HARBOR, MI (See Section 41 of Text) 
Piers and Revetments. 
Breakwaters. 
Repairing Revetments around Car Ferry Slip. 
Channel deepening and present project dimensions of channel. 
Piers and Revetments. 
H. Ex. Doc. 56, 39th Cong., 
2d Sess. pts. 1 and,2, and Annual 
Report, 1866, pp. 8 and 77. 
Annual Report, 1889, pp. 272 
and 2021. 
H. Doc. 573, 61st Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 20, 72d Cong., 1st Sess. 
H. Doc. 154, 86th Cong., 1st Sess.' 
Annual Report, 1867, P. 132. 
H. Doc. 419, 56th Cong., 1st Sess. 
H. Doc. 171, 70th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 28, 73d 
Cong., 2d Sess. 
H. Doc. 228, 76th Cong., 1st Sess. 
H. Doc. 112, 86th Cong., 1st Sess. 
Detailed Project Report 
Dec. 1960.' 
S. Doc. 175, 25th Cong., 2d Sess. 
Annual Report 1881, p. 2122. 
Annual Report 1906, p. 1752. (No 
prior survey or estimate affecting 
breakwater extensions.) 
H. Doc. 804, 66th Cong. 2d Sess. 
H. Doc. 289, 72d Cong. 1st Sess. 
S. Doc. 29, 76th Cong., 1st Sess. 
H. Doc. 285, 86th Cong., 2d Sess. 
H. Doc. 134, 87th Cong., 1st Sess.' 
Annual Report 1872, p. 237 
Rivers and Harbors Comm. 
Doc. 22, 71st Cong., 1st Sess. 
Rivers and Harbor Comm. Doc. 
12, .72d Cong., 1st Sess. 45, 
75th Cong., 1st Sess.' 
H. Doc. 104, 56th Cong. 2d Sess. 
H. Doc. 494, 67th Cong. 4th Sess. 
Rivers and Harbor Comm. Doc. 64, 
75th Cong., 1st Sess.' 
H. Doc. 474, 87th Cong., 2d Sess.' 
31-52

TABLE 31-B (Continued) 
DETROIT, MI DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Jun. 25, 1910 
Aug. 26, 1937 
Aug. 2, 1882 
1883 
Aug. 30, 1935 
Mar. 2, 1867 
Mar. 3, 1873 
Jul. 5, 1881 
Jul.13, 1892 
Mar. 25, 1907 
Aug. 18, 1894 
Jun. 13, 1902 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 16, 1984 
Mar. 3, 1879 
Mar. 2, 1945 
Jul. 11, 1870 
Aug. 14, 1876 
Aug. 30, 193523 
Jul. 3, 195824 
Jun. 13, 1902 
Jun. 30, 1948 
NEW BUFFALO HARBOR, MI (See Section 42 of Text) 
Entrance channel 10 feet deep by 80 to 180 feet wide and 850 feet long 
to mouth of Galien River, new no. and so. breakwaters 1,305 and 
740 feet, respectively, deepening inner channel to Galien River to 
8 feet and 80 feet wide and 1,250 feet long. 
ONTONAGON HARBOR, MI (See Section 43 of Text) 
Channel 17 feet deep and 150 feet wide through bar and 
15 feet deep and 100 feet wide between piers, and pier 
maintenance. 
Modified project widths and provide inner basin. 
PENSAUKEE HARBOR, WI (See Section 44 of Text) 
Construction of slab pier 2,500 feet long on the north side of the 
channel and dredging a channel 100 feet wide and 10 feet deep. 
Extending pier to 10-foot contour 
(2,700 feet) and dredging to 10 feet below datum. 
(Datum elevation 580.69 feet) 
Dredging entrance channel 100 feet wide 
and 8 feet deep. 
PENTWATER HARBOR, MI (See Section 45 of Text) 
Piers and revetments, dredging. 
Piers and revetments, dredging. 
Piers and revetments, dredging. 
Piers and revetments, dredging. 
Present project depth of channel. 
PETOSKEY HARBOR, MI (See Section 46 of Text) 
Breakwaters according to larger of two projects. 
Removal of north breakwater and extension of west breakwater 
if cost did not exceed $170,000 
POINT LOOKOUT HARBOR (AU GRES RIVER), MI 
(See Section 47 of Text) 
Breakwater, Anchorage Area, Channel Dredging. 
PORT AUSTIN HARBOR, MI (See Section 48 of Text) 
Breakwater, Anchorage Basin, Channel Dredging. 
Construct a breakwater access for recreation purposes. 
PORTAGE LAKE HARBOR, MI (See Section 49 of Text) 
Entrance Channel 18 feet deep portected by Piers and Revetments. 
PORT SANILAC HARBOR, MI (See Section 50 of Text) 
Entrance Channel 12 feet deep, Anchorage Basin, Breakwater. 
PORT WASHINGTON HARBOR, WI (See Section 51 of Text) 
North pier and south basin.' 2 
North basin. 
North breakwater, removal of 650 feet of north pier, outer 
turning basin, present project dimensions of channel 
and basin and extension of south breakwater. 
Extending and raising of north breakwater and placing 
rubble along sides; removing 456 feet of south breakwater 
and dredging in outer basin. 
PORT WING HARBOR, WI (See Section 52 of Text) 
Construction of parallel piers and dredging. 
Dredging inner channels and abandonment of certain revetments 
and channels. 
H. Doc. 474, 87th Cong. 2d Sess. 
H. Doc. 602, 61st Cong., 2d Sess. 
S. Committee print, 74th 
Cong., 2d Sess. 
H. Doc. No. 153, 42d Cong., 
3d Sess. 
R & H Act Aug. 2, 1882 
Modified 
H. Doc. No. 478, 
74th Cong., 2d Sess.' 
H. Ex. Doc. 70, 39th Cong., 2d Sess. 
H. Ex. Doc. 70, 39th Cong., 2d Sess. 
H. Ex. Doc. 70, 39th Cong., 2d Sess. 
H. Ex. Doc. 70, 39th Cong., 2d Sess. 
H. Doc. 181, 39th Cong., 2d Sess.' 
Annual Report 1890, p. 2673 
Annual Report 1895, p. 2819 
Annual Report 1896, p. 2722 
H. Doc. 446, 78th Cong., 2d Sess. 
H. Doc. 446, 78th Cong., 2d Sess. 
H.R. 5653, 98th Cong., 2d Sess., 
P.L. 98-360 (98 Stat. 405) Sec. 106. 
Annual Report 1879, p. 163422 
H. Doc. 446, 78th Cong., 2d Sess. 
H. Ex. Doc. 28, 41st Cong., 2d Sess. 
and Annual Report, 1879, p. 119. 
Annual Report, 1876, pt. 2, p. X3
79 
H. Doc. 168, 72d Cong., 
1st Sess. and Rivers and Harbors 
Committee Doc. 41, 74th Cong., 
1st Sess. 
H. Doc. 446, 83d Cong. 2d Sess.' 
H. Doc. 114, 56th Cong., 1st Sess. 
H. Doc. 668, 80th Cong., 2d Sess. 
31-53

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 5, 1977 
Mar. 2, 1907 
Aug. 26, 1937 
Mar. 2, 1945 
Aug. 8, 1917 
Aug. 30, 19352,26,27 
Jul. 3, 19582 
Oct. 23, 19622 
Jun. 25, 1910 
Jul. 3, 1930 
Aug. 26, 1937 
Jun. 20, 1938 
Sep. 3, 1954 
Oct. 23, 1962 
Oct. 27, 1965 
Jul. 13, 1892 
Jul. 8, 1930 
Mar. 2, 1945 
Jul. 24, 1946 
Mar. 21, 1956 
Mar. 3, 1875 
Jun. 14, 1880 
Mar. 3, 1899 
Deauthorization of 50 feet of entrance channel widening. 
RACINE HARBOR, WI (See Section 53 of Text) 
Breakwaters. 
Remove shoals lakeward of harbor entrance, enlarge 
19-foot channel through outer basin and 19-foot channel in 
river. 
Present project dimensions of channel through outer basin 
and in river. 
ROUGE RIVER, MI (See Section 54 of Text) 
21-foot channel via the Shortcut Canal. 
25-foot channel at mouth of Old Channel, 1,425 feet long and 
adjacent to latter, and 21-foot channel extending from junction 
of Old Channel and Shortcut Canal into Old Channel to Detroit, 
Toledo & Ironton R.R. Bridge. 
Old Channel; 100 feet wide from Peerless Cement Corp. to 
Junction with Shortcut Canal widened to 150 feet.at 2 bends. 
25-foot channel over modified limits from 
Detroit River to Jefferson Ave. (via Shortcut Canal). 
SAGINAW RIVER, MI (See Section 55 of Text) 
Channel 200 feet wide, with depth of 18.5 
feet in Bay and 16.5 feet in River. 
Project Depth of 18.5 feet extended up River 
to Saginaw 
Turning Basin. 
Present Project Channel Dimensions from Bay to 
Sixth Street Bridge in Saginaw 
New Channel in Bay, 350 feet wide and 24 feet deep from 
24-foot contour to River Mouth, Project Depth of 24 feet 
in River Channel up to Detroit & Mackinac Railway Bridge, 
Project Depth of 22 feet in River Channel up to Sixth Street 
Bridge, Turning Basins at Essexville and Carrollton, and 
elimination' of present Channel in Bay. 
Deepen Bay Channel, Deepen River Channel to Detroit & 
Mackinac Bridge, Extend 22-foot Project above 6th St. 
Bridge, Deepen Essexville Turning Basin, and Construct 
2 new Turning Basins.3 
Deepen River Channel to 25 feet, from Detroit & Mackinac Bridge 
to New York Central Railroad Bridge. 
ST. CLAIR RIVER, MI (See Section 56 of Text) 
20-foot Channel in the River. 
Deepen Channel to 25 and 26 feet, and 
Compensating Works. 
Widening Channel at Southeast Bend to 700 feet. 
Widen and deepen Southeast Bend and improve Outlet 
of North Channel, St. Clair River. 
Deepen and further improve Channels in St. Clair River 
between limits of 27.1 to 30 feet to provide safe navigation by 
vessels with drafts of 25.5 feet. A cutoff Channel in Canada of 
Southeast Bend and abandon old Southeast Bend Channels. 
ST. JOSPEH HARBOR, MI (See Section 57 of Text) 
Interior Revetments. 28 
Benton Harbor Canal. 28 
Present Project dimensions of Piers 
and a Turning Basin. 
H. Doc. 62, 59th Cong., 1st Sess., 
and Annual Report 1909, p. 1973. 
Rivers and Harbors 
Committee Doc. 46, 75th Cong. 
1st Sess. 
H. Doc. 816, 77th Cong., 2d Sess., 
and H. Doc. 255, 78th Cong., 
1st Sess.' 
H. Doc. 1063, 64th Cong., 2d Sess. 25 
H. Doc. 125, 85th Cong., 1st Sess. 
H. Doc. 509, 87th Cong., 2d Sess.' 
H. Doc. 740, 61st Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 30, 71st Cng. 2d Sess. 
Rivers and Harbors Comm. Doc. 21, 
75th Cong., 1st Sess. 
H. Doc. 576, 75th Cong., 3d Sess. 
H. Doc. 500, 83rd Cong., 2d Sess. 
H. Doc. 554, 87th Cong., 2d Sess. 
H. Doc. 240, 89th Cong., 1st Sess.' 
H. Doc. 207, 51st Cong., 2d Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
H. Doc. 309, 77th Cong., 1st Sess. 
H. Doc. 335, 80th Cong., 1st Sess. 
S. Doc. 71, 84th Cong., 1st Sess. 
H. Ex. Doc. 160, 43rd Cong., 
2d Sess., and Annual Report 1875, 
pt. 1, p. 162 
Annual Report 1880, pp. 2030, 2031 
and 2049, 2055. 
H. Doc. 307, 55th Cong., 2d Sess., 
and Annual Report 1898, p. 2496. 
31-54

TABLE 31-B (Continued) 
DETROIT, MI DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935 
Jun. 2, 1937 
Mar. 2, 1945 
Jul. 3, 1958 
Jul. 11, 1870 
Aug. 5, 1886 
Jul. 13, 1892 
Jun. 13, 1902 
Jun. 13, 1902 
Mar. 3, 1907 
Mar. 3, 1909 
Jul. 25, 1912 
Mar. 4, 1915 
Sep. 22, 1922 
Jan. 21, 1927 
Jul. 3, 1930 
Jun. 26, 19349 
Aug. 30, 1935 
Mar. 7, 1942 
Jun. 15, 1943 
Mar. 2, 1945 
Jul. 24, 1946 
Mar. 21, 1956 
Jul. 9, 1956 
Jun. 3, 1896 
Mar. 2, 1907 
Jun. 25, 1910 
Present project dimensions of 
Paw Paw River. 
Abandon easterly 1,000 feet of Channel above West Line of 9th St. 
Turning Basin above mouth of Morrison Channel 
and eliminate Turning Basin near mouth of Paw Paw River. 
Maintenance of Turning Basin near mouth of Paw Paw River. 
ST. MARYS RIVER, MI (See Section 58 of Text) 
Weitzel Lock (Replaced in 1943 by MacArthur Lock), 
widen and deepen existing State Channel. 28 
Poe Lock.' 
Dredging through shoals above falls and shoals below falls between lower 
end of Canal and upper entrance Channel into Lake Nicolet (formerly 
Hay Lake). 
Enlarging the Old Channel. 
Lake Nicolet and Neebish Channels work in that section of River below 
Locks. 
David Lock Second Canal, and Emergency Dam. 
Lease of Waterpower at Falls. Lease entered into with Michigan Northern 
Power Co. provided for construction of remedial and compensating works. 
Fourth Lock (Renamed 'Sabin' Lock in 1943). 
Deepen Tailrace of Power Plant. 
Widen upper approach to Canals through Vidal Shoals, extend anchorage 
and maneuver area below Locks. 
Remove Round Island, middle ground extension of Northwest Canal 
Pier, and widen Channels Middle Neebish Route. 
Deepen Channels throughout downbound Route. 
Operation and Care of Canal and Locks provided from War 
Department Appropriations for Rivers and Harbors. 
Widen Brush Point Turn and Channel from Brush Point 
to Point Louise. 
Construct new (MacArthur) Lock on site of former Weitzel Lock, 
deepen approach Channels to 27 feet, and reconstruct approach Piers. 
Name 'MacArthur' Lock and changed name of 'Fourth' 
Lock to 'Sabin' Lock. 
Remove Bridge Island and construct new Hydroelectric 
Power Plant. 
Replace Poe Lock at St. Marys Falls Canal with a new structure 
800 feet long, 100 feet wide and 32 feet deep with necessary 
construction of Nose and Center Piers, and widen and deepen Channel 
across Point Iroquois Shoals and in Lake Nicolet to provide wider 
anchorage and maneuver areas in St. Marys River. 
Deepen to provide a Project Safe Draft of 25.5 feet over full width to 
downbound and 2-way Channels (including anchorage areas) 
and over Westerly 300-foot width of upbound Middle Neebish Channel, 
when levels of Lake Superior and Huron are at their respective 
low-water datum. 
Repeal Authorization of Bridge as a part of Project, authorize 
alteration with cost to be apportioned by Sec. 6, Truman Hobbs Act, 
June 21, 1940. 
SAUGATUCK HARBOR AND KALAMAZOO RIVER, MI 
(See Section 59 of Text) 
Entrance Channel, Piers and Revetments. 
Deepening entrance to 16 feet. 
Deepening Channel in River to 14 feet. 
Rivers and Harbors Comm. Doc. 52, 
74th Cong., 1st Sess. 
H. Doc. 129, 76th Cong., 1st Sess. 
S. Doc. 95, 84th Cong., 2d Sess.' 
Report by Maj. O. M. Poe, Corps of 
Engineers, not published. 
H. Ex. Doc. 72, 49th Cong., 2d Sess. 
H. Ex. Doc. 207, 51st Cong., 2d Sess. 
and Annual Report 1891, p. 2810 
H. Doc. 138, 56th Cong., 2d Sess., 
and 215, 58th Cong., 3d Sess. 
H. Doc. 128, 56th Cong., 2d Sess. 
H. Doc. 333, 59th Cong., 2d Sess. 
(Plan 3) 
H. Doc. 65, 62d Cong., 1st Sess. 
District Engineer Report, 
Oct. 29, 1920. 
H. Doc. 270, 69th Cong., 1st Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
River and Harbor Comm. Doc. 53, 
74th Cong., 1st Sess. 
H. Doc. 218, 77th Cong., 1st Sess. 
H. Doc. 679, 78th Cong., 2d Sess. 
and H. Doc. 339, 77th Cong., 1st Sess. 
H. Doc. 335, 80th Cong., 1st Sess. 
S. Doc. 71, 84th Cong., 1st Sess.' 
None 
H. Doc. 912, 54th Cong., 1st Sess. 
Annual Report 1896, Vol. 2. 
Pt. 5, p. 2739 
Annual Report 1907, p. 6416 
H. Doc. 635, 61st Cong., 2d Sess. 
31-55

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 3, 1958 
Mar. 2, 1907 
Jan. 21, 1927 
Aug. 30, 1935 
Sep. 3, 1954 
Aug. 11, 1888 
Mar. 3, 1905 
Aug. 30, 1935 
Mar. 3, 1873 
Jul. 13, 1892 
Aug. 13, 1968 
Mar. 3, 1871 
Mar. 2, 1907 
Aug. 30, 1935 
Jul. 3, 1958 
Mar. 2, 1867 
Mar. 3, 1873 
Jul. 5, 1884 
Jul. 13, 1892 
Mar. 2, 1907 
Apr. 7, 1966 
Jul. 3, 1958 
Aug. 18, 1941 
SAXON HARBOR, WI (See Section 60 of Text) 
Provides for east and west breakwaters, an outer channel 10 feet deep, 
an inner basin and side channel 8 feet deep, and diversion of 
Oronto Creek to Parkers Creek by three short reaches of 
channel excavation and a levee. 
SHEBOYGAN HARBOR, WI (See Section 61 of Text) 
North breakwater. 
Preserving south pier as part of project, providing turning basin, and 
and elimination of proposed south breakwaters. 
Present project dimensions of channel. 
Widen and deepen outer harbor entrance channel to 450 feet, widen 
and deepen river channel from present project limit to north side of 
Jefferson Ave. 
SOUTH HAVEN HARBOR, MI (See Section 62 of Text) 
Channel from Inner End of Piers to Highway Bridge.' 2 
Present dimensions of Piers and for a Turning Basin. 
Present Project dimensions of Channel and Turning Basin. 
STURGEON BAY AND LAKE MICHIGAN SHIP CANAL, WI 
(See Section 63 of Text) 
Breakwaters. 12 
Acquisition of the canal. 
TAWAS BAY, MI (See Section 64 of Text) 
1,750 foot breakwater, 12 foot deep entrance Channel, 
10-foot deep anchorage area. 
TWO RIVERS HARBOR, WI (See Section 65 of Text) 
South pier, 750 feet of north pier, and about 44 feet of 
north revetment.' 12 
Remainder of north pier and stilling basin. 
Deepening entrance channel and inner basin to 18 feet. 
Extend existing project in West Twin River to 18 feet deep 
and in East Twin River to 10 feet deep to 22d Street Bridge. 
WHITE LAKE HARBOR, MI (See Section 66 of Text) 
New Channel, with Piers and Revetments. 
New Channel, with Piers and Revetments. 
New Channel, with Piers and Revetments. 
New Channel, with Piers and Revetments. 
Present Project Depth of Channel. 
KAWKAWLIN RIVER, MI (See Section 74 of Text) 
Deepening River Channel, altering Railway Bridge, 
Riprapping portions of Channel bottom, and utility relocations. 
SAGINAW RIVER, MI FLOOD CONTROL 
(See Section 75 of Text) 
Floor Control improvements to Saginaw River and its tributaries 
including Tittabawassee, Shiawassee, Flint, and Cass Rivers. 
SEBEWAING, SEBEWAING RIVER, MI 
(See Section 76 of Text) 
Enlarging present Channel of Sebewaing River, altering Railroad and 
Highway Bridges, removal of Dike. 
River and Harbor Act 
H. Doc. 169, 85th Cong., 1st Sess.,' 
Annual Report for 1965, p. 1025. 
H. Doc. 62, 59th Cong. 1st Sess. 
H. Doc. 475, 68th Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 47, 74th Cong., 1st Sess. 
H. Doc. 554, 82d Cong., 2d Sess.' 
No Prior Survey or Estimate. 
H. Doc. 119, 58th Cong., 2d Sess. 
Rivers and Harbors Comm. Doc. 9, 
73d Cong., 1st Sess.' and 
unpublished review Report of Chief of 
Engineers, Dated Dec. 21, 1934. 
H. Ex. Doc. 34, 42d Cong., 2d Sess. 
Annual Report, 1872, p. 171. 
H. Ex. Doc. 106, 49th Cong., 2d Sess. 
H. Doc. 189, 90th Cong., 1st Sess. 
Annual Report, 1871, p. 123 (as 
modified by Chief of Engineers, 
Feb. 27, 1897). 
H. Doc. 730, 59th Cong., 1st Sess. 
Modification of Plan A. 
Rivers and Harbors Committee 
Doc. 25, 73d Cong., 2d Sess. 
H. Doc. 362, 84th Cong., 2d Sess.' 
Unpublished Survey Report of 1868. 
Unpublished Survey Report of 1868. 
Unpublished Survey Report of 1868. 
No Prior Survey or Estimate. 29 
Section 205, 1948 Flood Control Act. 
H. Doc. 346, 84th Cong., 2d Sess.' 
H. Doc. 286, 76th Cong., Ist Sess.' 
31-56

TABLE 31-B (Continued) 
DETROIT, MI DISTRICT 
AUTHORIZING LEGISLATION 
'Contains latest published map. 
2Including Emergency Relief Administration Work authorized 
May 28, 1935, 
3Included in Public Works Administration Program 
September 6, 1933. 
4This modification deauthorized August 5, 1977 under Section 
12, Public Law 93-251. 
5Administrative Act, Section 4. 
6Public Law 568, 82d Congress. 
'Public Law 388, 87th Congress. 
8This portion inactive. 
9Permanent Appropriations Repeal Act. 
'�Transfer completed June 1962. 
"Amended 1868, 1879, 1892. 
'2Completed under previous project. 
'3Included in Public Works Administration Program 
January 3, 1934. 
4Inactive portion; removal of 200 linear feet of north pier, 
widening inner 200 feet of channel through outer basin, and closing 
gap in north shore connection of breakwater. 
'SLatest published map is in Annual Report 1914, p. 2974. 
16Latest published map in Annual Report 1914, p. 2914. 
"'Superceded by Act of October 23, 1962. 
'Uncompleted portion was deauthorized in 1977 (dredging 
Milwaukee River from Buffalo St. Bridge to North Humboldt Ave. 
Bridge). 
19Modified by Act of June 10, 1872. 
20Riprapping of protecting dikes portion of project is inactive. 
21War Department Appropriations Act. 
22Latest published map is in House Document 588, 64th Cong., 
1st Sess. 
23Work recommended in H. Doc. 588, 64th Cong., 1st Sess. 
24Deauthorized in 1977. 
25Contains latest published maps. See also map with Rivers and 
Harbors Committee Doc. 19, 72d Cong., 1st Sess. 
26Except for dredging 25-foot channel to 1,150 feet upstream of 
mouth in old channel, work authorized in this Act is considered 
inactive. 
27This modification deauthorized August 5, 1977 under Section 
12, Public Law 93-251. 
28 Completed under previous projects. Public Law 130, 75th 
Cong., 1st Sess. 
29Latest published map is in H. Doc. 2053, 64th Cong., 
2d Sess. 
30Project complete except for Work Authorized by River and 
Harbor Act of 1950. 
31-57

TABLE 31-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
FEATURES OF EXISTING PROJECT 
Project 
Datum Planes 
Length Miles Used by Above Mean 
of from Upbound Water Level 
Channel Mouth or Down- Project Project at Father 
of bound Width Depth Point,Quebec Year 
Name of Channel (Feet) River Vessels (Feet) (Feet) (Feet) Complete 
DETROIT RIVER, MI (SEE SECTION 11 OF TEXT) 
Channel North of Belle Isle 1,2 
Channel at Head of Detroit River 
Miscellaneous Shoals and Obstructions 
Belle Isle to Fighting Island Channel 
Fighting Island Channel 
Ballards Reef Channel North of Junction 
with Livingstone Channel 
Livingstone Channel Upper 
Livingstone Channel Lower: 
CS 260+00 to 368+87 
CS 368+87 to 492+00 
East Outer Channel 
Misc., Shoals and Obstructions, 
Detroit River to Pelee Passage 
Pelee Passage Shoal 
Amherstburg Channel: 
Upper Section, Ballards Reef Channel 
Middle Section 
Lower Section, Hackett Range 
West Outer Channel 
Trenton Channel: 
Wyandotte Reach 
Trenton Reach (Upper) 
Trenton Reach (Lower) 
Grosse Ile Shoal 
.30 
38,800 32 
44,500 25 
Both 
Both 
Both 
24,800 17 Both 
12,200 12 Both 
26,000 10 Down 
10,887 
12,313 
42,000 
5 Down 
Both 
Both 
- - Both 
- - Both 
6,500 
12,000 
24,000 
21,000 
31,500 
5,100 
600 
600 
10 
17 
14 
14 
Up. 
Up 
Up 
Down 
Local 
Local 
Local 
Local 
200 
800 
800 
600 
21.0 571.3 
28.5 571.5-570.9 
28.5 570.9-570.3 
28.5 
28.5 
569.8 
569.8 
450 27.7 569.8-568.6 
450,800 
800-1,200 
1,200 
29.0 
29.0 
28.5 
568.6 
568.6 
568.6 
- 28.5-29.53 568.6 
- 29.5 568.6 
600 
600 
6000 
800 
300 
300 
250-300 
27.5 
21.27.54 
21.28.55 
22.0 
27.0 
28.0 
28.0 
20.0 
569.8-569.5 
569.5-568.9 
568.9-568.6 
568.6 
569.9-569.7 
569.7-569.6 
569.6-568.8 
569.8 
ST. CLAIR RIVER MI (SEE SECTION 56 OF TEXT) 
Channel at Foot of Lake Huron 
Channel North of Blue Water Bridge 
Port Huron to Stag Island 
Widening at Upper and Lower 
Ends of Stag Island 
St. Clair to Russel Island 
Russel Island to Southeast Bend 
Southeast Bend CS 324+00 to 250+00 
Cutoff Channel 
North Channel Outlet 
26,500 44 Both 
4,100 39 Both 
38,000 
37,600 
77,000 
20,600 
7,400 
30,300 
8,000 
39 
31 
24 
11 
5 
Both 
Both 
Both 
Both 
Both 
Both 
Small 
Craft 
800 
800 
800 
900-1,000 
1,000 
700-1,000 
700 
700 
100 
30.0 576.8-576.5 
30.0 576.4-576.1 
30.0 
27.4 
27.3 
17.2 
27.1 
27.1 
10.0 
576.4-576.1 
574.9-573.8 
573.8-572.4 
572.4-572.1 
573.1-572.0 
572.1-571.7 
571.7 
'This is a Side Channel. 
2Extends from Deep Water Near Windmill Point to a Point Opposite 
Fairview Slip, about 3,000 Feet. 
3Project Depth 29.5 feet over Rock Shoals and 28.5 feet over 
other than Rock Shoals. 
4Project Depth 21 feet in Easterly 300-foot width of Channel 
and 27.5 feet in Westerly 300-foot width 
'Project Depth 21 feet in Easterly 300-foot width of Channel 
and 28.5 feet in Westerly 300-foot width. 
6Project Complete Except for Work Authorized by River and 
Harbor Act of 1950. 
31-58 
1964 
1964 
1964 
1962 
1963 
1964 
1961 
1961 
1964 
1962 
1964 
1960 
1960 
1960 
1929 
19646 
1964 
1941 
1904 
1961 
1962 
1961 
1962 
1962 
1962 
1962 
1962 
1962

TABLE 31-D 
DETROIT, MI DISTRICT 
ST. MARYS RIVER, MI: EXISTING PROJECT 
(SEE SECTION 58 OF TEXT) 
Lock Davis Sabin MacArthur New Poe 
Miles Above Mouth 47 47 47 47 
Clear Width of Chamber Feet 80 80 80 110 
Length Between Gate Quoins Feet 1,350 1,350 800 1,200 
Lifts Feet 21.7 21.7 21.7 21.7 
Depth Over Upper Breast Walls' Feet 24.3 24.3 31 32 
Depth Over Lower Breast Walls' Feet 23.1 23.1 31 32 
Foundation Rock Rock Rock Rock 
Type of Construction Concrete Concrete Concrete Concrete 
Estimated Cost $6,200,0002 $3,275,0003 $12,909,440 $39,000,000 
Actual Cost $2,200,0005 $1,750,0006 $12,718,8064, 7 $34,813,066 
Completed (Open to Commerce) Oct. 21, 1914 Sep. 18, 1919 Jul. 11, 1943 Jun. 26, 1969 
Emergency Dam for South Canal North Canal 
Miles Above Mouth 47 47 
Estimated Cost -9 $300,000 
Type Steel Stoplogs Recessed Steel Stoplogs Recessed 
Into Lock Masonry Into Lock Masonry 
Cost Completed -9 $169,2248 
Year Completed 1943 1922 (Modified 1963) 
'At low water datum 599.5 above and 577.8 below. 
2Includes Cost of North Canal. 
3Includes cost of canal excavations to provide necessary approaches 
to lock, canal walls, piers, and emergency dam, $662, 
919. 
4Excludes cost of deepening and enlarging South Canal, 
$1,653,378. 
SExcludes cost of North Canal, $2,572, 611. 
Note: Limiting draft to locks is determined by depth over breast walls. 
6Excludes cost of canal excavations to provide necessary approaches 
to lock, canal walls, piers, and emergency dam, 
$662,919. 
7Excluding cost of lower guard gates which were never 
installed. 
8Including engineering office, and inspection. 
9Not separable from cost of locks. 
31-59

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
FOX RIVER, WI: LOCKS AND DAMS 
(SEE SECTION 13 OF TEXT) 
Depth At 
Normal Pool 
Miles Avail- Lower 
from Dis- Clear able Breast Miter Character Kind Year 
Green Nearest tance Width Length Lift Wall' Sill of of Type of Com- 
Name of Lock and Dam Bay Town (miles) (feet) (feet) (feet) (feet) (feet) Foundation Dam Construction plete C 
DePere lock 2 
DePere dam2 
Little Kaukauna lock 2 
Little Kaukauna dam2 
Rapide Croche lock 2 
Rapide Croche Dam 2 
Kaukauna fifth lock 2 
Kaukauna fourth lock2 
Kaukauna third lock 2 
Kaukauna second lock 2 
Kaukauna first lock2 
w Kaukauna Dam2 
- Kaukauna guard lock 
Little Chute combined lock: 
Lower 
Upper 
Little Chute second lock2 
Little Chute first (guard) lock' 
Little Chute Dam2 
Cedars lock 2 
Cedars Dam 2 
Appleton fourth lock 2 
Appleton lower dam2 
Appleton third lock 2 
Appleton second lock2 
Appleton first lock 2 
Appleton upper dam 
Menasha lock 2 
Menasha Dam2 
7.1 DePere 
7.2 DePere 
13.0 DePere 
13.1 DePere 
19.2 Wrightstown 
19.3 Wrightstown 
22.8 Kaukauna 
23.1 Kaukauna 
23.3 Kaukauna 
23.4 Kaukauna 
23.6 Kaukauna 
24.0 Kaukauna 
24.0 Kaukauna 
24.4 Little Chute 
25.4 Little Chute 
26.4 Little Chute 
26.5 Little Chute 
26.6 Little Chute 
27.3 Little Chute 
27.4 Little Chute 
30.7 Appleton 
30.9 Appleton 
31.3 Appleton 
31.6 Appleton 
31.9 Appleton 
32.2 Appleton 
37.0 Menasha 
37.8 Menasha 
6622 
1
1
1
I
1 
Actual 
:ost 
36.0 146.0 8.9 10.3 12.0 Rock - Concrete 1936 $229,308 
- - - - - Rock Fixed3 4 Concrete 1929 209,536 
36.0 146.0 7.2 8.0 9.5 Clay - Concrete 1938 362,427 
S - - - - Clay and gravel Fixed3 4 Piers and concrete 1926 179,398 
36.0 146.0 8.3 8.8 9.3 Rock - Concrete 1934 228,738 
- - - - - Rock Fixed3 4 Concrete 1930 118,975 
35.6 144.0 9.1 6.7 9.3 Rock - Composite 1898 13,3105 
36.6 144.1 10.2 6.9 6.0 Rock - Stone masonry 1879 37,536 
30.6 144.0 10.2 6.9 6.3 Rock - Stone masonry 1879 39,948 
35.0 144.0 9.6 6.0 6.0 Rock - Stone masonry 1903 24,313 
35.1 144.4 11.0 6.9 6.0 Rock - Stone masonry 1883 38,704 
- - - - - Rock Fixed3 4 Concrete 1931 123,763 
40.0 - - 9.4 - Rock - Stone masonry 1891 12,630 
35.4 146.5 10.9 6.0 8.6 Rock 
36.3 144.1 10.6 7.6 6.0 Hardpan 
35.0 144.2 13.8 8.0 6.1 Rock 
35.4 - - 6.6 - Rock 
- - - - - Rock 
35.0 144.0 9.8 6.8 7.3 Rock 
- - - - - Rock 
35.0 144.0 7.6 8.1 7.9 Rock 
- - - - - Rock 
35.0 144.0 8.7 6.0 8.6 Rock 
35.1 144.6 9.6 6.9 6.0 Clay 
35.0 144.7 10.0 6.6 6.0 Rock 
- - - - - Rock 
35.4 144.0 8.5 7.2 8.0 Clay 
- - - - - Hardpan 
- Stone masonry 
- Stone masonry 
- Stone masonry 
- Stone masonry 
Fixed 3 4 Concrete 
- Stone masonry 
Fixed3 4 Concrete 
- Stone masonry 
Fixed3 4 Concrete 
- Stone masonry 
- Stone masonry 
- Stone masonry 
Fixed3 Concrete 
- Composite 
Fixed3 Concrete 
1879 102,304 
1879 
1881 48,555 
1904 7,8175 
1932 82,554 
1888 34,972 
1933 84,973 
1907 40,893 
1934 73,903 
1900 32,238 
1901 22,940 
1884 36,004 
1940 151,558 
1899 19,3265 
1937 84,686 
'Depth shown is on breast wall, which is controlling depth for 
upper pool. 
2Original structure built prior to assumption of control by 
United States on Sep. 18, 1872. 
3Provided with sluices. 
4Flash boards used. 
sPartially rebuilt. 
TABLE 31-E

TABLE 31-F 
DETROIT, MI DISTRICT 
RECONNAISSANCE & CONDITION SURVEYS 
Name of Project Date Survey Conducted 
Algoma Harbor, WI 
Alpena Harbor, MI 
Au Sable Harbor, MI 
Bayfield Harbor, MI 
Bayport Harbor, MI 
Belle River, MI 
Big Bay Harbor, MI 
Black River (P.H.) MI 
Caseville Harbor, MI 
Grand Marais, MI 
Greilickville Harbor, MI 
(formerly Traverse City Harbor, MI) 
Grays Reef, MI 
Lac LaBelle Harbor, MI 
Les Cheneaux Island Channels, MI 
Manistique Harbor, MI 
Pine River, MI 
Presque Isle Harbor, MI 
Sebewaing River, MI 
St. James Harbor, MI 
Two Harbors, MN 
Whitefish Point, MI 
July 1986 
June 1986 
July 1986 
June 1986 
February 1986 
April 1986 
June 1986 
July 1986 
June 1986 
April 1986 
October 1985 
June 1986 
October 1985 
September 1986 
May 1986 
April 1986 
June 1986 
June 1986 
July 1986 
October 1985 
May 1986 
31-61

TABLE 31-G 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation & 
Project Report for Construction Maintenance 
Alpena Harbor, MI 
Algoma Harbor, WI 
Au Sable Harbor, MI 
Bayfield Harbor, WI 
Bayport Harbor, MI 
Belle River, MI 
Beaver Bay, MN 
Big Bay Harbor, MI 
Black River (Alcona Co), MI 
Black River (P.H.), MI 
Caseville Harbor, MI 
Cedar River Harbor, MI 
Chnls. in the Straits of Mackinac, MI 
Chippewa Harbor, Isle Royale, MI 
Eagle Harbor, MI 
Forestville, MI 
Grand Marais Harbor, MI 
Grand Traverse Harbor, MI 
Grays Reef Passage, MI 
Greilickville Harbor, MI 
(Formerly Traverse City Harbor, MI) 
Lac La Belle Harbor, MI 
Les Cheneaux Islands Channels, MI 
Little Bay DeNoc, Gladstone Harbor, MI 
Lutsen Harbor, MN 
Manistique Harbor, MI 
Northport Harbor, MI 
Oconto Harbor, WI 
Pine River, MI 
Presque Isle Harbor, MI 
St. James, Beaver Island, MI 
St. Joseph River, MI 
Sebewaing River, MI 
Two Harbors, MN 
Washington Island, WI 
Whitefish Point, MI 
'Includes $18,889 for previous projects. 
2Includes $92,774 for previous projects. 
3Includes $114,786 for previous projects. 
4Excludes $56,500 contributed funds. 
5Includes $85,849 for previous projects and $349,921 
contributed funds. 
6Includes $12,008 for maintenance previous projects. 
7Excludes $27,800 for previous projects. 
"Includes $3,955 for previous projects. 
9Includes $84,569 for previous projects. 
'0Includes $8,161 for previous projects. 
"Excludes contributed funds of $7,500. 
'2Includes $48,404 National Industrial Recovery Act for 
new work funds. 
31-62 
1985 
1981 
1985 
1979 
1975 
1980 
1982 
1984 
1907 
1985 
1981 
1982 
1984 
1959 
1985 
1969 
1980 
1985 
1970 
1976 
1985 
1980 
1966 
1982 
1985 
1985 
1980 
1985 
1957 
1975 
1982 
1984 
1950 
1981 
337,394' 
205,0102 
209,7763 
183,855 
93,597 
24,301 
293,000 
390,4334 
830,1655 
587,314 
215,000 
2,832,629 
125,629 
205,1647 
1,055,871 
266,037 
190,521 
366,579 
269,270 
399,478 
332,832 
357,000 
1,299,3558 
130,7549 
13,649 
1,252,192 
49,17111 
54,555 
35,573 
4,170,71012 
62,838 
771,639 
920,222 
913,660 
2,474,814 
75,759 
54,417 
73,503 
2,818 
1,014,671 
509,4106 
109,194 
145,318 
8.871 
77,862 
1,687,290 
1,574,653 
657,856 
122,782 
474,761 
293,778 
64,869 
2,183,185 
1,103,94110 
32,675 
804,838 
55,388 
19,185 
2,289,433 
1,905,193 
67,084 
224,659

TABLE 31-H 
DETROIT, MI DISTRICT 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Grand River, Grandville, MI' 1966 -- 
Grand River, Lansing, MI 1971 7,300 
Kalamazoo River (Battle Creek) MI2 1975 4,471,235 
Kalamazoo River (Kalamazoo) MI 1975 421,466 
Mount Clemens, Clinton River, MI3 1953 1,136,0084 
Upper River Rouge, MIs 1968 7,935 
Red Run Drain-Lower Clinton River, MI 1983 3,823,000 
River Rouge, MI 1981 31,960,332 
'Awaiting Appropriation of Funds. 4Includes $202,996 Contributed Funds. 
2Includes $108,335 Contributed Funds. SPlanning indefinitely suspended due to lack of local 
'Completed. cooperation. 
TABLE 31-I DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Black River Harbor, MI 1976 Nov. 1977 0 0 
(Aug. 30, 1935 R&H Act) 
Detroit River, Trenton Chnl., MI 1976 Aug. 1977 0 0 
(May 17, 1950 R&H Act) 
Grand Haven Harbor, MI 1976 Nov. 1977 0 0 
(Mar. 2, 1945 R&H Act) 
Grand River at Grandville, MI 1966 Nov. 1977 0 0 
(Oct. 27, 1965 Flood Control Act) 
Kewaunee River, WI 1976 Aug. 1977 0 0 
(1960 R&H Act) 
Lansing, (Grand River), MI 1971 Jun. 1981 7,000 0 
(Jul. 3, 1958 Flood Control Act) 
Pentwater Harbor, MI 1976 Nov. 1977 0 0 
(Jul. 13, 1892 R&H Act) 
Rogers City Harbor, MI 1926 Aug. 1977 5,892 0 
(Jun. 25, 1910 R&H Act) 
Rouge River, MI 1976 Aug. 1977 22,000 0 
(Oct. 23, 1962 R&H Act) 
Rouge River, MI 1976 Aug. 1977 12,000 0 
(Jul. 3, 1958 R&H Act) 
Rouge River, MI 1976 Aug. 1977 0 O 
(Aug. 30, 1935 R&H Act) 
St. Clair River Compensating Works, MI 1976 Aug. 1977 0 O 
(Jul. 3, 1930 R&H Act) 
South Milwaukee Harbor, WI 1906 Aug. 1977 0 0 
(1836 Flood Control Act) 
St. Marys River (MacArthur Lock Guard 1977 Oct. 1978 0 0 
Gates), MI 
(Mar. 7, 1942 R&H Act) 
31-63

BUFFALO, N.Y., DISTRICT * 
The district comprises northern Ohio, northwestern 
Pennsylvania and western and northern New York, 
embracing U.S. waters of Lake Erie exclusive of 
small portion of' western end, Lake Ontario, and St. 
Lawrence River, with their tributary basins drainage 
from boundary between the states of Ohio and 
Michigan to international boundary line east of' 
Frontier, New York. 
IMPROVEMENTS 
Navigation Page 
1. Ashtabula Harbor, Ohio ............... 32-2 
2. Black Rock Channel and 
Tonawanda Harbor, N.Y. .............. 32-2 
3. Buffalo Harbor, N.Y.................... 32-3 
4. Cattaraugus Harbor, N.Y................. 32-3 
5. Cleveland Harbor, Ohio .................. 32-3 
6. Conneaut Harbor, Ohio .................. 32-4 
7. Dunkirk Harbor, N.Y .................. 32-5 
8. Erie Harbor, Pa. .................... 32-5 
9. Fairport Harbor, Ohio ................ 32-5 
10. Geneva-on-the-Lake, Ohio ................ 32-6 
11. Great Sodus Bay Harbor, N.Y............ 32-6 
12. Huron Harbor, Ohio .................. 32-6 
13. Irondequoit Bay, N.Y ..... ............. 32-7 
14. Little Sodus Bay Harbor, N.Y............ 32-7 
15. Lorain Harbor, Ohio ..................... 32-7 
16. Oak Orchard Harbor, N.Y............... 32-8 
17. Ogdensburg Harbor, N.Y................. 32-9 
18. Olcott Harbor, N.Y .................... 32-9 
19. Port Ontario Harbor, N.Y................ 32-9 
20. Rochester Harbor, N.Y. .................. 32-10 
21. Rocky River Harbor, Ohio .............. 32-10 
22. Sandusky Harbor, Ohio .................. 32-10 
23. Toledo Harbor, Ohio ..................... 32-10 
24. Vermilion Harbor, Ohio .................. 32-11 
25. Wilson Harbor, N.Y. ..................... 32-11 
26. Reconnaissance and condition surveys .. .32-11 
27. Other authorized navigation projects ..... 32-11 
28. Navigation work under 
special authorization . .................. 32-11 
Beach Erosion Control 
29. Lakeview Park, Lorain, Ohio ............ 32-12 
30. Maumee Bay State Park, Ohio .......... 32-12 
31. Presque Isle Peninsula, Erie, Pa..........32-13 
32. Other authorized beach erosion 
control projects .......................... 32-14 
33. Beach erosion work under 
special authorization ................... 32-14 
Flood Control 
34. Ellicott Creek, N.Y ...................... 32-14 
35. Mt. Morris Lake, N.Y., 
Genesee River .......................... 32-15 
36. Ottawa, Ohio ..... ................. 32-15 
37. Point Place, Toledo, Ohio ................ 32-15 
38. Reno Beach- 
Howard Farms Area, Ohio...............32-15 
39. Inspection of completed 
flood control projects ..................... 32-16 
40. National Emergency Preparedness ....... 32-16 
41. Other authorized flood 
control projects ........................ 32-16 
42. Flood control work under 
special authorization .................... 32-16 
Deauthorized projects 
43. Deauthorized Projects .................... 32-17 
General Investigations 
44. Surveys .................................. 32-17 
45. Collection and study of basic data ....... 32-17 
46. Advance Engineering & Design..........32-17 
47. Continuation of Planning 
and Engineering ........................ 32-17 
32-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. ASHTABULA HARBOR, OHIO 
Location. On the south shore of Lake Erie, at 
mouth of Ashtabula River, 59 miles easterly from 
Cleveland, Ohio. (See NOAA Nautical Chart 14836.) 
Previous projects. For details see page 1963 of 
Annual Report for 1915, and page 1593 of Annual 
Report for 1938. 
Existing project. For description see pages 1297- 
99 of Annual Report for 1966. Federal cost of 
completed project is $12,240,147. Non-Federal costs 
of $5,743,000, including contribution of $47,000, were 
for construction of access roads, docks, storage and 
handling facilities and dockside dredging. See Table 
32-B for authorizing legislation. 
Local cooperation. Fully complied with. Local 
interests contributed $47,000 for work authorized by 
1936 and 1970 acts. 
Terminal facilities. There are 16 piers and 
wharves. One facility is owned by city of Ashtabula 
and one is owned by Coast Guard. Ten facilities are 
along banks of Ashtabula River and six are on 
southside of outer harbor. Eleven terminals have 
railroad connections and six have mechanicalhandling 
facilities. Facilities are considered adequate 
for existing commerce. (See Port Series No. 42, 
revised 1972, Corps of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition sediment surveys by Government plant 
and hired labor cost $32,834. Contract for analysis 
of and dewatering sediments cost $37,265. Aerial 
photography of shoreline, by contract, cost $4,500. 
Repairs to 50 l.f. of the west breakwater by U.S. 
derrickboat Tonawanda cost $167,050. Snagging and 
clearing to remove logs in lower river by government 
plant and hired labor cost $3,038. Engineering effort, 
to include economics study and continued environmental 
and water quality analyses, cost $80,805. 
2. BLACK ROCK CHANNEL AND 
TONAWANDA HARBOR, N.Y. 
Location. Improvement is essentially that of 
upper 13.5 miles of Niagara River from its head at 
Lake Erie, Buffalo, N.Y., to and including Tonawanda 
Harbor, N.Y. It comprises improvements 
formerly designated by three titles; viz, Lake Erie 
entrance to Black Rock Harbor and Erie Basin, 
N.Y., Black Rock Harbor and Channel, N.Y., and 
Tonawanda Harbor and Niagara River, N.Y. (See 
NOAA Nautical Chart 14832.) 
Previous projects. For details see item 5 and 7, 
page 1970 of Annual Report for 1915, and page 1612 
of Annual Report for 1938. 
Existing project. For description of existing 
project and Federally owned Black Rock ship lock, 
see page 1548 of Annual Report for 1962. Improvement 
of guide pier at Black Rock Lock, as authorized 
by 1935 act was deauthorized by Congress in August 
1977. Cost for completed portion of new work is 
$10,457,093. Enlarging'of existing 21-foot turning 
basin and deepening lower 1,500 feet of Tonawanda 
inner harbor from 16 to 21 feet, authorized by the 
1954 act, was deauthorized by Congress in May 
1981, and is excluded from foregoing cost. Estimated 
cost (1961) of this portion is $339,000. Non-Federal 
costs are estimated at $1,540,000 for costs incurred 
by New York State for construction of Erie Basin 
and protecting breakwater, and construction and 
extension of Bird Island Pier, and by other local 
interests for relocation of utilities. See Table 32-B for 
authorizing legislation. 
Local cooperation. Fully complied with for 
existing project. Contract for cost-shared recreation 
development at completed projects (Code 713 program) 
was executed by the New York State Department 
of Environmental Conservation, Albany, NY, 
on April 16, 1985, and approved by the Assistant 
Secretary of the Army and Chief of Engineers on 
May 3, 1985. 
Terminal facilities. Two facilities are along 
upstream end of channel. Below Black Rock Lock 
and at Tonawanda Harbor there are 13 privately 
owned terminals. There are two State-owned barge 
canal terminals at Tonawanda, N.Y., and several 
marine service and supply, docks for recreational 
and other small craft. The Corps owns a wharf 
adjacent to Black Rock Lock which is priyate. Ten 
terminals have railroad connections and six 
mechanical-handling facilities. Facilities considered 
adequate for existing commerce. (Port Series No. 41, 
revised 1971, Corps of Engineers.) 
Operations and results during fiscal year. 
New Work: Construction of an elevated concrete 
walkway with railing and three refuge platforms on 
Bird Island Pier, under cost-shared recreation 
development at completed projects, was initiated in 
June 1985 and cost $310,000 Federal funds and 
$159,998 non-Federal funds. Operation and care 
(Black Rock Lock): Lock was in operation 251 days 
and closed for underwater cleaning and repairs from 
January 4, .1986 through April 28, 1986. Ordinary 
maintenance and repair of structures and grounds 
was accomplished throughout the year by Government 
plant and hired labor. Total costs of $2,718,745 
were distributed as follows: Operation and care: 
operation of lock, ordinary maintenance and repair 
$439,478; maintenance of grounds $32,504; miscellaneous 
inspection and condition sediment surveys, 
project supervision, real estate, and support of Water 
Control Center $81,690. Rehabilitation of the upper 
guard gates by U.S. derrickboats McCauley and 
Simonsen cost $45,002 and $365,901, respectively. 
Painting of upper guard gates, by contract, cost 
$54,131. Rehabilitation of the butterfly valves of 
gates, by contract, cost $31,102. Snagging and clearing 
in project channels by Government plant and 
hired labor cost $74,910. Dredging in channel, by 
contract, cost $124,605 and removed an estimated 
32-2

BUFFALO, NY DISTRICT 
20,000 cy material. Repairs to Bird Island Pier 
(within project channel) by contract, initiated in 
June 1985, cost $1,343,284. Construction will repair 
approximately 6800 1.f. of existing pier and provide a 
concrete walkway and three refuge platforms (Code 
713 work). Engineering effort in association with 
rehabilitation of gates and operation of locks cost 
$126,138. 
3. BUFFALO HARBOR, N.Y. 
Location. At eastern end of Lake Erie, at head of 
Niagara River, 176 miles easterly from Cleveland, 
Ohio. (See NOAA Nautical Charts 14820 and 14833.) 
Previous projects. For details see page 1967 of 
Annual Report for 1915 and page 1606 of Annual 
Report for 1938. 
Existing project. For description see page 1368 
of Annual Report for 1963. In addition, on 15 
December 1980, OCE authorized the removal of 
bridge abutments of South Michigan Avenue Bridge. 
New work for completed project cost $18,837,601. 
Estimated non-Federal costs were $9,188,000 for 
deepening, widening, and improving Buffalo River 
and ship canal, constructing piers, retaining walls, 
and dikes and performing dockside dredging. See 
Table 32-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 45 wharves and 
piers of which 4 piers, owned by Niagara Frontier 
Port Authority, and 9 privately owned and operated 
facilities are on outer harbor and along sides of 
Lackawanna and Union ship canal, 4 are along 
banks of Buffalo ship canal, and 26 along Buffalo 
River. Coast Guard facilities are at mouth of Buffalo 
River along left bank. City of Buffalo owns a slip on 
right bank of Buffalo River just north of Michigan 
Avenue Bridge for mooring city fireboat. Thirty-four 
terminals have railroad connections and 29 mechanical-
handling facilities. Facilities considered 
adequate for existing commerce. (See Port Series No. 
41, revised 1971, Corps of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services, condition 
sediment surveys by Government plant and 
hired labor, water control management, and real 
estate activities cost $288,994. Repairs to about 200 
l.f. of south breakwater and 450 l.f. of confined 
disposal area by U.S. derrickboat McCauley cost 
$690,746. Removal of an estimated 130,000 cubic 
yards of shoaled material, by contract, cost $651,196. 
Environmental testing at Times Beach, by contract, 
cost $75,025. Aerial photography of shoreline, by 
contract, cost $6,540. Snagging and clearing in 
Buffalo River by Government plant and hired labor 
cost $35,897. Engineering costs for plans and 
specifications for dredging cost $16,235. 
4. CATTARAUGUS HARBOR, N.Y. 
Location. At mouth of Cattaraugus Creek on 
south shore of Lake Erie about 12 miles northeasterly 
from Dunkirk Harbor, N.Y. and 24 miles southwesterly 
from Buffalo Harbor, N.Y. (See NOAA 
Nautical Chart 14823.) 
Existing project. For details of the existing 
project, see page 32-4 of Annual Report for 1983. 
Construction was completed in January 1983. Federal 
cost for new work was $4,797,821 (Oct. 1981). Non- 
Federal cost for new work was $2,566,529 (Oct. 1981). 
Existing project was authorized by 1968 River and 
Harbor Act (H. Doc. 97, 90th Cong., 1st sess.). 
Local cooperation. See page 32-5 of Annual 
Report for 1976 for details of requirements of local 
cooperation. The cash contribution paid was 
$2,566,529. The State of New York executed local 
cooperation agreement in July 1981. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately owned 
servicing and storage handling facilities for recreational 
and other small craft. 
Operations and results during fiscal year. 
New work: Expenditure of $157 was attributed to inhouse 
engineering effort. Maintenance: Project condition 
sediment surveys were conducted at a cost of 
$22,742. Removal of weather-beaten permanent 
markers within the channel, by contract, cost $16,298. 
Stream gage maintenance cost $10,000. 
5. CLEVELAND HARBOR, OHIO 
Location. On south shore of Lake Erie, at mouth 
of Cuyahoga River, 176 miles westerly from Buffalo, 
N.Y. (See NOAA Nautical Chart 14839). 
Previous projects. For details see page 1962, 
Annual Report for 1915, and page 1585, Annual 
Report for 1938. 
Existing project. For description of existing 
project, as authorized through the 1966 modification, 
see page 1269 of Annual Report for 1967. Further 
improvements in the interest of commercial navigation 
and recreational navigation were authorized in 
the 1985 Supplemental Appropriations Act (PL 99- 
88). The commercial navigation portion of the overall 
project consists of: (a) enlarging and deepening to 31 
feet LWD the east entrance channel; (b) deepening 
the east basin channel to 27 feet LWD; and (c) 
expanding the capacity of Dike Site 14 to contain 
the polluted dredged material resulting from the 
project. This portion of the project is currently on 
hold due to the inability of the local sponsor to 
finance their share of the project costs. The recreational 
navigation portion of the overall project consists 
of bulkheading and other necessary repairs to 
Pier 34 and approach channels and necessary protective 
structures for mooring basins for transient 
vessels in the area south of Pier 34. Estimated total 
Federal cost of the existing project is $34,565,100 
(Oct. 1985) exclusive of inactive and deferred portions 
of the project. The amount of $29,315,100 is for 
completed work and the balance of $5,250,000 is for 
32-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
new work. Estimated non-Federal cost is $13,433,000 
(Oct. 1985) of which $9,203,000 is actual cost for 
completed work and the balance of $4,230,000 is 
required for work authorized by PL 99-88. Remaining 
work authorized by 1946 River and Harbor Act, 
consisting of widening and deepening the right bank 
of Cuyahoga River at the downstream end of Cut 4, 
is considered inactive and excluded from foregoing 
cost estimate. Estimated Federal cost (1966) of this 
portion is $85,600 and non-Federal cost (1966) is 
$5,000,000. Remaining work authorized by 1958 R&H 
Act, consisting of planning and replacement of 
bridges number 19 (E.L.R.R.) and 32 (B.&O.R.R.) 
and widening Cuyahoga and Old River channels, 
and remaining work authorized by the 1960 R&H 
Act, consisting of deepening the remainder of 
Cuyahoga River from bridge number 1 to and including 
the Old River to a depth of 27 feet, has been 
classified as deferred and is also excluded from 
foregoing cost estimate. Estimated Federal cost (Oct. 
1976) of this portion is $18,033,300 and estimated 
non-Federal cost (Oct. 1976) is $21,251,000. See Table 
32-B for authorizing legislation. 
Local cooperation. Fully complied with for 
completed portion of project. Items of local cooperation 
for the commercial navigation portion of the 
overall project authorized by PL 99-88 consist of: (a) 
Provide without cost to the United States all lands, 
easements, and rights-of-way required for construction 
and maintenance of the harbor improvements, 
including suitable areas determined by the Chief of 
Engineers to be required in the general public interest 
for the initial and subsequent disposal of dredged 
material, and also necessary retaining dikes, bulkheads, 
and embankments therefor, or the cost of 
such retaining works; (b) Accomplish without cost to 
the United States all alterations and relocations of 
transportation systems, storm drains, sewer outfalls, 
utilities, and other relocations and alterations made 
necessary by the project; (c) Hold and save the 
United States free from damages due to the construction 
and maintenance of the project, not including 
damages due to the fault or negligence of the United 
States or its contractors; (d) Provide and maintain 
without cost to the United States adequate depths in 
berthing areas and local access channels; (e) Provide, 
during the period of construction, a cost contribution 
equal to 25 percent of the estimated total cost of 
construction of the general navigation facilities 
assigned to commercial navigation; and (f) Repay 
with interest, over a period not to exceed 30 years 
following completion of the project, an additional 0- 
10 percent of the total cost of construction of the 
general navigation facilities assigned to commercial 
navigation depending on the value of lands, easements, 
rights-of-way, relocations, and dredged 
material disposal areas provided by local interests 
for the general navigation features of the project. 
Items of local cooperation have not been established 
for the recreational portion of the overall project. 
Terminal facilities. There are 65 piers and 
wharves. Fourteen are located in the outer harbor, 
11 on banks of Old River and 40 along the deep-draft 
section of Cuyahoga River. Forty-one terminals have 
both railroad connections and mechanical-handling 
facilities. The Corps owns a wharf at the foot of East 
9th Street. Facilities are considered adequate for 
existing commerce. (See Port Series No. 43, revised 
1981, Corps of Engineers). 
Operations and results during fiscal year. 
New work: Preparation of an Affirmation Report 
and Plans and Specifications for the commercial 
navigation portion of the overall project authorized 
by PL 99-88 and initiation of the Formulation Report 
for the recreational navigation portion of the project 
was conducted under the General Investigation 
Appropriation at a cost of $193,000. Maintenance: 
Miscellaneous inspection services, condition sediment 
surveys, letter report on new confined disposal facility 
and economics report by Government plant 
and hired labor cost $468,591. Environmental testing, 
by contract, cost $70,820. Repairs to 125 1.f. of 
dolos structure at east end of east breakwater, 120 
l.f. of east arrowhead and east breakwater, and 50 
l.f. of west arrowhead by U.S. derrickboat Tonawanda 
cost $383,278. Repairs to approximately 50 
l.f. of breached portion of east breakwater by U.S. 
derrickboat Simonsen cost $122,960. Dike repairs by 
Government plant and hired labor cost $10,611. 
Removal of shoaled material: 221,758 cubic yards 
from Cuyahoga River, 85,899 cubic yards from the 
harbor and 35,898 cubic yards from upper Cuyahoga 
River, by contract, cost $1,992,751. In-house engineering 
costs for preparation of plans and specifications 
on contract dredging were $30,376. Engineering during 
construction of major rehabilitation cost $45,456. 
Major Rehabilitation: Repairs to 3,300 1.f. of the east 
breakwater, by contract, initiated in July 1985, is 
96% complete, and cost $3,597,237. Finalization of 
FY 85 aerial photography of shoreline contract cost 
$12,410. 
6. CONNEAUT HARBOR, OHIO 
Location. On south shore of Lake Erie, at mouth 
of Conneaut River, 73 miles easterly from Cleveland, 
Ohio. (See NOAA Nautical Chart 14824.) 
Previous projects. For details see page 1964, 
Annual Report for 1915. 
Existing projects. For description see page 1274 
of Annual Report for 1967. Actual costs for new 
work for completed portion of the project were 
$7,541,369. See page 1274, Annual Report 1967, for 
complete description of project modification authorized 
by 1966 R&H Act. Estimated cost (1970) of this 
modification is $717,000. For completed work non- 
Federal costs were $200,000 for dockside dredging 
and removal of existing dolphins. Estimated non- 
Federal cost of $2,877,000 (1970) includes cash 
contribution of $717,000 and the remainder is for 
construction of service facilities for the 1966 project 
32-4

BUFFALO, NY DISTRICT 
modification. See Table 32-B for authorizing legislation. 
Local cooperation. Fully complied with for 
completed portion of project. See page 32-6 of Annual 
Report for 1971 for requirements of local cooperation 
for project modification as authorized by the River 
and Harbor Act of 1966. 
Terminal facilities. There are seven piers and 
wharves. Six are privately owned and operated and 
located in inner harbor. Remaining facility is city 
owned on the south side of outer harbor. Six terminals 
have railroad connections and four mechanicalhandling 
facilities. (See Port Series No. 42, revised 
1972, Corps of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition sediment surveys were done by Government 
plant and hired labor at a cost of $36,584. 
Repairs to 175 l.f. of east and west breakwaters by 
U.S. derriclboat Tonawanda cost $369,318. Dredging 
for removal of 68,287 cubic yards of material, by 
contract, cost $213,284. Aerial photography of shoreline, 
by contract, cost $4,261. Engineering effort 
toward plans and specifications for dredging cost 
$10,400. 
7. DUNKIRK HARBOR, N.Y. 
Location. On south shore of Lake Erie, 37 miles 
southwesterly from Buffalo, N.Y. (See NOAA Nautical 
Chart 14823.) 
Previous projects. For details see page 1966 of 
Annual Report for 1915, and page 1604 of Annual 
Report for 1938. 
Existing project. For description of completed 
portion of existing project see page 32-8 of Annual 
Report for 1976. For description of small boat harbor 
project as authorized under Section 201 of Flood 
Control Act of 1965, see page 32-8 of Annual Report 
for 1978. Actual costs for completed work are 
$3,010,024. Actual non-Federal costs are $1,961,000. 
See Table 32-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately owned 
servicing and storage handling facilities for recreational 
and other small craft. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition sediment surveys by Government plant 
and hired labor cost $13,549. Environmental testing 
of harbor sediments, by contract, cost $20,857. 
8. ERIE HARBOR, PA. 
Location. On southerly side of bay formed by 
Presque Isle Peninsula, on south shore of Lake Erie, 
78 miles westerly from Buffalo, N.Y. (See NOAA 
Nautical Chart 14835.) 
Previous projects. For details see page 1965 of 
Annual Report for 1915 and page 1600 of Annual 
Report for 1938. 
Existing projects. For description see pages 
1363-64 of Annual Report for 1963. Entire project 
modification authorized by 1945 River and Harbor 
Act, providing for deepening channel and basin, 
both 23 feet deep, to Penn Central Company coal 
docks at westerly end of harbor, was deauthorized 
by Congress in August 1977. Actual costs for new 
work for completed portion of project were $2,860,906. 
Extension of north pier portion as authorized by 
1899 act was deauthorized in November 1981. 
Estimated cost (1955) of this portion is $1,071,000. A 
portion of work authorized by 1960 act, deepening 
strips adjacent to north and south piers, was deauthorized 
in August 1982. Estimated cost (July 
1962) of this portion is $78,000. Non-Federal costs for 
completed work were $51,000 for providing ore dock 
and dredging slip adjacent thereto. See Table 32-B 
for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Sixteen piers and wharves, 
of which 12 are privately owned and operated. Erie 
International Marine Terminal No. 1 owned by Port 
Commission, city of Erie, is along main waterfront 
on south side of Presque Isle Bay and Coast Guard 
facilities are on north side. Two offshore oil docks 
are on Lake Erie. Eight terminals have railroad 
connections and six mechanical-handling facilities. 
Facilities are considered adequate for existing commerce. 
(See Port Series No. 42, revised 1972, Corps of 
Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services, 
condition sediment surveys and economic study by 
Government plant and hired labor cost $47,517. 
Environmental testing, by contract, cost $20,907. 
Dredging, by contract, to remove approx. 75,004 
cubic yards of material cost $216,755. Engineering 
effort cost $11,656. 
9. FAIRPORT HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth 
of Grand River, 33 miles easterly from Cleveland, 
Ohio. (See NOAA Nautical Chart 14837.) 
Previous projects. For details see page 1963 of 
Annual Report for 1915, and page 1590 of Annual 
Report for 1938. 
Existing project. For description of existing 
project as authorized through the 1960 modifications, 
see page 1526 of Annual Report for 1962; for description 
of small boat harbor as authorized by Sec. 201 
of 1965 Flood Control Act, see page 32-10 of Annual 
Report for 1977. Estimated total Federal cost of new 
work is $4,931,000 (Oct. 1980) of which $2,591,000 is 
actual cost for completed portion of project and the 
balance of $2,340,000 is for proposed work authorized 
by Sec. 201 of 1965 FC Act which is deferred. Entire 
project modification authorized by 1960 River and 
32-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Harbor Act, providing for deepening lake approach 
channel, 800-foot wide channel through outer harbor 
and channel in Grand River, and enlargement of 
turning basin, is classified inactive and is excluded 
from foregoing cost. Estimated cost of this modification 
is $3,170,000 (1963). Estimated non-Federal cost 
is $4,991,000 of which $101,000 were for bulkheads 
and dockside dredging for completed portion of 
project and $2,560,000 which includes cash contribution 
of $2,330,000, is for work authorized by Sec. 201 
of 1965 FC Act. For the inactive 1960 project 
modification, estimated non-Federal cost of $3,821,000 
(1963) is for lands, relocations, utility changes, dock 
dredging and dock and bulkhead modifications. See 
Table 32-B for authorizing legislation. 
Local cooperation. See page 32-11 of 1976 Annual 
Report regarding assurances of local cooperation for 
work authorized by R&H Acts of 1927 and 1960 and 
page 32-11 of 1977 Annual Report for requirements 
of local cooperation for work authorized by Sec. 201 
of 1965 Flood Control Act. 
Terminal facilities. Sixteen piers and wharves, 
all along banks of Grand River. One facility is owned 
by Coast Guard. Nine terminals have railroad connections 
and ten mechanical-handling facilities. 
Facilities considered adequate for existing commerce. 
(See Port Series No. 42, revised 1972, Corps of 
Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition sediment surveys by Government plant 
and hired labor cost $21,876. U.S. derrickboat 
Simonsen repaired 50 l.f. of west breakwater at a 
cost of $241,856. Environmental testing, by contract, 
cost $25,844. Finalization of FY85 dredging contract 
resulted in a net credit of $26,399. 
10. GENEVA-ON-THE-LAKE, OHIO 
Location. On south shore of Lake Erie about 17 
miles east of Fairport Harbor, Ohio and 12 miles 
west of Ashtabula Harbor, Ohio (See NOAA Nautical 
Chart 14826.) 
Existing project. Small boat harbor project 
provides for: (a) breakwaters in Lake Erie aggregating 
about 1,350 feet in length; (b) entrance channel 
about 730 feet long, 100 feet in width, 9 feet deep; (c) 
inner channels, 100 feet wide totaling 1,500 feet in 
length and 6 feet deep; (d) a mooring area 0.5 acres 
in area with a depth of 6 feet; (e) development of 
recreational facilities and (f) development of wetland 
mitigation features. Estimated Federal cost for new 
work is $4,610,000 (Oct. 1985). Non-Federal cost 
estimate is $4,610,000 (Oct. 1985). Existing project 
was authorized under provision of Section 201 of 
Flood Control Act of 1965. (H.D. 409, 91st Cong., 2d 
sess.) 
Local cooperation. See page 32-11 of 1978 Annual 
Report for requirements of local cooperation for 
work authorized by Sec. 201 of 1965 Flood Control 
Act. The State of Ohio Department of Natural 
Resources (ODNR) the responsible agency, signed a 
Local Cooperation Agreement (LCA) on June 24, 
1986. The LCA was executed on the part of the 
Federal Government on June 26, 1986. Bids for the 
construction contract were opened on September 16, 
1986. The contract was awarded on September 25, 
1986 and the construction started on October 9, 1986 
is scheduled for completion by May 3, 1989. 
Terminal facilities. There are no commercial or 
recreational facilities at the harbor. 
Operations and results during fiscal year. 
New Work: In FY 86, Plans and Specifications were 
completed and a construction contract was awarded. 
Federal funds expended for in-house engineering 
effort were $6,943 to conclude the Advance Engineering 
and Design and $92,221 for Plans and Specifications 
under the Construction General Appropriation. 
Non-Federal expenditure was $64,036. 
11. GREAT SODUS BAY HARBOR, 
N.Y. 
Location. On Sodus Bay, which is a nearly 
landlocked indentation on south shore of Lake 
Ontario, 29 miles westerly from Oswego, N.Y. (See 
NOAA Nautical Chart 14814.) 
Previous projects. For details see page 1972 of 
Annual Report for 1915 and page 1526 of Annual 
Report for 1938. 
Existing project. For description, see page 1380 
of Annual Report for 1963. Improvements authorized 
by 1962 act, consisting of deepening lake approach 
channel, entrance channel and inner approach 
channel were deauthorized by Congress in August 
1977. Actual costs of new work for completed portion 
of project were $249,187. Costs incurred by local 
interests are not available. See Table 32-B for 
authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately owned 
servicing and storage handling facilities for recreational 
and other small craft. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition sediment surveys by Government plant 
and hired labor cost $7,398. 
12. HURON HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth 
of Huron River, 47 miles westerly from Cleveland, 
Ohio. (See NOAA Nautical Chart 14843.) 
Previous project. For details, see page 1961 of 
Annual Report for 1915, and page 1576 of Annual 
Report for 1938. 
Existing project. For description see page 1347 
of Annual Report for 1963 and page 32-12 of Annual 
32-6

BUFFALO, NY DISTRICT 
Report for 1978. Cost of completed portion of existing 
project was $4,834,006. Construction of detached 
breakwater as authorized by 1962 R&H act is deferred. 
Estimated cost of construction of breakwater 
is $12,970,000 (July 1972). Non-Federal costs of 
$163,000 were incurred by local interests in 1963 for 
dockside dredging of areas between Federal improvement 
and terminal facilities. See Table 32-B for 
authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Six privately owned wharves 
and docks, one along left bank of Huron River and 
remainder along right bank. Four terminals have 
railroad connections and four mechanical-handling 
facilities. Facilities are regarded as adequate for 
existing commerce. (See Port Series No. 42, revised 
1972, Corps of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition sediment surveys by Government plant 
and hired labor cost $18,316. Repairs to 800 1.f. of the 
west pier, by contract, cost $469,334. Economic study, 
by contract, cost $9,138. Repairs to 200 l.f. of confined 
disposal area fence and 50 l.f. of east breakwater 
by U.S. derrickboat Simonsen cost $79,685. 
Finalization of FY85 dredging contract resulted in a 
net credit of $31,082. In-house engineering effort for 
plans and specifications cost $53,457. 
13. IRONDEQUOIT BAY, N.Y. 
Location. On south shore of Lake Ontario, 4 
miles east of Rochester, N.Y. at month of Irondequoit 
Creek, Monroe County, N.Y. (See NOAA Nautical 
Charts 14804 and 14815.) 
Existing project. Provides for: (a) entrance 
channel 9 feet deep and 100 feet wide, extending 
from 9-foot depth in Lake Ontario to junction with 
inner bay channels a distance of about 1,300 feet; (b) 
inner channel, 8 feet deep and 100 feet wide, from 
entrance channel to deep water in bay, a distance of 
about 3,035 feet; (c) access channel, 8 feet deep, 100 
feet wide, and 500 feet in length from the inner bay 
channel to the west; (d) two stone rubblemound 
structures 1,350 feet and 750 feet in length at the 
natural entrance; and (e) recreational facilities of 
parking area, two comfort stations, concrete walkways 
and hand railings on the breakwater and jetty 
and a boat launching ramp. The local sponsor (New 
York State Office of Parks, Recreation and Historic 
Preservation) requested that the boat launching 
ramp, parking areas and other recreational features 
be constructed under a separate contract from that 
for the navigation features. Construction of the 
breakwaters, jetty, navigation channel and highway 
bridge removal was completed in May 1986. Total 
estimated project cost is $14,390,000 (Oct. 1984) 
including $2,903,000 Federal (which includes the 
CoE $2,852,000 and the USCG $51,000) and 
11,478,000 non-Federal, including a cash contribution 
of $2,367,000, lands and damages $290,000, and 
the cost of a movable highway bridge $8,830,000. 
Existing project was authorized by 1958 River and 
Harbor Act (H. Doc 332, 84th Cong., 2nd sess.) 
Local cooperation. The Buffalo District has a 
properly executed Local Cooperation Agreement with 
New York State, executed April 20, 1983. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately owned 
servicing and storage handling facilities for recreational 
and other small craft. 
Operations and results during fiscal year. 
New work: Construction of the breakwaters, jetties, 
navigation channel, bridge removal and certain 
recreational facilities were completed. A net contract 
credit of $236,690 (Federal funds) was attributable to 
an adjustment between the Federal and non-Federal 
accounts. Non-Federal contract cost was $1,520,293. 
In-house engineering effort cost $69,764 Federal and 
$68,931 non-Federal. A contract to complete construction 
of the recreational facilities was awarded 
on Sept. 25 1986 for $524,600. The work is scheduled 
for completion in July 1987. 
14. LITTLE SODUS BAY HARBOR, 
N.Y. 
Location. Little Sodus Bay, on south shore of 
Lake Ontario, 15 miles west of Oswego, N.Y. (See 
NOAA Nautical Chart 14803.) 
Previous projects. For details see page 1973 of 
Annual Report for 1915, and page 1628 of Annual 
Report for 1938. 
Existing project. For description see page 1378 
of Annual Report for 1958. New work for completed 
project cost $69,066. Non-Federal costs of $6,000 were 
incurred for channel dredging. See Table 32-B for 
authorizing legislation. 
Local cooperation. None required. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately owned 
servicing and storage handling facilities for recreational 
and other small craft. 
Operations and results during fiscal year. 
Maintenance: Inspection for structure evaluation 
cost $2,803. 
15. LORAIN HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth 
of Black River, 28 miles westerly from Cleveland, 
Ohio. (See NOAA Nautical Chart 14841.) 
Previous projects. For details, see page 1961 of 
Annual Report for 1915, and page 1580 of Annual 
Report for 1938. 
Existing project. For description see pages 1319- 
22 of Annual Report for 1966. Estimated Federal 
cost of new work is $26,246,000 (Oct 1976). Deepening 
and widening remainder of Black River Channel at 
Cut 1 and construction of bank stabilization as 
32-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
authorized by 1960 act and modified by 1965 act is 
classified deferred. The estimated cost of $5,317,000 
for this work is included in the above estimate. A 
portion of work authorized by 1960 act, dredging of 
15-to-25 foot wide strips adjacent to the U.S. East 
and West piers is also deferred and estimated cost of 
$60,200 (July 1966) is excluded from foregoing cost 
estimate. Total non-Federal cost estimate is 
$8,853,000 (Oct 1976) including $3,000 contributed by 
local interests toward construction of west breakwater 
shorearm. For work authorized by 1960 act, 
including deferred portion, non-Federal costs are 
estimated to be $8,805,000 for lands, relocations of 
utilities, modifications of existing dock and bulkheads, 
construction of new bulkheads and dockside 
dredging. For work authorized by 1965 act, classified 
as deferred, local interests must make a cash contribution 
presently estimated at $45,000. See Table 
32-B for authorizing legislation. On March 12, 1986 
the Chief of Engineers under authority of Section 
107 of the 1960 River and Harbors Act, as amended, 
authorized construction of a small-boat harbor. The 
project consists of constructing a 325-foot detached 
rubblemound breakwater and an 800-foot long rubblemound 
breakwater attached to the east breakwater 
shorearm in the east basin of the outer harbor. 
Estimated costs for this work are $1,913,000 Federal 
and $1,831,000 non-Federal (Oct 1985). 
Local cooperation. For coripleted work, local 
interests contributed $3,000. Work authorized by 
1960 act (and modified by 1965 act) is deferred. All 
other conditions fully complied with. On March 25, 
1986, the city of Lorain, Ohio signed the local 
cooperation agreement, for the Section 107 project, 
to: (a) Prior to construction, provide without cost to 
the United States, all lands, easements, and rightsof-
way necessary for construction and maintenance 
of the project, and for aids to navigation, upon 
request of the Chief of Engineers, including suitable 
areas determined by the Chief of Engineers to be 
required in the general public interest for initial and 
subsequent disposal of dredged material, including 
necessary retaining dikes, bulkheads, and embankments 
or the cost of such retaining works, (b) Provide 
and maintain a marina with adequate public access 
facilities, including launching ramps and a public 
dock, landing or berthing areas for transient vessels, 
all with sanitary facilities, parking space, with 
provisions for the sale of motor fuel, lubricants and 
potable water, available to all on equal terms, (c) 
Provide and maintain depths in berthing and 
mooring areas commensurate with those provided in 
the Federal project, (d) Establish and enforce regulations 
prohibiting discharge of pollutants into the 
waters of the harbor area by users thereof, which 
regulations shall be in accordance with applicable 
laws and regulations of Federal, State and local 
authorities responsible for pollution protection. Provide 
facilities for onshore disposal of untreated 
sewage, garbage, debris and other pollutants, (e) 
Maintain and replace recreational fishing facilities, 
(f) Hold and save the United States free from 
damages due to the construction and maintenance 
of the project except for damages due to the fault or 
negligence of the United States or its Contractors, 
(g) Accomplish without cost to the United States all 
alterations and relocations of buildings, streets, 
sewers, utilities, and other structures and improvements 
required for the construction of the project, (h) 
Contribute in cash 50 percent of that amount of the 
total first cost of construction of the project, except 
aids to navigation, which does not exceed $4,000,000 
and all of such costs in excess of $4,000,000; such 
contribution to be paid in a lump sum prior to 
initiation of construction or in annual installments 
as provided under the authority of Section 404 of the 
Water Resources Development Act of 1974 (Public 
Law 93-251), subject to final adjustment based on 
actual costs, (i) Comply with the applicable provisions 
of the Uniform Relocation Assistance and Real 
Property Acquisition Policies Act of 1970, Public 
Law 91-646, approved January 2, 1971, in acquiring 
lands, easements, and right-of-way for construction 
and subsequent maintenance of the project, and 
inform affected persons of pertinent benefits, policies, 
and procedures in connection with said Act, (j) 
Comply with Section 601 of Title VI of the Civil 
Rights Acts of 1964 (PL 88-352) and Department of 
Defense Directive 5500.11 issued pursuant thereto 
and published in Part 300 of Title 32, Code of Federal 
Regulations in connection with the maintenance and 
operation of the project. 
Terminal facilities. There are 23 piers and 
wharves, of which three are on outer harbor and 
remainder are along banks of Black River. Two are 
owned by the city. Eight terminals have railroad 
connections and 15 mechanical-handling facilities. 
Facilities are considered adequate for existing commerce. 
(See Port Series No. 42, revised 1972, Corps of 
Engineers.) 
Operations and results during fiscal year. 
New Work: Contract for Section 107 work was 
awarded August 8, 1986. Contract costs were $207,283 
Federal and $31 non-Federal. In-house engineering 
cost $56,173 Federal and $14,167 non-Federal. 
Maintenance: Miscellaneous inspection services and 
condition sediment surveys by Government plant 
and hired labor cost $40,552. Economic study, by 
contract, cost $9,071. Repairs to 100 l.f. of the west 
breakwater and 150 l.f. of the west breakwater 
extension by the U.S. derrickboat Simonsen cost 
$302,289. Removal of an estimated 175,000 cubic 
yards of shoaled material from Black River Channel 
and upper turning basin, by contract, cost $726,762. 
Confined disposal facility fencing required repair at 
a cost of $2,796. In-house engineering costs were 
$12,485. 
16. OAK ORCHARD HARBOR, N.Y. 
Location. On south shore of Lake Ontario at 
mouth of Oak Orchard Creek, 33 miles westerly of 
Rochester, N.Y. (See NOAA Nautical Chart 14805.) 
32-8

BUFFALO, NY DISTRICT 
Previous project. For details see page 628 of 
Annual Report for 1905. 
Existing project. For description of completed 
existing project see page 32-14 of 1975 Annual Report. 
Actual Federal cost for completed project was 
$1,613,500. Estimated non-Federal cost is $270,000 
(July 1971) including cash contribution of $170,700 
and $54,002 for recreational facilities and remainder 
for lands and construction of wharf. Existing project 
was authorized by the 1945 River and Harbor Act 
(H. Doc. 446, 78th Con., 2nd sess.). 
Local cooperation. Fully complied with. Local 
interests contributed $224,702. 
Terminal facilities. There is no commercial 
navigation at Oak Orchard Harbor. Terminal facilities 
consist of private docks for recreational craft. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection and condition 
sediment surveys cost $1,283. Maintenance dredging, 
by contract, removed an estimated 7,500 cubic yards 
of shoaled material at a cost of $84,014. 
17. OGDENSBURG HARBOR, N.Y. 
Location. On south shore of St. Lawrence River, 
62 miles by water from Lake Ontario. (See NOAA 
Nautical Chart 14764.) 
Previous projects. For details see page 1975 of 
Annual Report for 1915, and page 1635 of Annual 
Report for 1938. 
Existing project. For description see page 1568 
of Annual Report for 1962. Actual cost for new work 
for completed portion of project was $375,086. Removal 
of hard material shoals from lower basin 
portion of project as authorized by 1935 act, at an 
estimated cost of $183,000 (1954) is classified inactive. 
See Table 32-B for authorizing legislation. On April 
20, 1983, the Chief of Engineers under authority 
provided by Section 107 of the 1960 River and Harbor 
Act, as amended, authorized an extension of Lower 
East Entrance Channel, 600 feet west of the existing 
pier to a depth of 27 feet below LWD. This was 
completed in FY 1985. Actual contract cost for this 
work including supervision and administration was 
$974,903 Federal and $50,596 non-Federal. In addition 
to the above described dredging, the local 
cooperator is required to provide $4,000,000 for upland 
improvements. 
Local cooperation. For details of local cooperation 
requirements see page 32-8 of Annual Report for 
1983. 
Operations and results during fiscal year. 
New Work: Finalization of in-house engineering 
effort cost $5,406 Federal funds and $210 non-Federal 
funds. Maintenance: Project condition sediment surveys 
were completed at a cost of $17,691. Aerial 
photography of shoreline, by contract, cost $4,202. 
18. OLCOTT HARBOR, N.Y. 
Location. On south shore of Lake Ontario at 
mouth of Eighteen Mile Creek about 18 miles east of 
mouth of Niagara River and 63 miles by water west 
of Rochester, N.Y. (See NOAA Nautical Chart 14806.) 
Previous project. For details see page 1971 of 
Annual Report for 1915 and page 1621 of Annual 
Report for 1938. 
Existing project. For description see page 1555 
of Annual Report for 1962. Cost of new work for 
completed project was $1,500 exclusive of amounts 
expended on previous projects, all of which was 
contributed by local interests. See Table 32-B for 
authorizing legislation. 
Local cooperation. Fully complied with. Local 
interests contributed $1,500. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately owned 
servicing and storage handling facilities for recreational 
and other small craft. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition surveys by Government plant and hired 
labor cost $1,936. Finalization of FY85 dredging 
contract resulted in a net credit of $6,615. 
19. PORT ONTARIO HARBOR, N.Y. 
Location. On southeasterly end of Lake Ontario, 
19 miles northeasterly of Oswego, N.Y., and 32 miles 
southerly of Sackets Harbor, N.Y. (See NOAA Nautical 
Chart 14803.) 
Previous projects. Adopted by the River and 
Harbor Act July 4, 1836. Only information available 
is the index to the report of the Chief of Engineers. 
Existing project. As modified by Phase I and II 
General Design Memorandum, provides for: (a) two 
shore connected rubblemound breakwaters in Lake 
Ontario at mouth of Salmon River, south breakwater 
about 1,350 feet and north breakwater about 350 feet 
long; (b) entrance channel between breakwaters, 100 
feet wide and 8 feet deep, from deep water in lake to 
a limit about 1,200 feet from 8-foot depth contour in 
lake; (c) river channel 85 feet wide and 6 feet deep 
from inner limit of entrance channel for a distance 
upstream of about 450 feet. Estimated Federal cost 
for new work is $1,940,000 (Oct 1985). Estimated 
non-Federal cost for new work is $1,535,000 (Oct 
1985) including cash contribution of $1,225,000. 
Existing project was authorized by the River and 
Harbor Act of March 2, 1945 (H. Doc. 446, 78th 
Cong., 2nd Sess.) 
Local cooperation. See page 32-16 of Annual 
Report for 1976 for details of requirements of local 
cooperation. Assurances have been received from 
the New York State Office of Parks, Recreation and 
Historic Preservation. The LCA was executed on 
June 24, 1986. 
Terminal facilities. The only commercial navigation 
at Port Ontario is charter boat fishing. Term- 
32-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
inal facilities consist of private docks for recreational 
craft. 
Operations and results during fiscal year. 
New Work: In-house engineering effort was continued 
at a cost of $59,808. 
20. ROCHESTER HARBOR, N.Y. 
Location. On south shore of Lake Ontario, at 
mouth of Genesee River, 59 miles westerly from 
Oswego, N.Y. (See NOAA Nautical Chart 14815.) 
Previous project. For details see page 1471 of 
Annual Report for 1915, and page 1623 of Annual 
Report for 1938. 
Existing project. For description see page 1556 
of Annual Report for 1962. Actual cost for new work 
for completed project is $21,191,514. Non-Federal 
costs are estimated at $2,260,000, all for 1960 act, for 
lands, relocation of submarine cable crossing, relocations 
of small docks and boathouses, dockside 
dredging, structure modifications, and replacement 
of Baltimore & Ohio coal loader. See Table 32-B for 
authorizing legislation. 
Local cooperation. Complied with except provision 
for replacement of coal loading facility as 
required by River and Harbor Act of July 14, 1960. 
Terminal facilities. One terminal facility at 
mouth of Genesee River has been leased to the Great 
Lakes Division of Pittston Stevedoring Corp. Facilities 
also consist of private docks for recreational 
craft and privately owned servicing and storage 
handling facilities for recreational and other small 
craft. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition sediment surveys by Government plant 
and hired labor cost $46,957. Environmental testing, 
by contract, cost $22,313. Aerial photography of 
shoreline, by contract, cost $4,475. Removal of 
410,812 cubic yards of shoaled material, by contract, 
cost $1,098,099. Repairs to 400 l.f. of east pier, by 
contract, cost $531,384. In-house engineering effort 
toward plans and specifications cost $31,615. 
21. ROCKY RIVER HARBOR, OHIO 
Location. At mouth of Rocky River which empties 
into Lake Erie 7 miles westerly from Cleveland, 
Ohio. (See NOAA Nautical Chart 14826.) 
Existing project. For description see page 1329 
of Annual Report for 1966. Federal cost for completed 
project was $343,494 and non-Federal cost was a 
cash contribution of $249,346. See Table 32-B for 
authorizing legislation. 
Local cooperation. Fully complied with. Local 
interests contributed $249,346 for new work. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately-owned 
servicing and storage handling facilities for recreational 
and other small craft. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
project condition sediment surveys by Government 
plant and hired labor cost $16,966. Finalization of 
FY85 dredging contract resulted in net credit of 
$2,379. Repairs to 440 l.f. of east pier, by contract 
initiated late in FY85, were completed at a cost of 
$230,035. Engineering effort cost $958. 
22. SANDUSKY HARBOR, OHIO 
Location. On south shore of Lake Erie, in southeasterly 
portion of Sandusky Bay, 50 miles westerly 
from Cleveland, Ohio. (See NOAA Nautical Chart 
14845.) 
Previous projects. For details see page 1960 of 
Annual Report for 1915, and page 1574 of Annual 
Report for 1938. 
Existing project. For description see pages 1511- 
12 of. Annual Report for 1962. Actual costs for new 
work for completed project were $6,250,121, excluding 
$325,000 contributed by local interests. Non-Federal 
costs for completed project are estimated at $675,000 
including $325,000 cash contribution and the remaining 
$350,000 is for dockside dredging adjacent to 
deepened channels authorized by 1960 act. See Table 
32-B for authorizing legislation. 
Local cooperation. Fully complied with. Local 
interests contributed $325,000 for new work. 
Terminal facilities. Fourteen piers and wharves, 
three at west end of harbor and remainder along 
dock channel. One is a base for State-owned fish 
research and patrol boats. One publicly owned and 
six privately owned are used for mooring fishing 
boats and recreational craft and for ferry service. 
Five terminals have railroad connections and five 
mechanical-handling facilities. Facilities are considered 
adequate for existing commerce. (See Port 
Series No. 42, revised 1972, Corps of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services and 
condition sediment surveys by Government plant 
and hired labor cost $35,377. Maintenance dredging, 
by contract, removed 223,345 cubic yards of shoaled 
material and cost $763,228. Engineering effort cost 
$14,444. 
23. TOLEDO HARBOR, OHIO 
Location. Comprises lower 7 miles of Maumee 
River and channel through Maumee Bay to Lake 
Erie. Maumee River has its source in northern 
Indiana and empties into Lake Erie. Harbor is at 
westerly end of Lake Erie, 99 miles westerly from 
Cleveland, Ohio. (See NOAA Nautical Chart 14847.) 
Previous projects. For details see page 1959 of 
Annual Report for 1915, and page 1565 of Annual 
Report for 1938. 
Existing project. For description of existing 
32-10

BUFFALO, NY DISTRICT 
project see pages 32-18 and -19 of Annual Report for 
1978. Cost of completed existing project was 
$15,567,147. See Table 32-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Maumee River through city 
of Toledo has been developed extensively for deepdraft 
navigation. Detailed information on actual port 
and harbor facilities are in Port Series No. 44 
(revised 1972) prepared and published as Part 2, by 
Board of Engineers for Rivers and Harbors. Information 
on port administration and Federal services, 
port and terminal services and charges, and steamship 
services is prepared and published as Part I by 
the Port Development Staff, U.S. Department of 
Commerce. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition sediment surveys, environmental 
studies, and miscellaneous inspections and 
reports were performed by hired labor at a cost of 
$106,985. Removal of 1,237,612 cubic yards of shoaled 
material from the Bay Channel and the Maumee 
River Channel, by contract, cost $2,688,035. Repairs 
to diked disposal facility by hired labor cost $89,675. 
Biological and environmental study, by contract, 
cost $81,344. Aerial photography of shoreline, by 
contract, cost $16,774. Design of new confined disposal 
facility, by A/E contract, cost $204,779. Inhouse 
engineering effort cost $179,637. 
24. VERMILION HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth 
of Vermilion River, 37 miles westerly from Cleveland, 
Ohio. (See NOAA Nautical Chart 14826.) 
Existing project. For description of existing 
project see pages 32-17 and 32-18 of Annual Report 
for 1975. Actual Federal cost for the completed 
existing project was $1,156,118. Estimated non- 
Federal cost for new work is $754,679 including cash 
contribution of $740,679 and remainder for relocation 
of submarine cable and construction of public wharf. 
See Table 32-B for authorizing legislation. 
Local cooperation. Fully complied with. Local 
interests contributed $740,679. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately owned 
servicing and storage handling facilities for recreational 
and other small craft. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection and condition 
sediment surveys by Government plant and hired 
labor cost $97. Finalization of FY85 maintenance 
dredging contract cost $17,542. 
25. WILSON HARBOR, N.Y. 
Location. At mouth of east branch of Twelve 
Mile Creek, which enters Lake Ontario 12 miles 
easterly of mouth of Niagara River, and 67 miles 
westerly of Rochester Harbor, N.Y. (See NOAA 
Nautical Chart 14806). 
Previous project. For details see page 2395 of 
Annual Report for 1889, and page 628 of Annual 
Report for 1905. 
Existing project. For description see page 32-18 
of Annual Report for 1975. Actual Federal cost for 
the completed existing project was $477,904. Estimated 
non-Federal costs are $774,000 which includes 
cost of $16,000 for previously completed work. Remainder 
of non-Federal costs are for work required 
for 1968 R&H Act including cash contribution of 
$166,988. See Table 32-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately owned 
servicing and storage handling facilities for recreational 
and other small craft. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection and condition 
sediment surveys by Government plant and 
hired labor cost $1,695. Finalization of FY85 structure 
repair contract cost $3,299. 
26. RECONNAISSANCE AND 
CONDITION SURVEYS 
Project 
Barcelona Harbor, NY 
Oswego Harbor, NY 
Pt. Clinton Harbor, OH 
West Harbor, OH 
Date of Survey 
June 1986 
May 1986 
July 1986 
May 1986 
FY Cost 
$ 4,608 
17,703 
7,357 
48,744 
27. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 32-C. 
28. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
See Table 32-D. 
Navigation work pursuant to Section 302, Public 
Law 89-298. 
Lake Neatahwanta, Fulton, NY-Costs of $8,459 
were incurred for preparation of Detailed Project 
Study by contract. In-house engineering effort cost 
$20,662. 
Investigation and removal of sunken vessels and 
other obstructions to navigation under authority of 
Section 19 of the River and Harbor Act of 1899. 
Removal of sunken Barge No. 45, pinned against 
the upstream face of Peace Bridge pier 4, on the 
Niagara River was begun at a cost of $834,000. 
32-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Beach Erosion Control 
29. LAKEVIEW PARK, 
LORAIN, OHIO 
Location. In the city of Lorain, Lorain County, 
Ohio, on south shore of Lake Erie between 1,500 and 
3,000 feet west of Lorain Harbor west breakwater. 
(See NOAA Nautical Chart 14841.) 
Existing project. For description of existing 
project see page 32-19 of Annual Report for 1977. 
The Federal cost of the completed project was 
$1,360,986 and estimated non-Federal cost (Oct. 1976) 
was $50,000 for relocation. In addition, local interests 
contributed $583,280. Five-year monitoring program 
was completed in 1982. Cooperative beach nourishment 
was conducted in FY 80 and FY 81, during 
which time a total of 9,000 cubic yards of sand was 
placed within the project limits. Annual cost of 5- 
year program for beach replenishment and monitoring 
was approximately $75,000. In FY 84 an agreement 
was made between city of Lorain and the 
Federal government to continue cost sharing, 70% 
Federal and 30% local, the costs associated with 
annual beach nourishment until September 30, 1992, 
as provided by Section 156, P.L. 94-587. A beach 
nourishment contract was awarded and completed 
in FY 85, at a cost of $31,704 ($22,465 Federal funds, 
$9,239 non-Federal funds). Existing project authorized 
by 1954 River and Harbor Act (H. Doc. 224, 
83rd Cong., 1st sess.). 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New Work: In-house engineering effort cost $22 
Federal funds and $1,412 non-Federal funds. The 
Federal cost for nourishment has totalled approximately 
$98,000 and costs to local interests have 
totalled approximately $40,000. 
30. MAUMEE BAY STATE PARK, 
OHIO 
Location. Maumee Bay State Park is located in 
Lucas County, OH approximately 5 miles east of 
Toledo. The 1,855 acre park has 11,000 feet of shoreline 
along the southerly end of Maumee Bay (Lake 
Erie). (See U.S. Geological Survey Map, Oregon, OH). 
Existing project. The study for Maumee Bay 
was conducted under the Western Lake Erie Shore 
Study authorized by the Committee on Public Works 
of the House of Representatives on April 11, 1974. 
The recommended plan as described in the General 
Affirmation Report (Feb 1986) consists of a protective 
sand beach stabilized by rubblemound offshore 
breakwaters and jetties along the west half (5,300 
ft.) of park shoreline and a rubblemound revetment 
7,200 feet long at the east end of the park. Estimated 
cost of the project is $15,745,000 (Oct 1985) of which 
$8,407,000 is Federal cost (Corps of Engineers and 
U.S. Coast Guard) and $7,338,000 is non-Federal 
cost including Lands, Utilities and other recreation 
facilities. 
Local cooperation. The local sponsor, Ohio 
Department of Natural Resources, will, prior to 
construction enter into a binding agreement which 
addresses project construction and satisfies the 
requirements of Section 221 of Public Law 91-611. 
The items of local cooperation listed in the Final 
Feasibility Report (Dec 83) are: (a) Provide without 
cost to the United States, all lands, easements, and 
rights-of-way, including borrow and spoil disposal 
areas as determined by the Chief of Engineers, 
necessary for the construction and subsequent maintenance 
of the project; (b) Contribute in cash 30 
percent of the project construction cost, including 
periodic beach nourishment, to be paid in a lump 
sum prior to initiation of such work. In the event 
such work is scheduled over more than one Federal 
Fiscal Year, said contribution may be made in 
annual installments over the period of construction 
at a rate proportionate to the proposed or scheduled 
apportionment of Federal funds to the project with 
the final apportionment of cost to be made after 
actual completion of construction and determination 
of actual costs; (c) Provide appurtenant facilities 
shown on the State's Master Plan, for which recreational 
benefits have been taken; (d) Hold and save 
the United States free from all claims for damage 
due to construction, operation and maintenance of 
project, except for damage due to the fault or negligence 
of the Government or its Contractors; (e) 
Provide without cost to the United States all alterations 
and relocations to existing improvements 
including highways, buildings, utilities, sewers, and 
other facilities which may be required in connection 
with the construction of the project; (f) Construct 
permanent park structures and park roads above the 
100-year water surface elevation of 577.3 IGLD and 
consider such elevation when constructing other 
facilities, which would be significantly affected by 
high waters; (g) Maintain and repair the protective 
structures and improvement measures during the 
useful life thereof as may be required to serve their 
intended purposes; (h) Control water pollution from 
within the park to the extent necessary to safeguard 
the health of the bathers; (i) Maintain continued 
public ownership and use of the shore upon which 
the Federal participation is based during the economic 
life of the project; (j) Provide and maintain 
necessary access roads, parking areas, and other 
public use facilities open and available to all on 
equal terms; and, (k) Comply with the applicable 
provisions of the Uniform Relocation Assistance and 
Real Property Acquisitions Policies Act of 1970, 
Public Law 91-646, approved January 2, 1971, in 
acquiring lands, easements, and rights-of-way for 
construction and subsequent maintenance of the 
project, and inform affected persons of pertinent 
benefits, policies, and procedures in connection with 
said Act. 
Operations and results during fiscal year. 
New Work: In-house engineering effort cost $175,258. 
32-12

BUFFALO, NY DISTRICT 
31. PRESQUE ISLE PENINSULA, 
ERIE, PA 
Location. At Erie, Pa., on south shore of Lake 
Erie, 78 miles southwest of Buffalo, N.Y. and 102 
miles eastnortheast of Cleveland, Ohio, (See NOAA 
Nautical Charts 14824 and 14835). 
Existing project. For description of completed 
portion of existing project see page 1393 of Annual 
Report for 1963. The Water Resources Development 
(WRD) Act of March 7, 1974, reinstated and extended 
authorization for beach erosion control project, as 
provided in 1960 R&H Act, for a period of five years 
from date of enactment of 1974 WRD Act, or if the 
review study of such project is not completed prior to 
end of such period, until such study is completed and 
a report thereon submitted to Congress. Work authorized 
by the 1974 WRD Act was completed in 1979. 
The 1976 Water Resources Development Act provides 
for continued annual nourishment by stating: "At 
expiration of authorization provided in Section 57 of 
Water Resources Development Act of 1974, the Secretary 
of the Army, acting through the Chief of 
Engineers, may provide periodic beach nourishment 
in accordance with cost sharing provisions of Section 
103 (a)(2) of Act of October 23, 1962." The act also 
authorized preparation of a Phase I General Design 
Memorandum. The Final Phase I General Design 
Memorandum (GDM) was completed in June 1980 
and the recommended plan provides for construction 
of 58 offshore rubblemound breakwater segments, 
beach restoration by placement of sand fill, and 
annual beach replenishment for shore protection. A 
draft reformulation report was prepared in June 1985 
to reassess the Presque Isle project and analyze 
additional plans for controlling beach erosion. The 
report concluded that the plan selected in the Phase 
I GDM could be modified to reduce the number of 
offshore breakwater segments from 58 to 38 and to 
construct 10,000 feet of bank run gravel beaches 
along the neck of the peninsula. The project would 
be constructed by a 12-year staged construction 
program. On September 20, 1985, the Office, Chief of 
Engineers recommended to the Assistant Secretary 
of the Army that the Corps proceed with the ongoing 
58-breakwater plan with staged construction. Detailed 
engineering and design studies (CP&E) conducted 
in FY 1986 concluded that construction of the 58- 
breakwater plan by a 12-year staged construction 
program is the most efficient and practicable plan 
for reducing the net combined Presque Isle Beach 
and Erie Harbor annual costs. Estimated Federal 
cost for the authorized project and modifications 
(Oct 1985) is $16,291,000 which includes $5,646,000 
for completed work authorized by the 1954 and 1960 
R&H Acts and 1974 WRD Act and $6,872,000 for 
completed work authorized by the 1976 WRD Act. 
Estimated non-Federal cost for the authorized project 
and modifications (Oct. 1985) is $8,550,000 which 
includes $3,983,000 for completed work authorized 
by 1954 and 1960 R&H Acts and 1974 WRD Act and 
$2,952,000 for completed work authorized by the 1976 
WRD Act. The estimated Federal cost (Oct 1985) for 
the 58 breakwater project is $22,400,000 of which 
$7,600,000 is for continuation of the present annual 
nourishment project while the permanent features 
are being built. The estimated non-Federal cost (Oct 
1985) for the breakwater project is $12,000,000 of 
which $4,100,000 is for continuation of the present 
annual nourishment project while the permanent 
features are being built. See Table 32-B for authorizing 
legislation. 
Local cooperation. Fully complied with for completed 
project as authorized by 1954 and 1960 R&H 
Acts and 1974 WRD Act. An agreement between the 
United States of America and the Commonwealth of 
Pennsylvania, acting through the Department of 
Environmental Resources, was entered into on February 
21, 1979 for the annual nourishment which 
was extended by the 1976 Water Resources Development 
Act. The 58 breakwater project is contingent 
upon local sponsor, namely the Department of Environmental 
Resources of the Commonwealth of 
Pennsylvania, agreeing in writing to provide without 
cost to United States all lands, easements and 
rights-of-way, including suitable borrow and disposal 
areas for excavated material as determined by the 
Chief of Engineers and necessary for implementation 
and for periodic nourishment of the project; provide 
a cash contribution based on the appropriate percentage 
of final construction cost, exclusive of lands, 
easements, and rights-of-way, the percentage to be 
in accordance with existing law based on shore 
ownership and use existing at time of construction, 
which contribution is presently estimated at 
$12,000,000 or 35 percent ($7,900,000) for permanent 
project features and 30 percent ($4,100,000) for continuation 
of the present annual nourishment project 
while the permanent features are being built; pay 30 
percent of the cost for annual beach redistribution 
and replenishment work for the project; hold and 
save the United States free from damages due to 
construction works, except for damages due to fault 
or negligence of Government or its Contractors; 
maintain and operate all the works, including 
breakwaters and periodic sand nourishment and 
redistribution as needed, after completion in accordance 
with regulations prescribed by the Secretary of 
the Army; and assure continued public ownership 
and continued public use without cost to the United 
States of appropriate access and facilities including 
parking and sanitation, necessary for realization of 
public benefits upon which Federal participation is 
based, and administer and maintain beach for continued 
public use during life of project. Formal 
assurances of local cooperation will be requested 
and executed prior to initiation of construction of 
improvements. 
Operations and results during fiscal year. 
New work: Beach nourishment as authorized by the 
1976 WRD Act was continued. One contract for 
32-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
providing beach nourishment was awarded and 
completed. A total of 258,000 tons of course sand 
were placed on the beaches. The contract also included 
placement of a 12-inch top dressing layer of 
wave washed sand over the course sand that was 
used to construct the protective berms. About 37,000 
tons of sand that were washed onto the haul roads 
as a result of the December 2, 1985 storm were 
removed and used for the dressing layer. Investigations 
were initiated to locate sources of better quality 
sand that could be used for the dressing layer in 
future nourishment. During the year a total of 
$1,631,374 ($1,101,511 Federal and $529,863 non- 
Federal) was expended for beach nourishment operations. 
Of this total, contract costs were $1,030,134 
Federal and $484,104 non-Federal. In-house engineering 
effort cost $71,377 Federal and $45,759 non- 
Federal. The Commonwealth of Pennsylvania, contributed 
$497,143 for their share of the FY 86 
nourishment operations. The cumulative non-Federal 
total project share through FY 86 is $6,903,111. The 
Final Phase I General Design Memorandum was 
submitted to the Secretary of the Army in October 
1981 for his review and transmittal to Congress. In 
FY 86, a total of $181,831 was expended to complete 
all engineering and design for the permanent project. 
The Phase II General Design Memorandum which 
presents the detailed final design of the project 
recommended in the Phase I General Design Memorandum 
was prepared. 
32. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
See Table 32-E. 
33. BEACH EROSION WORK UNDER 
SPECIAL AUTHORIZATION 
LAKESHORE PARK 
ASHTABULA, OHIO 
Location. Lakeshore Park is located in Ashtabula, 
Ashtabula County, Ohio, about 40 miles southwest 
of Erie, Pennsylvania, and about 50 miles northeast 
of Cleveland, Ohio. (See U.S. Geological Survey Map, 
Ashtabula North, OH). 
Existing project. For description of existing 
project, see page 32-12 of Annual Report for 1983. 
Construction was completed in July 1983. 
Local cooperation. For details of local cooperation 
requirements, see page 32-12 of Annual Report 
for 1983. 
Operations and results during fiscal year. 
New work: FY 86 Federal cost was $10,937 for beach 
nourishment contract and $2,803 for in-house engineering 
effort. 
Beach erosion activity pursuant to Section 103, 
Public Law 87-874 (preauthorization). 
Century Park, Lorain, OH-Costs of $3,918 were 
incurred for preauthorization studies. 
Lake Erie, Timberlake, OH-Costs of $7,500 were 
incurred for preauthorization studies. 
Mentor Beach Park, Mentor, OH-Costs of $69,635 
were incurred for preauthorization studies. 
Simms Park, Euclid, OH-Costs of $49,050 were 
incurred for preauthorization studies. 
Flood Control 
34. ELLICOTT CREEK, N.Y. 
Location. The proposed channel improvement is 
located on the downstream portion of Ellicott Creek 
in the towns of Amherst and Tonawanda, Erie 
County. (See Geological Survey maps of Tonawanda 
East and Buffalo Northeast, N.Y.) 
Existing project. For detailed description of the 
original project as authorized by Section 201 of the 
1970 Flood Control Act, see page 32-24 of Annual 
Report for 1973. The basic authorization, as modified 
by the Water Resources Development Act of 1974, 
provides authority to undertake flood control measures 
to alleviate flooding that is compatible with 
authorized project and any alternatives currently 
under restudy pursuant to Flood Control Act of 1970. 
As a result of restudy of alternatives, the project 
provides for: (a) widening, straightening and deepening 
about 2.5 miles of existing creek channel including 
the existing by-pass channel in Ellicott Creek 
Park; (b) construction of a diversion channel about 
5,850 feet long between Maple Road and Millersport 
Highway; (c) construction of a diversion channel 
about 1,950 feet long through Pfohl Park; (d) construction 
of a diversion channel about 9,150 feet 
long from Niagara Falls Boulevard upstream to 
about Pfohl Park; (e) construction of 3 highway 
bridges; (f) modification of culverts at Tonawanda 
Creek Road; (g) modification of utilities and drainage 
outlets; and (h) recreation facilities consisting of a 
bike and hike path about 5.4 miles long, with open 
space park areas. The estimated Federal cost of 
existing project is $13,500,000 (Sept. 1985). The estimated 
non-Federal cost is $9,500,000 (Sept. 1985). 
Completion of preconstruction planning and construction 
was authorized Dec. 29, 1981, under Section 
5, P.L. 97-128. 
Local cooperation. For details of local cooperation 
see page 32-22 of Annual Report for 1976. On 
October 25, 1976, the New York State Department of 
Conservation furnished a letter of intent to cooperate 
toward construction of project. On June 22, 1983, a 
formal Local Cooperation Agreement was requested 
from N.Y. State. On January 20, 1984 this agreement 
was fully executed. 
Operations and results during fiscal year. 
New Work: The FY 85 Supplemental Appropriations 
Act (PL 99-88) provided funds to initiate construction 
of the Federal project. In August 1986 a contract for 
the Stage 1 portion of the flood control project was 
awarded. Completion of Stage 1 work is scheduled 
for August 1987. Stage 2 Plans and Specifications 
32-14

BUFFALO, NY DISTRICT 
are being prepared and are 75% completed. Costs for 
FY 86 were $251,543 contract and $253,740 for inhouse 
engineering effort. 
35. MT. MORRIS LAKE, N.Y. 
GENESEE RIVER 
Location. Dam is on Genesee River 66.9 miles 
above river mouth and about 32 miles southwesterly 
of Rochester, N.Y. Reservoir is in Livingston and 
Wyoming Counties, N.Y. (See Geological Survey 
maps of Nunda and Portage, N.Y.) 
Existing project. For description of existing 
project as authorized by 1944 Flood Control Act see 
page 1575 of Annual Report for 1962. New Work for 
completed project cost $23,365,559. In addition $5,000 
contributed funds expended for new work. 
Local cooperation. None required. Local interests 
contributed $5,000 for new work. 
Operations and results during fiscal year. 
Operation and maintenance: Operation and ordinary 
maintenance of dam, reservoir, and service facilities, 
condition and operation studies and miscellaneous 
reports were accomplished by hired labor for 
$365,042. Contract for debris removal cost $221,369. 
Co-Operative Stream Gaging program accomplished 
by U.S. Geological Survey and National Weather 
Service reporting and hydroclimatic network cost 
$103,158. Operation of the Water Control Center cost 
$157,264. Bank erosion study, by contract, was completed 
at a cost of $11,215. Stability analysis, by 
contract, cost $3,158. Engineering and design costs 
of $143,614 were incurred for the preparation of 
specifications for debris removal, annual facility 
inspection, dam safety study, seismic study by 
Waterways Experiment Station, and borings project. 
36. OTTAWA, OHIO 
Location. Ottawa is located on the Blanchard 
River, approximately 22 miles upstream from its 
confluence with the Auglaize River. The Blanchard 
River drains about 765 square miles of the extreme 
southeastern corner of the Maumee River Basin 
which covers about 6,586 square miles in northwestern 
Ohio, northeastern Indiana, and southeastern 
Michigan. (See U.S. Geological Survey map 
for Ottawa, OH). 
Existing project. The project is authorized by 
the Flood Control Act of November 7, 1966. The 
existing project, as recommended in the Preliminary 
Assessment Report dated July 1985, provides for: 
earth levees on both banks of the Blanchard River 
near the west side of the Village totalling 5,300 feet 
in length; about 2,500 feet of channel improvement 
work downstream of the Main Street bridge; snagging 
and clearing betwen the Grand Trunk Western 
bridge and Main Street bridge, and the installation 
of storm sewer check valves at about 190 homes. 
Estimated Federal cost of the project (Oct 85) is 
$952,000. Estimated non-Federal cost is $330,000 (Oct 
85) including a cash contribution of $318,000. 
Local cooperation. The local sponsor, Maumee 
Watershed Conservancy District, will, prior to construction, 
enter into a binding written agreement, 
which addresses project construction and satisfies 
the requirements of Section 221 of Public Law 91- 
611. For details of local cooperation, see page 32-15 
of Annual Report for FY 85. 
Operations and results during fiscal year. 
New Work: The Draft Reevaluation Report was completed 
and sent to Division in August for their review 
and comment at a cost of $142,821. 
37. POINT PLACE, TOLEDO, OHIO 
Location. Point Place is located on a peninsula in 
northeast portion of city of Toledo, Ohio. Its shores 
are bounded on the east by Maumee Bay of Lake 
Erie and on the west by Ottawa River. The peninsula 
extends in a northeasterly direction immediately 
north of mouth of Maumee River. 
Existing project. The project provides for: (a) 
combination of protective structures consisting of 
5,700 linear feet of steel sheet pile wall and 18,700 
feet of levee; (b) three new pumping stations; and (c) 
5,500 linear feet of new storm sewer facilities, including 
2,400 linear feet of gravity outfalls. Estimated 
costs (Oct. 1984) are $9,620,000 Federal and $4,120,000 
non-Federal including a cash contribution of 
$1,180,000. Existing project was authorized by 1972 
Flood Control Act (H.D. 363, 92nd Cong., 2d sess.). 
Local cooperation. For details of local cooperation 
see pages 32-24 and -25 of Annual Report for 
1978. The Local Cooperation Agreement was executed 
by city of Toledo on January 27, 1982. 
Operations and results during fiscal year. 
New Work: Construction to complete 520 linear feet 
of concrete-faced sheetpile wall protection along the 
Ottawa River under the Stage 2c contract was 
completed in Nov. 1985. The entire project was 
completed in June 1986. Total Federal costs for FY 
86 were $56,909 for contract costs, and $52,513 for 
in-house engineering efforts. Non-Federal funds expended 
were $34,397 for contract costs and $22,623 
for in-house engineering effort. 
38. RENO BEACH - HOWARD FARMS 
AREA, OHIO 
Location. Area is located in Lucas County, on the 
south shore of Lake Erie about 15 miles east of 
Toledo, Ohio. (See U.S. Geological Survey Map for 
Reno Beach and Metzger Marsh, OH). 
Existing project. The project, as authorized, 
provides for construction of 8,200 feet of roadway 
seawall, consisting of an earth dike, faced on the 
lakeward side with a quarry-run stone fill; and a 
steel sheet pile floodwall connecting the easterly end 
32-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
of this seawall at Wards Canal to the existing inland 
dike parelleling the canal. Estimated Federal cost of 
new work consisting of reconstructing to a permanent 
project the "Operation Foresight" work which was 
completed in 1973, is $6,290,000 (Oct. 1985). Non- 
Federal cost estimate of $2,095,000 (Oct. 1985) is a 
cash contribution toward first cost of construction 
plus all lands, easements, and rights-of-way. Project 
was authorized under Section 203 of the Flood 
Control Act of 1948. (H.D. 554, 80th Congress, 2nd 
Sess). 
Local cooperation. See page 32-16 of 1982 Annual 
Report for full requirements of local cooperation. A 
Local Cooperation Agreement will be requested upon 
approval of the General Design Memorandum. 
Operations and results during fiscal year. 
New Work: In FY 86 the General Design Memorandum 
and the Plans and Specifications were completed 
at the cost of $17,702, thereby completing the inhouse 
engineering effort. 
39. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed flood control works for 
compliance with Federal requirements were made 
during the period at a cost of $132,563. Total cost to 
Sept. 30, 1986 was $673,442. 
40. NATIONAL EMERGENCY 
PREPAREDNESS 
FY 86 costs were $211,247. 
41. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 32-F. 
42. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
See Table 32-G. 
CONESUS LAKE, LIVONIA, N.Y. 
Location. Conesus Lake is situated in western 
New York State about 25 miles south of the city of 
Rochester. (See U.S. Geological Survey Map, Livonia, 
NY). 
Existing project. Project was authorized for 
construction by the Chief of Engineers pursuant to 
Section 205 of the Flood Control Act of 1948, as 
amended on July 22, 1985. Project provides for a 
steel sheet piling and concrete control structure with 
sluice gates, just upstream of the Route 20A bridge. 
The outlet channel would be aligned immediately 
west of the trailer park. The channel is designed 
with a bottom width of 60 feet and 1V on 3H 
sideslopes. Downstream of the Route 20A bridge, the 
creek will be channelized with a 35-foot bottom width 
and 1V on 3H sideslopes. Downstream of the Route 
20A bridge, the creek will be channelized with a 35- 
foot bottom width and 1V on 3H sideslopes. The 
channel will continue downstream for about one 
mile. Approximately 14 acres of land would be needed 
for acquisition and easements. The non-Federal 
sponsor would be required to enact and enforce flood 
plain management regulations. A 1.2 acre parking 
lot will be provided at the north end of Conesus 
Lake. A small-boat launching platform and an icefishing 
access trail will be constructed. The "Ames 
Parcel" wetland located at the southern end of 
Conesus Lake is used by northern pike during spring 
high water levels as a spawning area. Under the 
mitigation plan, approximately 10 acres of this 
wetland will be shallowly scalped, graded, and revegetated, 
to prevent entrapment of fry and eggs, by 
receding water levels. This plan would provide 25- 
year flood protection and prevent 96 percent of flood 
damages. Estimated Federal cost of the project is 
$867,800 (Oct. 1983). Estimated non-Federal cost is 
$288,630 (Oct. 1983). 
Local cooperation. On September 25, 1985, the 
New York State Department of Environmental Conservation 
agreed to (a) Provide without cost to the 
United States, all lands, easements, and rights-ofway 
necessary for construction and maintenance of 
the project; (b) Hold and save the United States free 
from damages due to the construction, and subsequent 
operation and maintenance of the project, 
except for damages due to the fault or negligence of 
the United States or its Contractors; (c) Accomplish 
without cost to the United States all necessary 
changes to buildings, bridges, including approaches, 
streets, sewers, and utilities, as may be required for 
the construction of the project; (d) Maintain and 
operate without cost to the United States the completed 
works in accordance with regulations prescribed 
by the Secretary of the Army; (e) Enact and 
enforce flood plain management regulations, meeting 
the standards established by the Federal Emergency 
Management Agency for the National Flood Insurance 
Program under the National Flood Insurance 
Act of 1968 and the Flood Disaster Act of 1973; (f) 
Prevent encroachment of any project required flood 
channels and ponding areas, which would decrease 
the effectiveness of the project; (g) At least annually, 
publicize and notify all interested parties that the 
project does not provide protection against floods 
greater than the 25-year flood elevation; (h) Comply 
with the applicable provisions of the Uniform Relocation 
Assistance and Real Property Acquisition 
Policies Act of 1970, Public Law 91-646, approved 
January 2, 1971, in acquiring lands, easements, and 
rights-of-way for construction and subsequent maintenance 
of the project and inform affected persons of 
pertinent benefits, policies, and procedures in connection 
with said Act; (i) Assume all project costs in 
excess of the Federal statutory expenditure limitation 
of $4,000,000; (j) Comply with Section 601 of Title VI 
of the Civil Rights Act of 1964 (PL 88-352) and 
Department of Defense Directive 5500.11 issued pur- 
32-16

BUFFALO, NY DISTRICT 
suant thereto and published in Part 300 of Title 32, 
Code of Federal Regulations in connection with the 
construction, operation, and maintenance of the 
project; (k) Contribute 50 percent of the first cost of 
recreational facilities; including the value of lands, 
easements, and rights-of-way needed for access, 
parking, safety and health purposes, presently estimated 
at $70,000 total Federal and non-Federal 
costs; (1) Maintain, operate, and replace, without cost 
to the United States the recreational facilities, at a 
cost presently estimated at $2,400 annually; and (m) 
Establish rules to control the use, growth and 
development of the recreational facilities, with the 
understanding that public facilities will be open to 
all on equal terms. 
Operations and results during fiscal year. 
New Work: Contract costs were $73,402 Federal. Inhouse 
engineering effort cost $60,853. 
EUCLID CREEK, CLEVELAND, OH 
Location. Euclid Creek has a drainage area of 
approximately 25 square miles and is located east of 
Cleveland in Cuyahoga County and a small portion 
in Lake County, Ohio. (See U.S. Geological Survey 
Map, East Cleveland, OH). 
Existing project. For details of existing project, 
see page 32-14 of the Annual Report for 1983. 
Local cooperation. For details of local cooperation 
requirements, see page 32-13 of Annual Report 
for 1984. 
Operations and results during fiscal year. 
New Work: Construction of project is 99% complete, 
with minor finishing details to be done. Contract 
cost in FY 86 amounted to $98,461. In-house engineering 
effort cost $10,330. 
Flood Control and Coastal Emergencies (Public 
Law 99, 84th Congress, as amended by Sec. 206 of 
Flood Control Act of 1962). 
FY 86 costs for Disaster Preparedness were 
$187,680. Cost for Emergency Operations were 
$19,242. Federal costs for Advance Measures were 
$380,564 and non-Federal costs were $38,033. Two 
Advance Measures projects went to construction in 
FY 86. The project at Eastlake, Lake County, Ohio 
provided for repair to an existing 1,000 foot rubblemound 
dike. Federal costs for the contract were 
$107,312 and non-Federal costs were $38,033. The 
project at Bayview, Erie County, Ohio, provides for 
placement of a 1,400 foot impervious dike along 
Sandusky Bay. Federal costs for the contract were 
$94,085. 
43. DEAUTHORIZED PROJECTS 
See Table 32-H. 
General Investigations 
44. SURVEYS 
During FY 1986, costs of $1,244,186 were incurred 
as shown below: 
Navigation Studies ..................... $451,491 
Flood Damage Prevention Studies ......... 415,192 
Shoreline Protection Studies ..................... 0 
Special Studies ............... ............... 0 
Miscellaneous Investigations ............. 47,851 
Coordination Studies ....... .............. 138,757 
Phase I GDM Studies ........................... 
Comprehensive Studies ................ 185,895 
Review of Authorized Projects ................ 5,000 
45. COLLECTION AND STUDY 
OF BASIC DATA 
During the period, costs of $18,010 were incurred 
in connection with International Water Studies under 
the General Investigations appropriation and 
$383,260 incurred under the Operation and Maintenance 
appropriation for a total cost of $401,250. 
Flood plain management services were performed 
during the year at a cost of $226,403. During the 
year, flood hazard evaluation studies were completed 
for the West Branch of Silver Creek in the Village of 
South Russell, Geauga County, OH and Flat Rock 
Creek in the Village of Paulding, Paulding County, 
OH. A flood damage study of the Tonawanda Channel 
of the Upper Niagara River was also completed. 
The study will assist the New York Power Authority 
in developing a better understanding of the threshold 
water levels at which flood damages' may occur. The 
information will enable the NYPA to provide early 
warning of impending floods. Hundreds of technical 
assistance requests regarding flood plain matters 
were completed during the year responding to individuals, 
corporations, banks, insurance agents and 
other agencies. Costs for general hydrologic studies 
were $2,132. 
46. ADVANCE ENGINEERING AND 
DESIGN 
Costs during the period were $167,467 for advance 
engineering and design projects. For details of individual 
projects, see sections 10, 36 and 38 in text. 
47. CONTINUATION OF PLANNING 
AND ENGINEERING 
Costs during the period were $357,089 for continuation 
of planning and engineering. For details 
of individual projects, see sections 30 and 31 in text. 
32-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 32-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Funding FY 83 FY 84 FY 85 FY 86 Total Cost to 
Text Project Sept. 30, 1986 
1. Ashtabula Harbor, 
Ohio 
2. Black Rock Channel 
and Tonawanda 
Harbor, N.Y. 
(Federal Funds) 
(Contrib. Funds) 
3. Buffalo Harbor, 
N.Y. 
4. Cattaraugus Harbor, 
N.Y. 
(Federal Funds) 
(Contrib. Funds) 
5. Cleveland Harbor, 
Ohio 
6. Conneaut Harbor, 
Ohio 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
- - - - 12,805,3391 
- - - - 12,805,3391 
770,000 253,762 732,518 304,500 9,855,446 
673,834 435,196 757,638 325,492 9,835,471 
-100,000 
55,760 
- 6,077,000 
5 - 6,077,000 
- - 310,000 310,000 11,135,1202 
- - 310,000 310,000 11,135,1202 
1,065,000 1,502,215 2,423,821 2,869,826 33,735,2103 
820,815 1,688,268 2,463,803 2,718,745 33,541,8983 
- 620,000 
- 250,000 159,998 
620,000 
409,998 
- - - - 23,115,1874 
- - - - 23,115,1874 
470,000 980,715 2,222,000 1,610,000 51,099,5156 
1,033,360 947,421 2,043,936 1,764,633 51,002,8746 
- - - - 295,457 
- - - - 295,457 
951,560 -197,000 
954,186 -192,556 
- 956 
- 956 
192,500 50,029 
- 242,593 
422 
1,425 
1,425 
- 4,804,060 
157 4,804,060 
93,141 
49,039 
95,522 
51,420 
- 2,566,529 
- 2,566,529 
- - 15,000 178,000 31,846,2996 
- - - 193,000 31,846,2996 
6,169,500 4,472,125 2,942,000 3,050,000 139,346,4857 
4,477,275 6,057,166 3,265,105 3,088,149 139,277,6857 
9,492 
- 2,915,000 2,895,000 16,104,903 
- 2,109,110 3,646,340 16,050,353 
- 8,346,6418 
- 8,346,6418 
1,165,000 901,700 
1,074,711 979,729 
54,000 651,000 9,124,1029 
97,511 633,847 9,106,7369 
- 651,850 
- 651,850 
32-18

BUFFALO, NY DISTRICT 
TABLE 32-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Funding FY 83 FY 84 FY 85 FY 86 Total Cost to 
Text Project Sept. 30, 1986 
7. Dunkirk Harbor, 
N.Y. 
(Federal Funds) 
(Contrib. Funds) 
8. Erie Harbor, Pa. 
9. Fairport Harbor, OH 
10. Geneva-on-the-Lake, 
Ohio 
(Federal Funds) 
(Contrib. Funds) 
11. Great Sodus Bay 
Harbor, N.Y. 
12. Huron Harbor 
Ohio 
(Federal Funds) 
(Contrib. Funds) 
13. Irondequoit Bay 
N.Y. 
(Federal Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
229,335 
216,150 
2,588,000 
332,770 
11,161 
20,124 
72,944 
2,020,193 
9,338 
13,523 
- 3,010,02410 
- 3,010,02410 
35,095 1,712,870 
34,406 1,712,144 
- 1,950,00011 
- 1,950,00011 
- 3,597,87312 
- 3,597,87312 
-12,685 353,185 14,846,75513 
301,108 296,835 14,790,40513 
- - - - 1,154 
- - - - 1,154 
- - - - 2,959,61114 
- - - - 2,959,61114 
675,500 692,469 760,500 267,000 13,037,672 
595,053 783,369 764,300 263,177 13,031,840 
- 15,000 215,000 
- - 92,221 
- - 750,000 
- - 64,036 
- 10,925 
- 7,500 
706 
4,131 
892,000 
754,221 
750,000 
64,036 
- 610,9591s 
- 610,95915 
7,500 2,374,403 
7,398 2,374,301 
- - - - 713,544 
- - - - 713,544 
- - - - 5,103,79516 
- - - - 5,103,79516 
447,000 1,047,523 465,000 600,000 14,826,926 
444,078 996,446 530,980 598,849 14,808,825 
- - - - 247,030 
- - - - 247,030 
- - - - 63,079 
- - - - 63,079 
135,800 1,060,000 1,450,000 25,000 3,535,800 
65,534 838,951 1,747,319 -166,925 3,337,011 
32-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 32-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Funding FY 83 FY 84 FY 85 FY 86 Total Cost to 
Text Project Sept. 30, 1986 
(Contrib. Funds) 
14. Little Sodus Bay 
Harbor, N.Y. 
15. Lorain Harbor, 
Ohio 
(Federal Funds) 
(Contrib. Funds) 
16. Oak Orchard 
Harbor, N.Y. 
17. Ogdensburg Harbor, 
N.Y. 
(Federal Funds) 
(Contrib. Funds) 
18. Olcott Harbor 
N.Y. 
19. Port Ontario 
Harbor, N.Y. 
(Federal Funds) 
(Contrib. Funds) 
20. Rochester Harbor, 
N.Y. 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
- 1,200,000 
- 7,637 
- 12,289 
- 1,308 
- 11,000 
- 9,560 
- 1,389,500 2,589,500 
788,368 1,589,224 2,385,229 
62 
11,043 
- 301,39417 
- 301,39417 
3,000 3,042,569 
2,803 3,047,372 
- 742,822 
- 742,822 
70,000 575,000 21,395,55818 
43,839 263,456 21,056,41318 
1,397,000 1,421,000 906,000 1,124,000 23,236,429 
1,377,008 1,271,705 1,064,095 1,093,955 23,192,013 
- 660,000 
- 14,198 
660,000 
14,198 
- 1,586,99619 
- 1,586,99619 
- 1,436 
- 1,436 
924,000 
47,211 
788 
1,017 
35,000 
135,076 
24,062 
- 150,000 
317,647 703,736 
- 3,801 
- 3,801 
22,000 
50,585 6,205 
-25,717 
85,297 
191,518 
191,518 
- 1,720,46620 
5,406 1,720,46620 
26,823 1,357,00721 
21,893 1,352,07721 
210 
57,000 
57,000 
- 140,21022 
- 140,21022 
- 76,804 
- 69,019 
-12,464 
-4,679 
526,24823 
526,24823 
- 14,47724 
- 14,47724 
- 10,000 160,000 
- - 59,808 
- - 270,000 
980,00025 
869,80825 
270,000 
- 2,439,30826 
- 2,439,30826 
32-20

BUFFALO, NY DISTRICT 
TABLE 32-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Funding FY 83 FY 84 FY 85 FY 86 Total Cost to 
Text Project Sept. 30, 1986 
21. Rocky River, 
Ohio 
22. Sandusky 
Harbor, Ohio 
23. Toledo Harbor, 
Ohio 
24. Vermilion 
Harbor, Ohio 
25. Wilson Harbor 
N.Y. 
29. Lakeview Park, 
Lorain, Ohio 
(Federal Funds) 
(Contrib. Funds) 
31. Presque Isle 
Peninsula, Erie, Pa. 
(Federal Funds) 
(Contrib. Funds) 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
1,721,000 1,795,000 
1,106,232 2,069,140 
98,000 1,828,000 16,642,81627 
422,623 1,734,843 16,528,01627 
- 343,494 
- 343,494 
6,298 
7,237 
25,004 628,768 
14,432 397,652 
3,951 2,231,036 
245,580 2,230,977 
- - - - 6,727,27028 
- - - - 6,727,27028 
919,000 716,240 909,000 813,000 13,685,439 
916,506 683,523 956,276 813,049 13,685,333 
- - - - 675,606 
- - - - 675,606 
- - - - 17,191,84229 
- - - - 17,191,84229 
3,482,500 4,586,188 3,999,000 3,320,000 73,807,05330 
3,540,127 4,037,727 4,632,667 3,367,229 73,771,93930 
- - - - 1,156,11831 
- - - - 1,156,11831 
-- 17,839 543,670 
- 17,839 502,128 
- 265,885 
- 264,586 
22,737 
25,000 
7,108 24,927 
- 10,700 
- 9,239 
-23,903 1,928,219 
17,639 1,928,219 
- 139,775 
- 139,775 
- 535,24632 
- 535,24632 
3,695 
4,994 
489,25133 
489,25133 
- 1,741,125 
22 1,741,074 
1,412 
739,700 
739,651 
740,000 990,000 1,160,000 1,085,000 12,670,562 
741,242 426,294 1,708,859 1,101,511 12,667,932 
- 1,092 
- 1,092 
44 
44 
4,978 
4,978 
368,175 373,254 497,143 497,143 5,805,712 
307,785 1,656 870,230 529,863 5,779,529 
32-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 32-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Funding FY 83 FY 84 FY 85 FY 86 Total Cost to 
Text Project Sept. 30, 1986 
33. Lakeshore Park 
Ashtabula, Ohio 
(Federal Funds) 
(Contrib. Funds) 
34. Ellicott Creek, 
N.Y. 
35. Mt. Morris 
Lake, N.Y. 
Genesee River 
37. Point Place, 
Toledo, Ohio 
(Federal Funds) 
(Contrib. Funds) 
42. Conesus Lake, 
Livonia, N.Y. 
(Federal Funds) 
(Contrib. Funds) 
42. Euclid Creek, 
OH 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
195,000 
199,957 
81,438 
61,000 
73,709 
939 -2,808 
85,000 
13,739 
- -12,293 
3,187 14,745 
21,494 
871,844 
797,775 
- 249,707 
- 249,707 
15,000 865,000 2,760,000 
-239 505,283 2,384,130 
- - - - 23,365,55934 
- - - - 23,365,55934 
1,035,000 965,000 856,000 990,000 10,891,309 
784,649 1,042,141 999,826 1,004,820 10,854,469 
2,300,000 2,000,000 3,500,000 117,000 9,916,000 
1,348,602 3,149,683 3,512,573 109,421 9,905,490 
300,000 690,000 740,000 
15,150 290,895 1,408,243 
55,000 
25,462 
32,000 
59,834 
45,320 1,775,320 
57,021 1,771,309 
35,000 448,000 
24,443 134,255 
- 35,000 
2,220,000 
78,324 
- 390,000 
1,541,480 992,579 
990,000 
663,993 
35,000 
90,000 3,252,000 
108,791 3,222,085 
32-22

BUFFALO, NY DISTRICT 
TABLE 32-A (Continued) 
1. Includes $565,192 for previous projects. Excludes 
$47,000 contributed funds. 
2. Includes $58,027 for previous projects. 
3. Includes $4,922 emergency relief authority administrative 
costs transferred from new work to maintenance 
upon conversion to programming and budgeting system 
July 1, 1953, by direction of Office, Chief of Engineers. 
Also includes appropriations and costs under appropriation 
titles 96x3123 Operation and Maintenance and 96x5125 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
4. Includes $4,277,586 for previous projects. Excludes 
expenditures of $239,305 for work authorized by Section 
107. 
5. Includes $1,883,647 for previous projects. Excludes 
$446,805 contributed funds. 
6. Includes $1,564,154 for previous project and appropriations 
and costs of $16,596 for modification authorized 
for construction under authority of Sec. 107, 1960 R&H 
Act. 
7. Includes appropriations and costs under appropriation 
titles 96x3123 Operations and Maintenance and 
96x5125 Maintenance and Operation of Dams and Other 
Improvements of Navigable Waters. Excludes $201,960 
contributed funds. 
8. Includes $805,272 for previous projects. 
9. Includes $39,784 for previous projects. 
10. Includes $811,250 for previous projects. Excludes 
$11,000 contributed funds. 
11. Includes $176,520 for previous projects. 
12. Includes $736,967 for previous projects. 
13. Includes $104,900 for previous projects. Excludes 
$154,500 contributed funds. 
COST AND FINANCIAL STATEMENT 
14. Includes $368,940 for previous projects. 
15. Includes $361,772 for previous projects. 
16. Includes $269,789 for previous projects. 
17. Includes $232,328 for previous projects. 
18. Includes $292,203 for new work for previous projects. 
Excludes $3,000 contributed funds. Also excludes 
appropriation and cost of $29,570 under authority of 
Section 107, 1960 R&H Act. 
19. Excludes $224,702 contributed funds. 
20. Includes $271,380 for previous projects. 
21. Includes $130,512 for previous projects. 
22. Includes $140,210 for previous projects. Excludes 
$1,500 contributed funds. 
23. Includes $38,959 for previous projects. Excludes 
$5,000 contributed funds. 
24. Excludes $186,000 Public Works Acceleration Act. 
25. Includes $50,000 for previous projects. 
26. Includes $247,794 for previous projects. 
27. Includes $617,529 for previous projects and $478 
emergency relief authority administration costs transferred 
from new work to maintenance upon conversion to programming 
and budgeting system, July 1, 1953, by direction 
of Office, Chief of Engineers. 
28. Includes $477,149 for previous projects. Excludes 
$325,000 contributed funds. 
29. Includes $1,624,695 for previous projects. 
30. Includes $16,914 for previous projects. 
31. Excludes $740,679 contributed funds. 
32. Includes $57,342 for previous projects. Excludes 
$166,998 contributed funds. 
33. Includes $16,914 for previous projects. 
34. Excludes $5,000 contributed funds. 
32-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 32-B AUTHORIZING LEGISLATION 
Acts Work Authorized 
June 3, 1896 
Mar. 3, 1905 
June 25, 1910 
Mar. 2, 1919 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Sept. 3, 1954 
July 14, 1960 
Oct. 27, 1965 
Aug. 11, 1888 
June 3, 1896 
June 13, 1902 
June 13, 1902 
Aug. 8, 1917 
Mar. 3, 1905 
July 27, 1916 
Mar. 2, 1919 
Mar. 2, 1945 
Sept. 22, 1922 
ASHTABULA HARBOR, OHIO (See Section 1 of Text) 
Construction of breakwater. 
Enlarge outer harbor by extending west breakwater and 
constructing new east breakwater; pierheads on lakeward 
ends of breakwaters; and remove part of old east breakwater. 
Extend west breakwater to shore; dredge outer harbor to a 
depth of 20 feet. 
Remove portion of east breakwater, extend breakwaters to 
present project dimensions and dredging restrictions in 
portion of west basin. 
Dredge channel through outer harbor, channel of approach 
to Penn Central Co. slip, channel Ashtabula River, to 
and in turning basin all to present project dimensions; 
remove portion of old east inner breakwater and maintenance 
to 24-foot depth of portion of outer harbor. 
Extend river channel to present project limit. 
Dredging approach channel and turning basin in east 
outerharbor to 25-foot depth. 
A depth of 29 feet in soft and 30 feet in hard material in 
entrance channel to just inside outer ends of breakwaters; 
thence 28 feet in soft and 29 feet in hard material in a 
channel to inner breakwater; thence 27 feet in soft and 
28 feet in hard material in a channel extending to Penn 
Central Co. slip and extending 2000 feet up Ashtabula 
River; 22 feet in hard material in turning area; and 28 
feet in soft and 29 feet in hard material in areas adjacent 
to 250-foot section of inner breakwater when that section 
is removed as now authorized. 
Dredging approach, channel and turning basin in east 
outer harbor to 28 feet in soft material and 29 feet in 
hard material. 
BLACK ROCK CHANNEL AND TONAWANDA 
HARBOR, N.Y. (See Section 2 of Text) 
Dredging channel through Horseshoe Reef at outlet of Lake 
Erie and Tonawanda Inner Harbor, to 16 feet. 
Deepening Tonawanda Creek to 16 feet. 
Dredging channel from Buffalo outer harbor to foot of 
Maryland St., Buffalo, to 21 feet. 
Dredging channel from foot of Maryland St., Buffalo, to 
natural deepwater pool upstream from Tonawanda Harbor 
to 21 feet; construction of ship lock and bridge; and 
repair of Bird Island pier and towpath wall. 
Dredging channel along Tonawanda Island, with turning 
basin at its downstream end at the foot of the Island, to 
21 feet. 
Dredging triangular area at junction with Buffalo north 
entrance channel. 
Widening channel at foot of Maryland St., Buffalo. 
Annual Report, 1895, p. 
2132. 
H. Doc. 654,61st Cong., 2d 
sess. 
H. Doc. 997, 64th Cong., 1st 
sess. 
H. Doc. 43, 73rd Cong., 1st 
sess. 
Rivers and Harbors Committee 
Doc. 78, 74th 
Cong., 2d sess. 
H. Doc. 321, 77th Cong., 1st 
sess. 
H. Doc. 486, 83d Cong., 2d 
sess. 
H. Doc. 148, 86th Cong., 1st 
sess. 
H. Doc. 269, 89th Cong., 1st 
sess. 4 
H. Ex. Doc. 83, 50th Cong., 
1st sess. Annual Report, 
1888, p. 2066, and 
Annual Report, 1897, pp. 
3116-3120. 
H. Doc. 143, 56th Cong., 1st 
sess., and Annual Report, 
1900 p. 4152. 
H. Doc. 125, 56th Cong., 
2d sess., and Annual 
Report, 1901, p. 3343. 
H. Doc. 428, 58th Cong. 
2d sess. 
H. Doc. 658, 63rd Cong., 2d 
sess. 
H. Doc. 1004, 65th Cong., 
2d sess. and H. Doc. 
92, 79th Cong., 1st sess. 
H. Doc. 981, 66th Cong., 3d 
sess. 
32-24 
Documents

BUFFALO, NY DISTRICT 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1925 
June 26, 19345 
Aug. 30, 19356 
Mar. 2, 1945 
Sept. 3, 1954 
May 20, 1826 
June 23, 1866 
June 23, 1874 
June 3, 1896 
Mar. 3, 1899 
Mar. 3, 1909 
June 6, 1900 
June 13, 1902 
Mar. 2, 1907 
Mar. 2, 190710 
June 25, 1910 
July 25, 1912 
Mar. 2, 1919 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 193511 
Aug. 30, 1935 
Mar. 2, 194511 
July 14, 1960 
Widening canal south of International Bridge and removal 
of westerly end of Rattlesnake Island shoal. 
Operation and care of improvements provided for with 
funds from War Department appropriations for rivers 
and harbors. 
Removal of rock shoals in Lake Erie entrance to canal, and 
in canal south of Ferry Street Bridge, to 22 feet; enlargement 
of North Tonawanda turning basin; extension of 
Bird Island pier; improvement of guide pier at the lock; 
and elimination of upper 150 feet of Tonawanda Creek 
channel from the project.7 
Widening Lake Erie entrance to canal. 
Deepen lower 1,500 feet of Tonawanda inner harbor and 
enlarge turning basin. 
BUFFALO HARBOR, N.Y. (See Section 3 of Text) 
Construction of south pier (extended in 1868) 9 
Construction of old breakwater. 9 
Extension of old breakwater. 9 
Stony Point and south breakwater. 9 
North breakwater. 9 
Deepening entrance channel to inner harbor and removing 
rock shoal therein. 
Dredging at entrance to canals at South Buffalo in outer 
harbor.' 
South entrance breakwater. 9 
Extension of Federal project to Commercial St. and removal 
of Watson elevator site.9 
Deepening areas A, B, and D in outer harbor to 21 feet, and 
area C in north entrance to 23 feet. 
Deepening areas F and G in outer harbor to 21 feet. 
Removal of shoal between entrance channel to Buffalo 
River and Erie Basin to 21 feet. 
Deepening areas H, I, and K in outer harbor to 21 feet. 
Extension of south entrance and south breakwaters, deepening 
outer harbor to present project dimensions, and 
removal of shoals on approach to south entrance. 
Maintenance of channels in Buffalo River and Buffalo ship 
canal to 21 feet in cooperation with city of Buffalo. 
Deepening North and Buffalo River entrance channels, and 
deepening and maintaining Buffalo River and Buffalo 
ship canal to present project dimensions. 
Deepening approach to south entrance channel to 30 feet; 
deepen to 30 feet in outer area and 29 feet in inner area of 
south entrance channel; and deepen to 28 feet southerly 
part of outer harbor. 
H. Doc. 289, 68th Cong., 1st 
sess. 
H. Doc. 28, 73d Cong., 1st 
sess. 
H. Doc. 92, 79th Cong., 1st 
sess. 4 
H. Doc. 423, 83d Cong., 2nd 
sess.4, 8 
Annual Report, 1868, pp. 
222 and 232. 
Annual Report, 1868, pp. 
232-236. 
Annual Report, 1876, pt. 2, 
pp. 569 and 573. 
Annual Report, 1895, p. 
3153. 
H. Doc. 72, 55th Cong., 1st 
sess., and Annual Report, 
1897, p. 3245. 
Specified in acts. 
Specified in act. 
H. Doc. 240, 59th Cong., 1st 
sess. 
H. Doc. 298, Rivers and 
Harbors Committee Doc. 
2, 61st Cong., 2d sess. 
H. Doc. 550, 62d Cong., 2d 
sess. 
H. Doc. 1139, 64th Cong., 
1st sess. 
H. Doc. 481, 68th Cong., 2d 
sess. 
Rivers and Harbors 
Committee Doc. 1, 71st 
Cong., 1st sess. 
H. Doc. 46, 73d Cong., 1st 
sess. 
Rivers and Harbors 
Committee Doc. 54, 74th 
Cong., 1st sess. 
H. Doc. 352, 78th Cong., 1st 
sess. 
H. Doc. 151, 86th Cong., 1st 
sess. 
32-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Dec. 15, 1980 
Mar. 3, 1875 
Aug. 5, 1886 
Aug. 11, 1888 
June 3, 1896 
Mar. 3, 1899 
June 13, 1902 
Mar. 2, 1907 
June 25, 1910 
July 27, 1916 
Aug. 8, 1917 
Aug. 29, 1937 
Aug. 30, 193512 
Aug. 30, 193511 
Mar. 2, 194514 
July 24, 1946 
Deepening portion of outer harbor to 27 feet over a width of 
500 feet for 2,500 feet northward from 28-foot project 
area, widening within 1,700 feet to limits within 150 feet 
of breakwater axis and 75 feet from harbor line and 
continuing within these limits for 7,000 feet. Elimination 
of 25-foot wide strip between presently authorized and 
proposed easterly dredging limits. Elimination of easterly 
50-foot wide undredged strip in existing 23-foot depth 
project area, extending northerly from 27-foot depth area 
to Buffalo River entrance channel. Previously authorized 
but uncompleted portions of work authorized by 1935 act, 
combined with this act as a single improvement. 
Removal of abandoned abutments of South Michigan Avenue 
bridge. 
CLEVELAND HARBOR, OHIO (See Section 5 of Text) 
West breakwater 
Part of east breakwater. 9 
Extension of east breakwater. 9 
Reconstruction of piers. 9 
Dredging channel between piers and outer harbor to depth 
of 19 feet; dredging to depth of 23 feet in any portion of 
harbor in discretion of Secretary of War. 
Arrowhead breakwater and extension of east breakwater. 
Removal of deflecting arm of old east breakwater and 
closure of gap between old and new east breakwaters. 
Pierhead at easterly end of east breakwater. 
Maintenance and improvement of channels in Cuyahoga 
and Old Rivers to a depth of 21 feet to a point 2,000 feet 
upstream from Clark Ave. viaduct and 18-foot turning 
basin. 
Deepening outer harbor and channel between piers to 
present project dimensions, construction of 400-foot spur 
breakwater at gap in shore arm of west breakwater; 
removal of easterly 150 feet of west main breakwater; 
elimination from project of a 298-foot southerly extension 
of west pier; and abandonment of inner 932 feet of shore 
arm of west breakwater. 
Maintenance dredging in Cuyahoga and Old Rivers for 1 
year as an emergency measure. 
Maintenance of extension of Cuyahoga River channel. 
Extension, maintenance, and improvement to a depth of 21 
feet of Cuyahoga River channel to present project 
limit.15, 1 
Improvement of Cuyahoga and Old Rivers to a depth of 23 
feet and replacement or pier construction of 7 railroad 
bridges. 2 
H. Doc., 451, 87th Cong., 2d 
sess. 
Section 107, 1960 River 
and Harbor Act. 
Annual Report, 1876, p. 558. 
H. Ex. Doc. 116, 48th Cong., 
2d sess., and Annual 
Report, 1886, p. 1865. 
H. Ex. Doc, 189, 50th Cong., 
2nd sess., and Annual 
Report, 1888, p. 2005. 
H. Doc. 326, 54th Cong., 1st 
sess., and Annual Report, 
1896, p. 2949. 
H. Doc. 156, 55th Cong., 3d 
sess., and Annual Report, 
1899, pp. 3075 and 3078. 
H. Doc. 118, 56th Cong., 2d 
sess. 
No Printed report 
H. Doc. 891, 63d Cong., 2d 
sess. 
H. Doc. 707, 63d Cong., 2d 
sess., and Rivers and 
Harbors Committee Doc. 
84, 74th Cong., 2d sess. 
H. Doc. 477, 72d Cong., 2d 
sess. 
Rivers and Harbors 
Committee Doc. 39, 74th 
Cong., 1st sess. 
Specified in act. 
H. Doc. 95, 79th Cong., 1st 
sess. 
H. Doc. 629, 79th Cong., 2d 
sess. 
32-26

BUFFALO, NY DISTRICT 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 
July 14, 1960 
Oct. 23, 1962 
Dec. 6, 1966 
Oct. 22, 1976 
(Sec. 175) 
Deepening channel 25 feet through east basin of outer 
harbor; replacement of Erie-Lackawanna Railroad bridge 
over Cuyahoga River at mile 4.1 and widening of channel 
at that point, with elimination of reconstruction of east 
pier of bridge as previously authorized; and replacement 
of Baltimore & Ohio Railroad Bridge over Old River near 
its mouth and Willow Avenue Highway Bridge about 800 
feet above mouth and widening channel at four locations 
along lower 2,000 feet of river.3 
Depth of 29 feet in lake approach to main entrance; 28 feet 
in entrance channel to lakeward ends of piers at mouth 
of Cuyahoga River; 27 feet in river to a point just above 
its junction with Old River, and in Old River to upstream 
limit of present 23-foot project; 28 feet in west basin 
within existing project limits as modified to eliminate a 
triangular area at west end and to extend limits to a line 
parallel to and 75 feet from harbor line; and 28 feet in 
westerly 800 feet of east basin. 25 
An area in east basin 27 feet deep extending about 3,800 
feet easterly of 28-foot area with project limits 380 feet 
from east breakwater and on landward side generally by 
a line 75 feet lakeward of and parallel to harbor line. A 
dock channel to Nicholson Cleveland Terminal Co. pier, 
at easterly end of east basin, from 25-foot contour to a 
limit 75 feet north of pierhead line, 400 feet wide at 
shoreward end and flared toward the lake. 
Deepening upper end of Old River channel from 21 to 27 
feet. 
Preparation of Phase I design memorandum for improvements 
consisting of removal of portions of entrance 
breakwater: construction of breakwater extension of east 
entrance; deepening approach and entrance channels; 
construction of diked disposal area; and, installation of 
recreational fishing facilities on west breakwater. 
CONNEAUT HARBOR, OHIO (See Section 6 of Text) 
Extension of east breakwater, construction of new west 
breakwater removal of portion of old west breakwater, 
and dredging of outer harbor to 19 feet. 
Realinement of west breakwater, removal of remainder of 
old west breakwater, and deepening outer harbor to 20 
feet. 
Removal of Bessemer & Lake Erie R.R. Co. of inner 635 feet 
of west pier. 
Removal of a portion of west breakwater; extension of 
breakwaters to present project dimensions; construction 
of pierheads on outer ends of breakwaters; deepening 
outer harbor to present project dimensions; removal of 
portions of river pier, and elimination from project of a 
255-foot shoreward extension of west breakwater. 
Deepening easterly part of outer harbor to 28 feet in soft 
material and 29 feet in hard material; deepening remaining 
triangular area of outer harbor to 22 feet in soft 
material and 23 feet in hard material; deepening inner 
harbor for 2,450 feet upstream of outer end of west pier to 
27 feet in soft material and 28 feet in hard material; 
removal of east pier, extension of east breakwater to 
shore; and an access channel 8 feet deep in outer harbor 
to city dock. Previously authorized but uncompleted 
portion of work authorized by 1917 and 1935 acts combined 
with this act for accomplishment as a single 
improvement. 
32-27 
H. Doc. 107, 85th Cong., 1st 
sess. 
H. Doc. 152, 86th Cong., 1st 
sess. 
H. Doc. 527, 87th Cong., 2d 
sess. 4 
Sec. 107, 1960 River and 
Harbor Act. 
H. Doc. 653, 61st Cong., 2d 
sess. 
H. Doc. 983, 64th Cong., 1st 
sess. 
H. Doc. 48, 73d Cong., 1st 
sess. 
H. Doc. 415, 87th Cong., 2d 
sess. 
June 25, 1910 
Aug. 8, 1917 
17 
Aug. 30, 193511 
Oct. 23, 1962

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Nov. 7, 19668 
Mar. 2, 1827 
Mar. 2, 1867 
June 3, 1896 
June 25, 1910 
June 30, 1948 
Dec. 15, 1970 
(House Public 
Works Comm.) 
June 22, 1971 
(Senate Public 
Works Comm.) 
Sec. 201 of F.C. 
Act of 1965 
May 26, 1824 
Mar. 3, 1899 
June 15, 1910 
Nov. 28, 192220 
Aug. 30, 1935 
Mar. 2, 1945 
Sept. 3, 1954 
July 14, 1960 
Recreational small-boat harbor provided by: a stone dike 
about 2,200 feet long: access channels 6 feet deep, 2,800 
feet long and 100 feet wide; closing of 100-foot gap in 
existing west breakwater; and personnel guard rail on 
west breakwater. 
DUNKIRK HARBOR, N.Y. (See Section 7 of Text) 
Construction of west pier. 9,' 8 
Breakwater and excavation of entrance channel to 13 feet." 
Deepening of entrance channel and harbor basin to a depth 
suitable for vessels of 16-foot draft. 
Removal of rock reef bordering the inner entrance channel. 
Deepening outer entrance channel to present project depths; 
removal of rock shoal on the west side of the entrance 
channel to a depth of 17 feet, and changed limits of the 
inner entrance channel and basin to present project 
dimensions. 
Construction of small boat harbor. 
ERIE HARBOR, PA. (See Section 8 of Text) 
Breakwaters and piers; dredging entrance channel; and 
brushwood protection of beach of Presque Isle Peninsula. 9 
Deepening channel and harbor basin to 18 feet; repair and 
extension of piers; and plant growth and.emergency 
protection work on peninsula. 
Deepening channel and part of harbor to 20 feet. 
Reconveyed Presque Isle Peninsula to the State of Pennsylvania 
for park purposes. 
Deepening, widening, and straightening entrance channel, 
dredging channel at easterly end of harbor basin, deepening 
a portion of harbor basin, all to present project 
dimensions; elimination of north breakwater from project; 
and limitation of south breakwater to a length of 1,200 
feet. 
Protection of the peninsula south of the waterworks settling 
basin. 
Widen 25-foot deep approach channel to ore dock. 
Depth of 29 feet in the entrance channel to a point opposite 
the inner end of the north pier; thence 28 feet in soft and 
29 feet in hard material in the remainder of the entrance 
channel, within the general limits of the 25-foot basin 
and inner channel opposite the ore dock except as 
modified to eliminate from the project a triangular area 
along the easterly side; and a depth of 28 feet over a 300- 
foot westward extension of the 25-foot basin. 27 
H. Doc. 484, 89th Cong., 2d 
sess. 4 
S. Ex. Doc. 42, 35th Cong., 
1st sess., and Annual 
Report, 1866 pt. IV, 
p. 155 
Annual Report, 1871 p. 214 
H. Doc. 63, 54th Cong., 1st 
sess. 
H. Doc. 720, 61st Cong., 2d 
sess. 4 
H. Doc. 632, 80th Cong., 2d 
sess. 
H. Doc. 91-423, 91st Cong., 
2d sess. 
Annual Report, 1915, p. 
1965. 
H. Doc. 70, 55th Cong., 1st 
sess. and Annual Report, 
1896, p. 3237.19 
Rivers and Harbors 
Committee Doc. 26, 61st 
Cong., 2d sess. 
H. Doc. 52, 73d Cong., 1st 
sess. 
Specified in act. 
H. Doc. 345, 83d Cong., 2d 
sess. 
H. Doc. 199, 86th Cong., 1st 
sess.4 
32-28

BUFFALO, NY DISTRICT 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Mar. 3, 182521 
June 3, 1896 
Mar. 3, 1905 
Mar. 2, 1919 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 193522 
Aug. 26, 1937 
July 24, 1946 
July 14, 196028 
May 10, 1977 
(House Public 
Works Comm.) 
Oct. 1, 1976 
(Senate Public 
Works Comm.) 
Sec. 201 of F.C. 
Act of 1965 
Mar. 2, 1829 
Aug. 2, 1882 
Depth of 27 feet in soft material and 28 feet in hard material 
in approach area to Duquesne Marine Terminal. Previously 
authorized but uncompleted portion of work 
authorized by 1935 act is combined with this act as a 
single improvement. 
FAIRPORT HARBOR, OHIO (See Section 9 of Text) 
Construction of piers. 
Breakwaters and dredging outer harbor to a depth of 18 
feet. 
1,400-foot extension of east breakwater, present project 
dimension of east pier; and deepening of harbor to 19 
feet. 
4,000-foot extension of east breakwater at limit of cost to 
the United States of $715,000. 
Deepening of outer harbor and entrance channel to present 
project dimensions; extending the west breakwater to 
present project dimensions with pierhead at its outer 
end; removal of west pier; and construction of bulkhead 
on west side of river channel. 
Dredging of 21- and 24-foot river channels and turning 
basin in Grand River to present project dimensions. 
Dredging of 8-foot river channel. 
Depth of 29 feet in the approach channel from the lake; a 
depth of 28 feet over a width of 800 feet in the outer 
harbor; a depth of 27 feet in soft and 28 feet in hard 
material in Grand River, over a width of 200 feet to the 
upstream limit of the turning basin, with suitable widening 
at the bends, thence over widths reducing from 200 to 
100 feet to the upstream limit of the existing Federal 
project, except in the 8-foot channel; enlargement of the 
turning basin, including deepening of the entire basin to 
21 feet; and minor modification of the existing project 
limits in the outer harbor. 
Construction of small boat harbor. 
GREAT SODUS BAY HARBOR, N.Y. (See Section 11 
of Text) 
Construction of piers and breakwater. 9 
Extension of piers to 15-foot contour in the lake. 
H. Doc. 340, 87th Cong., 2d 
sess. 4 
Annual Report, 1889, pp. 
2147-2153 
H. Doc. 347, 54th Cong., 1st 
sess. and Annual Reports, 
1896, p. 2956; 1903, p. 
2084; 1905, p. 2349. 
H. Doc. 206, 63d Cong., 1st 
sess. 
H. Doc. 592, 69th Cong., 2d 
sess., Rivers and Harbors 
Committee Doc. 13, 70th 
Cong., 1st sess. 
H. Doc. 472, 72d Cong., 2d 
sess. 
Rivers and Harbors 
Committee Doc. 79, 74th 
Cong., 2d sess.4 
H. Doc. 706, 79th Cong., 2d 
sess.4 
H. Doc. 347, 86th Cong., 2d 
sess. 4 
H. Doc. 627, 94th Cong., 2d 
sess. 
Annual Report, 1876, pt. II 
p. 589. 
Annual Report, 1881, p. 
2442. 
32-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1925 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1905 
Mar. 2, 1919 
Aug. 30, 193522 
Oct. 23, 1962 
Aug. 30, 1852 
June 23, 1866 
Mar. 3, 1871 
Mar. 3, 1881 
June 13, 1902 
Mar. 3, 1899 
Mar. 2, 1907 
June 25, 1910 
Aug. 8, 1917 
Aug. 8, 1917 
July 3, 1930 
Aug. 30, 1935 
Deepening and widening of channel to 18-foot depth and 
150-foot width. 
Widening channel lakeward of piers to 250 feet. 
Dredging channel to present project dimensions. 
HURON HARBOR, OHIO (See Section 12 of Text) 
Extension of west pier; construction of east breakwater; 
removal of part of old east pier; deepening of channel to 
19 feet; and dredging of sheltered area. 
Widening river to 200 feet; removal of remainder of old east 
pier; construction of new spur pier; enlargement of sheltered 
area; and closure of breach at shore end of west 
pier. 
Extension of west pier with pierhead at its outer end; 
removal of outer end of east breakwater and constructing 
pierhead on new outer end; widening and deepening 
channel to present project dimensions; enlargement of 
turning basin at head of channel; shore protection west 
of west pier, and elimination from project construction of 
spur pier and dredging sheltered area outside channel 
limits. 
Depths of 29 feet in approach channel, 28 feet in entrance 
channel, 27 feet in river channel, 21 feet in turning 
basin, a detached breakwater, 1,575 feet long 2,000 feet 
lakeward of outer end of existing west pier; and, 
abandonment of lakeward end of existing approach 
channel. 29 
LITTLE SODUS BAY HARBOR, N.Y. (See Section 14 
of Text) 
West entrance pier 9 
Extension of west pier and construction of west breakwater, 
and dredging channel to 12 feet deep, 400 feet wide.9 
East pier and east breakwater. 9 
Extension of piers lakeward to 15.5-foot contour, and dredging 
channel to 15.5 feet. 
Extension of east pier 300 feet lakeward. 
LORAIN HARBOR, OHIO (See Section 15 of Text) 
Breakwaters and extensions of pies to present dimensions. 
Extend 18-foot channel from inner end of piers to Erie 
Avenue Bridge. 
Extend breakwaters and dredge to depth of 19 feet in outer 
harbor. 
Extend breakwaters to present project dimensions. 
Deepen outer harbor and river channel to Erie Avenue 
Bridge to 20 feet. 
Extend 20-foot channel to American Shipbuilding Co. drydock 
2. 
Widen 2 bends in river and enlarge turning basin opposite 
National Tube Co. dock. 12 
H. Doc. 192, 68th Cong., 1st 
sess. 
Rivers and Harbors 
Committee Doc. 17, 70th 
Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 23, 72d 
Cong., 1st sess. 
H. Doc. 122, 58th Cong., 2d 
sess. 
H. Doc. 5, 63d Cong., 1st 
sess. 
H. Doc. 478, 72d Cong., 2d 
sess. 
H. Doc. 165, 87th Cong., 1st 
sess.4 
Annual Report, 1874, p. 256. 
Annual Report, 1874 p. 256. 
Annual Report, 1871, p. 234 
Annual Report, 1881, pp. 
2444 and 2446. 
Annual Report, 1901, 
p. 3364 
H. Doc. 131, 55th Cong., 2d 
sess., and Annual Report 
1898, p. 2718 
H. Doc. 560, 60th Cong., 1st 
sess. 
H. Doc. 644, 61st Cong., 2d 
sess. 
H. Doc. 980, 64th Cong., 1st 
sess. 
H. Doc. 985, 64th Cong., 1st 
sess. 
H. Doc. 587, 69th Cong., 2d 
sess. 
H. Doc. 469, 72d Cong., 2d 
sess. 
32-30

BUFFALO, NY DISTRICT 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935 
Aug. 30, 1935 
Mar. 2, 1945 
July 14, 1960 
Oct. 2, 1965 
June 25, 1910 
Mar. 2, 1919 
Aug. 30, 193511 
Apr. 20, 1983 
Mar. 2, 1867 
Mar. 4, 1913 
Mar. 2, 1829 
Aug. 2, 1882 
June 25, 1910 
Aug. 30, 19356 
Mar. 2, 1945 
Approach channel to municipal pier. 
Deepen outer harbor and river channel to American Shipbuilding 
Co. drydock 2 to present project dimensions and 
extension of river channel to upper end of National Tube 
Co. dock with turning basin opposite that dock. Maintenance 
dredging in Black River from American Shipbuilding 
Co. drydock 2 upper end of National Tube Co. 
dock was authorized Apr. 7, 1934, by Public Works 
Administration. 
Enlarging turning basin opposite National Tube Co. dock 
to present project dimensions. 
Turning basin in bend of Black River immediately upstream 
from Baltimore & Ohio RR coal dock. 
Replace Norfolk and Western Railway swing bridge with a 
vertical lift bridge; construct two detached arrowhead 
breakwaters lakeward of existing breakwaters; construct 
extension of east breakwater to shore; remove 300 feet of 
lakeward end of west breakwater; remove outer 1,100 feet 
of east pier; deepen lake approach to 29 feet, 800-foot 
wide outer harbor channel to 27 feet; widen river channel 
at bends; and construct a new turning basin 21 feet deep 
near upstream limit of existing project.3o 
Construct bank of stabilization works at cut numbered 1 
along left bank of river channel above Erie Avenue 
Bridge.8 
OGDENSBURG HARBOR, N.Y. (See Section 17 of 
Text) 
Deepening the several channels to 19 feet. 
Widening upper entrance channel to 400 feet, and city front 
to 350 feet. 
Enlarging and deepening lower basin to 21 feet, and removal 
of elevator wharf. 
Extend Lower East Entrance Channel, 600 feet west of 
existing pier to a depth of 27 feet below LWD. Dredged 
material to be disposed of in dredged disposal area site 5, 
owned by Ogdensburg Bridge and Port Authority. 
OLCOTT HARBOR, N.Y. (See Section 18 of Text) 
Dredging a channel 11 feet deep betwen parallel piers. 9 
Deepening channel to 12 feet and maintenance of west pier. 
ROCHESTER HARBOR, N.Y. (See Section 20 of Text) 
Construction of piers.9 
Extension of piers to 15 foot contour in the lake. 
Concrete superstructure on piers. 9 
Deepening channel to 20 feet. 
Dredging of the entrance channel and turning basin, and 
the elimination of the inner ends of the east and west 
piers, all to present project dimensions. 
Maintenance of the existing channel upstream of the Penn 
Central Co. bridge. 
Senate Committee print, 
73d Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 51, 74th 
Cong., 1st sess. 
Specified in act. 
H. Doc. 161, 77th Cong. 
1st sess. 
H. Doc. 166, 86th Cong., 
1st sess. 4 
PL 89-298. 
H. Doc. 920, 60th Cong., 
1st sess. 
H. Doc. 663, 64th Cong., 
1st sess. 
H. Doc. 266, 72d Cong., 
1st sess. 4 ,24 
Section 107, 1960 
River and Harbor Act 
Annual Report, 1866, pt. III, 
p. 15 and pt. IV, p. 158. 
H. Doc. 780, 62d Cong., 
2d sess. 4 
Annual Report, 1874, p. 247 
Annual Report, 1881, p. 2437 
Annual Report, 1905, p. 
2383 
H. Doc. 342, 61st Cong., 
2d sess. 
H. Doc. 484, 72d Cong., 
2d sess. 
H. Doc. 139, 76th Cong., 
1st sess. 
32-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 14, 1960 
June 10, 1872 
Aug. 26, 1937 
Oct. 27, 1965 
Mar. 3, 1899 
June 13, 1902 
Mar. 2, 1919 
Jan. 21, 1927 
Aug. 30, 193526 
Mar. 2, 1945 
July 14, 1960 
Mar. 3, 1899 
June 25, 1910 
Depth of 24 feet in the channel from the lake to the west 
pier; a depth of 23 feet between the piers and in the lower 
river to the Penn Central Co. bridge, including the 
existing turning basin; a depth of 21 feet from the bridge 
to the upstream project limit, with suitable widening at 
the bends; and, upstream turning basin 21 feet deep and 
650 feet wide adjacent to the improved channel, with two 
mooring dolphins. 
ROCKY RIVER HARBOR, OHIO (See Section 21 of 
Text) 
East pier and dredging of channel. 
Extension of east pier and deepening channel to present 
project dimensions. 
Realign and extend channel and construct an anchorage 
basin. 
SANDUSKY HARBOR, OHIO (See Section 22 of Text) 
Construction of channel protection works. 
Widening of straight and dock channels and deepening to 
19 feet. 
Extension of east jetty to total length of 6,000 feet, with 
pierhead on outer end; deepening of the outer, straight, 
and easterly portion of dock channels to 21 feet, and 
westerly portion of dock channel to 20 feet. 
Deepening of dock channel to 22 feet. 
Enlargement of turning basin and construction of rock 
dike. 
Maintenance of bay channel to 22 feet; and elimination 
from project of portion of turning basin and rock dike. 
Extending Moseley channel and deepening that channel 
and the outer end of Straight channel to 26 feet, from 
deep water in the lake to the vicinity of Cedar Point 
dock; widening the bend at the junction of the Moseley 
and Straight channels and deepening to 26 feet; deepening 
the Straight Channel to 25 feet from the vicinity of 
Cedar Point dock to junction with Bay channel; deepening 
the Bay channel from junction with the Straight channel 
to the outer end of the Pennsylvania Coal dock No. 3 to 
25 feet, thence from outer end of the coal dock to the 
turning basin to 24 feet in soft material and 25 feet in 
hard, with no Federal dredging within 50 feet of the 
dock; and enlarging the turning basin, including removal 
of approximately 300 feet of the rock dike, and deepening 
to 24 feet in soft material and 25 feet in hard. 
TOLEDO HARBOR, OHIO (See Section 23 of Text) 
A channel 400 feet wide and 21 feet deep from 25-foot 
contour in Maumee Bay to Fassett Street Bridge, 200 feet 
wide and 19 feet deep above that point and a 500-foot 
turning basin at Upper End. A stone revetted earth dike 
in Maumee Bay Channel. 
Act 1899 modified to insure a navigable channel to 21 feet 
from Fassett Street Bridge to Lake. 
H. Doc. 409, 86th Cong., 
2d sess.4 
Annual Report, 1871, p. 211 
H. Doc. 70, 75th Cong., 
1st sess. 
H. Doc. 352, 88th Cong., 
2d sess. 4 
H. Doc. 362, 55th Cong., 
2d sess., and Annual 
Report 1898, p. 2708 
H. Doc. 120, 56th Cong., 
2d sess. 
H. Doc. 982, 64th Cong., 
1st sess. 
H. Doc. 584, 69th Cong., 
2d sess. 
Rivers and Harbors 
Committee Doc. 2, 73rd 
Cong., 1st sess. 
H. Doc. 328, 76th Cong., 
1st sess. 
H. Doc. 144, 86th Cong., 
1st sess. 4 
H. Doc. 198, 55th Cong., 2d 
sess. and Annual Report 
1898, p. 2693 
H. Doc. 865, 60th Cong., 
1st sess. 
32-32

BUFFALO, NY DISTRICT 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935 
May 17, 1950 
Sept. 3, 1954 
July 3, 1958 
July 14, 1960 
July 4, 1836 
Mar. 3, 1875 
Mar. 3, 1905 
July 3, 1958 
Mar. 2, 1945 
Aug. 13, 1968 
Sept. 3, 1954 
July 14, 1960 
Mar. 7, 1974 
Oct. 22, 1976 
(Sec. 101) 
Channel 25 feet deep and 500 feet wide from 25-foot contour 
to mouth of Maumee River (300 feet wide on each side of 
center dike in Bay Channel), thence 400 feet wide to 
Fassett Street Bridge, 200 feet wide above that point and 
a turning basin at Upper End 18 feet deep. 
Widening at bend of mouth of River opposite Chesapeake 
and Ohio Railway Dock. 
Removal of center dike in Maumee Bay Channel. 
Enlarge widening at bend opposite Chesapeake and Ohio 
dock and turning basin opposite American Shipbuilding 
Co. dock. 
Deepen Bay Channel including widenings to 28 feet, deepen 
River channels to New York Central Railroad Bridge to 
27 feet and construct new turning basin below Anthony 
Wayne Bridge.3 ' 
VERMILION HARBOR, OHIO (See Section 24 of Text) 
Parellel piers and dredging channel to 8 feet deep. 
Deepening of channel to 12 feet. 
Reconstruction of piers. 
New entrance formed by two overlapping arrowhead breakwaters 
and extension of existing river channel upstream 
to Liberty St. Bridge. 
WILSON HARBOR, N.Y. (See Section 25 of Text) 
Entrance channel 80 feet wide and 8 feet deep; and restore 
east and west piers. 
Extend existing channel 300 feet; and construct new channel 
3,800 feet long through Tuscarora Bay. 
PRESQUE ISLE PENINSULA, ERIE, PA. 
(See Section 31 of Text) 
Construction of groin system, seawall, bulkhead, placement 
of beach material at waterworks reservation and along 
remainder of peninsula; removal of portions of existing 
structures. 
Periodic nourishment of shore for a 10-year period. 
Periodic nourishment of shore for a 5-year period. 
Preparation of Phase I design memorandum for improvements 
consisting of construction of five sections of spaced 
off-shore breakwaters and replenishment of beach area 
with sandfill. 
Rivers and Harbors 
Committee Doc. 21, 72d 
Cong., 1st sess. 
H. Doc. 189, 81st Cong., 
1st sess. 
H. Doc. 620, 81st Cong., 
2d sess. 
H. Doc. 436, 84th Cong., 
2d sess. 
H. Doc. 153, 86th Cong., 
1st sess. 4 
Annual Report, 1880 
Annual Report, 1874, p. 219 
H. Doc. 252, 58th Cong., 
2d sess. 
H. Doc. 231, 85th Cong., 
1st sess. 
H. Doc. 679, 76th Cong., 
3d sess. 
H. Doc. 112, 90th Cong., 
1st sess. 
H. Doc. 231, 81st Cong., 
1st sess. 
H. Doc. 397, 86th Cong., 
2d sess. 
H. Doc. 796, 93d Cong., 
2d sess. 
32-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 32-B (Continued) 
1. Authorized by Public Works Administration, Sept. 
6 1933. 
2. Widening Cuyahoga River downstream at end of 
Cut 4 classified inactive. 
3. Replacement of bridges 19 and 32, widening 
Cuyahoga and Old River Channels, classified deferred. 
4. Contains latest published map. 
5. Permanent Appropriations Repeal Act. 
6. Authorized May 28, 1935 by Emergency Relief 
Administration Act of 1935. 
7. Improvement of guide pier at Black Rock Lock was 
deauthorized by Congress in August 1977. 
8. Classified deferred. 
9. Completed under previous projects. 
10. Also Sundry Civil Act of Mar. 3, 1905. 
11. Authorized in part by Public Works Administration, 
Sept. 6, 1933. 
12. Authorized by Public Works Administration Sept. 
6, 1933. 
13. Previously authorized by Public Works Administration. 
14. First Deficiency Appropriation Act approved April 
1, 1944. 
15. Authorized by Defense Plant Corp., May 19, 1942. 
16. Deepening left half of channel extension was 
eliminated from project by 1962 R&H Act. 
AUTHORIZING LEGISLATION 
17. Permit of Secretary of War, Aug. 5, 1927. 
18. Modified 1828 and 1852. 
19. Extension of north pier portion of this modification 
was deauthorized Nov. 81. 
20. Public Law 366. 
21. Modified 1830, 1881, and 1890. New work completed 
under previous projects. 
22. Partly included in Public Works Administration 
program, Nov. 15, 1933. 
23. First Supplemental National Defense Appropriation 
Act, 1944, approved Dec. 23, 1943. 
24. Removal of remaining hard-material shoals in 
lower basin is classified inactive. 
25. Deepening remainder of Cuyahoga River from 
bridge 1 to and including Old River, classified deferred. 
26. Included in Public Works Administration program, 
Nov. 15, 1933. 
27. Deepening strips adjacent to north and south piers 
was deauthorized Aug. 82. 
28. Modification classified inactive. 
29. Construction of breakwater classified deferred. 
30. Deepening and widening remainder of Black River 
channel at Cut 1 classified deferred. 
31. The 27-foot project extended 2,800 feet and turning 
basin relocated under authority of Chief of Engineers. 
32-34

BUFFALO, NY DISTRICT 
TABLE 32-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 27 of Text) 
Cost to September 30, 1986 
For Last 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Barcelona -Harbor, N.Y. 1985 1,185,85318 1,921,187 
Big (Cunningham) Creek, Ohio' _2 19,7633 
Black River Harbor, N.Y.4 -2 42,401 - 
Cape Vincent Harbor, N.Y. 1962 275,082 1,562,244 
Cattaraugus Creek, N.Y.5 .2 57,410 - 
Elk Creek Harbor, Pa. 1978 101,500 - 
Grasse River (Massena), N.Y. 4, 7 1891 9,0003 - 
Hamlin Beach Harbor, N.Y. 6 1973 72,052 - 
Kelleys Island, Ohio 197415 129,874 - 
Little River at 
Cayuga Island, N.Y.9 1969 46,8048 42,393 
Morristown Harbor, N.Y. 9 1949 6,221 9,69412 
Niagara Remedial Works, N.Y. 9,'0 1966 6,069,395 510,819 
Niagara River, N.Y. 9,' 6 1964 559,45711 141,059 
Oswego Harbor, N.Y. 1985 8,430,01619 5,969,81520 
Ottawa River Harbor, Michigan 
and Ohio14 197715 99,000 - 
Port Bay, N.Y. - - - 
Port Clinton Harbor, Ohio 1985 71,950 909,869 
Pultneyville Harbor, N.Y.'3 1934 68,219 20,087 
Put in Bay, Ohio 195115 51,609 12,720 
Sackets Harbor, N.Y. 1982 25,010 24,023 
Sandusky River, Ohio4 1894 58,0003 557 
West Harbor, Ohio9 1985 7,098,89817 35,103 
1. No commerce reported. 
2. Only information available is in index to reports of 
Chief of Engineers. 
3. Amount includes maintenance; not separable. 
4. Abandonment recommended in H. Doc. 467, 69th 
Cong., 1st sess. 
5. Abandonment recommended in Ex. Doc. 16, 35th 
Cong., 1st sess. 
6. Project classified deferred. 
7. Channel improved by local interests. 
8. Includes local interests contribution of $25,742. 
9. Completed. 
10. Costs of operation and maintenance of this project 
will be settled directly by concerned power agencies. No 
further appropriations will be made to this project. 
11. Includes local interests contribution of $27,563. 
12. Includes local interests contribution of $5,000. 
13. Abandonment recommended in H. Doc. 375, 64th 
Cong., 1st sess. 
14. Project classified inactive. 
15. Annual Report for Detroit District. 
16. Construction of compensating works as authorized 
by 1930 R&H Act was deauthorized by Congress in August 
1977. 
17. Includes local interests contribution of $3,795,000. 
18. Includes $56,616 for previous projects. Excludes 
$181,500 contributed funds. 
19. Includes $1,187,977 for previous projects. 
20. Includes $945,684 for previous projects. Excludes 
$307,590 for rehab. 
32-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 32-D NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
(See Section 28 of Text) 
Navigation Activities Pursuant to Section 107, Public Law 86-645 
(Preauthorization) 
Study Identification Fiscal Year Cost 
Beaver Creek, OH $ 7,500 
Chimney Bluffs State Park, Huron, NY 2,500 
Edgewater Marina, Cleveland, OH 12,525 
Huron Harbor, OH 5,796 
Lake Erie, Harbor Creek, PA 7,500 
Lake Erie, North East, PA 7,500 
Lake Erie, Sheffield, OH 5,653 
Lake Erie, Sturgeon Point, NY 96,898 
Little River, Niagara Falls, NY 42,064 
Long Point State Park, NY 2,500 
NFTA-Sm Boat Hbr. Buffalo, NY 449 
Seneca Lake, Watkins Glen, NY 6,246 
Toussaint River, Carrol Twsp, OH 30,939 
Wards Canal, Jerusalem Twp, OH 7,500 
TABLE 32-E OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
(See Section 32 of Text) 
For Last 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Cleveland and Lakewood, Ohio: 
Edgewater Park' 
White City Park' 
Fair Haven Beach State Park, 
Lake Ontario, N.Y. 2 
Fort Niagara State Park, N.Y. 3 
Hamlin Beach State Park, N.Y.5 1976 $1,769,600 - 
Selkirk Shore State Park, 
Lake Ontario, N.Y.4 1963 58,978 $2,946 
1. Project authorized by River and Harbor Act of 
September 3, 1954 is classified as deferred. 
2. Project authorized by River and Harbor Act of July 
3, 1958 is classified as deferred. 
3. Project authorized under provisions of Section 201, 
1965 Flood Control Act has been reclassified to active. 
4. Federal participation was limited to one-third of 
first cost when project was authorized by 1954 River and 
Harbor Act. Federal participation was changed from onethird 
to 70 percent of remaining work under Public Law 
87-874. Uncompleted portion of project is classified as 
deferred. 
5. Project completed. 
32-36

BUFFALO, NY DISTRICT 
TABLE 32-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 41 of Text) 
For Last 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Auburn, N.Y. Owasco Outlet1 1962 371,9856 
Batavia and vicinity, Tonawanda Creek, N.Y.1 1957 335,385 - 
Caledonia, Genesee River, N.Y. 1950 - - 
Camp Perry, Ohio' 1967" 275,00010 
Cayuga Creek, Cheektowaga, N.Y.' 1984 1,404,500 - 
Chittenango Creek and tributaries, N.Y.2,3 1948 12,464 - 
Cuyahoga River Basin, Ohio 1985 1,117,000 - 
Dansville and vicinity, Canaseraga Creek, N.Y. 1985 490,300 - 
Eastlake, Ohio, Chagrin River3 1976 506,344 - 
Fremont, Ohio, Sandusky River' 1976 8,589,8249 - 
Ithaca, N.Y., Cayuga Inlet, N.Y.' 1978 3,929,33012 
Lackawanna, N.Y., Smokes Creek' 1971 3,542,0687 - 
Lancaster, Cayuga Creek, N.Y.' 1954 797,300 - 
Marsh Creek, Geneva, N.Y.5 - 226,429 - 
Montour Falls, Oswego River Basin, N.Y.' 1954 1,681,785 - 
Onondaga Creek, Nedrow, N.Y.',5 1964 330,231 - 
Owasco Inlet and Outlet, Montville and Dry 
Creek, State Ditch and Crane Brook, N.Y.4 1950 281,559 - 
Red Creek, N.Y.3 1975 361,241 - 
Scajaquada Creek, N.Y.' 1985 4,944,852 - 
Syracuse, Oswego River Basin, N.Y.' 1954 3,349,248 - 
Warsaw, N.Y., Oatka Creek',5 1969 558,3178 - 
Wellsville, N.Y., Genesee River' 1978 3,145,30313 
1. Completed. 
2. Local interests required to contribute $25,000. 
3. Project not considered economically justified and is 
inactive. 
4. Inactive portion of work for State Ditch has been 
done by local interests and work on Crane Brook has been 
deferred at the request of local interests. 
5. Project authorized by Chief of Engineers. 
6. Excludes costs of $188,732 under Public Law 84-99, 
Flood Control and Coastal Emergencies Appropriation, 
incurred for project rehabilitation as a result of damages 
due to storm Agnes, June 1972. 
7. Includes local interests contribution of $50,000. 
8. Excludes costs of $26,807 under Public Law 84-99, 
Flood Control and Coastal Emergencies Appropriation, 
incurred for project rehabilitation as a result of damages 
due to storm Agnes, June 1972. 
9. Includes local interests contribution of $6,944. Excludes 
costs of $383,786 under Public Law 84-99, Flood Control 
and Coastal Emergencies Appropriation, for emergency 
restoration of levees damaged during 1973. 
10. Includes local interests contribution of $125,000. 
11. Annual Report for Detroit District. 
12. Includes local interests contribution of $99,000. 
Excludes costs of $104,005 under Public Law 84-99, Flood 
Control and Coastal Emergencies Appropriation, incurred 
for project rehabilitation as a result of damages due to 
storm Agnes, June 1972. 
13. Includes local interests contribution of $50,000. 
Excludes costs of $374,042 under Public Law 84-99, Flood 
Control and Coastal Emergencies Appropriation, incurred 
for project rehabilitation as a result of damages due to 
storms. 
32-37

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 32-G FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 42 of Text) 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Congress as amended (preauthorization) 
Study Identification 
Butternut Creek, Dewitt, NY 
Canadaigua Lake, NY 
Cazenovia Creek, Buffalo, NY 
Chagrin River, Willoughby Hills, OH 
Chittenango Creek, Sullivan, NY 
Keuka Lake Outlet, NY 
Limestone Creek, Fayetteville, NY 
Maumee River, Defiance, OH 
Oneida Creek, Oneida, NY 
Plum Creek, Columbia Station, OH 
Sandusky River, Fremont, OH 
Swan Creek, Toledo, OH 
W. Br. Limestone Creek, Manlius, NY 
Fiscal Year Cost 
$103,183 
48,615 
28,120 
239 
22,487 
91,902 
194 
27,136 
55,841 
36,502 
1,000 
69,340 
12,935 
Snagging and clearing of navigable streams and tributaries in interest 
of flood control. (Sec. 208, 1954 Flood Control Act, PL 780, 83rd Cong.) 
Project and location Fiscal Year Cost 
Blanchard River, Ottawa, OH $3,231 
Emergency bank protection (Sec. 14 of 1946 Flood Control Act, 
Public Law 526, 79th Cong.) 
Study Identification Fiscal Year Cost 
Baker Creek, Bridge No. 2-7, Allen, NY $ 700 
Black Creek, County Home, Angelica, NY 1,500 
Blanchard River, Ottawa, OH 1,383 
Chagrin River, East Branch, Baldwin Rd., OH 17,438 
Chagrin River, East Branch, SR 615, OH 3,737 
Chagrin River, Gates Mills, OH 298 
Cold Creek, Bridge No. 13-4, Hume, NY 700 
Cuyahoga River, Akron, OH (Bridge) 476 
Cuyahoga River, Akron, OH (Sewer) 202,5001 
Geneva, SR 531, OH 134,061 
Lake Erie, Beachview Dr., OH 7,500 
Rogers Cemetery, Amity, NY 408 
Rush Creek, Bridge No. 20-14, Angelica, NY 1,500 
Rush Creek, Bridge No. 2-1, Allen, NY 3,100 
Seneca Lake, Watkins Glen, NY 9,352 
Seneca River, Seneca Falls, NY 9,957 
Wendt Beach Pk, Evans, NY 276 
1. Does not include $315,886 in contributed funds. 
32-38

BUFFALO, NY DISTRICT 
TABLE 32-H DEAUTHORIZED PROJECTS 
(See Section 43 of Text) 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Black Rock Channel and 
Tonawanda Harbor, NY 
1935 R&H Act 1962 Aug 1977 - 
Black Rock Channel and 
Tonawanda Harbor, NY 
1954 R&H Act 1962 May 1981 - 
Crane Creek State Park, OH 
1962 R&H Act 19683 Nov 1979 - - 
Erie Harbor, PA 1945 R&H Act 1963 Aug 1977 - - 
Erie Harbor, PA 1899 R&H Act 1963 Nov 1981 - - 
Erie Harbor, PA 1960 R&H Act 1963 Aug 1982 - - 
Grandview Bay Harbor, NY 
1945 R&H Act 1948 Aug 1977 $ 1,524 
Great Sodus Bay Harbor, NY 
1962 R&H Act 1963 Aug 1977 - 
Hammondsport, Oswego River 
Basin, NY 1941 FC Act 1951 Nov 1983 29,000 
Ithaca, NY-Cascadilla Creek 
1941 FC Act 1950 Aug 1977 8,159 
Ithaca, NY-Fall Creek 
1941 FC Act 1950 Aug 1977 12,300 
Maumee River, above Toledo, OH 
1872 Act 19713 Nov 1977 12,000 
Niagara River, Compensating Works, 
NY 1930 R&H Act 1964 Aug 1977 - - 
Oswego Harbor, NY 1940 R&H Act2 1963 May 1981 - - 
Sackets Harbor, NY 
1945 R&H Act 1948 May 1981 19,010 
Sheffield Lake Community Park, 
OH 1962 R&H Act - Aug 1977 - - 
Watkins Glen, NY 1941 FC Act 1958 Aug 1977 43,182 - 
1. Extension of guide pier only; other improvements 
completed. 
2. Deepening of west outer harbor, other improvements 
completed. 
3. Annual Report for Detroit District. 
32-39

LOS ANGELES, CA, DISTRICT * 
This district (total area, about 230,000 square miles) 
comprises those drainage basins tributary to the Pacific 
Ocean that are in California between the Mexican 
boundary and Cape San Martin (about 265 miles north 
of entrance to Los Angeles Harbor); lower Colorado 
River drainage basin (below Lee Ferry, AZ), which is in 
southeastern California, southeastern Nevada, southwestern 
Utah, and all of Arizona, except the northeastern 
corner; that part of the Great Basin that is in 
southern Nevada and southeastern California; and the 
United States parts of those small drainage basins in 
southern Arizona that drain southward into Mexico. 
IMPROVEMENTS 
Navigation Page 
1. Los Angeles and Long Beach 
Harbors, CA ...................... 33-2 
2. Morro Bay Harbor, CA .............. 33-2 
3. Oceanside Harbor, CA ............ . 33-2 
4. Santa Barbara Harbor, CA ........... 33-2 
5. Ventura Marina (Ventura 
Harbor), CA ........................ 33-3 
6. Reconnaissance and condition 
surveys ............................. 33-3 
Beach Erosion Control 
7. Imperial Beach, San Diego 
County, CA ......................... 33-3 
Flood Control 
8. Alamo Lake, Bill Williams 
River, AZ .......................... 33-3 
9. Cucamonga Creek, Santa Ana 
River Basin, CA .................... 33-3 
10. Gila River Basin, AZ: ............... 33-4 
10A. Painted Rock Dam (Gila 
River), AZ .......................... 33-4 
10B. Phoenix, AZ, and vicinity 
(including New River) ............... 33-4 
10C. Tucson diversion channel, 
AZ ................................... 33-5 
10D. Whitlow Ranch Dam, Queen 
Creek, AZ .......................... 33-5 
11. Los Angeles County drainage 
area, CA ............................ 33-5 
12. Los Coches Creek, San Diego 
County, CA ......................... 33-6 
13. Lytle and Warm Creeks, Santa 
Ana River Basin, CA ................ 33-6 
14. Mojave River Dam, Mojave 
River Basin, CA .................... 33-6 
15. Pine and Mathews Canyons Dams, 
Colorado River Basin, NV ............ 33-7 
16. Santa Ana River Basin (and 
Orange County), CA ................ 33-7 
Flood Control (Cont'd) Page 
17. Sweetwater River, Sweetwater 
River Basin, CA ...................... 33-7 
18. West Magnesia Canyon channel, 
Rancho Mirage, CA ................. 33-7 
19. Inspection of completed flood 
control projects ...................... 33-7 
20. Scheduling flood control reservoir 
operations ........................... 33-7 
21. Flood control work under 
special authorization ................ 33-8 
General Investigations 
22. Surveys ............................. 33-8 
23: Collection and study of basic 
data ................................. 33-8 
24. Research and development ............ 33-8 
25. Continuation of planning 
and engineering ...................... 33-8 
25A. Holbrook levee, Little Colorado 
River, Colorado River Basin, AZ ....... 33-8 
25B. Santa Ana River main stemincluding 
Santiago Creek and Oak 
Street Drain, Santa Ana River 
Basin, CA ............................ 33-8 
26. Advance engineering and 
design ................................ 33-8 
Goleta, CA, and vicinity, 
Santa Barbara County .............. 33-8 
Tables 
Table 33-A 
Table 33-B 
Table 33-C 
Table 33-D 
Cost and financial 
statement .................... 33-10 
Authorizing 
legislation .................. 33-14 
Other authorized 
navigation projects .......... 33-18 
Other authorized 
beach erosion 
control projects .............. 33-18 
33-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Tables (Cont'd) Page 
Table 33-E Other authorized flood 
control projects ............... 33-19 
Table 33-F Not applicable 
Table 33-G Deauthorized projects ........ 33-21 
Table 33-H Reconnaissance and 
condition surveys ............ 33-22 
Table 33-I Los Angeles County 
drainage area, CA: Latest 
approved estimated first 
costs for all units of 
improvement under 
existing project .............. 33-22 
Table 33-J Santa Ana River Basin 
(and Orange County), CA: 
Latest approved estimated 
Federal first cost for all 
units ......................... 33-24 
Table 33-K Inspection of completed 
flood control projects ......... 33-24 
Table 33-L Flood control work under 
special authorization ......... 33-25 
1. LOS ANGELES AND LONG BEACH 
HARBORS, CA 
Location. On coast of southern California in San 
Pedro Bay about 25 miles south of City of Los Angeles, 
about 96 miles northwest of San Diego Harbor, and 
about 410 miles southeast of San Francisco Harbor. 
(See Coast and Geodetic Survey Chart 5147.) 
Previous projects. For details, see page 1977 of 
Annual Report for 1915 and page 1646 of Annual 
Report for 1938. 
Existing project. For details, see page 33-3 of Annual 
Report for 1984. 
Local cooperation. All items of local cooperation 
required under the terms of the previous authorizing 
acts have been fully complied with. See page 33-3 of 
Annual Report for 1981 for requirements under the 
terms of the 1976 Water Resources Development Act. 
Terminal facilities. In Los Angeles Harbor, 81,673 
feet of wharves, of which 74,849 feet are owned by the 
city and 6,824 feet are owned by private interests. In 
Long Beach Harbor, 58,985 feet of wharves, of which 
51,775 feet are owned by the city and 7,210 feet are 
owned by private interests. In Long Beach Harbor, 
Federal Government owns 19,700 feet of waterfront 
inside the Navy mole, exclusive of finger piers. 
Operations during fiscal year. Initiated and completed 
maintenance repair (phase 3) of San Pedro 
breakwater in September 1986 at a cost of $1,128,600 
regular funds. In addition, a reconnaissance and condition 
survey was conducted at a cost of $54,849. 
2. MORRO BAY HARBOR, CA 
Location. On coast of southern California 110 miles 
south of Monterey Bay, 120 miles northwest of Santa 
Barbara Harbor, and nearly midway between San 
Francisco and Los Angeles. (See Coast and Geodetic 
Survey Chart 5387.) 
Existing project. For details, see page 33-4 of Annual 
Report for 1980. 
Local cooperation. Fully complied with. None required 
under rehabilitation plan. 
Terminal facilities. Facilities, which are adequate 
for existing commerce, comprise 640 feet of existing 
piers constructed by Navy; 550 feet of piers and 150 feet 
of floating docks constructed by San Luis Obispo 
County; 263 feet of floating docks constructed by California 
Department of Parks and Recreation; 1,396 feet 
of floating docks constructed by City of Morro Bay; 
1,398 feet of privately owned piers; and 5,435 feet of 
privately owned floating docks. 
Operations during fiscal year. Completed maintenance 
repair of north breakwater (phase 2) in November 
1985 at a cost of -$6,835 regular funds. In addition, a 
reconnaissance and condition survey was conducted at a 
cost of $89,893. 
3. OCEANSIDE HARBOR, CA 
Location. On coast of southern California at Oceanside, 
about 30 miles north of City of San Diego. (See 
Coast and Geodetic Survey Chart 5101.) 
Existing project. For details, see page 33-4 of Annual 
Report for 1981. 
Local cooperation. Fully complied with for maintenance 
to date. 
Terminal facilities. Berthing for 915 boats (750 
single-tie slips, 46 double-tie slips, and 119 side-ties, of 
which 47 are visitors slips); 12 dry storage spaces at 
Oceanside Marine Center; a fuel dock; a boat hoist; a 
launching ramp, which can accommodate 4 launchings 
at the same time; parking for 1,732 cars, with temporary 
parking for about 141 boat trailers; a boat-repair 
facility; a pump-out facility; a Coast Guard cutter; 
restaurants; retail stores; yacht brokers; a boatel/motel; 
condominiums; and a sport-fishing facility. 
Operations during fiscal year. Awarded contract 
for and initiated maintenance dredging, which is about 
73 percent complete, at cost of $813,739 regular funds 
and $610,779 Navy funds. Continued construction of 
second contract for experimental sand bypass system, 
pump facilities and power system, which is about 62 
percent complete. Cost for construction was $3,134,943 
regular funds. 
4. SANTA BARBARA HARBOR, CA 
Location. On coast of southern California 90 miles 
northwest of Los Angeles Harbor and 320 miles southeast 
of San Francisco Harbor. (See Coast and Geodetic 
Survey Chart 5261.) 
Existing project. For details, see page 33-4 of Annual 
Report for 1983. 
33-2

LOS ANGELES, CA, DISTRICT 
Local cooperation. See page 1015 of Annual Report 
for 1969 for items of local cooperation under 1962 
authorized modification of existing project. 
Terminal facilities. A wharf 2,000 feet long; a pier 
325 feet long in harbor for tie-up mooring for Coast 
Guard cutter; a landing float; an open mooring and slip 
anchorage for small craft; and a launching ramp for 
small craft. 
Operations during fiscal year. Completed maintenance 
dredging in September 1986 at a cost of 
$486,627 regular funds. 
5. VENTURA MARINA (VENTURA 
HARBOR), CA 
Location. On coast of southern California about 65 
miles northwest of the City of Los Angeles, about 70 
miles northwest of Los Angeles and Long Beach Harbors, 
and about 6 miles northwest of Channel Islands Harbor. 
Existing project. For details, see page 33-5 of Annual 
Report for 1981.. 
Local cooperation. Fully complied with. 
Terminal facilities. Two fuel docks; guest berthing 
docks; 3 boat-repair facilities, 1 full service with a 60- 
ton travelift, 1 full service with a 150-ton marine 
elevator, and 1 do-it-yourself boatyard with a 20-ton 
travelift Fisherman's Pier, with 3 50-ton jib cranes for 
off-loading commercial fishing vessels; flake ice manufacturing 
and distribution system; 3 wholesale fish 
buying stations; a retail fish market and seafood restaurant; 
offshore oil industry crew transportation; 1,800 
boat slips; a mast up dry storage area for 112 trailerable 
boats; a 6-lane deluxe launch ramp; 2 yacht clubs; 
restaurants; cocktail lounges; sport-fishing facilities; 
harbor and offshore islands excursion boats; 3 yacht 
sales; marine communications sales and services; 3 
marine chandleries; 2 public restroom buildings; a 
harbor administration building/harbor master's office; 
a headquarters/visitors center for Channel Islands 
National Park; marine related ancillary businesses, 
including a convenience grocery store, a marine bookstore, 
a dive shop, gift shops, and a jewelry store; and a 
230-room resort and time-share hotel. 
Operations during fiscal year. Initiated and 
completed maintenance dredging of entrance channel 
and sand trap in March 1986 at a cost of $1,578,000 
regular funds and $10,000 other contributed funds. In 
addition, a reconnaissance and condition survey was 
conducted at a cost of $35,920. 
6. RECONNAISSANCE AND 
CONDITION SURVEYS 
See table 33-H. 
Beach Erosion Control 
7. IMPERIAL BEACH, SAN DIEGO 
COUNTY, CA 
Location. On coast of southern California at Imperial 
Beach in San Diego County. 
Existing project. Plan as modified by Chief of 
Engineers in August 1979 provides for a submerged 
offshore breakwater about 5,000 feet long, extending 
southward from northern groin; extension of northern 
groin about 100 feet to connect with breakwater; and a 
groin about 600 feet long from shoreline to southern end 
of breakwater. Latest approved estimated (1983) first 
cost for project as modified is $5,880,000 (includes 
allowance for estimated inflation through construction 
period), comprising $3,340,000 Federal and $2,540,000 
non-Federal. Map of modified plan is in "Design Memorandum 
No. 4, General Design Memorandum, Imperial 
Beach Erosion Control Project, San Diego County, 
California," prepared by Los Angeles District in September 
1978. 
Local cooperation. Requirements are described in 
full on page 33-6 of Annual Report for 1981. 
Operations during fiscal year. First construction 
contract, breakwater (phase 1), was terminated as a 
result of a U.S. Federal Court preliminary injunction in 
January 1986. 
Flood Control 
8. ALAMO LAKE, BILL WILLIAMS 
RIVER, AZ 
Location. About 70 miles southeast of Kingman, AZ, 
in a narrow gorge at river mile 39 on Bill Williams 
River, AZ, a tributary of Colorado River. 
Existing project. For details, see page 33-7 of Annual 
Report for 1981. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintained dam in 
good operating condition and administered real estate. 
Initiated preparation of water control manual. 
9. CUCAMONGA CREEK, SANTA 
ANA RIVER BASIN, CA 
Location. In and near the Cities of Upland, Rancho 
Cucamonga, and Ontario, and the communities of Alta 
Loma and San Antonio Heights, San Bernardino and 
Riverside Counties, CA. 
Existing project. Plan as modified provides for a 
debris basin on Cucamonga Creek and a concrete 
channel along Cucamonga Creek from the debris basin 
to Prado Dam; an improved San Antonio Heights 
diversion system that would include 6 debris basins and 
a concrete diversion channel to divert West Cucamonga 
Creek headwaters into Cucamonga Creek; a collection 
levee and a debris basin downstream from Demens, 
33-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Thorpe, and Angalls Canyons and a concrete outlet 
channel from the debris basin to Cucamonga Creek; a 
debris basin in Deer Canyon and a channel along Deer 
Creek from the debris basin to Cucamonga Creek; the 
Hillside debris basin in a canyon just west of Deer 
Canyon with an outlet channel to Deer Creek channel; 
improvement of an existing levee system along the west 
bank of Day Creek to assure that flows from Day 
Canyon do not enter Deer Creek channel; turnouts to 
mitigate ground water basin recharge losses; landscaping 
appropriate for esthetic treatment; and recreational 
facilities in the project area. Subdrainage would be 
provided along specific reaches of the channels. Latest 
approved estimated (1983) first cost for modified project 
is $117,856,000 (includes allowance for estimated inflation 
through construction period), comprising 
$93,900,000 Federal and $23,956,000 non-Federal. Map 
of modified plan is in "Design Memorandum No. 2, 
General Design for Flood Control and Recreation, 
Cucamonga Creek, Santa Ana River Basin, San 
Bernardino and Riverside Counties, California," prepared 
by Los Angeles District in June 1973. 
Local cooperation. Requirements are described in 
full on page 33-7 of Annual Report for 1981. 
Operations during fiscal year. Completed construction 
of thirteenth contract, erosion control of Cucamonga 
and Demens Creeks channels (part 2), in April 1986. 
Continued construction of fourteenth contract, erosion 
control of Cucamonga and Deer Creeks, which is about 
99 percent complete. Awarded contract for; initiated; 
and completed construction of fifteenth contract, 
recreational facilities (part 1), in May 1986. Initiated 
and completed preparation of plans and specifications 
for sixteenth contract, recreational facilities (part 2); 
awarded contract; and initiated construction, which is 
about 91 percent complete. Administered rights-of-way 
acquisition completed by local interests. Cost for 
construction of channels was $154,053 regular funds; 
and for recreational facilities, $329,669 regular funds 
and $301,644 required contributed funds. 
10. GILA RIVER BASIN, AZ 
10A. PAINTED ROCK DAM (GILA 
RIVER), AZ 
Location. On Gila River (mile 126) about 20 miles 
downstream from Gila Bend, AZ, in Gila River Basin, 
which is a part of Colorado River Basin. 
Existing project. For details, see page 33-9 of Annual 
Report for 1981. 
Local cooperation. Requirements are described in 
full on page 33-9 of Annual Report for 1981. 
Operations during fiscal year. Maintained dam in 
good operating condition and administered real estate. 
10B. PHOENIX, AZ, AND VICINITY 
(INCLUDING NEW RIVER) 
Location. On Cave Creek, Skunk Creek, Dreamy 
Draw, New River, and Agua Fria River in and adjacent 
to metropolitan Phoenix, AZ. 
Existing project. Plan as modified by Division Engineer, 
South Pacific Division, in July 1977, provides for 
four dams and detention basins, one each on Dreamy 
Draw, Cave Creek, Skunk Creek, and New River; 
Arizona Canal diversion channel; channel improvements 
on Cave Creek, Skunk Creek, and New River; flowage 
easements with some floodproofing along Skunk Creek 
and New and Agua Fria Rivers; flood plain management 
along Dreamy Draw, Cave Creek, Skunk Creek, and 
New River; and recreational facilities. Latest approved 
estimated (1985) first cost for modified project is 
$443,512,000 (full funding estimate and includes allowance 
for estimated inflation through construction 
period), comprising $255,009,000 Federal and 
$188,503,000 non-Federal. Map of modified plan is in 
"Design Memorandum No. 3, General Design Memorandum-
Phase I, Plan Formulation for New River 
and Phoenix City Streams, Arizona," prepared by Los 
Angeles District in March 1976. 
Local cooperation. Requirements are described in 
full on page 33-9 of Annual Report for 1981. 
Operations during fiscal year. Initiated construction 
of Arizona Canal diversion channel, reach 1, Skunk 
Creek to Cactus Road, which is about 95 percent 
complete. Costs for construction of channels were 
$11,868,854 regular funds, $266,859 required contributed 
funds, and $740,144 other contributed funds. 
Costs for construction of dam were $206,532 regular 
funds and $4,863 required contributed funds; for roads, 
railroads, and bridges, $18,221 regular funds and $429 
required contributed funds; and for buildings, grounds, 
and utilities, -$1,597 regular funds and -$39 required 
contributed funds. Completed preparation of part 4 of 
project plan, phase II, Skunk Creek and New and Agua 
Fria Rivers, and initiated preparation of plans and 
specifications. Initiated and completed preparation of 
plans and specifications for Arizona Canal diversion 
channel, reach 2A, Cactus Road to 47th Drive. Initiated 
and completed preparation of plans and specifications 
for recreational facilities (phase 2) at Dreamy Draw 
Dam. Initiated preparation of plans and specifications 
for Arizona Canal diversion channel, reach 2B, 47th 
Drive to Cave Creek. Initiated preparation of plans and 
specifications for recreational facilities, Arizona Canal 
diversion channel, City of Glendale. Administered 
rights-of-way acquisition continued by local interests. 
33-4

LOS ANGELES, CA, DISTRICT 
10C. TUCSON DIVERSION CHANNEL, 
AZ 
Location. In Pima County in drainage areas of 
Tucson Arroyo and Julian Wash, tributaries of Santa 
Cruz River near Tucson, AZ. 
Existing project. For details, see page 33-7 of Annual 
Report for 1982. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Completed construction 
of recreational facilities (phase 1) in December 
1985 at a cost of $109,960 regular funds and $109,961 
required contributed funds. 
10D. WHITLOW RANCH DAM, QUEEN 
CREEK, AZ 
Location. On Queen Creek, AZ, a tributary of Gila 
River, about 10 miles west of Superior, AZ. 
Existing project. For details, see page 33-10 of 
Annual Report for 1981. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintained dam in 
good operating condition; completed acquisition of 
rights-of-way; and administered real estate. 
11. LOS ANGELES COUNTY 
DRAINAGE AREA, CA 
Location. Along Los Angeles and San Gabriel Rivers, 
Rio Hondo, and Ballona Creek, and tributaries thereof 
in Los Angeles County, CA. 
Previous project. For details, see pages 1768 to 1772 
of Annual Report for 1941; page 1602 of Annual Report 
for 1942; and page 1535 of Annual Report for 1943. 
Existing project. Plan provides for flood control 
improvements in four stream basins in Los Angeles 
County, CA, as follows: Los Angeles River Basin, San 
Gabriel River Basin, Rio Hondo Basin, and Ballona 
Creek Basin. Provides for protection of about 325,000 
acres in densely populated Los Angeles County, including 
areas in Los Angeles, Pasadena, Glendale, Burbank, 
and other cities. Plan provides for construction of 5 
flood control dams (Hansen, Lopez, Santa Fe, Sepulveda, 
and Whittier Narrows); debris basins at mouths of 22 
canyons; channel improvements along 101.3 miles of 
Los Angeles River, San Gabriel River, Rio Hondo, and 
Ballona Creek; and channel improvements along 193.69 
miles of tributary channels. All units of improvement 
are physically completed in those four stream basins, 
except the one listed below, and are described in Annual 
Report for 1962. 
A rehabilitation plan was approved in May 1984. The 
rehabilitation plan provides for restoring deteriorated 
portions of the Los Angeles River channel along a 23.5- 
mile reach from Lankershim Boulevard to Stewart and 
Gray Road, and for repairing and improving the Los 
Angeles River channel along a 1-mile reach upstream 
from Sepulveda Dam in the vicinity of Balboa Boulevard. 
Latest approved estimated (1985) Federal first cost for 
rehabilitation is $29,700,000 (includes allowance for 
estimated inflation through construction period). A 
map of the rehabilitation plan is in "General Design 
Memorandum, Los Angeles River Rehabilitation under 
the Major Rehabilitation Program," dated January 
1984 and revised in March 1984. 
Unit of improvement not physically completed in Rio 
Hondo Basin is Sierra Madre Wash. Plan provides for 
the construction of about 0.8 mile of concrete channel on 
Sierra Madre Wash extending from inlet to existing 
Santa Anita Wash channel. (See table 33-I for latest 
approved estimated (1976) first costs for all units of 
improvement under existing project.) 
Local cooperation. Requirements are described in 
full on page 33-11 of Annual Report for 1981. 
Operations during fiscal year. Operations for units 
in Los Angeles River Basin: (a) Compton Creek: Maintained 
channel in good operating condition from Alameda 
Street to Hooper Avenue storm drain. (b) Haines 
Canyon: Maintained debris basin and channel upstream 
from Plainview Avenue in good operating condition and 
administered real estate. (c) Hansen Dam: Maintained 
dam in good operating condition and administered real 
estate. (d) Lopez Dam: Completed preparation of water 
control manual. Maintained dam in good operating 
condition and administered real estate. (e) Los Angeles 
River channel, Lankershim Boulevard to Stewart and 
Gray Road: Administered real estate. Completed construction 
of fourth rehabilitation contract, channel 
invert (Sepulveda Dam basin), in November 1985. 
Completed construction of fifth rehabilitation contract, 
low flow channel (Dayton Ave. to Stewart and Gray 
Rd.), in December 1985. Completed construction of 
sixth rehabilitation contract, main channel invert 
(Burbank-Western confluence), in October 1985. 
Completed preparation of plans and specifications for 
seventh rehabilitation contract, sideslope (Olympic Blvd. 
to Washington Blvd.) and main channel invert (4th St. 
to Washington Blvd.); awarded contract; and initiated 
construction, which is about 26 percent complete. 
Completed preparation of plans and specifications for 
eighth rehabilitation contract, subdrain flapgates 
(Dayton Ave. to Stewart and Gray Rd.); awarded 
contract; and initiated construction, which is about 56 
percent complete. Initiated and completed preparation 
of plans and specifications for ninth rehabilitation 
contract, main channel invert overlay under 4 bridges 
(Golden State Fwy to Fletcher Dr). Initiated and 
completed preparation of plans and specifications for 
tenth rehabilitation contract, main channel invert overlay 
(Dayton Ave. to Atlantic Blvd.); and awarded 
contract. Initiated preparation of plans and specifications 
for eleventh rehabilitation contract, main channel 
invert overlay (Niagara St. to Burbank-Western channel 
confluence). Initiated preparation of plans and specifica- 
33-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
tions for twelfth rehabilitation contract, joint repair 
(Dayton Ave. to Stewart and Gray Rd.). Cost for 
construction of channels was $2,899,361 regular funds. 
(f) Los Angeles River channel, Santa Ana Branch, 
Pacific Electric railway bridge to Pacific Ocean: Initiated 
construction of phase 2A construction of recreational 
facilities, which is about 87 percent complete, at a 
cost of $382,354 regular funds, $352,572 required contributed 
funds, and $221,716 other contributed funds. 
(g) Sepulveda Dam: Continued preparation of water 
control manual. Maintained dam in good operating 
condition and administered real estate. 
Operations for units in San Gabriel River Basin: (a) 
Santa Fe Dam: Maintained dam in good operating 
condition and administered real estate. Completed 
contract payment for construction of phase 5 recreational 
facilities at a cost of $2,000 other contributed funds. 
(b) San Gabriel River channel, San Gabriel Canyon to 
Santa Fe Dam, Approach channel to Santa Fe Dam 
(remedial work): Maintained channel in good operating 
condition. (c) Whittier Narrows Dam: Maintained dam 
in good operating condition and administered real 
estate. 
Operations for units in Rio Hondo Basin: (a) Alhambra 
Wash: Maintained channel upstream from Valley Boulevard 
in good operating condition. (b) Rio Hondo channel, 
Whittier Narrows Dam to Los Angeles River (lower): 
Initiated construction of phase 2A construction of 
recreational facilities, which is about 87 percent complete, 
at a cost of $382,354 regular funds, $352,572 
required contributed funds, and $221,716 other contributed 
funds. 
OpetLLIUII U IILl 111 DUlona Cl LG s.iL ni11. 
Creek channel and jetties: Maintained channel downstream 
from Washington Boulevard to La Salle Avenue 
and downstream from Los Angeles city boundary to 
ocean; jetties; and Pacific Avenue bridge in good operating 
condition. 
12. LOS COCHES CREEK, SAN DIEGO 
COUNTY, CA 
Location. In the community of Lakeside, San Diego 
County, CA. 
Existing project. Plan provides for a 1.8-mile-long 
rectangular concrete channel; an inlet structure just 
downstream from the Los Coches Creek bridge and 
adjacent to Los Coches and Ha-Hana Roads; and an 
outlet structure at the confluence of the San Diego 
River. Plan also provides for 5 double box culverts and 1 
triple box culvert. Latest approved estimated (1983) 
first cost for project is $6,197,000 ($4,000,000 Federal 
and $2,197,000 non-Federal). 
Local cooperation. Requirements are described in 
full on page 33-8 of Annual Report for 1985. 
Operations during fiscal year. Awarded first contract 
and initiated construction, which is about 67 
percent complete, at a cost of $1,823,430 regular funds 
and $3,915,870 required contributed funds. Initiated 
and completed preparation of plans and specifications 
for mitigation measures. 
13. LYTLE AND WARM CREEKS, 
SANTA ANA RIVER BASIN, CA 
Location. Near San Bernardino and Colton, San 
Bernardino County, CA. 
Existing project. Plan as modified provides for a 
rectangular concrete channel extending for 3.5 miles 
along East Branch of Lytle Creek from existing Foothill 
Boulevard inlet structure to confluence with Warm 
Creek; a concrete trapezoidal channel on Warm Creek 
for 1.5 miles from confluence with East Branch of Lytle 
Creek to confluence with Santa Ana River; a leveed 
channel extending about 1.8 miles along Santa Ana 
River from mouth of existing East Twin and Warm 
Creeks concrete channel to Mount Vernon Avenue 
crossing; replacement of 4 railroad bridges and 12 
highway bridges; 3 new highway bridges; inlets for side 
drainage; and relocation and protection of utilities. 
Design capacities of improvements would be: East 
Branch of Lytle Creek, 58,000 cubic feet per second; 
Warm Creek, 60,000 to 90,000 cubic feet per second; and 
Santa Ana River, 167,000 to 234,000 cubic feet per 
second. Latest approved estimated (1984) first cost of 
modified project is $44,410,000 (includes allowance for 
estimated inflation through construction period), comprising 
$37,600,000 Federal and $6,810,000 non-Federal. 
AuthorizI ed proj;+e ct .. as m;;odified by iDeign Memorandum 
No. 1, approved in May 1972, which contains a 
map of modified project plan. 
Local cooperation. Requirements are described in 
full on page 33-13 of Annual Report for 1981. 
Operations during fiscal year. Completed preparation 
of plans and specifications to correct project 
deficiency; awarded contract; and initiated construction, 
which is about 44 perent complete, at a cost of $946,437 
regular funds. 
14. MOJAVE RIVER DAM, MOJAVE 
RIVER BASIN, CA 
Location. On Mojave River at the Forks site, just 
downstream from mouth of Deep Creek and about 14 
miles upstream from Victorville, in Mojave River 
Basin, CA. 
Existing project. For details, see page 33-8 of Annual 
Report for 1983. 
Local cooperation. Requirements are described in 
full on page 33-13 of Annual Report for 1981. 
Operations during fiscal year. Completed preparation 
of water control manual. Maintained dam in good 
operating condition and administered real estate. 
33-6

LOS ANGELES, CA, DISTRICT 
15. PINE AND MATHEWS CANYONS 
DAMS, COLORADO RIVER BASIN, 
NV 
Location. In Lincoln County, NV, about 100 miles 
north of Hoover Dam and about 17 and 20 miles, 
respectively, east of Caliente, NV. 
Existing project. For details, see page 33-13 of 
Annual Report for 1981. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintained dams in 
good operating condition and administered real estate. 
16. SANTA ANA RIVER BASIN (AND 
ORANGE COUNTY), CA 
Location. On Santa Ana River and tributaries and on 
other streams in Orange, Riverside, and San Bernardino 
Counties, CA. 
General plan of improvement. For details, see page 
33-14 of Annual Report for 1981. 
Existing project. For details on active units, see 
Annual Report for 1968. For other pertinent information, 
see table 33-E, "Other Authorized Flood Control Projects," 
and table 33-G, "Deauthorized Projects." (See 
table 33-J for latest approved estimated Federal first 
cost for all units.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. Operations for units 
in existing project: (a) Brea Dam: Continued preparation 
of water control manual. Maintained dam in good 
operating condition and administered real estate. (b) 
Carbon Canyon Dam and channel: Initiated and completed 
construction of fourth contract for recreational 
facilities (phase 3) in February 1986 at a cost of $55,547 
regular funds and $57,049 required contributed funds. 
Maintained project in good operating condition; administered 
real estate; and completed acquisition of 
rights-of-way. (c) Fullerton Dam: Continued preparation 
of water control manual. Maintained dam in good 
operating condition and administered real estate. (d) 
Prado Dam: Maintained dam in good operating condition 
and administered real estate. (e) San Antonio Dam: 
Maintained dam in good operating condition and 
administered real estate. (f) San Antonio and Chino 
Creeks channel: Maintained project in good operating 
condition and administered real estate. 
17. SWEETWATER RIVER, 
SWEETWATER RIVER BASIN, CA 
Location. Lower Sweetwater River Valley, along 
Sweetwater River from Interstate Freeway 805 to San 
Diego Bay, San Diego County, CA. 
Existing project. Plan as modified provides for 
about 3.2 miles of improved trapezoidal channel along 
Sweetwater River from Interstate Freeway 805 to San 
Diego Bay as part of a combined flood control and 
highway project. Approved estimated (1986) first cost 
for project is $49,000,000 (includes allowance for estimated 
inflation through construction period), comprising 
$25,200,000 Federal and $23,800,000 non-Federal. 
Map of modified plan is in "General Design Memorandum 
No. 1 for Sweetwater River Flood Control 
Channel, San Diego County, California," prepared by 
Los Angeles District in March 1982 and revised in May 
1984. 
Local cooperation. Requirements are described in 
full on page 33-16 of Annual Report for 1981. 
Operations during fiscal year. Continued stage 2 
construction, which is about 50 percent complete. 
California State Department of Transportation awarded 
contract for and initiated stage 3 construction, which is 
about 30 percent complete. Cost for construction of 
channels was $5,635,391 regular funds. Cost for roads, 
railroads, and bridges was $185,475 regular funds. 
18. WEST MAGNESIA CANYON 
CHANNEL, RANCHO MIRAGE, CA 
Location. In the City of Rancho Mirage, Riverside 
County, CA. 
Existing project. Plan provides for a debris basin at 
mouth of Magnesia Spring Canyon; a 1.4-mile-long 
rectangular concrete channel; and an energy dissipator 
at the confluence of the Whitewater River. Plan also 
provides for preservation and enhancement of wildlife 
habitat values on 20 acres of alluvial cone. Latest 
approved estimated (1983) first cost for project is 
$8,279,000 ($4,000,000 Federal and $4,279,000 non- 
Federal). 
Local cooperation. Requirements are described in 
full on page 33-10 of Annual Report for 1985. 
Operations during fiscal year. Continued construction 
of first contract, which is about 99 percent 
complete, at a cost of $2,959,088 regular funds and 
$1,600,467 required contributed funds. Initiated and 
completed preparation of plans and specifications for 
mitigation measures, and awarded second contract. 
19. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection costs for fiscal year from regular funds for 
maintenance were $307,158. (See table 33-K on inspection 
of completed flood control projects.) 
20. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
In accordance with section 7, Flood Control Act of 
1944, studies of reservoir operations for flood control 
were conducted; and preparation of regulations for the 
use of storage allocated for flood control was continued 
for the following Bureau of Reclamation projects: Hoover 
Dam and Twitchell Dam. Costs for fiscal year from 
regular funds for maintenance were $60,328. 
33-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
21. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 80-858, as amended (preauthorization) 
See table 33-L on flood control work under special 
authorization. 
Emergency bank protection (sec. 14 of 1946 Flood 
Control Act, Public Law 526, 79th Cong.) 
Federal cost for fiscal year was $199,763 for Rillito 
River, Pima County, AZ; $49,095 for Nazlini Wash, 
Chinle, AZ; and $15,208 for Santa Ana River, Colton, 
CA. 
Emergency flood control activities - repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Cong., and antecedent legislation) 
Federal cost for fiscal year was $166,774, all of which 
was for advance preparation. 
Flood insurance activities (sections 1301-1377, 
1968 Housing and Urban Development Act, Public 
Law 90-448, as amended) 
In coordination with flood control activities, flood 
insurance studies were continued in accordance with 
Inter-Agency Agreements at fiscal year cost of $69,137 
under Housing and Urban Development reimbursable 
order. 
General Investigations 
22. SURVEYS 
Fiscal year cost was $5,010,712 regular funds, of 
which $557,626 were for navigation studies; $75,254 
were for beach erosion control studies; $2,990,848 were 
for flood control studies; $1,113,995 were for surveys; 
$107,127 were for special studies involving coordination 
with other agencies; $65,765 were for review of authorized 
projects; $95,963 were for miscellaneous activities; 
and $4,134 were for supplemental preauthorization 
studies, phase I. 
23. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs were $159,661 for technical services; 
and $90,512 for flood plain management. 
24. RESEARCH AND DEVELOPMENT 
Fiscal year cost was $13,605 for hydrologic studies. 
25. CONTINUATION OF PLANNING 
AND ENGINEERING 
25A. HOLBROOK LEVEE, LITTLE 
COLORADO RIVER, COLORADO 
RIVER BASIN, AZ 
Holbrook levee is on Little Colorado River at Holbrook, 
Navajo County, AZ, in northeastern Arizona, about 200 
miles northeast of Phoenix. Project was authorized by 
Flood Control Act of 1970, Public Law 91-611, dated 
December 31, 1970. 
Plan of improvement provides for raising existing 
north bank levee and adding a new south bank levee, a 
low flow channel, recreational facilities, and mitigation 
features. Existing levee (north) would be raised to a 
height ranging from 23 feet high upstream from Apache 
Railroad bridge to about 12 feet high downstream from 
bridge, and would be about 18,000 feet long. South side 
levee would be about 5,000 feet long and would have a 
maximum height of 23 feet. 
Continued preparation of project plan during fiscal 
year. Estimated preconstruction planning cost is 
$970,000. Total costs during fiscal year were $3,997. 
25B. SANTA ANA RIVER MAIN STEM 
-INCLUDING SANTIAGO CREEK 
AND OAK STREET DRAIN, SANTA 
ANA RIVER BASIN, CA 
Santa Ana River main stem-including Santiago 
Creek and Oak Street Drain, Santa Ana River Basin, 
CA, is on Santa Ana River and tributaries and on other 
streams in Orange, Riverside, and San Bernardino 
Counties, CA. Project was authorized by Water Resources 
Development Act of 1976, Public Law 94-587, dated 
October 22, 1976. 
Plan of improvement provides for construction of 
Mentone Dam near community of Mentone, San Bernardino 
County; management of flood plain between Mentone 
Dam and Prado Reservoir; improvement of Oak Street 
Drain in Corona, Riverside County; enlargement of 
existing Prado Dam and reservoir, Riverside and San 
Bernardino Counties; improvement of lower Santa Ana 
River channel from Prado Dam to Pacific Ocean; and 
improvement of lower reach of Santiago Creek channel 
in Orange County; recreational development along 
project length; purchase of 8 acres of salt marsh for 
mitigation of project effects; purchase of 84 acres of 
tidal lands at mouth of Santa Ana River for preservation 
of endangered least tern habitat; landscaping; and 
recreational features. 
Continued preparation of project plan, phase II, 
during fiscal year. Estimated preconstruction planning 
cost is $21,000,000. Total costs during fiscal year were 
$3,622,203. 
26. ADVANCE ENGINEERING AND 
DESIGN 
GOLETA, CA, AND VICINITY, 
SANTA BARBARA COUNTY 
Goleta, CA, and vicinity is in Goleta Valley along 
Atascadero Creek and its tributaries, including Tecolotito, 
Carneros, San Pedro, Las Vegas, San Jose, and 
Maria Ygnacio Creeks, from the Santa Ynez Mountains 
in Santa Barbara County to Pacific Ocean near Goleta, 
33-8

LOS ANGELES, CA, DISTRICT 
CA. Project was authorized by Flood Control Act of 
1970, Public Law 91-611, dated December 31, 1970. 
Plan of improvement provides for about 12.5 miles of 
channel improvement, comprising about 1.3 miles of 
channel clearing and about 11.2 miles of channel 
construction. Channel clearing would be required on 
Maria Ygnacio, San Jose, Las Vegas, San Pedro, and 
Carneros Creeks. Channel construction would include 
the improvement of Atascadero Creek from San Marcos 
Road to ocean; Maria Ygnacio Creek from Hollister 
Avenue to Atascadero Creek; San Jose Creek from 0.2 
mile north of U.S. Highway No. 101 to San Pedro Creek; 
Las Vegas Creek from Cathedral Oaks Road to San 
Pedro Creek; San Pedro Creek from a point 0.1 mile 
downstream from Stow Canyon Road to Atascadero 
Creek; Carneros Creek from 0.6 mile upstream from 
U.S. Highway No. 101, by means of a diversion route, to 
Tecolotito Creek; and Tecolotito Creek from U.S. Highway 
No. 101 to Atascadero Creek. Plan also provides for 
beautification and recreation features. 
Continued preparation of project plan, phase I, during 
fiscal year. Estimated preconstruction planning cost is 
$2,650,000. Total costs during fiscal year were $7,539. 
33-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 33-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
1. Los Angeles and New Work: 
Long Beach 
Harbors, CA 
(Regular Funds) 
Required Contrib. 
Funds) 
(Other Contrib. 
Funds) 
2. Morro Bay Harbor, 
CA 
3. Oceanside Harbor, 
CA (Regular 
Funds) 
(Other Contrib. 
Funds) 
4. Santa Barbara 
Harbor CA 
5. Ventura Marina 
(Ventura Harbor), 
CA 
7. Imperial Beach, 
CA (Regular 
Funds) 
(Required Contrib. 
Funds 
8. Alamo Lake, 
Bill Williams 
River, AZ 
9. Cucamonga Creek, 
Santa Ana River 
Basin, CA 
(Regular Funds) 
(Required Contrib. 
Funds) 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
$ 
458,000 57,000 
- 491,644 
600,512 
563,908 
33-10 
------- 
p5,323,000 -$340,000 -$69,000 - $64,710,7191 
5,721,814 -268,794 17,627 18,467 64,317,6311 
2,768,600 704,000 1,102,904 1,821,249 11,770,2122 
358,760 3,062,364 1,065,667 1,889,994 11,742,6152 
214,180 - - - 1,203,180 
175,655 80,057 - - 1,169,426 
3,807,130 - - - 37,961,7053 
4,641,542 515,690 - - 37,510,2813 
- - - - 2,612,0934 
- - - - 2,612,0934 
1,573,052 165,000 3,021,874 149,093 9,814,9065 
60,846 1,676,263 2,920,156 251,252 9,864,0415 
- - - - 2,128,411 
- - - - 2,128,411 
5,081,782 -1,970,133 1,162,500 5,019,575 14,247,6146 
642,862 2,411,303 1,001,590 5,192,340 14,092,6516 
- - - - 491,2867 
-- - - 491,2867 
-- - - 1,200,000 
7,500 - - - 1,187,500 
- - - - 172,0008 
- - - - 172,0008 
945,543 341,000 328,000 720,700 9,308,8199 
555,992 729,914 324,420 686,790 9,270,5609 
- - - - 1,711,53910 
- - - - 1,711,53910 
2,488,000 653,000 1,635,000 1,823,920 15,752,35711 
2,329,024 818,882 1,635,618 1,836,388 15,749,15611 
- 2,000,000 493,000 - 3,342,75712 
74,623 103,226 31,271 721,296 1,554,66412 
- - 2,710,000 - 2,735,601 
- - - 518,753 544,337 
- - - - 16,934,060's13 
- - -525 -56 16,933,47913 
487,000 494,000 546,000 697,000 5,125,799 
372,021 580,299 579,462 684,264 5,086,192 
3,950,000 100,000 1,553,000 160,600 93,360,500 
4,057,329 1,041,150 2,686,070 370,430 93,265,270 
--

LOS ANGELES, CA, DISTRICT 
TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
(Other Contrib. 
Funds) 
10A. Gila River Basin, 
AZ, Painted 
Rock Dam (Gila 
River) 
10B. Gila River Basin, 
AZ, Phoenix, 
AZ, and vicinity 
including New River) 
Regular Funds) 
Required Contrib.) 
unds) 
Other Contrib. 
Funds) 
10C. Gila River Basin, 
AZ, Tucson diversion 
channel (Regular 
Funds) 
Required Contrib. 
Funds) 
10D. Gila River Basin, 
AZ, Whitlow 
Ranch Dam, 
Queen Creek 
11. Los Angeles County 
drainage area, 
CA (Regular Funds) 
Required Contrib. 
Funds) 
(Other Contrib. 
unds) 
12. Los Coches Creek, 
San Diego County, 
CA (Regular Funds) 
(Required Contrib. 
unds) 
Funding 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Total Cost to 
FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
-270,893 
400,965 
594,000 
551,293 
4,680,000 
5,621,403 
-39,526 
6,823 
472,000 
479,419 
12,860,000 
11,998,004 
346,000 500,000 621,000 
81,743 624,923 149,008 
- - 1,775,000 
- - 10,169 
80,000 600,000 150,000 
6,638 88,109 561,122 
- - 750,000 
- - 567,634 
64,521 -57,000 9,390,853 
47,380 27,728 9,332,278 
- - 19,980,56414 
- - 19,980,56414 
752,000 651,000 8,185,148 
751,204 616,553 8,109,859 
5,600,000 16,539,000 84,894,297 
6,526,194 15,556,495 83,140,766 
333,500 2,668,714 
275,076 1,802,685 
- 2,234,700 
740,297 1,147,028 
- 6,927,62515 16 
165,457 6,917,76715 17 
178,217 
145,000 143,000 135,000 42,000 
84,911 206,863 134,559 39,914 
967,700 -23,800 
367,925 858,698 
9,107,000 3,084,000 
5,723,627 6,864,570 
- 5,000,000 
- 1,800,240 
286,818 
378,256 
50,000 
154,571 
166,382 
207,361 
4,264,000 
3,474,626 
6,520,000 
9,475,162 
6,028 
516,000 
308,007 200,000 
228,946 51,373 
- 245,000 
10,054 240,846 
- 100,000 
750,000 
745,851 
1,867,96318 
1,867,96318 
943,413 
940,305 
- 377,026,88519 20 
-1,199 377,018,68119 21 
3,444,000 55,624,02019 22 
4,423,901 55,343,99719 23 
6,869,000 18,389,000 
3,929,743 15,204,905 
- 13,933,34124 
659 13,890,86625 
- 516,00026 
352,572 352,57227 
- 36,644,86528 
- 36,639,88828 
161,186 669,19329 
241,091 521,41030 
2,070,399 2,600,399 
1,994,218 2,512,246 
4,700,000 4,800,000 
3,915,870 3,915,870 
33-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
13. Lytle and Warm 
Creeks, Santa Ana 
River Basin, CA 
14. Mojave River Dam, 
Mojave River 
Basin, CA 
(Regular Funds) 
Other Contrib. 
Funds) 
15. Pine and Mathews 
Canyons Dams, 
Colorado River 
Basin, NV 
16. Santa Ana River 
Basin (and Orange 
County), CA 
(Regular Funds) 
(Required Contrib. 
Funds) 
17. Sweetwater River, 
Sweetwater River 
Basin, CA 
18. West Magnesia 
Canyon channel, 
Rancho Mirage, CA 
(Regular Funds) 
(Required Contrib. 
Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
-21,026 
- 200,000 2,583,000 37,828,83131' 
-6,210 202,993 1,150,453 36,369,51431 
- - - 17,838,198 
- - - - 17,838,198 
653,000 342,000 275,000 116,000 3,144,548 
244,816 588,335 391,117 180,500 3,143,894 
- - - - 286,300 
- - - - 284,501 
- - - - 1,401,248 
- - - - 1,401,248 
63,000 
43,070 
819,300 
83,204 
2,266,000 
1,686,767 
21,149 
240,000 
261,434 
23,800 
770,398 
1,377,000 
1,775,951 
143,000 105,000 1,104,356 
139,766 108,416 1,101,925 
17,747 
2,039,000 
2,202,404 
-17,394 
-432 
75,000 
145,000 1,500,000 
136,413 467,244 
20,000 80,000 
16,223 84,040 
4,000,000 
4,964,685 
705,000 
322,836 
- 47,994,73832 33 34 
-436 47,992,52732 33 35 
1,886,600 
1,982,194 
24,157,41036 38 
24,075,50337 38 
- 3,122,76239 
4,132 3,103,32240 
67,555 
6,242,000 
6,295,436 
2,765,000 
3,146,924 
75,00041 
67,55542 
13,366,503 
13,343,279 
4,000,000 
3,999,725 
350,000 1,974,206 2,324,206 
266,137 1,715,919 1,982,056 
1. Includes $2,187,047 for new work for previous project; 
$1,593,667 public works funds; a credit of $33,050 for transfer 
of land at Reservation Point; and $996,792 emergency relief 
funds. Excludes Federal funds spent by the Navy for new 
work on middle breakwater, and Coast Guard costs. 
2. Includes $139,347 for maintenance for previous project 
and $177,076 for reconnaissance and condition survey costs 
since FY 1958. 
3. Includes $1,672,575 for new work betterments desired 
by local interests prior to 1976 modification. Excludes $87,120 
for maintenance betterments desired by local interests prior 
to 1976 modification. 
4. Navy funds. 
5. Includes $354,791 for reconnaissance and condition 
surveys since FY 1958 and $307,945 Navy funds. Excludes 
$124,578 other contributed funds. 
6. Includes $69,804 for reconnaissance and condition 
surveys. Excludes $5,170,266 for maintenance accomplished 
with Navy funds. 
7. For jetty and groin extensions desired by local interests. 
8. Excludes Coast Guard costs. 
9. Includes $29,198 public works funds; $11,000 working 
funds for work performed in addition to existing project; and 
$19,741 for reconnaissance and condition surveys. Excludes 
$462,986 other contributed funds spent by the Corps for 
maintenance-dredging betterments desired by local interests. 
10. Excludes $1,708,836 required contributed funds and 
Coast Guard costs. 
11. Includes $89,819 for reconnaissance and condition 
surveys. 
12. Excludes $66,124 other contributed funds and Coast 
Guard costs. 
13. Includes $57,000 Code 710 funds since FY 1975. 
14. Includes $357,469 Code 710 funds since FY 1962. 
15. Excludes $394,364 other contributed funds. 
16. Includes $1,163,000 Code 710 funds since FY 1977. 
17. Includes $1,153,142 Code 710 funds since FY 1977. 
33-12

LOS ANGELES, CA, DISTRICT 
TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT 
18. Includes $3,758 Code 710 funds since FY 1962. 
19. Includes $11,008,935 emergency relief funds for new 
work. Excludes $16,726,888 emergency relief funds spent by 
Corps in connection with emergency relief (previous) project 
and $107,939 for minor rehabilitation. 
20. Includes $23,763,900 Code 710 funds since FY 1974 
($1,226,100 for Sepulveda Dam; $6,290,000 for Whittier 
Narrows Dam; $22,000 for LACDA prototype; $535,000 for 
Hansen Dam; $10,422,100 for Santa Fe Dam; $215,000 for 
Tujunga Wash channel; $8,500 for Lopez Dam; $3,562,200 for 
Los Angeles River and Rio Hondo channels; and $1,483,000 
for Ballona Creek channel). 
21. Includes $23,755,695 Code 710 funds since FY 1974 
(1,223,226 for Sepulveda Dam; $6,290,000 for Whittier 
Narrows Dam; $22,000 for LACDA prototype; $535,000 for 
Hansen Dam; $10,416,769 for Santa Fe Dam; $215,000 for 
Tujunga Wash channel; $8,500 for Lopez Dam; $3,562,200 for 
Los Angeles River and Rio Hondo channels; and $1,483,000 
for Ballona Creek channel). 
22. Includes $925,000 for recreational facilities since FY 
1985 ($460,000 for Sepulveda Dam and $465,000 for Los 
Angeles River and Rio Hondo channels). 
23. Includes $870,613 for recreational facilities since FY 
1985 ($441,680 for Sepulveda Dam and $428,933 for Los 
Angeles River and Rio Hondo channels). 
24. Includes $13,933,341 Code 710 funds since FY 1974 
($992,650 for Sepulveda Dam; $6,797,556 for Whittier Narrows 
am; $199,541 for Tujunga Wash channel; $460,500 for 
Hansen Dam; $2,824,056 for Los Angeles River and Rio 
Hondo channels; $1,467,538 for Santa Fe Dam; and $1,191,500 
for Ballona Creek channel). 
25. Includes $13,890,866 Code 710 funds since FY 1974 
($992,650 for Sepulveda Dam; $6,755,401 for Whittier Narrows 
am; $199,541 for Tujunga Wash channel; $460,180 for 
Hansen Dam; $2,824,056 for Los Angeles River and Rio 
Hondo channels; $1,467,538 for Santa Fe Dam; and $1,191,500 
for Ballona Creek channel). 
26. Includes $516,000 for recreational facilities since FY 
1985 ($516,000 for Los Angeles and Rio Hondo channels). 
27. Includes $352,572 for recreational facilities since FY 
1986 ($352,572 for Los Angeles and Rio Hondo channels). 
28. Non-Federal funds spent by the Federal Government 
to September 30, 1986, for replacements required as part of 
local cooperation and betterments desired by local interests. 
Excludes $4,238,000 other contributed funds spent by the 
Corps in connection with emergency relief (previous) project. 
29. Includes $669,193 for recreational facilities since FY 
1984 ($299,193 for Santa Fe Dam and $370,000 for Los 
Angeles River and Rio Hondo channels). 
30. Includes $521,410 for recreational facilities since FY 
1984 ($299,193 for Santa Fe Dam and $222,217 for Los 
Angeles and Rio Hondo channels). 
31. Excludes $5,499,193 other contributed funds. 
32. Comprises funds for Brea, Fullerton, Prado, and San 
Antonio Dams, Carbon Canyon Dam and channel, Lytle and 
Cajon Creeks channel improvements, and San Antonio and 
Chino Creeks channel (active units). 
33. Includes $5,000 working funds for San Antonio Dam; 
$67,361 for San Juan Dam (inactive unit) (also reported under 
"Other Authorized Flood Control Projects"); and $85,310 
undistributed funds. Excludes other contributed funds spent 
by the Corps, as follows: $124,105 for water conservation 
betterments desired by local interests at Prado Dam; $8,500 
for betterments desired by local interests at San Antonio 
Dam; $234,709 for betterments desired by local interests on 
San Antonio and Chino Creeks channel; and $601,762 for 
required items of local cooperation on Lytle and Cajon Creeks 
channel improvements. Excludes $290,000 spent direct by 
local interests on San Antonio and Chino Creeks channel for 
local cooperation items not required. 
34. Includes $5,920,831 Code 710 funds since FY 1974 
($1,058,731 for Carbon Canyon Dam and channel; $1,264,300 
or Fullerton Dam; and $3,597,800 for Prado Dam). 
35. Includes $5,918,620 Code 710 funds since FY 1974 
($1,058,731 for Carbon Canyon Dam and channel; $1,262,882 
or Fullerton Dam; and $3,597,007 for Prado Dam). 
36. Includes $75,000 for recreational facilities since FY 
1985 ($75,000 for Carbon Canyon Dam and channel). 
37. Includes $71,421 for recreational facilities since FY 
1985 ($71,421 for Carbon Canyon Dam and channel). 
38. Excludes maintenance for Lytle and Cajon Creeks 
channel improvements, which are operated and maintained 
by local interests. 
39. Includes $3,122,762 Code 710 funds since FY 1974 
($1,426,973 for Carbon Canyon Dam and channel; $1,269,789 
or Fullerton Dam; and $426,000 for Prado Dam). 
40. Includes $3,103,322 Code 710 funds since FY 1975 
($1,426,973 for Carbon Canyon Dam and channel; $1,250,349 
or Fullerton Dam; and $426,000 for Prado Dam). 
41. Includes $75,000 for recreational facilities since FY 
1985 ($75,000 for Carbon Canyon Dam and channel). 
42. Includes $67,555 for recreational facilities since FY 
1986 ($67,555 for Carbon Canyon Dam and channel). 
33-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
1. June 3, 1896 
June 25, 1910 
July 25, 1912 
Aug. 8, 1917 
Sep. 22, 1922 
Mar. 3, 1925 
July 3, 1930 
Do. 
Aug. 30, 1935 
Oct. 17, 1940 
Sep. 3, 1954 
LOS ANGELES AND LONG BEACH HARBORS, CA 
A breakwater 8,500 feet long, east of Point Fermin. 
Extend said breakwater to shore, making a total length 
of 11,152 feet from Point Fermin. 
Dredge Los Angeles outer harbor west of entrance 
channel. 
For silt-diversion works. 
Triangular area approach to Los Angeles inner harbor 
entrance channel. 
Dredge Los Angeles Harbor main channel and entrance 
35 feet deep and 1,000 feet wide; dredge inner harbor 
turning basin 35 feet deep; and reclamation of Reservation 
Point. 
A detached breakwater 12,500 feet long in prolongation 
of existing breakwater (authorized by act of 1896). 
S. Doc. 18, 55th Cong., 
1st sess. 
H. Doc. 969, 60th Cong., 
1st sess. 
Rivers and Harbors 
Committee Doc. 8, 
62d Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 9, 
64th Cong., 2d sess. 
H. Doc. 1013, 66th Cong., 
3d sess. 
H. Doc. 349, 68th 
Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 33, 
71st Cong., 2d sess. 
Widen fairway on east side of entrance to Los Angeles S. Doc. 130, 71st Cong., 
inner harbor; dredge a channel 35 feet deep and 650 2d sess. 
feet wide in East Basin from turning basin to U.S. 
station 406; dredge 35 feet deep and 400 feet wide 
in Cerritos channel from U.S. station 406 to Long 
Beach turning basin; a turning basin 35 feet deep 
at Long Beach; entrance channel to Long Beach Harbor 
35 feet deep and 500 feet wide; and maintenance 
of the Long Beach breakwater south of outer end pier 
A. This act provides that in no case shall dredging 
be done within 50 feet of established pierhead lines 
of existing piers and wharves. 
Dredge 1,000-foot-wide entrance channel to Los Angeles S. Committee print, 
outer harbor to 40-foot depth and a turning basin 3,500 74th Cong., 1st sess. 
feet long and 1,500 feet wide to same depth; and enlarge 
entrance to inner harbor by dredging to 35-foot depth a 
triangular area at its junction with turning basin. 
Dredge to a depth of 40 feet areas A and B adjacent to H. Doc. 843, 76th Cong., 
40-foot-depth entrance channel; construct and maintain a 3d sess. 
rubblemound breakwater of composite type 21,000 feet 
long in eastward direction from northeast end of existing 
detached breakwater; dredge about 4 million cubic yards 
initially for a settling basin at mouth of Los Angeles 
River diversion channel, and deposit material on beaches 
eastward therefrom to Belmont pier; maintenance dredging 
of areas A and B, and at mouth of Los Angeles River 
diversion channel; all subject to such modifications as 
in discretion of the Chief of Engineers may be advisable 
to meet requirements of the Navy. 
Dredge to a depth of 35 feet in East Basin as a modifi- H. Doc. 161, 83d Cong., 
cation of existing project. This act provides that the Secre- 1st sess. 
tary of the Army is authorized to reimburse local interests 
for work they have done upon this project prior to 
July 1, 1953, at actual cost to local interests so 
far as same shall be approved by Chief of Engineers and 
found to have been done in accordance with the project 
hereby adopted and that such reimbursement shall be 
subject to appropriations applicable thereto or funds 
available therefor and shall not take precedence over 
other pending projects of higher priority for harbor 
improvements; and that such payments shall not exceed 
$500,000. 
33-14 
s

LOS ANGELES, CA, DISTRICT 
TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
July 14, 1960 
Oct. 22, 1976 
2. Mar. 2, 1945 
3. Oct. 27, 1965 
4. Aug. 30, 1935 
Mar. 2, 1945 
Oct. 23, 1962 
Dec. 31, 1970 
5. Aug. 13, 1968 
7. July 3, 1958 
8. Dec. 22, 1944 
9. Aug. 13, 1968 
10A. May 17, 1950 
Dredge to a depth of 35 feet in West Basin as a H. Doc. 401, 86th Cong., 
modification of existing project. 2d sess. 
Dredge Los Angeles Harbor entrance channel 45 feet H. Doc 94-594, 94th 
deep, 1,000 feet wide, and about 5,500 feet long; Los Cong., 2d sess.' 
Angeles channel 45 feet deep, 750 feet wide, and about 
12,500 feet long; inner harbor turning basin 45 feet 
deep, 1,350 feet wide, and about 1,650 feet long; East 
Basin channel 45 feet deep, 400 feet wide, and about 6,000 
feet long; West Basin 45 feet deep, from 350 to 1,350 feet 
wide, and about 3,800 feet long; and East Basin 45 feet 
deep, from 400 to 950 feet wide, and about 2,000 feet 
long. This act provides that no dredging shall be done 
within 125 feet of established pierhead lines, wharves, 
or other structures 
MORRO BAY HARBOR, CA 
Adoption and improvement of existing entrance channel to H. Doc, 283, 77th Cong., 
bay, a breakwater extending south by west from Morro 1st sess. 
Rock, and bay channels and basins at locations and of 
dimensions substantially as shown on the Navy Department 
map on file in the Office of the Chief of Engineers. 
OCEANSIDE HARBOR, CA 
Maintenance of general navigation features of Del Mar H. Doc. 76, 89th Cong., 
Boat Basin and of Oceanside Harbor. 1st sess. 
SANTA BARBARA HARBOR, CA 
Maintenance dredging present depths into harbor formed S. Committee Print, 73d 
by breakwater constructed by local interests. Cong., 2d sess. 
Permits maintenance by means of a fixed sand-intercept- H. Doc. 348, 77th Cong., 
ing plant to be provided and operated by and at expense of 1st sess. 
local interests. United States to contribute to operating 
expense an amount not to exceed $30,000 annually, 
whenever funds are allotted therefor; funds thus contributed 
to be reduced by actual cost of harbor maintenance if 
and when intercepting plant has been installed. 
Modification of existing project. H. Doc. 518, 87th Cong., 
2d sess.' 
Dredging and maintenance by United States. None 
VENTURA MARINA (VENTURA HARBOR), CA 
Adoption and maintenance of existing general navigation H. Doc. 356, 90th Cong., 
features of harbor, excluding interior basins; construction 2d sess. 
of an offshore breakwater; dredging a sand trap in lee of 
breakwater; repairing existing north and middle jetties; 
and construction of recreational fishing facilities on 
jetty crests. 
IMPERIAL BEACH, CA 
Federal participation by contribution of Federal funds H . Doc. 399, 84th Cong., 
toward cost of five groins. 2d sess. 
ALAMO LAKE, BILL WILLIAMS RIVER, AZ 
Multiple-purpose dam and reservoir. H. Doc. 625, 78th Cong., 
2d sess. 
CUCAMONGA CREEK, SANTA ANA RIVER 
BASIN, CA 
Debris-collection facilities, with a system of channels, and H. Doc. 323, 90th Cong., 
a diversion system. 2d sess. 
PAINTED ROCK DAM (GILA RIVER), GILA 
RIVER BASIN, AZ 
Dam and flood control basin. H. Doc. 331, 81st Cong., 
1st sess. 
33-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
10B. Oct. 27, 1965 
10C. June 30, 1948 
10OD. July 24, 1946 
11. June 22, 1936 
May 15, 1937 
June 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
July 24, 1946 
May 17, 1950 
Sep., 1954 
July 3, 1958 
July 14, 1960 
Oct. 23, 1962 
Dec. 30, 1963 
June 18, 1965 
12. Feb. 7, 19852 
PHOENIX, AZ., AND VICINITY (INCLUDING NEW 
RIVER), GILA RIVER BASIN 
Detention basins, diversion channels, and channel 
improvements. 
TUCSON DIVERSION CHANNEL, GILA RIVER 
BASIN, AZ 
Channel improvements. 
WHITLOW RANCH DAM, QUEEN CREEK, GILA 
RIVER BASIN, AZ 
Dam and flood control basin. 
LOS ANGELES COUNTY DRAINAGE AREA, CA 
Reservoirs and flood channels for flood control and related 
purposes at an estimated construction cost not to exceed 
70 million. 
Added flood channels on Ballona Creek and tributaries to 
project. 
Provision of lands, easements, and rights-of-way and 
relocations by Federal Government instead of by local 
interests. (Resultant additional cost to the United 
States, $12,541,000.) 
Project extended to include additional flood control 
reservoirs, flood control channels, and debris basins for 
flood control and related purposes. Also authorized to be 
appropriated $25 million for further accomplishment of 
plan. 
Authorized to be appropriated an additional $25 million 
for prosecution of comprehensive plan approved in Flood 
Control Act of Aug 18, 1941. 
Authorized to be appropriated an additional $25 million 
for further prosecution of comprehensive plan. 
Rio Hondo channel improvement, Whittier Narrows 
Reservoir to Los Angeles River (in lieu of enlarging 
channel and bridges on San Gabriel River downstream 
from reservoir). Also authorized to be appropriated 
an additional $40 million for further prosecution of 
comprehensive plan. 
Authorized to be appropriated an additional $12,500,000 
for further prosecution of comprehensive plan. 
Authorized to be appropriated an additional $44 million 
for further prosecution of comprehensive plan. 
Authorized to be appropriated an additional $32 million 
for further prosecution of comprehensive plan. 
Authorized to be appropriated an additional $3,700,000 
for further prosecution of comprehensive plan. 
Authorized to be appropriated an additional $30 million 
for further prosecution of comprehensive plan. 
In addition to all previous authorizations, completion of 
improvements under the comprehensive plan for flood 
control in the Los Angeles River Basin at a presently 
estimated cost of $31 million for completion. 
LOS COCHES CREEK, SAN DIEGO COUNTY, CA 
Channel improvements. 
LYTLE AND WARM CREEKS, SANTA ANA RIVER 
BASIN, CA 
H. Doc. 216, 89th Cong., 
1st sess. 
H. Doc. 274, 80th Cong., 
1st sess. 
H. Doc. 220, 80th Cong., 
1st sess. 
None 
None 
None 
H. Doc. 838, 76th Cong., 
3d sess. 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
33-16

LOS ANGELES, CA, DISTRICT 
TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
13. Oct. 27, 1965 
14. July 14, 1960 
15. May 17, 1950 
16. June 22, 1936 
June 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
July 3, 1958 
17. Aug. 13, 1968 
18. Feb. 7, 19852 
Channels and levees. 
MOJAVE RIVER DAM, MOJAVE RIVER BASIN, CA 
Dam and reservoir, and an earthfill dike. 
PINE AND MATHEWS CANYONS DAMS, 
COLORADO RIVER BASIN, NV 
Dams and flood control basins. 
SANTA ANA RIVER BASIN (AND ORANGE 
COUNTY), CA 
Reservoirs and flood channels for flood control and 
related purposes for protection of metropolitan area of 
Orange County, at an estimated construction cost not to 
exceed $13 million. 
San Antonio and Chino Creeks channel portion of 
improvement. Authorized to be appropriated $6,500,000 
for initiation and partial accomplishment of plans for 
those creeks. Rescinded provisions of Flood Control Act 
of 1936, providing that local interests pay for 
relocations, lands, easements, and rights-of-way. 
(Estimated resultant additional cost to United States, 
$3,500,000.) 
Authorized to be appropriated an additional $2,500,000 for 
prosecution of projects approved in above flood control acts. 
Authorized to be appropriated an additional $10 million 
for prosecution of projects adopted in above-mentioned 
flood control acts, including projects on Lytle and Cajon 
Creeks for local flood protection at San Bernardino and 
Colton, CA. 
Authorized to be appropriated an additional $8 million 
for prosecution of projects approved in abovementioned 
flood control acts. 
SWEETWATER RIVER, SWEETWATER RIVER 
BASIN, CA 
Channel improvement, as part of a combined flood 
control and highway project. 
WEST MAGNESIA CANYON CHANNEL, RANCHO 
MIRAGE, CA 
Debris basin, channel improvements, energy dissipator, 
and preservation and enhancement of wildlife 
values. 
S. Doc. 53, 89th Cong., 
1st sess. 
H. Doc. 164, 86th Cong., 
1st sess. 
H. Doc. 530, 81st Cong., 
2d sess. 
None 
H. Doc. 688, 75th Cong., 
3d sess. 
None 
H. Doc. 534, 78th Cong., 
2d sess.' 
None 
H. Doc. 148, 90th Cong., 
1st sess. 
None 
1. Contains latest published map. 
2. Date approved by Chief of Engineers under provisions 
of section 205, Public Law 80-858, as amended. 
33-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 33-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Channel Islands Harbor, CA Completed 1985 $5,123,3451 $21,484,2892 
Dana Point Harbor, CA Completed 1984 4,737,5503 555,1474 
Marina del Rey, Los Angeles 
County, CA Completed 1981 4,238,7525 1,382,6136 
Newport Bay Harbor, CA Inactive 1982 796,8977 609,5698 
Port Hueneme, CA Completed (part) 1984 1,496,4009 1,258,90410 
& Deferred (part) 
Port San Luis, CA Completed & 1984 1,322,01911 952,22212 
Active (mod) 
Redondo Beach Harbor 
(King Harbor), CA Completed 1984 4,766,89813 1,472,08514 
San Diego Harbor, CA Completed 1985 28,092,19915 2,386,52616 
San Diego River and 
Mission Bay, CA Completed 1985 11,972,23217 4,789,65818 
1. Excludes $1,361,668 Navy funds; Coast Guard costs; 12. Includes $54,715 for maintenance for project prior to 
and $210,748 other contributed funds. modification by 1965 River and Harbor Act and $18,958 for 
2. Includes $26,593 for reconnaissance and condition reconnaissance and condition surveys. Includes $105,608 
surveys. Excludes $4,889,313 for maintenance accomplished expended in FY 1986. 
with Navy funds. 13. Excludes Coast Guard costs. 
3. Excludes $4,777,000 required contributed funds and 14. Includes $20,517 for reconnaissance and condition 
Coast Guard costs. survey costs since FY 1958. Includes $184,273 expended in 
4. Includes $45,147 for reconnaissance and condition FY 1986. 
surveys. Includes $5,191 expended in FY 1986. 15. Includes $154,704 for new work for previous projects; 
5. Excludes $4,238,752 required contributed funds; $86,352 public works funds; and $1,226,793 emergency relief 
$1,843,146 other contributed funds; and Coast Guard costs. funds. Excludes $254,795 Navy funds for dredging entrance 
6. Includes $88,153 for reconnaissance and condition channel in FY 1961 to depth of-42 feet mean lower low water 
surveys. Excludes $114,000 required contributed funds. (or 2 feet below project depth); $715,215 required contributed 
Includes $47,705 expended in FY 1986. funds; $1,900,063 other contributed funds, including $4,441 
7. Public Works Administration funds. Excludes $796,897 for betterments desired by local interests prior to modification 
required contributed funds and $1,100 preauthorization costs. by 1968 River and Harbor Act; and Coast Guard costs. 
8. Includes $125,646 for reconnaissance and condition 16. Includes $59,904 for maintenance for previous projets 
survey costs since FY 1958. Excludes $7,000 other contributed and $200,972 for reconnaissance and condition surveys since 
funds. FY 1958. In addition, includes $144 for retroactive pay 
9. Excludes $57,609 other contributed funds. Includes increase shown in "cost" figure only, as reported in 1958 
$65,934 expended in FY 1986. Annual Report, page 1430. Excludes $270,696 for maintenance 
10. Includes $61,068 for reconnaissance and condition accomplished with Navy funds. 
surveys.Includes $16,191 expended in FY 1986. 17. Includes $2,610,000 regular funds and excludes 
11. Includes $568,417 for new work prior to modification $2,910,000 required contributed funds, both for new work on 
by 1965 River and Harbor Act. Excludes Coast Guard costs. flood control project, "San Diego River Basin, Calif." Excludes 
Includes $100,171 expended in FY 1986. $557,832 other contributed funds. 
18. Includes $103,116 for reconnaissance and condition 
surveys. 
TABLE 33-D OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Anaheim Bay Harbor, 
Orange County, CA' 
Bird Rock area, La Jolla, 
San Diego County, CA2 
Coast of California, Point Mugu 
to San Pedro breakwater, CA 
Completed 
Completed 
Completed 
1967 
1967 
1972 
$89,119 
25,881 . 
1,253,5944 
33-18

LOS ANGELES, CA, DISTRICT 
TABLE 33-D (Cont'd)
OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Doheny Beach State Park (Doheny 
State Beach), CA Completed 1968 578,7175 
Las Tunas Beach, San Diego 
County, CA Active 1976 107,484 
Ocean Beach, San Diego 
County, CA 6 Completed 1960 7,912 
Oceanside, San Diego County, CA Completed 1982 4,367,4427 
San Diego (Sunset Cliffs), CA Active 1979 365,0008 
San Gabriel River to Newport Bay 
(Surfside-Sunset and Newport Beach), 
Orange County, CA Active 1985 9,722,1009 
Ventura-Pierpont area, CA Completed (part) 1969 715,81910 
& Deferred (part) 
1. The project authorized by the Act of Congress of 5. Excludes $431,260 required contributed funds. 
October 23, 1962, H. Doc. 602, 87th Cong., 2d sess., in lieu of 6. Plant in service. 
part of the original Anaheim Bay Harbor project is covered 7. Excludes $604,817 other contributed funds. Includes 
under San Gabriel River to Newport Bay (Surfside-Sunset $2,287 expended in FY 1986. 
and Newport Beach), Orange County, CA. 8. Excludes $180,438 required contributed funds. 
2. Authorized by Chief of Engineers under authority of 9. Excludes $4,615,866 for required contributed funds. 
section 103, Public Law 87-874. 10. Excludes $117,406 other contributed funds for beach- 
3. Excludes $75,614 required contributed funds. nourishment betterments and $618,949 required contributed 
4. Excludes $1,238,418 required contributed funds. funds. 
TABLE 33-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Allenville 7.1 C lt 1QQ 8 $nn 02- 
City Creek levee, San Bernardino 
County, CA' 
Gila River Basin, AZ: 
Camelsback Dam (Gila River) 
Gila and Salt Rivers levee and 
channel improvements 
Indian Bend Wash 
Lower Gila River levee and channel 
improvements (Gila River and 
tributaries downstream from 
Painted Rock Dam) 
Middle Gila River channel 
improvements, upper end of 
Safford Valley to Buttes damsite 
(Camelsback damsite to 
Salt River) 
Pinal Creek channel improvements 
(Globe) 
Santa Rosa Wash (Tat 
Momolikot Dam and 
'Lake St. Clair) 
Completed 
Deferred 
Active (part) 
& Deferred (part) 
Completed 
Inactive 
Active 
Deferred 
Completed 
400,0003 
1963 
1966 
1985 
1975 
1970 
1968 
1982 
73,2014 
31,778,2235 
2,413,051 
402,867 
121,5094 
10,218,9006 
33-19 
I ll L V 11G~ , vvmpieieu 17O * eu, vvV,vvv

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 33-E (Cont') 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Goleta, CA, and vicinity 
Holbrook levee, Little Colorado 
River, Colorado River Basin, AZ 
Needles, San Bernardino County, 
CA' 
Oro Grande Wash channel improvements, 
Mojave River Basin, CA' 
Quail Wash levee, Joshua Tree, San 
Bernardino County, CA' 
Ridgecrest, Kern County, CA' 
Rose Creek channel improvements, 
San Diego, CA' 
San Diego River (Mission Valley), 
San Diego River Basin, CA 
San Luis Rey River, San 
Luis Rey River Basin, CA 
Santa Ana River Basin, CA: 
Devil, East Twin, and Warm 
Creeks channel improvements 
and Lytle Creek levee 
Mill Creek levees 
Riverside levees 
San Jacinto River levee and 
Bautista Creek channel 
Santa Ana River Basin (and Orange 
County), CA: 
Aliso Creek Dam 
San Juan Dam 
Trabuco Dam 
Santa Clara River levee improvement, 
Santa Clara River 
Basin, CA 
Santa Maria Valley levees, Santa 
Maria River Basin, CA 
Santa Paula Creek channel and 
debris basins (including 
Mud Creek), Santa Clara 
River Basin, CA 
Sespe Creek at Fillmore, Ventura 
County, CA' 
South Fork of the Santa 
Clara River, Santa 
Clarita Valley, CA' 
Telegraph Canyon Creek, 
Chula Vista, CA' 
Tijuana River Basin, CA 
University Wash and Spring Brook, 
Riverside, CA 
Ventura River Basin, CA: 
Stewart Canyon debris basin and 
channel 
Ventura River levee 
Whitewater River Basin, CA: 
Banning levee-San Gorgonio 
River, Riverside County1' 
Chino Canyon improvements, 
Palm Springs' 
Active 
Completed 
Completed 
Completed 
Completed 
Terminated 
Completed 
Inactive 
Active 
Completed 
Completed 
Completed 
Completed 
Inactive 
Inactive 
Inactive 
Completed 
Completed 
Active 
Completed 
Active 
Active 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
1982 
1950 
1973 
1970 
1973 
1972 
1978 
1982 
1962 
1961 
1959 
1985 
1950 
1961 
1984 
1983 
1984 
1985 
1985 
1979 
1975 
1964 
1950 
1966 
1973 
500,000 
335,000 
1,000,0007 
1,000,0008 
212,745 
195,194 
982,4329 
1,708,437 
1,438,27510 
7,753,93711 
617,89012 
2,104,478 
9,258,20713 
67,361 
2,126,672 
10,079,85314 
4,769,52115 
3,999,99516 
632,15817 
840,88618 
1,703,031'19 
213,313 
939,90820 
1,349,63821 
97,868 
819,87822 
33-20

LOS ANGELES, CA, DISTRICT 
TABLE 33-E (Cont') 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Tahchevah Creek detention basin 
and channel improvements Completed 1967 1,420,55223 
Tahquitz Creek Inactive 1974 1,063,600 - 
Winslow (tributaries of Little 
Colorado River), Little Colorado 
River Basin, AZ Completed (part) 1973 1,831,300 
& Deferred (part) 
1. Authorized by Chief of Engineers under authority of 12. Excludes $35,830 other contributed funds. 
section 205, Public Law 80-858, as amended. 13. Excludes $711,994 other contributed funds. Includes 
2. Excludes $187,965 required contributed funds. $318 expended in FY 1986. 
3. Excludes $371,058 other contributed funds. 14. Excludes $106,364 other contributed funds. Includes 
4. Advance planning only. $978 expended in FY 1986. 
5. Excludes $304,720 required contributed funds and 15. Excludes non-Federal costs of $295,000 for local cooper- 
$3,121,769 other contributed funds. Includes $174,336 ation items not required and $49,458 other contributed funds. 
expended in FY 1986. Includes $58,849 expended in FY 1986. 
6. Includes $515 expended in FY 1986. 16. Excludes $559,516 required contributed funds. 
7. Excludes $619,912 required contributed funds and 17. Includes $25,718 expended in FY 1986. 
$91,160 other contributed funds. 18. Includes $64,073 expended in FY 1986. 
8. Excludes $514,806 required contributed funds and 19. International Boundary and Water Commission funds. 
$176,295 other contributed funds. 20. Excludes $179,148 other contributed funds. 
9. Excludes $251,000 required contributed funds and 21. Includes $6,000 Code 710 funds since FY 1977. Excludes 
$154,733 other contributed funds. $17,006 other contributed funds. 
10. Includes $301 expended in FY 1986. 22. Excludes $8,718 required contributed funds and $53,470 
11. Excludes $200,000 required contributed funds and other contributed funds. 
$1,641,668 other contributed funds. 23. Excludes $74,718 required contributed funds. 
TABLE 33-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Hodges Dam, San Dieguito 
River Basin, CA 1958 1978 
Sec. 12, Public 
Law 93-251 
Las Vegas Wash tributaries, 
Colorado River Basin, NV 1964 1977 $295,191 
Sec. 12, Public 
Law 93-251 
Villa Park Dam, Santa Ana 
River Basin (and Orange 
County), CA 1978 
Sec. 12, Public 
Law 93-251 
33-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 33-H RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 6 of Text) 
Project Date 
Channel Islands Harbor, CA August 1986 
Dana Point Harbor, CA July 1986 
Marina del Rey, Los Angeles County, CA June 1986 
San Diego River and Mission Bay, CA March 1986 
TABLE 33-I LOS ANGELES COUNTY DRAINAGE AREA CA: 
LATEST APPROVED ESTIMATED FIRST COSTS FOR ALL UNITS 
OF IMPROVEMENT UNDER EXISTING PROJECT 
(See Section 11 of Text)
Latest Approved Estimated Cost 19761 
Project Units Federal Local2 Total 
UNITS IN $70 MILLION PROJECT 
Los Angeles River Basin: 
Compton Creek, Los Angeles River to Hooper Ave. storm drain $2,510,500 - $2,510,500 
Haines Canyon 524,000 - 524,000 
Hansen Dam 11,343,000 - 11,343,000 
Los Angeles River channel: 
Lankershim Blvd. to Steward and Gray Rd. 40,807,300 - 40,807,300 
Los Angeles River channel, Long Beach Blvd. 34,200 - 34,200 
Sepulveda Dam 6,657,000 - 6,657,000 
Sycamore Wash 24,000 - 24,000 
Verdugo Wash, Concord St. to upper Canada bridge 1,087,000 - 1,087,000 
San Gabriel River Basin: 
San Gabriel River channel: 
San Gabriel Canyon to Santa Fe Dam 810,800 - 810,800 
Approach channel to Santa Fe Dam (remedial work) 951,900 - 951,900 
Santa Fe Dam to Walnut Creek 32,300 - 32,300 
Santa Fe Dam 12,647,000 - 12,647,000 
Rio Hondo Basin: 
Alhambra Wash 1,109,000 - 1,109,000 
Ballona Creek Basin: 
Ballona Creek channel and jetties 1,280,000 - 1,280,000 
Subtotal 79,818,000 - 79,818,000 
UNITS OUTSIDE $70 MILLION PROJECT 
Los Angeles River Basin: 
Blanchard Canyon 682,000 $476,000 1,158,000 
Blue Gum Canyon 533,000 233,000 766,000 
Burbank-Eastern system 7,149,000 1,850,000 8,999,000 
Burbank-Western system (lower) 1,279,000 268,000 1,547,000 
Burbank-Western system (upper) 4,930,000 2,959,000 7,889,000 
Caballero Creek 1,484,200 493,000 1,977,200 
Compton Creek: 
Los Angeles River to Hooper Ave. storm drain 149,000 - 149,000 
Hooper Ave. storm drain to Main St. 1,052,000 457,000 1,509,000 
Dead Horse Canyon and.Royal Blvd. channel 664,000 316,000 980,000 
Lopez Canyon diversion. 743,500 665,000 1,408,500 
Lopez Dam 729,000 - 729,000 
Los Angeles River channel: 
Owensmouth Ave. to Lankershim Blvd. 8,135,800 4,247,000 12,382,800 
Lankershim Blvd. to Stewart and Gray Rd. 9,202,100 - 9,202,100 
Steward and Gray Rd. to Santa Ana Branch, Pacific 
Electric railway bridge 5,860,900 81,000 5,941,900 
Santa Ana Branch, Pacific Electric railway bridge to 
Pacific Ocean 32,612,000 9,173,000 41,785,000 
Pacoima Wash channel 3,178,100 1,306,000 4,484,100 
Tujunga Wash channel 7,322,900 2,557,000 9,879,900 
33-22

LOS ANGELES, CA, DISTRICT 
TABLE 33-I (Cont'd) 
LOS ANGELES COUNTY DRAINAGE AREA CA: 
LATEST APPROVED ESTIMATED FIRST COSTS FOR ALL UNITS 
OF IMPROVEMENT UNDER EXISTING PROJECT 
(See Section 11 of Text)
Latest Approved Estimated Cost 1976' 
Project Units Federal Local2 Total 
Verdugo Wash, upper Canada bridge to debris basin 635,000 363,000 998,000 
Wilson Canyon and Mansfield St. channel 3,917,500 857,000 4,774,500 
Winery Canyon 413,000 265,000 678,000 
San Gabriel River Basin: 
Coyote Creek (including North Fork) 18,802,300 8,426,000 27,228,300 
Emerald Wash and Live Oak Wash 1,658,600 1,182,000 2,840,600 
Marshall Creek 2,577,900 968,000 3,545,900 
San Gabriel River channel: 
Santa Fe Dam to Whittier Narrows Dam 5,748,800 1,797,000 7,545,800 
Whittier Narrows Dam to Pacific Ocean 20,887,200 3,108,000 23,995,200 
Thompson Creek and San Jose Wash (including San Jose Creek) 21,274,600 6,095,000 27,369,600 
Walnut Creek inlet channel 2,879,000 1,091,000 3,970,000 
Walnut Creek system 17,232,600 8,715,000 25,947,600 
Whittier Narrows Dam , 32,254,000 38,000 32,292,000 
Rio Hondo Basin: 
Arcadia Wash system 5,236,800 1,893,000 7,129,800 
Eaton Wash 4,225,100 1,194,000 5,419,100 
Rio Hondo channel: 
Peck Rd. to Rosemead Blvd. (upper) 4,412,000 550,000 4,962,000 
Whittier Narrows Dam to Los Angeles River (lower) 8,165,000 2,565,000 10,730,000 
Rubio Canyon diversion 1,066,400 254,000 1,320,400 
Santa Anita Wash 3,045,700 434,000 3,479,700 
Sawpit Wash 2,348,600 745,000 3,093,600 
Sierra Madre Villa channel 781,400 366,000 1,147,400 
Sierra Madre Wash 1,732,000 248,000 1,980,000 
Ballona Creek Basin: 
Ballona Creek channel 746,600 - 746,600 
Benedict Canyon system 15,284,900 3,785,000 19,069,900 
Centinela Creek 4,083,800 4,788,000 8,871,800 
Sawtelle-Westwood system (including Sepulveda channel) 9,620,700 1,492,000 11,112,700 
Subtotal 274,736,000 76,300,000 351,036,000 
Grand total for comprehensive plan 354,554,000 76,300,000 430,854,000 
1. Excludes estimated cost for Code 710 funds and 
estimated cost for minor rehabilitation. 
2. Approved by Los Angeles County Flood Control District 
as of September 30, 1976, except for Walnut Creek system 
channel estimate, which was increased by $42,000 to permit 
rounding of overall non-Federal estimate to three significant 
figures. 
33-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 33-J SANTA ANA RIVER BASIN 
(AND ORANGE COUNTY), CA: 
LATEST APPROVED ESTIMATED FEDERAL FIRST COST 
FOR ALL UNITS 
(See Section 16 of Text) 
Estimated Cost 
Project Total Latest Revision Date 
ACTIVE UNIT' 
Completed: 
Brea Dam $1,189,0682 3 
Fullerton Dam 411,0762 3 
Lytle and Cajon Creeks channel improvements 7,612,000 3 
Prado Dam 9,473,2732 3 
San Antonio and Chino Creeks channel 10,924,170 3 
San Antonio Dam 7,001,1764 3 
Completed Except for Minor Completion Items: 
Carbon Canyon Dam and channel 5,150,0002 1961 
INACTIVE UNITS5 
Aliso Creek Dam 340,000 1954 
San Juan Dam 5,960,000 1954 
Trabuco Dam 2,190,000 1954 
DEAUTHORIZED UNIT 
Villa Park Dam 2,270,000 1954 
1. For details, see section 16 of text. 
2. Not including estimated cost of Code 710 funds. 
3. Plant in service. 
4. Includes $5,000 working funds. 
5. For additional information, see "Other Authorized 
Flood Control Projects." 
TABLE 33-K INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 19 of Text) 
Project Date 
Banning levee-San Gorgonio River, Whitewater River Basin, CA September 1986 
Chino Canyon improvements, Palm Springs, Whitewater River Basin, CA September 1986 
Riverside levees, Santa Ana River Basin, CA September 1986 
Rose Creek channel improvements, San Diego, CA July 1986 
San Diego River channel and levees, San Diego River Basin, CA July 1986 
San Jacinto River levee and Bautista Creek channel, Santa Ana 
River Basin, CA September 1986 
33-24

LOS ANGELES, CA, DISTRICT 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, Public Law 80-858, 
As Amended (Preauthorization) 
TABLE 33-L (See Section 21 of Text) 
Project Fiscal Year Costs 
Ephriam Canyon Wash, Nogales, AZ $13,659 
Lake Elsinore, Riverside County, CA 84,573 
Mission Zanja Creek, CA 86,468 
Newhall Creek, Newhall, CA 4,672 
Rialto Channel, Rialto, CA 81,940 
Santa Clara River, Fillmore, CA 69,485 
33-25

SAN FRANCISCO, CA, DISTRICT * 
This district comprises the Klamath River Basin in 
southern Oregon and portions of northern and western 
California consisting of drainage basins tributary to the 
Pacific Ocean from the Oregon-California State line on 
the north to Cape San Martin, CA, on the south, except 
for basins tributary to the San Francisco Bay system 
which lie east of the Benicia-Martinez Bridge. 
IMPROVEMENTS 
Navigation PagE 
1. Fisherman's Wharf Area, 
San Francisco Harbor, CA ............... 34-1 
2. Richmond Harbor (Deepening), CA ...... 34-2 
3. San Francisco Bay to Stockton, CA 
(John F. Baldwin and Stockton 
Ship Channels)......................... 34-2 
4. San Francisco Bay and 
Delta Model, CA ....................... 34-2 
5. Santa Cruz Harbor, CA .............. 34-3 
6. Reconnaissance and Condition 
Surveys ............................... 34-3 
7. Navigation Work under Special 
Authorization ............................ 34-3 
Flood Control 
8. Inspection of Completed Flood 
Control Projects........................ 34-3 
9. Flood Control Work under Special 
Authorization ......................... 34-3 
e General Investigations 
10. Surveys ............................... 
11. Collection and Study of Basic Data ........ 
12. Continuation of Planning 
and Engineering ........................ 
13. Advance Engineering and Design....... 
Tables 
Table 34-A 
Table 34-B 
Table 34-C 
Table 34-D 
Table 34-E 
Table 34-F 
Table 34-G 
Cost and Financial 
Statement ................... 
Authorizing Legislation ........ 
Other Authorized 
Navigation Projects .......... 
Other Authorized Beach 
Erosion Control Projects ........ 
Not Applicable 
Not Applicable 
Deauthorized Projects ........ 
Page 
34-4 
34-4 
34-4 
34-4 
34-5 
34-8 
34-8 
34-9 
34-9 
Navigation 
1. FISHERMAN'S WHARF AREA, SAN 
FRANCISCO HARBOR, CA 
Location. Fisherman's Wharf is located on San 
Francisco Bay on the northern waterfront of the City of 
San Francisco, approximately 2-1/2 miles east of the 
Golden Gate Bridge. (See USGS Quad Sheet San 
Francisco North, Calif. N3745-W12222.5/7.5) 
Existing project. The project consists of a concrete 
sheet pile breakwater starting 150 feet to the west of 
Hyde Street Pier; curving around the end of Hyde 
Street Pier and extending in an easterly direction to an 
extension of the east fender line of Pier 45. The entrance 
is a 165-foot channel between the breakwater and the 
end of Pier 45. The total length of this sheet pile 
breakwater is 1,509 feet. In addition there are two 
segmented breakwaters (28-foot solid walls with 6-foot 
openings), one 150 feet long extending in a northerly 
direction in the abandoned slip at the end of Pier 45, and 
the second is a 250-foot section 250 feet from the 
bayward end of, and on the west side of Pier 45. Also 
included are two 10-foot wide caps which may be used 
as walkways for the purpose of recreational pier fishing. 
Access is constructed to the 150-foot segmented breakwater, 
and the second, included in Phase II construction, 
will be access to the 1,509-foot solid breakwater. The 
estimated total cost for the project is $9,600,000 of 
which $8,900,000 is Federal cost and $700,000 is non- 
Federal cost. Final Federal and non-Federal costs are 
now being determined. Construction contract was 
awarded in February 1985 to Riedel International, Inc. 
of Portland, OR. Total contract award was $7,887,000. 
Construction will be completed by October 1986. 
Local cooperation. The Agreement of Local Cooperation, 
along with estimated costs, has been negotiated 
34-1

SAN FRANCISCO, CA, DISTRICT 
with, and accepted by, the local sponsor. The 221 
Agreement was signed by the local sponsor on 
13 November 1984. 
Terminal facilities. Project protects existing commercial 
and recreational waterfront structures: commercial 
fishing fleet and fish handling structures; 
recreational small craft harbor; and Hyde Street Pier 
used for historic ship berthing. 
Operations during fiscal year. New Work: Complete 
construction. 
2. RICHMOND HARBOR 
(DEEPENING), CA 
Location. Richmond Harbor is located in central San 
Francisco Bay, in Contra Costa County near the City of 
Richmond. 
Existing project. The existing navigation channel 
extends from deep water in San Francisco Bay to the 
Port of Richmond. The channel is maintained at a depth 
of -35 feet MLLW, except at its terminus in the upper 
Santa Fe Channel where the depth decreases to -30 feet 
MLLW. The width of the navigation channel is 600 feet 
for most of its depth. At Point Potrero, however, the 
channel flares into a turn and then continues at a width 
of 850 feet in a northerly direction to the entrance of the 
Santa Fe channel. A rubble-mound training wall 
extending 10,000 feet from Brooks Island is also provided 
in the Potrero Reach. 
Proposed improvements consists of a two-phased 
construction plan. Phase I would deepen the channel to 
-38 feet for bulk carriers, increase the minimum width 
to 600 feet and provide a turning basin of 1,200 feet 
diameter near Point Potrero. Approximately 1,700,000 
cubic yards of sediment are to be dredged and transported 
to an ocean disposal site 30 miles from the Golden 
Gate. In addition, 2,600 cubic yards of rock are to be 
excavated and disposed of at the former Kaiser Shipyard 
site. 
Phase II would deepen the channel to -41 feet, provide 
a minimum width of 600 feet and enlarge the turning 
basin to 1,425 feet diameter. Approximately 3,900,000 
cubic yards of sediment and 3,690 cubic yards of rock 
are to be excavated. The estimated cost of the project is 
$26,900,000. 
The existing project was authorized on October 27, 
1965. Subsequent projects were authorized by Acts 
adopted in 1917, 1930, 1935, 1938, 1945 and 1954. 
Local cooperation. The local sponsor is the City of 
Richmond which would share 25% of the project cost 
during construction and repay 10% over 30 years. The 
local sponsor would also provide a disposal area for 
rock. 
Terminal activities. The Port of Richmond encompasses 
ten privately-owned terminals and six terminals 
owned by the Port. 
Operations during fiscal year. Complete preconstruction 
planning and engineering. 
3. SAN FRANCISCO BAY TO 
STOCKTON, CA (JOHN F. 
BALDWIN AND STOCKTON 
SHIP CHANNELS) 
Location. John F. Baldwin Ship Channel. On 
navigation channels extending from entrance to San 
Francisco Bay to vicinity of Concord through San 
Francisco, Marin, Contra Costa, and Solano Counties. 
(See National Ocean Service Charts 18649, 18654 and 
18656 for respective areas.) 
Existing project. Project provides for modification 
of the existing San Francisco Harbor, Richmond Harbor, 
San Pablo Bay and Suisun Bay Channels to the 
vicinity of Concord to provide depths of 55 feet for San 
Francisco Bar Channel, 45 feet (currently 35 feet) for 
main internal bay channels upstream to the vicinity of 
Concord; enlargement and deepening to 45 feet (currently 
35 feet) of maneuvering areas adjacent to major 
petroleum refinery terminals along the channel route; 
and widening the Suisun Bay Channel. San Francisco 
Harbor Main Channel was completed in February 
1974. For the approved cost estimate (1986) of Federal 
cost (Corps), see Sacramento District Annual Report. 
Existing project was adopted by 1965 River and Harbor 
Act (H. Doec. 208, 89th Cong., 1st sess., contains latest 
published map). 
Local cooperation. See Sacramento District Annual 
Report. The local sponsor, Contra Costa County, supports 
the project. 
Terminal facilities. See Port Series No. 30, revised 
1983, No. 31, revised 1982, and No. 32, revised 1986, 
titled respectively: "The Ports of San Francisco, Redwood 
City, and Humboldt Bay, Calif."; "The Ports of Oakland, 
Alameda, Richmond, and the Ports on Carquinez Strait, 
Calif."; and "The Ports of Sacramento, Stockton, 
Pittsburg, and Antioch, Calif." Facilities are considered 
adequate for existing commerce and will be adequate 
for future commerce upon completion of new terminal 
facilities. 
Operations during fiscal year. New Work: Construction 
and continued planning activities. 
4. SAN FRANCISCO BAY AND 
DELTA MODEL, CA 
Location. The model, including a regional visitor 
center, is located in Sausalito, CA, adjacent to San 
Francisco Bay about two miles north of the Golden Gate 
Bridge. 
Existing project. The San Francisco Bay/Delta 
Model, which covers 17 miles of the Pacific Ocean 
beyond Golden Gate, all of San Francisco Bay proper, 
San Pablo Bay, Suisun Bay, and all of the Sacramento- 
San Joaquin Delta east of Suisun Bay to the cities of 
Sacramento on the northeast and Stockton and Tracy on 
the south, was constructed in a rehabilitated warehouse 
at Sausalito, CA, as a part of the San Francisco Bay and 
Tributaries, California, Study authorized by the River 
34-2

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
and Harbor Act of May 17, 1950 (PL 81-516, Section 
110). The model was authorized as an operation and 
maintenance project in the Water Resources Development 
Act of 1974 (PL 93-251, Section 8). The model 
successfully reproduces to the proper scale the rise and 
fall of the tide, flow and currents of water, salinity 
intrusion, and trends in disposition of sediments. It is a 
useful tool to examine forces existing in the bay and 
estuarine system and to predict results of proposed 
changes. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Operation 
and maintenance of the model continues. 
Historical summary. Original model construction 
was initiated 1956 and completed 1957. The addition of 
the Sacramento-San Joaquin Delta to the original 
model was initiated 1966 and completed 1969. The 
central exhibits were completed in December 1981. 
Continued testing of proposals affecting the environmental 
quality of the region including, but not limited 
to: salinity intrusion, dispersion of pollutants, water 
quality, improvements for navigation, dredging, bay 
fill, physical structures, other shoreline changes. Total 
cost of regional visitor exhibits and model as of September 
30, 1986, was $12,702,538, of which $5,351,442 
was for the regional visitor center, $888,372 for exhibits, 
and $6,462,724 for maintenance. 
5. SANTA CRUZ HARBOR, CA 
Location. Santa Cruz Harbor is located on the 
northernmost part of Monterey Bay, near the southeastern 
boundary of the City of Santa Cruz. 
Existing project. Adopted by Act of July 3, 1958. 
Provided for construction of jetties, 850 feet (south jetty) 
and 1,125 feet long. The entrance channel is 100 feet 
wide, 20 feet deep, and.900 feet long, with an additional 
370 feet at a depth of 15 feet. The inner harbor channel 
is 15 feet deep, 150 feet wide, and 800 feet long, with an 
additional 600 feet, 10 feet deep. The turning basin is 
300 feet wide, 207 feet long and 10 feet in depth. 
Project authorization also provided for a sand bypassing 
plant, if required. A cooperative agreement 
finalized in April 1986, provides the Santa Cruz Port 
District with a bypass system to be used in Santa Cruz 
HarboF. The primary component of the system is a 16 
inch hydraulic dredge. The federal government shared 
in the cost of the dredge system in return for the Port 
District assuming full responsibility for channel 
maintenance for the remaining life of the authorized 
project. The Port District will assume responsibility of 
maintenance dredging upon delivery of the dredge 
system in October-November 1986. 
Local cooperation. See above concerning the Cooperative 
Agreement for the dredge system. 
Terminal facilities. N/A 
Operations during fiscal year. Procurement of 
dredge system. The Port District will assume responsibility 
for maintenance of the harbor during FY 
87. 
6. RECONNAISSANCE AND 
CONDITION SURVEYS 
Reconnaissance and condition surveys of channels to 
be dredged in years other than FY 86 were conducted 
on the following projects: Bodega Bay; Crescent City 
Harbor; Moss Landing Harbor; Napa River; Petaluma 
River; Redwood City Harbor; Richardson Bay Channel; 
San Leandro Marina; San Rafael Creek; Suisun Bay 
Channel; and Suisun Channel, all in California. Fiscal 
year cost was $267,932. 
7. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to section 107, Public 
Law 86-645 (preauthorization). 
Fiscal year cost for preauthorization studies was 
$30,335 for Larkspur Ferry, Marin County, CA. 
8. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Section 3, Flood Control Act of June 22, 1936, as 
amended and supplemented, included requirement that 
local interests maintain and operate completed flood 
control works in accordance with regulations prescribed 
by the Secretary of War. Inspections made throughout 
the year to determine effectiveness of operation and 
maintenance by local interests of completed local protection 
projects and works constructed under emergency 
and special authorities of Sections 205 and 208 of the 
1948 Flood Control Act, Section 14 of the 1946 Flood 
Control Act, and Public Law 99, 84th Congress. Fiscal 
year cost was $214,809. Total cost to September 30, 
1986 was $1,184,203. Projects inspected included Alameda 
Creek, March 1986; Butte Creek, August 1986; Canyon 
Creek, August 1986; Coffee Creek, August 1986; Colma 
Creek, May 1986; Corte Madera Creek, April 1986; 
Coyote Creek, April 1986; East Weaver Creek, August 
1986; Eel River at Sandy Prairie, May 1986; Klamath 
River, April 1986; Mad River at Blue Lake, April 1986; 
Mark West Creek, July 1986; Meiss Lake, August 1986; 
Pajaro River, April 1986; Pinole Creek, March 1986; 
Redwood Creek, May 1986; Rheem Creek, March 1986; 
Rodeo Creek, March 1986; Russian River, August 1986; 
Salinas River, June 1986; San Leandro Creek, March 
1986; San Lorenzo Creek, March 1986; San Lorenzo 
River, January 1986; Santa Rosa Creek, July 1986; 
Smith River, April 1986; Sonoma Creek, July 1986; Van 
Duzen River, June 1986 and Wildcat Creek, July 1986. 
9. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended (preauthorization). 
Fiscal year costs were $137,402 for preauthorization 
studies of which $1,708 was for Papermill Creek, Point 
Reyes, CA; $37,488 for Pescadero and Butano Creeks, 
34-3

SAN FRANCISCO, CA, DISTRICT 
CA; $62,300 for Rohner Creek, Fortuna, CA; $19,037 for 
San Pedro Creek, Pacifica, CA; and $16,869 for Soquel 
Creek, Santa Cruz County, CA. 
Emergency flood control activities-repair, flood 
fighting and rescue work (Public Law 99, 84th 
Congress, and antecedent legislation). 
Fiscal year costs of $103,477 were incurred for 
emergency flood control activities, of which $185,641 
was for disaster preparedness; $14,151 for emergency 
operations; and -$96,315 for rehabilitation. 
Emergency bank protection (Section 14, 1946 
Flood Control Act, Public Law 526, 79th Congress). 
Fiscal year costs were $38,077 for emergency bank 
protection of which $3,085 was for Emeryville and 
Frontage Road, CA; $444 for Emeryville, Alameda, 
CA; $17,153 for Marina County WWTP, CA; $120 for 
Richardson Bay, Belvedere, CA; $42 for River Road, 
Monterey County, CA; -$2,851 for San Francisquito 
Creek, Site 74, CA; $20,084 for Willow County, Water 
District Wells, Mendocino, CA. 
General Investigations 
10. SURVEYS 
Fiscal year costs for surveys were $1,058,716, of 
which $184,824 was for navigation; $815,150 for flood 
damage prevention; $53,427 for inventory of dams; and 
$5,315 for coordination with other agencies. 
11. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year total costs of $37,500 were incurred, of 
which $35,459 was for flood plain management service 
program and $2,041 was for hydrologic studies. 
12. CONTINUATION OF PLANNING 
AND ENGINEERING 
Fiscal year total costs were $731,243 of which $298 
was for Fisherman's Wharf, CA, $176,839 for Oakland 
Inner Harbor, CA; $138,609 for Oakland Outer Harbor 
(Deepening), CA, and $415,597 for Richmond Harbor, 
(Deepening), CA. 
13. ADVANCE ENGINEERING AND 
DESIGN 
NOYO RIVER AND HARBOR, CA 
Noyo River rises in the Coast Range, flows westerly, 
and empties into Noyo Harbor. Noyo Harbor is a cove on 
the California Coast about 87 miles south of Humboldt 
Bay and 135 miles northwest of San Francisco. The 
1962 Rivers and Harbors Act, modified by the 1976 
Water Resources'Development Act, authorized up to 
two breakwaters as necessary to provide'protection. 
The 1976 WRDA authorized construction of additional 
channel improvements. Recommended plans of improvement 
for the breakwater and channel improvement 
were previously considered as a single project. Due to 
significant differences iri the time required for planning 
and construction, each part is now reported separately. 
The plans df improvement for Noyo River and Harbor 
(Breakwater), CA, provide for one or two breakwaters 
immediately west of the entrance channel in Noyo 
Harbor. Estimated preconstruction planning cost is 
$1,560,000. Total costs during the fiscal year were 
$12,353 with General Investigation funds. Planning is 
about 65 percent complete. Model studies, using a 
physical model to test alternative plans, were initiated 
in FY 84 and completed in FY 86. 
The plan of improvement for Noyo River and Harbor 
(Channel Extension), CA, provides for a 60-foot wide 
channel, 7 feet deep, for a distance of about 3,000 feet 
upstream from the end of the existing Federal project to 
the Dolphin Isle Marina. Estimated preconstruction 
planning cost is $580,000. Total costs during the fiscal 
year were $71 with General Investigation funds. 
34-4

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 34-A 
See 
Section 
in Text Project 
Bodega Bay, CA 
Crescent City 
Harbor, CA 
1. Fisherman's Wharf 
Area, San Francisco 
Harbor, CA 
Halfmoon Bay, CA 
Humboldt Harbor 
and Bay, CA 
Moss Landing 
Harbor, CA 
Napa River, CA 
Noyo River and 
Harbor, CA 
Oakland Harbor, CA 
COST AND FINANCIAL STATEMENT 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Total Cost to 
FY 83 FY 84 FY 85 FY 86 Sep 30, 1986 
-- - - 1,226,765' 2 
99,249 4,314 - - 1,226,7651 3 
- 16,270 204,651 67,210 1,082,5254 
- 16,270 179,999 82,427 1,073,0904 
-- - - 397,7795 
- - - 397,7796 
802,000 - -44,000 - 9,454,9726 
419,303 850,808 11,409 1,993 9,454,9726 
2,875,300 230,000 1,093,278 5.110,486 18,487,7387 
645,408 2,333,215 1,657,383 5,004,776 18,371,0037 
-- - - 525,0008 
-- - - 525,0008 
- 350,000 3,000,000 5,265,000 8,615,00041 
- 180,543 1,138,269 7,151,055 8,289,86741 
- - - 6,697,39643 44 
-- - - 6,697,39643 44 
- - 271,000 10,000 2,088,06743 44 
- - 241,765 36,818 2,085,61144 ' 
- - - 9,847,2994�0 
-- - - 9,847,2999 40 
8,562,200 1,475,009 6,107,060 4,236,000 53,933,94110 40 
2,683,029 6,304,195 6,983,429 4,414,387 53,894,2261o 40 
-- - - 338,21511 40 
- - - 338,21511 40 
59,000 448,000 161,583 36,570 3,966,78412 40 
47,971 427,295 164,383 52,051 3,951,36512 40 
- - - 1,021,274'3 40 
-- - - 1,021,27413 40 
72,000 38,254 -426 26,583 1,840,22013 14 40 
240,156 43,816 -426 26,583 1,840,22013 14 40 
79,000 275,000 - - 1,521,482's 16 
181,133 156,999 115,747 12,423 1,520,654's 17 
826,900 530,000 405,000 598,000 6,253,65418 19 
314,635 991,649 470,898 534,352 6,183,59418 19 
- - - 222,81020 40 
- - - 222,81020 40 
... 9,646,98421 40 
... 9,646,98421 40 
1,796,000 1,294,000 1,325,973 1,075,000 28,717,24622 40 
1,771,880 1,251,503 1,414,766 1,060,589 28,689,11022 40 
34-5

SAN FRANCISCO, CA, DISTRICT 
TABLE 34-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep 30, 1986 
Petaluma River, CA 
Redwood City 
Harbor, CA 
2. Richmond Harbor, CA 
3. San Francisco Bay 
to Stockton, CA 
(John F. Baldwin and 
Stockton Ship 
Channels) 
4. San Francisco Bay 
and Delta Model, CA 
San Francisco 
Harbor, CA 
San Francisco 
Harbor and Bay, CA 
(Removal of Drift) 
San Leandro 
Marina, CA 
San Pablo Bay 
and Mare Island 
Strait, CA 
San Rafael, CA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
297,14623 40 
297,14623 40 
670,000 1,025,407 
912,547 1,797,546 
26,272 -168,185 7,813,65324 40 
446,628 -115,226 7,811,95424 40 
- - 1,672,72225 40 
- - 1,672,72225 40 
44,000 3,079,000 -588,465 14,674 
61,044 2,868,440 -374,925 14,674 
-- 15,000 370,000 
- - 345,184 
1,650,000 2,047,000 601,226 1,074,000 
493,783 2,663,006 1,136,050 1,097,818 
7,340,62826 40 
7,340,628 40 
3,271,69527 28 
3,231,87927 28 
16,572,342" 
16,561,69129 
- - - 164,689 
- - - 164,689 
432,000 1,200,000 10,580,000 5,166,000 24,288,200 
467,014 628,744 10,246,428 5,877,031 23,794,281 
1,782,000 1,141,000 1,159,000 1,100,000 
1,530,770 1,400,852 1,089,231 1,067,138 
12,882,700 
12,702,540 
-.- - - 2,689,35628 30 
- - - 2,689,3562 30 
1,401,000 424,860 2,087,500 1,566,340 22,489,24531 
1,409,397 478,865 2,042,272 1,726,548 22,465,29031 
-- - - - 40 
-- - - - 40 
1,073,000 1,143,000 1,018,000 930,000 20,976,18240 
1,075,404 1,040,828 1,010,551 1,047,460 20,835,71440 
- 410,176 147,205 44,171 1,245,90332 
45 274,097 261,171 66,284 1,245,90332 
- - - 1,369,3722 33 
- - - 1,369,3722 33 
1,465,000 3,696,143 1,725,125 1,939,000 
1,841,748 3,615,383 1,996,024 1,978,259 
32,311,70134 
32,309,7123 
32,35940 47 
32.35940 47 
26,924 
26,924 
8,545 970,994 2,988,36440 46 
8,545 932,781 2,950,15140 46 
34-6

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 34-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep 30, 1986 
5. Santa Cruz New Work 
Harbor, CA Approp. - - 120,000 2,134,000 4,106,340 
(Federal Funds) Cost - - 94,699 1,960,377 3,907,416 
(Contrib. Funds) New Work 
Contrib. - - - - 160,000 
Cost - - - - 160,000O 
Maint. 
Approp. 742,000 659,000 834,000 994,500 9,474,659 
Cost 566,161 769,335 935,374 1,035,571 9,465,027 
Suisun Bay Channel, New Work 
CA Approp. - - - - - 
Cost - - - - - 
Maint. 
Approp. 594,000 312,000 204,725 1,797 2,761,860 37 
Cost 782,935 305,091 204,887 8,568 2,758,974 s7 
Suisun Channel, CA New Work 
Approp. - - - - 217,677w 
Cost - - - - 217,677" 
Maint. 
Approp. -32,000 15,130 651 51,594 1,403,332" 
Cost 94,431 15,130 651 51,594 1,403,332" 
1. Includes $641,800 for jetties, bulkheads, main Bodega 
Bay Channel and turning basin completed in 1943. 
2. Includes $585,000 for Preconstruction Planning 
($456,000 Construction, General funds and $129,000 General 
Investigation funds). 
3. Includes $584,563 Preconstruction Planning costs 
($455,563 Construction, General costs and $129,000 General 
Investigation costs). 
4. Includes $147,975 for reconnaissance and condition 
surveys, FY 1956-1986. 
5. Excludes contributed funds of $2,000. 
6. Excludes contributed funds of $271,116 and $2,138 
surplus material from Corps military activities. 
7. Excludes contributed funds of $44,340. Includes 
$75,795 for reconnaissance and condition surveys, FY 1956- 
1986.
8. Excludes $2,000 contributed funds in lieu of royaltyfree 
rock. 
9. Includes $2,261,371 for previous project. Excludes 
$95,000 contributed funds for existing project. 
10. Includes $98,206 for previous project and $1,710 for 
reconnaissance and condition surveys, FY 1956-1986. 
11. Excludes $5,337 previous project costs. 
12. Excludes $8,539 surplus material from Corps' military 
activities. Includes $67,265 for reconnaissance and condition 
surveys, FY 1956-1986. Excludes contributed funds of 
$180,200. 
13. Excludes previous project costs. Excludes $154,500 
contributed funds. 
14. Includes $268,096 for reconnaissance and condition 
surveys, FY 1956-1986. 
15. Includes $11,985 for previous project. Excludes $7,180 
contributed funds for previous project. 
16. Includes $1,223,000 for Preconstruction Planning 
($773,000 for Breakwater of which $500,000 allocated under 
Construction, General and $273,000 under General Investigations); 
($450,000 for Channel Extension of which $165,000 
allocated under Construction, General and $285,000 under 
General Investigations). 
17. Includes $1,222,172 Preconstruction cost ($772,172 for 
Breakwater of which $500,000 was under Construction, 
General and $272,172 under General Investigations); ($450,000 
for Channel Extension of which $165,000 under Construction, 
General and $285,000 under General Investigations). 
18. Includes $32,097 for previous project and $15,436 for 
reconnaissance and condition surveys, FY 1956-1986. Excludes 
contributed funds of $820 for previous project. 
19. Excludes contributed funds of $4,000 in lieu of providing 
dike disposal areas on existing project. 
20. Excludes contributed funds of $1,700. 
21. Includes $2,899,232 for previous projects. Excludes 
$397,266 contributed funds on existing project. 
22. Includes $684,028 for previous projects and $774 for 
reconnaissance and condition surveys, FY 1956-1986. 
23. Includes $212,083 for previous project. Excludes contributed 
funds of $15,559 for previous project. 
24. Includes $314,692 for previous project and $122,402 
for reconnaissance and condition surveys, FY 1956-1986. Excludes 
contributed funds of $178,308. 
25. Includes previous project costs $31,443. Excludes 
$119,572 contributed funds for existing project. 
26. Includes $106,368 for reconnaissance and condition 
surveys, FY 1956-1986. 
27. Excludes contributed funds of $524,778. Includes 
$105,000 Public Works Administration funds. 
28. Excludes modification authorized October 27, 1965, 
under project "San Francisco Bay to Stockton, CA (John F. 
Baldwin and Stockton Ship Channels)." 
29. Excludes $34,800 contributed funds. Includes $3,364 
for reconnaissance and condition surveys, FY 1956-1986. 
30. Includes $1,030,399 for previous projects. Excludes 
134,591 contributed funds for existing project. Includes 
193,000 Public Works Administration funds. 
31. Includes $475,321 for previous projects and $23,659 
for reconnaissance and condition surveys, FY 1956-1986. 
32. Authorized by FC Act of 1965 (Sec. 201); Maintenance 
R&H Act of 1970 (Sec. 103). Includes $101,103 for reconnaissance 
and condition surveys FY 1979-1986. See FY 1977 
Annual Report for last full report. Excludes contributed 
funds of $746,947. 
33. Includes $1,086,703 for previous projects. 
34. Includes $1,359,380 for previous projects and $2,272 
for reconnaissance and condition surveys, FY 1956-1986. 
35. Excludes $810,046 contributed funds. 
34-7

SAN FRANCISCO, CA, DISTRICT 
36. See Sacramento District FY 1974 Annual Report for 
details. 
37. Project maintenance responsibility to Point Edith was 
transferred to San Francisco DistrictJanuary 1,1974. Excludes 
Sacramento District's portion. Includes $11,610 for reconnaissance 
and project condition surveys, FY 1976-1986. 
38. Project maintenance assigned to San Francisco District 
from Sacramento District January 1, 1974. See Sacramento 
District 1972 Annual Report for full report. 
39. Includes $95,823 for reconnaissance and condition 
surveys, FY 1978-1986. 
40. See FY 1981 Annual Report for last full report. 
TABLE 34-B AUTHORIZING 
41. Excludes Contributed Funds of $443,953. 
42. See Sacramento District FY 1985 Annual Report for 
full report. 
43. Excludes $100,000 contributed funds and $105,000 
contributed in lieu of royalty-free rock. 
44. See FY 1979 Annual Report for last full report. 
45. Includes $17,567 for reconnaissance and condition 
surveys, FY 1970-1986. 
46. Includes $138,417 for reconnaissance and condition 
surveys, FY 1970-1986. 
47. Excludes $41,094 contributed funds. 
LEGISLATION 
See Date 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
1. FISHERMAN'S WHARF AREA-SAN FRANCISCO 
CA 
Nov. 14, 1983 Breakwater. Cont. Res. (H.J. Res. 413) 
of 1984, Public Law 
98-151, 98th Cong., 
1st sess. 
TABLE 34-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Berkeley Harbor, CA' Completed 1966 155,5502 - 
Berkeley Marina, CA' Completed 1979 505,2013 - 
Lower San Francisco Bay, CA Inactive 1935 - - 
Monterey Harbor, CA Completed 1971 1,108,1824 85,880b 
San Francisco Marina (Gas House Cove), 
CA' Completed 1974 180,4726 - 
San Francisco Harbor (Islais Creek), CAx Completed 1976 848,2277 - 
San Leandro Marina (Breakwater), CA' Completed 1976 210,3908 - 
1. Authorized by Chief of Engineers (Sec. 107, Public 
Law 86-645). 
2. Excludes $155,551 contributed funds. 
3. Excludes $378,989 contributed funds. 
4. Includes $207,800 Public Works Administration funds 
and breakwater modifications (1960 Act) placed inactive 
1974. 
5. Includes $8,041 for reconnaissance and condition 
surveys for FY 1956-1986. 
6. Includes preauthorization costs $26,855 and excludes 
contributed funds $153,618. 
7. Includes $94,550 preauthorization costs. 
8. Includes $72,000 preauthorization costs and excludes 
contributed funds $138,189. 
34-8

TABLE 34-D 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
Project Status 
For Last 
Full Report 
See Annual 
Report For 
Cost to Sep 30, 1986 
Operation and 
Construction Maintenance 
Humboldt Bay, CA Inactive 1958 2,000 
Santa Cruz County, CA Inactive 1966 245,639 
TABLE 34-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Knights Valley Lake, R.R. Basin, 
CA 1974 Aug. 5, 1977 - 
Oakland Harbor, CA (Deepen Tidal 
Canal) 1981 Nov. 6, 1977 - 
Oakland Harbor, CA (Fruitvale 
Avenue Bridge) 1981 Nov. 6, 1977 
San Lorenzo Creek, CA (Upper 
Portion) 1962 Nov. 6, 1977 - 
San Pablo Bay and Mare Island 
Strait, CA (Approaches to Vallejo 
and South Vallejo) 1982 Nov. 6, 1977 - 
34-9

SACRAMENTO, CA, DISTRICT * 
This district comprises basins of Suisun Bay and San 
Joaquin and Sacramento Rivers in California; Goose 
Lake in Oregon; basins of the Great Salt Lake and 
Sevier Lake in Utah; an intervening portion of Great 
Basin in northern Nevada, northern California, and 
southeastern Idaho; and the upper Colorado River 
basin, which is in southwestern Wyoming, eastern 
Utah, northeastern Arizona, and western Colorado, 
west of the Continental Divide. 
IMPROVEMENTS 
Navigation Page 
1. Sacramento River, CA ................... 35-1 
2. Sacramento River Deep Water 
Ship Channel, CA ........................ 
3. San Francisco Bay to Stockton, CA 
(John F. Baldwin and Stockton 
Ship Channels) .......................... 35-2 
4. San Joaquin River, CA ................... 35-3 
Flood Control 
5. Buchanan Dam-H.V. Eastman Lake, 
Chowchilla River, CA .................. 35-4 
6. Calaveras River and Littlejohn 
Creek and tributaries, including 
New Hogan Lake and Farmington 
Dam, CA ............................... 35-4 
7. Corte Madera Creek, CA ............... 35-5 
8. Fairfield Vicinity Streams, CA ........... 
9. Hidden Dam-Hensley Lake, Fresno 
River, CA .......... ,.................. 35-6 
10. Isabella Lake, Kern River, CA ............ 35-7 
11. Kaweah and Tule Rivers, including 
Terminus Dam and Success Lake, CA ..... 35-8 
12. Little Dell Lake, UT ................... 
13. Lower San Joaquin River, CA ......... 35-9 
14. Martis Creek Lake, Martis Creek, 
NV and CA ............................. 35-9 
15. Merced County Streams, CA.............. 
16. Merced County Stream Group, CA ......... 35-10 
17. Pine Flat Lake and Kings River, 
CA ...................................... 35-10 
18. Russian River Basin, including 
Dry Creek (Warm Springs Lake) and 
Lake Mendocino (Coyote Valley 
Dam), CA ........................... 35-11 
Flood Control (Cont'd) Page 
19. Sacramento River and tributaries, 
CA from Collinsville to Shasta Dam ...... 35-12 
20. Walnut Creek, CA ........................ 35-14 
21. Wildcat and San Pablo Creeks, CA ...... 35-15 
22. Inspection of Completed Flood 
Control Projects ......................... 35-15 
23. Flood Control Work under Special 
Authorization........................... 35-16 
24. Scheduling Flood Control Reservoir 
Operations............................... 35-16 
Multiple-Purpose Projects Including Power 
25. New Melones Lake, CA ................... 35-16 
General Investigations 
26. Surveys ................................. 35-18 
27. Collection and Study of'Basic Data ........ 35-18 
28. Research and Development ............... 35-18 
29. Advance Engineering and Design........ 35-19 
30. Other Work under Special Authority ...... 35-20 
Tables 
Table 35-A Cost and Financial 
Table 35-B 
Table 35-C 
Table 35-D 
Table 35-E 
Table 35-F 
Table 35-G 
Statement ................... 35-21 
Authorizing 
Legislation ..................... 35-26 
Other Authorized 
Navigation Projects ........... 35-28 
Not Applicable 
Other Authorized Flood 
Control Projects .............. 35-29 
Not Applicable 
Deauthorized Projects .......... 35-31 
35-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. SACRAMENTO RIVER, CA 
Location. Rises in Trinity Mountains in north-central 
California, flows generally southerly about 374 miles 
and empties into Suisun Bay, an arm of San Francisco 
Bay, at Collinsville, CA. (See Geological Survey topographic 
map of Sacramento Valley, CA.) 
Previous projects. For details see page 1985 of 
Annual Report for 1915 and page 1708 of Annual 
Report for 1938. 
Existing project. For description of Sacramento 
Deep Water Ship Channel, see Annual Report for 1969. 
Total first cost for completed portion was $43,932,558 
($39,560,558 Federal (Corps), $300,000 (Coast Guard), 
and $4,072,000 non-Federal for lands and damages, 
including relocations) and excludes local interests cost 
$10,741,000 (June 1963) for 30-foot deep water ship 
channel and 13-foot deep connecting canal basic terminal 
facilities required under terms of project authorization. 
Project also provides for a shallow-draft channel 
10 feet deep at mean lower low water 150 to 200 feet 
bottom width, from Suisun Bay to Sacramento, CA, 60 
miles; a depth of 6 feet at low water between Sacramento 
and Colusa, 85 miles; a depth of 5 feet at low water 
between Colusa and:Chico Landing, 50 miles; and such 
depths as practicable between Chico Landing and Red 
Bluff, 53 miles, a total distance of 248 miles. Estimated 
Federal cost (July 1973) of new work for shallow-draft 
river channel is $1,360,000 (includes $1,163,000 for 
deferred portion between Colusa and Chico Landing). 
(See table 35-H on tidal and flood conditions prevailing.) 
Local cooperation. Fully complied with for deep 
water ship channel project. None required on shallowdraft 
feature. 
Terminal facilities. Piers, wharves, and docks at 
Port of Sacramento for shallow-draft navigation are 
open-pile structures with timber decks, some of which 
are designed to meet extreme high waters of flood 
stages. All main wharves at Sacramento have rail 
connections. Three of above facilities are owned by city 
of Sacramento and remainder by private interests; all 
are privately operated. For full description see "Port 
and Terminal Facilities at the Ports of Sacramento, 
Stockton, Pittsburg and Antioch, Calif., 1986." Deep 
water terminal facilities comprise wharves and piers, 
administration and storage buildings, and belt railroad 
facilities. Majority of these facilities are owned and 
operated by Sacramento-Yolo Port District; remainder 
are privately owned and operated. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. New 
work, Deep Water Ship Channel: None. Maintenance: 
Shallow Draft Channel: Minor maintenance and operation 
activities continued in Sacramento River, Sacramento 
upstream to Colusa. Deep Water Ship Channel: 
Maintenance and operation activities continued. Fiscal 
year costs for major maintenance items consisted of: 
Maintenance dredging on Sacramento River, vicinity of 
Rio Vista by suction dredge initiated by contract, 
$1,448,128. 
Historical summary. Construction of 7-foot shallowdraft 
channel below Sacramento was initiated in September 
1899 and completed in 1904. Modified 10-foot 
shallow-draft channel up to Sacramento was initiated 
in FY 1928 and completed in 1931. Shallow-draft 
channel above Sacramento was begun in April 1946 but 
new work was discontinued when about 48 percent 
complete. In February 1974, remaining work for shallowdraft 
portion of project, provision of a 5-foot depth 
between Colusa and Chico Landing (50 miles), was 
reclassified as "deferred." Channel is navigable all 
year; however, there is no regular navigation above 
Colusa, 145 miles above river mouth. Construction of 
30-foot deep water ship channel was initiated in July 
1949; improvement dredging by continuing contracts 
resulted in provision of an operational facility for 
oceangoing vessels during June 1963. Bascule bridge 
was completed in April 1960, barge lock in August 
1961, barge canal in November 1961, and entire deep 
water ship channel in June 1970. 
2. SACRAMENTO RIVER DEEP 
WATER SHIP CHANNEL, CA 
Location. On the Sacramento River between Collinsville 
and the Port of Sacramento, a distance of about 
43 miles, in the counties of Sacramento, Solano, and 
Yolo, CA. 
Existing project. Project provides for deepening to 
35 feet the Suisun Bay and Sacramento River Deep 
Water Ship Channels from New York Slough to the 
Port of Sacramento, and the Avon to New York Slough 
reach to 35 feet which will be accomplished under the 
San Francisco Bay to Stockton (John F. Baldwin and 
Stockton Ship Channels) project, and widening the 
channel 250 to 350 feet as necessary. 
Selected plan also provides for a water quality 
monitoring program, authority to construct a submerged 
sill, 45 acres of land for establishment of 
wetland habitat, and 156 acres of land for upland 
habitat to mitigate for losses of such habitat. 
Project estimate (October 1986) is $74,100,000 (includes 
an allowance for estimated inflation through the 
construction period) comprising Federal cost (Corps) of 
$40,100,000; Federal cost (Coast Guard) for navigation 
aids $600,000; and non-Federal cost of $34,000,000 for 
lands and damages, relocations, and spoil retention 
dikes, including the cash contribution ($13,600,000) 
that local interests must pay. Existing project was 
adopted by Supplemental Appropriations Act of 1985, 
August 15, 1985 (Public Law 99-88), 99th Cong., 1st 
sess. 
Local cooperation. Local interests, through a public 
body legally authorized and financially capable, must 
give assurances they will furnish lands, easements, 
rights-of-way, and dredged material disposal areas; 
35-2

SACRAMENTO, CA, DISTRICT 
modify or relocate buildings, utilities, roads, and other 
facilities where necessary in the construction of the 
project; and provide retention dikes for dredged material 
disposal area; and pay 25 percent of the costs allocated 
to deep draft navigation during construction, presently 
estimated at $13,600,000. Local interests have agreed to 
make all required payments concurrently with project 
construction. A Local Cooperation Agreement (sec. 221) 
was executed June 27, 1986. 
Terminal facilities. All main wharves at Sacramento 
have rail connections. Three of above facilities are 
owned by city of Sacramento and remainder by private 
interests; all are privately operated. For full description 
see "Port and Terminal Facilities at the Ports of 
Sacramento, Stockton, Pittsburg and Antioch, Calif., 
1986." Deep water terminal facilities comprise wharves 
and piers, administration and storage buildings, and 
belt railroad facilities. Majority of these facilities are 
owned and operated by Sacramento-Yolo Port District; 
remainder are privately owned and operated. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. General 
Design Memorandum combined with Environmental 
Impact Statement was submitted in April 1986, final 
comments incorporated and General Design Memorandum 
resubmitted. A Local Cooperation Agreement 
(sec. 221) was executed June 27, 1986. 
3. SAN FRANCISCO BAY TO 
STOCKTON, CA (JOHN F. 
BALDWIN AND STOCKTON 
SHIP CHANNELS) 
Location. On navigation channels extending from 
entrance to San Francisco Bay to Port of Stockton 
through San Francisco, Marin, Contra Costa, Solano, 
Sacramento, and San Joaquin Counties. (See Coast and 
Geodetic Charts 5527 and 5532-5534 for respective 
areas.) 
-Existing project. Project provides for modification 
of existing San Francisco Harbor, Richmond Harbor, 
San Pablo Bay and Mare Island Strait, Suisun Bay 
Channel, and San Joaquin River navigation projects to 
provide depths of 55 feet for San Francisco Bar Channel, 
45 feet for main internal bay channels upstream to 
vicinity of Avon, and 35 feet from Avon to Stockton; 
enlargement and deepening to 45 feet of maneuvering 
areas adjacent to major petroleum refinery terminals 
along channel route; widening Suisun Bay Channel; 
reclaiming shoreline marshes and inundated or lowlying 
areas by spoil deposit for public recreation and for 
industrial use; providing basic recreation facilities on 
some of the reclaimed areas for public use; and placing 
additional rock revetmenton waterside of levees bordering 
channels. 
Project estimate (October 1986) is $172,657,000, 
(includes an allowance for estimated inflation through 
the construction period) comprising Federal cost (Corps) 
of $132,000,000, including basic recreation facilities; 
Federal cost (Coast Guard) for navigation aids 
$1,100,000; and non-Federal cost of $39,557,000 for 
lands and damages, relocations, berthing areas, and 
spoil retention dikes, including the cash contribution 
($1,007,000) that local interests must make for land 
enhancement at time of construction. Local i.nterests 
must also pay, contribute in kind, or repay with interest 
one-half of separable cost of project allocated to 
recreation. Existing project was adopted by 1965 River 
and Harbor Act (H. Doc. 208, 89th Cong., 1st sess., 
contains latest published map). 
Local cooperation. Local interests, through a public 
body legally authorized and financially capable, must 
give assurances they will furnish lands, easements, and 
rights-of-way for construction and future maintenance 
of the project and for aids to navigation, including spoildisposal 
areas designated by the Chief of Engineers; 
provide necessary spoil retention dikes, bulkheads, and, 
embankments except as applicable to spoil-disposal 
areas designated as public recreation areas; make 
utility modifications and relocations required for construction, 
including new bridges or bridge alterations 
(except for railroad bridges), and absorb any increased 
annual maintenance and operation costs resulting therefrom; 
provide and maintain all necessary berthing 
areas, at a depth commensurate with project depth, at 
all terminals and wharves to be served by the deepened 
channels; and in recognition of the local land enhancement 
benefits to result from landfill during dredging, 
contribute to the United States 4 cents per cubic yard of 
all spoil material placed during initial construction for 
modification of Suisun Bay Channel project on areas not 
developed for public use. Local interests must-also give 
satisfactory assurances, before starting construction of 
the affected units, that they will maintain and operate 
the Federally provided recreation areas and facilities, 
continue to maintain to adequate standards the levees 
altered, set back or provided revetment protection, and 
hold the U.S. Government free from damages due to 
deposition of spoil and construction of new levees or 
reconstruction of existing levees. Local interests, represented 
by Board of Supervisors of Contra Costa County 
and Stockton Port District, must, at time of construction, 
contribute $1,007,000 in cash for land enhancement; 
pay, contribute in kind, or repay with interest one-half 
of separable cost of project allocated to recreation; and 
maintain and operate basic recreation facilities after 
construction and install additional basic facilities 
required as demands on area expand. No work shall be 
undertaken on a modification of Suisun Bay Channel 
project unit to deepen the channel to more than 35 feet 
between Avon and a proposed refinery or manufacturing 
plant, until local interests furnish formal assurances 
and definite plans for such installation within the Avon- 
Chipps Island reach of channel. Also, no work shall be 
undertaken on modification of San Joaquin River 
navigation project unit, regarding access channels in 
vicinity of Antioch, until local interests furnish formal 
assurances and definite plans for Port of Antioch. 
Formal assurances for deepening and otherwise im- 
35-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
proving the Stockton Deep Water Ship Channel from 
Pittsburg to Stockton were furnished by Stockton Port 
District April 9, 1970. The Stockton Port District, in 
August 1980, formally provided their intent to sponsor 
the Avon to Pittsburg reach (Suisun Bay Channel) and 
recreation development on Roberts Island. The Port of 
Stockton, by letter ofOctober 20, 1981, stated that they 
would furnish the necessary assurances for fish and 
wildlife mitigation and enhancement, and on April 13, 
1982, provided formal updated assurances for the Avon 
to Stockton portion. A sec. 221 agreement satisfying all 
requirements of local cooperation for Southampton 
Shoal and Richmond Long Wharf maneuvering area 
was obtained from Contra Costa County Board of 
Supervisors and signed by District Engineer July 31, 
1984. 
Terminal facilities. See Port Series No. 30, revised 
1983, and 31, revised 1982, titled respectively: "The 
Ports of San Francisco, Redwood City, and Humboldt 
Bay, Calif." and "The Ports of Oakland, Alameda, 
Richmond, and Ports on Carquinez Strait, Calif."; and 
Port Series No. 32, revised 1986, "The Ports of Sacramento, 
Stockton, Pittsburg and Antioch, Calif." Facilities 
are considered adequate for existing commerce and 
will be adequate for future commerce upon completion 
of new terminal facilities. 
Operations and results during fiscal year. New 
work: Sacramento District: Engineering continued. 
Channel improvement--dredging of various reaches 
between McDonald Tract and Avon was initiated by 
Contract No. 4 at fiscal year contract cost of $5,413,916. 
Dredging Jersey Island to New York Slough was 
completed at fiscal year contract cost of $122,200. San 
Francisco District: Continued planning activities. 
Channel improvement: A dredging contract for Richmond 
Long Wharf Maneuvering Area, Contra Costa 
County, (awarded in August 1985) was initiated and 
completed at fiscal year cost of $4,351,230. A second 
dredging contract for Richmond Long Wharf Maneuvering 
Area was awarded September 17, 1986. No 
fiscal year costs. 
Historical summary. Construction of project was 
initiated in June 1971 and is about 32 percent complete. 
4. SAN JOAQUIN RIVER, CA 
Location. Rises in east central California and flows 
westerly and northwesterly about 340 miles to its 
confluence with Sacramento River at head of Suisun 
Bay, 48 miles northeast of San Francisco. Deep water 
channel in San Joaquin River extends 41 miles from its 
mouth in Suisun Bay at Pittsburg to city of Stockton. 
Waterborne accessto city provided by Stockton Channel, 
an artificial cut extending from river about 2 miles into 
city. (See Coast and Geodetic Survey Sheet 5527.) 
Existing project. For description of completed 
improvement, modifications, and authorizing acts, see 
Annual Report for 1967. (See table 35-I for total cost of 
new work for project completed in May 1960.) 
Projects units (1950 modification) reclassified and 
excluded from project cost are set forth in table 35-J. 
Modification of existing project is included as one 
unit of San Francisco Bay to Stockton, CA, (Johi F. 
Baldwin and Stockton Ship Channels) project, authorized 
by 1965 River and Harbor Act (H. Doc. 209, 89th 
Cong., 1st sess.); this modification is reported in detail 
under Sacramento District, Improvement No. 3. 
Local cooperation. Fully complied with for completed 
portion of project; for details of required cash contributions 
on completed, inactive and deferred portions of 
project, see Existing project paragraph, Annual Report 
for 1967. 
Terminal facilities. For description of harbor facilities 
at Port of Stockton, CA, see Port Series 32, "The 
Ports of Sacramento, Stockton, Pittsburg and Antioch, 
Calif.," revised 1986. Downstream from Stockton, traffic 
is accommodated by bank landings and sheds except at 
Antioch and near Pittsburg, where there are wharves 
for shallow- and deep-draft vessels. Terminal transfer 
facilities at public ocean terminal of Port of Stockton 
are adequate for present and immediate future. 
Operations and results during fiscal year. Maintenance: 
Condition studies and miscellaneous inspections 
and reports were accomplished by hired labor. Stone 
protection maintenance on Stockton Deep Water Ship 
Channel was completed at fiscal year contract cost of 
$60,000. (Repair or restoration of wavewash protection 
is required by legislation authorized by Improvement 
No. 3.) 
Historical summary. Active portion of existing project 
was completed in May 1960. Construction of project 
was initiated in December 1877. 
Flood Control 
5. BUCHANAN DAM-H. V. EASTMAN 
LAKE; CHOWCHILLA RIVER, CA 
Location. On Chowchilla River about 36 miles above 
its mouth and about 16 miles northeast of city of 
Chowchilla, CA. (See Geological Survey quadrangles 
for area.) 
Existing project. Provides for construction of a 205- 
foot high rockfill dam to create a reservoir with gross 
storage capacity of 150,000 acre-feet for flood control, 
irrigation, recreation, and fish and wildlife. In conjunction 
with dam, project plan provides for about 12 miles 
of downstream levee and channel construction on Ash 
Slough to accommodate a project design flow of 5,000 
cubic feet per second within slough and 7 miles of levee 
and channel improvement on Berenda Slough. Operation 
and maintenance of dam and reservoir is the responsibility 
of the Federal Government. Total first cost for 
existing project is $28,919,597, of which $27,369,597 is 
Federal cost, including $4,580,000 for basic recreation 
facilities, and $1,550,000 non-Federal costs for lands 
and damages, including relocations for downstream 
levee and channel improvements. Local interests have 
contracted with the Bureau of Reclamation for irriga- 
35-4

SACRAMENTO, CA, DISTRICT 
tion service. For future non-Federal reimbursement, 
see Local cooperation paragraph. 
Local interests have also, over a period of years, 
expended about $500,000 for construction of low levees 
and clearing downstream channels to provide some 
local flood protection in project area. This work is 
inadequate during major floods. Existing project was 
adopted by 1962 Flood Control Act (S. Doc. 98, 87th 
Cong., 2d sess., contains latest published map). Lake 
formed by Buchanan Dam on Chowchilla River was 
designated "H. V. Eastman Lake" by Public Law 
93-217. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work: None. Maintenance: Maintenance and operation 
activities were continued. Runoff of Chowchilla River 
above Buchanan Dam was above normal for the year. 
Maximum storage of 131,200 acre-feet occurred May 17, 
1986. Maximum inflow to reservoir was 15,000 cubic 
feet per second on February 18,1986. Maximum release 
of 450 cubic feet per second on April 4, 1986, was below 
maximum permissible flood release. During the year, a 
total of 30,400 acre-feet of water was released for 
irrigation and other purposes. Project prevented an 
estimated $6,000,000 in damages from the February- 
March 1986 rainfloods. 
Historical summary. Construction began in July 
1971 and was completed in May 1979. Construction of 
Buchanan and Hidden dam and appurtenances were 
combined under one contract. Project was completed in 
September 1983, except for installation of piezometers 
(now deferred indefinitely). Dam closure was in March 
1975; dam was completed in January 1976. Reservoir 
clearing and boundary marking were completed May 
1975. Bifurcation structure was completed in February 
1976. Channel improvement, Ash and Berenda Sloughs, 
was completed in March 1976. Recreation areas: Phase 
I was completed in January 1976; Phase II was completed 
in February 1978. Residences, administration 
building, and visitors center contract was completed in 
May 1978. Landscaping was completed in May 1979 
and erosion control was completed in April 1979. A 
resources interpretive display and road relocation were 
completed in FY 1982. Dam safety assurance studies 
were initiated in FY 1981. Solar heating was installed 
at Chowchilla recreation area in FY 1984. Final land 
audit was approved on December 3, 1985. 
6. CALAVERAS RIVER AND 
LITTLEJOHN CREEK AND 
TRIBUTARIES, INCLUDING 
NEW HOGAN LAKE AND 
FARMINGTON DAM, CA 
Location. Streams comprising Calaveras River and 
Littlejohn Creek groups rise in Sierra Nevada and its 
foothillsg, flow easterly across flatlands of San Joaquin 
Valley and empty into San Joaquin River directly, or 
through various sloughs, in vicinity of Stockton, CA. 
Littlejohn Creek is in Calaveras, Stanislaus, and San 
Joaquin Counties. The three principal stream systems 
of the group are, from south to north, Lone Tree Creek, 
Littlejohn Creek, and Duck Creek. Calaveras River 
group is in Calaveras and San Joaquin Counties. The 
two principal streams of the groups are, from south to 
north, Calaveras River and Bear Creek. (See Geological 
Survey Valley Springs quadrangle for New Hogan 
reservoir area and Trigo and Bachelor Valley quadrangles 
for Farmington reservoir area.) 
Existing project. For description of completed 
improvements consisting of Farmington Dam, New 
Hogan Lake, and Bear Creek levee and channel improvement, 
and authorizing act, see Annual Report for 1967. 
(a) Farmington: Total first cost (July 1955) for project 
was $3,995,684, of which $3,676,384 was Federal and 
$319,300 non-Federal for lands and damages including 
relocations. (b) New Hogan: Federal cost for project is 
$15,906,150, including $543,514 for basic recreation 
facilities. For future non-Federal reimbursement, see 
Local cooperation paragraph. Federal cost for recreation 
facilities funded from Code 710 appropriations is 
$897,742. (c) Bear Creek: Project cost is $6,485,734, of 
which $3,242,867 is Federal, including reimbursement 
($488,096) to local interests of one-half of excess local 
interest cost of lands, rights-of-way, and relocations 
over estimated Federal construction cost in accordance 
with section 3, Public Law 738, 74th Congress. Non- 
Federal cost included in above amount is $3,242,867 for 
relocations and lands and damages, exclusive of above 
Federal reimbursement. 
Local cooperation. Fully complied with. New Hogan: 
Local interests must pay portion of first cost and annual 
operation and maintenance costs allocated to conservation 
functions of project. These costs are estimated at 
36.2 percent of first cost and 38 percent of annual costs. 
In addition, local interests contributed land, the (July 
1964) market value of which was $556,000. For years 
1961 through 1970, an interim contract between the 
Bureau of Reclamation and local water users provided 
for storage and payment of irrigation water; local 
interests paid $2,737,252 through December 31, 1985. 
A long-term contract between that agency and local 
water users was executed August 25, 1970. A concessionaire 
at New Hogan Marina provided public use 
facilities in accordance with lease agreement with the 
Secretary of the Army at an estimated cost to date of 
$234,000. 
Operations and results during fiscal year. New 
work: New Hogan Lake, regular funds: None. Code 710 
funds: None. Bear Creek, San Joaquin County: None. 
Maintenance: Farmington Dam-Maintenance and 
operation activities continued; structures were maintained 
in serviceable condition. During the rainflood 
season, maximum flow of Littlejohn Creek at Farmington 
was 3,000 cubic feet per second February 19, 
1986. This flow was all local, gates were closed at 
Farmington Dam. Maximum storage in reservoir was 
48,200 acre-feet on February 19, 1986, and maximum 
35-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
inflow to reservoir was 24,000 cubic feet per second on 
February 19, 1986. Project prevented an estimated 
$15,000,000 in damages from the February-March 
1986 rainfloods. New Hogan Lake-Maintenance and 
operation activities continued. Construction of a boathouse 
was completed at fiscal year contract cost of 
$42,679. Structures were maintained in serviceable 
condition. Runoff of Calaveras River above New Hogan 
was above normal for the year. Maximum storage of 
254,200 acre-feet occurred February 20, 1986. Maximum 
inflow to reservoir was 35,000 cubic feet per 
second on February 19, 1986. Maximum release of 
7,130 cubic feet per second on February 22, 1986, was 
below maximum permissible flood release. During the 
year, 178,800 acre-feet was released for flood control 
and 85,800 acre-feet was released for irrigation and 
other purposes. Project prevented an estimated 
$14,000,000 in damages from the February-March 
1986 rainfloods. 
Historical summary. Farmington Dam: Construction 
of Farmington project was initiated in July 1949 and 
completed for beneficial flood control operation in 1952. 
Duck Creek channel improvement was completed in 
November 1951; and channel improvement on south 
Littlejohn Creek was completed in May 1955. There are 
no recreation facilities or public-use areas. All work 
completed. Dam safety assurance studies were initiated 
in FY 1982. New Hogan Lake: Construction was initiated 
May 1960, main dam closure November 1963, project 
completed for operational use in June 1964, and all 
work completed October 1973. Recreation facilities 
have been provided from Code 710 appropriations. 
Seepage measurement weir constructed in June 1980. 
Dam safety assurance studies were initiated in FY 
1980. Bear Creek, San Joaquin County: Construction 
began in June 1963 and was completed in June 1967. 
Final cash contribution was made to local interests 
December 23, 1970. Solar heating was installed at 
recreation facilities in FY 1984. A cultural resources 
survey was completed in FY 1984. 
7. CORTE MADERA CREEK, CA 
Location. Creek and tributaries drain an area of 28 
square miles in Marin County, CA, and discharge into 
west side of San Francisco Bay at a point about 9 miles 
north of Golden Gate. (See Geological Survey quadrangle 
San Rafael.) 
Existing project. Provides for about 11 miles of 
channel improvements, including realignment, enlargement, 
levees, riprapping, rectangular concrete sections, 
interior drainage facilities, bridge relocations, and 
debris removal on Corte Madera Creek and lower 
reaches of its tributaries, and a continuous channel 
rights-of-way to deep water in San Francisco Bay 
reserved to assure channel outlet in the event of future 
tideland reclamation. Approved estimated cost for new 
work (October 1986) is $21,400,000, of which $12,700,000 
is Federal cost and $8,700,000 is non-Federal cost 
(includes $650,000 to be contributed by local interests.) 
(See table 34-B for authorizing legislation.) 
Local cooperation. Local interests must provide 
lands and rights-of-way, including suitable areas for 
disposal of waste material, modify or relocate all bridges 
and utilities necessary for construction and maintenance; 
hold and save the United States free from damages due 
to the construction works; maintain and operate the 
project after completion in accordance with the regulations 
prescribed by the Secretary of the Army, and 
prevent encroachment on flood channels that would 
result in decreasing the effectiveness of project for flood 
control; adjust all claims regarding water rights that 
might be affected by the project; and contribute in cash 
1.5 percent of Federal construction cost of Ross Valley 
unit and tidal areas, an estimated $650,000. Marin 
County Flood Control and Water Conservation District 
previously furnished resolution of local assurances 
dated March 29, 1966, March 28, 1967, August 15, 1967, 
and July 8,1969, and Marin County Board of Supervisors 
reaffirmed by letter dated September 28, 1978. Project 
was authorized by the State of California by 1965 
Statute, Chapter 1388. Board of Supervisors of Marin 
County Flood Control and Water Conservation District 
furnished assurances of willingness and ability to meet 
requirements for portion of project below Sir Francis 
Drake Boulevard. Acquisition of rights-of-way and 
dredge material disposal areas, relocations and construction 
for remaining work is being held in abeyance 
as a result of a request from Congress for a review of 
alternatives other than completing the project as an 
open concrete channel. 
On December 13, 1983, Marin County Board of 
Supervisors reconfirmed assurances of local cooperation 
because a Superior Court Judgment ordered that county 
to take all steps required by law to complete channel 
downstream of Sir Francis Drake Boulevard (Unit 4) 
and maintain entire project as agreed. A Local Cooperation 
Agreement for redredging the lower reach of Corte 
Madera Creek was executed on June 29, 1985. Marin 
County also provided support for Ross Valley Unit 4 on 
August 21, 1986. 
Operations and results during fiscal year. New 
work: Redredging Lower Corte Madera Creek channel 
was initiated at fiscal year contract cost of $1,321,429. 
Historical summary. Project responsibility was 
transferred from San Francisco District on April 1, 
1982. Project is about 75 percent complete cotsidering 
the portion being held in abeyance upstream of Sir 
Frances Drake Boulevard. Work remaining: Design 
and construction of the remaining 3,000 feet of channel 
downstream of Sir Francis Drake Boulevard and Ross 
Creek. In lieu of the authorized concrete channel, an 
alternative plan consisting of wing walls and individual 
house floodproofing is being recommended in the Significant 
Post-Authorization Change Report. The portion 
of Corte Madera Creek upstream of intersection of Sir 
Francis Drake Boulevard and Corte Madera Creek in 
Ross, near the city of San Anselmo, was classified as 
"inactive" on July 11, 1984, due to lack of local support. 
A Local Cooperation Agreement for redredging lower 
35-6

SACRAMENTO, CA, DISTRICT 
reach of Corte Madera Creek was executed June 29, 
1985. 
8. FAIRFIELD VICINITY 
STREAMS, CA 
Location. On five streams in vicinity of cities of 
Fairfield and Suisun, Solano County, CA. 
Existing project. Provides for channel improvement 
on Ledgewood, Laurel, and McCoy Creeks and diversion 
of three creeks upstream from Fairfield (Pennsylvania 
Avenue Creek into Ledgewood Creek, Union Avenue 
Creek into Laurel Creek, and Laurel Creek into McCoy 
Creek). Project related recreation facilities such as 
access roads, parking areas, a boat-launching ramp and 
hiking, bicycle, and horseback trails would also be 
construction. Estimated cost (October 1986) for existing 
project is $21,000,000 (includes an allowance for 
estimated inflation through the construction period), of 
which $10,500,000 is Federal and $10,500,000 is non- 
Federal. For future non-Federal reimbursement, see 
Local cooperation paragraph. Existing project was 
adopted by sec. 201, 1965 Flood Control Act (1970 
Senate and House Public Works Committee resolutions) 
and Further Continuing Appropriations Act for FY 
1986 (Public Law 99-190), December 19, 1985. (HD 91- 
159, 91st Cong., 1st sess., contains published map). 
Local cooperation. Local interests are required to 
provide lands, easements, rights-of-way, and dredged 
material disposal areas, modify or relocate buildings, 
utilities, roads, and other facilities, except railroad 
bridges, where necessary in the construction of the 
project, pay one-half of the separable costs allocated to 
recreation, presently estimated at $320,000, of which 
$120,000 is for lands and $200,000 is cash contribution; 
and bear all costs of operation, maintenance, and. 
replacement of recreation facilities and flood control 
facilities. Ultimate non-Federal cost for flood control 
will be reduced by a Federal reimbursement of one-half 
of the non-Federal costs in excess of the Federal 
construction costs. Local interests have agreed to make 
all required payments concurrently with project 
construction. 
Project had been in "deferred" status since September 
15, 1977, due to lack of local assurances. In April 1982, 
the cities of Fairfield and Suisun affirmed their support 
and intent to provide necessary assurances of local 
cooperation for a modified version of the authorized 
project from 200-year to 100-year flood protection. On 
June 23, 1982, project was reclassified from "deferred" 
to "active" status. The State of California Reclamation 
Board has provided a letter of intent to the Assistant 
Secretary of the Army, November 8, 1982, to cooperate 
with the Federal Government to begin construction of 
the project. In accordance with FY 1985 Supplemental 
Appropriations Act (Public Law 99-88) and sec. 117 of 
the Further Continuing Appropriations Act for FY 
1986 (Public Law 99-190), a Local Cooperation Agreement 
for flood control and recreation (sec. 221) was 
executed June 3, 1986. 
Sec. 117 of Further Continuing Appropriations Act 
for FY 1986 contained the following authorization 
language which will be reflected in any future modified 
agreements: "The Secretary shall include as part of the 
non-Federal contribution of the project for flood control, 
Fairfield Vicinity Streams, California, authorized in 
accordance with sec. 201 of Flood Control Act of 1965, 
the cost of any work carried out by non-Federal interests 
on the project after December 31, 1973, and before the 
date of the enactment of this joint resolution if the 
Secretary determines such work is reasonably compatible 
with the project. Costs and benefits resulting 
from such work shall continue to be included for 
purposes of determining economic feasibility of the 
project." Prior local expenditures of $6,800,000 have 
been reported by the sponsor. The Corps is evaluating 
costs and benefits of all completed works by non- 
Federal interests after December 31, 1973. 
Operations and results during fiscal year. Local 
Cooperation Agreement was executed on June 3, 1986. 
Construction contract for McCoy Creek and Laurel 
Creek Diversion Channel, Phase I, was awarded in 
September 1986. 
Historical summary. Construction contract for 
enlarging McCoy Creek and constructing Laurel Creek 
Diversion Channel, Phase I, was awarded on September 
30, 1986. 
9. HIDDEN DAM-HENSLEY LAKE, 
FRESNO RIVER, CA 
Location. On Fresno River about 50 miles above its 
mouth and about 15 miles northeast of Madera, CA (See 
Geological Survey quadrangles for area.) 
Existing project. Provides for construction of a 163- 
foot high earthfill dam to create a reservoir with gross 
storage capacity of 90,000 acre-feet for flood control, 
irrigation, recreation and other purposes. In conjunction 
with the dam, the project provides for about 13 miles of 
downstream levee and channel improvements on Fresno 
River immediately upstream of Chowchilla Canal crossing 
to accommodate project design flow of 5,000 cubic 
feet per second. Operation and maintenance of dam and 
reservoir is the responsibility of the Federal Government. 
Total first cost for existing project is $31,785,426, 
of which $30,555,426 is Federal cost, including 
$3,564,168 for basic recreation facilities, and estimated 
$1,230,000 non-Federal cost for lands and damages 
including relocations for downstream levee and channel 
improvements. Local interests have contracted with the 
Bureau of Reclamation for irrigation service. For 
future non-Federal reimbursement, see Local cooperation 
paragraph. Local interests have also, over a period 
of years, expended about $300,000 for construction of 
low levees and clearing downstream channels to provide 
some local flood protection in the project area. This 
work is inadequate during major floods. Existing project 
was adopted by 1962 Flood Control Act (S. Doc. 37, 87th 
Cong., 1st sess., contains latest published map). Lake 
35-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
created by Hidden Reservoir project on Fresno River 
was designated "Hensley Lake" by Public Law 93-603. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work. None. Maintenance: Maintenance and operation 
activities were continued. Erosion repair on downstream 
face of the dam was completed. Runoff of Fresno River 
above Hidden Dam was above normal for the year. 
Maximum storage of 67,100 acre-feet occurred May 18, 
1986. Maximum inflow to reservoir was 9,800 cubic feet 
per second on February 18, 1986. Maximum release of 
3,230 cubic feet per second on February 17, 1986, was 
below maximum permissible flood release. During the 
year, 77,100 acre-feet was released for flood control and 
57,300 acre-feet of water was released for irrigation and 
other purposes. Project prevented an estimated 
$41,800,000 in damages from the February-March 
1986 rainfloods. 
Historical summary. Construction began in July 
1971 and was completed in January 1979. Dam closure 
was in March 1975; dam was completed November 
1975. Instrumentation was completed in January 1976. 
Downstream channel improvement, Fresno River, was 
completed April 1976. Recreation areas: Phase I was 
completed in March 1976; Phase II was completed in 
June 1978. Residences, administration building, grounds, 
and utilities contract was completed in February 1978. 
Landscaping was completed in December 1978 and 
erosion control was completed in January 1979. Project 
was completed in September 1980. Final land audit was 
approved February 5, 1980. Dam safety assurance 
studies were initiated in FY 1980. Piezometer installation 
was completed in September 1982. Solar heating 
was installed at recreation areas in FY 1984. 
10. ISABELLA LAKE, KERN RIVER, 
CA 
Location. About 35 miles northeast of city of Bakersfield, 
CA, near confluence of north and south forks of 
Kern River; auxiliary dam is about one-half mile east of 
main dam. (See Geological Survey quadrangles of 
area.) 
Existing project. For description of completed 
improvement and authorizing act, see Annual Report 
for 1967. Federal cost for new work is $22,027,452. For 
future non-Federal reimbursement see Local cooperation 
and Licenses paragraphs. Federal cost funded 
from Code 710 appropriations is $2,199,085. Operation 
and maintenance of dam and reservoir is Federal 
responsibility. 
Local cooperation. Californiaofficially adopted project 
by chapter 1514 of statutes of 1945, State of California. 
Local interests, represented by North Kern, Buena 
Vista, and Tulare Lake Basin Water Storage Districts 
and La Hacienda Water District, were required to 
reimburse the Federal Government the portion of first 
cost and annual operation and maintenance costs allocated 
to irrigation functions of project. These costs, 
-based on a cost allocation study completed in December 
1955, are $4,573,000 of first cost and 21.7 percent of 
annual operation and maintenance cost. For the years 
1956 through 1964, an interim contract between the 
Bureau of Reclamation and local water users provided 
for storage and payment of irrigation water. Under 
provisions of this interim contract, local interests paid 
$1,936,229 through December 31, 1964. A long-term 
contract between the Bureau and local water users was 
executed October 23, 1964. Balance due on allocated 
first cost of $4,573,000 was paid by the water users on 
March 31, 1965. Kern County assumed administration 
of recreation and development and maintenance of 
public use areas at project in accordance with a 25-year 
license February 15, 1955. The agreement with Kern 
County provided for joint operation and development by 
the Corps and Kern County including permits granted 
to concessionaires by the county to provide certain 
services. As of September 30, 1971, Kern County relinquished 
all administration of recreation and development 
and maintenance of public use areas at the 
project. A State law permitting the Department of 
Boating and Waterways (known as the Department of 
Navigation and Ocean Development prior to January 
1979) to participate in inland water development with 
Federal agencies was signed by the Governor on 
August 11, 1972. All concessionaires will operate under 
permits granted by the Corps. Total cost to date of 
present recreation facilities developed by the county 
and the marina concessionaires is about $965,000; 
$235,000 of this was a grant from the California 
Wildlife Conservation Board and about $534,000 is 
investment by marina concessionaires. 
Licenses. In accordance with Federal Power Commission 
Docket No. E-6578, issued April 1, 1963, payment 
of $377,426 was made to the Federal Government by 
Pacific Gas and Electric Co.'($108,352) and Southern 
California Edison Co. ($269,074) for headwater benefits 
to downstream existing plants from Isabella Dam to 
cover benefits from April 15, 1954, to December 31, 
1962. Between 1962 and 1982 the power companies have 
in the aggregate made annual payments of $44,650 for 
headwater benefits. That amount was to be paid each 
year until changes in operation, development, or costs 
indicated some modification to be advisable. Federal 
Power Commission Docket No. E-6578 was revised by 
Docket No. HB07-75-4-000 (order issued July 11, 1983 
under 24 FERC, paragraph 62052) which modified 
cumulative use charges after 1974, effective retroactively. 
Such charges will now vary each year. An 
adjustment (years 1974 through 1984) was included in 
1984 payment of $244,790. The 1985 payment was 
$52,747; 1986 payment was $51,905. Cumulative use 
charges collected by the Federal Power Commission 
(known as the Federal Energy Regulatory Commission 
since January 9, 1978) and returned to the U. S. 
Treasury through period ending September 30, 1986, 
amounted to $1,709,168. 
35-8

SACRAMENTO, CA, DISTRICT 
Operations and results during fiscal year. New 
work, regular funds: None. Code 710 funds: None. 
Maintenance: Maintenance and operation continued. 
Fiscal year contract costs for major items of work 
included: Initiation of Eastside recreation area renovation, 
$299,000; completion of Paradise Cove recreation 
area renovation; and completion of road paving 
at miscellaneous recreation areas, Phase II, $85,157. 
Dam safety assurance studies at Isabella Dam were 
continued at a fiscal year cost of $51,898. Structures 
were maintained in good condition. Runoff of Kern 
River above Isabella Lake was above normal for the 
year. Maximum storage of 562,100 acre-feet occurred 
June 16, 1986. Maximum daily inflow to the reservoir 
was 14,000 cubic feet per second on February 19,1986, 
and maximum outflow of 4,550 cubic feet per second 
occurred June 3, 1986. During the year, 215,900 acrefeet 
was released for flood control and 970,700 acre-feet 
was released for irrigation. Project prevented an estimated 
$6,000,000 in damages from the February- 
March 1986 rainfloods and May-July 1986 snowmelt. 
Historical summary. Construction began in March 
1948 and was completed in June 1968. Main dam, Borel 
Canal outlet works and appurtenances, and auxiliary 
dam were completed in April 1953. Storage impoundment 
began December 1952. Piezometer was installed 
in August 1982. Project is operating to provide flood 
protection and irrigation benefits for which it was 
designed. Recreation facilities were provided by Code 
710 funds. Dam safety assurance studies were initiated 
in FY 1979. A cultural resources survey was completed 
in FY 1984. 
11. KAWEAH AND TULE RIVERS, 
INCLUDING TERMINUS DAM 
AND SUCCESS LAKE, CA 
Location. Terminus Dam is on Kaweah River about 
20 miles east of Visalia, CA. Success Lake is on Tule 
River about 5 miles east of Porterville, CA. (See Geological 
Survey quadrangles of area.) 
Existing project. Terminus Dam: For description of 
completed improvement and authorizing act, see Annual 
Report for 1975. Federal cost of new work is $19,302,957, 
including $242,605 for basic recreation facilities and 
excluding spreading works constructed by local interests 
at an estimated (July 1957) cost of about $750,000. 
Spreading works portion of project has been deauthorized. 
The 90-day Congressional project review period, 
required by sec. 12, Public Law 93-251, as amended, 
ended August 5, 1977, and resulted in deauthorization 
of that portion of project. Federal cost of recreation 
facilities funded from Code 710 appropriations is 
$700,004. Success Lake: For description of completion 
improvement and authorizing act, see Annual Report 
for 197&. Federal cost of new work for Success Lake is 
$14,247,221, including $253,697 for basic recreation 
facilities. Federal cost of recreation facilities funded 
from Code 710 appropriations is $747,048. For future 
non-Federal reimbursements, see Local cooperation 
paragraph. Operation and maintenance of reservoirs is 
Federal responsibility. 
Local cooperation. California officially adopted projects 
by chapter 1514 of statutes of 1945, State of 
California. Local interests for Terminus Dam are represented 
by Kaweah Delta Water Conservation District. 
Local interests for Success Lake are considered to be 
represented by the Vandalia, Porterville, and Lower 
Tule River Irrigation Districts, the Tulare Lake Basin 
Water Storage District, and Pioneer Water Co., which 
represent over 90 percent of irrigated land and waterright 
holders along Tule River below damsite. Local 
interests must reimburse the Federal Government the 
portion of first cost and annual operation and maintenance 
costs allocated to irrigation functions of projects. 
These costs are estimated at 14.1 percent of first and 
annual costs for Terminus and 9.5 percent of first and 
annual costs for Success. Local interests for Terminus 
stated they will continue to operate and maintain 
spreading works and downstream channel systems to 
provide required capacity for disposal of floodwaters. 
Local interests for Success stated they will continue to 
maintain downstream channel systems to provide 
required capacity for disposal of floodwaters. Repayment 
contracts between the Bureau of Reclamation and 
local water users for irrigation supply from Terminus 
and Success reservoirs were executed January 11, 1965, 
and April 30, 1965, respectively. Reservoirs are being 
operated for irrigation storage as well as flood control 
and incidental recreation use. Tulare County acquired 
water for recreation pools at the projects. Local interests 
paid the following total amounts for irrigation services 
from the reservoirs through December 31, 1985: 
Terminus, $1,611,455 and Success, $749,402. Tulare 
County was granted a 25-year license for planning, 
development, and management of public recreation 
areas at Success, July 10,1960, and at Terminus, June 5, 
1961. Basic public-use facilities constructed by Corps at 
the Success reservoir were transferred to jurisdiction of 
Tulare County on January 18, 1962; facilities at 
Terminus were transferred June 20, 1962. In March 
1967, an amendment to the license agreements was 
approved by the Assistant Secretary of the Army. 
Under these amended licenses, Tulare County retained 
administration of only specified land areas and operation 
and maintenance of recreation facilities in these 
areas. In addition, they continued their program of 
water safety, boat inspection, and law enforcement at 
both reservoirs. The Corps took over the administration 
of the remainder of the project land areas and the 
operation and maintenance of recreation facilities in 
these areas. Calif. Department of Fish and Game 
expended funds to improve fishery resources of the 
Terminus reservoir. As of April 1, 1972, Tulare County 
relinquished all planning, development, and management 
of public recreation areas at Terminus Dam. 
Tulare County by expenditure of county funds and by a 
lease to a marina concessionaire has aided in the 
development of recreation facilities at an estimated cost 
of $199,000. Calif. Department of Fish and Game 
35-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
expended funds in conjunction with Tulare Sportsman's 
Council, developing a habitat for upland game birds at 
Success Lake. As of April 1, 1972, Tulare County 
relinquished all planning, development, and management 
of public recreation areas at Success Lake, except 
for the Bartlett Park recreation area. Tulare County 
has aided in development of recreation facilities. Total 
cost to date of present recreation facilities developed by 
the county ($360,000) and the marina concessionaires 
($373,000) is about $733,000. 
Operations and results during fiscal year. New 
work: Terminus Dam, regular funds: None. Code 710 
funds: None. 
Success Lake, regular funds, None. Code 710 funds: 
None. 
Maintenance: Terminus Dam: Maintenance and operation 
continued. Dam safety assurance studies were 
continued at a fiscal year cost of $141,516. Structures 
were maintained in serviceable condition. Runoff of 
Kaweah River above Terminus Dam was above normal 
for the year. Maximum storage of 142,700 acre-feet 
occurred on June 18, 1986. Maximum inflow to the 
reservoir on February 13,1986, was about 20,000 cubic 
feet per second. Maximum outflow of 3,290 cubic feet 
per second occurred March 14, 1986. Water released 
for flood control amounted to 273,900 acre-feet and 
irrigation and spreading releases totaled 534,000 acrefeet. 
Project prevented an estimated $8,000,000 in 
damages from the February-March 1986 rainfloods 
and May-July 1986 snowmelt runoff. Success Lake: 
Maintenance and operation continued. Dam safety 
assurance studies were continued at a fiscal year cost of 
$143,604. Structures were maintained in serviceable 
condition. Runoff of Tule River above the reservoir was 
above normal during the year. Maximum inflow to the 
reservoir was 7,000 cubic feet per second on February 
19, 1986, and maximum outflow of 1,760 cubic 
feet per second occurred on March 14, 1986, Maximum 
storage of 82,300 acre-feet occurred on July 9, 1986. 
Water released for flood control amounted to 110,700 
acre-feet and irrigation and spreading releases 
amounted to 121,300 acre-feet. Project prevented an 
estimated $2,000,000 in damages from the February- 
March 1986 rainfloods and May-July 1986 snowmelt 
runoff. 
Historical summary. Terminus Dam: Construction 
of project began in July 1957 and was completed in June 
1968 except for final settlement for one tract of land 
upon decision of pending court case. Construction of 
main dam and appurtenances, initiated in February 
1959, was completed in June 1962. Dam has been 
operating since November 1961 to provide flood protection 
for which it was designed; conservation impoundment 
was commenced May 1962. Appurtenances are in 
good condition. Recreation facilities were provided by 
Code 710 funds. Dam safety assurance studies were 
initiated in FY 1979. Piezometer installation and a 
cultural resources survey were completed in FY 1984. 
Success Lake: Construction of project began in November 
1956, was completed in June 1968, and final audit of 
historical land record was approved December 17, 
1979. Construction of main dam and appurtenances, 
initiated in October 1958, was completed in May 1961. 
Dam has been operating since October 1960 to provide 
flood protection for which it was designed; conservation 
impoundment was commenced March 1962. Recreation 
facilities were provided by Code 710 funds. Dam safety 
assurance studies were initiated in FY 1979. A cultural 
resources survey was completed in FY 1984. 
12. LITTLE DELL LAKE, UT 
Location. On Dell Creek, a tributary of Parleys 
Creek, about 8 miles east of Salt Lake City upstream of 
Mountain Dell Reservoir in Salt Lake County, UT. 
Existing project. Project providing for construction 
of a dam about 253 feet high to create a reservoir with a 
gross capacity of 30,000 acre-feet for flood control, 
municipal and industrial water supply, recreation and 
fish and wildlife was authorized by the 1968 Flood 
Control Act (S. Doc. 53, 90th Cong., 1st sess., contains 
published map) as modified by sec. 170, Water Resources 
Development Act of 1976, Public Law 94-587, October 
22,1976. Facility would be operated in conjunction with 
existing downstream 3,200 acre-foot Mountain Dell 
Reservoir on Parleys Creek for flood control and water 
supply. 
Authorized project has been reexamined and scaled 
down to reflect local interests' ability to pay. Current 
plan of improvement includes only flood control and 
water supply purposes. Recreation was deferred as of 
May 30, 1986, and Emigration Creek Diversion was 
deleted and placed in an inactive status. Project will 
include an earthfill dam 224 feet high, a 20,500 acrefoot 
reservoir, and 10,035 feet of pipeline to divert water 
from Parleys Creek. Estimated project cost (October 
1986) is $49,200,000 (includes an allowance for estimated 
inflation through the construction period) of which 
$28,300,000 is Federal and $20,900,000 is non-Federal 
for lands and damages and includes a cash contribution 
of $15,220,000. Project is included in FY 1985 
Supplemental Appropriations Act (Public Law 99-88), 
August 15, 1985. 
Local cooperation. Local interests are required to 
provide lands, easements, rights-of-way, and dredged 
material disposal areas; modify or relocate buildings, 
utilities, roads, and other facilities where necessary in 
the construction of the project; pay all costs allocated to 
municipal and industrial water supply; bear all costs of 
operation, maintenance, and replacement of flood control 
facilities; and pay a cash contribution presently estimated 
at $15,220,000. By letters of January 22, 1986, 
and January 24, 1986, the Metropolitan Water District 
of Salt Lake City and Salt Lake County indicated their 
support and willingness to proceed with a reduced scale 
project based on their "ability to pay." A Local Cooperation 
Agreement (sec. 221) was executed on June 10, 
1896. Water Revenue Bonds were issued August 27, 
1986, and proceeds from the sale in the amount of 
35-10

SACRAMENTO, CA, DISTRICT 
$14,300,000 have been deposited in the Little Dell 
Construction Fund Account. 
Operations and results during fiscal year. Engineering 
activities included initiation of studies for 
Outlet Works Design Memorandum, initiation of studies 
for Embankment and Spillway Design Memorandum, 
and initiation and essential completion of embankment 
and foundation exploration program. Plans and specifications 
for redesign of Highway 65 realignment and 
relocation were completed by the Utah Department of 
Transportation. A Local Cooperation Agreement was 
executed in June 1986 making this project eligible for a 
new construction start. 
Historical summary. A Local Cooperation Agreement 
(sec. 221) was executed June 10, 1986. 
13. LOWER SAN JOAQUIN RIVER, CA 
Location. On Lower San Joaquin River, CA, from 
city of Stockton, CA, upstream to Friant Dam (about 19 
miles northeast of Fresno). 
Existing project. This project is a modification and 
extension of the previous Lower San Joaquin River and 
Tributaries project (see Annual Report for 1976) to 
provide clearing and snagging on the San Joaquin 
River from Stockton, CA, upstream to Friant Dam. 
Estimated first cost (October 1986) is $6,000,000, of 
which $5,000,000 is Federal and $1,000,000 is non- 
Federal for lands and damages (includes an allowance 
for estimated inflation through the construction period). 
Existing project was included in the 1983 Supplemental 
Appropriations Act, Public Law 98-63, July 29, 1983, 
which states that the project for flood protection on the 
Lower San Joaquin River, CA, authorized by the Flood 
Control Act approved December 22, 1984, as amended, 
is hereby further modified to authorize the Secretary of 
the Army, acting through the Chief of Engineers, to 
perform clearing and snagging on the San Joaquin 
River from Stockton, CA, to Friant Dam, at an estimated 
cost of $5,000,000. 
Local cooperation. Prior to initiation of construction, 
a non-Federal entity shall furnish adequate assurance 
for providing all lands, easements, rights-of-way and 
utility relocations at no expense to the Federal Government, 
execute a written agreement pursuant to sec. 221 
Public Law 96-611; agree to operate and maintain the 
project works upon completion of construction in accordance 
with rules and regulations prescribed by the 
Department of the Army; and hold and save the United 
States free from damages due to construction, operation, 
and maintenance of the project, not including damages 
due to the fault or negligence of the United States or its 
contractors. 
Operations and results during fiscal year. 
Coordination with local interests and pertinent agencies 
and redraft of a combined Design Memorandum and 
Environmental Impact Statement were continued at a 
fiscal year cost of $415,547. 
Historical summary. A Plan of Action, February 
1984, has been prepared. Design Memorandum No. 5 
for Eastside Bypass at San Joaquin River was prepared 
in September 1984. First construction contract, dredging 
Eastside Bypass, was awarded October 12, 1984 and 
completed in May 1985. 
14. MARTIS CREEK LAKE, MARTIS 
CREEK, NV AND CA 
Location. Reservoir is on Martis Creek a tributary of 
Truckee River, near Truckee, CA; intermittent channel 
improvements are on Truckee River in Reno, NV. (See 
Geological Survey quadrangles for areas.) 
Existing project. For description of completed 
improvement and authorizing act, see Annual Report 
for 1975. Federal cost for project was $8,503,789 including 
$289,506 for basic recreation facilities. Federal cost 
of recreation facilities funded from Code 710 appropriations 
was $1,200. Construction of recreation facilities 
under Code 710 was determined to be infeasible. Operation 
and maintenance of reservoir is Federal responsibility. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work: None. Maintenance: Maintenance and operation 
of project, including recreation facilities, was continued. 
Drainage control system modification at Martis Creek 
Dam was completed at fiscal year contract cost of 
$150,042. Structures were maintained in serviceable 
condition. Runoff above Martis Creek Dam was above 
normal for the year. Maximum storage of 6,800 acrefeet 
occurred on June 3, 1986. Maximum inflow to the 
reservoir on February 17, 1986, was about 1,260 cubic 
feet per second and maximum outflow of 664 cubic feet 
per second occurred February 28, 1986. 
Historical summary. Project construction began in 
August 1967; dam closure was in October 1971; dam 
completed in August 1972; basic recreation facilities 
were completed in December 1972; and project was 
completed in June 1974. Recreation facilities under 
Code 710 funding were considered infeasible. Dam 
safety assurance studies were initiated in FY 1981. 
15. MERCED COUNTY STREAMS, CA 
Location. In vicinity of city of Merced, CA, on 
streams draining from Mariposa County foothills of the 
Sierra Nevada into Merced County. Streams lie easterly 
of and drain into the San Joaquin River between 
Chowchilla River on the south and Merced River on the 
north. Drainage area represents about 1,000 square 
miles; nearly 700 square miles of foothills and mountains 
in Mariposa County and about 300 square miles of flood 
plain in Merced County. (See Geological Survey 
quadrangles for area.) 
Existing project. Project is a modification of Merced 
County Stream Group, Calif., Improvement No. 16, 
authorized by 1944 Flood Control Act (H. Doc. 473, 78th 
Cong., 2d sess.) and completed in FY 1957. Existing 
project provides for construction of three new reservoirs 
35-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
- Castle, Haystack Mountain, and Marguerite on 
Canal, Black Rascal, and Deadman-Dutchman Creeks, 
respectively, and enlargement of four existing reservoirs 
- Burns, Bear, Owens, and Mariposa, providing a total 
capacity of 126,700 acre-feet for multipurpose storage; 
and about 52 miles of levee and channel improvements 
in lower reaches of Bear, Black Rascal, Mariposa, and 
Deadman Creeks, thereby tying the existing project 
channels into Eastside Bypass of San Joaquin River 
flood control system. Haystack Mountain, Bear, and 
Owens projects would provide flood control oinly; Castle 
and Burns projects, flood control and recreation; 
Marguerite project, flood control and irrigation; and 
Mariposa project, all three purposes. Existing project 
was adopted by 1970 Flood Control Act (Document not 
yet printed.) 
Current plan of improvement would defer enlargement 
of existing Burns reservoir, Mariposa reservoir, 
construction of Marguerite Dam, and the irrigation 
function associated with the latter two facilities, 
enlargement of existing Owens reservoir and about 32 
miles of levee and channel improvement on Owens, 
Mariposa, and Deadman-Dutchman Creeks. Estimated 
project cost (October 1986) is $92,200,000 (includes an 
allowance for estimated inflation through the construction 
period), of which $62,000,000 is Federal and 
$30,200,000 is non-Federal 
Local cooperation. Local interests are required to 
provide lands, easements, and rights-of-way and 
dredged material disposal areas; modify or relocate 
buildings, utilities, roads, and other facilities, where 
necessary in the construction of the project; pay one-half 
of the separable and joint costs allocated to recreation, 
presently estimated at $215,000, of which $175,000 is a 
cash contribution and $40,000 is for lands; and bear all 
costs of operation, maintenance, and replacement of 
flood control facilities. Total non-Federal share of 
Castle Dam first cost is $2,880,000. 
The California Reclamation Board and the City of 
Merced are the local sponsors of the authorized project. 
The Reclamation Board will serve as sole sponsor for 
the Castle Dam Unit. Merced County Board of Supervisors 
reaffirmed their support for the project by letter 
of April 4, 1986. City of Merced by letter of March 13, 
1986, reaffirmed its support for and intent to furnish 
assurances for recreation aspects of the project. 
California Reclamation Board reaffirmed its support 
for total project by letter of April 9, 1986. A Local 
Cooperation Agreement (sec. 221) was executed for 
Castle Dam Unit on June 27, 1986. State of California 
legislation (AB3369) was enacted on September 14, 
1986 which enabled the Reclamation Board to financially 
participate in the project. 
Operations and results during fiscal year. A Local 
Cooperation Agreement (sec. 221) was executed for 
Castle Dam Unit on June 27, 1986. 
16. MERCED COUNTY STREAM 
GROUP, CA 
Location. Reservoirs and channel improvements are 
on Bear, Burns, Mariposa, and Owens Creeks, in foothills 
of Sierra Nevada about 15 to 20 miles east of city of 
Merced, CA. (See Geological Survey Haystack Mountain 
quadrangle for Burns and Indian Gulch quadrangle for 
Bear, Owens, and Mariposa areas.) 
Existing project. For description of completed 
improvements and authorizing act, see Annual Report 
for 1962. Improvements consist of reservoirs at Mariposa, 
Owens, Burns and Bear Creeks and diversions 
from Black Rascal Creek to Bear Creek and from Creek 
to Mariposa Creek. Total first cost for project was 
$3,899,259, of which $2,751,259 was Federal and 
$1,148,000 non-Federal for lands including relocations 
and channel improvement. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Maintenance: Ordinary maintenance and operation of 
the four completed reservoirs continued. Structures 
were maintained in a serviceable condition. Runoff 
from drainage areas above Merced County stream 
group reservoirs was below normal for the year. (See 
Table 35-K for maximum inflow storage and outflow 
for projects.) Outflows were less than channel capacity 
rates in the project streams. Project prevented an 
estimated $8,000,000 in damages from the February- 
March 1986 rainfloods. 
Historical summary. Construction was initiated 
March 1984, with construction of Mariposa project, 
which was completed in November 1984. Construction 
of Owens project, initiated in March, was completed in 
October 1949; Burns project, initiated in July 1949, was 
completed in January 1950; and Bear project initiated 
in April, was completed in December 1954. Black 
Rascal and Owens Creek diversion channels and streamgaging 
stations were completed in April 1956. Local 
interests completed channel enlargement and restoration 
of channel capacities of Miles, Burns, Owens, and 
Mariposa Creeks in 1956 at their expense. Improvement 
of Bear Creek and Black Rascal Slough, below their 
confluence, was deferred pending possible improvements 
downstream, outside limits of project. 
17. PINE FLAT LAKE AND KINGS 
RIVER, CA 
Location. Reservoir is on Kings River, about 25 miles 
east of Fresno, CA, and channel improvements are on 
Kings River downstream from Lemoore weir, about 25 
miles south of Fresno. (See Geological Survey quadrangles 
of area.) 
Existing project. Improvement is a unit in comprehensive 
plan for flood control and other related purposes 
for Sacramento-San Joaquin Basins. Project consists of 
a 429-foot high concrete gravity dam, including a gated 
overflow section with a maximum discharge capacity of 
35-12

SACRAMENTO, CA, DISTRICT 
391,000 cubic feet per second, creating a reservoir with 
gross storage capacity of 1 million acre-feet, for flood 
control, irrigation, and related purposes. Outlet provisions 
for future power development are included in 
dam, but Federal construction of power-generating 
facilities is not authorized. Improvement also includes 
levee and channel work on Kings River and its distributaries 
on valley floor about 25 miles south of Fresno. 
Channel improvement work will enlarge channel capacities 
and regulate flows in lower branches of the Kings 
River. There are nine public-use and recreation areas: 
One maintained by the Corps, four by the Forest 
Service, three jointly by the Corps and concession, and 
one by Fresno County. Also, five boat access-only areas 
are maintained by the Corps on the south side of the 
reservoir. Project cost is $42,072,330, of which 
$41,502,330 is Federal (including $13,700 for basic 
recreation facilities) and $570,000 non-Federal for 
rights-of-way for downstream channel improvements. 
For future non-Federal reimbursement, see Local 
cooperation paragraph. Federal cost of recreation 
facilities for Pine Flat Lake, funded from Code 710 
appropriations is $1,595,100 exclusive of recreation 
facilities previously provided at a cost of $13,700. In 
addition, Federal cost of recreation facilities for Pine 
Flat Lake, funded from Public Works Acceleration 
Executive Act of 1962 appropriations, was $239,235 
(July 1963). Operation and maintenance of dam and 
reservoir is Federal responsibility. Existing project 
was adopted by 1944 Flood Control Act (H. Doc. 630, 
76th Cong., 3d sess., contains latest published map). 
Local cooperation. Local interests must reimburse 
the Federal Government for first costs allocated to 
irrigation functions of reservoir portion of project in 
accordance with reclamation law. Under provision of 
War Department Civil Appropriations Act of 1947, the 
Secretary of War, with concurrence of the Secretary of 
the Interior, determined allocation of cost to irrigation 
should be set at an amount not to exceed $14,250,000. In 
addition, local interests must pay 37.4 percent of annual 
maintenance, operation, and replacement costs of dam 
and reservoir allocated to irrigation function. Repayment 
contracts between the Bureau of Reclamation and 
the local water users for the irrigation use of the 
reservoir were executed December 23, 1963. The Bureau 
is administering the contracts in accordance with 
reclamation law as amended by the Reclamation Reform 
Act of October 12, 1982. That act generally exempts the 
limitations under the early reclamation laws as being 
applicable to projects constructed by the Corps with two 
exceptions; however, all existing contracts to share 
construction and maintenance costs remain in effect. 
Prior to execution of the final contracts, the Bureau 
provided conservation water to local interests under an 
interim contract. Irrigation interests paid $12,686,828 
for irrigation services through December 31, 1985. 
With respect to the downstream channel improvements, 
sec. 3, Flood Control Act of June 22,1936, applies. King 
River Conservation District represents local interests; 
assurances were accepted November 20, 1959. Local 
interests have furnished all requirements for construction 
rights-of-way for construction of channel improvements 
required to date. Three concessionaires-one 
each at Lakeridge Marina (Deer Creek), Pine Flat 
Marina and Trimmer Marina provided public-use facilities 
in accordance with lease agreements with the 
Secretary of the Army. Estimated cost to date of 
facilities installed by these concessionaires is $1,727,000. 
Fresno County developed public-use facilities on an 85- 
acre tract immediately downstream from dam for 
picnicking, camping, swimming, and playground activities, 
at an estimated cost to date of $476,000 under 
provisions of a license agreement. The U.S. Forest 
Service developed and operates a picnic area at the 
upper end of reservoir. Cost of site development is about 
$37,500. Installation of a hydroelectric powerplant, 
located at the downstream toe of the Corps Pine Flat 
Dam, was completed in January 1984 by Kings River 
Conservation District. Project consists of an outdoortype 
powerhouse containing three generating units 
with capacities of 55 megawatts each for a total of 165 
megawatts. Conservation District would make use of 
the three existing 13.5-foot diameter penstocks that 
were installed in Pine Flat Dam when constructed in 
1954. 
Licenses. License No. 1988, effective April 1, 1955, 
was issued by Federal Power Commission to Pacific 
Gas and Electric Co. for hydroelectric power development 
of North Fork Kings River by the company 
upstream from the Pine Flat reservoir. Under interim 
Contract No. DA-04-167-eng-1182 with the Department 
of the Army, Pacific Gas and Electric Co. paid for 
storage of power water in the Pine Flat reservoir 
May 15, 1954, through March 31, 1955. Current Contract 
No. DA-04-167-eng-1328 with the Department of the 
Army provides for storage of power water at the rate of 
0.1375 per acre-foot; the contract covers April 1, 1955, 
through March 31, 2005. By an agreement of January 
1972, supplementing the December 1954 contract, 
Pacific Gas and Electric Co. transferred ownership of 
most of its Kings River system water to the Kings River 
Water Association. Accordingly, no further significant 
storage service to Pacific Gas and Electric Co. by the 
reservoir at Pine Flat is anticipated. Total payment 
under these contracts through June 30, 1972, (last year 
of payment), amounts to $2,478,798; these funds are 
paid to Sacramento District and deposited for return to 
the Treasury. 
Operations and results during fiscal year. New 
work, regular funds: None. Code 710 funds: None. 
Maintenance: Maintenance and operation activities 
continued. Structures were maintained in serviceable 
condition. Runoff of Kings River above Pine Flat Dam 
was above normal for the year. Maximum storage of 
1,002,500 acre-feet occurred on June 27, 1986. Maximum 
inflow to the reservoir was 35,000 cubic feet per 
second on February 18, 1986, and maximum outflow of 
12,060 cubic feet per second occurred on June 4, 1986. 
During the year, 1,592,000 acre-feet was released for 
35-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
flood control and 1,197,100 acre-feet was released for 
irrigation and spreading. Project prevented an estimated 
$29,000,000 in damages from the February- 
March 1986 rainfloods and May-July 1986 snowmelt 
runoff. Dam safety assurance studies were continued at 
a fiscal year cost of $105,587. 
Historical summary. Construction began in April 
1947 and project, including channel improvement, was 
completed in September 1977. Main dam was initiated 
in January 1950, completed in June 1954, and has been 
operating since February 1954 to provide flood protection 
for which it was designed. Total of 35.2 miles of new 
and reconstructed levees and 13.2 miles of channel 
clearing have been transferred to the Kings River 
Conservation District for maintenance. Recreation facilities 
for various recreation areas under Code 710 appropriation 
are complete. Completed preliminary design 
and cost estimates for Pine Flat fish barrier were 
reviewed by the State, but the State was unable to 
provide necessary assurances of local cooperation. Dam 
safety assurance studies were initiated in FY 1982. A 
cultural resources survey was completed in FY 1984. 
18. RUSSIAN RIVER BASIN, CA 
Location. Russian River rises in Coast Range in 
northwestern California, flows southerly for 87 miles, 
and then turns westerly to flow for 23 miles to Pacific 
Ocean at Jenner, 60 miles northwest of San Francisco, 
CA. (For general location see Geological Survey map 
for California.) 
Existing project. Active authorized project provides 
for construction of a dam on East Fork of Russian River 
at Coyote Valley to a height of 160 feet; a dam on Dry 
Creek at Warm Springs to a height of 319 feet; and 
channel stabilization works on Russian River between 
mouth and mile 98, on lower reaches of several tributaries, 
and on Dry Creek downstream from dam. Coyote 
Valley Dam (Lake Mendocino), completed in 1959, is 
operated and maintained by the United States. (See 
tables 35-L and 35-M for latest approved estimated 
costs.) 
Local cooperation. Fully complied with for Coyote 
Valley Dam and channel improvements accomplished 
to date. For the Dry Creek portion, local interests are 
required by the authorizing act to comply with the 
usual a., b., c. requirements for channel improvements 
and, in addition, prevent any encroachment in the 
channel of Dry Creek which would interfere with 
proper functioning of the channel improvement works; 
adjust all claims concerning water rights arising from 
the construction and operation of the improvements, 
including acquisition of water rights needed for preservation 
of fish and wildlife resources affected by the 
project; and reimburse the United States in accordance 
with the Water Supply Actof 1958, as amended, for that 
part of the construction cost, (27.8% of total construction 
cost, currently estimated at $99,400,000) and the annual 
operation, maintenance, and replacement costs allocated 
to municipal and industrial water supply, tentatively 
estimated at $358,400. The estimated annual cost to 
local interests for maintenance of channel improvement 
works is $74,900. Sonoma County Water Agency (formerly 
Sonoma County Flood Control and Water Conservation 
District) provided assurances of willingness and 
ability to meet requirements by Resolutions No. DR 
00793-1, September 25, 1961, No. DR 4770-1, 
December 17, 1962, and No. DR 45759, August 5, 
1974, for Dry Creek (Warm Springs) Lake and Channel. 
By letter dated March 7, 1967, Sonoma County Flood 
Control and Water Conservation District further indicated 
their interest in optimization. of the Dry Creek 
(Warm Springs) damsite to provide additional water 
supply storage. Reimbursement to the United States for 
Dry Creek (Warm Springs) Lake and Channel costs 
allocated to 212,000 acre-feet of water supply storage is 
specified in a water supply contract with the local 
sponsor approved in October 1982. Local interests have 
expended approximately $1,000,000 to provide partial 
flood protection in project area and have constructed 
facilities at an approximate cost of $20,000,000 to 
distribute water from the completed Coyote Valley 
reservoir. 
Operations and results during fiscal year. New 
work: Coyote Valley Dam: None. Dry Creek (Warm 
Springs) Lake and Channel: Engineering activities 
included initiating plans and specifications for the 
Yorty Creek Beach area; and essentially completing 
plans and specifications for upgrading Rockpile Road. 
Major items of contract work included: Functional 
completion of boundary fencing, Phase I, $387,213; 
functional completion of boat launching facilities, Phase 
II, $1,327,074; initiation of administration building 
modifications, $1,095,281; and initiation of Buzzard 
Rock camping area, $2,978,502. Maintenance: Coyote 
Valley Dam: Operation and maintenance continued. 
Spillway restoration was initiated at fiscal year contract 
cost of $799,000. Structures were maintained in 
serviceable condition. Runoff of East Fork at Russian 
River was above normal for the year. Maximum storage 
of 114,300 acre-feet occurred on February 18, 1986. 
Maximum inflow to reservoir was 12,000 cubic feet per 
second on February 17, 1986. Maximum release of 
6,400 cubic feet per second occurred on February 18, 
1986. During the year, 179,100 acre-feet was released 
for flood control, and 131,000 acre-feet was released for 
irrigation and other purposes. Project prevented an 
estimated $500,000 in damages from the February- 
March 1986 rainfloods. Dam safety assurance studies 
were continued at fiscal year cost of $85,455. Dry Creek 
(Warm Springs) Lake and Channel: Operation and 
maintenance continued. Structures were maintained in 
serviceable condition. Runoff of Dry Creek at Warm 
Springs Dam was above normal for the year. Maximum 
storage of 264,300 acre-feet occurred March 11, 1986. 
Maximum inflow to reservoir was 23,000 cubic feet per 
second on February 17, 1986. Maximum release of 
2,600 cubic feet per second occurred March 15, 1986. 
During the year, 71,300 acre-feet was released for flood 
control, and 53,700 acre-feet was released for irrigation 
35-14

SACRAMENTO, CA, DISTRICT 
and other purposes. Project prevented an estimated 
$13,200,000 in damages from the February-March 
1986 rainfloods. 
Historical summary. Entire project, exclusive of 
recreation facilities at completed project (Lake Mendocino), 
is about 94 percent complete. Coyote Valley Dam, 
initiated November 1958, was completed April 1959 
(cost $17,550,000, of which $11,952,000 was Federal; 
and $5,598,000 contributed). Work, including removal 
of slides resulting from storms in 1958, was completed 
April 1959. Bank stabilization work on Russian River 
near Geyserville was completed in 1957 and channel 
improvements in remaining reaches on Russian River 
and East Fork of Russian River were completed in 1974 
(cost $2,483,900). In April 1982, responsibility was 
transferred to the Sacramento District. 
Warm Springs construction completions include fish 
hatchery in December 1980, reservoir clearing in July 
1981, project overlook in May 1981, downstream stabilization 
sills in October 1981, dam closure in October 
1982, spillway repair at Warm Springs Dam in 
September 1985, and boat launching facilities, Phase I, 
in September 1985. Initial filling of Warm Springs 
reservoir was commenced on November 1, 1984. Major 
items of work remaining include upgrading Rockpile 
Road, minimal recreation facilities, boat ramp and 
administration facilities, and vegetation management 
program with remaining boundary fencing. Responsibility 
for construction was transferred to Sacramento 
District in August 1983. Dam safety assurance studies 
were initiated at Coyote Valley Dam in fiscal year 1984. 
19. SACRAMENTO RIVER AND 
TRIBUTARIES, CA, FROM 
COLLINSVILLE TO SHASTA DAM 
Location. Rises in Trinity Mountains in north-central 
California, flows generally southerly about 374 miles 
and empties into Suisun Bay, an arm of San Francisco 
Bay at Collinsville, CA. Works covered by this improvement 
are on Sacramento River and tributaries from 
Collinsville to Shasta Dam, about mile 312. Drainage 
area above Rio Vista is 26,500 square miles (See 
Geological Survey quadrangles of area for Sacramento 
River and Upper Butte Basin; Flournoy and Fruto 
quadrangles for Black Butte Lake; and Tuscan Buttes, 
Tehama, Redding, and Hooker quadrangles for Table 
Mountain Lake.) 
Existing project. Improvement of Sacramento River 
and tributaries, from Collinsville to Shasta Dam was 
authorized as a unit of a comprehensive plan for flood 
control and other related purposes in Sacramento River 
Basin. (a) Sacramento River and major and minor 
tributaries, for flood control purposes: Enlargement of 
existing levees on Sacramento River between vicinity of 
Moulton weir and Ord Bend; construction of new levees 
from present levee terminus to vicinity of Chico Landing; 
construction of a weir near Chico Landing, extension of 
Moulton weir, and construction of a bypass through 
Upper Butte Basin; construction of new levees in Lower 
Butte Basin; enlargement of existing levees in Sutter, 
Tisdale, Sacramento, and Yolo Bypasses; and levee 
construction and/or channel enlargement on following 
minor tributaries of Sacramento River: Antelope Creek; 
Chico and Mud Creeks and Sandy Gulch; Butte and 
Little Chico Creeks; Cherokee Canal; Elder Creek; Deer 
Creek (Tehama County); Thomes Creek; and Willow 
Creek. Improvement provides for about 155 miles of 
channel improvement and about 294 miles of levees 
with an average height of 12 feet and a freeboard of 3 
feet. Improvement also provides for revetment as required 
for protection of bypass levee slopes against 
erosion. Total first cost for project is $18,300,000 
(October 1986), of which $11,900,000 is Federal, and 
$6,400,000 non-Federal for lands and damages, including 
relocations. (See table 35-N on project units classified 
and excluded from cost estimate.) (b) Sacramento 
River, Chico Landing to Red Bluff, CA: An extension of 
the existing Sacramento River Flood Control project 
which provides for construction of bank protection 
works and minor channel improvements as required on 
Sacramento River between Chico Landing and Red 
Bluff for flood control purposes. Estimated first cost 
(October 1986) for project work in Tehama, Butte, and 
Glenn Counties is $31,800,000, of which $30,000,000 is 
Federal cost and $1,800,000 non-Federal cost for lands 
and damages including relocations. (c) Sacramento 
River, CA, Bank Protection Project: Includes initial 
phase covering 405,000 lineal feet of bank protection 
and a second phase covering 430,000 lineal feet of bank 
protection under a long range program of bank protection, 
erosion control works, and setback levees at critical 
locations within limits of authorized or existing levees 
included in the Sacramento River Flood Control project 
to protect integrity of levee system for flood control 
purposes. Total estimated (October 1986) first cost for 
project is $132,600,000, (includes an allowance for 
estimated inflation through the construction period) of 
which $92,300,000 is Federal (including $2,845,000 for 
recreation facilities) and $40,300,000 non-Federal comprising 
for lands and damages including relocations 
and $20,300,000 required cash contribution toward 
first cost. Construction in (a), (b), and (c) above 
supplements program of levee improvements as 
accomplished pursuant to 1917 Flood Control Act, as 
amended by subsequent acts, including 1941 Flood 
Control Act, and which are reported by California 
Debris Commission under Sacramento River, CA, flood 
control. (d) Authorization also provided for Black Butte 
Lake. For description of completed project see Annual 
Report for 1975. Federal first cost for project is 
$14,508,820, including $475,507 for basic recreation 
facilities. For future non-Federal reimbursement, see 
Local cooperation paragraph. Federal cost for recreation 
facilities funded from Code 710 appropriations 
is $1,000,162. A concessionaire at Black Butte Marina 
provided public use facilities in accordance with lease 
agreement with the Secretary of the Army at an 
estimated cost to date of $87,000. (e) Authorization also 
35-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
provided for construction of Table Mountain (Iron 
Canyon) project, an earthfill dam on Sacramento River 
about 3 miles north of Red Bluff, CA. This project unit 
was deauthorized August 5, 1977. For details, see 
Annual Report for 1978. 
Local cooperation. (a) Sacramento River and major 
and minor tributaries: Sec. 3, Flood Control Act of June 
22, 1936, applies. Fully complied with for all work 
completed or under contract, and local interests indicated 
they will be able to fulfill requirements for 
remaining work as scheduled. Levee construction (107 
miles) total requirement for the "active" project has 
been completed, transferred to, and accepted by the 
State. (b) Sacramento River, Chico Landing to Red 
Bluff: Sec. 3, Flood Control Act of June 22, 1936, 
applies; local interests must also assume responsibility 
for flood plain zoning. Fully complied with for portions 
completed in Tehama, Butte, and Glenn Counties; 
completed work, bank protection at 36 sites, was transferred 
to and accepted by the State. (c) Sacramento 
River Bank Protection Project: Sec. 3, Flood Control 
Act of June 22, 1936, applies. Local interests must also 
contribute an amount in cash that, when added to costs 
of lands, easements, rights-of-way and utility modifications, 
equals one-third of cost of each unit of remedial 
work; this contribution is estimated (October 1986) at 
$20,300,000. Local interests fully complied with requirements 
for all work completed or under contract, and 
indicated they will be able to fulfill requirements for 
remaining work as scheduled. In addition, for reaches 
where local interests request bank stabilization in lieu 
of more feasible levee setbacks, local interests will 
contribute costs over and above costs of setbacks, and 
provide local contribution indicated above. Completed 
units transferred to and accepted by the State. (d) Black 
Butte Lake: None required for construction. Local 
interests must pay the portion of first cost and annual 
operation and maintenance costs allocated to the conservation 
functions of the project; these costs are estimated 
at 39.9 percent of first cost and 40.2 percent of annual 
costs. From March 2, 1960, to October 22, 1970, contract 
between the Bureau of Reclamation and the State of 
California provided for repayment of irrigation storage 
costs; Bureau administered contract in accordance with 
reclamation law. Local interests paid a total of $77,205 
for irrigation services during this period. Public Law 
502, 91st Cong., 2d sess., October 23, 1970, provided that 
Black Butte project be financially integrated with the 
Central Valley project, coordinated operationally with 
other Central Valley project storage units by the Bureau 
under the Secretary of the Interior, and that dam and 
reservoir at Black Butte be physically operated and 
maintained by the Corps in a manner compatible with 
recreational use of the reservoir. 
Operations and results during fiscal year. New 
work: (a) Sacramento River and major and minor 
tributaries - Engineering activities continued. Contract 
No. 10 for bypass levee revetment on Yolo Bypass 
was awarded August 12, 1986, and construction was 
initiated at fiscal year cost of $69,999. Project prevented 
an estimated $3,000,000 in damages from the February- 
March 1986 rainfloods. (b) Sacramento River Bank 
Protection Project-Engineering and design activities 
continued. (See table 35-0 for construction accomplished 
and contract costs.) Project prevented an estimated 
$800,000,000 in damages from the February-March 
1986 rainfloods. (c) Sacramento River, Chico Landing 
to Red Bluff. California State Reclamation Board in 
cooperation with the Corps, constructed a demonstration 
project of the Palisades bank protection system at 
Woodson Bridge State Park within the project reach. 
Construction was completed in August 1986 at a fiscal 
year Corps cost of $250,000 and hopefully will have less 
environmental impact than the conventional placement 
of riprap. Project prevented an estimated $1,800,000 in 
damages from the February-March 1986 rainfloods. (d) 
Black Butte Lake, regular funds: None. Code 710 funds: 
None. Maintenance: Maintenance and operation activities 
continued. Dam safety assurance studies were 
continued at fiscal year cost of $34,324. Structures were 
maintained in serviceable condition. Runoff above Black 
Butte Dam was well above normal for the year. Maximum 
storage of 168,900 acre-feet occurred February 
18, 1986. Spillway flow occurred on February 
17, 1986, and continued through February 20, 1986, 
with maximum depth of 5.4 feet and 3,900 cubic-feet 
per second. Maximum daily inflow to Black Butte 
reservoir was 47,000 cubic feet per second on February 
17, 1986, and maximum outflow of 24,940 cubic 
feet per second occurred on February 18,1986. Releases 
of water for irrigation totaled 134,800 acre-feet and 
flood control releases totaled 615,800 acre-feet. Project 
prevented an estimated $5,500,000 in damages from the 
February-March 1986 rainfloods. (e) Table Mountain 
(Iron Canyon) Lake: None. 
Historical summary. (a) Sacramento River and 
major and minor tributaries (active portions): Construction 
was initiated in May 1949 on Deer Creek and Butte 
Creek units; Cherokee Canal, Elder Creek, Chico and 
Mud Creeks, and Sandy Gulch units have been completed. 
Active portion of this improvement is about 99 
percent complete. Work remaining is bypass levee 
revetment as required. (b) Sacramento River Bank 
Protection Project: Construction of first unit was initiated 
in June 1963; initial phase of project was completed 
in November 1974. Phase II is underway, and overall 
project is about 80 percent complete. (c) Sacramento 
River, Chico Landing to Red Bluff: Active portion of 
project, bank protection in Tehama County, was initiated 
in June 1963 and completed in March 1964. Project was 
reopened in June 1968 to place additional necessary 
bank protection. Work at 36 sites was completed in 
Tehama, Butte, and Glenn Counties as of September 
1985 and transferred to State for maintenance. Bank 
protection on Sacramento River, Tehama County-one 
site, mile 215, (Unit 5), was completed November 1982, 
two sites, mile 209.5 and mile 217.5, (Unit 6), were 
completed in November 1983, and four sites, 241.0, 
237.9, 237.7, and 237.5 (Unit 7) were completed in 
35-16

SACRAMENTO, CA, DISTRICT 
February 1985. (d) Black Butte Lake: Construction 
began in March 1960 and project is complete. Final 
land acquisition was completed in December 1966. 
Construction of main dam was initiated in June 1960 
and completed in December 1963. Dam has been operating 
since November 1962 to provide the flood protection 
for which it was designed. Final cost allocation 
approved May 3, 1977. Dam safety assurance studies 
were initiated in FY 1980. Piezometer installation and 
slope for protection at the dam were completed in FY 
1983. A cultural resources survey was completed in FY 
1984. (e) Table Mountain (Iron Canyon) Lake: Project 
unit deauthorized as of August 5, 1977. 
20. WALNUT CREEK, CA 
Location. Project is on Walnut Creek and lower 
reaches of its principal tributaries, Pacheco, Grayson, 
San Ramon, Las Trampas, Galindo, and Pine Creeks in 
Contra Costa County, CA. Improvement will extend 
from Suisun Bay to head of project about 1 mile above 
southern limits of city of Walnut Creek. City of Walnut 
Creek is about 10 miles south of Suisun Bay. (See 
Geological Survey quadrangles for area.) 
Existing project. Comprises extension of existing 
levees, construction of new levees and concrete channels, 
channel rectification and enlargement, and utilization 
of improvements constructed or planned by local interests. 
Plan provides for about 21.8 miles of channel 
improvement, two reinforced-concrete drop structures, 
two stilling basins, and 13.8 miles of levees. Cost 
estimate (1986) is $88,800,000 (includes an allowance 
for estimated inflation through the construction period), 
of which $63,700,000 is Federal cost and $25,100,000 is 
non-Federal cost (includes $20,000,000 for lands and 
damages and relocations except railroad facilities, and 
$5,100,000 required cash contribution for land enhancement 
benefits provided by the project). Local interests 
have expended about $3 million for flood control in the 
project area during the period 1955-1965, including the 
concrete conduits constructed through the city of Walnut 
Creek at an estimated cost of $1,000,000 considered a 
preproject condition to be incorporated in the Corps 
project. The cost thereof is not included in above costs of 
local cooperation. Improvement adopted by 1960 Flood 
Control Act (H. Doc. 76, 86th Cong., 1st sess., contains 
latest published map). 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies, except that relocation of railroad 
facilities is a Federal responsibility. In addition, local 
interests must make a cash contribution to the United 
States, in amount of 7.4 percent of cost of construction 
for land enhancement benefits provided by project. 
Cash contribution is estimated (October 1986) at 
$5,100,000. Local interests are represented by Contra 
Costa County Flood Control and Water Conservation 
District; formal assurances, including evidence of financial 
and legal ability to fulfill requirement for the cash 
contribution, were accepted by the Sacramento District 
Engineer on November 15, 1963. The Flood Control 
District furnished all rights-of-way required to date 
and indicated that it will furnish all requirements as 
needed for future construction. The Flood Control 
District will arrange for highway bridge modifications 
and utility relocations before start of work by the Corps 
contractor. Payment of required contributed funds will 
be made in installments in amounts equal to 7.4 percent 
of the estimated construction expenditure for each 
fiscal year. To date, $3,338,247 has been furnished. 
Operations and results during fiscal year. New 
work: Engineering and design for the uncompleted 
portions of Walnut and San Ramon Creeks and upper 
Pine Creek is continuing. Construction on San Ramon 
Bypass Channel has been split into three contracts. 
Contract No. 1 was initiated at fiscal year contract cost 
of $2,126,445 and Contract No. 2 was initiated at fiscal 
year contract cost of $399,999. Project prevented an 
estimated $12,500,000 in damages from the February- 
March 1986 rainfloods. 
Historical summary. Construction was initiated 
June 1964; project is about 82 percent complete. Total of 
16.7 miles of channel improvement, 9.2 miles of levee 
construction, part of channel improvement landscaping, 
and Drop Structures No. 1 and 2 have been transferred 
to local interests for operation and maintenance. Planning 
and design continued on remaining reaches. Work 
remaining consists of channel improvement on Walnut 
Creek and San Ramon bypass (Ygnacio Valley Road to 
Rudgear Road along SPRR alignment) and upper Pine 
Creek. 
Construction responsibility was transferred from 
San Francisco District on April 1, 1982. 
21. WILDCAT AND SAN PABLO 
CREEKS, CA 
Location. Project is located in vicinity of San Pablo 
and Richmond, Contra Costa County, CA, about 20 
miles northeast of San Francisco, CA. 
Existing project. Plan of improvement consists of 
15,900 lineal feet of channel improvements on Wildcat 
Creek and 9,600 lineal feet of channel improvements on 
San Pablo Creek. Improvements include channel deepening, 
levees, stilling basins, and flow control weirs. 
Plan would also create a linear park environment with 
picnic facilities, comfort stations, full environment 
treatment, and a two-mile segment of trail to connect 
with other regional park trails in the vicinity. Approved 
estimated cost of new work (1986) is $33,200,000 (includes 
an allowance for estimated inflation through the 
construction period), of which $19,200,000 is Federal 
cost, and $14,000,000 is non-Federal cost (includes 
$1,700,000 cash contribution). Improvements adopted 
by House and Senate Public Works Committee 
Resolutions June 9 and 15, 1976, respectively, under 
provisions of sec. 201 of Flood Control Act of 1965 (H. 
Doc. 511, 94th Cong., 2d sess., contains latest published 
map). 
35-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Local cooperation. Local interests will be required 
to: (a) provide, without cost to the United States, all 
lands, easements, and rights-of-way necessary for construction 
and operation of the project, including disposal 
areas, and adhere to requirements of sec. 210 of the 1970 
Uniform Relocation Assistance and Real Property 
Acquisition Policies Act, Public Law 91-646; (b) modify 
or relocate all utilities and bridges (except railroad) 
necessary for construction and maintenance of the 
project with such modifications and replacements being 
in accordance with plans approved by the Chief of 
Engineers, and replace vehicular traffic facilities, including, 
but not limited to, streets, curbs, gutters, and 
signs affected by the project; (c) maintain and operate 
the flood control portion of the project after completion, 
in accordance with regulations prescribed by the Secretary 
of the Army, and prevent encroachment of the 
flood channels that may result in decreasing the effectiveness 
of the project; (d) maintain, operate, and 
replace recreation facilities; (e) hold and save the 
United States free from damages due to construction 
works; (f) adjust all claims regarding water rights that 
might be affected by the project; (g) make a cash 
contribution prior to start of construction for that 
portion of the cost of recreation lands and recreational 
facilities; (h) assure access to all persons on equal terms 
for approved recreational use; (i) at least annually 
inform affected interests regarding the limitations of 
protection afforded by the project; and (j) publicize 
flood plain information in the areas concerned and 
provide this information to zoning and other regulatory 
agencies for their guidance and leadership in preventing 
unwise future development in the flood plain, and in 
adopting such regulations as may be necessary to insure 
compatibility between future development and protection 
levels provided by the project. The Board of 
Supervisors of Contra Costa County by Resolution 73- 
466, June 25, 1973, agreed to assume obligations of 
local cooperation. On November 9, 1976, the Board 
reaffirmed sponsorship by Resolution 76-960. Contra 
Costa County Flood Control and Water Conservation 
District Board of Supervisors formed an Assessment 
District, August 3, 1982, which assures availability of 
funds for local share of non-Federal portion of project 
costs for a modified plan of improvement. Prior to 
construction, the Board of Supervisors of Contra Costa 
County will be required to furnish assurances to comply 
with sec. 221 of the 1970 Flood Control Act and sec. 77 of 
the 1974 Flood Control Act and to furnish assurance 
that in the acquisition of all lands, easements, and 
rights-of-way they will comply with requirements of 
sec. 210 of the 1970 Uniform Relocation Assistance and 
Real Estate Acquisition Policy Act, Public Law 91-646. 
A letter of intent to sign sec. 221 agreement was 
furnished by local sponsor on April 23, 1985. 
Operations and results during fiscal year. In 
October 1983, work was resumed by Sacramento District 
on the project. A general design memorandum and an 
environmental impact statement were completed. Flood 
Control Local Cooperation Agreement was executed in 
June 1986. 
Historical summary. Project has been inactive since 
1979. Project responsibility was transferred from San 
Francisco District on April 1, 1982. In October 1983, 
project work was resumed by Sacramento District. A 
revised final environmental impact statement was filed 
March 28, 1986, and a general design memorandum 
was approved May 29, 1986. Flood Control Local 
Cooperation Agreement was executed June 20, 1986. 
22. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Approved regulations for operation and maintenance 
of flood control works, part 208, title 33, Code of Federal 
Regulations, provide for inspection of completed projects 
transferred to local interests for operation and maintenance 
to determine status of project and insure compliance 
with regulations. During fiscal year, inspections 
were made of: Completed units of Sacramento River 
and major and minor tributaries; completed units of 
Sacramento River, Chico Landing to Red Bluff; completed 
units of Sacramento River flood control project, 
Kings River Channel Improvement (Pine Flat Lake 
project), and Walnut Creek project; American River 
levees; Chester, North Fork Feather River; levee and 
channel improvements on Chowchilla River (Buchanan 
project) and Fresno River (Hidden project); Duck Creek 
diversion, Green Valley Creek, Littlejohn Creek, 
Mormon Slough, Bear Creek, Kern River-California 
Aqueduct Intertie, and North Fork, Pit River at Alturas, 
all in California; Truckee River, CA and NV; completed 
units of lower San Joaquin River and tributaries, CA; 
Big Dry Creek Dam and diversion, CA; Reese River, 
Battle Mountain, NV; Sevier River, Redmond and 
vicinity, Jordan River, Big Wash near Milford, and 
Kays Creek, all in Utah; various emergency flood 
control works under authority of sec. 208, Flood Control 
Act of June 30, 1948, and September 3, 1954; Public 
Law 99, June 28, 1955, and aftecedent legislation; and 
sec. 14 of Flood Control Act of July 24,1946. Maintenance 
inspections conducted indicate that existing agreements 
and regulations are being complied with on completed 
flood control works. Continuing effort is required to 
improve maintenance practices and active steps are 
being taken by responsible State and local agencies to 
achieve desired results. Local agencies were advised, as 
necessary, of measures required to maintain these 
projects in accordance with standards prescribed by 
regulations. Total cost of inspection for fiscal year of 
$572,070 included continuation of dam safety assurance 
program for Folsom Lake, CA ($390,327). 
35-18

SACRAMENTO, CA, DISTRICT 
23. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to sec. 205, Public 
Law 858, 80th Congress, as amended (Preauthorization). 
Costs for preauthorization studies for fiscal year were 
as follows: $45,105 for Fourteenmile Slough, CA; $5,069 
for Papermill Creek, CA; and $18,304 for Bear River, 
Smith Fork, Cokeville, WY. 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Cong., and antecedent legislation). 
Federal cost for fiscal year was $4,462,397, of which 
$199,477 was for disaster preparedness, $2,906,501 for 
flood emergency operations, $1,333,291 for repair and 
restoration, and $23,128 for advance measures. 
Emergency bank protection (sec. 14, 1946 Flood 
Control Act, Public Law 526, 79th Cong.). 
No emergency bank protection activities this fiscal 
year. 
Snagging and clearing navigable streams and 
tributaries in interest of flood control (sec. 208,1954 
Flood Control Act, Public Law 780, 83d Cong.). 
No snagging and clearing activities this fiscal year. 
Flood insurance activities (sec. 1301-1377, 1968 
Housing and Urban Development Act, Public Law 
90-448 as amended). 
In coordination with flood control activities, three 
flood insurance studies were initiated and two flood 
insurance studies were completed in accordance with 
Inter-Agency Agreements EMW-E-1153 and EMW-E- 
2226 at a fiscal year cost of $218,665 under Federal 
Emergency Management Agency reimbursable order. 
24. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
In accordance with sec. 7, Flood Control Act of 1944, 
summaries of monthly operations at Big Dry Creek, 
Boca, Camanche, Del Valle, Folsom, Friant (Millerton 
Lake), Indian Valley, Los Banos Detention, New Bullards 
Bar, New Don Pedro, New Exchequer (Lake McClure), 
New Melones, Oroville, Prosser, Shasta, and Stampede, 
CA; East Canyon, Echo, Lost Creek, Pineview, Starvation, 
and Wanship, UT; Blue Mesa, Lemon, Paonia, and 
Vallecito, CO; and Navajo, NM reservoirs were prepared. 
Work was continued on the Blue Mesa water 
control manual. Corps personnel provided advice as 
requested during flood control operations at all sec. 7 
reservoirs. Fiscal year cost was $285,755. Total cost to 
September 30, 1986, $2,952,911. 
Multiple-Purpose Projects including Power 
25. NEW MELONES LAKE, CA 
Location. On Stanislaus River about three-quarters 
mile downstream from existing Melones Dam and 
about 35 miles northeast of city of Modesto. (See 
Geological Survey quadrangles of the area.) 
Existing project. Provides for construction of (a) an 
earth and rockfill dam about 625 feet high to create a 
reservoir with gross storage capacity of about 2,400,000 
acre-feet for flood control, irrigation, power, general 
recreation, fish and wildlife, and other purposes, and (b) 
a powerplant below the dam with an installed capacity 
of 300,000 kilowatts. Upon completion of construction of 
dam and powerplant by the Corps, the project became 
an integral part of Central Valley project and is being 
operated and maintained by the Secretary of the Interior 
pursuant to Federal reclamation laws, except that the 
flood control operation of the project shall be in accordance 
with rules and regulations prescribed by the 
Secretary of the Army. Maintenance of Stanislaus 
River channel from Goodwin Dam to San Joaquin River 
to a capacity of at least 8,000 cubic feet per second will 
also be Corps responsibility. Approved estimated 
(October 1986) Federal cost is $385,000,000 (includes an 
allowance for estimated inflation through the construction 
period). For future non-Federal reimbursement, 
see Local cooperation paragraph. In addition, local 
interests expended $300,000 for levees along lower 
reaches of Stanislaus River. Existing project was 
adopted by 1962 Flood Control Act (H. Doc. 453, 87th 
Cong., 2d sess., contains latest published map). This act 
modified original authorization adopted by 1944 Flood 
Control Act. (H. Flood Control Committee Doc. 2, 78th 
Cong., 2d sess., contains latest published map.) The 
1944 Flood Control act established $8 million monetary 
limitation for partial accomplishment of project. Further 
monetary authorizations of $2.5 million, $5 million, 
$13 million, $2 million, $17 million, $18 million, $44 
million, $83 million, $46 million, $6 million, and $61 
million were provided for this project by Public Laws 
235 and 780, 83d Cong., and 85-500, 90-17, 90-483, 91- 
282, 92-222, 93-251, 94-397, 95-104, and 95-189, making 
a total monetary authorization of $305,500,000 available 
for the basin plan comprising Lower San Joaquin River 
and tributaries, including Tuolumne and Stanislaus 
Rivers, CA. Since FY 1979, appropriations have not 
been subject to the river basin monetary limitation. 
Local cooperation. Based on approved preliminary 
cost allocation studies (July 1965) local interests will be 
required to pay 35.2 percent of first cost and 12.7 
percent of annual operation and maintenance costs 
allocated to irrigation. In addition, 31.1 percent of first 
cost and 62.5 percent of annual cost would be allocated 
to power. Local interests must also maintain existing 
private levees along Stanislaus River from Goodwin 
Dam to San Joaquin River and prevent encroachment 
on channel and floodway between levees to preserve 
safe carrying capacity throughout the reach of at least 
8,000 cubic feet per second. Recovery of costs allocated 
to irrigation and power will be the responsibility of the 
Bureau of Reclamation. Reimbursement of costs will be 
in accordance with Bureau policies and procedures for 
the Central Valley project. State of California officially 
35-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
adopted project by chapter 918 of statutes of 1963, and 
by chapter 1438 of those statutes authorized State 
Reclamation Board to furnish required assurances. The 
Board, by letter dated December 13, 1963, stated it 
would furnish required assurances when formally 
requested to do so. Assurances were requested by letter 
of December 30, 1977. On October 2, 1979, the Board 
reaffirmed its intent to furnish the required assurances. 
On January 6, 1983, the Board provided formal assurances 
of local cooperation. 
Operations and results during fiscal year. New 
work: Engineering activities continued including continuation 
of plans and specifications for the Lower 
Stanislaus recreation areas, minimal recreation facilities 
only. Fiscal year costs for major items of work 
included: Continuation of land acquisition activities, 
$427,195; completion of Glory Hole minimal recreation 
facilities, Phase II contract, $106,050; final completion 
of Tuttletown minimal recreation facilities; $27,951; 
initiation of McHenry recreation area contract, 
$500,000, and completion of Lower Stanislaus Phase II 
minimal recreation facilities (including Knights Ferry 
and Horseshoe Bar recreation areas), $155,567, 
Maintenance: Maintenance and operation activities 
continued on Lower Stanislaus River. Project prevented 
an estimated $102,500,000 in damages from the 
February-March 1986 rainfloods. 
Historical summary. Construction was initiated in 
August 1966. Main dam contract which was awarded in 
March 1974 has been completed; dam dedication ceremonies 
were held July 14, 1979. Cultural resources 
preservation, water intake facilities, flood control and 
irrigation tailrace modification, reservoir area clearing, 
Tuttletown Phase I recreation area, Oakdale recreation, 
Glory Hole Phase I and Phase II recreation area, and 
operations access road contracts have all been completed. 
Glory Hole minimal recreation facilities contract has 
been completed. A boundary fencing contract, Lower 
Stanislaus Phase I and Phase II minimal recreation 
facilities contract, Lower Stanislaus Corporation Yard 
contract, and Lower Stanislaus Administration Building 
contract have been completed. Tuttletown minimal 
recreation facilities contract has been completed. 
McHenry recreation area contract has been initiated. 
Overall project is nearing completion except for Lower 
Stanislaus River recreation facilities. Remaining recreation 
facilities were unscheduled pending development 
of cost sharing agreements with local interests. A 
Memorandum of Understanding between the Department 
of the Interior and the Department of the Army 
transferring the New Melones dam and reservoir from 
the Corps of Engineers to the Bureau of Reclamation 
was executed on November 20, 1979. Agreement provides 
that the Corps complete land acquisition actions 
and retain budgeting, design, and construction responsibility 
for reservoir clearing and recreation development; 
completion of cultural resources mitigation in 
project area was vested in the Department of the 
Interior. The California State Water Resources Control 
Board's Decision 1422 of April 1973 established conditions 
which impacted on the planned filling and 
operation of the project by the Department of the 
Interior. As a result, the Department of Interior brought 
suit against the State of California claiming State 
limitations on project operation were contrary to 
Congressional intent and authority. The case was heard 
before the U.S. District Court in Fresno, CA, and in 
early March 1981, a Federal judge ruled that the 
Federal Government could fill the New Melones reservoir 
for purpose of generating electrical power, but not 
for agricultural or other purposes. Both the Government 
and the California State Resources Control Board 
appealed this decision to the 9th Circuit Court of 
Appeals in San Francisco, CA. 
On December 20, 1982, the Court upheld all 25 
requirements placed on the Federal Government by the 
State Water Resources Control Board. The decision 
reversed the lower court's decision to permit filling of 
the reservoir for generating electrical power. The 
Bureau of Reclamation subsequently filed for a permit 
from the State Water Resources Control Board to fill 
the reservoir. Permit was approved. The Bureau had 
originally started generating power on a limited basis 
on July 1, 1979; however, after the filling of the 
reservoir in spring of 1983, full power generating 
benefits are being attained. Project is about 98 percent 
complete. 
General Investigations 
26. Surveys 
Fiscal year costs were $2,103,028, of which $1,948,128 
was for flood damage prevention studies; $5,000 for 
coordination with Soil Conservation Service; $14,000 
for coordination with Bureau of Reclamation pertaining 
to projects under reclamation program (including 
PL 984); $82,000 for special investigations; $30,000 
review of FERC licenses; and $23,900 for planning 
assistance to states ($19,900, CA; and $4,000, CO). 
MORRISON CREEK STREAM 
GROUP, CA (PHASE I, STUDY) 
Phase I studies (estimated cost $3,000,000) were 
authorized by sec. 101(a), Water Resources Development 
Act, of 1976, in accordance with Report of Chief of 
Engineers, March 2, 1976. Proposed plan of improvement 
would be located on streams in Morrison Creek 
Stream Group Basin in the central part of Sacramento 
County and would provide for construction of a dam 
with an 11,000 acre-foot reservoir at the Vineyard site 
on Elder and Laguna Creeks, diversion of Morrison 
Creek flows into this reservoir, construction of 26 miles 
of levee and 66 miles of channel work along streams in 
the basin, and purchase of lands and related construction 
for a 7,800-acre flood retardation basin in the Beach- 
Stone Lakes area. Draft of Phase I General Design 
Memorandum was completed September 30; 1986, at a 
fiscal year cost of $120,249. City and County of Sacramento 
intend to construct channel portion of plan. 
Corps will pursue the flood control alternatives in 
35-20

SACRAMENTO, CA, DISTRICT 
Beach-Stone Lakes area under the Small Flood Control 
Project authority. 
CONTINUATION OF PLANNING 
AND ENGINEERING 
CACHE CREEK BASIN, CA 
Project is located on eastern slope of the Coast Range. 
Clear Lake unit is about 110 miles north of San 
Francisco and Settling unit is about 15 miles northwest 
of Sacramento. 
Plan of improvement consists of two project units: 
Upper basin at Clear Lake-widening and/or deepening 
3.3 miles of existing 5 mile long Clear Lake outlet 
channel to a capacity of 8,000 cubic feet per second, 
constructing a 1.1 mile long bypass channel around the 
highly developed area adjacent to existing channel, and 
nonstructural measures; and lower basin at the mouth 
of Cache Creek--enlarging existing perimeter levees of 
Cache Creek Settling Basin an average of 12 feet to 
provide 50 years of sediment storage capacity and 
enlarging existing project levees from settling basin 
mouth upstream to County Road 102, reconstructing 
and enlarging existing Cobble weir, degrading the 
existing training levees and rebuilding them adjacent 
to the western perimeter levee to allow utilization of 
entire basin for sediment deposition, purchasing in fee 
3,600 acres of existing settling basin and establishing a 
wildlife refuge and nonstructural measures. 
Preconstruction planning estimate is $3,000,000. Continuation 
of planning and engineering, including a 
sedimentation study for Upper Basin and separate 
General Design Memorandums for the Clear Lake 
Outlet Channel (Upper Basin) and Cache Creek Settling 
Basin (Lower Basin) without wildlife refuge was 
continued at a fiscal year cost of $375,436. 
GUADALUPE RIVER, CA 
Project is located in the downtown area of San Jose in 
Santa Clara County, CA. 
Plan of improvement includes widening and deepening 
of one or both sides of Guadalupe River for 3.5 
miles and the construction of an underground concrete 
channel bypass conduit 2,900 feet long to provide flood 
protection to downtown San Jose, including approximately 
550 commercial businesses, 2,400 private 
residences, 4 major traffic arteries, and the San Jose 
International Airport. Plan also includes fish and 
wildlife mitigation measures, would preserve to the 
greatest degree possible the existing riparian vegetation 
along Guadalupe River, and would also enhance the 
redevelopment potential of the downtown San Jose 
area. 
Estimated preconstruction planning cost is 
$2,000,000. Feasibility Report passed the Board of 
Engineers for Rivers and Harbors June 29, 1986 and is 
currently under consideration by the Chief of Engineers. 
Continuation of planning and engineering was initiated 
at fiscal year cost of $16,822. 
REDBANK AND FANCHER CREEKS, CA 
Project is located northeast of Fresno-Clovis metropolitan 
area in Fresno County, CA. 
Plan of improvement includes flood control detention 
basins on Redbank Creek, Pup Creek, and Alluvial 
Drain; construction of a flood control reservoir on 
Fancher Creek; and enlargement of Big Dry Creek 
project to provide increased flood protection and recreation 
opportunities. 
Estimated preconstruction planning cost is $3,545,000. 
General Design Memorandum was completed (approved 
June 11, 1986); Concrete Materials Design Memorandum 
was completed (approved July 17, 1986); three Site 
Geology Design Memorandums on Big Dry Creek, 
Fancher Creek, as well as on three detention basins 
(Pup Creek, Alluvial Drain and Redbank Creek) were 
completed (all approved August 20, 1986); and draft of 
Detention Basins Feature Design Memorandum was 
completed in August 1986 at a fiscal year cost of 
$813,805. 
27. COLLECTION AND STUDY OF 
BASIC DATA 
Technical assistance was performed for other Federal 
agencies as well as non-Federal agencies in connection 
with Flood Plain Management Services Program at 
fiscal year cost of $368,059. No Flood Plain Information 
Studies were prepared after FY 1980. 
Fiscal year costs for hydrologic studies were $8,000. 
28. RESEARCH AND DEVELOPMENT 
The Hydrologic Engineering Center was designated 
as a separate Field Operating Agency as of January 1, 
1979, in accordance with OCE permanent orders 1-1, 
January 10,1979, but Sacramento District is continuing 
to provide advisory and administrative support services 
to HEC as specified in local support agreement 
DACW05-79-A-0038 of March 1979. Fiscal year costs 
were $1,186,567, of which $152,995 was for planning 
methodologies, $622,960 was for analytical techniques, 
$133,537 for Water Conservation and Supply, $194,214 
for risk assessment for Corps dams and $82,861 for 
earth resources satellites, all at the Hydrologic Engineering 
Center. 
29. ADVANCE ENGINEERING AND 
DESIGN 
COTTONWOOD CREEK, CA 
Project will be located on main stem and the North, 
South, and Middle Forks of Cottonwood Creek on 
eastern slope of the Coast Range and southern slope of 
Trinity Range between cities of Redding and Red Bluff, 
CA, and was authorized by the 1970 Flood Control Act 
(Document not yet printed). 
Plan of improvement provides for two multiplepurpose 
reservoirs, one at Dutch Gulch (capacity 900,000 
35-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
acre-feet) and one at Tehama (capacity 700,000 acrefeet), 
and includes base facilities for future installation 
of hydropower generating equipment. 
General Design Memorandum and Environmental 
Impact Statement were completed in FY 1984. Advance 
Engineering and Design activities were essentially 
discontinued in FY 1985 as by letter of June 25, 1985, 
the State of California indicated they could not financially 
participate in the project at this time. Final 
documentation of record of the Advance Engineering 
and Design studies was initiated at a fiscal year cost of 
$17,510. 
PAJARO RIVER BASIN, CA 
Pajaro River and tributaries drain an area of 1,300 
square miles in the Coast Range and empty into Monterey 
Bay about 75 miles south of San Francisco. Pajaro 
Valley sub-basin in Santa Cruz and Monterey Counties 
includes 112 square miles in lower 13 miles of Pajaro 
River. 
Plan of improvement consists of construction of a 
variable setback levee beginning approximately 1,000 
feet upstream of Miller Avenue and ending 2,000 feet 
below Thomas Road Bridge on north side of Uvas 
Creek. 
Phase I General Design Memorandum with Environmental 
Impact Statement was completed by San 
Francisco District in FY 1982. A Post Authorization 
Change was approved by the Office of Chief of Engineers 
on August 4, 1982. Responsibility for remaining portions 
of advance engineering and design, plans and specifications 
and construction was transferred to the Sacramento 
District in April 1982. Phase I General Design Memorandum 
was approved as basis for continued preconstruction 
planning as a combined General Design 
Memorandum. Combined General Design Memorandum 
was completed in November 1984 and approved on 
June 17, 1985. Record of Decision was signed on June 20, 
1985. Plans and specifications for levee improvement 
and construction of recreation trails were approved in 
September 1985. Draft of a Local Cooperation Agreement 
for flood control was sent to the Santa Clara 
Valley Water District and reviewed by them in May 
1986. Estimated preconstruction planning cost is 
$580,000. 
30. OTHER WORK UNDER SPECIAL 
AUTHORITY 
Under the Aquatic Plant Control Program (River 
and Harbor Act of 1965, sec. 302, Public Law 289, 89th 
Congress) a State Design Memorandum and an environmental 
assessment regarding the waterhyacinth problem 
in the Sacramento-San Joaquin Delta, CA, were 
completed by the Corps in FY 1985. The Calif Department 
of Boating and Waterways had requested assistance 
from the Corps on September 28, 1981, to find a 
solution to the waterhyacinth problems in the Delta. In 
a meeting on May 28, 1985, the Department of Boating 
and Waterways notified the Corps that the State control 
program had reduced the problem to a maintenance 
problem, that State funding is adequate to operate the 
current waterhyacinth maintenance program, and that 
Federal assistance is not needed at this time. State 
control program included chemicals to eliminate the 
immediate problem and biological control agents to 
provide long term control. Cost sharing agreement (70 
percent Federal-30 percent State) was not applicable to 
preparation of State Design Memorandum nor the 
environmental assessment. Waterways Experiment 
Station (WES) has initiated a research study at an 
estimated cost of $60,000 to identify extent of waterhyacinth 
infestation in the Delta and Central Valley of 
California and to identify pathogens to control such 
infestation. Research report is to assist Sacramento 
District with its waterhyacinth problem and is scheduled 
for completion by mid FY 1987. Total Federal cost as of 
September 30, 1986, was $93,301. 
35-22

SACRAMENTO, CA, DISTRICT 
TABLE 35-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep 30, 1986 
1. Sacramento River, 
CA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
2. Sacramento River New Work 
Deep Water Ship Approp. 
Channel, CA Cost 
3. San Francisco Bay New Work 
to Stockton, CA Approp. 
(John F. Baldwin and Cost 
Stockton Ship 
Channels) 
4. San Joaquin River, New Work 
CA Approp. 
Cost 
Maint. 
Approp. 
Cost 
5. Buchanan Dam-H.V. New Work 
Eastman Lake, Approp. 
Chowchilla River, CA Cost 
(Federal Funds) Maint. 
Approp. 
Cost 
(Contributed Funds, New Work 
Other) Contrib. 
Cost 
6. Calaveras River and New Work 
Littlejohn Creek and Approp. 
Tributaries including Cost 
ew Hogan Lake and Maint. 
Farminton Dam, CA Approp. 
(Federal Funds) Cost 
(Contributed Funds, New Work 
Other) Contrib. 
Cost 
7. Corte Madera Creek, CA New Work 
(Federal Funds) Approp. 
Cost 
(Required Contributed New Work 
Funds) Contrib. 
Cost 
(Contributed Funds, New Work 
Other) Contrib. 
Cost 
8. Fairfield Vicinity New Work 
Streams, CA Approp. 
Cost 
9. Hidden Dam-Hensley New Work 
Lake, Fresno Approp. 
River, CA Cost 
(Federal Funds) Maint. 
Approp. 
Cost 
(Contributed Funds, New Work 
Other) Contrib. 
Cost 
1,514,000 
618,949 
600,000 
599,416 
6,700,000 
3,890,097 
943,000 
892,679 
33 
830,000 
766,878 
945,000 
923,280 
10,000 
2,248 
35,000 
34,868 
- - - 40,331,1921 
- - - 40,331,1921 
856,000 1,835,000 1,807,800 38,923,6312 
2,025,601 1,892,496 1,841,271 38,907,030 s 
650,000 65,000 800,000 2,340,000 
295,317 372,326 649,054 2,130,522 
3,680,000 13,580,000 12,513,000 47,456,0004 
4,314,658 14,903,051 12,140,776 45,804,7035 
850,000 
898,753 
804,000 
889,621 
- - 5,833,1176 
- - 5,833,1176 
625,000 20,000 11,947,4767 
565,138 80,224 11,944,8067 
- - 27,369,597 
- - 27,369,597 
819,000 853,000 6,726,500 
861,266 870,983 6,669,885 
- - 111,1878 
- - 111,1878 
- - 23,723,1449 
- - 23,723,1449 
1,074,000 1,563,000 1,124,000 13,142,16910 
1,093,472 1,551,672 1,132,703 13,013,47410 
30,000 40,000 20,000 1,394,25111 12 13 
24,440 43,920 26,468 1,391,32711 12 14 
325,000 525,000 2,374,000 10,258,725 xs 
281,271 390,052 1,602,532 9,308,44915 
- 110,000 -50,000 166,09516 17 
- 5,156 41,977 148,45717 
- - 270,000 806,92118 
- - 121,420 658,341'19 
320,000 155,000 905,000 2,067,000 
282,442 176,886 285,206 1,431,535 
- - - 30,555,426 
- - - 30,555,426 
510,000 773,000 969,000 874,000 7,858,500 
742,736 855,484 940,029 897,340 7,803,550 
- - - 165,11220 
- - - 165,11220 
35-23 
1
1 
l

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
10. Isabella Lake, Kern 
River, CA 
(Federal Funds) 
(Contributed Funds, 
Other) 
11 Kaweah and Tule 
Rivers including 
Terminus Dam and 
Success Lake, CA 
(Contributed Funds, 
her) 
12. Little Dell 
Lake, UT 
13. Lower San Joaquin 
River, CA 
14. Martis Creek Lake, 
Martis Creek, NV, 
and CA 
15. Merced County 
Streams, CA 
16. Merced County Stream 
Group, CA 
17. Pine Flat Lake and 
Kings River, CA 
(Federal Funds) 
(Contributed Funds, 
her) 
18. Russian River Basin, 
CA 
Coyote Valley Dam 
(Lake Mendocino) and 
Channel Improvements 
(Federal Funds) 
Contributed Funds, 
Other) 
Dry Creek (Warm 
Springs) Lake and 
Channel Improvements, 
CA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
- - - - 24,450,53721 22 
- - - - 24,450,53721 22 
2,227,400 1,773,000 3,450,000 2,426,000 23,439,99823 24 
1,924,520 1,920,956 3,633,385 2,519,690 23,322,71822 24 
- - - - 438,00025 
- - - - 438,00026 
- - - - 34,997,230w 
- - - - 34,997,230w 
1,850,000 1,524,000 1,652,000 1,893,000 20,973,52527 
1,660,695 1,758,899 1,623,969 1,918,526 20,839,1262 
- - 20,000 135,000 197,4202 29 31 
- - 3,364 80,405 126,18922 30 32 
50,000 515,000 90,000 1,335,000 4,144,900 
12,430 143,472 358,810 1,274,320 3,931,502 
- 350,000 2,300,000 448,000 3,098,000 
- 311,799 2,259,644 415,547 2,986,990 
- - - - 8,504,9893 
- - - - 8,504,9893 
243,000 242,000 1,069,000 252,000 3,698,350 
165,188 300,768 947,669 359,725 3,654,454 
500,000 - 20,000 180,000 6,550,000 
522,953 6,141 100 121,269 6,471,269 
- - - - 2,751,25934 
- - - - 2,751,2593 
120,000 47,000 130,000 81,000 1,440,506 
100,652 97,228 81,967 109,537 1,416,027 
- - - - 43,356,2656 3 37 
- - - - 43,356,26526 36 37 
1,498,000 1,481,000 1,448,000 1,492,000 18,248,285 8 39 
1,381,523 1,401,043 1,632,427 1,464,946 18,134,184 8 3 
- - - - 110,00040 
- - - - 110,00040 
-- - - 14,435,86941 
- - - ' - 14,435,86941 
1,518,000 1,707,000 1,500,000 2,542,000 22,689,07542 43 
1,196,832 2,036,905 1,565,404 2,518,357 22,574,50842 43 
20,000 50,000 85,000 78,411 233,411" 
12,795 56,295 81,218 66,758 217,06746 
23,548,000 12,000,000 5,500,000 8,615,000 293,449,64546 
22,397,207 16,490,897 5,301,011 8,878,305 292,219,90946 
35-24

SACRAMENTO, CA, DISTRICT 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
(Federal Funds) 
(Contributed Funds, 
Other) 
19. Sacramento River and 
Tributaries, CA 
from CollinSville to 
(dera nds) 
(Required Contributed 
Funds) 
(Contributed Funds, 
Other) 
20. Walnut Creek CA 
(Federal Funds) 
(Required Contributed 
Funds) 
(Contributed Funds, 
Other) 
21. Wildcat and San Pablo 
Creeks, CA 
Required Contributed 
Funds) 
(Contributed Funds, 
her 
25. Lower San Joaquin 
River and 
Tributaries, CA 
including Tuolumne 
and Stanslaus 
Rivers, CA, New 
Melones Lake, CA 
(Federal Funds) 
(Contributed Funds, 
Other) 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
N.ew Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
1,330,000 
1,141,392 
2,150,000 
1,925,392 
1,154,000 
1,554,463 
752,000 
97,482 
10,000 
4,428 
4,050,000 
4,119,569 
928,624 
800,233 
781,026 
877,114 
6,849,000 
5,825,274 
410,000 
368,700 
1, 
1, 
44 
1; 
1
1
2
,213,000 1,508,000 
,316,176 1,524,472 
30,000 30,000 
- 40,400 
,365,000 4,102,000 
,360,826 5,216,643 
;330,000 969,000 
,382,425 906,080 
495,000 1,723,000 
484,650 2,363,965 
34,000 75,000 
3,143 96,121 
,335,000 1,280,000 
,848,189 994,554 
47,165 -483,000 
239,037 -476,657 
220,000 622,000 
- 783,015 
320,000 500,000 
313,561 359,187 
- - 
5,700,000 
6,251,283 
411,000 
433,032 
80,000 
4,486 
4,700,000 
5,500,387 
437,000 
462,832 
1,772,000 
1,758,290 
3,381 
4,042,500 
3,921,536 
941,000 
1,011,304 
1,600,000 
923,511 
90,000 
101,299 
4,591,000 
3,667,875 
710,000 
641,386 
-210,000 
-232,098 
526,000 
404,415 
160,000 
150,000 
5,719,000 
2,855,897 
550,200 
529,709 
7,201,000<7 48 
7,045,62247 48 
60,00049 
43,781" 
92,643,00851 52 
92,282,24751 2 
12,877,334b 
12,808,773" 
18,555,538 
17,783,858 
2,651,362" 6 
2,647,353" 556 
43,447,43067 
42,149,585b" 
3,338,2476 
3,24 6,111� 
2,875,07161 
2,789,22961 
2,456,000 
2,187,163 
160,000 
150,00062 
347,156,996" 64 
343,682,9246 64 
2,910,200 
2,859,078 
80,000" 
4,486" 
1. Includes the following amounts for new work: Regular 
funds: Previous project, $185,198; existing project, $585,436 
for shallow-draft and $39,560,558 for deep-draft. 
2. Includes the following funds for maintenance: Regular 
funds: Previous project, $553,720; existing project, $15,463,707 
for shallow-draft and $22,836,204 for deep-draft; and deferred 
maintenance funds, $70,000 for shallow-draft. 
3. Includes the following costs for maintenance: Regular 
funds: Previous project, $553,720; existing project, $15,404,005 
for shallow-draft and $22,879,305 for deep-draft; and deferred 
maintenance funds, $70,000 for shallow-draft. 
4. Includes $23,167,800 funds for Sacramento District 
and $24,288,200 for San Francisco District. 
5. Includes $22,010,415 costs for Sacramento District 
and $23,794,287 for San Francisco District. 
6. Includes $1,158,348 public work funds, of which $207,198 
was for work done along 30-foot channel in Suisun Bay 
Channel; excludes $19,000 expended for engineering for 
inactive portion of 1950 modification. In addition, $1,342,500 
was expended from required contributed funds. 
7. In addition, $1,250 was expended from required contributed 
funds. 
8. Contributed funds, other, from State of California for 
design and construction of downstream channel improvements 
on Ash and Berenda Sloughs below Buchanan Dam. 
9. Includes Code 710 funds and costs for recreation 
facilities at New Hogan Lake: Total to date $897,742. 
35-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
10. Includes $99,000 special recreation use fees and costs 
at New Hogan Lake. 
11. For miscellaneous construction under local cooperation 
requirements, primarily Bear Creek, San Joaquin County; 
includes $108,056 as related to Duck and Littlejohn Creeks 
channel improvements as part of Farmington Dam project 
unit. 
12. Includes $393 195 contributed funds, other, from California 
Department of Boating and Waterways for design and 
construction of boat launching and related facilities, and 
$30,000 for design and construction of a boarding float at 
North Shore recreation area at New Hogan Lake. 
13. Includes $100,000 contributed funds, other, from 
Calaveras County Water District for New Hogan hydropower 
studies. 
14. Includes $97,076 contributed funds, other, costs for 
New Hogan hydropower studies. 
15. Includes $6,999,725 San Francisco District construction 
funds and costs. 
16. $8,695 contributed funds transferred to Sacramento 
District in FY 1983. 
17. Includes $97,400 San Francisco District required 
contributed funds and costs. 
18. Contributed funds, other, from Marin County including 
;536,921 for miscellaneous bridge and road relocations and 
270,000 for additional expenses for disposal sites at Corte 
Madera Creek. 
19. Contributed funds, other, costs including $536,921 for 
miscellaneous bridge and road relocations and $121,420 for 
additional expenses for disposal sites at Corte Madera Creek. 
20. Contributed funds, other, from State of California for 
miscellaneous design and construction at Hidden Dam. 
21. Includes total Code 710 funds and costs for recreation 
facilities at Isabella Lake: Total to date $2,199,085. 
22. Includes $224,000 Code 713 funds and costs for 
improvement at Tillie Creek and Live Oak campgrounds. 
23. Includes $407,640 special recreation use fees and costs 
at Isabella Lake. 
24. Includes $131,900 maintenance and operation of dam 
funds and costs (96X5125) at Isabella Lake beginning in FY 
1985. 
25. Funds from California Department of Boating and 
Waterways for design and construction of boat launching and 
related facilities at Old Isabella Road and Isabella Peninsula. 
26. Includes Code 710 funds and costs for recreation 
facilities: Success Lake: Total to date $747,048. Terminus 
Dam: Total to date $700,004. 
27. Includes $165,000 special recreation use fees and costs 
at Success Lake. 
28. Contributed funds, other, from State of California 
Department of Boating and Waterways and costs for acquisition 
of a boarding float at Success Lake, $30,000 and at 
Terminus Dam, $12,420. 
29. Includes $85,000 contributed funds, other, from the 
Kaweah River Power Authority, Visalia, CA, for Terminus 
Dam hydropower studies. 
30. Includes $53,812 contributed funds, other, costs for 
Terminus Dam hydropower studies. 
31. Includes $70,000 contributed funds, other, from DITT 
Inc., Paris, France, for hydropower studies at Success Lake. 
32. Includes $29,957 contributed funds, other, costs for 
Success Lake hydropower studies. 
33. Includes $1,200, initiation of plans and specifications 
for Code 710 recreation facilities, for FY 1978. Construction of 
recreation facilities at Martis Creek Lake under Code 710 was 
determined to be infeasible. 
34. In addition, $66,532 expended for new work from 
contributed fundsother, for miscellaneous construction under 
local cooperation requirements as related to acquisition of 
rights-of-way and utility alterations for project. 
35. Includes Code 710 funds and costs for recreation 
facilities at Pine Flat Lake: Total to date $1,595,100. 
36. Includes Public Works Acceleration, Executive (PL 
87-658) (Transfer to Corps of Engineers, Civil) 1963 funds and 
costs ($239,235) for recreation facilities. 
37. Includes $19,600 Code 713 funds and costs for Pine 
Flat fish barrier. 
38. Includes $158,300 special recreation use fees and costs 
at Pine Flat Lake. 
39. Includes $75,000 maintenance and operation of dam 
funds and costs at Pine Flat Dam. 
40. Miscellaneous construction and engineering and design 
services (non-project) accomplished at expense of State of 
California under local cooperation requirements in connection 
with acquisition of rights-of-way and utility alterations at 
Pine Flat Lake. 
41. Excludes $5,598,000 contributed funds; $400,000 for 
recreation facilities at completed projects funded under 
Public Works Acceleration Program; and $1,628,411 for 
recreation facilities at completed projects funded under Code 
711.
42. Includes $94,459 special recreation use fees and costs 
(FY 1982-1983), but excludes prior special recreation fees and 
costs for Coyote Valley Dam, Lake Mendocino. 
43. Includes $131,900 maintenance and operation of dam 
funds and costs at Coyote Valley Dam, Lake Mendocino for 
FY 1985 and FY 1986. 
44. Includes $233,411 contributed funds, other, from city 
of Ukiah for Coyote Valley Dam, Lake Mendocino, hydropower 
studies. 
45. Includes $217,067 contributed fund, other costs for 
Coyote Valley Dam, Lake Mendocino, hydropower studies. 
46. Includes $253,421,793 San Francisco construction 
funds and costs through August 1983 for Dry Creek, Warm 
Springs Dam. 
47. Includes $964,114 San Francisco maintenance funds 
and costs through April 1982 for Dry Creek, Warm Springs 
Dam. 
48. Includes $75,400 maintenance and operation of dam 
funds and costs at Dry Creek, Warm Springs Dam. 
49. Includes $60,000 contributed funds, other, from 
Sonoma County for Dry Creek, Warm Springs, hydropower 
studies. 
50. Includes $43,781 contributed fund, other costs for Dry 
Creek, Warm Springs hydropower studies. 
51. Excludes $614,608 for Table Mountain (Iron Canyon) 
project, deauthorized August 5, 1977, and $531,000 for Sacramento 
River and Major and Minor Tributaries portions which 
are considered inactive and deferred. 
52. Includes Code 710 funds and costs for recreation 
facilities at Black Butte Lake: Total to date $1,000,162. 
53. Includes $104,100 special recreation use fees and costs 
at Black Butte Lake. 
54. Miscellaneous construction and engineering and design 
services (non-project) accomplished at expense of State of 
California under local cooperation requirements in connection 
with acquisition of rights-of-way and utility alterations (primarily 
for Sacramento River and major and minor tributaries 
project). Includes State Highway Commission payment, 
789,008, for use of excess excavation from Chico and Mud 
Creeks and Sandy Gulch (Sacramento River and Major and 
Minor Tributaries) for freeway embankment through city of 
Chico. 
55. Includes $41,984, contributed funds, other, from State 
of California for required modification of existing private 
facilities, Sacramento River, Chico Landing to Red Bluff; 
$25,977 contributed funds, other, from State of California 
Department of Boating and Waterways for replacing a 
boarding float at Orland Buttes boat launching ramp at Black 
Butte Lake; and $175,000 contributed funds, other, from the 
35-26

SACRAMENTO, CA, DISTRICT 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
city of Santa Clara for hydropower studies at Black Butte 
Lake.
56. Includes $170,991 contributed funds, other, costs for 
Black Butte hydropower studies. 
57. Includes $8,849,825 San Francisco construction funds. 
58. Includes $9,049,609 San Francisco construction costs. 
59. Includes $450,268 San Francisco required contributed 
funds. 
60. Includes $525,846 San Francisco required contributed 
coSts. 
61. Includes $400,348 San Francisco contributed funds, 
other, and contributed fund costs. 
62. Includes $150,000, contributed funds, other, from 
Contra Costa Flood Control and Water Conservation District 
TABLE 35-A COST AND FINAN 
ADVANCE ENGINE 
for replacement of sewerline in Richmond for Wildcat and 
San Pablo Creeks project. 
63. Excludes funds applicable to other units of this basin 
authorization (Lower San Joaquin River and tributaries and 
Tuolumne River Basin, Calif.) (See Table 35-E). 
64. Includes $110,000 utilized for preparation of 1957 
Economic Feasibility Report and of Revised Feasibility 
Report (FY 1960, 1961, and 1962) applicable to 1962 reauthorization 
of project. 
65. Contributed funds, other, from the Bureau of Reclamation 
for visitors center at Mark Twain area, New Melones 
Lake. 
66. Contributed fund costs for visitors center at Mark 
Twain area, New Melones Lake. 
'CIAL STATEMENT 
ERING AND DESIGN 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep 30, 1986 ' 
Cottonwood Creek, New Work 
CA Approp. 3,375,000 2,885,000 1,055,000 -50,000 15,765,000 
Cost 2,667,898 3,472,949 1,019,478 17,510 15,745,469 
Pajaro River New Work 
Basin, CA Approp. 190,000 50,000 60,000 20,000 2,269,9682 
Cost 95,129 132,984 71,498 10,396 2,259,9762 
1. Beginning in FY 1982, Advance Engineering and 2. Includes $1,949,968 San Francisco construction funds 
Design programs are funded under General Investigations and costs and $240,000 Sacramento General Investigation 
Appropriations. funds and costs. 
35-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 35-B AUTHORIZING LEGISLATION 
See Date 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
Mar. 3, 1899 
July 25, 1912 
Jan. 21, 1927 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 26, 1937 
July 24, 1946 
Oct. 23, 1962 
Nov. 7, 1966 
May 17, 1950 
Feb. 10, 1956 
Oct. 23, 1962 
Mar. 7, 1974 
19. 
Dec. 22, 1944 
SACRAMENTO RIVER, CA 
A depth of 7 feet below Sacramento H. Doc. 186, 55th Cong., 
2d sess., and 48, 55th 
Cong., 3d sess. (Annual 
Report 1898, p. 2844 
and 1899, p. 3171). 
For work above Sacramento. H. Doc. 76, 62d Cong., 
1st sess. 
The 10-foot channel up to Sacramento. H. Doc. 123, 69th Cong., 
1st sess. 
A depth of 6 feet between Sacramento and Colusa and 5 feet Rivers and Harbors 
between Colusa and Chico Landing, at a cost of $390,000 Committee Doc. 35, 
provided flow of rivers is increased to minimum flow of 73d Cong., 2d sess. 
5,000 cubic feet per second after Shasta Reservoir is built. 
Authority for a special direct participation of Federal Rivers and Harbors 
Government of $12 million in cost of Shasta Reservoir. Committee Doc. 35, 
73d Cong., 2d sess. 
Transfer of authority for expenditure of above $12 million 
from Secretary of War to Secretary of the Interior. 
Modified existing navigation project for Sacramento River, S. Doc. 142, 79th Cong., 
CA, to provide for construction of a ship channel 30 2d sess. 
feet deep and 200 to 300 feet wide from deep water in 
Suisun Bay to Washington Lake, including such works as 
may be necessary to compensate for or alleviate any 
detrimental salinity conditions resulting from ship channel; 
a triangular basin of equal depth, 2,400 by 2,000 by 3,400 
feet at Washington Lake; and connecting channel 13 feet 
deep and 120 feet wide, with lock and drawbridge, thence to 
Sacramento River. 
CORTE MADERA CREEK, CA 
Levees and channel improvements, lower 11 miles of Corte H. Doc. 545, 87th Cong., 
Madera Creek and tributaries, as modified by Chief of 2d sess. 
Engineers. 
Local cooperation requirements modified to provide 1.5 Sec. 204, 1966 Flood 
percent cash contribution toward cost of Ross Valley unit. Control Act. 
RUSSIAN RIVER BASIN, CA 
Coyote Valley Dam (Lake Mendocino): Channel 
improvements on lower 98 miles of Russian River and 
lower reaches of tributaries. 
Increased appropriation authorization for initial stage of 
project development. 
Dry Creek (Warm Springs) Lake; Channel Improvements 
on Dry Creek below dam. 
Dry Creek (Warm Springs) Lake and channel; compensate 
for fish losses on the Russian River which may be 
attributed to the operation of the Coyote Dam 
component of the project through measures such as 
possible expansion of the capacity of the fish 
hatchery at the Warm Springs Dam component of the 
project. 
SACRAMENTO RIVER AND TRIBUTARIES, CA, 
FROM COLLINSVILLE TO SHASTA DAM 
Modify Sacramento River Flood Control Project to provide 
for extensions in levees and other structures along 
Sacramento River and major and minor tributaries; 
construct Black Butte Dam and Reservoir; construct lowlevel 
Table Mountain Dam and Reservoir with power 
facilities; and provision of monetary authorization of $15 
million for initiation of modification. 
H. Doc. 585, 81st Cong., 
2d sess. 
Public Law 404, 84th 
Cong., 2d sess. 
H. Doc. 547, 87th Cong., 
2d sess. 
Sec. 95, 1974 WRDA 
H. Doc. 649, 78th Cong., 
2d sess. 2 
35-28 
18.

SACRAMENTO, CA, DISTRICT 
TABLE 35-B (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
May 17, 1950 Improvement for protection of Upper Butte Basin (included H. Doc. 367, 81st Cong., 
full monetary authorization). 1st sess. 2 
July 3, 1958 Extend existing Sacramento River Flood Control Project to H. Doc. 272, 84th Cong., 
Keswick Dam for purposes of zoning area below dam and 2d sess.2 
modification of project by construction of bank protection 
and incidental channel improvements between Chico 
Landing and Red Bluff (included full monetary 
authorization). 
July 3, 1958 Additional authorization of $17 million for comprehensive 
plan approved in act of December 22, 1944. 
July 14, 1960 Further modification of Sacramento River Flood Control S. Doc. 103, 80th Cong., 
Project by construction of initial 10-year phase of 2d sess. 2 
bank erosion control works and setback levees on 
Sacramento River and authorization of $14,240,000 for 
prosecution of modification. 
May 12, 1967 Additional authorization of $7 million for bank protection PL 90-17 
approved in act of July 14, 1960. 
Mar. 7, 1974 Initiation of construction of second phase of bank erosion PL 93-251 
control works and setback levees on Sacramento River as 
approved in act of July 14, 1960, and additional 
authorization of $16 million for such purpose.3 
June 19, 1975 Deauthorization of Table Mountain Dam and Reservoir4 H. Doc. 94-192, 94th 
Cong., 1st sess. 
1. Contains latest published map of section above Sacramento. 
For map of section below Sacramento, see H. Doc. 
1123, 60th Cong., 2d sess. and S. Doc. 142, 79th Cong., 2d sess. 
2. Contains latest published map. 
3. Total monetary authorization available, exclusive of 
preauthorization studies from general investigations appropriations, 
amounts to $72,740,000. 
4. The 90-day Congressional project review period, required 
by sec. 12, PL 93-251, as amended by sec. 157, PL 
94-587, ended August 5, 1977, and resulted in deauthorization 
of project unit. 
35-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 35-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Feather River, CA 1951 - 5,7521 2 
Middle River and Connecting 
Channels, CA Completed 1974 8,354s 93,4944 
Mokelumne River, CA Completed 1974 8,500 189,152 
Navajo Reservoir, NM Completed - 2,1325 6 - 
Old River, CA Completed 1970 23,185' 631,128 
Stockton and Mormon Channels, CA Completed 1970 253,1518 218,854 
Suisun Bay Channel, CA Completed 1974 200,928 1o 11 3,316,62212 is 
Suisun Channel, CA Completed 1973 217,677 733,4891s 14 
Suisun Point Channel, CA Completed 1965 191,728s16 - 
1. Maintenance project, channels adequate for commerce. 
2. Includes $10 for maintenance for previous project. 
Excludes $6,160 for previous project and $3,840 for existing 
project for maintenance expended from contributed funds. 
3. Includes $1,600 for previous project. 
4. Includes $790 for previous project. 
5. Authorized by Chief of Engineers under authority of 
sec. 107, Public Law 86-645, as amended. 
6. All costs transferred from Los Angeles District in FY 
1968.
7. Estimated cost to local interests was $3,600 for lands, 
damages, and public landings. 
8. Upon completion of Mormon Slough, Calaveras River, 
CA in February 1970, local interests accepted maintenance 
responsibility for Mormon Slough as well as for Stockton and 
Mormon Channels, CA, and Federal maintenance was discontinued. 
No Federal maintenance costs have been incurred 
since FY 1969. 
9. Includes $58,901 for previous projects. 
10. Excludes $59,551 expended from required contributed 
funds for previous project. 
11. Excludes work accomplished under existing project at 
a cost of $207,198 from Public Works Administration funds 
allotted to San Joaquin River, CA. 
12. Includes $59,817 for previous projects. Excludes $5,449 
expended from required contributed funds for previous 
project. 
13. Maintenance responsibility transferred to San Francisco 
District, January 1, 1974. 
14. Includes reconnaissance and condition surveys of $5,496 
and $483 for fiscal years 1963 and 1964, respectively. 
15. Estimated cost (July 1964) to local interests was 
$12,000 for lands, damages, and spoil retention dikes. 
35-30

SACRAMENTO, CA, DISTRICT 
TABLE 35-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For' Last Cost to Sep 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Alameda Creek, CA 
Alhambra Creek, CA 
American River, CA 
Aquatic Plant Control, CA 
Bear River, CA 
Big Dry Creek Dam and diversion, CA 
Big Wash, Milford, Beaver County, UT 
Burch Creek, Weber County, UT 
Chester, CA 
Coyote Creek, CA 
Duck Creek, San Joaquin County, CA 
East Weaver Creek, CA 
Eel River, CA 
Folsom Lake, American River, CA 
Gleason Creek, NV 
Green Valley Creek, Solano 
County, CA 
Humboldt River and Tributaries, NV 
Kays Creek, UT 
Kern River-California Aqueduct 
Intertie, CA 
Klamath River, CA 
Lake Camanche, CA 
Lake Oroville, CA 
Lakeport Lake, CA 
Lower San Joaquin River and 
Tributaries, including Tuolumne 
and Stanislaus Rivers, CA 
Mad River Basin, CA 
Marysville Lake, CA 
Merced River, CA 
Middle Creek, CA 
Mormon Slough, CA 
Napa River Basin, CA 
New Bullards Bar, CA 
North Fork, Pit River at Alturas, CA 
Pinole Creek, CA 
Redwood Creek, Humboldt County, CA 
Reese River, Battle Mountain, N.V 
Rheem Creek, CA 
Rodeo Creek, CA 
Salinas River, CA 
Salt Lake City, Jordan River, UT 
San Leandro Creek, CA 
San Lorenzo Creek, CA 
San Lorenzo River, CA 
Sevier River near Redmond, UT 
Sonoma Creek, CA 
Truckee River and tributaries, 
CA and NV 
Completed 
Inactive 
Completed 
Completed 
Inactive 
Completed 
Completed 
Active/no FY 86 
expenditure 
Completed 
Completed 
Completed 
Inactive 
Completed 
Deferred 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Inactive 
Active/no FY 86 
expenditure 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Active/no FY 86 
expenditure 
1978 
1981 
1959 
1967 
1980 
1955 
1961 
1964 
1981 
1968 
1967 
1965 
1971 
1967 
1977 
1963 
1982 
1973 
1977 
1972 
1976 
1981 
1976 
1976 
1973 
1980 
1976 
1967 
1976 
1979 
1972 
1974 
1968 
1970 
1969 
1962 
1966 
1952 
1961 
1973 
1962 
1966 
1952 
1973 
1968 
26,995,350 
300,0001 s 
2,125,8184 
1,000 
_b 
1,369,9316 
217,8797 8 
26,0497 
3,570,0009 
705,6221 7 
664,8257 10 
220,6361 711 
1,272,8161 12 
63,014,810's 
215,8261' 
136,0267 's 
1,532,93216 
407,9897 17 
1,503,0737 18 
4,838,0001 
10,252,95019 
70,425,47020 
2,353,00321 
27,835,2632 
4,243,7501 23 
_24 
10,918,79626 
2,643,49926 
2,965,40227 
2,639,9551 
12,890,62528 
904,2787 29 30 
885,7501 7 
4,620,0701 31 
133,3397 32 
400,0001 7 33 
974,1001 7 
94,2131 34 
1,227,57035 
1,000,0001 36 
5,130,8211 37 
4,314,4061 38 
919,00039 
781,5001 40 
1,038,960 
35-31 
54,7781 2

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
1. Project responsibility transferred from San Francisco 
District to Sacramento District April 1, 1982. 
2. Scheduling of reservoir operations costs. 
3. Project classified as "inactive" January 19, 1982. 
4. Excludes $54,919 other contributed funds for miscellaneous 
construction for local interests pursuant to requirements 
of local cooperation. Total costs for all requirements of 
local cooperation were $951,000 (1959) for lands and relocations. 
5. Due to infeasibility, Bear River Phase I study was 
suspended and project classified as "inactive" on November 6, 
1981.
6. Excludes $44,008 other contributed funds for construction 
in connection with bridge construction pursuant to 
requirements of local cooperation. Total cost to local interests 
for all requirements of local cooperation was $370,000 (1959) 
for lands and relocations. 
7. Authorized by Chief of Engineers under authority of 
sec. 205 Public Law 80-858, as amended. 
8. Excludes $22,000 for preauthorization studies. 
9. Excludes $69,262 other contributed funds from State 
of California for two low water crossings and appurtenances 
at Chester. 
10. Excludes $50,000 for preauthorization studies. Estimated 
costs to local interests were $665,000 for lands and 
damages including relocations. 
11. Includes $174,938 Public Works Acceleration Program 
Funds. 
12. Excludes $194,821 contributed funds and placed inactive 
1973. 
13. Transferred to Bureau of Reclamation in May 1956 for 
operation and maintenance by that agency in conjunction 
with other units of Central Valley project. Project prevented 
an estimated $4,700,000,000 in damages from the February- 
March 1986 rainfloods. 
14. Due to lack of local support, Gleason Creek project was 
reclassified as "deferred" on November 3, 1977. Fiscal year 
1978 carryover funds of $27,984 were revoked. 
15. Excludes $20,000 for preauthorization studies. 
16. Vista and Devils Gate reservoirs and channel improvements 
were classified "inactive" on January 12, 1982, and 
Hylton reservoir was classified "inactive" on March 21, 1983, 
due to lack of economic feasibility. 
17. Includes $30,000 for preauthorization studies. Estimated 
costs (FY 1973) to local interests for all requirements of 
local cooperation were $150,117 for lands and damages 
including relocations. 
18. Includes $73,000 for preauthorization studies. Non- 
Federal (Kern County Water Agency) cost for road relocation 
was $18,260 (required contributed funds).. 
19. Constructed by East Bay Municipal Utility District. 
Final Federal contribution of $51,202 made July 18, 1978 
(total $10,111,684). Non-Federal costs $24,876,842. 
20. Constructed by State of California. Final Federal 
contribution of $64,186 was made on February 9, 1981 (total 
$69,994,015) for flood control reservation. Project prevented 
an estimated $262,800,000 in damages from the February- 
March 1986 rainfloods. 
21. Preconstruction planning complete. Necessary reaffirmation 
of local cooperation assurances by Lake County 
Flood Control and Water Conservation District not received. 
Project was reclassified as "deferred" on September 15, 1977. 
Includes $298,500 costs for advance acquisition of land, 
Public Law 91-439. 
22. Cherry Valley and New Don Pedro Reservoirs constructed 
by local interests. Federal contributions of $9,000,000 
and $5,464,000, respectively, for flood control reservation. 
Final Federal contribution of $308,898 was made on January 
18, 1972, for New Don Pedro. Excludes $3,004,946, 
contributed funds, other, for miscellaneous engineering and 
construction (non-project) at local interests expense under 
local cooperation requirements for acquisition of rights-ofway 
for levee and channel improvements on Lower San 
Joaquin River and tributaries. 
23. Placed inactive 1974. Excludes $225,000 applicable to 
Public Works Acceleration Program and $162,761 previous 
project Blue Lake levee. 
24. Planning and any future development is uncertain 
awaiting State of California's position on support of Marysville 
project. 
25. Constructed by Merced Irrigation District. Final 
Federal contribution of $839 was made December 2, 1975 
(total $10,818,638) for flood control reservation. 
26. Estimated cost's (FY 1967) to local interests for all 
requirements of local cooperation were $1,340,000 for lands 
and' damages including relocations. 
27. Non-Federal cost $2,965,402 (FY 1976) for lands and 
relocations. Federal contribution of $599,336 made to State 
Reclamation Board. 
28. Constructed by Yuba County Water Agency. Final 
Federal contribution of $33,470 was made in FY 1972 (total 
$12,759 127) for flood control reservation. 
29. includes $41,800 for preauthorization studies. 
30. Excludes $146,000 other contributed funds for miscellaneous 
construction and engineering and design services 
under local cooperation requirements in connection with 
acquisition of rights-of-way, relocation, and utility alterations. 
31. Includes $107,000 costs for remedial work to drainage 
system completed in FY 1977. 
32. Includes $19,000 for preauthorization studies. 
33. Excludes $52,549 contributed funds. 
34. Cost includes engineering and design prior to June 30, 
1952 and costs of $4,288 FY 1962 and 1963 to determine if 
project'classification to an active category was justified. 
35. Estimated costs to local interests for all requirements 
of local cooperation were $463,000 (July 1962) for lands and 
damages including relocations. Project prevented $2,300,000 
in damages from May-July 1986 snowmelt runoff. 
36. Excludes $285,329 contributed funds. 
37. Excludes $200,000 estimated value of work performed 
in lieu of cash contribution. 
38. Excludes $421,182 contributed funds. 
39. Excludes $48,000 required contributed funds toward 
first cost. Costs to local interests for all requirements of local 
cooperation, including required contributions, were $118,000 
(1951). 
40. Placed inactive 1974. 
35-32

SACRAMENTO, CA, DISTRICT 
TABLE 35-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Little Valley Wash, Magna, UT 1951 1977 - 
Spanish Fork River, UT 1955 1977 20,000 
Weber River and Tributaries, UT 1974 1972 75,120 
(Morgan County) 
TABLE 35-H SACRAMENTO RIVER, CA: 
TIDAL AND FLOOD CONDITIONS PREVAILING 
(See Section 1 of Text) 
Miles from Range in Feet 
Mouth of Mean Extreme Ordinary Extreme 
Place River Tidal' Tidal Floods Flood' 
Collinsville 0 4.3 7 8 10 
Sacramento 59 2.02 3 20 28 
Veropa (Mouth of Feather River) 80 - Trace 22 30 
Colusa 144 - - 26 32 
Chico Landing 193 - - 20 25 
Red Bluff 248 - - 24 30 
1. Mean lower low water to mean higher high water. 3. Mean lower low water to flood stage. 
2. Tide at low water season only. 4. Extreme low water to indicated flood condition. 
TABLE 35-I SAN JOAQUIN RIVER, CA: 
TOTAL COST OF NEW WORK FOR PROJECT1 
(See Section 4 of Text) 
Federal Non-Federal2 
Corps of Coast Required Lands and 
Engineers Guard Cash Damages (includ- Total 
Modification (Construction) (Construction) Contribution ing Relocations) Total Project 
Prior to 1950 Modification $4,009,938 $80,000 $1,307,500 $1,042,000 $2,349,500 $6,439,438 
1950 Modification 1,823,179 - 35,000 135,000 170,000 1,993,179 
Total $5,833,117 $80,000 $1,342,500 $1,177,000 $2,519,500 $8,432,617 
1. Completed in May 1960. 
2. Excludes $5,865,000 (Feb. 1954) local interests costs 
for Stockton Deep Water Channel terminal facilities required 
under terms of project authorization. 
35-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 35-J SAN JOAQUIN RIVER, CA: 
PROJECT UNITS (1950 MODIFICATION) RECLASSIFIED AND EXCLUDED 
FROM PROJECT COST 
(See Section 4 of Text)
Non-Federal 
Federal Required Lands and 
Corps of Cash Damages (includ- Total 
Unit Engineers Contribution ing Relocations) Total Project 
Settling Basin above head of Burns 
Cutoff $1,073,000 $ 30,000 $ 200,000 $ 230,000 $1,303,000 
Burns Cutoff improvement; new 
turning basin; dredging Mormon 
Channel2 7,882,0009 431,000 1,455,000 1,886,000 9,768,000 
Upper Stockton Channel enlargement* 535,000 34,000 15,000 49,000 584,000 
1. July 1959 price index. Deauthorized August 5, 1977. 4. Deleted by 1965 River and Harbor Act authorization 
2. Deferred; July 1960 price index, of San Francisco Bay to Stockton Channel, Sacramento 
3. For lands and construction. District, Improvement No. 3. 
TABLE 35-K MERCED COUNTY STREAM GROUP, CA, 
MAXIMUM INFLOW, STORAGE, AND OUTFLOW FOR PROJECTS 
(See Section 16 of Text) 
Maximum 
Inflow Maximum Maximum 
(c.f.s.) Storage Outflow 
Stream (bihourly) (acre-feet) (c.f.s.) 
Burns 2,100 440 1,350 
Bear 3,600 1,840 1,430 
Owens 1,200 1,220 145 
Mariposa 6,500 12,260 1,070 
TABLE 35-L RUSSIAN RIVER BASIN, CA: ESTIMATED 
COST FOR NEW WORK 
(See Section 18 of Text)
Estimated Cost 
Non-Federal 
Project Feature Federal Contribution Total 
Coyote Valley Dam (Lake Mendoc o); 
Channel Improvements below Dam 
on lower 98 miles of Russian River $ 14,436,000 $ 5,598,000 $ 20,034,0001 
Dry Creek (Warm Springs) Lake; Channel 
Improvements below Dam 246,600,000 100,290,0002 346,890,000 
Total $261,036,000 $105,888,000 $366,924,000 
1. Exclusive of $1,628,000 for recreation facilities at 
completed projects. 
2. Reimbursement by local interests to Federal Government 
for costs allocated to water supply storage to be paid 
over a period not to exceed 50 years after use of storage is 
initiated and exclusive of lands and damages. 
35-34

SACRAMENTO, CA, DISTRICT 
TABLE 35-M RUSSIAN RIVER BASIN, CA: PROJECT 
FEATURES AND ESTIMATED COSTS 
(See Section 18 of Text) 
Height of Reservoir 
Nearest City Distance Dam and Capacity Estimated 
Name (California) Above Mouth Type (Acre-Ft) Cost 
Coyote Valley Dam (Lake Ukiah Mile 0.8-East Fork 160 Feet-Earthfill 122,500 $ 17,550,0001 
Mendocino) of Russian River 
Channel Improvement (East Fork Ukiah Mile 0 to 0.8 East - - 2,484,000 
Fork 
below Coyote Valley Dam and Guerneville Mile 0 to 98, Russian 
lower 98 miles of Russian River) River 
Dry Creek (Warm Springs) Lake Healdsburg Mile 14.4 Dry Creek 319 Feet-Earthfil! 381,000 340,600,000 
Channel Improvement (Dry Creek) Healdsburg Mile 1 to 14.4 Dry - - 5,400,000 
below Dry Creek (Warm Springs Creek 
Dam) 
1. Exclusive of $1,628,000 for recreation facilities at 
completed projects. 
TABLE 35-N SACRAMENTO RIVER AND TRIBUTARIES, CA, 
COLLINSVILLE TO SHASTA DAM: 
PROJECT UNITS RECLASSIFIED AND EXCLUDED FROM COST ESTIMATE 
(See Section 19 of Text) 
Current Estimated Cost 
Unit Classification Federal Non-Federal' Total 
1944 Modification: 
Antelope Creek2 Inactive $1,400,000 $ 340,000 $1,740,000 
Lower Butte Basin3 Deferred 7,286,000 2,285,000 9,571,000 
Thomes Creek2 Deferred 1,140,000 140,000 1,280,000 
Willow Creek2 Inactive 1,290,000 120,000 1,410,000 
Bypass Levees Deferred 7,100,000 940,000 8,040,000 
Bypass Levees' Inactive 3,010,000 - 3,010,000 
1950 Modification: 
Upper Butte Basin2 Deferred 3,530,000 1,787,000 5,317,000 
1. For lands and damages, including relocations. 
2. July 1960 price level. 
3. Excludes work applicable to extension of Moulton 
weir (July 1954 price level). 
4. July 1961 price level. 
35-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 35-0 SACRAMENTO RIVER AND TRIBUTARIES, CA, 
FROM COLLINSVILLE TO SHASTA DAM: 
CONSTRUCTION ACCOMPLISHED AND CONTRACT COSTS 
(See Section 19 of Text) 
Required 
Contract Federal Contributed Total 
Contract 37 completion (Bank protection, 
selected sites, Sacramento River and 
Sloughs, downstream from Sacramento) $585,139 $284,219 $869,358 
Contract 38A completion (Bank protection, 
selected sites, Sacramento River, 
miles 80.0-193.0) 260,293 403,353 663,646 
Contract 38B initiation (Bank protection, 
selected sites, Sacramento River, 
miles 62.6-117.7) 657,925 657,925 
Contract 39 continuation (Bank protection, 
selected sites, Sacramento River, 
miles 178.0-189.0) 601,420 1,233,882 1,835,302 
Contract 40A initiation (Bank protection, 
selected sites, Sacramento River, 
miles 132.4-179.5) 250,000 250,000 
35-36

PACIFIC OCEAN DIVISION 
This division comprises the State of Hawaii. The division 
also performs such actions pertaining to preservation and 
protection of navigable waters on and about the island of 
Guam and Amercian Samoa as provided for under River and 
Harbor Act of 1899, and the Commonwealth of the Northern 
Mariana Islands as provided for under Public Law 94-241 
(H.J. Res 549) (March 24, 1976). 
IMPROVEMENTS 
Navigation 
1. Agat Harbor, Territory of Guam.......... . 
2. Barbers Point Harbor, Oahu, Hawaii....... 
3. Kaulana Bay Boat Harbor, 
Hawaii, Hawaii ........................ 
4. Manele Bay Small Boat Harbor, 
Lanai, Hawaii .......................... 
5. Nawiliwili Harbor, Kauai, Hawaii.......... 
6. Reconnaissance and Condition Surveys ..... 
7. Navigation Work Under Special 
Authorization .......................... 
Beach Erosion Control 
8. Aquatic Plant Control ................... 
9. Asquiroga Bay, Territory of Guam......... 
10. Ofu Airstrip, American Samoa............ 
11. Beach Erosion Work Under Special 
Authorization .......................... 
Flood Control 
12. Asan Village, Territory of Guam........... 
13. Kahoma Stream, Maui, Hawaii............ 
14. Waimea River, Kauai, Hawaii............. 
15. Flood Control Work Under Special 
Authorization .......................... 
Page 
36-1 
36-2 
36-2 
36-2 
36-3 
36-3 
36-3 
36-3 
36-3 
36-3 
36-3 
36-4 
36-4 
36-4 
36-4 
Flood Control (Cont.) 
16. Inspection of Completed Flood 
Control Projects ........................ 
17. Inspection of Completed PL-99 Works ...... 
Multiple-Purpose Projects, Including Power 
18. Nanpil River Hydropower, Pohnpei, 
Trust Territory of the Pacific Islands ....... 
General Investigations 
19. Surveys.......... .................... 
20. Collection and Study of Basic Data........ 
Tables 
Table 36-A Cost and Financial Statement ..... 
Table 36-B Authorizing Legislation ........... 
Table 36-C Other Authorized Navigation 
Projects...................... 
Table 36-D Other Authorized Beach 
Erosion Control Projects .......... 
Table 36-E Other Authorized Flood 
Control Projects ................. 
Table 36-F Not Applicable 
Table 36-G Deauthorized Projects ............ 
Navigation 
1. AGAT HARBOR, 
TERRITORY OF GUAM 
Location. On the southwestern coast of the island of 
Guam, about 3,318 miles west of Honolulu, Hawaii. (See 
NOAA Chart 81408.) 
Existing project. Project provides for dredging an entrance 
channel 14 feet deep and 1,000 feet long, an 11 foot 
deep turning basin, an access channel 9 feet deep and 500 
feet long, and constructing a 300-foot revetted mole and two 
breakwaters, a total of 1,100 feet long. The project also pro- 
36-1 
vides berthing space for 150 boats, a two-lane launch ramp 
and parking, and a shoreside facilities area. Estimated total 
project cost is $4,113,000 for which Federal cost is 
$2,026,000 (including $26,000 in U.S. Coast Guard cost) and 
non-Federal cost of $2,087,000. Project authority is Section 
107 of the River and Harbor Act of 1960, as amended. Project 
was authorized for construction in June 1986. 
Local cooperation. Local interests have agreed to: 
(a) Provide without cost to the United States all lands, 
easements, and rights-of-way required for construction of 
the project. 
Page 
36-4 
36-5 
36-5 
36-5 
36-5 
36-6 
36-7 
36-8 
36-10 
36-11 
36-12

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
(b) Provide without cost to the United States an area suitable 
to the Chief of Engineers for the disposal of spoils and, 
if necessary, retaining dikes, bulkheads, and embankments 
or the cost of such work, currently estimated to be $398,000. 
(c) Provide and maintain without cost to the United States 
the necessary pier and docking facilities, as well as all 
appropriate onshore structures, access roadways, utilities, 
parking areas, restrooms, and launching facilities to insure 
a complete and adequate project. These facilities must be 
open to all on equal terms. 
(d) Accomplish without cost to the United States the necessary 
alterations and relocations of all utilities as necessary 
for project purposes. 
(e) Hold and save the United States free from claims for 
damages due to the construction work and subsequent maintenance 
of the project, excluding damages due to fault or 
negligence of the United States or its Contractor. 
(f) Provide a cash contribution based on a percentage to be 
determined by final benefit and cost allocation analysis of 
the total Corps of Engineers first cost of project before 
apportionment. In addition, local interest must provide all 
cost in excess of the two million dollar statutory Federal 
limitation under Section 107 of the River and Harbor Act 
of 1960, as amended. The cash contribution is currently 
estimated to be $1,295,000. 
(g) In addition to the cash contribution for the project 
referenced in f. (above), Guam will provide to the Corps 
prior to commencement of project construction sufficient 
funds to cover the costs of the dredging of the berthing 
area. Costs for dredging the berthing area are currently estimated 
to be $426,000. 
(h) Create and construct at least 150 berths (boat slips), determined 
necessary in the Detailed Project Report, within 
3 years from completion of the Corps' project. 
(i) Fulfill the requirements of non-Federal cooperation 
as may be required by the Uniform Relocation Assistance 
and Real Property Policies Act of 1970 (Public Law 91-646), 
as amended. 
(j) Comply with Title VI of the Civil Rights Act of 1964 (Public 
Law 88-352), as amended. 
Terminal facilities. None. 
Operations during fiscal year. New Work: Plans and 
specifications were completed in May 1986. A construction 
contract is scheduled for award in October 1986. 
2. BARBERS POINT HARBOR, 
OAHU, HAWAII 
Location. On the west coast of Oahu, about 25 miles from 
metropolitan Honolulu. (See Coast and Goedetic Survey 
Charts 4110 and 4133.) 
Existing project. For description of existing project, 
see page 36-1 of FY84 Annual Report. Total project cost 
estimate is $63,600,000 of which Federal cost is $55,300,000 
(including $372,500 in U.S. Coast Guard cost) and non- 
Federal cost is $8,300,000 including lands and rights-of-way 
and cash contribution of $2,500,000. (See Thble 36-B for 
Authorizing Legislation.) 
Local cooperation. Requirements are described in full 
on page 36-1 of FY85 Annual Report. 
Terminal facilities. See page 36-2 of FY84 Annual 
Report. 
Operations during fiscal year. New Work: A construction 
contract awarded in March 1982 was completed in August 
1985. The contract cost, including claim payment made 
in January 1985 to the contractor, was $56,833,154 of which 
Federal cost is $52,104,660 (including $320,000 in U.S. Coast 
Guard cost) and non-Federal cost is $4,728,494. Work remaining 
to be completed includes project beautification and 
stockpile plantings estimated at $1,348,000. Remaining work 
is scheduled for completion in April 1989. Maintenance: 
Annual operational cost for the Regional Visitor Center 
located at Fort DeRussy was $53,921. 
3. KAULANA BAY BOAT HARBOR, 
HAWAII, HAWAII 
Location. On the southern tip of the island of Hawaii in 
the Ka'u Judicial District about 80 road miles southwest of 
the city of Hilo. (See NOAA Chart 19320.) 
Existing project. See page 36-2 of FY84 Annual Report. 
Local cooperation. Requirements are described in full 
on page 36-3 of FY82 Annual Report. 
Terminal facilities. There is an existing boat launching 
ramp owned by the State of Hawaii and open to all on 
equal basis. 
Operations during fiscal year. New Work: Favorable 
constructions bids were received in September 1983 
and a lawsuit filed in October 1983 for permanent injunction 
to enjoin construction contract award and negate lease 
agreement. A settlement agreement was signed by plaintiffs 
on May 30, 1984 removing the Corps from the suit. 
The project real estate is the subject of a State suit. The 
construction contract has been cancelled and further action 
on the project deferred. 
4. MANELE BAY SMALL BOAT HARBOR, 
LANAI, HAWAII 
Location. On the southern coast of the island of Lanai 
about 6 miles south of Lanai City. (See Coast and Geodetic 
Survey Chart 4130.) 
Existing project. Project provides for extension of 
an existing 100-foot long stub breakwater with a 470-foot 
rubblemound breakwater with crest elevation of 14 feet 
at the head and 6 feet at the root; an entrance channel 
12 feet deep, and main access channel and maneuvering 
areas 8 feet deep. The tidal range between mean lower low 
water and mean higher high water is 1.8 feet. Total project 
cost for maintenance dredging is $240,000 in Federal cost. 
Project authority is Section 107 of the 1960 River and 
Harbor Act, as amended. 
Local cooperation. Fully complied with. 
Terminal facilities. Shoreside facilities provided by the 
State of Hawaii include berths, sanitary facilities, launch 
ramp and parking areas. 
Operations during fiscal year. Maintenance: A maintenance 
dredging contract awarded in September 1985 was 
completed in December 1985 for $204,827. 
36-2

PACIFIC OCEAN DIVISION 
5. NAWILIWILI HARBOR, 
KAUAI, HAWAII 
Location. On the southwest coast of the island of Kauai 
and about 100 nautical miles northwest of Honolulu. (See 
NOAA Chart 19383.) 
Existing project. For description of existing project, see 
page 36-3 of FY84 Annual Report. Estimated total project 
cost for breakwater repair is $3,967,400 in Federal cost. (See 
Thble 36-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. See page 36-3 of FY84 Annual 
Report. 
Operations during fiscal year. Maintenance: Plans and 
specifications were completed in February 1986. A construction 
contract for repair of the breakwater was awarded in 
May 1986 for $3,303,000 with completion scheduled in 
August 1987. 
6. RECONNAISSANCE AND CONDITION 
SURVEYS 
Condition surveys were conducted on Honolulu Harbor, 
Oahu, in September 1986 for $24,732; Kahului Harbor, Maui, 
in September 1986 for $17,335; Nawiliwili Deep Draft Harbor, 
Kauai, in August 1986 for $16,112 and Nawiliwili Small 
Boat Harbor, Kauai, in August 1986 for $8,675. 
7. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645. 
Preauthorization studies were continued on Merizo Harbor, 
Guam, $4,722; East Molokai, Molokai, $48,720; and 
Kahului Small Boat Harbor, Maui, $40,011; completed on 
Pala Lagoon, American Samoa, $10,000; and terminated on 
Kahana Bay, Oahu, $24,999. Plans and specifications were 
initiated on Laupahoehoe Harbor, Hawaii, $76,793. 
Beach Erosion Control 
8. AQUATIC PLANT CONTROL 
Location. The program was conducted in streams, 
drainage channels, aquatic recreation areas, and other 
waters in the Hawaiian Islands. 
Existing project. The purpose of the program was to 
conduct reconnaissance investigations to evaluate aquatic 
plant control to determine whether Federal involvement was 
justified for the control of the water hyacinth and other 
aquatic plants. 
Operations during fiscal year. A contract was awarded 
in September 1985 and completed in April 1986 for 
$4,400. The report concluded that the aquatic plant control 
problems were not of a Federal interest. 
9. ASQUIROGA BAY, TERRITORY 
OF GUAM 
Location. On the southeastern shore of the island of 
Guam, about 3,318 miles west of Honolulu, Hawaii. (See 
NOAA Chart 81408.) 
Existing project. Project provides for a 275 foot rock 
revetment with a crest elevation + 14.0 feet MLLW with a 
slope of 1V on 1.5H. Total project cost is $227,181 in Federal 
cost. Project authority is Section 14 of the 1946 Flood Control 
Act, as amended. Project was approved for construction 
in August 1980. 
Local cooperation. Requirements are described in full 
on page 36-4 of FY83 Annual Report. 
Operations during fiscal year. New Work: A construction 
contract awarded in February 1985 was completed in 
December 1985 for $180,569. 
10. OFU AIRSTRIP, AMERICAN SAMOA 
Location. On the southern end of the island of Ofu, about 
2,300 miles southwest of Honolulu, Hawaii. (See Coast and 
Geodetic Survey Chart 4190, Manu Islands.) 
Existing project. Project provides for a 380 foot long rock 
revetment using two layers of 1,300 to 2,100 pound stones 
on a 2 foot thick underlayer/filter cloth. Estimated total 
project cost is $220,000 in Federal cost. Project authority 
is Section 14 of the Flood Control Act of 1946, as amended. 
Project was approved for construction in May 1986. 
Local cooperation. Local interests will be required to: 
(a) Provide without cost to the United States all lands, easements, 
rights-of-way, and relocations required for Project 
construction. 
(b) Hold and save the United States free from claims for 
damages which may result from construction and subsequent 
maintenance of the Project, except damages due to 
the fault or negligence of the United States or its contractors. 
(c) Assure continued condition of public ownership and use 
of the shore upon which the amount of Federal participation 
is based during the economic life of the Project. 
(d) Assure maintenance and repair during the economic life 
of the Project as required to serve the intended purposes. 
(e) Comply with the provisions of the Uniform Relocation 
Assistance and Real Property Acquisition Policies Act of 1970 
(Public Law 91-646). 
(f) Comply with Title VI of the Civil Rights Act of 1964 (Public 
Law 88-352). 
(g) Assume full responsibility for all Project costs in excess 
of the Federal cost limitation of $250,000. 
Operations during fiscal year. New Work: A construction 
contract was awarded in August 1986 for $149,000 with 
completion scheduled in November 1986. Construction has 
not been initiated as of September 30, 1986. 
11. BEACH EROSION WORK UNDER SPECIAL 
AUTHORIZATION 
Emergency streambank and shoreline protection activities 
pursuant to Section 14, Public Law 79-526. 
Preauthorization study was terminated on Waiehu Beach 
Park, Maui, $15,000. 
Beach erosion control activities pursuant to Section 103, 
Public Law 87-874. 
Preauthorization studies were continued on Masefau Bay, 
American Samoa, $2,500; completed on Lepua Area, American 
Samoa, $23,067; Poipu Beach Park, Kauai, $7,500, and 
36-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
terminated on Makaha Beach Park, Oahu, $42,833. Plans 
and specifications were terminated on Sand Island Shore 
Protection, Oahu, $6,062. 
Flood Control 
12. ASAN VILLAGE, TERRITORY 
OF GUAM 
Location. On the west central coastal area of the island 
of Guam and about 2.5 miles east of Agana, the capital of 
Guam. The island of Guam is approximately 3,318 miles 
west of Honolulu, Hawaii, and 1,300 miles south of Tokyo, 
Japan. (See NOAA Chart 81048.) 
Existing project. For description of existing project, see 
page 36-4 of FY84 Annual Report. Total project cost is 
$1,901,134 of which Federal cost is $1,275,500 and non- 
Federal cost is $625,634. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New Work: A construction 
contract awarded in September 1983 was completed in 
December 1985 for $1,401,247. A construction deficiency 
reported in August 1984 was settled in November 1985 for 
$29,500. 
13. KAHOMA STREAM, MAUI, HAWAII 
Location. Kahoma Stream drainage basin is located in 
Lahaina, Maui. Lahaina is on the west coast of Maui about 
4 miles from Kaanapali. The drainage basin of Kahoma 
Stream totals 5.3 square miles. (See NOAA Chart 19348.) 
Existing project. For description of existing project, see 
page 36-5 of FY84 Annual Report. Total project cost estimate 
(October 1986) is $17,200,000 of which Federal cost is 
$10,840,000 and non-Federal cost is $5,500,000 for lands, 
damages, relocations, and cash contributions ($860,000). 
(See Table 36-B for Authorizing Legislation.) 
Local cooperation. 
(a) The County shall provide, during the period of 
construction, not less than 25 percent of total project 
costs, such percentage to include the value of all lands, 
easements, rights-of-way, and utility and facility alterations 
and relocations required for construction of the project, 
as well as a cash payment of not less than 5 percent of total 
project costs. 
(b) The Government, using funds provided by the County 
and appropriated by the Congress, shall expeditiously 
construct the Project, applying those procedures usually 
followed or applied in Federal projects, pursuant to Federal 
laws, regulations, and policies. Award of Federal contracts 
and the work thereunder shall be exclusively within the 
control of the Government. 
(c) Upon completion of project construction, the Government 
shall turn the project over to the County who shall be 
solely responsible for operating, maintaining, and 
rehabilitating the project. 
(d) No less than once each year the County shall inform 
affected interests regarding the limitations of the protection 
afforded by the project. 
(e) The County shall publicize floodplain information in the 
area concerned and shall provide this information to zoning 
and other regulatory agencies for their guidance and 
leadership in preventing unwise future development in the 
floodplain and in adopting such regulations as may be 
necessary to prevent unwise development in the floodplain 
and in adopting such regulations as may be necessary to 
ensure compatibility between future development and 
protection levels provided by the project. 
(f) The County shall, to the extent of its powers, prescribe 
and enforce regulations to prevent obstruction of or 
encroachment on the project that would reduce the level of 
protection it affords or that would hinder operation and 
maintenance. 
Operations during fiscal year. New Work: Local 
Cooperation Agreement was executed in June 1986. A 
construction contract was awarded in September 1986 for 
$12,180,000 with completion scheduled in July 1989. 
14. WAIMEA RIVER, KAUAI, HAWAII 
Location. On the west-central portion of the island of 
Kauai which is about 103 statute miles northwest of 
Honolulu. (See NOAA Chart 19381.) 
Existing project. Project provides for 3,320 feet of 
concrete rubble masonry floodwall on existing levee, 4,600 
feet of rock toe protection, 500 feet of road raise 1,030 
feet of levee extension, 335 feet of concrete wall, new 
floodgates and a flood warning system. Estimated total 
project cost is $3,272,400 of which Federal cost is 
$3,212,400 and non-Federal cost is $60,000 for the flood 
warning system. Project authority is Section 205 of the 
Flood Control Act of 1948, as amended. Project was 
authorized for construction in May 1983. Construction funds 
were alloted under the Jobs Bill Program. 
Local cooperation. Requirements are described in full 
on page 36-8 of FY82 Annual Report. 
Operations during fiscal year. New Work: A 
construction contract awarded in September 1983 was 
completed in December 1984 for $2,467,005. Flood warning 
system, estimated at $300,000, remains to be completed 
upon receipt of non-Federal funds. 
15. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, Public 
Law 80-858. 
Preauthorization studies were continued on Garapan Area, 
Northern Marianas, $16,492; completed on Kahawainui 
Stream, Oahu, $9,033; Lake Susupe, Northern Marianas, 
$6,223; and terminated on Honaunau Area, Hawaii, 
$10,447. Plans and specifications were initiated on 
Kahawainui Stream, Oahu, $110,486. 
Federal cost during fiscal year for Flood Control and 
Coastal Emergencies appropriation was $169,099 for disaster 
preparedness. 
16. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Inspections were conducted on Asan River, Guam, in 
November 1985 and June 1986; Hanapepe River, Kauai, in 
November 1985; Iao Stream, Maui, in December 1985; 
36-4

PACIFIC OCEAN DIVISION 
Kaneohe-Kailua Dam in October 1985; Kawainui Swamp, 
Oahu, Kaunakakai Stream, Molokai, and Kuliouou Stream, 
Oahu, in December 1985; Namo River, Guam, in November 
1985 and June 1986; Paauau Stream, Hawaii, in 
December 1985; Wailoa Stream, Hawaii, in December 1985; 
and Waimea River, Kauai, in November 1985 for a total cost 
of $8,831. 
17. INSPECTION OF COMPLETED 
PL-99 WORKS 
Inspections were conducted at Hahaione Stream, Kapakahi 
Stream, Kapalama Stream, Moanalua Stream, Niu Stream, 
Omao Stream, Pearl City Channel, Waialae-Iki Stream and 
Waialae-Nui Stream, all on the Island of Oahu, during July 
1986 for a total cost of $2,478. 
Multiple-Purpose Projects Including Power 
18. NANPIL RIVER HYDROPOWER, 
POHNPEI, TRUST TERRITORY OF 
THE PACIFIC ISLANDS 
Location. Nanpil River is located on the island of Pohnpei 
in the Federated States of Micronesia, Trust Territory 
of the Pacific Islands. (See State of Hawaii, the New Pacific 
map.) 
Existing project. See page 36-4 of FY85 Annual Report. 
(See 'Table 36-B for Authorizing Legislation.) 
Local cooperation. Requirements are described in full 
on Page 36-5 of FY85 Annual Report. 
Operations during fiscal year. A construction contract 
for $5,622,000 was awarded in October 1985 with completion 
scheduled in December 1987. A contract to operate and 
maintain the project for a one-year period to October 1988 
is incorporated in the work to be done. Construction is approximately 
31% complete as of September 30, 1986. 
General Investigations 
19. SURVEYS 
Fiscal year costs were $679,090 of which $323,936 was 
for navigation studies, $120,129 for flood damage prevention 
studies, $14,995 for review of authorized projects, 
$57,012 for miscellaneous activities, and $163,018 for coordination 
with other agencies. 
20. COLLECTION AND STUDY OF 
BASIC DATA 
Flood plain management services. Flood Plain 
Management Services Program comes under Section 206, 
PL 86-645, 1960 Flood Control Act, as amended. Through 
technical services and planning guidance, the program provides 
information on floods and flood related information 
to improve planning for the careful use of the nation's flood 
plains, thereby reducing the potential for losses to life and 
property from floods and wave actions. Federal and nonfederal 
agencies and the Private sector are assisted with 
flood hazard evaluation and planning information for flood 
and coastal hazard areas. This assistance is in the form of 
local flood plain regulations, National Flood Insurance requirements, 
and Executive Order 11988 requirements for 
federal agencies. Such assistance may include flood information 
and timing, flood-water velocity, extent of flooding, 
duration of flooding, flood frequency and regulatory floodway 
limits. 
Services accomplished during fiscal year. Requests 
and responses for technical services and planning assistance 
totaled 648. Of this total, 73 were from other federal agencies, 
283 from non-federal agencies, and 292 from individuals, 
realtors, corporations, lending institutions, engineers, 
architects and others. Of the 648 requests, assistance resulted 
in 2,560 site specific responses. A hurricane vulnerability 
study initiated in September 1983 for the State of Hawaii 
was completed in January 1986 at a total cost of $140,000 
non-Federal funds. A hurricane wind strength study was 
initiated in February 1986 and completed in September 1986 
for the State of Hawaii at a total cost of $30,000. Costs for 
Providing Flood Plain Management services during fiscal 
year were $221,738. 
Hydrologic Studies. Storm studies cost was $5,002. 
Total costs for collection and study of basic data during 
the fiscal year were $226,740. 
36-5

TABLE 36-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATMENT 
Project 
Agat Harbor Territory of 
Guam (Federal Funds) 
2. Barbers Point Harbor, 
Oahu, Hawaii 
(Federal Funds) 
(Contributed Funds) 
3. Kaulana Bay Boat 
Harbor, Hawaii, Hawaii 
(Federal Funds) 
4. Manele Bay Small Boat 
Harbor, Lanai, Hawaii 
(Federal Funds) 
(Contributed Funds) 
5. Nawiliwili Harbor, 
Kauai, Hawaii 
(Federal Funds) 
(Contributed Funds) 
9. Asquiroga Bay, 
Territory of Guam 
(Federal Funds) 
10. Ofu Airstrip 
American Samoa 
(Federal Funds) 
12. Asan Village, 
Territory of Guam 
(Federal Funds) 
(Contributed Funds) 
13. Kahoma Stream, 
Maui, Hawaii 
(Federal Funds) 
14. Waimea River, 
Kauai, Hawaii 
(Federal Funds) 
18. Nanpil River Hydropower, 
Pohnpei, TTPI 
(Federal Funds) 
Funding 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Tobtal Cost 
lb 
FY 83 FY 84 FY 85 FY 86 Sept. 30, 1986 
- 35,000 18,800 52,000 
14,443 9,771 41,838 52,808 
17,690,000 16,500,000 11,827,000 -4,155,000 
21,659,777 14,346,100 8,348,616 1,485,293 
875,801 567,464 374,434 - 
943,309 673,952 376,920 58,485 
481,000 -406,000 - -35,600 
38,336 13,221 16 1,208 
86,000 154,000 
20,823 219,157 
1,489,400 -25,000 85,000 480,000 
1,474,014 34,328 537,875 511,030 
5,381 
5,381 
- 220,000 -22,800 
- 48,001 149,199 
- 32,000 160,000 
- 7,000 25,461 
908,400 119,600 
115,838 610,486 
630,000 15,000 
- 409,803 
246,330 55,643 
-19,366 
210,465 5,366 
20,000 10,000 20,000 87,000 
19,854 10,315 10,009 82,959 
2,564,000 -69,600 405,000 -130,000 
109,505 2,180,214 462,599 14,251 
- 60,000 114,000 6,000,000 
- 9,188 145,350 1,786,232 
36-6 
See 
Section 
In Text 
1. 
394,300 
392,917 
53,745,500 
53,326,007 
4,249,670 
2,273,281 
159,400 
159,400 
372,000 
372,000 
423,622 
423,602 
370,845 
370,845 
2,127,724 
2,127,724 
6,290,220 
6,290,019 
233,261 
233,261 
227,181 
227,181 
192,000 
32,461 
1,275,500 
1,275,500 
625,634 
625,634 
856,000 
841,942 
2,917,400 
2,914,569 
6,174,000 
1,940,770

PACIFIC OCEAN DIVISION 
TABLE 36-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
2. BARBERS POINT HARBOR, OAHU, HAWAII 
Oct. 27, 1965 An entrance channel 42 feet deep, 450 feet wide, and 3,100 H. Doc. 93, 89th Cong., 
feet long; an inshore basin of about 46 acres, 28 feet deep, a 1st sess.. 
breakwater on the north side of the entrance channel, if 
model study shows it to be necessary; spending beaches with 
wave absorbers within the harbor totaling 1,320 feet in length; 
and a main access channel 12 feet deep, 80 feet wide, and 
1,200 feet long to a small-boat harbor on the west side of the 
deep-draft harbor to be developed by local interests. 
5. NAWILIWILI HARBOR, KAUAI, HAWAII 
Mar. 2, 1919 An entrance channel 35 feet deep; a harbor basin 1,100 feet H. Doc. 609, 62nd Cong., 
wide, 35 feet deep, and.about 1,950 feet long; and a rubble- 2nd sess., as modified 
mound breakwater, by the Chief of 
Engineers. 
Sep. 3, 1954 Deepening entrance channel to 40 feet; enlarging harbor H. Doc. 453, 83 Cong., 
basin; and constructing a revetted-fill area. (Modified by the 2nd sess. (Contains 
Chief of Engineers.) lastest published maps.) 
Dec. 31, 1970 Modification of General Navigation features. River and Harbor Act. 
13. KAHOMA STREAM, MAUI, HAWAII 
Oct. 22, 1976 A debris basin 100 feet wide and 700 feet long with a capacity H. Doc. 94-488, 94th 
of 22,000 cubic yards; a rock sill, a diversion levee which is 80 Cong., 2nd sess. 
feet long to direct flows into the concrete channel; a concrete 
trapezoidal channel about 5,280 feet long; three concrete 
bridges with clear span of 50 feet; and revetted outlet extending 
70 feet seaward of the stream mouth. 
18. NANPIL RIVER HYDROPOWER, POHNPEI, TTPI 
Mar. 20, 1980 Construction of a hydroelectric power facility. Sec. 101, PL 96-205 
Dec. 8, 1983 Appropriation of funds for a feasibility study and construction Sec. 2, PL 98-213 
of a hydroelectric project.
36-7

TABLE 36-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operations and 
Project Status Report for: Construction Maintenance 
Agana Small Boat Harbor, Completed 1978 $ 937,798' $ 11,196 
'ITerritory of Guam 
Ala Wai Small Boat Harbor, Oahu, Hawaii 
Auasi Harbor, American Samoa 
Aunuu Harbor, American Samoa 
Haleiwa Small Boat Harbor, Oahu, Hawaii 
Heeia-Kea Small Boat Harbor, Oahu, Hawaii 
Hilo Harbor, Hawaii, Hawaii 
Honokohau Small Boat Harbor, 
Hawaii, Hawaii 
Honolulu Harbor, Oahu, Hawaii 
Kahului Beach Road, Maui, Hawaii 
Kahului Harbor, Maui, Hawaii 
Kailua Small Boat Harbor, Oahu, Hawaii 
Kalaupapa Harbor, Molokai, Hawaii 
Kaunakakai Harbor, Molokai, Hawaii 
Kawaihae Harbor, Hawaii, Hawaii 
Keehi Lagoon, Oahu, Hawaii 
Kikiaola Small Boat Harbor, Kauai, Hawaii 
Lahaina Small Boat Harbor, Maui, Hawaii 
Maalaea Small Boat Harbor, Maui, Hawaii 
Maunalua Bay Small Boat Harbor, 
Oahu, Hawaii 
Nawiliwili Small Boat Harbor, Kauai, Hawaii 
Ofu Small Boat Harbor, American Samoa 
Pohoiki Bay, Hawaii, Hawaii 
Port Allen Harbor, Kauai, Hawaii 
Reeds Bay Small Boat Harbor, 
Hawaii, Hawaii 
Rota Harbor, Northern Marianas 
Saipan Small Boat Harbor, 
Northern Marianas 
Tau Small Boat Harbor, American Samoa 
Waianae Small Boat Harbor, Oahu, Hawaii 
Wake Island Harbor, Wake Island 
Welles Harbor, Midway Island 
Deferred 
Completed 
Completed 
Completed 
Deferred 
Completed 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Deferred 
Active 
Completed 
Active 
Inactive 
Active 
Deferred 
Completed 
Completed 
Completed 
Completed 
Active 
Completed 
Active 
Completed 
Completed 
Inactive 
Completed 
1976 
1982 
1982 
1978 
1972 
1982 
1971 
1985 
1976 
1984 
1967 
1968 
1966 
1981 
1956 
1981 
1977 
1981 
1972 
1976 
1976 
1979 
1984 
1967 
1985 
1982 
1985 
1979 
1950 
1950 
40,117 
1,033,0152 
1,783,1293 
527,0474 
1,481 
5,423,440 
781,0365 
16,044,0956 
751,8677 
7,203,2218 
157,9979 
138,188 
5,983,50110 
3,348,00011 
193,000 
186,937 
195,000 
30,378 
584,51312 
980,01813 
432,52314 
752,41515 
_ 16 
2,000,000'" 
194,000 
1,991,56918 
1,940,011'9 
2,448,05620 
65,000 
71,897 
14,493 
2,111 
36-8 
5,883 
208,902 
3,680,856 
63,693 
2,038,271 
6,738,020 
3,127 
292,441 
61,800 
41,857 
30,707 
668,354 
884,833

PACIFIC OCEAN DIVISION 
TABLE 36-C 
(Continued) 
OTHER AUTHORIZED NAVIGATION PROJECTS 
'Authorized by the Chief of Engineers and completed in 
October 1977. In addition, Contributed Funds of $282,474 
for Construction. 
2Authorized by the Chief of Engineers and completed in 
February 1982. In addition, Contributed Funds of $86,563 
for Construction. 
3Authorized by the Chief of Engineers and completed in 
February 1982. In addition, Contributed Funds of $231,437 
for Construction. 
4Authorized by the Chief of Engineers and completed in 
November 1975. In addition, Contributed Funds of $410,077 
for Construction and $84,388 for Operation and Maintenance. 
6Completed in March 1970. In addition, Contributed Funds of 
$630,568 for Construction. 
6In addition Contriubted Funds of $201,282 for Construction. 
Authorized by the Chief of Engineers and completed in 
April 1976. 
8In addition, Contributed Funds of $30,200 for Construction. 
9Authorized by the Chief of Engineers and completed in 
September 1967. 
'�In addition, Contributed Funds of $62,102 for Construction. 
"Abandonment authorized by R & H Act of 1965 (HD 98, 89th 
Congress, 1st Session). 
12Authorized by the Chief of Engineers and completed in 
November 1974. In addition, Contributed Funds of $405,471 
for Construction. 
13Authorized by the Chief of Engineers and completed 
in August 1975. In addition, Contributed Funds of $61,953 
for Construction. 
"4Authorized by the Chief of Engineers and completed in 
April 1979. 
'SIn addition, Contributed Funds of $200,000 for Construction. 
'6Reclassified from deferred to active category on May 16, 1983. 
'7Authorized by the Chief of Engineers and completed in March 
1985. In addition, Contributed Funds of $774,373 for Construction. 
'8Authorized by the Chief of Engineers and completed in April 
1985. In addition, Contributed Funds of $54,034 for Construction. 
19In addition, Contributed Funds of $1,791,068 for 
Construction. 
20Completed in 1941 and Maintenance transferred to 
Department of Navy. 
36-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 36-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operations and 
Project Status Report for: Construction Maintenance 
Afono Area and Aoa Area, American Samoa Completed 1978 $ 254,0151 $ - 
Haleiwa Beach, Oahu, Hawaii Completed 1967 240,1482 - 
Hanapepe Bay, Kauai, Hawaii Deferred 1965 - - 
Kaaawa Beach, Oahu, Hawaii Completed 1976 176,4883 - 
Kapaa Tbwn, Kauai, Hawaii Completed 1977 158,9164 - 
Kekaha Beach, Kauai, Hawaii Completed 1981 999,9965 - 
Kihei Beach, Maui, Hawaii Completed 1972 154,3136 - 
Kualoa Regional Park, Oahu, Hawaii Terminated 1982 355,4727 - 
Matafao Shoreline, American Samoa Completed 1984 225,0008 - 
Pago Pago Airport, American Samoa Completed 1984 174,9419 - 
Pago Pago, to Nuuuli, American Samoa Active 1978 394,18710 - 
Poloa Area, American Samoa Completed 1978 136,0401 - 
Sand Island, Oahu, Hawaii Completed 1981 301,87912 - 
Vatia Area, American Samoa Completed 1978 154,30913 
Waikiki Beach, Oahu, Hawaii Active 1979 729,08714 - 
Waimea Beach, Kauai, Hawaii Deferred 15 85,043 
'Authorized by the Chief of Engineers and completed in 
October 1977. In addition, $209,549 in Contributed Funds. 
2Completed in April 1965. In addition, $160,098 in Contributed 
Funds. 
3Authorized by the Chief of Engineers and completed in April 
1975. In addition, $97,075 in Contributed Funds. 
4Authorized by the Chief of Engineers and completed in 
September 1976. In addition, $56,916 in Contributed Funds. 
5Authorized by the Chief of Engineers and completed in 
December 1980. In addition, $1,672,524 in Contributed Funds. 
6Authorized by the Chief of Engineers and completed in 
December 1980. In addition, $1,672,524 in Contributed Funds. 
7Authorized by the Chief of Engineers and terminated in April 
1980 as a Circuit Court ruled sand mining to be illegal. In 
addition, $177,300 in Contributed Funds. 
8Authorized by the Chief of Engineers and completed in 
June 1984. 
9Authorized by the Chief of Engineers and completed in 
June 1984. 
10Authorized by the Chief of Engineers and completed in 
September 1978. In addition, $312,480 in Contributed Funds. 
"Authorized by the Chief of Engineers and completed in 
October 1977. In addition, $101,547 in Contributed Funds. 
Z2 
Authorized by the Chief of Engineers and completed in April 
1981. In addition, $255,728 in Contributed Funds. 
13Authorized by the Chief of Engineers and completed in 
October 1977. In addition, Contributed Funds $132,075 in 
Contributed Funds. 
14In addition $82,000 in Advanced Funds and $17,640 in 
Contributed Funds. 
15No previous full report; project authorized by R & H 
Act of 1958. 
36-10

PACIFIC OCEAN DIVISION 
TABLE 36-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1986 
Full Report 
See Annual Operation and 
Project Status Report for: Construction Maintenance 
Hanapepe River, Kauai, Hawaii Completed 1967 $ 784,8671 $ 
Iao Stream, Maui, Hawaii Completed 1985 12,285,0002 
Kaneohe-Kailua Area, Oahu, Hawaii Completed 1985 25,552,4003 
Kaunakakai Stream, Molokai, Hawaii Completed 1950 73,4784 
Kawainui Swamp, Oahu, Hawaii Completed 1967 1,265,5675 
Kuliouou Stream, Oahu, Hawaii Completed 1971 1,000,0006 
Namo River, Territory of Guam Completed 1982 2,416,314 - 
Paauau Stream, Hawaii Completed 1985 1,978,5148 - 
Wailoa Stream and Tributaries, Completed 1966 1,044,8889 - 
Hawaii, Hawaii 
'Completed in November 1966. In addition, $11,953 in Contributed 
Funds. 
2Completed in November 1983. 
3Completed in October 1984. Includes Non-Federal reimbursement 
of reacreation construction cost of $5,668,300. In addition, 
$8,175 in Contributed Funds. 
4Authorized by the Chief of Engineers and completed in 
December 1950. 
5Completed in August 1966. 
6Authorized by the Chief of Engineers and completed in February 
1970. In addition, $540,335 in Contributed Funds. 
7Authorized by the Chief of Engineers and completed in April 
1982. 
sCompleted in September 1985. 
9Completed in August 1965. 
36-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 36-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report for: Authority Expended Expended 
Hana Small Boat Harbor, 1967 November 1977 $ - 
Maui, Hawaii HD #94-413 
Hanalei Small Boat Harbor, 1967 November 1981 
Kauai, Hawaii HD #97-59 
Kaimu Black Sand Beach, 1975 July 1981 86,235 
Hawaii, Hawaii Director of 
Civil Works 
Kapaakea Homestead Flood Control 1979 July 1981 221,500 
Molokai, Hawaii Director of 
Civil Works 
Kewalo Harbor, Oahu, Hawaii 1976 September 1975 98,800 
Director of 
Civil Works 
Talofofo Bay Bay Shore Protection - August 1981 80,764 
Territory of Guam Director of 
Civil Works 
36-12

PORTLAND, OR, DISTRICT * 
The territorial limits of the Portland District include the 
Pacific coastal drainage area of the State of Oregon, the 
portions of the States of Oregon and Washington which 
lie within the Columbia River watershed downstream of 
the Umatilla Bridge below McNary Dam, and south central 
Oregon west of the Malheur River and the Steens 
Mountains, but not including that part which drains into 
the Klamath Lake and River. 
IMPROVEMENTS 
Navigation 
1. Bonneville Navigation Lock, 
Bonneville Dam, OR and WA .......... 
2. Chetco River, OR ...................... 
3. Columbia and Lower Willamette Rivers 
below Vancouver, WA, and Portland, OR .. 
4. Columbia River at Baker Bay, WA ....... 
5. Columbia River between Chinook, WA, 
and Head of Sand Island ............... 
6. Columbia River at the Mouth, OR and WA 
7. Columbia River between Vancouver, WA 
and The Dalles, OR ................... 
8. Columbia River, Ilwaco, WA.............. 
9. Coos Bay, OR ......................... 
10. Coos and Millicoma Rivers, OR........... 
11. Coquille River, OR ................... . 
12. Depoe Bay, OR . ..................... 
13. Kalama Turning Basin, WA ............. 
14. Navigation Work Under Special 
Authorization ......................... 
15. Nehalem Bay, OR .................... 
16. Port Orford, OR ...................... 
17. Project Condition Surveys .............. 
18. Rogue River Harbor at Gold Beach, OR... 
19. Siuslaw River, OR ..................... 
20. Skamokawa Creek, WA................. 
21. Skipanon Channel, OR................. 
22. Tillamook Bay and Bar, OR............ 
23. Umpqua River, OR .................... 
24. Willamette River at Willamette Falls, OR. 
25. Yaquina Bay and Harbor, OR ........... 
Page 
37-2 
37-2 
37-2 
37-4 
37-4 
37-4 
37-4 
37-5 
37-5 
37-6 
37-6 
37-7 
37-7 
37-7 
37-7 
37-7 
37-8 
37-8 
37-8 
37-9 
37-9 
37-9 
37-9 
37-10 
37-10 
Flood Control 
26. 
27. 
28. 
29. 
30. 
31. 
32. 
Applegate Lake, Rogue River Basin, OR .. 
Blue River Lake, OR................. 
Cottage Grove Lake, OR ................ 
Dorena Lake, OR ..................... 
Elk Creek Lake, Rogue River Basin, OR .. 
Fall Creek Lake, OR ................... 
Fern Ridge Lake, OR .................. 
37-11 
37-11 
37-12 
37-12 
37-12 
37-13 
37-13 
Page 
33. Flood Control Work Under Special 
Authorization ......................... 37-13 
34. Inspection of Completed Flood Control 
Projects .............................. 37-14 
35. Inspection of Completed PL-99 Works .... 37-14 
36. John Day River (West), OR ............. 37-14 
37. Lower Columbia River Basin, OR and WA. 37-15 
38. Lower Columbia River Basin Bank Protection, 
OR and WA ...................... 37-15 
39. Mt. St. Helens & Vicinity, WA ............ 37-15 
40. Mt. St. Helens Sediment Control, Castle 
Rock, WA ............................ 37.16 
41. Scheduling Flood Control Reservoir 
Operations ........................... 37-16 
42. West Makinster Road, Wilson River, OR .. 37-16 
43. Willamette River Basin, OR ............ 37-16 
44. Willamette River Basin Bank Protection, 
O R ................... :....................37-17 
45. Willow Creek Lake, Heppner, OR..........37-17 
Multiple-Purpose Projects, 
Including Power 
46. Bonneville Lock and Dam - Lake 
Bonneville, OR and WA ................ 37-17 
47. Cougar Lake, OR...................... 37-18 
48. Detroit Lake, OR ..................... 37-19 
49. Green Peter-Foster Lakes, OR ........... 37-19 
50. Hills Creek Lake, OR ........................ 37-20 
51. John Day Lock and Dam - Lake 
Umatilla, OR and WA ................. 37-20 
52. Lookout Point Lake, OR ................ 37-21 
53. Lost Creek Lake, Rogue River Basin, OR . 37-21 
54. The Dalles Lock and Dam - Lake Celilo, 
WA and OR .......................... 37-22 
General Investigations 
55. Surveys .............................. 37-22 
56. Collection and Study of Basic Data ...... 37-23 
57. Continuation of Planning and Engineering 37-23 
37-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Tables 
Table 37-A Cost & Financial Statement .... 37-24 
Table 37-B Authorizing Legislation ........ 37-31 
Table 37-C Other Authorized Navigation 
Projects ..................... 37-39 
Table 37-D Not Applicable 
Table 37-E Other Authorized Flood Control 
Projects ..................... 37-40 
Table 37-F Other Authorized Multiple Purpose 
Projects, Including Power .. 37-44 
Table 37-G Deauthorized Projects ......... 37-44 
Table 37-H Columbia and Lower Willamette 
River Below Vancouver, WA and 
Portland, OR ................. 37-45 
Table 37-I Navigation Activities Pursuant 
to Section 107, Pub ic Law 
86-645 ...................... 37-45 
Navigation 
1. BONNEVILLE NAVIGATION LOCK, BONNEVILLE 
DAM, OR and WA 
Location. On Columbia River 40 miles east of 
Portland, OR about 146 miles above mouth of river. 
Existing project. The existing lock chamber is 76 feet 
wide and 500 feet long with 24.2 feet depth of water over 
the sill. Construction of a new navigation lock just south 
of the existing lock was authorized in the FY 1985 Supplemental 
Appropriations Act, Public Law 99-88 August 
15, 1985. The new lock chamber will be 86 feet wide and 
675 feet long with 19 feet depth of water over the sill. 
Estimated cost from construction of the new navigation 
lock is $203,000,000. 
Local cooperation. None required. Inland Waterways 
Trust Fund will fund 50 percent of project cost in accordance 
with the Water Resources Development Act of 1986. 
Operations during fiscal year. New Work: Construction 
of relocation portion of the new navigation lock was 
initiated in May 1986 with award of a horizontal drain 
contract for stabilization of a potential slide area. A contract 
for relocation of a section of the main line of the 
Union Pacific Railroad and for modification of the I-84 off 
ramp was awarded in July 1986. 
2. CHETCO RIVER, OR 
Location. Rises in Siskiyou Mountains of Coast Range 
at an elevation of 4,000 feet, flows for about 51 miles in 
a circuitous route, and empties into Pacific Ocean at 
Brookings, OR, 300 miles south of entrance to Columbia 
River and 345 miles north of San Francisco Bay. (See National 
Oceanic and Atmospheric Administration Charts 
18600 and 18203.) 
Existing projects. Provides for two jetties at the mouth 
of the river. Modification in 1965 authorized an entrance 
channel 120 feet wide by 14 feet deep; a barge turning 
Table 37-J Project Condition Surveys ...... 37-45 
Table 37-K Willamette River at Willamette 
Falls, OR, Principal Features of 
Existing Canal and Locks ...... 37-45 
Table 37-L Flood Control Activities Pursuant 
to Section 205, Public Law 
80-858 ...................... 37-46 
Table 37-M Flood Control Reservoir 
Operations .................. 37-47 
Table 37-N Lower Columbia River Basin, 
OR and WA, Levees and Improvements 
to Existing Works .. 37-48 
Table 37-0 Willamette River Basin Comprehensive 
Plan .............. 37-49 
Table 37-P Principal Data Concerning 
Navigation Lock, Spillway Dam 
and Powerpiant ............... 37-51 
basin about 250 feet wide, 650 feet long, and 14 feet deep; 
and a small boat access channel 100 feet wide by 12 feet 
deep. Also authorized was a 450-foot extension of north 
jetty with an increase in elevation of existing portion and 
a protective dike about 1,800 feet long with a top elevation 
of 18 feet. Mean lower low water is plane of reference. 
Tidal range between mean lower low water and mean 
higher high water is 6.9 feet and extreme is about 12 feet. 
Construction of jetties was completed December 1957. 
Removal of rock pinnacles and an abandoned bridge structure 
was accomplished in June 1959. Under authorized 
modification of October 1965, two contracts were completed. 
Construction of entrance channel and extension 
of north jetty was completed in July 1969. Construction 
of a protective dike, turning basin and small boat access 
channel was completed in March 1970. 
Local cooperation. Fully complied with. 
Terminal facilities. The Port of Brookings has 
developed two large boat basins, one for commercial 
fishing boats and the other for sport boats, and a public 
boat launching ramp. There are four fish receiving docks 
and a sea-going barge dock for lumber loading and 
storage. There is also a privately owned marina and a 
Coast Guard Station. 
Operations during fiscal year. Maintenance: A total 
of 40,267 cubic yards of material was removed by the U.S. 
hopper dredge Yaquina. 
3. COLUMBIA AND LOWER WILLAMETTE 
RIVERS BELOW VANCOUVER, WA, AND 
PORTLAND, OR 
Location. The Columbia River rises in British Columbia, 
through which it flows for 425 miles. It enters the 
United States in northeastern Washington, and empties 
into the Pacific Ocean 645 miles north of San Francisco 
Bay and 160 miles south of Strait of Juan DeFuca. Total 
length of river is 1,210 miles. (See NOAA Charts 18520, 
37-2

PORTLAND, OREGON DISTRICT 
18521, 18522, 18523, 18524, 18526, & 18531; also 
Geological Survey Map of Washington). Willamette River 
rises in Cascade Range in western Oregon, flows northerly, 
and empties into Columbia River about 100 miles from 
the sea. Its length from source of Middle Fork is about 
294 miles. Project embraces 103.5 miles of Columbia River 
below Vancouver, WA, and 14.6 miles of Willamette River 
below Portland, OR. (See NOAA Chart 18526 and 
Geological Survey Map, State of Oregon.) 
Existing project. Provides for a channel 35 feet deep 
and 500 feet wide from River Mile 106.5 to 105.5, the 
distance between existing highway and railroad bridges; 
a channel 40 feet deep and 600 feet wide from Vancouver, 
WA, River Mile 105.5 to mouth of Columbia River, River 
Mile 3; a turning basin at Vancouver, WA, 40 feet deep, 
800 feet wide, and about 5,000 feet long; a turning basin 
at Longview, WA, 40 feet deep, average width of 1,200 feet, 
and about 6,000 feet long; and a channel 40 feet deep in 
the Willamette River with varying widths of 600 to 1,900 
feet from mouth (River Mile 0) to Broadway Bridge (River 
Mile 11.6) which encompasses Portland Harbor area, subject 
to provisions that channel from mouth of Willamette 
River to turning basin at Vancouver, WA, be limited to 
500 feet in width until need for additional width is 
demonstrated by developed traffic. Existing project also 
provides for auxiliary channels 10 feet deep and 300 feet 
wide near Cathlamet, WA; 30 feet deep and 300 feet wide 
in St. Helens (Oregon); and 30 feet deep and 500 feet wide 
connecting upper end of St. Helens Channel with main 
ship channel of Columbia; 24 feet deep and 200 feet wide 
along frontage of town of Rainier, OR, extended at its upper 
and lower ends to deep water in Columbia River, 8 
feet deep and 150 feet wide from this depth in Columbia 
River through old mouth of Cowlitz River to a point about 
3,000 feet upstream from present terminus of harbor line; 
a channel from Longview Port dock downstream along 
pierhead line and past Weyerhaeuser Timber Co. plant 
at Longview to a connection with main ship channel below 
Mount Coffin, the downstream 2,400 feet of this channel 
to be 30 feet deep and 300 feet wide and remainder to be 
28 feet deep and 250 feet wide; construction of a smallboat 
mooring basin at Astoria, OR, to include a sheet-pile, 
sand-filled breakwater about 2,400 feet long with a 30-foot 
roadway along its full length, and steel pile shore wings 
totaling about 1,460 feet long and for stone-and-pile dikes 
and revetments. Plane of reference in estuary from mouth 
to Harrington Point is mean lower low water; thence to 
Portland and Vancouver, adopted low water. Tidal range 
between mean lower low water and mean higher high 
water at mouth of Columbia is about 8 feet, and at 
Portland and Vancouver about 3 feet at low stages of 
rivers. Extreme tidal ranges are about 13 and 3 feet, 
respectively. Annual freshets have little effect on stage 
of tide at mouth of Columbia; at Portland and Vancouver 
they average about 12 feet, while highest known reached 
a stage of 33 feet above low water at Portland. 
Work on the 40-foot channel in Columbia River from 
Portland, OR, and Vancouver, WA, to the sea was completed 
in 1976 except for observation of channel to determine 
if additional control structures or dredging will be 
required. Auxiliary channel in vicinity of Longview was 
completed in 1949, and improvement of mouth of Cowlitz 
River and small boat mooring basin at Astoria were completed 
in 1950. Project depths are maintained all year except 
for the period immediately following the annual 
freshet in May-June when shoaling occurs at several locations. 
Timing of vessel movement with tidal fluctuations 
permit maximum draft conditions. In Columbia and 
Willamette Rivers between mouth and Broadway Bridge 
at Portland a depth of 40 feet at low tide and 42 feet at 
high tide is practicable all year. In Columbia River between 
mouth of Willamette River and Vancouver, WA, 
depths of 40 and 42 feet at low and high tide, respectively, 
are practicable all year. (For details relating to previous 
project, see pages 1995 and 1998 of Annual Report for 
1915 and page 1746 of Annual Report for 1938.) 
Local cooperation. Fully complied with. Requirements 
are described in full on page 37-3 of FY 1981 
Annual Report. 
Terminal facilities. At Portland, OR, there are six Port 
of Portland terminals consisting of 43 berths equipped to 
handle general cargo, bulk cargo, lumber, automobiles, lift 
on-lift off and roll on-roll off containers, and breakbulk 
vessels. The Port of Portland owns and operates a major 
ship repair yard, which includes the West Coast's largest, 
and the world's third largest, floating dry dock. Also 
available in the harbor area are privately operated 
facilities for receiving, storing and outloading petroleum, 
wood chips, grain, logs, sand and gravel, cement and steel 
products. 
At Astoria, OR, there is a terminal with facilities for 
receiving and handling all types of general cargo. 
At Vancouver, WA, there are municipal facilities 
capable of berthing five ships simultaneously. Each berth 
is completely outfitted with mechanical and lift facilities 
for receiving and handling all types of cargo. The port has 
a low dock to handle roll on-roll off and side-port discharging 
vessels. The grain terminal has a storage capacity of 
4,500,000 bushels. 
Port of Longview has a public terminal on Columbia 
River and a privately owned grain elevator with a capacity 
of 6,900,000 bushels. This port also has a heavy lift facility, 
with a capacity of 600 tons. 
Port of Kalama has two berthing areas, one port owned 
and one private. 
At other locations on Columbia River between Portland 
and Columbia River entrance there are sufficient private 
facilities to accommodate river vessels and fishing craft. 
These facilities, with planned extensions, are considered 
adequate for existing commerce. (For details see Port 
Series Nos. 33 and 34, Corps of Engineers, published in 
1974 and 1975 respectively.) 
Operations during fiscal year. Maintenance: Regular 
maintenance continued through the year. A total of 
6,642,617 cubic yards of material was removed. The U.S. 
hopper dredge Essayons removed 2,172,200 cubic yards, 
and contract hopper dredge Stuyvesant removed 256,774 
cubic yards. In addition, the pipeline dredge Oregon 
37-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
removed 3,706,648 cubic yards, and the contract pipeline 
dredge Lofgren removed 506,995 cubic yards. 
4. COLUMBIA RIVER AT BAKER BAY, WA 
Location. Baker Bay is a shallow body of water about 
15 square miles in extent on the north side of Columbia 
River near its mouth. The bay is separated from the river 
by Sand Island, a low-lying sand bar only a few feet above 
high tide level. (See NOAA Chart 18521.) 
Existing project. A mooring basin 10 and 12 feet deep, 
about 20 acres in extent with protecting breakwaters; and 
a west channel 16 feet deep and 200 feet wide for the first 
2000 feet, then 16 feet deep and 150 feet wide to the boat 
basin; a channel east of Sand Island to Port of Ilwaco, a 
distance of about 4 miles. Mean lower low water is plane 
of reference. Tidal range between mean lower low water 
and mean higher high water is about 8 feet, and extreme 
about 13 feet. 
Channel extending through easterly passage of Sand 
Island was completed in 1934. This portion of authorized 
project is not passable and is not maintained at the present 
time. Dredging west channel to 8 feet was accomplished 
September 1948. Deepening west channel to 10 feet, 
and boat basin and breakwater construction at Ilwaco, 
WA, was finished December 1957, and again, deepening 
of the west channel to 16 feet completed in August 1985 
under Section 107, finished the project. 
Local cooperation. Fully complied with. 
Terminal facilities. Wharves, floats, ramps, and 
berths, for fishing craft, barges and tow-boats. Small-boat 
basin and protecting breakwater provides moorings for 
numerous fishing and recreational craft all year. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: A U.S. 
hopper dredge removed 58,921 cubic yards of material. 
5. COLUMBIA RIVER BETWEEN CHINOOK, WA, 
AND HEAD OF SAND ISLAND 
Location. At easterly end of Baker Bay, lying on north 
side of Columbia River near mouth. (See Coast and 
Geodetic Survey Chart 6151.) 
Existing project. Channel 10 feet deep and 150 feet 
wide, extending from head of Sand Island to Chinook: a 
turning and mooring basin at upper end of channel, 10 
feet deep, 660 feet long, and ranging from 275 to 500 feet 
wide; reconstruction of easterly 393 feet of existing 
breakwater; and extension of existing breakwater easterly 
and thence northerly to connect with shore in vicinity of 
Portland Street, Chinook, WA. Tidal range between mean 
lower low water and mean higher high water is about 8 
feet and extreme about 13 feet. 
Project as originally authorized was completed in 1940. 
The 10-foot channel depth modification was accomplished 
September 1958. Rehabilitation of existing breakwater 
was completed September 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. Chinook Packing Company owns 
a wharf for receiving fresh fish, and one additional fish 
buying company is located at Chinook. A portion of wharf 
is also used as a public landing. At upper end of channel 
there is a turning and mooring basin with facilities for 
mooring 350 fishing and recreational craft. Adequate terminal 
and mooring facilities include a public launching 
ramp, hoist with 10-ton capacity and suitable supply 
facilities. 
Operations during fiscal year. Maintenance: Contract 
Clamshell dredge Mukiltco removed 124,081 cubic 
yards of material. 
6. COLUMBIA RIVER AT THE MOUTH, OR 
AND WA 
Location. The Columbia River entrance is 645 miles 
north of San Francisco Bay. Project is about 120 miles 
downstream of Portland, OR, and Vancouver, WA. For 
description of Columbia River see Section 4. 
Existing project. Provides for a one-half-mile-wide 
channel across a bar 55 feet deep (mean lower low water) 
for the northernmost 2,000 feet, and 48 feet deep (mean 
lower low water) along the southern 640 feet, to be secured 
by two rubblemound jetties, spur jetty "A" on the north 
shore and by dredging. The north jetty is about 2.5 miles 
long and the south jetty about 6.6 miles long, spur jetty 
"A" is about 0.3 miles long. Tidal range on bar between 
mean lower low water and mean higher high water is 
about 8 feet, and extreme about 13 feet. 
The originally authorized project depth of 40 feet was 
completed in 1918; south jetty completed in 1914 and 
north jetty in 1917. A spur jetty (jetty "A") was completed 
in 1939 (repaired in 1961) for the purpose of channel 
stabilization. Spur jetty "B" currently is classified "inactive." 
Dredging of the 48-foot bar channel started April 
1956 was completed in September 1957. South jetty 
rehabilitation started June 1962 was completed 
September 1964. North jetty rehabilitation started 
January 1965 was completed April 1965. Additional 
rehabilitation of the south jetty was initiated in May 1982 
and completed in September 1982. Deepening bar channel 
to 55 feet completed September 1984. Project dimensions 
were available at end of fiscal year. (For details 
relating to previous projects, see page 1999, Annual 
Report for 1915 and page 1740 of Annual Report for 1938.) 
Local cooperation. Fully complied with. Local interests 
contributed $500,000 toward construction of the 
north jetty which was completed in 1917. 
Operations during fiscal year. Maintenance: A total 
of 7,832,392 cubic yards was removed. The U.S. hopper 
dredge Essayons removed 3,106,500 cubic yards of 
material and the contract dredge Stuyvesant removed 
4,725,892 cubic yards. 
7. COLUMBIA RIVER BETWEEN VANCOUVER, 
WA, AND THE DALLES, OR 
Location. On Columbia River, between Interstate 
Bridge at Vancouver, WA, 106.5 miles above mouth and 
The Dalles, OR, mile 191, a distance of 84.5 miles. For 
description of Columbia River, see Section 4, "Columbia 
37-4

PORTLAND, OREGON DISTRICT 
and Lower Willamette Rivers Below Vancouver, WA, and 
Portland, OR." 
Existing project. Channel 27 feet deep at low water 
and 300 feet wide between Vancouver, WA, and The 
Dalles, OR, 84.5 miles; a channel 10 feet deep at low water 
and 200 feet wide at upstream entrance to Oregon Slough, 
OR; a suitable turning basin adjacent to site of port 
development in vicinity of Camas and Washougal, WA; 
a boat basin at Hood River, OR, 500 by 1,300 feet and 10 
feet deep at normal Bonneville pool level, with a connecting 
channel of same depth to deepwater, and a protecting 
breakwater on easterly side; a barge channel to 
waterfront at Bingen, WA, 10 feet deep at normal Bonneville 
pool level, 200 feet wide and about 1 mile long, 
and an access channel 7 feet deep at normal Bonneville 
pool level, 100 feet wide and about 1,000 feet long, to a 
natural mooring basin for small boats near east end of 
channel; and construction of The Dalles small boat basin, 
to provide a breakwater and shear boom protected basin 
about 400 by 800 feet in size with depth of 8 feet below 
a pool elevation of 72.5 feet at mean sea level. Tidal range 
between mean lower low water and mean higher high 
water at Vancouver is about 3 feet and at Bonneville about 
0.2 foot at low stages of the river. Extreme tidal ranges 
are about 4 feet and 0.4 foot, respectively. 
Existing project is complete. Construction of The Dalles 
small boat basin, was completed in 1949. Channel dredging 
at upper end of Oregon Slough was accomplished in 
1957. Project depth of 27 feet between Bonneville and The 
Dalles, OR, was achieved April 1959. The 27-foot channel 
depth between Vancouver, WA, and Bonneville, OR, 
was completed May 1938. Improvement of lower entrance 
of Bonneville Dam lock was completed in May 1961. At 
the present time, the channel is maintained to a depth 
of 16 feet, which is adequate for using traffic. Construction 
of a boat basin at Hood River, OR, and of Camas- 
Washougal, WA, turning basin was accomplished 
February 1962. Construction of a barge channel in Columbia 
River near Bingen, WA, was completed September 
1963. Small boat recreation channel 100 feet wide 6 feet 
deep at South Channel Government Island completed 
1985 under section 107. 
Local cooperation. Fully complied with. 
Terminal facilities. At Vancouver, WA, upstream of Interstate 
Highway bridge at River Mile 108.1 on site of 
former shipyard are numerous ship-building facilities 
equipped with railway and river moorage facilities. Also 
in this area are a paper-storage warehouse with barge slip, 
two boat building businesses, and a storage dock with gantry 
crane. Sites are available for developrrnient to suit 
lessee. 
At Camas, WA, about 13.5 miles upstream from Vancouver, 
there is a private wharf used for transfer of papermill 
supplies and paper to and from barges, and facilities 
for discharging bulk oils from barges. 
At Port of The Dalles (mile 44 above Bonneville) there 
is a municipal wharf 125 by 1,100 feet for use by tugs and 
barges. There is one one-story timber and corrugated iron 
warehouse, 94 by 461 feet, on this wharf. A private 
elevator with a capacity of 40,000 bushels and a public 
elevator of 1,113,800-bushel capacity for handling bulk 
grain to barges are also at The Dalles. Public elevator has 
rail, truck, and water connections. There is a port owned 
rail connection about three-fourths mile below municipal 
wharf where certain types of cargo may be handled between 
railroad cars and barges. 
At numerous locations along the entire waterway there 
are facilities for transfer of logs to water from trucks and 
public and private boat basins. Facilities are considered 
adequate for present commerce. 
Operations during fiscal year. Maintenance: The 
U.S. hopper dredge Yaquina removed 305,799 cubic yards 
of material and the sand-bypasser Sandwick displaced 
sand from shoal areas. 
8. COLUMBIA RIVER, ILWACO, WA 
Location. West channel of Baker Bay, starting at Columbia 
River Mile 3 and extending northward 3 miles to 
the entrance of the mooring basin at Ilwaco, Pacific County, 
Washington. 
Existing project. The present channel is 10 feet deep 
and 200 feet wide for the first 2,000 feet, then 10 feet deep 
and 150 feet wide to the boat basin. Work was authorized 
under the special continuing authority contained in Section 
107 of the 1960 River and Harbor Act, as amended. 
The plan of improvement provides for deepening the channel 
to 16 feet along the existing alinement and the width 
to remain the same. This plan will reduce delays, 
minimize damages to commercial boats, and allow larger 
boats access to the processing facilities at Ilwaco, WA. 
Local cooperation. The project sponsor, Port of Ilwaco, 
has agreed to provide necessary easements, rights-of-way, 
and utility relocations. The Port also agreed to hold the 
United States free from damages and to provide and maintain 
mooring and public use facilities. 
Operations during fiscal year. New work: All 
scheduled dredging work was completed by August 1985. 
Seeding of disposal area completed 1986. 
9. COOS BAY, OR 
Location. On Oregon coast 200 miles south of mouth 
of Columbia River and 445 miles north of San Francisco 
Bay. It is about 13 miles long and 1 mile wide, with an 
area at high tide of about 15 square miles. (See NOAA 
Charts 18580 and 18587.) 
Existing project. Two rubblemound, high-tide jetties 
at entrance; a channel across the outer bar 45 feet deep 
and 700 feet wide, reducing gradually to 35 feet deep and 
300 feet wide near River Mile 1 and continuing to about 
mile 9; thence a channel 35 feet deep and generally 400 
feet wide to mile 15; an anchorage area 35 feet deep, 800 
feet wide, and 1,000 feet long at Empire (River Mile 5.5); 
turning basins at North Bend (River Mile 12.5) and 
Coalbank (River Mile 14.7) 35 feet deep, 650 feet wide and 
1,000 feet long; a channel 22 feet deep and 150 feet wide 
from Smith's Mill (River Mile 15) to Millington (River Mile 
17); a small boat basin, about 500 by 900 feet at 
Charleston, with a connecting channel, 16 feet deep, 150 
37-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
150 feet wide and 6,200 feet long, to deep water in Coos 
Bay, and construction of a protecting breakwater and 
bulkhead. Plane of reference is mean lower low water. 
Tidal range between mean lower low water and mean 
higher high water is 7 feet and extreme is about 11 feet 
at both the entrance and at Coos Bay. 
South jetty was completed in 1928, north jetty in 1929, 
and 24-foot channel in 1937. The south jetty was restored 
in 1941 and 1942 by construction of a concrete cap for full 
length of the jetty. Excavation of channel to 30 feet deep 
and generally 300 feet wide from entrance to Isthmus 
Slough was completed in 1951. Dredging outer bar channel 
to a depth of 40 feet, decreasing to 30 feet at Guano 
Rock was completed in 1952. Construction of the 
Charleston Channel and small-boat basin was completed 
in September 1956. Rehabilitation of south jetty was 
started in June 1962 and completed December 1963. 
Repair of north jetty was completed in August 1970. Construction 
of the deeper and wider channel to mile 15 was 
completed in 1979. Deepening of Charleston channel and 
turning basin completed in 1985 under Section 107. (For 
details relating to previous projects, see page 1987 of Annual 
Report for 1915 and page 1728 of Annual Report for 
1938.) 
Local cooperation. Fully complied with. Requirements 
are described in full on page 37-5 of FY 1981 
Annual Report. 
Terminal facilities. At North Bend there is a 
municipal dock 649 feet long fronting on channel, about 
2,380 feet of privately owned mill docks, and three oilreceiving 
terminals in vicinity. 
At Coos Bay there is a privately owned dock with a frontage 
of 1,345 feet, open to the public on equal terms; 
several small landings for fishing and harbor craft; and 
three lumber docks with 1,300, 576, and 500-foot frontages, 
respectively. 
At Eastside, on Isthmus Slough, there is a 200-foot 
dock. 
At Empire there is a privately owned lumber dock with 
frontage of 510 feet, and an oil terminal, owned by Port 
of Coos Bay, for receipt of petroleum products by barge. 
A barge slip also owned by the Port was completed in 1986. 
At Charleston there are wharves, for receipt of fresh 
fish and shellfish and a large seafood receiving and processing 
plant. There are also two municipally owned 
small-boat basins, open to all on equal terms, capable of 
mooring 250 fishing and recreation craft. -Servicing 
facilities for small craft are available at all facilities, and 
public launching ramps have been constructed in 
Charleston area by private interests. A privately owned 
floating moorage on Joe Ney Slough has facilities for 
mooring about 50 fishing vessels. 
At Jordan Cove area there is a dock, 248 feet long, for 
wood chip ships. 
These facilities are considered adequate for existing 
commerce. (For details see Port Series No. 33, Corps of 
Engineers, published in 1975.) 
Operations during fiscal year. Maintenance: Total 
of 951,584 cubic yards removed. U.S. hopper dredge Yaquina 
removed 192,083 cubic yards; Essayons removed 
75,500 cubic yards and the contract hopper dredge Stuyvesant 
removed 684,001 cubic yards of material. 
10. COOS AND MILLICOMA RIVERS, OR 
Location. South Fork and Millicoma Rivers rise in 
Coast Range in southern Oregon, flow generally westerly 
and join to make Coos River, 5.3 miles above mouth of 
Coos River in Coos Bay. (See NOAA Chart 18587, 
Allegany and Daniels Creek Quadrangle.) 
Existing project. Originally authorized project: a 
channel depth of 3 feet, generally, from mouth of Coos 
River and 1 foot near head of navigation. Project as 
modified: two channels 5 feet deep and 50 feet wide from 
mouth of Coos River to Allegany on Millicoma River, mile 
13.8 and to Dellwood on South Fork, mile 14, and thence 
a channel 3 feet deep and 50 feet wide to mile 14.7 on 
South Fork, including stabilization works on Coos River. 
Mean lower low water is plane of reference. Tidal range 
between mean lower low water and mean higher high 
water at the mouth of Coos River is 7 feet and extreme 
about 11 feet. Tidal range at head of navigation in both 
forks is about 1 foot. Freshet stages usually reach a height 
of from 10 to 15 feet at Allegany, head of navigation on 
Millicoma River. 
Originally authorized project providing for a channel 
from mouth of Coos River to head of navigation in both 
forks, to provide a depth of 3 feet generally and 1 foot near 
head of navigation, was completed in 1899. In March 1966 
construction of project as modified by 1948 River and Harbor 
Act was completed. 
Local cooperation. Fully complied with. 
Terminal facilities. Several small privately owned 
docks and landing places on the river are used by towboats 
and pleasure craft. There are no publicly owned docks. 
Present facilities are considered adequate for existing 
commerce. Major log processing yards are located at the 
head of navigation on both rivers. 
Operations during fiscal year. Maintenance: Contract 
pipeline dredge Marathon removed 32,747 cubic 
yards of material. 
11. COQUILLE RIVER, OR 
Location. Rises in Coast Range, flows generally westerly 
for about 100 miles, and empties into Pacific Ocean at 
Bandon, OR, 225 miles south of mouth of Columbia River 
and 420 miles north of San Francisco Bay. (See NOAA 
Charts 18580 and 18186.) 
Existing project. Two rubblemound high-tide jetties 
at river mouth, south jetty 2,700 feet long and the north, 
3,450 feet long; and a channel 13 feet deep at mean lower 
low water and of suitable width from the sea to a point 
1 mile above old Coquille River Lighthouse, and snagging 
to State highway bridge at city of Coquille. Mean lower 
low water is plane of reference. Tidal range between mean 
lower low water and mean higher high water at mouth 
is 7 feet and extreme about 10 feet. 
37-6

PORTLAND, OREGON DISTRICT 
Jetties were completed in 1908 and entrance channel 
in 1933. North jetty was reconstructed in 1942 and a 
750-foot extension to easterly end was constructed in 1951. 
South jetty was repaired in 1954 and north jetty in 1956. 
Coquille Lighthouse rehabilitation was completed June 
21, 1976. Port of Bandon constructed boat basin facility 
in conjunction with protective breakwater and entrance 
channel construction in 1985, under Section 107. (For 
details relating to previous projects, see page 1986 of Annual 
Report for 1915 and page 1727 of Annual Report for 
1938.) 
Local cooperation. None required. However, restoration 
of lighthouse using Code 710, Recreation Facilities 
at Completed Projects, funding required 50 percent cost 
sharing with non-Federal sponsor (Oregon State Parks). 
Terminal facilities. At Bandon: A privately owned mill 
dock used exclusively for shipping lumber on coastwise 
vessels, a publicly owned wharf, and a small-boat basin 
open to all on equal terms. 
Operations during fiscal year. Maintenance: U.S. 
hopper dredge Yaquina removed 61,339 cubic yards of 
material from entrance channel. 
12. DEPOE BAY, OR 
Location. Harbor on Oregon coast 100 miles south of 
mouth of Columbia River. (See Coast and Geodetic Survey 
Chart 5902.) 
Existing project. Two breakwaters north of entrance; 
an entrance channel 8 feet deep and 50 feet wide; and inner 
basin 750 feet long, 390 feet wide and 8 feet deep with 
retaining wall along easterly side; and a stone spending 
beach. Mean lower low water is plane of reference. Tidal 
range between mean lower low water and mean higher 
high water is 8 feet and extreme is about 12 feet. Project 
as originally authorized was completed in 1939 and project 
modification, enlarging the basin and deepening to 
8 feet, was accomplished in June 1952 and August 1966. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities, in inner basin, consist 
of landings and floats to accommodate operators of excursion 
and commercial fishing boats. Facilities considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were 
performed. 
13. KALAMA TURNING BASIN, WA 
Location. Columbia River between miles 73+10 and 
73+50 at Kalama, Washington. 
Existing Project. The present channel is 40 feet deep, 
600 feet wide and 4,000 feet long. The improvement provides 
for a turning basin 40 feet deep, averaging width 
of 1,100 feet and 4,000 feet long. 
Local Cooperation. The Port of Kalama agreed to provide 
necessary easements, rights-of-way and utility relocations. 
The Port also agreed to hold the United States free 
from damages and to provide and maintain mooring and 
public use facilities. 
Operations during fiscal year. New work. Contract 
pipeline dredge Oregon removed approximately 145,000 
cubic yards of material. All scheduled work completed 
February 1986. 
14. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, 
Public Law 86-645 (preauthorization). 
See Table 37-I. 
Aquatic plant control (Section 302, Public Law 
89-298): 
Sampling and identification of aquatic plant infestation 
in Columbia River and Willamette River Basins were 
accomplished. Total costs for fiscal year were $15,707. 
15. NEHALEM BAY, OR 
Location. On Oregon coast, 40 miles from Columbia 
River mouth and 10 miles north of the entrance to 
Tillamook Bay. 
Existing project. Provides for a jetty about 3,850 feet 
long on the north side of entrance and a jetty 4,950 feet 
long on the south side. Mean lower low water is plane of 
reference. Tidal range between mean lower low water and 
mean higher high water is 8 feet, extreme is about 15 feet. 
Project as originally authorized was completed in 1918. 
Rehabilitation work was initiated in May 1981 and completed 
November 1982. 
Local cooperation. None required. 
Terminal facilities. Facilities for pleasure craft only: 
Dart's Marina, Brighton Moorage, Jetty Fishery, Port of 
Nehalem and city of Nehalem Dock. All areas have approximately 
50-60 slips. 
Operations during fiscal year. Maintenance: Inspection 
performed. 
16. PORT ORFORD, OR 
Location. On Oregon coast 250 miles south of Columbia 
River entrance and 390 miles north of San Francisco 
Bay. (NOAA Chart 18203 and Geological Survey 
Quadrangle, Port Orford, OR.) 
Existing project. Improvement of harbor by 550-foot 
extension of existing locally constructed breakwater and 
dredging of a turning basin, 340 feet long, 100 feet wide 
and 16 feet deep. Breakwater was completed October 1968. 
Turning basin was completed September 1971. 
Local cooperation. Fully complied with. 
Terminal facilities. A dock which is a timber piling 
structure about 210 by 70 feet, equipped with hydraulic 
crane for lifting boats from the water to dock for repairs 
and/or storage and removing fish catches from boats. Expansion 
of the dock structure to 210 x 220 feet ia 90% complete. 
The installation of the second hydraulic crane was 
completed in FY 1986. About 150 fishing and private 
boats use this dock each year. 
37-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Operations during fiscal year. Maintenance: During 
the summer months, the sand-bypasser Sandwick displaced 
shoal areas to provide longer periods of channel depths 
for navigation traffic within the authorized project. A contract 
submersible pump dredge removed 2,509 cubic yards 
of material which would provide users with adequate 
depths to utilize cranes during the winter months. 
17. PROJECT CONDITION SURVEYS 
Surveys were conducted during FY 1986 at a cost of 
$105,344; cumulative costs, $593,000 (See Table 37-J). 
18. ROGUE RIVER HARBOR AT GOLD BEACH, 
OR 
Location. Rises in Cascade Range in southwestern 
Oregon, flows westerly through Coast Range, and empties 
into Pacific Ocean 264 miles south of mouth of Columbia 
River and 381 miles north of San Francisco Bay. 
(See NOAA Chart 18202.) 
Existing project. Two jetties at entrance, and a channel 
13 feet deep and 300 feet wide from ocean to a point 
immediately below State highway bridge, about 1 mile, 
including widening channel at a point about 0.25 mile 
below bridge to form a turning basin 13 feet deep, 500 feet 
wide, and 650 feet long. At request of local interests, turning 
basin was located in south portion of estuary 
downstream from a point 0.25 mile below bridge. This 
change was effected to permit adequate terminal facilities 
to be constructed adjacent to turning basin. Mean lower 
low water is plane of reference. Range of tide between 
mean lower low water and mean higher high water is 7 
feet, and extreme about 14 feet. 
Project as authorized has been completed. Construction 
of two jetties at entrance was completed September 1960. 
Dredging river channel by contract and entrance bar by 
government plant was completed October 1961. North jetty 
rehabilitation along channel side was completed October 
1966. Breakwater construction and dredging, under 
contract awarded in September 1964, was 17 percent accomplished 
when flood of December 1964 destroyed all 
completed works. Contract was terminated as further construction 
at that location was considered unfeasible. Bank 
protection work at Wedderburn location was completed 
in October 1972. A breakwater, constructed by Port of Gold 
Beach, was completed during 1973. In 1984, three pile 
dikes, south side of channel, oceanward of the boat basin 
entrance, were completed. 
Local cooperation. Fully complied with. 
Terminal facilities. There are various landings for 
fishing and recreational craft. At Wedderburn, across river 
from Gold Beach, is a facility to accommodate excursion 
passengers and small freight items destined for various 
private landings between Wedderburn and Agness, OR. 
Facilities considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: The 
sand-bypasser Sandwick displaced isolated shoals on the 
entrance. 
19. SIUSLAW RIVER, OR 
Location. Rises in coast range, flows about 110 miles 
westerly and empties into Pacific Ocean about 160 miles 
south of entrance of Columbia River and 485 miles north 
of San Francisco Bay, CA. (See NOAA Charts 18583 and 
18580.) 
Existing project. Provides for 2 high-tide, rubblemound 
jetties 750 feet apart at the outer end, the north 
jetty 8,390 feet long (600 feet unconstructed) and the south 
jetty 4,200 feet long; an entrance channel 18 feet deep and 
300 feet wide from deep water in ocean to a point 1,500 
feet inside the outer end of existing north jetty; thence 
a channel 16 feet deep, 200 feet wide with additional 
widening at bends, and about 5 miles long, to a turning 
basin, 16 feet deep, 400 feet wide, and 600 feet long, opposite 
Suislaw dock at Florence; a channel 12 feet deep, 
150 feet wide from Florence to mile 16.5; and at River Mile 
15.5 a turning basin 12 feet deep, 300 feet wide and 500 
feet long. Mean lower low water is plane of reference. Tidal 
range between mean lower low water and mean higher 
high water at mouth of river is 7 feet and extreme about 
11 feet. During low stages of river, tidal effect extends to 
Mapleton, 20.5 miles above mouth. (For details relating 
to previous project see page 1988 of Annual Report for 
1915.) 
A modification to the existing project was authorized 
by Public Law 96-367, October 1, 1980. North and south 
jetty modifications were completed in FY 85. Modifications 
provide for extending the north and south jetties by 
1,900 and 2,300 feet respectively. The jetty extensions will 
terminate at approximately the minus 25-foot contour. 
Spur jetties were constructed on each jetty extension to 
reduce longshore currents from transporting material 
around the heads of the jetties. Each spur jetty is 400 feet 
long and originate approximately 900 feet shoreward of 
the jetty head. The north jetty spur is oriented 45 degrees 
to the north of the existing jetty alignment and the south 
jetty spur 45 degrees to the south of the jetty alignment. 
Estimated cost of jetty work is $30,727,000; $30,500,000 
Corps of Engineers, $183,000 non-Federal, and $44,000 
U.S. Coast Guard. 
Local cooperation. Complied with. 
Terminal facilities. Port dock at Florence, 150 feet 
wide and 350 feet long, is about 5.3 miles above river entrance 
and accommodates a fish-receiving station at east 
end of wharf which maintains a 2-ton capacity winch and 
supplies gasoline, oil and ice to fishermen. Other facilities 
at Florence consist of various floatways which provide 
docking facilities for fishing vessels and other small craft 
and a floating dock with accommodations for 75 commercial 
fishing vessels. Adjacent to commercial basin is mooring 
basin with accommodations for 200 sport boats of all 
sizes. 
Modern docks for loading ocean-going barges with 
packaged lumber is maintained at Mapleton and owned 
by the Davison Lumber Company. 
There are also a number of private landings and log 
booms between Cushman and Mapleton to accommodate 
37-8

PORTLAND, OREGON DISTRICT 
river traffic. These facilities are considered adequate for 
existing traffic. 
Operations during fiscal year. New work: Contractual 
work on extension of the north and south jetties completed 
in FY 86. 
Maintenance: U.S. hopper dredge Yaquina removed 
218,836 cubic yards of material. 
20. SKAMOKAWA CREEK, WA. 
Location. Rises in Wahkiakum County, in 
southwestern part of the State of Washington, flows 
southwesterly and southerly about 10 miles, and empties 
into Columbia River about 34 miles above mouth. (See 
NOAA Chart 18523.) 
Existing project. Provides for a channel 6.5 feet deep 
at low water and 75 feet wide, between Steamboat and 
Brooks Sloughs, about 1,600 feet long. Tidal range between 
mean lower low water and mean higher high water 
is about 7 feet and maximum variation of water level due 
to tides or freshets is about 12 feet. During ordinary 
freshets a stage of 12 feet is reached in creek at 
Skamokawa, WA. Project as authorized was completed in 
1920. 
Local cooperation. None required. 
Terminal facilities. There are several privately owned 
docks on Skamokawa Creek, Steamboat Slough, and 
Brooks Slough for use of towboats, commercial fishing 
vessels, and pleasure craft. 
Operations during fiscal year. Maintenance: Inspection 
performed. 
21. SKIPANON CHANNEL, OR 
Location. In tidal waterway extending south 2.7 miles 
from deep water in Columbia River. Channel enters Columbia 
about 10 miles above mouth and 4 miles below 
Astoria, OR. (See NOAA Chart 18523.) 
Existing project. Channel 30 feet deep and generally 
200 feet wide extending from deep water in Columbia 
River to railroad bridge at Warrenton, OR, distance of 1.8 
miles, turning basin of same depth, mooring basin 12 feet 
deep at mean lower low water at Warrenton, OR, and 
channel 6 feet deep, generally 40 feet wide, with increased 
widths at log dumps and terminals, for 4,500 feet via 
cutoff channel above railroad bridge. Channel is maintained 
to 16 feet which is adequate for user traffic. Mean lower 
low water is plane of reference. Tidal range between mean 
lower low water and mean higher high water is about 8 
feet, extreme is about 13 feet. 
Project as authorized is complete. Dredging river channel 
and turning basin was completed in 1939. Construction 
of small-boat mooring basin at Warrenton, OR, was 
completed October 1957, and fill stabilization work was 
accomplished in August 1958. 
Local cooperation. None required. 
Terminal facilities. City of Warrenton owns wharf 
with a 300-foot frontage open to public on equal terms. 
One privately owned cannery wharf with a 300-foot frontage 
is used for unloading fish and handling fish nets. One 
privately owned boatyard has floats and moorage facilities 
for use of a maximum of 80 small boats. Small-boat basin 
has facilities for numerous fishing and recreation craft, 
and a privately owned lumber mill has a barge loading 
facility for chips and lumber. Facilities, are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: U.S. 
hopper dredge Yaquina removed 19,785 cubic yards of 
material. 
22. TILLAMOOK BAY AND BAR, OR 
Location. Bay is on Oregon coast about 50 miles south 
of mouth of Columbia River. (See NOAA Charts 18520 and 
18558.) 
Existing project. Provides for a jetty about 5,700 feet 
long on north side of entrance and a jetty 8,000 feet long 
on south side; a channel through bar 18 feet deep and of 
such width as can be practically and economically obtained; 
for a channel 200 feet wide and 18 feet deep from deep 
water in bay to Miami Cove; and for initial dredging to 
12 feet deep of a small-boat basin and approach thereto 
at Garibaldi, OR. Project also provides for improvement 
of Bayocean Peninsula, OR, by construction of sand and 
rockfill dike 1.4 miles long, on alinement extending between 
Pitcher Point and town of Bayocean. Mean lower 
low water is plane of reference. Tidal range between mean 
lower low water and mean higher high water is 8 feet, extreme 
is about 14 feet. Hobsonville Channel portion of project 
is inactive. 
Except for construction of Hobsonville Channel portion, 
classified inactive, channels were completed in 1927, north 
jetty in 1933, improvement of Bayocean Peninsula in 1956, 
and small-boat basin in 1958. Rehabilitation of north jetty 
was accomplished September 1965. Construction of 
south jetty was initiated April 1969 and was completed 
in September 1979. 18 foot channel to Miami Cove is inactive 
due to mill closure. (For details relating to previous 
projects, see page 1989 of Annual Report for 1915 and page 
1474 of Annual Report for 1936.) 
Local cooperation. Fully complied with. Requirements 
are described in full on page 37-9 of FY 1981 
Annual Report. 
Terminal facilities. At Garibaldi: A facility owned by 
the Port of Bay City, for shipping lumber and receiving 
logs, a public landing suitable for mooring fishing vessels, 
towboats, and other craft. Small-boat basin has adequate 
facilities for mooring fishing and recreational craft. A 
privately owned boat ramp and moorage is available for 
recreational craft. 
At Bay City: A privately owned wharf used exclusively 
for receipt of fresh fish and shellfish. Facilities considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports. 
23. UMPQUA RIVER, OR 
Location. Rises in Cascade Range, flows westerly about 
120 miles, and empties into Pacific Ocean 180 miles south 
of Columbia River and 465 miles north of San Francisco 
Bay. (See NOAA Charts 18580 and 18584.) 
37-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Existing project. A jetty on north side of entrance 
about 8,000 feet long, a south jetty 4,200 feet long extending 
to a point 1,800 feet south of outer end of north jetty; 
dredging to provide a usable entrance channel 26 feet 
deep, and a river channel 22 feet deep and 200 feet wide, 
from mouth to Reedsport, a distance of about 12 miles 
with a turning basin at Reedsport 1,000 feet long, 600 feet 
wide, and 22 feet deep; deepening of channel at Winchester 
Bay to 16 feet deep by 100 feet wide for 3,100 feet, 
then adding 16 feet deep by 100 feet wide for 500 feet, 
and 12 feet deep by 75 feet wide for 950 feet beyond boat 
basin making up the East Boat Channel. A new West Boat 
Channel was added 16 feet deep by 100 feet wide for 4,300 
feet and completed in 1984. Project was modified in 1954 
to provide a channel in Scholfield River, but this portion 
of the project is currently inactive. Mean lower low water 
is plane of reference. Tidal range between mean lower low 
water and mean higher high water at river mouth is 7 
feet, and extreme range is about 11 feet. 
North jetty was completed in 1930. Extension to 
original south jetty was completed in 1938. Dredging a 
22-foot channel from mouth of river to Reedsport was completed 
in 1941. Gardiner Channel and turning basin was 
completed in 1949 and Winchester Bay Channel and 
mooring basin in 1956. The 12-foot channel in Scholfield 
River is currently classified inactive. Rehabilitation of 
south jetty was completed August 1963. Extension of 
training jetty was completed October 9, 1980. Deepening 
Winchester Bay East Channel and new West Channel 
completed 1984 under Section 107. (For details relating 
to previous projects see page 2967 of Annual Report for 
1898 and page 1732 of Annual Report for 1938.) 
Local cooperation. None required. 
Terminal facilities. At Gardiner there is about 650 feet 
of wharf frontage. Also, there is an oil unloading facility 
owned by International Paper Co. for exclusive use of 
tanker barges. Port of Umpqua owns one wharf with 456 
feet of water frontage, of which 228 feet is usable for 
vessels and another with about 75 feet of water frontage 
which has not been used generally for commercial 
shipping. 
On Bolon Island across the river from Reedsport a 
wharf was constructed which has about 5 acres of open 
storage for lumber and available to all on equal terms. 
At Winchester Bay, 2 miles from river entrance there 
is a major sports and commercial fishing harbor. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. New work: Final fiscal 
requirements were completed. 
Maintenance: U.S. hopper dredge Yaquina removed 
263,028 cubic yards of material. Repairs to breakwater 
near the inshore end of the training jetty initiated. 
24. WILLAMETTE RIVER AT WILLAMETTE 
FALLS, OR 
Location. Locks and dam covered by this project are 
at Willamette Falls, a rocky reef in Willamette River at 
Oregon City, OR, about 26 miles above mouth of river. 
Existing project. Provides for construction of a new 
single-lift main lock and a guard lock each with clear 
dimensions of 56 by 400 feet and a minimum depth over 
sills of 9.5 feet, to replace existing facilities which were 
provided for by purchase, rehabilitation, and deepening 
to 6 feet at low water of existing canal and locks and 
separation of canal from waterpower intake by construction 
of a concrete division wall. Construction of a new lock 
has been deauthorized. The existing locks are on the National 
Register for historic sites. Total length of existing 
canals and locks is about 3,500 feet. Principal features 
of existing canal and locks at Willamette Falls are set 
forth in Table 37-K. Ordinary fluctuation of stage of water 
above locks is 12 feet and extreme, due to flood conditions, 
20 feet. Below locks, ordinary fluctuation is 15 feet and 
extreme 50 feet. 
Canal and locks originally constructed by private interests 
in 1873 were purchased by the United States in 
April 1915 for $375,000. Final report on purchase and 
rehabilitation of canal and locks is in Annual Report for 
1923, when project was reported 98 percent complete. 
Replacement of gates Nos. 6 and 7 was completed August 
1967 under minor rehabilitation funds. Existing locks and 
grounds are in fair condition and in continuous operation 
except when flooded out by high water or undergoing 
repair. 
Local cooperation. Fully complied with. 
Terminal facilities. James River Paper has a timber 
wharf about 850 feet long, extending to and supported by 
a concrete division wall built in lock canal by the United 
States. This wharf is used for receiving mill supplies and 
shipping paper and paper products. 
Operations during fiscal year. Normal operation and 
maintenance performed. Traffic through lock totaled 
802,937 tons during calendar year 1985. 
25. YAQUINA BAY AND HARBOR, OR 
Location. Bay is on Oregon coast, 113 miles south of 
mouth of Columbia River. (See NOAA Charts 18580 and 
18581.) 
Existing project. Two high tide rubblemound jetties 
at entrance, north jetty 7,000 feet, and south jetty 8,600 
feet long; a spur jetty on channel side of south jetty 4,700 
feet from its sea end, 800 feet long; five groins channelward 
from south jetty; channel 40 feet deep for a 
general width of 400 feet across bar and at outer end of 
entrance channel; a channel 30 feet deep and 300 feet 
wide to a turning basin of same depth, 900 to 1,200 feet 
wide and 1,400 feet long, and a channel 18 feet deep and 
200 feet wide from 30-foot channel at about mile 2.4, 
thence upstream to abandoned railroad terminus at Yaquina, 
a distance of about 4.5 miles. Project also provides 
for two small boat mooring basins at Newport, OR. Mean 
lower low water is plane of reference. Tidal range between 
mean lower low water and mean higher high water is 8 
feet and extreme is about 12 feet. At mile 1.2 a 1,300 foot 
long breakwater protecting the Port of Newport South 
Beach Marina together with an entrance channel 8 feet 
long by 100 feet wide for a distance of 2,035 feet. 
37-10

PORTLAND, OREGON DISTRICT 
Project as originally authorized was completed in May 
1952. Restoration of jetties was completed in 1934 and extension 
of north jetty 1,000 feet seaward was completed 
in 1940. Construction of mooring basin at Newport and 
dredging of channel and turning basin to project dimensions 
were completed during fiscal year 1949. Restoration 
of north jetty was again accomplished in 1956. Under 
modification of July 3, 1958, extension of north jetty was 
completed in September 1966, dredging of 40-foot bar 
channel and 30-foot river channel was completed in October 
1968, and extension of south jetty was completed 
in June 1972. (For details relating to previous projects see 
Annual Report for 1893, part 4, page 3314, and Annual 
Report for 1938, page 1736.) 
Local cooperation. None required. 
Terminal facilities. At McLean Point, on north side 
of bay, about 2 miles from entrance, Port of Newport has 
two berths capable of serving ocean-going vessels, one 435 
feet long, the second 520 feet long. At the time the second 
berth was dredged, a retaining wall and fill of 6 acres were 
constructed adjacent to deep water. There now is 40 acres 
of filled land adjacent to deep water, and of this total, 7 
acres were constructed in 1956-57. This facility has 
necessary carriers and lift trucks for handling 
lumber cargoes, warehouse for covered cargo storage, 
and is open to all on equal terms. 
Port of Newport also has a public wharf with 300 feet 
of frontage for servicing fishing boats. In addition, Port 
of Newport maintains 510 berths for mooring commercial 
and sport fishing vessels. There are several seafood companies 
on the bay which have their own facilities for 
handling fresh fish and crab. Supplies and petroleum products 
are readily available for small vessels. On south side 
of bay about 1.2 miles above entrance, Port of Newport 
has constructed South Beach Marina which can handle 
approximately 600 pleasure craft and shallow draft 
fishing boats. Public facilities include public automobile 
and boat trailer parking, boat launching ramp, fuel dock, 
fishing pier, and picnic area. A dry boat moorage for 120 
boats, is completed. A swing hoist with 3-ton capacity is 
currently available and one with 60-ton capacity is 
planned. 
About 1.5 miles above entrance, Oregon Aqua Foods, 
subsidiary of Weyerhaeuser Company, maintains a commercial 
fish farm facility. 
About 2.0 miles above entrance, Oregon State University, 
in conjunction with the Marine Science Center on 
52 acres, maintains a 220-foot pier for docking large and 
small research vessels and a 100-foot float for docking 
small boats. Docking facilities are restricted to research 
vessels and State of Oregon small boats. 
Operations during fiscal year. Maintenance: U.S. 
hopper dredge Yaquina removed 27,131 cubic yards and 
the contract hopper dredge Atchafalaya removed 210,232 
cubic yards of material. 
26. APPLEGATE LAKE, ROGUE RIVER BASIN, 
OR 
Location. In Jackson County, OR, on Upper Applegate 
River, a tributary of Rogue River, at River Mile 46, about 
23 airline miles southwest of Medford, OR. 
Existing project. A gravel-fill embankment dam, 242 
feet high from streambed to crest with an overall length 
of 1,300 feet. A gate-controlled concrete chute-type 
spillway on the left abutment, and a regulating outlet conduit, 
and intake tower with multilevel intakes on the left 
side of valley floor. Lake, 5 miles long, provides 75,000 
acre-feet of usable storage for flood control and water conservation 
utilization. Project controls runoff from a 
drainage area of 223 square miles. In addition to flood control, 
reservoir is operated to provide irrigation, fish and 
wildlife enhancement, water quality control, and recreation 
benefits. Recreation facilities were provided by the 
Corps of Engineers with operation and maintenance by 
the USFS under a memorandum of agreement. Project is 
complete and operating. 
Local cooperation. Authorizing act requires that 
State of Oregon insure maintenance of stream flow released 
for fishery. In addition, costs allocated to irrigation 
would have to be repaid in a manner and to an extent consistent 
with reclamation laws and policies. Oregon Department 
of Fish and Wildlife made filing May 31, 1962 with 
State Engineer for water rights for use of stored water 
and natural flows for fish habitat improvement in 
amounts and at times specified in project authorization. 
The U.S. Bureau of Reclamation has made a feasibility 
study of Applegate Irrigation Division. The results of the 
study indicate that at present there does not appear to 
be a feasible Federal irrigation project for the Applegate 
River valley. Local interests have furnished all local 
cooperation specified by the 1970 Flood Control Act. The 
assurances were approved by the Secretary of the Army 
on May 8, 1975. 
Operations during fiscal year. Maintenance: Normal 
operation and maintenance was performed. Freshets 
regulated by Applegate Lake on Applegate River and 
Rogue River are shown in Table 37-M. 
27. BLUE RIVER LAKE, OR 
Location. On Blue River, a major tributary of McKenzie 
River, 1.8 miles above confluence of the two streams 
at the confluence of Quartz Creek and Blue River and 
about 42 miles easterly of Eugene, OR. 
Existing project. A gravel-fill embankment dam 1,329 
feet long at crest including spillway and 319 feet above 
the lowest point of the general foundation. A concrete 
gravity chute-type spillway with two gates is located on 
left abutment. Outlet works are in left abutment. On left 
shore of reservoir an earth-and-gravel fill embankment, 
about 1,535 feet long and 70 feet high, closes a low 
saddle between Blue River and McKenzie River. Project 
controls runoff from drainage area of 88 square miles. 
Reservoir provides 85,000 acre-feet of usable flood control 
storage and is operated as a unit of coordinated reservoir 
system to protect Willamette River Valley and increase 
low waterflows for navigation and other purposes. Recreation 
facilities are provided by the U.S. Forest Service under 
a Memorandum of Agreement. Project is complete. Construction 
of dam and appurtenant works was initiated in 
37-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
May 1963 and operation for flood control was effective in 
October 1968. Settlement of claims was completed in May 
1974. Eugene Water and Electric Board made an application 
in April 1982 for permit to install two small 
hydropower units at Blue River Lake project. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Normal 
operation and maintenance work performed. Freshets 
regulated by Blue River Lake project on Blue River, a major 
tributary of McKenzie River, are shown in Table 37-M. 
28. COTTAGE GROVE LAKE, OR 
Location. On Coast Fork of Willamette River, 29 miles 
from mouth. Coast Fork rises in Douglas County, OR, on 
western slope of Cascade Range and northern slope of 
Calapooia Range, flows north for 49 miles, and unites with 
Middle Fork to form main Willamette River. 
Existing project. An earthfill dam, 1,750 feet long at 
crest, 114 feet high from lowest point of the general foundation, 
a concrete gravity free overflow spillway 264 feet 
long near the right abutment, and a concrete gravity nonoverflow 
section 96 feet long forming the right abutment. 
Total length of dam is 2,110 feet. Outlet works, consisting 
of three gate-controlled conduits, pass through spillway 
section. Reservoir provides 30,060 acre-feet of usable flood 
control storage and controls runoff of drainage area of 104 
square miles. Project is operated as a unit of coordinated 
reservoir system to protect Willamette River Valley and 
increase low waterflow for navigation and for other purposes. 
Recreational development consists of day use and 
overnight facilities at four sites operated by the Corps of 
Engineers. Construction of project initiated August 1940 
was completed April 1952. Dam and reservoir have been 
in continuous operation since September 1942. 
Local cooperation. Development of additional recreation 
facilities will require a local sponsor willing to cost 
share and assume all operation and maintenance of park 
facilities. 
Operations during fiscal year. Maintenance: Normal 
operation and maintenance work performed. Freshets 
regulated by Cottage Grove Lake on Coast Fork 
Willamette River are shown in Table 37-M. 
29. DORENA LAKE, OR 
Location. On Row River, OR, 7 miles from mouth. Row 
River rises in Lane County on western slope of Cascade 
Range, flows northwest for 19 miles, and enters Coast Fork 
of Willamette River 19.5 miles above mouth. 
Existing project. An earthfill embankment dam, 
3,352 feet long at crest and 145 feet high from lowest point 
of the general foundation. Concrete gravity free-overflow 
spillway, 200 feet long, forms right abutment. Outlet 
works on five slide-gate-controlled conduits pass through 
spillway section. Reservoir provides 70,500 acre-feet of 
usable flood control storage and controls runoff of 265 
square miles. The Project is operated as a unit of coordinated 
reservoir system to protect Willamette River 
Valley and increase low waterflows for navigation and 
other purposes. Construction of project initiated June 
1941 was completed October 1952 except for construction 
of additional recreation facilities that were funded under 
the Code 710 program. Future recreation facility construction 
will be accomplished in accordance with the costsharing 
contract with Lane County, OR. Dam and reservoir 
have been in continuous operation since November 
1949. 
Local cooperation. A multiple project cost sharing 
agreement has been inforce with Lane County since Sept. 
1976. It includes 4 projects and 13 parks. At Dorena Lake, 
6 parks included in the agreement are managed by Lane 
County under a lease agreement. Future recreation 
development will require a supplement to the cost sharing 
agreement.. 
Operations during fiscal year. Maintenance: Normal 
operation and maintenance work performed. Freshets 
regulated by Dorena Lake project on Row and Coast Fork 
Willamette Rivers are shown in Table 37-M. 
30. ELK CREEK LAKE, ROGUE RIVER BASIN, OR 
Location. In Jackson County, OR at River Mile 1.7 on 
Elk Creek, a tributary of Rogue River, about 26.5 miles 
northerly from Medford, OR. 
Existing project. Construction work continues to provide 
for a 249-foot high roller compacted concrete gravity 
dam, 2,600 feet long at the crest, with a gate controlled 
concrete chute spillway, regulating outlet conduits, 
power penstock and multiple use intake tower attached 
to the upstream face of the dam. Reservoir 6.2 miles long 
will provide 95,000 acre-feet of usable storage for flood control 
and water conservation utilization. Project will control 
runoff from a drainage area of 135 square miles. 
Reservoir will be operated to provide future municipal and 
industrial water supply, irrigation, fish and wildlife 
enhancement, water quality control, and recreation 
benefits. 
Construction of the project was initiated in February 
1971. Work completed to date includes construction of a 
bypass road to route traffic away from the damsite and 
stockpiling of gravels to be used in the main dam and 
relocated roads. All lands for the project have been acquired 
with the exception of the clearing of water rights 
for a seemingly abandoned irrigation canal which 
originates within the project boundaries. Final environmental 
statement was filed with Council of Environmental 
Quality June 15, 1972 and Supplement No. 
1 addressing water quality and social/demographic information 
was filed with EPA on December 24, 1980. 
Estimated Federal cost of project is $120,000,000. 
Local cooperation. Authorizing act requires that 
State of Oregon take action prior to construction to insure 
maintenance in stream of flow to be released for 
fishery. In addition, costs allocated to irrigation would 
have to be repaid in a manner and to an extent consistent 
with the U.S. Bureau of Reclamation laws and 
policies. On February 24, 1966, State of Oregon Water 
Resources Board filed for withdrawal rights of 25 cubic 
feet per second to maintain minimum flow for fish. 
Development of recreation facilities require a local sponsor 
37-12

PORTLAND, OREGON DISTRICT 
willing to cost share in recreation development and 
assume all operations and maintenance of park facilities. 
Operations during fiscal year. New work: Relocated 
county roadwork has essentially been completed. Main 
dam contract was awarded to Ohbayashi Corp. in January 
1986 in the amount of $63.7 million. The contractor has 
completed dam site clearing, excavation of foundation and 
is currently placing concrete in the regulating outlet of 
the dam. A reservoir clearing contract is scheduled to be 
awarded Spring 1987. 
31. FALL CREEK LAKE, OR 
Location. On Fall Creek, a tributary of Middle Fork 
Willamette River, about 7 miles above confluence of the 
streams and about 19 miles southeasterly of Eugene, OR. 
Existing project. An earth-and-gravel fill embankment 
about 5,100 feet long at crest and 193 feet high from 
lowest point of the general foundation. A gated concrete 
gravity spillway is in left abutment. Outlet is in right 
abutment. Reservoir provides 115,000 acre-feet of usable 
flood control storage and is operated as a unit of coordinated 
reservoir system to protect Willamette River 
Valley and increase low waterflows for navigation and 
other purposes. 
Construction of project began May 1962 and was essentially 
complete November 1965. Reservoir storage for flood 
control was effective October 1965. Sky Camp Lodge was 
completed October 1978. Future recreation facilities will 
be provided in accordance with the cost-sharing contracts 
with Lane County and Bethel School District. 
Local cooperation. Fall Creek Lake is included in the 
Lane County multiple project cost sharing agreement. 
Two parks are managed by Lane County under lease 
agreement. Future development will require a supplement 
to the cost sharing agreement. 
Operations during fiscal year. Maintenance: Normal 
operation and maintenance work performed. Freshets 
regulated by Fall Creek Lake project on Fall Creek, a 
tributary of Middle Fork, Willamette River, are shown in 
Table 37-M. 
32. FERN RIDGE LAKE, OR 
Location. On Long Tom River, 23.6 miles from the 
mouth. Long Tom River rises in Lane County, OR, on 
eastern slope of Coast Range, flows north for 50 miles, and 
enters Willamette River 147 miles above its mouth. 
Existing project. A main dam, 6,624 feet long at crest 
and 49 feet high from lowest point of the general foundation 
and two auxiliary dikes, 915 and 3,929 feet long, 
along northeasterly boundary of lake. Main dam consists 
of an earthfill embankment dam 6,330 feet long, a concrete 
gravity spillway near left abutment with a nonoverflow 
structure 46 feet long, containing outlet works, 
and an overflow structure, 248 feet long, controlled by six 
automatic gates. Project includes rectification of channel 
of Long Tom River downstream of dam. Reservoir provides 
110,000 acre-feet of usable flood control storage and controls 
runoff of tributary drainage area of 275 square miles. 
Reservoir protects Long Tom River Valley and is operated 
as a unit of coordinated reservoir system to protect 
Willamette River Valley generally and to increase low 
water-flows for navigation and other purposes. Dam was 
originally constructed in 1941 to height of 47 feet. Provision 
of additional storage for flood control was obtained 
in 1965 by raising embankments 2 feet to 49 feet above 
lowest point of the general foundation. 
Construction of project initiated April 1940 was completed 
August 1951, except for provision of additional 
storage for flood control authorized in 1962 and completed 
April 1965, and construction of additional recreation 
facilities funded through the Code 710 program. Dam and 
reservoir have been in continuous operation since 
December 1941. Development of future recreation 
facilities will be in accordance with the cost-sharing contract 
with Lane County, and requires a 50 percent contribution 
by the county. Development is subject to 
availability of funds by the Government and the county. 
Local cooperation. Fern Ridge Lake is included in the 
Lane County multiple project cost sharing areeement. 
Three parks are managed by Lane County under lease 
agreements. Future development will require a supplement 
to the cost sharing argreement. The Oregon Department 
of Fish and Wildlife manages 5,000 acres of land 
and water for migratory water fowl under a lease 
agreement. 
Operations during fiscal year. Maintenance: Normal 
operation and maintenance work performed. Freshets 
regulated by Fern Ridge Lake project on Long Tom River 
are shown in Table 37-M. 
33. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 205, 
Public Law 858, 80th Cong., as amended 
(preauthorization). 
See Table 37-L. 
Emergency bank protection (Section 14 of 1946 
Flood Control Act, Public Law 526, 79th Cong.). 
Fiscal year costs for preauthorization studies were: 
Pudding River, Anderson Road, OR, $186. 
Emergency flood control activities-repair, flood 
fighting and rescue work (Public Law 99, 84th Congress 
and antecedent legislation). 
Federal costs for fiscal year were: $270,740, disaster 
preparedness; $-10,250, emergency operations; $177,666, 
rehabilitation; $222,670, advance measures. Contributed 
funds for levee raising were $120. 
Mt. St. Helens Emergency Measures. The May 18, 
1980 eruption of Mt. St. Helens dramatically altered the 
hydraulic and hydrologic regimes of the Cowlitz and Toutle 
River valleys. Volcanic debris substantially reduced the 
river's hydraulic capacity to the point where major 
flooding could be expected even with normal runoff. 
A major recovery program for the Cowlitz and Toutle 
Rivers funded under advance measures was initiated a 
37-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
short time after the eruption and was essentially completed 
during FY 1982. 
Total cost of Mt. St. Helens emergency measures, from 
initiation through FY 1986, with some contract modifications 
remaining to be negotiated, is $275,727,000. The 
authorized navigation channel on the Cowlitz between 
River Mile 0 and 4.2 remains unusable due to continued 
sedimentation. 
Spirit Lake, WA. Portland District was directed on 
August 24, 1982 to respond to the Presidential declaration 
of a State of Emergency for the Spirit Lake area. This 
declaration was precipitated by the release of a U.S. Forest 
Service Spirit Lake Interagency Task Force report assessing 
the flood hazard posed by that body of water, which 
has been without a natural outlet since the May 18, 1980 
eruption of Mt. St. Helens. The report concluded that 
Spirit Lake would fill to an extremely dangerous level by 
as early as Spring 1983 and also mentioned concern over 
the structural stability of the debris plug holding back 
the lake due to the development of an extensive system 
of deep erosion gullies on its surface, some as deep as 40 
feet. 
To contain the threat of a possible devastating flood 
caused by a failure of the Spirit Lake debris plug, and in 
response to a tasking from the Federal Emergency 
Management Agency (FEMA), the Portland District initiated 
a program aimed at meeting two objectives: (a) 
undertake interim measures to assure that the lake is not 
allowed to continue rising unchecked so that the threat 
of a possible flood during 1983 is averted, and, (b) perform 
field investigations and preliminary design work 
necessary to make a recommendation to FEMA for a permanent 
solution to the threat of flooding from Spirit Lake. 
An interim solution was implemented to maintain the 
lake at a safe level through pumping water from the lake 
from October to July each year. 
A comprehensive plan for long-term flood control and 
navigation maintenance, as a result of the Mt. St. Helens 
eruption, was completed in 1983. This document included 
alternative methods of eliminating the threat of 
catastrophic flooding due to the unstable avalanche debris 
dam at Spirit Lake. 
A decision document selecting the final plan for responding 
to this threat was completed in February 1984. This 
plan called for the construction of an 8,500-foot-long tunnel 
through Harry's Ridge to permanently maintain 
Spirit Lake at a safe level. 
Until the tunnel was completed in April 1985, the lake 
elevation was maintained through pumping from a bargemounted 
pumping plant at Spirit Lake. Pumping was 
discontinued on April 1, 1985. A contract was initiated 
in August 1985 to restore the pumping area to a natural 
condition. The total cost for pumping and pump site 
restoration through FY 86 is $11,630,000. 
Construction of the tunnel began in June 1984. The 
tunnel began operating on May 6, 1985, and the lake was 
lowered by 20 feet to the design elevation of 3,400 by 
September 1985. The cost for tunnel construction through 
FY 86 is $13,716,000. 
34. INSPECTION OF COMPLETED FLOOD CONTROL 
PROJECTS 
Funds appropriated for inspection of completed local 
flood protection works are used to determine maintenance 
condition of completed works and to ascertain whether 
those works are being properly maintained by local interests. 
A total of 57 leveed areas and 264 bank protection 
works were inspected at various locations along both 
banks of Lower Columbia River below Bonneville Dam, 
along Oregon Coast, in eastern Oregon, in southern 
Oregon and in Willamette River Basin. Of this total, 10 
leveed areas in Oregon and 42 leveed areas in Washington 
were inspected during FY 1986. A representative of sponsoring 
districts accompanied the Portland District 
representatives performing the levee inspections. Aerial 
inspection of revetments in Willamette River Basin was 
supplemented by an onsite inspection at locations requiring 
maintenance. Deficiencies in maintenance and need 
for repairs were discussed with sponsoring districts' 
representatives and a report was made to each sponsor 
with recommendations for improving maintenance. The 
program to improve maintenance of completed Federal 
projects initiated by House Appropriations Committee on 
Civil Functions was continued. Periodic contact was maintained 
with uncooperative areas reported in FY 1985 and 
1986 to ascertain any change in attitude and to provide 
technical assistance, if requested. Of the 81 sponsors for 
some 125 local flood protection projects inspected in 
Portland District, 15 were reported deficient in 
maintenance. Fiscal year costs were $96,311 and total 
costs to September 30, 1986 were $1,247,288. 
35. INSPECTION OF COMPLETED PL-99 WORKS 
Annual inspections are made of levees, flood control 
structures, and communities that have received previous 
assistance under the various features of Public Law 84-99 
(flood fights, levee rehabilitation, advance measures). Inspections 
involve determining physical condition of levees 
and other structures, riprap displacement and vegetation 
control. Inspections also serve a valuable disaster 
preparedness function in terms of explaining to local interests 
their preparedness responsibilities and criteria for 
qualifying for future emergency assistance under PL 
84-99. Local sponsors are advised of results of inspections. 
Approximately 52 locations throughout the Portland 
District were inspected under this feature during FY 
1986, at a cost of $78,653. 
36. JOHN DAY RIVER (WEST), OR 
Location. Left bank of John Day River Road location, 
on the left bank of John Day River (West) mile 2.3, approximately 
4 miles east of Astoria, OR. Work would be 
accomplished under the authority of Section 14 of the 
1946 Flood Control Act, as amended. 
Existing Project: Plan of improvement provides protection 
for 776 linear feet of bankline from erosion at John 
Day River Road location with quarry stone embankment. 
A layer of filter fabric will be placed on the damaged bank 
to provide support for the stone. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Final fiscal 
requirements were completed. 
37-14

PORTLAND, OREGON DISTRICT 
37. LOWER COLUMBIA RIVER BASIN, OR AND 
WA 
Location. On Columbia River and minor tributaries, 
channels, and sloughs, between Sandy River, OR, about 
15 miles east of Vancouver, WA, and mouth of Columbia 
River. 
Existing project. Plan for bank protection work, improvements 
to existing projects, and construction of flood 
control works in Lower Columbia River Basin provides 
for new construction and supplementing and extending 
projects constructed in Lower Columbia River Basin under 
authority of 1936 Flood Control Act: (a) Lower Columbia 
River Bank Protection, OR and WA provides for bank protection 
works at 96 locations on Columbia River and 
tributaries between Sandy River and mouth of Columbia 
River, totaling about 224,000 linear feet. Estimated total 
Federal cost is $25,600,000 and non-Federal cost is 
$269,000; (b) See Table 37-N on Levees and Improvements 
to Existing Works; (c) Lower Columbia River Basin levees 
at new locations, Oregon and Washington, provides for 
construction of flood control works at: Washougal area, 
Clark County, WA, about 5.5 miles of levee and appurtenant 
works at a Federal cost of $1,803,488, and non- 
Federal cost at $98,000; and Vancouver Lake area in 
vicinity of Vancouver, WA, about 18 miles of levee and appurtenant 
works at an estimated Federal cost (1980) of 
$19,500,000 and non-Federal cost at $900,000. This portion, 
Vancouver Lake, WA, has been reclassified "deferred". 
Total estimated Federal costs (1980) for both areas 
of work are $21,303,488 and non-Federal costs $998,000. 
Federal cost for all work under project, Lower Columbia 
River Basin, OR, and WA, is $67,458,776. 
Construction of improvement to existing project in Sandy 
Drainage District, OR, was completed by local interests 
at no construction cost to the Government. Improvements 
of levees have been accomplished by contract at the following 
locations: Multnomah County Drainage District, No. 
1, OR, June 1962; Sauvie Island Drainage District, OR, 
October 1962; Woodson Drainage District, OR, December 
1963; Rainier Drainage District, OR, June 1964; Cowlitz 
County Diking Improvement District, No. 15, WA, 
December 1965; Cowlitz County Diking Improvement 
Districts, Nos. 2 and 13, WA, June 1965; Midland 
Drainage District, OR, April 1967; Cowlitz County Consolidated 
Diking Improvement District, No. 2, WA, June 
1974; Beaver Drainage District, OR, June 1978; 
Wahkiakum County Consolidated Diking District #1, WA, 
October 1979; and Scappoose Drainage District, OR, 
September 1980. Washougal Area, WA, (new location) 
levee construction has been completed. Under authorization 
for Lower Columbia River Basin bank protection 
works, construction has been completed at numerous locations. 
(See Section 44 for additional information). 
Local cooperation. Flood Control act of 1950 provides 
local interests furnish lands and rights-of-way; make 
necessary highway, highway bridge, and utility alterations; 
hold the United States free from damages; and 
maintain and operate completed works. Total non-Federal 
cost for all work is $4,567,000. For details of status or requirements 
of local cooperation see individual project reports. 
Operations during fiscal year. See individual 
projects. 
38. LOWER COLUMBIA RIVER BASIN BANK 
PROTECTION, OR AND WA 
Location. On Columbia River and tributaries between 
Sandy River, OR, and mouth of Columbia River. 
Existing project. Provides for construction of 224,000 
linear feet of bank protection works at 96 locations along 
Lower Columbia River below River Mile 125 and along 
principal tributaries in this reach, to protect existing improvements 
such as levees and developed industrial lands 
from further erosion. Existing project is a unit of general 
comprehensive plan for flood control, navigation, and 
other purposes in Columbia River Basin. Construction of 
project began in July 1961 and is 88 percent complete. A 
total of 191,000 linear feet of bank protection work at 84 
locations has been completed. Estimated Federal cost is 
$25,600,000. 
Local cooperation. Flood Control Act of 1950 provides 
local interests furnish lands and rights-of-way; make 
necessary highway, highway bridge, and utility alterations; 
hold the United States free from damages; and 
maintain and operate works after completion. Estimated 
costs for all requirements of local cooperation are 
$267,000. 
Operations during fiscal year. Tansy Railroad location 
near the cities of Hammond and Warrenton, OR was 
completed (3,840 linear feet). Protective work as Lerch 
location (700 linear feet) on Sauvie Island Drainage 
District, and 128th Avenue location (250 linear feet) at 
Multnomah County Drainage District No. 1 was initiated. 
39. MOUNT ST. HELENS & VICINITY, WA 
Location. Along the Cowlitz and Toutle Rivers from 
Spirit Lake at the base of Mt. St. Helens to the confluence 
of the Cowlitz with the Columbia River (River Mile 68) 
approximately 55 miles downstream from Portland, OR. 
Existing project. The May 18, 1980 eruption of Mt. 
St. Helens dramatically altered the hydraulic and 
hydrologic regimes of the Cowlitz and Toutle River valley. 
Mudflows triggered by the eruption carried large volumes 
of sediment from the debris avalanche into these river 
valleys, reducing the hydraulic capacity to the point where 
major flooding could be expected with even normal runoff. 
Storm runoff and surface drainage continue to deliver 
sediment from the debris avalanche into the rivers. Funds 
allocated under Public Law 84-99 were used for major 
recovery work on the Cowlitz and Toutle rivers. 
In late FY 1983, interim flood control measures were 
implemented under the authority of Public Law 98-63 to 
assure 100-year flood protection to developed areas along 
the Cowlitz River. Measures implemented are primarily 
dredging on the Cowlitz and Toutle Rivers and a monitoring 
program. 
Local cooperation. Local sponsors are responsible for 
obtaining any additional lands easements and rights-ofway. 
The State of Washington has agreed to act as the 
local sponsor. State funds have been appropriated for 
37-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
acquisition of lands and related expenses for Mt. St. 
Helens recovery operations. The State of Washington has 
spent over $2,500,000 to procure disposal sites for dredged 
material. 
Operations during fiscal year. A contract to remove 
4.0 million cubic yards of sediment from the LT-3 site on 
the Toutle River was awarded in late September 1985. A 
total of 3.3 million cubic yards was removed at LT-3 
through March 1986, at a cost of $4,323,000. Two additional 
contracts to remove sediment from LT-1, and LT-3 
are underway at this time. 
40. MT. ST. HELENS SEDIMENT CONTROL, WA 
Location. On the North Fork Toutle River, 2 miles 
upstream from its confluence with the Green River, in 
Cowlitz County, southwest Washington. The river systems 
impacted by the project include Toutle, Cowlitz and Columbia 
Rivers. Most of the population affected by the proplems 
reside in the communities of Longview, Kelso, Lexington 
and Castle Rock, Washington. 
Existing Project. The proejct was authorized by the 
Supplement Appropriations Act, 1985 (Public Law 88, 
99th Congress, August 15, 1985). The Act includes 
authorization "...to construct, operate and maintain a sediment 
retention structure near the confluence of the Toutle 
and Green Rivers, Washington, with such design 
features and associated downstream actions as are 
necessary, in accordance with the Feasibility Report of the 
Chief of Engineers dated December 1984." 
The project will provide a permanent solution to potential 
flooding on the Cowlitz River from sedimentation problems 
created by the eruption of Mt. St. Helens. The Decision 
Document recommended construction of a single sediment 
retention structure with a 125-foot high spillway at 
the Green River site on the North Fork Toutle River, improvements 
to the levee system at Kelso, Washington, and 
dredging downstream from the SRS. 
Local cooperation. Local interests are responsible for 
provision of all lands, easements, and rights-of-way for the 
sediment retention structure, dredging disposal areas, and 
levee improvements. Local interests are also responsible 
for all alterations and relocations of buildings, roads, 
bridges and other structures or utilities made necessary 
by implementation of the project. In addition, operation 
and maintenance of fish facilities, the levee system at 
Kelso and dredged material disposal sites will be the 
responsibility of local interests. Non-federal cash contribution 
is $3,500,000 and the estimated non-federal 
land, easements, right-of-ways, and relocations costs 
are $21,000,000. 
Operations during fiscal year: Work on the Sediment 
Retention Structure site clearing contract was 
initiated in FY 86. Advanced Engineering and Design 
was completed during FY 86 and construction was 
authorized in July 1986. 
41. SCHEDULING FLOOD CONTROL RESERVOIR 
OPERATIONS 
Corps of Engineers monitored flood control operations 
at four Bureau of Reclamation projects (Prineville, Ochoco, 
Emigrant, and Scoggins) and (Mossyrock) a municipal 
power project operated by Tacoma City Light. The Bureau 
of Reclamation projects were partially constructed with 
flood control funds, thereby subjecting project operation 
to monitoring by the Corps of Engineers under Section 
7, Flood Control Act of 1944. Monitoring of Mossyrock 
flood control operation is assigned to the Corps by the 
Federal Energy Regulatory Commission as the Mossyrock 
license calls for specific flood control regulation. Under 
licensing agreement, the Tacoma City Light utility is required 
to provide 360,000 acre-feet of flood storage by 
December of each year. The Bureau of Reclamation sponsored 
projects were operated satisfactorily during FY 1986 
for flood control. At Mossyrock there were two high water 
periods in 1986. During the last week of October to the 
10th of November 1985, reservoir regulation stored approximately 
224,000 acre-feet at Mossyrock. Peak 
discharges at Castle Rock were below the regulation goal 
of 70,000 cubic feet per second during the flood season. 
Unregulated flows would have also been 82,000 cubic feet. 
The spring snowmelt runoff was much below normal with 
very little precipitation during October through December 
period. Preparation of Reservoir Regulation Manuals for 
Scoggins and Mossyrock Projects is scheduled. Total cost 
of monitoring the five projects during FY 1985 was $3,602. 
42. WEST MAKINSTER ROAD, WILSON RIVER, 
OR 
Location. West Makinster location, on the left bank 
of Wilson River, mile 1, about 2 miles north-northwest of 
Tillamook, Tillamook County, OR. Work would be accomplished 
under authority of Section 14 of the 1946 
Flood Control Act, as amended. 
Existing project. Plan of improvement called for approximately 
8,400 cubic yards of quarry stone to be placed 
over a total of 960 linear feet of bankline to correct the 
erosion problem. A ground stabilizing fabric was placed 
on the damaged bank to provide support for the stone. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Final fiscal 
requirements were completed. 
43. WILLAMETTE RIVER BASIN, OR 
Location. Willamette River, formed by Coast and Middle 
Forks which join a few miles above Eugene, OR, flows 
north 189 miles, and enters Columbia River 101.5 miles 
above its mouth. The basin has an area of 11,200 square 
miles and lies between Cascade Range on the east and 
Coast Range on the west. Major tributaries of Willamette 
River rise in Cascade Mountains and consist of Coast and 
Middle Forks and McKenzie, Calapooia, Santiam, Molalla, 
and Clackamas Rivers. Important tributaries that head 
in the Coast Range are Luckiamute, Yamhill, and 
Tualatin Rivers. Minor tributaries, all of which enter the 
main stream from the west, are Long Tom River, Marys 
River, and Rickreall Creek. 
Existing project. Flood Control Act of 1938 approved 
general comprehensive plan for flood control, navigation, 
and other purposes in Willamette River Basin and 
authorized funds for initiation and partial accomplishment 
of plan recommended for initial development: the 
37-16

PORTLAND, OREGON DISTRICT 
reservoirs and related works to be selected by Chief of 
Engineers. Subsequent Flood Control Acts, 1941 through 
1974, authorized additional flood control and other works 
and increased monetary authority. 
Following projects were completed as authorized and 
are in continuous operation: Fern Ridge Lake, August 
1951; Cottage Grove Lake, April 1952; Dorena Lake, October 
1952; Detroit Lake, December 1960; Lookout Point 
Lake, June 1961; Hills Creek Lake, June 1963; Cougar 
Lake, March 1964; Fall Creek Lake, November 1965; 
Green Peter-Foster Lakes, June-December 1967 respectively; 
and Blue River Lake, October 1968. Under the 
authorization for construction of recreation facilities at 
completed projects, work has been accomplished at Fern 
Ridge, Cottage Grove, Dorena, Lookout Point, and Fall 
Creek Lakes. Under the memoranda of agreements with 
the U.S. Forest Service, recreation facilities also have been 
constructed at Detroit, Lookout Point, Cougar, Blue River, 
and Hills Creek Lakes. Recreational facilities were constructed 
at Green Peter-Foster Lakes with initial construction 
funds. Details of operation, construction, and financial 
status of projects are in individual reports. 
During low-water season, July-September, supplemental 
water releases are made from Willamette River Basin 
Reservoirs. Uses which benefit from increased 
downstream flows include irrigation, navigation, power, 
fisheries, pollution abatement, and recreation. Although 
optimum regulation cannot be provided for every purpose, 
water released from reservoirs during the low-water 
season for a particular purpose will usually provide 
benefits to other uses as well. Basic policy is to provide 
most beneficial overall regulation, consistent with 
established water-use priorities. (See Table 37-0 on 
Willamette River Basin comprehensive plan.) 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938 applies. Local cooperation for other projects 
is in individual reports for those projects. 
Operations during fiscal year. See individual reports. 
44. WILLAMETTE RIVER BASIN BANK 
PROTECTION, OR "" 
Location. On Willamette River and tributaries, between 
Cascade Range and Coast Range, from a point south 
of Eugene to Portland, OR. 
Existing project. Provides for clearing, sloping, and 
reveting riverbanks; construction of pile and timber 
bulkheads and drift barriers; minor channel improvements; 
and maintenance of existing works for control 
of floods and prevention of erosion at various locations 
along Willamette River and its tributaries. The current 
scope of the project is a total of 510,000 linear feet of bank 
protection at 236 locations. Estimated Federal cost is 
$30,300,000. 
Construction of project began in 1938 and is 96 percent 
complete. A total of 489,795 linear feet of bank protection 
work at 230 locations consisting of revetment of riverbanks, 
pile and timber bulkheads, drift barriers, and channel 
improvements, have been completed on Willamette 
River and tributaries. 
Local cooperation. Section 3, Flood Control Act of 
1936 applies. Estimated costs for all requirements of local 
cooperation under terms of project authorization were 
$377,000. 
Operations during fiscal year. New work: A total of 
3,650 linear feet of riprap revetment bank protection was 
completed at Minto-Brown location. No further construction 
was conducted during the fiscal year. 
Maintenance: Annual inspection of revetments was 
made by helicopter in July 1986. 
45. WILLOW CREEK LAKE, HEPPNER, OR 
Location. On Willow Creek immediately upstream 
from Heppner and just downstream from junction of Balm 
Fork and Willow Creek in Section 35, Township 2 South, 
Range 26 East, Willamette Meridian. 
Existing project. Project provides flood protection to 
the city of Heppner and downstream area by controlling 
runoff from a drainage area of 96 square miles. The dam 
is a roller compacted concrete structure 160 feet high at 
crest elevation 2,130. Ancillary features include a center 
uncontrolled spillway with a maximum flood capacity of 
93,300 cfs, (cubic feet per second) an outlet works with a 
capacity of 500 cfs, a minor flow works and diversion 
works. Gross storage capacity of the project is 13,250 acrefeet, 
consisting of 7,750 acre-feet for exclusive flood control, 
1,750 acre-feet for joint flood control and irrigation, 
1,750 acre-feet exclusive irrigation, and 2,000 acre-feet 
dead storage for fish, wildlife, recreation, sediment accumulation, 
and aesthetics. Limited recreation facilities 
are being provided. 
The final Environmental Impact Statement was filed 
with the Environmental Protection Agency on December 
20, 1979. The provision of the Clean Water Act were met 
by a Section 404(bX1) Evaluation and a public notice 
issued January 12, 1980, and a Section 401 certification 
from the State of Oregon on February 15, 1980. Land acquisition 
is about 99 percent complete. 
Local cooperation. None required. Development of 
recreation facilities will require cost sharing with a nonfederal 
local sponsor. 
Operations during fiscal year. New work: (See Walla 
Walla, WA District Annual Report.) 
Maintenance: Normal operation and maintenance 
performed. 
Multiple-Purpose Projects, 
Including Power 
46. BONNEVILLE LOCK AND DAM-LAKE 
BONNEVILLE, OR AND WA 
Location. Project is on Columbia River, 40 miles east 
of Portland, OR, about 146 miles above mouth of river. For 
description of Columbia River see Section 4. 
SExisting project. A dam, powerplant, and lock for 
power and navigation. Spillway dam extends across main 
channel from Cascade Island shore to Bradford Island. 
Overflow crest at 24 feet above mean sea level is surmounted 
by 18 vertical-lift steel gates, 10 with remote 
37-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
control hoists placed between piers which extend to 
elevation 99 feet where a service roadway provides 
access, and two 350-ton gantry cranes for regulating 
gates. Powerhouse No. 1 extending across Bradford 
Slough to the Oregon shore has an installation of 10 
units, consisting of two units of 43,200 kilowatts and 
eight units of 54,000 kilowatts each, totaling 518,400 
kilowatts. Ordinary and extreme fluctuations of river at 
lower lock gate are about 21 and 47 feet respectively. 
Project includes fish ladders to serve both main channel, 
Bradford Slough channel, and Powerhouse II channel. 
Navigation lock and powerhouses are founded on andesite, 
and main dam rests upon solidified sedimentary rock of 
volcanic origin. The pool created by dam provides a 
navigable channel 15 feet deep between Bonneville and 
The Dalles Dams, a distance of 47 river miles. Principal 
data concerning navigation lock spillway dam, and 
powerplant are set forth in Table 37-P. 
Dam, navigation lock, 10-unit power generating installation, 
fishways, and attendant buildings and grounds 
cost $83,239,395, of which $6,072,480 is for navigation 
facilities, $39,350,824 for power facilities and $37,816,091 
for joint facilities, consisting of dam, fishways, buildings 
and grounds, and headwall section of power units 0 to 6, 
cost of which $2,106,000 is allocated to dam and lake 
facilities. 
In response to flow regulations and peakings from 
upstream plants operating under conditions of Canadian 
storage and Pacific Northwest - Southwest Intertie, two 
modifications were undertaken at the Bonneville project. 
The modification for peaking project was undertaken to 
minimize adverse environmental effects under rapidly 
changing flow conditions from upstream dams. The project 
was completed in 1978 at a cost of $27,195,000. The 
second modification provides for increased power installation 
by building a second powerhouse located on the 
Washington shore adjacent to the end of the existing 
spillway. The new powerhouse contains eight units of 
66,500 kilowatts each and two fish attraction turbine 
generator units of 13,100 kilowatts each for a combined 
capacity of 558,200 kilowatts, bringing the entire Bonneville 
capacity to 1,076.6 megawatts. Additional fish 
facilities consist of the powerhouse collection system, second 
fish ladder on the Washington shore, transportation 
channel connecting the Cascade Island fish ladder with 
new exit control section, and fingerling bypass facilities 
which include fish screens in both the powerhouses. To 
provide for the anticipated increased visitor use, onsite 
visitor facilities are included. Under authority of the Bonneville 
Project Act (August 20, 1937), a letter from Bonneville 
Power Administration to North Pacific Division 
dated January 21, 1965, requested construction of a second 
powerhouse. 
Construction of project started October 1933, was completed 
February 1953. Modification of powerhouse control 
equipment started March 1957, was completed September 
1958. First two power units were placed in operation during 
fiscal year 1938. Powerhouse with complete installation 
of 10 units, was in operation December 1943. 
Construction of modification for peaking work commenced 
in September 1970 and was completed in September 1978. 
Construction of second powerhouse is near completion. 
Final environmental impact statement was filed with 
Council on Environmental Quality in April 1972. In 
response to increasing visitation which now exceeds 
800,000 a year at the dam site itself and 1,500,000 projectwide, 
a visitor center with windows into the fish ladders, 
a 60-seat theatre, exhibits and displays was completed in 
1975. Contracts for relocation of the highway, railroad and 
town of North Bonneville are 99 percent complete. Construction 
of the main powerhouse and supply contracts 
for associated powerhouse equipment are 99 percent complete 
and Units 11 through 18 were on-line by October, 
1982. The visitor facility for the new powerhouse (which 
does not require cost-sharing) is an integral part of that 
structure. Estimated cost for construction of second 
powerhouse is $663,000,000. 
A cost sharing agreement between The Corps and 
Skamania County has been finalized. Development of 
recreation facilities is now under way at Home Valley and 
is expected to be completed in 1987. 
Through September 1986 power generation totaled 
190.3 billion kilowatt-hours. Of the gross income from sale 
of this power by Bonneville Power Administration, 
$258,085,302 was reimbursed to the U.S. Treasury to 
recover Corps of Engineers project investment and 
operating costs. 
Local cooperation. None required, except for non- 
Federal cost-sharing for development of recreational 
facilities. 
Operations during fiscal year. New work: Construction 
continued on restoration of areas disturbed by 
powerhouse construction. Final stages of the juvenile 
bypass system and monitoring facilities were under construction. 
Correction of deficiencies in fish guidance efficiency 
at the Second Powerhouse will reduce fingerling 
mortality incurred during annual downstream migration. 
Maintenance: The modernization program continued 
to be implemented. Normal operation and maintenance 
was performed during period. During the fiscal year 
5,097,795,000 kilowatt-hours of electrical power energy 
were generated, of which 5,080,217,000 kilowatt-hours 
were delivered to Bonneville Power Administration, the 
marketing agency. Traffic through the navigation lock 
consisting of rafted logs, petroleum products, grains, and 
miscellaneous cargo amounted to 7,679,778 tons during 
calendar year 1985. 
4'f. COUGAR LAKE, OR 
Location. At mile 4.4 on South Fork McKenzie River 
which joins McKenzie River about 56.5 miles above its 
confluence with Willamette River. Project is about 42 
miles east of Eugene, OR. 
Existing project. A rockfill dam with an impervious 
earth core, about 1,738 feet long at crest and 445 feet high 
above the streambed. Reservoir is 6 miles long with 
storage capacity at full pool of 219,000 acre-feet and controls 
runoff of tributary drainage area of 210 square miles. 
Spillway is on right abutment and outlet and power tunnels 
in left abutment. Outlet tunnel is provided with a 
37-18

PORTLAND, OREGON DISTRICT 
chute and stilling basin. Powerplant consists of two 12,500 
kilowatt units with minimum provisions for installing a 
third unit of 35,000 kilowatts for future peaking capacity. 
Improvement functions as a unit in coordinated system 
of reservoirs for multiple-purpose development of water 
resources in Willamette River Basin. Recreation facilities 
are provided by the U.S. Forest Service. Also authorized 
(but unconstructed) is a reregulating dam, Strube Lake, 
below Cougar Lake, which would permit Cougar to 
operate as a peaking powerplant. The Strube dam would 
contain two units totalling 4,600 kilowatts. 
Construction of project initiated June 1956 is complete, 
excluding Strube Lake and Cougar Additional Unit for 
which planning is essentially complete. Also, plans and 
specifications for the first construction contract (relocations) 
have been completed. Generating units 1 and 2 were 
placed in commercial operation March 23 and February 
4, 1964, respectively. Physical in-service date for flood control 
was November 29, 1963. Through September 1986 
power generation totaled 3.0 billion kilowatt-hours. Of the 
gross income from sale of this power by Bonneville Power 
Administration, $15,591,461 was reimbursed to the U.S. 
Treasury to recover Corps of Engineers project investment 
and operating costs. Estimated Federal cost of Strube 
Lake and Cougar Additional Unit is $102,000,000. 
Local cooperation. None required. 
Operations during fiscal year. New work: Continuation 
of negotiations for the innovative financing of Strube 
Lake and Couger Additional Unit. 
Maintenance: Installation of a new alarm reporting 
system is increasing the ability to monitor the project for 
safety from the Foster Powerhouse. Ordinary operation 
and maintenance continued. During fiscal year, 
155,266,000 kilowatt-hours of electrical energy were 
generated at project, of which 154,392,000 kilowatt-hours 
were delivered to Bonneville Power Administration, the 
marketing agency. Freshets regulated by Cougar Lake on 
South Fork McKenzie River are shown on Table 37-M. 
48. DETROIT LAKE, OR 
Location. On North Santiam River with dam 50 miles 
from mouth 45 miles southeast of Salem, OR. North Santiam 
River flows north and west for 85 miles, and unites 
with South Santiam River to form Santiam River, which 
10 miles downstream enters Willamette River 108 miles 
above its mouth. 
Existing project. Main dam and a reregulating dam, 
both with power-generating facilities. Detroit Dam is a 
concrete gravity structure about 1,522 feet long and 454 
feet high from lowest point of the general foundation to 
roadway deck. Spillway is a gate-controlled overflow section, 
and outlet works are gate-controlled conduits 
through dam. Powerhouse with two units having a capacity 
of 50,000 kilowatts each is in right abutment immediately 
below dam. Reservoir has a storage capacity 
at full pool of 454,900 acre-feet and controls runoff of 
tributary drainage area of 438 square miles. It is being 
operated as a unit in coordinated reservoir system to protect 
Willamette Valley from floods, to increase low water 
flows in interest of navigation and irrigation, to generate 
power, and for other purposes. Reregulating dam 3 miles 
downstream at Big Cliff site is concrete gravity type, about 
191 feet high from lowest point of the general foundation 
to roadway deck. Power installation consists of one unit 
with a capacity of 18,000 kilowatts. Reservoir has a 
storage capacity of 5,930 acre-feet at full pool. Project is 
a unit of comprehensive plan for flood control and other 
purposes in Willamette Basin. Recreation facilities are 
provided by the U.S. Forest Service, Oregon State Park 
System and the town of Detroit. 
Construction of project begun in May 1947 was completed 
December 1960. The two powerhouse generating 
units were placed in commercial operation June and October 
1953. At Big Cliff powerhouse, single generating 
unit was placed on-line June 1954. Use of Big Cliff Dam 
for reregulating fluctuating flow from Detroit units was 
effected October 1953. Through September 1985 power 
generation totaled 16.5 billion kilowatt-hours. Of the gross 
income from sale of this power by Bonneville Power Administration, 
$53,942,534 was reimbursed to the U.S. 
Treasury to recover Corps of Engineers project investment 
and operating costs. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Installation 
of a new alarm reporting system is increasing 
the ability to remotely monitor the project from the Foster 
Powerhouse. Ordinary operation and maintenance continued. 
During fiscal year 493,484 kilowatt-hours of electrical 
energy were generated at project of which 460,309 
kilowatt-hours were delivered to Bonneville Power Administration, 
the marketing agency. Freshets regulated 
by the Detroit Lake project on North Santiam River are 
shown in Table 37-M. 
49. GREEN PETER-FOSTER LAKES, OR 
Location. At approximate mile 5.5 on Middle Santiam 
River which joins South Santiam River about 56.8 miles 
above its confluence with Willamette River. Dam is about 
30 miles southeast of Albany in Linn County, OR. 
Existing project. Main dam and a reregulating dam, 
both with power-generating facilities. Green Peter Dam 
is a concrete gravity structure, 1,400 feet long and 385 
feet high above the lowest point of the general foundation 
with a gate-controlled spillway. Outlet works consist of 
two conduits through spillway, discharging into a stilling 
basin. Powerplant, on right bank adjacent to spillway stilling 
basin, consists of two units with an installed capacity 
of 80,000 kilowatts. Reservoir provides storage capacity 
at full pool of 430,000 acre-feet, extending 
6.5 miles up Quartzville Creek and some 7.5 miles 
up Middle Santiam River above creek junction, forming 
a Y-shaped pool. Reservoir controls runoff of tributary 
drainage area of 277 square miles. 
Foster Dam, 7 miles downstream from Green Peter 
Dam is located on South Santiam River about 38 miles 
above its confluence with Santiam River and 1.5 miles 
below its confluence with Middle Santiam River. Foster 
Dam consists of an earth, gravel, and rock-filled embankment, 
146 feet high from lowest point of the general 
37-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
foundation and a concrete gravity gate-controlled spillway 
and stilling basin for a total length of 4,800 feet. Power 
installation consists of two units with a capacity of 20,000 
kilowatts. Foster Lake has a storage capacity, at full pool, 
of 61,000 acre-feet. Project functions as a unit in coordinated 
system of reservoirs for multiple-purpose development 
of water resources in Willamette River Basin. 
All construction on Green Peter-Foster Lakes project 
initiated June 1961 is completed. Green Peter Lake was 
placed in operation for useful flood control June 1967 as 
a unit of coordinated reservoir system for protection of the 
Willamette River Basin. First power-generation unit was 
placed on the line June 9, 1967 and second, June 28, 1967. 
Use of Foster Lake for reregulating fluctuating flows from 
Green Peter units was effective December 1967. First 
power generation unit was placed on-line August 22, 1968 
and second, September 6, 1968. Through September 1986 
power generation totaled 6.6 billion kilowatt-hours. Of the 
gross income from sale of this power by Bonneville Power 
Administration, $36,238,043 was reimbursed to the U.S. 
Treasury to recover Corps of Engineers project investment 
and operating costs. 
Local cooperation. Future recreation development at 
Foster or Green Peter will require cost sharing. Recreation 
facilities at Foster Lake includes 3 parks and 2 parks 
at Green Peter Lake. These parks were developed by the 
Corps and are operated by Linn County under lease 
agreement. 
Operations during fiscal year. Maintenance: Repair 
of the powerhouse roof was completed. Normal operation 
and maintenance continued. During the fiscal year 
353,475,000 kilowatt-hours of electrical energy were 
generated at project of which 350,668,000 kilowatt-hours 
were delivered to Bonneville Power Administration, the 
marketing agency. Freshets regulated by Green Peter 
Lake project on Middle Santiam River are shown in Table 
37-M. 
50. HILLS CREEK LAKE, OR 
Location. On the Middle Fork, Willamette River, 47.8 
miles from mouth and 26.5 miles upstream from Lookout 
Point Dam. Middle Fork, Willamette River rises on west 
slope of Cascade Range and flows northwesterly to its junction 
with Coast Fork, Willamette River. Dam is about 45 
miles southeast from Eugene, OR. 
Existing project. An earth-and-gravel-fill dam about 
2,150 feet long at the crest and 338 feet above lowest point 
of the general foundation. A gate-controlled concrete 
gravity chute-type spillway is in right abutment. Diversion 
tunnel, outlet tunnel and power tunnel are in same 
abutment. Powerhouse with two 15,000 kilowatt units is 
located next to spillway. Hills Creek Lake is about 8.5 
miles long and provides storage capacity at full pool of 
356,000 acre-feet. Project controls runoff of drainage area 
of 389 square miles and is an integral unit of comprehensive 
plan for development of water resources of Willamette 
River Basin. Hills Creek Lake and Lookout Point Lake 
are operated as a unit for control of floods and generation 
of power on Middle Fork Willamette River. These projects, 
in conjunction with Dexter reregulating dam and Fall 
Creek Lake flood control system, will effectively control 
floods on Middle Fork and provide maximum efficient 
generation of hydroelectric power. Recreation facilities are 
provided by the U.S. Forest Service. Hills Creek power 
units are remote controlled from Lookout Point. 
Construction of project, initiated May 1956, was completed 
June 1963. The project was placed in service for 
useful flood control in November 1961. On May 2, 1962, 
the two power units were placed on-line. Through 
September 1986 power generation totaled 3.9 billion 
kilowatt-hours. Of the gross income from sale of this power 
by Bonneville Power Administration, $15,868,213 was 
reimbursed to the U.S. Treasury to recover Corps of 
Engineers project investment and operating costs. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance continued. During 
fiscal year 172,172,000 kilowatt-hours of electrical power 
were generated, of which 171,602,000 kilowatt-hours were 
delivered to Bonneville Power Administration, the 
marketing agency. Freshets regulated by Hills Creek Lake 
on Middle Fork Willamette River are shown in Table 
37-M. 
51. JOHN DAY LOCK AND DAM-LAKE UMATILLA, 
OR AND WA 
Location. On Columbia River about 3 miles 
downstream from mouth of John Day River and about 215 
miles above mouth of Columbia River. 
Existing project. A dam, powerplant, navigation lock, 
fish ladders, and appurtenant facilities with a slack-water 
lake about 75 miles long extending to McNary Lock and 
Dam. Included is relocation of railroads, highways, 
utilities, and communities affected by the impoundment. 
The project as originally authorized would have provided 
2,000,000 acre-feet of flood control storage. As modified, 
the project provides 500,000 acre-feet of flood control 
storage between elevations 257 and 268. The structure is 
5,900 feet in length and stands about 161 feet above 
streambed. Powerhouse has space for 20 generating units 
of 135,000 kilowatts each; 16 units have been installed for 
a present capacity of 2,160,000 kilowatts. Principal project 
data are set forth in Table 37-P. 
A detailed description of project as authorized and 
modified is on pages 1992 and 1993 of Annual Report for 
1962 under the Walla Walla District. 
Construction began July 1958 and the project was opened 
to navigation April 1968. The main dam contract is 
complete. Lock rehabilitation work begun in FY 1980 is 
essentially complete. Entire project is estimated to be 99 
percent complete. Through September 1986 power generation 
totaled 190.8 billion kilowatt-hours. Of the gross income 
from sale of this power by Bonneville Power Administration, 
$230,860,730 was reimbursed to the U.S. 
Treasury to recover Corps of Engineers project investment 
and operating costs. Estimated Federal cost of new work 
is $512,043,000, consisting of $511,710,000 Corps of 
Engineers and $333,000 for Coast Guard navigation aids. 
Local cooperation. Recreation facilities at 4 parks are 
operated and maintained by local agencies under lease 
37-20

PORTLAND, OREGON DISTRICT 
agreement with the Corps. Irrigon Park was expanded 
under cost sharing agreement and is managed by the Irrigon 
Park and Recreation Commission. Any future 
recreation developlment will require cost sharing. 
Operations during fiscal year. New work: Contracts 
were awarded for the second of two phases of construction 
to complete work on a juvenile by-pass system in 
September 1985. The contract for the first phase of construction 
was physically completed in October 1985. The 
by-pass facility consists of a collection system of submersible 
traveling screens, a conduit mined above the intakes 
to each turbine-generator unit and across the length of 
the powerhouse, a conduit extending from the powerhouse 
to an outfall structure downstream, and an intake gantry 
crane to handle fish facilities equipment. The juvenile 
by-pass system work is anticipated to be completed by 
September 1987. 
Maintenance: Normal operation and maintenance continued. 
During fiscal year 10,257,924,000 kilowatt-hours 
of electrical power were generated by the 16 generating 
units of which 10,239,724,000 kilowatt-hours were 
delivered to Bonneville Power Administration, the 
marketing agency. Traffic through the navigation lock, 
consisting of petroleum products, grains, and 
miscellaneous cargo, amounted to 6,177,268 tons during 
calendar year 1985. 
Rehabilitation: Refurbishment of two generator windings 
and rebuilding (to strengthen) two turbines were completed. 
A multi-unit generator refurbishment contract 
awarded will enable completion of 75% of all turbine 
generator work included in the rehab program. The contract 
for upgrading the powerhouse control system was 
awarded in 1985, which when complete should increase 
the reliability and ease of operation of the powerhouse. 
52. LOOKOUT POINT LAKE, OR 
Location. On Middle Fork, Willamette River at Meridian 
site, 21.3 miles from mouth. Middle Fork, Willamette 
River, rises in Lane County on western slope of Cascade 
Range and flows northwesterly to its junction with Coast 
Fork, which is head of main stem Willamette River. Dam 
is about 22 miles southeast from Eugene, OR. 
Existing project. A main dam at Meridian site and 
a reregulating dam 3 miles downstream at Dexter site. 
Both dams are earth-and-gravel-fills with concrete 
spillways and have power generating facilities. Main dam 
is 258 feet high from lowest point of the general foundation 
to deck and is 3,381 feet long at crest forming a reservoir 
14.2 miles long providing storage of 456,000 acre-feet 
at full-pool level. Reservoir controls runoff of tributary 
drainage area of 991 square miles. Spillway, 274 feet long, 
is a gate-controlled overflow type, forming right abutment. 
Outlet works consisting of slide-gate-controlled conduits 
pass through spillway section. Powerhouse has three main 
generating units with a capacity of 120,000 kilowatts. 
Dexter reregulating dam has a maximum height of 107 
feet above lowest point of the general foundation and is 
2,765 feet long at crest, forming a full pool of 27,500 acrefeet 
extending upstream to main dam and providing 
pondage to regulate Lookout Point powerhouse water 
releases to a uniform discharge. Spillway consists of a 
gate-controlled overflow section 509 feet long forming 
right abutment. 
Flow regulation is accomplished by use of spillway 
gates and releases through powerhouse, which contains 
one 15,000-kilowatt unit. Lookout Point and Dexter Lakes 
are operated as a single unit of a coordinated system of 
reservoirs to protect Willamette River Valley against 
floods, to provide needed hydroelectric power, and to increase 
low water flows for navigation, irrigation, and other 
purposes. Existing project authorized as a unit of comprehensive 
plan for flood control and other purposes in 
Willamette River Basin. 
Construction of project initiated May 1947 was completed 
June 1961, except for construction of additional 
recreation facilities funded through the Code 710 program. 
Future recreation facilities will be provided in accordance 
with the cost-sharing contract with Lane County 
and will require a 50 percent contribution by Lane 
County and is subject to funding availability by the 
Government and the County. At Lookout Point 
powerhouse, generating units 1, 2 and 3 were placed in 
commercial operation December 1954, February 1955, 
and April 1955, respectively. At Dexter powerhouse the 
single unit was placed on-line May 1955. Use of Dexter 
Lake for reregulating fluctuating flows from Lookout 
Point units was effected in December 1954. Through 
September 1986 power generation totaled 13.1 billion 
kilowatt-hours. Of the gross income from sale of this power 
by Bonneville Power Administration, $55,562,601 was 
reimbursed to the U.S. Treasury to recover Corps of 
Engineers project investment and operating costs. 
Local cooperation. A multiple project cost sharing 
agreement has been in force with Lane County since 
September 1976. It includes 4 projects and 13 parks. All 
these parks are managed by Lane County under lease 
agreement. Future development will require a supplement 
to the cost sharing agreement. 
Operations during fiscal year. Maintenance: Normal 
operation and maintenance continued. During fiscal year 
411,607,000 kilowatt-hours of electrical power energy 
were generated at project of which 409,791,000 kilowatthours 
were delivered to Bonneville Power Administration, 
the marketing agency. Freshets regulated by Lookout 
Point Lake project on Middle Fork Willamette River are 
shown in Table 37-M. 
53. LOST CREEK LAKE, ROGUE RIVER BASIN, 
OR 
Location. On upper Rogue River at mile 153.6 about 
30 miles northeasterly from Medford, OR. 
Existing project. A rock and gravel-fill embankment 
dam about 327 feet high from streambed to crest, with 
an overall length of 3,750 feet with an impervious earth 
core and a gate-controlled concrete spillway. Powerhouse 
is on right abutment and houses two Francis-type turbines 
with installed capacity of 24,500 kilowatts each. 
Regulating outlet facility with provisions for temperature 
37-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
regulation for releases in interest of fishery enhancement 
is also on right bank. Reservoir 10 miles long provides 
315,000 acre-feet of usable storage. Project provides control 
of runoff of drainage area of 674 square miles. In addition 
to hydroelectric power generation, project provides 
flood control, irrigation, future municipal and industrial 
(M&I) water supply, fish and wildlife enhancement, water 
quality control and recreation benefits. 
Construction of project initiated July 1967 is complete. 
Generating units 1 and 2 were placed in commercial 
operation July 6 and July 13, 1977, respectively. Physical 
in-service date for flood control was February 18, 1977. 
Final environmental statement was filed with Council on 
Environmental Quality in June 1972. Through September 
1986 power generation totaled 2.7 billion kilowatt-hours. 
Of the gross income from sale of this power by Bonneville 
Power Administration, $13,614,364 was reimbursed to the 
U.S. Treasury to recover Corps of Engineers project investment 
and operating costs. 
Local cooperation. Authorizing act required that 
local agencies furnish assurances prior to construction 
that demands will be made for future use of water supply 
storage within a period that will permit repayment of 
costs, including interest, allocated to water supply within 
life of the project; that State of Oregon take action, prior 
to construction to insure maintenance in stream of flows 
to be released for fishery; in addition, costs allocated to 
irrigation would have to be repaid in manner and to an 
extent consistent with reclamation laws and policies; and 
costs allocated to power will be repaid on a system basis 
by revenue from sales of power in Pacific Northwest 
Federal system by Bonneville Power Administration. A 
survey in September, 1980 of M&I water supply needs 
showed nine communities with water supply needs. A contract 
for M&I supply has been completed with one of the 
communities. Assurances for municipal and industrial 
water supply were obtained from six communities in 
Rogue River Valley. On February 26, 1966 Oregon State 
Department of Fish and Wildlife agreed to operate Rogue 
River hatchery for mitigation and enhancement of fish. 
The Corps provides full funding for the operation and 
maintenance of the hatchery. The hatchery became operational 
in 1972. 
Operations during fiscal year. Maintenance: During 
fiscal year 277,700,000 kilowatthours of electrical power 
energy were generated at project bf which 275,182,000 
kilowatt-hours were delivered to Bonneville Power Administration, 
the marketing agency. Freshets regulated 
by Lost Creek Lake on Rogue Rivet are shown in Table 
37-M. 
54. THE DALLES LOCK AND D M-LAKE CELILO, 
WA AND OR 
Location. On Columbia River at head of pool behind 
Bonneville Dam, about 192 miles above mouth of river 
and 88 miles east of Portland, OR. 
Existing project. A dam, powerplant, navigation lock, 
and appurtenant facilities. Improvement provides for 
navigation and hydroelectric power generation. Dam is 
designed for a normal pool at elevation 160 feet at mean 
sea level. Normal pool forms a reservoir extending 
upstream about 23 miles providing slackwater to John 
Day Dam site. The Dalles Dam is 8,700 feet long and consists 
of a rock, gravel, and sand river closure section from 
Oregon shore connecting to a nonoverflow section which 
in turn joins powerhouse, then concrete nonoverflow sections 
connecting spillway with powerhouse and spillway 
with navigation lock at right abutment on Washington 
shore. Fish-passing facilities including two ladders and 
a fish lock are provided. Powerhouse was constructed for 
14 units initially and substructure for eight additional 
units, an ultimate total of 22 units. Initial installation, 
excluding two 13,500 kilowatt fishwater units, is 
1,092,000 kilowatts. With eight units installed for a 
capacity of 687,800 kilowatts, the 22 unit total is 
1,808,800 kilowatts. Structures are founded on Columbia 
River basalt. Principal data concerning lock, spillway, and 
powerhouse are set forth in Table 37-P. 
Major construction of project initiated February 1952, 
was completed October 1960 when unit No. 14 was placed 
in commercial operation. Initial contract for additional 
units 15-22 was awarded in September 1967. Additional 
8-unit phase was completed when unit 22 was placed in 
commercial operation in November 1973. Basic recreation 
facilities were developed with construction funds at 4 
parks on Lake Celilo. These parks were further expanded 
with code 710 funds in the late 60's and early 70's. Two 
parks are operated by Washington State Park Commission 
under a lease agreement. Studies for adding power 
generation facilities to the North Shore Fish Ladder Auxiliary 
Water Supply System were initiated in October 
1979 and completed in December 1980. These facilities 
would provide baseload generation (3.5 megawatts) and 
would not impact the present operation of the North Fish 
Ladder. Seufert Visitor Center was completed in 
September 1980. Through September 1986 power generation 
totaled 203.2 billion kilowatt-hours. Of the gross income 
from sale of this power by Bonneville Power Administration, 
$250,560,540 was reimbursed to the U.S. 
Treasury to recover Corps of Engineers project investment 
and operating costs. 
Local cooperation. Further recreation development 
will require cost sharing and assumption of operative and 
maintenace by local, non-federal sponsor. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance continued. During 
fiscal year 8,158,506 kilowatt-hours of electrical power 
energy were generated at project of which 8,139,778 
kilowatt-hours were delivered to Bonneville Power Administration, 
the marketing agency. Traffic through the 
navigation lock, consisting of petroleum products, grains 
and miscellaneous cargo amounted to 6,252,068 tons during 
calendar year 1985. 
General Investigations 
55. SURVEYS 
Fiscal year costs were $4,923,245 of which $385,766 
was for navigation studies, $3,852,316 for flood damage 
prevention studies, $458,173 for comprehensive studies, 
$4,912 for reviews of authorized projects, $179,953 for 
37-22

PORTLAND, OREGON DISTRICT 
miscellaneous activities, and $42,125 for coordination 
with other agencies. 
56. COLLECTION AND STUDY OF BASIC DATA 
International water studies. The Columbia River 
Treaty between Canada and the United States of America 
relating to cooperative Development of the Water 
Resources of the Columbia River Basin was signed at 
Washington, D.C., on January 17, 1961, and the exchange 
of ratifications took place on September 16, 1964. 
Implementation of the Treaty by the United States and 
Canada entities under the guidance of the Permanent 
Engineering Board has continued. The two permanent 
committees established by the entities, the Operating 
Committee and the Hydrometeorological Committee, continue 
to function. 
Costs for support of both committee activities were 
$15,760 for the fiscal year. 
Flood plain management services. Flood Plain 
Management Services Program comes under Section 206 
of the 1960 Flood Control Act, PL 86-645, as amended. 
Through technical services and planning guidance, the 
program encourages comprehensive flood plain management 
planning at all levels to reduce the potential for 
losses to life and property from floods. Federal and non- 
Federal agencies and the private sector are assisted with 
planning and development information for flood hazard 
areas. This assistance is in the form of local flood plain 
regulations, Federal Insurance Program requirements, 
and Executive Order 11988 guidelines. Such assistance 
may include factual flood information (available or determined) 
and interpretation on flood frequencies, extent of 
flooding, flood-water velocity, duration of flooding and 
floodway limits. 
Services accomplished during fiscal year: Technical services 
and planning guidance responses furnished totaled 
821. Of this total, 74 were from other Federal agencies; 
265 from non-Federal agencies; and 482 from private sector 
realtors, corporations, lending institutions, engineers, 
architects, and others. Cost for providing these services 
during FY 1986 totaled $116,528. 
Hydrologic studies. Environmental and ecological 
aspects are being considered on all hydrologic studies. Improvements 
in procedures to determine reservoir 
temperatures, nitrogen supersaturation, dissolved oxygen, 
suspended sediment, turbidity, design floods, flood forecasting 
and flood regulation are a continuing program. 
Costs for hydrologic studies during the fiscal year were 
$3,848. 
Total costs for collection and study of basic data for 
fiscal year 1986 were $177,044. 
57. CONTINUATION OF PLANNING AND 
ENGINEERING 
Cowlitz River and Tributaries, WA 
The project will provide a permanent solution to 
potential flooding on the Cowlitz River from sedimentation 
problems created by the eruption of Mt. St. Helens. 
The Feasibility Report completed in December 1984 
recommended construction of a single retention structure 
and associated downstream actions. The preferred plan 
in that report consisted of a 177-foot-high retention structure 
on the North Fork Toutle River upstream of its confluence 
with the Green River. 
Continuation of planning and engineering was initiated 
in December 1984. It included a comparative 
analysis of risks, benefits and costs, and design, at an 
equal level of detail, of a single stage sediment retention 
structure (SRS), a staged SRS, and dredging program. A 
Decision Document, submitted to ASA (CW) in October 
1985, recommended construction of a single stage.Sediment 
Retention Structure with a 125-foot spillway. This 
document affirmed earlier Department of the Army conclusions. 
The plan also includes a levee modification at 
Kelso, and dredging in the Cowlitz River. Continuation 
of Planning and Engineering was completed in FY 86 at 
a total cost of $4,644,200. A General Design Memorandum 
and a Feature Design Memorandum (Hydrology and 
Meteorology) were completed in FY 1985. Other Feature 
Design Memoranda initiated in FY 1985 and completed 
in FY 86 were Real Estate, Geology and Foundations, Concrete 
Materials and Construction Techniques, Embankment 
and Foundation Excavation. Feature Design 
Memoranda scheduled to be completed this fiscal year 
(with percentages complete) are Sedimentation (99%); 
Reservoir Clearing and Project Roads (96%); Spillway and 
Outlet Works (50%); Fish Facilities (30%); Sediment 
Ranges (99%); Dam Instrumentation and Inspection 
(95%); Initial Filling, Surveillance and Monitoring (10%); 
and Kelso Levee Improvement (20%). 
Authorizing legislation was contained in the FY 1985 
Supplemental Appropriations Act, Public Law 99-88, 
August 15, 1985. A Local Cooperation Agreement between 
the Federal Government and the sponsors was signed on 
April 26, 1986. Initial construction funding was authorized 
on July 2, 1986, in the FY 86 Urgent Supplemental 
Appropriations Bill. A Sediment Retention Structure site 
clearing contract was awarded in September 1986 to initiate 
construction. 
37-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 37-A COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
1. Bonneville Navigation New Work 
Lock, Bonneville Dam, 
OR and WA 
2. Chetco River, OR 
3. Columbia and Lower 
Willamette Rivers 
Below Vancouver, 
WA and Portland, 
OR (Federal Funds) 
(Contributed Funds) 
4. Columbia River at 
Baker Bay, WA 
5. Columbia River 
Between Chinook, 
WA, and Head of 
Sand Island 
6. Columbia River at 
The Mouth, OR 
and WA 
7. Columbia River 
Between Vancouver, 
WA and The Dalles 
OR 
8. Columbia River, 
Ilwaco, WA 
9. Coos Bay, OR 
(Federal Funds) 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
Major Rehab 
Approp. 
Cost 
130,000 6,451,000 6,581,000 
- 6,396,070 6,396,070 
- - - - 2,043,7131 
- - - - 2.043,7131 
535,500 361,300 475,000 552,000 4,819,426 
537,204 361,560 472,802 554,702 4,818,735 
- - - - 28,349,3042 
- - - - 28,349,3042 
15,812,000 20,815,100 15,213,000 11,459,400 236,147,5263 
17,042,261 20,716,288 15,306,888 11,430,195 236,088,191 
- - - - 665,9544 
- - - - 665,9544 
150,400 
137,965 
53,150 
663,437 
- - - 941,252 
- - - 941,252 
16,500 312,000 438,000 3,035,185 
29,861 312,160 438,112 3,035,182 
- - - 220,2835 
- - - 220,2835 
34,500 338,000 594,000 3,643,813 
51,058 321,474 605,577 3,638,133 
- 7,008,000 
-187,772 7,003,593 
2,131,100 5,744,000 
2,191,396 5,771,078 
177,000 
191,730 938 
347,900 
352,944 
7,250,000 
7,243,987 
- 24,913,6616 
- 24,913,6616 
8,911,415 84,291,0997 
8,818,651 84,179,419' 
- 7,322,878 
- - 7,322,878 
- - - - 5,989,5098 
- - - - 5,989,5098 
189,000 188,400 663,000 429,000 11,266,9489 
187,748 190,017 652,345 438,416 11,265,6609 
- 22,500 1,384,500 38,000 1,590,000 
26,614 20,374 1,362,243 60,683 1,589,231 
- - - - 29,750,09210 
- - - - 29,750,09210 
2,263,000 2,971,940 5,042,000 3,041,000 59,224,65211 
3,269,372 2,992,359 4,974,845 3,085,466 59,200,46311 
- - - - 2,335,966 
- - - - 2,335,966 
37-24

PORTLAND, OREGON DISTRICT 
TABLE 37-A COST AND FINANCIAL STATEMENT 
(Continued) 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
(Contributed Funds) New Work 
10. Coos and Millicoma 
Rivers, OR 
11. Coquille River, OR 
13. Depoe Bay, OR 
13. Kalama Turning 
Basin, Kalama 
WA 
15. Nehalem Bay, OR 
16. Port Orford, OR 
18. Rogue River Harbor 
At Gold Beach, OR 
19. Siuslaw River, OR 
(Federal Funds) 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
136,400 121,900 
122,851 135,609 
486,680 
486,680 
- - 350,23812 
- - 350,23812 
49,000 170,000 1,694,010 
43,230 175,970 1,693,095 
- - - - 693,36613 
- - - - 693,36613 
167,600 191,400 426,000 333,000 5,043,94414 
172,074 193,508 418,273 341,125 5,043,55014 
2,000 
2,464 
89,700 
89,446 
45,000 
41,976 
55,000 
52,512 
27,000 
29,397 
18,000 239,000 
14,878 245,146 
367,364 
367,364 
747,876 
747,318 
302,000 
302,000 
302,00615 
302,00615 
55,195 
55,195 
550,000 126,000 - - 12,088,000 
922,899 134,975 5,724 15,777 12,086,751 
- - - - 758,69216 
- - - - 758,69216 
191,000 365,900 392,000 208,000 2,404,329 
198,364 365,818 389,311 210,184 2,403,635 
- - - - 4,156,25217 
- - - - 4,156,25217 
1,044,500 387,700 1,000,000 354,000 8,328,72018 
796,151 677,713 985,538 368,738 8,326,97418 
4,999,813 
287,947 
504,000 
503,248 
8,000,000 
12,713,495 
719,900 
723,964 
12,900,000 
12,915,368 
646,000 
641,001 
2,081,000 
1,821,733 
581,000 
584,714 
635,783 
635,783 
29,465,21219 
29,201,59219 
10,484,09920 
10,482,49720 
879,285 
879,285 
37-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 37-A COST AND FINANCIAL STATEMENT 
(Continued) 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
(Contributed Funds) 
20. Skamokawa Creek, 
WA 
21. Skipanon Channel, 
OR 
22. Tillamook Bay and 
Bar, OR 
23. Umpqua River, OR 
24. Willamette River at 
Willamette Falls, 
OR 
25. Yaquina Bay and 
Harbor, OR 
26. Applegate Lake, 
Rogue River Basin, 
OR 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor 
Rehab 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
45,000 
-1,500 
534,100 
214,238 
68,800 
74,903 
-50,000 
13,654 
413,000 
503,589 
45,000 
90,000 
- 100,000 
143 98,845 1,394 
412,532 
412,532 
2,400 
2,400 
383,782 
383,782 
- - - 280,854 
- - - 280,854 
80,500 336,000 292,000 2,829,014 
403,165 334,934 291,905 2,827,820 
31,000 217,000 
32,593 205,228 
9,851 
827,700 
829,517 
- 22,434,82721 
- 22,434,82721 
59,000 2,917,79022 
68,044 2,914,87022 
- - 2,839,799 
- - 2,839,799 
- 47,500 17,766,37723 
161 10,902 17,729,77923 
604,000 956,000 21,407,989 
580,834 965,341 21,393,940 
- - - - 2,500,677 
- - - - 2,500,677 
- - - - 520,00525 
- - - - 520,00525 
720,000 528,000 501,000 496,000 13,958,82325 
537,797 710,319 480,860 510,761 13,945,98625 
- - - - 234,794 
- - - - 234,794 
- - - - 19,242,04626 
- - - - 19,242,04626 
1,085,100 1,493,400 1,131,000 493,000 18,675,30227 
1,089,700 1,494,202 1,094,881 523,138 18,667,81127 
- - - - 12,005 
- - - - 12,005 
291,000 
971,353 
30,000 
189,499 
31,300 
111,836 
9,300 91,642,489 
47,546 91,623,488 
37-26

PORTLAND, OREGON DISTRICT 
TABLE 37-A COST AND FINANCIAL STATEMENT 
(Continued) 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
27. Blue River Lake, OR 
28. Cottage Grove Lake, 
OR 
29. Dorena Lake, OR 
30. Elk Creek Lake, 
Rogue River Basin, 
OR 
31. Fall Creek Lake, OR 
32. Fern Ridge Lake, OR 
36. John Day River 
(West), OR 
38. Lower Columbia 
River Basin Bank 
Protection, OR & WA 
39. Mt. St. Helens and 
Vicinity, WA 
40. Mt. St. Helens 
Sediment Control 
Castle Rock, WA 
42. West Makinster 
Road, Wilson River, 
OR 
44. Willamette River 
Basin Bank Protection, 
OR 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
623,500 512,000 580,000 550,000 2,756,700 
474,474 650,948 590,699 556,380 2,754,301 
- - - - 32,038,22528 
- - - - 32,038,22528 
221,600 180,000 151,000 213,000 1,913,991 
246,991 184,659 147,919 219,165 1,912,534 
- - - - 4,013,12329 
- - - - 4,013,12329 
537,698 673,000 623,000 708,000 7,978,67830 
607,162 655,509 605,928 730,380 7,961,75430 
354,286 
307,200 
342,935 
1,350,000 
1,389,366 
1,200 
1,600 
342,000 
342,563 
- - 14,568,26231 
- - 14,568,26231 
352,000 382,000 4,420,174 
328,889 405,563 4,417,534 
3,500 10,000,000 32,226,000 54,092,579 
-8,100 4,773,965 20,345,020 36,948,495 
- - - - 22,118,26432 
- - - - 22,118,26432 
241,000 270,000 235,000 255,000 4,046,415 
296,904 269,304 232,116 258,853 4,045,259 
- - - - 8,526,93533 
16,958 77 - - 8,526,93533 
905,000 937,000 742,000 847,000 10,164,63434 
961,183 958,097 745,135 856,543 10,160,15834 
122,300 
122,291 
5,500 
5,509 
127,800 
127,800 
1,700,000 2,600,000 1,000,000 2,850,000 20,574,745 
1,710,021 2,458,996 1,149,563 2,840,161 20,561,949 
Approp. 15,730,000 10,345,000 6,133,000 6,280,000 38,488,000 
Cost 7,557,368 18,267,493 6,232,116 6,347,141 38,404,118 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
- 1,400,000 1,400,000 
- 1,365,665 1,365,665 
178,000 
175,012 2,988 
178,000 
178,000 
1,050,000 624,500 744,000 343,000 24,308,81635 
1,086,098 636,359 760,094 300,794 24,231,36935 
37-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 37-A COST AND FINANCIAL STATEMENT 
(Continued) 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
45. Willow Creek Lake, OR 
46. Bonneville Lock and 
Dam-Lake Bonneville, 
OR and WA 
47. Cougar Lake, OR 
48. Detroit Lake, OR 
49. Green Peter-Foster 
Lakes, OR 
50. Hills Creek Lake, OR 
51. John Day Lock and 
Dam-Lake Umatilla, 
OR and WA 
52. 'Lookout Point 
Lake, OR 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
160,000 
165,055 
56,600 178,000 
62,436 179,056 
96,000 3,541,544 
95,917 3,540,987 
(See Walla Walla, WA District) 
86,000 498,000 382,000 
83,904 467,009 405,626 
21,456,000 12,200,000 
21,390,863 12,032,268 
7,350,600 8,820,000 
8,369,863 8,478,177 
15,000 
8,233 
682,000 
716,706 
6,241 
860,000 
861,133 
17,530,000 
17,905,137 
10,468,000 
10,848,327 
492 
966,000 
956,539 
14,826,000 753,296,60436 
14,958,973 753,209,71936 
12,994,000 130,270,10137 
12,979,585 130,001,69237 
- 58,636,39338 
34 58,636,39338 
731,000 1,141,000 9,530,816 
733,379 1,153,266 9,529,297 
- - - - 62,729,698 
- - - - 62,729,698 
1,232,000 1,789.000 1,411,000 1,456,000 23,860,77249 
1,312,198 1,757,050 1,426,060 1,435,467 23,820,11949 
- - - - 363,086 
- - - - 363,086 
- - - - 84,005,78839 
- - - - 84,005,78839 
1,423,000 1,694,000 
1,550,143 1,679,567 
1,810,000 1,688,000 20,053,13240 
1,825,339 1,667,370 20,024,91740 
- - - - 45,700,619 
- - - - 45,700,619 
693,900 591,000 457,000 446,000 7,019,26741 
747,486 641,968 442,717 457,531 7,015,87241 
1,298,000 
1,597,688 
9,506,100 
10,647,483 
-45,000 
53,108 
10,624,000 
9,103,019 
9,746,000 
9,956,705 
6,483,000 
8,046,653 
10,633,000 
10,663,086 
8,685,000 
8,665,982 
6,125,000 
6,257,535 
509,936,24642 
509,839,43242 
90,374,15943 
90,225,77343 
- 138,000 4,450,000 11,743,000 
18,669 167,842 4,418,339 11,707,633 
- 88,238,39544 
- 88,238,39544 
37-28

PORTLAND, OREGON DISTRICT 
TABLE 37-A COST AND FINANCIAL STATEMENT 
(Continued) 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
53. Lost Creek Lake, 
Rogue River 
Basin, OR 
54. The Dalles Lock and 
Dam-Lake Celilo, 
WA and OR 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
2,092,100 2,348,000 2,119,000 2,194,000 33,914,60545 
2,356,652 2,332,882 2,138,429 2.156,310 33,834,65145 
250,000 
537,648 
'Excludes $17,742 contributed funds for new work. 
2Includes $1,529,413 for previous project. 
3Includes $150,955 allotted from deferred maintenance 
funds, Code 700, $62,296 for public works accelerated program 
repair, and $1,214,865 for previous project. Excludes $24,320 expended 
from contributed funds prior to 1964. 
4Excludes $31,636 contributed by city of Astoria and 
Bumble Bee Sea Foods, Astoria, OR (not part of regular project). 
Includes $223,026 expended from contributed funds prior 
to 1964 and $428,136 contributed by Port of Portland and 
$14,792 by Port of Vancouver. 
5Includes $84,930 rehabilitation funds. 
gIncludes $1,986,253 for previous project and $608,111 
allotted and expended under Code 710, recreation facilities at 
completed project. Excludes $500,000 contributed funds. 
'Includes $2,186,000 for previous project and $1,188,625 
under deferred maintenance, Code 700. 
"Includes funds under Code 721 (small authorized projects) 
$30,393 Entrance to Oregon Slough; $161,897, Camas- 
Washougal Turning Basin; $227,908, Hood River Small Boat 
Basin; $157,470, Bingen, WA, Barge Channel; and $140,619, The 
Dalles Small Boat Basin. 
'Includes $2,033,408 under Code 700 (Deferred Maintenance). 
1�Includes $802,096 for previous project. Excludes contributed 
funds. 
"Includes $178,801 for previous project and $1,444,640 
under Code 700, Deferred Maintenance. Excludes $8,387 contributed 
funds. 
1 Excludes $80,000 (other funds) contributed for new work 
by Port of Coos Bay to cover additional cost of disposing of dredge 
spoils in Coos Bay, OR; includes $8,000 for previous project. 
3Includes $340,726 for previous project. Excludes $72,891 
contributed funds. Includes $36,000 under Code 711. 
"Includes $41,467 for previous project and $78,500 under 
Code 700, Deferred Maintenance. 
5SExcludes $304,826 contributed funds. 
'6Excludes $9,900 contributed funds. 
"Excludes $13,779 (other funds) contributed for additional 
landfill and extension of drainage lines. 
"gIncludes $21,000, Wedderburn Study Funds. 
egIncludes $1,159,357 for previous project. 
"0Includes $10,611 for previous project and $188,000 under 
Code 700, Deferred Maintenance. 
- 290,000 
235,687 271,310 
4,700 136,408,150 
7,270 136,391,678 
,300 2,105,000 2,600,000 2,420,000 16,863,80046 
,181 2,100,169 2,522,379 2,466,125 16,809.55046 
- - - 301,064,28847 
- - - - 301,064,28847 
,000 6,201,000 7,606,000 8,927,000 82,970,00848 
,701 5,840,781 7,851,423 9,027,285 82,875,45148 
21Includes $77,209 for previous project and $57,767 under 
Code 720 (Small Authorized Projects) Garibaldi Boat Basin. 
Excludes $592, 622 contributed funds and $300,000 channel 
dredging by local interest. 
22Includes $71,498 for previous project. Excludes $6,450 expended 
from contributed funds. 
23Includes $39,242 for previous project and $58,824 under 
Code 720 (Small Authorized Projects) Winchester Bay and 
Schofield River, OR. Excludes $267,500 contributed funds. 
24Excludes $300,000 contributed funds. 
25Includes $452,110 on operation and care from permanent 
indefinite appropriation and $150,000 under maintenance and 
operation of dams and other improvements of navigable waters. 
26Includes $707,313 for previous project and $170,000 appropriated 
from public works acceleration program for north jetty 
rehabilitation. 
27Includes $6,026 for previous project. 
28Inlcudes $96,000 pro rata share of site selection costs in 
lieu of Quartz Creek Lake. 
29Includes $1,639,828 allotted and expended under Code 
710, recreation facilities at completed project. 
30lncludes $167,878 special recreation use fees. 
31Includes $1,038,790 allotted and expended under Code 
710, recreation facilities at completed project. 
2Includes $1,026,264 allotted and expended under Code 
710, recreation facilities at completed projects. 
33Includes $3,894,673 allotted and expended under Code 
710, recreation facilities at completed projects and $136,482 
allotted under 721 (small authorized project) reservoir modification. 
Excludes $2,100 (other funds constributed). 
34Includes $9,750 allotted under Code 700, deferred 
maintenance. 
35Excludes $93,733 contributed funds. 
36Includes $12,200,000 Public Works Administration funds, 
$20,240,700 National Recovery Act funds, $27,195,400 modification 
for peaking funds, $436,457 Code 710, recreation facilities 
at completed project funds and $627,593,352 allotted and 
$642,332,504 expended second powerhouse funds; $6,000 alloted 
$6,000 expended, power units funds. 
37Includes $540,000 deferred maintenance funds, Code 700 
and $1,692,148 maintenance and operation of dams and other 
improvements of navigable waters. 
37-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
38Includes $96,000 pro rata share of site selection in lieu 
of Quartz Creek Lake. Includes $1,789,988 allotted and 
$1,789,954 expended for Strube Lake and Cougar Additional 
Unit. 
39Includes $113,000 pro rata share of site selection costs in 
lieu of Sweet Home Lake. 
40Includes $131,900 under maintenance and operation of 
dams and other improvements of navigable waters. 
41 Includes $75,400 under maintenance and operation of 
dams and other improvements of navigable waters. 
42Includes $25,984 allotted and expended under Code 710, 
recreation facilities at completed projects. 
"Includes $1,361,900 for O&M and fish evaluation of Spring 
Creek Hatchery (funds revoked and paid to USFWS at OCE 
level, but a cost to project); includes $423,800 special recreation 
use fees. Includes $933,438 allotted under maintenance and 
operation of dams and other improvements of navigable waters. 
4Includes $457,611 allotted and expended under Code 710, 
recreation facilities at completed project. 
45Includes $131,900 under maintenance and operation of 
dams and other improvements to navigable waters. 
46Includes $131,900 under maintenance and operation of 
dams and other improvements to navigable waters. 
47Includes $1,140,747 allotted and expended under Code 
710, recreation facilities at completed project, and $52,997,220 
allotted and expended additional units 15-22 funds. 
48Includes $721,490 under maintenance and operation of 
dams and other improvements of navigable waters. 
Includes $75,400 under maintenance and operation of dams 
and other improvements to navigable waters. 
37-30 
TABLE 37-A 
(Continued) 
COST AND FINANCIAL STATEMENT

PORTLAND, OREGON DISTRICT 
TABLE 37-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug. 15, 1985 
Mar. 2, 1945 
Oct. 27, 1965 
Dec. 4, 1981 
3. 
Feb. 27, 1911 
July 25, 1912 
July 27, 1916 
Aug. 8, 1917 
Sep. 22, 1922 
Mar. 4, 19232 
Mar. 3, 1925 
Mar. 3, 1927 
July 3, 1930 
Sep. 6, 19333 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 26, 1937 
Aug. 26, 1937 
Mar. 2, 1945 
1. 
2. 
BONNEVILLE NAVIGATION LOCK, 
BONNEVILLE DAM, OR AND WA 
Construction of a new navigation lock just south 
of existing lock. 
CHETCO RIVER, OR 
'Topbro vide for the stabilization of the channel, 
by constructing jetties and dredging. 
Modification of channel entrance and channel 
improvements 
Deepen channel 2 feet to 16 feet, extend the existing 
jetty system 750 feet for the North, and 1,250 feet 
for the South jetty. 
COLUMBIA AND LOWER WILLAMETTE 
RIVERS BELOW VANCOUVER, WA AND 
PORTLAND, OR 
2 pipeline dredges and accessories. 
Increasing main channel to 30 feet 
Consolidating improvement below Portland, OR and 
between Vancouver, WA and mouth of Willamette. 
For the Cathlamet channel. 
Construct an additional dredge (dredge was not 
built) and accessories for better maintenance, and 
construct contraction works. 
Channel from deep water in Willamette Slough to 
deep water in Columbia River. 
Depth of 25 feet and width of 300 feet from mouth of 
Willamette River to Vancouver, WA. 
Closing east channel at Swan Island in Willamette 
River on condition that main channel to be opened 
to project dimensions on west side of island by Port 
of Portland. 
For a 35-foot channel 500 feet wide from Portland to 
the sea. 
A channel 28 feet deep and 300 feet wide from mouth 
of Willamette River to Vancouver, with 2 turning 
basins, each generally 28 feet deep by 800 feet wide 
by 2,000 feet long. 
A channel in Columbia River from mouth of Willamette 
to interstate highway bridge at Vancouver, 
WA, 30 feet deep and 300 feet wide, with 2 turning 
basins at Vancouver. 
Maintenance of not to exceed 35-foot depth at low 
water in Portland Harbor and Willamette River between 
its mouth and Broadway Bridge at Portland. 
Auxiliary channels, 30 feet deep, 300 feet and 500 
feet at St. Helens. 
Extension of lower turning basin at Vancouver, WA, 
1,000 feet downstream. 
An auxiliary channel 24 feet deep and 200 feet wide 
along waterfront at Rainier, OR. 
Improvement of old mouth of Cowlitz River. 
37-31 
P.L. 99-88 
H. Doc. 817, 77th Cong., 
2d Sess. 
S. Doc. 21, 89th Cong., 
1st Sess. 
S. Doc. 10, 96th Cong., 
1st Sess. 
H. Doc. 1278, 61st Cong., 
3d Sess? 
H. Doc. 1278, 61st Cong., 
3d Sess.1 
No Prior Report. 
H. Doc. 120, 63d Cong., 
1st Sess. 
H. Doc. 1009, 66th Cong., 
3d Sess. 
H. Doc. 156, 67th Cong., 
2d Sess. 
H. Doc. 126, 68th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 10 
69th Cong., 2d Sess. 
H. Doc. 195, 70th Cong., 
1st Sess. and Rivers 
and Harbors Committee 
Doc. 8, 71st Cong., 
1st Sess. 
H. Doc. 249, 72d Cong., 
2d Sess?. 
Rivers and Harbors 
Committee Doc. 1, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 6 
73d Cong., 1st Sess? 
H. Doc. 235, 72d Cong., 
1st Sess1 
Rivers and Harbors 
Committee Doc. 81, 
74th Cong., 2d Sess.' 
H. Doc. 203, 75th Cong., 
1st Sess? 
H. Doc. 341, 77th Cong., 
1st. Sess.?

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 37-B AUTHORIZING LEGISLATION 
(Continued) 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Mar. 2, 1945 
July 24, 1946 
Oct. 23, 1962 
Oct. 23, 1962 
Dec. 11, 1933 
Aug. 30, 1935 
Mar. 2, 1945 
May 17, 1950 
June 20, 1938 
Sep. 3, 1954 
Mar. 3, 1905 
Dec. 22, 1944 
as amended 
Sep. 3, 1954 
July 30, 1983 
Aug. 26, 1937 
Mar. 2, 1945 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 24, 1946 
An auxiliary channel in vicinity of Longview, WA. 
A small-boat mooring basin at Astoria, OR. 
A channel 35 feet deep and 500 feet wide from mouth 
of Willamette River to interstate highway bridge at 
Vancouver, WA, with 2 turning basins of same 
depth. 
A channel 40 feet deep and 600 feet wide from Vancouver, 
WA, to mouth of Columbia River; a turning 
basin at Vancouver, WA, a turning basin at Longview, 
WA, and a channel 40 feet deep in Willamette 
River from mouth to Broadway Bridge which 
encompasses Portland Harbor area. 
COLUMBIA RIVER AT BAKER BAY, WA 
East channel 
Main channel. 
West channel 8 feet deep. 
West channel 10 feet deep and mooring basin with 
protecting breakwaters. 
COLUMBIA RIVER BETWEEN CHINOOK, WA 
AND HEAD OF SAND ISLAND 
Channel 8 feet deep. 
Channel 10 feet deep and mooring basin. 
COLUMBIA RIVER AT THE MOUTH, 
OR AND WA 
Extend South Jetty and construct North Jetty and 
dredging. 
Construction, operation, and maintenance of recreation 
facilities. 
Bar channel of 48-foot depth and spur jetty on north 
shore.? 
Deepening the northernmost 2,000 feet of the channel 
cross section to 55 feet. 
COLUMBIA RIVER BETWEEN 
VANCOUVER, WA, AND THE DALLES, OR 
Construct a channel 27 feet deep by 300 feet from 
Vancouver, WA, to Bonneville, OR. 
Construct Camas-Washougal turning basin. 
Construct a channel 27 feet deep by 300 feet wide 
from Bonneville, OR, to The Dalles, OR. 
Construct a boat basin at Hood River, OR, 10 feet 
deep, 500 feet wide, by 1,300 feet long. 
Construct a barge channel at Bingen, WA, 10 feet 
deep, 200 feet wide, by 1 mile long, and an access 
channel 7 feet deep, 100 feet wide, by 1,000 feet long 
to natural mooring basin. 
Construct The Dalles Harbor 8 feet deep, 400 feet 
wide by 800 feet long. 
H. Doc. 630, 77th Cong., 
2d Sess.' 
H. Doc. 692, 79th Cong., 
2d Sess.' 
H. Doc. 203, 87th Cong., 
1st Sess. 
H. Doc. 452, 87th Cong., 
2d Sess.1 
Public Works 
Administration 
H. Doc. 44, 73d Cong., 
1st Sess. 
H. Doc. 443, 76th Cong., 
1st Sess. 
S. Doc. 95, 81st Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 50, 
75th Cong., 2d Sess. 
S. Doc. 8, 83d Cong., 
1st Sess? 
H. Doc. 94, 56th Cong., 
1st Sess. 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 249, 83d Cong., 
2d Sess.' 
P.L. 98-63 
H. Committee Doc. 94, 
74th Cong., 2d Sess. 
H. Doc. 218, 76th Cong., 
1st Sess. 
H. Doc. 704, 79th Cong., 
2d Sess. 
H. Doc. 704, 79th Cong., 
2d Sess. 
H. Doc. 704, 79th Cong., 
2d Sess. 
S. Doc. 89, 79th Cong., 
1st Sess. 
37-32 
5. 
7.

PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
July 14, 1960 
June 25, 1910 
Mar. 2, 1919 
Sep. 22, 1922 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
July 24, 1946 
June 30, 1948 
Dec. 31, 1970 
June 3, 1896 
June 30, 1948 
June 25, 1910 
Mar. 2, 1919 
July 3, 1930 
Aug. 30, 1935 
Dec 22, 1944 
as amended 
Mar. 2, 1945 
Aug. 26, 1937 
Mar. 2, 1945 
8. COLUMBIA RIVER, ILWACO, WA. 
Deepening of the channel a distance of 3 miles to 
provide improved access to the Ilwaco small boat basin. 
COOS BAY, OR 
Dredging the Ocean Bar Channel. 
A channel 22 feet deep to Smith's Mill. 
Restore North Jetty 9,600 feet long, construct a 
South Jetty about 3,900 feet long, extend 22-foot 
bay channel from Smith's Mill to Millington. 
Extend jetties to such lengths as may be practicable 
within estimate of total cost of jetties, $3,250,000 
given in H. Doc. 150, 67th Cong. 
A channel 24 feet deep and 300 feet wide, through 
Pigeon Point Reef, following a location along 
westerly side of bay. 
For 24-foot channel from Pigeon Point Reef to 
Smith's Mill and a turning basin above Marshfield. 
Increased dimensions of channel across bar and to 
Isthmus Slough and turning basin opposite Coalbank 
Slough and at city of North Bend; anchorage 
basins at mile 3.5 and near mile 7. 
A mooring basin and connecting channel at 
Charleston. 
Increase dimensions to provide for bar channel 45 
feet deep, inner channel 35 feet deep to mile 15, 
and deepening and widening existing turning 
basins and anchorage area. 
COOS AND MILLICOMA RIVERS, OR 
Dredging channel from mouth to head of navigation. 
For a 5 ft. depth from mouth to head of navigation 
on the Millicoma River and South Fork. Except on 
South Fork above M. 14 where 3 ft. will suffice. 
COQUILLE RIVER, OR 
Dredging shoals between mouth and Riverton, and 
removing obstruction between mouth of North Fork 
and Bandon 
For a 13-foot channel from ocean to Bandon 
Deepen channel to 16 feet between sea and eastern 
end of North Jetty. 
Present project depth between sea and eastern end of 
North Jetty. 
Construction, operation, and maintenance of 
recreation facilities. 
For 13-foot depth from sea to a point 1 mile above 
Coquille River Lighthouse and snagging to State 
Highway Bridge. 
DEPOE BAY, OR 
Construction of inner basin 375 feet long, 125 feet 
wide and 5 feet deep, with entrance channel of same 
depth and 50 feet wide. 
Construction of inner basin 750 feet long, 390 feet 
wide and 8 feet deep, with entrance channel at same 
depth and 30 feet wide. 
37-33 
TABLE 37-B 
(Continued) 
Section 107, P.L. 86-645, 
Authorized by Chief of 
Engineers, Oct. 22, 1984. 
H. Doc. 958, 60th Cong., 
1st Sess. 
H. Doc. 325, 65th Cong., 
1st Sess. 
H. Doc. 150, 67th Cong., 
2d Sess. 
H. Doc. 320, 69th Cong., 
1st Sess. 
H. Doc. 110, 70th Cong., 
1st Sess? 
S. Committee Print, 
73d Cong., 2d Sess? 
S. Doc. 253, 79th Cong., 
2d Sess. 
H. Doc. 646, 80th Cong., 
2nd Sess. 
H. Doc. 151, 91st Cong., 
2d Sess. 
H. Doc. 237, 53d Cong., 
3d Sess. 
S. Doc 124, 80th Cong., 
2d Sess. 
H. Doc. 673, 61st Cong., 
2d Sess. 
H. Doc. 207, 65th Cong., 
1st Sess 
H. Doc. 186, 70th Cong., 
1st Sess.' 
S. Committee Print, 
74th Cong., 1st Sess. 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 672, 76th Cong., 
2d Sess? 
H. Doc. 202, 75th Cong., 
1st Sess. 
H. Doc. 350, 77th Cong., 
1st Sess. 
10. 
11. 
12.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
13. KALAMA TURNING BASIN, KALAMA, WA 
15. 
16. 
July 14, 1960 Provides a turning basin 40 feet deep. 
July 25, 1912 
Oct. 27, 1965 
Dec. 31, 1970 
Sep. 3, 1954 
Sep. 19, 1890 
June 25, 1910 
Mar. 3, 1925 
July 3, 1958 
Oct 22, 1976 
Oct. 1, 1980 
Mar. 2, 1919 
July 3, 1930 
Aug. 26, 1937 
June 30, 1948 
July 26, 1912 
Mar. 4, 1913 
Mar. 2, 1919 
Mar. 3, 1925 
Mar. 2, 1945 
June 30, 1948 
Sep. 3, 1954 
NEHALEM BAY, OR 
Two rubble-stone jetties. 
PORT ORFORD, OR 
Extension of existing breakwater by 550 feet. 
Dredging of turning basin 340 feet long, 100 feet 
wide, 16 feet deep. 
ROGUE RIVER HARBOR AT GOLD 
BEACH, OR 
Two jetties at entrance and improvement of channel. 
SIUSLAW RIVER, OR 
Build two high-tide stone jetties. 
Extends North Jetty 3,700 feet from old work constructed 
under previous project and provides for 
4,200 foot South Jetty. 
12-foot deep channel. 
18-foot bar channel and 16-foot river channel and a 
600-foot extension of North Jetty. (600-foot 
extension classified deferred.) 
Phase I advance engineering and design for north 
and south jetty extensions. 
Extending north and south jetties about 2,000 and 
2,500 feet, respectively. 
SKAMOKAWA CREEK, WA 
Channel 6.5 feet deep and 75 feet wide, at low water 
between Steamboat and Brooks Slough. 
SKIPANON CHANNEL, OR 
Channel from deep water in Columbia River to railroad 
bridge, 30 feet deep. 
Channel extending upstream from railroad bridge a 
distance of 4,500 feet. 
Mooring basin 12 feet deep at Warrenton. 
TILLAMOOK BAY AND BAR, OR 
Construct North Jetty 5,700 feet long and dredging 
channel 16 feet deep,.200 feet wide, to Bay City. 
Abandon that portion of project above Bay City. 
Abandon Bay City Channel and present project 
dimension of channels and turning basins with 
regulating works as needed. 
Repair damage and check erosion on Bayocean 
Peninsula caused by storm Jan. 1939. 
Dredging small-boat basin and approach at 
Garibaldi, OR, to depth of 12 feet. 
Closure of breach in Bayocean Peninsula. 
37-34 
TABLE 37-B 
(Continued) 
Section 107, P.L. 86-645 
Authorized by Chief of 
Engineers, Feb. 7, 1986 
H. Doc. 623, 62d Cong., 
2d Sess. 
S. Doc. 62, 88th Cong., 
2d Sess. 
H. Doc. 151, 91st Cong., 
2d Sess. 
S. Doc. 83, 83d Cong., 
2d Sess. 
H. Doc. 71, 51st 
Cong., 1st Sess. 
H. Doc. 648, 61st Cong., 
2d Sess. 
S. Committee Print, 
Serial, 68th Cong., 
1st Sess. 
H. Doc. 204, 85th Cong., 
1st Sess.' 
Final Report of Chief 
of Engineers 
P.L. 96-367 
H. Doc. 3, 63rd Cong., 
1st Sess. 
H. Doc. 278, 70th Cong., 
1st Sess ? 
H. Doc. 201, 75th Cong., 
1st Sess,. 
S. Doc. 93, 80th Cong., 
1st Sess. 
H. Doc 349, 62d Cong., 
2d Sess. 
H. Doc 760, 65th Cong., 
2d Sess. 
H. Doc. 562, 68th Cong., 
2d Sess. 
S. Doc. 35, 79th Cong., 
1st Sess. 
H. Doc. 650, 80th Cong., 
1st Sess. 
S. Doc. 128, 83d Cong., 
2d Sess.? 
18. 
19. 
20. 
21. 
22.

PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
23. 
Oct. 27, 1965 Construct South Jetty, 8,000 feet long. 
Sep. 22, 1922 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
June 20, 1938 
Mar. 2, 1945 
Mar. 2, 1945 
June 30, 1948 
Sep. 3, 1954 
June 25, 1910 
Aug. 8, 1917 
June 26, 19346 
Mar. 2, 1945 
Mar. 2, 1919 
Aug. 26, 1937 
Mar. 2, 1945 
July 24, 1946 
July 3, 1958 
July 14, 1960 
UMPQUA RIVER, OR 
North Jetty, 7,500 feet long. 
Present project dimensions of North Jetty and 
dredging ocean bar. 
A short south jetty. 
A full length south jetty and maintenance dredging 
to a 26-foot depth. 
Channel 22 feet deep and 200 feet wide from mouth 
to Reedsport 
Channel 22 feet deep and 200 feet wide from river 
channel to Gardiner, and turning basin 22 feet 
deep, 500 feet wide and 800 feet long. 
Channel 10 feet deep and 100 feet wide from river 
channel to dock in Winchester Bay with mooring 
and turning basin 10 feet deep, 175 feet wide, and 
300 feet long at inner end. 
Channel 12 feet deep and 100 feet wide from river 
channel to dock in Winchester Bay with mooring 
and turning basin 12 feet deep, 175 feet wide, and 
300 feet long at inner end. 
Channel 12 feet deep, Scholfield River.5 
WILLAMETTE RIVER AT WILLAMETTE 
FALLS, OR 
For purchase and rehabilitation of system and 
construction of concrete division wall. 
Deepening of locks 
Operation and care of canal and locks provided 
for with funds from War Department appropriations 
for Rivers and Harbors. 
Construction of New Willamette Falls Locks.8 
YAQUINA BAY AND HARBOR, OR 
Restoration and extension of jetties constructed under 
previous projects, rock removal at entrance, and 
dredging in bay up to railroad terminus at Yaquina. 
Extension of north jetty seaward 1,000 feet. 
26-foot channel of suitable width across entrance bar, 
as far as rock bottom will allow, a 20-foot channel 
300 feet wide along south side of bay to and including 
a turning basin 22 feet deep, 1,000 feet wide and 1,200 
feet long. 
Construct a small-boat mooring basin at Newport, OR. 
40-foot bar channel and 30-foot river channel 
extension of jetties at entrance. 
A small boat basin, south shore. 
37-35 
TABLE 37-B 
(Continued) 
S. Doc. 43, 89th Cong., 
1st Sess' 
H. Doc. 913, 65th Cong., 
2d Sess. 
H. Doc. 320, 69th Cong., 
1st Sess. 
H. Doc. 317, 70th Cong., 
1st Sess? 
Rivers and Harbors 
Committee Doc. 9, 
72d Cong., 1st Sess' 
S. Doc. 158, 75th Cong., 
3d Sess' 
S. Doc. 86, 76th Cong., 
1st Sess 
S. Doc. 191, 77th Cong., 
2d Sess' 
S. Doc. 154, 80th Cong., 
2d Sess' 
S. Doc. 133, 81st Cong., 
2d Sess' 
H. Doc. 202, 56th Cong., 
1st Sess. and Annual 
Report, 1900, P. 4374 
H. Doc. 1060, 62d Cong., 
3d Sess' 
H. Doc. 544, 75th Cong., 
3d Sess. 
H. Doc. 109, 65th Cong., 
1st Sess. 
S. Committee Print, 
75th Cong., 1st Sess. 
S. Doc. 119, 77th Cong., 
1st Sess' 
S. Doc. 246, 79th Cong., 
2d Sess. 
S. Doc. 8, 85th Cong., 
1st Sess? 
Section 107, P.L. 86-645 
Authorized by Chief of 
Engineers, Mar. 4, 1977 
24. 
25.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Oct. 23, 1962 
Mar. 7, 1974 
May 17, 1950 
June 28, 1938 
Dec. 22, 1944 
as amended 
June 28, 1938 
Dec. 22, 1944 
as amended 
Oct 23, 1962 
Oct. 7, 1970 
May 17, 1950 
Dec. 22, 1944 
as amended 
June 28, 1938 
Dec. 22, 1944 
as amended 
Oct. 23, 1962 
July 24, 1946 
37. 
May 17, 1950 
38. 
May 17, 1950 
APPLEGATE LAKE, ROGUE RIVER 
BASIN, OR 
Authorizes a rockfill embankment dam. 
27. 
28. 
Authorizes construction of project but no operation for 
irrigation until local interests agree to repay cost 
allocated. 
BLUE RIVER LAKE, OR 
Authorizes gravel-filled embankment dam. 
COTTAGE GROVE LAKE, OR 
Earthfill dam. 
Construction, operation, and maintenance of recreation 
facilities. 
DORENA LAKE, OR 
Earthfill dam. 
Construction, operation, and maintenance of recreation 
facilities. 
ELK CREEK LAKE, ROGUE RIVER BASIN, OR 
Roller compacted concrete dam. 
Authorizes construction but not operation for irrigation 
until local interests agree to repay cost allocated. 
FALL CREEK LAKE, OR 
Earth and gravel fill embankment dam. 
Construction, operation, and maintenance of recreation 
facilities. 
FERN RIDGE LAKE, OR 
Earthfill embankment dam. 
Construction, operation, and maintenance of recreation 
facilities. 
Raise height of dam to obtain additional storage. 
JOHN DAY RIVER (WEST), OR 
Construction of riprap bank protection. 
LOWER COLUMBIA RIVER BASIN, OR 
AND WA 
Bank protection work, improvements to existing 
projects, and construction of flood control works in 
Lower Columbia River Basin. 
LOWER COLUMBIA RIVER BASIN BANK 
PROTECTION, OR AND WA 
Provides bank protection on Columbia River below 
river mile 125 and along principal tributaries. 
37-36 
TABLE 37-B 
(Continued) 
26. 
H. Doc. 566, 87th Cong., 
2d Sess. 
P.L. 93-251 
H. Doc. 531, 81st Cong., 
2d Sess. 
H. Doc. 544, 75th Cong., 
3d Sess. 
Sec. 4, Flood Control Act 
of 1944 
H. Doc. 544, 75th Cong., 
3d Sess. 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 566, 87th Cong., 
2d Sess. 
P.L. 91-439 
H. Doc. 531, 81st Cong., 
2d Sess. 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 544, 75th Cong., 
3d Sess. 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 403, 87th Cong., 
2d Sess. 
Section 14, P.L. 79-526 
Authorized by Chief of 
Engineers, July 25, 1985 
H. Doc. 531, 81st Cong., 
2d Sess. 
H. Doc. 531, 81st Cong., 
2d Sess. 
29. 
30. 
31. 
32. 
36.

PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
July 30, 1983 
Aug. 15, 1985 
July 24, 1946 
June 28, 1938 
May 17, 1950 
June 22, 1936 
June 28, 1938 
May 17, 1950 
Oct. 27, 1965 
Aug. 30, 1935 
Aug. 20, 1937 
Dec. 22, 1944 
as amended 
Mar. 7, 1974 
Aug. 22, 1984 
May 17, 1950 
Sep. 3, 1954 
Oct. 23, 1962 
June 28, 1938 
39. 
P.L. 98-63 
P.L. 99-88 
40. 
42. 
43. 
37-37 
TABLE 37-B 
(Continued) 
MT. ST. HELENS AND VICINITY, WA 
Implement and maintain flood control measures 
on the Cowlitz and Toutle Rivers to assure flood 
protection for developed areas in the vicinity of such 
rivers against a one-hundred-year flood and to 
reduce sedimentation flow and the chance of blockage 
on the Columbia River. 
MT. ST. HELENS SEDIMENT CONTROL, WA 
Authorized construction of sediment and retention structures. 
WEST MAKINSTER ROAD, WILSON RIVER, OR 
Construction of riprap protection. 
WILLAMETTE RIVER BASIN, OR 
Comprehensive plan for flood control, navigation and 
other purposes in Willamette River Basin. 
General improvements. 
WILLAMETTE RIVER BASIN BANK 
PROTECTION, OR 
Bank protection works, with channel clearing. 
Provide additional protection against flooding. 
Addition of 77 locations to scope of projects. 
WILLOW CREEK LAKE, OR 
Storage project for flood control, recreation, and fish 
and wildlife. 
BONNEVILLE LOCK AND DAM-BONNEVILLE 
LAKE, OR AND WA 
Existing project was originally authorized Sep. 30, 
1933, by Federal Emergency Administration 
of Public Works. 
Existing project authorized by Congress. 
Completion, maintenance, and operation of 
Bonneville Project under direction of Secretary of War 
and supervision of Chief of Engineers, subject to 
certain provisions herein relating to powers and 
duties of Bonneville Power Administrator. 
Construction, operation, and maintenance of 
recreation facilities. 
Authorizes relocation of town of North Bonneville 
to new town site. 
Acquisition of Steigerwald Lake wetland area. 
COUGAR LAKE, OR 
Rockfill dam. 
Addition of power. 
Strube Lake reregulating dam. 
DETROIT LAKE, OR 
Authorizes concrete gravity structure. 
Sec. 14, P.L. 79-526 
Authorized by Chief of 
Engineers, July 3, 1985 
H. Doc. 544, 75th Cong., 
3d Sess. 
H. Doc. 531, 81st Cong., 
2d Sess. 
F.C. Act 1936 
H. Doc. 544, 75th Cong., 
3d Sess. 
H. Doc. 531, 81st Cong., 
2d Sess. 
H. Doc. 233, 89th Cong., 
1st Sess. 
S. Committee Print, 73d 
Cong., 2d Sess., (Report 
of Chief of Engineers 
dated Aug. 21, 1933) 
Sec. 4, Flood Control 
Act of 1944 
P.L. 93-251 
P.L. 98-396 
H. Doc. 531, 81st Cong., 
2d Sess. 
P.L. 83-780 
P.L. 87-874 
H. Doc. 544, 75th Cong., 
3d Sess. 
44. 
45. 
46. 
47. 
48.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
49. 
54. 
May 17, 1950 
Dec. 22, 1944 
as amended 
June 30, 1948 
May 17, 1950 
Sep. 3, 1954 
July 14, 1960 
May 17, 1950 
May 17, 1950 
Dec. 22, 1944 
as amended 
Mar. 24, 1965 
June 28, 1938 
Dec. 22, 1944 
as amended 
May 17, 1950 
Sep. 21, 1962 
Oct 15, 1966 
Addition of power and regulating Big Cliff Dam 
with power. 
GREEN PETER-FOSTER LAKES, OR 
Authorized Green-Peter Dam in lieu of originally 
authorized Sweet Home Lake (1938). 
Addition of power at Green-Peter and White Bridge 
Reregulating Dam. 
Changes location of reregulating dam from White 
Bridge location to Foster. 
HILLS CREEK LAKE, OR 
Earth and gravel fill dam. 
JOHN DAY LOCK AND DAM-LAKE 
UMATILLA, OR AND WA 
Multiple-purpose dam, flood control, navigation and 
power. 
Construction, operation, and maintenance of 
recreation facilities. 
John Day waterfowl management area. 
LOOKOUT POINT LAKE, OR 
Earth-and-gravel filled dam. 
Construction, operation, and maintenance of 
recreation facilities. 
Addition of power and authorization of Dexter Lake 
as reregulating dam. 
LOST CREEK LAKE, ROGUE RIVER 
BASIN, OR 
Rock and gravel fill embankment dam, including 
power. 
Authorizes construction of project but not operation 
for irrigation until local interests agree to repay cost 
allocated. 
THE DALLES LOCK AND DAMLAKE 
CELILO, WA AND OR 
Multiple-purpose dam, flood control, navigation and 
power. 
Construction, operation, and maintenance of 
recreation facilities. 
'Contains latest published maps. 
2Public Resolution 105, 67th Cong. 
3Public Works Administration 
4Includes following work, classified inactive. A channel to 
Hobsonville 200 feet wide and 16 feet deep, with a turning basin 
500 feet wide at Hobsonville, and regulating works as needed. 
5Inactive. 
6Permanent Appropriations Repeal Act. 
7Flood Control Act. 
8Classified deferred. 
9Spur Jetty "B" classified inactive. 
37-38 
TABLE 37-B 
(Continued) 
P.L. 858, 80th Cong., 
2d Sess. 
H. Doc. 531, 81st Cong., 
2d Sess. 
P.L. 83-780 
F.C. Act 1954 
S. Doc 104, 86th Cong., 
2d Sess. 
H. Doc. 531, 81st Cong., 
2d Sess. 
H. Doc. 531, 81st Cong., 
2d Sess. 
Sec. 4, Flood Control 
Act of 1944. 
S. Doc. 28, 89th Cong., 
1st Sess. 
H. Doc. 544, 75th Cong., 
3d Sess. 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 531, 81st Cong., 
2d Sess. 
H. Doc. 566, 87th Cong., 
2d Sess. 
P.L. 89-689, Public Works 
Approp. Act, 1967. 
H. Doc. 531, 81st Cong., 
2d Sess. 
Sec. 4, Flood Control 
Act of 1944 
50. 
51. 
52. 
53.

PORTLAND, OREGON DISTRICT 
TABLE 37-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Alsea River, OR 
Astoria Turning Basin, OR' 
Bandon Small Boat Basin, 
Coquille, OR 
Bridges, Columbia River, 
Cascade Locks and Hood River, 
OR (Alteration) 
Cathlamet, WA' 
Charleston Channel, Coos Bay, OR 
Clatskanie River, OR2 
Cowlitz River, WA 
Cushman-Mapleton Channels 
(Siuslaw River), OR' 
Deep River, WA2 
Depoe Bay, OR1 
Elochoman Slough, WA2 
Grays River, WA2 
Hammond Small Boat Basin, OR' 
Interstate Bridge, Columbia 
River, Portland, OR to 
Vancouver, WA (Alteration) 
Interstate Highway Bridge 
(Barge Channel), OR1 
Lake River, WA 
Lewis River, WA 
Long Tom River, OR 
Mooring for Battleship 
Oregon, OR 
Multnomah Channel, OR2 
Nestucca River, OR 
Oregon Slough (North Portland 
Harbor), OR2 
Salmon River, OR 2 
Smith River, OR2 
South Channel, Government Island, OR 
South Slough (Charleston), OR1 
The Cascades Canal, 
Columbia River, OR10 
The Dalles-Celilo Canal, OR 
and WA 11 
Umatilla Harbor, OR12 
Westport Slough, OR2 
Willamette River above Portland 
and Yamhill River, OR 
Winchester Bay, Umpqua River, OR 
Yaquina Bay and Harbor 
Small Boat Basin, OR' 
Yaquina River, OR1 
Yaquina River, OR 
Youngs and Klaskanine 
River, OR 
Youngs Bay and Youngs 
River, OR2 
1Authorized by Chief of Engineers (Sec. 107). 
2Channel adequate for present commerce. 
3Includes $15,537 for previous project. 
4Includes $23,489 for previous project. 
5Excludes $42,000 contributed funds. 
gExcludes $86,586 contributed funds. 
7Excludes $75,000 contributed funds. 
8Non-Federal funds, $1,204,100. 
9Includes $419,557 for Sec. 107 project. 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Abandoned 
Abandoned 
Abandoned 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1977 
1985 
1944 
1971 
1985 
1969 
1985 
1975 
1963 
1971 
1971 
1941 
1977 
1961 
1963 
1983 
1985 
1982 
1963 
1949 
1974 
1985 
1970 
1939 
1957 
1952 
1966 
1985 
1985 
1979 
1971 
1984 
2,000 
870,139 
1,173,524 
1,081,806 
171,467 
1,197,300 
19,2403 
277,436 
329,423 
15,384 
145,5885 
18,6416 
2,500 
519,0907 
1,154,1628 
15,281 
2,700 
58,132 
4,000 
25,000 
437,6699 
6,000 
16,881 
2,145 
143,120 
221,80016 
26,821 
3,903,780 
4,716,205 
16,276 
862,918 
1,616,369 
891,69513 
195,31314 
28,800 
2,000 
26,237 
-
- 
- 
194,8934 
1,474,036 
32,768 
16,648 
35,670 
58,127 
685,677 
90,514 
205,130 
559,858 
2,833,888 
171,909 
17,900,293 
749,69415 
1979 9,348 34,449 
1�Project abandoned due to flooding by Bonneville Dam 
pool.
11Project abandoned due to flooding by The Dalles Dam 
pool.
12Project transferred to Portland District from Walla 
Walla District FY 1974 and abandoned due to flooding by 
the John Day Dam pool. 
13Excludes $969,342 contributed funds. 
"4Excludes $50,565 contributed funds. 
"SExcludes $3,000 contributed funds. 
1"Includes $102,000 contributed funds. 
37-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 37-E OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
COLUMBIA RIVER BASIN 
Blind Slough Diking District, 
Clatsop County, OR Completed 1939 163,397 
Consolidated Diking and 
Improvement District 1, Cowlitz 
County, WA Completed 1941 163,291 
Deep River Area, Wahkiakum 
County, WA Completed 1942 69,724 
Deer Island Area, Columbia 
County, OR Completed 1943 574,123 
Diking District 2, Clatsop 
County, OR Completed 1940 43,150 
Diking Dist 5, Clatsop 
County, OR Completed 1940 25,609 
Diking and Improvement 
District 5, Cowlitz County, WA Completed 1940 161,381 
Diking District 1 and 3 (Puget 
Island) and Little Island, 
Wahkiakum County, WA Completed 1941 258,795 
Diking Improvement District 
1, Pacific County, WA Completed 1941 26,810 
Diking and Improvement 
District 4, Wahkiakum 
County, WA Completed 1951 169,542 
Drainage District 1, Clatsop 
County, OR Completed 1939 240,939 
John Day River Area, Clatsop 
County, OR Completed 1942 33,080 
Karlson Island, Clatsop 
County, OR Completed 1941 25,773 - 
Knappa Area, Clatsop County, OR Completed 1942 18,789 - 
Lewis and Clark River Area, 
Clatsop County, OR Completed 1942 158,419 
Lower Cowlitz River Area, 
Clatsop County, OR Completed 1962 181,652 
Magruder Drainage District, 
Columbia County, OR Completed 1940 61,186 
Marshland Drainage District, 
Columbia County, OR Completed 1940 39,475 
Midland Drainage District 
Columbia County, OR Completed 1939 77,7743 - 
Multnomah Drainage District 1, OR Completed 1951 593,0344 - 
Peninsula Drainage District 1, 
Multnomah County, OR Completed 1942 211,160 
Peninsula Drainage District 2, 
Multnomah County, OR Completed 1942 241,148 - 
Port of Kalama, WA1 Completed - 99,844 - 
Rainier Drainage District, 
Columbia County, OR Completed 1942 47,662 
Sauvie Island Areas A and B, 
Multnomah County, OR Completed 1951 1,623,505 - 
Scappoose Drainage District, OR Completed 1984 3,991,558 - 
Skamokawa Creek Area, 
Wahkiakum County, WA Completed 1946 178,885 - 
Wahkiakum County Consolidated Completed 1985 5,289,833 - 
Diking District No. 1, WA 
Tenasillahe Island, Clatsop 
County, OR Completed 1939 133,778 - 
Upper Grays River Area, WA Completed 1947 61,263 - 
State Hwy 101 & 401, Columbia River, WA Completed 1985 504,64213 
37-40

PORTLAND, OREGON DISTRICT 
TABLE 37-E OTHER AUTHORIZED FLOOD 
(Continued) CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Walluski River, Clatsop 
County, OR Completed 1942 66,932 
Warrenton Diking District 1, 
Clatsop County, OR Completed 1940 69,503 
Warrenton Diking District 2, 
Clatsop County, OR Completed 1940 117,143 
Warrenton Diking District 3, 
Clatsop County, OR Completed 1940 74,596 
Webb District Improvement Co., 
Columbia County, OR Completed 1940 84,592 
Westland District Improvement Co., 
Columbia County, OR Completed 1940 205,531 
Westport District, Columbia and 
Clatsop Counties, OR Completed 1943 40,658 
Woodson Drainage District, 
Columbia County, OR Completed 1940 22,797 
Youngs River Dikes, Clatsop 
County, OR Completed 1942 248,802 - 
Total Columbia River Basin 16,399,775 - 
LEWIS RIVER BASIN 
Diking and Improvement District 11, 
Cowlitz County, WA Completed 1943 172,521 
COWLITZ RIVER BASIN 
Cowlitz County Drainage 
Improvement District 1, WA Completed 1939 42,978 
Diking Improvement District 2, 
Cowlitz County, WA Completed 1940 121,165 
Diking Improvement District 13, 
Cowlitz County, WA Completed 1939 28,592 - 
Huntington Avenue, Castle Rock, WA Completed 1985 250,000 - 
Total Cowlitz River Basin 442,735 - 
LOWER COLUMBIA 
RIVER BASIN 
Beaver Drainage District, OR Completed 1984 3,131,944 - 
Columbia Drainage District 1, OR Inactive - - - 
Cowlitz County Consolidated Diking 
Improvement District No. 2, WA Completed 1977 1,661,367 
Cowlitz County Diking 
Improvement District 2, WA Completed 1967 363,000 
Cowlitz County Diking 
Improvement District 13, WA Completed 1967 65,345 
Cowlitz County Diking 
Improvement District 15, WA Completed 1967 304,794 - 
Cowlitz River, Hopkins Creek, WA' Completed - 236,860 - 
Deer Island Drainage District, OR Inactive - - - 
Hayden Island, OR Inactive 1950 - - 
Midland Drainage District, OR Completed 1971 304,511 - 
Multnomah County Drainage 
District 1, OR Completed 1964 1,499,186 - 
Peninsula Drainage District 2, OR Active 1961 35,265 - 
Rainier Drainage District, OR Completed 1967 593,945 - 
Sandy Drainage District, OR Completed 1954 154,0125 - 
Sauvie Island Drainage 
District, OR Completed 1966 674,137 - 
Vancouver Lake Area, WA Deferred 1981 889,391 - 
Wahkiakum Co. Diking 
District 4, WA Inactive 1971 48,619 
37-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 37-E OTHER AUTHORIZED FLOOD 
(Continued) CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Washougal Area Levees, 
Clark County, WA 
Woodson Drainage District, OR 
Total Lower Columbia River Basin 
WILLAMETTE RIVER BASIN 
Amazon Creek, OR 
Cascadia Lake, OR 
Gate Creek Lake, OR 
Holley Lake, OR 
Sandy River and Sleepy Hollow, OR1 
Shelton Ditch, OR 
Willamette River Basin 
Channel Clearing and Snagging 
Total Willamette River Basin 
ALL OTHER FLOOD CONTROL 
Arlington, Alkali Canyon, OR9 
Bear Creek, Medford, OR1 
Beaver Creek Near Tillamook, OR2 
Castle Rock, Cowlitz River, WA 
Catching Inlet Drainage District 
Coos River, OR2 
Chewaucan River, Paisley, OR1 
Clackamas River at Dixon 
Farm Location, OR2 
Days Creek Lake, OR (Phase I) 
Depoe Bay, Lincoln County, OR' 
Johnson Creek, OR 
McDonald Dike Road, Nehalem River, OR 
McKenzie River Near Walterville, OR2 
Miami River, OR' 
Mill Four Drainage District, 
Yaquina River, OR 
Molalla River at Milk Creek 
Location, OR2 
Molalla River at Ressel 
Location, OR2 
Nestucca River, Condor Road, OR' 
Nestucca River, Vicinity 
Pacific City, OR' 
Pendleton Levees, Umatilla River, OR 11 
(a)Riverside Area Units 
(b)State Hospital and City 
Areas (Zone 1) 
(c)State Hospital and City 
Areas (Zone 2)2 
Pendleton, Umatilla River, 
OR' 0 
Reedsport Levees, Umpqua 
River, OR2 
Rogue River, OR1 
Salmon Creek at Oakridge, 
OR2 
Salmon Creek Near Vancouver, WA 
Siuslaw River, Lane County, 
OR' 
Stillwell Drainage District, 
Tillamook Bay, OR2 
Sumner Parker Airport, OR1 
Completed 
Completed 
Completed 
Deferred 
Deferred 
Deferred 
Completed 
Inactive 
1973 
1964 
1960 
1976 
1972 
1963 
1967 
Inactive 
1,803,488 
162,500 
11,928,364 
1,214,3006 
1,066,114' 
840,0008 
241,992 
276,700 
39,624 
3,678,731 
23,439 
23,050 
106,198 
104,921 
182,655 
42,761 
70,84510 
1,307,216 
22,963 
170,245 
29,500 
148,358 
15,321 
118,433 
55,007 
55,189 
11,690 
16,000 
9,100 
267,748 
161,540 
143,263 
968,71612 
86,230 
288,447 
435,00014 
215,939 
176,351 
92,500 
Abandoned 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Active 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1950 
1967 
1957 
1959 
1952 
1982 
1981 
1985 
1967 
1948 
1955 
1952 
1960 
1959 
1960 
1939 
1971 
1960 
1985 
1961 
37-42

PORTLAND, OREGON DISTRICT 
TABLE 37-E OTHER AUTHORIZED FLOOD 
(Continued) CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Trask River, Tillamook County, 
OR' 
Tualatin, OR 
Umatilla River, Stanfield, OR1 
Umatilla River, Thorn Hollow, OR 
Umpqua River and 
Tributaries, OR 
Vicinity of Nehalem, Nehalem 
River, OR 
Wilson River, Vicinity 
Highway 101, OR1 
Total All Other Flood Control 
'Authorized by Chief of Engineers (Sec. 14). 
2Authorized by Chief of Engineers (Sec. 205). 
3Includes $26,241, Emergency Relief Act funds. 
4Excludes $25,000 contributed funds. 
SPrevious completed project, $138,956; $15,056 engineering 
costs project constructed by local interests. 
6Excludes $154,751 contributed funds. 
'Includes $112,000 pro rata share of site selection in lieu 
of Sweet Home. 
8Includes $95,000 pro rata share of site selection in lieu of 
Quartz Creek Lake. 
9Project transferred from Walla Walla District FY 1974 and 
abandoned due to flooding by the John Day Dam pool. Includes 
$3,328 FY 1960 preauthorization costs, Sec. 205, P.L. 80-858. 
See FY 1960 Annual Report, page 1887. 
'�Excludes $2,520 contributed funds. 
"Reported by Walla Walla District prior to 1974. 
12Excludes $230,070 constributed funds for new work and 
$31,284 Government furnished sheet steel pile. 
37-43 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1984 
1985 
1985 
1952 
1952 
121,273 
1,803,094 
33,835 
154,600 
428,881 
45,677 
30,000 
7,965,985

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 37-F OTHER AUTHORIZED MULTIPLE PURPOSE 
PROJECTS, INCLUDING POWER 
For Last Cost to Sep. 30, 1986 
Full Report 
See Annual Operation 
and 
Project Status Report For Construction Maintenance 
Restoration of Indian Fishing Grounds, 
Bonneville, OR Completed 1969 185,000 
TABLE 37-G DEAUTHORIZED PROJECTS 
For Last Contri- 
Full Report Date Federal buted 
See Annual Deauth- Funds Funds 
Project Report For orized Expended Expended 
Area East of Albany, OR - 1977 
Bachelor Island, WA - 1977 
Bear Creek, Long Tom River, OR 1966 1971 
Calapooya River, OR 1959 1965 
Clatskanie River Area, Columbia County, OR 1960 1965 
Clatskanie Drainage Dist. 1, OR 1964 1978 
Clatsop County Drainage District 1, OR 1960 1974 
Clatsop County Diking District 3, OR 1938 1961 
Clatsop County, Diking District 4, OR - 1978 
Clatsop County Diking District 6, OR 1961 1978 
Columbia Slough, OR 1953 1978 
Coquille River, OR 1948 1953 
Cowlitz County Consolidated Diking Improvement Dist. 1, OR - 1977 
Cowlitz River at Randle, WA 1962 1977 
Coyote and Spencer Creek, Long Tom River, OR 1960 1970 
East Muddy and Lake Creek, OR 1959 1970 
Ferguson Creek, Long Tom River, OR - 1978 
Flat Creek, Long Tom River, OR - 1977 
Floodwall and Levees at Portland, OR - 1977 
John Drainage District, OR 1961 1979 
John Day River, OR 1974 1974 
Kalama River (South Area) Levee, Cowlitz County, WA 1969 1978 
Lake River Delta Area, WA - 1977 
Lewis River Area, WA - 1978 
Magruder Drainage District, OR 1940 1974 
Mud and Basket Slough Rickreall Creek, OR - 1977 
Peninsula Drainage District 1, OR 1942 1977 
Pilot Rock, Birch Creek, OR 1963 1968 
Prescott Area, Columbia County, OR 1941 1978 
Prineville Area, Crooked River and Ochoco Creek, OR 1962 1977 
Pudding River, OR 1950 1979 
Skamokawa (Steamboat Slough), WA 1939 1979 
Soap Creek, WA - 1977 
Turner Prarie, Mill Creek, OR - 1978 
Umatilla River (Echo), OR 1960 1964 
Waldo Lake Tunnel, OR - 1958 
West Muddy Creek and Mary's River, OR 1962 1970 
Westport Slough, OR (Modification for 32-foot channel) 1966 1977 
Wiley Creek Lake, OR - 1960 
Willamette Falls Fishladder, OR - 1961 
37-44 
- 
4,559 
11,595 
268 
18,543 
4,472 
258 
8,824 
21,352 
908 
- 
11,095 
6,819 
6,465 
23,754 
210,220 
55,594 
774 
43,292 
4,558 
125 
11,318 
5,000 
24,145 
4,056 
112,000

PORTLAND, OREGON DISTRICT 
TABLE 37-H COLUMBIA AND LOWER WILLAMETTE RIVER 
BELOW VANCOUVER, WA, AND PORTLAND, OR 
TOTAL COST OF EXISTING PROJECT TO SEP. 30, 1986 
(See Section 3 of Text) 
Funds New Work Maintenance Total 
Regular 26,235,146 234,760,144 260,995,290 
Public Works 446,296 14,515 460,811 
Emergency Relief Administration 138,449 98,668 237,117 
Total U.S. 26,819,891 234,873,327 261,693,218 
Contributed Prior to 1964 223,026 24,320 247,346 
Contributed (1975) 35 to 40-foot Channel 442,928 - 442,928 
Total Contributed 665,954 24,320 690,274 
Total All Funds 27,485,845 234,897,647 262,383,492 
TABLE 37-I NAVIGATION ACTIVITIES PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645 (PREAUTHORIZATION) 
Study Identification Fiscal Year Costs (1986) 
Astoria Deep Draft Anc, OR $29,190 
Columbia River, Kalama, WA 32,400 
Columbia River, Longview, WA 38,423 
Columbia River, Reed Island, OR and WA 7,500 
Columbia River (DDA), Vancouver WA 15,577 
Columbia River, Willow Bar, OR and WA 7,500 
Coquille River, Bandon, OR 24,954 
SKamokawa Creek, WA 500 
TOTAL $156,044 
TABLE 37-J PROJECT CONDITION SURVEYS 
Project Date Survey Conducted 
Depoe Bay, OR April 1986 
Tillamook, OR September 1986 
Willamette River, OR February/Sept. 1986 
Youngs Bay, OR January 1986 
TABLE 37-K WILLAMETTE RIVER AT 
WILLAMETTE FALLS, OR 
PRINCIPAL FEATURES OF EXISTING CANAL AND LOCKS 
(See Section 24 of Text) 
Usable Lock Dimensions Series of 4 locks, each 175 feet by 37 feet1 
Lift of Each Lock Lock 1 (Lower), 22.5 feet; Lock 2, 8.7 feet; 
Lock 3, 10.9 feet and Lock 4 (Upper), 8.1 feet 2 
Depth of Miter Sills at Lower Water Lower Lock, 8.4 feet; Upper Lock, 6 feet 
Character of Foundation Rock 
Kind of Dam Fixed3 
Type of Construction Concrete 
Year of Completion 1873; Purchased by United States Apr. 26, 1915 
Cost Unknown; purchase price $375,000 
1A guard lock 210 by 40 feet, which is used only at higher 
states of water, is at upper end of canal basin. 
2A concrete division wall, 1,227 feet long, extending from 
Lock 4 to Guard Lock, separates upper basin of canal from head 
race, which formerly led directly from basin and supplied water 
for powerplants operated by Crown Zellerbach Corp., and 
Portland Ry., Light & Power Co., which is now being operated 
by Portland General Electric Co. 
3The dam is owned by private parties. 
37-45

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 37-L FLOOD CONTROL ACTIVITIES PURSUANT TO 
SECTION 205, PUBLIC LAW 80-858 (PREAUTHORIZATION) 
Study Identification Fiscal Year Costs (1986) 
Clatskanie River, OR $ 7,500 
Clatsop County Drainage District Nos. 2 and 5, OR 587 
Deschutes River, Bend, OR 25,848 
Libby Dike, Coos County, OR 56,320 
Salmon Creek Levee, Oakridge, OR 32,319 
Tucker and Battle Creeks Dike, OR 413 
Umatilla at Riverside, OR 7,266 
Warrenton Diking Dist. I, OR 154,117 
Youngs River Dike No. 22, OR 15,865 
TOTAL $ 300,235 
37-46

PORTLAND, OREGON DISTRICT 
TABLE 37-M FLOOD CONTROL RESERVOIR OPERATIONS 
See 
Section 
in Text 
26. 
27. 
28. 
47. 
48. 
29. 
31. 
32. 
49. 
49. 
Hills Creek Lake, OR 
Lookout Point Lake, OR 
Lost Creek Lake, OR 
Project 
Applegate Lake, OR 
Blue River Lake, OR 
Cottage Grove Lake, OR 
Cougar Lake, OR 
Detroit Lake, OR 
Dorena Lake, OR 
.Fall Creek Lake, OR 
Fern Ridge Lake, OR 
Foster Lake, OR 
Green Peter Lake, OR 
37-47 
50. 
52. 
53. 
Date of 
Peak Inflow 
February 18, 1986 
February 23, 1986 
February 23, 1986 
February 23, 1986 
February 23, 1986 
February 23, 1986 
February 23, 1986 
February 23, 1986 
February 23, 1986 
October 23, 1985 
November 7, 1985 
November 15, 1985 
February 23, 1986 
February 23, 1986 
February 23, 1986 
February 18, 1986 
Peak Inflow 
Cu. Ft./Sec. 
7,550 
11,470 
6,030 
15,060 
54,480 
16,480 
13,660 
10,020 
24,700 
8,580 
10,360 
9,210 
40,010 
21,290 
33,560 
15,650 
Storage Used 
Acre/Feet 
19,130 
34,000 
18,070 
59,190 
127,850 
45,360 
43,180 
34,960 
23,010 
23,890 
13,600 
9,860 
127,780 
71,910 
130,100 
41,500

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 37-N LOWER COLUMBIA RIVER BASIN, OR AND WA 
LEVEES AND IMPROVEMENTS TO EXISTING WORKS 
(See Section 37 of Text) 
Estimated Cost 
of Work 
Location Approved 1986 
Beaver Drainage District, OR 
Cowlitz County Diking Improvement District 2, WA 
Cowlitz County Diking Improvement District 13, WA 
Cowlitz County Diking Improvement District 15, WA 
Cowlitz County Consolidated Diking Improvement District 2, WA 
Midland Drainage District, OR 
Multnomah County Drainage District 1, OR 
Peninsula Drainage District No. 2, OR 
Rainier Drainage District, OR 
Sandy Drainage District, OR 
Sauvie Island Drainage District, OR 
Scappoose Drainage District, OR 
Wahkiakum County Consolidated Diking District 1, WA 
Woodson Drainage District, OR 
Total Estimated Cost, Federal Funds 
Estimated Non-Federal Cost 
Locations deauthorized or reclassified inactive and excluded from above cost estimate: 
Bachelor Island, WA (Deauthorized - 1977) 
Clatskanie Drainage District, OR (Deauthorized - 1978) 
Clatskanie River Area, OR (Deauthorized - 1965) 
Clatsop County Drainage District 1, OR (Deauthorized - 1974) 
Clatsop County Diking District 4, OR (Deauthorized - 1978) 
Clatsop County Diking District 6, OR (Deauthorized - 1978) 
Columbia Drainage District 1, OR (Inactive) 
Cowlitz County Consolidated Diking Improvement District 1, WA (Deauthorized - 1977) 
Deer Island Drainage District, OR (Inactive) 
Hayden Island, OR (Inactive) 
John Drainage District, OR (Deauthorized - 1979) 
Kalama River Levee, WA (Deauthorized - 1978) 
Lake River Delta Area, WA (Deauthorized - 1977) 
Lewis River Area, WA (Deauthorized - 1977) 
Magruder Drainage District, OR (Deauthorized - 1974) 
Peninsula Drainage District 1, OR (Deauthorized - 1977) 
Wahkiakum County Diking District 4, WA (Inactive) 
1Cost is for Engineering only. Project was constructed by local interests. 
37-48 
$ 2,857,366 
363,000 
65,345 
304,794 
1,661,367 
304,511 
1,499,186 
3,197,000 
593,945 
15,0561 
674,137 
3,567,248 
5,289,833 
162,500 
20,555,288 
3,300,000

PORTLAND, OREGON DISTRICT 
TABLE 37-0 WILLAMETTE RIVER BASIN 
COMPREHENSIVE PLAN 
(See Section 43 in Text) 
Estimated 
Federal 
Project Authorizing Act Cost (1986) 
Blue River Lake, McKenzie Basin ' * 
Cascadia Lake, South Santiam River 4 s 
Channel Clearing and Snagging on Willamette 
River and Major Tributaries6 
Channel Improvements for Flood Control 
Major Drainage on 16 Streams 
Tributary to Willamette River' ' 
Cottage Grove Lake, Coast Fork' 
Cougar Lake, South Fork McKenzie' 3 
Detroit Lake, Including Big Cliff Lake, 
North Santiam River' 
Dorena Lake, Row River' 
Fall Creek Lake, Middle Fork' 
Fern Ridge Lake, Long Tom River,' 
Gate Creek Lake, McKenzie Basin 3 5 
Green Peter-Foster Lakes, Middle Santiam' 4 
Hills Creek Lake, Middle Fork' 
Holley Lake, Calapooya Rivers 
Johnson Creek, Vicinity of Portland, OR 
Lookout Point Lake, Including Dexter Lake, 
Middle Fork' 
Strube Lake & Cougar Additional Unit, 
(South Fork McKenzieXModification to 
Cougar Lake) 
Waldo Lake Tunnel and Reregulating Works 
North Fork, Middle Fork, Willamette River 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
Oct. 23, 1962, H. Doc. 403, 
87th Cong., 2d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. and 
Sep. 3, 1954, S. Doc. 131, 
83d Cong., 2d Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3d Sess. and 
June 30, 1948, Public Law 
858, 80th Cong., 2d Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3d Sess. 
Oct. 23, 1962, H. Doc. 403, 
87th Cong., 2d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. and 
Sep. 3, 1954, S. Doc. 131, 
83d Cong., 2d Sess. and 
July 14, 1960, S. Doc. 104 
86th Cong., 2d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 2d Sess. and 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
Oct. 23, 1962, H. Doc. 403, 
87th Cong., 2d Sess. 
May 17, 1950, H. Doc. 5318, 
81st Cong., 2d Sess. 
$ 32,038,2252 
104,000,000 
(1975) 
3,005,000 
(1960) 
1,214,3003 
4,013,1232 9 
56,750,4052 10 
62,729,6982 
14,568,2622 9 
22,118,2642 9 
8,526,9352 9 
127,000,000 
(1980) 
84,005,7882 
45,700,6192 
13,300,000 
(1960) 
5,670,000 
88,238,3952 9 
102,000,000 
37-49

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 37-0 WILLAMETTE RIVER BASIN 
(Continued) COMPREHENSIVE PLAN 
(See Section 43 of Text) 
Estimated 
Federal 
Project Authorizing Act Cost (1986) 
Willamette River Bank Protection1 June 22, 1936, Special Report 31,300,000 
Division Engr., June 28, (1985) 
1938, H. Doc. 544, 75th 
Cong., 3d Sess., and May 17, 
1950, H. Doc. 531, 81st 
Cong., 2d Sess. 
1See individual reports for details of the project. 7Does not include Reclassified Locations. 
2Actual cost. sAuthorization rescinded August 28, 1958, Public Law 
3For construction in lieu of originally authorized Quartz 85-820. 
Creek Lake. 9Includes cost of Recreation Facilities at Completed Projects. 
4For construction in lieu of originally authorized Sweet (710). 
Home Lake. 10Does not include $96,000 pro rata share of site selection 
5Project classified deferred. costs in lieu of Quartz Creek Lake and Strube Lake and Cougar 
6Project classified inactive. Additional Units. 
37-50

PORTLAND, OREGON DISTRICT 
TABLE 37-P PRINCIPAL DATA CONCERNING NAVIGATION 
LOCK, SPILLWAY DAM, AND POWERPLANT 
Project 
Bonneville Lock and Dam, 
OR and WA-Lake 
Bonneville 
(See Section 46 of Text) 
John Day Lock and Dam, 
OR and WA-Lake 
Umatilla (See Section 51 
of Text) 
NAVIGATION LOCK 
Dimensions: 
Clear Width of Chamber 
Greatest Length Available for Full Width 
Lift (Vertical): 
At Extreme Low Water and Normal Pool Level 
At Normal River Stage 
At Extreme High Water 
Depth Over Miter Sills at Adopted Low Water 
Character of Foundation 
Opened to Navigation
SPILLWAY DAM 
Type of Construction 
Completed 
Capacity 
Elevation of Gate Sills on Crest of Spillway 
Height Above Lowest Foundation 
Length of Dam Proper 
Length of Dam Overall 
Width at Base 
Gate Openings 
Crest Overflow (Above Mean Sea Level) 
Pool Elevation (NormalXAbove Mean Sea Level) 
POWERPLANT 
Length 
Length (Second Powerhouse) 
Width 
Width (Second Powerhouse) 
Height (Roof to Bedrock) 
Height (Roof to BedrockXSecond Powerhouse) 
Generator (Station Unit) 
Generators 
Generators (Second Powerhouse) 
Fishwater Supply Units (Second Powerhouse) 
Total Rated Capacity 
Speed 
NAVIGATION 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
76 Feet 
500 Feet 
66 Feet 
59 Feet 
About 30 Feet 
24.2 Feet 
Andesite 
January 1938 
Concrete Gravity 
1938 
1,600,000 Cubic Feet 
Per Second 
23.3 Feet 
About 170 Feet 
1,090 Feet 
1,230 Feet 
200 Feet 
18 
24 Feet 
72 Feet 
1,027 Feet 
953 
190 Feet 
235 
190 Feet 
200 Feet 
1-4,000 kw 
2 @ 43,200 kw each 
8 @ 54,000 kw each 
8 @ 66,500 kw each 
2 @ 13,100 kw each 
1,076,600 kw 
75 Revolutions per 
Minute 
86 Feet 
669 Feet 
97 Feet 
105 Feet 
113 Feet 
15 Feet 
April 1968 
Concrete Gravity 
March 1968 
2,250,000 cfs 
210 
Tainter 
50 Ft. by 58.5 Ft. 
20 
37-51

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 37-P PRINCIPAL DATA CONCERNING NAVIGATION 
(Continued) LOCK, SPILLWAY DAM, AND POWERPLANT 
Project 
The Dalles Lock and Dam, 
WA and OR-Lake Celilo 
(See Section 54 of Text) 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Space for Additional 
Rating, Each 
Total Installed Capacity 
Total Potential Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Flood Control Storage 
Lake Length 
Lake Water Surface Area at 
Elevation 268 
Navigation Channel, Depth by Width 
Length of Shoreline
NAVIGATION LOCK 
Type 
Lift Normal 
Net Clear Length 
Net Clear Width 
Normal Depth Over Upper Sill 
Minimum Depth Over Lower Sill 
Opened to navigation 
SPILLWAY DAM 
Type 
Elevation of Crest 
Top of Crest Gates 
Number of Gates 
Size of Gates 
Height (Foundation to Crest) 
Design Flood 
POWERPLANT 
Powerhouse Dimensions 
Generators Main Units 
Generators Main Units 
Fishwater Supply Units 
Total Rated Capacity 
Station Service Units 
1,975 Feet 
243 Feet 
16 
4
135,000 kw 
2,160,000 kw 
2,700,000 kw 
235 Feet 
July 1968 
268-257 
276 
500,000 Ac.-Ft. 
76.4 Miles 
55,000 Acres 
15 Ft. by 250 Ft. 
200 Miles 
Single Lift 
87.5 Feet 
675 Feet 
86 Feet 
20 Feet 
15 Feet 
March 17, 1957 
Controlled 
121 Ft. msl 
162 Ft msl 
23 
50 by 43 Feet 
120 Feet 
2,290,000 cfs 
240 by 2,150 Feet 
14 @ 78,000 kw each 
Additional 8 @ 
86,000 kw each 
2 @ 13,500 kw each 
1,807,000 kw 
2 @ 3,000 kw each 
37-52

SEATTLE, WA, DISTRICT * 
This District comprises Washington State except southern 
and southeastern portions, northern Idaho, and northwestern 
Montana embraced in drainage basins tributary 
to Pacific Ocean south of international boundary to Cape 
Disappointment, and to Columbia River above Yakima 
River, inclusively. 
IMPROVEMENTS 
Navigation 
1. Anacortes Harbor, WA.................. 
2. Bellingham Harbor, WA ............... 
3. Ediz Hook, WA ....................... 
4. Edmonds Harbor, WA ................. 
5. Everett Harbor and Snohomish 
River, W A ........................... 
6. Grays Harbor and Chehalis 
River, WA ........................... 
7. Kenmore Navigation Channel, WA ...... 
8. Lake Washington Ship Canal, WA ....... 
9. Navigation Work under Special 
Authorization ......................... 
10. Olympia Harbor, WA .................. 
11. Project Condition Surveys .............. 
12. Puget Sound and its 
Tributary Waters, WA ................. 
13. Quillayute River, WA ................. 
14. Seattle Harbor, WA ................... 
15. Swinomish Channel, WA ............... 
16. Tacoma Harbor, WA ................... 
17. Waterway Connecting Port Townsend 
and Oak Bay, WA ..................... 
18. Willapa River and Harbor and 
Naselle River, WA .................... 
Beach Erosion Control 
19. Beach Erosion Work under Special 
Authorization ......................... 
Flood Control 
20. Dungeness River, Sequim, WA .......... 
21. Howard A. Hanson Dam, WA ........... 
22. Inspection of Completed Flood 
Control Projects ....................... 
23. Inspection of Completed PL-99 Works .... 
24. Middle Fork Nooksack River, 
Deming, WA 
25. Mud Mountain Dam, WA.............. . 
26. Placer Creek, ID ................... ... 
27. Scheduling Flood Control 
Reservoir Operations .................. 
Page 
38-2 
38-2 
38-2 
38-2 
28. Stillaguamish River, WA........ 
29. Tacoma, Puyallup River, WA .... 
30. Wynoochee Lake, WA........... 
Multiple-Purpose Projects, 
38-3 Including Power 
31. Albeni Falls Dam, ID ........... 
38-3 32. Chief Joseph Dam - Rufus Woods 
38-4 Lake, WA ..................... 
38-4 33. Libby Dam - Lake Koocanusa, MT 
38-4 General Investigations 
38-5 34. Surveys................. 
38-5 35. Collection and Study of 
Basic Data .............. 
38-5 36. Continuation of Planning 
38-5 and Engineering ......... 
38-6 
38-6 Tables 
Qc) -- 
Page 
....... 38-9 
....... 38-10 
....... 38-10 
....... 38-10 
....... 38-10 
....... 38-11 
............. 38-11 
............. 38-12 
............. 38-12 
7O-I Table 38-A Cost & Financial Statement .... 38-14 
Table 38-B Authorizing Legislation ....... 38-19 
38-7 Table 38-C Other Authorized Navigation 
Projects ..................... 38-25 
38-8 Table 38-D Not Applicable 
Table 38-E Other Authorized Flood Control 
Projects ..................... 38-26 
Table 38-F Other Authorized Multiple 
38-8 Purpose Projects, Including 
Power ...................... 38-30 
Table 38-G Deauthorized Projects ......... 38-30 
38-8 Table 38-H Lake Washington Ship Canal, WA 
38-8 Principal Features of Double 
Lock and Dam ............... 38-31 
38-8 Table 38-I Project Condition Surveys ...... 38-31 
38-9 Table 38-J Flood Control Activities 
Pursuant to Section 205, Public 
38-9 Law 80-858 .................. 38-32 
38-9 Table 38-K Emergency Flood Control 
38-9 Activities - Public Law 99, 84th 
Congress .................... 38-32 
38-9
38-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. ANACORTES HARBOR, WA 
Location. On northern point of Fidalgo Island in Puget 
Sound, 17 miles south of Bellingham, WA, and 64 miles 
north of Seattle. The main harbor is on Guemes Channel. 
(See NOAA Survey Chart 18427.) 
Existing project. Channel in Capsante Waterway, 12 
feet deep and 150 to 250 feet wide, between east side of 
Q Avenue and deep water in Fidalgo Bay, a distance of 
2,850 feet; and mooring basin 12 feet deep, 570 feet wide, 
and 960 feet long adjacent to north side of Capsante 
Waterway, protected by two pile breakwaters, each 470 
feet long, east and southeast of basin. Plane of reference 
is mean lower low water. Range between mean lower low 
water and mean higher high water is 8.2 feet. Extreme 
range is about 15.5 feet. Project was completed in July 
1957, excluding the inactive portion and inner portion of 
boat basin. (For further details, see Annual Report for 
1958.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 24 piers and wharves 
in the Port of Anacortes; 15 on Guemes Channel, 3 on 
Capsante Waterway, and 7 on Fidalgo Bay. Three 
wharves on Guemes Channel are open for public use; of 
these, one is publicly owned and operated and used for 
handling general cargo in foreign and domestic trade. In 
addition, two wharves are used for ferries plying to the 
San Juan Islands and to Vancouver Island, British Columbia. 
Both are publicly owned and operated. Two of the 
wharves on Capsante Waterway and basin are publicly 
owned and operated and used for receiving petroleum products, 
and as a moorage for fishing and pleasure craft. 
All other wharves are used for general industrial purposes. 
In addition, there are two oil-refinery wharves 
located to the south of Capsante Waterway that are 
privately owned and operated and used for handling 
petroleum products in foreign and domestic trade. These 
facilities are considered adequate for existing commerce. 
(See Port Series No. 37 - Ports of Everett, Bellingham, 
Port Angeles, and Anacortes, WA, revised 1976). 
Operations during fiscal year. Maintenance, hired 
labor: Conducted channel conditions surveys. Channel 
sediments were analyzed to determine suitability of 
dredged material for open-water disposal. Puget Sound 
Dredged Disposal Analysis study costs resulted in an expenditure 
of $120,000. 
2. BELLINGHAM HARBOR, WA 
Location. Part of Bellingham Bay, an arm of Puget 
Sound, at Bellingham, in northwestern Washington. (See 
NOAA Survey Chart 18424.) 
Existing project. Channel 30 feet deep in Whatcom 
Creek Waterway from deep water to head of harbor, 363.2 
feet wide to 750 feet from inner end, thence 18 feet deep 
for inner 750 feet; Squalicum Creek Waterway, including 
dredging an entrance channel 200 feet wide and 26 feet 
deep from deep water in the bay to main pierhead line, 
and maintenance of southerly half and westerly end of 
Squalicum Creek basin to 26 feet deep, provided that no 
dredging can be done within 75 feet of wharves, piers, or 
similar structures; and small-boat basin adjacent to 
Squalicum Creek Waterway by construction and 
maintenance of two sections of rubblemound breakwater 
with combined length of 5,400 feet, including 
maintenance of minimum depths of 12 feet in entrance 
to basin. Plane of reference is mean lower low water. 
Range between mean lower low water and mean higher 
high water is 8.6 feet. Extreme range is about 16 feet. 
Project was completed in February 1961. (For further 
details see Annual Report for 1961. For details relating 
to previous project see page 797 of Annual Report for 
1907.) 
Local cooperation. Fully complied with. Requirements 
are described in full on page 38-2 of FY 1980 
Annual Report. 
Terminal facilities. Of the forty wharves and piers 
in Bellingham Harbor, 9 are on Whatcom Creek Waterway; 
3 on Squalicum Creek Waterway; 3 on I&J Street 
Waterway; and 9 on Bellingham Bay. Two wharves on 
Whatcom Creek Waterway serve general cargo terminals. 
One is publicly owned and operated and is suitable for 
use by ocean-going vessels; the other one is privately 
owned and operated. There is one publicly owned terminal 
and small-boat harbor with 11 wharves handling private 
craft and fishing boats. (See Port Series No. 37 - Ports of 
Everett, Bellingham, Port Angeles, and Anacortes, WA, 
revised 1976.) 
Operations during fiscal year. Maintenance, hired 
labor: Conducted channel condition surveys. 
3. EDIZ HOOK, WA 
Location. Ediz Hook and the city of Port Angeles are 
on the Strait of Juan de Fuca in Clallam County, WA, 
about 100 miles northwest of Seattle. (See NOAA Survey 
Chart 18468.) 
Existing project. Provides for about 13,300 lineal feet 
of rock revetment and 3,100 lineal feet of rock blanketing, 
together with initial beach replenishment and annual 
nourishment. Project was completed in October 1978. (For 
further details, see Annual Report for 1979.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 17 docks, wharves, and 
piers in Port Angeles protected by Ediz Hook, of which 
nine are public. Four of the private docks are operated 
by timber mills for transfer of logs, pulp and fuel. There 
are five general cargo/log docks, a ferry dock, three 
moorage docks (including docks for the Coast Guard and 
pilots), a fish unloading dock, and three log dump piers. 
Operations during fiscal year. Maintenance, hired 
labor: Annual inspection and coordination with local 
sponsor. 
4. EDMONDS HARBOR, WA 
Location. On easterly shore of Puget Sound in northwestern 
Washington, about 9 miles north of Seattle and 
immediately north of Edward's Point. (See Coast and 
Geodetic Survey Chart 6445.) 
Existing Project. Maintenance of breakwaters and entrance 
channel of small-boat harbor, at estimated cost of 
38-2

SEATTLE, WASHINGTON DISTRICT 
$5,000 annually. Project consists of mooring basin about 
600 feet wide and 1,100 feet long, varying from 8 to 13 
feet deep; a rubblemound breakwater about 1,850 feet 
long and with a top elevation of 18.5 feet, extending along 
southerly and westerly sides of basin; a rock-reinforced 
treated pile and plank breakwater about 250 feet long, 
extending from shore along northerly side of basin; an 
entrance channel 13 feet deep and about 610 feet long, 
with a minimum width of 65 feet between deep water in 
the Sound and the basin; and the necessary navigation 
lights. Project was constructed by local interests and completed 
in April 1962. 
Local cooperation. Fully complied with, except that the 
Port of Edmonds was not in compliance with "open to all 
on equal terms" provision, requiring termination of a 
breakwater repair contract in FY 1985. Compliance to 
this provision was reinstated in FY 1986. Requirements 
are described in full on page 1601 of FY 1966 Annual 
Report. 
Terminal facilities. Two wharves and 4 pleasure craft 
handling facilities at Edmonds Harbor. One wharf is 
publicly owned and operated as a ferry terminal, the 
other, privately owned, is a gravel-unloading facility. 
There is also a Port-operated and-owned small-boat 
basin. These facilities, with exception of the small-boat 
basin, are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance, hired 
labor: Conducted channel condition surveys. 
Maintenance, contract: A contract was awarded in 
September for repair of the Federally-maintained south 
rubblestone breakwater, providing for approximately 
11,500 tons of armor rock with scheduled completion in 
November 1986. 
5. EVERETT HARBOR AND SNOHOMISH 
RIVER, WA 
Location. On Port Gardner Bay, at northern end of 
Possession Sound, an arm of Puget Sound at Everett, in 
northwestern Washington; and Snohomish River for 6.3 
miles above mouth. (See NOAA Survey Chart 18443.) 
Existing project. Training dike extending from a 
point opposite 23d Street northward 12,550 feet to outlet 
of Snohomish River, with spur dike extending 400 feet 
to pierhead line from north end of main dike; spur dike 
extending 1,410 feet westward from Preston Point; 
removal of a section of training dike north of Snohomish 
River outlet; channel 150 to 425 feet wide and 15 feet deep 
from deep water in Port Gardner Bay to 14th Street dock; 
thence a settling basin 700 feet wide, 1,200 feet long, and 
20 feet deep, thence a channel 150 feet wide and 8 feet 
deep upriver to head of Steamboat Slough, a total distance 
of about 6.3 miles; settling basin within upper channel 
reach about 1 mile long with a capacity of 1 million cubic 
yards and maintaining East Waterway to 30 feet deep. 
The 1968 modification included raising the southerly 
4,100 feet of existing training dike, extending the training 
dike 1,500 feet farther south, and constructing a 
breakwater along the south and west sides of the 
existing small boat basin. Plane of reference is mean 
lower low water. Range between mean lower low water 
and mean higher high water is 11.1 feet. Extreme tidal 
range is about 19 feet. The boat basin breakwater has 
been deleted at the request of the local sponsor, and the 
remainder of the 1968 modification has been deferred indefinitely. 
Project was completed in April 1963, excluding 
the deleted and deferred portions. (For further details, see 
page 1683 of Annual Report for 1963. For details relating 
to previous projects, see page 704 of Annual Report for 
1905, page 2005 of Annual Report for 1915, and page 1883 
of Annual Report for 1938.) 
Local cooperation. Fully complied with. Requirements 
are described in full on page 38-3 of FY 1981 
Annual Report. 
Terminal facilities. There are 42 piers and wharves 
in the Port of Everett, 17 in Port Gardner and 25 on the 
Snohomish River. These include: 19 publicly owned terminals 
with 4 berths handling ocean-going vessels and 
1 publicly owned terminal and small-boat basin handling 
fishing and pleasure craft. The rest are at Bayside and 
the Snohomish River. 
Operations during fiscal year. Maintenance, hired 
labor: Channel condition surveys were conducted 
throughout the year. Puget Sound Dredged Disposal 
Analysis study costs resulted in an expenditure of 
$155,600. 
Maintenance, contract: A dredging contract to maintain 
the Upper Snohomish River channel and settling 
basin was awarded in August 1986. Contract provides for 
dredging approximately 205,000 cubic yards and disposal 
at three upland sites. 
6. GRAYS HARBOR AND CHEHALIS RIVER, WA 
Location. Harbor lies at mouth of Chehalis River, in 
southwestern part of Washington, 45 miles north of entrance 
to Columbia River. Inner portion comprises two 
main channels, the south and the north, connecting harbor 
proper with Chehalis River at Aberdeen. Chehalis 
River rises in southwestern part of Washington about 40 
miles east of Pacific Ocean, flows generally northwesterly 
and empties into eastern part of Grays Harbor. (See 
NOAA Survey Chart 18502.) 
Existing project. Provides for an entrance channel 
across the bar 600 feet wide and 30 feet deep, to be secured 
by a south jetty 13,734 feet long and a north jetty 17,200 
feet long, both at an elevation of 16 feet, and by dredging; 
maintenance of channel 30 feet deep and 350 feet 
wide from deep water in Grays Harbor 14 miles to Cow 
Point; thence 30 feet deep and 200 feet wide, suitably 
widened at bends, to a point 13,700 feet upstream from 
Union Pacific Railroad bridge at Aberdeen, a distance of 
4.125 miles; a turning basin 30 feet deep, 550 feet wide, 
and 1,000 feet long at upstream end of 30-foot channel 
near Cosmopolis; a channel 14 feet deep and 100 feet wide 
in South Bay to Bay City; three breakwaters at, and 
maintenance of entrance channel to Westhaven Cove; and 
protection of Point Chehalis for an exposed length of about 
7,500 feet. Plane of reference is mean lower low water. 
Tidal range between mean lower low water and mean 
higher high water is 8.9 feet at Point Chehalis, 10.1 feet 
at Aberdeen, and 8.1 feet at Montesano. Extreme range 
38-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
is 17.5 feet at Point Chehalis, 17.8 feet at Aberdeen, and 
23.8 feet at Montesano (river flood of 1935). Project was 
completed in March 1965 excluding deferred and inactive 
portions. Rehabilitation of 4,000 feet of the south jetty 
was completed in October 1966. (For further details, see 
Annual Report for 1967. For details relating to previous 
projects, see pages 2002-03 of Annual Report for 1915 and 
page 1863 of Annual Report for 1938.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 23 waterfront facilities 
(piers, wharves, and docks), exclusive of those available 
to recreational craft, at Grays Harbor, of which five are 
publicly owned. In foreign and domestic trade they serve 
various purposes which include the receipt and/or shipment 
of: logs and lumber, woodchips, conventional and 
containerized general cargo, seafood and fishing supplies, 
sand and gravel, and construction materials. Other uses 
include: mooring and icing fishing boats, mooring small 
vessels for outfitting and repair, and mooring companyowned 
tugs. Those piers operated by the U.S. Coast Guard 
moor government-owned vessels. Refer to Port Series No. 
35, revised 1983. 
Operations during fiscal year. Maintenance, hired 
labor: Channel condition surveys were conducted 
throughout the year. The Corps hopper dredge Yaquina 
accomplished dredging in South Reach in October 1985, 
removing 67,625 cubic yards of material at a cost of 
$287,042. The Corps hopper dredge Essayons accomplished 
dredging in Crossover Channel in October and 
November 1985, removing 95,711 cubic yards of material 
at a cost of $237,120. 
Maintenance, contract: Maintenance dredging of the 
inner and outer harbors was completed in June 1986 at 
a cost of $2,704,716 with 1,752,624 cubic yards of material 
being removed. 
7. KENMORE NAVIGATION CHANNEL, WA 
Location. The Kenmore Navigation Channel lies at 
the northern end of Lake Washington adjacent to the 
Sammamish River. Kenmore, an unincorporated industrial 
and business center in King County just north 
of Seattle, WA, encompasses the lands to the north of the 
channel. (See NOAA Survey Chart 18447.) 
Existing project. The construction of a navigation 
channel to serve the Kenmore industrial area, King County, 
WA, involves a 15-foot-deep channel which would consist 
of a 100-foot-wide inner channel 900 feet long, an 800- 
foot-long transition channnel with a 24 � 30-foot bend and 
a maximum width of 190 feet, and a 120-foot-wide outer 
channel 1,200 feet long. The project also consists of the 
installation of a goose nesting area on property adjacent 
to the new channel as mitigation for the removal of goose 
nests during construction. Project was completed in 
March 1981. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance, hired 
labor: Performed maintenance on the Canadian goose nesting 
area (project migitation) in February 1986. A maintenance 
dredging contract was advertised with bid opening for dredging 
approximately 32,000 cubic yards. 
of shoal material in FY 87. Puget Sound Dredged Disposal 
Analysis study costs resulted in an expenditure of 
$30,000. 
8. LAKE WASHINGTON SHIP CANAL, WA 
Location. Entirely within city of Seattle and extends 
from Puget Sound through Shilshole Bay, Salmon Bay, 
Lake Union, Portage Bay, and Union Bay to deep water 
in Lake Washington. (See NOAA Survey Chart 18447.) 
Existing project. Provides for a double lock and fixed 
dam with gated spillway and necessary accessory works, 
including fishladder, at the Narrows at entrance to 
Salmon Bay, about 1.25 miles from deep water in Puget 
Sound; for a channel 34 feet deep and 300 feet wide from 
Puget Sound to Burlington Northern Railway bridge, 
about 5,500 feet, with a passing basin 34 feet deep and 
log basin 8 feet deep at turn below railway bridge; then 
34 feet deep and 150 feet to 200 feet wide to locks, about 
900 feet; and a guide pier 600 feet long; for revetment of 
canal banks between locks and Lake Union and between 
Lakes Union and Washington; and for a channel 30 feet 
deep with a width of 100 feet from locks to Lake Union, 
200 feet thence to Portage Cut, 100 feet through Portage 
Cut, and thence 200 feet wide through Union Bay to Lake 
Washington. Section included in project is about 10 miles 
long. Plane of reference is mean lower low water. Extreme 
tidal range is 19.3 feet. Range between mean lower low 
water and mean higher high water is 11.3 feet, and between 
mean lower low water and extreme low water is 
4.6 feet. Ordinary fluctuation in upper pool is about 22 
inches; extreme fluctuation has been 3.6 feet. Principal 
features of double lock and dam (structures are at 
Seattle, WA) are set forth in Table 38-H. Project was completed 
in 1934. (For further details, see Annual Report 
for 1935. For details relating to previous projects, see page 
2003 of Annual Report for 1915, and page 1880 of Annual 
Report for 1938.) 
Local cooperation. Fully complied with. 
Terminal facilities. The eight waterfront facilities at 
Lake Washington Ship Canal are used for fuel oil, seafood, 
marine repair, drydocking, outfitting, mooring fishing 
vessels and repairs to the locks' equipment. Project is a 
part of Seattle Harbor's inner harbor. Refer to Port Series 
No. 36, revised 1983. 
Operations during fiscal year. Maintenance, hired 
labor: Locks were operated and maintained all year, passing 
20,000 commercial and 65,000 pleasure vessels, and 
2,200,000 tons of commerce. Fishladder passed 500,000 
fish and there were more than 860,000 project visitors. 
Puget Sound Dredged Disposal Analysis study costs 
resulted in an expenditure of $30,000. 
Major Rehabilitation. New work: Contract for construction 
of a new Emergency Closure System and 
rehabilitation of the downstream guard gate continues 
and is scheduled for completion in May 1987. 
9. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645 (preauthorization). 
38-4

SEATTLE, WASHINGTON DISTRICT 
Fiscal year costs for preauthorization studies were: 
Gooseberry Point Small Boat Harbor, Hale Passage, WA, 
$17,297; Oak Harbor Marina, WA, $152,604; Sandy Point 
Harbor, Whatcom County, WA, -$164. 
Aquatic plant control (Section 302, Public Law 
89-298): 
The program consists of control measures for selected 
water bodies currently infested with Eurasian watermilfoil 
and measures to prevent its spread into uninfested 
waters. Operations under the cost-share program included 
mechanical harvesting of 91 acres, maintaining 5 acres 
of fiberglass bottom screens, and adding 0.43 acres of 
fiberglass bottom screen at Lake Washington, Lake 
Union and Lake Sammamish, WA; rototilling 10 acres 
of lake bottom to dislodge milfoil roots at Osoyoos Lake, 
WA; rototilling 5 acres of river bottom to dislodge milfoil 
roots in preparation for planting the beneficial aquatic 
plant, dwarf spikerush, at Pend Oreille River, WA. The 
FY 1986 work also included treatment effectiveness and 
carry-over studies, cooperation with the University of 
Washington on a Grass Carp study, aquatic plant surveys, 
and public information efforts. Total costs for fiscal year 
were $465,775. 
10. OLYMPIA HARBOR, WA. 
Location. Near southern end of Puget Sound at head 
of Budd Inlet, about 45 miles southwest of Tacoma. (See 
Coast and Geodetic Survey Chart 6462.) 
Existing project. Provides a channel between deep 
water in Budd Inlet and port terminal, 30 feet deep at 
mean lower low water and 500 feet wide, with suitable 
additional width at bend, and a turning basin adjacent 
to port terminal 30 feet deep, 3,350 feet long, and 500 to 
960 feet wide. Extreme tidal range is 22.5 feet. Range between 
mean lower low water and mean higher high water 
is 14.4 feet. Existing project was completed in 1939. Entrance 
channel and turning basin authorized by 1945 
River and Harbor Act have been deferred. (For details 
relating to previous projects, see page 1369 of Annual 
Report for 1934 and page 1873 of Annual Report of 1938.) 
Local cooperation. Modification authorized by River 
and Harbor Act of March 2, 1945, requires that local interests 
furnish suitably bulkheaded areas for retention 
of dredged materials, when and as required. The Port of 
Olympia advised on January 25, 1949, that it could not 
comply with requirements at that time, but would do so 
on earliest possible date. 
Terminal facilities. Five port facilities are located in 
Olympia at Budd Inlet, exclusive of the numerous waterfront 
facilities in the ports used by recreational craft. The 
industrial docks are used for conventional general cargo, 
logs, timber products and miscellaneous mooring. Refer 
to Port Series No. 35, revised 1983. 
Operations during fiscal year. Maintenance, hired 
labor: Puget Sound Dredged Disposal Analysis study costs 
resulted in an expenditure of $100,000. 
11. PROJECT CONDITION SURVEYS 
Preliminary and detailed surveys to determine navigation 
conditions at boat basins, small navigation projects, 
channels, and tributaries of major rivers not within major 
project boundaries. Soundings and visual inspections 
in subject areas are conducted in order to evaluate shoaling 
conditions. Channel centerline markers are inspected 
for visibility and proper operation in applicable areas frequented 
by boating traffic consisting mostly of recreationalists. 
In addition, all subject areas are inspected to 
insure that they are clean of snags and obstructions. Total 
costs for fiscal year were $283,237. 
12. PUGET SOUND AND ITS TRIBUTARY 
WATERS, WA 
Location. Puget Sound is in the western part of 
Washington. Cities of Seattle, Tacoma, Olympia, Everett, 
Bellingham, and many small towns are on its bays and 
inlets. (See NOAA Survey Charts 18400, 18441 and 
18448.) 
Existing project. Maintenance of Puget Sound and its 
tributary waters by snagging and dredging; and removal, 
in cooperation with city of Seattle, of floating debris from 
the Seattle Harbor area. Work consists of collecting large 
pieces of drift, waterlogged pilings, logs and other debris, 
considered hazardous to navigation from Puget Sound and 
Federally authorized channels. (For details relating to 
previous projects, see page 2003 of Annual Report for 1915 
and page 1869 of Annual Report for 1938.) 
Local cooperation. None required. City of Seattle is 
cooperating in a program for control of floating debris in 
Seattle Harbor. 
Terminal facilities. Terminal facilities at numerous 
localities on Puget Sound and its tributary waters are, 
in general, considered adequate for existing commerce. 
Operations during fiscal year. Maintenance, hired 
labor: The debris vessel Puget operated continuously 
throughout Puget Sound and its tributary waters. The 
patrol boat Walton removed floating debris in the greater 
Seattle vicinity. Together they removed approximately 
2,000 tons of floating debris and hazards to navigation. 
Debris was disposed of locally or loaded aboard barges and 
disposed of by contract. Snagging operations were accomplished 
at Blaine Harbor, Bellingham Harbor, 
Swinomish Channel, Skagit River, Everett Harbor, 
Snohomish River (upstream to town of Snohomish), Lake 
Washington Ship Canal, Lake Washington, Tacoma Harbor, 
Olympia Harbor, Duwamish River, and Elliott Bay. 
A brochure describing the PS&TW program and the 
debris vessel Puget was prepared and distributed during 
FY 1986. 
Maintenance, contract: 1,307 tons of harbor debris were 
disposed of at a cost of $33,086. Current contractor is 
recycling some of the debris and placing the remainder 
in a landfill. 
13. QUILLAYUTE RIVER, WA 
Location. River is formed by junction of Soleduck and 
Bogachiel Rivers, in northwestern Washington, and flows 
westerly 5 miles to Pacific Ocean at La Push, about 30 
miles south of Cape Flattery. (See NOAA Survey Chart 
18480.) 
38-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Existing project. Provides for: (a) Jetty 15 feet high 
on easterly side of river mouth, and a dike on westerly 
side, with a view of stabilizing entrance; (b) channel 10 
feet deep and 100 feet wide extending 2,000 feet upstream 
from deep water; (c) basin 10 feet deep, 300 to 425 feet 
wide, and 2,400 feet long upstream of channel; and (d) 
maintenance of an ocean spit. Plane of reference is mean 
lower low water. Range between mean lower low water 
and mean higher high water at La Push is 8.3 feet. Extreme 
range is about 15 feet. The spit was nourished in 
conjunction with channel dredging contracts completed 
in 1973 and in 1977. The spit was rehabilitated with 
quarry rock in 1974, in 1979-80, and in 1982. In addition, 
a 500-foot breakwater section paralleling the channel and 
extending the spit was constructed. Project was completed 
in February 1960; however, the channel upstream of the 
boat basin has been classified as inactive. (For further 
details, see Annual Report for 1963.) 
Local cooperation. Complied with except that the requirement 
to provide a public landing open to all on equal 
terms in the boat basin was not complied with between 
May and July 1981, due to the closure of the Quileute Indian 
Reservation to the landing of salmon by sport and 
charter fishermen. 
Terminal facilities. There are 6 privately-owned docks 
at La Push, near the mouth of the Quillayute River. In 
addition, there is a protected boat basin owned by the 
Quileute Tribe Port Authority which is used by fishing 
boats, pleasure craft, and the Coast Guard, which has a 
separate pier. 
Operations during fiscal year. Maintenance, hired 
labor: Condition surveys were made of the river channel 
during the year. 
14. SEATTLE HARBOR, WA 
Location. Harbor at Seattle, WA, includes all waterways 
within city limits. Chief anchorage basin is Elliott 
Bay, an arm of Puget Sound. (See NOAA Survey Chart 
18450.) 
Existing project. Maintenance of East and West 
Waterways, 34 feet deep and 750 feet wide for 6,500 and 
5,200 feet, respectively, from pierhead line in Elliott Bay; 
maintenance of East Waterway between upper end of 
750-foot section and Spokane Street, 34 feet deep, 700 feet 
long, and 400 feet wide, and a turning basin, including 
head of East Waterway at junction of waterways south 
of Chicago, Milwaukee, St. Paul & Pacific Railroad 
Bridge, to 30 feet deep, after these sections of waterway 
are dredged by local interests to full project dimensions; 
and dredging Duwamish Waterway 200 feet wide and 30 
feet deep between West Waterway and First Avenue 
South, 150 by 20 feet between First and Eighth Avenues 
South, thence 150 feet by 15 feet to a point about 1.4 miles 
above 14th Avenue South Bridge, with turning basin 600 
by 350 feet and 20 feet deep just south of First Avenue 
South Bridge, and turning basin 500 by 250 feet and 15 
feet deep, and settling basin of about 100,000 cubic yardscapacity 
at upper end of waterway, a distance of 5.12 
miles. Total length of waterways included in project is 
about 7.5 miles. Plane of reference is mean lower low 
water. Range between mean lower low water and mean 
higher high water is 11.3 feet. Extreme tidal range is 19.3 
feet. Project was completed in 1931, excluding the settling 
basin at upstream end which is classified inactive and 
East Waterway above the 750-foot section. (For further 
details, see Annual Report for 1932.) 
Local cooperation. Complied with, except for inactive 
portion of project. 
Terminal facilities. There are 196 piers, wharves, and 
docks located on the inner and outer harbors at Seattle, 
WA. Salmon Bay, Lake Union, Portage Bay and Lake 
Washington form the inner harbor; Elliott Bay and East, 
West and Duwamish Waterways form the outer harbor. 
(Lake Washington Ship Canal, a part of the inner harbor, 
is a separate project in this report.) These terminals 
serve a variety of purposes which include cargo handling, 
bunkering vessels, ferry service (vehicular, passenger and 
rail car), marine repair/outfitting/drydocking/conversion, 
shipbuilding, handling supplies and equipment, and 
mooring company-owned equipment, excursion vessels, 
fire boats, fishing vessels, government equipment, harbor 
craft/tugs, and oceanographic research vessels. The 
numerous waterfront facilities in the port used exclusively 
by recreational craft are not included. Refer to Port 
Series No. 36, revised 1983. 
Operations during fiscal year. Maintenance, hired 
labor: Condition surveys made of channels. Puget Sound 
Dredged Disposal Analysis study costs resulted in an expenditure 
of $300,800. 
Maintenance contract: In March 1986, 33,637 cubic 
yards of contaminated sediment were dredged from the 
Duwamish Waterway at a cost of $191,249. The material 
was deposited in a confined water disposal site provided 
by the Port of Seattle. The annual maintenance dredging 
of the Duwamish Waterway was completed in July 1986, 
with the removal of 103,598 cubic yards at a cost of 
$253,815. 
15. SWINOMISH CHANNEL, WA 
Location. An inland passage, 11 miles long, between 
Saratoga Passage and Padilla Bay, in northwestern part 
of Washington, about 60 miles north of Seattle. (See 
NOAA Survey Charts 18400, 18427 and 18421.) 
Existing project. A channel 100 feet wide and 12 feet 
deep for 11 miles from deep water in Saratoga Passage 
to deep water in Padilla Bay, by dredging and dike construction 
where necessary; and removal of protecting 
rocky points of McGlinn and Fidalgo Islands obstructing 
navigation at "Hole-in-the-Wall". Plane of reference is 
mean lower low water. Range between mean lower low 
water and mean higher high water is 11.5 feet at south 
end of channel, 8.4 feet at north end, and 10 feet at La 
Conner. Extreme tidal range is about 19.5 feet at south 
end of channel and about 16 feet at north end. Project was 
completed in March 1965. (For further details, see Annual 
Report for 1965.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 18 wharves, docks, and 
piers on Swinomish Channel, all but 3 of which are 
38-6

SEATTLE, WASHINGTON DISTRICT 
privately owned. Of these, 1 is used for handling general 
cargo, 5 are used exclusively for moorage, unloading, and 
servicing of fishing vessels; 2 are used for handling 
petroleum products; 3 facilities are used for log dumps; 
and 2 for handling non-metallic minerals. Three publicly 
owned facilities for launching, mooring, and servicing 
small craft are within the city limits of La Conner. 
Operations during fiscal year. Maintenance, hired 
labor: Condition surveys were made of various reaches 
of the channel. Puget Sound Dredged Disposal Analysis 
study costs resulted in an expenditure of $100,000. 
Maintenance, contract: A maintenance dredging contract 
for clamshell dredging with open-water disposal was 
awarded in September 1986, with work to commence in 
November 1986. 
16. TACOMA HARBOR, WA 
Location. Harbor includes Commencement Bay and 
tributary waterways at Tacoma, in northwestern 
Washington. (See NOAA Survey Chart 18453.) 
Existing project. Provides for: (a) Channel in City 
Waterway 500 feet wide and 29 feet deep from deep water 
in Commencement Bay to 11th Street Bridge, 500 feet 
wide and 22 feet deep to 14th Street Bridge, and varying 
from 500 to 250 feet wide and 19 feet deep from 14th 
Street Bridge to end of this waterway, a total length of 
8,500 feet; (b) channel in Hylebos Waterway 30 feet deep, 
3.1 miles long, and 200 feet wide except where width is 
increased to 250 feet at the bend below East 11th Street, 
to 300 feet at Lincoln Avenue bend, and to 510 feet and 
770 feet, respectively, at the channel widening above Lincoln 
Avenue and the turning basin at the head of the 
waterway; (c) construction of two training walls, each 
about 700 feet long at mouth of Puyallup River; and (d) 
channel in Blair Waterway 2.6 miles long, including a 
portion seaward of East 11th Street, 650 feet wide and 
30 feet deep over southerly 350 feet, and 35 feet deep over 
northerly 300 feet; and remaining portion, 35 feet deep 
and 150 feet wide at East 11th Street, 600 feet wide between 
East 11th Street and Lincoln Avenue, and 300 feet 
wide between Lincoln Avenue and a 1,200-foot wide turning 
basin at head of waterway. Plane of reference is mean 
lower low water. Range between mean lower low water 
and mean higher high water is 11.8 feet. Extreme tidal 
range is about 20 feet. Project was completed in December 
1966. (For further details, see Annual Report for 1967. 
For details relating to previous projects, see pages 1372 
to 1376 of Annual Report for 1934 and page 1875 of Annual 
Report for 1938 for Puyallup Waterway, and page 
1702 of Annual Report of 1944 and page 1502 of Annual 
Report for 1954 for Blair (formerly Wapato and Port Industrial) 
Waterway.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 81 terminal facilities, 
exclusive of those available to recreational craft, located 
in Tacoma Harbor which is comprised of Commencement 
Bay and its many waterways. These facilities serve a 
variety of purposes which includes cargo handling, fueling 
small vessels, ferry traffic, marine repair, conversion/ 
outfitting, dry-docking, mooring, bunkering, ship-building, 
and shipbreaking. Refer to Port Series No. 35, revised 
1983. 
Operations during fiscal year. Maintenance, hired 
labor: Condition surveys were conducted during the year. 
Puget Sound Dredged Disposal Analysis study costs 
resulted in an expenditure of $50,000. 
17. WATERWAY CONNECTING PORT 
TOWNSEND AND OAK BAY, WA 
Location. Canal connects two bays which are arms of 
Admiralty Inlet on west side of Puget Sound, in northwestern 
part of Washington, about 40 miles north of Seattle. 
(See U.S. Coast and Geodetic Survey Chart No. 6405.) 
Existing project. Provides for a canal 15 feet deep, 
75 feet wide on the bottom, and about 4,800 feet long, and 
for construction of jetties to protect channel at southern 
or Oak Bay end, and a bulkhead for retention of dredged 
material. Plane of reference is mean lower low water. 
Range between mean lower low water and mean higher 
high water is 8.3 feet in Port Townsend Bay and 9.4 feet 
in Oak Bay. Extreme tidal range is 16 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. None directly served by the canal. 
Operations during fiscal year. Maintenance, hired 
labor: Conducted channel condition surveys. 
18. WILLAPA RIVER AND HARBOR AND 
NASELLE RIVER, WA 
Location. Willapa Harbor consists of lower reaches of 
Willapa River and Bay, an inlet of Pacific Ocean about 
30 miles north of mouth of Columbia River in 
Washington. Willapa River rises about 30 miles east of 
harbor, flows generally westerly, and empties into the 
bay. Naselle River enters the bay near its southerly end. 
(See NOAA Survey Chart 18504.) 
Existing project. Provides for: (a) channel over bar 
at mouth of Willapa Bay, 26 feet deep and at least 500 
feet wide; (b) channel 24 feet deep and 200 feet wide from 
deep water in Willapa Bay to foot of Ferry Street at South 
Bend, thence 300 feet wide to westerly end of narrows, 
thence 250 feet wide to forks of river at Raymond, including 
a cutoff channel 3,100 feet long at narrows and 
a closing dike at Mailboat Slough; (c) channel 24 feet deep 
and 150 feet wide up south fork to deep basin above Cram 
lumber mill, and up north fork to 12th Street, with a turning 
basin 250 feet wide, 350 feet long, and 24 feet deep 
at latter point; (d) channel 10 feet deep and 40 feet wide 
from deep water in Palix River to Bay Center dock, with 
widening at shoreward end to provide a small mooring 
basin; (e) mooring basin 15 feet deep, 340 feet wide, and 
540 feet long adjacent to port wharf at Tokeland; (f) entrance 
channel at Nahcotta 10 feet deep and 200 feet wide, 
and mooring basin 10 feet deep, 500 feet wide, and 1,150 
feet long, protected by a rubblemound breakwater about 
1,500 feet long; and (g) removal of snags, piles, and other 
obstructions in navigable channel of Naselle River between 
Naselle and mouth. Project includes about 26 miles 
of channel from entrance through Willapa River forks, 
2,800 feet of Palix River-Bay Center channel, and 9 miles 
of Naselle River upstream of U.S. Highway 101 Bridge. 
38-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Plane of reference is mean lower low water. Tidal range 
between mean lower low water and mean higher high 
water is 8.9 feet at Toke Point, 9.9 feet at Raymond, 8.9 
feet at Bay Center, and 10.8 feet near Naselle. Extreme 
range is 18 feet at Toke Point, 19.3 feet at Raymond, 
16 feet at Bay Center, and 18 feet near Naselle. Project 
was completed in November 1958. (For further details, 
see Annual Report for 1959. For details relating to 
previous projects, see page 968 of Annual Report for 1910, 
page 2001 of Annual Report for 1915, and page 1861 of 
Annual Report for 1938.) 
Local cooperation. Fully complied with. The local 
sponsor has now obtained funding to dredge Tokeland 
Boat Basin moorage area which will permit maintenance 
dredging of the boat basin access channel. 
Terminal facilities. There are 24 wharves on Willapa 
River and Harbor, including 5 in Willapa Bay, 4 in Bay 
Center, 12 in Raymond and South Bend, and 1 in 
Tokeland. Two of the wharves at Raymond and South 
Bend are suitable for use by ocean-going vessels; one of 
these is publicly owned and operated as a general cargo 
terminal, and one is located at a sawmill. The other 
wharves, including 3 that are publicly owned and 
operated, are used by shallow-draft vessels. These 
facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance, hired 
labor: Condition surveys were made of various segments 
of the project. Conducted ocean disposal study. 
Beach Erosion 
19. BEACH EROSION WORK UNDER SPECIAL 
AUTHORIZATION 
Beach erosion control activities pursuant to Section 
103, Public Law 84-874 (preauthorization). 
Fiscal year costs for Lincoln Park Beach, Seattle, WA, 
were $24,422. 
Flood Control 
20. DUNGENESS RIVER, SEQUIM, WA 
Location. The project is located in Clallam County on 
the right bank of the Dungeness River, 4.5 miles 
southwest of Sequim, WA, in Carlsborg Lake Quadrangle 
SW1/4 sec. 1,T. 29 N., R. 4 W. 
Existing project. Protection of the access road (210 
feet), near the intake structure for the water system, consists 
of a riprap blanket 36 inches thick on a 1V to 2H 
slope and a 10-foot-wide, 4-foot-thick weighted riprap toe 
with gravel fill to reconstruct the required 1:2 embankment 
slope. A concrete block wall, back filled with quarry 
spalls, protects the waterline and access road (150 feet). 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. 
Operations during fiscal year. New work, hired 
labor: Project fiscally completed. Construction was 
physically complete in September 1985. 
21. HOWARD A. HANSON DAM, WA 
Location. Green River, in northwestern Washington, 
flows westerly for 40 miles to Auburn, thence northerly 
32 miles to its mouth in Elliott Bay at Seattle. Dam is 
at river mile 64, 6 miles southeast of Kanaskat, and 1 
mile downstream from mouth of North Fork. (See 
Geological Survey topographic sheet, "Cedar Lake 
quadrangle, Wash.") 
Existing project. Rockfill dam about 235 feet high, 
with gated spillway having a concrete weir at elevation 
1176 feet above mean sea level and top of gates at elevation 
1206, creating a reservoir with capacity of 106,000 
acre-feet. Dam along crest is about 675 feet long. Improvement 
is designed to control flooding in Green River Valley 
to alleviate agricultural and urban flood damage, and 
make possible further expansion of Seattle industrial 
area. It also supplements Tacoma water supply which was 
included as a betterment. Project was completed in June 
1963. (For further details, see Annual Report for 1963.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance, hired 
labor: Operation continued all year. Routine maintenance 
was accomplished on roads, gages, debris booms, turbidimeter, 
ditches, powerline, and other project features. 
The outlet works stilling basin was inspected. Work continued 
on water quality surveys, water storage studies, 
and channel capacity study. 
Maintenance, contract: Settlement of the fill for the 
relocated Burlington Northern Railway between stations 
10989 and 10991 was under continued surveillance. The 
deferred construction period has been extended to cover 
this area to observe effect of remedial work. (Improvements 
to the drainage system have apparently 
stabilized the railroad fill.) Contracts awarded during the 
fiscal year: generator set replacement in the amount of 
$38,500 and exploratory drilling in the amount of 
$84,600. 
22. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Inspections are made of Federally constructed local 
flood protection projects which are maintained by local 
interests; and agencies responsible for their operation and 
maintenance are advised of any needed repairs. During 
the fiscal year, inspections were made on Okanogan River 
at Omak and Oroville, Dungeness River at Sequim, Sammamish 
River, Shelton Creek, Stillaguamish River and 
Yakima River, all in Washington State; Coeur d'Alene, 
and St. Maries projects in Idaho. Streambank vegetation 
evaluations were made at Omak and Oroville and on the 
Green River in Washington. 51 Section 14 bank protection 
projects in WA, ID and MT were inspected in conjunction 
with flood control projects. Fiscal year costs were 
$76,297. Costs to date have been $673,111. 
23. INSPECTION OF COMPLETED PL-99 WORKS 
Inspections are made of levees that have been 
rehabilitated under Public Law 84-99. Inspections involve 
determining condition of levees, riprap displacement and 
vegetative control. Local sponsors are advised of results 
and recommendations. Inspections made this fiscal year 
were on the Olympic Peninsula, the Nooksack, Cedar- 
Green, Puyallup, Spokane, and Yakima Rivers in 
38-8

SEATTLE, WASHINGTON DISTRICT 
Washington State, the St. Joe, Coeur d'Alene, and Pend 
Oreille Rivers in Idaho, and the Clark Fork, Flathead, 
and Kootenai Rivers in Montana. Fiscal year costs were 
$42,666. Total costs to date have been $165,613. 
24. MIDDLE FORK NOOKSACK RIVER, DEMING, 
WA 
Location. The project is to protect Rutsatz Road, a 
Whatcom County roadway which is adjacent to the Middle 
Fork Nooksack River, 2 miles southeast of Deming, 
WA, in Deming Lake Quadrangle SW1/4 sec. 5, T. 38 N., 
R. 5 E. 
Existing Project. A 400-lineal-foot bank protection 
project consisting of riprap 42 inches thick on a 1V to 2H 
slope and a 12-foot-wide, 5-foot-thick weighted riprap toe. 
A minimum of 12 inches filter material is required between 
the natural bank and the riprap blanket. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. 
Operations during fiscal year. New work hired 
labor: Work includes initial appraisal, plans and specifications, 
and construction. Construction by equipment rental 
began on 21 May 1986 and was physically complete 
on 2 July 1986, at a cost of $79,000, Federal funds. 
25. MUD MOUNTAIN DAM, WA 
Location. On White River, principal tributary of 
Puyallup River, near Mud Mountain, 28 miles above its 
confluence with Puyallup River, and 38 miles above 
mouth of Puyallup River. Dam is 6 miles southeast of 
Enumclaw, in northwestern Washington, and 38 miles 
east of Tacoma. (See Geological Survey topographic sheet 
"Cedar Lake quadrangle, Washington.") 
Existing project. Rockfill dam, 700 feet long at crest 
elevation, rises 425 feet above bedrock. Reservoir has 
storage capacity of about 106,000 acre-feet. Outlet works 
are in right abutment and permit controlled discharge of 
17,700 cubic feet per second through two concrete-lined 
tunnels with uncontrolled discharge over spillway having 
maximum capacity of 139,000 cubic feet per second. 
Improvement affords flood protection to White and 
Puyallup River Valleys and protects Tacoma industrial 
district in conjunction with Puyallup River project at 
Tacoma against floods about 50 percent greater than maximum 
discharge of record. Project was completed in June 
1953, except for recreational facilities. (For further 
details, see Annual Report for 1953.) To date the Corps 
has constructed two vistas, a picnic area, and playground 
adjacent to the project office, a reservoir access point for 
hunters and fishermen, and a 1,760-foot trail leading to 
the lower vista area. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance, hired 
labor: Project features were operated all year. 
Maintenance was accomplished on dam facilities, intake 
structure, gages, debris booms, power lines, roads, ditches, 
and fish facilities. Approximately 1,000 fish are 
transported annually from the fish collection facility. 
Engineering work continued on investigation and evaluation 
of a seepage problem in dam core. 
Dam Safety Assurance. New work, hired labor: Completed 
General Design Memorandum in July 1986. 
Prepared plans and specifications and awarded contract 
for construction of resident engineer's facility. 
New work, contract: Contract for resident engineer's 
facility was awarded in July 1986 in the amount of 
$311,000 and 60% complete. Contract for exploratory 
drilling in the amount of $159,169 was awarded and completed 
during the FY. Total expenditures were 
$1,326,358. A Feature Design Memorandum for correcting 
earthquake and debris blockage deficiences in the 
intake tower will be prepared in FY 1987. 
26. PLACER CREEK, ID 
Location. Placer Creek rises in the St. Joe Mountains 
of northern Idaho, flows northerly about 7.8 miles, and 
discharges into the South Fork of Coeur d'Alene River 
at the city of Wallace. 
Existing project. Provides for flood control by construction 
of a 3,700-foot-long concrete channel to confine 
Placer Creek flows through Wallace. A debris basin 
capable of storing 17,000 cubic yards of debris is located 
upstream from the channel to prevent plugging of the 
channel. Project was physically complete in September 
1983. 
Local cooperation. Fully complied with. Requirements 
are described in full on page 38-10 of Fiscal 
Year 1981 Annual Report. 
Operations during fiscal year. New work, contract: 
A flood warning system contract was completed. 
27. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Flood control storage space was available in Hungry 
Horse Reservoir, MT, Flathead Lake, MT (controlled by 
Kerr Dam), Grand Coulee Project, WA, Upper Baker and 
Ross Reservoirs, WA. Guidance forecasts were made during 
the flood control season, as required. No Lost Valley 
storage replacement was requested at Rocky Reach, Priest 
Rapids, and Wells Dams. Daily and/or hourly data were 
collected and tabulated as required to check compliance 
with operating criteria. Coordination necessary in 
preparation or revision of reservoir regulation manuals 
was carried on during the year with agencies responsible 
for the operation of these projects. Fiscal year costs were 
$180,960. 
28. STILLAGUAMISH RIVER, WA 
Location. Formed by confluence of its north and south 
forks at Arlington, in northwestern Washington, 
Stillaguamish River flows westerly 22 miles to Puget 
Sound, entering Port Susan through Hat Slough and 
South Pass, and Skagit Bay through West Pass. (See 
NOAA Survey Chart 18441, and Geological Survey 
quadrangles Stanwood, Marysville, and Stillaguamish, 
WA.) 
Existing project. Works to reduce bank erosion and 
channel changes on Stillaguamish River 15 miles between 
Arlington and head of Hat Slough, and on Cook 
Slough, 3 miles long, as follows: Revetment at 26 places 
38-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
on river and Cook Slough; concrete weir 275 feet long between 
steel-sheet-pile piers at head of Cook Slough to 
limit flow through slough; and two cutoff channels, each 
about 900 feet long, to eliminate sharp bends in Cook 
Slough. Tidal influence extends about 3 miles into improved 
section. Flood stages of 16 feet above low water 
at Cook Slough weir have been observed. Project was completed 
in July 1939. (For further details, see Annual 
Report for 1940.) 
Local cooperation. None required. 
Operations during fiscal year. Maintenance, hired 
labor: Utilized in-house labor and equipment to remove 
brush on 9,000 linear feet of 4 segments. Repaired 3 
segments with gravel and riprap. 
29. TACOMA, PUYALLUP RIVER, WA 
Location. Puyallup River has its source in glaciers on 
western slopes of Mount Rainier, WA, flows northwesterly 
50 miles, and empties into Commencement Bay, an arm 
of Puget Sound, at Tacoma. Work covered by this project 
is on Puyallup River, within city limits of Tacoma. (See 
NOAA Survey Chart 18453.) 
Existing project. A channel with a capacity of 50,000 
cubic feet per second between East 11th Street Bridge and 
lower end of inter-county improvement, a distance of 
about 2.2 miles, by straightening channel, building 
levees, revetting channel and levees, and making 
necessary bridge changes. The 11th Street Bridge at lower 
end of project is 0.75 mile above mouth of Puyallup River. 
Diurnal tidal range at mouth of river is 11.8 feet and extreme 
range is 20 feet. Improvement was planned in conjunction 
with Mud Mountain Dam and affords protection 
against floods about 50 percent greater than maximum 
discharge of record. A real estate design memorandum, 
approved by Office of the Chief of Engineers on October 
2, 1985, changed the project boundary to allow the Port 
of Tacoma to create a wetland adjacent to the project. This 
action resulted in the Corps acquiring approximately 
2,450 lineal feet of setback levee in fee simple. 
Maintenance funds to cover the increased length of the 
project will be provided by the Port of Tacoma for the project 
life. Project was completed in May 1950. (For further 
details, see Annual Report for 1950.) 
Local cooperation. None required. 
Operations during fiscal year. Maintenance, hired 
labor: Utilized in-house labor and equipment to remove 
brush and trees on approximately 20,000 lineal feet. Rental 
equipment was used to redress and crown the levee 
road on the left bank. 
30. WYNOOCHEE LAKE, WA 
Location. On Wynoochee River, a tributary of 
Chehalis River, about 28 miles north of Montesano, Grays 
Harbor County, WA. (See Geological Survey quadrangles, 
Grisdale, Wynoochee Valley, and Montesano.) 
Existing project. Provides for a concrete and earthfill 
dam, 177 feet high, and reservoir of 70,000 acre-feet of 
total storage for water supply, flood control, irrigation, 
and fish and wildlife. Upstream fish facilities were operational 
in the fall of 1970. The project was completed and 
became operational in December 1972. Installation of 
power-generating facilities was not authorized, pending 
a reexamination report by the Chief of Engineers. In 
February 1966, the Federal Power Commission asserted 
that power production as part of the Wynoochee project 
was not feasible at that time. (For further details, see Annual 
Report for 1972.) 
Local cooperation. Fully complied with. Requirements 
are described in full on page 38-12 of FY 1981 
Annual Report. 
Operations during fiscal year. Maintenance, hired 
labor: Project facilities were operated all year. Maintenance 
was accomplished on dam and fish facilities, roads, ditches, 
culverts, and visitors' facilities. The project tank truck hauled 
upstream migrant fish past the dam. 
Maintenance, contract: Contract for spillway gate repainting 
in the amount of $96,188 is 99% complete. 
Multiple-Purpose Projects, 
Including Power 
31. ALBENI FALLS DAM, ID 
Location. Dam is on Pend Oreille River about 25 miles 
west of Sandpoint, in northern Idaho, and 50 miles northeast 
of Spokane, WA. Dam is 838 and 90 miles upstream 
from mouths of Columbia and Pend Oreille Rivers, respectively. 
(See Geological Survey topographic sheets, Sandpoint, 
ID, and Newport, WA.) 
Existing project. Provides flood control, hydroelectric 
power, and related water uses on Pend Oreille River as a 
part of the multiple-purpose plan for development of 
Columbia River Basin, including recreation development. 
At the dam, channel was formerly divided by an island and 
a low waterfall of about 7 feet. Dam is a gated, gravitystructure 
spillway in left channel and a powerhouse having 
an installation of 42,600 kilowatts in right channel, creating 
a reservoir with a usable storage capacity of 1,153,000 acrefeet. 
Project was completed in June 1957. (For further details, 
see Annual Report for 1957.) Recreational facilities for public 
use have been provided at Albeni Cove, Priest River, Riley 
Creek, Johnson Creek, Trestle Creek, Strongs Island, and 
Springy Point. (Strongs Island was closed in FY 1982 to 
reduce O&M costs.) (Refer to Albeni Falls Master Plan dated 
June 1981 for further planned development.) 
Local cooperation. None required. 
Operations during fiscal year. Maintenance, hired 
labor: Reservoir was operated through its annual cycle of 
storage and release. Routine structural, mechanical, and 
electrical maintenance was performed on spillway, dam, 
powerhouse, and equipment. 
Maintenance, contract: A $50,000 debris facility 
rehabilitation contract was awarded in September 1986 to 
repair damage from a June 1986 storm. The shop-storage 
building contract was completed. Work continued on the station 
service circuit breaker contract and boundary 
monumentation. 
32. CHIEF JOSEPH DAM, RUFUS WOODS 
LAKE, WA 
Location. On Columbia River in north central 
Washington, at river mile 545, just upstream from mouth 
38-10

SEATTLE, WASHINGTON DISTRICT 
of Foster Creek, 1.5 miles upstream from Town of 
Bridgeport. (Geological Survey topographic sheet 
Okanogan, WA, shows general locality.) 
Existing project. A concrete gravity structure which 
consists of a 19-gate spillway and a 27-unit powerhouse. 
The powerhouse has sixteen 64,000 kilowatt and eleven 
95,000 kilowatt generators with nameplate capacity of 
2,069,000 kilowatts. Pool raising to elevation 956 was 
completed in 1981 which increased the powerplant 
capability to 2,482,000 kilowatts. Project providing initial 
16 power units was completed in FY 1961. (For further 
details, see Annual Report for 1962.) Generator units 17 
through 27 are producing power; however, additional 
work will be required to bring turbine efficiency up to 
design standards. Construction of structural modifications 
to dam and powerhouse, installation of additional units, 
uprating and plant modernization of units 1-16, and other 
miscellaneous project work is approximately 93 percent 
complete. Estimated cost of current construction project 
is $387,000,000. 
Local cooperation. None required. 
Operations during fiscal year. New work, hired 
labor: Continued real estate acquisition. 
New work, contract: Contracts were awarded for 
Bridgeport State Park, Phase II, and relocation of public 
access in powerhouse. 
Contracts continuing through the fiscal year included 
generator stator rewind, installation and fire protection, 
transformers, governor system, station service system, 15 
kV circuit breakers, turbine cavitation, main unit excitation 
system, powerhouse shops, mobile sealing inspection 
unit, and wildlife mitigation: mule deer study and mitigation 
evaluation. Contracts completed during the fiscal 
year included warehouse addition and sandblast building 
($1,154,400), O&M maintenance building and dock 
($252,530), and spillway gate deficiencies ($3,635,825). 
Maintenance, hired labor: Project was operated all 
year, and routine maintenance work was performed. 
Maintenance, contract: Contracts awarded during the 
fiscal year included: stator laminations in the amount of 
$76,230, and miscellaneous replacement parts orders. 
33. LIBBY DAM-LAKE KOOCANUSA, MT 
Location. On Kootenai River in Lincoln County, MT, 
about 17 miles upstream from Libby, and 219 miles 
upstream from confluence of Kootenai with Columbia 
River. (See Geological Survey topographic sheet, Thompson 
Lakes, MT.) 
Existing project. Provides storage for local flood control 
protection in Montana and Idaho, and main stem 
flood control in Lower Columbia River, hydroelectric 
power generation at-site and at downstream plants 
through storage release. Project will be operated as a unit 
of comprehensive system for improvement of Columbia 
River Basin for flood control, navigation, hydroelectric 
power, and other purposes. 
Local cooperation. Fully complied with. 
Libby Dam-Lake Koocanusa Project. Dam is a 
straight concrete gravity overflow type, 420 feet high, 
3,055 feet long, with normal full pool at elevation 2459 
feet above mean sea level. Powerhouse has an initial 
installed capacity of 420,000 kilowatts from four 
hydroelectric generating units with provision for four additional 
units, one of which is currently under construction. 
Lake Koocanusa is 90 miles long, backing water 42 
miles into Canada and has a usable storage capacity of 
4,965,000 acre-feet at 50 percent drawdown. Construction 
of dam was in accordance with treaty between United 
States and Canada relating to international cooperation 
in water-resource development of the Columbia River 
Basin. Construction is complete. 
Operations during fiscal year. New work, contract: 
Payment for damage claims was made in the amount of 
$64,000 for Libby downstream effects in Kootenai Flats, ID. 
Maintenance, hired labor: Reservoir was operated 
through its annual cycle of storage and release. Routine 
structural, mechanical, and electrical maintenance was 
performed on spillway, dam powerhouse, and equipment. 
Maintenance, contract: Contract in the amount of 
$23,942 was awarded to fabricate a lifting beam for the 
dam gantry crane. Contract in the amount of $24,180 was 
awarded for the treaty tower floor repair. 
Libby Additional Units Project. Provides for installation 
of 4 additional units at the Libby Dam 
Powerhouse. Fabrication of generators for units 5 through 
8 is complete; however, only the unit 5 generator was installed. 
Installation of the electrical equipment is limited 
to unit 5. Parts for units 6 through 8 have been stored 
at the site. Project is 99% complete. Units 6 through 8 
have been reclassified inactive. 
Operations during fiscal year. New work, contract: 
Contracts for turbines and generators continued. 
Libby Reregulating Dam Project. Provides for construction 
of a reregulating dam about 10 miles downstream 
of Libby Dam and associated relocation of about 9 miles of 
Burlington Northern Railroad, 7.5 miles of St. Regis log haul 
road, 0.5 mile of Forest Development Road, and 7.5 miles 
of Montana State Highway. Funds were provided for a construction 
start in 1977; however, courts have found that Congress 
did not authorize construction of the reregulating dam. 
Operations during fiscal year. In FY 82, all work was 
terminated due to court direction. 
Libby Reregulating Dam - Power Units Project. Provides 
for installation of three hydroelectric generating units 
at the reregulating dam with 78,900 kilowatt installed 
capacity. A General Design Memorandum 1, Phase II, 
Preliminary Design Report was approved by the Office, Chief 
of Engineers on March 3, 1981. 
General Investigations 
34. SURVEYS 
Fiscal year costs were $203,635 for navigation studies, 
$166,936 for flood damage prevention studies, $349,809 for 
comprehensive studies, $4,538 for review of authorized projects, 
$66,731 for miscellaneous activities and $36,590 for 
coordination with other agencies and non-Federal interests, 
a total of $828,239. 
38-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
35. COLLECTION AND STUDY OF BASIC DATA 
The work programmed for collection and study of basic 
data covers international water studies, flood plain 
management services, and hydrologic studies. Work on 
international water studies included checking Kootenay 
Lake storage computations to determine compliance of 
West Kootenay Power & Light Co. with orders of International 
Joint Commission, and coordination with International 
Kootenay Lake and Osoyoos Lake Board of Control 
in enforcement of International Joint Commission 
orders. Technical assistance was provided other Federal 
and non-Federal agencies in flood hazard evaluation and 
related services as requested. Fiscal year costs were 
$2,945 for international water studies, $108,942 for flood 
plain management services, and $4,260 for hydrologic 
studies, a total of $116,147. 
36. CONTINUATION OF PLANNING AND 
ENGINEERING 
Blair and Sitcum Waterways, Tacoma Harbor, WA 
Tacoma Harbor, Pierce County, is located in southern 
Puget Sound at Tacoma, WA, about 30 miles south of 
Seattle. 
The proposed plan of improvement provides for (a) 
modification of the existing Federal project for Blair 
Waterway to provide for the construction and 
maintenance of a 45-foot and a 41-foot channel including 
replacement of the East 11th Street Bridge and (b) Federal 
maintenance of the locally constructed Sitcum Waterway 
to depths of 40 and 35 feet. 
Accomplishments during the fiscal year included environmental 
coordination on contaminated sediments and 
contracting with the Washington State Department of 
Transportation for bridge replacement evaluations. 
Estimated preconstruction planning cost is $2,640,000. 
Fiscal year costs were $194,893. Total costs to date have 
been $855,481, including $300,000 appropriated and expended 
under Section 101(c). 
Chehalis River at South Aberdeen and Cosmopolis, 
WA
The cities of Aberdeen and Cosmopolis are located at 
the mouth of the Chehalis River in Grays Harbor County, 
west central Washington. The Chehalis River, about 
125 miles in length, rises in the Willapa Hills in west central 
Washington. 
The proposed plan of improvement would protect most 
of the left bank flood plain at the mouth of the Chehalis 
River in the cities of Aberdeen and Cosmopolis. The improvement 
would include: an earthen levee 22,500 feet 
long roughly following the left bank of the Chehalis River 
from Devonshire Slough to Cosmopolis; 2,200 feet of concrete 
floodwall in two industrial areas; five pumping stations 
and tide gates; and 10 smaller gravity drain culverts 
with flap gates. The levee would protect 1,318 acres of 
the cities from inundation by the standard project flood. 
Accomplishments during the fiscal year included 
hydrologic, hydraulic, and economic studies, preparation 
of preliminary design and cost estimates, and Fish and 
Wildlife coordination. 
Estimated preconstruction planning cost is $1,097,000. 
Fiscal year costs were $276,930. Total costs to date have 
been $760,764. 
East, West and Duwamish Waterways, Seattle 
Harbor, WA 
Seattle Harbor, WA, an authorized project, includes 
East, West and Duwamish Waterways within its city 
limits. Chief anchorage basin is Elliott Bay, an arm of 
Puget Sound. 
The proposed plan of improvement includes: Deepening 
and narrowing East and West Waterways (from 34 
x 750 feet to 39 x 500 feet); deepening and widening 
Duwamish Waterway (from 34 x 200 feet to 39 x 250 feet); 
replacement of the constrictive Burlington Northern 
Railroad Bridge with one having 250 feet horizontal 
clearance; deepening one turning basin to 39 feet; 
deauthorizing an unneeded turning basin; mitigation for 
loss of 4 acres shallow-water and 27 acres deep-water fish 
habitat; creation of 2 acres of shallow-water habitat for 
fish enhancement; and construction of a public boat ramp 
for recreation access. 
Continuation of planning and engineering studies were 
initiated in October 1984. During the fiscal year the 
testing for contamination of sediments to be dredged was 
completed and environmental studies and Fish and 
Wildlife coordination continued. At the request of the 
local sponsor, further studies at this time are deferred. 
Estimated preconstruction planning cost is $2,910,000. 
Fiscal year costs were $292,320. Total costs to date have 
been $653,737. 
Grays Harbor, Chehalis and Hoquiam Rivers, WA 
Grays Harbor is a large tidal estuary in southwestern 
Washington. The entrance is 45 miles north of the mouth 
of the Columbia River and 110 miles south of the Strait 
of Juan de Fuca. The estuary lies entirely within Grays 
Harbor County, State of Washington. 
The proposed plan of improvement consists of modifying 
the existing Federal project for Grays Harbor. The 
existing 30-foot channel would be deepened to a depth of 
46 feet through the Outer Bar and widened in this reach 
from the existing 600 feet to a 1,000-foot-wide channel; 
thence, the entrance reach would be widened and deepened 
from the existing designated 350 feet wide by 30 feet 
deep channel to a channel tapering landward from 1,000 
to 600 feet wide and 46 to 38 feet deep; thence, the existing 
channel to Cow Point would be widened and 
deepened from 350 feet wide and 30 feet deep to 400 feet 
wide by 38 feet deep for the South reach and Crossover 
reach and to 350 feet wide by 38 feet deep for the Moon 
Island, Hoquiam, and Cow Point reaches; and thence, the 
Aberdeen and South Aberdeen reaches would be widened 
and deepened from the existing designated 200 feet wide 
by 30 feet deep channels to channels 250 feet wide by 36 
feet deep. Two turning basins located at Aberdeen would 
be constructed and the existing railroad bridge would be 
replaced with a new bridge having horizontal clearance 
of 250 feet. 
During the fiscal year major progress was made on environmental 
and engineering studies leading to a General 
38-12

SEATTLE, WASHINGTON DISTRICT 
Design Memorandum (GDM). Based on preliminary 
results, it appears some project dimensions can be reduced 
without affecting the project benefits. The final project 
design will be presented in the GDM which is scheduled 
for completion in September 1987. 
Estimated preconstruction planning cost is $3,860,000. 
Fiscal year costs were $1,100,604. Total costs to date have 
been $2,964,762. 
Yakima River at Union Gap, WA 
The flood plain under study is located between the confluence 
of the Yakima and Naches Rivers and the community 
of Union Gap, within Yakima County, in 
southeastern Washington State. 
The proposed plan of improvement consists of: Constructing 
two levees downstream of the Moxee Bridge on 
the Yakima River (1.1 miles of levee on the west bank 
and 2.5 miles on the east bank); improving sections of existing 
7 miles of levee by raising and providing additional 
riprap; installation of drainage control gates on existing 
culverts and flood plain management for unprotected 
areas. 
Continuation of Planning and Engineering studies 
were initiated in October 1984. During the fiscal year 
detailed hydraulic and economic analyses were completed. 
These analyses showed that the project is not economically 
feasible. Study was deferred. 
Estimated preconstruction planning cost is $566,000. 
Fiscal year costs were $279,388. Total costs to date have 
been $496,368. No work is scheduled for FY 87. 
38-13

TABLE 38-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1984 
1. Anacortes Harbor, 
WA (Federal Funds) 
(Contrib. Funds) 
Bellingham Harbor 
WA (Federal Funds) 
(Contrib. Funds) 
Ediz Hook, WA 
(Federal Funds) 
(Contrib. Funds) 
Edmonds Harbor, WA6 
Everett Harbor and 
Snohomish River, 
WA (Federal Funds) 
(Contrib. Funds) 
Grays Harbor and 
Chehalis River, WA 
(Federal Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
279 
3,025 
3,270 
15,000 
11,813 
- 222,345 
- 222,3451 
185,000 729,239 
175,612 719,851 
- 59,523 
- 59,523 
- 5,000 
- 5,000 
- 1,566,840 
- 1,566,8402 
- 1,064,067 
3,147 1,064,0273 
29,421 
29,4214 
9,103 
9,103 
15,000 
8,925 
855 
2,165 
- 1,860 
- 1,860 
80,000 950,000 
81,492 947,282 
- 122,375 
1 111,793 
- 160,000 
- 5,878,740 
- 5,878,7405 
-3,140 1,124,860 
6,679 1,123,360 
12,652 
20,000 
28,836 
396,000 
396,000 
130,585 
129,895 
180,000 
28,836 
- - - - 1,775,744 
- - - - 1,775,7447 
363,617 792,000 155,000 291,000 7,062,079 
363,615 689,169 253,987 294,189 7,061,4238 
- - - - 116,618 
- - - - 116,618 
- - - - 584,090 
- - - - 584,090 
35,000 
35,010 
3,289,000 
3,289,402 
- -9,635 
4,347,000 4,252,725 
4,339,277 4,243,299 
-9,600 5,155,796 
36 5,155,7969 
3,927,140 78,237,329 
3,944,749 78,234,51910 
38-14 
2. 
3. 
4. 
6.

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
(Contrib. Funds) 
Kenmore Navigation 
Channel, WA 
Lake Washington 
Ship Canal, WA 
10. Olympia Harbor, 
WA 
12. Puget Sound and its 
Tributary Waters, 
WA 
13. Quillayute River, 
WA 
(Federal Funds) 
(Contrib. Funds) 
14. Seattle Harbor, WA 
(Federal Funds) 
Minor 
Rehab. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- 120,592 
- 120,592 
- 4,606,145 
- 4,606,145 
- 35,834 
- 35,834 
- 47,889 
-- 47,889 
134,000 
112,775 
946,000 
946,00011 
134,000 
112,775 
- - - - 4,803,952 
- - - - 4,803,95212 
2,851,000 2,999,240 3,595,440 3,755,000 61,123,910 
2,856,510 2,936,228 3,560,062 3,778,291 61,018,78013 
2,275,000 2,970,000 1,120,230 
2,275,220 2,951,805 994,066 
- 7,465,230 
133,987 7,454,857 
100,000 
100,000 
359,315 
359,31514 
625,377 
625,37715 
- - - - 43,337 
- - - - 43,337 
600,000 593,000 542,500 617,000 16,414,802 
601,269 552,674 575,607 612,490 16,403,07316 
-310,000 454,000 536,261 
501,062 452,875 530,793 
- 521,850 
- 521,85017 
17,000 9,136,022 
19,410 9,130,338 
- - - - 20,000 
- - - - 20,000 
- - - - 170,335 
- - - - 170,335 
428,358 405,000 274,000 1,001,000 7,192,746 
428,995 398,225 273,308 940,157 7,124,434 
38-15 
7. 
8.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 38-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
(Contrib. Funds) 
15. Swinomish Channel, 
WA 
(Federal Funds) 
(Contrib. Funds) 
16. Tacoma Harbor, WA 
(Federal Funds) 
(Contrib. Funds) 
17. Waterway 
Connecting Port 
Townsend and Oak 
Bay, WA 
18. Willapa River and 
Harbor and Naselle 
River, WA 
(Federal Funds) 
(Contrib. Funds) 
20. Dungeness River, 
WA 
21. Howard A. Hanson 
Dam, WA 
(Federal Funds) 
(Contrib. Funds) 
24. . Middle Fork 
Nooksack River, WA 
25. Mud Mountain 
Dam, WA 
(Federal Funds) 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
69,333 
69,333 
20,000 
20,000 
70,000 347,760 
65,360 352,506 
- - 808,332 
- - 808,33218 
20,000 353,000 5,867,940 
19,797 149,813 5,664,323 
32,000 
32,000 
20,000 
21,289 
- 2,383,891 
- 2,383,89119 
50,000 1,364,745 
50,000 1,364,74520 
- 1,144,416 
- 1,144,416 
- 222,500 
- 222,500 
- 73,322 
- 73,322 
- 90,000 
- 89,712 
60,000 578,000 
59,914 573,690 
16,500 
16,169 
84,000 
80,542 
66,500 
43,934 
619 
326,378 
326,378 
- 1,579,269 
- 1,579,2692' 
- 13,240,978 
4,953 13,238,07722 
- 98,372 
- 98,372 
-19,000 47,500 
3,566 47,500 
- 37,048,061 
- 37,048,061 
528,000 515,000 693,049 727,000 9,558,300 
527,245 496,871 681,307 616,769 9,417,160 
- - - - 2,000,000 
- - - - 2,000,000 
- - - 79,000 79,000 
- - - 79,000 79,000 
- - - 1,439,000 14,734,848 
- - - 1,326,358 14,622,20623 
38-16

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
(Contrib. Funds) 
26. Placer Creek, ID 
28. Stillaguamish 
River, WA 
(Federal Funds) 
(Contrib. Funds) 
29. Tacoma, Puyallup 
River, WA 
30. Wynoochee Lake, 
WA 
31. Albeni Falls Dam, 
ID 
32. Chief Joseph Dam- 
Rufus Woods Lake, 
WA 
33. Libby Dam, Lake 
Koocanusa, MT 
(Federal Funds) 
(Contrib. Funds) 
Maint. 
Approp. 
Cost 
Minor 
Rehab. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
1,136,162 1,138,000 2,967,944 1,230,000 18,190,476 
1,110,512 1,118,723 2,937,358 1,272,504 18,145,76924 
- - - - 285,908 
- - - - 285,908 
845,000 390,000 
722,954 497,172 20,329 
- 3,928 
- 3,928 
- 5,865,000 
1,699 5,865,000 
- - - - 220,594 
- - - - 220,59425 
150,000 155,000 100,000 110,000 1,574,845 
142,972 162,671 100,163 110,406 1,574,824 
S- - - 21,000 
- - - - 21,000 
- - - - 3,947,853 
- - - - 3,947,85326 
40,000 
39,947 
40,000 
39,829 
50,000 
48,911 
40,000 
40,851 
496,597 
496,134 
- - - - 23,494,445 
- - - - 23,494,44527 
908,000 994,500 1,047,877 1,032,000 10,909,446 
934,637 963,671 1,027,462 1,020,809 10,844,844 
- - - - 31,878,297 
- - - - 31,878,29728 
1,923,231 2,018,000 2,580,000 2,974,000 28,473,831 
1,843,759 2,062,473 2,555,530 2,971,854 28,368,60929 
11,900,000 18,200,000 13,990,000 11,023,000 506,091,235 
12,088,050 18,292,811 14,012,821 10,091,596 505,110,41630 
5,198,000 5,890,000 5,968,576 6,608,000 72,870,511 
5,194,095 5,811,108 5,966,340 6,525,685 72,667,89831 
- - - - 297,630 
- - - - 297,630 
6,250,000 1,915,000 830,000 630,000 543,726,14032 
6,365,210 1,844,303 853,369 715,232 543,705,99633 
2,590,900 2,860,500 2,877,000 3,653,000 25,460,479 
2,583,965 2,824,490 2,852,195 3,654,719 25,362,23234 
- - - - 1,458,252 
- - - - 1,458,252 
38-17

TABLE 38-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COST AND FINANCIAL STATEMENT 
1Excludes $2,000 Coast Guard funds expended. 
2Includes $56,582 appropriated and expended for previous 
project. 
3Includes $1,092 appropriated and expended for previous 
project. 
4Excludes $13,000 Coast Guard funds expended and 
$2,159,633 expended by Port of Bellingham in fulfilling requirements 
of local cooperation. 
5Includes $1,157,570 preauthorization cost. 
6Constructed by local interests. Corps of Engineers is 
responsible for maintenance. 
7Includes $418,209 appropriated and expended for previous 
projects. Excludes $43,000 Coast Guard funds expended. 
8Includes $5,869 appropriated and expended for previous 
projects . 
9Includes $124,945 appropriated and expended for recreation 
facilities at completed project (Code 710), and $113,134 appropriated 
and expended for previous projects. 
Excludes $162,000 Navy funds and $6,000 Coast Guard funds 
expended. 
1"Includes $37,415 appropriated and expended for previous 
projects. Excludes $798,135 Emergency Relief Funds and 
$57,000 Public Works Administration funds expended. 
"Includes $148,765 preauthorization cost, appropriated and 
expended. 
'2Includes $779,655 for recreation facilities at completed 
project (Code 710), and $485,002 for previous projects, appropriated 
and expended. Excludes $246,567 expended by State 
of Washington and $742,071 expended by King County. Excludes 
$192,516 Public Works Administration funds expended. 
'3Includes $1,631,195 (1916 to 1936) and $338,163 subsequently 
appropriated and expended under Maintenance and 
Operation of Dams and Other Improvements of Navigable 
Waters. 
'4Includes $183,257 for previous projects, and $18,000 expended 
for restudy Fiscal Years 1968-1973. Excludes $105,467 
Public Works Administration Funds expended. 
15Includes $14,418 expended for previous projects. 
"Includes $67,496 appropriated and expended for previous 
project. 
17Excludes Navy funds expended on dredging river channel 
in 1944 and Coast Guard funds expended for channel dredging 
in 1948 and 1949. 
18Excludes $1,000 Coast Guard funds expended and $9,000 
expended by Skagit County in fulfilling requirements of local 
cooperation. 
19Includes $159,584 appropriated and expended for previous 
projects. Excludes $51,609 Public Works Administration Funds 
expended. Excludes $62,697, value of work contributed by Port 
of Tacoma in fulfilling requirements of local cooperation. 
20Includes $5,347 appropriated and expended for previous 
projects. 
21Includes $228,084 appropriated and expended for previous 
projects. Excludes $40,000 Coast Guard funds and $192,557 
Emergency Relief Funds expended. 
22Includes $309,177 appropriated and expended for previous 
projects. Excludes $78,532 Public Works Administration Funds 
expended. 
23Includes $87,785 appropriated and expended for recreation 
facilities at completed project (Code 710). Excludes $26,000 
Emergency Relief Funds expended. 
"Includes $5,000 Advance Procurement Funds expended 
and $131,900 appropriated and expended under Maintenance 
and Operation of Dams and Other Improvements of Navigable 
Waters. 
25Excludes $281,000 Works Progress Administration Funds 
and $85,999 Emergency Relief Funds expended. 
"sIncludes $5,035 appropriated and expended for recreation 
facilities at completed project (Code 710). 
27Includes $102,200 appropriated and expended for recreation 
facilities at completed project (Code 710). 
28Includes $136,736 Public Works Acceleration Act Funds 
and $971,947 for recreation facilities at completed project (Code 
710), appropriated and expended. 
29Includes $174,776 Special Recreation Use Fees and 
$10,000 Advance Procurement Funds, appropriated and expended. 
Includes $131,900 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
3"Includes $58,000 Public Works Acceleration Act Funds 
and $147,983 for recreation facilities at completed project (Code 
710), appropriated and expended. 
"Includes $774,561 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
32Includes $42,221,634 for additional units, $16,276,363 for 
reregulating dam, and $475,000 for power planning. 
33Includes $42,201,602 for additional units, $16,276,363 for 
reregulating dam, and $475,000 for power planning. 
34Includes $299,546 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
38-18

TABLE 38-B 
SEATTLE, WASHINGTON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Mar. 2, 1919 
Sep. 3, 1954 
June 25, 1910 
July 3, 1930 
Aug. 26, 1937 
Sep. 3, 1954 
July 3, 1958 
Mar. 7, 1974 
Oct. 27, 1965 
June 25, 1910 
July 3, 1930 
June 20, 1938 
Sep. 3, 1954 
July 14, 1960 
Aug. 13, 1968 
June 3, 1896 
Mar. 2, 1907 
Mar. 2, 1907 
ANACORTES HARBOR, WA 
Channel in Capsante Waterway. 
Mooring basin. 
BELLINGHAM HARBOR, WA 
Whatcom Creek Waterway 26- and 18-foot channels. 
Entrance channel in Squalicum Creek Waterway. 
Maintenance of southerly half and westerly end of 
Squalicum Creek Basin. 
Small-boat basin adjacent to Squalicum Creek 
Waterway. 
Whatcom Creek Waterway, 30-foot channel. 
EDIZ HOOK, WA 
Construction of 10,000 linear feet of rock revetment, 
together with initial beach replenishment and 
annual nourishment. 
Emergency interim measures necessary to prevent 
breaching of Ediz Hook prior to construction of 
authorized project. 
EDMONDS HARBOR, WA 
Maintenance of rubblemound breakwater, 
1,850 feet long, and entrance channel, 
13 feet deep, 610 feet long and 65 feet 
wide. 
EVERETT HARBOR AND SNOHOMISH 
RIVER, WA 
Training dike 10,500 feet long extending across bar 
at outlet of old river channel. 
Raise 6,000 feet of training dike, extend spur dike, 
widen gap in dike as required, maintain East 
Waterway and channel to gap. 
Abandon project for Snohomish River and provide 
settling basin near 14th Street. 
Spur dike at Preston Point, remove training dike 
north of river outlet, enlarge channel to 14th Street, 
and deepen settling basin. 
Widen channel from settling basin to gap; extend 
channel to head of Steamboat Slough; and a settling 
basin within upper channel reach. 
Raise and extend existing training dike; and construct 
breakwater on westerly and southerly sides 
of 14th Street small-boat basin.4 
GRAYS HARBOR AND CHEHALIS 
RIVER, WA 
South jetty. 
A north jetty 9,000 feet long. 
The 18-foot channel. 
H. Doc. 1117, 64th Cong., 
1st Sess. 
S. Doc. 102, 83rd Cong., 
2d Sess. 
H. Doc. 1161, 60th Cong., 
2d Sess. 
H. Doc. 187, 70th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 70, 74th 
Cong., 1st Sess.' 
H. Doc. 558, 82d Cong., 
2d Sess.2 
S. Doc. 46, 85th Cong., 
1st Sess.3 
H. Doc. 93-101, 93d Cong., 
1st Sess., P.L. 93-251 
H. Doc. 147, 88th Cong., 
1st Sess., P.L. 89-298 
H. Doc. 1108, 60th Cong., 
2d Sess. 
H. Doc. 377, 71st Cong., 
2d Sess. 
H. Doc. 546, 75th Cong., 
3d Sess. 
H. Doc. 569, 81st Cong., 
2d Sess. 
H. Doc. 348, 86th Cong., 
2d Sess. 
H. Doc. 357, 90th Cong., 
2d Sess.5 
Annual Report, 1895, 
pp. 3517-3533 
Rivers and Harbors 
Committee Doc. 2, 59th 
Cong., 2d Sess. 
H. Doc. 507, 59th Cong., 
1st Sess. 
38-19 
3. 
4.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 38-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
June 25, 1910 
June 25, 1910 
Aug. 8, 1917 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
Aug. 30, 1935 
Dec. 22, 1944 
as amended 
Mar. 2, 1945 
June 30, 1948 
Sep. 3, 1954 
Sep. 3, 1954 
July 14, 1960 
as amended 
June 25, 1910 
Mar. 4, 1913 
Aug. 8, 1917 
Sep. 22, 1922 
June 26, 19348 
Aug. 30, 19359 
Dec. 22, 1944 
as amended 
Extend north jetty 7,000 feet; length of south jetty 
fixed at 13,734 feet. 
A 6-foot channel above Cosmopolis 
Dredging in bar channel. 
Dredging in bar channel. 
16-foot channel from Cosmopolis to Montesano6 
Reconstruct north and south jetties to an elevation of 
16 feet above mean lower low water. 
Maintain 26-foot channel below Aberdeen (as authorized 
by Public Works Administration Dec. 11, 1933) 
and combining projects for Grays Harbor and bar 
entrance and Grays Harbor, inner portion, and 
Chehalis River under a modified project for Grays 
Harbor and Chehalis River. 
Construction, operation, and maintenance of 
recreation facilities 
Maintain 30-foot depth in channel from deep water in 
Grays Harbor to Port of Grays Harbor Commission 
terminal, which was deepened from 26 to 30 feet 
with Navy funds. 
14-foot channel to Bay City; breakwater at 
Westhaven; protection of Point Chehalis; and 
maintenance of Westhaven entrance channel.' 
Dredging and maintenance of a 30-foot channel and 
turning basin from Aberdeen to Cosmopolis. 
Additional breakwater, 1,400 feet long, at Westhaven 
Cove. 
KENMORE NAVIGATION CHANNEL, WA 
Construction of navigation channel 15 feet deep 
consisting of a 100-foot wide inner channel 900 feet 
long, an 800-foot long transition channel with 24 o 
30-foot bend and maximum width of 190 feet, and a 
120-foot wide outer channel 1,200 feet long. 
LAKE WASHINGTON SHIP CANAL, WA 
For a double lock and fixed dam with gated spillway 
and necessary accessory works at entrance to 
Salmon Bay; dredging a channel from locks to deep 
water in Puget Sound, and excavation by local 
interests of a channel from locks into Lake 
Washington. 
Dredging below locks and revetting canal banks. 
Increased dimensions of channel between Puget 
Sound and locks and a 600-foot extension of lower 
guide pier. 
Operating and care of locks and dam provided for 
with funds from War Department appropriations for 
Rivers and Harbors. 
Enlarge channel between locks and Lake 
Washington. 
Construction, operation, and maintenance of 
recreation facilities. 
Rivers and Harbors 
Committee Doc. 29, 
61st Cong., 2d Sess. 
H. Doc. 1125, 60th Cong., 
2d Sess. 
H. Doc. 1729, 64th Cong., 
2d Sess. 
H. Doc. 582, 69th Cong., 
2d Sess. 
H. Doc. 315, 70th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 2, 74th 
Cong., 1st Sess. 
H. Doc. 53, 73rd Cong., 1st 
Sess.; Rivers and 
Harbors Committee 
Doc 2, 74th Cong., 
1st Sess. 
Sec. 4, Flood Control Act 
of 1944 
Report in Office, Chief of 
Engineers 
H. Doc. 635, 80th Cong., 
2d Sess. 
H. Doc. 412, 83d Cong., 
2d Sess. 
H. Doc. 30, 84th Cong., 
1st Sess.5 
Sec. 107, P.L. 86-645. 
Authorized by Chief of 
Engineers, Oct. 7, 1980 
H. Doc. 953, 60th Cong., 
1st Sess. 
H. Doc. 800, 64th Cong., 
1st Sess. 
H. Doc. 324, 67th Cong., 
2d Sess. 
H. Doc. 140, 72d Cong., 
1st Sess. 5 
Sec. 4, Flood Control Act 
of 1944 
38-20 
7. 
8.

TABLE 38-B 
(Continued) 
SEATTLE, WASHINGTON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 193510 
Aug. 26, 1937 
Mar. 2, 1945 
July 13, 1892 
July 3, 1930 
Mar. 2, 1945 
Sep. 3, 1954 
Mar. 2, 1919 
Mar. 3, 1925 
July 3, 1930 
Aug. 30, 1935 
July 13, 1892 
Aug. 30, 1935 
Oct. 23, 1962 
June 13, 1902 
July 3, 1930 
Aug. 26, 1937 
OLYMPIA HARBOR, WA 
Channel 22 feet deep and 150 feet wide. 
Channels of 26-foot depth on east side of harbor. 
Elimination from project of 12-foot channel on east 
and west sides of harbor, and for a channel 30 feet 
deep and 300 feet wide between Budd Inlet and port 
terminal, with turning basin of same depth. 
Widen outer portion of channel to 500 feet, and 
widen entrance to turning basin. 
Entrance channel 500 feet wide to and including 
a turning basin 3,350 feet long and generally 
960 feet wide, all at a depth of 30 feet at mean 
lower low water.' 
PUGET SOUND AND ITS TRIBUTARY 
WATERS, WA 
Maintenance of the rivers tributary to Puget Sound 
by snagging and dredging; and removal of floating 
debris from Seattle Harbor. 
QUILLAYUTE RIVER, WA 
Jetty (5 feet high) on easterly side of mouth, and a 
dike with groins, on westerly side, to stabilize 
entrance." 
Maintenance dredging to provide a channel 6 feet 
deep and of suitable width from ocean to within 
river mouth. 
Raising jetty to 15 feet; channel 10 by 100 feet, 2,000 
feet long; moorage basin.12 
SEATTLE HARBOR, WA 
Maintenance of East and West Waterways 750 feet 
wide and 34 feet deep, and of Duwamish Waterway 
20 feet deep and 150 feet wide as far south as 
Eighth Avenue South Bridge. 
Enlargement of Duwamish Waterway.13 
Maintenance of East Waterway between 750-foot 
section and Spokane Street, and turning basin at 
junction of East and Duwamish Waterways. 
SWINOMISH CHANNEL, WA 
Channel 4 feet deep and 100 feet wide, and dike 
construction. 
Enlargement of channel to present project 
dimensions. 
Removal of navigation hazards at "Hole-in-the-Wall". 
TACOMA HARBOR, WA 
City Waterway. 
Hylebos Waterway 
H. Doc 244, 69th Cong., 
1st Sess. 
Rivers and Harbors 
Commmittee Doc. 5, 71st 
Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 21, 
73rd Cong., 2d Sess. 
Rivers and Harbors 
Committee Doc. 75, 
74th Cong., 2d Sess. 
H. Doc. 699, 76th Cong., 
3d Sess.5 
Annual Report for 1893, 
page 342510 
H. Doc. 125, 71st Cong., 
1st Sess. 
H. Doc. 218, 78th Cong., 
1st Sess. 
H. Doc. 579, 81st Cong., 
2d Sess.5 
S. Doc. 313, 65th Cong., 
3d Sess. 
H. Doc. 108, 68th Cong., 
1st Sess. and H. Doc. 
126, 71st Cong., 2d Sess.5 
H. Doc. 211, 72d Cong., 
1st Sess.5 
H. Doc. 31, 52d Cong., 
1st Sess., and Annual 
Report, 1892, p. 2752 
S. Committee Print, 73rd 
Cong., 1st Sess. 
H. Doc. 499, 87th Cong., 
2d Sess.5 
H. Doc. 76, 56th Cong., 
2d Sess. 
Rivers and Harbors 
Committee Docs. 25, 
71st Cong., 2d Sess., 
and 91, 74th Cong., 
2d Sess. 
38-21 
10. 
12. 
13. 
14. 
15. 
16.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 38-B 
(Continued) 
AUTHORIZING LEGISLATION 
Date 
Authorizing 
Act Project and Work Authorized 
Aug. 30, 1935 
Sep. 3, 1954 
Oct. 23, 1962 
Mar. 4, 191314 
July 27, 1916 
Aug. 30, 19359 
Aug. 30, 193515 
Mar. 2, 1945 
Sep. 3, 1954 
July 24, 1946 
as amended 
May 17, 1950 
Aug. 6, 1958 
July 24, 1946 
as amended 
June 22, 1936 
Dec. 22, 1944 
as amended 
Dec. 15, 1970 
June 22, 1936 
June 28, 1938 
17. 
Training walls at mouth of Puyallup River (previously 
authorized by Public Works Administration Sep. 
6, 1933) 
Blair Waterway extension. 
Blair and Hylebos Waterways extensioh. 
WATERWAY CONNECTING PORT 
TOWNSEND AND OAK BAY, WA 
Canal 15 feet deep, 75 feet wide on the bottom, and 
about 4,800 feet long; construct jetties to protect 
channel at southern or Oak Bay end, and a bulkhead 
for retention of dredging material. 
WILLAPA RIVER AND HARBOR AND 
NASELLE RIVER, WA 
Channel 24 feet deep, 200 feet wide, in Willapa River, 
and 150 feet wide in the forks. 
Maintenance of channel over bar to a depth of 26 feet 
and minimum width of 500 feet. 
For cutoff channel at Narrows. 
Channel from deep water in Palix River to Bay 
Center dock. 
Widen Willapa River channel to 360 and 250 feet 
between South Bend and the forks; Tokeland and 
Nahcotta basins; and Naselle River clearance. 
DUNGENESS RIVER, SEQUIM, WA 
Construction of riprap bank protection. 
HOWARD A. HANSON DAM, WA 
Eagle Gorge flood control dam on Green River. 
Redesignation of project as Howard A. Hanson Dam 
MIDDLE FORK NOOKSACK RIVER, DEMING, 
WA 
Construction of riprap bank protection. 
MUD MOUNTAIN DAM, WA 
Flood control dam on White River. 
Construction, operation, and maintenance of 
recreation facilities. 
PLACER CREEK, ID 
Construction of 3,700-foot concrete channel to confine 
Placer Creek flows through Wallace, Idaho. 
STILLAGUAMISH RIVER, WA 
Improvement of flood channel by clearing and bank 
revetment at 26 places; concrete weir at head of 
Cook Slough; and 2 cutoff channels in Cook Slough. 
Maintenance of improvements. 
38-22 
See 
Section 
in Text 
Rivers and Harbors 
Committee Doc. 55, 
72nd Cong., 2d Sess. 
H. Doc 171, 84th Cong., 
2d Sess.5 
S. Doc. 101, 87th Cong., 
2d Sess.5 
H. Doc. 625, 62d Cong., 
2d Sess. 
H. Doc. 706, 63d Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 41, 
72d Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 37, 
73d Cong., 2d Sess. 
H. Doc. 481, 76th Cong., 
2d Sess. 
H. Doc. 425, 83d Cong., 
2d Sess.5 
Sec. 14, P.L. 79-526 
Authorized by Chief of 
Engineers, June 21, 1985 
H. Doc. 271, 81st Cong., 
1st Sess.5 
P.L. 85-592 
Sec. 14, P.L. 79-526 
Authorized by Chief 
of Engineers, 
Apr. 7, 1986 
S. Committee Print, 
Puyallup River, WA, 
74th Cong., 2d Sess. 
Sec. 4, Flood Control Act 
of 1944 
H. Doc. 357, 91st Cong., 
2d Sess.5 
H. Doc. 657, 71st Cong., 
3d Sess.5 
P.L. 75-761 
Documents 
18. 
20. 
21. 
24. 
25. 
26. 
28.

TABLE 38-B 
(Continued) 
SEATTLE, WASHINGTON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
June 22, 1936 
Dec. 22, 1944 
as amended 
Oct. 23, 1962 
Dec. 22, 1944 
as amended 
Mar. 7, 1974 
Mar. 7, 1974 
May 17, 1950 
Dec. 22, 1944 
as amended 
July 24, 1946 
June 30, 1948 
July 9, 1952 
Dec. 22, 1944 
as amended 
Oct. 22, 1976 
as amended 
May 17, 1950 
Nov. 7, 1966 
Jan. 2, 1968 
Aug. 13, 1968 
June 19, 1970 
Dec. 31, 1970 
29. 
30. 
38-23 
TACOMA, PUYALLUP RIVER, WA 
Channel improvement to protect people and industrial 
section of city of Tacoma. 
Construction, operation, and maintenance of 
recreation facilities. 
WYNOOCHEE LAKE, WA 
Dam and reservoir for water supply, flood control, 
irrigation, fish and wildlife, and recreation. 
Construction, operation, and maintenance of 
recreation facilities. 
Transfer to State of Washington as a part of project 
costs, $696,000 for construction of fish hatchery 
facilities. 
Amend contract between city of Aberdeen and 
United States for use of storage space, permitting 
deferral of the major portion of the first 10-year 
payments. 
ALBENI FALLS DAM, ID 
Multi-purpose dam with powerhouse. 
Construction, operation, and maintenance of 
recreation facilities. 
CHIEF JOSEPH DAM - RUFUS WOODS 
LAKE, WA 
Multi-purpose dam and powerhouse on Columbia 
River at Foster Creek. 
Redesignation of the project as Chief Joseph Dam. 
Designation of reservoir as Rufus Woods Lake. 
Construction, operation, and maintenance of 
recreation facilities. 
School facilities for education of dependents of 
construction personnel. 
LIBBY DAM - LAKE KOOCANUSA, MT 
Multi-purpose dam and powerhouse, and 
reregulating facilities. 
School facilities for education of dependents of 
construction personnel, Libby project. 
Airport facility at Kelley Flats, MT. 
Design standards for relocation of Montana State 
Highway 37 to be those adopted by State of 
Montana pursuant to provisions of Highway Safety 
Act of 1966. 
Participation with State of Montana in construction, 
operation and maintenance of fish hatchery 
facilities. 
Designation of lake formed by the waters impounded 
by Libby Dam as Lake Koocanusa. 
S. Committee Print, 
Puyallup River, WA, 
74th Cong., 2d Sess.5 
Sec. 4, Flood Control Act 
of 1944 
H. Doc. 601, 87th Cong., 
2d Sess.5 
Sec. 4, Flood Control Act 
of 1944 
P.L. 93-251 
P.L. 93-251 
S. Doc. 9, 81st Cong., 
1st Sess.5 
Sec. 4, Flood Control Act 
of 1944 
H. Doc. 693, 79th Cong., 
2d Sess.5 
P.L. 858, 80th Cong., 
2d Sess. 
P.L. 469, 82d Cong., 
2d Sess. 
Sec. 4, Flood Control Act 
of 1944 
P.L. 94-587 
P.L. 95-26 
H. Doc. 531, 81st Cong., 
2d Sess.5 
P.L. 89-789 
P.L. 90-23915 
P.L. 90-48317 
P.L. 91-28218 
P.L. 91-625 
31. 
32. 
33.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 38-B 
(Continued) 
AUTHORIZING LEGISLATION 
Date 
Authorizing 
Act Project and Work Authorized 
Dec. 31, 1970 
Mar. 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
Design and construction of sewage collection and 
sewage treatment facility as part of relocation of 
municipal facilities of Rexford, MT; and 
compensation for railroad employees suffering longterm 
economic injury through reduction of income 
as result of the relocation of rail transportation 
facilities due to the construction of Libby Dam. 
Phase I design memorandum stage for installation 
of power generating facilities at Libby Reregulating 
Dam. 
Construction of fish production measures to 
compensate for fish losses attributed to the project, 
and for acquisition of necessary real estate, 
construction of access roads and utilities (amends 
P.L. 91-282 by increasing limitation from $750,000 
to $4,000,000). 
Acquisition of land not to exceed $2,000,000 for 
prevention of wildlife grazing losses caused by the 
project. 
Reimbursement (not to exceed $350,000) to Boundary 
County, ID for reconstruction of Deep Creek 
Bridge made necessary by duration of high flows 
during drawdown operations at Libby Dam. 
Compensation, not to exceed $1,500,000, to Drainage 
Districts and owners of leveed and unleveed lands, 
in Kootenai Flats, Boundary County, ID, for 
damages caused by duration of higher flows during 
drawdown operations at Libby Dam. 
P.L. 91-611 
S. Doc. 93-29, 93d Cong., 
1st Sess., P.L. 93-251 
P.L. 93-251 
P.L. 93-251 
P.L. 93-251 
P.L. 93-251 
1 Contains latest published map of Squalicum Creek 
Waterway. 
2Contains latest published map of small-boat basin. 
3Contains latest published map of Whatcom Creek 
Waterway. 
4Deferred. 
5Contains latest published map. 
"Inactive. 
'A portion deferred. 
8Permanent Appropriations Repeal Act. 
9Included in Public Works Administration Program. 
'�Annual Report for 1913 contains latest published map 
(page 3127). 
11A portion inactive. 
12Maintenance of these items, as well as sandspit north of 
James Island, is included in this modification. 
'3Includes settling basin of 100,000 cubic yards capacity 
which has been classified as inactive. 
14Annual Report of 1915 contains latest published map (page 
3441). 
15Included in Emergency Relief Program, May 28, 1935. 
16 Supplemental Appropriations Act of 1968, Section 502. 
"Flood Control Act of 1968, Section 212. 
18River Basin Monetary Authorization and Miscellaneous 
Civil Works Amendments Act of 1970, Section 7. 
38-24 
See 
Section 
in Text Documents

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Anacortes Navigation Channel, WA' Completed 1977 825,2634 
Bellingham Harbor, WA (I&J 
Street Waterway)' Completed 1966 125,634 
Bellingham, Squalicum Small 
Boat Harbor, WA' Completed 1981 1,744,0255 - 
Blaine Harbor, WA Completed 1958 346,650 - 
Columbia River, Wenatchee 
to Kettle Falls, WA Completed 1923 274,3906 7,693 
East Bay Small Boat Basin, Completed 1985 1,619,956 - 
Olympia, WA' 
Flathead River, MT Completed 1901 9,811 
Floating Breakwater Prototype 
Test Program, WA' Completed 1985 1,461,590 - 
Friday Harbor Marina, WA1 Completed 1985 1,618,5378 - 
Hammersley Inlet, WA Completed 1950 9,000 10,683 
Hoquiam River, WA Completed 1950 51,294 5,316 
Kingston Harbor, WA Completed 1967 262,570' 5,00010 
Kootenai River, ID and MT Completed 1933 9,255 5,643 
Lake Crockett, WA Completed 1983 377,99011 512,940 
Mats Mats Bay, WA 1 Completed 1970 137,67912 - 
Neah Bay, WA Completed 1982 2,057,266 1,854,05813 
Okanogan and Pend Oreille Rivers, WA Abandoned 1913 63,880 7,634 
Polson Bay, Flathead Lake, MT Completed 1918 4,491 259 
Port Angeles Harbor, WA2 Completed 1960 470,873 - 
Port Gamble Harbor, WA Completed 1953 11,91114 13,337 
Port Orchard Bay, WA3 Completed 1928 42,804 - 
Port Townsend, WA Completed 1974 480,89915 26,787 
Shilshole Bay, Seattle, WA Completed 1962 2,575,09116 
Skagit River, WA Completed 1950 102,33017 36,258 
Stillaguamish River, WA Inactive 1946 4,23418 
Westhaven Cove Small Boat 
Basin, WA 1 Completed 1981 2,000,00019 
1Authorized by Chief of Engineers under authority of Section 
107, Public Law 86-645. 
Maintenance by Port of Port Angeles. 
'No maintenance required. 
4Includes $87,963 preauthorization cost, appropriated and 
expended. Excludes $457,200 contributed funds expended. 
5Includes $132,349 preauthorization cost, appropriated and 
expended and excludes $1,570,886 contributed funds expended. 
Includes $40,790 appropriated and expended for WA State 
Sales and Use Tax, FY 85. 
'Includes $8,005 expended for previous project. Excludes 
$50,000 expended by State of Washington in fulfilling terms of 
local cooperation. 
'Includes $330,517 appropriated and expended for 
preauthorization cost and excludes $2,186,612 contributed funds 
expended. 
*Includes $43,037 for previous project and $235,341 
preauthorization cost, appropriated and expended. Excludes 
$1,267,881 contributed funds expended. 
'Excludes $390,753 contributed funds and $3,000 Coast 
Guard funds expended. 
10Mitigation shore damages study expended. 
11Includes $117,750 appropriated and expended for recreation 
facilities at completed project (Code 710). 
12Excludes $28,288 contributed funds expended. 
1 Includes $34,352 appropriated and expended for WA State 
Sales and Use Tax, FY 85. 
14Excludes $21,260 contributed funds expended. 
"Excludes $92,423 contributed funds expended. 
1"Excludes $15,000 Coast Guard funds expended. 
17Includes $2,500 expended for previous project. 
"sFor economic study only. 
18Includes $178,371 preauthorization cost, appropriated and 
expended, and excludes $1,230,035 contributed funds expended. 
38-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 38-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report Operation 
See Annual and 
Project 
American Lake, Vicinity of Fort 
Lewis, WA1 
Bear Creek, Flathead County 
Bridge, near Essex, MT2 
Blackfoot River, Matt Little Road, MT2 
Bogachiel River, Highway 101, 
near Forks, WA2 
Bogachiel River, Undie Road, Forks, WA2 
Cedar River, Renton, WA2 
Chehalis River, City of Chehalis, 
Raw Water Pumphouse, WA2 
Chehalis River, Independence Road, 
Thurston County, WA2 
Chehalis River, Montesano, WA2 
Clallam Bay, Sekiu, WA2 
Clallam River, Highway 112, WA2 
Clark Fork River, Drummond, MT 2 
Clark Fork River, Missoula, MT 
Clark Fork River, Missoula, MT2 
Clark Fork River, Superior, MT 2 
Clark Fork River, Vicinity of Plains, MT2 
Clearwater River, Jefferson County Road, WA2 
Clearwater River, Queets River Bridge, WA2 
Coeur d'Alene, Spokane River, ID 
Coeur d'Alene River, Springston, ID 2 
Columbia River Basin, Local Protection 
Projects, ID, MT, and WA: 
Entiat River, WA 
Lightning Creek, Clark Fork, ID 
Methow River, WA 
Okanogan River, WA 
Yakima River at Ellensburg, WA 
Deschutes River, Gleason Road Bridge, 
near Tumwater, WA2 
Deschutes River, Rich Road Bridge, 
near East Olympia, WA2 
Dungeness River, Area #5, WA2 
Dungeness River, Area #8, WA2 
Dungeness River, Clallam County, WA' 
Dungeness River, Sequim, WA 2 
Dungeness River, Taylor Cut-off Road, WA2 
Elwha River, Clallam County, WA2 
Entiat River, Chelan County, WA2 
Flathead River, MT2 
Flathead River, Bradley Channel Area, MT2 
Flathead River, near Kalispell, MT2 
Status Report For Construction Maintenance 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Inactive 
Inactive 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1957 
1971 
1964 
1981 
1981 
1949 
1966 
1965 
1977 
1977 
1981 
1978 
1983 
1978 
1971 
1950 
1968 
1950 
1941 
1950 
1958 
1959 
1958 
1958 
1980 
1965 
1967 
1950 
1950 
1964 
1981 
1961 
1951 
1978 
1972 
1955 
1948 
59,5825 
1,424 
17,836 
156,000 
57,000 
32,264 
35,454 
47,916 
140,080 
48,698 
43,500 
18,660 
385,0106 
31,548 
28,356 
27,947 
50,0007 
49,165 
152,872 
25,452 
42,726 
1,1008 
30,0009 
26,292 
22,956 
2,155 
2,895 
52,04010 
99,000 
14,09311 
17,303 
38,000 
20,940 
26,265 
33,347 
38-26

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-E OTHER AUTHORIZED FLOOD 
(Continued) 
CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Flathead River, near Kalispell, MT 
Flathead River, Old Steel Bridge, 
near Kalispell, MT2 
Foster Creek Road, Douglas County, WA2 
Green River between Kent and Auburn, WA 
and Allentown, WA2 
Green River, State Highway 181, WA2 
Henderson Bay, Purdy, WA2 
Hoh River, County Road 16, WA 2 
Hoh River, U.S. Highway 101, WA 2 
Hoh River Road, Jefferson County, 
WA (HO 1360)2 
Hoh River Road, Jefferson County, 
WA (HO 1361)2 
Hoh River Road, Jefferson County, 
WA (HO 1362)2 
Hoh River, near Forks, WA2 
Hoko River, Sekiu, WA2 
Hood Canal, Hoodsport, WA2 
Hoquiam River, WA2 
Kootenai River, Bonners Ferry, ID2 
Kootenai River, Kootenai Flats Area, 
District #1, ID 2 
La Conner, Swinomish Channel, WA2 
Methow River, WA (MET 1-74)2 
Methow River, WA (MET 2-74)2 
Methow River, WA (MET 3-74)2 
Methow River, Barclay Canal, WA2 
Methow River, Twisp, WA2 
Methow River, Twisp-Carlton Highway, 
Vicinity of Twisp, WA2 
Methow River, Vicinity of Pateros, WA2 
Mineral Creek, Lewis County, WA2 
Moclips River, Moclips, WA2 
Naches River, Naches, WA2 
Newaukum River, Lewis County, 
Hamilton, WA2 
Nisqually River, near Elbe, WA2 
Nisqually River, Thurston County, WA2 
Nisqually River, Vicinity of Elbe, WA 2 
Nooksack River, Acme, WA2 
Nooksack River, Guide Bridge 
Location, WA2 
Nooksack River, above Highway 1Z 
Bridge, WA2 
North Fork Skykomish River, WA2 
Deferred 1981 300,0008 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1964 
1962 
1972 
1976 
1977 
1980 
1980 
1956 
1961 
1964 
1983 
1977 
1977 
1977 
1950 
1965 
1979 
1974 
1974 
1974 
1976 
1949 
1951 
1951 
1972 
1977 
1982 
1972 
1948 
1960 
1952 
1985 
1950 
1960 
1981 
13,438 
50,000 
24,605 
27,001 
37,359 
143,000 
194,000 
22,08212 
11,916 
41,622 
173,00013 
21,083 
59,812 
52,600 
42,325 
14,885 
40,525 
15,700 
11,200 
13,450 
19,810 
31,783 
33,200 
11,726 
11,836 
17,608 
59,000 
24,792 
37,636 
26,790 
19,445 
77,300 
6,075 
10,807 
222,500 
38-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 38-E OTHER AUTHORIZED FLOOD 
(Continued) 
Project 
Okanogan River, WA2 
Okanogan River, Omak, WA' 
Okanogan River, Oroville, WA 
Pilchuck River, WA 
Pilchuck River, WA2 
Pilchuck River, Everett, WA2 
Pilchuck River, State Highway 92, 
Granite Falls, WA2 
Powell County High School, Deer Lodge, MT2 
Pysht River, Sekiu, WA2 
Queets River, Jefferson County 
Sewage Lagoon, WA2 
Quillayute River, Quileute Tribal Float 
and Bridge, WA2 
Quinalt River, Grays Harbor, WA2 
Quinalt River Road, Jefferson County, WA2 
Rock Creek, Granite County, MT2 
Rock Creek, Missoula County, MT2 
Rock Creek Road, MT2 
Rye Creek, MT 2 
St. Maries, St. Joe River, ID 
Sammamish River, WA 
Sauk River, WA 2 
Sewage Treatment Plant, Missoula, MT 2 
Shelton Creek, WA' 
Skagit Creek, WA 
(Avon Bypass) 
Skagit River, WA (Levee and 
Channel Improvements) 
Skagit River, Cape Horn Road, WA 2 
Skagit River, Deadman's Slough, WA2 
Skagit River, Pressentin Creek, WA2 
Skagit River, South Skagit Highway, WA2 
Skagit River, South Skagit Highway, 
WA (Job 66-1)2 
Skagit River, South Skagit Highway, 
WA (Job 67-1)2 
Snohomish River, Lowell- 
Snohomish River Road, WA2 
Snohomish River, Snohomish, WA2 
Snoqualmie River, West Snoqualmie, WA2 
Soleduck River Bridge, WA2 
Soleduck River, near Mora Road Bridge, WA2 
Spokane, Spokane River, WA 
Startup, Skykomish and Wallace Rivers, WA' 
Status 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Deferred 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
CONTROL PROJECTS 
38-28 
For Last 
Full Report 
See Annual 
Report For 
1974 
1981 
1982 
1985 
1971 
1980 
1971 
1964 
1977 
1981 
1972 
1981 
1961 
1974 
1973 
1980 
1973 
1942 
1967 
1974 
1965 
1979 
1968 
1982 
1966 
1980 
1980 
1963 
1966 
1967 
1969 
1970 
1977 
1961 
1963 
1939 
1970 
Cost to Sep. 30, 1986 
Operation 
and 
Construction Maintenance 
10,100 
2,231,03014 
1,787,630's 
81,000 
10,713 
54,000 
30,973 
11,291 
86,160 
125,000 
39,300 
208,000 
15,92816 
49,657 
31,565 
50,000 
22,819 
357,698 
2,582,53617 
20,860 
50,00018 
872,02119 
54,4687 
1,934,79220 
46,489 
93,000 
137,000 
40,753 
17,719 
50,00021 
44,227 
60,90022 
15,565 
16,43623 
11,433 
2,9448 
271,713

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-E OTHER AUTHORIZED FLOOD 
(Continued) 
CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Stillaguamish River, South Fork, Mountain 
Loop Highway, near Robe, WA2 Completed 1964 50,00024 - 
Stillwater River, MT2 Completed 1973 17,457 - 
Stillwater and Whitefish Rivers, MT2 Completed 1977 34,513 - 
Strong Creek, Hope, ID2 Completed 1970 8,442 - 
Tahola, WA2 Completed 1979 223,893 - 
Upper Puyallup River, WA3 Completed 1938 71,49525 - 
Wenatchee Canyons 1 and 2, WA4 Active 1977 544,331 - 
West Fork Foster Creek, WA2 Completed 1958 19,513 - 
Willapa River at Raymond, WA Deferred 1982 508,13026 - 
Wynoochee River, County Road 141, WA2 Completed 1976 111,072 - 
Wynoochee River, near Montesano, WA2 Completed 1969 50,00027 
Wynoochee River, near Montesano, 
WA (WR-1-72)2 Completed 1972 50,000 - 
Yakima, Yakima River, WA Completed 1948 381,961 - 
Yakima River, Cle Elum, WA2 Completed 1949 8,047 - 
Yakima River, below mouth of Teanaway 
River, near Cle Elum, WA2 Completed 1947 48,272 - 
Yakima River, West Richland, WA2 Completed 1977 36,768 - 
Yakima River, Yakima, WA2 Completed 1983 125,500 - 
'Authorized by Chief of Engineers under authority of Section 
205, Public Law 858, 80th Congress, as amended. 
2Authorized by Chief of Engineers under authority of Section 
14, Public Law 526, 79th Congress, as amended. 
3Authorized by Works Progress Administration Project No. 
OP 65-93-917. 
4Authorized by Secretary of Army under authority of Section 
201, Public Law 298, 89th Congress, H. Doc. 91-370. 
5Excludes $10,000 contributed funds expended. 
I6ncludes $7,850 appropriated and expended for recreation 
facilities at completed project (Code 710). Excludes $13,500 contributed 
funds expended. 
7Excludes $24,728 contributed funds expended. 
8Preconstruction planning only. 
9Excludes $14,300 for restudy. 
10Excludes Public Works Acceleration Act funds of $340,066. 
"Excludes $3,314 contributed funds expended. 
'2Excludes $21,807 contributed funds expended. 
'3Excludes $189,000 Federal Highway Administration funds 
expended. 
14Includes $125,000 preauthorization cost. Includes $1,030 
appropriated and expended for WA State Sales and Use Tax, 
FY 85. 
"Includes $160,700 preauthorization cost. Includes $8,130 
appropriated and expended for WA State Sales and Use Tax, 
FY 85. 
1"Excludes $4,843 contributed funds expended. 
17Excludes $696,923 contributed funds expended. Includes 
$117,420 preconstruction planning cost. 
"1Excludes $5,340 contributed funds expended. 
19Includes $100,221 preauthorization cost. 
20Includes $1,806,792 preauthorization planning cost. 
2'Excludes $24,488 contributed funds expended. 
22Excludes $14,307 contributed funds expended. 
23Excludes $1,960 contributed funds expended. 
24Excludes $46,182 contributed funds expended. 
"Emergency Relief Funds, Works Progress Administration. 
Excludes $13,704 contributed funds expended. 
26Includes $32,630 preconstruction planning cost. 
27Excludes $21,311 contributed funds expended. 
38-29

TABLE 38-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
OTHER AUTHORIZED MULTIPLE PURPOSE 
PROJECTS, INCLUDING POWER 
For Last 
Full Report 
See Annual 
Project Report For 
Cost to Sep. 30, 1986 
Construction 
Operation and 
Maintenance 
Priest Rapids Dam, Columbia River, WA 1954 350,0001 
1For partnership planning. Excludes funds expended for 544, 83d Congress. Project constructed by Grant County Public 
acquisition of lands under partnership arrangement for Priest Utility District. 
Rapids and Wanapum Dams, in accordance with Public Law 
TABLE 38-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report Deauthorized Expended Expended 
Columbia River Basin, Local 
Protection Projects, ID, MT, 
and WA: 
Crab and Wilson Creeks, WA 1958 1964 $9,1001 
St. Regis River, MT 1958 1978 4,4002 
Wenatchee River, WA 1958 1978 2,0003 
Hammersley Inlet, WA 1950 1978 -- 
(Uncompleted Portion) 
Port Angeles Harbor, WA 1960 1977 
(Uncompleted Portion) 
Port Gamble Harbor, WA 1953 1977 
(Uncompleted Portion) 
Skagit River, WA 1950 1978 
(Uncompleted Portion) 
1Includes $100 for preauthorization studies and $9,000 for 
preconstruction planning. 
2Includes $3,000 for preauthorization studies and $1,400 for 
preconstruction planning. 
3Preauthorization studies only. 
38-30

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-H LAKE WASHINGTON SHIP CANAL, WA 
PRINCIPAL FEATURES OF DOUBLE LOCK AND DAM 
(See Section 8) 
Section Large Lock Small Lock 
Miles above mouth 1Y4 1/4 
Clear width of chamber Feet 80 28 
Maximum available length Feet 760 123 
Lift Feet 26 26 
Depth on upper miter sill1 Feet 331/2 16 
Depth on intermediate miter sill2 Feet 29 - 
Depth on lower miter sill2 Feet 29 16 
Character of foundation Clay Clay 
Kind of dam Fixed dam with Fixed dam with 
gated spillway. gated spillway. 
Type of construction Concrete Concrete 
Year completed 1916 1916 
Cost 3 3 
1Low water in upper pool. 3Cost of double lock and dam was $2,224,712 and the 
2Mean lower low water in Puget Sound. emergency gates, completed in 1923, $174,693. 
TABLE 38-I PROJECT CONDITION SURVEYS 
(See Section 11) 
Name of Project 
Washington: 
Anacortes Harbor 
Bellingham Harbor 
Blaine Harbor 
Kenmore Navigation Channel 
Lake Crockett 
Mats Mats Bay 
Port Gamble 
Port Townsend 
Tacoma Harbor 
Waterway Connecting Port 
Towsend and Oak Bay 
Date Survey Conducted 
March 1986 
April-May 1986 
May 1986 
July 1986 
April 1986 
June 1986 
July 1986 
May 1986 
January 1986 
June 1986 
38-31

TABLE 38-4 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
FLOOD CONTROL ACTIVITIES 
PURSUANT TO SECTION 205, 
PUBLIC LAW 858, 80TH CONGRESS, AS AMENDED 
(PREAUTHORIZATION) 
Study Identification Fiscal Year Costs (1986) 
Bowman Hilton Mobile Home Park, WA $ -134 
Clear & Clarks Creeks, Pierce County, WA 15,000 
Cottonwood Creek, Deer Lodge, MT1 35 
Elwha Klallam Reservation, Elwha River, WA 70,712 
Flood Warning System, Snohomish Valley, WA2 7,500 
Satus Creek, Yakima Indian Reservation, WA2 7,500 
Sauk River, Darrington, WA2 7,500 
Toppenish/Simcoe Creek, Yakima Indian Nation, WA 7,500 
TOTAL $ 115,613 
1Study terminated. 
2Unfavorable appraisal 
TABLE 38-K EMERGENCY FLOOD CONTROL ACTIVITIES 
REPAIR, FLOOD FIGHTING, AND RESCUE WORK 
(PUBLIC LAW 99, 84TH CONG., AND ANTECEDENT LEGISLATION) 
Project and Location Fiscal Year Costs (1986) 
Disaster Preparedness 
Emergency Operations 
Rehabilitation 
$ 272,346 
7,129 
154,318 
TOTAL $ 433,793 
38-32

WALLA WALLA, WA, DISTRICT * 
This District consists of all Columbia River drainage 
and tributaries thereto between the head of the McNary 
pool (River Mile 345.4) and the Umatilla Bridge (River 
Mile 290.5) below McNary Dam, except the Yakima River 
Basin above the Van Giesen Street Bridge (River Mile 8.4) 
near Richland, WA. 
IMPROVEMENTS 
Navigation 
1. Navigation Work Under 
Special Authorization .................. 
Flood Control 
2. Columbia River Basin, Local 
Flood Protection Projects ............... 
3. Catherine Creek OR ................... 
4. Clear & Burnt River, OR ............... 
5. Colfax, Palouse River, WA .............. 
6 Flood Control Work 
Under Special Authorization ............. 
7. Inspection of Completed Flood 
Control Projects ....................... 
8. Inspection of Completed PL-99 Works .... 
9. Lucky Peak Lake, ID .................. 
10. Mill Creek Lake, WA ................. 
11. Owyhee River, OR ..................... 
12. Scheduling Flood Control 
Reservoir Operations ................... 
Multiple-Purpose Projects, 
Including Power 
13. Dworshak Dam and Reservoir, ID ........ 
14. Ice Harbor Lock and Dam- 
Lake Sacajawea, WA ................... 
15. Lewiston-Clarkston Bridge, 
ID and WA ........................... 
16. Little Goose Lock and Dam- 
Lake Bryan, WA ...................... 
17. Lower Granite Lock and Dam, WA ....... 
18. Lower Monumental Lock and 
Dam-Lake Herbert G. West, WA ........ 
19. Lower Snake River Fish & Wildlife 
Compensation Plan, WA, OR, ID......... 
Page 
20. McNary Lock and Dam-Lake Wallula, 
39-2 OR and WA .......................... 
21. Snake River Downstream from Johnson 
Bar Landing, OR, WA and ID ........... 
39-2 
39-2 
39-2 
39-2 
39-2 
39-2 
39-3 
39-3 
39-3 
39-3 
39-4 
39-4 
39-4 
39-5 
39-5 
39-5 
39-6 
39-6 
General Investigations 
22. Surveys .............................. 
23. Collection and Study of Basic Data ...... 
24. Continuation of Planning and Engineering 
25. Advance Engineering and Design ........ 
Page 
39-7 
39-7 
39-8 
39-8 
39-8 
39-8 
Tables 
Table 39-A Cost & Financial Statement.... 39-9 
Table 39-B Authorizing Legislation ........ 39-11 
Table 39-C Other Authorized Navigation 
Projects ..................... 39-14 
Table 39-D Not Applicable .............. 
Table 39-E Other Authorized Flood Control 
Projects ..................... 39-14 
Table 39-F Not Applicable.............. 
Table 39-G Deauthorized Projects ......... 39-16 
Table 39-H Columbia River Basin, Local 
Flood Control Projects ......... 39-16 
Table 39-I Inspection of Completed Flood 
Control Projects .............. 39-17 
Table 39-J Principal Data Concerning 
Navigation Lock, Spillway Dam, 
Powerplant and Impoundment .. 39-18 
Table 39-K Snake River Downstream from 
Johnson Bar Landing, OR, WA 
and ID ...................... 39-22 
39-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Navigation 
1. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, 
Public Law 86-645 (preauthorization). 
Fiscal year costs were $364 for Port of Clarkston, WA 
reconnaissance report and $134,715 for Clearwater River, 
Lewiston, ID draft detail project report. 
Flood Control 
2. COLUMBIA RIVER BASIN, LOCAL FLOOD 
PROTECTION PROJECTS 
Location. Improvements included in this project are 
along Columbia River and its tributaries. 
Existing project. Flood Control Act of 1950 approved 
a general comprehensive plan for Columbia River Basin 
for flood control and other purposes based on plans in H. 
Doc. 531, 81st Cong., 2d Sess., and authorized $75 million 
to be appropriated for partial accomplishment of certain 
projects. Of that authorization, an amount not to exceed 
$15 million was allotted for construction of local flood protection 
works throughout Columbia River Basin, subject 
to conditions that all work undertaken pursuant to 
authorization should be economically justified prior to 
construction, and local cooperation specified in 1936 Flood 
Control Act, as amended, should be required. (See Tables 
39-B and 39-H for projects in Walla Walla District.) 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies. 
Operations during fiscal year. No projects were 
recommended for deauthorization during the fiscal year. 
3. CATHERINE CREEK, OR 
Location. Catherine Creek is a tributary to the Grande 
Ronde River located 8 miles east of the City of La Grande, 
Union County, OR. 
Existing project. Organic debris such as fallen trees, 
brush, and a select number of large cottonwood trees were 
removed from the creek to increase its capacity to convey 
future floods. The work was funded under authority of Section 
208 of the Flood Control Act of 1954. 
Local cooperation. The Catherine Creek Corridor Improvement 
District sponsored the project and complied 
with requirements as set forth in Section 3 of the Flood 
Control Act of 1936 plus additional requirements set forth 
in the project document. 
Operations during fiscal year. New work: Removal 
of debris was completed in FY 1986. 
4. CLEAR & BURNT RIVER, OR 
Location. At the City of Huntington waste water 
lagoon, Malheur County, Oregon. 
Existing project. Place 800 feet of rip rap along three 
cells of the lagoon system under authority of Section 14 
of the 1946 flood control act. 
Local Cooperation. City of Huntington sponsored the 
project and agreed to sponsorship requirements. 
Operations during fiscal year. New work: work was 
completed in FY 1986. 
5. COLFAX, PALOUSE RIVER, WA 
Location. On the main stem North and South Forks 
of the Palouse River and includes a portion of Spring Flat 
Creek, a tributary stream, all within the city of Colfax, 
WA. 
Existing project. Project consists of 3740 feet of concrete 
lined channel, 4910 feet of revetted channel, and 
2330 feet of unrevetted channel and drainage structures. 
Authorizing legislation was provided under PL 78-534, 
Section 10, Flood Control Act of 1944. 
Local cooperation. The city of Colfax has provided 
the necessary right of way and other sponsorship 
requirements. 
Operations during fiscal year. New work: A study 
was completed on the adequateness of the channel 
dewatering pump, and indicated excessive surface water 
from behind the retaining wall was entering the pumping 
system. Subsequently, the surface water has been 
diverted away from the pump and its capacity now appears 
to be adequate. 
6. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended. 
Fiscal year costs were $66,741 for preauthorization 
studies: $28,604, Oakley Westside Channel, ID; $32,138, 
Salmon River, Vicinity of Salmon, ID; $6,000, Squaw 
Creek, Bancroft, ID. 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th Congress, 
and antecedent legislation). 
Federal costs for fiscal year were $95,692 for disaster 
preparedness, $3,700 for emergency operations, $394,666 
for rehabilitation. 
Emergency Bank Protection (Section 14, 1946 
Flood Control Act, Public Law 526, 79th Congress) 
Fiscal year costs were $23,086 for preauthorization 
studies: $4,000, Big Wood River, Blane County, ID; 
$19,086 Pocatello Creek, Bannock County, ID. 
Snagging and clearing of navigable streams and 
tributaries in interest of flood control (Section 208, 
1954 Flood Control Act, Public Law 780, 83d 
Congress). 
Fiscal year costs were $15,500 for preauthorization 
studies: $7,500 Big Lost River, Butte County, ID; $3,000, 
Henry's Fork River, Freemont County, ID; $5,000, South 
Fork Teton River, Madison County, ID. 
7. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Federal law requires local interests to maintain and 
operate completed local protection projects in accordance 
with regulations prescribed by Secretary of Army. Inspections 
were made to determine extent of compliance and 
39-2

WALLA WALLA, WASHINGTON DISTRICT 
to advise local interests as necessary of measures required 
to correct deficiencies. A contract to investigate the 
geological and seismological conditions at Ririe Dam, ID 
continued through the fiscal year. See Table 39-I for inspections 
made during fiscal year. 
Fiscal year costs were $307,426. Total costs to 
September 30, 1986 have been $1,759,366. 
8. INSPECTION OF COMPLETED PL-99 WORKS 
Inspections are pursuant to Public Law 84-99 which 
directs the Corps to establish through inspection whether 
non-federal flood control works will continue to provide 
the intended degree of flood protection and to determine 
if the maintenance program is adequate. FY 1986 costs 
for this program were $59,822. 
9. LUCKY PEAK LAKE, ID 
Location. On Boise River in southwestern Idaho about 
10 miles southeast of city of Boise. 
Existing project. A rolled-earthfill dam about 250 feet 
high above streambed and 1,700 feet long at crest, with 
a lake providing a total storage at upper operating lake 
level of 306,000 acre-feet. (For further details see page 
2000 of Annual Report for 1962.) 
Construction of existing project was initiated November 
1949 and completed June 1961. A feasible method of 
achieving better flood control through diversion into New 
York Canal, through Lake Lowell, and into the Snake 
River has been developed but rejected by local interests 
due to the infrequent use of this diversion method. Since 
1961, $118,443,000 in potential flood damages have been 
prevented by the project. Final Environmental Impact 
Statement on the initial project was filed with the Council 
on Environmental Quality on November 29, 1976. A 
revised draft Environmental Impact Statement for the 
modification work was filed with the Council on Environmental 
Quality on September 18, 1978. 
During the detailed investigation of outlet capacity and 
the potential for adding hydropower to the existing project, 
a need for an auxiliary outlet became apparent. Construction 
of an auxiliary outlet was authorized in the 
Water Resource Development Act of 1976 but to date it 
has not been funded. In FY 1978, an "Interim Feasibility 
Report on Modification of Lucky Peak Dam and Lake" 
(power facilities) was submitted to the Board of Engineers 
for Rivers and Harbors and approved. States, agencies, and 
the Chief of Engineers have commented on the report to 
the Secretary of the Army. The report was forwarded to 
the Office of Management and Budget in February 1982. 
No further action has been taken. 
A license to construct and operate power facilities at 
the project was issued by the Federal Energy Regulatory 
Commission (Project #2832) to the Boise Project Board of 
Control on June 10, 1980 and modified on October 9, 1980 
and 1982. Construction of a power plant and new auxiliary 
outlet tunnel began in May 1984. The new auxiliary 
outlet tunnel modification to the existing outlet tunnel 
and new power plant were awarded in Fiscal Year 1986. 
Power on the line is scheduled for May 1988. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Installation 
of the steel liner on the flip lip section immediately 
downstream from the outlet control valve was completed in 
July of 1986. A contract to repair the discharge gate guides 
was initiated in FY 86. 
10. MILL CREEK LAKE, WA 
Location. In and upstream from Walla Walla, WA, on 
Mill Creek, a tributary of Walla Walla River. 
Existing project. Off-stream earthfill storage dam 
about 145 feet high and 3,200 feet long at the crest, two 
concrete-lined outlet channels, an earthfill diversion dam, 
and division structures. 
Authorizing legislation to provide a channel through 
the city of Walla Walla was added to the project in 1941. 
Federal cost of original project was $2,162,155. Adding 
recreation facilities has thus far increased project costs 
by $96,340 to $2,258,495. Not included in that cost is 
$80,000 contributed by local interests toward construction 
of the channel through Walla Walla. (For further details 
see page 2005 of Annual Report for 1962.) 
Construction of dam and appurtenant works was completed 
in 1942. Paving of channel through city of Walla 
Walla was completed in 1948. Park and recreation 
facilities were opened to the public July 1, 1964. Since 
1942, $5,424,000 in potential flood damages have been 
prevented by the combined storage and channel operation. 
Final Environmental Impact Statement was filed with the 
Council on Environmental Quality on December 12, 1975. 
The rehabilitation of the existing project is designed 
to correct the seepage and internal erosion which have 
occurred during each subsequent filling of the reservoir 
requiring limited flood control use of the project. 
Local cooperation. Fully complied with. For details 
see page 2006 of Annual Report for 1962. 
Operations during fiscal year. Major rehabilitation: 
continued on Phase I & II of the channel rehabilitation, 
which is the segment of channel from 9th Street to Gose 
Street and the Diversion Dam to Tausick Way. A contract 
for Phase III of the channel rehabilitation which extends 
from Tausick Way to Roosevelt street bridge was also 
awarded in FY 1986. 
Maintenance: Routine maintenance by Government 
forces continued, which included regulation of water control 
structures and care of recreation areas. 
11. OWYHEE RIVER, OR 
Location. The lower 12 miles of the Owyhee River from 
the junction with the Snake River, upstream 23 miles to 
the Owyhee River diversion dam, Malheur County, OR. 
Existing project. Remove organic debris and gravels 
from the lower 12 miles of the Owyhee River under the 
authority of Section 208 of the 1954 Flood Control Act. 
Local cooperation. The Owyhee River Water Control 
District sponsored the project and agreed to sponsorship 
requirements. 
Operations during fiscal year. Work was completed 
in FY 1986. 
39-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
12. SCHEDULING FLOOD CONTROL RESERVOIR public opposition. Units 4, 5, and 6 are now classified 
OPERATIONS "inactive". 
Functional regulation of non-Corps projects was accomplished 
under several authorities. Regulations of 
Palisades, Little Wood, and Anderson Ranch Reservoirs 
in Idaho, and Bully Creek, Warm Springs, Agency Valley, 
and Mason Reservoirs in Oregon, was accomplished as 
authorized under Section 7, Flood Control Act of 1944, and 
coordinated with the Bureau of Reclamation. 
Flood control operations at Jackson Lake, Arrowrock 
Reservoir, and Lake Lowell were in accordance with formal 
agreements with the Bureau of Reclamation. Regulation 
of American Falls, Owyhee, Magic, Mackay, Cascade, 
and Deadwood Reservoirs, Idaho, for flood control was accomplished 
under informal agreements. Brownlee, Oxbow, 
and Hells Canyon Reservoirs provided flood control regulation 
in accordance with provisions of the Federal Power 
Commission license to Idaho Power Company. 
Fiscal year costs were $252,987. 
Multiple-Purpose Projects, 
Including Power 
13. DWORSHAK DAM AND RESERVOIR, ID 
Location. Dam is on North Fork Clearwater River 1.9 
miles above its junction with Clearwater River, near 
Orofino, ID, and about 35 miles east of Lewiston, ID. 
Existing project. A straight concrete gravity dam 
about 717 feet in maximum structural height above foundation 
and 3,300 feet long at crest Elevation 1613. The 
reservoir has a gross storage capacity of 3,453,000 acrefeet, 
of which 2,000,000 acre-feet are effective for both local 
and regional flood control, and for at-site and downstream 
power generation. In addition, the reservoir, extending 53 
miles into a Iagged and relatively inaccessible 
timberland, provides important transportation savings in 
connection with movements of marketable logs. The project 
also provides substantial recreation benefits. 
Powerhouse includes two 90,000 and one 220,000 kilowatt 
generating units, with provisions for three additional 
220,000 kilowatt units for an ultimate installed capacity 
of 1,060,000 kilowatts. Principal project data are set forth 
in Table 39-J. 
Fish passage at Dworshak Dam is not feasible due to 
the height of the dam and a hatchery has been built below 
the dam to assure continuance of anadromous fish runs. 
The reservoir area has been habitat for elk, deer, and other 
wildlife. Project plans include acquisition of land outside 
reservoir limits to mitigate losses of big game winter 
browse areas inundated by reservoir. 
Construction of the project started April 1963 and was 
completed in 1986. Since the project became operational 
in June of 1972 it has prevented about $737,000 of potential 
flood damage. A reconnaissance report justifying the 
feasibility and cost benefits for the addition of a 
220,000-kilowatt fourth generating unit was completed 
in FY 1978. Environmental and economic studies on additional 
generating units have been curtailed due to 
Power generating Unit No. 1, 90,000-kilowatt capacity, 
was put in service March 1, 1973; Unit No. 2, also 
90,000-kilowatt capacity, began producing April 6, 1973; 
Unit No. 3, 220,000-kilowatt capacity, went on the line 
April 20, 1973. Power generation through September 1986 
has been 24.37 billion kilowatt hours. 
Eighty mini-recreation sites have been established 
along the reservoir shoreline. Each site includes at least 
a picnic table, U.S. Forest Service-type fireplace, and 
chemical toilet. Some of the sites have several picnic 
tables. 
Dent Acres and Freeman Creek recreation sites are 
open to the public. Facilities consist of a boat launching 
ramp, boat docks, car-trailer parking, comfort stations, and 
fully developed overnight camping at each site. 
Local cooperation. None required. 
Operations during fiscal year. New work: Wildlife 
habitat browse development continued on project lands to 
provide winter browse for elk and deer. Contracts for the 
Energy Recovery Contract at the Dworshak Hatchery, 
Three Meadows Group Camp, Freeman Creek Road slide 
repair, electrical service to Three Meadows Group Camp 
were completed. Contracts for paving of the parking lot 
at the hatchery and Merry Bay road repair were also 
completed. 
Maintenance: Normal operations and maintenance 
continued. Hatchery operations continue to be impaired 
by IHN virus. Steelhead eggs have been transfered to 
Kooskia National Fish Hatchery for incubation and early 
rearing of fry to a point past their normal period of 
susceptability. In spring of 1986, 2,900,000 steelhead 
smolts weighing approximately 400,000 pounds were 
released. A return of 8,000 to 10,000 adults is expected 
in 1986. In addition to steelhead, the hatchery also released 
800,000 spring chinook smolts (40,000 pounds) and 
160,000 rainbow trout (10,000 pounds). Rainbow trout production 
is also hindered by the IHN virus and fish were 
acquired from Hagerman Hatchery. 
14. ICE HARBOR LOCK AND DAM-LAKE 
SACAJAWEA, WA 
Location. On Snake River, 9.7 miles above river mouth 
at head of Lake Wallula and 12 miles east of Pasco, WA. 
Existing project. The project includes a dam, 
powerplant, navigation lock, fish ladders, appurtenant 
facilities, and relocation of railroads. Project provides for 
navigation, hydroelectric power generation, recreation, 
and incidental irrigation. Reservoir has normal operating 
range between Elevations 440 and 437 mean sea level, 
and extends upstream about 31.9 miles, providing slack 
water to Lower Monumental Lock and Dam. Structure is 
about 2,790 feet long and about 130 feet high above 
streambed. 
Beginning at south end, project consists of a concrete 
nonoverflow section, concrete powerhouse, spillway dam, 
navigation lock, and an earth and rockfill embankment 
at north abutment. Fish passing facilities, including two 
39-4

WALLA WALLA, WASHINGTON DISTRICT 
90,000-kilowatt units and three 111,000-kilowatt units in 
operation. Spillway dam is 610 feet long, and overflow 
crest at Elevation 391 mean sea level is surmounted by 10 
radial gates, 50 feet wide by 51 feet high, which provide 
the capacity to pass a design flood of 850,000 cubic feet 
per second. Deck is at Elevation 453 mean sea level and 
provides a service road and track for a gantry crane. 
Navigation lock is single-lift type with clear plan dimensions 
of 86 by 675 feet and 15-foot minimum depth over 
the sills. A navigation channel 250 feet wide and 14 feet 
deep is provided from the mouth of the Snake River to 
the dam. Principal project data are set forth in Table 39-J. 
Construction started December 1955 and the project 
was placed in useful operation January 1962. The project 
is complete. 
An Environmental Impact Statement concerning power 
units 4 through 6 was filed with the Council on Environmental 
Quality August 1971. 
Power generation through September 1986 has been 
56.02 billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Normal 
operation and maintenance continued. Work was completed 
for the painting of spillway gates and gate seal 
heaters, fish viewing window cleaner, installation of guide 
wall anchor cables and piling installation. 2.66 billion 
kilowatt hours of electric energy were delivered to Bonneville 
Power Administration, the marketing agency. A 
total of 2,708,866 tons of cargo passed through the navigation 
lock during calendar year 1985. 
15. LEWISTON-CLARKSTON BRIDGE, ID AND WA 
Location. On the Snake River, River Mile 141.3, 1.7 
miles upstream of the existing interstate bridge connecting 
the towns of Lewiston, ID and Clarkston, WA. 
Existing project. The project consists of a new fixed 
high-level four lane highway bridge and approaches on 
U.S. Highway 12 across the Snake River constructed at 
a cost "not to exceed $21,000,000". In December 1981 Congress 
authorized an additional expenditure of $2,200,000 
for construction of Lewiston's North Ramp. An approach 
roadway from the bridge to 16th Avenue in Clarkston, WA 
was authorized in July 1983 at an additional expenditure 
of $800,000. 
Final Environmental Impact Statement Supplement 
was filed with the Council on Environmental Quality on 
July 16, 1979. 
Local cooperation. Non-Federal interests have provided 
without cost to the United States all lands, 
easements, and rights-of-way necessary for the construction 
of the bridge and its approaches, and after construction 
have agreed to own, operate toll free, and maintain 
the bridge and approach facilities. The non-Federal costs 
for land and relocation are $755,193. 
Operations during fiscal year. New work: Completion 
of as built drawings. 
16. LITTLE GOOSE LOCK AND DAM-LAKE 
BRYAN, WA 
Location. Dam is 70.3 miles above mouth of Snake 
River at head of Lower Monumental Lake, about 40 
airline miles northerly of Walla Walla, WA, and 50 miles 
westerly of Lewiston, ID. 
Existing project. The project includes a dam, 
powerplant, navigation lock, fish ladder, and appurtenant 
facilities. Improvements provide navigation, hydroelectric 
power generation, recreation, and incidental irrigation. 
The reservoir has a normal operating range between 
Elevations 638 and 633 mean sea level. Lake Bryan extends 
upstream about 37.2 miles and provides slack water 
to Lower Granite Lock and Dam. Dam structure is 2,670 
feet long and about 160 feet high above streambed and 
consists of a powerhouse, spillway dam, navigation lock, 
and necessary nonoverflow sections. Fish passage facilities 
include one ladder with entrances on both shores with a 
fish channel through the spillway which connects to the 
powerhouse fish collection system and south shore ladder. 
Powerhouse now has six 135,000-kilowatt generating 
units for a capacity of 810,000 kilowatts. Spillway dam 
can pass a design flood of 850,000 cubic feet per second. 
Navigation lock is single-lift type with clear plan dimensions 
of 86 by 675 feet and a minimum depth of 15 feet 
over the sills. Relocations along the lake include 32 miles 
of Camas Prairie Railroad, 5.8 miles of county roads, 2.2 
miles of state highways, and Central Ferry bridge. Principal 
project data are set forth in Table 39-J. 
A final Environmental Impact Statement was filed 
with the Council on Environmental Quality on January 
8, 1975. 
Power generation through September 1986 has been 
43.24 billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Normal 
operation and maintenance continued. A total of 3.37 
billion kilowatt hours of electric energy was delivered to 
Bonneville Power Administration, the marketing agency. 
Work continued on reconditioning of spillway gates and 
fish viewing window washers were installed. 
Work is continuing on the design memorandum for a 
permanent juvenile fish facility. 
A total of 2,224,584 tons of cargo passed through the 
navigation lock during calendar year 1985. 
17. LOWER GRANITE LOCK AND DAM, WA 
Location. At River Mile 107.5 on Snake River at head 
of Lake Bryan and about 33 miles downstream from 
Lewiston, ID. 
Existing project. The facility includes a dam, 
powerplant, navigation lock, fish ladder, and appurtenant 
facilities, and requires about 8 miles of backwater levees 
along Snake and Clearwater Rivers at Lewiston, ID. 
Benefits afforded by project include slack-water navigation, 
power generation, recreation, and incidental irrigation. 
Water surface at the dam varies between Elevations 
738 and 724 to maintain a normal operating range 
39-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
between Elevations 738 and 733 in the Lewiston, IDClarkston, 
WA area. Dam structure is about 3,200 feet 
long and about 146 feet high above streambed. 
Powerhouse now has six 135,000-kilowatt units. Spillway 
has a capacity for a design flood of 850,000 cubic feet per 
second. Navigation lock is a single-lift type (105 feet maximum) 
with clear plan dimensions of 86 by 675 feet and 
a minimum depth of 15 feet over the sills. Principal project 
data are set forth in Table 39-J. 
Construction started July 1965 and is complete. Acquisition 
of lands is also complete. Lake was filled 
February 15, 1975 and the first power generating unit 
went on the line April 15, 1975. Approximately 
$4,119,300 in potential flood damage has been prevented 
since the levees became functional. An Environmental Impact 
Statement was filed with the Council on Environmental 
Quality November 1971. A revised statement 
to include the additional units was filed with the Council 
on Environmental Quality on July 23, 1975. 
Power generation through September 1986 has been 
34.16 billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Normal 
operation and maintenance continued. Contracts completed 
were fish viewing window cleaner, Lewiston Levee 
improvements, paving parking lot at Chief Timothy Park, 
modifications to Hell;s Gate Park, miscellaneous piling 
installation and Dredging at the Confluence of Snake & 
Clearwater Rivers. 
As the first juvenile fish collection point on the Snake 
River, Lower Granite is a primary component in the 
District's fish collection and transport program. This program 
was begun because construction of eight dams on 
the Columbia and Snake Rivers has had a significant 
impact on the survival during downstream migration of 
juvenile anadromous fish such as salmon and steelhead 
trout. Since the early 1960's, efforts to mitigate the 
adverse impacts have included extensive research, structural 
modifications of the dams, installation of turbine 
screening systems, and implementation of a system for 
collecting and transporting juvenile fish. 
The Walla Walla District operates the fish collection 
and transportation program for the Columbia-Snake 
system. Three primary collection points have been 
established at Lower Granite, Little Goose and McNary 
dams, with fish sorting and handling facilities. Fingerlings 
collected at these facilities are taken by specially 
designed barges and trucks to an area downstream of Bonneville 
Dam and released to make the rest of their journey 
to the sea. In 1986 a total of 13,563,000 juvenile fish were 
transported and 14,787,592 fingerlings were transported. 
Increased hatchery production has resulted in increased 
numbers of fish to be transported. 
A total of 3.38 billion kilowatt hours of electric energy 
were delivered to Bonneville Power Administration, the 
marketing agency. A total of 1,557,299 tons of cargo passed 
through the navigation lock during calendar year 1985. 
18. LOWER MONUMENTAL LOCK AND DAMLAKE 
HERBERT G. WEST, WA 
Location. On Snake River at head of Lake Sacajawea, 
about 45 miles northeast of Pasco, WA, and 41.6 miles 
above river mouth. 
Existing project. The facility includes a dam, 
powerplant, fish ladders, navigation lock, appurtenant 
facilities, and relocated railroads and highways. The project 
functions include navigation, hydroelectric power 
generation, recreation and irrigation. Reservoir has normal 
operating range between Elevations 540 and 537. The 
lake extends about 28.7 miles upstream to Little Goose 
Lock and Dam. The dam is concrete gravity type with 
earthfill and rockfill abutments. It is 3,800 feet long including 
abutments, spillway, navigation lock, and 
powerhouse, and is about 135 feet high above streambed. 
There are two fish ladders, one at each end of the dam. 
Powerhouse has six 135,000-kilowatt units for a total 
capacity of 810,000 kilowatts. Spillway is 508 feet long, 
and overflow crest at Elevation 483 feet above mean sea 
level is surmounted by 8 radial gates, each 50 feet wide 
and 61 feet high. Deck is at Elevation 553 feet and provides 
a service road and track for a gantry crane. Navigation 
lock is single-lift type, with lock chamber 86 by 675 
feet and minimum depth of 15 feet over the sills. Principal 
project data are set forth in Table 39-J. 
Construction began June 1961, and the project was 
opened to navigation April 1969. The project is complete. 
A final Environmental Impact Statement was filed 
with the Council on Environmental Quality on May 21, 
1976. 
Power generation through September 1986 has been 
47.00 billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Normal 
operation and maintenance continued. Contracts completed 
were: Installation of guide wall anchor cables, 
repair of heat pump, generator thrust bearing repair, fish 
viewing window cleaner, miscellaneous piling installation 
and vertical barrier screen guide installation. A total of 
2.77 billion kilowatt hours of electric energy was delivered 
to Bonneville Power Administration, the marketing agency. 
Cargoes totaling 2,350,789 tons passed through the 
navigation lock during calendar year 1985. 
19. LOWER SNAKE RIVER FISH & WILDLIFE 
COMPENSATION PLAN, WA, OR, ID 
Location. At various locations within the Columbia 
Snake River drainage in the States of Idaho, Oregon and 
Washington. 
Existing project. The project will consist of a series 
of fish hatcheries and wildlife development areas at sites 
to be selected. The project will compensate for loss of 
wildlife habitat and anadromous and resident fishery inundated 
as a result of construction of four multiple purpose 
dams and reservoirs on the Lower Snake River (Ice 
Harbor, Lower Monumental, Little Goose, Lower Granite). 
In 1980 the first release from the McCall, ID summer 
chinook hatchery was made, and the adult trapping facility 
39-6

WALLA WALLA, WASHINGTON DISTRICT 
which provides the fish egg supply for the McCall 
Hatchery became operational. 
The real estate design memorandum, and feature 
design memorandums on the McCall Hatchery, Hagerman 
Hatchery, Lookingglass Hatchery, Lyons Ferry Hatchery, 
Dworshak Hatchery Expansion, Irrigon Hatchery, 
Magic Valley Hatchery, Sawtooth Hatchery, East Fork 
Salmon River Satellite Facility, the off-project wildlife 
lands, and the site selection report have all been approved. 
A final Environmental Impact Statement was filed 
with Council on Environmental Quality on November 2, 
1977. The Dworshak National Fish Hatchery, the Irrigon 
and Wallow Sattelite Hatcheries, Hagerman Hatchery, 
Lyons Ferry Hatchery, Lookingglass Hatchery, McCall 
Hatchery, Sawtooth Hatchery are in operation. The compensation 
plan is 67 percent complete. 
Estimated Federal cost of the project is $177,000,000. 
Local cooperation. None required. 
Operations during fiscal year. New work: Construction 
contracts were awarded for: Magic Valley Hatchery 
and Spring Water Collection system, Big Canyon Hatchery, 
Hagerman Hatchery completions, Lyons Ferry Hatchery 
completions, Tucannon Hatchery completion, Red 
River Sattelite Hatchery, Dayton Hatchery Ponds and 
Irrigon landscaping. The final hatchery site has been 
selected at Ahsahka, Idaho, for the Clearwater River 
basin. This hatchery will rear both spring chinook and 
steelhead. Red River-Crooked River & Powell hatcheries 
have been identified as satellite sites for the Clearwater 
Hatchery. 
20. McNARY LOCK AND DAM-LAKE WALLULA, 
OR AND WA 
Location. On Columbia River 292 miles above mouth, 
near Umatilla, OR, and 3 miles above mouth of Umatilla 
River. 
Existing project. Includes a concrete dam 7,300 feet 
long overall and 183 feet high above streambed, 
powerplant with 14 power generating units, navigation 
lock, fishways, levees and pumping plants, incidental irrigation, 
and modification and relocation of railroad 
bridges over the Columbia and Snake Rivers in order to 
eliminate hazards to navigation. Principal project data are 
set forth in Table 39-J. 
Construction started May 1947 and is complete. Project 
placed on permanent operating basis and lake raised 
to Elevation 340 in November 1953. Except for 
maintenance interruptions, all 14 power units have been 
in commercial operation since February 1957. 
A final Environmental Impact Statement was filed 
with Council on Environmental Quality in June 1976. 
Power generation through September 1986 has been 
197.39 billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Normal 
operation and maintenance of project continued. The 
modernization program is basically completed. Contracts 
initiated were roof repairs for the powerhouse, repair to 
excitation equipment, stator replacement for unit 14 and 
purchase of fish pump transformer. Contracts completed 
were fish viewing window cleaners, realignment of beach 
entrance road, painting of intake crane, paving of public 
use areas, and dredging below Ice Harbor Dam. Approximately 
6.96 billion kilowatt hours of electric energy were 
delivered to Bonneville Power Administration, the 
marketing agency. A total of 5,338,751 tons of commodities 
passed through the navigation lock during calendar 
year 1985. 
21. SNAKE RIVER DOWNSTREAM FROM 
JOHNSON BAR LANDING, OR, WA, AND ID 
Location. On Snake River downstream from Johnson 
Bar Landing, River Mile 230. Snake River, which is 
largest tributary of Columbia River, rises in Yellowstone 
National Park in western part of Wyoming, flows generally 
westerly for about 1,000 miles, and empties into Columbia 
River near Pasco, WA, 324 miles from Pacific 
Ocean. 
Existing project. The River and Harbor Act of 1945 
authorized construction of dams as necessary and open 
channel improvements for purposes of providing slackwater 
navigation and irrigation between mouth of Snake 
River and Lewiston, ID. That authorization modified 
previous authorizations only for that portion of improvement 
below Lewiston, ID. Acts of June 13, 1902, and 
August 30, 1935, as they pertain to open river improvement 
from Lewiston, ID, to Johnson Bar Landing, remain 
part of existing project. 
Improvements included in existing project are Ice Harbor 
Lock and Dam-Lake Sacajawea; Little Goose Lock 
and Dam-Lake Bryan; Lower Granite Lock and Dam; 
Lower Monumental Lock and Dam-Lake Herbert G. 
West; and open-river improvement, Lewiston to Johnson 
Bar Landing. Each of the four locks and dams is described 
in an individual report, and cost and financial data for 
the entire project are shown on Tables 39-A and 39-K. 
Ice Harbor, Lower Monumental, Little Goose and Lower 
Granite are in full operation. (See individual reports for 
details.) (For further details see Annual Reports, page 
2246 for 1903; page 1986 for 1906; page 1991 for 1915; 
and page 1981 for 1962.) 
Local cooperation. None required. 
Terminal facilities. On Snake River from the mouth 
to Johnson Bar Landing there are 18 privately owned 
barge terminals in use for shipping grain, petroleum products, 
fertilizers, cement, and other general cargo. There 
are also 5 marinas and 28 small-boat launching ramps, 
all open to public use. The facilities serve slack-water 
navigation to Snake River Mile 140, the site of Lewiston, 
ID. That slack-water reaches the Lewiston, ID-Clarkston, 
WA area since the lake behind Lower Granite Dam was 
filled in February 1975. 
Operations during fiscal year. See individual reports 
for Ice Harbor, Lower Monumental, Little Goose, and 
Lower Granite locks and dams. On Snake River from 
Lewiston, ID, to Johnson Bar Landing, reconnaissance 
39-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
and condition surveys were conducted and survey markers 
were maintained. 
General Investigations 
22. SURVEYS 
The Upper Snake River and Tributaries is the principal 
ongoing survey. The area covered by the study extends 
from the headwaters of the Snake River in Wyoming down 
to and including the Weiser River in Idaho. The potential 
for supplemental water storage, power generation, and 
streamflow augmentation to enhance fisheries, continues 
to be the primary focus. 
A survey study of the Mill Creek Basin continued in 
FY 1986. Mill Creek originates in the Blue Mountains 
in northern Oregon and southern Washington, and is 
tributary to the Walla Walla River. Water resource problems 
and needs being investigated include municipal and 
industrial water supply, power generation, fish enhancement, 
flood control, and irrigation. 
The Columbia River and Tributaries is a survey study 
directed by the North Pacific Division in which the Walla 
Walla District is participating. A major activity of the 
CR&T study in FY 1986 was the Regional Hydropower 
Assessment being performed in coordination with the 
Northwest Power Planning Council. Other work on the 
CR&T study involved preparation of basin summary 
reports, development of flood control operational information, 
and continued work on the John Day and Clearwater 
River Basin interim study. 
A survey study is underway that is investigating the 
flooding problems associated with the rising water levels 
of Malheur Lake in Harney County, Oregon. Five consecutive 
years of above normal runoff from the basin have 
raised the level of this closed basin lake above any 
historical record and caused great economic and social impacts 
on Harney County. Alternatives being investigated 
include a canal from Malheur Lake that would discharge 
lake water into the South Fork of the Malheur River, 
relocations of transportation facilities and land exchange 
and/or buy out of private lands. 
Total cost of surveys during fiscal year was $1,349,627. 
That sum was expended for: flood control studies, 
$1,201,692; special studies including Soil Conservation 
Service, Bureau of Reclamation, River Basin and Regional 
Planning Commissions, Cooperation with States, $35,285; 
and Special Investigations and FERC Licensing Activities, 
$112,650. 
23. COLLECTION AND STUDY OF BASIC DATA 
During the fiscal year flood hazard data for a number 
of locations in the District were collected and analyzed. 
Flood information was provided to several Federal agencies, 
to the States of Idaho, Oregon, and Washington, to 
various cities and counties in those states, and to some 
private organizations. 
Total cost of collection and study of basic data during 
fiscal year was $112,940 which was expended for flood 
plain management services, $59,398; and technical services, 
$53,542. 
24. CONTINUATION OF PLANNING AND 
ENGINEERING 
McNary Lock and Dam (Second Powerhouse), OR 
and WA 
McNary Second Powerhouse is a proposed addition on 
the south shore of McNary Lock and Dam on the Columbia 
River near Umatilla, OR. The project will increase the 
present 1127 megawatt generating capacity by an additional 
742 megawatts. Provisions are included for compensation 
of negative impacts on fish and wildlife. The project 
is estimated to cost $660,000,000 at October 1, 1985 
price levels. 
The General Design Memorandum Phase I was 
prepared under the Water Resource Development Act of 
1976, Public Law 94-587, and submitted to the Secretary 
of the Army on July 1, 1981. 
Studies were initiated in FY 1982 and continued 
through FY 1984 on the General Design Memorandum 
Phase II and the Powerhouse Preliminary Design Report. 
1986 expenditures were $19,506 spent on hydraulic model 
study by Waterway Experiment Station in Vicksburg, MS. 
25. ADVANCE ENGINEERING AND DESIGN 
Zintel Canyon Dam, WA 
The proposed project consists of a roller compacted concrete 
dam 102 feet high with uncontrolled spillway and 
a fixed maximum release outlet works that would create 
a detention reservoir of 2,500 acre-feet of capacity. The 
storage comprises 2,100 acre-feet for flood control and 400 
acre-feet for sediment. In addition, the project also includes 
a channel with a capacity of 400 cfs. The plan of 
improvement would provide protection against heavy 
rainfall, snowmelt, and thunderstorm floods to the city 
of Kennewick, WA. Estimated Federal project cost is 
$4,800,000. 
Reevaluation of the project was initiated to review 
economic feasibility with fiscal year costs of $385. 
39-8

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 39-A COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
3. Catherine Creek, OR New Work 
4. Clear & Burnt 
River, OR 
5. Colfax, Palouse 
River, ID 
9. Lucky Peak Lake, 
ID 
10. Mill Creek Lake, 
WA 
11. Owyhee River, OR 
13. Dworshak Dam and 
Reservoir, ID 
14. Ice Harbor Lock 
and Dam, WA 
15. Lewiston-Clarkston 
Bridge, ID & WA 
16. Little Goose Lock 
and Dam, WA 
17. Lower Granite Lock 
and Dam, WA 
18. Lower Monumental 
Lock and Dam, 
WA 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
- 185,000 
- 107,968 
- 71,400 
698,800 839,000 
740,442 654,651 
299,044 
298,254 
1,596,734 
1,594,699 
27,894 
27,894 
317,200 
302,422 
1,775,000 
1,710,362 
38,000 
15,603 
68,000 
131,581 
12,932 
88,500 
63,974 
38,000 
28,535 
88,500 
63,974 
- 5,810,240 
11,215 5,808,004 
71,400 - 19,652-0811 
- - 19,652,0811 
1,211,650 1,101,999 10,205,853 
1,358,698 1,136,570 10,197,214 
302,500 
309,107 
2,281,043 
2,346,813 
7,500 
7,500 
1,630,000 
1,634,122 
3,750,922 
4,515,463 
-2,299 
-3,290 
4,800,141 
4,869,452 
3,081,100 
3,052,306 
4,527,800 
4,478,567 
200,106 
200,106 
4,004,900 
3,969,635 
692,664 640,000 
693,216 486,402 
- 2,258,4952 
- 2,258,4952 
616,000 6,517,893 
613,230 6,503,285 
2,517,000 17,795,607 
2,517,177 17,794,485 
68,000 
35,014 
3,983,000 
3,487,491 
5,481,000 
5,369,881 
49,004 
50,004 
4,168,629 
3,875,053 
80,000 
227,516 
- 1,000,500 55,995 
11 1,000,036 
4,904,122 5,436,056 4,338,143 
4,868,523 5,292,141 3,998,368 
2,052,181 
2,047,995 
5,896,535 
5,776,641 
-906 
394,800 
396,804 
5,249,400 
5,263,880 
-2,600 
-1,706 
50,000 
559,901 
5,446,000 
5,499,554 
75,500 
42,514 
329,523,2963 
329,507,9583 
48,587,7874 
48,442,0054 
- 167,240,7575 
- 167,240,7575 
4,868,671 50,242,7746 
5,183,795 50,205,2706 
- 22,957,664 
6,210 22,957,664 
56,460 
3,921,401 
4,442,150 
221,355,0227 
221,355 022' 
39,430,7958 
39,331,1688 
74,689 - 367,780,3159 
84,600 - 367,780,3128 
5,706,000 8,890,205 45,084,50210 
5,594,704 9,053,763 44,939,03810 
18,121 
18,141 
- 236,373,73211 
- 236,373,73211 
39-9

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-A COST AND FINANCIAL STATEMENT 
(Continued) 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
Maint. 
Approp. 3,677,483 4,300,500 3,220,629 4,037,830 34,785,23212 
Cost 3,691,797 3,390,678 3,819,029 4,322,908 34,717,30412 
19. Lower Snake Fish & New Work 
Wildlife Compensa- Approp. 19,656,180 25,225,000 13,235,129 14,971,000 119,136,909 
tion, ID, OR & WA Cost 19,706,580 25,024,768 12,989,270 15,096,848 118,806,292 
(Contributed Funds) New Work 
Contrib. - - 223,965 - 223,965 
Cost - - 223,965 - 223,965 
20. McNary Lock & New Work 
Dam-Lake Wallula, Approp. 439,000 202,600 19,019 - 322,515,105 '3 
OR & WA Cost 479,320 203,380 19,242 - 322,515,105 '3 
Maint. 
Approp. 10,317,455 14,767,500 13,147,025 9,977,999 127,341,03514 
Cost 11,024,478 12,505,395 13,859,268 11,305,733 127,071,07614 
(Contributed Funds) Maint. 
Contrib. - - 43,707 - 43,707 
Cost - - - 43,707 43,707 
21. Snake River Down- New Work 
stream from John- Approp. 2,049,882 1,592,806 197,809 - 993,184,58915 
son Bar Landing, Cost 2,043,810 1,595,240 209,206 - 993,184,58715 
OR, WA & ID Maint. 
Approp. 19,311,281 18,990,856 17,455,401 21,725,107 170,112,82616 
Cost 19,254,422 17,916,334 17,305,877 23,008,630 169,757,65716 
'Includes $570,831 appropriated and expended for Code 710, 
Recreation Facilities at Completed Projects. 
2Excludes $80,000 contributed funds, but includes $96,340 
appropriated and expended for Code 710, Recreation Facilities 
at Completed Projects. 
3Includes $2,046,100 regular project construction funds appropriated 
for and expended by Department of Interior in Fiscal 
Years 1969 through 1972 for hatchery operations. Includes 
$655,000 appropriated and expended for additional unit. 
4Includes $14,337,680 regular project operation and 
maintenance funds expended by Department of Interior starting 
FY 1972 for hatchery operations. FY 72-78 funds of 
$6,097,000 were charged to the project as a cost, but not as an 
expenditure for accounting purposes. Includes $59,996 allotted 
and expended under Special Recreation Use Fees. Includes 
$75,400 allotted and expended under Maintenance and Operation 
of Dams and Other Improvements of Navigable Waters. 
5Excludes $82,500 contributed for artificial spawning channel. 
Includes $36,748,021 appropriated and expended for additional 
units 4 through 6. Includes $914,256 appropriated and 
expended for Code 710, Recreation Facilities at Completed 
Projects. 
6Includes $71,507 allotted and expended under Special 
Recreation Use Fees; $641,063 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
'Includes $60,941,807 appropriated and expended for additional 
units 4 through 6. 
8Includes $621,063 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
9Includes $46,212,534 appropriated and expended for additional 
units 4 through 6. Excludes $405,819 contributed funds 
on lock and dam project. Includes $63,800 appropriated and expended 
for Code 710, Recreation Facilities at Completed Projects. 
'oIncludes $338,163 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
"Includes $51,661,371 appropriated and expended for additional 
units 4 through 6. 
"Includes $372,376 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
'3Includes $1,976,586 appropriated and expended for Code 
710, Recreation Facilities at Completed Projects. 
'4Includes $125,258 allotted and expended under Special 
Recreation Use Fees and $1,035,860 allotted and expended 
under Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
1"Includes $400,150 for new work on previous projects (Pasco 
to Lewiston), and $34,613 for new work appropriation used for 
maintenance prior to 1953. Excludes $167,500 contributed funds 
for new work consisting of $82,500 for new work on existing projects 
(Pasco to Riparia), plus $82,500 for new work on existing 
artificial spawning channel. 
i"Includes $186,570 appropriated and expended for 
maintenance on previous projects (Pasco to Lewiston) and 
$375,953 appropriated and $372,293 expended open river Pasco 
to Lewiston and Lewiston to Johnson Bar Landing. 
39-10

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 39-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Sep. 24, 1954 
as amended 
July 24, 1946 
Dec. 22, 1944 
July 24, 1946 
Oct. 22, 1976 
Dec. 22, 1944 
as amended 
June 28, 1938 
Aug. 18, 1941 
2. 
May 17, 1950 
39-11 
COLUMBIA RIVER BASIN, LOCAL FLOOD 
PROTECTION PROJECTS 
Blackfoot Area, Snake River, ID. Levee left bank 
Blackfoot River, ID. Levees, channel improvement, 
and rectification works. 
Boise Valley, Boise River, ID. Channel improvement 
and enlargement, levees, and revetments in Ada 
County. Canyon County unit was deauthorized 
April 18, 1967. 
Grande Ronde Valley, OR. Levees and channel 
clearing, straightening, and realignment; would 
complement stream regulation by upstream storage 
projects. 
Heise-Roberts Extension, Snake River, ID. Channel 
clearing and rectification, levees, and bank 
protection. 
Kendrick, Potlatch River, ID. Revetted levee. 
Malheur River, OR. Channel rectification, levees, and 
bank protection at Vale. Willow Creek unit was 
deauthorized October 14, 1969. 
Palouse River, WA. Flood protection for urban and 
rural areas at Garfield and near Malden. 
Payette Valley, ID. Channel rectification, levees, and 
bank protection along 38 miles of Payette River 
below Black Canyon Dam. Payette Valley was 
deauthorized October 3, 1978. 
Portneuf River and Marsh Creek, ID. Concrete-lined 
channel through Pocatello. Inkom-Marsh Creek unit 
was deauthorized October 14, 1969. 
Shelley Area, Snake River, ID. Bank protection 
Weiser River, Weiser Area, ID. Intermittent channel 
realignment and improvement, levees, and bank 
protection, lower river area. 
CATHERINE CREEK, OR 
Organic debris removal 
along Catherine Creek 
CLEAR & BURNT RIVER, OR 
Construction of riprap bank protection at City of 
Huntington waste water lagoon. 
COLFAX, PALOUSE RIVER, WA 
Provides for flood control works in vicinity of and 
through Colfax, WA, by channel enlargement and 
modification, levees, floodwalls, revetments, and 
modification of railroad bridges 
LUCKY PEAK LAKE, ID 
Dam for flood control, irrigation, and recreation. 
Second outlet for streamflow maintenance. 
Construction, operation, and maintenance of 
recreation facilities. 
MILL CREEK LAKE, WALLA WALLA, WA 
Off-stream storage project upstream from Walla 
Walla. 
Channel improvement through Walla Walla; 
concrete lined channel. 
H. Doc. 531, 81st 
Cong., 2nd Sess. 
Sec. 208, P.L. 83-780 
Authorized by Chief 
of Engineers 
Sep. 3, 1985 
Sec. 14, P.L. 79-526 
Authorized by Chief of 
Engineers July 10, 1986 
Flood Control Act 
of 1944 
H. Doc. 888, 77th 
Cong., 2nd Sess. 
P.L. 79-526, Chief of 
Engineers Report 
dated May 13, 1946 
P.L. 94-587 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 578, 75th 
Cong., 3d Sess. 
H. Doc. 719, 76th 
Cong., 1st Sess. 
3. 
4. 
5.

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Sep. 24, 1954 
as amended 
July 3, 1958 
Oct. 23, 1962 
Aug. 15, 1963 
Mar. 2, 1945 
Dec. 22, 1944 
as amended 
Oct. 22, 1976 
Dec. 29, 1981 
July 30, 1983 
Mar. 2, 1945 
Dec. 31, 1970 
Mar. 2, 1945 
Mar. 2, 1945 
May 25, 1978 
Oct. 22, 1976 
Mar. 2, 1945 
Dec. 22, 1944 
as amended 
June 13, 1902 
June 25, 1910 
10. 
12. 
39-12 
OWYHEE RIVER, OR 
Gravel, brush and small tree removal from lower 
12 miles of Owyhee River 
(BRUCES EDDY) DWORSHAK DAM AND 
RESERVOIR, ID 
Preparation of detailed plans. 
Bruces Eddy dam and reservoir for flood control, 
navigation, power, recreation, and area redevelopment. 
Redesignation of project as Dworshak Dam and 
Reservoir. 
ICE HARBOR LOCK AND DAM - 
LAKE SACAJAWEA, WA 
Unit 1 of 4, Lower Snake River project, Lock and dam 
for navigation, power, recreation, and irrigation. 
Construction, operation, and maintenance of 
recreation facilities. 
LEWISTON-CLARKSTON BRIDGE, ID AND WA 
Four lane highway bridge and approaches. 
Increase of authorized amount to $23,200,000. 
Approach roadway from bridge to Sixteenth Avenue 
in Clarkston, WA. Increase of authorized amount to 
$24,000,000. 
LITTLE GOOSE LOCK AND DAMLAKE 
BRYAN, WA 
Unit 3 of 4, Lower Snake River project. Lock and dam 
for navigation, power, recreation, and irrigation. 
Designation of reservoir as Lake Bryan. 
LOWER GRANITE LOCK AND DAM, WA 
Unit 4 of 4, Lower Snake River project. Lock and dam 
for navigation, power, recreation, irrigation. 
LOWER MONUMENTAL LOCK AND DAMLAKE 
HERBERT G. WEST, WA 
Unit 2 of 4, Lower Snake River project. Lock and dam 
for navigation, power, recreation, and irrigation. 
Designation of reservoir as Lake Herbert G. West. 
LOWER SNAKE RIVER FISH & WILDLIFE 
COMPENSATION PLAN, WA, OR AND ID 
Fish hatcheries and replacement of wildlife habitat. 
McNARY LOCK AND DAM-LAKE WALLULA, 
OR AND WA 
Lock and dam for navigation, power, recreation, and 
irrigation. 
Construction, operation, and maintenance of recreation 
facilities. 
SNAKE RIVER MOUTH TO JOHNSON BAR, OR, 
WA AND ID 
Open-river navigation. 
Riparia to Pittsburg Landing. 
Mouth to Riparia. 
Sec. 208, P.L. 83-780 
Authorized by Chief 
of Engineers 
Feb. 11, 1985. 
S. Doc. 51, 84th Cong., 
1st Sess. 
H. Doc. 403, 87th Cong., 
2d Sess. 
P.L. 88-96 
H. Doc. 704, 75th Cong., 
3d Sess. 
Sec. 4, Flood Control 
Act of 1944 
P.L. 94-587 
P.L. 97-140 
P.L. 98-63 
H. Doc. 704, 75th Cong., 
3d Sess. 
P.L. 91-638 
H. Doc. 704, 75th Cong., 
3d Sess. 
H. Doc. 704, 75th Cong., 
3d Sess. 
P.L. 95-285 
P.L. 94-587 
H. Doc. 704, 75th Cong., 
3d Sess. 
Sec. 4, Flood Control 
Act of 1944 
H. Doc. 127, 56th Cong., 
2d Sess. 
H. Doc. 411, 55th Cong., 
2d Sess. 
13. 
14. 
15. 
16. 
17. 
18. 
19. 
20.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 39-B AUTHORIZING LEGISLATION 
(Continued) 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug. 30, 1935 
Mar. 2, 1945 
Pittsburg Landing to Johnson Bar. 
Supersedes previous legislation mouth to Lewiston, ID 
only. See Ice Harbor, Lower Monumental, Little 
Goose, and Lower Granite Locks and Dams. 
Rivers and Harbors 
Committee Doc. 25, 
72d Cong., 1st Sess. 
H. Doc. 704, 75th Cong., 
2d Sess. 
39-13

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Columbia River and Tributaries Completed 1968 1,851,195 
above Celilo Falls to 
Kennewick, WA1 
'Obviated by The Dalles, John Day, and McNary projects 
TABLE 39-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Asotin Creek, Asotin, ID' Completed 1951 12,019 - 
Bear Creek, Kendrick, ID' Completed 1970 133,518 - 
Big Wood River, ID5 Completed 1985 170,000 - 
Blackfoot Area, Snake River, 
Columbia River Basin, ID Completed 1958 42,796 - 
Blackfoot Reservoir, ID Deferred 1980 267,626 - 
Blackfoot River, Columbia 
River Basin, ID Completed 1965 391,143 
Boise Valley, Ada County 
Unit, Columbia River Basin, ID Deferred 1967 46,084 - 
Boise, River, ID5 Completed 1985 236,500 - 
Catherine Creek Lake, OR Deferred 1978 1,552,000 - 
Connell, WA1 Completed 1967 60,000 - 
Cottonwood Creek Community Church, 
Culdesac ID2 Completed 1984 23,400 - 
Dayton, Touchet River, WA Completed 1966 380,617 - 
Dry Creek, WA' Completed 1961 384,426 - 
Esquatzel Coulee, Connell, WA Completed 1967 232,792 - 
Esquatzel Coulee, Mesa, WA1 Completed 1969 2,665 - 
Gooding Area, ID' Completed 1954 59,167 - 
Grande Ronde Lake, OR Deferred 1966 - - 
Grande Ronde Valley, 
Columbia River Basin, OR Deferred 1958 102,458 - 
Graves Creek, ID' Completed 1953 75,469 - 
Heise-Roberts Area, Snake 
River, ID Completed 1955 1,575,838 
Heise-Roberts Extension, 
Columbia River Basin, ID 1968 
(a)Henrys Fork Unit Deferred 27,800 - 
(b) Snake River Unit Completed 3,375,158 - 
Jackson Hole, Snake River, WY Completed 1978 2,388,270 - 
Kendrick, Potlatch River, 
Columbia River Basin, ID Completed 1960 59,942 - 
Lapwai Creek, Culdesac, ID1 Completed 1972 176,833 - 
Lava Hot Springs, Portneuf 
River, ID1 Completed 1973 113,296 - 
Lower Dry Creek, Lowden, WA1 Completed 1972 17,592 - 
Lower Walla Walla River, 
Columbia River Basin, WA Inactive 1953 4,000 - 
Lyman Creek, ID1 Completed 1971 230,315 - 
Malheur Improvement District, 
Snake River, OR Completed 1957 55,894 
Malheur River, Vale Unit, 
Columbia River Basin, Or Completed 1961 325,581 - 
Milton-Freewater, Walla Walla River, OR3 Completed 1968 1,786,753 - 
39-14

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 39-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(Continued) 
For Last Cost to Sep. 30, 1985 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Mission and Lapwai Creeks, ID1 
Mud Lake, Columbia River 
Basin, ID 
Orofino Creek & Clearwater 
River, Orofino, ID2 
Rapid Creek, ID 5 
Palouse River, Columbia 
River Basin WA 
Pataha Creek, Pomeroy, WA2 
Payette River, Emmett 
Sewage Lagoon, ID 2 
Portneuf River & Marsh 
Creek Pocatello Unit, 
Columbia River Basin, ID 
Pullman, Palouse, WA 
Riverside Area, Pasco, WA 1 
Ririe Lake, ID 
Sewage Lagoons, Vale, OR 2 
Shelley Area, Snake River, 
Columbia River Basin, ID 
Shobe Canyon, Heppner, OR1 
Snake River, Blackfoot, ID' 
Snake River, Heise Bridge 
Location, ID2 
Snake River, Stevens, 
Blackfoot, ID 1 
South Firk, Boise River, ID 5 
South Fork Clearwater River, 
Coluumbia River Basin, ID 
South Fork Clearwater River, 
Kooskia-Stites, ID' 
Teton River, Columbia River 
Basin, ID 
Tomanovich-Salmon City, ID' 
Touchet River, Waitsburg, WA1 
Tucannon River, Wooten, WA' 
Umatilla River, OR1 
Wallowa River, Weaver 
Bridge OR2 
Weiser River, Columbia River 
Basin, ID 
Weiser River, ID 5 
Whitebird Creek, Columbia 
River Basin, ID 
Willow Creek, ID 1 
Willow Creek Lake, OR 
Yakima River, 
West Richland, WA' 4 
Completed 1965 54,538 
Inactive 
Inactive 
Completed 
Deferred 
Completed 
Completed 
Completed 
Deferred 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Inactive 
Completed 
Completed 
Completed 
1957 
1949 
1985 
1977 
1967 
1969 
1964 
1972 
1983 
1985 
1958 
1970 
1980 
1952 
1968 
1985 
1973 
1973 
1955 
1955 
1973 
1971 
1961 
1960 
1960 
1985 
1956 
1963 
1985 
1964 
5,996 
23,050 
19,500 
110,815 
39,172 
6,456,032 
99,540 
28,839 
39,677,448 
75,000 
32,335 
5,000 
131,700 
8,501 
32,425 
44,400 
3,899 
61,055 
10,387 
128,635 
72,140 
73,932 
161,540 
16,118 
37,757 
106,900 
1,896 
976 
37,168,114 
238,890 
'Authorized by Chief of Engineers pursuant to Section 
205, PL 80-858. 
'Authorized by Chief of Engineers pursuant to Section 
14, PL 79-526 
3Exclusive of $6,300 contributed funds. 
4Includes $9,000 contributed funds. 
5Authorized by Chief of Engineers pursuant to Section 
208, PL 83-780 
39-15

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Asotin Dam, Snake R. ID & WA 1964 1975 - - 
Boise Valley, Canyon County 
Unit, ID - 1967 10,600 - 
Camas Creek, ID - 1965 9,080 - 
Cottonwood Creek Dam, Boise, ID - 1984 183,100 - 
Little Wood River, ID - 1965 21,334 - 
Malheur River, Willow Creek 
Unit, OR - 1969 13,000 - 
Mill Creek, WA - 1977 3,537 - 
Payette Valley, ID - 1978 23,178 - 
Portneuf River, Inkom-Marsh 
Creek, ID - 1969 - - 
Stuart Gulch Dam, Boise, ID 1974 1979 234,100 - 
Touchet River, WA - 1977 11,198 - 
Weiser River, Cambridge- 
Midvale, ID - - 75,000 - 
TABLE 39-H COLUMBIA RIVER BASIN, LOCAL 
FLOOD PROTECTION PROJECTS 
(See Section 2 of Text) 
Estimated 
Federal 
Project Status Cost Cost to Sep. 30, 1986 
Blackfoot Area, Snake River, ID Completed - 42,796 
Blackfoot River, ID Completed - 391,143 
Boise Valley, ID 
Ada County Unit Deferred 1,060,000 46,084 
Canyon County Unit Deauthorized - 10,600 
Camas Creek, ID Deauthorized - 9,080 
Grande Ronde Valley, OR Deferred 8,639,000 102,458 
Heise-Roberts Extension, ID 
Henrys Fork Unit Deferred 165,000 27,800 
Snake River Unit Completed - 3.375.158 
Kendrick, Potlatch River, ID Completed - 59,942 
Little Wood River, ID Deauthorized - 21,334 
Lower Walla Walla River, WA Inactive 372,000 4,000 
Malheur River, OR 
Vale Unit Completed - 325.581 
Willow Creek Unit Deauthorized - 13,000 
Mill Creek, WA Deauthorized - 3,537 
Mud Lake, ID Inactive 1,187,000 5,996 
Palouse River, WA Deferred 914,000 - 
Payette Valley, ID Deauthorized - 23,178 
Portneuf River and Marsh Creek, ID 
Pocatello Unit Completed - 6,456,0321 
Shelley Area, Snake River, ID Completed - 32,335 
South Fork Clearwater River, ID Inactive - 3,899 
Teton River, ID Inactive - 10,387 
Touchet River, WA Deauthorized - 11,198 
Weiser River, ID Deferred 1,565,000 37,757 
Weiser River, ID 
Cambridge-Midvale Deauthorized - 75,000 
Whitebird Creek, ID Inactive - 1,896 
Total 11,090,191 
'Exclusive of $36,800 contributed funds. 
39-16

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 39-I INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
(See Section 7 of Text) 
Big Canyon Creek, Peck, ID April 1986 
Big Lost River, Arco, ID August 1986 
Big Wood River, ID July 1986 
Boise River, South Fork, ID August 1986 
Buffalo Fork, Ferry Location, WY August 1986 
Catherine Creek, Union, OR April 1986 
ClearWater River, Middle Fork, Kooskia, ID April 1986 
Clearwater River, Kooskia & Stites, ID April 1986 
Cottonwood River, Culdesac, ID April 1986 
Esquatzel Coulee, Connell, WA April 1986 
Gros Ventre River, WY August 1986 
Hoback River, WY August 1986 
Lawyers Creek, Kamiah, ID April 1986 
Malheur River, OR April 1986 
Salmon River, ID July 1986 
Snake River, Annex Location, OR April 1986 
Snake River, ID August 1986 
Snake River, ID August 1986 
Weiser River, ID April 1986 
Yakima River, West Richland, WA April 1986 
39-17

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 394 PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, 
POWERPLANT, AND IMPOUNDMENT 
Project 
Dworshak Dam and 
Reservoir, ID 
(See Section 13 of Text) 
Ice Harbor Lock and Dam, 
WA (See Section 14 of 
Text) 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Generating Units: 
Number Installed 
Space for Additional 
Rating, Each 
Total Capacity Installed 
Total Potential Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Flood Control Storage 
Lake Length 
Lake Water Surface Area at Elevation 1600 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
Concrete Gravity 
September 1974 
150,500 Cubic Feet 
Per Second 
1613 Feet 
Tainter 
50 Ft. by 55 Ft. 
2
428 Feet 
3
3
2 @ 90,000 kw; 
4 @ 220,000 kw 
400,000 kw 
1,060,000 kw 
150 Feet 
March 1973 
1600-1445 Feet 
1605 Feet 
2,000,000 Ac.-Ft. 
53 Miles 
17,090 Acres 
175 Miles 
86 Feet 
675 Feet 
97 Feet 
100 Feet 
103 Feet 
15 Feet 
May 1962 
Concrete Gravity 
January 1962 
850,000 cfs 
391 Feet 
Tainter 
50 Ft. by 51 Ft. 
10 
39-18

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 39-J PRINCIPAL DATA CONCERNING 
(Continued) NAVIGATION LOCK, SPILLWAY DAM, 
POWERPLANT, AND IMPOUNDMENT 
Project 
Little Goose Lock and Dam, 
WA (See Section 16 of 
Text) 
POWERPLANT 
Length 
Generating Units: 
Number Installed 
Rating, Each 
Total Installed Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 440 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Rating, Each 
Total Installed Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 638 
Navigation Channel, Depth by Width 
Length of Shoreline 
671 Feet 
6
3 @ 90,000 kw; 
3 @ 111,000 kw 
603,000 kw 
226 Feet 
December 1961 
440-437 Feet 
446 Feet 
31.9 Miles 
9,200 Acres 
14 Ft. by 250 Ft. 
80 Miles 
86 Feet 
675 Feet 
93 Feet 
98 Feet 
101 Feet 
15 Feet 
May 1970 
Concrete Gravity 
January 1970 
850,000 cfs 
581 Feet 
Tainter 
50 Ft. by 60 Ft. 
8
656 Feet 
243 Feet 
6
135,000 kw 
810,000 
244 Feet 
March 1970 
638-633 Feet 
646.5 Feet 
37.2 Miles 
10,025 Acres 
14 Ft. by 250 Ft. 
92 Miles 
39-19

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-J PRINCIPAL DATA CONCERNING 
(Continued) NAVIGATION LOCK, SPILLWAY DAM, 
POWERPLANT, AND IMPOUNDMENT 
Project 
Lower Granite Lock 
and Dam, WA (See 
Section 17 of Text) 
Lower Monumental 
Lock and Dam, WA 
(See Section 18 of Text) 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type: 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Rating, Each 
Total Capacity Installed 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface area at Elevation 738 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Contruction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
86 Feet 
675 Feet 
95 Feet 
100 Feet 
105 Feet 
15 
Concrete Gravity 
February 1975 
850,000 cfs 
581 Feet 
Thainter 
50 Ft. by 60.5 Ft. 
8
656 Feet 
243 Feet 
6
135,000 kw 
810,000 kw 
246 Feet 
April 1975 
738-733 Feet 
746.5 Feet 
38 Miles 
8,900 Acres 
14 Ft. by 250 Ft. 
91 Miles 
86 Feet 
675 Feet 
97 Feet 
98 Feet 
103 Feet 
15 Feet 
April 1969 
Concrete Gravity 
March 1969 
850,000 cfs 
483 Feet 
Tainter 
50 Ft. by 61 Ft. 
8 
39-20

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 39-J4 PRINCIPAL DATA CONCERNING 
(Continued) NAVIGATION LOCK, SPILLWAY DAM, 
POWERPLANT, AND IMPOUNDMENT 
Project 
McNary Lock and 
Dam, OR and WA 
(See Section 20 of Text) 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Rating, Each 
Total Installed Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 540 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Generating Units: 
Number Installed 
Rating, Each 
Total Installed Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 340 
Navigation Channel, Depth by Width 
Length of Shoreline 
656 Feet 
243 Feet 
6
135,000 kw 
810,000 kw 
242 Feet 
May 1969 
540-537 Feet 
548 Feet 
28.7 Miles 
6,590 Acres 
14 Ft. by 250 Ft. 
78 Miles 
86 Feet 
675 Feet 
67 Feet 
75 Feet 
83 Feet 
15 Feet 
November 1983 
Concrete Gravity 
October 1953 
2,200,000 cfs 
291 Feet 
Vertical Life 
50 Ft. by 51 Ft. 
22 
1,348 Feet 
14 
70,000 kw 
980,000 kw 
193 Feet 
November 1953 
340-335 Feet 
356.5 Feet 
64 Miles 
38,800 Acres 
14 Ft. by 250 Ft. 
242 Miles 
39-21

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-K SNAKE RIVER DOWNSTREAM FROM 
JOHNSON BAR LANDING 
OR, WA, AND ID 
(See Section 21 of Text) 
Estimated 
Cost (Corps New Work Maintenance Percent 
of Engineers to Sep. 30, 1986 to Sep. 30, 1986 Com- Constr. 
Project Funds Only) Approp. Cost Approp. Cost pleted Started 
Ice Harbor Lock & Dam 
Initial Project 
Code 710 Recreation 
Facilities 
Power Units 4-6 
Totals 
Little Goose Lock & Dam 
Initial Project 
Power Units 4-6 
Totals 
Lower Granite 
Lock & Dam 
Initial Project 
Code 710 Recreation 
Facilities 
Power Units 4-6 
Totals 
Lower Monumental 
Lock & Dam 
Initial Project 
Power Units 4-6 
Totals 
Open River Lewiston to 
Johnson Bar Landing 
Open River Pasco to 
Lewiston 
Totals Existing 
Project 
Previous Projects 
Pasco to Lewiston 
129,578,480 
914,256 
36,748,021 
167,240,757 
160,413,215 
60,941,807 
221,355,022 
321,503,981 
63,800 
46,212,534 
367,780,315 
184,712,361 
51,661,371 
236,373,732 
34,613 
129,578,480 129,578,490 50,242,774 50,205,270 
914,256 
36,748,021 
167,240,757 
160,413,215 
60,941,807 
221,355,022 
914,256 
36,748,021 
167,240,757 
160,413,215 
60,941,807 
221,355,022 
50,242,774 
39,430,795 
39,430,795 
50,205,270 
39,331,168 
39,331,168 
321,503,981 321,503,979 45,084,502 44,939,038 
63,800 
46,212,534 
367,780,315 
184,712,361 
51,661,371 
236,373,732 
63,800 
46,212,534 
367,780,313 
184,712,361 
51,661,371 
236,373,732 
45,084,502 
34,785,232 
34,785,232 
44,939,038 
34,717,304 
34,717,304 
100 FY 57 
100 
100 
100 
100 
100 
100 
FY 57 
FY 71 
FY 63 
FY 74 
100 FY 65 
100 
100 
100 
100 
100 
100 
FY 84 
FY 74 
FY 61 
FY 75 
34,6131 34,6131 378,603 373,9572 
- - - 4,350 4,350 
992,784,439 992,784,439 992,784,437 169,926,256 169,571,087 100 
400,150 400,150 400,150 186,570 186,570 
Totals Authorized 
Project 993,184,589 993,184,589 993,184,587 170,112,826 169,757,657 
1New Work appropriations used for maintenance prior 
to 1953. 
2Includes $6,014 FY 1986 project condition survey cost.
39-22

ALASKA DISTRICT * 
This District consists of the State of Alaska.
IMPROVEMENTS 
Navigation 
1. Anchorage Harbor, AK ................. 
2. Bethel Small Boat Harbor, AK .......... 
3. Cordova Small Boat Harbor, AK.......... 
4. Dillingham Harbor, AK ............... 
5. Homer Harbor, AK .................... 
6. Kake Harbor, AK ..................... 
7. King Cove Harbor, AK ................. 
8. Mekoryuk, AK ........................ 
9. Metlakatla Harbor, AK ................ 
10. Ninilchik Harbor, AK .................. 
11. Nome Harbor, AK ..................... 
12. Port Lions Small Boat Harbor, AK ....... 
13. Project Condition Surveys .............. 
Flood Control 
14. Bethel, Mission Road, Emergency Bank 
Stabilization, AK ..................... 
15. Chena River Lakes, AK ................ 
16. Dillingham Emergency Bank 
Stabilization, AK ..................... 
17. Galena Emergency Bank Stabilization, AK 
18. Kuskokwim River, Bethel, AK ........... 
19. Flood Control Work Under 
Special Authorization .................. 
20. Inspection of Completed Flood 
Control Projects ....................... 
Page 
40-1 
40-2 
40-2 
40-2 
40-3 
40-3 
40-3 
40-3 
40-4 
40-4 
Multiple-Purpose Projects, 
Including Power 
21. Snettisham, AK ...................... 
General Investigations 
22. Surveys ............................. 
23. Collection and Study of 
Basic Data ........................... 
24. Continuation of Planning and Engineering 
Page 
40-6 
40-6 
40-7 
40-7 
40-4 Tables 
40-5 Table 40-A Cost & Financial Statement .... 40-8 
40-5 Table 40-B Authorizing Legislation ........ 40-11 
Table 40-C Other Authorized Navigation 
Projects ..................... 40-13 
Table 40-D Not Applicable.............. 
40-5 Table 40-E Other Authorized Flood Control 
40-5 Projects ..................... 40-14 
Table 40-F Not Applicable.............. 
40-5 Table 40-G Deauthorized Projects ......... 40-14 
40-6 Table 40-H Navigation Work Under Special 
40-6 Authorization ................ 40-15 
Table 40-I Project Condition Surveys ...... 40-15 
40-6 
40-6 
Navigation 
1. ANCHORAGE HARBOR, AK 
Location. Anchorage is in southcentral Alaska on the 
southeast shore of Knik Arm, north of Turnagain Arm 
near its junction with Cook Inlet. (See NOAA Charts 
16660 and 16664.) 
Existing project. Provides for dredging along a 
3,000-foot baseline adjacent to the Port of Anchorage dock 
to a depth of 35 feet below mean lower low water. Tidal 
range between mean lower low water and mean higher 
high water is 29.0 feet and the extreme range is 42.0 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. The Port of Anchorage facility consists 
of a POL terminal at the southern end and three 
general cargo terminals northward. The northernmost terminal, 
completed during 1976 and 1977 was outside the 
Federal project limits. Extension of limits from 2,070 feet 
northward to 3,000 feet was authorized by Public Law 
94-587 and funded in FY 1978. 
Operations during fiscal year. Maintenance: The 
dredging was performed by U.S Hopper dredge Essayons 
with 800,000 cubic yards of silt removed during July and 
August 1986. 
Dredging has been accomplished across the entire project 
during FY 1986. Controlling depth at the harbor was 
-31 feet mean lower low water, with a majority of the 
40-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
harbor at project depth of -36. Because of the lack of 
maneuverability by the dredge within the tight confines 
of Anchorage Harbor, deposuts of sediments at both ends 
of the dock could not be reached by the dredge. A separate 
cleanup contract was advertised in September 1986 and 
scheduled to be awarded in October 1986. 
2. BETHEL SMALL BOAT HARBOR, AK 
Location. The city of Bethel is 65 miles upriver on the 
north bank of the Kuskokwim River, which flows through 
southwestern Alaska. Bethel is about 400 miles west of 
Anchorage. (See Coast and Geodetic Survey Chart 9302 
and USGS Map Bethel D8.) 
Existing project. Project (Section 107) includes provision 
of a 12-acre small boat harbor and 1,270 foot entrance 
channel by deepening, widening, and straightening a portion 
of the Lousetown Slough which is 0.3 miles east of 
Bethel. Range between mean lower low water and mean 
higher high water is 4.0 feet and extreme tidal range is 
10.0 feet, during low summer water flow in Kuskokwim 
River. Water level also depends on river state; tidal effects 
decrease with higher river flows, disappearing only at the 
20-year-frequency flood stage. 
Local cooperation. Fully complied with. 
Terminal facilities. Bethel serves as a regional 
transportation center for approximately 50 villages. A 
medium-draft port facility was built along the city's riverfront 
in 1975. Goods, including gas, oil, food, clothing, and 
construction material are all brought into Bethel for 
redistribution to outlying villages. Generally, river 
shipments of bulk goods are transported by medium-draft 
barges. Personal supplies are often moved in individually 
owned riverboats which also are used for fishing activities. 
The riverboat fleet in Bethel is estimated to 
number between 1,000 and 1,100 boats, of which 400 are 
transient boats from other villages along the Kuskokwim 
River. There are also eight river barges varying in size 
to as large as 30 by 100 feet. The barges are powered by 
five locally-based tug boats with lengths ranging from 25 
to 40 feet. No protected berthing areas exist at Bethel for 
any water craft. The riverboats are beached on the sandbars 
and banks for temporary storage. Brown's Slough is 
particularly popular as a berthing area, resulting in overcrowding 
and congestion. 
Operations during fiscal year. New work: Construction 
was physically completed in FY 1983 and fiscally 
complete in FY 1986. 
3. CORDOVA SMALL BOAT HARBOR, AK 
Location. Cordova is on Orca Inlet, a strait near the 
eastern entrance of Prince William Sound, about 150 air 
miles south-southeast of Anchorage. (See Coast and 
Geodetic Survey Charts 8520, 8525, and 8551.) 
Existing project. The Office of the Chief of Engineers 
approved construction of a harbor expansion from 8.26 
acres to 20 acres by removal of the existing 1400-foot 
breakwater and construction of a new 2000-foot long 
breakwater. The entrance channel is dredged to -16 feet 
mean lower low water and the turning basin is dredged 
from -10 to -12 mean lower low water. Tidal range between 
mean lower low water and mean higher high water is 12.4 
feet with an extreme range of 21.7 feet. The dredged 
material is disposed of in two diked upper tidal areas 
which will be used as staging facilities. 
Local cooperation. Fully complied with. 
Terminal Facilities. Two municipal docks accommodate 
general cargo and passengers, including 
automobile ferry traffic. One privately owned wharf, 
reduced by fire, provides oil handling and bunkering 
facilities. Three privately owned wharves are used for industrial 
purposes. A small boat float system for public use 
is in original basin. State ferry dock in basin has been 
superseded by municipal dock and is inactive. Facilities 
are considered adequate for present commerce. 
Operations during fiscal year. New work: Project is 
physically complete. Contractor claim is pending for attorneys' 
fees. 
4. DILLINGHAM HARBOR, AK 
Location. At head of Nushagak Bay, an arm of Bristol 
Bay, on right bank of Nushagak River just below its confluence 
with Wood River; about 470 miles northeasterly 
of Dutch Harbor and 300 miles southwest of Anchorage. 
(See NOAA/NOS Chart #16660.) 
Existing project: A small-boat basin 230,000 square 
feet in area with a depth of 2 feet above mean lower low 
water along Scandinavian Creek; with entrance channel 
1,100 feet long and 40 feet wide in Scandinavian Creek; 
and a sheet pile sill across the basin outlet with a top 
elevation of 7 feet above mean lower low water. During 
design stage the project was revised to include a rock sill 
with adjacent scour-protection blankets and the embankment 
was relocated to include a berm between the basin 
and the embankment. Tidal range between mean lower 
low water and mean higher high water is 19.8 feet. Extreme 
range is 30.0 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Four docks at the city of Dillingham; 
three privately owned one owned by the city of 
Dillingham, and four publicly owned small-boat floats in 
the project basin. Two docks are used for salmon-cannery 
operations; the third is an oil handling and bunkering terminal; 
the fourth dock is used by the city to unload barges 
which come into Dillingham. New floats for the harbor 
were installed in June 1982 and removed before fall 
freezeup. They are replaced each spring. Cargo and 
passengers from ocean vessels are unloaded at the docks 
or in the small-boat basin. Facilities are inadequate for 
number of boats using small boat harbor. 
Operations during fiscal year. Maintenance: Government 
plant and hired labor performed dredging from the 
end of May to the middle of June and from the middle of 
August to the first of September 1986. A total of 100,000 
cubic yards of material were removed. A major breakdown 
in the middle of June caused the dredge to be shutdown 
until the middle of August 1986. An impeller for the 
dredge pump had to be manufactured and shipped to 
Dillingham. 
40-2

ALASKA DISTRICT 
5. HOMER HARBOR, AK 
Location. In Kachemak Bay, on Kenai Peninsula, 152 
miles by water southwest of Anchorage. Harbor site is 
land based near the extremity of Homer Spit which varies 
to one-quarter mile in width and extends 4.5 miles 
southeasterly from the mainland. (See NOAA/NOS Chart 
#16645.) 
Existing project. Provides for sheltered small-boat 
harbor, relocated and based within Homer Spit about 50 
acres in area. Project depth varies from 10 feet mean lower 
low water in the most western segment of the harbor to 
20 feet below mean lower low water in the entrance channel 
and the most eastern segment of the harbor; a north 
entrance channel; protected by a main rock breakwater 
1,018 feet long and secondary rock breakwater 238 feet 
long. Tidal range between mean lower low and mean 
higher high water is 18.1 feet, with an extreme range of 
30.4 feet. (For details relating to previous projects, see page 
1593 of Annual Report for 1964.) 
Local cooperation. Fully complied with. 
Terminal facilities. One publicly owned and operated 
wharf capable of handling oceangoing vessels serves for 
passengers and general cargo. Small-boat facilities in 
basin area include publicly owned mooring floats, a publicly 
owned wharf, and an industrial wharf. Construction 
has tripled size of the harbor. The city of Homer has tripled 
the size of its fish dock located at the southern end of 
the harbor. 
Operations during fiscal year. Maintenance: Dredging 
operations were initiated in February 1986 but were 
suspended when the U.S. dredge Warren George sank in 
the boat harbor. Hydrographic surveys were performed 
and operations will be resumed in October, 1986. 
6. KAKE HARBOR, AK 
Location. Kake Harbor is located in the city of Kake, 
on the northwest corner of Kupreanof Island in 
southeastern Alaska, 39 air miles west of Petersburg, AK, 
and 850 water miles northwesterly of Seattle, WA. (See 
Coast and Geodetic Chart 8201.) 
Existing project. The authorized project consists of a 
1,580-foot-long west breakwater and a 900-foot long south 
breakwater, enclosing a 7-acre berthing area. Poor foundation 
conditions found during preconstruction investigations 
have forced modification of the project to include a 
1,760-foot-long west breakwater and a 1,750-foot-long 
south breakwater. Tidal range between mean lower low 
water and mean higher high water is 14.0 feet with an 
extreme range of 22 feet. Estimated project cost is 
$12,537,000 (October 1985), including $12,500,000 Corps 
of Engineers funds $21,000 Coast Guard funds, and 
$16,000 non-Federal cost. 
Local cooperation. Fully complied with. 
Terminal facilities. At Kake, a publicly owned wharf 
with seaplane float equipped airplanes and shallow-draft 
vessels is located within area of proposed basin. At cannery 
1 mile from city, there are two privately owned deepdraft 
piers: one for cargo, open to all local boat owners, 
the second for fuel, including a float for fueling small 
boats. At Portage Cove, there is one publicly-owned smallboat 
float. Facilities are not considered adequate for present 
commerce due to the following deficiencies in smallboat 
facilities: the complete lack of protection in the directions 
of the most severe storms; shallow water at Portage 
Cove float and its approaches; ice formation on the cove 
during the winter months causes major boat damage and 
limits the use of the mooring float; and transportation 
problems between city and present small-boat float at Portage 
Cove. 
Operations during fiscal year. New work: A 
biological study was completed which investigated the 
aquatic habitats and organisms of the project area 
through the use of a joint United States Fish and Wildlife 
Service - Corps of Engineers dive effort. The data gathered 
is being used to understand temporal changes in these 
natural systems, pre- and post-project conditions, as well 
as provide background information for a recolonization 
study of man-made rubble structures in Alaska. Analysis 
of the data was completed and the report was prepared 
in FY 1986. A temporary automatic meteorburst wind 
monitoring station was maintained to gather wind velocity 
and directional data more closely associated with the 
location of the project for comparison with data used in 
preparing the plans and specifications. 
7. KING COVE HARBOR, AK 
Location. The city of King Cove, Alaska, is located 
near the southwesterly tip of the Alaska Peninsula in 
southwestern Alaska, 630 miles southwest of Anchorage. 
(See NOAA/NOS Chart #16549.) 
Existing project. Provides for an 11-acre small-boat 
basin having an anchorage basin 900 feet long by 550 feet 
wide and an entrance channel 100 feet wide and about 
400 feet long, both at a depth of 15 feet below mean lower 
low water, a 1,400-foot long training dike, top elevation 
10 feet above mean lower low water; and a 200-foot long 
rock sea groin, top elevation 14 feet above mean lower low 
water. Tidal range between mean lower low water and 
mean higher high water is 6.8 feet, with an extreme range 
of 14.0 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Consists of twin wharves with a 
small basin between them; marine rail and slipways 
flanked by catwalks and oil terminal facilities; and mooring 
buoys, dolphins, and piling for small boats. All are 
privately owned. Facilities are considered adequate for 
present oceangoing commerce but inadequate for the commercial 
fishing vessels operating in the area. A study for 
a new dock to be built by the State has been completed 
and engineering specifications for the new dock are now 
in the process of being written. The new dock will be 
leased to the city after construction. 
Operations during fiscal year. Maintenance: Project 
is fiscally complete. 
8. MEKORYUK, AK 
Location. Mekoryuk, is on the northeast shore of 
Nanivak Island in the Bering Sea approximately 23 miles 
40-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
from mainland Alaska in the region of the Yukon- 
Kuskokwim Delta. 
Existing project: Construction of a rock breakwater 
is to provide both boat protection and beach erosion protection. 
The breakwater is constructed adjacent to the 
existing boat beaching area; this location would offer erosion 
protection against waves generated within Shoal Bay; 
side slopes are 1 on 2 and crest elevation is 17.5 feet above 
mean lower low water. The top width is six feet. Length 
is 510 feet. 
Local cooperation. Fully complied with. 
Operation during fiscal year. New Work: Contract 
was awarded in May 1986 and physically completed in 
September 1986. 
9. METLAKATLA HARBOR, AK 
Location. Metlakatla is located in the southern portion 
of Port Chester, a small bay on the northwest coast 
of Annette Island in southeastern Alaska, 18 miles south 
of Ketchikan. (See Coast and Geodetic Charts 8074, 8075, 
and 8102.) 
Existing project. Consists of two small-boat basins. 
Existing basin is 2.18 acres in extent with a depth of 10 
feet below mean lower low water, protected by a rubblemound 
breakwater 900 feet long. New basin consists of 
two rubblemound breakwaters, 1,255 and 1,150 feet long, 
and an entrance channel and maneuvering area, 1,100 
feet long, 100 feet wide, dredged to a depth of 15 feet below 
mean lower low water and a basin area of 6.25 acres 
dredged to a depth of 15 feet below mean lower low water. 
Tidal range between mean lower low water and mean 
higher high water is 14.7 feet, with an extreme range of 
24 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Publicly owned facilities are one 
general-cargo dock, one barge ramp, and a small-boat float 
system in existing basin. Privately owned facilities are 
one oil pier and one industrial wharf. Facilities are not 
adequate for mooring the commercial fishing vessels 
operating from Metlakatla. Existing protected harbor 
area is fully utilized. 
Operations during fiscal year. New work: Project is 
physically complete; however, various contractor claims 
are still pending. 
Maintenance: In October 1984 erosion problems at the 
beach adjacent to the east breakwater of the Metlakatla 
Small Boat Harbor were first reported. A site investigation 
was made on October 30, 1984. Beach erosion in this 
area has accelerated since construction of the harbor. A 
letter report describing the erosion and two recommended 
alternatives was completed in January 1985, and 
forwarded to higher authority for review and funding. 
Funding was obtained and a contract for placing a 4-foot 
thick riprap blanket (approximately 3,300 cubic yards of 
quarry spalls) on the beach and placing riprap on the landward 
connection of the east breakwater was awarded on 
September 30, 1985. The work was completed in 
November 1985. 
10. NINILCHIK HARBOR, AK 
Location. At mouth of Ninilchik River in Cook Inlet, 
at the community of Ninilchik, AK, about 40 miles upcoast 
from Homer and 112 miles southwest of Anchorage. 
(See NOAA/NOS Chart #16640.) 
Existing project. A small-boat basin 320 feet long by 
150 feet wide dredged to elevation of 2 feet above mean 
lower low water, with an approach channel 400 feet long 
and 50 feet wide dredged to an elevation of 9 feet above 
mean lower low water; protected by a pile jetty 410 feet 
long. Project was modified in design stage to delete pile 
jetty and revise harbor dimensions to 400 feet long by 125 
feet wide, and was completed in November 1961. Modification, 
including river channel diversion, two armor rock 
jetties, and beach protection, was accomplished 1967 and 
1969. Range between mean lower low water and mean 
higher high water is 19.1 feet, with an extreme range of 
29.3 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities, limited to shallow-draft 
vessels and accessible from Cook Inlet only at half-tide 
or higher, are a cannery dock along Ninilchik River 
available for offloading fish, and small-boat floats in project 
basin, provided by State of Alaska. Other supplies are 
landed on beach or brought by road from deep-draft ports 
in the vicinity. Facilities are extremely inadequate for the 
number of boats presently using harbor. Expansion of 
facilities would require construction of additional protected 
harbor area. 
Operations during fiscal year. Maintenance: Dredging 
of the harbor and entrance channel was accomplished 
with 8,200 cubic yards removed in 1986. A survey of the 
basin during May 1986 indicated project depth was 
available throughout the Federal limits. Due to storm action, 
littoral drift beach material shoaled the entrance 
channel three times necessitating removal by bulldozer. 
Approximately 1,800 cubic yards of material was removed 
during these operations. 
11. NOME HARBOR, AK 
Location. At mouth of Snake River at the city of Nome, 
AK, on northerly shore of Norton Sound, an arm of Bering 
Sea. It is a shallow open roadstead, 581 nautical miles 
north of Dutch Harbor and 545 air miles northwest of Anchorage. 
(See NOAA/NOS Chart #16206.) 
Existing project. Provides for two jetties, the easterly 
951 and the westerly not exceeding 676 feet long, at 
mouth of Snake River; a channel 8 feet at mean lower low 
water, 75 feet wide, from Norton Sound through Snake 
River to mouths of Bourbon and Dry Creeks, in city of 
Nome, ending in a turning basin of the same depth, 250 
feet wide and 600 feet long; revetting banks of rivers; and 
protecting all existing water-front improvements on 
easterly beach by means of rock-mound seawall 3,350 feet 
long extending easterly from east jetty. Project has been 
completed except extension of jetties beyond present 400 
and 240 feet, which is classified inactive. Range between 
mean lower low water and mean higher high water is 1.6 
feet and extreme tidal range is 7.5 feet, but water levels 
40-4

ALASKA DISTRICT 
are influenced more by wind than tide. Levels of 5 feet 
below mean lower low water have been observed during 
offshore winds, and a level of 14 feet above mean lower 
low water has been observed during a southerly storm. 
Local cooperation. Fully complied with. 
Terminal facilities. Cargoes and passengers from 
ocean vessels are lightered to and from shore a distance 
of about 2 miles. Traffic enters dredged channel and is 
handled over revetment, where lighterage company has 
transfer facilities which are open to the public. Facilities 
considered inadequate for existing commerce. In July 
1984, the city of Nome received Department of Army 
authorization (permit) to construct a 3,600-foot gravelfilled 
causeway. Construction of the causeway began in 
July 1985. Due to lack of complete funding the length of 
the causeway was shortened to 2,700 feet. Construction 
is scheduled to be completed in the first quarter of FY 1987. 
Operations during fiscal year. Maintenance: Dredging 
by contract was accomplished throughout the ice-free 
season. 7,200 cubic yards were removed in FY 1986. 
Seriously damaged conditions of the entrance channel 
sheetpile wall necessitated immediate interim repairs. A 
Letter Report for interim repairs was prepared and approved. 
Construction was initiated in September 1986 
with a scheduled completion date of November 1986. A 
new DM for Entrance Channel Permanent Repairs and 
Modifications will be initiated in FY 1987. 
12. PORT LIONS SMALL BOAT HARBOR, AK 
Location. Port Lions is located on the north end of 
Kodiak Island, approximately 19 air miles west of the city 
of Kodiak. (See NOAA/NOS Chart #16594.) 
Existing Project. The Office of the Chief of Engineers 
approved construction for a small boat harbor at Port 
Lions on April 9, 1979. Construction consisted of a 
600-foot-long breakwater, a 170-foot-long stub breakwater 
inclosing a 12-acre harbor. Tidal range between mean 
lower low water and mean higher high water is 9.6 feet 
with an extreme range of 18 feet. 
A severe storm in November 1981 badly damaged the 
project. The repair work included replacing material of 
the existing main breakwater, extending the main 
breakwater 125 feet, changing the seaward breakwater 
slope to a 2.OH:1.OV adding a layer of armor rock and raising 
the design crest elevation from +18.5 mean lower low 
water to + 22.0 mean lower low water. Minor dredging in 
the entrance channel to -15.0 mean lower low water was 
also included. 
Local Cooperation. Fully complied with. 
Terminal facilities. A municipal timber pile dock at 
Port Wakefield serves as both a shallow-draft and deepdraft 
facility for Port Lions. 
Operations during fiscal year. Maintenance: Project 
is complete. Contractor claim for differing site conditions 
for dredging is pending. 
13. PROJECT CONDITION SURVEYS 
Preliminary and detailed surveys to determine navigation 
conditions at boat basins, small navigation projects, 
channels, and tributaries of major rivers not within 
major project boundaries. Total costs for fiscal year were 
$512,796 (See Table 40-I). 
14. BETHEL, MISSION ROAD EMERGENCY 
BANK STABILIZATION, AK 
Location. Mission road at Bethel, AK. 
Existing project: Construct protection stone layer in 
front of bulkead piling along Mission Road. 
Local cooperation. Fully complied with. 
Operation during fiscal year. New Work: Contract 
was awarded in August 1986 and is scheduled for completion 
in October 1986. 
Flood Control 
15. CHENA RIVER LAKES, AK 
Location. In the vicinity of Fairbanks, AK, and encompassing 
the Tanana River, Chena River, Little Chena 
River, and their tributaries. (See USGS map Fairbanks, 
C1, D1, D2, and Big Delta D6.) 
Local cooperation. Fully complied with. 
Existing project. Moose Creek Dam has been constructed 
17 miles east of Fairbanks with control works 
on Chena River. The dam itself extends from a bluff one 
mile north of the Chena River and south past the control 
works for approximately six miles to the Tanana River. 
The dam connects with a completed 22-mile levee system 
along the north boundary of the Tanana River to a point 
south and west of Fairbanks. Estimated Federal cost is 
$209,000,000, (excluding Little Chena Dam, presently 
deferred) and estimated non-Federal cost is $12,548,000. 
Operations during fiscal year. New work: Constructtion 
of the Tanana River Levee System Repair was completed 
in August 1986 and the new Office and Warehouse 
contract is under construction. A construction contract for 
the Tanana River Levee Protection Phase II, Groins 9 and 
10 was awarded in August 1986 and a construction contract 
for 30 Relief Wells was awarded in September 1986. 
Maintenance: High water events occured in June, July 
and August 1986 necessitating lowering the flood gates. 
Although no direct flooding was caused by the highwater 
events, Salmon and Grayling Fry were killed in Ox-Bow 
Lakes within the floodway area. Corrective action will be 
reviewed in FY 1987. 
16. DILLINGHAM EMERGENCY BANK 
STABILIZATION, AK 
Location. City of Dillingham is located at the confluence 
of the Wood and Nushagak Rivers in the Bristol 
Bay area of southwestern Alaska. 
Existing project: Relocate water and sewer lines. 
Local cooperaiton. Will be required prior to 
construction. 
Operation during fiscal year. New Work: Initial contact 
with local sponsor. 
40-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
17. GALENA EMERGENCY BANK 
STABILIZATION, AK 
Location. Galena is located on the north bank of the 
Yukon River approximately 270 miles west of Fairbanks, 
AK and 325 miles north-northwest of Anchorage, AK. 
Existing project: The project will provide approximately 
1200 feet of riverbank protection when contributed 
funds are included. The protection will be in front 
of "New Town" Galena or the Alexander Lake area, thus 
extending the bank stabilization project the State started 
in 1985. 
Local cooperation. A Local Cooperation Agreement 
is being developed. 
Operation during fiscal year. New Work: Initiated 
plans and specifications. 
18. KUSKOKWIM RIVER, BETHEL, AK 
Location. Kuskokwim River bank at Bethel, AK. 
Existing project. Work was authorized under the continuing 
authority contained in Section 14 of the 1946 
Flood Control Act. This authority allowed construction of 
emergency bank protection to prevent loss of the city's 
multipurpose bulkhead and petroleum dock. 
Local cooperation. The project sponsor, city of Bethel, 
provided construction easements and rights-of-way, and 
agreed to hold the United States free from damages and 
maintain and operate the completed bank protection 
works. 
Operations during fiscal year. New work: Contract 
was awarded in September 1985 and work was completed. 
Approximately 1,650 cubic yards of rock toe was constructed 
prior to the fall river freeze-up. 
19. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
Emergency flood control activities - repair, flood 
fighting, and rescue work (Public Law 99, 84th Congress, 
and antecedent legislation). 
Federal costs for the fiscal year were $134,454 for 
disaster preparedness and emergency operations. 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Cong., as amended (preauthorization). 
Fiscal year cost for preauthorization study was: Aniak, 
$84,481. 
Emergency bank protection activities pursuant to 
Section 14, 526, 79th Cong. (preauthorization) 
Fiscal year cost for preauthorization study was: Anchor 
River, $7,500. 
20. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Inspections were made of flood control works at Gold 
Creek, Skagway River, Salmon River, Talkeetna River, and 
Klutina River during September 1986. Repairs at each 
project were recommended to the local authority. Total 
costs for the fiscal year: $7,807. 
Multiple-Purpose Projects, 
Including Power 
21. SNETTISHAM, AK 
Location. At mouth of Speel River, between Crater 
Lake to the west and Long Lake to the north, 28 nautical 
miles southeast of Juneau. (See Coast Geodetic Survey 
Chart 8227.) 
Existing project. Snettisham is a multi-stage power 
project. The initial stage of the initial phase which was 
completed in 1977 tapped Long Lake and included an 
underground powerhouse with two 23.4 megawatt units 
and a transmission line to Juneau, AK. The project was 
turned over to the Alaska Power Administration for operation 
and maintenance. The second stage which is under 
construction, will provide a tunnel to Crater Lake and add 
a third unit. The final phase will provide a dam on Long 
Lake to increase storage and the energy capability of Long 
Lake. The Long Lake Dam is currently unscheduled. The 
existing Long Lake (elevation 815 feet) water is 
transported through an approximately horizontal 13-foot 
diameter tunnel 8,400 feet long and a 1,400-foot penstock 
dropping at a 46 degree angle to the undergound 
powerhouse at tidewater to drive two turbines with a combined 
generating capacity of 47,600 kilowatts. Power from 
two generators is supplied to Juneau by a 13.8 kilovolt 
overhead transmission line and a submarine cable traversing 
Taku Inlet. The Crater Lake stage of construction provides 
for tapping Crater Lake (elevation 1,022 feet) to 
drive a third turbine to be installed in the existing 
underground powerhouse to provide an additional 
nameplate-rated generating capacity of 34,500 kilowatts. 
Estimated cost of initial phase construction is 
$139,000,000. 
Local cooperation. None required. 
Operations during fiscal year. New work: Engineering 
and design is complete on the Crater Lake Phase including 
the feature design memorandum for power tunnel, 
penstock, lake tap, gate structure and surge tank; 100 
percent completion of plans and specifications for completing 
the initial development including gate structure, 
penstock surge tank, machine shop powerhouse completion 
and lake tap; and 100 percent completion of plans 
and specifications for generator, powerhouse completion 
and electrical contracts. A study to determine the 
economic viability of proceeding with the development of 
the Long Lake Dam was undertaken. The initial construction 
contract of the Crater Lake Phase II was awarded 
August 1986. Work performed under the contract includes 
completion of the power tunnel, excavation of a surge shaft 
a gate shaft with access adit, performing a lake tap; installation 
of a penstock, turbine an sperical valve, governor, 
switchgear, and transformer; and completion of the 
powerhouse. 
General Investigations 
22. SURVEYS 
Fiscal year costs of $1,752,771 for surveys include 
$275,822 for navigation studies, $1,323,638 for flood 
40-6

ALASKA DISTRICT 
control studies, $32,000 for coordination studies and the Kuskokwim River. The recommended plan calls for 
$111,311 for miscellaneous activities, rock riprap protection for 8,500 feet of river bank with 
the rock extending from above the active wave zone to the 
23. COLLECTION AND STUDY OF BASIC DATA thalweg of the river. 
Technical assistance, information, flood plain manage- A Plan of Study was prepared for the General Design 
ment guidance and other flood plain management serv- Memorandum in FY 1984. 
ices have been provided to military and nonmilitary 
Federal agencies, local communities, State agencies, Ar- Work on the General Design Memorandum initiated 
chitectural/Engineering firms, lending institutions and in FY 1984 is 75% complete and scheduled for completion 
private individuals at a fiscal year cost of $135,124. in FY 1987. Estimated preconstruction planning cost is 
Fiscal year costs for Hydrologic Studies were $11,550. $614,000. Fiscal year costs were $259,183. 
24. CONTINUATION OF PLANNING AND 
ENGINEERING 
Bethel Bank Stabilization, AK 
The proposed project would provide streambank protection 
to the city of Bethel, located in western Alaska on
40-7

TABLE 40-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
1. Anchorage Harbor, New Work 
AK Approp. - - 
Cost - - 
2. Bethel Small Boat 
Harbor, AK 
(Contrib. Funds) 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
946,000 
1,225,405 
307,000 
915,017 
-1,284,600 
-633 
113,000 
301,525 
266,000 
295,862 
30,000 
78,817 
294,000 
316,897 
Cordova Small Boat 
Harbor, AK 
(Contrib. Funds) 
4. Dillingham Harbor, 
AK 
(Contrib. Funds) 
5. 
6. 
7. 
Homer Harbor, AK 
(Contrib. Funds) 
Kake Harbor, AK 
King Cove Harbor 
AK 
8. 
9. 
Mekoryuk, AK 
Metlakatla Harbor 
AK 
1,679,000 
754,434 
2,090 
-106,290 
1,1 
2,0 
52,800 
53,677 
350,000 
325,219 
1,723,000 
1,729,421 
70,000 
72,435 
- 8,057,500 
- 8,010,237 
30,000 70,000 
)1,298 85,533 
- 491,494 
- 436,119 
35,000 45,000 
36,257 858 
- - 533,235 
- - 533,235 
.81,725 1,102,000 16,512,172 
)86,585 1,250,458 16,509,474 
- -5,899 1,514,373 
406 -77 1,514,373 
- . 609,110 
- - 609,110 
i62,000 80,000 9,642,0001 
i61,366 76,656 9,636,9951 
- - 4,813,000 
98,731 - 4,811,891 
- - 548,790 
- - 548,790 
372,000 400,000 5,338,821 
L21,969 393,395 5,321,772 
- - 1,700 
- - 1,700 
- - 3,512,3502 
- - 3,512,3502 
50,000 65,000 2,463,711 
49,655 63,991 2,462,288 
- - 67,974 
- - 67,974 
358,960 - 8,316,4603 
375,719 2,059 8,288,0153 
25,000 15,000 870,700 
34,887 4,507 856,944 
- - 2,264,948 
- - 2,264,948 
76,000 -1,000 566,494 
L31,314 -939 566,494 
40,000 1,065,000 1,420,000 
65,372 1,035,909 1,372,139 
75,000 
17,134 
99,000 
13,839 
67,698 
-1,000 
84,161 
4,922,470 
4,912,300 
148,520 
148,520 
12
9
2
2 
-25,000 -229,000 
28,597 -204,702 
40-8 
- 7,5 
- 7,5
34 
2
2
1

ALASKA DISTRICT 
TABLE 40-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
(Contrib. Funds) New Work 
10. Ninilchik Harbor, 
AK 
11. Nome Harbor, AK 
(Contrib. Funds) 
12. Port Lions Small 
Boat Harbor, AK 
(Contrib. Funds) 
14. Bethel, Mission Road, 
Emergency Bank 
Stabilization, AK 
15. Chena River Lakes, 
AK 
(Contrib. Funds) 
16. Dillingham, 
Emergency Bank 
Stabilization, AK 
17. Galena, 
Emergency Bank 
Stabilization. AK 
18. Kuskokwim River, 
Bethel, AK 
(Contrib. Funds) 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
- - - - 830,644 
- - -206,827 150,923 772,096 
- - - - 428,720 
- - - - 428,720 
237,000 300,000 156,000 200,000 3,320,476 
244,916 302,425 155,806 197,723 3,317,991 
- - - - 1,348,240 
- - - - 1,348,240 
291,000 273,000 561,000 1,195,045 8,149,952 
532,403 367,979 407,142 1,245,955 8,024,785 
- - - - 125 
- - - - 125 
2,500 
510 
-83,423 
9,215 
56,378 
5,000 
5,000 
35,171 
2,500 
2,500 
160,000 
160,000 
- 1,825,311 
1,825,311 
- 1,596,577 
- 1,596,577 
- 1,061,137 
3,008 1,040,121 
580,000 
538,942 
199,995,7654 
199,964,5144 
3,839,8245 
3,782,7965 
2,500 
1,600,000 
1,555,354 
904,018 
- 580,000 
- 538,942 
13,900,000 
13,522,702 
538,000 
536,356 
4,656,300 
5,349,609 
718,000 
685,741 
2,031,700 150,600 
1,616,440 522,722 
7,103,000 
7,114,257 
859,000 
938,688 
6,767 
3,478,000 
3,590,751 
913,500 
871,881 
- 2,182,300 
- 2,145,929 
20,000 
5,419 
50,000 
45,420 
132,500 114,000 
15,028 231,472 
115,000 -85,000 
30,000 
20,000 
5,419 
50,000 
45,420 
246,500 
246,500 
30,000 
30,000 
40-9

TABLE 40-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 
COST AND FINANCIAL STATEMENT 
See 
Section :Total to 
In Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
21. Snettisham, AK New Work 
Approp. 570,000 1,499,700 7,997,000 3,505,000 96,954,556 
Cost 1,157,838 1,258,244 8,226,946 3,561,846 96,934,479 
1Includes judgment and associated cost. 
"Includes $2,672 of Code 710 Rec. Funds and $1,509,678 for 
previous project. 
3Includes only actual Funds retained and cost incurred. 
4Includes $310,000 for previous project (Fairbanks). 
5Includes $1,624 for previous project (Fairbanks). 
40-10

ALASKA DISTRICT 
TABLE 40-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
July 3, 1958 
Oct. 22, 1976 
July 14, 1960 
July 14, 1960 
Aug. 15, 1985 
July 3, 1958 
July 2, 1958 
Aug. 19, 1964 
July 14, 1960 
Aug. 13, 1968 
Aug. 13, 1968 
July 14, 1960 
Mar. 2, 1945 
Oct. 27, 1965 
2. 
ANCHORAGE HARBOR, AK 
Deep water harbor, adjacent to docks, dredge to 35 
feet below mean lower low water, protected 
by two jetties.1 
Extension of project limits. 
BETHEL SMALL BOAT HARBOR, AK 
Construct 7,700-foot-long small boat harbor 
and entrance channel by deepening, widening, and 
straightening the upper 6,800 feet of Brown's Slough. 
CORDOVA SMALL BOAT HARBOR, AK 
Construction of 2,000-foot breakwater. 
Payment of judgment and associated interest. 
DILLINGHAM HARBOR, AK 
Basin 230,000 square feet in area with depth of 2 feet 
above mean lower low water along Scandinavian 
Creek, with entrance channel 1,100 feet long and 40 
feet wide. 
HOMER HARBOR, AK 
Basin 2.7 acres in area with depth of 12 feet below 
mean lower low water, and rock breakwater 1,260 feet 
long. 
Relocation and rehabilitation of project destroyed by 
March 27, 1964 earthquake, by construction of basin 
10 acres in area with 12-foot depth over 2.75 acres 
and 15-foot depth over 7.25 acres protected by rock 
breakwaters, 1,018 feet and 238 feet long. 
Increased width and depth of entrance channel and an 
enlarged staging area. Basin enlarged from 16.5 to 
50 acres. 
KAKE HARBOR, AK 
Basin 7-acre berthing area, 15 feet deep, inclosed by a 
1,580-foot west rock breakwater and a 900-foot south 
rock breakwater. 
KING COVE HARBOR, AK 
Anchorage basin of 11 acres, 15 feet deep, an 
entrance channel 125 feet wide and 15 feet deep; 
an earth fill training dike; and a rockfill groin. 
MEKORYUK, AK 
Construction of 510-foot breakwater 
METLAKATLA HARBOR, AK 
Dredging small boat basin 2.18 acres in extent to a 
depth of 10 feet below plane of mean lower low 
water; construction of rubblemound breakwater 900 
feet long. 
Entrance channel and two rubblemound breakwaters 
inclosing a 7.0 acre basin. 
40-11 
H. Doc. 34, 85th Cong., 
1st Sess.2 
P.L. 94-587 
Section 107, P.L. 86-645 
Authorized by Chief 
of Engineers, June 29, 
1978 
Section 107, P.L. 86-645 
Authorized by Chief 
of Engineeers, 
April 23, 1981 
P.L. 98-88 
H. Doc. 390, 84th Cong., 
2d Sess.2 
H. Doc. 34, 85th Cong., 
1st, Sess.2 
P.L. 88-451 
Section 107, P.L. 86-645 
Authorized by Chief 
of Engineers, 
Nov. 13, 1981 
S. Doc. 70, 90th Cong., 
2d Sess.2 
S. Doc. 13, 90th Cong., 
1st Sess.2 
Section 107, P.L. 86-645 
Authorized by Chief 
of Engineers, 
May 7, 1986 
H. Doc. 138, 76th Cong., 
91st Sess. 
Section 201, P.L. 89-298 
S. Doc. 92-64, 92d Cong., 
2d Sess.2 Authorized 
Oct. 12, 1972 
3. 
5. 
6. 
8. 
9.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 
TABLE 40-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
10. NINILCHIK HARBOR, AK 
July 3, 1958 
Aug. 8, 1917 
Aug. 30, 1935 
June 16, 1948 
July 14, 1960 
Dec. 19, 1985 
Aug. 13, 1968 
Dec. 19, 1985 
Dec. 19, 1985 
July 24, 1946 
Oct. 23, 1962 
11. 
H. Doc. 34, 85th Cong., 
1st Sess. 2 
Basin 320 feet long by 150 feet wide with depth of 
2 feet above mean lower low water, approach 
channel 400 feet long and 50 feet wide with depth of 
9 feet above mean lower low water, protected by 
410-foot jetty. 
NOME HARBOR, AK 
Two jetties, easterly 335 feet and westerly 460 feet long 
revetment, channel and basin 200 feet wide and 250 
feet long. 
Extension of the jetties and enlarging basin to 250 
feet wide and 600 feet long.3 
Seawall 
PORT LIONS SMALL BOAT HARBOR, AK 
Construction of a 600-foot breakwater and a 170-foot 
stub breakwater inclosing a 12-acre harbor. 
BETHEL, MISSION ROAD 
EMERGENCY BANK STABILIZATION, AK 
Construct protection stone layer'in front of 
bulkhead piling along Mission Road. 
CHENA RIVER LAKES, AK 
Dam and reservoir on the main Chena River, a dam 
and detention reservoir on the Little Chena River, and 
a levee along the north side of the Tanana River.4 
DILLINGHAM EMERGENCY BANK 
STABILIZATION, AK 
Relocate Water and Sewer Lines 
GALENA EMERGENCY BANK STABILIZATION, 
AK 
Provide approximately 1200 feet of riverbank 
protection in front of the Alexander Lake area. 
KUSKOKWIM RIVER, BETHEL, AK 
Construct rock and riprap mat in front of pile 
structures. 
SNETTISHAM, AK 
Multi-purpose dam, with powerhouse and transmission 
facilities. 
1Purchase of dredge and deepwater jetties deauthorized 
November 6, 1977 under section 12, Public Law 93-251. 
2Contains latest published map. 
3Extension of jetties classified "inactive". 
4Little Chena Dam classified "deferred". 
40-12 
H. Doc. 1932, 64th Cong., 
2d Sess.2 
H. Doc. 404, 71st Cong., 
2d Sess., and Rivers 
and Harbors Committee 
Doc. 38, 73d Cong., 
2d Sess.2 
Report of Chief of 
Engineers dated 
March 8, 1948 
Section 107, P.L. 86-645 
Authorized by Chief 
of Engineers, 
April 9, 1979 
Section 116 of P.L. 99-190 
(H.J.Res. 465) 
S. Doc. 89, 90th Cong., 
2d Sess.2 
Section 116 of P.L. 99-190 
(H.J.Res. 465) 
Section 116 of P.L. 99-190 
(H.J.Res. 465) 
Section 14, P.L. 79-526 
Authorized by Chief 
of Engineers 
Sep. 13, 1985 
H. Doc. 40, 87th Cong., 
1st Sess.2 
12. 
14. 
15. 
16. 
17. 
18. 
21.

ALASKA DISTRICT 
TABLE 40-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Apoon Mouth of Yukon River, AK 1 Completed 1920 $ 128,896 $ 2,154 
Bar Point Harbor, AK2 Completed 1983 2,000,000 - 
Cook Inlet Shoals, AK Completed 1977 1,220,000 5,000 
Cordova Harbor, AK Completed 1978 843,534 488,156 
Craig Harbor, AK Completed 1983 1,033,5004 72,500 
Douglas Harbor, AK Completed 1963 282,019 - 
Dry Pass, AK Completed 1983 943,351 23,466 
Egegik River, AK Completed 1972 4,441 3,107 
Elfin Cove, AK Completed 1959 154,191 - 
Gastineau Channel, AK Completed 1964 789,461 102,701 
Haines Harbor, AK2 Completed 1977 1,000,0005 - 
Hoonah Harbor, AK Completed 1983 4,255,0006 - 
Humboldt Harbor, AK Completed 1977 3,679,683 - 
Iliuliuk Harbor, AK Completed 1941 66,037 - 
Juneau Harbor, AK Completed 1974 1,381,150 260,991 
Kasilof Harbor, AK 2 Completed 1975 109,848 - 
Ketchikan Harbor, AK Completed 1979 1,602,417 331,256 
Kodiak Harbor, AK Completed 1973 1,891,2128 37,946 
Myers Chuck Harbor, AK Inactive 1970 9,700 - 
Naknek River, AK Completed 1961 20,789 - 
Neva and Olga Straits, AK Completed 1960 155,009 - 
Old Harbor, Kodiak Island, AK2 Completed 1972 370,415 132,946 
Pelican Harbor, AK Completed 1964 369,683 18,973 
Petersburg Harbor, AK Completed 1972 252,932 26,800 
Port Alexander, AK Completed 1949 17,000 - 
Rocky Pass, AK Completed 1960 337,668 - 
St. Michael Canal, AK Completed 1916 377,062 560 
Seldovia Harbor, AK Completed 1974 1,051,8839 5,518 
Sergius Whitestone, AK Completed 1973 1,798,010 1,934 
Seward Harbor, AK Completed 1973 712,36910 219,789 
Sitka Harbor, AK Completed 1973 1,611,009 15,490 
Skagway Harbor, AK Completed 1972 133,180 32,665 
Stikine River, AK Completed 1985 - 181,549 
Valdez Harbor, AK Completed 1968 649,74011 221,498 
Wrangell Harbor, AK Completed 1969 537,020 331,352 
Wrangell Narrows, AK Completed 1979 3,562,343 309,260 
1Adandonment recommended in H. Doc. 467, 69th Cong., 
1st Sess. 
2Authorized by Chief of Engineers (Sec. 107). 
3In addition, $272,779 of State funds. 
4Includes $656,240 for Sec. 107 project. 
5In addition, $925,500 of State funds. 
6In addition, $973,875 of State funds. 
7In addition, $857,000 of State funds. 
8Includes $594,163 for rehabilitation. 
9Includes $400,000 for rehabilitation. 
o1 Includes $90,026 for rehabilitation and $2,528 Code 710, 
Recreation Facilities at Completed projects. 
11Includes $73,000 for rehabilitation and $2,713 Code 710, 
Recreation Facilities at Completed projects. 
40-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1985 
TABLE 40-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1986 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Fairbanks, Tanana River & 
Chena Slough, AK Completed 1943 557,000 - 
Gold Creek, AK Completed 1975 876,0061 4,301 
Klutina River, Copper Center, 
AK2 Completed 1973 260,681 - 
Lowell Creek, AK Completed 1945 416,3823 30,771 
Salmon River, AK Completed 1963 37,770 4 5 162,9256 
Skagway River, AK Deferred' 1966 26,385 - 
Talkeetna River, AK Completed 1981 516,694 - 
11n addition, $25,000 expended from contributed funds. 5In addition, $7,000 expended from contributed funds. 
2Authorized by Chief of Engineers (Sec. 205). 6In addition, $27,400 expended from contributed funds. 
3In addition $25,000 expended from contributed funds. 'Project eligible for deauthorization. 
4Includes $34,197 of PWA funds. 
TABLE 40-G DEAUTHORIZED PROJECTS 
Project 
Anchorage Harbor, AK 
(Uncompleted Portion) 
Bradley Lake, AK 
Ketchikan Harbor, AK 
(West Breakwater) 
Port Alexander, AK 
(Inner Harbor) 
Tolovana River, AK 
(Snagging) 
For Last 
Full Report 
See Annual 
Report 
1967 
1983 
1979 
1949 
1931 
Date 
Deauthorized 
1977 
1982 
1979 
1977 
1977 
Federal 
Funds 
Expended 
Contributed 
Funds 
Expended 
$6,701,000 
40-14

ALASKA DISTRICT 
TABLE 40-H NAVIGATION WORK 
UNDER SPECIAL AUTHORIZATION 
Navigation Activities Pursuant to Section 107, Public 
(Preauthorization) 
Study Identification 
Chignik, AK 
Dillingham Small Boat Harbor, AK 
Juneau Harbor, AK 
Larson Bay Small Boat Harbor, AK 
Ouzinkie Small Boat Harbor, AK 
Sand Point, AK 
Saxman, AK 
Seward, AK 
Togiak Harbor, AK 
Whittier, AK
TOTAL 
Law 86-645 
Fiscal Year Costs 
$ 95,558 
27,915 
105,854 
160,913 
37,647 
22,956 
58,840 
14,583 
10,598 
70,626 
$605,490 
TABLE 40-I PROJECT CONDITION SURVEYS 
Name of Project Date Survey Conducted 
ALASKA: 
Bethel Harbor October 1985 
Iliuliuk Harbor October 1985 
Kodiak Channel November 1985 
Craig Harbor January 1986 
Wrangell Harbor January 1986 
Wrangell Narrows February 1986 
Sitka Harbor March 1986 
Hoonah Harbor March 1986 
Skagway Harbor March 1986 
Haines Harbor March 1986 
Dry Pass Channel August 1986 
Port Alexander Channel August 1986 
Port Lions Harbor September 1986 
40-15

BOARD OF ENGINEERS FOR RIVERS AND HARBORS 
The Board of Engineers for Rivers and Harbors is a 
continuing body created by Section 3 of the 1902 River 
and Harbor Act. The board is selected by the Chief of 
Engineers and consists of seven senior engineer officers. 
The Deputy Chief of Engineers normally serves as chairman. 
Five members are division engineers with membership 
rotated among divisions having civil works 
missions. The seventh member, assigned full time to the 
board as Resident Member, also directs the staff in 
carrying out the responsibilities of the board. The board 
meets quarterly or on call of the chairman. 
The board has several statutory duties. It conducts independent 
reviews of Corps survey reports covering 
water resources projects and reports its conclusions and 
recommendations to the Chief of Engineers. The Chief 
of Engineers then forwards the reports with his conclusions 
and recommendations to the Assistant Secretary 
of the Army (Civil Works) for transmission to the Congress. 
The board also conducts independent reviews of 
special reports ordered by the Congress. It considers 
and approves general plans for major modification and 
reconstruction of any lock, canal, canalized river or 
other work for the use or benefit of navigation. 
In addition to its statutory duties, the Chief of 
Engineers has assigned further duties to the board. It 
reviews corps policies and procedures as directed, additional 
special reports for the Secretary of the Army and 
the Chief of Engineers, reports of other Federal agencies 
pertaining to water resources development as directed, 
and conducts a 10-month program of in-service training 
for approximately 15 Corps planners annually - 
generally at GS 12 and 13 levels - in all aspects of 
Federal water resources development. The training program 
helps meet Corps needs for increased numbers of 
qualified people in the planning field. The board also has 
administrative responsibility for processing proposed 
reports of the Chief of Engineers, along with Final Environmental 
Impact Statements, to states and Federal 
agencies for their 90-day review. 
In addition to other duties, the resident member of the 
board has served as second alternate for the Secretary 
of the Army on the Foreign Trade Zones Board. The 
Secretary of the Army has also appointed the resident 
member to serve as his representative on the Committee 
of Alternates of the Foreign Trade Zones Board and 
authorized him to act directly on the secretary's behalf 
on all nondiscretionary matters involving foreign trade 
zones. This appointment relieves the Assistant 
Secretary of the Army for Civil Works of routine duties 
in this regard; however, discretionary matters concerning 
the Foreign Trade Zones Board remain under 
previous delegations of authority. 
Total membership of the board is fixed by law at 
seven. In December 1982, the Chief of Engineers instituted 
a mechanism for predesignating future 
members, based on their time of service as division 
engineers, geographical factors, and other criteria. This 
procedure achieves a wider involvement of division 
engineers and their staffs with the proceedings of the 
board. Members Designate attend and participate in 
meetings of the board, but are not permitted to vote on 
board actions. 
The membership of the board as of September 1, 1986 
was as follows: 
Members: Major General Norman G. Delbridge, Jr., 
Chairman, Deputy Chief of Engineers, 
Casimir Pulaski Building, Washington, 
DC 
Major General Jerome B. Hilmes, Division 
Engineer, Southwestern, Dallas, TX 
Major General George R. Robertson, 
Division Engineer, North Pacific, 
Portland, OR 
Major General Thomas A. Sands, Division 
Engineer, Lower Mississippi Valley, 
Vicksburg, MS 
Brigadier General Ernest Edgar III, Division 
Engineer, South Atlantic, Atlanta, 
GA 
Brigadier General Charles E. Dominy, 
Division Engineer, Missouri River, 
Omaha, NE 
Colonel Robert B. Wilson, Resident 
Member, Board of Engineers for Rivers 
and Harbors, Fort Belvoir, VA 
Members Designate: Brigadier General Joseph Pratt, 
Division Engineer, North Central, 
Chicago, IL 
Brigadier General Charles E. 
Williams, Division Engineer, 
North Atlantic, New York, NY 
Official Board Actions. In compliance with resolutions 
of Congress and instructions from the Chief of Engineers, 
the board completed 28 official report reviews during 
Fiscal Year (FY) 1986. 
The favorable reports category includes favorable 
recommended projects for Federal construction as well as 
projects for solving water resources problems for major 
metropolitan areas, even though they may not include 
recommendations for construction by any agency of the 
Federal government. 
Reports Recommending Favorable for Federal Construction- 
The board recommended 18 projects at an 
estimated total first cost of $1,358,048,000, of which 
$1,307,875,000 is the first cost to the United States. A 
listing of the projects follows: 
Lower Ohio River Navigation, IL and KY 
Papillion Creek and Tributaries Lakes, NE 
Pearl River Basin, MS* 
Guadalupe River and Adjacent Streams, CA 
Slidell-Pearlington, LA and MS 
Fort Pierce Harbor, FL 
Pine Bluff Harbor Expansion, AR 
*Report was too late to be included in FY 85 Report 
41-1

Upper Santa Ana River, CA - Flood Storage Alternatives 
Study 
Martin County, FL 
Twin Valley Lake, MN - Fish and Wildlife Compensation 
Plan 
Guadalupe River, Channel to Victoria, TX 
Wolf and Jordan Rivers and Bayou Portage, MS 
Galveston County Shore, TX 
Arthur Kill Channel, NY and NJ 
Hazard, KY - Local Protection Project 
St. Marys Falls Canal Lock Facilities, MI 
Upper Alameda Creek Urban Study, CA 
Tucson Urban Study, AZ 
Reports Recommending Unfavorably for Federal Construction. 
During FY 1986, the board concurred in the 
unfavorable recommendations of the reporting officers 
for Federal construction on 9 projects: 
Dredged Material Containment, Long Island Sound, 
Drainage Control, CT and NY 
San Diego County Streams, CA 
Raritan River Basin, NJ 
Kissimmee River, FL 
Tennessee-Tombigbee Waterway Corridor Study 
Susquehanna River Basin, NY, PA, and MD 
Six Mile Cypress Slough, FL 
South Yadkin River, NC 
Escambia River, Escambia County, FL 
General Design Memoranda: The board reviewed and 
submitted favorable recommendations on one General 
Design Memorandum during the reporting period: Wears 
Creek, Jefferson City, Missouri. 
During Fiscal Year 1986, the board held five meetings: 
October 30, 1985, March 5 and 6, 1986, April 17, 1986, 
June 4, 1986, and October 7, 1986. 
Since 1902, the board has acted on 8,752 reports, 
recommending favorably on 3,908 and unfavorably on 
4,844. 
41-2

MISSISSIPPI RIVER COMMISSION* 
The Mississippi River Commission (MRC) was 
created by an act of Congress on Jun. 28, 1879. The 
Flood Control Act of May 15, 1928, authorized the 
Flood Control, Mississippi River and Tributaries 
(MR&T) Project. The Commission consists of three 
officers of the Corps of Engineers, one from the former 
Coast and Geodetic Survey (presently the National 
Oceanic and Atmospheric Administration), and three 
civilians, two of whom must be civil engineers. All 
members are appointed by the President with the 
advice and consent of the Senate. 
During the fiscal year the Commissioners were: BG 
Thomas A. Sands, U.S. Army, President, appointed 
May 10, 1985; Mr. Sam E. Angel, appointed Sept. 25, 
1979; Mr. R. D. James, civil engineer, appointed Dec. 
1, 1981; BG Jerome B. Hilmes, U.S. Army, appointed 
Nov. 21, 1983; RA John D. Bossler, NOAA, appointed 
Mar. 14, 1984; BG Robert J. Dacey, appointed May 10, 
1985; COL Dennis B. Bulger served as Secretary of the 
Commission. There is one civilian/engineer vacancy 
due to the death of Mr. Roy T. Sessums on Mar. 10, 
1984. 
The MRC is charged, under direction of the 
Secretary of the Army and supervision of the Chief of 
Engineers, with prosecution of improvements for flood 
control of the Mississippi River and of its tributaries 
and outlets in its alluvial valley, so far as they are 
affected by Mississippi River backwater, between 
Head of Passes, LA (mile 0), and Cape Girardeau, MO 
(1,006 miles AHP-Lower Mississippi mileage 
terminates at mile 954 AHP), and with prosecution of 
improvements in the interest of navigation between 
Cairo, IL (954 miles AHP), and Baton Rouge, LA (234 
miles AHP); and for stabilization of the lower 7 miles 
of the right bank of the Ohio River, to former mouth of 
Cache River. It also is charged with prosecution of 
certain flood control works on the Mississippi River 
and tributaries, as far as they are affected by 
backwater, between Cape Girardeau, MO, and Rock 
Island, IL (1,437 miles AHP), and with prosecution of 
improvements on designated tributaries and outlets 
below Cape Girardeau for flood control, navigation, 
major drainage, and related water uses. Authorized 
operations of the Commission below Cape Girardeau 
are conducted by District Engineers of New Orleans, 
Vicksburg, and Memphis Districts within the areas 
described below, in accordance with approved 
directives and programs and congressional appropriations 
therefor. 
New Orleans District: Mississippi River project 
levees and river channel stabilization as required from 
Head of Passes, mile 0 to 320 AHP, construction of four 
salinity-control structures for fish and wildlife enhancement 
in lower Mississippi River Delta region; 
Bonnet Carre' and Morganza Floodways; maintenance 
and improvements of Mississippi River navigation 
channel from Baton Rouge, LA (mile 234 AHP), to 
mile 320; Baton Rouge Harbor (Devils Swamp); 
navigation improvement of Atchafalaya and Old 
Rivers from Mississippi River to Morgan City; control 
of Old and Atchafalaya Rivers; Atchafalaya Basin 
Floodways; flood control and drainage improvements 
in Bayou Cocodrie and tributaries, in Bayou des 
Glaises, and in Upper Pointe Coupee Loop area; flood 
protection in eastern Rapides and south-central 
Avoyelles Parishes, LA; and freshwater distribution 
from Atchafalaya River to Teche-Vermilion Basins. 
Vicksburg District: Mississippi River project levees 
and river channel stabilization as required from upper 
limits of New Orleans District (mile 320 AHP) in 
vicinity of Black Hawk, LA, to Coahoma-Bolivar 
County line, MS (mile 620 AHP) on left bank, and to 
vicinity of mouth of White River, AR (mile 599 AHP), 
on right bank including south bank Arkansas River 
levee to vicinity of Pine Bluff, AR, and north bank 
levee to vicinity of Tucker on left bank of Plum Bayou, 
AR; bank stabilization in lower 36.1 miles of Arkansas 
River; maintenance and improvement of Mississippi 
River navigation channel between miles 320 and 599 
AHP; Vicksburg and Greenville Harbors; specific fish 
and wildlife facilities in Tensas, Yazoo, and Big Sunflower 
Basins; a streambank erosion control project in 
the Yazoo Basin; flood control and drainage improvements 
in Red River backwater area including leveed 
portion east and west of Black River and south of Red 
River; Jonesville, LA, Boeuf and Tensas Rivers, Bayou 
Macon Basins and tributaries, AR and LA, and Bayou 
Lafourche, LA; Yazoo River Basin, MS, including 
backwater area; Big and Little Sunflower Rivers, 
Deer Creek, and Steele Bayou, MS; and Grand Prairie 
Region and Bayou Meto Basin, AR, including 
provision for agricultural water supply. 
Memphis District: Mississippi River project levees 
and river channel stabilization as required, from 
upper limits of Vicksburg District to north bank of 
Little River diversion channel, MO (1,003 miles AHP), 
a few miles below Cape Girardeau, MO, on right bank, 
and to Cache River diversion channel (967 miles AHP) 
* Authorizing legislation (Tables 42-D and 42-E) is listed at the end of this chapter. All other tables are referenced in text and also appear 
at the end of this chapter. 
42-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
above Cairo, IL, on left bank, including levees and 
revetment on right bank of Ohio River, in Mounds- 
Mound City area, IL; except operations above Cairo, 
IL, do not include channel stabilization on the 
Mississippi River. Maintenance and improvement of 
Mississippi River navigation channel between mile 
599 and 954 AHP and of Memphis Harbor, TN; 
specific fish and wildlife facilities in St. Francis Basin; 
levees in White River backwater area up to vicinity of 
Augusta, AR, and a pumping plant near mouth of 
White River; levees and pumping plants at De Valls 
Bluff and Des Arc, AR; channel improvements in 
Cache River Basin, AR; channel improvements in Big 
Creek and tributaries, AR; improvement works in St. 
Francis River Basin, MO and AR, including 
backwater area improvements in Belle Fountain Ditch 
and Drainage District No. 17, AR; Little River 
diversion channel, MO, and L'Anguille River, AR; 
Wolf River Basin, TN; Obion and Forked Deer River 
Basins, TN; Reelfoot Lake area, including channel 
improvement for Bayou du Chien and Lake No. 9, TN 
and KY; West Kentucky tributaries, KY; Mud Lake 
pumping station, TN; and pumping plants and outlet 
structures in the Cairo-Mounds-Mounds City area, IL. 
Field operations of the Commission restricted to 
levee construction under Sec. 6, 1928 Flood Control 
Act (local interests contributing one-third of costs and 
furnishing rights-of-way) are conducted within the 
following limits by two districts reporting directly to 
the Commission on matters within their jurisdiction- 
St. Louis District: Mississippi River (Sec. 6) levees 
from upper limits of Memphis District to Clemens 
Station, MO (1,254 miles AHP), on right bank, and 
Hamburg Bay, IL (1,215 miles AHP), on left bank, and 
Illinois River from its mouth to mile 120 at Havana, 
IL. Rock Island District: Mississippi River (Sec. 6) 
levees from upper limits of St. Louis District to Rock 
Island, IL (1,437 miles AHP). For work accomplished 
see Table 42-N, page 42-50, Annual Report for 1975. 
MISSISSIPPI RIVER AND 
ALLUVIAL VALLEY BELOW 
CAPE GIRARDEAU, MO. 
Location and description. The Mississippi River 
rises in Lake Itasca, MN, and flows generally 
southerly for 2,340 miles through the central portion of 
United States to empty into the Gulf of Mexico 115 
miles below New Orleans. It is improved for barge 
navigation for 1,832 miles to Minneapolis, MN. The 
Mississippi River and its major tributaries, the 
Missouri, Ohio, St. Francis, White, Arkansas, Yazoo, 
and Red-Old Rivers, drain 1,245,000 square miles in 
all or part of 31 states between the Rocky and 
Appalachian Mountains and part of two Canadian 
provinces. Below Cape Girardeau, MO, 53 miles above 
Ohio River, river bottomlands widen abruptly into an 
alluvial valley of 35,460 square miles which was 
originally subjected to flood overflow. A major part of 
the alluvial valley has been protected from floods by 
levees which confine floodflows within a floodplain 
having an average width of 5 miles. (See map of 
alluvial valley of Mississippi River, scale 1:500,000.) 
Observations made by Mississippi River Commission 
to Sep. 30, 1982, show approximate all-time maximum 
and minimum discharges between levees as follows: 
Cairo to White River, 2,000,000 and 70,000 cubic feet 
per second; thence to Red River, 2,150,000 and 90,000 
cubic feet per second; thence to the Gulf of Mexico, 
1,500,000 and 50,000 cubic feet per second in 
Mississippi River and 660,000 and 11,000 cubic feet 
per second in Atchafalaya River. As the 1927 floodflow 
was not confined between levees, maximum discharges 
recorded do not include entire flow of the 1927 flood, 
maximum of record below White River. High water 
and flood stages usually occur in late winter or early 
spring, but great floods such as that of 1937 occurred 
as early as January. Low water stages generally 
prevail from August to December. Extreme all-time 
ranges in stages recorded at representative gages 
(rounded to nearest foot) are 60 feet at Cairo, 49 feet at 
Memphis, 57 feet at Red River Landing, and 21 feet at 
New Orleans (Carrollton). The river is nontidal above 
Red River Landing where tidal amplitude rarely 
exceeds 0.1 foot during extreme low water. 
Previous projects. For details see page 1944, 
Annual Report for 1932. 
Existing project. The Mississippi River and Tributaries 
Project in the alluvial valley between Head of 
Passes, LA, and Cape Girardeau, MO, provides protection 
from floods by means of levees, floodwalls, 
floodways, reservoirs (in Yazoo and St. Francis 
Basins), bank stabilization, and channel improvements 
in and along the river and its tributaries and outlets 
insofar as affected by backwater of Mississippi River, 
including levee work on the main stem between Cape 
Girardeau and Rock Island. When completed, 23,621 
square miles will be protected from the Mississippi 
River project flood. The project also provides for a 12- 
by 300-foot navigation channel between Baton Rouge, 
LA, and Cairo, IL; for salinity-control structures; and 
for channel realinement and improvement including 
bank stabilization and dikes to reduce flood heights, 
control natural tendency of river to lengthen by 
meandering, and protect levees from being destroyed 
by caving banks. Locations of major main stem 
Mississippi River improvements are shown in Table 
42-A and those for off-main stem tributaries are shown 
in Table 42-B. Pertinent data on dams and lakes are 
shown in Table 42-C. Authorizing and incorporating 
legislation are shown in Tables 42-D and 42-E. 
Summary of presently estimated Federal cost of 
authorized improvements is shown in Table 42-F. 
Construction of the existing project began in 1928 and 
has continued throughout ensuing years. Based on the 
estimated cost of $9,902,820,000 (Cost projected 
through the construction period), and actual 
expenditures through Sep.30, 1986, of $4,143,861,589, 
the entire project is about 78.4 percent complete. 
Recommended modifications. None. 
Local cooperation. The Flood Control Act of 1928. 
42-2

MISSISSIPPI RIVER COMMISSION 
as amended, applies. Such requirements have, in 
general, been complied with by local interests. 
Terminal facilities. See volume 1 of two-volume 
Port Series No. 21, 1979, "Ports on the Gulf Coast of the 
United States," for Baton Rouge and Lake Charles, 
LA; Port Series No. 20, 1981, for New Orleans, LA; 
also folio of Flood Control and Navigation Maps of 
Mississippi River Cairo, IL, to the Gulf of Mexico (53rd 
edition), 1985. 
Project cost. Total allotted for flood control, including 
maintenance charges through Aug. 18, 1941, 
chargeable under authorizations to Sep. 30, 1986, was 
$4,166,358,837. (See Table 42-S.) (See also Tables 42-R, 
42-T, and 42-U for additional financial statements.) 
Operations and results during fiscal year. Commission 
activities: 
The 326th session was held on Sept. 23-27, 1985, on 
board the Motor Vessel Mississippi en route on the 
Mississippi River from Cairo, IL, to Morgan City, LA. 
Bank protection works, levees and channel conditions 
were observed en route. Public meetings were held at 
Cairo, IL; Memphis, TN; Greenville, MS; and Morgan 
City, LA, with approximately 170 people in attendance. 
This session adjourned at Morgan City, LA, at 10:45 
a.m., Sept. 27, 1985. 
The 327th session was held on Apr. 21-25, 1986 on 
board the U.S. MV Mississippi en route on the 
Mississippi River from Cairo, IL, to New Orleans, LA. 
Bank protection works, levees, and channel conditions 
were observed en route. On Apr. 21, 1986, the 
Commission members and staff made a tour of the 
Reelfoot Lake and Tiptonville, TN area. Public 
meetings were held at Cairo, IL; Memphis, TN; 
Vicksburg, MS; and New Orleans, LA, with 
approximately 175 people in attendance at these 
meetings. This session adjourned at 10:10 a.m., Apr. 
25, 1986. 
Records of Proceedings of all sessions of the Mississippi 
River Commission are on file in the office of the 
President. 
Alluvial Valley Mapping 
General. Contoured quadrangles and general maps 
of the alluvial valley are available for departmental 
use and public distribution under prescribed 
regulations. Preparation, revision, and publication of 
quadrangle maps (scale 1:62,500) continued. Roadmap-
type information brochures of principal portions 
of the overall project were published along with 
pamphlets on the subject of flood control and 
navigation. Maps and supplemental data sheets for 
active works were updated and published as required. 
The 1985 (53rd) edition of the folio of flood control 
and navigation maps (scale 1:62,500) covering the 
Mississippi River from Cairo, IL, to the Gulf of Mexico 
was revised and printed. The 1986 folio of flood control 
and navigation maps (scale 1:62,500) covering the 
Atchafalaya River was revised and will be printed. 
Approximately 684 flight-line miles of infra-red 
color; 7,587 flight-line miles of black-and-white aerial 
photography (various scales); 100 flight-line miles of 
color photography; and about 206.75 hours of oblique 
photography were flown along the Mississippi River 
and tributaries in the New Orleans, Vicksburg, and 
Memphis Districts. 
Work accomplished in the Districts: New Orleans 
District-Revisions of Chef Menteur, and Spanish 
Fort, LA, 1:62,500-scale quadrangles and New 
Orleans Area Map, 1:250,000-scale are completed. 
Revision of Breton Sound Map, 1:250,000-scale is 
nearing completion. 
Memphis District-Series conversion of USGS 
1:24,000 scale to 1:62,500 scale quads of Piggott, 
Marmaduke, Kennett, Leachville, Manila, Marked 
Tree, Horseshoe Lake and Tilton are complete. 
Vicksburg District-Series conversion of U.S. Geological 
Survey 1:24,000-scale to 1:62,500-scale quadrangles 
Crowder, MS; Oakland, MS; Grenada, MS; 
Sledge, MS; Horn Lake, MS; Crenshaw, MS; Camden, 
AR; Princeton, AR; and Warren, AR, is in progress. 
Hernando, MS was completed. 1:250,000 scale maps of 
Helena, Greenwood, Jackson, and Natchez were 
printed. 
Floods 
Streamflow observations during the fiscal year 
follow: 
Memphis District-Mississippi River crest stage of 
45.8 feet at Cairo gage on Dec. 5, 1985, and maximum 
discharge of 1,028,000 cubic feet per second, occurred 
on March 5, 1985, at Hickman, KY and crest stage of 
28.9 feet at Memphis on Dec. 8-9, 1985, with maximum 
discharge of 1,110,000 cubic feet per second on Dec. 9, 
1985. 
Vicksburg District-No significant flooding occurred 
in the Vicksburg District during FY 86. Peak stages 
and discharges on the Vicksburg District's reach of the 
Mississippi River were as follows: Arkansas City - 32.5 
feet on Dec. 4, 1985, and maximum discharge of 
1,308,000 cubic feet per second; Vicksburg - 38.7 feet 
on Dec. 16, 1985, and maximum discharge of 1,312,000 
cubic feet per second; and Natchez - 46.3 feet on Dec. 
16, 1985, and maximum discharge of 1,303,000 cubic 
feet per second. 
New Orleans District-On the Mississippi River, the 
Red River Landing gage recorded a maximum stage of 
50.51 feet NGVD on Dec. 17, 1985, and the New 
Orleans gage recorded a maximum stage of 14.40 feet 
NGVD on Dec. 17, 1985. On the Atchafalaya River, the 
Simmesport gage recorded a maximum stage of 33.0 
feet NGVD on Dec. 19, 1985. 
Studies and Investigations 
General investigations. Surveys and reports, 
authorized by laws and by Senate and House Public 
42-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Works Committee resolutions, were made as required. 
Collection and study of basic data continued. Actions 
taken on various requests for modifications of the 
existing project, Mississippi River and Tributaries, 
authorized by the Flood Control Act of May 15, 1928, 
as amended (see Table 42-D), follow: 
West Memphis, AR Feasibility Report-The MRC 
Report dated May 5, 1983, contained recommendations 
for 23.86 miles of channel improvement on Ten and 
Fifteen Mile Bayous, restrictive easements and a 
limited revegetation program and to provide a 10-year 
degree of protection in urban and rural areas. The 
total estimated cost of this recommended improvement 
is $21,300,000 (Oct. 86). 
Helena, AR and Vicinity Feasibility Report--The 
MRC Report dated Dec. 16, 1982, contained recommendations 
for a 225 cfs pumping station, 1.85 miles of 
channel enlargement to contain a 10 year storm and 7' 
x 7' gated culvert at Long Lake. The total estimated 
cost of this improvement is $14,100,000 (Oct. 86). 
Yazoo Backwater Project, Mississippi, Mitigation 
Report. The Chief of Engineers Report dated July 12, 
1984, recommended the acquisition of perpetual landuse 
easements on 11,300 acres of woodlands, or any 
combination of easements and fee title that would 
provide the same level of mitigation for fish and 
wildlife losses associated with the Yazoo Area Pump 
Project. The total estimated cost of this acquisition is 
$4,993,000 (Oct. 85). 
Mississippi and Louisiana Estuarine Areas, Louisiana 
and Mississippi Feasibility Report-The Chief of 
Engineers Report, dated May 19, 1986, contained 
recommendations for a diversion structure through 
the mainline Mississippi River levee adjacent to the 
Bonnet Carre Spillway; inflow and outflow channels; a 
sediment trap; and levee modifications necessary to 
accommodate the diversion structure. Total estimated 
cost of the recommended improvement is $57,000,000. 
Southwest Mississippi Tributaries Basin, MS 
Feasibility Report-The Chief of Engineers Report 
dated June 12, 1986, concurred in the recommendation 
of the President, MRC. No further investigations of 
flooding, bank stabilization erosion, and sedimentation, 
in the Southwest Mississippi are warranted. 
Engineering studies. A research program was 
continued for development of materials and more 
effective and economical design of regulation features 
for placing and stabilizing the Mississippi River in a 
suitable alinement. 
Potamology investigations of river behavior 
continue to be made. Investigations into the major 
cause-and-effect relationships attributable to major 
changes in stage-discharge relationships on the 
Mississippi River as a result of both natural and manmade 
modifications are continuing. 
Mississippi River and Tributaries-Levees 
Operations and results during fiscal year. This 
feature consists of construction of new, and enlargement 
of existing, levees to approved grade and section; 
construction and restoration of levee berms; and construction, 
repair, and maintenance of roads on levees. 
Work accomplished is summarized in Table 42-N and 
further broken down as follows: 
New Orleans District-Enlarged 17.7 miles of levees 
and surfaced 10.3 miles of roads on levees in the Main 
Stem System. See Table 42-K. 
Vicksburg District-Constructed 11.8 mile of 
berms, and enlarged 2.4 miles of levees in the Main 
Stem System. See Table 42-L. 
Memphis District-Constructed 5.9 miles of berms 
in the Main Stem System. See Table 42-M. 
Condition as of Sep. 30. (See Tables 42-K, 42-L, 42- 
M, and 42-N.) There are 1,608.3 miles of levees 
authorized for the Mississippi River below Cape Girardeau, 
of which 1,601.5 are in place with 1,183.6 built to 
approved grade and section. The Main Stem Levee 
System consists of 2,202.1 miles, of which 2,195.3 are 
in place with 1,608.9 miles completed to approved 
grade and section. Included in this system are 
additional levees and structures along the south bank 
of Arkansas River (85.4 miles); along the south bank of 
Red River (59.2 miles, with 59.2 completed); and 449.2 
miles in the Atchafalaya River Basin, with 449.2 in 
place with 280.8 completed to grade and section (see 
Table 42-N). Of the authorized 723.4 miles of berms, 
510.5 are complete. Graveled or hard-surfaced roads 
have been constructed on 1,800.5 miles of these levees. 
There are an additional 1,608.2 miles of authorized 
levees off the main stem, of which 1,117.2 are in place 
with 876.6 to approved grade and section. Berms have 
been completed on 9.8 miles and 800.7 miles of 
graveled or hard-surfaced roads have been constructed 
on the levees. 
For last summary of levee work accomplished under 
Sec. 6, 1928 Flood Control Act, see Table 42-N, pages 
42-50, Annual Report for 1975. 
Mississippi River and Tributaries- 
Channel Improvements 
Operations and results during fiscal year. Dredging: 
Mississippi River Main Stem-(See Table 42-G). 
Work included dredging 29,781,300 cubic yards for 
maintenance of channel and harbor improvements. 
Minimum channel depth of 9 feet was maintained. 
Dredging was done with the following plant: New 
Orleans District, Baton Rouge Harbor (Devil's 
Swamp) was maintained by Unit Price dredge DAVE 
BLACKBURN. Vicksburg District, channel 
maintenance was performed by Government-owned 
dustpan dredge Jadwin and leased cutterhead 
dredge George D. Williams. The MR&T Harbors, 
in the Vicksburg District, maintained were Greenville 
and Vicksburg by leased cutterhead, George 
D. Williams. Memphis District channel maintenance 
dredging was performed by Government-owned 
42-4

MISSISSIPPI RIVER COMMISSION 
dustpan dredge, Burgess, leased cutterhead dredge, 
Natchez, and leased dustpan dredge, Lenel Bean. 
The MR&T Harbor maintained was Memphis 
Harbor (MCKeller Lake). 
Bank revetment and dikes: (See Table 42-H, 42-I, 
and 42-J.) Construction of 13.78 miles of new bank 
revetment and 105,432 squares of concrete mattress, 
for maintenance, along the Mississippi River was completed 
by Government plant and hired labor. Also, 4.26 
miles of new dikes were constructed and 4.76 miles 
required for maintenance. 
In addition, work on tributaries consisted of 1.10 
miles of new bank revetment and 15,599 squares of 
concrete mattress for maintenance. 
Other work performed in the interest of navigation, 
supplementing maintenance dredging on Mississippi 
River between Cairo, IL, and Baton Rouge, LA, included 
removal of snags, wrecks, and obstructions; 
issuance of bulletins by the Vicksburg District providing 
information on available high-water velocities 
at selected locations; maintenance of bulletin boards 
showing daily gage readings at regular MRC gages; 
and contact pilot service furnishing navigation interests 
with latest information and advice on channel 
conditions and navigation interests. Cost of this work is 
given in Table 42-R. 
Condition as of Sep. 30. In carrying out authorized 
channel improvement program between Baton Rouge 
and Cairo, 16 cutoffs were developed between 1933 and 
1942. These, combined with chute channel development 
and alignment improvements, decreased channel 
length between these cities by about 170 miles. 
However, current velocities increased the attack on the 
banks and the river began to regain its length. As a 
result, the net shortening between 1933 and 1962 was 
114 miles of the theoretical 170-mile cutoff. 
There are now in place 865.49 miles of operative 
bank revetment and 215.39 miles of dikes on the lower 
Mississippi River. This amount of channel stabilization 
should prevent the river from regaining much more of 
its length due to meandering. A navigation channel 9- 
by 300-feet is being accomplished by revetment and 
dikes and maintained by dredging as required during 
the low-water season. Due to growing effectiveness of 
channel improvement program, average maintenance 
dredging requirements are steadily being reduced, 
and an increase in navigable depth is being obtained. 
Approximately 99.8 miles of foreshore protection have 
been constructed along the lower Mississippi River. 
There are 65.03 miles of revetment and 5.2 miles of 
dikes on tributary channels as listed in Tables 42-H, 
42-I, and 42-J.
New Orleans District 
ATCHAFALAYA BASIN, LA 
Operations and results during fiscal year. New 
work by hired labor: Real estate activities and 
planning for construction were continued. 
New work by contract: Construction of floodside and 
landside berms and levee enlargement continued on 
the east and west protection levees. One contract on the 
west protection levee was completed over a distance of 
2.3 miles with placement of 144,124 cubic yards; and 
on the east protection levee, one contract was 
completed over a distance of 3.6 miles with placement 
of 359,600 cubic yards during this period. An 
additional 11.9 miles of levee enlargement and 
floodside and landside berms are under construction 
on the west protection levee with placement of 
1,462,364 cubic yards during this period. A contract 
for 5.2 miles of steel sheet piling in the east protection 
levee was completed. Construction of the new Morgan 
City floodwall, north of Brashear Avenue, is 98 percent 
complete. On the east protection levee, two floodwall 
contracts, a total of 4.6 miles, were completed, and one 
contract for 1.1 miles of floodwall is under construction. 
Maintenance by hired labor: Operation and maintenance 
of Bayou Boeuf, Berwick, and Bayou Sorrell 
Locks, Morganza Control Structure, and numerous 
drainage structures as required, condition and operation 
studies, and water control management. 
Maintenance by contract: Contract for a culvert 
replacement at Melville was initiated Dec. 17, 1985, 
and completed Feb. 15, 1986. 
Maintenance dredging was performed, resulting in 
the removal of 1,309,356 cubic yards by one leased 
cutterhead dredge from Berwick Bay harbor between 
Jul. 7 and Sep. 7, 1986. 
Condition as of Sep. 30. Construction was initiated 
Aug. 7, 1929, with commencement of the west protection 
levee from Bordelonville to Hamburg, LA. The 
project is 72 percent complete, based on the current 
estimated Federal cost of $1,423,000,000 and non- 
Federal cost of $8,000,000. Of the 449.2 miles of levees 
and floodwalls authorized for the Atchafalaya system, 
280.8 miles are built to grade. See Table 42-K for 
status of levees. 
Major items remaining to be completed include 
completion of levees to grade and section, channel 
training works in the lower basin, control of 
distribution of flows through Wax Lake Outlet, and 
construction of two freshwater distribution structures. 
Drainage improvements in Upper Pointe Coupee Loop 
area have not been initiated. Approximately 36.7 miles 
of bank stabilization have been placed as shown in 
Table 42-H. 
BATON ROUGE HARBOR 
(DEVILS SWAMP), LA 
Operations and results during fiscal year. Maintenance 
by contract: Dredging for the removal of shoal 
from the entrance channel was performed, resulting in 
the removal of 94,676 cubic yards between Aug. 27 and 
31, 1986. 
42-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Condition as of Sep. 30. Construction of the first 2.5 
miles of the proposed 5.0 miles of channel was initiated 
in January 1958 and completed in July 1959, with 
7,458,086 cubic yards excavated. 
The project is 16 percent complete, based on the 
current estimated Federal cost of $699,200 and cash 
contributions of $650,000. Completion of the remaining 
2.5 miles is dependent on economic justification by 
developments on the initial channel. 
BAYOU COCODRIE AND TRIBUTARIES, LA 
Operations and results during fiscal year. Maintenance 
by hired labor consisted of water control 
management. 
Condition as of Sep. 30. Construction was initiated 
in June 1946 and is 57 percent complete, based on the 
current estimated Federal cost of $26,500,000 and non- 
Federal cost of $323,000. See page 2031, Annual 
Report for 1961, for description of completed work. 
Work required to complete the project consists of 
enlargement of 13.5 miles of upper Bayou Boeuf, 
channel improvement of 25.3 miles of Bayou Cocodrie, 
enlargement of Bayou Courtableau from Washington, 
LA, to the west protection levee, and additional 
culverts through the west protection levee at 100 
percent Federal cost in lieu of the previously 
authorized diversion channel from Washington to the 
Bayou Courtableau drainage structure. 
BONNET CARRE' SPILLWAY, LA 
Operations and results during fiscal year. Maintenance 
by hired labor: Condition and operation 
studies, water control management, and ordinary 
maintenance of the control structure and spillway 
continued. 
Condition as of Sep. 30. Construction of the 
spillway was initiated in Fiscal Year 1929. The control 
structure was completed in 1931, levees were 
completed in 1932, and utility crossings were 
completed in 1936. The cost of the completed work is 
$14,212,200. 
It was necessary to operate the structure to reduce 
flood stages in 1937, 1945, 1950, 1973, 1975, 1979, and 
1983. 
OLD RIVER, LA 
Operations and results during fiscal year. New 
work by hired labor consisted of engineering studies 
and placement of revetment (articulated concrete 
mattress) in the auxiliary structure inflow channel. 
New work by contract: Old River Control Auxiliary 
Structure, Phase II construction was completed Sep. 5, 
1986. Stone bank paving in the auxiliary structure 
outflow channel was completed Mar. 24, 1986, with 
270,815 tons of stone placed. Bank stabilization in the 
inflow channel is 52 percent complete with 175,190 
tons of stone placed during this period. Dredging of 
shoal material from the auxiliary structure inflow and 
outflow channels resulted in the removal of 1,438,089 
cubic yards between Jul. 1 and Sep. 15, 1986. 
Maintenance by hired labor consisted of operation 
and maintenance of the lock and control structures as 
required, condition and operation studies, water 
control management, maintenance of cleared areas, 
levee shaping, operation of a picket boat at the inflow 
channel to the low-sill control structure during high 
river stages, and engineering studies. 
Maintenance by contract: From Sep. 8 to 13, 1986, 
170,000 cubic yards of shoal were dredged from the 
lock forebay, and 22,000 cubic yards of shoal from the 
lock tailbay. 
Condition as of Sep. 30. Construction began September 
1955 and is 96 percent complete based on the 
current estimated Federal cost of $306,000,000. Principal 
items completed are as follows: Low-sill 
structure, June 1959; overbank structure, October 
1959; levees and levee enlargements, October 1963; 
inflow and outflow channels for the low sill structure, 
February 1961; navigation lock completed December 
1962 and opened to navigation March 1963, at which 
time Old River was closed to navigation with a rock 
and earthfill dam; highway approaches and bridge 
over the lock completed March 1965. Approximately 
6.2 miles of bank protection have been constructed at 
the inflow and outflow channels. (See Table 42-H for 
details of bank protection.) 
Principal item remaining to complete the project 
consists of bank stabilization of the inflow channel. 
Vicksburg District 
TENSAS BASIN, ARK AND LA 
Operations and results during fiscal year. 
(a) Boeuf and Tensas Rivers, and Bayou Macon, 
AR and LA. Planning and design were continued on 
project features. The Lake Chicot Pumping Plant and 
related features are complete and in operation, except 
for the Rowdy Bend recreational facility; scheduled for 
award in FY 87, and two future recreational sites. 
(b) Red River backwater area. Planning and 
design continued on project features. All channel work 
required to get flows to the Tensas Cocodrie Pumping 
Plant and gravity structure is complete. The gravity 
structure is complete and the pumping plant is 
scheduled for completion in FY 87. Structural 
mitigation features for this project are scheduled to be 
constructed in FY 87 and FY 88. Design and right-ofway 
acquisition are continuing for the remainder of 
the Tensas-Cocodrie levee enlargement. An 8A 
contract has been completed for construction of the 
1.5-mile connecting channel and drainage structure at 
42-6

MISSISSIPPI RIVER COMMISSION 
the Six Mile Bayou Project. A contract for Sicily 
Island Item 1A is complete. Item 1A includes 1.0 mile 
of levee and a water control structure (two 60" pipes). 
An 8A contract for construction of Item 1B which 
included 2.8 miles of levee, has also been completed. 
Preparation of the Fool River Bayou Pumping Plant 
design document is being initiated. Work on the Below 
Red River Phase II GDM is under way. 
Condition as of Sep. 30. 
(a) Boeuf and Tensas Rivers, and Bayou Macon, 
AR and LA. Channel improvement has been accomplished 
on 741.7 miles of project streams, providing 
major drainage outlets for the tributary areas. Additionally, 
61.0 miles of the Tensas River has been 
cleared and snagged. A Reevaluation report for the 
Tensas River Project, above mile 61.0, and the Mill 
Bayou-Bayou Vidal project has been completed and 
work on the Phase II GDM is under way. 
(b) Red River backwater area. Levees in Tensas- 
Cocodrie area are complete except for levee raising of 
19.0 miles. The work comprised 93.1 miles of new 
levee, excluding 2.1 miles of high ground where no 
levees are required, and 86.9 miles of gravel road on 
levees. Construction of 68.6 miles of levee, Larto Lake 
to Jonesville levee system, has been completed. A levee 
grade reevaluation study for all levee systems in the 
Red River Backwater area was completed in Mar. 
1985. Based on results of that study, work is underway 
to complete enlargement of the Tensas-Cocodrie levee 
system. 
LOWER ARKANSAS BASIN, AR 
Condition as of Sep. 30. Arkansas River levees. A 
total of 56.2 miles of the 61.5 miles of north bank levees 
and all of the 85.4 miles of south bank levees have been 
completed to approved grade and section. These levees 
above mile 36.1 are protected by bank-protection 
works constructed as a feature of project for Arkansas 
River and tributaries, AR and OK. For present status 
of this work, see report of Little Rock District. Below 
mile 36.1, needed bank protection is constructed with 
project maintenance funds. 
YAZOO BASIN, MS 
Operations and results during fiscal year. 
(a) Yazoo City and Belzoni protection works. 
Hired labor forces continued operation and maintenance 
of levees, drainage facilities, and pumping 
plant. 
(b) Greenwood protection works. Hired labor 
forces continued operation and maintenance of pumping 
plant, levees, and drainage facilities. 
(c) Main stem. Construction is complete on the 
Wasp Lake Drainage Structure and levee closure. A 
contract was awarded on Sep. 29, 1986, at a contract 
amount of $1,662,543 for Bee Lake Drainage 
Structure. Planning is underway to provide levee 
closure at Bee Lake. A contract was awarded on Aug. 
22, 1986 for $457,512, for bank stabilization at Site 3 
Greenwood Bendway. 
Channel maintenance. No clearing and snagging 
and herbicide willow control were exercised in the 
Yazoo Basin Main Stem in FY 85. 
(d) Big Sunflower River, etc. A contract is 
scheduled for award on Item 66A, Steele Bayou 
Channel Improvement, Miles 63.0 to 68.7. Plans and 
specifications are being prepared for the next item 
which is scheduled foraward in March 1988. 
(e) Tributaries. Construction: (1) Levees. Levee 
work associated with the last item of work on 
Ascalmore-Tippo Project is proceding with 
approximately 80% complete. Panola-Quitman Levee 
Item C(r) was awarded in FY 83 and is substantially 
complete. Levee work associated with Item 1, Pelucia 
Creek is substantially completed. Pelucia Creek, Item 
1A was awarded September 29, 1986. 
(2) Channels. Removal of a portion of the plug on 
Alligator-Catfish Bayou channel at the site of bridge 
relocations was accomplished. The Alligator-Catfish 
channel enlargement project is now complete except 
for removal of the remaining portion of the plug. 
Controls in Alligator-Catfish channel may be 
necessary prior to removal of the plug. A study is 
under way to evaluate these needs. Construction on the 
remaining channel work on the Ascalmore-Tippo 
Project is under way. 
(3) Bank Stabilization. A construction contract for 
Tillatoba Creek Phase II was completed in Dec. 84. 
The planning of the Pelucia Creek Levee Project, 
printed as Supplement B to the Greenwood Protection 
Works (GDM #1), is complete. Pelucia Creek, Item 1 
contract was awarded Jun. 24, 1985, and is still under 
construction. Pelucia Creek, Item 1A was awarded 
Sep. 30, 1986 at a cost of $897,655. 
Channel maintenance was continued for Yalobusha, 
Little Tallahatchie, and Yocona Rivers; Cassidy, 
David, Burrell, and Bobo Bayous; and Ascalmore 
Creek, by random clearing and snagging and 
herbicide willow control. 
(f) Enid Lake. (See Table 42-C.) The dam and 
appurtenant structures were maintained and operated. 
Rehabilitation of boat channels and snagging and 
clearing of tributary streams in the lake area 
continued. Maximum pool elevation in the lake was 
248.76 feet NGVD on July 4, 1986, when storage in the 
flood control pool was 250,500 acre-feet. Peak 24-hr. 
inflow was 9,100 cubic feet per second on Jun. 6,1986. 
On Sep. 30, 1986, pool elevation was 241.81 feet NGVD 
and storage in the flood control pool was 158,800 acrefeet. 
(g) Grenada Lake. (See Table 42-C.) Construction 
of remaining public-use facilities has been deferred 
pending development of cost-sharing agreements with 
local interests for construction and non-Federal 
operation and maintenance, consistent with projects 
42-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
for which recreation facilities are being constructed 
under the provisions of the Federal Water Project 
Recreational Act of 1965 (Public Law 89-72), as 
amended. Maximum pool elevation in the lake was 
211.92 feet NGVD on July 4, 1986, when storage in the 
flood control pool was 446,100 acre-feet. Peak 24-hour 
inflow was 21,800 cubic feet per second on Jun. 7, 1986. 
On Sep. 30, 1986, the pool elevation was 206.79 feet 
NGVD and storage in the flood control pool was 
305,200 acre-feet. 
Construction of a levee to provide protection to the 
community of Coffeeville from high Grenada Lake 
stages was begun in FY 82. In addition to the levee, 
other features of Coffeeville project include: three 
drainage structures through the levee; portable 
pumps; area rehabilitation; and raising of a town 
street. Construction of the levee and two of the 
drainage structures was completed in FY 82. The 
remaining feature of the Coffeeville project was 
completed in early FY 84. 
(h) Sardis Lake. (See Table 42-C.) The dam and 
appurtenant structures were maintained and operated. 
Clearing of tributary streams in the lake area continued. 
Maximum pool elevation in the lake was 258.36 
feet NGVD on July 2, 1986, when storage in the flood 
control pool was 560,400 acre-feet. Peak 24-hour inflow 
was 15,000 cubic feet per second on June 9, 1986. On 
Sep. 30, 1986, the pool elevation was 241.89 feet NGVD 
and storage in the flood control pool was 184,500 acrefeet. 
An 8-mile reach of the Little Tallahatchie River 
from Sardis Dam to Highway 51 was clogged with 
sediment restricting releases from the lake. This reach 
has been dredged to restore the design capacity of the 
river. Six disposal sites were selected, located in 
upland hill areas to reduce the adverse impact on 
prime agricultural lands along the river and still be in 
compliance with environmental laws and regulations. 
Dredging was completed in August 1982. 
(i) Arkabutla Lake. (See Table 42-C.) The dam and 
appurtenant structures were maintained and operated. 
Clearing of tributary streams in the lake area was 
continued. Maximum pool elevation in the lake was 
227.39 feet NGVD on Jun. 14, 1986, and storage in 
flood control pool was 239,900 acre-feet. Peak 24-hour 
inflow was 20,500 cubic feet per second on Jun. 6, 1986. 
On Sep. 30,. 1986, the pool elevation was 216.51 feet 
NGVD, and storage in the flood control pool was 
83,600 acre-feet. 
(j) Yazoo Basin backwater. The Yazoo Area backwater 
levees are complete, including the backwater 
levee from the Mississippi River levee to the west levee 
of the lower Auxiliary Channel, the Little Sunflower 
River drainage structure, and the connecting channel 
from the Steele Bayou drainage structure to the Big 
Sunflower River. A Phase I GDM was completed in 
FY 82 which addresses rural flooding from ponded 
runoff inside the backwater levee. A GDM for a 
pumping station of 17,500 cfs to reduce this ponding 
was approved Jul. 12, 1985. Later budgetary guidance 
reduced the pumping plant capacity to 10,000 CFS. A 
contract for portions of the inlet and outlet channel 
excavation for the pumping plant was awarded in 
March 1986. Although design on remaining features 
has continued, construction of the pumping plant is 
pending approval of the Assistant Secretary of the 
Army and there is no scheduled expenditure of funds 
beyond FY 86. 
The Satartia area backwater levee is complete. 
Rocky Bayou area levee Item 1A was awarded in 
March 1985. Plans and specifications are being 
prepared for levee Item 1B with award scheduled for 
March 1986. Completed backwater levees will require 
raising to provide the degree of protection intended 
based on the project design flow line developed for the 
Mississippi River following the 1973 flood. 
Four Greentree Reservoirs are now complete. Two of 
the three remaining reservoirs will be constructed 
when funds are appropriated. One reservoir has been 
indefinitely delayed because of right-of-way problems. 
Pumping stations for Greentrees 8 and 3 are under 
construction and will be completed in FY 87. Pumping 
stations for Greentrees 1 & 7 are scheduled for award 
in FY 87. 
(k) Upper Yazoo projects. The first seven items of 
work, approximately 54 miles of channel improvement 
has been completed. This work extends from Yazoo 
city to about 15 miles upstream of Belzoni, MS. About 
1.6 miles of channel enlargement along the Belzoni 
Front was skipped until bank stabilization problems 
at this location were resolved. 
The next item of work, Item 2-B, consisting of the 1.6 
miles of channel improvement and bank stabilization 
along the Belzoni Front that was previously skipped is 
now under construction. Planning is continuing on 
upstream channel and levee work. 
(1) Streambank erosion control. Construction of 
the following projects has been completed: Tillatoba 
and Hunter Creeks, Items 1 and 2; Hunter Creek 1A; 
South Fork Tillatoba Creek, Items 5A and 5B; North 
Fork Tillatoba Creek, Items A and 3A; Batupan 
Bogue, Items 4A, 4A-1, and 4A-2; Perry Creek, Items 
6A and 6B; Johnson Creek, Items 9A, 9B, and 
vegetative treatment, Item 12; Goodwin Creek, Items 
8A, 8B, and 8C; and Hotopha Creek, Item 7. 
All construction under this feature is complete, and 
a final report was submitted to the Secretary of the 
Army Jan. 5, 1982. All work constructed has been 
turned over to the local sponsors for operation and 
maintenance except for the instrumented system on 
Goodwin Creek where the structures were retained for 
possible future studies. The Demonstration Erosion 
Control Project (DEC), a joint project with the USDA 
Soil Conservation Service was initiated by FY 85 
appropriations and continued in the same manner in 
FY 86. The purpose of the project is to demonstrate the 
applicability of a systems approach to the design of 
erosion, sedimentation, and flood control works by 
applying this approach to six demonstration watersheds 
in the Yazoo Basin Hill area. 
Condition as of Sep. 30. The first feature of Yazoo 
Basin project was started in 1936, and the total project 
42-8

MISSISSIPPI RIVER COMMISSION 
is about 35 percent complete. A total of 50.9 miles of 
backwater levee has been completed to the interim 
grade. The ongoing Yazoo Basin Comprehensive Study 
will address other water resources problems and needs 
in the area to include urban and rural flood damage 
prevention, hydropower, and water supply. During 
FY 86, considerable progress was made in the DEC 
toward development of the systems plans and 
implementation of a monitoring program. The district 
completed construction of two major grade control 
structures and 41,900 linear feet of bank stabilization. 
Construction of five major grade control structures 
and 28,700 linear feet of bank stabilization was 
initiated during the year. 
LOWER RED RIVER-SOUTH BANK 
RED RIVER LEVEES, LA 
Operations and results during fiscal year. New 
work by hired labor consisted of engineering studies. 
Maintenance by hired labor consisted of water 
control management and economic studies. 
Condition as of Sep. 30. Construction was initiated 
in FY29 and is 90 percent complete, based on the 
current estimated cost of $42,000,000. All of the 59.2 
miles of levees authorized, are complete to approved 
grade and section. (See Table 42-L for status of levees 
and Table 42-I for status of revetments. 
Memphis District 
ST. FRANCIS BASIN, AR AND MO 
Operations and results during fiscal year. 
(a) Little River Drainage. Channel Improvement, 
Castor River, Item No. 2, Transition Reach awarded 
Oct. 31, 1985, completed Jan. 24, 1986. 
(b) Upper St. Francis River. Ditch 251 channel 
cleanout awarded Jul. 9, 1985, completed Dec. 18, 
1985. Upper Ditch 1 channel cleanout awarded Jun. 
26, 1985, completed Mar. 18, 1986. Ditch 81 channel 
cleanout awarded Jun. 28, 1985, completed Dec. 24, 
1986. Stateline Ditch channel cleanout awarded May 
17, 1985, 68 percent complete. Drainage Ditch 17 
Storage Building awarded May 6, 1985, completed 
Feb. 24, 1986. Highway 181, Ditch 29, bridge 
alterations awarded Jul. 12, 1985. Highway 18 
alterations awarded Dec. 12, 1984, completed Jul. 22, 
1986. Upper Buffalo Creek Bridges 30.70 and 33.04 
awarded Jul. 31, 1985, completed Apr. 25, 1986. Upper 
Buffalo Creek Bridges 29.65 and 34.10 awarded Jul. 
29, 1985, completed Apr. 9, 1986. Belle Fountain 
Ditch, alteration of Missouri State Highway NN 
bridge awarded Jul. 16, 1986, 1 percent complete. 
State Line Ditch 29 alteration of Arkansas State 
Highway 181 bridge awarded Jul. 12, 1985, 70 percent 
complete. Upper Buffalo Creek alteration of Missouri 
State Highway 164 and N awarded Jun. 27, 1985, 60 
percent complete. State Line Outlet Ditch alteration of 
Arkansas Highway 18 awarded Jan. 3, 1984, 
completed Jul. 22, 1986. Upper Buffalo Creek channel 
enlargement awarded Sep. 23, 1986, 1 percent 
complete. Alternation of railroad bridge, Item No. 2, 
Blackfish Bayou awarded Aug. 10, 1984, completed 
Aug. 27, 1986. Alteration of Arkansas State Highway 
119, Upper Buffalo Creek, awarded Aug. 29, 1983, 78 
percent complete. 
(c) Lower St. Francis River. Upper Buffalo Creek 
Alterations of Highways 77 and 119 awarded Aug. 29, 
1983, 90 percent complete. Huxtable Access Road 
awarded Sept. 17, 1985. Helena Floodwall awarded 
Aug. 23, 1985. Blackfish Bayou Item 2 awarded Jun. 
28, 1985, completed Jul. 2, 1986. Ditches 9 and 10 
awarded Jun. 13, 1985, completed Jul. 3, 1986. 
Blackfish Bayou Item 2 Railroad Bridge awarded 
Aug. 10, 1984, completed Aug. 2, 1986. Asphalt 
surfacing, W. G. Huxtable Pumping Plant, awarded 
Sep. 22, 1986, 1 percent complete. Repair oil and water 
leakage, W. G. Huxtable Pumping Station, awarded 
Oct. 25, 1985, completed Apr. 20, 1986. Outlet channel 
scour repair, W. G. Huxtable Pumping Plant, awarded 
Oct. 11, 1985, 31 percent complete. Reconstruction of 
access road, W. G. Huxtable Pumping Station, 
awarded Sep. 17, 1985, completed Dec. 21, 1985. Big 
Lake Floodway, ditch bank repair, awarded Sep. 23, 
1986, 1 percent complete. Bank repair, Ditch No. 81, 
Big Lake area, awarded Sep. 23, 1986, 1 percent 
complete. Castor River bank repair, Missouri flood 
control, awarded Aug. 22, 1986, 75 percent complete. 
Riprap stone protection at Arkansas State Highway 
139, Big Slough Drainage Ditch, awarded Jan. 22, 
1985, 95 percent complete. 
Condition as of Sep. 30. 
(a) Little River Drainage. Project was initiated 
during 1938 and is 76 percent complete. 
(b) Upper and Lower St. Francis River and 
Tributaries. Project was initiated during 1937 and is 
78 percent complete. 
WHITE RIVER BACKWATER LEVEES 
Operations and results during fiscal year. 
(a) Graham Burke cleaning and painting awarded 
Sep. 26, 1984, completed Mar. 28, 1986. Water service 
to Graham Burke Pumping Station, awarded Aug. 20, 
1986, 1 percent complete. 
Condition as of Sep. 30. 
(a) Graham Burke Pumping Plant, metallizing 
impellers and exhaust system, awarded Sep. 17, 1982, 
was completed Sep. 29, 1983. 
LOWER WHITE RIVER 
Operations and results during fiscal year. 
(a) Augusta to Clarendon Levee. There were no 
42-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
contracts awarded or completed during the fiscal year. 
(b) Clarendon Levee. There were no contracts 
awarded or completed. 
Condition as of Sep. 30. 
(a) Augusta to Clarendon Levee. Project was 
initiated during 1946 and is 39 percent complete. 
(b) Clarendon Levee. Project was initiated during 
1972 and is 36 percent complete. 
CACHE BASIN, AR 
Operations and results during fiscal year. No 
contracts awarded or completed during the fiscal year. 
Condition as of Sep. 30. Project was initiated 
during 1971 and is 4 percent complete. 
REELFOOT LAKE-LAKE NO. 9, TN AND KY 
Operations and results during fiscal year. No 
contracts awarded or completed during the fiscal year. 
Condition as of Sep. 30. Project was initiated 
during 1974 and is 89 percent complete. 
WEST TENNESSEE TRIBUTARIES, TN 
Operations and results during fiscal year. 
(a) Obion River, TN. South Fork-Forked Deer 
River awarded Aug. 22, 1985. Obion River Channel 
Improvement awarded Aug. 29, 1984, was completed 
Aug. 9, 1986. Obion Rivers channel improvement is 59 
percent complete. 
(b) Forked Deer River, TN. Fowlkes Channel Item 
1-1 on the South Fork was awarded Aug. 22, 1985. 
Forked Deer River channel improvement was 
completed Apr. 17, 1986. 
Condition as of Sep. 30. West Tennessee Tributaries 
Project is 41 percent complete. Work resumed in Sep. 
1985 after having a court injunction lifted in May 
1985. 
WEST KENTUCKY TRIBUTARIES, KY 
Operations and results during fiscal year. No 
contract awarded or completed during fiscal year. 
Condition as of Sep. 30. Project was initiated 
during 1978 and is 4 percent complete. 
MISSISSIPPI RIVER LEVEES 
Operations and results during fiscal year. 
(a) L-10 AC Cairo awarded Sep. 27, 1985. Birds 
Point-New Mardid awarded Aug. 21, 1985, completed 
Oct. 13, 1986. Seepage control-Parcel 3 Cairo Mound 
City Jun. 25, 1985, completed Sep. 12, 1986. Seepage 
control R05AC Parcel I Cairo, Mound City awarded 
Aug. 27, 1984, completed Jul. 18, 1986. Caruthersville 
floodwall repairs awarded Mar. 27, 1984, completed 
Dec. 6, 1984. L-628 Rena Lara Coahoma awarded Sep. 
30, 1985. Levee roadway resurfacing, Point Pleasant, 
MO, awarded Sep. 26, 1986, 1 percent complete. Levee 
roadway resurfacing, Concord, MO, awarded Sep. 22, 
1986, 25 percent complete. Levee roadway resurfacing, 
Cottonwood Point, MO, awarded Sep. 23, 1986, 5 
percent complete. Wave wash repairs, Parcel I, below 
Hickman, KY, awarded Nov. 12, 1985, completed Sep. 
16, 1986. Floodwall alterations, Hickman Floodway, 
awarded Oct. 24, 1985, 80 percent complete. Levee 
work, Item No. L-101, Parcel 2, above Cairo, awarded 
Sep. 27, 1985, 51 percent complete. Levee work, 
seepage control, Parcel 3, Cairo Mound City, awarded 
Jun. 25, 1985, completed Sep. 12, 1986. Levee work, 
seepage control, Parcel I, Cairo-Mound City, awarded 
Aug. 27, 1984, completed Aug. 25, 1986. Nash Relief 
Wells, Parcel I, Cape Girardeau, MO, awarded Mar. 
30, 1984, 92 percent complete. Levee work, Item R-678, 
Walnut Bend, AR, awarded Jul. 16, 1986, 96 percent 
complete. Construction of a chemical storage facility, 
Ensley Engineering Yard, Memphis, awarded Dec. 
11, 1985, completed Aug. 28, 1986. Excavation of 
drainage ditches, Rena Lara, MS, awarded Sep. 20, 
1985, completed May 31, 1986. Helena Floodwall 
repairs, Helena, AR, awarded Aug. 23, 1985, 
completed Dec. 9, 1985. Levee work, Lambethville, 
awarded May 31, 1984, completed Sep. 30, 1985. 
42-10

MISSISSIPPI RIVER COMMISSION 
TABLE 42-A MISSISSIPPI RIVER IMPROVEMENTS 
Mileage 
Above Head 
of Passes Locality Improvement Remarks 
0-9571 Head of Passes, LA-Cairo, IL Dredging, revetment, and 
10-81 
11-25 
38 
45 
59 
75 
44-91 
81-96 
91-104 
96-279 
101-234 
127-129 
235 
279-287 
287-303 
303-314 
306-572 
437 
437-721 
490 
537 
646 
605-666 
672-993 
722-725 
721-734 
contraction work 
Main line levee, right bank 
Main line setback, left bank 
The Jump-New Orleans, LA 
Baptiste Collette-Bayou Ostrica, 
LA 
Homeplace, LA 
Bohemia, LA 
Myrtle Grove, LA 
Caernarvon (Scarsdale), LA 
Bohemia, LA-New Orleans, LA 
New Orleans, LA 
New Orleans, LA 
New Orleans-Morganza, LA 
New Orleans-Baton Rouge, LA 
Bonnet Carre Floodway, LA 
Baton Rouge Harbor 
Morganza Floodway, LA 
Morganza-Old River, LA 
Old River, LA control 
Old River-Cypress Creek, AR 
Vicksburg Harbor, MS 
Vicksburg-Lake View, MS 
Wilson Point, LA 
Greenville Harbor, MS 
Long Lake, Helena, AR 
Henrico-Helena, AR 
St. Francis River-Commerce, 
MO3 
Industrial levee (Ensley Bottoms) 
Memphis Harbor, TN 
Salinity control structure, right 
bank 
Salinity control structure, left bank 
Salinity control structure, right 
bank 
Salinity control structure, left bank 
Main line levee and floodwall, left 
bank 
Main line levee, right bank 
Main line levee and floodwall, left 
bank 
Main line levee, right bank 
Main line levee and floodwall, left 
bank 
Regulating spillway, left bank 
Devils Swamp barge channel 
Regulating spillway, right bank 
Main line levee, right bank 
Levee closure and enlargement, 
low and high water spillway 
structures, navigation lock, and 
approach channels, right bank 
Main line levee, right bank 
Harbor extension and industrial 
fill 
Main line levee, left bank 
Pumping Plant and drainage 
structure, right bank 
Harbor improvements and port 
area 
Culvert and floodgate, right bank 
Main line levee and floodwall, right 
bank 
Main line levee, right bank 
Levee and pumping station 
Closure of Tennessee Chute, 
industrial fill, levee, harbor 
channels, etc. 
42-11 
Authorized by Public Law 
89-298 (HD 308/74/1). 
Included in MS Delta 
Region, LA feature. 
Authorized by Public Law 
89-298 (HD 308/74/1). 
Included in MS Delta 
Region, LA feature. 
Authorized by Public Law 
89-298 (HD 308/74/1). 
Included in MS Delta 
Region, LA feature. 
Authorized by Public Law 
89-298 (HD 308/74/1). 
Included in MS Delta 
Region, LA feature. 
Authorized by Public Law 
81-516. 
Authorized by Public Law 
81-516. 
Modified by Public Law 
87-874. 
Extends up south bank of 
Old River to Barbre 
Landing. 
Authorized by Public Law 
83-780. 
Joins Arkansas River, south 
bank levee. 
Authorized by Public Law 
70-391. Modified by Public 
Laws 79-526 and 83-780. 
Unpublished Vicksburg 
District's MRC report 
approved Apr. 14, 1966.2 
Authorized by Public Law 
85-500. 
Authorized by Public Law 
79-526.2 
Authorized by Public Law 
79-526.

TABLE 42-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
MISSISSIPPI RIVER IMPROVEMENTS 
Mileage 
Above Head 
of Passes Locality Improvement Remarks 
803-873 Tiptonville-Obion River Main line levee, left bank, levee Modified by Acts of Jul. 24, 
extension, and diversion Obion 1946 and Dec. 23, 1971. 
River 
857 Near Mud Lake, TN Pumping station and adjacent Authorized Dec. 15 and 17, 
channel improvements 1970 under Sec. 201 of Oct. 
27, 1965 FC Act. 
890 St. Johns Bayou, MO Drainage floodgate and levee Modified by Jul. 24, 1946 
closure Act. 
890 New Madrid Floodway, MO Drainage floodgate and levee Modified by Sep. 3, 1954 
closure Act. 
890-954 New Madrid-Birds Point, MO Floodway, right bank 
902-922 Slough Bend, Hickman, KY Main line levee, left bank 
922 Hickman, KY Floodwall, left bank 
946 Peafield, MO Drainage floodgate Authorized by Sep. 3, 1954 
Act. 
9571 Cairo, Cairo drainage district Floodwalls and levees 
9571 Cairo, Cairo drainage district, Floodwalls, levees, and pumping 
Mounds, Mound City, and plant 
vicinity 
Thebes-Rock Island, IL Levees, both banks Intermittent (Sec. 6). 
Cape Girardeau, MO to Rock Levees Intermittent (Sec. 6). 
Island, IL 
1. Cairo, IL, is on Ohio River about 3 miles above its 
mouth (Mississippi River mile 954 AHP). 
2. Also see Table 42-D, "Authorizing Legislation." 
3. Commerce, MO, is on 
miles above mouth of Ohio RivE
Upper Mississippi River, 39 
42-12

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
0-54 
27-54 
54-117 
20-27 
25-117 
27 
0-27 
31-57 
80 
53-117 
117 
117-129 
117-129 
105 
105-120 
115 
116 
5 
5-105 
29 
29 
40 
40 
40 
Floodway 
Floodway 
Floodway 
ATCHAFALAYA BASIN, LA' 
Atchafalaya Basin. Morganza 
and West Atchafalaya 
Floodways 
West Atchafalaya Floodway 
between Red River and 
Alabama Bayou 
Morganza Floodway between 
Mississippi River and Alabama 
Bayou 
Atchafalaya Basin Floodway 
between Alabama Bayou and 
Morgan City 
East protection levee (Morganza 
and Atchafalaya Floodways) 
Lacour-Red Cross 
Morganza-Morgan City 
Bayou Latenache 
Upper Pointe Coupee Loop area 
Bayou Fordoche-Ramah 
Bayou Sorrel' 
Bayou Sorrel Lock-Morgan City 
Morgan City 
Below Morgan City 
Below Morgan City 
Atchafalaya Basin Floodway 
lower protection levee 
Calumet 
Below Morgan City 
Berwick' 
Patterson 
West protection levee (Atchafalaya 
Basin and West Atchafalaya 
Flood ways) 
Simmesport-Hamburg 
Mansura to Wax Lake Outlet 
Coulee des Grues 
West Atchafalaya Floodway 
Morganza Floodway 
Bayou Darbonne 
West Atchafalaya Floodway 
Morganza Floodway 
Including lower Morganza 
Floodway guide levee. 
Through upper Morganza 
guide levee and enlargement 
of outlet channel. 
Enlargement of Bayou 
Latenache. Approved Jun. 
4, 1970. See Table 42-D. 
Levee landside borrow pit. 
Alternate route, Gulf 
Intracoastal Waterway 
Port Allen to Morgan City. 
Gulf Intracoastal Waterway 
utilizes levee west side 
borrow pit channel. 
Gulf Intracoastal 
Waterway. 
Bypass route for Gulf 
Intracoastal Waterway. 
East of lower river. 
Bayou Teche-Wax Lake 
Outlet. 
Inclosed area between Wax 
Lake Outlet and Berwick. 
Lower Atchafalaya River. 
Adjustment to provide fresh 
water. 
West Atchafalaya 
Floodway. 
Through West Atchafalaya 
protection levee. 
42-13 
Levee, upper Morganza guide 
Levee and Morgan City floodwall 
Drainage structure, Pointe Coupee, 
and channel enlargement 
Additional drainage facilities 
Drainage channel 
Lock 
Alternate navigation channel, Gulf 
Intracoastal Waterway 
Lock in Bayou Boeuf' 
Channel relocation 
Levee, floodwall 
Floodgate, east 
Levees, floodwall, drainage 
structures, and pumping plants 
Lock 
Water system 
Levee fuse plug 
Protection levee 
Levee enlargement and floodgate 
extension 
Railway 
Railway 
Gated drainage structures 
Highway 
Highway

TABLE 42-B 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
41 
41 
41 
94 
94 
105 
105 
0-54 
5-6 
5-66 
28-30 
40-41 
54-117 
94-106 
Mileage 
Above 
Mouth 
0-8 
50-133 
96 
133 
0-17 
17-40 
40-51 
51-60 
17-42 
87-107 
40 
60 
Bayou Courtableau 
West Atchafalaya Floodway 
Morganza Floodway 
Charenton 
Jaws-Lake Fausse Pointe 
Calumet 
Wax Lake Outlet 
Atchafalaya River 
Barbre Landing-Alabama Bayou 
Simmesport 
Simmesport-Bayou Garofier 
Melville 
Krotz Springs 
Below Alabama Bayou 
Mississippi River-Morgan City 
TECHE-VERMILION BASINS, 
LA 
Atchafalaya River to Teche- 
Vermilion Basins 
Courtableau Basin, LA, and 
outlets 
Charenton Canal 
West Atchafalaya protection levee 
borrow pit channel 
Bayou Courtableau spillway 
Bayou des Glaises 
BAYOU COCODRIE AND 
TRIBUTARIES 
Bayou Courtableau 
Bayou Cocodrie 
Bayous Cocodrie-Bouef diversion 
Bayou Boeuf 
Bayous Boeuf-Rapides diversion 
Upper Cocodrie 
Bayou Boeuf 
Bayou Lamourie to Kincaid 
Structures 
Lecompte Control Structure 
Bayou Rapides Control Structure 
Enlargement, realinement, 
clearing and snagging 
Fixed elevation weir 
Gated drainage structure 
42-14 
Gated drainage control structures 
and channels 
Railway 
Railway 
Floodgate and approach channels 
Outlet, Charenton drainage canal 
and protection levee. 
Floodgate, west 
Drainage canal-railway and 
highway bridges 
East bank, levee 
Levee, ring, and drainage structure 
West bank, levee 
Levee, ring 
Levee, ring 
Channel enlargement 
12- by 125-foot navigation channel 
Pumping station above Krotz 
Springs, conveyance channels, 
and appurtenant works 
Drainage channel 
Drainage channel 
Drainage control structure 
Diversion channel 
Enlargement and additional 
culverts 
Enlargement and realinement 
New channel 
New channel 
New channel 
Enlargement, clearing, and 
snagging 
Borrow pit channel to 
Grand Lake through West 
Atchafalaya protection 
levee. 
Restoration of drainage 
west of West Atchafalaya 
Basin protection levee. 
Bayou Teche and Wax Lake 
Outlet. 
To lower flood heights. 
Increase channel capacities 
to decrease flood heights. 
Through Grand and Six 
Mile Lakes. 
Freshwater distribution 
from Atchafalaya River to 
Teche-Vermilion Basins. 
Outlet to gulf. 
Intercepting drainage 
channel. 
Washington to west 
protection levee.

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
Bayou Lamourie Control 
Structure 
Various 
LAKE PONTCHARTRAIN, LA 
Lake Pontchartrain, Jefferson 
Parish, LA 
AMITE RIVER, LA 
Amite River, LA 
LOWER RED RIVER, SOUTH 
BANK, RED RIVER LEVEES, 
LA 
Moncla-Hotwells 
Red River-Moncla to Lake Long 
EASTERN RAPIDES AND 
SOUTH-CENTRAL 
AVOYELLES PARISHES, LA 
Eastern Rapides and southcentral 
Avoyelles Parishes, LA 
TENSAS BASIN, AR AND LA 
Red River backwater area 
Tensas-Cocodrie area 
Larto Lake-Jonesville 
Sicily Island area 
Below Red River area 
Black River, LA 
Six Mile Bayou area 
Jonesville, LA 
Ouachita River 
Boeuf and Tensas Rivers and 
Bayou Macon, AR, and LA 
Boeuf River, AR, and LA 
Below Bayou La Fourche 
Bayou LaFourche 
Boeuf River, AR, and LA above 
Bayou LaFourche 
Canal 19 
Canal 19 extension 
Big and Colewa Creeks 
Gated drainage structure 
Railway, highway, and local road 
bridges, and pipeline crossing 
(2, 3) Flood protection 
Bank protection 
Levee, south bank 
Levees 
Flood protection and drainage 
improvement 
Levees, drainage channels, 
structures, and pumping plant 
Levees, drainage channels, and 
structures 
Levees, drainage channels, 
structures, and pumping plants 
Levees, drainage channels, 
structures, and pumping plants 
Drainage structure and 
appurtenant channel works 
Levees, floodwall, pumping plant, 
and interior drainage 
Levees, drainage channels, and 
structures 
Clearing 
Channel improvement and 
realinement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvements 
Authorized by Public Law 
81-516. Eliminated by 
Public Law 89-298. 
Intermittent (Sec. 6). 
Authorized by Public Law 
91-611. 
(4) 
(4) 
(4) 
(4) 
Unpublished VXD-MRC 
Letter Report dated May 
31, 1977. MR&T 
authority. 2 
Portion of levee built under 
Sec. 6. Incorporated in 
MR&T by Public Law 
81-516.2 
Monroe to Sandy Bayou and 
Bawcomville (Sec. 6). 
(5) 
(5) 
Authorized by Public Laws 
78-534 and 79-526. 2, 3 
(5) 
(6) 
Authorized by Public Law 
78-534. 3 
42-15 
87 
82-145 
3-56 
3-56 
5 
56 
0-32 
0-56 
151-235 
210-286 
286-296 
0-75

TABLE 42-B 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
0-8 
0-7 
0-33 
0-10 
0-9 
0-14 
0-170 
0-34 
0-35 
Lake Chicot 
0-6 
0-160 
0-16 
0-0.2 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
To divert flows from Lake Chicot 
Tributaries of Boeuf River- 
Canal 19 
Fleschmans Bayou 
Caney Bayou 
Big Bayou 
Canal 18 
Kirsch Lake Canal 
Black Pond Slough 
Bayou Macon, AR, and LA 
Bayou Macon 
Canal 43 
Canal 81 
Pumping plant and drainage 
structure 
Tributary of Bayou Macon 
Rush Bayou 
Tensas River, AR and LA 
Tensas River 
Tributary of Tensas River 
Mill and Vidal Bayous 
Grant's Canal, LA 
Grant's Canal at Lake Providence 
LOWER ARKANSAS RIVER, 
AR 
Yancopin-Pine Bluff 
Fletcher Bend, AR to Pine Bluff 
North Little Rock to Gillett (below 
Plum Bayou) 
GRAND PRAIRIE-BAYOU 
METO, AR 
Grand Prairie Region and Bayou 
Meto Basin, AR 
YAZOO BASIN, MS 
Yazoo Backwater area 
Yazoo River System below 
Arkabutla Lake 
Yazoo River between Yazoo City 
and Prichard 
Yazoo River between Yazoo City 
and Askew 
Will M. Whittington Auxiliary 
Channel 
Yazoo City protection 
Rocky Bayou area 
Belzoni protection 
Greenwood protection 
Arkabutla Lake 
Channel improvement 
Channel improvement 
Filling canal 
(6) 
(6) 
(5) 
(6) 
(6) 
(6) 
See Table 42-E
(5) 
(5) 
Authorized by Public Law 
90-483. 
(6) 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
89-298. 
Authorized by Public Law 
81-516. 
Levee, south bank 
Revetment 
Levee, north bank (5) 
Water supply and drainage 
improvements 
Levees and pumping plants 
Channel improvement 
Levees, right bank 
Levees, left bank 
Floodway channel 
Levee, drainage structure, and 
pumping plant 
Channel clearing and enlargement 
Levee and floodwall 
Levees, channel improvement, 
drainage structures, and pumping 
plants 
Flood detention and conservation 
Authorized by Public Law 
81-516. 
Including Tallahatchie and 
Coldwater Rivers. 
Intermittent. 
Intermittent. 
Improvement of 7.8 miles 
was approved Apr. 29, 
1970. 
See Table 42-C. 
42-16 
Clearing 
23-98 
35-98 
48-102 
0-75 
0-381 
75-366 
75-345 
45-109 
75 
127 
185 
381

TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River 
0-64 
64 
0-24 
0-26 
26 
0-13 
13 
0-88 
137-260 
75-381 
0-8.3 
0-23 
0-42 
275-290 
0-204 
0-8 
0-28 
0-81 
0-43 
0-4 
0-27 
153-160 
0-68 
13-55 
0-68 
99 
Locality 
Yalobusha River below Grenada 
Lake 
Grenada Lake 
Tallahatchie River-Little 
Tallahatchie River 
Little Tallahatchie River below 
Sardis Lake 
Sardis Lake 
Yocona River below Enid Lake 
Enid Lake 
Cassidy Bayou below Old 
Coldwater River 
Upper Yazoo Projects 
Area between main stem and hills 
including Bobo Bayou 
McKinney Bayou 
Alligator-Catfish Bayous 
Bear Creek 
Whiteoak Bayou 
Tallahatchie River, MS 
Big Sunflower River, etc. 
Big Sunflower River 
Hull Brake-Mill Creek Canal 
Hushpuckena River 
Quiver River 
Gin and Muddy Bayous, MS 
Bogue Phalia 
Ditchlow Bayou 
Little Sunflower River 
Deer Creek 
Steele Bayou 
Muddy Bayou 
LOWER WHITE RIVER AND 
BASIN, AR 
Laconia Circle-Old Town Lake 
Big Creek and tributaries 
Clarendon levee 
42-17 
Improvement 
Channel improvement 
Flood detention and conservation 
Levees, Panola-Quitman Floodway 
Channel improvement 
Flood detention and conservation 
Channel improvement 
Flood detention and conservation 
Channel improvement 
Floodway channel 
Levees and channel improvement 
Channel improvement and 
enlargement of pumping plant 
Channel improvement 
Channel improvement 
Channel improvement 
Two road crossings of Panola- 
Quitman Floodway, MS and for 
protection of Sheley Bridge 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Water-control structure 
Levee, backwater including outlet 
Pumping plant 
Channel improvement and 
structures 
Levee and outlet structures 
Remarks 
See Table 42-C. 
See Table 42-C. 
See Table 42-C. 
Including Moores Bayou, 
Cutoff Bayou, Whiting 
Lake and outlet. 
Authorized by Public Law 
79-526. 
Authorized by Public Law 
79-526. 
Authorized by Public Law 
89-298. As modified in 
GDM in 1967. 
Authorized by Public Law 
89-298. 
Authorized by Public Law 
89-298. 
Authorized by Public Law 
90-147. 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
87-874. 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
78-534.3 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
78-534. 3 Modified in 
December 1970. See Table 
42-D. 
Approved Mar. 3, 1970. See 
Table 42-D. 
Mile 605-645 Mississippi 
River. 
(6) 
Authorized by Public Law 
89-298. 
Authorized by Public Law 
89-298.

TABLE 42-B 
(Continued) 
Mileage 
Below Head 
of Atchafalaya 
River 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Locality Improvement 
108-192 
122 
143 
0-196 
0-90 
260 
0-225 
225 
0-105 
86 
0-36 
0-29 
0-17 
0-12 
0-108 
0-25 
0-20 
0-15 
Augusta to Clarendon 
De Valls Bluff 
Des Arc, AR 
CACHE BASIN, AR 
Cache River, AR 
Bayou DeView, AR 
ST. FRANCIS RIVER AND 
BASIN, AR, AND MO 
Inter-River Drainage District in 
Missouri 
Mouth of St. Francis River- 
Wappapello Dam 
Wappapello Lake 
Little River Basin 
Marked Tree, AR 
Tyronza River 
Big Slough Ditch 
Mayo Ditch 
Cross County Ditch 
Belle Fountain Ditch 
Drainage District No. 17 
L'ANGUILLE RIVER, AR 
L'Anguille River and tributaries, 
Brushy and First Creeks 
WEST TENNESSEE 
TRIBUTARIES 
Wolf River and tributaries, TN 
Obion River and tributaries, 
North, South, Middle, and 
Rutherford Forks 
Forked Deer River and 
tributaries, North, Middle, and 
South Forks 
Mud Lake Pumping Station, TN 
Harris Fork Creek, TN and KY 
Porter Gap, TN 
REELFOOT LAKE-LAKE NO. 
9, TN AND KY 
Running Reelfoot Bayou, TN 
Bayou du Chien and Lake No. 9, 
KY and TN 
Levees, outlet structures 
Levee, outlet structure, and 
pumping station 
Levee, outlet structure, and 
pumping station 
Channel improvement and 
structures 
Channel improvement and 
structures 
Channel improvement and two 
outlet structures 
Floodway, levees, drainage 
channels, and structures 
Flood detention and conservation 
Floodway, levees, drainage 
channels, and structures 
Marked Tree Siphon 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement and 
pumping station 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Pumping plant 
Flood control improvements 
Construction to main-stem 
standards, levee and appurtanent 
structures for flood control 
Channel improvement 
Channel improvements and 
pumping station 
42-18 
Remarks 
(5) 
(5) 
Authorized by Public Law 
81-516. 
Authorized by Public Law 
81-516. 
Authorized by Public Law 
81-516. 
Authorized Dec. 16, 1975. 
See Table 42-D. 
See Table 42-C. 
Authorized by Public Law 
90-483. 
Authorized by Public Law 
90-483. 
Authorized by Public Law 
80-858. 
(6) 
Authorized by 1948 Flood 
Control Act. 
Authorized by 1948 Flood 
Control Act. 
Authorized by Resolutions 
Dec. 15 and 17, 1970.2 
Authorized by Water 
Resources Act of Oct. 22, 
1976.2 Section 102, 1976.2 
Section 183, 1976.2 
Authorized by Public Law 
83-780. 
Authorized in December 
1970, See Table 42-D. 
_ I

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
WEST KENTUCKY 
TRIBUTARIES, KY 
0-47 Obion Creek, KY Channel improvement Authorized by Public Law 
89-298. 
LITTLE RIVER DIVERSION 
CHANNEL, MO 
Delta to Ancell, MO Levees Mile 49 above Cairo. 
MISSOURI RIVER, MO 
0-28 Mouth to St. Charles, MO Levees Intermittent (Sec. 6). 
ILLINOIS RIVER, IL 
0-120 Mouth to Havana, IL Levees Intermittent (Sec. 6). 
OHIO RIVER, IL AND KY 
Cairo to Mound City and Mounds, Floodwall, levee, revetment, and 
IL pumping plant 
1. General data concerning Bayou Boeuf, Bayou Sorrel, 
and Berwick locks where Atchafalaya Basin protection levees 
cross Gulf Intracoastal Waterway, alternate route to Plaquemine, 
LA and lower Atchafalaya River (extension of Bayou 
Teche Waterway), respectively, are in report of New Orleans 
district. 
2. Also see Table 42-D, "Authorizing Legislation." 
3. Public Law 81-516 modified requirements of local 
cooperation. 
4. Authorized by Public Law 77-228. Modified by Public 
Law 89-298. 
5. Authorized or incorporated in MR&T by Public Law 
79-526. 3 See Table 42-D. 
6. Authorized by Public Law 85-500. 
42-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 42-C MISSISSIPPI RIVER TRIBUTARY 
DAMS AND LAKES 
Grenada Enid Sardis Arkabutla Wappapello 
Name' Lake Lake Lake Lake Lake 
River Yalobusha Yocona Little Tallahatchie Coldwater St. Francis 
Nearest town to damsite Grenada Enid Sardis Arkabutla Wappapello 
Drainage area, square miles 1,320 560 1,545 1,000 1,310 
Conservation pool: 
Area, thousand acres 10 6 11 5 4 
Volume, thousand acre-feet 86 58 108 31 31 
Elevation, feet, NGVD 193 230 236.0 209.3 354.7 
Flood control pool: 
Area, thousand acres 65 28 58.5 33 23 
Volume, thousand acre-feet 1,252 602 1,462 494 582 
Runoff, inches 17.8 20.2 17.7 9.3 8.4 
Outlet gates: 
Number 3 2 4 3 3 
Size, feet 7.5 by 14 8 by 16 6 by 12 8.5 by 19 10 by 20 
Capacity, thousand cubic 
feet per second 10.7 9.4 10.0 10.0 18.0 
Spillway: 
Type, uncontrolled Chute Chute Chute Chute Gravity 
Length, feet 200 200 400 300 740 
Elevation, crest, feet, NGVD 231 268 281.4 238.3 394.7 
Discharge capacity, thousand 
cubic feet per second 52 50 132 89 229 
Surcharge pool: 
Area, thousand acres 106 41 90 63 32 
Volume, thousand acre-feet 1,385 554 1,447 858 521 
Runoff, inches 19.7 18.5 17.6 16.1 7.5 
Elevation, feet, NGVD 247.5 284.0 301.0 256.3 413.7 
Dam: 
Type, earthfill Rolled Rolled Hydraulic Rolled Rolled 
Length, thousand feet 13.9 8.4 15.3 11.5 2.7 
Elevation, crest, feet, NGVD 256.0 293.0 311.4 264.3 419.7 
1. Grenada, Enid, Sardis and Arkabutla Lakes are in 
Yazoo River Basin, MS; Wappapello Lake is in St. Francis 
River Basin, MO. 
42-20

TABLE 42-D 
MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Actor 
Authorization Work Authorized Document 
May 15, 1928 
Jun. 19, 1930 
Feb. 15, 1933 
Apr. 23, 1934 
Aug. 30, 1935 
Jun. 15, 1936 
Aug. 28, 1937 
Jun. 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
Jul. 24, 1946 
Flood protection in alluvial valley of Mississippi River, revetment 
and contraction works and dredging to provide least channel 
depth of 9 feet and width of 300 feet below Cairo. 
Provided for allotment of the balance of emergency rescue funds 
to reimburse levee districts and others for expenditures in floodcontrol 
works during the 1927 and subsequent floods. 
Provided for ownership of lands in Bonnet Carr6 Spillway and 
Floodway with proviso for granting rights-of-way, easements, 
and permits, in said lands 
Authorized payment for purchase of, or to reimburse states and 
local levee districts for the cost of, levee rights-of-way for flood 
control work in the Mississippi Valley, and for other purposes. 
Improvement of Wolf and Nonconnah Rivers, TN (Nonconnah 
Creek is correct title) 
Improvement of Wolf River (Memphis Harbor), TN 
Modification of the 1928 Act to provide for: 
Construction of a backwater levee at mouth of White River, AR 
Construction of Eudora floodway in lieu of Boeuf floodway; flood 
control, Yazoo River; construction of Morganza floodway; and 
an outlet to the Gulf of Mexico west of Berwick, LA, including a 
6-year program for the improvement and regularization of the 
Mississippi River between Arkansas and Red Rivers, and 
Atchafalaya River; and construction of roads on levees and 
drainage adjustments incident to floodway levees. 
Provided for construction of floodwalls, levees, and revetments 
along Wolf River and Nonconnah Creek for protection of 
Memphis, TN 
Modify the Yazoo River project to substitute a combined 
reservoir floodway and levee plan. 
Construction of Mounds to Mound City levee and control works 
along Cache River, IL 
Modification of previous act pertaining to floodways and outlets 
and lands therein; including program for the improvement and 
regularization of the Mississippi River, between Cairo and 
Arkansas River, extension of levee road system; strengthening 
of levees. 
Enlarge main line levees to offset abandonment of floodways 
between Arkansas and Red Rivers, flood control works in 
backwater areas of Yazoo and Red Rivers, and in Bayous 
Rapides, Boeuf, and Cocodrie, LA 
Navigation channel 12 feet deep and 300 feet wide between Baton 
Rouge and Cairo; flood protection of Yazoo River Backwater 
Area in vicinity of Satartia, MS 
Continue prosecution of channel improvement and stabilization 
program, $200 million. 
Flood control on the Big Sunflower, Little Sunflower, 
Hushpuckena, and Quiver Rivers and their tributaries, and on 
Hull Brake-Mill Creek Canal, Bogue Phalia, Ditchlow Bayou, 
Deer Creek, and Steele Bayou, MS' 
Improve Boeuf and Tensas Rivers and Bayou Macon, AR' 
Improve Bayou Lafourche, LA 
Improve Yazoo River tributaries. 
North bank, Arkansas River levees (below Plum Bayou).' 
42-21 
H. Doc. 90, 70th Cong., 1st 
sess. 
Public 395, 71st Cong., 2d 
sess. 
Public 351, 72d Cong. 
Public 171, 73d Cong. 
R&H Comm. Doc. 26, 72d 
Cong., 1st sess. 
R&H Comm. Doc. 45, 74th 
Cong., 1st sess. 
Unpublished report dated 
Apr. 2, 1925. 
H. Comm. on Flood Control, 
Doc. 1, 74th Cong., 1st sess. 
Unpublished report on 
record in OCE. 
H. Comm. on Flood Control, 
Doc. 1, 75th Cong., 1st sess. 
H. Comm. on Flood Control, 
Doc. 1, 75th Cong., 1st sess. 
H. Doc. 359, 77th Cong., 1st 
sess. 
H. Doc. 509, 78th Cong., 2d 
sess. 
Public Law 534, 78th Cong., 
2d sess. 
H. Doc. 516, 78th Cong., 2d 
sess. 
S. Doc. 151, 78th Cong., 2d 
sess. 
S. Doc. 191, 79th Cong., 2d 
sess. 
H. Doc. 516, 78th Cong., 2d 
sess. 
H. Doc. 308, 74th Cong., 1st 
sess.

TABLE 42-D 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
AUTHORIZING LEGISLATION 
Actor 
Authorization Work Authorized 
Levees on White River (Augusta to Clarendon).' 
Bayou des Glaises diversion channel, LA' 
Modify local cooperation requirements in St. Francis and Yazoo 
Basins. 
Tiptonville-Obion levee and drainage improvements.' 
Improvement of St. Johns Bayou, MO 
Big Sunflower River, etc.' 
Tennessee Chute (Memphis Harbor), TN 
Continue prosecution of project for flood control and channel 
improvement, $100 million. 
Improve Mississippi River below Cape Girardeau, MO with 
respect to West Tennessee tributaries. 
Improve L'Anguille River, AR 
Baton Rouge Harbor (Devils Swamp), LA' 
Flood protection at Des Arc, AR 
Improve St. Francis River and Basin, AR and MO 
Improve Cache River and Bayou DeView, AR and MO 
Improve Grand Prairie Region and Bayou Meto Basin, AR 
Flood protection, Lake Pontchartrain, Jefferson Parish, LA' 
Filling Grant's Canal, Lake Providence, LA 
Additional protection to Red River Backwater Area. 
Extend Federal jurisdiction to cover levees in Orleans Parish, LA 
Bank protection, Amite River, LA 
Continue prosecution of project for flood control and channel 
improvement, $200 million. 
Jonesville, LA levee, retaining wall, and drainage structure.' 
Modify requirements for local cooperation in White River 
Backwater Area, AR 
Navigation improvement of Atchafalaya from Mississippi River 
to Morgan City, LA 
Modify project for Vicksburg-Yazoo Area (Harbor), MS 
Improve New Madrid Floodway, MO, including Peafield 
drainage floodgate. 
Control of Old and Atchafalaya Rivers and a lock for navigation. 
Improve Reelfoot Lake area, KY and TN 
Improve Greenville Harbor, MS 
42-22 
~ 
Jun. 30, 1948 
May 17, 1950 
Oct. 30, 1951 
Sep. 3, 1954 
Jul. 3, 1958 
Document 
H. Doc. 98, 76th Cong., 1st 
sess. 
H. Doc. 602, 79th Cong., 2d 
sess. 
Public Law 526, 79th Cong., 
2d sess. 
H. Doc. 757, 79th Cong., 2d 
sess. 
H. Doc. 138, 80th Cong., 1st 
sess. 
H. Doc. 516, 78th Cong., 2d 
sess. 
S. Doc. 51, 80th Cong., 1st 
sess. 
Public Law 526, 79th Cong., 
2d sess. 
H. Doc. 627, 80th Cong., 2d 
sess. 
H. Doc. 651, 80th Cong., 2d 
sess. 
H. Doc. 321, 80th Cong., 1st 
sess. 
H. Doc. 485, 81st Cong., 2d 
sess. 
H. Doc. 132, 81st Cong., 1st 
sess. 
S. Doc. 88, 81st Cong., 1st 
sess. 
H. Doc. 255, 81st Cong., 1st 
sess. 
S. Doc. 139, 81st Cong., 2d 
sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
S. Doc. 117, 81st Cong., 1st 
sess. 
Public Law 237, 82d Cong., 
1st sess. 
S. Doc. 53, 82d Cong., 1st 
sess. 
H. Doc. 85, 83d Cong., 1st 
sess. 
H. Doc. 183, 83d Cong., 1st 
sess. 
H. Doc. 478, 83d Cong., 2d 
sess. 
S. Doc. 160, 83d Cong., 2d 
sess. 
S. Doc. 15, 86th Cong., 1st 
sess.

TABLE 42-D 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Actor 
Authorization Work Authorized Document 
Jul. 14, 1960 
Oct. 23, 1962 
Jun. 18, 1965 
Oct. 27, 1965 
Extensions to project for Boeuf and Tensas Rivers and Bayou 
Macon in Arkansas. 
White River backwater area pumping plant. 
Wolf River and tributaries for flood protection in Tennessee. 
Continue prosecution of project for channel improvement-$50 
million. 
Modification-Baton Rouge Harbor (Devils Swamp), LA 
Construct improvements in Gin and Muddy Bayous, Yazoo River 
Basin, MS 
Replace 2 bridges with adequate floodway over Boeuf River and 
Big Bayou in Boeuf Basin, AR 
Continue prosecution of project for flood control and channel 
improvement, $53 million. 
Modify and expand levees and channel improvement features of 
main stem project. 
Modify flood control improvements in following tributary areas 
and basins: Cairo-Mounds-Mounds City, St. Francis, Lower 
White, Boeuf-Tensas-Macon, Red River backwater, Yazoo 
headwater, Grand Prairie, and Bayou Meto. 
Acquire any modified easements required in New Madrid 
Floodway as provided by Sec. 4 of May 15, 1928 act. 
Operate and maintain pumping plant in Red River backwater 
area (Tensas-Cocodrie Pumping Plant). 
Provide improvements in West Kentucky tributaries. 
Provide fish and wildlife facilities in St. Francis and Big 
Sunflower Basins; Yazoo Headwater and Backwater Areas; and 
Mississippi Delta region. 
Deauthorize Amite River, LA project. 
Modify St. Francis River, MO and AR, project within District 
No. 7, Poinsett County, AR 
Provide pumping plant and drainage structure at Wilson Point, 
LA 
Construction of improvements to supplement freshwater supply 
in Teche-Vermilion Basins in Louisiana. 
Bank revetment for protection of existing industrial facilities 
along Mississippi River below Baton Rouge, LA 
Modification of West Tennessee tributaries feature to provide 
relocation of gas transmission lines at Federal expense. 
Continue emergency work, $87,135,000, which includes $100,000 
for road crossing of Panola-Quitman Floodway, MS, and $80,000 
for protection of Sheley Bridge, Tallahatchie River, MS 
Improvements in Boeuf and Tensas Rivers and Bayou Macon 
Basin to divert flows that would otherwise enter Lake Chicot, 
AR 
Improvements in the Belle Fountain ditch and tributaries, MO, 
and Drainage District No. 17, AR 
Provide pumping plants and other drainage facilities in Cairo, 
IL, and vicinity. 
Modification of Yazoo Headwater Project to include cleanout 
along David Bayou, MS 
Modify Yazoo Backwater feature to include a control structure in 
Muddy Bayou, MS 
42-23 
H. Doc. 108, 85th Cong., 1st 
sess. 
S. Doc. 26, 85th Cong., 1st 
sess. 
H. Doc. 76, 85th Cong., 1st 
sess. 
Public Law 86-645. 
Public Law 87-874. 
Public Law 87-874. 
Public Law 87-874. 
Public Law 89-42. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
S. Doc. 57, 89th Cong., 1st 
sess. 
Unpublished Vicksburg 
District's MRC report 
Approved-Apr. 14, 1966. 
H. Doc. 524, 89th Cong., 2d 
sess. 
Public Law 89-789. 
Public Law 89-789. 
Public Law 90-147. 
H. Doc. 168, 90th Cong., 1st 
sess. 
H. Doc. 339, 90th Cong., 2d 
sess. 
Public Law 90-483. 
Unpublished MRC report 
dated May 8, 1968. 
Unpublished MRC report 
dated Feb. 2, 1970. 
Apr. 14, 19662 
Nov. 7, 1966 
Nov. 20, 1967 
Aug. 13, 1968 
Sep. 10, 19683 
Mar. 3, 19703

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 42-D 
(Continued) 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Apr. 29, 19703 
Jun. 4, 19703 
Dec. 31, 1970 
Senate and 
House Public 
Works 
Resolutions 
adopted Dec. 17 
and 15, 1970, 
respectively.4 
River Basin 
Monetary Act 
of Dec. 23, 1971 
Jan. 19, 19732 
TITLE I Water 
Resources 
Development 
Act of 1974. 
Modification of Yazoo Headwater Project to include drainage 
structure and channel improvement on Rocky Bayou, MS 
Provide for enlargement of Bayou Latenache from Pointe Coupee 
drainage structure to Alabama Bayou, LA 
Modify and expand project to include flood protection within the 
area of eastern Rapides and south-central Avoyelles Parishes, 
LA, that are drained by Bayou des Glaises diversion channel and 
Lake Long, and their tributaries. 
Modify the project for West Kentucky tributaries (Obion Creek), 
KY, to provide for all relocations, at Federal expense, of all 
transmission lines required by the project. 
Report on Western Tennessee Tributaries, TN and KY, 
authorized: 
a. Modification of Reelfoot Lake feature to provide channel 
imorovements on Bayou du Chien and Lake No. 9 in KY and 
TN 
b. Modification of Mississippi levee feature to include a 
pumping station near Mud Lake floodgate and adjacent 
channel improvements. 
Modification of Big Sunflower Basin feature to provide 
additional improvements in Steele Bayou Basin, MS 
Continue prosecution of project for the comprehensive 
development of the basin, $97 million. 
Modification of Tiptonville-Obion River levee feature to relieve 
local interests of all responsibility except that of providing 
maintenance. 
Modification of the Mississippi levee feature to provide additional 
drainage facilities in Long Lake area, vicinity of Helena, AR 
Projects recommended by four completed reports were 
authorized for accomplishment of Phase I design memorandum 
of advance engineering and design on: 
a. Greenville Harbor, Greenville, MS 
b. East bank of Mississippi River, Warren to Wilkinson 
Counties, MS (Natchez area). 
c. East bank of Mississippi River, Warren to Wilkinson 
Counties, MS (Vicksburg-Yazoo area). 
d. Bushley Bayou Area of Red River Backwater Area, LA 
Modification of West Tennessee tributaries feature (Obion and 
Forked Deer Rivers), TN, to acquire lands for fish and wildlife, 
recreation, and environmental purposes. 
Modification of the Yazoo Basin, MS, feature to provide for a 
streambank erosion control demonstration project for the delta 
and hill areas of basin. 
Modification of project to provide that the Secretary of the Army, 
acting through the Chief of Engineers, can substitute authorized 
mitigation lands, not yet acquired and no longer suitable, for 
like acreage in the same or adjacent subbasins of the project 
area. This section provides the authority to substitute authorized 
mitigation lands in: 
a. Tensas Basin, LA and AR, feature (Red River backwater). 
b. St. Francis Basin, AR and MO, feature. 
Modification of Bayou Cocodrie and tributaries, LA, feature, to 
provide for: enlargement of Bayou Courtableau from 
ashington to west protection levee; right-of-way and spoil 
disposal areas at Federal expense; and necessary additional 
culverts through west protection levee. 
Unpublished MRC report 
dated Mar. 6, 1970. 
Unpublished MRC report 
dated Sep. 22, 1969. 
S. Doc. 91-113, 2d sess. 
Public Law 91-611. 
H. Doc. 91-414, 2d sess. 
S. Doc. 91-74, 2d sess. 
Sec. 1, Public Law 92-222. 
Sec. 7, Public Law 92-222. 
Unpublished Memphis 
District's MRC report 
dated Oct. 4, 1972. 
Sec. 1, Public Law 93-251. 
Mar. 7, 1974. 
S. Doc. 93-38, 1st sess. 
H. Doc. 93-148, 1st sess. 
H. Doc. 93-148, 1st sess. 
H. Doc. 93-157, 1st sess. 
Sec. 3, Public Law 93-251. 
Sec. 32, Public Law 93-251. 
Sec. 42, Public Law 93-251. 
Sec. 87, Public Law 93-251. 
42-24

TABLE 42-D 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Actor 
Authorization Work Authorized Document 
TITLE II River 
Basin 
Monetary 
Authorization 
Act of 1974 
River Basin 
Monetary Act 
of Oct. 2, 1975 
Dec. 16, 19752 
TITLE II Public 
Works for 
Water and 
Power 
Development 
and Energy 
Research 
Appropriation 
Act 1976. 
TITLE II Public 
Works for 
Water and 
Power 
Development 
and Energy 
Research 
Appropriation 
Act, 1977. 
Water Resources 
Development 
Act of 1976. 
TITLE II Public 
Works for 
Water and 
Power 
Development 
and Energy 
Research 
Appropriation 
Act, 1978. 
Modification of Cache River Basin, AR, feature to provide for: 
acquisition by fee easements of lands for fish and wildlife 
management, recreation, and environmental purposes. 
Continue prosecution of project for the comprehensive 
development of the basin, $211 million. 
Continue prosecution of project for the comprehensive 
development of the basin, $158,000,000. 
Modification of St. Francis Basin, AR and MO, feature to provide 
relief from ponding of interior runoff in the Inter-River 
Drainage District of Missouri. 
Continue prosecution of project for comprehensive development 
during period Jul. 1- Sep. 30, 1976, $60,300,000. 
Continue prosecution of project for flood control, rescue work, 
repair, restoration, and control of bank erosion, $231,497,000. 
Sec. 101(a) authorized accomplishment of Phase I - Advanced 
Engineering and Design Memoranda - On: 
a. St. Johns Bayou and New Madrid Floodway, MO, project: 
Report of OCE - Sep. 26, 1975. 
b. Nonconnah Creek, TN and MS, project: Report of OCE - Jun. 
23, 1976, and as an independent part of the project: 
Improvements for flood control and allied purposes on Horn 
Lake Creek and tributaries, including Cowpen Creek, TN 
and MS. 
Modification of West Tennessee Tributaries feature (Obion and 
Forked Deer Rivers), TN, to: 
a. (Sec. 102) - Provide project for flood control for Harris Fork 
Creek, TN and KY: (H.D. 94-221) except that highway bridge 
relocations and alterations shall be at Federal expense. 
b. (Sec. 183) - Provide for construction of a levee and 
appurtenant works from mouth of Obion diversion channel to 
vicinity Highway 88 and thence to vicinity of Porter Gap, TN 
Continue prosecution of project for flood control, rescue work, 
repair, restoration, and control of bank erosion, $253,081,000. 
Sec. 99, Public Law 93-251. 
Sec. 201, Public Law 93-251. 
Mar. 7, 1974. 
Sec. 1, Public Law 94-101. 
Unpublished Memphis 
District's MRC report 
dated Nov. 11, 1975. 
Public Law 94-180, Dec. 26, 
1975. 
Public Law 94-355, Jul. 12, 
1976. 
Public Law 94-587, Oct. 22, 
1976. 
Public Law 95-96 Aug. 7, 
1977. 
42-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 42-D 
(Continued) 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Dec. 9, 1977, 5th Modification of the Tensas Basin Project, Red River Backwater Unpublished Vicksburg 
Ind. on VXD Area, to include a drainage structure and appurtenant channel District report dated May 
May 31, 1977, works in the Six Mile Bayou area of Concordia Parish, LA 31, 1977, on Cynthia and 
Letter Report.2 Six Mile Bayous, LA 
Jun. 28, 1980 The establishment of the Tensas River National Wildlife Refuge Public Law 96-285, Jun. 28, 
for the preservation and development of environmental 1980. 
resources and in lieu of mitigation acquisitions which otherwise 
would be required for certain water resources projects, within 
designated limits, in the basins of the Tensas, Boeuf, and Red 
Rivers in the State of Louisiana. 
Energy and For expenses necessary for prosecuting work of flood control Public Law 96-367, Oct. 1, 
Water projects, rescue work, repair, restoration or maintenance of 1980. 
Development flood control projects threatened or destroyed by flood, 
Appropriation $232,519,000: Provided, That not less than $250,000 be available 
Act, 1981 for control of bank erosion of streams in the Yazoo Basin, 
including the foothill area. Provided further, That funds for the 
Tensas Basin Red River Backwater Area, be used for flood 
control, etc. for Sicily Island and Below Red River including 
pumping stations. 
Supplemental Authorizes and directs the Secretary of the Army acting through FY 1985 Supplemental 
Appropriations the Chief of Engineers to proceed with planning, design, Appropriations Bill (PL 
Bill for FY engineering and construction of 41 water resources projects, 99-88) 
Ending Sep. including Atchafalaya Basin Floodway System. The bill 
30, 1985 (PL provides that the funds appropriated shall lapse on Jun. 30, 1986 
99-88) unless formal cost-sharing agreements have been reached with 
the local sponsor. For the Atchafalaya Basin Floodway Systems 
project, cost-sharing will be as recommended in the Report of 
the Chief of Engineers, Feb. 28, 1983. 
1. Incorporated into Mississippi River and tributaries 
project as shown in Table 42-E. 
2. Date minor modification for blocked drainage was 
approved under delegated authority of the President, Mississippi 
River Commission, and in accordance with Sec. 10(p) of 
the 1946 Flood Control Act (Public Law 79-526). 
3. Date minor modification was approved under discretionary 
authority of Chief of Engineers contained in May 
15, 1928, Flood Control Act, as amended. 
4. Projects approved under the provisions of Sec. 201 of 
Flood Control Act of Oct. 27, 1965. 
42-26

MISSISSIPPI RIVER COMMISSION 
TABLE 42-E INCORPORATING AND AUTHORIZING LEGISLATION 
For Last 
Public Full Report 
Act of Law Authorizing See Annual 
Incorporation No. Act Description Report for 
Jul. 24, 1946 79-526 Jun. 22, 1936 Tiptonville-Obion levee and drainage 1941, p. 943 
improvements, TN 
Jul. 24, 1946 79-526 Jun. 22, 1936 Bayou des Glaises diversion ditch, LA 1946, p. 1029 
Jul. 24, 1946 79-256 Jun. 22, 1936 From North Little Rock, AR, to Gillett, AR, on 1946, p. 1053 
north bank of Arkansas River (portion belbw 
Plum Bayou). 
Jul. 24, 1946 79-256 Aug. 18, 1941 White River levees, Augusta to Clarendon and De 1946, p. 1083 
Valls Bluff, AR 
Jul. 24, 1946 79-526 Dec. 22, 1944 Boeuf and Tensas Rivers and Bayou Macon, LA 1945, p. 982 
Jul. 24, 1946 79-526 Dec. 22, 1944 Big Sunflower River, etc. 1946, p. 1061 
Jun. 30, 1948 80-858 Jul. 24, 1946 Devils Swamp barge channel at Baton Rouge, LA 1948, p.1059 
(Baton Rouge Harbor) 
May 17, 1950 81-516 Jun. 22, 1936 Jonesville, LA 1953, p.773 
May 17, 1950 81-516 Jul. 24, 1946 Lake Pontchartrain-Jefferson Parish, LA 1953, p. 737 
42-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 42-F SUMMARY OF PRESENTLY ESTIMATED 
FEDERAL FIRST COST OF AUTHORIZED IMPROVEMENTS 
Estimated Cost' 
Project Title Fiscal Year 1986 
Completed features 2 
Mississippi River levees 
Mud Lake Pumping Station, TN 
Sec. 6 levees, 1928 Flood Control Act 
Channel improvement 
Atchafalaya Basin, LA 
Bayou Cocodrie and tributaries, LA 
Old River, LA 
Lower Red River- South Bank Red River levees, LA 
Eastern Rapides and South-Central Avoyelles Parishes, LA 
Mississippi Delta Region, LA 
Tensas Basin, AR and LA 
Lower Arkansas River, AR 
Grand Prairie-Bayou Meto, AR (Flood Control & Water Supply) 
Yazoo Basin, MS 
Lower White River, AR (All except Big Creek & Tribs.) 
Lower White River (Big Creek & Tribs.) 
Cache Basin, AR 
St. Francis Basin, AR and MO 
L'Anguille Basin, AR 
West Tennessee Tributaries, TN 
Harris Fork Creek, TN & KY 
Reelfoot Lake-Lake No. 9, TN & KY 
Reelfoot Lake, TN & KY (Completed) 
Reelfoot Lake-Lake No. 9, TN & KY 
West Kentucky Tributaries, KY 
Tensas River National Wildlife Refuge 
Atchafalaya Basin Floodway System, LA 
Eight Mile Creek, AR 
Sardis Dam (Dam Safety Assurance) 
TOTAL 
$ 199,238,000 
1,218,000,000 
4,480,0003 
4,000,0003 
3,008,000,000 
1,423,000,000 
20,300,000 
301,300,000 
28,400,0003 
50,000,000 
53,000,000 
442,000,000 
35,000,0003 
130,900,0003 
1,276,000,000 
16,802,0003 
37,100,0003 
157,000,000 
371,000,000 
10,200,000 
99,000,000 
17,900,0003 
(10,400,000)3 
440,000 
9,960,000 
21,000,0003 
40,000,0003 
105,000,000 
6,700,000 
7,100,000 
$ 9,092,820,000 
1. Inflation projected through the construction period. 
2. Includes Bonnet Carre', Morganza, and New Madrid 
Floodways; Memphis, Greenville, and Vicksburg Harbors; 
Lake Pontchartrain; Wolf River; completed roads on main 
stem levees; channel construction works; Atchafalaya River 
and Basin; Wax Lake Outlet; Charenton Canal; Bayou des 
Glaises diversion channel, Boeuf Basin levees; Grant's Canal; 
De Valls Bluff, Jonesville, and Des Arc protection works; 
Baton Rouge Harbor; and miscellaneous features; Teche- 
Vermilion Basins, LA. 
3. Incremental (not projected through the construction 
period.) 
42-28

MISSISSIPPI RIVER COMMISSION 
TABLE 42-G MISSISSIPPI RIVER MAIN STEM 
CHANNEL IMPROVEMENTS
Operations in 1,000 Cubic Yards 
Location Fiscal Year 1986 
Mileage 
Above Head Channel 
District of Passes Construction Maintenance Total 
New Orleans 
Baton Rouge Harbor 
(Devils Swamp) 235 - 94.7 94.7 
Main stem channel 234-320 - 0.0 0.0 
Vicksburg 
Main stem channel 322-600 - 2,710.7 2,710.7 
Vicksburg Harbor 437 140.2 140.2 
Greenville Harbor 537 213.9 213.9 
Memphis 
Main stem channel 600-954 25,480.9 25,480.9 
Memphis Harbor, 
McKellar Lake 725 1,140.9 1,140.9 
TOTAL 29,781.3 29,781.3 
42-29

TABLE 42-H BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1986) 
Operations This FY 
Construction Nonop- Operaerative 
tive 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
MISSISSIPPI RIVER 
Standard revetment: 
Venice, LA .................. 12 
Lower Childress- 
Fort Jackson, LA ............. 22 
Buras, LA .................. 25 
Tropical Bend, LA ............ 30 
Bayou Lamoque, LA .......... 33 
Port Sulphur, LA ............. 39 
Point Michel, LA ............. 44 
Bohemia, LA................. 46 
Diamond, LA ................ 49 
Gravolet, LA................. 51 
Junior, LA .................. 54 
Harlem, LA ................. 56 
Myrtle Grove, LA ............. 59 
Monsecour, LA ............... 61 
Alliance, LA................. 62 
Belair, LA .................. 65 
Jesuit Bend, LA .............. 68 
Linwood, LA................. 71 
Oak Point, LA ............... 72 
Scarsdale, LA................ 75 
English Turn, LA ............ 78 
Poydras, LA ................ 82 
Cutoff, LA .................. 88 
Third district reach, LA ....... 93 
Algiers Point, LA ............. 95 
Gouldsboro Bend, LA ......... 96 
Gretna Bend, LA ............. 97 
Greenville Bend, LA .......... 100 
Carrollton Bend, LA .......... 104 
Avondale Bend, LA ........... 109 
Kenner, LA................. 114 
Luling,LA ................. 119 
Good Hope, LA............... 126 
Waterford, LA............... 128 
Montz, LA .................. 132 
Lucy, LA ................. 136 
Reserve, LA ................ 138 
Willow Bend, LA ............. 141 
Angelina, LA................ 145 
Vacherie, LA................. 148 
Belmont, LA ................. 152 
R
RRRLRRLRL
RLRLRLRLRLRLRLRRRR
LRL 
R
L
R
L
R
L
R
L
R
L 
- 
4,325 
4,763 
790 
185 20,921 
- 28,306 
80 8,559 
- - 
- - 
- - 
- - 
- - 
- - 
80 8,559 
1,952 
3,475 
2,175 
- 
8,740 
12,321 
5,961 
16,210 0 
15,430 
17,283 
25,012 
7,264 
36,995 
21,932 n 
12,380 
8,750 
17,435 
19,345 
15,148 
15,925 
10,020 Z 
9,750 
22,841 2 
22,860 
10,638 
12,377 
11,575 m 
16,408 
45,864 
21,256 
27,167 
7,728 
4,960 
9,662 - 
22,045 o 
15,015 
26,696 
37,167 
28,908 
16,298 
12,295 
17,502 
17,826 
20,947 
7,618 
19,000 
13,295 
25,575 
14,500 
03 
0

Rich Bend, LA .............. 157 
Romeville, LA ............... 161 
St. Alice, LA................. 165 
Burnside, LA................ 170 
Aben, LA ................... 172 
St. Elmo, LA................. 174 
Smoke Bend, LA ............. 177 
Marchand, LA............... 180 
Philadelphia Point, LA ........ 183 
New River Bend, LA .......... 185 
White Castle, LA ............. 193 
St. Gabriel, LA .............. 201 
Plaquemine Bend, LA ......... 209 
Manchac, LA................. 215 
Missouri Bend, LA ........... 222 
Arlington, LA................ 227 
Port Allen, LA .............. 231 
Allendale, LA................ 238 
Springfield Bend, LA ......... 244 
Arboth, LA ................. 250 
Faulkner Lake, LA ........... 253 
Grand Bay, LA .............. 258 
Bayou Sara, LA ............. 265 
Red Store, LA ............... 269 
Arrow Bend, LA ............. 272 
Boies Point, LA .............. 275 
Morganza, LA .............. 279 
Iowa Point, LA .............. 282 
Brunette Point, LA ........... 285 
Greenwood Bend, LA ......... 289 
Hog Point, LA .............. 296 
Carr Point, LA .............. 304 
Above Old River, LA .......... 305 
Fort Adams, MS ............. 308 
Point Breeze, LA ............. 313 
Coochie, LA ................ 317 
Palmetto, MS ............... 322 
Subtotal 
New Orleans District, 
Mississippi River ....... 
RLRLRL
RL
RL
RLRL
RL
RRLRLRLRLRRLRLRRRLRRL 
- 
1,866 
3,394 
2,203 
7,562 
4,732 
29,635 
(5.61 Miles) 
50 6,949 
50 13,893 
200 16,794 
- - 
400 39,666 
26,946 
965 162,034 
1,725 10,177 
734 5,374 
1,512 8,059 
826 3,267 
1,107 5,291 
392 
543 
2,156 
2,312 
- 
14,441 63,658 
(2.74 Miles) 
1,580 
1,674 
7,128 
3,286 
11,185 
1,402,108 
(265.55 Miles) 
27,408 
21,625 
27,052 
22,145 
10,063 
10,240 
17,075 
10,144 
5,379 
33,414 
35,536 
26,809 
36,137 
35,480 
22,632 
12,244 
14,073 
25,502 
25,690 
13,190 
4,732 
7,090 
16,958 
11,315 
13,600 
16,094 
20,513 
11,375 
8,038 
14,987 
13,368 
8,600 
4,800 
17,219 
11,165 
17,150 
30.864 
39,353 
Dikes: 
None 
OLD RIVER CONTROL 
Standard revetment: 
Inflow channel .............. 315 
Inflow channel ............... 315 
Outflow channel .............. 315 
Total standard revetment, 
Old River .............. 
L
RR
5,790 
2,415 
4,365 
48,081 25,681 
5,790 48,081 
32,461 
5,790 - 48,081 
(1.10 Miles) 
I 
32,461 
(6.15 Miles)

TABLE 42-H 
(Continued) 
BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1986) 
Operations This FY 
Construction Nonop- Operaerative 
tive 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
Below Confluence 
ATCHAFALAYA RIVER of Red and 
Atchafalaya 
Rivers 
Standard revetment: 
Mile One, LA ................ 1 
Coville, Bayou, LA ............ 3 
Legonier, LA ............. 4 
Simmesport, LA ............. 6 
Kuhlman Bayou, LA .......... 7 
Odenburg, LA ............... 9 
Cason, LA .................... 12 
McCrea, LA ................ 13 
Woodside, LA ................ 14 
Provosty, LA ................ 17 
Crooked Bayou, LA ........... 18 
Mercier, LA ................. 22 
Barberton, LA .............. 23 
Evans Point, LA .............. 24 
Goudeau, LA ................ 26 
Morris Bayou, LA ............. 27 
Goodwood, LA ............... 28 
Red Cross, LA ............... 29 
Melville, LA ................ 30 
Cross Bayou, LA .............. 31 
Melville South, LA............ 33 
Toles, LA ................... 35 
Petite Prairie, LA ............ 36 
Holloway Lake, LA .......... 37 
Bayou Sherman, LA .......... 38 
Krotz Springs, LA ............ 40 
Sherburne, LA ............... 43 
Bayou Big Graw, LA .......... 46 
Morgan City ................ 115 
Total standard revetment ... 
L
RL
RL
RRLRLRLRL 
R
LRLRL 
R
L
R
LL
RRR 
L 
930 
-
930 
(0.18 Mile) 
-30 
-M01i e 
3,431 
3,431 
4,150 
6,550 
8,940 
10,636 
5,565 
5,375 
10,798 
5,027 
13,002 
7,768 
9,600 
10,478 
3,592 
4,898 
3,938 
3,800 
8,505 
8,065 
4,870 
3,815 
4,070 
6,355 
8,381 
7,085 
5,200 
4,625 
7,035 
8,394 
3,410 
193,927 
(36.73 Miles) 
1,893 
1,361 
1,886 
1,968 
1,105 
910 
3,846 
2,630 
15,599 
Dikes: 
None

LOWER RED RIVER 
Standard revetment: 
Long Lake, LA .............. 
Naples, LA ................. 
Turnbull Island, LA .......... 
Total standard revetment 
Below Confluence 
of Old River 
Outflow Channel 
and Red River 
10
79 
RRL 
- - - - - - - 6,652 
- - - - - - - 6,190 
- - - - - - 11,038 
- - - - - - - 23,880 
(4.52 Miles) 
Dikes: 
None 
1. Gross squares articulated concrete mattress (100 
square feet).

TABLE 42-I BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(FISCAL YEAR 1986) 
Operations This FY 
Construction Nonop- Operaerative 
tive 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
MISSISSIPPI RIVER 
Standard revetment: 
Bougere Bend, LA ........... 329 
Dead Mans Bend, MS ......... 335 
Railroad Landing, MS ......... 346 
St. Catherine Bend, LA ........ 350 
Morville, LA ................ 356 
Natchez Island, MS ........... 357 
Carthage, MS................ 361 
Natchez Front, MS ........... 364 
Gibson, LA ................. 371 
Ashland, LA-MS ............. 374 
Kempe Bend, LA ............ 383 
Browns Field, LA ............ 389 
Goldbottom, MS.............. 392 
Hardscrabble, LA ............ 398 
Grand Gulf, MS .............. 403 
Point Pleasant, MS-LA ........ 413 
Togo Island, LA .............. 415 
Lake Karnac, LA-MS ......... 419 
Diamond Point, LA-MS ....... 423 
Reid-Bedford, LA ............ 429 
Racetrack, MS............... 433 
Barge Line Terminal, MS ..... 437 
Vicksburg Harbor, MS ........ 437 
Delta Point, LA .............. 437 
King's Point-Opposite 
Delta Point, LA-MS ......... 439 
False Point, LA .............. 443 
Marshall-Brown's Point, 
LA-MS .................... 446 
Milliken Bend, LA ............ 453 
Belle Island, LA-MS .......... 460 
Goodrich, LA................. 467 
Cottonwood Bar, MS, TF ...... 470 
Fitler-Cottonwood, MS ........ 474 
Hagaman, LA ............... 481 
Ben Lomond, MS ............. 486 
Baleshed Towhead-Stack 
Island, LA-MS . ........... 488 
Lake Providence, LA .......... 489 
Mayersville, MS ............. 497 
Sarah Island-Opossum Point, 
LA-MS .................... 503 
RLL
RRRLL
RL
RRL
RLRRL
RRL
LL 
R
LR 
LRLRR
LRL 
R
RL 
865 
1,600 
990 
3,275 
115 
4,168 
5161 
4,882 
11,262 
7,770 
1,915 
130 
1,210 
530 
900 
50 
1,030 
530 
780 
855 
703 
5,080 
2186 
200 
1,783 
391 
8,311 
3,818 
2,467 
- 
3,192 
4,437 
20,805 0 
19,145 y 
11,595 
28,093 
11,815 
2,180 
14,700 
6,510 
23,725 
22,137 
28,285 
9,280 
30,250 
22,530 
53,948 Z 
32,345 
5,670 2 
19,260 M 
12,125 M 
18,392 
13,935 m 
3,040 0 
7,350 c 
7,650 
19,330 
12,860 4 
19,580 00 
44,650 
24,160 
37,220 
15,270 
28,427 
37,756 
10,235 
52,1242 
11,600 
34,992 
2,494 
R 5940 - 20,981 530 2,068 23,825

Carolina, MS ................. 
Cracraft, AR ............... 
Worthington, MS-AR ......... 
Walnut Point Kentucky 
Bend, MS ................ 
American Cutoff, MS-AR ..... 
Sunnyside-Lakeport, AR ...... 
Vancluse, AR .............. 
Island 84, AR, MS ........... 
Warfield Point, MS ......... 
Leland-LaGrange, AR-MS .... 
Spanish Moss, AR ............ 
Tarpley Island, MS .......... 
Miller Bend, MS ............ 
Island 82, AR ............... 
Ashbrook Island, MS ........ 
Arkansas City-Yellow 
Bend, AR ............... 
Huntington Point, MS ........ 
Pair O'Dice, AR ........... 
Eutaw-Mounds, MS ........ 
Cypress Bend, AR .......... 
Catfish Point, MS ........... 
Ozark, AR-MS ............... 
Prentiss, AR-MS ............. 
Rosedale Bend, AR ........... 
Riverton, MS ................ 
Klondike, AR ............... 
Victoria Bend-Terrene, MS ... 
Big Island, AR ............. 
Smith Point, MS ............. 
Dennis, MS .................. 
Cessions, MS ............... 
Total revetment, 
Vicksburg District, 
Mississippi River ....... 
Dikes: 
Jackson Point, MS ............ 
Opposite Warnicott Ldg, MS 
Natchez Island, LA-MS ....... 
Waterproof Bar, LA .......... 
Spithead Towhead, MS ....... 
Browns Field, LA .......... 
Cottage Bend, LA-MS ....... 
Bondurant Towhead, LA ...... 
Coffee Point, LA ........... 
Yucatan, MS ............... 
Togo Island, LA .............. 
Below Racetrack, MS ......... 
Racetrack Towhead, MS ...... 
Marshall Cutoff, LA .......... 
Forest Home Towhead, LA .... 
Willow Cutoff, LA ............ 
Arcadia Point, MS ........... 
Point Lookout, LA .......... 
507 
511 
514 
519 
526 
530 
534 
535 
537 
538 
539 
542 
544 
546 
549 
553 
556 
561 
563 
568 
573 
578 
582 
585 
586 
588 
593 
598 
601 
611 
615 
L
R
R
LLRRLLLRRLRR 
RLRL
RL
RLLLRLRLLL 
20,440 
(3.87 Miles) 
330 
352 
358 
379 
386 
388 
389 
394 
405 
410 
416 
430 
431 
448 
449 
462 
470 
478 
LLRRLRLRRRLL 
R
RL
RL 
R 
115 46,454 
1,440 
- 
1,294 
11,080 
22,210 
8,350 
45,653 
2,980 
33,685 
4,300 
13,475 
4,320 
14,150 
4,580 
2,000 
29,360 
3,080 
3,455 
40,560 
10,045 
9,095 
40,188 
26,585 
20,075 
22,015 
20,315 
4,820 
12,500 
23,400 
29,245 
16,515 
18,185 
25,195 
10,910 
4,182 
9,900 13,705 28,901 0 1,329,120 
(251.73 Miles) 
(3) 
4,306 
5,351 
7,695 
11,372 
3,6614 
4,8354 
14,049 
4,421 
3,260 
9,010 
8,256 
14,7294 
1,752 
5,1664 
4,5744 
4,2754 
12,4854 
2,751 
2,960 
7,075 
-

TABLE 42-I 
(Continued) 
BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(FISCAL YEAR 1986) 
Operations This FY 
Construction Constrerative Nonop- Otpiveera- 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
MISSISSIPPI RIVER 
continued 
Dikes: 
Ajax Bar, MS ............... 
Ben Lomond, MS .......... 
Balshed Ldg., MS ........... 
Wilson Point, LA ........... 
Corregidor, MS ............... 
Carolina, AR ................. 
Cracraft Lower, AR .......... 
Cracraft, AR ................ 
Leota, MS .................... 
Island, 86, AR .............. 
Seven Oaks, AR ............ 
Walnut Point, MS ............ 
Refuge, MS ................ 
Island 84, AR ................ 
Leland Bar, AR-MS .......... 
Leland Neck, AR-MS ....... 
Tarpley Cutoff, MS-AR ....... 
Island 82-Miller Bend, 
AR-M S ................... 
Ashbrook-Miller Bend, 
AR-MS .................... 
Ashbrook Cutoff, MS ....... 
Chicot Ldg., AR .............. 
Catfish Point, MS ........... 
Below Prentiss, MS ........... 
Malone Field, AR ............ 
Terrene, MS ................. 
White River Landing, AR ..... 
Montgomery Towhead, AR .... 
Victoria Bend, AR .......... 
Smith Point, MS .............. 
Island 70, MS ................ 
Total dikes, 
Vicksburg District, 
Mississippi River ........ 
482 
488 
493 
500 
505 
509 
510 
513 
514 
520 
523 
525 
528 
532 
538 
540 
540 
544 
547 
549 
564 
571 
580 
585 
590 
591 
592 
596 
600 
608 
LLL 
RLLR 
RL 
R
R
LLLRL 
R 
740 
O 
24,319 
24,6674 
8,238 
3,592 
6,730 
2,897 
9,614 
3,809 
7,571 
6,592 
5,754 O 
4,725 
5,278 
4,580 
16,668 
4,315 Z 
10,318 
13,646 
13,015 
8,728 
17,451 
5,290 
7,813 
7,549 - 
7,921 
2,201 
6,071 
5,0334 
7,617 
14,949 
R&L 
L&R 
LRL 
R
RL 
R
RRLL 
10,775 
(2.04 Miles) 
388,899 
(73.66 Miles)

Miles 
Above 
Mouth 
ARKANSAS RIVER5 
Standard Revetment: 
Menard Bend, AR ............ 31 
Como, AR .................. 34 
Morgan Bend, AR ............ 36 
Yancopin, AR ................ 24 
Total standard revetment, 
Arkansas River ........... 
Dikes: 
Hopedale Cutoff, AR .......... 30 
Morgan Bend, AR ............. 36 
Fletcher Bend, AR ............ 39 
Total dikes, Arkansas River.... 
RED RIVER6 
Standard revetment:8 
Dupre, LA .................. 69 
Bringol, LA ................. 73 
Egg Bend, LA ................ 75 
Cologne Bend, LA ............ 77 
Roxana, LA ................ 83 
Ryland, LA .............. 88 
Whittington, LA .............. 89 
Smith, LA ................... 91 
Latanier, LA ................ 93 
Hudson, LA ................ 99 
Robert, LA .................. 102 
Alexandria Front, LA ......... 105 
Callahan, LA ................ 110 
Cotton, LA ................. 116 
Rapides, LA ............... 119 
Boyce, LA ............. .... 125 
Total standard revetment, 
Red River ............... 
Dikes: 
Choctaw Bayou Bend, LA ...... 71 
Bringol (Egg Bend), LA ..... 73 
Egg Bend, LA ............... 75 
Cologne Bend, LA ............ 77 
Echo, LA .................. 78 
Richardson, LA .............. 79 
RL 
R
RRRRRR 
R
R
RRRRRRRR 
- - - 1,848 i 
- - - - - - 3,658 
- - - - - - - 2,187 r 
7,693 
(1.46 Miles) 
- - - - - - - 2,690 
- - - - - - - 4,000 0 
-- - - - - - 2,400 
- - - - - - - 650 
- - - - - - - 3,325 - 
- - - - - - - 3,925 m 
- - - - - - - 2,900 8 
- - - - - - - 2,700 z 
- - - - - - - 2,460 
- - - - - - - 1,458 
- - - - - - - 5,500 
- - - - - - - 5,280 
-- - - - - - 4,000 
- - - - - - - 14,700 
- - - - - - - 1,030 
- - - - - - - 4,548 
- - - - - - - 61,566 
(11.66 Miles) 
RRRRRR 
2,000 
2,477 
900 
1,850 
1,900 
2,700 
L
RL 
R 
11,770 
11,720 
5,250 
2,800 
31,540 
(5.97 Miles)

TABLE 42-I 
(Continued) 
BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(FISCAL YEAR 1986) 
Operations This FY 
Construction eNroantoivpe- Otpiveera- 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
RED RIVER' 
continued 
Dikes': 
Alexandria, LA .............. 105 R - - - - - - (Rock groin) 270 
Bertrand, LA................ 122 R - - - - - - 7,630 
Total dikes, Red River ....... - - - - - 19,727 
(3.74 Miles) 
1. Gross squares articulated concrete mattress (100 
square feet). 
2. Contains 7,814 linear feet of trenchfill revetment 
(stone). 
3. Linear feet of dike on which repairs were made. 
4. Changed to correct previous errors. 
5. See report on Arkansas River and tributaries, AR 
and OK, under Little Rock District. 
6. Mileages based on 1967 hydrographic survey. 
7. Includes all types of dikes and retards.

TABLE 42-J BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(FISCAL YEAR 1986) 
Operations This FY 
Construction eNroantoivpe- Otpiveera- 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)1 Feet) Feet) 
MISSISSIPPI RIVER 
Standard revetment: 
Big Island, AR .............. 598 R - - - - - - - 3,905 
Scrubgrass Bend, AR ......... 600 R - - - - - - 7,315 
Henrico, AR................. 606 R - - - - - - - 25,040 
Cessions Towhead, AR ........ 615 L - - - - - 2,683 - 10,615 
Knowlton, AR................ 620 R - - - - - - - 16,900 
Island 67, MS ............... 621 L - - - - - - - 7,625 
Island 68 Bar, AR ............ 622 R - - - - - - - 6,445 
Ludlow, AR ................. 626 R - - - - - - - 10,390 
Rescue Landing, AR-MS ...... 629 L - - - - - - - 27,020 
Fair Landing, AR ............ 632 R 25,690 
Burke Landing, MS ........... 637 L - - - - - 4,701 - 19,070 
Island 62, AR ............... 638 R - - - - - - - 9,030 
Island 63, MS ............... 639 L - - - - - - - 11,454 
Island 63 Bar, MS ............ 639 L - - - - - - - 3,795 
Oldtown Bend, AR ............ 644 R - - - - - 4,985 - 26,860 
Horseshoe, MS............... 647 L - - - - - - - 16,385 
Westover, AR................ 650 R - - - - - - - 12,730 
Delta-Friars Point, MS ........ 655 L - - - - - 2,550 - 30,090 
Helena, AR .................. 660 R - - - - - 1,417 - 36,460 
Trotters Landing, MS ......... 665 L - - - - - - - 32,905 
Flower Lake, MS ............. 667 L - - - - - - - 16,385 
St. Francis, AR............... 672 R - - - - - - - 24,663 
Harbert Point, MS ............ 675 L - - - - - - - 9,065 
Walnut Bend, AR ............ 680 R - - - - - - - 27,220 
Mhoon Bend, MS ............ 685 L - - - - - 10,826 - 35,828 
Peters, AR ................. 692 R - - - - - - - 23,675 
Commerce, MS .............. 695 L 5,3608 - - - - - - 23,575 
Porter Lake, AR ... :.......... 700 R - - - - - - - 34,155 
Pickett, MS-AR .............. 703 R - - - - - - - 12,575 
Norfolk-Star, MS ............ 709 L - - - - - - - 35,582 
Cow Island Bend, AR ......... 714 R - - - - - - - 22,274 
Cow Island Bend (Upper), 
TN ..................... 716 R - - - - - - 6,853 
Coahoma, TN ............... 717 L 9,270 
Ensley, TN ................. 723 L 41,766 
Dismal Point, AR ............ 724 R - - - - - - - 7,200 
Bauxippi-Wyanoke, AR ....... 730 R - - - - - 8,195 - 24,530 
Presidents Island, TN ......... 733 L 12,755 
Hopefield Point, AR, TN ....... 736 R - - - - - - - 5,390 
Loosahatchie-Memphis, TN .... 737 L - - - - - - - 31,293 
Loosahatchie Bar, TN ......... 740 R - - - - - - - 2,070 
St. Clair, AR ................. 742 R - - - - - - - 2,9302 
Island 40, TN-AR ............ 744 R - - - - - - - 30,750

TABLE 42-J 
(Continued) 
BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(FISCAL YEAR 1986) 
Operations This FY 
Construction Constrerative Nonop- Otpiveera- 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
MISSISSIPPI RIVER 
continued 
Standard Revetment: 
Brandywine, AR-TN ......... 
Shelby Forest, TN ......... 
Dean Island, AR .............. 
Cedar Point-Densford, TN ..... 
Chute of Island 35, TN ........ 
Lookout Bar, TN .......... 
Lookout, TN ................ 
Sunrise Towhead, TN ......... 
Lower Bullerton, AR .......... 
Kate Aubrey Towhead- 
Island 30, TN ............. 
Osceola, AR................ 
Osceola, AR .................. 
Ashport-Keyes Point, TN ...... 
Kate Aubrey, TN ............ 
Island 26, TN .............. 
Bend of Island 25, TN ......... 
Barfield, AR ................. 
Obion-Tamm, TN ............ 
Huffman-Hickman, AR-TN .... 
Heloise, TN ................ 
Island 18, MO ................ 
Linwood Bend, TN ......... 
Blaker Towhead, TN ....... 
Bells Point, MO .............. 
Gayoso-Caruthersville, MO .... 
Island 15, TN ............. 
Hathaway Landing, TN ....... 
Robinson Bayou, MO .......... 
Fritz Landing, TN ........... 
Lee Towhead, MO ............ 
Bend of Island 14, TN ......... 
Above Lee Towhead, TN ....... 
Little Cypress, MO .... .... 
Merriwether-Cherokee, TN .... 
Linda, MO .......... ......... 
Below Toney's Towhead, TN ... 
Toney's Towhead, KY-TN ..... 
New Madrid Bend, MO ........ 
Kentucky Point, KY .......... 
New Madrid Bar, KY ......... 
750 
753 
756 
759 
764 
772 
774 
776 
782 
786 
786 
786 
791 
793 
798 
803 
808 
819 
826 
831 
836 
841 
845 
845 
848 
851 
852 
852 
857 
859 
859 
861 
864 
869 
876 
879 
882 
886 
887 
888 
RL 
RLRRRRR 
RRRLRRLRLRLRLL 
RR 
LLRLLL 
L
RL 
RLL 
RL 
R 
(7) 
(7) 
7,900 20,859 
3,430 
1,450(9) 
1,821 
7,382 
18,010 
9,550 
7,555 
20,190 
29,190 
2,9902 
5,005 
14,615 
28,350 
(7) 30,808 
- 1,3503 
- 5,823 
44,232 
(7) 2,500 
- 15,690 
- 30,630 
- 46,070 
- 51,321 
- 26,984 
- 12,935 
- 22,170 
- 14,850 
- 17,087 
- 5,420 
- 25,600 
- 3,630 
- 1,000 
- 22,630 
- 15,670 
- 8,470 
- 12,050 
- 4,943 
- 34,090 
- 41,058 
- 11,950 
- 20,895 
- 3,430 
- 30,348 
- 7,960 
16,825 
0 
0
0
C2 
O
y
x
n
x
0
MW 
W

New Madrid, MO ............. 
La Forge, MO .............. 
Slough Landing Neck, 
TN-KY .................... 
Winchester Towhead, MO ..... 
Island 9, KY-TN ........... 
Milton Bell, MO ............ 
Chute of Island 8, KY ......... 
Bend of Island 8, MO ........ 
Island 8, KY ............... 
Hickman-Reelfoot, KY ....... 
Beckwith Bend, MO .......... 
Williams, KY ............... 
Wolf Island, KY ............. 
Columbus, KY .............. 
Belmont, MO ................. 
Island 3 and 4, KY ......... 
Campbell, KY ............... 
Pritchard, MO.............. 
Mayfield Creek, KY ........... 
Wickliffe, KY ........ 
Cache-Cairo, IL (Ohio River) ... 
Total revetment, 
Memphis District 
Mississippi River ......... 
Dikes: 
Henrico, AR ................. 
Below Knowlton, AR ........ 
Island 67, MS ............... 
Below Ludlow, AR .......... 
Sunflower, AR .............. 
Island 64, AR ................ 
Island 62, AR ............... 
Island 63 Bar, MS ........... 
Island 63, MS ............... 
Kangaroo Point, AR .......... 
Friars Point, MS ............. 
Montezuma Bar, MS ........ 
Montezuma Towhead, AR ..... 
Prairie Point, AR ............ 
Flower Lake, MS ............ 
St. Francis Towhead, MS ...... 
Below Walnut Bend, AR ....... 
Bordeaux Point, MS ......... 
Peters, AR ................... 
Commerce, MS .............. 
Basket Bar, AR ............. 
Buck Island, MS ............. 
Porter Lake, AR ........... 
Pickett, MS ................. 
Seyppel, AR .................. 
Cat Island, AR .............. 
Coahoma, TN ............... 
Armstrong, AR-TN ........... 
889 
892 
899 
900 
905 
908 
913 
914 
914 
919 
924 
927 
934 
937 
938 
940 
943 
948 
949 
953 
958 
RR 
LRLRLRRLRL
RL
RRLRLLR 
4,580 
-_ 
(7) 
(7) 
22,720 
(4.30 Miles) 
603 
616 
621 
624 
627 
630 
638 
639 
640 
649 
652 
657 
656 
668 
668 
671 
676 
681 
693 
694 
696 
700 
701 
704 
706 
710 
718 
720 
RRL
RL
RRLL
RLL
RRLL
RL
RL
RL
RL
RRL 
R 
28,241 
5,559 
20,680 
37,5207 
5,540 
33,5854 
14,375 
12,620 
9,800 
13,175 
43,359 
14,588 
10,015 
19,205 
3,825 
5,785 
19,970 
6,865 
15,045 
8,935 
8,455 
26,152 
37,178 
(5) 
400 - 
(7) 
(7) 
1,000 - 
- - 
- - 
- - 
6,98010 
7,830 
1,350 
350 
700 
200 
440 
1,838,545 
(348.21 Miles) 
(6) 
6,310 
10,233 
4,320 
5,040 
5,520 
7,330 
23,180 
2,600 
5,640 
5,730 
6,870 
12,430 
3,450 
10,391 
11,060 
3,380 
6,420 
4,920 
7,830 
5,700 
5,060 
4,705 
17,480 
7,180 
12,250 
15,590 
4,640 
18,690

TABLE 42-J BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(Continued) (FISCAL YEAR 1986) 
Operations This FY 
Construction eNroantiovpe- Otpiveera 
Above New Work Reinforcement Since Thru 
Head Bank Exten- Prior This 
Location of R sion Lap Mainte- FY FY 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)' Feet) Feet) 
MISSISSIPPI RIVER 
continued 
Dikes: 
Dismal Point, AR............. 724 R 25,510 
Hopefield Point, AR .......... 736 R 1,330 
Robinson Crusoe, TN .......... 738 R 21,9391 
Loosahatchie Bar, TN ......... 739 R - - - - - - - 3,950 
Above Loosahatchie, TN ....... 742 L - - - - - - - 8,990 
Redman Point, AR ............ 743 R - - - - - - - 7,750 
Randolph Point, TN ......... 747 L - - - 910 - - - 16,740 
Poker Point, AR .............. 748 R - - - 550 - - - 8,050 
Corona Bar, TN-AR ......... 755 R 8,430 
Densford, TN .............. 757 L - - - 500 - - - 7,780 
Cedar Point, TN .............. 759 L 2,890 
Below Richardson Landing, 
TN ........ ....... 767 L - - - - - - - 5,950 
Lookout, TN-AR ........... 771 R - - - - - - - 5,538 
Plum Point, TN .............. 784 L 1,785 - - - - - - 9,695 
Lake Neark, AR ............ 786 R - - - - - - - 2,5459 
Kate Aubrey, TN ........... 791 R - - - - - - - 11,270 
Keyes Point, TN .............. 791 L 19,775 
Ashport-Goldust, TN-AR ...... 795 R 17,330 
Forked Deer, TN ............. 798 L 8,550 
Island 25, AR .............. 804 R - - - - - - - 5,450 
Nebraska Point, TN ......... 808 L - - - - - - - 12,149 
Below Tamm Bend, TN ....... 813 L - - - - - - -8,300 
Wrights Point, AR ............ 820 R 2,130 - - - - - 32,635 
Island 21, Chute, TN .......... 824 L - - - - - - 3,170 
Head of Island 21, TN ......... 828 L - - - - - - - 5,460 
Island 20, MO-TN ........... 831 R - - - 4,600 - - - 18,139 
Island 18, TN .............. 837 L - - - - - - 8,670 
Tennemo, TN................ 842 L - - - 800 - - - 4,390 
Blaker Towhead, TN .......... 843 L - - - 4,000 - - - 4,070 
Caruthersville-Linwood 
Bend, MO ................ 844 R - - - - - - - 25,877 
Sandy Hook, TN .............. 850 R 2,350 
Island 15, TN................ 851 L - - - - - -7,510 
Robinson Bayou, MO ........ 853 R - - - 6,550 - - - 9,890 
Hathaway, TN............... 854 L - - - 500 - - - 26,750 
Island 15 Neck, TN ........... 854 L - - - - - - - 21,100 
Above Lee Towhead, TN ....... 859 L - - - - - - - 1,300 
Below Cherokee, TN .......... 866 L - - - - - - - 6,230 
Stewart Towhead, MO ........ 871 R - - - - - - - 18,290 
Ruddles Point, MO ........... 874 R - - - 900 - - - 8,130

Island 11, MO ................ 
Kentucky Point, KY .......... 
Morrison Towhead, MO ....... 
Hotchkiss Bend, MO .......... 
Below Island 9, TN ........... 
Donaldson Point, MO ........ 
Island 9, KY ............... 
Moore Island, KY-MO ........ 
Above Williams, KY .......... 
Campbell, KY................ 
Pritchard, MO............... 
Island 1, KY ................. 
Total dikes, 
Memphis District, 
Mississippi River ......... 
882 
887 
890 
895 
901 
905 
906 
929 
930 
942 
944 
948 
RLRRLRLRLLRL 
700 (7 ) 
(7) 
4,039 
11,550 
1,070 
6,583 
18,859 
8,320 
7,0106 
4,685 
1,1508 
2,610 
9,390 
15.260 
-
180 
500 
11,745 
(22.2 Miles) 
6,980 25,130 - 748,347 
(141.73 Miles) 
1. Gross squares-articulated concrete mattress (100 
square feet). 
2. Lumber mattress revetment 
3. Rock groins. 
4. Stone in pile dike. 
5. Linear feet of dike on which repairs were made. 
6. Linear feet of triangular frame retards and pile 
dikes. 
7. Changed to correct previous errors. 
8. No ACM, riprap paving only, unattached trench fill. 
9. No ACM, riprap paving only. 
10. Raised the height of the dike. 
H
Ct2 
c
C, 
0
C,, 
Cn 
O
0z

TABLE 42-K PROJECT LEVEES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1986) 
Levees and Floodwalls Berms (Miles) Surfaced Roadson Levees 
(Miles) (Miles) 
Built to Approved Total 
Location Total Grade and Section In In Com- 
In Total System Com- System plete 
Authorized Place Thru When Built plete When Built Thru 
for This This This Com- This This Corn- This This 
System FY FY FY pleted' FY FY pleted FY FY 
MISSISSIPPI RIVER 
Fifth Louisiana Levee District .......... 
Levees ............................ 
Floodwalls ..... ............... 
Old River structures and levees ....... 
Atchafalaya Basin Levee District ...... . 
Levees ........................... 
Floodwalls ..... ............... 
Morganza structure and levee ...... 
Morganza forebay levee .............. 
Port Allen lock ..................... 
Lafourche Basin Levee District ......... 
Levees ............................. 
Plaquemines West Levee District ....... 
Levees ..... ....................... 
Floodwalls ..................... 
Buras Levee District ................... 
Levees ............................. 
Floodwalls ...................... 
Empire lock ....................... 
Baton Rouge front levees ........... .... 
Pontchartrain Levee District ........... 
Levees .............................. 
Floodwalls ...................... 
Bonnet Carre guide levees ......... 
Bonnet Carre forebay levee ........ 
Bonnet Carre structure .............. 
East Jefferson Levee District ........... 
Levees ........................... 
Floodwalls .................... 
West Jefferson Levee District ........... 
Levees ... ....................... 
Floodwalls .......................... 
Harvey Canal Lock ............... 
Orleans Levee District ................. 
Left descending, east bank 
Levees ........................... 
Floodwalls .......................... 
IHNC lock .................... 
(16.8) 
15.5 
1.3 
(126.3) 
118.7 
0.8 
6.7 
0.1 
(61.7) 
61.7 
(37.9) 
37.9 
(34.1) 
34.0 
0.1 
(2.1) 
(124.9) 
110.8 
11.3 
1.3 
1.5 
(11.6) 
11.6 
(20.0) 
19.8 
0.1 
0.1 
(27.2) 
4.6 
8.6 
0.1 
(16.8) 
15.5 
1.3 
(126.3) 
118.7 
0.8 
6.7 
0.1 
(61.7) 
61.7 
(37.9) 
37.9 
(34.1) 
34.0 
0.1 
(2.1) 
(124.9) 
110.8 
11.3 
1.3 
1.5 
(11.6) 
11.6 
(20.0) 
19.8 
0.1 
0.1 
(27.2) 
4.6 
8.6 
0.1 
(-) 
(-) 
(-) 
(-) 
- 
(-) 
(-) 
(5.0) 
5.0 
(0.1) 
0.1 
(1.8) 
1.6 
(10.7) 
9.4 
1.3 
(85.4) 
77.8 
0.8 
6.7 
0.1 
(24.1) 
24.1 
(28.5) 
28.5 
(19.7) 
19.7 
(0.9) 
(91.1) 
77.0 
11.3 
1.3 
1.5 
(10.8) 
10.8 
(4.6) 
4.4 
0.1 
0.1 
(19.5) 
(-) 
(5.3) 
5.3 
(0.1) 
0.1 
(-) 
(-) 
(-) 
(4.7) 
4.7 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(1.1) 
1.1 
(-) 
- 
(0.1) 
0.1 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) 
0.6 
6.8 
0.1 
(15.5) 
15.5 
(118.7) 
118.7 
(61.7) 
61.7 
(37.9) 
37.9 
(34.0) 
34.0 
(2.1) 
(110.8) 
110.8 
(11.6) 
11.6 
(19.9) 
19.8 
0.1 
(18.4) 
- 4.6 
(-) (15.5) 
- 15.5 
(-) (118.7) 
- 118.7 
(-) (61.7) 
- 61.7 
(-) (37.9) 
- 37.9 
(-) (34.0) 
- 34.0 
(-) (2.1) 
(-) (110.8) 
- 110.8 
(-) (11.6) 
- 11.6 
(-) (19.9) 
- 19.8 
- 0.1 
(-) (18.4) 
- 4.6

Right descending, west bank 
Levees .............................. 
Floodwalls .................... 
Algiers Canal lock ................. 
Lake Borgne Basin Levee District ....... 
Levees ........................... 
Floodwalls ...................... 
Grand Prairie Levee District ........... 
Levees ........................... 
Floodwalls ..... ............... 
Total Mississippi River ........... 
ATCHAFALAYA BASIN FLOODWAY 
Atchafalaya River and 
Bayou des Glaises ................ 
East bank Atchafalaya River ....... 
Bayou des Glaises .................... 
West bank Atchafalaya River ......... 
Simmesport Ring .................. 
Melville Ring .................. 
Krotz Springs Ring ................ 
Mansura Hills to Hamburg .......... 
West protection levee, Hamburg to Berwick 
drainage canal via Calumet ....... 
Levees west of Berwick, Berwick drainage 
canal to Charenton drainage canal ..... 
Morganza upper guide levee ............ 
East protection levee, Morganza to Cutoff 
Bayou, including 19.5 miles of Morganza 
lower guide levee .... .............. 
Total Atchafalaya Basin and 
Floodway ................... 
Total-Main Stem System ...... 
LAKE PONTCHARTRAIN, LA 
Lake Pontchartrain, LA ............... 
Item A levees ........................ 
Item B levees ........................ 
Item C levees ........................ 
Total ........................... 
C? 
13.8 
0.1 
(11.6) 
11.6 
(37.4) 
37.4 
511.6 
(148.4) 
52.5 
7.9 
60.1 
1.6 
4.1 
1.7 
20.5 
13.8 
0.1 
(11.6) 
11.6 
(37.4) 
37.4 
511.6 
(148.4) 
52.5 
7.9 
60.1 
1.6 
4.1 
1.7 
20.5 
(128.7) (128.7) 
(56.5) (56.5) 
(8.9) (8.9) 
(106.7) (106.7) 
0.2
(-) 
(0.5) 
0.5 
7.4
(-) 
11.9 
0.1 
(11.5) 
11.5 
(19.7) 
19.7 
326.5 
(143.9) 
52.5 
7.9 
55.6 
1.6 
4.1 
1.7 
20.5 
(2.3) (69.6) 
(-) 
(-) 
(9.6) 
(8.9) 
(8.0) (48.8) 
(-) 
- 
(-) 
10.1
(-) 
(-) 
(-) 
(-) 
- 
(-) 
(-) 
1.2 
(-) 
-
- 
(-) (-) 
(-) 
(-) 
(-) 
(-) 
(-) (-) 
(-) 
- 
13.8 
(11.6) 
11.6 
(37.4) 
37.4 
479.6 
(148.4) 
52.5 
7.9 
60.1 
(-) 
(-) 
(-) 
13.8 
(11.6) 
11.6 
(37.4) 
37.4 
479.6 
(43.9) 
20.2 
12.0 
- 1.ti - - 
- 4.1 - - 
- 1.7 - - 
- 20.5 - 11.7 
(-) (127.7) (2.3) (68.6) y 
(-) (56.5) (-) (-) 
(-) (8.9) (-) (8.9) C 
(-) (105.0) (8.0) (47.2) 
449.2 449.2 10.3 280.8 - - - 446.5 10.3 168.6 
960.8 960.8 17.7 607.3 10.1 1.2 926.1 10.3 648.2 
(17.4) (17.4) (-) (17.4) (-) (-) (-) (17.4) (-) (17.4) 
5.0 5.0 - 5.0 - - - 5.0 - 5.0 
10.1 10.1 - 10.1 - - - 10.1 - 10.1 
2.3 2.3 - 2.3 - - - 2.3 - 2.3 
17.4 17.4 - 17.4 - - - 17.4 - 17.4 
D 
CI) 
CI) 
zz 
1. Figures indicate !andside seepage berms only. 
-

TABLE 42-L PROJECT LEVEES: VICKSBURG DISTRICT 
(FISCAL YEAR 1986) 
Levees and Floodwalls Berms (Miles) Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved Total 
Location Total Grade and Section In Com- In Com- 
In Total System System plete 
Authorized Place Thru When Built plete When Built Thru 
for This This This Comrn- This This Com- This This 
System FY FY FY2 pleted3 FY4 FY pleted FY FY 
MISSISSIPPI RIVER 
East bank in Mississippi .............. 178.35 178.3 - 109.1 158.9 6.8 114.9 168.4 - 168.4 
Greenville Harbor dikes ................ 7.8 7.8 - 7.8 - - - - 
West bank in Arkansas ................ 75.6 75.6 2.4 47.6 51.7 12.9 49.3 75.4 - 75.4 
West bank in Louisiana 
(above Red River) .................. .. 198.7 198.7 - 67.1 88.7 2.1 69.4 197.8 197.8 
Total Mississippi River ............. 460.4 460.4 2.4 231.6 299.3 11.8 233.6 442.5 - 442.5 
YAZOO RIVER BASIN 
Headwater .......................... 624.76 305.6 6.1 136.7 - - - 620.7 (-) 281.5 
Backwater .......................... 96.6 44.6 - 0.0 - - - 96.6 39.0 
Total Yazoo River Basin ............ 721.3 350.2 6.1 136.7 - - - 717.3 (-) 320.5 
ARKANSAS RIVER, ARKANSAS 
North bank .......................... 61.57 56.2 - 56.2 8.3 - 8.3 47.4 - 47.4 
South bank .......................... 85.4 85.4 - 85.4 24.7 - 24.7 84.1 - 81.1 
Total Arkansas River .............. 146.9 141.6 - 141.6 33.0 - 33.0 131.5 - 128.5 
RED RIVER BACKWATER LEVEES 
Total Red River backwater ......... 263.6 157.7 - 138.78 - - - 249.0 - 141.9 
LOWER RED RIVER- SOUTH BANK 
RED RIVER 
Lower Red River-South Bank 
Red River levees .................... (59.2) (59.2) (.1) (59.2) (-) (-) (-) (59.2) (-) (33.6) 
Hotwells to Moncla, LA, levees ........ 59.2 59.2 .1 59.29 - - - 59.2 33.6 
Floodwalls.........................- - - - - - - 
Total Lower Red River ............. 59.2 59.2 - 59.2 - - - 59.2 33.6 
1. This tabulation does not include riverside berms 
which are considered an integral part of the levee section. 
Riverside berms will be constructed along with levee 
enlargements or seepage berm contracts. 
2. Levee that has adequate freeboard based on the 
refined 1973 MR&T project flood flow line for the 
Mississippi River. Levees with more than 2 feet of freeboard 
are considered adequate. 
3. Subject to change as planning progresses. Does not 
include existing berms which need restudy. 
4. Based on refined 1973 MR&T project flood flow line. 
5. Includes 1.4 miles of concrete floodwall and 0.3 mile 
of levee on Vicksburg city front. 
6. Includes 36.9 miles of local protection works; 61.3 
miles along Whittington Auxiliary Channel; 210 miles in 
Upper Yazoo Projects; 156.1 miles along main stem; and 
160.4 miles on tributaries. 
7. Includes 5.3 miles for Gillett new levee. 
8. Reflects results of 1985 flowline reanalysis.

TABLE 42-M PROJECT LEVEES: MEMPHIS DISTRICT 
(FISCAL YEAR 1986) 
Levees and Floodwalls Berms (Miles)1 Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved Total 
Location Total Grade andSection In Com- In Com- 
In Total System System plete 
Authorized Place Thru When Built plete When Built Thru 
for This This This Com- This This Com- This This 
System FY FY FY pleted' FY FY pleted FY FY 
MISSISSIPPI RIVER 
Mounds, IL ............................ 
Mound City, IL ........................ 
Cairo Drainage District ............ 
City of Cairo ........................... 
Little River Drainage District .......... 
Levee District No. 2, 
Scott County, MO ................... 
Levee District No. 3, 
Mississippi County, MO ............... 
St. Johns Leveee and 
Drainage District ................... 
St. Francis Levee District of MO ........ 
City of Hickman, KY ................. 
Board of Levee Commissioners 
Fulton County, KY ................... 
Reelfoot Levee District of Lake and 
Obion Counties, TN ................. 
Madrid Bend Levee District, 
Lake Co., TN ......................... 
Lake County Levee and 
Drainage District ................... 
Dyer County Levee and 
Drainage District No. 1 ............... 
Tipton-Obion levee extension ........... 
St. Francis Levee District of AR ......... 
Helena Improvement District No. 1 ...... 
Cotton Belt Levee District No. 1 ......... 
Laconia Drainage and Levee District 
Phillips County, AR ................ 
Laconia Levee District No. 1 of 
Desha County, AR ................... 
Laconia Circle Special Drainage 
District of Desha County, AR ........... 
Yazoo-Mississippi Delta Levee 
District .............................. 
Madrid Bend L.D., 
Fulton Co., KY ....................... 
3.9 
2.7 
13.82 
6.2 
19.3 
3.9 
2.7 
13.8 
6.2 
19.3 
3.9 
2.7 
13.8 
6.2 
19.3 
13.8 
26.0 
13.8 13.8 
26.0 26.0 
59.0 58.7 
55.7 55.7 
1.4 1.4 
16.7 16.7 
4.5 4.5 
5.2 5.2 
15.9 15.9 
21.3 
6.5 
156.7 
5.3 
23.9 
0.5 
2.5 
4.6 
4.4 
4.9 
4.2 
12.9 
.0 .5 
.1 1.7 
0.9 
3.3 4.9 
4.9 26.0 
- 46.9 
12.0 55.1 
- 0.5 
58.2 43.0 
55.7 23.0 
1.4 - 
16.74 15.5 
4.54 
5.2 4 
15.9 
21.3 
153.24 
5.3 
23.9 
21.3 
156.7 
5.3 
23.9 
20.5 20.5 
18.1 18.1 
6.6 6.6 
93.6 93.6 
20.5 
0.6 
9.1 
1.3 
94.6 
2.4 
18.8 
11.5 
18.14 12.9 
6.64 
93.6 87.3 
11.4 
0.3 4.5 
5.2 
4.5 15.9 
0.4 
80.3 
2.4 
18.8 
11.5 
9.2 16.5 
87.3 
4.4 4.4 - 4.44 
3.6 
1.1 
8.5 
4.0 
19.3 
13.8 
16.3 
3.6 
1.1 
8.5 
3.5 
19.3 
13.8 
26.0 
46.1 
55.1 - C 
16.3 C 
4.3 
5.2 
15.9 
21.3 
156.7 
4.2 
23.9 
20.5 
16.5 
93.6 
21.3 
6.5 
156.7 
4.7 
23.9 
20.5 
93.6 
4.4 -4.4

TABLE 42-M 
(Continued) 
PROJECT LEVEES: MEMPHIS DISTRICT 
(FISCAL YEAR 1986) 
Levees and Floodwalls Berms (Miles)' Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved Total 
Location Total Grade and Section In Com- In Com- 
In Total System System plete 
Authorized Place Thru When Built plete When Built Thru 
for This This This Com- This This Com- This This 
System FY FY FY pleted' FY FY pleted FY FY 
MISSISSIPPI RIVER-continued 
Birds Point-New Madrid 
setbacklevee ......................... 35.3 35.3 - 35.3 35.3 - - 35.3 - 35.3 
Total Mississippi River ............. 636.3 629.5 - 625.5 389.3 3.4 251.0 604.1 - 595.1 
ST. FRANCIS RIVER 
East bank ............................. 159.5 156.2 - 156.2 - - - 156.7 - 81.7 
West bank ........................... 148.7 146.7 - 146.7 - - - 144.3 - 38.8 
Total St. Francis River ............. 308.2 302.9 - 302.9 - - - 301.0 - 120.5 
LITTLE RIVER 
East bank (left) ....................... 40.7 40.7 - 40.7 - - - 40.7 - 13.1 
West bank ................. ......... 35.1 35.1 -35. 35.1 - 23.7 
Elk Chute ............................. 39.9 39.9 - 39.9 - - - 39.7 - 17.3 
West Basin and middle valley ........... 14.4 14.4 - 14.4 - - - 13.4 - 13.4 
Total Little River .................. 130.1 130.1 - 130.1 - - - 128.9 - 67.5 
LOWER WHITE RIVER 
White River backwater levee ........... 40.2 40.2 - 40.2 - - - 38.8 - 38.8 
Augusta to Clarendon .................. 49.2 39.5 - 39.5 - - - 49.2 - 36.2 
Clarendon levee ....................... 6.2 6.2 - 4.4 - - - - 
Total Lower White River ........... 95.6 85.9 - 84.1 - - - 88.0 - 75.0 
MEMPHIS HARBOR 
Memphis Harbor ...................... 10.5 10.5 - 10.5 7.0 - 1.5 10.5 10.5 
1. Subject to change as planning progresses. 
2. Includes 5.1 miles of Cache River levee. This levee was 
enlarged to 1928 grades with Federal funds, but since that 
time has been classified as a secondary levee. 
3. Includes 12.1 miles of Farrenburg levee. This levee 
was enlarged to 1928 grades with Federal funds, but since 
that time has been classified as a secondary levee. 
4. Shown complete. Authority MSRC-ED-TL (MD 19 
Mar. 80) 1st Ind. 21 Apr. 80.

TABLE 42-N 
RECAPITULATION 
PROJECT LEVEE TABLES 42-K, -L, AND -M 
(FISCAL YEAR 1986) 
Levees and Floodwalls Berms (Miles) Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved Total 
Location Total Grade and Section In Com- In Com- 
In Total System System plete 
Authorized Place Thru When Built plete When Built Thru 
for This This This Com- This This Comrn- This This 
System FY FY FY pleted FY FY pleted FY FY 
MISSISSIPPI RIVERMAIN 
STEM 
New Orleans District, Table 42-K ....... 511.6 511.6 7.4 326.5 10.1 (-) 1.2 479.6 - 479.6 
Vicksburg District, Table 42-L .......... 460.4 460.4 2.4 231.6 299.3 11.8 231.3 442.5 - 442.5 
MemphisDistrict, Table 42-M .......... 636.3 629.5 - 625.5 389.3 5.9 251.0 604.1 - 595.1 
Subtotal-Main Stem ............... 1,608.3 1,601.5 9.8 1,183.6 698.7 17.7 483.5 1,526.2 - 1,517.2 
TRIBUTARIES (OFF MAIN STEM) 
INCLUDED IN MR&T SYSTEM 
Atchafalaya Basin 
Floodway--NOD .................... 449.2 449.2 10.3 280.8 - - - 446.5 10.3 168.6 
Lower Red River- 
South Bank-VXD .................. 59.2 59.2 .1 59.2 - - - 59.2 - 33.6 
Arkansas River-South Bank-VXD...... 85.4 85.4 - 85.4 24.7 - 24.7 84.1 - 81.1 
Subtotal-Tribs. in MR&T System .... 593.8 593.8 10.4 425.4 24.7 - 24.7 589.8 10.3 283.3 
Total in MR&T System ............. 2,202.1 2,195.3 20.2 1,609.0 723.4 17.7 510.5 2,116.0 10.3 1,800.5 
OTHER TRIBUTARIES IN 
MR&T PROJECT 
Lake Pontchartrain, LA,-NOD ........ 17.4 17.4 - 17.417.4 - 17.4 
Yazoo River Basin-VXD .............. 721.3 356.5 6.1 136.7 - - - 717.3 - 320.5 
Arkansas River-North Bank-VXD....... 61.5 56.2 - 56.2 8.3 - 8.3 47.4 - 47.4 
Red River Backwater-VXD ........... 263.6 157.7 - 138.7 - - - 249.0 - 141.9 
St. Francis River-MD ................ 308.2 302.9 - 302.9 - - - 301.0 - 120.5 
Little River-MD ...................... 130.1 130.1 - 130.1 - - - 128.9 - 67.5 
Lower White River-MD ............... 95.6 85.9 - 84.1 - - - 88.0 - 75.0 
Memphis Harbor-MD ................ 10.5 10.5 - 10.5 7.0 - 1.5 10.5 - 10.5 
Subtotal-Other Tribs. in 
MR&T Project .................... 1,608.2 1,117.2 6.1 814.3 15.3 - 9.8 1,559.5 - 800.7 
Grand Total in Project ............. 3,810.3 3,312.5 26.3 2,485.6 738.7 17.7 520.3 3,675.5 10.3 2,601.2 
Cl) 
C12 
C,, 
0
zO7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 42-0 CHANNEL IMPROVEMENTS: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1986) 
Location 
Year 
Initiated 
In 
System 
When 
Completed 
Built 
This 
FY 
(Miles) 
Total 
Complete 
Thru 
This 
FY 
Bayou des Glaise diversion channel ................. 1938 6.0 - 6.0 100 
Bayous Rapides, Boeuf, and Cocodrie ............... 1946 92.6 - 63.4 75 
Charenton drainage and navigation canal ........... 1939 6.3 - 6.3 100 
Wax Lake Outlet .................................. 1938 15.7 - 15.7 100 
Atchafalaya Basin Floodway ...................... 1933 244.2 - 186.4 76 
Morganza Floodway ............... ............... 1941 3.3 - 3.3 100 
Old River outflow channel ........................ 1956 8.3 - 8.3 100 
Old River inflow channel .......................... 1960 2.3 1.9 2.3 100 
Old River lock approach channels ................. 1961 2.2 - 2.2 100 
Baton Rouge Harbor (Devils Swamp) ............... 1958 2.5 - 2.5 100 
Eastern Rapides-S.C. Avoyelles ..................... - 83.5 - - - 
Teche-Vermillion Water Supply .................... - 6.3 - 6.3 100 
42-50 
Percent 
Complete

MISSISSIPPI RIVER COMMISSION 
TABLE 42-P CHANNEL IMPROVEMENTS: VICKSBURG DISTRICT 
(FISCAL YEAR 1986) 
In Total 
System Complete 
Year When Built Thru 
Location Initi- Corn- This This Percent 
ated pleted FY FY Complete 
(Miles) 
BIG SUNFLOWER RIVER, ETC., MS 
Big Sunflower River .............. ............... 1947 199.1 - 199.1 100 
Quiver River ..................................... 1947 69.6 - 69.6 100 
Deer Creek ............................ ...... .... 1947 7.0 - 7.0 100 
Steele Bayou ...................................... 1947 54.9 - 54.9 100 
Steele Bayou' ................ .... ............... 1965 71.2 - 63.0 70 
Main Canal ............... ....................... 1959 21.1 - 21.1 100 
M ain Canal2 . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . - 22.2 - - 
Black Bayou ..................................... - 36.5 - - 
Big Sunflower River tributaries ................... 1957 227.2 - 227.2 100 
Quiver River tributaries ........................... 1960 35.4 - 35.4 100 
YAZOO BACKWATER 
Yazoo Backwater ................................. 1960 39.9 - 39.9 100 
YAZOO BASIN HEADWATER, MS 
Upper Yazoo Project .............................. 1976 179.0 1.6 54.1 30 
Coldwater River .................................. 1941 54.6 - 54.6 100 
Arkabutla Canal ............................... 1948 0.4 - 0.4 100 
Tallahatchie Canal ................................ 1940 74.8 - 73.5 85 
little Tallahatchie River and 
Panola-Quitman Floodway .................... 1939 48.0 - 48.0 100 
Greenwood protection works ....................... 1971 2.9 - 2.9 100 
Yacona River ..................................... 1952 1.8 - 1.8 100 
Bobo Bayou ....................................... 1944 16.1 - 16.1 100 
Cassidy Bayou .................................... 1934 69.0 - 69.0 100 
Cassidy Bayou3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . - 26.0 - - 
Bear Creek Diversion ....................... .......... - 4.8 - - 
Lake Cormorant ................................. . - 20.9 - - 
Hurricane Bayou ................................. - 2.5 - - 
Opossum Bayou ..................... ............ - 20.8 - - 
Abaica Creek ................................... - 7.7 - - 
Chicopa Creek ................................. - 7.0 - - 
Bear Creek ....................................... - 23.3 - - 
Rocky Bayou ......... .... ..... ... ............... - 7.8 - - 
Whiteoak Bayou ................................. - 55.9 - - 
Miscellaneous ditches ........................... .. - 12.3 - - 
Yalobusha River .................................. 1939 46.0 - 46.0 100 
Yazoo River ...................................... 1940 160.2 - 160.2 100 
Whittington Auxiliary Channel .................... 1956 30.8 - 30.8 100 
Tchula Lake ................................... 1964 26.4 - 26.4 100 
David-Burrell Bayou ............................ 1957 40.4 - 40.4 100 
McKinney Bayou ................................. 1960 3.5 - 3.5 100 
Hillside Floodway .............................. 1964 11.0 - 11.0 100 
Yazoo City protection works ...................... 1953 1.6 - 1.6 100 
Ascalmore-Tippo Bayous ......................... 1975 30.2 - 15.1 50 
Alligator-Catfish Bayou ........................... 1973 8.3 - 8.2 99 
Pelucia Creek ................................. 1975 6.4 - 2.9 25 
BOEUF & TENSAS RIVERS, ETC., 
LA AND AR 
Bayou Lafourche ............ ... ........... 1949 45.3 - 45.3 100 
Bayou Lafourche4 ,7 . . . . . . . . . . . . . . .. . . . . . . .. . . .. 1972 43.0 - 4.4 10 
Big & Colewa Creeks ........................... 1947 81.4 - 81.4 100 
42-51

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 42-P CHANNEL IMPROVEMENTS: VICKSBURG DISTRICT 
(Continued) (FISCAL YEAR 1986) 
Location 
BOEUF & TENSAS RIVERS, ETC., 
LA AND AR- continued 
Big & Colewa Creeks 5,7 . . . . . . . . .. . . . . . . . . . ... . . . .... 
Tensas River ..................................... 
Tensas River 6 ......... . . . . . . . . . . . . . . . . . . . . . . . . . . . . 
Boeuf River, AR and LA .......................... 
Fleschmans Bayou, AR ............................ 
Caney Bayou, AR ............. ............. 
Canal 18, AR .................................... 
Big Bayou, AR ................................... 
Black Pond Slough, AR ........................... 
Bayou Macon, AR and LA 
Rush Bayou, AR ................................. 
Canal 19, AR .................................... 
Canal 43, AR .................................... 
Canal 81, AR .................................... 
Mill Bayou-Bayou Vidal ........................... 
Kirsch Lake Canal ................................ 
Canal 19 Extension ............................... 
Lake Chicot Pumping Plant .................... 
RED RIVER BACKWATER, LA 
Tensas-Cocodrie Pumping Plant ............ .... 
Six Mile Bayou, LA ............................ 
GRAND PRAIRIE, AR .......................... 
BAYOU METO, AR ............................. 
1. Includes further work on 54.9 miles and adds 16.3 
miles of channel to the project. 
2. Includes further work on 21.1 miles and adds 1.1 
miles of channel to the project. 
3. Includes further work on 26.0 miles. 
4. Includes further work on 38.6 miles and adds 4.4 
miles of channel to the project. 
5. Includes further work on 75.3 miles and adds 11.5 
miles of channel to the project. 
6. Includes further work on 96.5 miles and adds 68.5 
additional miles of channel to the project. 
7. Further work on these items has been deferred due to 
local oppositions and withdrawal of sponsorship by the levee 
district. 
42-52 
Year 
Initiated 
In 
System 
When 
Completed 
Built 
This 
FY 
(Miles) 
Total 
Complete 
Thru 
This 
FY 
1965 
1947 
1968 
1953 
1963 
1964 
1963 
1952 
1962 
1959 
1964 
1957 
1956 
1957 
1964 
1976 
51.5 
96.5 
61.0 
103.9 
6.6 
7.4 
10.3 
33.3 
14.3 
150.8 
6.7 
50.2 
34.5 
32.7 
9.4 
2.5 
86.8 
96.5 
165.0 
103.9 
6.6 
7.4 
10.3 
33.3 
14.3 
150.8 
6.7 
50.2 
34.5 
32.7 
14.8 
9.3 
9.4 
2.5 
6.9 
1.5 
338.1 
164.9 
Percent 
Complete 
60 
100 
37 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
94 
100 
6.5 
1.5

MISSISSIPPI RIVER COMMISSION 
TABLE 42-Q CHANNEL IMPROVEMENTS: MEMPHIS DISTRICT 
(FISCAL YEAR 1986) 
In Total 
System Complete 
Year When Built Thru 
Location Initi- Com- This This Percent 
ated pleted FY FY Complete 
(Miles) 
BIRDS POINT-NEW MADRID 
FLOODWAY 
Birds Point-New Madrid Intercepting Ditch 
Enlargement, Samos and Vicinity, MO ........... 1952 9.6 - 9.5 100 
ST. FRANCIS BASIN 
Little River Drainage, MO. ........................ 1963 291.3 7.3 247.0 85 
St. Francis River, MO and AR ..................... 1953 602.7 7.0 378.0 63 
West Memphis Drainage, AR ..................... 1951 19.8 - 19.8 100 
Big Slough and Mayo Ditch, AR .................... 1960 28.0 - 28.0 100 
Tyronza River, AR ............................. 1939 12.7 - 12.7 100 
L'Anguille River, AR ............................. (1) 112.0 - - 
LOWER WHITE RIVER 
BASIN, AR 
Cache River Basin, AR ......................... 1972 231.5 - 7.2 3 
Big Creek and tributaries, AR ...................... (1) 103.8 - - 
WEST KENTUCKY TRIBUTARIES 
Obion Creek, KY ................................ (1) 41.7 
WEST TENNESSEE TRIBUTARIES 
MS River, Western TN tributaries 
(Backwater Areas) (1946 Act) ................... 1952 34.3 - 34.3 100 
Obion River Diversion Channel, 
TN (1946 Act) ................................. (1) 9.3 
Reelfoot Lake-Lake No. 9, KY 
and TN ....................................... 1974 15.8 - 3.0 19 
Running Reelfoot Bayou, TN ...................... 1955 19.7 - 19.7 100 
MS River Below Cape Girardeau; West 
TN tributaries. (1948 Act) ...................... 1961 225.0 5.0 89.8 40 
Wolf River and tributaries, TN .................... 1960 25.5 - 25.5 100 
1. Not started. 
42-53

TABLE 42-R 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
COSTS DURING FISCAL YEAR 1986 
Item Construction Maintenance Other 
FEDERAL FUNDS 
Flood control, Mississippi River and tributaries: 
St. Louis District: 
General investigations 
Advance engineering and design 
St. Francis Basin-WappapelloLake 
Subtotal 
Memphis District: 
General investigations 
Advance engineering and design 
Mississippi River levees 
St. Francis Basin 
Lower White River 
Cache Basin, Ark. 
Channel improvement 
West Tennessee tributaries 
West Kentucky tributaries 
Inspection of completed works 
Mapping 
Reelfoot Lake No. 9, TN-KY 
Mud Lake, TN 
Eight Mile Creek 
Subtotal 
Vicksburg District: 
General investigations 
Advance engineering and design 
Mississippi River levees 
Lower Arkansas River 
Tensas Basin 
Yazoo Basin 
Channel improvement 
Mapping 
Inspection of completed works 
Tensas National Wildlife Refuge, LA 
Lower Red River-South Bank Red River Levee 
Dam Safety Assurances 
6,525,196 
9,288,482 
14,834 
12,035,502 
2,746,236 
100,003 
35,308 
7,043 
423,426 
31,176,030 
7,258,721 
9,608,172 
19,878,153 
12,789,569 
60,287 
44,699 
10,034 
3,368,034 
3,368,034 
2,826,774 
4,380,119 
340,007 
23,081,609 
660,782 
108,731 
31,398,022 
852,303 
537,605 
2,548,627 
16,737,727 
12,898,743 
200,836 
136,716 
119,718 
-- 
2,711,043 
-- 
_-- 
-- 
-- 
-- 
-- 
2,711,043 
1,508,761 
Subtotal 
New Orleans District: 
General investigations 
Advance engineering and design 
Mississippi River levees 
Old River 
Bayou Cocodrie and tributaries 
Atchafalaya Basin 
Atchafalaya Basin Floodway System 
Channel improvement 
Teche-Vermilion Basin water supply 
Inspection of completed works 
Mapping 
Subtotal 
Total Federal Funds 
49,649,635 34,032,275 1,508,761 
-- -- 1,735,728 
13,948,537 8,365,246 -- 
34,408,774 5,413,810 -- 
165,217 113,831 -- 
26,560,637 8,599,948 -- 
160,779 -- -- 
40,462,157 11,265,100 -- 
3,959 -- -- 
-- 203,502 -- 
-- 198,577 -- 
115,710,060 34,160,014 1,735,728 
196,535,725 102,958,345 5,999,532 
42-54

TABLE 42-R 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
COSTS DURING FISCAL YEAR 1986 
Item Construction Maintenance Other 
CONTRIBUTED FUNDS 
New Orleans District: 
Old River -- 120,039 -- 
Atchafalaya Basin 20,758 -- -- 
Mississippi River Levees 331,991 6,756 -- 
Channel Improvement -- 12,826 
Total Contributed Funds 352,749 139,621 -- 
Grand Total, Federal 
and Contributed Funds 196,888,474 103,097,966 5,955,532 
42-55

TABLE 42-S 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES FOR FLOOD CONTROL, 
MISSISSIPPI RIVER AND TRIBUTARIES, 
FROM MAY 15, 1928, THROUGH SEP. 30, 1986 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30, 1986 
ALLOTMENTS AND ACCRUED EXPENDITURES 
CHARGEABLE AGAINST FLOOD CONTROL 
ACT LIMITATIONS: 
COMPLETED WORKS: 
Waterways Experiment Station 
Office, Chief of Engineers 
Rock Island District: 
S. G. & O. prior to Aug. 18, 1941 
St. Louis District: 
S. G. & O. prior to Aug. 18, 1941 
Subtotal 
Memphis District: 
Des Arc, Ark. 
Contraction works 
DeValls Bluff, Ark. 
Mapping 
Memphis Harbor 
New Madrid Floodway 
Wolf River and tributaries 
Roads on levees (Mississippi River levees) 
S. G. & O. prior to Aug. 18, 1941 
Subtotal 
Vicksburg District: 
Boeuf Basin levees 
Channel realignment, Arkansas River 
Contraction works 
Eudora Floodway 
Vicksburg Harbor 
Greenville Harbor 
Grants Canal (Mississippi River levees) 
Mapping 
Jonesville, LA 
Roads on levees 
S. G. & O. prior to Aug. 18, 1941 
Subtotal 
New Orleans District: 
Baton Rouge Harbor, LA 
Atchafalaya River and Basin, LA 
Bonnet Carrb Spillway, LA 
Contraction works 
Mapping 
Roads on levees 
S. G. & O. prior to Aug. 18, 1941 
Wax Lake Outlet and Charenton Canal 
Morganza Floodway and structure 
Lake Pontchartrain 
Atchafalaya Basin, rights-of-way and flowage, 
Bayou des Glaises setback 
Subtotal 
All other completed items: 
Surveys under Sec. 10, Flood Control Act of 1928 
Impounded savings 
Plant transferred to revolving fund 
OCE (portion of allotment transferred to 
revolving fund, Washington Dist.) 
Subtotal 
Total completed works 
$ 874,000 
19,158 
14,010 
$ 874,000 
19,158 
14,010 
169,352 169,352 
1,076,520 1,076,520 -- 
178,925 178,925 -- 
8,692,791 8,692,791 -- 
231,215 231,215 -- 
1,450,337 1,450,337 -- 
18,736,432 18,736,432 -- 
6,521,543 6,521,543 -- 
1,723,620 1,723,620 -- 
12,426 12,426 -- 
1,998,766 1,998,766 -- 
39,546,055 39,546,055 -- 
2,764,605 2,764,605 -- 
125,074 125,074 -- 
1,972,183 1,972,183 -- 
826,235 826,235 -- 
4,664,515 4,664,515 -- 
2,864,516 2,864,516 -- 
7,070 7,070 -- 
1,531,021 1,531,021 -- 
172,950 172,950 -- 
105,660 105,660 -- 
2,350,201 2,350,201 -- 
17,384,030 17,384,030 
699,185 699,185 -- 
3,375,492 3,375,492 -- 
14,212,198 14,212,198 -- 
1,258,916 1,258,916 -- 
1,112,967 1,112,967 -- 
540,838 540,838 -- 
2,701,566 2,701,566 -- 
10,098,817 10,098,817 -- 
35,992,117 35,992,117 -- 
5,513,110 5,513,110 -- 
387,917 387,917 
75,893,123 75,893,123 -- 
4,995,215 4,995,215 -- 
1,593,097 1,593,097 -- 
24,924,578 24,924,578 -- 
19,882 19,882 -- 
31,532,772 31,532,772 -- 
165,432,500 165,432,500 -- 
42-56

MISSISSIPPI RIVER COMMISSION 
TABLE 42-S 
(Continued) 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES FOR FLOOD CONTROL, 
MISSISSIPPI RIVER AND TRIBUTARIES, 
FROM MAY 15, 1928, THROUGH SEP. 30, 1986 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30,1986 
UNCOMPLETED WORKS: 
Rock Island District: 
Levees under Sec. 6, Flood Control Act of 1928 
St. Louis District: 
Levees under Sec. 6, Flood Control Act of 1928 
Subtotal 
Memphis District: 
Mississippi River levees 
Mississippi River levees 
New Madrid 
Channel improvement: 
Revetments 
Dredging 
Dikes 
Reelfoot Lake 
Reelfoot Lake, Lake No. 9, TN-KY 
St. Francis Basin: 
Wappapello Lake 
St. Francis River and tributaries 
Big Slough and Mayo ditch 
Little River drainage 
Lower White River: 
Clarendon Levee 
Augusta to Clarendon, AR 
White River backwater levee, AR 
Levees under Sec. 6, Flood Control Act of 1928 
West Tennessee tributaries 
Cache Basin, AR 
West Kentucky tributaries 
Mud Lake Pumping Station, TN 
Eight Mile Creek 
Subtotal 
Vicksburg Distict: 
Mississippi River levees (excludes Grants Canal, 
$7,070, shown under completed works) 
Lower Arkansas River: 
North Bank 
South Bank 
Tensas Basin: 
Lake Chicot pumping plant 
Boeuf and Tensas Rivers, etc. 
Red River Backwater: 
Red River backwater levee, LA 
Tensas, Cocodrie pumping plant 
Lower Red River South Bank Red River Levees 
Tensas National Wildlife Refuge, LA 
Channel improvement: 
Revetments 
Dredging 
Dikes 
Levees under Sec. 6, Flood Control Act of 1928 
Yazoo Basin: 
Sardis Lake 
Enid Lake 
Arkabutla Lake 
579,462 
1,897,980 
2,477,442 
163,284,354 
98,000 
320,796,307 
57,249,400 
111,945,000 
439,434 
7,895,000 
9,019,908 
189,911,282 
965,429 
47,505,992 
496,715 
1,779,846 
10,624,501 
108,651 
34,607,900 
7,930,000 
1,344,000 
107,000 
424,000 
966,532,720 
194,311,990 
7,049,414 
15,676,286 
88,756,800 
40,333,200 
52,344,646 
49,509,300 
438,400 
39,800,000 
350,833,065 
23,549,260 
78,017,040 
958,175 
26,537,600 
21,325,400 
16,017,700 
579,462 
1,897,980 
2,477,442 
163,257,429 
98,000 
320,763,622 
57,249,400 
111,913,145 
439,434 
7,871,650 
9,019,908 
189,752,603 
965,429 
47,487,535 
496,715 
1,779,846 
10,624,501 
108,651 
34,550,304 
7,929,834 
1,093,946 
80,169 
423,426 
965,905,551 
193,712,453 
7,049,414 
15,676,286 
88,388,085 
40,176,135 
52,166,032 
48,612,805 
231,325 
39,787,700 
349,687,941 
23,549,260 
77,035,635 
958,175 
26,503,676 
21,292,057 
16,000,700 
33,924 
33,343 
42-57 
26,925 
-- 
32,685 
31,855 
-- 
23,350 
-- 
158,679 
-- 
18,457 
-- 
-- 
-- 
57,596 
166 
250,054 
26,831 
574 
627,169 
599,537 
368,715 
157,065 
178,613 
896,495 
207,075 
12,300 
1,145,124 
981,405

TABLE 42-S 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES FOR FLOOD CONTROL, 
MISSISSIPPI RIVER AND TRIBUTARIES, 
FROM MAY 15, 1928, THROUGH SEP. 30, 1986 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30,1986 
Yazoo Basin: (Continued) 
Grenada Lake 
Greenwood 
Belzoni 
Yazoo City 
Will M. Whittington auxiliary channel 
Big Sunflower, etc. 
Main Stem 
Upper Yazoo Projects 
Yazoo Basin-Tributaries 
Tributaries (Except Ascal-Tippo-Opossum Bayous) 
Tributaries-Bank Stabilization 
Ascalmore-Tippo-Opossum Bayous 
Yazoo Basin Backwater 
Yazoo Backwater (Except Muddy Bayou) 
Muddy Bayou 
Steambank Erosion Control, Eval. and Demo. 
Demonstration Erosion Control 
Dam Safety Assurances-Sardis Dam 
Subtotal 
New Orleans District: 
Teche-Vermilion Basin Water Supply 
Bayou Cocodrie and Tributaries 
Channel improvement: 
Dredging 
Revetments 
Lower Red River (South Bank Levees) 
Levees Under Sec. 6, Flood Control Act of 1928 
Mississippi River Levees 
Atachafalaya Basin: 
Atachafalaya Basin Floodway 
Atachafalaya River Navigation 
Atachafalaya Basin Floodway System 
Old River 
Subtotal 
TOTAL UNCOMPLETED WORKS 
ADVANCE ENGINEERING AND DESIGN 
(CONSTRUCTION) 
Memphis District: 
L'Anguille River Basin, AR 
Reelfoot Lake, Lake No. 9 
Cache River 
Big Creek and Tributaries, Lower White River 
Clarendon Levee, Lower White River 
West Kentucky Tributaries 
Mud Lake Pumping Station, TN 
Harris Fork Creek, KY & TN 
Subtotal 
Vicksburg District: 
Yazoo Basin, Big Sunflower River, Steele Bayou 
Tensas - National Wildlife Refuge, LA 
Subtotal 
45,375,900 
11,543,000 
316,656 
2,205,611 
10,950,966 
35,075,300 
30,405,000 
50,4.40,006 
63,234,310 
612,484 
24,082,200 
64,067,200 
5,145,200 
14,767,000 
12,877,000 
387,000 
1,376,926,110 
33,806,000 
4,918,008 
35,945,266 
529,183,117 
18,056,600 
200,680 
206,936,000 
529,552,537 
303,463 
270,000 
281,068,000 
1,640,239,671 
45,354,193 
11,543,000 
316,656 
2,205,611 
10,950,966 
34,012,070 
27,891,401 
49,174,440 
62,225,154 
612,484 
23,434,559 
60,905,768 
5,145,200 
14,767,000 
7,323,412 
10,034 
1,356,699,627 
33,806,000 
4,898,700 
35,945,266 
528,712,999 
18,056,600 
200,680 
206,689,374 
528,916,184 
303,463 
160,778 
280,906,441 
1,638,596,485 
21,707 
--
-- 
1,063,230 
2,513,599 
1,265,566 
1,009,156 
-- 
647,641 
3,161,432 
-- 
5,553,588 
376,966 
20,226,483 
19,308 
470,118 
-- 
246,626 
636,353 
109,222 
161,559 
1,643,186 
3,986,175,942 3,963,679,105 22,496,838 
150,000 150,000 -- 
30,000 30,000 -- 
420,000 420,000 -- 
365,000 364,339 -- 
65,000 65,000 -- 
175,000 175,000 -- 
350,000 350,000 -- 
540,000 540,000 -- 
2,095,000 2,095,000 -- 
29,700 29,700 -- 
200,000 200,000 -- 
229,700 229,700 -- 
42-58

MISSISSIPPI RIVER COMMISSION 
TABLE 42-S 
(Continued) 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES FOR FLOOD CONTROL, 
MISSISSIPPI RIVER AND TRIBUTARIES, 
FROM MAY 15, 1928, THROUGH SEP. 30, 1986 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30,1986 
New Orleans District: 
Mississippi Delta Region 69,753 69,753 -- 
Teche Vermilion Basin-Water Supply 1,109,000 1,109,000 -- 
East Rapides & S. Central Avoyelles Parishes 965,247 965,247 -- 
Subtotal 2,144,000 2,144,000 -- 
TOTAL ADVANCE ENGINEERING 
AND DESIGN 4,468,700 4,468,700 -- 
TOTAL COMPLETED WORKS, UNCOMPLETED 
WORKS AND ADVANCE ENGINEERING 
AND DESIGN 4,156,077,142 4,133,580,304 22,496,838 
RECREATION FACILITIES-COMPLETED 
PROJECTS 
Eight-Year Program Funds 
St. Louis District: 
Wappapello Lake, MO 2,405,300 2,404,890 410 
Wappapello Lake, MO, Rockwood Landing 203,286 203,286 -- 
Subtotal 2,608,586 2,608,176 410 
Vicksburg District: 
Sardis Lake 1,584,339 1,584,339 -- 
Enid Lake 2,268,209 2,268,209 -- 
Arkabutla Lake 2,189,280 2,189,280 -- 
Grenada Lake 1,631,281 1,631,281 -- 
Subtotal 7,673,109 7,673,109 -- 
Total Eight-Year Program Funds 10,281,695 10,281,285 410 
Total chargeable against Flood Control 
Act Limitations excluding flood 
control emergencies 4,166,358,837 4,143,861,589 22,497,248 
Total maintenance since Aug. 18, 1941 1,587,427,855 1,584,352,178 3,075,677 
Total rehabilitation 31,113,000 31,113,000 -- 
Total flood control emergencies 14,900,300 14,900,300 -- 
Total general investigations 60,341,881 58,229,130 2,112,752 
Total flood control, MR&T appropriations 5,860,141,873 5,832,456,197 27,685,677 
Appropriations in addition to flood control, MR&T 
Other appropriations itemized in footnote (1), 
pp. 2068-69, Annual Report for 1953 32,068,909 32,068,909 -- 
Grand total appropriated to Sep. 30, 1985 5,892,210,782 5,864,525,105 27,685,677 
Note: Preauthorization study costs chargeable to the MR&T authorization have been transferred to completed work. Costs 
not chargeable have been exluded from this report. 
42-59

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 42-T STATEMENTS OF EXPENDITURES FOR LEVEES 
BY STATE AND LOCAL ORGANIZATIONS 
THROUGH DEC. 31, 1985 
Engineer 
District Expenditures 
St. Louis $ 79,372,809 
Memphis 257,043,764 
Vicksburg 125,192,794 
New Orleans 548,153,561 
Total $1,009,762,928 
42-60

MISSISSIPPI RIVER COMMISSION 
TABLE 42-U COST AND FINANCIAL STATEMENT 1 
Total 
Project Funding FY 83 FY 84 FY 85 FY 86 Sep. 30, 1986 
Mississippi River General investigations: 
and tributaries Alloted 4,271,000 6,805,000 4,510,000 6,809,000 60,341,8812 
(Regular Funds)1 Cost 4,583,214 5,722,645 5,499,308 5,955,532 58,229,129 
Construction (includes 
advance engineering 
and design): 
Alloted 289,370,000 199,330,000 216,083,000 194,438,000 3,986,175,942 
Cost 204,211,601 265,108,622 224,369,411 196,535,725 3,963,679,105 
Maintenance 
Alloted 109,548,000 94,345,000 102,554,000 100,480,000 1,637,806,406 
Cost 90,732,587 111,777,503 104,920,222 102,958,345 1,424,890,280 
Rehabilitations 
Alloted 137,000 -- -- -- 31,113,000 
Cost 18,385 -- -- -- 31,113,000 
Flood control emergencies 
(Maintenance): 
Alloted -- -- -- -- 14,885,922 
Cost -- -- -- -- 14,885,922 
(Contributed Funds) New Work: 
Contributed 393,600 46,311 315,294 20,000 9,580,771 
Cost 296,065 56,321 63,875 352,749 9,558,878 
Maintenance 
Contributed 125,424 128,923 279,972 169,279 2,335,014 
Cost 51,592 161,616 242,576 139,621 2,170,324 
1. Appropriations were as follows: 
Appropriations chargeable against Flood Control Act authorizations: 
Flood Control, MR&T except for emergencies (excludes Maintenance 
allotments Aug. 18, 1941, through Sep. 30, 1986): 
Net total allotted for works under Mississippi River Commission: $4,155,657,370 
Eight-Year Program Funds, Construction General: 10,281,695 
Surveys under Sec. 10, Flood Control Act of 1928 (not under MRC): 4,995,215 
Transferred to revolving fund: 24,944,460 
Impounded savings: 1,593,097 $4,197,471,837 
Flood control emergencies: 
Net total alloted: 14,885,922 
Impounded savings: 14,378 14,900,300 
Additional funds not chargeable against Flood Control Act authorizations: 
Appropriations for Flood Control, MR&T, except for flood control emergencies: 
General investigations: 60,341,881 
Maintenance allotments Aug. 18, 1941, through Sep. 30, 1986 1,587,427,855 1,647,769,736 
Appropriations in addition to appropriations for Flood Control, MR&T 
(itemized in footnote (1), pp. 2068-69, Annual Report for 1953): 32,068,909 
Budgetary and OCE Reserves: 
Grand total: 5,892,210,782 
Reconciliation of appropriations and allotments: 
Total allotted to Sep. 30, 1986 5,860,663,632 
Transferred to revolving fund: 24,944,460 
Surveys under Sec. 10, Flood Control Act of 1928 (not under MRC): 4,995,215 
Impounded savings withdrawn by Chief of Engineers: 1,607,475 
Total Appropriations to Sep. 30, 1986: 5,892,210,782 
Appropriations for past four reporting periods were as follows: 
FY 82: $262,798,000; FY 83: $403,052,000; 
FY 84: $300,480,000; FY 85: $323,297,000; 
FY 86: $301,727,000. 
2. Totals for General Investigations include four projects transferred from 
Construction totals per DAEN-CWB-W, Aug. 4, 78, teletype. 
42-61

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 42-V MISSISSIPPI RIVER AND TRIBUTARIES 
ACTIVE GENERAL INVESTIGATIONS 
(96x3112) 
Federal Cost Totals by 
Item and CWIS Number FY 86 Categories 
($) ($) 
SURVEYS (Category 100) 
Flood Damage Prevention (112) 
New Orleans District 
Atchafalaya Basin Water & Land Res - 12026 173,345 
Subtotal 173,345 
Vicksburg District 
Boeuf-Tensas Basin, AR & LA - 81273 614,351 
Larto Lake-Saline Lake, LA - 12065 288,745 
Southwest Mississippi Tributaries Basin, MS - 12351 3,089 
Yazoo River Basin, MS - 12074 354,557 
Subtotal 1,260,742 
Memphis District 
Bayou du Chien - 33008 239,283 
Eastern AR Reg-Comprehensive Study - 81266 428,756 
Helena & Vicinity- 12165 2,906 
Mayfield Creek- 10850 54,437 
Reelfoot Lake, TN -00086 299,593 
St. Francis River Below Wappapello - 22000 306,220 
Tiptonville, TN- 12246 189,968 
West Memphis, AR- 12164 1,185 
Subtotal 1,552,348 
TOTAL (Category 110) 2,956,435 
COLLECTION AND STUDY OF BASIC DATA (Category 120) 
Vicksburg District 167,264 
MemphisDistrict 67,575 
TOTAL (Category 120) 234,839 
SUPPLEMENTAL PRE-AUTH STUDIES (Category 130) 
Flood Damage Prevention 132) 
Vicksburg District 
MS River East Bank Natchez - 76022 25,599 
Memphis District 
Nonconnah Creek, TN (Phase I)- 77007 26 
TOTAL (Category 130) 25,625 
CONTINUATION OF PLANNING & ENGINEERING (Category 140) 
Flood Control Projects (142) 
New Orleans District 
MS-LA Estuarine Area ADVCPE - 12193 964,516 
Vicksburg District 
Bushley Bayou Area, LA- 75226 55,157 
Memphis District 
St. Johns Bayou & New Madrid Fdwy - 77005 378,753 
Nonconnah Creek, TN & MS- 12417 302,653 
TOTAL (Category 140) 681,406 1,701,079 
42-62

MISSISSIPPI RIVER COMMISSION 
TABLE 42-V 
(Continued) 
MISSISSIPPI RIVER AND TRIBUTARIES 
ACTIVE GENERAL INVESTIGATIONS 
(96x3112) 
Federal Cost Totals by 
Item and CWIS Number FY 86 Categories 
ADVANCE ENGINEERING & DESIGN (Category 160) 
Flood Control Projects (162) 
New Orleans District 
Eastern Rapides & S.C. Avoyelles Parishes - 75031 124,960 
Mississippi Delta Region - 23270 472,907 
Subtotal 597,867 
Memphis District 
Harris Fork Creek, TN & KY - 77009 5,403 
L'Anguille River Basin - 00082 434,284 
Subtotal 439,687 
TOTAL (Category 160) 1,037,553 
GRAND TOTAL MR&T GENERAL INVESTIGATIONS 5,955,531 
42-63

NATURAL DISASTER PREPAREDNESS 
RESPONSE AND RECOVERY ACTIVITIES 
Authority. Public Law 84-99, as amended, (Flood Control 
and Coastal Emergencies) provides authority for 
the Chief of Engineers to undertake disaster 
preparedness activities, flood fighting and rescue work, 
rehabilitation of flood control works damaged or 
destroyed by flood, protection or repair of Federally 
authorized shore protective works threatened or damaged 
by coastal storm, provision of emergency drinking 
water, and drought assistance. 
Activities. FY 1986 disaster preparedness activities 
included the review and update of existing emergency 
response plans; development of required new plans; 
training of response personnel exercises to test plans, 
personnel and training procurement and maintenance of 
critical supplies and requirements not readily available 
during initial response phase; maintenance and required 
upgrade of emergency operations centers; coordination 
with Federal, State and local response agencies and 
other public entities; and overall management of the 
preparedness program. 
The Corps responded to major flood problems on the 
Island of Puerto Rico in October 1985 and again in May 
1986. In October, a tropical wave (became Tropical 
Storm Isabel) caused major flooding and extensive landslides. 
Deaths were estimated at 180 people, over 5,000 
people were forced from their homes, and damage 
estimates reached $125 million. The Corps of Engineers 
responded by sending geotechnical people to assist in 
the search for survivors in landslide areas, in addition to 
damage assessment teams. 
During FY 86, the record high water levels in the 
Great Lakes continued to cause flood problems. The excess 
precipitation has continued averaging six percent 
above normal during the first seven months of the year. 
The Corps of Engineers have provided $7 million in temporary 
flood protective works and flood fighting 
assistance in those areas which were beyond State and 
local capabilities. Technical assistance and investigations 
continue. 
As the year progressed flooding throughout the 
United States was extensive. The Midwest from the 
Lower Great Lakes, across the Ohio River Valley and into 
the Mid-Atlantic states experienced severe flooding 
in November 1985 and May to June 1986. The Great 
Lakes Region was to be hit with flooding once more, in 
September 1986. In February 1986, it was the Coastal 
and Central Valley of California to Western Nevada to 
experience disastrous flooding. After suffering the effects 
of one of the severest droughts in the history of the 
South, heavy rains brought flooding to North and South 
Carolina in August 1986. The Corps provided technical 
assistance, flood fighting equipment and materials to 
Federal, State, and local entities. After the flood waters 
receded, the Corps undertook necessary investigations 
and appropriate rehabilitation of damaged flood control 
projects. 
In the South and East, the Corps responded to several 
hurricanes and tropical storms from October 1985 to 
August 1986. Four hurricanes struck the United States 
in FY 86, killing at least 21 people and doing more than 
$1,03 billion in damages. The Hurricane Juan system 
brought flooding through the South and East. Hurricane 
Kate hit Mexico Beach, Florida on November 21, 
1985, and was downgraded to a tropical storm ten hours 
later but, not before it had left four dead, over $1 million 
in damages and caused the evacuation of 100,000 people 
in thirteen counties. On June 26, 1986, Hurricane Bonnie 
hit land between Galveston and Port Arthur, Texas 
with 85 mph winds. Four people died and damage was 
well in excess of $1 million. Hurricane Charlie traveled 
up the East Coast, crossing the Outer Banks, North 
Carolina on August 17, 1986 leaving six dead and over 
$1 million in damages. 
Corps assistance as a result of these major storms included 
flood fight assistance and rehabilitation activities 
under the Corps PL 84-99 emergency authority, 
and work in support of the Federal Emergency Management 
Agency under its PL 93-288 assistance authority. 
STATUS OF THE PL 84-99 EMERGENCY FUND 
Unallocated Balance as of 30 Sep 85 .... 
FY 1986 Appropriation .............. 
FY 1986 Supplement Appropriation ... 
FY 1986 Cut (Graham-Rudman) ....... 
Revocation FY 1986 ................. 
Total Funds Available ............... 
Allocations 
Disaster Preparedness ............ 
Emergency Operations ............ 
Rehabilitation..................... 
Advance Measures................ 
Hazard Mitigation . ............... 
Unallocated Balance as of 30 Sep 86 .... 
$ 24,559,307 
25,000,000 
25,000,000 
(1,075,000) 
6,432,035 
$79,916,338 
$ 9,642,999 
3,850,932 
20,212,874 
4,611,413 
20,868 
$ 41,577,252 
43-1

CALIFORNIA DEBRIS COMMISSION 
This Commission, consisting of three Corps officers 
appointed by the President with the consent of the 
Senate, created by act of March 1, 1893 (27 Stat. L., p. 
507), was organized in San Francisco, CA, on June 8, 
1893, and has jurisdiction and duties extending over 
drainage area of Sacramento and San Joaquin Rivers, 
comprising great central valley of California and extending 
from crest of the Sierra Nevada on the east to that of 
the Coast Range on the west, and from Mount Shasta 
and Pit River Basin on the north to Tehachapi Mountains 
on the south. These rivers empty into head of Suisun 
Bay ultimately discharging into Pacific Ocean through 
connecting bays and straits and the Golden Gate. Duties 
of the Commission comprise regulation of hydraulic 
mining in drainage area of Sacramento and San Joaquin 
Rivers, CA, so that debris will not be carried into 
navigable waters or otherwise cause damage; jurisdiction 
over construction and control of water storage 
facilities for domestic, irrigation, and power development 
purposes; and direction of improvements for 
control of floods on Sacramento River. 
IMPROVEMENTS 
Navigation Page 
1. Regulation of hydraulic mining and 
preparation of plans ..................... 44-1 
2. Sacramento River and tributaries, CA 
(debris control) ........................... 44-2 
3. Treatment of Yuba River debris 
situation-restraining barriers, CA ...... 44-2 
Navigation 
1. REGULATION OF HYDRAULIC 
MINING AND PREPARATION 
OF PLANS 
Location. Operations largely limited to territory 
between Mount Lassen on the north and Yosemite 
Valley on the south, on western watershed of Sierra 
Nevada. (See Geological Survey sheets for the area, 25 
in number.) 
Existing project. Provides for regulating hydraulic 
mining operations, planning improvement of conditions 
upon Sacramento and San Joaquin Rivers and their 
tributaries affected by such operations, and preparation 
of plans to enable hydraulic mining to be resumed in 
their drainage areas. In addition, the Secretary of the 
Army is authorized to enter into contracts to supply 
storage for water and use of outlet facilities from 
debris-storage reservoirs for domestic and irrigation 
purposes and power development upon such conditions 
of delivery, use, and payment as he may approve. 
Applications of prospective miners are fully investigated 
by California Debris Commission and permits to operate 
Flood Control Page 
4. Sacramento River, CA .................. 44-3 
Tables 
Table 44-A Cost and Financial 
Table 44-B 
Statement .................... 44-5 
Authorizing 
Legislation .................... 44-6 
are issued to those who provide satisfactory debrisrestraining 
basins by construction of suitable dams 
where necessary or agree to make payment for storage 
in Government-constructed debris-restraining reservoirs 
constructed under act of June 19, 1934, as set forth 
below. For location and description of Governmentconstructed, 
debris-restraining reservoirs for general 
hydraulic mining, see Improvement 2. 
Local cooperation. Mineowners must bear all expenses 
incurred in complying with orders of the Commission 
for regulation of mining and restraint of debris. 
Operations and results during fiscal year. Minor 
administrative duties were accomplished. Administrative 
work overlaps that of improvements 2, 3, and 4, 
hereunder, and that of Sacramento District. 
Historical summary. The Commission received 1,292 
applications for hydraulic mining licenses; 1 mine is 
licensed, but does not use storage behind Government 
debris dams. Work remaining is, in general, continuation 
of above or similar operations. 
44-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
2. SACRAMENTO RIVER AND 
TRIBUTARIES, CA (DEBRIS 
CONTROL) 
Location. Project reservoirs are to be constructed in 
watersheds of Yuba, Bear, and American Rivers, CA 
(See Geological Survey sheets for basin areas, seven in 
number.) 
Existing project. For description of completed North 
Fork and Harry L. Englebright projects and authorizing 
act, see Annual Report for 1975. Initial recreation 
facilities were provided in FY 1959. Recreation areas at 
Harry L. Englebright Dam are maintained by the 
Corps. Recreation areas at North Fork Dam are no 
longer maintained and operated by Auburn Recreation 
Park and Parkway District, but have been turned over 
to the Bureau of Reclamation (known as the Water and 
Power Resources Service between November 6, 1979, 
and May 18, 1981) on a permit basis. Total Federal cost 
of new work for construction of these reservoirs was 
$4,646,872, including $40,000 and $25,000, respectively, 
for basic recreation facilities at Englebright Dam and 
North Fork Dam. Reservoir project sites on Middle 
Fork of American River and on Bear River have been 
deauthorized and excluded from foregoing cost. The 
90-day Congressional project review period, required 
by sec. 12, Public Law 93-251, as amended, ended 
August 5, 1977, and resulted in deauthorization of that 
portion of the project. Estimated cost of that portion is 
$1,820,000 (1935). 
Local cooperation. Fully complied with. Improvements 
made to facilities at North Fork Dam by Auburn 
Recreation Park and Parkway District under a lease 
agreement with the Secretary of the Army and Auburn 
Boat Clubs (concessionaire) at an estimated cost of 
$46,000 since September 1953. On March 1, 1979, lands 
and waters at North Fork Dam were turned over to the 
Bureau of Reclamation on a 5-year renewable basis. On 
March 1, 1984, Permit No. DACWO5-4-79-527 was 
renewed for another 5 years and will be effective until 
February 28, 1989. Bureau will operate and maintain 
such use until Auburn project is completed, then a fee 
transfer will be made. Actual operation and maintenance 
of the recreation resource is being done by State 
of California by contract with the Bureau. 
Licenses. Under provisions of Contract No. W-1105- 
eng-2998 with Pacific Gas and Electric Co., payment is 
to be made to the Federal Government of $18,000 per 
year for the first 30 years (December 29, 1942 through 
December 28, 1972) and $48,000 per year between 
December 29, 1972, and December 28, 1992, in return 
for use of head at Englebright Dam and generation of 
hydroelectric power. Total payment through September 
30, 1986, amounts to $1,182,393; these funds 
are paid to California Debris Commission and deposited 
for return to the Treasury. License No. 2246, effective 
April 9, 1970 (date New Narrows powerplant put in 
operation) was issued by Federal Power Commission 
(known as the Federal Energy Regulatory Commission 
since January 9, 1978) to Yuba County Water Agency 
for hydroelectric power development of Yuba River by 
the company upstream from Englebright Dam. Under 
provisions of Contract No. DA-04-167-CIVENG-66-95 
with Yuba County Water Agency, payment is to be 
made to the Federal Government of $100,000 per year 
for no more than 50 years. First payment (partial) of 
$73,151 was made April 1, 1971; total payment through 
September 30, 1986, amounts to $1,573,151. These 
funds are paid to Sacramento District and deposited for 
return to the Treasury. 
Operations and results during fiscal year. New 
work: Maintenance: Maintenance and operation activities 
continued at Harry L. Englebright Dam at a cost of 
$644,522, including recreation facilities. Dam safety 
assurance studies were continued at Englebright Dam 
at a fiscal year cost of $192,168. 
Historical summary. Construction of dams was 
initiated in 1937; North Fork project was completed 
and in use at end of FY 1939, and Harry L. Englebright 
project was completed in January 1941. The two debriscontrol 
structures are in good condition. Public use of 
these reservoir recreation areas greatly overtaxes present 
capacities. Dam safety assurance studies were 
initiated at Englebright Dam in FY 1981. 
3. TREATMENT OF YUBA RIVER 
DEBRIS SITUATIONRESTRAINING 
BARRIERS, CA 
Location. Works are on Yuba River between Marysville 
and where the river emerges from the foothills, 
near Hammonton, some 10 miles easterly from Marysville, 
or about 9 miles below the Narrows. (See Geological 
Survey Topographic map of Sacramento Valley, CA) 
Existing project. For description of completed project 
and authorizing act, see Annual Report for 1975. 
Total cost of new work was $723,259, of which $361,482 
was U.S. funds and $361,777 required contributed 
funds by State of California. (For details of project in its 
form, see Annual Report, 1917, p. 1810.) In February 
1963, center section of dam failed and major rehabilitation 
of structure was completed in December 1964. 
Total cost for required rehabilitation was 
$1,660,000, of which $830,000 was Federal cost and 
$830,000 required contribution by State of California 
toward rehabilitation cost. During the December 24, 
1964, floodflows on the Yuba River, the rehabilitated 
Daguerre Point Dam sustained considerable damage. 
(See 1965 Annual Report, p. 1647 "Operations and 
results during fiscal year.") The reconstructed portion 
of the dam completed earlier in December 1964 was 
undamaged by the flood. Permanent repair of Daguerre 
Point Dam abutment and fish facilities was completed 
in October 1965 at a cost of $447,808 with Federal and 
required State contributed funds on a matching basis. 
Local cooperation. Fully complied with for new 
work and major rehabilitation work. Total first cost to 
local interests for new work was $361,777 (required 
44-2

CALIFORNIA DEBRIS COMMISSION 
contribution by State of California). In addition, training 
walls were built on each bank below Daguerre Point for 
11,250 feet and just above Daguerre Point, on the south 
bank, for 11,000 linear feet by two gold-dredging 
companies in connection with their dredging operations. 
To build these training walls would have cost the 
United States $450,000 (1902 estimate). Flood channels 
were also built by gold-dredging companies within 
confines of project works. Cost to the United States of 
equally effective works to restrain debris movement 
would have been more than $776,000 (1926 estimate). 
Total costs to local interests for initial and permanent 
major rehabilitation works were $830,000 and $223,904, 
respectively, (required contribution by State of California). 
State of California must contribute annually an 
amount equal to the Federal allotment for maintenance. 
Operations and results during fiscal year. Maintenance: 
Operations included condition and operation 
studies by hired labor; and bank protection, Yuba 
River, various locations upstream from Marysville 
completed by contract, $40,926. 
Historical summary. Construction of project works 
was initiated in November 1902. Construction of 
Daguerre Point Dam was completed in May 1906; 
diversion of river over dam was completed in 1910; 
training walls and dikes were completed in 1935. About 
149 million cubic yards of debris are held in lower 7 
miles of Yuba River between Marysville and downstream 
end of training walls. About 20 million cubic 
feet, are confined in river channel by Daguerre Point 
Dam. Additional millions of yards of loose material are 
in mine tailing fields adjacent to project training walls 
in upper 7-mile reach of project. Initial rehabilitation of 
Daguerre Point Dam begun in July 1963 was completed 
in December 1964. Contract for permanent rehabilitation 
of structure was initiated in July and completed in 
October 1965. 
Flood Control 
4. SACRAMENTO RIVER, CA 
Location. Works covered by this improvement are on 
Sacramento River and tributaries in north-central 
California from Collinsville to Ordbend, a distance of 
184 miles. 
Previous project. For details see page 1815 of 
Annual Report for 1917, page 1995 of Annual Report for 
1938, and page 2262 of Annual Report for 1907. 
Existing project. Sacramento River flood control 
project is a comprehensive plan of flood control for 
Sacramento River and lower reaches of its principal 
tributaries. Improvement extends along Sacramento 
River from Ordbend in Glenn County, CA, 184 miles 
downstream to its mouth at Collinsville at upper end of 
Suisun Bay, and comprises a system of levees, overflow 
weirs, drainage pumping plants, and flood bypass 
channels or floodways designed to carry surplus floodwaters 
without inundation of valley lands. About 980 
miles of levee construction, with an average height of 15 
and 98 miles of bank protection are involved in project. 
For further details, see Annual Report for 1962, page 
2115. (See table 44-B for authorizing legislation.) 
Estimated (October 1986) cost for existing project 
(exclusive of supplemental levee improvements), including 
new work and maintenance, is $169,600,000 of 
which $74,600,000 is Federal cost and $95 million non- 
Federal ($90,050,562 for lands and damages and relocations 
and $4,949,438 required contributed funds for 
levee construction, bank protection works, and levee 
setbacks). Of this amount, $4,939,752 was for new work 
and $9,686 for maintenance. In addition to project 
requirements, local interests constructed several pumping 
plants for drainage of agricultural and urban land 
protected by project levees. Some channel clearing 
work was accomplished by State of California and other 
local interests to supplement project levee construction. 
Dredging below Cache Slough and reconstruction of 
Cache Creek settling basin weir are considered deferred 
and excluded from foregoing cost estimate. Estimated 
cost (July 1962) of these project units is $2,560,000 and 
$520,000, respectively, a total of $3,080,000 plus U.S. 
costs, for construction. Operation and maintenance of 
completed project will be responsibility of local interests; 
as units of project are completed, they are transferred to 
agencies of State of California for operation and maintenance. 
Existing project was adopted by 1917 Flood 
Control Act (H. Doc 81, 62d Cong., 1st sess., as modified 
by Rivers and Harbors Committee Doc. 5, 63d Cong., 1st 
sess.), 1928 Flood Control Act (S. Doc. 23, 69th Cong., 
1st sess.), River and Harbor Act of 1937 (S. Committee 
print 75th Cong., 1st sess.), and 1941 Flood Control Act 
(H. Doc. 205, 77th Cong., 1st sess.). 
Local cooperation. Local interests have fully complied 
with requirements for all work completed or 
under contract, and indicated they will be able to fulfill 
requirements for remaining work as scheduled. Local 
interest costs from required contributed, funds for 
project work total $4,949,438 for levee construction, 
bank protection works, and levee setbacks, of which 
$4,939,752 was for new work and $9,686 for maintenance. 
Operations and results during fiscal year. Regular 
funds: Engineering continued. Project prevented an 
estimated $7,300,000,000 in damages from the February- 
March 1986 rainfloods. 
Historical summary. Construction of existing project 
began in FY 1918 and is about 99 percent complete. 
Channel improvement to date has produced a channel 
with a capacity of 579,000 cubic feet per second in 
Sacramento River below Cache Slough. In addition, 
discharges up to 21,000 cubic feet per second can be 
diverted from Sacramento River through Georgiana 
Slough. Completed major project items include about 
977 miles of levees; five weirs with a combined discharge 
capacity of 602,000 cubic feet per second; two cutoff 
channels; two sets of outfall gates; channel improvement 
and clearing in Sacramento River, Butte Creek, Putah 
Creek, and Sutter and Tisdale Bypasses; construction of 
two main bypasses or floodways and secondary bypasses 
44-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
at Tisdale and Sacramento weirs and at Wadsworth 
Canal; construction of Knights Landing ridge cut and of 
Cache Creek settling basin; installation of gaging stations; 
and enlargement of Sacramento River below 
Cache Slough. Cutoffs at Collins Eddy and between 
Wild Irishman and Kinneys Bends were made in 1918 
and 1919, respectively. Sacramento weir was completed 
in 1917, Fremont weir in 1924, Tisdale and Moulton 
weirs in 1932, and Colusa weir in 1933. Outfall gates at 
Knights Landing were constructed in 1930 and at 
mouth of Butte Slough in 1936. Pumping plants on 
Sutter Bypass were completed in 1944. Work items 
with reference to clearing, snagging, rectification of 
channels, and bank protection on Sacramento River 
and tributaries in Tehama County and from Red Bluff 
southerly, provided for by.1941 Flood Control Act were 
accomplished in fiscal years 1947,1948,1949, and 1951. 
Work remaining comprises completion of levee stage 
construction, Yolo Bypass and Cache Slough. (See table 
44-C for total cost of existing project to September 30, 
1986.) 
44-4

CALIFORNIA DEBRIS COMMISSION 
TABLE 44-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 83 FY 84 FY 85 FY 86 Sep 30, 1986 
1. RHeygrualuatliiocn Mofining 
and Preparation of 
Plans 
2. Sacramento River and 
Tributaries, CA 
(Debris Control) 
Contributed Funds, 
ther) 
3. Treatment of Yuba 
River Debris 
Situation Restraining 
Barriers, CA 
(Federal Funds) 
(Required Contributed 
Funds) 
(Contributed Funds, 
Other) 
4. SAcramento River, 
(Federal Funds) 
(Contributed Funds) 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Costp 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
(ontrib. 
Cost 
Rehab. 
Contrib. 
ost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
M int. 
ontrib. 
ost 
821,325 
821,325 
713,000 554,000 
605,227 653,198 
16,564 
20,000 
19,026 
2,257 
25,000 
22,435 
15,000 
19,436 
702,000 69 
695,102 69 
24,000 2 
10,066 4 
14,000 2 
11,282 4 
300,000 20 
274,092 16 
- 5,093,9991 2 
- 5,093,9991 s 
5,000 7,162,043' 
)0,522 7,109,9886 
- 12,4206 
- 12,4206 
361,482 
361,482 
4,000 1,670,6567 
4,177 1,663,0477 
- 1,053,904 
- 1,053,904 
- 361,777 
- 361,777 
6,500 1,660,723 
1,476 1,656,899 
- 1,053,904 
- 1,053,904 
- 34,0008 
- 34,0008 
1,500 68,127,8359 
5,245 68,065,6739 
- 1,979,104 
- 1,979,104 
- 10,724,08510 
- 10,724,0851o 
- 9,68611 
- 9,68611 
1. Exclusive of $644,503 appropriation and cost on inactive 
portion of project. 
2. Includes $447,127 for recreational facilities at North 
Fork ($32,473) and Harry L. Englebright ($414,654), Code 
710 appropriations. 
3. Includes $447,127 for recreational facilities at North 
Fork ($32,473) and Harry L. Englebright ($414,654), Code 
710 costs. 
4. Includes $6,035,961 from regular funds and $1,126,082 
from Hydraulic Mining in California funds. 
5. Includes $5,983,906 from regular costs and $1,126,082 
from Hydraulic Mining in California costs. 
6. Funds from State of California Department of Navigation 
and Ocean Development for acquisition of a boarding 
float at Englebright Dam. 
7. Includes deferred maintenance funds in amount of 
$207,500. 
8. Miscellaneous engineering and construction accomplished 
at expense of local interests in connection with 
rehabilitation of Daguerre Point Dam necessitated by 
December 1964 floodflows. 
9. Includes appropriation and cost of $680,000 for new 
work for previous project and $1,486,469 public works funds 
for new work for existing project. 
10. Includes $680,000 required contribution for previous 
project; $4,939,752 required contributed funds for existing 
project; and $310,801 voluntary contribution for bank protection 
for existing project. 
11. Includes $9,686 required contributed funds for existing 
project. 
44-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
TABLE 44-B AUTHORIZING LEGISLATION 
See Date 
Section in Authorizing 
Text Act Project and Work Authorized Documents 
1. 
Mar. 1, 1893 
Feb. 27, 1907 
June 19, 1934 
June 25, 1938 
Dec. 22, 1944 
and May 17, 1950 
July 3, 1958 
July 14, 1960 
REGULATION OF HYDRAULIC MINING AND 
PREPARATION OF PLANS 
Created California Debris Commission and authorized: (a) Ex. Doc. 267, 51st Cong., 
Hydraulic mining under its regulation in drainage areas of 2d sess., Ex. Doc. 98, 
Sacramento and San Joaquin Rivers, if possible without 47th Cong., 1st sess.' 
injury to navigability of these river systems or to lands 
adjacent thereto; and (b) preparation of plans by 
Commission for improvement of navigability of these river 
systems, and flood and debris-control therein. 
Authorized California Debris Commission to permit (Amendment of sec. 13, 
hydraulic mining without construction of impounding Act of Mar. 1, 1893.)' 
works, provided there is no injury to navighbility of above 
river systems or lands adjacent thereto. 
Amended act of Mar. 1, 1893, which provides for construction 
of debris dams or other restraining works by California 
Debris Commission and collection of a 3-percent tax on 
gross proceeds of each mine using such facilities, 
so as to eliminate this tax and substitute an annual tax 
per cubic yard mined, obtained by dividing total capital cost 
of each dam, reservoir, and rights-of-way, by total capacity 
of reservoir for restraint of debris; and authorized 
revocation of Commission orders permitting such mining, 
for failure to pay this annual tax within 30 days after its due 
date; and also authorized receipt of money advances, from 
mineowners to aid such construction, to be refunded later 
from annual payments of yardage taxes on material mined. 
Added at end of sec. 23 of above act, a provision that the 
Secretary of the Army is authorized to enter into contracts 
to supply storage for water and use of outlet facilities 
from debris-storage reservoirs for domestic and irrigation 
purposes and power development, upon such conditions of 
delivery, use, and payment as he may approve, these 
payments are to be deposited to credit of such reservoir 
project, reducing its capital cost to be repaid by tax 
on mining operations. 
SACRAMENTO RIVER, CA 
Additional levee construction and reconstruction, including H. Docs. 649, 78th Cong., 
levee protection of Upper Butte Basin, and multipurpose 2d sess., and 367, 81st 
reservoirs.2 Cong., 1st sess. 
Bank protection and incidental channel improvements, H. Doc. 272, 84th Cong., 
Sacramento River from Chico Landing toRed Bluff, and 2d sess. 
local interests flood plain zoning above Chico Landing.2 
Bank protection works at critical locations, Sacramento S. Doc. 103, 86th Cong., 
River.2 2d sess. 
1. For latest published map, see Annual Report for 1913, 
p. 3170, and Rivers and Harbors Committee Document 50, 
74th Cong., 1st sess. 
2. This supplemental work is reported in detail under 
Sacramento District, Improvement No. 19. 
44-6 
4.

CALIFORNIA DEBRIS COMMISSION 
TABLE 44-C SACRAMENTO RIVER, CA: TOTAL COST OF 
EXISTING PROJECT TO SEPTEMBER 30, 1986 
(See Section 4 of Text) 
Funds New Work Maintenance Total 
Regular $65,899,204 $1,979,104 $67,878,308 
Public Works 1,486,469 - 1,486,469 
Total U.S. $67,385,673 $1,979,104 $69,364,777 
Contributed Project Work 4,939,752 9,686 4,949,438 
Contributed, Other 5,104,333 - 5,104,333 
Total All Funds $77,429,758 $1,988,790 $79,418,548 
1. Includes $429,671 representing book value of plant 
purchased with previous project funds and transferred to 
existing project without reimbursement. 
44-7

U.S. ARMY ENGINEER WATERWAYS 
EXPERIMENT STATION 
Organization and functions. The Waterways Experiment 
Station (WES) is a field operating agency of the 
Chief of Engineers operating under the staff supervision 
of the Director, Research and Development. COL 
Dwayne G. Lee, Corps of Engineers, is Commander 
and Director. Dr. Robert W. Whalin, PE, is Technical 
Director. 
WES, the Corps of Engineers largest laboratory 
complex for research, testing, and development, consists 
of six technical laboratories: Hydraulics, 
Geotechnical, Structures, Environmental, Coastal 
Engineering Research Center, and Information 
Technology Laboratory. The Hydraulics Laboratory, 
the largest laboratory of its kind in the world, uses a 
wide range of working models and computer-based 
numerical models for research and analysis of dams, 
levees, river and harbor projects, soil and streambank 
erosion, thermal pollution, etc. The Geotechnical 
Laboratory conducts research in soil mechanics, 
structural foundation design, embankment design and 
slope stability, seepage analysis, military pavements, 
engineering geology, rock mechanics, expedient surfacing, 
earthquake engineering, and mobility and 
trafficability. The Structures Laboratory uses theoretical, 
analytical, experimental, and modeling 
approaches to research the effects of nuclear and nonnuclear 
explosions, the response of structures to natural 
and explosive disturbances, and various construction 
materials with emphasis on concrete, especially the 
testing, repair, and preservation of existing concrete 
structures. The Environmental Laboratory researches 
the problems caused by man's activities with respect to 
the environment. Research programs include Dredged 
Material, Aquatic Plant Control, Environmental and 
Water Quality Operational Studies, Environmental 
Impact, Wetlands, and the Natural Resources Research 
Program. These and other programs of the Environmental 
Laboratory range through waste management, 
environmental regulations, and military aspects of terrain 
and camouflage. The Coastal Engineering 
Research Center conceives, plans, and conducts 
research and data collection in coastal/ocean engineering 
and nearshore oceanography to: provide a 
better understanding of waves, winds, water levels, 
tides, and currents; provide scientific and engineering 
data and design criteria; and determine the effects of 
the coastal activities of the Corps of Engineers which 
are important to environmental considerations in the 
coastal zone. The Information Technology Laboratory 
was formed on 1 July 1986 by combining all information 
functions in one organization. This organization is 
cognizant of all communication, computer, graphic 
presentation, and printed media at the station. 
WES Laboratories are engaged in research and engineering 
investigations in support of the civil and 
military missions of the Chief of Engineers. On a 
reimbursable basis, WES performs basic and applied 
research, develops state-of-the-art methods and techniques, 
tests materials and equipment, and provides 
consulting services. Subject to the approval of the Chief 
of Engineers, studies and investigations may be undertaken 
for agencies outside the Department of the Army. 
WES maintains an extensive scientific and engineering 
reference library to serve the specialized 
needs of the Corps of Engineers and issues publications 
of general interest; operates DoD Information Analysis 
Centers in the fields of Pavements and Soils Trafficability, 
Concrete Technology, Hydraulic Engineering, 
Soils Mechanics, and Coastal Engineering; and maintains 
the Corps of Engineers Engineering Computer 
Programs Library. 
During Fiscal Year 1986, 237 WES numbered 
reports of individual studies conducted at or for WES, 
15 information reports, 35 information exchange bulletins, 
9 video reports, 10 technical manuals, and 18 
various special,'purpose technical documents (conference 
reports, special study reports, etc.) for WES and 
other offices Were printed and distributed to Corps 
offices and interested outside agencies. 
Operations and results during the period. Work 
accomplished at WES is, in general, initially financed 
by the Corps of Engineers Revolving Fund, with direct 
reimbursement from agencies requesting research 
investigations and related services. The Station's total 
program during Fiscal Year 1986 was $121,745,478 
which included $34,988,000 performed by contract. Of 
the total program $58,515,442 was oriented toward the 
civil sector and $63,230,036 to military. The plant 
replacement and improvement program was $4,920,990 
for this period. 
45-1

PERMANENT INTERNATIONAL ASSOCIATION OF NAVIGATION CONGRESSES 
(PIANC) 
The Permanent International Association of Navigation 
Congresses (PIANC) is an international organization 
with headquarters in Brussels, Belgium. It is a 
clearing house where engineers and port operators of the 
nations of the world exchange views and experiences on 
problems relating to ocean and inland navigation improvements. 
Its objective is broadly stated "to promote 
the progress of inland and maritime navigation". 
In 1902, the United States began an annual appropriation 
for the support and maintenance of the Permanent 
International Commission of Congresses of Navigation 
and for payment of the actual expenses of properly accredited 
national delegates of the United States to 
meetings of the Congresses and Commissions. As a 
member nation to the Association, the U.S. Section 
pays an annual subvention of about $6,900 to the International 
Secretariat in Brussels, Belgium. 
The objective of the Association - to promote the 
progress of inland and maritime navigation - is met by 
holding International Congresses and publishing 
technical bulletins and other documents. The Congresses 
are held in various member countries, usually at 
four-year intervals. The Association is supported principally 
by member governments, but membership also 
extends to corporations and to individuals. Member 
governments are represented at the Congresses and at 
meetings of the Permanent International Commission 
by delegates, the number of official delegates to be 
determined by the amount of the annual subvention 
paid by the government, but not to exceed ten in 
number. Corporate members may send one official 
representative to the Congresses. Currently, the Permanent 
International Commission has 41 countries 
represented. Individual membership is of two classes - 
Annual and Life - depending on the method of payment 
of dues. There are 1,495 annual international 
members, 552 life members, and 692 corporate 
members, for a total of 2,739 members. Membership of 
the U.S. section on July 31, 1986, totaled 648, consisting 
of 106 life members, 442 individual members, 
and 100 corporate members. 
The affairs of the Association are managed by the Permanent 
International Commission composed of 
delegates from the supporting governments. The National 
Commission constitutes the governing body of 
the U.S. Section and the U.S. Members of the Permanent 
International Commission. The Director of Civil 
Works, Office of the Chief of Engineers, US Army, and 
the Commander and Director, Water Resources Support 
Center, are the ex-officio Chairman and Secretary, 
respectively, of the National Commission. The 
Secretary handles all administrative matters of the U.S. 
Section. 
During Fiscal Year 1986, National Commissioners 
were: Major General Henry J. Hatch, Director of Civil 
Works, USACE, ex-officio Chairman; Colonel George R. 
Kleb, Commander and Director, Water Resources Support 
Center, ex-officio Secretary; Rear Admiral John 
Paul Jones, USN; Mr. John Pisani, MARAD; Mr. Jack 
E. Ravan, EPA; Mr. J. Ron Brinson, Port of New 
Orleans; Mr. John A. Downs, National Association of 
Dredging Contractors; Mr. James M. Goldston, 
Goldston Corporation; and Mr. Charles R. Roberts, Port 
of Oakland. One position on the U.S. Section National 
Commission was vacant. 
Lieutenant General John W. Morris, USA (Ret) is an 
honorary Vice President of PIANC, having served two 
terms as a Vice President. Major General Charles G. 
Holle, USA (Ret), Secretary-General, XXth International 
Navigation Congress, 1961, is ex-officio member 
of the Permanent International Commission. 
The annual meeting of the Permanent International 
Commission (PIC) was hosted by the U.S. Section and 
was held in Portland, Oregon, on May 27, 1986, and was 
attended by all National Commissioners, except Mr. 
Brinson. The Honorable Robert K. Dawson, Assistant 
Secretary of the Army for Civil Works, welcomed the 
delegates to the meeting and to the United States. Mr. 
Harry N. Cook, Commissioner Emeritus, filled the vacant 
position on the Commission. Lieutenant General E. 
R. Heiberg III, Chief of Engineers and PIANC International 
Vice-President, and Lieutenant General John W. 
Morris, USA (Ret) also attended the PIC meeting. 
American representatives attended meetings of the 
International Study Commissions, two Permanent 
Technical Committees (PTCs) and Working Groups of 
PTCs. U.S. representation on these groups during this 
fiscal year was as follows: 
International Commission for Study of Locks, Ship 
Lifts, and River Weirs - Dr. Michael Yachnis, USN. 
The Commission has published the portion of the study 
dealing with locks and continues working on the sections 
devoted to ship lifts. Dr. Yachnis replaces Mr. 
John Davis, who resigned after having served as the 
U.S. Representative to the Locks Commission for 13 
years. 
Permanent Committee for Developing Countries - 
Major General Bates Burnell, USA (Ret) 
Permanent Technical Committee I - Major General 
Robert Seedlock, USA (Ret) 
Working Group 1, Economic Implications of Inland 
Waterways - Mr. Howard E. Olson 
Working Group 2, Disposal and Land Dumping of 
Dredged Materials: Impact on the Environment - Mr. 
Paul Sorensen 
Working Group 3, Consideration of Risk in Determining 
Bank Protection - Mr. Alan D. Crowhurst 
Working Group 4, Use of Geotextiles for Inland 
Waterways Bank Protection - Mr. Max Lamb 
Working Group 5, Container Transport with Inland 
Vessels - Mr. Morris A. Clyde 
Working Group 6, Problems Created by Salt Water 
Intrusion in Inland Navigation Canals and Rivers - 
Ms. Christina Correale 
46-1

Working Group 7, Economic and Statutory Aspects 
of Management of Materials Dredged from Inland 
Waterways - Mr. Charles Hummer 
Permanent Technical Committee II - Mr. Eugene H. 
Harlow 
Working Group 1, Navigation in Muddy Areas - 
Dr. John Herbich 
Working Group 2, Stability of Rubble Mound 
Breakwaters in Deeper Water - Mr. Eugene H. Harlow 
Working Group 3, Ice Navigation - Mr. C. Allen 
Workley 
Working Group 4, Handling of Dangerous Goods in 
Ports - Captain William R. Reidel 
Working Group 5, Underkeel Clearance, Hard Bottoms/
Sea Conditions - Mr. Ronald Uhlin 
Working Group 6, Classification of Soils and Rocks 
to be Dredged - Mr. James W. Bean 
Working Group 7, Dimensions and Lay-out of Chan- 
-nels, Including two-way Channels - Mr. Leonard Van 
Houten 
Working Group 8, Damage Inflicted by Ships With 
Bulbous Bows on Underwater Structures - Mr. Wesley 
Allen
Working Group 9, Development of Modern Marine 
Terminals - Mr. Charles Roberts 
Working Group 10, Disposal of Dredged Materials 
Into the Sea - Colonel Herbert Haar, USA (Ret.) 
Working Group 11, Consequences of New Developments 
of Car/Passenger Ferries - U.S. not participating 
Working Group 12, The Performance and Design 
Parameters of Rubble Mound Breakwaters - Mr. 
Robert Whalin 
Working Group 13, Floating Breakwaters - Mr. 
John Oliver 
Working Group 14, Economical Channel Maintenance 
Methods - Mr. James W. Bean 
Working Group 15, Graving Docks - Dr. Michael 
Yachnis 
Working Group 16, Specifications of Loading, 
Transportation and High Temperature Destruction of 
Toxic and Chemical Wastes at Sea - Mr. Patrick Tobin 
Working Group 17, Inspection, Maintenance and 
Repair of Maritime Structures in Salt Waters Exposed 
to Material Degradation 
Joint Subcommittee on Sport and Pleasure Navigation 
- Mr. John M. Nichol 
Working Group 1, Ecological Conservation in Relation 
to Sport and Pleasure Navigation - Mr. Neil Ross 
Working Group 2, Waves in Yacht Harbors & 
Marinas - Mr. Orson Smith 
Working Group 3, Provision of Navigation Aids for 
Sport & Pleasure Craft - Mr. Austin E. Brant, Jr. 
Working Group 4, Chartering Services - Their 
Growth and Impact on Sport & Pleasure Navigation - 
Vacant 
Working Group 5, Standards for Construction, 
Equipment and Operation of Yacht Harbors and 
Marinas - Vacant 
U.S. Section regional meetings were held on 25-26 
June 1986 in St. Louis, Missouri, by the Central Region 
and on 4-5 September 1986 in Seattle, Washington, by 
the Western Region. 
During 1986, the U.S. Section also held concurrent 
meetings and the PIANC exhibit was displayed at 
meetings with the Western Dredging Association, 
American Association of Port Authorities, National 
Waterways Conference. 
46-2

INVESTIGATION OF PROJECTS UNDER FEDERAL POWER ACT 
The Federal Water Power Act of June 10, 1920, created 
the Federal Power Commission (in 1977 renamed the 
Federal Energy Regulatory Commission, FERC) composed 
of the Secretaries of War, Interior and Agriculture, 
with authority to grant permits and licenses for 
hydroelectric development in all water over which Congress 
has jurisdiction. The act further required that work 
of the commission be performed by and through the 
Departments of War, Interior and Agriculture and their 
engineering, technical, and other personnel except as may 
be otherwise provided by law. By an act of June 23, 1930, 
entitled "An Act to Reorganize the Federal Power Commission," 
Secs. 1 and 2 of the Federal Water Power Act 
of 1920 were amended. A commission was provided for, 
to be composed of five commissioners to be appointed by 
the President, by and with the advice and consent of the 
Senate. The necessity of performing work through the 
Department of War, Interior and Agriculture was removed 
and the commission was authorized to appoint such officers 
and employees as necessary in executing its function. 
By Title II, Public Utility Act of 1935, the original 
Federal Water Power Act was made Part I of the Federal 
Power Act, and Parts II and III were added to that Act. 
On October 1, 1977, pursuant to the provisions of the 
Department of Energy Organization Act (DOE Act), 
Public Law 59-91 Stat. (August 4, 1977) and Executive 
Order No. 12009, 42 Fed. Reg. 46267 (September 15, 
1977), the Federal Power Commission ceased to exist and 
its functions and regulatory responsibilities were 
transferred to the Secretary of Energy and the Federal 
Energy Regulatory Commission (FERC) which, as an independent 
commission within the Department of Energy 
was activated on October 1, 1977. 
Section 4(e) of the Federal Power Act provides that no 
water power license affecting navigable capacity of any 
navigable waters of the United States shall be issued until 
plans of the dam or other structures affecting navigation 
have been approved by the Chief of Engineers and 
the Secretary of the Army. By an action, notice of which 
was published in the Federal Register Volume 40, 
Number 74, dated April 16, 1975, the Secretary of the 
Army delegated to the Chief of Engineers his authority 
under Sec. 4(e) of the Federal Power Act. The Chief of 
Engineers on 5 September 1980 delegated to the Corps 
division engineers the authority for Section 4(e) approval 
of plans for non-Federal hydropower development affecting 
navigation. 
The following work of an engineering nature was accomplished 
by the Corps division and district offices 
under the direction of the Chief of Engineers during the 
fiscal year: 819 applications from non-Federal entities for 
planning, design, construction and operation of 
hydropower projects were reviewed and appropriate 
recommendations in the interest of flood control, navigation, 
and structural safety, relative to Corps projects, 
were furnished to the FERC. Of the total 819 applications, 
93 applications were specifically for hydropower 
development at the existing Corps projects. Recommendations 
were furnished to the Commission concerning the 
impact of hydroelectric power development on the existing 
and proposed Federal water resources projects. 
Recommendations also were provided to the Commission 
on the environmental impacts of constructing power 
plant(s) at either proposed or existing projects. 
To date, there are 34 constructed non-Federal power 
plants at Corps projects with a total capacity of 1227 
MW. Non-Federal entities had 14 power plants under 
construction at Corps projects during the fiscal year, and 
had 35 licensed power plants in various design stages. 
The Corps bills FERC licensees for the costs incurred by 
the Corps in approving final design, plans and construction 
of power plants at Corps projects. In FY 1986, the 
total cost reimbursement to the Corps for this service 
was $761,589. Review of license applications is funded by 
the Corps as a line item in the General Investigation Account. 
In FY 86, the cost for this pre-licensing activity 
was $639,585, which was reported to FERC for the Commission's 
assessment of annual charges to licensees. 
47-1

REGULATORY, SUNKEN VESSEL REMOVAL & 
NATIONAL EMERGENCY PREPAREDNESS ACTIVITIES 
1. Regulatory Activities 
Authorities. The following authorities charge the 
Corps of Engineers with the regulation of various waterrelated 
construction activities: Sections 9 and 10 of the 
River and Harbor Act of 1899 (structures in an alteration 
of waterways, e.g. boat docks); Section 103 of the 
Marine Protection Sanctuaries Act of 1972 (ocean 
dumping); and Section 404 of the Clean Water Act 
(discharge of dredged and fill material). 
Work Completed. During FY 1986, the Corps received 
approximately 14,000 applications for permits and 
issued 7,800 permits and 2,500 letters of permission. In 
addition about 20,000 activities were authorized by 
regional or statewide permits which did not require individual 
applications from the public. Many thousands 
of other minor activities were authorized by the Corps' 
nationwide permits. 
In FY 1986 the Corps continued its efforts toward 
regulatory reform based on a May 7, 1982, directive 
from the President's Task Force on Regulatory Relief. 
By the end of FY 1985, actions to streamline the Corps' 
procedures had reduced average permit application processing 
time to 75 days compared with 119 days at the 
end of FY 1982. 
TABLE 48-A 
GENERAL REGULATORY FUNCTIONS 
Obligations 
Unobligated Balance--30 Sep 85 ....... $ 619,363 
Allotments ........................... 56,708,570 
Total Funds Available .................. 57,327,933 
Obligations ........................... 56,687,534 
Unobligated Balance-30 Sep 86 ........ $ 613,501 
Expenditures 
Unexpended Balance-30 Sep 85 .......... 2,309,338 
Allotments .......................... 56,708,570 
Total Funds Available .................. 59,017,908 
Expenditures ......................... 57,261,152 
Unexpended Balance-30 Sep 86 ........ $ 1,756,756 
2. Investigation and Removal of Sunken Vessels 
Under the authority of Sections 19 and 20 of the River 
and Harbor Act of 1899, the Corps of Engineers investigated 
sunken vessels in navigable waters and removed 
those obstructing navigation. For obligations expenditures, 
see Table 48-B. 
3. National Emergency Preparedness Activities 
Authority. Executive Order 11490, as amended, 
assigns responsibilities to executive departments and 
agencies to undertake national emergency planning and 
preparedness to develop an effective national capability 
to meet essential civilian and defense needs during 
major domestic emergencies and national security 
emergencies. 
Status: During FY 1985, the Corps of Engineers 
continued its efforts to improve its readiness posture 
and ability to respond to various national emergencies. 
Emphasis was placed on the initiation of program activities 
that require a long-term commitment of 
resources. These activities included regional macroanalysis 
of mobilization requirements and resources; 
maintenance of, planning for and development of 
emergency facilities to support continuity of operations: 
and, planning to meet the nation's water resources 
requirements during a national emergency. In the latter 
case, Executive Order 11490 has tasked the Corps of 
Engineers to be the Executive Agency responsible for 
emergency water planning. 
Significant strides were made in the development of 
preparedness guidance and execution plans at all levels. 
While the efforts undertaken identified additional shortfalls 
or problems to be addressed, the Corps program 
continues to move towards the goal of ensuring a national 
engineering and construction capability that can 
respond to any national emergency. For fiscal year 
obligations and expenditures see Table 48-C. 
TABLE 48-B 
REMOVAL OF SUNKEN VESSELS 
Obligations 
Unobligated Balance-30 Sep 85 ........ $ 5,398 
Allotments ............... ............ 2,319,391 
Total Funds Available ................. 2,324,789 
Obligations ............................ 2,322,270 
Unobligated Balance-30 Sep 86 ........ $ 2,519 
Expenditures 
Unexpended Balance--30 Sep 86 ............ 5,398 
Allotments ............................ 2,319,391 
Total Funds Available .................. 2,324,789 
Expenditures..... ...... ........... 2,246,270 
Unexpended Balance--30 Sep 86 ........ $ 78,519 
48-1

TABLE 48-C 
NATIONAL EMERGENCY PREPAREDNESS 
Obligations 
Unobligated Balance-30 Sep 85 ......... $ 1,083,339 
Allotments ........................... 10,307,804 
Total Funds Available ................... 11,391,143 
Obligations ........................... 10,534,374 
Unobligated Balance-30 Sep 86 ......... $ 856,769 
Expenditures 
Unexpended Balance-30 Sep 85 .......... 1,710,220 
Allotments ........................... 10,307,804 
Total Funds Available .............. .. 12,018,024 
Expenditures ........................ 10,404,139 
Unexpended Balance-30 Sep 86 ......... $ 1,613,885 
48-2

INTERNATIONAL BOUNDARY WATERS BOARDS 
In order to carry out United States obligations under 
international agreements, the Office of the Chief of 
Engineers and several Corps Divisions and Districts 
with jurisdiction over areas bordering Canada have 
representation on numerous international boards and 
committees. The majority of these boards were 
established by the International Joint Commission 
(IJC) as empowered in accordance with the provisions of 
the Boundary Waters Treaty of 1909 between the. 
United States and Great Britain (for Canada). IJC 
boards fall into two broad categories: boards of control, 
which are more or less permanent and supervise compliance 
over an IJC order; and engineering or technical 
boards, which are usually dissolved after completing 
and reporting on an investigation assignment. In addition 
to boards created by the Commission, other international 
boards and committees are created by treaties 
or other informal arrangement in matters concerned 
with the water resources of joint interest, and the 
members report directly to the Governments or 
establishing agency. International boundary waters 
boards and committees having Corps of Engineer 
memberships during the fiscal year are listed in Table 
49-1. For an explanation of the constitution of the 
various boards and committees, see the FY 77 and FY 
80 annual reports. 
TABLE 49-1 
IJC BOARDS OF CONTROL HAVING CE MEMBERS 
YEAR 
ESTABLISHED 
1. Int. Lakes Superior 
2. Int. St. Croix River 
3. Int. Lake of the Woods 
4. Int. Lake Champlain 
5. Int. Kootenay Lake 
6. Int. Rainy Lake 
7. Int. Osoyoos Lake 
8. Int. Niagara 
9. Int. St. Lawrence River 
10. Int. Skagit River 
11. Int. Souris River 
1914 
1915 
1925 
1937 
1938 
1941 
1943 
1953 
1953 
1967 
1959 
UNITED STATES REPRESENTATION 
*Div. Engr., NCD 
*Div. Engr., NED 
*Dist. Engr., St. Paul 
*Dist. Engr., New York 
*1. Dist. Engr., Seattle 
2. Dept. of Interior, USGS, Boise, ID 
*Dist. Engr., St. Paul 
1. Dist. Engr., Seattle 
*2. Dept. of Interior, USGS, Tacoma, WA 
3. Washington State Parks & 
Recreation Commission 
*1. Div. Engr., NCD 
2. Dept. of Energy, FERC, Washington, D.C. 
*1. Div. Engr., NCD 
2. St. Lawrence Seaway Development Corporation 
Massena, NY 
3. St. Lawrence-Eastern Ontario Commission, 
Waterton, NY 
*Dist. Engr., Seattle 
1. Dist. Engr., St. Paul 
*2. ND State Engr., Bismark, ND 
3. Dept. of Interior, USGS, Bismark, ND 
*Signifies U.S. Section Chairman. 
49-1 
BOARD NAME

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
IJC ENGINEERING OR STUDY BOARDS HAVING CE MEMBERS 
BOARD NAME 
12. Int. Souris-Red Rivers 
Engineer 
13. Int. Champlain-Richelieu 
14. Int. Great Lakes Diversions 
and Consumptive 
Uses Study 
15. Int. Great Lakes Technical 
Information Network 
Board 
YEAR 
ESTABLISHED 
1948 
1975 
1977 
1979 
UNITED STATES REPRESENTATION 
1. Dist. Engr., St. Paul 
*2. Dept. of Interior, BOR, Washington, D.C. 
3. Dept. of Interior, USGS, Reston, VA 
*1. New York Dept. Envir. Conser. 
2. Dist. Engr., New York 
3. Vermont Agency Envir. Conser. 
4. New England River Basins Commission, 
Staff Associate 
5. Dept. of Interior F&WS Boston, MA 
*1. Div. Engr., NCD 
2. Michigan Dept. Nat. Res. 
3. Illinois Dept. of Trans. 
4. Pennsylvania Dept. of Envir. Res. 
5. Dept.of Energy, FERC, New York, NY 
*1. NCEED-L, Detroit, MI 
2. Great Lakes Environmental Research Lab., 
NOAA, Ann Arbor, MI 
3. USGS, Reston, VA 
OTHER INTERNATIONAL BOARDS OR GROUPS HAVING CE MEMBERS 
BOARD NAME 
16. Int. Lake Memphremagog 
17. Coordinating Committee 
on Great Lakes Basic 
Hydraulic and Hydrologic 
Data 
18. Int. Niagara Committee 
19. Columbia River Treaty 
Entities 
20. Columbia River Treaty 
Permanent Engineering 
*Signifies U.S. Section Chairman. 
YEAR 
ESTABLISHED 
1920 
1953 
1955 
1964 
1964 
UNITED STATES REPRESENTATION 
*Dist. Engr., New York 
*1. Eng. Div., North Central Div. 
2. Dept. of Commerce, NOAA, Rockville, MD 
*Div. Engr., NCD 
1. Div. Engr., NPD 
*2. Bonneville Power Admin., Portland, OR 
*1. OCE, DAEN-ECZ, Washington, D.C. 
2. Dept. of Energy, Washington, D.C. 
49-2

U.S. ARMY CONSTRUCTION ENGINEERING RESEARCH LABORATORY 
Organization and functions. The U.S. Army Construction 
Engineering Research Laboratory (CERL) is 
a field operating agency of the Chief of Engineers 
operating under the supervision of the Chief, Directorate 
of Research and Development. CERL, which is 
located in Champaign, IL, was officially dedicated on 
July 25, 1969, and is one of the Corps' four major 
laboratories. The laboratory is closely affiliated with 
the University of Illinois, sharing laboratory, library, 
computer, and personnel resources with the University. 
Colonel Norman C. Hintz, Corps of Engineers, is Commander 
and Director. 
CERL research programs are oriented toward the 
support of the total Army, the Army in garrison, the 
military installation, the Department of Defense, and 
the nation as a whole. The laboratory, which has base 
support, combat support, and civil works missions, is 
engaged in a construction research program designed to 
improve planning, design, construction, operation, and 
maintenance of a variety of Army and civil works 
facilities. The ultimate goal of the overall research 
effort is to create products that will save the Army 
resources. Research findings are transmitted directly 
to the field, as well as to private industry and the 
academic community. Within the Corps, research 
supports both military and civil works projects in the 
general areas of environmental quality, energy, materials, 
engineering management, and military engineering. 
In the area of environmental quality, CERL has developed 
a broad-based program designed to maintain 
military readiness standards, while still conforming to 
environmental quality regulations. These programs 
have included development of methods to predict 
noise impacts, water and air pollution control techniques, 
adaptations of currently used technologies to 
more stringent fluid and solid waste control, and computerized 
methods to cut the time and costs involved 
in environmental impact assessment. 
Energy research is oriented toward helping the 
Army meet its energy conservation goals. These projects 
include development of computer simulation 
technology for selection of more fuel-efficient energy 
systems and design methods and exploration of alternative 
fuel sources like solar energy and biomass. 
CERL's materials program is designed to lower the 
Army's costs for construction, modification, operation, 
and maintenance of its facilities. These projects include 
investigations on protective coatings, polymer technology, 
seismic criteria, quality monitoring systems, and 
materials syntheses and selection programs. 
CERL supports the Army decision-maker through 
its engineering management programs that are designed 
to increase facility efficiency and productivity. The development 
of automated data processing systems for 
management information, cost estimating, profit determination, 
architecture and design, corrosion mitigation, 
pavement management, housing contract maintenance, 
and habitability information have helped reduce costs 
throughout the military. 
During Fiscal Year 1986, CERL produced 160 
publications, of which 63 were technical reports, 15 
were Army-level publications, and 82 were publications 
presented in the public domain. In addition, 
CERL presonnel presented 51 papers at scientific 
meetings. CERL personnel prepared and presented 17 
training programs in areas such as corrosion, automated 
specification editing and energy conservation. 
Operations and results during the period. Work 
performed during Fiscal Year 1986 was funded both 
directly and through reimbursable programs. CERL's 
total program was $39.2 million, of which $12.2 
million was direct RDT&E funding and $14.3 million 
was reimbursable funding from the Office of the Chief 
of Engineers and Corps Divisions and Districts. Other 
Federal agencies, such as the Air Force, Navy, Federal 
Aviation Administration, and Environmental Protection 
Agency accounted for $12.7 million. About $2.5 
million or 6.3% of the FY86 funding was in support 
of civil works activities. 
Several CERL technologies were developed or 
implemented for use by the Corps in support of civil 
works projects during FY86. The automated budget 
system (ABS) was installed at the Office of the Chief 
of Engineers and over 40 districts. The ABS assists 
managers of operations and maintenance activities on 
civil works structures in preparing budget information. 
The civil works energy data system (CWEDS) was 
field tested at the Detroit and Albuquerque Districts 
in FY86. The system assists Corps managers in maintaining 
data in support of energy management programs 
for civil works projects. Cathodic protection 
systems using the CERL-developed ceramic anode were 
installed on the Cape Canaveral Lock (Jacksonville 
District) and tainter gates on the Cordell Hull Dam 
(Nashville District). The anode can be manufactured 
and installed for half the cost of the previously used 
silicon-iron anode. The anode is being manufactured 
and marketed by an Ohio firm under an exclusive 
licensing agreement with the Army. 
50-1

U.S. ARMY ENGINEER TOPOGRAPHIC LABORATORIES 
Organization and functions. The U.S. Army 
Engineer Topographic Laboratories (USAETL) 
began during World War I as a temporary Engineer 
Detachment formed to test aerial photographic 
mapping. Since that time, USAETL has grown into 
a sophisticated, modern research and development 
laboratory, applying the latest advances in 
electronics, computer data processing, space 
sciences, and related technologies to military and, 
civil problems in mapping, surveying, land navigation 
and geodesy. USAETL is now a field operating 
activity of the Corps of Engineers commanded by 
Colonel Alan L. Laubscher. 
USAETL is the only defense research and 
development laboratory that addresses the full 
range of developments in the topographic sciences, 
from basic research to a final product. Support is 
provided to both the Military and Civil Works 
elements of the Corps and to the Army Materiel 
Command, Army Space Program Office, Defense 
Advanced Research Projects Agency (DARPA) and 
the Defense Mapping Agency. To provide this support, 
USAETL is organized into five operational 
elements, three of which are developmental 
laboratories. The Geographic Systems Laboratory 
performs research and development associated with 
the extraction and presentation of geographic data 
for the Army in the field. The Topographic 
Developments Laboratory supports technological 
developments in surveying and mapmaking. The 
Space Programs Laboratory conducts research and 
development relating to the Army Space Program, 
and acts as the Corps' executive agent for space. 
The Research Institute performs most of the 
Laboratories' basic and applied research, and the 
Terrain Analysis Center prepares terrain studies 
needed by the Army elements in the field, as 
directed by the Army Assistant Chief of Staff for 
Intelligence. During FY 86, copies of 38 USAETL 
reports on individual studies conducted at or for 
USAETL were distributed to Corps' offices and interested 
outside agencies. 
In recent years, the emphasis of USAETL's 
research and development program has shifted from 
conventional mapmaking and surveying equipment 
and related techniques to new topographic data 
systems, which are required to support the coming 
generation of complex weapon systems and military 
geographic information systems required by field 
commanders for improved command, control, communications 
and intelligence. The new systems frequently 
use data acquired by remote sensing, and 
much of the work done at USAETL involves this 
technology. USAETL researchers are investigating 
the types of data derived from sensors and the 
means for exploiting that data. Studies showing the 
possibility of automating image interpretation are 
an important aspect of this work. The knowledge 
gained in these areas will be applicable not only to 
the mapping and terrain analysis missions of 
USAETL, but also to the Army thrust of 
teleoperated and autonomous vehicles. Other work 
is to investigate the digital processing of remotely 
sensed data and to define remote sensing inputs required 
for Army terrain graphics and terrain data 
bases. In addition, USAETL conducts short courses 
on remote sensing for Corps of Engineers and other 
government personnel. 
Operations and results during FY 86. The 
USAETL's total program for FY 86 was 
$85,393,000 (including $19,079,000 DARPA Direct 
Cite funds). This included work done for other agencies 
as well as for the Corps of Engineers. Of this 
total program, $33,699,000 supported work performed 
by contract. Work in FY 86 included 
$225,000 charged to civil works fund'. 
Civil works efforts in FY 86 focused on developing 
and demonstrating new survey techniques and 
equipment for use by districts and divisions. Scientists 
evaluated a complete survey system which 
uses signals transmitted by satellites of the 
NAVSTAR Global Positioning System (GPS) to 
calculate extremely precise three-dimensional coordinates. 
Also using GPS, USAETL researchers 
began the development of an automatic dam deformation 
monitoring system. Other projects include 
work on a new technique for computing dredge 
volumes, and the investigation of the use of low-cost 
digital image analysis equipment in areas under the 
Corps' protection. 
51-1

U.S. ARMY COLD REGIONS RESEARCH 
AND ENGINEERING LABORATORY 
Background. The U.S. Army Cold Regions Research 
and Engineering Laboratory (USACRREL), located 
in Hanover, New Hampshire, was created in 
January 1961. It merged the Snow, Ice and Permafrost 
Research Establishment (created in 1949) and 
the Arctic Construction and Frost Effects Laboratory 
(created in 1953), both of which were outgrowths 
of the Army's World War II experience in 
Alaska, Iceland and Greenland. 
The Laboratory's mission is to conduct and coordinate 
research and technology applicable to the Army's 
needs in those geographic areas of the world 
where cold presents a problem. 
The total authorized strength of USACRREL is 297 
(279 civilian and 18 military), with a budget for FY86 
of $25 million. USACRREL has six main buildings in 
Hanover (which total 284,000 square feet on 31 acres 
of land), including the main laboratory, the ice engineering 
facility, the logistics and supply building, the 
plant and equipment building, the equipment storage 
building and the frost effects research facility. 
CRREL's new Frost Effects Research Facility 
(FERF) is now operational and will aid in the study of 
frost heave. This unique 29,000-square-foot facility 
will allow research into the freeze-thaw phenomena 
of soil at an accelerated rate. The FERF's test program 
places emphasis on research into better ways of 
installing and maintaining paved surfaces, on frost 
heave problems, and on improving the performance 
of buried utilities in cold regions. 
USACRREL maintains a presence in Alaska at facilities 
located at Ft. Wainwright in Fairbanks. Cold 
regions research, appropriate to the Alaska location, 
is carried out by CRREL researchers. Facilities available 
include six buildings (totaling 30,000 square feet) 
and a permafrost tunnel (360-ft shaft drilled into 
frozen ground). 
USACRREL's basic and applied research covers a 
broad spectrum of cold regions studies. Basic research 
includes work in the physical, mechanical and 
chemical properties of snow and other forms of frozen 
precipitation, freshwater ice, sea ice and frozen 
giound. Basic research supports applied research in 
the major cold regions mission areas of Fire Support, 
Combat Support, Combat Service Support, Base 
Support, Flood Control and Navigation, Surveying 
and Remote Sensing, Civil Works Environmental 
Quality and Civil Works Construction, and Operation 
and Maintenance. Major Civil Works cold regions 
research topics include Ice Engineering, River 
Ice Management, Cold Regions Hydrology, Remote 
Sensing, and Environmental Impact. 
As the only Federal laboratory dedicated to cold 
regions research, USACRREL has an international 
reputation and maintains close ties with the international 
research community and with Federal and 
State agencies where it provides consulting services 
on a reimbursable basis. As the center of cold regions 
scientific and engineering expertise for the Corps of 
Engineers, USACRREL supports Corps districts and 
divisions by publishing field engineering reports, conducting 
demonstrations, sponsoring technical seminars 
for field engineers, and by making field visits to 
consult on engineering problems. In recognition of 
USACRREL's arctic expertise, this summer the Navy 
relocated NORDA's polar oceanographic research 
group to Hanover. 
Operations and Results During FY86. During FY 
86, USACRREL published and distributed 288 scientific 
and engineering reports (CRREL Reports; Monographs; 
Special Reports; Technical Notes; Technical 
Digests and information bulletins; journal articles; 
conference papers and abstracts; Corps, DA and 
other government publications; and books and nongovernment 
publications), contributed to 20 U.S. Army 
publications and presented 33 technical seminars 
and meetings. A total of 411 Installation Support or 
One-Stop Consulting Services were provided. 
One of USACRREL's major civil works research efforts 
is the five-year, $12-million River Ice Management 
(RIM) program. The goal of RIM is to develop 
and demonstrate techniques to improve navigation 
on inland waterways, particularly at Corps facilities. 
The work is focused on the Ohio and Upper Mississippi 
Rivers and the Illinois Waterway. USACRREL 
researchers received the Army Research and Development 
Award for development and demonstration 
of effective ice control measures at Corps locks and 
dams. High-efficiency bubbler systems were developed 
to force ice out of critical lock components. 
CRREL is directly supporting the basing of light infantry 
divisions at Ft. Drum, N.Y., and Ft. Wainwright, 
Alaska. An assistance group has been established 
to provide technical points of contact to assure 
52-1

that the most up-to-date cold regions facilities technology 
is made available to Army construction agencies 
for these new facilities. CRREL is maintaining 
close contact with the Ft. Wainwright and Ft. Drum 
DEHs, the New York and Alaska Districts, and participating 
architect-engineer firms. Consultations 
have been provided on design of roofing systems, including 
roofing type and snow load criteria, and paving 
system, including roller compacted concrete. 
USACRREL is the Corps manager for remote sensing 
research. This Civil Works program assures that 
Divisions and Districts are provided with the latest 
remote sensing technology. In 1986-87 the French 
SPOT satellite is being evaluated for application to 
Corps requirements. 
In FY86 CRREL was asked to provide engineering 
services and cold weather testing for the U.S. Navy 
Fleet Hospital Project. A Navy fleet hospital and an 
Army field kitchen have been erected and the winter 
test is underway. 
Support in combat engineering, facility design and 
training area use was also provided to General Corns, 
6th ID, Ft. Wainwright. 
Technical support is also provided to other DOD 
customers such as the Navy and the Air Force. This 
past winter extensive field and laboratory studies in 
support of the Navy's arctic submarine warfare efforts 
were conducted. For the Air Force, USACRREL 
continued to support planning and design efforts for 
the North Warning radar system. 
52-2

WATER RESOURCES SUPPORT CENTER 
The Water Resources Support Center (WRSC), under 
the staff supervision of the Director of Civil Works, 
Headquarters, U.S. Army Corps of Engineers, is 
commanded by Colonel George R. Kleb. The Center is 
located at the Humphreys Engineer Center, Ft. Belvoir, 
Virginia. Its divisions are the Institute for Water 
Resources, Dredging Division, Data Collection and 
Management Division, Publications and Training Division, 
and Office of Budget and Management Support. 
Elements managed by the Center in other locations 
include the Hydrologic Engineering Center at Davis, 
California; the Marine Design Branch of the Dredging 
Division at Philadelphia, Pennsylvania; and the Waterborne 
Commerce Statistics Center of the Data Collection 
and Management Division at New Orleans, 
Louisiana. The accomplishments of WRSC during 1986 
are given by division. 
DATA COLLECTION AND MANAGEMENT 
Video Disc: 
WRSC-C is the program manager for the interagency 
emergency operation video disc prototype system which 
was tested and evaluated in FY86. The system performed 
well but the telecommunication requires improvements 
which should be completed by mid FY87. 
This cooperative program involves Chief of Engineers 
Civil Works Operations and Readiness Division 
(DAEN-CWO), Southwestern Division (SWD), Lower 
Mississippi Valley Division (LMVD), Federal Emergency 
Management Agency (FEMA), U.S. Geological 
Survey (USGS), National Oceanic and Atmospheric Administration 
(NOAA) and United States Coast Guard. 
The objective is to provide the capabilities to transfer 
geographically related emergency operation data in 
near-real-time between Corps elements and other 
Federal, state, and local organizations for improved 
emergency management coordination. The system integrates 
"off the shelf," low cost video disc, microcomputers, 
graphics, and telecommunications technologies. 
Other applications for storage and retrieval of map products, 
training and briefing systems, as a subsystem for 
information network, are being explored. 
Remote Sensing Research Program: 
WRSC has begun the planning for the Corps 6th 
Remote Sensing Symposium to be held in Galveston, 
TX November 2-4, 1987. It will be hosted by the 
Southwestern Division, Galveston District with an expected 
attendance of 300 people. The Defense Mapping 
Agency has been designated as the DOD focal point for 
acquisition of space acquired imagery. WRSC is working 
with DMA to develop standard procedures for acquiring 
this imagery. 
Water Control Data Systems: 
The Corps use of the Geostationary Operational Environmental 
Satellite (GOES) data collection system 
(DCS) continues to increase but at a slower pace than in 
recent years. This slow down is the result primarily of 
two factors. One is that the Corps has already installed 
its most critical stations. Therefore, future increases can 
be expected to be less. The other major reason is the impending 
saturation of the NESDIS Ground System 
which is expected to be corrected in FY89. The Corps 
had 1992 Data Collections Planforms (DCP) in the 
system at end of FY86. This is more than any other 
agency and represents about 33 percent of the DCP's in 
the DCS. Following the acquisition in FY85 of computers 
dedicated to water control, field water control activities 
in FY86 concentrated on the development and 
enhancement of computer software to better utilize the 
computers and to further advance the automation of 
real time control of Corps projects. The automated 
cooperative stream gaging program with the U.S. 
Geological Survey was enhanced with additional programs 
written to help evaluate and manage the 
program. Such things as the various types of gages 
being used, their average costs by locale as well as maximum 
and minimum costs can now be readily derived. 
Telecommunications Planning: 
Telecommunications is one of the most important 
resources in support of the U.S. Army Corps of 
Engineers operational functions. Today, the 
technological opportunities and the effects of deregulation 
together with increasing costs and dependencies 
has created a need for a centralized planning function 
within USACE to formulate a more coherent and integrated 
plan for utilization of the resource. WRSC-C is 
establishing a telecommunications planning organization 
responsible for developing and recommending a 
clear direction for management control and for formulation 
of guidelines to ensure a more integrated and cost 
effective approach to implementation and management 
of telecommunications systems and networks within the 
agency. 
Waterborne Commerce Statistics Center: 
The Waterborne Commerce Statistics Center (WCSC) 
has made several significant accomplishments in FY86: 
Completion of A-76 Management Study: 
The A-76 Management Study concluded that in order 
for WCSC to implement a most efficient organization 
(MEO), the computer software must be upgraded to the 
state of the art. Therefore, the schedule calls for a total 
redesign of WCSC's computer software with implemen- 
53-1

tation in mid FY89. WCSC will reorganize into the 
MEO in FY90. 
Installation of the Harris 1000 Computer System: 
WCSC has installed a new Harris-1000 computer 
system and is in the process of converting software from 
the old computer system in time to process the CY87 
Waterborne Commerce data. WCSC has already built a 
1984 and 1985 data base using the ORACLE Data Base 
Management System on the Harris which allows for 
prompt querying of the data to respond to special data 
requests. A preliminary CY86 data base will be 
available in June 1987. 
Public Domain Data Base: 
In order to provide origin-destination waterborne 
commodity flow data to the public, WCSC has 
developed a public domain data base. Before making it 
available to the public, however, WCSC will show it to 
the 15 companies that have objected to the creation of 
such a data base and hope to convice them that their 
company-specific data is sufficiently immersed in the 
aggregated data such that no competitive harm will 
result from making this data public. A description of the 
public domain data base is as follows: 
a. The origins/destinations are the 26 National Waterways 
Study reaches. 
b. The commodities are the following 2-digit classifications: 
01 Farm Products 
09 Fish 
10 Metallic Ores 
11 Coal 
13 Crude Oil 
14 Non-Metallic Minerals 
20 Food & Kindred Products 
24 Lumber 
26 Paper 
28 Chemicals 
29 Petroleum Products 
32 Stone, Clay, & Glass 
33 Primary Metal Products 
40 Waste & Scrap Materials 
41 Other 
Future Plans: 
WCSC will be improving its communications capability 
to provide remote data access at faster baud rates. 
This will be coupled with a set of standard queries for 
Corps offices to use to extract data from the WCSC data 
base.directly. Preliminary data bases will be created to 
allow for earlier, more timely estimates of waterborne 
tonnage. 
Radio Systems: 
WRSC-C is the technical coordinator for radio communications 
within the USACE. Major activities during 
FY86 include: 
High Frequency/Single Side Band Base Station: 
Has been awarded to ITT Mackey. The first system is 
scheduled for delivery in September 1987 and the last 
(47th) approximately 12 months later. This is a Civil 
Works program. The primary use of these radios is in 
coping with natural disasters. The design objectives are 
for divisions to communicate with neighboring divisions 
and subordinate districts. Districts will have the 
capability to communicate with neighboring districts 
and within their district boundaries. The system is 
designed to have a 90 percent reliability, 24-hours a day 
throughout the 11-year solar cycle. Cost of the system is 
6 million dollars. 
High Frequency/Single Side Band Reconstitution Radio 
Program: 
This is an Army (ISC) - funded program in which 
USACE is scheduled for 48 systems at a value of more 
than 1.2 million dollars. The primary use of this radio is 
for natural emergencies, and for national mobilizations. 
Delivery is scheduled to commence in the first quarter 
of FY88. 
Transportable Communications System (TCS): 
A request for bids for a prototype Emergency Communications 
Shelter was announced in June 1986. 
Technical proposals were received November 1986 and 
evaluated. Further negotiations are scheduled for 
February 1987 with award in April 1987. The TCS is a 
self-contained transportable radio communications 
system capable of accommodating 2 communicators, as 
well as the equipment to communicate with ground personnel, 
mobile units, watercraft, aircraft, police, fire, 
and other emergency type vehicles. The shelter's basic 
use is similar to that of a permanent fixed station. In an 
emergency or major disaster the shelter can be moved 
into remote areas that lack commercial power or 
telephone lines. The shelter can also be used prior to, or 
during construction of a permanent communication network. 
The shelter will be deployable by means of a standard 
2 1/2 ton military truck, helicopter, or a C-130 type 
cargo aircraft. 
HYDRAULIC ENGINEERING CENTER 
The mission of the Hydrologic Engineering Center 
(HEC) is to support the Corps and the Nation in its 
water resources management responsibilities through 
research, training and technical assistance in hydrologic 
engineering and planning analysis. The HEC makes 
every effort to be aware of the present needs and emerging 
problems of the water resources community. HEC 
maintains continuous dialogue with universities, 
private industry, other Federal agencies and state and 
53-2

local governments to keep abreast of the latest 
developments through the profession. 
The Center provided substantial technical assistance 
to 25 Corps offices during FY86, including the Office of 
the Chief of Engineers, the Waterways Experiment Station 
and the Cold Regions Research and Engineering 
Laboratory. Technical assistance was also provided to 
other Federal agencies: the Federal Highway Administration 
and the Federal Emergency Management 
Agency. About one-fourth of HEC's resources were 
devoted to direct field assistance projects during FY86. 
Nine formal training courses involving 11 weeks of 
training were conducted at HEC. Two workshops, totaling 
one and one-half weeks, were also held. A Fulbright 
Fellow from Australia worked with the HEC for three 
months. Research funding was a relatively high (about 
one-half) proportion of HEC's budget this year. 
Planning, design, construction, operation and 
maintenance of today's multiple-purpose water projects 
require complex interdisciplinary analyses. These complex 
problems present major methodological and computational 
tasks to water resources professionals. The 
HEC seeks solutions to these problems through 
development of systematic methods and application of 
the computational power of computers. 
Research activities were carried out in 14 work units. 
These work units represent specific technical areas that 
have been identified in the Corps R&D program. The 
HEC's primary research area is entitled "Analytical 
Techniques in Water Resources Planning Studies." The 
HEC also participates in the Corps research program in 
water conservation and supply, planning methodologies, 
remote sensing, and dam safety. New work 
units addressing flood warning systems and water 
quality procedures for water control management began 
this year. HEC's R&D work units for FY87 are shown 
below: 
Improvements in Methods of 
Evaluating Hydrologic 
Phenomena 
Computer Methods for Water 
Resources Planning 
Real-Time Reservoir Regulation 
Modernization of Computer 
Programs 
Water Resource Data Storage 
System 
Flood Forecasting for Use During 
Flood Emergencies 
Analytical Techniques for 
Evaluating Reservoir Systems 
Water Quality Procedures 
for Water Control 
Management 
Spatial Data Management 
and Analysis System 
Flood Warning Systems 
Groundwater Recharge and 
Storage 
Remote Sensing and Spatial 
Data Applications 
Hydrologic/Hydraulic Risk 
Assessment of Dams 
Hydrologic Methods for 
Determining Water Supply 
Potential 
Focus continues on the development of practical computer 
programs and companion user materials for use 
by field office professional staff. Areas that received 
particular emphasis this past year include: dam safety 
risk-cost studies; water control and flood forecasting;, 
flood damage computations and data management; and 
water surface profile accuracy. 
Extensive analyses of risk-cost methods for dam safety 
applications were made. The research investigated 
the feasibility of determining the probability of rare 
floods like the probable maximum flood used for 
spillway design. Two case studies were used to evaluate 
the trade-offs between the cost of increasing spillway 
capacity versus the benefits expected from fewer dam 
failures. 
The use of microcomputers to assist in flood control 
planning continued to receive increased attention. 
Several important HEC hydrologic engineering and 
flood damage analysis computer programs were integrated 
into a package for analysis of flood control/
damage mitigation benefits. 
An in-depth assessment of the importance of the accuracy 
of land surveys and hydraulic parameter 
estimates on the accuracy of computer water surface 
profiles in the vicinity of highway bridge crossings was 
made for the Federal Highway Administration. The 
primary objective of the study was to develop the 
methodology to enable sound decisions regarding field 
surveys and data collection that would be needed to obtain 
a desired water surface profile accuracy. Several 
commercially available survey technologies were 
studied. 
Significant advances were made in improving HEC's 
library of computer programs during FY86. Ten programs 
were developed or revised this year, mostly in the 
reservoir system simulation area. HEC programs were 
upgraded to FORTRAN77 standards to make them 
more transportable to other computers. Eleven HEC 
programs were added to the 16 microcomputer versions 
already available in FY85 from HEC. These 27 
microcomputer programs cover technical areas of 
rainfall-runoff, river hydraulics, flood flow frequency, 
flood damage computations, groundwater analysis, 
small-scale hydropower cost, and spatial data management. 
Also available are utility programs for printing 
summary output reports, editing files, and assisting in 
preparing data input for channel hydraulics analysis. 
Several others will be available next year. During FY86 
HEC distributed about 2300 computer programs to 
other Federal, state, local governments, universities, 
and private industry, both domestic and foreign. HEC 
actively provides assistance to all its program users. 
INSTITUTE FOR WATER RESOURCES 
Policy Studies Division 
The Policy Studies Division develops analysis, 
background, and decision support on critical water 
issues for the Civil Works Directorate, coordinated 
through the Office of Policy. The work of the Division 
includes investigations in policy development, program 
management, evaluation methodologies, new missions, 
and strategic planning. In fiscal year 1986, important 
water issue areas addressed were water project development 
and implementation partnerships, private sector 
access to Corps lockage statistics, institutional impacts 
of cost sharing requirements, effectiveness of flood warning 
systems, and financial analysis on the Oregon Inlet 
project. 
53-3

The Policy Studies Division also provided a wide 
range of other support activities for OCE in FY86. Some 
of these activities included such items as preparation of 
materials for the National Council on Public Works Improvement 
(NCPWI), assistance to high school debate 
activities on national water policy, data development 
customer care and dispute resolution activities, and 
coordination for an engineering pamphlet on partnership 
in planning and Corps strategic planning policies. 
Other topics and support developed by the Policy 
Studies Division consisted of the following: slackwater 
port development, hydrology workshops, and professionalism 
in engineering and participation in policy. 
development task force. 
Research Division 
The Research Division work in FY86 included 
development of a comprehensive microcomputer-based 
water demand forecasting model for use in water supply 
studies, testing of a contingent valuation methodology 
for recreation assessment, and Deep Draft Evaluation 
procedures. Work continues in the areas of economic 
and demographic forecasting, economic effects of lock 
congestion, port analysis and flood damage assessment 
and evaluation techniques. Research into microcomputer 
applications for planning analysis and research to 
develop techniques for risk assessment related to the 
safety of Corps dams is continuing. 
The Institute's training program provides a means for 
transferring research results and state-of-the-art planning 
techniques to various Corps users. Courses on 
topics ranging in scope from Conflict Management to 
Economic Analysis for Water Resources Planning were 
conducted during the year. During FY86 approximately 
380 persons attended 15 sessions of 10 training courses. 
Navigation Division 
The Navigation Division was formed in 1983 by combining 
the Navigation Analysis Center and the National 
Waterways Study staff. The Navigation Division supports 
Corps planners by development and maintenance 
of transportation planning data bases on waterway carriers, 
other transportation modes, and commodity 
movements; development of analytical capabilities; and 
dissemination of technical information and advice with 
regard to use of navigation data and analytical techniques. 
The division also conducts studies and performs 
reimbursable and research studies for HQUSACE and 
field offices. 
One of the important data bases is the lock Performance 
Monitoring System (PMS), which contains information 
of Corps lock operations 'on the inland 
waterways. This data base enables Corps personnel to 
study lock operation and performance; to determine 
methods, benefits, and costs of improving the waterway 
system; to monitor traffic and commodities moving on 
the inland waterways; and monitor conditions that 
could affect traffic flow. 
The Navigation Division lead Corps efforts to develop 
and test methodologies for multiport analysis. These 
methods help local ports to design workable cost 
recovery strategies and help identify the traffic which 
can shift easily between ports as relative port and ocean 
leg costs shift. A draft manual combining significant 
economic and engineering attributes of non-deepening 
alternatives which facilitate loading and unloading of 
deep draft vessels has been developed. 
Vessel operating costs (ocean and inland), waterway 
and tow characteristics, and commodity and other 
economic projections are maintained to support various 
navigation systems studies. The Navigation Division 
has developed computer models to estimate economic 
development which would occur due to water resource 
and navigation projects, and maintains the navigation 
user charge data base, which is used to estimate impacts 
of various cost recovery policies and strategies. 
DREDGING DIVISION 
National Dredging Program 
In FY86, the U.S. Army Corps of Engineers spent 
$350 million for maintenance and improvements to 
dredge rivers, channels, and harbors to remove 300 
million cubic yards of material. There was little change 
in the amount of material removed in recent years; 
however, there was a significant decrease in the annual 
expenditure because of the increased pricing competition 
in the dredging industry during this period. 
Environmental Studies 
During FY86, the Dredging Division of the Water 
Resources Support Center continued to place a high 
priority on completing required designation studies for 
the 124 historically used ocean disposal sites which the 
Environmental Protection Agency (EPA) designated on 
an interim basis in 1977. To date, EPA has provided 
final designation for 17 of these sites. The EPA is 
continuing to place emphasis on completing the supporting 
environmental documentation required by their 
policies for final designation of these sites. The Corpsestablished 
goal for completing all remaining studies to 
support EPA final designation for these sites is by the 
end of FY88. 
Based on guidance from the Office of the Assistant 
Secretary of the Army for Civil Works, the Dredging 
Division revised 33 CFR 209.145, the Corps regulation 
specifying environmental compliance requirements for 
Corps O&M dredging projects. This proposed regulation 
revision, which will be moved to 33 CFR Parts 
335-338 to follow the Corps permit regulation, was 
published as a proposed rule on 30 May 1986 in the 
Federal Register. The public comment period on this 
regulation ended on 15 August 1986. Since a large 
number of comments were received and are being 
evaluated, the final regulation is scheduled for publication 
in the spring or summer of 1987. 
53-4

The Dredging Division continued technical discussions 
with EPA on the development of consistent and 
technically appropriate testing procedures and disposal 
alternative evaluations for projects requiring the 
removal of highly contaminated bottom sediments. A 
technical protocol developed by the Corps in FY85 is 
being applied by EPA at two of its major Superfund 
projects, Commencement Bay, Washington; and New 
Bedford Harbor, Massachusetts. Dredging is being 
evaluated at these two projects as a remedial action 
alternative for cleaning up highly contaminated bottom 
sediment "hot spots" within the waterways. The Corps 
is continuing to refine this testing protocol based on the 
experience gained at these Superfund sites as well as 
through other project applications within the Corps, one 
such project being a dredging and disposal demonstration 
project at Indiana Harbor within the North Central 
Division. 
Under a Memorandum of Understanding (MOU) and a 
broad agreeement for cooperation in the field of environmental 
protection between the United States and 
Japan, the 11th annual meeting of experts on the 
management of bottom sediments containing toxic 
sediments was held in Seattle, WA. Papers of particular 
importance were delivered on dewatering of dredged 
sediments, long-term management of dredged material 
disposal and containment activities, rehabilitation of 
contaminated water bodies, eutrophication, control of 
dredge-induced turbidity, and effects of contaminated 
sediments on the water column and the biological community. 
Developments in recent technology for stabilizing 
soft, highly organic sediments such as found at 
Superfund projects have proven particularly useful in 
ongoing efforts. 
In support of proposed deep-draft navigation projects 
included under P.L. 99-662 and the anticipated large 
volumes of new work dredged material which would be 
generated, the Dredging Division sponsored two national 
workshops during FY86. The first of these, on the 
subject of long-term management strategies for dredged 
material, was held in Jackson, Mississippi, and was well 
attended by FOAs. The recommendations derived from 
that workshop will provide major input in the development 
of national Corps policy and guidance on this subject. 
The second workshop, on "Beneficial Uses of 
Dredged Materials", was an interagency workshop held 
in Pensacola, Florida, co-sponsored by EPA, National 
Marine Fisheries Service (NMFS) and the U.S. Fish and 
Wildlife Service. The results of that workshop are 
scheduled for publication as a bound proceedings in 
March 1987. 
The Dredging Division also provided support to the 
Office of Policy, Civil Works Directorate, on the planning 
of the deepenings of Baltimore and Norfolk 
Harbors. In addition, the planning for a feeder beach 
concept using dredged material to improve the badly 
eroded shore line caused by hurricanes at Dauphin 
Island was coordinated with the South Atlantic Division 
and the Mobile District. Plans for a stable berm in 
this area created from dredged material from the Mobile 
Harbor deepening project will be underway in FY87 in 
conjunction with the South Atlantic Division and the 
Mobile District. These initiatives are being closely coordinated 
with NMFS headquarters personnel. 
Revolving Fund 
The Dredging Division allocated $93 million from the 
Plant Replacement and Improvement Program (PRIP) 
Fund to divisions, districts, and field operating activities 
for FY86. These allocations were for 
replacements and improvements to structures, dredges, 
floating plants, mobile and fixed land plant, as well as 
tools, office furniture and equipment necessary to support 
Corps-wide missions and activities. During the 
year, the Director of Civil Works reviewed the use and 
status of PRIP and implemented procedures for its 
more effective management. 
Marine Design Center 
In FY86, the Marine Design Center (MDC) managed 
44 floating plant projects on a fully reimbursable basis. 
The work included both design and construction contract 
management. The design work was carried out by 
the regular staff of naval architects and marine 
engineers together with architect engineer contract support. 
Approximately 32 percent of the engineering and 
design program, which consisted of 34 projects for 20 
Corps districts, was performed by contract. The design 
projects included the preliminary design of a new 
minimum fleet dustpan dredge, the conceptual design of 
a SWATH surveyboat to provide improved performance 
in exposed waters and a design and contract 
package of a river ice plow for the Cold Regions 
Research and Engineering Laboratory. 
Construction contract management was carried out 
on nine projects for eight districts at a total contract 
value of $7,622,222. New plant delivered to the 
operators in FY86 consisted of six deck cargo barges, a 
60-foot surveyboat/towboat, and a power service barge. 
Two major design projects came to fruition in FY86 in 
the form of completed shipyard conversions of vintage 
Corps of Engineers plant from steam to diesel power. 
One of these was the dustpan dredge JADWIN, completed 
in July so that the dredge would be available for 
the full dredging season. The total project cost was $8.5 
million and resulted in a vessel with 10 percent greater 
production and a fuel savings of 50 percent. The other 
was the gatelifter PAUL BUNYAN, completed in June 
Sat a total project cost of $1.4 million. The vessel, as converted, 
is more fuel efficient and can operate with a 
reduced crew. Both projects included conversion and 
repair work designed to extend the life of each vessel by 
a minimum of 15 years with little loss of productive 
dredging time due to the rehabilitations. 
53-5

Support to Others 
The Dredging Division prepared a cost-estimate, construction 
methodology, geotechnical assessment and environmental 
review of the Gaillard Cut Widening Project 
for the Panama Canal Commission at their request. 
The final report on this effort was provided to the Commission 
during the last quarter of 1986. 
53-6

APPENDIX A 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1986 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage)' 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
ALASKA 
Chena River Lakes 
ARIZONA 
Adobe 
Alamo 
Cave Buttes 
Dreamy Draw 
New River 
Painted Rock 
Tat Momolikot 
Whitlow Ranch 
ARKANSAS 
Yukon-Kuskokwim 
Gila 
Colorado 
Gila 
Gila 
Gila 
Gila 
Gila 
Gila 
Blakely Mountain Dam Ouachita 
Blue Mountain Arkansas 
DeGray Ouachita 
DeQueen Red 
Dierks Red 
Gillham Red 
Millwood Red 
Narrows Dam Ouachita 
Nimrod Arkansas 
CALIFORNIA 
Black Butte Sacramento 
Brea Santa Ana 
Buchanan Dam- 
H.V. Eastman Lake San Joaquin 
Carbon Canyon Santa Ana 
Coyote Valley Russian 
Dry Creek (Warm Springs) 
Lake and Channel Russian 
Farmington San Joaquin 
Fullerton Santa Ana 
Hansen Los Angeles 
Harry L. Englebright Sacramento 
Hidden Dam-Hensley Lake San Joaquin 
Isabella San Joaquin 
Lopez Los Angeles 
Martis Creek Sacramento 
Merced County 
Stream Group: 
Bear San Joaquin 
Burns San Joaquin 
Mariposa San Joaquin 
Owens San Joaquin 
Mojave River Mojave 
New Hogan San Joaquin 
North Fork Sacramento 
Pine Flat San Joaquin 
Prado Santa Ana 
San Antonio Santa Ana 
Santa Fe San Gabriel 
Sepulveda Los Angeles 
Success San Joaquin 
Terminus San Joaquin 
Whittier Narrows San Gabriel 
COLORADO 
Bear Creek 
Chatfield 
Cherry Creek 
John Martin 
Trinidad 
CONNECTICUT 
Black Rock 
Colebrook River 
Hancock Brook 
Hop Brook 
Mansfield Hollow 
Northfield Brook 
Thomaston 
West Thompson 
IDAHO 
Lucky Peak 
Missouri 
Missouri 
Missouri 
Arkansas 
Arkansas 
Housatonic 
Connecticut 
Housatonic 
Housatonic 
Thames 
Thames 
Housatonic 
Thames 
Columbia 
Chena River Fairbanks 
Skunk Creek Phoenix 
Bill Williams River Wenden 
Cave Creek Phoenix 
Dreamy Draw Phoenix 
New River Phoenix 
Gila River Gila Bend 
Santa Rosa Wash Casa Grande 
Queen Creek Superior 
Ouachita Hot Springs 
Petit Jean River Paris 
Caddo Arkadelphia 
Rolling Fork River DeQueen 
Saline River Dierks 
Cossatot River Gillham 
Little River Ashdown 
Little Missouri Murfreesboro 
Fourche La Fave River Plainview 
Stony Creek Orland 
Brea Creek Fullerton 
Chowchilla River Chowchilla 
Carbon Canyon River Brea 
East Fork Russian River Ukiah 
Dry Creek Healdsburg 
Littlejohn Creek Farmington 
East Fullerton Creek Fullerton 
Big Tujunga Wash Los Angeles 
Yuba River Marysville 
Fresno River Madera 
Kern River Bakersfield 
Pacoima Wash San Fernando 
Martis Creek Reno 
Bear Creek Merced 
Burns Creek Merced 
Mariposa Creek Merced 
Owens Creek Merced 
Mojave Victorville 
Calaveras Valley Springs 
American River Auburn 
Kings River Piedra 
Santa Ana River Corona 
San Antonio Creek Upland 
San Gabriel River Duarte 
Los Angeles River Van Nuys 
Tule River Porterville 
Kaweah River Visalia 
San Gabriel River 
and Rio Hondo El Monte 
Bear Creek Denver 
South Platte River Denver 
Cherry Creek Denver 
Arkansas River Lamar 
Purgatoire River Trinidad 
Branch Brook Thomaston 
West Branch, 
Farmington River Riverton 
Hancock Brook Plymouth 
Hop Brook Middlebury 
Natchaug River Willimantic 
Northfield Brook Thomaston 
Naugatuck River Thomaston 
Quinebaug Thompson 
Boise River Boise 
1981 2,000 NPP FR Earth 
1982 18,350 
1968 1,046,310 
1979 46,600 
1973 320 
1985 43,520 
1959 2,491,700 
1974 198,550 
1960 35,500 
1955 2,768,500 
1947 257,900 
1971 881,900 
1977 136,100 
1975 96,800 
1975 221,800 
1966 1,854,930 
1949 407,900 
1942 336,010 
1963 160,000 
1942 4,010 
1975 150,000 
1961 6,610 
1959 122,500 
1983 381,000 
1952 52,000 
1941 760 
1940 25,450 
1941 69,000 
1975 90,000 
1953 570,000 
1954 440 
1971 20,400 
1954 7,700 
1950 7,000 
1948 15,000 
1949 3,600 
1971 89,670 
1963 325,000 
1939 14,700 
1954 1,000,000 
1941 196,240 
1956 7,700 
1948 32,110 
1941 17,430 
1960 85,000 
1961 150,000 
1957 35,150 
1978 30,810 
1974 231,429 
1950 93,920 
1943 615,500 
1977 123,500 
1970 8,700 
1969 97,700 
1960 4,030 
1968 6,970 
1952 52,000 
1965 2,430 
1960 42,000 
1965 26,800 
1956 306,000 
NPP FR Earth 
560 FRWX Earth 
NPP FRX Earth 
NPP FRX Earth 
NPP F Earth 
NPP FRWX Earth 
NPP FWX Earth 
NPP FX Earth 
50 40,200 
109 2,275 
283 975 
109 2,275 
50 448 
104 2,320 
181 4,780 
75.5 12,500 
149 837 
20,900 FP Earth 235 1,100 
2,910 FRWX Earth 115 2,800 
6,400 FPQRS Earth 243 3,400 
1,680 FSQRW Earth 160 2,360 
1,360 FSRAW Earth & Rock 153 2,500 
1,370 FSQW Earth & Rock 160 1,750 
29,200 FSW Earth 88 17,554 
2,500 FP Concrete 175 941 
3,550 FSWX Concrete 97 1,012 
770 FIRX Earth 156 2,970 
NPP FRX Earth 87 1,765 
470 FIRW Earth & Rock 205.5 1,800 
NPP FRX Earth 99 2,610 
1,700 FRX Earth 160 3,500 
500 FRSW Earth 319 3,000 
NPP F Earth 60 7,800 
NPP FRX Earth 46 575 
120 FRWX Earth 97 10,475 
400 DR Concrete 280 1,142 
5,000 FIRW Earth 163 5,730 
1,850 FIRW Earth 185 4,952 
NPP FX Earth 50 1,300 
71 FSR Earth 113 2,670 
NPP F Earth 92 1,830 
NPP F Earth 55 4,075 
NPP F Earth 88 1,330 
NPP F Earth 75 790 
NPP FRWX Earth 200 2,200 
715 FIRX Earth & Rock 210 1,960 
280 DR Concrete 155 620 
NPP FIRX Concrete 429 1,820 
NPP FRX Earth 106 2,280 
NPP FX Earth 160 3,850 
NPP FRX Earth 92 23,800 
NPP FRX Earth 57 15,444 
400 FIRX Earth 142 3,490 
345 FIRX Earth 250 2,375 
NPP FRWX Earth 56 16,960 
109 FRX Earth 180 5,300 
1,412 FRX Earth 148 12,500 
852 FRX Earth 141 14,300 
1,844 FIR Concrete 
& Earth 106 13,274 
280 FIRX Earth 200 6,610 
20 FR Earth 
760 FRSX Earth 
40 FRW Earth 
21 FR Earth 
450 FRW Earth 
8 FRW Earth 
NPP F Earth 
200 FRW Earth 
2,850 FIR Earth 
154 933 
223 1,300 
57 630 
97 520 
68 12,420 
118 810 
142 2,000 
70 2,550 
250 1,700 
A-1

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1986 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
ILLINOIS 
Carlyle 
Farmdale 
Fondulac 
Shelbyville 
Rend Lake 
INDIANA 
Brookville 
Cagles Mill 
Cecil M. Harden 
Huntington 
Mississinewa 
Monroe 
Patoka 
Salamonie 
IOWA 
Upper Mississippi 
Upper Mississippi 
Upper Mississippi 
Upper Mississippi 
Upper Mississippi 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Coralville Upper Mississippi 
Rathbun Missouri 
Red Rock Upper Mississippi 
Saylorville Upper Mississippi 
KANSAS 
Clinton Missouri 
Council Grove Arkansas 
El Dorado Arkansas 
Elk City Arkansas 
Fall River Arkansas 
Hillsdale Missouri 
John Redmond Arkansas 
Kanopolis Missouri 
Marion Arkansas 
Melvern Missouri 
Milford Missouri 
Pearson Skubitz Big Hill Arkansas 
Perry Missouri 
Pomona Missouri 
Toronto Arkansas 
Tuttle Creek Missouri 
Wilson Missouri 
KENTUCKY 
Barren River 
Buckhorn 
Carr Fork 
Cave Run 
Dewey 
Fishtrap 
Grayson 
Green River 
Martins Fork 
Paintsville 
Nolin 
Rough River 
Taylorsville 
LOUISIANA 
Bayou Bodcau 
Caddo Lake 
Wallace Lake 
MARYLAND 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Cumberland 
Ohio 
Ohio 
Ohio 
Ohio 
Red 
Red 
Red 
Jennings Randolph Lake Potomac 
MASSACHUSETTS 
Barre Falls Connecticut 
Birch Hill Connecticut 
Buffumville Thames 
Charles River Natural Charles 
Valley Storage 
Conant Brook Connecticut 
East Brimfield Connecticut 
Hodges Village Connecticut 
Knightville Connecticut 
Kaskaskia River 
Farm Creek 
Fondulac Creek 
Kaskaskia River 
Big Muddy River 
East Fork of 
Whitewater River 
Mill Creek 
Raccoon Creek 
Wabash River 
Mississinewa 
Salt Creek 
Patoka River 
Salamonie 
Iowa River 
Chariton River 
Des Moines River 
Des Moines River 
Wakarusa River 
Grand (Neosho) 
Walnut River 
Elk River 
Fall River 
Big Bull Creek 
Grand (Neosho) 
Smoky Hill River 
Cottonwood River 
Marias Des Cygnes 
Republican River 
Big Hill Creek 
Delaware River 
110 Mile Creek 
Verdigris River 
Big Blue River 
Saline River 
Barren River 
Middle Fork of 
Kentucky River 
Carr Fork 
Licking River 
Johns Creek 
Levisa Fork, 
Big Sandy River 
Little Sandy 
Green River 
Martins Fork 
Paint Creek 
Nolin River 
Rough River 
Salt River 
Bayou Bodcau 
Cypress Bayou 
Cypress Bayou 
North Branch 
Potomac River 
Ware River 
Millers River 
Little River 
Charles River 
Conant Brook 
Quinebaug River 
French River 
Westfield River 
Carlyle 
East Peoria 
East Peoria 
Shelbyville 
Benton 
Brookville 
Terre Haute 
Rockville. 
Huntington 
Peru 
Harrodsburg 
Ellsworth 
Wabash 
Iowa City 
Centerville 
Des Moines 
Des Moines 
Lawrence 
Council Grove 
El Dorado 
Independence 
Fall River 
Kansas City 
Burlington 
Salina 
Marion 
Melvern 
Junction City 
Cherryvale 
Perry 
Pomona 
Toronto 
Manhattan 
Wilson 
Glasgow 
Buckhorn 
Hazard 
Farmers 
Paintsille 
Pikeville 
Grayson 
Campbellsville 
Harlan 
Paintsville 
Kyrock 
Leitchfield 
Taylorsville 
Shreveport 
Shreveport 
Shreveport 
Barnum 
Barre 
So. Royalston 
Charlton 
Millis 
Monson 
Fiskdale 
Oxford 
Huntington 
1967 983,000 
1951 15,500 
1951 3,780 
1970 684,000 
1970 294,000 
1974 359,600 
1952 228,120 
1960 132,800 
1969 153,100 
1967 368,400 
1964 441,000 
1978 301,600 
1966 263,600 
1958 492,000 
1969 552,000 
1969 1,830,000 
1975 602,000 
1977 397,200 
1964 112,265 
1981 236,200 
1966 284,300 
1949. 256,400 
1981 160,000 
1964 630,250 
1948 450,000 
1968 143,850 
1972 363,000 
1965 1,160,000 
1981 40,600 
1969 770,000 
1963 230,000 
1960 200,800 
1962 2,346,000 
1964 776,000 
1964 815,200 
1960 168,000 
1976 47,700 
1974 614,100 
1949 93,000 
1968 164,360 
1967 118,990 
1969 723,200 
1978 21,000 
1983 73,500 
1963 609,400 
1958 334,400 
1983 291,670 
1949 357,300 
1971 175,000 
1946 88,300 
1981 130,900 
1958 24,000 
1941 49,900 
1958 12,700 
1983 35,000 
1966 3,740 
1960 30,000 
1959 12,800 
1941 49,000 
26,000 FSNRWA Earth 
NPP F Earth 
NPP F Earth 
11,100 FSNRW Earth 
18,900 FQRSW Earth 
67 6,570 
80 1,275 
67 1,000 
108 3,000 
54 10,600 
2,250 FRSW Earth & Rock 182 3,000 
1,400 FRX Earth 150 950 
1,100 FRX Earth 117 1,790 
500 FRW Earth 91 5,332 
1,100 FRW Earth 137 8,100 
3,280 FARS Earth 93 1,400 
2,010 FRSQW Earth & Rock 84 1,550 
976 FRW Earth 133 6,100 
1,820 FARW Earth 
11,000 FNRWXQ Earth 
8,950 FARWQ Earth 
74,000 FARWQ Earth 
100 1,400 
86 10,600 
110 5,676 
125 6,750 
7,000 FSWAXR Earth 114 9,250 
3,235 FSQR Earth 96 6,500 
8,000 FSQR Earth 99 20,930 
4,450 FSQ Earth 107 4,840 
2,350 FSX Earth 94 6,015 
4,580 FSQR Earth 75 11,600 
9,280 FSQR Earth 86.5 21,790 
3,815 FRWX Earth 131 15,360 
6,200 FRQS Earth 67 8,375 
6,930 FRQWX Earth 98 9,700 
15,600 FRSXWQ Earth & Rock 126 6,300 
1,240 FSR Earth 83 3,870 
12,200 FRSXW Earth & Rock 95 . 7,750 
4,000 FRSWXQ Earth & Rock 85 7,750 
2,660 FX Earth 90 4,712 
15,800 FRWXQAN Earth & Rock 157 7,500 
9,000 FIRWXNA Earth 160 5,600 
4,340 FARS Earth 146 3,970 
550 FR Earth 162 1,020 
530 FQRW Earth & Rock 130 720 
6,790 FQRW Earth & Rock 148 2,740 
1,100 FARW Earth 118 913 
569 FARW Rock 195 1,100 
1,050 FQRW Earth & Rock 120 1,460 
5,070 FRSQW Earth & Rock 142 2,350 
578 FQ Concrete 97 574 
261 FQRW Earth & Rock 160 1,600 
2,890 FAR Earth & Rock 174 990 
2,180 FRX Earth & Rock 124 1,530 
1,625 FQRW Earth & Rock 164 1,280 
NPP FRW Earth 
32,700 NFRS Concrete 
& Earth 
2,300 FR Earth 
76 12,850 
3,600 
48 4,934 
952 FQRS Earth & Rock 296 2,130 
NPP FRW Earth & Rock 62 885 
NPP FRW Earth & Rock 56 1,400 
200 FRW Earth & Rock 66 3,255 
NPP F Nonstructural - - 
NPP F Earth & Rock 85 1,050 
360 FRW Earth & Rock 55 520 
NPP FRW Earth & Rock 55 2,140 
NPP FRW Earth & Rock 160 1,200 
A-2

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1986 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage)' 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
MASSACHUSEITTS (Continued) 
Littleville 
Tully 
West Hill 
Westville 
MINNESOTA 
Big Stone Lake- 
Whetstone River 
Lac Qui Parle 
Chippewa River 
Lac Qui Parle 
Marsh Lake 
Orwell 
Red Lake 
MISSISSIPPI 
Arkabutla Lake 
Enid Lake 
Grenada Lake 
Okatibbee 
Sardis Lake 
MISSOURI 
Clearwater 
Long Branch 
Longview 
Pomme de Terre 
Smithville 
Wappapello 
NEBRASKA 
Harlan County 
Papillion Creek 
and Tributaries: 
Glenn Cunningham 
(Site 11) 
Standing Bear Lake 
(Site 16) 
Salt Creek & Tributaries: 
Olive Creek (Site 2) 
Blue Stem (Site 4) 
Wagon Train (Site 8) 
Stagecoach (Site 9) 
Yankee Hill (Site 10) 
Conestoga (Site 12) 
Twin Lake (Site 13) 
Pawnee (Site 14) 
Holmes Park Lake 
(Site 17) 
Branched Oak (Site 18) 
NEW HAMPSHIRE 
Blackwater 
Edward MacDowell 
Franklin Falls 
Hopkinton-Everett 
Otter Brook 
Surry Mountain 
NEVADA 
Mathews Canyon 
Pine Canyon 
NEW MEXICO 
Abiquiu 
Cochiti 
Conchas 
Connecticut 
Connecticut 
Blackstone 
Thames 
Upper Mississippi 
Upper Mississippi 
Upper Mississippi 
Upper Mississippi 
Red River of the North 
Red River of the North 
Lower Mississippi 
Lower Mississippi 
Lower Mississippi 
Pascagoula 
Lower Mississippi 
White 
Grande Chariton 
Missouri 
Missouri 
Missouri 
Lower Mississippi 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
Merrimack 
Merrimack 
Merrimack 
Merrimack 
Merrimack 
Connecticut 
Connecticut 
Colorado 
Colorado 
Rio Grande 
Rio Grande 
Arkansas 
Middle Branch, 
Westfield River 
Tully River 
West River 
Quinebaug River 
Minnesota River 
Chippewa River 
Minnesota River 
Minnesota River 
Otter Tail River 
Red Lake River 
Coldwater River 
Yocona River 
Yalobusha River 
Okatibbee Creek 
Little Tallahatchie River 
Black River 
Little Chariton 
Little Blue River 
Pomme de Terre River 
Little Platte River 
St. Francis River 
Chester 
Fryville 
Uxbridge 
Sturbridge 
Ortonville 
Montevideo 
Montevideo 
Montevideo 
Fergus Falls 
Red River 
Arkabutla 
Enid 
Grenada 
Meridian 
Sardis 
Piedmont 
Macon 
Kansas City 
Hermitage 
Smithville 
Wappapello 
1965 
1949 
1960 
1961 
1973 
1950 
1950 
1950 
1953 
1951 
1943 
1951 
1954 
1969 
1940 
1948 
1980 
1986 
1961 
1982 
1941 
32,400 
22,000 
12,350 
11,100 
45,000 
(2) 
122,800 
35,000 
14,100 
2,680,000 
525,300 
660,000 
1,337,400 
142,400 
1,570,000 
413,700 
65,000 
46,900 
650,000 
246,500 
613,200 
275 FRWS 
300 FRW 
NPP FRW 
23 FRW 
12,700 
NPP 
6,500 
5,100 
210 
279,000 
FRW 
FRWX 
FRWX 
FRWX 
FARS 
FARSX 
5,100 F Earth & Rock 
6,100 F Earth & Rock 
9,800 F Earth & Rock 
1,280 FQSR Earth 
10,700 F Earth & Rock 
1,630 
2,430 
930 
7,820 
7,190 
4,100 
FRWX 
FRSQW 
FRWQ 
FRWX 
FSQRW 
FR 
Republican River Republican City 1952 850,000 13,600 FIRWX Earth & Rock 107 11,827 
Knight Creek 
Trib. of Big Papillion 
Creek 
S. Trib. Olive Br. Creek 
N. Trib. Olive Br. Creek 
N. Trib. Hickman Creek 
S. Trib. Hickman Creek 
Cardwell Creek 
Holmes Creek 
Middle Creek 
N. Middle Creek 
Antelope Creek 
Oak Creek 
Blackwater River 
Nubanusit Brook 
Pemigewasset River 
Contoocook River 
Piscataquog River 
Otter Brook 
Ashuelot River 
Omaha 
Omaha 
Kramer 
Sprague 
Holland 
Hickman 
Denton 
Denton 
Pleasantdale 
Emerald 
Lincoln 
Raymond 
Webster 
West Peterborough 
Franklin 
West Hopkinton 
East Weare 
Keene 
Keene 
Mathews Canyon Caliente 
Pine Canyon Caliente 
Rio Chama 
Rio Grande 
Canadian River 
Abiquiu 
Pena Blanca 
Tucumcari 
1975 
1973 
1964 
1963 
1963 
1964 
1966 
1964 
1966 
1965 
1963 
1968 
1941 
1950 
1943 
1962 
1962 
1958 
1941 
17,910 392 FQRX Earth 
5,220 137 FRX Earth 
5,470 
10,260 
9,280 
6,640 
7,560 
10,640 
8,080 
29,520 
6,510 
97,560 
46,000 
12,800 
154,000 
71,500 
87,500 
18,300 
32,500 
174 
315 
303 
196 
208 
230 
255 
728 
100 
1,780 
NPP 
NPP 
NPP 
200 
120 
85 
265 
FR 
FR 
FR 
FR 
FR 
FR 
FR 
FR 
FR 
FR 
FRW 
FRW 
FRW 
FRW 
FRW 
FRW 
FRW 
1957 6,270 NPP FX Earth 
1957 7,750 NPP FX Earth 
1963 
1975 
1939 
1,212,000 
596,300 
529,000 
NPP FXS Earth 
1,200 FRWX Earth 
3,000 FI Concrete 
& Earth 
A-3 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth & Rock 
1,164 
62 
51 
78 
25 
23.3 
21 
19.5 
47 
15.5 
81 
99 
102 
67 
117 
154 
71 
120 
155 
95 
109 
1,360 
1,570 
2,400 
560 
13,700 
17,975 
4,100 
11,800 
1,355 
36,500 
11,500 
8,400 
13,900 
6,543 
15,300 
4,225 
3,800 
1,900 
4,630 
4,200 
2,700 
Earth & Rock 
Earth 
Earth & Rock 
Earth & Rock 
Earth 
Earth & Rock 
67 
70 
45 
57 
52 
48 
52 
63 
58 
65 
55 
70 
75 
67 
140 
76 
115 
133 
86 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
1,940 
1,460 
3,020 
2,760 
1,650 
2,250 
3,100 
3,000 
2,075 
5,000 
7,700 
5,200 
1,150 
1,030 
1,740 
790 
2,000 
1,288 
1,670 
71 800 
92 884 
325 
251 
200 
1,540 
28,300 
19,400

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1986 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage)' 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
NEW MEXICO (Continued) 
Galisteo Rio Grande 
Jemez Canyon Rio Grande 
Two Rivers: 
Diamond "A" Dam Rio Grande 
Rocky Dam Rio Grande 
Santa Rosa Dam & Pecos 
Reservoir 
NEW YORK 
Almond 
Arkport 
East Sidney 
Mount Morris 
Whitney Point 
NORTH CAROLINA 
B. Everett Jordan 
Falls 
W. Kerr Scott 
NORTH DAKOTA 
Baldhill 
Bowman-Haley 
Homme 
Pipestem 
OHIO 
Alum Creek Ohio 
Berlin Ohio 
Caesar Creek Ohio 
Clarence J. Brown Ohio 
Deer Creek Ohio 
Delaware Ohio 
Dillon Ohio 
Michael J. Kirwan Ohio 
Mosquito Creek Ohio 
Muskingum River 
Reservoirs: 
Atwood Ohio 
Beach City Ohio 
Bolivar Ohio 
Charles Mill Ohio 
Clendening Ohio 
Dover Ohio 
Leesville Ohio 
Mohawk Ohio 
Mohicanville Ohio 
Piedmont Ohio 
Pleasant Hill Ohio 
Senecaville Ohio 
Tappan Ohio 
Wills Creek Ohio 
North Branch, Ohio 
Kokosing River Lake 
Paint Creek Ohio 
Tom Jenkins Ohio 
West Fork Mill Creek Ohio 
William H. Harsha Ohio 
OKLAHOMA 
Birch Arkar 
Canton Arkar 
Copan Arkar 
Fort Supply Arkar 
Greak Salt Plains Arkar 
Heyburn 
Hugo 
Hulah 
Kaiw 
Oologah 
Optima 
Pine Creek 
Sardis 
Skiatook 
Waurika 
Wister 
Susquehanna 
Susquehanna 
Susquehanna 
Genesee 
Susquehanna 
Cape Fear 
Neuse 
Yadkin-Pee Dee 
Galisteo Creek 
Jemez River 
Rio Hondo 
Rocky Arroyo 
Pecos 
Canacadea Creek 
Canisteo Creek 
Ouleout Creek 
Genesee River 
Otselic River 
New Hope 
Neuse 
Yadkin 
Albuquerque 
Bernalillo 
Roswell 
Santa Rosa 
Hornell 
Arkport 
Franklin 
Mount Morris 
Whitney Point 
Durham 
Raleigh 
Wilkesboro 
Red River of the North Sheyenne River Valley City 
Missouri North Fork, Grand River Haley 
Red River of the North South Branch of Park River 
Park River 
James River Pipestem Creek Jamestown 
Alum Creek 
Mahoning River 
Caesar Creek 
Buck Creek 
Deer Creek 
Olentangy River 
Licking River 
West Branch, 
Mahoning River 
Mosquito Creek 
Africa 
Deerfield 
Wilmington 
Springfield 
New Holland 
Delaware 
Zanesville 
Newton Falls 
Cortland 
Indian Fork New Cumberland 
Sugar Creek Beach City 
Sandy Creek Bolivar 
Black Fork Mufflin 
Brushy Fork Tippecanoe 
Tuscarawas River Dover 
McGuire Creek Leesville 
Walhonding River Nellie 
Lake Fork Mohicanville 
Stillwater Creek Piedmont 
Clear Fork Perrysville 
Seneca Fork Senecaville 
Little Stillwater Creek Tappan 
Wills Creek Conesville 
North Branch of Fredericktown 
Kokosing River 
Paint Creek New Petersburg 
East Branch, Gloucester 
Sunday Creek 
Mill Creek Mount Healthy 
Little Miami River Williamsburg 
Birch Creek Barnsdall 
North Canadian River Canton 
Little Caney River Copan 
Wolf Creek Fort Supply 
Salt Fork, Cherokee 
Arkansas River 
Polecat Creek Sapulpa 
Kiamichi River Hugo 
Caney River Caney 
Arkansas River Ponca City 
Verdigris River Oologah 
North Canadian River Hardesty 
Little River Wright City 
Jackfork Creek Clayton 
Hominy Creek Skiatook 
Beaver Creek Waurika 
Poteau River Wister 
A-4 
Isas 
nsas 
nsas 
nsas 
nsas 
Arkansas 
Red 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Red 
Red 
Arkansas 
Red 
Arkansas 
1970 89,000 
1953 102,700 
1963 168,000 
1979 447,000 
1949 14,600 
1940 7,900 
1950 33,550 
1952 337,000 
1942 86,440 
1982 753,500 
1983 335,600 
1963 153,000 
1950 70,000 
1967 92,980 
1951 3,650 
1974 146,880 
1975 134,800 
1943 91,200 
1978 242,200 
1974 63,700 
1968 102,500 
1951 132,000 
1961 273,000 
1966 78,700 
1944 104,100 
1937 49,700 
1937 71,700 
1938 149,600 
1936 88,000 
1937 54,000 
1938 203,000 
1937 37,400 
1937 285,000 
1936 102,000 
1937 65,000 
1938 87,700 
1937 88,500 
1936 61,600 
1937 196,000 
1973 14,900 
1972 145,000 
1951 26,900 
1952 11,380 
1978 284,500 
1977 58,200 
1948 377,100 
1983 227,700 
1942 100,700 
1941 271,400 
1950 55,030 
1974 966,700 
1951 289,000 
1976 1,348,000 
1963 1,519,000 
1978 229,500 
1969 465,780 
1983 429,600 
1985 500,700 
1977 343,500 
1949 427,900 
NPP FX 
NPP FX 
NPP FX 
NPP FIX 
Earth 
Earth 
Earth 
Earth 
124 FRW Earth 
NPP F Earth 
210 FRW Concrete 
& Earth 
170 FR Concrete 
1,200 FRW Earth 
14,300 FQRSWX Earth 
11.300 FQRSWX Earth 
1,470 FARSX Earth 
325 FARS Earth 
1,750 FSRWX Earth 
51 FARS Earth 
885 FRWX Earth 
158 2,820 
135 780 
98 4,885 
118 2,940 
212 1,950 
90 1,260 
113 1,200 
130 2,010 
210 1,028 
95 4,900 
112 1,330 
92 1,915 
148 1,740 
61 1,650 
79 5,730 
67 865 
108 4,000 
348 FRSW Concrete 93 10,000 
& Earth 
240 FARSWQ Concrete 96 5,750 
& Earth 
13,300 FRSQW Earth & Rock 165 2,750 
1,010 FQRW Earth & Rock 72 6,620 
727 FRW Earth 93 3,880 
950 FARWX Earth 92 18,600 
1,325 FRWX Earth 118 1,400 
580 FAQRSW Earth 83 9,900 
700 FARSWQ Earth 47 5,650 
1,540 FRX Earth 65 3,700 
420 FRX Earth 64 5,600 
NPP FR Earth 87 6,300 
1,350 FRX Earth 48 1,390 
1,800 FRX Earth 64 950 
350 FRX Concrete 83 824 
1,000 FRX Earth 74 1,694 
NPP FR Earth 111 2,330 
NPP FR Earth 46 1,220 
2,270 FRX Earth 56 1,750 
850 FRX Earth 113 775 
3,550 FRSX Earth 45 2,350 
2,350 FRX Earth 52 1,550 
900 FRX Earth 87 1,950 
98 FRW Earth 71 1,400 
710 FRSQW Earth & Rock 118 700 
394 FRSWX Concrete 84 944 
200 FRX Earth 100 1,100 
18,760 FRSQW Earth 200 1,450 
1,137 FSQRW Earth 
7,910 FSI Earth 
4,850 FSQRW Earth 
1,820 FSX Earth 
8,690 FRWX Earth 
880 FRWXS Earth 
13,250 FSQRW Earth 
3,570 FSAX Earth 
17,040 FSQRW Earth 
29,460 FSN Earth 
5,340 FSRW Earth 
3,750 FSQW Earth 
14,360 FSRW Earth 
10,190 FSQRW Earth 
10,100 FISQWR Earth 
5,360 FSAX Earth 
97 3,193 
73 15,140 
70 7,730 
85 12,225 
68 6,010 
89 2,920 
101 10,200 
94 5,200 
125 9,466 
137 4,000 
120 15,200 
124 7,712 
81 14,138 
143 3,590 
106 16,600 
99 5,700

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1986 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage)' 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
OREGON 
Applegate 
Blue River 
Cottage Grove 
Dorena 
Fall Creek 
Fern Ridge 
Willow Creek 
PENNSYLVANIA 
Alvin R. Bush 
Aylesworth Creek 
Beltzville 
Blue Marsh 
Conemaugh 
Cowanesque 
Crooked Creek 
Curwensville 
East Branch, 
Clarion River 
Foster Joseph Sayers 
Francis E. Walter 
(Bear Creek) 
Gen. Edgar Jadwin 
Indian Rock 
Kinsua 
Loyalhanna 
Mahoning Creek 
Prompton 
Raystown 
Shenango 
Stillwater 
Tioga-Hammond Lakes 
-Hammond Lakes 
Tionesta 
Union City 
Woodcock Creek 
Youghiogheny River 
SOUTH DAKOTA 
Cold Brook 
Cottonwood Springs 
Lake Traverse: 
Reservation Control 
Dam 
White Rock 
TEXAS 
Rogue River 
Columbia 
Columbia 
Columbia 
Columbia 
Columbia 
Columbia 
Susquehanna 
Susquehanna 
Delaware 
Delaware 
Ohio 
Susquehanna 
Ohio 
Susquehanna River 
Ohio 
Susquehanna 
Delaware 
Delaware 
Susquehanna 
Ohio 
Ohio 
Ohio 
Delaware 
Susquehanna 
Ohio 
Susquehanna 
Susquehanna 
Susquehanna 
Ohio 
Ohio 
Ohio 
Ohio 
Applegate River 
Blue River 
Coast Fork, 
Willamette River 
Row River 
Middle Fork, 
Willamette River 
Long Tom River 
Willow Creek 
Medford 
Blue River 
Cottage Grove 
Cottage Grove 
Eugene 
Eugene 
Heppner 
Kettle Creek Renovo 
Aylesworth Creek Archbald 
Pohopoco Lehighton 
Tulephocken Blue Marsh 
Conemaugh River Saltsburg 
Cowanesque River Lawrenceville 
Crooked Creek Ford City 
West Branch, Curwensville 
Susquehanna River 
East Branch, Wilcox 
Clarion River 
Bald Eagle Creek Blanchard 
Lehigh River White Haven 
Dyberry Creek Honesdale 
Codorus Creek York 
Allegheny River Warren 
Loyalhanna Creek Saltsburg 
Mahoning Creek New Bethlehem 
Lackawaxen River Honesdale 
Raystown Branch, Huntingdon 
Juniata River 
Shenanago River Sharpsville 
Lackawanna River Uniondale 
Tioga River Tioga 
Crooked Creek Tioga 
Tionesta Creek Tionesta 
French Creek Union City 
French Creek Meadville 
Youghiogheny River Confluence 
Missouri Cold Brook 
Missouri Cottonwood Springs 
Creek 
Red River of the North Bois de Sioux River 
Red River of the North Bois de Sioux River 
Addicks San Jacinto 
Aquilla Brazos 
Bardwell Trinity 
Barker San Jacinto 
Belton Brazos 
Benbrook Trinity 
Canyon Guadalupe 
Ferrells Bridge Dam- Red 
Lake O' the Pines 
Granger Dam and Lake Brazos 
Grapevine Trinity 
Hords Creek Colorado 
Lake Kemp Red 
Lavon Trinity 
Lewisville Trinity 
Navarro Mills Trinity 
North San Gabriel Dam, Brazos 
Lake Georgetown 
Hot Springs 
Hot Springs 
Wheaton 
Wheaton 
South Mayde Creek Addicks 
Aquilla Creek Hillsboro 
Waxahachie Creek Ennis 
Buffalo Bayou Barker 
Leon River Belton 
Clear Fork, Trinity River Fort Worth 
Guadalupe New Braunfels 
Cypress Creek Jefferson 
San Gabriel River Granger 
Denton Creek Grapevine 
Hords Creek Coleman 
Wichita River Wichita Falls 
East Fork, Trinity River Fort Worth 
Elm Fork, Trinity River Lewisville 
Richland Creek Corsicana 
North Fork, Georgetown 
San Gabriel River 
1981 82,000 
1968 85,000 
1942 30,060 
1949 70,500 
1965 115,000 
1941 110,000 
1983 13,250 
1962 75,000 
1970 1,700 
1971 68,250 
1978 22,900 
1952 274,000 
1980 89,000 
1940 93,900 
1965 124,200 
1952 84,300 
1969 99,000 
1961 110,000 
1960 24,500 
1942 28,000 
1965 1,180,000 
1942 95,300 
1941 74,200 
1960 52,000 
1973 762,000 
1966 191,400 
1960 12,000 
1978 62,000 
1978 63,000 
1940 133,400 
1970 47,640 
1973 20,000 
1943 254,000 
1953 7,200 
1970 8,385 
1941 164,500 
1941 85,000 
1948 204,500 
1983 146,000 
1965 140,000 
1945 207,000 
1954 1,097,600 
1952 258,600 
1964 740,900 
1959 842,100 
1980 244,200 
1952 425,500 
1948 25,310 
1972 502,900 
1953 748,200 
1954 989,700 
1962 212,200 
1980 130,800 
988 AFIQRSW Gravel Em- 242 1,300 
bankment 
975 FINR Earth 319 1,329 
1,155 FINR Concrete 114 2,110 
& Earth 
1,885 FINR Concrete 145 3,352 
& Earth 
1,865 FINR Rockfill 193 5,100 
& Concrete 
10,305 FINR Rockfill 49 6,624 
& Concrete 
96 FRN Roller 160 1,780 
Compacted 
Concrete 
160 FRW Earth & Rock 165 1,350 
NPP F Earth & Rock 90 1,270 
947 FQRSW Earth & Rock 170 4,300 
963 FAQRS Earth & Rock 98 1,775 
300 FW Concrete 137 1,265 
& Earth 
410 FR Earth & Rock 151 3,100 
350 FRW Earth 143 1,480 
790 FR Earth 131 2,850 
90 FARQW Earth 184 1,725 
1,730 FRW Earth 100 6,835 
90 FNRW Earth & Rock 234 3,000 
NPP F Earth 109 1,225 
NPP FRW Earth 83 1,000 
1,900 PFAQRW Concrete 177 1,877 
& Earth 
210 FRW Concrete 114 960 
& Earth 
170 FRW Concrete 162 926 
290 FNRW Earth 140 1,230 
8,300 FRW Earth & Rock 225 1,700 
1,910 FAQRW Concrete 68 720 
85 FS Earth 77 1,700 
470 FR Earth & Rock 140 2,710 
680 FR Earth & Rock 122 6,450 
480 FRW Earth 154 1,050 
NPP F Earth 88 1,420 
118 FQRA Earth 90 4,650 
450 FARWQ Earth 184 1,610 
36 FRWX Earth 
41 FRWX Earth 
10,925 FRX Earth 
6,500 FRX Earth 
127 925 
123 1,190 
14 9,100 
16 14,400 
NPP FX Earth 49 61,166 
3,280 FSX Earth 104.5 11,890 
3,570 FRSX Earth 82 15,400 
NPP FX Earth 37 72,844 
12,300 FIRSX Earth 192 5,524 
3,770 FNRXA Earth 130 9,130 
8,240 FRSX Earth 224 6,830 
18,700 FRS Earth 97 ].0,600 
4,400 FRSWX Earth 115 16,320 
7,280 FNRSXA Earth 137 12,850 
510 FARSX Earth 91 6,800 
15,590 FX Earth & Rock 115 8,890 
21,400 FRSX Earth 81 19,483 
23,280 FRSX Earth 125 32,888 
5,070 FRSX Earth 82 7,570 
1,310 FRSWX Rock 164 6,700 
A-5

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1986 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage)' 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
TEXAS (Continued) 
O. C. Fisher 
Pat Mayse 
Proctor 
Somerville 
Stillhouse Hollow 
Waco 
Wright Patman 
VERMONT 
Ball Mountain 
North Hartland 
North Springfield 
Townshend 
Union Village 
VIRGINIA 
John W. Flannagan 
Gathright Dam & 
Lake Moomaw 
North Fork of 
Pound River 
WASHINGTON 
Howard A. Hanson 
Mill Creek 
Mud Mountain 
Wynoochee 
WEST VIRGINIA 
Beech Fork 
Bluestone 
Burnsville 
East Lynn 
R. D. Bailey 
Summersville Lake 
Sutton 
Tygart River 
WISCONSIN 
Eau Galle 
Colorado 
Red 
Brazos 
Brazos 
Brazos 
Brazos 
Red 
Connecticut 
Connecticut 
Connecticut 
Connecticut 
Connecticut 
Ohio 
James 
Ohio 
Green 
Columbia 
Puyallup 
Chehalis 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Chippewa 
North Concho River 
Sanders Creek 
Leon River 
Yegua Creek 
Lampasas River 
Bosque River 
Sulphur River 
West River 
Ottauguechee River 
Black River 
West River 
Ompompanoosuc River 
Pound River 
Jackson 
North Fork, Pound River 
Green River 
Mill Creek 
White River 
Wynoochee River 
Beech Fork 
New River 
Little Kanawha 
Twelve Pole Creek 
Guynabdot River 
Gauley River 
Elk River 
Tygart River 
Eau Galle 
San Angelo 
Paris 
Comanche 
Somerville 
Belton 
Waco 
Texarkana 
Jamaica 
North Hartland 
Springfield 
Townshend 
Union Village 
Haysi 
Alleghany 
Pound 
Kanaskat 
Walla Walla 
Enumclaw 
Montesano 
Lavalette 
Hinton 
Burnsville 
East Lynn 
Justice 
Summersville 
Sutton 
Grafton 
Spring Valley 
1952 
1967 
1963 
1967 
1968 
1965 
1957 
1961 
1960 
1960 
1961 
1950 
1963 
1979 
1966 
1961 
1942 
1953 
1972 
1977 
1952 
1977 
1970 
1979 
1965 
1960 
1938 
396,400 
189,100 
374,200 
507,500 
630,400 
726,400 
2,654,300 
54,600 
71,420 
51,067 
33,700 
38,000 
145,700 
123,739 
11,293 
106,000 
8,300 
106,000 
70,000 
37,540 
631,000 
65,400 
82,500 
203,700 
413,800 
265,300 
287,700 
5,440 
5,993 
4,610 
11,460 
6,430 
7,270 
20,300 
75 
220 
290 
100 
NPP 
FRSX 
FRSX 
FRSX 
FRSX 
FRSX 
FRSX 
FRSX 
FRW 
FRW 
FRW 
FRW 
FRW 
Earth 
Earth 
Earth 
Earth 
Earth 
Concrete & 
Earth 
Earth 
Concrete & 
Earth 
Concrete & 
Earth 
Concrete & 
Earth 
Concrete & 
Earth 
Concrete & 
Earth 
310 FAQR Concrete & 
Earth 
2,532 FQR Earth & Rock 
106 FR Rock 
1,600 FAS 
225 FR 
NPP FR 
1,150 FSARI 
450 
1,800 
550 
823 
440 
407 
270 
620 
FRW 
FRWX 
FQRW 
FQRW 
FQRW 
FANR 
FARWX 
FNAR 
Rock 
Earth 
Rock 
Concrete & 
Earth 
Earth 
Concrete 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Rock 
Concrete 
Concrete 
1969 43,600 150 FR Earth 
A-6 
128 40,885 
96 7,080 
86 13,460 
80 26,175 
200 15,624 
140 24,618 
100 18,500 
265 915 
185 1,520 
120 2,940 
133 1,700 
170 1,100 
250 960 
257 1,172 
122 600 
235 675 
145 3,200 
425 700 
177 1,700 
86 1,080 
180 2,048 
89 1,400 
122 650 
310 1,397 
390 2,280 
220 1,178 
230 1,921 
122 1,600

FLOOD CONTROL RESERVOIRS CONSTRUCTED OR CONTRIBUTED TO 
BY CORPS OF ENGINEERS BUT OPERATED BY OTHERS 
SEPTEMBER 30, 1986 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage)' 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
CALIFORNIA 
Big Dry Creek 
Camanche
2 
Cherry Valley' 
Del Valle 
Eaton Wash 
New Bullards Bar
2 
New Don Pedro' 
New Exchequer 
Oroville' 
Tahchevah Creek 
COLORADO 
Pinon Canyon 
CONNECTICUT 
East Branch 
Hall Meadow Brook 
Mad River 
Sucker Brook 
HAWAII 
Kaneohe Dam 
IDAHO 
Ririe 
MARYLAND 
Savage River 
MISSOURI 
Bear Creek 
NEW YORK 
Onondaga 
OKLAHOMA 
Altus' 
Lake Hudson
s 
Grand Lake O' 
the Cherokees 
UTAH 
Big Wash 
VERMONT 
East Barre 
Waterbury 
Wrightsville 
San Joaquin 
San Joaquin 
Tuolumne 
Alameda 
Rio Hondo 
Sacramento 
San Joaquin 
San Joaquin 
Sacramento 
Whitewater 
Colorado 
Housatonic 
Housatonic 
Connecticut 
Connecticut 
Kaneohe 
Upper Snake 
Potomac 
Upper Mississippi 
Oswego 
Red 
Arkansas 
Arkansas 
Beaver 
Winooski 
Winooski 
Winooski 
Big Dry Creek 
Mokelumne River 
Cherry Creek 
Arroyo Del Valle 
Eaton Wash 
Yuba River 
Tuolumne River 
Merced River 
Feather River 
Tahchevah Creek 
Pinon Canyon Arroyo 
East Branch, 
Naugatuck River 
Hall Meadow Brook 
Mad River 
Sucker Brook 
Fresno 
Clements 
Sonora 
Livermore 
Pasadena 
Marysville 
Modesto 
Merced 
Oroville 
Palm Springs 
Trinidad 
Torrington 
Torrington 
Winchester 
Winchester 
Kaneohe Stream Kaneohe 
Willow Creek 
Savage 
Bear Creek 
Idaho Falls 
Western Port 
Hannibal 
Onondaga Creek Syracuse 
North Fork, Red 
Grand (Neosho) River 
Grand (Neosho) River 
Big Wash 
Jail Branch 
Waterbury 
North Branch, 
Winooski River 
Altus 
Locust Grove 
Disney 
Milford 
East Barre 
Waterbury 
Wrightsville 
1948 
1963 
1956 
1968 
1937 
1968 
1970 
1966 
1964 
1965 
16,250 
431,500 
268,000 
77,000 
960 
960,000 
2,030,000 
1,026,000 
3,539,000 
960 
NPP F 
NPP FRS 
475 FS 
200 FRS 
NPP F 
1,910 FIRPW 
3,520 FISP 
1,900 FIR 
5,838 FIRSW 
NPP F 
Earth 
Earth & Rock 
Earth & Rock 
Earth 
Earth 
Concrete 
Earth & Rock 
Rock 
Earth 
Earth 
1964 4,350 NPP FRW Earth 
1964 
1962 
1963 
1970 
4,350 NPP FR 
8,620 NPP F 
9,700 10 FR 
1,480 NPP F 
Earth 
Earth & Rock 
Earth 
Earth 
1981 3,800 26 FR Earth 
1979 100,500 364 FIR Earth 
1952 20,000 360 FRS Earth & Rock 184 
1962 8,700 NPP F 
1949 18,200 NPP F 
1948 
1964 
1941 
152,429 
444,500 
2,197,000 
6,260 FISR 
10,900' FRP 
46,500 " FRP 
1961 1,200 NPP F 
1938 
1938 
1938 
Earth 
Earth 
Concrete 
Concrete 
& Earth 
Concrete 
Earth 
12,050 NPP F Earth 
37,000 890 FRH Earth 
20,300 570 FR Earth 
NOMENCLATURE FOR PROJECT FUNCTIONS: 
A-Low Flow Augmentation 
D-Debris Control 
F -Flood Control 
I -Irrigation 
N- Navigation 
P -Power 
Q-Water Quality Control 
R--Public Recreation (Annual Attendance exceeding 5,000) 
S -Water Supply 
W-Fish and Wildlife (Federal or State) 
X-Water Conservation and Sedimentation 
' Acres of water surface at top of permanent pool. 
'Federal Government contributed for flood control storage. 
' Cherry Valley Reservoir: Planned and constructed by local interests as initial phase; provided flood control on interim basis. Second and final phase, New Don Pedro Reservoir: Federal 
Government contributed for flood protection, construction and operation by City and County of San Francisco, and Turlock and Modesto Irrigation Districts. 
4 Construction by Bureau of Reclamation. Participation by Department of the Army to finance flood control portion. 
'Construction by Grand River Dam Authority. Participation by Department of the Army to finance flood control portion. 
'Top of power pool. 
A-7 
40 
171 
315 
223 
82 
645 
565 
480 
770 
42 
20,038 
2,450 
2,500 
880 
1,795 
2,323 
1,920 
1,200 
6,850 
3,610 
92 700 
92 
73 
178 
68 
100 
1,200 
940 
1,160 
76 2,200 
184 840 
1,050 
65 1,450 
67 1,782 
98 
90 
147 
1,112 
4,494 
6,565 
34 2,814 
65 
158 
115 
1,460 
1,800 
1,525

APPENDIX B 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1986 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Adams Co., Overy Bridge, Little Blue River, NE (Sec 14) ............. 
Alamosa, CO (Sec 14) .. ................................ 
Allegheny River, Oil City, PA (Sec 205)............................. 
Allegheny River, Tionesta, PA (Sec 14) ............................. 
Alpena, M I (Sec 14).................................... 
Alton to Gale Levee System, Mississippi River, IL and MO ........... 
Alum Creek Lake, OH. ................................. 
Andrew Co., Road T, Nodaway River, MO (Sec 14) ................... 
Andrew-Holt Co's Bridge, Nodaway River, MO (Sec 14) .............. 
Ararat River, Mt. Airy, NC (Sec 205) ............................... 
A rcadia Lake, OK ....................................... ........ 
Arkansas-Red Basins Chloride Control (Area VIII), OK, TX, and 
K S (Stage I) ................................................... 
Ascalmore-Tippo Items, M S ................ ...................... 
Asquiroga Bay Shoreline (Guam) (Sec 14) ............................ 
B. Everett Jordan Dam and Lake, NC .............................. 
Barkers Island, W I (Sec 14) ................ ....................... 
Bayshore, W I (Sec 14)................. ........................... 
Beaver Brook, Keene, NH (Sec 205) ................................ 
Beaver River, Bridgewater, PA (Sec 14) ............................ 
Beech Fork Lake, WV. ............ ..................... 
Bettendorf, IA ....................................... 
Big Brown Creek & Tributary, Prentiss Co., MS ................ 
Big Sioux River, Harrisburg, SD (Sec 14)........................... 
Big Sioux River, Plymouth Co., IA (Sec 14) ......................... 
Big Sioux River, Sec. 32, Plymouth Co., IA (Sec 14) .................. 
Big Sioux River, Well House, SD (Sec 14) ........................... 
Big South Fork National River & Recreation Area, KY and TN ........ 
Big Stone Lake & Whetstone River, MN and SD ..................... 
Big W ood River, ID (Sec 208)...................................... 
Black Bear and Miller Lakes, Crow Wing County, WI (Sec 205) ........ 
Blackbird Creek, Burt Co., NE (Sec 14) ............................. 
Black River, Butler County Road 607, MO (Sec 14) ................... 
Blackstone River, Millbury, MA (Sec 14).. . ................. 
Bloomington Lake, MD and WV ................................... 
Blue River Channel, M O ................ .......................... 
Boise River, ID (Sec 208) ................. ......................... 
Boligee Canal, Boligee, AL ................. ....................... 
Bradford, TN (Sec 208) ................ ........................... 
Bridgeport, MI (Sec 14) ........................................... 
Brookville Lake, IN ................. ............................. 
Brush Bayou, LA ............... ...................... 
Buffalo Bayou and Tributaries, TX ................................ 
Buffalo Bayou and Tributaries, TX, Addicks and Barker, 
Dam Safety Assurance ................ ......................... 
Burnsville Lake, WV............. ......... 
Caesar Creek Lake, OH ........................................... 
Calloway Branch, TX .. ...... ........................... 
Candy Lake, OK ................. ................................ 
Canton Bridge, Trigg Co., KY ................ ..................... 
Catherine Creek, OR (Sec 208) ................. .................... 
Cave Run Lake, KY ................. ............................. 
Central and Southern, FL ................. ........................ 
Charlevoix, M I (Sec 14) ................... ...................... 
Chartiers Creek, McKees Rocks & Kennedy TWP, PA (Sec 14) ........ 
Chatfield Lake, CO .................. ............................. 
Chattahoochee River, Eufaula, AL ................................. 
Chena River Lakes, AK .................. ......................... 
Chillicothe, OH ...................................... 
Clear River, Burrillville, RI (Sec 14) ................ ................ 
Colfax, Palouse River, WA . ........ ...................... 
Columbus, NE (Sec 205)............ ..................... 
Conesus Lake, Livonia, NY (Sec 205)............. ........... 
Cooper Lake and Channels, TX ............. .................... 
Copan Lake, OK................ ..................... 
Corte Madera Creek, CA ..... ............. .................. 
Covered Bridge, Housatonic River, Sheffield, MA (Sec 14).......... 
1985 
1983 
1982 
1983 
1982 
1983 
1970 
1985 
1986 
1985 
1980 
1976 
1984 
1985 
1967 
1985 
1985 
1985 
1986 
1970 
1982 
1986 
1985 
1984 
1984 
1985 
1979 
1971 
1984 
1984 
1985 
1985 
1985 
1971 
1984 
1984 
1986 
1983 
1986 
1966 
1977 
1956 
1986 
1972 
1971 
1985 
1976 
1986 
1985 
1965 
1950 
1984 
1986 
1967 
1986 
1973 
1971 
1986 
1962 
1982 
1986 
1958 
1973 
1966 
1986 
1986 
1984 
1983 
1984 
1983 
1975 
1986 
1986 
1987 
1986 
1982 
1985 
1985 
1986 
1978 
1986 
1975 
1985 
1986 
1981 
1986 
1984 
1987 
1974 
1978 
1986 
1982 
1985 
1974 
1981 
1966 
1986 
1983 
1986 
1984 
1984 
1984 
1983 
1984 
1986 
1986 
1986 
1987 
1987 
19853 
1987 
1986 
1989 
1986 
1986 
1987 
1987 
1987 
1987 
1987 
1987 
1986 
1987 
1987 
1988 
1986 
1985 
1987 
1987 
1986 
1986 
1984 
1994 
1985 
1986 
1984 
1987 
1984 
1980 
Indefinite 
ID 
Streambank protection 
Streambank protection 
Streambank protection 
Streambank protection 
Local protection 
Local protection 
Reservoir 
Streambank protection 
Streambank protection 
Local protection 
Reservoir 
Chloride Control 
Local protection 
Emergency protection 
Reservoir 
Shoreline protection 
Shoreline protection 
Local protection 
Streambank protection 
Reservoir 
Local protection 
Streambank protection 
Streambank protection 
Streambank protection 
Streambank protection 
Streambank protection 
National Recreation Area 
Local protection 
Snagging and Clearing 
Local protection 
Streambank protection 
Streambank protection 
Streambank protection 
Reservoir 
Local protection 
Snagging and Clearing 
Snagging and Clearing 
Local protection 
Streambank protection 
Reservoir 
Local protection 
Local protection 
1989 Dam Safety 
1986 Reservoir 
1986 Reservoir 
1986 Local protection 
)eferred Reservoir 
1987 Streambank protection 
1986 Snagging and Clearing 
1987 Reservoir 
1997 Local protection 
1986 Shoreline protection 
1987 Streambank protection 
1989 Reservoir and Channel 
Improvement 
1987 Shoreline protection 
1994 Reservoirs and levee 
1986 Local protection 
1987 Streambank protection 
1984 Local protection 
1987 Local protection 
1987 Local protection 
1992 Reservoir, channel 
improvement and levees 
1985 Reservoir 
1989 Local protection 
1987 Streambank protection 
B-1

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1986 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Creek Road Bridge, MS ............... .................. 
Cucamonga Creek, CA....... ................ ........... 
Cuyahoga River, Akron, OH (Sewerline) (Sec 14) ..................... 
Cuyahoga Street Bridge, Akron, OH (Sec 14) ........................ 
D ade County, FL ................. ............................... 
Darby Creek, PA ........ .............................. 
Dayton, KY.......... ........................... .... 
Demonstration Erosion Control, MS ............... ......... .. 
Devils Lake, ND (Sec 205) .. ............. ................. 
Dry Creek (Warm Springs) Lake & Channel, CA ..................... 
Dunbar (Sewage Facilities), WV (Sec 14) ...................... 
.East Branch, Cooper River, Pompion Hill Chapel near 
Huger, SC (Sec 14) .................................... 
East Bridge, Chagrin River, Baldwin Rd, Kirtland, OH (Sec 14) ....... 
East Bridge, Chagrin River, SR 615, Kirtland, OH (Sec 14)............ 
East Lynn Lake, W V ................................... 
East Rockaway Inlet to Rockaway Inlet & Jamaica Bay, NY, 
Part I......................................... ............... 
East St. Louis and Vicinity, IL ................... ........... 
El Dorado Lake, KS . ................................... 
E l Paso, T X .................. ................................... 
Elizabeth, NJ ................... .................... 
Elk Creek, Clarksburg, WV (Sec 14) ................................ 
Elk Creek, Jackson, NE (Sec 14) .............. .................... 
Elk Creek, Lake, OR.............. ...................... 
Elk Creek, W illis, NE (Sec 14) ............... ..................... 
Elkhart, IN (Sec 14) .................. ............................ 
Ellicott Creek, N Y .................. ............................. 
Elm Creek, Burt Co., NE (Sec 14) ............... ................... 
Enderlin, Maple River, ND (Sec 205) ............................... 
Euclid Creek, OH (Sec 205) .................. ...................... 
Fairfield Vicinity Streams, CA ................ .................... 
Falls Lake, NC........ ................................ 
Fire Island Inlet to Montauk Point, NY ................. ......... 
(Remainder)... ................ .................... 
Four Rivers Basin, FL .............. ................... 
Goodfood Creek, Chickasaw Co., MS ........ ................ 
Grays Creek Canal, Shelby Co., TN ................................ 
Grays Creek, Memphis, TN (Sec 14) .. ........................... 
Great Falls, MT................. ...................... 
Greenwood Bendway, Site 3, MS .................................. 
Gulf Street and Trumbull Avenue, Milford, CT (Sec 14) ............... 
Hanover, Hannapin County, MN (Sec 14) ........................... 
Hatchie River, Alcorn Co., MS .............. ................... 
Holt Co. Bridge, Kimsey Creek, MO (Sec 14) ......................... 
Hooverson Heights, WV (Sec 14) .......... ................. 
Humboldt, TN.. .......... ......... ............ 
Hwy 90, St. Francis River, AR (Sec 14) ..: ..................... 
Indian Creek, Emerson, IA (Sec 205) ............................... 
Irving Township at Nicols Road, Jackson County, WI (Sec 14) ........ 
Joe Pool Lake, TX ............... . .................... 
John Day River (West), OR (Sec 14) ................................ 
Johnson Co., Tecum Bridge, Yankee Creek, NE (Sec 14) .............. 
Johnson Co., Vesta Bridge, Yankee Creek, NE (Sec 14) ............... 
Kahoma Stream, Maui, HI ................................. 
Kaskaskia Island Drainage & Levee Dist, IL ........................ 
Kickapoo River, Gays Mills, WI (Sec 14) ......................... 
Kuskokwim River, Bethel, AK (Sec 14) ............................. 
Lake Chicot Pumping Plant, AR ................ ........... 
Lake Darling, Souris River, ND ... .......... ............. 
Lake Erie, SR 531, Geneva, OH (Sec 14) ............................ 
Lake Michigan, Cleveland, WI ............. ................... 
Lake Michigan, Grand Haven, WI (Sec 14) ........................ 
Lake Michigan, Pt. Washington, WI (Sec 14) ..... ................. 
Lake Michigan, Waterworks Facility, Cudahy, WI.............. 
Lake Pontchartrain, LA ..................................... 
Lake Pulaski, Wright County, MN (Sec 205)...................... 
Larose to Golden Meadow, LA .............. ................... 
1985 
1976 
1985 
1984 
1975 
1986 
1978 
1985 
1983 
1967 
1986 
1986 
1986 
1986 
1965 
1975 
1974 
1974 
1971 
1972 
1986 
1984 
1971 
1985 
1984 
1986 
1985 
1982 
1983 
1986 
1973 
1963 
1963 
1966 
1986 
1985 
1984 
1982 
1986 
1986 
1986 
1985 
1985 
1986 
1986 
1984 
1983 
1985 
1975 
1985 
1985 
1985 
1986 
1980 
1986 
1985 
1981 
1985 
1986 
1986 
1986 
1984 
1986 
1967 
1986 
1972 
1985 
1982 
1986 
1985 
1982 
1986 
1983 
1987 
1970 
1977 
1981 
1973 
1986 
1985 
1986 
1986 
1983 
1985 
1986 
1986 
1987 
1985 
1986 
1986 
1986 
1987 
1986 
1985 
1987 
1985 
1988 
1986 
1986 
1992 
1987 
1986 
Indefinite 
1987 
1988 
1987 
1987 
1987 
1987 
1982 
1988 
1986 
1986 
Indefinite 
1986 
1987 
1986 
1990 
1987 
1986 
1989 
1987 
1986 
1986 
1989 
1990 
Indefinite 
Indefinite 
1990 
1987 
1986 
1987 
1987 
1987 
1987 
1987 
1986 
1986 
1987 
1988 
1985 
1986 
1986 
1990 
1986 
1986 
1986 
1989 
1986 
1987 
1986 
1985 
1991 
1987 
1987 
1986 
1986 
1987 
Indefinite 
1987 
1992 
Streambank protection 
Local protection 
Local protection 
Local protection 
Shore protection 
Streambank protection 
Local protection 
Local protection 
Local protection 
Reservoir 
Streambank protection 
Streambank protection 
Streambank protection 
Streambank protection 
Reservoir 
Beach nourishment 
Local protection 
Reservoir 
Local protection 
Local protection 
Streambank protection 
Streambank protection 
Reservoir 
Streambank protection 
Streambank protection 
Local protection 
Streambank protection 
Local protection 
Local protection 
Local protection 
Reservoir 
Local protection 
Local protection 
Local protection 
Bridge protection 
Bank protection 
Streambank protection 
Local protection 
Riverbank protection 
Streambank protection 
Streambank protection 
Flood control 
Streambank protection 
Streambank protection 
Flood control 
Streambank protection 
Local protection 
Streambank protection 
Reservoir 
Streambank protection 
Streambank protection 
Streambank protection 
Local protection 
Local protection 
Streambank protection 
Streambank protection 
Local protection 
Reservoir 
Streambank protection 
Shoreline protection 
Shoreline protection 
Shoreline protection 
Shoreline protection 
Local protection 
Local protection 
Local protection 
B-2

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1986 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Lavon Lake Modification and East Fork Channel Improvement, 
TX ..................................... . 
Lead Bayou, MS (Sec 205) ...................................... 
Leaf & Bowie Rivers, Hattiesburg, MS ...................... ... 
Levee Unit 5, W abash River, IN ................................. 
Levisa & Tug Forks of the Big Sandy River & Cumberland 
River, KY, WV & VA ........................................... 
Lewis Branch (Mile 2.0 to 4.0) County Rd, Houston Co., TN ........... 
Little Blue River Channel, MO .................................... 
Little Blue River Lakes, MO ................ ................... 
Little Dell Lake, UT ..................................... 
Little Kanawha River, Glenville, WV (Sec 14) .................. 
Little MassardCreek, Ft. Smith, AR (Sec 205) . ................. .. 
Little Red River, Clinton, AR (Sec 205) ................ ......... 
Long Branch Lake, MO ....................................... 
Los Coches Creek, San Diego County, CA (Sec 205) .................. 
Lower Columbia River Bank Protection, OR and WA ................ 
Lower San Joaquin River, CA (Snagging & Clearing) ................. 
Lytle & Warm Creeks, Santa Ana River Basin, CA ................... 
Mahoning River, Highway 139 A, OH (Sec 14) ....................... 
Mahoning River, Warren, TWP, OH (Sec 14) ...................... 
Manistee, MI (Sec 14) ................ ................... ...... 
Mankato and N. Mankato, MN ................ ................. 
Maple River, MI (Sec 208) ......................................... 
Marginal Way, Ogunquit, ME (Sec 14) ................ .......... 
Martin Creek, Prentiss Co., MS ................ ................. 
Martins Fork Lake, KY .......................... .......... 
Mauvaise Terre, IL............. ... .................... 
McGee Creek Drainage and Levee Dist., IL ......................... 
Medicine Bow River, Elk, MT, WY (Sec 14) .......................... 
M erced County Streams, CA ....................... ............... 
Middle Fork Nooksack River, Deming, WA (Sec 14) .................. 
Middle River at Argyle, MN (Sec 205) ................. .......... 
Milan, IL ............................................ 
Mill Brook, Brownsville, VT (Sec 14) .............. .............. 
Mill Creek, OH... ..................................... 
Miller Co. Roadway, Osage River, MO (Sec 14) ................. .... 
Minnesota River at Le Sueur, MN (Sec 14) . ....................... 
Missouri River Levee System, IA, NE, KS, and MO .................. 
Miss. River Levees....................................... 
Monongahela River, Granville, WV (Sec 14) ......................... 
Mt. St. Helens Sediment Control, WA ................... ......... 
Mt. St. Helens & Vicinity, WA ................ ................. 
Muddy Creek, Syracuse, NE (Sec 14)............... ............. . 
Mudline to Pineville, MS ................ ... ................ .... 
Murder & Burnt Corn Creeks, Brewton, AL ...................... 
Muskingham River Lakes, OH ................ ................. 
Muskingum River Lakes, OH 
(Dam Safety Assurance) .................. ......... ........ 
New London, CT ............................................... 
New Orleans to Venice, LA ................... .. ................. 
Newark, OH......................................... 
Nonconnah Creek at Lamar Ave., Memphis, TN ................... 
Nonewaug River, Woodbury, CT (Sec 14) ................ ....... 
Noxubee River Relief Bridge, Shuqualak, MS ...................... 
Ofu Airstrip, American Samoa (Sec 14) ............................. 
Ohio River, Chester, WV (Sec 14) ................ ............. 
Otter Creek, Shannon Hills, AR (Sec 205) .............. ........ 
Owyhee River, OR (Sec 208) ................................. .. . 
Paintsville Lake, KY .......................................... 
Panola-Quitman Item C, MS ................................... 
Papillion Creek and Tributaries Lake, NE ........................ 
Patoka Lake, IN ................ ............................ 
Paw Paw, MI (Sec 205) ................... ..................... 
Pawtuxet River, Warwick, RI (Sec 205) ................ .......... 
Pearl River, MS ............ ........ .. .... .......... 
Pelucia Creek, Item 1, MS ..................................... 
Perkiomen Creek, PA ......................................... 
1970 
1982 
1986 
1964 
1981 
1986 
1975 
1978 
1986 
1986 
1983 
1985 
1973 
1986 
1961 
1985 
1973 
1985 
1986 
1984 
1971 
1984 
1986 
1986 
1973 
1985 
1979 
1986 
1986 
1986 
1985 
1980 
1986 
1981 
1985 
1985 
1948 
1928 
1986 
1986 
1983 
1984 
1984 
1986 
1976 
1982 
1978 
1969 
1976 
1986 
1984 
1986 
1986 
1983 
1984 
1986 
1973 
1984 
1972 
1972 
1985 
1982 
1984 
1985 
1986 
1976 1985 
(mod.) 
1985 
1987 
1969 1986 
Indefinite 
1987 
1987 
1989 
1990 
1987 
1984 1984 
1987 
1980 Indefinite 
1987 
Indefinite 
1988 
1987 
1985 1985 
1987 
1985 1986 
1990 
1985 1985 
1987 
1987 
1978 1982 
1987 
1985 
1986 1986 
Indefinite 
1986 
1988 
1987 
1987 
1998 
1986 1986 
1986 1986 
Indefinite 
(4) 2008 
1987 
Indefinite 
1987 
1987 
1985 1985 
1988 
1988 
1985 
1987 
1984 
1984 
1983 
1974 
1978 
1987 
1995 
1986 
Indefinite 
1989 
1987 
1984 
1987 
1987 
1984 
1986 
1986 
1990 
1986 
1989 
1985 
1987 
1987 
1985 
1987 
1987 
Reservoir and channel 
improvement 
Local protection 
Bridge protection 
Local protection 
Local protection 
Streambank protection 
Local protection 
Reservoir 
Reservoirs 
Streambank protection 
Local protection 
Local protection 
Reservoir 
Local protection 
Local protection 
Snagging and Clearing 
Local protection 
Streambank protection 
Streambank protection 
Shoreline protection 
Local protection 
Snagging and Clearing 
Streambank protection 
Streambank protection 
Reservior 
Local protection 
Local protection 
Streambank protection 
Reservoirs 
Streambank protection 
Local protection 
Local protection 
Streambank protection 
Local protection 
Streambank protection 
Streambank protection 
Local protection 
Main Line Levees 
Streambank protection 
Local protection 
Local protection 
Streambank protection 
Streambank protection 
Local protection 
Major rehabilitation 
Modernization of Dams 
Local protection (hurricane) 
Local protection 
Local protection 
Bank protection 
Local protection 
Streambank protection 
Shoreline protection 
Local protection 
Local protection 
Snagging and Clearing 
Reservoir 
Local protection 
Reservoirs 
Reservoir 
Local protection 
Local protection 
Local protection 
Local protection 
Streambank protection 
B-3

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1986 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Perry County L & D Nos. 1, 2, 3, MO ............................... 
Phoenix, AZ, and Vicinity (including New River) .................... 
Platte River, Ashland, NE (Sec 14) ................ .............. 
Platte River, Brady, NE (Sec 14) ................................... 
Platte River, Hanson Lake, NE (Sec 14) ............................ 
Pleasant Point, Perry, ME (Sec 14) ................ .............. 
Plum Creek, Penn Hills, PA (Sec 14) ................ ............. 
Point Place, OH ................ . .................. ........... 
Porter Bayou, MS (Sec 205) ................ .................... 
Portugues and Bucana Rivers, PR ................ .............. 
Prairie Du Chien, WI .......................................... 
Presque Isle Peninsula, PA ....................................... 
Pt. Leflore, M S ................ ................... ............ 
R. D. Bailey Lake, W V........... ................................ 
Rapidan River, Orange, VA (Sec 14) ........................... 
Raritan Bay and Sandy Hook Bay, NJ, Matawan and Union 
Beach Sections ................ . . . ................. .......... 
Ray Roberts Lake, TX ......................................... 
Redbird Creek, Holt Co., NE (Sec 14) ................................ 
Red River below Denison Dam, TX ................ ............. 
Red River Emergency Bank Protection ......................... 
Red River of the North at Argusville, ND (Sec 205) .................. 
Red River of the North at Halstad, MN (Sec 205) .... ................ 
Roberto Clemente Park, Pittsburgh, PA (Sec 14) .................... 
Rockford, IL (Kent Creek) ................ ..................... 
Root Creek, Bolivar, NY (Sec 205).................. ............... 
Sacramento River Bank Protection, CA .......................... 
Sacramento River, Chico Landing to Red Bluff, CA .................. 
Sacramento River Flood Control, CA ................ ............ 
Sacramento River, Major and Minor Tributaries, CA ................ 
Saginaw River, M I ................. .............................. 
Saline Co. Tuxedo Bridge, Big Blue River, NE (Sec 14) ............... 
Salt Creek, Lincoln, NE (Sec 14) ................ ................ 
San Antonio Channel Improvement, TX ......................... 
San Gabriel River, TX ...................................... ..... 
San Jacinto River Levee & Bautista Creek Channel, CA .............. 
Sandy Creek, Jackson, TN (Sec 14) ................ . ............. 
Sardis Lake, OK ...................................... 
Saxis Island, Accomack Cnty, VA . . ................. ............ 
Saylorville Lake, IA ............... ............... .............. 
Scotts Creek, Newberry, SC (Sec 205) ................ ........... 
Scottsville, VA ..................... .. ........................ 
Seneca River, Sewage Treatment Plant, Seneca Falls, NY (Sec 14) ..... 
Sheyenne River, Valley City, ND (Sec 14) ................... ....... 
Sicily Island, LA, Levee ................ . ...................... 
Siena Center, Racine, WI (Sec 14) ................ ............... 
Skiatook Lake, OK .............................................. 
Smithville Lake, MO ............................................ 
Sope Creek, Marietta, GA ................... ...................... 
Souris River, Velva, ND (Sec 14) ................ ................ 
South Creek, Martinsburg, NE (Sec 14) ................ .......... 
South Fork, Big Nemaha River, Dubois Bridge, NE (Sec 14) .......... 
South Fork, Boise River, ID (Sec 208) ............................. 
South Platte River, Goodrich, CO (Sec 14) .......................... 
South Platte River, Kersey, CO (Sec 14) ............................ 
South Platte River, Merino, CO (Sec 14) .................. ... ..... 
South Platte River, Morgan Co., CO (Sec 14) ........................ 
South Platte River, Weldona, CO (Sec 14) ............. ............. 
South River, Conway, MA (Sec 14) ................................. 
Southwestern Jefferson County, KY .............................. 
Steele Bayou, MS ............................................. 
St. Francis Basin ................................... ......... 
Stonewall Jackson Lake, WV ..................... .............. 
Stratmoor Hills, Colorado Springs, CO (Sec 14) ..................... 
Stuart, Patrick Co., VA (Sec 205) ................. .............. 
1977 
1973 
1986 
1985 
1984 
1986 
1983 
1982 
1982 
1975 
1979 
1975 
1985 
1967 
1983 
1965 
1975 
1984 
1948 
1971 
1985 
1983 
1983 
1979 
1979 
1963 
1963 
1918 
1949 
1965 
1986 
1985 
1957 
1973 
1960 
1983 
1976 
1986 
1965 
1986 
1986 
1986 
1986 
1983 
1981 
1974 
1974 
1986 
1986 
1985 
1985 
1984 
1985 
1984 
1985 
1985 
1984 
1986 
1974 
1966 
1938 
1977 
1983 
1986 
1985 
1985 
1986 
1984 
1986 
1975 
1986 
1986 
1985 
1984 
1984 
1979 
1986 
1985 
19801 
1985 
1983 
1977 
1982 
1985, 
1982 
1985 
1986 
1985 
1983 
(4) 
1984 
1985 
1991 
1987 
1986 
1986 
1987 
1984 
1987 
1985 
1993 
1986 
1989 
1986 
1986 
1987 
Indefinite 
1991 
1986 
1986 
1987 
1987 
1986 
1984 
1988 
1984 
1991 
Indefinite 
1989 
1988 
1992 
1986 
1986 
1991 
19842 
1985 
1984 
1986 
1987 
Indefinite 
1987 
1988 
1987 
1987 
2010 
1982 
1986 
1986 
1987 
1987 
1987 
1985 
1985 
1987 
1986 
1986 
1987 
1987 
1987 
1989 
1995 
1999 
1988 
1984 
1987 
Local protection 
Local protection 
Streambank protection 
Streambank protection 
Streambank protection 
Streambank protection 
Streambank protection 
Local protection 
Local protection 
Local protection 
Non-structural local protection 
Beach replenishment 
Streambank protection 
Reservoir 
Streambank Erosion 
Local protection 
Reservoir 
Streambank protection 
Local protection 
Streambank protection 
Local protection 
Local protection 
Streambank protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Local protection 
Streambank protection 
Streambank protection 
Local protection 
Reservoir 
Local protection 
Streambank protection 
Reservoir 
Streambank protection 
Reservoir 
Local protection 
Local protection 
Streambank protection 
Streambank protection 
Local protection 
Local protection 
Reservoir 
Reservoir 
Local protection 
Streambank protection 
Streambank protection 
Streambank protection 
Snagging and Clearing 
Streambank protection 
Streambank protection 
Streambank protection 
Streambank protection 
Streambank protection 
Streambank protection 
Local protection 
Local protection 
Tributary levees & channels 
Reservoir 
Streambank protection 
Local protection 
B-4

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1986 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Swan Creek, Taney County, MO (Sec 14) ................ ......... 
Sweetwater River, CA ................. . .................. ...... 
Tallabinella Creek, Chickasaw Co., MS ............................. 
Taylors Bayou, TX ................... ........................... 
Taylorsville Lake, KY ............................................ 
Tennessee River (Mile 254) City Duck, Sheffield, AL ................. 
Tennessee River (Mile 67.0) Paris Landing State Park, TN ............ 
Tennessee River (Mile 650) Downtown Is. Airport, TN ............... 
Tensas Cocodrie Pumping Plant, LA 11 ... ....................... 
Texas City and Vicinity, TX (1958 authorization) .................... 
Tombigbee River, Hwy. 39 Bridge, Gainesville, AL ................. 
Tombigbee River Tributaries, AL and MS .......................... 
Trout Run, Portage Borough, PA (Sec 14) ........................ 
Truchas Creek, Ft Summer, NM (Sec 14) ......................... 
Turner Creek, Corinth, MS ..................................... 
Twenty-mile Creek, Airport Rd., Prentiss County, MS (Sec 14) ........ 
Tynes Branch, Houston School Road Bridge, Itawamba Co., MS ...... 
Upper Scioto River, Marion County, OH (Sec 205) ................... 
Upper Yazoo Projects, MS ................ ..................... 
U.S. Hwy. 11 Bridge, Fosters, AL (Sec 14) ....................... 
U.S. Hwy. 82 Bridge, Columbus, MS (Sec 14) ..................... 
U.S. Interstate 59 Bridges, Fosters, AL (Sec 14) .................... 
Valley Creek, AL (Sec 14) ..................................... 
Vermillion River, Vermillion, SD (Sec 14) ..................... 
Vermillion River, WWTP, SD (Sec 14) ................ ........... 
Vince and Little Vince Bayous, TX ................................. 
Walnut Creek, CA ............... .................. 
Warner Road, Mississippi River, St. Paul, MN (Sec 14) ............... 
W aterloo, IA ...................................... ........... 
Webster Co. Bridge 14710, Beaver Creek, NE (Sec 14) ................ 
Webster Co. Bridge 23015, Elm Creek, NE (Sec 14) .................. 
Webster Co. Bridge 23025, Beaver Creek, NE (Sec 14) ................ 
Webster Co. Bridge 33425, Elm Creek, NE (Sec 14) .............. 
Webster Co. Bridge 43430, Beaver Creek, NE (Sec 14) ................ 
West Magnesia Canyon Channel, CA (Sec 205) .................... 
West Makinster Road, Wilson River, OR (Sec 14) .................... 
West Papillion Creek, Douglas Co., NE (Sec 14) ................... 
West Tennessee Tributaries .................................... 
Wheeler Creek, Gainesville, TX (Sec 205) ................... ....... 
White River, Batesville, AR (Sec 14) ................................ 
White River, Jacksonport, AR (Sec 205) ........................... 
Wigle Creek, Homer, NE (Sec 14). . .......... ......... ......... 
Wildcat and San Pablo Creeks, CA .......... ...................... 
Wild Rice River, Mahnomen County, MN (Sec 14) .................. 
Willamette River Basin Bank Protection, OR .................. 
William H. Harsha Lake, OH ................ ................... 
Winona, MN....... ............... ................... 
Wolf Cr., Hwy 45, Prentiss Co, MS (Sec 14) . ........................ 
Wood River Drainage and Levee District, IL ........................ 
Wyoming Valley, PA ............................................. 
Yatesville Lake, KY .............................................. 
Yonkers, NY ................ ... ................. .............. 
Zoological Gardens, Racine, WI .................... ............. 
1984 
1984 
1986 
1982 
1974 
1986 
1986 
1986 
1983 
1962 
1986 
1965 
1984 
1983 
1986 
1984 
1986 
1986 
1976 
1985 
1985 
1985 
1985 
1985 
1985 
1968 
1964 
1986 
1973 
1986 
1986 
1986 
1986 
1986 
1985 
1985 
1985 
1960 
1983 
1984 
1984 
1985 
1986 
1985 
1938 
1970 
1979 
1984 
1953 
1983 
1964 
1975 
1983 
1986 
1983 
1984 
1984 
1987 
1985 
1985 
1986 
1986 
1986 
1986 
1986 
1986 
1986 
1986 
1986 
(4) 
1984 
1986 
1986 
1986 
1986 
1978 
1985 
1962 
1976 
1984 
1986 
1988 
1987 
1992 
1989 
1987 
1987 
1987 
1987 
1987 
1988 
Indefinite 
1984 
1984 
1987 
1985 
1987 
1987 
2013 
1986 
1985 
1986 
1986 
1986 
1986 
1988 
1990 
1986 
1986 
1986 
1986 
1986 
1986 
1986 
1987 
1986 
1986 
2003 
1984 
1986 
1986 
1986 
1990 
1986 
Indefinite 
1987 
1987 
1985 
1986 
1986 
Not scheduled 
1985 
1984 
Streambank protection 
Local protection 
Bridge protection 
Local protection 
Reservoir 
Streambank protection 
Streambank protection 
Streambank protection 
Local protection 
Local protection 
Riverbank protection 
Local protection 
Streambank protection 
Streambank protection 
Bank protection 
Streambank protection 
Bridge protection 
Local protection 
Local protection 
Streambank protection 
Streambank protection 
Streambank protection 
Sewerline protection 
Streambank protection 
Streambank protection 
Local protection 
Local protection 
Streambank protection 
Local protection 
Streambank protection 
Streambank protection 
Streambank protection 
Streambank protection 
Streambank protection 
Local protection 
Streambank protection 
Streambank protection 
Tributary channels 
Local protection 
Local protection 
Local protection 
Streambank protection 
Local protection 
Streambank protection 
Local protection 
Reservoir 
Local protection 
Streambank protection 
Local protection 
Rehabilitation of levee system 
Reservoir 
Local protection 
Shoreline protection 
1 Granger Dam & Lake Georgetown - complete FY 83 
2 South Fork - Construction deferred indefinitely, work on Reevaluation Report only 
3 Completion of Stage I (Truscott facilities) only. Stage II (Ross facilities) indefinite 
4 Project was in useful operation before Corps started working on it. Work consists primarily of improvements to existing local interest 
channel and levees. 
B-5

APPENDIX C 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1986 
Locks Dams Authorized Channel 
Lift at 
Miles Width Available Normal Depth on Sills 
Above Community of Length for Pool Length Year Length Depth Width 
Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) 
Alabama-Coosa Rivers, AL 
Claiborne Lock and Dam 
Millers Ferry Lock and 
Dam 
Jones Bluff Lock and Dam 
Allegheny River, PA and NY 
Lock and Dam No. 2 
Lock and Dam No. 3 
Lock and Dam No. 4 
Lock and Dam No. 5 
Lock and Dam No. 6 
Lock and Dam No. 7 
Lock and Dam No. 8 
Lock and Dam No. 9 
- Apalachicola, Chattahoochee, 
and Flint Rivers, GA, AL 
and FL 
Jim Woodruff Lock 
and Dam 
George W. Andrews 
Lock and Dam 
Walter F. George 
Lock and Dam 
Atlantic Intracoastal 
Waterway 
Albemarle and Chesapeake 
Canal Route: 
Great Bridge Lock 
Dismal Swamp Canal 
Route: 
Deep Creek Lock 
South Mills Lock 
Bayou Teche, LA 
Berwick Lock 
Keystone Lock 
Black Rock Channel and 
Tonawanda Harbor, NY 
Black Rock Lock 
Black Warrior, Warrior 
and Tombigbee Rivers, AL 
Coffeeville (Jackson) 
Lock and Dam 
Demopolis Lock and Dam 
Armistead I. Selden Lock 
and Dam 
Wm. Bacon Oliver 
Lock and Dam 
Holt Lock and Dam 
John Hollis Bankhead 
Lock and Dam (new lock) 
Canaveral Harbor, FL 
Canaveral Lock 
Cape Fear River, NC 
Lock and Dam No. 1 
Lock and Dam No. 2 
William O. Huske 
Lock and Dam 
Central and Southern Florida 
S561 Lock 
S-65 Lock 
S-65A Lock 
S-65B Lock 
S-65C Lock 
S-65D Lock 
S-65E Lock 
S-308B 
S-310 
Chicago Harbor, IL 
Chicago Lock 
Columbia River, OR and WA 
Bonneville Lock and Dam 
The Dalles Lock and Dam 
John Day Lock and Dam 
McNary Lock and Dam 
Cross-Florida Barge Canal 
Inglis Lock, Dam 
and Spillway 
Eureka Lock and Dam 
Harry H. Buckman Lock 
81.82 Claiborne, AL 
142.32 Camden, AL 
254.42 Benton, AL 
6.7 Aspinwall, PA 
14.5 Cheswick, PA 
24.2 Natrona, PA 
30.4 Freeport, PA 
36.3 Clinton, PA 
45.7 Kittanning, PA 
52.6 Templeton, PA 
62.2 Rimer, PA 
107.6' Chattahoochee, FL 
154.3' Columbia, GA 
182.86 Fort Gaines, GA 
11.5' Great Bridge, VA 
10.6* Deep Creek, VA 
33.2' South Mills, NC 
1.5' Berwick, LA 
72.5' New Iberia, LA 
0.0 Buffalo, NY 
116.61� Coffeeville, AL 
213.2 
'0 
Demopolis, AL 
261.1 
'0 
Eutaw, AL 
338.1'0 Tuscaloosa, AL 
347.0 
'0 
Holt, AL 
365.1'� Adger, AL 
2.7 Cocoa, FL 
67.0 Kings Bluff, NC 
99.0 Browns Landing, NC 
123.0 Tolars Landing, NC 
0.0 St. Cloud, FL 
56.0 Frostproof, FL 
46.0 Avon Park, FL 
32.0 Sebring, FL 
25.0 Sebring, FL 
16.0 Okeechobee, FL 
12.0 Okeechobee, FL 
38.7 Port Mayaca, FL 
0.0 Clewston, FL 
0.0 Chicago, IL 
146.0 Bonneville, OR 
190.0 The Dalles, OR 
215.0 Rufus, OR 
292.0 Umatilla, OR 
168.6" Inglis, FL 
20.0 Sparr, FL 
90.4 Palatka, FL 
84 
84 
84 
56 
56 
56 
56 
56 
56 
56 
56 
82 
82 
82 
600 
600 
600 
360 
- 360 
360 
360 
360 
360 
360 
360 
450 
450 
450 
30 
45 
45 
11 
13 
10 
12 
12 
13 
18 
22 
33 
25 
88 
16 
16 
16 
11 
12
9 
10 
11 
11 
14 
11 
14 
19 
18 
13 
13 
13 
12 
11 
10 
11 
11 
10 
10 
11 
14 
13 
13 
Movable 
Movable 
Movable 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Movable 
Movable 
Movable 
3,160' 
9,900' 
14,9623 
1,393 
1,436 
876 
780 
1,140 
916 
984 
950 
5,924 
620 
13,371 
72 530 3 167 16' None 
52 300 12 12' 12' None 
52 300 12 12' 12' None 
45 307 75 97 
36 162 9 9 
9' None 
8 Fixed 
1973 60.5 
1969 103.1 
1974 88.0 
193420 
193420 
1927 
1927 
1928 
1930 
1931 
1938 
1957 
1963 
1963 
1932 
1940 
1941 
1950 
175 1913 
68 625 5 21.6 21.6 None 
110 
110 
110 
95 
110 
110 
600 
600 
600 
460 
600 
600 
33 
40 
22 
28 
64 
68 
13 
13 
13 
12 
19 
13 
13 
13 
13 
12 
13 
13 
Movable 
Fixed 
Movable 
Fixed 
Movable 
Fixed 
200 
200 
200 
200 
200 
200 
200 
200 
200 
200 
200 
100 
100 
100 
7.8 
9.7 
6.2 
5.9 
9.4 
6.9 
9.6 
9.8 
46.7 
28.5 
85.0 
12 90 
6 50 
6 50 
8 80 
34.5 6 80 
1914 7.1 21 200 
1,185 
1,485 
1,832 
700 
1,138 
1,170 
90 600 3 14 14 None 
40 
40 
40 
30 
30 
30 
30 
30 
30 
30 
56 
50 
200 
200 
300 
90 
90 
90 
90 
90 
90 
90 
400 
60 
11 
9
9
2
666 
7
65 
14 
5 
9 
12
9
66
666
66 
14 
13 
80 600 4 23 
76 
86 
86 
86 
84 
84 
84 
500 
675 
675 
675 
600 
600 
600 
C-1 
65 
88 
110 
75 
28 
20 
20 
32 
15 
15 
15 
18 
14 
14 
9 
12
9
6
6666
66 
14 
13 
Fixed 
Fixed 
Fixed 
275 
229 
220 
None 
None 
None 
None 
None 
None 
None 
Movable 
Movable 
23 None 
24 
15 
15 
20 
15 
15 
Movable 
Movable 
Movable 
Movable 
Movable 
Movable 
None 
1965 
1962 
1962 
1940 
1969 
1975 
1965 
1915 
1917 
1935 
1963 
1964 
1967 
1965 
1965 
1964 
1964 
1977 
1980 
96.6 
47.9 
77.0 
8.9 
18.1 
42.7 
32.0 
24.0 
20.0 
28.0 
10.0 
14.0 
7.0 
9.0 
4.0 
5.0 
.5 
200 
200 
200 
200 
200 
200 
12 125 
100 
100 
100 
20 
30 
30 
30 
30 
30 
30 
100 
50 
1939 .15 21 470 
2,680 1938 
8,735 1957 
5,900 1968 
7,365 1953 
5,100 1968 
3,830 1971 
1972 
47.5 27 
25.0 14 
76.0 14 
64.0 14 
11.0 12 
12 
21.2 12 
300 
250 
250 
250 
150 
150 
150

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1986 
Locks Dams Authorized Channel 
Lift at 
Miles Width Available Normal Depth on Sills 
Above Community of Length for Pool Length Year Length Depth Width 
Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) 
Cumberland River, KY 
and TN 
Barkley Dam 30.6 Kuttawa, KY 
Cheatham Lock and Dam 148.7 Ashland City, TN 
Old Hickory Lock and Dam 216.2 Old Hickory, TN 
Cordell Hull Dam 
and Reservoir 313.5 Carthage, TN 
Fox River, WI 
DePere Lock 7.1 DePere, WI 
DePere Dam 7.2 DePere, WI 
Little Kaukauna Lock 13.0 DePere, WI 
Little Kaukauna Dam 13.1 DePere, WI 
Rapide Croche Lock 19.2 Wrightstown, WI 
Rapide Croche Dam 19.3 Wrightstown, WI 
Kaukauna Fifth Lock 22.8 Kaukauna, WI 
Kaukauna Fourth Lock 23.1 Kaukauna, WI 
Kaukauna Third Lock 23.3 Kaukauna, WI 
Kaukauna Second Lock 23.4 Kaukauna, WI 
Kaukauna First Lock 23.6 Kaukauna, WI 
Kaukauna Dam 24.0 Kaukauna, WI 
Kaukauna Guard Lock 24.0 Kaukauna, WI 
Little Chute combined Lock 
Lower 25.4 Little Chute, WI 
Upper 25.4 Little Chute, WI 
Little Chute Second Lock 26.4 Little Chute, WI 
Little Chute First 
(Guard) Lock 26.5 Little Chute, WI 
Little Chute Dam 26.6 Little Chute, WI 
Cedars Lock 27.3 Little Chute, WI 
Cedars Dam 27.4 Little Chute, WI 
Appleton Fourth Lock 30.7 Appleton, WI 
Appleton Lower Dam 30.9 Appleton, WI 
Appleton Third Lock 31.3 Appleton, WI 
Appleton Second Lock 31.6 Appleton, WI 
Appleton First Lock 31.9 Appleton, WI 
Appleton Upper Dam 32.2 Appleton, WI 
Menasha Lock 37.8 Menasha, WI 
Menasha Dam 37.8 Menasha, WI 
Freshwater Bayou, LA 
Freshwater Bayou Lock 19.08 Intracoastal City, LA 
Green and Barren Rivers, KY 
Green River: 
Lock and Dam No. 1 9.1 Spottsville, KY 
Lock and Dam No. 2 63.1 Calhoun, KY 
Gulf Intracoastal Waterway 
Inner Harbor Navigation 
Channel Lock 92.612 New Orleans, LA 
Harvey Lock 98.312 Harvey, LA 
Algiers Lock 88.012 Algiers, LA 
Bayou Boeuf Lock 93.3 Morgan City, LA 
Bayou Sorrel Lock 131.013 Plaquemine, LA 
Port Allen Lock 228.512 Port Allen, LA 
Vermilion Lock 162.713 Abbeville, LA 
Calcasieu Lock 238.513 Lake Charles, LA 
Brazos River Floodgates 404.1'13 Freeport, TX 
Colorado River 
East Lock 444.8 Matagorda, TX 
West Lock 444.8 Matagorda, TX 
Hudson River, NY 
Troy Lock and Dam 153.8 Troy, NY 
Illinois Waterway, IL 
LaGrange Lock and Dam 80.2 Beardstown, IL 
Peoria Lock and Dam 157.7 Peoria, IL 
Starved Rock Lock 
and Dam 231.0 -Utica, IL 
Marseilles Lock 244.6 Marseilles, IL 
Marseilles Dam 247.0 Marseilles, IL 
Dresden Island 
Lock and Dam 271.5 Morris, IL 
Brandon Road Lock 
and Dam 286.0 Joliet, I1 
Lockport Lock 291.1 Lockport, IL 
Thomas J. O'Brien 
Lock and Dam 326.5 Chicago, IL 
Inland Route, MI 
Crooked River 
Lock and Weir 30.0 Alanson, MI 
110 
110 
84 
84 
36 
36 
36 
36 
37 
31 
35 
35 
40 
35 
36 
35 
35 
35 
35 
35 
35 
34 
34 
800 
800 
400 
400 
146 
146 
146 
144 
144 
144 
144 
144 
147 
144 
144 
144 
144 
144 
145 
145 
144 
57 
26 
60 
59
9
7
8
9 
10 
10 
10 
11 
9 
11 
11 
14
7 
10
8
9 
10 
10
8 
84 600 
11 
14 
14 
14 
10
8
9
77767 
688 
7
8
677 
7 
13 Movable 
12 Movable 
10 Movable 
13 Movable 
12 
10 
10
96
666 
9
66 
7
8
966 
8 
16 16 None 
84 600 12 12 11 Fixed 
84 600 14 15 12 Fixed 
75 
75 
75 
75 
56 
84 
56 
75 
75 
640 
425 
797 
1,158 
800 
1,198 
1,200 
1,205 
9' 
10' 
10' 
6' 
10' 
45
3' 
6' 
75 1,200 
75 1,200 
317 
12' 
137 
13' 
14' 
137 
11' 
13' 
15' 
31' None 
12' None 
13' None 
137 None 
14' None 
14' None 
11' None 
13' None 
15' None 
5' 15' 157 None 
5' 15' 15' None 
9,959 1964 
801 1959 
3,605 1957 
1,138 1973 
1936 
Movable 986 1929 
1938 
Movable 588 1926 
1934 
Movable 461 1930 
1898 
1879 
1879 
1903 
1883 
Movable 603 1931 
1891 
1879 
1879 
1881 
1904 
Movable 562 1932 
1888 
Movable 654 1933 
1907 
Movable 549 1934 
1900 
1901 
1884 
Movable 691 1940 
1899 
Movable 401 1937 
118.1 9 
67.5 9 
97.3 9 
71.9 9 
5.9 
6.2 
3.6 
0.3 
0.2 
0.1 
0.2 
0.4 
1.4 
1.0 
0.7 
3.4 
0.6 
0.3 
0.3 
5.1 
28.3 
401 1968 
482 1956 54.0 9 200 
519 1956 45.4 9 200 
1923 
1935 
1956 
1956 
1952 
1961 
1934 
1950 
1943 
1954 
1954 
45 493 17 16 13 Fixed 1,495 1917 2.2 14 200 
110 
110 
110 
110 
110 
110 
110 
110 
600 
600 
600 
600 
600 
600 
600 
1,000 
10 
11 
19 
24 
22 
34 
40
2 
16 
16 
17 
19 
17 
18 
12 
14 
13 Movable 
12 Movable 
14 Movable 
14 
Movable 
12 Movable 
14 Movable 
15 None 
14 Movable 
1,066 1939 
536 1939 
1,280 1933 
1933 
819 1933 
1,616 1933 
2,373 1933 
1933 
257 1960 
77.5 9 
73.3 9 
13.6 9 
26.9 9 
24.6 
14.5 9 
5.1 99 
6.9 9 
17.8 66 1 6.9 7.9 SSP Weir 83 1967 4.0 5 30 
C-2 
150 
150 
150 
150 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
12 125 
12 
12 
16 
16 
12 
12 
16 
16 
12 
150 
125 
150 
150 
125 
125 
200 
200 
125 
12 125 
12 125 
300 
300 
300 
300 
300 
300 
300 
300

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1985 
Locks Dams Authorized Channel 
Lift at 
Miles Width Available Normal Depth on Sills 
Above Community of Length for Pool Length Year Length Depth Width 
Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) 
Kanawha River, WV 
Winfield Lock and Dam 
Marmet Lock and Dam 
London Lock and Dam 
Kaskaskia River, IL 
Kaskaskia Lock and Dam 
Kentucky River, KY 
Lock and Dam No. 1 
Lock and Dam No. 2 
Lock and Dam No. 3 
Lock and Dam No. 4 
Lock and Dam No. 524 
Lock and Dam No. 624 
Lock and Dam No. 724 
Lock and Dam No. 824 
Lock and Dam No. 924 
Lock and Dam No. 1024 
Lock and Dam No. 1124 
Lock and'Dam No. 1224 
Lock and Dam No. 1324 
Lock and Dam No. 1424 
Lake Washington Ship Canal 
Hiram M. Chittenden Lock 
Large Lock 
Small Lock 
McClellan-Kerr Arkansas 
River Navigation System, 
AR and OK 
Norrell Lock and Dam 
Lock No. 2 
Dam No. 2 
Lock and Dam No. 3 
Lock and Dam No. 4 
Lock and Dam No. 5 
David D. Terry Lock 
and Dam 
Murray Lock and Dam 
Toad Suck Ferry Lock 
and Dam 
Lock and Dam No. 9 
Dardanelle Lock and Dam 
Ozark-Jetta Taylor Lock 
and Dam 
Lock and Dam No. 13 
W. D. Mayo Lock and Dam 
Robert S. Kerr Lock and 
Dam and Reservoir 
Webbers Falls Lock and 
Dam 
Chouteau Lock and Dam 
Newt Graham Lock 
and Dam 
Mississippi River 
Between Ohio and Missouri 
Rivers 
Lock and Dam No. 27 
Mississippi River Between 
Missouri River and 
Minneapolis, MN 
Lock and Dam No. 26 
Lock and Dam No. 25 
Lock and Dam No. 24 
Lock and Dam No. 22 
Lock and Dam No. 21 
Lock and Dam No. 20 
Lock and Dam No. 19 
Lock and bam No. 18 
Lock and Dam No. 17 
Lock and Dam No. 16 
Lock and Dam No. 15 
Lock and Dam No. 14 
Lock and Dam No. 13 
Lock and Dam No. 12 
Lock and Dam No. 11 
Lock and Dam No. 10 
Lock and Dam No. 9 
Lock and Dam No. 8 
Lock and Dam No. 7 
31.1 Winfield, WV 
67.8 Marmet, WV 
82.8 London, WV 
.8 Ellis Grove, IL 
4.0 Carrolton, KY 
31.0 Lockport, KY 
42.0 Gest, KY 
65.0 Frankfort, KY 
82.2 Tyrone, KY 
96.2 High Bridge, KY 
117.0 High Bridge, KY 
139.9 Camp Nelson, KY 
157.5 Valley View, KY 
176.4 Ford, KY 
201.0 Irvine, KY 
220.9 Ravenna, KY 
239.9 Willow, KY' 
249.0 Heidelberg, KY 
1.3 Seattle, WA 
1.3 Seattle, WA 
10.3 Arkansas Post, AR 
13.3 Arkansas Post, AR 
40.5 Arkansas Post, AR 
50.2 Grady, AR 
66.0 Pine Bluff, AR 
86.3 Redfield, AR 
108.1 Little Rock, AR 
125.4 Little Rock, AR 
155.9 Conway, AR 
176.9 Morrilton, AR 
205.5 Russellville, AR 
256.8 Ozark, AR 
292.8 Fort Smith, AR 
319.6 Fort Smith, AR 
336.2 Sallisaw, OK 
366.6 Webbers Falls, OK 
401.2 Muskogee, OK 
421.4 Inola, OK 
185.1"4 Granite City, IL 
202.91' Alton, IL 
241.4' Cap Au Gris, MO 
273.4'" Clarksville, MO 
301.21' Saverton, MO 
324.9" Quincy, IL 
343.216 Canton, MO 
364.2" Keokuk, IA 
410.51' Burlington, IA 
437.11' New Boston, IL 
457.21" Muscatine, IA 
482.916 Rock Island, IL 
493.116 LeClaire, IA 
493.31' LeClaire, IA 
522.5'" Clinton, IA 
556.7'5 Bellevue, IA 
583.0'" Dubuque, IA 
615.1'" Guttenberg, IA 
647.9'" Lynxville, IA 
679.2" Genoa, WI 
702.5'" Dresbach, MN 
56 
56 
56 
360 
360 
360 
28 
24 
24 
18 
18 
18 
12 Movable 834 1937 36.7 9 300 
12 Movable 707 1934 15.0 9 300 
12 Movable 707 1934 7.8 9 300 
84 600 32 18 11 Movable 130 1973 35.0 9 225 
38 
38 
38 
38 
38 
52 
52 
52 
52 
52 
52 
52 
52 
52 
145 
145 
145 
145 
145 
147 
147 
146 
148 
148 
148 
148 
148 
148 
8 
14 
13 
13 
15 
14 
15 
19 
17 
17 
18 
17 
18 
17 
889 
6 
10
9 
9 
11 
11
9 
10 
10 
10
9 
15 Fixed 
6 Fixed 
7 Fixed 
6 Fixed 
6 Fixed 
6 Fixed 
7 Fixed 
6 Fixed 
7 Fixed 
6 Fixed 
6 Fixed 
6 Fixed 
6 Fixed 
6 Fixed 
80 760 26 33.5 29 Movable 
28 123 26 16 16 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
30 
20 
20 
14 
17 
18 
18 
16 
19 
54 
34 
20 
20 
48 
30 
21 
21 
16 
18 
18 
18 
18 
18 
18 
18 
18 
18 
18 
18 
14 
18 
19 
15 
15 
15 Fixed 
14 
Movable 
14 Movable 
14 Movable 
14 Movable 
14 Movable 
14 Movable 
14 Movable 
14 Movable 
14 Movable 
15 Movable 
14 Movable 
15 Movable 
14 Movable 
16 Movable 
14 Movable 
424 
400 
465 
543 
556 
413 
350 
257 
362 
472 
208 
240 
248 
248 
1839 
1939 
1844 
1844 
1844 
1891 
1897 
1900 
1907 
1907 
1906 
1910 
1915 
1917 
235 i916 
4,677 
42,073 
6,110 
5,745 
7,455 
8,890 
3,930 
1,580 
1,505 
1,815 
2,480 
4,725 
7,400 
7,230 
4,370 
11,490 
14 Movable 1,629 
1967 
1967 
1968 
1968 
1968 
1968 
1968 
1969 
1969 
1969 
1969 
1969 
1969 
1970 
1970 
1970 
1970 
1970 
27.0 
11.0 
23.0 
17.2 
14.0 
20.8 
22.9 
17.6 
18.9 
24.6 
19.9 
19.0 
9.1 
9.6 
17.0 34 150 
3.0 
36.9 
15.8 
20.3 
21.8 
17.3 
30.5 
21.0 
28.6 
51.3 
36.0 
26.8 
16.6 
30.4 
34.8 
20.2 
23.7 
110 1,200 21 16 15 Fixed 3,240 1953 17.8 9 200 
110 
110 
110 
110 
110 
110 
110 
110 
100 
110 
110 
110 
80 
110 
110 
110 
110 
110 
110 
110 
110 
600 
360 
600 
600 
600 
600 
600 
1,200 
600 
600 
600 
600 
360 
320 
600 
600 
600 
600 
600 
600 
600 
600 
24 
24 
15 
15 
10 
10 
10 
38 
10
89 
16 
16 
11 
11 
11
9 
11
89 
11
8 
19 
16 
19 
19 
18 
17 
15 
15 
17 
16 
17 
27 
27 
18 
21 
19 
17 
19 
15 
16 
22 
18 
10 Movable 1,725 
10 
12 Movable 1,296 
12 Movable 4,280 
14 Movable 1,024 
12 Movable 1,066 
12 Movable 2,144 
13 Fixed 4,434 
14 Movable 1,350 
13 Movable 921 
12 Movable 1,099 
11 Movable 1,203 
11 
11 
14 Movable 1,343 
13 Movable 1,066 
13 Movable 849 
13 Movable 1,278 
12 Movable 763 
13 Movable 811 
14 Movable 935 
12 Movable 940 
1938 
1939 
1940 
1938 
1938 
1936 
1913 
1i37 
1939 
1937 
1934 
1922 
1939 
1939 
1938 
1937 
1937 
1937 
1937 
1937 
38.5 
32.0 
27.8 
23.7 
18.3 
21.0 
46.3 
26.6 
20.1 
25.7 
10.4 
29.2 
34.2 
26.3 
32.1 
32.8 
31.3 
23.3 
11.8 
C-3 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
250 
250 
250 
250 
250 
250 
250 
250 
250 
250 
250 
250 
250 
250 
250 
150 
150 
200 
200 
200 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS 
NS

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1986 
Locks Dams Authorized Channel 
Lift at 
Miles Width Available Normal Depth on Sills 
Above Community of Length for Pool Length Year Length Depth Width 
Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) 
Mississippi River (Continued) 
Between Missouri River 
and Minneapolis, MN 
Lock and Dam No. 6 714.315 Trempealeau, WI 
Lock and Dam No. 5A 728.515 Winona, MN 
Lock and Dam No. 5 738.115 Minneiska, MN 
Lock and Dam No. 4 752.815 Alma, WI 
Lock and Dam No. 3 796.91
' 
Red Wing, MN 
Lock and Dam No. 2 815.216 Hastings, MN 
Lock and Dam No. 1 847.6
' 
Minneapolis-St. Paul, MN 
St. Anthony Falls 
Lower Lock and Dam 853.3'" Minneapolis, MN 
Upper Lock and Dam 853.9'" Minneapolis, MN 
Monongahela River, PA 
and WV 
Locks and Dam No. 2 11.2 Braddock, PA 
Locks and Dam No. 3 23.8 Elizabeth, PA 
Locks and Dam No. 4 41.5 Monessen, PA 
Maxwell Locks and Dam 61.2 Maxwell, PA 
Locks and Dam No. 7 85.0 Greensboro, PA 
Locks and Dam No. 8 90.8 Point Marion, PA 
Morgantown Lock and Dam 102.0 Morgantown, WV 
Hildebrand Lock and Dam 108.0 Morgantown, WV 
Opekiska Lock and Dam 115.4 Morgantown, WV 
Ohio River 
Locks and Dam No. 53 18.4 Mound City, IL 
Locks and Dam No. 52 42.1 Brookport, IL 
Smithland Locks and Dam 35.3 Smithland, KY 
Uniontown Locks and Dam 135.0 Uniontown, KY 
Newburgh Locks and Dam 204.9 Newburgh, IN 
Cannelton Locks and Dam 260.3 Cannelton, IN 
McAlpine Locks and Dam 374.2 Louisville, KY 
Markland Locks and Dam 449.5 Markland, IN 
Captain Anthony Meldahl 
Locks and Dam 544.8 Chilo, OH 
Greenup Locks and Dam 640.0 Greenup, KY 
Gallipolis Locks and Dam 701.8 Hogsett, WV 
Racine Locks and Dam 743.5 Letart Falls, OH 
Belleville Locks and Dam 777.1 Reedsville, OH 
Willow Island Locks 
and Dam 819.3 Waverly, WV 
Hannibal Locks and Dam 854.6 New Martinsville, WV 
Pike Island Locks and Dam 896.7 Warwood, WV 
New Cumberland Locks 
and Dam 926.6 Stratton, OH 
Montgomery Island Locks 
and Dam 949.3 Industry, PA 
Dashields Locks and Dam 967.7 Glenwillard, PA 
Emsworth" Locks and Dam 974.8 Emsworth, PA 
Okeechobee Waterway, FL 
St. Lucie Lock and Dam 
Moore Haven Lock 
Ortona Lock and Dam 
W. P. Franklin Lock and 
Control Structure 
15.1 Stuart, FL 
78.0 Moore Haven, FL 
93.6 LaBelle, FL 
121.4 Fort Myers, FL 
110 
110 
110 
110 
110 
110 
56 
56 
600 
600 
600 
600 
600 
600 
500 
400 
400 
7 17 13 Movable 
6 18 13 Movable 
9 18 12 Movable 
7 17 13 Movable 
8 17 14 Movable 
12 22 13 Movable 
12 16 15 
38 13 8 Fixed 
38 13 10 
56 400 25 14 10 Movable 
56 400 49 16 14 Fixed 
56 
110 
56 
56 
56 
56 
84 
84 
56 
56 
84 
84 
84 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
56 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
56 
110 
56 
110 
56 
50 
50 
50 
56 
360 
720 
360 
720 
360 
720 
720 
720 
360 
360 
600 
600 
600 
600 
1,200 
600 
1,200 
1,200 
1,200 
1,200 
600 
1,200 
600 
1,200 
600 
1,200 
600 
360 
1,200 
600 
1,200 
600 
1,200 
600 
600 
360 
1,200 
600 
1,200 
600 
1,200 
600 
1,200 
600 
1,200 
600 
1,200 
600 
600 
360 
600 
360 
600 
360 
9 16 16 Fixed 
9 16 16 
8 12 12 Fixed 
8 12 12 
17 20 11 Movable 
17 20 11 
20 21 15 Movable 
20 21 15 
15 11 10 Fixed 
19 15 10 Movable 
17 18 15 Movable 
21 14 15 Movable 
22 18 14 Movable 
12 15 10 Movable 
12 15 10 Temporary Lock 
12 15 11 Movable 
12 15 11 Temporary Lock 
22 34 12 Movable 
22 34 12 
22 34 12 Movable 
22 34 12 
16 32 16 Movable 
16 32 16 
25 38 13 Movable 
25 38 13 
37 49 12 Movable 
37 19 11 
37 19 11 
35 50 15 Movable 
35 50 15 
30 45 15 Movable 
30 45 15 
30 45 15 Movable 
30 45 15 
23 18 15 Movable 
23 18 15 
22 37 15 Movable 
22 37 15 
22 37 15 Movable 
22 37 15 
20 35 15 Movable 
20 35 15 
21 38 17 Movable 
21 38 17 
21 17 18 Movable 
21 17 18 
21 17 15 Movable 
21 17 15 
18 16 15 Movable 
18 16 15 
10 13 18 Fixed 
10 13 18 
18 17 13 Movable 
18 16 13 
250 13 14 12 Movable 
250 2 10 11 None 
250 11 12 11 Movable 
400 3 13 - Movable 
893 1936 14.2 9 NS 
682 1936 9.6 9 NS 
1,619 1935 14.7 9 NS 
1,367 1935 44.1 9 NS 
365 1938 18.3 9 NS 
822 1931 32.4 9 NS 
1948 
574 1932 5.7 9 NS 
1917 
188 1956 0.6 9 100 
3,584 1963 3.8 9 100 
748 1951 12.6 9 300 
195321 
670 1907 17.7 9 300 
190721 
535 1932 19.7 9 300 
193221 
460 1964 23.8 9 300 
1964 
610 19252' 5.8 9 300 
560 19252122 11.2 9 300 
410 1950 6.0 9 300 
530 1959 7.4 9 300 
366 1964 7.0 9 300 
3,978 1929 23.7 9 300 
1980 
3,073 1928 35.8 9 300 
1969 
3,560 1980 99.7 9 300 
3,516 1975 69.9 9 300 
2,272 1975 55.4 9 300 
1,965 1972 116.3 9 400 
8,627 1961 75.3 9 300 
1921 
1930 
1,395 1963 95.3 9 300 
1963 9 300 
1,756 1962 95.2 9 300 
1962 
1,287 1962 61.8 9 300 
1,132 1937 41.7 9 300 
1,202 1970 33.6 9 300 
1,206 1969 36.4 9 300 
1,128 1973 35.3 9 1,000 
1,098 1972 36.0 9 300 
1,306 1965 29.9 9 300 
1,315 1961 22.7 9 300 
1,379 1936 18.4 9 300 
1,585 1929 7.1 9 300 
1,717 1921 6.2 9 300 
170 1941 15.1 8 80 
1953 15.6 8 90 
104 1937 15.6 8 90 
1,150 1965 7.9 8 90 
C-4

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1986 
Locks Dams Authorized Channel 
Lift at 
Miles Width Available Normal Depth on Sills 
Above Community of Length for Pool Length Year Length Depth Width 
Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) 
Old River, LA 
Old River Lock 
Ouachita and Black Rivers, 
AR & LA 
Jonesville Lock and Dam 
(Black River) 
Columbia Lock and Dam 
(Ouachita River) 
Calion Lock 
(Ouachita River) 
Felsenthal Lock 
(Ouachita River) 
Pearl River, MS and LA 
Lock 1 
Lock 2 
Lock 3 
Red River Waterway 
Lock 1 
Sacramento River, CA 
Barge Canal Lock 
Snake River, WA 
Ice Harbor Lock and Dam 
Lower Monumental Lock 
and Dam 
Little Goose Lock and Dam 
Lower Granite Lock 
and Dam 
St. Mary's River, MI 
South Canal: 
MacArthur Lock 
Poe Lock 
North Canal: 
Davis Lock 
Sabin Lock 
Savannah River, GA 
New Savannah Bluff Lock 
and Dam 
Tennessee River, TN, AL, 
MS, and KY"
' 
Kentucky Lock and Dam 
Pickwick Landing Lock 
and Dam 
Auxiliary Lock 
Main Lock 
Waterway Connecting 
Tombigbee and Tennessee 
Rivers, AL and MS 
Gainesville Lock and Dam 
Aliceville Lock and Dam 
Columbus Lock and Dam 
Aberdeen Lock and Dam 
Lock A and Spillway 
Lock B and Spillway 
Lock C and Spillway 
Lock D and Spillway 
Lock E and Spillway 
Bay Springs Lock and Dam 
Wilson Lock and Dam 
Main Lock 
Auxiliary Lock 
General Joe Wheeler Lock 
and Dam 
Main Lock 
Auxiliary Lock 
Guntersville Lock and Dam 
Main Lock 
Auxiliary Lock 
Nickajack Lock and Dam 
Chickamauga Lock and Dam 
Watts Bar Lock and Dam 
Fort Loudon Lock and Dam 
Melton Hill Lock and Dam 
(Clinch River) 
304.0 Simmesport, LA 
25.0 Jonesville, LA 
117.2 Columbia, LA 
281.7 
226.8 
29.4" Pearl River, LA 
40.7" Bush, LA 
43.9" Sun, LA 
43.8 
42.8 West Sacramento, CA 
9.7 Pasco, WA 
41.6 Kahlotus, WA 
70.3 Starbuck, WA 
107.5 Pomeroy, WA 
47.0 Sault Ste. Marie, MI 
47.0 Sault Ste. Marie, MI 
47.0 Sault Ste. Marie, MI 
47.0 Sault Ste. Marie, MI 
187.2 Augusta, GA 
22.4 Gilbertsville, KY 
206.7 Hamburg, TN 
206.7 Hamburg, TN 
49.1 Gainesville, AL 
89.8 Aliceville, AL 
117.6 Columbus, MS 
140.4 Aberdeen, MS 
154.1 Amory, MS 
159.3 Smithville, AL 
174.0 Fulton, MS 
181.4 Fulton, MS 
189.7 Belmont, MS 
194.9 Tupelo, MS 
259.4 Florence, AL 
259.4 Florence, AL 
274.9 Florence, AL 
274.9 Florence, AL 
349.0 Guntersville, AL 
349.0 Guntersville, AL 
424.7 Chattanooga, TN 
471.0 Chattanooga, TN 
529.9 Breedenton, TN 
602.3 Lenoir City, TN 
23.1 Kingston, TN 
75 1,200 35 11 11 None 
84 
84 
84 
84 
65 
65 
65 
600 
600 
600 
600 
310 
310 
310 
30 18 
18 18 
12 18 
13 ' 18 
26.7 
15 
11 
10 
10 
10 
14 Movable 
13 Fixed 
13 Movable 
13 Movable 
1963 
450 1972 
400 1972 
350 1984 
350 1984 
10 None 
10 None 
10 None 
84 685 36 22 13 Fixed 
86 600 4 13 13 None 
86 
86 
86 
86 
80 
110 
80 
80 
675 
675 
675 
675 
100 
98 
98 
100 
800 22 
1,200 22 
1,350 22 
1,350 22 
15 
15 
15 
15 
31 
32 
24 
24 
15 Movable 
15 Movable 
15 Movable 
15 Movable 
31 None 
32 None 
23 None 
23 None 
1951 
1951 
1951 
12 125 
92.2 
106.2 
50.3 
55.2 
11.1 
3.2 
13.2 
9
9
9 
9
7
77 
100 
100 
100 
100 
80 
80 
80 
550 1984 44.2 9 200 
1961 1.5 13 120 
2,790 1962 
3,800 1969 
2,670 1970 
3,200 1975 
31.9 
28.7 
37.2 
32.0 
1943 
1968 
1914 
1919 
14 
14 
14 
14 
27 
250 
250 
250 
250 
56 360 15 14 12 Movable 360 1936 16.2 9 90 
110 600 56 11 13 Tainter 7,976 1944 184.3 9 300 
110 600 55 10 13 Bulkhead 7,385 1937 52.7 9 300 
110 1,000 55 10 13 Bulkhead 7,385 1984 52.7 9 300 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
60 
110 
60 
110 
60 
110 
60 
60 
60 
75 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
292 
600 
400 
600 
400 
600 
360 
360 
360 
400 
36 
27 
27 
27 
30 
25 
25 
30 
30 
84 
94 
94 
48 
48 
39 
39 
39 
49 
58 
72 
54 
15 
15 
15 
15 
15 
18 
18 
18 
18 
18 
13 
11 
13 
15 
13 
13 
13 
10 
12 
12 
13 
15 Movable 
15 Movable 
15 Movable 
15 Movable 
15 Movable 
18 Movable 
18 Movable 
18 Movable 
18 Movable 
18 None 
13 Bulkhead 
11 Bulkhead 
13 Bulkhead 
13 Bulkhead 
13 Tainter 
12 Tainter 
11 Tainter 
14 Tainter 
12 Tainter 
12 Tainter 
13 Tainter 
15,460 1978 
14,790 1979 
10,040 1981 
10,640 1984 
- 1985 
- 1985 
- 1985 
- 1985 
- 1985 
10,640 1985 
3,728 1959 
3,728 1927 
5,738 1963 
5,738 1962 
3,837 1965 
3,837 1939 
3,763 1967 
5,654 1940 
2,646 1942 
3,687 1943 
1,072 1963 
49.1 
40.7 
27.8 
22.8 
13.7 
14.7 
7.4 
8.3 
5.2 
64.5 
15.5 
15.5 
74.1 
74.1 
75.7 
75.7 
46.3 
58.9 
72.4 
49.8 
38.2 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300 
300" 
C-5

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1986 
Locks Dams Authorized Channel 
Lift at 
Miles Width Available Normal Depth on Sills 
Above Community of Length for Pool Length Year Length Depth Width 
Project Mouth In Vicinity Chamber Full Width Level Upper Lower Type' (feet) Opened (miles) (feet) (feet) 
Willamette River at 
Willamette Falls, OR 
Lock No. 1 26.0 Oregon City, OR 40 210 20 6 8 None 1872 6 150 
Lock No. 2 26.0 Oregon City, OR 40 .210 10 6 8 None 1872 
Lock No. 3 26.0 Oregon City, OR 40 210 10 6 8 None 1872 
Lock No. 4 26.0 Oregon City, OR 40 210 10 6 8 None 1872 .4 
Guard Lock 26.4 Oregon City, OR 40 210 10 6 8 None 1872 23.6 6 NS 
' Fixed: crest without gates or other facility to control streamflow. Movable: includes any type of crest gates, tainter gates, wickets, or others to control streamflow. 
2 Above mouth of Mobile River. 
3 Includes length of earth dikes. 
4 From mouth of Apalachicola River. 
" From mouth of Chattahoochee River. 
SAbove Norfolk, VA. 
7 With reference to mean low water, or low mean Gulf as case may be. 
" From Gulf Intracoastal Waterway. 
' Average high and low water conditions, lift varying widely, depending on tides and river stages. 
'o From foot of Government Street, Mobile, AL. 
" From mouth of St. Johns River. 
2 Above Head of Passes. 
'3 From New Orleans, LA. 
"4 Salt water barrier in down position. Will clear 15-foot vessels in normal position. 
"Above the Ohio River. 
'6 Channel completed to depth of 6.5 feet. 
"7 From mouth of West Pearl River. 
'"Tennessee River locks operated by the Corps, dams operated by the Tennessee Valley Authority. 
'300-foot width from lock to mouth of Clinch River and 175-foot width upstream from lock to Clinton, TN. 
20 Dates shown represent replacement structures. 
21 Dates shown represent reconstruction for locks and dams Nos. 2-8 inclusive. 
22 Dam was rebuilt in 1959. 
23 Old 110' X 358' lock replaced in 1957. 
24 Inoperable, caretaker status September 7, 1982. 
25 Inoperable, caretaker status October 1, 1981. 
C-6

APPENDIX D 
NAVIGATION PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1986 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
AIWW-Replacement of Federal Hwy Bridges in NC ......... 
Barbers Point Harbor, Oahu, Hawaii ........................ 
Barnegat Inlet, NJ ................. .... ................. 
Bonneville Navigation Lock, OR & WA ...................... 
Brandon Road Lock and Dam, Illinois Waterway, IL .......... 
Burns Waterway Small Boat Harbor, IN (Sec 107) ............ 
Calumet Harbor & River, IL and IN ......................... 
Calumet-Sag. Mod., Illinois Waterway, IL and IN, Part 1...... 
Cannelton Locks and Dam, Ohio River, IN and KY ........... 
Channel to Newport News, VA (1965 Mod.) .................. 
Columbia River, Ilwaco, WA (Sec 107) .. .................. 
Corpus Christi Ship Channel, TX ................ ........ 
Emsworth Locks and Dams, Ohio River, PA ................. 
Fisherman's Wharf Area, CA............................. 
Falls of the Ohio National Wildlife Conservation Area, IN and 
KY ...................................... .............. 
Gallipolis Locks and Dam, Ohio River ............. .......... 
Geneva-on-the-Lake, OH .................................. 
Herring Creek, Tall Timbers, MD ........................... 
Irondequoit Bay, NY ................ ................... 
Kalama Turning Basin, WA (Sec 107) .................. 
Kaskaskia River, IL ....................................... 
Krebs Lake, MS (Sec 107) .................................. 
Lock and Dam 26 Replacement IL and MO .................. 
Lockport Lock, Illinois Waterway, IL ....................... 
Locks and Dam 52, IL and KY ................ ............. 
Locks and Dam 53, IL and KY ................ ........... 
Lorain Small Boat Harbor, OH (Sec 107) .................... 
Lower Thorofare, Somerset County, MD .................... 
M anitowoc Harbor, W I .................................... 
Marseilles Lock and Dam, Illinois Waterway, IL ............. 
McClellan-Kerr Arkansas River Navigation System, AR ...... 
Mekoryuk, AK (Sec 107) .................................. 
Mississippi River between Ohio and Missouri Rivers .......... 
Mississippi River, Gulf Outlet, LA .... .................... 
Missouri River, Sioux City, IA to mouth .................... 
Montgomery Locks & Dams, Ohio River, PA ................. 
Mouth of Colorado River, TX (Gulf Intracoastal Waterway) ... 
Nawiliwili Harbor, Kauai, HI ................ ............ 
New York Harbor, NY and NJ .............................. 
Newburgh Locks & Dam, Ohio River, IN and KY ............. 
Norfolk Harbor Channel, VA (1965 Mod.) .................... 
Ocean City Harbor and Inlet, MD ..................... 
Ouachita and Black River, AR and LA .................... 
Port Everglades Harbor, FL ........ .;. .................... 
Port Ontario Harbor, NY .................................. 
Red River WW, Mississippi River to Shreveport, LA .......... 
Rockport Harbor, Rockport, MA (Sec 107) ................ 
R'ota Harbor, Northern Marianas (Sec 107) ................. 
Sacramento River Deep Water Ship Channel, CA ........... 
San Diego River and Mission Bay, CA .................... 
1974 
1982 
1985 
1985 
1983 
1984 
1964 
1955 
1962 
1967 
1985 
1972 
1980 
1984 
1984 
1985 
1986 
1986 
1984 
1986 
1966 
1983 
1974 
1983 
1979 
1979 
1986 
1986 
1981 
1985 
1963 
1986 
1910 
1958 
1912 
1983 
1984 
1985 
1976 
1965 
1966 
1983 
1964 
1979 
1986 
1974 
1986 
1982 
1948 
19861 Indefinite 
1985 1985 
1991 
1992 
1988 
1987 
1966 Indefinite 
1968 Indefinite 
1966 1986 
1968 Indefinite 
1986 
1986 
1974 
1983 
1984 
1968 
1980 
Incremental 
1969 
1967 
1936 
1984 
1985 
1986 
1986 
1990 
1985 
1987 
Indefinite 
1995 
1988 
1987 
1987 
1986 
1986 
1984 
1991 
1987 
1985 
1987 
1987 
1987 
1984 
1988 
1989 
1986 
2000 
1984 
Indefinite 
1987 
1991 
1987 
1993 
1987 
Indefinite 
1985 
1994 
1987 
1988 
Indefinite 
1987 
1985 
1994 
Indefinite 
Replacement of existing bridges 
Dredging and breakwater 
Jetty realignment and dredging 
New larger lock 
Major rehabilitation of lock and dam 
Dredging and breakwater 
Dredging and channel, widening 
and deepening 
Channel improvements and relocation 
Replacement of existing locks and 
dams 43-45 inclusive 
Deep draft channel widening and 
deepening, deferred anchorage 
construction 
Dredging, deepening channel 
Dredging 
Major rehabilitation of lock and dam 
Breakwater 
Protection of a National Natural 
Landmark 
Replacement of existing locks and 
major rehabilitation of the dam 
Breakwaters, channel excavation, 
wetland mitigation 
Beachfill, stone revetment 
Dredging and breakwater 
Turning basin 
Lock, dam and channel 
Dredging, navigation channel 
Lock and dam 
Major rehabilitation of lock 
Major rehabilitation of locks and dam 
Major rehabilitation of locks and dam 
Breakwaters 
Stone breakwater, jetty 
Dredging and breakwater 
Major rehabilitation of lock and dam 
Locks and dams 
Breakwater 
Regulating works 
Dredging and jetties 
Navigation and bank 
stabilization complete. Wildlife 
mitigation awaiting authorization 
Major rehabilitation of locks & dams 
Breakwaters, dredging, and 
recreation 
Breakwater repair 
Collection and removal of drift 
Replacement of locks and dams 
46 and 47 
Deep draft channel, deepening and 
deferred anchorage const. 
Rehabilitation of south jetty 
Replacement of six locks and dams, 
channel deepening to 9 feet and 
realignment 
Dredging 
Breakwaters, channel excavation 
Lock and dam construction. Channel 
improvement and realignment 
Channel improvement and deepening 
Dredging and breakwater 
Deep draft channel, widening 
and deepening 
Dredging and breakwater 
D-1

APPENDIX D (Continued) 
NAVIGATION PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1986 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
San Francisco Bay to Stockton, CA (John F. Baldwin and 
Stockton Ship Channels) ............ ............. 
Santa Cruz Harbor, CA. ................. ................ 
Siuslaw River and Bar, OR ......... .. .................... 
Smith Island, MD (Sec 107) ................ ............ 
Smithland Locks and Dam, IL, IN, and KY ................. 
Starved Rock Lock and Dam, Illinois Waterway, IL ......... 
Tampa Harbor, FL (Main Channel) ...................... 
Tennessee-Tombigbee Waterway, AL and MS .............. 
Uniontown Locks and Dam, Ohio River, IN and KY ......... 
1971 
1985 
1983 
1982 
1971 
1980 
1976 
1973 
1965 
1986 
1982 
1980 
1985 
1985 
1970 
Wallisville Lake, TX ................ .................. 1967 
Indefinite Deep draft channel, widening, 
deepening and dredging 
1987 Sand bypass system 
1986 Extending jetties 
1983 Channel cut with breakwater 
1987 Replacement of existing locks 
and dams 50 and 51 
1986 Major rehabilitation of lock and dam 
1987 Dredging 
1985 Dredging and locks and dams 
1986 Replacement of locks and dams 
48 and 49 
Indefinite Multipurpose lake (navigation, 
salinity control, water supply, 
fish & wildlife, & recreational) 
1 Walter Jones and Coinjock Bridges completed; the three remaining bridges have not been funded. 
D-2

APPENDIX E 
MULTIPLE-PURPOSE PROJECTS INCLUDING POWER IN OPERATION 
SEPTEMBER 30, 1986 
Flood Control 
and/or 
Total Nay. Feature 
Storage Placed Initial Existing Scheduled Ultimate 
Community in Capability in Useful Power Installation Installation Installation Project Height Length 
Project River Vicinity (acre-feet)' Operation CY In FY (KW) (KW) (KW) Functions Type
Z 
(Feet) (Feet) 
Albeni Falls, ID Pend Oreille Newport, WA 1,153,000 1952 
Allatoona Lake, GA Etowah Cartersville, GA 670,000 1950 
Barkley Dam & Cumberland Grand Rivers, 
Lake Barkley, KY KY 
& TN 2,082,000 1964 
Beaver Lake, AR White Eureka Springs, 
AR 1,952,000 1963 
Big Bend Dam (Lake 
Sharpe), SD Missouri Chamberlain, SD 1,883,000 1964 
Blakely Mountain 
Dam-Lake 
Ouachita, AR Ouachita Mt. Pine, AR 2,768,000 1953 
Bonneville L&D 
Lake Bonneville, 
OR & WA Columbia Bonneville, OR 537,000 1938 
Broken Bow Lake, OK Mountain Fork Broken Bow, OK 1,368,230 1968 
Buford Dam Lanier, GA Chattahoochee Buford, GA 2,554,000 1956 
Bull Shoals Lake, White Mountain Home, 
AR & MO AR 5,408,000 1952 
Clarence Cannon Dam Salt Perry, MO 1,428,000 1983 
Carters Dam, GA Coosawatte Carters, GA 472,756 1975 
Center Hill Lake, TN Caney Fork Lancaster, TN 2,092,000 1948 
Cheatham L&D, TN Cumberland Ashland City, TN 104,000 1952 
Chief Joseph Dam 
(Rufus Woods 
Lake), WA Columbia Bridgeport, WA 593,100 1955 
Clarks Hill Lake, GA 
& SC Savannah Augusta, GA 2,900,000 1952 
Cooper River, Charleston 
Harbor, SC Santee St. Stephen, SC 2,560,000 N/A 
Cordell Hull L&D, TN Cumberland Carthage, TN 310,900 1973 
Cougar Lake, OR S. Fork McKenzie Blue River, OR 219,000 1963 
Dale Hollow Lake, 
TN & KY Obey Celina, TN 1,706,000 1943 
Dardanelle L&D, AR Arkansas Dardanelle, AR 486,200 1969 
DeGray Lake, AR Caddo Arkadelphia, AR 831,900 1969 
Denison Dam (Lake 
Texoma), TX & OK Red Denison, TX 5,312,300 1944 
Detroit Lake, OR, 
including Big Cliff 
Lake, OR North Santiam Mill City, OR 461,000 1953 
Dworshak Dam & N. Fork, 
Reservoir, ID Cleanwater Orofino, ID 3,453,000 1972 
Eufaula Lake, OK Canadian Eufaula, OK 3,825,400 1964 
Fort Gibson Lake, OK Grand (Neosho) Ft. Gibson, OK 1,284,400 1950 
Fort Peck Lake, MT Missouri Glasgow, MT 18,909,000 1938 
Fort Randal Dam 
(Lake Francis 
Case), SD Missouri Lake Andes, SD 5,574,000 1953 
Garrison Dam (Lake 
Sakakawea), ND Missouri Riverdale, ND 24,137,000 1954 
Gavins Point Dam 
(Lewis & Clark 
Lake), SD & NE Missouri Yankton, SD 504,000 1956 
Green Peter Lake, 
OR, including 
Foster Lake, OR Middle Santiam Sweet Home, OR 491,000 1967 
Greers Ferry Lake, AR Little Red Heber Springs 2,844,000 1962 
Harry S. Truman 
Dam & Res. Osage Warsaw, MO 5,202,000 1982 
Hartwell Lake, GA 
& SC Savannah Hartwell, GA 2,842,700 1961 
Hills Creek Lake, Middle Fork 
OR Willamette Oakridge, OR 356,000 1961 
Ice Harbor L&D 
(Lake 
Sacajawea), WA Snake Pasco, WA 417,000 1962 
Jim Woodruff Dam 
(Lake Seminole), 
FL, GA & AL Appalachicola Chattahoochee, FL 367,300 1957 
John Day L&D 
(Lake Umatilla), 
OR & WA Columbia Rufus, OR 2,500,000 1968 
John H. Kerr 
Dam & 
Reservoir, NC 
& VA Roanoke Boydton, VA 2,750,300 1952 
Robert F. Henry 
L&D, AL Alabama Benton, AL 234,200 1972 
J. Percy Priest 
Dam & 
Reservoir, TN Stones Nashville, TN 652,000 1967 
1955 42,600 
1950 74,000 
1966 
1965 
1965 
130,000 
112,000 
468,000 
1956 75,000 
1938 
1970 
1957 
1953 
1985 
1975 
1951 
1958 
1956 
1953 
1985 
1974 
1964 
1949 
1965 
1972 
1945 
1954 
1973 
1964 
1953 
1944 
1954 
1956 
1,076,600 
100,000 
86,000 
340,000 
58,000 
500,000 
135,000 
36,000 
2,069,000 204,160 
s 
280,000 
84,000 
100,000 
25,000 
54,000 
124,000 
68,000 
70,000 
118,000 
400,000 
90,000 
45,000 
185,250 
320,000 
430,000 
1957 100,000 
1967 
1964 
19824 
1962 
1962 
100,000 
96,000 
160,000 
344,000 
30,000 
1962 603,000 
1957 30,000 
1969 2,160,000 
1953 204,000 
1975 68,000 
1970 28,000 
42,600 NFPR C 
74,000 FPRW C 
130,000 NPFR CE 
112,000 FPSR CE 
468,000 FPRIW E 
75,000 FPRW E 
1,076,600 NPR C 
100,000 FPWSR E 
86,000 NFPW E 
340,000 FPR C 
58,000 FNPRSW CE 
500,000 FPRW ER 
135,000 FPR CE 
36,000 NPR C 
2,273,160 PIR C 
280,000 NFPRSW CE 
84,000 PW CE 
100,000 NPR CE 
64,600 NFPRI ER 
54,000 FPR C 
124,000 NPR C 
108,000 FNPRS E 
175,000 FPSRN E 
118,000 NFPRI C 
1,060,000 PNFR C 
90,000 ENPS E 
67,500 FP CE 
185,250 NFPRIW E 
320,000 NFPRIW E 
430,000 NFPRIW E 
100,000 NFPRIW E 
100,000 PFNIR C 
96,000 FPRS C 
160,000 FPRW CE 
344,000 NFPRS CE 
30,000 NFPRI GE 
603,000 NPRI CE 
30,000 NPRW CE 
2,700,000 NPRFI CE 
204,000 FPRW CE 
68,000 NPRW CE 
28,000 FPRW CE 
E-1 
90 1,055 
190 1,250 
157 9,959 
228 2,575 
95 10,570 
235 1,100 
122 2,690 
225 2,750 
192 5,400 
258 2,256 
138 1,700 
450 1,950 
250 2,160 
75 801 
220 4,300 
200 5,680 
86 876 
93 1,306 
445 1,738 
200 1,717 
68 2,683 
243 3,400 
165 17,200 
382 1,528 
717 3,300 
114 3,200 
110 2,990 
251 21,026 
165 10,700 
210 11,300 
74 8,700 
340 1,380 
243 1,704 
96 5,000 
204 17,852 
304 2,150 
130 2,790 
67 6,150 
161 5,900 
144 22,285 
101 14,962 
147 2,716

APPENDIX E (Continued) 
MULTIPLE-PURPOSE PROJECTS INCLUDING POWER IN OPERATION 
SEPTEMBER 30, 1986 
Flood Control 
and/or 
Total Nay. Feature 
Storage Placed Initial Existing Scheduled Ultimate 
Community in Capability in Useful Power Installation Installation Installation Project Height Length 
ect River Vicinity (acre-feet)' Operation CY In FY (KW) (KW) (KW) Functions Type
2 
(Feet) (Feet) 
stone Lake, OK Arkansas Tulsa, OK 1,737,600 1964 1968 70,000 70,000 FNPWS E 121 4,600 
el River Lake, KY Laurel London, KY 435,600 1973 1978 61,000 61,000 FPRW R 282 1,420 
y Dam, Lake 
ocanusa, MT Kootenai Libby, MT 5,809,000 1972 1975 525,000 840,000 FPR C 420 3,055 
e Goose L&D 
Ike Bryan), WA Snake Starbuck, WA 565,000 1970 1970 810,000 810,000 NPRI CE 160 2,670 
Lookout Point 
Lake, 
including 
Dexter Lake, 
OR 
Lost Creek Lake, OR 
Lower Granite 
L&D, WA 
Lower 
Monumental 
L&D, WA 
McNary L&D - 
Lake Wallula, 
OR & WA 
Millers Ferry 
L&D, AL 
Narrows Dam - 
Lake Greeson, AR 
New Melones 
Lake, CA
� 
Norfolk Lake, AR 
& MO 
Oahe Dam (Lake 
Oahe), SD & ND 
Old Hickory L&D, 
TN 
Ozark-Jeta Taylor 
L&D, AR 
Philpott Lake, VA 
Robert S. Kerr 
L&D and 
Reservoir, OK 
Sam Rayburn Dam 
& Reservoir, TX 
St. Mary's River, 
MI 
Snettisham, AK
7 
Stockton Lake, MO 
Table Rock 
Lake, AR & MO 
Tenkiller Lake, OK 
The Dalles L&D 
(Lake Celilo), 
WA & OR 
Walter F. George 
L&D, GA & FL 
Webbers Falls 
L&D, OK 
West Point 
Lake, AL & GA 
Whitney Lake, TX 
Wolf Creek Dam 
(Lake 
Cumberland), KY 
483,000 1954 
465,000 1977 
484,000 1975 
Willamette 
Middle Fork, 
Willamette 
Rogue 
Snake 
Snake 
Columbia 
Alabama 
Little Missouri 
Stanislaus 
North Fork 
Missouri 
Cumberland 
Arkansas 
Roanoke 
Arkansas 
Angelina 
Great Lakes 
Speel 
Sac 
White 
Illinois 
Columbia 
Chattahoochee 
Arkansas 
Chattahoochee 
Brazos 
Cumberland Jamestown, KY 6,089,000 1950 
1955 135,000 
1977 49,000 
1975 810,000 
1969 810,000 
1954 980,000 
1970 75,000 
1950 25,500 
1979 300,000 
1944 80,550 
1962 595,000 
1957 100,000 
1973 100,000 
1954 14,000 
1971 110,000 
1966 52,000 
1952 18,400 
1973 46,700 27,000' 
1973 45,200 
1959 200,000 
1953 34,000 
1957 1,806,800 
1963 130,000 
1973 60,000 
1975 73,375 
1954 30,000 
1952 270,000 
135,000 NFPRI CE 243 3,381 
49,000 DFPISWR CE 345 3,600 
810,000 NPRIF CE 146 3,200 
810,000 NPRI CE 135 3,800 
1,625,000 NPRI CE 183 7,300 
75,000 NPRW CE 90 11,380 
25,500 FPRW C 183.5 941 
300,000 FIPRW ER 625 1,560 
163,000 FPRS C 216 2,624 
595,000 NFPRIW E 245 9,300 
100,000 NPR CE 98 3,605 
100,000 NPR C 58 2,480 
14,000 FPR C 220 892 
110,000 NPR E 75 7,230 
52,000 FPWR CE 120 19,430 
18,400 NP Control Gate 
73,700 P C' 18 338 
45,200 FPRW CE 128 5,100 
200,000 FPR CE 252 6,423 
34,000 FP E 197 3,000 
1,806,800 NPR CR 300 8,875 
130,000 NPRW CE 114 13,585 
60,000 NP E 84 4,370 
108,375 FPRW CE 97 7,250 
30,000 FPR CE 159 17,695 
270,000 FPR CE 258 5,736 
' Total of all storage functions, including inactive and dead storage to normal full pool level 
2 G: gravel; R: rock; C: concrete; E: earth 3 
Chief Joseph Additional Units & Operating Units 1-16 
4 All units are synchronized-to-line and two units have passed the pumpback test. 
However, due to damaging effects to fish, no further pumping will be done for their testing or operation until a solution to the problem is found. 
' Being operated for the Department of Interior by the Bureau of Reclamation 
7 Being operated by the Alaska Power Administration 
' Crater Lake Unit 
' Weir for Long Lake 
Nomenclature for Project Functions 
D-Debris Control P -Power 
F-Flood Control R--Public Recreation Annual Attendance exceeding 5,000 
I -Irrigation S -Water Supply 
N-Navigation W-Fish and Wildlife (Federal or State) 
E-2 
Proj 
Keys 
Laur 
Libb 
Ko 
Littl 
(La 
Lowell, OR 
Trail, OR 
Pomeroy, WA 
Kahlotus, WA 376,000 1969 
Umatilla, OR 1,550,000 1953 
Camden, AL 331,800 1969 
Murfreesboro, AR 407,900 1950 
Oakdale, CA 2,400,000 1978 
Norfolk, AR 1,983,000 1943 
Pierre, SD 23,337,000 1959 
Hendersonville, 
TN 545,000 1954 
Ozark, AR 148,400 1969 
Bassett, VA 318,500 1951 
Sallisaw, OK 525,700 1970 
Jasper, TX 3,997,600 1965 
Sault Ste. Marie, 
MI - 1855 
Juneau, AK 352,400 
Stockton, MO 1,674,000 1969 
Branson, MO 3,462,000 1958 
Gore, OK 1,230,800 1952 
The Dalles, OR 53,000 1957 
Fort Gaines, GA 934,000 1963 
Webbers Falls, OK 170,100 1970 
West Point, GA 604,500 1975 
Whitney, TX 1,999,500 1953

APPENDIX F 
MULTIPLE-PURPOSE PROJECTS INCLUDING POWER UNDER CONSTRUCTION 
SEPTEMBER 30, 1986 
Nameplate Capacity 
Fiscal Scheduled Scheduled 
Year for for Scheduled Ultimate 
Project Started Operation Completion Functions Installation Installation 
Bonneville Second Powerhouse, OR and WA ...... 1974 1981 1991 PR 558,200 558,200 
Clarence Cannon Dam, Salt River, MO............ 1966 1985 1987 FNPRSW 58,000 58,000 
Harry S. Truman Dam and Reservoir, Osage 
River, MO ................................... 1965 19821 19871 FRPW 160,000 160,000 
Nanpil River Hydropower, Pohnpei, TTPI ........ 1985 1987 1987 P 2,000 2,000 
New Melones Lake, CA2 . . . . . . . . . . . . . . . . . . . ..... 1966 1979 1988 DFIPRW 300,000 300,000 
Richard B. Russell Dam and Lake, Savannah 
River, GA and SC ............................ 1975 1985 1991 FRP 600,000 600,000 
Copper River, Charleston Hbr, SC................ 1977 1985 1986 NWD 84,000 84,000 
Snettisham, AK .............................. 1967 1989 1989 P 73,700 27,000 
1 All units are synchronized-to-line and two units have passed the pumpback test. However, due to damaging effects to fish, no 
further pumping will be done for either testing or operation until a solution to the problem is found. 
2 New Melones Lake was turned over to the Bureau of Reclamation for operation on November 20, 1979. Corps retains responsibility for 
facilities along the lower Stanislaus River. Remaining construction consists of recreation facilities and minor feature closeouts. 
KEY 
D--Redevelopment 
F -Flood Control 
I -Irrigation 
N--Navigation 
P -Power 
R -Recreation 
S -Water Supply 
W-Fish and Wildlife 
F-1

FLOOD DAMAGES SUSTAINED AND PREVENTED DURING FISCAL YEAR 1986 
Month 
Oct 85 
Oct 85 
Nov 85 
Feb 86 
May 86 
May 86 
Aug 86 
Sep 86 
Estimated Total 
OTHER MAJOR WEATHER EVENTS AND DAMAGES 
Event Number 
Tropical Cyclones 
Major Blizzard 
Major Drought 
Tornadoes 
8
1
1 
770 
Lives 
Lost 
200* 
11
0 
40-50 
Estimated Total (Exclusive of Floods) 
Damages 
Sustained 
($000) 
2,092,000* 
3,000,000 
900,000 
194* $5,000,000* 
* 62 deaths and $1,065,000,000 were flood related and included in the above table. 
G-1 
Location 
Puerto Rico 
Gulf Coast 
Appalachia 
West Coast 
Missouri 
Pennsylvania 
Wisconsin 
Middle America 
All Floods in U.S. 
Lives 
Lost 
55 
11 
63 
15
3
92 
12 
Damages 
Sustained 
($000) 
65,000 
1,000,000 
1,000,000 
450,000 
50,000 
23,000 
30,000 
3,000,000 
208 $6,000,000

DISTRIBUTION BY REGION 
FLOOD DAMAGES PREVENTED BY CORPS 
(IN THOUSANDS OF DOLLARS) 
FY 1986 10-Year Average (1976-1985) 
$000 $000 
New England 
Mid-Atlantic 
Gulf and South Atlantic 
Ohio 
Tennessee 
Great Lakes 
Upper Mississippi 
Souris-Red-Rainy 
Missouri 
Arkansas-Red-White 
Lower Mississippi 
Rio Grande 
Texas and Gulf 
Colorado 
Great Basin 
California 
Columbia-North Pacific 
Alaska 
Hawaii 
Total 
700 
357,700 
41,800 
633,600 
600 
28,100 
113,800 
19,000 
860,500 
174,700 
9,336,100 
87,100 
208,200
0 
16,300 
13,910,900 
1,521,700 
6,800 
200 
$27,317,800 
152,568.1 
405,474.6 
49,228.6 
479,068.3 
280.5 
17,453.4 
63,165.0 
11,889.7 
337,899.9 
104,561.4 
6,471,918.8 
38,845.2 
88,596.0 
39,826.0 
4,401.5 
508,145.0 
570,333.0 
3,466.8 
712.9 
$9,347,834.7 
G-2 
Region

DISTRIBUTION BY DISTRICT 
FY 86 FLOOD DAMAGES PREVENTED BY CORPS OF ENGINEERS* 
(IN THOUSANDS OF DOLLARS) 
District $000 
Vicksburg 
Memphis 
New Orleans 
St. Louis 
Kansas City 
Omaha 
Baltimore 
New York 
Norfolk 
Philadelphia 
Buffalo 
Chicago 
Detroit 
Rock Island 
St. Paul 
New England 
Alaska 
Portland 
Seattle 
Walla Walla 
Huntington 
Louisville 
Nashville 
Pittsburgh 
Pacific Ocean 
Charleston 
Jacksonville 
Mobile 
Savannah 
Wilmington 
Sacramento 
Los Angeles 
San Francisco 
Albuquerque 
Fort Worth 
Galveston 
Little Rock 
Tulsa 
Total 
672,489 
385,870 
8,277,781
0 
682,870 
177,643 
281,154 
3,383 
71,283 
1,845 
17,545 
1,000 
10,526 
104,809 
26,934 
665 
6,828 
1,483,652 
10,891 
27,116 
173,056 
70,837 
570 
389,765 
220 
157 
25,000
0
0 
16,617 
13,916,300 
1,220 
9,700 
87,641 
179,934 
28,234 
59,073 
115,162 
$27,317,770 
*Includes Corps-controlled projects and Corps-supported emergency operations. 
G-3

DISTRIBUTION BY STATE 
FY 86 FLOOD DAMAGES PREVENTED BY CORPS OF ENGINEERS* 
(IN THOUSANDS OF DOLLARS) 
State 
Alabama 
Alaska 
Arizona 
Arkansas 
California 
Colorado 
Connecticut 
Delaware 
Florida 
Georgia 
Hawaii 
Idaho 
Illinois 
Indiana 
Iowa 
Kansas 
Kentucky 
Louisiana 
Maine 
Maryland 
Massachusetts 
Michigan 
Minnesota 
Mississippi 
Missouri 
Montana 
Nebraska 
Nevada 
New Hampshire 
New Jersey 
New Mexico 
New York 
North Carolina 
North Dakota 
Ohio 
Oklahoma 
Oregon 
Pennsylvania 
Puerto Rico 
Rhode Island 
South Carolina 
South Dakota 
Tennessee 
Texas 
Utah 
Vermont 
Virginia 
Washington 
West Virginia 
Wisconsin 
Wyoming 
Total 
$000
0 
6,828
0 
466,429 
13,910,920 
502 
25
000 
220 
20,757 
68,235 
46,287 
106,878 
114,694 
16,110 
8,478,185
0 
109,102 
437 
10,411 
22,083 
360,552 
717,926 
19,531 
72,187 
14,000 
350 
121 
87,139 
80,610 
4,034 
4,324 
97,966 
61,857 
1,394,551 
224,267 
25,000
0 
157 
811 
10,749 
208,333 
2,300 
1,362 
87,703 
98,808 
354,265 
127 
10,637 
$27,317,770 
*Includes Corps-controlled projects and Corps-supported emergency operations. 
G-4

FY 86 FLOOD DAMAGES INCURRED 
Property 
State ($000) 
Alabama 
Alaska 
Arizona 
Arkansas 
California 
Colorado 
Connecticut 
Delaware 
Florida 
Georgia 
Hawaii 
Idaho 
Illinois 
Indiana 
Iowa 
Kansas 
Kentucky 
Louisiana 
Maine 
Maryland 
Massachusetts 
Michigan 
Minnesota 
Mississippi 
Missouri 
Montana 
Nebraska 
Nevada 
New Hampshire 
New Jersey 
New Mexico 
New York 
North Carolina 
North Dakota 
Ohio 
Oklahoma 
Oregon 
Pennsylvania 
Rhode Island 
South Carolina 
South Dakota 
Tennessee 
Texas 
Utah 
Vermont 
Virginia 
Washington 
West Virginia 
Wisconsin 
Wyoming 
Puerto Rico 
Total 
* 
3,000+ 
2,240+ 
402,000 
166+
*
* 
7,275+ 
2,000+
* 
2,005+ 
104,705 + 
2,500+ 
45,307 + 
181,700+ 
25+ 
1,515,250+ 
5,000+
* 
21,500+ 
405,000+ 
1,501+ 
651+ 
155,000+ 
38,674+ 
28,482+ 
20,650+ 
5,962+
*
* 
30,820+ 
1,990+ 
315+ 
10,000+ 
802,250+ 
33,900+ 
71,540+
* 
3,070+ 
6,665+ 
15,150+ 
34,100+ 
479,000
* 
800,000 + 
20,351 + 
600,000 + 
80,000 + 
250+ 
67,369 
Acres Inundated 
(Thousands of Acres) 
90 
1,800+ 
1 
236+ 
75+ 
50+ 
371 
540+ 
1,500 
602+ 
5+ 
55+ 
1+ 
1+ 
3,000+ 
1,407+ 
184+ 
915+ 
2+ 
750+ 
1,800+ 
350+ 
Over $6 billion 
Lives Lost 
0000 
14
0000000 
1
0
11 
0
1
0
12 
6
2
07 
2
0
1
00
241 
0
121 
11
0301 
25
10 
22
0 
38
2
0 
55 
(127 mudslide victims) 
208 
*Property damage unavailable but flooding occurred 
G-5

ANNUAL REPORT FY 86 OF THE CHIEF OF 
ENGINEERS ON CIVIL WORKS ACTIVITIES 
INDEX 
The following abbreviations are used in the index: 
LMK 
LMM 
LMN 
LMS 
MR+T 
MRK 
MRO 
NAB 
NAN 
NAO 
NAP 
NCB 
NCC 
NCD 
NCE 
NCR 
NCS 
NED 
NPA 
NPP 
VICKSBURG, MISS., DISTRICT 
MEMPHIS, TENN., DISTRICT 
NEW ORLEANS, LA., DISTRICT 
ST. LOUIS, MO., DISTRICT 
MISSISSIPPI, RIVER AND 
TRIBUTARIES PROJECT 
KANSAS CITY, MO., DISTRICT 
OMAHA, NEBR., DISTRICT 
BALTIMORE, MD., DISTRICT 
NEW YORK, N.Y., DISTRICT 
NORFOLK, VA., DISTRICT 
PHILADELPHIA, PA., DISTRICT 
BUFFALO, N.Y., DISTRICT 
CHICAGO, ILL., DISTRICT 
MISSISSIPPI RIVER BETWEEN MISSOURI 
RIVER AND MINNEAPOLIS, MINN. 
DETROIT, MICH., DISTRICT 
ROCK ISLAND, ILL., DISTRICT 
ST. PAUL, MINN., DISTRICT 
NEW ENGLAND DIVISION 
ALASKA DISTRICT 
PORTLAND, OREG., DISTRICT 
A 
Aberdeen, Ohio (ORH) 25-21 
Aberdeen Creek, Va. (NAO) 5-23 
Abilene, Kans. (MRK) 20-17, 20-19 
Abiquiu Dam, N. Mex. (SWA) 17-3, 17-10 
Absecon Creek, N.J. (NAP) 3-21 
Absecon Inlet, N.J. (NAP) 3-21 
Accotink Creek, Va. (NAB) 4-33 
Adams, Hossic River Basin, Mass. (NAN) 2-36 
Adams Creek, S.C. (SAN) 7-15 
Adams Levee, Ind. (ORL) 24-22, 24-26 
Addison, N.Y. (NAB) 4-13, 4-25 
Adena, Ohio (Short Creek) (ORP) 26-23 
Adldn Branch, N.C. (SAW) 6-28 
Afono Area and Aoa Area, American Samoa (POD) 
36-10 
Agana Small Boat Harbor, Guam (POD) 36-8 
Agat Harbor, Territory of Guam (POD) 36-1, 36-6 
AIWW-Mooring Basins, N.C. (SAW) 6-28 
AIWW-Tidal Lock in Snows Cut, N.C. (SAW) 6-28 
Airport Road Bridge, Frankstown, Miss. (SAM) 
10-13, 10-28, 10-38 
Ala Wai Small Boat Harbor, Hawaii (POD) 36-8 
Alabama River at Montgomery, Ala. (SAM) 10-43 
NPS 
NPW 
ORD 
ORH 
ORL 
ORN 
ORP 
POD 
SAJ 
SAM 
SAN 
SAS 
SAW 
SPK 
SPL 
SPN 
SWA 
SWF 
SWG 
SWL 
SWT 
SEATITLE, WASH., DISTRICT 
WALLA WALLA, WASH., DISTRICT 
OHIO RIVER DIVISION 
HUNTINGTON, W. VA., DISTRICT 
LOUISVILLE, KY., DIVISION 
NASHVILLE, TENN., DISTRICT 
PITTSBURGH, PA., DISTRICT 
PACIFIC OCEAN DIVISION 
JACKSONVILLE, FLA., DISTRICT 
MOBILE, ALA., DISTRICT 
CHARLESTON, S.C., DITRICT 
SAVANNAH, GA., DISTRICT 
WILMINGTON, N.C., DISTRICT 
SACRAMENTO, CALIF., DISTRICT 
LOS ANGELES, CALIF., DISTRICT 
SAN FRANCISCO, CALIF., DISTRICT 
ALBUQUERQUE, N. MEX., DISTRICT 
FORT WORTH, TEX., DISTRICT 
GALVESTON, TEX., DIVISION 
LITTLE ROCK, ARK., DISTRICT 
TULSA, OKLA., DISTRICT 
Alabama-Coosa Rivers, Ala. and Ga. (SAM) 10-18, 
10-29, 10-40, 10-45 
Alameda Creek, Calif. (SPK) 35-31 
Alamo Lake, Ariz. (SPL) 33-3, 33-10, 33-15 
Alamogordo Diversion Channel, Tularosa (Closed) 
Basin, N. Mex. (SWA) 17-7, 17-10 
Albemarle and Chesapeake Canal (Great Bridge, 
Va.) (NAO) 5-22 
Albeni Falls Dam, Idaho (NAS) 38-10, 38-17, 
38-23 
Albuquerque Diversion Channels, N. Mex. (SWA) 
17-1, 17-8, 17-10 
Alford, Green River, Mass. (NED) 1-22, 1-43, 
1-50 
Algoma Harbor, Wis. (NCE) 31-61, 31-62 
Alhambra Creek, Calif. (SPK) 35-31 
Aliso Creek Dam, Calif. (SPL) 33-24 
Allatoona Lake, Ga. (SAM) 10-21, 10-30, 10-40 
Allegany, N.Y. Unit I (Allegheny River) (ORP) 
26-22, 26-26 
Allegany, N.Y. Unit II (Five Mile Creek Area) (ORP) 
26-22, 26-26 
Allegheny River, Pa. (ORP) 26-2, 26-13, 26-17, 
26-21, 26-26 
Allegheny River, Pa., Locks and Dams (ORP) 26-24 
Allegheny River, Oil City, Pa. (ORP) 26-3, 26-13 
Allentown, Pa. (NAP) 3-23 
I-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Allenville, Ariz. (SPL) 33-19 
Alley Bay, Beals, Maine (NED) 1-43 
Alloway Creek, N.J. (NAP) 3-14, 3-21 
Alluvial Valley Mapping (MR+T) 42-3 
Alma Harbor, Wis. (NCD) 29-7 
Almond Lake, N.Y. (NAB) 4-13, 4-25 
Almond Village, N.Y. (NAB) 4-37 
Aloha-Rigolette Area, Grant and Rapides Parishes, 
La. (LMN) (LMK) 11-16, 11-18, 12-18, 12-19 
Alpena Harbor, Mich. (NCE) 31-61, 31-62 
Alpine Dam, Rockford, Ill. (NCR) 28-16 
Alpine, Tex. (SWA) 17-7, 17-10 
Alsea River, Oreg. (NPP) 37-39 
Altamaha, Oconee, and Ocmulgee Rivers, Ga. (SAS) 
8-1, 8-11, 8-12 
Alteration of Berwick Bay Bridge (LMN) 11-14 
Alteration to Rosiclare, Ill. (ORD) 22-3 
Alternative for Sugar Hill Reservoir (NED) 1-45 
Alton, Ind. (ORL) 24-22, 24-25 
Altus Reservoir, Okla. (SWT) 19-18 
Alum Creek Lake, Ohio (ORH) 25-2, 25-12, 25-16 
Alvin R. Bush Dam, Pa. (NAB) 4-18, 4-26 
Amazon Creek, Oreg. (NPP) 37-42 
American Lake, Vicinity of Fort Lewis, Wash. (NPS) 
38-26 
American River, Calif. (SPK) 35-31 
Atchison,.Kans. (MRK) 20-17 
Athalia, Ohio (ORH) 25-21 
Athens, Ohio (ORH) 25-20, 25-22 
Atlantic Beach Channels, N.C. (SAW) 6-25 
Atlantic City, N.J. (NAP) 3-23 
Atlantic Coast of Maryland and Assateague Island, 
Va. (NAB) 4-20 
Atlantic Coast of N.J. Sandy Hook to Barnegat Inlets 
(NAN) 2-36 
Atlantic Gulf Ship Canal, Fla. (SAJ) 9-46 
Atlantic Intracoastal Waterway between Norfolk, Va. 
and St. Johns River, Fla. (NAO) (SAW) (SAN) 
(SAS) (SAJ) 5-2, 5-14, 5-18, 5-22, 6-2, 6-18, 
6-22, 
7-2, 7-9, 7-11, 8-2, 8-11, 8-13, 9-2, 9-25, 
9-32 
Au Sable Harbor, Mich. (NCE) 31-61, 31-62 
Auasi Harbor, American Samoa (POD) 36-8 
Auburn, N.Y., Owasco Outlet (NCB) 32-37 
Augusta, Ga. (SAS) 8-7, 8-16 
Augusta, Ky. (ORH) 25-20 
Augusta Levee, Ga. (SAS) 8-7 
Augusta Levee, Kans. (SWT) 19-15 
Aunuu Harbor, American Samoa (POD) 36-8 
Aurora, Ind. (ORL) 24-22, 24-26 
Aurora, Westerly Creek-Kelley Road Dam, Colo. 
(MRO) 21-20 
Avoca, N.Y. (NAB) 4-13, 4-25 
Avon Harbor, N.C. (SAW) 6-4, 6-18 
Aylesworth Creek Lake, Pa. (NAB) 4-12, 4-24 
B 
B. Everett Jordan Dam and Lake, N.C. (Formerly 
New Hope Lake, N.C.) (SAW) 6-10, 6-15, 6-20 
Bachelor Island, Wash. (NPP) 37-44, 37-48 
Back Creek, Md. (NAB) 4-33 
Bad River, Bank Protection, Fort Pierre, S. Dak. 
(MRO) 21-20 
Bagaduce River, Maine (NED) 1-38, 1-43, 1-45 
Bailey, R.D., Lake, W. Va. (ORH) 25-9, 25-14, 
25-18 
Bainbridge, N.Y. (NAB) 4-35, 4-39 
Baker Brook, Mass. (NED) 1-45 
Baker River, Warren, N.H. (NED) 1-23 
Bakers Haulover Inlet, Fla. (SAJ) 9-3, 9-25, 9-32 
Ball Mountain Lake, Vt. (NED) 1-12, 1-27, 1-48 
Baltimore Harbor, Md. Collection and Removal of 
Drift (NAB) 4-4, 4-22, 4-28 
Baltimore Harbor, Md. Prevention of Obstruction 
and Injurious Deposits (NAB) 4-8, 4-23, 4-30 
Baltimore Harbor and Channels, Md. and Va. (NAB) 
4-3, 4-22, 4-27 
Baltimore Harbor and Channels (Norfolk District) 
(NAO) 5-2, 5-14, 5-18, 5-25 
Bandon Small Boat Basin, Oreg. (NPP) 37-39 
Bank Revetments and Dikes: Memphis District 
(MR+T) 42-39, 42-42 
Bank Revetments and Dikes: New Orleans District 
(MR+T) 42-30, 42-32 
Bank Revetments and Dikes: Vicksburg District 
(MR+T) 42-34, 42-36 
Bank Stabilization and Channel Rectification, Ark. 
(SWL) 18-2, 18-11, 18-21 
Bank Stabilization and Channel Rectification, 
Arkansas River, Ark. and Okla. (SWT) 19-16 
Bank Stabilization and Channel Rectification, Short 
Mountain to Fort Smith (SWL) 18-21 
Banner Special Drainage and Levee Districts (NCR) 
28-14, 28-16 
Banning Levee-San Gorgonio River, Calif. (SPL) 
33-24 
Bar Harbor, Maine (NED) 1-38 
Bar Point Harbor, Alaska (NPA) 40-13 
Barataria Bay Waterway, La. (LMN) 11-14 
Barbers Point Harbor, Hawaii (POD) 36-2, 36-6, 
36-7 
Barbourville, Ky. (ORN) 23-13, 23-19 
Barcelona Harbor, N.Y. (NCB) 32-11, 32-35 
Bardwell Lake, Tex. (SWF) 16-3, 16-15, 16-19 
Barkley Dam and Lake Barkley, Ky. and Tenn. 
(ORN) 23-14 
Barnard, Kans. (MRK) 20-17 
Barnegat Inlet, N.J. (NAP) 3-2, 3-15, 3-18 
Barnegat Light, N.J. (NAP) 3-23 
I-2

INDEX 
Barnett Creek, Ky. (ORL) 24-24 
Barre Falls Dam, Mass. (NED) 1-12, 1-27, 1-48 
Barren River Lake, Ky. (ORL) 24-5, 24-14, 24-27 
Bartley, Nebr. (MRK) 20-17, 20-19 
Bashbish Brook, Copake, N.Y. (NAN) 2-39 
Bass Harbor, Maine (NED) 1-38, 1-46 
Bass Harbor Bar, Maine (NED) 1-38 
Bassett Creek, Minn. (NCS) 27-4, 27-19 
Bastrop Bayou, Tex. (SWG) 15-27 
Batavia and Vicinity, N.Y. (NCB) 32-37 
Bath, N.Y. (NAB) 4-36, 4-39 
Baton Rouge Harbor, La. (LMN) 11-14 
Baton Rouge Harbor (Devil's Swamp), La. (MR+T) 
42-5, 42-29, 42-50 
Battle Creek, Bank Protection, Battle Creek, Nebr. 
(MRO) 21-20 
Baudette Harbor, Minn. (NCS) 27-23 
Bay City Harbor, Wis. (NCD) 29-7 
Bay Ridge and Red Hook Channels, N.Y. (NAN) 
2-2, 2-22, 2-27, 2-33 
Bay River, N.C. (SAW) 6-25 
Bayard, W. Va. (NAB) 4-36, 4-39 
Bayfield Harbor, Wis. (NCE) 31-61, 31-62 
Bayou Bartholomew and Tributaries, Ark. and La. 
(LMK) 12-4, 12-9, 12-11, 12-14, 12-16 
Bayou Bodcau and Tributaries, Ark. and La. (LMK) 
12-4, 12-9, 12-11, 12-17 
Bayou Bodcau, Red Chute, and Loggy Bayou, La. 
(LMN) (LMK) 11-16, 12-18, 12-19 
Bayou Bodcau Reservoir, La. (LMK) 12-16, 12-18, 
12-19 
Bayou Bonfouca, La. (LMN) 11-14 
Bayou Choupique, La. (LMN) 11-16 
Bayou Cocodrie and Tributaries, La. (MR+T) 42-6, 
42-14, 42-28, 42-54, 42-58 
Bayou Coden, Ala. (SAM) 10-3, 10-26, 10-32 
Big Sandy Lake, Tex. (SWF) 16-3, 16-15, 16-19 
Big Sandy River, W. Va. and Ky., including Levisa 
and Tug Forks (ORH) 25-19 
Big Sioux River at Sioux City, Iowa and S. Dak. 
(MRO) 21-16 
Big Sioux River, Fink Bridge, near Flandreau, S. 
Dak. (MRO) 21-20 
Big Sioux River, Schofield Bridge, near Flandreau, 
S. Dak. (MRO) 21-20 
Big Slough - Mayo Ditch, Ark. (MR+T) 42-57 
Big South Fork National River and Recreation Area, 
Ky. and Tenn. (ORN) 23-4, 23-9 
Big Spring, Tex. (SWF) 16-22 
Big Stone Lake and Whetstone River, Minn. and S. 
Dak. (NCS) 27-4, 27-19 
Big Stranger Creek, Kans. (MRK) 20-17 
Big Suamico River, Wis. (NCE) 31-2, 31-33, 
31-46 
Big Sunflower River, Miss. (LMK) (MR-T) 12-14, 
42-51 
Big Swan Drainage and Levee District, Ill. (LMS) 
14-14 
Big Thompson River, Johnstown (MRO) 21-20 
Big Timber Creek, N.J. (NAP) 3-21 
Big Walnut Lake, Ind. (ORL) 24-21, 24-28 
Big Wash, Milford, Utah (SPK) 35-31 
Big Wood River, Idaho (NPW) 39-14, 39-17 
Billings, Montana (MRO) 21-18 
Biloxi Harbor, Miss. (SAM) 10-4, 10-26, 10-33, 
10-45 
Biloxi Harbor, East Harrison County Canal, Miss. 
(SAM) 10-5, 10-26, 10-33 
Biloxi River at Lorraine Road, Harrison County, 
Miss. (SAM) 10-43 
Binghamton, N.Y. (NAB) 4-14, 4-25 
Birch, W. Va. (ORH) 25-20 
Birch Hill Dam, Mass. (NED) 1-13, 1-28, 1-48 
Birch Lake, Okla. (SWT) 19-3, 19-9, 19-13, 19-17 
Bird Rock Area, La Jolla, Calif. (SPL) 33-18 
Birds Point-New Madrid Floodway, Mo. (MR+T) 
42-53 
Biscayne Bay, Fla., Hurricane Protection (SAJ) 9-53 
Black Bayou-Pine Island Area, La. (LMN) 11-16 
Black Bayou Reservoir, La. (LMN) (LMK) 11-16, 
12-18, 12-19 
Black Bear and Miller Lakes, Minn. (NCS) 27-5, 
27-19 
Black Creek, Gadsden, Ala. (SAM) 10-43 
Black Fork at Hendricks, W. Va. (ORP) 26-22 
Black River, Ark. - Mo. (SWL) 18-16, 18-17 
Black River, Mich. (NCE) 31-61, 31-62 
Black River, N.C. (SAW) 6-25, 6-27 
Black River, Wis. (NCS) 27-23, 27-25 
Black River, Butler County Road 607, Mo. (SWL) 
18-4, 18-11 
Black River Harbor, Mich. (NCE) 31-3, 31-33, 
31-46, 31-63 
Black River Harbor, N.Y. (NCB) 32-35 
Black River Lake, Wis. (NCS) 27-25 
Black River (North Bend), Wis. (NCS) 27-27 
Black River, Poplar Bluff, Mo., to Knobel, Ark. 
(SWL) 18-17 
Black River (Port Huron), Mich. (NCE) 31-61, 
31-62 
Black Rock Channel and Tonawanda Harbor, N.Y. 
(NCB) 32-2, 32-18, 32-24, 32-39 
Black Rock Harbor, Conn. (NED) 1-3, 1-25, 1-33 
Black Rock Lake, Conn. (NED) 1-16, 1-29, 1-49 
Black Walnut Harbor, Md. (NAB) 4-33 
Black Walnut Point, Md. (NAB) 4-36 
Black Warrior and Tombigbee Rivers, Ala. (SAM) 
10-5, 10-26, 10-33, 10-47 
Blackberry Creek, Henry County, Va. (SAW) 6-31 
Blackbird Creek near Macy, Nebr. (MRO) 21-16 
Blackfoot Area, Snake River, Idaho (NPW) 39-14, 
39-16 
I-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Blackfoot Reservoir, Idaho (NPW) 39-14 
Blackfoot River, Idaho (NPW) 39-14, 39-16 
Blackfoot River, Mont. (NPS) 38-26 
Blackstone, Mass. (NED) 1-22 
Blackstone River Basin, Mass. and R.I. (NED) 1-10, 
1-23, 1-47 
Blackstone River, Millbury, Mass. (NED) 1-10, 
1-23, 1-27, 1-35, 1-48 
Blackwater Dam, N.H. (NED) 1-18, 1-30, 1-51 
Blackwater River, Fla. (SAM) 10-42, 10-45 
Blackwater River, Va. (NAO) 5-23 
Blaine, Maine (NED) 1-22 
Blaine Harbor, Wash. (NPS) 38-25, 38-31 
Blair and Sitcum Waterways, Tacoma Harbor, Wash. 
(NPS) 38-12 
Blakely Mountain Dam-Lake Ouachita, Ark. (LMK) 
12-16, 12-19 
Blind Slough Diking District, Oreg. (NPP) 37-40 
Block Island, Harbor of Refuge, RI (NED) 1-53 
Bloomington Lake, Md. and W. Va. (NAB) 4-11, 
4-24, 4-32 
Blue Marsh Lake, Pa. (NAP) 3-11, 3-17 
Blue Mountain Lake, Ark. (SWL) 18-4, 18-11, 
18-22 
Blue River Basin (Kansas City District) (MRK) 
20-17 
Blue River Channel, Kansas City, Mo. (MRK) 20-2, 
20-10, 20-13 
Blue River Lake, Oreg. (NPP) 37-11, 37-27, 
37-36, 37-47, 37-49 
Bluestone Lake, W. Va. (ORH) 25-3, 25-12, 25-16 
Bluff Creek, Miss. (SAM) 10-42 
Board of Engineers for Rivers and Harbors (BERH) 
41-1 
Bodega Bay, Calif. (SPN) 34-5 
Bodie Island, N.C. (SAW) 6-28 
Boeuf and Tensas Rivers and Bayou Macon, Ark. 
and La. (MR+T) 42-51 
Boeuf River, La. (LMN) 12-14 
Bogachiel River, Wash. (NPS) 38-26 
Boggy Creek, Tex. (SWF) 16-4, 16-15, 16-19 
Boise River, Idaho (NPW) 39-17 
Boise Valley, Idaho (NPW) 39-14, 39-16 
Boligee Canal, Boligee, Ala. (SAM) 10-13, 10-28, 
10-38 
Bolivar, N.Y. (ORP) 26-28 
Bolles Harbor, Mich. (NCE) 31-3, 31-33, 31-46 
Bon Secour River, Ala. (SAM) 10-6, 10-26, 10-34, 
10-42, 10-45 
Bonnes Coulee, Velva, N.D. (NCS) 27-24 
Bonnet Carre Spillway, La. (MR+T) 42-6, 42-56 
Bonneville Lock and Dam-Lake Bonneville, Oreg. 
and Wash. (NPP) 37-2, 37-17, 37-24, 37-28, 
37-31, 37-37, 37-51 
Bonpas Creek, Ill. (ORL) 24-22, 24-26 
Bonum Creek, Va. (NAB) 4-33 
Boone County, Ky. (ORL) 24-20 
Booneville Lake, Ky. (ORL) 24-21, 24-27 
Boothbay Harbor, Maine (NED) 1-38 
Boston Harbor, Mass. (NED) 1-38, 1-52, 1-53 
Boswell Lake, Okla. (SWT) 19-15 
Boulder Creek, Boulder, Colo. (MRO) 21-16 
Bound Brook, Scituate, Mass. (NED) 1-43 
Bowman, Leland, Lock, La. (formerly Vermilion 
Lock) (LMN) 11-2, 11-10, 11-12 
Bowman-Haley Lake, N. Dak. (MRO) 21-2, 21-10, 
21-13 
Brackenridge, Tarentum and Natrona, Pa. (ORP) 
26-22, 26-26 
Bradford, Pa. (ORP) 26-22, 26-28 
Bradford, Tenn. (LMM) 13-6 
Bradley Lake, Alaska (NPA) 40-14 
Bramwell, W. Va. (ORH) 25-22 
Brandon Road Lock and Dam, Ill. (NCC) 28-20, 
28-21 
Branford Harbor, Conn. (NED) 1-38 
Branson Cove, Va. (NAB) 4-33 
Brant Rock Beach, Marshfield, Mass. (NEi) 1-45 
Braymer Lake, Mo. (MRK) 20-17 
Brazos Island Harbor, Tex. (SWG) 15-2, 15-13, 
15-16, 15-28, 15-29, 15-34 
Brazos River, Tex., Velasco to Old Washington 
(SWG) 15-27 
Brea Dam, Calif. (SPL) 33-24 
Breckenridge, Minn. (NCS) 27-27 
Breton Bay, Md. (NAB) 4-33 
Brevard County, Fla. (SAJ) 9-17, 9-29, 9-40 
Brevoort Levee, Ill. (ORL) 24-20, 24-29 
Bridge Alterations Authorized 
Chicago, Ill., District (NCC) 30-15 
Nashville, Tenn., District (ORN) 23-4 
New England Division (NED) 1-9 
Bridgeport Harbor, Conn. (NED) 1-22, 1-38, 
1-45, 1-53 
Bridges, Columbia River, Oreg. (NPP) 37-39 
Bridgewater, Va. (NAB) 4-36, 4-39 
Brilliant, Ohio (ORP) 26-23 
Bristol Harbor, R.I. (NED) 1-3, 1-25, 1-33, 1-38 
Broad Creek, Md. (NAB) 4-33 
Broad Creek, N.C. (SAW) 6-27 
Broad Creek, Va. (NAO) 5-3, 5-14, 5-18 
Broad Creek River, Del. (NAB) 4-33 
Broadkill River, Del. (NAP) 3-21 
Broadwater Creek, Md. (NAB) 4-37 
Broadway Lake, S.C. (SAS) 8-7, 8-11, 8-15 
Brockway, Pa. (ORP) 26-23 
Brockway Lake, Vt. (NED) 1-45 
Broken Bow, Nebr. (MRO) 21-20 
Broken Bow Lake, Okla. (SWT) 19-7, 19-12, 
19-14, 19-17 
Bromley, Ky. (ORL) 24-22, 24-25 
Bronx River, N.Y. (NAN) 2-2, 2-22, 2-27, 2-37 
I-4

INDEX 
Brookfield Lake, Mo. (MRK) 20-17 
Brooklyn, W. Va. (ORH) 25-21 
Brookport, Ill. (ORL) 24-20, 24-24, 24-29 
Brookville, Pa. (ORP) 26-22, 26-28 
Brookville Lake, Ind. (ORL) 24-5, 24-14, 24-27 
Broward County, Fla., Beach Erosion Control and 
Hillsboro Inlet, Fla., Navigation Project (SAJ) 
9-18, 9-29, 9-40 
Brown, Clarence J., Dam and Reservoir, Ohio (ORL) 
24-8, 24-15 
Browns Creek, N.Y. (NAN) 2-3, 2-22, 2-27, 2-33, 
2-37 
Brownwood Channel Improvement, Tex. (SWF) 
16-22 
Brunswick County Beaches, N.C. (Cape Fear to 
North Carolina-South Carolina 
State Line) (SAW) 6-27 
Brunswick Harbor, Ga. (SAS) 8-3, 8-6, 8-11, 
8-13 
Brush Creek, Kansas City, MO. (MRK) 20-9 
Buchanan Dam-H. V. Eastman Lake, Calif. (SPK) 
35-4, 35-23 
Buck Creek, N.C. and S.C. (SAN) 7-8, 7-16 
Buckhannon, W. Va. (ORP) 26-22, 26-28 
Buckhannon River, W. Va. (ORP) 26-21 
Buckhorn Lake, Ky. (ORL) 24-6, 24-14, 24-27 
Bucks Harbor, Machiasport, Maine (NED) 1-38 
Bucksport Harbor, Maine (NED) 1-38 
Buena Vista, Ohio (ORH) 25-21 
Buena Vista, Va. (NAO) 5-24 
Buffalo, Wyo. (MRO) 21-16 
Buffalo Bayou and Tributaries, Tex. (SWG) 15-9, 
15-14, 15-25 
Buffalo Creek, Lee County, N.C. (SAW) 6-31 
Buffalo Creek, Meadow Grove, Nebr. (MRO) 21-16 
Buffalo Creek, Scranton, N. Dak. (MRO) 21-16 
Buffalo Fork, Ferry Location, Wyo. (NPW) 39-17 
Buffalo Harbor, N.Y. (NCB) 32-3, 32-18, 32-25 
Buffalo River, Miss. (LMK) 12-19 
Buffumville Lake, Mass. (NED) 1-21, 1-31, 1-52 
Buford Dam, Ga. (SAM) 10-22 
BUll Run, Pa. (NAB) 4-36 
Bull Shoals Lake, Ark. (SWL) 18-8, 18-13, 18-24 
Bullocks Point Cove, R.I. (NED) 1-38 
Bunker Harbor, Maine (NED) 1-38 
Burbank-Eastern System, Calif. (SPL) 33-22 
Burbank-Western System (Lower) Calif. (SPL) 
33-22 
Burbank-Western System (Upper) Calif. (SPL) 
33-22 
Burch Creek, Weber County, Utah (SPK) 35-31 
Burgettstown, Pa. (ORP) 26-22 
Burgettstown-Slovan, Pa. (ORP) 26-28 
Burial Hill Beach, Westport, Conn. (NED) 1-42 
Burketts Creek, Amory, Miss. (SAM) 10-43 
Burlington, Iowa (NCR) 28-16 
Burlington, Ohio (ORH) 25-20 
Burlington Dam, N. Dak. (NCS) 27-24 
Burlington Harbor, Vt. (NAN) 2-34 
Burns Small Boat Harbor, Ind. (NCC) 30-15 
Burns Waterway Harbor, Ind. (NCD) 30-2, 30-6, 
30-9, 30-11, 30-14, 30-15 
Burnsville Lake, W. Va. (ORH) 25-3, 25-12, 25-16 
Bush, Alvin R., Dam, Pa. (NAB) 4-18, 4-26 
Butler, Pa. (ORP) 26-22, 26-28 
Buttermilk Bay Channel, Mass. (NED) 1-38 
Buttermilk Channel, N.Y. (NAN) 2-3, 2-22, 2-27, 
2-33 
Byram River at Pemberwick, Conn. (NAN) 2-36 
C 
Cache Basin, Ark. (MR+T) 42-10, 42-18, 42-28, 
42-53 
Cache Creek Basin, Calif. (SPK) 35-21 
Cache La Poudre River, Ft. Collins, Colo. (MRO) 
21-20 
Cache La Poudre River, Windsor, Colo. (MRO) 
21-20 
Cache River Diversion, Ill. (LMS) 14-14 
Cache River Levee, Ill. (ORL) 24-29 
Caddo Lake, La. (LMK) 12-5, 12-9, 12-11, 12-17 
Cadet Bayou, Miss. (SAM) 10-42, 10-45 
Cadle Creek, Md. (NAB) 4-37 
Caesar Creek Lake, Ohio (ORL) 24-6, 24-15, 
24-27 
Cagles Mill Lake, Ind. (ORL) 24-6, 24-15, 24-27 
Cahaba River, Ala. (SAM) 10-42 
Cairo, W. Va. (ORH) 25-22 
Calabash Creek, N.C. (SAN) 7-15 
Calapooya River, Oreg. (NPP) 37-44 
Calaveras River and Little John Creek and 
Tributaries, including New Hogan Lake and 
Farmington Dam, Calif. (SPK) 35-5, 35-23 
Calcasieu River and Pass, La. (LMN) 11-14 
Calcasieu River at Coon Island, La. (LMN) 11-14 
Calcasieu River at Devil's Elbow, La. (LMN) 11-14 
Calcasieu River Salt Water Barrier, La. (LMN) 
11-14 
Caledonia, N.Y. (NCB) 32-37 
Calf Pasture Beach Park, Conn. (NED) 1-42 
California (Cincinnati) Ohio (ORL) 24-22, 24-26 
California Debris Commission (CDC) 44-1 
Calion, Ark. (LMK) 12-13, 12-16 
Calloway Branch, Hurst, Tex. (SWF) 16-22 
Calumet Harbor and River, Ill. and Indiana (NCC) 
30-2, 30-9, 30-11, 30-14, 30-15 
Calumet River Bridges, Ill. (NCC) 30-15 
Camas Creek, Idaho (NPW) 39-16 
Cambridge Harbor, Md. (NAB) 4-33 
Cambridgeport Lake, Vt. (NED) 1-45 
I-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Camden Harbor, Maine (NED) 1-38 
Camelsback Dam, Ariz. (SPL) 33-19 
Camp Ground Lake, Ky. (ORL) 24-21 
Camp Perry, Ohio (NCB) 32-37 
Campbells Island, Ill. (NCR) 28-16 
Campti-Clarence Area in Natchitoches Parish, La. 
(LMN) (LMK) 11-16, 12-17, 12-19 
Canal Point, Fla. (SAJ) 9-47 
Canapitsit Channel, Mass. (NED) 1-38 
Canaveral Harbor, Fla. (SAJ) 9-3, 9-25, 9-32, 9-42 
Candy Lake, Okla. (SWT) 19-3, 19-9, 19-13 
Cane River, La. (LMN) 11-14 
Caney Fork River, Tenn. (ORN) 23-13 
Canisteo, N.Y. (NAB) 4-14, 4-25 
Cannelton, Ind. (ORL) 24-20, 24-24, 24-29 
Cannelton Locks and Dam, Ind. (ORD) 22-3, 22-9 
Cannon, Clarence, Dam and Reservoir, Mo. (LMS) 
14-8, 14-10, 14-12 
Canoe Creek, Henderson, Ky. (ORL) 24-20 
Canton, Mass. (NED) 1-22, 1-43 
Canton, Mo. (NCR) 28-14, 28-16 
Canton Lake, Okla. (SWL) (SWT) 18-22, 19-3, 
19-9, 19-14, 19-17 
Canton (Nimishillen), Ohio (ORH) 25-22 
Canyon Lake, Tex. (SWF) 16-4, 16-15, 16-19 
Cape Charles City Harbor, Va. (NAO) 5-3, 5-14, 
5-18 
Cape Cod Canal, Mass. (NED) 1-3, 1-25, 1-33, 
1-53 
Cape Fear River, N.C., above Wilmington (SAW) 
6-5, 6-18 
Cape Fear River Basin, N.C. (SAW) 6-10, 6-30 
Cape Florida State Park, Fla. (SAJ) 9-47 
Cape Girardeau, Mo., No. 2 (LMS) 14-14 
Cape Girardeau, Mo., Reaches Nos. 1, 3 and 4 
(LMS) 14-14 
Cape Henry Channel, Va. (NAO) 5-2, 5-18 
Cape Lookout, N.C. (SAW) 6-28 
Cape May City, N.J. (NAP) 3-23 
Cape May Inlet, N.J. (NAP) 3-21 
Cape Porpoise Harbor, Maine (NED) 1-38 
Cape Vincent Harbor, N.Y. (NCB) 32-35 
Captain Anthony Meldahl Locks and Dam, Ky. 
(ORD) 22-3, 22-8 
Carbon Canyon Dam and Channel (SPL) 33-24 
Carden's Bottom Drainage District No. 2, Arkansas 
River, Ark. (SWL) 18-17 
Carl L. Estes Dam and Lake, Tex. (SWF) 16-22 
Carlyle Lake, Ill. (LMS) 14-14 
Carolina Beach and Vicinity, N.C. (SAW) 6-11, 
6-20, 6-31 
Carr Fork Lake, Ky. (ORL) 24-7, 24-15, 24-27 
Carrabelle Bar and Harbor, Fla. (SAM) 10-42 
Carrabelle, Fla. (SAM) 10-44, 10-45 
Carroll County Levee and Drainage District, Ill. 
(NCR) 28-16 
Carrollton, Ky. (ORL) 24-22, 24-25 
Carters Creek, Va. (NAO) 5-23 
Carters Lake, Ga. (SAM) 10-19, 10-29 
Caruthersville Harbor, Mo. (LMM) 13-5 
Carvers Harbor, Vinalhaven, Maine (NED) 1-38 
Carvins Creek, Roanoke, Va. (SAW) 6-31 
Cascadia Lake, Oreg. (NPP) 37-42, 37-49 
Caseville Harbor, Mich. (NCE) 31-61, 31-62 
Caseyville, Ky. (ORL) 24-21, 24-24 
Cashie River, N.C. (SAW) 6-25 
Cassville Harbor, Wis. (NCD) 29-7 
Castine, Maine (NED) 1-22 
Castle Rock, Wash. (NPP) 37-42 
Castlewood Lake, Colo. (MRO) 21-16 
Catching Inlet Drainage District, Oreg. (NPP) 37-42 
Cathance River, Maine (NED) 1-38 
Catherine Creek, Oreg. (NPW) 39-2, 39-9, 39-11, 
39-17 
Catherine Creek Lake, Oreg. (NPW) 39-14 
Cathlamet, Wash. (NPP) 37-39 
Cattaraugus Creek, N.Y. (NCB) 32-35 
Cattaraugus Harbor, N.Y. (NCB) 32-3, 32-18 
Cattlettsburg, Ky. (ORH) 25-20, 25-22 
Cave Run Lake, Ky. (ORL) 24-7, 24-15, 24-27 
Cave-In-Rock, Ill. (ORL) 24-22, 24-25 
Cayuga Creek, Cheektowaga, N.Y. (NCB) 32-37 
Cecil M. Harden Lake, Ind. (ORL) 24-7, 24-15, 24-27 
Cedar Bayou, Tex. (SWG) 15-27 
Cedar Canyon Dam, S. Dak. (MRO) 21-16 
Cedar Creek, Sussex City, Del. (NAP) 3-21 
Cedar Keys Harbor, Fla. (SAJ) 9-45, 9-46 
Cedar Point, Ga. (SAS) 8-16 
Cedar Point Lake, Kans. (SWT) 19-15 
Cedar River, Wash. (NPS) 38-26 
Cedar River Harbor, Mich. (NCE) 31-62 
Cedars Lock and Dam, Wis. (NCE) 31-60 
Celina Dam, Ky. (ORN) 23-14 
Center Hill Lake, Ohio River Basin, Tenn. (ORN) 
23-6, 23-9, 23-18 
Central and Southern Florida (SAJ) 9-21, 9-30, 
9-40, 9-47, 9-48, 9-49, 9-50, 9-51 
Central City Lake, Iowa (NCR) 28-16 
Ceredo-Kenova, W. Va. (ORH) 25-20, 25-22 
Chambersburg, Ohio (ORH) 25-21 
Channel between North and South Hero Island, 
Lake Champlain, Vt. (NAN) 2-34 
Channel Clearing and Snagging on Willamette River 
and Major Tributaries, (NPP) 37-49 
Channel Connecting Plain Dealing Creek and Oak 
Creek, Md. (NAB) 4-37 
Channel Connecting Thoroughfare Bay with Cedar 
Bay, N.C. (SAW) 6-25 
Channel Connecting York River, Va. with Back 
Creek to Slaights Wharf (NAO) 5-23 
Channel from Back Sound to Lookout Bight, N.C. 
(SAW) 6-5, 6-18 
I-6

INDEX 
Channel from Naples to Big Marco Pass, Fla. (SAJ) 
9-4, 9-25, 9-32 
Channel from Pamlico Sound to Rodanthe, N.C. 
(SAW) 6-25 
Channel from Phoebus, Va. to Deep Water in 
Hampton Roads (NAO) 5-23 
Channel Improvements for Flood Control and Major 
Drainage on 16 Streams Tributary to Willamette 
River (NPP) 37-49 
Channel Islands Harbor, Calif. (SPL) 33-18, 33-22 
Channel to Liberty, Tex. (SWG) 15-8 
Channel to Newport News, Va. (NAO) 5-23 
Channel to Port Bolivar, Tex. (SWG) 15-2, 15-13, 
15-16, 15-34 
Channels in the Straits of MacKinac (NCE) 31-62 
Chapel Hill, N.C. (SAW) 6-31 
Chaplin River, Perryville, Ky. (ORL) 24-20 
Charenton Drainage and Navigation Canal (MR+T) 
42-50 
Chariton River, Mo. (1944 Act) (MRK) 20-17 
Chariton-Little Chariton Basin, Mo. (1965 Act) 
(MRK) 20-17 
Charles River Dam, Mass. (NED) 1-22, 1-43 
Charles River (Natural Valley Storage Areas), Mass. 
(NED) 1-11, 1-27, 1-36 
Charleston Channel, Oreg. (NPP) 37-39 
Charleston Harbor, S.C. (SAN) 7-2, 7-9, 7-11, 
7-15, 7-17 
Charlestown, N.H. (NED) 1-22, 1-43, 1-49 
Charlevoix Harbor, Mich. (NCE) 31-3, 31-33, 
31-46 
Charlotte Harbor, Fla. (SAJ) 9-4, 9-25, 9-32 
Chartiers Creek, Pa. (ORP) 26-3, 26-13, 26-28 
Chaska, Minn. (NCS) 27-5, 27-19 
Chatfield Lake, Colo. (MRO) 21-2, 21-10, 21-13 
Chatham (Stage) Harbor, Mass. (NED) 1-38, 1-53 
Chattahoochee River, Eufaula, Ala. (SAM) 10-14, 
10-38 
Chattanooga, Tenn. and Rossville, Ga. (ORN) 23-13 
Chattooga Dams and Lakes, Ga. and S.C. (SAS) 
8-17 
Cheat River, W. Va. (ORP) 26-21 
Cheatham Lock and Dam, Tenn. (ORN) 23-14 
Cheboygan Harbor, Mich. (NCE) 31-4, 31-33, 
31-46 
Cheesequake Creek, N.J. (NAN) 2-33, 2-37 
Chefuncte River and Bogue Falia, La. (LMN) 11-14 
Chehalis River, Wash. (NPS) 38-12, 38-26 
Chelsea Street Highway Bridge, Mass. (NED) 1-9 
Chena River Lakes, Alaska (NPA) 40-5, 40-9, 
40-12 
Cheney Reservoir, Kans. (SWT) 19-18 
Cherry and Red Fork Creeks Channel Improvement, 
Okla. (SWT) 19-15, 19-17, 19-18 
Cherry Creek Lake, Colo. (MRO) 21-3, 21-10, 
21-13, 21-19 
Cherryfield, Maine (NED) 1-22, 1-43 
Chesapeake, Ohio (ORH) 25-20 
Chesconessex Creek, Va. (NAO) 5-23 
Cheshire, Ohio (ORH) 25-21 
Chester, Calif. (SPK) 35-31 
Chester River, Md. (NAB) 4-4, 4-22, 4-28 
Chester River, Pa. (NAP) 3-21 
Chester River at Chester, Pa. (NAP) 3-13 
Chetco River, Oreg. (NPP) 37-2, 37-24, 37-31 
Chewaucan River, Oreg. (NPP) 37-42 
Chicago Harbor, Ill. (NCC) 30-3, 30-9, 30-11, 
30-14, 30-15 
Chicago River, Ill. (NCC) 30-3, 30-9, 30-11, 30-14 
Chicago River, Ill. (North Branch) (NCC) 30-6, 
30-10 
Chickamauga Lock and Dam, Tenn. (ORN) 23-17 
Chickasaw Bogue Creek, U.S. Highway 43 Bridge, 
Linden, Ala. (SAM) 10-43 
Chicopee, Mass. (NED) 1-22, 1-43, 1-45, 1-49 
Chicopee Falls, Mass. (NED) 1-43, 1-49 
Chief Joseph Dam-Rufus Woods Lake, Wash. (NPS) 
38-10, 38-17, 38-23 
Chignik, Alaska (NPA) 40-15 
Chillicothe, Ohio (ORH) 25-3, 25-12, 25-16, 
25-22 
Chilo, Ohio (ORH) 25-21 
Chincoteague Bay, Va. (NAO) 5-23 
Chincoteague Harbor of Refuge, Va. (NAO) 5-23 
Chincoteague Inlet, Va. (NAO) 5-4, 5-14, 5-18 
Chino Canyon Improvements, Palm Springs, Calif. 
(SPL) 33-24 
Chippewa Harbor, Isle Royale, Mich. (NCE) 31-62 
Chittenango Creek and Tributaries, N.Y. (NCB) 
32-37 
Choctaw Bayou and Tributaries, La. (LMN) 11-16 
Choctawhatchee Bay to Pensacola Bay, Fla. (SAM) 
10-35 
Choctawhatchee Bay to West Bay, Fla. (SAM) 
10-35 
Choctawhatchee River, Fla. and Ala. (SAM) 10-42 
Choptank River, Md. (NAB) 4-33 
Chouteau Lock and Dam, Okla. (SWL) (SWT) 
18-20, 19-16 
Chouteau, Nameoki, and Venice Drainage and Levee 
District, Ill. (LMS) 14-14 
Chowan River, N.C. (NAO) 5-23 
Chowan River, N.C. (SAW) 6-25 
Christiansted Harbor, V.I. (SAJ) 9-45, 9-46 
Cibolo Creek, Tex. (SWA) 17-7, 17-10 
Cincinnati, Ohio (ORL) 24-20, 24-22, 24-24, 
24-25, 24-29 
Cincinnatus, N.Y. (NAB) 4-39 
City Creek Levee, Calif. (SPL) 33-19 
City of Aurora, Colo. (MRO) 21-16 
Clackamas River at Dixon Farm Location, Oreg. 
(NPP) 37-42 
I-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Claiborne County Port, Miss. (LMK) 12-14 
Claiborne Harbor, Md. (NAB) 4-5, 4-22, 4-29 
Claiborne Lock and Dam, Ala. (SAM) 10-19, 10-30 
Clallam Bay, Wash. (NPS) 38-26 
Clallam River, Wash. (NPS) 38-26 
Clanton, Ala. (SAM) 10-43 
Claremont Lake, N.H. (NED) 1-45 
Clarence Cannon Dam and Reservoir, Mo. (LMS) 
14-8, 14-10, 14-12 
Clarence J. Brown Dam and Reservoir, Ohio (ORL) 
24-8, 24-15 
Clarendon to Laconia Circle, Ark. (LMM) 13-6 
Clarington, Ohio (ORP) 26-23 
Clark Fork River, Mont. (NPS) 38-26 
Clark Point Beach, New Bedford, Mass. (NED) 
1-42 
Clarks Hill Lake, Ga. and S.C. (SAS) 8-8, 8-11, 
8-15, 8-17 
Clarkson, Nebr. (MRO) 21-16, 21-20 
Clarksville, Ark. (SWL) 18-17 
Clatskanie Drainage District 1, Oreg. (NPP) 37-44, 
37-48 
Clatskanie River, Oreg. (NPP) 37-39 
Clatskanie River Area, Oreg. (NPP) 37-44, 37-48 
Clatsop County Diking District 3, Oreg. (NPP) 
37-44 
Clatsop County Diking District 4, Oreg. (NPP) 
37-44, 37-48 
Clatsop County Diking District 6, Oreg. (NPP) 
37-44, 37-48 
Clatsop County Drainage District 1, Oreg. (NPP) 
37-44, 37-48 
Clear and Burnt River, Oreg. (NPW) 39-2, 39-9, 
39-11 
Clear Creek, Tex. (SWG) 15-10, 15-14, 15-25 
Clear Creek and Clear Lake, Tex. (SWG) 15-27 
Clear Creek Drainage and Levee District, Ill. (LMS) 
14-14 
Clear River, Burrillville, R.I. (NED) 1-10, 1-23, 
1-27, 1-36, 1-48 
Clearwater Lake, Mo. (SWL) 18-4, 18-11, 18-24 
Clearwater Pass, Fla. (SAJ) 9-45, 9-46 
Clearwater River, Idaho (NPW) 39-17 
Clearwater River, Wash. (NPS) 38-26 
Clesson Brook, Buckland, Mass. (NED) 1-23 
Cleveland and Lakewood, Ohio (NCB) 32-36 
Cleveland Harbor, Ohio (NCB) 32-3, 32-18, 32-26 
Cleves, Ohio (ORL) 24-22, 24-25 
Clewiston, Fla. (SAJ) 9-47 
Cliff Walk, Newport, R.I. (NED) 1-42 
Clifton, W. Va. (ORH) 25-21 
Clifty Creek Lake, Ind. (ORL) 24-22 
Clinch River, Tenn., and Va. (ORN) 23-13 
Clinton, Ind. (ORL) 24-22, 24-25 
Clinton, Iowa (NCR) 28-14, 28-16 
Clinton Harbor, Conn. (NED) 1-38, 1-53 
Clinton Harbor, Iowa (NCD) 29-7 
Clinton Lake, Kans. (MRK) 20-2, 20-10, 20-13 
Clinton River, Mich. (NCE) 31-4, 31-33, 31-46 
Cloverport, Ky. (ORL) 24-21, 24-24 
Clyde, R.I. (NED) 1-45 
Clyde Park, Mont. (MRO) 21-19 
Coal Creek and Tributaries (Lake City), Tenn. 
(ORN) 23-13 
Coal Creek Drainage and Levee District, Ill. (NCR) 
28-14, 28-16 
Coal Grove, Ohio (ORH) 25-20 
Coal River, W. Va. (ORH) 25-20 
Coan River, Va. (NAB) 4-37 
Coast of California, Point Mugu to San Pedro 
Breakwater, Calif. (SPL) 33-18 
Coastal Engineering Research Center (CERC) 45-1 
Coasters Island Harbor, R.I. (NED) 1-38 
Cobscook Bay, Maine (NED) 1-38 
Cocheco River, N.H. (NED) 1-38, 1-43 
Cochiti Lake, N. Mex. (SWA) 17-3, 17-8, 17-10 
Cochrane, Wis. (NCS) 27-27 
Cockrells Creek, Va. (NAO) 5-23 
Coeur D'Alene, Idaho (NPS) 38-26 
Cohansey River, N.J. (NAP) 3-2, 3-14, 3-15, 3-18 
Cohasset Harbor, Mass. (NED) 1-38 
Colchester, Conn. (NED) 1-22 
Cold Regions Research Engineering Laboratory 
(CRREL) 52-1 
Cold Spring Inlet, N.J. (NAP) 3-2, 3-15, 3-18, 
3-21 
Colebrook River Lake, Conn. (NED) 1-13, 1-28, 
1-48 
Colfax, Wash. (NPW) 39-2, 39-9, 39-11 
Colfax, Grant Parish, La. (LMN) (LMK) 11-16, 
12-18, 12-19 
Colliers, W. Va. (ORP) 26-28 
Collinsville, Ala. (SAM) 10-43 
Colonial Beach, Va. (NAB) 4-11, 4-24, 4-32 
Colorado River, Matagorda, Tex. (SWG) 15-11, 
15-27 
Colorado Springs, Colo. (Templeton Gap Floodway) 
(SWA) 17-7, 17-10 
Columbia, La. (LMK) 12-13, 12-16 
Columbia and Lower Willamette Rivers below 
Vancouver, Wash., and Portland, Oreg. (NPP) 
37-2, 37-24, 37-31, 37-45 
Columbia Drainage and Levee District No. 3, Ill. 
(LMS) 14-14 
Columbia Drainage District 1, Oreg. (NPP) 37-41, 
37-48 
Columbia River and Tributaries above Celilo Falls to 
Kennewick, Wash. (NPW) 39-14 
Columbia River at Baker Bay, Wash. (NPP) 37-4, 
37-24, 37-32 
Columbia River at the Mouth, Oreg. and Wash. 
(NPP) 37-4, 37-24, 37-32 
I-8

INDEX 
Columbia River Basin, Local Flood Protection 
Projects (NPW) 39-2, 39-11, 39-16 
Columbia River Basin, Local Protection Projects, 
Idaho, Mont., and Wash. (NPS) 38-26, 38-30 
Columbia River between Chinook, Wash., and Head 
of Sand Island (NPP) 37-4, 37-24, 37-32 
Columbia River between Vancouver, Wash., and The 
Dalles, Oreg. (NPP) 37-4, 37-24, 37-32 
Columbia River, Ilwaco, Wash. (NPP) 37-5, 37-24, 
37-33 
Columbia River Treaty Entities 49-2 
Columbia River Treaty Permanent Engineering 
Board 49-2 
Columbia River, Wenatchee to Kettle Falls, Wash. 
(NPS) 38-25 
Columbia Slough, Oreg. (NPP) 37-44 
Columbus, Nebr. (MRO) 21-20, 21-21 
Columbus, Ohio (ORH) 25-21 
Compo Beach, Westport, Conn. 1-42 
Conant Brook Dam, Mass. (NED) 1-13, 1-28, 1-48 
Conchas Lake, N. Mex. (SWA) 17-2, 17-8 
Concordia, Ky. (ORL) 24-21, 24-24 
Conemaugh River Lake, Pa. (ORP) 26-6, 26-14, 
26-18, 26-27 
Conesus Lake, Livonia, N.Y. (NCB) 32-16, 32-22 
Conetoe Creek, N.C. (SAW) 6-27 
Coney Island Channel, N.Y. (NAN) 2-33 
Coney Island Creek, N.Y. (NAN) 2-33, 2-37 
Coney Island Inlet, N.Y. (NAN) 2-34 
Conklin-Kirkwood, N.Y. (NAB) 4-19, 4-36, 4-39 
Conneaut Harbor, Ohio (NCB) 32-4, 32-18, 32-27 
Connecticut River (above Hartford), Conn. (NED) 
1-38 
Connecticut River Basin, Vt., N.H., Mass. and Conn. 
(NED) 1-11, 1-23, 1-48 
Connecticut River below Hartford, Conn. (NED) 
1-4, 1-25, 1-33, 1-45, 1-53 
Connecticut River, Comish, N.H. (NED) 1-23 
Connecticut River, North Stratford, N.H. (NED) 
1-23, 1-43 
Connecticut River, W. Stewartstown, N.H. (NED) 
1-43 
Connecticut River, Walpole, N.H. (NED) 1-23 
Connell, Wash. (NPW) 39-14 
Conoho Creek, N.C. (SAW) 6-28 
Consolidated Diking and Improvement District 1, 
Cowlitz County, Wash. (NPP) 37-40 
Construction Engineering Research Laboratory 
(CERL) 50-1 
Construction of Locks and Dams, Ohio River (ORD) 
22-1, 22-5, 22-6 
Contentnea Creek, N.C. (SAW) 6-25, 6-27, 6-28 
Conway County Drainage - Levee District No. 1, 
Arkansas River, Ark. (SWL) 18-17 
Conway County Levee District No. 6, Arkansas 
River, Ark. (SWL) 18-17 
Conway County Levee Districts Nos. 1, 2, - 8, 
Arkansas River, Ark. (SWL) 18-17 
Cook Inlet Shoals, Alaska (NPA) 40-13 
Cooper Lake and Channels, Tex. (LMN) (SWF) 
11-16, 16-5, 16-15, 16-19 
Cooper River, N.J. (NAP) 3-21 
Cooper River, Charleston Harbor, S.C. (SAN) 7-3, 
7-9, 7-12 
Cooper River, Pompion Hill Chapel, S.C. (SAN) 7-8, 
7-10, 7-14 
Cooper River Seismic Modification, S.C. (SAN) 7-4, 
7-9, 7-12 
Coordinating Committee on Great Lakes Basic 
Hydraulic and Hydrologic Data Board 31-30, 
49-2 
Coos and Millicoma Rivers, Oreg. (NPP) 37-6, 
37-25, 37-33 
Coos Bay, Oreg. (NPP) 37-5, 37-24, 37-33 
Coosa River Navigation, Ala. (SAM) 10-20, 10-30 
Copan Lake, Okla. (SWT) 19-3, 19-9, 19-14, 
19-17 
Copes Corner Lakes, New York (NAB) 4-37 
Coquille River, Oreg. (NPP) 37-6, 37-25, 37-33, 
37-44 
Coralville Lake, Iowa (NCR) 28-4, 28-8, 28-12 
Coraopolis, Pa. (ORP) 26-23 
Corbin, Ky. (ORN) 23-19 
Corbin (Lynn Camp Creek), Ky. (ORN) 23-13 
Cordell Hull Lock and Dam, Tenn. (ORN) 23-14 
Cordova Harbor, Alaska (NPA) 40-13 
Cordova Small Boat Harbor, Alaska (NPA) 40-2, 
40-8, 40-11 
Core Creek, N.C. (SAW) 6-27 
Corea Harbor, Maine (NED) 1-38 
Coming, N.Y. (NAB) 4-14, 4-25 
Coming-Monkey Run, N.Y. (NAB) 4-39 
Cornucopia Harbor, Wis. (NCE) 31-4, 31-33, 
31-46 
Corpus Christi, Tex., Channel to Navy Seaplane 
Base, Encinal Peninsula (SWG) 15-27 
Corpus Christi Beach, Tex. (Restoration Project) 
(SWG) 15-9, 15-14, 15-25 
Corpus Christi Ship Channel, Tex. (SWG) 15-3, 
15-13, 15-16, 15-28, 15-29, 15-34 
Corsica River, Md. (NAB) 4-33 
Corson Inlet and Ludlam Beach, N.J. (NAP) 3-23 
Corte Madera Creek, Calif. (SPK) (SPN) 34-3, 
35-6, 35-23, 35-28 
Cortland, N.Y. (NAB) 4-36, 4-39 
Cottage Grove Lake, Oreg. (NPP) 37-12, 37-27, 
37-36, 37-47, 37-49 
Cottonwood Creek, Calif. (SPK) 35-21, 35-27 
Cottonwood Creek Community Church, Idaho 
(NPW) 39-14 
Cottonwood Creek Dam, Boise, Idaho (NPW) 39-16 
Cottonwood River, Culdesac, Idaho (NPW) 39-17 
I-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Cottonwood Slough Pumping Plant, Ill. (LMN) 13-6 
Cotuit Harbor, Mass. (NED) 1-45 
Cougar Lake, Oreg. (NPP) 37-18, 37-28, 37-37, 
37-47, 37-49 
Council Bluffs, Iowa (MRO) 21-16, 21-19, 21-21 
Council Grove Lake, Kans. (SWT) 19-3, 19-9, 
19-14, 19-17 
County Road Bridge Over Leaf River, Miss. (SAM) 
10-14 
Courtenay Channel, Fla. (SAJ) 9-45, 9-46 
Cove Island, Stamford, Conn. (NED) 1-42 
Covered Bridge, Housatonic River, Sheffield, Mass. 
(NED) 1-17, 1-23, 1-30 
Covington, Ky. (ORL) 24-20, 24-24, 24-29 
Cow Castle Creek, S.C. (SAN) 7-8, 7-16 
Cow Creek Channel Improvement, Kans. (SWT) 
19-15 
Cowanesque Lake, Pa. (NAB) 4-17, 4-26 
Cowlitz County Consolidated Diking Improvement 
District 1, Wash. (NPP) 37-41, 37-44, 37-48 
Cowlitz County Diking Improvement Districts 2, 13, 
and 15, Wash. (NPP) 37-41, 37-48 
Cowlitz County Drainage Improvement District 1, 
Wash. (NPP) 37-41 
Cowlitz River, Wash. (NPP) 37-23, 37-39, 37-41 
Cowlitz River at Randle, Wash. (NPP) 37-44 
Cowpens Swamp, S.C. (SAN) 7-8, 7-16 
Coyote and Spencer Creeks, Oreg. (NPP) 37-44 
Coyote Creek, Calif. (SPK) 35-31 
Coyote Valley Dam (Lake Mendocino) and Channel 
Improvements, Calif. (SPK) 35-34, 35-35 
Crabtree Creek and Tributaries, Wake County, N.C. 
(SAW) 6-31 
Crabtree Swamp, S.C. (SAN) 7-8, 7-16 
Craig Harbor, Alaska (NPA) 40-13, 40-15 
Crane Creek Drainage and Levee District (NCR) 
28-14, 28-16 
Crane Creek State Park, Ohio (NCB) 32-39 
Cranes Creek, Va. (NAO) 5-4, 5-14, 5-18 
Crawford County Levee District, Arkansas River, 
Ark. (SWL) 18-17 
Creede, Willow Creek, Colo. (Floodway) (SWA) 
17-7 
Crescent City Harbor, Calif. (SPN) 34-5 
Criehaven Harbor, Maine (NED) 1-38 
Crisfield Harbor, Md. (NAB) 4-33, 4-38 
Crooked Creek Lake, Pa. (ORP) 26-6, 26-14, 
26-18, 26-27 
Crooked Creek Lake - Levee, Ark. (SWL) 18-17 
Cross-Florida Barge Canal (SAJ) 9-4, 9-25, 9-32, 
9-42, 9-43 
Cross Rip Shoals Nantucket Sound, Mass. (NED) 
1-38 
Crutcho Creek Channel Improvement, Okla. (SWT) 
19-15 
Crystal River, Fla. (SAJ) 9-45, 9-46 
Cucamonga Creek, Calif. (SPL) 33-3, 33-10, 
33-15 
Cuckold Creek, Md. (NAB) 4-37 
Cuivre River, Mo. (LMS) 14-13 
Cumberland, Ky. (ORN) 23-18 
Cumberland, Md., and Ridgeley, W. Va. (NAB) 4-12, 
4-24, 4-32, 4-39 
Cumberland River, Tenn. and Ky. (ORN) 23-2, 
23-9, 23-11, 23-15 
Cummings Park, Stamford, Conn. (NED) 1-42 
Cunninghill Cove, Md. (NAB) 4-37 
Current River, Ark. - Mo. (SWL) 18-16 
Curry Creek Dam and Lake, Ga. (SAS) 8-16 
Curwensville Lake, Pa. (NAB) 4-18, 4-26 
Cushman-Mapleton Channels Oreg. (NPP) 37-39 
Cuttyhunk Harbor, Mass. (NED) 1-38, 1-53 
Cuyahoga River Basin, Ohio (NCB) 32-37 
Cypress Bayou and Waterway between Jefferson, 
Tex., and Shreveport, La. (LMN) (LMK) 11-14, 
12-14 
Cypress Creek, Ky. (ORL) 24-30 
Cypress Creek, Md. (NAB) 4-33 
D 
Dade County, Fla. (SAJ) 9-18, 9-29, 9-40 
Dade County, North of Haulover Beach, Fla. (SAJ) 
9-19, 9-29, 9-40 
Dale Hollow Lake, Ohio River Basin, Tenn. and Ky. 
(ORN) 23-7, 23-9, 23-18 
Dallas Floodway, Tex. (SWF) 16-22 
Dam "A" Lake, Tex. (SWF) 16-13, 16-19 
Dam Neck Disposal Area, Va. (NAO) 5-25 
Dam Safety Program, New York District (NAN) 
2-20 
Damariscotta River, Maine (NED) 1-38 
Dana Point Harbor, Calif. (SPL) 33-18, 33-22 
Danbury, Conn. (NED) 1-22, 1-43, 1-50 
Dansville and Vicinity, N.Y. (NCB) 32-37 
Danville, Va. (SAW) 6-31 
Dardanelle Lock - Dam, Ark. (SWL) 18-8, 18-13, 
18-20 
Darien Harbor, Ga. (SAS) 8-16 
Dashields Locks and Dam, Pa. (ORD) 22-3, 22-7 
Data Collection and Management Division, 53-1 
Dauphin Island Bay, Ala. (SAM) 10-6, 10-27, 
10-34, 10-45 
Davenport, Iowa (NCR) 28-4, 28-8, 28-12 
Davenport Center Lake, N.Y. (NAB) 4-37 
Davenport Harbor, Iowa (Lindsay Park) (NCD) 
29-7 
David D. Terry Lock - Dam, Ark. (SWL) 18-2, 18-19 
Davids Creek Lake, Iowa (MRO) 21-16 
Davis, N.C. (SAW) 6-28 
Davis Creek, Va. (NAO) 5-23 
I-10

INDEX 
Day, John, Lock and Dam-Lake Umatilla, Oreg. and 
Wash. (NPP) 37-20, 37-28, 37-38, 37-51 
Day, John, River, Oreg. (NPP) 37-14, 37-27, 
37-36, 37-40, 37-44 
Days Creek Lake, Oreg. (NPP) 37-42 
Dayton, Ky. (ORL) 24-3, 24-14, 24-24, 24-29 
Dayton, Wash. (NPW) 39-14 
Dayton, Wyo. (MRO) 21-18 
Daytona Beach Side Channel, Fla. (SAJ) 9-45 
De Kalb, Ill. (NCR) 28-16 
Deadman's Gulch, Sturgis, S.D. (MRO) 21-17 
Deep Creek, N.C. (SAW) 6-27 
Deep Creek, Accomack Co., Va. (NAO) 5-23 
Deep Creek, Newport News, Va. (NAO) 5-23 
Deep Fork River, Okla. (SWT) 19-17 
Deep River, Wash. (NPP) 37-39 
Deep River Area, Wash. (NPP) 37-40 
Deer Creek Lake, Ohio (ORH) 25-4, 25-12, 25-16 
Deer Creek Prairie Levee, Ind. (ORL) 24-22, 24-25 
Deer Island Area, Oreg. (NPP) 37-40 
Deer Island Drainage District, Oreg. (NPP) 37-41, 
37-48 
Deer Island Thoroughfare, Maine (NED) 1-38 
Degognia and Fountain Bluff Levee and Drainage 
District, Ill. (LMS) 14-14 
DeGray Lake, Ark. (LMK) 12-16, 12-19 
DeKalb, Ill. (NCR) 29-16 
Delaware Coast Protection, Del. (NAP) 3-11, 3-17 
Delaware Lake, Ohio (ORH) 25-4, 25-12, 25-16 
Delaware River, Pa., N.J. and Del., Philadelphia to 
the Sea (NAP) 3-4, 3-15, 3-18 
Delaware River at Camden, N.J. (NAP) 3-21 
Delaware River at East Branch, N.Y. (NAP) 3-13 
Delawiare River at Pennsville, N.J. (NAP) 3-21 
Delaware River between Philadelphia, Pa., and 
Trenton, N.J. (NAP) 3-3, 3-15, 3-18 
Deleware River, Mouth of Neversink (NAP) 3-24 
Delphi, Ind. (ORL) 24-20, 24-24, 24-29 
Denison Dam-Lake Texoma, Tex. and Okla. (SWT) 
19-13 
Dennis Creek, N.J. (NAP) 3-21 
Depere Lock and Dam, Wis. (NCE) 31-60 
Depoe Bay, Oreg. (NPP) 37-7, 37-25, 37-33, 
37-39, 37-42, 37-45 
Dequeen Lake, Ark. (SWL) 18-5, 18-11, 18-23 
Derby, Conn. (NED) 1-22, 1-43, 1-50 
Derby, Ind. (ORL) 24-22, 24-25 
Des Moines, Iowa (NCR) 28-14, 28-16 
Des Moines and Mississippi Levee District No. 1, 
Mo. (NCR) 28-14, 28-16 
Des Moines Recreational River and Greenbelt, Iowa 
(NCR) 28-4, 28-8, 28-12 
Deschutes River, Wash. (NPS) 38-26 
Detour Harbor, Mich. (NCE) 31-4, 31-34, 31-47 
Detroit Lake, Oreg. (NPP) 37-19, 37-28, 37-37, 
37-47, 37-49 
Detroit River, Mich. (NCE) 31-5, 31-34, 31-47, 
31-58, 31-63 
Devils Lake, N. Dak. (NCS) 27-5, 27-19 
Devil's Swamp, La. (MR+T) 42-5, 42-29 
Dewey Lake, Ky. (ORH) 25-4, 25-13, 25-16 
Dickey Lake, Maine (NED) 1-45 
Dickinson Bayou, Tex. (SWG) 15-27 
Dierks Lake, Little River Basin, Ark. (SWL) 18-5, 
18-12, 18-23 
Diking and Improvement District 4, Wahlkiakum 
County, Wash. (NPP) 37-40 
Diking and Improvement District 5, Cowlitz County, 
Wash. (NPP) 37-40 
Diking and Improvement District 11, Cowlitz 
County, Wash. (NPP) 37-41 
Diking Districts 1 and 3 (Puget Island) and Little 
Island, Wash. (NPP) 37-40 
Diking Districts 2, 3, and 5, Clatsop County, Oreg. 
(NPP) 37-40 
Diking Improvement District 1, Pacific County, 
Wash. (NPP) 37-40 
Diking Improvement Districts 2 and 13, Cowlitz 
County, Wash. (NPP) 37-41 
Dillingham Emergency Bank Stabilization, Alaska 
(NPA) 40-5, 40-9, 40-12 
Dillingham Harbor, Alaska (NPA) 40-2, 40-8, 
40-11, 40-15 
Dillon Lake, Ohio (ORH) 25-4, 25-13, 25-16 
Dillonvale, Ohio (Short Creek) (ORP) 26-23 
Dismal Swamp Canal (Deep Creek), Va. (NAO) 
5-22 
Dismal Swamp Canal (South Mills, N.C.) (NAO) 
5-22 
Dively Drainage - Levee District, Ill. (LMS) 14-14 
Dodge City, Kans. (SWT) 19-17 
Dog and Fowl Rivers, Ala. (SAM) 10-7, 10-27, 
10-34 
Doheny Beach State Park (Doheny State Beach), 
Calif. (SPL) 33-19 
Dorchester Bay and Neponset River, Mass. (NED) 
1-38 
Dorena Lake, Oreg. (NPP) 37-12, 37-27, 37-36, 
37-47, 37-49 
Double Bayou, Tex. (SWG) 15-27 
Double Creek, N.J. (NAP) 3-21 
Douglas Harbor, Alaska (NPA) 40-13 
Dover, Ky. (ORH) 25-20 
Downeyville Lake, Ind. (ORL) 24-21, 24-28 
Drainage District 1, Clatsop County, Oreg. (NPP) 
37-40 
Dresden Island Lock and Dam, Ill. (NCC) 28-20, 
28-21 
Drinkwater Sewer, Mo. (LMM) 13-6 
Drum Inlet, N.C. (SAW) 6-25 
Drury Drainage District, Ill. (NCR) 28-14, 28-16 
Dry Creek, Wash. (NPW) 39-14 
I-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Dry Creek, Hawarden, Iowa (MRO) 21-17 
Dry Creek (Warm Springs) Lake and Channel 
Improvements, Calif. (SPK) 35-24, 35-34, 35-35 
Dry Fork and East Fork Lakes, Mo. (MRK) 20-17 
Dry Pass, Alaska (NPA) 40-13, 40-15 
Dry Run, Iowa (NCS) 27-24 
Dubois, Pa. (ORP) 26-22, 26-28 
Dubuque, Iowa (NCR) 28-14, 28-16 
Dubuque Harbor, Iowa (NCD) 29-7 
Duck Creek, Calif. (SPK) 35-31 
Duck Creek Channel Improvement, Tex. (SWF) 16-22 
Duck Island Harbor, Conn. (NED) 1-38, 1-53 
Duck Point Cove, Md. (NAB) 4-34 
Duck River, Tenn. (ORN) 23-13 
Duluth-Superior Harbor, Minn. and Wis. (NCE) 
31-5, 31-34, 31-47 
Dune Road, Southampton, N.Y. (NAN) 2-40 
Dungeness River, Wash. (NPS) 38-8, 38-16, 
38-22, 38-26 
Dunkirk Harbor, N.Y. (NCB) 32-5, 32-19, 32-28 
Dunn Branch, Woodbine, Camden County, Ga. 
(SAS) 8-7, 8-16 
Duval County, Fla. (SAJ) 9-19, 9-29, 9-40 
Duxbury Harbor, Mass. (NED) 1-38 
Dworshak Dam and Reservoir, Idaho (NPW) 39-4, 
39-9, 39-12, 39-18 
Dyersburg, Tenn. (LMM) 13-6 
Dyersburg, Tenn. (Southwest) (LMM) 13-6 
Dymers Creek, Va. (NAO) 5-23 
E 
Eagle Bay and Fort Yates Highway Bridges, N. Dak. 
(MRO) 21-17 
Eagle Creek, S.C. (SAN) 7-7, 7-8, 7-10, 7-14 
Eagle Creek Lake, Ky. (ORL) 24-21 
Eagle Creek Reservoir, Ohio (ORP) 26-22, 26-27 
Eagle Harbor, Mich. (NCE) 31-62 
East Barre Dam, Vt. (NAN) 2-36 
East Bay (Hanna Reef), Tex. (SWG) 15-27 
East Bay Small Boat Basin, Olympia, Wash. (NPS) 
38-25 
East Boothbay Harbor, Maine (NED) 1-38 
East Branch, Clarion River Lake, Pa. (ORP) 26-6, 
26-14, 26-18, 26-27 
East Branch Dam, Conn. (NED) 1-22, 1-43, 1-49 
East Brimfield Lake, Mass. (NED) 1-21, 1-31, 1-52 
East Canada Creek, Dolgeville, N.Y. (NAN) 2-39 
East Cape Girardeau and Clear Creek Drainage 
District, Ill. (LMS) 14-14 
East Chester Creek, N.Y. (NAN) 2-34 
East Fork, Tex. (SWF) 16-22 
East Fork of Boyer River, Near Vail, Iowa (MRO) 
21-21 
East Hartford, Conn. (NED) 1-22, 1-43, 1-49 
East Liverpool Drainage and Levee District (NCR) 
28-14, 28-16 
East Lynn Lake, W. Va. (ORH) 25-5, 25-13, 25-17 
East Moline, Ill. (NCR) 28-14, 28-16 
East Muddy and Lake Creek, Oreg. (NPP) 37-44 
East Muddy Creek, Mo. (MRK) 20-17 
East Nishnabotna River, Near Griswold, Iowa 
(MRO) 21-21 
East Nishnabotna River, Page Co. Bridge, Near 
Essex, Iowa (MRO) 21-21 
East Nishnabotna River, Red Oak, Iowa (MRO) 
21-3, 21-10, 21-13, 21-21 
East Pass Channel from Gulf of Mexico into 
Choctawhatchee Bay, Fla. (SAM) 10-7, 10-27, 
10-34 
East Peoria Drainage and Levee District (NCR) 
28-14, 28-16 
East Peoria Sanitary District, Ill. (NCR) 28-16 
East Point, La. (LMN) (LMK) 11-16, 12-19 
East Poplar Bluff - Poplar Bluff, Mo. (SWL) 18-17 
East Rainelle, W. Va. (ORH) 25-20, 25-22 
East River, N.Y. (NAN) 2-34 
East Rockaway (DEBS) Inlet, N.Y. (NAN) 2-37 
East Rockaway Inlet, N.Y. (NAN) 2-4, 2-22, 2-27 
East Rockaway Inlet to Rockaway Inlet and Jamaica 
Bay, N.Y. (Part I) (NAN) 2-16, 2-25, 2-31 
East Rockaway Inlet to Rockaway Inlet and Jamaica 
Bay, N.Y. (Part II) (NAN) 2-36 
East Sidney Lake, N.Y. (NAB) 4-15, 4-25 
East St. Louis and Vicinity, Ill. (LMS) 14-3, 14-9, 
14-11 
East Weaver Creek, Calif. (SPK) 35-31 
East, West and Duwamish Waterways, Seattle 
Harbor, Wash. (NPS) 38-12 
Eastchester Creek, N.Y. (NAN) 2-33 
Eastern Branch, Va. (NAO) 5-20 
Eastern Rapides and South-Central Avoyelles 
Parishes, La. (MR+T) 42-15, 42-28, 42-50, 
42-59 
Eastlake, Ohio (NCB) 32-37 
Eastman, H. V., Lake, Calif. (SPK) 35-4, 35-23 
Eastport Harbor, Maine (NED) 1-38 
Eau Galle River, Wis. (NCS) 27-6, 27-19 
Eau Gallie Harbor, Fla. (SAJ) 9-5, 9-25, 9-32 
Echo Bay Harbor, N.Y. (NAN) 2-34 
Edenton Harbor, N.C. (SAW) 6-25 
Edgar Jadwin, General, Dam and Reservoir, Pa. 
(NAP) 3-13, 3-17 
Edgartown Harbor, Mass. (NED) 1-38 
Edisto River, S.C. (SAN) 7-8, 7-15, 7-16 
Edisto River, North Fork, S.C. (SAN) 7-16 
Edisto River, Vicinity Canadays Landing, S.C. (SAN) 
7-16 
Ediz Hook, Wash. (NPS) 38-2, 38-14, 38-19 
Edmonds Harbor, Wash. (NPS) 38-2, 38-14, 
38-19 
I-12

INDEX 
Edward MacDowell Lake, N.H. (NED) 1-18, 1-30, 
1-51 
Eel River, Calif. (SPK) 35-31 
Eel River, Ind. (ORL) 24-30 
Egegik River, Alaska (NPA) 40-13 
Eight Mile Creek, Ark. (MR+T) 42-28 
Eighteen Mile Island, Ky. (ORL) 24-30 
El Dorado, Kans., W. Br., Walnut River, Channel 
Improvement (SWT) 19-15 
El Dorado Lake, Kans. (SWT) 19-4, 19-10, 19-14, 
19-17 
El Paso, Tex. (SWA) 17-2, 17-8, 17-9 
El Tuque Beach, P.R. (SAJ) 9-47 
Eldred, Pa. (ORP) 26-28 
Eldred and Spankey Drainage and Levee District, Ill. 
(LMS) 14-3, 14-9, 14-11 
Eldrid, Ill. (LMS) 14-14 
Elfin Cove, Alaska (NPA) 40-13 
Elizabeth, N.J. (NAN) 2-37 
Elizabeth River, Hillside, N.J. (NAN) 2-39 
Elizabethtown, Ill. (ORL) 24-22, 24-25 
Elk and Little Elk Rivers, Md. (NAB) 4-34 
Elk City Lake, Kans. (SWL) (SWT) 18-22, 19-4, 
19-10, 19-14, 19-16, 19-17 
Elk Creek, Clyde, Kans. (MRK) 20-17 
Elk Creek Harbor, Pa. (NCB) 32-35 
Elk Creek Lake, Oreg. (NPP) 37-12, 37-27, 37-36 
Elk River, Ala. and Tenn. (ORN) 23-13 
Elk River, Minn. (NCS) 27-24 
Elk River, W. Va. (ORH) 25-19 
Elkhorn River, Q Street Bridge, near Gretna, Nebr. 
(MRO) 21-20 
Elkhorn River, Ray Bridge, near Norfolk, Nebr. 
(MRO) 21-20 
Elkins, W. Va. (ORP) 26-4, 26-13, 26-18, 26-26 
Elkland, Pa. (NAB) 4-36, 4-39 
Elkport, Iowa (NCR) 28-14, 28-16 
Ellerbe Creek, Durham County, N.C. (SAW) 6-27 
Ellicott Creek, N.Y. (NCB) 32-14, 32-22 
Ellis Swamp, Gates County, N.C. (SAW) 6-27 
Elm Creek, Nebr. (MRO) 21-21 
Elm Fork Floodway, Tex. (SWF) 16-6, 16-15, 16-19 
Elmira, N.Y. (NAB) 4-15, 4-25 
Elochoman Slough, Wash. (NPP) 37-39 
Elwha River, Wash. (NPS) 38-26 
Emergency Bank Protection Activities 
Alaska District (NPA) 40-6 
Albuquerque, N. Mex., District (SWA) 17-7 
Buffalo, N.Y., District (NCB) 32-38 
Chicago, Ill., District (NCC) 30-7 
Detroit, Mich., District (NCE) 31-25 
Huntington, W. Va., District (ORH) 25-11 
Kansas City, Mo., District (MRK) 20-7 
Little Rock, Ark., District (SWL) 18-5 
Los Angeles, Calif., District (SPL) 33-8 
Louisville, Ky., District (ORL) 24-13, 24-31 
Nashville, Tenn., District (ORN) 23-19 
New England Division (NED) 1-23 
Omaha, Neb., District (MRO) 21-7 
Philadelphia, Pa., District (NAP) 3-12 
Pittsburgh, Pa., District (ORP) 26-29 
Portland, Oreg., District (NPP) 37-13 
Rock Island, Ill., District (NCR) 28-18 
Sacramento, Calif., District (SPK) 35-19 
San Francisco, Calif., District (SPN) 34-4 
St. Louis, Mo., District (LMS) 14-8, 14-14 
St. Paul, Minn., District (NCS) 27-28 
Tulsa, Okla., District (SWT) 19-19 
Vicksburg, Miss., District (LMK) 12-8 
Walla Walla, Wash., District (NPW) 39-2 
Emergency Flood Control Activities 
Alaska District (NPA) 40-6 
Albuquerque, N. Mex., District (SWA) 17-7 
Baltimore, Md., District (NAB) 4-19 
Buffalo, N.Y., District (NCB) 32-38 
Charleston, S.C., District (SAN) 7-16 
Chicago, Ill., District (NCC) 30-7 
Detroit, Mich., District (NCE) 31-28 
Fort Worth, Tex., District (SWF) 16-12 
Galveston, Tex., District (SWG) 15-12 
Huntington, W. Va., District (ORH) 25-11 
Jacksonville, Fla., District (SAJ) 9-24 
Kansas City, Mo., District (MRK) 20-7 
Little Rock, Ark., District (SWL) 18-5 
Los Angeles, Calif., District (SPL) 33-8 
Louisville, Ky., District (ORL) 24-13 
Memphis, Tenn., District (LMM) 13-3 
Mobile, Ala., District (SAM) 10-18 
New England Division (NED) 1-23 
New Orleans District (LMN) 11-9 
New York District (NAN) 2-20 
Norfolk, Va., District (NAO) 5-12 
Omaha, Neb., District (MRO) 21-6 
Philadelphia, Pa., District (NAP) 3-12 
Portland, Oreg., District (NPP) 37-13 
Rock Island, Ill., District (NCR) 28-19 
Sacramento, Calif., District (SPK) 35-19 
San Francisco, Calif., District (SPN) 34-4 
Savannah, Ga., District (SAS) 8-7 
Seattle, Wash., District (NPS) 38-32 
St. Louis, Mo., District (LMS) 14-8 
St. Paul, Minn., District (NCS) 27-28 
Tulsa, Okla., District (SWT) 19-19 
Vicksburg, Miss., District (LMK) 12-8 
Walla Walla, Wash., District (NPW) 39-2 
Wilmington, N.C., District (SAW) 6-14 
Emergency protection for highway and railroad 
facilities at Chester, Ill., bridge (LMS) 14-14 
Emergency protection for Illinois approach, Chain 
of Rocks Bridge (LMS) 14-14 
Emergency repairs to levees on Mississippi, Illinois 
and Kaskaskia Rivers (LMS) 14-14 
I-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Emergency Streambank and Shoreline Protection 
Detroit, Mich., District (NCE) 31-25 
Jacksonville, Fla., District (SAJ) 9-24 
Little Rock, Ark., District (SWL) 18-5 
Mobile, Ala., District (SAM) 10-18 
New York, N.Y., District (NAN) 2-20 
Pittsburgh, Pa., District (ORP) 26-29 
Tulsa, Okla., District (SWT) 19-19 
Emerson, Indian Creek, Mills County, Iowa (MRO) 
21-21 
Empire-Stratton, Ohio (ORP) 26-22, 26-26 
Emsworth Locks and Dam, Pa. (ORD) 22-2, 22-7 
Enderlin, N. Dak. (NCS) 27-6, 27-19 
Endicott-Johnson City and Vestal, N.Y. (NAB) 
4-36, 4-39 
Engineer Topographic Laboratories (ETL) 51-1 
England Pond Levee, Ill. (ORL) 24-20, 24-24, 
24-29 
English, Ind. (ORL) 24-20, 24-30 
Enid, Okla. (SWT) 19-15, 19-17, 19-18 
Enid Lake, Miss. (MR+T) 42-20, 42-59 
Entiat River, Wash. (NPS) 38-26 
Ephraim Canyon Wash, Nogales, Ariz. (SPL) 33-25 
Erie Harbor, Pa. (NCB) 32-5, 32-19, 32-28, 
32-39 
Escambia and Conecuh Rivers, Fla. and Ala. (SAM) 
10-42, 10-45 
Esopus Creek, Ulster, N.Y. (NAN) 2-39 
Esquatzel Coulee, Wash. (NPW) 39-14, 39-16 
Essex River, Mass. (NED) 1-38 
Estes, Carl L., Dam and Lake, Tex. (SWF) 16-22 
Euclid Creek, Cleveland, Ohio (NCB) 32-17, 32-22 
Eufaula Lake, Okla. (SWL) (SWT) 18-22, 19-7, 
19-12, 19-14, 19-16, 19-17 
Evansdale, Iowa (NCR) 28-14, 28-16 
Evanston, Ill. (NCC) 30-15 
Evansville, Ind. (ORL) 24-3, 24-14, 24-24, 24-29 
Everett Harbor and Snohomish River, Wash. (NPS) 
38-3, 38-14, 38-19 
Everglades Harbor, Fla. (SAJ) 9-46 
Exeter River, N.H. (NED) 1-38 
Existing levees and extensions from Bastrop, La. to 
mouth of Boeuf River (LMK) 12-16 
F 
Fabius River Drainage District, Mo. (NCR) 28-14, 
28-16 
Factory Brook, Middlefield, Mass. (NED) 1-23 
Fair Haven Beach State Park, N.Y. (NCB) 32-36 
Fairbanks, Tanana River and Chena Slough, Alaska 
(NPA) 40-14 
Fairbury, Nebr. (MRK) 20-17 
Fairfield Vicinity Streams, Calif. (SPK) 35-7, 35-23 
Fairport Harbor, Ohio (NCB) 32-5, 32-19, 32-29 
Fajardo Harbor, P.R. (SAJ) 9-46 
Fall Brook Lake, Pa. (NAB) 4-37 
Fall Creek Lake, Oreg. (NPP) 37-13, 37-27, 37-36, 
37-47, 37-49 
Fall of the Ohio National Wildlife Conservation Area 
(ORD) 22-3 
Fall River Basin, S. Dak. (MRO) 21-3, 21-10, 
21-13 
Fall River Harbor, Mass. (NED) 1-38 
Fall River Lake, Kans. (SWL) (SWT) 18-22, 19-4, 
19-10, 19-14, 19-16, 19-17 
Falling Creek, Rockingham, N.C. (SAW) 6-31 
Falls Lake, N.C. (SAW) 6-12, 6-15, 6-20 
Falmouth Harbor, Mass. (NED) 1-38 
Falmouth Lake, Ky. (ORL) 24-21, 24-27 
Falulah Brook, Fitchburg, Mass. (NED) 1-23 
Fancy Bluff Creek, Ga. (SAS) 8-16 
Far Creek, N.C. (SAW) 6-25 
Fargo, N. Dak. (NCS) 27-27 
Farm Creek, Ill. (NCR) 28-5, 28-8, 28-12 
Farmers Levee and Drainage District (NCR) 28-14, 
28-15, 28-16 
Farmington, N.H. (NED) 1-22 
Faulkner County Levee District No. 1, Arkansas 
River, Ark. (SWL) 18-17 
Feather River, Calif. (SPK) 35-30 
Federal Energy Regulatory Commission (FERC) 
47-1 
Federal Energy Regulatory Commission Licenses at 
Locks and Dams, Ohio River (ORD) 22-6 
Federal Prison Creek, Ga. (SAS) 8-7 
Felsenthal, Ark. (LMK) 12-13 
Ferguson Creek, Oreg. (NPP) 37-44 
Fern Ridge Lake, Oreg. (NPP) 37-13, 37-27, 
37-36, 37-47, 37-49 
Fernandina Harbor, Fla. (SAJ) 9-5, 9-26, 9-32 
Ferrells Bridge Dam-Lake O' The Pines, Tex. 
(LMN) (SWF) 11-16, 16-6, 16-15, 16-19 
Filberts Creek, N.C. (SAW) 6-27 
Fire Island Inlet to Jones Inlet, N.Y. (NAN) 2-4, 
2-22, 2-27, 2-36 
Fire Island Inlet to Montauk Point, N.Y. (NAN) 
2-36 
Fisher, O. C., Dam and Lake, Tex. (SWF) 16-9, 
16-16, 16-20 
Fisherman's Wharf Area, San Francisco Harbor, 
Calif. (SPN) 34-1, 34-5, 34-8 
Fishing Bay, Md. (NAB) 4-34 
Fishing Creek, Md. (NAB) 4-5, 4-22, 4-29 
Fishing Creek, N.C. (SAW) 6-25 
Fishing Creek, Pine Grove, W. Va. (ORH) 25-22 
Fishtrap Lake, Ky. (ORH) 25-5, 25-13, 25-17 
Fitchburg, Mass. (NED) 1-22, 1-43 
Fivemile River Harbor, Conn. (NED) 1-38, 1-45 
Flannagan, John W., Dam and Reservoir, Va. (ORH) 
25-6, 25-13, 25-17 
1-14

INDEX 
Flat Creek, Oreg. (NPP) 37-44 
Flat Rock Creek Channel Improvement, Tulsa, Okla. 
(SWT) 19-15, 19-17, 19-18 
Flathead River, Mont. (NPS) 38-25, 38-26, 38-27 
Fletcher and Sunshine Gardens Levee, Ind. (ORL) 
24-22, 24-25 
Floating Breakwater Prototype Test Program, 
Seattle, Wash. (NPS) 38-25 
Flood Control and Coastal Emergency Activities 
Buffalo, N.Y., District (NCB) 32-38 
Huntington, W.Va., District (ORH) 25-11 
Pittsburgh, Pa., District (ORP) 26-12 
Tulsa, Okla., District (SWT) 19-19 
Flood Damage Prevention Studies, Tulsa, Okla., 
District (SWT) 19-20 
Flood Insurance Activities 
Detroit, Mich., District (NCE) 31-31 
Los Angeles, Calif., District (SPL) 33-8 
Sacramento, Calif., District (SPK) 35-19 
Flood Insurance Studies and Flood Hazard 
Information Reports, Mobile, Ala., District (SAM) 
10-49 
Floodwall and Levees at Portland, Oreg. (NPP) 
37-44 
Florence Levee, Kans. (SWT) 19-15, 19-17, 
19-18 
Floyd River, Sioux City, Iowa (MRO) 21-17 
Flushing Bay and Creek, N.Y. (NAN) 2-33, 2-34 
Fly Creek, Ala. (SAM) 10-7, 10-27, 10-35, 10-45 
Follansbee, W. Va. (ORP) 26-23 
Folly Brook, Wethersfield, Conn. (NED) 1-43, 
1-49 
Folly River, S.C. (SAN) 7-4, 7-9, 7-12 
Folsom Lake, Calif. (SPK) 35-31 
Forest Heights, Md. (NAB) 4-36, 4-39 
Forestville, Mich. (NCE) 31-62 
Forked Deer River, Tenn., including South Fork 
(LMM) 13-5 
Forsyth, Mont. (MRO) 21-17, 21-19 
Fort Chartres and Ivy Landing Drainage District No. 
5 and Stringtown Drainage and Levee District No. 
4, Ill. (LMS) 14-14 
Fort Cobb Reservoir, Okla. (SWT) 19-18 
Fort Fisher and Vicinity, N.C. (SAW) 6-17, 6-26 
Fort Gibson Lake, Okla. (SWL) (SWT) 18-22, 19-7, 
19-12, 19-14, 19-16, 19-17 
Fort Kent, Maine (NED) 1-22, 1-43 
Fort Leavenworth, Kans., Bridge Removal (MRK) 
20-16 
Fort Loudon Lock and Dam, Tenn. (ORN) 23-17 
Fort Macon State Park, N.C. (SAW) 6-26 
Fort Madison Harbor, Iowa (NCD) 29-7 
Fort Myers Beach, Fla. (SAJ) 9-5, 9-26, 9-33 
Fort Niagara State Park, N.Y. (NCB) 32-36 
Fort Peck Lake, Mont. (MRO) 21-7, 21-12, 21-15, 
21-19 
Fort Pierce, Fla. (SAJ) 9-20, 9-29, 9-40 
Fort Pierce Harbor, Fla. (SAJ) 9-6, 9-26, 9-33 
Fort Randall Dam-Lake Francis Case, S. Dak. 
(MRO) 21-8, 21-12, 21-16, 21-19 
Fort Scott Lake, Kans. (MRK) 20-17, 20-19 
Fort Smith, Arkansas River, Ark. (SWL) 18-17 
Fort Supply Lake, Okla. (SWT) 19-4, 19-10, 
19-14, 19-17 
Fort Trumbull Beach, Milford, Conn. (NED) 1-23 
Fort Worth Floodway (Clear Fork), Tex. (SWF) 
16-22 
Fort Worth Floodway (West Fork), Tex. (SWF) 
16-22 
Foss Reservoir, Okla. (SWT) 19-18 
Foster Creek Road, Wash. (NPS) 38-26 
Foster Joseph Sayers Dam, Pa. (NAB) 4-18, 4-26 
Foster Lake, Oreg. (NPP) 37-47 
Four Pole Creek, W. Va. (ORH) 25-22 
Four River Basins, Fla. (SAJ) 9-23, 9-30, 9-41, 
9-52 
Fourche Creek, Little Rock, Ark. (SWL) 18-17 
Fourmile Run, Va. (NAB) 4-36, 4-39 
Fowl River, Ala. (SAM) 10-45 
Fox Point Hurricane Barrier, R.I. (NED) 1-23, 
1-43 
Fox River, Wis. (NCE) 31-6, 31-34, 31-48 
Fox River Locks and Dams, Wis. (NCE) 31-60 
Francis E. Walter Dam, Pa. (NAP) (NAB) 3-12, 
3-17, 4-21 
Frankfort, Kans. (MRK) 20-17 
Frankfort, Ky. (ORL) 24-20, 24-21, 24-24, 24-29 
Frankfort Harbor, Mich. (NCE) 31-6, 31-34, 
31-48 
Franklin Falls Dam, N.H. (NED) 1-19, 1-30, 1-51 
Franklin, W. P., Lock and Dam, Fla. (SAJ) 9-48 
Frazer-Wolf Point, Mont. (MRO) 21-17 
Frazeysburg, Ohio (ORH) 25-21 
Freeport, Ill. (NCR) 28-15 
Freeport, Pa. (ORP) 26-23 
Freeport and Vicinity, Tex. Hurricane-Flood 
Protection (SWG) 15-11, 15-27 
Freeport Harbor, Tex. (SWG) 15-3, 15-13, 15-18, 
15-28, 15-29, 15-34 
Fremont, Ohio (NCB) 32-37 
French Broad and Little Pigeon Rivers, Tenn. (ORN) 
23-13 
Frenchboro Harbor, Maine (NED) 1-38 
Freshwater Bayou, La. (LMN) 11-14 
Friday Harbor Marina, Wash. (NPS) 38-25 
Friendly, W. Va. (ORH) 25-21 
Friendsville, Md. (ORP) 26-22, 26-28 
From North Little Rock to Gillett, Ark. (Above Plum 
Bayou) (SWL) 18-17 
Fullerton, Ky. (ORH) 25-20 
Fullerton Dam, Calif. (SPL) 33-24 
Fulton, Ill. (NCR) 28-14, 28-16 
I-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
G 
Galax, Va. (ORH) 25-20, 25-22 
Galena, Ill. (NCR) 28-14, 28-17 
Galena Emergency Bank Stabilization, Alaska (NPA) 
40-6, 40-9, 40-12 
Galisteo Dam, N. Mex. (SWA) 17-4, 17-8 
Gallipolis Locks and Dam, W. Va. (ORD) 22-3, 
22-8 
Gallipolis, Ohio (ORH) 25-21 
Galveston Harbor and Channel, Tex. (SWG) 15-4, 
15-13, 15-19, 15-28, 15-29, 15-34 
Galveston Seawall Extension, Tex. (SWG) 15-11 
Gapway Swamp, N.C. and S.C. (SAN) (SAW) 6-27, 
7-8, 7-16 
Gardner, Mass. (NED) 1-22, 1-43, 1-49 
Gardners Creek, N.C. (SAW) 6-27 
Garland City, Ark. (LMN) (LMK) 11-16, 12-17, 
12-19 
Garnett Lake, Kans. (MRK) 20-18, 20-19 
Garrison Dam-Lake Sakakawea, N. Dak. (MRO) 
21-8, 21-12, 21-16, 21-19 
Gasconade River, Mo. (MRK) 20-16 
Gastineau Channel, Alaska (NPA) 40-13 
Gate Creek Lake, Oreg. (NPP) 37-42, 37-49 
Gathright Dam and Lake Moomaw, Va. (NAO) 5-10, 
5-16, 5-21 
Gauley River, W. Va. (ORH) 25-19 
Gavins Point Dam-Lewis and Clark Lake, Nebr. and 
S. Dak. (MRO) 21-8, 21-12, 21-16, 21-18, 
21-19 
Gaysville Lake, Vt. (NED) 1-45 
Genegantslet Lake, N.Y. (NAB) 4-37 
General Edgar Jadwin Dam and Reservoir, Pa. 
(NAP) 3-13, 3-17 
General Joe Wheeler Dam (ORN) 23-17 
Geneva-On-The-Lake, Ohio (NCB) 32-6, 32-19, 
32-35 
Genoa Sewer Facility, N.C. (SAW) 6-27 
Geographic Systems Laboratory 51-1 
George Street, Keene, N.H. (NED) 1-23 
George, Walter F., Lock and Dam, Ala. and Ga. 
(SAM) 10-24, 10-31, 10-41 
George W. Andrews Lock and Dam, Ala. and Ga. 
(SAM) 10-22, 10-30, 10-41 
Georges River, Maine (NED) 1-38 
Georgetown Harbor, S.C. (SAN) 7-4, 7-9, 7-12 
Gering Valley, Nebr. (MRO) 21-17, 21-20 
Gila River Basin, Ariz. (SPL) 33-4, 33-11, 33-19 
Giles Creek, Elkhorn, Nebr. (MRO) 21-18 
Gill Township Levee, Ind. (ORL) 24-20, 24-29 
Gillham Lake, Ark. (SWL) 18-5, 18-12, 18-23 
Gill's Creek, Lancaster, S.C. (SAN) 7-17 
Girty's Run, Millvale, Pa. (ORP) 26-4, 26-13 
Glasgow, Mont. (MRO) 21-17, 21-19 
Gleason Creek, Nev. (SPK) 35-31 
Glen Cove Creek, N.Y. (NAN) 2-5, 2-22, 2-27 
Glen Cove Harbor, N.Y. (NAN) 2-37 
Gloucester Harbor and Annisquam River, Mass. 
(NED) 1-38, 1-46, 1-53 
Goat Island, Ga. and S.C. (SAS) 8-17 
Golconda, Ill. (ORL) 24-20, 24-24, 24-29 
Gold Creek, Alaska (NPA) 40-14 
Goldsboro, Neuse River, N.C. (SAW) 6-27 
Goleta, Calif., and Vicinity (SPL) 33-8, 33-20 
Goodfood Creek, Miss. (SAM) 10-14, 10-28, 
10-39 
Gooding Area, Idaho (NPW) 39-14 
Goose Creek, Md. (NAB) 4-34 
Gordons Creek, Hattiesburg, Miss. (SAM) 10-43 
Gordons Landing, Lake Champlain, Vt. (NAN) 2-34 
Goshen Creek, N.J. (NAP) 3-21 
Governor's Run, Md. (NAB) 4-37 
Gowanus Creek Channel, N.Y. (NAN) 2-34 
Grafton, N. Dak. (NCS) 27-24 
Grafton Small Boat Harbor, Ill. (LMS) 14-13 
Grahn, Ky. (ORH) 25-22 
Grand Bayou Pass, La. (LMN) 11-14 
Grand Calumet River Lock, Ind. (NCC) 28-21 
Grand Forks, N. Dak. (NCS) 27-27 
Grand Haven Harbor and Grand River, Mich. (NCE) 
31-7, 31-35, 31-48, 31-63 
Grand Isle and Vicinity, La. (LMN) 11-5, 11-10, 
11-12 
Grand Lake O' the Cherokees, Okla. (SWT) 19-7, 
19-12, 19-14, 19-16, 19-18 
Grand Marais Harbor, Mich. (NCE) 31-61, 31-62 
Grand Marais Harbor, Minn. (NCE) 31-7, 31-35, 
31-48 
Grand Prairie, Tex., Sanitary Landfill (SWF) 16-6, 
16-15, 16-19 
Grand Prairie, Tex., Streambank Erosion at Meyers 
Road (SWF) 16-6, 16-15, 16-19 
Grand Prairie-Bayou Meto, Ark., (MR+T) 42-16, 
42-28, 42-52 
Grand River, Grandville, Mich. (NCE) 31-63 
Grand River, Lansing, Mich. (NCE) 31-63 
Grand Tower Drainage and Levee District, Ill. (LMS) 
14-14 
Grand Traverse Bay Harbor, Mich. (NCE) 31-62 
Grande Ronde Lake, Oreg. (NPW) 39-14 
Grande Ronde Valley, Oreg. (NPW) 39-14, 39-16 
Grandview, Ind. (ORL) 24-22, 24-25 
Grandview Bay Harbor, N.Y. (NCB) 32-39 
Granger, Tex. (SWF) 16-17 
Grant Parish, Below Colfax, La. (LMN) (LMK) 
11-16, 12-18, 12-19 
Grant's Canal Lake Providence, La. (MR+T) 42-56 
Granville, Pa. (ORP) 26-22, 26-28 
Grapevine Lake, Tex. (SWF) 16-7, 16-16, 16-20 
Grasse River (Massena), N.Y. (NCB) 32-35 
I-16

INDEX 
Grassy Creek, Ind. (ORL) 24-20, 24-30 
Graves Creek, Idaho (NPW) 39-14 
Grays Creek Canal, Shelby Co., Tenn. (LMM) 13-6 
Grays Harbor and Chehalis River, Wash. (NPS) 
38-3, 38-12, 38-14, 38-19 
Grays Landing Lock and Dam, Pa. (ORP) 26-25 
Grays Reef Passage, Mich. (NCE) 31-61, 31-62 
Grays River, Wash. (NPP) 37-39 
Grayson Lake, Ky. (ORH) 25-5, 25-13, 25-17 
Great Chazy River, N.Y. (NAN) 2-34 
Great Coharie Creek, N.C. (SAW) 6-31 
Great Egg Harbor Inlet and Peck Beach, N.J. (NAP) 
3-23 
Great Falls, Mont. (MRO) 21-4, 21-10, 21-13 
Great Kills Harbor, N.Y. (NAN) 2-34 
Great Lakes Information Management 31-30 
Great Lakes to Hudson River Waterway, N.Y. (NAN) 
2-34 
Great Miami River, Ind. (ORL) 24-27, 24-30 
Great Pee Dee River, S.C. (SAN) 7-15 
Great Salt Plains Lake, Okla. (SWT) 19-4, 19-10, 
19-14, 19-17 
Great Salt Pond, R.I. (NED) 1-38, 1-53 
Great Sodus Bay Harbor, N.Y. (NCB) 32-6, 32-19, 
32-29, 32-39 
Great South Bay, N.Y. (NAN) 2-34 
Green and Barren Rivers, Ky. (ORL) 24-2, 24-14, 
24-18, 24-23, 24-27 
Green Bay Harbor, Wis. (NCE) 31-7, 31-35, 31-48 
Green Bay Levee and Drainage District No. 2, Iowa 
(NCR) 28-14, 28-17 
Green'Brook, Green Brook, N.J. (NAN) 2-40 
Green Harbor, Mass. (NED) 1-4, 1-25, 1-33, 
1-46, 1-53 
Green Island Levee and Drainage District, Iowa 
(NCR) 28-16 
Green Peter-Foster Lakes, Oreg. (NPP) 37-19, 
37-28, 37-38, 37-47, 37-49 
Green River, Ky. (ORL) 24-30 
Green River, Wash. (NPS) 38-27 
Green River Lake, Ky. (ORL) 24-8, 24-15, 24-27 
Green Valley Creek, Calif. (SPK) 35-31 
Greene, N.Y. (NAB) 4-36, 4-39 
Greenfield Bayou Levee, Ind. (ORL) 24-21, 24-24 
Greenport Harbor, N.Y. (NAN) 2-34 
Greenup, Ky. (ORH) 25-20 
Greenup Locks and Dam, Ky. (ORD) 22-3, 22-6, 
22-8 
Greenvale Creek, Va. (NAO) 5-4, 5-15, 5-18 
Greenville, Tex. (SWF) 16-22 
Greenville Harbor, Miss. (MR+T) 42-29, 42-56 
Greenwich Bay, R.I. (NED) 1-38 
Greenwich Harbor, Conn. (NED) 1-38 
Greenwich Point Beach, Conn. (NED) 1-45 
Greenwood Beach, Evanston, Ill. (NCC) 30-6 
Greers Ferry Lake, Ark. (SWL) 18-9, 18-13, 18-24 
Gregory Drainage District, Mo. (NCR) 28-14, 
28-17 
Greilickville Harbor, Mich. (Formerly Traverse City 
Harbor) (NCE) 31-61, 31-62 
Grenada Lake, Miss. (MR+T) 42-20, 42-59 
Greybull, Wyo. (MRO) 21-17, 21-19 
Griffithsville-Yawkey, W.Va. (ORH) 25-22 
Grifton, N.C. (SAW) 6-31 
Gros Ventre River, Wyo. (NPW) 39-17 
Grove Lake, Kans. (MRK) 20-17 
Guadalupe River, Calif. (SPK) 35-21 
Guadalupe River (Remove Log Jams), Tex. (SWG) 
15-27 
Guayanes Harbor, P.R. (SAJ) 9-46 
Guilford Creek, Norfolk, Va., District (NAO) 5-25 
Guilford Harbor, Conn. (NED) 1-38 
Guilford Point Beach (Jacobs Beach), Guilford, 
Conn. (NED) 1-42 
Gulf Beach, Milford, Conn. (NED) 1-42 
Gulf Intracoastal Waterway between Apalachee Bay, 
Fla. and Mexican Border (Mobile District) (SAM) 
10-8, 10-27, 10-35 
Gulf Intracoastal Waterway between Apalachee Bay, 
Fla., and Mexican Border (New Orleans Dist.) 
(LMN) 11-14 
Gulf Intracoastal Waterway between Apalachee Bay, 
Fla., and Mexican Border (Galveston, Tex., 
District) (SWG) 15-5, 15-13, 15-19, 15-28, 
15-34, 15-32, 15-34 
Gulf Intracoastal Waterway St. Marks to Tampa Bay, 
Fla. (SAJ) 9-46 
Gulf Street and Trumbull Avenue, Milford, Conn. 
(NED) 1-18, 1-30, 1-36 
Gulfport Harbor, Miss. (SAM) 10-42 
Gull Lake Reservoir, Minn. (NCS) 27-26 
Guntersville Lock and Dam, Ala. (ORN) 23-17 
Guttenberg, Iowa (NCS) 27-24 
Guyandotte River, W. Va. (ORH) 25-19 
Gypsum, Kans. (MRK) 20-17 
H 
H. V. Eastman Lake, Calif. (SPK) 35-4, 35-23 
Hackleman Corners Lake, Mo. (MRK) 20-18 
Haines Harbor, Alaska (NPA) 40-13, 40-15 
Haleiwa Beach, Hawaii (POD) 36-10 
Haleiwa Small Boat Harbor, Hawaii (POD) 36-8 
Hall Meadow Brook Dam, Conn. (NED) 1-22, 
1-43, 1-49 
Hamburg L-575, Iowa (MRO) 21-21 
Hamlin Beach Harbor, N.Y. (NCB) 32-35 
Hamlin Beach State Park, N.Y. (NCB) 32-36 
Hammersley Inlet, Wash. (NPS) 38-25, 38-30 
Hammonassett Beach, Madison, Conn. (NED) 1-42 
I-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Hammond Bay Harbor, Mich. (NCE) 31-8, 31-35, 
31-49 
Hammond Small Boat Basin, Oreg. (NPP) 37-39 
Hammondsport, N.Y. (NCB) 32-39 
Hampton Beach, Hampton, N.H. (NED) 1-42 
Hampton Creek, Va. (NAO) 5-23 
Hampton Harbor, N.H. (NED) 1-5, 1-25, 1-53 
Hampton Institute, Va. (NAO) 5-24 
Hampton Roads and Harbors of Norfolk and 
Newport News, Va.-Collection and Removal of 
Drift (NAO) 5-4, 5-15, 5-18 
Hampton Roads Harbor, Supervision of (NAO) 5-8, 
5-16 
Hana Small Boat Harbor, Hawaii (POD) 36-12 
Hanalei Bay Small Boat Harbor, Hawaii (POD) 
36-12 
Hanapepe Bay, Hawaii (POD) 36-10 
Hanapepe River, Hawaii (POD) 36-11 
Hancock Brook Lake, Conn. (NED) 1-17, 1-29, 
1-49 
Hanging Rock, Ohio (ORH) 25-21 
Hannibal, Mo. (NCR) 28-9, 28-13 
Hannibal Harbor, Mo. (NCD) 29-8 
Hannibal Locks and Dam, W. Va. (ORD) 22-1, 
22-7 
Hanover, Minn. (NCS) 27-7, 27-19 
Hanson, Howard A., Dam, Wash. (NAS) 38-8, 
38-16, 38-22 
Harbor Beach Harbor, Mich. (NCE) 31-8, 31-35, 
31-49 
Harbor of Refuge, Block Island, R.I. (NED) 1-38 
Harbor of Refuge, Delaware Bay, Del. (NAP) 3-21 
Harbor of Refuge, N.C. (SAW) 6-28 
Harbor of Refuge and Pt. Judith Pond, R.I. (NED) 
1-7, 1-26, 1-35 
Harden, Cecil M., Lake, Ind. (ORL) 24-7, 24-15, 
24-27 
Harkers Island Harbor, N.C. (SAW) 6-29 
Harlan County Lake, Nebr. (MRK) 20-2, 20-10, 
20-13, 20-19 
Harlem River, N.Y. (NAN) 2-34 
Harpers Ferry, W. Va. (NAB) 4-37 
Harpswell, Maine (NED) 1-22 
Harraseeket River, Maine (NED) 1-38, 1-53 
Harriet Island Harbor, St. Paul, Minn. (NCD) 29-7 
Harris Fork Creek, Tenn. and Ky. (MR+T) 42-28, 
42-58 
Harrisburg, Ill. (ORL) 24-20, 24-24, 24-29 
Harrison County, Miss. (SAM) 10-42 
Harrisonville Levee and Drainage District, Ill. (LMS) 
14-14 
Harrisville Harbor, Mich. (NCE) 31-8, 31-36, 
31-49 
Harrodsburg, Ky. (ORL) 24-30 
Harry S. Truman Dam and Reservoir, Mo. (MRK) 
20-8, 20-12, 20-16, 20-19 
Harsha, William H., Lake, Ohio (ORL) 24-12, 
24-17, 24-27 
Hartford, Conn. (NED) 1-22, 1-43, 1-49 
Hartford, Vt. (NED) 1-43, 1-49 
Hartford, W. Va. (ORH) 25-21 
Hartland, Maine (NED) 1-22 
Hartwell Drainage and Levee District, Ill. (LMS) 
14-3, 14-9, 14-11 
Hartwell Lake, Ga. and S.C. (SAS) 8-8, 8-12, 8-15, 
8-17 
Harvey Canal, Bayou Barataria Levee, La. (LMN) 
11-16 
Hastings Harbor, Minn. (NCD) 29-7 
Hatchie River, Miss. (LMM) 13-1, 13-4 
Haverhill, Mass. (NED) 1-22 
Havre, Mont. (MRO) 21-17, 21-19 
Havre, Scott Coulee-Bull Hook Dam, Mont. (MRO) 
21-19 
Hawarden, Iowa (MRO) 21-21 
Hawesville, Ky. (ORL) 24-20, 24-24, 24-29 
Hay Creek, Birdsboro, Pa. (NAP) 3-23 
Hay (West Harbor), Fisher's Island, N.Y. (NED) 
1-38, 1-53 
Hayden Island, Oreg. (NPP) 37-41, 37-48 
Hays, Kans. (MRK) 20-18 
Haysi, Va. (ORH) 25-20 
Hayward Creek, Mass. (NED) 1-22, 1-43 
Hayward Creek, Quincy-Braintree, Mass. (NED) 
1-22, 1-43 
Heeia-Kea Small Boat Harbor, Hawaii (POD) 36-8 
Heise-Roberts Area, Idaho (NPW) 39-14, 39-19 
Heise-Roberts Extension, Idaho (NPW) 39-14, 
39-16 
Helena Harbor, Ark. (LMN) 13-5 
Hellens Creek, Md. (NAB) 4-37 
Helm Lake, Ill. (ORL) 24-22, 24-28 
Hempstead County Levee District No. 1, Ark. (LMN) 
(LMK) 11-16, 12-18, 12-19 
Hempstead Harbor, N.Y. (NAN) 2-34 
Henderson, W. Va. (ORH) 25-21 
Henderson Bay, Wash. (NPS) 38-27 
Henderson County Drainage Districts Nos. 1, 2 and 
3, Ill. (NCR) 28-14, 28-17 
Henderson River, Ill. (NCR) 28-16 
Hendrick's Harbor, Maine (NED) 1-38 
Hennepin Drainage and Levee District, Ill. (NCR) 
28-14, 28-17 
Henry, Robert F., Lock and Dam, Ala. (SAM) 10-20, 
10-30 
Henry T. Rainey Dam, Ill. (NCD) 29-6 
Hergot Drainage and Levee District (NCR) 28-17 
Herkimer, N.Y. (NAN) 2-36 
Herreid, Spring Creek, S. Dak. (MRO) 21-17, 21-20 
Herring Bay - Rockhold Creek, Md. (NAB) 4-5, 
4-22, 4-29 
Herring Creek, Md. (NAB) 4-5, 4-22, 4-29 
1-18

INDEX 
Heyburn Lake and Polecat Creek, Okla. (SWT) 
19-4, 19-10, 19-14, 19-17 
Hickman Harbor, Ky. (LMM) 13-5 
Hidden Dam-Hensley Lake, Fresno River, Calif. 
(SPK) 35-7, 35-23 
Higginsport, Ohio (ORH) 25-21 
Highland Bayou, Tex. (SWG) 15-27 
Highway 12, Colo. (SWA) 17-7, 17-10 
Highway 39 Bridge, Gainesville, Ala. (SAM) 10-14, 
10-29, 10-39 
Highway 101, Oreg. (NPP) 37-43 
Highway 362 Bridges, Prentiss County, Miss. (SAM) 
10-43 
Hildebrand Lock and Dam, W. Va. (ORP) 26-25 
Hills Creek Lake, Oreg. (NPP) 37-20, 37-28, 
37-38, 37-47, 37-49 
Hillsborough Bay, Fla. (SAJ) 9-53 
Hillsborough River, Fla. (SAJ) 9-38 
Hillsdale Lake, Kans. (MRK) 20-3, 20-10, 20-13, 
20-19 
Hillview Drainage and Levee District, Ill. (LMS) 
14-4, 14-9, 14-11 
Hilo Harbor, Hawaii (POD) 36-8 
Hingham Harbor, Mass. (NED) 1-38 
Hiwassee River, Tenn. (ORN) 23-13 
Hoback River, Wyo. (NPW) 39-17 
Hockingport, Ohio (ORH) 25-21 
Hodges Dam, Calif. (SPL) 33-21 
Hodges Village Dam, Mass. (NED) 1-21, 1-31, 
1-52 
Hoh River, Wash. (NPS) 38-27 
Hoko River, Wash. (NPS) 38-27 
Holbrook Levee, Ariz. (SPL) 33-8, 33-20 
Holland Harbor, Mich. (NCE) 31-9, 31-36, 31-49 
Holley Lake, Oreg. (NPP) 37-42, 37-49 
Holly, Colo. (SWA) 17-7 
Hollywood-Ardmore Beach along Lake Michigan, 
Ill. (NCC) 30-15 
Holmes Bay, Whiting, Maine (NED) 1-43 
Holmes Creek, Fla. (SAM) 10-42 
Holston River, Tenn. (ORN) 23-13 
Holyoke, Mass. (NED) 1-22, 1-43, 1-49 
Homer Harbor, Alaska (NPA) 40-3, 40-8, 40-11 
Hominy Swamp, N.C. (SAW) 6-28 
Homme Lake and Dam, N. Dak. (NCS) 27-7, 27-20 
Homochitto River, Miss. (LMK) 12-14, 12-19 
Homosassa River, Fla. (SAJ) 9-46, 9-47 
Honey Creek Levee, Ind. (ORL) 24-22, 24-25 
Honey Hill Lake, N.H. (NED) 1-45 
Honga River and Tar Bay, Md. (NAB) 4-34 
Honokohau Small Boat Harbor, Hawaii (POD) 36-8 
Honolulu Harbor, Hawaii (POD) 36-8 
Hood Canal, Wash. (NPS) 38-27 
Hoonah Harbor, Alaska (NPA) 40-13, 40-15 
Hooper, Nebr. (MRO) 21-17, 21-20 
Hoosic Falls, Hoosic River Basin, N.Y. (NAN) 2-36 
Hop Brook Lake, Conn. (NED) 1-17, 1-29, 1-49 
Hopkinton-Everett Lakes, N.H. (NED) 1-19, 1-30, 
1-51 
Hoquiam River, Wash. (NPS) 38-25, 38-27 
Hords Creek Lake, Tex. (SWF) 16-7, 16-16, 16-20 
Horn Harbor, Va. (NAO) 5-23 
Hornell, N.Y. (NAB) 4-15, 4-25 
Horseshoe Cove, Fla. (SAJ) 9-46 
Hoskins Creek, Va. (NAO) 5-23 
Hot Springs, S. Dak. (MRO) 21-20 
Houlka Creek, Miss. (SAM) 10-43 
Houma Navigation Canal, La. (LMN) 11-14 
Housatonic River, Conn. (NED) 1-38, 1-45 
Housatonic River, Pittsfield, Mass. (NED) 1-17, 
1-29, 1-35, 1-43 
Housatonic River, Salisbury, Conn. (NED) 1-43 
Housatonic River, Sheffield, Mass. (NED) 1-43 
Housatonic River Basin, Conn. (NED) 1-16, 1-23, 
1-49 
Houston School Road Bridge, Miss. (SAM) 10-14, 
10-29, 10-39 
Houston Ship Channel, Tex. (SWG) 15-6, 15-14, 
15-21, 15-28, 15-30, 15-34 
Howard A. Hanson Dam, Wash. (NAS) 38-8, 38-16, 
38-22 
Howards Mill Lake, N.C. (SAW) 6-27 
Hudson River, Fla. (SAJ) 9-46 
Hudson River, N.Y. (NAN) 2-5, 2-23, 2-28, 2-32, 
2-33, 2-38 
Hudson River Channel, N.Y. (NAN) 2-33, 2-34 
Hugo Lake, Okla. (SWT) 19-4, 19-10, 19-14, 
19-17 
Hulah Lake, Okla. (SWT) 19-4, 19-10, 19-14, 
19-17 
Hull, Cordell, Lock and Dam, Tenn. (ORN) 23-14 
Humboldt, Tenn. (LMM) 13-2, 13-4 
Humboldt Bay, Calif. (SPN) 34-9 
Humboldt Harbor, Alaska (NPA) 40-13 
Humboldt Harbor and Bay, Calif. (SPN) 34-5 
Humboldt River and Tributaries, Nev. (SPK) 35-31 
Hunt Drainage District and Lima Lake Drainage 
District, Ill. (NCR) 28-14, 28-17 
Hunting Island Beach, S.C. (SAN) 7-15 
Huntingdon, Tenn. (LMM) 13-6 
Huntington, Mass. (NED) 1-22, 1-43, 1-49 
Huntington, W. Va. (ORH) 25-20, 25-22 
Huntington Avenue, Castle Rock, Wash. (NPP) 37-41 
Huntington Harbor, N.Y. (NAN) 2-38 
Huntington Lake, Ind. (ORL) 24-8, 24-15 
Huot, Minn. (NCS) 27-27 
Huron Harbor, Ohio (NCB) 32-6, 32-19, 32-30 
Hurricane Barrier Operations, New England Division 
(NED) 1-23 
Hutchins, Ky. (ORH) 25-22 
Hutchinson Levee and Channel, Kans. (SWT) 19-15, 
19-17, 19-18 
I-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Hyannis Harbor, Mass. (NED) 1-5, 1-25, 1-34 
Hyde County Dike, N.C. (SAW) 6-28 
Hydraulics and Hydrology of the Great Lakes 31-31 
Hydrologic Engineering Center (HEC) 53-2 
I 
Iao Stream, Hawaii (POD) 36-11 
Ice Harbor at Marcus Hook, Pa. (NAP) 3-21 
Ice Harbor at New Castle, Del. (NAP) 3-21 
Ice Harbor Lock and Dam-Lake Sacajawea, Wash. 
(NPW) 39-4, 39-9, 39-12, 39-18, 39-22 
Ida Grove, Iowa (MRO) 21-17, 21-21 
Iliuliuk Harbor, Alaska (NPA) 40-13, 40-15 
Illinois and Mississippi Canal, Ill. (NCR) 28-2, 
28-8 
Illinois River, Ill. (MR+T) 42-19 
Illinois Waterway, Ill. and Ind. (NCR) 28-2, 28-8, 
28-10, 28-16, 28-20, 28-21, 28-22 
Imperial Beach, Calif. (SPL) 33-3, 33-10, 33-15 
Indian Bend Wash, Ariz. (SPL) 33-19 
Indian Creek Area, Ill. (LMS) 14-14 
Indian Creek, Corydon, Ind. (ORL) 24-20, 24-30 
Indian Creek Lake, Emerson, Iowa (MRO) 21-4, 
21-10, 21-13, 21-18 
Indian Grave Drainage District, Ill. (NCR) 28-14, 
28-17 
Indian Island, Maine (NED) 1-22 
Indian Lake, Kans. (MRK) 20-17 
Indian River Inlet and Bay, Del. (NAP) 3-4, 3-15, 
3-19 
Indiana Dunes National Lakeshore Emergency Stone 
Repairs, Beverly Shores, Ind. (NCC) 30-6, 30-9, 
30-13 
Indiana Harbor, Ind. (NCC) 30-4, 30-9, 30-12, 
30-14, 30-15 
Indianapolis, Ind. (ORL) 24-21, 24-29 
Indianapolis, Ind. (Fall Creek Section) (ORL) 24-20 
Indianola, Nebr. (MRK) 20-17, 20-19 
Industry, Pa. (ORP) 26-23 
Inez, Ky. (ORH) 25-22 
Inland Route, Mich. (NCE) 31-9, 31-36, 31-49 
Inland Waterway from Chincoteague Bay, Va., to 
Delaware Bay, Del. (NAP) 3-21 
Inland Waterway from Delaware River to 
Chesapeake Bay, Del. and Md. (NAP) 3-6, 3-16, 
3-19 
Inland Waterway from Franklin to Mermentau River, 
La. (LMN) 11-14 
Inland Waterway, Rehoboth Bay to Delaware Bay, 
Del. (NAP) 3-5, 3-15, 3-19 
Institute for Water Resources 53-3 
Intercounty D. D., Little Sioux River, Iowa (MRO) 
21-21 
International Boundary Waters Boards, 49-1 
International Champlain-Richelieu Board 49-2 
International Great Lakes Diversions and 
Consumptive Uses Study Board 31-30, 49-2 
International Great Lakes Technical Information 
Network Board 31-30, 49-2 
International Joint Commission Board of Control 
(IJC) 49-1 
International Kootenay Lake Board of Control 49-1 
International Lake Champlain Board of Control 
49-1 
International Lake Memphremagog Board 49-2 
International Lake of the Woods Control Board 
49-1 
International Lake Superior Board of Control 
31-29, 49-1 
International Niagara Board of Control 31-30, 
49-1 
International Niagara Committee 49-2 
International Niagara Working Committee 31-30 
International Osoyoos Lake Board of Control 49-1 
International Rainy Lake Board of Control 49-1 
International Skagit River Board of Control 49-1 
International Souris River Board of Control 49-1 
International Souris-Red Rivers Engineering Board 
49-2 
International St. Croix River Board of Control 49-1 
International St. Lawrence River Board of Control 
31-30, 49-1 
Interstate Bridge, Portland, Oreg. (NPP) 37-39 
Interstate Highway Bridge (Barge Channel), Oreg. 
(NPP) 37-39 
Interstate 20 Bridges, Jackson, Miss. (SAM) 10-43 
Interstate 59 Bridges, Fosters, Ala. (SAM) 10-17, 
10-29, 10-40 
Intracoastal Waterway, Caloosahatchee River to 
Anclote River, Fla. (SAJ) 9-6, 9-26, 9-33 
Intracoastal Waterway, Jacksonville to Miami, Fla. 
(SAJ) 9-7, 9-26, 9-33, 9-46 
Intracoastal Waterway, Miami to Key West, Fla. 
(SAJ) 9-46, 9-47 
Intracoastal Waterway, Mississippi River to Bayou 
Teche, La. (LMN) 11-14 
Investigations of Projects Under the Federal Power 
Act 47-1 
Iola Levee, Kans. (SWT) 19-15, 19-17, 19-18 
Iowa River-Flint Creek Levee District No. 16, Iowa 
(NCR) 28-14, 28-17 
Ipswich Harbor, Mass. (NED) 1-39 
Irondequoit Bay, N.Y. (NCB) 32-7, 32-19 
Ironton, Ohio (ORH) 25-20, 25-22 
Irving Floodway, Tex. (SWF) 16-22 
Irving Township, Jackson Co., Wis. (NCS) 27-7, 
27-20, 27-24, 27-27 
Irvington Harbor, N.Y. (NAN) 2-38 
Isabella Lake, Kern River, Calif. (SPK) 35-8, 35-24 
Island Avenue, Quincy, Mass. (NED) 1-22, 1-43 
1-20

INDEX 
Island Creek, Md. (NAB) 4-34, 4-38 
Island Creek, St. Georges Island, Md. (NAB) 4-6, 
4-22, 4-29 
Island End River, Chelsea, Mass. (NED) 1-39 
Island Levee, Ind. (ORL) 24-21, 24-24 
Isle Au Haut Thoroughfare, Maine (NED) 1-39, 
1-53 
Isle of Shoals Harbor, Maine and N.H. (NED) 1-39 
Islesboro (The Narrows), Maine (NED) 1-18, 1-22, 
1-29, 1-36, 1-43 
Ithaca, N.Y., Cascadilla Creek (NCB) 32-39 
Ithaca, N.Y., Cayuga Inlet (NCB) 32-37 
Ithaca, N.Y., Fall Creek (NCB) 32-39 
J 
J. Percy Priest Dam and Reservoir, Ohio River 
Basin, Tenn. (ORN) 23-7, 23-9, 23-18 
Jackson, Ky. (ORL) 24-20, 24-24, 24-30 
Jackson and East Jackson, Miss. (SAM) 10-43 
Jackson Creek, Va. (NAO) 5-23 
Jackson Hole, Wyo. (NPW) 39-14 
Jacksonburg, Fishing Creek, W.Va. (ORH) 25-22 
Jacksonville Harbor, Fla. (SAJ) 9-7, 9-26, 9-34 
Jadwin, General Edgar, Dam and Reservoir, Pa. 
(NAP) 3-13, 3-17 
Jamaica Bay, N.Y. (NAN) 2-33, 2-34 
James River, Va. (NAO) 5-5, 5-15, 5-19, 5-25 
Jamestown Reservoir, N. Dak. (MRO) 21-17 
Janesville and Indian Ford Dams, Wis. (NCR) 28-16 
Jarvis Creek, Va. (NAO) 5-23 
Jefferson River, Bank Protection, near Waterloo, 
Mont. (MRO) 21-19 
Jefferson River, Willow Creek Bridge, near Three 
Forks, Mont. (MRO) 21-19 
Jeffersonville-Clarksville, Ind. (ORL) 24-20, 
24-24, 24-29 
Jemez Canyon Dam, N. Mex. (SWA) 17-4, 17-8, 
17-10 
Jenkins, Tom, Dam, Ohio (ORH) 25-15, 25-18 
Jenkins, Tom, Reservoir, Ohio (ORH) 25-10 
Jenks Levee, Okla. (SWT) 19-15, 19-17, 19-18 
Jennings Beach, Fairfield, Conn. (NED) 1-42 
Jeremy Creek, S.C. (SAN) 7-15 
Jim Woodruff Lock and Dam, Ga. and Fla. (SAM) 
10-23, 10-30, 10-41 
Joe Creek Channel Improvement, Okla. (SWT) 
19-17, 19-18 
Joe Pool Lake (Lakeville Lake), Tex. (SWF) 16-7, 
16-16, 16-20 
John Day Lock and Dam-Lake Umatilla, Oreg. and 
Wash. (NPP) 37-20, 37-28, 37-38, 37-51 
John Day River, Oreg. (NPP) 37-14, 37-27, 37-36, 
37-40, 37-44 
John Drainage District, Oreg. (NPP) 37-44, 37-48 
John H. Kerr Dam and Reservoir, Va. and N.C. 
(SAW) 6-14, 6-16, 6-20 
John Martin Reservoir, Colo. (SWA) 17-2, 17-8 
John Redmond Dam and Reservoir, Kans. (SWT) 
19-5, 19-10, 19-14, 19-17 
John W. Flannagan Dam and Reservoir, Va. (ORH) 
25-6, 25-13, 25-17 
Johns Pass, Fla. (SAJ) 9-8, 9-26, 9-34 
Johnson Bay, Lubec, Maine (NED) 1-43 
Johnson Bayou, La. (SWG) 15-27 
Johnson Creek, Vicinity of Portland, Oreg. (NPP) 
37-42, 37-49 
Johnsonburg, Pa. (ORP) 26-22, 26-26, 26-28 
Johnstown, Pa. (ORP) 26-4, 26-13, 26-18, 26-26 
Jones Inlet, N.Y. (NAN) 2-6, 2-23, 2-28, 2-33 
Jonesport Harbor, Maine (NED) 1-5, 1-26, 1-34 
Jonesville, La. (LMK) 12-13 
Jordan, B. Everett, Dam and Lake, N.C. (SAW) 
6-10, 6-15, 6-20 
Jordan Creek, Henry County, Va. (SAW) 6-31 
Josias River, Maine (NED) 1-39 
Joyce Creek, Camden County, N.C. (SAW) 6-27 
Julian, Nebr. (MRO) 21-20 
Juneau Harbor, Alaska (NPA) 40-13, 40-15 
K 
Kaaawa Beach, Hawaii (POD) 36-10 
Kahoma Stream, Hawaii (POD) 36-4, 36-6, 36-7 
Kahului Beach Road, Hawaii (POD) 36-8 
Kahului Harbor, Hawaii (POD) 36-8 
Kailua Small Boat Harbor, Hawaii (POD) 36-8 
Kaimu Black Sand Beach, Hawaii (POD) 36-12 
Kake Harbor, Alaska (NPA) 40-3, 40-8, 40-11 
Kalama River (South Area) Levee, Wash. (NPP) 
37-44, 37-48 
Kalama Turning Basin, Wash. (NPP) 37-7, 37-25, 
37-35 
Kalamazoo River (Battle Creek), Mich. (NCE) 
31-63 
Kalamazoo River (Kalamazoo), Mich. (NCE) 31-63 
Kalaupapa Harbor, Hawaii (POD) 36-8 
Kanawha River, W. Va. (ORH) 25-2, 25-12, 25-16 
Kaneohe-Kailua Area, Hawaii (POD) 36-11 
Kankakee River, Ill. and Ind. (NCC) 30-15 
Kanopolis Lake, Kans. (MRK) 20-3, 20-10, 20-13, 
20-19 
Kansas City, Kans. (1962 Mod.) (MRK) 20-17 
Kansas Citys on Mo. and Kansas Rivers, Mo. and 
Kans. (MRK) 20-17 
Kansas River and Minor Tributaries (MRK) 20-19 
Kansas River Navigation, Kans. (MRK) 20-16 
Kapaa Town, Hawaii (POD) 36-10 
Kapaakea Homestead Flood Control, Hawaii (POD) 
36-12 
1-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Karlson Island, Oreg. (NPP) 37-40 
Kasilof Harbor, Alaska (NPA) 40-13 
Kaskaskia Island Drainage and Levee District, Ill. 
(LMS) 14-4, 14-9, 14-11, 14-14 
Kaskaskia River, Ill. (LMS) 14-2, 14-9, 14-11 
Kaukauna Dam, Wis. (NCE) 31-60 
Kaukauna Fifth Lock, Wis. (NCE) 31-60 
Kaukauna First Lock, Wis. (NCE) 31-60 
Kaukauna Fourth Lock, Wis. (NCE) 31-60 
Kaukauna Guard Lock, Wis. (NCE) 31-60 
Kaukauna Second Lock, Wis. (NCE) 31-60 
Kaukauna Third Lock, Wis. (NCE) 31-60 
Kaulana Bay Boat Harbor, Hawaii (POD) 36-2, 
36-6 
Kaunakakai Harbor, Hawaii (POD) 36-8 
Kaunakakai Stream, Hawaii (POD) 36-11 
Kaw Lake, Okla. (SWT) 19-5, 19-11, 19-14, 19-17 
Kawaihae Harbor, Hawaii (POD) 36-8 
Kawainui Swamp, Hawaii (POD) 36-11 
Kaweah and Tule Rivers, including Terminus Dam 
and Success Lake, Calif. (SPK) 35-9, 35-24 
Kawkawlin River, Mich. (NCE) 31-26, 31-44, 31-56 
Kays Creek, Utah (SPK) 35-31 
Keach Drainage and Levee District, Ill. (LMS) 
14-14 
Keehi Lagoon, Hawaii (POD) 36-8 
Keene, N.H. (NED) 1-22, 1-43, 1-49 
Kehoe Lake, Ky. (ORH) 25-20 
Keithsburg Drainage District, Ill. (NCR) 28-16 
Kekaha Beach, Hawaii (POD) 36-10 
Kelleys Island, Ohio (NCB) 32-35 
Kendrick, Idaho (NPW) 39-14, 39-16 
Kenmore Navigation Channel, Wash. (NPS) 38-4, 
38-15, 38-20, 38-31 
Kennebec River, Maine (NED) 1-6, 1-26, 1-34 
Kennebunk River, Maine (NED) 1-6, 1-25, 1-33, 
1-39 
Kenosha Harbor, Wis. (NCE) 31-10, 31-36, 31-49 
Kentucky Lock and Dam, Ky. (ORN) 23-17 
Kentucky River, Ky. (ORL) 24-2, 24-14, 24-23, 
24-27 
Keokuk Harbor, Iowa (NCD) 29-8 
Kern River-California Aqueduct Intertie, Calif. 
(SPK) 35-31 
Kerr, John H., Dam and Reservoir, Va. and N.C. 
(SAW) 6-14, 6-16, 6-20 
Kerr, Robert S., Lock and Dam, Okla. (SWL) (SWT) 
18-20, 19-8, 19-13, 19-15, 19-16 
Kerr, Robert S., Marine Terminal, Sallisaw, Okla. 
(SWT) 19-16 
Kerton Valley Drainage and Levee District, Ill. 
(NCC) 28-17 
Ketchikan Harbor, Alaska (NPA) 40-13, 40-14 
Kewalo Harbor, Hawaii (POD) 36-12 
Kewaunee Harbor, Wis. (NCE) 31-10, 31-36, 
31-50 
Kewaunee River, Wis. (NCE) 31-63 
Keweenaw Waterway, Mich. (NCE) 31-10, 31-37, 
31-50 
Key West, Fla. (SAJ) 9-45, 9-47 
Key West Harbor, Fla. (SAJ) 9-46 
Keyport Harbor, N.J. (NAN) 2-34 
Keystone Lake, Okla. (SWL) (SWT) 18-22, 19-7, 
19-12, 19-15, 19-16, 19-17 
Kickapoo River, Gay Mills, Wis. (NCS) 27-7, 27-20 
Kihei Beach, Hawaii (POD) 36-10 
Kikiaola Small Boat Harbor, Hawaii (POD) 36-8 
Kill Van Kull-Newark Bay Channel, N.J. and N.Y. 
(NAN) 2-7, 2-23, 2-28 
King Cove Harbor, Alaska (NPA) 40-3, 40-8, 
40-11 
Kings Creek, Va. (NAO) 5-23 
Kingston Harbor, Wash. (NPS) 38-25 
Kingston Harbor (North Plymouth), Mass. (NED) 
1-39 
Kingston-Edwardsville, Pa. (NAB) 4-36, 4-39 
Kingstree Branch, S.C. (SAN) 7-8, 7-16 
Kinzua Dam and Allegheny Reservoir, Pa. and N.Y. 
(ORP) 26-7, 26-14, 26-18, 26-27 
Kirwan, Michael J., Dam and Reservoir, Ohio (ORP) 
26-8, 26-14, 26-19, 26-27 
Kishwaukee River at De Kalb, Ill. (NCR) 28-14 
Kissimmee River, Fla. (SAJ) 9-45, 9-46 
Kittanning, Pa. (ORP) 26-28 
Kittanning, Pa. Part I (ORP) 26-22, 26-26 
Kittanning, Pa. Part II (ORP) 26-23 
Kitzmiller, Md. (NAB) 4-36, 4-39 
Klamath River, Calif. (SPK) (SPN) 35-31 
Klutina River, Copper Center, Alaska (NPA) 40-14 
Knappa Area, Oreg. (NPP) 37-40 
Knapps Narrows, Md. (NAB) 4-34 
Knife River Harbor, Minn. (NCE) 31-11, 31-37, 
31-50 
Knights Valley Lake, Calif. (SPN) 34-9 
Knightville Dam, Mass. (NED) 1-13, 1-28, 1-48 
Knobb's Creek, N.C. (SAW) 6-25 
Kodiak Harbor, Alaska (NPA) 40-13, 40-15 
Konkapot River, North Canaan, Conn. (NED) 1-23 
Kootenai River, Idaho and Mont. (NPS) 38-25, 
38-27 
Kualoa Regional Park, Hawaii (POD) 36-10 
Kuliouou Stream, Hawaii (POD) 36-11 
Kuskokwim River, Bethel, Alaska (NPA) 40-6, 
40-9, 40-12 
L 
L'Anguille Basin, Ark. (MR + T) 42-28 
L'Anguille River, Ark. (MR+T) 42-18 
La Conner, Wash. (NPS) 38-27 
La Crosse, Wis. (NCS) 27-24 
1-22

INDEX 
La Farge Lake and Channel Improvement, Wis. 
(NCS) 27-8, 27-20 
La Grange Bayou, Fla. (SAM) 10-42, 10-45 
La Grange Lock and Dam, Ill. (NCC) 28-20 
La Pointe Harbor, Wis. (NCE) 31-11, 31-37, 
31-50 
La Trappe, Md. (NAB) 4-34 
Lac La Belle Harbor, Mich. (NCE) 31-61, 31-62 
Lac Qui Parle Lake, Minnesota River, Minn. (NCS) 
27-8, 27-20 
Lacey Drainage and Levee District, Ill. (NCC) 28-17 
Lacey, Langellier, West Mantanzas and Kerton Valley 
Drainage and Levee District, Ill. (NCR) 28-14 
Lackawanna, N.Y. (NCB) 32-37 
Lackawanna River Basin, Pa. (NAB) 4-12, 4-32 
Lafayette Lake, Ind. (ORL) 24-21 
Lafayette River, Va. (NAO) 5-23 
Lago De Cerrillos, P.R. (SAJ) 9-41 
Lago De Portugues, P.R. (SAJ) 9-41 
Lagoon Pond, Martha's Vineyard, Mass. (NED) 1-39 
Lahaina Small Boat Harbor, Hawaii (POD) 36-8 
Lake Ashtabula and Baldhill Dam, Sheyenne River, 
N. Dak. (NCS) 27-9, 27-20 
Lake Borgne and Chef Menteur-Bulkheads and 
Jetties (LMN) 11-14 
Lake Brownwood Modification, Tex. (SWF) 16-22 
Lake Bryan, Wash. (NPW) 39-5, 39-12 
Lake Camanche, Calif. (SPK) 35-31 
Lake Celilo, Wash. and Oreg. (NPP) 37-22, 37-29, 
37-38, 37-52 
Lake City, Tenn. (ORN) 23-19 
Lake Champlain, Plattsburgh, N.Y. (NAN) 2-39 
Lake Charles Deep Water Channel, La. (LMN) 
11-14 
Lake Chautauqua and Chadakoin River, N.Y. (ORP) 
26-23 
Lake City Harbor, Minn. (NCD) 29-7 
Lake Crescent and Dunns Creek, Fla. (SAJ) 9-46 
Lake Crockett, Wash. (NPS) 38-25, 38-31 
Lake Darling, N. Dak. (NCS) 27-9, 27-20 
Lake Douglas, Ga. (SAM) 10-43 
Lake Erie-Ohio Canal, Ohio and Pa. (ORP) 26-23 
Lake Fork Lake, Sabine River, Tex. (SWF) 16-22 
Lake Francis Case, S. Dak. (MRO) 21-8, 21-12, 
21-16 
Lake Georgetown, Tex. (SWF) 16-17 
Lake Greeson, Ark. (LMK) 12-16, 12-19 
Lake Harbor, Fla. (SAJ) 9-47 
Lake Hudson, Okla. (SWT) 19-16, 19-18 
Lake Kemp, Tex. (SWT) 19-5, 19-11, 19-14, 
19-17 
Lake Meredith, Okla. (SWT) 19-18 
Lake Michigan, Edgewater/Rogers Park 
Communities, Chicago, Ill. (NCC) 30-7, 30-10, 
30-13 
Lake Michigan-Lake Bluff, Ill. (NCC) 30-15 
Lake Michigan-Lake Forest, Ill. (NCC) 30-15 
Lake Montauk Harbor, N.Y. (NAN) 2-33, 2-34 
Lake Neatahwanta, Fulton, N.Y. (NCB) 32-11 
Lake Ocklawaha, Fla. (SAJ) 9-5 
Lake Ogleton, Md. (NAB) 4-37 
Lake Oroville, Calif. (SPK) 35-31 
Lake Pontchartrain, La. (MR+T) 42-15, 42-56 
Lake Pontchartrain, La. Project Levees (MR+T) 
42-45, 42-49 
Lake Pontchartrain and Vicinity, La., (Hurricane 
Protection) (LMN) 11-6, 11-10, 11-12 
Lake Providence Harbor, La. (LMK) 12-14 
Lake Pulaski, Minn. (NCS) 27-9, 27-20 
Lake River, Wash. (NPP) 37-39 
Lake River Delta Area, Wash. (NPP) 37-44, 37-48 
Lake Rousseau, Fla. (SAJ) 9-5 
Lake Sacajawea, Wash. (NPW) 39-4, 39-12 
Lake Sakakawea, N. Dak. (MRO) 21-8, 21-12 
Lake Sharpe, S. Dak (MRO) 21-7, 21-12 
Lake Shelbyville, Ill. (LMS) 14-14 
Lake Sidney Lanier, Ga. (SAM) 10-30, 10-41 
Lake St. Clair, Mich., Channels (NCE) 31-11, 
31-37, 31-50 
Lake Texoma, Tex. and Okla. (SWT) 19-7, 19-13, 
19-15, 19-17 
Lake Traverse, Minn. and S. Dak. (NCS) 27-23 
Lake Traverse and Bois De Sioux River, S. Dak. and 
Minn. (NCS) 27-10, 27-20 
Lake Umatilla, Oreg. and Wash. (NPP) 37-20, 
37-28, 37-38, 37-51 
Lake Wallula, Wash. (NPW) 39-7, 39-10, 39-12 
Lake Washington Ship Canal, Wash. (NPS) 38-4, 
38-15, 38-20, 38-31 
Lakeport Lake, Calif. (SPK) 35-31 
Lakeshore Park, Ashtabula, Ohio (NCB) 32-14, 
32-22 
Lakeview Park, Lorain, Ohio (NCB) 32-12, 32-21 
Lamoille River, Vt. (NAN) 2-36, 2-38 
Lamprey River, N.H. (NED) 1-39 
Lancaster, Mass. (NED) 1-22 
Lancaster, N.Y. (NCB) 32-37 
Lancaster, Israel River, N.H. (NED) 1-43 
Langdon Park, Wilmette, Ill. (NCC) 30-6 
Langellier Drainage and Levee District, Ill. (NCC) 
28-17 
Lansing (Grand River), Mich. (NCE) 31-63 
Lansing Harbor, Iowa (NCD) 29-7 
LaPlatte River, Shelburne Bay, Vt. (NAN) 2-38 
Lapwai Creek, Culdesac, Idaho (NPW) 39-14 
Larchmont Harbor, N.Y. (NAN) 2-34 
Largo Sound Channel, Fla. (SAJ) 9-45, 9-46 
Lamed, Kans. (SWT) 19-17 
Larose to Golden Meadow, La. (Hurricane 
Protection) (LMN) 11-7, 11-10, 11-13 
Larson Bay Small Boat Harbor, Alaska (NPA) 40-15 
I-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Las Animas, Colo. (SWA) 17-7, 17-10 
Las Cruces, N. Mex. (SWA) 17-7, 17-10 
Las Tunas Beach, Calif. (SPL) 33-19 
Las Vegas Wash Tributaries, Nev. (SPL) 33-21 
Latrobe, Pa. (ORP) 26-22, 26-26, 26-28 
Latta Brook Road, N.Y. (NAB) 4-36 
Laurel River Lake, Ohio River Basin, Ky. (ORN) 
23-7, 23-9, 23-18 
Lava Hot Springs, Idaho (NPW) 39-14 
Lavaca-Navidad River, Tex. (SWG) 15-27 
Lavon Lake, Tex. (SWF) 16-8, 16-16, 16-20 
Lavon Lake Modification and East Fork Channel 
Improvement, Tex. (SWF) 16-8, 16-16, 16-20 
Lawrence, Kans. (MRK) 20-17, 20-19 
Lawrenceburg, Ind. (ORL) 24-20, 24-24, 24-29 
Lawyers Creek, Kamiah, Idaho (NPW) 39-17 
Lead Bayou, Miss. (LMK) 12-5, 12-9, 12-11 
Leading Creek, W. Va. (ORH) 25-20 
Leaf and Bowie Rivers, Hattiesburg, Miss. (SAM) 
10-14, 10-29, 10-39 
Leaf and Chickasawhay River, Miss. (SAM) 10-42 
Leavenworth, Ind. (ORL) 24-22, 24-25 
Lebanon Junction, Ky. (ORL) 24-20, 24-29 
Le Claire Lock (Canal), Iowa (NCD) 29-5 
Lee County, Fla. (SAJ) 9-47 
Lee, Housatonic River, Mass. (NED) 1-22, 1-43 
Leech Lake Reservoir, Minn. (NCS) 27-26 
Leesville, Va., Roanoke River, Sec. 32, Demo. Project 
(SAW) 6-12, 6-20 
Leetonia, Ohio (ORP) 26-22 
Leetsdale, Pa. (ORP) 26-22, 26-26 
Lehigh River at Allentown, Pa. (NAP) 3-13 
Lehigh River at Bethlehem, Pa. (NAP) 3-13, 
3-24 
Leipsic River, Del. (NAP) 3-21 
Leith's Creek, N.C. (SAW) 6-27 
Leith's Creek, S.C. (SAN) 7-16 
Leland Bowman Lock, La. (formerly Vermilion Lock) 
(LMN) 11-2, 11-10, 11-12 
Leland Harbor, Mich. (NCE) 31-12, 31-37, 31-50 
Lemon Creek, N.Y. (NAN) 2-34 
Les Cheneaux Islands, Channels, Mich. (NCE) 
31-61, 31-62 
Letart, W. Va. (ORH) 25-21 
Letart Falls, Ohio (ORH) 25-21 
Levee Districts between Carlyle and New Athens, Ill. 
(LMS) 14-14 
Levee Districts between Cowden and Vandalia, Ill. 
(LMS) 14-14 
Levee Unit No. 1, Ill. (ORL) 24-21 
Levee Unit No. 5, Ind. (ORL) 24-4, 24-14, 24-29 
Levee Unit No. 8, Ind. (ORL) 24-20, 24-29 
Levees (LMK) (LMS) (MR+T) (ORL) 14-14, 24-22, 
24-25, 42-4, 42-10, 42-28, 42-44, 42-46, 
42-47, 42-54, 42-55, 42-57 
Levels of the Great Lakes 31-31 
Levisa and Tug Forks of the Big Sandy River and 
Cumberland River, W. Va., Va., and Ky. (ORH) 
25-6, 25-13, 25-17, 25-19 
Lewis and Clark Lake, Nebr. and S. Dak. (MRO) 
21-8, 21-12, 21-16 
Lewis and Clark River Area, Oreg. (NPP) 37-40 
Lewis River, Wash. (NPP) 37-39 
Lewis River Area, Wash. (NPP) 37-44, 37-48 
Lewisport, Ky. (ORL) 24-21, 24-24 
Lewiston-Clarkston Bridge, Idaho and Wash. 
(NPW) 39-5, 39-9, 39-12 
Lewisville Dam, Tex. (SWF) 16-8, 16-16, 16-20 
Lexington Harbor, Mich. (NCE) 31-12, 31-37, 
31-51 
Libby Dam-Lake Koocanusa, Mont. (NAS) 38-11, 
38-17, 38-23 
Liberty Local Protection Project, Tex. (SWG) 15-27 
Liberty State Park Levee and Seawall, N.J. (NAN) 
2-18, 2-25, 2-31 
Lick Run, Roanoke, Va. (SAW) 6-27 
Licking River, Ky. (ORL) 24-19, 24-27, 24-30 
Lido Key, Fla. (SAJ) 9-47 
Lighthouse Point Park, Conn. (NED) 1-42 
Lincoln, N.H. (NED) 1-22 
Lincoln, Nebr. (MRO) 21-20 
Lincoln Lake, Ind. (ORL) 24-22 
Lincoln School Lake, Me. (NED) 1-43 
Linton, N. Dak. (MRO) 21-17 
Lisle, N.Y. (NAB) 4-16, 4-26 
Little Bay, Tex. (SWG) 15-27 
Little Bay De Noc, Gladstone Harbor, Mich. (NCE) 
31-62 
Little Blue River Channel Improvement, Mo. (MRK) 
20-3, 20-11, 20-14 
Little Blue River Lakes, Mo. (MRK) 20-3, 20-11, 
20-14 
Little Caillou Bayou, La. (LMN) 11-14 
Little Calumet River, Ill. (NCC) 30-15 
Little Chute Combined Lock, Wis. (NCE) 31-60 
Little Chute Dam, Wis. (NCE) 31-60 
Little Chute First (Guard) Lock, Wis. (NCE) 31-60 
Little Chute Second Lock, Wis. (NCE) 31-60 
Little Cove Creek, Glencoe, Ala. (SAM) 10-43 
Little Creek, Kent Island, Md. (NAB) 4-34 
Little Dell Lake, Utah (SPK) 35-10, 35-24 
Little Egg Harbor, N.J. (NAP) 3-21 
Little Goose Lock and Dam-Lake Bryan, Wash. 
(NPW) 39-5, 39-9, 39-12, 39-19, 39-22 
Little Harbor, N.H. (NED) 1-39 
Little Harbor, Woods Hole, Mass. (NED) 1-39 
Little Kanawha River, W. Va. (ORH) 25-19 
Little Kaukauna Lock and Dam, Wis. (NCE) 31-60 
Little Lake Harbor, Mich. (NCE) 31-12, 31-38, 
31-51 
Little Machipongo River, Va. (NAO) 5-5, 5-15, 
5-19 
1-24

INDEX 
Little Manatee River, Fla. (SAJ) 9-46 
Little Massard Creek, Fort Smith, Ark. (SWL) 18-6, 
18-12 
Little Miami River, Ohio (ORL) 24-27, 24-30 
Little Missouri River, Ark. (LMK) 12-14, 12-16 
Little Neck Bay, N.Y. (NAN) 2-34 
Little Nemaha River, Nebr. (MRO) 21-17 
Little Papillion, Nebr. (MRO) 21-17, 21-20 
Little Pee Dee and Pee Dee Rivers, N.C. and S.C. 
(SAN) 7-17 
Little Red River and Tributaries, Clinton, Ark. (SWL) 
18-6, 18-12 
Little Red River, White County Road Bridge, 
Judsonia, Ark. (SWL) 18-17 
Little River, Del. (NAP) 3-21 
Little River, La. (LMK) 12-14 
Little River at Cayuga Island, N.Y. (NCB) 32-35 
Little River Basin (Little Rock District), Ark. (SWL) 
18-6, 18-12, 18-23 
Little River (Creek), Va. (NAO) 5-23 
Little River Dike, Westfield, Mass. (NED) 1-43 
Little River Diversion Channel, Mo. (MR+T) 42-19 
Little River Inlet, N.C. and S.C. (SAN) 7-5, 7-9, 
7-13 
Little River Project Levees (MR+T) 42-48, 42-49 
Little Rock Levee, Ark. (East End Fourche Bayou) 
(SWL) 18-17 
Little Rock Slackwater Harbor, Arkansas River, Ark. 
(SWL) 18-3, 18-11 
Little Rockfish Creek, Hope Mills, N.C. (SAW) 6-27 
Little Sioux River and Tributaries, Iowa (MRO) 
21-4, 21-11, 21-13 
Little Sodus Bay Harbor, N.Y. (NCB) 32-7, 32-20, 
32-30 
Little Sugar Creek, Charlotte, N.C. (SAW) 6-27 
Little Tallahatchie River, Miss. (LMK) 12-14 
Little Tennessee River, Tenn. (ORN) 23-13 
Little Valley Wash, Magna, Utah (SPK) 35-33 
Little Wicomico River, Va. (NAB) 4-6, 4-22, 
4-29 
Little Wood River, Idaho (NPW) 39-16 
Littleville Lake, Mass. (NED) 1-13, 1-28, 1-48 
Liverpool Drainage and Levee District, Ill. (NCR) 
28-14, 28-17 
Lloyd Park, Winnetka, Ill. (NCC) 30-6 
Lock and Dam No. 1, Minn. (NCD) 29-5, 29-9 
Lock and Dam No. 2, Allegheny River, Pa. (ORP) 
26-24 
Lock and Dam No. 2, Ark. (SWL) 18-3, 18-19 
Lock and Dam No. 2, Minn. (NCD) 29-5 
Lock and Dam No. 2, Monongahela River, Pa. (ORP) 
26-25 
Lock and Dam No. 3, Allegheny River, Pa. (ORP) 
26-24 
Lock and Dam No. 3, Ark. (SWL) 18-3, 18-18 
Lock and Dam No. 3, Minn. (NCD) 29-5 
Lock and Dam No. 3, Monongahela River, Pa. (ORP) 
26-25 
Lock and Dam No. 4, Allegheny River, Pa. (ORP) 
26-24 
Lock and Dam No. 4, Ark. (SWL) 18-3, 18-18 
Lock and Dam No. 4, Monongahela River, Pa. (ORP) 
26-25 
Lock and 
Lock and 
26-24 
Lock and 
Lock and 
Lock and 
Lock and 
26-24 
Lock and 
Lock and 
26-24 
Dam No. 4, Wis. (NCD) 29-5 
Dam No. 5, Allegheny River, Pa. (ORP) 
Dam No. 
Dam No. 
Dam No. 
Dam No. 
5, Ark. (SWL) 18-3, 18-18 
5, Minn. (NCD) 29-5 
5A, Minn. (NCD) 29-5 
6, Allegheny River, Pa. (ORP) 
Dam No. 6, Wis. (NCD) 29-5 
Dam No. 7, Allegheny River, Pa. (ORP) 
Lock and Dam No. 7, Minn. (NCD) 29-5 
Lock and Dam No. 7, Monongahela River, Pa. (ORP) 
26-25 
Lock and Dam No. 8, Allegheny River, Pa. (ORP) 
26-24 
Lock and Dam No. 8, Monongahela River, Pa. (ORP) 
26-25 
Lock and Dam No. 8, 
Lock and Dam No. 9, 1 
26-24 
Lock and Dam No. 9, 1 
Lock and Dam No. 9, 
Lock and Dam No. 10, 
Lock and Dam No. 11, 
Lock and Dam No. 11, 
Lock and Dam No. 12, 
Lock and Dam No. 13, 
18-20, 19-16 
Lock and Dam No. 13, 
Lock and Dam No. 14, 
Lock and Dam No. 15, 
Lock and Dam No. 16, 
Lock and Dam No. 17, 
Lock and Dam No. 18, 
Lock and Dam No. 19, 
Lock and Dam No. 20, 
Lock and Dam No. 21, 
Lock and Dam No. 22, 
Lock and Dam No. 24, 
Lock and Dam No. 25, 
Lock and Dam No. 26, 
Lock and Dam No. 52, 
Lock and Dam No. 53, 
Lock S-53, Fla. (SAJ) 
Lock S-55, Fla. (SAJ) 
Lock S-57, Fla. (SAJ) 
Lock S-58, Fla. (SAJ) 
Lock S-59, Fla. (SAJ) 
Wis. (NCD) 29-5 
Alegheny River, Pa. (ORP) 
Ark. (SWL) 18-3, 18-19 
Wis. (NCD) 29-5 
Iowa (NCD) 29-5 
Ark. (SWL) 18-20 
Iowa (NCD) 29-5 
Iowa (NCD) 29-5 
Ark. (SWL) (SWT) 18-3, 
Iowa (NCD) 29-5 
Iowa (NCD) 29-5 
Ill. (NCD) 29-5 
Iowa (NCD) 29-5 
Ill. (NCD) 29-6 
Iowa (NCD) 29-6 
Iowa (NCD) 29-6 
Mo. (NCD) 29-6 
Ill. (NCD) 29-6 
Mo. (NCD) 29-6 
Mo. (NCD) 29-6 
Mo. (NCD) 29-6 
Ill. (NCD) 29-6 
Ill. (ORD) 22-3, 22-10 
Ill. (ORD) 22-3, 22-10 
9-49 
9-49 
9-48 
9-48 
9-48 
1-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Lock S-60, Fla. (SAJ) 9-48 
Lock S-61, Fla. (SAJ) 9-48 
Lock S-62, Fla. (SAJ) 9-48 
Lock S-63, Fla. (SAJ) 9-48 
Lock S-63A, Fla. (SAJ) 9-48 
Lock S-65, Fla. (SAJ) 9-48 
Lock S-65A, Fla. (SAJ) 9-48 
Lock S-65B, Fla. (SAJ) 9-48 
Lock S-65C, Fla. (SAJ) 9-48 
Lock S-65D, Fla. (SAJ) 9-48 
Lock S-65E, Fla. (SAJ) 9-48 
Lock S-96, Fla. (SAJ) 9-48 
Lock S-96A, Fla. (SAJ) 9-48 
Lock S-157, Fla. (SAJ) 9-48 
Lock S-158, Fla. (SAJ) 9-48 
Lock S-193, Fla. (SAJ) 9-48 
Lock S-308B, Fla. (SAJ) 9-48 
Lock S-310, Fla. (SAJ) 9-48 
Lock Haven, Pa. (NAB) 4-20, 4-36 
Locklies Creek, Va. (NAO) 5-23 
Lockport Lock and Dam, Ill. (NCC) 28-20, 28-21 
Lockwoods Folly River, N.C. (SAW) 6-5, 6-18 
Logan, Ohio (ORH) 25-20 
Logan Creek, Bank Protection, near Bancroft, Nebr. 
(MRO) 21-20 
Lone Rock, Ark. (SWL) 18-18 
Long Beach Island, N.J. (NAP) 3-23 
Long Branch Lake, Mo. (MRK) 20-4, 20-11, 20-14 
Long Island Intracoastal Waterway, N.Y. (NAN) 2-7, 
2-23, 2-28, 2-33 
Long Lake Area, Helena, Ark. (LMM) 13-6 
Long Tom River, Oreg. (NPP) 37-39 
Longboat Pass, Fla. (SAJ) 9-8, 9-27, 9-34 
Lookout Point Lake, Oreg. (NPP) 37-21, 37-28, 
37-38, 37-47, 37-49 
Lopez Canyon Diversion, Los Angeles River Basin, 
Calif. (SPL) 33-22 
Lopez Dam, Los Angeles River Basin, Calif. (SPL) 
33-22 
Lorain Harbor, Ohio (NCB) 32-7, 32-20, 32-30 
Los Angeles and Long Beach Harbors, Calif. (SPL) 
33-2, 33-10, 33-14 
Los Angeles County Drainage Area, Calif. (SPL) 
33-5, 33-11, 33-16, 33-22, 33-23 
Los Coches Creek, Calif. (SPL) 33-6, 33-11, 33-16 
Lost Creek, Columbus, Nebr. (MRO) 21-4, 21-11, 
21-13 
Lost Creek Drainage and Levee District, Ill. (NCR) 
28-14, 28-17 
Lost Creek Lake, Oreg. (NPP) 37-21, 37-29, 
37-38, 37-47 
Lost River, Minn. (NCS) 27-24 
Louisville, Ky. (ORL) 24-20, 24-24, 24-29 
Louisville Lake, Ill. (ORL) 24-21, 24-28 
Loup River, Columbus, Nebr. (MRO) 21-17 
Loves Park, Ill. (NCR) 28-9 
Lowell, Mass. (NED) 1-22, 1-43, 1-51 
Lowell Creek, Alaska (NPA) 40-14 
Lower Arkansas River, Ark. (MR�T) 42-16, 42-28, 
42-54, 42-57 
Lower Arkansas River Basin, Ark. (MR+T) 42-7 
Lower Big Sioux River, Iowa and S. Dak. (MRO) 
21-17 
Lower Branch Rush River, N. Dak. (NCS) 27-24 
Lower Columbia River Basin, Oreg. and Wash. 
(NPP) 37-15, 37-36, 37-41, 37-48 
Lower Cowlitz River, Wash. (NPP) 37-40 
Lower Creek, Lenoir, N.C. (SAW) 6-31 
Lower Dry Creek, Lowden, Wash. (NPW) 39-14 
Lower Gila River Levee and Channel Improvements 
(Gila River and Tributaries) Downstream from 
Painted Rock Dam, Ariz. (SPL) 33-19 
Lower Grand River, Mo. (MRK) 20-17 
Lower Granite Lock and Dam, Wash. (NPW) 39-5, 
39-9, 39-12, 39-20, 39-22 
Lower Guyandotte River Basin, W. Va. (ORH) 25-20 
Lower Heart River, N. Dak. (MRO) 21-17 
Lower Machodoc Creek, Va. (NAB) 4-34 
Lower Monumental Lock and Dam, Wash. (NPW) 
39-6, 39-9, 39-12, 39-20, 39-22 
Lower Red River-South Bank, Red River Levees, 
La. (MR+T) 42-9, 42-15, 42-28, 42-46, 42-49, 
42-57 
Lower Red River Standard Revetments (MR+T) 
42-33, 42-37 
Lower San Francisco Bay, Calif. (SPN) 34-8 
Lower San Joaquin River, Calif. (SPK) 35-11, 
35-24, 35-33 
Lower San Joaquin River and Tributaries, including 
Tuolumne and Stanislaus Rivers, Calif. (SPK) 
35-25, 35-31 
Lower Snake River, Wash., Oreg., Idaho, Fish and 
Wildlife Compensation (NPW) 39-6, 39-10, 
39-12 
Lower Thorofare, Deal Island, Md. (NAB) 4-6, 
4-22, 4-29 
Lower Walla Walla River, Wash. (NPW) 39-14, 
39-16 
Lower White River and Basin, Ark. (MR+T) 42-9, 
42-17, 42-28, 42-53 
Lower White River Levees (MR+T) 42-9, 42-48, 
42-49, 42-57 
Lower Woonsocket, R.I. (NED) 1-43, 1-48 
Lowes Wharf, Md. (NAB) 4-6, 4-23, 4-29 
Loyalhanna Lake, Pa. (ORP) 26-7, 26-14, 26-19, 
26-27 
Loyalsock, Pa. (NAB) 4-39 
Lubec, Maine (NED) 1-22 
Lubec Channel, Maine (NED) 1-39 
Lucky Peak Lake, Idaho (NPW) 39-3, 39-9, 39-11 
Ludington Harbor, Mich. (NCE) 31-12, 31-38, 
31-51 
I-26

INDEX 
Ludlow, Ky. (ORL) 24-22, 24-25 
Ludlow Lake, Vt. (NED) 1-45 
Lukfata Lake, Okla. and Ark. (SWT) 19-15 
Lusk Creek, Ill. (ORL) 24-30 
Lutsen Harbor, Minn. (NCE) 31-62 
Lyford Levee, Ind. (ORL) 24-20, 24-29 
Lyman Creek, Idaho (NPW) 39-14 
Lynches River and Clark Creek, S.C. (SAN) 7-15 
Lynn Harbor, Mass. (NED) 1-39 
Lynn-Nahant Beach, Mass. (NED) 1-9, 1-27, 
1-35, 1-42 
Lynnhaven Inlet, Va. (NAO) 5-23 
Lytle and Cajun Creeks channel improvements, 
Calif. (SPL) 33-24 
Lytle and Warm Creeks, Calif. (SPL) 33-6, 33-12, 
33-16 
M 
Maalaea Small Boat Harbor, Hawaii (POD) 36-8 
MacDowell, Edward, Lake, N.H. (NED) 1-18, 1-30, 
1-51 
Machias River, Maine (NED) 1-23, 1-39 
Mackay Creek, N.C. (SAW) 6-25, 6-28 
Mackinac Island Harbor, Mich. (NCE) 31-13, 
31-38, 31-51 
Mackinaw City Harbor, Mich. (NCE) 31-13, 31-38, 
31-51 
Macon, Ga. (SAS) 8-7, 8-16 
Macy, Nebr. (MRO) 21-20 
Mad Creek, Muscatine, Iowa (NCR) 28-17 
Mad River, Conn. (NED) 1-22, 1-48 
Mad River Basin, Calif. (SPK) 35-31 
Mad River Lake, Conn. (NED) 1-43 
Madison, Ind. (ORL) 24-22, 24-25 
Madison, Nebr. (MRO) 21-17, 21-20 
Madison Bay, Md. (NAB) 4-34 
Madison Parish Port, La. (LMK) 12-14 
Magruder Drainage District, Oreg. (NPP) 37-40, 
37-44, 37-48 
Mahnomen, Minn. (NCS) 27-27 
Mahoning Creek Lake, Pa. (ORP) 26-7, 26-14, 
26-19, 26-27 
Maiden Creek Reservoir, Pa. (NAP) 3-23 
Maintenance and Repair Fleet and Marine 
Terminals, Ark. (SWL) 18-3, 18-21 
Malden River, Mass. (NED) 1-39 
Malheur Improvement District, Oreg. (NPW) 39-14 
Malheur River, Oreg. (NPW) 39-14, 39-16, 39-17 
Mamaroneck Harbor, N.Y. (NAN) 2-34 
Manasquan River, N.J. (NAP) 3-7, 3-16, 3-19 
Manatee County, Fla. (SAJ) 9-47 
Manatee River, Fla. (SAJ) 9-45, 9-46 
Manchester, Ohio (ORH) 25-21 
Manchester Harbor, Mass. (NED) 1-45 
Mandan, N. Dak. (MRO) 21-17, 21-19 
Manele Bay Small Boat Harbor, Hawaii (POD) 36-2 
Manhasset Bay, N.Y. (NAN) 2-34 
Manhattan, Kans. (MRK) 20-17, 20-19 
Maniece Bayou, Ark. (LMN) (LMK) 11-16, 12-17, 
12-19 
Manistee Harbor, Mich. (NCE) 31-13, 31-38, 
31-51 
Manistique Harbor, Mich. (NCE) 31-61, 31-62 
Manitowoc Harbor, Wis. (NCE) 31-14, 31-38, 
31-51 
Mankato and North Mankato, Minn. (NCS) 27-10, 
27-20 
Mann's Harbor, N.C. (SAW) 6-28 
Manokin River, Md. (NAB) 4-34 
Mansfield Hollow Lake, Conn. (NED) 1-21, 1-31, 
1-52 
Manteo (Shallowbag) Bay, N.C. (SAW) 6-6, 6-19 
Mantua Creek, N.J. (NAP) 3-21 
Maple River, N. Dak. (NCS) 27-25 
Mapleshade, Ohio (ORH) 25-21 
Marblehead Harbor, Mass. (NED) 1-45 
Marengo, Iowa (NCR) 28-14, 28-17 
Marginal Way, Ogunquit, Maine (NED) 1-20, 1-23, 
1-31, 1-37 
Markham Ferry, Okla. (SWL) 18-22 
Marietta, Ohio (ORH) 25-21 
Marina Del Rey, Calif. (SPL) 33-18, 33-22 
Marine Design Center 53-5 
Marion, Ind. (ORL) 24-21, 24-28 
Marion, Kans. (SWT) 19-5, 19-11, 19-14, 19-17, 
19-18 
Marion County Drainage District, Mo. (NCR) 28-14, 
28-17 
Marion Lake, Kans. (SWT) 19-5, 19-11, 19-14, 
19-17 
Markham Ferry Lake, Okla. (SWL) 18-22 
Markham Ferry Reservoir, Okla. (SWT) 19-18 
Markland Locks and Dam, Ind. (ORD) 22-3, 22-6, 
22-9 
Marmarth, N. Dak. (MRO) 21-17, 21-19 
Marquette Harbor, Mich. (NCE) 31-14, 31-39, 
31-52 
Marseilles Lock and Dam, Ill. (NCC) 28-20 
Marsh Creek, Geneva, N.Y. (NCB) 32-37 
Marshalltown, Iowa (NCR) 28-14, 28-17 
Marshland Drainage District, Oreg. (NPP) 37-40 
Martin, John, Reservoir, Colo. (SWA) 17-2, 17-8 
Martin, Ky. (ORH) 25-20 
Martin Creek, Miss. (SAM) 10-15, 10-29, 10-39 
Martins Ferry, Ohio (ORP) 26-22, 26-26 
Martins Fork Lake, Ky. (ORN) 23-5, 23-9, 23-18 
Martis Creek Lake, Martis Creek, Nev. and Calif. 
(SPK) 35-11, 35-24 
Marysville, Kans. (MRK) 20-18 
Marysville Lake, Calif. (SPK) 35-31 
I-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Mason, W. Va. (ORH) 25-21 
Mason and Menard Drainage District, Ill. (NCR) 
28-14, 28-17 
Mason J. Niblack Levee, Ind. (ORL) 24-4, 24-14, 
24-20, 24-24, 24-29 
Massillon, Ohio (ORH) 25-6, 25-13, 25-17 
Matafao Shoreline, American Samoa (POD), 36-10 
Matagorda Ship Channel, Tex. (SWG) 15-6, 15-14, 
15-22, 15-30, 15-35 
Matawan Creek, N.J. (NAN) 2-34 
Matinicus Harbor, Maine (NED) 1-39 
Mats Mats Bay, Wash. (NPS) 38-25, 38-31 
Mattapoisett Harbor, Mass. (NED) 1-45 
Mattituck Harbor, N.Y. (NAN) 2-33, 2-34 
Mauckport, Ind. (ORL) 24-22, 24-25 
Maumee Bay State Park, Ohio (NCB) 32-12 
Maumee River, above Toledo, Ohio (NCB) 32-39 
Maunalua Bay Small Boat Harbor, Hawaii (POD) 
36-8 
Maurice River, N.J. (NAP) 3-21, 3-24 
Mauvaise Terre Drainage and Levee District, Ill. 
(LMS) 14-4, 14-9, 14-11 
Maxwell Locks and Dam, Pa. (ORP) 26-25 
Mayaguez Harbor, P.R. (SAJ) 9-9, 9-27, 9-34 
Mayo, W. D., Lock and Dam, Okla. (SWL) (SWT) 
18-20, 19-16 
Mayse, Pat, Lake, Tex. (SWT) 19-5, 19-11, 19-14, 
19-17 
Maysville, Ky. (ORH) 25-20, 25-22 
McAlpine Locks and Dam (ORD) 22-3, 22-6, 22-9 
McClellan-Kerr Arkansas River Navigation System 
(SWT) 19-2, 19-9, 19-13, 19-16 
McCook Lake, S. Dak. (MRO) 21-17 
McDonald Dike Road, Ore. (NPP) 37-42 
McGee Creek Drainage and Levee District, Ill. 
(LMS) 14-5, 14-9, 14-12 
McGinnis Levee, Ind. (ORL) 24-22, 24-25 
McKees Rocks, Pa. (ORP) 26-23 
McKenzie River near Walterville, Oreg. (NPP) 
37-42 
McKinney Bayou, Finn Bayou Segment, Ark. (LMN) 
(LMK) 11-16, 12-17, 12-19 
McLean Bottom Levee District No. 3, Arkansas 
River, Ark. (SWL) 18-17 
McNary Lock and Dam-Lake Wallula-Oreg. and 
Wash. (NPW) 39-7, 39-8, 39-10, 39-12, 39-21 
Meadow Grove, Nebr. (MRO) 21-20 
Medomak River, Maine (NED) 1-39 
Meherrin River, N.C. (NAO) 5-23 
Mekoryuk, Alaska (NPA) 40-3, 40-8, 40-11 
Melbourne Harbor, Fla. (SAJ) 9-9, 9-27, 9-34 
Meldahl, Captain Anthony, Locks and Dam, Ky. 
(ORD) 22-3, 22-8 
Melton Hill Lock and Dam, Tenn. (ORN) 23-17 
Melvern Lake, Kans. (MRK) 20-4, 20-11, 20-14, 
20-19 
Melvern Lake and Pomona Lake (Road 
Improvement), Kans. (MRK) 20-19 
Memphis Harbor, Tenn. (MR+T) 42-29 
Memphis Harbor Project Levees (MR+T) 42-48, 
42-49 
Memphis, Wolf River, and Nonconnah Creek, Tenn. 
(LMM) 13-6 
Menasha Lock and Dam (NCE) 31-60 
Menemsha Creek, Martha's Vineyard, Mass. (NED) 
1-39 
Menominee Harbor and River, Mich. and Wis. (NCE) 
31-15, 31-39, 31-52 
Meramec Park Lake, Mo. (LMS) 14-5, 14-9 
Meramec River Basin, Mo. (LMS) 14-4, 14-12, 
14-13 
Merced County Stream Group, Calif. (SPK) 35-12, 
35-24, 35-34 
Merced County Streams, Calif. (SPK) 35-11, 35-24 
Merced River, Calif. (SPK) 35-31 
Mercer Lake, Mo. (MRK) 20-17 
Meredosia, Ill., and Meredosia, Willow Creek, and 
Coon Run Drainage and Levee Districts, Ill. 
(LMS) 14-5, 14-9, 14-12 
Meredosia Lake and Willow Creek Drainage and 
Levee District, Ill. (LMS) 14-6, 14-10, 14-12, 
14-14 
Meredosia Levee and Drainage District, Ill. (NCR) 
28-14, 28-17 
Mermentau River, La. (LMN) 11-14 
Mermentau River, Bayou Nezpique, and Bay Des 
Cannes, La. (LMN) 11-14 
Merriam, Kans. (MRK) 20-18 
Merriconeag Sound, Harpswell, Maine (NED) 1-43 
Merrimack River, Mass. (NED) 1-39, 1-51 
Merrimack River Basin, N.H. and Mass. (NED) 
1-18, 1-23, 1-51 
Merrimack River, Concord, N.H. (NED) 1-23 
Metamora Lake, Ind. (ORL) 24-22, 24-27 
Methow River, Wash. (NAS) 38-27 
Metlakatla Harbor, Alaska (NPA) 40-4, 40-8, 
40-11 
Metropolis, Ill. (ORL) 24-21, 24-24 
Miami Harbor, Fla. (SAJ) 9-9, 9-27, 9-34 
Miami River, Fla. (SAJ) 9-45 
Miami River, Oreg. (NPP) 37-42 
Mianus River, Conn. (NED) 1-39 
Michael J. Kirwan Dam and Reservoir, Ohio (ORP) 
26-8, 26-14, 26-19, 26-27 
Michigan City Harbor, Ind. (NCC) 30-5, 30-9, 
30-12, 30-14, 30-15 
Middle Beach, Conn. (NED) 1-42 
Middle Creek, Calif. (SPK) 35-31 
Middle Fork Nooksack River, Deming, Wash. (NPS) 
38-9, 38--16, 38-22 
Middle Gila River Channel Improvements, Upper 
End of Safford Valley to Buttes Damsite 
I-28

INDEX 
(Camelsback Damsite to Salt River), Ariz. (SPL) 
33-19 
Middle Pebble Creek, Snyder, Nebr. (MRO) 21-21 
Middle River and Connecting Channels, Calif. (SPK) 
35-30 
Middle River and Dark Head Creek, Md. (NAB) 
4-34 
Middle River at Argyle, Minn. (NCS) 27-11, 27-20 
Middleport, Ohio (ORH) 25-21 
Middlesboro, Ky. (ORN) 23-5, 23-9 
Middlesboro, Ky. (Diversion Canal) (ORN) 23-19 
Middlesboro, Ky. (Yellow Creek) (ORN) 23-13, 
23-18, 23-19 
Middleton Shoals, Ga. and S.C. (SAS) 8-17 
Midland Drainage District, Oreg. (NPP) 37-40, 
37-41, 37-48 
Milan, Ill. (NCR) 28-5, 28-9, 28-12, 28-17 
Miles City, Mont. (MRO) 21-17 
Milford Harbor, Conn. (NED) 1-39, 1-53 
Milford Haven, Va. (NAO) 5-23 
Milford Lake, Kans. (MRK) 20-4, 20-11, 20-14, 
20-19 
Mill Brook, Brownsville, Vt. (NED) 1-14, 1-23, 
1-28 
Mill Creek, Ky. (ORL) 24-20, 24-27, 24-30 
Mill Creek, Md. (NAB) 4-37 
Mill Creek, N.C. (SAW) 6-28 
Mill Creek, Ohio (ORL) (ORH) 24-4, 24-14, 25-21 
Mill Creek, Tex. (SWG) 15-27 
Mill Creek, Va. (NAO) 5-23 
Mill Creek, Wash. (NPW) 39-16 
Mill Creek and South Slough at Milan, Ill. (NCR) 
28-3, 28-8, 28-11 
Mill Creek, Fort Smith, Ark. (SWL) 18-6, 18-12 
Mill Creek Lake, Wash. (NPW) 39-3, 39-9, 39-11 
Mill Creek levees, Calif. (SPL) 33-20 
Mill Four Drainage District, Oreg. (NPP) 37-42 
Mill Lake, Mo. (MRK) 20-17 
Miller, Ohio (ORH) 25-20 
Miller Pond Drainage District, Ill. (LMS) 14-14 
Millers Ferry Lock and Dam, Ala. (SAM) 10-20, 
10-30 
Millersburg, Ohio (ORH) 25-21 
Millican Lake, Tex. (SWF) 16-9, 16-16, 16-20 
Millwood, W. Va. (ORH) 25-21 
Millwood Lake, Little River Basin, Ark. (SWL) 18-6, 
18-12, 18-23 
Milton, Ky. (ORL) 24-22, 24-25 
Milton, Pa. (NAB) 4-39 
Milton-Freewater, Oreg. (NPW) 39-14 
Milton Harbor, N.Y. (NAN) 2-34 
Milwaukee Harbor, Wis. (NCE) 31-15, 31-39, 
31-52 
Mineral Creek, Wash. (NPS) 38-27 
Mingo Creek, S.C. (SAN) 7-15 
Mingo Junction, Ohio (ORP) 26-23 
Mining City Lake, Ky. (ORL) 24-21, 24-27 
Minneota, Minn. (NCS) 27-24 
Minnesota River, Minn. (NCS) 27-2, 27-19, 27-22 
Minnesota River at Le Sueur, Minn. (NCS) 27-11, 
27-20 
Minot, N. Dak. (NCS) 27-24, 27-27 
Mispillion River, Del. (NAP) 3-7, 3-14, 3-16, 3-19 
Misquamicut Beach, Westerly, R.I. (NED) 1-42 
Mission and Lapwai Creeks, Idaho (NPW) 39-15 
Mission Zanja Creek, Calif. (SPL) 33-25 
Missisquoi River at Richford, Vt. (NAN) 2-36, 2-39 
Mississinewa Lake, Ind. (ORL) 24-9, 24-16 
Mississippi and Leech Rivers, Minn. (NCS) 27-23 
Mississippi Delta Region, La. (MR+T) 42-28 
Mississippi River Agricultural Area No. 8, Mo. (LMS) 
14-6, 14-10, 14-12 
Mississippi River Agricultural Area No. 10, Mo. 
(LMS) 14-15 
Mississippi River Agricultural Area No. 12, Mo. 
(LMS) 14-15 
Mississippi River Alluvial Valley Mapping (MR+T) 
42-3 
Mississippi River, Alton to Gale, Ill., Underseepage 
Measures (LMS) 14-15 
Mississippi River and Alluvial Valley below Cape 
Girardeau, Mo. (MR+T) 42-2 
Mississippi River and Tributaries (MR+T) 42-1 to 
42-63 
Mississippi River and Tributaries-Channel 
Improvements (MR+T) 42-4 
Mississippi River and Tributaries-Levees (MR+T) 
42-4 
Mississippi River at Alton, Ill. (LMS) 14-13 
Mississippi River at St. Louis, Mo. (LMS) 14-15 
Mississippi River Bank Revetments and Dikes 
(MR+T) 42-30, 42-34, 42-39 
Mississippi River, Baton Rouge to Gulf of Mexico, 
La. (LMN) 11-2, 11-10, 11-12 
Mississippi River between Brainerd and Grand 
Rapids, Minn. (NCS) 27-23 
Mississippi River between Missouri River and 
Minneapolis, Minn. (NCS) (NCD) 27-2, 28-3, 
29-1, 29-4, 29-10 
Mississippi River between Ohio and Missouri Rivers, 
Mo. and Ill. (LMS) 14-2, 14-9, 14-11 
Mississippi River Channel Improvements (MR+T) 
42-29, 42-50, 42-51, 42-53 
Mississippi River Commission (MR+T) 42-1 
Mississippi River Delta at and below New Orleans, 
La., (New Orleans to Venice, La., Hurricane 
Protection) (LMN) 11-8, 11-11, 11-13 
Mississippi River Delta Region, La. (MR+T) 42-59 
Mississippi River-Gulf Outlet, La. (LMN) 11-3, 
11-10, 11-12 
Mississippi River-Gulf Outlet, Michoud Canal, La. 
(LMN) 11-15 
I-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Mississippi River Headwater Reservoirs, Minn. 
(NCS) 27-2, 27-19, 27-22, 27-26 
Mississippi River Improvements (MR+T) 42-11 
Mississippi River Levees (MR+T) 42-10, 42-28, 
42-44, 42-46, 42-47, 42-49 
Mississippi River Main Stem Channel Improvements 
(MR+T) 42-29 
Mississippi River near Aitkin, Minn. (NCS) 27-24 
Mississippi River Outlets, Venice, La. (LMN) 11-4, 
11-10, 11-12 
Mississippi River Project Levees (MR+T) 42-44, 
42-46, 42-47, 42-49 
Mississippi River Tributary and Outlet 
Improvements (MR+T) 42-13 
Mississippi River Tributary Dams and Lakes 
(MR+T) 42-20 
Missouri National Recreational River, Nebr. and S. 
Dak. (MRO) 21-4, 21-11, 21-13 
Missouri River, Mo. (MR+T) 42-19 
Missouri River at New Haven, Mo. (MRK) 20-17 
Missouri River, Aten, Nebr. (MRO) 21-17 
Missouri River, Bank Protection, Greenwood, S. 
Dak. (MRO) 21-20 
Missouri River, Bank Stabilization, Fort Benton, 
Mont. (MRO) 21-19 
Missouri River, Garrison Dam to Lake Oahe, N. Dak. 
(MRO) 21-5, 21-11, 21-14, 21-19 
Missouri River, Kenslers Bend, Nebr. to Sioux City, 
Iowa (MRO) 21-5, 21-11, 21-14 
Missouri River Levee System, Iowa, Nebr., Kans., 
and Mo. (Rulo, Nebr. to Mouth) (MRK) 20-5, 
20-11, 20-14, 20-18, 20-19, 20-21 
Missouri River Levee System, Iowa, Nebr., Kans., 
and Mo. (Sioux City, Iowa, to Rulo, Nebr.) (MRO) 
21-5, 21-11, 21-14, 21-18, 21-19, 21-21 
Missouri River Main Stem (MRK) 20-19 
Missouri River, Marina, Sioux City, Iowa (MRO) 
21-21 
Missouri River, Niobrara, Nebr. (MRO) 21-17 
Missouri River, Sioux City, Iowa, to Fort Benton, 
Mont. (MRO) 21-16 
Missouri River, Sioux City, Iowa, to Mouth (Rulo, 
Nebr., to Mouth) (MRK) 20-2, 20-10, 20-13 
Missouri River, Sioux City, Iowa, to Rulo, Nebr. 
(MRO) 21-2, 21-10, 21-13, 21-18 
Mitigation of Shore Damages, Detroit, Mich., District 
(NCE) 31-26 
Mobile Bay, Ala. to New Orleans, La. (SAM) 
10-35 
Mobile Harbor, Ala. (SAM) 10-9, 10-27, 10-36 
Mocassin Swamp, N.C. (SAW) 6-28 
Moccasin Springs, Mo. (LMS) 14-13 
Moclips River, Wash. (NPS) 38-27 
Mojave River Dam, Calif. (SPL) 33-6, 33-12, 
33-17 
Mokelumne River, Calif. (SPK) 35-30 
Molalla River at Milk Creek location, Oreg. (NPP) 
37-42 
Molalla River at Ressel location, Oreg. (NPP) 37-42 
Moline, Ill. (NCR) 28-9, 28-13 
Moline Harbor, Ill. (NCD) 29-7 
Monona-Harrison Ditch Control, Monona County, 
Iowa (MRO) 21-21 
Monongahela River, Pa. and W. Va. Locks and Dams 
(ORP) 26-2, 26-13, 26-17, 26-25, 26-26 
Monoosnoc Brook, Mass. (NED) 1-43, 1-51 
Monoosnoc Lake, Mass. (NED) 1-43, 1-51 
Monroe, La., floodwall extension (LMK) 12-16 
Monroe Bay and Creek, Va. (NAB) 4-34 
Monroe Floodwall, La. (LMK) 12-19 
Monroe Harbor, Mich. (NCE) 31-16, 31-39, 31-52 
Monroe Lake, Ind. (ORL) 24-9, 24-16, 24-27 
Montcalm, W. Va. (ORH) 25-22 
Monterey Harbor, Calif. (SPN) 34-8 
Montgomery Locks and Dam, Pa. (ORD) 22-2, 
22-7 
Montour Falls, N.Y. (NCB) 32-37 
Moore Haven Lock, Fla. (SAJ) 9-48 
Moorefield, W. Va. (NAB) 4-37 
Moores Ferry, Va. (ORH) 25-20 
Moorhead, Minn. (NCS) 27-25 
Mooring for Battleship Oregon, Oreg. (NPP) 37-39 
Moosabec Bar, Maine (NED) 1-39 
Morehead City Harbor, N.C. (SAW) 6-7, 6-19 
Morgan City and Vicinity, La. (LMN) 11-7, 11-10, 
11-13 
Morgantown Lock and Dam, W. Va. (ORP) 26-25 
Morganza Floodway, La. (MR+T) 42-50 
Moriches Inlet, N.Y. (NAN) 2-7, 2-23, 2-28 
Mormon Slough, Calif. (SPK) 35-31 
Morrison, Colo. (MRO) 21-18 
Morrison Creek Stream Group, Calif. (SPK) 35-20 
Morristown Harbor, N.Y. (NCB) 32-35 
Morro Bay Harbor, Calif. (SPL) 33-2, 33-10, 
33-15 
Moscow, Ohio (ORL) 24-22, 24-25 
Mosquito Creek Lake, Ohio River Basin, Ohio (ORP) 
26-8, 26-14, 26-19, 26-27 
Moss Bluff Lock, Fla. (SAJ) 9-52 
Moss Landing Harbor, Calif. (SPN) 34-5 
Mott, N. Dak. (MRO) 21-17 
Mound City Locks and Dam, Ill. (ORD) 22-1, 
22-10 
Mounds and Mound City, Ill. (LMM) 13-6 
Moundsville, W. Va. (ORP) 26-22, 26-26 
Mount Clemens, Clinton River, Mich. (NCE) 31-63 
Mount St. Helens and Vicinity, Wash. (NPP) 37-15, 
37-27, 37-37 
Mount St. Helens Emergency Measures, Wash. 
(NPP) 37-13 
Mount St. Helens Sediment Control, Wash. (NPP) 
37-16, 37-27, 37-37 
1-30

INDEX 
Mountain Brook Dam, N.H. (NED) 1-45 
Mountain Park Reservoir (Tom Steed Lake), Okla. 
(SWT) 19-18 
Mouth of Yazoo River, Miss. (LMK) 12-14 
Moyock Creek, N.C. (SAW) 6-28 
Mt. Baldy, Indiana Dunes National Lakeshore, Ind. 
(NCC) 30-15 
Mt. Carmel, Ill. (ORL) 24-20, 24-29 
Mt. Holly, N.J. (NAP) 3-23 
Mt. Morris Lake, N.Y. (NCB) 32-15, 32-22 
Mud and Basket Slough, Rickreall Creek, Oreg. 
(NPP) 37-44 
Mud Creek, Broken Bow, Nebr. (MRO) 21-17, 
21-20 
Mud Lake, Idaho (NPW) 39-15, 39-16 
Mud Lake Pumping Station, Tenn. (MR+T) 42-28 
Mud Mountain Dam, Wash. (NAS) 38-9, 38-16, 
38-22 
Mud River, W. Va. (ORH) 25-21 
Muddy Creek Dam, Pa. (ORP) 26-22 
Muddy Creek near Syracuse, Nebr. (MRO) 21-20 
Muddy Hook and Tyler Coves, Md. (NAB) 4-34, 
4-38 
Mulberry Creek, Va. (NAO) 5-23 
Mullet Key, Fla. (SAJ) 9-47 
Multnomah Channel, Oreg. (NPP) 37-39 
Multnomah Drainage District 1, Oreg. (NPP) 37-40, 
37-41, 37-48 
Muncie, Ind. (ORL) 24-20, 24-29 
Munday Floodway, Tex. (SWF) 16-22 
Murder and Burnt Corn Creeks, Brewton, Ala. 
(SAM) 10-15, 10-29, 10-39, 10-43 
Murder Creek, East Brewton, Ala. (SAM) 10-14, 
10-29, 10-39 
Murderkill River, Del. (NAP) 3-7, 3-14, 3-16, 
3-19 
Murfreesboro Dam and Lake (LMK) 12-19 
Murray Lock - Dam, Ark. (SWL) 18-3, 18-19 
Murrells Inlet, S.C. (SAN) 7-5, 7-10, 7-13 
Muscatatuck River, Crothersville, Ind. (ORL) 24-30 
Muscatine, Iowa (Mad Creek) (NCR) 28-14 
Muscatine Harbor, Iowa (NCD) 29-7 
Muscatine Island L. and D. D., Louisa D. D. No. 13, 
Iowa (NCR) 28-14, 28-17 
Muscooten Bay, Ill. (NCR) 28-13 
Muskegon Harbor, Mich. (NCE) 31-16, 31-39, 
31-52 
Muskingum River, Ohio (ORH) 25-19 
Muskingum River Lakes, Ohio (ORH) 25-7, 25-14, 
25-17 
Mustinka River, Minn. (NCS) 27-27 
Myers Chuck Harbor, Alaska (NPA) 40-13 
Myrtle Beach, S.C. (SAN) 7-17 
Mystic, Conn. (NED) 1-45 
Mystic River, Conn. (NED) 1-39 
Mystic River, Mass. (NED) 1-6, 1-26, 1-34 
N 
Naches River, Naches, Wash. (NPS) 38-27 
Nagel Drainage District, Iowa (MRO) 21-21 
Nahunta Swamp, N.C. (SAW) 6-28 
Naknek River, Alaska (NPA) 40-13 
Namo River, Territory of Guam (POD) 36-11 
Nan Cove, Md. (NAB) 4-34 
Nandua Creek, Va. (NAO) 5-23 
Nanpil River Hydropower, Pohnpei, Trust Territory 
of the Pacific Islands (POD) 36-5, 36-6, 36-7 
Nansemond River, Va. (NAO) 5-23 
Nantasket Beach, Mass. (NED) 1-42 
Nanticoke River, Md. (NAB) 4-34 
Nanticoke River at Bivalve, Md. (NAB) 4-34 
Nanticoke River (including Northwest Fork), Del. 
and Md. (NAB) 4-34 
Nantucket (Harbor of Refuge), Mass. (NED) 1-39 
Napa River, Calif. (SPN) 34-5 
Napa River Basin, Calif. (SPK) 35-31 
Napatree Beach, R.I. (NED) 1-45 
Narragansett Pier, R.I. (NED) 1-45 
Narraguagus River, Maine (NED) 1-24, 1-39, 1-53 
Narrows Dam-Lake Greeson, Ark. (LMK) 12-16, 
12-19 
Narrows of Lake Champlain, N.Y. and Vt. (NAN) 
2-8, 2-23, 2-28, 2-33 
Nashua, N.H. (NED) 1-22, 1-43, 1-51 
Natchez Port Area, Miss. (LMK) 12-19 
Natchitoches Parish, La. (LMN) (LMK) 11-16, 
12-18, 12-19 
National Dredging Program 53-4 
National Emergency Management Activities, 
Huntington, W.Va., District (ORH) 25-11 
National Emergency Preparedness Activities, 3-14, 
21-9, 32-16, 48-1 
Natural Disaster Activities, New York District (NAN) 
2-20 
Natural Disaster Preparedness, Response and 
Recovery Activities, 43-1 
Navajo Reservoir, N. Mex. (SPK) 35-30 
Navarro Mills Lake, Tex. (SWF) 16-9, 16-16, 
16-20 
Navasota Lake, Tex. (SWF) 16-22 
Navigation Aids (U.S. Coast Guard), Ark. (SWL) 
18-21 
Navigation Locks and Dams, Ark. (SWL) 18-11 
Navigation Work under Special Authorization 
(Calcasieu Pass Channel in Old River Bend at 
Cameron, La.) (LMN) 11-15 
Nawiliwili Harbor, Hawaii (POD) 36-3, 36-6, 36-7 
Nawiliwili Small Boat Harbor, Hawaii (POD) 36-8 
NCD Master Plan for Water Control Data System 
31-30 
Neabsco Creek, Md. (NAB) 4-34 
Neah Bay, Wash. (NPS) 38-25 
1-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Neale Sound, Md. (NAB) 4-34 
Near Dardanelle, Arkansas River, Ark. (SWL) 18-17 
Near Springfield on Sangamon River, Ill. (NCR) 
28-14 
Neavitt Harbor, Md. (NAB) 4-34 
Neches River and Tributaries, Salt Water Barrier at 
Beaumont, Tex. (SWG) 15-27 
Needles, Calif. (SPL) 33-20, 33-31 
Nehalem Bay, Oreg. (NPP) 37-7, 37-25, 37-34 
Neodesha Lake, Kans. (SWL) (SWT) 18-22, 19-15, 
19-16 
Neon-Fleming, Ky. (ORL) 24-20, 24-30 
Neshaminy State Park Harbor, Pa. (NAP) 3-21 
Nestucca River, Oreg. (NPP) 37-39, 37-42 
Neuse River, N.C. (SAW) 6-25, 6-28 
Neuse River Barrier, N.C. (SAW) 6-28 
Neuse River Basin, N.C. (SAW) 6-12, 6-30 
Neuse River, 300 foot-wide channel in front of New 
Bern, N.C. (SAW) 6-28 
Neva and Olga Straits, Alaska (NPA) 40-13 
Neville Island, Pa. (ORP) 26-22, 26-26 
New Albany, Ind. (ORL) 24-20, 24-24, 24-29 
New Amsterdam, Ind. (ORL) 24-22, 24-25 
New Bedford and Fairhaven Harbors, Mass. (NED) 
1-39 
New Bedford, Fairhaven, and Acushnet, Mass. 
(NED) 1-19, 1-30, 1-36 
New Bedford-Fairhaven Hurricane Barrier, Mass. 
(NED) 1-23 
New Boston Harbor, Ill. (NCD) 29-7 
New Buffalo Harbor, Mich. (NCE) 31-16, 31-40, 
31-53 
New Bullards Bar, Calif. (SPK) 35-31 
New Cumberland, W. Va. (ORP) 26-23 
New Cumberland Locks and Dam, Stratton, Ohio 
(ORD) 22-7 
New Fairfield, Conn. (NED) 1-22 
New Harbor, Maine (NED) 1-39 
New Harmony, Ind. (ORL) 24-22, 24-25 
New Harmony Bridge, Ill. and Ind. (ORL) 24-20, 
24-21, 24-24 
New Haven Breakwater, Conn. (NED) 1-39 
New Haven Harbor, Conn. (NED) 1-6, 1-26, 1-34, 
1-38 
New Jersey Intracoastal Waterway (NAP) 3-8, 
3-16, 3-19 
New Kensington and Parnassus, Pa. (ORP) 26-22, 
26-26 
New Lock and Dam 26, Ill. (NCD) 29-6 
New London, Conn. (NED) 1-19, 1-22, 1-23, 
1-30, 1-37 
New London Harbor, Conn. (NED) 1-7, 1-26, 
1-34, 1-53 
New Madrid Harbor, Mo. (LMM) 13-5 
New Martinsville, W. Va. (ORH) 25-21 
New Matamoras, Ohio (ORH) 25-21 
New Melones Lake, Calif. (SPK) 35-19 
New Orleans to Venice, La., Hurricane Protection 
(LMN) 11-8, 11-11, 11-13 
New Pass, Sarasota, Fla. (SAJ) 9-10, 9-27, 9-35 
New Richmond, Ohio (ORL) 24-22, 24-25 
New River, Fla. (SAJ) 9-45, 9-46 
New River, N.C. (SAW) 6-27 
New River, Onslow County, N.C. (SAW) 6-27 
New River, Va. and W. Va. (ORH) 25-19 
New Rochelle Harbor, N.Y. (NAN) 2-34 
New York and New Jersey Channels, (NAN) 2-10, 
2-24, 2-29, 2-32, 2-33, 2-38 
New York Harbor, N.Y. (NAN) 2-33 
New York Harbor-Collection and Removal of Drift 
(NAN) 2-11, 2-24, 2-29 
New York Harbor-Entrance Channels and 
Anchorage Areas (NAN) 2-11, 2-24, 2-29 
New York Harbor, Supervisor of (NAN) 2-16, 2-25, 
2-32 
Newark, Ohio (ORH) 25-7, 25-14, 25-17, 25-20, 
25-22 
Newark Bay, Hackensack and Passaic Rivers, N.J. 
(NAN) 2-8, 2-23, 2-28, 2-33, 2-38 
Newaukum River, Wash. (NPS) 38-27 
Newbegun Creek, N.C. (SAW) 6-25 
Newburgh, Ind. (ORL) 24-20 
Newburgh Locks and Dam, Ind. (ORD) 22-3, 22-9 
Newburyport Harbor, Mass. (NED) 1-7, 1-26, 
1-34, 1-53 
Newhall Creek, Calif. (SPL) 33-25 
Newmarket Creek, Va. (NAO) 5-24 
Newport, Ark. (SWL) 18-17 
Newport, Ky. (ORL) 24-20, 24-21, 24-24, 24-29 
Newport, Ohio (ORH) 25-21 
Newport Bay Harbor, Calif. (SPL) 33-18 
Newport Harbor, R.I. (NED) 1-39 
Newport News, Va. (NAO) 5-24 
Newport News Creek, Va. (NAO) 5-23 
Newry-Old Pickens Dam and Lake, S.C. (SAS) 
8-17 
Newt Graham Lock and Dam, Okla. (SWL) (SWT) 
18-20, 19-16 
Newtown Creek, N.Y. (NAN) 2-9, 2-24, 2-29, 
2-33 
Niagara Remedial Works, N.Y. (NCB) 32-35 
Niagara River, N.Y. (NCB) 32-35, 32-39 
Niantic Bay and Harbor, Conn. (NED) 1-39 
Niblack, Mason J., Levee, Ind. (ORL) 24-4, 24-14, 
24-20, 24-24, 24-29 
Nicholasville, (Townfork) Vicinity, Ky. (ORL) 24-30 
Nichols, N.Y. (NAB) 4-36, 4-39 
Nickajack Lock and Dam, Tenn. (ORN) 23-17 
Nimrod Lake, Ark. (SWL) 18-7, 18-12, 18-22 
Ninilchik Harbor, Alaska (NPA) 40-4, 40-9, 40-12 
Nishnabotna River at Hamburg, Iowa (MRO) 21-17, 
21-21 
1-32

INDEX 
Nisqually River, Wash. (NPS) 38-27 
Nixon Creek, Tenn. (LMM) 13-6 
Nolin Lake, Ky. (ORL) 24-9, 24-16, 24-27 
Nome Harbor, Alaska (NPA) 40-4, 40-9, 40-12 
Nomini Bay and Creek, Va. (NAB) 4-34 
Nonconnah Blvd., Nonconnah Creek, Tenn. (LMM) 
13-6 
Nonconnah Creek, Interceptor Sewer, Memphis, 
Tenn. (LMM) 13-2, 13-4 
Nonewaug River, Conn. (NED) 1-43 
Nookagee Lake, Mass. (NED) 1-43, 1-51 
Nooksack River, Wash. (NPS) 38-27 
Norfolk, Nebr. (MRO) 21-17, 21-20 
Norfolk Floodwall, Va. (NAO) 5-24 
Norfolk Harbor, Va. (NAO) 5-6, 5-15, 5-19, 5-25 
Norfork Lake, Ark. (SWL) 18-9, 18-13, 18-24 
Normal, Ky. (ORH) 25-20 
Norman Reservoir (Lake Thunderbird), Okla. (SWT) 
19-18 
Norrell Lock - Dam (No. 1) - Entrance Channel, 
Ark. (SWL) 18-4, 18-18 
North Adams, Hoosic River Basin, Mass. (NAN) 
2-36 
North Alexander Drainage and Levee District, Ill. 
(LMS) 14-15 
North Andover and Lawrence, Mass. (NED) 1-45 
North Branch of Kokosing River Lake, Ohio (ORH) 
25-7, 25-14, 25-17 
North Canaan, Conn. (NED) 1-22, 1-43, 1-50 
North Ellenville, N.Y. (NAN) 2-36 
North Fork of Pound River Lake, Va. (ROH) 25-8, 
25-14, 25-17 
North Fork, Pit River at Alturas, Calif. (SPK) 35-31 
North Fork Skykomish River, Wash. (NPS) 38-27 
North Hampton Beach, North Hampton, N.H. (NED) 
1-45 
North Hartland Lake, Vt. (NED) 1-14, 1-28, 1-48 
North Little Rock, Arkansas River, Ark. (SWL) 
18-17 
North Nashua River, Fitchburg, Mass. (NED) 1-43 
North Nashua River, Lancaster, Mass. (NED) 1-43, 
1-51 
North River Dike, N.C. (SAW) 6-28 
North Scituate Beach, Scituate, Mass. (NED) 1-42 
North Second St., Memphis, Tenn. (Wolf River 
Bridge) (LMM) 13-6 
North Shore of Long Island, Suffolk County, N.Y. 
(NAN) 2-36 
North Springfield Lake, Vt. (NED) 1-14, 1-28, 
1-48 
North Stratford, N.H. (NED) 1-22, 1-49 
North Wildwood, N.J. (NAP) 3-23 
Northampton, Mass. (NED) 1-22, 1-43, 1-49 
Northeast (Cape Fear) River, N.C. (SAW) 6-25, 
6-27 
Northeast Harbor, Maine (NED) 1-39 
Northeast River, Md. (NAB) 4-34 
Northfield Brook Lake, Conn. (NED) 1-17, 1-29, 
1-49 
Northport Harbor, N.Y. (NAN) 2-34 
Northport Harbor, Wis. (NCE) 31-62 
Norwalk, Conn. (NED) 1-22, 1-43 
Norwalk Harbor, Conn. (NED) 1-39 
Norwalk-Wilton, Conn. (NED) 1-45 
Norwich, Conn. (NED) 1-43, 1-52 
Norwich, N.Y. (NAB) 4-36, 4-39 
Nottoway River, Va. (NAO) 5-7, 5-15, 5-20 
Noxubee River, Miss. (SAM) 10-15, 10-29, 10-39, 
10-42 
Noyo River and Harbor, Calif. (SPN) 34-5 
Nutwood Drainage and Levee District, Ill. (LMS) 
14-6, 14-10, 14-12 
O 
Oahe Dam-Lake Oahe, Missouri River Basin S. Dak. 
and N. Dak. (MRO) 21-9, 21-12, 21-16, 21-19 
Oak Bluffs Town Beach, Mass. (NED) 1-42 
Oak Orchard Harbor, N.Y. (NCB) 32-8, 32-20 
Oakdale, Pa. (ORP) 26-22 
Oakford Special Drainage District (NCR) 28-14, 
28-17 
Oakland Beach, Warwick, R.I. (NED) 1-42 
Oakland Harbor, Calif. (SPN) 34-5, 34-9 
Oates Creek, Ga. (SAS) 8-10, 8-16 
Obey River, Tenn. (ORN) 23-13 
Obion River, Tenn. (LMM) 13-5 
O'Brien, T.J., Lock and Dam, Ill. (NCC) 28-20, 
28-21 
Occohannock Creek, Va. (NAO) 5-23 
Occoquan Creek, Va. (NAB) 4-34 
Ocean Beach, Calif. (SPL) 33-19 
Ocean City, N.J. (NAP) 3-23 
Ocean City Harbor and Inlet and Sinepuxent Bay, 
Md. (NAB) 4-7, 4-23, 4-29 
Oceana, W. Va. (ORH) 25-20 
Oceanside, Calif. (SPL) 33-19 
Oceanside Harbor, Calif. (SPL) 33-2, 33-10, 33-15 
Ocholockonee (Ochlockney) River, Ga. and Fla. 
(SAM) 10-42 
Oconto Harbor, Wis. (NCE) 31-62 
Ocracoke Inlet, N.C. (SAW) 6-7, 6-19 
Ocracoke Island, N.C. (SAW) 6-27 
Ofu Airstrip, American Samoa (POD) 36-3, 36-6 
Ofu Small Boat Harbor, American Samoa (POD) 
36-8 
Ogdensburg Harbor, N.Y. (NCB) 32-9, 32-20, 
32-31 
Ohio National Wildlife Conservation Area (ORD) 
22-3 
Ohio River, Ill. and Ky. (MR+T) 42-19 
I-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Ohio River Basin (Huntington District) (ORH) 
25-8, 25-14 
Ohio River Basin (Louisville Dist.) (ORL) 24-10, 
24-16, 24-18, 24-24, 24-30 
Ohio River Basin (Nashville District) (ORN) 23-6, 
23-12, 23-18 
Ohio River Basin (Pittsburgh District) (ORP) 26-8, 
26-14, 26-19, 26-26, 26-27 
Ohio River, Locks and Dams (ORD) 22-1, 22-5, 
22-6 
Ohio River, Open Channel Work (ORD) 22-4, 22-5, 
22-6 
Oil City, Pa. (ORP) 26-22 
Okabena Creek at Worthington, Minn. (NCR) 28-14 
Okanogan and Pend Oreille Rivers (NPS) 38-25 
Okanogan River, Wash. (NPS) 38-28 
Okanogan River, Omak, Wash. (NPS) 38-28 
Okanogan River, Oroville, Wash. (NPS) 38-28 
Okatibbee Lake, Miss. (SAM) 10-12, 10-28, 
10-38 
Okeechobee Waterway, Fla. (SAJ) 9-10, 9-27, 
9-35, 9-44, 9-45, 9-47 
Oklahoma City Floodway, Okla. (SWT) 19-15, 
19-17, 19-18 
Oklawaha River, Fla. (SAJ) 9-11, 9-27, 9-35 
Olcott Harbor, N.Y. (NCB) 32-9, 32-20, 32-31 
Old Field Swamp, N.C. (SAW) 6-27 
Old Harbor, Kodiak Island, Alaska (NPA) 40-13 
Old Hickory Lock and Dam, Tenn. (ORN) 23-14 
Old Highway 82 Bridge, Columbus, Miss. (SAM) 
10-17, 10-29, 10-40 
Old River, Calif. (SPK) 35-30 
Old River, La. (MR+T) 42-6, 42-28, 42-50 
Old River, Standard Revetments (MR+T) 42-31 
Old Town Creek, Miss. (SAM) 10-42 
Oldmans Creek, N.J. (NAP) 3-21, 3-24 
Olean, N.Y. (ORP) 26-22, 26-26 
Olive Hill, Ky. (ORH) 25-22 
Olympia Harbor, Wash. (NPS) 38-5, 38-15, 38-21 
Omaha, Nebr. (MRO) 21-17, 21-19, 21-20 
Onaga Lake, Kans. (MRK) 20-17 
Onancock River, Va. (NAO) 5-23 
Oneonta, N.Y. (NAB) 4-39 
Onondaga Creek, Nedrow, N.Y. (NCB) 32-37 
Ontonagon Harbor, Mich. (NCE) 31-17, 31-40, 
31-53 
Oologah Lake, Okla. (SWL) (SWT) 18-22, 19-5, 
19-11, 19-14, 19-16, 19-17 
Oostanaula and Coosawatee River, Ga. (SAM) 
10-42 
Opekiska Lock and Dam, W. Va. (ORP) 26-25 
Open Channel Work, Ohio River (ORD) 22-4, 22-5, 
22-6 
Open River Lewiston to Johnson Bar Landing 
(NPW) 39-22 
Open River Pasco to Lewiston (NPW) 39-22 
Optima Lake, Okla. (SWT) 19-5, 19-11, 19-14, 
19-17 
Orange River, Fla. (SAJ) 9-45, 9-46 
Orchard Beach, Bronx, N.Y. (NAN) 2-39 
Oregon Slough (North Portland Harbor), Oreg. 
(NPP) 37-39 
Orleans, Ind. (ORL) 24-22 
Oro Grande Wash Channel Improvements, Calif. 
(SPL) 33-20, 33-31 
Orofmo Creek and Clearwater River, Idaho (NPW) 
39-15 
Orowoc Creek, N.Y. (NAN) 2-34 
Orwell Reservoir (Otter Tail River) (NCS) 27-27 
Osage River, Kans. and Mo. (MRK) 20-19 
Osage River, Mo., Lock and Dam (MRK) 20-16 
Osawatomie, Kans. (MRK) 20-17, 20-19 
Osborne Creek, Highway 362 Bridge, Prentiss 
County, Miss. (SAM) 10-43 
Osceola Harbor, Ark. (LMM) 13-5 
Oslo, Minn. (NCS) 27-27 
Oswego Harbor, N.Y. (NCB) 32-11, 32-35, 32-39 
Ottawa, Kans. (MRK) 20-17, 20-19 
Ottawa, Ohio (NCB) 32-15 
Ottawa River Harbor, Mich. and Ohio (NCB) 
32-35 
Otter Brook Lake, N.H. (NED) 1-14, 1-28, 1-48 
Otter Creek, Vt. (NAN) 2-34 
Otter Creek and Tributaries, Shannon Hills, Ark. 
(SWL) 18-7, 18-12 
Otter Creek Park, Ky. (ORL) 24-31 
Otter Tail River, Minn. (NCS) 27-27 
Ottumwa, Iowa (NCR) 28-15 
Ouachita and Black Rivers, Ark. and La. (Felsenthal 
Canal) (LMK) 12-14 
Ouachita and Black Rivers, Ark. and La., Locks and 
Dams (LMK) 12-13 
Ouachita and Black Rivers below Camden, Ark. 
(LMK) 12-2, 12-9, 12-11 
Ouachita River and Tributaries, Ark. and La. (LMK) 
12-5, 12-12, 12-16 
Ouachita River Basin (LMK) 12-21 
Ouachita River Levees, La. (LMK) 12-5, 12-9, 
12-16 
Ouzinkie Small Boat Harbor, Alaska (NPA) 40-15 
Overton-Red River Waterway, La. (LMK) 12-14 
Owasco Inlet and Outlet, Montville and Dry Creek, 
State Ditch and Crane Brook, N.Y. (NCB) 32-37 
Owego, N.Y. (NAB) 4-39 
Owensboro, Ky. (ORL) 24-21, 24-24 
Owl's Head Harbor, Maine (NED) 1-39 
Owyhee River, Oreg. (NPW) 39-3, 39-9, 39-12 
Oxford, Md. (NAB) 4-35 
Oxford, N.Y. (NAB) 4-16, 4-26 
Oyster Channel, Va. (NAO) 5-23 
Oyster Creek, Tex. (SWG) 15-27 
Ozan Creek, Ark. (LMK) 12-16 
1-34

INDEX 
Ozark-Jeta Taylor Lock - Dam, Ark. (SWL) 18-9, 
18-13, 18-20 
Ozona, Fla. (SAJ) 9-46 
P 
Paauau Stream, Hawaii (POD) 36-11 
Paducah, Ky. (ORL) 24-20, 24-24, 24-29 
Pagan River, Va. (NAO) 5-23 
Pago Pago Airport, American Samoa (POD) 36-10 
Pago Pago to Nuuuli, American Samoa (POD) 
36-10 
Paint Creek at Chillicothe, Ohio (ORH) 25-22 
Paint Creek at Washington Court House, Ohio 
(ORH) 25-22 
Paint Creek Lake, Ohio (ORH) 25-8, 25-14, 25-18 
Paint Rock River, Ala. (ORN) 23-13, 23-19 
Painted Post, N.Y. (NAB) 4-36, 4-39 
Painted Rock Dam, Ariz. (SPL) 33-4, 33-11, 33-15 
Paintsville Lake, Ky. (ORH) 25-8, 25-14, 25-18 
Pajaro River Basin, Calif. (SPK) 35-22, 35-27 
Palm Beach, Fla. (SAJ) 9-46 
Palm Beach County, Fla., from Lake Worth Inlet to 
South Lake Worth Inlet (SAJ) 9-47 
Palm Beach County, Fla., from Martin County Line 
of Lake Worth Inlet and from South Lake Worth 
Inlet to Broward County Line (SAJ) 9-20, 9-29, 
9-40 
Palm Beach Harbor, Fla. (SAJ) 9-11, 9-27, 9-36 
Palouse River, Wash. (NPW) 39-15, 39-16 
Pamlico and Tar Rivers, N.C. (SAW) 6-7, 6-19 
Pamunkey River, Va. (NAO) 5-23 
Panacea Harbor, Fla. (SAM) 10-42, 10-45 
Panama City Harbor, Fla. (SAM) 10-9, 10-27, 
10-36, 10-45 
Pantego Creek and Cucklers Creek, N.C. (SAW) 
6-27 
Panther Creek, Curdsville, Ky. (ORL) 24-20, 24-30 
Panther Creek, W. Va. (ORH) 25-20 
Papillion Creek and Tributaries Lakes, Nebr. (MRO) 
21-5, 21-11, 21-14 
Parish Creek, Md. (NAB) 4-7, 4-23, 4-30 
Park City, Kans. (SWT) 19-17 
Park River, Hartford, Conn. (NED) 1-14, 1-28, 
1-36, 1-49 
Parker Creek, Va. (NAO) 5-7, 5-15, 5-20 
Parkersburg, W. Va. (ORH) 25-20, 25-22 
Parrotts Creek, Va. (NAO) 5-23 
Pascagoula Harbor, Miss. (SAM) 10-10, 10-28, 
10-36 
Pascagoula River, Miss. (SAM) 10-42, 10-45 
Pasquotank River, N.C. (SAW) 6-27 
Pass Christian, Miss. (SAM) 10-42, 10-45 
Pass Christian Harbor, Miss. (SAM) 10-42 
Pass Manchac, La. (LMN) 11-15 
Pass-a-Grille Pass, Fla. (SAJ) 9-45, 9-46 
Passaic River, N.J. (NAN) 2-39 
Passaic River Basin, N.J. and N.Y., Phase I (NAN) 
2-18, 2-31 
Passamaquoddy Tidal Power Project, Maine (NED) 
1-44 
Pat Mayse Lake, Tex. (SWT) 19-5, 19-11, 19-14, 
19-17 
Pataha Creek, Wash. (NPW) 39-15 
Patchogue River, Conn. (NED) 1-39 
Patman, Wright, Dam and Lake, Tex. (LMN) (SWF) 
11-17, 16-12, 16-17, 16-21 
Patoka Lake, Ind. (ORL) 24-10, 24-16, 24-27 
Patoka River at Jasper, Ind. (ORL) 24-30 
Patoka River, Winslow, Ind. (ORL) 24-30 
Patriot, Ind. (ORL) 24-22, 24-25 
Patten Bay, Maine (NED) 1-46 
Pattonsburg Lake, Mo. (MRK) 20-17 
Patuxent River, Md. (NAB) 4-34 
Pawcatuck, Conn. (NED) 1-22, 1-23, 1-43 
Pawcatuck River, R.I. and Conn. (NED) 1-39, 1-45 
Pawtucket, R.I. (NED) 1-45 
Pawtuxet Cove, R.I. (NED) 1-39 
Pawtuxet River, Cranston, R.I. (NED) 1-23 
Pawtuxet River, Warwick, R.I. (NED) 1-11, 1-27, 
1-36, 1-47, 1-48 
Pax, W. Va. (ORH) 25-22 
Payette River, Idaho (NPW) 39-15 
Payette Valley, Idaho (NPW) 39-16 
Peacock Creek, Liberty County, Ga. (SAS) 8-7, 
8-16 
Pearl River, Miss. and La. (LMK) 12-6, 12-9, 
12-12, 12-14, 12-21 
Pearl River Basin, Miss. and La. (LMK) 12-6, 
12-21 
Pearl River, Interstate 20 Bridges, Jackson, Miss. 
(SAM) 10-43 
Pearson-Skubitz Big Hill Lake, Kans. (SWT) 19-5, 
19-11, 19-14, 19-17 
Pebble Creek, Scribner, Nebr. (MRO) 21-22 
Pecan Bayou Lake, Pecan Bayou, Tex. (SWF) 16-22 
Pecatonica River at Darlington, Wis. (NCR) 28-16 
Peconic River, N.Y. (NAN) 2-34 
Pecos, Tex. (SWA) 17-7, 17-10 
Peekskill Harbor, N.Y. (NAN) 2-34 
Pekin-LaMarsh Drainage and Levee District, Ill. 
(NCR) 28-15, 28-17 
Pelican Harbor, Alaska (NPA) 40-13 
Pembina, N. Dak. (NCS) 27-27 
Pembina River, N. Dak. (NCS) 27-24 
Pembina River Lake, N. Dak. (NCS) 27-24 
Pembroke Creek, N.C. (SAW) 6-25 
Pendleton, Oreg. (NPP) 37-42 
Pendleton Levees, Oreg. (NPP) 37-42 
Peninsula Drainage District 1, Oreg. (NPP) 37-40, 
37-44, 37-48 
I-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Peninsula Drainage District 2, Oreg. (NPP) 37-40, 
37-41, 37-48 
Penny Slough, Ill. (NCR) 28-15, 28-17 
Penobscot River, Old Town, Maine (NED) 1-20, 
1-31, 1-37, 1-39 
Pensacola Bay, Fla. to Mobile Bay, Ala. (SAM) 
10-35 
Pensacola Harbor, Fla. (SAM) 10-10, 10-28, 
10-37, 10-45 
Pensacola Lake, Okla. (SWL) 18-22 
Pensaukee Harbor, Wis. (NCE) 31-17, 31-40, 
31-53 
Pentwater Harbor, Mich. (NCE) 31-17, 31-40, 
31-53, 31-63 
Peoria, Ill. (NCC) 28-15 
Peoria Lock and Dam, Ill. (NCC) 28-20 
Pepin Harbor, Wis. (NCD) 29-7 
Pepper Creek, Del. (NAP) 3-21 
Pepperell Cove, Maine (NED) 1-39, 1-45 
Perdido Pass Channel, Ala. (SAM) 10-11, 10-28, 
10-38 
Permanent International Association of Navigation 
Congresses (PIANC) 46-1 
Perquimans River, N.C. (SAW) 6-25, 6-27 
Perry County Drainage and Levee Districts Nos. 1, 
2, and 3, Mo. (LMS) 14-6, 14-10, 14-12 
Perry Lake, Kans. (MRK) 20-5, 20-11, 20-14, 
20-19 
Perry Lake Area (Road Improvements) Kans. (MRK) 
20-17 
Perth Amboy, N.J. (NAN) 2-36 
Petaluma River, Calif. (SPN) 34-6 
Peters Creek, Roanoke, Va. (SAW) 6-31 
Petersburg Harbor, Alaska (NPA) 40-13 
Petit Jean River, Ark. (SWL) 18-17 
Petite Anse, Tigre, and Carlin Bayous, La. (LMN) 
11-15 
Petoskey Harbor, Mich. (NCE) 31-18, 31-40, 
31-53 
Peyton Creek, Tex. (SWG) 15-27 
Phillippi Creek Basin, Fla. (SAJ) 9-53 
Phillips Lake, Mass. (NED) 1-43, 1-51 
Philpott Lake, Va. (SAW) 6-15, 6-16, 6-20 
Phoenix, Ariz., and Vicinity (including New River) 
(SPL) 33-4, 33-11, 33-16 
Pick-Sloan Missouri Basin Program (Kansas City 
Dist) (MRK) 20-5, 20-14 
Pick-Sloan Missouri Basin Program (Omaha Dist) 
(MRO) 21-5, 21-14, 21-19 
Pickwick Landing Lock and Dam, Tenn. (ORN) 
23-17 
Pierce, Nebr. (MRO) 21-17, 21-20 
Pig Island Gut, Maine (NED) 1-39 
Pike Island Locks and Dam, W. Va. (ORD) 22-1, 
22-7 
Pilchuck River, Wash. (NPS) 38-28 
Pilot Rock, Oreg. (NPP) 37-44 
Pinal Creek Channel Improvements (Globe), Ariz., 
(SPL) 33-19 
Pine and Mathews Canyons Dams, Nev. (SPL) 33-7, 
33-12, 33-17 
Pine Bluff, Ark. (LMK) 12-16 
Pine Creek, Angle Inlet, Minn. (NCS) 27-23 
Pine Creek Lake, Okla. (SWT) 19-6, 19-11, 19-14, 
19-18 
Pine Flat Lake and Kings River, Calif. (SPK) 35-12, 
35-24 
Pine Ford Lake, Mo. (LMS) 14-5, 14-9 
Pine Mountain Lake, Ark. (SWL) 18-17 
Pine River, Mich. (NCE) 31-61, 31-62 
Pine River Reservoir, Minn. (NCS) 27-26 
Pinellas County, Fla. (SAJ) 9-21, 9-30, 9-40 
Pineville, Ky. (ORN) 23-13, 23-19 
Pineville, La. (LMN) (LMK) 11-16, 12-18, 12-19 
Pinole Creek, Calif. (SPK) 35-31 
Pinon Canyon Dam, Trinidad, Colo. (SWA) 17-7, 
17-10 
Pioneer Lake, Kans. (MRK) 20-18 
Pipestem Lake, N. Dak. (MRO) 21-6, 21-11, 21-15 
Pithlachascotee River, Fla. (SAJ) 9-45, 9-46 
Pittsburgh, Pa. (Golden Triangle) (ORP) 26-23 
Pittsburgh, Pa. (North Side) (ORP) 26-23 
Pittsburgh, Pa. (The Strip) (ORP) 26-23 
Pittsburgh Harbor, Pa. (ORP) 26-21 
Pittsfield, Mass. (NED) 1-22, 1-50 
Placentia Canal, Ga. (SAS) 8-7 
Placer Creek, Idaho (NPS) 38-9, 38-17, 38-22 
Plainviw Local Flood Protection Project (SWF) 
16-22 
Platoro Reservoir, Colo. (SWA) 17-6 
Platte River, Mo., Channel Improvement (MRK) 
20-17 
Platte River and Lost Creek, Schuyler, Nebr. (MRO) 
21-17 
Platte River and Tributaries, Nebr. (MRO) 21-17 
Platte River, Bank Protection, Louisville, Nebr. 
(MRO) 21-20 
Platte River Basin, Colo. (MRO) 21-21 
Platte River, M.U.D. Protection, Cedar Island, Nebr. 
(MRO) 21-20 
Platte River near Schuyler, Nebr. (MRO) 21-17, 
21-20 
Plattsburgh Harbor, N.Y. (NAN) 2-12, 2-24, 2-30 
Pleasant Bay, Mass. (NED) 1-39 
Pleasant Point, Perry, Maine (NED) 1-20, 1-24, 
1-31 
Pleasant River, Maine (NED) 1-39 
Pleasanton Floodway, Tex. (SWF) 16-22 
Plum Creek, Colo. (MRO) 21-20 
Plum Creek, Ky. (ORL) 24-30 
Plum Creek, Bank Stabilization, Aurora, Colo. 
(MRO) 21-20 
I-36

INDEX 
Plum Island, Mass. (NED) 1-42 
Plymouth, Pa. (NAB) 4-36, 4-39 
Plymouth Harbor, Mass. (NED) 1-39 
Poca, W. Va. (ORH) 25-21 
Pocomoke River, Md. (NAB) 4-34 
Pohoiki Bay, Hawaii (POD) 36-8 
Point Judith Pond and Harbor of Refuge, R.I. (NED) 
1-7, 1-26, 1-35, 1-45, 1-46, 1-53 
Point Lookout Harbor (Au Gres River), Mich. (NCE) 
31-18, 31-40, 31-53 
Point Place, Toledo, Ohio (NCB) 32-15, 32-22 
Point Pleasant, W. Va. (ORL) 25-20, 25-22 
Pokegama Reservoir, Minn. (NCS) 27-26 
Pollock Rip Shoals, Nantucket Sound, Mass. (NED) 
1-39 
Poloa Area, American Samoa (POD) 36-10 
Polson Bay, Flathead Lake, Mont. (NPS) 38-25 
Pomeroy, Ohio (ORL) 25-21 
Pomme De Terre Lake, Mo. (MRK) 20-5, 20-11, 
20-15, 20-19 
Pomona Lake, Kans. (MRK) 20-6, 20-11, 20-15, 
20-19 
Ponce, P.R. (SAJ) 9-41 
Ponce De Leon Inlet, Fla. (SAJ) 9-12, 9-28, 9-36 
Ponce Harbor, P.R. (SAJ) 9-12, 9-28, 9-36 
Pontiac Diversion, R.I. (NED) 1-45 
Pool, Joe, Lake (Lakeview Lake), Tex. (SWF) 16-7, 
16-16,.16-20 
Port Alexander, Alaska (NPA) 40-13, 40-14, 
40-15 
Port Allen Harbor, Hawaii (POD) 36-8 
Port Angeles Harbor, Wash. (NPS) 38-25, 38-30 
Port Arthur and Vicinity, Tex. Hurricane-Flood 
Protection (SWG) 15-10, 15-15, 15-25 
Port Austin Harbor, Mich. (NCE) 31-18, 31-41, 
31-53 
Port Bay, N.Y. (NCB) 32-35 
Port Chester Harbor, N.Y. (NAN) 2-34 
Port Clinton Harbor, Ohio (NCB) 32-11, 32-35 
Port Dickinson, N.Y. (NAB) 4-39 
Port Everglades Harbor, Fla. (SAJ) 9-13, 9-28, 
9-36 
Port 5 Facility, Bridgeport, Conn. (NED) 1-18, 
1-24, 1-30, 1-36 
Port Gamble Harbor, Wash. (NPS) 38-25, 38-30, 
38-31 
Port Henry Harbor, N.Y. (NAN) 2-34 
Port Hueneme, Calif. (SPL) 33-18 
Port Jefferson Harbor, N.Y. (NAN) 2-34 
Port Jervis, N.Y. (NAP) 3-13 
Port Lions Small Boat Harbor, Alaska (NPA) 40-5, 
40-9, 40-12, 40-15 
Port of Kalama, Wash. (NPP) 37-40 
Port Ontario Harbor, N.Y. (NCB) 32-9, 32-20 
Port Orchard Bay, Wash. (NPS) 38-25 
Port Orford, Oreg. (NPP) 37-7, 37-25, 37-34 
Port Royal Harbor, S.C. (SAN) 7-6, 7-10, 7-13 
Port San Luis, Calif. (SPL) 33-18 
Port Sanilac Harbor, Mich. (NCE) 31-19, 31-41, 
31-53 
Port St. Joe Harbor, Fla. (SAM) 10-42, 10-45 
Port Townsend, Wash. (NPS) 38-25, 38-31 
Port Washington Harbor, Wis. (NCE) 31-19, 31-41, 
31-53 
Port Wing Harbor, Wis. (NCE) 31-19, 31-41, 
31-53 
Portage, Pa. (ORP) 26-22 
Portage Lake Harbor, Mich. (NCE) 31-18, 31-41, 
31-53 
Portchester Harbor, N.Y. (NAN) 2-38 
Porter Bayou, Miss. (LMK) 12-6, 12-9, 12-12 
Portland, Ind. (ORL) 24-20, 24-30 
Portland, Ohio (ORH) 25-21 
Portland Harbor, Maine (NED) 1-39 
Portneuf River and Marsh Creek, Idaho (NPW) 
39-15, 39-16 
Portsmouth Harbor, Va. Channel to Nansemond 
Ordnance Depot (NAO) 5-23 
Portsmouth Harbor and Piscataqua River, Maine and 
N.H. (NED) 1-39 
Portsmouth-New Boston, Ohio (ORH) 25-20, 
25-22 
Portugues and Bucana Rivers, P.R. (SAJ) 9-23, 
9-30, 9-41 
Portville, N.Y. (ORP) 26-22, 26-26 
Posten Bayou, Ark. and La. (LMN) (LMK) 11-16, 
12-17, 12-19 
Poteau River Navigation, Ark. and Okla. (SWT) 
19-15 
Poteet Floodway, Tex. (SWF) 16-22 
Potomac and Anacostia Rivers, D.C., Collection and 
Removal of Drift (NAB) 4-7, 4-23, 4-30 
Potomac River and Tributaries at and below 
Washington, D.C., Elimination of Waterchestnut 
(NAB) 4-34 
Potomac River Aquatic Plant Control, Md., Va., D.C. 
(NAB) 4-8, 4-23, 4-30 
Potomac River at Alexandria, Va. (NAB) 4-34 
Potomac River at Lower Cedar Point, Md. (NAB) 
4-34 
Potomac River at Mount Vernon, Va. (NAB) 4-34 
Potomac River below Washington, D.C. (NAB) 4-34 
Potomac River North Side of Washington Channel, 
D.C. (NAB) 4-34 
Potowomut River, R.I. (NED) 1-39 
Pottstown, Pa. (NAP) 3-23 
Poverty Point, La. (LMN) 12-6, 12-10, 12-12 
Powell County High School, Mont. (NPS) 38-28 
Powhatan Point, Ohio (ORP) 26-22, 26-26 
Prado Dam, Calif. (SPL) 33-24 
Prairie Du Chien, Wis. (NCS) 27-11, 27-20 
Prairie Du Chien Harbor, Wis. (NCD) 29-7 
I-37

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Prairie du Pont Levee and Sanitary District, Ill. 
(LMS) 14-15 
Prairie du Rocher and Vicinity, Ill. (LMS) 14-15 
Prattville, Ala. (SAM) 10-43 
Pre-Authorization Studies for Beach Erosion 
Control Activities 
Baltimore, Md., District (NAB) 4-11 
Buffalo, N.Y., District (NCB) 32-14 
Chicago, Ill., District (NCC) 30-6 
Detroit, Mich., District (NCE) 31-26 
Galveston, Tex., District (SWG) 15-8 
Jacksonville, Fla., District (SAJ) 9-21 
Mobile, Ala., District (SAM) 10-12, 10-44 
New England Division (NED) 1-46 
New York, N.Y., District (NAN) 2-36 
Norfolk, Va., District (NAO) 5-10 
Pacific Ocean Division (POD) 36-3 
Philadelphia, Pa., District (NAP) 3-10 
Savannah, Ga., District (SAS) 8-6 
Seattle, Wash., District (NPS) 38-8 
Pre-Authorization Studies for Flood Control 
Activities 
Alaska District (NPA) 40-6 
Albuquerque, N. Mex., District (SWA) 17-7 
Baltimore, Md., District (NAB) 4-19 
Buffalo, N.Y., District (NCB) 32-38 
Charleston, S.C., District (SAN) 7-16 
Chicago, Ill., District (NCC) 30-7 
Detroit, Mich., District (NCR) 31-28 
Fort Worth, Tex., District (SWF) 16-12, 16-23 
Galveston, Tex., District (SWG) 15-12 
Huntington, W. Va., District (ORH) 25-11 
Jacksonville, Fla., District (SAJ) 9-53 
Kansas City, Mo., District (MRK) 20-7, 20-21 
Little Rock, Ark., District (SWL) 18-5, 18-25 
Los Angeles, Calif., District (SPL) 33-25 
Louisville, Ky., District (ORL) 24-13, 24-31 
Memphis, Tenn., District (LMM) 13-3 
Mobile, Ala., District (SAM) 10-44 
Nashville, Tenn., District (ORN) 23-6, 23-19 
New England Division (NED) 1-47 
New Orleans, La., District (LMN) 11-9 
New York, N.Y., District (NAN) 2-37 
Norfolk, Va., District (NAO) 5-12 
Omaha, Nebr., District (NRO) 21-6, 21-22 
Pacific Ocean Division (POD) 36-4 
Philadelphia, Pa., District (NAP) 3-12 
Pittsburgh, Pa., District (ORP) 26-29 
Portland, Oreg., District (NPP) 37-46 
Rock Island, Ill., District (NCR) 28-18 
Sacramento, Calif., District (SPK) 35-19 
San Francisco, Calif., District (SPN) 34-3 
Savannah, Ga., District (SAS) 8-7 - 
Seattle, Wash., District (NPS) 38-32 
St. Louis, Mo., District (LMS) 14-8 
St. Paul, Minn., District (NCS) 27-28 
Tulsa, Okla., District (SWT) 19-7, 19-19 
Vicksburg, Miss., District (LMK) 12-8 
Walla Walla, Wash., District (NPW) 39-2 
Wilmington, N.C., District (SAW) 6-31 
Pre-Authorization Studies for Navigation Activities 
Alaska District (NPA) 40-15 
Baltimore, Md., District (NAB) 4-11 
Buffalo, N.Y., District (NCB) 32-11, 32-36 
Charleston, S.C., District (SAN) 7-15 
Chicago, Ill., District (NCC) 30-6 
Detroit, Mich., District (NCE) 31-25 
Galveston, Tex., District (SWG) 15-9 
Jacksonville, Fla., District (SAJ) 9-17 
Little Rock, Ark., District (SWL) 18-4 
Memphis, Tenn., District (LMM) 13-1 
Mobile, Ala., District (SAM) 10-12, 10-44 
Nashville, Tenn., District (ORN) 23-4 
New England Division (NED) 1-46 
New Orleans, La., District (LMN) 11-5 
New York, N.Y., District (NAN) 2-37 
Norfolk, Va., District (NAO) 5-9 
Pacific Ocean Division (POD) 36-3 
Philadelphia, Pa., District (NAP) 3-8 
Portland, Oreg., District (NPP) 37-45 
San Francisco, Calif., District (SPN) 34-3 
Savannah, Ga., District (SAS) 8-6 
Seattle, Wash., District (NPS) 38-4 
St. Louis, Mo., District (LMS) 14-7 
Vicksburg, Miss., District (LMK) 12-3 
Walla Walla, Wash., District (NPW) 39-2 
Wilmington, N.C., District (SAW) 6-29 
Prescott Area, Oreg. (NPP) 37-44 
Presque Isle Harbor, Mich. (NCE) 31-61, 31-62 
Presque Isle Peninsula, Erie, Pa. (NCB) 32-13, 
32-21, 32-33 
Prestile Stream, Blaine, Maine (NED) 1-43 
Preston Drainage and Levee District, Ill. (LMS) 
14-15 
Prestonburg, Ky. (ORH) 25-22 
Prestonville, Ky. (ORL) 24-22, 24-25 
Priest, J. Percy, Dam and Reservoir, Tenn. (ORN) 
23-7, 23-9, 23-18 
Priest Rapids Dam, Wash. (NPS) 38-30 
Princeton, W. Va. (ORH) 25-20, 25-22 
Prineville Area, Oreg. (NPP) 37-44 
Proctor, Otter Creek Basin, Vt. (NAN) 2-38 
Proctor, W. Va. (ORP) 26-22, 26-26 
Proctor Lake, Tex. (SWF) 16-9, 16-16, 16-20 
Proctorville, Ohio (ORH) 25-20 
Prompton Lake, Pa. (NAP) 3-13, 3-17 
Prospect Beach, West Haven, Conn. (NED) 1-42, 
1-46 
Providence River and Harbor, R.I. (NED) 1-39 
Provincetown Beach (Herring Cove), Mass. (NED) 
1-45 
Provincetown Harbor, Mass. (NED) 1-39, 1-45 
I-38

INDEX 
Pudding River, Oreg. (NPP) 37-44 
Pueblo Arkansas River, Colo. (Floodway Levee 
Extension) (SWA) 17-7, 17-10 
Puget Sound and Its Tributary Waters, Wash. (NPS) 
38-5, 38-15, 38-21 
Pullman, Palouse, Wash. (NPW) 39-15 
Pultneyville Harbor, N.Y. (NCB) 32-35 
Pumpkinvine Creek, Emerson, Ga. (SAM) 10-43 
Pungo Creek, N.C. (SAW) 6-27 
Pungo River, N.C. (SAW) 6-27 
Punta Salinas, P.R. (SAJ) 9-47 
Punxsutawney, Pa. (ORP) 26-5, 26-13, 26-18, 
26-26 
Punxsutawney, Pa. (Allegheny River Basin) (ORP) 
26-26 
Put In Bay, Ohio (NCB) 32-35 
Pysht River, Wash. (NPS) 38-28 
Q 
Quail Wash Levee, Joshua Tree, Calif. (SPL) 33-20 
Queens Creek, Va. (NAO) 5-24 
Queenstown Harbor, Md. (NAB) 4-34 
Queets River, Wash. (NPS) 38-28 
Quillayute River, Wash. (NPS) 38-5, 38-15, 38-21, 
38-28 
Quinalt River, Wash. (NPS) 38-28 
Quinby Creek, Va. (NAO) 5-7, 5-16, 5-20 
Quincy, Ill., Harbor Access Channel (NCR) 28-13 
Quincy, Mass. (NED) 1-22 
Quincy Harbor, Ill. (NCD) 29-8 
Quincy Shore Beach, Quincy, Mass. (NED) 1-42 
Quinnipiac River, North Haven, Conn. (NED) 1-23 
R 
R. D. Bailey Lake, W. Va. (ORH) 25-9, 25-14, 
25-18 
Raccoon Creek, N.J. (NAP) 3-21 
Raccoon Levee, Ind. (ORL) 24-22, 24-25 
Racine, Ohio (ORH) 25-21 
Racine Harbor, Wis. (NCE) 31-19, 31-41, 31-54 
Racine Locks and Dam, Ohio (ORD) 22-3, 22-6, 
22-8 
Rahway, N.J. (NAN) 2-36 
Rahway, South Branch, N.J. (NAN) 2-36 
Rahway River, N.J. (NAN) 2-38 
Rainey, Henry T., Dam, Ill. (NCD) 29-6 
Rainier Drainage District, Oreg. (NPP) 37-40, 
37-41, 37-48 
Ramapo River, Monroe, N.Y. (NAN) 2-39 
Rancocas Creek at Mt. Holly, N.J. (NAP) 3-13 
Rancocas River, N.J. (NAP) 3-24 
Randleman Lake, N.C. (SAW) 6-10, 6-20 
Rapid City, Cedar Canyon Dam, S. Dak. (MRO) 
21-20 
Rapid Creek, Idaho (NPW) 39-15 
Rapid Creek, Rapid City, S. Dak. (MRO) 21-17, 
21-20 
Rapide Croche Lock and Dam, Wis. (NCE) 31-60 
Rappahannock River, Va. (NAO) 5-24 
Rappahannock River at Bowlers Wharf, Va. (NAO) 
5-24 
Rappahannock Shoal Channel, Va. (NAO) 5-2, 
5-18 
Raritan Bay and Sandy Hook Bay, N.J. (NAN) 2-36 
Raritan River, N.J. (NAN) 2-12, 2-24, 2-30, 2-33, 
2-38 
Raritan River to Arthur Kill Cutoff Channel, N.J. 
(NAN) 2-33, 2-34 
Rathbun Lake, Iowa (MRK) 20-6, 20-12, 20-17 
Rathbun Lake Fish Hatchery (MRK) 20-17 
Ravenswood, W. Va. (ORH) 25-20 
Ray Roberts Lake, Tex. (SWF) 16-10, 16-16, 
16-20 
Rayburn, Sam, Dam and Reservoir, Tex. (SWF) 
16-13, 16-17, 16-20 
Raystown Lake, Pa. (NAB) 4-12, 4-24, 4-32 
Red Brook Harbor, Bourne, Mass. (NED) 1-39 
Red Creek, N.Y. (NCB) 32-37 
Red Lake and Red Lake River, Minn. (NCS) 27-23 
Red Lake Falls, Minn. (NCS) 27-27 
Red Lake River, Minn., including Clearwater River, 
Minn. (NCS) 27-11, 27-20 
Red Lake River at Huot, Minn. (NCS) 27-24 
Red Lake River at Red Lake Falls, Minn. (NCS) 
27-24 
Red River, Tenn. (ORN) 23-13 
Red River at East Grand Forks, Minn. (NCS) 27-27 
Red River at Fargo, N. Dak. (NCS) 27-27 
Red River at Grand Forks, N. Dak. (NCS) 27-27 
Red River Backwater Levees (MR+T) 42-46, 
42-49, 42-52 
Red River below Denison Dam including Little River 
Basin, Okla. and Ark. (SWL) 18-15 
Red River below Denison Dam, Levees and Bank 
Stabilization (LMK) (SWT) 12-7, 12-10, 12-12, 
12-17, 19-15 
Red River below Denison Dam (Vicksburg District) 
(LMK) 12-7 
Red River below Fulton, Ark. (LMK) 12-14 
Red River Emergency Bank Protection (LMK) 12-2, 
12-9, 12-11 
Red River from Fulton, Ark., to Mouth of Washita 
River (SWT) 19-15 
Red River in Vicinity of Shreveport, La. (LMN) 
(LMK) 11-16, 12-18, 12-19 
Red River Lake, Ky. (ORL) 24-21 
Red River of the North, Minn. and N. Dak. (NCS) 
27-23 
I-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Red River of the North, Argusville, N. Dak. (NCS) 
27-12, 27-20 
Red River of the North at Breckenridge, Minn. 
(NCS) 27-24 
Red River of the North at Oslo, Minn. (NCS) 27-24 
Red River of the North at Pembina, N. Dak. (NCS) 
27-24 
Red River of the North Drainage Basin, Minn., S. 
Dak. and N. Dak. (NCS) 27-12, 27-21, 27-27 
Red River of the North, Halstad, Minn. (NCS) 
27-13, 27-21 
Red River Parish, La. (LMN) (LMK) 11-16, 12-18, 
12-19 
Red River Standard Revetments (MR+T) 42-37 
Red River Waterway, La., Ark., Okla., and Tex. 
(LMK) 12-14 
Red River Waterway-Mississippi River to 
Shreveport, La. (LMK) 12-2, 12-9, 12-11 
Red River Waterway, Shreveport, La., to 
Daingerfield, Tex. (LMK) 12-14 
Red River Waterway-Shreveport, La., to Index, Ark. 
(LMK) 12-7, 12-10, 12-12 
Red Rock Dam and Lake Red Rock, Iowa (NCR) 
28-5, 28-9, 28-12 
Red Run Drain-Lower Clinton River, Mich. (NCE) 
31-63 
Red Wing Harbor, Minn. (NCD) 29-7 
Redbank and Fancher Creeks, Calif. (SPK) 35-21 
Redbank Creek Lake, Pa. (ORP) 26-23 
Reddies River Lake, N.C. (SAN) (SAW) 6-27, 
7-16 
Redmond, John, Dam and Reservoir, Kans. (SWT) 
19-5, 19-10, 19-14, 19-17 
Redondo Beach Harbor (King Harbor), Calif. (SPL) 
33-18 
Redwater River and Hay Creek, S.D. (MRO) 21-18 
Redwood City Harbor, Calif. (SPN) 34-6 
Redwood Creek, Humboldt County, Calif. (SPK) 
35-31 
Redwood River at Marshall, Minn. (NCS) 27-13, 
27-21 
Redwood River below Marshall, Minn. (NCS) 27-24 
Reeds Bay Small Boat Harbor, Hawaii (POD) 36-8 
Reedsport Levees, Oreg. (NPP) 37-42 
Reedy River, S.C. (SAN) 7-16 
Reelfoot Lake-Lake No. 9, Tenn. and Ky. (MR+T) 
42-10, 42-18, 42-28 
Reese River, Battle Mountain, Nev. (SPK) 35-31 
Reevesville, Ill. (ORL) 24-20, 24-24, 24-29 
Regulation of Hydraulic Mining and Preparation of 
Plans (CDC) 44-1, 44-5, 44-6 
Regulatory, Sunken Vessel Removal and National 
Emergency Preparedness Activities 48-1 
Rehoboth Beach to Indian River Inlet, Del. (NAP) 
3-23 
Removal of Aquatic Growth, La. (LMN) 11-15 
Removal of Aquatic Growth from Navigable Waters 
in the State of Florida (SAJ) 9-13, 9-28, 9-37, 
9-45 
Removal of Sunken Vessels 48-1 
Removing Snags and Wrecks from Mississippi River 
below Mouth of Missouri River and from Old and 
Atchafalaya Rivers (LMK) (LMM) 12-14, 13-5 
Removing Water Hyacinths, Mobile District (SAM) 
10-42 
Rend Lake, Ill. (LMS) 14-7, 14-10, 14-12 
Reno Beach-Howard Farms Area, Ohio (NCB) 
32-15, 32-37 
Republican River, Neb. and Kan. (MRK) 20-19 
Reservoirs at Headwaters of Mississippi River, Minn. 
(NCS) 27-2, 27-19, 27-22, 27-26 
Restoration of Indian Fishing Grounds, B44neville, 
Oreg. (NPP) 37-44 
Revere Beach, Mass. (NED) 1-10, 1-27, 1-35 
Reynoldsville, Pa. (ORP) 26-22 
Rheem Creek, Calif. (SPK) 35-31 
Rhodes Point to Tylerton, Md. (NAB) 4-8, 4-23, 
4-30 
Rice Creek, Fla. (SAJ) 9-46 
Richard B. Russell Dam and Lake, Ga. and S.C. 
(Formerly Trotters Shoals Lake) (SAS) 8-9, 
8-12, 8-15 
Richland Creek, Ill. (LMS) 14-15 
Richland Lake, Mo. (MRK) 20-18 
Richmond, Va. (NAO) 5-10, 5-16, 5-21 
Richmond Filtration Plant, Va. (NAO) 5-24 
Richmond Harbor, Calif. (SPN) 34-2, 34-6 
Richmond Harbor, Maine (NED) 1-39 
Richmond's Island Harbor, Maine (NED) 1-39 
Richwood and Fenwick, W. Va. (ORH) 25-22 
Ridgecrest, Calif. (SPL) 33-20 
Ridgeley, W.Va. (NAB) 4-39 
Ridgway, Pa. (Allegheny River Basin) (ORP) 26-26 
Ridgway, Pa. (Elk Creek) (ORP) 26-22 
Ridgway and Vicinity, Pa. (On Clarion River) (ORP) 
26-22 
Right and Left Forks of Beaver Creek, Ky. (ORH) 
25-22 
Rio Grande Basin, N. Mex. (SWA) 17-3, 17-9, 
17-10 
Rio Grande Floodway, N. Mex. (SWA) 17-4, 17-9, 
17-10 
Ripley, Ohio (ORH) 25-21 
Ripley, W. Va. (ORH) 25-22 
Ririe Lake, Idaho (NPW) 39-15 
Rising Sun, Ind. (ORL) 24-22, 24-25 
River Rouge, Mich. (NCE) 31-63 
Riverdale, Mass. (NED) 1-43, 1-47, 1-49 
Riverland Levee District, Mo. (LMS) 14-15 
Riverside Area, Pasco, Wash. (NPW) 39-15 
Riverside levees, Santa Ana River Basin, Calif. (SPL) 
33-24 
I-40

INDEX 
Riverview, W. Va. (ORH) 25-21 
Roanoak Lake, Tex. (SWF) 16-22 
Roanoke River, N.C. (SAW) 6-25 
Roanoke River Basin, Va. and N.C. (SAW) 6-14, 
6-30 
Roaring River, N.C. (SAN) 7-16 
Roaring River Lake, N.C. (SAW) 6-27 
Robert F. Henry Lock and Dam, Ala. (SAM) 10-20, 
10-30 
Robert S. Kerr Lock and Dam, Okla. (SWL) (SWT) 
18-20, 19-8, 19-13, 19-15, 19-16 
Robert S. Kerr Marine Terminal, Sallisaw, Okla. 
(SWT) 19-16 
Roberts, Ray, Lake, Tex. (SWF) 16-10, 16-16, 
16-20 
Rochester and McCleary's Bluff Levee, Ill. (ORL) 
24-20, 24-24, 24-29 
Rochester, Minn. (NCS) 27-13, 27-21 
Rochester, Pa. (ORP) 26-22, 26-26 
Rochester Harbor, N.Y. (NCB) 32-10, 32-20, 
32-31 
Rochester Lake, Iowa (NCR) 28-16 
Rock Creek, Mont. (NPS) 38-28 
Rock Hall Harbor, Md. (NAB) 4-34 
Rock Island, Ill. (NCR) 28-15, 28-17 
Rock Island District (NCD) 29-2, 29-3, 29-4, 
29-7 
Rock Island Harbor, Ill. (NCD) 29-7 
Rock River Agricultural Levees, Ill. (NCR) 28-15 
Rockfish Creek, N.C. (SAW) 6-28 
Rockford, Ill. (NCR) 28-5, 28-9, 28-12 
Rockingham, Vt. (NED) 1-22 
Rockland Harbor, Maine (NED) 1-39 
Rockland Lake, Tex. (SWF) 16-13, 16-16, 16-20 
Rockport, Ind. (ORL) 24-22, 24-25 
Rockport and Old Harbors, Mass. 1-8, 1-26, 1-46 
Rockport Harbor, Maine (NED) 1-39, 1-53 
Rockport Harbor, Mass. (NED) 1-35, 1-39 
Rocky Ford Drainage and Levee District, Ill. (NCR) 
28-15 
Rocky Fork, Ohio (ORH) 25-21 
Rocky Pass, Alaska (NPA) 40-13 
Rocky River Harbor, Ohio (NCB) 32-10, 32-21, 
32-32 
Rodeo Creek, Calif. (SPK) 35-31 
Rogers City Harbor, Mich. (NCE) 31-63 
Rogue River, Oreg. (NPP) 37-42 
Rogue River Harbor at Gold Beach, Oreg. (NPP) 
37-8, 37-25, 37-34 
Roland Drainage District, Arkansas River, Ark. 
(SWL) 18-17 
Rolling Fork Road, Sevier County, Ark. (SWL) 
18-17 
Rollinson Channel, N.C. (SAW) 6-8, 6-19, 6-29 
Rome, Ga. (SAM) 10-43 
Rome, Ind. (ORL) 24-22, 24-25 
Rome Mohawk River, N.Y. (NAN) 2-38 
Rondout Harbor, N.Y. (NAN) 2-13, 2-25, 2-30 
Root Creek, Bolivar, N.Y. (ORP) 26-5, 26-13 
Rose Creek Channel Improvements, San Diego, 
Calif. (SPL) 33-20, 33-24 
Roseau River, Minn. (NCS) 27-14, 27-21 
Rosedale Harbor, Miss. (LMK) 12-14 
Rosendale, N.Y. (NAN) 2-36 
Roseville, Ohio (ORH) 25-9, 25-15, 25-18, 25-22 
Rosiclare, Ill. (ORL) 24-20, 24-29 
Rossview Reservoir, Ohio River Basin, Tenn. and Ky. 
(ORN) 23-13, 23-18 
Rota Harbor, Northern Marianas (POD) 36-8 
Rouge River, Mich. (NCE) 31-20, 31-42, 31-54, 
31-63 
Rough River, Ky. (ORL) 24-19, 24-24, 24-27, 
24-30 
Rough River Lake and Channel Improvements, Ky. 
(ORL) 24-10, 24-16 
Rouses Point, Lake Champlain, N.Y. (NAN) 2-34 
Rouseville, Pa. (ORP) 26-22 
Rowlesburg Lake, W. Va. (ORP) 26-22 
Royal River, Maine (NED) 1-8, 1-27, 1-35 
Ruby River, Wheatly Bridge, near Twin Bridges, 
Mont. (MRO) 21-19 
Rudee Inlet, Norfolk, Va., District (NAO) 5-25 
Ruffy Brook, Minn. (NCS) 27-25 
Rufus Woods Lake, Wash. (NPS) 38-10, 38-16, 
38-22 
Rush River, N. Dak. (NCS) 27-27 
Rushford, Minn. (NCS) 27-24 
Russell, Ky. (ORH) 25-20, 25-22 
Russell and Allison Levee, Ill. (ORL) 24-20, 24-24 
Russell, Richard B., Dam and Lake, Ga. and S.C. 
(SAS) 8-9, 8-12, 8-15 
Russian River Basin, Calif. (SPK) 35-14, 35-24, 
35-28, 35-34, 35-35 
Rutland, Otter Creek, Vt. (NAN) 2-36 
Rutledge Hollow Creek Channel Improvement, 
Poteet, Tex. (SWF) 16-22 
Rye Creek, Mont. (NPS) 38-28 
Rye Harbor, N.H. (NED) 1-39 
S 
Sabine-Neches Waterway, Tex. (SWG) 15-7, 
15-14, 15-22, 15-28, 15-30, 15-35 
Sabine River and Tributaries, Tex. (Echo to Morgan 
Bluff) (SWG) 15-27 
Sabula, Iowa (NCR) 28-15, 28-17 
Sackets Harbor, N.Y. (NCB) 32-35, 32-39 
Saco, Mont. (MRO) 21-17, 21-19 
Saco River, Maine (NED) 1-9, 1-27, 1-35, 1-45, 
1-53 
Sacramento River, Calif. (CDC) 44-3, 44-5, 44-6, 
44-7 
I-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Sacramento River, Calif. (SPK) 35-2, 35-23, 
35-28, 35-33 
Sacramento River and Tributaries, Calif. (CDC) 
44-2, 44-5 
Sacramento River and Tributaries, Calif., from 
Collinsville to Shasta Dam (SPK) 35-15, 35-25, 
35-28, 35-35, 35-36 
Sacramento River Deep Water Ship Channel, Calif. 
(SPK) 35-2, 35-23 
Sacred Heart Hospital, Yankton, S. Dak. (MRO) 
21-17, 21-20 
Sag Harbor, N.Y. (NAN) 2-34 
Saginaw River, Mich. (NCE) 31-20, 31-26, 31-42, 
31-49, 31-54, 31-56 
Saint John River Basin, Maine (NED) 1-20 
Saipan Small Boat Harbor, Northern Marianas 
(POD) 36-8 
Sakonnet Harbor, R.I. (NED) 1-39, 1-45 
Sakonnet River, R.I. (NED) 1-39 
Salamanca, N.Y. (ORP) 26-22 
Salamonie Lake, Ind. (ORL) 24-11, 24-16 
Salem Church Lake, Va. (NAO) 5-24 
Salem Harbor, Mass. (NED) 1-39 
Salem River, N.J. (NAP) 3-14, 3-21 
Salina, Kans. (MRK) 20-17, 20-19 
Salinas River, Calif. (SPK) 35-31 
Saline Point, La. (LMN) (LMK) 11-16, 12-18, 
12-19 
Saline River, Ark. (LMK) 12-14 
Saline River and Tributaries, Ill. (ORL) 24-20, 
24-30 
Salisbury, Conn. (NED) 1-22, 1-50 
Salkahatchie River, S.C. (SAN) 7-15 
Salmon Creek at Oakridge, Oreg. (NPP) 37-42 
Salmon Creek near Vancouver, Wash. (NPP) 37-42 
Salmon River, Alaska (NPA) 40-14 
Salmon River, Idaho (NPW) 39-17 
Salmon River, Oreg. (NPP) 37-39 
Salmon River, Colchester, Conn. (NED) 1-43, 1-49 
Salt Creek, Ohio (ORH) 25-20 
Salt Creek and Tributaries, Nebr. (MRO) 21-6, 
21-11, 21-15 
Salt Lake City, Jordan River, Utah (SPK) 35-31 
Saluda River, S.C. (SAN) 7-16 
Salyersville, Ky. (ORL) 24-21 
Sam Rayburn Dam and Reservoir, Tex. (SWF) 
16-13, 16-17, 16-20 
Sammamish River, Wash. (NAS) 38-28 
San Antonio Channel Improvement, Tex. (SWF) 
16-10, 16-17, 16-20 
San Antonio and Chino Creeks Channel, Calif. (SPL) 
33-24 
San Antonio Dam, Calif. (SPL) 33-24 
San Antonio Floodway, Tex. (SWF) 16-22 
San Diego Creek, Alice, Tex. (SWG) 15-27 
San Diego Harbor, Calif. (SPL) 33-18 
San Diego River and Mission Bay, Calif. (SPL) 
33-18, 33-22 
San Diego River (Mission Valley), Calif. (SPL) 
33-20, 33-24 
San Diego (Sunset Cliffs), Calif. (SPL) 33-19 
San Francisco Bay and Delta Model, Calif. (SPN) 
34-2, 34-6 
San Francisco Bay to Stockton, Calif. (John F. 
Baldwin and Stockton Ship Channels) (SPK) 
(SPN) 34-2, 34-6, 35-3, 35-23 
San Francisco Harbor, Calif. (SPN) 34-6, 34-8 
San Francisco Harbor and Bay (Removal of Drift), 
Calif. (SPN) 34-6 
San Francisco Marina (Gas House Cove), Calif. 
(SPN) 34-8 
San Gabriel River, Tex. (SWF) 16-10, 16-17, 
16-20 
San Gabriel River to Newport Bay (Surfside-Sunset 
and Newport Beach), Calif. (SPL) 33-19 
San Jacinto River Levee and Bautista Creek 
Channel, Calif. (SPL) 33-24 
San Joaquin River, Calif. (SPK) 35-4, 35-23, 
35-33, 35-34 
San Juan, P.R. (SAJ) 9-47 
San Juan Dam, Calif. (SPL) 33-24 
San Juan Harbor, P.R. (SAJ) 9-15, 9-28, 9-37 
San Leandro Creek, Calif. (SPK) 35-31 
San Leandro Marina, Calif. (SPN) 34-6 
San Leandro Marina (Breakwater), Calif. (SPN) 
34-8 
San Lorenzo Creek, Calif. (SPK) (SPN) 34-9, 35-31 
San Lorenzo River, Calif. (SPK) 35-31 
San Luis Rey River, Calif. (SPL) 33-20 
San Pablo Bay and Mare Island Strait, Calif. (SPN) 
34-6, 34-9 
San Rafael Creek, Calif. (SPN) 34-6 
Sand Creek Channel Improvement, Kans. (SWT) 
19-15, 19-17, 19-18 
Sand Hill Cove Beach, R.I. (NED) 1-42 
Sand Hill River, Minn. (NCS) 27-27 
Sand Island, Hawaii (POD) 36-10 
Sand Lake, Okla. (SWT) 19-15 
Sand Point, Alaska (NPA) 40-16 
Sandburg Creek, Ellenville, N.Y. (NAN) 2-40 
Sandburg Creek, Spring Glen, N.Y. (NAN) 2-36 
Sandusky Harbor, Ohio (NCB) 32-10, 32-21, 
32-32 
Sandusky River, Ohio (NCB) 32-35 
Sandy Bay, Cape Ann, Mass. (NED) 1-39, 1-45 
Sandy Bay (Harbor of Refuge), Cape Ann, Mass. 
(NED) 1-39 
Sandy Creek, Jackson, Tenn. (LMM) 13-6 
Sandy Drainage District, Oreg. (NPP) 37-41, 37-48 
Sandy Hook Bay, N.J. (NAN) 2-34 
Sandy Hook Bay at Leonardo, N.J. (NAN) 2-33, 
2-34 
I-42

INDEX 
Sandy Lake Reservoir, Minn. (NCS) 27-26 
Sandy River and Sleepy Lake, Oreg. (NPP) 37-42 
Sangamon River (Mouth), Ill. (NCR) 28-15 
Sanitary District of Beardstown, Ill. (NCR) 28-17 
Sans Bois Navigation Channel, Okla. (SWT) 19-16 
Santa Ana River Basin (and Orange County), Calif. 
(SPL) 33-7, 33-12, 33-17, 33-20, 33-24 
Santa Ana River Basin, Calif.: Devil, East Twin, and 
Warm Creeks Channel Improvements (SPL) 
33-20 
Santa Ana River Main Stem, Calif. (SPL) 33-8 
Santa Barbara Harbor, Calif. (SPL) 33-2, 33-10, 
33-15 
Santa Clara River Levee Improvement, Calif. (SPL) 
33-20 
Santa Cruz County, Calif. (SPN) 34-8 
Santa Cruz Harbor, Calif. (SPN) 34-3, 34-7 
Santa Fe River and Arroyo Mascaras, N. Mex. 
(SWA) 17-7, 17-10 
Santa Maria Valley Levees, Calif. (SPL) 33-20 
Santa Paula Creek Channel and Debris Basins 
(including Mud Creek), Calif. (SPL) 33-20 
Santa Rosa Dam and Lake, N. Mex. (SWA) 17-5, 
17-8 
Santa Rosa Wash (at Momolikot Dam and Lake St. 
Clair), Ariz. (SPL) 33-19 
Santee River, N.C. and S.C. (SAN) 7-15 
Sapelo Harbor, Ga. (SAS) 8-16 
Sardis, Ohio (ORH) 25-21 
Sardis Lake, Miss. (MR+T) 42-20, 42-59 
Sardis Lake, Okla. (SWT) 19-6, 19-11, 19-14, 
19-18 
Sasanoa River, Maine (NED) 1-40 
Sasco Hill Beach, Fairfield, Conn. (NED) 1-42 
Satilla River, Ga. (SAS) 8-16 
Saugatuck Harbor and Kalamazoo River, Mich. 
(NCE) 31-23, 31-43, 31-55 
Saugerties Harbor, N.Y. (NAN) 2-34 
Sauk River, Wash. (NPS) 38-28 
Sauquoit Creek, Whitesboro, N.Y. (NAN) 2-39 
Sauvie Island Drainage District, Oreg. (NPP) 37-40, 
37-41, 37-48 
Savage, Md. (NAB) 4-39 
Savage River Dam, Md. (NAB) 4-36 
Savanna Harbor, Ill. (NCD) 29-7 
Savannah Harbor, Ga. (SAS) 8-4, 8-6, 8-10, 8-11, 
8-14 
Savannah River above Augusta, Ga. (SAS) 8-16 
Savannah River. at Augusta, Ga. (SAS) 8-16 
Savannah River Basin, Ga. and S.C. (SAS) 8-8, 
8-17 
Savannah River below Augusta, Ga. (SAS) 8-5, 
8-6, 8-11, 8-15 
Saw Mill River at Elmsford and Greenburgh, N.Y. 
(NAN) 2-19, 2-31 
Sawkill Creek, Kingston, N.Y. (NAN) 2-39 
Sawmill Branch, S.C. (SAN) 7-8, 7-16 
Saxis Island, Va. (NAO) 5-11, 5-17, 5-21 
Saxman, Alaska (NPA) 40-15 
Saxon Harbor, Wis. (NCE) 31-23, 31-43, 31-56 
Saxonville, Mass. (NED) 1-22, 1-43, 1-51 
Saxtons River, Rockingham, Vt. (NED) 1-24 
Sayers, Foster Joseph, Dam, Pa. (NAB) 4-18, 4-26 
Saylorville Lake, Iowa (NCR) 28-5, 28-9, 28-12 
Scajaquada Creek, N.Y. (NCB) 32-37 
Scappoose Drainage District, Oreg. (NPP) 37-40, 
37-48 
Scarboro River, Maine (NED) 1-40 
Schuyler, Nebr. (MRO) 21-20 
Schuylkill River, Pa. (NAP) 3-9, 3-16, 3-20 
Schuylkill River above Fairmount Dam, Pa. (NAP) 
3-21 
Schuylldll River-Fairmount Park, Pa. 3-8 
Scioto River at Portsmouth, Ohio (ORH) 25-19 
Sciotoville, Ohio (ORH) 25-21 
Scituate Harbor, Mass. (NED) 1-22, 1-40, 1-46, 
1-53 
Scott, W. Kerr, Dam and Reservoir, N.C. (SAW) 
6-13, 6-16, 6-20 
Scott County Drainage and Levee District, Ill. (LMS) 
14-15 
Scotts Creek, S.C. (SAW) 7-7, 7-10, 7-14 
Scotts Creek, Va. (NAO) 5-20, 5-25 
Scottsville, Va. (NAO) 5-12, 5-17, 5-21 
Scranton, Pa. (NAB) 4-36, 4-39 
Scranton, Buffalo, N. Dak. (MRO) 21-19 
Scuppernong River, N.C. (SAW) 6-13, 6-20, 6-25 
Sea Bright to Ocean Township, N.J. (NAN) 2-17, 
2-25, 2-31 
Seahorn Drainage and Levee District, Ill. (NCR) 
28-15, 28-17 
Searsport Harbor, Maine (NED) 1-40 
Seaside Park, Conn. (NED) 1-42 
Seattle Harbor, Wash. (NPS) 38-6, 38-15, 38-21 
Sebasticook River, Hartland, Maine (NED) 1-20, 
1-30, 1-36, 1-43 
Sebewaing, Sebewaing River, Mich. (NCE) 31-27, 
31-45, 31-56, 31-61 
Seekonk River, R.I. (NED) 1-40 
Seldovia Harbor, Alaska (NPA) 40-13 
Selkirk Shore State Park, N.Y. (NCB) 32-36 
Sergius Whitestone, Alaska (NPA) 40-13 
Sespe Creek at Fillmore, Calif. (SPL) 33-20 
Sesuit Harbor, Mass. (NED) 1-40, 1-53 
Sevier River near Redmond, Utah (SPK) 35-31 
Sewage Lagoons, Vale, Oreg. (NPW) 39-15 
Sewage Treatment Plant, Missoula, Mont. (NPS) 
38-28 
Seward, Nebr. (MRK) 20-17 
Seward Harbor, Alaska (NPA) 40-13, 40-15 
Sewerline Protection, Valley, Ala. (SAM) 10-16, 
10-29, 10-39 
I-43

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Shad Landing State Park, Md. (NAB) 4-34 
Shallotte River, N.C. (SAW) 6-25, 6-29 
Shark River, N.J. (NAN) 2-33, 2-34 
Shawneetown, Ill. (ORL) 24-20, 24-21, 24-24, 
24-29 
Sheboygan Harbor, Wis. (NCE) 31-23, 31-43, 
31-56 
Sheepshead Bay, N.Y. (NAN) 2-34, 2-38 
Sheffield, Mass. (NED) 1-22, 1-50 
Sheffield Lake Community Park, Ohio (NCB) 32-39 
Shelburne, N.H. (NED) 1-22, 1-43 
Shell Creek, Nebr. (MRO) 21-18, 21-21 
Shelley Area, Idaho (NPW) 39-15, 39-16 
Shelton Creek, Wash. (NAS) 38-28 
Shelton Ditch, Oreg. (NPP) 37-42 
Shenango River Lake, Pa. and Ohio (ORP) 26-9, 
26-14, 26-20, 26-27 
Shepard Road, St. Paul, Minn. (NCS) 27-24 
Sherburne, N.Y. (NAB) 4-39 
Sheridanf, Wyo. (MRO) 21-17, 21-19 
Sherwood Island State Park, Conn. (NED) 1-42 
Sheyenne River, N. Dak. (NCS) 27-14, 27-21, 
27-25 
Shidler Lake, Okla. (SWT) 19-15 
Shields River, near Clyde Park, Mont. (MRO) 21-17, 
21-19 
Shilshole Bay, Seattle, Wash. (NPS) 38-25 
Shinnecock Inlet, N.Y. (NAN) 2-14, 2-25, 2-30 
Shipyard River, S.C. (SAN) 7-6, 7-10, 7-13 
Shoal Harbor and Compton Creek, N.J. (NAN) 
2-33, 2-34 
Shoals, Ind. (ORL) 24-22 
Shobe Canyon, Oreg. (NPW) 39-15 
Shooters Island, N.Y. and N.J. (NAN) 2-34 
Shoreline Erosion Control Demonstration, 
Philadelphia, Pa. District (NAP) 3-10 
Shoreline Erosion Control Work Under Special 
Authorization 
Philadelphia, Pa., District (NAP) 3-10 
Pittsburgh, Pa., District (ORP) 26-29 
Short Beach, Conn. (NED) 1-42 
Shoshone River, Bank Protection, Lovell, Wyo. 
(MRO) 21-19 
Shoshone River, Lovell, Wyo. (MRO) 21-19 
Shot Pouch Creek, S.C. (SAN) 7-8, 7-16 
Shrewsbury River, N.J. (NAN) 2-14, 2-25, 2-30, 
2-33 
Shufflebarger Levee, Ind. (ORL) 24-22, 24-25 
Sid Simpson Project, Ill. (NCR) 28-15 
Siler City Streams, N.C. (SAW) 6-31 
Silver Beach to Cedar Beach, Conn. (NED) 1-42 
Silver Lake Harbor, N.C. (SAW) 6-8, 6-19, 6-23 
Simmons Bay, N.C. (SAW) 6-27 
Simpson Creek, S.C. (SAN) 7-8, 7-16 
Sioux City, Iowa (MRO) 21-21 
Sioux City Marina, Iowa (MRO) 21-2, 21-10 
Sioux Falls, S. Dak. (MRO) 21-17, 21-20 
Sistersville, Ohio (ORH) 25-21 
Sitka Harbor, Alaska (NPA) 40-13, 40-15 
Siuslaw River, Oreg. (NPP) 37-8, 37-25, 37-34, 
37-42 
Six Runs Creek, N.C. (SAW) 6-28 
Sixes Bridge Lake, Md. and Pa. (N) 4-37 
Skaggs Ferry, Black River, Ark. (SWL) 18-17 
Skagit Creek, Wash. (Avon By-Pass) (NPS) 38-28 
Skagit River, Wash. (NPS) 38-25, 38-28, 38-30 
Skagit River, Wash. (Levee and Channel 
Improvements) (NPS) 38-27 
Skagway Harbor, Alaska (NPA) 40-13, 40-15 
Skagway River, Alaska (NPA) 40-14 
Skamokawa Creek, Wash. (NPP) 37-9, 37-26, 
37-34, 37-45 
Skamokawa Creek Area, Wash. (NPP) 37-40 
Skamokawa (Steamboat Slough), Wash. (NPP) 
37-44 
Skiatook Lake, Okla. (SWT) 19-6, 19-12, 19-14, 
19-18 
Skipanon Channel, Oreg. (NPP) 37-9, 37-26, 
37-34 
Slaughter Creek, Md. (NAB) 4-9, 4-23, 4-30 
Slovan, Pa. (ORP) 26-22 
Small Boat Harbor Opposite Chester, Ill. (LMS) 
14-13 
Small Boat Harbor Opposite Hamburg, Ill. (LMS) 
14-13 
Small Navigation Project at Sioux City, Iowa (MRO) 
21-16 
Smelt Brook, Mass. (NED) 1-43 
Smith Creek, Colo. (SWA) 17-7, 17-10 
Smith Creek, Md. (NAB) 4-34, 4-38 
Smith Creek, Pamlico County, N.C. (SAW) 6-25 
Smith Ferry, Pa. (ORP) 26-23 
Smith River, Oreg. (NPP) 37-39 
Smithfield, W. Va. (ORH) 25-22 
Smithland, Ky. (ORL) 24-21, 24-24 
Smithland Locks and Dam, Ky. (ORD) 22-3, 22-9 
Smiths Creek (Wilmington), N.C. (SAW) 6-25 
Smithville Channel, Little Platte River, Mo. (MRK) 
20-17 
Smithville Lake, Little Platte River, Mo. (MRK) 
20-6, 20-12, 20-15 
Smoky Hill, Saline, and Solomon Rivers (MRK) 
20-19 
Smyrna River, Del. (NAP) 3-21, 3-24 
Snagging and Clearing Activities 
Buffalo, N.Y., District (NCB) 32-38 
Charleston, S.C., District (SAN) 7-7 
Huntington, W.Va., District (ORH) 25-11 
Louisville, Ky., District (ORL) 24-13, 24-31 
New England Division (NED) 1-23 
Rock Island, Ill., District (NCR) 28-18 
Sacramento, Calif., District (SPK) 35-19 
I-44

INDEX 
St. Paul, Minn., District (NCS) 27-28 
Tulsa, Okla., District (SWT) 19-19 
Vicksburg, Miss., District (LMK) 12-8 
Walla Walla, Wash., District (NPW) 39-2 
Snake River, Idaho (NPW) 39-15, 39-17 
Snake River, Minn. (NCS) 27-28 
Snake River Downstream from Johnson Bar 
Landing, Oreg., Wash., and Idaho (NPW) 39-7, 
39-10, 39-12, 39-22 
Snettisham, Alaska (NPA) 40-6, 40-10, 40-12 
Snohomish River, Wash. (NPS) 38-28 
Snoqualmie River, Wash. (NPS) 38-28 
Sny Basin, Ill. (NCR) 28-15, 28-17 
Sny Island Levee Drainage District, Ill. (NCR) 
28-15, 28-17 
Soap Creek, Wash. (NPP) 37-44 
Socorro Diversion Channel, Tributaries of Rio 
Grande, N. Mex. (SWA) 17-7, 17-10 
Soleduck River Bridge, Wash. (NPS) 38-28 
Somerville Lake, Tex. (SWF) 16-11, 16-17, 16-20 
Sonoma Creek, Calif. (SPK) 35-31 
Sope Creek, Marietta, Ga. (SAM) 10-16, 10-29, 
10-39 
Soules Swamp, Whiteville, N.C. (SAW) 6-31 
Souris River, Velva, N. Dak. (NCS) 27-15, 27-21 
South Amsterdam, Mohawk River, N.Y. (NAN) 2-36 
South Bank Arkansas River, (Head Fourche Island 
to Pennington Bayou), Ark. (SWL) 18-17 
South Bank Arkansas River, Little Rock to Pine 
Bluff, Ark. Tucker Lakes (SWL) 18-17 
South Beardstown and Valley Drainage and Levee 
District, Ill. (NCR) 28-15 
South Beardstown Drainage and Levee District, Ill. 
(NCR) 28-15, 28-17 
South Beloit, Ill. (NCR) 28-15 
South Bristol Harbor, Maine (NED) 1-40 
South Channel, Government Island, Oreg. (NPP) 
37-39 
South Coventry Lake, Conn. (NED) 1-45 
South Creek, N.C. (SAW) 6-27 
South Deer Creek Levee, Okla. (SWT) 19-17 
South Ellenville, N.Y. (NAN) 2-36 
South Fork, Boise River, Idaho (NPW) 39-15 
South Fork, Clearwater River, Idaho (NPW) 39-15, 
39-16 
South Fork of Cumberland River, Ky. (ORN) 23-13 
South Fork of the Santa Clara River, Calif. (SPL) 
33-20 
South Haven Harbor, Mich. (NCE) 31-24, 31-43, 
31-56 
South Milwaukee Harbor, Wis. (NCE) 31-63 
South Orange, N.J. (NAN) 2-36 
South Platte River, Adams County, Colo. (MRO) 
21-20 
South Platte River, Bank Protection, Denver, Colo. 
(MRO) 21-20 
South Platte River Basin, Colo. (MRO) 21-6, 21-15 
South Platte River, Iliff, Colo. (MRO) 21-20 
South Platte River, Kersey, Colo. (MRO) 21-20 
South Platte River Levees and Channel 
Improvements, Chatfield Lake to Ft. Morgan, 
Colo. (MRO) 21-17 
South Platte River, Merino, Colo. (MRO) 21-20 
South Platte River, Platteville, Colo. (MRO) 21-20 
South Plymouth Lake, N.Y. (NAB) 4-38 
South Point, Ohio (ORH) 25-20 
South Portsmouth, Ky. (ORH) 25-20 
South Quincy Drainage and Levee District, Ill. 
(NCR) 28-9, 28-15, 28-17 
South River, N.C. (SAW) 6-25 
South River, Conway, Mass. (NED) 1-15, 1-24, 
1-29 
South River Drainage District, Mo. (NCR) 28-15, 
28-17 
South Slough (Charleston), Oreg. (NPP) 37-39 
South Tunbridge Lake, Vt. (NED) 1-45 
South Williamson, Ky. (ORH) 25-22 
South Williamsport, Pa. (NAB) 4-39 
Southern Branch, Va. (NAO) 5-19 
Southern New York Flood Control Projects (NAB) 
4-13, 4-32 
Southport Beach, Conn. (NED) 1-42 
Southport Harbor, Conn. (NED) 1-40 
Southwest Harbor, Maine (NED) 1-40 
Southwestern Jefferson County, Ky. (ORL) 24-5, 
24-14 
Sowashee Creek, Meridian, Miss. (SAM) 10-43 
Space Programs Laboratory 51-1 
Spanish Fork River, Utah (SPK) 35-33 
Spewrell Bluff Lake, Ga. (SAM) 10-23, 10-30, 
10-41 
Spirit Lake, Wash. (NPP) 37-14 
Spokane, Wash. (NAS) 38-28 
Spring City, Tenn. (ORN) 23-19 
Spring Lake Drainage and Levee District, Ill. (NCR) 
28-15, 28-17 
Springdale, Mass. (NED) 1-43, 1-49 
Springer, William L., Lake, Ill. (NCR) 28-16 
Springfield, Mass. (NED) 1-22, 1-44, 1-49 
Springfield, S.D., Water Intake (MRO) 21-18 
Springfield Canal, Ga. (SAS) 8-7 
Squantz Pond, New Fairfield, Conn. (NED) 1-22, 
1-44, 1-50 
Squaw Chute at Quincy, Ill. (NCR) 28-13 
St. Albans Harbor, Lake Champlain, Vt. (NAN) 2-34 
St. Anthony Falls, Lower Lock and Dam, Minn. 
(NCD) 29-5, 29-9 
St. Anthony Falls, Upper Lock, Minn. (NCD) 29-5 
St. Augustine Harbor, Fla. (SAJ) 9-14, 9-28, 9-37 
St. Catherines Sound, Md. (NAB) 4-34, 4-38 
St. Clair River, Mich. (NCE) 31-21, 31-42, 31-54, 
31-58, 31-63 
I-45

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
St. Croix River, Maine (NED) 1-39 
St. Croix River, Minn. and Wis. (NCS) 27-2, 27-19, 
27-22 
St. Francis and L'Anguille Rivers and Blackfish 
Bayou, Ark. (LMM) 13-5 
St. Francis Basin, Ark. and Mo. (MR+T) 42-9, 
42-28, 42-53 
St. Francis River and Basin, Ark. and Mo. (MR+T) 
42-9, 42-18 
St. Francis River, Highway 90, Ark. (LMM) 13-6 
St. Francis River Levees (MR+T) 42-48, 42-49 
St. Georges Creek, Md. (NAB) 4-34, 4-37 
St. James, Beaver Island, Mich. (NCE) 31-62 
St. James Harbor, Mich. (NCE) 31-61 
St. Jeromes Creek, Md. (NAB) 4-34, 4-38 
St. Johns River, Fla., Jacksonville to Lake Harney 
(SAJ) 9-14, 9-28, 9-37 
St. Johns River and Tributaries and Withlacoochee, 
Kissimmee and Crystal Rivers, Fla. (SAJ) 9-45 
St. Jones River, Del. (NAP) 3-21, 3-22 
St. Joseph Harbor, Mich. (NCE) 31-21, 31-42, 
31-54 
St. Joseph River, Mich. (NCE) 31-62 
St. Louis County Drainage and Levee District No. 1, 
Mo. (LMS) 14-15 
St. Louis District (NCD) 29-3, 29-4 
St. Lucie Inlet, Fla. (SAJ) 9-15, 9-28, 9-37 
St. Maries, Idaho (NAS) 38-28 
St. Marks River, Fla. (SAM) 10-42, 10-45 
St. Marys, Pa. (ORP) 26-23 
St. Marys, W. Va. (ORH) 25-21 
St. Marys River, Ga. and Fla., and North River, Ga. 
(SAS) 8-16 
St. Marys River, Mich. (NCE) 31-22, 31-43, 31-55, 
31-59, 31-63 
St. Michael Canal, Alaska (NPA) 40-13 
St. Michaels Harbor, Md. (NAB) 4-34 
St. Patricks Creek, Md. (NAB) 4-8, 4-23, 4-30 
St. Paul, Minn. (NCS) 27-27 
St. Paul and South St. Paul, Minn. (NCS) 27-24 
St. Paul District (NCD) 29-3, 29-4 
St. Paul Harbor, Minn. (NCD) 29-7 
St. Peters Creek, Md. (NAB) 4-34 
St. Petersburg Harbor, Fla. (SAJ) 9-45, 9-46 
St. Thomas Harbor, V.I. (SAJ) 9-46 
Ste. Genevieve County Drainage and Levee District 
No. 1, Mo. (LMS) 14-15 
Stamford, Conn. (NED) 1-20, 1-22, 1-31, 1-37 
Stamford Barrier, Conn. (NED) 1-23 
Stamford Harbor, Conn. (NED) 1-40, 1-45 
Starlings Creek, Va. (NAO) 5-24 
Startup, Wash. (NAS) 38-28 
Starved Rock Lock and Dam, Ill. (NCC) 28-20 
State Highway 101 and 401, Wash. (NPP) 37-40 
State Road and Ebner Coulees, Wis. (NCS) 27-15, 
27-21 
Staten Island, N.Y. (NAN) 2-36 
Staten Island Rapid Transit Railway Co. Bridge 
Across Arthur Kill, N.Y. (NAN) 2-34 
Steinhatchee River, Fla. (SAJ) 9-46 
Stewart Canyon Debris Basin and Channel, Calif. 
(SPL) 33-20 
Stikine River, Alaska (NPA) 40-13 
Stillaguamish River, Wash. (NPS) 38-9, 38-17, 
38-22, 38-25, 38-29 
Stillhouse Hollow Dam, Tex. (SWF) 16-11, 16-17, 
16-21 
Stillwater and Whitefish Rivers, Mont. (NPS) 38-29 
Stillwater Lake, Pa. (NAB) 4-16, 4-26, 4-32 
Stillwater River, Mont. (NPS) 38-29 
Stillwell Drainage District, Oreg. (NPP) 37-42 
Stockton and Mormon Channels, Calif. (SPK) 35-30 
Stockton Harbor, Maine (NE) 1-40 
Stockton Lake, Mo. (MRK) 20-9, 20-12, 20-16, 
20-19 
Stone Harbor, N.J. (NAP) 3-23 
Stonehouse Creek, Kans. (MRK) 20-17 
Stoner Creek, Ky. (ORL) 24-30 
Stonewall Jackson Lake, W. Va. (ORP) 26-9, 
26-15, 26-20, 26-27 
Stonington Harbor, Conn. (NED) 1-40, 1-46 
Stonington Harbor, Maine (NED) 1-40, 1-45; 1-53 
Stony Brook, Wilton, N.H. (NED) 1-44 
Stony Creek, Branford, Conn. (NED) 1-40 
Stratford, Conn. (NED) 1-45 
Streambank Erosion Control Evaluation and 
Demonstration Project 
New England Division (NED) 1-23 
Omaha, Nebr., District (MRO) 21-9, 21-12, 
21-16 
Pittsburgh, Pa., District (ORP) 26-29 
Strington, Ft. Chartres and Ivy Landing, Ill. (LMS) 
14-15 
Strong Creek, Idaho (NPS) 38-29 
Strube Lake - Cougar Additional Unit, (South Fork 
McKenzie) (Modification to Cougar Lake) Oreg. 
37-49 
Stuart, Va. (SAW) 6-13, 6-20 
Stuart Gulch Dam, Boise, Idaho (NPW) 39-16 
Stumpy Point Bay, N.C. (SAW) 6-25 
Sturgeon Bay and Lake Michigan Ship Canal, Wis. 
(NCE) 31-24, 31-43, 31-56 
Sturgis, Ky. (ORL) 24-20, 24-24, 24-29 
Subdistrict No. 1 of Drainage Union No. 1 and Bay 
Island Drainage and Levee District No. 1, Ill. 
(NCR) 28-15, 28-17 
Sucker Brook Dam, Conn. (NED) 1-22, 1-44, 1-48 
Sugar Creek Basin, N.C. and S.C. (SAN) 7-17 
Sugar Creek Levee, Ind. (ORL) 24-22, 24-25 
Sugar Hill Reservoir, N.H. (NED) 1-45 
Suisun Bay Channel, Calif. (SPK) (SPN) 34-7, 
35-30 
I-46

INDEX 
Suisun Channel, Calif. (SPK) (SPN) 34-7, 35-30 
Suisun Point Channel, Calif. (SPK) 35-30 
Sullivan Falls Harbor, Maine (NED) 1-40 
Sulphur River, Ark. and Tex. (LMN) 11-15 
Sulphur River Levees, Tex. (SWF) 16-22 
Summersville Lake, W. Va. (ORH) 25-9, 25-15, 
25-18 
Sumner Parker Airport, Oreg. (NPP) 37-42 
Sumpawanus (Babylon Creek) Inlet, N.Y. (NAN) 
2-34 
Sun Creek, Miss. (SAM) 10-43 
Sunbury, Pa. (NAB) 4-36, 4-39 
Sunken Vessel Removal 48-1 
Supervision of the Harbor of Hampton Roads 
(Prevention of Obstructive and Injurious 
Deposits) (NAO) 5-8, 5-16 
Supervisor of New York Harbor (NAN) 2-16, 2-25, 
2-32 
Surry Mountain Lake, N.H. (NED) 1-15, 1-29, 
1-48 
Surveillance of Northern Boundary Waters (NCE) 
31-29, 31-45 
Susquehanna Basin at Harrisburg, Pa. (NAB) 4-20 
Susquehanna River above and below Havre De 
Grace, Md. (NAB) 4-34 
Susquehanna River at Williamsport, Pa. (NAB) 4-34 
Susquehanna River Flood Control Projects, N.Y. and 
Pa. (NAB) 4-17, 4-32 
Sutton Lake, W. Va. (ORH) 25-9, 25-15, 25-18 
Suwannee River, Fla. (SAJ) 9-45, 9-46 
Swan Creek Bank Stabilization, Taney County, Mo. 
(SWL) 18-7, 18-12 
Swanton Harbor, Vt. (NAN) 2-38 
Sweetwater Creek, N.C. (SAW) 6-28 
Sweetwater River, Calif. (SPL) 33-7, 33-12, 33-17 
Swift Creek, N.C. (SAW) 6-25 
Swift Creek, Pitt and Craven Counties, N.C. (SAW) 
6-27 
Swinomish Channel, Wash. (NPS) 38-6, 38-16, 
38-21 
Swoyersville, and Forty Fort, Pa. (NAB) 4-36, 4-39 
Sykesville, Pa. (ORP) 26-22 
Syracuse, N.Y. (NCB) 32-37 
Syracuse, Ohio (ORH) 25-21 
T 
Table Rock Lake, Mo. (SWL) 18-9, 18-13, 18-24 
Tacoma, Puyallup River, Wash. (NPS) 38-10, 
38-17, 38-23 
Tacoma Harbor, Wash. (NPS) 38-7, 38-16, 38-21, 
38-31 
Tahchevah Creek Detention Basin and Channel 
Improvements, Calif. (SPL) 33-21 
Tahola, Wash. (NPS) 38-29 
Tahquitz Creek, Calif. (SPL) 33-21 
Talkeetna River, Alaska (NPA) 40-14 
Tallabinella Creek, Miss. (SAM) 10-16, 10-29, 10-39 
Tallahala Creek Lake, Miss. (SAM) 10-13, 10-28, 
10-38 
Tallahatchie and Coldwater Rivers, Miss. (LMK) 
12-14 
Tallapoosa River, Ala. (SAM) 10-42 
Tallow Hill, Ga. (SAS) 8-17 
Talofofo Bay Shore Protection, Guam (POD) 36-12 
Tamaqua, Pa. (NAP) (NAB) 3-23, 4-21 
Tampa and Hillsborough Bays, Fla. (SAJ) 9-38 
Tampa Bay, Fla. (SAJ) 9-38 
Tampa Harbor, Fla. (SAJ) 9-16, 9-28, 9-38 
Tangeman, Nebr. (MRO) 21-20 
Tangier Channel, Va. (NAO) 5-8, 5-16, 5-20 
Tangipahoa River, La. (LMN) 11-15 
Tar River, N.C. (SAW) 6-27 
Tar River and Tributaries, N.C. (SAW) 6-27 
Tar River, Princeville, N.C. (SAW) 6-27 
Tarentum, Pa. (ORP) 26-22 
Tarrytown Harbor, N.Y. (NAN) 2-35 
Taskinas Creek, Va. (NAO) 5-24 
Tau Small Boat Harbor, American Samoa (POD) 
36-8 
Taunton River, Mass. (NED) 1-40 
Tawas Bay Harbor, Mich. (NCE) 31-24, 31-44, 
31-56 
Taylors Bayou, Tex. (SWG) 15-10, 15-15, 15-25 
Taylorsville, Ky. (ORL) 24-20, 24-24, 24-29 
Taylorsville Lake, Ky. (ORL) 24-11, 24-17 
Teche-Vermilion Basins, La. (Water Supply) 
(MR+T) 42-50, 42-59 
Telegraph Canyon Creek, Calif. (SPL) 33-20 
Tell City, Ind. (ORL) 24-20, 24-24, 24-29 
Tenants Harbor, Maine (NED) 1-40 
Tenasillahe Island, Oreg. (NPP) 37-40 
Tenkiller Ferry Lake, Okla. (SWL) (SWT) 18-22, 
19-8, 19-13, 19-15, 19-16, 19-18 
Tenmile Creek at Marianna, Pa. (ORP) 26-22 
Tennessee River, Tenn., Ala., and Ky. (ORN) 23-3, 
23-9, 23-11, 23-17, 23-18 
Tennessee-Tombigbee Waterway, Ala. and Miss. 
(ORN) (SAM) 10-48, 23-4, 23-9, 23-12 
Tensas Basin, Ark. and La. (MR+T) 42-6, 42-15, 
42-28 
Tensas River and Bayou Macon, La. (LMK) 12-15 
Tensas River National Wildlife Refuge (MR+T) 
42-28 
Terrain Analysis Center 51-1 
Terre Haute, Ind. (ORL) 24-22 
Terre Haute (Conover Levee), Ind. (ORL) 24-20, 
24-29 
Terre Noire Creek, Ark. (LMK) 12-16 
Terry, David D., Lock and Dam, Ark. (SWL) 18-2, 
18-19 
I-47

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Teton River, Idaho (NPW) 39-15, 39-16 
Texas City and Vicinity, Tex., Hurricane-Flood 
Protection (SWG) 15-11, 15-15, 15-25 
Texas City Channel, Tex. (SWG) 15-7, 15-14, 
15-24, 15-28 
Thames River, Conn. (NED) 1-40 
Thames River Basin, Conn., R.I., and Mass. (NED) 
1-21, 1-23, 1-52 
The Cascades Canal, Oreg. (NPP) 37-39 
The Dalles-Celilo Canal, Oreg. and Wash. (NPP) 
37-39 
The Dalles Lock and Dam-Lake Celilo, Wash. and 
Oreg. (NPP) 37-22, 37-29, 37-38, 37-52 
The Island Lake, Vt. (NED) 1-45 
Thimble Shoal Channel, Va. (NAO) 5-24 
Thomaston Dam, Conn. (NED) 1-17, 1-30, 1-49 
Thoroughfare Swamp, N.C. (SAW) 6-28 
Three Forks, Mont. (MRO) 21-19 
Three Islands Reservoir, Tenn. (ORN) 23-14 
Three Rivers, Mass. (NED) 1-22, 1-44, 1-49 
Three Rivers, Tex. (SWG) (SWF) 15-27, 16-21 
Thumpertown Beach, Eastham, Mass. (NED) 1-45 
Tickfaw, Natalbany, Ponchatoula, and Blood Rivers, 
La. (LMN) 11-15 
Ticonderoga River, N.Y. (NAN) 2-38 
Tijuana River Basin, Calif. (SPL) 33-20 
Tilghman Island Harbor, Md. (NAB) 4-34 
Tillamook Bay and Bar, Oreg. (NPP) 37-9, 37-26, 
37-34, 37-45 
Tioga-Hammond Lakes, Pa. (NAB) 4-17, 4-26 
Tionesta Lake, Pa. (ORP) 26-10, 26-15, 26-20, 
26-27 
Toad Suck Ferry Lock - Dam, Ark. (SWL) 18-4, 
18-19 
Tocks Island Lake, Pa., N.J., and N.Y. (NAP) 3-24 
Tocks Island (Relocation of U.S. Route 209 Only) 
Pa. (NAP) 3-24 
Todd Swamp, S.C. (SAN) 7-8, 7-16 
Togiak Harbor, Alaska (NPA) 40-15 
Toledo Harbor, Ohio (NCB) 32-10, 32-21, 32-32 
Tolovana River, Alaska (NPA) 40-14 
Tolu, Ky. (ORL) 24-21, 24-24 
Tom Jenkins Dam, Ohio (ORH) 25-15, 25-18 
Tom Jenkins Reservoir, Ohio (ORH) 25-10 
Tomahawk Lake, Kans. (MRK) 20-17 
Tomanovich-Salmon City, Idaho (NPW) 39-15, 
39-19 
Tombigbee River, Miss. and Ala. (SAM) 10-17, 
10-29, 10-39 
Tombigbee River Tributaries, Miss. and Ala. (SAM) 
10-17, 10-29, 10-40 
Toms River, N.J. (NAP) 3-21, 3-24 
Tongue River Lake, N. Dak. (NCS) 27-24 
Topeka, Kans. (MRK) 20-17, 20-19 
Topographic Laboratory 51-1 
Topsail Beach and Surf City, N.C. (SAW) 6-28 
Toronto Lake, Kans. (SWL) (SWT) 18-22, 19-6, 
19-12, 19-14, 19-16, 19-18 
Torrington, East Branch, Conn. (NED) 1-22, 1-44, 
1-50 
Torrington, West Branch, Conn. (NED) 1-22, 1-44, 
1-50 
Totuskey Creek, Va. (NAO) 5-24 
Touchet River, Wash. (NPW) 39-15, 39-16 
Towanda Lake, Kans. (SWT) 19-15 
Town Beach, Plymouth, Mass. (NED) 1-42 
Town Bluff Dam-B. A. Steinhagen Lake, Tex. 
(SWF) 16-13, 16-17, 16-21 
Town Bluff Hydropower, Tex. (SWF) 16-13, 16-21 
Town Creek, Md. (NAB) 4-34, 4-38 
Town Creek, S.C. (SAN) 7-7, 7-10, 7-14 
Town Creek, Americus, Ga. (SAM) 10-43 
Town Creek, Harrodsburg, Ky. (ORL) 24-20 
Town Neck Beach, Sandwich, Mass. (NED) 1-42 
Townsend Inlet and Seven Mile Beach, N.J. (NAP) 
3-23 
Townshend Lake, Vt. (NED) 1-15, 1-29, 1-48 
Trabuco Dam, Calif. (SPL) 33-24 
Tradewater River, Ky. (ORL) 24-19 
Tranquitas Creek, Kingsville, Tex. (SWG) 15-27 
Tranters Creek, N.C. (SAW) 6-28 
Trask River, Oreg. (NPP) 37-43 
Traverse City Harbor, Mich. (NCE) 31-61, 31-62 
Treasure Island, Mo. (LMM) 13-6 
Treatment of Yuba River Debris Situation- 
Restraining Barriers, Calif. (CDC) 44-2, 44-5 
Tred Avon River, Md. (NAB) 4-9, 4-24, 4-31 
Trent River, N.C. (SAW) 6-25, 6-27, 6-28 
Trenton Lake, Mo. (MRK) 20-17 
Trexler Lake, Pa. (NAP) 3-23 
Trim Cane Creek, Miss. (SAM) 10-43 
Trinidad Lake, Colo. (SWA) 17-5, 17-8 
Trinity River and Tributaries, Tex. (SWG) 15-7, 
15-14, 15-24, 15-28, 15-35 
Trinity River Project, Tex. (SWF) 16-2, 16-15, 
16-21 
Triplett Creek, Morehead, Ky. (ORL) 24-20, 24-30 
Tri-Pond Levee, Ill. (ORL) 24-22, 24-25 
Trotters Shoals Lake (SAS) 8-9, 8-12, 8-15 
Troublesome Creek, Hindman, Ky. (ORL) 24-30 
Troy, Ind. (ORL) 24-22, 24-25 
Truckee River and Tributaries, Calif. and Nev. (SPK) 
35-31 
Truman, Harry S., Dam and Reservoir, Mo. (MRK) 
20-8, 20-12, 20-16, 20-19 
Trumbull Lake, Conn. (NED) 1-44 
Trussville, Ala. (SAM) 10-43 
Truth or Consequences (Hot Springs) Unit, N. Mex. 
(SWA) 17-5, 17-9 
Tualatin, Oreg. (NPP) 37-43 
Tucannon River, Camp Wooten, Wash. (NPW) 
39-15 
1-48

INDEX 
Tuckahoe River, Md. (NAB) 4-34 
Tuckerton Creek, N.J. (NAP) 3-9, 3-16, 3-20 
Tucson Diversion Channel, Ariz. (SPL) 33-5, 
33-11, 33-16 
Tug and Levisa Forks of the Big Sandy River and 
Cumberland River, W. Va., Va., and Ky. (ORN) 
23-5, 23-9 
Tully Lake, Mass. (NED) 1-16, 1-29, 1-48 
Tulsa and West Tulsa Levee, Okla. (SWT) 19-15, 
19-17, 19-18 
Turkey Creek, S.C. (SAN) 7-8, 7-16 
Turtle Creek, Pa. (ORP) 26-22 
Turtle Creek Channel Improvement, Yukon, Okla. 
(SWT) 19-16 
Tuskahoma Lake, Okla. (SWT) 19-16 
Tuttle Creek Lake, Kans. (MRK) 20-6, 20-12, 
20-15, 20-19 
Tuttle Creek Lake (Road Improvement), Kans. 
(MRK) 20-19 
Twelvemile Bayou, La. (LMN) (LMK) 11-17, 12-20 
Twin Valley Lake, Wild Rice River, Minn. (NCS) 
27-16, 27-21 
Twitch Cove and Big Thorofare, Md. (NAB) 4-9, 
4-24, 4-31 
Two Harbors, Minn. (NCE) 31-61, 31-62 
Two Rivers Dam, N. Mex. (SWA) 17-6, 17-8 
Two Rivers Harbor, Wis. (NCE) 31-24, 31-44, 
31-56 
Tyaskih Creek, Md. (NAB) 4-34 
Tybee Island, Ga. (SAS) 8-6, 8-11, 8-15 
Tygart Lake, W. Va. (ORP) 26-3, 26-13, 26-17 
Tylers Beach, Va. (NAO) 5-24 
Tyrone, Pa. (NAB) 4-36, 4-39 
U 
Umatilla Harbor, Oreg. (NPP) 37-39 
Umatilla River (Echo), Oreg. (NPP) (NPW) 37-43, 
37-44, 39-15 
Umpqua River, Oreg. (NPP) 37-9, 37-26, 37-35 
Umpqua River and Tributaries, Oreg. (NPP) 37-43 
Unadilla, N.Y. (NAB) 4-36, 4-39 
Union City Dam, Pa. (ORP) 26-10, 26-15, 26-20, 
26-27 
Union Lake, Mo. (LMS) 14-15 
Union River, Maine (NED) 1-40, 1-53 
Union Township Drainage District, Mo. (NCR) 
28-15 
Union Village Dam, Vt. (NED) 1-16, 1-29, 1-48 
Uniontown, Ky. (ORL) 24-20, 24-24, 24-29 
Uniontown, Pa. (ORP) 26-22, 26-26 
Uniontown Locks and Dam, Ky. (ORL) 22-3, 22-9 
University Wash and Spring Brook, Riverside, Calif. 
(SPL) 33-20 
Upper and Lower Woonsocket, R.I. (NED) 1-22 
Upper Chipola River, Fla., from Mariana to its 
mouth (SAM) 10-42 
Upper Grand River, Mo. (MRK) 20-17 
Upper Grays River Area, Wash. (NPP) 37-40 
Upper Iowa River, Iowa (NCS) 27-24 
Upper Machodoc Creek, Va. (NAB) 4-34 
Upper Marlboro, Md. (NAB) 4-36, 4-39 
Upper Mississippi River Environmental Management 
Program, Ill., Ia., Minn., Mo., Wis. (NCR) 28-3, 
28-8, 28-11 
Upper Puyallup River, Wash. (NAS) 38-29 
Upper River Road, Jefferson Co., Ky. (ORL) 24-30 
Upper River Rouge, Mich. (NCE) 31-63 
Upper Thorofare, Deal Island, Md. (NAB) 4-10, 
4-24, 4-31 
Upper White River, Ark. (SWL) 18-16 
Urban Areas at Alton, Ill. (LMS) 14-15 
Urbanna Creek, Va. (NAO) 5-24 
U.S. Highway 11 Bridge, Fosters, Ala. (SAM) 10-17, 
10-29, 10-40 
U.S. Highway 43 Bridge, Linden, Ala. (SAM) 10-43 
U.S. Highway 45 Bridge, Prentiss County, Miss. 
(SAM) 10-17, 10-29, 10-40 
U.S. Highway 51, Tenn. (LMM) 13-6 
Utica, Ind. (ORL) 24-22, 24-26 
Utica, Ohio (ORH) 25-20, 25-22 
V 
Valdez Harbor, Alaska (NPA) 40-13 
Valley City Drainage and Levee District, Ill. (LMS) 
14-15 
Valley Drainage and Levee District, Ill. (NCR) 
28-17 
Van Buren, Arkansas River, Ark. (SWL) 18-17 
Van Meter, Iowa (NCR) 28-15, 28-17 
Vanceburg, Ky. (ORH) 25-20 
Vancouver Lake Area, Wash. (NPP) 37-41 
Vatia Area, American Samoa (POD) 36-10 
Vaughn, Mont. (MRO) 21-17, 21-19 
Velva, N. Dak. (NCS) 27-24, 27-27 
Ventnor, Margate and Longport, N.J. (NAP) 3-23 
Ventura Marina (Ventura Harbor), Calif. (SPL) 
33-3, 33-10, 33-15 
Ventura-Pierpont Area, Calif. (SPL) 33-19 
Ventura River Basin, Calif. (SPL) 33-20 
Vermilion Harbor, Ohio (NCB) 32-11, 32-21, 
32-33 
Vermilion Lock, La. (Replacement of Lock) (LMN) 
11-2, 11-10, 11-12 
Vermillion River, S.D. (MRO) 21-18 
Vermillion River, Hastings, Minn. (NCS) 27-24 
Verona Lake, Va. (NAB) 4-36 
Veteran's Memorial Levee, Hastings, Minn. (NCS) 
27-24 
I-49

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Vevay, Ind. (ORL) 24-22, 24-25 
Vicinity of Nehalem, Oreg. (NPP) 37-43 
Vicksburg Harbor, Miss. (MR+T) 42-29 
Victory Lake, Vt. (NED) 1-45 
Villa Park Dam, Calif. (SPL) 33-21, 33-24 
Village Creek, S.C. (SAN) 7-15 
Village Creek, Jackson - Lawrence Counties, Ark. 
(SWL) 18-17 
Village Creek, White River, and Mayberry Levee 
District, Ark. (SWL) 18-17 
Village of New Athens, Ill. (LMS) 14-15 
Village of Saxtons, Vt. (NED) 1-44 
Vince and Little Vince Bayous, Tex. (SWG) 15-11, 
15-15, 15-25 
Vincennes, Ind. (ORL) 24-20, 24-21, 24-24, 
24-29 
Vineyard Haven, Mass. (NED) 1-40 
Vinton Waterway, La. (LMN) 11-15 
Virginia Beach, Va. (NAO) 5-9, 5-16, 5-21 
Virginia Beach Streams Canal Number 2, Va. (NAO) 
5-12, 5-17, 5-21 
Virginia Key and Key Biscayne, Fla. (SAJ) 9-47 
Volga, Iowa (NCR) 28-17
W 
Wabash Railroad Bridges, Illinois River, Meredosia, 
and Valley City, Ill. (LMS) 14-13 
Wabash River Basin, Ind., Ill., and Ohio (ORL) 
24-11, 24-19, 24-27, 24-28, 24-30 
Wabasha Harbor, Minn. (NCD) 29-7 
Waccamaw River, N.C. and S.C. (SAN) 7-7, 7-15 
Waccamaw River and Seven Creeks, N.C. and S.C. 
(SAN) 6-27 
Waco Lake, Tex. (SWF) 16-11, 16-17, 16-21 
Wahkiakum County Consolidated Diking District No. 
1, Wash. (NPP) 37-48 
Wahkiakum County Diking District 4, Wash. (NPP) 
37-41, 37-48 
Waianae Small Boat Harbor, Hawaii (POD) 36-8 
Waikiki Beach, Hawaii (POD) 36-10 
Wailoa Stream and Tributaries, Hawaii (POD) 
36-11 
Waimea Beach, Hawaii (POD) 36-10 
Waimea River, Hawaii (POD) 36-4, 36-6 
Wake Island Harbor, Wake Island (POD) 36-8 
Waldo Lake Tunnel and Reregulating Works, Oreg. 
(NPP) 37-44, 37-49 
Wallabout Channel, N.Y. (NAN) 2-35 
Wallace, W. Va. (ORP) 26-22 
Wallace Channel, Pamlico Sound, N.C. (SAW) 6-25 
Wallace Lake, La. (LMK) 12-16, 12-18, 12-20 
Wallis Sands State Beach, N.H. (NED) 1-42 
Wallisville Lake, Tex. (SWG) 15-8 
Wallkill River, N.Y. (NAN) 2-39 
Wallowa River, Oreg. (NPW) 39-15 
Walluski River, Oreg. (NPP) 37-41 
Walnut Creek, Calif. (SPK) 35-17, 35-25 
Walter, Francis E., Dam, Pa. (NAP) (NAB) 3-12, 
3-17, 4-21 
Walter F. George Lock and Dam, Ala. and Ga. 
(SAM) 10-24, 10-31, 10-41 
Walters Slough, N.C. (SAW) 6-29 
Wappapello Lake, Mo. (MR+T) 42-20, 42-59 
Wappinger Creek, N.Y. (NAN) 2-35, 2-36 
Wappinger Creek at Pleasant Valley, N.Y. (NAN) 
2-36 
Ware, Mass. (NED) 1-22, 1-23, 1-44, 1-49 
Wareham Harbor, Mass. (NED) 1-40, 1-53 
Wareham-Marion, Mass. (NED) 1-45 
Warner Road, Mississippi River, St. Paul, Minn. 
(NCS) 27-16, 27-21 
Warren River, R.I. (NED) 1-40 
Warrenton Diking Districts 1, 2, and 3, Oreg. (NPP) 
37-41 
Warroad Harbor and River, Minn. (NCS) 27-3, 
27-19, 27-22, 27-25 
Warroad River and Bull Dog Creek, Minn. (NCS) 
27-24 
Warsaw, N.Y. (NCB) 32-37 
Warsaw Harbor, Ill. (NCD) 29-8 
Warwick Cove, R.I. (NED) 1-40 
Warwick River, Md. (NAB) 4-34 
Warwood, W. Va. (OPR) 26-22, 26-26 
Washington, D.C. and Vicinity (NAB) 4-21, 4-36, 
4-39 
Washington, Pa. (ORP) 26-22 
Washington Aqueduct (NAB) 4-20 
Washington Canal and South River, N.J. (NAN) 
2-35 
Washington Harbor, D.C. (NAB) 4-10, 4-24, 4-31 
Washington Island, Wis. (NCE) 31-61, 31-62 
Washougal Area Levees, Wash. (NPP) 37-42 
Water Resources Support Center (WRSC) 53-1 
Water Valley, Ark. and Mo. (SWL) 18-18 
Waterborne Commerce Statistics Center 53-1 
Waterbury, Vt. (NAN) 2-38 
Waterbury Dam, N.Y. (NAN) 2-20 
Waterbury Reservoir, Vt. (NAN) 2-36 
Waterbury-Watertown, Conn. (NED) 1-22, 1-44, 
1-50 
Wateree River, S.C. (SAN) 7-15 
Waterford, N.Y. (NAN) 2-38 
Waterloo, Iowa (NCR) 28-6, 28-12, 28-17 
Waterloo, Nebr. (MRO) 21-17, 21-20 
Waterway Connecting Pamlico Sound and Beaufort 
Harbor, S.C. (SAW) 6-8, 6-19, 6-23, 6-29 
Waterway Connecting Port Townsend and Oak Bay, 
Wash. (NPS) 38-7, 38-16, 38-22, 38-31 
Waterway Connecting Swanquarter Bay with Deep 
Bay, N.C. (SAW) 6-25 
I-50

INDEX 
Waterway Connecting Tombigbee and Tennessee 
Rivers, Ala. and Miss. (SAM) 10-11, 10-28, 
10-38 
Waterway from Empire, La., to Gulf of Mexico 
(LMN) 11-15 
Waterway from Indian River Inlet to Rehoboth Bay, 
Del. (NAP) 3-21 
Waterway from Intracoastal Waterway to Bayou 
Dulac, La. (Bayous Grand Caillou and LeCarpe, 
La.) (LMN) 11-5, 11-10, 11-12 
Waterway from Little Choptank River to Choptank 
River, Md. (NAB) 4-38 
Waterway from White Lake to Pecan Island, La. 
(LMN) 11-15 
Waterway-Norfolk, Va. to Sounds of N.C. (SAW) 
6-25 
Waterway on the Coast of Virginia (NAO) 5-8, 
5-16, 5-21 
Waterways Experiment Station (WES) 45-1 
Watkins Glen, N.Y. (NCB) 32-39 
Watts Bar Lock and Dam, Tenn. (ORN) 23-17 
Waukegan Harbor, Ill. (NCC) 30-5, 30-9, 30-13, 
30-14 
Waurika Lake, Okla. (SWT) 19-6, 19-12, 19-14, 
19-18 
Waverly, W. Va. (ORH) 25-21 
Wax Lake Outlet, La. (MR+T) 42-50 
Waycake Creek, N.J. (NAN) 2-35 
Webb District Improvement Co., Oreg. (NPP) 37-41 
Webbers Falls Lock and Dam, Okla. (SWL) (SWT) 
18-20, 19-8, 19-13, 19-15, 19-16 
Weber River and Tributaries, Utah (SPK) 35-33 
Weiser River, Weiser Area, Idaho (NPW) 39-15, 
39-16, 39-17 
Welles Harbor, Midway Island (POD) 36-8 
Wellfleet Harbor, Mass. (NED) 1-40 
Wells Harbor, Maine (NED) 1-40 
Wellsburg, W. Va. (ORP) 26-23 
Wellsville, N.Y. (NCB) 32-37 
Wellsville, Ohio, Sec. I (ORP) 26-22, 26-26 
Wellsville, Ohio, Sec. II (ORP) 26-22, 26-26 
Wenatchee Canyons 1 and 2, Wash. (NPS) 38-29 
Wessagusset Beach, Weymouth, Mass. (NED) 1-42 
West Atchalafaya Floodway, La. (MR+T) 42-13 
West Branch Chisholm Creek Channel Improvement, 
Kans. (SWT) 19-16, 19-18 
West Branch of Susquehanna River, Pa. (NAB) 
4-18, 4-33 
West Branch, Westfield River, Mass. (NED) 1-44 
West Bridgewater, Pa. (ORP) 26-23 
West Brookfield Reservoir, Mass. (NED) 1-45 
West Canaan Lake, N.H. (NED) 1-45 
West Fork, W. Va. (ORH) 25-20 
West Fork, Foster Creek, Wash. (NPS) 38-29 
West Fork of Mill Creek Lake, Ohio (ORL) 24-12, 
24-17, 24-27 
West Glendive, Mont. (MRO) 21-19 
West Harbor, Ohio (NCB) 32-11, 32-35 
West Hickman Area, Hickman, Ky. (LMM) 13-6 
West Hill Dam, Mass. (NED) 1-11, 1-27, 1-47 
West Kentucky Tributaries, Ky. (MR+T) 42-10, 
42-19, 42-28, 42-53 
West Magnesia Canyon Channel, Calif. (SPL) 33-7, 
33-12, 33-17 
West Makinster Road, Wilson River, Oreg. (NPP) 
37-16, 37-27, 37-37 
West Matanzas Drainage and Levee District, Ill. 
(NCR) 28-17 
West Muddy Creek and Marys River, Oreg. (NPP) 
37-44 
West Nishnabotna River, Mills Co. Bridge, near 
Hastings, Iowa (MRO) 21-21 
West Nishnabotna River, Mills Co. Bridge, near 
Malvern, Iowa (MRO) 21-21 
West Nishnabotna River, near Hancock, Iowa (MRO) 
21-21 
West of Morrilton, Arkansas River, Ark. (SWL) 
18-17 
West Oneonta Lake, N.Y. (NAB) 4-38 
West Point, Ga. (SAM) 10-43 
West Point, Ky. (ORL) 24-21, 24-24 
West Point, Nebr. (MRO) 21-17, 21-20 
West Point Lake, Ga. and Ala. (SAM) (SAS) 8-9, 
10-24, 10-31, 10-41 
West Springfield, Mass. (NED) 1-16, 1-22, 1-29, 
1-36, 1-44, 1-49 
West Stewartstown, N.H. (NED) 1-22 
West Tennessee Tributaries, Tenn. (MR+T) 42-10, 
42-18, 42-28, 42-53 
West Terre Haute, Ind. (ORL) 24-20, 24-24, 24-29 
West Thompson Lake, Conn. (NED) 1-22, 1-31, 
1-52 
West Union, W. Va. (ORH) 25-22 
West Warren, Mass. (NED) 1-22, 1-44, 1-49 
Westchester Creek, N.Y. (NAN) 2-15, 2-25, 2-31, 
2-38 
Westcott Cove, Conn. (NED) 1-40 
Westerly, R.I. (NED) 1-44 
Western Branch, Va. (NAO) 5-20 
Westfield, Mass. (NED) 1-45 
Westhaven Cove Small Boat Basin (Westport 
Marina), Wash. (NPS) 38-25 
Westland District Improvement Co., Oreg. (NPP) 
37-41 
Weston, Vt. (NED) 1-22, 1-44, 1-49 
Weston Mills, Olean, N.Y. (ORP) 26-22 
Weston Mills, Portville, N.Y. (ORP) 26-22 
Westport, Conn. (NED) 1-45 
Westport, Ky. (ORL) 24-22, 24-25 
Westport District, Oreg. (NPP) 37-41 
Westport Harbor and Saugatuck River, Conn. (NED) 
1-40, 1-45 
1-51

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Westport River, Mass. (NED) 1-40 
Westport Slough, Oreg. (NPP) 37-39, 37-44 
Westville Lake, Mass. (NED) 1-22, 1-32, 1-52 
Wethersfield, Conn. (NED) 1-22 
Weymouth Back River, Mass. (NED) 1-40 
Weymouth-Braintree, Mass. (NED) 1-22 
Weymouth-Fore - Town Rivers, Mass. (NED) 
1-40, 1-53 
Wheeler Creek, Tex. (SWF) 16-22 
Wheeler, General Joe, Lock and Dam, Ala. (ORN) 
23-17 
Wheeling, W. Va. (ORP) 26-22, 26-26 
Wheeling, W. Va. (North Wheeling) (ORP) 26-22, 
26-27 
Wheeling, W. Va. (Wheeling Island) (ORP) 26-22, 
26-27 
White Lake Harbor, Mich. (NCE) 31-25, 31-44, 
31-56 
White Oak Bayou, Tex. (SWG) 15-11 
White Oak Creek, Ohio (ORH) 25-21 
White Oak Dike, Bladen and Pender Counties, N.C. 
(SAW) 6-27 
White Oak River, N.C. (SAW) 6-29 
White River, Ark. (above Peach Orchard Bluf) 
(SWL). 18-16 
White River, Ark. (below Newport) (LMM) 13-5 
White River, Ind. (ORL) 24-19, 24-30 
White River at Highway 14, 1/4 mile east of Oil 
Trough, Ark. (SWL) 18-17 
White River Backwater Levees (MR+T) 42-9 
White River Bank Stabilization, Batesville, Ark. 
(SWL) 18-7, 18-13, 18-25 
White River Basin (Little Rock District), Ark. and 
Mo. (SWL) 18-7, 18-13, 18-15, 18-24 
White River, Jacksonport, Ark. (SWL) 18-8, 18-13 
Whitebird Creek, Idaho (NPW) 38-15, 39-16 
Whitefish Point, Mich. (NCE) 31-61, 31-62 
Whitesburg, Ky. (ORL) 24-30 
Whitewater River, Ind. (ORL) 24-30 
Whitewater River Basin, Calif. (SPL) 33-20 
Whiting, Maine (NED) 1-22 
Whitings Creek, Va. (NAO) 5-24 
Whitlow Ranch Dam, Ariz. (SPL) 33-5, 33-11, 
33-16 
Whitmanville Lake, Mass. (NED) 1-44, 1-51 
Whitney Lake, Tex. (SWF) 16-14, 16-17, 16-21 
Whitney Point Lake, N.Y. (NAB) 4-16, 4-26 
Whitney Point Village, N.Y. (NAB) 4-16, 4-26 
Whittier, Alaska (NPA) 40-15 
Wichita and Valley Center Channel Improvement, 
Kans. (SWT) 19-16, 19-17, 19-18 
Wickford Harbor, R.I. (NED) 1-40 
Wicomico River, Md. (NAB) 4-10, 4-24, 4-31 
Wiedmer Chemical Drainage and Levee District, Mo. 
(LMS) 14-15 
Wilcox, Pa. (ORP) 26-23 
Wild Rice and Marsh Rivers, Minn. (NCS) 27-27 
Wild Rice River, Minn. (NCS) 27-28 
Wild Rice River, Mahnomen Co., Minn. (NCS) 
27-17, 27-21 
Wild Rice River, South Branch and Felton Ditch, 
Minn. 27-24 
Wildcat and San Pablo Creeks, Calif. (SPK) 35-17, 
35-25 
Wilders, Ky. (ORL) 24-24 
Wiley Creek Lake, Oreg. (NPP) 37-44 
Wilkes-Barre, Hanover Township, Pa. (NAB) 4-36, 
4-39 
Willamette Falls Fishladder, Oreg. (NPP) 37-44 
Willamette River above Portland and Yamhill River, 
Oreg. (NPP) 37-39 
Willamette River at Willamette Falls, Oreg. (NPP) 
37-10, 37-26, 37-35, 37-45 
Willamette River Basin, Oreg. (NPP) 37-16, 37-37, 
37-42, 37-49, 37-50 
Willamette River Basin, Oreg.-Bank Protection 
(NPP) 37-17, 37-27, 37-37, 37-50 
Willamette River Basin Channel Clearing and 
Snagging (NPP) 37-42 
Willapa River and Harbor and Naselle River, Wash. 
(NPS) 38-7, 38-16, 38-22 
Willapa River at Raymond, Wash. (NPS) 38-29 
Willard Beach, South Portland, Me. (NED) 1-42 
William H. Harsha Lake, Ohio (ORL) 24-12, 24-17, 
24-27 
William L. Springer Lake, Ill. (NCR) 28-16 
Williamson, W. Va. (ORH) 25-20, 25-22 
Williamsport, Pa. (NAB) 4-36, 4-39 
Williamstown, W. Va. (ORH) 25-21 
Williamsville Reservoir, Vt. (NED) 1-45 
Williston, N.D., Water Intake (MRO) 21-18 
Willoughby Channel, Va. (NAO) 5-24 
Willow Creek Lake, Heppner, Oreg. (NPP) 37-17, 
37-28, 37-37 
Willow Creek Lake, Heppner, Oreg. (NPW) 39-15 
Willow Island Locks and Dam, W. Va. (ORD) 22-3, 
22-7 
Wilmington Harbor, Del. (NAP) 3-8, 3-10, 3-16, 
3-20 
Wilmington Harbor, N.C. (SAW) 6-9, 6-19, 6-29 
Wilmore, Pa. (ORP) 26-22 
Wilson Branch, Cheraw, S.C. (SAN) 7-8 
Wilson Creek, Sumter County, S.C. (SAN) 7-16 
Wilson Harbor, N.Y. (NCB) 32-11, 32-21, 32-33 
Wilson Lake, Kans. (MRK) 20-7, 20-12, 20-16, 
20-19 
Wilson Lock and Dam, Ala. (ORN) 23-17 
Wilson Point Harbor, Conn. (NED) 1-40 
Wilson River, Oreg. (NPD) 37-43 
Wilton, N.H. (NED) 1-22 
Winchester Bay, Oreg. (NPP) 37-39 
Winfield Levee, Kans. (SWT) 19-16 
1-52

INDEX 
Winnibigoshish Reservoir, Minn. (NCS) 27-26 
Winnipesaukee Lake, N.H. (NED) 1-40 
Winona, Minn. (NCS) 27-17, 27-21 
Winona Harbor, Minn. (NCD) 29-7 
Winooski River, Vt. (NAN) 2-36 
Winslow (Tributaries of Little Colorado River), Ariz. 
(SPL) 33-21 
Winsted, Conn. (NED) 1-22, 1-44, 1-49 
Winter Harbor, Maine (NED) 1-40 
Winter Harbor, Va. (NAO) 5-24 
Winthrop Beach, Mass. (NED) 1-42 
Winthrop Harbor, Mass. (NED) 1-40, 1-46 
Wisconsin River, Wis. (NCS) 27-23 
Wishart Point Channel, Va. (NAO) 5-24 
Wister Lake, Okla. (SWL) (SWT) 18-22, 19-6, 
19-12, 19-14, 19-16, 19-18 
Withlacoochee River, Fla. (SAJ) 9-46 
Wolf and Jordan Rivers, Miss. (SAM) 10-42, 10-45 
Wolf-Coffee Lake, Kans. (MRK) 20-17 
Wolf Creek Dam-Lake Cumberland, Ohio River 
Basin, Ky. (ORN) 23-8, 23-10 
Wolf Creek, U.S. Highway 45 Bridge, Prentiss 
County, Miss. (SAM) 10-17, 10-29, 10-40 
Wolf Creek, Highway 362 Bridge, Prentiss County, 
Miss. (SAM) 10-43 
Wolf River (Memphis Harbor), Tenn. (LMM) 13-5 
Wood Island Harbor, Biddleford, Maine (NED) 1-40 
Wood River Drainage and Levee District, Ill. (LMS) 
14-7, 14-10, 14-12 
Woodbridge Creek, N.J. (NAN) 2-35 
Woodbury, Conn. (NED) 1-22 
Woodbury Creek, N.J. (NAP) 3-21 
Woodcock Creek Lake, Pa. (ORP) 26-11, 26-15, 
26-20, 26-27 
Woodland St. Bridge, Tenn. (ORN) 23-4 
Woodlands, W. Va. (ORP) 26-22, 26-27 
Woodmont Shore, Milford, Conn. (NED) 1-42 
Woodruff, Jim, Lock and Dam, Ga. and Fla. (SAM) 
10-23, 10-30, 10-41 
Woods Hole Channel, Mass. (NED) 1-40 
Woodson Drainage District, Oreg. (NPP) 37-41, 
37-42, 37-48 
Woonsocket, R.I. (NED) 1-22, 1-44, 1-48 
Worcester, Mass. (NED) 1-22, 1-48 
Worcester Diversion, Mass. (NED) 1-44 
Worthington, Minn. (NCR) 28-17 
Wrangell Harbor, Alaska (NPA) 40-13, 40-15 
Wrangell Narrows, Alaska (NPA) 40-13, 40-15 
Wright Patman Dam and Lake, Tex. (LMN) (SWF) 
11-17, 16-12, 16-17, 16-21 
Wright's Creek, N.C. (SAW) 6-25 
Wrightsville Beach, N.C. (SAW) 6-27 
Wrightsville Dam, Vt. (NAN) 2-36 
Wynoochee Lake, Wash. (NPS) 38-10, 38-17, 
38-23 
Wynoochee River, Wash. (NPS) 38-29 
Wyoming Valley, Pa. (NAB) 4-19, 4-20, 4-27, 
4-33 
Y 
Yadkin River Basin, N.C. - S.C. (SAW) 6-13, 6-30 
Yakima, Wash. (NPS) 38-29 
Yakima River at Union Gap, Wash. (NPS) 38-13 
Yakima River, Cle Elum, Wash. (NPS) 38-29 
Yakima River, West Richland, Wash. (NPS) (NPW) 
38-29, 39-15, 39-17 
Yakima River, Yakima, Wash. (NPS) 38-29 
Yalobusha River, Miss. (LMR) 12-15 
Yaquina Bay and Harbor, Oreg. (NPP) 37-10, 
37-26, 37-35 
Yaquina Bay and Harbor Small Boat Basin, Oreg. 
(NPP) 37-39 
Yaquina River, Oreg. (NPP) 37-39 
Yatesville Lake, Ky. (ORH) 25-10, 25-15, 25-18 
Yazoo River, Miss. (LMK) 12-3, 12-9, 12-11 
Yazoo River Backwater Area (MR+T) 42-51 
Yazoo River Basin, Miss. (MR+T) 42-7, 42-16, 
42-28, 42-46, 42-51 
Yazoo River Basin Project Levees (MR+T) 42-46, 
42-49 
Yellow Jacket Creek, Hogansville, Ga. (SAM) 10-43 
Yellowstone River, Bank Protection, Billings, Mont. 
(MRO) 21-19 
Yellowstone River, Greycliff Bridge, Mont. (MRO) 
21-19 
Yellowstone River, near Miles City, Mont., Water 
Intake and Sewage Lagoon (MRO) 21-19 
Yellowstone River, Reedpoint Bridge, Mont. (MRO) 
21-19 
Yellowstone River, Springdale Bridge, Mont. (MRO) 
21-19 
Yellowstone River, Voges Bridge, near Big Timber, 
Mont. (MRO) 21-19 
Yellowstone River, W. Glendive, Mont. (MRO) 
21-17, 21-19 
Yellowstone River, Water Plant, Livingston, Mont. 
(MRO) 21-19 
Yellowstone River, Yellowstone Co. Bridge, near 
Billings, Mont. (MRO) 21-19 
Yonkers, N.Y. (NAN) 2-36 
Yonkers, Nepera Park, N.Y. (NAN) 2-39 
York Harbor, Maine (NED) 1-40, 1-53 
York, Indian Rock Dam, Pa. (NAB) 4-19, 4-27, 
4-33 
York River, Va. (NAO) 5-9, 5-16, 5-21 
York Spit Channel, Va. (NAO) 5-2, 5-18 
Youghiogheny River, Pa. and Md. (ORP) 26-21 
Youghiogheny River Lake, Pa. and Md. (ORP) 
26-11, 26-15, 26-20, 26-27 
Youngs and Klaskanine River, Oreg. (NPP) 37-39 
I-53

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1986 
Youngs Bay and Youngs River, Oreg. (NPP) 37-39, 
37-45 
Youngs River Dikes, Oreg. (NPP) 37-41 
Youngstown, Ohio (ORP) 26-22 
Z 
Zacate Creek Channel Improvement, Tex. (SWF) 
16-22 
Zanesville, Ohio (ORH) 25-21 
Zintel Canyon Dam, Wash. (NPW) 39-8 
Zippel Bay, Lake of the Woods County, Minn. (NCS) 
27-3, 27-19 
Zippel Bay Harbor, Minn. (NCS) 27-23 
Zumbro River, Minn. (NCS) 27-24 
I-54 
*U.S. GOVERNMENT PRINTING OFF ICE:1988-520-682:00104

111111111 
1 
?i 
VIIiI i / ' w4 r' " 'j 
-'- 
i ; .: i 
1 ,1..1 : , , __ ,,, ' 
' 
\ 
, 
i 
=',
' . . 
r 
f 
. ;__ 
rt 
i 
; 
,j ' 
4 
1 
.- 
. 
1 
t } 
.ter., 
' 
{{ 
1
1
ti 
-, 
i } 
C
I l 
ii 
i 
l 
3 i, 
. 
, ., 
_, f,,- ' ,

